HomeMy WebLinkAboutNome Koint Utility System Renewable Energy Fund Wind Project AppNOME JOINT UTILITY SYSTEM
a component unit of
P.O.Box 70 •Nome,Alaska 99762 •(907)443-NJUS •Fax (907)443-6336
October 7,2008
Dear Review Committee,
It is with a deep sense of immediacy that this application is submitted on behalf of City of
Nome/Nome Joint Utility System (NJUS)as a request for funding through the Alaska Energy
Authority’s Renewable Energy Grant Program.
As you are very much aware,the energy crisis facing rural Alaska has reached unsustainable levels
that threaten the health,security and abilities for residents to maintain the basic necessities of life in
a cost effective manner.The community of Nome is no exception to this challenge which can be
largely attributed to the escalation of our primary energy source,diesel fuel.Since 2003,the price of
diesel delivered to NJUS has increased by more than 250%.As a utility committed to providing
reliable and affordable electricity,we have developed a very strong and personal understanding of
how these rising costs impact our community.We,like so many other utilities across Alaska,search
on a daily basis for ways to reduce these costs that must be passed on to our consumers in order to
maintain our system and the reliable delivery of our services.
The enclosed application documents a proposed system design that will dramatically reduce the
amount of diesel being consumed by our utility through utilization of a strong,documented wind
resource.In working towards this goal,we have created a partnership consisting of the state’s most
experienced engineers,contractors and consultants to complete the wind energy project that is
documented on the following pages of this application.We aim to create what will be the largest
wind-diesel system operating in the state of Alaska through collaboration between our City of Nome
utility,our designated project manager,project partners and the regional organizations who have
pledged their support of this initiative.
We are prepared to begin the final permitting,development and construction phases for this 3MW
project immediately and request the financial support of the Alaska Energy Authority in helping us to
implement the project.We also believe we have presented a conservative estimate regarding the
expected total benefits of the project,$56 million in diesel savings alone over its operational life,
which could be dramatically increased if current fuel price trends continue to follow annual
projections.
Residents in the Nome area are also essentially hit with a double punch as we are forced to pass on
our costs to not just individuals,but also to our numerous commercial customers.As costs increase
for this market segment,retailers and service providers must also pass along the additional overhead
to residents.This,in turn,contributes to the unhealthy and unsustainable economic conditions
currently experienced in Nome and so many other rural communities.Moreover,and as a hub for
Western Alaska,it is imperative that Nome’s economy remains strong in order to support the villages
found throughout our region.In this regard,both stable and affordable energy prices become a
necessity to support existing populations and infrastructure found throughout the Bering Strait
Region.
Providing reliable utility services to system rate payers efficiently and economically by
prudently operating and maintaining system assets in a fiscally responsible manner
AEA Review Committee
October 7,2008
Page 2.
These points are well understood by many of the regional organizations that have either offered
documented support of this application,raised concern about energy costs and seeking methods to
reduce them,are implementing or have implemented alternative technology on their own,or are
involved in ongoing community discussions.These grounds include Norton Sound Economic
Development Corporation,Norton Sound Health Corporation,Kawerak,Inc.,Sitnasuak Native
Corporation and the Bering Straits Native Corporation among others.All of these parties believe the
survival of our community has been placed in jeopardy through energy inflation and our dependence
on electricity created through diesel generation.We are in desperate need of more affordable and
renewable energy supplies in order to support the continued existence of rural communities in our
state.If we are to be successful in maintaining a basic quality of life for bush residents,the
immediate implementation of renewable technologies that are proven,scalable and regional in focus
will be needed.We believe we have proposed a project that meets these requirements.
In addition to Nome,our development team has also committed to each other to develop projects
utilizing the same turbine model and similar system design in the community of Unalakleet.Through
this approach,NJUS along with Unalakleet Valley Electric Cooperative will be able to realize cost
reduction synergies,facilitate knowledge transfer regarding the utilization of wind power technology
on a regional basis and develop a higher level of understanding regarding the effective
implementation of wind power.We understand Kotzebue is also developing a similar project.We
remain open to working with them to further capitalize on any and all economies of scale that can be
realized through a partnership approach.We have worked with several regional utilities through a
fuel purchasing partnership with much success,Unalakleet and Kotzebue included;we believe we can
build on this relationship to continue to address other facets of energy cost reductions throughout
the region.
Additionally,we have received support from the Alaska’s Department of Labor indicating that
financial support for regional training will also be made available to ensure the projects that have
been proposed for Nome and Unalakleet will be sustainable if developed.In this regard,we believe
the enclosed application represents one of the greatest opportunities to reduce the cost of energy for
rural Alaska,and also one that can be utilized for future regional efforts across the state.
On behalf of the City of Nome/NJUS and the partners who have committed themselves to this
project,we respectfully submit this request for funding.Thank you for your review and please do not
hesitate to contact me should there be a need for further information regarding our application.
Sincerely,
K.Handelarid
,eneral Manager/Chief Operating Officer
NOME JOINT UTILITY SYSTEM
NJUS Renewable Energy Fund Wind Project
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 1 of 51 10/8/2008
SECTION 1 – APPLICANT INFORMATION
Name (Name of utility, IPP, or government entity submitting proposal)
City of Nome d/b/a Nome Joint Utility System (NJUS)
Type of Entity: Electric Utility
Mailing Address
P.O. Box 70, Nome, Alaska, 99762
Physical Address
1226 Port Road, Nome, Alaska, 99762
Telephone
907-443-6587
Fax
907-443-6336
Email
johnh@njus.org
1.1 APPLICANT POINT OF CONTACT
Name
John Handeland
Title
General Manager/Chief Operating Officer
Mailing Address
P.O. Box 70, Nome, Alaska, 99762
Telephone
907-443-6587
Fax
907-443-6336
Email
johnh@njus.org
1.2 APPLICANT MINIMUM REQUIREMENTS
Please check as appropriate. If you do not to meet the minimum applicant requirements, your
application will be rejected.
1.2.1 As an Applicant, we are: (put an X in the appropriate box)
X An electric utility holding a certificate of public convenience and necessity under AS
42.05, or
An independent power producer, or
A local government, or
A governmental entity (which includes tribal councils and housing authorities);
YES
1.2.2. Attached to this application is formal approval and endorsement for its project by
its board of directors, executive management, or other governing authority. If a
collaborative grouping, a formal approval from each participant’s governing
authority is necessary. (Indicate Yes or No in the box )
YES
1.2.3. As an applicant, we have administrative and financial management systems and
follow procurement standards that comply with the standards set forth in the grant
agreement.
YES
1.2.4. If awarded the grant, we can comply with all terms and conditions of the attached
grant form. (Any exceptions should be clearly noted and submitted with the
application.)
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 2 of 51 10/8/2008
Direct Labor and Benefits $ 21,200
Travel, Meals, or Per Diem $ ‐
Equipment $ 9,020,700
Supplies $ ‐
Contractual Services $ 1,737,881
Construction Services $ 3,922,528
Other Direct Costs $ 832,000
TOTAL DIRECT CHARGES $ 15,534,309
SECTION 2 – PROJECT SUMMARY Provide a brief 1-2 page overview of your project.
2.1 PROJECT TYPE
Describe the type of project you are proposing, (Reconnaissance; Resource Assessment/
Feasibility Analysis/Conceptual Design; Final Design and Permitting; and/or Construction) as
well as the kind of renewable energy you intend to use. Refer to Section 1.5 of RFA.
The NJUS Renewable Energy Fund Wind Project is a Final Design/Permitting and Construction
project for a wind energy installation in Nome, Alaska. Over the years, extensive documentation
and analysis have been conducted in the Nome region to evaluate the potential of utilizing wind
energy. These studies, including the Department of Energy’s Nome Region Energy Assessment
(published in March 2008) and various Alaska Energy Authority reports, document strong wind
resources across the Nome area including the project installation site. Moreover, these studies,
combined with conceptual designs, illustrate that reconnaissance (Phase I) and detailed project
feasibility studies (Phase II) as described in this Request for Grant Applications (RFA# AEA-09-
004) have been substantially completed.
2.2 PROJECT DESCRIPTION
Provide a one paragraph description of your project. At a minimum include the project location,
communities to be served, and who will be involved in the grant project.
The NJUS Renewable Energy Fund Wind Project involves the installation of five 600 kW wind
turbines on Newton Peak located approximately one mile north of Nome. The completed
project, with a total size of three MW, will be owned and operated by NJUS. The wind turbines
will be connected into NJUS’s electrical distribution system through a constructed transmission
line. The project will offer benefits to the community of Nome and its electric customers
through a system-wide reduction and stabilization of energy prices. NJUS has assembled a
project team, headed by STG Incorporated, that is prepared to immediately begin work on an
accelerated schedule. The project team includes members from Intelligent Energy Systems LLC,
DNV Global Energy Concepts Inc, Electrical Power Systems, Duane Miller Associates LLC,
Hattenburg Dilley & Linnell LLC, BBFM Engineers and Aurora Consulting. All aspects of the
Final Design/Permitting and Construction project, detailed in the following pages of this
application, can be completed by fall 2010.
2.3 PROJECT BUDGET OVERVIEW
Briefly discuss the amount of funds needed, the anticipated sources of funds, and the nature and source
of other contributions to the project. Include a project cost summary that includes an estimated total cost
through construction.
Project production and cost estimates, generated from independent analysis and contractor
estimates, are summarized below:
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 3 of 51 10/8/2008
The total project costs of the NJUS Renewable Energy Fund Wind Project is estimated to be
$15,534,309, inclusive of Phases I to IV. This project has advanced through Phases I and II and
is ready for Phases III and IV activities. Much of the cost of Phase I and II were borne by third-
party researchers, however, project team members have contributed $29,552 in project
conceptual design and initial feasibility study. The total grant request for the NJUS Renewable
Energy Fund Wind Project is $13,951,326 based upon the following:
Total Project Costs $15,534,309
Less: Phase I and II Contributed Costs ($ 29,552)
Total Phase III and IV Costs $15,504,757
Less: Additional Investments ($ 1,553,431)
Total Grant Request $13,951,326
The additional investment of $1,553,431 is inclusive of $830,000 of land contributed by the City
of Nome, $128,200 in labor and equipment contributed by NJUS for line transmission
construction, and $595,231 in cash contributed by NJUS/City of Nome.
2.4 PROJECT BENEFIT
Briefly discuss the financial benefits that will result from this project, including an estimate of economic
benefits (such as reduced fuel costs) and a description of other benefits to the Alaskan public.
Total net energy production estimates NJUS Renewable Energy Fund Wind Project are
8,963,000 kWh annually with an estimated net displacement of 430,195 gallons of diesel per
year. At a year-one cost of $3.72 per gallon, the project is estimated to reduce fuel costs for
NJUS by $1,600,325 annually and reduce diesel-fuel storage costs by $154,913 annually.
Other benefits of the NJUS Renewable Energy Fund Wind Project include the reduction of
atmospheric pollution, tourism development within the Nome region (estimated value $5,200
annually) and a contribution towards decreased reliance on imported fossil fuels (national
security). The projected benefit/cost ratio for this project is 3.14, payback is estimated to be
10.85 years and the internal rate of return is estimated to be 8.72%. An explanation of our
calculations and financial assumptions is included in section 4.4.6.
2.5 PROJECT COST AND BENEFIT SUMARY
Include a summary of your project’s total costs and benefits below.
2.5.1 Total Project Cost
(Including estimates through construction.)
$ 15,534,309
2.5.2 Grant Funds Requested in this application. $ 13,952,326
2.5.3 Other Funds to be provided (Project match) $ 1,582,983
2.5.4 Total Grant Costs (sum of 2.5.2 and 2.5.3) $ 15,534,309
2.5.5 Estimated Benefit (Savings) $1,755,238 – Annual
$59,846,943 – Cumulative
2.5.6 Public Benefit (If you can calculate the benefit in terms of
dollars please provide that number here and explain how
you calculated that number in your application.)
$94,830
Annual REC/Tourism Revenue
$2,370,750
Cumulative REC/Tourism
Revenue
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 4 of 51 10/8/2008
SECTION 3 – PROJECT MANAGEMENT PLAN
Describe who will be responsible for managing the project and provide a plan for successfully
completing the project within the scope, schedule and budget proposed in the application.
3.1 Project Manager
Tell us who will be managing the project for the Grantee and include a resume and references
for the manager(s). If the applicant does not have a project manager indicate how you intend to
solicit project management Support. If the applicant expects project management assistance
from AEA or another government entity, state that in this section.
NJUS will utilize James St. George, President of STG Incorporated (STG), as the project
manager for the NJUS Renewable Energy Fund Wind Project. STG is one of Alaska’s premier
construction services and management companies and has past direct experience with NJUS.
Dealing mainly in rural Alaska, the company has played a major role in high profile projects
such as wind energy installations, communication tower installation and community bulk fuel
and diesel generation upgrades. STG specializes in remote project logistics, pile foundation
installations, tower erections and construction management. STG has managed and constructed
many of the Alaska Energy Authority’s and the Alaska Village Electric Cooperative’s bulk fuel
facility and rural power system upgrade projects. STG’s core competencies include bulk fuel
systems, power plant construction, wind farms and pile foundations. Additionally, STG has
expanded to become United Utilities’ preferred contractor for its “Delta Net Project”, which
involves the installation of communication towers and related equipment throughout the Yukon
Kuskokwim Delta. STG has achieved this preferred status by demonstrating competitive rates
and the ability to perform in remote locations with extreme logistical challenges.
As project manager, James St. George and STG will be responsible to NJUS for direct project
oversight and coordination, assure project schedules, provide recommendations for NJUS
approval, have direct project oversight in accordance with NJUS policies and procedures on
labor and contractor management, equipment procurement and mobilization, review of plans and
specifications, on-site inspections, review and approval of work and other project management
duties assigned by NJUS.
References for James St. George and STG include:
Krag Johnsen, Chief Operating Officer, Denali Commission
510 L Street, Suite 410, Anchorage, AK 99501
Phone (907) 271-1413, Fax (907) 271-1415
kjohnsen@denali.gov
Meera Kohler, President/CEO, Alaska Village Electric Cooperative
4831 Eagle Street, Anchorage, AK 99503
Phone (907) 565-5531, Fax (907) 562-4086
mkohler@avec.org
Jim Lyons, Operations Manager, TDX Corporation
4300 B Street, Suite 402, Anchorage, AK 99503
Phone (907) 762-8450, Fax (907) 562-0387
JLyons@tdxpower.com
Resumes for STG are included in Section 7: Additional Documentation and Certification.
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 5 of 51 10/8/2008
PROPOSED ENERGY RESOURCE ANALYSIS
Generic Survey of Wind Energy Potential
Selection of Potential Sites
Site Specific Wind Assessment
Computation of Potential/Probable Output
EXISTING ENERGY SYSTEM ANALYSIS
Survey Transmission Access/Existing Infrastructure
Transmission Lines and System Layout and Capacity
Switchgears and Existing Power Plant Equipment
Generation Demands
Load Information
Peak Loads and Projections
Wind Energy Contributions to Power Supply
Determine Sizing Requirements
Annual O&M and R&R Costs
Annual Fuel Consumption and Fuel Price
Prepare Initial Economic Analysis
Average Cost of Installed Equipment
Avoided Cost of Energy
Service Rates
Production Estimates
Plans for System Upgrades
PROPOSED SYSTEM DESIGN
Collect Localized Wind Measurements
Annual Survey (Min)
Conduct Technology Review
Analysis of System Alternatives
Identify Technical Barriers & Issues
Conduct Layout and Design Review
Begin Site Specific Design Review with Engineering Firm
Conduct Site Assessment
Conceptual layout
Conduct Public Review
Develop Basic Integration Concept
Conceptual Integration Deisgn
PROPOSED SYSTEM COSTS
Identify Total Project Costs
Projected capital, O&M, and Fuel Costs
PROPOSED BENEFITS
Annual Fuel Displacement & Costs Analysis
Annual Review Estimates
Identify Non Monetary Benefits
ENERGY SALE
Identification of Market
Sale Rates
BEGIN PERMITTING PROCESS
Identify List of Permits Required
Develop Permit Timeline
Identify Potential Regulatory Barriers
ENVIRONMENTAL ISSUES
Initial Environmental Screening
Identify Potential Impacts
Identify Potential Regulatory Barriers
LAND OWNERSHIP
Sign Site Agreements
ANALYSIS AND RECOMMENDATIONS
Basic Economic Analysis of Alternatives
Recommendations of Additional Project Work
AEA / GEC
OCTOBER 8THSTG
DMA
STG / NJUS
Partners
STG
NJUS AURORA CONSULTING /
STG
IES/STG NJUS
STG
HDL
AURORA CONSULTING /
STG
NJUS RENEWABLE ENERGY FUND WIND PROJECT SCHEDULE
STG NJUS
NJUS AURORA CONSULTING /
STG
NJUS
PROJECT TIMELINE
Responsibility
NJUS STG / LEGAL
HDL/STG NJUS
NJUS AURORA CONSULTING /
STG
NJUS
STG NJUS/AURORA
CONSULTING
NJUS CITY
IES/EPS STG / NJUS
Phase I ‐ Reconnaissance & Phase II ‐ Feasability Analysis, Conceptual Design
3.2 Project Schedule
Include a schedule for the proposed work that will be funded by this grant. (You may include
a chart or table attachment with a summary of dates below.)
Below is a project schedule for the NJUS Renewable Energy Fund Wind Project. Note that
Phase 1 & 2 tasks are anticipated to be completed prior to receipt of grant funding. The
Grant-funded portion of the project will begin with Phase III and continue through Phase IV.
Thus, work will begin with grant funding in early 2009 and continue through delivery and
erection of wind turbines in Summer 2010.
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 6 of 51 10/8/2008
FINALIZE ENGINEERING DESIGNS
Foundation Designs
Interconnection Diagrams
Preliminary Site Layout
BID KEY EQUIPTMENT
Turbine Procurement
Tower Procurement
Switchgear Procurement
Other Procurement
BEGIN FINANCING DEVELOPMENT
Define Contract Terms
Sign Final Construction Agreement
Access Necessary Capital
Place Equipment Orders
Tax Planning for Private Entities
PROJECT COST
Final Project Costing
PERMITS & ENVIRONMENTAL
Necessary Permits Obtained
Environmental Issues Resolved
ANALYSIS AND RECOMMENDATIONS
Finalize Draft Busiiness Plan
Periodic Reporting as Required by Grant
RENEWABLE ENERGY RESOURCE
Monitor to Update Resource
PROPOSED SYSTEM DESIGN
Formal Survey Work ‐‐ Final Site Design
Take Off And Mobilization
Finalize Supply Delivery Schedules
Finalize Heavy Equipment Delivery Schedules
Organize Project Freight / Logistical Requirements
Barge Deliveries
Crew Housing
Team Development
Excavators, Operators, Electricians, Laborers
Site Access Development
Road Construction
Road Repair
Foundation Excavation
Foundation Installation
Pile Driving
Concrete Pours & Backfill
System Integration
Connection to Transmission Lines
Connection to Sub-Stations
Connection to Metering Systems
Connection to Power Distribution System
Infrastructure Connection to Powerhouse
Transmission Line Installation
SCADA Installation
System Calibration
Tower Erection
Tower Installation
Nacelle Placement
Blade Placement
PROJECT COST
Monitor to Update Resource
PERMITTING & ENVIRONMENTAL
Finalize Regulatory Requirements
Finalize Permitting Reports
ANALYSIS AND RECOMMENDATIONS
Develop Safety And Maintenance Schedule
As Built Diagrams
Relevant to Construction Changes
Relevant to Electrical/Distribution Changes
Business Plans
Update Business Plans
Periodic Reporting as Required by Grant
NJUS
STG
SUBS
HDL/STG
STG
STG IES
STG NJUS / LEGAL
NJUS/ SUPPLIER EPS/IES
HDL STG / NJUS
STG
DMA STG
BBFM/DMA STG
NJUS AURORA CONSULTING SPRING 2009
STG/ SUPPLIER(S)NJUS
STG
STG DUANE MILLER / BBFM /
NJUS
STG BARGE TRANSPORTATION
NJUS STG
STG
NJUS/STG/ EPS
EPS
FALL 2010
NJUS/GEC
NJUS AURORA CONSULTING
STG
EPS IES/SUPPLIER
SPRING 2010
STG
Phase IV ‐ Construction, Commissioning, Operation, and Reporting
Phase III ‐ Final Design & Permitting
NJUS Renewable Energy Fund Wind Project
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 7 of 51 10/8/2008
3.3 Project Milestones
Define key tasks and decision points in your project and a schedule for achieving them.
Following are the key project milestones, by project phase, and anticipated completion date:
Phase I and II Tasks (Reconnaissance , Analysis & Design)
1. Initial Renewable Resource Review Completed
2. Existing Energy System Analysis Completed
3. Proposed System Design Completed
4. Proposed System Costs Estimations Completed
5. Proposed Benefits Completed
6. Energy Market/Sales Analysis Completed
7. Permitting Review Completed
8. Analysis of Potential Environmental Issues Completed
9. Land Ownership Preparations Completed
10. Legal Consultations Completed
11. Preliminary Analysis and Recommendations Completed
Phase III Tasks (Final Design and Permitting)
12. Project Management Winter/Spring 2009
12. Perform Geotechnical Analysis Winter/Spring 2009
13. Finalize Energy Production Analysis Winter/Spring 2009
14. Finalize Foundation Designs Winter/Spring 2009
15. Finalize System Integration Designs Winter/Spring 2009
16.1 Finalize Land Agreements Winter/Spring 2009
16.2 Purchase Land Winter/Spring 2009
17. Turbine Procurement Winter/Spring 2009
18. Begin Financing Development Winter/Spring 2009
19. Apply for/Obtain Permits Winter/Spring 2009
20. Draft Final Operational Business Plan Winter/Spring 2009
Phase IV Tasks (Construction, Commissioning, Operation and Reporting)
22. Project Management Fall 2010
21.1 Foundation Material Procurement Spring 2010
21.2 Mobilization and Demobilization Costs Spring 2010
21.3 Site Access and Foundation Development Spring 2010
21.4 Foundation Installation Spring 2010
21.5 Tower/Turbine Erection Fall 2010
21.6 Transmission/Distribution Lines Fall 2010
21.7 Power Storage Foundation Pad Fall 2010
21.8 Construction Survey/As-Built Diagrams Fall 2010
21.9 Job Site Clean Up Fall 2010
22. System Integration Fall 2010
23. SCADA Installation Fall 2010
24. System Calibration Fall 2010
25. Final Business Plan Development Fall 2010
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 8 of 51 10/8/2008
Chris Schimschat Sandy St. George
VP, Field Operations Accounting
Dave Myers
Project Manager
Brennan Walsh
Project Engineer
Mia Devine Dennis Meiners Dan Rogers, P.E. Richard Mitchells, P.E. Scott Hattenburg, P.E. Troy Feller, P.E. Ann Campbell, MBA
Engineer Principal Principal Project Engineer Principal Principal Principal
Resource Wind/Integration Electrical Integration Geotechnical Project Permitting
Analysis Consultant Services Engineering
Sub-Contractors
DNV Global
Energy
Concepts (GEC)
INTELLIGENT
ENERGY
SYSTEMS (IES)
ELECTRICAL
POWER SYSTEMS
(EPS)
CITY OF NOME
NOME JOINT UTILITY SERVICE
STG INCORPORATED
DUANE MILLER
ASSOCIATES
(DMA)
HATTENBURG
DILLEY & LINNELL
(HDL)
Aurora
Consulting
James St. George, President Project Manager,
General Contractor
Denise Michaels, Mayor
John Handeland, General Manager
Land Owner
Project Owner
Business
Plannin
Structural
Engineering
BBFM
ENGINEERS
(BBFM)
g
3.4 Project Resources
Describe the personnel, contractors, equipment, and services you will use to accomplish the project.
Include any partnerships or commitments with other entities you have or anticipate will be needed to
complete your project. Describe any existing contracts and the selection process you may use for
major equipment purchases or contracts. Include brief resumes and references for known, key
personnel, contractors, and suppliers as an attachment to your application.
The NJUS Renewable Energy Fund Wind Project will be under the overall direction of John
Handeland, general manager of NJUS; while the project manager will be James St. George,
president of STG Incorporated.
Personnel: The NJUS general manager, John Handeland, will have ultimate responsibility
and authority over project decisions and will ensure that all grant requirements are fulfilled.
Mr. Handeland will be assisted by NJUS chief financial officer, Michael Cusack CPA, who
will oversee all grant accounting functions; the NJUS superintendent of field operations,
Toby Schield, will coordinate on-going field operations with the project manager, STG, and
oversee NJUS staff working on transmission construction; the NJUS power plant foreman,
Doug Johnson, will coordinate power house operations with the project manager, STG, and
assist with integration of the wind resource to the existing power generation system; and, the
NJUS line foreman, John Gould, will coordinate new line extensions with the project
manager, STG. (See Section 4.4.5 Business Plan for a more detailed discussion of NJUS – its
business structure, management, operations, etc.)
Contractors: James St. George (STG) will be the project manager of the NJUS Renewable
Energy Fund Wind Project and under NJUS management oversight will manage project
labor, consultants, procurement, construction contractors; review plans and specifications and
project work; conduct on-site inspections; and, other management functions assigned by
NJUS to ensure that the project objectives are attained. NJUS and STG have established
contractual relationships with a strong team of subcontractors to assist with this project
including Intelligent Energy Systems LLC, DNV Global Energy Concepts Inc., Electrical
Power Systems, Duane Miller Associates LLC, Hattenburg Dilley & Linnell, BBFM
Engineers and Aurora Consulting. The organizational chart below shows the key project
partners and project roles:
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 9 of 51 10/8/2008
DNV Global Energy Concepts will provide validation and analysis of wind resources. GEC
is a multi-discipline engineering and technology consulting firm providing services to clients
involved in the energy industry. Recognized as leaders in the wind energy industry, the firm
specializes in the analysis, design, testing and management of wind energy systems and
projects. GEC supported the Kotzebue Electric Association with wind resource assessment
and power performance testing tasks; is siting met towers at several locations in southeast
Alaska, worked with AEA on power performance testing at Toksook Bay and performed site
assessments at U.S. Air Force Long Range Radar Stations along Alaska’s west coast.
Intelligent Energy Systems (Principal: Dennis Meiners) will provide wind project
development and coordination services. IES provides energy project development,
management and coordination services to communities in rural Alaska with high energy
costs. IES services include: feasibility, financing, regulatory compliance, project planning,
and implementation evaluation and support/maintenance programs. Recent projects include
the Puvurnaq Power Company Model High Penetration Wind Diesel Project and three high
penetration wind diesel systems, with smart grids, for the Chaninik Wind Group.
Electrical Power Systems (Principal: Dan Rogers, P.E.) will provide electrical integration
services. EPS has historically focused on providing substation, generation, control,
protection, system planning and analysis and distribution engineering for utility, industrial
and governmental clients. The majority of EPS’ clients are based in Alaska and the firm has
extensive experience working within rural communities including the development of a
wind/diesel SCADA system for Kotzebue Electric to control the city’s six diesel generators
and its wind farm.
Duane Miller Associates, LLC (Principal: Duane Miller, P.E.) will provide geotechnical
engineering services. DMA engineers are peer reviewed and recognized experts in cold
regions geotechnical engineering as well as unfrozen ground geotechnical engineering. DMA
geotechnical engineering project experience ranges from small rural projects to large
industrial and defense projects.
Hattenburg, Dilley & Linnell (Principal: Scott Hattenburg, P.E.) will provide project
permitting and environmental services. HDL specializes in civil, geotechnical and
transportation engineering as well as providing permitting and environmental services. HDL
has extensive experience with rural energy projects and working with rural communities
including the recent completion of permitting and environmental review for the Hooper Bay
and Chevak wind projects.
BBFM Engineers (Principal: Troy Fellers, P.E.) will provide structural engineering services.
BBFM has provided structural engineering design services to military and civilian clients
throughout Alaska. BBFM has particular expertise in rural Alaska; completing more than 80
building and tower projects in western Alaska. Additionally, BBFM has designed tower
foundations in 12 different villages in soil conditions ranging from marginal permafrost in
deep silty soils to mountain-top bedrock.
Aurora Consulting (Principal: Ann Campbell, M.B.A.) will provide project planning and
business planning services. Aurora Consulting has over 30 years of experience providing
business and management consulting services throughout Alaska to a wide variety of
governmental and private entities. Additionally, Aurora Consulting has assisted with the
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 10 of 51 10/8/2008
development of business operating plans for over 75 rural utility projects, including
water/sewer projects, bulk fuel projects, electric utilities, hydro-electric projects and wind
generation projects.
Suppliers: The NJUS Renewable Energy Fund Wind Project will follow competitive
purchasing procedures that meet the standards defined in the sample AEA Grant Agreement.
Through the conceptual design planning efforts completed during Phase I and II of this
project, it has been determined that the two most critical equipment suppliers for the NJUS
Renewable Energy Fund Wind Project will be the entities supplying wind turbines and
energy storage equipment components. Independent wind resource analysis and production
estimates generated by GEC indicates that two currently available turbines, the Fuhrländer
600 FL (600 kW) and Vestas PS-RRB (600 kW), would provide similar benefits and could be
installed as proposed in this application. Conceptual planning along with the solicitation of
bids from both turbine suppliers and independent energy production estimates also indicates
that the delivery of a turn-key wind energy system, utilizing either model, would produce
both comparable costs and benefits. Detailed evaluation of both models in regards to
estimated installed cost, delivery schedules, available cold weather packages and expected
performance has been performed. Other less tangible evaluation criteria including each
supplier’s ability to provide parts for anticipated repairs over the life of the project, their
ability to support local training efforts regarding the wind turbines themselves and the
documented performance of previously installed units were also considered.
Through the conceptual planning process, we have also determined that numerous supply
options exist regarding available energy storage components.
Our conceptual planning and design work to date has incorporated the anticipated utilization
of the Vestas turbines to complete the project. Nonetheless, and due to both strong demand
for this technology in the global marketplace, along with our inability to secure a fixed
delivery schedule and fixed price of this key equipment without a secured down payment, it
is possible that the costs and delivery schedules of these turbines may become less attractive
by the time grant funds would be released to fund the proposed project (quotes remain valid
for only a 30 day period). While we believe that we could obtain comparable delivery
schedules and costs similar to those quoted, we believe that these purchasing decisions should
be revisited once awards for this grant are announced.
Equipment: All of the major construction equipment required for the NJUS Renewable
Energy Fund Wind Project will be made available by NJUS, from the local community
and/or STG. NJUS will contribute the use of equipment for project support and the
construction of transmission lines, to include:
Backhoes
Marooka (small tracked dump)
6 wheeled ATV hauler
Bucket trucks
Pickups
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 11 of 51 10/8/2008
Kobelco CK 1600, series 2, with luffing boom, 160 ton hydraulic craw
Tadando 28 ton rough terrain crane
Caterpillar D9T, bulldozer w/ ripper
Caterpillar D6R, bulldozer w/ ripper
Caterpillar 980G loader, bucket forks
Caterpillar 980G loader with masted fork lift
Caterpillar 345B excavator
Caterpillar 680E compactor
Caterpillar 287B tracked loader
3 each, Terex Series 7, 30 ton articulated dump trucks
Advanced mixer truck 12 yard
Quick way batch plant
Ingersoll -Rand ECM 370 drill
Chevy 1-1/2 ton 4x4, mechanic truck
4 pickup trucks 4x4, crew cabs
ler crane
Other major construction equipment required can be obtained in the local community or be
provided by STG from their fleet which includes:
Resumes and general information for key personnel, contractors and suppliers is included in Section
7: Additional Documentation and Certification.
3.5 Project Communications
Discuss how you plan to monitor the project and keep the Authority informed of the status.
As the grantee, NJUS general manager, John Handeland, will be the point of contact between
NJUS and the Alaska Energy Authority. As such, Mr. Handeland will be responsible for
submitting AEA monthly and quarterly progress and financial reports, which will summarize
the progress made during the reporting period and identify any difficulties in completing
tasks or meeting goals or deadlines as well as financial reports. NJUS will utilize the AEA
format for these reports.
In addition, the project manager, James St. George (STG), will be responsible to monitor the
project activities and to coordinate with NJUS. STG will coordinate daily team meetings to
outline daily objectives and issues and, weekly, will communicate with NJUS’s general
manager to identify any outstanding issues and suggested resolutions. Additionally, STG will
provide the NJUS general manager information for the AEA required monthly and quarterly
reporting. STG will focus on variance analysis, comparing actual project results to planned
or expected results; a summary of tasks completed during the reporting period; a summary of
tasks scheduled for completion in the next reporting period; and, identification of project
challenges and problems. STG will provide the information to the NJUS in the approved
AEA format for these reports.
Change Process: The information contained within the project plan will likely change as the
project progresses. While change is both certain and required, it is important to note that any
changes to the project plan will impact at least one of three key success factors: available
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 12 of 51 10/8/2008
time, available resources or project quality. The decision by which to make modifications to
the project plan will be coordinated using the following process:
Step 1: As soon as a change that impacts project scope, schedule, staffing or spending is
identified, the project manager will document the issue.
Step 2: The project manager will review the change and determine the associated impact
to the project and will forward the issue, along with a recommendation, to NJUS
and/or AEA for review and decision.
Step 3: Upon receipt, the NJUS general manager, project manager and/or AEA should
reach a consensus opinion on whether to approve, reject or modify the project
plan based upon the project manager’s recommendation and their own judgment.
