HomeMy WebLinkAboutAPA188pc.wo J88G; DRAFT July 22,1982 JRP 'SUSITNA HYDROELECTRIC PROJECT ACCESS STUDY Development Qfa Plan to Complete Access to Watana Within One'Year of Licensing The following report reviews the task of completing initial access to the Watana site within twelve months of receipt of FERC license.•Three routes have been considered.These are Denali (Plan #17),North (13)and South (16).. In assessing the problems of constructing these alternative routes it has been concluded that the South Route would be the most difficult.Therefore,the report uses this r-oute as the basis for developing a construction plan. The objective of initial access construction is to provide land access for the start of delivery of heavy construction plant and materials within one year. The tas k is rev;ewed under the fo 1.1 ow;ng head;ngs: 1 -Management It is essential that the Project Management and Powei'Author;ty are commi tted -.to achieving the goal set forth,and that all necessary resources 'are made avail- able well in advance of need.In addition,numerous restraints that could impede progress must be removed.The Project Team must have the authority to act quickly and in direct response to field situations as they develop,and not be required to obtain Management approval for the day to day running of the construction work..Direct on-site management by a resident engineering staff of experienced earthwork,geotechnical,civil,surveying,hydraulic and expediting personnel can alleviate the nonnal consttuction delays caused by surveys and change order approval procedures. • •I I•I•I # .. -3 in selection of construction methods. A number of techniques can be used to speed up work: a)Constt'uct .minimum width .and fi'll depth consistent with available materials and foundation conditions. b)Place gravel fill in winter on frozen ground. c)Develop borra'"areas ahead of road construction..If work is to be done in freezing weather,open a limited face and keep work going 24 hours per day .. Backup eguipment,especially loaders.and dozers,will be required. d)Install culverts by excavating through fill,or use partially prefabricated Super Arch and panel box culverts which can be rapidly placed and covered. e)Use short construction time single span military IiBailey"or panel type bridges over narrow.stream channe'ls,which have spans up to 210 feet,and 90 ton capacities up to 110 foot spansm These can be replaced later with permanent bridges. f)Place fill oVer filter or geotextile fabric,using load distribution or stress bulb spreading method. g)Avoid cut a~d fill operations.Generally initial road should be constructed with gravel fill. h)Provide adequate right-o~way width~and locally,several alternative routes,to give flexibility in alignment in areas of poor foundation condit'ions (bogs;permafrost,sidehill spring areas,slope stability problem areas). i)t1i nimi ze stri ppi ng,both to (..ave time and to avo;d many of the permafrost problems -clear and fill directly. • ·'c:..........'..".. "...".... '1 -.'", // '...'.'. /0 '••1 ---'---I '. / / -- 7 . I f .' .- // // /.I / i/ / l1 .32 / , l--,-- I I / I /'=-.GIC....