Loading...
HomeMy WebLinkAboutI - HBC AEA Project ScheduleHUMPBACK CREEK PROJECT – CONSTRUCTION ACTIVITY SCHEDULE BY TASK AND ANTICIPATED STREAMFLOW RATE DURING TASK PERFORMANCE 09/27/08 TASK DESCRIPTION STREAM FLOW START DATE FINISH DATE A. Procurement (CEC) - of long lead equipment and steel embedments N/A 12/2/08 5/27/09 B. Procurement (GCC) - of short lead time items and prepare concrete placement plans and lift drawings N/A 1/5/09 8/27/09 Task 1 - Mobilization on Site - set up camp and store materials at staging areas near powerhouse. >10 CFS 1/12/09 1/30/09 Task 2 - Operate Construction Camp - for duration of construction project N/A 2/1/09 9/6/09 Task 3 - Site Access - to construction sites from Eyak Road >10 CFS 1/29/09 2/12/09 Task 4 - Left Abutment Stabilization - rock removal and stabilization >10 CFS 2/12/09 3/1/09 Task 5 - Downstream Tunnel Portal - excavate tunnel portal >10 CFS 2/8/09 3/4/09 Task 6 - Tunnel - excavate rock from tunnel and line tunnel with shotcrete >10 CFS TO 50/60 CFS 3/4/09 6/7/09 Task 7 - Cofferdams and Flow Diversion - install to control stream at dam construction site. >10 CFS 3/26/09 4/26/09 Task 8 - Intake Excavation excavate tunnel portal at intake and for intake structure >10 CFS TO 50/60 CFS 3/2/09 5/21/09 Task 9 - Dam Excavation - remove rock from bottom of dam site 50/60 CFS 5/21/09 6/16/09 Task 10 - Intake/Diversion Foundation Grouting - drill and grout cutoffs for dam stabiity 50/60 CFS 5/17/09 6/26/09 Task 11 - Intake Structure – Construct concrete intake structure 50/60 CFS 5/17/09 6/30/09 Task 12 - Diversion Dam – Construct concrete intake/diversion structure 50/60 CFS 6/16/09 7/28/09 Task 13 - Intake/Diversion Mechanical Equipment & Misc. Steel - installation 50/60 CFS 6/9/09 7/24/09 Task 14 - Penstock – Install new penstock and connect to existing penstock 50/60 CFS 6/9/09 7/26/09 Task 15 - Controls, Power, Scada – run from Dam to Power house 50/60 CFS 7/27/09 8/20/09 Task 16 - Test, Commissioning and Turnover N/A 8/20/09 8/30/09 Task 17 - Demobilzation – of contractor N/A 8/31/09 9/9/09 HUMPBACK CREEK FLOWS AND DURATIONS Description of Streamflow Duration Start Finish Streamflow under 10 CFS 70days 1/9/09 4/16/09 Streamflow 50 to 60 CFS 87days 4/17/09 8/17/09 Streamflow 200 CFS 30days 8/20/09 9/30/09