HomeMy WebLinkAboutSusitna Finance History 1986W�"'Ah
Susitna Hydroelectric Project
FUTILE QUEST FOR A PLAN OF FINANCE
IN ALASKA two contemporary large.
scale engineering projects are noteworthy.
One is the development of North Slope oil
resources, including construction of the
trans -Alaska pipeline. This impressive
achievement is the work of private com-
panies and private capital. A second impor-
tant contemporary megaproject in Alaska
is one planned by a public agency of the
state —the Susitna hydroelectric project.
Planning activity on this project was re-
cently suspended, and the current prospect
for its revival is not good. Despite the un-
happy fate of this project (or perhaps be-
cause of it), the Susitna project is an
interesting case study of public sector
planning for a major infrastructure de-
velopment project.
This article considers only the finan-
cial aspect of the Susitna project. As it
happens, this is the critical dimension,
because the failure to devise a workable
and acceptable financing plan led to the
Project's demise. In this paper I will review
the history of financial planning for the
project from 1982 (date of completion of
the feasibility study) through March of
1986, when the project was put on the
shelf. The objectives of this review are to
explain why a workable plan of finance
was so elusive and, more important, to seek
insights from the history of the Susitna
project that may benefit future planning
for major energy projects.
PROJECT DESCRIPTION
The Susitna hydroelectric project was
to include two dams along the Susitna
Riaar in the Talkeetna Mountains of
soutt"ntral Alaska. When completed, the
by Gordon S. Harrison
project would have a combined installed
capacity of 1620 megawatts and an aver-
age annual energy yield estimated at 6200
gigawatt-hours.
The Watana Dam, intended for oper.
ation in 1996, was to be a rock structure
885 feet high and 4100 feet long, capable
Of generating 1020 megawatts. At this
height, Watana would be the fifth highest
embankment dam in the world, and the
highest in North America, exceeding the
Mica Creek embankment dam in British
Columbia (794 feet) and the Oroville Dam
in California (771 feet). The Watana reser-
voir would extend upstream 48 miles; it
would be 1 to 5 miles wide, and it would
have a maximum depth of 680 feet.
The Devil Canyon Dam, located 32
miles downstream from Watana, was
scheduled to be operating by 2002. It was
to be a double -curved concrete arch 645
feet high and 1500 feet long, capable of
generating 600 megawatts. The dam's
height would include it among the nine
tallest arch dams in the world, including
the Hoover Dam in Arizona (725 feet)
and Inguiri in the Soviet Union (892 feet).
The reservoir for Devil Canyon would be
26 miles long, 'h mile wide at its widest
Point, and have a maximum depth of 550
feet.
ALASKA POWER AUTHORITY
In the United States, major public
sector infrastructure projects are typically
built, owned, and operated by quasi -
independent public corporations. So it is
in Alaska, where the Susitna project is
under the jurisdiction of the Alaska Power
Authority (APA), The APA is a public
corporation governed by a board of direc-
tors appointed by the governor of Alaska.
It has its own professional staff but relies
heavily on consulting firms to provide
engineering and other technical expertise.
APPROACHES TO STATE
SUBSIDIZATION
Large infrastructure projects that are
developed by public corporations usually
rely on the sale of revenue bonds for
financing. Revenue bonds are debt issues
(the interest on which is usually exempt
from state and federal taxation) sold in
the national capital markets that are
secured by income generated by the prof.
ect (road tolls, electricity sales, gate
receipts, and other fees charged to users
of the project).
However, Susitna was such a large,
expensive project that it could not be fi-
nanced exclusively by conventional reve.
nue bonds. Payment of interest and
principal on revenue bonds sold to cover
all project costs would result in an exorbi-
tant price for electricity in the early years
of the project. Therefore, it was always
assumed that the State of Alaska would
need to subsidize the project.'
Two forms of state subsidy for Susitna
were proposed during the course of project
Planning. One was referred to as state
"equity" investment in the project. In this
case, state appropriations would be used
to pay some or all construction costs, and
thereby reduce or eliminate altogether the
requirement for borrowing. The second
form of state subsidy was referred to as
"rate stabilization." In this case, state ap-
propriations would be used to help make
Gordon S. Harrison was associate director of the Alaska Office of Management and Budget, and a director of the Alaska Power
Authority from 1983 to 1986. This paper was prmnted to the conference on Global Infrastructure Projects, Alaska Pacific Univer-
sity, Anchorage, July 8, 1986, sponsored by the Intemational Federation of Institutes of Advanced Study.
22 The Northern Enginew, Vol. 19, No. 2 and 3
payr'nents of principal and interest on
revenue bonds. Thus, state subsidy would
be used to service debt rather than reduce
the overall amount of debt.
State subsidy to the project in the
form of loans was among the financing
mechanisms considered by project plan-
ners, but loan alternatives were never
fully developed and incorporated into
financing plans for Susitna.
The two main financing concepts of
equity and rate stabilization can be illus-
trated graphically. Line AE in Figure 1
represents the real wholesale price of
electricity from a large, hypothetical hy-
droelectric project that is financed entirely
by debt. This line gradually slopes down-
ward to point E because hydro projects
are typically built to accommodate load
growth (resulting in lower unit costs), and
because of the effect of inflation on level
nominal debt service. At point E. the initial
debt is retired and the price of power
thereafter is based on operation and main-
tenance costs.1
Line 80 in Figure 1 represents the pro-
jection of wholesale electricity prices that
would prevail without the hydro project.
In the case of Susitna, this line represents
the wholesale price of power in the Railbelt
from gas- and coal-fired thermal plants.
This projection assumes real price increases
due to rising fossil fuel prices and other
costs of operations.
Line BF in Figure 1 represents the whole-
sale price of electricity from the hydro
project with a combination of revenue
bonds and state equity. In this case, the size
of the state's equity investment reduces
the amount of debt to that level which
Produces an entry price of power from the
hydro project equal to the price of power
from the thermal alternative (point 8). In-
creasingly larger equity investment in the
project would further reduce the price of
hydropower. If the project were entirely
financed by cash grants from the state-
100 percent equity financing —the whole-
sale cost of power would not have a debt
service component, and it would represent
the variable costs of operation and main-
tenance only (this scenario is not shown
in Figure 1).
