Loading...
HomeMy WebLinkAboutUse of north slope gas for heat and electricity in the railbelt 1983USE OF NORTH SLOPE GAS FOR H EAT AND ELECTRICITY IN THE RAILBEL T L FINAL REPORT FEASIBILITY LEVEL ASSESSMENT EBt(£:0 EBASCO SERVICES INCORPORATED SEPTEMBER 1983 ~-ALASKA POWER AUTIIORITY _ _____, S u s 1tna Join-t Venture ~-;o ::-;;::::-.• ~··;,,;...... -----.. -------~~---'"-···· .. -..... _________ _ 0 __________________________ , I ~0~3--1 1 Please Return To DOCUMENT CONTROL r -~ ~SE OF NORTH SLOPE GAS FOR - HEAT AND ELECTR ICIT Y IN THE RAILBEL T Fl AL REPO RT . FEASIB~LITY LEVE L ASSESSMEN T EBfJSCO EBASCO SERVI CES INCORPORATED SEPTEMBER 1983 I ' ' I I I I am pleased to present this report prepared for the Alaska Power Authority by Ebasco Services,Incorporated.The purpose of this study is limited,and care should be taken not to draw un- founded conclusions. it is a feasibility assessment of certain technical aspects of North Slope gas utilization in the Railbelt.The study examines the engineering and environmental feasibility of three alternative approaches for generating and transmitting electrical energy.For each approach,the preferred type of power generation technology, gas transport facility,and electrical transmission system is identified.Based on representative electrical energy demand scenarios,a representative scale ~nd conceptual design is presented for each of the various facilities.The costs for construction of the facilities are estimated at a reconnaissance level.To provide a sound basis for the cost estimates,realistic physical settings are identified for each facility.Siting and environmental constraints are discussed. The study does not purport to offer a complete power development plan or to offer insight into the economic or environment~l tradeoffs of Nort~Slope.gas utilization in relationtootherRallbeltpowergeneratl0noptlons.On the other'hand~'" this report does provide a sound engineering,environmental and cost basis for undertaking more comprehensive power generation planning and analysis,where North Slope gas utilization might be one part of an integrated power development plan. The Power Authority's review of Ebasco's work has led to a difference of opinion on the selected electrical transmission line tower design and,therefore,on its construction cost.The Author- ity's view of the matter is discussed in the attached memorandum. The differences are a matter of professional judgement and resolu- tion will require a more detailed level of analysis. iN egg I .Al.I £;).. J~~3 LTBRAR-Z August 29~1983 USE OF NORTH SLOPE GAS FOR HEAT AND ELECTRI- CITY IN THE RAILBELT DATE: FILE NO: SUBJECT: -----.......-·ate of Alaska TELEPHONE NO: ReadersTO; MEMORAN'OUM FROM.~~,.(~ Director of Engineering 1~·4';;..~'-,\' I(., I I I I I I I I I I I I Attachment:As Stated 9986/065 ARLIS Alaska Resources Library &Information Services llnchorage,AJaska '.02-001AIRev.10 179! ~ After meeting with EBASCD,I instructed Diversified Engineers to prepare a conceptual tower design and,based on that design,prepare an independent cost estimate for the North Slope to Fairbanks Transmission System -Medium Load Forecast.Attachment 1 is a summary of the Diversi- fied cost estimate.A copy of Diversified's detailed cost estimate and tower design analysis is in the project file.(The Diversified concep- tual tower design was reviewed and considered satisfactory by Mr.Yerkes). To make the Diversified estimate comparable to the EBASCD estimate,I adjusted the costs for Land and Land Rights and added a 20 percent contjngency (see Attachment 2).The adjusted Divesified estimate is $1,680,118 t OOO.This compares to the EBASCD estimate of $2,370,827,000 (Table 2-6).In my opinion,the Diversified estimate is the more reasonable. This study included project scoping,preliminary siting,conceptual design and cost estimates for three alternative scenarios for the utili- zation of North Slope natural gas to generate electricity for use in the Railbelt Region.The three scenarios are based on generating facilities located on the North Slope,at Fairbanks,and on the Kenai Peninsula and the study is based on medium and low load growth forecasts.The concep- tual estimates prepared by EBASCD can be grouped into three categories; 1)generating facilities,2)natural gas transmission and distribution facilities and 3)electrical transmission facilities.After reviewing the cost of estimates,it is my opinion that the cost estimates for the generating facilities and natural gas transmission facilities are con- servative,but reasonable and satisfactory for this level of study. However,in my opinion,EBASeD's transmission facility cost estimates are overly conservative (too high)and I cannot support them. In order to try to resolve differences,I requested and received estimating backup data from EBASCD,and on May 16,1983,Mike Yerkes of our staff and Art Lee of Diversified Engineers and Constructors,Inc.11 met with the EBASCD staff at Bellevue,Washington.The EBASCD cost estimates are high,because,in my opinion,they are based on a very conservative transmission line tower design and because EBASCD used very conservative cost assumptions.EBASCD still maintains their design assumptions and cost estimates are reasonable. MEMORANDUM Project File --. August 26,1983 North Slope Gas Study, Cost Estimates Draft Final Report by Ebasco, January 1983 State of Alaska' DATE: FILE NO: SUBJECT: TELEPHONE NO: <i:> !10 ,,!,'l'~ Robert A.Mohn ~n 9 Project Manager Remy G.Williams ~ Cost Estimator TO: FROM:- Thru:_ 1-· 1- I~ 1-, 1-- I- I- I- I I I I I I I Based on the Diversified estimate and on Power Authority bid experience on the Anchorage-Fairbanks Intertie,I prepared cost estimate \"' !iL)02-o<llA(Rev.10;79) 'I· I I' I I I I I I I I I I I I Memo to Project File Through Robert Mohn From Remy G.Williams August 26,1983 Page 2 summaries for the -remaining transmissi9n schemes.The summaries are shown on Attachment 3 thru 7.In my opinion these estimates should be used in lieu of the EBASCO estimates. 1/Diversified Engineers and Constructors,Inc.,is under contract to the Alaska Power Authority to provide independent cost estimating services on an as-needed basis. North Slope to Fairbanks Transmission Line Medium Load Forecast May 26,1983 DIVERSIFIED ENGINEERS &CONSTRUCTORS,INC. COST &ESTIMATE SUMMARY 1-' I- I- I I I- I- I I I I I I I 1- Item l. 2. 3. 4. 5. 6. 7. 8. 9854/037 Description Switching Stations Substations Energy Management System Steel Towers &Fixtures Conductors &Devices Clearing Subtotal Land &Land Right Engineering &Construction Total Construction Cost Amount $86,190,302 140,399,826 5,786,116 891,777,010 36,238,112 143,253,589 $1,303,644,955 18,000,000 60,452,966 $1,382,097,921 -----" ~-- ALASKA POWER AUTHORITY 7/18/83 , R.Williams COST SUMMARY North Slope to Fairbanks Transmission System North Slope Power Generator -Medium Load Forecast (January '82 Dollars) Item Description Amount 1.Switching Stations $86,190,302n-2.Substations 140,399,826 3.Energy Management System "5,786,116"--'-"--4.Steel Towers &Fixture 891,777 ,010 r:-5.Conductors &Devices 36,238,112 6.Clearing 143,253,589U ,., Subtotal $1,303,644,955 Iu 7.Land &Land Right 36,000,000 [8.Engineering &Construction 60,452,966~.-Management C Subtotal'$1,400,097,921 Contingency 20%280,019,584 I~Total Construction Cost $1,680,117,505L.: Lc Rounded $1,680,118,000 [j [ C C. b. L.9860/053 AlTA t.-;';1'1 EN I L ALASKA POWER AUTHORITY 7/18/83 . R.Wi l1iams COST SUMMARY Fairbanks to Anchorage Transmission System North Slope Power Generation -Medium load Forecast (January 182 Dollars) This estimate is based on Power Authority experience on the Anchorage -Fairbanks Intertie. [ r: L~ 820 mile x $750,000/mile Contingencies 20% Total Construction Cost =$615,000,000 123,000,000 $738,000,000 [ I L.....:..3 Note -This estimate is also for: Fairbanks to Anchorage Transmission System Fairbanks Power Generation -Medium load Forecast 9860/053 . ALASKA POWER AUTHORITY COST SUMMARY 7/19/83 .. R.Williams North Slope to Fairbanks Transmission System North Slope Power Generation -Low Load Forecast (January 182 Dollars) 36,000,000 60,452,966 263,501,558 Amount $57,000,000 87,000,000 5,786,116 891,777,010 36,238,112 143,253,589 AITItt.H!'1£N'4 1,317,507,793 .},221,054,827 $1,581,009,351 $1,581,009,000 Contingency 20% Subtotal Rounded Subtotal Land &Land Rtghts Engineering &.Construction Management Total Construction Cost Description Switching Stations Substations Energy Management System Steel Towers &Fixtures Conductors &Devices Clearing. 9860/053 7. 8. Item--r:- 2. 3. 4. 5. 6.r L [ [ c e L G_ r.·.··tJ· [ E [- [~ r'~ r~ [~'-~ o . [ r~· L- C: COST SUMMARY Total Construction Cost $441,000,000 ALASKA POWER AUTHORITY 7/19/83 - R.Williams $367,500,000 73,500,000Contingencies20% Fairbanks to Anchorage Transmission System North Slope Power Generation -Low Load Forecast (January 182 Dollars) 490 miles x $750,000/mile = This estimate is based on Power Authority experience on the Anchorage -Fairbanks Intertie [. c [ [ [ [ [' [ r L [ C C [ [ [ [ L L [ Note -This estimate is also for: Fairbanks to Anchorage Transmission System Fairbanks Power Generator -Low Load Forecast 9860/053 AfTJl ':H !'-!~A'T .) ALASKA POWER AUTHORITY .-'.;~ 7/19/83 Rev 8/25/83 R.Wi'll iams :. COST SUMMARY Kenai to Anchorage Transmission System Kenai Area Power Generation -Medium Load Forecast Submarine Cable Crossing Alternative (January 182 Dollars) ';::':':,- ~, [ [ L [ Item-1-.- 2. 3. 4. 5. 6. 7. 8. 9. 9860/053 Description Switching Stations Substations Energy Management System Steel Towers &Fixtures Conductors &Devices Clearing Submarine Cable &Devices Subtotal Land &Land RIghts Engineering &Construction Management Subtotal Conti~gency 20% Total Construction Cost Amount $120,000,000 5,000,000 151,200,000 7,200,00.0 36,000,000 104,080,000 $423,480,000 7,200,000 25,409,000 $469,089,000 91,218,000 $547,307,000 fTL~_, r..-..·.·· L [ .r~.;~ [} ['. 1 _-: --~';;" [.~.....:-.•...-."' c·····.···:.~. _.~-' ALASKA POWER AUTHORITY 7/19/83 Rev •.8/25/83 R.Williams COST SUMMARY Kenai to Anchorage Transmission System Kenai Area Power Generation -Low Load Forecast Submarine Cable Crossing Alternative (January 182 Dollars) This estimate is equal to the medium foreca$t estimate less $40,000,000 for reduced substation cost. $547,307,000 -40,000,000 c·- [c~~ [T ~Tw C [ C· ··- --- .:--~ [' -?_--- LL C' Total Construction Cost 9860/053 $507,307,000 ~~'~ t~-. n- L~", [- r.'-..·t" [: r~- [-~ C' 2999A USE OF NORTH SLOPE GAS FOR HEAT AND ELECTRICITY IN THE RAILBELT FINAL REPORT FEASIBILITY LEVEL ASSESSMENT EBASCO SERVICES INCORPORATED with FRANK MODLIN &ASSOCIATES and ALASKA ECONCMICS INCORPORATED SEPTEMBER 1983 TABLE OF CONTENTS -'!..••: 1.0 SlMMARY _ •It _ _ _. ......-... .. Page 1-1 1.1 PURPOSE.......• • • • • • • • • •1-1 1 .2 STUDY APPROACH •••• • • • • • • •••1-1 1.3 SCOPE .•It • •• • • • • • • • • • • • •1-2 1.4 RESULTS.• • • • • • • • • • • • • •••1-6 2.0 NORTH SLOPE POWER GENERATION -MEDIUM LOAD FORECAST.2-1 2.3 COST ESTIMATES •••••••••••• 2.3.1 Constructton Costs •••••••••••• 2.3.2 Operation and Maintenance Costs •••••• 2.3.3 Fuel Costs ••••••••••••••••• 2.3.4 Total Systems Costs •••••••••••• 2-1 2-1 2-2 2-7 2-7 2-10 2-12 2-14 2-15 2-16 2-16 2-18 2-19 2-19 2-20 2-20 2-22 2-22 2-24 2-24 •2-25 2-25 2-25 2-28 2-28 2-32 2-32 2-34 ... ..... ...... ·.... ·... ·.... .. ·. . ..... General • • • • • • • • • • • Combustion Turbine Equipment ••••••• Fuel Supply • • • • • • • • • • • • • • SUbstation •••••••••••••• Power Plant Support System Descriptions Construction and Site Services •••••• Operation and Maintenance •••••• Site Opportunities and Constraints •••• 2.2.1 Overvi ew of the System • • • • • ••• 2.2.2 Voltage Selection ••••••••• 2.2~3 Towers ••••••••• 2.2.4 Conductors ••••• 2.2.5 Insulators •••••••••••••••• 2.2.6 Switching Stations •• 2.2.7 Fairbanks Substation ••••••••••• 2.2.8 Construction •••••• 2.2.9 Operatton and Maintenance 2.2.10 Communications ...... 2.2.11 Siting Opportunities and Constraints ••• 2.2.12 Fairbanks to Anchorage Line. 2.2.13 Anchorage SUbstation ••••••••••• 2.1.1 2.1.2 2.1.3 2.1.4 2.1.5 2.1.6 2.1.7 2.1.8 2.2 TRANSMISSION SYSTEM ••••• 2.1 POWER PLANT •••••••••••••• ~... ~-- -~... 2.4 ENVIRONMENTAL AND SOCIOECONOMIC CONSIDERATIONS ••2-34 2.4.1 2.4.2 2.4.3 2.4.4 2.4.5 Ai rResource Effects • • • • • • • Water Resource Effects •••••••••• Aquatic Ecosystem Effects • • • • • Terrestrial Ecosystem Effects ••••••• Socioeconomic and Land Use Effects 2-38 2-41 2-43 2-44 2-49 ii 2999A f' -, TABLE OF CONTENTS (Continued)r Page LJ 3.0 NORTH SLOPE POWER GENERATION -LOW LOAD FORECAST · · •3-1 [ .1 3.1 POWER PLANT .······ · ·····3-1 3.2 TRANSM ISS ION SYSTEM.······ · ..3-3 [3.3 .COST ESTIMATES · ···· · ·· ··3-5 1 3.3.1 Construction Costs ······· · ··3-5 ['3.3.2 Operation and Maintenance Costs ·3-5 3.3.3 Fuel Costs ···· · · ········3-5 3.3.4 Total Systems Costs ·· · ····3-5 L3.4 ENVIRONMENTAL AND SOCIOECONOMIC CONSIDERATIONS 3-8 J 4.0 FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST •4-1 [ 4.1 NORTH SLOPE TO FAIRBANKS NATURAL GAS PIPELINE 4-2 , 4.1.1 Gas Conditioning Plant · ···0 •4-3 [ 4.1.2 Pipeline ·· · ···· ··4-7 }········4.1.3 Compressor and Metering Stations ·····4-11 r4.1.4 Supervisory Control System ····4-11 4.1.5 Communications System •••··· · · •4-23 L· ·4.1.6 Operation and Maintenance Facilities ···4-23 4.1.7 Construction and Site Support Services 4-24 [ 4.2 POWER PLANT 4-25 ~.:j.················ 4.2.1 General ··· ·········· ··4-25 [4.2.2 Combustion Turbine Equipment.····· ··4-30 4.•2.3 Steam Plant ······· · ······4-30 [4.2.4 Substation ······ · ······4-35 4.2.5 Other Systems · ············4-35 ._-0 4.2.6 Construction and Site Support Services ··4-37 4.2.7 Operation and Maintenance ••••••4-37 [4.2.8 Site Opportunities and Constraints 4-38 ..->oJ 4.3 TRANSMISSION SYSTEM ····· · · ·····4-39 [ 4.4 FAIRBANKS GAS DISTRIBUTION SYSTEM 4-39······--j 4.4.1 Fairbanks Residential/Commercial [:Gas Demand Forecasts •••••••··4-39 4.4.2 Fairbanks Gas Distribution System 4-43 _...J· 4.5 COST EST IMATES ·· · · ··············4-55 l~ 4.5.1 Capital Costs.··· · · · · ··4-55 [4.5.2 Operation and Maintenance Costs ····4-59 4.5.3 Fuel Costs.• • • • • • • • • •4-62 ..-.J 4.5.4 Total Systems Costs ·········4-62 iii -G -" 2999A t iv 5.5 COST ESTIMATES •••••••••••••• TABLE OF CONTENTS (Continued) 5-6 5-6 6-3 6-3 6-5 6-5 6-5 6-7 Page 4-69 4-74 4-77 4-79 4-81 4-82 5-1 5-1 5-2 5-3 5-3 5-6 5-6 5-6 5-8 5-8 5-10 ·5-13 5-13 5-23 6-1 6-3 .. . .~.. . ... .. 6.1.1 General ••••••••••• 6.1.2 Combustion Turbine Equipment •••••••• 6.1.3 Steam Plant •••••••••• 6.1.4 Fuel Supply •••••••••••••• 6.1.5 Electrical Equipment and Substation •• 6.1.6 Other Systems ••••••••••••••• 5.4.1 Fairbanks Residential/Commercial Gas Demand Forecasts ••••••••••• 5.4.2 Fairbanks Gas Distribution System .•••• 5.1.1 Gas Conditioni ng Pl ant • • • • • • • • 5.1.2 Pipeline •...•••••••.•••0 • 4.6 ENVIRONMENTAL AND SOCIOECONOMIC CONSIDERATIONS •• 4.6.1 Air Resource Effects ••••••• 4.6.2 Water Resource Effects·.• • • • • • 4.6.3 Aquatic .Ecosystem Effects •.••••• 4.6.4 Terrestrial Ecosystem Effects ••••••• 4.6.5 Socioeconomic and Land Use Effects •••• 5.2 POWER PLANT ••••••••• 5.3 TRANSMISSION SYSTEM • •••• 5.3.1 Fairbanks to Anchorage 5.4 FAIRBANKS GAS DISTRIBUTION SYSTEM 5.0 FAIRBANKS POWER GENERATION -LOW LOAD FORECAST 5.1 NORTH SLOPE TO FAIRBANKS NATURAL GAS PIPELINE 5.5.1 Capital Costs ••••••••••• 5.5.2 Operation and Maintenance Costs. 5.5.3 Fuel Costs •••••••••••••••• 5.5.4 Total Systems Costs ••••••• 5.6 ENVIRONMENTAL AND SOCIOECONOMIC CONSIDERATIONS 6.0 KENAI AREA POWER GENERATION -MEDIUM LOAD FORECAST 6.1 POWER PLANT • • • • • • • • • • • • v 2999A APPENDIX A-REPORT ON EXISTING DATA AND ASSUMPTIONS APPENDIX B-REPORT ON SYSTEM PLANNING STUDIES APPENDIX C -REPORT ON FACILITY SITING AND CORRIDOR SELECTION APPENDIX D-REPORT ON TRANSMISSION SYSTEM DESIGN APPENDIX E -FAIRBANKS RESIDENTIAL/COMMERCIAL GAS DEMAND FORECASTS APPENDIX F -OFFICE OF MANAGEMENT AND BUDGET DRAFT REPORT COMMENTS AND ASSOCIATED RESPONSES 6.4 ENVIRONMENTAL AND SOCIOECONOMIC CONSIDERATIONS • • .[ ............1 [ C :[. ..._I .-.~ "E _,J [ :_.J L:.--1 - ...[ _..,;J L _J r,- 7[ .,~-~- --[ -[ .J [ J -- "r' -'-f j----' [ •.J CO r G Page 6-7 6-7 6-10 6-10 6-10 6-12 6-12 6-17 6-17 6-19 6-19 6-24 6-24 _ 6-26 6-27 6-28 7-1 7-1 7-3 7-5 7-5 .7-5 7-8 7-8 7-8 8-1 9-1 . . · .. · .. ·.. ·.. ·.. ·.. ·.. ·.. ·.. · ....·. . .. . . .... .. . ...... ... ..... ..... .. TABLE OF CONTENTS (Continued) 7.3.1 Construction Costs ••••••••• 7.3.2 Op~ration and Maintenance Costs •••••• 7.3.3 Fuel Costs •••••-•••••••• 7.3.4 Total Systems Costs ••••••• 6.4.1 'Air Resource Effects ••••••• 6.4.2 Water Resource Effects •••••••••• 6.4.3 Aquatic Ecosystem Effects ••••••••• 6.4.4 Terrestrial ECosystem Effects ••••••• 6.4.5 Socioeconomic and Land Use Effects •••• 6.2.1 Kenai to Anchorage Line •• 6.2.2 Anchorage Substation •••• 6.2.3 Anchorage to Fairbanks Line.• •••• 6.2.4 Fairbanks Substation •••••• 6.3.1 Construction Costs ••••••••• 6.3.2 Operation and Maintenance Costs • 6.3.3 Fuel Costs •••••••••••• 6.3.4 Total Systems Costs • • • • • • • 6.2 TRANSMISSION SYSTEMS 6.3 COST ESTIMATES ••••••••••• 7.0 KENAI AREA POWER GENERATION -LOW LOAD FORECAST. 7.1 POWER PLANT ••••• 7.2 TRANSMISSION SYSTEM 7.3 COST ESTIMATES ••• 7.4 ENVIRONMENTAL AND SOCIOECONOMIC CONSIDERATIONS •• 8.0 COMPARISON OF SCENARIOS 9.0 REFERENCES ••••••• ~~-LIST OF TABLES Tab 1e Number Title Page 2-1 NEW CAPACITY ADDITIONS AND FUEL REQUIREMENTS NORTH SLOPE POWER GENERATION -MEDIUM LOAD FORECAST 2-3 2-2 COMBUSTION TURBINE WITH GENERATOR DESIGN PARAMETERS NORTH SLOPE POWER GENERATION -MEDIUM LOAD FORECAST 2-8 2-3 TRANSMISSION LINE DESI GN CRI TERIA NORTH SLOPE POWER GENERATION -MEDIUM LOAD FORECAST 2-17 2-4 FEASIBI LITY LEVEL INVESTMENT COSTS 77 MW SIMPLE CYCLE COMBUSTION TURBINE NORTH SLOPE POWER GENERATION -MEDIUM LOAD FORECAST 2-29 2-5 FEASIBILITY LEVEL INVESTMENT COSTS 220 MW COMBINED CYCLE PLANT NORTH SLOPE POWER GENERATION -MEDIUM LOAD FORECAST 2-30 '-'--':.2-6 FEASIBILITY LEVEL INVESTMENT COSTS "..~ NORTH SLOPE TO FAIRBANKS TRANSMISSION SYSTEM NORTH SLOPE POWER GENERATION -MEDIUM LOAD FORECAST 2-31 --~ 2-7 FEASIBILITY LEVEL INVESTMENT COSTS ~--FAIRBANKS TO ANCHORAGE TRANSMISSION SYSTEM NORTH SLOPE POWER GENERATION -MEDIUM LOAD FORECAST 2-33 --~ 2-8 TOTAL ANNUAL CAPITAL EXPENDITURES NORTH SLOPE POWER GENERATION -MEDIUM LOAD FORECAST 2-35 ~.~- 2-9 TOTAL ANNUAL NON-FUEL O&M COSTS-,NORTH SLOPE POWER GENERATION -MEDIUM LOAD FORECAST 2-36 2-10 TOTAL ANNUAL SYSTEMS'COSTS NORTH SLOPE POWER GENERATION -MEDIUM LOAD FORECAST 2-37 ~2-11 ENVIRONMENT RELATED FACILITY CHARACTERISTICS SIMPLE CYCLE COMBUSTION TURBINES NORTH SLOPE POWER GENERATION -MEDIUM LOAD FORECAST 2-39 ~ 3-1 NEW CAPACITY ADDITIONS AND FUEL REQUIREMENTS _.~NORTH SLOPE POWER GENERATION -LOW LOAD FORECAST 3-2 --:.-.3-2 FEASIBILITY LEVEL INVESTMENT COSTS --NORTH SLOPE TO FAIRBANKS TRANSMISSION SYSTEM NORTH SLOPE POWER GENERATION -LOW LOAD FORECAST 3-6 vi --' LIST OF TABLES (Continued) Table Number Title Page 3-3 FEASIBILITY LEVEL INVESTMENT COSTS FAIRBANKS TO ANCHORAGE TRANSMISSION SYSTEM NORTH SLOPE POWER GENERATION -LOW LOAD FORECAST 3-7 3-4 TOTAL ANNUAL CAPITAL EXPENDITURES NORTH SLOPE POWER GENERATION -LOW LOAD FORECAST 3-9 3-5 TOTAL ANNUAL NON-FUEL OPERATION AND MAINTENANCE COSTS NORTH SLOPE POWER GENERATION -LOW LOAD FORECAST 3-10 3-6 TOTAL ANNUAL COSTS NORTH SLOPE POWER GENERATION -LOW LOAD FORECAST 3-11 3-7 ENVIRONMENT RELATED POWER PLANT CHARACTERISTICS NORTH SLOPE POWER GENERATION -LOW LOAD FORECAST 3-12 4-1 GAS DELIVERY AND QUALITY SPECIFICATIONS FAIRBANKS POWER GENERATION -MEDIlJt1 LOAD FORECAST 4-4 4-2 COMPRESSION STATION PIPE DETAILS FAIRBANKS POWER GENERATION -MEDIlJt1 LOAD FORECAST 4-14 4-3 CIVIL DESIGN DETAILS, FAIRBANKS POWER GENERATION -MEDIlJt1 LOAD FORECAST 4-15 4-4 BUILDING DETAILS FAIRBANKS POWER GENERATION -MEDIlJt1 LOAD FORECAST 4-16 4-5 COMPRESSOR AND GAS SCRUBBER DETAILS FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST 4-17 4-6 REFRIGERATION SYSTEM AND GAS HEATER DETAILS FAIRBANKS POWER GENERATION -MEDIlJt1 LOAD FORECAST 4-18 4-7 COMPRESSOR STATION ELECTRICAL SYSTEM AND CONTROL SYSTEM DETAILS FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST 4-19 4-8 MISCELLANEOUS COMPRESSOR STATION SYSTEMS'DETAILS FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST 4-20 vii 2999A \ -[ ~.f r( [' i [' I l,' r Li [ , r L [ [ , C [ .I L_...1 L ...I t _..1 L .-1 L __..1 L [ [LIST OF TABLES (Continued) Tab 1e Number Title Page [:4-9 METERS AND METERING STATION ELECTRICAL AND CONTROL SYSTEMS DETAI LS [FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST 4-21 4-10 MISCELLANEOUS METERING STATION SYSTEMS'DETAILS r~FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST 4-22 4-11 NEW CAPACITY ADDITIONS AND FUEL REQUIREMENTS FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST 4-26 L 4-12 HEAT RECOVERY STEAM GENERATOR DESIGN PARAMETERS FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST 4-31 r -4-13 STEAM TURBINE GENERATOR UNIT DESIGN PARAMETERS FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST 4-34 C '4-14 FEASIBILITY LEVEL'INVESTMENT COSTS NORTH SLOPE TO FAIRBANKS NATURAL GAS PIPELINE FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST 4-56 C 4-15 FEASIBILITY LEVEL INVESTMENT COST ESTIMATESL77MWSIMPLECYCLEC()1BUSTION TURBINE [FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST 4-57 4-16 FEASIBILITY LEVEL INVESTMENT COSTS 220 MW COMBINED CYCLE PLANT [FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST 4-58 4-17 FEASIBILITY LEVEL INVESTMENT COSTS [FAIRBANKS TO ANCHORAGE TRANSMISSION SYSTEM FAIRBANKS POWER GENERATION -MEDIlt1 LOAD FORECAST 4-59 [J 4-18 0A VALUES FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST 4-65 4-19 TOTAL ANNUAL CAPITAL EXPENDITURES C FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST 4-66 4-20 TOTAL ANNUAL NON-FUEL OPERATING AND MAINTENANCE [COSTS FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST 4-67 4-21 TOTAL ANNUAL COSTS L FAIRBANKS POWER GENERATION -MEDIUM·LOAD FORECAST 4-68 viii L C 2999A [ 2999A -[ ) 'f, ~-l. i [ _., -.' J l T' i ,~-~ r"l._~ ._.l n L ,[ [ " -[~ .~,., :[ .1 L,.1' r~ .,-~ "-~~; -,l'•,~ "IL,.1--, ,~ ':L _.J ·,t· o- r- ~-, [-- ;";.;. [~---- c-- ----t._.~ f~:- -"'(-,.. [" c·' r~ w c- [; [ c c_ c' p (j L- r:-t-~ L LIST OF TABLES (Continued) Table Number Title Page 5-9 APPORTIONMENT VALUES FOR THE GAS DISTRIBUTION SYSTEM FAIRBANKS POWER GENERATION -LOW LOAD FORECAST 5-19 5-10 CAPITAL COSTS ASSOCIATED WITH THE DISTRIBUTION SYSTEM FAIRBANKS POWER GENERATION -LOW LOAD FORECAST 5-20 5-11 OPERATION AND MAINTENANCE COSTS ASSOCIATED WITH THE DISTRIBUTION SYSTEM FAIRBANKS POWER GENERATION -LOW LOAD FORECAST 5-21 5-12 ANNUAL SYSTEMS COST SUMMARY FOR THE GAS DISTRIBUTION SYSTEM FAIRBANKS POWER GENERATION -LOW LOAD FORECAST 5-22 5-13 ENVIRONMENT RELATED POWER PLANT CHARACTERISTICS COMBINED CYCLE POWER PLANT FAIRBANKS POWER GENERATION -LOW LOAD FORECAST 5-24 6-1 NEW CAPACITY ADDITIONS AND FUEL REQUIREMENTS KENAI AREA POWER GENERATION -MEDIUM LOAD FORECAST 6-4 6-2 FEASIBILITY LEVEL INVESTMENT COSTS 77 MW SIMPLE CYCLE PLANT KENAI AREA POWER GENERATION -MEDIUM LOAD FORECAST 6-13 6-3 FEASIBILITY LEVEL INVESTMENT COSTS 220 MW COMBINED CYCLE PLANT KENAI AREA POWER GENERATION -MEDIUM LOAD FORECAST 6-14 •6-4 FEASIBI LITY LEVEL INVESTMENT COSTS SUBMARINE CABLE CROSSING ALTERNATIVE KENAI AREA POWER GENERATION -MEDIUM LOAD FORECAST .6-15 6-5 FEASIBILITY LEVEL INVESTMENT COSTS LAND BASED ROUTE ALTERNATIVE KENAI AREA POWER GENERATION -MEDIUM LOAD FORECAST 6-16 6-6 FEASIBILITY LEVEL INVESTMENT COSTS ANCHORAGE TO FAIRBANKS TRANSMISSION SYSTEM KENAI AREA POWER GENERATION -MEDIUM LOAD FORECAST 6-18 6-7 ANNUAL CAPITAL EXPENDITURES KENAI AREA POWER GENERATION -MEDIUM LOAD FORECAST 6-20 x LIST OF TABLES (Continued) Tabl e Number Title Page 6-8 ANNUAL NON-FUEL OPERATION AND MAINTENANCE COSTS KENAI AREA POWER GENERATION -MEDIUM LOAD FORECAST 6-21 6-9 TOTAL ANNUAL COSTS KENAI AREA POWER GENERATION -MEDIUM LOAD FORECAST 6-22 6-10 ENVIRONMENT RELATED POWER PLANT CHARACTERISTICS NATURAL GAS COMBINED CYCLE KENAI AREA POWER GENERATION -MEDIUM LOAD FORECAST 6-23 7-1 NEW CAPACITY ADDITIONS AND FUEL REQUIRa4ENTS KENAI AREA POWER GENERATION -LOW LOAD FORECAST 7-2 7-2 FEASIBI LITY LEVEL INVESTMENT COSTS SUBMARINE CABLE CROSSING ALTERNATIVE 7-6 KENAI AREA POWER GENERATION -LOW LOAD FORECAST 7-3 FEASIBILITY LEVEL INVESTMENT COSTS LAND BASED ROUTE ALTERNATIVE KENAI AREA POWER GENERATION -LOW LOAD FORECAST 7-7 7-4 ANNUAL CAPITAL EXPENDITURES "KENAI AREA POWER GENERATION -LOW LOAD FORECAST 7-9 7-5 ANNUAL NON-FUEL OPERATION AND MAINTENANCE COSTS KENAI AREA POWER GENERATION -LOW LOAD FORECAST 7-10 7-6 TOTAL ANNUAL COSTS KENAI AREA POWER GENERATION -LOW LOAD FORECAST"7-11 7-7 ENVIRONMENT RELATED POWER PLANT CHARACTERISTICS COMBINED CYCLE POWER PLANT KENAI AREA POWER GENERATION -LOW LOAD FORECAST 7-12 8-1 COMPARISON OF SCENARIOS 8-2 xi :::=: LIST OF FIGURES F;gure Number T;t1e Page 1-1 NORTH SLOPE SCENARIO 1-3 --1:'2 FAIRBANKS SCENARIO 1-5 "1-3 KENAI SCENARIO 1-7 2-1 SIMPLE CYCLE GAS TURBINE GENERAL ARRANGEMENT 2-4 2-2 SIMPLE CYCLE GAS TURBINE SITE PLAN 2-5 2-3 NORTH SLOPE POWER GENERATION -MEDIUM LOAD FORECAST -SUBSTATION ONE LINE SCHEMATIC 2-9 2-4 NORTH SLOPE POWER GENERATION -MEDIUM LOAD FORECAST -INITIAL STAGE OF SUBSTATION ~DEVELOPMENT 2-11 2-5 NORTH SLOPE POWER GENERATION -MEDIUM LOAD FORECAST -TYPICAL TWO LINE SWITCHING STATION SCHEMATIC 2-21 2-6 NORTH SLOPE POWER GENERATION -MEDIUM LOAD FORECAST -FAIRBANKS SUBSTATION SCHEMATIC 2-23 2-7 NORTH SLOPE POWER GENERATION -MEDIUM LOAD FORECAST -TYPICAL THREE LINE SWITCHING --'STATION SCHEMATIC 2-26 ---,2-8 NORTH SLOPE POWER GENERATION -MEDIUM LOAD ~:=j FORECAST -ANCHORAGE SUBSTATION SCHEMATIC 2-27 3-1 NORTH SLOPE POWER GENERATION -LOW LOAD FORECAST -SUBSTATION ONE LINE SCHEMATIC 3-4 4-1 GAS CONDITIONING FACILITY 4-6 ~4-2 HYDRAULIC SUMMARY -MEDIUM FORECAST 4-10 PEAK DAILY FLOW ·0 4-3 TYPICAL COMPRESSOR STATION LAYOUT 4-12 -:::} 4-4 TYPICAL METERING STATION LAYOUT 4-13-. '-;~4-5 COMBINED CYCLE PLANT GENERAL ARRANGEMENT 4-27 -PLAN VIEW 4-6 COMBINED CYCLE PLANT "GENERAL ARRANGEMENT 4-28 .--ELEVATIONS x;; ~ LIST OF FIGURES (Continued) Figure Number Title 4-7 COMBINED CYCLE PLANT SITE PLAN 4-8 COMBINED CYCLE PLANT FLOW DIAGRAM AND HEAT BALANCE 4-9 FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST -SUBSTATION ONE LINE SCHEMATIC 4-10 CITY OF FAIRBANKS -GAS DISTRIBUTION 5-1 HYDRAULIC SUMl1ARY -LOW FORECAST PEAK DAILY FLOW .' 6-1 KENAI POWER GENERATION -MEDIUM LOAD FORECAST SUBSTATION ONE LINE SCHEMATIC 6-2 KENAI POWER GENERATION -MEDIUM LOAD FORECAST ANCHORAGE SUBSTATION ONE LINE SCHEMATIC 7-1 KENAI POWER GENERATION -LOW LOAD FORECAST SUBSTATION ONE LINE SCHEMATIC xiii Page 4-29 4-32 4-36 4-45 5-4 6-6 6-11 7-4 -[ _.I -r --(' -L '-r'.,.- 'L f ·' .. .~ -n L..i., r~ L [ [ ,[ [ .1 ",[-~ ,- L: [ ~--j -L L L .- • I I •• •r I I- I I. I I I I I Ioo SUMMARY [ [ F [~ I~' L;;. r L [ [ b [ [ [ l L- r:li- l~ 1 •.0 SUMMARY 1.1 PURPOSE The purpose of this study is to examine the technical and environmental feasibility of several alternatives for the utilization of North Slope natural gas to generate electricity for use in the Railbe1t region,and to develop feasibility level cost estimates for each alternative.The alternatives are grouped into three scenarios based on selected generating locations,and the study is based on the medium and low growth forecasts of Rai1be1t electrical needs provided by previous studies.One scenario also provides for the development of a residential and commercial natural gas distribution system in Fairbanks. Previous reports developed for this feasibility assessment have detailed the existing data and assumptions to be used in developing the scenarios,the technical and economic bases for establishing power generating technologies,and the factors to be considered in facility siting and corridor selection~Potential environmental effects are detailed in this report.Tne previous reports are appended to this report for completeness. 1.2 STUDY APPROACH An initial survey of the electrical demand growth forecasts and the availability and characteristics of North Slope gas provided a basis for establishing candidate power generating technologies.Meetings and discussions with knowledgeable officials and industry representatives were held to focus the study on factors unique to each region,and factors unique to North Slope natural gas.Candidate generating sites and routing corridors (both electrical and natural gas)were evaluated.Forecasts of po~ential natural gas demand in Fairbanks and .details for a gas distribution system were prepared. 26478 1-1 Much of the above was completed prior to performing cost estimating tasks.While this study uses assumptions consistent with previous studies of other electrical generating scenarios for the Railbelt,cost estimating tasks have not included fuel cost derivation nor the development of cost of power values.Comparisons with alternative electric generating scenarios are therefore outside the scope of this studY.Such comparisons can be considered as .a logical extension of these studies which m~be performed by the Alaska Power Authority. 1.3 SCOPE The scope of the study was defined by the Al aska Power Authority to consist of three distinct scenarios.Each scenario was evaluated for .its feasibility to meet the medium and low load forecasts of recent previous studies which examined the electrical demand requirements of the Railbelt Region.The first scenario is characterized by the generation of electricity on the North Slope using simple cycle combustion turbines fired by untreated natural gas.A major,new transmission line system would be required from the North Slope.to Fairbanks,with substantial improvements to the transmission system connecting Fairbanks and Anchorage.Figure 1-1 is a depiction of the North Slope scenario showing the major differences between the medium and low load cases.The medium load forecast requires 15 units with a total capacity of almost 1400 megawatts (MW),two 500 kilovolt (kV) circuits from the North Slope to Fairbanks,and three 345 kV circuits from Fairbanks to Anchorage.The low load forecast can be met with 8 units (700 MW),two 500 kV circuits from the North Slope to Fairbanks, and two 345 kV circuits from Fairbanks to Anchorage.The present worth of costs of the medium load forecast is $3.8 billion versus $2.7 billion for the low load forecast.80th costs are in 1982 dollars and do not include fuel costs. The second scenario consists of two distinct parts:a generating facility in the Fairbanks area and a gas distribution system in Fairbanks.Transmission of the gas to Fairbanks from the North Slope would require construction of a high pressure gas pipeline,although 26478 1-2 r.' ~ ....,l l~ I ~ . I [ ; F [ .[~ .~,J .) r L, [ i C [ , [ .•J [; •.•.1 [ L •.j L;......J L"....J L FIGURE 1-1 SUBSTATION SUBSTATION AND LOCAL DISTRIBUTION SUBSTATION AND LOCAL DISTRIBUTION EXISTING INTERTIE LOW, LOAD FORECAST ••••8 SIMPLE~-_..CYCLE UNITS .1..1..1..1. FAIRBANKS POWER PLANT PRUDHOE BAY TRANSMISSION LINE LENGTH =450 MILES FAIRBANKS TO HEALY=110 MILES WILLOW TO ANCHORAGE:50 MILES ANCHORAGE TRANSMISSION LINE HEALY TO WIUOW:170 MILES EXISTING INTERTIE NORTH SLOPE SCENARIO SUBSTATION ALASKA POWER AUTHORITY NORTH SLOPE GAS FEASIBILITY STUDY HEALY 1-3 BASCO SERVICES INCORPORATED· SUBSTATION AND LOCAL DISTRIBUTION WILLOW SUBSTATION AND LOCAL DISTRIBUTION MEDIUM LOAD FORECAST 15 SIMPLE .L .L .L .L .I. CYCLE UNITS .L.&..L.L.L .LJ..L.L.I. [ L C' [ C C C [ L L E, [ ---- [~ r-'-' r [ C' L< [Y C' the size of the pipeline would be somewhat smaller than that proposed for the Alaska Natural Gas Transportation System (ANGTS).Electrical power generation near Fairbanks would use combined cycle plants consisting of gas fired combustion turbines,waste heat recovery boilers and steam turbines.A gas conditioning facility would be required on the North Slope. The Fairbanks generating scenario is depicted in Figure 1-2 which shows that five combined cycle and two simple cycle units are required to meet the year 2010 medium load forecast (1400 MW).The low load forecast (700 MW)requires three combined cycle units.The Fairbanks generating scenario requires a 22 inch diameter gas pipeline from the North Slope to Fairbanks and includes a natural gas distribution system to meet residential and commercial heating needs.Three 345 kV transmission circuits from Fairbanks to Anchorage ate required for the medium forecast and two for the low load forecast.Present worth of costs of the electrical generating scenarios,excluding fuel costs,in 1982 dollars is $5.4 billion (medium forecast)or $3.6 billion"(low forecast).The present worth of costs for the Fairbanks gas distribution system is $0.9 billion for the medium load forecast and $1 .1 bi 11 i on for the low load forecast. The third scenario is contingent on the construction of a major natural gas ~ip1ine from the North Slope to tidewater on the Kenai Peninsula. Delays in the construction of ANGTS have renewed interest in such an all-Alaska pipeline.This system is described in the Governor's Economic Committee on North Slope Natural Gas Report (1983)entitled "Trans Alaska Gas System:Economics of an Alternative for North Slope Natural Gas.II The Kenai e1 ectric generating scenari 0 incorporates the anticipated energy demand from this system's tidewater facilities into the Rai1be1t's demand forecasts.Fuel for the power plant will be derived from a blend of waste gas from the conditioning facilities and sales gas.A major transmission line would also be required from near tidewater to the load center in Anchorage.The existing transmission 26478 1-4 ,or 1 -l~ i ..[ .-.j l' r'~_J f l ", "[ [ .•..1 TJ il .l [ {~ ...j [ [ _,.l L_..1 .0 [ MEDIUM LOAD FORECAST LOW LOAD FORECAST PRUDHOE BAY CONDITIONING PLANT GAS PIPELINE LENGTH =450 MILES SUBSTATION AND LOCAL DISTRIBUTION SUBSTATION AND LOCAL DISTRIBUTION EXISTING INTERTIE ___~..~3 COMBINED -CYCLE UNITSPOWERPLANT FAiRBANICS TO HEALY:110 MILES WILLOW 10 ANCHORAGE =50 MILES ANCHORAGE FAIRBANKS GAS DISTRIButiON SYSTEM TRANSMISSION LINE t£ALY TO WILLOW =170 MILES EXISTING INTERTIE 1-5 ALASKA POWER AUTHORITY NORTH SLOPE GAS FEASIBILITY 8TUDY EBASCO SERVICES ..CORPORATED FAIRBANKS SCENARIO FIGURE 1-2 HEALY WILLOW SUBSTATION AND LOCAL DISTRIBUTION 2 SIM PLE CYCLE UNITS SUBSTATION AND LOCAL DISTRIBUTION 5 COMBINED .......... CYCLE UNITS ; ,~i - [ l l~ l L· line from Anchorage to Fairbanks would have to be up-graded to handle the generatiny capacity. The Kenai scenario (Figure 1-3)includes seven combined cycle units and one simple cycle unit to meet the energy demand in 2010 for the medium load forecast,and four combined cycle units and two simple cycle units for the low load forecast.In order to provide a highly reliable electric transmission system from Anchorage to Fairbanks,two parallel 345 kV circuits are required,even though a single circuit would be adequate in the low load forecast.Underwater cable crossing of Turnagain'Arm is cost effective,with two 500 kV circuits from Kenai to Anchorage.Cost estimates (excluding the pipeline and gas processing facilities as well as fuel costs)result in a present worth of costs for the medium load forecast of $2.0 billion,and $1.7 billion for the.. low load forecast (in 1982 dollars). 1.4 RESULTS This work has resulted in the development of several scenarios for meeting the electrical generating needs of the Rai1belt region using North Slope natural gas for fuel.Each scenario has been refined to establish schedules of generating capacity additions consistent with medium and low load forecasts through the year 2010.Chapter 2 and Chapter 3 detail the North Slope Power Generation scenario for the... medium and low forecasts,respectively.Chapter 4 and Chapter 5 detail the Fairbanks scenario,while Chapter 6 and Chapter 7 describe the Kenai Power Generation scenario. Engineering and cost evaluations of technologies capable of using natural gas to generate electricity provide a consensus for the use of gas fired combustion turbines.For the Fairbanks and Kenai scenarios, the turbines are exhausted through waste heat recovery boilers to power steam turbines. 26478 1-6 f' L,~ [ J L [" -~~ L._i l: ~.•'.J l' L -.1 1~ L [ .--_.. MEDIUM LOAD FORECAST LOW LOAD FORECAST WILLOW SUBSTATION· AND LOCAL DISTR I BUTION SUBSTATION AND LOCAL DISTRIBUTION SUBSTATION AND LOCAL DISTRIBUTION ANCHORAGE FAIRBANKS FAiRBANI<S TO KEAL.Y=110 MIlES ANCHORAGE TO .KENAI =87 MILES WILLOW 10 ANCHORAGE =50 MILES TRANSMISSION LINE tEALY TO WlLLDW.ITO MIlES EXISTING INTERTIE SUBSTATION AND LOCAL DISTRIBUTION WILLOW HEALY SUBSTATION AND LOCAL DISTRIBUTION SUBSTATION AND LDCAL DISTRIBUnON I SIMPLE CYCLE UNIT d' 7COMBfNED .. CYCLE UNITS ... .I. KENAI POWER PLANT .........4 COMBLNED CYCLE UNITS.L .L 2 SIMPLE CYCLE UNITS ~:.ALASKA POWER AUTHORITY NORTH 8LOPE GAS .,FEASIBILITY STUDY KENAI SCENARIO FIGURE 1-3 EBASCO SERVICES INCORPORATED .........1-7 All of the scenarios will require substantial construction of electric transmission lines.A power plant on the North Slope separates the generation and load centers by almost 900.miles,requi ri ng special transmission system design considerations to obtain a stable and reliable system.Generation near Kenai,on the other hand,requires a 500 kV underwater crossing of Turnagain Arm. Socioeconomic and environmental effects of generating significant amounts of electricity are substantial in both the construction and operation of the system.However,no effect would appear to preclude any of the scenarios.Both air and water pollution control measures associated with gas fired combustion turbines are generally modest compared to other technologies. Cost estimates are provided for each forecast of all three scenarios. Because each scenario is distinctly different,except for providing the required electricity,cost comparisons should not be the sole factor in evaluating the desirability of any scenario.However,within the scope' of this study,Kenai generation shows the least cost because it does not factor in the cost of the Trans Alaska Gas System and its associated processes.The Fairbanks scenario is the most costly because it includes a 450 mile natural gas pipeline,and a gas conditioning facility on the North Slope.The North Slope scenario is in the middle of the cost range and is characterized by the high capital cost of constructing high voltage transmission lines to Fairbanks. 2647B 1-8 or'..-,' r~ l-- °t I- F [ -[ r L [ ../ L [ .! IL, ,....J 'L •~_J [~ .._.:! L-'oo- j L ~,..J L___-J L r I' I I- I I I I I I I I I I I I 1- D- O- SCENARIO I NORTH SLOPE POWER GENERATION MEDIUM LOAD &JrA"BKA:RP'Q(ITn>,..",,,T .n.,..- U.s..DEPT.0 [ u [ c c o [ ,;~ L L L rl. [ 2.0 NORTH SLOPE POWER GENERATION MEDIUM LOAD FORECAST The first scenario,under the medium load forecast,centers on a major electric generating station on the North Slope at Prudhoe Bay,near the source of natural gas used to fuel the station.By the year 2010,the station would consist of 15 simple cycle combustion turbines capable of generating almost 1400 megawatts (MW)of power to serve the Railbelt. North Slope power generation does not require the construction of major gas pipelines,but does require construction of 500 kilovolt (kV) electric transmission lines from the North Slope to Fairbanks and additional transmission lines of 345 kV from Fairbanks to Anchorage. De.tai 1ed analysi s of the transmi ssi on system shows that a stabl e and reliable system can be designed despite the generation and major load centers being over 800 miles apart.The total construction costs for the system described are $4.2 billion,with total annual operation and maintenance costs of $1.1 billion.The present worth of these costs excluding fuel costs is $3.8 billion as of 1982.Environmental and socioeconomic effects of this scenario are substantial,but none have been identified which would preclude the project. 2.1 POWER PLANT The power generation technology selected for the North Slope scenario employs simple cycle combustion turbines utilizing 91 MW baseload, combustion turbine generators.The criteria and parameters which resulted in this selection are discussed in the Report on Systems Planning Studies (Appendix B). 2.1.1 General Development of a North Slope site for the required generating units, construction and maintenance facilities,worker housing,and access 2601B 2-1 facilities will be a major undertaking.In addition to continuously expanding facilities for maintenance and operation,there will be permanent construction facilities and a semi-permanent construction staff. The scenario for utilizing simple cycle gas turbine-generators to generate power at the North Slope requires fifteen 91 MW (nominal) units for satisfying load demand under the medium load forecast.The units would be added in increments beginning in 1993.On the average, slightly less than one unit per year is required through the end of the study period in 2010.Incremental and total required new generation capacity for this scenario are summarized in Table 2-1. The functional parts of the plant will consist of a gas supply system(s),the turbine-generators,various auxiliary and support systems,a central control facility,switchyards,and the northern terminus of the transmission line. A single simple cycle unit will require approximately a 90 ft x 150 ft enclosure as shown in Figure 2-1.It is planned that the units be installed side by side as shown in Figure 2-2 up to the maximum of 15 units required for the medium load forecast.The site will include the 138 kV switchyard behind the units and a 500 kV transmission line termination centered on the planned maximum plant site.A 300 ft wide buffer area surrounding the site is planned,yielding a maximum total site acreage of 90 acres. 2.1.2 Combustion Turbine Equipment The combustion turbine plant design envisioned is based on using currently available gas turbine units,rated by one manufacturer at approximately 77 MW each.Various other manufacturers'turbines of similar size could be used to satisfy the requirement of this study, but it must be pointed out that the specific plant output and various specific design parameters may be expected to change accordingly. 26018 2-2 r:u L C C [ [ .[ ,f" L L L .L n [ [ [ [ c [' c [ u [ [ c [ [ [: [: l~ L TABLE 2-1 NEW CAPACITY ADDITIONS AND FUEL REQUIREMENTS NORTH SLOPE POWER GENERATION -MEDIUM LOAD FORECAST New Capacity (MW)Gas Requi red Year (Increment/Total)(r.t4SCFy).!I Z/ 1990 0/0 O. 1991 0/0 O. 1992 0/0 O. 1993 91/91 6,574.6 1994 0/0 6,574.6 1995 91/182 13,,149.1 1996 91/273 19,778.7 1997 91/364 26,287.3 1998 91/455 32,861.9 1999 0/455 32,861.9 2000 91/546 39,546.7 2001 0/546 39,436.4 2002 182/728 52,585.6 2003 0/728 52,585.6 2004 91/819 .59,325.0 2005 182/1001 63,546.9 2006 91/1092 66,548.2 2007 91/1183 69,538.7 2008 91/1274 72,540.2 2009 0/1274 75,530.6 201 0 91/1365 78,532.0 .!I MMSCFY =mill i on standard cubic feet per yea'r. ~Values as calculated are shown for purposes of reproducibility only and do not imply accuracy beyond the 100 MMSCFY level. 2601B 2-3 ~----·IOOOI'..JA~ILI~ T~.FOtlM&a --------.-J I ~HT 14a'·O gO N I ~ 'LAN-77 HWNOHINALIATlNG/SIH'LE CYCLE 'L.ANT ALASKA POWE"AUTHORITY NORTH elOPE GAl FEA ••LITY ITUDY SIMPLE CYCLE GAS TURBINE GENERAL ARRANGEMENT EBASCO 8ERVlCEIIICORPORATED ,--,cr-:.~,--.,,~,0Tl ~~'rT'J ,~~......."r----',CD ..--....-.--....,.----";--":--"j c-''J ~ \Ii \;.",j o'l C ~'~r-:-J c:---J ,"rJ rr7"J 'IT":Tl 'L.,.J rr-:l r-,C=-:J ["C';"J ;")~~r---,.~c-J r~.., \"1 ...,]"J'<>1/:-'-"-J k """_)~_..J '-" , t &, III 11 ,~ 11 ..0 ~'O !~ 7!50 -no ""01410 '''!50 ?IHIN..ON,,,' ALASKA POWER AUTHORITY &\lNI'T.•.0 ,.,liMIT.•1110 -~---- ---+-- ------....J --.-..--------..--.----.---_.------.---*----T A --...--......------.-.-----~I (!:leI!'DIMI'NSlOH ~1!JI...). ~qd I -I t~~DDDDD§lD j i,-0--EJ-~---0 ----~~I ~,~KV A~!.A.I I t I I + I I 1 *M~liN P'tII!f'lM)H()l ~'T"Ol!.1C1~1 L()C,6,.'TION1O, ~4!5""I"OIt F"'~~~'T10!'0I. r-----.----- I I f I I t I I t I I N I 11l NORTH SLOPE GAS FEASIBILITY STUDY SIMPLE CYCLE GAS TURBINE SITE PLAN NORTH SLOPE FIGURE 2-2 EBASCO SERVICES INCORPORATED At International Standards Organization (ISO)referenced conditions (59°F and sea level)plant performance will consist of a net unit output of 77 MW.The ISO heat rate of the units will be approximately 11,900 Btu/kWh (higher heating value [HHV]).For the actual conditions eXisting at the North Slope (average annual temperature of 9°F and sea .level)the rating of the turbines is approximately 91 MW and the heat rate is 11,500 Btu/kWh (HHV). Each combustion turbine is a large frame industrial type with an axial flow multi-staged compressor and power turbine on a common shaft.The combustion turbine is directly coupled to an electric generator,and can be started,synchronized,and loaded in about one half hour under normal conditions. The gas turbine generators are "pac kaged"units and as such include all auxiliary equipment.The package generally includes: (l)13.8 kV switchgear which houses the generator grounding transformer,and generator air circuit breaker. (2)Nonsegregated phase (iso-phase)bus work wnich runs from the generator to the main transformer. (3)A master control panel for overall operation and monitoring. (4)A transformer (13.8/4.16 kV)sized to support the ancillary load (estimated to be 2 megavolt-amperes [MVA]). (5)A 4.16 kV switchgear with air circuit breakers for other loads (e.g.800 horse power [HP]cranking motor).The largest load (gas compressor)is fed from the pl ant common 4.16 kV swi tchgear. (6)Electrical protection equipment. Each combustion turbine generator package also includes an inlet air filtration system,fuel system,lUbricating oil cooling system,and various minor subsystems as required,furnished by the manufacturer: 2601B 2-6 [ rL. [ [ [ r [ r F [ [ rL [ C C [ [ r,--' [ L 6 [ The design parameters for each combustion turbine with generator are presented in Table 2-2.Inlet air preheating using a heat exchanger will also be necessary. 2.1.3 Fuel Supply Annual fuel requirements for power generation at the North Slope will be 6.5 BCFY (billion cubic feet per year)in 1993 and grow to 78 BCFY by 2010 for the medium growth forecast.Maximum potential firing rate for the medium load growth scenario will be 2.5 x 10 5 SCFM (standard cUbic feet per minute)in the year 2010. Fuel requirements on a year by year basis will vary with installed generating capacity and are shown in Taple 2-1.These gas demands were generated based on an average annualized unit heat rate of 11,500 Btu/kWh (HHV)for the simple cycle gas turbines at average ambient conditions •. The HHV of the fuel gas is assumed to be 1046 Btu/SCF (lower heating value [LHV]942 Btu/SCF).These values reflect the fact that no gas conditioning facilities will be required for the North Slope scenario. The gas supply system will consist of piping from one or more of the eXisting North Slope natural gas gathering centers,a pressure reduction station and an in-plant distribution system •.The supply and distribution system will be designed for maximum flexibility to operate any configuration of the available gas turbines.The pressure reduction system will be required to assure a constant gas supply pressure at 250 psig. 2.1.4 Substation The circuit diagra~of the power plant sUbstation is shown in Figure 2-3:Two generators will be connected to the two primary windings of the 250 MVA 13.8/138 kV transformers.The bus arrangement will use a breaker and a half scheme unless reliability considerations 2601B 2-7 TABLE 2-2 COMBUSTION TURBINE WITH GENERATOR DESIGN PARAMETERS NORTH SLOPE POWER GENERATION -MEDIU4 LOAD FORECAST Turbine Type:l/Simp1e-cyc1e,single-shaft,·three bearing. Generator Type:Hydrogen-coo1ed unit rated 130 MVA at 13.8 kV,with 30 psig hydrogen pressure at lOoC. (Each Turbine -at ISO Conditions)Performance: Heat Rate (LHV) Heat Rate (HHV) Air Flow Turbine EXhaust Temp Turbine Inlet Temp Inlet Pressure Drop EXhaust Pressure Drop Overall Dimensions 10,700 Btu/kWh 11,500 Btu/kWh 609 1bs/sec 995°F 1985°F 3.5 in.water 0.5 in.water 38 ft.wi de by 118 ft.long by 32 ft.high [ [ f [ [ r: [ o n L Combustion Turbine Features: Accessories include starting motor,motor control center for all base-mounted motors,lubrication system,hydraulic control system. EXcitation compartment complete with static excitation equipment. Switchgear compartment complete with generator breaker,potential and current transformers,disconnect link for auxiliary feeder,·and a power takeoff. Fuel system capable of utiliZing natural gas,mixed gas fuel,or liquid fuel. Fire protection system (low pressure C02). 1/Based on General Electric Model MS7001. 2601B 2-8 [ C C L C C L L L•..~od [ r-:.C'r'"1,rn O':""""'J ,.--r-l c--:"J C":"J CJ r-J en c-J i~,----..,~""(~r-l c-J CD l")J J l ; 200MVARII~ TYPICAL 1 'IOU'll lI-S 21Z5MVA I!IAICO .ERVICts 1NC000000ATED NORTH SLOPE POWER GENERATION MEDIUM LOAD FORECAST 8UB8TATION ONE LINE 8CHEMATIC ALASKA POWER AUTHORITY NORTH ILOPE GAS FEASlBlLfTY ITUDY TO FAIRBANkS 500kV 1.3.8 kV ex 2 22 2 2 ex 2 22 22 22 TO FAIRBANKS 250 MVA TYPICAL 75D MVA TYPICAL -I\./V'v-REACTOR ::k CAPACITOR LEGEND .0 GENERATOR ~OR~TRANSF'ORMERoC.IRCU/T BRfAKER N I U) mandate otherwise.Two 750 MVA 138/525 kV autotransformers will supply each of the transmission line circuits.Each of the transmission lines will have a circuit breaker.On the line side of the circuit breakers will be the series capacitors and the shunt reactor~.This arrangement has the advantage of being flexible as far as operation is concerned, and can be expanded easily.The system1s flexibility is demonstrated in Figure 2-4,which shows the initial development associated with the· installation of the first generator.There are seemingly more circuit breakers than necessary in this initial circuit;their purpose is to facilitate future expansion work. The grounding mat of the switchyard is connected to four insulated 1000 kCM1/cables which terminate in a grounding rod system driven into the sea floor.The ground mat is also connected to the two ·counterpoises 2/which run under the entire length o~the transmission line. 2.1.5 Power Plant Support System Descriptions The auxiliary systems described in this section represent generally the minimum necessary to operate a simple cycle combustion turbine facility.These systems include water supply,waste management,fire protection,electrical,and lUbricating oil sy~tems. Plant makeup water will be derived from an assumed existing lake of at least 150 acres to supply the needs of two water systems:a potable water system for the plant and the camp,and a service water system. The potable water system will be designed to supply water for the maximum crew on hand through completion of the final unit.Service water will be provided to all units for maintenance,construction uses 1/k04 stands for thousands of circular mils,a measure of the cross-secti on of a cab1 e. 2/Counterpoises are buried grounding cables,running under transmission lines,which are necessary in areas with poorly conducting soils. 26018 2-10 r~ L [ [ [ [ L [ [ l L L [ [ [ [ r [ [' r· 'L..~ cu 13.8 kV 9~ 13BkV 750MVA TYPICAL ~......500kV ,---~500 kV CAPACITOR [ [ [ C L [ L L [-.".. -u: L - 11""-'\1\1----1 200 MVAR TYPICAL LEGENDoGENERATOR ~ORtnY\TRANSFORMER D CIRCUIT BREAKER J\/\/'v-REACTOR ~ 2-11 ALASKA POWER AUTHORITY NORTH ILOPE GAS FEASlBlLrry STUDY NORTH SLOPE POWER GENERATION MEDIUM LOAD FORECAST INITIAL STAGE OF SUBSTATION DEVELOPMENT 'IGUftE 2-4 EBASCO SERvtCES ItCORPORATED and area cleaning.A water injection system should not be required for NOx control on the North Slope (see Section 2.4.1 for further explanation). Waste control systems for the plant will consist of control and processing through oil/water separation treatment of all floor drainage from operation and maintenance areas.This treated effluent and domestic wastes will be transported to an existing sanitary waste treatment facility.Because the natural gas supply is low in sulfur content,no sulfur dioxide (S02)emissions control will be required. Due to the climatic conditions existing during most of the year,fire protection will be ba~ed on standard halon systems rather than water systems.Automatic halon systems will be installed for high risk areas,and manual systems will be used for low risk areas.Also,each system sel ected shall be compati bl e with any of the specific hazards it is intended to combat. A system for storing ~oth clean and dirty lubricating oil shall be included.The system will include a central storage area and portable units capable of transporting,replacing,and/or cleaning the lUbricating oil in an operating gas turbine. 2.1.6 Construction and Site Services The construction and operation of a simple cycle power plant will require a number of related services to support all work activities at the site.These site services will include the following for the North Slope power plant: (1)Access (2)Construction Water Supply (3)Construction Transmission Lines (4)Construction Camp 2601B 2-12 [ [ [1 [ CL~~ [ [ L L [ c- [ [ [' r [ [ Fu o L [ E [ C [ [ l L E [ .Access Gravel roads with a 5 foot minimum gravel base will be required to connect the plant site with the existing road network at the North Slope.It is expected that no more than 2 miles of new road construction will be required. It is anticipated that all personnel travel wi.ll be by air with pre-arranged commercial charter carriers to Deadhorse Airport.All perishable goods,mail,and rush-cargo,will be flown in.Equipment for construction will be flown in only under extraordinary circ umstances. The site will use the existing marine landing facilities during the six week IIthaw ll period to receive all major equipment and suppl ies.A fenced interim storage area will be provided.The Dalton Highway (Haul Road)from Fairbanks will be utilized for smaller shipments to the site. Construction Water Supply A complete water supply,storage and distribution system will be installed.Due to the nature of the site,a heated and insulated one-million gallon water storage tank will be incorporated into the camp's design,with one-half of this storage capacity dedicated to fire protection needs.The water supply will be derived from an existing 1ake. Construction Transmission Lines Power requirements during the construction phase will be supplied by constructing a 69 kV transmission line tapped from the area1s existing transmission system. 26018 ?-,~ Construction camp Facilities A 200 (maximum)bed labor camp will be provided unless an existing camp can be utilized.All personnel housed in this camp will be on single status.Provisions will be made to accommodate a work fo~e of both men and women by providing separate facilities. The 200 bed camp will accommodate the maximum required workforce for those years when two turbines will need to be installed and started up at the same time.For other years,a workforce of 50 to 100 (maximum) is anticipated.This camp will also be used to house operating personnel. 2.1.7 Operation and Maintenance Plant Life Each gas turbine will have a 30 year life expectancy.It is expected that the gas turbine units will be overhauled in accordance with manufacturer's suggestions and good operating practice for the life of the units. Heat Rate of Units Unit heat rates for the plants will vary,depending on ambient conditions at the sites.It is common practice for gas turbine manufacturers to quote heat rates in terms of the lower heating value (LHV)of the fuel.However,since fuel is purchased based on higher heating values (HHV),HHV figures are used in,the balance of this report.The site specific HHV heat rate is 11,500 Btu/kWh.ISO conditions give a heat rate of 10,700 Btu/kWh (LHV)for base load operation. 2601B 2-14 r r~ "••_..i [ [ f' f [' [ n L [ [ [ C U [ [ l [ [ c [ [ L [ [ [ fiL c L [ E C t t [ [ b t [ Scheduled and Forced Outage Rate It is expected that the forced outage rate will be about 8 percent. Operational experience on other plants indicates higher forced outages in the first few years,but this is attributed to operational adjustments required for a new plant.It is expected that a slight increase in forced outages will occur as the plant ages. Scheduled outages will be an additional 7 percent based on two periods of regular semi-annual maintenance requiring shut down and one 5 week period every three years for overhaul. Operating Workforce The number of personnel required to operate a plant of this type can vary widely,depending on plant utilization and system operating practices.Based on Electrical Power Research Institute Operational Development Group study figures,and considering the severity of climate and operational failure,an on-duty operation and maintenance workforce of 10 persons will be required starting in 1993,when one unit is operating.This will grow as units are added until an on-duty force of approximately 50 persons will be required for the 15 units operating in 2010.Assuming a 12 hour shift and a 7-day-on,7-day-off work schedule,the total required workforce will vary from 40 to 200 personnel. 2.1.8 Site Opportunities and Constraints Climate is the single most important site characteristic affecting design at the North Slope.As previously mentioned,the 77 MW rating of the turbine is based on ISO conditions with an ambient temperature of 59°F.As the ambient temperature decreases,the capacity of these units increases.At O°F,the rated capacity of these units is 122 percent of the capacity at 59°F,or approximately 94 MW.The heat rate decreases as the temperature decreases,and at O°F is 97.5 percent of 2601B 2-1; that at 59°F,or approximately 11,600 Btu/kWh (HHV).Clearly a cold climate site such as the North Slope offers some operational performance advantages.This is especially true since the cold weather also produces the annual peak loads for the Railbelt area.The average annual temperature at the North Slope site is 9°F resulting in an average annual unit capacity and heat rate of 91 MW and 11,500 Btu/kWh (HHV),respectively. The remoteness of the site combined with the climatic conditions present the most significant problems to construction of this scenario.The short construction season and the cost of construction at the North Slope generally dictate that as much prefabrication as possible be performed prior to shipping units to the site.In addition the arrival of shipments via barge will be delayed until mid-summer when the Arctic coast becomes free of ice.This further shortens the construction season for shipped materials and may require storage over winter for completion of construction the following summer. 2.2 TRANSMISSION SYSTEM 2.2.1 Overview of the System For reasons of reliability,two parallel circuits have been considered.The design criteria used in the study are presented in Table 2-3.Additional details regarding system design and alternatives are presented in Appendix D.The 450-mile length of the proposed transmission system between the North Slope and Fairbanks will be interrupted by two intermediate switching stations,one at Galbraith Lake and one at Prospect Camp;this will establish three almost exactly equal 150-mile-long segments. The two circuits will originate in the Prudhoe Bay/Deadhorse area of the North Slope.Each circuit will be supplied by two 750 MVA transformers,protected by one circuit breaker and compensated with a series.capacitor bank and shunt reactor.The two circuits will be 26018 2-16 [ [ [ [ [~ [' [' [ r L [ [ D C t [ E [ U [ 2-17 2601B TABLE 2-3 TRANSMISSION LINE DESIGN CRITERIA NORTH SLOPE POWER GENERATION -MEDIUM LOAD FORECAST maximum 18 kV per centimeter 1.5"radial thickness with 8 lbs/sq.ft.wind load at 32°F 25 1 bs per sq.ft above the Arctic Circle and 8 lbs/sq.ft.below it;2.3 lbs/sq.ft.at +86°F 36"north of the Arcti c Ci rcl e and 24"south of it minimum 38 feet with snow on the ground maximum 50%of rated tensile strength Ice on conductor: Tension in conductors: Temperature range: Wi nd loads:..!.! Clearance to ground: Snow on ground: Gradient on conductor surface:~/ l/25.0 lbs per square foot corresponds to 100 mph wind 8.0 lbs per square foot corresponds to 55 mph wind 2.5 lbs per square foot corresponds to 30 mph wind ~/To reduce corona losses and mitigate radio and television interference nL [ [ C C C [ [ [~ [J [ [ r- L [ [ [ [ [ located on opposite sides of the road for the first 60 miles,to Pump Station 2.South of the 60 mile mark,the line may not necessarily be located on the two sides of the road. The first switching station will be at Galbraith Lake approximately 150 miles south of Prudhoe Bay.Immediately south of the switching station is a 30-mi1e portion of the route where the suitable terrain narrows, possibly requiring the two circuits to be placed on single towers.In the Atigun Pass area the slopes of the mountainside are not overly rugged and the two circuits could be constructed a few hundred feet up the slopes from the roadway.The Atigun Pass section is about 5 miles long and reaches an elevation of approximately 5,000 feet,the highest point of the transmission system. The second switching station will be located at Prospect Camp.It will be identical to the one at Galbraith Lake.The line will cross the Yukon River near the Yukon River Bridge,and will terminate in the Fairbanks area. 2.2.2 Voltage Selection Three voltage levels were investigated in detail:500 kV AC,765 kV AC, and ~350 kV DC '(see Appendix D).Each of these are capable of transmitting the required power from the 'North,Slope to Fairbanks.A comparative cost study has been made using the methodology and cost figures supplied by Commonwealth Associates (1978).The study indicated that all three versions are within +10%as far as capital investment is concerned,which is within the expected range of accuracy of these types of calculations.Therefore,all three can be considered to be equal with respect to capital cost.The 500 kV alternative was chosen for detailed cost estimating because this version represents the most conventional approach and would likely have the best reliability. 2601B 2-18 c [ [ [ [' [ [ c r L [ [ [ [ L " ---: L [ L [J [ [ [ [ [ [ [ [ L c U [ [ C C t [ E L [j [ 2.2.3 Towers Tubular steel H-frame towers will be utilized for the line;their average height will be 90 feet and the average span will be 1000 feet. There will be one dead end tower at approximately every 10 miles,or in other terms 2%of the towers will be dead end.l / Special consideration has been given to the crossing of the Yukon River,about 1000 feet downstream from the highway bridge.The required span will be approximately 3000 feet.At the selected location the right (north)bank of the river is a flat,low floodplain, but an approximately 300-foothill rises at the left (south)bank making the design of the crossing easier.The span will be between two lattice type dead end towers,one approximately 120 feet tall at the north shore and the other approximately 100 feet tall on the top of the hi 11 at the south end of the span.Thi s arrangement shoul d pose no greater hazard to waterborne traffic than does the bridge. 2.2.4 Conductors Bundled conductors will be used for the 1 ine with two conductors per bundle at 18 inches apart.Except for the Yukon River crossing,Chukar conductor,a 1780 kCM ACSR~/conductor wi th a rated strength of 51,000 lbs and an outside diameter of 1.6 inches,should be used.With a 1000-foot average span,the maximum sag will be 42 feet,Which,with a 95 foot tall tower,will provide adequate clearance to ground.In satisfying all appropriate design criteria,the conductors will be oversized with respect to current carrying capacity,consequently,one circuit will be capable of carrying almost twice the required medium forecast power.The line will be provided with spacer dampers. 11 A dead end tower is capable of withstanding a conductor break, preventing structural failure of the transmission system from proceeding beyond a dead end tower. 2/ACSR -aluminum conductor,steel reinforced. 2601B 2-19 For the Yukon River crossing a special conductor with an ultimate strength of 235,500 1bs may have to be ordered,such as 61x5 strand A1umoweld from the Copperwe1d Company.With the recommended towers, minimum clearance to high water will be 70 feet during the summer and 45 feet in the winter.Construction of the span will be done during the winter months when ice cover permits working over the river bed. Special vibration studies must precede actual design and vibration recording instruments must be installed after erection. 2.2.5 Insulators Suspension insulators,such as type 5-3/4"x 10"x 50 K 1b,will be used.Two strings in a V configurati on will ho1 d the conductor bundle.Normally,25 insulators are in each string •. For the first 60 miles from Prudhoe Bay fog type insulators will be installed and the number of insulators in the strings will be increased by two over that provided for the remainder of the route.Also,fixed insulator washing installations will be provided at each tower,based on the experience that Sohio has operating 69 kV lines at the North Slope.A tank truck equipped with pumps,hoses and other equipment will perform the annual washing in the fall. 2.2.6 Switching Stations The two switching stations at Galbraith Lake and at Prospect Camp will divide each of the line circuits into three,almost equal,150 mile long segments.The circuit schematic can be seen in Figure 2-5.The arrangement is conventional.The intermediate switching stations will make it possible to switch a shorter segment out of the system in case of a fault of a circuit,instead of the entire line length;this will improve the stability,hence the reliability,of the power system. 2601B 2-20 n L [ [ [ [ [ [~.~ [ [ .r: ~;c L sOOI<V ALASKA POWER AUTHORITY NORTH ILOPE GAS FEAStBILfTY STUDY FIQUflE 2-6 E8ASCO SERVICES ICORPORATED NORTH SLOPE POWER GENERATION MEDIUM LOAD FORECAST TYPICAL TWO LINE SWITCHING STATION SCHEMA TIC CAPACITOR CIRCUIT BREAKER TO PRUDHOE BAY SOOKV TO -PROSPECT CAMP II LEGENDoGENERATOR ~OR~TRANSFORM£R o -I\/\/\r REACTOR ~ c L [ C C C [j [ [ 6 C C [ ~- [ [ [ [ [ [j 2.2.7 Fairbanks Substation The Fairbanks substation one line schematic is shown in Figure 2-6. Two 500 kV line.circuits,originating at Prudhoe Bay,will be connected to the substation,through either one 1500 MVA or two 750 MVA 345/525 kV transformers.Three 345 kV circuits will leave the substation'in the direction of Anchorage.Two transformers will provide power for local area loads.The bus will be at 345 kV.The schematic shows two static VAR compensators connected to the bus through dedicated transformers.These static compensators will not necessarily be located where shown in Figure 2-6;their connections to the system are described in detail in Appendix D.The circuitry will use breaker and a half .or double breaker arrangements.The substation will be designed so that the loss of one line,transformer,circuit breaker or compensator allows uninterrupted operatio~at full power. 2.2.8 Construction Five camps will be used to house the work force;each camp will serve about a 90-mile section of the line for most of the construction period.The number of people will vary between 41 and 155 per camp, including the camp crew.The one exception is the period of building the gravel pads,when a total of 2400 people will have to be housed during the first summer of construction,which may require the opening of additional camps. A 100'X 100'gravel pad must be constructed to serve as the base of each tower,and every 18 miles 300'x 1200'pads will serve as marshalling yards.Fifteen crews,with the aid of helicopters,can erect the towers during a six month work period.The last operation will be the stringing,which can be done by 5 crews,each with helicopter assistance.The switchyards will be constructed during the time that the line is stringed. 2601B 2-22 c [ [~ [ [ [: [ c p L [ [ o [ C L [ C L L ,-, l J l:--l CT·"'"] TO PRUDHOE BAY i cOO MVAR II......,Jv\-~ TYPICAL 500 kV II TO ANCHORAGE itASCa RRvtCESINCORPOAATED ALASKA POWER AUTHORITY NOATH eLOPE GAS FEASlBlLfTY STUDY NORTH SLOPE POWER GENERATION MEDIUM LOAD FORECAST FAIRBANKS SUBSTATION SCHI!MATIC ..:5TATIC VAR COMPEN611TOR T38 LOCAL I--JIIII ......." TTr8kV LOCAL T LEGENDoGENERATOR =oa",""TRANSF"ORMERoCIRCUITBREAKER .JV\/\,-REACTOR i-,.,....CAPACITOR Pad building will take place in one summer using two 10-hour shifts. All other operations,except for surveying,will each take six months to perform and will be scheduled for fall and spring when the soil is frozen,but when enough day1 i ght is avail ab1 e to work at 1east one a-hour shift. 2.2.9 Operation and Maintenance The least reliable equipment will be the series capacitors.The cost of a series compensated 500 kV line is about the same as that of an uncompensated 765 kV line.The 765 kV alternative should be investigated in more detail during detailed design of the line.The trade-offs of not having series capacitors are wider rights-of-way, increased problems due to contamination near Prudhoe 8ay and i~creased difficulties to construct the two circ'uits through Atigun Pass." 2.2.10 Communications To provide adequate communications,a microwave system will be installed.The North Slope-Fairbanks line will require 16 repeater stations.Five channels will be required,at least,one for supervisory voice communication,one for data transmission,one for relaying,one for service communication (below 4 kHz)and for alarm (above 4kHz),and one spare channel.Each repeater station will have a radio transceiver to maintain voice communication between vehicles and the dispatcher,using the service voice channel. In addition,each transmission line circuit segment will be provided with a line carrier,mainly to provide redundancy for vital transfer tri p functi ons. Though this project assumed a dedicated microwave system,t~e project proponent may consider leasing microwave channels from ALASCOM. Several options,including direct satellite link,may be cost effective. 26018 2-24 n n l~ [ f' [ [ [ c L [ [ [ [ [ f' [ , -~ [ L L e- n [ [ [ [ [ c [ [ [ C C [ L C ~ [ 2.2.11 Siting Opportunities and Constraints An inspection of the route indicated that most of the route should not cause significant construction problems.However,three areas are of some concern.The first 60 miles of the line south from the North Slope is a tundra area;civil engineering design and construction methods will have to be carefully investigated.Second,the grounding problems posed by frozen soil require that a bare copper conductor, called a counterpoise,be buried under each circuit along the entire length of the transmission line and be connected to the ground mats of all the substations and SWitching stations.Third,crossing Atigun Pass,as mentioned earlier,will require careful design;here the counterpoises may have to be routed farther from the circuits or be .carr.i ed on the towers. 2.2.12 Fairbanks to Anchorage Line System studies perfonned by Ebasco (see Appendix D)indicate that 345 kV is a suitable voltage for this transmission line.This voltage is compatible with the 345 kV Intertie under construction.Therefore, two new 345 kV lines will be built and the Intertie will be extended fully between Fairbanks and Anchorage. At the time of writing this report,the detailed design of the Intertie is available.Based on this information,the designs of the Intertie extension and the two new lines are assumed to be the same as the Commonwealth Associates (1981)design.The only additions will be the intermediate switching station,shown in Figure 2-7,the series capacitors and the shunt reactors. 2.2.13 Anchorage Substation The Anchorage substation will be the termination of the three 345 kV line circuits.The substation bus will be 138 kV,as can be seen in Figure 2-8.All other details will be similar to that described for the Fairbanks substation (Section 2.2.7). 2601B 2-25 [ [ l~ [ [' [ [ [ L [ [; C C E [ [ L l [ 345KV ALASKA POWER AUTHORITY NORTH SLOPE GAS FEASIBILITY STUDY EBASCO SERVICES NCORPOAA TED 'tGURE 2-7 II II NORTH SLOPE POWER GENERATION MEDIUM LOAD FORECAST TYPICAL THREE LINE .....SWITCiilNG STATION SCHEMA TIC ANCHORAGE f~IRBANKS TO II 345KV CAPACITOR II II LEGENDoGENERATOR ~oRrnon TRANSFORMER D C.IRCUIT BREAKER TO r-J c::r:n rr:-:;c-;)~.~c:-1 c=J r=l C"J c-:n C.1.J rJ r---;l II II !----"'J crJ [L]l , TO FAIRBANK:5 ~45kvl 1 600 MVA TYPICAL l~c·H LOCAL -~TATIC VAR COMPEN6ATOR ALAIKA 'OWER AUT'HORITY IIOATH aLOftE GAS PlAS.IUTY .TUDY NORTH SLOPE POWER GENERATION MEDIUM LOAD FORECAST ANCHORAGE SUBSTATION SCHEMATIC ...lIM '-I 2.3 COST ESTIMATES 2.3.1 Construction Costs 2.3.1.1 Power Plant To support the derivation of total systems costs which are presented in. Section 2.3.4,feasibility level investment costs were developed for the major bid line items common to a 77 MW (ISO conditions)natural gas fired simple cycle combustion turbine and a 220 MW (ISO conditions) natural gas fired combined cycle plant.These costs are presented in Tables 2-4 and 2-5.The costs represent the total investment for the first unit to be developed at the site.Additional simple cycle units will have an estimated investment cost of $53,560,000 while additional combined cycle units will have an estimated investment cost of $218,820,000.The cost differential for additional units is due to significant reductions in line items 1 and 15,improvements to Site and Off-Site Facilities,and reductions in Indirect Construction Cost and Engineering and Construction Management. For the North Slope power generation scenario only simple cycle unit costs have been used in the total system cost analysis (Section 2.3.4).Combined cycle costs were developed to support the cost sensitivity analysis performed in conjunction with the system planning studies (Appendix B). 2.3.1.2 North Slope to FairDanks Transmission Line Transmission line feasibility level investment cost estimates for the North Slope to Fairbanks connection are presented in Table 2-6.These estimates are based on two 500 kV lines of 1400 MW capacity with series compensation,and two intermediate switching stations. 2601B 2-28 [ C L~ [ [ ~ I [ [ n L [ C D C [ [~ [ [ [ Construction Total Descri pti orl!./ Material Labor Di rect Cost ($1000)($1000) ($1000) l.Improvements to Site 385 4,800 5,185 2.Ea rthwork a nd Pi 1i ng 605 1,710 2,315 3.Circulating Water System 0 0 0 4.Concrete 25 450 475 5.Structural Steel Lifting Equipment,Stacks 675 1,230 1,905 6.Buildings 4,625 1,710 6,335 7.Turbine Generator 11 ,200 2,700 13,900 8.Steam Generator and Accessories 0 0 0 9.Other Mechanical Equipment 460 ·985 1,445 10.Pipi ng 200 2,100 2,300 11.Insulation and Lagging 30 450 480 12.Instrumentation 100 300 400 13.Electrical Equipment 1,500 10,800 12,300 14.Painting 5 90 95 15.Off-Site Faci1itiesf!500 9,000 9,500 SUBTOTAL $20,310 $36,325 $56,635 Freight Increment 1,015 TOTAL DIRECT CONSTRUCTION COST $57,650 Indirect Construction Cost 3,505 SUBTOTAL FOR CONTINGENCIES 61,155 Co nti ngenc i es (15%)9,175 TOTAL SPECIFIC CONSTRUCTION COST 70,330 Engineering and Construction 2,300 Management TOTAL CONSTRUCTION COST $72,630 2601B nL cl~ [ [ C C [ L L [ U L l/ 2/ TABLE 2-4 FEASIBILITY LEVEL INVESTMENT COSTS 77 MW SIMPLE CYCLE COMBUSTION TURBINE NORTH SLOPE POWER GENERATION -MEDIUM LOAD FORECAST (January,1982 Dollars) The following items are not addressed in the plant investment pricing: laboratory equipment,switchYard and transmission facilities,spare parts,land or land rights,and sales/use taxes. Costs for construction camp and construction workforce travel included in Construction Labor category. 2-29 TABLE 2-5 FEASIBILITY LEVEL INVESTMENT COSTS 220 MW COMBINED CYCLE PLANT NORTH SLOPE POWER GENERATION -MEDIUM LOAD·FORECAST .(January,1982 Do 11 ars). Construction Total Descri pti onl.! Materi a1 Labor Di rect Cost ($1000 )($1000)($1000) l.Improvements to Site 385 4,800 5,185 2.Earthwork and Piling 1,860 5,460 7,320 3.Circulating Water System 0 0 0 4.Concrete 100 2,160 2,260 5.Structural Steel Lifting Equipment,Stacks 900 2,400 3,300 6.Buildings 12,575 4,560 17,135 7.Turbine Generator 30,300 10,500 40,800 8.Steam Generator and Accessories 9,600 18,000 27,600 9.Other Mechanical Equipment 5,625 11 ,705 17,330 10.Pipi ng 1,470 12,000 13,470 11.Insulation and Lagging 290 2,880 3,170 12.Instrumentation 1,700 1,200 2,900 13.Electrical Equipment 4,500 36,000 40,500 14.Painting 25 360 385 15.Off-Site Facilities2/500 9,000 9,500 SUBTOTAL $69,830 $121,025 $190,855 Frei ght Increment 3,490 TOTAL DIRECT CONSTRUCTION COST $194,345 Indirect Construction Cost 8,760 SUBTOTAL FOR CONTINGENCIES 203,105 Contingencies (15%)30,465 TOTAL SPECIFIC CONSTRUCTION COST 233,570 Engineering and Construction 7,000 Management TOTAL CONSTRUCTION COST $240,570 1/The following items are not addressed in the plant investment pricing: laboratory equipment,switcnyard and transmission facilities,spare parts,land or land rights,and sales/use taxes. 2/Costs for construction camp and construction workforce travel lncluded in Construction Labor category. 2601B 2-30 ['I [ [ [' f' nu Construction ?:/Total Materi al Labor Direct Cost De sc ri pti onl/($1000)($1000)($1000) Switching Stations 33,335 26,100 59,435 Substations 58,655 44,941 103,596 Energy Management System 12,900 12,000 24,900 Steel Towers and Fixtures 822,212 873,012 1,695,224 Conductors and Devices 63,962 149,760 213,722 Cl eari ng 0 85,200 85,200 SUBTOTAL $991,064 $1,191 ,013 $2,182,077 Land and Land RightSY 36,000 Engineering and Construction Management 152,750 TOTAL CONSTRUCTION COST $2,370,827 Construction camp facilities and services are included in the Construction Labor cost category. The investment costs reflect two 500 kV lines,1400 MW capacity with series compensation and two intermediate switching stations.A 15 percent contingency has been assumed for the entire project and has been distributed among each of the cost categories shown.Sales/use taxes have not been included. l [ r--:' r [ [ [' E C L [ [j [ C L C L L ~ [ 1/ 2/ 2601B TABLE 2-6 FEASIBILITY LEVEL INVESTMENT COSTS NORTH SLOPE TO FAIRBANKS TRANSMISSION SYSTEM NORTH SLOPE POWER GENERATION -MEDIUM LOAD FORECAST (January,1982 Dollars) Assumes a cost'of $40,000 per mile (Acres American Inc.1981). 2-31 2.3.1.3 Fairbanks to Anchorage Transmission Line Transmission line feasibility level investment cost estimates for the Fairbanks to Anchorage connection are presented in Table 2-7.These estimates are based on two new 345 kV lines,with shunt and series compen.sation aryd ·an intermediate switching station.The investment cost estimates also reflect upgrading from 138 kV to 345 kV of the Willow-Anchorage and Healy-Fairbanks segments of the eXisting grid. 2.3.2 Operation and Maintenance Costs 2.3.2.1 Power Plant The power plant operation and maintenance (O&M)costs were derived to support the system planning studies (Appendix B).They reflect a review of figures from previous Rai1be1t studies,operation of other" utilities,and salary requirements and expendable materials.The O&M costs for this scenario are estimated to be $0.0063 per ki1lowatt hour (6.3 mils/kWh). 2.3.2.2 Transmission Line Systems Annual operation and maintenance costs (January,1982 dollars)have been developed for the scenario's required transmission line facilities and total $35 million per year.These costs should be viewed as an annual average over the life of the system.Actual O&M costs should be less initially,and increase with time. 2.3.3 Fuel Costs For the economic analyses which follow fuel costs were treated as zero.This approach permits fuel cost and fuel price escalation to be treated separately;~nd makes possible SUbsequent sensitivity·analyses of the Present Worth of Costs for this scenario based upon a range of fuel cost and cost escalation assumptions. 2601B 2-32 L [ [ [ ro, [ l r: L [ [ C C C [ [ [ '-~[i [ [ f.'t--~=, [ [ [ [ [ o [ l: [ G C· C f](j [ C [ L [ TABLE 2-7 FEASIBILITY LEVEL INVESlMENT COSTS FAIRBANKS TO ANCHORAGE TRANSMISSION SYSTEM NORTH SLOPE POWER GENERATION -MEDIUM LOAD FORECAST (January,1982 Dollars) Constructi on Total Descri pti on.!! Material Labor Direct Cost ($1000)($1000)($1000) Switching Station 14,112 12,445 26,557 Substations 62,308 41 ,716 104,024 Energy Management Systems 12,300 10,960 23,260 Steel Towers and Fixtures 216,495 305,085 521,580 Conductors and Devices .33,678 78,361 112,039 C1 earing 0 83,144 83,144 SUBTOTAL $338,893 $531 ,711 $870,604 Land and Land Rights 2/0 0 27,600 Engineering and Construction 60,950 Management TOTAL CONSTRUCTION COST $959,154 .l!The investment costs reflect two new 345 kV lines,1400 MW capacity with shunt and seri es compensati on and an i ntermedi ate swi tchi ng stati on,and upgrading of the WillOW-Anchorage and Healy-Fairbanks segments of the eXistin~grid to 345 kV. 2/Assumes a cost of $40,000 per mile (Acres American Inc.1981). 2601B 2-33 2.3.4 Total Systems Costs The total system for the North Slope scenario,medium load forecast, consists of simple cycle gas turbines and an extensive transmission line system.No gas conditioning facili-ties or pipeline are. reqUired.Total annual systems costs reflect the relative simplicity of thi s system. The methodology and assumptions utilized to derive the systems'costs which are presented below have been previously described in the Report on Systems Planning Studies (Appendix B).This methodology is consistent with previous studies of electric generating scenarios for the Rai1be1t,specifically Acres American,Inc.(1981),Susitna Hydroelectric ProJect Feasibi"lity Report and Battelle (1982);Railbelt Electric Power Alternatives Study.The period of the analysis was assumed to be 1982 through 201 O. Annual capital costs for the system are presented in Table 2-8. Annual non-fuel operation and maintenance (O&M)costs are presented in Table 2-9.Total annual systems costs are then summarized in Table 2-10. For scenario comparisons,the present worth of total annual costs for the North Slope medium load f~recast has been.calculated.Assuming a 3 percent discount rate and excluding fuel costs,the 1982 present worth of costs is $3.7 billion.The values are in 1982 dollars. 2.4.ENVIRONMENTAL AND SOCIOECONOMIC CONSIDERATIONS Development of a gas fired simple cycle combustion turbine facility at the North Slope and transmission facilities to bring the energy to the Rai1be1t region will engender a variety of significant environmental effects.Precise quantification of environmental impacts will require more detailed site-specific analysis.However,most major potential 2601B 2-34 [' L [ [ C [] L [ L L [ [ [ [ r [~ [: L C cu [ [ C C C C C L 6 TABLE 2-8 TOTAL ANNUAL CAPITAL EXPENDITURES NORTH SLOPE POWER GENERATION -MEDIUM LOAD1/FORECAST (Millions of Januar,y,1982 Dollars)_ Calendar Electricity Generation 2/Transmi ssi on Ye.ar Unit A Uni t B Line Total 1982 O.O.O.O. 1983 O.O.O.O. 1984 O.O.O.O. 1985 O.O.O.O. 1986 O.O.O.O. 1987 O.O.O.O. 1988 O.O.O.O. 1989 .O.O.1,803.30 1,803.3.1990 O.O.418.45 418.5 1991 19.07 3/O.823.50 842.6 1992 53.56 O.3'34.76 388.3 1993 O.O.O.O. 1994 53.56 O.O.53.6 1995 53.56 O.O.53.6 1996 53.56 O.O.53.6 1997 53.56 O.O.53.6 1998 O.O.O.O. 1999 53.56 O.O.53.6 2000 O.o.O.o. 2001 53.56 53.56 O.107.1 2002 o.o.o.O. 2003 53.56 O.O.53.6 2004 53.56 53.56 O.107.1 2005 53.56 O.o.53.6 2006 53.56 O.o.53.6 2007 53.56 O.o.53.6 2008 O.O.O.O. 2009 53.56 O.O.53.6 201 0 O.O.O.o. Total $715.