Step 4: Following an approval or denial, the project manager will modify the project plan
and notify all the affected project partners.
3.6 Project Risk
Discuss potential problems and how you would address them.
If constructed, The NJUS Renewable Energy Fund Wind Project would become the largest
wind-diesel system operating in the state of Alaska. As such, the project planning must
incorporate an ongoing analysis of potential problems and strategies to address them.
Outlined below are the key issues the project is anticipated to encounter:
Issue #1: Quantifying wind and ice loads for the structure at the 1,000 +/- foot elevation
to derive reliable foundation loading conditions. Structures at this elevation will
have significantly different ice and wind loading - unreliable tower loading
conditions may lead to over-designed or under-designed foundation systems.
Strategy to address: We will rely upon historic data from Anvil Mountain and the
Nome met station data to estimate icing and wind design considerations. The design
team will incorporate meteorological assessment conducted by trained climatologists,
specific to the Nome area. Ice and wind measurements at Anvil Mountain will be
conducted routinely over the winter/spring 2008/2009 to establish baseline design
data.
Issue #2: Powerline access routing and design. Overhead powerlines will need reliable
wind and ice loading states for their design life in order to design adequate powerline
structures. Permafrost and seasonal frost forces as well as groundwater will impact
both the route alignment and powerline performance. If icy soils are encountered
along the alignment, thaw strains can be expected. Trench backfill may increase
trench drainage with potential piping of fill along the powerline.
Strategy to address: Powerline routing will be conducted concurrent with site road
access. Icing data will be used to determine the conversion point from lower
elevation overhead to higher elevation underground systems. Frost considerations
along the alignment will be investigated as part of the tower geotechnical design.
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 13 of 51 10/8/2008
Issue #3: Constructing a cost-effective tower foundation.
Strategy to address: Foundation design will be developed with both the contractor
and engineer, working together as a team, to determine appropriate materials and
systems for the site. STG and BBFM have successfully worked together on many
other communication tower and wind tower foundation designs in remote Alaskan
locations. Getting contractors input up front at the concept stage of design will allow
for an appropriate foundation system to be developed.
Issue #4: Developing a tower foundation design that can be adapted for unforeseen field
and geotechnical conditions.
Strategy to address: Design and selection of foundation systems that can be modified
in the field will allow us to overcome unforeseen conditions. This also applies to the
quantity of foundation materials that will be transported to the site.
Issue #5: Cold weather operations/Turbine icing. Extremely low temperatures may cause
materials to become brittle and less ductile, and lubricants to become less viscous,
which could result in damage to parts. Such temperatures may also cause electronic
and hydraulic systems to cease working.
Strategy to address: It is anticipated that the turbines will experience icing conditions
which will result in the loss of potential energy production. While these losses have
been included in the production estimates, and anticipated in the system design,
reducing these losses represents a significant opportunity to improve project
economics. And several approaches to increasing production have been proposed;
including blade coating, careful selection of materials and the addition of special
heaters and sensors.
Issue #6: Coordinated integration; matching wind to the community.
Strategy to address: The value of a variable wind resource is maximized through the
integrated operation of both generation equipment and loads. This is accomplished
with automated control systems and ability to rapidly visualize, diagnose and make
adjustments. This is enabled by remote monitoring and diagnostics. Data,
information and observations obtained from operational monitoring are necessary to
ensure on-going performance and reliability. Each major system component will be
monitored and its performance recorded and reported automatically. This information
will be readily available and from the internet. This information will allow the
system to be continuously recommissioned, insuring confirmation or proper operation
of all controls, communications and system components.
.
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 14 of 51 10/8/2008
SECTION 4 – PROJECT DESCRIPTION AND TASKS
• Tell us what the project is and how you will meet the requirements outlined in Section 2 of the
RFA. The level of information will vary according to phase of the project you propose to
undertake with grant funds.
• If you are applying for grant funding for more than one phase of a project provide a plan and grant
budget for completion of each phase.
• If some work has already been completed on your project and you are requesting funding for an
advanced phase, submit information sufficient to demonstrate that the preceding phases are
satisfied and funding for an advanced phase is warranted.
4.1 Proposed Energy Resource
Describe the potential extent/amount of the energy resource that is available.
Discuss the pros and cons of your proposed energy resource vs. other alternatives that may be
available for the market to be served by your project.
In March 2008, the Department of Energy released a final draft report that evaluates the energy
resources and energy needs of the Nome region. This report contains extensive analysis that
documents the options currently available for the Nome area to reduce energy costs through the
implementation of non-diesel electricity generation technologies. Excerpts from this report, which
determined that “the most likely prospect of immediate savings gain is the installation of wind
turbines to offset diesel generation for the electric utility”, are contained in the appendix of this
application. The authors’ summary of the energy resources evaluated for the Nome area along with
their conclusions are copied below:
“The energy technologies analyzed for Nome fall into two categories, (a) technologies that rely upon
known energy resources—diesel, wind and coal; and (b) technologies that would rely upon
hypothetical (or untested) resources—geothermal and natural gas. Geothermal and natural gas
resources are known to exist based on limited evaluation, but will require expensive exploration to
prove the resources exist in sufficient quantity and deliverability to meet the requirements. The
exploration and development costs for geothermal and natural gas are not well established and will
require additional analysis to confirm the estimates. The natural gas options assumed that a drill ship
would be available at day rates only and that the costs to obtain and move a ship to and from Norton
Sound would not have to be borne by the project.
The present value comparisons indicate that for the assumptions incorporated in the analysis regarding
each of the alternatives, the wind/diesel, geothermal plant, barge-mounted coal plant using high Btu
coal and natural gas exploration and development are all economically equal or better than continued
reliance on diesel for both mid-range and high-range diesel price escalation. The lower Btu coal
option is slightly better in the instance of a high-range diesel price escalation. The development of a
natural gas resource, in addition to showing a strong potential for savings in the operation of the
electric utility, would provide an economical option by providing natural gas for water and space
heating throughout the community.
Of the alternatives investigated, the most likely prospect of immediate savings gain is the installation
of wind turbines to offset diesel generation for the electric utility. Wind units are commercially
available, and the Nome utility system has already anticipated the advent of wind by including
integration capability in the construction of the new power house.
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 15 of 51 10/8/2008
The geothermal and natural gas prospects both indicate potential savings greater than the wind
resource, but will require additional investment in exploration and development to verify the resource
potential. Nevertheless, the potential gain from each is significant, with the natural gas prospect in
particular providing the additional benefit of displacing fuel oil for space and water heating.
The coal plant prospect with high-Btu coal provides savings to the electric system, but to a lesser
extent than the other alternatives. With low-Btu coal, savings would only be available under a high
rate of diesel price escalation and under conditions of coal prices remaining constant in real terms. In
either case, the savings associated with the prospect of a coal power plant are based on an engineering
estimate of costs to construct an initial unit. Economies of scale from construction of multiple units of
a similar design could reduce the capital cost of the system and improve the economics of a coal-
based alternative.”
See Section 7: Additional Documentation and Certification for detailed studies on the Nome wind
resource, including studies by the U.S. Department of Energy, the Alaska Energy Authority and DNV
Global Energy Concepts Inc.
4.2 Existing Energy System
4.2.1 Basic configuration of Existing Energy System
Briefly discuss the basic configuration of the existing energy system. Include information about the
number, size, age, efficiency, and type of generation.
In 2007, NJUS put on-line a new $35 million state-of-the-art power generation plant that replaced the
antiquated plant, which served the community for the previous 50 years. Currently, the NJUS
electrical power generation system consists of diesel powered generators, as outlined below:
Brand/Model Size (kW) Age Avg. Efficiency (kWh/Gal. Diesel)
EMD #20-645F4B 2,865 23 13.08
EMD #12-645E4 1,500 19 12.84
Caterpillar #3516 3,660 17 16.39
Caterpillar #3516B-LS 1,875 9 14.35
Wärtsilä #12V32B 5,211 3 16.32
Wärtsilä #12V32B 5,211 3 16.32
Caterpillar #3456B 430 3 Black start – not yet used
Boiler 1.5M BTU 3 Emergency only – not yet used
Boiler 1.5M BTU 3 Emergency only – not yet used
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 16 of 51 10/8/2008
4.2.2 Existing Energy Resources Used
Briefly discuss your understanding of the existing energy resources. Include a brief discussion of any
impact the project may have on existing energy infrastructure and resources.
Currently, NJUS utilizes diesel to generate its electricity. During the past 12 months, NJUS consumed
2.3 million gallons of diesel for power generation purposes; at a cost of $5.5 million. As with other
rural Alaska locations, the price of diesel fuel is rising exponentially - since 2003, the price of diesel
delivered to NJUS has increased by more than 250%. According to project planning estimates, NJUS
should achieve net generation of approximately 6,812 MWh utilizing the new wind turbines. Based
upon a reported average diesel-generator efficiency of 15.83 kWh/Gal, NJUS would realize an annual
savings of 430,195 gallons of diesel fuel per year. At an average price of $3.72 per gallon, NJUS
would recognize an annual fuel savings of $1,600,325.
4.2.3 Existing Energy Market
Discuss existing energy use and its market. Discuss impacts your project may have on energy
customers.
Currently, the majority (80%) of NJUS customers are residential (single phase) customers, with
commercial customers constituting the second largest (13%) number of customers.
Number of Customers ‐ Twelve Months Beginning September 1, 2007
Nome is a hub community for western Alaska and has a large population for one of the state’s rural
communities – the 2007 State of Alaska certified population for Nome was 3,497. According to the
2000 U.S. Census data, Nome averages 2.90 persons per household. The vast majority of Nome’s
population is on the power-grid and is experiencing economic pressure from the rapidly rising energy
costs.
Additionally, as the regional hub, much of the Bering Straits region economy is focused on commerce
and industry based in or near the City of Nome. Residents in the Nome area are negatively impacted
as NJUS passes on rising fuel costs to its commercial customers. Currently, while constituting only
16% of customers, the commercial and governmental customers (non-PCE customers) purchase
77.3% of the kWh produced.
kWh Sold ‐ Twelve Months Beginning September 1, 2007
Average %
Single Phase 1,642 80.18%
Commercial 273 13.33%
Comm Fac 82 4.00%
Govt 51 2.49%
Total 2,048 100.00%
Total %
Residential 5,485,167 22.65%
Comm Fac 2,010,273
Total PCE 7,495,440
Non PCE 25,602,975 77.35%
Total 33,098,415 100.00%
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 17 of 51 10/8/2008
As costs increase for this market segment, retailers and service providers must also pass along the
additional overhead to individual residents. This, in turn, contributes to the unhealthy and
unsustainable economic conditions currently experienced in Nome and, so many, other rural
communities.
Moreover, and as a hub for Western Alaska, it is imperative that Nome’s economy remains strong in
order to support the villages within the region. Both stable and affordable energy prices become a
necessity to support existing populations and infrastructure throughout the Bering Strait Region.
These points are well understood by many of the regional organizations that have offered documented
support of this application including Norton Sound Economic Development Corporation, Norton
Sound Health Corporation and the City of Nome. All of these parties believe that Nome’s economy is
in jeopardy due to energy inflation and the region’s dependence on diesel-generated electricity.
4.3 Proposed System
Include information necessary to describe the system you are intending to develop and address
potential system design, land ownership, permits, and environmental issues.
4.3.1 System Design
Provide the following information for the proposed renewable energy system:
• A description of renewable energy technology specific to project location
• Optimum installed capacity
• Anticipated capacity factor
• Anticipated annual generation
• Anticipated barriers
• Basic integration concept
• Delivery methods
System Overview
Wind-diesel power systems are categorized based on their penetration levels and categorized as low
penetration, medium penetration, high penetration and high penetration diesel off configurations. As
the level of penetration increases, the average proportion of wind-generated energy to the total amount
of energy supplied to the system, the degree of communication between existing power generation
facilities and the installed wind energy systems increases in complexity. It has been demonstrated that
low penetration systems, ones in which the proportion of wind-generated energy to total generated
energy rarely does not exceed 30%, require few modifications to the existing diesel systems, but are
generally less economical due to limited fuel savings, in comparison to total installation costs. This is
especially true for systems designed for rural Alaskan communities because of the fixed installation
costs - primarily the cost of transporting the heavy construction equipment and foundation materials
needed to complete village power systems. And, these costs are incurred regardless of the total size of
the project. In efforts to construct a system that considers the realities of these cost issues, this
application documents a medium penetration system design that aims to maximize the absorption of
available wind energy, while keeping power quality high and reducing diesel generation costs as much
as possible. Furthermore, and as a result of the estimated penetration levels of the proposed system,
specific equipment and operating changes will be needed to integrate the proposed wind farm into
NJUS’s existing infrastructure.
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 18 of 51 10/8/2008
The Wind-diesel system proposed in this application is based on the following objectives:
• Maximize fuel savings through the implementation of a system design that will deliver the
highest cost to benefit ratio possible
• Maintain high power quality and system stability
• Utilize standardized, proven and scalable commercial components that will provide
opportunities to utilize additional renewable energy supplies in the future
The system architecture proposed in this application consists of four primary elements:
• Five 600 kW Vestas PS-RRB wind turbines
• A kinetic (flywheel) energy storage system
• A distributed integrated control system
• A heat recovery boiler to capture any excess wind energy
While the design proposed in this application would make the completed project the largest wind
turbine installation in Alaska once constructed, it consists of proven technology that will be completed
and supported through contracted services with a team of Alaska’s most experienced wind energy
professionals. Similar wind-diesel systems, to the one proposed in this application, have been
deployed successfully in markets across the world. Moreover, it is believed that the implementation
of this proposed wind installation will provide significant opportunities to further develop Alaska’s
knowledge base regarding wind energy systems.
Project Location
Various installation locations for the project were considered based on the review of documented wind
resource data, land availability and existing electrical distribution infrastructure. Project team
members have concluded that the most suitable location for the wind farm would be on Newton Peak,
a documented class 6 wind site, which is property owned by the City of Nome. The City of Nome has
issued a resolution stating that land would be made available to NJUS to develop a project at this
location, which is approximately 1 mile north of Nome. This resolution is included in Section 7 –
Additional Documentation and Certification. Moreover, and through consultation with an appraiser
hired by the City of Nome, the land’s value has also been determined and allocated as a certified
project match. A letter from the City of Nome is included in Section 7: Additional Documentation
and Certification attesting to the land value. Below is a site diagram of the proposed wind farm:
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 19 of 51 10/8/2008
System Architecture
Wind Turbines
During the conceptual design phases of this project, two 600 kW turbines were evaluated based on a
variety of criteria. These considerations included estimated delivered price of all wind turbine
components (generator, blades, tower, controls, etc.), estimated delivery schedule, expected
performance and total potential savings. Our analysis has produced estimates which indicate that both
turbines would produce similar cost benefit ratios if selected as the primary component of the
proposed system in this application. Nonetheless, due to the high demand of wind turbines in the
global market, along with the limited supply of turbines of this particular size, we believe that it is
possible that we will no longer have access to either of the turbines that have been evaluated at the
prices that have been quoted to us or within the delivery times that have been promised by the time
grant funds are allocated. We believe that the final decision as to what turbine will be utilized will
need to be made at the time when funds are made available. Of the two turbines that have been
considered, the Fuhrländer 600 FL (600 kW) and the Vestas PS-RRB (600 kW), we have based our
conceptual planning on the installation of the Vestas model. Should it become more attractive for
NJUS to consider the Fuhrländer unit at the time of an award, we believe that only minor
modifications of previously completed conceptual designs and cost estimates would be necessary.
Our project team is prepared to move forward on an accelerated construction schedule utilizing either
model should an award be granted.
This application proposes that five 600 kW Vestas PS-RRB wind turbines be installed on top of
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 20 of 51 10/8/2008
Newton Peak on 50 meter tubular towers. Summary specifications of the PS-RRB turbine are
included below:
The Vestas PS-RRB is a three-bladed, horizontal axis wind turbine based on the Vestas V-47 design.
The PS-RRB model is currently being manufactured new by RRB Energy in India through the
oversight of Vestas corporate, the world’s leading wind turbine manufacturer. Approximately 3,000
of the previously discontinued V-47 turbines have been installed in the U.S. market and over 600 of
the RRB design are currently in operation. With the exception of the Siemens generator that is
included in the RRB model, all parts are interchangeable with standardized V-47 components. Due to
the familiarity of the V-47 design to the majority of wind industry technicians and the ability to obtain
replacement parts, it is believed that the RRB turbines could be readily serviced and the further
utilization of Vestas turbines would support the number of Vestas machines already in service across
rural Alaska.
To further evaluate the attractiveness of utilizing the wind resource at the proposed installation site, in
general, and to compare the two particular turbine models under consideration specifically, DNV
Global Energy Concepts was commissioned to perform a wind energy production analysis. The study
was completed through the use of computer modeling software supported by documented wind
resource data supplied by the Alaska Energy Authority and historical production information supplied
by NJUS. The complete study is contained in Section 7: Additional Documentation and Certification
and a summary of their conclusions are noted below:
Energy System Modeling Results (Total project production based on 8 m/s wind speed)
Description VESTAS FUHRLÄNDER
Gross wind energy production (MWh/yr) 8,963 9,989
Gross wind turbine capacity factor (%) 34.10% 38.00%
Fuel consumption of diesel-only system (gal/yr) 2,103,000 2,103,000
Fuel consumption of wind-diesel system (gal/yr) 1,539,000 1,527,000
Gross diesel fuel savings (gal/yr) 563,000 562,000
Energy loss correction factor 0.76 0.76
Net diesel fuel savings (gal/yr) 428,000 427,000
Net diesel fuel savings (%) 20% 20%
Source: DVN Global Energy Concepts
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 21 of 51 10/8/2008
In addition to cost and production considerations, the Vestas PS-RRB turbine was selected for its
relationship with an industry standard and proven design, access to a service and support network, an
estimated nine month delivery time, and the willingness of the manufacturer to support and customize
these turbines for extended cold weather operation.
Project partners have also engaged Alaska’s Department of Labor in discussions regarding the
creation of a training program that would provide local residents with the skills necessary to perform
routine maintenance and repairs on the installed turbines. Similar programs have already been
developed through partnership between the Department of Labor, Alaska Village Electric
Cooperative, STG and Northern Power Systems that have successfully trained individuals to perform
these services within their communities. Initial discussions about the creation of similar programs
designed around the specifications of the Vestas machines have been positive and further
collaboration between all involved parties is expected to materialize into the development of a new
training program, should grant funds be awarded to implement this proposed project.
Flywheel Energy Storage System
The NJUS diesel generator sets have capacities of 5200 kW, 3800 kW and 1875 kW respectively.
The existing plant control system senses the demand, at any given point in time, and automatically
dispatches the most efficient generator set, or combination of sets, to meet that load. As a result of
the intermittent supplies of energy that will be fed into NJUS’s distribution system through the
completion of this proposed project, some modifications of the existing NJUS infrastructure will be
necessary. Moreover, and due also to the energy demands placed on NJUS through mining operations
at Rock Creek, we believe that the installation of a flywheel at the NJUS plant would both add
stability to the overall system and provide opportunities to more efficiently balance the intermittent
energy supplies delivered from the installed wind turbines.
Our proposed system design involves the installation of a flywheel that is electrically coupled to the
existing power system. The flywheel and power electronics interface combination, by itself, is
capable of basic stabilization of both the voltage and frequency of the power system without any
additional information from external sources. Inherently, flywheels are able to achieve this
stabilization through frequency and voltage sensing of the grid along with the stepless absorption and
exportation of real power for frequency variation and reactive power for voltage support. The energy
stored in the flywheel reduces cyclic loading and smoothes out power fluctuations as the electric load
and wind turbine outputs change. This level of stabilization also allows for greater diesel cost savings
due to lower diesel set points on the generators, reduced spinning reserve on the flywheel itself and
reduced maintenance costs with diesel generator sets.
The fast acting flywheel energy storage system will also provide system stability on a sub-cycle basis.
The sub-second response of flywheel systems is supplemented by the multi-second response of the
diesel generators. This capability decreases the contribution of the diesel generators while riding
through fluctuations of the wind. Finally, additional system stabilization is achieved by controlling
the pitch and power set points of wind turbines themselves.
We believe that there are numerous suppliers of flywheel technology that could provide NJUS with
necessary integration components once exact system specifications have been established. As
indicated in the guidelines relayed in the sample grant agreement for this RFA, NJUS intends to
follow a competitive bid process to secure this equipment when conceptual integration designs
become finalized.
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 22 of 51 10/8/2008
Distributed Integrated Control Network
To maximize the diesel savings generated through the installed wind energy system while maintaining
system stability, all components must operate in a coordinated manner across the grid. This will be
achieved through the installation of a network of distributed integrated controllers. These controllers,
but more specifically the larger network, are designed to interface with existing power station
controls. Controllers are typically mounted into existing control cabinets. Each device is driven by
advanced software applications that allow each component within the system to recognize and
coordinate its activities with the other units supplying or regulating energy flows on the system.
The Distributed Integrated Control Network (DICN) also expands the capabilities of the existing plant
supervisory control and data acquisitions system (SCADA) through the network of standard,
commercially available component controllers, which run sophisticated software to integrate
increasing levels of wind energy. In the wind-diesel configuration that has been proposed in this
application, the power plant SCADA would trigger the various diesel generators to start and stop;
while also issuing power set-points for each component in the power plant. The DICN would
incorporate the setting and commands of the SCADA and configure the other components of the
system, based on the load and available wind energy.
In addition to the installed wind turbines and existing generator sets, a DICN controller would also be
embedded in the flywheel module. Thus, the modular distributed control system controller could also
be used as a complete, or supplementary, SCADA system, if called for during the development of
finalized integration plans. Software will need to be either developed by partners or sourced by
suppliers for this level of functionality - functionality designed to issue start, stop, step point
commands and drive user interfaces, while providing opportunities for remote diagnosis. These
features will be an essential component of the completed project that ultimately will be monitored by
NJUS and electrical integration partners.
Other components of the control network include:
• Diesel Generator Monitors: Small DIN-rail monitoring modules will be added to the existing
generator controllers. These modules communicate information between the generator sets
and installed flywheel about the current state of the generator (running, stopped, on-line or off-
line) as well as how much power the generator is delivering at any given point in time.
• Wind Turbine Interface: The wind turbines are provided with a customer interface to the
wind turbine controller (WTC) and monitoring modules will be added in order to communicate
with the wind turbines. These modules send and receive data, such as the state of the machine
(running, stopped, on-line and off-line, power generated, alarms, nacelle position, etc.), current
energy production, system performance and system monitoring. Commands can be initiated
from the wind turbine controller itself or from a centralized control station and typically
include options that will allow system operators to start/stop turbines, control power outputs of
the turbines through pitch regulation or power set point control and adjust other blade
components. The WTC would communicate with NJUS via fiber optic cable that will be run
from the installation site into the existing distribution system adjacent to Nome’s high school
and will be provided by the turbine supplier.
Heat Recovery System
There will be times when the output of the wind farm proposed in this application could exceed the
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 23 of 51 10/8/2008
electric requirements of the community. Under these conditions, two options are available to maintain
system stability:
1. wind turbine output can be curtailed or
2. loads can be managed to capture or control this excess energy.
In efforts to capture all energy supplied from the installed wind turbines, our system design includes
the installation of an electric boiler grid interface to be installed at the Nome High School swimming
pool complex. This boiler grid interface would be utilized primarily as a system dump load designed
to capture excess wind energy.
Through communication with other system components and system wide energy monitoring, the
dump load interface can be used to efficiently manage power supplies while making maximum use of
the wind energy generation. During times of increasing wind power generation, the dump load system
funnels excess energy (energy that at any given point in time exceeds current system wide electricity
demand) into a thermal heating unit. Thus, excess energy supplies are managed by increasing the total
system load.
During times of collapsing wind power generation, the dump load interface follows the total system
load closely and reacts by decreasing its load. Thus, the dump load interface is able to lower the total
power demand on the entire system. The installation of the dump load interface is also expected to
improve the grid quality by providing reactive power and voltage level stabilization.
The electric heat recovery boiler would be plumbed into the existing heating system located at the
community pool. Excess wind energy, when available, would be captured in this boiler and the heat
used to offset fuel costs of running the high school and swimming pool. The heat recovery load at the
high school would also require a separate metering and service panel, including cables and breakers.
The system would also be designed to utilize the existing temperature controls and act as demand
managed devices controlled through the master control overlay. The method of communication
proposed is Ethernet.
Major community buildings with large heating requirements, such as the school, city offices, the
Nome hospital, city shop, and water and sewer treatment facilities also have been considered as other
potential installation sites for dump load components if the proposed wind farm is expanded at a later
date and it is deemed necessary to install additional system dump loads.
Energy Delivery and Integration Design
Installed wind turbines will be placed approximately 900 feet apart on top of Newton Peak as
described earlier in this section. Conceptual project designs also indicate that approximately two
miles of new transmission lines will be needed to connect the installed turbines to existing 12.47 kV
transmission lines on the Kougarok Road, west of the installation site. Power lines connecting the
turbines and substations to existing electrical distribution lines will be buried in order to achieve cost
savings and reduce the potential of icing complications. Once connected to the existing system,
energy supplies and system performance will be monitored as indicated earlier in this application. A
one-line diagram of the proposed system is below:
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 24 of 51 10/8/2008
4.3.2 Land Ownership
Identify potential land ownership issues, including whether site owners have agreed to the project or
how you intend to approach land ownership and access issues.
The City of Nome owns the land at Newton Peak where the proposed wind farm will be located. As
the owner of the NJUS, the City of Nome definitely has a vested interest in the proposed NJUS
Renewable Energy Fund Wind Project and is committed to providing the land resources needed for
the project. The City of Nome will contribute, as match, the required land.
There are no known, or unresolved, land issues at this time.
See Section 7: Additional Documentation and Certification for a letter of commitment from the City
of Nome and certification of land valuation.
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 25 of 51 10/8/2008
4.3.3 Permits
Provide the following information as it may relate to permitting and how you intend to address
outstanding permit issues.
• List of applicable permits
• Anticipated permitting timeline
• Identify and discussion of potential barriers
Based upon consultation with Hattenburg Dilley & Linnell LLC and information supplied in the
“Nome Region Energy Assessment, DOE/NETL 2007/1284”, the following chart has been prepared to
indicate applicable Federal and State permitting activities and their relevance to project components:
Permit/Activity Applicability
EPA
National Pollutant Discharge Elimination System Applicable (if
stormwater from
construction
disturbance)
National Marine Fisheries Service
Endangered Species Act Consultation Applicable
F&W Coordination Act Consultation, Marine Mammal Act Applicable
U.S. Fish & Wildlife
ESA Consultant Applicable
F&W Coordination Act Consultation
Migratory Bird Protection Act Consultation Applicable
Federal Aviation Administration
Tower/lighting permit Applicable
Alaska Department of Natural Resources
Alaska Coastal Management Program (ACMP) Consistency
Review
Applicable (within
coastal zone)
Coastal Plan Questionnaire Applicable (within
coastal zone)
Cultural Resource Protection Applicable
Alaska Department of Environmental Conservation
Section 401 Certification Applicable
HDL will lead project permitting efforts and anticipates that the permitting process will be completed
within 120 days of the start of the project. This is based upon similar project experience and the
following:
• A field archaeological survey will not be needed for SHPO concurrence
• There is no reason to assume there will be any significant environmental impacts
• A Phase I Environmental Site Assessment should not be needed
• Field delineation of wetlands should not be needed
While there is not reason to believe that the project will encounter any insurmountable barriers, there
are two potential challenges that could arise:
1. The U.S. Fish & Wildlife Service may express concern regarding transmission lines and their
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 26 of 51 10/8/2008
potential impact on migratory birds or the eiders, an endangered species found in the area
surrounding Nome.
Strategy to Address: Coordination will begin early in the project. At times mitigation can
involve slight relocations to avoid potential concerns and this will be done early in Phase III.
Underground transmission lines will be used to avoid these concerns.
2. Coordination with the FAA to determine air hazards will be critical.
Strategy to Address: Coordination will begin as soon as the project begins in order to
incorporate FAA considerations into final designs.
4.3.4 Environmental
Address whether the following environmental and land use issues apply, and if so how they will be
addressed:
• Threatened or Endangered species
• Habitat issues
• Wetlands and other protected areas
• Archaeological and historical resources
• Land development constraints
• Telecommunications interference
• Aviation considerations
• Visual, aesthetics impacts
• Identify and discuss other potential barriers
Environmental analyses will be conducted to evaluate the potential effects of the proposed
project. This analysis will not involve field work at this level outside of the site visit.
Anticipated environmental issues to be addressed include:
• Historical and Cultural Impacts. A search of the Alaska Historical Resource Survey will
be conducted. After consulting with the native tribes and corporations, we will seek a
State Historical Preservation Office (SHPO) concurrence of “No Historic Properties
Affected.”
• Wetlands. A review of the U.S. Fish & Wildlife Service’s National Wetlands Inventory
will be conducted to identify wetlands in the project area. Where wetlands are
encountered, a delineation report will be submitted to the U.S. Army Corps of Engineers
for a jurisdictional determination. Wetlands impacts will be minimized to the greatest
extent feasible.
• Threatened & Endangered Species. An informal U.S. Fish & Wildlife Service (USF&W)
Section 7 Consultation is anticipated due to the concern generated from wind towers and
transmission lines with regards to migratory birds.
• FAA Determination of No Hazard. HDL will apply for a determination from the FAA
that the wind towers will not be a hazard to air traffic in the area due to its proximity to
the airport.
Issues that are not anticipated to be of major concern, but will be addressed, include land
development constraints, telecommunications interference and visual impacts.
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 27 of 51 10/8/2008
4.4 Proposed New System Costs (Total Estimated Costs and proposed Revenues)
The level of cost information provided will vary according to the phase of funding requested and any
previous work the applicant may have done on the project. Applicants must reference the source of
their cost data. For example: Applicants Records or Analysis, Industry Standards, Consultant or
Manufacturer’s estimates.
4.4.1 Project Development Cost
Provide detailed project cost information based on your current knowledge and understanding of the
project. Cost information should include the following:
• Total anticipated project cost, and cost for this phase
• Requested grant funding
• Applicant matching funds – loans, capital contributions, in-kind
• Identification of other funding sources
• Projected capital cost of proposed renewable energy system
• Projected development cost of proposed renewable energy system
The total project cost of the NJUS Renewable Energy Fund Wind Project is estimated to be
$15,534,309, inclusive of Phases I to IV. As discussed previously, this project has advanced through
Phases I and II and is ready for Phases III and IV activities.
Much of the cost of Phase I and II were borne by third-party researchers, however, project team
members have contributed $29,552 in project conceptual design and initial feasibility study. The total
grant request for the NJUS Renewable Energy Fund Wind Project is $13,951,326 based upon the
following:
Total Project Costs $15,534,309
Less: Phase I and II Contributed Costs ($ 29,552)
Total Phase III and IV Costs $15,504,757
Less: Additional Investments ($ 1,553,431)
Total Grant Request $13,951,326
The additional investment of $1,553,431 is inclusive of $830,000 of land contributed by the City of
Nome, $128,200 in labor and equipment contributed by the NJUS for line transmission construction,
and $595,231 in cash contributed by the NJUS.
As indicated in the following budget summary, project costs have been developed utilizing contractor
and vendor bids and cost quotes. The professional, contractual and construction cost estimates are
expected to remain valid until the end of 2008; however, the turbine cost estimates are only valid for
30 days. As discussed earlier, this is not anticipated to create insurmountable project delay or
overruns.
Additionally, the budget summary below indicates that approximately 10% of the total project cost
will be contributed by the NJUS and the City of Nome - $595,231 in cash and $958,200 in in-kind
contributions.
The capital costs for this project are estimated to be $15,102,757 and development costs are estimated
to be $431,552.
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 28 of 51 10/8/2008
4.4.2 Project Operating and Maintenance Costs
Include anticipated O&M costs for new facilities constructed and how these would be funded by the
applicant.
• Total anticipated project cost for this phase
• Requested grant funding
The anticipated fixed operating and maintenance (O&M) costs for the NJUS Renewable Energy Fund
Wind Project are 3% of the project costs annually and variable O&M costs are $.00975 per kWh.
(Based upon industry standards presented in the U.S. Department of Energy report, “The Nome
Region Energy Assessment, DOE/NETL 2—7-1284”) Therefore, based upon total project costs of
$15, 534,309, the annual fixed O&M would be $436,397. And, based upon expected annual gross
energy generation of 8,963 MWh, variable O&M costs would be $87,389. The total estimated annual
O&M costs would be $523,786. While it is expected that NJUS would potentially add one new staff
member to manage the new wind farm, the annual estimated expenses would vary and are not
anticipated to reach this total amount each year. The anticipation of performing certain major repairs
on the wind farm during certain periods of its operational life (gear box replacement, blade repair,
etc.) has been factored into this estimated annual average O&M expense. On-going O&M costs of the
constructed wind project would be funded by energy sales by NJUS.
