HomeMy WebLinkAboutAPA387--------·-------
ENVIRONMENTAL REPORT
·rASK 7: ENV tRONMENTAL
SUMMARY j.\NNUAL
REPOY~'T '·1980
MAY 1981
' I ,
I
i
J
l
!·
I I
!
I
l I l
1 I
! l l .'
I I
C:dU· 1""LJnR· .tTY ---J .... · .•.. · 1 ~ . 1 r· ~ ._J . • . ___ _....,..,
i'
I
l
-
-
-
Tt<
l L.j ;~.;5
E=5g ~---------------------------------------~--------~--~ .----------------------------.,Jilt~ 38/
SUSITNA HYDROELECTRIC PROJECT
M
1.0
~ Prepared for:
1.0 ~-M
ENVIRONMENTAL REPORT
TASK 7: ENVIRONMENTAL
SUMMARY ANNUAL
REPORT . -1980
MAY 1981
ARLIS
Alaska Resources
Library &.. tnfonnatton Servtces
Anchorage. Alaska
Prepared by:
Teuethial
E nvitonmentc.l
SpeciaUttt, Inc.
~....--.;....-_____ ALASKA POWER AUTHORrTY __ __.~
'
,_
I
-
-
I""'
I
ALASKA POWER AUTHORITY
SUSITNA HYDROELECTRIC PROJECT
TASK 7
ENVIRONMENTAL STUDIES
SUMMARY ANNUAL REPORT -1980
MAY 1981
by
TERRESTRIAL ENVIRONMENTAL SPECIALISTS, Inc.
ARLIS
Alaska Resources
Library & Informatmn Servtces
Anchorage, Alas.kl.l
Phoenix, New York 13135
for
ACRES AMERICAN, INCORPORATED
Liberty Bank Building, Main at Court
Buffalo, New York 14202
-
TABLE OF CONTENTS
LIST OF TABLES
LIST OF FIGURES
1 -INTRODUCTION----------------------------------------------1
2 -THE STUDY AREAS--------~----------------------------------2
2.1-Subtask 7.05: Socioeconomic Analysis------------------2
2.2 -Subtask 7.06: Cultural Resources Investigation--------20
2.3 Subtask 7.07: Land Use Analysis-----------------------20
2.4-Subtask 7.08: Recreation Planning---------------------21
2.5-Subtask 7.09: Susitna Transmission Corridor
Assessment------------------------------21
2.6-Subtask 7.10: Fish Ecology Studies--------------------21
2.7-Subtask 7.11: Wildlife Ecology Studies----------------22
2.7.1 -Big Game---------------------------------------22
2.7.2-Furbearers-------------------------------------23
2.7.3-Birds and Non-game Mammals---------------------23
2.8-Subtask 7.12: Plant Ecology Studies-------------------24
2.9-Subtask 7.14: Access Road Environmental Analysis------25
3 -SUBTASK SUMMARIES--------------------------~--------------25
3.1-Subtask 7.01: Coordination of Environmental Studies---25
3.2-Subtask 7.02: Monitoring of Field Activities for
Environmental Acceptability-------------27
3.3 -Subtask 7.03: Evaluation of Alternatives--------------28
3.4-Subtask 7.04: Water Resources (Quality) Analysis------28
3.5-Subtask 7.05: Socioeconomic Analysis------------------29
3.6-Subtask 7.06: Cultural Resources Investigation--------43 ·
3.7-Subtask 7.07: Land Use Analysis-----------------------47
3.8-Subtask 7.08: Recreation Planning---------------------50
3.9-Subtask 7.09: Susitna Transmission Corridor
Assessment------------------------------53
3.10-Subtask 7.10: Fish Ecology Studies-----~--------------58
3.11 -Subtask 7.11: Wildlife Ecology Studies----------------59
3.11.1 -Big Game--------------------------------------59
3.11.2 -Furbearers------------------------------------71
3.11.3 -Birds and Non-Game Mammals--------------------73
3.12-Subtask 7.12: Plant Ecology Studies-------------------76
3.13 -Subtask 7.13: Geological Analysis---------------------79
3.14-Subtask 7.14: Access Road Environmental Analysis------79
3.15-Subtask 7.15: Preparation of FERC License
Application Exhibit---------------------82
3.16-Task 12: Public Participation Program-----------------83
--
-
-
Page
4 -REPORTS-------------------------------------------·--------84
4.1 -Reports by TES and Subcontractors~-----------------------84
4.1.1 -Reports Prepared---------------------------------84
4.1.2 -Reports in Preparation---------------------------87
4.2 -Reports by Alaska Department of Fish and Game------------87
4.2.1 -Reports Prepared---------------------------------87
4.2.2 -Reports in Preparation---------------------------88
5 -AUTHORITIES CONTACTED--------------------------------------89
5.1 -Federal Agencies-----------------------------------------89
5.2 -State Agencies-------------------------------------------92
5.3 -Local Agencies-------------------------------------------95
5.4 -Other Institutions. Organizations, and Individuals-------96
-
LIST OF TABLES
Table
1. Total Resident Population and Components of Change
by Study Area: 1970-1980--------------------------------31
2. Community Population---------------------------------------32
3. Estimated Housing and Vacancy Rates-------~----------~-----33
4. Housing Stock Estimates by Areas of Mat-Su Borough---------34
5. Community Facilities Summary------------------:-------------35
6. Study Area 3 Annual Nonagricultural Employment
by Sector------------------------------------------------38
7. Matanuska-Susitna Borough Annual
Nonagricultural Employment by Sector---------------------39
8. Valdez-Chitina-Whittier Annual Nonagricultural
Employment by Sector-------------------------------------40
9. Potential Fish Ecology Impact Issues by Project Stage------60
10. Hectares of Different Vegetation Types to be Affected
Compared With Total Hectares of Those Types in The
Entire Upper Susitna River Basin~------------------------77
LIST OF FIGURES
Figure
1. Study Areas for Socioeconomic Analysis--------------~------------3
2. Study Area for Cultural Resource Investigations------------------4
3. Study Areas for Land Use Analysis---------------:................................... 5
4. Sites Investigated for Recreation Planning-----------------------6
5. Transmission Corridors Evaluated -Northern Study Area---~-------7
6. Transmission Corridors Evaluated -Central Study Area------------8
7. Transmissi.on Corridors Evaluated Southern Study Area-----------9
8. Fish Ecology Study Area------------------------------------------10
9. Study Areas for Big Game Species -Wolverine, Wolf, Moose
(Upstream)-----------------------------------------------------11
10. Study Areas for Big Game Species -Black Bear, Brown Bear--------12
11. Study Area for Moose -Downstream------~-------------------------13
12. Furbearer Study Area -Upstream----------------------------------14
13. Furbearer Study Area -Downstream----------------------------.,;___ 15
14. Bird and Small Mammal Study Area---------------------------------16
15. Plant Ecology Study Area -Upstream------------------------------17
16. Plant Ecology Study Area -Downstream----------------------------18
17. Access Corridors------------------------~------------------------19
18. Cultural Resource Site Locations---------------------------------46
19. Transmission Corridors Surviving Preliminary Screening-
I""' Northern Study Area-------------------------------------------55
I
20. Transmission Corridors Surviving Preliminary Screening -
Central Study Area--------------------------------------------56 -21. Transmission Corridors Surviving Preliminary Screening -
Southern Study Area--------------------------------------------57
22. Vegetation Map of Upper Susitna River Basin------------------Back Pocket
-
1 -INTRODUCTION
Terrestrial Environmental Specialists, Inc. (TES), on behalf of the
Alaska Power Authority (APA) and as a subcontractor to Acres American,
Inc. (Acres), is performing environmental studies as part of a
feasibility study and Federal Energy Regulatory Commission (FERC)
license application effort for the Susitna Hydroelectric Project. The
environmental program consists of baseline studies, impact analysis, and
mitigation planning, each of which is ~ing conducted in two phases:
preceding submission of the license application (Phase I) and following
the license application (Phase II).
Work is being performed for TES by subcontractors (University of Alaska,
Frank Orth & Associates) and consultants (M. Bell, C. Atkinson, R.
Williams, R. Taber, B. Kessel). Studies to describe the existing fish
and big game ecology are being performed by the Alaska Department of
Fish and Game ( ADF&G) under a direct agreement with APA. A water
qua 1 ity program is being performed by R&M Consultants as a subcontractor
to Acres.
This report summarizes the accomplishments and findings of the 1980
environmental program. Details of the program objectives and design may
be found in the Plan of Study (Acres American, Inc., February 1980), in
which the environmental program is referred to as Task 7, and in the
Procedures Manuals prepared for the major environmental subtasks by TES
and its subcontractors. Complete results of the 1980 studies may be
found in the Annual Reports for the various specific subtasks. These
and other Task 7 reports are listed in Section 4.
-
-
2 -THE STUDY AREAS
The study areas for the subtasks of the Susitna Hydroelectric Project
vary considerably; some subtasks require larger study area-s than
others. By necessity, there is even variation in study areas among
portions of some subtasks. The following descriptions indicate the
areas that are being studied. The accompanying maps (Figures 1-17)
delineate these study areas.
2.1 -Subtask 7.05: Socioeconomic Analysis
Several levels of socioeconomic analysis are being carried out; thus,
there are four basic study areas (Figure 1). Study Area 1 includes the
proposed dam sites, most of the transmission and access road corridors,
and some project staging areas.
Study Area 2 includes the Matanuska-Susitna Borough and Valdez-Cordova
(formerly Valdez-Chitina-Whittier) census divisions. This study area
contains the primary political units within which the project and, to a
substantial degree, its impacts will occur.
Study Area 3 is the Railbelt Region and data from this region form the
basis for most of the quantitative analyses regarding many of the
economic variables. Analysis of the Alaska socioeconomic structure
leads to the inclusion (in this study area) of major census divisions:
Anchorage, Kenai-Cook Inlet, Seward, Valdez-Cordova, Matanuska-Susitna,
Southeast Fairbanks, and Yukon-Koyukuk.
Study Area 4 encompasses the State of Alaska. It will be used
primarily for purposes of comparing existing statewide conditions with
those resulting from the project, and for general comparison with data
for the total nation.
2
1 J l --j 1
-Study Area 1
Study Area 2
0
SUSITNA HYDROELECTRIC PROJECT
Figure 1
Study Areas for
Socioeconomic Analysis
Paleontology Study Area
Archeology Study Area-~
P leistoce~~u~ye~~~~ (!iU}:?~i:;j:;:;({J
1 l
0
0 10 20
Kilometers
1 J
20
30
l
SUSITNA HYDROELECTRIC PROJECT
Figure 2
Study Areas for
Cultural Resource Investigations
1
.. J l 'l ,_ .) . '1 .. ) ... -) l l ··-1 ---1 ) Zone 1 Zone2 ~-Zone 3 f{f.:~·)'/J{,';:f.J 0 20 10 20 30 0 Kilometers . ' ., l l J .. r..,,, ;~ 'l><'_ ·~~7"-J;;.~y_J,, "~J,."Y'•_, ~-;=;; ,--{?r'" ;<--;). ~ ~ . -: l ~_r::: ' ·~ ., ,;-·;~· \ r • -~ .• ,__ ,; "· v . 1L .(; J '\?./.'_/ rPz:_,--._----) 0 SUSITNA HYDROELECTRIC PROJECT Figure 3 Study Areas for land Use Analysis J
Scenic Sites Potential· Recreation Sites • ... ~l ~l l } 1 0 10 20 0 10 20 30 Kilometers ) -1 l 0 SUSITNA Figure 4 Sites Investigated for Recreation Planning
-
-
Miles
0 5 10 15
0 5 10 15 20 25
Study Corridor
lntertie
(Hypothetical)
•••••
0
Transmission Corridors Evaluated
Northern Study Area
Study Corridor
I ntertie
(Hypothetical)
•••••
.· .. 1
Miles
0 5 10 15
0 5 10 15 20 25
Kilometers
}
POWER AUTHORITY
Figure 6
Transmission Corridors Evaluated
Central Study Area
1
Study Corridor
I ntertie
(Hypothetical)
)
•••••
0 5
0 5
10 15
10 15 20 25
Kilometers
1 l
ALASKA POWER AUTHORITY
Transmission Corridors Evaluated
Southern Study Area
-"
l'""'
-~
-
-
0
0
1980
Study Area
10
Miles
10
20
20
30
ALASKA
Figure 8
Fish Ecology Study Area
0
Miles
10 20
0 10 20 30
Wolverine
Wolf,
Moose (Upstream)
SUSITNA HYOROEl£CTRIC PROJECT
Figure 9
Study Areas for Big Game Species
1
Black Bear
Brown Bear 0
0 10 20
Kilometers
SUSITNA HYDROELECTRIC PROJECT
Figure lO
20
30
Study Areas for Big Game Species
-
~\
. \
0
0
Miles
10
20
Study Area ~
20
30
ALASKA POWER AUTHORITY
Figure 11
Study Area for Moose
Downstream
. -, 1
Study Area 10"'#21
0
0
. Miles
10
10 20
Kilometers
20
30
0
SUSITNA HYDROELECTRIC PROJECT
Figure 12
Furbearer Study Area
. Upstream
-
0
0 10
Miles
10
20
Study Area ~
20
30
0
ALASKA POWER AUTHORITY
SUSITNA HYDROELECTRIC PROJECT
Figure 13
Furbearer Study Area
Downstream
0 >-t:: ~~ C';) ·W E ~ . ' :~ E c... C';)
u ~ C';) ;;: ""'" ~ .... ,_ cz: u C';) w ~ E -' ~ w :::> V) 0 bj) = c::: w:: Cl "C -;> V')
:I: = ,.
C';)
..:
2:. "C ,_ .... u:; Q5 ::>
"' ~"""·
-~
I'C
QJ
l.. -<(
>-"'0
~ -.... (/)
-
-"'C
I.("> ::::1 -E (I') n:l
CLl
= r;a Q) ....
1:>0 -;,=: Q VI
Q c.
u = Ll.l
~ -.... c
c;; ..!S!
::;:)
VI Cl...
~ ~
0 0 = 0 c.o = 0 t"":J = ...,( c-o-i = C'..J c.o o.n
C'..J --.........
"" "" -"'0 "'0 "" CLl CLl "'0 c. c. CLl c. c.. c.
!""" "" "" ~ ~
c.
"" ~
.....
.....
i_;
-i
Mites
0~~~ ... 10~-===~20
0 10 20 30
Mapped at 1:24,000
Mapped at 1:63,360 w::21
Mapped at 1:250,000 brr'\'(<\' I
Figure 16
Plant Ecology Study Areas
Downstream
l
Corridor 1 ----
Corridor 2 ••••••
0
Corridor 3 •-•-• 0 10 20
Kilometers
20
30
SUSITNA HYDROELECTRIC PROJECT
Figure 17
Access Corridors
. ~.
.....
-'
-
2.2 -Subtask 7.06: Cultural Resources Investigation
The cultural resources studies include these components: archeology,
geology, and paleontology. The study areas for each of these
components are indicated in Figure 2.
For 1980, the study area for archeological investigations is defined as
those lands within approximately 3 km (2 miles) of the Susitna River
from just below Devil Canyon to the mouth of the Tyone River. In
addition, ct corridor ·approximately 2 km (1.2 miles) wide from the
Watana Camp north to the Denali Highway was studied.
The study area for geological studies, which support the cultural
resource analysis, extends approximately 16 km (10 mi1es) on each side
of the Sus i tna River, from the Portage Creek area to the mouth of the
Maclaren River. When necessary, contiguous areas were examined .
The study area for paleontological studies is confined to the Watana
Creek vicinity. This locale was selected because it was the only area
identified within the entire Susitna basin that provided suitable
deposits for the study of pre-Pleistocene paleontology.
2.3 -Subtask 7.07: Land Use Analysis
Three basic study areas (Zones 1, 2, and 3) were defined for the Land
Use Analysis (Figure 3). These zones were designated according to
geographic and land use relationships with the Susitna Hydroelectric
Project and extend to varying widths from the river between Gold Creek
and the mouth of the Tyone River.
Zone 1 was designated to include those structures and land uses which
would be affected by inundation. Zone 2, extending about 10 km (6
miles) from the river, is based upon the locations of lakes which
characterize aggregations of land use. Zone 3, which extends
approximately 20 km (12 miles) beyond Zone 2, is characterized by fewer
aggregations of land use; existing structures and land use are sparse.
20
2.4 -Subtask 7.08: Recreation Planni~g
The overall objective of this subtask is to develop a recreation plan
for the Susitna Hydroelectric Project. A considerable number of scenic
and potential recreation sites were considered during the first year's
effort. These sites are indicated in Figure 4.
The 1980 study concentrates on the irrmediate project zone within 60 m
(200 feet) of the shoreline of the proposed impoundments. Adjacent
lands and areas along alternative access routes are also considered.