$107.$3,380.$4,202. 1/Values as calculated are shown for purposes of reproducibility only,and should not be taken to imply the indicated accuracy of significant figures.. ~/Unit A refers to first unit built in a given year and Unit B to the second unit built. ~/Construction of campsite and site preparation for all units. 2601B 2-35 TABLE 2-9 TOTAL ANNUAL NON-FUEL O&M COSTS NORTH SLOPE POWER GENERATION -MEDIUM LOAD FORECAST (Millions of January,1982 Dollars) Calendar Electricity Transmission Year Generation System Total 1982 O.o.O. 1983 O.O.O. 1984 O.O.O. 1985 O.O.O. 1986 O.O.O. 1987 O.O.o. 1988 O.O.O. 1989 o.O.O. 1990 O.O.O. 1991 O.O.O. 1992 O.O.o. 1993 3.767 35.0 38.8 1994 3.767 35.0 38.8 1995 7.535 35.0 42.5 1996 11.334 35.0 46.3 1997 15.063 35.0 50.1 1998 18.831 35.0 53.8 1999 18.831 35.0 53.8 2000 22.661 35.0 57.7 2001 22.598 35.0 57.6 2002 30.133 35.0 65.1 2003 30.133 35.0 65.1 2004 33.995 35.0 69.0 2005 36.414 35.0 71.4 2006 38.134 35.0 73.1 2007 39.848 35.0 74.8 2008 41.567 35.0 76.6 2009 43.281 35.0 78.3 2010 45.001 35.0 80.0 Total $463.$630.$1,093. 2601B 2-36. r' [ r L [ [ [ [: [ [ [ L b [, c [ [ [. [ [ [ c [ L; [ [j C C·e .... - 3 C C [ L 6· [ TABLE 2-10 TOTAL ANNUAL SYSTEMS COST NORTH SLOPE POWER GENERATION -MEDIUM LOAD FORECAST (Millions of January,1982 Dollars) Calendar Capital o &M Total Year Expenditures Costs Expenditures 1983 O.O.O. 1984 O.O.O. 1985 O.O.O. 1986 O.O.O. 1987 O.O.O. 1988 O.O.O. 1989 1,803.3 O.1,803.3 1990 418.5 O.418.5 1991 842.6 O.842.6 .1992 388.3 O.388.3 1993 O.38.8 38.8· 1994 53.6 38.8 92.4 1995 53.6 42.5 96.1 1996 53.6 46.3 99.9 1997 53.b 50.1 103:7 1998 O.53.8 53.8 1999 53.6 53.8 107.4 2000 O.57.7 57.7 2001 107.1 57.6 164.7 2002 o.65.1 65.1 2003 53.6 65.1 118.7 . 2004 107~1 69.0 176.1 2005 53.6 71..4 125.0 2006 53.6 73.1 126.7 2007 53.6 74.8 128.4 2008 O.76.6 76.6 2009 53.6 78.3 131.9 2010 O.80.0 80.0 Total $4,202.$1,093.$5,295. Present Worth @ 3%$3,156.$600.$3,757. 2601B 2-37 environmental concerns related to this scenario have been identified, and may be categorized as follows: (l)Ai r Resource Effects (2)Water Resource Effects (3)Aquatic Ecosystem Effects (4)Terrestrial Ecosystem Effects (5)Socioeconomic Effects Each of these subject areas is discussed in the following subsections. Power plant characteristics related to each of these subject areas is summarized in Table 2-11. 2.4".1 Air Resource Effects Development of the North Slope generating facility may be governed in large part by air quality considerations.The federal Clean Air Act and the Alaska rules for air quality control require the generating facility to meet both atmospheric emission and ambient air quality standards.Emission standards are defined in terms of New Source Performance Standards (NSPS)and Best Available Control Technology (BACT).NSPS apply generically to combustion turbines,and set a ceiling of emission levels that cannot be exceeded.Because gas fired power plants are relatively clean,NSPS levels do not pose a constraint to the development of this generating facility.BACT requirements are determined on a case-by-case basis,taking into account energy, environmental,and economic impacts,but are never less stringent than NSPS. The Prevention of Significant Deterioration (PSD)program protects relatively clean areas from undergoing substantial degradation through ambient air quality standards.The PSD increments for particulate and sulfur dioxide have not been exhausted on the North Slope,and 2601B 2-38 L [ [ [ L [= [ [ r L [ C C o C [ [ [ L [ Ai r En vi ronment TABLE 2-11 ENVIRONMENT RELATED FACILITY CHARACTERISTICS SIMPLE CYCLE COMBUSTION TURBINES NORTH SLOPE POWER GENERATION -MEDIUM LOAD FORECAST n [ [ [ [ [ [ [ n LJ [ C C C fJf:j C C L r~.LJ [ Emissions Particulate Matter Sulfur Dioxide Nitrogen Oxides PhYsical Effects Water Environment Plant Water Requirements Plant Discharge Quantity, Including Sanitary Waste and Floor Drains La nd En vi ronment Land Requirements Plant and Switchyard Construction Camp Socioeconomic Environment Construction Workforce Operating Workforce 2601B Below standards Below standards Emissions variable within standards - dry control techniques would be used to meet calculated NO~standard of 0.014 percent of total volume of gaseous emissions •.This value calculated based upon new source performance standards,facility heat rate,and unit size. Maximum structure height of 50 feet 50 Ga 11 ons per Mi nute (GPM) Less than 50 GPM 90 acres 5 acres Approximately 200 personnel at peak construction (power plant only) Approximately 200 personnel employed in the year 2010 (power plant only) 2-39 therefore do not constrain development.PSD increments for nitrogen oxides,the major pollutant from combustion turbines,have not been established.However,general PSD requirements dictate that Best Available Control Technology be used to reduce nitrogen emission levels. .. In the case of combustion turbines,BACT usually consists of using water or steam injection techniques to control emission levels by reducing combustion temperatures.Unfortunately,water or steam injection in the Prudhoe Bay area causes undesirable levels of ice fog.Furthermore,water or steam injection requires fresh water supplies that are generally not economically available on the North Slope.For these reasons,ai r qual ity regu1 atory agenci es have not defined BACT for the North Slope to include using water or steam injection to control nitrogen oxides.Im~osition of the requirement for water or steam injection would add substantial costs and· significantly decrease the relative feasibility of this scenario.For the purposes of this study it is assumed that water injection for NO x control would not be required. Even with no water injection requirement,air quality regulations would not be likely to hamper installation of a gas fired power plant in the Prudhoe Bay area.However,a jUdicious siting effort would still be necessary to avoid compounding any air pollution problems from existing facilities. The construction of two 500 kV transmission lines between the North Slope and Fairbanks would result in temporary air quality impacts.The use of heavy equipment and other construction vehicles would generate fugutive dust and exhaust emissions.Slash burning of material to clear the right-of-way would produce emissions.The impacts from these construction-related activities are expected to be small because the emi ssi ons wou1 d be wi de1:y.di spersed and occur in unpopul ated or sparsely populated areas. 2601 B 2-40 r [ [ r~ [ [: r [ cc [ [ [ [, 6 [ [ L L [ L [ [ [ [ [ [ PL~ nL: The long term impacts from operation of the transmission lines are expected to be negligible.The transmission lines would generate small amounts of ozone which would be undetectable at ground levels and would not cause problems with nearby vegetation. The air quality impacts of constructing the transmission lines from Fairbanks to Anchorage would result from activities similar to those mentioned above.The impacts are expected to be of approximately the same magnitude t although the amount of slash material to be burned would be greater within this corridor and would be within proximity to more populated areas. The long term impacts from transmission line operations would be similar to those of the Prudhoe Bay-Fairbanks transmission line cor.ri dora 2.4.2 Water Resource Effects The principal effects of the proposed generating facility on the water resources of the Prudhoe Bay area include consumptive withdrawals from freshwater sources (existing lakes)for potable supplies and miscellaneous uses such as equipment wash-down.Because the generating station will require minor volumes of water and will be served by existing waste treatm~nt facilities in the area t water resources effects associated with these uses will not be significant. For the medium load forecast t the site must have access to approximately 50 gpm.This water will be taken from a nearby freshwater lake of sufficient size so that the lake level and ~drologic balance is not significantly affected. Transmission line construction between the North Slope and Fairbanks may impact the quality of surface water resources through erosion caused by landdisturbance t but has little or no impact on water supplies.Erosion control t especially in steep terrain or areas of 2601B 2-41 susceptible soils,will be a major requirement imposed by permits issued for right-of-way clearing and construction of the transmission and related facilities,such as access roads.For example,the Bureau of Land Management (BUM)land use plan for the Prudhoe Bay-Fairbanks Utility Corridor (BUM 1980)within which the transmission facilities would be routed,specifically requires protection of stream banks and lake shores by restricting activities to prevent loss of riparian vegetati on. Construction activities of the transmission lines between Fairbanks and Anchorage would result in temporary impacts.The transmission lines would cross several large rivers and numerous creeks,resulting in temporary stream siltation,bank erosion,and the potential for accidental spillage of lubricating oils and o~her chemicals into the watercourses.Construction equipment working along streambanks or crossing smaller streams could cause direct siltation of the watercourse or cause indirect stream bank erosion and siltation through the removal of vegetation and disturbance of permafrost.The effects of siltation could alter stream channels,fill ponds,or damage aquatic flora or fauna. Significant effects on watercourses may be prevented by keeping •,.0 • construction activities out of channels and away from stream b~nks. Measures that could be taken to avoid impacts include a set back of 200 feet from watercourses for transmission structures as well as establishment of a buffer strip along major watercourses to minimize disturbance of vegetation and soils by construction equipment.In cases where watercourses must be crossed by construction equipment, such crossings could be conducted either during cold periods when the stream is frozen or in a manner to limit pollution or siltation.The use of helicopters to erect the towers will help to minimize overall construction impacts,since ground access requirements will be minimized. 2601B 2-42 c" r~ l [' [ [ f' [~ [ C L [. [ [ [ [ [ [ u [; L [ C C C GLJ [ C L ['~.' .' [ 2.4.3 Aquatic Ecosystem Effects The major aquatic ecosystems of the North Slope area include the marine environment of the Beaufort Sea,the freshwater environments of the Sag and Put Rivers and their tributaries,and estuarine habitats at the rivers'mouths.Shallow lakes in the area do not support fish because of complete freezing in the wintertime.Deeper lakes may contain resident species such as stickleback,but in general,knowledge of these lakes is presently limited.In the rivers and estuaries,two groups of fish are considered important:river fish such as the grayling,and anadromous fish such as the the Arctic char and cisco. The anadromous species descend local rivers at ice-breakup to feed in the shallow littoral and sublittoral zone of the Beaufort Sea.They ascend these rivers in the autumn and overwinter in deep pools.These fishod~not appear to undertake extensive migrations up the Sag or Put Rivers. These fishery resources could be affected by construction and operation of a water supply intake,pipeline and access road construction,gravel mining in rivers which could affect overwintering and general habitat quality of the fish,and the need to cross larger river channels which could interfere with fish passage.The latter item may require the use of speci a]ocu1 verts to mai ntai n mi gratory routes.Each of these potential effects would be analyzed on a site-specific basis,and detailed impact avoidance or mitigation measures developed •. Aquatic ecosystems within the transmission line corridor will also require protection during project construction.Between the North Slope and Fairbanks,the transmission lines may cross as many as 150 waterbodies which are utilized by fish for migration,rearing, spawning,a~d/or wintering.Siting should avoid or minimize impact to spawning areas in approximate~y 35 waterbodies and to wintering areas in approximately 15 waterbodies.Information regarding specific waterbodi es of concern is presented in Appendi x C,"Report on Faci 1i ty Siting and Corridor Selection.II 2601B 2-43 Counterpoise (ground cable)construction may require excavation in streambeds;this activity must be carefully planned (both spatially and temporally)and monitored in accordance with individual permit requirements.Conditions vary along the corridor,so that environmental protection stipulations imposed by the regulatory agencies will tend to be site-specific. The transmission line corridor between Fairbanks and Anchorage makes as many as 100 crossings of rivers and streams and comes within one mile of numerous lakes and ponds.All of these waterbodies are important habitat for endemic and anadromous fisheries.Impacts to fisheries such as increased runoff and sedimentation could occur through clearing of the right-of-way and crossing of watercourses by construction equipment.The introduction of ·silt into streams·can delay hatching, reduce hatchi ng success,prevent ·swimup,and produce weaker fry. Siltation also redUces the benthic food organisms by filling in available intergrave1 habitat. The potential adverse impacts can be reduced or eliminated through construction schedUling.Construction of the transmission lines during the winter would minimize erosion since the snow protects low vegetative cover that stabilizes soils.Ice bridges could be used by construction equipment for crossing spawning areas,where possible. Otherwise,where equipment would move through watercourses, construction could occur during periods when there are no eggs or fry in the gravel. 2.4.4 Terrestrial Ecosystem Effects The North Slope area and specifically the river delta areas provide a variety of habitats that are important to a diversity of plants and anima1s.Project related impacts which require special consideration include:(1)direct habitat elimination through the construction of project facilities,access roads,and gravel borrow areas;(2)indirect 2601B 2-44 [ C C E C b L L L L c [ [ [ [ [ r' rL.3 r: L [ o C· [~ ~ [ C L C [ habitat elimination resulting from access roads which impede drainage or which generate significant traffic related dust;and (3)restrictions to large mammal movements,especially caribou. Construction of the powerplant,switchyard,construction camp and related access road~will disturb approximately 65 acres of·land.All construction equipment should be restricted to areas covered with a gravel pad.Tundra adjacent to the generating facility should not be disturbed. Because the generating facility will be located within the Prudhoe Bay industrial complex,terrestrial habitat impacts engendered by this project will be an added increment to those which have already occurred as a result of oil field development.Final siting efforts should include evaluation of the factors listed above,and will be the mechanism through which highly significant terrestrial impacts can be avoided,particularly the indirect impacts and migratory blockages. The direct impacts of habitat removal due to facility construction are generally unavoidable,1>ut can be minimized through careful site planning and construction management. Construction of the transmission line facilities will require vegetative clearing in forested areas.Clearing shoulq be restricted to the following categories of vegetation: (1)Trees and brush which may fall into a structure,guy,or conductor (2)Trees and brush into which a conductor may blow during high winds. (3)Trees and brush within 25 feet of a conductor,and trees within 110 feet of the line centerline. (4)Trees or brush that may interfere with the assembly and erection of a structure. 2601B .2-45 Between the North Slope and Fairbanks,much of the area south of Nutirwik Creek will require clearing of trees within the right-of-way. Because two lines will be built and trees within 110 feet of the line will be cleared,the total width of cleared vegetation will be 440 feet.Over the length of the line,approximately 7000 acres will be cleared. The transmission line corridor passes through a wide variety of terrestrial ecosystems,and is adjacent to several major federal land areas which have been protected,in part,for their wildlife values. The Bureau of Land Management (BLM)land use'p1an for the Utility Corridor (BU4 1980)has identified several areas as containing critical wildlife habitat.Specific management restrictions have not as yet been formulated;however,measures may be re~uJred for a number of areas.Details regarding these areas are given in Appendix C. The land use plan also specifically requires protection of raptor habitat and critical nesting areas.Protection of crucial raptor habitats preserves the integrity of raptor populations and maintains predator-prey relationships. Facilities and long term habitat alterations are prohibited within one mile of peregrine falcon nest sites unless specifically authorized by the U.S.Fish and Wildlife Service,because of the endangered species status of the peregrine falcon. As the transmission line corridor generally avoids known nesting areas, the restriction may only apply to material sites.Information regarding specific raptor nesting areas and siting restrictions are presented in Appendix C. It is unlikely that the transmission line would be sited in or near important Da11 sheep habitat.A primary concern is aircraft traffic over critical wintering,lambing,and movement areas.Moose winter browse habitat in the Atigun and Sag River valleys is limited to areas 2601B 2-46 [ [ [ [ [ [ e b [ [j L [ [ [ [-:..~-~ J [ l [ of tall riparian wjllow.Habitat has already been eliminated by the construction of Trans Alaska Pipeline System (TAPS)and further destruction of this habitat should be avoided or minimized.The willow stand along Oksrukuyik Creek,in particular,should not be disturbed. System design must allow free passage for caribou,but these animals should not be a major consideration in siting.Carnivore/human interaction is a major concern in facilities design and in construction and operations methods,but not in siting considerations. Line routing and tower siting should avoid or minimize disturbance of the treeline white spruce stand at the head of the Dietrich Valley, which has been nominated for Ecology Reserve status. For the Fairbanks to Anchorage transmission line approximately 80 percent of the corridor is located in forested areas (Commonwealth Associates,1982).Assuming two additional lines are built and the Intertie is extended,a total of about 8700 acres will be cleared.The principal impacts associated with clearing a right-of-way and construction of the transmission line are the alteration of existing habitats and SUbsequent disruption of wildlife species that use those habitats and disturbance to indigenous fauna and bird populations. Most big game species would relocate during the construction of the transmission lines.The construction schedule should be flexible so as to avoid construction near calving and denning sites.The moose,which adapts to many different habitat types,would establish a sUbclimax community in the cleared right-of-way.The distribution of caribou is limited along the transmission line corridor but those that do occur in the vicinity of the right-of-way would be displaced.The caribou, however,generally utilize habitats with low vegetative cover, resulting in little alteration of caribou habitat. Grizzly and black bears would relocate to avoid construction activity along the right-of-way,except where construction occurs near a den 2601B 2-47 si te during winter dormancy.Constructi onactivi ty near denning areas should be avoided from October 1 through April 30.The alteration of habitats could temporarily affect bear use of the right-of-way but this impact is expected to be relatively short-term. Wolves within the vicinity of the right-of-way would also be displaced during construction of the transmission line.While these impacts would be temporary,long term impacts would occur to the wolf if their principal prey species,such as caribou,sheep,and moose were adversely affected. Oa11 sheep occur only at the northern end of the transmission line corridor and would be impacted only minimally by construction activities.The use of he1 icopters to construct the 1 ines in the Moody and Montana Creek drainages could severely disturb sheep in the vicinity of Sugarloaf Mountain. The impact to the regional populations of any of the small game ~pecies is expected to be neg1 igible.Small game speci es are expected to relocate during construction activities and re-invade the right-of-way once constructi on is over. In heavily forested areas along the corridor,the fight-of-way clearing could provide an improved habitat for most of the small game species that utilize sUbclimax communities. Migratory waterfowl are susceptible to disturbance from construction activities from mid-April to the end of September when they are nesting and brood reari ng •Constructi on ac ti vi ti es shou1 d be restricted from May through August in areas with active trumpeter swan nesting territories.Collisions with transmission lines,guywires,and overhead groundwires are another potential impact.To date,however, the levels of avian mortality from line collision have not been biologically significant (Beau1aurier et a1.1982). 2601B 2-48 C L c [ [ [ [ r' [ n b r L [ [J C. C ~ [ C L L L Furbearers are not expected to be greatly affected by construction activities except during the initial right-of-way clearing.Most furbearers will either adapt to the presence of the cleared right-of-way or undergo short term impacts.The maintenance of a shrub community in the right-of-way will reduce the loss of individuals. The impacts on nongame mammal sand bi rds are expected to be insignificant.Some small mammals and nongame birds would undergo population shifts during construction activities but populations are expected to recover within one to two reproductive seasons.Raptors may lose some habitat as a result of clearing.Benefits of a cleared right-of-way could occur as some raptors could find that it provides hunting habitat or hunting perches not previou~ly available. 2.4.5 Socioeconomic and Land Use Effects Potential socioeconomic and land use effects of the North Slope scenario include both temporary impacts related to the influx of workers and permanent land use impacts. Since the generating plant would be located within the Prudhoe Bay/Deadhorse industrial complex,the in-migrating work force would not significantly affect the social and economic structure of the region. The work force requirements are small in comparison to the existing size of the transient work force in the Prudhoe Bay region.FQr 5 months of each year during the period 1993 through 2010 a maximum of 200 employees will be needed to assemble the prefabricated units of the plant.Housing facilities would be provided for the employees at the adjacent construction camp.During off-work periods,the majority of the employees would spend time outside of the borough.The operations work force is expected to be approximately 150 and will reside in the labor camp.The spending of wages earned by the employees within the North Slope Borough is expected to be minimal due to the transience of the work force. 2601B 2-49 The use of land for an electrical generating plant would be compatible with the land uses of the industrial enclave.The Coastal Zone Management Program for the North Slope Borough has delineated zones of preferred development.Permanent facilities are allowed in the industrial development zone,consisting of the existing Prudhoe Bay/Deadhorse.complex and the Pipeline/Haul Road Utility corridor (North Slope Borough 1978).The generating plant would be located within the preferred development zone. Within the Prudhoe Bay/Deadhorse complex,the plant would be located to minimize interferences with existing or planned facilities,including buildings,pipelines,roads,and transmission lines.Land ownership and lease agreements will limit the land available for the electrical generating facility. Socioeconomic and land use impacts related to construction and operation of transmission facilities between Prudhoe Bay and Fairbanks will be strictly controlled as a result of the guidelines and constraints for development within the designated utility corridor. Construction employees would be housed either at the pump stations or the permanent camp facilities constructed for the trans-Alaska oil pipeline.Construction activities would be consistent with the land use criteria developed by the BUM.The BLM has prepared land use plans ••0 •• for the utility corrido!between Sagwon Bluffs and Washington Creek. Road and highway crossings would be minimized,and areas of existing or planned mineral development would be avoided. Construction facilities would be sited at carefully selected locations in the vicinity of Livengood Camp,Yukon Crossing,Five Mile Camp, Prospect, Coldfoot,Chandalar,and Pump Station #3.Existing facilities such as work pads,highways,access roads,airports, material sites and communications would be used to the maximum extent possible. 2601B 2-50 c [' l~ [ [ [: [: r~ L; CL~ [, [1 C C Q [ l L [ [ [ [ [ [ [ [ [ c nL c c [ C G [ l··~.3 L [ [ The schedule for constructing the transmission lines is approximately 3 years with activities occurring mainly during the autumn and spring of each year.A peak work force of 2400 employees would be required during the first year of construction when the pads would be built,and in subsequent years the total work force would be sUbstantially reduced to approximately 500 in the second year,600 in the third year,and 670 in the final year.It is expected that these workers will be hired from the Anchorage and Fairbanks union hiring halls. Development of additional transmission facilities between Fairbanks and Anchorage would engender potentially more significant socioeconomic and land use impacts,since this segment is more populated and subject to future land use development.Temporary campsites would be provided to house the work crews at locations accessible by the Parks Highway or the Alaska Railroad.'The work force requirements would be lower for this corridor because pads would not need to be constructed.The schedule for constructing the transmission lines is approximately 22 months.A peak work force of approximately 520 employees would be required during the last 6 months and the average work force would be approximately 300.It is assumed that the project would utilize the labor pools of Fairbanks and Anchorage. Impacts to local communities would be minimized through careful siting of the temporary work camps.It is expected that the work camps would be self-contained in order to keep to a minimum interaction between the construction workers 'and the local residents.The project is expected to have minor primary economic benefits since few,if any,residents would be employed on the project. Land use impacts could include encroachment of the project on residential areas as well as preclude future residential development land available for homesteading.The most significant potential impact would be the crossing of recreation lands and the sUbsequent effects on recreation and aesthetic vaiues these lands are meant to preserve. 26018 2-51 The potential aesthetic impacts of the proposed new and additional transmission facilities are significant.The cumulative effects of these facilities and previous linear developments (e.g.,TAPS)could result in significant degradation of the aesthetic character of pristine wilderness landscapes.The visibility of the transmission lines from existing travel routes (Dalton Highway,Parks Highway,etc.) will vary depending on distance,topography and intervening vegetation.Special care would betaken in selecting final route alignments in proximity to areas of special visual significance,such as national parks,or high visual sensitivity,such as areas within the viewing range of motorists on the Parks Highway.In locations where visual impacts cannot be avoided through careful routing or tower spotting,mitigating measures,such as the use of non-reflective paint or vegetative screening,can be employed. 26018 2-52 r n [ o rL. [.~ --~ [ C CL [ C [. l W [ C L L [ I I I I I I I I- I I I I I I I I [I o ~ SCENARIO I NORTH SLOPE POVVER GENERATION LOW LOAD r [ [ r r~ L L n b r L [ G C [ ~-'''' C·.····~..- .~ L L L l [ 3.0 NORTH SLOPE POWER GENERATION LOW LOAD FORECAST The North Slope power generation scenario,under the low load forecast, is conceptually the same as the medium growth case,except that units are phased in at a slower rate.By the year 2010,eight simple cycle combustion turbine units are required to produce 728 MW.The electric transmission system requires two 500 kV lines;however,series capacitors are not required to ensure system stability.Total system cost is estimated to be $3.3 billion,with annual operation and maintenance costs of $0.7 billion.The present worth of these costs excluding fuel costs is $2.7 billion as of 1982.Environmental effects of the project are sUbstantial,but would not preclude construction. Information presented in this section is designed to highlight only those conditions which are significantly different from those of the medium load forecast presented in Chapter 2. 3.1 POWER PLANT This scenario requires eight 91 MW simple cycle gas turbines to satisfy.. the low Toad forecasted demand.The first of these w.ill go on line in .1996 and the eighth in 2010.Additions are summarized in Table 3-1 and scenario details are addressed in Appendix B.Annual fuel requirements for power generation will start at 6.60 BCFY in 1996 and grow to 47.2 BCFY in 2010.The maximum potential firing rate in 2010 will be approximately 1.33 x 105 SCFM.Fuel requirements on an annual basis are also shown in Table 3-1. With the exception of the sUbstation,all details of individual plant items are identical to those described for the m~dium load case.in 'Section 2.1.The sUbstation for this scenario differs from the medium forecast design (Figure 2-3)in that there are no series capacitors 2589B 3-1 TABLE 3-1 NEW CAPACITY ADDITIONS AND FUEL REQUIREMENTS NORTH SLOPE POWER GENERATION -LOW LOAD FORECAST New Capacity (MW)Gas Requi red!/ Year (Increment/Total)(MMsCFY) 1990 0/0 0 1991 0/0 0 1992 0/0 0 1993 0/0 0 1994 0/0 0 1995 0/0 0 1996 91/91 6,596.6 1997 91/182 13,149.1 1998 0/182 13,149.1 1999 0/182 13,149.1 2000 0/182 13,182.1 2001 0/182 13,149.1 2002 91/273 19,723.7 2003 91/364 26,287.3 2004 0/364'26,364.2 2005 182/546 39,216.5 2006 0/546 39,436.4 2007 0/546 39,436.4 2008 91/637 44,284.9 2009 0/637 45,736.1 2010 91/728 47,187.4 11 Values as calculated are shown for reproducibility only,and do not imply accuracy beyond the 100 MMSCFY level. 2589B 3-2 r r: [' I' I l l f'u [: L [ [ L'...•'..•..'..t- ~ [. [' [" L [ C L [ C b [ [ L L_ L installed and the facility is smaller in size.The circuit diagram is shown in Figure 3-1.Only four 13.8/138 kV generator transformers are needed,and each transmission line circuit is supplied by only one 750 MVA 138/500 kV transformer.The initial installation is essentially the same as in Figure 2-4 except that the series capacitors are not required. Personnel required for operation and maintenance will be less for this scenario than for the medium load forecast.Ten on-duty personnel will be required in 1996 for the first unit.This number will increase to approximately 35 on-duty personnel when 8 units are operating in 2010. The total two-shift,full year,work force would therefore range from 40 to 140 for the study period. 3.2 TRANSMISSION SYSTEM The North Slope to Fairbanks,and the Fairbanks to Anchorage transmission systems for the low load forecast scenario do not differ significantly from the medium forecast designs.A voltage of 500 kV is cost effective for the line between the North Slope and Fairbanks; however,for this case,series capacitors will not be needed.For the Fairbanks-Anchorage section,two 345 kV lines with series compensation are sufficient.That is,one new 345 kV line will be constructed and the Healy-Fairbanks and the Willow-Anchorage segments of the existing. intertie will be upgraded from 138 kV to 345 kV. The number and sizes of the intermediate switching stations remain unchanged.There are two such stations on the 500 kV line (without any series capacitors),at Galbraith Lake and at Prospect Camp.There is only one switching station on the 345 kV line from Fairbanks to Anchorage,but in this case it has to be at the midpoint of the line, i.e.,some 30 miles north of the Devil's Canyon switchyard of the medium forecast sc·enario. The substation at Fairbanks and Anchorage are slightly scaled down from those described in Section 2.3 and Figures 2-5 and 2-6. 2589B 3-3 250 MVA TYPICAL 500kV 13.8kV 22 22 22 22 750MVA TYPICAL ZOO MVAR TYPICAL 1---'\"''''-.-III TO FAIRBANKS LEGENDoGENERAToR =ORtw'I"TRANSFORMER o CIRCUIT BREA!<ER ....IV\I\r-REACTOR ;k CAPACITOR TO FAH?BANKS ALASKA POWER AUTHORITY NORTH ILOPE GAS FEASIBILITY InlOY NORTH IlOPE POWER GENERATION lOW lOAD FORECAST SUBSTATION ONE LINE SCHEMATIC 'ICIUflE a -1 .IAICO IERVICES ICOAPORATED rn j~ ,J .~,,.~i~' r [ [' [' [ [ f " _._...J rt~ L L c [ [ [,~ -.d L [ L L L. L 3.3 COST ESTIMATES 3.3.1 Construction Costs The capital cost of e~ch simple cycle gas turbine is the same as that presented in Section 2.3 for the medium load forecast. The feasibility study investment costs of the transmission line systems are presented in Table 3-2 and 3-3.Table 3-2 presents the estimates for two 500 kV,700 MW capacity lines without series compensation,and two intermediate switching stations.Table 3-3 contains the estimates for one new 345 kV line,700 MW capacity,with series compensation and an intermediate switching station,and the required upgrading of the Willow-Anchorage and Healy-Fairbanks transmission lines. 3.3.2 Operati~n and Maintenance Costs Power plant operati on and maintenance (O&M)costs are the same for both the medium and low load forecasts,6.3 mils/kWh.Transmission line O&M costs are estimated to be $30 million per year.These costs should be viewed as an annual average over the life of the system.Actual O&M costs should be less initially and will increase with time. 3.3.3 Fuel Costs For the economic analyses which follow fuel costs were treated as zero.This approach permits fuel cost and fuel price escalation to be treated separately;and makes possible sUbsequent sensitivity analyses of the Present Worth of Costs for this scenario based upon a range of fuel cost and cost escalation assumptions. 3.3.4 Total Systems Costs The total sy~tem for the North Slope low load forecast,like the North Slope medium growth forecast,consists only of simple cycle combustion turbines and a transmission line system. 2589B 3-5 Construction Labor 2/ ($1000) Materi a1 ($1000) TABLE 3-2 FEASIBILITY LEVEL INVESTMENT COSTS NORTH SLOPE TO FAIRBANKS TRANSMISSION SYSTEM NORTH SLOPE POWER GENERATION -LOW LOAD FORECAST (January,1982 Dollars.) Descri pti on.!! F. r' r I ----------------------------~--- Tota 1 I.·.·.'..Direct Cost l ($1000) [ [ [ e l~ L L L L L [ L. \ [" 19,253 39,693 28,694 64,212 12,000 24,900 873,012 1,695,224 149,760 213,452 85,200 85,200 $1 ,167,919 $2,122,681 36,000 148,600 $2,307,281 20,440 35,518 12,900 822,212 63,962 $954,762 TOTAL CONSTRUCTION COST Clearing 2589B 3-6 SUBTOTAL Land and Land Right~ Engineering and Construction Management Conductors and Devices Switching Stations Substations 11 The investment costs reflect two 500 kV lines,700 MW capacity without series compensation and two intermediate switching stations.A 15 percent contingency has been assumed for the entire project and has been distributed among each of the cost categories shown.Sales/use taxes have not been included. 2/Construction camp facilities and services are subsumed in the Constructi on Labor cost category. l!Assumes a cost of $40,000 per mile (Acres American Inc.1981). Energy Management System Steel Towers and Fixtures --------------------------r- L !!The investment costs reflect one new 345 kV line,700 MW capacity without series compensation and an intermediate SWitching station,and upgrading of the Willow-Anchorage and Healy-Fairbanks segments of the Intertie to 345 kV. 2/Assumes a cost of $40,000 per mile (Acres American Inc.1981). Switching Station 8,857 8,414 17 ,271 SUbstation and Switching 32,958 30,872 63,830 Station Energy Management Systems 12,300 10,960 23,260 Steel Towers and Fixtures 129,214 182,083 311 ,291 Conductors and Devices 20,049 53,183 73,232 Clearing 41,572 41 ,572 SUBTOTAL $203,378 $327,084 $530,456 Land and Land Right~14,400 Engineering and Construction 37,130 Management TOTAL CONSTRUCTION COST $581 ,986 Total Di rect Cost ($1000) Constructi on 2/ Material Labor ($1000)($1000) 3-7 TABLE 3-3 FEASIBILITY LEVEL INVESTMENT COSTS FAIRBANKS TO ANCHORAGE TRANSMISSION SYSTEM NORTH SLOPE POWER GENERATION -LOW LOAD FORECAST (January,1982 Dollars) 2589B Description!! [ L L L L~ r L The methodology and assumptions utilized to derive the systems·costs which are presented below have been previously described in the Report on Systems Planning Studies (Appendix B).This methodology is consistent with previous studies of electric generating scenarios for the Rai1be1t,specifically the Acres American,Inc.(1981),Susitna .Hydroe1ectric Project Feasibility Report ~nd Battelle (1982),Rai1be1t Electric Power Alternatives Study.The period of the analysis was assumed to be 1982 through 2010. The annual capital expenditures are presented in Table 3-4.Annual non-fuel O&M costs are presented in Table 3-5.The summary of all annual costs in presented in Table 3-6.The 1982 present worth of costs for this scenario (in 1982 dollars)is $2.7 billion,exclusive of fuel costs. 3.4 ENVIRONMENTAL AND SOCIOECONOMIC CONSIDERATIONS The power plant for the low load forecast will consist of 8 simple cycle units,in contrast to 15 units for the medium load forecast. Most environmental impacts will therefore be correspondingly smaller than the medium load forecast.Environment related power plant characteristics are summarized in Table 3-7. Air emissions will be approximately one-half the medium,growth value and will not pose constraining air quality problems.Approximately 25 gpm of fresh water will be pumped from a nearby lake to provide equipment wash-down and potable water supplies.Wastewater discharges will be less than 25 gpm and will be discharged to the existing facilities in the area. Aquatic resources,as for the medium load forecast,will not be significantly affected.Plant acreage,i nc1 udi ng the constructi on camp and switchyard,will be approximately 65 acres,as compared to 95 acres for the medium load forecast.Terrestrial impacts,such as tundra disturbance and habitat elimination,are correspondingly less. 2589B 3-8 [ r. I ( [ [-, [ L~' -j ~ [ L L [ [' r [ L [' [ [- [ P1..-----" rL [0 fJ r -' -, [ L [ L L L. L TABLE 3-4 TOTAL ANNUAL CAPITAL EXPENDITURES NORTH SLOPE POWER GENERATION -LOW LOAD FORECAST (Millions of January,1982 Do11ars)1/ Calendar E1ectricitY'Generate~Transmission Year Unl t A Unit B Line Total 1982 O.O.O.O. 1983 O.O.O.O. 1984 O.O.O.O. 1985 O.O.O.O. 1986 O.O.O.O. 1987 O.O.O.O. 1988 O.O.O.O. 1989 O.O.O.O. 1990 O.O.O.O. 1991 O.O.O.O. 1992 O.O.1,540.1 1,540.1 1993 O.O.358.0 358.0 1994 19.oi~./O.704.6 723.7 1995 53.56 O.286.4 340.0 1996 53.56 O.O.53.6 1997 O.O.O.o. 1998 O.O.O.O. 1999 O.O.O.O. 2000 O.o.o.O. 2001 53.56 O.O.53.6 2002 53.56 O.O.53.6 2003 o.o.o.o. 2004 53.56 53.56 O.107.1 2005 O.O.O.o. 2006 O.O.O.O. 2007 53.56 O.O.53.6 2008 O.O.O.O. 2009 53.56 O.O.53.6 201 0 O.O.O.O. TOTAL $394 .•$54.$2,889.$3,337. 1/Values as calculated are shown for purposes of reproducibility only,and should not be taken to imply the indicated accuracy of significant figures. 2/Unit A refers to the first unit built in a given year and Unit 8 to the second unit built. 3/Construction of camp site and site preparation for all units. ·25898 TABLE 3-5 TOTAL ANNUAL NONFUEL OPERATION AND MAINTENANCE COSTS NORTH SLOPE POWER GENERATION -LOW LOAD FORECAST (Millions of January,1982 Dollars))- Cal endar El ectri ci ty Transmi ssi on Year Generated Line Total 1982 O.O.O. 1983 O.O.O. 1984 O.O.O. 1985 O.O.O. 1986 O.O.O. 1987 O.O.O. 1988 O.O.O. 1989 O.O.O. 1990 O.O.O. 1991 O.O.O. 1992 O.O.O. "1993 o.O.O. 1994 O.O.O. 1995 o.o.o. 1996 3.8 30.0 33.8 1997 7.5 30.0 37.5 1998 7.5 30.0 37.5 1999 7.5 30.0 37.5 2000 7.5 30.0 37.5 2001 7.5 30.0 37.5 2002 11.3 30.0 41.3 2003 15.1 30.0 45.1 2004 15.1 30.0 45.1 2005 22.6 30.0 52.6 2006 22.6 30.0 52.6 2007 22.6 30.0 52.6 2008 25.4 30.0 55.4 2009 26.2 30.0 56.2 201 0 27.0 30.0 57.0 TOTAL $229.$450.$679. 2589B 3-10 [ L: [ [ [; [: ~ [ [ [, [ L [ [ [ L [ l" [ [ C L~ [ [ [ [ t: [ [ L L L TABLE 3-6 TOTAL ANNUAL COSTS NORTH SLOPE POWER GENERATION -LOW LOAD FORECAST (Millions of January,1982 Dollars)) Calendar Capital o &M Total Year Expenditures Costs Expenditures 1982 O.O.O. 1983 O.O.O. 1984 O.O.O. 1985 O.O.O. 1986 O.O.O. 1987 O.O.o. 1988 O.O.O. 1989 O.O.O. 1990 O.o.O. 1991 O.O.O. 1992 1,540.1 O.1,540.1 1993 358.0 O.358.0 1994 723.7 O.723.7 1995 340.0 O.340.0 1996 53.6 33.8 87.4 1997 O.37.5 37.5 1998 O.37.5 37.5 1999 O.37.5 37.5 2000 O.37.5 37.5 2001 53.6 37.5 91.1 2002 53.6 41.3 94.9 2003 O.45.1 45.1 2004 107.1 45.1 152.2 2005 O.52.6 52.6 2006 O.52.6 52.6 2007 53.6 52.6 106.2 2008 O.55.4 55.4 2009 53.6 56.2 109.8 201 0 O.57.0 57.0 Total $3,337.$679.$4,016. Present Worth @ 3%$2,345.$360.$2,.705. 2589B 3-11 TABLE 3-7 ENVIRONMENT RELATED POWER PLANT CHARACTERISTICS NORTH SLOPE POWER GENERATION -LOW LOAD FORECAST Ai r Envi ronment Emissions Particulate Matter Su1 fur Di ox i de Nitrogen Oxides Physical Effects Water Environment Plant Water Requirements Plant Discharge.Quantity Including Sanitary Waste and Floor Drains La nd En vi ro nme nt Land Requirements Plant and Switchyard Construction Camp Socioeconomic Environment Construction Workforce Operating Workforce 2589B Below standards Be low standa rds Emissions variable within standards - dry control techniques would be used to meet calculated NO~standard of 0.014 percent of total volume of gaseous emissions.This value calculated based upon new source performance standards,facility heat rate,and unit size • .Maximum structure height of 50 feet 25 GPM Less than 25 GPM 60 acres 5 acres Approximately 115 personnel at peak construction Approximately 140 personnel 3-12 [ L: [ [ [ [ C [ L [ L L [ [ [- [' [~ I [' r~ L Impacts associated with the transmission line from the North Slope to Fairbanks are identical to those discussed for the medium load forecast (Section 2.4).From Fairbanks to Anchorage only one line in addition to the Intertie will be necessary,in contrast to two new lines for the medium load forecast.Cleared acreage within the right-of-way will be approximately 5200 acres,as compared to 8700 acres for the medium load forecast.Impacts associated with vegetative clearing,including erosion,sedimentation,and habitat disturbance,are correspondingly less than those discussed in Section 2.4. Construction of the project according to the low demand forecast would result in a smaller work force than under the medium demand forecast as well as a shorter work schedule.The construction work force is forecasted to be 115 employees,or a 40 percent reduction over the 200 employees forecasted for the medium growth scenario.The operations work force is predicted to be 140 persons,Which is 70 percent of the work force requirements of the medium growth forecast. Operation of the first generation unit would begin in 1996 compared to 1993 under the medium growth forecast.For five months of each of seven years during the period 1996-2010 a prefabricated unit of the plant would be assembled.During off-work periods,the majority of the employees would spend time outside of the North Slope Borough.The spending wages earned by the employees within the borough is expected to be minimal due to the "transience of the workforce. Despite the differences in work force reqUirements and schedule between the low and medium growth forecasts,the socioeconomic impacts would be expected to be similar.The relatively low level of impact can be attributed to the location of the generating plant within the Prudhoe Bay/Deadhorse industrial complex,which is isolated from communities. The work force requirements and schedule for construction of the transmission.lines is almost identical to that of the medium forecast scenario,and,therefore,socioeconomic impacts will be essentially the same as those discussed in Section 2.4. 2589B 3-13 I I I I I I I I- I I I I I I I •[. oo SCENARIO 1/. .... FA!RBANKS POWER GENERATION MEDIUM LOAD 4.0 FAIRBANKS POWER GENERATION MEDIUM LOAD FORECAST Fairbanks power generation,under the medium load forecast,re~uires a gas conditioning plant on the North Slope,a medium diameter pip"e1ine to the Fairbanks area,an electric generating station at the pipeline terminus,and electrical transmission capacity between FairbankS and Anchorage.The North Slope gas conditioning plant will remove carbon dioxide (12%by volume of the raw gas)and natural gas liquids. Initial and final peak delivery volumes are anticipated to be 230 MMSCFD and 407 MMSCFD,respectively,using a 22 inch diameter pipeline operating at 1260 pounds per square inch of"pressure.The pipeline will be buried.Initially,three gas compressor stations along the pipeline route will be required,increasing to 10 by the year 2010. The electric generating station necessary to produce almost 1400 MW of capacity in 2010 will consist of 5 combined cycle units,each consisting of two gas fired co~ustion turbines paired with two waste heat recovery boilers and one steam turbine generator,and 2 simple cycle gas turbines,which can be paired with waste heat recovery boilers to form a sixth combined cycle unit after 2010.Transmission lines to carry the power to·the load center in Anchorage will require two additional (total of 3)345 kV lines from Fairbanks to Anchorage. This scenario also includes the construction of a natural gas distribution system in Fairbanks to serve residential and commercial space and water heating needs.Forecasting a fuel demand which replaces existing fuels is speculative,but highest demand (inclUding growth)is based on 100 percent penetration of the potential market. In Fairbanks,in 2010,this is estimated to be as much as 63 MMSCFD. 2648B 4-1 Costs for shared facilities have been apportioned between the electric generating facility and the residential/commercial gas distribution system.Given this apportionment,construction of the gas conditioning facilities,gas pipeline,power generating facilities and transmission systems,is estimated to cost $6.5 billion.Total annual operation and .maintenance costs are estimated to be $0.8 billion.The present worth of these costs excluding fuel costs is $5.4 billion.Construction costs for the Fairbanks gas distribution system serving residential/commercial markets total $1.2 billion,with total annual operation and maintenance costs totalling $86 million.The present worth of costs for this system consisting of a portion of the pipeline and gas conditioning facilities, plus the distribution network itself,is $0.9 billion. 4.1 NORTH SLOPE TO FAIRBANKS NATURAL GAS PIPELINE The design of the gas pipeline and the gas conditioning facilities proceeded on the basis of preliminary gas demand calculations (detailed in Appendix A).SUbsequent refinement of total peak demand for the Fairbanks scenario based on domestic gas distribution and electric usage (detailed in Appendix E and Appendix B,respectively)did not require design changes in the pipeline but resulted in small differences in gas demands in the sections that follow.The pipeline gas demands are as foll ows: f l C L- [j 2648B Pipe1 ine Design (Preliminary Demand) Power Generation Annual Average Demand Daily Peak D~mand Residential/Commercial Annual Average Demand Daily Peak Demand Totals Annual Average Demand Daily Peak Demand 4-2 Medium Load Forecast (MMSCFD) 186 307 27 76 213 383 L L L The refined values on which the Fairbanks gas distribution system and the electric generating un1t additions depend are as follows: Utility Systems Design (Re fi ned Demand) Power Generation Peak Daily Demand Residential/Commercial Peak Daily Demand Totals Peak Daily Demand Medium Load Forecast (MMSCFD) 271 63 334 c C L C G_7' r-~ L L L [ The refined gas demand is about 50 MMSCFD less than the preliminary value,an amount insufficient to necessitate pipeline design changes. 4.1.1 Gas Conditioning Plant Gas to be transmitted through the pipeline will first be conditioned on the North Slope.The conditioning facility will receive the gas from the production fields,treat it,and compress it to 1260 psig and a temperature of 25 to 30°F.Initial design delivery volume \,ill be 230 MMSCFD;however,the plant will be capable of expansion to 407 MMSCFD as future demand increases.These values are based on total Fairbanks gas demand,compressor station requirements and a pipeline availability of 96.5 percent.The gas delivery and quality specifications are presented in Table 4-1. The process assumed for carbon dioxide removal is Allied Chemical's SELEXOL physical solvent process,the same process sel~cted for use with ANGTS.A mechanical refrigeration process will control hydrocarbon de~point.Water dewpoint control will be accomplished in the dehydration equipment located in the eXisting Prudhoe Bay Unit gas/crude oil separation sites called Gathering Centers and Flow Stati ons.The hydrogen sul fi de content of the feed gas is very -10\'{. It was therefore assumed that no process equipment will be required for either water"dewpoint control or hydrogen sulfide removal. 2648B 4-3 TABLE 4-1 GAS DELIVERY AND QUALITY SPECIFICATIONS FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST [ L (L, [' 2.0 volume % 1.0 grain/100 SCF -10°F @ 1000 psia -25°F @ 1000 psia 1260 psig 25-30°F 230 MMSCFD 407 fvMSCFD Speci fi cati onsParameter Initial Delivery Volume Ultimate Delivery Volume ijydrogen Sulfide Content (max.) Hydrocarbon Dewpoint (max.) Water Dewpoint (max.) Delivery Pressure Delivery Temperature Carbon Dioxide Content (max.) 26488 4-4 L L f C [ r [-. L l. r~ ~L t [ L [ A simplified process flow diagram illustrates the basic process flow of the conditioning facilities (Figure 4-1).Two trains will be installed,one for continuous operation and the other as a spare.Feed gas,originating from the gas/crude separators,will be compressed in the Gdthering Centers and Flow Stations and flow to the inlet separation unit.The inlet gas streams will be met~red,and any s01ids or free liquids in the gas will be removed at this point.The feed gas will flow first to the natural gas liquids (NGL)extraction section for hYdrocarbon dewpoint control.The gas will then flow to the SELEXOL section where the carbon dioxide is removed.The conditioned gas will then go to the gas compressors where it will be boosted to pipeline pressure,then refrigerated for transmission.SELEXOL solvent characteristically absorbs,along with the carbon dioxide,a significant quantity of hydrocarbons,particularly the heavier hydrocarbons.During the regeneration of the SELEXOL solvent,both the carbon dioxide and hydrocarbons are flashed from the solvent,producing a low Btu gas.The gas will be utilized within the facility to offset some of the energy requirements. The hydrocarbon liquids from the NGL Extraction and SELEXOL flash gas will be separated in the fractionation unit into propane,butanes,and pentanes-plus products to facilitate disposal.Some propane will be used for heating value control of certain fuel streams.The remaining propane will be injected"into the pipeline gas.The butanes will be eitner rnjected into the pipeline gas up to hYdrocarbon dewpoint limits or into the crude oil delivered to the Trans Alaskan Pipeline System (TAPS)as is presently accomplished at the existing central compression facility for gas reinjection.The pentanes-plus will be injected into the same crude oil stream. The facilities will require approximately 175,000 total installed horsepower including motors,power recovery units and gas turbines. The bulk of this horsepower will be developed by 9 operating gas turbines with 6 spare gas turbines.The major auxiliary systems will include refrigeration,offsite and general utilities,and power generation facilities. 2648B ..,........ --------------------.Ji7lo:~:m• J -'--~IiZ>...... r-.a;::;}II-~-------IiZ>~~:=·"t'• .--=".,~_O"..."'I""" ~1----- an_Ill,-,. ~f---_ " .-'u-------1I!8!J-Wto ~~(\:.:::.t.,'.1 L..__._..,,-.".• limn --li?'.',,~''''cw......----------------------Jii" L---L------------__~_=:_·I_----l;;~~~-----f,--------_J ~..".:::'.I..r-----------------------5~:::·,,11f\.", •tI,UI'... I.'.till..... I.e.MI ...... .p. I 0"\ ALASKA POWER AUTHORITY NORTH SLOPE GAS FEASIBILITY STUDY GAS CONDITIONING FACILITY 'IQUIlE 4-1 EBASCO 8ERVICES INCORPORATED ---,I ,;---"I \"J '~' ,--'",,--~,.~ J c c [: [ r [ r: n '--' b [ b L L [ C L L L The remoteness and severe environmental conditions at the North Slope impose limitations on both the process and mechanical design of the facilities.All equipment will therefore be housed in totally enclosed modules. Modules,with contained equipment,will be fabricated prior to shipment to the North Slope.They will De sea-lifted to the North Slope by ocean-going barges.At Prudhoe Bay they will be offloaded by crawler transporters or rUbber-tired vehicles and moved to their pile supports on graveled sites. A critical timing factor in any construction program at Prudhoe Bay is the limited time period during which the sea lanes are passable.Major plant components can only be delivered via ocean-going barges during the short (4-6 weeks)period each year when the sea lanes are not blocked by ice.Failure to deliver any critical major component during the stheduled period could effectively delay full-capacity startup by •••0"• one fUll year. 4.1.2 Pipeline 4.1.2.1 Pipeline and Route Gas to be transported will be provided to the pipeline from the gas conditioning plant.Pipeline q~ality gas will be a hydrocarbon mixture with approximately 88 percent m~thane,and a gross higher heating value of approximately 1100 Btu/SCF.The pipeline will be designed and operated to maintain the soil around the buried sections of the pipeline in a frozen state.The operating temperature of the gas in the pipeline will be between O°F and 32°F under normal conditions. However,during transient periods,the gas in the line may exceed 32°F or may go down to as low as _5°F for short periods of time. The proposed p.ipeline route originates in the Prudhoe Bay area in northern Alaska (refer to Appendix C).The pipeline will connect to . the gas condJtioning plant at the metering station,designated Milepost O.The pipeline route,which assumes the ANGTS right-of-way, 2648B 4-7 follows TAPS in a southerly direction to about Milepost 274 near Prospect Creek.The pipeline route then follows TAPS in a southeasterly direction to about Milepost 480,the assumed location of the power plant metering station.A tap will be pr.ovided at Milepost 455 near Fox to supply gas to Fairbanks for residential and commercial uses. The pipeline will cross 15 major streams requlrlng special construction considerations,such as heavy wall pipe,continuous concrete coating or set-on concrete weights.At the Yukon River an existing aerial crossing will be used. There will be 20 uncased road crossings,27 road crossings with 28 inch casings,and 8 road crossings with 36 inch casings.The pipeline will cross TAPS at 21 locations,the TAPS fuel gas line at 1~locations,and other pipelines at 3 locations. ct T [ I' r l~ r', LF 4.1.2.2 P.ipe1ine Design The basic assumption that this pipeline will follow the ANGTS right-of-way is a major one.Pipeline design and sUbsequently cost could be greatly affected if this right-of-way could not be used. Significant areas of concern would include the narrow Atigun Pass area and the Yukon River crossing. The pipeline design pressure will be 1260 psig,based on current proven technology for resistance to crack propagation at low temperatures. The pipeline has been designed for the daily peak flow required to satisfy the gas demand associated with the medium forecast assuming a pipeline availability of 96.5 percent.The following f10wrates were used for the hydraulic design of the pipeline: 26488 Annual Average Flow (MMSCFD) Daily Peak Flow (MMSCFD) 4-8 213/0.965 =220 383/0.965 =397 [ [ [ Fl~-,~ L [- L~ L [ L [ [ L [ [ [ r-'- r L~~ r: L r-; G [ [ L [ [ Initial annual average daily capacity of the pipeline will be 127 MMSCFD with a peak daily load of 227 MMSCFD during extreme cold weather periods. The peak daily f10wrate will require a pipeline outside diameter of 22 inches.The pipe shall be API 5LX or API 5LS Grade X70 with a minimum wall thickness of 0.275 inches for the majority of the length.At road crossings,bridges,and within pUblic road right-of-ways,the minimum wall thickness will be 0.330 inches.These thicknesses are based on the entire pipeline being located in a Class 1 location as defined in CFR 49,Part 192. The peak daily f10wrate requires 10 compressor stations of approximately 3400 HP each.The average daily f10wrate will require the operation of only 3 compressor stations,Stations 2,4 and 7.The compressor stations are at the locations selected by ANGTS and use the same numbering system.The delivery pressure to the power plant will be 1038 psig.Figure 4-2 summarizes this f10wrate condition. Compressor station fuel consumption will be approximately 1 MMSCFD per operating station. A total of 28 mainline block valve assemblies will be provided at a nominal spacing of 20 miles including the initial compressor sites.. where the mainline valves will be installed in the station bypa~s loop.Seven of the 28 block valves will be installed at the additional station sites to facilitate system expansion.Pig launchers and receivers will be installed at the compressor and metering stations. The pipe will be installed in a buried mode,using the proposed ANGTS construction techniques.Pipe ditches will be selected from several basic types,based on site-specific conditions.Special ditch configurations will be required to provide for the mitigation of frost heave e!!ects in areas having frost-susceptible soils. 2648B 4-9 , M.5._.5"...s."s:s.c....,~"..'.S 55.".5.'-s.~~~7 ."'.S.'-0.2.So..,~,'Z.~~47."r;;; C.S..5.3 e.s..S.~S.l V LP.!>.~Q "'Ii ..I)VI .."Ill lila 2 ~......~t~O 'l'l >:i ~..~~~t it'"h .. ..0 h II.C"II.•S.o~"t ~!Jh~"80 MM'sc:.r/D I 'l ~)' TOTAL "'0 MILES.22"0.0.PIPELINE •.WALL THICKNESS •Q215 INCH MINIMUM STATION DESIGNATION .....c.•.I C••.I C.L'C.1.4 C.,••C.,••C•••,C.,••C.,••C.,.to '..... ..IlUDHOI...,..OIIE1l ....., MILEPOST (MILES)D.O 4+.5''a'O.1 , \3.7 141.3 17'.1 2:~S:O 273.'J 320.7 3lrO.,....32..1 41rO.O ELEVATION (FEET)21 3"Z.82.S'I S"'Z 5'305'0 3/S"'8 12.20 131 S'17:30 'i1''IlO /5'20 S'ao•3"M 31"8~STATION INLET VOLUME (MMSCf ID)407 407 .....0'"4Q5'404-403 402-401 400 3 c'nr.. ;!TOTAL fUEL (M..SCFID)-1 ,1 I I I I ,,,-.. STATION OUTLET VOLUME (MMSCf/D)407 406 405"404-403 402..401 ....00 3er"'l 3CJW 3""7 31"8 ITATION SUCTION PRESSUR£('''0)/2.'-0 10-+7 /0(,.3 1057 1031 /0'3 "24 /0,S-103er 1021 '71 '038 STATION DISCHARGE PR£SSURE (PSIG)12'"0 1245 124S 1'2.4S 1'2.30 12.30 /2bO 12(;.0 1230 1230 ".,.~- •COMPRESSOR SUCTION PRESSURE(PSIG)10'3'/047 /041 lOIS 1047 1I0'i!l 107'1023 1012...,S5 -0.-COMPRESSOR DISCHARGE PHESSUM (PSIG)125'12~/2.5'11:44-/2.44 1274 1'2.74 1244 /24...115'-..-...-=COMPR£SSIOH RATIO I.::20'/.II'1./48 I./711 1.2/3 1.22''.2/0 -..-I.2./.,1.200 1.2.22:I 0 HOftSEPOWI:,."(QUlftED 215"0 3200 3250 3"'00 -u -3400 315'0 3200 3400 2"00 '2..300 ALASKA POWER AUTHORITY NORTH SLOPE GAS FEASIBILITY 8TUDY HYDRAULIC sur1~1ARY t1EDIUt1 FORECAST PEAK DAILY FLOW FIGURE 4-2 EBASCO SERVICES INCORPORATED rrr-' l ~!l Pipeline corrosion control will be provided by a combination of external coating and a cathodic protection system that will be compatible with the sacrificial zinc anode system used on the adjacent TAPS pipeline.The pipeline will be hydrostatically tested to 1.25 times the maximum allowable operating pressure. 4.1.3 Compressor and Metering Stations Two metering stations will be provided.One will measure the quantity of gas supplied to the pipeline from the gas conditioning plant at the North Slope,and the other will measure the gas delivered to the power plant just south of Fairbanks.Details of the compressor and metering stations design are provided in the Figures 4-3 and 4-4. Each compressor station site will require about 10 acres,and the metering stations about 1.5 acres of land.Compressor stations will include buildings for the compressors,refrigeration equipment, utilities and control room,flammable liquids storage,warm storage and garage,a gas scrubber unit,living quarters and interconnecting hallways.Additional living quarters,office,and shop and warehouse building will be included at compressor stations 2 and 7. Two refrigeration units will be provided at every compressor station to maintain the pipeline gas temperature.Gas heaters will be Rrovided at compressor stations 2 and 4 to assure that gas temperatures will be maintained above the hydrocarbon dewpoint of the mixture under all operating conditions.Pipeline gas will be used to power the drivers for the gas compressors,refrigerant compressors and electric generators.Compressor station and metering station design and equipment are summarized in Tables 4-2 through 4-10. 4.1.4 Supervisory Control System A supervisory control system will be provided to operate the pipeline system,perform related system balancing,and coordinate functions with the gas conditioning plant at the North Slope and the Fairbanks power plant. 26488 4-11 p L. [ L [ [ [ L b L L L L [ T' T' L f - L r- L_, ~I t4.I, I I I I J., 6AS OV~ FIGURE 4-3 NORTH SLOPE GAS FEASIBILITY STUDY EBASCO SERVICES INCORPORATED ~F"I~e.1VlT'1 0-.1 eL..D~. TYPICAL COt1PRESSOR STATION LAYOUT ALASKA POWER AUTHORITY ~A511\l 1" I I, -I~ I,.-..., a----e----i*1.: SCRU8aE.!\.I I I &LDCS !lJ~: r-~~ •II'I I .....~_tiil._~ • I I I II REaI..,£1tc"I-.I l I I I GcIM~Re.S.sP'"I eo LD.!I I L.AL1AIOtUt I I I~II.J..USI \I I I 10 I I :I I I I I I__.L_~~_~I H£.ATER.I-J •AT'c..S.2~+I OIIIL..Y I 4-12 II II ~L::=J v ..rMIC."OWAY~ /'{Tow£R.,\ -1--.. "P~~"""ONS ~ """'HT&N"''''c.&~ACoI LIT'I E S AT Co.$.~*7 ONL.Y [- [ f --c ,- ...._-- [' r L [, rLj [' L L [ C p.•'b n [ [ L L r '~,, I I 1/I rJ ~~%.--f~Ul./e"'E!.Y'RECEI v E.R;.'~I I I ...I!I I I -I INII \'Illt*----' I I CS~'III -~DWE.R...L.,......T' ,.l..GAS OV'r -PItUE)t'DE e,.." 4-13 Q 'I' 6L.OWDCWN~ £)RVM c::::Il °V£I.JT' ST'~K ALASKA POWER AUTHORITY NORTH SLOPE GAS FEASIBILITY STUDY TYPICAL t1ETERING STATION LAYOUT FIGURE 4-4 EBASCO SERVICES INCORPORATED TABLE 4-2 COMPRESSOR STATION PIPE DETAILS FAIRBANKS POWER GENERATION -MEDIUM LOAD·FORECAST Major piping -1280 psig design pressure a.22"0.0.x 0.406"wall API 5LX,GR.X70 pipe b.18"0.0.x 0.750"wall ASlM A333,GR.6 pipe c.16"O.D.x 0.656"wall ASlM A333,GR.6 pipe d.12"XS ASlM A333,GR.6 pipe e.10"XS ASlM A333,GR.6 pipe f.8"STD.WT.ASlM A333,GR.6 pipe NOTE:API 5LX piping to have additional specifications for -50°F Charpy Impact requirements and chemical requirements for improved we1dabi1ity. 2648B 4-14 [ [~ T" r O '• '. .. r [ l [ [ L [ [ [ r [' L L l L 4-15 2648B e.Amuient temperature range-70°F to +80°F TABLE 4-3 CIVIL DESIGN DETAILS FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST 30 1 height 30 I-50 I hei ght 50 1 -100 1 height 100 I hei ght d.Wind loads will be:30 psf 40 psf 50 psf .60 psf a.All buildings and heated components will be elevated on steel pile foundations above a gravel pad to allow free air circulation under the structures.The pile embedment will be adequate to prevent frost jacking of the structures. Non-heated facilities will be supported by a granular fill and sand paa. b.Snow loads will be 60 psf c.Edrthquake design will be Zone 3 f.Structural steel -inside heated structures,will use normal s~eel materials.OUtside heated structures,will use suitable low temperature steels. g.The diesel fuel storage tank will be placed over an impermeable liner covering the entire diked area. [ [ [ C U [ [ L C [ r L c [: [ [ [ L [ rIc_> TABLE 4-4 BUILDING DETAILS FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST a.All buildings will be pre-engineered insulated-panel metal structures,suitable for their intended use. b.Buildings suitable for truck transportation through size or modu1arization will be prefabricated. c.Hazardous materials storage buildings will be mechanically ventilated.Ventilation rates will be four air changes per hour for normal ventilation and 15 air changes per hour for emergency conditions. d.The sizes of buildings will be as follows: Scrubber bldg.20'"x 40'X 24 1 eave height Compressor b1 dg.30 1 X 40 1 X 20'eave height Refrigeration bldg.60'x 60 1 X 30 1 eave height Warm Storage bldg.40 1 x 80'x 20'eave height Ut i1i ti es bldg.50 1 X 60'X 16 1 eave height Living quarters (except C.S.2 &7)30 1 X 60'x 16'eave height Flammable Liquids Bldg.15'x 20'x 10 1 eave height Living quarters (C.S.2 &7)30 1 X 100'X 16 1 eave height Office (C.S.2 &7)20'X 30'X 8 1 eave height Shop and Warehouse (C.S.2 &7)70'x 70'X 20'eave height Hallways 6 1 -8 1 wide x 10 1 eave height Meter b1 dg.40'x 50'X 20 1 eave heigh.t Generator b1 dg.10 1 X 15 1 X 10 1 eave height Control b1 dg.10'x 15'x 10'eave height 2648B 4-16 r L ~[ [ [ [ ~ [ L' L L L r- [.. [ [ L [. [~. f' L. [ 8 [ l U [ [ L [ [ 2648B TABLE 4-5 COMPRESSOR AND GAS SCRUBBER DETAILS FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST Main Compressors - 1 each per compressor station a.Compressor -1280 psig min.design pressure 1.23 pressure ratio 6000 ft.adiabatic head 2750 ACFM b.Gas Turbine Driver -3800 ISO Horsepower gas fueled c.Typical Equipment -Solar Centaur Gas Turbine Natural Gas Compressor Set with a C-304 Single Stage Compressor,or equal. Gas Scrubber -(l )each per station a.Designed to remove 99.5%of all solid and liquid particles 1 micron and larger. b.Design flowrates will range from 130 to 400 MMSCFD. c.Typical Equipment -Peco Robinson filter and liquid-gas separator,Model 75H-56-FG372,or equal .. 4-17 TABLE 4-6 REFRIGERATION SYSTEM AND GAS HEATER DETAILS FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST Refrigeration System a.Refrigeration system will be a compression/expansion type using Freon gas and a gas turbine driver for the refrigerant compressors. b.Chillers will be shell and tUbe with natural gas in the tubes at 1280 psig and Freon in the shell. c.Condensers will be air cooled with multiple electric driven fans. d.Required capacity will be 2200 HP. e.The system will be comprised of two parallel 50%refrigeration trains to meet the total requi red capaci ty. f.Typical Equipment -Two (2)1100 HP refrigeration trains using Solar Saturn Gas Turbine Compressor Sets,or equal. Gas Heater -One (1)each at Compressor Stations 2 and 4 only a.Designed to add 5,000,000 Btu/hr to heat the pipeline gas during low flow winter conditions. b.Equipment will be a gas fired heater and utilize a water/glycol solution to heat the gas in a shell and tube heat exchanger. 2648B 4-18 [ [ [' [ f' r L [ [ l [ [ [ L ,~~ L L L L L [' [ L [ L [ [ r f' L [ [ C E C [ L [ L l TABLE 4-7 COMPRESSOR STATION ELECTRICAL SYSTEM AND CONTROL SYSTEM DETAILS FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST Electrical System a.Each station will be self-sufficient in electric power with its own power generation and distribution system. b.Power will be 480 V.,3 phase,60 Hz. c.Main genera~ors will be two (2)800 KW continuous duty dual-fueled gas turbine driven generator sets,one will normally supply the station load and one will be standby. d.Emergency (lifeline)generator will be one (1)200 KW diesel engine driven generator connected to the essential services bus. e.The emergency generator will be located in the warm storage bUilding or another location remote from the main generators in the utilities building. f.Typical Equipment: r~in generators -Solar Saturn GSC-1200,or equivalent Emergency generator -caterpiller 3406 TA,or equivalent Control System a.Each station will have a control system designed for completely remote and unattended operation. b.The station Central Control Unit '(CCU)will be linked by communications to the Operations Control Center (OCC)~ c.Each individual piece of station equipment will have its individual control system which in "turn will be controlled by the CCU which is the master controller. d.The OCC input to the CCU will primarily be start/stop commands and setpoint changes. e.The oec will have sufficient information transmitted to it to allow for full compressor station control. 2648B 4-19 TABLE 4-8 MISCELLANEOUS COMPRESSOR STATION SYSTEMS·DETAILS FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST a.Blowdown and Flare System will be sized for 100,000 lb/hr.of saturated light hydrocarbon gases and liquid storage capacity of 10,000 gallons. b.Nitrogen Purge System -for purging. c.Instrument and Utility Air System -Instrument air to be clean and dry for operating pneumatic control system components. Utility air for power tools and maintenanc~. d.Fuel Gas Conditioning -Gas for station fuel requirements will be filtered,heated,reduced in pressure,and distributed at 500 psig. e.Diesel Fuel - A diesel fuel storage and back-up fuel system will be provided for electric power generation and heating. The tank size will be 40,000 gallons to provide 14 days of capacity. f.Fire Protection -Station fire protection will be provided by a Halon 1301 extinguishing system with a water/foam back-up system. g.Water System - A single 40,000 gallon water tank will provide a source of water for potable uses as well as for the back-Up water/foam fire system.The fire pump will be diesel driven. The potable water will be filtered,chlorinated,and distributed. h.Sewage System -Sewage will be collected by a vacuum collection system.Final disposal will be through a septic system or a lagoon as site conditions warrant.Lagoon disposal will reqUire secondary treatment ana chlorination. i.Heating System -The station will be heated by a water/glycol system utilizing waste heat from the station turbine generators.A combustion boiler unit will be provided as back-up to the waste heat system. j.Cathodic Protection - A cathodic protection system will be provided to protect all buried piping,tank bottoms,ana other structures in contact with the soil.The station will be electrically insulated by isolation flanges where the pipeline enters and leaves the compressor station property. 2648B 4-20 ;F' ·l_~. [ [ [ f [ .[ lJ [ U [ L C E C [ [ [ L L [ f~ [ .r [' r~ [' [' [ b f.; ., W E [ [ L L [ TABLE 4-9 METERS AND METERING STATION ELECTRICAL AND CONTROL SYSTEMS DETAILS FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST Meters a.Each metering station will have 3 parallel meters with provisions for future addition of a fourth meter. b.Meters will be concentric orifice plate with differential pressure transmitters. c.Meter runs will be 12 inch diameter by 3D'long. Electrical System a.Both metering stations will be powered by an outside cornmercial power source. b.A 50 kW diesel-powered back-up generator will automatically come on line during a power failure. Control System a.Designed for remote and unattended operation. b.Gas flow will be computed by a microprocessor-based flow computer with 100%redundancy. c.The flow computer will be linked to the acc by telecommunications • 2648B 4-21 TABLE 4-10 MISCELLANEOUS METERING STATION SYSTEMS'DETAILS FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST a.B10wdown drum and vent stack system.. b.Nitrogen purge system. c.Diesel Fuel - A diesel fuel storage system will be provided for electric power generation. d.Fire Protection -Fire protection will be provided by a Halon 1301 extinguishing system with a water/foam back-up system. e.Heating System -Heating and ventilating will be by means of redundant gas-fired furnaces and warm air duct systems. f.Cathooic Protection - A cathodic protection system will be provided to protect all buried piping,tank bottoms,and other structures in contact with the soil.The station will be electrically isolated by isolation flanges where the pipeline enters and leaves the compressor station property. ,, \. 2648B 4-22 I'· l' [ r~ r l' f . l r:L. [ [ [ [, G l [' L~ L L [ [ C [ [ f' [ L L [ The supervisory control system master station will be located near the Fairbanks power plant at the operations control center (OCC).A communication system will provide the voice and data intertie to each compressor and metering station from the OCC.Each station will include a control system that will interface through the communication link to the acC. Tne DeC in Fairbanks will include the dispatcher console,which will provide the monitoring and control equipment necessary for centralized operation of the pipeline. 4.1.5 Communications System The communications system will include voice and data transmission... systems,the mobile radio system,and record communications.A basic communication system will be installed during the construction phase to provide voice and data links among the pipeline and compressor station camps,and the Fairbanks construction headquarters. MObile radio equipmen~will be provided to permit communication by field construction teams through a network of repeater stations to the camps, stations and other facilities.This basic communication system will later be modified to provide the operational communications system.This operational system will support the supervisory control system.Data communications will also be provided. 4.1.6 Operation and Maintenance Facilities Operation and maintenance (O&M)facilities will be located at three sites along the pipeline:Compressor Stations 2 and 7,and the Fairbanks operations headquarters.Each O&M facility will include the following: (1)Warehouse for storing project spare parts inventory. (2)Maintenance shop,including maintenance equipment. (3)District office. (4)Living quarters for the O&M personnel. 26488 4-23 The Fairbanks operations headquarters near the power plant will also house the OCC,the related supervisory control equipment,required power supplies and the communications system equipment. Stations 2 and 7 will serve as shop and warehouse with both living qtlarters and maintenance facH ities.The other stations will have ·small 1 iving quarters attached.It is anticipated that a staff of 5 to 6 will serve at each compressor station except stations 2 and 7,wnich will have a total of 16 each,including 6 maintenance personnel.This would then require a total staff of 80 for the medium load forecast peak demand (10 stations)• 4.1.7 Construction and Site Support Services Temporary f~cilities will include those facilities requ~red to support the construction phase activities.These facilities will include the Fairbanks construction headquarters,the pipeline and compressor station construction camps,airfields,access roads,material (borrow)sites and di sposal sites. Thirteen pipeline construction camps will be provided along the route, including one located at the Fairbanks construction headquarters site. These camps will be capable of accommodating between 250 to 1,300 persons,depending on location and planned use. The camps,once completed,will be turned over to contractors for operation.The twelve camps along the pipeline will be renovated generally in place using equipment and modules obtained mostly from the existing TAPS camps.Three compressor station construction camps will be provided by relocating and renovating equipment and modules available from eight existing TAPS pump station camps. Airfields will consist of certain existing commercial airfields,as well as renovatea private airfields previously built in support of TAPS. Material (borrow)sites are available along the pipeline route to provide 26488 4-24 c L [ [ l [ r [~ [ r~ L [ U [ C U [ [ [ L [ construction materials,as well as areas to dispose of construction spoil.Maximum haul distances should be kept under 5 miles. A pipe yard at Fairbanks will be provided to receive mainline pipe, store,externally coat,double-joint (weld)and insulate pipe as required.Access roads will be provided as needed to allow access to stations,borrow sites,pipeline spreads and related facilities. 4.2 POWER PLANT The Report on System Planning Studies (Appendix B)concluded that combined cycle power plants are the most technically feasible and economical choice for satifying demand when generating electrical power at a Fairbanks site.The individual combined cycle plants will consist of two gas turbines,each with a heat recovery steam generator and one steam turbine for a total of three ~urbine-generator sets. 4.2.1 General The Fairbanks site will contain all required generating units, construction and maintenance facilities,various auxiliary and support systems,a central control facility and switchyards.This power generation scenario calls for five 242 MW combined cycle and two 86 MW simple cycle units to satisfy the demand for energy in the year 2010. The first unit,a simple cycle gas turbine,is required in 1993 and in SUbsequent years either gas turbines or steam turbines are added. Incremental and total required new generation capacity for this scenario are summarized in Table 4-11. A single combined cycle unit will require an area with outside dimensions of 300 feet by 440 feet.The arrangement of the three turbine-generator sets,the air cooled condenser and auxiliary equipment is shown in Figures 4-5.and 4-6.The site plan shown in Figure 4-7 illustrates the planned installation method (side by side)for up to six units with switchyards.This arrangement will require a total area of approximately 150 acres. 26488 4-25 TABLE 4-11 NEW CAPACITY ADDITIONS AND FUEL REQUIREMENTS FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST Ne\1 Capaci ty (MW)Gas Requi red!! Year (Increment/Total)O+'SCF) 1990 0/0 O. 1991 0/0 O. 1992 0/0 O. 1993 86/86 6,265.8 1994 0/86 6,265.8 .1995 86/172 12,531.6 1996 70/242 12,633.1 1997 172/414 25,132.7 . 1998 70/484 25,202.9 1999 0/484 25,202.9 2000 86/570 31,551.3 2001 0/570 31,467.3 2002 156/726 37,804.3 2003 0/726 37,804.3 2004 86/812 44,188.1 2005 156/968 45,809.0' 2006 86/1050 49,535.1 2007 86/1140 53,145.7 2008 70/1210 52,292.0 2009 86/1296 55,892.6 201 0 86/1382 59,424.8 l!Values as calculated are shown for reproducibility only,and do not imply accuracy beyona the 100 MMSCF level. 2648B 4-26 [ [ [ [ r f' [' f' LJ [' L [ L .[~ _I [ b L. L L L [ (~ r-l c:-J ~r-'i rJ ~~c-D IT')c:-l rrJ r:J r-:J r----',r-----.,~ U ."I I..,ii'III ,j l ,~ J ,'---'-"" ... . t l tV·-. I j IDll'Wooot I I ~""".. I---..........I PLAN -220 Mil NOMINAL RUING/COMBINED CYCL E PLANT IIr-f "'-'~ I JI ALASKA POWER AUTHORITY NOATH 'LOPE GAS 'EAS.ILlTY ,rUDY COMBINED CYCLE PLANT GENERAL ARRANGEMENT PLAN VIEW .BASCO IERYICES INCORPORATED ..j:>o I N CO I II .... l'l""0MI . I SECTION -8 -p ,. I, i"-MIIIIWMlSY'TACI..ri ....,~".~~._----_._.. • , I --__..=..~~::....".,,:.:.;.;:----.~ SECTIlJH -A (1 I MADI,'1lUIMlGCI. ALASKA POWER AUTHORITY NORTH IlOPE GAS fEASIBILITY STUDY COMBINED CYCLE PLANT GENERAL ARRANGEMENT ELEVATIONS '10""1 4-6 IBASCO IERVICES INCORPORATED 'r--:ltd 'I.,I' ~ii '>I) ALASKA POWER AUTHORITY , 2 !I.. S•T 8 ~O"OOI1PlfTI Q)t1LC''1CU UN"' ~ 700 1100 I~oo IqOO 2'&00 1'7t:lO 5~ 'DI"'~ION .~ TYP. CO~I"'P GYCl,.t MOPUL! ~6MI~101Il ltN;~ 10 l.Ot\'P C INTI!~!o r---~~-_.~~_~-=_=__~-._-~-=___=_.=~~_-----------tf----~ (tOEE PIM~"""'ION""'~ll)1 : -~D-·ff'fr-! +:'--0-[}'0-0 \\8 ,..~.-+ I ~l-EJ--D--DOD-D-'" 1!>6fiN#EA T f : I ""c;}&-25/64&II~AIUA*"OT~l,.ftlT~AC.~I I ~·t~~IJNIT••'110 i!J LJJrT!».·f 20t.11...,T&•'40 I I-----91TI ~Mmlt'~I ~Y400'I I &lNITS •'75I'2~~.mo("LtII~v(~2'!lI<VYAIlD)\'I wi I L---__----~-_\__~~~."*-~J ~!S'2~tN ~~11!>A"(~I(I!.NAI I.OCATIONI,:: i!l4~t('I mil FAIIl~6L.OCATIClN.t t *~~'MU'"D1MW!5IotJ~~H'rNi!J' J:> .. NORTH SLOPE GAS· FEASIBILITY STUDY COMBINED CYCLE PLANT SITE PLAN FAIRBANKS AND KENAI FIGURE 4-7 EBASCO SERVICES INCORPORATED The functional parts of the plant will be similar to those described in Section 2.0 for the gas turbine portion of the plant.The steam cycle will requi re the addi tion of neat recovery steam generators,steam and auxiliary system piping,a steam turbine generator,condenser,condensate polishing,water qUdlity control systems,and an increase in the quantity of water used. 4.2.2 Combustion Turbine Equipment All combustion turbine equipment will be identical to that described in Secti on 2.1. 4.2.3 Steam Plant The heat recovery steam generators (HRSG)are considered part of the steam plant although physically the steam generators will be housed together with the gas turbines in a large common building. Each heat recovery steam generator package,one at each gas turbine· eXhaust,will include the steam generator complete with ductwork from the combustion turbine to the steam generator,a uypass damper and bypass stack,and a steam generator exhaust stack.The steam generators will have a steam outlet pressure of 850 psig at 950°F.Each steam generator is designed to produce one half of the plant's normal flow for steam when supplied with feedwater at a temperature of 250°F.The heat recovery steam generators are designed for continuous operation.All steam generator controls will be located in a common area in the central control room. During start-up and other load conditions,the bypass damper may be operated to provide operational flexibility.By opening the bypass damper and closing the louvered dampers,the combustion turbine exhaust is routed to the stdck dnd does not reach the steam generator.Design parameters for the heat recovery steam generators are shown in Table 4-12.The flow diagram and anticipated heat balance for a single combined cycle unit is presented in Figure 4-8. 26488 4-30 [ [~ [ [ c:L [ C [ [ b [ [ ~•..