Figure 2 illustrates how rate stabiliza-
tion works. Here, state contributions to
the project do not reduce the amount of
debt; rather, they reduce the price of
hydropower (line AC) to the level of the
thermal alternative (line BC) until the two
are the same (at point C). Customers will
Pay for electricity along the line BC, with
the state making up the difference through
EQUITY FINANCING
Figure 1. providing its, subsidy in the form of equity, reduces the requirement for debt financkM
In this figure, the shaded arre represents the amount of squity rweded to make the Who— — price
of hydropower equal to the whobeale price of power from the thermal alternative.
RATE STABILIZATION
cast
per kwh Thermal alternative
A D
Rate stabilisat" C Hydra
subsidy
E
B
0 Years
Figure 2, providing state subsidy thrw4h rate sta67litation requires utilities to pay for hydropower
along the proiscted curve of the thermal alternative until the crossover point C is reached. This
financing aPPr«eA is more desirable then the equity approach from the state's point of view.
rate stabilization. At the crossover point C,
hydropower becomes cheaper than the
altemative, and no further subsidy is re-
quired (customers then pay along the line
CE). An underlying assumption of this ap-
proach is that customers will not be willing
to pay more than they would otherwise
PAY for electricity, notwithstanding future
savings that the project will create.
It is evident from the relative size of
the shaded area in these two figures that
less state subsidy is involved with rate
stabilization than with the equity ap-
proach (on the basis of the general assump-
tions underlying these curves). Also, it is
no doubt evident that utility customers
would prefer to pay along the line BF in
Figure 1 than BCE in Figure 2.
REAL AND NOMINAL DOLLARS
Because of the long time involved in
debt repayment, it is necessary to account
for the effects of inflation when analyzing
the cost of any major project. Thus, fi-
The Northern Engineer, Vol. 1e, No. 2 and 3
23
nance Planners and economists distinguish
between real (or constant) dollars, which
exclude inflation, and nominal dollars,
which include the effects of inflation, In
those terms, the cost of the Susitna project
was estimated to be about $5 billion at
prices prevailing in 1985 (real dollars), but
more than $12 billion at the prices pre-
vailing when the expenditures actually
would be made (nominal dollars).
REVIEW OF FINANCE PLANNING
A review of finance planning for the
Susitna project is best approached chrono-
logically, beginning in 1982 when a major
feasibility study was completed.
1982
In 1982 a feasibility study of the proj-
ect was completed and three financing
options proposed. During this time, how-
ever, the long-term oil price outlook was
deteriorating.
Acres American report. In March 1982,
the firm Acres American released a major
feasibility study of the Susitna project.
The firm had been under contract to the
APA since late 1979. The Acres American
report proposed the two -stage construc-
tion schedule described above under
"Project Description." This project con-
figuration and the supporting analysis
became the basis for APA's license appli-
cation to the Federal Energy Regulatory
Commission (FERC).
With regard to financing, the Acres
American report proposed three options:
(1) 100 percent state appropriation of the
total cost of construction, estimated to
be 35.1 billion in 1982 dollars; (2) a state
appropriation of $3 billion 0982 dollars),
with the remaining project cost financed
Table 1. Finance Plans for the Susitna Project
with revenue bonds; or (3) a minimum
state appropriation of $2.3 billion (1982
dollars) with the remaining project cost
financed with revenue bonds. (The Acres
American and other major financing
proposals are summarized in Table 1.) It
is noteworthy that one of the financing
options was a cash grant from the state
for the full cost of the project. At this
time, it was widely presumed that Alaska's
statewide hydroelectric development pro-
gram would be funded entirely by state
grants.
The other two financing options are
variations of the equity approach shown in
Figure 1. An equity contribution of S3 bil-
lion would represent an entry rate for the
project somewhat below point B in the
figure; an equity contribution of $2.3 bil-
lion was calculated to represent an entry
rate at point B (i.e., at a price equal to the
Report'
Constant S
Construction
Total costs (billions)
Nominal $
Construction Financing
Total
Revenue
forecast
Finance options
Constant $ (Sarno year as "Constant S" column)
Acres American
5.1
15.3 0.0
16.3
Battelle
1. 100% state appropriation of total capital cost
Feasibility Study
(Jan. 1982 $)
Report
($5.1 billion). Consistent with S825.
(Mar. 1982)
15.3 1.6
16.9
2. State appropriation of S3 billion with residual bond
financing.
15.3 1.7
17.0
3. Minimum state appropriation of S2.3 billion with
residual bond financing.
FERC License
5.1
15.3 2.0
17.3
Battelle
State appropriation of $1.8 billion with residual
Application
(Jan. 1982 $1
Report
bond financing,
(Feb. 1983)
Kentco Report
5.1
13.4 3.4
16.8
00R mean
State appropriation of $800 million In equity and
for the Anchorage
(1983 S)
Sept. 1983
$778 million in rate stabilization. Remaining
Chamber of Commerce
financing requirements met by combination of R EA
(Jan. 1984)
guaranteed loan and municipal bonds.
APA Economic
5.4
11.8 5.2
17.0
DOR mean
1. State appropriation of $1.5 billion in equity and
and Financial
(Jan. 1983 S)
Dec. 1983
$400 million in rate stabilization funds (RSF).
Update (Feb. 1984)
11 .8 4.4
16.2
2- State appropriation of $1.7 billion in equity and
S350 million in RSF, plus an REA•guaranteed loan
of $1.5 billion, with residual bond financing,
Draft FERC
5.4
12.7 7.8
20.5
DOR mean
State appropriation of $220 million for rate s»bil-
License
(Jan. 1985 $)
June 1985
ization, with revenue bonding of full project cost.
