HomeMy WebLinkAboutAPA111ri
M ij
~
$
~
I
I
t
i
1
i
I
:I
. ~
·I
,j
·~ ~
~
.
I
·~· -., ..
'·--.
I
~
~
~
I
11
IJ.~
v
11
IJ
u •
u
Jj
u .
·r·· . .
~"' !
I
i
u .
I
HARZA .. EBASC~
Susitna Joint Venture
Document Number
. Bt!Jok (P) UNIT COSTS -BACKUP CALCULATIONS
TRANSMISSION COSTS
/I I
' ..
ll
n:.
-.L ' . ,·
g"
~
~
f'J . . J
l
•
~~
L.
a
~
I.
I
I -
I '
1 f
1 • r
1 t'~ .. •I
·~'.
--'· ~~~~--------~--------------------------~----------------------~
. _,;-......_.,. ~ "._c...-v. ....,.
Project ___ __.;s£:::::::::~-o~C~Y~~-Y7,-q.l..--a_0.;:;;::;:-....,';_?_--~-:_ . ·DEC 31 19tH
Subject ___ _.;~=......:::a· ~~z2~·c;.~zk.:::::Joo<:;---::-_.;,--------I\-Af-~ -------
~ll(~){f~~~~~~~~~~~~~~~~n~o~·~c~~=-~~~~~~~ho~No. ~~d~Mrn
~---,. (Compeny)
Discussion between ~~/~ __________ and ______________________ __
(of C"'mpeny)
Copies to (1) rJ., k->wl-~.n·c.e
(2) j}. /v~//£4
-.. ! l
(3) ~ ;':..:_ i\ .· ,._, ... : ~ t; l .
(4) ______ _
I
(1) . ,· \
' '
(2)
(3}
(4)
(of Acres)
"' Actic.m Required ______ _
' rT (5)
(6)
(7)
(8) File /
,
/·
r ~ .. ----------~---~J
-~ .
' '
...
-,~!,· .• • . {~ ~
ALASKA ?OWER AUiHORiiY
ANCHORAG~ ... FAIRBArn:s INTERTIE
PROJECT COST EST!MATE
(Thousands of Dollars)
Route Descriotion: Eastern-100~ Overhead with Broad Pass East
--~--------------------~----------------~------------------Confi our a ti on·: 1Bl9 138/345
Suoer Link No. Miles
1 21.6
3 41.4
F ?8 -. . ~
7 5.1
Q 14.9
12 22.4
13 19.9
15 1.4.9
16 0.9
Subtotal Intertie 169.6
iee1and .. Wil1ow 5.5
Total Line 175.1
ictal Substation Cost
Subtotal
R/W Acquisition (S4~,000/~i1e)
M~bilization-Demobi1tzation 5:
Surveying
Engineering 6~
Construction Management .5~
·subtotal
Contingencies 25:
Total September 1981 Dollars
Inflation @ 10:/Year - 2 Years
Total Cost
6,747 • r.: -:.:-./
c• ·• • •
14,055 "3:-f tJ'j~ • . 1 --
9.713 ;,tJ:;1 irJ7
-... I
14427 , .... ·.~ (' Cl~-
, • I ; 1
4 640 .... I I c!. oq
~. . ' _,
6,794 ·:. :' ":' ~;. .. ,.,.....,
·-" .... f .,
6,964 ,;;).·-. (• of.;!
.,l I ) . • . . ~I., ~q: 4,759 ..,.,. ·•· .D I
328 "'U t;.\J.~
"""" ! .
t
i
55,42i 7 ,· , 5 , t} I
., ~ . ~ t.
I
l
I
1,129
55.556
I
___ 9 .:...' 44;....;.,;;;..9 ___ _
66,005
I l
I
\
6,784
3,.300
3,100
3,300 Jt t.
,.. _ 1\f" q5···.)V l _a_s ___ ,4_4_9 ___ . [,,Y"'' 00 : .. 1
( .,.. .I ~2.....,1 ...... 6.....,.] 2....__ __ L ,. (I h / . I
~·,()~:· t \
__ _..1-.;,:08...:...~•-..:0..:.61"-~S?:~--'1 ~ ~ '{ l ~ 'f, (1 \'3\.' li
, 3 0 '7 54 ~ tD \ ' ' l
..; r
J
j
i
II .
'
J!~~
--~
(
ll \..
. ~
I]
l!
J1 Ll
~-:
J
,~ . ,i
OFFICE MEMORANDUM
TO: Dave MacDonald
FROM: J. Plurrmer
SUBJECT: Susitna Hydroe~lectric Project
Feastbi 1 i ty Report Estimate
Information Requirements
Date: January 12, 1982
File: P5700.07.09
In reply to ycur memo dated January 6, 1982, 1 have reviewed and marked
up the attached sheet. 1 have also attached a similar activity listing f''i for Watan~.
r1 'i
R. Plummer
JRP:dmb
Attachment
cc: F. Toth
R. Lang
r;
' J
J/
1!-· ·_
I I :!
11 '
l
r".·_ ' j
I''
I,.
J
'
J '
l'
{\.
TO:
FROM:
SUBJECT:
OFFICE MEMORANDUM
J. Plununer Date:
File:
D. H. MacDonald cc:
Susitna Hydroelectric Project
Feasibility Report Estimate
Information Requirements
January 6, 1.982
AN-AB4
Attached is a very prel~nary 1isti~g of activities
associated with the estimating and pl-anning of Devil
Canyon dam site. I have made a fast indication on
that listing as to where I understand the assigned
pricing.is to be carried out.
Example -tunnels and plugs -the escalation pr~c~ng ~nd
quantities will be done in
Buffalo
-lining and plugs -will be quantified and priced
in Niagara Falls.
This list is being provided for discussion, so that we can
break down the assignment packaging in the very near future.
I would like to take certain quantifying and pricing packages
and assign them to people in this office -andt-with your
agreement, have you do the same with those ite:ns associated
with the total Devil Canyon estimate.
DHMacD:pm
Attachment D. H. MacDonald
Head, Planning & Estimating
Dept.
11.
(
11 '··
,y.
17.. -j
!: .
r·
I, I
)
{ .
I
. , ,r" r ,_
SUSITNA ACTIVITY LIST
Watana
1 -Diversion
-Tunne1s and Plug
-Portals
~Gates
-Cofferdams
-Dewatering
2 -Chute Spillway
-Exc. 0/B and Rock
-Headworks
-Gates
-Chute
-Ancho·rs
-Flip Bucket
3 -Emergency Spillway
-Exc.
-Slab
-Anchors
-Fuse Plug
-Bridge.
4 -Service Spillway Tunnel
..... -
-Exc.
-Headworks
-Gate
-Out·iet: Civil
Mechanical
5-Mlin Dam -
-Exc. 0/B & Rock
-Fill
--Grouting
-Valves Spillway
-Access Shaft
. -_c.;.· .. ,·., T,
/,~ .:~
"
Assigned T,..Q_
B
N
B
B
B
B
N
B
N
N
N
B
N
N
B
N
B
N
B
N
B
B
B
B
e
B
;,
l'"
I· ' 4
SUSITNA ACTIVITY LIST - 2
~~ ! Watana -Continued Assigned To r ..
. ~
_,.-. 6 -Relict Channel (
r \._ -Exc. B
-Fill B
l'f 7 -Construction Facilities
y,
-Roads B r -Yards B
-Bridges B
[ -Batch Plant N
-Agg. Plant N
-Gran. Fi11 Plant B r ., Power Facilities
r 8 -!ntake
'
-Exc. 0/B & Rock B
-Concrete N r -Anchors N
-Gates B
11
--Bulkhead B
·-~
9 -Powerhouse
i -Access exc. -Portal and Tunnel B
-T/R Exc. -Portal and Tunnel B
I\, -Access Tunnel Lining N ,,
-T/R Tunnel -Lining N
r
-Penstocks -Exc. B
·-Cone. Lining N
-Steel Lining B (S ) N (I)
10 -Transformer Gallery
-EXCo Rock B ,.
-Concrete N
-Equipment B
11 -Vault . -Exc. Rock B
-Concrete -
.,..-1st Stage N
:.'
i) ' 2nd Stage N ' It '" I , .. -Crane Support N ·_;
-Crane B
-Roof B ; ..
= I;
·~-~
!
fl
I)
I'
I_
I' ;
f
I
I~.
1-
,.
I
I
I,
\ I)
.,,:.J-
I~
/
f ·~--
I
,.--'
'•
SUSITNA ACTIVITY LIST - 3
Watana -Continued
11 -Vault-Continued
-Turb. EP
RP
-Gen.
12 -Surge Chamber
-Exc. Rock
-Concrete
-Gates
-Crane
B = Pricing in Buffalo
N = Pricing by Niagara Falls
Assi9ned To
B
B
B
B
N
B
B
i~~ .
-
I
I
~~
I
I
I
I •
I
I
~ !,i'J
'-'-'
~ ' IJ .. ;
J
]
4\ !-,jY,u
,.,
.,
J
,,A
•
Estimate Work Sheet
PROJECT """'St..\~ \\94." --WA\A.NA
CONTRACT -:r-rr:o,\'>S,.,\ss\a"-PI~V\\
DESCRIPTION Ai'JD BASIS OF ESTIMATE QUANTITY
.,. .. ,.,
'-5COO l.-&~~11\.t/\ 0\t-\,.~ ~11\.d Rl~l.cts
-T 't-ZI\1'-.S ""''t.s s, a~ I 1-::f. ~
-<=5v.los·""'-t\c::~h$ (h--sites-)
UNIT 'UNIT
COST
'rlti\~.s-
L<5
LABOR
AMOUNT
ooo.s
ITEM REFERENCE No. JOB No. P ...,-..oo • ~ ~
DESCRIPT,ON SHEET .IJ OF
OPERATION No. REF. BY R. -:o . C:...~,.,toev\<"-'..._
.., 8' Ralaru ~ "1 q 8'" :2:...