2.5 -Subtask 7.09: Susitna Transmission Cor'ridor Assessment
The study areas involved in the Susitna Transmission Corridor
Assessment are geographically separated from each other, because the
intertie between Willow and Healy is not part of the Susitna Project.
The three study areas are described as the northern; the central, and
the southern (Figures 5-7). The northern study area encompasses
transmission corridors from Healy to the Fairbanks/Ester area.
Alternative corridors lie to the east as far as the Wood River and Fort
Wainwright Military Reservation and on the west along the Nenana River
and the Parks Highway. The central study area encompasses the
corridors originating at the Devil Canyon and the Watana dam sites.
These corridors generally run westward to the Gold Creek/Canyon area or
northward to the Cantwell/Summit area. The southern study area
encompasses the transmission corridors from Willow to the Anchorage
area via Palmer or via more westerly corridors in the Red Shirt Lake
and Lynx Lake areas.
2.6-Subtask 7.10: Fish Ecology Studies
The area for the Fish Ecology Studies includes the entire Susitna River
from its confluence with the Tyone River downstre~m to Cook Inlet. It
includes areas (i.e., subreaches of the Susitna River mainstem, sloughs
and side channels, tributary confluences, lakes a~d ponds) that are
likely to be affected by post-project flows.
21
r
P"'
'
""" I
!
-
For Phase I work, the Susitna River has been divided into three
segments: Cook Inlet to Talkeetna, Talkeetna to Devil Canyon, and
Devil Canyon to the Tyone River.
In 1980, sampling was conducted by ADF&G at road accessible areas near
following: Willow Creek, Caswell Creek, Rabideaux Creek~ Montana
Creek, Kashwitna River, the Rustic Wilderness Subdivision and the Parks
Highway Bridge. Additional sampling in the Susitna River was done at
roadside locations from Willow Creek to Talkeetna (Figure 8).
2.7 -Subtask 7.11: Wildlife Ecology Studies
The Wildlife Ecology Studies are divided into three major efforts: big
game, furbearers, and birds and non-game mammals. The study areas vary
in size for each effort.
2.7.1-Big Game
The land areas studied by ADF&G for the big game program vary
depending upon the species that are being radio-collared. The
largest study area is for caribou. This study area consists of
the entire range of the Nelchina herd, although monitoring is
more frequent in the vicinity of the proposed impoundments. This
area extends north of the Denali Highway to the foothills of the
Alaska Range and south to the Glenn Highway, and from the
foothills of the Talkeetna Mountains and the Parks Highway on the
west to the Copper River Basin and the foothills of the Wrangell
Mountains on the east.
Study areas for wolves and upstream moose populations are
basically the same (Figure 9). The area is bordered on the north
by the Denali Highway and extends south to the Little Nelchina
River. The eastern boundary extends from the Maclaren River at
the Denali Highway south to Tyone Lake and Lake Louise, then to
the Glenn Highway. The western boundary is generally defined as
northwest from the Little Nelchina River along the upper
elevations of the Talkeetna Mountains to near the mouth of
Portage Creek and then northeast to the Denali Highway.
22
r·
-
Study areas for wolverines (Figure 9) and brown bears (Figure
10) are generally within this same area, although the boundaries
differ in various places. Black bears (Figure 10) are being
studied in two considerably smaller areas within the basin.
Moos1: are also being studied in a downstream area (Ffgure 11)
from near Portage Creek to the Delta Islands. Moose were
radio-collared along the river in this area; browse availability
and utilization were measured and pellet group counts were made.
An intensive study area for browse availability/utilization and
pellet group transects was also investigated. This area
consists of several islands near the mouth of Goose Creek and
the north end of Sheep Creek Slough.
2.7.2 -Furbearers
The area for the furbearer studies includes the impoundment
areas, the area within 12 km (7.5 miles) of the impoundments,
and the downstream floodplain to the Delta Islands. The most
intensive study is being performed upstream of Gold Creek
{Figure 12). Downstream surveys of furbe'arer sign and habitat
prefE~rence were made from 3 km ( 1. 9 mi 1 es) above the confluence
with the Indian River to 4 km (2.5 miles) below the confluence
with the Kashwitna River (Figure 13).
2.7.3-Birds and Non-game Mammals
The area for bird and small (non-game) mammal investigations
extends from near Sherman up the Susitna River to the mouth of
the t~ac 1 aren River and to approximate 1 y 15 km ( 10 mi 1 es) on
either side of the river (Figure 14). Intensive study plots,
mammal trapping sites, bird survey transects, and waterbodies
surveyed for waterfowl are within this area.
23
r
2.8-Subtask 7.12: Plant Ecology Studies
The study area for Plant Ecology during 1980 includes the upper Susitna
River drainage and the floodplain of the Susitna River from Gold Creek
to Talkeetna (Figures 15-16). Within this area, vegetation was mapped
at several scales.
The entire upper Susitna River basin was mapped at a scale of
1:250,000. Vegetation within 16 km (10 miles) of the proposed
impoundment areas was mapped at a scale of 1:63,360. The vegetation
within 0.8 km (0.5 mile) of the proposed impoundments, the borrow
sites, and the floodplain from Portage Creek to Talkeetna was mapped at
a scale of 1:24,000. Sampling locations for vegetation were
concentrated in the area of the 1:24,000 maps after reconnaissance
level surveys in each major vegetation type.
2.9-Subtask 7.14: Access Road Environmental Analysis
After initial screening of numerous alternative corridors for the
access route, three corridors were chosen for environmental analysis
(Figure 17). Corridor 1 is a road access route north of the Susitna
River from the Parks Highway to Devil Canyon and Watana. Corridor 2 is
access to Devil Canyon and Watana on the south side of the Susitna
River, either by road from the Parks Highway or by rail from the Alaska
Railroad. Corridor 3 is a road access route to Watana from the Denali
Highway.
24
.,_.
!
3 -SUBTASK SUMMARIES
As described in the Plan of Study, the various components of the
environmental program are subtasks within Task 7 of the overall
feasibility study for the Susitna Hydroelectric Project. Summaries of
the 1980 activities and findings byTES and ADF&G in each of these
subtasks follow, including a summary of TES involvement in Task 12,
Public Participation. Complete results of the 1980 program in the
major environmental disciplines may be found in the discipline-
specific Annual Reports (Section 4).
3.1-Subtask 7.01: Coordination of Environmental Studies
The objectives of this subtask are diverse and include planning and
implementation of contractual matters, logistics, technical aspects of
the program, reports, quality assurance, and agency consultation.
During 1980, the administration and coordination of the environmental
program required intensive effort by TES.
Contractual matters included ensuring conformance with the details of
formal agreements between Acres and TES, as well as between TES and its
subcontractors and consultants. Manpower and cost projections, and
actual expenditures, were continuously provided to the prime
contractor. All project equipment was inventoried in the prescribed
manner. At the end of the year, the environmental program was on
schedule and within its projected annual budget.
Complex logistics are involved in implementing the field program in
this large and remote study area (Section 2). The TES Resident Manager
at the Anchorage Project Office and the TES Field Representative at
Watana Base Camp (see Subtask 7 .02) worked closely with Acres and other
team members to ensure that the logistical needs of the environmental
team were met during 1980.
25
-
Logistics of a different scale are involved in scheduling the overall
environmental program, and require the continuous exchange of current
information among the various participants of the feasibility study.
During 1980, TES met these needs with reports, written correspondence,
meetings, and phone conversations. To identify the input required by
TES and its subcontractors (from Acres, Acres' other subcontractors,
and ADF &G) , TES d eve 1 oped a Master List and Sc hedu 1 e of I nf ormation
Needs, which covers the remainder of the Phase I period.
Technical coordination of the environmental studies involved providing
direction concerning the Procedures Manuals, Semi~Annual Reports, and
Annual Reports (Section 4). The Procedures Manuals were prepared as
practical subtask-specific documents designed for (1) the exchange of·
program design details among TES subcontractors during the first field
season, {2) TES control of adherence to the program by TES
subcontractors, and (3) assurance of continuity in the event of changes
in project personnel. Semi-annual Reports for the major disciplines
were prepared by TES subcontractors solely as a means of exchanging
information among disciplines. Annual Reports, which were not
scheduled for completion during 1980, will serve as a means of
information exchange during 1981, as well as a formal reporting of
activities and findings of the various subtasks. Editorial review, as
well as sorne technical review, was also performed under the
Coordination Subtask. In addition, TES distributed such reports among
the investigators in the various, related environmental disciplines.
Technical coordination also involves making modifications to the
environmental program. Since the Plan of Study was issued in February,
1980, a number of refinements have been made. The most notable changes
are as follows: additional emphasis on fish and wildlife mitigation
planning, additional emphasis on areas downstream of the proposed dam
sites, and acceleration of the recreation planning effort. An
acceleration of the socioeconomic studies and a boater-use survey were
proposed during 1980. Other refinements have been or may soon be made
in response to findings of the first year's program, concerns of state
agencies, and the possible implementation of revised FERC license
application guidelines.
26
-I
Coordination and consultation with state and federal agencies were
among the activities of the 1980 program. A list of authorities
contacted during the year is presented in Section 5. Many additional
ADF&G personnel were contacted, in their capacity as feasibility study
team members, concerning the fisheries and big game studies. Related
activities included TES representation at various meetings with agency
representatives, such as a field visit by and meetings \'lith the Susitna
Hydroelectric Project Steering Committee in July. Also during 1980,
TES prepared and submitted to Acres written responses to agency
concerns and comments, including the Steering Cormnittee's review of the
TES Procedures Manuals, conments by the U. S. Fish and Wi 1 dl ife
Service, and concerns raised during the July field visit.
3.2 -Subtask 7.02: Monitoring of Field Activities for
Environmental Acceptability
A TES Field Representative was stationed at the· Watana Base Camp full-
time during the 1980 field season, and made field visits as needed
during the remainder of the year .. Although the role of this Field
Representative was not one of an environmental inspector, she did
observe field activities and make suggestions to lessen the environmental
impact of the feasibility study. The TES Field Representative kept aware
of proposed ground disturbance activities, and informed Project
Archeologists so that such areas could be investigated for possible
cultural resources in advance. Consideration was also given to
environmentally sensitive areas such as denning sites and nesting
locations. Through cooperation among the various groups, especially the
helicopter pilots, these areas were for the most part avoided.
The majority of the Field Representative's time was Spent assisting the
environmental study groups by scheduling helicopters and getting
provisions to the field tent camps. Assistance in data collection was
occasionally provided. Wildlife observations, including those made by
field personnel not involved in the environmental studies, were
recorded and reported to the appropriate environmental study group.
Numerous coordination, .scheduling and information retrieval activities
were also performed under this subtask throughout the year.
27
-
r
-
3.3 -Subtask 7.03: Evaluation of Alternatives
When a notice to stop work on Task 1 of the Susitna Hydroelectric
Project was received from Acres, little effort had been invested in
this task by Terrestrial Environmental Specialists, Inc. TES had begun
to search the literature on hydroelectric alternatives and to
develop logic diagrams .for proposed approaches to each of the subtasks
(1.03 and 1.05) in which TES was involved. The results of this effort
were presented to Acres in a Termination Report filed in August 1980.
Environmental evaluation of alternatives to Susitna is now being
performed in a separate study by Battelle, and Acres has assumed
responsibility for the environmental evaluation of Susitna
alternatives.
During 1980, TES did provide some input to Acres in the evaluation of
alternative development schemes, although the work was. performed under
other subtasks. Two pertinent reports were prepared by TES: (1) a
preliminary environmental assessment of tunnel alternatives (December
1980), and (2} a report on environmental considerations of alternative
hydroelectric development schemes for the upper Susitna basin (January
1981). TES also provided input concerning mitigation through design,
primarily under the Fish Ecology Subtask (7.10).
3.4-Subtask 7.04: Water Resources (Quality) Analysis
The water qua 1 ity program is being performed for Acres American by R&M
Consultants under Task 3. To ensure that parameters needed for fish
ecology impact analysis would be measured, TES provided input into the
design of the Task 3 program.
Water quality data collection was performed during the 1980 field
season by R&M. These data are included in the Water Quality Data
Collection Annual Report (Subtask 3.03) prepared by R&M. A list of
project reports on the lower Susitna is also available. Both of these
documents have been supplied toTES. All pertinent reports and
available data are being analyzed in relation to fish ecology impacts
byTES, and this procedure will continue as more information is made
available.
28
··~"""'
-
-
3.5 -Subtask 7.05: Socioeconomic Analysis
The Socioeconomic Analysis is designed to identify social and economic
factors that will be affected by the Susitna Hydroelectric Project and to
determine the extent of change. Phase I entails four Work Packages: a
literature review, development of a socioeconomic profile, preliminary
socioeconomic impact studies, and a forecast of future socioeconomic
conditions in the absence of a Susitna project.
Specific objectives for Phase I include the following: (1) review impacts
resulting from energy-development projects and assess their applicability
to the proposed hydroelectric project in the upper Susitna basin, (2)
develop descriptors (categories of variables) for socioeconomic conditions
and determine which variables are most likely to be influenced by
development, (3) geographically delineate impact areas, (4) identify and
describe important socioeconomic conditions in areas likely to be affected
by development, (5) review forecasting models and assess their
applicability to forecasting socioeconomic conditions in the impact areas,
(6) adopt, modify, and/or develop a methodology for forecasting
socioeconomic conditions and for conducting preliminary and final impact
analyses, (7) conduct a preliminary socioeconomic impact analysis of
hydroelectric development, including consideration of a one or two dam
scheme, access routes, transmission facilities, and other areas, concerns
and issues that may be appropriate, and (8) forecast socioeconomic
conditions in the impact areas assuming there will be no hydroelectric
development in the upper Susitna basin:
At the end of the first year, the first four Phase I objectives were
accomplished. Work relating to the next three objectives was in process,
and work relating to the last objective had not begun.
Results of the baseline study include a description of current
socioeconomic conditions in geographic areas that could be affected.
Information concerning places and communities in or near the Susitna basin
is provided subject to the availability of secondary data.
29
,....
'
,-.,
·-
-
Preliminary 1980 census figures indicate that Mat-Su Borough has a
population of 17,938, and Valdez-Cordova 8,546. The Railbelt contains
285,011 people, 71% of the state population of 400,331. The 1980 state
population is up 32% from the 1970 total of 302,361. Tables 1 and 2
contain additional details.
Housing in Mat-Su Borough is primarily single-family, year-round units. Of
5,844 such units, 5,546 are occupied, resulting in a vacancy rate of 5.1%
(298 units); Valdez has a vacancy rate of 3.1% (31 units); Fairbanks has a
vacancy rate of 9.1% {1,072 units); and Anchorage has a vacancy rate of
10.2% (5,769 units). In addition to year-round units, Mat-Su Borough has
some 1,141 recreational units. Additional details are presented in Tables
3 and 4.
Government structure, taxation, and existing infrastructure (Table 5) vary
by community in the Rai1belt according to its classification, population,
and other factors. Larger areas generally have more developed services and
infrastructure, and therefore are able to support or accommodate
significantly greater economic development activity.
Communities and other developed areas in the Railbelt (Table 5) generally
have basic urban utilities, electricity, and telephone service. Fire,
police, and health services vary according to the size of the population.
Communities in the southern portion of Mat-Su Borough are served by various
fire service districts; some have local police protection, although the
Alaska State Police provides service to remote areas. Electric and
telephone service usually are not available in isolated areas.
Mat-Su Borough operates seventeen elementary, junior, and senior high
schools ancl a community college. Anchorage and Fairbanks are fully served
by primary and secondary schools and the University of Alaska (Table 5).
30
--
_··/~""'·
·.~.
1980
Preliminary
Census
l!;;/U
Census
Net Change
Percent
Change
Change in
TABLE 1
TOTAL RESIDENT POPULATION AND COMPONENTS OF CHANGE
BY STUDY AREA: 1970 -198n
Study Area 2 Study Area 3* Study Area 4
Matanuska-Susitna Valdez-
Borough Cordova
179938 89546 285,011 400,331
6,509 5,000 200,023 302,361
+11 ,429 +3,546 +84,988 +97,970
+175 +71 +42 +32
Mi 1 ita ry Pop +141 +58 -4,730 -8,102
Natural
Increase +1,430 +844 +459107 +619142
(Births &
Deaths)
Impl1ed net
Civilian 9,858 ... 2,644 40,111 44,930
Migration
*Fairbanks, S.E. Fairbanks Mat-Su, Anchorage, Kenai Peninsula, and
Valdez-Cordova Census Divisions
Source: Alaska Department of Labor, Administrative Services Division.
January 1. 1981. Alaska's 1980 Population: A Preliminary
Overview. Juneau, AK. p. 26.
,_
I
r
--~
c.-
-
TABLE 2
COMMUNITY POPULATION:
MATANUSKA-SUSITNA BOROUGH CENSUS DATA
1939~ 1950, 1960, 1970,1976, 1980
Corm1unity 1939 ·1950 1960 1970 1976 1980*
Talkeeta --rJb --rt5b ---r6 -m--m 26!