Amendment
(Nov. 1985)
APA Draft Plan 5.4 12.7 7.8 20.5 Not stated State to provide $520 million for rate stabilization by
of Finance (Jan. 1985 S) appropriation or pledging earnings from the Parma -
(Jan. 20, 1986) nent Fund. $2 billion (nominal $) of project revenue
bonds to be secured by Railbelt utilities. Residual
bond financing issued by state and secured by
Permanent Fund earnings.
IAll reports are available at the Alaska Power Authority, Anchorage.
2Alaska economic projections for estimating slactricity requirements for the Railbeft, Vol. 9, by S. Goldsmith and E. Porter, ISER, University
of Alaska -Anchorage, Sept. 1982 report, Birmile Pacific Northwest Laboratories.
24
The Northern Engineer, Vol. 18, No. 2 and 3
Price,of electricity from natural gas gener-
ation at the time the project would begin
operation).
Chanyiny revenue outlook. Worldwide
crude oil prices had escalated dramatical.
ly in the aftermath of the Iranian crisis of
1979. In February 1981, the contract
Price for Alaska North Slope crude on the
Gulf Coast had peaked at 536.90 per bar-
rel, with experts predicting that prices
would steadily increase into the distant
future. Long-term revenue forecasts pre-
pared in mid-1981, consequently, indicated
that the State of Alaska would be phe-
nomenally wealthy. The Acres American
feasibility study referenced the long-term
revenue forecast published by Battelle
Pacific Northwest Laboratories as part of
a major study of alternatives to the Su.
sitna project. Table 2 and Figure 3 show
this revenue forecast. Clearly, cash financ-
ing of Susitna was a plausible option in
1981.
In mid-1982, however, a dramatic de-
cline occurred in the long-term revenue
forecast, as indicated in Table 2 and Figure
3. Full cash financing for the Susitna proj.
ect was no longer an obvious possibility,
but some form of state subsidy remained
clearly plausible.
Because of the revised revenue outlook
between 1981 and 1982, some disquieting
commentary on the viability of the proj.
ect began to appear. A report by Tuning
and Erickson in September 1982, for
example, argued that the oil prices of
1980 and 1981 were artificially high and
could not continue to be tolerated in the
marketplace; that lower oil prices nulli-
fied most of the economic assumptions
used to justify the Su3ltna project; and
that, by implication, the state would not
be able to provide the cash grants rt"s-
sary to finance the project.'
1983
In 1983 an application for a federal
license for the Susitna project was filed;
it proposed two financing options. In spite
of this, however, the APA initiated new
financial and economic analyses for the
project because of continuing declines in
oil prices.
FERC application. On 28 February 1983,
an application was filed with FERC for a
federal license to construct and operate
the Susitna project. With regard to finan-
Table 2. State of Alaska General Fund Revenue Forecasts, 1981 to 1986.
(In $ millions, nominal.)
19811912
1913
YEAR
MARCH
TUNE
SEPT.
DEC.
MARCH
TUNE
SE".
DEC.
1913
a0al
3497
3575
1367
ZM6
2981
3430
3514
3435
1916
9273
3979
4259
4261
3523
3198
3564
3892
36"
19V
10649
450
JIM
4a17
3769
3393
MW
4240
4172
196t
12179
4709
5147
4%1
4181
3540
3753
4106
4220
1999
13991
5242
3732
3379
4384
3554
3816
4442
48611
1990
15074
5141
Sul
5096
4324
36M
410e
4606
5100
1991
16688
4717
4992
450
4063
3374
3994
4290
4911
1992
17932
4696
4966
4441
39U
3298
39t3
4157
4963
1993
19395
4611
4679
4235
3971
3250
4103
4103
49%
1994
20326
AIM
4652
4163
3990
3232
4173
40"
305E
1995
20666
4268
4391
3892
3304
3092
3977
3927
4632
19%
2081E
4033
4020
3609
3644
2930
3t54
3612
4715
1997
20797
4246
4236
3786
3919
300E
4039
3741
4983
19"
20320
4296
4Z76
3837
349
300
4129
3737
5110
1984
tltS
0116
YEAR
MARCH
JUNE
SEPr.
DEC.
MARCH
JUKE
SEPr.
DEC.
MARCH
1915
3521
3340
345E
3343
3Xn
3253
3266
3290
3260
1986
rM
3475
3s"
34M
3037
2"
2954
3213
2721
1937
40C
3921
395a
Um
3001
2177
26M
2925
2077
199t
4194
3957
4065
3241
2764
2470
22A3
2474
1614
19t9
4649
4149
4360
3290
2694
2403
2106
2397
1454
1990
49"
4175
4C25
3295
2652
2324
204E
2310
1419
1991
4466
4237
4414
3204
2582
2259
1926
2299
1312
1992
4394
4431
4361
3212
2515
2308
1950
2277
1232
1993
4521
4579
46M
3263
2647
2337
1958
2727
1155
1994
4535
4592
4490
3162
2551
22-M
1sw
2321
10%
1995
4510
4535
4479
311E
2A45
2160
last
2W
1045
19%
4516
4401
44M
3077
7313
2063
1753
22SS
997
1997
4527
4248
4353
29"
22tZ
20W
1750
2307
1083
199E
4326
4123
43V
MI
2257
1998
1750
2307
1061
None The 19t
1 funcaet wall P 4 by
er bmdaee o(Saod
and Eomo.Lk Rrreek
Uoiwsiy o(Alaeke
for aalwa So want LAa wxWs; delved ha n fotedat of paelaiMI0 Twain to ted
MY "my k KMW& by
ee Alaska Deprtmw of
Rneaee. Jar 19e1.