-:'7'1).C _ // // /' V .300 /00 ..........."A~_---...__~---.. ~-'O - BY«~..r::,T.;?;fzk Z-stJ Bj C:CT ~__.~,____ CHKP.Ely DATE ".~______.. 2 Zz / 6 12 G /2 E~?I Z z. 2 z / P/r --.[)7 DCJ££R.s 9So Lo40£RS P/FL.7/CZ/CK:.5 /://.:l/l'..//:772po.::.J CR:.rs:'r-l.::::K/..;-'C;;?~-=:·-I $Jd.t..///G -co 7ON'Z)aHPS 3.5/0101 7/ SJ5R&40 t:jCOMP;:cr /.:f0 G G./39lJE72..s D 7 002.£.12:5 B/SCOH?4c/oj~ Pf//l7EZTZPCKS R,.tJIL#c8f? .s~gC:;-E".DE He/} + 4- 4- 4- 4- G,e--;-:D.C. 1 ZJ·c -7 8RIj}GE"I tv'19//7,..",4 ?.e<?/-?'c1 8E/..ZJ<S"E .c=H H .E PI£.E t4 2 4-2-4-2 4-2 4- 2 4-2-4-2-4 Z 2- /2 I Z I 2 I Z Z...;-2.4-2-4-/2- I 4-/4 /2 24-I#-28 10 /2 - 2 4 2 4 .J 2 2-4 2 4 I 2-.q.. 2 ",,"L 2 4-I 2 /2-/2.------ l '7_·_ V _--'~_,_~_S ~, CL Z=;::Je./NG P7 DOZcRS H/JC --c!3/4 772/lt:.7lJef Jl':/iC~Dl2ltt.5 CoH?££SJO..eS ·-"~E.r//LIc5HTJ 2ss8;t;;t:/C'/-/OE S""H 8/lCK.J!oE SO 7O/VCR/9NE -Lo-L?oY77<C/(';<s ;.z'/(",e-V?~0'("tt:S" ?ER..R:JA//'/EL.II @AlJ /"/h'VI'ITS//9/v'cE IJOG~.c;oER /;)7 ;Doz;.c-z. Atez//j;J/~/T L4/?o,<S C/lRPS'Y'LER..r/R/C:;-CFeJ I z 4- 4-z z. "1- 8 .2- 2 2-- /2- 90 32- /Z E!. 2 I 2 2 3 I / I 2 4 / L I / 4- 2 4- 2 / 2 2_ 2 2.- Z 2- 2 /2 4- 9$ 33-/3'2 /2 /2 /2 2 2 3 6 /2 2 2 3 2 /2-Z 123/3 /2 /2 /2: ,2-I z /z / /Z /Z 2-4- 2 2 /2 "I I 4--2 2 -- Z./2--- 3 C /?-- 3 C /2 /2-/2- /2 8 /0 _4-4-/C!- /07 77 5'1 38 27 2/ --S-9//4~.;J/S//09-80 Ar-'h-c-/...·"- ...._a--"-.-,-_._______ .. JI.. .. I By Checked 60.04.03 For.m 1488 Rev -- '-"By ['late Project No.~~~~~Checked __Date Calculation No.____Page8 0 f -- ---.---.----'~1t -(J'Tov v,--A- ----. I-)-\.."....- Ca Iculat ionsSUBJECT..".•..pOJ LL..-. -:; t ... CJ - 2 - a - VJ-,r~,,, U - ([ - -; V}- co -;; () ..--- 'S:" - <1. - ~ - LL - "/ •aI .04.m Calculations By Date Project No.~~~f~SUBJECT Checked Date Calculation No.Page.k.of ~Rev By Checkedt/~~•I ~'R~C'\Q ~It~.~~~ "~~\"~\J ~i\ \1 ~\' \) ~l {\ ~'"\)~ ~\~~" "i""~~.•.~4 ~~\' r~I ~~~,""'-.,""~'\~, ~~...s~~I ~\}\' ~.~ \Q '\.~V 'S'\0 "}~~,\. ~~'*~ \~"-Z2 ~~.~ ,.. ~ "~.\:~~~~t\~~ e:&~i ~ 60 03 Fof'148B ..."",e I> .. .. , • • ,....../YJ.,-.;.~.~'.........,.,:=t ~.. ~-4 /Y1,7~ .~= --~o , Rev By Checked By .Date _~'"""'"-_Project No.__ Checked Date ---.Calculation No.------Page-'7-0f -E.. 7.1//2~-o /0 • 60.04.03 Form 1488 24-It /700 - // S-6 ~~'.//"00 ~~I"tJQ ,/C1 /YI /Za-o ~cS""o l t.x. CO.-?U-~2-rC.-.r 16;)To.?.?!d:r~~c~ ~/4- c:s:-;c~--;.D.C /...?/'"YJ /9'OC7/¢r'"C S"Q #j.r ~e a,C ->8r.:?2'I /700 ~,/00 I,-4-- A;-/~Je C. !I/-?~--:>J{" ....'....---- ~e::'~~~~~ -/'I&/J':--:;>7'. i/U.=>(y I ..r..--_--. f C a Ie ul a t ions SUBJECT u • • A REV, CHECtrEP f 1 seA\"·1! DRAWING NO. DRAWING NO. I DATE IS Jt.J1.""(&2.•SCALE DEPARTMENT ... ALASKA POWe~.AJjT'-IOre fry 2 peeLIMIJJA~Y L-O~t(:'-W~TA~A I ~as .f,1C3 a'- lGEOTECHNICAl IHYOR"""c I~ECHANICAl I IDESIGNED DR ....N .,j I I I ~...1PII'..ALA~~APOWe1e ALri~~rrY~• III ~l $tJ<a,\Tt-JA.H,,(r;?~CJ!l.e(;.TR.Ic:.~~v=:r::J II pre et-.I MJ JJA2YL-~",fC--WATAIJA ACe,8S7?~A:t'?L.AIJ.v,. sou l'H \=t 0 \.)TE ~.ic., t CONsrRUCTlON 1ELE;CTRICAl I 3 .rR;p 7J2lJra~ ---~~-----t-----+----+-----J._--.---'_.-.--t-----------t IS CH..API'.AI'P.ACRES AMERICAN INCORPORATED PROJECt p~1()()?q SHEft .z OF 2.. -....-J.....-...'.,'.~~......