Wi 11 ow 78 38 384 134
Wasilla 96 97 112 300 1566 1.548
Palmer 150 890 1181 1140 1643 2143
Montana 39 33 76 40
Big Lake 74 36 721 412
Butte 559 448 2207
Chickaloon 11 43 22 62 20
Eska Sutton 14 54 215 89 496
Curry 2
---------------------------------------------------------------------------
COMMUNITY~POPULATJON:
OTHER COMt~UNITI ES NOT IN MATANUSKA-SUSITNA BOROUGH
Community 1950 1960 1970 1976 1980*
Nenana 242 286 382 493 471
Healy 79 503 333
Cantwell 85 62 95
Denali 3
Paxson 20 30
Glennallen 142 169 363 488
Copper Center 90 151 206 213
Gakona 50 33 88 85
Gulkana 65 51 53 111
*Alaska Department of Labor, Administrative Services Division. January 1,
1981. Alaska 1980 Population: A Preliminary Overview. Juneau~ AK; pp.
14-24.
Source: Matanuska-Susitna Borough Planning Department. April 1978. Phase
I: Comprehensive Development Plan. Palmer, AK; p. 50.
F"
'
-
-
-
-
-
-
TABLE 3
ESTIMATED HOUSING AND VACANCY RATES
TOTAL YEAR-ROUND OCCUPIED VACANT VACANCY
AREA HOUSING UNITS UNITS UNITS RATES (~)
Anchorage 1 56,823 51,054 5,769 10.2
Valdez 2 979 948 31 3.1
. 1 Fairbanks 11,809 10,737 1,072 9.1
Matanuska-Susitna 3 5,844 5,546 298 5.1
Valdez-Chitina-
Whittier N/A N/A N/A N/A
1 Fairbanks North Star Borough, Corrrnunity Research Center. Fall 1980.
Corrrnunity Research Quarterly, A Socioeconomic Review. Fairbanks, AK; p. 81
2 U.S. Environmental Protection Agency, Region 10. December 1979. ·Alaska
Petrochemical Company, Refinery and Petrochemical Facility: Environmental
Impact Statement; Appendix Vol. II. Valdez, AK; p. II-93.
3 Over a 11 Economic Deve 1 opment Program, Inc. July 1980. Vo 1 ume II: Economic
Conditions, Development Options and Projections, Palmer, AK; pp. 76.
TABLE 4
.I~
,.... HOUSING STOCK ESTIMATES BY AREAS OF MAT-SU BOROUGH
Estimated
!""" Recreati anal
Total Year-Round Units Units
Areas n 11• -1 Talkeetna, Montana
Caswell 214 3.7 97
2 Willow 173 3.0 274
r 3 Houston 225 3.8 92
4 Big Lake 425 7.3 530
5 Goose Bay, Knik,
MacKenzie 83 1.4 13
I""' 6 Wasi 11 a 2,020 34.6 133
7 Sutton, Chickaloon
Independence Mine 143 2.4
8 Palmer 1,502 25.7 2
9 Butte 519 8.9
10 Road1ess Areas 540 9.2 Unknown
F""' TOTAL 5,844 100.0% 1,141
-Source:. Overa1 1 Economic Development Program, Inc. July 1980. Volume
II: Economic Conditions, Development Options and Projections;
p. 76.
-,
!
) ) ···,}ABLE ~ l l l l j
COMMUNITY FACILITIES SUMMARY
.0 t:: Government .--...... 0
n:l . ,_. .,... n:l
1/1 +> u .,.... .j...J 0'1 .,...
0 1/1 n:l u n:l s:: OJ u OJ 0.. 0 lL n:l ,...... .j...J .,... u OJ ,......
1/1 n. lL ((] ~ u .,.... ;::;:: ::l Schools ...... OJ .j...J 0 .--> -. u ~ Cl ~ ~ ~ ..c: .,... 0.. .,.... ~ s:: OJ
OJ OJ OJ OJ ra .j...J 0. 1/1 ;::) OJ 0 1/1 .j...J OJ OJ 0.. u .j...J u .--Vl s:: r::a OJ E Vl .,.... til til n:l E ~ .j...J 0 .,... .j...J s:: ra 0 ra u OJ .j...J til ra ~ 0 >, 1/1 0 .....,. til ,_. OJ E OJ :X: ~ .0 .,.. .j...J OJ ra QJ ra .--0 :X: ra ~ n:l !-0 >, .--u !-:::r:: -o 1-0.. 4--til s:: u ...-.--u 0.. +-' ra 3: 1-0.. !.1) n:l OJ .--n:l .,... >, ..... 4-->, 0 .,... ;:J u !-u s:: u !-:X: ..c: 1-...-ra 0 u !-~ s:: 0 Vl ..c s:: 0:: u 0 OJ OJ s:: OJ ~ ~ u OJ ...-.j...J .j...J ra !-til. ~ .,... .j...J ra ;::1 ~ 0.. ;::1 .j...J s:: u •..-E 0 ..r:: OJ OJ .,... .j...J ra ~ OJ .--0'1 .j...J OJ -o r-,_. til !-~ .j...J .::L Q) Q) E QJ Vl 0 s:: 4--QJ u 0'1 .j...J 3: ..... ra u ;::1 ~ ra s:: c: c: ((] .,... LJ !-.0 til ~ ::: .--E E ~ u .... ...... .--QJ .,... ra OJ 0 .j...J 0 0 .,... ~ 0 OJ OJ 0 ra ::l .,... . ,... 0 0 ra 0 QJ 0 0 .... QJ s:: s:: w Vl :X: 3: Vl Vl Vl -l u lL -l ~ (.!) ~ ~ n. <( _, u 0... 0... 0... 1-u :X: LL.. Vl ::;) :::J
Nenana * * * * * * * * * * * * * * * * ·Jr *
Cantwe 11 * * * * * * * * * * * ·,\-*
Talkeetna * * * * * * * * * * * * * * *
Hill ow * * * * * * * * * * * * ~
Palmer * * * * * * * , ... * * -!: * * * * * * * * * * * * * *
Has ill a * * * * * * * * * * * * * * * * * *
Paxson * * * * * •k *
Glennallen * * * * * * * ft * * * * * * * * tr *
Copper Center * * * * * * * * * * * ·k *
Gakona * * * * * * * * *
Healy ·Jr * * * * '* * * * * ft * * * *
Gulkana -* * * * * * * * * *
Valdez * * * * * * * * * * * * >'r * * * * * * * * * •k
Anchorage * * * * * * * '" * * * '{( * * * * * * * * * * * * * *
Fairbanks * * * * * * * * * * * * * * * * * "'1: * * f, * * * * *
.
-
-
-' I
Alaska relies heavily on air and marine
dispersed population. The southcentral
comprehensive transportation networks.
in terms of annual tonnage (60 million
transportation, owing to its small,
and interior regions have the most
Valdez is the State 1 s largest port
tons). Virtually all (99%) of this
involves sh·ipment of crude petroleum from the pipeline. The ports of
Anchorage and Whittier handle some 2.2 million tons and 0.4 million tons,
respectively. Paved roads in the Rai"lbelt area include the following: the
127 mile Seward-Anchorage Highway which includes 38 miles of the 174 mile
Sterling Highway between Seward and Homer, the 358 mile Parks Highway
between Anchorage and Fairbanks, a 205 mile section of the Alaska Highway
~hat connects Tok Junction with Fairbanks, the 328 mile Glenn Highway
connecting Anchorage with Tok Junction, and the 266 mile Richardson Highway
from Valdez to its junction with the Alaska Highway at Delta Junction.
The only road access through the upper Susitna basin is the 135 mile,
gravel Denali Highway between Paxson_ on the Richardson Highway and Cantwell
on the Parks Highway, and the 20 mile, gravel road from the Glenn Highway
to Lake Louise. The Denali Highway is not open for use during the winter
months.
The Alaska Railroad runs from Seward on the Gulf of Alaska, past Anchorage,
up the Susitna Valley, past Mount McKinley National Park, and down to
Fairbanks on the Tanana River, a distance of 483 miles. The federally
constructed and operated Alaska Railroad was built between 1914 and 1923.
Annual traffic volume varies between 1.8 and 2.3 million tons; coal and
gravel account for 75% of this. It is estimated that the system is working
at only 20% of its capacity. In addition to major airlines within Alaska,
there are numerous small commercial operators plus the highest per capita
ratio of private aircraft in the nation. Many small, remote landing strips
are scattered throughout the Susitna basin, and float planes utilize many
1 akes and streams to ferry freight and passengers to the remote backcountry
areas. In many areas, airplanes provide the only access.
36
--~
-
-
-i'
-
Both Anchorage and Fairbanks are regional economic centers for the
southcentral Railbelt area. Government, trade, and services comprise the
major portion of the area's total employment (Tables 6-8). Construction and
transportation are also important. Smaller employers are the financing,
mining, and manufacturing industries, while agriculture, forestry, and
fisheries employ fewer still. Federal, state, and local governments are the
largest employers and were responsible for $3.3 billion in wages in 1976.
After government, the two groups having the 1 argest employment are trade and
services. Their importance as sources of employment for residents of the
Railbelt area is a further manifestation of the region's two relatively
concentrated population centers and of the high degree of economic
diversity in the Railbelt, as well as levels of demand for goods and
services, which are substantially higher than in most other parts of Alaska.
The importance of construction is due to the high level of expansion
experienced by Anchorage and Fairbanks since 1968. This growth can
partially be attributed to the trans-Alaska pipeline project, which
encouraged new public and private construction.
High levels of employment in the region's transportation industry reflect
the positions of Anchorage and Fairbanks as major transportation centers,
not only for the Southcentral Railbelt area but for the rest of the state
as well. The Port of Anchorage handles most of the waterborne freight
moving into southcentral and northern Alaska. International airports at
Anchorage and Fairbanks serve as hubs for commercial air traffic throughout
Alaska and are important stopovers for major international air carriers.
Anchorage also serves as the transfer point for goods brought into the area
by air and water, which are then distributed by air transport, truck, or by
Alaska Railroad to more remote areas.
Mining, finance, insurance, and real estate play important roles in terms of
the secondary employment they generate in the state. Most people employed
in mining are engaged in petroleum extraction from fields in the North
Slope, Cook Inlet, and the Kenai Peninsula. A substantial portion of the
royalties and taxes collected by the State as a result of oil production in
the area is returned in the form of jobs in state government and through
revenue sharing with various local governments. The total value of oil
37
> )
'"~.)
TABLE 6
STUDY AREA 3 ANNUAL NONAGRICULTURAL EMPLOYMENT BY SECTOR
PERCENT OF STATE
1970 1975 1979 1970 1975 1979
Total __!_ Total ~ Total ~ I _I __!__ -------
TOTAL 1-Nonagricultural Industries 62,690 100.0 113,818 100.0 113,204 100.0 67.8 70.4 68.0
Mining 1,6}0 2.6 2,243 2.0 2,822 2.5 53.7 59.2 48.9
Construction 5,264 8.4 16,359 14.4 8,257 7.3 76.3 63.6 81.8
Hanufacturi n9 I ,850 3.0 2,596 2.3 3,705 3.3 23.7 26.9 28.9
Transportation • Communication &
Ut1lities 6,021 9.6 12,094 10.6 12,062 10.7 66.2 73.4 72.2
Wholesale Trade 5,366 4.7 5,083 4.5 90.8 92.2
12,111 19.3 79.2
Retail Trade 15,965 14.0 18,309 16.2 78.6 76.7
Finance-Insurance and Real Estate 2,520 4.0 4,696 4.1 6,139 5.4 81.3 77.9 76.4
Services 8,868 14.1 20,995 18.4 19,674 17.4 77.8 83.5 69.4
Federal Government 12,372 19.7 13,022 11.4 12,728 11.2 72.4 71.2 11.0
State and local Government 11,585 18.5 17.799 15.6 21,130 18.7 62.6 60.9 57.7
Miscellaneous 52 .I 217 .2 712 .6 26 19.0 98.9
1 Figures may not total correctly because of averaging and disclosure limitations on data.
Source: Alaska Department of labor. Statistical Quarterly. Juneau, AK. (various issues)
) ) ·• .,,, ) ) ----~ } ) ··-, ) ") l ... ~ ] --~ l ~ -Cl )
TABLE 7
HATANUSKA-SUSITNA BOROUGH ANNUAL NONAGRICULTURAL EMPLOYMENT BY SECTOR
PERCENT OF
STUDY MEA 3
1970 1975 1979 1970 1975 1979
Total _!_ Total % Total _!_ _ J_ _t _l _
TOTAL 1-Nonagricultural Industries 1,145 100.0 2,020 100.0 3,078 100,0 1.8 1.8 2.7
Mining * * ll .3 * • .o
Construction 120 10.5 188 9.3 184 6.0 2.3 1.1 2.2
Hanufacturl ng * 30 1.5 40 1.3 * 1.2 1.1
Transportation -Communication & ' Ut 111t les 114 9.6 218 10.8 316 10.2 1.9 1.8 2.6
Wholesale Trade 44 2.2 49 1.6 .8 1.0
174 15.2 1.4
Retail Trade 211 13.4 696 22.6 1.7 3.8
Finance-Insurance and Real Estate 22 1.9 62 3.1 129 4.2 .8 1.3 2.1
Services 179 15.6 288 14.3 447 14.5 2.0 1.4 2.3
Federal Government 106 9.3 124 6.1 97 3.1 .9 1.0 .8
State and Local Government 376 32.8 756 37.5 1,101 35.8 3.2 4.3 5.2
Mhce 11 aneous · * * 21 .7 * * 1.8
* Oata unavailable due to disclosure policy.
1 Figures may not total correctly because of averaging and disclosure limitations on data.
Source: Alaska Department of Labor. Statistical Quarterly. Juneau, AK. (varfous fssues)
---) -~, } -'--l " -, ~--"'1 ·-·· __ :c:::f , :>c~--1 ---~~-') '1 l
TABLE B
VALDEZ-CIHTINA-WHITTIER ANNUAL NONAGRICULTURAL EMPLOYMENT BY SECTOR
PERCENT OF
STUDY AREA 3
1970 1975 1979 1970 1975
Total I Total _!_ Total _..!_ _I -~-
TOTAL 1-Nonagricultural Industries 831 100.0 4. 763 100.0 2,180 100.0 1.3 4.2
Mining * " " " "
Construction 21 2.5 2,518 52.9 86 3,9 .4 15.4
Manufacturing * 14 ,3 19 .9 " .5
Transportation -Communication &
Utilities 61 7.3 389 8.2 472 21.7 1.0 3.2
Wholesale Trade 62 1.3 18 .8 1.2
95 11.4 .8 Retail Trade 321 6.7 181 8.3 z.o
Finance-lnsuranc~ and Real Estate * 73 1.5 70 3.2 " 1.6
Services 99 11.9 709 14.9 445 20.4 1.1 3.8
Federal Government 63 7.6 58 1.2 46 2.1 .5 .4
State and Local Government 464 55.8 613 12.9 840 38.5 4.0 3.4
Miscel hneous 0 o.o • • 0.0 •
• Data unavailable due to disclosure policy.
1 Figures may not total correctly because of averaging and disclosure limitations on data.
Source; Alaska Department of labor. Statistical Quarterly. Juneau, AK. (various issues)
l ) ""---,-.,.
l
1979
X
1.9
"
1.0
.5
3.9
.4
1.0
1.1
2,3
.4
4.0
"
r
:-
i
i.
production revenues for the State is estimated to be $3.3 billion in
1981, 90% of total unrestricted State revenues. The total value of
crude petroleum in 1979 was $5.5 billion; other mineral values (natural
gas, sand and gravel, gold, and others) totaled $259 million.
Most agricultural activities in the southcentral Railbelt area take
place in the Matanuska, Susitna, and Tanana Valleys. The potential for
agriculture in these areas of Alaska is considered favorable, ~though
development of the industry has not been extensive.
Commercial fisheries activity is the oldest cash-based industry of
major importance within the region. The industry has changed
substantially during the past 20 years and continues to be modified as
a result of both biologic and economic stimuli. The salmon industry
has always been a major component in terms of volume and value. Since
1955, the king crab, shrimp, and Tanner crab fish.eries have undergone
major development, and halibut landings have increased substantially in
recent years. The total wholesale value of domestic corrmercial fish
and shellfish for Alaska in 1979 was over $1.2 billion, including a
catch of 459 million pounds of salmon with a wholesale value of $704
mi 11 ion.
The Alaskan forest products industry centers on the resources of two
national forests, the Chugach in southcentral Alaska and the Tongass in
southeastern Alaska. These two forests are the largest in the United
States and account for roughly 93% of the annual Alaskan timber
harvest. The industry is concentrated in the Southeast, and the
principal products of the industry are pulp, cant 1 umber, and round
logs. Over 50% of Alaska's forest products are exported to foreign
countries, principally Japan. Most of the remainder is shipped to the
Lower Forty-Eight. The transfer of 1 ands to native corporations is
expected to increase the avail ability of timber resources, especially
round logs. In general, the industry is cyclical depending upon
housing construction patterns in the United States and abroad.
