HomeMy WebLinkAboutR - HBC AEA Access Road BidWILSON CONSTRUCTION, INC.
BOX 813 • CORDOVA, AIASKA 99574 • (907) 424-3452
September 15, 2008
CEC
P.O. Box 20
Cordova; AK 99574
RE: HBC — Eyak Road
Construction Access Road to New Intake Diversion
Fixed -price cost estimate: $369,570.00; this price is based on a 4200' long road with 9 —
24" culvert crossings & 4 — 48" culvert crossings. The number of culverts is a best guess
estimate & will be billed according to the culvert size crossing price as indicated below.
We gave prices for all sizes of culvert with installation as to have a more accurate price.
Road Construction- cost per linear foot: $72.50; based on 4,200' long road
Culvert installed cost per installation:
Using 24" CMP: $3,180.00/installed crossing
Using 30" CMP: $5,115.00/installed crossing
Using 36" CMP: $6,385.00/installed crossing
Using 42" CMP: $7,735.00/installed crossing
Using 48" CMP: $9,015.00/installed crossing
Wilson Construction, Inc. is available to start work on this project as soon as it is
awarded. Date of start will depend on soonest availability of barge and tides to mob
equipment.
We plan to use the EX400 Excavator and our D8L Dozer to pioneer and build this road.
We plan to use existing pioneer road to access new road alignment.
We are planning on using the bunkhouse for crew quarters.
We will use stabilization fabric near meadows as needed.
Silt fence will be installed as needed.
GAAiY-n"
Tammy Altermott
I1`1Cl_l..LbEtS tai+h bid, proof o-� insurance, licensing
3 bonding