BUDGET INFORMATION
BUDGET SUMMARY:NJUS Renewable Energy Fund Wind Project
Milestone Federal Funds State Funds
Local Match
Funds (Cash)
Local Match Funds
(In‐Kind) Other Funds TOTALS
Phase I and II Tasks (Reconnaissance, Feasibility and Conceptual Design)
1. Initial Renewable Resource Review (DOE Report)$0 $0
2. Existing Energy System Analysis (DOE Report ‐ Partners)$4,302 $4,302
3. Proposed System Design (All Project Partners)$8,004 $8,004
4. Proposed System Costs Estimations (All Project Partners)$3,336 $3,336
5. Proposed Benefits (GEC ‐ STG)$3,804 $3,804
6. Energy Market/Sales Analysis (NJUS)$1,998 $1,998
7. Permitting Review (HDL)$230 $230
8. Analysis of Potential Environmental Issues (HDL)$230 $230
9. Land Ownership Preparations (NJUS)$1,998 $1,998
10. Legal Consultations $400 $400
11. Preliminary Analysis and Recommendations (Aurora Consulting)$5,250 $5,250
$29,552
Phase III Tasks (Final Design and Permitting)
12. Project Management (STG Estimate)$125,000 $125,000
13. Perform Geotechnical Analysis (DMA Estimate)$44,000 $44,000
14. Finalize Energy Production Analysis (GEC Estimate)$10,000 $10,000
15. Finalize Foundation Designs (BBFM Estimate)$19,000 $19,000
16. Finalize System Integration Designs (IES/EPS Estimate)$222,346 $222,346
17.1 Finalize Land Agreements (Legal Estimate ‐ NJUS)$2,000 $2,000
17.2 Purchase Land (NJUS)$830,000 $830,000
18. Turbine Procurement (Turbine Estimate ‐ IES/STG)$6,713,700 $6,713,700
19. Begin Financing Development (Legal Estimate ‐ NJUS)$2,000 $2,000
20. Apply for/Obtain Permits (HDL Estimate)$20,000 $20,000
21. Draft Final Operational Business Plan (Aurora Consulting Estimate)$15,000 $15,000
$8,003,046
Phase IV Tasks (Construction, Commissioning, Operation and Reporting)
22. Project Management (STG Estimate)$125,000 $125,000
23.1 Foundation Material Procurement (STG Estimate)$1,259,478 $1,259,478
23.2 Mobilization and Demobilization Costs (STG Estimate)$1,028,075 $1,028,075
23.3 Site Access and Foundation Development (STG Estimate)$285,580 $285,580
23.4 Foundation Installation (STG Estimate)$823,544 $823,544
23.5 Tower/Turbine Erection (STG Estimate)$396,639 $396,639
23.6 Transmission/Distribution Lines (NJUS/STG/EPS Estimates)$434,400 $128,200 $562,600
23.7 Power Storage Foundation Pad (STG Estimate)$45,330 $45,330
23.8 Construction Survey/As‐Built Diagrams (STG Estimate)$26,220 $26,220
23.9 Job Site Clean Up (STG Estimate)$15,866 $15,866
24. System Integration (EPS Estimate)$1,608,769 $591,231 $2,200,000
25. SCADA Installation (IES Estimate)$503,380 $503,380
26. System Calibration (IES/EPS Estimate)$220,000 $220,000
27. Final Business Plan Development (Aurora Consulting Estimate)$10,000 $10,000
$ 7,501,710.63
Total Project Costs (Phase I, II, III and IV)$ 13,951,326 $ 595,231 $ 958,200 $ 29,552 $ 15,534,309
Total Phase I and Phase II Costs
Total Phase III Costs
Total Phase IV Costs
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 29 of 51 10/8/2008
4.4.3 Power Purchase/Sale
The power purchase/sale information should include the following:
• Identification of potential power buyer(s)/customer(s)
• Potential power purchase/sales price - at a minimum indicate a price range
• Proposed rate of return from grant-funded project
NJUS generates electricity for sale to the community of Nome. Currently, NJUS sells electricity for
an average price of $.31 per kWh and upon completion of the wind project anticipates an average
price of $.285 per kWh.
Based upon estimated project cashflows, as discussed throughout this proposal, the proposed rate of
return from the grant-funded project is 8.78%. A detailed summary of cash flow assumptions and rate
of return calculations is presented in Section 4.4.6
4.4.4 Cost Worksheet
Complete the cost worksheet form which provides summary information that will be considered in
evaluating the project.
A completed Cost Worksheet is included in Section 7: Additional Documentation and Certification.
Information included on the worksheet was derived from existing system data and the proposed
project design information as well as from the “NJUS Renewable Energy Fund Wind Project
Supporting Documents” also included in Section 7: Additional Documentation and Certification.
4.4.5 Business Plan
Discuss your plan for operating the completed project so that it will be sustainable. Include at a
minimum proposed business structure(s) and concepts that may be considered.
The NJUS Renewable Energy Fund Wind Project will be owned and operated by NJUS, upon
completion of the project, which is a sustainable, well-managed, city-owned utility. As such, it is
anticipated that the on-going operations and maintenance – both short and long term – will be
incorporated into the existing NJUS utility operations and management plans. Below are
highlights of the NJUS management plan:
History and Business Structure
The City of Nome (“City” or “Nome”) is an Alaska municipal corporation, incorporated April 9,
1901. The City of Nome operates under the provisions of Alaska Statutes, Title 29 (“AS 29”),
and the Nome Code of Ordinances (“NCO”) as enacted and amended from time to time by the
Nome Common Council (“Council”). Nome has elected to utilize the Council-Manager form of
government, whereby a city manager is appointed to administer the operations of the city. A
mayor is also elected and performs the responsibilities outlined in AS 29, the NCO, and as
directed or delegated by the Council. The Nome Joint Utility System (“NJUS” or “Utility”) is a
component unit of the City created by NCO Chapter 15. The elected five-member Utility Board
(“Board”) is charged with operation and management of all utilities owned by the City and hiring
a utility manager.
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 30 of 51 10/8/2008
Organizational Chart
Management Team
The general manager is the chief operating and administrative officer whose areas of
responsibility include: manage and operate all public utilities; enforce the ordinances and
regulations pertaining to the policies and practices of the utility; manage public utility employees,
prepare and administer annual operating and capital improvement program budgets; prepare and
submit reports on finances and administrative activities; strategic planning; grant writing and
administration; operational reporting to elected Board and Council; assume such other authority
and perform such other duties as may be lawfully prescribed by the Board.
Additionally, as outlined above, the general manager will be assisted by the chief financial
officer, superintendent of field operations, power plant foreman and line foreman.
Utility Accounting
NJUS is operated from accounting funds separate from the general fund of the City of Nome.
Separate books, records and accounts are maintained to reflect the financial condition of the
utilities, their income and expenses and the status of their bond redemption funds. None of the
income, money or property of the Utility is placed in the general fund of the City or is used for
the benefit of anything other than NJUS, unless NJUS is compensated or due value is received in
return. The NJUS Board provides for an annual independent audit of the accounts and financial
transactions of the Utility, performed by an independent certified public accountant. For the past
20+ years, the NJUS’ independent auditors have issued “unqualified” (clean) opinions on the
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 31 of 51 10/8/2008
utility’s financial records. Copies of the audit are available upon request.
Accounting functions of the Utility are performed under the direction of a chief financial officer,
appointed by the general manager, and a support staff of accounting technicians. The Utility is a
government enterprise fund. The Utility maintains separate accounts for electrical production and
distribution, water and sewer operations and construction projects, which are funded by general
fund appropriations, grant assistance from state and federal agencies and other contributors. The
Utility utilizes an integrated accounting software suite “Insight” for general accounting and
“Connect” for consumer accounting/billing, developed by Professional Computer Systems (PCS),
Denison, IA, and an automated electric meter reading program, referred to as “the Turtle system”,
developed by Hunt Technologies, Pequot Lakes, MN.
The Utility currently uses the following “Insight” accounting modules: General Ledger, Payroll,
Accounts Payable, Fixed Assets, Cash Management and Project Costing. “Connect” software
drives customer management and Accounts Receivable, and interfaces directly with “Insight”.
As noted previously, the Utility maintains separate cost centers within its accounting records for:
Power Generation, Power Distribution, Water & Sewer (with further segregation to water
distribution and wastewater collection), Consumer Accounting and General & Administrative
expenses and construction activities segregated by project. Within the Project Costing module,
costs are segregated by components such as labor, materials and supplies, services, equipment
rental, engineering, inspection, travel, etc., and allow for summary or detailed transaction listing,
as may be required for internal or external (grant) reporting.
Staffing Requirements
It is anticipated that NJUS will require an additional power operator upon completion of the wind
farm, which has been included in the anticipated cost information provided above.
Staff Training
The State of Alaska, Division of Labor and Workforce Development has expressed interest in
working with NJUS/STG, on the NJUS Renewable Energy Fund Wind Project, to fund OJT-type
training for the NJUS operators on the wind turbines, system controls and other project
components. Currently, project members plan to bring representatives of the chosen turbine
supplier to Nome to provide O&M training for the Nome Joint Utility System and UVEC
operators. Training plans will be finalized closer to the startup of the project.
4.4.6 Analysis and Recommendations
Provide information about the economic analysis and the proposed project. Discuss your
recommendation for additional project development work.
As part of the Phase I and II activities of this project, an initial economic analysis and feasibility
was conducted for the proposed project. Based upon this analysis, the project Benefit/Cost ratio
is estimated to be 3.14 and the Project Payback is expected to be 10.85 years. Based on a discount
rate of 4%, which corresponds to the effective interest rate for borrowing by municipal electric
systems such as NJUS, the project has a NPV of $7,994,612. A detailed model of project cash
flows can be provided upon request and a summary of this analysis is included below:
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 32 of 51 10/8/2008
Project Returns NPV Cumulative Benefit (w/ O&M)Total Project Costs
Discount Rate 3% $10,576,905 48,849,138$ 15,534,309$
4% $7,994,612
5% $5,790,391 Benefit/Cost Ratio Total Grant Request
6% $3,902,946 3.14 13,951,326$
7% $2,281,834
8% $885,408 Payback (Years)Total Cash Match
10.85 595,231$
Project IRR 8.72%
Cost/Installed KW 4,849$ Phase I & II Contributions
29,552$
The next step for the project is to proceed with Phase III activities upon receipt of grant funding,
followed quickly by Phase IV activities. No additional development recommendations have been
formulated at this time – additional recommendations will be formulated upon conclusion of
Phase III and IV activities.
The major economic assumptions utilized in our economic forecasting are included on the
following page.
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 33 of 51 10/8/2008
Assumptions
Turbine Cost V 6,713,700$
Permitting Costs ($)20,000$
Geotechnical Engineering Costs ($)74,000$
Structural Engineering Costs ($)19,000$
System Integration Costs ($)3,044,172$
Construction Costs ($)4,190,707$
Professional Services/Project Management/Other ($)484,978$
Total Contractual Costs 14,546,557$
In ‐Kind (non‐cash) Contributions
Conceptual Design Contributions (Phase I & II Costs)29,552$
Land Contribution (Certified Value)830,000$
Labor/Equipment Contributions 128,200$
Total In‐Kind Contributions 987,752$
Include In‐Kind Contributions in Cash Flows Y
Total Project Match Contribution (% of Total Project Costs)10%
Project Match Contribution (In‐Kind Labor/Equipment ‐Line Work)128,200$
Include Project Match Labor in Cash Flows Y
Include Estimated Energy Sales in Cash Flows N
Estimates Sale Price of Wind Energy ($/kWh)0.285$
Estimated Project Life (Years ‐ Based on DOE/Industry Data)25
Installed Turbines 5
Fixed Annual Project O/M Costs (DOE/Industry ‐ % of Total Project Cost)3.00%
Variable Annual Project O/M Costs (DOE/Industry ‐ $/Generated kWh)0.00975$
Estimated Diesel Cost for Year 1 ‐ (NJUS Data ‐ $/gal)3.72$
Estimated Annual Diesel Cost Inflation (DOE %)2.12%
Estimated Value of Green Tag Sales ($/kWh ‐ Based on AK sales data)0.01$
Additional Annual "Ecotourists" (people)4
Average Value of Tourist (State of Alaska ‐ $)1,300$
Estimated Annual Value of Health Benefits ($)‐$
Generated through reduced diesel usage
Estimated Annual Value of Reduced Diesel Handling ($)154,913$
NJUS currently leases additional per gallon diesel storage space @:0.36$
Expected Annual Gross Energy Generation (GEC Est. ‐ Project ‐ MWH)8,963
Estimated Wind Project Loss Factor (GEC Estimate ‐ %)24%
Estimated Annual Net Generation (GEC Estimate ‐ Total Project ‐ MWH)6,812
Estimated Efficiency of Existing Diesel Gen‐Sets (NJUS Data ‐ kWh/Gal)15.83
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 34 of 51 10/8/2008
SECTION 5– PROJECT BENEFIT
Explain the economic and public benefits of your project. Include direct cost savings,
and how the people of Alaska will benefit from the project.
The benefits information should include the following:
• Potential annual fuel displacement (gal and $) over the lifetime of the evaluated
renewable energy project
• Anticipated annual revenue (based on i.e. a Proposed Power Purchase Agreement price,
RCA tariff, or avoided cost of ownership)
• Potential additional annual incentives (i.e. tax credits)
• Potential additional annual revenue streams (i.e. green tag sales or other renewable
energy subsidies or programs that might be available)
• Discuss the non-economic public benefits to Alaskans over the lifetime of the project
Based upon assumptions presented throughout this proposal, the potential annual displacement of
diesel fuel is expected to 430,195 gallons per year over the lifetime of the project. At an assumed
starting fuel price of $3.72 per gallon without considering expected annual energy inflation, the
annual dollar savings is estimated to be $1,600,325.
Based upon the anticipated Regulatory Commission of Alaska tariff of $.285 per kWh, it is
anticipated that NJUS will generate $1,941,385 from wind generated electricity annually. Green
tag sales also are assumed to be project revenue streams. Based upon recent Alaskan green tag
sales involving Nome projects, our economic analysis assumes that we would also be able to
negotiate a similar purchase price with the wind project proposed in this application. We have
estimated that NJUS would be able to sell green tags generated through the project at $.01 per
kWh. Based on the project’s expected production, annual green tag sales have been estimated at
$89,630.
Two additional project benefits include potential community-wide tourism revenue and reduced
diesel-fuel storage costs for NJUS. The project economic analysis assumes that four individuals
will be motivated, at least partially, to travel to Nome to learn more about the wind project and to
visit the wind farm each year. Based upon economic research by the State of Alaska, Department
of Commerce, Community and Economic Development (AVSP 2006), the average visitor to the
Nome area provides an economic benefit of $1,300 to the visited community; therefore,
additional community benefits would be $5,200 per year. Currently, NJUS leases bulk fuel
storage space for $.36 per gallon of fuel. Therefore, based upon reduced diesel fuel consumption,
NJUS should save an average of $154,913 per year.
The utilization of wind power technologies in Nome is also expected to provide benefits that are
less quantifiable or non-financial in nature. Through the implementation of this project and the
resulting volume of displaced fuel, NJUS will significantly reduce the amount of greenhouse
gasses emitted through the use of diesel electricity generation. While this environmental benefit
can be quantified through emissions calculations and valued through the expected sale of green
tags, the project’s complete contribution towards global climate change mitigation efforts is
difficult to precisely determine.
The completed project is also expected to reduce volatility in electric rates across the community
of Nome and provide more stabilized prices for those who purchase energy from NJUS.
Additionally, it is also possible that Nome could experience an increase in local employment due
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 35 of 51 10/8/2008
to a decrease in the amount of funds that previously have been leaving the community to cover
rapidly increasing fuel prices expenditures. Finally, as a result of this decrease in fuel purchases,
the State of Alaska’s PCE program will also be able to free up funds to spend elsewhere in the
state due to the reduced need of PCE support of the Nome community.
SECTION 6 – GRANT BUDGET
Tell us how much your total project costs. Include any investments to date and funding sources,
how much is requested in grant funds, and additional investments you will make as an
applicant.
Include an estimate of budget costs by tasks using the form - GrantBudget.xls
The total project costs of the NJUS Renewable Energy Fund Wind Project is estimated to be
$15,534,309, inclusive of Phases I to IV. As discussed previously, this project has advanced
through Phases I and II and is ready for Phases III and IV activities.
Much of the cost of Phase I and II were borne by third-party researchers, however, project team
members have contributed $29,552 in project conceptual design and initial feasibility study. The
total grant request for the NJUS Renewable Energy Fund Wind Project is $13,951,326 based
upon the following:
Total Project Costs $15,534,309
Less: Phase I and II Contributed Costs ($ 29,552)
Total Phase III and IV Costs $15,504,757
Less: Additional Investments ($ 1,553,431)
Total Grant Request $13,951,326
The additional investment of $1,553,431 is inclusive of $830,000 of land contributed by the City
of Nome, $128,200 in labor and equipment contributed by the NJUS for line transmission
construction, and $595,231 in cash contributed by the NJUS.
A completed Grant Budget is attached in included in Section 7: Additional Documentation and
Certification.
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 36 of 51 10/8/2008
SECTION 7 – ADDITIONAL DOCUMENTATION AND CERTIFICATION
SUBMIT THE FOLLOWING DOCUMENTS WITH YOUR APPLICATION:
A. Resumes of Applicant’s Project Manager, key staff, partners, consultants, and
suppliers per application form Section 3.1 and 3.4
B. Cost Worksheet per application form Section 4.4.4
C. Grant Budget Form per application form Section 6.
D. An electronic version of the entire application per RFA Section 1.6
E. Governing Body Resolution per RFA Section 1.4
Enclose a copy of the resolution or other formal action taken by the applicant’s
governing body or management that:
- authorizes this application for project funding at the match amounts indicated in
the application
- authorizes the individual named as point of contact to represent the applicant for
purposes of this application
- states the applicant is in compliance with all federal state, and local, laws
including existing credit and federal tax obligations.
F. CERTIFICATION
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 37 of 51 10/8/2008
LIST OF ADDITIONAL DOCUMENTATION AND CERTIFICATION:
A. Resumes of Applicant’s Project Manager, key staff, partners, consultants and suppliers
1. NJUS Management Team Resumes
2. Project Manager – STG Inc. – Resumes
3. Contractor/Consultant Resumes
i. Intelligent Energy Systems LLC
ii. DNV Global Energy Concepts Inc.
iii. Electrical Power Systems
iv. Duane Miller Associates LLC
v. Hattenburg, Dilley & Linnell LLC
vi. BBFM Engineers
vii. Aurora Consulting
B. Cost Worksheet
C. Grant Budget Form
D. Electric Version of Application (Attached on CD Rom)
E. Governing Body Resolution
1. NJUS Resolution
2. City of Nome Resolution
3. Match Documentation (NJUS/City of Nome)
4. Partners’ Match Documentation
F. “NJUS Renewable Energy Fund Wind Project Supporting Documents”
1. GEC Report: “Preliminary Assessment for Nome Wind Energy Project”
2. “The Nome Region Energy Assessment, DOE/NETL 2—7-1284”
G. Project Correspondence & Letters of Support
1. Documentation of Land Value
2. Norton Sound Health Corporation Board Resolution
3. Norton Sound Economic Development Corporation Correspondence
4. Letter of Support from Adjacent Land Owner
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 38 of 51 10/8/2008
Resumes of Applicant’s
Project Manager, Key Staff,
Partners, Consultants and
Suppliers
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 39 of 51 10/8/2008
NJUS Management Team
Resumes
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 40 of 51 10/8/2008
Project Manager Resumes
STATEMENT OF QUALIFICATIONS
11820 S. Gambell Street • Anchorage, Alaska 99515 • Phone: (907) 644‐4664 • Fax: (907) 644‐4666
info.stginc@gci.net • www.stginc.cc
Over the past fifteen years, STG, In remier construction services and
management company. Dealing mainly in rural Alaska, the company has played a major role in high
profile projects such as wind energy installations, communication tower installations, and community
bulk fuel and diesel generation upgrades, to name a few. STG specializes in remote project logistics, pile
foundation installations, tower erections, and construction management. STG takes pride in its wealth of
experience, gained from years of work throughout “bush” Alaska, and through its ability to deal with the
diverse and challenging logistics and conditions which it encounters on nearly every project it
undertakes in remote locations.
Company Overview
In 1996, St. George Construction was incorporated as STG, Inc.
Since incorporation, STG has become the preferred construction
management company for both the Alaska Energy Authority (AEA)
and the Alaska Village Electric Cooperative (AVEC). Many of the
projects executed by these two entities are managed and constructed
by STG.
STG’s core competencies include bulk fuel systems, power plant
construction (both modular and steel-framed), wind farms, and pile
foundations (driven piles, post tension rock anchors, helical anchor
systems, freeze back, and active refrigerated piles). STG is the
prevalent pile foundation contractor for Interior and Western Alaska.
Additionally, STG has expanded to become United Utilities’
preferred contractor for its “Delta Net Project”, which involves the
installation of communication towers and related equipment
throughout the Yukon Kuskokwim Delta. STG has achieved this
preferred status by demonstrating competitive rates and the ability to
perform in remote locations with extreme logistical challenges.
Qualifications
The STG team has developed and maintained the capacity to manage projects through a set of key
deliverables to ensure appropriate management of jobs across the complete project cycle including:
• Provision of a quality project at a fair and reasonable price
• Timely delivery within budget
• Safe and professional performance on all work
• Positive relationships with clients to ensure that project deliverables are met
• New modern equipment that results in high productivity
• State of Alaska Professional Land Surveyor (Reg. 10192) on staff with modern Topcon GPS
Control through Detailed Project Planning
STG focuses pre-construction efforts on planning and preparation. A project team is identified which
includes management, administrative, and field supervision personnel. The team establishes budgets,
c. has grown and developed into a p
production targets, a master construction schedule, and detailed work plan for each project.
The planning process involves key supervisory
personnel as all aspects of the project are analyzed
with particular attention to logistics, labor and
equipment resource needs, along with specific
material requirements. This results in a clear
understanding of the goals of the client, the
ontractual requirements, scope of work, and
entification of potential obstacles that may impact
ion of the job.
ough to the administrative level
, accurate documentation and reporting, and on to the field level where clear goals of
roduction and quality are reinforced through the superintendent’s and foremen’s daily huddles and
ost Containment
anagement decisions. The project manager and field
ork together through this reporting
y potential problems and direct resources
rform “crisis management” while providing clients with
TG employees
’s civic responsibility to local
c
id
the successful complet
The project-planning phase also establishes key
systems which help assure quality throughout the
project. This begins at the management level with a
commitment to providing a quality project to the client and carries thr
with timely
p
schedule reviews.
C
STG maintains budgets for all labor, material, and
equipment for each project allowing managers to
effectively manage project costs. Expense categories are
tracked and updated weekly by the project managers and
this information is then communicated to the field
pervision level for use in making timely, proactive su
m
superintendent w
system to identif
as required to address issues before they impact the work.
This proactive approach prevents STG from having to
pe
on-budget, on-time, turnkey deliveries of completed projects
built to engineered specifications.
STG maintains a philosophy to deliver the highest level of quality within the industry. S
also realize the company’s commitment to its clients along with STG
communities. The work that STG performs is a reflection of this commitment.
Construction Management and Project Supervision Experience
STG has built a reputation of professionalism an
products within a set schedule and defined budget.
construction services and management contracts wit
• Alaska Village Electric Cooperative (A
• Alaska Energy Authority (AEA)
• United Utilities Inc. (Recently acquire
STG has built a wealth of knowledge
d thoroughness by delivering the highest quality
As a result, STG has been awarded and maintains
h the following clients:
VEC)
d by GCI, Inc.)
and experience for
lanning, execution, and completion of projects across
ral Alaska. Over the years, STG has also enjoyed the
ay of
he company prides itself in its ability to professionally
eal with all the different entities that are related to a
roject. In this regard, STG maintains a close working relationship with AVEC’s engineering
presentatives, a so id relationship with the AVEC management staff, along with strong connections to
rs and vendors across the state of Alaska.
e-of-the-art dump trucks, loaders, excavators, pile
ural construction projects. During the
efficiently supported logistically from two
cation shop located in Anchorage, AK and its
ons, company construction crews are fully
needs that may arise during the course of the
p
ru
opportunity to successfully implement a large arr
projects specifically for AVEC including bulk fuel
upgrades, diesel power, wind generation, and energy
distribution systems. STG can also coordinate all project
logistics from procurement, to transportation, to the final
project demobilization.
T
d
p
re l
various sub-contracto
STG operates a modern fleet of fourteen cranes, stat
drivers, and other equipment needed to support full scale r
construction phase of STG projects, remote field crews are
STG offices: the company’s headquarters and fabri
staging yard located in Bethel, AK. From these locati
supported in the field for parts, groceries, and any other
project.
STG Projects
Selawik Power Plant, Tank Farm, and Wind Turbine Installation
Client: AVEC
Year Completed: 2004
The Selawik Bulk Fuel Upgrade Project exemplifies STG’s diverse capabilities. STG was highly
he tank farm and power plant. The company executed the pile
site, erected four 65kW wind turbines,
of pipelines.
n Kasigluk, STG once again demonstrated its abilities to execute
omplex, multi-faceted projects. This project entailed transferring
primary power generation from Nunapitchuk to Akula Heights while
maintaining power generation to these two villages and also m intaining
power to Old Kasigluk. As part of this project, STG constructed a new
bulk fuel retail facility for the communities of Akula Heights and Old
Kasigluk along with a new bulk fuel storage facility, totaling over
600,000 gallons of storage capacity in all. This project also included the
construction of a power distribution system to the three aforem
villages, the installation of a new diesel generation plant, the erection of
three 100 kW wind turbines, the installation of a heat recovery system,
upgrades to the school districts bulk fuel facilities, and the installation of
a standby generator in Nunapitchuk.
involved with the planning and design of t
foundation work, fabricated ten 50,000 gallon storage tanks on-
and tied the completed system together with a complex network
Nunapitchuk-Kasigluk Bulk Fuel Upgrade, Power Plant, and Wind Turbine Installation
Client: AVEC
Year Completed: 2006
I
c
a
entioned
Toksook Bay Power Plant, Wind Generation, and Interties
and Nightmute are located in Western Alaska on Nelson Island, an ideal
installation of 23 miles of
ower lines.
STG orchestrated schedules, equipment, materials, field work and logistics to successfully bring this
project to completion. Due to the impassible summer tundra conditions, all the intertie work took place
in the winter season during sub-zero temperatures.
many different levels of scope.
iversity in rural construction and
e Alaska Energy Authority
the set-up, installation, and
ties along the middle
g the winter
Client: AVEC
d: 2008 Year Complete
oksook Bay, Tununak,T
location for wind generation. STG helped deliver a wind/diesel integrated power project for these
communities. With three Northwind 100kW wind turbines and a new power plant complete with switch
gear and heat recovery module in Toksook Bay, power can now be produced from either diesel fuel, or
the natural powers of the wind. In order to capture the greatest value for all island residents, an intertie
etwork was established, which connected the three communities through the n
p
Additional STG Projects
STG has completed numerous projects for AVEC throughout the state on
The company would also like to highlight a few other examples of its d
management for other clients.
STG has managed and constructed over a dozen bulk fuel upgrades for th
across the western half of Alaska. The most notable of these projects was
commissioning of eight modular power plants in eight unique communi
Kuskokwim River. The units were built and prepared in STG’s Anchorage yard durin
months, then delivered and installed on each site during the short summer season.
The company has also gained valuable experience dealing with tower erection and foundation design.
ontract with UUI, STG has built foundations for, and has erected, over thirty
hroughout western Alaska. This project, known as the Delta-Net Project, has
nked dozens of communities for tele-medicine and broadband communication. Two of the most
hich
unity of St. Paul.
Under its term c
communication towers t
li
notable towers are the 305-foot tower in Eek, and the 60-foot tower on top of Marshall Mountain w
also required construction of a five-mile access road from the village of Marshall.
STG has grown into one of the most experienced integrators of alternative energy systems within the
state of Alaska. In addition to the previously referenced projects, this experience is documented through
STG’s work to erect and install two Vestas 225 kW wind turbines for TDX Power on the remote Bering
Sea island comm
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 41 of 51 10/8/2008
Contractor/Consultant
Resumes
Company Overview
Global Energy Concepts, LLC (GEC) is a
multi-discipline engineering and technology
consulting firm providing services to clients
involved in the energy industry. Recognized as
leaders in the wind energy industry, the firm
specializes in the analysis, design, testing, and
management of wind energy systems and
projects. Our experience includes both utility-
scale and small-scale applications of wind
energy technologies. GEC combines technical
expertise, managerial capabilities, and common-
sense financial and business knowledge to
provide comprehensive consulting services to
assist our clients in meeting their objectives.
The services offered by GEC encompass a wide
range of assignments including independent
engineer and due diligence services; project
feasibility and economic assessments; wind
resource monitoring; power curve, noise, power
quality, and loads measurement and
documentation; wind flow and wake modeling;
energy projections, site optimization, and
visualization; component and turbine
specification, design, analysis, test and
certification; education and outreach materials;
international training and development support;
litigation support and dispute resolution; project
performance evaluation and reporting; and
database management and data analysis
software. Projects are managed by experienced
personnel who ensure all work products are of
Page 1 of 3GEC - Company Overview
9/30/2008http://www.globalenergyconcepts.com/overview.htm
the highest quality and are produced on time and
within budget.
CLIENTS
GEC provides consulting services to a broad
spectrum of clients including all sectors of the
domestic and international energy industry. Our
clients include electric utilities, investors, banks,
wind turbine owners, insurance companies,
equipment manufacturers, developers, law firms,
the U.S. Department of Energy, the World Bank,
the Electric Power Research Institute, the
National Renewable Energy Laboratory, the U.S.
Agency for International Development, and other
public institutions both in the United States and
abroad.
STAFF AND COMPANY RESOURCES
GEC personnel have been providing services to
the wind industry for over 20 years. Staff
members are internationally recognized for their
work, are on industry advisory committees, have
written numerous reports and papers, and
frequently testify and lecture before industry
audiences.
The staff is supported by extensive library and
computer facilities including current software and
specialized wind energy analysis tools. We
maintain extensive files on equipment suppliers,
specifications, and turbine performance. Our
inventory of test equipment, which includes data
loggers, sensors, and towers, is available for
lease to our clients.
We also maintain affiliations with technical,
regulatory, economic, and environmental experts
from leading industry and academic positions.
The frequent use of this expertise to support
project implementation and enhance staff
qualifications provides for additional flexibility
Page 2 of 3GEC - Company Overview
9/30/2008http://www.globalenergyconcepts.com/overview.htm
Electric Power
Systems, Inc.
Statement of
Qualifications for
Engineering, Design,
Testing, Maintenance &
Construction
Statement of Qualifications
Electric Power Systems, Inc. (EPS) was incorporated in 1996 and was founded by David
Burlingame and Daniel Rogers. Their prior experience included working as engineers and
managers for a variety of utility and manufacturing interests focusing on power transmission,
distribution, generation, and control. EPS has historically focused on providing substation,
generation, controls, protection, system planning and analysis and distribution engineering for
utility, industrial, and governmental clients. EPS holds a number of long term and alliance type
contracts and relationships. Most of EPS’ clients are based in Alaska, and are long-term,
mature clients, which require little or no proposal effort to obtain work. For the past five years,
EPS has been successfully expanding into the Pacific Northwest and South Pacific markets.
KEY PERSONNEL
The following are brief overviews of ESG’s key personnel’s qualifications and experience:
DAVID BURLINGAME, PE, PRINCIPAL
David Burlingame has over 25 years of experience in power system operation, engineering and
administration. His experience includes a full range of services, from planning studies, design,
construction, and start-up/commissioning to periodic testing and maintenance. His specific
experience includes the following:
Bradley Lake Governor Project for Homer Electric Association, Homer, Alaska
Tyee Lake Governor Project, Four Dam Power Pool, Anchorage, Alaska
Unalaska Power Plant, City of Unalaska, Unalaska, Alaska
System Reliability Review, Guam Power Authority, Agana, Guam
System Stability and Reliability Studies, Kauai Island Utility Cooperative, Lihue, Hawaii
Marathon Substation Final Design, Startup and Commissioning, Homer Electric Association,
Inc., Kenai, Alaska
Seldovia and Port Graham Generation Plants, Homer Electric Association, Homer, Alaska
Nikiski Co-Gen Corrective Action, Alaska Electric Generation and Transmission
Cooperative, Homer, Alaska
RW Retherford Substation, Chugach Electric Association, Inc., Anchorage, Alaska
Postmark Substation, Chugach Electric Association, Anchorage, Alaska
Diamond Ridge Substation, Homer Electric Association, Homer, Alaska
Heidenview Station Design, Copper Valley Electric Association, Inc., Valdez, Alaska
Kukuulia Substation Design, Kauai Island Utility Cooperative, Kauai, Hawaii
ITSS switchgear design, Chugach Electric Association, Anchorage, Alaska
Heidenview Substation Design, Copper Valley Electric Association, Valdez, Alaska
BP Substation Design, Homer Electric Association, Kenai, Alaska
DANIEL C. ROGERS, JR., PE, PRINCIPAL
Daniel Rogers has over 20 years of experience in electrical power system engineering. He
holds a Masters and Bachelors degree in Electrical Engineering and a Bachelors degree in
Physics. His experience includes electrical design, project management and construction
management of electrical system projects throughout Alaska. His specific experience includes
the following:
Snake River Power Plant, Nome Joint Utilities, Nome, Alaska
SCADA System, City of Soldotna, Soldotna, Alaska
Kodiak Power Plant Generator Replacement, Kodiak Electric Association, Kodiak, Alaska
Statement of Qualifications
Facilities relocation in support of Water/Wastewater Upgrades, Nome Joint Utility Systems,
Nome Alaska
Power Creek Hydro Plant Design, Startup, and Commissioning, Cordova Electric
Cooperative, Cordova, Alaska
Pump Installation – Nome storage tank, Nome Joint Utility System, Nome, Alaska
PRV Design, Various Contractors/Developers for AWWU, Anchorage, Alaska
Orca Diesel Plant SCADA/Controls Upgrades, Cordova Electric Cooperative, Cordova,
Alaska
Elfin Cove Diesel Plant Control Systems Upgrade, Elfin Cove, Elfin Cove, Alaska
Humpback Creek Hydro Plant Design, Startup, and Commissioning, Cordova Electric
Cooperative, Cordova, Alaska
DR. JAMES W. COTE, P.E. PRINCIPAL
Dr. Cote has been involved in the planning and studies of electric power systems for over 25
years. His special area of expertise is analyzing the performance and planning requirements of
islanded power systems. In addition to studies involving the electrical grid of the continental US,
Dr. Cote has participated in the analysis, review and planning of islanded power systems from 5
MW up to the 1000 MW. This experience allows Dr. Cote to foresee many problems in isolted
power systems that are not prevalent in larger networks. His specific experience includes the
following:
Railbelt Operating Studies – Alaska Intertie Operating Committee
Wind Turbine Impact Study - Hawaiian Electric Light Company
Aero-derivative turbine modeling – Kauai Island Utility Cooperative
Bradley Lake Transient Stability Investigation – Chugach Electric Association
Reliability Assessment – Guam Power Authority
Static Var Compensation Study – Alaska Intertie Operating Committee
Loadshedding Study – Homer Electric Association
Bradley Governor Design & Operating Studies – Homer Electric Association
LM-2500 Impact Studies – Kauai Island Utility Cooperative
Transmission Long Range Plan – Chugach Electric Association
PROJECT EXPERIENCE
The following is an overview of EPS’s recent project experience:
PROTECTIVE RELAYING AND AUTOMATION UPGRADES, CHUGACH ELECTRIC ASSOCIATION, INC.,
ANCHORAGE, ALASKA
The Chugach Electric Association’s protective relaying and
automation upgrades consisted of both the design and the
subsequent project construction located at Chugach’s Beluga and
Douglas Substations. The projects included the design and
installation of protective relaying and automation on Chugach’s
critical generation station and transmission system. All projects
were completed in energized facilities without an outage. The
projects included relaying upgrades on two 28 MW gas-fired
turbines and station relaying on a 415 MW generation plant. The
design was performed by Electric Power Systems (EPS) and the
installation was performed by Electric Power Constructors (EPC).