41
,-
·~~
The tourist industry plays an increasingly important role in the
economy of the region. The numbers of Alaskan visitors have increased
from about 130,000 in 1971 to approximately 505~000 in 1977. Visitors
spent approximate 1 y $37 4 mi 11 ion in 1977.
The results of the baseline study (the socioeconomic profile) will be
utilized in the development of the forecast. ,During 1980, all relevant
forecasting models used by Alaskan institutions, and other potentially
relevant models and studies, were identified and information concerning
them was collected. Next, evaluation criteria were developed and
applied to each relevant model or study in order to compare them. It
was concluded that the primary app~oach to forecasting would be causal
(i.e., the leVel of one variable~ the »caus~ variable,» determines the
level of another variable, the 11 forecasted variable"). It was further
determined that time series or trend analysis and qualitative
(judgemental) analysis would serve as supporting approaches, where
appropriate.
Two types of causal models remained under consideration at the close of
1980. These were economic base and econometric models. Several
methodological structures for an economic base model are being
developed. The advantages and disadvantages of each alternative
structure will be weighed against those of the existing, or of a
,modified, Man in the Arctic Program (econometric} model.
The conclusions of the preliminary impact analysis and assessment of
alternative access routes are that socioeconomic impacts wi 11 vary both
in magnitude and area of concentration depending upon which access
route or combination of access routes is selected, and whether a road
or railroad is used. With the socioeconomic assessment of access
schemes, there is more concern with the origin and type of access than
with the actual route, because these will affect communities throughout
the southcentral part of the state.
42
-
··I"""
With a road from the Parks Highway to the dam site(s)~ effects
generally would be concentrated on the western side of the project
area. An easily accessible road corridor would provide for transport
of construction materials~ equipment and labor as well as
post-construction uses of the upper Susitna basin (such as
recreation).
The impacts of a railroad from the same side would likewise be
concentrated on the western side. However, in every socioeconomic
category~ impacts would be the same or less than with the road. The
single exception would be in rail industry activities, which would
experience major changes.
With a road constructed from the Denali Highway to the dam site(s),
impacts along the Parks Highway-Alaska Railroad corridor would depend
upon whether materials were to be shipped by road or rail to Cantwell
before being transported along the Denali Highway to the access road.
Mitigation planning should include the selection of the route and mode
of access that will avoid or minimize potentially adverse socioeconomic
impacts. The location and relative magnitude of impacts in almost
every socioeconomic impact category will vary considerably depending
upon which mode and origin are chosen for access.
Mitigation planning should also consider minimizing irreversible
impacts on socioeconomic resources. Existing and potential mining
claims and recreational activities should enter into the dam(s) siting
and design decision processes.
3.6-7.06: Cultural Resources Investigation
The University of Alaska Museum developed a five step program to assist
the APA, Acres American, and TES in complying with federal and state
law and regulations concerning protection of cultural and
pa 1 eonto 1 ogi ca 1 resources. The five steps aim toward the f o 11 owing:
(1) locating and documenting archeological, historical, and
43
-
paleontological resources in the study area (reconnaissance level survey),
(2) intensively testing and evaluating these resources to determine their
significance, and (3) proposing mitigation measures to avoid or lessen the
adverse impact which may result from the proposed project.
The methods and defined study area {Figure 2) varied for each aspect of
the study, i.e., archeology, geology, and paleontology. In preparation
for field studies, all necessary permits were obtained, 1 iterature
pertaining to the archeology, ethnology, history, geology, paleoecology,
paleontology, flora and fauna in and near the study area was reviewed, and
avai 1 able aerial photographs were examined. A tentative cultural
chronology for the study area was developed and types of archeological
site locales for each cultural period within geochronologic units were
defined.
Geological analysis performed under this subtask generated data which were
used in selecting archeological survey locales. Data concerning surficial
geological deposits and events of the last glaciation were compiled and
provided limiting dates for the earliest possible human occupation of the
upper Susitna River basin. This information was collected by literature
review and field studies. All the assembled background data, coupled with
paleoecological information, were used to select the sixty locales which
were surveyed in 1980.
A review of the paleontological literature and aerial reconnaissance of
the upper Susitna River basin delineated an area suitabl~ for paleon-
tological investigations. Paleontological studies were conducted (1)
to develop baseline paleontological data within the study area, and (2)
to assess the significance of these deposits and develop appropriate
mitigation measures for these resources.
The archeological reconnaissance implemented surface and subsurface
testing within each of the selected survey locales in an effort to
locate historic and archeological sites. Data were consistently and
systematically recorded on Site Survey forms for each site and survey
locale.
44
(""'
!
!'!"""
.. ,1
The 1980 archeological reconnaissance located and documented one
historic and thirty-three prehistoric sites. An additional four sites
were discovered during a brief survey of one alternative access route
(Corridor 3, Figure 17) north of Watana base camp. The thirty-seven
archeological sites found during the 1980 field season and four sites
previously known {from studies sponsored by the Corps of Engineers)
total forty-one archeological sites now known within the study area.
Site locations are shown on Figure 18; each dot may represent several
sites because of their proximity. It is expected that continued survey
in 1981 will locate additional sites. Sites adjacent to the study area
(and not shown on Figure 18) are known to occur near Stephan Lake, Fog
Lakes, Lakes Susitna, Tyone and Louise, and along the Tyone River.
A large proboscidean femur, probably the bone of a mammoth, was found
~ situ in a bluff exposure at the mouth of the Tyone River. This
documented find, dated at 29,450 ~ 61o14c yr. B.P., extends the
range for Pleistocene fauna and possibly steppe-tundra conditions
southward at least 150 km {93 miles):
For each archeological site which was located, regional maps, site
maps, soil profiles, photographs, and other data were recorded. All
specimens collected were accessioned by the University of Alaska
Museum. Sites were given both University of Alaska Museum accession
numbers and Alaska Heritage Resources Survey numbers. In addition,
sites where surface disturbing activities were to occur {e.g., seismic
trenches, bore holes, and borrow areas) were surveyed to determine if
any cultural material was present. Clearance was given to conduct
geotechnical activities if no cultural material was found.
Impact on cultural resources will vary in relation to the type of
activities that occur on or near them. Based on the Devil Canyon and
Watana dam proposal, most of the sites known to date within the study
area will likely receive direct or indirect impact during construction
and subsequent use and operation of the facility. The impact of
transmission facilities, recreational activities, and upriver and
downriver changes in hydrology and land access and use cannot be
assessed at this time.
45
--l
HY!}ROELECTRIC PROJECT
Lo~ations previously kn~wn
or discovered during 1980 • Figure 18
0 20 Cultural Resource Site locations
0 10 20 30
Kilometers
r
Intensive testing, scheduled for 1981, is designed to collect the data
necessary to evaluate the significance or the cultural resources
discovered during 1980. Following intensive testing and completion of
ancillary studies, the effect of the Susitna Hydroelectric Project on
individual sites can be determined and the appropriate mitigation
measures recommended. Mitigation measures cannot be suggested until the
extent and significance of the sites are known. It is recommended that
non-archeological personnel and preconstruction activities avoid
documented sites until investigations are complete.
3.7 -Subtask 7.07: Land Use Analysis
The Land Use Analysis involves an assessment of the direct land use
effects of the proposed Susitna Hydroelectric Project. The analysis is
designed to evaluate changes in land use which would occur with and
without the proposed project, inc 1 ud i ng the effects of the proposed
dam(s) and reservoir(s), access transportation system, and transmission
line corridors. The objectives of the Land Use Analysis are to describe
past, present, and future land use trends, identify the potential major
changes in land use that would result with the development of the
project, and evaluate these changes.
The methodology for the Land Use Analysis is comprised essentially of
assessing historic, existing, and future land use. The first year has
dealt only with recent historic and present land use. Specific steps
include a literature review, aerial photography and map reconnaissance,
interviews of area residents and agency personnel, field reconnaissance,
and reconstruction of history.
Existing land use in the Susitna Project area is characterized by broad
expanses of open, wilderness area. Those areas where developments have
occurred typically include small clusters of cabins. There are also many
single cabins scattered throughout the basin.
47
"'
,....
'
Most of the existing structures are related to the historical development
of the area which initially involved hunting, mining and trapping, and then
guiding activities associated with hunting and, to a lesser extent, fishing.
Today there are a few lodges mostly used by hunters and other recreationists.
Many lakes in the area also include small clusters of private year-round or
recreational cabins.
There are approximately 109 structures within 30 km (18 miles) of the
Susitna River between Gold Creek and the Tyone River. These include four
lodges involving some 21 structures. Significant concentrations of
residences, cabins, or other structures are found near the Otter Lakes
area, Portage Creek, High Lake, Gold Creek, Chunilna Creek, Stephan Lake,
Clarence Lake, and Big Lake.
Perhaps the most significant use activity for the past forty years has been
the study of the Susitna River for potential hydroelectric development.
Hunting, boating, and other forms of recreation are also important uses.
There are numerous trails throughout the basin used by dog sled,
snowmobile, and all-terrain vehicles (ATVs). Air access is significant; the
many lakes provide landing areas for planes on floats.
There has been little land management activity for the area. However,
federal and state agencies, native corporations, and the private sector
have been involved heavily in the selection and transfer of land ownership
under the Alaska Statehood Act and the Alaska Native Claims Settlement Act.
Most of the lands in the project area and on the south side of the river
have been selected by the native corporations. Lands to the north are
generally federal, and are managed by the Bureau of Land Management.
Impacts associated with the proposed dam(s) and reservoir(s) include the
inundation of four cabins and structures in the Devil Canyon area. Travel
patterns of the few trappers in the upper portion of the proposed Devil
Canyon inundation area will also be affected. A major impact will be the
elimination of Devil Canyon itself, a significant scenic resource. The
Watana reservoir would inundate an area with seven cabins or other
structures. The Watana reservoir also would affect travel patterns of
trappers, but to a greater extent than the Devil Cal")yon reservoir as this
area contains more of the secondary drainages utilized for trapping activity.
48
-
-
-I
"""" I
Impact assessment during the first year concerning land use analysis of
access alternatives is summarized below. A road from the west to the dam
site(s) on the north side of the Susitna (Corridor 1, Figure 17} would
create increased traffic and activity affecting the Parks Highway and
communities situated on it. It is likely that commercial and residential
uses would be affected with corresponding effects on land values. Some
twenty-four cabins and other residential structures along this corridor
would be affected, in addition to two lodges involving ten structures.
A road from the west, located on the south side of the river (Corridor 2),
would create impacts similar to those of Corridor 1 on the Parks Highway
and the conmunities there. Residential and commercial use and land values
would be affected. ·Ten buildings associated with Stephan Lake Lodge and
seventeen other cabins and residences would be affected.
With a rail route from the west (Corridor 2), there would be some increase
in activity in communities near the Alaska Rai1road, but probably less than
with a road corridor. Rail would tend to restrict public access to land
more than a road would. However, as a rail-head, the general area of the
communities of Sherman, Gold Creek, and Canyon might be affected in terms
of residential and commercial uses. The same impacts on structures as with
a road corridor would occur.
A road constructed from the Denali Highway to the dam site(s) (Corridor 3)
would affect the fewest number of structures (four) and one small lodge.
Impacts along the Parks Highway-Alaska Railroad corridor would depend
upon whether materials were shipped by road or rail to Cantwell before
being transported along the Denali Highway to the access road. Because of
the openness of the land traversed by this corridor, ATV use and associated
impacts could be expected to increase considerably.
The most significant aspect of the analysis of access route schemes
relates not so much to various impacts associated with a given
individual scheme, but to the concept of access itself, in any form, to the
interior of the Susitna basin. The provision of a means by which the
. general public can easily and frequently venture inland to an essentially
pristine wilderness area potentially w~ll induce profound alterations
49
-
in the character of the Susitna area, affecting both small
concentrations and isolated residences, peripheral commercial and
transportation systems, resource utilization and the level of
recreational activity, visual and aesthetic factors, and the overall
natural character of the area. In addition, these effects will have
ramifications concerning the extent, adequacy, and need for management
activity (e.g., fish and game, land, etc.), and concerning changes in
land values and development.
3.8-Subtask 7.08: Recreation Planning
"fhe Recreation Planning effort involves the preparation of a Recreation
Plan for the proposed Susitna Hydroelectric Project. Subtask 7.08 was
modified during 1980 to incorporate the objective of Subtask 10.06 (to
prepare Exhibit R of the FERC license application), as described in the
Plan of Study. Assessmen~ of the effects of the hydroelectric project
on existing recreational use of the Susitna baiin is being performed
under Subtasks 7.05 and 7.07 (Socioeconomic Analysis and Land Use
Analysis).
The Recreation Planning effort focuses on the immediate reservoir
area(s) and any additional lands recommended for acquisition for
recreational purposes. The objective of this effort is to develop a
plan for an optimal mix of pub1ic recreational opportunities. As such,
the planning process will do the following: (1) result in a variety of
activities and level of development desired by the public, (2) analyze
the environmental setting and recommend developments consistent with
the environmental limitations of the area, (3) balance the development
of facilities with the capacity of natural resources to sustain the
resultant use, (4) incorporate unique natural features into the plan,
(5) result in a plan consistent with the planning guidelines and
objectives of the agency ultimately responsible for managing the public
use·of recreational lands and waters, and (6) maximize compatibility of
the plan with the total hydroelectric operation.
50
'-
r
!"""
-
The methods for recreation planning include the following: (1) a literature
review of recreation data, (2) a summary of resource data, (3) an
assessment of recreation resource potential, including field data
collection and site analysis, (4) the identification of potential
management structure, (5) the development of initial concept plans, (6) a
concept plan survey, (7) the selection of the best concept plan, (8) a
public participation survey, (9) detailed site feasibility studies, (10)
agency and public review, and (11) the development of the final plan.
During 1980, the first six steps were completed. Field work included
analysis of project lands for potential as recreation sites. Seventy-eight
sites currently are under consideration.
Also during the first year, several preliminary plan sketches were
developed. These were narrowed to five concept plans incorporating the
various possible recreation sites. The plans provide a range of facilities
and recreational opportunities, from minimal, wilderness development and
primitive facilities to a full spectrum of highly developed facilities.
These plans are briefly summarized below.
Approach 11 A11 -A Minimally Developed and Managed Wilderness
This approach could be used in the event that public access by road to
the Susitna reservoir areas were restricted or not permitted at all. In
this case, development would probably be limited to a visitor information
center on the Parks Highway. Access by float plane would likely be
extended to include the reservoirs. Access by canoe, kayak, and river
boat via the upper Susitna, Maclaren, and Tyone Rivers would continue.
Land use surrounding the project area would probably be much the same as
at present with management 1 imi ted to fish and game and the regulation of
mining activities.
Approach 11 B11 -Managed Wilderness with Limited Access
In the event that road access to both reservoirs were possible, the area
could be managed as a wilderness recreation area, with development
limited to minimal interpretive services, primitive campgrounds, and
simple boat ramps at both dam sites. These ramps would facilitate
51
-
r-
.. i
'i
'I"""'
i
,.,,.
-
access by boat to the reservoir shorelines and adjacent areas for
camping, hunting, fishing, and other backcountry activities. As in
Approach "A", a visitor center would be built on the Parks Highway.
Information would be provided on the Denali Highway should access be
available at this location. A tour boat service would be offered at the
Devil Canyon dam site for day tours of the reservoir.
Approach 11 C" -Watana Reservoir Development
One possible approach to more extensive recreational development is to
offer highly developed facilities at the Watana dam site and only minimal
interpretive services at the Devil Canyon dam site. In addition to the
services.offer~d at both reservoirs in Approach "B", there would be
greater development at the Watana dam site to accommodate increased
visitor use. Simple backcountry camp sites would be provided at selected
locations around the Watana reservoir; additional improvements would be
made at the mouth of Jay Creek. More intensive resource management would
be necessary around the Watana reservoir, but the remaining project area
would still be managed as wilderness. As in· Approaches "A" and "B",
visitor information would be available at the highway entrance(s).
Approach "0" -Devil Canyon Reservoir Development
In this approach highly developed facilities would be offered at the
Devil Canyon reservoir and dam site and only minimal facilities at the
Watana dam site. The Devil Canyon area would be developed and managed
intensively to provide a diversity of recreational opportunities, while
the Watana reservoir area could be developed and managed in a manner that
would maintain its wilderness character.
Approach "E" -Development and Management Throughout
This approach involves a high level of recreational development and
offers a wide variety of recreation activities around both reservoirs.
Complete visitor facilities would be located at the dam sites, with
additional improvements made at the Jay Creek site, and backcountry
boat-in camp sites built at five locations. Intensive resource
management would be necessary throughout much of the recreation area to
reduce conflicts between uses and to maintain the quality of the
environment.
52
-i
-
.....