~ L E rt Steam production under normal operation will be achieved with an exhaust "gas flow through the boiler of 2,286,000 lbs/hr at 970 0 F. Feedwater will be supplied to theHRSG at 250°F from the feedwater heater. Watertube,forced circulation TABLE 4-12 HEAT RECOVERY STEAM GENERATOR DESIGN PARAMETERS FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST (Two Required Per Unit) 850 psig,950°F 250,400 lbs/hr (Each Steam Generator) Main Steam Outl et Condi ti on Quantity Type: Performance: r L [ C b [ 6 [ [ [ l [ Heat Recovery Steam Generator Features Feedwater Heater Economizer Evaporator Section with Steam Drum Superheater Section- Econoini zer Evaporator Section with Steam Drum Exhaust Gas Bypass Dampers with Separate Stack 2648B 4-31 'HI""E 4-0 -_ML I.=~-=::O"'l.I=-.:=:.. •••,IlI1'PUT , a."'*'_..",... ---.....-... CONCIJOTUAL ONLY NOT GUARANTEED ---_...... NORTH SLOPE GAS fUSIBILITY STUDY COMBINED CYCLE PLANT FLOW DIAGRAM AND HEAT BALANCE ALA8KA POWER AUTHORITY ..,.,....,-")--....'a~TI••N.'.ICON.I.IT .r "..,.1...'. •-G:w:=>::: G4~-I \L".I1'IA.fOm"..~ •--I L.'.•tI_TO ........ _'Ito.•'...--.--.'a~l,..r_lc...., , •.•,JOY..,,, I L.r.DtKMiUtW '0 'LAIN rAIM-L -_.")-,--t !\11... '::."--..............I- :~-1Il.1:~"'.._"-('.~~J'\~)-..U"'l' ft~ftJ .L .c....<••,.,...,,, u_ ~:L ,I-- ~!:!AI2Il _INM_ a..-:.--\- L:~~.....,....,....Y L,p.fUO'!MTlII '.J:~.~~ M ~/f---(•.•...,.,,,'lIiUlIMf--/n(I!'MTQI L.:.............ITI..\...-...f'!.!fIr. )J LIQILU..1( •.Y,,,'\.....,.(•.41....'..',,7....IUI..,.. .,<~.{<IIIC.PUMP ~:,."" A'l "- ~=~-L--,', ITIAM TUI'lIINt: iEtlEBAn!Il Ci!!.!!!...------------ _.'''''''.11 io-m=..- •.11.'"j~_..'..YII_')." .,.~.:;:=--~----._- a.,_"..~~....1<': ----e ........,.."•.•M~....,,~)-, , ..L-l~~«l L.--. ~.1 <1 [:"V'' tAl TUftlIHE m::IL-:~~!'ILIt~IQ!!NO.1 --L.--m'.-=r.t- UCH....".~'.'M.•~ ----~---------------L~I -------------- ~-J G~----~------------COflOlMMl1l ,....ItMMIIlMI ".I'"'11tO -.... ,......... _..-.. TO __ ,.......---........ ........- t rrna-w .ATI..'''''IUIOII N 'UlL.,..--- .tAICO IEfMCEllNCOAPOAATED ~'r-lL.....j ••,"~II-----------',---- ,..", , The generator is rated 72 MW.The unit auxiliary transformer is a three winding 15 MYA,13.8/4.16/4.16 kY.The two secondary windings supply 4.16 kV buses 3A and 3B.The step-up transformer is rated 50 MVA,18/138 kY. The main steam produced in the heat recovery steam generators will be conveyed to a common turbine generator set.The turbine generator will be a tandem compound,multistage condensing unit,mounted on a pedestal with a top exhaust going to the air cooled condenser.Design parameters for the turbine generator are shown on Table 4-13.The turbine generator set will be furnished complete with lUbricating oil and e1ectrohydraulic control systems as well as the gland seal system, and the generator cooling and sealing equipment. In addition to the combustion generators,steam generators and steam turbine,-the building will also contain the feedwater pumps,condensate pumps,vacuum pumps,deaerator,instrument and service air compressors, motor control centers,control room,and diesel generator (see Figure 4-5).The diesel generator will be sized for black start-up service. Heat will be rejected from the steam turbine cycle at the outside mounted air-cooled condenser where air flowing across cooling fins absorbs heat from the exhaust system.The condensate from the condenser will then flow to the condensate storage tank where it will be pumped back into the cycle. Fuel requirements for this scenario will start at approximately 6.27 BCFY in 1993,when the first gas turbine starts delivering power,and increase to 59.43 BCFY in the year 2010.The maximum anticipated gas consumption rate,in the year 2010,with 1382 MW of capacity in operation,is 1.88 x 10 5 SCFM.Detailed annual gas use figures are presented in Table 4-11. 2648B 4-33 TABLE 4-13 STEAM TURBINE GENERATOR UNIT DESIGN PARAMETERS FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST (One Required Per Unit) Turbi ne Type:Multistage,straight condensing,top exhaust Hydrogen-cooled unit rated 72MW at 13.8 kV with 30 psig hydrogen pressure at lOGe Generator Type: Performance:Base Rating Steam Inlet Pressure Steam Inlet Temperature Exhaust Pressure Exh~ust Temperature Speed 72 MW 850 psig 950°F 211 to 4 11 Hg 108°F 3600 RPM c' l r~ r: l" Steam Turbine Generator Features: 26488 Common base mounted with direct-drive couplings.Accessories include multiple inlet control valves,electric hydraulic control system,lUbricating oil system with all pumps and heat exchangers for cooling water hook-up,gland steam system and generator cooling.Excitation compartment complete with static excitation equipment. Swi tchgear compartment compl ete wi th generator and breaker potential transformers.. 4-34 [ L [ r, L L L f' r I~ ( le,"-- / ('C [ L [ [ [ C C [ F.' L L [ 4.2.4 Substation The circuit diagram of the powerp1ant sUbstation is shown in Figure 4-9.It is quite similar to the North Slope sUbstation (Figure 2-3).Two generators will be connected to the two primary windings of the 250 MVA 13.8/138 kV·transformers,and the last generator to a 125 MVA two winding transformer.The bus arrangement will use a breaker and a half scheme unless reliabi1 ity considerations mandate otherwise.One 600 MVA 138/345 kV transformer will supply each of the transmission line circuits.Each of the transmission lines will. have a circuit breaker.On the line side of the circuit breakers are the series capacitors and the shunt reactors.This arrangement has the advantage of being flexible as far as operation is concerned and can be expanded easi 1y. 4.2.5 Other Systems In addition to the potable and service water system described in Section 2.1,this plant will require make-up water for the steam cycle.To purify the make-up water a demineralizing system will be required. B1owdown from the HRSGs and waste from the demineralizer and the condensate polisher represent additional waste handling capacity requirements over and above that previously discussed (Section 2.1). These waste streams will require treatment,in accordance with regulation,prior to discharge. Other systems such as fire protection or lUbricating oil will not change in scope or capacity to any significant degree from those presented in Section 2.1. 2648B 4-35 22 St2 22 22 22 22 22 22 'HIlMI:4-. 2 110 MVA IIASCO .ERVICES INCORPORATED FAIRBANKS POWER GENERATION MEDIUM LOAD FORECAST SUBSTATION ONE LINE SCHEMATIC ALASKA POWER AUTHORITY NORTH 'LOPE GAS FEASIBILITY ,TUDY LOCAL .345 kV ~II LOCAL TO ANCHORAGE 220 MVA TYPICAL 600 MVA TYPICAL 75 MVAR 1TYPICAL III--'W\r- LEGENDoGENERATOR =ORI'tn"TRANSFORMER o C.IRCUIT BREAKER .JV\I\r-REACTOR ~CAPACITOR +:=0 I W 0'1 ~..,...-...-r---r-l [ill ~c-l rrl .~rn r--=J r---,~r----,-.-~:-J .:--] I:.L ,J.'.,J ; c [1 C [ L~ [ C L L L 4.2.6 Construction and Site Support Services The construction of this power plant in the Fairbanks area will require the following services: (l)Access Roads (2)Construction Water Supply (3)Construction Power Supply All new roads will be of similar design to existing public roads in the Rai1belt.The roads will be paved,and will meet all code design requirements for the maximum loads expected. A complete water supply similar to that described in Section 2.1 will be provided,except the source of water will be wells.The construction power supply will be a 12.47 kV line run from existing facilities. Since a permanent construction force will be utilized through the period of the study,it is assumed that the local area can supply living accommodations for the work force.The number of workers necessary for construction of the power station will vary over the total period of the project from a low of 50 to a high of approximately 200.Construction facilities required are:utility services;temporary construction office; temporary and permanent access roa~s;temporary en~l~sed and open laydown storage facilities;temporary office and shop spaces for various sUbcontractors;sett1 i ng basins to collect constructi on area storm runoff;and permanent perimeter fencing and security facilities. 4.2.7 Operation and Maintenance Pl ant Life Each unit will have a 30 year life expectancy,which is based on the life of the gas turbine units.It is expected that the gas turbine units will be overhauled a number of times throughout the 1ife of the units during scheduled or unscheduled outages. 26488 4-37 Heat Rate of Units The facility's heat rate will vary,depending on the number of gas turbines and heat recovery units operating at a given time.Ideally, with only combined cycle units in operation,a heat rate of 8290 Btu/kWh (HHV,ambient conditions)can be realized. Scheduled and Forced Outage Rate It is expected that the forced outage rate will be about 8 percent. Operational experience on other plants indicates higher forced outages in the first few years,but this is attributed to operational adJustments required for a new plant.It is expected that a slight increase in forced outages will Dccur as the plant ages.Scheduled outages for annual maintenance and periodic overhaul are expected to be approximately 5 percent. Operating Workforce The combined cycle power plant will require a con.tinuously increasing staff over the s~udy period.The staff will start at approximately 10 on-duty personnel when the first gas turbine begins operation and will increase to approximately 80 on-duty personnel in ~he year 2010. 4.2.8 Site Opportunities and Constraints Fairbanks represents the nearest location to which North Slope gas can be transported to and have the resulting generation of electrical energy be fed directly into an exis~ing portion of the Railbelt electric transmission network.Transportation of heavy equipment to the site do~s not represent technical problems;however,the location will require expensive overland transport from the port facilities at Anchorage. 2648B 4-38 rt r-' l r l--e L l [ [ C L [ L L L l c [ [ C U [ L L L [ 4.3 TRANSMISSION SYSTEM The power to be transmitted from Fairbanks to Anchorage equals the power generated less the Fairbanks area load.This amount is the same as the North Slope generation scenario,except for the line losses between the North Slope and Fairbanks,which are not significant when compared to the power generated.Therefore,the conditions for the Fairbanks to Anchorage transmission line are almost exactly identical for both cases and consist of two new 345 kV lines,and an upgrade of the Wi 11 ow-Anchorage and Healy-Fa i rbanks segments of the Interti e from 138 kV to 345 kV (Refer to Section 2.2). 4.4 FAIRBANKS GAS DISTRIBUTION SYSTEM 4.4.1 Fairbanks Residential/Commercial Gas Demand Forecasts The following paragraphs are a summary of the study performed by Alaska Economics Incorporated to forecast residential and commercial gas demand in Fairbanks.The text of this report appears in Appendix E. The potential residential and cOl1lllercial demand for natural gas in the Fairbanks area is dependent on the price competitiveness of natural gas with respect to No.2 distillate fuel.oil and propane in heating and ."water heating markets,and its price competitiveness with propane and. electricity in cooking applications.The potential demand of natural gas as a cooking fuel is estimated to be less than 5.0 percent of the total potential demand for natural gas even if the gas were to fully displace bottled propane in commercial cooking applications. The forecasts of potential gas demand have been made conditional on the gas achieving discrete percentages of the total market for heating and cooking energy flO percent,25 percent,40 percent,and 100 percent displacement of fuel oil and propane.in heating and of propane in cooking).The size of the total market to which these percentages have been applied "has,in turn,been projected to grow at a 1.43 percent annual average rate from 1981 for the low growth forecast,and at a 2.30 26488 4-39 percent annual average rate for the medium growth forecast.These growth rates are the rates of Fairbanks population growth implied,respectively, by Battell e IS (1982)low forecast of the demand for e1 ectricity in the Rai1be1t area,and Acres American1s (1981)medium forecast of Rai1be1t electricity demand. The prices at which residential and commercial users would have a minimum financial incentive to convert from fuel oil to natural gas for heating purposes have been derived.These "consumer breakeven ll prices are based upon the assumption that the maximum discounted payback period for consumers is 5 years.At the 1982 price of No.2 distillate,$1.22 per gallon,the calculated consumer break even prices are $9.58 per MCF for residential heating and $9.94 per MCF for commercial heating.These prices will rise annually at approximately the real (inflation free)rate of increase ~f fossil fuel prices in general.If this rate is the 2.0 percent real rate assumed by Battelle (1982)and Acres (1981),by the year 2010 the breakeven prices in (1982 dollars)will have reached $16.68 per MCF (residential)and $17.31 per MCF (commercial). The presence of calculated breakeven prices is necessary for the forecasting of natural gas demand.However,break even price data and price elasticity data are insufficient for such a forecast in this case. These price and e1 astici ty data are insuffici ent because the situati on involves a new product (natural gas)competing with an existing product (e.g.,distillate oil,propane).Additional factors influence consumer demand inc1uding:.(1)consumer perceptions of the two products; (2)consumer inertia;(3)initial and/or unusual incentives offered by suppliers of the competing fuels based upon their calculated present worth of achieving certain market shares;and (4)other less defined factors.Because of these unquantified factors,conditional demand estimates have been forecast;and these are based upon price analysis alone. If natural gas is priced below the consumer breakeven level,users will have an increased financial incentive to shift from fuel oil.For every 10¢by which the price of gas falls below the breakeven level, 2648B 4-40 r l C L r~ L- r [ b C [, L L L L residential users will realize approximately $81.00 (1982 dollars)in additional savings over the estimated cost of conversion.It might be expected that extensive inroads against fuel oil will begin to be made if gas is priced sufficiently below breakeven so as to cover conversion costs and to achieve a significant level of savings (measured as the excess of the present value of annual cash savings over conversion costs). It must be recognized that the producers and suppliers of fuel oil are likely to respond to the intrusion of natural gas by either lowering the price of No.2 distillate or by offering other incentives.While the intensity of reaction by oil suppliers cannot be forecast,it can be assumed that suppliers are capable of at least offsetting the price advantage that natural gas has traditionally enjoyed based on its reputation as a "c1ean"fuel.Theref~re,the above calculation of consumer breakeven prices correctly ignores the fact.thqt many consumers might be willing to pay a premium for such natural gas properties. DELIVERED GAS,BCF PER YEAR 1985 2010 The conditioned demand projections derived are presented in detail in Appendix E and are summarized below for the medium growth projection.L [ [ C MARKET GROWTH @ 2.30 PERCENT 10%of Market 25%of Market 40%of Market 100%of Market 0.527 1 .319 2.110 5.274 0.931 2.328 3.726 9.314 These values represent the annual demand for delivered gas conditional upon the pertentage of market penetration indicated,where the total market,defined in terms oT effective MMBtu'~/is set equal to 100 !!Effective MMBtu's (million Btu's)are delivered MMBtu's adjusted for the fuel burning efficiency of heating ·units and cooking units.For example,if oil burners are 65 percent efficient,one delivered MMBtu equals 0.65 effective MMBtus. 2648B 4-41 percent of cOlllJ1ercial and residential heating energy requirements plus 29 percent of residential cooking energy requirements.The delivered gas demand values were calculated based upon different thermal efficiencies for oil and gas fired units. [ [ ·The demand for gas would not be constantly distributed throughout the year.Based on an appraisal of normal monthly heating degree days in Fairbanks,and an assumed indoor temperature setting of 6So Fahrenheit, approximately 16.6 percent of annual Fairbanks heating energy is consumed in January,the peak month for demand.1/Although cooking energy requirements may be more evenly spread across the year,the relatively small size of cooking demand,less than 5.0 percent of the total,suggests rather strongly that an apportionment of total demand dccording to the conductive heat transfer formula will yield a good estimate of peak monthly dem~nd.Use of this method implies the foll owi ng peak monthly demand (January)for natural gas in Fai rbanks for the medium growth projection. [ f'e, r'L 2648B 4-42 DELIVERED GAS,BCF PER PEAK MONTH January January 1985 2010 1/Heat loss is proportional to the indoor-outdoor temperature differential and inversely proportional to the insulation factor. At an indoor temperature setting of 6So Fahrenheit,relative monthly heating degree days is the appropridte measure of relative monthly heat loss. [ [ [ L L' [ L L L t' 0.155 0.386 0.619 1.546 0.087 0.219 0.350 0.875 10%of Market 25%of Market 40%of Market 100%of r~d rke t MARKET GROWTH @ 2.30 PERCENT Peak daily demand during the month of January can reasonably be estimated as 0.0322 (1/31)of the monthly demand times a factor that allows for extremes of cold.Between 1961 and 1982,the highest number of January heating degree days recorded in Fairbanks was 3002 (in January 1971).The January average was 2384.The ratio of the two DELIVERED GAS,BCF,PEAK DAILY January January 1985 2010 Peak hourly demand,defined as 0.0417 (1/24)times peak daily demand is quite small.For example,in the maximal case of 2.30 percent growth and 100 percent market penetration,the peak hourly demand is only 0.0026 BCF,or 2,600 MCF. (l.26)when mu1ti·p1ied by 0.0322 yields an appropriate measure of peak daily demand when their product is in turn multiplied by peak monthly demand.Thus,peak daily demand equals 0.0406 times peak monthly demand.The daily peaks are given in the following table for the medium growth projection: [ [ I' L [ [ [ C MARKET GROWTH @ 2.30 PERCENT 10%of Market 25%of Market 40%of Market 100%of Market 0.004 0.009 0.014 0.036 0.006 0.016 0.025 0.063 [ [j C C G~ r..'.~·L,' U L~ L [ Finally,expansion of the Fairbanks steam district heating system could reduce the demand for natural gas below the estimates presented above. On the assumption that the district heating system supplies only commercial and government users,the implied reduction is at most 15.0 percent of the estimates given above,since commercial use of gas is projected to be at most 15.0 percent of total demand. 4.4.2 Fairbanks Gas Distribution System The Fairbanks natural gas transmission and distribution system will be designed in conformance with Part 5,Alaska Public Utilities Commission,Chapter 48,Practice and Procedures;Federal Safety Standards for Transportation of Natural Gas and Other Gas by Pipeline, 49 CFR Part 192,Latest Revision;and the American National Standard Code for Gas Transmission and Distribution Piping ·Sys.tems,B 31.8, Latest Edition. 2648B 4-43 The overall system network will consist of a transmission lateral from a metering station near Fox to a City Gate Station with a minimum inlet pressure to the gate station of 250 psig,a 125 psig high pressure system to distribute gas to district regulators,and a 60 psig maximum distribution system to carry gas to individual customer services. Generally,the rural facilities will be considered in Location ~ass 3, and those in the urban areas in Location Class 4. 4.4.2.1 Gas Transmission Line The gas transmission line will connect to the 22-inch pipeline near Fox (Figure 4-10).The line will b~in public right-of-way,adjacent to the traveled roadway.The line will follow the Steese Highway to the intersection of Farmers Loop Road to the City Gate Station.This is approximately 12 miles of transmission line. As load develops north of the Chena Hot Spring Road along the Steese Hi ghway and McGrath Road,a secondary tap and gate stati on mi ght be considered at the intersection of Chena Hot Spring Road and the Steese Highway for service to this northern load,and as a back feed to the McGrath and Farmers Loop Road facilities. .The transmission line will operate at the main pipeline pressure of approxilllately 1,000 psig at the take-off point and have a design pressure of 1,260 psig.The gas flow will be metered at the take-off poi nt. The transmission line has been designed to provide peak hour coverage for commercial and residential customers in the year 2010.At this point,depending on actual growth and the location of additional supply sources,the transmission line may have to be supplemented.The 2010 peak hour projections were used to detennine the range of transmission line sizes required. 26488 4-44 [ L [ [ [ [ [~ r.'--,L, L L~ L L , ( i '.'11..,G:.,,.].~J;;,;I,i,,,.il r- I J , tlll'll UHlur.) I If If](IIJI,I(')[IUti. _____--::::::==-::.-:.;-~~~~:gf:III 1 ~~fflANI(~~rc's1~i?f'At(S INC ,If II 'lr-_~"'-'()IWWII 'NC'''''''''',''''''' :[''11.1 I III LEGENDL,..'"",,,~H_'_J.~.:.~::]J II I ~~~:~~~NTERS NOTES. I HIGH PAESSunE DIS1RlDlHION FROM CHY OAT(STATION At 125 "SIO 2 LOW PRESSURE DIS1RIJunON FROM LOAD CENTER AT 60 PSKJ 3 LOAD Cf.NT£RS 0.@.ANO@ FOR fUTURE U~E ALASKA POWER AUTHORITY NORTH ILOPE GAS FEASIBILITY STUDY CITY OF FAIRBANKS GAS DISTRIBUTION "0""(4-10 (BASCO SERVICES M:~ATED 4.4.2.2 City Gate Station The City Gate Station will be designed for an incoming gas pressure of 1,260 psig.TIle normal incoming operating pressure.could drop as low as 250 psig during the medium forecast peak daily flowrates.The outlet pressure Will be 125 psig.Gas heating equipment may be required to prevent the gas temperature from dropping below _20 0 F. The vicinity of the intersection of Farmers Loop Road and the old Steese Highway appears to be a suitable location for the City Gate Station.No specific inquiries were made as to availability and cost of vacant land in the area.The station will be above ground and can be accommodated on an average city lot. United States Geological Survey (USGS)maps indicate that this is a pennafrost area.One test bore in the immediate area indicates that permafrost begins at a depth of 19 feet.Further analysis will have to D~made to determine soil and founuation conuitions before any land commitments are made. Gas metering,conditioning,pressure reduction and flow control are the basic functions that will take place at the gate station.It is anticipated that the meter runs,control valves,odorization equipment and instrumentation devices will be indoors.A single story concrete block or insulated corrugated metal building approximately 20'x 50· would fulfill the requirement. Gas purity is a major concern to distribution companies and specifications are incorporated into gas purchase contracts.The North Slope gas conditioning facility,however,will produce a pipeline gas that meets typical specifications for domestic and commercial natural gas.It is therefore assumed that the only gas processing required at the gate station will be particulate and liquids removal carried over from the North Slope to Fairbanks pipeline after primary processing has been accomplished. 2648B 4-46 r f, r r l [ [ [ r:1 61 [~ [. f... [~i fl~'- r L r'L [ [ [ C·~ .._-~ L [ C' l~~ [ L L Suspended solids and liquids will be removed prior to pressure reduction by means of a conventional scrubber,and liquid resulting from the condensation phenomena accompanying pressure reduction will be removed by liquid knockout drip pots. A gas odorization system will be part of the gate station facilities. The system will be designed to maintain a relatively constant rate of odorizdtion with varying gas volumes.A liquid injection system based upon gas volume measurement is anticipated.The odorization rate will be in th~range of 0.25 to 1.00 pounds odorant per million cUbic feet of gas. Pressure reduction from 1,000 psig inlet pressure to 125 psig station outlet pressure will be accomplished at the gate station.Conventional pressure reducing valve(s)with pilots and bypasses will be used.The outlet of the gate station (inlet to high pressure system)will also be provided with overpressure protection.An atmospheric relief sized to relieve at the maximum allowable operating pressure plus 10 percent or series monitor regulation will be considered. Metering and gas flow control will take place at parallel meter runs. Station flow will be remotely controlled by the gas dispatcher from the headquarters office.Remote control telemetering will allow the station to be normally unmanned. 4.4.2.3 High Pressure System Tne high pressure system will operate at an inlet pressure of 125 psig from the City Gate Station.It is expected to traverse public rights-of-way adjacent to traveled roads as shown on the conceptual grid map (Figure 4-10).Laterals will branch off to load centers where pressure reduction and overpressure protection will be provided at ~istrict regulating stations.From these regulator stations,gas will be distributed to the individual 60 psig networks. 26488 4-47 HIGH PRESSURE SYSTEM MAINS . Individual high pressure mains are sized based upon peak hour load center estimates using the Spitzg1ass high pressure formula.The sizes and footages of the high pressure mains based upon the preliminary network analysis are listed below.The high pressure system will be standard wall API 5L GR.8 steel pipe as required.. Size 8" 10" 12" 14" 18" 4.4.2.4 District Regulators Length -Feet 6,000 15,000 27,375 7,500 District regulator stations will be 1pcated at the inlet to 60 psig distrioution networks as shown on Figure 4-10.These fifteen (15) stations will be designed to reduce the inlet pressure to 60 psig,and to provide overpressure protection for the distribution system.The method of overpressure protection (e.g.,atmospheric relief,monitor regulators,etc.)will be determined during final design. The type of construction and location of district regulator stations will also be determined during final design.The options of underground vault versus aboveground station construction must be reviewed with respect to considerations of the availability of public right-of-way,private easement,soil and groundwater characteristics, equipment operating capabilities and safety. 4.4.2.5 Distribution Systems The distribution systems as shown on Figure 4-10 will deliver maximum 60 psig and minimum 15 psig gas to individual customer services.The lines will be polyethylene pi'pe,PE 3408 per ASTM D 2513.The pipe will be SDR 11 for Class 4 locations and SDR 13.5 for Class 3 26488 4-48 nL [ L [ C b [ f~ [ l l locations.The smoother inside surface of plastic pipe allows the same sizes as steel pipe to handle the higher f10wrates.Individual lines will be sized using the Spitzg1ass formula.In general,distribution lines will be 2"as standard.Larger size lines will be the exception.Distribution lines will be valved to comply with code requirements and good operating practices. The distribution lines will be laid in pUblic rights-of-way at a depth of three feet to the top of the main.The lines will be laid on the opposite side of the road from existing or proposed water mains.The estimated footages by size of distribution mains are tabulated below. SCHEDULE OF DISTRIBUTION MAINS 4-49 2648B Services will be sized to deliver gas for maximum estimated demand of approximately 225 cubic feet per hour (CF/HR). Residential temperature compensated meters sized for this demand load must also satisfy the following specifications: Length -Feet 450,000 78,000 87,000 2,250 1,500 -0.5"Water Column (W.C.) -30°F -7"w.c. -_70 0 F .2" 4" 6" 8" 12" Size Maximum pressure drop Gas temperature In 1et pressu re Ambient air temperature Residential regulators sized to deliver the demand load at an inlet pressure range 15 to 60 psig and an outlet pressure of 6"to ]"W.C. will be specified for residential customers as standard. 4.4.2.6 Residential Services n L [ [ b C L [ [ l L [ Residential services will be standardized as welded and wrapped steel. The meter and regulator will,when desirable,be in the basement.The service will have a curb cock where the meter and regulator is indoors. If a service meter/regulator set cannot be placed indoors,consideration will ~e given to enclosing them in a metal or wooden,insulated and heated enclosure.In this case,a curb cock may not be required.The service head will be designed to allow for flexibility of movement due to frost heave and settlement. Services will be sized for a 1.5 to 3 psig maximum allowable pressure drop for inlet pressures of.15 psig minimum to 60 psig maximum. Assuming an average service length of 100 feet (allowing for equivalent length for fittings),and a 15 psig inlet pressure and a maximum 1..5 psig pressure drop,a 1/211 steel service has the capacity of 395 CF/HR at a specific gravity of 0.65 and a temperature of 30°F.This is in excess of the 225 CF/HR estimated maximum residential demand,and the allowable pressure drop is not exceeded.Therefore,a system standard of 1/2" service size will be used for the average residential customer. 4.4.2.7 Commercial/Industrial Services Commercial/industrial services will be designed and constructed following the same general procedures as for residential services.However,no attempt is made to standardize on size.Rather,each service will be sizea to meet its special load requirements.In addition,it is highly possible that some commercial/industrial customers may be better served from a 125 psig main.In these cases,the requirement of dual regulation or other secondary overpressure protection will be provided in the service design. 4.4.2.8 Headquarters Building The headquarters building will contain office space for the gas dispatch and operati~g personnel.It will also include telemetry for controlling 2648B 4-50 r L !~ [ [ [ Co L rL C L [ [ [ [ D [" [ [ L [ C L [ [ C C [ [ L C L gas flow at the City Gas Station.Building size will be approximately 25 1 x 50'single story,constructed of concrete block or insulated corrugated metal suitable for climatic conditions in Fairbanks,Alaska. 4.4.2.9 Cold Temperature Design and Environmental Factors The Fairbanks gas distribution facilities will be designed to meet or exceed the most stringent applicable minimum construction and safety standards.However,there are technical considerations which are not now specifically covered by code which must be investigated in great detail and solutions developed prior to final site selection ana completion of detailed design.In addition,there are environmental considerations which must be investigated and addressed more fully during the design phase of the project.Among these are: 1.Permafrost and Frost Heave 2.Field (hydrostatic)Testing 3.Cold Temperature Operation of System Components 4.River and Stream Crossings 5.Ice Fog Permafrost and Frost Heave United States Geological Survey data for the area of the gas distribution system has been reviewed.This review indicates that the distribution system will traverse three generalized units of subsurface conditions. These are the Tanana-Chena River Flood Plain,the Upland Hills,and the Creek Valley Bottom formations. The Tanana-Chena River Flood Plain consists of alternating layers of alluvial silt,sand and gravel.The top silt layers ranges from 1 to 15 feet thick.Permafrost is discontinuous and randomly located and.ranges in depth to the top from 2 to 4 feet in older parts of the flood plain, and to 25 to·40 feet in cleared areas.Where frozen,silt has a low to modera~ice content in the form of thin seams.The silt will develop 2648B 4-51 some subsidence when thawed,and may undergo intense seasonal frost heave.The portion of the distribution system lIin town ll is generally in the flood plain formation. Adjacent to the flood plain are gently rolling bedrock hills covered by from 3 to 200 feet of windblown silt (loess).The Upland Hills are generally free of permafrost although perennially frozen silt does occur along the base of most hills.Portions of the transmission lateral along the Steese Highway traverse this formation,as do portions of the distribution system along Farmers Loop Road. The valley bottoms of the upland contain silt accumulations that are perennially frozen and have high ice content.The depth to permafrost is from 1-1/2 to 3 feet on lower slopes and valley bottoms,from 5 to 20 feet near contact with the unfrozen silt zone,and from 10 to 25 feet in cleared areas. The seasonal frost layer is from 1-1/2 to 3 feet thick.Seasonal frost action is intense,and there is great subsidence when permafrost thaws. Sections of the transmission lateral along the Steese Highway as well as part of the distributi on system along Farmers Loop Road cross thi s formation.In addition,the proposed location of the City Gate Station is within the limits of the Creek Valley Bottom formation. The relation made between the distribution system and area geology above is based upon subsurface formation areas generally described on USGS Quadrangle Maps.Local variations may occur,particularly near the interface between formations.Therefore,a detailed analysis of soil conditions along the proposed right-of-way will be necessary to determine where and to what extent frost susceptible soil and/or permafrost exist. Final facilities location and design must be based upon flowing gas temperatures within the system and subsurface soil survey and analysis. Systems operating temperatures,at one extreme,may cause thermal degradation of permafrost,and at the other extreme frost heave may be 26488 4-52 r [' [ r' L [' [ r: L [ L [ L [ L L~ [ [ [ C L [ [ [ L [ the problem.In either case,specialized design may be necessary to assure that the integrity of the system and/or the environment are not jeopa rdi zed. Field (HYdrostatic)Testing The detailed design phase of the project will result in final determination of the pipe specifications for the project.These will be based upon the balance of service performance expectations and the economics of purchase and installation.At that time,the final code and permit requirements with respect to testing will be more exactly known. HYdrostatic testing will require that procedures and specifications address testing at ambient air temperatures below 32 0 F.,and dewatering ana IIdrying li of pipe lines after testing.In addition,cold temperature testing will require a review of brittle fracture mechanics for the specifiea pipe material. As generally designed now,the 60 psig distribution system would be pneumatically tested to 100 psig.The 125 psig high pressure system would be hydrostatically tested to 175 psig.The transmission lateral would be tested hydrostatically to 1.4 times the maximum operating pressure. System Component Operation The effects of subarctic temperatures and the temperature of flowing gas will require particular attention and perhaps specialized design to assure long,·trouble free operation of the system.Among the areas where special effort may be required are: Gas Meters:Diaphragm materials with acceptable lower operating temperature limit to _70 0 F.must be provided. Potential condensate problems must be analyzed. Shut Off Valve:LUbricant freeze up potentidls must be investigated. Valve box and operating nut accessibility in frozen snow and ice must be reviewed. 2648B 4-53 Regulators: Pipe Material:Effects of stress at cold temperature must be considered.Stresses resulting from cold temperature must be considered in design. Effects of cold temperature and condensate freeze up on diaphragm and valve discs must"be studied. River and Stream Crossings The conceptual system layout indicates that there are nine river and creek pipeline crossings.They are: Jesse1a Creek at Farmers Loop Road; Isabella Creek at Farmers Loop Road; Pearl Creek at Farmers Loop Road; Chena River at N.Hall Street; Noyes Slough at Illinois Street; Noyes Slough at Alder Avenue; Deadman Slough at Geist Road; Deadman Slough at Loftus Road,and Deadman Slough at Fairbanks Street. It is anticipated that the major crossings can be made using existing bridges.These will require close interface with highway officials and engineers.Specialized design for support,thermal movement, installation procedures,and protective coating may.be necessary. Those crossings for which a bridge crossing is not possible will require that stream flows,bed movement and scour,and potential fishery impacts be analyzed,and that appropriate design and construction procedures be developed accordingly. keF~ Ice fog is a serious and complex problem which is still being studied. Many solutions have been suggested to reduce the occurrence of ice fog. The principal focus has been on reducing water vapor emissions from the generation of heat and power.It is understood that as the quantity of water vapor released to this atmosphere is reduced,the temperature at which ice fog forms will decrease away from zero,thus decreasing the frequency of occurrence.Any design of a gas distribution system in 26488 4-54 [ [ [ C b [' [~ L L [ [ [ [ L [ [' [ PL [ [ U C 6 [ L' [ [ [ Fairbanks must include appropriat~measures to reduce water vapor released to the atmosphere. 4.5 COST ESTIMATES 4.5.1 Capital Costs 4.5.1.1 North Slope to Fairbanks Natural Gas Pipeline Feasibility level investment cost estimates have been prepared for the systems and facilities which comprise the North Slope to Fairbanks natural gas pipeline.Thes~estimates are presented in Table 4-14. 4.5.1.2 Power Plant To support the derivation of total systems costs which are presented in Section 4.5.4,feasioility level investment costs were developed for the major bid lin~s items cornmon to a 77 MW (ISO conditions)natural gas fireu simple cycle combustion turbine and d 220 MW (ISO conditions) natural gas fired combined cycle plant.These costs are presented in Tables 4-15 and 4-16.Tne costs represent the total investm~nt for the first unit to be developed at the site.Additional simple cycle units will have an estimated investment cost of $33,900,000 while additional combined cycle units will have an estimated investment cost of $127,430,000.The cost differential for additional units is due to significant reductions in line items 1 and 15,improvements to Site and Off-Site Facilities,and reductions in Indirect Construction Cost and Engineering and Construction Management. 4.5.1.3 Transmission Line Systems Transmission line feasibility level investment cost estimates for the Fairbanks to Anchorage connection are presented in Table 4-17.These estimates are based on two new 345 kV lines,in parallel,1400 MW capacity,with series compensation and an intermediate switching 26488 4-55 [ L TABLE 4-14 FEASIBILITY LEVEL INVESTMENT COSTS NORTH SLOPE TO FAIRBANKS NATURAL GAS PIPELINE FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST (January,1982 Dollars) Oesc ri pti onl./ Material s Cons~ructi on Total Oi rect ($1000)LaborJ ($1000)Cost ($1000) 22 in 0.0.Gas Pipeline 480,000 4,100,000 4,580,000 Compressor Stations -10 ea 96,800 83,400 180,200 Metering Stations -2 ea 2,800 6,000 8,800 Valve Stations -28 ea 2,500 3,800 6,300 Eng i neeri ng &Construction 286,500 Management SUBTOTAL $582,100 $4,193,200 $5,061,800 Gas Conditioning Faci1 ity 3/780,000 TOTAL CONSTRUCTION COST $5,841,800 [ [ !I A 15 percent contingency has been assumed for the entire project and has been di stributed among each of the cost categori es shown.r Sales/use taxes and land and land rights expenses have not been LJ incl uded. ?:./Construction camp facilities and services are sUbsummed in the C Constructi on Labor cost category. 3/Factored pricing basis which includes engineering and construction [ management costs. [ [ [' L 2648B 4-56 .[ [ r' [ [ [' [' r~ n L C L TABLE 4-15 FEASIBILITY LEVEL INVESTMENT COSTS 77 MW SIMPLE CYCLE COMBUSTION TURBINE FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST (January,1982 Do 11 ars) Construct;on Total Descri pti onl/ Materials Labor Di rect Cost ($1000)($1000)($lOOO) 1.Improvements to Site 405 1,240 1,645 2.Earthwork and Piling 195 345 540 3.Circulating Water System 0 0 0 4.Concrete 475 2,145 2,620 5.Structural Steel Lifting 1,725 1,370 3,095 Equipment,Stacks 6.Buildings 750 1,440 2,190 7.Turbine Generator 11,100 650 11,750 8.Steam Generator and Accessories 0 0 0 9.Other Mechanical Equipment 460 235 695 10.Pi pi ng 205 510 715 11.Insulation and Lagging 30 110 140 12.Instrumentation 100 70 170 13.Electrical Equipment 1,510 2,590 4,100 14.Painting,70 250 320 15.Off-Site Facilities 300 1,080 1,380 SUBTOTAL $17,325 $12,035 $29,360 "Freight Increment 865 TOTAL DIRECT CONSTRUCTION COST $30,225 Indirect Construction Costs 1,665 SUBTOTAL FOR CONTINGENCIES 31,890 Contingencies (l5%)4,790 TOTAL SPECIFIC CONSTRUCTION COST 36,680 Engineering and Construction 2,200 Management TOTAL CONSTRUCTION COST $38,880 1/The following items are not addressed in the plant investment pricing: laboratory equipment,switchyard and transmission facilities,spare parts,1and or 1and ri ghts,and sales/use taxes. 2648B 4-57 TABLE 4-]6 FEASIBILITY LEVEL INVESTMENT COSTS 220 MW COMBINED CYCLE PLANT FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST (January,1982 Dollars)0 Total Constructi on Direct Descri pti orJ/ Materi a1 labor Cost ($1000)($1000 )($1000 ) 1.Improvements to Site 425 1,295 1,720 2.Earthwork and Piling 570 1,050 1,620 3.Ci rcul ati ng Watet·System 0 0 0 4.Concrete 1,485 6,730 8,215 5.Structural Steel lifting 3,800 3,530 7,330 Equipment,Stacks , 6.Buildings 1,800 3,600 5,400 7.Turbi ne Generator 30,100 2;520 32,620 8.Steam Generator and Accessories 9,600 4,320 13,920 9.Other Mechanical Equipment 6,735 3,425 10,160 10.Pi pi ng 1,500 2,910 4,410 11.Insulation and lagging 290 690 980 12.Instrumentati on 1,700 290 1,990 13.E1 ectrica1 Equi pment 4,550 8,640 13,190 14.Painting 200 720 920 15.Off-Site Facilities 300 1,080 1,380 SUBTOTAL $63,055 $40,800 $103,855 Freight Increment 3,155 TOTAL DIRECT CONSTRUCTION COST $107,010 Indirect Construction Costs 4,235 SUBTOTAL FOR CONTINGENCIES 111 ,245 Contingencies (15%)16,685 TOTAL SPECIFIC CONSTRUCTION COST 127,930 Engin~ering and Construction 6,800 ptanagement TOTAL CONSTRUCTION COST $134,730 11 Tne following items are not addressed in the piant investment pricing: laboratory equipment,switchyard and transmission facilities,spare parts,land or land rights,and sales/use taxes. 2648B .4-58 or [ f~ r" l~ ~." C L [ L [. f.-.•·.'.'t---o 6 [" [ L [ [ 2648B 4-59 2/Assumes a cost of $40,000 per mile (Acres American Inc.1981). 26,557 104,024 23,260 521,580 112,039 83,144 $870,604 27,600 60,950 $959,154 Total' Di rect Cost ($1000) 12,445 41 ,716 10,960 305,085 78,361 83,144 $531,711 Cons tructi on Labor ($1000) Material (S1000) 14,112 62,308 12,300 216,495 33,678 $388,893 TABLE 4-17 FEASIBILITY LEVEL INVESTMENT COSTS FAIRBANKS TO ANCHORAGE TRANSMISSION SYSTEM FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST (January,1982 Dollars) Oescri ption.!! Switching Stations Substations Energy Management Systems Steel Towers and Fixtures Conductors and Devices Cl ear'i ng SUBTOTAL Land and Land Rights 2/ Engineering and Construction •Management TOTAL CONSTRUCTION COST !I The investment costs reflect two new 345 kV lines,1400 MW capacity,with series compensation and an intermediat~switching station and upgrading of 'the Willow-Anchorage and',Healy-Fa irbanks segments of the exi sti ng gri d to 345 kV.. C L [ [ C C G E [ [ [ [ 4.5.1.4 Gas Distribution System station.The investment cost estimates also reflect upgrading from 138 kV to 345 kV of the Willow-Anchorage and Healy-Fairbanks segments of the existing grid. Feasibility level investment cost estimates (January,1982 dollars) have been prepared for the systems and facilities which comprise the Fairbanks gas distribution system.The results of the analyses are given below.A 15 percent contingency has been assumed for the entire project and has been distributed between each cost category.Sales/use taxes and land rights have not been included. $59,700$48,200 Construction Total Direct Labor ($1000)·Cost ($1000) Materi a1 s ($1000 ) $11 ,500GasDistributionSystem 4.5.2.1 Gas Pipeline and Conditioning Facility .. Annual operation and maintenance costs (January,1982 dollars)for the· gas conditioning facilities are estimated to be as follows: Engineering and Construction Management TOTAL CONSTRUCTION COST 4.5.2 Operation and Maintenance Costs ITEM Salaries Maintenance Costs (Parts and Expendables) TOTAL 26488 4-60 3,582 $63,282 ANNUAL COSTS ($1000) $2,480 3,750 $6,230 [ [ [ [ [ [~ [ [ [ [ Annual operation and maintenance costs (January,1982 dollars)for the gas compressor stations and pipeline maintenance activities are estimated to be as follows: operation and maintenance costs for the combined cycle facility at Fairbanks are estimated to be $0.0040/kWh.These are based on discussions with operating plant personnel,history of similar units, Electric Power Research Institute data,published data and other studies performed. [ f~ f~ [ [ [~ L r ~ ITEM Salaries Maintenance Costs (Parts, Expendables,Other) 4.5.2.2 Power Plant Total ANNUAL COSTS ($1000) $4,400 5,850 $10,250 4.5.2.4 Gas Distribution System 4.5.2.3 Transmission Line Systems Annual operation and maintenance costs (January 1982 dollars)for the Fairbanks gas distribution system a~e estimated to be as follows: Annual operation and maintenance costs (January 1982 dollars)have been developed for the scenario's required transmission line facilities and total $12 million per year.These costs should be viewed as an annual. average over the life of the system.Actual OaM costs should be less initially,and will increase with time. ANNUAL COSTS ($1000) $1,290 500 $1,790 4-~ Total ITEM Salaries Maintenance Costs (Parts,Consumables,Other) 26488 [ [ C f~ L [ [ L [ [ 4-62 26488 [' L c: [ [ r: L [ L L L r (1) (2) PE/(P E +PR)=01 01 (I GC +I p)=ESCC Where peak natural gas demand for electricity generation peak natural gas demand for residential and commercial uses the proportion of investment costs charged to electricity generati on IGC =capital investment in the conditioning plant I Q =capital investment in the pipeline EsCC =e1 ectricservice re1 ated capi tal charges 4.5.4 Total Systems Costs 4.5.4.1 Cost Allocation Methodology Capital cost allocation is based upon the peak demand for natural gas, and consequently the capacity requirements of the ~ine.In this all oc ati on it is useful to make 'the c onservati ve assumpti on that both peak loads may occur simultaneously.Given that assumption,the following formulas can be used to allocate capital costs: 4.5.3 Fuel Costs For purposes of total system cost comparisons,natural gas pipeline and conditioning plant costs from the North Slope to Fairbanks must be allocated between electricity generation applications and residential/commercial customer applications.In this way the non-electric system costs can be removed from the total cost comparison associated with electricity supply.Two types of costs must be allocated:(1)capital investment costs;and (2)annual costs,including operation and maintenance (O&M)costs and fuel costs (e.g.,for pipeline compressor stations). For the economic analyses which foll ow fuel costs were treated as zero. This approach permits fuel cost and fuel price escalation to be treated separately;and makes possible sUbsequent sensitivity analyses of the Present Worth of Costs for this scenario based upon a range of fuel cost and cost escalation assumptions. 4-63 26488 Annual costs are allocated on an energy basis rather than on a capacity basis.Those costs are allocated by the following formula: Again,disaggregation may be accomplished for 0cVt1 or fuel costs;and this is accomplished by multiplying the 0A term by either SC OcVt1 or SC F•Again,only shared costs are considered,and user community- specific costs are not consi dered. (3) (4) (5) total shared annual charges shared O&M costs shared fuel costs annual natural gas consumpti on for el ectrici ty generati on annual natural gas consumption by residential and c onrnerc ia1 users the proportion of annual costs charged to electricity generation electrical service related annual costs SCA =SC OcVt1 +SC F ECE/(EC E T EC R)=0A 0A x SCA =ESAC ESAC = °=A Where: SCA = SC OcVt1 = SC F = EC E = EC R = Given these formulae,costs may be disaggregated.Costs may be al1oc.ated to residential and commercial users by substituting (1-01) for 01 and (l-OA)for 0A.Precise comparison of the electrical generation options can now be accomplished. The second formula arrives at the specific dollar value for allocation purposes.It can be applied either to I GC or I p separately when capital costs must be disaggregated by component,or as shown for the total capital burden.Neither formula is applied to investments that are specific to one user community (e.g.the residential gas distribution system),as those investment costs must be borne totally by the appropriate users. b L C C L [ [ L [ [ r~ L [ [ [" [ [' [ L rL 4.5.4.2 Power Generation System Costs The Fairbanks medium load growth scenario is far more complex than the Prudhoe Bay medium load growth scenario in that it,inc1udes:(1)d gas conditioning facility,(2)a natural gas pipeline,(3)power generation faci1iti~s,and (4)transmission line facilities. Further,the conditioning plant and pipeline facilities serve both electricity and residential/commercial markets.As a consequence,the capital,operating and maintenance,and fuel costs associated with the conditioning facility and pipeline must be apportioned to the respective user communities. The method for apportionment has been previously described (see Section 4.5.4.1)'On thi s basi s 01 and 0A val ues are cal cu1 ated (0 refers to the fraction of costs apportioned to the electricity segment of the natural gas market).0 1,the capital cost apportionment term,is calculated as follows for the medium load forecast: [ L 4-64 2648B 0A'the annual costs apportionment term,varies over time for the medium load forecast.Values for 0A are presented in Table 4-18. Gi ven the apporti onment tenns,the annual systems costs for the electricity generation system can be presented.The annual capital expenditures are shown in Table 4-19.The annual non-fuel O&M costs are shown in Table 4-20.The summary of total systems costs is presented in Table 4-21.The perlod of the analysis was assumed to be 1982 through 201 O. [ L [ [ [i_...-, [ L L L [ 63 MMSCFD 271 MMSCFD 334 MMSCFD 0.82= Total Peak Dai 1y F10\'I = Electricity Generation = Peak Daily Flow (2010) Residential/Co~aercia1 = Peak Da ily Flow (201 0) [ [ [ [ [ [ r·~. ..J [ C L [ [ C C E [ [ [ C [ TABLE 4-18 o VALUEsl/A FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST Resi denti al El ectri cal Total Calendar Demand .Demand Demand Year (BCFY)(BCFY)(BCFY)°A 1982 O.o.O.NA~/ 1983 O.O.O.NA 1984 O.O.O.NA 1985 O.O.O.NA 1986 O.o.O.NA 1987 O.O.O.NA 1988 O.O.O.NA 1989 O.O.O.NA 1990 O.O.O.NA 1991 O.O.O.NA 1992 O.O.O.NA 1993 1.219 6.266 7.485 0.84 1994 2.494 6.266 8.760 0.72 1995 3.827 12.532 16.359 0.77 1996 5.220 12.633 17.853 0.71 1997 6.676 25.133 31.809 0.79 1998 6.829 25.203 32.032 0.79 1999 6.986 25.203 32.189 0.78 2000 7.147 31.551 38.698 0.82 2001 .7.311 31.467 38.778 0.81 '2002 7.479 37.804 45.283 0.83 2003 7.651 37.804 45.455 0.83 2004 7.827 44.188 52.015 0.85 2005 8.008 45.809 53.817 0.85 2006 8.192 49.535 57.727 0.86 2007 "8.380 53.146 61.5L6 0.86 2008 8.573 52.292 60.865 0.86 2009 8.770 55.893 64.663 0.86 201 0 8.971 59.425 68.396 0.87 1/Val~es as calculated are shown for purposes of reproducibility only,and do not imply accuracy beyond 100 MMSCFD. ~/NA -Not applicable 26488 4-65 TABLE 4-19 .TOTAL ANNUAL CAPITAL EXPENDITURES FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST (Millions of January,1982 Dollars) Electricity Generat~al!Gas Calendar Transmission Conditioning Year Unlt A Unit B Line Pipeline Plant Total 1982 O.O.O.O.O.O. 1983 O.O.O.O.O.o. 1984 o.O.O.O.O.o. 1985 o.o.O.o.o.o. 1986 O.O.O.O.O.o. 1987 O.O.O.O.o.O. 1988 O.O.514.2 O.O.514.2 1989 O.O.118.1 1 ,383.6 O.1,501 !7 1990 O.O.232.4 1 ,383.6 319.8 1 ,935.8 1991 9.91Y O.94.5 1 ,383.6 319.8 .1,807.8 1992 33.90 O.O.O.O.33.9 1993 O.O.O.O.O.O. 1994 33.90 O.O.O.O.33.9 1995 56.97 O.O.O.O.57.0 1996 33.90 33.90 O.O.O.67.8 1997 56.97 O.O.O.O.57.0 1998 O.O.O.O..O.O. 1999 33.90 O.O.O.O.33.9 2000 O.O.O.o.O.O. 2001 33.90 56.97 O.O.O.90.0 2002 O.O.O.O.O.O. 2003 33.90 O.O.O.O.33.9 2004 33.90 56.97 O.O.O.90.9 2005 33.90 O.O..O.O.33.9 2006 33.90 O.O.O.O.33.9 2007 56.97 O.O.O.O.57.0 2008 33.90 O.O.O.O.33.9 2009 33.90 O.O.O.O.33.9 2010 O.O.O.O.O.O. Total $554.$148.$959.$4,15l.$640.$6,451 • !I Unit B denotes a second unit erected in any give year. 2/Incl udes all sit~preparation activities for multiple unit site. 2648B 4-66 [ r: [ c c [ L L [ C' -- TABLE 4-21 TOTAL ANNUAL COSTS FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST (Millions of January,1982 Dollars) Calendar Capital o &M Total Year Expenditures Costs Expendi tures 1983 O.O.O. 1984 O.O.O. 1985 O.O.O. 1986 O.O.O. 1987 O.O.O. 1988 514.2 O.514.2 1989 1,501.7 O.1,501.7 1990 1,935.8 O.1,935.8 1991 1,807.8 O.1,807.8 1992.33.9 O.33.90 1993 O.28.1 28.14 1994 33.9 26.1 60.04 1995 57.0 29.2 86.29 1996 67.8 30.1 97.94 1997 57.0 35.9 92.94 1998 O.37.7 37.77 1999 33.9 37.6 71.57 2000 O.40.5 40.54 2001 90.9 40.3 131 .24 2002 O.44.8 44.81 2003 33.9 44.8 78.72 2004 90.9 .47.4 138.30 .- 2005 33.9 49.1 83.03 2006 33.9 50.4 84.39 2007 57.0 51.5 85.43 2008 33.9 52.6 86.54 2009 33.9 53.7 87.63 2010 O.54.9 54.90 Total $6,451 •$755.$7,206. Present Worth @ 3%$4,965.$415.$5,380. 2648B 4-68 [ U [ r-: [ c [ [ [ L L L [ [ [ L [ [ [ nL. r~ L b U C C C [ L [ [ l For comparison purposes,the 1982 present worth of power generating costs has been calculated,assuming a real discount rate of 3 percent and excluding fuel costs.The present worth of costs,expressed in 1982 dollars,is $5.4 billion. 4.5.4.3 Gas Distribution System Costs The costs attributable to the gas distribution system are those costs not associated with electricity generation.The capital costs include a portion of the gas conditioning plant,a portion of the pipeline,and the Fairbanks residential/commercial gas distribution itself. Operation and maintenance costs,and internal fuel requirements,must be treated in a like manner. In Section 4.5.4.2 the values for 01 and 0A were presented. Allocation of costs to the gas distribution system require the presentation of (1-0)1 and (1-0)A values;and these are presented in Table 4-22.These are required because,by definition,1-0 defines the portion of costs associated with joint investments attributed to non-electric purposes. Given such values,the annualized expenditures associated with the natural gas distribution system can be calculated.These are summarized in Tables 4-23 through 4-25.The present worth of all costs associated with the distribution system,as of 1982,is $0.9 billion (January,1982 dollars),exclUding fuel costs.The period of the analysis was assumed to be 1982 through 2010. 4.6 ENVIRONMENTAL AND SOCIOECONOMIC CONSIDERATIONS Environmental effects associated with the Fairbanks power generation scenario will be similar in many re~pects to those of the North Slope scenario.Because the pipeline from-the North Slope to Fairbanks will be buried and chilled,it will result in different environmental effects and will require different types of mitigation than would a 2648B 4-69 2648B TABLE 4-22 APPORTIONMENT VALUES FOR THE GAS DISTRIBUTION SYSTEM FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST 4-70 [ L [ L [ [' r~ b f' L L L [ L L [-TABLE 4-23 TOTAL ANNUAL CAPITAL EXPENDITURES FOR THE GAS DISTRIBUTION SySTEM FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST ['(Millions of January,1982 Dollars) r Gas Gas r'Calendar Distribution Conditioning Year System Pipeline P1 ant Total ['1982 O.O.O.O. 1983 O.o.O.O. 1984 O.O.O.-0. C 1985 O.o.O.O. 1986 O.O.O.O. 1987 o.O.O.O. 1988 O.O.O.O.r 1989 12.66 303.7 O.316.4 l~1990 12.66 303.7 70.2 386.6 1991 12.66 303.7 70.2 386.6 r 1992 12.66 O.O.12.7 L 1993 12.66 O.O.12.7 1994 O.O.O.O. b 1995 o.O.O.O. 1996 O.O.O.O. 1997 O.O.O.o. 1998 O.O.O.O. G 1999 O.o.O.O. 2000 O.O.O.o. 2001 o.O.O.O. C 2002 O.O.O.o. 2003 o.o.O.O. 2004 O.O.O.O. C 2005 O.O.O.O. 2006 O.O.O.O. 2007 o.O.O.o. 2008 o.O.O.o. ~2009 O.O.O.O. 2010 O.O.o.o. [Total $63.$911.$140.$1,115. l [ [ 0_-2648B [4-71 TABLE 4-24 TOTAL ANNUAL NON-FUEL OPERATING AND MAINTENANCE COSTS FOR THE GAS DISTRIBUTION SYSTEM FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST (Millions of January,1982 Dollars·) Gas Gas calendar Distribution Conditioning Year System Pi pel ine Plant Total 1982 O.O.O.O. 1983 O.O.O.O. 1984 O.o.O.o. 1985 o.O.O.O. 1986 O.O.O.o. 1987 O.O.O.O. 1988 O.O.o.O. 1989 o.O.O.O. 1990 O.O.O.o. 1991 o.o.O.O. 1992 O.O.O.o. 1993 1.8 1.7 1.0 4.5 19:J4 1.8 3.0 1.7 6.5 1995 1.8 2.4 1.4 5.6 1!:I 96 1.8 3.0 1.8 6.6 1997 1.8 2.2 1.3 5.3 1998 1.8 2.2 1.3 5.3 1999 1.8 2.3 1.4 5.5 2000 1.8 1.8 1.1 4.7 2001 1.8 1.9 1.2 4.9 2002 1.8 1.7 1.1 4.6 2003 1.8 1.7 1.1 4.6 2004 1.8 1.5 0.9 4.2 2005 1.8 1.5 0.9 4.2 20U6 1.8 1.4 0.9 4.2 2007 1.8 1.4 0.9 4.2 2008 1.8 1.4 0.9 4.2 2009 1.8 1.4 0.9 4.2 2010 1.8 1.3 0.8 3.9 Total $32.$34.$20.$86. 2648B 4-72 [ L [ f~ b [ r L L L L L [ f- r~ L [ C,~ c' [ L TABLE 4-25 ANNUAL SYSTEMS COST SUMMARY,GAS DISTRIBUTION SYSTEM FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST (Millions of January,1982 Do11ars)_ Calendar Capital OBM Total Year Expenditures Costs Expenditures 1982 O.O.O. 1983 O.O.O. 1984 O.O.O. 1985 O.O.O. 1986 O.O.O. 1987 O.O.O. 1988 O.O.O. 1989 316.4 O.316.4 1990 386.6 O.386.6 1991 386.6 O.386.6 1992 12.7 O.12.7 1993 12.7 4.5 17 .2 1994 O.6.5 6.5 1995 O.5.6 5.6 1996 O.6.6 6.6 1997 O.5.3 5.3 1998 O.5.3 5.3 1999 O.5.5 5.5 2000 O.4.7 4.7 2001 O.4.9 4.9 2002 O.4.6 4.6 2003 O.4.6 4.6 2004 O.4.2 4.2 2005 O.4.2 4.2 2006 O.4.2 4.2 2007 O.4.2 4.2 2008 O.4.2 4.2 2009 O.4.2 4.2 2010 O.3.9 3.9 Total $1,115.$86.$1 ,201. Present Worth @ 3%$877 •$5l.$928. 2648B 4-73 transmission line through the same area.As in the North Slope scenario,power plant emissions will bea significant consideration because of existing air quality problems in the Fairbanks area. Environmental impacts caused by the transmission line from Fairbanks to Anchorage wi 11 be i denti ca 1 to those d.i.scussed ,for the North Slope scenario,Sections 2.5 and 3.5,and are not repeated here.Power plant characteristics related to environmental effects are summarized in Table 4-26. 4.6.1 Air Resource Effects Meteorological conditions in the Fairbanks area playa very important role in determining the ambient air quality levels in the area. Analyses of the Fai rbanks urban "hea't i sl and"have shown that winds are generally light in the winter and that wind directions 'change dramatically in the vertical direction during the wintertime.During the \'/inter months,the air near the ground is relatively cold,compared to the air aloft.This reduces mixing of the air i.n the vertical direction,and when combined with relatively light winds,often leads to periods of air stagnation. In large part due to the winter stagnation conditions,the Fairbanks area is'currently designated as a non-attainment area for carbon monoxide (CO).Emissions of CO are largely due to automobiles.The State Department of Environmental Conservation and the Fairbanks North Star Borough Air Pollution Control Agency are implementing a plan to reduce the ambient CO mainly through the use of vehicle emission or traffic control techniques.In addition,relatively high levels of nitrogen oxides have recently been monitored in the Fairbanks area. Only an annual average nitrogen dioxide standard exists,but the short term measurements of nitrogen oxides are as high as in major urban areas such as Los 'Angel es. The installation and permitting of a major fuel-burning facility,such as a power plant,will require a careful analysis of the impact of its 26488 4-74 [ L Air Environment TABLE 4-26 ENVIRONlwJENT RELATED POWER PLANT CHARACTERISTICS COMBINED CYCLE POWER PLANT FAIRBANKS POWER GENERATION -MEDIUM LOAD FORECAST Land Environment Plant Water Requirements 200 GPM Plant Discharge Quantity Less than 200 GPM including treated sanitary waste,floor drains,boiler blowdown and demineralizer wastes c. r' f r [ [~ r:- rL [ b [ C C [ [ [ [ L [. Emissions Particulate Matter Sul fur Di oxi de Nitrogen Oxides Physical Effects Water Environment Land Requirements Plant Socioeconomic Environment Construction Workforce Operating Workforce 26488 Below Standards Below Standards Emissions variable within standards - dry control techniques would be used to meet calculated NO x standard of 0.014 percent of total volUlile of gaseous emissions.This value calculated based upon new source performance standards,facility heat rate,and unit size. Maximum structure height of 50 feet 140 acres Approximately 200 personnel at peak construction Approximately 150 employed personnel 4-75 emissions on ambient air quality.Because Fairbanks is a non- attainment area,the operators of such a facility must demonstrate that they will reduce,or offset,impacts of the power plant by reducing emission levels of CO at other sources.Emissions .of CO from a natural gas fired power plant are relatively low,and any displacement of the burning of other fuels,such as coal or oil,will likely lead to improved air quality.'This arises from the clean burning nature of natural gas and from the fact that emissions from a major facility will be injected higher in the atmosphere (due to plume buoyancy)than the displaced emissions.During the very stagnant conditions in midwinter, the plume from a power plant will likely remain well aloft with little mixing to the surface layers.The complex urban heat island and associated wind pattern will require a great deal of in-depth modeling and analysis ~o determine air quality ~mpacts in terms that will wi thstand reg u1 atory scruti ny.. . A large combustion turbine power plant must meet the existing New Source Performance Standards and Best Available Control Technology. The nitrogen oxides limits will be the most constraining atmospheric pollutant.The operation of the power plant will also consume a portion of the allowable deterioration in air quality for nitrogen oxides.While it is possible that the power plant could be sited near Fairbanks,its installation would constrain other development efforts which also might consume a portion of the air quality increment.The nature,magnitUde,and duration of emission plumes must be studied as well as the potential for beneficial impacts due to reduced combustion at other sources within the area. The Fairbanks area is also SUbjected to extended periods of wintertime ice fog,and the Alaska Department of Environmental Conservation will require the impact of any water vapor plumes to be carefully assessed. A combustion turbine power plant which uses water or steam injection techniques would have an adverse impact on the ice fog and icing deposition nearby.For the purposes of this study,it is assumed that Best Available Control Technology would be defined to not include water or steam injection. 2648B 4-76 C L [ L [ r..c....~'.b C [ L L L [ [ r [ r"'Co [ [, [' r,,- r~ L [ L~ C L ~ [ L [ [ L Construction of the gas pipeline from the North Slope to Fairbanks will result in fugitive dust and exhaust emissions from construction vehicles.These air quality impacts will be temporary and located in very sparsely populated areas,and will therefore be insignificant. Ten comp~essor stations.~ill be located along the pipeline route,each producing relatively low levels of emissions.The impacts of these facilities will most likely not cause exceedances of the Alaska Ambient Air Quality Standards and will not be required to meet the Prevention of Significant Deterioration Increments.The emissions will not impact any air quality sensitive areas. 4.6.2 Water Resource Effects The gas fired combined cycle power plant described in Section 4.2 will use approximately 200 gpm of fresh water for boiler make-up,potable supplies,and miscellaneous uses such as equipment wash-down.Because ample groundwater exists in the Fairbanks area and because the water requirements are not particularly large,impacts on water supplies in the area will not be significant. Power plant wastes will consist of waSh-down water (for cleaning of equipment),sanitary wastes,boiler blowdown,and demineralizer regenerant wastes.The wash-down water will be treated for oil and suspended solids removal.Sanitary wastes will be passed through a sanitary wastewater treatment facility,and demineralizer wastes will be treated for pH control.No treatment should be required for boiler blowdown.The resultant wastewater stream,up to 200 gpm,will meet all applicable effluent guidelines and will be discharged to a local water body with sufficient assimilating capacity. The gas pipeline from the North Slope to Fairbanks will cross 15 major streams and rivers,inclUding the Yukon River,and could potentially impact num~rous additional small streams and drainages.The pipeline will be burfed for its entire length;vegetation will be disturbed within a 50 ft wide strip.Without careful siting and construction 2648B 4-77 practices,erosion from exposed areas could cause sedimentation problems in nearby water bodies. To control soil loss and sUbsequent sedimentation effects,several mitigation practices should be used during pipeline construction. Existing work pads,highways,access roads,airports,material sites, and disposal sites should be used whenever possible to minimize vegetation disturbance.Pipeline rights-of-way and access roads should avoid steep slopes and unstable soils.Hand clearing could be used in areas where the use of heavy equipment would cause unacceptable levels / of soil erosion.A 50-foot buffer.strip of undisturbed land could be maintained between the pipeline and streams,lakes,and wetlands wherever possible.Construction equipment should not be operated in water bodi es except.where necessary •.Where high 1eve1 s of sediment are expected from construction activity,settling basins should be constructed and maintained.All disturbed areas should be left in a stabilized condition through the use of revegetation and water bars; culverts and bridges should be removed,and slopes should be restored to approximately their original contour. A significant problem with the operation of a chilled,buried pipeline is the formation of aufeis.Aufeis is an ice structure formed by water overflowing onto a surface and freezing~with SUbsequent layers formed by repeated overflow.Chilled pipe in streams can cause the stream to freeze to the bottom in the vicinity of the pipe,creating aufeis over the blockage.A chilled pipe through unfrozen ground can also form a frost bulb several times larger than the pipe diameter.This frozen area can block subsurface flow,forcing water to the surface and causing aufeis.Road cuts can also expose SUbsurface flow channels, causing aufeis build-up over the roadway.The potential for aufeis and possible effects will require detailed considerations for all construction areas. All stream crossing facilities should be designed to withstand the Pipeline Design Flood as defined for the ANGTS system.Streams should be stabilized and returned to their original configuration,gradient, 2648B 4-78 [ L [ L L L [ [ [ [' r [' [' f'Lj [; L~ r~ L [ [ [ r -J ,~ L [ [ l L L substrate,velocity,and surface flow.Water supplies for compressor or meter stations should not be taken from fish spawning beds,fish rearing areas,overwintering areas or waters that directly replenish those areas during critical periods. TIle YUKon River crossing will utilize an existing bridge.The Yukon River will therefore not be significantly affected by the pipeline. 4.6.3 Aquatic Ecosystem Effects The Fairbanks power plant will not cause significant impacts to the aquatic resources.The water supply for the power plant will be obtained from groundwater,and therefore will not affect surface waterbodies.Discharges from the plant will be treated to meet effluent guidelines before being released,so that fish habitat should not be significantly affected.Discharge quantities will be relatively low,less than 200 gprn. The pipeline from the North Slope to Fairbanks will cross numerous rivers and creeks,including the Yukon River.Aquatic resource impacts will include all those discussed for the North Slope scenario (Section 2.5.3),and additional impacts caused by the chilled pipeline crossing waterbodies.Several mitigation measures,in addition to those already discussed,should be implemented to protect the fish habitat affected by pipeline construction and operation.·Stream crossings·should be constructed such that fish passage is not blocked and flow velocity does not exceed the maximum allowable flow velocity for the fish species in a given stream.If these criteria cannot be met,a bridge should be installed. Chilled pipes in streams should not cause:a)lower stream temperatures so as to alter biological regime of stream;b)slow spring breakup and delay of fish migration;or c)early fall freeze-up which Would affect fish migration.In addition,the temperature of surface or subsurface water should not be changed significantly by the pipeline system or by any construction-related activities. 26488 4-79 All mitigation measures designed to reduce sedimentation of water bodies (discussed in the Section 4.6.2)will protect fish spawning, rearing and overwintering areas. For the purpose of making recommendations regarding timing of ANGTS construction activities,the pipeline corridor was divided into three large geographical regions:Region I,Beaufort Sea to the Continental Divide of the Brooks Range;Region II,Continental Divide of the Brooks Range to the Yukon River;and Region III,Yukon River to Fairbanks.In association with the ANGTS development,the following broad temporal gUidelines were developed for recommendation for each gas1ine corridor region based on fish use habitat (Schmidt et al 1981).These would also be applicable to a smaller diameter pipeline. Regi on I 1 May-20 July A cri tical peri od for most Region II 15 April-15 July streams due to the occurrence Regi on III 1 April-15 July of major spring migrations and (early breakup streams)spring spawning (primarily 15 April-15 July grayling). (late breakup streams) Regi on I 20 July-25 August A sensitive period.Fry of Region II 15 July-25 August spring spawning species have Regi on III 15 July-l September emerged and major fall emigrati ons have not yet begun.Fish are mobile at this time and can move to avoid or reduce effects of disturbance. Regi on I 25 August-1 OCtober A critical period for all (small streams)streams.Fish must emigrate 25 August-15 OCtober from streams that do not (l arge streams)provide winter habitat prior Regi on II 25 August-l OCtober to freeze-up.Major upstream (small streams)migrations and spawning of 25 August-15 OCtober fall spawning species occurs (l arge streams)in streams that provide over- Regi on II I 1 September-l November wintering habitat. 2648B 4-80 r~ L [ C C L [ [' L L [ The Fairbanks power plant will affect terrestrial resources primarily through habitat disturbance.As discussed in the Report on Facility Siting and Corridor Selection (Appendix C),potential pmler plant sites in the Fairbanks area are located in developed or previously disturbed areas.The.potenti al for adversely affecti ng terrestri·al habi tats ;s therefore not considered to be.significant. Region I Region II Region III A preferred period for con- struction in many streams that do not provide winter habitat. These streams generally are dry or freeze to the bottom during winter.This is a critical period for fish overwintering in springs,large rivers,and lakes.. 1 October-1 May (small streams) 15 October-l May (l arge streams) 15 October-15 April (small streams) 1 November-15 April (l arge streams) 1 Novemoer-l April (early breakup streams) 1 November-15 Apri 1 (late breakup streams) 4.6.4 Terrestrial Ecosystem Effects C L c [ [ [ [ [ f' PL-, [ L C L L [ [ L [ [ Construction of the gas pipeline from the North Slope to Fairbanks will require total clearing of a 50-foot right-of-way for the length of the gas1ine.In addition,ten lO-acre compressor stations,two 1.5 acre metering stations and a gas conditioning facility (15 acres)will be constructed.Construction activities will disrupt terrestrial animals near ~he corridor during the 3-year construction period.The pipeline alignment will avoid the peregrine falcon nest sites near.the Franklin ana Sagwon Bluffs,but other raptors may restrict construction schedules (refer to Appendix C).Special construction measures may be necessary in tile areas delineated by the BLlt!lana use plan,as discussed for the North Slope scenario.Construction activities,especially aircraft traffic, could disturb Dall sheep habitat in critical wintering,lambing and movement areas.These construction-related impacts would be less than 3 years in duration. Long term terrestrial impacts will result primarily from habitat elimination •.Important moose browsing habitat,such as the willow stand along Oksrukuyik Creek,should be preserved.The treeline white spruce 2648B 4-81 stand at the heaa of Dietrich Valley,which has been nominated for Ecology Reserve status,should be avoided.The pipeline design should allow for free passage of caribou and other large animals. 4.6.5 Socioeconomic and Land Use Effects The potential socioeconomic and land use effects of locating an electrical generdting facility in the vicinity of Fairbanks includes the temporary impacts related to the influx of workers and permanent land use impacts. The size of the construction work force for the generating facility is expected to be approximately 200 persons.These generation units will be .constructed during the summer for about 4-5 months. Since the project could draw on the large labor pool of Fairbanks,it can be expected that the majority of workers will be hired locally.Economic benefits to tile region will not be significant as employment on the project will be temporary.Any in-migrating work force will have to seek temporary housing on their own since housing will not be provided at the project site.The extent of the impacts on the local housing supply will depend on the vacancy rate for the summer of each year of construction. As discussed in the Report on Facility Siting and Corridor Selection (Appendix C),development of a generating facility on the outskirts of the Fairbanks area should not engender significant land use conflicts, since the focus of the final site selection activities will be on areas which are presently used for industrial development.However,the long-ten"staged development of a major electric generating complex will certainly be a determinant of future land uses in the local area. Construction activities at the generating plant site will generate additional worker and construction vehicle traffic loads on the local road system.However,disruptions to existing traffic patterns can be minimized through site selection by utilizing major highways and 26488 4-82 r' r [ f' [- f r -- -, -nL-" [ L [ [ C F'b b [ L L [ [ r~ L b U [ r: b [ [ L L l arterials to the maximum extent possible and by developing a local access plan and schedule.Depending on the site selected,new access requirements will be planned in recognition of local traffic requirements. For construction of the gas pipeline in the North Slope-Fairbanks corridor,employees will be housed either at the pump stations or the permanent camp facilities that were constructed for the trans-Alaska oil pipeline.Construction activities will be consistent with the BUM land use criteria as discussed in Section 2.5.5. The potential socioeconomic and land use impacts of the transmission facilities between Fairbanks and Anchorage included in this scenario are identical to those discussed in Section 2.5.5 for the North Slope scenario,with-the addition of transmission facilities from the Fairbanks generating site to the power grid.Again,assuming the site is located on the outskirts of Fairbanks to the southeast,transmission -" interconnections can probably expand on existing GVEA rights-of-way with minimal additional impacts to existing land uses.However,future land use patterns will be signficantly affected by the presence of the three parallel 345 kV transmission lines. 2648B 4-83 I I I I I I I I I I I I I I I • I I oo seEf 'ARlO II FAIRBANKS POVVC:R GENERATION LOW LOAD C 8 C C E [ [ [ L E 5.0 FAIRBANKS POWER GENERATION LOW LOAD FORECAST The Fairbanks generation scenario,under the low load forecast, requires all of the major systems of the medium growth forecast except that fewer compression stations are required to transport the gas and fewer units are required to generate electricity.The Fairbanks area electrical generating station will require 3 combined cycle plants, each consisting of two gas fired combustion turbines paired with two waste heat recovery boilers,and a steam turbine generator for a station capacity of 726 MW in 2010.Units will be phased-in by bringing each combustion turbine on-line individually,followed by the waste heat recovery boilers and steam turbine generator.Between Fairbanks and Anchorage,one new 345 kV transmission line and upgrading of the Healy-Fairbanks and Willow-Anchorage segments of the existing line will be reqUired.The Fairbanks residential/commercial,gas system peak demand at 100 percent penetration of potential market is 49 MMSCFD. Construction of the gas conditioning facilities,gas pipeline,power generating facilities and transmission systems,is estimated to cost $4.9 billion.Total annual operation and maintenance costs are ~stimated to be ~q.4 billion.The present worth of costs exclUding fuel costs is $3.6 billion.Construction costs of the Fairbanks gas distribution system serving residential/commercial markers total $1.6 billion,with total annual operation and maintenance costs totalling S41 million.The present worth of costs for this system, consisting of a portion of the pipe1irie and gas conditioning facilities,plus the distribution network itself,is Sl.l billion. 5.1 NORTH SLOPE TO FAIRBANKS NATURAL GAS PIPELINE As explained.in Section 4.1,pipeline design proceeded on the basis of preliminary gas demand calculations.Because the refined demand values 2631B 5-1 did not warrant design changes,certain of the gas demand calculations differ in the low load forecast as follows: Pipeline Design (Preliminary Demand) Power Generation . Annual Average Demand Peak Daily Demand Residential/Commercial Annual Average Demand Peak Daily Demand Total Annual Average Demand Peak Daily Demand Low Load Forecast (MMSCFD) 108 179 14 40 122 219 -[ r~ l f t- L' [~ After refined demand values were available,the results were: 5-2 26318 5.1.1 Gas Conditioning Plant For the low load forecast,the refined demand was 40 MMSCFD less than the preliminary calculation. c L [ [ [ C L f L L L L 49 179 130 Low Load Forecast (MMSCFD) Uti11ty System Design (Refined Demand) Residential/Commercial Peak Daily Demand Total Peak Daily Demand Power Generation Peak Daily Demand The gas conditioning facility required for the low growth scenario will utilize the SELEXOL physical solvent process,as described in Section 4.1.1.The design f10wrate will be 230 MMSCFD based on the daily peak load anticipated for this growth forecast,a pipeline availability of 96.5 percent and compressor station demands.All other details and specifications will be as described in Section 4.1.1. r~ [ [ r~ [ L [ r L c L [ t [ [ [ [ [ [ l~ [ 5.1.2 Pipeline Similar to the medium forecast design,the pipeline will have an outside diameter of 22 inches and will follow the same route,the ANGTS right-of-way.Details regarding pipeline design and route are presented in Section 4.1.2. The peak daily flowrate,however,requires only three compressor stations,which will be located at Stations 2,4 and 7 when using the ANGTS numbering system.The flow conditions anticipated for the demand scenario are presented in Figure 5-1.The design of the compressor stations is indentical to that presented for the medium load forecast. All other required systems,facilities and support services will also be the same as those presented in Section 4.1.2. 5.2 POWER PLANT The scenario for power generation at a Fairbanks site,under the low load forecast requires three combined cycle plants to satisfy the anticipated demand in the year 2010.The schedule for unit addition which resulted from the analyses presented in the Report on System Planning Studies (Appendix B)is shown in Table 5-1. The details of p1~nt design and operation are identical to those described for the medium load case in Section 4.2.Only where there are variances due to the decreased number of units are specific items addressed below. Total operations and maintenance personnel will be less for this scenario than the medium load case.Ten on duty operations and maintenance personnel will be reqUired per shift in 1996 When the first gas turbine begins operation.In the year 2010 when three complete units are operating,60 on duty personnel will be required per shift.The plant. site will be.approximately 90 acres in size and will include all three units,two switchyards,and a 300 foot buffer zone around the plant. 2631B 5-3 .r;;:;"".~.'10.1 ".2.132..'S-I1r 1.1.5..s. L ~P.!>.~o ~~"1:\11 ~~to(< • ...2't ~f1110lL~,-~L-"ilia 1:1'1 !I II L"Za:;"~{:ilL f litgtp: ....z MM sCJ"j'b if? TOTAL 480 MILES.22"0.0.PIPELINE.WALL THICKNESS •0.275 INCH MINIMUM STATION DESIGNATIO,.M.L c.•.t c.•.I e.LI e.I.4 c.•.•c.•.•c.,.,c.,.•c.,.•e.L to POWI::-I.....,'RUDHOE lA, MILEPOST (MILES)0.0 vo.1 '41.3 2.73."....'0.0 REVATION (FEET)2.1 "if2.S'305"0 '3/S"500•STATION INLET VOLUME (MMSCF /0),.,s-o 2.30 2.30 2.'2.~2.2.1.. ~TOTAL FUEL (MMSCFID)-.,,I -.. STATION OUTLET VOLUME (MMSCFID)2.30 22.'2.2!2.2.7 '1S STATION SUCTION PRESSURE (PSIG)12.'-0 II(H /()3~II 'lifo '0,",,'I STATION DISCHARGE PRESSURE (PSIG)12.'0 IUO IIV~12.'0 - •COMPRESSOR SUCTION PRESSURE (PSIG)ID.,,?/032."'0 -0 ii COMPRESSOR DISCHARGE PRESSURE (PSIG)12.'-+IIr,./2.&4--..-III It COMPRESSION RATIO './37 -..-'.150 1.15'02 0 HORSE paW[lt RlQUIRED 1'32.0 -u ,....50 .'~70 . ALASKA POWER AUTHORITY NORTH SLOPE GAS FEASIBILITY STUDY HYDRAUL IC SUi'1f1ARY LmJ FORECAST PEAK DAILY FLOH FIGURE !i-I EBASCO SERVICES INCORPORATED rn .~ J [ [ [ [ [ [' [ G L C L [ L [ C L L [ L [] [ TABLE 5-1 NEW CAPACITY ADDITIONS AND FUEL REQUIREMENTS 1/ FAIRBANKS POWER GENERATION -LOW LOAD FORECAST_ Combined Cycle (MW)Gas Requi red Year (Increment/Total)(MMSCFD) 1990 0/0 O. 1991 0/0 O. 1992 0/0 O. 1993 0/0 O. 1994 0/0 O. 1995 0/0 '0. 