Statement of Qualifications
WOODINVILLE SUBSTATION, BP OLYMPIC PIPELINE, WOODINVILLE, WASHINGTON
EPS completed the design and construction inspection for the new Portage Substation along
the Turnagain Arm south of Anchorage. The substation consisted of four 4.16 kV feeders in
metal-clad switchgear. EPS was responsible for the design of the substation civil work, bus
layout, grounding and lighting. EPS was responsible for the switchgear design and
specifications, station layout and protective relaying settings, and implementation. EPS
completed the quality control inspection, testing and commission for the substation construction.
Project cost: $0.500 million.
KUKUULIA SUBSTATION, KAUAI ISLAND UTILITY COOPERATIVE, KAUAI, HAWAII
EPS completed the civil, structural and electrical design for the 69 kV/ 12.47 kV Kukuuulia
Substation. Project included four 69 kV breakers, two 20 MVA transformers and provisions for
twelve 12.47 kV feeder breakers, control building, communication and relaying control panels.
EPS provided the structure design, electrical service, grounding, protective relaying and controls
design. Project cost: $2.500 million.
AIRAI SUBSTATION, PALAU PUBLIC UTILITIES CORPORATION, KOROR, PALAU
EPS completed the civil, structural and electrical design for the 34.5 kV / 12.47 kV Airai
Substation. Project included concrete block control building, relaying and control panels, four
12.47 kV breakers, installation of controls and modifications for one 34.5 kV breaker and three
34.5 kV motor-operated switches and SCADA control and monitoring for the station. EPS
provided the structure design, electrical service, grounding, protective relaying and controls
design. EPS completed the installation and commissioning. Project cost: $1.200 million.
HEIDENVIEW STATION DESIGN, COPPER VALLEY ELECTRIC ASSOCIATION, INC., VALDEZ, AK
This project consisted of the complete design of a new 138/24.9 kV station, including one line
development, DC system design, controls and protection specification, equipment specification,
bid evaluation and award, commissioning and startup assistance. In addition, EPS constructed
the installed the controls into the station control house at our Anchorage facility, and shipped the
completed control structure to Valdez for installation on the pad.
INTERNATIONAL 35 KV METALCLAD SWITCHGEAR DESIGN, CHUGACH ELECTRIC ASSOCIATION,
INC., ANCHORAGE, AK
The project included development of design criteria, one
lines, three lines, DC schematics and physical drawings for
a common aisle 35 kV metalclad switchgear for Chugach’s
main bulk substation. Implicit in the design of the
switchgear was the limited space at the existing facility,
and the need to minimize outage times during constru
ction. The design included SEL-351, 287, 311C and 321
relays. The design included an evaluation of alternatives
and recommendations for service and replacement of the
existing station.
HUMPBACK CREEK POWER PLANT FIRE REBUILD, CORDOVA ELECTRIC COOPERATIVE,
CORDOVA, ALASKA
Humpback Creek is a remote plant connected electrically to the Cordova Electric Cooperative
system. The plant has over 100’ of head, and three units, with a plant capacity of over 1 MW.
The plant had a fire in late 2005, with significant damage resulting from the heat, flames, and
smoke. Engineered Solutions Group, Inc. (ESG) was hired by the owner to design, procure,
and reconstruct the plant. The project scope included electrical design and construction,
Statement of Qualifications
general building construction, hydraulic system design and construction, and
control/communications design and construction. ESG personnel performed all of the work on
the project. The design was completed and a conformed set of drawings provided to the owner.
The construction was bid and performed under a separate construction contract based on the
conformed set of drawings. The project will be completed on time and on budget. The owner is
pleased with the work, and ESG is in negotiations for additional work at the forebay with the
owner following the completion of the power plant rebuild. Project cost: $1.5 million.
MAIN GENERATOR RELAY UPGRADES, ALYESKA PIPELINE SERVICE COMPANY, VALDEZ,
ALASKA
In order to more reliably operate the power production facility at the Valdez Marine Facility,
Alyeska Pipeline Service Company (APSC) decided to upgrade and install new microprocessor-
based protective relays in the three main turbine generators at the Valdez Marine Terminal
power plant. Electric Power Systems (EPS) acted as the design resource and Electric Power
Constructors (EPC) as the contractor to perform the installation. EPS performed the overall
project and construction management, as well as all of the electrical design. EPC personnel
performed the installation tasks working with Alyeska personnel. The relays have been in
operation since 2003 without any outages associated with the installation. The work was
completed on time and on budget. Project cost: $120,000.
NIKISKI POWER PLANT, ALASKA ELECTRIC GENERATION AND TRANSMISSION COOPERATIVE,
NIKISKI, ALASKA
The Nikiski Power Plant project consisted of
feasibility studies, conceptual design, final
design, construction and testing services and
final acceptance testing associated with a 48
MW gas-turbine facility located on Alaska’s
Kenai Peninsula. The project included the
design and installation of protective relaying and
SCADA systems, the design and installation of
auxiliary power systems and the design and
installation of low and medium voltage power
systems. Electric Power Systems (EPS)
designed and installed medium voltage switchgear in the project substation, designed and
installed substation transformer electrical and fire protection systems. EPS was responsible for
final commissioning tests and procedures on the SCADA, protection and station control systems
and the protection improvements on six 3.5 MW gas-fired turbines and substations within the
Agrium Nitrogen facility.
LIFELINE SWITCHGEAR RELAY/CT UPGRADES, ALYESKA PIPELINE SERVICE COMPANY, VALDEZ,
ALASKA
In order to more reliably operate the power distribution facility at the Valdez Marine Facility,
Alyeska Pipeline Service Company (APSC) decided to upgrade and install new microprocessor-
based protective relays in the lifeline generator switchgear at the Valdez Marine Terminal. In
addition, CT’s were installed to replace outdated linear couplers on the switchgear. Electric
Power Systems (EPS) acted as the design resource and Electric Power Constructors (EPC)
performed the installation as the contractor. EPS performed the overall project management, as
well as all of the electrical design. EPC personnel performed the installation tasks. Some
coordination issues were addressed onsite by the crew and Alyeska personnel, allowing for
flexible operation of the terminal and no change orders to the project. The relays have been in
Statement of Qualifications
operation since 2005 without any outages associated with the installation. The work was
completed on time and on budget. Project cost: $100,000.
SNAKE RIVER POWER PLANT, NOME JOINT UTILITY SYSTEM, NOME, ALASKA
The Snake River Power Plant project consisted of
feasibility studies, site selection, conceptual design, final
design, construction, construction management and
testing services and final acceptance testing for the 30 MW
diesel power plant located in Nome, Alaska. The project
consists of the design and installation of a 30 MW plant (12
MW installed) to serve the community of Nome, Alaska.
The project includes site design, building design (25,000
sq. ft. facility), utility interconnections, SCADA/automation
design, protective relaying design, switchgear design,
construction and installation, coordination studies, fuel tank
and fuel delivery systems design and installation and project commissioning and testing.
The project is located at a remote site on the Seward Peninsula, in Nome Alaska. Nome has no
road connection to the rest of Alaska, and is served only during the summer by barge. The
plant, when commissioned, will serve as the primary
power source for the communities, and the
surrounding area.
During the course of the project, where the Board did
not receive bids that were responsive, either from a
cost or capabilities perspective, they have turned to
the ESG Companies to assist in the construction.
Subcontract portions that have been preformed by
ESG Companies, include the electrical rough in
(subgrade conduit), medium voltage switchgear
installation, power transformer installation, all medium
voltage plant work (480V through 15kV class equipment), PLC control/ SCADA installation and
electrical system startup and commissioning.
Final startup will be completed in 2007. Project cost: $28 million.
SCADA SYSTEM ENGINEERING, PROCUREMENT AND CONSTRUCTION, CITY OF SOLDOTNA,
SOLDOTNA, ALASKA
The City of Soldotna desired to upgrade their existing control system, which was limited due to
age, technology employed, and the number of sites at which it was deployed. EPS teamed with
the prime contractor AirTek of Soldotna to provide the City a new SCADA system. EPS
performed all of the design engineering for the electrical installation and the UL 508A control
panels. In addition, EPS provided the materials for the control system, including a Wonderware
HMI (human-machine interface), four GE 90-30 PLC’s for the well sites and reservoir, and the
920 MHz radio system to allow the remote sites to communicate with the HMI at the treatment
plant. EPS programmed the PLC’s and HMI, assisted AirTek with construction-related
engineering, and provided final startup, commissioning, and training for the Owner. EPS staff
worked with the electrical contractor as a subcontractor, while keeping the goals of the owner in
mind. The project was completed on time and budget, with only minor changes required from
the original design. EPS has maintained a working relationship with both the owner and the
contractor in the ensuing years. In fact, EPS continues to work for the City upgrading and
adding facilities to their SCADA system. Since the completion of this project, EPS has added
Statement of Qualifications
two additional wells and one reservoir, and has discussed the costs and requirements for adding
the waster water facilities into the system. Project cost: $70,000.
SELDOVIA AND PORT GRAHAM POWER PLANTS, HOMER ELECTRIC ASSOCIATION, ALASKA
The Seldovia and Port Graham Power Plant project
consisted of feasibility studies, conceptual design, final
design, construction and testing services and final
acceptance testing for two power plants located on
Alaska’s Kenai Peninsula. The plants consisted of the
design and installation of a 600 kW plant installed in an
existing power plant in Port Graham and the removal of
an existing plant and design and construction of a new
3,000 kW plant in the town of Port Graham. Both
projects included system automation design and
installation, SCADA design and installation, protective
relaying design and installation, switchgear design,
construction and installation, coordination studies, fuel tank and fuel delivery systems design
and installation and project commissioning and testing. The projects were located in remote
sites on the Kenai Peninsula and served as back-up and emergency power sources for the two
communities. The EPS contract was $1,207,500. Electric Power Constructors performed the
construction.
UNALASKA POWER PLANT, CITY OF UN ALASKA, UNALASKA, ALASKA
The Unlaska Power Plant project consisted of feasibility
studies, site selection, conceptual design, final design,
construction, construction management and testing
services and final acceptance testing for the 22 MW
diesel power plant located in Unalaska, Alaska. The
project consists of the design and installation of a 22 MW
plant to serve the city and processors located in
Unalaska, Alaska. The project includes site design,
building design, utility interconnections,
SCADA/automation design, protective relaying design,
switchgear design, coordination studies, fuel tank and
fuel delivery systems design and project commissioning
and testing.
The project is located at a remote site on the Aleutian Islands, in Unalaska, Alaska.
Final startup will be completed in 2009. Project cost: $28 million.
HUMPBACK CREEK POWER PLANT FLOOD DAMAGE, CORDOVA ELECTRIC COOPERATIVE,
CORDOVA, ALASKA
Humpback Creek is a remote plant connected electrically to the Cordova Electric Cooperative
system. The plant has over 100’ of head, and three units, with a plant capacity of over 1 MW.
The plant and associated facilities had major flood damage in late 2006. Power Builders, Inc.
(PBI) was hired by the owner to reconstruct the facilities damaged by the flood. The project
scope included replacing damaged outside electrical equipment, the access bridge, gravel and
fill material, replacement of stream bank riprap, and the replacement of the plants tailrace. ESG
Statement of Qualifications
personnel performed all of the work on the project. The work was predominantly replacement in
kind, and funded largely with FEMA monies. Project cost: $800,000.
KOTZEBUE SWITCHGEAR AND SCADA SYSTEM UPGRADES, KOTZEBUE ELECTRIC
ASSOCIATION, KOTZEBUE, ALASKA
Kotzebue is a remote hub-community that is electrically isolated from any other system. The
community runs predominantly on diesel and windpower. The windpower installation consists of
14 turbines, located on the edge of town. The project
consisted of completing a design for the switchgear,
SCADA, and mechanical/electrical instrumentation
systems. Following completion of the design and
acceptance by the Owner, the construction phase of the
project commenced, installing all of the switchgear and
controls in a phased manner to allow continuing plant
operation. EPS continues to work with the Owner to
implement additional upgrades to the plant and wind
system to further enhance operation. A performance
bond was required for the project, due to funding agency
rules. EPS met this requirement with a letter of credit.
Project cost: $1.1 million.
MEDIUM POWER TRANSFORMER MAINTENANCE/REPAIR, ALYESKA PIPELINE SERVICE
COMPANY, VALDEZ, ALASKA
To better assess the condition of medium power transformers at the Alyeska Valdez Marine
Terminal, Alyeska requested Electric Power Constructors (EPC) personnel to assist in the
testing, assessment, and repair of several medium power transformers on the terminal. EPC
personnel work with and under the direction of Alyeska personnel providing assistance and
technical expertise in assessing the condition of the VMT power transformers. EPC worked
cooperatively with Alyeska personnel performing DGA, power factor, and other testing to assess
the condition of the terminals medium power transformers. Some coordination issues were
addressed onsite by the crew and Alyeska personnel, allowing for flexible operation of the
terminal. The work was performed in 2005, with additional technical assistance on an as-
needed basis.
KODIAK GENERATOR REPLACEMENT, KODIAK ELECTRIC ASSOCIATION, KODIAK, ALASKA
Kodiak is an island community that is electrically isolated from any other system. The
community runs predominantly on diesel and
hydropower. The diesel plant, which provides the
majority of the peaking and emergency energy for
the community, consists of four large diesel
machines. During a four month period, two of the
engines experienced catastrophic failure. The
project consisted of completing a design for the
selection and installation of two new units, including
mechanical, electrical, and civil. Following
completion of the design and acceptance by the
Owner, the construction phase of the project
commenced with Power Builders personnel
Statement of Qualifications
performing the civil/structural portions, the mechanical portions being contracted to CRL
Services, and EPC doing the majority of the electrical installation, in conjunction with KEA
personnel. Project cost: $850,000.
SUBSTATION MAINTENANCE & TESTING, CHUGACH ELECTRIC ASSOCIATION, ANCHORAGE
ALASKA
EPC has completed substation testing and maintenance for
Chugach for the past 5 years on a task order basis under our
alliance contract. Testing and maintenance services have
included 34.5 kV – 230 kV oil circuit breaker testing and
maintenance, including bushing power factor, ductor, time travel,
speed adjustments and other tests associated with maintenance
activities. Power transformer testing and maintenance for
transformers up to 80 MVA and 230 kV. LTC testing and
maintenance and metal-clad breaker testing and maintenance.
KING SALMON SWITCHGEAR UPGRADE, CHEVRON , COOK INLET, ALASKA
EPC completed the design and rebuild of the existing main 600 V switchgear bus work for the
King Salmon Platform. The work included upgrading the bus for increased short circuit capacity,
installing bus bracing and fabrication of bus work. The project also included the installation of
protective relays for the switchgear, protective relay settings, testing and commissioning. The
project was completed in a scheduled shutdown of the platform on time and on budget. The
platform’s shutdown was a critical component and needed to be completed in the time allowed
to avoid well shutdowns on the platform.
PHILLIPS BELUGA RIVER , CHEVRON , COOK INLET, ALASKA
EPC completed the testing and maintenance of the facilities’ contactors, transformers, breakers,
RTDs and protective relays for the Beluga River gas field. The work was completed during a
scheduled shutdown of the facility and was completed on time and budget.
Tacoma Power Lincoln Avenue Line Relocation, TACOMA POWER
EPS is providing complete engineering services for the line relocations, including structure and
foundation design, coordination with the road designers, line design, plans and specifications for
material procurement and construction, and construction inspection.
CLIENT REFERENCES
MR. MIKE LEWIS
Alyeska Pipeline Service Company
(907) 834-7356
MR. ROD RHOADES
Alyeska Pipeline Service Company
(907) 834-7076
MR. BRAD REEVE
Kotzebue Electric Association, Inc.
(907) 442-4391
MR. DARRON SCOTT
Kodiak Electric Association, Inc.
(907) 486-7739
DMA Resume Page 1 of 4
Duane Miller Associates LLC (DMA)
5821 Arctic Boulevard, Suite A
Anchorage, AK 99518-1654
(907) 644-3200
Duane Miller Associates LLC (DMA) was established as Duane Miller &
Associates in 1982 to provide geotechnical engineering and consultation in the
problems unique to Alaska. The firm has evolved to a consultancy of engineers
and geologists, all of whom have many years of Alaskan experience. The two
senior consultants, Principal Engineer Duane Miller, P.E., and Principal Geologist
Walt Phillips, C.P.G., each have more than 30 years experience with Alaskan
projects. With a total of 17 Alaskan geotechnical engineers, geologists, laboratory
technicians and administrative/IT support staff, DMA can address any
geotechnical issue throughout Alaska in a timely basis.
Professional staff at DMA consists of four Alaska licensed geotechnical engineers
and one Alaska licensed geologist. We have five geologists and four EIT-level
engineers. We have a full time geotechnical laboratory manager and one lab
technician. Administrative and IT personnel support the professional staff. We
are located at 5821 Arctic Blvd. in Anchorage, Alaska with our laboratory
facilities, including our walk-in testing freezer, in the same building.
DMA project experience ranges from small rural projects to large industrial and
defense projects. Experience with remote site work has led to the development
of specialized exploration and sampling tools for permafrost investigations.
Field work is most often preceded by collection of available data from previous
projects and examination of existing aerial photographs. DMA maintains an
extensive library of past geotechnical reports prepared by us and other
geotechnical service providers. These reports include data from most of the
communities in the state. Our laboratory is equipped to perform nearly every
primary soil test along with secondary strength and consolidation tests for
undisturbed or remolded soil. The laboratory has a walk-in freezer for the
storage and testing of frozen soils.
DMA’s client base primarily includes major oil companies and other consulting
engineers. Typical rural projects include improvements to sanitation systems
through contracts administered by Village Safe Water (VSW) and ANTHC,
hospital projects through the Indian Health Service (IHS), improvements to bulk
fuel, wind farm, and diesel power plant facilities through AVEC and ADC&RA
Division of Energy, rural housing through regional and local housing authorities,
rural airfields and roads through DOT&PF and BIA, and school projects through
regional school districts.
DMA Resume Page 2 of 4
We pride ourselves on bringing custom geologic and geotechnical engineering
solutions to many of Alaska’s most demanding foundation engineering
problems, particularly in arctic and subartic conditions, from remote village
projects necessary to improve local well-being to major industrial oil and gas
projects important to our nation’s energy and security needs.
Every geotechnical project undertaken by DMA has a principal or senior staff
geotechnical engineer AND geologist assigned to properly scope our customer’s
needs and expectations. As an important first step, our senior staff works closely
with each customer to properly balance Scope, Schedule, Quality and Cost prior
to finalizing a Notice to Proceed for three key reasons. First, this dialog defines
our field, laboratory, and engineering objectives for all parties. A clear and
concise definition of a project’s objectives is fundamental to our management
philosophy. Second, this dialog provides the basis for project management
decision making as field findings and project needs evolve. Third, this dialog
establishes our role in the project’s scheme in terms of Chain of Command, site
safety, and compliance with environmental documentation/requirements.
The planning effort does not stop at the completion of the field effort. Upon
completion of each field phase, field logs, geotechnical samples, field notes,
geotechnical instrumentation data (ground temperatures, CPT data, piezometer,
etc), photographs and GPS/GIS data are summarized. Laboratory effort is
prioritized and managed through our Laboratory Manager with weekly updates
on laboratory status to the Project Team. This permits refinement on laboratory
schedules and scheduling engineering team effort to coincide with laboratory
effort.
Geology and engineering efforts are developed in tandem at the project level.
We strongly believe that our success is based on treating geology and
engineering as equally important elements of a project deliverable. This is the
key reason a senior or principal level geologist and engineer are assigned at the
very earliest stages of a project scoping effort.
DMA maintains an extensive in-house library of both DMA and third-party
geotechnical studies from nearly every area of Alaska. In-house studies are
DMA efforts that start with the initial work effort by Duane Miller when he
started DMA. This system spans over 1,000 separate reports retrieved by
Lat/Long, site, work type, region, permafrost conditions and other search terms.
This in-house database permits immediate retrieval of boring log and laboratory
data, Alaskan ground temperature data dating back to the late 1970s, and
geologic interpretation and engineering recommendations. Our system provides
a notification of proprietary data that cannot be used without the customer’s
DMA Resume Page 3 of 4
authorization. This database was developed internally and is unique is its ability
to capture and retrieve key project information as part of the scope refinement
process.
In additional to our internal database system, we maintain a hardcopy file of
many obscure and hard to locate third-party geotechnical reports. These reports
often provide site specific geotechnical and ground temperature data from the
late 1960s through today. These data are very useful in establishing a site history
as part of a new scoping process. We maintain these hard copy reports by village
location or by North Slope oil and gas project area.
We also maintain a large collection of US, Canadian, and Russia (Federation and
Soviet era) geotechnical research papers, some the founding work efforts in
permafrost engineering. While most recent permafrost research efforts are
available digitally through the Internet, many of our internal research papers are
not commercially digitized and are very valuable in constructing design analysis
spreadsheets or understanding the technical basis – and limitations – developed
as part of the original research.
DMA has seven experienced engineers/geologists able to supervise large,
complex geotechnical field investigation projects. Two, Duane Miller and Walt
Phillips bring a combined 75+ years of Alaskan experience to schedule, budget
and resource assignment to any geotechnical effort regardless of size, locations or
logistical complexity. Duane and Walt have successfully conducted concurrent
large, complex geotechnical investigations for major oil and gas projects on the
North Slope where remote camps, fuel logistics and Rolligon/helicopter support
elements were necessary in areas of extreme environmental sensitivity. In
additional to Duane and Walt, four senior personnel at DMA: Richard Mitchells,
Susan Wilson, Jeremiah Drage, and Daniel Willman bring strong field
geotechnical supervision capabilities. All four have experience with helicopter
sling drilling operations, coring projects, remote camp and Alaskan ‘Bush’
experience. DMA field geologists/engineers including Nathan Luzney, Jeff
Kenzie and Heather Brooks each bring field experience managing day-to-day
drilling operations and logistical support for field projects.
DMA maintains a complete in-house field sampling program for nearly any
geotechnical investigation need. Unique to cold regions field investigations, we
have developed a continuous sampling system that eliminates the need for
refrigerated coring. Of particular importance for arctic and subarctic
geotechnical field efforts is the need to collect reliable ground temperatures. We
have adopted digital temperature measurement systems to accurately capture
ground temperature data.
DMA Resume Page 4 of 4
DMA engineers are peer recognized experts in cold regions geotechnical
engineering as well as unfrozen ground geotechnical engineering. We have four
geotechnical engineers licensed in Alaska and one Alaska licensed geologist. In
unfrozen soil conditions, we adhere to geotechnical engineering designs using
NAVFAC DM-7 and USACE EM-1110-1 and EM-1001-2 series design manuals.
In addition, we rely on computer aided engineering support for many projects
using Apile, Lpile, GRL-WEAP, PYWall, Reame, and a variety of other limit
equilibrium slope analysis software tools.
Our engineering staff also has expertise in seismic analysis capabilities,
augmented with ProShake and Newmark displacement analysis software
analysis tools. We are able to conduct liquefaction analysis using methodologies
developed by Youd, et. al. as part of the NCEER Workshop Evaluation on
Liquefaction.
Since virtually no commercial engineering design software has been developed
for cold region foundation engineering, DMA has developed and maintains an
in-house library for cold regions foundation design, ranging form codified US
Air Force/Army TM 5-852-4 (Arctic and Subarctic Design Manual) to salinity
based primary and secondary creep in ice poor and ice rich permafrost as
developed by Nixon, Sego and Bigger, CRREL, and Sayles. We also use
Temp/W for finite element thermal analyses on our cold regions projects.
We maintain a comprehensive internal climate database using six key climate
centers (Barrow, Bethel, Nome, Kotzebue, Fairbanks and Gulkana) of daily
climatic and temperature records from at least 1940 through present. In addition,
we maintain a comprehensive temperature database for Prudhoe Bay with daily
temperatures from the mid 1960’s. These data are used to forecast warming
trends for air temperature and freezing or thawing indices throughout arctic and
subarctic Alaska.
DMA conducts groundwater analysis as part of our routine geotechnical
assessments for foundation design and embankment seepage analysis. We rely
on specialized third-party providers for more detailed groundwater analysis, if
necessary.
3333 Arctic Boulevard, Suite 100
Anchorage, Alaska 99503
Phone: (907) 564-2120
Fax: (907) 564-2122
Our Firm. Hattenburg Dilley & Linnell LLC (HDL), is an engineering firm specializing in
“client-focused” planning, civil engineering, transportation engineering, project management,
earth science, geotechnical services, construction administration, and material testing.
Scott Hattenburg and Lorie Dilley started Hattenburg & Dilley in July 2000. Dennis Linnell
joined the firm in March of 2002, creating HDL. Our principals are actively involved with projects
and are hands-on managers. We have structured our firm to produce a quality-centered, client
focused atmosphere to provide you with superior services. Our main office and U.S. Corps of
Engineer and AASHTO certified soils laboratory is located in Anchorage and we maintain a
branch office in Palmer.
HDL maintains a seasoned full-time staff of thirty-six (36), including seven licensed professional
engineers, one professional surveyor, two geologists, three construction inspectors, two
roadway designers, five engineers-in-training, three civil designers, four engineering
technicians, one environmental specialist, and four administrative support personnel. We use
state-of-the-art, field-to-finish civil software and computer hardware. Our workstations are
equipped with a variety of the latest software including AutoCAD Release 2008, Land
Development Desktop and Civil Design Software, Rockware Rockworks and Logger, Microsoft
Office, MS Project, Adobe Photoshop and Illustrator, geotechnical software, and Topo Maps 3D.
Our computer design personnel are high production graphic oriented technicians experienced
with generating presentation graphics, drawings, engineering plans, and 3-dimensional graphic
products.
COMPANY OVERVIEW
3
; Site Development
; Water and Sewer System Design
; Community and Regional Planning
; Project Programming
; Airport Planning and Design
; Bulk Fuel, POL and Pipelines
; Geotechnical Engineering
; Geothermal Resources
; Wind Power
; Geochemistry
; Soil, Aggregate, Concrete Testing
; Construction Administration
; Environmental Services and
Permitting
; Surveying
; Road and Transportation
Engineering
CIVIL ENGINEERING
HDL provides civil engineering services to a wide variety of clients throughout
Alaska. These projects include civil site design, grading plans, and designs for
utility improvements.
AIRPORT PLANNING, DESIGN
HDL offers airport master planning services as well as design of taxiways, runways,
access roads, and related facilities. We also have conducted wind studies using our
instrumentation expertise. Scott Hattenburg, our principal airport engineer has completed
over 35 airport-related projects and has a 16 year working history with the FAA. We
specialize in rural and city-owned airports.
City of Wasilla Airport Master Plan
Palmer Southwest Utility Extension to the Matanuska Valley Medical Center
Valley Pathway School Site Design
Alaska Zoo Entrance Site Design
Chugach Alaska Office Building Site Design
City of Palmer Sherrod Building
ACS Parking Lot Design
Palmer Airport Forestry Parking Lot
Southcentral Foundation Primary Care Facility, Iliamna
Wasilla Sewer Master Plan
City of Palmer Headworks Building
Chugach Street Water Replacement
Helen Drive Utility Improvements
South Anchorage Substation
Nome Power Plant
Elmendorf Fuel CEU Maintenance Hangar
OUR SERVICES
4
Red Dog Mine Airport Planning
Kaktovik Airport Master Plan
Seldovia Airport Master Plan
Merrill Field Access Road Reconstruct
City of Palmer Airport Improvements
City of Wasilla Airport Apron Improvements
Nondalton Wind Study
Rural Airport Embankment Evaluation: Chevak, Chefornak, Tuntutuliak & Kipnuk
RURAL ENERGY
We manage all phases of rural energy
projects from the concept phase through
final completion of construction. We provide
in-house civil, geotechnical, and
environmental phase services for these
projects. HDL currently has two term
agreements for design of rural energy
projects: one with Alaska Energy Authority
and the other with Alaska Village Electric
Cooperative.
In addition to the rural energy projects we
have two certified tank inspectors on staff
and have produced a number of Spill
Prevention Control and Countermeasure (SPCC) Plans for the State and private
companies throughout Alaska.
Middle Kuskokwim Regional Energy Project (Sleetmute, Stony River, Crooked Creek,
Chuathbaluk, Red Devil, Aniak & Takotna) Concept Design, Design, and CA
White Mountain Bulk Fuel CA
Koyukuk Power Plant and Bulk Fuel Facility Design and CA
Chevak Power Plant & Bulk Fuel Facility Concept Design
Noatak Bulk Fuel Concept Design
Hooper Bay Bulk Fuel Concept Design
Mountain Village Bulk Fuel Concept Design
Koyuk Bulk Fuel Facility Concept Design, Design and CA
Nunapitchuk/Kasigluk Amalgamated Energy Concept Design and Design
Golovin Bulk Fuel Facility Construction
5
GEOTECHNICAL ENGINEERING
HDL’s geotechnical division provides foundation
design recommendations for a wide variety of
structures including power plants, transmission
lines, bulk fuel facilities, substations, roads,
bridges, and buildings. We have developed pile
recommendations for warm permafrost, cold
permafrost, and organic rich soils. We have
specialties in thermal analysis, instrumentation, and
geochemical assessments. Given the nature of
soils in Alaska we offer creative solutions to the more common foundation problems.
Nome Power Plant Foundation – Dynamic Compaction of Loose Soils
Merrill Field Access Road – Dynamic Compaction of Landfill
Unalaska Power Plant Foundation and Site Selection
Chugach Electric Transmission Line for South Anchorage
Nunapitchuk/Kasigluk Helical Pier Foundation for Wind Towers
Helical Anchor Design for Multiple Subdivisions
Thermal Analysis of Four Rural Airport Embankments
Parks Highway Geotechnical Study MP 72-83
Foundation Design for F-22 Fuel Maintenance Hangar
Quarry Source Assessment for Village of Elim
GEOTHERMAL RESOURCES
HDL’s geotechnical group has been actively involved in the development of geothermal
resources. We offer a wide range of geological and geochemical services for the
exploration and development of geothermal power in Alaska. We are developing a new
method, Fluid Inclusion Stratigraphy (FIS), based on measuring the gas concentrations
trapped within minerals for evaluating the hydrological regime in geothermal reservoirs.
This low cost, rapid, logging method can be used as the well is being drilled to determine if
hot reservoir fluids have been encountered and if permeable zones exist in the well. We
are also working under a grant from the US Department of Energy on using this technique
for determining fracture locations in Enhanced Geothermal Systems. We work closely in
collaboration with the Department of Earth Sciences of New Mexico Tech and the Energy
and Geoscience Institute at the University of Utah.
Preliminary Feasibility Study – Pilgrim Hot Springs – Alaska Energy Authority
Preliminary Geological Evaluation – Naknek Geothermal Sources
Fluid Inclusion Stratigraphy – New Tool for Geothermal Reservoir Assessment: Coso
Geothermal Field, California – California Energy Commission
Identifying Fractures using FIS in Enhanced Geothermal Systems – Department of Energy
2D and 3D Fluid Model of Coso Geothermal Field, California – US Navy Geothermal
Program Office
6
WIND POWER
HDL provides civil engineering solutions for the development of
wind power in Alaska. We have provided foundation design
recommendations, permitting and civil engineering services.