-~
. ' i
r-
1
i
r
r
To solicit public reaction to Approaches "A" through "E" a concept plan
survey was developed and distributed to 2250 randomly selected persons
in Anchorage, Fairbanks, and the Railbelt area. Results of this survey,
input from a public workshop in March, 1981, and identification of an
access scheme by the Alaska Power Authority will be used in developing
and selecting the best concept plan during 1981.
3.9-Subtask 7.09: Susitna Transmission Corridor Assessment
The objectives of the Transmission Corridor Assessment performed to date
are as follows: (1) to begin a literature search, (2) to review existing
Susitna transmission studies, (3) to compare proposed transmission line
corridors from an environmental standpoint, and (4) to make a
preliminary identification of those corridors that warrant further
consideration as viable routes.
The literature search was initiated. Information was gathered from
several libraries, institutions, and authorities. This is an on-going
effort.
Existing Susitna transmission studies were reviewed. These include the
1979 IECO/Retherford draft report for the Alaska Power Authority, the
1975 Corps of Engineers' Interim Feasibility Report, and other
associated reports. A critical review of the Corps' report {11 Critique
of the Corps of Engineers' Assessment for Transmission Systems") was
prepared byTES in February, 1981. It concluded that for a preliminary
feasibility study the Corps' method of environmental inventory was quite
complete but that their impact assessment could be found inadequate
because the analysis was unquantified. The critique concurred with the
transmission corridors preferred by the Corps.
Locations of transmission corridors under consideration for the present
Susitna study were obtained from Acres in November, 1980. Because
another consultant to APA would be doing the feasibility analysis for an
intertie between Willow and Healy, the effort of the Susitna
Transmission Corridor Assessment was limited to investigations of
53
-
'.
r
......
....
I
alternatives in three study areas: Healy to Fairbanks, dam sites to the
Intertie, and Willow to Anchorage/Pt. MacKenzie. Habitat information was
gathered and an aerial reconnaissance was made of corridors in these
three areas.
In February, 1981, additional corridor alternatives in the three areas
were received from Acres; these were to be included in the environmental
evaluation. The locations of the alternative corridors are shown in
Figures 5-7. The evaluation efforts culminated in the preparation of the
TES report "Preliminary Environmental Screening of Alternative
Transmission Corridors" in March, 1981.
Evaluation of the alternative corridors began with the development of an
environmental inventory for segments of each corridor. The following
parameters were included in the inventory: approximate length,
approximate number of road and river/creek crossings, topography, soils~
land ownership status, existing or proposed developments, existing
rights-of-way, scenic quality and recreation, cultural resources,
vegetation, fish resources, birds, furbearers, and big game.
Environmental constraints were then identified for each corridor. These
constraints included the following: length, topography and soils, land
use, aesthetics, cultural resources, vegetation, fish resources, and
wildlife resources. Each corridor was given an environmental rating to
indicate whether it warranted, probably did not warrant, or did not
warrant further consideration as a viable route. This was a subjective
rating and indicated the relative worth of each corridor from an
environmental standpoint .
One corridor each in the northern and southern study areas (ABC and ADC,
respectively) and one corridor (encompassing corridor segments ABCO,
ABCF, ACD, and ACF) in the central study area warrant further
consideration (Figures 19-21). (Also shown on Figures 19-21 are those
corridors rated as probably not warranting further consideration.)
54
......
I
Miles
0 5 10 15 ----0 5 10 15 20 25
Study Corridor
lntertie
(Hypothetical)
•••••
0
Figure 19
Transmission Corridors
Surviving Preliminary Screening
Northern Study Area
"--1
Study Corridor
lntertie
{Hypothetical)
•••••
0
0
Miles
5 10
5 10 15
Kilometers
.. --1
15
20 25
l
POWER AUTHORITY
susrfNA HYDROELECTRIC PROJECT
Figure 20
Transmission Corridors
Surviving Preliminary Screening
Central Study Area
) -1
') ]
Study Corridor
lntertie
(Hypothetical)
•••••
0 5
0 5
10
10 15 20
Kilometers
15
25
,, 1
ALASKA POWER AUTHORITY
Figure 21
Transmission Corridors
Surviving Preliminary. Screening
Southern Study Area
-i
-
. ,....
-i
......
Recommendations were made for use of construction techniques which would
mitigate potential impacts. These included winter construction in
wetlands, helicopter-based construction in areas that are remote or too wet
for surmner access, use of techniques that allow for minimum clearing of
vegetation, and use of aesthetically designed towers.
3.10-Subtask 7.10-Fish Ecology Studies
The following are the specific objectives of TES with respect to fish
ecology in the first year of the program: (1) identify areas of potential
impact and the information necessary to assess these impacts, (2) locate
available information appli~able to the Susitna River and the Susitna
Hydroelectric Project, (3) identify information deficiencies, and (4) aid
in the selection of a project development scheme. In addition, assistance
has been given (under Subtask 7 .04) in the development of hydrology and
water quality samp1 ing programs that wi 11 be beneficial .in ascertaining
possible impacts upon the fishery resource and ·aid in mitigating these
impacts.
ADF&G baseline fisheries studies commenced in late 1980. TES has assisted
in the preparation of the ADF&G Procedures Manual. Data from the field
studies will not be available until the completion of ADF&G•s first 1981
Quarterly Report.
TES is collecting pertinent literature on impact assessment and mitigation
measures applicable to the Susitna Hydroelectric Project. The compilation
of fundamental life history and ecology information on selected anadromous
and resident fishes has also been assumed by TES to supplement the fishery
field program results. This information is being obtained by contacting
individuals with expertise in specific facets of fish ecology, searching
personal libraries and files, gathering information from university and
federal agency libraries, reviewing indexes of appropriate foreign
publications, examining "in-house 11 programs for research and progress
reports of appropriate federal and state agencies, as well as universities,
and reviewing reports from the management agents of the Alaska Department
of Fish and Game for the Susitna-Cook Inlet area and adjacent waters .
58
-
As a guide to compliance with FERC's criteria for license application,
potential impact issues (Table 9) and the kinds of engineering,
hydrological and biological information required have been compiled.
This information is to be supplied toTES from Acres, R&M Consultants and
ADF&G.
Acres has been provided with, by request and for use in their design
considerations, information and reconrnendations concerning downstream
flow, total dissolved gas pressure, and temperature of the discharge
water. Reregulation of downstream flow from daily peaking operations has
been recommended as an essential part of ~ny deyelopment plan.
Potential program modifications and the concerns of federal, state, and
local agencies in regard to the fish eco1?9Y studies have been addressed
by TES. Recorrnnendations have been submitted to Acres American.
3.11 -Subtask 7.11: Wildlife Ecology Studies
The baseline ecology of big game is being studied by ADF&G. Much of
the following summary concerning big game is taken from draft sections
of the ADF&G 1980 Annual Report. Impact assessment and mitigation
planning for big game is the responsibility of TES and its consultants,
as are the studies of furbearers, birds, and non-game mammals.
3 . 11. 1 - B i g G arne
Biometrics and Data Processing
Field investigations of big game are being facilitated by the
use of radio-collars. The study involves (1) repeated habitat
descriptions of habitats and repeated physical locations of big
game, and (2) a body of data requiring initial standardization
and periodic computer-aided analysis. Technical and conceptual
problems associated with these requirements have been outlined
and proposed solutions presented. Computer resource requirements
have been identified; also, progress has been made in acquiring
those resources and developing a production system.
59
-!
·--
;·r-
TABLE 9
POTENTIAL FISH ECOLOGY IMPACT ISSUES BY PROJECT STAGE
(a)
Project Stages
CC, CD, RD, 0
co, 0
CD
CD, 0
RD, 0
CD, RD, 0
CO, RD, 0
RD
0
0
0
0
CD, 0
a. Project stages:
Potential Impact Issues
Changes in the water quality
Alteration of the temperature structure of the
stream
Possibility of excessive dissolved gas (nitrogen
and oxygen) concentrations caused by plunging
flows
Changes in the chemical and physical conditions in
spawning areas of anadromous fish
Impact of temperature structure of reservoir
on reservoir management and downstream conditions
Reduction of turbidity downstream during the
summer, resulting in increased predation
Winter turbidity changes in the reservoir and
downstream (including potential problem of silt
trapped in layers because of density differences)
Increase in nutrients in the reservoir and
downstream from leaching
Changing water quality conditions under the ice
as a result of operation
Development of new ice-free areas with increased
predation and density of small fishes
Development of frazil ice downstream
Changed ice thickness downstream (because of
increased winter flows) affecting temperature and
downstream movement of fish
Summer and winter flow changes and the ~mpact on
fish reproduction, growth, and predation as well
as critical flows for transportation (including
access to tributaries and sloughs)
CC -Construction of the cofferdam and river diversion
CD Construction of the dam and reservoir filling time
RD Development of limnological conditions and fishery management
in the reservoir after filling
0 Operational stage including start-up
-
. F""
!
.....
(a)
Project StaQeS
0
CD
0
CD, 0
0
CD, RD, 0
CD, RD, 0
CD, RD, 0
RD, 0
CD, 0
CD, RD, 0
CD, 0
CD, RD
CD, 0
TABLE 9 {Cont•d)
Potential Impact Issues
Effect on present type of fish collection devices
Extension of upstream anadromous fishery (if
WatBna is constructed first)
Bank scour caused by piping effect of increased
flows under the ice
Bed scour as affected by changing flows and ice
Potential for increased production by the addition
of new spawning areas and new rearing areas
Potential loss of many present productive areas
Formation (and management) of new lakes
(impoundments)
Changes in tributary stream access for fish
Changes in personal use fishery
Potential stranding and exposure of redds due to
diel variation
Changes in the habitats of resident fish
popu 1 at ions
Changes in the stream channel in terms of creation,
alteration, or elimination of habitat
Loss of existing fishery in impoundment area
In general, effects on rearing, fish passage and
egg incubation in the Susitna River from its
mouth upstream to Devil Canyon
F'
'
-I
!'*'
I
r I
Brown and Black Bear
Both black bear {Ursus americanus) and brown bear (.!:!_. arctos)
populations in the vicinity of the proposed dam{s) appear to
be healthy and productive. Brown bears occur throughout the
study area (Figure 10) while black bears appear largely
confined to the finger of forested habitat along the Susitna
River. This finger becomes progressively narrower upstream.
In 1980, twenty-seven brown bears and twenty-sev_en black bears
were captured, utilizing helicopter darting techniques.
Adults were marked and radio-call ared and were periodically
relocated.
Winter denning sites (1980-81) of nine radio-collared brown.
bears are well above the proposed impoundment level. Brown
bear uses of areas that would be directly affected by the
proposed impoundments appeared greatest in the early spring
following the bears' emergence from dens. Brown bears may be
attracted to these areas in the spring by the early
availability of both vegetable and animal foods. The proposed
impoundments wi 11 presumably reduce this spring habitat.
The most interior run of salmon known in the study area occurs
at Prairie Creek, a feeder stream running from Stephan Lake to
the Talkeetna River. Four of eleven radio-collared brown
bears moved to Prairie Creek during the surrmer salmon run.
Brown bear movements to or from Prairie Creek may be inhibited
by impoundments or access routes, thereby reducing the
availability of this salmon resource to an appreciable
proportion of the bears in the study area.
Studies in the headwaters of the Susitna River conducted by
ADF&G in 1979 estimated a brown bear density of 1 bear/41-62
km2. It is conjectured that brown bear density in the
impoundment area is roughly comparable. If so, the
impoundment study area of 3,500 km2 contains approximately
seventy brown bears.
62
-' I
-
Records of capture and subsequent locations for black bears
suggest that black bear distribution in 1980 was largely
confined to or near the spruce forests found in the vicinity
of the Susitna River and its major tributaries. These are the
habitats which will be most severely affected by the proposed
impoundments; the restricted nature of black bear distribution
in the study area suggests that these populations may be
highly vulnerable to habitat losses by inundation as well as
to disturbances associated with construction and improved
access.
Black bears were observed to cross the Susitna River more
frequently than brown bears. This activity probably reflects
the re 1 at i ve proximity of b 1 ack bear home ranges to the river.
The motivation for or importance of these river crossings for
black bears is not known, nor is it yet known whether the
proposed impoundments waul d represent ·a significant barrier to
such crossings.
A 11 five of the radio-colla red black bears with 1980 dens in
the vicinity of the Watana impoundment denned below 670 m
(2,200 feet) elevation, which is the approximate, proposed
high water mark of the Watana impoundment. Two of nine black
bears denning in the vicinity of the Devil Canyon impoundment
denned below 442 m (1,450 feet), which is the approximate,
proposed high water mark for this impoundment. Thus, it seems
clear that many den sites utilized by black bears in 1980
would be inundated by the proposed impoundments. The impact
of this den inundation on black bear populations is as yet
unknown.
Black bear density appeared variable throughout the study
area. A very rough estimate of 1 bear/4.1 km2 was offered
for one area of relatively high density. Further study will
ultimately permit a more accurate estimate of bear populations
in the impact area.
63
-
-i
-
-
Caribou
The Nelchina caribou herd, which occupies a range of about
50,000 km2 (20,000 mi2) in southcentral Alaska, has
been important to hunters because of its size and proximity to
population centers. The proposed Susitna impoundments would
inundate a very small portion of apparently low quality
caribou habitat. However, concern has been expressed that the
impoundments and associated development might serve as
barriers to caribou movement, increase mortality, decrease use
of nearby areas and tend to isolate subherds. The overall
objectives of the current study are to evaluate the potential
impacts of the proposed hydroelectric project on Nelchina
caribou and to suggest possible mitigating measures.
Because of the changeab 1 e nature of car~ bou movement patterns,
short-term studies of distribution and movements must be
tempered with historical perspective. It is fortunate that
the Nelchina herd has been studied continuously since about
1948; records previous to that time have been reviewed also.
The primary methodology for this study is the repetitive
location of radio-collared caribou. Population estimates are
made with a modified version of the aerial photo.,-direct count-
extrapolation census procedure.
Late winter distribution of caribou in 1980 was in the
Chistochina-Gakona River drainages, the western foothills of
the Alphabet Hills and the Lake Louise Flat. The two main
routes to the traditional calving grounds in the northern
foothills of the Talkeetna Mountains were (1) across the Lake
Louise Flat into the calving area via the lower Oshetna River
and (2) across the Susitna River in the area from Deadman
Creek to the big bend ~f the Susitna. Calving occurred
between the Oshetna River and Kosina Creek from 900 to 1,400 m
(3,000 to 4,500 feet) elevation. The main summering
64
-
-
concentration of Nelchina caribou occurred on the northern and
eastern slopes of the Talkeetna Mountains between Tsisi Creek
and Crooked Creek, primarily between 1,200 and 1,800 m (4,000
and 6,000 feet). Most caribou were located on the Lake Louise
Flat during the rut. During early winter, the herd was split
in two groups; one was in the Slide Mountain-Little Nelchina
River area, and the other was spread from the Chistochina
River west to the Gakona River through the Alphabet Hills to
the Maclaren River.
It appeared {based on only eight months data) that at least
two small subherds with separate calving areas existed, one in
the upper Talkeetna River and one in the upper Nenana-Susitna
River drainages. Insufficient data were available to evaluate
the status of the Chunilna Hills group.
The Nelchina caribou herd was estimated to contain 18,558
animals in October, 1980. Herd composition was estimated at
49.0% cows, 30.3% bulls and 20.7% calves.
It was apparent from historical records (and to a lesser
degree from movements of radio-collared animals) that the
proposed Watana impoundment would intersect a major migratory
route. It seems possible that the impoundment could be a
barrier t·o movement and a potential source of mortality,
particularly during spring migration when females are in
relatively poor condition and various combinations of ice
shelving, ice sheets, overflow, ice floes. and wind-blown glare
ice could occur. The impoundment could tend to isolate the
northwestern corner of the Nelchina range, an area which has
been heavily used by caribou in the past. Access routes
{roads, railroads, and air fields) could affect caribou
movements depending on their locations and amount of use. The
proximity of the calving grounds to the Watana impoundment is
of concern because of the traditional fidelity to this calving
ground and the possibility that increased human access and
activity could result in reduced use.
65
•""'
-
-
·-
The Devil Canyon dam site and impoundment appears to have
virtually no potential to impact Nelchina caribou. The Watana
site, however, would almost certainly have negative impacts,
although the extent cannot yet be predicted.
Dall Sheep
No sheep were radio-collared, but an aerial survey of known or
suspected Dall sheep habitat in the vicinity of the proposed
project was conducted in July, 1980, to delineate sheep
distribution. Three discrete areas of habitat were
identified. Sheep in all three areas may be subject to
disturbance from construction activities, helicopter traffic
or access routes, although disturbance may be reduced or
eliminated through routing or scheduling of human activities.
Sheep occupying the Watana Creek Hi 11 s were observed in lowland
habitats that might be inundated by the proposed Watana
impoundment. Little is known about the importance of this habitat
to the population, but it is possible that some attractant such as
a mineral lick occurs there. If so, assessment of the impact of
the Susitna Project on this sheep population will be more complex
than anticipated.