TV 19a2-196616eeraw won prrpe4d by
AJata OAke o(Mru pemw4 aed 1Sad,ey dn'vsd sue faecae of p4eakM wvQroe
ea are MrLky
ax om ade by &a M da Depenaaa of R4.�L Tb= hmme tepe�eat the 306 peorrik
mobsUity ftwumn
(dwe a r spd dlara dl *A aooul rdr wig he cent or ku d= de (n era d vabeL
The Northern Engineer. Vol. 18. No. 2 and 3 25
Millions of Dollars
$12000
$10000
$8000
$6000
$4000
$2000
STATE OF ALASKA
GENERAL FUND REVENUE FORECAST
1981-1986
1981 (Battelle Report)
March 1982
Much 1984 '
March 1983
March 1985
March 1986 "
$0
1985 1986 1987 1988 1989 1990 1991 1992 1993 1994 1995 1996 1997 1998
Fiscal Year Sewce Meeks Deowinnn• of Rtwnw and Offlca of k4napamanr and Budget
Figure 3. State of Alaska General Fund revenue forecast, 1981.1986.
cing, the license application stated that
"costs for Watana through 1989 would be
financed by $1.8 billion (1982 dollars) of
state appropriations. Thereafter comple-
tion of Watana is expected to be accom-
plished by issuance of approximately $2.4
billion (1982 dollars) of revenue bonds."
It also stated that the Devil Canyon phase
would be financed entirely by revenue
bonds. No doubt in response to revised
revenue forecasts, the APA had dropped
the full cash financing option, and recal-
culated the minimum state cash contribu-
tion to be $1.8 billion, or $500 million
less than the minimum contribution of
$2.3 billion identified earlier in the Acres
American report.
Concern about the future price of crude
oil —the keystone of the project's economic
and financial feasibility assessments —was
thereupon expressed by FERC's staff -
Noting several deficiencies in the state's
application, FERC called for the APA to
incorporate updated oil price forecasts in
its economic and financial feasibility
sttsdies. In response to this and to other
critiques of the existing analysis, as well
as to the changing oil price outlook gen-
erally, the APA contracted with the firm
Sherman H. Clark and Associates (SHCA)
to provide updated forecasts- In the mean-
time, a joint venture of two major engi-
neering and construction firms, Harza
Engineering and Ebasco Services (Harza-
Ebasco), had been hired by the APA to
provide engineering, design, and technical
assistance in the FERC licensing process.
Harza-Ebasco now initiated a review of
the economic and financial studies for
Susitna.
1964
During 1984 the financial dimension
of the Susitna project began to receive
serious attention from the APA, the legis-
lature, and others. At mid -year, the long-
term revenue outlook was robust enough
to support an optimistic view that the
project could be financed with the help
of sizeable state grants. By the end of the
year, however, it had become apparent
to APA financial planners that a new
approach was needed.
1964 Up -data. In February 19M the APA
released the draft report Susitna Hydro-
e/ectrk Project Economic and Firm wad
Up -date. Much of this report was the work
of Harza-Ebasco; It incorporated the oil
Price forecasts of Sherman H. Clark and
Associates. The report validated the eco-
nomic feasibility of the project, but con-
tained a lengthy discussion of the major
unresolved financing issues facing the proj-
ect. This report also introduced the subsidy
mechanism of "rate stabilization."
Several financing options were reviewed
by the authors of the report, but two were
advanced as the most feasible: (1) state
appropriations of $1.5 billion for equity
in the project, and $400 million for rate
stabilization, with the remaining costs
financed by revenue bonds; or, (2) state
appropriations of $1.7 billion for equity
and S350 million for rate stabilization,
plus a $1.5 billion loan guaranteed by the
U.S. Rural Electrification Administration
(REA), with the remaining costs financed
by tax-exempt revenue bonds (all figures
in 1984 dollars).
Thus, under these financing proposals,
the state would not only pay a substantial
Portion of the project's construction costs;
but would also create and finance a rate
stabilization fund. This fund (as explained
under "Approaches to State Subsidiza-
tion") would then be used to offset
enough debt service on the outstanding
bonds to keep the project's wholesale
cost of power equal to the cost of the
best thermal alternative until suoh time as
26 The Northern Enelrwer, Vol. 18, No, 2 and 3
the cost of alternative power for the prof.
ect surpassed the cost of hydropower (i.e.,
until the "crossover point" was reached).
What characterizes the 1984 APA Up-
date is its somber assessment of the many
conditions that would have to be met,
and the public policy decisions and com-
mitments that would have to be made, to
finance the Susitna project successfully
using multi -billion -dollar debt issues.
Among these were the necessity for: (1)
recognizing Susitna as one of the state's
highest capital funding priorities; (2) pro-
viQing adequate security for the very high
volume of debt, which might require a con-
stitutionally dedicated stream of revenue
from the state's petroleum resources; (3)
obtaining tax-exempt status for Susitna
bonds; and (4) immediately providing for
sizeable state appropriations to the Susit-
na fund, as well as for the retention in the
fund (by annual appropriation, if neces-
sary) of the interest earned on that
money.
Kentco raport. Also early in 1984, a re-
port on the Susitna project was issued by
the consulting firm of William Kent and
Company (Kentco), which was working
under a contract with the Anchorage
Chamber of Commerce. This report, too,
recommended a combination of state
equity, a rate stabilization fund, and re-
sidual revenue bond financing. The pro•
posal, however, called for a larger rate
stabilization fund ($778 million) and less
equity ($800 million) than the 1984 Up-
date. (These amounts are 1983 dollars.)
The report further called for a majority
of the debt to be guaranteed by REA,
with the remainder to be tax-exempt
municipal debt.
The Kentco report was optimistic in
its treatment of the financing issue.' Ad-
dressing the Anchorage Chamber of Com-
merce, consultant William Kent stressed
that his finance plan "allowed a minimum
need for state investment, spread the
need for state appropriation over a larger
number of years, and did not present a
tax exemption problem." The plan, he
said, "suggests a need to start appropri-
ating from 178 to 226 million dollars
annually starting with this legislative
session."
legislative action. During the 1984 legi-
slativo session (January to June), two
measures were enacted that dealt with
Susitna financing: (1) the legislature ap-
proved the Watana project at a cost of
$3.75 billion in 1983 dollars; and (2) the
legislature made a continuing appropria.