1996 86/86 5,957.6 1997 86/172 11 ,873.2 1998 0/172 11 ,873.2 1999 0/172 11 ,873.2 2000 0/172 11 ,904.7 2001 70/242 11,939.4 2002 86/328 17,876.4 2003 0/328 17,876.4 2004 86/414 23,873.6 2005 70/484 23,873.8 2006 86/570 29,814.1 2007 0/570 29,814.1 2008 86/656 33,413.4 2009 0/656 34,508.4 2010 70/726 32,228.9 !I Values as calculated are shown for purposes of reproducibility only,and do not imply accuracy beyond the·100 MMSCFD 1eve 1. 2631B 5-5 Annual fuel requirements for power generation will grow from 5.96 BCFY in 1996 to 32.23 BCFY in 2010.The maximum potential firing rate in the year 2010,based on a heat rate of 8280 Btu/kWh,will be apprOKimate1y 9 x 10 4 SCFM.Annual fuel requirements for the study period are also shown in Table 5-1. 5.3 TRANSMISSION SYSTEM 5.3.1 Fairbanks to Anchorage This transmission system uses two 345 kV lines as described in Section 3.2.Other details are similar,including series compensation. 5.4 FAIRBANKS GAS DISTRIBUTION SYSTEM 5.4.1 Fairbanks Residential/Commercial Gas Demand Forecasts A study has been performed by Alaska Economics Incorporated to forecast residential and commercial gas demand in Fairbanks.A summary of the study's methodology and the results of the medium growth projection appear in Section 4.4.1.The text of the stUdy appears in Appendix E. Table 5-2 presents the study's results for the low growth forecast. These forecasts have been made conditional on t~e gas achieving the discrete percentages of the total market for heating and cooking energy applications shown in Table 5-2.The size of the total market to which these percentages have been applied has been projected to grow at a 1.43 percent annual average rate,the low growth forecast,beginning in 1981.This rate is the implied population growth rate for Fairbanks as derived in Batte11e's (1982)low forecast of the demand for electricity in the Rai1be1t area. 5.4.2 Fairbanks Gas Distribution System The gas distribution system has been designed to supply Fairbanks a low growth demand value of 5.2 BCFY.The differences in flowrates and service areas between the medium and low growth scenarios affect the 2631B 5-6 T ~[~ 1 L' ~ r ' l ~L, C l_ [ L r.~lJ [ ~ ,[= [ .L ,C [ Delivered Gas,BCF Per Year TABLE 5-2 FAIRBANKS RESIDENTIAL/COMMERCIAL GAS DEMAND FAIRBANKS POWER GENERATION -LOW GROWTH FORECASTl/ ".!!Refer to Appendix E for details. Delivered Gas,BCF Peak Daily Delivered Gas,BCF Per Peak Month [ [ [ [- [ [ L P L I~ L [ 6 [ C b [ L L L [ Market growth at 1.43 Percent 10%of Market 20%of Market 40%of Market 100%of Market 10%of Market 20%of Ma rket 40%of Market 100%of Market 10%of Market 2"0%of Market 40%of Market 100%of Market 2631B 1985 0.510 1.275 2.039 5.098 1985 0.085 0.212 0.338 0.846. 1985 0.003 0.009 0.014 0.034 2010 0.727 1.818 2.908 7.720 2010 0.121 0.302 0.483 1.207 2010 0.005 0.012 0.020 0.049 size and lengths of the high pressure and distribution system mains. The sizes and footages of the high pressure mains and the distribution mains required for the low growth forecast are presented below.All other system and piping details are the same as the medium growth forecast which is described in Section 4.4.2. High Pressure System Mains Size (Inches)Length (Feet) 8 6,000 10 15,000 12 27,375 14 7,500 'Schedule of Distribution Mains Size (Inches) 2 4 6 5.5 COST ESTIMATES 5.5.1 Capital Costs Length (Feet) 450,000 78,000 90,750 c L 5.5.1.1 North Slope to Fairbanks Gas Pipeline Feasibility level investment cost estimates have been prepared for the systems and facilities which comprise the North Slope to Fairbanks natural gas pipeline.These estimates are presented in Table 5-3. 5.5.1.2 Power Plant The capital cost of simple cycle combustion turbines and'combined cycle facilities are the same as that presented in Section 4.5 for the medium load forecast. 26318 5-8 I~ L l.: [ [ L~ [ [ C L [ [ [ [ U [ [ [ L [ TABLE 5-3 FEASIBILITY LEVEL INVESTMENT COSTS FAIRBANKS POWER GENERATION -LOW LOAD FORECAST (Millions of January,1982 Dollars) Total Descriptionl/ Materials Constructi on Labor 21 Di rec t Costs ($1000)($1000)($1000) 22 in O.D.Gas Pipeline 480,000 4,100,000 4,580,000 Compressor Stations - 3 ea 30,300 25,300 55,600 Metering Stations - 2 ea 2,800 6,000 8,800 Valve Stations -28 ea 2,500 3,800 6,300 Engineering &Construction 279,000 Management SUBTOTAL $515,600 $4,135,100 $4,929,700 Gas Conditioning Faci1 i ty3/538,300 TOTAL $5,468,000 1/A 15 percent contingency has been assumed for the entire project and has been distributed among each of the cost categories shown.Sales/use taxes and land and land rights expenses have not been included.• 2/Construction camp facilities and services are subsummed in the Constructi on Labor cost category. 3/Factored pricing basis which includes engineering and construction management. 2631B 5-9 5.5.1.3 Transmission Line Systems Feasibility level investm~nt cost estimates have been prepared for all required transmission line systems.The results of this analysis are presented in Table 5-4.The estimate is of one new 345 ~V lines 700 MW capacitys with series compenSation and an intermediate switching stations and the required upgrading of the Willow-Anchorage'and Healy-Fairbanks segments of the existing grid. 5.5.1.4 Gas Distribution System Feasibility level and investment cost estimates (Januarys 1982 dollars) have been prepared for the systems and facilities which comprise the Fairbanks gas distribution system.The results of the analysis are presented below.A 15 percent contingency has been assumed for the entire project and has been distributed between each.cost category. Sales/use taxes and land and land rights have not been included. 5.5.2.1 Gas Pipeline and Conditioning Facility Annual operation and maintenance costs (Januarys 1982 dollars)for the gas conditioning facilities are estimated to be as follows: 5.5.2 Operation and Maintenance Costs Annua 1 Co sts ($l 000) CL [ c r L [ [ [ L [ 3 s 390 $59 s890 $56 s500 $ls390 2,100 $3 s 490 $45 s200 Construction Total Direct Labor ($lOOO)Costs ($lOOO) 5-10 Materi al s ($1000 ) $11 s300 Item Total Salaries Maintenance Costs (Parts and Expendables) Gas Distribution System Engineeri ng and Construction Management Total Construction Costs. 26318 1/'The investment costs one new 345 kV line,700 MW capacity with series compensation and an intermediate switching station,and reflect upgrading of the Willow-Anchorage and Healy-Fairbanks segments of the existing grid to 345 kV. 2/Assumes a cost of $40,000 per mile (Acres American Inc.1981). TABLE 5-4 FEASIBILITY LEVEL INVESTMENT COSTS FAIRBANKS TO ANCHORAGE TRANSMISSION SYSTEM FAIRBANKS POWER GENERATION -LOW LOAD FORECAST (Millions of January,1982 Dollars) Total Construction Di rect Costs Labor ($lOOO)($lOOO) 8,414 17,271 30,872 63,830 10,960 23,260 182,083 311 ,291 53,183 73,232 41,572 41,572 $327,084 $530,456 14,400 37,130 $581,986 8,857 32,958 12,300 129,214 $203,378 Material s ($1000 )De sc ri pti onll TOTAL Cl eari ng Conductors and Devices SUBTOTAL Land and Land Rights~/ Engineering and Construction Management Switching Stations Substations Energy Management Systems Steel Towers and Fixtures r: L~ [ L [ [ [: L [ l L l [ 26318 5-11 .Annual operation and maintenance cost (January,1982 dollars)for the gas compressor stations and pipeline maintenance activities are estimated to be as follows: Operation and maintenance costs for the combined cycle facility at Fairbanks are estimated to be $0.0040/kWh.These are based on discussions with operating plant personnel,history of similar units, EPRI published data and other studies. Item Sal ari es Maintenance Costs (Parts and Expendables) Total 5.5.2.2 Power Plant Annua 1 Co sts ($1000) $2,090 1,750 $3,840 n L 5.5.2.3 Transmission Line Systems Annual operation and maintenance costs (January,1982 dollars)have been developed for the scenario·s required transmission line facilities and total $8 million per year.These costs should be viewed as an annual average over the life of the system.Actual O&M costs should be less initially,and increase with time. 5.5.2.4 Gas Distribution System [~ L [ \- \...---- rL; Annual operation and maintenance costs (January,1982 dollars)for the Fairbanks gas distribution system are estimated to be as follows: 26318 Item Sal aries Maintenance Costs (Parts and Expendables) Total 5-12 Annual Costs ($1000) $680 270 $950 ("c L L [ f' L [ C [ [ G L [ [ L [ 5.5.3 Fuel Costs For the economic analyses which follow fuel costs were treated as zero. This approach permits fuel cost and fuel price escalation to be treated separately;and makes possible subsequent sensitivity analyses of the Present Worth of Costs for this scenario based upon a range of fuel cost and cost escalation assumptions. 5.5.4 Total Systems Costs 5.5.4.1 Cost Allocation Methodology The methodology that was developed and presented in Section 4.4.4.1 is equally app1 icabl e to the low growth scenari o. 5.5.4.2 Total System Costs Like the Fairbanks medium load growth scenario,the Fairbanks low load growth scenario involves a complex series of investments in a gas conditioning facility,a natural gas pipeline,power generation facilities,and transmission lines.Also,like the previous Fairbanks scenario,the costs of the the gas conditioning facility and pipeline must be apportioned according to the formulae presented in Section 4.5.4.1.After that apportionment,total annual system .costs can be calculated. The formulae for conditioning facility and pipeline cost apportionment are the same regardless of growth;however,the resulting 01 and 0A values are quite different between the low and medium growth scenarios. For the low load forecast the 01 value is as follows: ~esidential/Commercial Peak =49 MMSCFD Da i1y Flow (201 0) El ectri-ca 1 Generati on Peak =130 MMSCFD Da i1y Flow (201 0) Total Peak Daily Flow (2010)=179 MMSCFD 01 =0.73 26318 The 0A values for the Fairbanks low load forecast are presented in Table 5-5.Significant to note is the fact that in the low load forecast case,the residential/commercial customers must assume a higher share of the capital and annual cos~burdens 'of the gas conditioning and pipeline facilities. Given the joint systems cost apportionment,the total annual electrical systems costs can be calculated.Total annual capital'costs are presented in Table 5-6.Total annual O&M costs are presented in Table 5-7.Total annual costs are then summarized in Table 5-8.The period of the analysis was assumed to be 1982 through 2010. The present worth of costs has peen calculated for comparison purposes.The present worth of costs as of 1982,assuming a discount rate of 3 percent,is $3.6 billion (1982 dollars)exclusive of fuel costs. 5.5.4.3 Gas Distribution System Costs The costs attributable to the gas distribution system serving residential and commercial customers include a portion of ,the gas conditioning plant,a portion of the pipeline,and all of those costs associated with the distribution system within Fairbanks.Again,the apportionment method discussed in Section 4.5.4.1 is an essential precursor to the calculation of final total system costs. Gas distribution costs depend upon calculating 1-0 1 and 1-0 A .values.These are presented in Table 5-9.Pgain,it is clear that the non-electric'customers must assume a larger portion of the capital and operating expenses in the low load growth scenario as compared to the medium load growth scenario. Given those apportionment values,the total systems costs for the gas distribution system can be calculated.Capital and O&M are presented in Tables 5-10 and 5-11.Total annual systems costs are summarized in Table 5-12.The present worth of these costs of 1982,assuming a real discount rate of 3 percent,is $1.1 billion,exclusive of any fuel costs. 26318 f" L r:::: L [ [ [ r L [ [ [' I' l~ L L [ [TABLE 5-5 ~VALUES . [FAIRBANKS POWER GEN TION -LOW LOAD FORECAST [Residential El ectri cal Total Calendar Demand Demand Demand['Year (BCFY)(BCFY)(BCFY)°A r 1982 O.O.O.NA!/ 1983 O.O.O.NA 1984 O.O.O.NA L 1985 O.O.O.NA 1986 O.O.O.NA 1987 O.O.O.NA 1988 O.O.O.NA P 1989 O.O.O.NA L 1990 O.O.O.NA 1991 O.O.O.NA C 1992 O.O.O.NA L 1993 O.O.O.NA 1994 O.O.O.NA 1995 O.O.O.N/A [1996 1.266 5.958 7.224 0.82 1997 2.568 11.873 14.441 0.82 1998 3.906 11.873 15.779 0.75 C 1999 5.283 11.873 17.156 0.69 2000 6.698 11.905 18.603 0.64 2001 6.794 11.939 18.913 0.63 l 2002 .6.891 17.876 24.767 0.72 2003 6.990 17.876 24.866 0.72 2004 7.090 23.874 30.964 0.77 2005 7.191 23.874 31.065 0.77 [.2006 7.294 29.814 37.108 0.80 2007 7.398 29.814 37.212 0.80 2008 7.504 33.413 40.917 0.82 C 2009 7.611 34.508 42.119 0.82 2010 .7.720 32.229 39.949 0.81 [1I NA -Not applicable C. [ [ 2631B L 5-15 TABLE 5-6 ANNUAL CAPITAL EXPENDITURES FAIRBANKS POWER GENERATION -LOW LOAD FORECAST (Millions of January,1982 Dollars) Electricity Generated!! Gas Calendar Transmission Conditioning Year Unit A Unit B Line Pipeline Plant Total 1982 O.O.O.O.O.O. 1983 O.O.O.O.O.O. 1984 O.O.o.O.O.O. 1985 O.O.O.O.O.o. 1986 o.o.o.O.O.O. 1987 O.O.o.O.O.O. 1988 O.O.o.O.O.O. 1989 O.O.O.o.O.o. 1990 O.O.o.O.O.O. 1991 O.O.O.O.O.o. 1992 O.O.311.3 O.O.311.3 1993 O.o.71.8 1 ,199.6 o.1,271.4 1994 9.96Y O.141.4 1 ,199.6 196.5 1,547.5 1995 33.90 O.57.5 1,999.6 196.5 1,487.5 1996 33.90 O.O.O.O.33.9 1997 O.O.o.O.O.o. 1998 O.O.O.O.O.O. 1999 O.O.O.O.O.O. 2000 56.97 O.o.O.o.57.0 2001 33.90 O.O.O.o.33.9 2002 O.O.O.o. o.O. 2003 33.90 O.O.O.O.33.9 2004 56.97 O.o.O.O.57.0 2005 33.90 O.O.o.O.33.9 2006 O.O.O.O.o.O. 2007 33.90 O.O.O.O.33.9 2008 O.O.o.O.O.O. 2009 O.O.O.O.O.o. 201 0 O.O.O.O.O.o. Total $327.O.$582.$3,599.$393.$4,901 • !!Unit A refers to first unit built in a given year and Unit B to second unit built. 2/Includes site preparation activities for multiple unit site. 2631B 5-16 c: L r L c [ rc' n L ,[ L [ [ [ [TABLE 5-7 ANNUAL NON-FUEL OPERATION AND MAINTENANCE COSTS [FAIRBANKS POWER GENERATION -LOW LOAD FORECAST (Millions of January,1982 Dollars), [~Gas Calendar Transmission Conditioning [Year Electricity Generated Line Pi pel i ne Pl ant Total L 1982 O.O.O.O.O. 1983 O.O.O.O.O. 1984 O.O.O.O.O. 1985 O.O.O.O.O. [~1986 O.O.O.O.O. 1987 o.o.o.o.o. 1988 o.o.O.o.o. P 1989 o.o.o.o.o. 1990 o.o. o.o.o.Lj 1991 o.·0.O.o.o. 1992 O.o.o.o. o.r~1993 o.o. o.o.o.L 1994 o.o. o.o. o. 1995 o.o.o.o.o. ['1996 2.268 8.00 3.15 2.86 16.3 1997 4.520 8.00 3.15 2.86 18.5-"1998 4.520 8.00 2.88 2.62 18.0 U 1999 4.520 8.00 2.65 2.41 17.6 2000 4.520 8.00 2.46 2.23 17 .2 2001 6.360 8.00 2.42 2.20 19.0 2002 8.620 8.00 2.76 2.51 21.9[2003 8.620 8.00 2.76 2.51 21.9 2004 10.908 S.OO 3.00 2.69 24.6 2005 12.720 8.00 3.00 2.69 26.4 [2006 14.980 8.00 3.07 2.79 2.8.8 2007 14.980 8.00 3.07 2.79 28.8 2008 16.112 8.00 3.15 2.86 30.1 r:2009 16.640 8.00 3.15 2.86 30.7 2010 17.168 8.00 3.11 2.83 31.1U Total $147.$120.$44.$40.$351. [ [ [ rc : u 2631B L 5-17 TABLE 5-8 TOTAL ANNUAL COSTS FAIRBANKS POWER GENERATION -LOW LOAD FORECAST (Millions of January,1982 Dollars) Calendar Capital o &M Total Year Expenditures Costs Expendi tures 1983 O.O.O. 1984 O.O.O. 1985 O.O.O. 1986 O.O.O. 1987 O.O.O. 1988 O.O.O. 1989 O.O.O. 1990 O.O.O. 1991 O.O.O. 1992 311.3 O.311.3 1993 1,271.4 O.1,271.4 1994 1,547.5 O.1,547.5 1995 1,487.5 O.1,487.5 1996 33..9 16.3 50.2 1997 O.18.5 18.5 1998 O.18.0 18.0 1999 O.17.6 17.6 2000 57.0 17 .2 74.2 2001 33.9 19.0 52.9 2002 O.21.9 21.9 2003 33.9 21.9 55.8 2004 57.0 24.6 61.6 2005 33.9 26.4 60.3 2006 O.28.8 28.8 2007 33.9 28.8 62.7 2008 O.30.1 30.1 2009 O.30.7 30.7 2010 O.31.1 31.1 Total $4,901 •.$351.$5,252 • Present Worth @ 3%$3,405.$185.$3,590. 2631B 5-18 [' [ ! L c: L [ l~ t F [ L [ L [ [ c- r L [~ [ [ P L n L [ Ll C [ [J [ [ [ [ L 26318 TABLE 5-9 APPORTIONMENT VALUES FOR THE GAS DISTRIBUTION SYSTEM FAIRBANKS POWER GENERATION -LOW LOAD FORECAST Tenn Year Value (1-0 )1 NA 0.27 (1-0 )A 1983-1995 NA 1996 0.18 1997 0.18 1998 0.25 1999 0.31 2000 0.36 2001 0.37 2002 0.28 2003 0.28 2004 0.23 2005 0.23 2006 0.20 2007 0.20 2008 0.18 2009 0.18 2010 0.19 5-19 [ TABLE 5-10 [CAPITAL COSTS ASSOCIATED WITH THE DISTRIBUTION SYSTB~ FAIRBANKS POWER GENERATION -LOW LOAD FORECAST r'(Millions of January,1982 Dollars) l , [' Gas Calendar Conditioning Distribution Year Plant Pipeline System Total '[ 1982 O.O.O.O.['1983 O.O.O.O. 1984 O.O.O.O. 1985 O.O.O.O.f'1986 o.O.O.O. 1987 O.O.O.O.\.._" 1988 O.O.O.O. 1989 O.O.O.O.[1990 O.O.O.O. 1991 O.O.O.O. 1992 O.O.O.O.C 1993 O.443.7 12.0 455.7 I199472.6 443.7 12.0 528.3 '-- 1995 72.6 443.7 12.0 528.3 [1996 O.O.12.0 12.0 1997 O.O.12.0 12.0 1998 o.O.O.O. 1999 O.O.O.O.[2000 o.o.o.o. 2001 O.o.o.o. 2002 o.o.o.o.C2003o.o.o.o. 2004 o.o.O.o. 2005 o.o.o.o.[2006 o.o.o.o. 2007 o.o.o.o. 2008 o.o.o.o. 2009 o.o.o.o.[2010 o.O.o.o. Total $145.$1 ,331.$60.$1,536.f I, f: 2631B L 5-20 ,L TABLE 5-12 ANNUAL SYSTEMS COST SUMMARY FOR THE GAS DISTRIBUTION SYSTEM FAIRBANKS POWER GENERATION -LOW LOAD FORECAST (Millions of January,1982 Dollars) Calendar Year Capital Cost o &t·'Cost Total Cost 1982 O.O.O. 1983 o.O.O. 1984 O.O.O. 1985 O.O.O. 1986 O.O.O. 1987 O.O.O. 1988 O.O.O. 1989 O.O.O. 1990 O.O.O. 1991 O.O.O. 1992 O.O.O. 1993 455.7 O.455.7 1994 528.3 O.528.3 1995 528.3 O.528.3 1996 12.0 2.3 14.3 1997 12.0 2.3 14.3 1998 O.2.8 2.8 1999 O.3.2 3.2 2000 O.3.6 3.6 2001 O.3.7 3.7 2002 O.3.0 3.0 2003 O.3.0 3.0 2004 O.2.6 2.6 2005 O.2.6 2.6 2006 O.2.4 2.4 2007 O.2.4 2.4 2008 O.2.3 2.3 2009 O.2.3 2.3 2010 O.2.3 2.3 Total $1 ,536.$41-$1,577 • Present Worth at 3%$1 ,075.$22.$1,097. 2631B 5-22 L [' r f' L.. [ [ [ c L [ [ E [' .r=-: L t L [ 1; '-""..; L I [ I [ I [ ! [ r i [ [ P L c o B L o [ L [ [ L -------------------._----------._-"--_._-_.-------_.------~----------_.__._~---------------~-----------;------------_.-._--------~._._-------=---.--------.~-------------~------~-- -----------~----._---~ 5.6 ENVIRONMENTAL AND SOCIOECONOMIC CONSIDERATIONS The Fairbanks power plant for the low load forecast will consist of three combined cycle units in contrast to five combined cycle and two simple cycle units for the medium load forecast.Power plant characteristics are summarized in Table 5-13. It is assumed that water or steam injection would not be required for NOx control because of associated ice fog problems.Air emissions will be reduced by apprQKimately one-half from the medium load forecast,and will meet all applicable air quality standards.Groundwater will provide approximately 100 gpm for eqUipment waSh-down,potable supplies,and boiler make-up water.This relatively small amount of water will not affect groundwater supplies in the area.Wastewater discharges will be less than 100 gpm and will be treated to meet effluent gUidelines. Aquatic resources,as for the medium load forecast,will not be significantly affected.Plant acreage will be apprQKimately 90 acres,as compared to 140 acres for the medium load forecast.Terrestrial impacts on vegetation and habitat elimination are correspondingly reduced. Pipeline-related impacts are identical to those discussed for the Fairbanks scenario medium load forecast,Section 4.5.Impacts associated.. with the transmission line from Fairbanks to Anchorage are identical to those discussed in Section 3.5 for the North Slope scenario,low load forecast.Socioeconomic impacts are expected to be similar to those for the medium demand scenario. Soc i oeconomic impacts,as for the medi urn load forecast,are not expected to be significant.The majority of workers will be hired locally.Any in-migrating workforce will have to seek temporary housing on their own but this number is expected to be low. 26318 5-23 Ai r Envi ronment TABLE 5-13 ENVIRONMENT RELATED POWER PLANT CHARACTERISTICS COMBINED CYCLE POWER PLANT FAIRBANKS POWER GENERATION -LOW LOAD FORECAST Emissions Particulate Matter Sulfur Dioxide Nitrogen Oxides Physi ca 1 Effects Water Environment Below standards Below standards Emissions variable within standards - dry control techniques would be used to meet calculated NO~standard of 0.014 percent of total volume of gaseous emissions.This value calculated based upon new source performance standards,facility heat rate,and unit size. Maximum structure height of 50 feet [, [ [ [ [). [ L Plant Water -Requirements 100 GPM Pl ant Di scharge Quantity,Less than 100 GPM including treated sanitary waste,floor drains, boiler blow-down and demineralizer wastes Land Environment Land Requirements Plant and Switchyard 90 acres Socioeconomic Environment Construction Workforce Approximately 100 personnel at peak construction Operating ~orkforce Approximately 50 personnel 2631B 5-24 E o [ L [j L [ [ [ L I I I I • I I I I • I •• I I I I I oo SCENARIO III KENAI POWER GENERATION MEDIUM LOAD [ [ [ [ [ [ [ r L~ [ L 6.0 KENAI AREA POWER GENERATION MEDIUM LOAD FORECAST The development of power generation facilities in the Kenai area which will utilize North Slope natural gas is dependent on the construction of a major,high pressure gas pipeline from the North Slope to a tidewater location near Kenai.The details concerning this pipeline and the attendant tidewater gas conditioning and liquefaction facilities are presented in The Governor's Economic Committee (1983) report entitl ed "Trans Al aska Gas System:Economics of an Al ternative for North Slope Natural Gas." The gas conditioning and liquefaction facilities associated with the Trans Alaska Gas System (TAGS)will have numerous power loads,many of which cannot be satisfied by any source except electricity.These loads will include lighting,certain types of heating,ventilation and air conditioning systems,pumps,various process coolers and compressors,controls,tools,and any shaft horsepower requirements that are intermittant,such as some refrigeration applications,or too small to be economical for a combustion turbine.Based on the electrical demand values required for the ANGTS gas conditioning facility and discussions with gas liquefaction process equipment vendors,the total peak electrical demand of these tidewater processing facilities has been estimated to be approximately 300MW.This value is only an approximation;the actual demand requirements will be dependent upon the type of liquefaction facility selected for design (e.g.compressor/expander system,cascade refrigerant system),and specific design decisions regarding various process power sources made during detailed engineering.To ensure that the Kenai power generation scenario presents a realistic development approach and that the entire Railbe1t utility system can support such a major contingency of demand, the anticipated electrical requirements of these processing facilities have been included in the electrical demand analysis.As TAGS will be developed in phases,the total electrical demand of the facilities has 2554B 6-1 been proportioned~based on the flow rates anticipated during each phase. This scenario~then~centers on a major electric generating station in the Kenai area near the terminus of the TAGS pipeline.By the year 2010~the station would consist of 7 combined cycle units and 1 simple cycle gas turbine to satisfy the medium energy demand forecast for the Rai1be1t and the additional power requirements of the TAGS gas conditioning and liquefaction faci1ities~a total of 1743 MW.The fuel for the power plant will be a blend of waste gas from the TAGS gas conditioning facilities and TAGS sales gas.A major electrical transmission system from the Kenai generating station to Anchorage is required.The Kenai to Anchorage lines would be operated at 500 kV and' emp10y·an underwater crossing of Turnagain Arm.To ensure system re1iabi1ity~both the 500 kV lines from Kenai to Anchorage and the 345 kV lines from Anchorage to Fairbanks would consist of two parallel lines.A residential/commercial gas distribution system for Fairbanks is not an integral part of this scenario~although it is not precluded as an adjunct to TAGS.The total construction cost of this scenario is $2.1 bi11ion~with total operation and maintenance costs of $0.8 billion per year.The present worth of these costs excluding fuel costs is $2.0 billion. The Kenai development scenario described above represents a revised scheme from that originally envisioned.The original scenario anticipated the use of gas conditioning facility waste gas only to fuel the electric generating station.Investigation of this alternative~ however~determined that the amount of waste gas available (approximately 430 MMSCFD)would only result in approximately 350 MW of electrical power.As this amount would probably be totally consumed within the TAGS gas processing facilities~it was decided to supplement the waste gas with TAGS sales gas to satisfy the electrical demands of the Railbelt and the TAGS facilities. 2554B 6-2 [ L~ [ L [ k L [ [ .l~ L L L [ [ [ [ [ [ r [' L 6.1 POWER PLANT 6.1.1 General The power generation technology selected for the Kenai locale is combined cycle utilizing 237 MW baseloaded plants (refer to Appendix B).The plants are identical in configuration with those described in Section 4.2.The difference in capacity rating is due to the slightly higher average annual temperature encountered in the Kenai 1oca 1e. Facilities required for the site and the site arrangement will be the same as that described in Section 4.2.Equipment arrangement will be as previously shown in Figures 4-1 and 4-2 and the site arrangement as shown in Figure 4-3.A total of 7 complete combined cycle plants plus 1 simple cycle gas turbine will be required to satisfy the demand for energy in the year 2010.The land area required for this development will be approximately 175 acres.The schedule for addition of these facilities is shown on Table 6-1 along with the total of new capacity on a yearly basi s. The functional parts of the power plant will include all the systems described in Section 4.2.Additionally,a system for gas quality monitoring will be necessary.The fuel.to be utilized ~i)l be a blend of waste gas and sales gas from the gas conditioning plant (see Section 6.1.4 Fuel Supply)• 6.1.2 Combustion Turbine Equipment The combustion turbines will be identical to those described previously except for one operating detail.The gas burner nozzle in the combustion chamber is typically designed to operate at a specific fuel heat value pl us or mi nus 10 percent.A nozzl e purchased to burn 400 Btu/ft3 fuel will .be useful to 440 Btu/ft3•In order to burn higher Btu content gas,a different nozzle would need to be installed. Several nozzles for a range of potential fuels should be inventoried for each turbine. 2554B .6-3 TABLE 6-1 NEW CAPACITY ADDITIONS AND FUEL REQUIREMENTS KENAI AREA POWER GENERATION -MEDIUM LOAD FORECAST New Capacity (MW)Gas Required (MMSCFy)l/ Year (Increment/Total)Waste Gas Sales Gas 1989 84/84 12,451.6 3,625.4 1990 84/168 24,903.3 7,250.7 1991 0/168 24,903.3 7,250.7 1992 237/405 49,864.6 14,518.3 1993 0/405 49,864.6 14,518.3 1994 69/474 49,924.1 14,535.7 1995 84/558 62,372.7 18,160.2 1996 84/642 74,827.0 21,689.7 1997 153/795 87,336.2 25,428.4 1998 84/879 99,786.8 29,053.5 1999 0/879 99,786.8 29,053.5 2000 69/948 99,848.2 29,071.4 2001 0/948 99,848.2 29,071.4 2002 168/1116 124,745.6 36,320.0 . 2003 0/1116 124,745.6 36,320.0 2004 69/1185 124,810.1 36,339.3 2005 168/1353 141,620.7 41,234.4 2006 69/1422 139,175.5 40,522.0 2007 84/1506 146,795.8 42,740.2 2008 153/1659 147,913.1 43,066.1 2009 84/1743 155,253.6 45,203.9 2010 0/1743 156,950.0 46,994.3 !!Values as calculated are shown for reproducibility only,and do not imply accuracy beyond a 100 MMSCFD level. 25548 6-4 C L [' L L e L [ 1 L [..' ...~ l~ [ [- r [ [ r' [ n \-) r L [ [ C C C C [ L l [ 6.1.3 Steam Plant The effect of burning a low Btu content fuel on the heat recovery steam generator {HRSG}will be negligible.Since the gas turbines are controlled at a constant gas temperature,the response of the system to a higher flow of noncombustibles in the waste stream will be to reduce the amount of excess air while maintaining gas temperature and mass flow constant.Therefore,no changes to the HRSG or the balance of the steam cycle from that described in Section 4.2 is expected. 6.1.4 Fuel Supply Depending upon the gas conditioning facility design chosen,a waste gas stream comprised mainly of carbon dioxide and heavier hYdrocarbons may be generated.It has been previously estimated {ref~r to Appendices A and B}that a waste gas stream of approximately 430'MMSCFD with a higher heating value of 195 Btu/ft3 could result.While it is possible to directly burn this waste gas in combustion turbines,it will require expensive redesign of the turbines,and increased equipment supply costs.Since the waste stream alone could not supply enough energy to satisfy demand through the year 2010,it was decided to blend the waste ~as with sales gas to achieve a minimum heating value of 400 Btu/ft {HHV}.Tnis resultant heating value does not require combustion turbine modifications.The required amounts of both waste and sales gas are shown in Table 6-1. 6.1.5 Electrical Equipment and Substation The electrical equipment,including the generators,will essentially be the same as that described for the North Slope and Fairbanks medium forecast scenarios {Sections 2.1 and 4.2}.Major differences involve the number of units installed,their actual ratings,and the bus voltage.Figure 6-1 presents a simplifi~d one line diagram of the substation.There will be 22 generators feeding the 11 transformers, each rated 200 MVA 13.8/115 kV.For this alternative 115 kV bus 2554B 6-5 13.&kV 2 2 22 2 2 2 2 2 2 <:2 2 2 2 2 2 22 2·2 22 LOCAL .-uRI I-I .tAICO ."val 1eC0NI0RATID KENAI POWER GENERATION MEDIUM LOAD FORECAST 8UB~TATION ONE LINE ICHEMATIC ALAlIA POWIR AUTHORITY NORTH ILOPE GAl FlAI.UTY lTUDY 500kV TO ANCHORAGE LOCAL TO ANCHORAGE 200MVAR ~ TYPICAL R ! 150 MYA TYPICAL LOCAL 200MVA TYPICAL LEGENDoGENERATOR =ORI'\'W\TRANSFORMER o C.IRCUIT BREAKER J\.I\/"v-REACTOR ~CAPACITOR 0'1 I 0'1 :~ L;,;...' c-:n·r..,.---""\:r-----;. ~.:;_J } [ [ [ [ [- [ [ [j rL [ U C [ C [ [ [ L L voltage was chosen to be compatible with the existing 115 kV Chugach Electric Association line in the area.Three circuits will provide power for local area loads.The outgoing voltage will be 500 kV with the two lines,each supplied by two 750 MVA transformers.The lines will terminate in Anchorage.Whenever possible,a breaker and a half configuration will be used. 6.1.6 Other Systems Depending on interpretation of regulations.governing the application of Best Available Control Technology (BACT),it may be necessary to add an NOx control system to the gas turbines at the·Kenai location.All other systems will be identical to those described for the Fairbanks medium load growth forecast (Section 4.2). The NOx control system will consist of either steam or water injection directly into the combustion chamber.This is used to control the gas temperature,keeping it below the range of high NOx formation. 6.2 TRANSMISSION SYSTEMS 6.2.1 Kenai to Anchorage Lin~ 6.2.1.1 Overview of the System To transmit medium forecast power from Kenai to Anchorage,a 500 kV transmission alternative was developed and found to be a cost effective voltage.Two routes were investigated in detail:a 150 mile long land based route around Turnagain Arm,crossing the mountains west of Girwood to Anchorage;and an underwater cable crossing of Turnagain Arm.The latter route was chosen as the better alternative.A brief description of the line is presented below. 2554B 6-7 The line,with its two circuits on separate towers,will originate at the Kenai generating plant substation and will run eastward to approximately Sterling.The two circuits will then run towards the northeast and follow an existing pipeline right-of-way.-The overland route on the Kenai peninsula will be 65 miles in length and will.. terminate at Gull Rock.From this point 4 mile-long cables will carry the power underwater to the north shore of Turnagain Arm to a location marked Isle 29,which is less than a ha1f-mi1e northwest of McHugh Creek.The remaining overhead line segment will parallel the Seward-Anchorage highway for about 25 miles before reaching the substation at Anchorage. This routing is made possible by recent advancements in cable technology developed by Pire11i of Italy and Standard Telefon O.G. Kabel Fabrik A/S of Norway,which are a~out to install,for the ~ritish Columbia ~dro and Power Authority,two 500 kV circuits,each consisting of three single phase cables between the British Columbia mainland and Vancouver Island.The Turnagain Arm crossing will consist of 7 cables:3 for each circuit and 1 spare. The system is simi 1ar to the one presented for the North Slope to Fairbanks connection,except there will be no intermediate switching stati ons and there wi 11 be a cab1 ecrossi ng.The desi gn of the· overhead section of the line will be .identica1 to the North Slope-Fairbanks connection described in Section 2.3 and Appendix 0, except that guyed type transmission towers will be used for this line and only 3 repeater stations will be required for communication purposes. 6.2.1.2 Alternatives Several alternative transmission corridors between Kenai and Anchorage were considered in order to select a reasonable route for cost estimating purposes.Factors considered were general engineering and environmental constraints.Of the many potential routes,two were investigated in detail.A·land based route was assumed to follow the 2554B 6-8 [ L~ [ ~.. [ [. [ [ [ r: 'L-,' [' L [ C C E o [ [ L L [ existing Chugach Electric Association (CEA)right-of-way,which generally follows the Sterling and Seward Highways,and which traverses the eastern end of Turnagain Arm.However,closer examination of that route in light of the major transmission facility requirements disclosed the following severe constraints: (1)The existing transmission lines between Portage and Indian Creek are co-located with the Seward Highway and the Alaska Railroad on a narrow bench between Turnagain Arm and the Chugach Mountains. The bench is at the base of a unifonmly steep slope which rises to above 3500 feet in elevation.The proposed transmission facilities could not reasonably be accommodated within or adjacent to the existing rights-of-way.One option for avoiding this area would be to traverse the Chugach Mountains between Portage and Anchorage.This woul d,however,.i nvol ve crossing difficult terrain,much of which is included in the Chugach State Park. (2)The existing CEA right-of-way parallels the Sterling Highway for most of its length.In the vicinity of Bear Mountain,designated wilderness areas within the Kenai National Wildlife Refuge are within close proximity of the highway.Development of transmission facilities of the magnitude required by this scenario would engender severe aesthetic impacts to travelers along this scenic highway,and possibly infringe on wilderness l.and use val ues. As a consequence of these severe routing constraints,this study focused on a transmission line corridor which utilizes a Turnagain Anm crossing from Gull Rock to McHugh Creek.The total length of this preferred corridor route is 94 miles,as compared to the 150 mile route which would be required for a completely overland route around the eastern end of Turnagain Arm. 2554B 6-9 6.2.2 Anchorage Substation The planned Anchorage substation is shown in Figure 6-2.The two 500 kV lines will terminate in two 750 MVA 345/525 kV transformers. The bus will feed the area transmi·ssion system using 138n45 kV transformers.From the bus two 345 kV lines will connect to Fairbanks.These lines will have shunt reactors but no series capacitors connected to them. 6.2.3 Anchorage to Fairbanks Line This line must carry about half the amount of power that the Fairbanks to Anchorage lines have to carry under previously discussed low growth forecast conditions (5ection·3.2).Therefore,one 345 kV line would be· adequate as far as power carrying capability and system performan'ce is concerned.However,the reliability of electric power transmission over a single line is very poor,making two lines in parallel a minimum requirement.With two lines,neither series compensation nor an intermediate switching station is required at 345 kV.Therefore,in this scenario,the 345 kV intertie will be fully extended and a second line will be built between Anchorage and Fairbanks using the Gilbert Commonwealth (1981)design. 6.2.4 Fairbanks Substation The Fairbanks substation will be the terminus of the two 345 kV lines. It will be a conventionally designed 345/138 kV substation using a breaker and a half scheme to supply the two 138/345 kV transformers that will provide power locally. 25548 6-10 r r't -r- I r I I C' !~.'·L [ C .L [ L .C, L -[ r:--:r-T::.r--;~c-J .ITT:J .~~en .rr-1 ;---,t -:-::J ~.["""j ~:-J ,-----' l ".;j l ', ..1 TO FAIRBANK5 KENAI POWER GENERATION MEDIUM LOAD FORECAST ANCHORAGE SUBSTATION ONE LINE SCHEMATIC DAleO IIfMCIllNCOIIPOMTlD '''11M I-I! ALAIKA 'OWl"AUTHO"ITY MOATH 1L000E GAl 'EA....IlY lTUDY Z.OO MVAR TYPICAL 750 MVA TYPICAL T TO KENAI T L.OCAL kvl LEGENDoGENERATOR ~Ollt'l'W\TRANSF"ORMER o C.IRCUIT BRE'AKER J'VV'v-REACTOR L"'""CAPACITOR ·STATIC VAR COMPEN.5ATOR 1.38 .... 6.3 COST ESTn~ATES 6.3.1 Construction Costs 6.3.1.1 Power Plant To support the derivation of total systems costs which is presented in Section 6.3.4,feasibility level investment costs were developed for the major bid lines items common to a 77 MW (ISO conditions)natural gas fired simple cycle combustion turbine and a 220 MW (ISO conditions) natural gas fired combined cycle plant.These costs are presented in Tables 6-2 and 6-3.The costs represent the total investment for the first unit to be developed at the site.Additional simple cycle units will have an estimated investment cost of $35,680,000 while additional combined cycle units will have an estimated investment cost of $128,060,000.The unit cost differential for addition units is due to significant reductions in line items 1 and 15,improvements to Site and Off-Site Facilities,and reductions in Indirect Construction Cost and Engineering and Construction Management. 6.3.1.2 Kenai to Anchorage Transmission Line Transmission line feasibility level i·nvestment cost estimates for the submarine cable crossing alternative are presented in Table 6-4.These estimates are based on two 500 kV lines of 1400 MW capacity with series compensation.A feasibility level investment cost estimate has also been prepared for the land based route which traverses the eastern end of Turnagain Arm.These estimates are presented in Table 6-5.As the sUbmarine cable crossing alternative i~preferred,only this estimate has been used in the derivation of total systems costs (Section 6.3.4). 25548 6-12 r [ r [~ [ [ [~ rL._ [ L [ [ [ C C [ [ L [ L TABLE 6-2 FEASIBILITY LEVEL INVESTMENT COSTS 77 MW SIMPLE CYCLE PLANT KENAI AREA POWER GENERATION -MEDIUM LOAD FORECAST (January,1982 Dollars) Total De scri pti onl/ Material Constructi on Di rect Cost ($1000)Labor ($1000)($1000) l.Improvements to Site 475 1,410 1,885 2.Earthwork and Piling 75 500 575 3.Circulating Water System 0 0 0 4.Concrete 475 2,145 4,505 5.Structural Steel Lifting 1,725 1,370 3,095 Equipment,Stacks 6.Buil di ngs 750 1 ;440 2,190 7.Turbine Generator 11 ,400 685 12,085 8.Steam Generator and Accessories 0 0 0 9.Other Mechanical Equipment 955 530 1,485 10.Pi pi ng 265 590 855 ll.Insulation and Lagging 35 135 170 12.Instrumentation 100 70 170 13.Electrical Equipment 1,535 2,665 4,200 14.Pa i nting 70 250 320 15.Off-Site Facilities 300 1,080 1,380 SUBTOTAL $18,160 $12,870 $31 ,030 Frei ght Increment 910 TOTAL DIRECT CONSTRUCTION COST $31,940 Indirect Construction Costs 1,780 SUBTOTAL FOR CONTINGENCIES 33,720 Contingencies (15%)5,060 TOTAL SPECIFIC CONSTRUCTION COST 38,780 Engineering and Construction 2,200 Management TOTAL CONSTRUCTION COST $40,980 11 The following items are not addressed in the plant investment pr.cing:laboratory equipment,switchYard and transmission facilities,spare parts,land or land rights,and sales/use taxes. 2554B 6-13 TABLE 6-3 FEASIBILITY LEVEL INVESTMENT COSTS 220 MW COMBINED CYCLE PLANT KENAI AREA POWER GENERATION -MEDIUM LOAD FORECAST _(January,1982 Dollars) Total De sc ri pti onl/ Materi al Constructi on Di rect Cost- ($1000)Labor ($1000)($1000) l.Improvements to Site 490 1,440 1,930 2.Earthwork and Piling 220 1,520 1,740 3.Circulating Water System 0 0 0 4.Concrete 1,485 6,730 8,215 5.Structural Steel Lifting 3,800 3,530 7,330 Equipment,Stacks 6.Buildings 1,800 3,600 5,400 7.Turbine Generator 30,700 2,590 33,290.8.Steam Generator and Accessories 9,600 4,320 13,920 9.Other Mechanical Equipment 6,230 3,120 9,350 10.Pi ping 1,630 3,055 4,685 1l.Insulation and Lagging 295 720 1,015 12.Instrumentation 1,700 290 1,990 13.Electrical Equipment 4,600 8,785 13,385 14.Painting 200 720 920 15.Off-Site Facilities 300 1,080 1,380 SUBTOTAL $63,050 $41,500 $104,550 Freight Increment 3,150 TOTAL DIRECT CONSTRUCTION COST $107,700 Indirect Construction Costs 4,310 SUBTOTAL FOR CONTINGENCIES 112,01 0 Conti ngencies (15%)16,800 TOTAL SPECIFIC CONSTRUCTION COST 128,810 Engineering and Construction -6,800 Management TOTAL CONSTRUCTION COST $135,610 !/The following items are not addressed in the plant investment pricing:laboratory equipment,switchyard and transmission facilities,spare parts,land or land rights,and sales/use taxes. 2554B 6-14 r f' L _; [ [ ~ [ [ L r= L. f'L, -L L l [ [- r [ L L [ FlL, C L' [ [ [ C f~ lJ [ .re » l~- ."- L L TABLE 6-4 FEASIBILITY LEVEL INVESTMENT COSTS SUBMARINE CABLE CROSSING ALTERNATIVE KENAI AREA POWER GENERATION -MEDIUM LOAD FORECAST (January,1982 Doll ars) Total De scri pti on1/ Material Construction Direct Cost ($1000)Labor ($1000)($1000) Switching Stations Substations 63,073 43,729 106,802 Energy Management System 11,400 9,400 20,800 Steel Towers and Fi xtures 112,370 130,909 243,279 O.H.Conductors and Devices 12,726 29,919 42,645 Submarine Cable and Devices 77 ,900 52,200 130,100 Clearing 4,164 4,164 SUBTOTAL 277 ,469 270,321 547,790 Land and Land Ri ght~/7,200 Engineering and Construction Management ..38,290 TOTAL CONSTRUCTION COST $593,280 1/The investment costs reflect two 500 kV lines,1400 MW capacity with series compensation.A 15 percent contingency has been assumed for the entire project and has been distributed among each of the cost categories shown.Sales/use taxes have not been i ncl uded. Y Assumes a cost of $40,000 per mile (Acres American Inc.1981)• 2554B 6-15 TABLE 6-5 FEASIBILITY LEVEL INVESTMENT COSTS LAND BASED ROUTE ALTERNATIVE KENAI AREA POWER GENERATION -MEDIUM LOAD FORECAST (January,1982 Do 11 ars). Total De scri pti onl!Materi a1 Construction Di rect Cost ($1000)Labor ($1000)($1000) Switching Stations 0 0 0 Substations 51,262 35,540 86,802 Energy Management System 11 ,400 9,400 20,800 Ste~l Towers and Fixtures 265,066 ·281,477 546,543 Conductors and Devices 20,522 48,248 68,770 C1 eari ng 0 6,720 6,720 SUBTOTAL 348,250 381,385 729,635 Land and Land Rightsfl 11,600 Engineering and Construction Management 51,100 TOTAL CONSTRUCTION COST $792,335 1/The investment costs reflect two 500 kV lines,1400 MW capacity with series compensation.A 15 percent contingency has been assumed for the entire project and has been distributed among each of the cost categories shown.Sales/use taxes have not been i nc1 uded.. -2/Assumes a cost of $40,000 per mile (Acres American Inc.1981). 2554B 6-16 [ !. r: L [ [ L [ L [ C C C [~ [~ [ l~ L l 6.3.1.3 Anchorage to Fairbanks Transmission Line Feasibility level investment cost estimates have been prepared for the Anchorage-Fairbanks connection.These estimates which are presented in Table 6-6 are based on one new 345 kV line without series compensation and an intermediate switching statiQn.The estimates also reflect upgrading of the Willow-Anchorage and Healy-Fairbanks segments of the present Intertie. 6.3.2 Operation and Maintenance Costs 6.3.2.1 Power Plant The power plant operation and maintenance (P&M)costs were derived to support the system planning studies (Appendix e).They reflect a review of figures from previous Rai1be1t studies,operation of other utilities,and salary requirements and expendable materials.The O&M costs for this scenario are estimated to be $O.0040/kWh. 6.3.2.2 Transmission Line Systems Annual operation and maintenance costs (January,1982 dollars)have been developed for the scenario's required transmission line faci1itie~ and total $12 mi1~ion per year.These costs should be viewed as an annual average over the life of the system.Actual OaM costs should be less initially,and will increase with time. 6.3.3 Fuel Costs For the economic analyses which follow fuel costs were treated as zero.This approach permits fuel cost and fuel price escalation to be treated separately;and makes possible SUbsequent sensitivity analyses of the .Present Wor~h of Costs for this scenario based upon a range·of fuel cost an~cost escalation assumptions. 25548 6~17 TABLE 6-6 FEASIBILITY LEVEL INVESTMENT COSTS ANCHORAGE TO FAIRBANKS TRANSMISSION SYSTEM KENAI AREA POWER GENERATION -MEDIUM LOAD FORECAST (January,1982 Do 11 ars) Total Materi al Constructi on Di rect Cost Descri pti onll ($1000 )Labor ($1000)($1000) Switching Stations Substations 38,531 32,100 70,631 Energy Management System 12,?00 10,960 23,260 Steel Towers and Fixtures 129,.214 182,091 .311,305 Conductors and Devices 20,049 53,183 73,232 C1 eari ng 41,572 41,572 SUBTOTAL 200,094 319,906 520,000 Land and Land Right~14,400 Engineering and Construction Management 36,400 TOTAL CONSTRUCTION COST .$570,800 !I The investment costs reflect one new 345 kV line without series compensation or an intermediate sWitching station,and the upgrading of the Willow-Anchorage and Healy-Fairbanks segments of the Intertie to 345 kV. 2/Assumes a cost of $40,000 per mi 1e (Peres Ameri can Inc.1981). 2554B 6-18 -r [ [ -r ( f' L f- L Of'I _ L [- [ C L L [ L L L L [ [-- ['. [ [ [ [ c [ L [ C [ E ~1~ [ [ L L [ 6.3.4 Total Systems Costs Total systems costs for Kenai reflect a very different situation than the North Slope or Fairbanks scenarios.The Kenai medium growth scenario recognizes that a pipeline and gas conditioning facility are required;however,these capital investments are external to the electricity generation system per see The costs of the pipeline and the gas conditioning facility should be reflected in the purchase price of the natural gas rather than in the capital or O&M outlays. The methodology and assumptions utilized to derive the systems costs which are presented below have been previously described in the Report on Systems Planning Studies (Appendix B).This methodology is consistent with previous studies of electric generating scenarios for the Railbelt,specifically Acres American,Inc.(1981),Susitna Hydroelectric Project Feasibility Report and Battelle (1982),Railbelt Electric Power Alternative Study.The period of the analysis was assumed to be 1982 through 201 O. The total systems costs for the Kenai medium growth scenario have been calculated.Annual capital outlays are presented in Table 6-7.Annual O&M costs are presented in Tabl e 6-8.Total annual costs are summarized in Table 6-9.The present worth of these costs,exclusive of fuel costs,is $2.0 billion as of 1982,assuming a discount rate of 3 percent and a value base of 1982 dollars. 6.4 ENVIRONMENTAL AND SOCIOECONOMIC CONSIDERATIONS The Kenai power plant and transmission line to Anchorage and Fairbanks will have many environmental effects similar to those discussed for the North Slope and Fairbanks scenarios.The environmental and socioeconomic considerations associated with the transmission line from Anchorage to Fairbanks will be identical to those discussed in Section 3.5,the North Slope Scenario (low load forecast),and therefore will not be repeated here.Power plant characteristics related to environmental impacts are summarized in Table 6-10. 2554B 6-19 TABLE 6-7 ANNUAL CAPITAL EXPENDITURES KENAI AREA POWER GENERATION -MEDIUM LOAD FORECAST (Millions of JanuarYs 1982 Dollars) Calendar Electricity Generated!!Transmi ssion Year Unlt A Unit B Line Total 1982 O.O.O.O. 1983 O~O.O.O. 1984 O.O.O.o. 1985 O.O.621.2 621.2 1986 O.2/O.142.8 142.8 1987 10.6 O.282.2 292.8 1988 35.68 O.114.9 150.6 1989 35.68 O.o.35.7 1990 O.o.O.o. 1991 53.65 71.36 O.125.0 1992 o.o.o.o. 1993 53.65 o.o.53.7 1994 35.68 o.o.35.7 1995 35.68 o.o.35.7 1996 53.65 35.68 o.89.3 1997 35.68 o.o.35.7 1998 O.o.o.o. 1999 53.65 o.o.53.7 2000 o.O.o.o. 2001 35.68 35.68 o.71.4 2002'o.o.o.'0. 2003 53.65 o.o.53.7 2004 35.68 35.68 o.71.4 2005 53.65 o.o.53.7 2006 35.68 o.o.35.7 2007 35.68 53.65 o.89.3 2008 35.68 o.o.35.7 2009 o.o.o.o. 2010 o.O.o.o. Total $689.$232.$1 s16l.$2 s083. l!Unit A refers to first unit built in a given year and Unit B to second unit built. ~/Includes site preparation activities for multiple unit site. 2554B 6-20 T~ L C' ru [ L [ 6 C 6 ~ [ L L [ L TABLE 6-8 ANNUAL NON-FUEL OPERATION AND MAINTENANCE COSTS KENAI AREA POWER GENERATION -MEDIUM LOAD FORECAST (Millions of January,1982 Dollars) Calendar Transmission Year Electricity Generated Line Total 1982 O.O.O. 1983 O.O.O. 1984 O.O.O. 1985 O.O.O. 1986 O.O.O. 1987 O.o.O. 1988 O.O.O. 1989 2.21 12.0 14.21 1990 4.42 12.0 16.42 1991 4.42 12.0 16.42 1992 10.64 12.0 22.64 1993 10.64 12.0 22.64 1994 12.46 12.0 24.46 1995 14.66 12.0 26.66 1996 16.87 12.0 28.87 1997 20.89 12.0 32.89 1998 23.10 12.0 35.10 1999 23.10 12.0 35.10 2000 24.91 12.0 36.91 2001 24.91 12.0 36.91 2002 29.33 12.0 41.33 .2003 29.33 12.0 41.33 ?004 31.14 12.0 43.14 ·2005 33.64 12.0 45.64 2006 34.72 12.0 46.72 2007 35.81 12.0 47.81 2008 36.90 12.0 48.90 2009 37.99 12.0 49.99 2010 39.08 12.0 51.08 Total $501.$264.$765. 2554B 6-21 TABLE 6-9 TOTAL ANNUAL COSTS KENAI AREA POWER GENERATION -MEDIUM LOAD FORECAST (Millions of January,1982 Dollars) Calendar Capital o &M Total Year Expenditures Costs Expenditures 1982 O.O.O. 1983 O.O.O. 1984 O.O.O. 1985 621.2 O.621.2 1986 142.8 O.142.8 1987 292.8 O.292.8 1988 150.6 O.150.6 1989 35.7 14.21 49.91 1990 O.16.42 16.42 1991 125.0 16.42 141.42 1992 O.22.64 22.64 1993 53.7 22.64 76.34 1994 35.7 24.46 60.16 1995 35.7 26.66 62.36 1996 89.3 28.87 118.17 1997 35.7 32.89 68.59 1998 O.35.10 35.10 1999 53.7 35.10 88.80 2000 O.36.91 36.91 2001 71.4 36.91 108.31 2002 O.41.33 41.33 2003 53.7 41.33 95.03 2004 71.4 43.14 114.54 2005 53.7 45.64 99.34 2006 35.7 46.72 82.42 2007 89.3 47.81 137.11 2008 35.7 48.90 84.60 2009 O.49.99 49.99 201 0 O.51.08 51.08 Total $2,083.$765.$2,848. Present Worth @ 3%$1,612.$436.$2,048. 2554B 6-22 ~[ r [ [ r~ r~ L r~ f' L [ L [; t L [' [~ t LO L Air Environment TABLE 6-10 ENVIRONMENT RELATED POWER PLANT CHARACTERISTICS NATURAL GAS COMBINED CYCLE KENAI AREA POWER GENERATION -MEDIUM LOAD FORECAST r-- 'L, c· [ r [ [ L E>; C L Emissions Particulate Matter Sulfur Dioxide Nitrogen Oxides PhYsical.Effects Water Environment Plant Water Requirements Water Injection Other Requirements Plant Discharge Requirements Demineralizer Steam Generators .Treated Sanitary Waste Floor Drains Land Envi ronment Land Requirements Socioeconomic Environment Be low standards Below standards Emissions variable within standards -dry control techniques would be used to meet calculated NO xstandardof0.014 percent of total volume of gaseous emissions.This value calculated based upon new sou'rce perfonmance standards, facility heat rate,and unit size. maximum structure height of 50 feet 800 GPM 200 GPM 40 GPM 70 GPM 15 GPM 25.GPM 175 acres [ [ [. l L Construction Workforce Operating Workforce 2554B Approximately 200 personnel at peak construction Approximately 150 employed personnel 6-23 6.4.1 Ai r Resource Effects As is typical of many exposed coastal locations,the air quality and meteorological conditions are generally favorable to the development of facilities such as power plants.It is not likely that an intense ll mar ine 1ayer ll ,which may restrict dispersion of pollutants,develops in this area.The air quality attains the applicable ambient standards,but the locale is burdened with several existing petroleum refinery emissions.A new natural gas fired power plant could probably be sited in the area with the use of appropriate emissions controls including water or steam injection to reduce nitrogen oxides emissions.The impact of water vapor emissions on the formation of fog must al so beconsi dered.The power pl ant must be carefully sited in order to avoid adding to the air quality impacts of the existing faci1 ities. Construction of the transmission line from Kenai to Anchorage will result in temporary air quality impacts.Heavy equipment and construction vehicles will cause fugitive dust and exhaust emissions, and slash burning will cause particulate emissions.As discussed in Section 2.5,these emissions would occur rarely and would be widely dispersed,generally in unpopulated areas.Long term impacts would be negl igibl e. 6.4.2 Water Resource Effects As in the Fairbanks scenario,water resource effects will be minimal. Groundwater will supply up to 1000 gpm for water or steam injection (for control of nitrogen oxides emissions),boiler make-up,potable supplies and miscellaneous uses.Wastewater discharges wii1 consist of boiler b10wdown,deminera1izer regenerant wastes and sanitary wastes, each treated within the plant to meet the appropriate effluent gUidelines.Because water used for water or steam injection is consumed rather than recycled,wastewater quantities will be less than 200 gpm. 2554B 6-24 L lJ [ L r lJ [ C [ [' [ J~ L L .6-25 2554B The transmission line from Kenai to Anchorage would cross the streams and creeks listed below. The water quality of these streams should not be directly affected if towers will be set back from the streambank at least 200 feet,and construction activities stay out of stream channels.Indirect impacts on the.waterbodies,however,will result from construction activity in the small .drainageways that feed the main channel,primarily from removal of vegetation (causing higher erosion rates),equipment crossings of small drainages,and access road construction.Because helicopter construction will be used along most of the route,the use of heavy equipment,vegetation removal,and access road construction should be minimal. Moose River Chickaloon River Little Indian Creek Furrow Creek Chester Creek Soldatna Creek Mystery Creek Big Indian Creek Potter Creek Campbell Creek Ship Creek The transmission line will cross Turnagain Arm from Gull Rock to the mouth of McHugh Creek via seven buried submarine cables.Cqnstruction phase impacts will consist of increased turbidity from the cable installation,and construction activity near the shore on both shorelines.Operation phase impacts will primarily be the potential for cable rupture and sUbsequent cable oil contamination of Turnagain Arm.The cable will be designed to have a very low probability of rupture over the life of the project.A synthetic cable oil, dodecobenzene,should be used for cable insulation.If this oil accidentally leaks,it will rise to the surface and quickly evaporate when exposed to air.This oil is used specifically to ~inimize environmental effects associated with a cable rupture~ rL [ [ C C C [ [ L [ L [ [ [ [ [ r [: p L"'; 6.4.3 Aquatic Ecosystem Effects Because groundwater will provide the power plant's water supply,and wastewater discharges will be low,the power p1ant;'n Kenai will not significantly affect aquatic resources. Soldatna Creek and Moose River flow into the Kenai River System,a major river for anadromous fish habitat.Sodatna Creek provides spawning and rearing habitat for silver salmon,and Moose River contains king,silver,and sockeye salmon (U.S.Army Corps of Engineers 1978).Sedimentation of these water bodies,as discussed in the previous section,could affect spawning and rearing habitat in these streams.Because.helicopter construction will be used for most of the route,however,sedimentation effects would be relatively minor. Impacts to freshwater aquatic resources will be mitigated primarily through the control of sedimentation of waterbodies,keeping construction equipment out of streambeds and wetlands,and avoiding areas of high biological value.These mitigation measures are discussed in greater detail in Section 2.5.3 for the North Slope scenari o. Crossing Turnagain ~rm'with underwater cables poses additional environmental hazards.Turnagain Arm is an environmentally sensitive area in the general vicinity of the project that contains marine mammals,inclUding harbor seals,sea lions and beluga whales (U.S. Department of Commerce 1979).Salmon are present in some of the small streams that enter this area (Alaska Department of Fish and Game 1978). Installation of buried,submarine cables will temporarily disrupt the sea floor along the cable route and increase turbidity and suspended solids in the vicinity of the crossing.Tidal currents could carry suspended sediment beyond the immediate crossing site.Special construction techniques should be used to minimize disturbance of the substrate.Installation should take place when biological activity is at its lowest point in the yearly cycle. 2554B 6-26 [ L [ L [ C [ L L L. f' t= l [ L [-- [ [ [ [' p- '--..J C L c [ C C C [ L L L l An accidental rupture of a cable would leak cable oil into the aquatic environment.As discussed in the previous section,the cable oil used, dodecobenzene,was chosen because it evaporates when exposed to air, thereby minimizing environmental impacts. The cables may operate at a temperature level above ambient conditions.Because the cables will be buried six to ten feet,only the substrate temperature and not water temperature would be elevated (Bonneville Power Administration 1981). 6.4.4 Terrestrial Ecosystem Effects Because the Kenai power plant will be located in an area already extensively developed,little habitat degradation will occur.The area disturbed for power plant construction,approximately 140 acres,will not significantly affect terrestrial resources in the area. The transmission route passes through an area of caribou habitat northeast of Kenai (University of Alaska 1974).Little alteration of caribou habitat will result from construction of the transmission line because the animal utilizes cover types that require little if any c1 eari ng. Much of the route between Kenai and·Anchorage is within moose rangeland.However,because moose utilize many different habitat types,they will be the least adversely affected by habitat alterations (Spencer and Chatelain 1953).Where the proposed route crosses heavily forested areas,moose will benefit from additional clearing of the right-of-way and the subsequent establishment ofa subclimax community (Leopold and Darling 1953).The route does not cross Da1l sheep or mountain goat habitat. 25548 6-27 The transmission line corridor passes near Chickaloon Flats and Potter Marsh on Turnagain Arm,both key waterfowl areas.Various puddle ducks,geese and sandhill cranes feed and rest during seasonal migration periods in these areas.The shoreline of Turnagain Arm is also used by seals and sea lions.Theotransmission line would not directly affect this wildlife habitat. Construction of the submarine cable could slightly affect terrestrial habitat indirectly by increasing turbidity of Turnagain Arm and thereby affecting food sources.This would be a temporary effect during the construction phase only. The transmission corridor passes through several vegetation types. Between Kenai and Sterling,the vegetation is primarily bottomland spruce-popl ar forest.As the corri dor extends northeasterly towards Turnagain Arm,the vegetation becomes upland spruce-hardwood forest and,on the foothills of the Kenai Mountains,coastal western hemlock-Sitka spruce forest.North of Turnagain Arm,the vegetation is primarily bottomland spruce-poplar forest (University of Alaska 1974). Transmission line construction will necessitate clearing a 220-foot wide corridor in all forested areas.Over the length of the corridor, it is assumed that a total of 550 acres woul d be cleared withi n the . ri ght-of-waj. 6.4.5 Socioeconomic and Land Use Effects The socioeconomic effects of locating a gas conditioning facility and electrical generating plant depends primarily on the size of the in~igrating work force.Land use impacts are not expected to occur as these facilities are compatible with the heavily industrialized development that dominates the Kenai-Nikiski area. 2554B 6-28 CL [ L C C C [ [' L L L [ [ C C C [' > [ l~ [ [~ The size of the construction work force for the generating facility is expected to be approximately 175 persons.The construction schedule would require that a unit be constructed every year during the period 1993-2010,with the exception of 1994 and 1999,when no new units would be required.The duration and time of the construction period would be 4 to 5 months in the summer. The extent to which local people would be hired would depend on the match of skills required for the project to those skills of the available labor force.Labor union policies would also influence the extent of local hires on the project.The in-migrating work force would have to seek temporary housing on thei.r own since housing would not be provided at the project site.The magnitude of the impacts on the local housing supply would depend on the vacancy rate for the summer of each year a unit was constructed. The project is expected to have little effect on the unemployment rate since employment on the project would be seasonal.In addition,these job openings would be competitive with other employment opportunities in seasonal industries such as construction and fisheries. The operations work force is expected to be approximately 100.The magnitude of potential impacts depends on the availability of local labor to meet the work force requirements.If the majority of the employees migrate to the Kenai-Nikiski region,.the demand for housing could exceed the supply. Construction of the transmission lines between Kenai and Anchorage is expected to take 22 months.-The peak work force is estimated at 221 persons during the last 6 months and average construction work force is expected to be approximately 163 workers.It is assumed that workers would be hired from the labor pools of Kenai and Anchorage. 25548 6-29 I I I I I I I I I I I I I I I I I oo .SCENARIO III KENAI POWER GENERATION LOW LOAD [ [ [ [ [ [~ [ r L [ c C B b B L L [ [ L 7.0 KENAI AREA POWER GENERATION LOW LOAD FORECAST The Kenai area power generation scenario,under the low load forecast, is also depedent upon the development of TAGS.The anticipated electrical requirements associated with TAGS gas conditioning and liquefaction facilities have also been included in the electrical demand analysis.The development scheme will consist of 4 combined cycle plants and 2 simple cycle combustion turbines conditioning facility.Fuel for the power plant will bea blend of waste gas and sales gas.A reliable electrical transmission system will require parallel lines from the Kenai area to Anchorage (at 500 kV and underwater across Turnagain Arm)and from Anchorage to Fairbanks (at 345 kV).A residential/commercial gas distribution system is not a part of the scenari o.Constructi on costs for thi s scenari 0 are $1.7 billion,with total operation and maintenance costs of $0.6 billion.The present worth of these costs excluding fuel costs is $1.7 billion. The information in this section is intended to include only those conditions which are significantly different from those for the medium load forecast presented in Section 6.0. 7.1 POWER PLANT This scenario will require four complete combined cycle plants,each capable of generating 237 MW and two simple cycle combustion turbines, to satisfy the low load forecast demand for energy in the year 2010. The first gas turbine unit will go on line in 1990.The scheduled additions are summarized in Table 7-1 and details are addressed in Appendix B.·Fuel requirements for this scenario are also shown in Table 7-1. 2593B 7-1 TABLE 7-1 NEW CAPACITY ADDITIONS AND FUEL REQUIREMENTS KENAI AREA POWER GENERATION -LOW LOAD FORECAST New'Capacity (MW)Gas Requirements (MMSCFD)!/ Year (Increment/Totai)Waste Gas Sales Gas 1990 84/84 12,451.6 3,625.4 1991 0/84 12,451.6 3,625.4 1992 153/237 24,962.1 7,267.8 1993 0/237 24,962.1 7,267.8 1994 84/321 37,413.5 10,893.2 1995 84/405 49,864.6 14,518.3 1996 0/405 49,864.6 14,518.3 1997 '153/558 62,372.7 18,160.2 1998 0/558 62,372.7 18,160.2 1999 0/558 62,372.7 18,160.2 2000 0/558 62,372.7 18,160.2 2001 84/642 74,827.0 21 ,689.7 2002 69/711 74,886.2 21,803.5 2003 0/711 74,886.2 21,803.5 2004 84/795 .87.,336.2 25,428.4 2005 84/879 99,786.8 29,053.5 2006 69/948 99,848.2 29,071.4 2007 0/948 99,848.2 29,071 .4 2008 84/1032 110,241.2 32,097.3 2009 0/1032 95,864.8 27,911.6 2010 84/1116 117,735.7 34,279.4 !/Values as calculated are shown for reproducibility only,and do "not imply accuracy beyond a 100 MMSCFD level. 2593B 7-2 f~' L r·-: '; L r 1 [ L l f" L L [ C B b [j [ [ [ L [ Facilities required for the site and the site arrangement will be the same as that described in Section 4.2.Equipment arrangement will be as previously shown in Figures 4-1 and 4-2 and the site arrangement as sho~n in Figure 4-3.The land area required for this development will be approximately 120 acres. The one line schematic of the low forecast generation plant substation is shown in Figure 7-1.It is essentially a scaled down version of Figure 6-1.The number of generators is reduced to 14 and only one I transformer will supply each of the 500 kV lines,which will be without series compensation. 7.2 TRANSMISSION SYSTEM The Kenai-Anchorage transmission system will be similar to the medium forecast design inclUding the utilization of 7 cables:3 for each circuit and 1 spare (Section 6.2).Series compensation is not required,however, because the power transmitted to Anchorage in this low forecast case will be much reduced from that of the medium forecast. Installing a reduced number of cables under Turnagain Arm was investigated but was not considered feasible because it is unlikely that the required switehyards could be located at the two terminations due to the lack of suitable land.During the system studies performed for this project,the possibility of transmitting the power on two 230 kV circuits,with one intermediate switching station,was also considered.Complete investigation of this system would have required detailed studies far beyond the scope of this project.However,such an alternative should be investigated during detailed engineering. At the substation in Anchorage the 500 kV voltage will be transformed to 345 kV for transmittal to Fairbanks and to supply local Anchorage loads. The one line diagram would be similar to that presented in Figure 6-2, except that there will only be two 750 kVA transformers at the substation and the 500 k·V 1i nes will not be seri es compen.sated.The Fa i rbanks SUbstation will terminate the two 345 kV circuits and supply,via transformers,the local area load at 138 kV. 25938 7-3 ZOOMVA TYPICAL LOCAL LOCAL 750MVA TYPICAL 500KV LOCAL 200 MVAR TYPICAL I.-Jl/\/\_....1,/1 TO ANCHORAGE LEGENDoGENERATOR :=OR""",,TRANSFORMERoCIRCUITBREAKER .JVV\r REACTOR ;:k CAPACITOR TO ANCHORAGE ALAlIA 'OWIER AUTHORITY NORTH IlOH GAl nAl.loITY lTUDY KENAI POWER GENERATION LOW LOAD FORECAST- 8UB8TATION ONE LINE ICHEMATIC ,18UItI 7-t DAleO IERVlCEIINCORIIOMTfD ""--0L..!L .. --------,: J ------r'r L, [ [ [ [ [' [ r L r L (J C L L [ [ [ [ 7.3 COST ESTIMATES 7.3.1 Construction Costs 7.3.1.1 Power Pl ant The capital cost of simple cycle combustion turbines and combined cycle facilities are the same as that presented in Section 6.3 for the medium load forecast. 7.3.1.2 Transmission Line Systems Feasibility level investment cost estimates for the submarine cable crossi ng a l.ternative for the Kenai -Anchorage 1i ne are presented in Table 7-2.These estimates are based on two 500 kV lines of 700 MW capacity without series compensation.A feasibility level investment cost estimate has also been prepared for the land based route which traverses the eastern end of Turnagain Arm.These estimates are presented in Table 7-3.As the submarine cable crossing alternative is preferred,only this estimate has been used in the derivation of total systems costs (Section 7.3.4). The construction costs associated with the Anchorage-Fairbanks line are the same for both the medium and low growth forecasts.These costs were previously presented in Table 6-6. 7.3.2 Operation and Maintenance Costs Power plant operation and maintenance (O&M)costs are the same for both the medium and low load forecasts,$0.0040/kWh.Transmission line O&M costs are estimated to be $12 million per year.These costs should be viewed as an annual average over the life of the system.Actual O&M costs should be l~ss initially and will increase with time~ 25938 7-5 TABLE 7-2 FEASIBILITY LEVEL INVESTMENT COSTS SUBMARINE CABLE CROSSING ALTERNATIVE KENAI AREA POWER GENERATION -LOW LOAD FORECAST (January 1982 Dollars) Total Material Construction Di rect Cost Description!!($1000)Labor ($1000)(-$1000) Switching Stations Substations 41,620 30,885 72,505 Energy Management System 11,400 9,400 20,800 Steel Towers and Fixtures 112,370 130,909 243,279 O.H.Conductors and Devices 12,726 29,919 42,645 Submarine Cable and Devices 77 ,900 52,200 130,100 Clearing 4,164 4,164 SUBTOTAL 256,016 257,477 513,493 Land and Land Ri ght~/7,200 Engineering and Construction Management 35,950 TOTAL CONSTRUCTION COST $556,643 1/The investment costs reflect two 500 kV lines,700 MW capacity with no series compensation.A 15 percent contingency has been assumed for the entire project and has been distributed among each of the cost categories shown.Sales/use taxes have not been i ncl uded. 'E./Assumes a cost of $40,000 per mile (Acres American Inc.1981). 2593B 7-6 ..[ [~ ! r i- f- t F3 L~J r--' L [ C [: E .[ L [ [ [ [; L [- [ [ [ [' [' n L c L [ U B G B L C [ L L TABLE 7-3 FEASIBILITY LEVEL INVESTMENT COSTS LAND BASED ROUTE ALTERNATIVE KENAI AREA POWER GENERATION -LOW LOAD FORECAST (Janua~1982 Dollars) Total Materi a1 Constructi on Di rect Cost Descri pti on.!/($1000)Labor ($1000)($1000) Switching Stations Substations 30,140 22,366 52,506 Energy Management System 11 ,400 9,400 20,800 Steel Towers and Fixtures 265,066 281,477 546,543 Conductors and Devices 20,522 48,248 68,770 Cl eari ng 6,720 6,720 SUBTOTAL 327,128 368,211 695,339 La nd a nd La nd Ri ghtsY 11 ,600 Engineering and Construction 48,700Management TOTAL CONSTRUCTION COST $755,639 1/The investment costs reflect two 500 kV lines,700 MW capacity with no series compensation.A 15 percent contingency has been assumed for the enti re project and has been di stri buted among each of the cost categories shown.Sales/use taxes have not been i ncl uded. Y Assumes a cost of $40,000 per mile (Acres American Inc.1981). 2593B ·7-7 7.3.3 Fuel Costs For the economic ana1y"ses which foll ow fuel costs were treated as zero.This approach permits fuel cost and fuel price escalation to be treated separately;and makes possible sUbsequent sensitivity analyses of the Present Worth of Costs for this scenario based upon a range of fuel cost and cost escalation assumptions. 7.3.4 Total Systems Costs Total systems costs for the Kenai low load growth scenario are constructed in a manner identical to that used for the Kenai medium load growth scenario,except for the number of power plants installed an~operated. The methodology and assumptions utilized to derive the systems costs .which are presented below have been previously described in the Report on Systems Planning Studies (Appendix B).This methodology is consistent with previous studies of electric generating scenarios for the Rai1belt,specifically Acres American,Inc.(1981),Susitna Hydroelectric Project Feasibi1ty Report and Battelle (1982),Rai1belt Electric Power Alternatives Study.The period of the analysis was assumed to be 1982 through 2010. Annual capital expenditures are presented in Table 7-4.Annual O&M costs are presented in Table 7-5.The summary of all annual costs is presented in Table 7-6.For comparison purposes the 1982 present worth of costs,assuming a discount rate of 3 percent and excluding fuel costs,is $1.7 billion (1982 dollars). 7.4 ENVIRONMENTAL AND SOCIOECONOMIC CONSIDERATIONS The Kenai power plant for the low load forecast will consist of three combined cycle units,in contrast to the five combined cycle and two simple cycle units for the medium load forecast.Power plant characteristics related to environmental resources are summarized in Table 7-7. 2593B 7-8 rl . L I \ rL. [ [j b [ L L L L [ L [ L [ C r-' L_J [ n L: r l [ C D C [ [ [ [ [ [ TABLE 7-4 ANNUAL CAPITAL EXPENDITURES KENAI AREA POWER GENERATION -LOW LOAD FORECAST (Millions of January,1982 Dollars) Calendar Electricity Generated Transmission Year Onlt A Omt B Line Total 1982 O.O.O.O. 1983 O.O.O.O. 1984 o.O.o.O. 1985 O.O.O.O. 1986 o.O.603.2 603.2 1987 o.O.138.6 138.6 1988 10.60 o.274.0 284.6 1989 35.68 O.111.6 147.3 1990 o.O.O.o. 1991 35.68 53.65 O.89.33 1992 o.O.O.O. 1993 35.68 O.o.35.7 1994 35.68 o.o.35.7 1995 O.O.O.O. 1996 53.65 35.68 O.89.3 1997 O.O.O.O. 1998 O.O.O.O. 1999 O.O.O.o. 2000 35.68 O.O.35.7 2001 53.65 O.O.53.7 2002 O.O.O.O. 2003 35.68 O.o.35.7· 2004 .35.68 O.O.35.7 2005 53.65 O.O.53.7 2006 O.O..O.O. 2007 35.68 O.O.35.7 2008 O.O.O.O. 2009 35.68 O.O.35.7 201 0 O.O.O.O. Total $405.$89.$1 ,128.$1,710. 25938 7-9 TABLE 7-5 ANNUAL NON-FUEL OPERATION AND MAINTENANCE COSTS KENAI AREA POWER GENERATION -LOW LOAD FORECAST (Millions of January,1982 Dollars) Calendar El ectri ci ty Transmission Year Generated Line Total 1982 O.O.O. 1983 O.O.O. 1984 O.O.O. 1985 O.O.O. 1986 O.O.O. 1987 O.O.O. 1988 O.O.O. 1989 O.O.O. 1990 2.21 12.0 14.21 1991 .2.21 .12.0 14.21 1992 6.23 12.0 18.23 1993 6.23 12.0 18.23 1994 8.44 12.0 20.44 1995 10.64 12.0 22.64 1996 10.64 12.0 22.64 1997 14.66 12.0 26.66 1998 14.66 12.0 26.66 1999 14.66 12.0 26.66 2000 14.66 12.0 26.66 2001 16.87 12.0 28.87 2002 18.68 12.0 30.68 2003 18.68 12.0 30.68 2004 20 ..89 12.0 32.89 2005 23.10 12.0 35.10 2006 24.91 12.0 36.91 2007 24.91 12.0 36.91 2008 26.62 12.0 38.62 2009 23.15 12.0 35.15 201 0 27.68 12.0 39.68 Total $331.$252.$583. 2593B 7-10 L [ l~ , r l cL~ [ [ L ~ r [ [ [ L [ [ [ [ [ [ [ n L nL [ C G C 8 L [ L [ E TABLE 7-6 TOTAL ANNUAL COSTS KENAI AREA POWER GENERATION -LOW LOAD FORECAST (Millions of January,1982 Dollars) Calendar Capital o &M Total Year Expendi tures Costs Expenditures 1982 O.O.o. 1983 O.O.O. 1984 O.O.-o. 1985 O.O.o. 1986 603.2 O.603.2 1987 138.6 O.138.6 1988 284.6 O.284.6 1989 147.3 O.147.3 1990 o.14.21 14.21 1991 89.3 14.21 103.51 1992 O.18.23 18.23 1993 35.7 18.23 53.93 1994 35.7 20.44 56.14 1995 O.22.64 22.64 1996 89.3 22.64 111 .92 1997 o.26.66 26.66 1998 o.26.66 26.66 1999 o.26.66 26.66 2000 35.7 26.66 62.36 2001 53.7 28.87 82.57 2002 O.30.68 30.68 2003 35.7 30.68 66.38 2004 35.7 32.89 68.59 2005 53.7 35.10 88.80 2006 o.36.91 36.91 2007 35.7 36.91 72.61 2008 O.38.62 38.62 2009 35.7 35.15 70.85 201 0 o.39.68 39.68 Total $1,710.$583.$2,292. Present Worth @ 3%$1,342.$331.$1,673. 2593B 7-11 TABLE 7-7 ENVIRONMENT RELATED POWER PLANT CHARACTERISTICS COMBINED CYCLE POWER PLANT KENAI AREA POWER GENERATION -LOW LOAD FORECAST Air Environment Emissions Particulate Matter Sul fur Di oxi de Nitrogen Oxides Physical Effects Be low standards Below standards Emissions variable without standards - dry control techniques would be used to meet calculated NOx standard of 0.014 percent of total volume of gaseous emissions.This value calculated based upon new source performance standards, facility heat rate,and unit size. Maximum structure height of 50 feet [ [' n [ 1- l __~ [ [, G Water Environment Plant Water Requirements 500 GPM Plant Discharge Quantities 100 GPM Wastewater Holding Basin including treated sanitary waste,floor drains,boiler blow-down,and demineralizer wastes Land Environment Land Requirements Plant and Switchyard 120 acres Socioeconomic Environment Construction Workforce Approximately 200 personnel at peak construction Operating Workforce Approximately 130 personnel 2593B 7-12 cl~ [ [j [J t [ [~ [ r' L [' l [ [ [ [ [ L [ C c L [ D o [j r.~J.]D [ L [ L L Approximately 500 gpm of fresh water will be supplied by groundwater for water or steam injection (for NOx control),equipment wash-down, boiler make-up water,and potable supplies.This amount of water will not significantly affect groundwater supplies in the area.Wastewater discharges will be less than 100 gpm and will be treated to meet effluent guidelines. Aquatic resources,as for the medium load forecast,will not be significantly affected.Plant acreage will be approximately 120 acres as compared to 175 acres for the medium load forecast.Terrestrial impacts are correspondingly reduced. Impacts associated with the transmission line from Kenai to Anchorage and on to Fairbanks are identical to those discussed in Section 6.4 for the medium load forecast. Socioeconomic impacts are expected to be similar to those for the medium load forecast.They would be less significant for the low load forecast.The in-migrating work force,which would have to seek temporary housing on their own,would be smaller than for the medium growth forecast,and thus would cause fewer demands on local housing and public services. 25938 7-13 I I I I I I I I I I I I I I I I il_ Do COMPARISON OF SCENARIOS [ r -"- , [ [ [ [ [ r~ L [ [ [ [ [ 8.0 COMPARISON OF SCENARIOS The three development scenarios have a common purpose of meeting the electrical generating needs of the Rai1be1t region using North Slope gas as a fuel source.However,the electric generating schemes and auxiliary systems vary widely among the scenarios making comparison of their relative merits complex.Table 8-1 is a side-by-side comparison of some of the important features of the three scenarios for both medium and low load forecasts.Each power plant meets the respective electricity demand forecast for the Rai1be1t.The Kenai plants also include the anticipated electrical requirements of the TAGS gas conditioning and liquefaction facilities.Simple cycle units are the recommended technology for electric generators on the North Slope,but combined cycle is more appropriate for the other two scenarios.The environmental and socioeconomic effects of all development scenarios are SUbstantial,but none have been identified which would preclude any project.All scenarios are technically feasible from an engineering point of view. The ultimate feasibility of each development scenario described herein will depend upon a comparison of power costs between these scenarios and alternative electric generating technologies.Such comparisons are outside Ebasco's scope of work,bU~can be considered as a logical extension of these studies which may be performed by the Alaska Power Authority. 26038 8-1 Power Plant Location and Demand Forecast TABLE 8-1 COMPARISON OF SCENARIOS Factor North Slope Medium Low Fairbanks Medium Low Kenai Medium Low [ [ r', [ I~ l, Power Plant Capac i ty (MW) Required Units (Simple Cycle/Combined Cycle) Plant Site Acreage North Slope to Fairbanks Transmission Lines (500 kV) Fairbanks to Anchorage Transmission Lines (345 kV) 1365 15/0 90 2 3 728 8/0 60 2 2 1383 2/5 140 NA1/ 3 726 0/3 90 NA 2 1743 1/7 175 NA 2 1116 2/4 120 NA 2 [ L Kenai to Anchorage Transmission Lines (500 kV) North Slope to Fairbanks Pipeline Compressor Stations POWER GENERATION (1982 $P~ilion) Capital Investment Total O&M Present Worth DISTRIBUTION SYSTEM (l 982 $Bill ion) Capital Investment Total O&M Present Worth 1/NA -Not applicable 2603B NA NA NA NA 4.2 3.3 1.1 0.7 3.8 2.7 NA NA NA NA NA NA 8-2 NA 10 6.5 0.8 ,5.4 1.2 0.09 0.9 NA 3 4.9 0.4 3.6 1.6 0.04 1.1 2 NA 2.1 0.8 2.0 NA NA NA 2 NA 1.7 0.6 1.7 NA WA NA [ [ L [ =-0.,f ~( l '\ ! ~- ----! __~:d [ '0. .-.~ '['" L, [, ['., I I I I I I I I I I I I '. I I I I il oo REFERENCES [ L [, [" [ [' L o E § C C'· U tJ [ 9.0 REFERENCES Acres Pinerican,Inc.1981.Susitna hydroelectric project - feasibility report -Volume 1,engineering and economics aspects, final draft.Alaska Power Authority.Anchorage,Alaska. Alaska Department of Fish and Game.1978.Alaska Fisheries Atlas. Vol urnes I and 11.Alaska Department of Fi sh and Game.Juneau', Alaska.. Battelle Pacific Northwest Laboratories.1982.Rai1be1t electric power alternative study:evaluation of rai1be1t electric energy plans -comment draft.Office of the Governor,State of Alaska. Juneau,Alaska (February 1982). Beau1aurier,D.L.,B.W.James,P.A.Jackson,J.R.Meyer,and J.M.Lee, Jr.1982.Mitigating the incidence of bird collisions with transmission lines.Paper to be presented at the Third Symposium on Environmental Concerns in Rights-of-way Management,San Diego, California,February 15-18,1982.21 pp. Bonneville Power Administration.1981.Underground cable systems: .'Potentia1 environmental impacts,Draft Report.Bonneville Power Administration,Washington,D.C. Bureau of Land Management.1980.The utiliy corridor,land use decisions.U.S.Department of the Interior,Bureau of Land Management,Fairbanks,Alaska. Commonwealth Associates,Inc.1982.Environmental Assessment Report for the Anchorage-Fairbanks Transmission Intertie.Alaska Power Authority,Anchorage,Alaska. Commonwealth Associates.1978.Model for the ready definition and approximate comparison of alternative high voltage transmission systems.DOEIET 1591"6-1. Commonwealth Associates,Inc.1981.Anchorage-Fairbanks transmission intertie route selection report. The Governor's Economic Committee.1983.Trans Alaska Gas System: economics of an alternative for North Slope Natural Gas.State of Alaska,Office of the Governor,Anchorage,Alaska. Leopold,A.and F.Darling.1953.Effects of land use on moose and caribou in Alaska.Transactions of the North American Wildlife Conference.18:553-582. North Slope Borough.1978.Coastal management program,Pr~dhoe Bay Area.North Slope Borough,Barrow,Alaska. 2588B 9-1 Schmidt,D.R.,Neterer,C.,Willing,D.,Troy,P.Olson.1981. Fisheries resources along the Alaska Gas Pipeline route (Prudhoe Bay to Yukon Territroy)proposed by Northwest Alaskan Pipeline Company.A summary report.Prepared for Northwest Alaskan Pipeline Compay by LGL Alaska Research Associates,Inc.608 p. Spencer,D.L.,and E.F.Chatelain.1953.Progress in the management of the moose of South central Alaska.Transactions of the North American Wildlife Conference.18:539-552. u.S.Army Corps of Engineers.1978.Kenai river reivew.U.S.Army Corps of Engi neers,Al aska Di stri ct.Anchorage,Al aska. U.S.Department of Commerce.1979.Environmental assessment of the Alaskan Continental Shelf,Lower Cook Inlet Interim synthesis report.U.S.Department of Commerce,National Oceanic and Atmospheric Administraton,Environmental Research Laboratories, Boulder,Colorado. u.S.Department of Commerce.Federal safety standards for transportation of natural gas and other gas by pipeline.49 CFR Part 293,Latest Edition. U.S.Department of Commerce.American standard code for gas transmission and distribution piping systems.B 31.8,Latest edition. University of Alaska,Arctic Environmental Information and Data Center. 1974.Alaska Regional Profiles,Southercentral Region.State of Alaska,Office of the Governor,Juneau,Alaska. 2588B 9-2 [" r t- ~" [. [", L, ,.c L [~ L· [' C. L L, L'-, .-, L b. F -- I ...... I", I~ .- I I- I I- I I- I. I I." I I I II Dn APPENDIX A ~-..