DESCRIPTION CKD DATE
JOB MATERIALS I PERM.MATERIALS·I SUBCOi\ITRACTS EOPT.OWNERSHIP I EQPT.OPERATION
g&nl AMO.UNT I~&HI A¥~· !NT 1 g~n~ AMOUNT ~~HI AMOUNT lg&HI AMOUNT 5%r~ITOT.AL AMOUNT
OQO!s oo-os • 0 00 :s-I IG? Ol:fO's ,~oc::o-$
lt0<700
':f<'oOO
"J I t• ~ ::i;~-r-J;::l ~s-o
·1 "00
I -I --1--+----····1--t----~+-----1-·-~ ~ .. <6 b"5CI! I I ~ 'I ·cg; bS9 ~"«<~--,--..---~-.... ,--.... ~1-~--.... J.-.-. ·-I
_ '"5=5-:5 .:Su~-\'\oh./s:'wr\t:.W~ est~-ho'-~~,·~ .
I -1 G\G\.-:5
t.-st"e-r
Wt \\ow
"'"'\~ A~
UV\\VersiT7
1
1
1
1
L-5 I IA.Ci"3:Z
LS 1 8" ;l. q
LS 151:;z...
l-._'5 )+..)f._ cr; b
~ev\\ Ca!t\yoh. _J_ _1---+---1---+----LSI I 181:Z.1i-
1 ::z. sg 1
z 0 -=(-'":f-5
1 ;;t._ c:t bO
10T-00
I I -
-c1 goo
I I
1 :Z.T-1::50 ·-
<6~ q~s
~ "5\'b.."\\o"' L I q ~ ~0 -:5'52. "'5'-'b<rla.i\,."' "'""-"Swo "':l I 1 . I ~~" ._j_!-::--.11..., ~--·-. ,.....,._,_., I . -::s\N&d-.y""-td. • I -• • .....
..
'"3~0
:Z06 I I
1-=1-o
COOb
;<'Ok,. --
1~1p
-~~~I ... ~~..,.,._. -
l.;
"'.;:-;. ,.,. C· \:'I
1-f-0-:5 -;z. Jr., H. H. 0
A.CS1 I I 1s, ~4.&
:zo~ 1~, s<q:o
61?; 3 -:r, P... -z. -o
4.~ 1~-o .. rs -1-J
"1~4 1 0 )r_,-=f-11 ·----
7.-.t:ft,.. 111 re;so
<
"'
~
0 u.
1 ~~ ,..:
011
I
'-l
I
I
I
I -
I
r---------~----------------------------------------------------------------------------------------------------------------·-------------, I A~IIII Estimate Work Sheet
PROJECT -.:5 L\S \IN A. -WA. 'T"A.'N."
CONTRACT \~V\.S'IMIS:t\o"-?\GI4'"
DESCRIPTION AND BASIS OF ESTIMATE -I QUANTITY
·.H· I
"C.S-:5 W~ \\:;>W ~~ \--\VInW~"t '"'Sys (E..\"\SJ
-:-" i:=:~l-m~~ 01."'-~ CC:y.rt""~ Cos-h-
-N,~wr:we, Coln .... u~l~~s EV'''f'~t
-"E_H,S C-o~Qo\ Ce..-..-+e::-t3l~ ~ ~ip.
.,
1
1
LABOR
UNIT 'H&rf-1 AMOUNT
---'t)OC>~
I l-."5 I I '2.-=r--ZJG. I
I LSI I 1..~'7Jr I
ILS I I .14-00
I
ITEM REFEREI\CE No.
DESCRIPTION
OPERATION No. REF.
DESCRIPTION
JOB No. Pc::::io~-ro. '0~
SHEET :z_, OF
BY R,-:.t). CL-~,...,..\o~.._
1 X' reJ..,ru~ 1 C\1?2.
CI<D DATE
JOB MATERIALS I PERM.MATERIALS·I SUBCONTRACTS I EOPT.OWNERSHIP I EOPT.OPERATION
g&HI Ai,10UNT IH&HI A~··vuNT H&rf AMOUNT g&rf AMOUNT H&rf-1 AMOUNT
ooo.·':r ooo:S OQo.J-~oco--::s=
I I I '8'110
I
-soy; --:.5> -=t-b
I I I -:<..1~0 ~Ob z~o
Equivi-~-.AL AMOUNT UNIT' ., It~· "C)-QC) s
" 1 c;:;-;so
tt-c:r::z..o
/
/
;:7...110 1C03 1 q:z_ I I -;s 'ii" ,;o I r
jflrJil' IIU'. "" -w.,.,_~,_, .... "'4\ ::::t::lev\\ Cii!CA,.o\.o. (. '"'-?'"~ •·v D. . W\'0\'\1.-n:.Y\ a.~d.. C::Olo\.~\ ~~~ ..... e--r).
1 ILSI . 1S<9 1 <=1'5
-110 -99
~
l)Yl
i1 .. tjJ
:1! u
c-·{
li!~
L.:l
~
'"'5.:::54-...:::sr~c:..\ To~ 0111\.4 '\=\~res
-"'\ t:.\6\"'S (vJ~N\)
-I
A.kt;::r-I&;~ l:1t.l'14 ~4 f-1."6 I I 1-:,o.zg~ -=fk-0 q 51 I
-::::ar:.::.
• c-a-IC:"'-'"""C" -... ~ . . !~
-,
~ot;;bl '"5 0--:51 ~s1:sj G 1 ~ ~ .:d~-!>1
;t....? 1b'CJ
.I
~ .... ...._._._.
i . I I
1;t:.cq 6\C\-;;Z...
t------------------·-------·--l-----l--·l--1----·--1·---·-t---·--··-~·-1 ··· t·· ·-··•·· · ··~·-··-!----·----1---1-··--··-t-----1--.. ---·-1-·-··I· ·-···· f.
~'5b Ove-,-1,..~ Cov.duc::*"oY.S a~cJ.. ~ev\<:es
- 1 q C\ ·;:, '.NGrtc:tl'lc:t.
c~~d"&or.s(;z,., q:::>;,._ kc.,..,'t \f f"h.a.5:e.) ~b lv;\i\es IG;(S;U.I -~4.-=f~~ '3ST19 1 q '6Sg" ,,.~,~..:;:.I :ssq 11~ . .'8''l -=1-1-=f-
/
C01"f'$ =5'5 b G\'0 V
/
-C:::S 1..\lo ....._a. v\"'~ Co..lo \e.s I I (, IL"St:"1iT-ob~~ I 14 ~~'l~s,oa:>l I ·~~--;<so~t=
s1 ~T-k-tr-r;s:g II "1 oq 1 "''5/1-qqjf.f.r..1
4-sT--::rt"~r ,4_-"3-=?7,5CJ • /
-t · I ~ I· I -1------1
3"54' R..""::>.:uls-G{'M ~ ~; \s
-Roctil::-~"'d l'~·h ~00 Wli\e.:-1t:.ss$ :t-~T1 j:r<l;(cl 1Sg'")f.. 1
'
I ..
.
-Cl~r\~ o"'cl. Roet.dt' ~ 1--1-----· -~-___ _ ~ ________ .. ________ .
lro;zol 1H..O~ 1~s1 ~r=r-4-1 ~6~ -==f-'7..,o'O
t;s$19 't 1 '1,3 ~~s:zt 1h cg' 0 '\jlrooc b1;ZO
1-------1---1·---·--i--+---__ .__ __ l -~~9-, ..:.1 .... ,.,,. ..
1
;Z 101 r·· l-"5k-.6 " ..
If.. ?-::f:t-7... q-s 0 -··1--·---.. --1-..... -1-... -t-------..--~--·-!-,_:.:.~u. ~_?q-=fl-L-:5 ';Z~ 11 j1:53'.Z-O ---------------------
/D
<t
"'
~
0 ...
"' I~ ,.:
on
--~--·'t"'<~~-.... ~·-------,__,. ______ .-----·----·-·---·· ·-~~~-·----~,.-::~-~--"'~-· .. -...._.,~--~~-~~-------~ .. ---.--..,..r"---...... ---;-........;r--(· · · ,,:-;.;,:~-<j,:.;;;?~'.-.?:f~-~4;:t*;:.':1':..~~~~~:'f;f~1i1:,!~{~"·:~:~~-~;-~~;:·~;p.:;\;,c.';~iZ·~.:c:r;::;~~-:~ .;. ~."··.,, ~.\t1">~':'.·· ~~:-~~~~----;r~·
C:,l
I
.L
I
I
I
I •
II
I
~~:
l ;. !.,... . (
n/ u
r;v L_~
··~ ;1
LJ
...,
J
-I A~~~~~ Estimate Work Sheet ITEM REFERENCE No.
DESCRIPTION
PROJECT ~UC:S.l-r-NA -~E\/lL CA-NYOt--\ OPERATION No.