Wolverine
During April and May, 1980, five adult wolverines were captured
and four (three males, one female) were radio-collared.
Eighty-six radio locations were obtained during 1980. Only three
occurrences of river crossings were documented during the study
period. Within their home ranges, all radio-collared wolverines
showed a fidelity to upland shrub (willow-birch) habitats and
to southerly and westerly slopes.
66
-
~
' i
--
Potential impacts on wolverines include the following: a loss of
habitat due to inundation and construction (including roads and
transmission lines), a probable reduction in prey densities,
increased competition with other scavengers and predators, and a
readjustment of home range size and seasonal movements.
There is evidence that wolverines are intolerant of human
disturbance. Impacts from disturbance might be influenced by
the timing and placement of construction activities. For
example, activities on southerly and westerly slopes are more
likely to affect wolverines than are those on northerly or
easterly slopes.
Downstream Moose
The present study focuses on the seasonal distribution of moose
populations using the lower Susitna, the relative magnitude of
seasonal moose use of the Susitna floodplain, and the relative
use of associated habitats. In April, 1980, ten moose were
equipped with radio/visual collars. Periodic relocation flights
were conducted to determine each moose•s location, activity, and
association with other moose and with habitat type. The small
sample of marked moose, and the difficulty of spotting unmarked
moose in the timber, made determination of major seasonal
patterns of population distribution impracticable, although a
variety of individual patterns was noted. More work on seasonal
movement and distribution is needed.
A preliminary survey of browse distribution and use along the
river showed a mean of 1.4 browse p1antsfm2. Willow, most
prevalent in early successional stages, was consistently well
browsed. Birch, near the river, was also a preferred forage.
Cottonwood, rose, and highbush cranberry were less used, and
alder was largely unused.
67
-
-
-
r-·
Since moose forage is associated with the riparian area
freqently disturbed by fluviatile processes, it would be
expected that a major change in downstream flow patterns would
influence downstream plant communities and, through them,
downstream moose populations. The potential for such impact
has not yet been assessed. The potential for managing
downstream plant communities for increased production of moose
forage, if this proves a desirable avenue of mitigation,
appears excellent.
Upstream Moose
During April, 1980, forty adult moose were captured and each
was radio-collared. Biological specimens were collected to
evaluate the physical condition of each moose. Results were
compared with those from a 1977 ADF&G study in the Susitna
area and with data on other Alaskan moose populations.
The physic a 1 condition of Sus it na moose appears to have
deteriorated since 1977. This, in conjunction with the
possibility of a lower pregnancy rate and an older age
structure, suggests that this population is declining or is
about to decline.
Forty-three radio-collared moose (three were fromearlier
studies} were radio-located on 563 occasions. Of that total,
9.2% occurred at elevations that would be inundated by the
proposed impoundments. Most moose exhibited relatively short
movement patterns, spending late winter and early spring at
lower elevations and occupying upland areas in summer and
fall. Only one moose was observed calving in the areas
proposed to be inundated. Migratory moose were 1 ocated in
areas east of Jay Creek except for one moose located at Watana
Creek. Moose river crossings on the Susitna by radio-collared
animals were concentrated at the mouth of Fog Creek, between
Watana and Jay Creek, and above Goose Creek. The proposed
impoundment zones cti d pot appear to harbor any significant
rutting groups of moose.
68
-I
·-
Rates of calf production were c9mparable with those observed
in 1977 and 1978. Mortality of newborn moose calves was high
and comparable to that observed in 1977 and 1978 when brown
bears were identified as th~ largest cause of mortality. Of
·the moose observed during a winter distribution survey
conducted in March, 1980, 6% were located in areas to be
inundated. Tracks suggested that considerably more moose had
been in these areas earlier in the winter.
Sex and age composition surveys and a random stratified census
were conducted in the study area during November, 1980. It
was estimated that 2,046 ~ 382 moose occupied the areas north
and south of the proposed Wat ana impoundment. A crude
population estimate of 1,151 moose was made for the project
area lying west of Kosina and Watana Creeks.
The potential impacts of the proposed project include the
following: loss of habitat and mortality of moose occupying
the impoundment areas, decreased range carrying capacity of
adjacent areas due to overstocking by the d i sp 1 aced moose,
disruption and perhaps prevention of both sedentary and
migratory moose crossings of the Susitna River, alteration of
weather patterns causing increased mortality and decreased
productivity, and an increase in accidental deaths. It was
suggested that the Watana impoundment would have a larger
impact on moose than the Devil Canyon impoundment.
Wolves
During 1980, Twenty-three wolves from five separate wolf packs
were radio-collared in an effort to identify some packs which
could be impacted by hydroelectric development. An additional
four or five wolf packs were suspected of occupying parts of
the project area, but no wo 1 ves from these packs were captured
because of the late arrival of telemetry equipment and
69
poor snow conditions. During 1980, 556 radio locations were
obtained on the twenty-three radio-collared wolves. A minimum
of forty wolves were known to inhabit the study area in spring
1980. By fa 11, the packs had increased by 93% to an estimated
seventy-seven wolves.
Territory sizes for the five studied wolf packs averaged 1,171
km2 (452 mi2) and ranged from 549 to 2,126 km2
(212 to 821 mi2). Known and suspected wolf territories
were mapped. Based upon track counts, public sightings, and
radio telemetry st~dies,. it was determined that at least four
and perhaps five wolf packs would be directly affected by the
proposed impoundments. An additional five wolf packs could be
indirectly affecte~ by the proposed project if it results in
lower moose densities or disrupts the movement patterns of
migratory moose.
Radio-collared wolves were observed on forty-eight kills
during
kills.
of a 11
1980. Moose of all age classes comprised 52% of the
Calves were the most common moose age class. Caribou
age classes comprised 38% of the observed kills.
During 1980 two packs were intensively monitored to determine
rates of predation on moose. Predation rates varied from 1
k ill/4. 0 days for a pack of four wo 1 ves to 1 k i 11/4.9 days for
a pack of eight wolves. Moose counts were conducted in each
pack terri tory and the observed numbers were compared with
predation rates. It was concluded that these two wolf packs
were a significant cause of calf (short yearling) mortality.
The locations of seventeen wolf den and rendezvous sites have
been observed in the study area si nee 1975. Thus far, two
wolf packs have been discovered which have either den or
rendezvous sites in areas that would be directly impacted by
the project.
70
lf"'
I
The most important potental impact of the Susitna
Hydroelectric Project on wolves would occur indirectly due to
reductions in prey density~ particularly of moose. The
disruption of movements or reductions in migratory moose
densities may reduce wolf densities for considerable distances
away from the areas actually inundated. Temporary increases
in wolf density may occur in the project area due to the
displacement of moose and caribou from the impoundment areas.
Direct inundation of wolf habitat, particularly den and
rendezvous sites~ may also lower wolf densities. Additional
wolf mortality will probably occur due to increased hunting
and trapping activities resulting from publicity concerning
the area•s wildlife and as access becomes developed.
3.11.2 -Furbearers
Progress was made on all aspects of furbearer and habitat
inventories and impact assessment during the first year of
investigation. Emphasis was placed on population surveys and
seasonal furbearer /habitat re 1 at i onshi ps. Furbearers that may
inhabit the impact areas include red fox~ coyote, lynx, mink,
pine marten, river otter, short-tailed weasel, least weasel,
muskrat and beaver.
General estimates of furbearer abundance and habitat use during
periods of snow cover were based upon aerial transects and
aerial checks of lakes and ponds. Surveys of aquat.ic furbearers
were conducted from a river boat during August in the downstream
area. Movements of individual foxes, marten and mink, and their
preference for particular habitats were monitored by radio
telemetry. Diets of carnivorous furbearers were investigated by
identifying food remains in their droppings and food remains in
the digestive tracts of furbearers taken by trappers in the
area.
71
Populations of all furbearers identified for investigation exist
within the impoundment areas and along the Susitna River from Devil
Canyon to Cook Inlet; however, numbers of coyotes and lynx are
presently low. Beavers and muskrats are present along much of the
river and its main tributaries. Beaver numbers increase
progressively from Devil Canyon downstream to the confluence of the
Kashwitna River.
Five red fo.xes were outfitted with radio-cellars. Red foxes in the
study area used dens 1 ater in the autumn than has previously been
reported for foxes. Some red foxes appear to uti 1 i ze the shores of
the Susitna River and deltas of tributaries during surrmer and autumn,
then shift to alpine zones in winter as snow depth increases along
the river. Other foxes appear to remain above timberline throughout
the year.
Four pine marten and two mink were radi6-collared during 1980. It
appears that adult male marten have mutually exclusive home ranges
during summer with creeks in some cases forming the boundaries.
The activity data gathered during autumn suggest that marten at
that time are generally nocturnal with a minor activity peak around
noon.
Loss of habitat and reductions in furbearer numbers may be expected
in areas inundated, where roads are constructed, and at borrow
pits. It is expected that pine marten will be most severely
affected, followed in decreasing order by mink, fox, otter and
weasel. High levels of human activity and noise pollution during
furbearer breeding and denning seasons could severely alter the
reproductive success of all species. Projected changes in flow
rates of the Sus itna River downstream from the Dev i1 Canyon
impoundment could result in marked changes in the habitats
available to aquatic furbearers. Beaver and muskrat could benefit
from delayed freeze-up in autumn and possibly benefit from more
stable rates of flow. The anticipated seasonal drawdown of the
Watana impoundment is likely to p~event the impoundment from
becoming suitable habitat for beaver, muskrat, mink and river otter.
72
!""',
{ i
Changes in impoundment design to lower and/or stabilize the pool
levels would mitigate the negative impact on furbearers by
reducing the Toss of foraging and denni ng habitats. Loss of
habitat from construction of dams, borrow pits, access roads and
diversion tunnels could be minimized by utilizing borrow and
fill sites as close as possible to actual construction.
Regarding the access route to impoundment sites, the best access
route would probably be Corridor 2, from Gold Creek (south of the
river) to Devil Canyon, then across the river and following
Corridor 1 from Devil Canyon to the Watana site (Figure 17). If
only the Watana dam is to be constructed, Corridor 3 from the
Denali Highway to the Watana site would be preferred from the
standpoint of the impact on furbearers.
Creek drainages and adjacent areas are extremely important to
furbearers. It is recommended that access roads and construction
activities be outside creek valleys wheri practical.
3.11.3 -Birds and Non-Game Mammals
The first year 1 s field studies of the birds and small (non.-game)
mammals of the upper Susitna River basin were conducted from 6
July to 4 October 1980. The overall study area extended from
near Sherman on the west to the mouth of the Mac 1 aren River on
the east and for approximately 15 km (10 miles) on either side
of the Susitna River channel (Figure 14). Within this region
during 1980, {1) ten 10.-ha (25-acre) intensive sites were
established for subsequent animal-habitat studies, ( 2) thirteen
small mammal traplines were established and, between 26 August
and 2 September, sma 11 mamma 1 s in the respective habitats of
these traplines were sampled, (3) a raptor survey was flown on 6
July, {4) fall waterbird surveys were flown between 7 September
and 4 October, and {5) general bird and small mammal surveys
were conducted throughout the period at a number of more-or-1 ess
random locations. Data for the region are still very limited,
so interpretations made are preliminary in nature and conclusions
are tentative.
73
-
-
r
r-1
~I
~
I
Intensive study plots were established in vegetation types that
represented each of the major woody avian habitats present in
the region in sufficient size and uniformity to accommodate a
square 10-ha plot: low birch shrub thicket, medium birch shrub
thicket, low-medium willow shrub thicket, tall alder thicket,
cottonwood forest, paper birch forest, white spruce-~aper birch
forest, white spruce forest, white spruce scattered woodland,
and black spruce dwarf forest. Small mammal traplines were
established in all but the low birch shrub thicket and, in
addition, in sedge-low shrub meadow, tall forb meadow, and black
spruce-white spruce forest.
Thirteen small mammal species were found during 1980, and the
presence of three others was suspected. During the fall survey,
red-backed voles and masked shrews were the most abundant
species trapped; these, plus the dusky shrew, appeared to be
habitat generalists, occupying a wide range of vegetation types.
Meadow voles and pygmy shrews were least abundant and the most
restricted in their habitat use, the former occurring only in
meadows and the latter in forests.
Tall forb meadow, sedge-low shrub meadow, and cottonwood forest
had the most small mammals and most diverse communities, while
paper birch forest and white spruce forest had the fewest
individuals and lowest diversities.
A total of 115 species of birds was recorded during the 1980
field season; the most abundant were scaup sp. and Common
Redpoll. Blue-winged Teal, American Kestrel, White-tailed
Ptarmigan, Short-eared Owl, Northern Phalarope, Greater
Yellowlegs, Lesser Yellnwlegs, Surfbird, Sanderling, and
Pectoral Sandpiper were classified as "rare" on the basis of
1980 sightings. All, however, are represented by healthy
breeding populations elsewhere, and futurefield work is
expected to prove some of them more abundant in the study area
than currently classified.
74
-j
\ I
I I
Ten active raptor/raven nests were counted during the raptor
survey; of these, two Bald Eagle nests and at least four Golden
Eagle nests would be flooded by Devil Canyon-Watana
impoundments, as would about three currently inactive
raptor/raven nest sites.
Little time was spent in wetland areas during the summer season,
but cursory observations indicated a low population of
waterbirds .on tne lakes of the region. Trumpeter Swans,
however, nested on a number of the 1 akes between the Oshetna and
Tyone Rivers. At least twenty-one species of loons, grebes, and
waterfowl were identified during the fall aerial surveys.
Species composition was similar to that in interior Alaska, with
scaup sp. being the most abundant species (38% of observations)
and American Wigeon the second most abundant (lS%)~ The
relative importance in the region of the waterbodies of the
upper Sus i tna River basin for migrants appeared 1 ow; a 1 ake near
the mouth of the Maclaren River and the Stephan Lake area are
relatively most important.
Assessment of impacts of the Susitna Hydroelectric Project can
only be general at this stage of study and this stage of
planning for construction and operation. The major impacts
would be from habitat destruction due to f1ooding and from a
range of habitat alterations due to various factors of
construction and operation. Flooding would destroy a large
percentage of the riparian cliff habitat and forest habitats
upriver of the Devil Canyon dam. Raptors and ravens using the
cliffs could be expected to find alternative nesting sites in
the surrounding mountains, and the forest inhabitants are
relatively common breeders in forests in adjacent regions.
Lesser amounts of lowland meadow and of fluviatile shoreline and
alluvia (each important to a few species) would also be lost.
None of the waterbodies that appear to be important to waterfowl
would be flooded, nor would the important prey species of the
75
r
I
-
upland tundra areas be thus affected. Impacts of other types of
habitat alteration would depend on the type of alteration, e.g.,
which habitats are destroyed or altered or which replacement
habitats develop. Generally, animals that are habitat
generalists will be less affected than habitat specialists.
Mitigation of potential impacts on waterfowl, raptors, and their
habitats through avoidance is recommended, i.e., by keeping
construction and related activities at a distance from potential
raptor cliffs and from the Stephan-Murder Lake area.
3.12-Subtask 7.12: Plant Ecology Studies
The objectives of the Plant Ecology Studies during 1980 were (1) to
produce preliminary vegetation/habitat and wetlands maps, (2) to
provide vegetation descriptions of each type mapped, and (3} to survey
for proposed endangered and threatened species. The vegetation/habitat
types found in the upper Susitna River basin and the floodplain down to
Talkeetna were described, classified, and mapped. Reconnaissance of
many locations throughout the study area was made in summer 1980 to
obtain information on species composition and community structure.
Ocular estimates of the cover of each species in each layer of
vegetation were made, and these data were used to classify the
vegetation according to the system developed by Viereck and Dyrness (A
Preliminary Classification System for Vegetation of Alaska, U.S. Forest
Service, 1980). High altitude (U2) color infrared photographs and
LANDSAT imagery were used to map the vegetation cover types. Maps were
produced at the scales of 1:250,000 for the entire basin and 1:24,000
·for the direct impact areas. Additionally, the area extending 16 km
(10 miles) in any direction from the proposed impoundment areas is
being mapped at a scale of 1:63,360. A 1:24,000 scale map of apparent
wetlands was also produced, based on the 1:24,000 scale vegetation map
and the wetlands classification system used by the U.S. Fish and
Wildlife Service {Cowardin et ..!!._., Classification of Wetlands and Deep-
water Habitats of the United States, 1979}. Surveys on foot and by
helicopter were also made of several lakes and ponds within and
adjacent to the direct impact areas to determine the composition and
structure of plant communities occurring in or near the water.
76
. _ _:__] ~ __] ~-] ~-_]; _-]
TABLE 10
HECTARES OF DIFFERENT VEGETATION TYPES TO BE AFFECTED COMPARED WITH TOTAL HECTARES OF THOSE TYPES IN THE ENTIRE UPPER
SUSITNA RIVER BASIN. (Number in parentheses is the percent of the vegetation type as found in the entire upper basin.)
