HomeMy WebLinkAboutChistochina Prelim SchedIDTask NameDurationStartFinish1Phase I - Reconnaissance Complete0 daysFri 12/12/08Fri 12/12/082Grant Award and NTP10 daysFri 12/19/08Mon 1/5/093Resource Assessment / FeasibilityAnalysis / Conceptual Design (35%)42 daysTue 1/6/09Wed 3/4/094Perform resource assessment /feasibility analysis / concept design21 daysTue 1/6/09Tue 2/3/095Agency Review of 35% plans21 daysWed 2/4/09Wed 3/4/096Phase III - Final Design72 daysThu 3/5/09Mon 6/15/097Final Design50 daysThu 3/5/09Wed 5/13/098Permitting21 daysThu 5/14/09Fri 6/12/099Approval to Construct Issued1 dayMon 6/15/09Mon 6/15/0910Phase IV - Construction131 daysMon 6/15/09Thu 10/15/0911Construction90 daysMon 6/15/09Mon 9/7/0912Startup-Commissioning10 daysMon 9/7/09Wed 9/16/0913Final Inspection & Acceptance0 daysThu 9/17/09Thu 9/17/0914Project Closeout Activities20 daysThu 9/17/09Thu 10/15/0912/122/46/159/17Dec '08Jan '09Feb '09Mar '09Apr '09May '09Jun '09Jul '09Aug '09Sep '09Oct '092009TaskMilestoneSummaryCheesh-Na Tribal Council Preliminary Schedule:Proposed Cordwood District Heating SystemChistochina, AlaskaPage 1Project: Cheesh-Na Tribal Council Cordwood HeatingDate: Wed 10/1/08