CONTRACT -\'";-o.,..o!w-• :t \ -::,.,_ ~1..,..,..-t' DESCRIPTION
LABOR JOB MATERIALS PERM.MATERIALS
DESCRIPTION AND BASIS OF ESTIMATE QUANTITY UNIT
UNIT AMOUNT UNIT M10UNT H&n' AMOUNT .. COST COST
~~~-~ .... to~\o~ alf\a. C:::Swih:b-.i~ ~.::~-..... ooo·:o oc·o'~ oo~
C::S w~.r .... nt " l-C:S =t;z_1 "5qoo
-:sc::s-:s. ""5u,bs-\c:...-h~fsw"~tel...lll~ ~ EiP~-r·
~~ (2._ooo -+-) ~ l-"5 :=.tt--g ;1..4._Z5S
W\\to\oJ 1 J-.<5 ~J..t-0 GOOO
Ktl\\k ~ 1 '-~ 1h..O Cl&'O
u~h,M"rr,. " L'S 10ic,'? f-?b"5 . -
;z:s!i b ~-=f-;000 __ __..,_.~ Jr ,.....-
~...,.._---............ ----.... -·----....-~ r-·~ -· -----· .. ~=""'..-..~
-"35#-;2.000 +-(-:s;;;,eJ..il i CD"'ro")
~
-tovJe.-d' 54-fo ~c.h. ~'?~ C{. C1-;:;:-'$' ~0$0 1C::,S'33
( :r::::,..,c:-fu.cl~s ~~,,....,JA'fl-;,"': .;... h<~t•·elw.--.e.)
-:sc::::::,6 Ove,y~G\ Coll'lduc.+o~ ~ "::::DeM~
-Colt'\cluc:t"o~ (2..,.,_ <::{?k ~c:.• .... t\ / p'-'o.=~ 1~ W~lles ~lf-~1 6-=fqk--~1"15 1-r-k-Z.C(
'
-~v.'o~a>\~Q.. C..a.to\~s C;:::.) --:::::, L~ ;t: ~~·~ 0 '6"3~ ;.,. ~u.~ ~1'Zso:::>
1'51"5~ r--
16q;tt{
3S-3 W J..LLo J1/ JEAI~"'c..y
/1 C. PIT .5 "j ..t J51fv 770
'A; OF-/ttl JJt-;J-r.// C't.J/1'..!
----~---~----... ...,_.,_..~ .__,.......,_..,___.._..,.._...,. __ ~_,_.___.__ ~ri'~~ ~.&>~(~~i;~~-~ ~-~~ ·-·~~~-~·--._....... __ . --.-----"-~-~----~---~ ' ''. 'f ·-,~-·--. '• ~ ,•:;~ ... ~~~7--·~f"'' =~~l~411
JOB No. p ~-:f-O'<:l • 0"\
SHEET~ OF
REF. BY R, "':S:), ~~ evk.~
1 ~ T'""elof'~Jt ..... '7 1 G'\ 'i? ~
CKD DATE
SUBCONTRACTS EOPT.OWNERSHIP EOPT.OPERATION
gNIT OST AMOUNT gNIT OST AMOUNT ~NIT OST AMOUNT Em•jv
U~J!T TOTAL AMOUNT
c:;;:i:::£> 'J' O:O's ~o·.r oo-o 's-
1""3Jr-1'::f? f, q:;,o ../
-::::,.q .4-'6 :z. g-q '0
;
cl
qs 1 1 t:;S -::r-0 ?0
1b 1~
.)
~ ~ C:St5
1-:zo i),... --::r tgq'Oo J
-:z..-=r-o ·-2~6:71__ 1'1'4C{S
~ • >001 ....-:! co-..___,. • ........._ ........ ~ ....... -.... -~ooo.,:oo.t..• -·~ .. .; ... .-... -· ---
-~o~ 11 :z::.s 1"St3 1-s:t-7--, f-5~1;1.1: .zq ,005 /
-sz~~ 4-g'"O 5'i501 -=Mq "OOf~ ~ 1 A.H-'2-.'L v
1$ J._?o H..b'11 r;.~-' tS b:Z.T. Z.~6~ rr-~ 1 7; -=1-5 v
·-
qh-q 1 ;zrg1 31{-7-.a.T-/
-
.110 '19 I ;:A /..3
I
J
I
I
'
I
' tl
I -. ~
I
(~
I ~J
~···
\.
~
~
I j
~
~
I :
.Ji
I
J
l' ' J ..
If
\--.!)
J;. LJ
r ~
"
q d.
' -~
I! ,, .......
~~ \ .. J
r •'!
~~
r ;A. _,. r
l l ~'· .l\
.I ;.,;e
I
l,l,
TRANSMISSION LINE COSTS January 12, 1982
P5700.07.09
Basically transmission line costs breakdown into the
following elements
-right of way
-clearing
-structur<es
-fotindations
-hardware.·
c·onductors
-engineering and construction managemen·t
-owners cost.
In our estimate we included all the elements except the last
two which will be looked after by the project.
Background -Transmission Estimates
During Acres trip to Alaska in 1980, we met with our sub-
contractor R. W. Retherford Associates and discussed various
facets of transmission line design and construction in
Alaska. Rw~ had developed a special type of tower, X-type
which was sui table for installa.tion in permafrost. This
x-tower design was hinged at the foundations and guyed for ...
stability. Further developments saw a move from alumin~u
lattice design to tubular steel tower members. This lowered
the cost of the labor component.
RWPA provided Acres with the details of their estimates for
a 230 kV, tubular steel tower line between Point Mackenzie
and Fairbanks. This was based on 230 kV line (aluminum
lattice) constructed in 1975 and 115 kV line (tubular steel)
constructed in 1978. The RWRA estimate was. in 1978 dollars.
Acres ve=y first estimates were based on a tubular steel,
X-type tower. This has been justified by the decision of
Commonwealth Associates recommending this type of tower and
the eventual acceptance by APA.
The Acres first estimates used the RWRA data and were
developed for various voltage levels for the electric system
studies. Telephone consultation with CAI confirmed Acres
line costs. The present cost:s which are in the attached
back-up material are based on CAI "Route Selection Report"
dated October 1981. The estimate is in September, 1981
dollars.
11 .
11 J
I·~
·'
I!
I!
'I I, '
I ;
.[~(
'
2
The following table sectionalizes the transmission lines
with number of circuits and cost per mile. A total is
generated for each section. The total cost is then divided
by the estimated total length. This will give an average
cost per mile. This cost will be used to stage the
estimates, .e.g. Watana ·1993 and Devil Canyon 2002.. The
di£ferences. in costs per mile are accounted for by the
terrain, difficulty of access, type of fo.unda.tions required,
etc.. Some areas will require winter construction or heli-
copter assistance.
section
Watana-
Devil Canyon
Devil Canyon
Gold Creek
Gold Creek -
Willow
Wil10'\v -
Xnik Ar.rn
Knik Arm -
University
(one tower)
Gold Creek -
Healy
Healy -
Ester
Total
No. of
Circuits
2
5
3
3
2
2
2
Length
!vliles
52
65
213
120
36
200
164
850
Cost
per Mile
($)
340,000
340,000
331,394
285,000
251,111
318,990
310,000
Total
($)
17,680,000
22,100,000
70,587,000
34,200,000
63,798,000
50,840,000
268,245,000
September, 1981 average cost of transmission per mile
including intertie-268,245,000-$315,582.
850
The FERC format requires splitting the estimate into steel
towers and fixtures and overhead conductors and devices.
ll
11 \
11
~
ll
11
If
1·:
, I
I '.
I
I 1
I l
,j
I 1
l
·'
l l
j
··~J
·.;;.-
For 1993 construction we require 600 mi of transmission.
The avera~e cost per mile developed above does not include
costs for mobilization/demobilization or surveying. We
also have to bring the costs up to January 1982 figures.
For 1993 constr.uction
600 mi x $315,582
mobilization/
demobilization 5%
surveying
January 1982 costs x 1.04
deduct clearing
$189,349,200
9,467,460
3,500,000
$202,316,660
210,409,326
10,409,326
$200,349,326
cost per mi -200,349,326 = $333,916
600
The tower costs according ~o FERC should include towers,
foundations, hardware and insulators. Tower costs account
for approximately 70 percent of line costs which are in
turn split into approximately 57 percent for material and
43 percent for labor.
We are a~surning that towers will be spaced at 1,200 ft and
will require 4.4 tow~rs per mile. The total towers for
600 mi would be 600 x 4.4 -2,640.
The tower costs will be
333,916 x 0.7 = $233,741/mi
233,741 -
4.4 $53,122.96/tower
Material cost per tower -$53,123 x 0.57 -
Labor cost per tower -$53,123 x 0.43 ~
$30,280
$22,843
3
I
)
1\.
11
J
I
II
_j
I'
·'
J
The conduc~or 90sts will be
333,916 -233,741 = $100,175/mi
Conductor 954 kcmil
Weight-pounds per foot
Cost per pound
1 .. 075
$0:97
Shield wire 3/8 in.
Weight-pounds per foot
Cost per pound
Materia.l cost
5,280 X 1.075 X 0.97 X 6 -
5,280 X 0.273 X 0.93 X 2 -
Labor costs per mile will be
100,175 -35,715 = $64,460
0.273
0 .. 97
$33,034
2,681
$35,751/mi
0
The abo·ve figures were used in the FERC format.
Substation/Switchyard Estimates
.
Substations/switchyards costs based on the number of· elements
contained and the space required to accommodate voltage
. levels. The costs for this estima·te were based on the
following
-station base costs
-circuit breaker positions
-transformer positions8 .