Impoundments Borrow Areas
Upper Sus i tna .
Devi 1 Can ,Yon Watana A c D F H River Basin
Woodland spruce 162 (0.09) 4766 (2,53) 228 (0.12) 77 ~ 0. 04 ~ 15 (0. 01 ) 227 ~0.12~ 188,391
Open spruce 862 ( 0. 73) 3854 (3.24) 48 (0.04) 7 0.01 125 0.11 118,873
Open birch 73 p .54) 318Af2.85) ly
968
Closed birch 470~ . 491-323
Open conifer-deciduous 300 (1.28) 1329 (5.68) 19 (0.08) 9 ( o. 04) 94 (0.40) 23,387
Closed conifer-deciduous 758bf4.75) 869 (5.44) 2 (0.01) 15,968
Open balsam poplar 7-
2PJ Closed balsam poplar 10PJ
Wet sedge-grass 12 (0.25) 100 ( 2. 07) 6 (0.12) {0.02) 4,839
Mat and cushion tundra 78 (0.12) 65 ,o01Y
Tall shrub 19(0.01) 580 ( 0. 45) 18 ( 0. 01 ) Z3 (0.02) 8 ~0. 01) 129,035
Birch shrub 58 (0.17) 474 ~1 .41) 18 (0.05) 92 (0. 27) 73 0.22) 33,549
~Ji 11 ow 16 (0. 15) 55 0.52) 7 ( 0. 07) 10,645
Low mixed shrub 6 {+) .785 (0.15) 101 (0.02) 113 {0.02) 109 (0.02) 55 ( 0. 01 ) 46 (0.01) 471,461
Lakes 1 (+) 47 (0.22) 3 ( 0. 01) 1 (+) 21,162
Rivers 835 (5.69) 21 06 ( 14 . 35 ) 10 (0. 07) 6 (0.04) 14,673
Rock "14 (0,01} 63 (0.06) (.+ l 113,712
Total ar~as 3603 (0.22) 15839 ( 0. 97) 500 (0.03) 322 {0.03)· 228 (0. Ol) 71 (+) 499 (0.03) 1 ,211 , 992
~ Hectares of closed birch are apparently greater in the impact areas than for the entire basin, because the basin was
mapped at a much smaller scale, and many of the closed birch stands did not appear at that scale.
Pi Balsam poplar stands were too small to be mapped at the scale of which the upper Susitna River basin was mapped.
Y Total hectares of mat and cushion tundra are much greater than this, but many hectares were mapped as a complex with
sedge-grass tundra.
-I '
' '· !
-
Results of reconnaissance surveys of the vegetation/habitat types show
that at least 243 species in 130 genera and 55 families are present in
the upper Susitna River basin. Of these, the presence of 21
represented extensions of the previously known ranges of the species.
Special effort was made to locate any species which are currently under
review by the U.S. Fish and Wildlife Service for possible status as
~endangered or threatened. Although some potential habitats of these
species were located, none of the species was found.
The preliminary 1:250,000 seale vegetation/habitat type map of the
entire upper Susitna basin (Figure 22) is provided in the back pocket
of this report. The major vegetation/habitat types found in the upper
basin study area are low mixed shrub, woodland and open black spruce,
sedge-grass tundra, mat and cushion tundra, and birch shrub. These
vegetation/habitat types are typical of those covering vast areas of
Alaska and northern Canada. Characteristically these types are found
on cold, wet soils and exhibit slow or stuntedgrowth. less than 3%
of the upper basin area is vegetated by deciduous or mixed
conifer-deciduous forests which, by contrast, have more robust growth
characteristics.
The approximate area of each vegetation/habitat type to be inundated by
the proposed impoundments and eliminated by proposed borrow areas,
relative to the area of each type in the entire upper Susitna basin,
are presented in Table 10 .. Deciduous and mixed conifer-deciduous
forests occur primarily along the Susitna River where soils are better
drained and the growing season is longer than elsewhere in the upper
basin. Consequently, a large portion of deciduous and mixed forests
found in the study area would be destroyed by the proposed
impoundments. Other vegetation/habitat types (mixed shrub, birch
shrub, tall shrub, and spruce) would also be lost by inundation, but in
small degree relative to their availability across the entire upper
Susitna River basin.
78
-
,....
!
-
l
If that vegetation/habitat which is destroyed is found to have
considerable importance as browse for moose, there may be some
opportunity to create replacement browse supplies in adjacent areas
either by burning or clearing to stimulate the regrowth of palatable
shrubs. Generally speaking, however, losses of vegetation can not be
mitigated. However, in those situations where the vegetation is only
temporarily destroyed (e.g., around construction sites, along roads,
and at borrow areas) revegetation by mulching and seeding with native
species may quickly restore ground cover .. Natural revegetation
following fertilization also appears promising in mitigating temporary
losses of vegetation.
3.13-Subtask 7.13: Geological Analysis
This subtask is being performed as part of the studies conducted under
Task 5 -Geotechnical Exploration. As such, TES has no formal
involvement. However, the University of Alaska performed some
geological analyses as background for the Cultural Resources
Investigation (Subtask 7.06) and discussions have been held with other
Project Geologists. Geological information of interest to Acres and
its other subcontractors is contained in the 1980 Semi-annual Report
and Annual Report for Subtask 7.06.
3.14 -Subtask 7.14: Access Road Environmental Analysis
The general objective of this subtask is to provide environmental input
into the screening of alternatives and the selection of an access route
to the dam site(s). The specific objectives are {1) to coordinate the
exchange of information between those studying the engineering and
those studying the environmental aspects of the route selection, and
(2) to compile environmental input regarding specific potenti~ impacts
of routing for each alternative proposed.
79
r
~
I, :
~
I
.n
, .....
The methods used consisted of initial screening of numerous alternative
routes by aerial reconnaissance early in 1980. This initial screening
resulted in narrowing the number of alternatives to three basic
corridors (Figure 17). Information (maps) about these corridors was
disseminated to environmental subcontractors and ADF&G so that
preliminary screening could be accomplished during the summer of 1980.
Input on potentially significant impact areas was solicited from these
groups in the fall and early winter of 1980. Information was also
solicited about the impacts on land use and the socioeconomic
consequences of the various alternative corridors. Inputs from all
disciplines were compiled by TES into a summary report submitted to
Acres and APA in March, 1981. At the same time, locations of specific
potential impacts were drawn on maps and supplied to R&M Consultants
for inclusion in their engineering and cost report on access.
A summary of the potential cultural resource and biological impacts
along the three. corridors follows. Access routing as it affects
socioeoC'nomic issues and regional and local land use is discussed in
this report under Subtasks 7.05 and 7.07, respectively.
Archeological sites have been discovered near all access corridors. In
addition, certain areas along the corridors (i.e., the margins of
1 akes, stream banks, confluences of drainages, and areas of high
topographic relief with commanding views of the surrounding terrain)
have higher probabilities for containing sites than do others. The
access corridor from the Denali Highway (Corridor 3) has the potential
for greater secondary impacts (deliberate or accidental disturbance of
archeological sites by visitors), because the surrounding terrain is
more open and accessible than other areas through which corridors
pass.
Impacts on vegetation due to the construction of an access road are
fairly straightforward: habitat removal and/or disturbance. Major
wetland areas have been and could be further avoided by slight
realignments and do not necessarily constitute major environmental
problem areas. No known locations of endangered or threatened plant
species would be intersected by any of the alternative access
corridors; searches for such species will continue during 1981.
80
....
Little is currently known about fish and fish habitat in the areas to be
affected by any of the access corridors. The two routes from the west
(Corridors 1 and 2) cross the Indian River and/or the Susitna River, and
the corridor on the north side of the Susitna from the Parks Highway
(Corridor 1) is also routed close to Portage Creek. In these cases,
there is potential for disturbance to the salmon fishery. In addition,
other stream crossings in the upper basin and construction of routes in
proximity to streams and lakes may adversely affect resident fish and
their habitats.
The primary :impact.on birds and small marrmals by any access corridor
would be through the actual removal or disturbance of habitats. Some
species of birds, particularly raptors, may be secondarily impacted by
disturbance due to human activity near their nesting habitat even if the
nest site itself is undisturbed. Cliff-nesting birds of prey in areas
such as near the confluence of Portage Creek and the Susitna Ri~er~ in
the Devil Canyon area (Corridor 1), and in cliffs along unnamed
drainages on the south side of the river (Corridor 2) may be disturbed.
Waterfowl may also be disturbed, particularly by the corridor that
passes close to the Stephan Lake-Fog Lakes area (Corridor 2).
As for furbearers, ·habitat removal may have less ·impact on them than the
indirect effects of increased access. There is some evidence that
certain species of furbearers are more sensitive to the presence of man
than others and therefore avoid areas near human activity. With
furbearers, there also may be indirect, but possibly significant,
impacts due to increased access by trappers after construction. Certain
locations, through or near which alternative corridors pass, have been
found to support high populations of furbearers. Examples of these
areas are the Portage Creek drainage (Corridor 1), the High Lake area
(Corridor 1), and the Stephan Lake-Fog Lakes area (Corridor 2).
81
' ' I
Big game impacts are perhaps the most difficult to ascertain because of
the mobility of these species and other biological factors. Site-
specific impacts may be of lesser magnitude than indirect impacts due
to increased human activity. including not only hunting but traffic and
other kinds of activity. The corridor south of the Susitna River
(Corridor 2) will intersect a brown bear summer migration route from
the Susitna to the Prairie Creek drainage. This same corridor
intersects good habitat for moose in the Stephan Lake area. Moose
habitat is also intersected north of the Susitna River in the Tsusena
Creek drainage {Corridor 1) and along Deadman Creek (Corridor 3).
Finally. important caribou habitat is intersected by all three
corridors: at higher elevations between Devil Creek and Deadman Creek
(Corridor 1). a wintering area south of Devil Canyon {Corridor 2). and.
subherd ca 1 vi ng areas in a 1 arge area south of the Dena 1 i Highway near
Butte lake (Corridor 3). Partial avoidance of this last area could
possibly be accomplished by rerouting the northern portion of this
corridor toward the west.
In summary. the potentially greatest impacts with respect to many
different environmental disciplines would appear to be in three areas
through which various portions of the alternative corridors pass:
(1) the Portage Creek drainage, (2) the Stephan Lake-Fog lakes area,
and {3) the northern end of the route from the Denali Highway. Each
alternative corridor would adversely affect one of these areas.
3.15-Subtask 7.15: Preparation of FERC License Application Exhibit
This subtask will consist of the compilation and condensation of
project reports from the various environmental disciplines into an
environmental report, which will be incorporated by Acres into the
feasibility report and FERC 1 icense application. No work on this
subtask was scheduled for 1980.
82
,,...,
•. I
, I
3.16-Task 12: Public Participation Program
TES personnel were involved in two specific public participation
activities that occurred during 1980. In addition, environmental
personnel cooperated with the APA public participation staff and Acres'
Task 12 Coordinator throughout the year.
In July, 1980, several TES staff members and several consultants
participated in an informational presentation of the Plan of Study to
the Susitna Hydroelectric Project Steering Committee. Representatives
of the FERC were also present at the meeting. The presentation
included outlining plans for the environmental and other studies to be
done to obtain the necessary information for the FERC license
application submission. In November, 1980, a TES consultant and APA
participated in a presentation in Soldotna to the Board of Directors of
the Cook Inlet Aquaculture Association. The Susitna Project fisheries
program was outlined and discussed, and questions concerning i:t were
· answered.
83
,....,
4 -REPORTS
The following reports have been prepared by TES and its subcontractors
concerning the environmental studies for the Susitna Hydroelectric
Project. For completeness and currency of reference, reports prepared
through May, 1981, and reports under preparation are included, as well
as reports by ADF&G.
4.1 -Reportsby TES and Subcontractors
4.1.1 -Reports Prepared
Subtask 7.01: Coordination of Environmental Studies
February, 1980. Susitna Hydroelectric Project Plan of Study: Task
7 Environmental Studies.
March, 1981. Susitna Hydroelectric Project Environmental Studies:
Plan for Agency Contact Coordination.
April, 1981. Susitna Hydroelectric Project: Task 7 Environmental
Studies Status Report.
May, 1981. Susitna Hydroelectric Project: Task 7 Environmental
Studies Summary Annual Report.
Subtask 7.03: Evaluation of Alternatives
August, 1980. Susitna Hydroelectric Project: Task 1 Termination
Report -Subtasks 1.03 and 1.05.
December, 1980. Susitna Hydroelectric Project Environmental
Studies: Preliminary Environmental Assessment of Tunnel
Alternatives.
January, 1981. Susitna Hydroelectric Project Environmental
Studies: Environmental Considerations of Alternative
Hydroelectric Development Schemes for the Upper Susitna Basin.
(Draft)
Subtask 7.05: Socioeconomic Analysis
June, 1980. Susitna Hydroelectric Project Environmental Studies
Procedures Manual Subtask 7.05: Socioeconomic Analysis.
84
r-
1
I
-
. I
-. I
rr""
August, 1980. Susitna Hydroelectric Project Environmental Studies
Semi-annual Report Subtask 7.05: Socioeconomic Analysis.
{Draft)
May, 1981. Susitna Hydroelectric Project Environmental Studies
Annual Report Subtask 7.05: Socioeconomic Analysis.
Subtask 7.06: Cultural Re~ources Investigation
July, 1980. Susitna Hydroelectric Project Environmental Studies
Procedures Manual Subtask 7.06: Cultural Resources
Investigation.
August, 1980. Sus itna Hydroelectric Project Environmental Studies
Semi-annual Report Subtask 7.06: Cultural Resources
Investigation. ·(Draft)
May, 1981. Susitna Hydroelectric
Annual Report Subtask 7.06:
Subtask 7.07: Land Use Analysis
Project Environmental Studies
Cultural Resources Investigation.
July, 1980. Susitna Hydroelectric Project Environmental Studies
Procedures Manual Subtask 7.07: Land Use Analysis.
August, 1980. Susitna Hydroelectric Project Environmental Studies
Semi-annual Report Subtask 7.07: Land Use Analysis. {Draft)
Subtask 7.08: Recreation Planning
July, 1980. Susitna Hydroelectric Project Environmental Studies
Procedures Manual Subtask 7.08: Recreation Planning.
October, 1980. Susitna Hydroelectric Project Recreation
Questionnaire.
Subtask 7.09: Susitna Transmission Corridor Assessment
February, 1981. Critique of the Corps of Engineers• Environmental
Assessment for Transmission Systems.
March, 1981. Susitna Hydroelectric Project Environmental Studies:
Preliminary Environmental Screening of Alternative
Transmission Corridors.
Subtask 7.10: Fish Ecology Studies
August, 1980. Susitna Hydroelectric Project Environmental Studies
Procedures Manual Subtask 7.10: Fish Ecology Impact
Assessment and Mitigation Planning.
85
-
--
Subtask 7.11: Wildlife Ecology Studies
July, 1980. Susitna Hydroelectric Project Environmental Studies
Procedures Manual Subtask 7.11: Wildlife Ecology· Big Game
Impact Assessment and Mitigation Planning.
July, 1980. Sus itna Hydroelectric Project Environmental Studies
Procedures Manual Subtask 7.11: Wildlife Ecology-
Furbearers.
July, 1980. Susitna Hydroelectric Project Environmental Studies
Procedures Manual Subtask 7.11: ·Wildlife Ecology· Birds and
Non-game Mammals.
August~ 1980. Susitna Hydroelectric Project Environmental Studies
Semi-annual Report Subtask 7.11: Furbearers Studies. (Draft)
April, 1981. Susitna Hydroelectric Project Environmental Studies
Annual Report Subtask 7.11: Birds and Non-game Marnnals.
May~ 1981. Susitna Hydroelectric Project Environmental Studies
Annual Report Sutbask 7.11 • Furbearers Studies.
Subtask 7.12~ Plant Ecology Studies
August, 1980. Susitna Hydroelectric Project Environmental Studies
Procedures Manual Subtask 7~12: Plant Ecology Studies.
August, 1980. Susitna Hydroelectric Project Environmental Studies
Semi-annual Report Subtask 7.12: Plant Ecology Studies.
(Draft)
May, 1981. Susitna Hydroelectric Project Environmental Studies
Annual Report Subtask 7.12: Plant Ecology Studies.
Subtask 7.14: Access Road Environmental Analysis
July, 1980. Susitna Hydroelectric Project Environmental Studies
Procedures Manual Subtask 7.14: Access Road Analysis.
February, 1981. Susitna Hydroelectric Project Environmental
Studies: Environmental Analysis of Access Road
Alternatives.
86
-
··~
··-:
:_: 'I
·.~
4.1.2 -Reports In Preparation
Subtask 7.07: Land Use Analysis
Susitna Hydroelectric Project Environmental Studies Annual Report
Subtask 7.07: Land Use Analysis.