- [ "...., [ r--' [ L [~' ~0 L r.:, nL...,. [ L [ ~. Q C.. ~ [ l L ! L {'. l c. APPENDIX A REPORT ON EXISTING QATA AND ASSUMPTIONS NOVEMBER 1982 A4.0 GAS SUPPLY AND AVAILABILITY ••• • • • • • • • • • • • •0 • • • • • A6.0 ECONOMIC ASSUMPTIONS . . AS.O ENGINEERING ASSUMPTIONS Aiv A3-1 o • • • • • • • • • • • • • o •••.• TABLE OF CONTENTS ... ... . . ... ... ... . . .A3.0 GAS COMPOSITION Al.O INTRODUCTION. A2.0 BACKGROUND .•. SUMMARY .. . .•. [ [--, c-- r~ \:"_.~ r- L r--- c- -(.- rr r L.(. c c c u· ~ ,- C f,.- L i..••_ C ! L A7.0 OTHER QUESTIONS AND ISSUES .. ADDENDUM A -BIBLIOGRAPHY ADDENDUM B -LIST OF CONTACTS Ai; LIST OF TABLES Tab1 e No.Tit1 e Page A3-1 NORTH SLOPE NATURAL GAS COMPOSITION A'3-2 AS-1 PRELIMINARY GAS REQUIREMENTS FOR POWER AS-2 GENERATION AND FAIRBANKS RESIDENTIAL/ COMMERCIAL USE IN THE YEAR 2010 A5-2 TRANSMISSION LINE CONDUCTOR LOADINGS AS-5 A6-1 INVENTORY OF FUEL PRICES IN FAIRBANKS A6-2 Aiii [ L [ C L [ [: L L L r~ r~ r~~ l-' [~ l~ [. [ r'. L [ C C C L [ L t~ l... U L SUMMARY Ebasco prepared this report to identify existing data and various assumptions concerning the composition and availability of North Slope gas and potential constraints to its use for meeting future energy needs in the,Railbelt.The report plays an essenti~l role in the ongoing feasibility level assessment by establishing a common data base from which to proceed.The report discusses the physical composition of North Slope gas,the quantity and availability of the gas,and various engineering and economic factors.An extended bibliography and a list of persons contacted to compile the data and assumptions are appended. ., Mv [~ C', ..~.._., [ [- [--- L, C' nL,. l_ b' e C G C !._~ [ [ I C b A1 .0 INTRODUCTION This report is the first of a series in developing a feasibility level assessment regarding the use of North Slope natural gas for power generation in the Rai1be1t and for residential/commercial heating uses in Fairbanks.Use of North Slope natural gas to meet these needs has not been fully assessed by previous studies because it has been presumed that all North Slope gas would be dedicated to the Alaska Natural Gas Transportation System (ANGTS).Alternative evaluations for ANGTS were based on transportation and utilization of the gas outside of the Rai1be1t market area.It now appears that ANGTS will be substantially de1~ed and that the gas may be available for Railbelt utilization. The overall study of which this report is a part is charged with developing the conceptual design with subsequent cost estimates and environmental impact assessments of three energy development scenarios for two energy demand forecasts:the medium demand forecast presented in the final draft Susitna'Hydroelectric Project Feasibility Report 1 and the 10\'/demand forecast presented in Battell e Pac;fi c Northwest Laboratories'Evaluation of Rai1belt Electric Energy Plans -Cement Draft.23 The scenarios included: 1)Electrical generation at the North Slope with attendant electrical transmission to Fairbanks and on to Anchorage; 2)Electrical generation at the tenninus of a high pressure natural gas pipeline to tidewater fueled by the "waste"gas byproduct of a gas conditioning facility,with necessary electrical transmission to Anchorage and Fairbanks;and, 3)Transportation of North Slope gas via a small diameter pipeline to Fairbanks,with electrical generation at Fairbanks,electrical transmission to Anchorage,and gas distribution for residential/comercia1 use at Fairbanks. 2965A A1-l All three scenarios require an analysis of the energy demand forecasts to determine optimum facility staging and capacity requirements,and an analysis of facility and corridor siting constraints and/or opportunities.These latter two topics are the subj~ct of other project reports. Ebasco has prepared this report to identify existing data and various study assumptions which concern the composition and availability of North Slope gas and potential constraints to its use.In addition,several engineering and economic assumptions fundamental to the other aspects of the study are presented.The report is based on a revie\'1 of the literature as well as numerous discussions with knowledgeable agency and industry representatives. This report.plays an essential role in the feasibility level assessment by establishing study assumptions so that all disciplines formulating the technical details of the three scenarios will have a co~on data base frolll which to proceed.A comon data base will also facilitate comparisons among the scenarios. The structure of this report begins with a short background chapter (Chapter A2.D),which serves to establish an historical perspective to the various studies that are re"ferenced.Following this background,is a· discussion of the physical composition and characteristics of North Slope gas (Chapter A3.D).Gas supply and availability (Chapter A4.D)are reviewed and summarized.Engineering (Chapter AS.D)and economic (~hapter A6.D)assumptions are provided to establish an early,common data base for the scenarios.Chapter A7.D is reserved for issues of concern to utilization of North Slope natural gas to meet the future energy needs of the Railbelt.Following these chapters is an addendum of literature on North Slope natural gas and Railbelt energy needs,and an addendum listing Ebasco's contacts with agency and industrial personnel. 2965A Al-2 [ [ C p f' [' r n....."~ [j [ [ [ E L [ L L L L [ r' [ [' e [0. r', e.' rL..-. [ C C [ C C. [, [ , t. L) L \..... A2.0 BACKGROUND The natural gas reserves on the North Slope have been the subject of numerous studies and reports since their discovery.Since development on the North Slope began,various proposals to build a pipeline to carry the gas to markets in the lower 48 states have.been formulated.As a result of the proposals,an ~tensive literature of economic,technical,and environmental studies that evaluate the alternatives to each proposal has been accumulating.Many of these studies have been reviewed to assemble the data contained in this report and are listed in the Addendum.* Ebasco presents a background to the literature survey by summarizing some of the most useful studies in chronological order in this chapter. liThe Final Environmental Impact Statement for the Alaska Natural Gas Transportation Systems"is representative of studies in support of the initial attempts to develop North Slope natural gas.29 This statement by the Federal Power Commission,which analyzes two separate proposals and numerous alternatives for pipeline systems,was issued in April 1976 and is of principal interest for historical purposes.The document established a preferred pipeline route from Prudhoe Bay to Fairbanks and then through Canada to the lower 48 states. A second study 9f interest is "Ana1ysi s of Prudhoe Bay Royal ty Natural Gas Demand and t~e Proposed Prudhoe Bay Royalty Natural Gas Sa1e,"dated .January 1977.34 While the analysis is out of date and should be used for informational purposes only,the report covers many of the issues which are relevant to the present stUdy.In particular,it discusses the royalty share (12.5 percent)of the produced gas,the expected gas production rate,and natural gas demand and demand growth. *Reference numbers refer to the bibliography in the Addendum of this Appendix.The bibliography also contains documents not referenced in this report. 2966A A2-1 Studies by electric power planning agencies during the early years of development of the Prudhoe Bay field is typified by the report,IINorth Slope Natural Gas Transport-Systems and their Potential Impact on Electric Power Supplies and Uses in A1aska ll • 36 This report by R.W. Retherford Associates for the Alaska PO\ier Administration updated various analyses presented in the previously cited Federal Power Commission EIS concerning the impacts of a natural gas pipeline on Alaskan electric power generation.This study is also out of date but of interest because of its negative conclusions on the economics of using natural gas for electrical generation.The studY concludes that electricity from other sources should be used to power the gas pipeline. In March of 1977,the A1 aska Department of Commerce and Economi c Development issued a report written by the staff of Battelle Pacific Northwest Laboratories enti t1 ed,"A1 askan North Slope Royal ty Natural Gas -An Ana1ysi s of Needs and Opportunities for In-State Use ll • 22 This report concludes that North Slope natural gas had no potential for electrical generation since other less expensive fuels were available. Like many of the studies prior to 1980,it assumed the timely completion of a major gas pipeline carrying all of the available gas to markets outside of Alaska. In November 1977,Presi dent Carter desi gnated the A1 aska Hi ghway Pipeline Project (A1can)for construction based on the provisions of the Alaska Gas Transportation Act of 1976.The A1can proposal is the project which is now referred to as the Alaska Natural Gas Transportation System (ANGTS).Typical of the several informative reports commissioned by the Alaska legislature concerning the ANGTS project is the report by K.Brown and C.Barlow,IIAn Overvi e\/of Natural Gas and Pipeline Issues,1I dated June 1978.24 The document provides insight to the issues regarding development of North Slope gas.While this study is a critique of the A1can project,it raises issues on possible licensing and development constraints and the effects of well head pri ce on the economi c vi abil i ty of the project. 2966A A2-2 [ [ [ L L [ [ L L L r [ l~J c [ C E C C ( r~...L,- ~-, L 1.- L In September 1978.the Ral ph M.Parsons Company produced a report entitled.IlSa·les Gas Conditioning Facilities.Prudhoe Bay. A1 aska 11.35 The i mportan~e of th;s document ;sin its spec;fi cati on of the composition of North Slope gas and the conditioning needed to produce a pipeline quality gas for ANGTS.The stuqy presumes a major pipeline but many of the specifications are applicable to the present feasibility level assessment. The State of A1 aska Department of Natural Resources issued a report by C.Barlow of Ar10n R.Tussing &Associates in March 1980 which presents a highly informative technical discussion of the characteristics of North Slope gas.written for the 1ayman.21 Titled IlNatural Gas Conditioning and Pipeline Design.1I the report is particularly useful in explaining the effects of carbon dioxide and penmafro~t on pipeline design for the delive~of North Slope gas. Among the later documents which are important to the present study context is."A1aska-Historical Oil and Gas Consumption:'a report written by Battelle and issued by the State of Alaska Department of Natural Resources in January 1982 as a statutory requirement to the Alaska legislature.37 The report provides a basis for projecting the amount of gas required for the analyses in this feasibility level study. A study representativ~of the current economic issues which arise concerning North Slope gas utilization is a report by Kidder.Peabody. and COr.1pany.IlReport to the Governor's Task Force on State of A1 aska Participation in Financing the Alaskan Segment of the Alaska Natural Gas Transportation System ll • 31 This report is dated March 1982 and explores alternatives the state could use to help finance the Alaska Natural Gas Transportation System segment in Alaska.Likewise.a recent report ti t1 edt IIA1 aska Natural Gas Development:An Economic Assessment of Marine Systems.1I is representative of alternatives to ANGTS for moving North ·Slope natural gas to markets outside"A1aska.30 2966A A2-3 Several studies to utilize North Slope gas are currently being conducted in addition to this feasibility level assessment.Booz, Allen &Hamilton,Inc.is performing a study for the Alaska Department of Natural Resources to screen a wide range of transport and use options (including ANGTS),and to analyze economic and environmental aspects resulting in a general ranking of promising options.Brown and Root,Inc.is performing a study for the Governor's Economic Committee on Alaska Natural Gas which focuses on a gas pipeline to a tidewater conditioning plant in the Kenai/Nikiski area.The study is also investigating various marketing options for the gas.Use of the waste gas strea~from this conditioning plant is the basis of the Kenai generation scenario in Ebasco's assessment. The U.S.General Accounting Office recently contracted for another study with Parsons,Brinkerhoff,Quade and Douglas,Inc.to generate a financial report on engineering costs associated with transporting Alaska natural gas to markets in the lower 48 states. 2966A A2-4 .~\ f~ [" [ r~ [ [- r [ [ L [ L [ l f~ [ [ 1 L L [ [- [~ [ [ r'""-," C" fJ" \....r j [ L, c" [J C C ~. C i L [ I L 1- [ \ AJ.O GAS COMPOSITION A detennination of the physical composition of North Slope natural gas is essential to evaluate the economics of its utilization under alternative scenarios.The trade-offs among gas conditioning,gas transportation, and gas utilization alternatives depend on the types and quantities of chemical compounds.present in the natural gas.In particular,North Slope natural gas is characterized as II swee t and wet ll (generally desirable factors),but is relatively high in carbon dioxide (undesirable factor).21 Several studies and sources of data on chemical composition of North Slope natural gas are available.21 ,35 The data are in substantial agreement to support a preliminary feasibility level analysis.Variation among the data sources may be attributable to the fact that North Slope natural gas can be obtained from the top of the Sadlerochit fonmation (the gas cap)or from the lower lying oil as a dissolved gaseous constituent. Ebasco,based on consultation with industry and government personnel, will use the natural gas composition shown in Table AJ-l as the common data base for each scenario.The Ralph M.Parsons Company assembled these data in September 1978 to support a study for sales gas conditioni"ng facilities at Prudhoe Bay.35 The Parson~·study,in support of a major all-Alaska pipeline proposal,embodies several gas composition assumptions appropriate for the three Railbelt scenarios considered in Ebasco·s study. The singl e most si gni fi cant factor in the composi ti on of North Slope natural gas which influences the economics of its utilization is the relatively high carbon dioxide content.Table A3-1 shows that over 12 percent (by volume)of the gas is carbon dioxide,a combustion product gas which is a generally undesirable constituent,Carbon dioxi~e removal" 2967A A3-1 0.00.08 TABLE A3-1 6.47 0.47 74.17 12.63 Vol ume Percent NORTH SLOPE NATURAL GAS COMPOSITION Ethane Constituent Methane ----------------------------- Propane Butanes Pentanes-pl IjS Raw Gas Heati n9 Val ue 2967A A3-2 3.48 1.66 1.22 100.00 1046 Btu/ft3 [ [ [ e -L -C i L _L l r: [[ [- b [ [ [ [,. r'L3 [ !. ~ B C, C [ ,- I [ [ L" Y B 'I.. is required to produce a high quality pipeline gas.The gas represents an added transportation cost if conditioning facilities are not on the North Slope.Carbon dioxide may also promote pipeline corrosion through the fonmation of carbonic acid and must be removed if natural gas is to be stored as liquid natural gas (LNG).(Carbon dioxide does allow a pipeline to carry greater quantities of heavy hydrocarbons,but the net benefit is rather small.) The sulfur content of North Slope natural gas is low and treatment is not required prior to pipeline transmission.35 Sulfur is an undesirable constituent of natural gas which can increase treatment costs considerably,contribute to air pollution,and promote pipeline corrosion.The low sulfur content is denoted by the gas being termed Iisweetll. The rel atively hi gh proporti on of natural gas 1i qui ds (NGL)'compared to methane is a desirable characteristic if natural gas is used as a petrochemica~feed stock.21 ,24 Natural gas liquids are present in North Slope gas because it is derived from an oil reservoir.The heavier hydrocarbons (ethane,propane,and butane)which make up the natural gas liquids are not desirable for domestic utility use where IIdry gas ll is favored.The Ilwetll gas can be conditioned to remove the heavier hydrocarbons. The composition of the waste gas stream associated with the Kenai electrical generation scenario arises from the assumption that gas conditioning will be employed at the tidewater terminus rather than on the North Slope.In the ,absence of a specific gas conditioning process design,Ebasco derived a theoretical maximum gas composition based on a stipulated waste gas heating value of 300 Btu/SCF.This analysis shows that an unrealistic quantity of raw gas hydrocarbons is necessary to achieve this heating value.Based on a brief analysis of available gas conditioning processes,the waste gas stream could have an approximate heating value of 175 to 195 Btu/SCF.An exact composition of the waste gas stream cannot be specified at this time,but it will be high in heavier'hydrocarbons and carbon dioxide. 2967A A3-3 l~-­ ,~~ l ..> [ [~- -c [' f.'·- l_> [ [ [ , C C C [ L [ [ 1. L I [ A4.0 GAS SUPPLY AND AVAILABILITY Gas supply refers to the physical quantity of natural gas present in the Prudhoe Bay field.Gas availability refers to phYsical and institutional constraints on gas production.Most estimates of the total volume of gas are in.the range of 30 to 40 trillion cubic feet (TCF)for the known reserves in the Sadlerochit formation,of which some 25 to 30 trillion cubic feet are recoverable.21 ,22,28,34 To place these quantities in perspective,the North Slope contains 10 percent of the known U.S. natural gas reserves and could supply 5 percent of the present demand in the lower 48 states for 30 years. For purposes of this study,Ebasco will use a quantity of 26 TCF as an estimate of the recoverable reserves of North Slope gas.This is consistent with the 1977 Battelle report on North Slope royalty gas.22 This quantity refers only to the Sadlerochit formation gas,for which the State of Alaska royalty share is 12.5 percent of production. Production of Prudhoe Bay natural gas will be at a rate to maximize recovery of oil in the formation.At present,some 2 billion cubic feet (BCF)of gas are brought to the surface with the oil each day.All but a few percent are injected back into the gas cap in order to maintain reservoir pressures and maximize oil recovery.The State of Alaska Oil and Gas Conservation Committee establishes the operating methods through pool rules,an administrative rule making procedure.Conservation Order No.145 (June 1,1977)provides for annual average offtake rates of 1.5 mill i on barrel s per day for oil and 2.7 BCF per day for gas.The pool rule production rate is consistent with other pUblished production capabilities for the Prudhoe Bay field and therefore will be used by Ebasco.A production rate of 2.7 BCF per day is assumed to yield 2.0 BCF per day of conditioned gas.21 IIproducti on ll is·a term whi ch must be carefully defi ned in context once a significant quantity of Prudhoe Bay gas can be utilized.According to the Prudhoe Bay Lease Agreements,the State of Alaska royalty share (12.5 2968A A4-1 percent)appl ies to gas that is II pro duced,saved,sold or used off said land ll ,and does not include gas utilized to operate the oil field and gas injected to maintain reservoir pressure.The only gas now being produced is the 60 million cubic feet per day sold to Alyeska to.operate four of the Trans-Alaska Pipeline System (TAPS)pump stations.If North Slope gas is to be utilized solely for the scenarios considered in this stUdy, the project proponent would have to enter into discussions with the producers to negotiate for the sale of the gas. Of the approximately 2.0 BCF per day of conditioned gas available for use,the Railbelt low and medium future electricity needs could only absorb on the average 0.11 BCF per day and 0.19 BCF per d~, respectively.The Alaskan royalty share alone (12.5 percent)would .generally be sufficient to meet both growth forecasts. The waste gas stream associated with the Kenai electrical generating scenario is incapable of meeting the needs of even the low forecast.The amount of available gas is approximately 430 x 106 SCF/day,with a heating value of 175 to 195 Btu/SCF.This is only about 50 percent of the required en~rgy to meet the electrical needs in the low growth case. The waste gas stream must,therefore,be supplemented with appropriate quantities of sales gas to meet energy needs. 2968A A4-2 [ L [ C C f.--'~6 [ [ [, [ L L [ C· o, E C [ L [ [ 1- L :- L A5.0 ENGINEERING ASSUMPTIONS Several engineering assumptions have been made to facilitate development of the electrical generation scenarios.These include using the medium load and energy demand forecasts presented in the final draft Susitna ~droe1ectric Project Feasibility Report (Table 5.7)1 and the low load and energy demand forecasts presented in Battelle Pacific Northwest Laboratories'Evaluation of Rai1be1t Electric Energy Plans -Comment Draft (Executive Summary,Pageiv).23 It should be noted that the latter forecasts are lower than the low range forecasts given in the Susitna Feasibility Report.These particular forecasts are being used at the request of the Alaska Power Authority to ensure comparability with previous Rai1be1t electric energy analyses.It is also expected that these fnrecasts will br?cket a revised medium range forecast which is currently being prepared by Battelle Pacific Northwest Laboratories using their existing RED model and based on revised economic forecasts currently being prepared by the University of Alaska Institute of Social and Economic Research. Preliminary estimates of the amount of gas to meet power generation needs are being based on the use of a conversion (heat)rate of approximately 10,000 Btu/kWh and a sales gas heating value of approximately 1,000 Btu/SCF.These values,when applied to the low electrical demand forecast result in an annual average usage in the year 2010 of 39.4 BCF. Similarly,the medium electrical demand forecast results in an annual usage in the year 2010 of 67.9 BCF for electrical generation.These annual average values as well as required peaking values and preliminary Fairbanks residentia1/commercial usage estimates are presented in Table A5-l.The assumptions utilized to generate Fairbanks gas demand are presented in Chapter A6.0 The preliminary gas demand estimates presented in Tab1 e A5-1 are presently being utilized for North Slope to Fai rbanks small diameter gas pipeline design and the Fairbanks gas distribution system design.When final estimates of gas demand are generated appropriate refinements in gas pipeline and distribution system design will be made. 2969A AS-1 --------_... TABLE A5-1 PRELIMINARY GAS REQUIREMENTS FOR POWER GENERATION AND FAIRBANKS RESIDENTIAL/COMMERCIAL USE IN THE YEAR 2010 USE POWER GENERATION Maximum Requirements* (SCFM x 105) Average Requirements** (SCFM x 10 5 ) Average Annual Requirements (BCFY) LOW LOAD FORECAST 1.2 0.75 39.4 MEDIUM LOAD FORECAST 2.1 -1.3 67.9 [' U *Natural gas firing rate at peak demand based upon the following required new gas fired generating capacity in the year 2010:741 MW for low load forecast and 1278 MW for medium load forecast. **Natural gas firing rate associated with total annual energy require- ments:required new gas.fired energy requirements in the year 2010 are 3937 GWh for.low load forecast and 6788 GWh for medium load forecast. A5-2 2969A [ , 'G C E 1: [ L ·l-'. .- L [ 78.0 10.1 . Refer to Chapter A6.0 for 5.3 44.7 Values represent "Extreme of Reasonable". di scussi on.*** RESIDENTIAL/COMMERCIAL USE*** TOTAL AVERAGE ANNUAL REQUIREMENTS (BCFY) Average Annual Requirements (BCFY) [~ e- LI f'- ~-..-. [: [" [-- r"Lori. c..0 -,"" I L i C C· ~ [ Il.. r l..-d [ L L i ._.~ [. All three scenarios involve power plant facilities.The diversity of the Alaskan environment requires each location to have different facility design conditions.A North Slope facility must be built on steel piles using modular construction in the manner of the existing Prudhoe Bay facilities.Zone 1 earthquake design criteria will apply.For both Fairbanks and Kenai,conventional construction methods for Zone.3 earthquakes are applicable,although Fairbanks also requires consideration of greater temperature extremes.Air cooled condensers will be used for steam cycles in order to avoid large cooling water flows and problems associated with cooling water such as availability limitations and intake icing.In many places in Alaska,evaporative cooling water can also be a significant source of ice fog. Engineering assumptions applicable to construction of a natural gas pipeline to serve Fairbanks begin with the original ANGTS route using a minimum separation of 200 feet with TAPS.This distance is commensurate with that specified in the U.S.Department of the Interior grant of right-of-way for ANGTS.43 Ebasco assumes the use of buried line which requires the gas to be kept cooled to maintain the permafrost.An initial line pressure of 1260 psig will be used in sizing the pipeline. Because of the high carbon dioxide content of North Slope gas,the Fairbanks scenario will include gas treatment for CO 2 removal at Prudhoe Bay.The numb~r of compressor stations has not been determined.. yet,but will be established using standard computer programs. Associated with the small diameter line to Fairbanks is a domestic gas distripution system.Minimum inlet pressure will be 350 psig at gas regulators,125 psig in the high pressure system to district regUlators, and 60 psig in the distribution system to customers.Distribution lines will be laid in public rights-of~ay at a depth of 3 feet using standard 2 inch 1 ines. 2969A A5-3 For the purpose of slzlng the transmission lines from Prudhoe Bay to Fairbanks and from Kenai to Anchorage,preliminary estimates of required new generating capacity were made.These estimates,which accounted for plant retirements,planned additions and energy demand forecasts, resulted in required capacities for the year 2010 of approximately 700 MW for the low demand forecast and 1400 MW for the medium demand forecast •. ReQui red additions to and upgradi ng of the Anchorage-Fai rbanks Interti e were designed to distribute capacity and ensure stability,and not to optimize the entire Railbelt transmission system.Therefore,it was assumed that 80 percent of the power that either arrives at Fairbanks from Prudhoe Bay or is generated in the Fairbanks area,depending upon the development scenario,is transmitted to Anchorage.Similarly,for the Kenai scenario it was assumed that 20 percent of the power arriving in Anchorage is transmitted to Fairbanks.The 4 to 1 split assumed is based on the ratio of total utility sales in the Railbelt during 1980.11 For the Prudhoe Bay generation scenario,the transmission line from the "- North Slope to Fairbanks carries 100 percent of the generating capacity through adverse environmental conditions.The contamination,due to salt,dust,and moisture is severe from Prudhoe Bay to approximately 60 miles inland,requiring washing of insulators at the switchyard and on that portion of the line to prevent flashover.Several combinations of wind,temperature,and ice loading will he evaluated to determine conductor design.Table AS-2 summarizes conductor loading conditions for the Prudhoe Bay-Fairbanks transmission line.The stream crossing design for the Yukon River requires special investigation.A DC alternative will also be analyzed.With one AC line segment or one of the DC poles out of service,the Prudhoe Bay-Fairbanks-Anchorage system will remain stable in the steady-state at normal peak continuous loading. The Fairbanks-Anchorage lines (330 miles)carry 80 percent of the capacity for the Prudhoe Bay and Fairbanks generation scenarios,but only 20 percent for the Kenai scenario.The Fairbanks-Anchorage Intertie which is presently under construction (170 miles at 345 kV AC)will be 2969A AS-4 [ '''1. r~ .; f' r~ ! [ [' [ j" L---, [ L [ f" ~ [ F~b C [ L L L L CONDUCTOR LOADINGS FOR KENAI -ANCHORAGE TRANSMISSION LINE CONDUCTOR LOADINGS FOR FAIRBANKS -ANCHORAGE TRANSMISSION LINES TABLE AS-2 TRANSMISSION LINE CONDUCTOR LOADINGS CONDUCTOR LOADINGS FOR PRUDHOE BAY -FAIRBANKS TRANSMISSION LINE* Ice Thickness Wind Pressure (radial inches)'(lb/sq ft) 100 60 30 100 60 30 100 60 30 Corresponding Wi nd Speed (miles per hour) Corresponding Wind Speed (mil es per hour) Corresponding Wind Speed (mil es per hour) 25 8 2.3 25 8 2.3 25 8 2.3 Wind Pressure (l b/sq ft) Wi nd Pressure (l b/sq ft) none 0.75 none none 1.5 none none 0.75 none Ice Thi ckness (radial inches) Ice Thi ckness (radial inches) -60 32 86 -40 32 90 -60 32 86 Temperature (OF) Tempe ra ture (OF) Temperature (oF) r: L c L c [ f:'rl [ [ [~ [ [ [' f' p ~~] [ ~. [ C L .. U l [ *All conductor loadings derived from published literature,evaluations of environmental conditions,discussions with utility operations personnel,and engineering jUdgement. 2969A A5-5 fully extended (to 330 miles)in each scenario,and additional lines will be considered,as required,to carry the projected loads.Only AC operation will be considered.Conductor loading conditions for these scenarios are also given in Table A5-2. The Kenai generation scenario assumes construction of a Kenai-Anchorage Intertie which would carry 100 percent of the load for about 150 miles. Environmental conditions are moderate for this line including mild contamination.Table A5-2 summarizes expected conductor loadings. Design parameters for the AC switchyard at the generating station and intermediate switching stations will assume breaker and a half bus arrangement. 2969A A5-6 n l..-i c U [ L [' -, [ b" c~ L [ [ L [ [ [- [Y- [~ [- f" [- F'.... [ t'u C..._- C-·. C C [ [ l [ , [ ~-". A6.0 ECONOMIC ASSUMPTIONS FOR FAIRBANKS NATURAL GAS DBMAND Preliminary residential and commercial gas demand has been estimated for Fairbanks so that the North Slope natural gas pipeline and the Fairbanks natural gas distribution system conceptual design could proceed. Numerous assumptions were made in order to develop the preliminary forecast of natural gas demand. Based upon an inventory of current fuel prices in Fairbanks (Table A6-1) and a subsequent economic evaluation,the primary assumption is that natural gas will be used exclusively for space and water heating;and that it will compete directly with #2 distillate oil which is currently used in most residential and commercial installations.It is assumed that natural gas will not compete with coal,wood,or electricity for either price or application reasons • Given the age of the bui 1di ng stock in Fai rbanks,it is assumed that oil fired equipment operates ~t a thenmal efficiency of 6~,and that gas-fired units will have a thema1 efficiency of 74%.The cost of conversion from oil to natural gas is assumed to be $600/unit,based upon contacts with local oil dealers.There are about 23,000 residences in Fairbanks to be heated.Average #2 distillate consumption is 1,500 ga1/yr,at a higher heating value of 138,100 Btu/gal.Natural gas for distributio~is assumed to have a higher heating value of 1,000 Btu/ft3• The commercial demand for natural gas is based upon an assumed consumption rate of 160,000 Btu/ft2• A cOlIlJlercia1 building inventory of 3.22 million ft2 of space exists in Fairbanks. Given these assumptions,preliminary demand forecasts have been made. They will be used,subsequently,in engineering analyses. 2970A A6-1 TABLE A6-l INVENTORY OF FUEL PRICES IN FAIRBANKS A6-2 2970A *Gplden Valley Electric Association. **Fairbanks '-1unicipalUtilities System. Fuel/Energy Type #2 distillate Residential Coal (Healy) Wood (split and del ivered) Residential electricity (GVEA)* Residential electricity (FMUS)** Commercial electricity (GVEA) Commercial electricity 1981 Fuel Price In Fairbanks $1.23/gal $61/ton $lOO/cord $0.1051 /kWh $0.0906/kWh $0.0922/kWh $0.0770/kWh Equivalent 1981 Price - Efficiency Adjusted (Simi 11 ion Bt u) $14.84 $5.36 $9.83 $30.70 $26.55 $27.01 $22.56 f [' f-: [" [ [J [j L [ [ [ [ L The extreme of reasonable value,used for sUbsequent engineering design studies (capacity planning)is based upon replacing 63.3%of the #2 distillate demand in the year 2010.In this case the projections are as foll ows: The preliminary forecasts assume growth rates of 2%and 4.3%,per year, in heating system demand.1 ,23 At a 2%/yr growth rate,the maximum demand in the year 2010 will be 8.4 BCF,or 8.4 trillion Btu.At a 4.3%/yr growth rate,the upper 1imi t of demand in 201 0 ; s 15.9 BCF of natural gas,or 15.9 trillion Btu. [ [ [ [ [ [ nu r; L Growth Scenario Low (2%/yr) Medium (4.3%/yr) Natural Gas Demand (BCF) 5.3 10.1 Natural Gas Demand (tri1li on Btu) 5.3 10.1 E C D.- [ 6 [ i [ '-.- [ l _ 6 ( [ These projections are based upon an initial break-even price between natural gas and oil of $10.14/thousand cubic feet (MCF)for residential applications,and $10.54/MCF for commercial applications (1981 prices). After an assumed competitive response to natural gas by the ~orth Pole Refinery,these break-even prices may drop to $9.07/MCF for residential users and $9.43/MCF for commercial users (also 1981 prices). These preliminary demand estimates will be expanded upon,and refined, for the final report.Such refinement will be based upon additional data now being developed. 2970A A6-3 --.r [' [. [ [~ ['. L f'L· L L [ 6 C [ L [ C· [ c. L l-·. [ A7.0 OTHER CONSIDERATIONS ·A7.1 POWERPLANT AND INDUSTRIAL FUEL USE ACT A new gas or oil fired electric generating facility using North Slope natural gas will be subjectto the provisions of the Power Plant and Industri al Fuel Use Act of 1978 (FUA).Pursuant to section 201 of the FUA,oil and/or natural gas may not be used as a primary energy source in a new electric power plant unless special permission is obtained. Special permission is granted by the Economic Regulatory Administration (ERA)within the Department of Energy (DOE)in the form of an exemption from the FUA prohibition of the use of natural gas.A statutory exemption for Alaskan utilities was recently (December 30,1982)signed into law by President Reagan as part of the fiscal 1983 Department of the Interior Appropriations Bill (H.B.7356).The exemption,however,does not apply to any new electric power plant which would use natural gas produced from the Prudhoe Bay unit. Prior to this exemption,a ver,y thorough analysis of the Act and potential exemptions applicable to Alaskan utilities were provided as an appendix to a report submitted to the Legislative Affairs Agency of the Alaska State Legislature by G.Erickson.28 The analysis concluded that: It appears there do exist grounds under which any of the utilities along the Rai1belt might qualify for a permanent exemption from the requirement of the Act to use coal or other alternate fuel.Such grounds might include (a)lack of alternate fuel supply for the first 10 years of the useful 1ife of the facility;(b)lack of alternate fuel at a cost which does .not sUbstantially exceed the cost of imported oil;(c)site limitations (this seems less likely);(d)inability to comply with applicable environmental requirements,and (e)inability to use alternative fuel because of a State or local requirement. It should he cautioned that this analysis has no legal implications and that a final decision regarding an exemption will not be known until an application is submitted to the ERA.For the purposes of this study, however,the FUA is not considered prohi biti ve of development of new electric power plants using Prudhoe Bay unit natural gas. 2973A A7-1 A7.2 COST OF NATURAL GAS Cost of North Slope gas at the point of use is fundamental to scenario planning and the ultimate determinant of project viability.The constraints,technical and institutional,to determining a reliable cost have prevented,in large part,the implementation"of all previou·s proposal s to use North Slope gas,and no definitive cost can be presented here.However,upper limits to the wellhead cost of North Slope gas can be established through comparison to alternative fuel costs by subtracting engineering estimates of gas upgrading and transmission (;-nc1uding distribution)system costs.Essentially all costs incurred between the well and the consumer must be so accounted for.Thus,by "backing out"the wellhead cost as a remainder,it can be determined whether gas can compete with alternative fuels. It has been determined,by Alaska Economics,Inc.,that natural gas will compete almost exclusively with #2 distillate oil.The reasons,and price comparisons,are discussed in Chapter A6.0 of this report. Presently,#2 oil costs $14.84 per million Btu (efficiency adjusted)in Fairbanks.In the simplest case,any combination of gas wellhead cost plus upgrading and transportation cost (including distribution cost)plus system conversion costs that is significantly less than $14.84 per million·Btu (net heat delivered to the house)means gas can compete with oil in Fairbanks.Ebasco·s approach will be to detennin~all conditioning,transportation and system costs to allow the wellhead cost of North Slope gas to be derived.The desired result of this calculation is to obtain a value which indicates that for any given the cost,North Slope gas will be either competitive or non-competitive (in price)with alternative fuels.The only basis for estimating the cost of North Slope gas at this time is the cost for gas used to operate the Trans-Alaska Pipeline System stations.The delivered cost varies somewhat in time, but is about $1.86 per million Btu. Facility costs and derived wellhead values will also provide information essential in the development of any comparative power costs between alternative generation technologies.Such comparisons are outside Ebasco·s scope of work,but can be considered as a logical extension which may be performed by the Alaska Power Authority. 2973A A7-2 [ L [, r~ b .L L [ L [ c [ I . C L ~t r't~ [ ..-:.. L L._ U .......- L ADDENDUM A BI Bl IOGRAP HY cc cy - r~ ~­ f-- r~:~, [-- p- Lr CL (.•./-- C C f."'.U L [ [ [ L _ [ l BIBLIOGRAPHIC MATERIALS FOR APA NORTH SLOPE NATURAL.GAS FEASIBILITY STUDY 1.Acres American,Inc.,1982."Susitna Hydroelectric Project - Feasibility Report -Volume I,Engineering and Economic Aspects, Sections 1-8,Final Draft ll •Alaska Power Authority.Anchorage, Alaska. 2.Acres American,Inc.,1982."Susitna Hydroelectric Project- Feasibility Report -Volume I,Engineering and EConomic Aspects, Sections 9-19,Final Draft ll •Alaska Power Authority.Anchorage, Alaska. 3.State of Alaska,Dept.of Environmental Conservation,1982. 1 set containing: 1.Waste discharge permit application form 2.Copies of current waste discharge permits for a.domestic wastewater to lands or waters of the state b.wastewater from a desalination plant c.discharge of drill muds and cuttings onto sea ice d.oily waste injection facilities 4.State of Alaska,Dept.of Transportation and PUblic Facilities Planning and Programming Map,PUblications by the Southeast Region Mapping and Graphics Section. 5.State of Alaska,Division of Economic Enterprise,January 1978, IIFairbanks,An Alaskan Community Profile"Fairbanks Chamber of Commerce,City of Fairbanks,State of Alaska Division of Economic Enterprise. 6.State of A1 aska,Di vi sion of Ec onomic Enterprise,March 1978,IINorth Pole,An Alaskan Community Profile"City of North Pole,State of A1 ask a Di vi si on of EC onomi c Enterpri se. 2972A 1 7.State of Alaska,Division of Economic Enterprise,November 1979, II Ba rro\'1,An Alaskan COl!lJlunity Profi1e ll North Slope Borough,State of Alaska Division of Economic Enterprise. 8.A1 aska Interi or Resources Co.,Inc.,October 1981 I~Methano1 /Energy Complex,Fairbanks,Alaska -Executive Summary and Preliminary Financing Plan ll Foster and Marshall,Inc.,Seattle,Washington. 9.Alaska Interior Resources Co.,Inc.,1981,IIMethano1 -Report to the State of Alaska ~Feasibility of a Petrochemical Industry,Vol.4 of 1011 The Dow-Shell Group,Anchorage,Alaska. 10.A1 aska In teri or Resources Co.,Inc.,1981,II Energy Study -Report to the State of Alaska -Feasibility of·a Petrochemical Industry,Vol. 80f 1011 The [Jo",-Shell Group,Anchorage,Alaska. 11.Alaska Oil and Gas Conservation Commission,1982,111981 Statistical Report ll State of A1Slska,Alaska Oil and Gas Conservation Commission, Anchorage,Al aska. 12.Alaska Oil and Gas Association,1~82,IIAlaska Oil and Gas Industry Facts ll Alaska Oil and Gas Association,Anchorage,Alaska. 13.U.S.Dept.of Energy,Alaska Power Administration,February,1.982. IIUpdate of 1972 North Slope Transmission Study II ,U.S.Dept.of Energy,Alaska Power Administration. 14.Al askan Northwest Natural Gas Transportation Company,II Al aska Natural Gas Transportation System,Al aska Segment -48 11 Natural Gas Pipeline (Prudhoe Bay to Canadian Border). 15.Alyeska Pipeline Service Co.,no date,liThe Trans Alaska Pipeline ll Alyeska Pipeline Service Co.,Anchorage,Alaska. 2972A 2 , cI r c ( I l. t L [ L L C,."' L 1j L L L, C [ 16.Alyeska Pipeline Service Co.,no date,IIPump Station Oneil Alyeska Pi peli ne Service Co.,Anchorage,Al aska. 17.Alyeska Pipeline Service Co.,no date,"Operating the Trans Alaska Pipeline ll Alyeska Pipeline Service Co.,Anchorage Alaska. 18.Alyeska Pipeline Service Co.,1980,"Trans Alaska Pipeline Atlas - Prudhoe Bay to Valdez ll Alyeska Pipeline Service Co. 19.ARCO Alaska Inc.,1981,"ARCO in Alaska"ARCO Alaska Inc. 20.ARCO Alaska Inc.,1982,IIWelcome to the North Slope"ARCO Alaska Inc. 21.Connie C.Barlow,March 1980,IlNatural Gas Conditioning and Pipeline .Design"Arlon R.Tussing and Associates,Inc.for State of Alaska, Dept.of Na tura 1 Resou rce's. 22.Battelle Pacific Northwest Laboratories,March 1977."Alaskan North Slope Royalty Natural Gas -An Analysis of Needs and Opportunities for In-State Use -Prel imi nary Draftll •For Al aska Dept.of Commerce and Economic Development,Division of Energy and Power Development. 23.Battelle Pacific Northwest Laboratories,February 1982.IIRailbelt Electric Power Alternatives Study:Evaluation of Railbe1t Electric Energy Pl ans -Conment Draft".For Office of the Governor,State of Alaska Division of Policy Development and Planning. '24.K.Brown and C.Barlow,June 1978,"An Overview of Natural Gas and Gasline Issues"Legislative Affairs Agency. 25.COlilJ1onwealth Associates,Inc.,March 1982.IIEnvironmenta1 Assessment Report -Anchorage-Fairbanks Transmission Intertie ll • Alaska Power Authority,Anchorage,Alaska. 2972A 3 r 26.Ebasco Services Incorporated,April 1981.IlRailbelt Electric Power (' Alternatives StuQy -Technology Assessment Profile Report -An l Overvi ew ll •For Battelle Paci fi c No rthwes t Labs. 27.Electric Power Research Institute,October 1978.IlCosts and Benefits of Ove.r/Under Capacity in Electric Po\~e·r System Planning" prepared by Decision Focus,Inc.Palo Alto,.CA for EPRI,EPRI EA-927. 28.Gregg K.Erickson,March 1981.II Natural Gas and Electric Power: Alternatives for the Railbeltll prepared for the Legislative Affairs Agency,Alaska State Legislature. 29.Federal Power Commission Staff,April 1976.IIA1aska Natural Gas. Transportation Systems,Final Environmental Impact Statement,Volume I,General Economic Analysis Comparison of Systems ll for E1 Paso Alaska Company Dockett No.CP 75-96 et a1.Federal Power Commission. 30.ICF Incorporated,Ed.,S~ptember 1982,IIAlaska Natural Gas Development:An Economic Assessment of Marine Systems ll ICF Incorporated for Maritime Research and Development,Office of Maritime Technology. 31.Kidder,PeaboQy and Co.Inc.,March 1982 IlReport to the Governor1s Task Force on State of Alaska Participation in Financing the Alaskan Segment of the Al aska Natural Gas Transportation System IIKi dder, Peabody and Co.Inc.New York,New York. 32.L;ndah1,Dav;d,November 1981,liThe Methanol A1 ternative to the Al aska Natural Gas Transportati on System ll ,Congressi ona 1 Resea rch Service,The Library of Congress,Environment and Natural Resources PoliCY Division,Washington,D.C. 2972A 4 ('" l !' f-: [, (~ '-.-, F l. (, \, L l L E r [ c- f' [ r~;"" C" p- {,c-_ [" U C L (i [ [ "0 •• c- l..-•.• L-·.~-. I L 33.H.Malone and B.Rogers,Chairmen,Sept.1980,"Final Report House PO~/er A1 ternatives Study COrmJittee,Alaska State Legis1ature"State of Alaska. 34.K.M.O·Connor and P.O.Dobey,January 1977."Analysis of Prudhoe Bay Royalty Natural Gas Demand and the Proposed Prudhoe Bay Royalty Natural Gas Sa1e ll •State of Alaska,Dept.of Natural Resources, Di vi si on of Mi nera1 s and Energy Management,Anchorage,A1 aska. 35.Ralph M.Parsons Co.,September 1978 "Sa1es Gas Conditioning Facilities,Prudhoe Bay,Alaska -Volume I,Summary"Ralph M. Parsons Co.,Job No.5795-1 36.Robert W.Retherford Associ ates,March 1977.II North Slope Natural Gas Transport Systems and thei r Potential Impact on Elect"'i c Power Supply and Uses in Alaska".Robert W.Retherford Associates, Anchorage,A1 ask.a. 37.Scott,Michael J.et al,January 1982,"Alask.a -Historical and Projected Oil and Gas Consumption II ,Battell e Pacifi c Northwest Laboratories,Richland,Washington,for State of Alaska,Department of Natural Resources,Division of Minerals and Energy Management. 38.Sl avi ch,A.L.,Jacobsen,J.J.,November 1982,liRa il be 1t El ectri c Power Alternatives Study;OVER/UNDER (AREEP VERSION)Model Users Manual -(Volume XI -Draft)1I Battelle Pacific Northwest Laboratories,Richland,Washington,for Office of the Governor, State of Alaska,Division of Policy Development and Planning and the Governor·s Policy Review Committee. 39.Smith,Daniel W.,Ed.,Januar,y 1977,Proceedings:Symposium on Utilities Delivery in Arctic Regions;Edmonton,Alberta.Report EPS 3-WP-77-1. 2972A 5 LIST OF CONTACTS (Continued) Peter Christensen Brown &Root,Inc. Name R.H.Dempsey Mead Treadwell Don Hale Don Wold 2910A Organization/Agency Al aska Interior Resources Company,Vice President Governor's Economic Committee on Alaska Natural Gas,Executive Director Brown &Root,Inc.Manager Pipeline Engineering Department Royalty Oil and Gas Advi sory Board 6 Reason for Contact Methanol Plant plans for Fairbanks,gas and electricity use. Governor's Economic Committee on Alaska Natural Gas study, "was te"gas compositi on,"was te" gas volumes,location of all- Alaska pipeline route and conditioning plant. Governor's Economic Committee on Al aska Natural Gas study, "waste"gas composition,"was te" gas volumes,location of all- Alaska pipeline route.and conditioning plant. Governor's Economic Committee on Alaska Natural Gas study, "waste"gas composition,"waste" gas volumes,location of all- Alaska pipeline route and conditioning plant. Governor's Economic Committee on Al aska Natural Gas study, "waste"gas composition,"waste" gas volumes,location of all- Alaska pipeline route and conditioning plant. r r r~ l F= ~. L' I\L_~_, c [: L t. L. L l C L [ C C 6 6 [ [ [,. CI . [ 48.Uni versity of Al aska,Arcti c Envi ronmenta 1 Infonnati on and Data Center,July 1978,"Deadhorse"U.S.Dept.of Interi or. 49.University of Alaska,Arctic Environmental Infonnation and Data Center,July 1978,"Nuiqsutll U.S.Dept.of Interior. 50.University of Alaska,Arctic Environmental Infonmation and Data Center,July 1978,liThe Region"U.S.Dept.of Interior. 51.University of Alaska,Arctic Environmental Infonnation and Data Center,July 1978,"Anaktuvuk Pass"U.S.Dept.of Interior. 52.University of Alaska,Arctic Environmental Infonnation and Data Center,July 1978,I'Barrow -Sheet I II U.S.Dept.of Interi or. 53.H.K.Van Poollen and Associates,Inc.,March 1980, "Three-Dimensional Reservoir Study,Sadlerochit Fonnation,Prudhoe Bay Field"State of Alaska,Oil and Gas Conservation Commission, Anchorage,Alaska. 2972A 7 [ [ [~ r\~~~ r~ f~- [' G ~ [ [ [ [ [; [ [ [ L . C l [ ADDENDUM B LIST OF CONTACTS Darrell Jordan ARCO-A1aska NORTH SLOPE GAS FEASIBILITY STUDY LIST OF CONTACTS [ [ [ [' [ [ [ PL; Name Ben Ball Bob Crosky Loren Doug1 as William Friar Organization/Agency ARCO-A1aska ARCO,Vice President Alaska Affairs ARCO-A1aska ARCO-A1aska Reason for Contact Gas composition at Central Compressor Plant. Gas use and facilities tour. AReo's electrical system. General North Slope information, facil i ti es tour. Foundation design practice-North Slope. 1 Archie Walker ARCO-Alaska Richard Blumer SOHIO 29l0A Gas use and plant tour. ARCO's electrical system. Facilities tour. North Slope construction and operation considerations. General North Slope information, faci1 ities tour. Fairbanks'electrical system and climatological data. Fairbanks'electrical system and climatological data.. Weight &size restrictions for barged modules to North Slope. Foundation design practice-North Slope.. SOHIO's North Slope electrical system and power plant design. Gas use and plant tour. ARCO-A1aska Charles Elder SOHIO,Vice President Al aska Affairs Mary Jane Little ARCO-A1aska, Administrative Supervisor Paul Norga'rd ARCO-A1aska,President Brad Spencer ARCO (Pasadena) Richard Lipinski SOHIO,Manager Construction Support Paul Martin SOHIO,Vice President Operations Larry Co1p Fairbanks Municipal Utilities System Alan Martin Fairbanks Municipal Utilities System Jim Moreland C L 8 o p c.c» 6 [ [ [ C, [ LIST OF CONTACTS (Continued) Name Organization/Agency George Ott Fairbanks Municipal Utilities System,Public Services Director William Per~Fairbanks Municipal Utility System,General Manager Gary Rice Fairbanks Municipal Utilities System Keith Sworts Fairbanks Municipal Utilities Systems Harold Alexander Alyeska Pipeline Co. Reason for Contact General information.Chena plant design. Power requirements and plant tour. General Civil Information.Chena Pl ant Desi gn. General utility statistics - fuel consumption by type;steam and electric baseload data, rate structure,expansion plans. Chena plant design,facility tour. General information,facility tour. c L Alyeska,Technical Manager,Proximity to TAPS,right-of- ANGTS Relations way constraints. Frank Fi sher Jim Hdrley Eldon Johnson Joe Pitman John Ratterman Andrew Sma rt Jim Weiss Bela Gevay Bonnie Rappaport 29l0A Alyeska,Al aska Manager, ANGTS Relations Alyeska Pipeline Co. Aleyska,Pump Station 1 A1yeska,Manager Publ ic Affairs Alyeska,Corrosion Engineer Artic Environmental Informati on Data Center Private Consultant MAPCO (Parent of North Pole Refine~) 2 Proximity to TAPS,right-of- way constrai nts. Climatological data. Pump station operation. General information,facility tour. Effect of HVDC on TAPS. Climatological data. Prudhoe Bay e1ectr.network data Current fuel oil prices, Residential Btu requirements. [ L r [ L tJ [ L -L -l [ LIST OF CONTACTS (Continued) Reason for Contact Energy needs. Potential fuel cell use in Fai rbanks. Power plant sta~tistics,fuel . consumption by type;number and area of buildings served for both steam and electricity peak and baseload data and expansion pl ansa Potential gas use. Organization/Agency Uni versity of Al aska Plant Engineer University of Alaska (Fairbanks)Power Plant Operator Name Gerald England College Utilities General Manager Dr.James Ma10sh University of Alaska (Fairbanks)Director Dept.of Transportat;'on Fuel Cell Study George Gordan Staples Brown [ [ [ r-- [~ [- e- n- L Energy needs. Right-of-way corridor. Annual energy reports,energy balance report,fuel source & end use statistics. 3 City of Fairbanks,Right- of-Way Agent Ft.Wainwright Facility Engineer Energy Specialist - Communi ty Resource Center, Fa i rbanks 29l0A Craig Helmuth University of A1 aska Appliance stock and saturation (Fairbanks)Cooperative data. Extension Agency -Energy Special ist Mayor,North Star Borough Electricity and gas use. Assessor,North Star Gas and electricity use and Borough land values. Director of Planning Gas and electricity use. North Star Borough Fonner Mayor,North Star Gas use. Borough Richard Van Orman Deputy Director of Planning Gas distribution right-of-way. North Star.Borough Robert 5i eforts Bill Allen Ca ry Brewster Dave Braden John Weaver John Carlson. Scott Burgess f' L 8 tl A.-.,tj C fj [ r..-ri~.__ l I- ii [ LIST OF CONTACTS (Continued) Name Major Terry Lane Jan Bre\ter John Vdradi Wally Droz Len McLean Tim Wallace A.W.Baker Organization/Agency Elmendorf AFB Residential Energy Audit Program Shawani gan Engi neeri ng City Manager,Fairbanks Pacific Alaska LNG Al aska Affai rs Manager Doyan,Inc.,President Golden Valley Electric Association Reason for Contact Federal building fuel use in Fairbanks. Energy audit data base, Fairbanks. Prudhoe Bay electrical network data. Gas distribution system. Status of LNG plant,gas development plans,gas prices. Gas distribution. North Pole and Fairbanks plant design,tour. [' L Ron Hansen Eri c Haemer Dan Li ndsey W.McKinney f4ark All i sson Bruce Pasternak Ben Schlesinger Kathy Thomas 29l0A Golden Valley Electric General utility statistics - Association fuel consumption by type;steam and electric baseload data, rate structure,expansion plans. Chugach Electric Beluga PO\'Ier Plant design,tour. Association,Inc.Division Manager-Systems Planning Chugach Electric Beluga Power Plant design,tour. Association,Inc. G.E.A.,san Diego Air-cooled condenser design information. General Electric Co.Gas turbine data. Seattle,Washington Booz-Allen &Hamilton,Inc.To discuss DNR North Slope gas Vice President,Energy and study,coordinate study efforts. Environmental Division Booz-Allen &Hamilton,Inc.To discuss DNR study,coordinate Principal study efforts. Booz-Allen &Hamilton,Inc.To discuss DNR study,coordinate study efforts. 4 [ [ [ [ r't~~ [ r-'l._; [ L L 5 LIST OF CONTACTS (Continued) State of Alaska,~partment Gas revenues. of Revenue Reason for Contact Constraints on use of North Slope gas. Constraints on use of North Slope gas. Organization/Agency Attorney General's Office, Supervising Attorney State of Alaska,Attorney General State of Alaska,Department To discuss DNR study,coordinate of Natural Resources,study efforts. Budget &Management State of Alaska,Department Gas composition,availability, of Natural Resources,constraints and prices. Special Assistant to the COnuDissioner State of Alaska,Department Gas revenues,production. of Revenue,Petroleum Revenue Division State of Alaska Department Status of ANGTS,SPCO Library, of Natural Resources,right-of-way constraints. State Pipeline Coordinator State of A1 aska,Department Gas production. of Natural Resources. State of Alaska,Department Determine gas supplies, of Natural Resources,Oil constraints,availability.&Gas Conservation Commission,Commissioner State of Alaska,Department Determine gas supplies, of Natura1'Resources,Oil constraints,availability. &Gas Conservation Commission,Commissioner State of Alaska,Department Determine gas supplies, of Natural Resources,Oil constraints,availability. &Gas Conservation Commission,Commissioner Alvin G.Ott Name R.Maynard Vi nce Wri ght Ed Park Ronald Ripple B.Hennan Chuck Logsdon Mark Wittow L.Smith C.V.Chatsworth H.Kugler 2910A [ [ ~. C [ l~ L~ 1.._- L L_ [ L L [ LIST OF CONTACTS (Continued) Peter Christensen Brown &Root,Inc. Name R.H.Dempsey Mead Treadwell Don Hal e Don Wo1 d 2910A Organization/Agency Alaska Interior Resources Company,Vice President Governor1s Economic Committee on Alaska Natural Gas,Ex ec uti ve Di rector Brown &Root,Inc.Manager Pipeline Engineering Department Royalty Oil and Gas Advi sory Board 6 Reason for Contact Methanol Plant plans for Fairbanks,gas and electricity use. Governor1s Economic Committee on Alaska Natural Gas study, Ilwaste ll gas compositi on,IIwas te ll gas volumes,location of a1l- Alaska pipeline route and conditioning plant. Governor1s Economic Committee on Alaska Natural Gas study, IIwas te ll gas compositi on,II was te ll gas volumes,location of a1l- Alaska pipeline route and conditioning plant. Governor1s Economic Committee on Alaska Natural Gas stUdy, IIwas te ll gas compositi on,IIwas te ll gas volumes,location of a11- Alaska pipeline route and conditioning plant. Governor1s Economic Committee on Alaska Natural Gas study, .lIwas te ll gas composi ti on,IIwas te ll gas volumes,location of a1l- Alaska pipeline route and conditioning plant. L r ["' c L [ C U r b [ [ L L U [ II I I I I I I~ I I ~ l~ I _. ~- I I L I I I L I L_ I APPENDIX 8 [ r··C· [ (- [: [ ,•._. [ r n L C'· L 8 Q o C 8 [ [ [ [.. ...-. j [ APPENDIX B REPORT ON SYSTEM PLANNING STUDIES DECEMBER 1982 B2.1 Technology Review ••.•••••••• B2.2 Derivation of New Capacity Requirements • B2.3 Application of Technologies to Requirements • B2.4 Economic Evaluation •••• . . ... . . ... . . .. .. ... . B4.1 Technical Assumptions and Data ••. 84.2 Economic Assumpti ons and Input Data Page Bv B1-1 .B2-1 B2-1 B2-1 B2-2 82-3 B3-1 B3-1 B3-2 B3-3 B4-1 84-1 B4 ...5 B5-1 B5-1 B5-1 65-5 B5-24 B6-1 B6-1 B6-1 B6-2 B7-1 . .... .. TABLE OF CONTENTS . . ... . . . . ... . Bi i B5.1 System Capacity Review. B5.2 Selection of Unit Sizes B5.3 New Capacity Requirements • B5.4 Economic Analyses and Results B6.1 Economic Conc1u~ion 86.2 Technical Conclusion B6.3 Recommendation B3.1 Simple Cycle Technology • B3.2 Combined Cycle Technology. B3.3 Gas Fired Boilers ••• 3105A B7.0 REFERENCES B6.0 CONCLUSIONS AND RECOMMENDATIONS B5.0 RESULTS •.••••.••• B3.0 TECHNOLOGY REVIEW ••••••• B4.0 ASSUMPTIONS AND INPUT DATA .•• B1.0 INTRODUCTION. B2.0 METHODOLOGY • SLMMARY •• t~ ~ C C· p..-:E [ [ '. L C E [' L r LIST OF TA8LES [ Tabl e Number Title Page L84-1 CAPACITIES AND HEAT RATES FOR SIMPLE AND COMBINED CYCLE UNITS B4-2 B4-2 ASSUMED CAP !TAL COSTS B4-4 [ B4-3 ECONOMIC ASSUMPTIONS B4-6 l- B5-1 EXISTING CAPACITY,PLANNED ADDITIONS, UNIT RETIREMENT SCHEDULE,AND PEAK DEMANDS B5-2 rB5-2 CAPACITY REQUIREMENTS AT PLANNING RESERVE MARGINS -LOW LOAD FORECAST B5-3 B5-3 CAPACITY REQUIREMENTS AT PLANNING RESERVE [ MARGINS -MEDIUM LOAD FORECAST 85-4 B5-4 NEW CAPACITY ADDITIONS -LOW LOAD FpRECAST ['NORTH SLOPE 85-6 85-5 NEW CAPACITY ADDITIONS -LOW LOAD FORECAST [ FAIRBANKS 85-7 L B5-6 NEW CAPACITY ADDITIONS -LOW LOAD FORECAST [KENAI B5-8 B5-7 NEW CAPACITY ADDITIONS -MEDIUM LOAD [FORECAST -NORTH SLOPE 85-9 85-8 NEW CAPACITY ADDITIONS -MEDIUM LOAD FORECAST -FAIRBANKS B5-10 C B5-9 NEW CAPACITY ADDITIONS -MEDIUM LOAD FORECAST -KENAI 85-11 L85-10 PRESENT WORTH OF COSTS -0%ESCALATION B5-26 CB5-11 PRESENT WORTH OF COSTS -1%ESCALATION 85-27 , B5-12 PRESENT WORTH OF COSTS -2%ESCALATION 85-28 85-13 PRESENT WORTH OF COSTS -3%ESCALATION B5-29 [ [ Biii L .[ [ SUMMARY Ebasco prepared this report to identify from both an economic and technical viewpoint,the power generating technology and scale which .best satisfy the requirements associated with Railbelt electric. capacity demand forecasts.The report also identifies on a preliminary basis the year of installation of each new generating unit to be added to the system through the year 2010. As discussed herein,a 220 MW (ISO conditions)combined cycle plant size is considered optimum for development for the Fairbanks and Kenai scenarios for reasons of flexibility,economics,and number of units to be installed.In the case of the North Slope,simple cycle combustion turbines are preferred.Each 220 MW combined cycle plant is cemprised of two 77 MW gas turbines and a 66 MW.steam turbine.Si·mple cycle units are 77 MW gas turbines.These capacities are at ISO conditions, as discussed within the text;actual capacities are higher at specific locations due to temperature differentials.The staging plan recommended for each location and technology is summarized below: LOW LOAD FORECAST MEDIUM LOAD FORECAST YEAR NORTH SLOPE FAIRBANKS KENAI NORTH SLOPE FAIRBANKS KENAI 1993 0/0 0/0 0/0 91/91 86/86 84/84 1994 0/0 0/0 0/0 0/0 0/0 0/84 1995 0/0 0/0 0/0 91/182 86/172 84/168 1996 91/91 86/86 84/84 91/273 70/242 69/237 1997 91/182 86/172 84/168 91/364 172/414 168/405 1998 0/182 0/172 0/168 91/455 70/484 69/474 1999 0/182 0/172 0/168 0/455 0/484 0/474 2000 0/182 0/172 0/168 91/546 86/510 84/558 2001 0/182 70/242 69/237 0/546 0/570 0/558 2002 91/223 86/328 84/321 182/728 156/726 153/711 2003 91/364 0/328 0/321 0/728 0/726 84/795 2004 0/364 86/414 84/405 91/819 86/812 84/879 2005 182/546 70/484 69/474 182/1001 156/968 153/1032 2006 0/546 86/570 84/558 91/1092 86/1050 84/1116 2007 0/546 0/570 0/558 91/1183 86/1140 0/1116 2008 91/637 86/656 84/642 91/1274 70/1210 69/1185 2009 0/637 0/656 0/642 0/1274 86/1296 84/1269 201 0 91/728 70/726 69/711 91/1365 86/1382 84/1353 Bv [ r -L r~ r- L [ F= L~ [ L [ [ C L L L L [' :[ [ [ [ [; r- [ r- [' p ~ [ L [ o C F.~ b U, [ ['........., L [ [ B1.0 INTRODUCTION The use of North Slope natural gas,or any other fossil fuel,for generating power to meet the demand for electrical energy in the Rai1be1t region requires careful system planning to optimize the addition of new generation capacity.Capacity additions must be sized and scheduled to meet increased demand for energy,replace older units as they are reti red,and provide a system reserve margi n that assures an un~nterrupted power supply. This system planning studY utilizes data from the Acres American Inc. (1981)and Bal1el1e Pacific Northwest Laboratories (1982)studies to detenmine demand levels for energy,an acceptable range for Rai1belt system reserve margins,and the capacity deficits that must be... satisfied with new electrical generation.This capacity deficit forecast is then used to develop various scenarios for addition of new capacity from one of the available technologies capable of utilizing North Slope natural gas. Planning for the growth of the system requires selection of a type or types of technology to be used for the new generation capability. Selection of the optimum technology(s)is a function of the fuel type and cost,technology efficiency,required capacity additions,capital and operating and maintenance costs,and licensing and cC?nstruction times.'The purpose of this system planning study is to evaluate and recommend,from both an economic and a technical viewpoint,the techno1ogy(s)and scale which best satisfy capacity,reliability and least cost criteria.Further,the study recommends on a pre1imina~ basis the year of installation of each new generating unit to be added to the system through the year 201 O. This System Planning Report is the second of a series in developing a feasibility level assessment regarding the use of North Slope natural gas for power generation in the Rai1be1t and for residential/commercial heating uses in Fairbanks,and as such provides reqUired data necessa~ for the completion of the overall feasibility study.The results of 3105A 81-1 this analysis assure that the feasibility study analyzes scenarios which meet the needS of the Rai1be1t region.The specific outputs which will be used to complete the balance of the feasibility study are selection of the optimum power generating technology and unit size,and proper~iming of unit addition to maintain reserve margins,thus providing the bases for facility design,siting,cost estimating,and environmental assessment. 3105A 81-2 [ [ [ r [' f f F~ Lc [ L [ [ L C L [, rL [' L L [ [ C C L [ L [ [ [. B2.0 METHODOLOGY B2.1 TECHNOLOGY REVIEW It was detenmined that there are three applicable technologies that could be used to generate electricity by using North Slope gas.These are simple cycle gas turbines,combined cycle installations (gas turbines with heat recovery boilers and steam turbines),and gas fired boilers with steam turbines.Each technology was reviewed to detenmined the state-of-the-art,efficiency,size,availability, constructability,and conceptual design criteria.This review data was then evaluated in light of the three locations considered in the feasibility stuqy,(i.e.,the North Slope,the Fairbanks area,and the Kenai area)to detenmine technology appl icabi 1ity.Fi nally, advantages,disadvantages and potential problems associated wit~each technology in each location were detenm1ned and evaluated. B2.2 DERIVATION OF NEW CAPACITY REQUIREMENTS Data from two sources were used to develop the new capacity requirements for the Railbelt region.Reserve margins and low load growth forecasts for the region were derived from Battelle's Evaluation of Railbelt Electric Energy Plans -Comment Draft (Battelle 1982). Medium load growth·forecasts,planned power plant additions for the immediate future,and the retirement schedule for existing Railbelt generating capacity were obtained from the final draft Susitna Hydroelectric Project Feasibility Report (Acres American Inc.1981). The reserve margins and load forecasts were used to establish maximum required capacities for each year through the year 2010.Existing capacity plus planned additions and retirements were used to establish the balance of existing capacity for each year.These two derived data sets were then used to establish the required new capacity for each year. 3105A B2-1 82.3 APPLICATION OF TECHNOLOGIES TO REQUIREMENTS The results of the technology review provided the data necessary to project the units of new generation capacity required to satisfy electrical demand.The size of units for addition were selected based on least capital cost and the range of unit sizes which satisfied the new capacity requirements without greatly exceeding maximum reserve requirements.These unit sizes were then applied to create scenarios for new generating capacity.Of the three technologies previously mentioned (simple cycle,combined cycle and gas boiler)two were found to be acceptable for applicQtion in this study.Those two are simple cycle and combined cycle gas turbines.The direct fired gas boiler/steam turbine was jUdged to be non--competitive due to high capital costs which are not offset by any significant advantage in either heat rates or operating and maintenance costs.Operating costs advantages which might be realized with this technology in very large plants are not available in the unit size range (150-350 MW)being consi dered here. [ L 82-2 3105A Locale!! Temp 2/Gas Turbine Steam Turbin~Heat Consumption OF Capacity Change Capacity Change Change North Slope 90 +18.2%+3.5%+14.6% Fairbanks 26 0 +12.0%+2.2%+9.6% Kenai 33 0 +9.5%+1.7%+7.5% The two remaining technologies with the two different load growth forecasts resul tin four basi c scenari os.It is then necessary to consider the effect of ambient conditions on capacity and efficiency at each of the three potential scenario locations.The primary factor affecting operation is temperature.After reviewing the effects of the average annual temperature on capacity and efficiency at each location, it was decided that the locales must be considered separately.The following table shows the effect of temperature on capacity and efficiency. [ [ [ C [; [ [ -L C [ Changes are based on International Standards Organization (ISO) conditions for base loaded units,which are 59 0 F and sea level. Average annual temperature. Applies to steam turbines as part of combined cycle only. .!/ 2/ ""5/ L [ C' [' [ L [ n L,..i C L b [ C C ['~ ; C C L L ! [ IL"_ These three sets of conditions combined with the four basic scenarios result in 12 locale specific scenarios for evaluation and comparison. As input for economic evaluation,the total energy (GWh)generated for each scenario in each year was also developed. 82.4 ECONOMIC EVALUATION Developed scenarios were analyzed to determine which resulted in the lowest overall cost on the basis of present worth of costs.In order to perform this analysis it was necessa~to develop capital,operating and maintenance,and fuel costs for each technology and to calculate the total energy generated in each year for each scenario.The economic model yielded the total cost of each scenario in 1982 dollars. 3l05A 82-3 rL c [J C b C [ [ L [ ! L B3.0 TECHNOLOGY REVIEW Three mature and proven technologies were reviewed for application to the Railbelt.They are Simple Cycle Gas Turbines,Combined Cycle Systems (Gas Turbine with Heat Recovery Boilers and Steam Turbines), and Gas Fired Boilers with Steam Turbines. It is common industrial practice to quote heat rates for oil and gas fired simple cycle turbines as a function of the lower heating value of the fuel.However,fuel is purchased by higher heating value,and other technologies'heat rates are in tenms of higher heating values. In this report heat rates quoted and used for analysis are based on higher heating values.Where applicable,lower heating value heat rates are given in parentheses. B3.1 SIMPLE CYCLE TECHNOLOGY Simple cycle gas turbines are available from several vendors ina variety of sizes.Review of the designs,lead times for licensing and construction,and constructabi1ity of the gas turbines led to the . conclusion that they would be applicable to all three potential locations considered in the feasibility study.Heat rates for these units vary from 11,800 to 13,000 Btu/kWh (10,600-11,700 Btu/kWh-LHV). Pre-constructed simple cycle units for the North Slope can be shipped by barge from a lower 48 port for installation at the slope.Existing piling and support methods at the slope are adequate for units up to 100 MW,the largest commercially available unit size.Handling capabilities for 2400 ton units a1reaqy exist at the North Slope and are sufficient for this option.The units would be moved into place on crawl ers,1eve led on pre-pl aced steel and concrete pilings,and connected to the gas supply and electrical systems.Several gas fi:ed simple cycle units of this type are already in operation at the North Slope. 3105A B3-1 A Fairbanks area location for gas turbines wou1 d all ow "i n p1 ace" construction on typical spread footings or pilings.There are many existing combustion turbine units in operation in the Fairbanks area using distillate fuel. The Kenai area option for simple cycle differs from that for Fairbanks only in the quality of the fuel.The waste stream fuel to be used here is expected to have a very low heating value (approximately 175-195 Btu/ft3 )and high CO 2 content.Gas turbines can be modified for firing on fuel with heating values as low as approximately 150 Btu/ft3 •Such firing requires modification of the combustion chamber,valving and piping,and requires that the units be started up on higher Btu fuel such as distillate or natural gas.An additional problem is that the high CO2 content of North Slope gas res~lts in a c~nditioning facility waste gas that will be difficult to'burn due to the quenching effect that CO 2 has in the combustion chamber.This problem can be overcome by blending higher Btu content gas during startup and less than full load operation,and through modifications to hardware,similar to those for the low Btu problem. The total energy available in the waste stream is insufficient to meet the'energy needs of the Ra i 1belt.It is,therefore,necessary to supplement the waste 'stream with some of the sales gas which will be the main product of the conditioning facility. B3.2 COMBINED CYCLE TECHNOLOGY Combined cycle technology has matured in the past 10 to 15 years. Typically larger gas turbines (50 MW and greater)are used for combined cycle plants in order to supply enough waste heat for an economically designed heat recovery boiler.Also,two or more heat recovery boilers are used to drive one steam turbine.The range of heat rates for operating combined cycle plant is 8,350 to 9,200 Btu/kWh (7550-8300 Btu/kWh-LHV).For the steam CYCle,the site environments considered in this study strongly favor the use of air cooled condensers.Air cooled condensers have been built for combined cycle plants and for steam 3105A B3-2 [ [' L r 'I' I [' F Lc I. L [ t-.·~..., ~-; [ C r..;'c [ L [ L [ [ r-- ~­ [ [ [', ~l~, r L c' [ C C C [ [ [ L L _" [ boiler plants as large as 350 MW,and have been operated under applicable ambient conditions.An air cooled condenser is presently operating in the Beluga area for the steam cycle of a 179 MW combined cycle plant. Combined cycle plants for the North SlQpe will be pre-constructed in three subunits for assembly at the slope in a manner similar to that described for simple cycle units.A plant would consist of two gas turbine units with heat recovery steam generators,one steam turbine-generator set with attendant equipment,and one air cooled condenser.The heaviest unit to be handled is the steam turbine-generator module that weighs approximately 2300 tons. Constructability could be a problem since the three modular units and the field-erected condenser would require assembly during the short.'. North Slope construction season.It is felt,however,that careful planning of logistics and manpower can make this feasible. Combined cycle plants in the 150 MW range have been built within the Railbelt region.Only one problem other than typical siting and environmental questions is anticipated for either of the two southerly locations.That problem is the low heating value and high CO 2 content of the conditioning facility waste gas which will also effect the design of the gas turbines for the combined cycle units.Further, this gas quality may a)so effect the'size and efficiency of the heat recovery boilers and the steam cycle. B3.3 GAS FIRED BOILERS The direct fired steam boiler with steam turbine-generator is the most widely used technology of the three being considered.Identical in concept and general design features with coal fired plants,gas fired boilers are most efficient and economical in larger units.For this reason the technology was considered in 200 MW and larger sizes. 3l05A B3-3 At the North Slope,the short construction period and phYsical size of the boiler.present severe problems for erection of a gas fired boiler unit.PhYsically handling a pre-assembled boiler on crawlers is not practical,especially when one considers the difficulty .of maintaining the integrity of the pressure parts and t~e casing.Another problem is the physical size of the turbine-generator set.A 200 MW steam turbine-generator pre-assembled on foundations far exceeds the North Slope handling capacity of 2400 tons.Finally,the short construction season of the North Slope does not allow erection at the site.An alternative which may be viable,however,is to pre-erect the entire unit on barges,move the barges to the North Slope and pennanently anchor or beach them in shallow water.Three barges would be necessary,one for the boiler,one for the turbine-generator,and one for the air cooled condenser and auxiliaries. Construction of gas fired boilers within the Railbelt (e.g.,at Fairbanks and Kenai)does not present the severe problems seen at the North Slope and could be accomplished in the same manner as the other technical alternatives.As with the other alternatives,the waste gas option presents problems.The low heating value of the gas will result in much larger furnace volumes and lower efficiencies. Gas fired steam turbine gener.ationsystems have higher capital costs (approximately 50 percent higher)on a $/kW installed basis and higher heat rates (9,500-ll,000 Btu/kWh)than combined cycle units.As a consequence,it would not be advantageous to install them in any of the considered locations,in that there would be a capital cost and fuel cost disadvantage.Operating cost advantages which might be realized with this technology in very large plants are not available in the required unit size range.For these reasons gas fired boilers were eliminated from further study. 3l05A B3-4 r ~ [ [ [ r- [ [ [ L [ L C C~··'···.-. L [' \ L L L L B4.0 ASSUMPTIONS AND INPUT DATA B4.1 TECHNICAL ASSUMPTIONS AND DATA The plant heat rates used in this study result from a review of existing plants and data supplied by equipment vendors.As mentioned, simple cycle gas turbines have heat rates which vary from 11,800 to 13,000 Btu/kWh (10,600-11 ,700 Btu/kWh-LHV).The simple cycle capacities and heat rates used are listed in Table B4-1. The range of heat rates for operating combined cycle plants is 8350 to 9200 Btu/kWh (7,550-8,300 Btu/kWh LHV)while available technology for new plants claim heat rates as low as 8200 Btu/kWh for a 225 MW (net) plant.The heat rates assumed in this study are shown in Table B4-1. Fuel costs for coal,oil,and gas fired plants in the Railbe1t region were investigated.At present coal generally varies from $2.10 per million Btu for a mine mouth location to as much as $4.50 per million Btu when remote from its source.Based upon discussions with utilities in the Railbe1t region,distillate prices for uti1iti~s are presently .ina range of $5.03 to $5.60 per mtll ion Btu.Thi s price is al so sensitive to location and is higher at remote locations.A current export market price for natural gas is $5.50 per million Btu,While the Battelle (1982)IIRai1be1t Electric Power Alternatives StUdy: Evaluation of Rai1be1t Electric Energy Plans"cites an anticipated Fairbanks price of $5.92 per million Btu for North Slope gas.There are existing contracts for sale of natural gas in the Cook Inlet area at prices under $1.00 per million Btu.Due to these low prices and the relatively high prices of alternate fuels,it was decided to utilize a range of gas prices thus providing a sensitivity analysis for technology selection as a function of fuel price.The fuel prices that were used were $0.00,$1.50,$2.50,$3.50,and $5.50 per million Btu. 3105A B4-1 TABLE B4-1 CAPACITIES AND HEAT RATES FOR SIMPLE AND COMBINED CYCLE UNITS SIMPLE CYCLE GAS TURBINES Locale Ambient Capacity Heat Rate Temperature..!!(MW)(Btu/kWh)2/ North Slope 9°91 11,500 Fairbanks 26°86 11 ,600 Kenai 33°84 11 ,650 COMBINED CYCLE UNITS Local e Jlmbient Capacity Heat Rate Temperaturell (MW)(Btu/kWh)2I North Slope 9°F 253 8,320 Fairbanks 26°F 242 8,290 Kenai 33°F 237 8,280 1I/Average annual temperature. ~Based on higher heating value. 3105A B4-2 r [ [ l [~ [' [ Rl~; c [ C [, [ [ l L L L Ebasco reviewed the operating and maintenance (DIM)costs used in the Railbelt Electric Power Alternatives Study (Battelle 1981)for applicability to this analysis.After comparing these to current manufacturer's maintenance recommendations,other utility DIM costs and to Edison Electric Institute's (1981)Guides for Operating Practice,it was decided that th~~attelle figures remained adequate for application to the Railbelt region scenario in this stUdy.For the North Slope option,higher wages,shorter work seasons,and adverse working conditions resulted in revised higher DIM costs.All DIM costs are 11 sted below: [- r~ [' [- [ [ [ nw.. Locale North Slope Fairbanks or Kenai Simple Cycle Units (mil s/kWh) 6.3 4.6 Combined Cycle Units (mil s/kWh) 5.5 4.0 Capital costs for each new technology were also developed.The costs are in 1982 dollars/kWh for the unit sizes used in each technology. These costs were derived after reviewing costs of past and current similar projects in both Alaska and the lower 48 states.It should also be noted that these costs refer only to the power generation facilities and do not include costs associated with transmission lines or fuel supply facilities.These costs are shown in Table 84-2. In order to develop the number of gigawatt~hours generated for each scenario,it was necessary to make several assumptions.First,it was assumed that the new units would operate at an average capacity factor of 0.75.Secondly,it was assumed that all existing hydro power would be base loaded and operated at a capacity factor of approximately 0.50 (Acres Ameri can Inc.1981).It was also assumed that the new gas fired 3105A 84-3 TABLE 84-2 3105A 1/Adjusted for capacities at specific locations. North Slope Simpl e Cycl e 798 589 Combi ned Cycl e 951 865 Fairbanks Simpl e Cycl e 452 394 Combined Cycle 557 527 Kenai Simpl e Cycl e 488 415 Combined Cycle 572 540 ASSUMED CAPITAL COSTs!./ C L (~ °o~ r~ [ c [ [ r~ L [ [ r 0,[ \" Co [. r~ l~ 84-4 Capital Cost (1982 $/kW installed) First Plant Subsequent PlantTechnologyRegion L units would replace older existing units for base load and that the older units would become part of the reserve margin until they are retired.Finally,all new gas fired capacity was assumed to generate energy up to the lower of either their limit at 0.75 capacity factor, or to the total required energy in each year after deducting the ~dro supplied energy.The 0.75 capacity factor was selected as a conservative estimate for individual gas turbine or combined cycle units.The system capacity factor will be significantly lower. 84.2 ECONOMIC ASSUMPTIONS AND INPUT DATA In perfonming the economic evaluation of the alternate development scenarios,economic factors utilized in the Rai1belt Electric Power Alternatives Study (Battelle 1982)were employed.These are summarized in Table 84-3.The period of analysis was assumed to be 1983 through 201 O.The useful 1ife of the combusti on turbines and heat recovery steam generators (waste heat boilers)was assumed to be 30 years.The inflation ,rate was assumed to be 0 percent.Capital costs were assumed to escalate at the rate of inflation.Operating and maintenance costs, similarly,were assumed to escalate at the rate of inflation.Fuel costs were assumed to escalate at a rate varying from 0 to 3 percent greater than inflation,in 1%increments.The discount rate was assumed to be 3 percent. These standard factors were developed in order to make different economic studies comparable.In some cases additional comment is warranted.Inflation,for example,is taken at 0%in order to convert all analyses into urea 1u doll ars.Capital costs are assumed to escalate at the rate of inflation,as this trend has existed for the last few years and has been documented by the Power Authority.Fossil fuel costs (typically oil)are escalated at a rate higher than i nfl ati on. 3105A 84-5 TABLE B4-3 Item Period of Analysis ECONOMIC ASSUMPTIONS Assumptions 1983-2010 r' l Life of Boilers,Combustion Turbines, and Heat Recovery Steam Generators Salvage Value,All Cases Fuel Costs Inflation Rate Capital Cost Escalation Rate Fuel Cost Escalation Rate O&M Escalation Rate Discount Rate 3l05A B4-6 30 yrs $0 $0 to $5.50jmi11ion Btu (1982) 0% 0%(Real) 0%to 3%(Real) 0%(Real) 3.0%(Real) C1-Li [, I~- L fJ r-- C· L r"l", (, l,c '. C r; G U [ L L I _ [' - ,- [ In addition,no salvage values were taken despite the fact that some projected generating units only had a project life of 1 to 2 years within the period of analysis.The elimination of salvage values (or val ues of unuti lized capital)from the analysi s was made for two reasons:1)it was assumed that if differentials in annual costs occurred between technologies following the year 2010,they would accentuate trends emerging within the period of analysis;and 2)it was recognized that the influence of discounting,even at 3 percent,would make any apparent differences after the year 2010 small (e.g.,one dollar,discounted at 3 percent from 1982 to the year 2010,is only worth $0.44). 