The costs were contained in the pi.·eliminary electric system
report. These costs were upgraded to January 1982 figures
and an additional factor to equalize them with the higher
line costs.
J
I'· ~
I
f
I ,!
I I
I .i
li
J
,D ,,
Substations 1993·
Willow
Base Cost
Circuit Breakers 9 >~ 345 kV @ $1,155,000
3 X 138 kV @ $ 462,000
Transformers 2 x 75 1-1VA @ $ 577,500
Total
Knik Arm
Base Cost
Circuit Breakers 8 x 345 kV @ $1,155,000
1 X 138 kV @ $ 462,000
Transformers 1 x 75 MVA @ $ 578,000
Total
University
Base Cost
Circuit Breakers 9
6
Transformers 4
Static Var Source
Total
Devil Canyon
Base Cost
X 345 kV @
X 230 kV @
X 250 MVA @
400 MVAR
$1.,155,000
$ 810,000
$1,500,000
Circuit Breakers 11 x 345 kV @ $1,155,000
Total
$ 2 , 310, o.o 0
-10,395.,000
1,386,000
l,J..SS,OOO.
$15,246,000
$ 2,310,000
9,240,000
462,000
578,000
$12,590,000
$ 2,310,000
10,395,000
4,860,000
6,000,000
13,855,000
$37,420,000
$ 2,:310,000
12,705,000
$15,015,000
5
(!
l
I:
I
I
l
I
I,,
t~:'
l 1,~
:/o,
I
I
'
I ' I
li
I'
I
I
I
I
Ester
Base Cost
Circuit Breakers 10 x 345
4 .. 5· X 138
Transformers 3 x 150
Static Var source 100
Shunt Reactors · 2 x 75
Total
Total Substat~ons 1993
Material
Labor
Substations 2002--
Ester
Circuit Breakers 1 X
1.5 X
Transformers 1 X
Total
w: .. 11ow
Circuit Breakers 5 X
1 .. 5 X
Transformers 1 X
Total
Knik A-rm
345
138
150
345
138
75
kV @ $1,155,000
kV @ $ 462,000
MVA @ $1,040,000
MVAR
MVAR (345 kV)
kV @ $1,155,000
kV @ $ 462,000
MVA @ $1,040,000
kV @ $1,155,000
kV @ $ 462,000
MVA
Circuit Breaker 1 x 345 kV @ $1,155,000
Total
$ 2,310,000
11,550,000
2,080,000
3,120,000
3,460,000
1,920,000
$24,440,000
$104,711,000
88,985,000
15,726,000
$ 1,155,000
695,000
1,040,000
$ 2,890,000
$ 5,775,000
695,000
580,000
$ 7,050,000
$ 1,155,000
$ 1,155,000
'·
ll
11 ~ ..
f.,~
; .
\..
I
r·
I
I
I
I
I
I
I
I
I
I
u
·~
' .... ~.'"""·~ ;,:_. ··.·
University
Circuit Breakers 3 X 345 kV
3 X 230 kV
Transformers 2 X 250 !-!VA
Total
Total Substations 2000+
Material
Labor
Substations at Powerhouses
Watana
Base Cost
@ $1,155,00
@ $ 810,000
@ $1,500,000
Circuit Breakers 8 x 345 kV @ $1,155,000
Total
Material
Labor
Devil Canvon
To be built in year 200L for 4 units
Circuit Breakers 6 x 345 kV @ $1,155,000
Total
Material
Labor
$ 3,465,000
2,435,000
3,.000,000 .
$ 8,900,.000
$19,995,000
17,000,000
2,995_..000
$ 2,310,000
9,240,000
$11,550,000
$
$
9,820,000
1,730,000
6,930,000
6,930,000
5,900,000
1,030,000
7
i,\'
,w·;;:-~
I
I'·· .
. ..
\
'
I
.
I
I
-· I
I
I
I
1.
I
I
u
u
u
Q r.·
/ ,.
\
~·}-
Land Rights (ROW)
Transmission
166 mi @ $40,000
13 mi @ $70,000
Substations
Willow
Knik Arm
University
Ester
.~J ...... ,.-~7·
·~I ~ -' ~, •
p
$. 200,000
200,000
500,000
200,000
$ 6,640,000
910,000
$ 7,550,000
$1,100,000 $1,100,000
Total $8,650,000
ENS:jlh
•• I·
FROM:
.SUBJECT:
I
I
OFFICE MEMORANDUM
J. R. Plummer
D. Meilhede ~
E. N. Shadeed
SUSITNA ~ROELECTRIC PROJECT
TRANSMISSION SYSTEM
Date:
File:
cc:
COST ll.STIMATES -JANUARY, 1982
January 25, 1982
P5700.07.08
J. o. Lawrence/Circulation
R. T. Sarofim
A. Jex/D. Kaushal
r am attaching copies of sheets 3 and 4 of the preliminary
cost estimates which were revised. The revision wa~ r~lated
to transmission line length which should be coordinated with
the system diagram forwarded recently.
The total Susitna length is 850 mi which is constructed at
various times as· follows.
Year
.1984
1993
2002
Mi~e·s
170 (Intertie)
~s·o ----124
Total 850
The length of transmission was revised to coordinate with
the above. This will change the cost estimates as shown on
r·evised sheets.
ENS:j1h
Attachment
:C:'
~
~c.:~ -'~"""·~ ,...-. ·-,s j,,~.:.
1.\;: ·-~· ~ ;:;· ~'\ ,, i . .
~'~
'::. ~-:." '.... ...-~-, " ,. ";--:.. -"'-···""':":;;
·'"'"= ~,..-~--'". -~---;-"-' __ •::;..-:;:". -_:_...;;: -~-~
~ ~.,.,. .... ;:..:;::u
SUSITNA HYDROELECTRIC PROJECT
PRELIMINARY ESTUtATE -ACRES AMERICAN
HATANA -DAM CREST E~ 2205 FT - 3
Item
354
356
Description
Steel Tower and Fixtures
Steel '!'ower and Fixtures
-1993 (Watana)
Towers
(Includes foundations and hardware)
2000+ (Devil Canyon)
Towers
(Includes foundations and hardware)
Overhead Conductors and Devices
overhead Conductors and Devices
-1993 (Watana
-Conductors (2 x 954 kcmil/phase}
Shield Wire (3/8 in., 2/circuit)
-Submarine Cables
r-1 -Material
L -Labor
~ ~-~"'~M 11"'!! ---~~·~ -... ~.::;;;;
Quantity
I
i. 2,447
' ,
546
-·
( 556
6
',
-~ Jl!!l
Units
Each
Each
Miles
Lump sum
.1!11
Unit Price
M 30,280
L 22,843
M 30,280
L 22,843
Pi~ 35,715
L 64,460
Material
Labor
Jll!ll .. .. Jill/
'
Amount Total
($)
.--,
(
/" 74,095,160 ~
55,896,821 ;
' I 129,991,981 f
16l532,880
12,472,278
($)
29,005,158 158,997,139
19,857,540
35,839, ?_~!!
55,693,300
25,000,000
18,750,000
43,750,000
.. .,
j
Revised January 25, 1982
... ..
··I •:.t_.
' '
~}
·~
~-
~
-c,:~~ x.~-~-~!~~
j:: -;. ,.-:.. ~ ' '
~ ...
..,.,..,._.,~ l t~~~~ ,_..
,,k·-:,"".~~"""'1
SUSlTNJ\ HYDROELECTRIC PROJBCT
PRELIMINARY ESTIMATE -ACRES M4ERIC1\N
WATJ\NA -DAM CREST EL 2205 FT -4
Item Description
?!!!!!!! "' .... -..:..:..__.'fl
2000+ (Devil Canyon)
Conductors (2 x 954 kcmll/phase)
359
-Submarine Cables
Roads and Trails
Roads and Trails
-Clearing and Roads
M -Material
L -Labor
~gg~ ~~
Quantity
124
3
200
l··~a.->"~,
~•, I -.lf'l)
',I ,J '-
~!J~ 1!!1 .... ...
Units ---
Miles
Lump sum
Miles
Miles
Unit Price
M 35,715
L 64,460
Material
Labor
$36,000
$18,000
.. 1111
Amount
($)
4,428,660
7,993,040
12,421,700
12,500,000
. 9,375,000
21,875,000
•; 1200,000
3,060,00~
10,060,000
1111.11
Total 1$)-
.-,.-_,..,
l
( 133,740,000
\ •,
10,060,000
Revised January 25 1 1982
.....
..
I :_,'~"
•'
!;:1:
I
. FROM:
l.suBJ£CT.·
I
I
I '
I~
I l
l
'J
IJ,
If' Jj
··'
OFFICE MEMORAl"~DUM
J. R. Plummer
D. Meilhede ~
E. N. Shadeed
-
Date:
File:
cc:
SUSITNA HYDROELECTRIC PROJECT
TRANSMISSION SYSTEM .
COST ESTIMATES -JANUARY 1982
January 12, 1982
P5700.07.08
J. D. Lawrence/circulation
M. w. Stoddart/U. J. Woelke
R. T. Sarofim
.A. .:tex/D. Kausha1
I am attaching a report on transmission line costs which
gives a history of the development .of transmission costs
and shows how~hey were arr~ved at. The transmission line
costs were est5~ated on a per mile basis and then broken
down to suit the FERC format. We also used the CAI estimates
for different terrain. This is summarized on page 2 of the
report. The CAI estimates are close to ones we have devel-
oped. See telephone conversation to D. Meilhede dated
November 10, 1981 which explains main differences. At that
time John Lawrence requested that our line estimates be
adjusted to include the differences applicable to our lines.