Revenue outlook. Was it reasonable to ex-
pect that S316 million a year (plus interest
earnings of the fund) would be forthcom-
ing from the legislature for six successive
years to finance Susitna? In mid-1984, a
plausible argument indeed could be made
that the money was available, if the legi-
slature had the will to see the project
through. Note that the revenue projections
shown in Table 2 and Figure 3 for 1984
are significantly higher than those made
the previous year. If one were to project
that the state's operating budget would
grow at the rate of inflation (approximate-
ly 5 percent) from a base of approximate.
ly $2.2 billion in FY1984, then the 1984
revenue forecasts suggest that the State
would have over $1 billion a year during
FY 1986.1991 to allocate for the capital
projects and loan programs. Under these
fiscal circumstances, appropriations of
$316 million per year to a fund retaining
its own investment earnings certainly was
not, on the face of it at least, impossible.
By the end of 1984, however, revenue
forecasts had fallen to their 1983 levels.'
Also, additional oil price reductions
seemed probable, due to a steady erosion
of OPEC's influence over oil prices.
There were other reasons, as well, to
believe that the expectation of massive
and continuing state appropriations for
Susitna was unrealistic. Notably, the 19M
Legislature had appropriated only $100
million for Susitna for FY 1985, while
total capital appropriations that session
tion for "equity investment in and rate
stabilization for the Susitna project" in
the amounts of $100 million for fiscal
year 1985 and $200 million for each of
the six succeeding fiscal years.°
While the Watana construction cost
figure of S3.75 billion was traceable to
the Harza-Ebasco Up -dare, the origin of
the $1.3 billion (nominal dollars) total set
aside by the continuing appropriation was
a mystery. Many people assumed that it
was based on the Kentco report and Wil.
liam Kent's Chamber of Commerce speech.
In any case, it bore no resemblance to the
finance plans proposed in the Up -date or
those being discussed by the APA staff
and board.
Meanwhile, APA staff continued to
maintain that some $2 billion (constant
dollars) was needed from the state to help At its meeting of January 23, 1985, the
finance the project. Thus, instead of the board of directors of the APA adopted a
$200 million per year for FY1986.1991 staff recommendation for a Susitna plan
appropriated by the legislature, $578 mil- of finance that called for state appropria-
lion per year would be required —or at tions o4 $1.94 billion over the fiscal years
least S316 million per year if interest 1985.1995 to a fund that would retain its
could accumulate in the Susitna fund.° interest earnings. This money would be
used for both equity and rate stabilization.
Minutes of the meeting show that the
board considered this option the best pre-
sented to date, and directed the staff to
continue refining it.
By this time, however, it was increas-
ingly apparent to many people that if the
project were to go forward, it would
have to do so under a financing scheme
that did not require such largd state cash
contributions. Among those recognizing
this were high-level individuals in the par-
ent companies of the Harza-Ebasco joint
venture, who in January 1985 held infor-
mal meetings with the Governor, APA
executive staff, and board members to
discuss a proposal for staging the con-
struction of the Watana dam. Under this
approach, Watana would be constructed
in two phases (the first and the third
Phase), the Devil Canyon dam would be
the second, middle phase of the project.
The virtue of developing the project in
three phases instead of two was primarily
financial. Three phases of construction
would match more closely than two
phases the growth of electricity demand
in the Railbelt. As a consequence, there
would be less unused capacity in the Wa-
tana dam in the early years of project
operation, and therefore a greater ability
of utility customers to carry the burden
of revenue bond financing. Thus, accord-
ing to the staging proposal, all three
Phases would be financed entirely by
revenue bonds, with a comparatively
modest state cash contribution remain -
exceeded $1.2 billion, comprising the
largest unrestricted general fund capital
budget in the state's history. This was
hardly a good indication of legislative will
to sacrifice other capital projects in order
to pay for Susitna.
19185
During 1985 the APA and its consul.
tants redesigned the Susitna project in an
effort to facilitate its financing. Toward
the end of the year a team of financial
experts initiated work on a definitive plan
of finance based on the reconfigured proj-
ect.
Staging Proposal
The Northern Engineer, Vol. 18, No. 2 and 3 27
ing necessary for rate stabilization only
in the early years.
In February the Board received a
Public presentation of the conceptual
proposal and authorized Harza-Ebasco to
develop it further in an expeditious man-
ner. At its meeting of May 3, 1985, the
Board approved the staged approach, and
directed the APA staff to begin preparing
an amendment to the FERC license appli-
cation that incorporated the reconfigured
project.
By October, APA staff and consultants
had prepared a comprehensive analysis of
the economic and financial aspects of the
new three-phase project. On the basis of
assumptions about the cost of generating
power from natural gas and coal (the next
best altematives to Susitna, the APA
staff calculated that a rate stabilization
fund adequate to keep the wholesale cost
of Susitna power equal to its thermal
competitor would require as little as
$253 million (1985 dollars). During the
1985 legislative session the continuing
appropriation to Susitna of $200 million
had been made, so there was already
enough money in the bank to finance
the project under this scheme (provided
the interest on this money was allowed
to accumulate in, or was annually appro-
priated to, the fund).
When the APA released its draft License
Application Amendment in November, the
estimate of state contributions to a rate
stabilization fund had decreased further to
$220 million (1985 dollars). The primary
reason for these low estimates of rate sta-
bilization was the assumption that without
Susitna large-scale coal plants would be
required in the 1990s to meet Railbelt
energy demand, causing substantial rate
increases.
Preparation of a financial plan. By late
1985 it was increasingly evident that the
question of financing was critical for the
Susitna project. In particular, financial
advisers to the APA were concerned about
the real -world problems of selling so much
debt for a single project in the national
market. These were the same individuals
who had contributed the lengthy discus-
sion of these problems to the 1984 Up-
date. The task of marketing Susitna
bonds was much more problematic now
VW the state equity contribution had
been eliminated altogether.
Pressure also was coming from the i
legislature for the APA to produce a cred
ible plan of finance for Susitna. Finally,
critics of the project, such as representa
tives of public interest advocacy groups
and the environmental lobby, were openly
asserting that the project was not finan-
cially viable. They claimed_ that the bond
market would not absorb so much debt
for a single massive project inTenied-for a
__ .
comQaralively_smtll market areaihat was
isolated from the.��yer_al: of_the c_onti.
nental United States.