AVEC has been instrumental in developing wind power in rural
Alaska and the firm has worked closely with AVEC on these
technically challenging projects. We have teamed with an
Alaskan construction company and a wind turbine manufacturer
to create the Alaska Wind Resource Group (AWRG).
Prototype Designs for the AOC Wind Turbine Foundations,
Various Villages - AVEC
Nunapitchuck/Kasigluk geotechnical and civil design for Northwood 100 turbines - AVEC
Hooper Bay geotechnical and permitting for three Northwind 100 turbines - AVEC
Chevak geotechnical, permitting and civil design for four Northwind 100 turbines - AVEC
Nome/Bering Straits Native Corp wind turbines permitting for 18 Entegrity 60kW turbines
CONSTRUCTION ADMINISTRATION AND MATERIAL TESTING
Our construction quality control programs typically
include our strong daily presence on the jobsite. Our
field technicians maintain contact with project
managers and the client representative through daily
reports and weekly status reports. We are typically
responsible for certifying compliance with shop
drawings; measuring quantities of pay items; auditing
survey data (line, grade, and quantities); computing
quantities; monitoring yields and overseeing field
adjustments; performing and managing materials
inspection; inspecting workmanship; preparing
directives, change orders, and supplemental
agreements; preparing periodic/final payment estimates and reports; confirming
materials/equipment tests; coordinating off-site inspection services by others; analyzing
construction contractor claims if any, and maintaining photo record of construction.
Our laboratory technicians provide testing in accordance with ASTM, AASHTO, ATM, and
WQTEC testing standards for soil and concrete. Our laboratory is certified by US Army
Corps of Engineers, AASHTO, and concrete to conduct a wide variety of soil, concrete,
aggregate, and grout testing. We can provide both ACI certified concrete and NRC
certified nuclear equipment field technicians. The laboratory maintains nuclear
densometers, concrete field sampling equipment and laboratory concrete strength testing
equipment. In addition, we maintain triaxial strength testing equipment, permeability
testing equipment, and consolidation testing equipment for non-routine soil testing.
7
Glenn-Bragaw Interchange, DOT, Anchorage
Taxiway Alpha Construction, Palmer
Division of Forestry Fire Retardant Loading Facility, Palmer
Highland Subdivision Road Reconstruction, Palmer
Nome Power Plant Pad Construction, Nome
Fuel Maintenance Hangar and Taxiway, Elmendorf AFB
Eagle-Gulkana Street, Palmer
Wasilla Airport Apron Construction, Wasilla
Nome Power Plant Concrete Testing, Nome
Wasilla Airport Apron Construction, Wasilla
ENVIRONMENTAL AND PERMITTING
Our environmental and permitting team provides all phases of environmental documents
and permitting for a wide range of engineering projects. We are skilled in the NEPA
process having completed many Environmental Reviews, Environmental Checklists, and
Environmental Assessments. Our services include Phase 1’s; Wetland Delineation;
Wetland Functional Assessment; Hydrology Assessments; Section 7 Consultation; and
Government to Government Consultation. We have permitted airports, roads, bulk fuel
facilities, power plants, water and sewer improvements, site layouts, and wind generators.
Palmer Airport Apron Categorical Exclusion
Barter Island Airport Phase I Environmental Site Assessment
Palmer Airport Phase I Environmental Site Assessment
Nunapitchuk/Kasigluk Amalgamated Energy Improvements
Middle Kuskokwim Regional Energy Project
Chugach Electric South Anchorage Substation Storm Water Pollution Prevention Plan
Hatcher Pass Scenic Outlook Storm Water Pollution Prevention Plan
Seldovia Airport Master Plan Permits
Hooper Bay Wind Turbine Environmental Assessment
Savoonga Wind Turbine FAA Permits
Chevak Energy Upgrades Permitting
Government to Government Consultation with Native Village of Kaktovik
City of Palmer Water and Sewer Extension Permits
Kipnuk New Airport Stream Gauging
SURVEYING
At HDL we understand that land surveying is often the starting point for the design of a
project. As such, we realize how important precise, quality field data can be in starting
your project in the right direction. Our field crews and office technicians are equipped with
the latest survey equipment and software. We have recently acquired a new conventional
and GPS survey equipment system that easily integrates traditional survey techniques
with Static and Real-Time Kinematic GPS surveying. This new system utilizes GPS and
Russian Glonass Satellites enabling us to gather data in areas previously unsuitable for
GPS surveying. As part of this system we have developed an innovative data collection
process which uses comprehensive field coding and data reduction software to quickly
8
transfer field data into final processed information ready for design. This new way of
thinking towards surveying providing our clients with precise, quality controlled data for
even the most aggressive schedules and budgets. Our experienced survey staff has
provided survey services across Alaska for a variety of projects and clients. This
experience along with HDL’s commitment to a client focused atmosphere provides our
clients with the best possible survey and mapping products.
ALTA/ACSM Land Title & Boundary Surveys
Engineering Design Surveys
Right of Way and Boundary Surveys
Platting for Commercial and Residential Subdivisions
Control for Photogrammetric and LIDAR Mapping
Construction Surveying
ROAD AND TRANSPORTATION ENGINEERING
Our road and highway design team provides planning, preliminary and final engineering,
and peer/quality control review for a wide range of road and highway projects. We
manage the right-of-way acquisitions, traffic studies, public meetings and all aspects of
providing a complete road design package.
Palmer Dogwood Avenue Extension & Signalization
Anchorage 3rd Avenue Rehabilitation
Seldon Road—Matanuska-Susitna Borough
Parks Highway MP 72-83 Rehabilitation
Palmer Evergreen & Gulkana Street
Wasilla Church Road Analysis
Parks Highway MP 44-52.3 Upgrade
Wasilla Crusey Street Improvements
Wasilla Lucas Road Improvements
Palmer Chugach Street
Wasilla Transportation Plan Update
BBFM Engineers, Inc.
510 L Street, Ste 200
Anchorage, AK 99501
Phone: 907-274-2236
Fax: 907-274-2520
Company Overview
Alaska Business License 218579
MBE status – N/A
BBFM Engineers Inc. is an Alaskan company specializing in structural engineering design. The
principals of BBFM Engineers are: Dennis L. Berry PE, Forrest T. Braun PE, Troy J. Feller PE
and Colin Maynard PE. All four principals were either raised or born in Alaska. The company
was established in 1996; however, the principals have been working together for over 18 years
(in fact, two have been working together for over 30 years). The ten structural engineers and
four drafters make BBFM Engineers one of the larger structural engineering staffs in the state.
BBFM Engineers has been fortunate to average over 150 projects per year, on a variety of
different project types using several different delivery systems. Over 80% of our work comes
from repeat clients. Over the years, BBFM Engineers has received numerous awards for a
variety of facilities—for public and private clients. The engineers have worked with all of the
various structural materials in designs for structures in over 150 different communities around
the state: from Ketchikan to Shemya, from Kodiak to Barrow. BBFM Engineers prides itself on
working within the constraints set by nature, and the owner, and finding a solution that is not
only structurally sound, but also cost effective and, when exposed, aesthetically pleasing.
BBFM Engineers has a proven record of successful work on small, large and medium projects.
This experience has been gained over the last 11 years (up to 34 years for the principals) on
projects all over Alaska for military and civilian clients. We are aware of the level of production
effort and coordination that is necessary for the development of high quality construction
documents. In addition, we understand the level of management required to ensure that a
quality product is produced. Our firm has a depth and breadth of experience with Alaskan Arctic
projects to its credit and we are skilled in providing cost-effective, creative design solutions to
meet the needs of our clients. Our engineers are experienced team players who are flexible and
responsive to client needs.
Project Experience
BBFM Engineers has completed more than 80 building and tower projects in the Yukon
Kuskokwim Delta and Northwest Alaska. We have experience designing tower foundations in
many of the different geotechnical conditions that exist throughout Northwest Alaska. We have
designed tower foundations in 12 different villages in soil conditions ranging from marginal
permafrost in deep silty soils, to mountain top bedrock.
Page 2 of 4
Resources
BBFM Engineers has a staff of ten structural engineers (nine licensed), four CAD drafters, an
office manager and an administrative assistant. This makes us one of the largest structural
engineering staffs in the state of Alaska and, as such, we have the ability to work on projects
with aggressive schedules. The engineers work as a team to complete established work
schedules and we are able to re-assign staff as needed to meet accelerated schedules. Our
staff meets weekly to review the workload and upcoming deadlines. We are capable of adding
new design projects soon and having them blend readily into our workload. BBFM Engineers is
committed to providing timely services and meeting all project schedules; we know we can bring
the Wind Turbine projects to a successful completion.
Equipment: BBFM Engineers uses a variety of automated systems to produce quality designs
and quality construction documents. For contract documents, the latest version of AutoCAD is
used. For specifications, the staff has used a variety of programs including MasterSpec. The
office has its own computer network for sharing of databases, communication programs, the
Internet, direct modem connections and, of course, complete backup records. In addition, the
staff at BBFM Engineers is proficient in the use of computers for structural analysis and design,
and uses the following analysis software:
• ETABS – Static and Dynamic wind and seismic lateral load analysis software for multi-story
buildings
• STAAD III – General 3D Finite Element Analysis for both large and small projects including
vertical, and wind and seismic lateral loadings.
• ENERCALC – Miscellaneous element design for individual beam column wall and
footing design in concrete, masonry, steel, and wood and well as general seismic and
wind design.
• PCAMats – Concrete Mat Analysis Program used for the design of large mat
foundations supporting multiple columns.
• WoodWorks – A software package for the design of various wood components
including plywood sheathed shear walls.
• ADAPT – A post-tensioned concrete software package used to assist in the design of
post-tensioned concrete slabs.
• RAM Structural Systems – A computer program that analyzes and designs concrete
and steel buildings, considering dead, live, snow, snow drift, wind, and seismic loads.
RAM also converts the output into Autocad drawings, creates a list of all structural
steel members in the building, and totals the structural steel weights.
• SAFE – This program assists with the design of flat slabs, foundation mats, spread
and combined footings based upon the finite element method and also includes 3D
modeling.
These programs allow us to work very efficiently and coordinate the design with the drafting
effort.
Page 4 of 4
AURORA CONSULTING PAGE 1
1999- 2007
Communities in Blue
1983 – 1999
Black Dots
Denali
Anchorage
Glacier Bay
Nikolski
Nome
Egegik
Juneau
Dillingham
Saxman
Chenega Bay
Port Graham
Nanwalek
Bettles
Togiak
Quinhagak
Chignik
Kodiak
Mat-Su
Naknek
Fairbanks
Cordova
Nenana
Dutch Harbor/Unalaska
Galena
Aniak
Venetie
Arctic Village
Eagle
Mountain
Village
Circle
St Mary’s
Unalakleet
IliamnaNewhalen
Allakaket
Huslia
Kaltag
Stevens Village
Wales
Perryville
Scammon Bay
Ahkiok
Chalkyitsik
Diomede
Igiugig
Kokhanok
Nikolai
Port Heiden
Takotna
Tuluksak
Akutan
Atka
False Pass
Ft Yukon
Kalskag
Nondalton
Solomon
Koyukuk
Stony River
Sleetmute
White
Mountain
AkiachakAtmauthluk
Beaver
Buckland
Chefornak
Deering
Golovin
Kongiganak
Kwigillingok
Larsen BayManokotak
Nelson Lagoon
Newtok
Hoonah
Kenai
King Salmon
Barrow
Pedro Bay
1999-2007
1983-1999
z
z
z
zz
z
z
z
z
z
z
z
z
z z
z
zz
z
z
z
z
z
zz
z
z
z
z
zz
zzWhittier
zz
z
z
z
z
z
z
zz
zz
zzz
z
z
z
z
z
z
z
z
z
zz Denali
Anchorage
Glacier Bay
Nikolski
Nome
Egegik
Juneau
Dillingham
Saxman
Chenega Bay
Port Graham
Nanwalek
Bettles
Togiak
Quinhagak
Chignik
Kodiak
Mat-Su
Naknek
Fairbanks
Cordova
Nenana
Dutch Harbor/Unalaska
Galena
Aniak
Venetie
Arctic Village
Eagle
Mountain
Village
Circle
St Mary’s
Unalakleet
IliamnaNewhalen
Allakaket
Huslia
Kaltag
Stevens Village
Wales
Perryville
Scammon Bay
Ahkiok
Chalkyitsik
Diomede
Igiugig
Kokhanok
Nikolai
Port Heiden
Takotna
Tuluksak
Akutan
Atka
False Pass
Ft Yukon
Kalskag
Nondalton
Solomon
Koyukuk
Stony River
Sleetmute
White
Mountain
AkiachakAtmauthluk
Beaver
Buckland
Chefornak
Deering
Golovin
Kongiganak
Kwigillingok
Larsen BayManokotak
Nelson Lagoon
Newtok
Hoonah
Kenai
King Salmon
Barrow
Pedro Bay
1999-2007
1983-1999
z
z
z
zz
z
z
z
z
z
z
z
z
z z
z
zz
z
z
z
z
z
zz
z
z
z
z
zz
zzWhittier
zz
z
z
z
z
z
z
zz
zz
zzz
z
z
z
z
z
z
z
z
z
zz
Aurora Consulting
880 H St, Ste 105
Anchorage, Alaska 99501
Phone: (907) 245-9245
Fax: (907) 245-9244
Email: us@auroraconsulting.org
A. GENERAL OVERVIEW
Aurora Consulting and its business consulting staff have many years of experience in developing
economic development projects, preparing business feasibility studies and business plans,
submitting funding proposals and implementing economic development projects throughout the
state. Although our offices are located in Anchorage, the professional consulting staff of Aurora
Consulting has many years of experience in providing business development and management
consulting services throughout the state. We have provided both private entrepreneurs and
communities throughout the state with feasibility studies, business planning, market research,
market strategies, development plans and project implementation assistance essential to successful
business growth.
B. EXPERIENCE WORKING WITH RURAL ALASKA
Aurora Consulting’s staff has over thirty years of experience working with rural Alaska communities
and organizations. We have worked with literally hundreds of rural communities, as illustrated by
the map below and have traveled frequently to communities in every region of the state.
C. SAMPLE CLIENTS
AURORA CONSULTING PAGE 2
1. Anchorage Water & Wastewater Utility - Transition & Implementation Planning
Aurora Consulting provides business planning and management services to the Anchorage
Water and Wastewater Utility (AWWU) in conjuction with its transition from a department of
the Municipality of Anchorage to an Authority. Aurora Consulting has assisted with an analysis
of MOA provided services; IGC methodologies, historical charges and budgets; preliminary
identification of problems areas, potential areas for cost savings and other issues by functional
work area. Aurora Consulting assisted the AWWU to develop “Transition Plan” documents and
materials, including Phase I and Phase II Transition Plans. The level of assistance provided
required excellent communication skills and a broad understanding, interpretation and
application of the MOA Charter, Code, Policies and Procedures and MOA/AWWU IGC’s and
budgets.
Project Schedule: October, 2005 – Current
Contact: Mark Premo, General Manager
and/or Brett Jokela, Assistant General Manager
Anchorage Water & Wastewater Utility
3300 Arctic Blvd
Anchorage, AK 99503
(907) 564-2700
2. Alaska Energy Authority (AEA) – Energy Project Business Planning Services
Aurora Consulting provides professional consulting services to the Alaska Energy Authority
under a Term Services Contract to assist the Alaska Energy Authority with the development of a
Denali Commission approved business operating plan template and associated documents for
rural energy projects. Aurora Consulting assists the Rural Energy Group with preparing
templates for business plans, operation and maintenance schedules, repair and replacement
schedules, regulatory agency coordination and other business related tasks for both the Bulk Fuel
Upgrade program and the Rural Power System Upgrade program. Additionally, Aurora
Consulting provides follow-up monitoring and evaluation of completed rural energy projects, as
well as on-going business training and development.
Additionally, working with the Alaska Energy Authority’s design/engineering term contractors,
Aurora Consulting has provided a variety of business planning services for rural bulk fuel and
electric utility operations, including the development of business operating plans for over 60
communities including Akiachak, Akhiok, Akutan, Atka, Buckland, Chalkyitsik, Chefornak,
Chenega Bay, Chuathbaluk, Crooked Creek, Deering, Diomede, Egegik, False Pass, Fort Yukon,
Golovin, Hoonah, Iguigig, Kokhanok, Kongiganak, Koyukuk, Kwigillingok, Karluk, Larsen Bay,
Manokotak, Nanwalek, Nikolai, Nelson Lagoon, Newhalen, Newtok, Nikolski, Pedro Bay, Pilot
Point, Port Heiden, Stony River, Sleetmute,Takotna, Tuluksak, Unalakleet, Venetie, White
Mountain, Whitestone and many others.
Through the process of developing these services to the Alaska Energy Authority, Aurora
Consulting has worked closely with the rural communities, the Alaska Energy Authority and its
contractors and the Denali Commission; performed a variety of research and analysis tasks;
conducted interviews of project participants and engineering firms; and, communicated findings
back in well organized and understandable oral, written and electronic formats. The level of
assistance provided requires excellent communication skills and a broad understanding,
interpretation and application of the local, state and federal utility codes and regulations,
operating policies and procedures and application and governance of these at the local level.
AURORA CONSULTING PAGE 3
During the eight plus years that Aurora Consulting has worked with the Alaska Energy
Authority, we have always completed projects on-budget and on-time and have experience no
significant customer complaints. The work that we have done under this contract is relevant in
many ways – we have developed business plan outlines and templates, have worked on multiple
business plans simultaneously, have worked closely with project engineers on project scope and
design/costing and other factors, have worked closely with rural communities and residents in
the development of the plans, and, have been asked to provide our assessment of financial
viability and other key strategic decisions.
Key Individuals: Ann Campbell, Sandy Williams, Carolyn Bettes
Project Dates: October 2001 – Present
Project Managers: Chris Mello
Alaska Energy Authority
813 West Northern Lights Blvd.
Anchorage, AK 99503
(907) 771-3000
Additional references include:
Steve Stassel, Alaska Energy & Engineering Inc 349-0100
Jeff Stanley, CRW Engineering Group, 562-3252
Wiley Wilheim, LCMF Inc., 273-1851
Project Budget: Over $750,000
3. Organizational Board of Director/Management Planning and Training – 2004 - 2008
Aurora Consulting principal, Ann Campbell, has facilitated numerous community/strategic
planning sessions and provided a wide variety of business management and planning trainings
and workshops for rural and statewide organizations. Ann Campbell provided over 35 trainings
and workshops on “How to Read Financial Statements”, “How to Structure New Investments”,
“How to Track Financial Indicators and Business Activities”, “How to Set Product Pricing”,
“How to Manage Effectively”, “Marketing Planning”, “How to Plan for CEO Succession”,
“Strategic Planning” and other general financial and business topics. Clients have included
native village corporations (Becharof Corporation, Chenega Corporation, Kijik Corporation,
Toghotthele Corporation), regional non-profits (Kawerak Corporation, SEARHC Foundation),
CDQ organizations (Norton Sound Economic Development Corporation, Aleutian Pribilofs
Island Community Development Association), and statewide organizations (Sea Otter Sea Lion
Commission, AWRTA, University of Alaska, Anchorage).
Key Individuals: Ann Campbell
Project Dates: 1999-2008
Sample Project Managers: Hazel Nelson, CEO
Becharof Corporation
1225 E International Airport Rd, Ste 135
Anchorage, Alaska 99581
(907) 561-4777
Fax: 561-4778
Email: becharof@gci.net
AURORA CONSULTING PAGE 4
Sample Consulting Clients
Client Project
Ahtna Heritage Foundation Feasibility Study
Alaska Aggregate Products Business Planning
Alaska Energy Authority Community Infrastructure Business Planning
Alaska Lodging Management Hotel Business Planning
Alaska Native Heritage Center Market Demand/Financial Projections
Alaska Native Tourism Council Strategic Marketing
Alaska SeaLife Center Business Planning/Market Demand
Aleutian Pribilof Islands Community Development Assoc Business Planning/Feasibility Study
Anchorage Water & Wastewater Utility Management Planning
Becharof Corporation Strategic Planning, Marketing Planning
Bering Straits Native Corporation Business Acquisition/Financial Consulting
Bermello, Ajamil & Partners (City & Borough of Juneau) Juneau Waterfront Master Planning
BP Exploration Marketing Consulting
Bradley Reid Communications Tourism Marketing Planning
Cape Fox Corporation Tourism Marketing Assistance
Central Council Tlingit & Haida Indian Tribes of Alaska Board Training, Project Development
Chenega Corporation Feasibility Analysis
Chenega Corporation Acquisition Analysis
Chenega IRA Council Community Planning – CEDS; Market Feasibility Study
Chogguing, Ltd Board Training/Strategic Planning
CIRI Market Analysis
CIRI Tourism Acquisition Analysis
City of Akutan Community Planning
City of Aleknagik Feasibility Study
Circle Tribal Council Market Demand Analysis/Marketing Planning
City of Bettles Destination Marketing Planning, Community Planning
City of Shaktoolik Fish Processing Plant Feasibility Study
City of Togiak Community Planning – CEDS
City of Wrangell Marine Feasibility Study, Business Planning
Dillingham Chamber of Commerce Destination Marketing Planning,
Eagle Tribal Council Feasibility Analysis
Eyak Corporation Strategic Planning
Glacier Bay Tours & Cruises Marketing Analysis
Goldbelt Business Acquisition, 8(a) Planning
Hawaiian Vacations Market Demand Analysis/Strategic Planning
Kake Tribal Council Fishing Lodge Business Plan
Ketchikan Indian Corporation Marketing & Development
The Kijik Corporation Strategic Planning
Kodiak Tribal Council Business Planning
Kuskokwim Corporation Business Planning/Feasibility Study
Mat-Su Convention & Visitors Bureau Visitor Research & Analysis / Economic Impact Analysis
McDowell Group Community Planning – Yakatat
Naknek Native Village Council Fish Processing Plant Feasibility Study
North Pacific Volcano Learning Center Business Plan/Economic Impact Analysis
Northern Air Cargo Strategic Planning
Norton Sound Economic Development Council Feasibility Analysis/Management Services
Quvaq, Inc Management Planning, Business Planning
State of Alaska, Village Safe Water Community Infrastructure Business Planning
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 42 of 51 10/8/2008
Cost Worksheet
Renewable Energy Fund
Application Cost Worksheet– NJUS Wind Project
1. Renewable Energy Source
The Applicant should demonstrate that the renewable energy resource is available on a
sustainable basis.
Annual average resource availability. Average Windspeed = 8 m/s
Unit depends on project type (e.g. windspeed, hydropower output, biomasss fuel)
2. Existing Energy Generation
a) Basic configuration (if system is part of the Railbelt 1 grid, leave this section blank)
i. Number of generators/boilers/other 7 generators, 2 boilers
ii. Rated capacity of generators/boilers/other See below
iii. Generator/boilers/other type See below
iv. Age of generators/boilers/other See below
v. Efficiency of generators/boilers/other 15.81 average
Brand/Model Size (kW) Age Avg. Efficiency (kWh/Gal. Diesel)
EMD #20-645F4B 2,865 23 13.08
EMD #12-645E4 1,500 19 12.84
Caterpillar #3516 3,660 17 16.39
Caterpillar #3516B-LS 1,875 9 14.35
Wärtsilä #12V32B 5,211 3 16.32
Wärtsilä #12V32B 5,211 3 16.32
Caterpillar #3456B 430 3 Black start – not yet used
Boiler 1.5M BTU 3 Emergency only – not yet used
Boiler 1.5M BTU 3 Emergency only – not yet used
b) Annual O&M cost (if system is part of the Railbelt grid, leave this section blank)
i. Annual O&M cost for labor $1,187,403
ii. Annual O&M cost for non-labor $6,958,135
c) Annual electricity production and fuel usage (fill in as applicable) (if system is part of the
Railbelt grid, leave this section blank)
i. Electricity [kWh] 30,542,141 kWh
ii. Fuel usage
Diesel [gal] 1,932,287 gal.
Other
1 The Railbelt grid connects all customers of Chugach Electric Association, Homer Electric Association, Golden
Valley Electric Association, the City of Seward Electric Department, Matanuska Electric Association and Anchorage
Municipal Light and Power.
RFA AEA 09-004 Application Cost Worksheet revised 9/26/08 Page 1
Renewable Energy Fund
iii. Peak Load 5,080 MW/kWh
iv. Average Load 4,030 MW/kWh
v. Minimum Load 2,173 MW/kWh
vi. Efficiency 15.81 kWh/gal. of diesel
vii. Future trends
d) Annual heating fuel usage (fill in as applicable) NA
i. Diesel [gal or MMBtu]
ii. Electricity [kWh]
iii. Propane [gal or MMBtu]
iv. Coal [tons or MMBtu]
v. Wood [cords, green tons, dry tons]
vi. Other
3. Proposed System Design
a) Installed capacity 3 MW
b) Annual renewable electricity generation
i. Diesel [gal or MMBtu]
ii. Electricity [kWh] 8,963 MWh/year
iii. Propane [gal or MMBtu]
iv. Coal [tons or MMBtu]
v. Wood [cords, green tons, dry tons]
vi. Other
4. Project Cost
a) Total capital cost of new system $ 15,102,757
b) Development cost $ 431,552
c) Annual O&M cost of new system $ 523,786
d) Annual fuel cost $ 0
5. Project Benefits
a) Amount of fuel displaced for
i. Electricity 430,195 gallons per year
ii. Heat
iii. Transportation
b) Price of displaced fuel $3.72 per gallon x 430,195 gallons = $1,600,325/year
RFA AEA 09-004 Application Cost Worksheet revised 9/26/08 Page 2
Renewable Energy Fund
RFA AEA 09-004 Application Cost Worksheet revised 9/26/08 Page 3
c) Other economic benefits $ 249,743/year
d) Amount of Alaska public benefits $ 249,743/year
6. Power Purchase/Sales Price
a) Price for power purchase/sale N/A – Estimated $.285/kWh average rate
7. Project Analysis
a) Basic Economic Analysis
Project benefit/cost ratio 3.14
Payback 10.85 years
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 43 of 51 10/8/2008
Grant Budget Form
Alaska Energy Authority ‐ Renewable Energy FundBUDGET INFORMATIONBUDGET SUMMARY: NJUS Renewable Energy Fund Wind ProjectMilestone Federal Funds State FundsLocal Match Funds (Cash)Local Match Funds (In‐Kind)Other FundsTOTALSPhase I and II Tasks (Reconnaissance, Feasibility and Conceptual Design)1. Initial Renewable Resource Review (DOE Report)$0 $02. Existing Energy System Analysis (DOE Report ‐ Partners)$4,302 $4,3023. Proposed System Design (All Project Partners)$8,004 $8,0044. Proposed System Costs Estimations (All Project Partners)$3,336 $3,3365. Proposed Benefits (GEC ‐ STG)$3,804 $3,8046. Energy Market/Sales Analysis (NJUS)$1,998 $1,9987. Permitting Review (HDL)$230 $2308. Analysis of Potential Environmental Issues (HDL)$230 $2309. Land Ownership Preparations (NJUS)$1,998 $1,99810. Legal Consultations$400 $40011. Preliminary Analysis and Recommendations (Aurora Consulting)$5,250 $5,250$29,552Phase III Tasks (Final Design and Permitting)12. Project Management (STG Estimate) $125,000 $125,00013. Perform Geotechnical Analysis (DMA Estimate) $44,000 $44,00014. Finalize Energy Production Analysis (GEC Estimate) $10,000 $10,00015. Finalize Foundation Designs (BBFM Estimate) $19,000 $19,00016. Finalize System Integration Designs (IES/EPS Estimate) $222,346 $222,34617.1 Finalize Land Agreements (Legal Estimate ‐ NJUS) $2,000 $2,00017.2 Purchase Land (NJUS)$830,000 $830,00018. Turbine Procurement (Turbine Estimate ‐ IES/STG) $6,713,700 $6,713,70019. Begin Financing Development (Legal Estimate ‐ NJUS) $2,000 $2,00020. Apply for/Obtain Permits (HDL Estimate) $20,000 $20,00021. Draft Final Operational Business Plan (Aurora Consulting Estimate) $15,000 $15,000$8,003,046Phase IV Tasks (Construction, Commissioning, Operation and Reporting)22. Project Management (STG Estimate) $125,000 $125,00023.1 Foundation Material Procurement (STG Estimate) $1,259,478 $1,259,47823.2 Mobilization and Demobilization Costs (STG Estimate) $1,028,075 $1,028,07523.3 Site Access and Foundation Development (STG Estimate) $285,580 $285,58023.4 Foundation Installation (STG Estimate) $823,544 $823,54423.5 Tower/Turbine Erection (STG Estimate) $396,639 $396,63923.6 Transmission/Distribution Lines (NJUS/STG/EPS Estimates) $434,400 $128,200 $562,60023.7 Power Storage Foundation Pad (STG Estimate) $45,330 $45,33023.8 Construction Survey/As‐Built Diagrams (STG Estimate) $26,220 $26,22023.9 Job Site Clean Up (STG Estimate) $15,866 $15,86624. System Integration (EPS Estimate) $1,608,769 $591,231 $2,200,00025. SCADA Installation (IES Estimate) $503,380 $503,38026. System Calibration (IES/EPS Estimate) $220,000 $220,00027. Final Business Plan Development (Aurora Consulting Estimate) $10,000 $10,000$ 7,501,710.63 Total Project Costs (Phase I, II, III and IV)$ 13,951,326 $ 595,231 $ 958,200 $ 29,552 $ 15,534,309 Total Phase I and Phase II CostsTotal Phase III CostsTotal Phase IV CostsRFA AEA09-004 Budget Form
Alaska Energy Authority ‐ Renewable Energy FundMilestone # BUDGET CATEGORIES: 1 2 3 4 5 6Direct Labor and BenefitsTravel, Meals, or Per DiemEquipmentSuppliesContractual Services4,302$ 8,004$ 3,336$ 3,804$ 1,998$ Construction ServicesOther Direct CostsTOTAL DIRECT CHARGES$ ‐ $ 4,302 $ 8,004 $ 3,336 $ 3,804 $ 1,998 789 10 1112Direct Labor and BenefitsTravel, Meals, or Per DiemEquipmentSuppliesContractual Services 230$ 230$ 1,998$ 400$ 5,250$ 125,000$ Construction ServicesOther Direct CostsTOTAL DIRECT CHARGES$ 230 $ 230 $ 1,998 $ 400 $ 5,250 $ 125,000 13 14 15 16 17.1 17.2Direct Labor and BenefitsTravel, Meals, or Per DiemEquipmentSuppliesContractual Services 30,000$ 10,000$ 19,000$ 222,346$ 2,000$ Construction Services 14,000$ Other Direct Costs830,000$ TOTAL DIRECT CHARGES$ 44,000 $ 10,000 $ 19,000 $ 222,346 $ 2,000 $ 830,000 18 19 20 21 22 23.1Direct Labor and BenefitsTravel, Meals, or Per DiemEquipment 6,713,700$ SuppliesContractual Services2,000$ 18,000$ 15,000$ 125,000$ Construction Services1,259,478$ Other Direct Costs2,000$ TOTAL DIRECT CHARGES$ 6,713,700 $ 2,000 $ 20,000 $ 15,000 $ 125,000 $ 1,259,478 RFA AEA09-004 Budget Form
Alaska Energy Authority ‐ Renewable Energy Fund23.2 23.3 23.4 23.5 23.6 23.7Direct Labor and Benefits21,200$ Travel, Meals, or Per DiemEquipment107,000$ SuppliesContractual Services 785,559$ 30,000$ 94,424$ Construction Services 242,516$ 285,580$ 793,544$ 396,639$ 339,976$ 45,330$ Other Direct CostsTOTAL DIRECT CHARGES$ 1,028,075 $ 285,580 $ 823,544 $ 396,639 $ 562,600 $ 45,330 23.8 23.9 24 25 26 27Direct Labor and BenefitsTravel, Meals, or Per DiemEquipment2,200,000$ SuppliesContractual Services220,000$ 10,000$ Construction Services 26,220$ 15,866$ 503,380$ Other Direct CostsTOTAL DIRECT CHARGES$ 26,220 $ 15,866 $ 2,200,000 $ 503,380 $ 220,000 $ 10,000 TOTALSDirect Labor and Benefits$ 21,200 Travel, Meals, or Per Diem$ ‐ Equipment$ 9,020,700 Supplies$ ‐ Contractual Services$ 1,737,881 Construction Services$ 3,922,528 Other Direct Costs$ 832,000 TOTAL DIRECT CHARGES$ 15,534,309 RFA AEA09-004 Budget Form
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 44 of 51 10/8/2008
Electronic Version of
Application
(See attached CD Rom)
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 45 of 51 10/8/2008
Governing Body
Resolution
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 46 of 51 10/8/2008
NJUS Board Resolution
NOME JOINT UTILITY SYSTEM
NOME JOINT UTILITY BOARD
RESOLUTION 08-18
A RESOLUTION AUTHORIZING AND SUPPORTING THE RENEWABLE ENERGY FUND
GRANT APPLICATION TO THE ALASKA ENERGY AUTHORITY
FOR WIND GENERATION IN NOME
WHEREAS,the City of Nome through the Nome Joint Utility System owns and operates the electric utility
for the community of Nome,Alaska;and,
WHEREAS,the cost of diesel fuel in rural Alaska is extraordinarily expensive and Nome/NJUS has been
pursuing alternatives to the use of diesel generation to provide electricity to the community
which can reduce reliance on diesel fuel and the cost of electricity to residents and
businesses of the community;and,
WHEREAS,the Alaska State Legislature has established a Rural Energy Grant Fund and the Alaska Energy
Authority is soliciting proposals for funding of renewable energy projects on behalf of the
State of Alaska;and,
WHEREAS,Nome/NJUS is desirous of substituting diesel-generated power with wind-generated power;
NOW,THEREFORE BE IT RESOLVED,that the Nome Joint Utility Board authorizes management to submit
the Nome Renewable Energy Fund Wind Project grant application to the Alaska Energy Authority;and,
BE IT FURTHER RESOLVED,that NJUS authorizes submittal of the Nome Renewable Energy Fund Wind
Project application at the match levels indicated in the application;and,
BE IT FURTHER RESOLVED,that the Nome Joint Utility Board designates and authorizes the Utility Manager
as Chief Operating Officer to be the point of contact to represent Nome for purposes of the application;and,
BE IT FURTHER RESOLVED,that NJUS attests that it is in compliance with all federal,state,and local laws,
including existing credit and federal tax obligations.