I tried in the report to give you a breakdown of the sub-
station costs for each one and explained the main elements
used. '
I am also including revised copies of the estL~ates.
ENS: jlh
Attachment
,
I
/..
·,
'I JiJ
---"·
FROM:
)SUBJECT:
I
-
ll
11 '
'
fi
1
I ...
I
I' \ r': \,
I~
J
;:J
.;;..... ·"
, ·:~ fT
OFFICE MEMORANDUM
J. R. Plummer
D. Meilhede
Date:
File:
E. N. Shadeed cc:
SUSITNA HYDROELECTRIC PROJECT
TRANSMISSION SYSTEM
COST EST~TES -J~JARY 1982
January 5, 1982
P5700.07.08
f) \.\
J. D .. Lawrence/Circulation
M. w. Stoddart/U. J. woelke
R. T. Sarofim
A. Jex/D. Kaushal
L. Pereira
The attached cost estimates do not include the following
-contingency allowance
-engineering
-construction management
-owners cost. ·
Previously we have used the following formula fer our
estimates
(engineering 5% + construction management 5% + O'tt."'lers cost
2-1/2%) x contingenoy 20%. The total percentage would theu
amount to 35%.
The cost estimate for switchyards at the powerhouses, e.g~
Watana and Devil Canyon have not been included. The cost
estimate for the In-Plant Control System at Watana has been
included. Also note that the Energy Management Syste.ui
Center (System Control Center} is now included in the
estimate.
The material and labor costs were identified as requested.
You will also note that the estimates have been staged for
transmission lines and substations, e.g. 1993 and 2000+.
The cost estimates have been identified by item numbers in
accordance with FERC requirements. I believe the contingency
etc should be applied to each item number rather than at the
end of the total estimate.
.·
ENS:jlh.
Attachment
' I
l
!
I
I
l
I
!
I l
l
'
~~~~! _:!:~~ !'!~'!!! e!!.~ e~~ ~ -'~
{
(
-;; ~~, ,;
~ r
SUSITNA HYDROELECTRIC PROJECT
PltELIMINl\RY ESTUIATE -ACRES AMERICAN
WATANA -DAM CREST EL 2205 FT
Item Description
Transmission Plant
350 Land and Land Rights
Land and Land Rights
-Transmission
-Substations (4 sites)
~.-.-~-A
353 Substation/Switching Station Equipment
Substation/Switching Station Equipment
,_ 1993
Ester
Willow
Knik Arm
University
Devil Canyon
(')
'"'
~ _f!!l ~ f!B!J
I
Quantity Units
179 Miles
Lump Sum
1 Lump sum
1 Lump sum
1 Lump sum
1 Lump sum
1 Lump sum
Ell ... Jlllll -.. .-..
Jannary 5, 1982
Unit .Price Amount Total
($} ($)
40,000/70,000 7,550,000
1,100,000 8,650,000
Material 20,775,000
Labor 3,665,000
Material 12,960,000
Labor 2,2BG,OOO
Material 10,700,000
r .. abor 1,890,000
Material 31,800,000
J ,t. Labor. 5,620,000
Material 12,750,000
Labor 2 , 2 6 5 , 0 0 o.
I· <>
l1aterial 89,985,000
Labor 15,726,000 104,711,000 i .
ll ' !.'' I ,
l; ~ I ..
Revised January 12, 1992
\
-J:f., ... -~~ ~ z=.-!~ ~.!!·~ ~~ ~~~c::crl-~"" ;.1\:<"~,e;::~
(
SUSI1l'NA IIYDROELECTRIC PROJECT
PRELIMINARY ES'l1IMATE -ACRES AMERICAN
WATANA -DAM CREST EL 2205 FT - 2
Item Description
-2000+
Ester
Willow
Knik Arm
University
!!¥~~
Willow Energy Management System (EMSj
-Equipment and System Costs
-Microwave Communications Equipment
EMS Control Center
Building and Equipment
~t~'t!
-\vatana/Devil Canyon In-Plant Honitoring
and Control Equipment
...
"""
!@''§'! ~ ~ ~
gual!tity Units
1 Lump sum
1 Lump sum
1 Lump sum
1 Lump sum
1 Lump sum
1 Lump sum
1 Lump sum
1 Lump sum
.. ... -1111 Ill .. ..
) 1 .. \
Unit ;!?rice Amount Total nr-rn
Material 2,455,000
Labor 435,000
Material 6,000,000
Labor 1,0507000
Material 980,000
Labor 175,000
Material 7,565,000
Labor 1,335,000
Material 17,000,000 ll, ',,.I " Labor 2,995,000 19,995,000
c, 'l
Material 8,110,000
Labor 3,420,000
Material 2,140,000 I.,
Labor 2,780,000
Material 2,110,000 t ·.. . :~
·. '. l'(J . ~ ~J!' Labor 1,750,000 ! -~-~ '"·" Material 3,000,000 I ... ""' Labor 1,770,000
Material 15,440,000
Labor 9, '.720, 000 25,160,000
l: ,,
I•
~ <• r
()
Revised January 12, 1982
e!! ~ it,..,.;."~.}.,.., (t=_:iiii! ~ ~ @}§ ~--
. r
SUSITNA HYDROELECTRIC PROJECT
PRELIMINARY ESTU!ATE -ACRES AMERICAN
WATANA -DAM CREST EL 2205 FT - 3
Item
354
Description
Steel Tower and Fixtures
Steel Tower and Fixtures
1993 (Watana)
Towers
(Includes foundations and hardware)
2000+ (Devil Canyon)
Towers
(Includes foundations and hardware)
356 Overhead Conductors and Devices
Overhead Conductors and Devices
-1993 (Watana
-Conductors (2 x 95.;; kcmil/phase)
Shield Wire (3/8 in., 2/circuit)
-Submarine Cables
~
M -Material
L -Labor
~.,. \.
"
~ ~ -4---ALY
Quantity
2 640
546
600
6
@@§I ~!!@
Units
Each
Each
Miles
Lump sum
)II§ ~
Unit Price
M 30,280
r. 22,843
M 30,280
L 22,843
~t 35,715
L 64,460
Na,terial
.Labor
ftll'
Amount
($)
~
79,939,200
60,305,520
140,244,720
16i532,880
12,472,278
29,005,158
21,429,000
30,676,000
60,105,000
25,000,000
18,750,000
43,750,000
111!1 ' '
Total
.( $)
..
169,249,078
Revised January 12, 1982
1111
'', J ' I '
·"'·
.t
'~·
• ' -• . . I • ' • ~ . . . ,., . ... ' ' .. . -' . . ' v . . -• •
'#?I.it§oi;w·•e . ., ''!~ • ma1 rir.; ••~···--~~~-· rye t!'A·_·_~)••--~--~·~t:-!=:ro ~··;·.·_tort"_· . ;;;:.e .. t't "-··"li~·Siii!IMl~ · 2 ~ · ... '~-:ur&i ... l&b' ·• •· • ·t ~__,:,_ • -;;,:,....,.,_ ~ •• ~""1£ · -~,,...8•••it~.; •• aliiliiiL~ •..
•
e_ ~~~~! ~II!! !'?"!! --'\~~ ................. t!'~IJ @ -'
I.
SUSITNZ\ llYDROELECTRIC PROJECT
PRELIMINZ\RY ESTIMATE -ACRES AMERICAN
Wl\TANA -DAM CREST EL 2205 ~T -4
Item Description
-2000f (Devil Canyon}
Conductors {2 x 954 kcmil/phase)
-Submarine Cables
359 Roads and Trails
Roads and Trails
-Clearing and Roads
~
M -Material r. -Labor
{\
ZL!ij MIJ ~ !mit llilf
Quantity Units
124 Miles
3 Lump sum
200 Miles
170 Miles
~ ~ 1M A!• -•• -
Unit Price Amount Total TSr-($)
M 35,715 4,428,660
L 64,460 7,993,040
12,421,700
Material 12,500,000
Labor 9,375,000
21, 875., 000 138,151,700
i !'I
JL 'I
$36,000 7,200,000
$18,000 3,0b0,000
10,060,000 10,060,000 . '
"L
Revised January 12, 1982
~-"'~ •• :w:::~· . :as< i ·, ... JaG~~:
~
(]
~· ~ ._~ ·;-:·~· Jd_.f ' .· .... ·, • o .. '' • ' '-....:,· ... ·:_·&·' • . ,• ' , .. • .. #•"'> ...... ' • ',, '," -("-·. ' 0: '' ~-~ ~~'-'C ·-·· ;J:\. "'"<f -·'~·. '' 'l' ·.'co :':f(, f' ,( '>;)' -: •• • •lit~.·.,_.· • C ~_JM·? ,{) 't; ,. -:: . : ', ' ', .' : • \' .... '. ','' ••• . • ;lf"'.·. --T\~'-_·"!-., "• , 7 (' ._-~j ••• -.·
•. rnr•----~~-..::.-:~:=z:z;:::::_::~=~!!J~~~"!!i 7 E ' 1 TtL:* ! ----:===== ~. -B~:Ua;; .:t ~ · • -nl,a±e ;',W...,.._ ~f._,~~: .. ~~A:t. .~,.~:A<···,.·*~»)4itb rWetnti'·ii::~-""~~ -~AA"'~~~ ...
~.; -.::::;-1/1'-
,_
~;;;~~:.~:--~ e:!'! t=?.! ~ ,..,. ""'-'-..... ,_·
I \
!