Late in 1985, APA's executive director
assembled a team of financial advisers (in-
cluding several bond underwriters, bond
lawyers, and others) to begin preparing a
definitive plan of finance for the project.
1986
The team of financial advisers charged
with preparing a workable financing plan
for the Susitna project presented a draft
Dian of finance to the board of directors
Dn January 23, 1986. The revelationscon. _
:arced in this-documentledsiirecttyto-the
-
' :.. the finance team
concluded that only a
commitment of the
earnings of the
Alaska Permanent
Fund would suffice to
secure the state's
special revenue
bonds."
ermina_tion of the project two months
ater.
Plan of finance. The draft finance plan
presented to the Board in January was
built on the premise that very little state
cash would be available, and that all proj-
ect costs would therefore have to be
covered through the sale of revenue bonds.
Summed over time, these bonds would
total more than $20 billion (nominal).
The key question was whether the
utilities and the state could successfully
carry that much debt.
To assess the debt capacity of the util-
ities, the finance team calculated the max-
imum annual revenue that the utilities
could generate for debt service, using as
a basis the assumption that the utilities'
customers could tolerate a maximum rate
ncrease of 3 percent (real) per year. Then,
using a 25 percent estimate for the maxi-
mum tolerable one-time rate hike that the
Railbelt ratepayers could withstand in the
event the project never operated, the
finance team estimated the maximum
security that the Railbelt utilities could
Offer bondholders against the risk of the
project's never being completed.
the results of this analysis indicated
that the upper limit of indebtedness for
the utilities for the project was $2 billion
(nominal). Thus, the State of Alaska
would have to Issue special revenue bonds
to cover the remaining project costs. The
State of Alaska, however, could not ade-
quately secure that amount of bonds, even
with the pledge of its general obligation
debt capacity. After reviewing all plausible
alternative sources of security, conse-
quently, the finance team concluded that
only a commitment of the earnings of the
Alaska Permanent Fund would suffice to
secure the state's special revenue bonds.
The financial team also concluded that,
beyond issuing special revenue bonds and
pledging the income from the Permanent
Fund as security, the State of Alaska
would also have to provide a rate stabiliza-
tion fund of S520 million (1985 dollars;
or $2.3 billion in nominal dollars) and an
additional S323 million 0985 dollars) pre -
construction licensing and development
costs. The reason the rate stabilization
requirement was higher than the APA
estimate published in the draft FERC
license amendment ($220 million, 1985
dollars) is that the draft finance plan sta-
bilized rates to the level of a 3 percent
(real) annual increase in retail electric
rates, rather than to the somewhat higher
level of electric rates estimated by the
APA to result from the best thermal
alternative.
At its meeting of January 23, the APA
board requested its executive director to
submit the draft Susitna plan of finance
to rigorous scrutiny by a major munici.
Pal bond underwriting firm, to test the
validity of the finance team's findings.
Under contract to APA, the firm of Pru.
dential-Bache Securities then reviewed
the analysis and conclusions of the plan,
and concurred with them in a report dated
March 21, 1986. Three days later, at its
meeting of March 24, the APA board voted
to withdraw the Susitna license applica.
tion.
REFLECTIONS ON THE CIUEST
FOR FINANCE: PROBLEMS
WITH RATE STABILIZATION
Even if a politically acceptable means
of securing the state's Susitna revenue
bonds had been found, it is doubtful that
negotiations between the APA and the
Railbelt utilities would have been consum-
28 The Northern Engineer, Vol. 18, No. 2 and 3
'mated under the finance plan advocated
by the APA—that is, with rate stabiliza-
tion providing the only vehicle ofstate
subsidy.
At the time the Susitna project col.
lapsed, negotiations between the Railbelt
utilities and the APA for conditional
power sales contracts had been under way
for some time, but they, were still in very
Preliminary stages. The underlying prob-
lems of developing a contract that incor-
porated a rate stabilization fund were
therefore never fully identified nor con-
fTtx ted by the negotiators.
Neither of the existing contracts be.
tween APA and purchasers of power from
its projects (the four -dam pool and Bradley
Lake) incorporate rate stabilization. There-
fore the following analysis of the rate sta.
bilization approach is speculative insofar
as the concept has yet to be implemented.
Nonetheless, in the course of financial
planning for the Susitna project, several
seriously complicating features of rate
stabilization emerged.
Problems with Rare Stabilization
There are two reasons for doubting
that power sales contracts placing signifi-
cant reliance on a rate stabilization fund
could have been successfully negotiated
between the APA and Railbelt utilities,
The first has to do with the pervasive pub.
f ` lic opinion in the Railbelt region that the
Susitna project was going to bring immed-
iate rate relief, or at least stabilize electric
energy prices at their then -current level.
The second is that probably neither the
utilities nor the state would have been
willing to expose themselves to the risks
that rate stabilization entails.
to be caused by the expiration of existing
favorable contracts which made Cook
Inlet natural gas some of the cheapest
fuel in the country.
By the time rate stabilization entered
the financial picture in 1984, however,
Susitna could promise favorable rates to
consumers only in the long run. With rate
stabilization, utility customers would
have to pay along the price curve of the
thermal alternative until a point some-
where in the distant future (10 or more
years after the project was operating). That
Price curve, consequently, would expose
utility customers to the very same near.
term rate shocks from rising fuel costs
that Susitna was presumed to avoid.
As this realization permeated the utili-
ties' governing boards, the municipal gov-
ernments, and the public generally, it is
reasonable to expect that negotiations
over Susitna power sales agreements would
"Thus, a definite risk
existed that the
Railbelt utilities
might have to pay a
substantial premium
for Susitna power.
Further, the potential
magnitude of this
premium was very
great ...."
the APA after 1985—i.e., subsidy to be
used exclusively for rate stabilization —so
accentuated the risk of falling alternative
energy prices that neither the utilities nor
the state would have been willing to as.
sume it.