3105A 84-7 [ c-- [- r c-- L [ G te'_ (>- U 85.0 RESULTS 85.1 SYSTEM CAPACITY REVIEW The capacity retirement schedule,planned additions,and resulting balance of existing capacity are listed in Table 85-1 along with the peak demand for both the low and medium forecasts.The total required capacity for each reserve margin,the balance of existing capacity,and the resulting requirements for new capacity are listed in Tables 85-2 and 85-3 for the low and medium load forecasts,respectively.The ve~ large reserve margins which exist at present are the result of the isolated nature of the region1s utilities,wherein each small community maintains a reserve capacity of 50-150%or more,and of the transition that the region is going through from small local plants to larger central generating stations.The retirement schedule is controlled by a single input,the operating life of the existi-ng plants~ B5.2SELECTION OF UNIT SIZES The size range of units'selected for the technologies was governed by two items.The first was capital costs.Where there were significant capital cost variance over the size range,the range was restricted to the lower cost end.The second is the range of reserve margins within.. which the Rai1be1t system will operate.Previous studies have used a loss of load probability (LOLP)of one day in ten years as the basis for design (Acres American Inc.1981).The Battelle system evaluation studies initially determined that this LOLP results in a range of reserve margins of 24 to 32 percent (Battelle 1982).For all future system evaluation studies,Battelle utilized an average reserve margin of 30 percent.A1 so,the Battelle report states that the cost of power is nearly constant within this range of reserve margins.This system planning report employs the reserve margin range determined by Battelle (1982).Unit sizes for the two technologies have been evaluated based upon these reserve margins and other factors. 3105A B5-1 TABLE B5-1 EXISTING CAPACITY,PLANNED ADDITIONS,UNIT RETIREMENT SCHEDULE AND PEAK DEMANDS Ex i sting P1anned*Unit**Peak Demand*** Year Capacity Additions Retirements Low Load Medium Load (MW)(MW)(MW)Forecast Forecast 1982 1154.1 158.4 0.3 560 603 1983 1154.1 580 631 1984 1154.1 600 659 1985 1154.1 620 687 1986 1154.1 656 728 1987 1050.1 4.0 692 769 1988 1247.1 97 728 810 1989 1242.1 5.0 764 851 1990 1242.1 800 892 1991 '1223.7 18.4 808 910 1992 1190.0 33.7 816 928 1993 1173.2 16.8 824 947 1994 1142.3 30.9 832 965 1995 1094.8 47.5 840 983 1996 1023.9 70.9 836 1003 1997 927.5 96.4 832 1023 1998 811.7 55.8 828 1044 1999 871.7 824 1064 2000 853.1 18.6 820 1084 2001 852.9 0.2 830 1121 2002 775.1 77.8 840 1158 2003 722.1 53.0 850 1196 2004 722.1 860 1233 2005 609.5 112.6 870 1270 2006 604.3 5.2 896 1323 2007 604.3 922 1377 2008 577.9 26.4 948 1430 2009 577.0 0.9 974 1484 2010 577.0 1000 1537 *Derived from Table 6.3 of Susitna Feasibility Report (Acres American Inc.1981).The 1988 additions consist of Bradley Lake (90 MW)and Grant Lake (7MW).More recent Alaska Power Authority plans envision a Bradley Lake Project with 135 MW of total installed capacity and eliminate the Grant Lake Project (R.W.Beck and Associates 1982). **Derived from Table 6.2 of Susitna Feasibility Report (Acres American Inc.1981). ***Low load forecast derived from summary table (page iv)in Battelle (1982);medium growth forecasts derived from Table 5.7 of Susitna Feasibility Study (Acres American Inc.1981). 3105A B5-2 r~\. [-" .-? r\; [ L L c:L" r r--,-- .--~ [- r [- r- " L- p... L; [, f -~ =_7 C C G [ L C L E A gas turbine of 77 MW capacity (ISO conditions,baseload)was chosen based on minimizing the number of plants and satisfying the new capacity requirements range.Combined cycle unit increments are very suitable to this study with gas turbine units of 50 to 100 MW being available and steam cycles from 40 to 80 MW available for heat recovery.Total combined cycle unit sizes of 220 MW (ISO conditions, baseload)total were selected.This includes two 77 MW gas turbine units and a 66 MW steam turbine unit.This size unit was selected for economY of scale reasons and the fact that it closely matches the required capacity additions. 85.3 NEW CAPACITY REQUIREMENTS The requirements for new capacity and proposed additions are 1isted in Tables 85-4 through 8-9 and are a function of the previously discussed system characteristics and available unit sizes.Units were added as appropriate to maintain the total capacity needed within the required range.Twelve different tabulated scenarios resulted from this -analysis with three locations having two technological and two load forecast possibilities. Possible variation in load growth for the region has been taken into account by performing all analysis for both the low and medium load growth forecasts.This provides a wide range for study since the total hew capacity required in 2010 under the medium forecast is approximately twice that for the low load forecast. The new generating units to be added for each technology under each load growth forecast are shown in Figures 85-1 through 85-12.In applying the technologies,it was demonstrated that simple cycle unit additions most closely followed the targeted total capacity corresponding to the 30 percent reserve margin.Combined cycle systems could be added within the target range,but were less flexible in following capacity addition requirements than simple cycle combustion turbines. 3105A 85-5 [' ['TABLE B5-5 NEW CAPACITY ADDITIONS -LOW LOAD FORECAST [-FAIRBANKS r Actual New Capacity (MW) Required New Capacity Simple Cycle Combi ned Cyc1 e L At Peak Demand (MW)(Increment/(Increment/ Year 24%RSRY 30%RSRY 32%RSRY Total)Total) r 1990 0 0 0 -0/0 0/0 1991 0 0 0 0/0 0/0 ['1992 0 0 0 0/0 0/0 1993 0 0 0 0/0 0/0.-" 1994 0 0 0 0/0 0/0r19950a140/0 0/0l.,; 1996 13 63 80 86/86 86/86r199710415417086/172 86/172L 1998 155 204 221 0/172 0/172 [1999 150 199 216 0/172 0/172 2000 164 213 229 0/172 0/172 C 2001 176 226 243 86/758 70/242 2002 267 317 334 86/344 86/328 C 2003 282 333 350 0/344 0/328 2004 344 396 413 ..86/430 86/414 '- 2005 469 521 538 86/516 70/484 C 2006 507 561 579 0/516 86/570 2007 539 595 613 86/602 0/570 6 2008 598 654 673 0/602 86/656 2009 631 689 709 86/688 0/656 [2010 663 723 743 0/688 70/726 .- L. C.._-~3105A U B5-7 --- L [ TABLE B5-6 CNEWCAPACITYADDITIONS-LOW LOAD FORECAST KENAI [ Actual New Capac i ty (MW)[ Required New Capacity Simple Cycle Combined Cycle At Peak Demand (MW)(Increment/(Increment/,.--~ Year 24%RSRY 3m RSRY 32%RSRY Total)Tota 1)L 1990 0 0 0 0/0 0/0 L19910 0 0 0/0 0/0 1992 0 0 0 0/0 0/0 L19930 0 0 0/0 0/0 1994 0 D 0 0/0 0/0 1995 0 0 14 0/0 0/0 [ 1996 13 63 80 84/84 84/84 1997 104 154 170 84/168 84/168 [ L19981552042210/168 0/168 1999 150 199 216 0/168 0/168 r 2000 164 213 229 0/168 0/168 C 2001 176 226 243 84/252 69/237 [2002 267 317 334 84/336 84/321 2003 282 333 350 0/336 0/321 2004 344 396 413 ..84/420 84/405 ['--:. 2005 469 521 538 84/504 69/474 2006 507 561 579 84/588 84/588 l20075395956130/588 0/588 2008 598 654 673 84/672 84/642 C20096316897090/672 0/672 2010 663 723 743 0/672 69/711 l' L 3105A L B5-8 L [ [ [--TABLE B5-7 NEW CAPACITY ADDITIONS -MEDIUM LOAD FORECAST r-'NORTH SLOPE [Actual New Capacity (MW) Required New Capacity Simple Cycle Combined Cycle r At Peak Demand (MW)(Inc rement/(Increment/ Year 23 RSRY 30%RSRY 32%RSRY Total)Total) ---~ t:-1990 0 0 0 0/0 0/0 1991 0 0 0 0/0 0/0 r 1992 0 16 35 0/0 0/0 1993 1 58 77 91/91 91/91-c n 1994 55 113 132 0/0 0/91 1995 124 .183 203 91/182 91/182I.-J 1996 1220 280 300 91/273 71/253 [1997 341 402 422 91/364 91/344L 1998 423 485 506 91/455 91/435 [1999 447 511 532 0/455 71/506 2000 491 556 578 91/546 91/597 [2001 537 604 627 0/546 0/597 2002 661 730 754 182/728 91/688 C 2003 711 783 807 0/728 71/759 2004 807 881 906 91/819 91/850 L 2005 965 1041 1066 182/1001 162/1012 2006 1037 1116 1142 91/1092 91/1103 2007 1103 1186 1214 91/1183 91/1194 C 2008 1195 1281 1310 91/1274 71/1265 2009 1263 1352 1382 0/1274 91/1356 [2010 1329 1421 1452 91/136~0/1356 .. [ . LL ....--- L 3105A ..--B5-9 [ [ TABLE 85-8 [ NEW CAPACITY ADDITIONS -MEDIUM LOAD FORECAST FAIRBANKS [ Actual New Capacity (MW)t' Required New Capacity Simp1 e Cyc1 e Comb i ned Cyc 1e At Peak Demand (MW)(Increment/(Increment/['Year 24%R5RY 3m R5RY 32%R5RY Total)Tota 1) 1990 0 0 0 0/0 0/0 [' 1991 0 0 0 0/0 0/0 1992 .0 16 35 0/0 0/0 L199315877,86/86 86/86 1994 55 113 132 0/0 0/86 R199512418320386/172 86/172 L..J 1996 1220 280 300 86/258 70/242 1997 341 402 422 86/344 172/414 [' L 1998 423 485 506 86/430 70/484 1999 447 511 532 86/516 0/484 [ 2000 491 556 578 0/516 86/570 2001 537 604 627 86/602 0/570 L200266173075486/688 156/726 2003 711 783 807 86/774 0/726 [2004 807 881 906 86/860 86/812 2005 965 1041 1066 172/1032 156/968 2006 1037 1116 1142 86/1118 86/1050 C 2007 1103 1186 1214 86/1204 86/1140 2008 1195 1281 1310 86/1290 70/1210 L 2009 1263 1352 1382 0/1290 86/1296 2010 1329 1421 1452 86/1376 0/1382 [, L L 3105A C85-10 [ M E G c:o A 'flU ~A T T S 2eee 15ee Ieee see LOU LOAD FORECAST~NORTH SLOPE/SIMPLE CYCLE OPTION ~BALANCE EXISTING CAPACITY ~--------PEAK DEMAND -------RESERVE MARGIN=.24 ------RESERVE MARGIN=.3e 0 _--RESERVE MARGIN=.32 NEU CAPACITY 85 6 7 8 9 ge I 2 3 4 5 6 7 8 9 ee I 23 4 5 6 7 8 9 I e YEAR 1985 THRU 2010 ALAIKA POWER AUTHORITY NORTH .LOPE GAl 'EAI_UTY ITUDY Plot of System Requirements and Capacities for Simple Cycle Technolgy, low load Forecast,with Generating Facilities at the North Slope. ........1 85-1 .BASCO IERVlCEI M:OfIPOAATED r--'""\," ~. J .~ I T S 2000 1500 1000 500 o LO~LOAD FORECAST~FAIRBANKS/SIMPLE CYCLE OPTION ~BALANCE EXISTING CAPACITY ---------PEAK DEMAND -------RESERVE MARGIN=.24 ------RESERVE-MARGIN=.30 0 _--RESERVE MARGIN=.32 NEW CAPACITY 85 6 7 8 9 90 1 2 3 4 5 6 7 8 9 00 1 2 3 4 5 6 7 8 9 10 YEAR 1965 THRU 2010 ALAIKA POWER AUTHORITY NORTH ILOPE GAS nAS.l.fTY lTUDY Plot of System Requirements and Capacities for Simple Cycle Technology. low load Forecast.with Generating Facilities at Fairbanks. '''''''1 B5·2 LO~LOAD FORECAST~KENAI/SIMPLE CYCLE OPTION ...._----. o BALANCE EXISTING CAPACITY PEAK DEMAND RESERVE MARGIN=.24 RESERVE MARGIN=.3e RESERVE MARGIN=.32 NE\oI CAPACITY M E G A \01 OJ A 'f T -"+=-T S 15ee 1eee 5ee 85 6 7 8 9 ge 1 2 3 4 5 6 7 8 9 ee 1 2 3 4 5 6 7 8 9 1e YEAR 1985 THRU 2e1e ALAIKA POWER AUTHORITY NORTH 'LOPE GAil fEAII.lLrrV 'TUDV Plot of System Requirements and Capacities for Simple Cycle Technology, low load Forecast.with Generating Facilities at Kenai. ,teUllI 85-3 I."KO IEAVlCU INCORPORATED r-l r---J i-r-J ,~r:r-l c-J)C"J ~:0'''r--I irrj rTJ ,-.-.-..,,-,~~,r-~..~....:\! \I \" , M E G A \.I A T T S LO\.l LOAD FORECAST~NORTH SLOPE/253 M\.I COMB.CYCLE OPTION ~BALANCE EXISTING CAPACITY 2000 .~~~--~~--PEAK DEMAND -----~.RESERVE MARGIN=.24 ------RESERVE MARGIN=.30 0----RESERVE MARGIN=.32 NE\.I CAPACITY 1500 1000 500 85 6 7 8 9 90 I 2 3 4 5 6 7 8 9 00 1 2 3 4 5 6 7 8 9 I 0 YEAR '985 THRU 2~'0 ALASKA POWER AUTHOR"Y NORTH aLOPE GAl PEAI_ILITY aTUDY Plot of System Requirements and Capacities for Combined Cycle Technology,Low Load Forecast, with Generating Facilities at the North Slope. "'''''185-4 .aAICO ."VICE'1IC000000ATED 2000 . LOW LOAD o FORECAST,FAIRBANKS/242 MW BALANCE EXISTING CAPACITY PEAK DEMAND RESERVE MARGIN=.24 RESERVE MARGIN=.30 RESERVE MARGIN=.32 NEW CAPACITY COMB.CYCLE OPTION M E G A \oJ~AI ~T T S 1500 1000 500 o 85 6 7 8 9 90 1 2 3 4 5 6 7 8 900 1 2 3 4 5 6 7 8 9 10 YEAR 1985 THRU 2010 ALAIKA POWER AUTHORITY NORTH .LOPE ClAS fUSIBILITY ITUDY Plot of System Requirements and .Capacities for Combined Cycle Technology,low load Forecast, with Generating Facilities at FairbankS. '''''''E 85-5 IIASCO aERVICEa INCORPORATED r------\,----., ,l J 2000 LOW LOAD FORECAST,KENAI/237 MW COMB.CYCLE OPTION ~BALANCE EXISTING CAPACITY ---------PEAK DEMAND -------RESERVE MARGIN=.24 ------RESERVE MARGIN=.30-0---RESERVE MARGIN=.32 NEW CAPACITY M E G A W A T T S 1500 1000 500 o 85 6 7 8 9 90 1 2 3 4 5 6 7 8 9 00 1 2 3 4 5 6 7 8 9 10 YEAR 1985 THRU 2010 ALASKA POWER AUTHORITY NORTH ILOPE GAS r:EASIBIUTY STUDY Plot of System Requirements and Capacities for Combined Cycle Technology,low load Forecast, with Generating Facilities at Kenai. ."""1 85-6 RASCO IEfMCES IICORPORATID MEDIUM LOAD FORECAST,NORTH SLOPE/SIMPLE CYCLE OPTION 85 6 7 8 9 90 1 2 3 4 5 6 7 8 9 00 1 2 3 4 5 6 7 8 9 10 YEAR 1985 THRU 2010 M E G A \.I ~A ~T <..OT S 2000 1500. 1000 500 o ~BALANCE EXISTING CAPACITY ---------PEAK DEMAND .------RESERVE MARGIN=.24 ------RESERVE MARGIN=.30 0----RESERVE MARGIN=.32 NEW CAPACITY ,.,.'" .,.,. ,.,. ALAaKA POWER AUTHORITY NORTH .LOPE GAl 'UI....rTY ,nJOY Plot of System Requirements and Capacities for Simple Cycle Technology. Medium load Forecast.with Generating Facilities at the North Slope. 'IIIUflE 85-7 IIAICO IEAVlCElItCOAPOAATED r~r--,r---r---,Ci.------.,-----.,-r ':--0t_"".,..,).),'1 J,Jl )l ]I ;I , MEDIUM LOAD FORECAST,FAIRBANKS/SIMPLE CYCLE OPTION 85 6 7 8 9 90 I 2 3 4 5 6 7 8 9 00 1 2 3 4 5 6 7 8 9 10 M E G A W A T T S 2000 . 1500 1000 500 o ~BALANCE EXISTING CAPACITY ......----PEAK DEMAND .------RESERVE MARGIN=.24 ------RESERVE MARGIN=.30 0----RESERVE MARGIN=.32 NEW CAPACITY .!! YEAR 1985 THRU 2010 ... ...... ALAIKA POWER AUTHORITY NOATH ILOPE GAlS rEAI_ILIlY ITUDY Plot of System Requirements and Capacities for Simple Cycle Technology, Medium load Forecast,with Generating Facilities at Fairbanks • '''''''1 85-8 M E G A W ~A ~T a T S 2000 1500 1000 500 MEDIUM LOAD FORECAST,KENAI/SIMPLE CYCLE OPTION ~BALANCE EXISTING CAPACITY .~~~~~~~-PEAK DEMAND .~---~-RESERVE MARGIN=.24 ------RESERVE MARGIN=.30 D~---RESERVE MARGIN=.32 NEW CAPACITY 85 6 7 8 9 90 1 2 3 4 5 6 7 8 9 00 1 2 3 4 5 6 7 8 9 10 YEAR 1985 THRU 2010 ALAIKA 'OWER AUTHORITY NORTH ILME GAl FEAI_IlI'TY 'TUDY Plot of System Requirements and Capacities for Simple Cycle Technology, Medium Load Forecast,with Generating Facilities at Kenai. ....""E 85-9 IIASCO IEAVlCEI INCOAPOAA TED r--..r---;..cn ;-----"",.~.., ) .c---j;.) ~..; J .:--l.... ,:--r i MEDIUM LOAD FORECAST,NORTH SLOPE/COMBINED CYCLE OPTION ...._------------------------ 85 6 7 8 9 90 I 2 3 4 5 6 7 8 9 00 I 2 3 4 5 6 7 8 9 I 0 YEAR 1985 THRU 2010 18AICO ."VlCES INCOAfIOAATED "'''''185-10 Plot of System Requirements and Capacities for Combined Cycle Technology,Medium load Forecast. with Generating Facilities at the North,Slope. ALAIKA POWER AUTHORITY NORTH ILOPE GAl FEASIBlLfTY lTUDYo 500 1500 1000 ~BALANCE EXISTING CAPACITY 2000 .---------PEAK DEMAND .------RESERVE MARGIN=.24 ------RESERVE MARGIN=.30 0----RESERVE MARGIN=.32 NEW CAPACITY M E G A W A T T S \\ "MEDIUM LOAD FORECAST,FAIRBANKS/COMBINED CYCLE OPTION 85 6 7 8 9 90 1 2 3 4 5 6 7 8 9 00 1 2 3 4 S 6 7 8 9 10 YEAR·198S THRU 2010 2000 M 1500 E G CXJ AU1 I N WNA T ·1000 T S 500 o ~BALANCE EXISTING CAPACITY ---------PEAK DEMAND .------RESERVE MARGIN=.24 ------RESERVE MARGIN=.30 0----RESERVE MARGIN=.32 NEW CAPACITY , ,, ALASKA POWER AUTHORITY NOATH ILOPE ClAI fEAS.IlITY ITUDY Plot of System Requirements and . Capacitities for Combined Cycle Technology,Medium load Forecast, with ~enerating Facilities at Fairbanks. 'HIURE 85-11 flAICO SERVICES 1tCON"ORATED r---.r- l ~. l":J n--J .r-n cn ~ I j --".,) ·~.~r--"'(",~·rJ f- ,r----. r, I .•.'j r--n., 85 6 7 8 9 90 1 2 3 4 5 6 7 8 9 00 1 2 3 4 5 6 7 8 9 10 YEAR 1985 THRU 2010 M E G A W A T T S 2000 1500 1000 500 o .MEDIUM o LOAD FORECAST,KENAI/COMBINED CYCLE OPTION BALANCE EXISTING CAPACITY PEAK DEMAND RESERVE MARGIN=.24 RESERVE MARGIN=.30 RESERVE MARGIN=.32 NEW CAPACITY ,, ALAIKA POWER AUTHORITY NORTH ILOPE GAS FEAS.ll.rTY InJOY Plot of System Requirements and Capacities for Combined Cycle Technology,Medium Load Forecast, .with Generating Facilities at Kenai. '''''''1 85-12 18ASCO IEAVlCES IICOAPORATED A resultant factor of this unit slzlng and staging for each technology is that no two scenarios for new capacity result in the same amount of total energy being supplied.This is also considered in the economic analysis. As will be discussed below,the simple and combined cycles costs are nearly identical for low cost fuels at the North Slope.The simplicity of operation and maintenance,combined with much lower freshwater requirements result then in selection of simple cycle technology for the North Slope scenarios. The combined cycle alternative results in the least cost option for Fairbanks and Kena~and will be applied exclusively to meet the capacity requirements as shown in Tables 85-4 thrqugh 85-9 and Figures 85-1 through 85-12.As previously mentioned,other sizes of combined- cycle plants are available.The alternatives are smaller gas turbines and heat recovery boilers,and a combination of three or more heat recovery boilers with one steam turbine.There are,however,no cost advantages to be gained by either of these choices while a great deal of flexibility is lost.The total number of plants would also increase significantly if smaller plants were used. 85.4 ECONOMIC ANALYSIS AND RESULTS Given the assumptions presented in Section 84.0,and the technologies available,the systems analysis was made by applying the accepted Alaska Power Authority model for calculation of the Present Worth of Costs for the alternative options.All costs were considered for each system;that is,the analysis included capital costs,operating and maintenance costs,and fuel costs.These costs were accounted for in the year they occurred.As a consequence,all capital costs were taken in the year of installation and did not include interest during construction. 3l05A 85-24 [ L~ [ r~t~ [ r [ r -' ~..~ l_~ l-~ L l~ f [~ [~ r r'~ L f'· L.~ PL, c, [ C C [ [ (--- C 1 ...-: C ~-' [ This data when input to the model generated a total cost stream per year for each scenario.This cost stream was then discounted back to 1982 at a rate of 3.0 percent.The discounted values,for each scenario,were summed to achieve the present worth of costs for each scenario.The present worth of costs for each scenario were then used to compare different scenarios.The cost analyses made by employing Alaska Power Authority economic analyses techniques were compared on the basis of total present worth of costs for each scenario. The results of the economic analysis of alternative technologies and load growths are shown in Tables 85-10 through 85-13.These results demonstrate that the combined cycle technology exhibits both the lowest present worth of costs except in cases where natural gas costs were less than $1.50/million 8tu.The results reflect the fact that the combined cycle power plant has the lowest heat rate and a modest installed capital cost,particularly in the size range considered in thi s study. 3105A 85-25 TABLE 05-10 PRESENT WORTH OF COSTS FOR NATURAL GAS FIRED GENERATION AS A FUNCTION OF LOAD GROWTH.LOCATION.TECHNOLOGY.AND FUEL PRICE AT A0 PERCENT,FUEL PRICE ESCALATION (VALUES IN 1982$x 109) FUEL PRICE LOAD GROWTH FORECAST LOCATION TECHNOLOGY o 1.50 ($x 106 Otu) 2.00 2.50 3.50 5.50 Low North Slope Sfmple Cycle 0.360 0.678 0.784 0.890 1.103 1.527 Combfned Cycle 0.420 0.692 0.783 0.874 1.056 1.419 Fafrbanks Sfmple Cycle 0.239 0.568 0.677 0.787 1.006 1.444 Combfned Cycle 0.256 0.517 0.605 0.692 0.866 1.215 Kenaf Sfmple Cycle 0.248 0.577 0.687 0.797 1.017 1.457 Combfned Cycle 0.284 0.542 0.628 0.713 0.885 1.229 Medfum North Slope Sfmple Cycle 0.707 1.370 1.591 1.812 2.255 3.319 Combfned Cycle 0.875 1.387 1.558 1.728 2.069 2.751 Fafrbanks Sfmple Cycle 0.486 1.157 1.381 1.604 2.052 2.946 Combfned Cycle 0.556 1.061 1.229 1.398 1.735 /2.408 Kenaf Sfmple Cycle 0.505 1.184 1.410 1.636 2.088 2.993 Combined Cycle 0.562 1.072 1.242 1.413 1.753 2.433 3105A 05-26 r----"">l 'en r----':'~::-T].: r::-J ··rTl ~ I ~, : I TABLE B5-11 PRESENT WORTH OF COSTS FOR NATURAL GAS FIRED GENERATION AS A FUNCTiON OF LOAD GROWTH.LOCATION.TECHNOLOGY.AND FUEL PRICE AT A1 PERCENT FUEL PRICE ESCALA~ION (VALUES IN 1982$x 109) FUEL PRICE LOAD GROWTH FOIi:CAST LOCATION TECHNOLOGY o 1.50 ($x 106 Btu) 2.00 2.50 3.50 5.50 Low North Slope Simple Cycle 0.360 0.759 0.892 1.026 1.292 1.825 Combined Cycle 0.420 0.761 0.874 0.988 1.125 1.669 Fairbanks Simple Cycle 0.239 0.651 0.789 0.926 1.201 1.751 Combined Cycle 0.256 0.583 0.692 0.801 1.019 1.456 Kenai Simple Cycle 0.248 0.662 0.800 0.938 1•.213 1.765 Combined Cycle 0.284 0.606 0.714 0.821 1.036 1.467 Medium North Slope Simple Cycle 0•.707 1.530 1.805 2.079 2.628 3.726 Combined Cycle 0.875 1.509 1.720 1.932 2.354 3.119 Fairbanks Simple Cycle 0.486 1.319 1.600 1.875 2.430 3.541, Combined Cycle 0.556 1.182 1.390 1.599 2.016 2.851 Kenai Simple Cycle 0.505 1.347 1.628 1.908 2.469 3.592 Combined Cycle 0.562 1.195 1.405 1.616 2.038 2.881 3105A 85-27 TABLE B5-12 PRESENT WORTH OF COSTS FOR NATURAL GAS FIRED GENERATION AS A FUNCTION OF LOAD GROWTH,LOCATION,TECHNOLOGY,AND FUEL PRICE AT A2 PERCENT FUEL PRICE ESCALATION (VALUES IN 1982$x 10 9) FUEL PRICE LOAD GROWTH FORECAST LOCATION TECHNOLOGY o 1.50 ($x 10 6 Btu) 2.00 2.50 3.50 5.50 Low North Slope Simple Cycle 0.360 0.861 1.028 1.195 1.529 2.197 Combined Cycle 0.420 0.846 0.988 1.130 1.413 1.980 Fairbanks Simple Cycle 0.239 0.756 0.928 1.101 1.445 2.135 Combined Cycle 0.256 0.665 0.801 0.938 1.210 1.756 Kenai Simple Cycle 0.248 0.767 0.940 1.113 1.459 2.151 Combined Cycle 0.284 0.687 0.822 0.956 1.225 1.763 Medium North Slope Simple Cycle 0.707 1.748 2.088 2.429 3.110 4.472 ComM ned Cyc Ie 0.875 1.660 1.922 2.184 2.707 3.753 Fairbanks Simple Cycle 0.486 1.520 1.865 2.210 2.899 4.278 Combined Cyc1 e 0.556 1.331 1.590 1.848 2.365 3.399 Kenai Simple Cycl e 0.505 1.549 1.897 2.245 2.942 4.334 Combined Cycle 0.562 1.346 1.607 1.869 2.391 3.436 3105A B5-28. I~,--"]"'~- r-J TABLE B5-13 PRESENT9 WORTH OF COSTS FOR NATURAL GAS FIRED GENERATION AS A FUNCTION OF LOAD GROWTH.LOCATION.TECHNOlOGY.AND FUEL PRICE AT A3 PERCENT FUEL PRICE ESCALATION (VALUES IN 1982$x 10 9) FUEL PRICE LOAD GROWTH FORECAST LOCATION TECHNOLOGY o 1.50 ($X 10 6 Btu) 2.00 2.50 3.50 5.50 Low North Slope Simple Cycle 0.360 0.988 1.197 1.406 1.825 2.662 Combined Cycle 0.420 0.952 1.129 1.306 1.661 2.369 Fairbanks Simple Cycle 0.239 0.887 1.103 1.318 1.750 2.614 Combined Cycle 0.256 0.767 0.937 1.108 1.448 2.130 Kenai Simple Cycle 0.248 0.898 1.115 1.332 1.766 2.633 Co)nbi ned Cyc 1e 0.284 0.788 0.956 1.124 1.460 2.132 Medium North Slope Simple Cycle 0.707 1.994 2.416 2.838 3.683 5.373 Combined Cycle 0.875 1.847 2.171 2.495 3.143 4.439 Fairbanks Simple Cycle 0.486 1.769 2.197 2.625 3.480 5.191 i Combined Cycle 0.556 1.516 1.836 2.157 2.797 4.077 Kenai Simple Cycle 0.505 1.800 2.232 2.663 3.527 .5.253 Combined Cycle 0.562 1.533 1.857 2.181 2.828 4.123 3105A B5-29 r L [ L C b C [ , [ L i L L~ 86.0 CONCLUSIONS AND RECOMMENDATIONS 86.1 ECONOMIC CONCLUSION The economic data as portrayed in Tables 85-10 through 85-13,and particularly those in 85-12 (2%fuel price escalation rate)clearly illustrate that for fuel costs greater than about $1.50/106 8tu for both medium and low growth forecasts at all three locations,the combined cycle technology has a clear economic edge,but less so at the North Slope.Combined cycle is capital cost effective,and has a slightly lower operating and maintenance factor than the simple cycle option.It has the highest thenma1 efficiency of any of the technologies considered.For these reasons,there is ample justification for selecting the combined cycle technology as the method for future power generation,should natural gas be available in the quantities required.Higher fuel costs favor this technology even more. 86.2 TECHNICAL CONCLUSION There are several technical factors favoring the selection of the combined cycle option:a 220 MW plant (ISO conditions,baseload) consisting of two 77 MW independently operated gas turbines and one 66 MW steam turbine generator offers virtually the same flexibility in construction,timing,operation,and maintenance that the simple cycle gas turbine offers;at the same time it achieves a heat rate far better than the simple cycle units. At the North Slope location,for the range of fuel costs expected ($1.00 to $2.00/106 8tu),the combined cycle option enjoys a very slight margin in present worth costs versus simple cycle units. However,to be weighed against this are the added complexities of operating boilers on the North Slope with attendant water supply,water treatment,water chemistry control and other more specialized maintenance requirements of the higher temperature steam cycles.In addition,spare parts reqUirements increase due to the addition of the steam turbine cycle and attendant waste heat boilers,duct work, dampers,and other equipment. 3105A 86-1 Thus,for the North Slope,the technical advantages of the simple cycle unit outweigh the slight economic edge of the combined cycle.At Fairbanks and Kenai,the advantages of the combined cycle unit,where fuel prices are higher,clearly show combined cycle units being favored,especially since operation of these units is more favorable due to the availability of trained operators familiar with similar units and fossil fired boilers and steam turbines.In addition,the standard construction methods used in these areas more readily lend themselves to combined cycle plants,whereas the North Slope requires modular or non-standard methods. 86.3 RECOMMENDATION Since both th~technical evaluation anq economic analysis favor use of combined cycle plants for utilizjng North Slope gas to generate electricity,this technology is recommended for the Fairbanks and Kenai locations.For the North Slope,the range of fuel costs anticipated do not outweigh the additional complexities of construction and operation of the combined cycle unit,and the use of simple cycle units is recommended. As discussed previously,simple cycle plants are considered optimum at the North Slope for reasons of operation flexibility and cost.The low load forecast results in eight 77 MW (ISO conditions)simple cycle units at the the North Slope site,for the medium load forecast this would be fifteen units,as shown in Tables 85-4 and 85-7. For Fairbanks and Kenai,for low load forecast,three 220 MW (ISO conditions)combined cycle systems would be installed for the low load forecast and 5 2/3 combined cycle systems for the medium load forecast by the year 2010,as shown in Tables 85-5, 85-6,85-8 and 85-9. 3105A 86-2 [ l [ .[' [ l [ F L [ [ [ t' -, L [ [ l [ [ F' [. [..•.. ....., [ [ I.~· --L. C· Eii.,. [ [, o c c [ B c [ Ll_ [ [ B7.0 REFERENCES Acres American,Inc.1981.Susitna Hydroelectric Project - Feasibility Report -Volume I,Engineering and Economic Aspects, Final Draft.Alaska Power Authority.Anchorage,Alaska. Battelle Pacific Northwest Laboratories.1982.Railbelt Electric Power Alternatives Study:Evaluation of Railbelt Electric Energy Plans -Comment Draft.Office of the Governor,State of Alaska. Juneau,Al aska (February 1982). Battelle Pacific Northwest Laboratories.1981.Railbelt Electric Power Alternatives Study -Comment Draft Working Paper 3.1 - candidate Electric Energy Technologies for Future Application in... the Alaska Railbelt Region.Office of the Governor,State of Alaska.Juneau,Alaska. Edison Electric Institute.1981.Combustion Turbine Operational Practices Guidebook.EPRJ Operating Development Group.Edison Electric Institute.Washington,D.C. R.W.Beck and Associates,Inc.1982.Kenai Peninsula Power Supply and Transmission Study.Alaska Power Authority.Anchorage,Alaska (June 1982). 3105A 87-1 NORTH SLOPE GAS FEASIBILITY STUDY SYSTEM PLANNING REPORT ADDENDUM 1 Supplemental infonmation for the economic analysis is contained in two sets of.tables included in this addendum.Each set contains 12 separate tables.The first set shows energy requirements and gas requirements for each of the twelve scenarios in each year of the study period.The second set of tables is a summary of generation and economic data input to the model for analysis of each scenario in each year. ENERGY USE AND GAS REQUIREMENTS TABLES This set of tables utilizes the low and medium load forecasts and the energy available from nYdro sources to detenmine the net energy required from thenmal sources.The energy available from the new plants utiliZing North Slope gas is then calculated.It is then assumed that use of the new gas units will be preferenti aland actual utilization of those plants is listed based on their supplying as much as possible (up to a capacity factor of 0.75)of the net reqUired.The last column then lists millions of cubic feet of North Slope gas· required to generate the energy utilized. There are twelve tables,six for each load forecast,within those six, three for each technology,for the two technologies.All tables cover every year of the study period.The North Slope locale tables assume utilization of untreated gas at 1046 Btu/ft3 (HHV).The Fairbanks scenario assume treated gas at 1104 Btu/ft3 (HHV)and the Kenai assumes utilization of a gas treatment plant waste stream of up to 200 x 10 6 ft3/day at 195 Btu/ft3 (HHV).For the waste stream utilization blending with sales gas to acheive a usable gas of 400 Btu/ft3 (HHV)is .assumed.This allows purchase of turbines with no modification from those burning pure sales gas. 2573B 1 ELECTRICITY PRODUCED,COSTS AND HEAT RATES The four data items listed in this table,electricity produced in gigawatt hour,capital expenditure,operating and maintenance (0 &M) expenditures and system heat rates,all for each year operation,are the inputs for economic analysis generated by engineering.design and estimating. The project year is listed to indicate the discount period for each cost item.The electricity produced combined with annual heat rates and fuel prices yield annual fuel costs. 25738 2 r=L L [ [ L L [ r' C-J [ l L r-~ >• lh-"NORTH SLOPE GAS FEASIBILITY STUDY SYSTEM PLANNING REPORT -ADDENDUM 1 TABLE 3 ('-'TOTAL ENERGY USE AND GAS REQUIREMENTSL:~ LOW LOAD FORECAST,SIMPLE CYCLE GENERATION ['. KENAI LOCALE [.- LOAD -HYDRO NET AVAILABLE UTILIZED GAS~EQ~DYEARGWHGWHGWHNSG-GWH NSG-GWH FT 10[f WASTE GAS SALES GAS ('1980 2550 254 2296 t 81 2646 254 2392 82 2742 254 2488 83 2838 254 2584r8429342542680 "-85 3030 254 2776 86 3194 254 2940 C 87 3358 254 3104 l~88 3522 648 2874 89 3686 648 3038 C 90 3850 648 3202 91 3892 648 3244 92 3934 648 3286 fJ 93 3976 648 3328 94 4018 648 3370 95 4060 648 3412 96 4046 648 3398 553 553 12,474.2 3,631.9 C 97 4032 648 3384 1104 1104 24,903.3 7,250.7 98 4018 648 3370 1104 1104 24,903.3 7,250.7 99 4004 648 3356 1104 1104 24,90'3.3 7,250.7 C 2000 3990 648 3342 1107 1107 24,970.9 7,270.4 01 4048 648 3400 1656 1656 37,354.9 10,876.1 02 4106 648 3458 2208 2208 49,806.5 14,501.5 G 03 4164 648 3516 2208 2208 49,806.5 14,501.5 04 4222 648 3574 2767 2767 62,416.1 18,172.8 05 4280 648 3632 3311 3311 74,687.3 21,745.6,.06 4412 648 3764 3863 3764 84,905.7 24,720.8 C 07 4544 648 3896 3863 3863 87,138.9 25,371.0 08 4676 648 4028 4427 4028 90,860.9 26,454.6," 09 3808 648 4160 4415 4160 93,838.4 27,321.8 L 10 4940 648 4292 4415 4292 96,816.0 28,188.5 ,. [ I,e 2573B .--"..,5 C [ ~NORTH SLOPE GAS FEASIBILITY STUDY [SYSTEM PLANNING REPORT -ADDENDUM 1 TABLE 13 ~. [LOADS,COSTS AND HEAT RATES LOW LOAD FORECAST,SIMPLE CYCLE GENERATION C.NORTH SLOPE LOCALE C ELECTRICITY CAPITAL O&M PROJECT PRODUCED EXPENDI~URE EXPENDITURE HEAT RATE [YEAR YEAR (GWH)($x10 )($x 106 )(BTU/KWH) [1980 81 0 82 1 83 [,.2 84 J.3 85 4 86 r=5 87 L 6 88 7 89 ['8 90 9 91 /--10 92 11 93 C 12 94 13 95 72.63 14 96 ,600 53.56 3.780 11 ,500 0 15 97 1,1~6 -0-7.535 11 ,500 16 98 1,196 -0-7.535 11 ,500 17 99 1,196 -0-7.535 11 ,500 C 18 2000 1,196 -0-7.535 11 ,500 19 01 1,196 53.56 7.535 11 ,500 20 02 1,794 53.56 11.302 11,500 G 21 03 2,391 -0-15.063 11 ,500 22 04 2,398 107.12 15.107 11,500 23 05 3,587 -0-22.598 11 ,500'.24 06 3,587 -0-22.598 11 ,500 C 25 07 3,587 53.56 22.598 11 ,500 26 08 4,028 -0-25.376 11,500 27 09 4,160 53.56 26.208 11 ,500 [j 28 10 4,292 -0-27.040 11 ,500 ., L.- ~- L 2573B .-15 t r NORTH SLOPE GAS FEASIBILITY STUDY [SYSTEM PLANNING REPORT -ADDENDUM 1 TABLE 16 LOADS,COSTS AND HEAT RATES r LOW LOAD FORECAST,COMBINED CYCLE GENERATION NORTH SLOPE LOCALE [ [' ELECTRICITY CAPITAL O&M PROJECT PRODUCED EXPENDI~URE EXPENDI~URE HEAT RATE YEAR YEAR (GWH)($x10 )($x10 )(BTU/KWH)[' " 1980 ['81 0 82 1 83 2 84 R385L_": 4 86 5 87 E688 7 89 8 90 [9 91 10 92 11 93 12 94 [13 95 91.70 14 96 600 ·53.56 3.300 11 ,500 15 97 1,196 -0-6.578 11 ,500 C16981,196 -0-6.578 11 ,500 17 99 1,196 -0-6.578 11,500 18 2000 1,196 95.31 6.578 11 ,500 r19011,662 53.56 9.141 8,320 ,~20 02 2,260 -0-12.430 9,161 21 03 2,260 53.36 12.430 9,161 2'2 04 2,866 111.70 15.763 9,650 ['23 05 3,324 53.36 18.282 8,320 ~_c ; 24 06 3,764 -0-20.702 8,805 25 07 3,896 53.56 21.428 8,305 [26 08 4,028 -0-22.154 9.16t 27 09 4,160 -0-22.880 9,161 28 10 4,292 -0-23.606 9,161 [ L 2573B L18 .[ [ NORTH SLOPE GAS FEASIBILITY STUDY ['SYSTEM PLANNING REPORT -ADDENDUM 1 TABLE 18 LOADS,COSTS AND HEAT RATES [ LOW LOAD FORECAST,COMBINED CYCLE GENERATION KENAI LOCALE [ ['ELECTRICITY CAPITAL O&M PROJECT PRODUCED EXPENDIlURE EXPENDITURE HEAT RATE YEAR YEAR (GWH)($x10 )($x 106 )(BTU/KWH)[ 1980 L81 0 821·83 2 84 R385L'4 86 5 87 [6 88 7 89 8 90 9 91 C1092 11 93 12 94 [;13 95 46.28 14 96 553 35.98 2.212 11 ,650 15 97 1,104 -0-4.416 11 ,650 [16 98 1,104 -0-4.416 11 ,650 17 99 1,104 -0-4.416 11 ,650 18 2000 1,104 53.65 4.416 11 ,650 19 01 1,557 35.68 6.228 8,280 t20022',109 -0-8.436 9,162 21 03 2,109 35.68 8.436 9,162 22 04 2,668 56.70 10.672 9,678 ~23 05 3,114 35.68 12.456 8,280 24 06 3,666 -0-14.664 8,787 25 07 .3,666 35.68 14.664 8,787 [26 08 4,028 -0-16.112 9,162 27 09 4,160 56.70 16.640 9,162 28 10 4,292 -0-17.168 8,280 [ l_ 25738 [ 20 L [ NORTH SLOPE GAS FEASIBILITY STUDY [SYSTEM PLANNING REPORT -ADDENDUM 1 TABLE 22 [LOADS,COSTS AND HEAT RATES MEDIUM LOAD FORECAST,COMBINED CYCLE GENERATION (' NORTH SLOPE LOCALE t [ ELECTRI CITY CAPITAL O&M PROJECT PRODUCED EXPENDITURE EXPENDITURE HEAT RATE r~YEAR YEAR (GWH)($x 106 )($x 106 )(BTU/KWH) 1980 [~81 0 82 1 83 r284 3 85 ~-' 4 86 5 87 [ 6 88 L 7 89 8 90 [9 91 10 92 91.76 11 93 598 -0-3.289 11 ,500 [12 94 598 53.56 3.289 11 ,500 13 95 1,196 95.31 6.578 11 ,500 -, 14 96 1,667 53.56 9.169 8,320 15 97 2,260 53.56 12,340 9,161 [16 98 2,858 111.70 15.719 9,650 17 99 3,324 53.56 18.282 8,320 18 2000 3,933 -0-21.632 8,805 e19013,922 53.56 21.571 8,805 20 02 4,520 111.70 24.860 9,161 21 03 4,987 53.56 27.429 8,320 L22045,588 165.26 30.734 8,660 23 05 5,780 53.56 31.790 8,320 24 06 6,053 53.56 33.292 8,582 25 07 6,325 111.70 34.788 8,805 [26 08 6,598 53.56 36.289 8,320 27 09 6,870 -0-37.785 8,533 28 10 7,143 -0-39.287 8,533 [ L 2573B L 24 L, [ ~NORTH SLOPE GAS FEASIBILITY STUDY ['SYSTEM PLANNING REPORT -ADDENDUM 1 TABLE 23r:"(-'.LOADS,COSTS AND HEAT RATEStoMEDIUMLOADFORECAST,COMBINED CYCLE GENERATION ~.---. FAIRBANKS LOCALEr', ,-.- [ELECTRICITY CAPITAL O&M PROJECT PRODUCED EXPENDI~URE EXPENDI~URE HEAT RATE r'---YEAR YEAR (GWH)($xl0 )($xl0)(BTU/KWH)f', C" 1980 81 ..;0 82 1 83 C~2 84 3 85 '4 86 C 5 87 6 88u789 [''" 8 90 9 91 ~;J 10 92 43.86 11 93 565 -0-2.260 11,600 [12 94 565 33.90 2.260 11,600 13 95 1,130 56.97 4.520 11 ,600 14 96 1,594 67.80 6,376 8,290 C 15 97 2,720 59.63 10.880 9,665 16 98 3,180 -0-12.720 8,290 17 99 3,180 33.90 12.720 8,290 E 18 2000 3,755 -0-15.020 8,789 19 0]3,745 93.53 14.980 8,789 20 02 4,770 -0-19.080 8,290 21 03 4,770 33.90 19.080 8,290 ~22 04 5,349 93.53 21.396 8,641 23 05 5,780 33.90 23.120 8,290 24 06 6,053 33.90 24.212 8,560 C 25 07 6,325 59.63 25.300 8,789 26 08 6,598 33.90 26.392 8,290 27 09 6,870 33.90 27.480 8,510 [28 10 7,143 -0-28.572 8,702 [ L 2573B 25 L' [ NORTH SLOPE GAS FEASIBILITY STUDY [SYSTEM PLANNING REPORT -ADDENDUM 1 TABLE 24 LOADS,COSTS AND HEAT RAT~S [ MEDIUM LOAD FORECAST,COMBINED CYCLE GENERATION KENAI LOCALE L [ELECTRICITY CAPITAL O&M PROJECT PRODUCED EXPENDI~URE EXPENDI~URE HEAT RATE YEAR YEAR (GWH)(Sx 10 )(Sx 10 )(BTU/KWH)[~ 1980 L81 0 82 . 1 83 2 84 8385 4 86 5 87 C688 7 89 t~. 8 90 C991 10 92 46.28 11 93 552 -0-2.208 11 ,650 12 94 552 35.68 2.208 11,650 L13951,104 53.65 4.415 11 ,650 14 96 1,561 71.36 6.244 8,280 15 97 2,661 56.70 10.644 9,678 C16983,114 -0-12.456 8,280 17 99 3,114 35.68 12.456 8,280 18 2000 3,676 -0-14.704 8,787 e19013,666 92.38 14.664 8,787 20 02 4,671 35.68 18.684 8,280 21 03 5,223 35.68 20.892 8,636 22 04 5,588 92.38 22.352 8,924 O[ 23 05 5,780 35.68 23,120 8,554 :=..;J 24 06 6,053 -0-24.212 8,787 25 07 6,325 56.70 25.300 8,787 C26086,598 35.68 26.392 8,280 27 09 6,870 35.68 27.480 8,503 28 10 7,143 -0-28.572 8,&98 [, [ 2573B r~ 26 U L I I I I I I I I I I I I,- I, I I I_ I :- oo APPENDIX C [ T--- [' r c: [~. -j c: [ nL.> r L C b C C ~ [ L l L ,--- [ APPENDIX C REPORT ON FACILITY SITING AND CORRIDOR SELECTION EBASCO SERVICES,INCORPORATED JAtmARY 1983 Page C1-1 C1-1 C1-1 C1-1 Cl-2 Cl-5 C3-1 C3-1 C3-3 C3-4 C3-9 C3-10 C3-11 C3-25 C4-1 C4-1 C4-1 C4-3 C4-8 C4-10 C4-11 C4-11 C4-13 C4-15 C4-16 ·. . · . . · . . ·. . .... ..... . .. .... . .... . TABLE OF CONTENTS C3.2.1 Prudhoe Bay-Fairbanks •••••• C3.2.2 Fairbanks-Anchorage •••••• C3.1.1 Description of Region •••••• C3.1.2 Siting Considerations ••••• C3.1.3 Generic Site Description •••• I NTROD UCT ION • • • • • • • • • • • • • • • • • • C4.2.1 Routing Considerations •••••• C4.2.2·Applicability of the ANGTS Route. C4.3 GAS DISTRIBUTION SYSTEM FOR FAIRBANKS • • • • C4.4 TRANSMISSION FACILITY ROUTING EVALUATION C4.2 GAS PIPELINE ROUTING EVALUATIONS C4.1.1 Description of the Region •••• C4.1.2 Siting Considerations •••••• C4.1.3 Candidate Siting Areas ••••••••••• C4.1.4.Generic Site Description •• C3.2 TRANSMISSION FACILITY ROUTING EVALUATIONS • • C2.1 OBJECTIVES •• C2.2 SITING FACTORS 26058 C4.0 SCENARIO II -FAIRBANKS POWER GENERATION. C4.1 GENERATING FACILITY SITE EVALUATIONS •• CLO C2.3 IDENTIFICATION AND EVALUATION OF CANDIDATE AREAS • C2.4 DEVELOPMENT OF GENERIC SITE AND ROUTE DESCRIPTIONS. C3.0 SCENARIO I -NORTH SLOPE POWER GENERATION C3.1 GENERATING FACILITY SITE EVALUATIONS C2.0 FACILITY SITING AND CORRIDOR SELECTION PROCESS. [ b [ [ C C [ C L " L C·I [ r-, c [ [ L L n L C5.2 TRANSMISSION FACILITY ROUTING EVALUATIONS . C5.1 GENERATING FACILITY SITE EVALUATIONS •• C5.2.1 Kenai-Anchorage Corridor •.•. C5.2.2 Anchorage-Fa'irbanks Corri dor .•• C5.0 SCENARIO III -KENAI POWER GENERATION .•• ~r r' r r' r~ f l 'Fl___ Page C5-1 C5-1 C5-1 C5-3 C5-5 C5-6 C5-7 C5-11 C6-1 ..... .. ..... .. ·. . ... ·. . ... · . . ... ·..... TABLE OF CONTENTS • • • • • • • • • • • • •0 • • C5.1.1 Description of the Region ••• C5.1.2 Siting Conditions ••..••• C5.1.3 Generic Site Description .•.• C6.0 REFERENCES. iii [ C [, [ _J 'C I [' ..1 L ,I L ~-j L_J "[ [ i~-\ (.":? i C C l" r. " -".... n-" u~ C L C [.~/ .~' [ 1 __ [ L L [. Table Number C3-l Fi gure Number C3-l C4-l C5-l LIST OF TABLES Title State of Alaska Temporal and Spatial Protection Criteria for Nesting Raptors LIST OF FIGURES Title Scenario I -North Slope Power Generation Scenario II -Fairbanks Power Generation SCenario III -Kenai Power Generation iv C3-20 C3-2 C4-2 C5-2 [ [ r-·· [ [ L c: [' nL~ r L c ~ [ C [j, \ [, l_ C, L L \ [ Cl.O INTRODUCTION The North Slope gas feasibility level assessment will result in a series of four reports.This report on facility siting and corridor selection is the third of that series.The complete series of reports is as follows: 1.Report on Existing Data and Ass~mptions 2.Report on System Planning Studies 3.Report on Facility Siting and Corridor Selection 4.Feasibility Assessment Report (draft and final) This overall study is focused on three alternative development scenarios for power generation and gas and electrical transportation systems to move the energy from its source to points of consumption: o Electrical generation at the North Slope,with electrical transmission to Fairbanks via a new transmission line,and on to Anchorage via an upgraded Anchorage-Fairbanks Intertie; o Transport of North Slope natural gas via a small diameter pipeline to Fairbanks,with electrical generation at Fairbanks and simi,lar upgrading of the In~ertie for transmission to Anchorage; o Electrical generation at the terminus of a high-pressure natural gas pipeline to tidewater (Kenai-Nikiski area of the Kenai Peninsula),fueled by a waste component of the gas stream,with necessary electrical transmission to Anchorage and Fairbanks. These are hereafter referred to as Scenario I:North Slope Power Generation;Scenario II:Fairbanks Power Generation;and Scenario III: Kenai Power Generation,respectively.- 26058 Cl-l Following this introductory chapter,Chapter.C2 details the siting process used in this study.Chapters C3,C4,and C5 provide complete siting descriptions for each respective scenario.Maps of the scenarios are provided in each of those chapters. 26058 Cl-2 (. [ r~ ~, L'r: C. c" [- r- L C2.0 FACILITY SITING AND CORRIDOR SELECTION PROCESS C2.l OBJECTIVES Prelimina~siting of the facilities included within each development scenario was accomplished at a level of detail cOlll11ensur~te with the conCeptual design requirements of this feasibility level assessment.The objective of this stuqy component is to provide a realistic p~sical setting for engineering,economic and environmental evaluations of the. power generating,gas transport,and electric transmission facilities included within each of the three scenarios under consideration,rather than to identify specific sites or routes.The siting process has emphasized those considerations most critical to facility cost.In addition,siting opportunities and/or constraints associated with each of the candidate areas and corridors are identified. The general areas considered for siting the generating facilities and routing the gas transportation and transmission facilities are identified in Section C2.3 below.These areas were used to develop generic site and route descriptions for each scenario.It is expected that further planning studies will be required in order to select actual sites and preci se routes. C2.2 SITING FACTORS Because the objectives of this study are oriented to the requirements of conceptual engineering and cost estimating,and not toward the selection of specific sites or rights-of-way,the siting factors developed for the study's purposes are limited in number and are broad in scope. Establishment of suitable factors was an interactive process in which siting considerations important to each scenario/region were identified by the stuqy participants,in parallel with the development of prelimina~infonnation regarding unit sizing and generation/transmission concepts.For example,based on the region's climatic extremes,it was evident early in ·the stuqy process that the stuqy would focus on 2605B C2-l air-cooled (dry)condenser systems for combined-cycle plants. Therefore,unlike ,most traditional power plant siting studies,the availability of sUbstantial volumes of water for condensercoolfng purposes would not be a significant siting criterion. For each scenario (as discussed in succeeding chapters),relevant factors were developed for land status and use,geotechnical,engineering and environmental considerations.In general,the considerations were developed to ensure that 1)significant site-related factors were not overlooked in each scenario,2)descriptions of the pnYsical settings for further evaluations of the generating and transmission facilities would be focused on factors which are significant engineering and/or cost Concerns and 3)"fatal-flaw"environmental constraints would not prohibit development. C2.3 IDENTIfICATION AND EVALUATION OF CANDIDATE AREAS The regions encompassed by each generation scenario are large and can pose significant constraints to industrial development.It was necessary to substantially narrow the geographic focus of the siting activities early in the study process,so that study resources could be allocated to the development of a realistic pnYsical setting for the sUbsequent assessments,rather than to a search for specific sites or routes which offer the greatest development potentia).The following paragraphs describe the basis for this "narrowing of focus,"first for the generating facilities siting evaluations,and then for the transmission and pipeline corridor delineations. The potential siting area for a generating facility for Scenario I - North Slope Power Generation -encompasses a vast region from the Beaufort sea to the foothills of the Brooks Range.Primarily because of the existing support infrastructure,including road and electrical transmission systems and centralized waste treatment facilities,the generating site evaluation was confined to locations reasonably close to the Prudhoe Bay/Deadhorse development complex.Close proximity minimizes 2605B C2-2 f' r', -r l~ r- -f C -r-=L _ --r [ ,-j-' [ [ ,[- .._.., J ~'.~ l~ L _.i -[ ,_I L~-,:\ [' rJ cr:J l:'!'""]CJ r:r-:J cr::o cr:TID L"J]DID CJ C~C::JJ c-J ~~r-:r-J :':";':1 et~·"ti~t....·,,~·I...."..'~'....~._...•.~.r',!.4'"'...~1 I;'I ..',.....",...fj . ~."'t ..J POWER PLANT SITING AREA TRANSMISSION LINE CORRIDOR NATURAL GAS PIPELINE CORRIDOR .,. "l I tv \ s, ",·j'roIO \ \. \ \ \ \ \ " \ \ ,,,,,,, \ \-\~r!jC'oe\\ 'i60':l"'l~tl.' FIGURE C 3-1 StENARIO I ALASKA POWER AUTHORITY EBASCO SERVICES INCORPORATED NORTH SLOPE POWER GENERATION NORTH SLOPE GAS FEASIBILITY STUDY I 1 I I r~' l' I I I u/1"IiE-J o --- IC.l'l.'~"t [ r r [ [ [ [ F L> r L c o C b G C Ll L L [ haul distances from the existing barge unloading facilities.and minimizes new road construction.The Prudhoe Bay area is relatively unifonn with respect to the occurrence of permafrost.small surface lakes.topographY.and climate.ACtual site selection would consider the following factors:1)minimizing interferences with ~isting land uses and facili~ies such as the pipelines comprising ,the gathering system; 2)optimizing the use of the supporting infrastructure.particularly roads;and 3)avoiding locations of significant environmental value.such as snow goose nesti ng areas.For these reasons.a generic site description encompassing significant factors likely to be encountered in' most specific locations within the Prudhoe Bay area was developed. Scenario II -Fairbanks Power Generation -is the most complex from a siting perspective with topograpic.land use.and air quality/ meteorologic conditions exhibiting significant variation within the area~This variation makes it difficult to define a homogeneous siting area.For purposes of this stuqy.prelimina~evaluations considered an approximate 50~ile radius centered on Fairbanks.Fairbanks is located at the northern edge of the broad Tanana River Valley.Extensive low, flat areas occur to the south and east,While the terrain rises significantly just to the north and west of the city.Most of the area south and east of Fairbanks is occupied by military reservations (Ft.Wainwright and Eielson Air Foree Base);these designated land uses have concentrated some industrial expansion from the city into a narrow corridor along the Richardson Highway,particularly at or near the. community of North Pole.This area would be potentially suitable for the generating facility site.Industrial development north and west of Fairbanks is limited by the steepening terrain and by federal land holdings.The southern boundary of the White Mountains National Recreation Area is about 25 miles north of Fairbanks.Suitable topographY and access indicates that industrial development could be accommodated to the southwest,toward Nenana,but that is in the opposite directi on from the TAPS Corri dor.which passes to the east of Fai rbanks. For'these reasons.the geographic focus of this stuqy was narrowed to include Fairbanks itself and nearby areas suggested by local utility 2605B C2-3 representatives.Specific candidate siting areas are discussed in Chapter C4,along with a discussion of the climatic peculiarities of the Fairbanks area which may influence the siting of new generating facilities.The generic site description developed for Scenario II is based on conditions likely to be encountered within a short distance (10-15 miles)southeast of Fairbanks.This is not to imply that generating facilities could not be sited elsewhere in the Fairbanks region,but rather to provide a reasonable and realistic basis for the subsequent engineering investigations. Scenario III -Kenai Area Power Generation -encompasses a much smaller area than the previous scenarios.This area is the assumed terminus of an all-Alaska large diameter natural gas pipeline.The communities of Kenai,Sa1amatof and Nikiski comprise a linear residential,commercial, and industrial development area,linked together by the North Kenai Road, along the west side of the Kenai Peninsula.The area occupies a relatively narrow strip between the Kenai National Wildlife Refuge and Cook Inlet.Within this well-defined area,p~sica1 and environmental characteristics are relatively uniform.The area is relatively flat, varying from 100 to about 150 feet in elevation,with spruce bogs and small lakes predominating.The principal siting consideration is the existing industrial infrastructure,which consists of petrochemical refineries and supporting facilities,a gas-fired generating station and transmission system operated by Chugach Electric Association,and one major road.For this scenario,a "narrowing of focus "was·not necessary for development of a generic site description. The geographic focus of the transmission corridor evaluations under each scenario was determined by the existence of established utility corridors or routes.The established Utility Corridor was used as the basis of the gas pipeline and electric transmission routing evaluations between Prudhoe Bay and Fairbanks.The Utility Corridor is defined by the Bureau of Land Management (BLM 1980)as a strip of land 336 miles in length from Washington Creek (28 miles north of Fairbanks)to Sagwon B1 uffs (60 miles south of Prudhoe Bay).It varies in width from 12 to 24 miles and 2605B C2-4 I \ L r~ l [ r l. '[ L --- [' C' [ [ [ [ l~ F L----" contains about 3.6 million acres.The Corridor was withdrawn and designated as a utility and transportation corridor by Public Land Order 5150 in 1971.For the purposes of.this stu~,the Utility Corridor (and extensions to Prudhoe Bay and Fairbanks at either end)was divided into seven segments,each exhibiting relatively uniform characteristics for pipeline and transmission line routing. Electric transmission between Fairbanks and Anchorage was assumed to involve three geographic segments: o the Anchorage-Fairbanks Intertie,now under construction between Willow and Healy; o existing Golden Valley Electric Association transmission rights-of-way between Healy and Fairbanks;and o existing Chugach Electric Association transmission rights-of-way between Willow and Anchorage. [ [J [. C C· , [ L L, L .~..-. L The routi ng eval uati ons focused on upgrade requirements in each segment rather than on alternative routes.Electric transmission between Kenai and Anchorage was likewise assumed to be via the existing Chugach Electric Association rights-of-way;these would also require substantial upgrading and possibl ere-routing in selected areas.One such area i ~ the right-of-way alongside the highway which traverses the north shoreline of Turnagain Arm.The ve~limited area available between the shoreline and steep cliff in thi s segment milY preclude upgradi ng the existing transmission line.Routing alternatives to avoid this severe constraint include a submarine cable crossing Turnagain Arm.These alternatives are discussed in greater detail in Chapter C5. C2.4 DEVELOPMENT OF GENERIC SITE AND ROUTE DESCRIPTIONS The methods described above were used to develop generic site and route descriptions upon which the subsequent feasibility assessments are 26058 C2-5 based.For each generation and transmission scenario,a generalized site and corridor description was developed by the study team.Important parameters included access (in relation to the overall area),size and surface characteristics,water resources,soils and foundations,and environmental conditions. .Gas transportation and electric transmission facility routes are described on the basis of relatively homogeneous spatial segments,such as the Arctic Coastal Plain.Significant routing considerations specific to individual segments are given special attention in the generic route descri pti ons. 26058 C2-6 T' T' f C T l E r~: L~ i L } t~_J "l .-1 L J r r [ [ [ [ [ [ rL: [ C [, E C l [ L [ l L \.. L C3.0 SCENARIO I -NORTH SLOPE POWER GENERATION The North Slope scenario consists of electrical generation at the North Slope,with electrical transmission to Fairbanks via a new transmission line,and transmission from Fairbanks to Anchorage via an upgraded. Anchorage-Fairbanks Intertie.This scenario is illustrated in Figure C3-l. C3.l GENERATING FACILITY SITE EVALUATIONS The·previous report issued in this series,"Report on System Planning StUdies,"concluded that the best generating plant design for the North Slope is either a series of 220 MW combined cycle units consisting of two 77 MW gas turbine units and a 66 MW steam turbine,or a series of 77 MW simple cycle gas turbines alone,depending on fuel price.Three combined cycle units with one simple cycle unit or nine simple cycle units alone would be required for the low load forecast,while six combined cycle units with one simple cycle unit or eighteen simple cycle units alone would be required for the medium load forecast.In evaluating potential sites for the generating facilities,the plant size corresponding to the medium load forecast for both the combined cycle and simple cycle alternatives was used,under the assumption that a~site appropriate for the larger development scenario would be more than adequate for the other a 1ter.natives. The purpose of the generating facility site evaluations was to provide realistic site characteristics for engineering,economic,and environmental evaluations;not to identify a specific site.The geographic focus 'of the North Slope site selection process was the existing Prudhoe Bay/Deadhorse development complex,because of the existing support infrastructure.An overview of the Prudhoe Bay region is given below,followed by siting criteria and the generic site d.escription. 2605B C3-l _.-.r r r [- [' [ r~ r~ '--' [ L [ [ [0 [ L [-- ," [ L- L L C3.1.1 Description of Region -the Prudhoe Bay/Deadhorse Area The Prudhoe Bay area is located at the northernmost reaches of the North Slope in flat.treeless.lake-filled tundra that extends from the foothills of the Brooks Range to the Arctic Ocean.It is an industrial enclave eight to ten miles inland from the coast near the mouth of the Sagavanirktok (Sag)and Putuligayuk (Put)Rivers.The Prudhoe Bay industrial area consists of numerous facilities to support oil recovery. processing and transportation.and a number of work camps housing construction and operations personnel.The Deadhorse airport is located in the southeastern section of the industrial area. Pnrsical setting The Prudhoe Bay area is located i'n the Arctic Coastal Pl ain.a subdivision of the Interior Plains physiographic province.The Arctic Coastal Plain topography consists of a smooth plain that rises from the Arctic OCean to a maximum altitude of 600 feet at its southern border (W~hrhaftig 1965).Since the area is poorly drained.numerous marshes form in the summer.The land area is underlain by continuous pennafrost approximately 2.000 feet thick which thaws a short distance below the surface in summer.Common permafrost landforms include ice-wedge pOlygons,braided streams,oriented thaw lakes.and pingos (University of Al aska 1978b). The Prudhoe Bay area is beset with harsh weather conditions.The seasonal variation is dramatic due to the high latitUde.where d~light lasts continuously during the summer and the sun remains below the horizon for 56 d~s in midwinter.The prevailing winds are east-northeast year-round with an average speed of 11 mph.Periods of stagnation are very rare.Fog is a regular occurrence at Prudhoe Bay. particularly during the summer months.Temperature ranges are large with measured annual extremes of _60°F and +75°F.The ground is covered with snow a major portion of the year but precipitation is less than 7 inches per year (University of Alaska 1978a). 26058 C3-3 Social Profile Prudhoe Bay/Deadhorse is the largest community in the North Slope Borough with a transient population of approximately 6000.The second largest cOlllnunity is Barrow,the economic center of the North Slope Borough, located 110 miles northwest of Prudhoe Bay.As an industrial enclave, Prudhoe Bay is geographically isolated from communities on the North Slope and does not depend on the North Slope Borough for provision of services. Travel in the region is primarily by air carrier,although nonperishable goods and bulkY items are shipped by barge during the navigable season, generally a six-week period duri ng August and the first half of September.The only major road is the Dalton Highway (Haul Road)which links Prudhoe Bay to Fairbanks. The Inupiat,or northern Eskimos,are the indigenous people of the North Slope.The region is characterized by a dual economy of wage employment and subsistence that allows many of the Inupiat to continue cultural traditions using modern technology.In general,unemployment is a serious problem among the permanent residents.Both economic and cultural pressures have intensified the need for continued access to subsistence resources.The Inupiat are oriented both to the sea and interior regions for resources to maintain a subsistence lifestyle. Bowhead whale,seal,and caribou provide the bulk of subsistence needs for the Inupiat;waterfowl,furbearers,and fish are relied on to a 1esser degree. C3.l.2 Siting Considerations Development of siting criteria focused on major factors that could affect the cost and design of the generating facility.Siting criteria for the North Slope scenario were developed under the assumption that the plant would be located in the Prudhoe Bay/Deadhorse industrial area,and would 2605B C3-4 ,r f~ r~ r r I' [ r L.-- [ L [ "[ [ r-·' .-- .~-.) L_J [' .. L.-1 t~ !~......... L I L! f'L [ ~ [ C C C L L, L L consist of six 220 MW combined cycle units and one 77 MW simple cycle unit,or eighteen simple cycle units. C3.1.2.1 Land Status and Use Considerations The Coastal Zone Management Program for the North Slope Borough has delineated zones of preferred development.Permanent facilities are allowed in the industrial development zone,consisting of the existing Prudhoe Bay/Deadhorse complex and the Pipeline/Haul Road Utility corridor (North Slope Borough 1978). Within the Prudhoe Bay/Deadhorse complex,land use criteria consist of minimiZing interferences with existing or planned facilities,including buildings,pipelines,roads,and transmission lines.Land ownership and lease agreements will al so limi t the land availabl e for the electrical generating facility. C3.1.2.2 Geotechnical Considerations Due to the uniformity of foundation conditions at the North Slope (i.e., a thin active zone overlying permafrost),the major geotechnical consideration is developing a foundation scheme that would not cause permafrost degradation.The entire area is in seismic zone one,so seismic risk is not a significant siting criteria within the Prudhoe Bay area. C3.l.2.3 Engineering Considerations The site must be sufficiently large to house the generating units,a sWitchyard,and a construction and operations camp (should existing facilities be inadequate)for approximately 400 workers (approximately 70 acres).The site should be fairly level and adequate drainage must be provided. 2605B C3-5 The site should be in close proximity to the barge unloading facilities to minimize the cost of transporting equipment and should be close to existing electrical transmission lines,access roads,and gravel borrow areas to minimize cost and minimize land disturbance. The site should have access to the existing sewage and solid waste disposal facilities.It should be possible to route a natural gas pipeline from the gas source (the compressor facility)to the site. Combined cycle units require water for boiler feedwater makeup reqUirements,potable demand and other minor miscellaneous uses such as eqUipment wash down.Depending upon ambient air quality,a water or steam injection system may be required to limit the emissions of oxides of nitrogen (N~).In this syst~demineralized water is injected directly into the combustors limiting the peak flame temperature which in turn limits the fonnation of HOx •Typical water injection rates for each unit at base load are about 50 gallons per minute (gpm)for gas fuel. For the medium load forecast and both the combined cycle and simple cycle alternatives,the site must have access to approximately 900-1000 gpm of water if water injection for NOx control is required.If water injection is not required,the combined cycle alternative will require approximately 200 gpm while the simple cycle alternative will require about 50 gpm. C3.l.2.4 Environmental Considerations The major environmental considerations for siting a generating facility in'Prudhoe Bay relate to air quality,aquatic,and terrestri al ecology. Air Quality Air quality concerns playa signficant role in the siting of thermal power plants anywhere in the United States,and Alaska is no exception. The facility will be required to meet atmospheric emission standards and 2605B C3-6 [ U [' L [ FL~~j [; -_i ['-" --' [ __J -.to L •.1 L i [ [- L ~.. [ r [' r l,c~ b [j [ C 6 [ [ L, [ [ f to demonstrate compliance with ambient air quality standards.TWo sets of emission standards exist..These are the New Source Perfonnance Standards (NSPS),which apply generically to combustion turbines;and the Best Available Control Technology (BACT),which is the best control system which can be affordably used on the plant's emissions.The Prudhoe Bay area is currently undergoing an intensive development of its oil resources.This development is having an impact on the air quality of the region.The Clean Air Act Amendments of 1977 establish allowable increments of degradation of ai r quality.These amendments,called the "Prevention of Significant Deterioration"(PSD)program,protect the air quality of relatively clean areas from undergoing substantial degradation.However,the allowable PSD increments for particulates and sulfur dioxide in the Purdhoe Bay area have not been used up.In addition PSD increments for nitrogen oxides,the major pollutant from combustion turbines have not been established.Therefore,it is unlikely that the installation of a gas-fired 'power plant in Prudhoe Bay wou1d~be hampered by air quality regulations,if a judicious siting effort is undertaken to prevent the compounding of any air pollution problems from existing facilities. For combustion turbines,the PSD requirements would nonnally dictate the use of water or steam injection techniques to reduce the emission of nitrogen oxides to a level which meets the definition of Best Available Control Technology.The use of water injection measures will lead to the fonmation of ice fog in the Prudhoe Bay'area and will also require the availabil ity of an adequate supply of suitabl e fresh water.These additional requirements pose a substantial threat to the installation of combustion turbines,which use water injection control,in the Arctic e nvi ro lIDent.In the recent past,agenc i es wi th revi ew a uthori ty 0 ve r the installation of the combustion turbines have granted a waiver from the use of water or steam injection in the Prudhoe Bay area.It will also be necessar,y in the specific case being examined to obtain a waiver from these same requirements before the pl'anned combustion turbines can be installed.The use of air cooled condensers or dry cooling towers is also required in order to eliminate the fonnation of ice fog and its 2605B C3-7 associated hazards (primarily the reduction of visibility for road traffic)• Aquatic Ecology Two groups of fi sh util i ze the freshwater resources of the Prudhoe Bay area and would thus require consideration ·during the detailed site selection process:river fish such as the grayling,and anadromous fish such as the Arctic char and cisco.The·anadromous species descend local rivers at ice-breakup to feed in the shallow littoral and sublittoral zone of the Beaufort sea.They ascend these rivers in the autumn and overwinter in deep pools.These fish do not appear to undertake extensive migrations up the Sag or Put Rivers.Potential development-related impacts on fish which would require consideration include:pipeline and access road construction,and gravel mining in rivers which could affect overwintering and general habitat quality of the fish;and the need to cross larger river channels which could interfere with fish passage.The latter item may require the use of special culverts to maintain migrato~routes. Terrestrial Ecology The Prudhoe Bay area and specifically the river delta areas provide a variety of habitats that are important to a diversity of plants and animals.The varied features of estuarine and river delta shorelines, sand dunes and dr,y,moist,wet,and aquatic tundra provide conditions for ma~types of vegetation that in turn provide breeding,feeding,nesting, and staging areas for many birds and mammals.A prime eoncern relative to the effects of any major development on the North Slope is the effect of vegetation change on important wildlife habitat.In addition,the ecological value of wetland vegetation has been nationally recognized, and these areas have been granted special regulator,y status under section 404 of the Clean Water Act of 1977.Project related impacts which would require special consideration during a detailed siting study include: 1)direct habitat elimination through the construction of project 2605B C3-8 -r T' r r r~ I~ .[ L [ .[~ .._-_. .[ L .-_1 [ .J [ •__.1 L_.1 L__I .[OC '.". ,..J L [ r [ l~ [- [ [ nw b b L C E [ ~- L L, L, [ facilities,access roads,and gravel borrow areas;2)indirect habitat elimination resulting from access roads which impede drainage or which generate significant traffic related dust;and 3)restrictions to large mammal movements,especially caribou. C3.1.3 Generic Site Description It is assumed that one or more locations could be found that would fit the generic description given below.The descriptions are of p~sical characteristics as they are assumed to exist,and emphasizes factors that may significantly affect cost or engineering design. C3.1.3.1 Location and Access The electrical generating facility site is located within the industrial enclave of Prudhoe Bay/Deadhorse,in the general vicinity of the existing SOHIO-operated powerplant,approximately five miles from the Beaufort 'Sea shoreline.This general location does not involve extensive transport distances for equipment received at the barge unloading facilities,and is also accessible for material transported by air or via the Haul Road. The area is served by existing roads,transmission lines,and waste treatment and disposal facilities,minimizing the cost for developing these facilities. C3.1.3.2 Size and Surface Characteristics The power plant site is approximately 65 acres in size,inclUding the power plant housing and switchyard.An additional five acres will be used for the construction camp,operations personnel housing,and related facilities.The construction camp site is located adjacent to the generating facility site. The power plant site is on a nearly level $lope,although final grading will be achieved by shaping the gravel mat that will underlie the structure. 2605B C3-9 C3.1.3.3 Water Source The power plant site is located adjacent to a lake of approximately 600 acres.The lake will be dredged to an appropriate depth to provide adequate storage volumes.The lake will provide the water needed for boiler feedwater req~irements~potable,and ~ther miscellaneous uses,but will not provide sufficient quantities for water or steam injection associ ated wi th NOx control.If water i njecti on is requi red,a suitable fresh water source would have to be developed. C3.1.3.4 Soils and Foundations The existing soil profile consists of an active zone approximately 1.5 feet thick overlying permafrost.The permafrost in this area is about 2000 feet thick. Because mai ntenance of the permafrost is the pri mary geotechnical consideration in building a generating facility on the North Slope, foundation design will ensure permafrost integrity.A five foot thick engineered gravel mat will be placed directly over the tundra.Power plant modules will be set on 2-foot diameter steel pipe piles having a wall thickness of one inch.The pipe piles will be placed in 30 to 35-foot deep pre-augered holes,and backfilled with a sand-water slurry. A 90-day freezeback period will be required prior to loading any piling. Piling will extend above the ground surface six to eight feet,resulting ina total pil e 1ength of 36 to 43 feet.Thi s foundati on des i gn wi n prevent any thawing of the permafrost from the generating facility. C3.2 TRANSMISSION FACILITY ROUTING EVALUATIONS The North Slope scenario involves transmitting electricity generated at the North Slope to Fairbanks and on to Anchorage.Discussion of the transmission route is divided into two sections,Prudhoe Bay to Fairbanks,within the utility corridor,and Fairbanks to Anchorage,via the Intertie now under construction.This scenario assumes that 100 2605B C3-l0 [' .._-.' [ F·L; L~ -~ L ~:~ [ L.-.J L L .c - [ [ c. C L [ r·~· p L.' [ C C L L [ [ Ll-_.. L I'._ L percent of the generated electricity woul d be transmitted to Fairbanks, and approximately 80 percent transmitted on to Anchorage. C3.2.1 Prudhoe Bay to Fairbanks C3.2.1.1 Description of the Region The designated utility corridor extending from Prudhoe Bay to Fairbanks consists of a strip of land about 425 miles long and from 12 to 24 miles wide.The portion of the corridor from Sagwon Bluffs,60 miles south of Prudhoe Bay,to Washington Creek (28 miles north of Fairbanks)was designated as a utility transportation corridor by Public Land Order (PLO)5150 in 1971.This PLO also designated an inner corridor, extending the entire length and var,ying in width from three to 20 miles. The trans-Alaska oil pipeline (TAPS)occupies a 54-foot right-of-way within the corridor.Related pipeline facilities such as pump stations, material sites,and access roads are located along the corridor's length.The Dalton Highw~(Haul Road)completed in 1974 to serve pipeline construction-needs,·is a 28-foot wide,a1l~eather,gravel highway within a 200~foot right-of-way granted to the State of Alaska. It extends from the Elliott Highway to Prudhoe Bay.North of the Yukon River the highway is closed to the public except during June,July and August,when it is open as'far as Dietrich camp. Physical Setting The physiographic provinces along the corridor are the Arctic Coastal Plain,Arctic Foothills,Arctic Mountains,and Northern Plateaus Provinces.The Arctic Coastal Plain is a wet tundra and mosaic of small lakes that extends from Prudhoe Bay to a maximum altitude of 600 feet. To the south,the Arctic Foothills consists of rolling plateaus and low linear mountains.The central and eastern Brooks Range and the Ambler- Chandalar ridge and lowland section comprise the Arctic Mountains Province.The Brooks Range is a series of rugged glaciated ridges that 2605B C3-ll rise to summits of 7,000 to 8,000 feet in altitude in the northern part and 4,000 to 6,000 feet in the southern part.Small cirque and valley glaciers and lakes are cOlllllon features. The Northern Plateaus Province includes the region south of the Brooks Range and is cha racteri zed by ever:w-topped ri dges.These mountai ns descend to the Yukon Flats characterized by gently sloping outwash fans and nearly flat floodplains.Continuing south,the corridor extends into the rolling uplands of the Yukon and Tanana valleys. Five major federal land designations are located adjacent to or near the corridor.Immediately to the west of the corridor in the Brooks Range is Gates of the Arctic National Park.To the east is the Arctic National Wildlife Refuge.Further south are the Yukon Flats National Wildlife Refuge and the Kanuti National Wildlife·Refuge.To the south of the designated utility corridor is the White Mountains National Recreation. Area. The climate along the corridor can be divided into two zones.The Arctic zone extends from the Arcti c OCean to the Brook s Range and the Continental zone,which is the predominant zone of Alaska,covers the area from the Brooks Range to Fairbanks.Annual precipitation ranges from less than 5 inches in some Arctic areas to 20 inches in the Interi or. The corridor parallels major north-south rivers including the sagavanirktok,Atigun,Dietrich,and Koyukuk Rivers.South of the Brooks Range,river valleys are primarily in an east~est orientation and the corridor crosses numerous streams. North of the Brooks Range,in the foothills and coastal plain,the vegetation consists mainly of moist tundra composed of dwarf shrubs, sedges,cotton grass tussocks,mosses,and lichens with some high brush occurring in the floodplains.Alpine tundra,consisting of dwarf birch, willow,and low heath shrubs,and barren ground are found in the Brooks Range.Upland spruce-hardwood forest occurs south of the Brooks Range 2605B C3-l2 r ~. .j t 'rJ Il ...., T' L c'L. :r'" .~.....,~j T' L l~_,.l l L .........J L·'.. ._.1 L I [ r~- c-. C. r [ C [ [ rL-.J- r~ L [ 8 C C ~ [ L [ 1- L [ along riverine systems.Treeless tundra occurs above 2,000 feet.In the Yukon and Tanana Rivers region the vegetative cover is predominantly bottomland spruce and hardwood forests. Social Profile There are few signs of human inhabitance along the Prudhoe Bay-Fairbanks corridor.The villages of Livengood and Wiseman,and a number of small mining operations.near the Wiseman area,are located near the Haul Road. TAPS pump stations with transient personnel are located at Pump Station 2,Slope Mountain (Pump Station 3),Galbraith Lake (Pump Station 4), Prospect (Pump Station 5)and the Yukon River (Pump Station 6). Department of Transportation camps are located at Slope Mountain, Chandalar,Dietrich,Coldfoot,Prospect and seven miles north of the Yukon River.Some of these camps have worker dependents and a school is located at the Yukon River camp.Comercia1 service establistlnents (i.e.,truck stops)are located at Coldfoot and the Yukon River. C3.2.1.2 Routing Considerations Trans-Alaskan Pipeline System Restrictions One of the most important siting criteria for the transmission line is to protect the integrity of the existing TAPS line and to avoid interference with pipeline operations.However,the present stuqy assumes that no "fata1 fl aws"to the routi ng of ei ther a transmi ssi on 1i ne (Scena ri 0 I) or a gas pipeline (SCenario II)would be imposed by the presence of the TAPS line.This assumption is based on the fact that a major additional linear facility (the ANGTS line)within the Utility Corridor has been licensed.While it is reasonable to expect that either transmission or new pipeline facilities could be routed within the corridor,such routing would not be done without numerous local complications imposed by physical and environmental constraints,including.the presence of the TAPS line. 26058 C3-13 Specific TAPS restrictions would be negotiated during the detailed siting procedure.However,the following general critiera would be applicable: Minimize crossing the trans-Alaskan pipeline.Each crossing of the TAPS line poses a risk to the pipeline's integrity."Crossing of the li ne shoul d only take place where requi red by topograpfly, ".' right-of-way,or other restrictions. Locate the transmission line at least 200 feet from the existing oil pipeline whenever possible.This was the minimum separation agreed upon for the ANGTS line,and it can be assumed that a similar separation would be reqUired for the transmission line. Locate the transmission line downslope of TAPS and the haul road when feasible.This would prevent a~ground slumping or deposition of eroded materials from affecting the TAPS line. Utility Corridor Considerations The Bureau of Land Management (BLM)has prepared land use plans for the Utility Corridor between Sagwon Bluffs and Washington Creek.These plans provide for a minimum of interference among alternate land uses, preservation of the environment,and appropriate use of the natural resources within the corridor.The land use plans contain specific programs for intensive land uses (such as pipelines,airports,and roads),mineral development,forest products use,rangeland,watershed protection,wildlife protection,and recreation.Specific components of the land use plan that relate directly to transmission line construction are sUllllla ri zed below (BLM 1980). Consolidate all pennanent facilities except pump and compressor facilities at carefully selected nodes in the vicinities of Livengood Camp,Yukon Crossing-Five Mile camp,Prospect;Coldfoot,Chandalar, and Pump Station #3 area. 2605B C3-14 [" L .r: [ [ f;j l.ei r f C rr [ r~ [ r L~ b b C C t [. L [-~ L '...- C- Take appropriate action to safeguard against damages to the pipeline and aqy new pipelines and related facilities. Protect stream banks and lakeshores by restricting activities to prevent loss of streamside vegetation. Restrict development of land within the floodplains of rivers to avoid loss of property by floodwaters. Protect raptor habitat and critical nesti ng areas.The Endangered Species Act mandates protection of threatened and endangered wildlife species.'Protection of crucial raptor habitats preserves the integrity of raptor populations and maintains predator-prey re 1ati onshi ps. Protect fish overwintering habitat.The critical overwintering areas have been mapped by BUM.Sufficient water levels should be maintained to meet the needs of overwintering fish.Conditions va~ at each site,so stipulations should vary at each site to mitigate or prevent adverse alterations in fish habitat. The land use plan has identified several areas as containing critical wildlife habitat.Specific management restrictions have not as yet been fonnulated;however,measures may be required for the following areas at the time of transmission-line construction: A.The Galbraith Lake-Toolik Lake-Atigun Caqyon area. B.The Sukakpak-Wiehl Mountain area. Because of critical wildlife habitat,rare plants, historical,and archaeological sites and scenic values within the Corridor,all of vital national interest, special management is needed to focus properly on these two areas. C.The Joe Creek-Chandalar Shelf area. This area has a concentration of mineral licks,nesting raptor sites,and a Dall sheep lambing area. 2605B C3-15 D.The bluffs along the Yukon River. E.sagwon Bluffs. These ·areas have been identified as peregrine falcon habitat. F.The Jim River and Prospect Creek areas. Thi s has the highest qual ity year-long habitat for salmon in the Corridor.Proposed development and mining endanger this habitat.Also,these areas have high archaeological val ues. G.The Bonanza Creek area. Just below Bonanza Creek is an important salmon f~ overwintering area.Spri ngs originati ng here are the mai n source of wintertime water flow. H.The Ivishak River,Lupine River,Accomplishment Creek,Ribdon •River area. These are important char overwi nteri ng areas. I.The Kanuti and sagavanirktok River areas. J.The Wickersham Dome Area. These areas have been identified as caribou winter range. In addition to the BLM land use plans,general land use criteria include: o Maximize use of existing facilities such as work pads,highw~, access roads,airports,material sites,and communications. o Minimize crossing roads and highways. o Avoid areas of existing or planned mineral development. Engineering Considerations The design of the transmission line from Prudhoe Bay to Fairbanks faces special challenges.This line must be able to serve the Rai1belt with a substantial amount of power by the year 2010 and will provide for greater than 50 percent of the state's total available capacity at that time.A sudden loss of more than half,or almost three quarters of the power at the low or the medium load forecast,respectively,would cause serious 2605B C3-16 [ r L~ [' r' \. [ L - [ [ r'o _~ [ c [ [: [ r L---.i c ~ C C 6 [ '. [ L L [ interruptions in the Railbelt's electricity supply.In order to prevent this from happening,the line must be designed such that potential outages will be kept to a minimum,and that the loss of a single line segment will not jeopardize system operation even during peak loading. The minimum condition to achieve this objective is to build two transmission lines (i.e.,to have two circuits on separate towers):This is obviously a major cost consideration,and will be treated in detail in the subsequent Feasibility Assessment Report.The width of the right-of~ay (ROW)of these 500 kV circuits is assumed to be 300 feet each or 600 feet total if they run side by side.This is somewhat more than the ROW used in the lower 48 (220 and 440 feet)but the rugged conditions require heavier structures and therefore wider ROWs.In general,two circuits would be routed side by side over the entire length with local exceptions.In the Atigun Pass area,for example,separate route alignments wou.l.d be necessary. The alternating current transmission line with its two circuits would be sectionalized by installing two switcqyards at about 1/3 and 2/3 of the way along the line,or approximately 150 miles apart.With the substations at the two ends of the line,switching can be accomplished at four locations:Prudhoe Bay,Galbraith Lake (Pump Station 4),Prospect Camp (Pump Station 5)and Fairbanks.Should a failure occur at any of the line sections,a 150 mile stretch of one circuit has to be disconnected.During such a time period,'one of the circuits would carry the power over the 150 mile long section,While for the rest of the line, both circuits would carry power.The circuits would be designed to carry the full load without any damage. As transmission line grounding poses severe problems in many areas, including Prudhoe Bay,a continuous conductor wire,called contrepoise, would be carried along the entire length of each circuit,buried underground.This will assure proper behavior of the line during switching operations. 