SUSITNA llYDROELECTRIC PROJECT
PRELIMINARY ESTIMATE -ACRES AMERICAN
WATANA -DAM CREST EL 2205 FT
Item Description
Transmission Plant
350 ( Land and Land Rights
( Land and Land Rights
vl -Transmission
-Substations (4 sites)
353
-..... -~ ~ ~..._..,
St:bstation/Switchi.ng Station Equipment
Substation/Switching Station Equipment
-~
Ester
Willow
vJ Knik Arm
University
Devil Canyon
~
(
~~ ...
n
;; __ J! ggg Wi@ .IJ!!II
-----~
Quantity Units
18~ Miles
Lump Swn
1 Lump sum
1 Lump sum
1 Lump sum
1 Lump sum
1 Lump sum
II\. I@ MMM ·IIIII ~ ~ -
\
Jqnua,ry 5, 1982
Unit Price Amount Total ($) m
40,000 7,950',000
1,100,000 9,050,000
Material 20,775,000 -,
1/;/·ro / Labor 3,665,000 _.! -,# ...
l-!aterial 12,965,000 ·-·1 • j /·-;!"-'( Labor 2,295,000 1,.) ,:,>}
Material 10,700,000 • 1
/ .... ' -"i~(> Labor 1,890,000 ! •" . I -
f.1ateria1 31,800,000 -I .3 7 ·;/:;o Labor 5,620,000 I
Material 12,750,000 _I j s ()M) r .. abor 2,250,000
Material 88"990,000 Labor 15,710,000 104,700,000
!~
..
I" -i, . d
'~J
It ,.,
I
I ·-
!
'i")_
!)
•,t
Ol.•· (',
,,·
.::o
C-'
•_-;.
<.:--
I:" .:'j~-.. ·---~.,..·:--·""'-----;::-~~;:-·-~·~-~.-~--~--~~ --·-----~-,-·-:-~e """'t· .··:;Fj , .~~~T~Wi"l?M\ili!Jfi''lot !"' w:;;;:Qx·~t]'P"JJ"'!~"'"'~IJiPi'FJWJt U£.iiNW'UV1f
'111\ } • • a • • • ..,.
1
' .. •
• • . .• • ~ • . ·• • • ·•.. • . -' • ' • : .• • . , • . • ' • :. • ·• ' •. "" • !> _. • .• . • • •
' .. -
·~# "' ...... ~'"""''. '• . : !! ::: ..,._ .. ...._,. .'!' ~ ~!!!!~ ! . . ,,r •I ·• . •, . "•' " . • • ···~',. •"'·>( o ~" 4" .,'<· -''c• .. < , .. ; ' rrrrnmt:rtttf' . . =::: = !S =~:::::: b!l!'!:::"* nro "'1'!!;r!t tal! ::t~ 0 • ·;;:,_~·~'t...i..._.;.. -A .• ~-.OU • .-111-~ ''·o "" . ~~-·.,..>iih~ Jo!U, ... ~ .. · ,... --.... ~;41 ~ ~ ... ~':.~·.vt;l<-~"""'~'"' '"_,,_,.. .._,,.'<'.;;;c.--\..~ ... "--'If "'";-• { __ _.. " ~·--·
SUSITNA HYDROELECTRIC i?ROJECT
PRELIMINAR~ ESTIMATE -ACRES ~iERICAN
WATANA -DAM CREST EL 2:G05 FT -.2 _..;;;., __
Item DeSQJ:iption
~-
Ester
Willow
p.c. Knik Arm
University
-'-».-----·--'""
\~~~ Willow Ene.rgy Management System (EMS)
-Equipment and System Costs
® -Microwave Communications Eqttipment
.. -EMS Control Center
Building and Equipment
-Wata.na/Devil Canyon In-Plant Honitoring
I f' and Control Equipment
'} lf ~·
'IJt o·
'-tl
G-
--... 11!1!!111 .. .. ~-""""-'\,·"'--l.; ···~•-•· r .. _ .... ._""""'_.._,. ~-~......... ,_,_,_,_~· -~._._, ___ ....
QuantitY.. Units
1 Lump sum
1 Lump sum
1 Lump sum
1 Lump sum
1 Lump sum
1 Lump sum
1 Lump sum
1 oOJ Lump sum
1 7 ~· ~ tJ qriJ
? (}.
v I V·
Jb!M ISQ .tift ~ .. -~ --~-~
Unit Price Amount Total ($) m
Material 2,000,000 J , . . ,., _, Labor 370,000 } .• ' t1 . • •
If
l-1ateria1 6,000,000 7 0 5""() rJ c.?O Labor 1,050,000
Material 985,000
1 Jc,o orJ() Labor 175,000
.Haterial 7,565,000
..-f .,1."}.-J () 'I ,•J Labor 1,335,000 l;\ .fl 1-
Material 16,550,000
II Labor 2,930,000 19,480,000
I ___ _.. __ ..
·,bfi(./')'fV{it.q7 •I'
" ... ---·· 3 I I) (1 0 I . .f.'laterial 8,110,000 ] r,, j I }-':io I ooo .... --··-; Labor 3,420,000
Material 2,140,000 ~-~~ ~ o ... •, u (j /; ~~'"i"~"-0 I J 4 -?i 72o oJu _ ···-Labor 2,780,00{)
Material 2,110,000 1(.. ( 01"1)( 3ll' 7 5".111&
Labor 1,750,000 ] /j J r&o () o u .. ' ' l
Material 3,080,000 ]
r, 7..t}·/foq'){~c_!_~
Labor 1,770,000 7' $)() 000
f.faterial 15,449,000
Labor 9,720,000 25,160,000
r lo . ! .
·~
-.;.~ . ' ~ ...... ) l l 0 .•..
~ ...
I
().
··~.
---/111!!!1!!!1 '.:.J,.,. .,_ -..;;, ~.-""'""' """"
;M!l!l!lli ... !1!!111 \· t-.• ~ • ' '
;i'\
SUSITNA UYDROELECTRIC PROJECT
PRELIMINARY ESTIMATE -ACRES AMERICAN
WATANA -DAM CREST EL 2205 FT -3
Item
354
Description
Steel Tower and Fixtures
Steel Tower and Fixtures
~.93:::.(\iataRa)
Tower a
-
\j\) (Includes £oundations and hardware)
.
pL-
___ ., __ ....__
(Includes foundations and llardware)
356 Overhead Conductors and Devices
Overhead Conductors and Devices
.-ir99'3-(Watana
""
-Conductors (2 x 954 kcmil/phase)
Shield Wire (3/8 in., 2/circuit)
-Submarine Cables·
\J
v -
M -Material
L -Labo\.,_.
,"'''-"'·
--.. ~ ~ ~
Quantitl Units
2 650 Each
665 Each / ..
-,
602 Miles
6 Lump SUI1l
~' ~
.,
Unit Price
M 30,413
L 22,943
-s-Jr3.>G
M 30,413 '\ T. ?? OA':I
M 35,614
L 70,000 ~
l-1~ter.j.al
Labor
')
.... ~'
Amount ITr-
.. \ ..
Total
($)
..
80,594.450 ]
60,798,950 /'// .J9J ~CJV
141,393,400
20,224,645 l J) .lfJ'/ 7L!o ~257,095 ..J
35,481,740 176p875,140
] (5 579 (2j
21,439,628
42,140,000
63,579,628
25,000,000 ] lf3 7)0 t)VO 18,750,000
43,750,000
·~--~Mli Ill ... ,.
·-I II
I~"
. I
' I \)
. . . . . . . . .._ . ~ . . . . ('
• .. • • • ~ II ~ • • ~ ' _1( ,. ... : p .., • •
"' ' • ' a, • ,. 1o I o 'II • ~ " ' ~ ,. , . ~ • ·) . • , ~ .. • • 9 • . ~ • •
~~,:•::;;;~~~~-~-~~.~·:~·--t \f,._, rl"'M!'t.·"""*-:•+ "'t. = * .,. e •• -... --.;~~~---f ~lil .• J:~)~·-,'"( " !' ;«-!~ ,J; ~ --b ·~,~ r:~" :."h~, ~ •. ~., .~;.: .; ... :,,;:,_.:,~4'>.. -~~-~:~.4~ ~doL '!l'
l 3f1ij " :,
.... ~ -ill!!!!!:l!!l ...... .,... .. -
r·
SUSITNA UYDROELECTRIC PROJECT
PRELIMINARY ESTIMATE -ACRES AMERICAN
WATANA -DAM CREST EL 2205 FT - 4
Item De§_Qription
~ODO~(eev~~&1Qn) 0(, -Conductors (2 x 954 kcmil/phase)
-Submarine Cables
ov
359 Roads and Trails
Roads ~nd T~ails
-Clearing and Roads
~
......,
r
M -Material
L -J.~abor
· .......
. '
.
MIBI .. ....
Quantity
151
3
200
170
-~ .. ..
Units ---
Miles
Lump sum
Miles
Miles
I
Unit Price
---· . ,.,.
(' M 35,614
L 70,000 ---'Jo.s-~14-
Material
Labor
$36,000
$18', 000
:' .. ,
\,.J
.. .. .. .. -\
I
I !
f
I Amount Total i ($) ($) I
i
I
l
5,377,714 J \
10,570,000 /) 7LJ7 7/lf
15,947,714
] 12,500,000 ;l/ Jl> Oou __!t_~75,000
21,875,000 145,152,342
: II , I
7,.200,000
3,060,000
10,060,000 10,060,000
I ~ ,,
I
I
I
I
I
I
I
I
I
I
)
I
I
I
I
I
t. ·~
I
I
UNtT FULL GATE FLOW=
UNIT FULL GATE OUTPUT=
UNIT BEST GATE OUTPUT=
875
1 ~
:tJ · KAPLAN TURBINES SPECIFIED
THIS PLANT DOES NOT HAU~ A !