The risk of cost overruns on any major
engineering project is always present, and
has many potential sources. In the case of
Susitna, the probability of significant cost
overruns was not especially high when
compared to major projects using new
and complex technology and subject to
strict governmental regulation (as in the
case of nuclear power plants, for example).
Nonetheless, it is unlikely that the utilities
would have accepted any of this risk in
Power sales agreements with the APA.
A risk that was more difficult to ana-
lyze and to deal with in the Susitna case
surrounds the behavior of alternative en.
ergy prices. Here is where the risk -related
problems inherent in rate stabilization
financing became apparent. A rate stabili.
zation fund of a fixed amount for Susitna
would guarantee a floor on wholesale elec-
tricity prices, based on a projection of
Prices from the thermal alternative. If al-
ternative energy prices were to fall be-
low this projected floor, access to them
would be blocked by a Susitna power
sales agreement. Thus, a definite risk
existed that the Railbelt utilities might
have to pay a substantial premium for
Susitna power. Further, the potential
magnitude of this premium was very
great, as revealed in an analysis prepared
by the APA in October 1985.
The APA's 1985 risk analysis for Susit-
have become very protracted and compli- na investigated the sensitivity of the re-
cated indeed quirement for rate stabilization to certain
Allocation of risk. Among the risks associ•
fossil fuel price assumptions.1* It showed,
Public expectations. Financing for APA's
ated with any major energy project, two
in particular, that the present value of the
other major hydroelectric projects, the
projects of the so caller"f"TAAm
are crucial: (1) the risk that the project
cost of a rate stabilization fund was only
$253 million using a "base case" set of as -
-four
_--
pool" and &radl__.ey Lake, relies on ;trite-
will cost substantially more to build than
-. assumed in feasibility studies; and (2) the
sumptions about (a) long-term crude oil
su`bsRf in the form of equity. In both
--- --
risk that the price of competing energy
price trends, (b) the future availability of
-----
._._..S,ases, state cash appropriations to the
sources will not perform as expected (i.e.,
�k Inlet natural gas for electrical gener-
protects cover approxrrrrately ha7taf the
cost of construction, with the remaindee
will fail to increase, or not increase as rap-
ation, and (c) the method by which Cook
Inlet gas prices would be set in the future.
of project costs covered by borrowing.
idly as thought).' ither eventuality will
leave the project an overpnced pricer
When those "base case" assumptions were
This financing assures customers-_af-_a
�'"- �`—
m the market, at least in the near term,
relaxed, however, the present value of the
wholesale cost of power that is comparable
Somehow, then, these risks must be
cost of the rate stabilization fund soared.
at the outset to the cost of power from
borne by the developer of an energy prof-
Under conservative but very reasonable
thermal plants.
act or the purchasers of the power, or al-
assumptions, for example, the analysis
Aailbelt residents had come to expect
located between them.
showed that a fund of between $1 billion
the same of the Susitna project. The proj-
In the case of Susitna, contract negotia-
and $2 billion in 1985 dollars would be
necessary to stabilize Susitna's rates at
ect, after all, had long been touted as the
tions between the APA and Railbelt utili-
the level of the thermal alternative (nat-
most economical source of Rail belt power
ties never progressed to the issue of the
ural gas). The difference between the
available, and the best defense against
allocation of these risks. Nevertheless, the
"base case" estimate of $253 million and
sudden and dramatic rate increases likely
approach to project financing adopted by
this estimate, consequently, represented
The Northern Engineer, Vol. 18, No. 2 and 3 29
Figure 4. Rink of cost
overrun Is the seme under
either form of subsidy,
but the rlsk of fond fuel
prices being knver then
expected is Ice with
equity then with nets
stabilization. Figure 5.
RISKS OF EQUITY FINANCING
Coat
per kwh — Therms! alternative
✓�D
/ — Thermal alternative
Risk of cost overrun ' with price drop
A
B 7<;
Hydro cost with overrun
Risk of
Price drop Hydro coat
E
0 years
the magnitude of the total rate premium
that Susitne customers might have to pay
if those conservative but reasonable as-
sumptions proved true.
l Exposure to the risk of declining al-
ternative (fossil) fuel prices is sianif_� icantly .
less under the equity financing aowoach
S
n the rate stabilization approach. This
is because the gap between the cost of
power from the hydro project and the cost
of power from the thermal alternative will
close sooner under equity financing. The
differences between rate stabilization and
equity in this respect are best explained
graphically. Figures 4 and 5 illustrate that
the risk of cost overruns are identical un-
der both financing approaches, but that
the risk of declining fossil fuel prices is
greater under rate stabilization. The cross-
over point C in Figure 4 occurs much
sooner than the crossover point C in Fig-
ure 5, thereby reducing the length of time
consumers would have to pay a premium
for hydropower in the early years, if an
unexpected decline in fossil fuels should
occur.
F.as the consumers' perspective, a
sizeable equity contribution is the pre-
ferred method of providing state subsidy
to an energy project such as Susitna, be.
cause it minimizes risk and offers the pros-
pect of rates lower than those that would
otherwise prevail. From the state's per-
spective, on the other hand, rate stabiliza-
tion is the preferred approach because it
minimizes the state subsidy. The experi-
ence of the APA with the Susitna project
suggests that to the extent it is relied
upon exclusively, rate stabilization may
simply not be viable, particularly when
used for a sizeable project and particularly
in a period of unstable fossil fuel prices,
When state subsidy in the form of cash
grants is made to a project, the money
should be used to reduce the overall level
of debt for the project, rather than reduce
the debt service burden in the early years
of operation with the aim of keeping
wholesale electricity costs -comparable to
a long-term projection of the avoided costs
from alternative generation sources.
SUMMARY
In the course of planning for the Susit-
na project, dune sources of financingwere
proposed: (1) state appropriations to
cover some portion of construction costs
(equity); (2) state appropriations to cover
some portion of the debt service on reve-
nue bonds during the early years of proj-
ect operation (rate stabilization); and (3)
revenue bonds.