2605B C3-l7 Access from the Haul Road to the transmission line right-of-way would be provided at suitable locations along the entire route.Construction personnel would utilize the existing camp facilities developed for TAPS. Geotechnical Considerations Geotechnical criteria consist of avoiding steep slopes,unstable soils, bedrock slide areas,and active fault zones.In some segments of the corridor,however,adverse geotechnical conditions cannot be avoided.In these cases,tower foundations would be designed to accommodate unfavorable subsurface conditions.Soil types within the corridor consist of marine sediments,floodplain gravels,alluvial fan and slopewash deposits,residual soil over bedrock and aeolian deposits. Continuous and discontinuous penmafrost is also present. Environmental Considerations . There are numerous environmental considerations that must be taken into account during detailed siting efforts and design engineering for a Prudhoe Bay to Fairbanks transmission line.These considerations have.. been derived from numerous environmental studies perfonmed in conjunction with the evaluation of the TAPS line and in support of the ANGTS project.Some of the major considerations are discussed below. Facilities and long tenm habitat alterations are prohibited within one mile of peregrine falcon nest sites unless specifically authorized by the U.S.Fish and Wildlife Service,because of the endangered species status of the peregrine falcon.Along the utility corridor six nests are loCated along Franklin Bluffs,and Sagwon Bluffs,and one nest on Slope Mountain.As a transmission line or gasline alignment along or west of the Dalton Highway would avoid the Franklin Bluffs and Sagwon Bluffs locations,the restriction may apply primarily to material sites. Other rap tors which may influence routing and siting include golden eagles (at least 42 nests between the Yukon River and Slope Mountain), 26058 C3-18 r: -r T' T- r L r oOF l.,- ~[ [ [ C oj oI~ [ L O....J "L ....,..:1 L_J L ..1 - [ [. r-· [ r r [ C· nL..J_ [ C. o nq e L L L [ l __. [ [ rough legged hawk (24 nest locations between Slope Mountain and Prudhoe Bay),and gyrfalcons (5 nest locations between the Yukon River and Atigun Pass,11 nest locations from Atigun Pass to the end of Sagwon Bluffs). Siting restrictions for these rap tors which were applicable to ANGTS are presented in Table C3-l. It is unlikely that the transmission line would be sited in or near important Dall sheep habitat.A primary concern is aircraft traffic over critical wintering,lambing,and movement areas.Moose winter browse habitat in the Atigun and sag River valleys is limited to areas of tall riparian willow.Habitat has already been eliminated by the construction of TAPS and further destruction of this habitat should be avoided or minimized.The willow stand along Oksrukuyik Creek,in particular, should not be disturbed. System design must allow tree passage for caribou,but these animals should not be a major consideration in.siting.carnivore/human interaction is a major concern in facilities design and in construction and operations methods,but not in siting considerations. Major impacts to fish would be from contrepoise construction.Between Fairbanks and Prudhoe Bay,the transmission line may cross as many as 150 waterbodies which are utilized by fish for migration,rearing,spawning, and/or wintering.Sit~ng should avoid or mini~ize impact to spawning areas in approximately 35 waterbodies and to wintering areas in approximately 15 waterbodies.Important spawning waterbodies include large to middle sized rivers and streams such as the Chatanika River; Kanuti River,Fish Creek,Bonanza Creek,Prospect Creek,Jim River,and Koyukuk River and adjacent sloughs,Dietrich River and associated side channels and sloughs and the Kuparuk River,and also such small streams as Mar,y Angel Creek.Waterbodies that include important fish overwintering areas include Fish Creek,Bonanza Creek,the Jim River,the Koyukuk River,and the Dietrich River and associated springs and sloughs. 2605B C3-19 TABLE C3-1 STATE OF ALASKA TEMPORAL AND SPATIAL PROTECTION CRITERIA FOR NESTING RAPTORS!I Protection Criteria Minor Major Sensitive Aerial Ground Ground Facility Habftat Species Time Period Activity 21 Acti vi ty Activity Siting Disturbance Peregrine 15 April -1 mf h 1 mi 2 mf 2 mi 2 mi falcon 31 August or 1500 ft v Gyrfalcon 15 February-1/4 mi h 1/4 mi 1/4 mf 1/2 mi 15 A~gust or 1000 ft v Golden eagle 15 Aprl1-1/2 mi h 1/4 mf 1/2 mi 1/2 mf 31 August or 1000 ft v Rough-legged 15 Aprll-1/4 mi h 1/4 mi 1/4 mf 1/2 mi hawk 31 August or 1000 ft v Bald eagle 15 March.Y-1/4 mi h 1/8 mi 1/4 mi 1/2 mi 1/8 mi 15 August or 1000 ft v Osprey 15 March-1/4 mi h 1/8 mi 1/4 mi 1/2 mi 1/8 mi 15 August or 1000 ft v 11 Extracted from l5ensitive wildlife areas of the Northwest Alaskan gas pipeline corridor l , C.E.Behlke,State Pipeline Coordinator,letter to E.A:Kuhn,NWA,15 July 1980 and presented in Roseneau et·al •.1981.. 2/h :=horizontal;v =vertical. ~I 1 March for areas between mileposts 472 and 573 (Tanana River from near North Pole to near Gerstle River).. 2645B ~L~"I,.:':. r"l......,....J C--JJ . [ [ ~--'-'. f' C [: [ [~ ['-' ••• [~ [" ~ C C 8 [ [ [ [ 1.,__ [ Identified overwi nteri ng areas such as SChroeder's Spring on the Dietri ch River should be avoided altogether.Another ve~important area to be avoided is the wetland between Pump Station 4 and the Dalton Highway.and important rearing areas for fish in the Atigun Valley. Line routing and tower siting should avoid or minimize disturbance of the treeline white spruce stand at the head of the Dietrich Valley.which has been nominated for Ecology Reserve status. Transmission line construction may cause increased erosion rates in disturbed areas.This impact can be minimized by routing the line so that existing access roads can be used as much as possible.In addition.steep slopes and highly erodible soils should be avoided wherever possible. Water quality impacts.primarily increased suspended solids concentrations.are closely related to'erosion effects~In addition to the soil erosion considerations discussed above.the line should be routed so that a buffer strip of vegetation can be maintained between the disturbed areas and all water bodies. C3.2.1.3 Generic Route Description Because the topography and climateva~dramatically ~etween Prudhoe Bay and Anchorage.the transmission line route has been divided into seven segments,as shown in Figure C3-1.Within each segment,the engineering design of the transmission line and tower foundations would be generally uniform.A brief summa~description of each segment is given below,with emphasis given to topographic and climatic factors that affect transmission line costs. Segment 1 -Arctic Coastal Plain (Prudhoe Bay to Pump Station 2) The first segme~t encompasses the route from the Prudhoe Bay oil fields ta Pump Station 2 of the pipeline.It is a 60 mile long segment.consisting of fl at tundra wfth numerous 1akes and ponds.The soi 1 is mal nly coarse 26058 C3-2l alluvium and is u~derlain with continuous penmafrost.Near the coast, arctic sand,picked up by moist,salty winds would contaminate the insulators in the late summer and/or early fal.l;this requires annual washing of the insulators. The temperatures in this segment range from -60 to 86°F,.with an average annual snowfall of 35 inches.Wind speeds can be up to 100 miles per hour.Ice thickness on transmission lines can reach 1.5 inches radially. segment 2 -Northern Brooks Range (Pump Station 2 to Galbraith Lake) The second segment is approximately 95 miles long and gently rises from 500 feet above sea level to 3000 feet.No serious contamination problems are anticipated here because of the distance from the Beaufort sea and because dust is generated only on the roads.The soil is alluvial deposits,floodplain gravel and slopewash deposits;it is in the zone of" discontinuous pennafrost.One of two intennediate switching stations would be located at the end of this segment,at Galbraith Lake,.The area is in the vicinity of Pump Station 4 and is easily accessible by road or ai r all year round. Temperatures range from -60°to 90°F,and winds reach 100 miles per hour. Snowfall averages 63 inches annually,with a maximum of approximately 48 inches on the ground at any time."Maximum ice loading on the proposed line would be 1.5 inches radial thickness. Segment 3 -Atigun Pass (Galbraith Lake to Nutirwik Creek) The Atigun Pass segment of the line is only 30 miles long.For most of this length the road and the TAPS pipeline would be between the two, circuits.Should any ROW be reserved for future pipelines or other structures,this should be specified in advance in order to avoid future conflicts.For about a 5-mile stretch at the pass itself at 3,000 feet above sea level,the circuits would be routed on the mountainsides. SUitably designed transmission towers can be erected on the slopes of 2605B C3-22 -[ r T~ r l' ·r l. r~ L [ -c~· b [ l .) b -•.j [ [ .._' L.._1 [ _e; [' [ [ C r [ [. c (~ L n'-.-J CL L C C C U L~ [ L W [ Atigun Pass.Far more difficult terrains have been successfully crossed with electric transmission lines elsewhere in the United States and abroad.Avalanches,however,are a major consideration.Another potential problem is that the contrepoises cannot be lowered into the rock soil,in which case two alternatives are available.The contrepoises can be either continued on the top of the towers as ground (aerial,s~)wires or they can be routed a few hundred feet away from the circuits close to the road and pipeline with tie connections to as many towers as possible. The temperatures in this area range from -60°to 90°F.Average annual snowfall is approximately 63 inches,with roughly 48 inches maximum snow depth on the ground.Ice loading can reach 1.5 radial inches,and dust contamination would occur from the haul road.Wind speeds reach 120 miles per hour. Segment 4 -Southern Brooks Range (tlItirwik Creek to Jim River) From Atigun Pass to the Jim River the line would gradually descend from 3000 feet to 1000 feet in elevation.In this 90~il~section,extensive geotechnical surveying is necessa~to identify a route Which provides suitable soil for transmission tower footings.Being south of the Continental Divide and having only the road as a dust source,no serious contamination problems are expected in this segment. Temperatures range from _75°to 90°F,with approximately 150 inches of snowfall per year.Maximum snow depth is about 110 inches.Wind speeds reach 90 mph. Segment 5 -Caribou Mountain (Jim River to Yukon River) The fifth segment runs between the Jim and Yukon Rivers and is 75 miles long.It is charactertzed by rolling hills and some flat terrain with an average elevation of approximately 1000 feet".Construction and operation of the line would be less demanding here than many of the other segments. The Prospect Camp/Airport area (about 25 miles south of the Jim River)is 2605B C3-23 a good location for one of the fntenmediate switching stations.This site is next to Pump Station 5 and a DOT camp and therefore,has year-round access. Temperatures range from -80 to 95°F,with 100 inches annual snowfall and 75 inches maximum snow depth.Wind speeds reach 80 mph.Dust contamination occurs from the road. Segment 6 -Yukon River Crossing The Yukon River crossing was identified as a separate segment,because of the dissimilar engineering problems it involves.The line would cross the river west (downstream)of the highway bridge.The bridge is approximately 2100 feet long and carries the TAPS line on its upriver side.The span of the line,located several hundred feet downriver of the bridge,is estimated to be approximately 2500 feet long.The span would originate on the flat area on the north (right)bank of the river.It would tenminate on top of a hill on the left bank,at some 300 feet in elevation above the river.The hill provides the necessa~height required for such a long span and eliminates the use of unusually large, hea~,expensive and unsightly transmission towers.With a 100 foot tower on the North Bank and a less than 200 ft tower on the South bank,on the top of the hill,the profile of the conductors would be almost exactly a half catena~curve,with the lowest point at the north end.The line therefore,would not create an obstruction to river traffic. Temperatures range from -80 to 95°F.Average annual snowfall is 66 inches wi th a max imum snow depth of 50 inches.Wi nd speeds reach 70 mph. Segment 7 -livengood (Yukon River to Fairbanks Area) The last segment of the transmission line runs to.the Fairbanks area,the site of the final substation.The line would be routed among rolling hills.For approximately one mile the grade is in excess of 30 percent, the steepest grade along the entire route.The soil is residual soil over 2605B C3-24 CL [ ['~ -, c e,-, [. ,j L ,.; [ ,J L__.J t", = L; r [" ['- C-, r- r r~··· ~-~. r ~ [ [J U C'".. f'.~.•'U C ! [ [ ~'- L i L bedrock with aeolian and silt deposits down-slope.The soil of the smaller valleys consists of ice-rich silts to·a depth of over 100 feet. and the larger streams have unfrozen floodplain gravels and sand. Temperatures range from -70 to 98°F.with an .average annual snowfall of 66 inches and maximum snow depth of about 50 inches~Wind speeds reach 70 mph.Dust or other contamination problems can be serious near c~nstruction sites or other disturbed areas. C3.2.2 Fairbanks-Anchorage C3.2.2.1 Description of the Region The Anchorage-Fairbanks corridor encompasses these two economic centers and the major portion of the State's population.The transmission intertie would parallel the Alaska RailrQad as well as the Parks Highw~. Which is the major transportation link between the two major cities.The area falls within three jurisdictions.the Anchorage Area Borough.the Fairbanks North Star Borough.and Matanuska-Susitna Borough.The Denali National Park.adjacent to and west of the Parks Highw~.has national as well as international importance and attracts thousands of visitors each sUlJll1er. Physical Setting The topography of the area is dominated by the north to south river valleys of the Susitna.Talkeetna.Chulitna.and Nenana Rivers.and the Alaska Range to the west and north.The transmission line corridor falls wi thi n the vall ey floor of these ri verso The hi ghestpoi nt along the corridor is 2.300 feet at Broad Pass.which marks a watershed divide.The p~siographY of the region is widely varied.The corridor crosses four physiographic subdivisions that belong to the Pacific Mountain System division.The Cook Inlet-Susitna Lowland.a glaciated lowland less than 500 feet above sea level.covers the area from Anchorage to Talkeetna. This subdivision 'contains most of Alaska's developed agricultural land and 2605B C3-25 is almost ice-free except for sporadic pennafrost present in the northern part.The Broad Pass Depression is 1.000 to 2,500 feet in altitUde,a trough having a glaciated floor that covers the area between Talkeetna and Healy.To the north.the central and eastern Alaska Range consists of rugged glaciated ridges broken at intervals by cross-drainages or low passes.The Northern Al~~·ka Range Foothills includes the area between Healy and Fairbanks and is characterized by flat-topped east-trending t>ri dges sepa rated by roll i ng 1owl ands.The transmi ssi on corri dor is.~ situated in the glaciated valleys of this subdivision. The region falls within the northern extension of the North American boreal forest which is characterized by interior forests of willow, spruce,and alder in the southern two-thirds and open woodland,shrubs, and tundra in the northern one-third.The vegetation cover supports big game species of moose,'caribou,brown and black bear,small game, migrator,y game birds,furbearer,raptors,and other nongame mammals and birds.The Susitna River Basin and portions of the Nenana River Basin are important spawning grounds for anadromous salmon and common river species. Social Profile• The region is dominated by two population centers,Anchorage to the south and Fairbanks to the north.small population centers are located in Wasilla,Palmer,Houston,Talkeetna,Willow,Cantwell,and Healy with the remaining population scattered along the Parks Highway and the Alaska Railroad.Cantwell.Montana Creek,and Caswell are native villages within the corridor•.The 1980 estimated population for the region was approximately 247,000 with over 70 percent of that population based in Ancjlorage. Although Anchorage and Fairbanks are major centers with diversified economic bases,the economy of the region between the two cities is largely undeveloped.No significant additions to the project area's economic base has occurred during the past decade except for the expansion of commercial activity along the Parks Highway and the expansi'on of coal 2605B C3-26 c J' f r l" r f--- ..L.j r=L._ [ [- [ [ --j L" ",.- -; -' L -' l..-J J-- _W L [ L b [ [. C L [ [ L, C " [ mining activities in Healy.Some major development projects proposed for the region could dramatically impact the demographic and employment outlook. Outside of the Anchorage and Fairbanks labor markets,job opportunities are limited mostly to construction labor and tourist and recreation- oriented services.As a result,the labor force along the corridor is highly mobile in search of work and the unemploYment rates are chronically high with wide seasonal swings. C3.2.2.2Routing Considerations Route Descriptions An existing transmission line corridor connects Fairbanks to Anchorage and is essentially divided into three segments.From Fairbanks to Healy,a 138 kV transmission line is operated by Golden Valley Electric Association.This 110-mile segment parallels the Fairbanks-Anchorage Highway for its entire 1ength. From Healy to Willow,the Intertie now under construction will consist of a 345 kV line that will be initially operated at 138 kV.This line will extend for 179 miles with a right-of-way width of 400 feet (Commonwealth Associates 1982). The Intertie corridor passes through the Montana and Mooqy Creek drainages between Healy and Windy Pass,and is routed along the eastern portion of Broad Pass.The route then passes east of Chulitna Butte and crosses the Susitna River near Indian River,paralleling the Alaska Railroad until just north of Deadhorse Creek.The route crosses the Talkeetna River near Bartlett Hills,five miles east of Talkeetna,and proceeds south and west to near the village of Montana.The route parallels the Matanuska Electric Association right-of-way for the last 19 trlileS into the Willow Substati on. 2605B C3-27 Between Willow and Anchorage,an eXisting 115 kV line passes along the eastern side of Knik Arm.In addition,a 138 kV line extends from Tee1and,seven miles south of Wasilla,to Anchorage,along the western side of Knik Arm.As part of the Intertie construction,the Teeland substation will be connected to the Willow-Anchorage line with a 5.5 mile new 138 kV segment.The re~ainder of the 30~ile line from Teeland ~o Willow will then be converted to 138 kV. Applicability of the Intertie Route The transmission corridor selected for the Intertie balances concerns for environmental resources,public interests,economics and reliability. During route selection,substantial input was incorporated from both the public and private sector,inclUding the Rai1be1t communities through the Public Participation Program,the resource management agencies through infonma1 meetings and fonmal presentations and the part'icipating Alaskan Utilities through the Technical Review Committee (Commonwealth Associates 1982).Based on this methodical siting process,the designated Intertie route 'was assumed to be the most appropriate for the.present study's purposes. The Intertie route was chosen specifically to minimize engineering and geotechnical complications,land use interferences and environmental.,... ... consequences.The route avoids most.of the local communities along the Parks Highway and Alaska Railroad.The route includes no crossing of the Denali National Park and Preserve,one crossing of the Denali State Park, no crossings of the Parks Highway,and only two crossings of the Alaska Railroad. In addition to siting considerations,special measures are being implemented during the construction phase to further minimize environmental consequences.Several of these mitigating measures,as presented in the Environmental Assessment of the Intertie (Common~ea1th Associates 1982),are summarized below. 2605B C3-2~ [ [ C" -. t··~~ -, " b J [ ~ l~ ~ ~ l C [ [ [ [ [ C U [ C·· L [ l C In the ver,y steep areas,soils will likely be cleared by hand to avoid excessive soil erosion.Soils susceptible to severe erosion or creep will be avoided. The transmission line will unavoidably cross several large rivers and numerous creeks.However,all towers will be set back from water bodies at least.200 feet where possible.A buffer strip will be established along major watercourses to minimize siltation of streams.Equipment crossings of streams will take place when the stream is frozen,whenever possible. Because trumpeter swans are ver,y susceptible to human disturbance, construction activit~will be restricted from May through August in areas with active trumpeter swan nesting territories. The route avoids all known ba1 d and golden eagle nests.Peregrine falcons are not known to utilize the project area except as migrants. Because even a single equipment pass c~n cause serious penmafrost degradation (Brown 1976),construction in penmafrost areas will be completed when the ground is frozen.Construction in muskeg-bog soils will also be completed when the ground is frozen. Fisheries resources will be protected by mfnimizing erosion and the' SUbsequent s iltati on of water bodi es.At stream crossi ngs where equi pment will move directly through the water,the crossings will be made during periods when there are no eggs or fry in the gravel.Generally,this will be a period in June and July after the rainbow trout and Dolly Varden fry have developed through swim-up and before the Pacific salmon start to spawn.Activities will be closely coordinated with the Alaska Department of Fish and Game.Construction activity will avoid small lakes and beaver ponds that are important nurser,y habitat for local and anadromous fish cOlllTluni ties. 2605B C3-29 The Moody Creek-Montana Creek portion of the line will be constructed by helicopter.In other areas,existing roads and trails will be used as much as possible. Upgrade Considerations satisfying the forecasted electrical energy demands within the Railbelt will require upgrading of each transmission line segment between Fairbanks and Anchorage including the Intertie.For all development scenarios evaluated in this study the existing 138 kY lines connecting Healy to Fairbanks and Willow to Anchorage will have to be upgraded to 345 kY essentially through line replacement.The Intertie would then be operated at 345 kY.One or two additional 345 kY lines are also required, extending the entire length of the corridor.In addition,various other electrical equipment changes inclUding a switching station m~be required,depending upon the developed scenario.Each aspect of the required upgrade is presently under stuQy and will be specified in the Feasibility Assessment Report.It is realized that incremental environmental impacts will accrue due to line upgrading activities and these will also be discussed in the Feasibility Report.Because transmission line upgrading will utilize existing corridors,engineering and/or environmental considerations which could significantly affect system design or preclUde d~ve10pment are not envisioned at the present time.It should be noted that substantial upgrading of the Anchorage-Fairbanks Intertie,on the order of that described above,will be requi red for any major energy development al ternati ve to serve increased Rai1be1t power demands. 2605B C3-30 [ T~.C [ [ ; L f '~ .~ "•._.l L L L L C4.1 GENERATING FACILITY SITE EVALUATIONS C4.0 SCENARIO II -FAIRBANKS POWER GENERATION An overall description of the Fairbanks region,followed by power plant siting criteria,a discussion of candidate siting areas,and the generic site description is provided in this section. The Fairbanks scenario (Figure C4-1)consists of a small diameter gas pipeline from Prudhoe Bay to Fairbanks,a gas distribution system within Fairbanks,an electrical generating facility in the Fairbanks vicinity, and transmission of 80 percent of the energy produced to Anchorage.Each of these components is discussed below. \ C4.1.1 Description of the Region ['." r- [,< [ r [ C" r L· r L C"" U C C L [ [ [ [ L Fairbanks is the regional conmercial center of interior Alaska.The communities surrounding Fairbanks (e.g.,Fox,North Pole)are located to the north,west,and southeast along the major transportation corridors. Fairbanks and these neighboring communities comprise the Fairbanks North Star Borough. P~sical Setting Fairbanks is located in a broad floodplain near the confluence of the Chena and Tanana Rivers.Two vegetation types are located in the region. The lowland spruce-hardwood forest is an interior forest of evergreen and deciduous trees dominated by black spruce which sometimes occurs in pure stands.The bottomland spruce-poplar forest,located adjacent to the Tanana River,is a tall,relatively dense,interior forest primarily of white spruce.The vegetation cover supports big game species of black and grizzly.bear,moose,small game,migratory game birds,furbearers, raptors,and other nongame mammals and birds.The Tanana River is an important spawning ground for anadromous salmon,arctic grayling,and whitefish. 26058 C4-1 r::.19 0:--:-::~,c-l [:--J (CTJ gn ~~Ii ~!l ..J f~.c-:J r---"\r---'1 -r-J ~~:-~,J,'._-J Jr=I.~~)~~~,.l ~-'(--ir,!",-,~,'.'':. POWER PLANT SITING AREA TRANSMISSION LINE CORRIDOR NATURAL GAS PIPf.LINE ;:ORRIDOR FIGURE C 4-1 ,,,,,,,, I \ \. \r \\. C1dof \ \ ·E ~ \ \ \ -\ \ \ \ \ ~a.y ~o\n\ \ \ \, \4",rsche\\ S60'drltl-.ctle\ s SCENARIO II FAIRBANKS POWER GENERATION EBASCO SERVICES INCORPORATED NORTH SLOPE GAS FEASIBILITY STUDY 7R6\ IFI- I I I uA o --- [ [-- [ [V [ [, l-' -" n L..; [ L b C C ~. C C [ , [ I 1.·._ [ In the winter,stagnant conditions occur often,with ver,y light winds and a strong temperature inversion in the v~rtical direction.These conditions bring about persistent air stagnation with ice fog and high levels of carbon monoxide.Ice fog,fonned through the concentration of pollutants from automobiles,power plants,and domestic heating,settles in the bowl-like depression in Fairbanks during these stagnant conditions.Annual temperatures are extreme and range from a mean minimum of -24°F in Januar,y to a mean maximum of 75°F in July.Extremes can range from -60°F to over 90°F.The annual average precipitation in Fairbanks is 11 inches,which includes roughly 70 inches of snow. Soc ia1 Profil e The 1980 population for the Fairbanks North Star Borough was approximately 54,000.Data on non-agricultural wage and salar,y employment indicates that in the Fairbanks area government is the largest economic sector followed by trade and transportation,communications,and utilities.Tourism is a major factor in the trade sector and this activity has grown in the last few years.Since 1979,the average annual unemployment rate has exceeded 10 percent (Alaska Department of Labor 1981)• C4.1.2 Siting Considerations .Siting a generating facility in the Fairbanks area is more complex than on the North Slope,because of the diversity in topograpny and population patterns.Preliminar,y siting efforts have concentrated on areas of industrial development with space for expansion that are already served by utility facilities and have adequate transportation access. C4.1.2.1 Land Status and Use Considerations Land use criteria for power plant siting in.the Fairbanks area are: 2605B C4-3 1)Compatibility with existing land uses.The Fairbanks area is bordered on the east and south by large milita~reservations. It is assumed that siting a power plant on these reservations would be precluded.While there are industrial areas within the city's immediate vicinity,sufficient space does not appear to .be available for major new electrical generating facilities. Power plant siting on the outskirts of Fairbanks must take into account compatibil ity with specific land ownership and uses, such as new residential developments,the University of Alaska campus,and the Fairbanks Airport and its zone of influence. Preferably,the site would be located within or adjacent to an existing industrialized area,isolated from residential and commercial population centers.Ideally,the potential generating facil ity site will be zoned for i.ndustri al development. 2)Adequate existing transportation system.Because the generating facility will involve a large number of construction and operating personnel,the surrounding road network will experience a significant increase in use.The development of new roads or highways to provide site development access to as yet undeveloped portions of the Fairbanks area is assumed to be undesirable,both from a cost standpoint and because new transportation facilities should be part of a comprehensive, rather than project-specific,pl anni ng process.Therefore it is assumed that the plant site must be located within a reasonably short distance of existing major roads or highways. 3)Compatibility with adjacent utility corridors.The location of the gas pipeline and electrical transmission lines to and from the plant must not interfere with existing utility corridors. However,it would be advantageous to locate new generating facilities to optimize the use of existing pipeline and transmission line rights-of-way,and to minimize,to the extent possible,the acquisition of new rights-of-way. 2605B C4-4 -[ -[ T- ro , -.[ [ r' Le -- [ r' [ L_l L..1 [ -.J :[ .--... -[ .-J '[ ~.J [ [; [. [ [ [ [' .----' [ r~.·". u r L \ c ~ C' F.';b ~ [ I [ ~. CL__ [ L.. L These land status and land use considerations suggest that the vicinity of North Pole,east of Fairbanks along the Alaska Highway,should be examined in more detail.candidate siting areas are disCussed in Section C4.1.3. C4.1.2.2 Geotechnical Considerations In selecting the location of the power generating facility,the major geotechnical criteria are: 1)Foundation soils with good bearing capacity and limited settlement potential. 2)Suitable site drainage. 3)Primarily non-frost susceptible foundation materials. 4)Foundation soils generally free of penmafrost or penmafrost with low ice content. These criteria are conmon to any industrial facility.In addition,given the imposed loads,the criteria allow the foundation design to consist of a concrete mat on a grade,with or without an engineered gravel pad. C4.1.2:3 Engineering Considerations In general,the power plant should be sited in relatively flat terrain, to minimize the amount of required grading and excavation.It will also minimize the potential for adverse environmental impacts due to erosion and transport of suspended solids to nearby waterw~s.The plant should also be sited above the 100-year floodplain of any major surface water resource in the area to avoid flooding. An area's seismic activity can also be an important site differentiating factor,with preference given to those sites located in regions of low 26058 C4-5 activity.In the Fairbanks area,however,all potential site locations fall within regions of high seismic activity (Zone 3).While this will not preclude development nor differentiate between the sites,it will increase construction costs as more material will be re~uired to insure plant foundation stability.The location and extent of all faults within the general Fairbanks area should be studied during the actual site selection process,as the plant should not be sited in close proximity to faul t 1i nes. Siting a power plant in close proximity to existing roads,railroads,and transmission lines minimizes the cost associated with these required connection links.Exhting electrical power will be necessary during the initial construction phase.Railroads will be used to transport large equipment as close to the site as possible,and trucks for the remaining distance.The site must have acces~to approximately 200 gpm of fresh water.'Thi s assumes that water injection for nitrogen oxides control will not be required,in order to avoid severe ice fogging. C4.l.2.4 Environmental Considerations Air Qual ity Meteorological conditions in Fairbanks playa very important role in detenmining the ambient air quality levels in the area.Analyses of the Fairbanks urban "heat island ll have shown that winds are generally light in the winter and that wind directions change dramatically in the vertical direction during the wintertime.During the winter months,the air near the ground is relatively cold,compared to the air aloft.This reduces mixing of the ~ir in the vertical direction,and when combined with relatively light winds,often leads to periods of air stagnation. In large part due to the winter stagnation conditions,the Fairbanks area 1S currently designated as a non-attainment area for carbon monoxide . (CO).Emissions of CO are largely due to automobiles.The State Department of Environmental Conservation and the Fairbanks North Star 26058 C4-6 :r r 'r: T" .[ r L [ LJ L [, [' o ; r l~..J [~ --...; .r L l..:J-. L --; L co r-- [._~ [ [: [. [ r: Lei r: L i. [ I L C C C, L, [ I L I C [ Borough Air Pollution Control Agency are implementing a plan to reduce the ambient CO mainly through the use of vehicle emission or traffic control techniques.In addition,relatively high levels of nitrogen oxides have recently been monitored in the Fairbanks area.Only an annual average nitrogen dioxide standard exists,but the short term measurements of nitrogen oxides are as high.as in major urban areas such as los Angeles. The installation and permitting of a major fuel-burning facility,such as a power plant,will require a careful analysis of the impact of its emissions on ambient air quality.The operators of such a facility must demonstrate that they will reduce,or offset,impacts of the power plant by reducing emission levels of CO at other sources. The protection of air quality in Fairbanks and its associated regulatory framework will 'pose a significant concern for the siting of a major power plant.However,these concerns will not preclude the development of at least some form of a natural gas fired power plant.Emissions of CO from this fuel source are relatively low,and any displacement of the burning of other fuels,such as coal or oil,will likely lead to improved air quality.This arises from the clean-burning nature of natural gas and from the fact that emissions from a major facility will be injected higher in the ~tmosphere (due to plume.buoyancy)than the displaced emissions.During the very stagnant conditons in midwinter,the plume from a power plant will likely remain well aloft with little mixing to the surface l~ers.The complex urban heat island and associated wind pattern will require a great deal of in-depth modeling and analysis to determine air quality impacts in terms that will withstand regulatory scrutiny. A large combustion turbine power plant must meet the existing New Source Perfonmance Standards and Best Available Control Technology.The nitrogen oxides limits will be the'most constraining atmospheric pollutant.The operation of the power plant will also consume a portion of the allowable deterioration in air quality for nitrogen oxides.While 2605B C4-7 it is possible that the power plant could be sited near Fairbanks,its installation would constrain other development efforts which also might consume a portion of the air quality increment. The Fairbanks area is also subjected to extended periods of wintertime ~ice fog,and the Alaska Department of Environmental Conservatio~will require the impact of any water vapor plumes to be carefully assessed.A combustion turbine power plant which uses water or steam injection techniques would have an adverse impact on the ice fog and icing deposition nearby.The nature,magnitude,and duration of plumes must be studied as well as the potential for beneficial impacts due to reduced combustion at other sources within the area.The combustion turbine facility would have to use water or steam injection techniques to meet the standards of Best Available Control Technology.The requirements for water injection will·be waived if and when it is determined that the subsequent formation of ice fog will cause a traffic hazard (40 CFR 60.332)• Other Environmental Considerations If more detailed siting analyses were to be conducted for Scenario II, the land use and air quality concerns previously discussed would provide the only signiJic~n~screening criteria to discriminate among alternative areas.At a more 1oc·al ized scale,there coul d be significant ecological or cultural resources affected,but judicious siting and project planning could avoid or mitigate such impacts.In this scenaricr,air quality and land use concerns will override other envirorvnental concerns because the si~ing effort would focus on previously disturbed areas or areas of low biological significance. C4.1.3 candidate Siting Areas Three general areas in the Fairbanks vicinity have been identified by local GVEA and Fairbanks Municipal Utility personnel as possible locations for an electrical generating facility:1)near the Chena Power 2605B C4-8 T' 'C -F' ( I C" I [ \ l C' L (, I .F [ ---_. ,[ L L-, L [ U [ C, E, [ I [ L I I [ IL _ LI., Plant in Fairbanks;2)in the North Pole area approximately 14 miles southeast of Fairbanks •.and 3)in the Fox area.approximately 9 miles north of Fairbanks.In addition.there may be additional potential 'generating facility sites in the Fairbanks region that have not yet been identified.Each of the identified areas is described below in order to provide a frame of reference for the subsequent description of the generic site. C4.l.3.l Chena Power Plant Area The Chena power plant is located in downtown Fairbanks.The plant is located on floodplain gravel.adjacent to the ChenaRiver.The area is nearly fully developed;expansion of the plant would be restricted by lack of available space. C4.1.3.2 Nort'h Pole Power Plant Area North Pole.Alaska is located 14 miles southeast of Fairbanks.on the Richardson Highway.near the Tanana River.The town of North Pole has a population of 470.although 6.000 people live in the municipal area. Golden Valley Electrical Association (GVEA)operates a 130 MW power plant outside of North Pole.Sufficient space exists for expansion of the plant.The topograp~in this area is generally flat.with little forest vegetation and sparse ground cover. C4.1.3.3Fox Area The town of Fox is located approximately nine miles north of Fairbanks. The area consists of extensive dredge tailings remaining from past gold mining operations in the Goldstream Creek Valley.The valley floor is generally flat.and is about 300 feet higher in elevation than Fairbanks. / 26058 C4-9 C4.1.4.Generic Site Description C4.1.4.1 Location and Access The generating site is assumed to be located within several miles of Fairbanks,along a major transportation route.The area is served by eXisting electrical transmission lines,so that electricity will be availab1 e duri ng the construction phase.A rail road spur extends to within several miles of the site;transportation of equipment over the remaining distance will be handled by truck.The small diameter pipeline route from Washington Creek (the southern end of the Utility Corridor from Prudhoe Bay)is over relatively gentle terrain and does not cross any major population centers,rivers,or other constraining features. C4.1.4.2 Size and Surface Characteristics The power plant site is approximately 65 acres in size.Because no construction camp will be used at the Fairbanks site,no additional acreage will be needed during the construction phase. The terrain in the vicinity of the site is flat to gently rolling.Very little vegetation is present because much of the area is already disturbed by existing .or previous development. C4.1.4.3 Water Source The water supply for plant operations will be provided by wells,and treated to bring the quality up to the necessary standards.The water table in the area is within 20 feet of the surface. C4.1.4.4 Soils and Foundations The generic site soils can be described as river floodplain sands and gravels with low ground ice content overlaid by approximately 5 feet of silt with low to moderate ice content.The site is free of permafrost. 2605B C4-l0 -:-1 [ ~r -r T' T'" "l __, -r Ii I . l-- ...-_.~ [ [ C -L -, [ --~ .1--, -t l-~-.... .-.i:__J -L' [--, [ [' [ [ co [ n- ~. [ [ C C (, Q [ ! [ l ; U L __ l A generic foundation design can be described as a 2 to 4-foot thick concrete mat overlying a 5-foot thick gravel pad.The overburden silts , will be excavated and spoiled. C4.2 GAS PIPELINE ROUTING EVALUATIONS A major component of the Fairbanks scenario is the construction of a small diameter gas pipeline from Prudhoe Bay to Fairbanks.The pipeline would have a 22-inch outside diameter with a maximum operating pressure of 1260 psig.The pipeline would have ten compressor stations for the medium load forecast,and three for the low load forecast.The pipeline would be buried for its entire length,and would have an operating temperature between 0 and 32°F.At the Yukon River the existing aerial crossing would be used.The pipeline would be routed within the Utility Corridor described in Section C3.2.1.1. C4.2.l Routing Considerations C4.2.1.1 Trans-Alaskan Pipeline System and Utility Corridor Restrictions Development restrictions imposed by TAPS and the Bureau of Land Management regarding transmission line construction from the North Slope to Fairbanks,discussed in Section C3.2.1.2,would also be applicable to the construction of the gas pipeline. C4.2.1.2 Engineering and Geotechnical Considerations Within the designated Utility Corridor,certain natural hazards exist which must be identified and considered during pipeline design.Such things as potential land slides,snow avalanche areas,earthquake faults, and erosion areas cause a threat to the pipeline integrity.'Thus,their location and potential magnitude is of primary concern.Additionally, the construction of a workpad and the interaction of the pipe with the soil thenmal regime and local hydrological conditions can significantly 2605B C4-1l alter nonna1 terrain stability.liquefaction,ice damming,aufeising, flooding,and thaw degradation are but a few concerns which must be addressed. Two major considerations of prima~importance to a safe design are the mitigation or prevention of frost heave and thaw settlement.Both these phenomena pose a hazard to a gas line by changing the delicate thermal balance in certain soil conditions along the route.A significant effort has been put into understanding these phenomena by A1yeska and Northwest Alaskan Pipeline Company (NWA),but additional research will be required to understand the specific interaction of any new design configuration or construction mode. Another potential pr~b1em concerns ~dditiona1 rights-of-way for future pipelines or other structures in the Atigun Pass area.This region is extremely narrow with little ground space available for pipeline development.Should other rights-of-way be envisioned they should be specified in advance so that the least costly alternative for all routes can be achieved. Some specific engineering criteria that must be considered during pipeline design include: 1)Minimize cross drainage blockage. 2)Avoid thaw unstable slopes as much as possible. 3)Minimize traversing areas with frost susceptible soil. 4)Minimize the haul distance for construction materials. 5)Provide year-round,all-weather access to the proposed pipeline. 6)Maximize route cost effectiveness. 7)Prevent degradation of the permafrost. 26058 C4-12 [ r [ r~ L r L~ r' I [ C r LJ.. lJ ,.....l l' r.J' L --,-) l .~~j L c [ [ r~ I:....~ [ [ L [ r~ L; C4.2.1.5 Environmental Considerations The environmental considerations discussed in Section C3.2.1.2 regarding transmission line construction from the North Slope to Fairbanks are generally applicable to the gas pipeline system.Additional considerations specific to the gas pipeline include: 1.Fish passage must not be blocked and flow velocity must not exceed the maximum allowable flow velocity for the fish species on a given stream.If these criteria cannot be met,a bridge must be installed. 2.Stream crossings must be able to withstand the pipeline design flood as determined for each stream.. 3.Chilled pipes in streams should not cause:a)lower stream temperature so as to alter biological regime of stream;b)slow spring breakup and delay of fish migration;c)early fall freeze-up .which would affect fish migration. 4.Chilled pipe in streams should not .aggravate or initiate aufeis buildup,if possible. 5.The original configuration,gradient,substrate, velocity,and surface flow of streams should not be altered. 6•.For fish,construction scheduling should avoid in-stream construction during critical sensitivity periods and be miniminal in moderate peri ods.. 7.Disturbance of wetlands should be minimized. B.The temperature of natural surface or groundwater should not be .changed significantly by the pipeline system or by aqy constructi on-rel ated acti viti es. C4.2.2 Applicability of the ANGTS Route The Alaska Natural Gas Transportation System (ANGTS)route is located within the Utility Corridor,set aside under Public Law Order 5150 in 1971.The Alaska Natural Gas Transportatio~Act (1976)and the Presidential Decision (1977),routed the 4B-inch diameter pipeline within this corrJdor,inclUding its infrastructure of roads,material sites,and ancilla~development.The corridor,from Washington Creek north to about 60 miles south of Prudhoe Bay,is managed by the Bureau of Land 2605B C4-13 Management under a land use plan centered around nodal development. Construction on State lands on the North Slope is further regulated through North Slope Borough ordinances.In addition,private property owners,native corporation lands,holders of sub-SUrface mineral rights, and Alyeska had numerous stipulations that had to be resolved. During the evolution of the gas pipeline routing,environmental, socioeconomic,and land use decisions dictated gas1ine locale.The selection process took several years while Northwest Alaskan Pipeline Company (NWA)developed the resources and environmental data base to be used for route selection and design criteria.NWA reviewed existing trans-Alaska oil pipeline and State highway construction data,resource agency files,and implemented biological,physical,and civil field programs to further delineate constraints. The infonmation provided by NWA was reviewed by State and Federal agency representatives through the State Office of Pipeline Coordinator and the Office of the Federal Inspector --a 'one window'coordinated effort where government resource and NWA personnel developed acceptable mitigation measures to be incorporated ;-n ANTGS route selection,project design activities,and construction stipulations. Through the processes described above,NMA minimized the crossings of the trans-Alaska oil pipeline,the Alyeska gas1ine (Prudhoe B~to Pump Station 4),and the Dalton Highway.The environmental and non-technical programs conducted since the environmental impact report (1976)have provided infonnation that altered the route to mitigate gasline impact on sensitive areas (e.g.,a white spruce stand on the Dietrich River was avoided).The gas1ine alignment has been reviewed in detail and the general route approved by resource agency personnel.It has also been reviewed by the public during the public participation program developed by NWA. 2605B C4-l4 J~ T T~ '[ r rl.,-.' r c [ ,.I C., b "J [ "",1 [ ! [ ~,j 'l _..1 L: [ [ c [ [ L [ n L.....J C L [ [ C C C [ , [ L L l _~ [ Based on the synopsis provided here.which is supported by years of field research by NWA.Alyeska.and resource agencies.it is reasonable to base the present st~dy on the assumption that the ANGTS route is a viable pipeline route for the transportation of gas from the North Slope to the Fairbanks area. C4.3 "GAS DISTRIBUTION SYSTEM FOR FAIRBANKS As indicated at the beginning of Chapter C4.SCenario II includes the development of a gas distribution system within Fairbanks.It is generally assumed that siting of this system would necessarily conform to good engineering practice in municipal environments.Specific engineering considerations related to facility location decisions are discussed in the following paragraphs. The overall system network would consist of a transmission lateral from a metering station at the main pipeline near Fox to one or several city gate stations.The metering station would be located where the gas pipeline crosses the Steese Highway about 2 miles northeast of Fox.From there a transmission line would run into Fairbanks in public rights-of-way adjacent to traveled roadways.to the city gate station(s}. The type of construction and location of district regulator stations will be detennined during final design.The options of underground vault versus aboveground station construction must be reviewed with respect to considerations of the availab1ility of public right-of-way.private easement.soil and groundwater characteristics.equipment operating capabilities and safety. The distribution lines would be laid in public rights-of-way at a depth of three feet to the top of the main.The lines would occupy the opposite side of the road from existing or proposed water mains. 2605B C4-l5 C4.4 TRANSMISSION FACILITY ROUTING EVALUATION The Fairbanks to Anchorage transmission line routing requirements for this scenario are the same as those for the North Slope.power generation scenario.The regional description,engineering and environmental considerations,and route des~ription presented in Section C3.2.2 of this report are also applicable to this scenario. 26058 C4-l6 r r~ [ L LJ -L __J L [ [ [ [ [ [ [ [ r '-J [ L C I.. C ~o c [ l !I.,__ C l [ C5.0 SCENARIO I II -KENAI POWER GENERATION The Kenai Power Generation scenario (Figure C5-l)is predicated on the development of a large diameter natural gas pipeline from Prudhoe Bay to a tidewater location near Kenai or Nikiski.This all-Alaska pipeline is being studied by others.Several assumptions regarding this facility are used in this report.A conditioning facility would be located at the tidewater site to remove impurities (mainly carbon dioxide)from the gas and liquefy the gas for transhipment to appropriate markets.The waste gas from this conditioning facility would be used to fuel the power generating facility discussed in this stuqy.Because the waste gas could only produce a small amount of electrical power,.it would be supplemented by sales gas from the pipeline to satisfy the requirements of both load forecasts.Electricity generated at this plant would be transmitted to Anchorage where 80 percent of the capacity would be used,by constructing new transmission lines.The remaining 20 percent capacity would be transmitted on to Fairbanks,via the upgraded Intertie. C5.l GENERATING FACILITY SITE EVALUATIONS Siting for the Kenai scenario focused on the coastal area between Kenai and Nikiski.This section gives an overview of the region,siting considerations,and the generic site description. C5.l.1 Description of the Region The Kenai-Nikiski area is on the western border of the Kenai Peninsula. Kenai is situated on the Sterling Highway at the mouth of the Kenai River.A corridor of industrial and rural residential development is situated along the North Kenai Road,which extends about 20 miles north of Kenai.The communities of Salamatof and Nikiski are included within this area.Major onshore facilities are "l.ocated in Nikiski,including refineries,an ammonia urea manufacturing plant,and natural gas liquefaction facility. 2605B C5-l J n \-.-- r~l J J ... '....•.~. ,. [J ],. ~J J J. 'J J' ]. ,J 1._... J. ] L_.. Je..- [ r [ [- [ [ [ GL, r: L [ E [ C U [ L [ L [ PhYsical Setting The Kenai-Nikiski area ranges in elevation from 100 to 150 feet above sea level.The shoreline on Cook Inlet is an abrupt,steep bluff.Much of the surface is marshes or muskeg bogs interspersed among numerous small lakes.Subsurface drainage ranges from good to poor,depending on the nature of underlying sediments and topography.Vegetation ranges from sedge-grass..moss cover on the wettest sites to mature stands of white spruce,white birch,aspen and cottonwood on the drier sites (Karl strom 1958)• Meteorological conditions in the area are generally favorable for the development of facilities such as power plants.The site ;s in an exposed coastal setting with generally moderate winds and good .~tmospheric dispersion conditions.Fog develops often in the area during the .winter months,but is relatively rare during the spring and summer months.Temperature extremes can range from -30°F to 80°F in the site area but the average winter temperature is 13°F while the average sUlll1ler temperature is 54°F. Social Profile Kenai is the largest economic center on the Kenai Peninsula.The 1980 populations at Kenai and Nikiski were 4,324 and 1,109.,respectively.The three largest economic sectors for the Kenai-Cook Inlet census subarea are manufacturing,government,and wholesale and retail trade,in that order.Unemployment is high due to the seasonality of construction and cOJllJ1ercial fishing and averaged 13 percent in 1981 (Alaska Department of Labor 1982). C5.1.2 Siting Considerations C5.1.2.1 Land Status and Use Considerations Because the Kenai-Nikiski area ;s already extensively industrialized, compatibility with existing land uses will not pose serious problems. 2605B C5-3 Detailed facility siting analyses for this scenari.o should address potential effects on locally significant land uses such as the Captain Cook Recreation Area at the north end of the North Kenai Road;existing and future rural residential developments;flight operations of the Kenai Municipal Airport;and the numerous pipeline rights-of~ay serving the area's refineries.New generating facilities might be sited to t~ke advantage of the existing Bernice Lake .Generating Station operated by the Chugach Electric Association. C5.1.2.2 Geotechnical Considerations In selecting the location for a generating facility,the key geotechnical criteria are foundation s011s with good bearing capacity and limited settlement potential,and suitable site drainage.These conditions are prevalent just north of Kenai adjacent to the North Kenai Road,where terrace and alluvial plain silts,sands.and gravels predominate.These terrace and alluvial deposits are of glacio-lacustrine and glacio-fluvial origin.The topography is flat to undulating. C5.1.2.3 Engineering Considerations General engineering considerations presented for both the North Slope and Fairbanks power generating scenarios (Sections 3.1.2.3 and 4.1.2.3)are also applicable to the Kenai area. All potential site locations in the Kenai area fall within regions of high seismic activity (Zone 3).While this will not preclude development,it will increase construction costs as more material will be required to insure plant foundation stability.The site must also have access to approximately 1000 gpm of water because water or steam injection for the control of nitrogen oxides will likely be required. 2605B C5-4 I~ -[ 'T~ r ~ I .l""~ L f~ L" [ l'".- [' .~ ['~ F--~ -L _.J [ ..~ L _...J L [ [ [ [ [ [ [ L. n L.J [ o [J [ C l ~, --i' [ L [ [ C5.l.2.4 Environmental Considerations Air Quality As is typical of many exposed coastal locations,the air quality and meteorological conditions are generally favorable to the development of facilities such as power plants.It is not likely that an intense "marine layer",which may restrict dispersion of pollutants,develops in this area.The air quality attains the applicable ambient standards,but the locale is burdened with several existing petroleum refinery emissions.A new natural gas-fired power plant could probably be sited in the area with the use of appropriate emissions controls including water or steam injection to reduce nitrogen oxides emission.The impact of water vapor emissions on the fonmation of fog must also be considered.The power plant must be carefully sited in order to avoid adding to the air quality impacts of th.e existing facilities. Other Environmental Considerations The Kenai-Nikiski industrial corridor,by virtue of its past development, is generally not an ecologically important land area.The Kenai National Wildlife Refuge,a few miles to the east,is a major environmental resource which provides habitat protection for both resident and migratory wildlife.However,there are other local environmental concerns which must be con"sidered in siting additional power generating facilities in the area.Effects on local residential developments, recreational facilities and tourism must be addressed on a site-specific basis,but probably would not preclude site development in this rural i ndustri al area. C5.l.3 Generic Site Description C5.l.3.l Location and Access Because the generating facility will be using waste gas and sales gas from a gas conditioning facility,the plants will be located in close 2605B C5-5 C5.1.3.3 Water Source The power plant site is approximately 65 acres in size. camp will be used at the site because sufficient local be available. proximity to each other.The generic site is in the general Kenai-Ni ki ski area withi n a few miles of the coast.The area is served by existing electrical transmission lines and access roads. C5.1.3.2 Size and Surface Characteristics No constructi on housing appears to The terrain in the site vicinity is flat to gently rolling.Vegetation consists generally of sparse stands of shallow-rooted trees with local patches of denser forest and shrub. Groundwater will be used for all plant water needs.The water will be treated to reach the qual ity needed for make-up water.Groundwater is generally available in the Nikiski area,so that water supply will not pose a significant constraint to development. C5.l.3.4 Soils and Foundations Generic site topographY and soils consist of flat to undulating topographY and well-drained granular materials (i.e.,sands and gravel). The foundation will consist of a concrete mat 2 to 4 feet thick on grade.Other than clearing and grubbing,and perhaps some minor grading, no other foundation work will be required. C5.2 TRANSMISSION FACILITY ROUTING EVALUATIONS All of the electricity generated at the Kenai/Nikiski site would be transmitted to Anchorage via new transmission lines.Eighty percent of the generated capacity would be used in Anchorage;the remaining 20 26058 C5-6 I~ r r [ L l ~ [ f~ '-c,o [ [ C [ [ ..1 [ L~-j L ~~.j L _•._.1 [ [ [ r-- [ [ [ [' [ P L r L [ B C C o [,__ [ [ L [ percent woul d be transmitted on to Fairbanks vi a the upgraded I nte rti e. The Kenai-Anchorage corridor is discussed first below,followed by the Anchorage-Fairbanks corridor. C5.2.l Kenai-Anchorage Corridor C5.2.l.l Description of the Corridor The transmission corridor between Kenai and Anchorage is maintained by the Chugach Electric Association (CEA).The corridor generally parallels the Sterling Highw~across the Kenai Peninsula to the upper end of Turnagain Arm at Portage.It is located on a narrow bench along the highway traversing the north shore of Turnagain Arm as far west as Indian Creek,where it turns north to traverse Powerline Pass in the Chugach Mountains.The corridor then descends to the northwest into Anchorage. PhYsical setting The corridor lies within the Coastal Trough and Pacific Border Ranges phYsiographic provinces.That portion of the corridor which lies north of Turnagain Arm is within the Cook Inlet-Susitna Lowland subdivision of the Coastal Trough province.This is a glaciated lowland containing areas of ground moraine and stagnant ice topography,drumlin fields, eskers and outwaSh plains.The lowland is generally less than 500 feet above sea level.That portion of the corridor to the ~outh of Turnagain Arm lies within the Kenai-Chugach Mountains subdivision of the Coastal Trough province.The Kenai Mountain range has been heavily glaciated and is characterized by rock-basin lakes,U-shaped valleys,and incised ravines.The Kenai Lowlands extend west of the mountains and are drained by the Kenai Ri ver (Wahrhaftig 1965). The Kenai River system is a major phYsiographic feature of the region. The Kenai River and its tributaries are important spawning grounds for king,sockeye,and silver salmon.The vegetation of the Kenai River watershed lies in a transition ~one between the Pacific rainforest biome and the Arctic-alpine biome.Vegetation types within this zone include the coastal western hemlock-Sitka spruce forest,upland spruce-hardwoods, 2605B C5-7 lowland spruce-hardwoods,high brush,muskeg,and tundra.These habitat types support an abundance and variety of bird and mammal populations CU.S.A~Corps of Engineers 1978). The climate of the studY corridor varies with changes in the topography and relationship to the Kenai Mountain range.The climate,in general, is not as wet as that characteristic of the maritime climatic region and is not as extreme as the continental climate of interior Alaska.Annual precipitation ranges from 15 inches in Anchorage to 23 inches along the western coast of the Kenai Peninsula.Temperatures in Kenai average 13° F in winter and 54°F in summer CU.S.Army Corps of Engineers 1978). Soci a1 Profi 1e The studY corridor falls within the jurisdiction of the Kenai Peninsula Borough.In 1980 the population of the borough was 25,282 with Soldotna and Kenai the major communities within the corridor.The area around Kenai,Soldotna,and Sterling has undergone rapid subdivision.Increased tourism and recreational activity have contributed to the growth in Soldotna and,to a lesser extent,in Ste·r1ing.Growth in population and employment has been i nf1 uenced strongly by growth in the hydrocarbon industr,y.As a result of petroleum and natural gas activity,the peninsula has experienced extensive development,including pipelines, marine tennina1s,refjneries and other processing facilities.The food and kindred products industr,y is important to the regional economy, particularly with regard to fish processing.Unemployment is currently.. and historically has been high,due in part to seasonal variations in the 1abor market. The studY corridor falls with the Chugach National Forest,administered by the U.S.Forest Service,and the Kenai National Moose Range, administered by the U.S.Fish and Wildlife Service.These areas offer numerous recreational opportunities to residents of the peninsula as well as of Anchorage. 2605B C5 ..8 [ [: r' .r: [' [ r flw 'f'._.0 :[ [J C B ..J [ L -..•.j [ _eJ C [ r~ L, C" G.c.~t~~~ fl.;U C C [ l._ [ C_ L l ..·· [ i_ C5.2.1.2 Existing Transmission Facilities Chugach Electric Association,Inc.presently operates a 115 kV line from Anchorage to Soldotna and Nikiski (Bernice Lake),via Portage and Quartz Creek,and a 69 kV line between Quartz Creek and Soldotna which continues to Homer.These transmission lines cannot be considered as part of the system evaluated in this feasibility stu~because their load carr,ying capacity is a small fraction of the considered electrical requirements. The established rights-of-w~associated with these lines have been considered to the maximum extent possible,however. Engineering Considerations Because of the relatively short distance there is no need for intenmediate switching stations between Kenai and Anchorage,even in the medium forecast scenario.The two circuits of the transmission line req~ire a 440 foot wideright-of-w~or two 220 foot wide corridors. Should less than 440 feet be available for the entire length,the two circuits m~be routed for short distances on single towers,though this would lower the avai1abi1ty of the system. Environmental Considerations Several environmental protection factors should be taken into account in pl ann'ing and desi gn of an expanded right-of-way and,in certain areas, for new rights-of-way. To minimize soil erosion,steep slopes and highly erodible soils should be avoided where possible.Existing access roads should be used at all possible locations.New access roads should incorporate adequate drainage systems to minimize erosion of the road surface. The selected route should minimize the number of additional stream crossings.Where stream crossings are unavoidable,the towers should be set back a minimum distance from streambanks and a buffer strip of 26058 C5-9 vegetation should be retained along water bodies to minimize siltation of streams.Equi pment shoul d cross streams usi ng well-desi gned bri dges that protect the stream bank. The present route passes through a small area of caribou habitat near Kenai (University of Alaska 1974).Little alteration of caribou habitat will result from construction of the transmission line because the animal utilizes cover types that require little if any clearing.The route also passes adjacent to Dall Sheep and Mountain Goat range between Cooper Landing and Saxton,but does not extend into the rangeland at any location.Much of the route between Kenai and Cooper Landing is within Moose fall and winter rangeland.However,because the moose utilizes ma~different habitat types,it will be the least adversely affected by habitat alterations (Spenc~r and Chatelain 1953).Where the proposed route crosses heavily forested areas,the moose will benefit from .additional clearing of the right-of-way and the subsequent establishment of a subc1imax community (Leopold and Darling 1953). Fisheries resources can be protected by closely coordinating construction activity with the Alaska Department of Fish and Game.Equipment should not cross streams without bridges when eggs or fry are in the streambed. C5.2.1.4 Route Description Two 500 kV circuits are required for both the medium and low electrical demand forecasts.No intennediate switching stations are required but series compensation is required for the medium load forecast. The line would originate at the powerhouse in the Kenai area.Routed in an easterly direction,it would parallel the 115 kV Chugach line.It would follow the Kenai River Valley,the north shore of Kenai Lake,and would tur.n northeast along Quartz Creek.At the East Fork of the Bend River it would make a sharp turn,and follow the river until the Granite Creek Valley.The line would then follow the Seward Highw~around Turnagain Ann to Girdwood. 2605B C5-10 --[ f r ·r -r l~ L r Lc r-··.. L F ·U·J·; ; C [ L ~.--' [ [ _'i L [~ [ [ r~ [ C· [ [ [ [ [ r' L [ [j U C B [ L_ [ C [ l... C· The section between Girdwood and Rainbow Creek is the most difficult as fa r as eng i neeri ng is concerned.In thi s report it is a sumed that the line wQuld be located on the mountain side,which slopes to 1000 feet in elevation with an average grade in excess of 50 percent and then,between 1000 and 2000 feet at a 20 percent slope.From Rainbow Creek to Anchorage the area is flat and sufficiently wide to accommodate the line. In order to avoid the Girdwood to Rainbow Creek section,other route alternatives will be investigated.All alternatives would carry the power using a Turnagain Arm crossing with undersea cables from Windy Point to Bird Creek.From the Bird Creek table termination three alternative routings will be investigated:1)traversing Bird Creek Pass into the valley of the North Fork of Ship Creek;2)crossing from Girdwood to Penguin Creek over the mountains and following Bird Creek Pass as outlined above;and 3)following Penguin Creek across th~ mountains at an elevation of less than 3000 feet into Bird Creek and then following the existing Chugach line through Powerline Pass to Anchorage. C5.2.2 Anchorage-Fairbanks Corridor The Fairbanks to Anchorage transmission line routing requirements for this scenario are the same as those for the North Slope and Fairbanks power generation scenarios.The regional description,engineering and environmental consjderations,and route description presented in Section C3.2.2 of this report are also applicable to Scenario III. 2605B C5-11 [ [- [- [ [ f'· [ ru [ I C \ C [} 5 [ 1- [.~ -'-" ,-- L I L [ C6.0 REFERENCES Alaska Department of Labor,Research and Analysis section.1981. Alaska economic trends.Juneau,Alaska. Alaska Department of Labor,Research and Analysis Section.1982. Personal communication. Brown,J.1976.Ecological and Environmental Consequences of Off-Road Traffic in Northern Regions.U.S.Department of the Interior. Bureau of Land Management.1980.The Utility Corridor,Land Use Decisions.U.S.Department of the Interior,Bureau of Land Management,Fairbanks,Alaska. Commonwealth Associates Inc.1982.Environmental Assessment Report for the Anchorage-Fairbanks Transmission Intertie.Alaska Power Authority,Anchorage Alaska. Karlstrom,T.1958.Ground conditions and surficial geology of the Kenai-Kasilof area Kenai Peninsula,South-Central Alaska.U.S. Geological Survey map scale 1:63,360. Leopold,A.and F.Darling.1953.Effects of Land Use on Moose and Caribou in Alaska.Transactions of the North American Wildlife· Conference.18:553-582. North Slope Borough.1978.Coastal Management Program,Prudhoe Bay Area. North Slope Borough,Barrow ,Alaska. Roseneau,D.G.,C.E.Tull,and R.W.Nelson.1981.Protection strategies for peregrine falcons and other raptors along the planned Northwest Alaskan gas pipeline route.Unpub.rep.by LGL Alaska Res.Assoc., Inc.,Fairbanks,for Northwest Alaskan Pipeline Co.and Fluor Northwest,Inc.,Fairbanks.' Spencer,D.L.,and E.F.Chatelain.1953.Progress in the Management of the Moose of South central Alaska.Transactions of the North American Wildlife Conference.18:539-552. U.S'.Army Corps of Engineers,Alaska District.1978.Kenai River Review. Anchorage,Alaska. University of Alaska,Arctic Environmental Information and Data Center. 1974.Alaska Regional Profiles,Southcentral Region.State of Alaska,Office of the Governor,Juneau,Alaska. University of Alaska,Arctic Environmental Information and Data Center. 1978a.Deadhorse.U.S.Department of the Interior.' 2605B C6-1 ~[ University of Alaska,Arctic Environmental Infonmation and Data center.l' 1978b.The Region.U.S.Department of the Interior.l Wahrhaftig,Clyde.1965.P~siographic divisions of Alaska.Geological ['." Survey Professional Paper 482.Washington,D.C.~~. r T ( IL 26058 C6-2 L G [', [~'~. oJ b L [ L L [ '---_.... L11 c--:J :-l I::-:J r--t,.rTJ (C""J r--:~.~ I.. crJ C------:J cr:-J r···- EBASCO SERVICES INCORPORATED ,..,,, \ E \-\~rst.n4S\\ Soo-;".I~to.\ s SCENARIO m FIGURE C 5-1 \ \, \ \ \,. .......~.-_.-\ \ \ KENAI POWER GENERATION NORTH SLOPE GAS FEASIBILITY STUDY n 1/107 PIPELINE SITING AREAl uAB o --- Ha.lkoU ••.••••••• I ••••••• [. oo APPENDIX D c c [ [ [ [ [ nu (~ U C 8 ~ o u C B C 8 C 25608 APPENDIX D REPORT ON TRANSMISSION SYST91 DESIGN JANUARY 1983 TABLE OF CONTENTS Oi 02.2 SPECIAL PROBLEMS PERTAINING TO THE NORTH SLOPE PAGE 01-1 02-1 02-1 02-1 02-1 02-2 02-2 02-3 03-1 03-1 03-1 03-1 03-2 03-2 03-2 03-3 03-3 03-3 03-3 03-9 03-9 03-9 04-1 04-1 04-2 04-2 04-2 04-2 04-4 04-5 ... . . . .. 02.2.1 Contamination Mitigation in the Prudhoe Bay Area . . . . . . . . . . . . . • . 02.2.2 Grounding •••••••••••••••• Meteorological and Climatic Conditions Mitigation of Contamination Transmission Voltages ••• Conductors and Bundle Types •••• Cl earances ••••••••••••• Insulators •••••.•••••••• Safety Factors and Strength Requirements of Support Structures . • • • • • • • • 03.2.8 Lightning Protection and Grounding ••• 03.2.9 Oistance Between Parallel Lines,Route and Pipeline •••••••••• 03.2.10 Corona Criteria for Conductor Size ••• 03.2.11 Radio and Television Interference: RI and TVI •• 03.2.1 03.2.2 03.2.3 03.2.4 03.2.5 03.2.6 03.2.7 02.1.1 One-L i ne Oi agram • • • • 02.1.2 Auxiliary Power Source. 04.2.J Conductor Selection ••••••• 04.2.1.1 Current Carrying Criteria ••••••• 04.2.1.2 Acceptable Conductor Gradient. .04.2.1.3 Mechanical Oesign Selection of. Conductor,Towers and the Ruling Span ••••••••• 04.2.1.4 Ri ver Crossi ngs • • • • • • • • • • • D3.1 GENERAL............ . • • • . . • • • 03.2 OESI GN CO NSI OERA TIONS • . • • • • • • • • • • • 04.1 GENERAL •••••••••••••••••• 04.2 OESIGN OF THE 500 kV TRANSMISSION LINES. 03.0 NORTH SLOPE TO ANCHORAGE TRANSMISSION SYSTEM OESIGN • 04.0 TRANSMISSION OESIGN (HAROWARE)•••.•••• 01.0 INTROOUCTION •••••••• 02.0 FACILITIES AT NORTH SLOPE. 02.1 SUBSTATION ••••• 2560B [' 8 G.'". C b., [ C C L ~;.:... lo [ PAGE 04-6 04-7 04-8 04-8 04-8 04-9 04-9 04-9 05-1 05-1 05-3 • •e _ LINE • • • • •.-.• . • • • • • • • . . . TABLE OF CONTENTS (continued) 04.6.1 Fairbanks Substation •••••••••• 04.6.2 Anchorage Substation ••••••• 04.6.3 Series and Parallel Compensation 04.5 DESIGN DATA OF THE 345 kV TRANSMISSION LINES •• 04.6 SUBSTATIONS AND SWITCHING STATIONS ••••• 04.3 DESIGN DATA OF THE 765 kV TRANSMISSION LINE ••••• 04.4 OESI GN DATA OF THE +350 kV BI POLAR DC TRANSMISSION 04.7 COMMUNICATION SYSTEM •••• 05.0 SYSTEM DESIGN (LOAD FLOW STUDIES)• 05.1 GENERAL ••••••••••• 05.2 PERFORMANCE STUDIES •••• 05.2.1 Alternatives A and AA -1400 MW Generation at Prudhoe Bay,Two 500 kV Lines from Prudhoe Bay to Anchorage and the 345 kV Intertie In Parallel Between Fairbanks and Anchorage 05-3 05.2.2 Alternative B -1400 MW Generation at Prudhoe Bay,Two 500 kV Lines Between Prudhoe Bay and Fairbanks and Three 345 kV Lines Between Fai rbanks and Anchorage • • •05-10 05.2.3 Alternative C -1400 MW Generation at Prudhoe Bay,Two 765 kV Lines Between Prudhoe Bay and Fairbanks and Three 345 kV Lines Between Fairbanks and Anchorage • • • • • •05-13 05.2.4 Alternative 0 -1400 MW Generation at Prudhoe Bay,Two Bi polar +350 kV DC Lines Between Prudhoe Bay and Fii rbanks and Three 345 kV Lines Between Fairbanks and Anchorage 05-16 05.2.4.1 Description of the System.• •05-16 05.2.4.2 Perfonmance Studies.• • • • •05-20 [ r~ t~ U C •.J 05.2.5 Alternative E -700 MW Generation at Prudhoe Bay,Two 345 kV Lines from Prudhoe Bay to Anchorage • • • • • • • • • • • • •05-22 05.2.6 Alternative F -700 MW Generation at Prudhoe Bay,Two 500 kV Lines Between Prudhoe Bay and Fairbanks and Two 345 kV Lines Between Fairbanks and Anchorage • • • • • •••05-23 Oi i L .J L r- C> L [ t' [' R· l-; c·· G C C Q [ [ C U [ TABLE OF CONTENTS (continued) PAGE 06.0 CONCLUSIONS •..·.. ...· · ·····06-1 07.0 SAG AND TENSION CALCULATIONS · · · · · . ... ..07-1 08.0 FIGURES •.·..··· · ···... . 08-1 09.0 REFERENCES . . .··· ···· · 09-1 Oiii TOWER OVERLOAD CAPACITY FACTORS (OFCs) OVERLOAD CAPACITY FACTORS (OFCs)OF GUYS OF . GUYED TOWERS ELECTROSTATIC FIELD INTENSITY LIMITS AT . 1 METER ABOVE GROUND Tabl e No. 0-1 0-2 0-3 0-4 0-5 0-6 0-7 P-8 LIST OF TABLES Title CONDUCTORS CONSIDERED • • . CLEARANCES REQUIRED • • • INSULATORS CONSIDERED • Nt1PAC IT!ES SYMBOLS .. Div .... . .. Page 03-4 03-5 03-6 03-7 03-8 03-10 04-3 08-1 T·L r- .\. r-) r [, ·r L C,.,'-< L [; LI L -' r-_.I -[ _.J :L .....; LJ -L LOAD FLOW ••••••••••• • • • • • • • • •D8-5 No Generation at Prudhoe Bay.One Line Segment Open North of Fairbanks ONE LINE SCHEMATIC WITH IMPEDANCES • • • • • • • •D8-3 1400 MW Capacity at Prudhoe Bay;500 kV Transmission System;345 kV Intertie in Parallel Between Fairbanks and Anchorage; No Intermediate Transformation at Fa;rbanks 1400 MW Capacity at Prudhoe Bay;500 kY Transmission System;345 kY Intertie in Parallel Between .Fairbanks and Anchorage; Intermediate 138 kV Bus at Fairbanks Page D8-2.... • . • • .D8-4 Normal LIST OF FIGURES LOAD FLOW • • • • • • • • • • • No Generation at Prudhoe Bay. System Configuration ONE LINE SCHEMATIC WITH IMPEDANCES Title D-3 D-2 D-4 D-l Figure No. D-5 D-6 D-7 D-8 D-9 2560B LOAD FLOW • • • • • • • • • • • • • • • • • •••D8-6 No Generation at Prudhoe Bay.One Line Segment Open North of Gold Creek LOAD FLOW ••••••••• • • • • • • • • • • •D8-7 No Generation at Prudhoe Bay.One Line Segment Open North of Gold Creek Less One Reactor ONE LINE SCHEMATIC WITH IMPEDANCES • • • • • •••D8-8 No Generation at prudhoe Bay.The 345 kV Intertie Opened at Anchorage LOAD FLOW •••••••••••• • • • • • • • •08-9 No Generation at Prudhoe Bay.The 345 kV Intertie Opened at Anchorage,Less One Reactor LOAD FLOW • • • • • • • • • • • • • • • • • •••D8-10 No Generation at Prudhoe Bay.One Line Segment-Opened North of Galbraith Lake Dv LOAD FLOW • • • • • • • • • • • • • • • • • •••08-13 1400 MW Generation at Prudhoe Bay.One Line Segment Out of Service North of Fairbanks LOAD FLOW • • • • • • • • • • • • • • • • • • • •08-17 1400 MW Generation at Prudhoe Bay.One o of,the 500-345 kV Transfonners Out of ,Service at Fairbanks ONE LINE SCHEMATIC WITH IMPEDANCES.• •08-18 1400 MW capacity at Prudhoe Bay;Two 500 kV Transmission Line Circuits Between Prudhoe Bay and Fairbanks and Three 345 kV Transmission Line Circuits Between Fairbanks and Anchorage. LOAD FLOW • • • • • • • • • • • • • • • • • • • •08-14 1400 MW Generation at Prudhoe Bay.One Line Segment Out of Service South of Prudhoe Bay LOAD FLOW •••• • • • • • •.'.• • • • • •••08-1 5 1400 MW Generation at Prudhoe Bay.One 500 kV Line Segment Out of Service South of Fairbanks c [ fj e,I ~""J L [ , L _,J 1, E,J [ c r''" [ r r-" L t' r~ ,L~j 'rL Page 08-11 08-16 ••08-12 ••08-19 .... . . Nonna1 Nonna1 System 1400 MW Generation at Prudhoe Bay.One 500 kV Line Segment Out of Service North of Anchorage LIST OF FIGURES (continued) LOAD FLOW • • • . • . . • . • . • • . • . • • Dvi LOAD FLOW • • • • • • • • • • • • • 1400 MW Generation at Prudhoe Bay. System Configuration LOAD FLOW • • • • • • • • • • • • • • • • No Generation at Prudhoe Bay.One Line' Segment Opened North of Galbraith Lake, Less One Reactor Title LOAD FLOW • • • • • • • • • • • No Generation at Prudhoe Bay. Configuration 0-10 0-12 0-11' 0-13 0-16 0-15 0-14 0-17 0-18 Figure No. [ [' [- [ [ r [ n '-' Fi gure No. 0-19 0-20 0-21 0-22 LIST OF FIGURES (continued) Title Page LOAD FLOW • • • •••• • • • • • • • • •08-20 1400 MW Generati on at Prudhoe Bay.Nonnal System Configuration.Generator Bus Voltage 1.05 p.u. LOAD FLOW • •'.• • • • • • • • • • • • • • • • •,08-21 1400 MW Generation at Prudhoe Bay.Nonnal System Configuration.Generator Bus Voltage 1.00 p.u. LOAD FLOW • • • • • • • • • • • • • • • • • •••08-22 1400 MW,Generation at Prudhoe Bay.One Line Segment Ou t 0 f Se rvi ce South of Prudhoe Bay.Generator Bus Voltage 1.05 p.u. LOAD FLOW • • • • • • • • • • • • • • • • • •••08-23 1400 MW Generati on at Prudhoe Bay.One Line Segment Out of Service South of Prudhoe Bay.Generator Bus Voltage 1.00 p.u. Ovii LOAD FLOW •.•• • • • • • • • • • • • •08-27 1400 MW Generation at Prudhoe Bay.Nonnal System Configuration, LOAD FLOW • • • • • • • • • • • • • • • •'.•••08-24 1400 MW Generation at Prudhoe Bay;One Line Segment Out of Service North of Anchorage LOAD FLOW • • • • • • • • • • • • • • • • • •08-25 1400 MW Generation at Prudhoe Bay;Two 765 kV Transmission Line Circuits Between Prudhoe Bay and Fa i rbanks and Three 345 kV Transmi 5si on Li ne Ci rcuits between Fai rbanks and Anchorage, •08-28 • • •••08-26 One 765 kV • • • • 0 • Nomal ONE LINE SCHEMATIC WITH IMPEDANCES ••,•••••0 08-29 1400 MW capacity at Prudhoe Bay;HVOC Transmission Between Prudhoe Bay and Fairbanks and Three 345 kV Transmission Line Circuits Between Fairbanks and Anchorage. LOAD FLOW • • • • • • • • • • • • • 1400 MW Generation at Prudhoe Bay; Line Segment South of Prudhoe Bay Out of Service LOAD FLOW..• • • • • • • • • • No generation at Prudhoe Bay. System Configuration 0-23 0-25 0-24 0-28 0-27 0-26 r; c, c c c [ L [ t...• o [ LIST OF FIGURES (continued) ONE LINE SCHEMATIC WITH IMPEDANCES • • • • • •D8-35 700 MW Capacity at Prudhoe Bay;345 kV lransmission System with Series Compensation LOAD FLOW • • • • • • • • • • • • • • • • •D8-33 1400 MW Generation at Prudhoe Bay;HVDC Transmission Between Prudhoe Bay and Fairbanks. Nonmal System Configuration;Voltage Raised by 5%at Fairbanks LOAD FLOW • • • • • • • • • • • • • • • • • • • •D8-34 1400 MW Generation at Prudhoe Bay;HVDC Transmission Between Prudhoe Bay and Fairbanks. One 345 kV Li ne Segment Out of Service North of Anchorage;Voltage Raised by 5%at Fairbanks r' L [. C., [ C -, L C .J L ..J L.,-..) L .~J l -r r r T' -~. f-i'~ l r-- L~ Page D8-30 D8-37 •D8-36 • 0 D8-38 .... ... .. eo.• • LOAD FLOW • • • • • • • • • • • • • • No Generation at Prudhoe Bay;Nonmal System Configuration LOAD FLOW • • • • • •0 • • • • • • • • • • •••D8-32 1400 MW Generation at Prudhoe Bay;HVDC Transmission Between Prudhoe Bay and Fairbanks and One 345 kV Line Segment Out of Service North of Anchorage Dviii Title LOAD FLOW • • • • • • • • • •0 • • • • • No Power Transfer Between Fairbanks and' Anchorage.Nonma1 System Configuration LOAD FLOW • • • • • • • • • •0 • • • • • •D8-31 1400 MW Capacity at Prudhoe Bay;HVDC Transmission Between Prudhoe Bay and Fairbanks. Nonma1 System Configuration LOAD FLOW • • • • • • • • • • • • • • • • No Generation at Prudhoe Bay;One Line Segment Opened North of Fairbanks with the Loss of an Additional Reactor LOAD FLOW • •0 • • • • • • • • • • • • No Generation at Prudhoe Bay;One Line Segment Opened North of Fairbanks D-33 D-31 D-30 D-32 D-35 D-29 D-34 D-37 D-36 Fi gure No. LOAD FLOW • • • • • • • • • • • • • • • • • •••08-40 700 MW Generation at Prudhoe Bay,One Line Segment Out of Service South of Prudhoe Bay ONE LINE SCHEMATIC WITH IMPEDANCES • • • • • •08-41 700 MW Capacity at Prudhoe Bay;500 kV Transmission Between Prudhoe Bay and Fairbanks and 345 kV Transmission with Series Compensation Between Fairbanks and Anchorage . No nna 1 •'.•••08-42 •••08-43 Page 08-39... Nonna1 Nonna1 .. .. LOAD FLOW • • • • • • • • • • • No Generation at Prudhoe Bay. System Configuration LIST OF FIGURES (continued) LOAD FLOW • • • • • • • • • • • • • 700 MW Generation at Prudhoe Bay. System Configuration LOAD FLOW • • • • • • • • • • • • • 700 MW Generation at Prudhoe Bay. System Configuration Title D-39 0-41 D-38 0-40 0-42 Fi gure No. r: L [ L-" [- [ [ r"-"- L~ ["' _J r l-.J 0-43 0-44 LOAD FLOW • • • • • • • • • • • • • • • • • •••08-44 700 MW Generation at Prudhoe Bay,One Line Segment Out of Service South of Prudhoe Bay LOAD FLOW • • • • • • • • • • • • • •.'• • •••08-45 700 MW Generation at Prudhoe Bay,One Line Segment Out of Service North of Anchorage Dix [ [ [ [.- f '''·· > [ [ F,-,.,J rL t. [j C e G c [ [ [ L __ [ D1.0 INTRODUCTION In the descriptions that follow,the North Slope-Fairbanks-Anchorage system,medium load forecast level,is used as a model.However,many of the findings are directly applicable to the Fairbanks and Kenai generation scenarios and to the low load forecast cases. An important aspect of this design study is that the load carrying capacity of the lines is not the limiting factor of this transmission system.Rather,the critical factor is the stability of the system, and the system was designed around this factor.The North Slope medium forecast scenario concentrates the bulk of Alaska's generation at one location,from which the greatest part of the power has to be transmitted over a long (almost 800 miles)line to the bulk of the load at Anchorage.By the time the system is fully developed,all other power generation stations connected to the system will be less than 50% of the single large power station located at Prudhoe Bay and most of them will be even further than 800 miles away from it.Therefore,in addition to the criteria listed in Section 2.3,performance considerations and criteria had to be introduced into the design process.In the following pages,these additional considerations/criteria are also described. Sections D2.0 through D4.0 deal with the hardware aspects of the transmission system and Section D5 summarizes the findings of the system des.ign.Section D6 presents conclusions from the preceding studies.Section D7.0 presents the results of the sag and tension calculations and section D8.0 contains all Appendix D figures. Dl-l 2560B _._-. [. r~ L.- [-. [-- t, ['- r- Li . C L [ i __ (J C C· L [ [ [ I C [ 02.0 FACILITIES AT NORTH SLOPE 02.1 SUBSTATION 02.1.1 One-Line Oiagram The line diagram for the North Slope Substation is shown in Figure 2-3.1/There are 15 generators in the fully developed plan,with each two connected,through 15kV iso-phase buses,to one 250/125/125 MVA,138/13.8/13.8 kV three-wi ndi ng transfonner,except one generator which is connected to a two-winding 125 MVA transfonner.Each generator can be synchronized to the 345 kV bus through its 13.8 kV circuit breaker installed inside the plant.Four 450/600/750 MVA OA/OAF/OAF,138/525 (or 765)kV step-up transformers,two connected in parallel,feed the two transmission line circuits heading south to Fairbanks.The 138 kV bus,whenever reliability considerations pennit, uses breaker-and-a-half arrangements.The series capacitors and the shunt reactors are on the 1 ine side of the 500 (or 765)kV circuit breakers protecting the lines.,The arrangement enables the buswork of the substation to be expanded gradually,as can be seen from Figure 2-4,in which the first stage of development is displayed. 