UNITS
1
UNITS
1.
FULL
'1·999.
POt..fEf'• c KlrJ ·
ENEHGY <KWN.J
654860.
TOTAL ENEF~GY= 654860. KWH
TOTAL CAPACITY REVENUE~$
TOTAL FNERGv REVENUE= $
TOTAL REVENt '£= $
PLANT CAPACITY FACTOR= 44.9~
DO YOU WISH TO RE-EVALUATE?
1
INDICATE VARIABLE~ 1=PLANT T
UNITS!' 4=POWER VALUES" 5=E:
B=FLOW-DURATION CURVE. !1 9=MAI.
77
UNIT FI.ILL GATE FLOW!' CFS'?
1~~~2~5
0
.'Jsernarrn? t ST~~flN
j::·~s!:!.t..ro rd!
WeJ~om~ to VAX/VMS U~r~ion
ENTER PROJECT CODE CPl23456J ; P~1~
Terminal1 CP>rint~r or <V>ideo: P
~**********~***********~**********~
F. M I ~-(.\ '{' • ., • ·~ 0 I" (l N· ·":' , I .:_. ~ ·-. ~, .. I
,,, •II •II •II [I ., s 1.•' ('• !:• ~ (' F. rr R D ''I • T. ,"'J,. .~ .. ~ • ~ ~\ ~I •• ~ • & t.._•. 6
~~ t=;~UN HYDF\•O 1
NO OF VALUES ON f.JHICH FLOM-DIJ
l
-~ . f
.• J
\
.)
\ ' /
V" .1'
> ,'' : r
.. :
':
FULL GATE FLOW= 875. CFS
1999. KW
1800. KW
FULL GATE OUTPUT=
UNIT BEST GATE OUTPUT=
KAPLAN TURBINES SPECIFIE~
THIS PLANT DOES NOT HAU~ A PENSTOCK
UNITS
1.
UNITS
1
POWER CKWl
FULL BE~T
·1999. 1800.
ENERGY <KWH)
654860.
~~ TIMF
4 .. 80
TOTAL ENERGY= 654860. KWH
TOTAL CAPACITY REVENUE~$ n.
TOTAL ENERGY REVENUE= $ o.
TOTAL REVENUE= « 0 ..
PLANT CAPACITY ~ACTOR= 44.9Z
:"/. TIME
4 .. 80
tJALIJE ( $/f(J.,:. 1
o .. oo
U~LUE (MIL LS/1-~f·IH)
o ... oo
--
DO YOU WISH TO RE-EVALUATE? O=N07 l=YES
1.
fi'E 1 .. 1ENUE < $ )
o .. oo
REVENUE {$.)
o .. oo
INDICATE VARIABLE~ 1=PLANT TYP~~P~NSTOCK LENGTH. VELOCITY. 2=UNIT TYPE• 3=NO. OF UNITS~ 4=POWER VALUES, 5=ENERGY VALUES,. 6=-Gf\"OSS HEAD,. 7=UNIT FULL G~TE FLDl>l • 8=FLOW-DURATION CURV~, 9=MAINTENANCE FLnw, 10=0MIN
Y7
UNIT FIJLL GATE FLOI.oJ ~ CFS?
1.~:3:e2S5
0
.lJsern~me t qTH11N
P:;;o;~worti!
ijeJ~ome to VAX/VMS U~r~ion V~.3
ENTER PROJFCT CODE CPj2345~J ; P~~QOA1
Terminal, <P>I'inter or (V)ideot P ·~·--......
«*******'***************************************************~
PM'S AT 3!30 MONDAY NOV. 1A
~****~~************~ f*a*************~~*******~**t*~****~*~** .I
jf_,
I > :t ·• * n 1 sK sr.-c·F. n~B;,: It: s n LL t.llbl • • ,, .,
't RIJN HYDr:;:o 1 .. I NO OF VALlJF.S IJN IJ>JTCH FLQI.I-DIJP.ATION CIJP.VF.: TS !;<A . L---~·--·----~----~----·---~ ~-~----------·--·-----~~--·-··"-·---------··-------~---·----~~. -~-~.__,...,....-·. ~
'o
----··_,__,_----. -·-:r--·
C.~ •, "]
6 0
('
I
. "}
,_
. )
)
"~ ...
I
I
'1r-----~-----·~-------·-----~-·~-..,----·o·~._ •• ,_':'_·--~------~·==--~-~-+.......--~ .. ·--··
:.-:c
~.:
-
1,·
J '
(
~-I -~
~
~
f ~ J ..
f,
11 .>
~ '
/ )
·I
~ J
~~ j
l
r} 1
!
1
f' ~
' ' J
fl ~
. .:
r~ 't)
.]i , r,
.if
r·:~ . l!
w 'J
~
I r:.~ '~
~ ~ i
j f :~ .j v--r
I
•.. , s
I f f·· ·"' i ~ '
1 ,1)
I rR -~ r
f.
' ~
. .
~RID
M.emo Re Telephone Call
. JOB No.
DATE
FILE No ..
fs-7o-z). r.;; r
-~lin_,~ . I o jg I
CIRCULATE TO:
-
FROM ( Origi~ator) -£.11 · JLR-td
Cotnpony =-::Z6. c· . · .
TO r~/) -~~
Company f4{/ -d-<'~
L~~~k
'
I I 2...1 t)-nJ
/ .. >J .b
:f J-.:,7 S£ 2/j., 7 x. I o
-
--(
~·
~·
~
~
~
r\
r .•. l'
r·;
' t '
!· l' "'
,...
> w a:
N
U'l
, ... ~-........ ,...
0 z
:: a:
0
J· ' u. •
l !'
~--..
JOB NUMBER ____ _
FILE NUMBER __ _,.___ Calculations §v J 17 /V P-
SHEET I
BY /)QTt
;
APP G/VV'
susJecT: 7"7( IJ//.J/"'/J J/& )'!/
-t.#-/1/L.i T~ M~~ /'11-i~/PN
W,f-7/)/l/~ ..,. ",v; N
('C) /ZI ~7-7? /19 L.. t:2'7; 7 7 19~c;~
.r' -.P, .ft. J.;•.;.. ~ /A/7£~/l~ I;J.?~ '35'~ ICf
--T07/JL-//,()~-/59,J'S'
{CJur/ll w':~,q
a ; .J --
J"ZI Tlf~ 23 ~ r:Y~ X //t?.s-
l~t,;; IJA 1c E:
~E II I(; ( /J /II YO 1?.1 71/I;V..I IV/I.t fl brV
y
C/AIJJ, j'VT,9L #!~~0
~~~r,~~~~#G~ /d, 9?
6S:~1
I
ll
tf
~
~
~
f1
>
~
rJ
J .. ·.:r.~ J
-:> w a;
N
ll) -
--
,a (I
--)
0
Calculations
SUBJECT: T/(19/1/~·M/...S.J /o/1/
cO..J7S
0
l·j'/J 7/1 i--i/! I// I 9 J ~
NJO
/9[/-'2
~~·,-.. lv'.:-"/"1/J./ It/ /"1 ~7' .Sir ;";()r>~.-· /S~a~s-
CJ/J,I;.)
~s-o, s-o
2!J, 10 -300, ~0
II ,,
-":;7,$1 -
'3 3 3,/J'
1)}3 Cl/t-Cl9t1'!~17/ !Ill JP2
/-;< iJ (//~ '?' f ;-r; 7/t)111 j
CONT
,F-.n/6-#1.... ~~(14;11/
J5 o, 20
~5,?8'
/3,;~
v.;?
ff.i';
\;;. ' '
JOB NUMBER ____ _
FILE NUMBER. ___ _,____
SHEET __ ~2----OF_-<__.;,____
BY---.....-DATE IIJ/,~1:/
-
/t7,3'/
CfS./J
2~J CJ::?
§~~)
~;.:;,6 3
39, ~t
3 5.')-,{) 7'
·" . . .
DATE/::? ;-:J1!:~'
<)
-
··~----·-~-...__ .. _
"---.
~ ~
~
~
~
~
/{ E/'VltJv£ __ .. _/ /t/TE ;R T/£. _. ..c (,)! ?/ .. _r-~0/!? ·----···---
;~::> .-r
I ---
;;;---· .... '·-_, ____ ---·-------·--· -----------·-·---·--·-______ .. ________________ ---·····
3tJ 7, .J? -[///J-7/}·11/,Il .. . ... -·-
?--~---..
, ~JO o
/ lt 7
J73 ~-TA' I} /vt.i /t/J...:.;-; tfr'/
~~~T:
r r·~----. .. . . -----~ ... --·-.. ----·-·-----~------·-----------------·--. ---· -·-·-· --··---·-··-··--· ··-·--·--·--. -·----
-~ 4;
.
.... .. ~ .. • -' ...... ·• ,.... .. .. . • ... ... .. .• ~ •• ,... .... -... ~ .. -·-.... ~ -· ·• ,.. "* .. '
!-· , . .
ll
.1
-................ ,_ ....... ..,..,.._,. ~4 ·~ ··-·t· _.,
I
--_ ... ____ .,. ___ ,. ____ ----·-----·--------
. •'~ 0
vi . ~ g: g
2d f.-
;' , ........, ..