Planning for the Susitna project began
with the assumption that cash appropria-
tions from the state's general fund would
cover all project costs—i.e., a 100 percent
equity approach. Later, it was proposed
that a mix of state equity and revenue
bonds be used to finance the project. Fol-
lowing that, the concept of a rate stabili-
zation fund was added to the combination
of equity and revenue bonds (because rate
stabilization tended to reduce the amount
of required state equity). Finally, the
equity component was eliminated alto-
gether, and it was decided that financing
for the Susitna project would be accomp-
lished entirely by revenue bonds and a rate
stabilization fund.
This evolution of Susitna's financial
planning was driven by the eroding out-
look for state revenues and by uncertain
evidence of legislative resolve regarding
financial commitment to the project.
From the beginning, it was recognized that
Susitna would require a substantial subsidy
from the state. V t mateiyj an -acceptable
plan of finance for the project eluded the
APA because the state dTa not have enou fit
money to provide the subsidy the pry
neeted,The end came beciuse of the prob-
lem of providing adequate security for
the large volume of revenue bonds celled
for by the finance plan, and this problem
stemmed from the state's inability to pro-
vide equity investment in the project
sufficient to reduce borrowing require-
ments to levels that could be secured by
the utilities through conventional power
sales contracts.
30 The Northern Engineer, Voi. 18, No. 2 and 3
RISKS OF RATE STABILIZATION FINANCING
Cost
per kwh
Even if a politically acceptable means
had been devised to secure the Susitna
project revenue bonds, it is unlikely that
a workable contract could have been suc.
cessfully negotiated between the Railbeit
utilities and the APA that relied heavily
on a rate stabilization fund of a fixed
amount. There are two reasons for this
evaluation of the situation: (1) utility
customers in the Railbelt expected the
Susitna project to protect them from re-
tail electricity rate hikes, when in fact the
rate stabilization approach assured them
of rate hikes and would not result in sav-
ings to customers for many years, and (2)
the concept of rate stabilization entailed
risks that neither the state nor the utilities
would be willing to assume. From the
point of view of Public policy considera-
tions, rate stabilization might be the pre-
ferred approach to providing state subsidy
to large energy projects because it mini.
mizes state contribution. However, the
experience of the Susitna project suggests
that it is not practical. §4te subsidy for
future hydroelectric projects (to the ex-
tent it is necessary and avaiiabie) should
taste Ote form of equity; i.e., it should re-
duce the need for borrowing.
NOTES
'State subsidy was regarded by many people ss
desirable from a public policy peralow ive,
because It provides a means of distributing
— Thermal alternative
Thermal altemattee
/ with price drop
— Hydro coat with onmsa
— Hydro cost
E
Years
the state's oil wealth to citizens. Other as -
pacts of the issue of subsidy for the project
are discussed in Gordon S. Harrison, "Science,
Susitna arch political decision making." The
Nord wrr Engineer, 1984, Vol. 16, No. 3.
= In the real world, a project would never be
without debt, because major renewals and
nplacafrNntr of the turbine, generator, and
switchyard equipment would have to be fi.
named through the issueiof new debt.
3Arlon R. Tussing and Gregg K. Erickson,
"Alaska Energy Planning Studies," policy
Analysis Paper No. 82-13, a review of three
consultant studies submitted to Alaska state
agencies In fecal year 1982, November 18,
1982. See also, Richard Emerman, "The
Probable Effect of Lower State Ravenus
Foret:ats on the Projection of Electricity
Demand in the Railbelt," policy and analy-
sis paper 82-10, Division of Policy and
Development and Planning, Office of the
Gavemor. September 21, 1982. See tests.
mony of Gregg Erickson on SS 25, SS 26,
and SB 244 before House Finance Commit.
tee on K%V 18, 1981 (minutes, p. 1325).
'The Kentco plan of finance was not realistic,
however, because of cutbacks in federal
funds for REA. In any case, the Susitne
Project would not have received favorable
consideration by that agency because most
Of the power from the project would be sold
to "urban cooperatives," which are accorded
a low prl)(hy in the distribution of REA
funds. Sao "Transcript of Questions and An.
swer Session~ following address by u.S.
Senator Ted Stevens to the Thirteenth Alaska
State Laoblature, February 1984.
"The continuing appropriation was declared
unconstitutional on August 30, 1985, by
the Alaska Superior Court.
Figure 5. Rick of fossil
fuel pricy being lower
than expected is greater
under the rate
stabilization subsidy
It takes larger to reach
the Crossover pant
than with the equity
approach, F Igure 4.
"See minutes of APA board meeting of Noyem.
ber 9, 1984.
7It should be noted that the 30th percentile,
risk-adjurted forecasts developed by the De-
partment of Revenue ware even lower, sig-
nificantly, than the mean probability fore.
cast shown in Table 2. The 30th percentile
forecast reflects a 70 percent probability
that the estimate will be exceeded, and is
used by the executive and legislative bran-
ches for budgeting purposes.
I In the can of the four -dam pool, the debt
component is a state -funded long-term sub-
sidized loon. In the came of Bradley Lake,
which has just begun construction, the debt
component will be project revenue bonds is-
sued by the APA and secured by contract/
with the utilities purchasing power from the
project.
"A third major risk is that the forecast demand
for the output of the project will not mate-
rialize. This was a major risk of the Susitna
project, but one that was not taken seriously
by Railbelt utility managers, who constantly
chided the APA for its conservative estimates
of load growth. Thus, it seems unlikely that
allocation of this risk would have impeded
contract negotiations with APA.
10The results of the analysis, in table format,
were included in a package of material pre.
pared by APA staff end consultants and his.
tributed to the Board of Directors at the
nreetlno of October 2, 1985. The table is ti-
tled "Sensitivity Analyals, " but has rwlther
table number nor page number. Further, the
table is not reproduced In the APA's draft
FERC license amendment, although ttse gen-
eral outcome of the sensitivity analysis is al-
luded to In Exhibit D, P. D-4-5, of cute draft
amendment,
The Northern Engineer, Vol. 18, No. 2 and 3 31