SIGNED THIS 30th DAY OF SEPTEMBER,2008 AT NOME,ALASKA.
Jim qst,Jr.,Chairmar\
NOMyJOINT UTILITY BbARD
ATTEST:
David Barron,Secretary
NOME JOINT UTILITY BOARD
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 47 of 51 10/8/2008
City of Nome Resolution
Presented by:
Utility Manager
Action Taken:
Yes4,No’C’
Abstain -‘-
CITY OF NOME,ALASKA
RESOLUTION NO.R-08-09-03
A RESOLUTION AUTHORIZING AND SUPPORTING A RENEWABLE ENERGY FUND
GRANT APPLICATION TO THE ALASKA ENERGY AUTHORITY
FOR WIND GENERATION IN NOME
WHEREAS,the City of Nome through the Nome Joint Utility System (NJUS)owns and
operates the electric utility for the community of Nome,Alaska;and,
WHEREAS,the cost of diesel fuel in rural Alaska is extraordinarily expensive and Nome/NJUS
has been pursuing alternatives to the use of diesel generation to provide electricity to the community
which can reduce reliance on diesel fuel and the cost of electricity to the residents and businesses of
the community;and,
WHEREAS,the Alaska State Legislature has established a Rural Energy Grant Fund and the
Alaska Energy Authority is soliciting proposals for funding of renewable energy projects on behalf of
the State of Alaska;and,
WHEREAS,Nome/NJUS is desirous of substituting diesel-generated power with wind-
generated power;
NOW,THEREFORE BE IT RESOLVED,that the Nome Common Council authorizes the
Nome Joint Utility System to submit the Nome Renewable Energy Fund Wind Project grant
application to the Alaska Energy Authority;and,
BE IT FURTHER RESOLVED,that the City authorizes submittal of the Nome Renewable
Energy Fund Wind Project application at the match levels indicated in the application;and,
BE IT FURTHER RESOLVED,that the City designates and authorizes the Utility Manager as
Chief Operating Officer of Nome Joint Utility System to be the point of contact to represent Nome for
purposes of the application;and,
BE IT FURTHER RESOLVED,that Nome attests that it is in compliance with all federal,state,
and local laws,including existing credit and federal tax obligations.
APPROVED and SIGNED this 29 day of September,2008.
ATTEST:
RER
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 48 of 51 10/8/2008
Match Documentation –
NJUS and City of Nome
NOME JOINT UTILITY SYSTEM
a component unit of
P.O.Box 70 •Nome,Alaska 99762 •(907)443-NJUS •Fax (907)443-6336
STATE OF ALASKA RENEWABLE ENERGY FUND
NOME WIND PROJECT GRANT APPLICATION
MATCH CERTIFICATION
This is to certify the City of Nome/Nome Joint Utility System will make the following match
contributions should funds be awarded to support the wind energy project described in our
grant application of $13,951,326 submitted under RFA #AEA-09-004.
Should grant funds be awarded,the applicant will provide a match representing a local cash
and in-kind investment of ten percent (10%)of the grant funds awarded.Based on the
application amount,our match will be comprised of the following:
Land identified for location of wind farm on Newton:
672 acres,more or less,based on a restricted appraisal,
valulation date of October 1,2008 (exceeds)830,000
Management oversight and rental value of equipment
provided in-kind to the project 128,200
Cash Match Commitment to Project 595,231
1.553,431
I further confirm I am specifically authorized by the Nome Joint Utility Board and the Nome
Common Council to commit the items listed as grant match and to provide this certification.
JoIn K.Handeland
General Manager/Chief Operating Officer
NOME JOINT UTILITY SYSTEM
Dated:October 7,2008
Providing reliable utility services to system rate payers efficiently and economically by
prudently operating and maintaining system assets in a fiscally responsible manner
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 49 of 51 10/8/2008
Partners’ Match
Documentation
October 4, 2008
To Whom It May Concern:
As the Project Manger of the NJUS Renewable Energy Fund Wind Project, this letter is to serve as
documentation of the contributions made by project partners during the conceptual design phases of this
project. To date, the following firms have either offered their services as in-kind contributions or directly
billed STG Incorporated for their time completing work regarding this wind energy installation:
Firm Total Contribution
STG Incorporated $9,215.00
Duane Miller Associates $825.00
BBFM Engineers $1,240.00
Electric Power Systems $2,168.00
Intelligent Energy Systems $2,500.00
HDL Engineers $460.00
Nome Joint Utility System $6,000.00
Legal Counsel $400.00
Aurora Consulting $5,250.00
DNV Global Energy Concepts $1,500.00
Total: $29,558.00
More detailed cost accounting for this work is available upon request.
Signed,
James St. George
President, STG Incorporated
11820 S. Gambell Street • Anchorage, Alaska 99515 • Phone: (907) 644-4664 • Fax: (907) 644-4666
info.stginc@gci.net • www.stgincorporated.com
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 50 of 51 10/8/2008
NJUS Renewable Energy
Fund Wind Project
Supporting Documents
DNV Global Energy Concepts Inc.
1809 7th Avenue, Suite 900
Seattle, Washington 98101
Phone: (206) 387-4200
Fax: (206) 387-4201
www.globalenergyconcepts.com
www.dnv.com
Preliminary Energy Assessment for
Nome Wind Energy Project
October 6, 2008
Prepared for:
STG Inc
11820 South Gambell Street
Anchorage, AK 99515
Preliminary Energy Assessment, Nome, Alaska EARP0046-A
DNV Global Energy Concepts Inc. i October 6, 2008
Approvals
October 6, 2008
Prepared by Mia Devine Date
October 6, 2008
Reviewed by Kevin J. Smith Date
Version Block
Version Release Date Summary of Changes
A October 6, 2008 Original
Preliminary Energy Assessment, Nome, Alaska EARP0046-A
DNV Global Energy Concepts Inc. ii October 6, 2008
Table of Contents
BACKGROUND AND SITE DESCRIPTION........................................................................... 1
WIND RESOURCE MEASUREMENTS................................................................................... 2
Wind Rose............................................................................................................................... 2
Air Density.............................................................................................................................. 3
Wind Speeds at the Project Site.............................................................................................. 3
ENERGY ANALYSIS.................................................................................................................. 6
Wind Turbine Power Curves and Gross Energy Production.................................................. 6
Energy Losses......................................................................................................................... 7
Electric Load........................................................................................................................... 9
Diesel Generators and Controls............................................................................................ 10
Balance of System Equipment.............................................................................................. 10
Energy System Modeling Results......................................................................................... 11
Preliminary Energy Assessment, Nome, Alaska EARP0046-A
DNV Global Energy Concepts Inc. iii October 6, 2008
List of Figures
Figure 1. Proposed Wind Project Site, Nome................................................................................. 1
Figure 2. Wind Rose at Anvil Mountain, Nome (September 15, 2005, to July 8, 2007) ............... 3
Figure 3. Estimated Monthly Diurnal Wind Speeds at Newton Peak............................................. 5
Figure 4. Estimated Year 2015 Electric Load Requirements in Nome......................................... 10
Figure 5. Estimated Hourly Electric Load and Wind Energy Production .................................... 12
List of Tables
Table 1. Monthly Average Wind Speeds (m/s) .............................................................................. 5
Table 2. Turbine Power Curves and Gross Energy, 1.26 kg/m3 Air Density................................. 6
Table 3. Estimated System Energy Losses..................................................................................... 7
Table 4. Estimated Year 2015 Power Generation Requirements in Nome..................................... 9
Table 5. Specifications for Diesel Generators in Nome ............................................................... 10
Table 6. Energy System Modeling Results, Five Fuhrländer FL600 Wind Turbines .................. 13
Table 7. Energy System Modeling Results, Five Vestas RRB PS600 Wind Turbines ................ 13
Preliminary Energy Assessment, Nome, Alaska EARP0046-A
DNV Global Energy Concepts Inc. 1 October 6, 2008
Background and Site Description
DNV Global Energy Concepts Inc. (DNV-GEC) has been retained by STG Inc to evaluate the
wind resource in Nome, Alaska, and complete a preliminary estimate of the potential energy
production and diesel fuel displacement of a proposed wind power project in the community.
This report describes the methodology and assumptions used in the analysis. This report is not
intended as a detailed technical or economic feasibility study of the proposed wind power
system. DNV-GEC has not completed a site visit of the proposed project area.
STG intends to install five 600 kW wind turbines on Newton Peak, located about 7 km northeast
of the town of Nome. The hybrid wind-diesel power plant is intended to be a medium-
penetration system, with wind energy providing up to 30% of the village load on average. The
location of the proposed project site on Newton Peak and the turbine layout provided by STG is
shown in Figure 1. Also shown are the locations of wind monitoring stations discussed in this
report.
Figure 1. Proposed Wind Project Site, Nome
Preliminary Energy Assessment, Nome, Alaska EARP0046-A
DNV Global Energy Concepts Inc. 2 October 6, 2008
Wind Resource Measurements
Data are available from a 30-m meteorological (met) tower, located along the Snake River valley
in Nome at an elevation of 18 m. Wind speed and direction measurements were recorded at
heights of 19.5 m and 29 m above ground level. Standard, uncalibrated NRG#40 anemometers
and NRG #200P wind vanes were used at the site. Data were recorded as 10-minute averages
from November 9, 2005, to May 8, 2008.
A second wind monitoring station is located on Anvil Mountain, at an elevation of 305 m.
Standard, uncalibrated NRG#40 anemometers and NRG #200P wind vanes were mounted on a
12-m tall telephone pole and data were recorded as 10-minute averages from September 15,
2005, to July 8, 2007.
DNV-GEC compiled, validated, and incorporated data from both met towers into the analysis.
DNV-GEC followed a standard validation process to identify and remove erroneous data (e.g.,
due to icing). Invalid wind data were removed from the data set and a secondary anemometer
was used to fill the gaps when available. Both sites experienced a significant amount of data loss
due to icing as well as data that is missing for unknown reasons. The average data recovery rates
were 75% at Anvil Mountain and 81% at Snake River. The Windographer software program was
used to fill all gaps in the data set by making use of the statistical properties of the measured data
surrounding the gap.
Wind Rose
A wind rose depicts the frequency and energy content of wind by direction and influences the
layout of a wind farm with multiple wind turbines. As shown in Figure 2, the prevailing wind
direction on top of Anvil Mountain is from the northeast, with secondary wind directions from
the northwest and south. The wind rose from the Snake River met tower site and the airport
weather station in Nome also indicate frequent winds from the northeast, as well as secondary
winds from the southwest and north. The turbine layout developed by STG is oriented to capture
the prevailing northeast winds.
Preliminary Energy Assessment, Nome, Alaska EARP0046-A
DNV Global Energy Concepts Inc. 3 October 6, 2008
0
2
4
6
8
10
12
14
0
10 20
30
40
50
60
70
80
90
100
110
120
130
140
150
160170
180
190200
210
220
230
240
250
260
270
280
290
300
310
320
330
340 350
% of Energy % of Time
Figure 2. Wind Rose at Anvil Mountain, Nome (September 15, 2005, to July 8, 2007)
Air Density
The density of the air affects power production from a wind turbine, with denser air leading to
greater power production potential. The density of air depends on the air temperature and the
elevation of the site. An annual average air density value of 1.26 kg/m3 was calculated for
Newton Peak based on the long-term average air temperature of -5.5°C measured at the Nome
airport weather station and an elevation of 350 m (site elevation of 300 m plus hub-height
elevation of 50 m). The wind turbine power curves are adjusted to the site air density.
Wind Speeds at the Project Site
DNV-GEC investigated the availability of long-term reference meteorological data to adjust the
measured met tower wind speeds to represent long-term conditions. The Automated Surface
Observation Station (ASOS) at Nome was identified as the only valid source of long-term data in
close proximity to the met tower sites; however the correlation between the met towers and
ASOS site is poor, with an R-squared value of 0.46 based on a comparison of monthly average
wind speeds. Adjustments to the met tower data based on this reference station are not likely to
reduce uncertainty in long-term wind resource estimates; therefore, long-term adjustments were
not made to the measured data. The multi-year record at the met tower sites helps to reduce
uncertainty in lieu of a long-term reference station.
The proposed wind project site is on a hill approximately 3 km east of Anvil Mountain and 8 km
southeast of the Snake River measurement site. The wind resource is highly variable from one
Preliminary Energy Assessment, Nome, Alaska EARP0046-A
DNV Global Energy Concepts Inc. 4 October 6, 2008
location to the next, particularly in complex terrain such as the hills and valleys around Nome.
Therefore, DNV-GEC made adjustments to the measured wind resource to account for variations
of wind flow over the terrain between the met tower sites and the proposed project site on
Newton Peak. The primary tool used to extrapolate from one site to the next is the High
Resolution Wind Map of Alaska produced by AWS Truewind, which presents expected annual
average wind speeds at heights of 30 m and 50 m above ground level.
The measured met tower data at both Snake River and Anvil Mountain were compared to
predictions from the wind map. At the Snake River site, the expected annual average wind speed
based on the 30-m wind map is 5.1 to 5.8 m/s at a height of 30 m above ground level. The actual
30-month weighted average wind speed measured at the site is 5.4 m/s at a 30-m height, which is
in the middle of the expected range. Based on the standard wind shear value of 0.14 used in the
wind map classification system, the Anvil Mountain site is expected to experience an annual
average wind speed of 6.5 to 7.2 m/s at a 12-m height above ground level. The actual 22-month
weighted average wind speed measured at Anvil Mountain is 6.1 m/s at a 12-m height, which is
6% below the range predicted by the wind map. A possible explanation for a lower than expected
wind resource on Anvil Mountain is the significant amount of data loss experienced due to ice
during the windy winter months at this site. However, without a valid long-term reference
station, the magnitude of the possible under-estimation cannot be quantified with available data.
Since the terrain at the proposed project site on Newton Peak appears similar to the terrain at
Anvil Mountain based on our desk-level map analysis, DNV-GEC has assumed that Newton
Peak will experience the same relationship between estimated and actual wind speeds as at the
Anvil Mountain site. According to the 50-m wind speed map (see Figure 1), the annual average
wind speed at the proposed turbine locations is expected to range from 8.0 to 8.8 m/s at a height
of 50 m. Based on the magnitude of over-estimation at the Anvil Mountain site, the actual range
of wind speeds estimated at Newton Peak is 7.5 to 8.5 m/s.
In order to create an hourly data set for use in energy calculations, a year of hourly data
measured at Anvil Mountain was scaled to the expected annual average wind speeds at Newton
Peak. Due to the similar topography between the sites, DNV-GEC expects the diurnal and
seasonal wind patterns between the sites to be similar. Although the wind map suggests that one
of the turbine locations may be located in a higher wind speed class than the other turbines, to be
conservative, DNV-GEC assumed all turbine locations would be exposed to the same wind
resource when calculating gross energy production. Table 1 and Figure 3 summarize the
measured and the calculated monthly average wind speeds for Nome.
Preliminary Energy Assessment, Nome, Alaska EARP0046-A
DNV Global Energy Concepts Inc. 5 October 6, 2008
Table 1. Monthly Average Wind Speeds (m/s)
Month
Snake River,
Measured
(29 m)
Anvil Mountain,
Measured
(12 m)
Newton Peak Wind Project
Site, Long-Term Estimate
(50 m)
January 5.9 4.2 8.6 – 10.1
February 6.9 7.2 8.8 – 10.4
March 5.4 5.3 6.8 – 8.0
April 5.5 5.1 5.9 – 6.9
May 3.8 4.4 4.3 – 5.1
June 3.9 4.8 5.7 – 6.6
July 3.7 4.7 6.7 – 7.9
August 4.1 4.5 5.6 – 6.5
September 5.6 6.4 8.2 – 9.6
October 5.6 8.0 11.6 – 13.6
November 6.3 8.9 10.1 – 11.9
December 6.2 6.7 7.7 – 9.0
Annual Average 5.5 6.0 7.5 – 8.8
Note: The annual average wind speed at Snake River is based on 30 months of data and the annual
average wind speed at Anvil Mountain is based on 22 months of data.
Figure 3. Estimated Monthly Diurnal Wind Speeds at Newton Peak
Preliminary Energy Assessment, Nome, Alaska EARP0046-A
DNV Global Energy Concepts Inc. 6 October 6, 2008
Energy Analysis
DNV-GEC used the software program HOMER, developed by the National Renewable Energy
Laboratory, to estimate energy production (www.nrel.gov/homer). The HOMER modeling
software compares the hourly output of the wind turbines with the hourly electric load of the
community and dispatches the appropriate diesel generator to make up any difference in power
needs. The operating reserve, minimum loading of the diesel engines, and the diesel-fuel
efficiency curves are also taken into consideration to calculate the fuel consumption of the
system. Inputs into the model include the local wind resource, the wind turbine power curve, the
community’s hourly electric load, and diesel generator fuel curves. Assumptions used for each of
these inputs and results of the analysis are described below.
Wind Turbine Power Curves and Gross Energy Production
STG is considering either the Fuhrländer FL600 or the Vestas RRB PS600 wind turbine for the
project site. The suitability and long-term reliability of either turbine model for operation in cold
climates has not been specifically evaluated by DNV-GEC for this preliminary assessment. The
energy analysis was completed for both turbine models. The manufacturer-provided power
curves were adjusted to the site air density of 1.26 kg/m3 and are shown in Table 2. The turbine
power curves are used to calculate energy production for each hourly average wind speed value.
The hourly energy production is summed over a year to estimate gross annual energy production
for each wind turbine.
Table 2. Turbine Power Curves and Gross Energy, 1.26 kg/m3 Air Density
Wind Speed
(m/s)
Fuhrländer
Power (kW)
Vestas RRB
Power (kW)
0 0 0
1 0 0
2 0 0
3 6 0
4 28 22
5 63 44
6 120 84
7 196 147
8 298 224
9 421 311
10 527 408
11 595 479
12 611 536
13 615 566
14 615 584
15 615 597
16 615 600
17 615 602
18 615 600
19 615 600
Preliminary Energy Assessment, Nome, Alaska EARP0046-A
DNV Global Energy Concepts Inc. 7 October 6, 2008
Wind Speed
(m/s)
Fuhrländer
Power (kW)
Vestas RRB
Power (kW)
20 615 600
21 0 600
22 0 600
23 0 600
24 0 600
25 0 600
Annual Average Wind
Speed, 50 m Height 8.0 m/s 8.0 m/s
Gross Energy Production
per Turbine 1,997 MWh/yr 1,792 MWh/yr
Gross Capacity Factor 38.0% 34.1%
Energy Losses
The gross annual energy represents the energy delivered at the base of the wind turbine towers
under ideal conditions. Net energy production takes into account typical losses and represents the
energy delivered to the grid interconnection point for a typical (average) year. Exact losses can
vary significantly from project to project and are strongly influenced by factors such as
equipment reliability, owner/operator’s approach to maintenance and repairs, turbine and
subcomponent supplier responsiveness, and site conditions. DNV-GEC evaluated each potential
area of energy loss in the Nome wind power system and estimated a correction factor to be
applied to the projected diesel-fuel savings calculated by the HOMER model, which otherwise
assumes 100% turbine availability and zero system losses. Aggregate energy losses are estimated
to be 24% for the site, as listed in Table 3. Estimated values are long-term averages over an
expected 20-year project life. Year to year losses, particularly availability, can fluctuate
significantly.
Table 3. Estimated System Energy Losses
Description
Losses
(% of Energy)
Correction
Factor
Availability 11% 0.89
Electrical 2% 0.98
Turbine Performance 2% 0.98
Environmental 7% 0.93
Wake Effects 3% 0.97
Curtailment 1% 0.99
Total 24% 0.76
Turbine availability is the primary cause of energy losses for the wind system. Availability is the
percent of time during the year that the wind turbines are online and available to produce power.
Factors affecting turbine availability include downtime due to routine maintenance, faults, minor
or major component failures, and balance-of-plant downtime (substation transformer failures,
electrical collection system or communication system problems, or transmission outages). While
a “typical” year may have relatively limited downtime associated with component failures, the
Preliminary Energy Assessment, Nome, Alaska EARP0046-A
DNV Global Energy Concepts Inc. 8 October 6, 2008
infrequent events of long duration can result in significant lost energy. As the equipment ages,
failure of minor components with design lives less than 20 years is expected to increase;
however, the increasing failure rate may be offset somewhat by increased efficiency as
experience is gained in replacing these components. DNV-GEC estimated a long-term turbine
availability of 89% which corresponds to an average of 960 turbine-hours per year of project
downtime due to planned or unplanned maintenance. This estimate is based on the assumption
that the wind power system will have remote monitoring capability that would allow both the
turbine supplier and the power system operator to monitor production, troubleshoot faults and
take corrective action on some tasks without sending a technician to the site. It is also assumed
that technicians experienced with electrical and mechanical systems employed by the power
system operator would be capable of completing routine maintenance and minor component
repairs with some basic training from the turbine manufacturers.
Electrical losses represent the difference between energy measured at each wind turbine and the
point of revenue metering, including transformers, collection wiring, conversion to and from
energy storage devices, and parasitic consumption within the power plant. DNV-GEC estimates
electrical losses to be 2%.
Turbine performance losses include a variety of issues related to the normal control of the wind
turbine that prevent performance in accordance with the reference power curve. These issues
include high-wind hysteresis (production lost during the time it takes to recover from automatic
high-wind shutdowns), low-wind hysteresis (startup and cut-in), off-yaw operations, and
turbulence. DNV-GEC estimates turbine performance losses to be 2%.
Environmental losses include weather-related shutdowns to avoid hail, lightning, or other storm
damage, reduced site access due to inclement weather conditions, and shut downs due to ambient
temperatures outside the turbine’s operating range. Also included in this category is blade soiling
and degradation, which occurs with the accumulation of dirt, insects, or ice, impacts the
aerodynamics of the blades, thus lowering production. The cold weather specifications of the
Fuhrländer and Vestas RRB were not available for this analysis; however, wind turbines are
typically designed to operate in temperatures as low as -20°C without special modifications.
Based on the temperature data measured at the Snake River met tower, temperatures drop below
-20°C during approximately 600 hours per year. Some of these hours are likely to coincide with
periods of energy loss due to icing and reduced access to the site during poor weather. DNV-
GEC estimates an average 7% energy loss per year due to environmental-related issues.
Wake effects refer to lost energy production caused by turbines located downwind of other
turbines. The wind turbine layout in Nome is based on a primary wind direction of northeast;
however, the wind rose shows that power-producing winds also come from the southwest and
north. During those times, some of the wind turbines will be located downwind, or in the wake,
of other turbines, leading to energy losses for those wind turbines. Based on the current turbine
layout with a single row of turbines and turbine-to-turbine spacing of 5.5 rotor diameters, DNV-
GEC estimates a 3% energy loss due to wake losses; however, a complete wake loss simulation
has not been completed.
Preliminary Energy Assessment, Nome, Alaska EARP0046-A
DNV Global Energy Concepts Inc. 9 October 6, 2008
Curtailment includes commanded shutdowns related to wind sector management, losses due to
the power purchaser electing to not take power generated by the facility, and altered operations
to reduce noise, shadow flicker impacts, or for bird or bat mitigation. Curtailment of the
proposed wind facility is expected to be minimal; DNV-GEC estimates 1% energy loss to
account for occasional curtailment when wind power generation exceeds the community
demand.
Since each loss category is independent of the other categories, total losses are calculated by
multiplying each system loss correction factor to result in a total correction factor of 0.76.
HOMER does not incorporate the above-discussed energy losses into the power system model.
Therefore, the loss correction factor is applied to the gross fuel savings results from HOMER.
Wind-generated electricity not immediately used by the community may be diverted into an
electric dump load and used for space heat. Since this electricity is not sold at retail electric rates,
it is considered an energy loss from the power plant operator’s point of view. This electrical
energy loss is included in the HOMER model and is therefore not repeated in the energy loss
categories above.
Electric Load
According to the Nome Region Energy Assessment report prepared by the Department of
Energy’s National Energy Technology Laboratory in 2007, the annual electric generation
requirements in Nome in the year 2015 are expected to be 31,200 MWh, and daily loads are
expected to range from 2.7 MW to 4.3 MW seasonally. Based on the monthly and diurnal load
profiles presented in the report, DNV-GEC synthesized a year of hourly electric load data as
summarized in Table 4 and Figure 4.
Table 4. Estimated Year 2015 Power Generation Requirements in Nome
Month
Average
Load (MW)
Gross Energy
Production (MWh)
Jan 4.1 3050
Feb 4.0 2654
Mar 3.9 2902
Apr 3.6 2592
May 3.3 2455
Jun 2.9 2088
Jul 2.9 2158
Aug 3.1 2306
Sep 3.3 2376
Oct 3.6 2641
Nov 4.0 2844
Dec 4.1 3013
Total 3.6 31,080
Preliminary Energy Assessment, Nome, Alaska EARP0046-A
DNV Global Energy Concepts Inc. 10 October 6, 2008
Figure 4. Estimated Year 2015 Electric Load Requirements in Nome
Diesel Generators and Controls
The sizes of the diesel generators at the Nome power plant are summarized in Table 5. DNV-
GEC estimated fuel efficiency data based on available specifications from similar sized diesel
gensets. In the HOMER model it is assumed that the minimum load to be placed on these diesels
is 30% of rated power.
Table 5. Specifications for Diesel Generators in Nome
Estimated Fuel Efficiency Data
Make Rating
Minimum
Load 100% Load 30% Load
Wartsila 1875 kW 562 kW 41% 34%
Wartsila 3660 kW 1098 kW 41% 34%
Wartsila 5200 kW 1560 kW 41% 34%
Balance of System Equipment
Balance of system equipment could include electric dump loads, energy storage systems,
flywheels, or other equipment necessary to ensure high quality and reliable power. The
evaluation and specification of various balance of system equipment is beyond the scope of this
analysis. For the purpose of estimating diesel fuel displacement, DNV-GEC assumes that
adequate balance of system equipment and/or control systems are in place to absorb and/or
curtail any excess wind generated electricity that is not instantaneously consumed by the
community.
Preliminary Energy Assessment, Nome, Alaska EARP0046-A
DNV Global Energy Concepts Inc. 11 October 6, 2008
Typically, energy storage systems only prove economically beneficial in high-penetration
systems where the diesel generators can be shut down when the wind turbines supply more
power than is needed by the load. During lulls in wind power generation, the energy storage
device supplies any needed power. If the lulls are prolonged and the storage becomes discharged,
a diesel generator is started and takes over supplying the load. The primary energy storage
devices commercially available include flywheels, ultra-capacitors, and batteries. This equipment
can be coupled with a low-load diesel to extend fuel savings.
Since the proposed number of wind turbines in Nome would result in a medium-penetration
wind-diesel system, DNV-GEC assumes that the proposed wind-diesel system will not include
an energy storage device. The wind turbines will rarely generate more electricity than can be
instantaneously consumed by the community. Without an energy storage device, at least one
diesel generator will remain in operation at all times to cover fluctuations between the wind
generated electricity and the electric load. In HOMER, the dispatch of diesel generators is
modeled by setting the spinning reserve value to 50% of the wind turbine output and 10% of the
electric load. In other words, at any given time the appropriately-sized diesel generator will be
selected that is capable of covering a sudden decrease in wind power output of up to 50% and a
simultaneous increase in electric demand of up to 10%. The benefit of the wind power system
will be to reduce the electric demand on the diesel power plant and allow for the operation of a
smaller diesel generator with a lower fuel consumption rate than would be used in a diesel-only
system.
Energy System Modeling Results
The HOMER modeling software compares the hourly output of the wind turbines with the hourly
electric load of the community and dispatches the appropriate diesel generator to make up any
difference in power needs. Figure 5 illustrates the daily energy production from the wind power
system consisting of five 600 kW Fuhrländer turbines compared to the electric load of the
community, assuming an average hub-height wind speed of 8.0 m/s. The difference between the
electric load and the wind power output is supplied by the diesel generators.
Preliminary Energy Assessment, Nome, Alaska EARP0046-A
DNV Global Energy Concepts Inc. 12 October 6, 2008
Figure 5. Estimated Hourly Electric Load and Wind Energy Production
System energy production and fuel savings are summarized in Table 6 and Table 7 for the range
of expected wind speeds at the site. The gross wind energy output is the amount of electricity
available to meet the community demand prior to energy losses. The turbine capacity factor is
calculated by dividing the gross energy output by the maximum possible energy production
throughout the year. The gross diesel-fuel savings of the wind-diesel system represents the
results of the HOMER modeling. The correction factor for energy losses described previously
was applied to the gross diesel-fuel savings to arrive at the net fuel savings listed. Estimated fuel
consumption of the diesel-only system is provided for comparison.
Some excess electricity is generated by the wind-diesel system since the diesel generators are not
allowed to shut off and must maintain a minimum load. In northern climates, it is common to
install an electric boiler consisting of fast-acting electric resistive heaters to absorb excess wind
electricity. The heat generated by the excess wind electricity can be incorporated into the diesel
generator heat recovery loop or supplement the heat system of the school, community buildings,
or water treatment plant. Modeling of the thermal energy and sizing of the dump load is beyond
the scope of this report; however, the amount of excess electricity generated by the proposed
wind power system is presented.
Preliminary Energy Assessment, Nome, Alaska EARP0046-A
DNV Global Energy Concepts Inc. 13 October 6, 2008
Table 6. Energy System Modeling Results, Five Fuhrländer FL600 Wind Turbines
Hub-Height Wind Speed (m/s)
Description 7.5 8.0 8.5
Gross wind energy production (MWh/yr) 9,363 9,989 10,555
Gross wind turbine capacity factor (%) 35.6% 38.0% 40.2%
Excess electricity generated (MWh/yr) 600 700 800
Fuel consumption of diesel-only system (gal/yr) 2,103,000 2,103,000 2,103,000
Fuel consumption of wind-diesel system (gal/yr) 1,560,000 1,527,000 1,499,000
Gross diesel fuel savings (gal/yr) 543,000 562,000 590,000
Energy loss correction factor 0.76 0.76 0.76
Net diesel fuel savings (gal/yr) 413,000 427,000 448,000
Net diesel fuel savings (%) 20% 20% 21%
Note: The results represent DNV-GEC’s current best estimate of the range of P50 values (the average
expected value, or the value below which 50% of the outcomes are expected to be found).
Table 7. Energy System Modeling Results, Five Vestas RRB PS600 Wind Turbines
Hub Height Wind Speed (m/s)
Description 7.5 8.0 8.5
Gross wind energy production (MWh/yr) 8,335 8,963 9,603
Gross wind turbine capacity factor (%) 31.7% 34.1% 36.5%
Excess electricity generated (MWh/yr) 600 700 800
Fuel consumption of diesel-only system (gal/yr) 2,103,000 2,103,000 2,103,000
Fuel consumption of wind-diesel system (gal/yr) 1,609,000 1,539,000 1,574,000
Gross diesel fuel savings (gal/yr) 493,000 563,000 528,000
Energy loss correction factor 0.76 0.76 0.76
Net diesel fuel savings (gal/yr) 375,000 428,000 401,000
Net diesel fuel savings (%) 18% 20% 19%
Note: The results represent DNV-GEC’s current best estimate of the range of P50 values (the average
expected value, or the value below which 50% of the outcomes are expected to be found).
It is expected that the wind power system will reduce diesel fuel consumption in Nome by 18%
to 21%, or an average of 375,000 to 450,000 gallons per year.
Nome Region Energy Assessment
DOE/NETL-2007/1284
Final Draft Report
March 2008
FINAL DRAFT
iii
Nome Region Energy Assessment
DOE/NETL-2007/1284
Final Draft Report
March 2008
NETL Contact:
Brent Sheets
Manager
Arctic Energy Office
Prepared by:
Charles P. Thomas–Research & Development Solutions, LLC(RDS)/SAIC
Lawrence Van Bibber–RDS/SAIC
Kevin Bloomfield–RDS/SAIC
Tom Lovas–Energy & Resource Economics
Mike Nagy–ENTRIX
Jeanette Brena–ENTRIX
Harvey Goldstein–WorleyParsons
Dave Hoecke–ENERCON
Peter Crimp–Alaska Energy Authority (AEA)
David Lockard–AEA
Martina Dabo–AEA
National Energy Technology Laboratory
www.netl.doe.gov
FINAL DRAFT
v
NOME REGION ENERGY ASSESSMENT
EXECUTIVE SUMMARY
The purpose of this assessment is to present an analysis of technologies available to the City of
Nome for electric power production. Nome is a city of 3,500 people located on the Bering Sea
coast of the Seward Peninsula 539 air miles northwest of Anchorage, 102 miles south of the
Arctic Circle and 161 miles east of the Russian coast.