·.!
____ , ______ -· ·~" ---.
. •
--#---. ~.:. 0 Ml ~~ ~~::~t.(k-----·--·-----·-· ---·-·-··-··-··---·-··3 __ ?. 7~-e _ '-.-!& _____ ... -·~-------·--
~.t~d:~ti..:o.f.d.,.._ -··-----__ . ---···· ---L:!Ji:' .. s-@ __ ---If
4
--~.,~,.--·3----
Jj ·----------··· ... --·-!_ __ 4__;1_~-·--~ ·-··--··--·-··---~~ --. ~~----
r
:J__.._.,t._)_ll-:x-.-~-_ _--a~~>V u;t)~J:: ____ ~~--~-~--=~--~-: ___ ·_·_-... --~~~-=~-~~ ----
F . V
j!. ---------·-·---·---·---.• ·--··---. .. # ·-------~~-----··· -·-·--.. -·---t;. R: '6. @ ..
l' 1
;!, t/. c""' ~'5~,
. ----·--------~ -:!..-·• ~. . ··-·---.J,i'-. -···---
-----.. -·--··-------------:--.'!.? 3.. "!-l. -.. . ·-·---.... ?1. '1~ . .,._.:?_
--------·---·-··-·. ------. --· -·-----·-. . . .. . ·----··· ... -s.:;..9, t __ _
. -
r
I,
r' \
•.
..
(
TR~SMISSION -1993
October 30, 1981
$M
Watana -Devil Canyon
·'
2 x 26 mi, 345 kV, 2 x 954 kcmil
@ $207,000/mi 10.76
Devil Canyon -Fairbanks
2 x 189 mi, 345 kV, 2 x 954 kcmil (note conductor)
@ $207,000/mi 78.25
Devil Canyon -Willow .
2 X 90 mi, 345 kV, 2 X 954 kcmi1
@ $207,000/mi
Willow -Knik Arm
2 X 38 mi, 345 kV, 2 X 954 kcmil
@ $207,000/mi
~~ik Arm Crossing
2 x 4 mi, 345 kV submarine cable
@ $22,000,000/circuit
Knik Arm -University Substation
2 x 18 mi, 345 kV, 2 x 1,351 kcmil
@ $251,000/mi
Subtotal
Contingency etc -35 percent
Total Transmisston 1993
37.26
15.73
44.00
9.04
$195.04
68.26
$263.30M
·'·"'a ; o i
--.I ~
. J
I
I
11.
j
1\ ;
~~,
f '
'
li}
~:~.
_ji
0 ,jJ
/;
TRANSMISSION -·2000
Devil Canyon -Willow
l x 90 mi, 345 kV, 2 x 954 kcmil
@ $207,000/rni
Wi~low -Knik Arm
l x 38 mi, 345 k\7, 2 x 954 kcmil
@ $207,000/mi
Knik Arm Crossing
l x 4 mi, 345 kV s'Ubmarine cable
@ $22,000,000/circuit
Subtotal Contingenc~ 35 percent
Total Transmission 2000
,
• /,n I ,.,.: I ,,. "
co
()
•. .
$M
18.63
7.87
22.00
$ 48.50
16 .. 98
$ 65.48~1
~; { -. ·-.. ~ ~ --·
·I '· •I· • / .... :. ...-. .-..
~ :.~ ( " ~ ,{ J
4(
(
I ' I
I
I
' '
f
m
f
r
I
I
m
!, ~1
r
~; ,,
U.
r·
r
r
r
[
i
...
.'
r
l~
'
TRANSMISSION LAND ACQUISITION
AND CLEARING -1993
Watana -Devil Canyon
26 mi @ $75,000/mi
Devil Canyon -Fairbanks
189 mi @ $75,000/mi
Devil Canyon -Willow
90 mi @ $96,000/mi
Willow -Knik Arm
38 mi @ $96,000/mi
Knik Arm -Unive~sity Substation
18 mi @ $75,000/mi
Total Land Acquisition and Clearing
...
$M
1.95
l4.18
8.64
3.65
1.35
$29.77M
l
1
I
' I
t
r
I
I
!,
L 1'
f
r·
I'
f
f
r
r
r.
f
I'
SUBSTATIONS -1993
Base
Subtotal
Contingenqy e
To~t------
Devil Canyon
Base Cost
Circuit Break~rs -ll x 345 kV
Subtotal
Contingency etc -35 percent
Total
Fair-banks
HV
$M
2.00
$M
2.00
8.00
$10.00
3.50
2.00
11.00
$13.00
4.55
$17.55M
LV
$M
Base Cost
Circuit Breakers -10 X 345 kV 10.00
-4.5 X 138 kV 1.80
Transformers - 3 X 150 MVA, 345/138 kV 2.70
Shunt Reactors - 2 x 75 MVAR, 345 kV 1~66
Static Var Sources -100 ~!VAR
Subtotal
Contingency etc -35 percent
Total
S~tion Total
3.00
$16.66 $ 4 .. 50
5.83 $ 1.58
$22.49 $ 6.08 ---
4>
I
\
l
~*~----·---_ .. ··---
SUBSTATIONS 1993 -cont'd
Willow
Base Cost
Circuit Breakers -9 X 345 kV
138 kV - 3
X
Transformers -2 X 75 M'VA, 345/138 kV
Subtotal
Contingency etc -35 percent
Total
Station Total
Knik Arm -East
Base Cost
Circuit Breakers -B x 345 kV
- l X 138 kV
Transformers -1 x 75 MVA, 345/138 kV
Subtotal
Contingency etc -35 percent
Total
Station Total
University Subs~ation (AML&P Tap incl)
Base cost
Circuit Breakers - 9 X 345 kV
- 6 X 230 kV
Transformers -4 % 250 MVA,
Static var sources -400 MVAR
Subtotal
Contingency etc -35 peroent
Total
Station Total
Total Substations 1993
345/230 k\T
f)
HV LV
$M $M
$
$
2.00
9.00
1.20
1_. 00
11.00 $ 2.20
3.85 .77
14.85 $ 2.97
$17.82M
2.00
8.00
.40 .so
$ 10.00 $ .90
3.50 .,32
$ 13.50 $ 1.22
$14.72M ----
2.00
9.00
12.00
$ 23.00
8.05
$ 31.05
4.20
5.20
$ 9.40
3.29
$ 12.69
$43 .. 74M
$~ J 2 ...Q4 j 22A6-
.$!:35~M.
v~s.Cj-/3."?) x/. () ~
(j) ::: ~~~.$"'
I
I
l
\ l!
I
I
l r
\
l
l
1
(
1
I
I
\
I
a
~
a
~
a
~.
o:
• u
a
D
rn,
n
M . u
l.
I
r,
-·
SUBSTATIONS 2000
Devil Cany~
Circuit Br"eak~ kV
Subtotal ~-~
Contingency
Total
Fairbar1ks
Circuit Breakers -1 x ~45 kV
-1.5 X 138 kV
Transformers - l X 150 MVA, 345/138 kV
Subtotal
Contingency etc -35 percent
Total
Station Total
Willow
Circuit Breakers -5 x 345 kV
-1.5 X 138 kV
Transformers -1 x 75 MVA, 345/138 kV
Subtotal
Contingency etc -35 percent
Total
Station Total
1.00
.60
.90
$ 1.00 $ .1.50
.35 .53 __ ..;.....;.._
$ 1.35 $ 2 .. 03
$3 .. 38M
5.00
.60
.so
$ 5.00 $ 1.10
1.75 .39
$ 6.75 $ 1.49
$8.24M
l
I
I I,
l I
f
I
1'-
\ 1-
8
0'
rT ~
c·
c
00
~·
a
0
rr u
D
D
r
LS·
l,c /
t &·
I.
SUBSTATIONS 2000 -Cont'd
Knik Arrn -East
Circuit Breakers -1 x 345 kV
Contingency etc -35 percent
Total
Station Total
University Substation (AML&P Tap incl)
Circuit Breakers 3 x 345 kV
- 3 X 230 kV
Transformers - 2 x 250 MVA, 345/230 kV
Subtotal
Contingency etc -35 percent
Total
Station Total
Total Substations 2000
.,.Grand .. !r.Q,i;al-.Substations .
HV LV
$M ..;..$M __ _
1.00
.35
$ 1 .. 35 $ ===
$1.35M
3.00
2.10
2.60
$ 3~00 $ 4.,70
1.05 1.65
$ 4.05 $ 6.35
$10.40M
$ 21.60 $ 9.87
$31.47M
~3:34. 54 $. ,3.2 ....... 8-3-
6'· t./ 7-€ I J >< I.:._-__,
,24.~11
@
t I)
\
I
~
0
c
c
n u
0
0
0
n u
[j
0
1 ..
j
I'
I
'.l)
.. -. .. ... ~---~ . ..,
Total Transmission
Total Land Acquisition
Total Substations (EHV transmission and
switchyards only)
Not included transformers and
subtransmission switchyards
Notes
l. All quantities and equipment ratings, especially for Var
compensating equipment are subject to revision in final
electric system studies.
2 .. "Contingency etc" --. .. .. consist of 20 percent contingency .. : plus -5 percent engineering !"'
5 percent construction management
-2:.5 percent owner's cost
3. HV substation costs include EHV switchyards only.
LV substation costs include transformers and low-voltage
circuit breakers for transformer entries.
...
" ..
'17 .
I)
•.
'