Loading...
HomeMy WebLinkAboutKenny Lake Preliminary ScheduleIDTask NameDurationStartFinish1Phase I - Reconnaissance Complete0 daysFri 12/12/08Fri 12/12/082Grant Award and NTP10 daysFri 12/19/08Mon 1/5/093Phase II - Resource Assessment /Feasibility Analysis / Conceptual Design(35%)44 daysTue 1/6/09Fri 3/6/094Perform resource assessment /feability analysis / develop conceptdesign30 daysTue 1/6/09Mon 2/16/095Agency Feasibility review / comment14 daysTue 2/17/09Fri 3/6/096Phase III - Final Design72 daysMon 3/9/09Wed 6/17/097Final Design50 daysMon 3/9/09Fri 5/15/098Permitting22 daysMon 5/18/09Wed 6/17/099Approval to Construct Issued0 daysWed 6/17/09Wed 6/17/0910Phase IV - Construction Phase109 daysThu 6/18/09Thu 11/19/0911Procurement30 daysThu 6/18/09Thu 7/30/0912Construction90 daysThu 7/30/09Thu 10/22/0913Startup-Commissioning7 daysWed 10/14/09Thu 10/22/0914Final Inspection & Acceptance0 daysThu 10/22/09Thu 10/22/0915Project Closeout Activities20 daysFri 10/23/09Thu 11/19/0912/122/176/1710/22Dec '08Jan '09eb '0Mar '09Apr '09May '09Jun '09Jul '09Aug '09Sep '09Oct '09Nov '092009TaskSplitProgressMilestoneSummaryCopper River School District Kenny Lake School Proposed Wood Biomass Heat SystemPreliminary ScheduleKenny Lake, AlaskaPage 1Project: Kenny Lake wood biomass District Heating SystemDate: Tue 10/7/08