Typical of most of Alaska’s rural communities, Nome is totally dependent upon diesel
generators for electricity. The current load range for the city is 1.8 MWe to 5.2 MWe (yearly
average of 3.35 MWe). All power is supplied by diesel generation. Diesel fuel is also required
by the residents for residential and commercial space and water heating. The addition of
industrial activity, the Rock Creek Mine, increased the load by about 9 MWe for an average load
of 12.35 MWe. The mine, which began initial operations in late 2007, is estimated to be in
operation for 7 to10 years.
Recovered heat is currently used for heating the plant site and the potable water system for the
City. The diesel generators require 1.8 to 2.0 million gallons of fuel each year. The consumer
power rate has held steady in Nome since 2001. It ranges from $0.165 to 0.185/kWh
depending upon usage. However, the fuel surcharge has risen to $0.075/kWh in 2006, making
the current effective rate from $0.24 to 0.26/kWh. The continuing increase in diesel fuel costs
has caused the City to look at alternative power sources to offset the total reliance on diesel.
Scope and Approach
Alternatives to the city’s dependence on diesel generators analyzed in this assessment are:
• A barge-mounted coal-fired power plant using coal from: (1) the Usibelli mine near
Healy, AK and transported by rail to Seward, AK and then by barge to Nome; or (2)
British Columbia coal transported by barge to Nome.
• Wind power with the wind turbines located on Anvil Mountain approximately 1 mile north
of Nome.
• Geothermal power plant at Pilgrim Hot Springs located 60 miles north of Nome with a
power transmission network to Nome.
• Natural gas from the Norton Sound delivered to Nome from a sub-sea development with
a pipeline to shore and conversion of one of the new diesel engines to burn natural gas.
Tidal/wave energy, hydroelectric dams, and coalbed natural gas were also considered, but
these options did not appear viable and were not included in the final analysis. Tidal/wave
energy technology is less mature than the other technologies considered and its applicability at
Nome could not be assessed under current budget restrictions. The hydroelectric power option
was not considered feasible and was not analyzed. Coalbed natural gas is not expected to be
present in the vicinity of Nome and was not evaluated beyond some initial inquiries.
Coal resources are known to exist on the Seward Peninsula, specifically at Chicago Creek on
the north side of the Seward Peninsula and other coal resources are known to exist on the
Seward Peninsula and in the Northwest. However, none of the Northwest Alaska resources are
being actively mined and would require significant capital investment to start operations. This
start-up cost would not be justified to supply coal for a small power plant. Hence, the coal plant
design and economics contained within this report are based on coal available from within
Alaska and from British Columbia.
FINAL DRAFT
vi
Infrastructure requirements, environmental regulations and the status of technology
development for the coal plant, wind, geothermal, and natural gas options were assessed and
compared with the existing diesel generation system on an equivalent economic basis.
Economic Results
The economic analysis model calculates the total cost of providing electric power to the Nome
Joint Utility electrical distribution system (the “busbar cost”). Total cost is the cost of all capital
and operating costs, including distribution and administrative costs, and the cost of providing
heat energy on a Btu basis to residential and commercial residents. The analysis runs for thirty
years, from 2015 to 2044. All existing electrical and thermal loads currently served by the
system are treated as firm; that is, fully and continuously supplied throughout the period. A
reasonable expectation of electrical load growth over the 30-year period is included to account
for increases in population and economic activity of the city.
For each alternative case, the model estimates the electrical load requirement for each day of
the year and computes how much energy is supplied by the primary generation source (e.g.,
diesel, coal, wind/diesel, geothermal, or natural gas). It also estimates how much must be
delivered from diesel units as a backup resource. The model calculates the net present value of
all annual costs, including current system fixed costs and the carrying cost of investments in
new resources, to determine the total system life-cycle cost of power to the utility. The present
values for each energy option are shown in Table 1.
Table 1. Present Value of Busbar Electricity, $Millions
Present Value of Busbar Electricity, $Millions
Scenario Diesel
Cost
Escalation Diesel
System
Wind &
Diesel Geothermal Coal @
$63/ton
Coal @
$78/ton
Natural
Gas
Mid 116 111 90 134 117 107
High 140 128 92 137 120 107
Present Value Savings Residential/Commercial Heat, $ Millions
Mid 5
High 13
The model also computes the approximate average electric rate necessary to cover each year’s
annual cost of providing electrical service, which includes estimated distribution and
administration costs, based on recent financial statistics. The savings to residential and
commercial consumers from an alternative source of heating fuel is estimated on a per Btu
basis for the natural gas option. The average electricity rates for each energy option are shown
in Table 2.
FINAL DRAFT
vii
Table 2. Average Electric Rates and Space Heating Rates
Year 2015 2020 2025 2030 2035 2044
Avg.
2015
to
2044
Diesel System $/kWh
Mid-range diesel escalation 0.30 0.31 0.31 0.31 0.31 0.32 0.31
High-range diesel escalation 0.30 0.32 0.34 0.36 0.38 0.43 0.36
Coal Scenarios
Coal $63/ton, Mid-Range Diesel 0.35 0.34 0.33 0.32 0.32 0.31 0.33
Coal $63/ton, High-Range Diesel 0.35 0.34 0.33 0.32 0.32 0.33 0.33
Coal $78/ton, Mid-Range Diesel 0.32 0.31 0.30 0.29 0.29 0.28 0.30
Coal $78/ton, High-Range Diesel 0.32 0.31 0.30 0.29 0.29 0.30 0.30
Wind/Diesel
Mid-Range Diesel escalation 0.30 0.30 0.30 0.30 0.30 0.30 0.30
High-Range Diesel escalation 0.30 0.31 0.32 0.33 0.35 0.39 0.34
Geothermal
Mid-Range Diesel escalation 0.29 0.28 0.26 0.25 0.24 0.24 0.26
High-Range Diesel escalation 0.29 0.28 0.27 0.26 0.25 0.25 0.26
Natural Gas
Mid-Range Diesel Escalation 0.32 0.31 0.29 0.28 0.27 0.27 0.29
High-Range Diesel Escalation 0.32 0.31 0.29 0.28 0.27 0.28 0.29
Natural Gas Water and Space Heating—Relative Costs ($/MMBtu)
Mid-Range Diesel Escalation 24 24 25 26 26 27 25
High-Range Diesel Escalation 24 26 28 31 33 39 31
Natural Gas 25 24 23 22 21 19 22
All costs are expressed in real dollars that have purchasing power at a constant reference point,
in this case 2007.
Diesel fuel cost increases in real terms (i.e., price increases over and above general inflation
rates) are the same in all scenarios. For the purposes of estimating future costs of diesel fuel,
the Alaska Energy Authority (AEA) prepares projections of delivered fuel prices for a number of
locations in Alaska, including the city of Nome. These projections are used for analysis of a
variety of energy issues throughout the state, including evaluation of wind-diesel hybrid systems
and other alternative generation options. For consistency with statewide energy planning, the
diesel fuel rate of change over time (other than general inflation) for the city of Nome was drawn
from the Alaska Energy Authority estimates and applied to the price of diesel delivered to Nome
in 2007.
FINAL DRAFT
viii
• Diesel Fuel Initial Price: $2.54/gal
• Diesel Fuel Escalation (real)
Mid-Range case 0.58%/yr
High-Range case 2.12%/yr
These diesel fuel escalation rates result in estimates of diesel costs of $3.00/gal by 2044 for the
mid-range case, and to as much as $4.67/gal in the high-range case. A low-range case, which
assumes an average decline in diesel prices of over 1%/yr over the AEA analysis period, was
not examined for the purposes of this screening analysis.
The net present values are derived with a real discount rate of 4%, corresponding to the
effective interest rate for borrowing by municipal electric systems such as Nome.
For each case, the life-cycle cost of providing electricity is the discounted present value of all
annual costs for the 30-year period of analysis. In the natural gas case, where natural gas is
made available for utility requirements, a net present value is estimated for the electric utility
that compares directly with other electric production options, and a separate estimate is
provided for the savings from the availability of natural gas for space and water heating,
Diesel System
The generating efficiency of the two new units recently installed by the Nome Joint Utility
System will average 16 kWh/gallon of diesel fuel, an efficiency that is expected to remain
unchanged year-to-year, so diesel consumption will vary directly with changes in electric load
requirements. For the Nome system in 2006, with fuel costs at an average of $1.99/gallon,
diesel fuel constituted 50% of the average cost of electricity in Nome. The cost of fuel used for
generation reached $2.54/gallon (Nov. 2007), significantly increasing the share of electricity
costs attributable to generation.
The fixed costs of the generation facilities are “sunk costs” that will not be diminished by the
addition of alternative generation facilities. Those fixed costs, along with administrative
expenses are assumed not to vary with load changes and are held at a constant level
throughout the analysis. Distribution system costs, however, will likely vary as system loads
increase, due to the need to add and maintain new services. Distribution system costs are
estimated on a per kWh basis. The total cost of distribution system ownership, operation and
maintenance will increase as the distribution load increases.
The results of the economic analysis for the operation between 2015 and 2044 of the diesel
generation system installed at Nome indicate system operating costs of between $116 million
in present value under the expectations of a mid-range diesel fuel cost escalation to $140
million present value under conditions of a high-range escalation of diesel fuel costs.
The results indicate that the existing diesel system is fully available to meet energy
requirements for the electric system at a stable cost, net of fuel cost increases. The greatest
risk to the system is the potential variability in the cost of diesel delivered to Nome, or the
additional or extended load requirements associated with local mining activities.
Wind-Diesel System
As part of this analysis, the Alaska Energy Authority (AEA) performed an analysis of the
availability of wind energy to supplement the existing diesel generation. .A wind generation
system of 3 MW, consisting of two 1.5 MW units installed on Anvil Mountain near Nome
appeared to provide annual electric energy at a cost slightly less than the current cost of diesel
generation. The wind source, however, is intermittent and provides energy as a function of wind
FINAL DRAFT
ix
velocity rather than electricity requirements, and cannot be relied upon for energy at any
particular point in time. Integrating wind units with diesel generation systems requires
specialized control systems that respond to the variation in wind energy production and electric
load requirements to ensure that maximum efficiency is made of the combination of wind and
diesel units.
The wind turbine installation is expected to provide about 8,988 MWh/year or about 30% of the
initial year load of the Nome electric system. For the purposes of the economic analysis, it was
assumed that the energy provided by the wind turbines will be contributed throughout the year,
displacing that amount of diesel generation each and every year of the analysis period. Nome’s
new power plant controls were designed to integrate alternative and intermittent sources so no
additional costs for integration hardware and software are expected to be required for the two
wind turbines of 1.5 MW each.
Adding wind turbine capacity adds cost to the system. Thus, the installed cost of $4,000/kW is
recovered in electric rates over the analysis period, as well as the expected fixed operating
costs of 3% of the installed costs and variable operating costs of slightly less than 1 cent/kWh.
Initially, the installation of new wind turbines is expected to require 1 additional staff member to
adequately maintain the wind system.
The installation of two 1.5 MW wind turbines near Nome, producing at a 34% capacity factor
that offset diesel generation, results in system operating costs for the 30-year period of $111
million in present value under conditions of a mid-range escalation in diesel fuel costs. In the
case of high-range escalation in diesel fuel costs, the total present value would increase to $128
million. In both cases, the total cost of providing electricity under these assumptions is several
million dollars less than the cost of continuing to operate the system with only diesel generation.
If green tag sales are available and successful at the time of installation and throughout the life
of the wind system approximately $4.7 million in credits may contribute to a further reduction in
the cost of electricity to the residents
With proper siting and mitigation measures, most impacts from wind energy development would
be negligible. Obtaining required permits in accordance with federal and state regulations is
anticipated to be routine.
Geothermal System
A geothermal installation located at Pilgrim Hot Springs, approximately 60 miles north of Nome,
was evaluated as an option with the potential to displace a very large portion of the diesel
generation in the initial years of operation. The analysis, described in Section 6, suggests the
possibility of a 5 MWe geothermal installation providing about 41,600 MWh/yr, 33% more than
required in 2015. The generating capability of the geothermal facility is just slightly less than the
41,633 MWh/year expected to be required in 2044.
If successfully developed, the geothermal facility can provide nearly all of the electric load
requirements, and with the load shape of the electric system, maintenance activities can be
scheduled during low load periods without significantly impacting system operating costs. The
existing diesel system will be available for backup service in the event of unscheduled outages
or transmission failures. Further, the existing diesels will be available to meet short-term and
intermittent peaking requirements (although a diesel generating unit may be selected to operate
during high load periods for reliability, but not necessarily economic, purposes).
The installed cost of the geothermal system, including all exploratory activities, construction
costs and the transmission system to interconnect with Nome, is assumed to be $12,800/kW for
a system with a lifetime of at least 30 years. A geothermal installation, while generally robust,
will require specialized staff to operate and maintain the installation, increasing personnel costs,
FINAL DRAFT
x
particularly in the initial years of operation (and perhaps toward the later years), while the
increase in miles of transmission lines may increase line worker requirements. For the
screening analysis, two additional staff members are estimated to be required over the analysis
period, but it may be possible that generation facility staff currently operating the diesel system
could be redeployed. The diesel system must be maintained for backup (or high load reliability
service), and some personnel will remain assigned to the power house.
The geothermal operating costs would consist primarily of manpower and supplies. Very little is
currently known about the cost of operating and maintaining a geothermal facility of that
magnitude in the Nome region, but information from other geothermal investigations suggests
that annual supplies, such as chemicals, lube oil, etc. will amount to about 1.5% of the installed
cost of the facility. That cost is considered a fixed annual cost recovered in power rates in
similar fashion to the acquisition cost.
The displacement of the diesel generation with a geothermal power source eliminates, for the
most part, the availability of water-jacket heating for the Nome city water supply. Consequently,
in the early years of the geothermal scenario, the city water heat is assumed to be supplied by
the direct-fired boilers. In later years, as more supplemental diesel generation will be required,
the diesel engines will contribute to the city water heating load.
Installation of a geothermal power generation facility at Pilgrim Hot Springs would significantly
reduce the cost of electricity for the Nome Joint Utility System. The cost for 30 years of energy
supply to Nome would drop to $90 million in present value with a mid-range diesel fuel cost
escalation and to $92 million for the high-range diesel cost escalation. Generation costs
increase in the latter years as a result of the increasing component of diesel generation as loads
increase, and the contribution of geothermal energy declines as a proportion of generation.
The low cost associated with the geothermal option must be weighed against the risk that the
geothermal resource will not prove to be adequate to support the generation capability of
scenario described.
The lack of a steam phase in binary geothermal power systems prevents the airborne release of
CO2 and other gases, which remain in solution and are reinjected back into the reservoir to help
sustain resources. The permitting process should only involve standard permits related to land
use.
Coal Plant
A conceptual design was completed for a barge-mounted coal plant that would provide 4.655
MW of coal-fired electrical power to the city upon installation in 2015. A barge-mounted coal
plant has the advantage that it could be constructed in an existing ship yard in the Lower 48,
tested, and then towed to Nome reducing on-site construction time and costs. In addition to the
coal plant capability, the design of barge mounted system includes a 1 MW diesel generation
unit for startup power and auxiliary loads in order to accomplish a self-contained system. For
the purposes of the Nome system evaluation with the addition of a barge-mounted coal plant,
the diesel unit will provide only a backup power source for black-start conditions or other system
emergencies and not be routinely operated or included in the net capability.
Other than the estimated capital cost ($14,100/kWe based on the 4.655 MWe output only), the
most significant cost element for the evaluation of a coal plant in Nome is the fuel cost. The fuel
cost of the coal system is a function of the delivered cost and quality (i.e., heat content) of the
coal and the efficiency of the coal boilers. The coal units were designed to accommodate a
variety of coal, but with emphasis on the character of the coal available within Alaska. The
Usibelli coal source in central Alaska provides an available source of coal at a somewhat lower
cost than coal obtained elsewhere, but it has a heat, or energy, content lower than some other
FINAL DRAFT
xi
coals. Coal obtained in British Columbia that is readily transportable to Nome will have a higher
cost and heat content than the coal currently available in Alaska. Usibelli coal is estimated to
cost $63/ton delivered to Nome, whereas British Columbia coal is estimated to cost $78/ton.
Considering the Btu content of the coal, the British Columbia coal will provide for the needs of
the plant at $2.82/MMBtu. Usibelli coal on an equivalent basis will cost about $4.06/MMBtu.
Coal unit net efficiency (electric output/coal input) is a function of a variety of factors, most
notably the size of the units relative to the auxiliary loads. The operation of boiler feed water
pumps, fans and other ancillary equipment will have a significant impact on the net efficiency in
converting the energy of coal into electric power. The barge-mounted coal system designed for
the Nome installation has a net efficiency of 16%, which is relatively low compared to larger
coal-fired power plants in operation or planned for construction.
Regardless of the source of coal, the delivered cost is estimated to remain constant in real
terms, including transportation. Coal price projections available for review have indicated a
trend of stable prices for both the commodity and transportation for the foreseeable future as a
result of supply and demand characteristics worldwide. Consequently, no real increase is
expected above general inflation for coal delivered to Nome.
The barge-mounted coal fired generation alternative introduces a cost of production that will
vary dramatically as a function of the assumptions regarding the coal fuel purchased and
delivered to the Nome location. Assuming Usibelli coal at $63/ton delivered, the cost of
operating the system for 30 years will be $134 million in present value under conditions of mid-
range diesel fuel escalation. With the same coal fuel, but a presumed high-range escalation of
diesel costs, the present value cost of operating the system rises to $137 million.
If British Columbia coal at $78/ton is assumed to be used to fuel the coal generation facility the
present value for the midrange case will be about $117 million and high-range case will be
about $120 million.
The displacement of the diesel generation with a coal plant eliminates, for the most part, the
availability of diesel unit water-jacket heating for the Nome city water supply. The coal plant,
however, would be capable of providing a source of heat to replace that provided by the diesel
units if a steam or hot water interconnection is constructed between the coal plant and the
existing power house. In the absence of an interconnection, the city water heating requirement
would need to be supplied by the direct-fired boilers. In later years as more supplemental diesel
generation is required, the diesel engines could contribute to the water heating load.
The diesel fuel required by the direct-fired boilers to provide the heat required for the city water
system is estimated to cost $6 million in present value for the mid-range escalation case and $7
million for the high-range case. A steam line that could be installed and operated at a lower
cost over the 30-year period for installation and ownership would provide additional benefits to
the coal scenario. A withdrawal of steam from the coal plant at the rate required would,
however, introduce a loss of about 2% of the coal plant’s electric capability and result in more
supplemental diesel generation.
As long as the project can avoid triggering Hazardous Air Pollutants (HAP) major status (10 tons
per year (tpy) of a single HAP or 25 tpy of multiple HAPs), then the permitting process and
applicable limits associated with operation of a coal-fired boiler would be relatively
straightforward with no red flags. In this instance, the boiler would not be subject to the boiler
maximum achievable control technology (MACT) because it was not HAP major, and it would
not be subject to the Clean Air Mercury Rules since it would be rated at only 4.655 MWe.
Because coal will be stockpiled from one delivery per year, the Alaska Department of
Environmental Conservation will most likely require reasonable precautions to prevent
FINAL DRAFT
xii
emissions of particulate matter (e.g., fugitive dust). Coal slag and fly ash from the boiler and
elemental sulfur could be disposed of at an approved landfill or monofill. Mercury content of
slag and fly ash could become a regulatory issue for reuse or disposal in the future.
Permitting as described in Section 7 will be required for siting, water use, etc. but is expected to
be straight forward.
Natural Gas
An entirely new fuel source for Nome is potentially possible from a Norton Sound natural gas
drilling and production investment, described in Section 6. Successful exploration and
development of a Norton Sound resource would provide for both the electric energy needs and
the space and water heating requirements of the community. The economic analysis of the
natural gas scenario requires consideration of the investment costs of the natural gas system,
both to deliver fuel to the utility, and to the commercial and residential business sectors. In
addition to the investment in the system of production and delivery, costs will be incurred to
convert generation units to operate on natural gas, as will space and water heating equipment.
The assessment includes an evaluation of the shared costs of the investment in the off-shore
production facilities and pipeline costs for delivery to the city gate. Of the total investment of
$62.7 million overall required to provide the fuel supply, $56.2 million will be committed to the
installation of the production and primary delivery systems. Annual fixed costs estimated at $4
million/year associated with the operation of the system and variable operating costs will add
significantly to the costs, such that initial-year total costs of the production and primary
transmission of gas are estimated at $7.3 million. These costs are assumed to be shared
between the electric utility and the gas distribution system customers on the basis of the relative
shares of natural gas volumes consumed for each purpose.
A distribution system to provide access to gas, along with the conversion of heating equipment
from fuel oil to natural gas, is estimated to cost about $4.2 million and require about 1.0% of that
amount in annual variable operating costs for maintenance and repairs. All of the annual costs
of the distribution system are assumed to be paid by the users of the commercial and residential
service.
For the electric utility to operate on natural gas, it is assumed that one of the newest installed
units will be changed out for a unit that will operate on natural gas. Each of the two recently
installed diesel units will provide 5.2 MW of electrical energy, individually meeting nearly all of
the energy requirements of Nome. For the purposes of screening, the analysis assumes that all
of the annual electrical energy is provided from natural gas, while some diesel fuel will
undoubtedly continue to be required for emergency purposes and during short periods of natural
gas unit outages. An investment in a second unit to operate on natural gas would add a modest
cost to the analysis, or about $2 million.
A $2 million investment represents about 787,000 gallons of diesel fuel, enough to produce over
400,000 kWh of electricity each year, providing for several outage days a year during low load
periods. If the natural gas system proves feasible, the change out of an additional unit may be
appropriate, since other units will remain in place to operate on diesel fuel for emergency
purposes.
A significant economic factor associated with the investment in a natural gas system is that the
sole cost of the natural gas for the utility and other users will be embodied in the capital and
operating costs of the production and delivery systems. There are no taxes or commodity costs
assumed for the volumes of gas delivered by the system by which to compare directly with the
cost of diesel fuel that is sold on a gallon-by-gallon basis. Consequently, unlike the electric
FINAL DRAFT
xiii
utility for which average power costs may be compared, the economic evaluation of the space
and heating requirement is a comparison of the relative cost of thermal energy on a Btu basis.
The installation of a natural gas system allows the displacement of nearly all diesel fuel used by
the Nome electric utility system. The present value of system operating costs includes full
recovery of all investment costs necessary to both obtain and deliver natural gas.
For the electric system, the present value of the busbar cost of electricity using natural gas fuel
is estimated at between $107 million. This is about $10 million less than operating the diesel
system at mid-range fuel escalation, and about $33 million less under a high-range escalation
assumption. Different assumptions of diesel cost escalation for the system operating on natural
gas has very little effect on the economics, because so little diesel generation is likely to occur
until late in the analysis period. (Only emergency and maintenance requirements will be met
with diesel.) Thus, electric rates between the mid-range and high-range cases will be nearly
identical until the last few years.
The permitting process and applicable limits of a gas-fired engine or turbine would be relatively
straightforward with no red flags. However, caution should be used when selecting a turbine to
ensure compliance with the federal limit.
Natural Gas Space Heating
The installation of a natural gas system for Nome would provide a source of fuel as an
alternative to diesel fuel for the provision of commercial and residential space and water
heating. The economic evaluation of the impact of the installation of the gas system indicates a
present value savings for the thermal requirements for space and water heating, in the instance
of a mid-range fuel price escalation, of about $5 million. Under a high-range cost escalation,
the economic benefit to the community will reach slightly more than $13 million. The impact on
heating consumers is described in terms of the cost per Btu for energy providing space and
water heat and is shown in Table 2.
Conclusions
The energy technologies analyzed for Nome fall into two categories, (a) technologies that rely
upon known energy resources—diesel, wind, and coal; and (b) technologies that would rely
upon hypothetical (or untested) resources—geothermal and natural gas. Geothermal and
natural gas resources are known to exist based on limited evaluation, but will require expensive
exploration to prove the resources exist in sufficient quantity and deliverability to meet the
requirements. The exploration and development costs for geothermal and natural gas are not
well established and will require additional analysis to confirm the estimates. The natural gas
options assumed that a drill ship would be available at day rates only and that the costs to
obtain and move a ship to and from Norton Sound would not have to be borne by the project.
The present value comparisons indicate that for the assumptions incorporated in the analysis
regarding each of the alternatives, the wind/diesel, geothermal plant, barge-mounted coal plant
using high BTU coal, and natural gas exploration and development are all economically equal or
better than continued reliance on diesel for both mid-range and high-range diesel price
escalation. The lower Btu coal option is slightly better in the instance of a high-range diesel
price escalation. The development of a natural gas resource, in addition to showing a strong
potential for savings in the operation of the electric utility, would provide an economical option
by providing natural gas for water and space heating throughout the community.
Of the alternatives investigated, the most likely prospect of immediate savings gain is the
installation of wind turbines to offset diesel generation for the electric utility. Wind units are
FINAL DRAFT
xiv
commercially available, and the Nome utility system has already anticipated the advent of wind
by including integration capability in the construction of the new power house.
The geothermal and natural gas prospects both indicate potential savings greater than the wind
resource, but will require additional investment in exploration and development to verify the
resource potential. Nevertheless, the potential gain from each is significant, with the natural gas
prospect in particular providing the additional benefit of displacing fuel oil for space and water
heating.
The coal plant prospect with high-Btu coal provides savings to the electric system, but to a
lesser extent than the other alternatives. With low-Btu coal, savings would only be available
under a high rate of diesel price escalation, and under conditions of coal prices remaining
constant in real terms. In either case, the savings associated with the prospect of a coal power
plant are based on an engineering estimate of costs to construct an initial unit. Economies of
scale from construction of multiple units of a similar design could reduce the capital cost of the
system and improve the economics of a coal-based alternative.
FINAL DRAFT
5-1
5 WIND RESOURCES
5.1 INTRODUCTION
Excellent wind resources are known to exist very near Nome at Anvil Mountain and the potential
for offsetting a major portion of the diesel fuel used for power generation in a cost effective
manner by developing this resource is described in this section.
5.2 ELECTRICAL LOAD PROFILE
The electric load profile was generated by importing hourly load data provided by the Nome
Energy Assessment Group into the economic optimization software HOMER, developed by the
National Renewable Energy Laboratory.1 A graphic overview of year 2007 is show in Figure
5.1.
Figure 5.1. Hourly load profile for year 2007
1 https://analysis.nrel.gov/homer/includes/downloads/HOMERBrochure_English.pdf
FINAL DRAFT
5-2
The monthly scaled averages for 2007 are shown in Figure 5.2.
Figure 5.2. Nome scaled averages for year 2007
A scaled daily profile for year 2007 is shown in Figure 5.3.
Figure 5.3. Nome scaled daily load data for year 2007
FINAL DRAFT
5-3
5.3 WIND RESOURCE
In September 2005, wind monitoring equipment was installed in Nome on Anvil Mountain. The
purpose of this monitoring effort is to evaluate the feasibility of utilizing utility-scale wind energy
in the community (Dolchok 2006). The site is described in Figure 5.4.
Figure 5.4. Nome Anvil Mountain Site summary.
A one-year synthesized wind-data set was developed by filling the data gaps due to icing by
using probability methods that calculate the most likely scenario for this time period.
The site has the following beneficial factors:
The potential wind site is in slightly mountainous terrain, which enhances terrain induced
wind acceleration from certain wind directions.
Existing roads and transmission lines are in the proximity of the site.
No living quarters or other housing within a safe ice-throw distance (≥250m) (Bossani
and Morgan 1996).
Visible intrusion is assumed to be minimal from main developments. Viewshed analysis
has to be performed to confirm.
FINAL DRAFT
5-4
A topographic map indicating the Met-tower location is shown in Figure 5.5.
Figure 5.5. Nome–Met Tower location, Anvil Mountain
FINAL DRAFT
5-5
A map that combines high-resolution wind modeling results with topographic information is
shown in Figure 5.6. The red marks indicate potential turbine locations.
Figure 5.6. Nome—High Resolution wind map, Anvil Mountain
FINAL DRAFT
5-6
Color coding for the high resolution wind map is shown in Figure 5.7
Figure 5.7. High Resolution wind map color coding
Wind Speed 70m
Wind Class 1 - Poor ( < 5.8 m/s)
Wind Class 2 - Marginal ( 5.8 - 6.7 m/s)
Wind Class 3 - Fair ( 6.7 - 7.4 m/s)
Wind Class 4 - Good ( 7.4 - 7.9 m/s)
Wind Class 5 - Excellent ( 7.9 - 8.5 m/s)
Wind Class 6 - Outstanding ( 8.5 - 9.2 m/s)
Wind Class 7 - Superb ( >9.2 m/s)
The collected data were evaluated with the Windographer software.2 An unfiltered wind
probability profile is shown in Figure 5.8. Icing events appear as calm periods.
Figure 5.8. Nome Anvil Mountain wind probability profile.
2 Mistaya Engineering Inc. http://www.mistaya.ca/products/windographer.htm
FINAL DRAFT
5-7
A wind frequency rose is shown in Figure 5.9.
Figure 5.9. Nome Anvil Mountain wind frequency rose.
FINAL DRAFT
5-8
During the monitoring period, time periods with severe icing occurred. The collected data
showed time gaps with no events recorded, attributable to ice coated sensors. In Figure 5.10
the ice built-up on the Met-Tower is shown.
Figure 5.10. Nome Anvil Mountain, Met-Tower after icing event.
In order to obtain a more complete picture of the wind resource, it is recommended that a 60 to
80 meter ice-rated Met-tower be installed to measure wind speed at the hub height of large size
wind turbines. The data collection period is recommended to be at least twelve continuous
months. The current data collection at 30 meters will most likely not satisfy the needs for an
industry standard wind feasibility study for large size wind turbine development.
FINAL DRAFT
5-9
5.4 WIND MODELING
5.4.1 GENERAL INFORMATION
The wind modeling was performed using a Clean Energy Project Analysis Software from
RetScreen 3 and provided data which was then used to develop the comparative economics
described in Section 8. For the purpose of this screening report, no optimization between
different wind-diesel system designs was performed due to different integration design
possibilities such as available equipment and its costs, controls, switchgear, and
interconnection.
A detailed engineering study is necessary to evaluate the feasibility, costs, and performance of
an integrated wind-diesel system. This is outside the scope of this study.
For maximum utilization of investment only the high penetration scenario is described. This
increases the complexity and integration cost compared to a medium or low penetration system.
However, it is assumed that the increased wind absorption rate and resulting diesel fuel savings
will justify the higher cost for integration. The cost estimation for the different integration
controls (low, medium, high penetration) are outside the scope of this study. For preparation of
a final design study the different scenarios should be taken into consideration and a cost
comparison should be made.
5.4.2 WIND RESOURCE
An annual average wind speed of 6.0 m/s at 10 meter (class 5) was used to conservatively
compensate for uncertainty in the high-resolution wind map and the monitoring data gaps. The
wind speed distribution is calculated as the Weibull probability density function. A wind shear
component of 0.16 was estimated to take moderate rough terrain features like hills or cliffs into
account. The model calculated the average wind speed at hub height to be 8 m/s with a wind
density of 580 W/m2.
5.4.3 ATMOSPHERIC CONDITIONS
The standard atmosphere of 101.3 kPA was used for modeling, although local average pressure
data are likely to be more favorable for wind density.
The annual average temperature of 27.1°F or -3°C was used. 4
5.4.4 SYSTEM CHARACTERISTICS
Several models runs were performed by AEA. The recommended wind generation system was
a 3 MW central-grid system using two 1.5 MW or similar-sized turbines. A project life of 20
years for the wind turbines was used.
The model calculates the wind plant capacity factor (%), which represents the ratio of the
average power produced by the plant over a year to its rated power capacity. It is calculated as
the ratio of the renewable energy delivered over the wind plant capacity multiplied by the total
hours in a year. The wind plant capacity factor will typically range from 20 to 40%. The lower
end of the range is representative of older technologies installed in average wind regimes while
the higher end of the range represents the latest wind turbines installed in good wind regimes.
A wind farm capacity of 34% is used in the economic assessment.
3 http://www.retscreen.net/ang/d_o_view.php
4 http://climate.gi.alaska.edu/climate/Temperature/mean_season.html
FINAL DRAFT
5-10
5.4.4.1 WIND TURBINES
The power curve for the wind turbine was modeled after the specifications of the GE 1.5se
turbine with a hub height of 65 meters, a swept area of 3,904 m2, and a rotor diameter of 70
meters. The electricity output is 1,500 kW at a rated wind speed of 13 m/s. The cut-in wind
speed for this model is set at 4m/s and the cut-out wind speed is 25 m/s. The rotor speed is 12
to 22.2 rpm.
5.4.4.2 TURBINE LOSS FACTORS
Following turbine loss factors were taken into account:
Array losses: 5%
Icing losses: 10%
Other downtime losses: 5%
Miscellaneous losses: 10%
Total Losses: 30%
The current industry estimate for turbine loss factor is in the range of 15 to 33%.
5.4.5 COST DATA
The turbine costs are estimated to be $4000/kW installed. A recent study undertaken by the
Berkeley National Laboratory (Harper et al. 2007) states the installed cost for utility scale, grid
connected wind turbines in the U.S. market (lower 48) are $1,725 to $1,829 per installed kW.
The higher installed cost used in this evaluation is warranted due to Alaska’s high transportation
and construction cost according to wind developers in Alaska, and verified by AEA experience
with past wind projects. This assumption results in an initial capital cost for the 3 MW system of
$12 million.