Subtask 7.10: Fish Ecology Studies
Susitna Hydroelectric Project Environmental Studies Annual Report
Subtask 7.10: Fish Ecology Impact Assessment and Mitigation
Planning.
Susitna Hydroelectric Project Environmental "Studies Series of
Mini-reports Subtask 7.10: Fish Ecology Studies-
Chinook Salmon Do 11 y Varden
Coho Sa1mon Bur bot
Pink Salmon Eulachon
Chum Salmon Rainbow Trout
Sockeye Salmon Lake Trout
Arctic Grayling
Susitna Hydroelectric Project Environmental Studies Subtask 7.10:
Fish Ecology Studies Bibliography of Impact Assessment and
Mitigation Literature Applicable to the Susitna Hydroelectric
Project.
Subtask 7.11: Wildife Ecology Studies
Susitna Hydroelectric Project Environmental Studies Annual Report
Subtask 7.11: Big Game.
4.2 -Reports by Alaska Department of Fish and Game
4.2.1 -Reports Prepared
Wildlife Ecology Studies: Big Game
June, 1980. Susitna Hydroelectric Project Quarterly Reports:
Caribou, Bears, Wolf, Downstream Moose, Upstream Moose,
Wolverine.
87
( 1
··~
.:.l""l'
September, 1980. Susitna Hydroelectric Project Quarterly Reports:
Caribou, Bears, Wolf, Downstream Moose, Upstream Moose,
Wolverine, Dall Sheep.
October, 1980. Susitna Hydroelectric Project Environmental Studies
Procedures Manual Subtask 7.11: Wildlife/Big Game.
March, 1981. Susitna Hydroelectric Project Environmental Studies
Annual Progress Report Subtask 7.11: Big Game.
4.2.2 -Reports in Preparation
Fish Ecology Studies
Susitna Hydroelectric Project Environmental Studies Phase I
Procedures Manual Subtask 7.10: Fish Ecology Studies.
Susitna Hydroelectric Project Quarterly Report: Fish Ecology
Studies.
Wildlife Ecology Studies: Big Game
Susitna Hydroelectric Project Quarterly Reports: Big Game
Studies.
88
.....
I
5 -AUTHORITIES CONTACTED
The following authorities were contacted byTES and its subcontractors
between October 1, 1979 and December 31, 1980. Included are contacts with
federal, state, and local agencies and other institutions, organizations
and individuals. These contacts range from inquiries concerning pertinent
available data to presentations concerning the approach of the
environmental studies. This list is not intended to include those contacts
made with other members of the Environmental Studies Team, although some
project personnel are listed because of the capacity in which they were
contacted.
5.1 Federal Agencies
United Stat~s Department of Agriculture
Agricultural Stabilization and Conservation Service
• Lola Britton: File Manager
Economics and Statistics Service
-Paul Fuglestad: Agricultural Economist
Farmers Home Administration
-Delon Brown
Forest Service, Institute of Northern Forestry
-Joan Foote: Biologist
-Fred Larson: Research Forester
·Vic VanBallenberghe: Wildlife Biologist
-Leslie Viereck: Principal Plant Ecologist
Soil Conservation Service
-Weymeth Long: Director of State Office
-Sterling Powell: Physical Engineer, Water Resource Specialists
United States Department of Commerce
National Marine Fisheries Service
-Bradley Smith, Fishery Biologist
89
-
-
·-
··-[
United States Department of Defense
Army Corps of Engineers, Alaska District
-Loran Baxter: Civil Engineer
-Phillip Brna: Biologist
-James Caruth: Chief of Regulatory Functions
Army Corps of Engineers, Portland District
-Ruth Love: Sociologist
United states Department of Education
-Lee Hays
United States Department of Energy
Alaska Power Administration
-Robert Cross: Administrator
-Donald Shira
Federal Energy Regulatory Commission, Division of Licensed Projects
-Paul Carrier: Engineer
-Donald Clarke: Staff Counsel
-Ronald Corso: Director
-Quentin Edson: Chief, Environmental Analysis Branch
-Peter Foote
-Mark Robinson: Environmental Biologist
Dean Shumway: Chief, Conservation Section
-Gerald Wilson: Chief, Project Analysis
United States Department of Housing and Urban Development
-Debra Pevl ear
-E. Robinson
United States Department of the Interior
Bureau of Land Management
-Lee Barkow: Planner, Easement Identification Branch
-Stanley Bronczyk: Chief, Easement Identification Branch
-Gary Hennigh: Socioeconomic Specialist
-Paula Krebs: Remote Sensing Specialist
-Ray Leicht: Archeologist
-John Rego: Geologist
-Debbie Robertson: Land Management Officer, Division of Forest, Land
and Water Management
90
-
-
' .I"-
-
-Charles Smythe: Socioeconomics Specialist
-Page Spencer: Remote Sensing Specialist
-Steve Talbot: Ecologist
Bureau of Mines
-Michael Brown: Chemist
-Joanne Gidlund: Public Affairs
Fish and Wildlife Service
-Robert Bowker: Field Supervisor, Western Alaska Ecological Services
Unit
-Gregory Konkel: Habitat Evaluation Coordinator
-John Morrison: Supervisor, Biological Services Program
-Wayne Regelin: Research Biologist
-Me 1 Schamerger: Habitat Evaluation Procedures Group Leader,
Biological Services Program
-John Trapp: Marine Bird Management Project Leader
-Richard Wilmot: Fisheries Research Project Leader
Geological Survey
-Robert Lamke: Chief, Hydrology Section
Heritage Conservation and Recreation Service
-Charles McKinney: Consulting Archeologist
-Gail Russell: Interagency Services Divison
-Bradley Smith
-William Weler
-Larry Wright: Review Section Chief, Federal Projects
United States Department of Transportation
Federal Railroad Administration, The Alaska Railroad
-Fred Hoefler, Traffic Officer
United States Environmental Protection Agency
Environmental Evaluation Branch
-Judi Schwartz: Environmental Protection Specialist
Environmental Impact Statement Review Section
-Dan Sternborn: Team Leader
91
5.2 -State Agencies
Alaska Department of Commerce and Economic Development
Division of Energy and Power Development
-Heinz Noonan: Economist
-David Reume
Alaska Department of Community and Regional Affairs
-Sylvia Spearon: Assistant Planner
-Richard Spitler: Planner
-Mark Stephens: Planner
Alaska Department of Environmental Conservation
-Robert Martin: Regional Supervisor
-David Sturdevant: Management and Technical Assistant Ecologist
Alaska Department of Fish and Game
-Ronald Skoog: Commissioner
Division of Boards
-Robert Larson: Biologist, Division Director
Division of Commercial Fisheries
-Dennis Haanpaa: Assistant Regional Supervisor
-Alan Kingsbury: Regional Research Supervisor
Division of Forest, Land and Water Management
-Raymond Mann: Southcentral District Planning Officer
Divison of Enforcement
-Lt. Mi 11 s
Division of Game
-Paul Arneson: Biologist
-Gregory Bas: Game Biologist IV
-Sterling Efde: Regional Supervisor
-David Johnson: Game Biologist
-Herbert Melchior: Game Biologist III
-Lee Miller: Fish and Game Technician V
-Sterling Miller: Game Biologist III
-Suzanne Miller: Statistician, Biometrician III
-Kenneth Pitcher: Game Biologist
-Charles Schwartz: Biologist II
-Karl Schneider: Research Coordinator
-Jerome Sexton: Game Biologist II
92
-~
-
i_A""
-~
I
-!
r I i
' I
Division of Habitat Protection
-Dimitri Bader: Lands Coordinator, Habitat Biologist
-Richard Cannon: Habitat Biologist III
-John Clark: Assistant Chief
-Richard Logan: Chief
-Frances VanBallenberghe: Habitat Biologist III
Division of Sport Fisheries
-Christopher Estes: Fishery Biologist III, Susitna Aquatic Studies
-Larry Heckart: Fishery Biologist IV
-Michael Mills: Senior Fisheries Biometrician III
-Thomas Trent: Regional Supervisor, Susitna Aquatic Studies
Coordinator, Vice Chairman of Susitna Steering Committee
-Kyle Watson: Clerk -IV
Subsistence Division
-Ronald Stanek: Resource Specialist II
Alaska Department of Labor
-Rod Brown: Supervisor of Research, Administration Services,
Research and Analysis Section
-Chuck Caldwell: Chief of Research and Analysis Section
-Cal Daue1: Labor Economist
-Neil Fried: labor Economist
-Steve Harrison: labor Economist
-Chris Miller: Labor Economist
-Sally Sadler: labor Economist
Alaska Department of Natural Resources
Division of Forest Land and Water
-Mary lou Harle: Water Management Officer
Division of Lands
-Dean Brown: Southcentral District Lands Officer
-Michael Franger: Special Projects Officer
Division of Parks
-Chip Dennerlein: Director
-liza Holzapple: Park Planner, Division of Parks
-Jack Wiles: Chief
93
·~ I
: I
.·~
-
-
Divison of Pipeline Surveillance
-Elstun Lauesen: Socioeconomic Officer
Divison of Research and Development
-William Beatty: Planning Supervisor, Land Resources
-Randy Cowart: Planner
-Carol Larsen: Public Information Officer
-Robert Loeffler: Associate Planner
-Steve Reeve: Chi~f, Land and Resources Planning Section
-Ronald Swanson: Land Management Officer, Policy Research Land
Entitlement Unit
Division of Water Resources
-Richard Stern: Historian~ Research and Planntng
Alaska Department of Revenue
-Linda Lockridge: Records and Licensing Supervisor, Fish and Game
Licensing Division
Hazel Nowlin: Administrative Assistant, Administration Services
-William Yankee: Economist II
Alaska Department of Transportation
-Jay Bergstrand: Transportation Planner IV
-Reed Gibby: Transportation Planner
-William Humphrey: Transportation Planner I
-Richard Quiroz: District Environmental Coordinator
Alaska State Housing Authority
-William Foster: Administrative Officer
Glennallen State Trooper Post
-Robert Cockrell: 1st Sergeant
House Power Alternatives Study Committee
-Hugh Malone: Corrnnittee Co-Chairman, District 13
Office of the Governor
Division of Policy Development and Planning
-David Allison: Policy and Planning Sp~cialist
University of Alaska
-Lydia Selkreg: Professor of Resource Economics and Planning
Arctic Environmental Information and Data Center
-Chuck Evans: Research Associate, Wildlife Biologist
-Barbar.a Sokolov: Senior Research Analyst, Library Science
94
-
ll'""l' ' i
! !
t: i :1 I
Geophysical Institute
-Ken Dean: Remote Sensing Geologist
Institute of Social and Economic Research
-Scott Goldsmith: Assistant Professor of Economics
-Lee Gorsuch: Director
-Lee Huskey: Associate Professor of Economics
Museum
-David Murray: Herbarium Curator
Urban Observatory
-Richard Ender
5.3 -Local Agencies
Copper River School District
-Dr. Krinke: Superintendent
Fairbanks North Star Borough
-Philip Berrian: Planning Director
Community Information Center
-Karen Fox: Research Analyst
Matanuska-Susitna Borough
Borough Office
-Rodney Schulling: Planning Director
-Alan Tesche: In-house Authority
-Lee Wyatt: Acting Borough Manager, Planning Director
School District
-Mr. Hotchkiss: Business Manager
Municipality of Anchorage
-Charles Becker: Economic Development Director
-Shawn Hemme: Assistant Planner
-Michael Meehan: Director of Planning
-Barbara Withers: Regional Economist
Valdez Police Department
Magistrates
-Sheldon Spector: Magistrate, Glennallen
95
-
·.-:~
5.4 -Other Institutions, Organizations and Individuals
Institutions and Organizations
Ahtna, Inc.
-Lee Adler
-Douglas MacArthur: Specia] Projects Director
Alaska Hospital
Alaska Miners 1 Association
Battelle Pacific Northwest Laboratories
-Lester E. Ebechardt: Terrestrial Ecology Section
Community Council Center Federation of Community Schoo 1 s
-Mary Amouak
-Margaret Wolfe
Cook Inlet Aquaculture Association
-Floyd Hetmback: Director
-Thomas Mears: Biologist
-Thomas Walker: Economist
Cook Inlet Region, Incorporated
-Marge Sargerser: Land Manager
Copper River Housing Authority
-Thea Smelcher
Copper River Native Association
-Billy Peters
Copper Valley Electric Association
-Daniel Teggler
Copper Valley Views
Darbyshire and Associates
-Charles Darbyshire
Doyon Corporation
-Doug Williams: Land Planner
Fairbanks Borough Community Information Center
-Karen Fox: Research Analyst
Fairbanks Chamber of Commerce
-Robert Dempsey
96
-
-
.. ·~
-
-
....,
-
Fairbanks Town and Village Association for Development, Inc.
-Art Patterson
Fairbanks Visitor and Convention Bureau
-Karla Zervos: Executive Director
Guide License Review Board
High Lake Lodge
-John Wilson: Resident Manager
Knikatnu Incorporated
Land Field Services, Incorporated
-P. Sullivan
L.G.L. Alaska, Incorporated
Matanuska Electric Association, Incorporated
-Bud Goodyear: Public Informatinn Office~
-Ken Ritchey: Manager, Engineering Services
Matanuska Telephone Association
-Graham Rolstad: Chief Engineer
-Donald Taylor
Ninilchik Native Association, Incorporated
Northern Prairie Wildlife Research Center
-Al Sargeant
Northwest Alaskan Pipeline Company
-Susan Fisson: Director, Socioeconomic Analysis
-Virginia Manna
Over a 11 Economic Deve 1 opment Program, Incorporated
-Donald Lyon: Executive Director
Palmer Chamber of Commerce
Palmer Fire Hall
-Daniel Canteen
Palmer Valley Hospital
-Ann Demmings
Public Power Supply System, Richland, Washington
-Alice Lee: Coordinator
Puget Sound Power and Light Company
-Terry Galbraith: Public Relations Officer
Sagehen Creek Field Station, California
-Wayne Spencer; Biologist
-William Zielinski; Biologist
97
',..... . I
:I
-I
Salamatoff Native Association, Incorporated
Seldovia Native Associ at ion, Incorporated
Susitna Power Now
-E. Di schner
Tyonek Native Corporation
-nurse
Valdez Community Hospital
Valdez Vanguard
Yukon Wildlife Branch
-Ralph Archiba1d: Biologist
Individuals
Glenn Bacon: Consulting Archeologist
Warren Ballard: Game Biologist, Hunter
Dennis Brown: President Akland Air Service
Verna and Carrol Close: Owners of Talkeetna Roadhouse
Mike Fisher: Pilot, Talkeetna Resident
Jim and Vannie Grimes:· Pi lots, Owners of Adventures Unlimited Lodge
Pete Haggland: President of Alaska Central Air, Pilot
Paul Holland: Owner-Manager of Evergreen Lodge, Boater
Cliff Hudson: Owner/Pilot of Hudson's Air Taxi, Talkeetna Resident
John Ireland: Alaskan Sourdough, Murder Lake Resident
Dave Johnson: Manager, Denali State Park
Dorothy Jones: President of Talkeetna Historical Society,
Representative-elect of Mat-Su Borough Assembly
Frenchy Lamoureux: Hunter, Trapper, Wife and Mother of Big Game
Guides
Harold Larson: Agent for Alaska Railroad at Gold Creek, Trapper
Don Lee: Manager Stephan Lake Lodge, Pilot
Ron Long: Trapper
Mary Kay McDonald: Trapper
Chuck McMahon: Pilot, Hunter, Trapper, Fisherman in Upper Susitna
Basin
Cleo McMahon: Pilot, Hunter in Upper Susitna Basin
Tom Mercer: President of Denali Wilderness Treks, Bush Pilot, Dog
Mus her
James Moran: Pilot, Partner in Tsusena Lake Lodge
98
r
Don Newman: Trapper
Mrs. Ken Oldham: Co-owner of High Lake Lodge, Guide, Bush Pilot,
Author
Butch Potterville: Sportfish Biologist in Upper Susitna Basin
Carol Resnick: Tsusena Creek Resident
Andy Runyon: Pilot, Hunter, Trapper
Roberta Sheldon: Partner in Sheldon Air Service, Talkeetna Resident
Leroy Shank: Trapper
Judy Simco: Hunter, Trapper
Roger Smith: Trapper
Kathy Sullivan: Owner of Genet Expeditions
Minnie Swanda: W1dow of Master Guide, Talkeetna Resident
Jake Tansy: Native Hunter and Trapper
Bob Toby: Game Biologist, Hunter
Lee and Helen Tolefson: Subsistence Trappers/Hunters, Talkeetna
Residents
Mrs. Oscar Vogel: Hunter, Trapper, Stephan Lake Resident, Widow of
Master Guide
Jeff Weltzin: Devil Canyon Backpacker
Ed Wick: Talkeetna Resident
Glen Wingkte: Trapper
99