The amount of displaced diesel was calculated by dividing the 8,992,503 kWh/year produced by
the wind generators by the diesel system efficiency number of 16 kWh/gal. This results in
displacement of 562,031gal/year.
The cost for operation and maintenance is a combination of fixed and variable cost. The fixed
cost used is 3% of installed cost and the variable cost is 0.975¢/kWh per year. These annual
costs are applied throughout the estimated project life of the wind turbines and include repair
and replacement costs. The variable cost was determined by applying a 5% annual increase of
1996 industry data of 0.65¢/kWh.5 Planners consider adding variable cost to take wear and tear
that increases with project life into account. The resulting annual operation and maintenance
cost is $447,677.
A price for environmental attributes, renewable energy credits or green tags, may be available.
The price for the green tag calculation is $0.03/kWh for 20 years. This price is based on price
information from Bonneville Environmental Foundation’s Denali Green Tag Program. 6 The
actual price depends on project parameters and can be negotiated in individual contracts. The
typical range is between $0.03 to $0.05/kWh.
5 http://www.awea.org/faq/cost.html
6 www.greentagsusa.org/greentags/denali.cfm.
FINAL DRAFT
5-11
5.4.6 TIME FRAME
Met-data collection: at least one year from starting point.
Site development: 1.5 years from starting point.
Turbine Selection/Procurement: 2 years from starting point.
Construction: 6 to 12 months from point app. 1.8 years after starting point
Final commissioning: 2 to 6 months after construction start.
Full commercial operation: App. 1 year after final commissioning.
5.4.7 GREENHOUSE GAS ANALYSIS
Green House Gas (GHG) emissions were calculated based on 100% energy mix of diesel #2
generation using the following default values:
CO2 74.1kg/GJ;
CH4 0.0020 kg/GJ;
NO2 0.0020 kg/GJ;
Fuel conversion efficiency 30%
To obtain a more accurate emission analysis, actual energy mix data have to be applied.
5.5 CONCLUSION AND RECOMMENDATION
Current turbine development in the wind industry is targeted to multi-megawatt wind generators.
For smaller applications the equipment choice is limited. Two emerging trends for the Alaska
market are visible.
One market sector supply caters towards used, refurbished wind turbines. These machines are
decommissioned at existing wind projects (‘Lower 48’ or Europe) and are remanufactured,
rebuilt, and often upgraded to meet modern standards. However, the lifetime of these re-
manufactured turbines is uncertain, since not enough performance data have been collected to
make a valid statement. The overall industry consensus is that the lifetime of a re-manufactured
wind turbine is about 15 years. Another uncertainty is the spare part supply and service
support. Vendors or re-manufactured turbines, in general, do not offer warranty contracts over
one year and service, technical support, and maintenance contracts are unusual. However
exceptions exist, warranty and service contracts are a negotiation point that should be
considered when re-manufactured turbines are the project choice.
The second market sector is the small to medium size wind turbine sector. Manufacturers offer
new turbines with warranty contracts between 1 to 2 years, and extended warranty periods of 5
years are negotiable. The spare part supply is usually guaranteed by the manufacturer
throughout the lifetime of the turbine, which ranges from 20 to 25 years. Service contracts and
technical support are available. The capital costs for these turbines are generally higher.
However, the levelized maintenance, replacement and repair costs are believed to be equal to
or lower than those of the re-manufactured turbines. Due to limited data a firm statement in
regard to the operation costs cannot be made. Operation and maintenance costs are in general
an uncertainty, especially with the limited data for Alaska installations.
Recently a commitment from a large turbine manufacturer was made to install 2 megawatt size
turbines in Alaska, on Kodiak Island. It is uncertain if this presence will guarantee the
deployment of additional large size turbines into the Alaska market and the necessary technical,
FINAL DRAFT
5-12
spare part, and service support for further machines. The application for these machines in
Alaska is limited due to electrical load demand requirements, construction equipment
requirements, and maintenance requirements. However, the selected large size wind turbines
for this screening report are believed to be an appropriate choice for Nome due to the relatively
large current and projected load demand as well as the local skilled workforce, a well run and
organized utility, and the ability to support large construction projects. However, special
attention should be given to the fact that Nome’s met data collection showed moderate to
severe icing conditions. This might limit the ability to obtain a large size wind turbine without
modifying the manufacturer’s standard model. Usually the offered cold climate packages are
not suited to withstand the climatic conditions of Nome. It will be dependent on the
manufacturer’s willingness to modify the standard turbine model and the structural limitations
thereof.
The number of installed turbines per project in rural Alaska applications can differ due to a
number of reasons. The intended installed capacity can usually be met with the choice of a
number of smaller turbines or one or two larger turbines. The benefit of fewer turbines is the
reduced cost of foundation, transmission line and construction time, to a limited extend. The
disadvantage is the risk of losing a higher percentage of electricity output if a turbine fails or
downtime occurs, than with a higher number of smaller turbines. The repair skill, spare part
availability, remoteness of location, complexity of system (medium or high penetration system),
and responsiveness of technical support are factors that have to be taken into consideration in
the decision making process. A good general rule of thumb is that the less certain the above
stated factors are, the recommendation is to install more, smaller turbines in order to avoid a
large percentage reduction of production capability.
Another important factor for wind-diesel installations in Alaska is the integration design and
integration controls. Low, medium, and high penetration systems are currently installed in
Alaska. Low penetration systems require only a minimum of control function on the diesel
generation side, but displace only a minimal amount of diesel. Medium penetration designs
require a more advanced level of integration and switchgear design and are capable of
displacing up to ~25% of the annual diesel consumption. High penetration systems are highly
complex designs that require experienced engineers and operators to develop a successful
wind-diesel system. It also displaces the largest amount of diesel. High penetration wind-diesel
systems are still in the pilot project phase and experience data for Alaska installations is
minimal.
When trying to determine the desired level of wind penetration in a specific village application
one must balance the potentially greater diesel savings of higher penetration systems against
the higher costs and risks associated with the greater complexity of the system. Local
conditions such as availability of skilled technicians and remoteness of location should help to
determine where along the risk/reward continuum a project should be selected.
The owner and operator of the system as well as the utility have to be aware of the risk involved
in installing a high penetration system in a remote location in Alaska and have to evaluate the
benefits and disadvantages in terms of reliability and quality of energy supply, diesel savings,
and environmental attributes.
5.5.1 FURTHER STUDY NEEDS
If the comparison with other energy scenarios should be favorable for wind development in
Nome, the following studies are suggested before a final decision is made for implementing the
proposed wind generation system, or variations thereof:
Met-data collection with 60 to 80 meter ice rated tower
FINAL DRAFT
5-13
Detailed system integration design
Turbine availability for Nome including O&M options
Environmental assessment
Potential funding sources and/or business structure
Detailed economic and financial analysis
5.5.2 RECOMMENDATION
Based on the modeling results the preferred wind generation system would be comprised of two
1.5 MW or similar sized turbines. We think that wind development could potentially be
considered as a viable option for the citizens of Nome to displace a significant amount of diesel
fuel and thus have the potential to reduce the price of energy as well as the dependency on
diesel as a fuel source.
FINAL DRAFT
8-1
8 ECONOMIC EVALUATON OF POWER GENERATING OPTONS
Evaluating various energy alternatives involves technology, environmental factors and
economics. Previous sections of this report addressed the status of the various technologies
and the environment impacts of the alternatives. Central to the evaluation of competing
technologies is the economic value of generating useful energy from the various resources
available.
The economic analysis presented here examines the economic value of the alternatives by
comparing the impact on energy costs of the various power generating options identified for
Nome. The comparison is made by estimating the cost of providing energy from the alternatives
against the cost of using the existing generation, transmission and distribution system for
serving electric loads and providing thermal energy over the period 2015 through 2044.
8.1 OVERVIEW OF METHODOLOGY
The economic analysis model calculates the total cost of providing electric power to the Nome
Joint Utility electrical distribution system (the “busbar cost”). Total cost is the cost of all capital
and operating costs, including distribution and administrative costs, and the cost of providing
heat energy on a Btu basis to residential and commercial residents. The analysis runs for thirty
years, from 2015 to 2044. All existing electrical and thermal loads currently served by the
system are treated as firm; that is, fully and continuously supplied throughout the period. A
reasonable expectation of electrical load growth over the 30-year period is included to account
for increases in population and economic activity of the city.
For each alternative case, the model estimates the electrical load requirement for each day of
the year and computes how much energy is supplied by the primary alternative generation
source (diesel, coal, wind/diesel, geothermal, and natural gas). It also estimates how much
must be delivered from diesel units as a backup resource. The model calculates the net present
value of all annual costs, including current system fixed costs and the carrying cost of
investments in new resources, to determine the total system life-cycle cost of power to the
utility. The model also computes the approximate average electric rate necessary to cover each
year’s annual cost of providing electrical service, which includes estimated distribution and
administration costs, based on recent financial statistics. The savings to residential and
commercial consumers from an alternative source of heating fuel is estimated on a per Btu
basis.
The uncertainty associated with different expectations of the changes in the cost of diesel fuel
over time is treated by testing one or more expected annual increases in the price of diesel fuel
delivered to Nome. Other variations in assumptions may be tested, as well, to derive the
sensitivity of the results to changes in the fundamental variables.
All costs are expressed in real dollars that have purchasing power at a constant reference point,
in this case 2007. Diesel fuel cost increases in real terms—i.e., price increases over and above
general inflation rates - are the same in all scenarios. The net present values are derived with a
real discount rate of 4%, corresponding to the effective interest rate for borrowing by municipal
electric systems such as Nome.
For each case, the life-cycle cost of providing electricity is the discounted present value of all
annual costs for the thirty year period of analysis. In the natural gas case, where natural gas is
made available for utility requirements, a net present value is estimated for the electric utility
that compares directly with other electric production options, and a separate estimate is
provided for the savings from the availability of natural gas for space and water heating.
FINAL DRAFT
8-2
8.1.1 EXAMPLES OF THE MODEL CALCULATIONS
The economic model includes a number of basic steps. These steps are illustrated by the
following example for estimating the cost of providing electric power.
Assume the total firm load to be served on January 1, 2015, is four megawatts (4 MW) of
electricity measured at the bus bar–the point of interconnection with the transmission and
distribution system–and that the primary generation resource is diesel.
• The busbar energy requirement for that day is:
o 4 MW x 24 hours = 96 megawatt-hours (MWh), or 96,000 kilowatt-hours (kWh)
• The amount of diesel required is:
o 96,000 kWh / (16 kWh/gallon) = 6,000 gallons/day
• The cost of the fuel is:
o 6,000 gallons times $2.54/gallon = $15,240/day
• Additional variable operating costs (such as lube oil and overhauls) are:
o 96,000 kWh times $0.02 = $1,920/day
• The total variable cost of generation for this one day is:
o $15,240 + $1,920 = $17,160/day
The total variable cost for other days differs because more or less electricity is produced. The
model adds all of these daily variable costs together; the total variable cost for one year may
then be on the order of $5.5 million.
• The annual fixed generation cost is:
o $1,200,000 (for labor) + $500,000 (for generation equipment) = $1,700,000.
• Therefore, the total annual cost of generation for the year 2015 is $7.2 million.
If the annual cost of ownership and operation of the distribution system is $0.8 million, and the
annual cost of the administration of the system is $0.6 million, then the total cost of electric
service for the year is approximately $8.6 million.
• The total electric sales for the year are based on an annual energy load of 32,000 MWh:
o 32,000 MWh x 0.9 = 28,800 MWh
where the factor 0.9 accounts for the 10% losses between the point of generation and the
customers’ meters.
To cover the total cost of generation, the average electric rate for the system must be:
• $8,600,000 / 28,800,000 kWh = $0.30/kWh
Of this, $0.19/kWh is for the variable costs of generation (fuel, lube and overhaul) and the
remaining $0.11/kWh covers the fixed ownership costs of the generation, transmission and
distribution system, the distribution system operating costs, and all of the administrative
expenses attributable to providing electric service. In subsequent years, as the load grows and
costs increase, the electric rate may go up or down over time.
In the instance of an alternative fuel source for generation that will displace the current primary
use of diesel for electric generation, the model also considers the impact of sales of the fuel for
FINAL DRAFT
8-3
other purposes. Another simple example illustrates the steps in the model to evaluate an
impact of a natural gas alternative for generation that also may be used to displace diesel fuel
for commercial and home heating applications.
As before, a 4 MW load corresponds to 96,000 kWh of electricity to be generated daily.
The amount of natural gas required to provide generation for the kWh load is:
• 96,000 kWh x (7,653 Btu/kWh) (See Table 4.3) = 735 MMBtu per day.
Over the course of a year, the electric system natural gas requirement may reach as much as
238 Billion Btu just to meet the electric load requirements.
However, if the natural gas fuel is available, a portion of the gas may be available to displace
the fuel oil normally used for space and water heating. The residential and commercial fuel oil
used throughout the year must be estimated on an equivalent energy content basis.
The amount of natural gas that is required annually to displace the fuel oil needed for residential
and commercial space and water heating is:
• (683,000 gal/yr) x (138,000 Btu/gal) = 94 Billion Btu/yr;
Other potential heating loads may add a billion Btu or so a year, for a total natural gas energy
requirement of about 333 Billion Btu.
Delivery from a natural gas source to Nome, however, will require an investment in the
infrastructure to extract the gas from underground sources and deliver the natural gas to the
initial point of use. The annual carrying cost of the investment in the infrastructure, and the
variable cost of operating the natural gas system could reach $7.3 million, shared on the basis
of volume of gas required.
The annual cost for the availability of a natural gas supply source by user would be:
• Utility: $7.3 million x (238 B Btu / 333 B Btu) = $5.2 million,
• Res/Comm: $7.3 million x (95 B Btu / 333 B Btu) = $2.1 million.
In addition, the electric system would incur the capital cost of converting the generation
equipment to operate on natural gas, adding about $116,000/year of amortization expenses to
the cost of generating power. The variable generation cost for lube and overhaul of $0.7 million
would remain as in the earlier example, as would the $1.7 million for labor and other fixed costs,
for a total annual generation cost of $7.7 million. The electric distribution system costs and
administrative costs would add an additional $1.4 million for a total system cost of $9.1 million.
The average electric rate for the system to cover the total generation cost would be:
• $9.1 million / 28,800,000 kWh = $0.32/kWh.
For the commercial and residential natural gas users, the difference in cost between operating
on diesel fuel and natural gas can be expressed as the difference in dollars per Btu of energy
provided for space and water heating. Heating fuel must be distributed to the end user,
however, resulting in a higher cost than diesel supplied in bulk to the utility. And, since a
distribution system is required to deliver the natural gas to the end user, an investment in
distribution pipe and meters, and the equipment to convert existing water and space heaters will
result in an annual distribution system cost of about $285,000.
The average annual cost per Btu for fuel oil for the commercial and residential users is:
• (683,000 gal/yr) x ($2.50/gal + $0.75/gal) x 138,000 Btu/gal = $24/MMBtu.
FINAL DRAFT
8-4
The average annual cost per Btu for natural gas for space and water heating would be:
• $2.1 million + $0.3 million / 95 B Btu = $25/MMBtu
The actual year-by-year costs will vary with the relative change in costs of operating the system,
the growth in electric and natural gas requirements, and the expected increase in costs of fuels
supplied to meet the electrical and thermal loads.
8.1.2 ECONOMIC MODEL LIMITATIONS
The methodology of the economic analysis is a comparison of scenarios. The scenarios are
structured to identify the costs of operating the electric utility system and meet the electric
requirements of the Nome system over a period of time 30 years into the future. The annual
production and operations costs of the system are estimated for each year to obtain the present
value of the life-cycle costs for providing electricity and, in one case, fuel for commercial and
residential space and water heating. The scenarios compare current system operations
projected into the future with alternative generation or fuel opportunities.
A benefit of scenario analysis using the economic model is that the assumptions are clearly
defined and a clear comparison may be made of the benefits and costs between scenarios.
However, there are limitations. Some of those limitations are:
• The validity of each scenario depends on the validity of the assumptions.
• No probabilities are assigned to the outcomes of the scenarios, nor are a range of
probabilities provided for the assumptions (such as, for example, the success of a
natural gas drilling program).
• Feedback loops are not included, so there are no estimates of changes in electric or
thermal load forecasts as a consequence of changes in the cost of electricity or the price
of fuel for space and water heating.
• Other impacts to Nome, such as higher costs for delivery of smaller volumes of fuel, and
the resultant economic impact on users of diesel other than for electric power
production, are not considered.
• There is no explicit estimation of the risk associated with any of the scenarios, either
financial or economic.
The results obtained from the scenario analysis therefore provides an indication (“screening”) of
the relative economic value of the generation alternatives and alternative fuel source for the
Nome electric system and for space and water heating. The model is very effective as a system
for developing a ranking of alternatives. The limitations of the methodology, however, suggest
that further and more detailed investigation of any one scenario may be required prior to
investing in the development of any particular alternative.
8.2 ECONOMIC INTEGRATION
The basic assumptions for each of the energy options (diesel system, wind-diesel, geothermal,
coal plant, and natural gas) are described in this section.
8.2.1 NOME DIESEL SYSTEM ASSUMPTIONS
The electric generation system of Nome has recently been upgraded with two new generating
units and improved interconnection and auxiliary systems. With the advent of the new
generation facilities, the diesel-based system is expected to provide adequate capacity and
FINAL DRAFT
8-5
energy for the foreseeable future. With appropriate routine maintenance and periodic
overhauls, the existing units are likely to be available for operation throughout the entire period
of the analysis.
The generating efficiency of the new units will average 16 kWh/gallon of diesel fuel, an
efficiency that is expected to remain unchanged year-to-year, so diesel consumption will vary
directly with changes in electric load requirements. For the Nome system in 2006, with fuel
costs at an average of $1.99/gallon, diesel fuel constituted 50% of the average cost of electricity
in Nome. The cost of fuel used for generation reached $2.54/gallon (Nov. 2007), significantly
increasing the share of electricity costs attributable to generation
For the purposes of estimating future costs of diesel fuel, the Alaska Energy Authority (AEA)
prepares projections of delivered fuel prices for a number of locations in Alaska, including the
city of Nome. These projections are used for analysis of a variety of energy issues throughout
the state, including evaluation of wind-diesel hybrid systems and other alternative generation
options. For consistency with statewide energy planning, the diesel fuel rate of change over
time (other than general inflation) for Nome was drawn from the Energy Authority estimates and
applied to the price of diesel delivered to Nome in 2007.
• Diesel Fuel Initial Price: $2.54/gal
• Diesel Fuel Escalation (real)
Mid-Range case 0.58%/yr
High-Range case 2.12%/yr
These diesel fuel escalation rates will result in estimates of diesel costs of $3.00/gal by 2044 for
the mid-range case, and to as much as $4.67/gal in the high-range case. A low-range case,
which assumes an average decline in diesel prices of over 1%/yr over the AEA analysis period,
was not examined for the purposes of this screening analysis.
Other assumptions regarding the current electric system costs include the estimates of the new
unit maintenance on a “per/kWh” basis. The maintenance includes all routine lubrication and
component replacements over a 20-year maintenance cycle recommended by the
manufacturer. Effectively, the costs of operating the units in addition to fuel costs are recovered
on the basis of the energy produced rather than availability.
The fixed costs of the generation facilities are “sunk costs” that will not be diminished by the
addition of alternative generation facilities. Those fixed costs, along with administrative
expenses are assumed not to vary with load changes and are held at a constant level
throughout the analysis. Distribution system costs, however, will likely vary as system loads
increase, due to the need to add and maintain new services. Distribution system costs are
estimated on a per kWh basis. The total cost of distribution system ownership, operation and
maintenance will increase as the distribution load increases.
8.2.2 DIESEL SYSTEM ECONOMIC ANALYSIS RESULTS
The results of the economic analysis for the operation between 2015 and 2044 of the diesel
generation system indicate system operating costs of between $116 million in present value
under the expectations of a mid-range diesel fuel cost escalation to $140 million present value
under conditions of a high-range escalation of diesel fuel costs.
The average electric rates (2007$) are shown in Figure 8.1. The rates reflect the expected
increase in diesel prices. For the mid-range escalation of 0.58%, the increase in electric rates
FINAL DRAFT
8-6
from 2015 to 2044 is small, from $0.30 to $0.32/kWh as compared to the increase to $0.43/kWh
for the high-range escalation in diesel prices.
The results indicate that the existing diesel system is fully available to meet energy
requirements for the electric system at a stable cost, net of fuel cost increases. The greatest
risk to the system is the potential variability in the cost of diesel delivered to Nome, or the
additional or extended load requirements associated with local mining activities.
Figure 8.1. Diesel System–Electric Rates.
8.2.3 WIND-DIESEL SYSTEM ASSUMPTIONS
As a part of this study the AEA completed an initial screening analysis of the availability of wind
energy to supplement the current generating sources of the Nome utility. The results of the
screening analysis, described in Section 5, included an assessment of possible wind turbine
configurations available for the wind energy regime of Anvil Mountain, located just north of
Nome.
The results indicate that a wind system of 3 MW, consisting of two 1.5 MW units, could provide
electricity at a cost slightly less than the current cost of diesel based generation. The wind
source, however, is intermittent and provides energy as a function of wind velocity rather than
electricity requirements, and cannot be relied upon for energy at any particular point in time.
Integrating wind units with diesel generation systems requires specialized control systems that
respond to the variation in wind energy production and electric load requirements to ensure that
maximum efficiency is made of the combination of wind and diesel units. The load requirements
will have an effect on the operation and the choice of diesel units that may be dispatched to
meet the load unmet by the wind generators.
The wind turbine installation is expected to provide about 8,988 MWh/year or about 30% of the
initial year load of the Nome electric system. For the purposes of the economic analysis, it was
Diesel System: Average Electric Rates
0.20
0.25
0.30
0.35
0.40
0.45
201520172019202120232025202720292031203320352037203920412043real year 2007 $ per kWhDiesel $2.54, Mid-range escalation Diesel $2.54, High-range escalation
FINAL DRAFT
8-7
assumed that the energy provided by the wind turbines will be contributed throughout the year,
displacing that amount of diesel generation each and every year of the analysis period. Nome’s
new power plant controls were designed to integrate alternative and intermittent sources so no
additional costs for integration hardware and software are expected to be required for the two
wind turbines of 1.5 MW each.
However, adding wind turbine capacity adds cost to the system. Thus, the installed cost of
$4,000/kW is recovered in electric rates over the analysis period, as well as the expected fixed
operating costs of 3% of the installed costs and variable operating costs of slightly less than 1
cent/kWh. Initially, the installation of new wind turbines is expected to require 1 additional staff
member to adequately maintain the wind system.
A simplifying assumption is that the units installed in 2015 will operate over the analysis period
with routine maintenance. The actual availability of the turbines suggested for installation, with
a forecasted effective lifetime of 20 years, is not certain. It is also possible that more robust
units with greater operating efficiency and longer lifetimes may become available over the
analysis period as a result of the rapid advances that are being routinely achieved in wind
turbine technology. Replacing units after 20 years with more efficient turbines would likely
increase the economic benefits of a wind-diesel system, as would adding more turbine capacity
over time as electric load requirements increase. (See Section 5 for more on this.)
8.2.4 WIND/DIESEL SYSTEM ECONOMIC ANALYSIS RESULTS
The installation of two 1.5 MW wind turbines producing at a 34% capacity factor that offsets
diesel generation results in system operating costs for the 30-year period of $111 million in
present value under conditions of a mid-range escalation in diesel fuel costs. In the alternative
case of high-range escalation in diesel fuel costs, the total present value would increase to $128
million. In both cases, the total cost of providing electricity under these assumptions is several
million dollars less than the cost of continuing to generate electricity with only diesel generators.
If green tag sales are available and successful at the time of installation of the wind system,
approximately $4.7 million in credits may contribute to a further reduction in the cost of
electricity (See Section 5.4.5).
The rate of change of the average electric rates is shown in Figure 8.2. For this case, the rates
remain almost constant for the mid-range escalation case and increase about 30% to
$0.39/kWh for the high-range escalation.
Figure 8.2. Wind/Diesel system: Average Electric Rates
Wind/Diesel System: Average Electric Rates
0.20
0.25
0.30
0.35
0.40
0.45
201520172019202120232025202720292031203320352037203920412043real year 2007 $ per kWhMid-Range Diesel escalation High-Range Diesel escalation
Renewable Energy Fund
Grant Application
NJUS Renewable Energy Fund
Grant Application Page 50 of 51 10/8/2008
NJUS Renewable Energy
Fund Wind Project
Supporting Documents
Appraisal Company of Alaska
3940 ARCTIC BOULEVARD, SUITE 103
ANCHORAGE, LASKA 99503
office@appraisalalaska.com
Fax
(907) 563-1368
Telephone
(907) 562-2424
A
October 1, 2008
John Handeland, Manager
Nome Joint Utility
P.O. Box 70
Nome, Alaska 99762
Re: Restricted Appraisal – 672 Acres More or Less Located in
Sections 5 & 6, Township 11 South, Range 33 West,
Kateel River Meridian – Nome, Alaska
Dear Mr. Handeland:
As requested, I have completed a restricted appraisal of the above referenced property which is
described in the following report. The purpose of the appraisal is to estimate the market value of
the fee simple estate of the subject land.
As a result of the investigation and analysis, and subject to the assumptions and limiting
conditions, it is my opinion the market value of the subject property, as of October 1, 2008 is:
EIGHT HUNDRED FORTY THOUSAND DOLLARS
($840,000)
The report is intended to meet the current Uniform Standards of Professional Appraisal Practice
as formulated by the Appraisal Foundation, and conform to the Appraisal Standards for Federally
Related Transactions adopted by the Office of the Comptroller of the Currency (OCC).
I hope this limited appraisal proves relevant to your decisions regarding the property. If you have
any questions, please contact me at this office.
Sincerely,
APPRAISAL COMPANY OF ALASKA
Michael C. Renfro
Partner
08-3189
NORTON SOUND HEALTH CORPORATION
BOARD OF DIRECTORS As of 09/30/08
Name Representing Officer/Executive Committee
Emily Hughes Region‐At‐Large Chairperson
June Walunga Native Village of Gambell 1st Vice Chair
Kathy Johnson Native Village of Unalakleet 2nd Vice Chair
Berda Willson Native Village of Council Secretary
John Handeland Nome Community‐At‐Large Treasurer
Mary Knodel City of Nome Assistant Secretary/Treasurer
Alfred Sahlin Nome Eskimo Community (President) Executive Committee #1
Virginia Washington Native Village of St. Michael Executive Committee #2
Karlin Itchoak Nome Eskimo Community Executive Committee #3
Leonard Adams Native Village of Brevig
Karen Kazingnuk Native Village of Diomede
Frederick Murray Native Village of Elim
Mary Lou Amaktoolik Chinik Eskimo Community (Golovin)
Robert Keith Kawerak, Inc. (Chairman), Elim
Ruth Ojanen King Island Community
Morris Nassuk Native Village of Koyuk
Carol Ablowaluk Mary’s Igloo
Preston Rookok Native Village of Savoonga
Simon Bekoalok Jr. Native Village of Shaktoolik
Karla Nayokpuk Native Village of Shishmaref
Brian James Village of Solomon
Becky Odinzoff Stebbins Community Assoc.
Wesley Okbaok Native Village of Teller
Joanne Keyes Native Village of Wales
Lincoln M. Simon Sr. Native Village of White Mountain
RECEIVED
C.NORTON SOUND AUG 8ECONOMIC 2008
DEVELOPMENT NJ U S
CORPORATION
_________________
Serving the fisheries of the Bering Strait Region
Elim Gambell Golovin Koyuk Nome Saint Michael Savoonga Shaktoolik Stebbins Teller Unalakleet Wales White Mountain
August 25,2008
Mr.John Handeland,Manager
Nome Joint Utility Systems
P.O.Box 70
Nome,Alaska 99762
Re:Renewable Energy Discussions
Dear Mr.Handeland,
The Norton Sound Economic Development Corporation (NSEDC)Board of Directors (Board)met for
their 2008 2’quarter meeting from July 30-August 1.As with most businesses and households,the
recent surge in energy costs has NSEDC examining options to decrease costs of our operations.At the
meeting the Board directed NSEDC staff to pursue engaging Nome Joint Utility Systems (NJUS)in
discussion regarding NSEDC objectives and the potential for cooperating with NJUS to achieve those
objectives.In order to meet NSEDC’s goal of decreasing operational costs,the best solution,from both
an energy output and installation standpoint,is to cooperate with the local utility.
NSEDC is interested in NJUS’consideration of a net-billing program for commercial buildings in Nome.
In the event NSEDC installs renewable energy resources,in addition or as an alternative to cooperating
with NJUS,the success of a potential NSEDC wind turbine installation project depends upon NSEDC’s
decision on net-billing.The predicament is that NSSP is using a vast majority of its energy during the
four months that the wind blows the least.If NSSP is unable to gain credits during the winter months
when the plants use much less power,but the wind is blowing much more,these wind systems may
simply not be cost effective to install.
NSEDC would like to meet with you to discuss the above stated issues.Please let me know your
availability at your soonest convenience.I can be reached at (800)650-2248 orjanis@nsedc.com.
Please do not hesitaLe to oiitact me and I look forward to hearing from you.
Thank you,
14
Jas Ivanoff
C6mmumty Benefits Director
cc:Mr.Don Stiles,NSEDC Board Member
Mr.Josh Osborne,Northern NSSP Manager
Mr.Richard Ferry,Facilities Engineer
Community Benefits Department
File
“NSEDC will pariicopae in and encouras the dean harvest ofa/I Bering Sea fisheries toprnnwte and provide econo,uic develop snerst throinh education,employment,training and
financial assistance to member communities and Wistern Alaska,while protecting subsistence ,esourcss”
Brevig Mission Diomede
420 L Street Suite 310 Anchorage,Alaska 99501 (907)274-2248 Fax:(907)274-2249
1
John K. Handeland
From:Janis Ivanoff [JDIVANOFF@nsedc.com]
Sent:Tuesday, October 07, 2008 3:45 PM
To:John K. Handeland
Subject:RE: [Junk released by User action] RE: Renewable Energy Discussions
Good afternoon John,
We look forward to this discussion with NJUS on pursuing an opportunity for NSEDC to
cooperate and assist our member communities with energy solutions. Please let us know when a
good time would be for a meeting.
Janis Ivanoff
Community Benefits Director
________________________________
From: John K. Handeland [mailto:johnh@njus.org]
Sent: Tue 10/7/2008 3:29 PM
To: Janis Ivanoff
Subject: [Junk released by User action] RE: Renewable Energy Discussions
From: John K. Handeland [mailto:johnh@njus.org]
Sent: Tuesday, October 07, 2008 12:06 PM
To: 'janis@nsedc.com'
Subject: Renewable Energy Discussions
Janis,
I have not forgotten about your August 25, 2008 letter, which we briefly discussed at the
Rural Energy Conference in Girdwood last month. I believe there are some possibilities that
we can pursue that would benefit both NSEDC/NSSP and Nome/NJUS.
As I told you, we are seriously working to install alternative energy (wind) into our grid.
Bering Straits/Sitnasuak through Banner Wind LLC is in the process of installing about 1MW of
capacity to feed to us. We are pursuing our own 3MW farm and are working cooperatively with
Unalakleet to develop similar equipment and operations, so we can share expertise, parts,
maintenance, etc.
I am aware that NSEDC is collaborating with UVEC on a project that would allow them to
install wind turbines with financial assistance from NSEDC in exchange for a negotiated long‐
2
term power rate reduction for your facilities in that community. This is a win‐win situation
for them; and I think a like situation in Nome also bears further discussion.
When it is convenient, I would welcome the opportunity you requested to meet with to discuss
how we can meet mutual objectives, which ultimately could lead to reductions in costs for not
just NSEDC, but for the community as a whole, and also perhaps strengthen your presence here
‐ and provide additional opportunities for year‐round employment for the region.
Thanks,
John Handeland
Adem and Melissa Boeckmann
P.O.Box 1007
Nome,AK 99762
Sunday,September 28,2008
John Handeland,Manager
Nome Joint Utility
P.O.Box 70
Nome,AK 99762
Dear John,
Thank you for visiting with us to share the Utility’s plans for a wind generation site on city property
adjoining ours.This is a very exciting development,and one which we fully support.The cost of
energy is having a big impact on communities throughout the region and we applaud the efforts to
bring some relief to Nome area residents.
The extreme southwest border of city property is common a common property line with our
property.We acquired the North Star Placer claim in 2002 and the adjoining No.6 &No.7 Above
on Dry Creek Placer in 2006.
This is to confirm that in 2006 we paid $2.000 per acre for No.6 &No.7 Above on Dry.The Anvil
Bypass Road goes through this property but Alaska Gold required us to buy the entire claims,
including the road section.Therefore,a portion of our property is encumbered,so if you remove
the road area not useable by us,effectively the price paid was much more than $2,000 per acre for
the remaining property.
Please keep us informed as your plans develop.While your property is accessible from the state
road now,as you refine plans for permanent access —we would be most willing to work with you.
As we already have some existing roads established on our property,we are willing and open to
working out an agreement that would allow the city access from our private road if this is
something that would assist in developing the project.Our course,we would need to work out a
few details to formalize.We would not want this access to become a public thoroughfare,so there
would need to be a gate,liability protection for your use of our road,and an arrangement on
maintenance and snow removal.
This is so exciting!Thanks for keeping us in the loop.