02.1.2 Auxiliary Power Source An auxiliary 69 kV tie line should be negotiated with SOHIO to avoid installing additional diesel generators for black start.The tie and 13.8 kV distribution will be developed as each plant is built. 1/Fi gures 2-3 and 2-4 are in the main text. 02-1 2560B 02.2 SPECIAL PROBLEMS PERTAINING TO THE NORTH SLOPE 02.2.1 Contamination Mitigation in the North Slope The 138 kV and 525 kV switchyard and 60 miles of transmission lines are exposed to heavy pollution.The main source of contamination is dirt picked up off the arctic desert (tundra)by wind mixed with salt from the Beaufort sea,even when frozen,and,to a lesser extent,calcium chl ori de spread on the roads as a dust supressor(Ruef 1981).Based on local research performed by the SOHIO Company,effective washing of insulators on their 69 kV and 13.8 kV lines is necessary to prevent fl ashovers. Experience with hot-line washing of insulators in substations in other areas with .voltages above 230 kV demonstrated that the risk of using mobile washing installations in high voltage substations is too high, even in more temperate climates with higher temperatures and lower winds.Therefore,it is planned that a fully automated,fixed hot-line washing installation will be adopted for the substation,and a fixed installation with mobile operation of the water pumps will be used for the towers along the first 60 miles. The fully automated fixed installation at the Prudhoe Bay substation consists of two high pressure pumps,a demineralized water tank filled with water from the water treatment plant of the power plants,fixed washing nozzles around each substation insulator,and controls which automatically start the washing of insulators when the test insulator accumulates a given amount of pollutant. The insulators on the transmission line are equipped with fixed nozzles connected to a pipe that is brought down to the bottoms of the towers. A truck equipped with a stainless steel water tank and a pump with a. head and flow sufficient to spray the insulators is used.A hose and 02-2 2560B .J~ J' T' .J 'T' •••__J f' ..~~ ]~ [ .:l--:C': [ 'J l~ _.J 'C _..1 [ ..J ._~ L~j [ I [ ! ,---.J [ [. r~ [ [- [~ [Y P' L,~ r L c' o ITb o 6 L, 8 [ L.. [ L __ [ E L._ [ an operator will be lifted from the haul road to the pads at the towers.The operator attaches the hose to the pipe at the tower and washes the insulators.Special measures (such as blowing the water out with compressed air)are taken after completing the washing of the insulators to prevent freezing the water inside the fixed pipes of the washing installations. The cost of hot-line washing of insulators is relatively high but is the only way to maintain the reliability of a transmission system on the North Slope.The cost estimate,based on Ebasco·s experience in designing and installing such installations,includes a hot-line washing installation. 02.2.2 Grounding The permafrost is an important obstacle in.obtaining a low resistance grounding mat.In the Prudhoe Bay area the grounding mat of the Dalton substation will be designed as follows: A copper mat will be installed in trenches under the gravel inside the switchyard perimeter.From this mat four 1000 kCM insulated copper cables will be installed in trenches to the sea shore (about 6 miles north)• Four electrodes,each fifty feet long,will be driven into the bottom of the sea near the shore,connected together,and connected to the four cables.The vertical electrodes will be in the sea sufficiently deep enough to avoid damages caused by movement of the ice.The distance between the electrodes will be about 100 feet. Both transmission line circuits will require counterpoises along the entire length to Fairbanks.Both counterpoises will be connected to the substation mat. 02-3 2560B [- [~- -~ [, [~ [' [' [~'- ... F LJ 03.0 NORTH SLOPE TO ANCHORAGE TRANSMISSION SYSTEM DESIGN 03.1 GENERAL The transmission line routing from North Slope to Fairbanks follows the Alaska pipeline (TAPS line)and the Haul .Road (offic·ially called Dalton Highway)for approximately 450 miles.The route includes the crossing of Atigun Pass and the Yukon River.The portion from Fairbanks to Anchorage follows the ROW selected for the 345 kV Intertie (Commonwealth Associates,Inc.1981). The basic design criteria for this transmission line considers the special climatic conditions,such as low temperature,heavy winds and ice formation,as well as permafrost on most of the ROW. 03.2 DESIGN CONSIDERATIONS 03.2.1 Meteorological and Climatic Conditions The transmission system is designed using the ,following basic design c ri teri a. 03-1 25 1 bs per sq.ft north of the Arctic Ci rcle and 8 lbs/sq.ft.below it;2.3 lbs/sq.ft. at +86°F. Temperature range: Wi nd loads: The reliability of transmission requires a minimum of two lines to be built for any alternative.Each line (in the cae of two parallel lines)ortwo lines (in the case of three parallel lines)should be able to car~the entire design power,in order to provide uninterrupted service in the event one of the line segments is tripped. For the North Slope-Fairbanks Portion of the transmission system,the following conditions were assumed: 25608 c", 0' O· o , c', G, [ = .;i" i_.;... (. L __ c- 1_- C, '--~ EI . n'L L .. 2560B 03-2 03.2.3 Transmission Voltages 03.2.4 Conductors and Bundle Types -[ L.J [ L_..1 C ..•-1 J' -....--' [ ..1 -L C I -J L -r -[ r [ '"[' [ -'r'" .---' C maximum 50%of rated·tensi1e strength. maximum 18 kV R~S p~r centimeter. 36"north of the Arc ti c Ci rc 1e and 24"south of it. 1.5"radial thickness with 8 1bs/sq.ft. wind load at 32°F. Ice on conductor: Gradient on conductor surface: Tension in conductors: compact snow on ground: The conductors investigated are listed in Table 0-1. Two AC voltage levels were investigated for each of the two load levels.For the medium forecast load 500 kV and 765 kV AC transmissions were compared.For the low forecast level 500 kV and 345 kV AC transmissions were analyzed.HVOC transmission was also considered as an alternative for both forecast scenarios. The above are values used in the overall design of the transmission lines.In certain areas,like Atigun Pass,special conditions exist and,therefore,different criteria would have to be established as part of a detailed engineering process. 03.2.2 Mitigation of Contamination EXcept for the portion from Prudhoe Bay to Pump Station #2,the line is in a non-polluted atmosphere.However,in the first 60 miles the line is exposed to heavy pollution in the periods between Septembe~and January,when the northeast winds coat the insulators with a black conducting film.For this portion of the transmission line the insulation requires long leakage distance,and is provided with fixed insulator washing nozzles. r' L 03.2.5 Clearances line clearances should permit safe operation in all climatic conditions.Clearance to ground will be increased 36 or 24 inches above minimum to account for the snow on the ground and clearances required for maximum sag under ice conditions and are shown in Table 0-2. 03.2.6 Insulators The insulators considered ane listed in Table 0-3. For 60 miles from Prudhoe Bay to Pump Station #2,high leakage distance (fog type)insulators are used and the number of insulators is increased by two in each string. 03.2.7 Safety Factors and Strength Requirements of Support Structures The overload capacity factors (OCF)applied for the structures and the foundations are shown in Tables 0-4 and 0-5. 03.2.8 lightning Protection and Grounding The Prudhoe Bay-Fairbanks portion of the system will not be equipped with shield wir~s because the isokeraunic level (average number of. thunder-days per year)is very low.However,one 4/0 AWG copper conductor counterpoise will be planned beneath each line.The counterpoise is connected to each tower and buried at least one foot under ground level.At the substations and switching stations the counterpoise will be connected to the ground mats. The Fairbanks-Anchorage portion will be equipped with shield wires. 03-3 2560B CONDUCTORS CONSIDERED TABLE 0-1 Cardi na1 ACSR Chukar ACSR Bunting ACSR Martin ACSR Special 2"di ameter ACSR Voltage kV 345 AC 500 AC 500 AC 765 AC +350 DC 2560B Code Word Conductor 03-4 Type KCM 954 1781 1193 1351 2839 Conductors per bundle 2 2 3 4 1 r c r r r f' [' r~ L T' ..L..' Phase to Phase or Pole to Pole Phase to Tower [ r-' r r- c [ [ r LJ Vol tage kV 345 AC 500 AC 765 AC +350 DC To Ground 35 38 45 35 TABLE D-2 CLEARANCES REQUIRED Minimum Clearance in Feet 26 35 45 38 8 10 18 8 C 8 o C G e" G L ._ [ i o L. [ 25608 D3-5 TABLE 0-3 INSULATORS CONSIDERED Strings Insu~ators per String Voltage Size and Strength per Phase Suspens10n .Stra1n 345 AC 5-3/4"x 10"x 50 K 1b 1.!L 18 20 345 AC 5-3/4"x 10"x 50 K1b 2·V21 18 201n- 500 AC 5-3/4 11 X 10"x 50 K1b 2 in V 25 26 765 AC 6-3/4"x 11"x 50 K 1b 4 in V 28 29 +350 DC 6-3/4"x 11"x 50 K 1b 2 in V 28 28 ill Outside phases _Center phase [ t L r [ [' [ r'l~ Cj LJ 25608 03-6 [ C LJ J~ .~ [ l··'···.'".. ...~.r.. l~ o [ L [ [ C [ [ [ nI' LJ TABLE D-4 TOWER OVERLOAD CAPACITY FACTORS (OFCs) Load NESC OCFl! Vertical strength 1.50 Transverse strength Wind load 2.50 Wire tension load at angles 1.65 Longitudinal strength At crossi ngs In general 1.10 At dead ends 1.65 r L c, [J C F.·...·.6 t [ [ [ r n..~6 l [ E1 sewhere In general At dead ends !/For hea~ice loading the OFC is 1.10. 03-7 25608 1.00 1.65 TABLE 0..5 OVERLOAD CAPACITY FACTORS (OFCs)OF GUYS OF GUYED TOWERS Load Transverse strength Wind loaci Wire tension load Longitudinal strength In general At dead ends II For heavy ice 1oadi ng the OFS is 1.1O. 03-8 25608 NESC OCFY 2.67 1.50 1.00 1.50 r: L [ H C C L··.··'···........, ._~_:I [ [ .,...J t' .-i .~ [ [ [- [- rr [- [ [ n l,-,. r L c- e c c c C I [ L I.e. o l,..' [ 03.2.9 Distance Between Parallel Lines,Route and.Pipeline The transmission lines will follow the Prudhoe Bay-Fairbanks Highway and the TAPS 1i.ne as closely as possibl e.Except at the substations and switching stations,the distance between center lines of the two parallel lines is such that failure of one line will not affect operation of the other.For the 525 kV,345 kV and ~350 kV DC alternatives the 1 ines are 200 feet apart.For the 765 kV alternative, the lines are 300 feet apart.Distances to the highway and pipeline will be desi gned to mi nimi ze e1ectromagneti c i nducti on into the pipeline during line to ground faults and to maintain the level of electrostatic field below harmful values at the edge of the right-of-way as shown in Table 0-6.The admissible induced short circuit current under the line is limited to a maximum of 5 rnA RMS as recommended by the NESC. 03.2.10 Corona Criteria for Conductor Size The minimum corona onset voltages of the selected conductor bundle are 1.25 times the rated line to ground voltage as follows: 249 kV for 345 kV lines 379 kV for 525 kV lines 552·kV for 765 kV lines D3.2.11 Radio and Television Interference:RI and TVI The noise level at 230 feet from the center line of the line at ground level is less than that allowable for low residential density areas. D3-9 25608 TABLE 0-6 All other terrain At the edge of the line's ROW Location Publ ic road Private road ELECTROSTATIC FIELD INTENSITY LIMITS AT 1 METER.ABOVE GROUND kV/Meter 7 11.0 11.8 1.6 'r -r~ r r [' f" f' f' Lj 03-10 25608 [ [ ~[ L1 I~ -[ "'C',-- "J L _0 ,[ n L E C b C 8 [ [; C:... C l. L 04.0 TRANSMISSION DESIGN (HARDWARE) 04.1 GENERAL The following alternatives were investigated in detail for the Prudhoe Bay generating scenarios. For the medium forecast generation alternative: Two 500 kV transmission line circuits from Prudhoe Bay to Anchorage and the existing 345 kV Intertie line from Anchorage to Fairbanks fully extended and operating in parallel with the 500 kV lines. Two 765 kV line circuits from Prudhoe Bay to Fairbanks and two new ·345 kV line circuits from Fairbanks to Anchorage with the existing 345 kV Intertie in operation as above. Two +350 kV DC line bipo1es from Prudhoe Bay to Fairbanks and two new 345 kV line circuit~from Fairbanks to Anchorage with the existing 345 kV Intertie in operation as above. For the low forecast generation alternative: Two 500 kV transmission lines from Prudhoe·Bay to Fairbanks and two 345 kV lines (the extended Intertie and a new line)from Fairbanks to Anchorage. Two 345 kV transmission lines from Prudhoe Bay to Anchorage. The five above alternatives were investigated to select a feasible solution for economic comparison with the other generation scenarios. 04-1 2560B 04.2 DESIGN DATA OF THE 500 kV TRANSMISSION LINES A cursory investigation of the 500 kV alternatives was performed to select the most cost effective design for the transmission line. 04.2.1 Conductor Selection 04.2.1.1 Current Carrying Criteria The maximum load of the medium forecast transmission is considered to be 1400 MW.Assuming a 0.93 power factor,the line should be able to carry 1500 MVA or 1730 A per phase.This current has to be carried by a single circuit during emergencies.A bundle of two Chukar conductors and a bundle of three Bunting conductors are compared in Table 0-7, from which it can be seen that the current carrying capacity is not a limiting factor for the conductor selection. 04.2.1.2 Acceptable Conductor Gradient The noise level of the line depends on the electrical gradient.The size and the number of conductors in the bundle as well as the clearances determine the maximum gradient.For a bundle of two Chukar conductors the allowable gradient is 18 kV RMS/cm while for three Bunting conductors the allowable gradient is 18.8 kV RMS/cm.With these values the noise level will stay within allowable limits at 230 feet from the centerline of the line. Maintaining the gradient on the conductor surface under 18 kV rms/cm will also satisfy the RIV and corona loss requirements for the line. Using the curves of conductor surface gradients given in the EPRI Transmission Line Reference Book (EPRI 1982),the surface gradients for 550 kV class are 17 kV/cm for three Bunting and 18 kV/cm for two Chukar conductors. 04-2 2560B r r r: r r r [' r~ L [ P...:.;.:? [ [ ___J l4..j' [ ...:.j [ •_.1 L .....J [ .-.; [ ! 1/At 75°conductor temperature,25°C ambient temperature and 2 ft/sec wind velocity. 1 Conductor Bundle TABLE D-7 AMPACITIES Current carrying Capacity!! Amperes 1730 1730 Required capacity Amperes 2920 3480 1460 11603 x Bunti ng 2 x Chukar Conductor Type [: c·- [~'. [ [ [' e- n L c CE g o C 6 [ U [ C, l . [ D4-3 2560B Both conductors are acceptable for the proposed 500 kV transmission. The equivalent cross-sections of the two bundles are 2x1781 =3562 KCM for the Chukar conductor compared to 3x1993 =3579 KCM for the Bunting conductor.Consequently,the resistances are practically the same and the losses will also be nearly the same. 04.2.1.3 Mechanical Design Selection of Conductor,Towers and the Ruling Span The selection of long spans results in high towers.Selection of lower towers on the other hand leads to shorter spans but larger number of towers.Length of span and height of average tower is established from preliminary sag and tension calculations.The following assumptions were made: Average tower height to the lowest crossarm should not "exceed 100 feet. Low number of piles per tower for foundations and guys. Easy shipping of towers to site. Reduced manpower for construction on site. The sag and tension calculations for Bunting and Chukar conductors are shown in Section 07.0 of this Appendix.The calculations were performed for six ruling spans:"1500,1200,1000,800,600 and 400 feet.The limiting condition for all spans is the 1.5"radial ice load with 8 1b/sq ft wind pressure.In order to maintain the towers under 100 feet heights,with 13.5 feet long insulator and 38 feet clearance to ground,the maximum sag must be under 48.5 feet.The maximum sag for 1000 foot spans with two Chukar conductors is 41.7 feet while with three Bunting conductors the sag is 56.7 feet.The ruling span of the line is taken as 1000 feet.The average height of tower,for the 04-4 2560B [, L C [ [ [~ r [ [ r: n·"__'i. r L [ ,. C C C r.•..•b [ , l [ 1 •••_ C L. L Chukar,results in 41.7 +13.5 +38 =93.2 feet or approximately 95 feet;this compares to 108 feet tower"height to lowest crossarm if Bunting conductors are used.Phase conductors are required to be equipped with spacer dampers. It is assumed for cost estimates that one dead end or angle tower is installed every 10 miles,or roughly 2%of the towers.For the 30 mile section at Atigun Pass the number of dead end and angle towers is increased to 8%. In order to provide work areas for the towers and maintenance areas, 100'x 100'gravel pads are built at each tower site between Prudhoe Bay and Fairbanks.In addition,300'x 1200'gravel marshalling yards are built every 18 miles along the Haul Road to permit helicopter work. 04.2.1.4 River Crossings River crossings along the selected route,except for the Yukon River crossing,do not raise special problems.The Yukon River will be crossed downstream of the highway bridge.In this area the south shore is approximately 300 feet above the water level.A special span of 3,000 feet with two dead end towers and high strength A1 umoweld conductors is anticipated to permit overhead crossing. The minimum clearance to high water level is 76 feet for +86°F ambient' temperature and no wind.At this stage no attempt of optimization of tower heights or exact location of towers was made.The main problem is the special conductor that has to be manufactured to obtain the lowest possible sag under maximum load.The worst loading condition is during the winter when the conductors are covered with ice.However, during this period the river is frozen and no barges or boats can pass under the line.Therefore the minimum clearance to ice level with ice load on conductors is only 45 feet. 04-5 2560B The two dead end towers are of lattice type.Installation of conductors is assumed during the winter when the river is frozen. Special foundations will be used to avoid movement in the soil due to pressure and temperature variation at surface.Automatic equipment tq monitor conductor vibration and settling of towers will be necessary. Alternatives with two low dead-end and one high tangent tower m~y result in lower cost;however,for the feasibility level of estimating the alternative with two high dead end towers is on the conservative side.The height of the towers depends on the maximum sag of the conductor.A bundle of two special 61 x 5 strand A1umowe1d conductors with an ultimate strength of 235,500 lb.,manufactured on special order by Copperwe1d,is able to carry the maximum current of 1000 A per conductor.The maximum sag of the conductor for a 3000 foot span with 1.5"radial ice load and 8 1b/sq.-ft.wind pressure is approximately 105 feet.As a resu1 t,the requi red tower heights are 100 feet on the northern shore and 70 feet on the southern shore. 04.3 DESIGN DATA OF THE 765 kV TRANSMISSION LINE Following the same procedures as for the 500 kV line,the maximum current per phase is 1195 A.A bundle of four Martin (1351 KOt1 ACSR) conductors is able to carry 5000 A.The surface gradient for 800 kV class conductors from Figure 5.4.34 of the EPRI Transmission Line Reference Book (EPRI 1982)for a bundle of four Martin conductors is 17.5 kV/cm.The allowable lever for this conductor is 18 kV/cm. The sag and tension calculation for six ruling spans are given at the end of this Appendix.The limiting condition for this conductor is the 1.5"radial ice load with 8 1b/sq.ft.wind pressure.The most recent design of 765 kV James Bay #3 line in Canada uses guyed towers for special medium design load district and self supporting lattice type towers for the spec;a1 heavy load di strict.However,Ni agara I~ohawk Power Company used an H-frame design for their 765 kV line in 1974. For the reasons of easy shipment and installation as well as simple 04-6 2560B r L f' b [ .C 6 r L ;-~/ [ L --" L ._. [ c- [O- r [ [ [ [ C L foundation of the tubular steel towers,it is assumed that the 765 kV line is also built on H-frame tubular steel towers.The sag and tension calculations show that for a 1200 foot span the maximum sag is 61.07 feet.With this sag the height of the average tower results H =61.07 +19.0 +45 =125.07 feet.With 1000 foot span the maximum sag is only 42.28 feet and the total height would be 106.28 feet.The 17~decrease in tower height cannot compensate for the 20~i nC.rease in the numoer of towers.The 1200 foot span is more economical. Therefore,a 125 foot high tubular steel H tower is selected for the 765 kV line.It is assumed for cost estimating purposes that one dead end or angle tower is installed each 10 miles or 2.27%of the towers are dead end types.For the Atigun Pass portion (30 miles)the number of dead end and angle towers is increased to 8~. River crossings along the selected route,except the Yukon crossing,do not raise special problems.The Yukon River will be crossed,similar to·the 500 kV a1 ternative,near the highway bri dge.The same speci al A1umowe1d conductor will be used as for the 500 kV line,only instead of two conductors,a four conductor bundle will be used for each .. phase.The dead end tower on the northern shore will be about 120 feet high,and on the southern shore the tower will be 100 feet high. 04.4 DESIGN DATA OF THE +350 kV BIPOLAR DC TRANSMISSION LINE The HVDC transmission uses two bipolar circuits.The selection of one large conductor instead of a two conductor bundle reduces the ice load on the line and the total cost of the line.For cost estimating purposes it is assumed that the line will have a 1000 foot ruling span with 90 foot high towers.The selected 2839 KCM conductor is able to carry the normal 1000 A (700 MW)per bipo1e and 2000 A (1400 MW)per bipo1e in case of an emergency.The conductor is similar to that used for the Square Butte DC transmission line. 04-7 2560B The towers will be of the guyed tubular steel type with a single pole, except for the dead end towers which will be guyed A frames • .The DC system is designed ~o not resort to ground return"during anY conditions.This was necessa~to avoid corrosion of the pipeline due to stray currents.Grounding of the line is similar to the AC lines using counterpoise along the ROW.Special attention must be given to the grounding electrodes on both ends of the transmission.Tests of stray current magnitude along the transmission must be performed before line commissioning. 04.5 DESIGN DATA OF THE 345 kV TRANSMISSION LINES The 345 kV lines were based on the design developed by Commonwealth Associates for the Anchorage-Fairbanks Intertie under construction. 04.6 SUBSTATIONS AND SWITCHING STATIONS Several switching stations are required to insure reliable operation of .the transmission in all AC alternatives.The switching stations must be able to isolate a fault on any segment of the transmission lines without affecting the operation of the rest of the system.The switching stations are built with a breaker and half scheme.The reliability of the system can be improved if double circuit breaker arrangements are adopted for the switching stations,because this prevents the loss of two line segments for a common breaker failure. The one-line diagram of a typical switching station is shown on Figure 2-5. 04.6.1 Fairbanks Substation The substation in Fairbanks is an intermediate point for the transmission system,but it is also handling the power used in the area.A one-line diagram is shown on Figure 2-6 for the preferred transmission system. 04-8 2560B [ [ [ [ [ L C" o rL [ ~ C E g [ [ [ , t I L 04.6.2 Anchorage Substation The one line diagram is shown on Figure 2-8 for the preferred transmission system. 04.6.3 Series and Parallel Compensation Series and Parallel compensation is installed in several locations. Each series compensation bank is built on insulating platforms for the corresponding voltage and is equippee with full protective systems. 04.7 COMMUNICATION SYSTEM In order to provide reliable service,a microwave link is proposed. The number of repeater stations assumed is the same number ALASCOM has between Prudhoe Bay and Fairbanks.Information received from them, A1yeska Pipeline,and other sources form the basis of Section 2.2.10. To provide redundancy for vital functions,a carrier system is also p1 anned. 04-9 2560B r [- r- [ [' [~ [' [ [ ~- C lJ C [ l.~ 2'3 [ [ [ L l [ 05.0 SYSTEM DESIGN (LOAD FLOW STUDIES) 05.1 GENERAL This series of alternatives is concerned with how the Prudhoe Bay, medium forecast scenario would be integrated into the Fairbanks-Anchorage system.Many alternatives were investigated, however,this report contains only those alternatives which proved to be vi abl e. It was assumed that the electrical angular displacement between any two buses should never exceed 45°.This is a rather generous allowance, which assumes that voltage regulation at those terminal buses will be sufficient to hold flat voltage schedules.Another criterion that was used for ~ransmission systems extending from North Slope to Anchorage was that the electrical displacement between the extreme ends of the system should not exceed 60°.This is an attempt to limit the amount of shunt compensation which would be required at Fairbanks and could possibly be relaxed if extraordina~amounts of regulation were present at Fairbanks. It should be recognized that all of these angular criteria are merely rough approximations.In case of detailed engineering design,the chosen alternatives must be verified by transient stability studies. In those cases performance will depend upon the nature of the testing criteria,the duration of the faults,and the nature of the remedial action,to determine what angular displacements are acceptable across the system. In adding shunt compensation to the system a philosophy had to be developed.It was assumed in this case that the dynamic compensation requirements at Fairbanks and Anchorage would best be met by static compensation of an inductive nature.It was therefore attempted ·to leave enough line-charging uncompensated on the lines so that all 05-1 2560B losses during the worst outages would be supplied from the lines without requiring a positive (capacitive)output from the VAR compensators at Fairbanks and Anchorage.In the unloaded condition or the zero generation cases,Anchorage and Fairbanks ~re forced to absorb rather large amounts of reactive power.These may not be completely ahsorbed by the VAR compensating devices,but may also be assisted by switched shunt reactors.Although it was not always possible,there was an attempt to limit the magnitude of the capacitive output of the compensators at Fairbanks and Anchorage. In determining the location of the VAR compensators at Fairbanks and Anchorage,a compensator shoul d not be lost at the same time as a critical line would be lost.This necessitates double breaker or breaker and a half switching at the various stations,and also the separation of the compensators from the ~tep down transformers at Anchorage.To do otherwise in Anchorage would result in a common mode failure potential for a transformer outage,which would remove both a line and a static compensator from service simultaneously.At Fairbanks the static compensators may be located on the tertiaries of the step down transformers since the switching on the EHV bus at Fairbanks is such that a transformer and a line will not be lost for a common contingency.However,these details are not shown in the one line schematics presen.ted in the main body of this report. 05-2 25608 r c r~ [ r l l ' ."-',- e r~ L [ C •..J [ f='G~ r··~ "-'? .,._.J L _..J [ L;-..... L ....J L [ [j C C L C C L, [ i L D5.2 PERFORMANCE STUDIES D5.2.1 Alternatives A and AA -1400 MW Generation at Prudhoe Bay,Two 500 kV Lines from Prudhoe Bay to Anchorage and the 345 kV Intertie In Parallel Between Fairbanks and Anchorage Alternative A was one of the first alternatives considered.It is shown in Figure D-1 •This alternative consists of two 500 kV circuits from Prudhoe Bay to Fairbanks and two 500 kV circuits from Fairbanks to Anchorage.The latter two circuits would operate in parallel with a 345 kV Intertie under construction!!which is presumed to be extended to both Fairbanks and Anchorage. The 500 kV circuits are sectiona1ized at two places between the North Slope'and Fairbanks so that the primary HV segments are approximately 15,0 miles i.n length.Between Fairbanks and Anchorage there is one intermediate station which would be located ideally at the mid-point of the system.However,for Alternative A,it is assumed to be 10caterl at,or near,Gold Creek,which makes the segments approximately 190 miles from Fairbanks to Gold Creek and 140 miles from Gold Creek to Anchorage. Alternative A uses 50 percent series compensation for the 500 kV system in all of .its segments,including terminal transformers.In each of the six segments between the North Slope and Fairbanks and four segments between Fairbanks and Anchorage a 200 MVAR shunt reactor has been provi ded to compensate the 1i ne chargi ng of the system. There are two transformers rated at 750 MVA at Prudhoe Bay for each circuit,stepping up the voltage from 138 to 500 kV.A 1500 MVA l/·Construction of the 345 kV 1ine is to begin in the spring of 19a3 with completion expected by the fall of 1984. D5-3 2560B transfonner cannot be used on one circuit because it would provide excessively high current duties on 138 kV switchgear,but two banks in parallel on each of the two circuits provide acceptable circuit breaker and bus duties.The same configuration is maintained in·Anchorage. However,the transformers there are sized 500 MVA each because of the lower loadings expected at that point.Transfonnation is arso provided at Fairbanks from 500 to 138 kV to serve the local loads at Fairbanks and to connect to th~Intertie,which would consist of 500 to 138 kV and 138 to 345 kV transfonnation.The transfonnation at Fairbanks provides double transformation between the 500 kV and the 345 kV systems.However,this is believed to be less expensive than providing direct transformation from 500 to 345 kV.The 345 kV circuit,when operating in parallel with the two 500 kV circuits,does not provide significant support,so it is not.a critical support element in the system. The transfonners at Fairbanks are sized at 500 MVA each,even though the load at Fairbanks is expected to be only about 250 MW.The extra transfonner capaci ty is pro v;ded both to a 11 ow for through-flows through the 345 kV system and to allow use of the transfonners at Fairbanks for connection of a static VAR system or synchronous condensers on their tertiaries. The system of Alternative A was not directly tested for load flow. However,a similar system,Alternative AA,was tested and is shown in Figure 0-2.The difference between Alternative A and AA is that in Alternative AA switching at North Slope and Anchorage was assumed to be at 345 kV rather than 138 kV,but it turned out to be more expensive than A1 ternati ve A•.However,performances of these two a1 ternati ves are Quite similar. Figure 0-3 shows Case AA1,where there is no generation at North Slope and the system is unloaded;this,therefore,represents an extreme case ~where the line c~~~f the transmission system has to be absorbed --~~.~"by the static compensators at Fairbanks and Anchorage.The reactive ------~/ ....-/ 05-4 25608 ~[ -r r r I' I L [ C L [ [ ..1 [ L .J l--- .~~::} L ~,.J [ i L ..J L.. -" L J - [ [ r c [ [ L F r- L) c c c [ 6, C [ [ l_. l l. L power absorbed is shown on the Fairbanks and Anchorage 345 kV buses. In Alternative A they would be on the 138 kV bus or on the tertiaries of the 500 to 138 kV transfonmers.The difference is rather insignificant in the overall picture.Case AA1 shows that the system north of Fairbanks produces about 262 MVAR of excess line charging and the location of the shunt reactor and the series capacitors have been . arranged so that the vol tage at North Slope is at the bottom end of its possible range.This allows for a maximum voltage rise in the event there are reactor failures or circuit outages.The voltage at North Slope for this configuration is approximately 95%of nonmal,whereas the voltage at Fairbanks is 102%.The locations of the shunt reactors between Fairbanks and North Slope have been arranged in such a manner that it produces the lowest possible voltage at North Slope.This is ideal from the point of view of energizing the system from Fairbanks. However,the arrangement may have to be"modified if the system is to be energized initially from the North Slope end.The kind of modification expected might be to relocate the shunt reactors from the northern ends of their segments to the southern ends in one or more of the sections, which would tend to ~eve10p a more·ba1anced voltage profile along the .1ines.The configuration shown in Alternative AA,however,is that which would give the lowest possible voltages on the 500 kV system north of Fairbanks for contingencies involving outages of reactors or segments when the system is only connected to Fairbanks.For the ci rcui ts of the system south of Fai rbanks,reacti ve compensati on i's.not particularly critical,since both Fairbanks and Anchorage are asssumed to have substantial voltage regulating capabilities.In this case, Fairbanks is required to absorb 242 MVAR of 1i ne charging and Anchorage is forced to absorb 346 MVAR of line charging.This balance can be changed by modification of transfonmer taps at Anchorage.However,as shown in Figure 0-3,this system is designed so that Anchorage absorbs the maximum amount of reactive power at no load,but it will be lightly loaded when full power is being delivered.This is more compatible witp the use of static compensators with inductive capabilities than with synchronous condensers. 05-5 25608 The compensation of the 345 kY Intertie between Fairbanks and Anchorage is not known exactly at thi s point;it ;s assumed that six 35 MYAR reactors are on the line.The six reactors,shown in a later case, appear to give a reasonable amount of compensation,and should not have any significant effect on the conclusions regarding the remainder of the 500 kY system. The system was tested at no generati on to insure that it has enough strength for energization and failures of components.Case AA2,Figure 0-4,for instance,shows a case where,at Fairbanks,a circuit breaker on one of the 500 kY lines to the north would be open.The intent was to see how high the voltage at the Fairbanks end of the transmission line would go.In this case it goes up to 107%of normal voltage, which is certainly well within the.capabilities of.the equipment installed.The outage of this segment interrupts the major reactive power flow and one could expect that the voltages at the far end'of the system would also rise.In this case they went up to only 97%from their system normal value of 94.6%.This is a relatively insignificant voltage rise at the North Slope and the voltage rise at the Fairbanks end of tne line is quite acceptable. Opening of the Gold Creek end of the Fairbanks-Gold Creek Line segment ,is shown as Case AA3 in Figure 0-5.This being the 1.ongest segment,it is believed to be a possible critical case for voltage rise.However, all voltages are acceptable.The series capacitors at Fairbanks tend to keep the voltage levels down because of the reactive flow from the 1ine to Fairbanks through the series capacitors. Case AA4 in Figure 0-6 shows a double contingency,with a Fairbanks to Gold Creek line segment open at Gold Creek and the shunt reactor located on the line removed.The voltage increased in this case to approximately 109%of normal.This is still acceptable. An outage designed to test the suitability of the shunt compensation of the 345 kY intertie is Case AA5,shown in Figure 0-7.This case 05-6 25608 [ [ [ [, [' [' [ [j C LJ [ r~ [-- [- L.. [ [J [' f'u [, [ E [ C C [ [ L l. L represents a condi tion where the breaker at the Anchorage end is open. The voltage rose to 10~which is considered to be ~cceptab1e.However the amount of compensation is not sufficiently great that the loss of a reactor in addition to the open ended line could be tolerated.This is shown in case AA6,Figure 0-8,where the voltage level reaches 115%. It can be concluded,therefore,that the amount of shunt compensation on the 345 kV system as modelled was reasonable although it could undergo some fine tuning. Case AA7,shown in Figure 0-9,is another test to determine the adequacy of the shunt compensation of the system and the location of the shunt reactors.It shows an outage of the line from North Slope to the first intermediate station which in this case is termed GL 500. The voltage rise at both North Slope and the GL 500 end of the open ended line is reasonable. Case AAB,Figure 0-10,takes the preceding outage one contigency level further by removing the shunt reactor on the open ended line.In this case the voltage reached 110%which,again,should be acceptable.If a modification were made to allow the system to be energized initially from the North Slope end,the initial voltages at North Slope would be higher than the 98%shown in Figure 0-3.In that case a higher amount of shunt compensation might be required to keep voltages down to the 110%shown in Case AA8.The additional compensation ~ould be installed in the intermediate switching station,rather than on the line and could be viewed as switched spare reactors. Case AA9,shown in Figure 0-11,deals with 1400 MW generation at the North Slope.It is assumed that the power is divided between Fairbanks and Anchorage with Fairbanks getting 250 MW and Anchorage getting the remainder less losses.In Case AA9 the full load line losses are approxmate1y 77 MW or roughly 5%of the total power generated.Case AA9 shows electrical angular displacements between the generation-at North Slope and Anchorage of 43 degrees.This appears to be acceptable provided that ther.e is a substantial voltage support in Fairbanks which 05-725608. is assumed for this case.In Case AA9 the North Slope generation voltage schedule has been assumed to be 10~higher than the voltage scheduled with no generation in service.This 10~swing on the generator bus tends to maximize the reactive power output of the North -- Slope generation and to minimize the swing required by the voltage regulation at Fairbanks and Anchorage.In this case Anchorage absorbs only 69 MVAR and ~airbanks absorbs 95 MVAR.With 1400 MW generation both Fairbanks and Anchorage are lightly loaded with reactive power because the generation is required to put out the most reactive power. Voltages across the system are all quite reasonable,with the possi,b1e exception of the intermediate switching station at Gold Creek,which is down to about 94~and may require some shifting of the shunt reactor locations to bring that up. Figure 0-12 shows Case AA10 which represents one of the critical outages of the system with one line segment north of Fairbanks out of service.The most significant factor to note is the e1 ectrical ang1 e across the system which increased from the 43 degrees of Case AA9 to 50.7-degrees.Though this seems to be a rather wide angular swing,it is tolerable considering the voltage support provided at Fairbanks. Voltages along the 500 kV system are all acceptable.Thereactive power swing at Fairbanks is also reasonable;it is now a positive 60 MVAR instead of a negative 95 MVAR as it is in Case AA9.This is an acceptable outage case. Case AA11,shown in Figure 0-13,appears to be slightly more severe that the previous case.The loss of a line segment between the North Slope and the first intermediate sWitching station causes a slightly higher impedance increase on the system.The electrical angle across the system i~now 55.6 degrees,rather than the 50.7 degrees of Case AA10.This,therefore,is probably the most severe outage to the system.Even in this case,however,voltages are quite acceptable across the system.The voltages at the intermediate stations are down around 94 to 96~,but that is tolerable.The reactive output at North 05-8 25608 r~ I' [ f' L~ r~ r~ [' r'L,~ [ G [ -L _'..1 -c --, -r ; [ -~ -[ _J C--.- L j [ C C'. [ C i, [ [ '. [ L. [ i L Slope is on the order of 90%power factor,which would tend to determine the reactive rating of the generators.The reactive output at Fairbanks is also moderate'with 88 MVAR,and Anchorage essentially floats.So the original intention to have Anchorage absorbing on the order of 350 MVAR appears to be well designed. In Case AA12 of ~igure D-14 the outage of the Fairbanks Gold Creek line segment is modelled.This case was run to see if it would compete in severity with the outage of the line segment between the North Slope and the first switching station.This contingency turns out to be less severe because the electrical angle across the system is 49.5 degrees which is less than the 55.6 degrees of Case AA11.Therefore it is of no concern if Gold Creek is selected rather than a point eocactly halfway between Fairbanks and Anchorage.This case also demonstrates the potential magnitude of throughflow on the 345 kV Intertie.In this case the intertie carries only l84MW between Fairbanks and Anchorage. The 500 kV line segment remaining in service with its 50 percent series compensation is much more significant as it carries 930 MW.Therefore, whether or not the 345 kV intertie is in service is not a prime consideration with this alternative.The loadings on the transformers at Fairbanks are also quite acceptable,being only on the order of 217 MyA per DanK.Therefore,the bank size of 500 MVA is more than adequate to handle the through flow.It could probably even handle an outage of one of the transformers at Fairbanks in addition to this line outage,and still stay within the 500MVA rating.Case AA12 represents a condi ti on which produces the highest reactive output requi rement in' Anchorage,in this case 81 MVAR. Case AA13 deals with an outage of the Anchorage-Gold Creek line.It is shown in Figure D-15 and appears to have approximately the same severity as an outage at the Gold Creek-Fairbanks line,even though it is shorter,because in this case the impedance of the step down transformers is included with the line which is equivalent to an increase in the length of·the line.The electrical angle across the D5-9 2560B system,however,is only 48.7 degrees and therefore the situation is not as severe as an outage of any of the segments between the North Slope and Fairbanks. Case AA14 again is designed to test the effects of throughf10ws on the 345 kV system and·is shown in Figure 0-16.In this case,an outage of one of the transformers at Fairbanks would load the remaining transformer to 71%of its 500 MVA rating,indicating that the 500 MVA rating is reasonable for these transformers. Referring back to Case AA12,the increase in loading on the 345 kV intertie for an outage on the Gold Creek-Fairbanks 500 line was on the order of 60 MW.If this increase of 60 MW is added to Case AA14,the loading on tile remaining bank would just be over 400 MW.This demonstrates again that the sizing of the banks at 500 MVA is sufficient to withstand the loss of even one bank and one-line between Fairbanks and Gold Creek. The previous case studies show that the Intertie1s presence or absence does not appear to have a major impact on loadings across the system. As a result,this alternative is overbuilt.Therefore sUbsequent alternatives attempted to use weaker system configurations between Fairbanks and Anchorage,such as two new 345 kV circuits,'instead of the two 500 kV circuits,in addition to the Intertie under construction. 05.2.2 Alternative B -1400 MW Generation at Prudhoe Bay,Two 500 kV Lines Between Prudhoe Bay and Fairbanks and Three 345 kV Lines Between Fairbanks and Anchorage The basic configuration of Alternative B is shown in Figure 0-17.This alternative differs from Alternative A in that three 345 kV circuits between FairDanks are substituted for the one 345 kV and two 500 kV circuits of Alternative A.Alternative B therefore has switching at Fairbanks at the 345 kV level and requires transformation at Fairbanks 05-10 2560B r [ f- [ f' f' L [ [ [ L C E ._J [-' '...-' ! C f'. L ......J .[ -J L .",_J L [' [ r- [ [ [- L C r~ L c·e C [ = j C ~.'G [ [ L: c. C c L to step up to the 500 kV level used for the lines north of Fairbanks. It also incorporates 345 to 138 kV transformation at Fairbanks purely to serve the local area loads and to incorporate the reactive power compensation of the system required at Fairbanks.Also shown is 345 to 138 kV transformation at Anchorage.Therefore,138 kV is present at the Nortn Slope,Fairbanks,and Anchorage. The 345 kV 1ines are 50 percent series compensated.The 50 percent includes the impedance of the step down transformers when they are part of the line switching,similarly to the previous alternative.The shunt compensation of Alternative B on the 500 kV portion is identical to that of Alternative A.The 345 kV lines,however,require less shunt compensation since they produce less line charging.In this case it is·assumed that each of the six line segments between Fairbanks and Anchorage have one 75 MVAR shunt reactor attached to it. The transformers in Alternative B are sized at 1500 MVA,or two 750 MVA,on each of the circuits from the North Slope to Fairbanks.Two 400 MVA transformers step down the voltage to 138 kV.The 400 MVA size is selected because,in the absence of any through-flow problems,the transformers are used to serve the local load.The three transformers at Anchorage are sized at 600 MVA each,to allow 1200 MVA capability remain even after the outage of one circuit.This is essentially the same capability that remained in Alternative A with the loss of one 500 kV circuit between Fairbanks and Anchorage. The intermediate switching station between Fairbanks and Anchorage is assumed to be approximately half w~between the two cities,since a 190 mile long 345 kV line segment,which would result from a Gold Creek location,might not be acceptable for this configuration. Case Bl of Figure D-18 is a no generation case with no outages.The attempt here is to duplicate the v.oltage profile of earlier alternatives,so the voltages are approximately 95~at the North Slope and about 102~at Fairbanks.It was also attempted to absorb as much D5-11 2560B reactive power as possible at Anchorage and to minimize the absorption at Fairbanks.It turned out to bea success by 444 MVAR being absorbed at Anchorage and 191 MVAR at Fairbanks.Voltages all across the system are satisfactory. Case 82 shows 1400 MW generation at North Slope.Conditions between North Slope and Fairbanks are quite similar to those in Alternative A. 8etween Fairbanks and.Anchorage power flows are evenly distributed on the three 345 kV lines since they are now equally series compensated. Voltages along the system are also acceptable.The reactive absorption as in the previous cases,is low,being down to 43 MVAR at Anchorage and 64 MVAR at Fairbanks.The angular difference across the system is 47.4 degrees,compared to 43 degrees in Alternative AA.Therefore,the e1 ectri cal conditions .are quite simi1 ar to those of A1 ternati ve AA. This case is shpwn in Figure 0-19. Figure 0-20 is labeled Case 83 and was run to show the effect of changing the voltage schedule at the North Slope generator bus.In this case the voltage was raised only 5%over the'no load case,instead of 10%as in Case 82.That reduced the reactive output of the North Slope generation by 97 MVAR.However,in doing so the reactive output at Fairbanks had to increase by 105 MVAR and reactive output at Anchorage increased by 45 MVAR.Therefore,it is highly desirable to hold the highest possible operating voltage and the peak-to-off-peak voltage differential at the North Slope to minimize the dynamic reacti ve power requi rements of other pa rts of the system. Case 84 (Figure 0-21)is quite similar to Case AAll of Alternative AA. In either case it is an outage of the line from the North Slope to the first intermediate switching station.In this case the electrical displacement across the system is 58.7 degrees instead of 55.6.This alternative,therefore,has only a slightly higher transfer impedance between the North Slope and Anchorage than Alternative AA.The loading on the one remaining circuit between the North Slope and the first 05-12 25608 , [ T' [' 'r T r r" l-., p ~-~. [ L [ E _..,..J ,[;~ -J __..J C ~ '1~ L ....J [ l [- [c [ L [ [ [~ L~_ lr- r'-[ [ r C C l [ i L L , [ L c- L.__ Lj' I . l: intenmediate station is approximately 15 per unit current.Therefore, all the facil ities on each of the 500 kV ci rcuits were sized at 1500 MVA. Case B5 was investigated to measure once more the sensitivity of the system to changes in voltage at Prud.hoe Bay.In this case,as is shown in Figure 0-22,lowering the voltage by 5%during the outage reduced the reactive output of the generator by only 57 MVAR,but Fai rbanks and Anchorage must increase their outputs by 98 MVAR and 41 MVAR, respectively.So again,this demonstrates that the voltage should be held as high as possible at the North Slope,even during outage condi ti ons. Figure 0-23 shows Case B6 which represents an outage of one of the three 345 kV circuits from the midpoint switching station to Anchorage.The electrical displacement across the system is only 52.8 degrees thi s time.Therefore,it is significantly less severe than an outage of one of the 500 kV circuits in Figure 0-15.Loadings on the remaining two circuits in parallel are on the order of 520 MVA, therefore they are within the 600 MVA capabilities that were assumed for the transfonmers at the ends of the lines.Voltages are quite acceptable.The reactive output requirement at Anchorage is 111 MVAR, which is as high as it becomes for any contingency. 05.2.3 Alternative C -1400 MW Generation at Prudhoe Bay,Two 765 kV Lines Between Prudhoe Bay and Fairbanks and Three 345 kV Lines Between Fairbanks and Anchorage Alternative C differs from Alternative B in that 765 kV is'used north of Fairbanks.It is displayed in Figure 0-24.Instead of having two 500 kV series compensated circuits in parallel,it has two 765 IcV circuits without series compensation.The impedances are on the same order of magnitude as those.on the 10we~voltage circuits.One major difference,though,is that the line charging of the 765 kV circuits is sUbstantially higher than that of the 500 kV circuits.In Alternative Ca ve~high degree of shunt compensation is required.In this case 05-13 2560B 660 MVAR of shunt reactors are placed at each 150 mile segment of the 765 kV line.The line charging from each of these segments is approximately 700 MVAR.Therefore the 660 MVAR represents about 94~ shunt compensation of the lines •.Changes in net reactiv~output could prove to be a problem if the frequency of the system should deviate significantly from 60 Hertz.Other'than the higher voltage,the circuiting is identical to that of Alternative 8.The transfonmers at the North Slope remain at 750 MVA,each having two paralleled on each circuit in the same manner as they were in the 500 kV alternative,and the transfonmers at Fairbanks on the lines to the north also remain at 1500 MVA. The shunt reactors have been located to lower the voltage as much as possible at the North Slope.The shunt reactor compensation requirements are large,and it is impossible to supply all the shunt reactive requirements of the line segments in one location with excessive open end voltages.Therefore,three 220 MVAR reactors are connected to each line segment,with two of them being located at the northern ends and one at the southern ends,to attempt a voltage decrease from Fairbanks as the lines go north. One of the great advantages of this alternative,in addition to reduced losses,is that it does -not require series compensation on the 76~kV--. lines.This could be important in view of the long maintenance times, high maintenance cost and relatively low reliability record of such series capacitors.Therefore,at detailed feasibi1ity-engineering studies this alternative has to be considered. Alternative C,Case C1 (Figure 0-25)is a no generation case comparable to Case 81 of A1 ternati ve 8.The net 1i ne chargi ng output of the circuitry north of Fairbanks is approximately 260 MVAR as it was in Case 81.However,the absence of the series capacitor compensation in the line makes it difficult to obtain the same voltage profile that was obtainable in Alternative 8.In this case the voltage at North Slope can be brought down only to 1.013 per unit with the distribution 05-14 25608 [ L [ [j [ C C [ L l:_ [ L_ L L of the shunt reactors as shown.Alternatives with series capacitors could give more flexibility to obtain the desired voltage profile by adjusting the location of the series capacitor compensation.Other than this the voltage profiles across the system are quite similar to those of Alternative B. Case C2 (Figure 0-26)shows 1400 MW generation at the North Slope.The voltage level at the generator bus was raised by 10%as it was in previous cases.However,this appears to result in exce$sivel~high voltages on both the 765 kV system and on the 138 kV bus at Prudhoe Bay.Therefore,the 765 kV alternative may be more difficult to optimize in tenns of producing maximum reactive output at the North Slope.The voltage levels on the 138 kV bus are relatively easy to clear up by changing the taps on the generator step up banks and the 765/138 kV banks.However,the voltage level of 1.069 on the 765 kV line is probably excessive unless transfonners with higher rated voltages are purchased.Therefore it may not be possible to raise the voltage 10%from no load to full load with the 765 kV alternative unless some further optimization of the shunt reactor locations can be made.The electrical angular displacement across the system is approximately 45 degrees which is again comparable to the other alternatives that have been looked at so far.The reactive loading at Anchorage is low,as it was in the other alternatives;at Fairbanks approximately 154 MVAR would have to be absorbed.Line losses are only 75 MW,which is 35 lower than 'Alternative B. Case C3,in Figure 0-27,shows an outage of the 765 kV circuit between the North Slope and the first intennediate station.As in Alternative B the electrical angle across the system is in the mid 50 degree range, in this case 56.1 degrees,Therefore,it perfonns in quite a similar fashion to that of the 500 kV system.For this case one should note that the reactive output of Fairbanks and Anchorage is essentially zero,This indicates that shunt compensation levels on the lines are appropriate,if the North Slope voltage level can be maintained. 05-15 2560B D5.2.4 Alternative D-1400 MW Generation at Prudhoe Bay,Two Bipolar +350 kV DC Lines Between Prudhoe Bay and Fairbanks and Three 345 kV Lines Between Fairbanks and Anchorage Alternative D is designed to carry 1400 MW from the North Slope to Fairbanks using HVDC transmission.The inverter station,at Fairbanks, converts DC to AC.From Fairbanks to Anchorage the transmission is at 345 kV AC.The DC performance and an AC perfonmance of the system can be treated separately in the given configuration.The following sections first describe the DC portion of the system followed by that of the AC system portion. D5.2.4.1 Description of the System The system schematic is shown in Figure D-28. A prima~design criteria for the DC system is system reliability.It was concluded that a system of two bipoles would provide perfonmance comparable to that of two AC circuits. There are other compelling reasons why the two bipo1e arrangement is better for the Prudhoe Bay to Anchorage transmission rather than a system which has one bipole and is in monopolar operating mode during a contingency.The main reason is to avoid potential problems with ground return current flow in the TAPS line.In case of two bipoles each one can be carefully balanced to assure that no DC current flows in the ground.If only a monopolar DC line remains after an outage, the·full DC return current would have to flow in the ground.That current wou1 d be twice the operati ng current for the requi red power level.Currents always t~to find the path of least resistance and the pipeline provides an excellent means to provide a good path between Prudhoe Bay and Fairbanks.Such currents would have destructive effects on the pipeline and its operation. D5-16 2560B T' [' l' .G ~[ ·r~LJ.; [ ,_l [ _..J ..8 J~ l' .~r L~.J -L'"---, i_..:....J L_J [ [~ c- [- r- [ [-\ E- c" C G C i. C 6 l._ [ i [ Li C l_~ L L_ The voltage to be selected for the DC system is a variable which can be changed to meet a minimum cost criterion.Our calculations indicate that a voltage level of approximately +350 kV on each bipole and designed to carry normally 700 MW on each bipo1e is close to optimum, and was,therefore,used in this developme"nt.The reliability criterion applied was that either bipo1e should be able to carry the entire 1400 MW.This,plus the influence of normal line loss considerations,determine the approximate conductor size to be used on each bipole. Sizing the converter poles at each terminal is an independent decision.In this case it is assumed that each of the four poles would have a converter with 33%of full load capability.Thus one of the four converters could be lost and still maintain full power transfer. It can be assumed that the valves have 10%emergency capability,which can be used in the event of a converter"outage.Thus each pole is rated at 467 MW in an emergency,so that three of them would have a total rating of 1400 MW in normal operation.This results in a converter normal rating of 425 MW per pole,which was used for pricing purposes. These ratings apply to the converter/rectifier terminal at the North Slope.The vol tage and power rati ngs of the converter poles at the inverter terminal at Fairbanks are slightly lower because line losses, normally amounting to some 6%,are dis~ipated in the DC tr~nsmission system.The ratings of the converters at Fairbanks are assumed to be 400 MW normal and 440 MW emergency per converter pole,thus allowing up to 1200MW to be inverted during one converter pole outage at Fairbanks.Because higher than normal line losses occur during such a contingency,the rectifier terminal and generator capabilities would 1imit rather than the inverter. A major design consideration for the inverter is providing adequate short circuit levels to enable commutation of the inverters.This is a major problem for "the DC alternative,since much of the generation in D5-17 2560B Fairbanks and Anchorage will be decOlllDissioned by the time the Prudhoe Bay generation is operating.For this case it is assumed that the system would be very weak in the absence of local generation and it is necessary therefore to add a large amount of synchronous condenser capacity at Fairbanks to supply an adequate short circuit level.'It is generally regarded that a short circuit level approximately 2 1/2 times the DC 'power inverted is the minimum acceptable level of system strength.At Fairbanks it is assumed that with much of the generation shut down the short circuit level might be as low as 200 MVAR on the system without augmentation by condensers.Therefore,the additional short circuit level required was on the order of 3125 MVAR.This would be supplied by synchronous condensers,which are assumed to have transient impedances of 40%on their own base and connected to the system with transformers having 5%impedances,a1 so on thei r own base.Thus each MVA of condenser would be able to supply 1/0.45 or 2.22 MVA of short circuit capacity.To raise the system capacity by 3125 MVAR would therefore require 3125/2.22 or 1406 MVAR of synchronous condensers,or approximately the same capacity as the inverter termi na1 is required to convert. To connect the 1400 MVAR of synchronous condensers to the system,each of the converter poles could conveniently have two converter transformers (about 250 MVA each)associated with it,therefore there are 8 converter transformers available for connecting the synchronous condensers.If all 8 transformers have condensers on them,each of the condensers would have to be rated at approximately 234 MVAR to tolerate the outage of two condensers and still maintain adequate short circuit levels.The 234 MVAR rating for the condensers is excessive in light of the fact that the largest hydrogen-cooled condensers in the world are 250 MVAR and gave unsatisfactory performance on the AEP system. Also,the 234 MVAR rating would significantly influence converter transformer sizing. It should be noted that the assumption of the outage of two condensers out of 8 amounts to a 25%outage rate.Hydro-Quebec concluded that a 05-18 25608 I' U [ L C E__.J [~~ c- [- ,-o~_. [ c- [- c'p- L n- L I.e Ci__. [J C ! b I G [ (,..- [ "; C lJ- iL_ [ 30%reserve of condensers is needed on their system to meet an acceptable level of availability.To counteract both the large number of condensers and the poor availability,a second iteration on the condensers was attempted.In this case,the tertiaries of the two 345/138 kV transfonners are also used to connect the condensers.This allows 10 condensers to be in service and,planning for an outage of two,allowed a rating of 176 MVAR per condenser to be used.This is a more satisfactory arrangement.Alternatively,a rating of 195 MVAR each would allow the loss of three condensers.Such refinements must also depend upon more accurate detennination of condenser impedances and short circuit contributions from other sources. Although the synchronous condenser capacity installed at Fairbanks must be on the order of 1750 MVA,the reactive power requirements of the... converters themselves is on the order of 800 MVAR,with about half of that provided by filters.Thus there is a substantial reactive power capability in excess of that required by the converters at Fairbanks which becomes available to control voltages on the AC system south of Fairbanks. The description is as follows. The AC system south of Fairbanks consists of three 345 kV circuits with one inte,nnediate switching station.Because the transient s1:ability problems of this system are substantially less severe than that of the other completely AC transmission system,series compensation is not necessary for this portion of the system.The transmission requirements are those of a power plant located at Fairbanks shipping power to Anchorage.Therefore,a larger angular displacement can be allowed between Fairbanks and Anchorage. The AC line south of Fairbanks is compensated by shunt reactors in the same way as Alternative 8 using 75 MVAR reactors on each of the six line sectors.A description of the DC system operation is rather trivial,hence the analysis shown in the following figures concentrates on the AC system. 05-19 2560B 05.2.4.2 Performance Studies Figure 0-29 displays case 01 showing the AC system with no power transfer between Anchorage and Fairbanks.It represents either zero generation at the North Slope or no more generation than is consumed by the load of the Fairbanks are~.The excess line charging'of the AC system is absorbed at Fairbanks and Anchorage.Fairbanks absorbs 107 MVAR and Anchorage absorbs 281 MVAR.It is assumed that Anchorage has three static compensator systems.Each of the three static VAR systems in Anchorage is sized at -100 to +200 MVAR.This represents the addition of one static compensator system more than has been used in Alternatives A,Band C.It also reflects the fact that series compensation is not used in the AC portion of the transmission system and,therefore,the changes in reactive line losses are greater during outages and during load swings. This approach of using more dynamic shunt compensation and no series compensation was a natural outgrowth of the presence of the enormous amount of reactive capacity available at Fairbanks.Therefore,this approach appears to be more economical than to continue to use series compensati on. Case 02 shows full load generation at Prudhoe Bay (Figure 0-30),which would result in approximately 1330 MW being inverted at Fairbanks. This amount of power,less the Fairbanks load,is shipped from Fairbanks to Anchorage (1080 MW).Voltage levels on the 345 kV system are acceptable;however,Anchorage is forced to output 133 MVAR to sustain its voltage level.It should be noted that the reactive power swing from no load to full load at Anchorage is 464 MVAR.This,again, is an indication of the effect of the omission of series capacitors and indicates the approximate range of the dynamic reactive p·ower source requi red at Anchorage. Case 03,in Figure 0-31,shows an outage of one of the three circuits between Anchorage and the mid-point switching station.It is the most 05-20 2560B r~ [ r :r T [ 1 r l~-, ·r [ [ .:.1 [ _--J Ct~ •.J---' [ -j L__,J -[ --J L:-.; L [., [- t_-,. C' L [. [ f -·., L p. L. L-. c u C i C G [ ! [ j ~ !~- C ! [ severe outage of the AC system which can affect this alternative.It increases the reactive power requirements at Anchorage from 183 to 405 MVAR.Thi"s outage agai n shows the 1arge increase in reacti ve power losses caused because of the omission of series compensation.The 405 MVAR output of the condensor represents an increase of 686 MVAR over the output of the same compensation system at no load.Also,the ~lectrica1 angular displacement across the system is increased to a considerable 53°by this outage.However,when the DC power is fully controlled,as it is in this alternative,transient stability concerns on the AC system are substantially less important than they are in conventional power systems,therefore a larger angular displacement can be allowed in steady state. Case 04,in Figure D-32,shows the effect of raising the voltage level at Fairbanks by 5%at full load,as compared to the zero generation· case.The net effect of this is the reduction of the reactive power output of the static compensation system at Anchorage by 109 MVAR. Case 05 (Figure D-33)shows the effect of a 5%voltage increase at Fairbanks for the same contingency that was discussed as Case 03.In this case the reactive power output at Anchorage is reduced from 405 MVAR to 298 MVAR,corresponding to a change of 107 MVAR.This appears to be a desirable operating procedure because it reduces the magnitude of the reactive power'requirements at Anchorage.It also has a beneficial impact on the angular displacement across the system, because the displacement is now only 50°instead of 53°.Raising the voltage schedule at Fairbanks by 5%increases the reactive demands on the'synchronous condensers at Fairbanks.In this case the AC system lines require 332 MVAR.The demands of the converter terminals are on the order of 800 MVAR,however,apprOXimately half of that would be suppli ed by the fil terse Therefore,the total condenser 1o.adi ng at Fairbanks for this case would be 732 MVAR plus whatever reactive demand is present in the Fairbanks area.Since the condensers have a rating in excess of 1700 MVAR,there is no need in this alternative to correct the power factor of the load of Fairbanks. 05-21 25608 05.2.5 Alternative E -700 MW Generation at Prudhoe Bay,Two 345 kV Lines from Prudhoe Bay to Anchorage A1 ternative E provi des transmi ssi on for 700 MW of generation at the North Slope.The system,as shown in Figure 0-34,consists of two 345 kV circuits north of Fairbanks with two intennediate switching stations.The 345 kV circuits,including their tenninating transfonners,are 5~seri es compensated.The system south of Fairbanks also has two 345 kV circuits with one intennediate switching station.It,too,is given 5~series compensation.Shunt compensation is also provided on each of the circuits.The 150 mile long segments north of Fairbanks have 100 MVAR shunt reactors and the 165 mile segments south of Fairbanks have 75 MVAR shunt reactors.In this alternative,it is assumed to have dynamic ~eactive power regu1 ati on at both Fai rbanks and Anchorage.At each station it is assumed that there are two devices with -10OMVAR to +10OMVAR ranges. For light load conditions this range would have to be supplemented by additional switched reactors at each station and at the other intennediate stations. Case E1 shows the system energized with no generation at the North Slope Figure 0-35.With the shunt reactors located at the northern ends of all the circuits,a voltage level of about 94%is obtained at the North Slope,which appears to be satisfacto~.The.exce~~line charging is absorbed at Fairbanks and Anchorage,with Fairbanks taking 119 MVAR and Anchorage taking 277 MVAR. Figure 0-36 shows case E2 which represents a no generation case,with the line between Fairbanks and the first intennediate station north of Fairbanks open at the Fairbanks end.Voltage levels on the open-ended circuit are acceptable. Case E3 goes further by one more contingency level.It removes the shunt reactor from the line as well as open-ending it at Fairbanks 05-22 2560B r L. ..[-~ -::. ._, r r1 L (Figure 0-37).The voltage reaches a level of 111~at the Fairbanks open end of the line;the North Slope voltage level has risen to only 102%,both are acceptable. Case E4 represents Alternative E with 700 MW of generation at the North Slope.Full load losses on the lines are 67.3 MW.The voltage schedule at the North Slope has been raised by l~from the zero generation case as can be seen on Figure 0-38.Voltage profiles across the system are all near unity and are acceptable.Line charging has been consumed to a great extent by the line losses.This is also indicated by the loading of the reactive power sources at Fairbanks and Anchorage which are required to absorb only 48 and 113 MVAR, respectively. Case E5 shows the worst outage for this alternative (Figure 0-39), namely the loss of one line segment between Prudhoe Bay and the first intermediate station.Line losses increase to 85.7 MW and voltage at the first intermediate station drops to 95~.In other respects,the system performs quite acceptably,the electrical displacement across the system is 52°which,again,though on the high side,is still acceptable. 05.2.6 Alternative F -700 MW Generation at Prudhoe Bay,Two 500 kV Lines Between Prudhoe Bay and Fairbanks and Two 345 kV Lines Between Fairbanks and Anchorage Alternative F also provides a transmission system for 700 MW of generation at the North Slope.The system shown in Figure 0-40 consists of two 500 kV circuits with two intermediate switching stations,but without series compensation,between Prudhoe Bay and Fairbanks.South of Fairbanks it is the same as Alternative E,with two 345 kV circuits,one intermedi~te switching station,and 5~series compensation of the lines and corresponding terminating transformers. Reactive shunt compensation is provided on the circuits north of Fairbanks in the amount of 200 MVAR for each of the circuits.South of 05-23 25608 Fairbanks the same 75 MVAR shunt reactors are provided on the 345 kV circuits.Only the 345 kV lines are series compensated.At Fairbanks two static VAR systems with ranges of +100 MVAR are provided and the same is provided at Anchorage.At Fairbanks the reactive devices may be locate~on the tertiaries of the 400 MVA transformers.At Anchorage the reactive devices are located on the 138 kV bus to avoid their loss if an outage of the 345 to 138 kV transformers occurs. Alternative F at zero generation is shown in case F1 (Figure 0-41). The voltage profile across the system from Fairbanks to North Slope is reasonably flat.The same is true for the profile between Fairbanks and Anchorage.The excess line charging is absorbed at Fairbanks and Anchorage with Fairbanks taking 216 MVAR and Anchorage taking 303 MVAR.These amounts can be changed by varying the tap settings on the transformers at Anchorage. Case F2 shows 700 MW of generation at the North Slope.The voltage schedule on the generation has been increased only 5%because of the al ready hi gh no-load voltage as c an be seen 0 n Fi gure 0-42.Lo sses are 35.7 MW on the lines.The voltage profiles are all acceptable across the system.The reactive power absorbed at Fairbanks and Anchorage has been reduced to 123 MVAR and 121 MVAR,respecti vely.The electrical angular displacement across the system is 45.40,which is acceptable. Case F3 (Figure 0-43)shows an outage of one of the circuits between the North Slope and the first intermediate switching station.It results in a 60°electrical angle across the system and 45°electrical displacement between Fairbanks and North Slope.This can be regarded as the upper limit.It should be noted that the reactive power demand at Fairbanks dropped to a level where Fairbanks absorbs only 10 MVAR. This confirms that the initial loadings at Fairbanks are acceptable while coping with this outage. Case F4 represents an outage of the line from Anchorage to the midpoint switching station as shown in Figure 0-44.Since the lines at this 05-24 25608 ··'-'1 r' L [ r'L r': L ~[ L [ [ Pl_ f~ 1~ ,T' ~........ L L c· [~ c-. c C r~~ I:. r' \ p l.o~ C L C L \ [ $0 (5., r~ LL C)". :',-". [ point in the system are shorter than those north of Fairbanks and are more lightly loaded,this is not as critical a contingency as an outage of one of the circuits north of Fairbanks.This can be seen by observing that the electrical angular displacement is only 53 0 rather than 60 0 which was the case for an outage north of Fairbanks. 05-25 25608 [ r [ t=-'~-" C C C G C C [ L C \_. [ 06.0 CONCLUSIONS With all the prefeasibility level design completed,a preliminary cost estimate was made based on figures published by the Department of Energy.Although these figures are based on lower 48 costs,their relative value was used to do a cursory comparison.The results were within ~10%dollar range for both the medium forecast and the low forecast scenarios.This meant that within the accuracy of the level of this study the costs of each of the alternatives described in this Appendix is about the same.This meant that the following 15 transmission lines are about equivalent within their respective groups. Prudhoe Bay Generation Pruanoe Bay to Fairbanks Medi um Forecast (1)765kV,twocircuits (2)500 kV,two circuits with series compensation (3)+350 kV DC,two bipo1esl! Low Forecast (4)500 kV,two circuits .(5)345 kV,two circuits with series compensation (6)+350 kV,two bipo1esl/ l!The two HVDC versions may differ in current and/or voltage ratings. 06-1 2560B Fairbanks Generation Fairbanks to Anchorage Medium Fo recast (7)500 kV,two circuits and with or without the 345 kV Interti e (8)345 kV,three circuits with series compensation Low Forecast (9)345 kV,two circuits with series compensation Kenai Generation Kenai to Anchorage Medi um Forecast (10)500 kV,two circuits with some series compensation (11)345 kV,two tircuitswith series compensation ·(12)345 kV,three circuits Low Forecast (13)500 kV,two circuits (14)345 kV,with series compensation Anchorage to Fairbanks Both Medium and Low Forecasts (15)345 kV,two circuits without an intermediate switching station D6-2 2560B 'r --r -l,_ r L f':L r....:::.:-~ l; w J' L- .j><' L i-t-; -1' l--' -,-. -j C F t 8 o 6 C C...'.u G C [ I C [ It was much simpler to design the transmission system for the Kenai generation scenarios than to do it for the Prudhoe Bay scenarios.The reason:Kenai is much closer to Anchorage,the main bulk of load,than is Prudhoe Bay.With the many studies made for the other scenarios completed,the Kenai alternatives,with a 150 mile transmission distance,!/needed only few computer runs. As the costs of the versions within a group are nearly the same,the final versions were selected in such a manner as to minimize the work required for the detailed cost estimating.Ultimately,the following seven versions were chosen for final evaluation:(2), (4), (8),(9), (10),(13),and (15). !!Initially,a 150 mile long route was selected around Turnagain Arm. In the final round,an even shorter,90 mile route,with undersea cable crossing,was selected.This final version should perfonm even better. 06-32560B 07.0 SAG AND TENSION CALCULATIONS This section contains·the computer generated sag and tension calculations using Bunting and Chukar conductors.Calculations were performed for six ruling spans:1500,1200,1000,800,600 and 400 feet.Towers were limited to 100 foot heights,with 13.5 foot long insulators and 38 foot clearance to ground,thus limiting maximum sag to 48.5 feet.Conductor loadings were specified as follows: Special NESC Heavy o lb/sq ft wind pressure 25 1b/sq ft wind pressure 8 1 b/s q ft wi nd pre ssure 2.3 '1 b/sq ft.wi nd pressure No ice No ice 1.5 11 radi al ice No ice -60°F _60°F 32°F 86°F [ [.~ .~.iI G C G C [ [ L [ 25608 07-1 I ••ICO I._'ICI.IIC • I •••'.NSIO.M/',I.I NODULU. ALA.ra 'OWEI AU'MO.'T'11/01ln CA ...II 119Z.'ICC"I'"u ••un ·.u.n ...·tlAMUfll 1•.,OZO II WIII"Y,'.5440 LI/'T..I'A,1.00100 "1.'T.,'ZOOO LI·"ol.Of ILAna.,!toooo ,...""P.COI'F,0.000011''DII.' .'AI.400.00"I.'F.I.ILI'.-0.00" *LI"IT .t II 10"'.1'" C -...J I N LI"n....CON'1IT10IIUJ, A't0560 LI (2)AT'-6o .rl.'.oJOO I'ICI.0.00 'I'MI.D.1-0.00 ·"_'6000 1I1 U)n -60 1.1.',.0.00 II I cr.25.00 ,..MIND.IC-O.OO CJ "000 L.I U,AT SZ 11'1.',.r.50 II ICE.1.00'.,111111 ••80.00 10.·."",.ICI Milt r ';1:):.d·.:....fI....O••CLI)I n. ,IN "IF •n .."o.n IlYI UP.su,cn .,.·60 0.00 0.00 .00 .~,ZeISS.10SS'10160*10S62 H.01 ......2 ..........·60 _..0.00 ..25.00 _.00 ..........4.6'....._.._'291'...U9"..1296'40.55 .!JZ 1.50 1.00 .00 '''''.1..'4625 U641 146"n.91 ,.16 0.00 Z.50 .00 1.11 '416 SUO 5411 10.'0 cu ...OIlUMTAL TlllnOI CZ,"FEC TIVI •WElt_II 'IIUOI •.cn..U"•.IUPPORT.TIll 1011 _._....,.....,... i U,'TA"eUT IAI . ' ., ~'.110.MY M"MI LeN 'OIITcn, "'''T "'""LI'n "011 r.'Ute_t_.....1 .3440_0.0000 __'.5UO .~...ZOO.OO._l." ·Z·1.3UO 2.1U,S.OU2 ZOO.OO 4." .,'.S'2S Z••680 '.1"0 ZOO.OO ,••t 4 ~.,.'UO 0.149'.1.5670 ZOO ..OO ,.., AI'.L "._...O.00 .._.._ 0.00 0.00 0.100 UISTII.1. n'59'."599.5' 4CO.02 400.26 l_~....L~\.;.:(J....,~ l~ \,...,""j••) \':[[) ,\ ~.,...---;:.') l ~i··J _.,~ ,,,""J ..r-J c-J..r-J..'".-."\ II ••eo ".fIC"INC -••••"N.IOI W"IRII ~ODULU' UIOIIII C"ILt.1t'2.'IC~IL "C,."'1 ·'UN'IN'·'I.~I"I.'.3020 IN wrIIN'.t.1440 Lei",.R'••1.00100 ••IN "S.SZOOO LI .__._~Ol.'O'fun I..'550000 ''''.TI"'.CO""o.oooot U "u., .,.11.600.00 n ••".IN fLE'.-0.00" C -..J I W LI~I'."'COIll'IONCI', AI 10560 "'''fl)U -60 .E••'.-0.00 Itt lei,0.00'"WIN',.-0.00 I)....'6000 U .U)At ·60 .EI......O.OO II .ICE,.ZS.Oo ,.,WIN',.-0.00 ..__ C),.000 LI (2)A'52 D't.',".'o I.ICt,'1.00 ,.,WINI,1-0.00 t"'·.~.,,~,. 110 •..nil".lei III'I(...:;J'.:!'.It;:-.j~'.T.unIllCLI'I U'...',IN,.,,.".A "oRn An UP.IU'cn t ·60 0.00 0.00 .00 ,,.;"10.'80 S60S 1609 'U'f'.56 .....2 __·60_0.00 .....21.00 .•.aoo .~'S.'I t 0110 __.•on.....'on,_st.n --0._ !.52'."·1.00 .00 ·20.II ...·u,u .."000-teo"so.so ·.,16 0.00 2.50 .,00;,H.1O ,."5417 "05 '0." "ct)"CiRnO"UIl TlitlO". ...._.,....:..-i.iN.T Ci iii"IIII1I'" 12)"nc inl •tEUI'tellllO. _C5),..U"U,_'U"OItT_:..n.'.IO.__~·«')..'''""I'•••..'.'v·_·.-..-..-..--.•------..--".- .... :r:• ._...._~ .,.~--..."o.~'If "".WI "'...'01'11'''')....i.UNI".L Lei""'I'.T LI/',"'111.'tl'.""no-,__,.suo...--o.0000 __'.5440 _.500.00 __10.10 _._0.00 _.~_600.U _ ·I,;'.3UO·'1.712''..'.OZ7I SOO.OO U ..4I OeiOO .to.U S .:••51n z.lno 1.1110 500.00 ZO.26 0.00 600." ~...:,'.'d"O __0.24".,'.'''0 SOD.00 tI.rG 0.00 .•01.".. ___"_..,IAlCO IUnCl'UC -U ••"NIIO..II/,un "OIULUI 1t/OI/U '. C.ltl."'2.'.c,.~,e'l 4'"-.UNT'I'-1'1""11.1.5020 IINt'I"'.1.5440 LI"T.Aiel.'.00100 '1.1 I'"51000 LI _._....-_."OIt.'OP I ....n','~'OOOO ,..,TE"'.COE".01l0000U5 /tEl., I'AN-100.00"II".IN I~IV..0.00" ......._.f '. c....... I-r:=- LI"I,.I'COIDITIONel)1 A)10560 LI (2).T -60 .f•••,0.00 IN rCI,0.00 'I'III.D,.-0.00 1),_'6000 LI C2J ..AT -60 If'.'~0.00 II ICI,25.00 'S'IIINI,.-0.00 C.I"~OO "I CIJ.T 52 lEI.',1.10 II Ice,'.00 'S,IIINI,.-0.00 '.\t w',.....10•._TI"'..lei ..lUI .•..__;(:'.1/.:~.tel..OMICLI'I n. •llI'IF ."...ItOI II AVI U'.IU'en ,-60 0.00 0.00 .00 'a '.11 ,,:3962 59,.5998 1Z.49 ~2~60~0.00_u.00_.•OO..,..2"~"........1515 __..ISU ..'1401 ..26.25 _._ S'J2 '.'0 1.00 .00,'56..".,Il'U'U UCIIOO.unJ SOelt4 4 86 0.00 l.10 .00 Sl.S1 5264 5ZRO·5510 10.54 ,~'.'. C1t HOI.IONTAL tll'IO' (2.I"ICTI'I AVIIAIE TlI.IO.. ..C5LU"U .U"U'-U..1I0N __,_t,:;_,.._,__,_..._'_.._.._. :CUtu...,IU· >."'i'..,-.~. 10.·IIV ""III \LOll polin".•...&.UIIU.LLI'"LI"T LI"T \MOUI.VUT.fT "_.'__'.'440'"1."""O.OOOO~I ..SUO _400.100 _27.11_.O.OO._.__~10l.U ~ . Z .'.SUO ".2.rus "S.OUZ 400.00 29.tt 0.00 10l.12:'.s,••"n·,2.1610 .'_"'0 ,400.'00 56.n 0.00 .0Z.tl ..I:4 ..".:I .SUO..·/.0.Z4ft ,'.:I.uro ',400.00,ss."0.00 les..., ,rr'r"\ .(.,-~ r--, ) C:TJ c-J-rTl iI ___....IU.eo .uncn IIC -"'I'""II".,FlllEt "ODULU. ALl._A 'OV81 AUTROII'Y "/01'82 CAlLI."'2.'KC"'L AC.I ""-IUNT."'·.I."ETII.1.S020 IN VEI,.T,1.5'40 LI"'.A".,1.00'00 "'"ITS.5Z000 LI _11I01.0'fLASTt ':UOOOO.'IJ~n"'.COI",o.oooo'n IDU.' .,.".'000.00 """...N ILIV.-011I00 n 0.00 ,.,VI"',.-0.00 2'.00 P"IIIND ••-0.00 1.00 PI'v."'••-0.00 c...., I (J1 L'''ITI"'CO"DITIONC"• •,'0'60 LI CZ'At .-eo ••1.'_OJOO '"lel~ .•'._'eOOO.LI C2'.AT.-eo 'f'.'~.0.00 .1 ICf~ CJ "000 LI C'Z'AT SZ ....,•.'_'0 '"ICE. •.I ~~""r~i'w.•O.L~filii'.ItI •.If.'".*...l.:..•.'"!..~..""IIONlnl'I ItT. ,IN PI'n .,..."..Ho"n .AV'......UP (J' , .-eO 0.00 0.00 .00 ..,48.04)::'SlOI 3U':n12 ft.,., "'"Z ............·60 •.0.00._.2'.00 .~.•00~4'~"~7629 .._.._1619 ..."""UJ5,.• .532 '.10 1.'00 .00:56.I14·"t'I6'16000t tun 10.". :4 16 0.00 I.SO .00 ,.54.11 sur S'"Sl..10.15 I·ctt "IIO"!OlTA~"INIION ,..•.-_..-u"n d ••'''1111I.' CZt ",rtT'"."'.'E ""sloM .,..U'_"'ER ,''''OIT_Tl'''IO''..~,_.._.._.._.__._._ II t4 J '....!lIIT ••I '...;'. .:: ~.~. r--_..'I-.eo VlCII INC •UI'nNllo""',nlt ",IULUI AL ••IA '011'1 AU'HOI."U/O"II C.ILlt "'2.5 ICR.L .ell 45"·IU"'INI·I ••"E"I.t.5020 .N YfIIN,•••54.0·ll"'••IIA •••00.00 'tlN .,••52000 ..1 ~._._.._.."OD.OF lun.95.0000 'II.n"p.lCOE".O.IOCOO"S 'DU., .,.".'200.00 ,f '1".IN ILIV~O.OO,f ~I".'I.'CO"I"IO"(I». ~,.0560 LI el'.,-60 .,t.,.0.00 .N ICf_0.00 ,.,'1"'.1-0.00 .1'_16000 "I.en At,·60 'fl.'".O.OO.n.IU.25.00'".......aO.OO .._ C»'6000 ~I (2).,52 '.1.'"'.SO IN .Cf.8.00 'I'WJ'D,.-0.00 c...... Im 'f ~,.,,:.a-",......fI..,•.ICf..WII.•.._~....:~'.,nItONUU) ,IN PlF.·n.,.HOI1I .VI U,.SU, t ·60 0.00 0.00 .Ga'-·U.6D"3]05 5554 3402 2 ..........·60 .._0.00 _ZS.00 __..00--.;.....'.1-'20"'2f""_7ZU _..n'D _..1111 ,52 t.IO 1.00 .00 .OJ'12.'1 ",t··n.04 UOOO.tl393 .4 ••0.00 Z.SO .00 '9.60 S10'SUS Uti II"e]) to.,nH.n _".n ' 10.0• ."---'_."_._.-.,..-- " -'i',••_.~_._.•~.........J.-......"''N WI LOW 'O.N,e'f»••••L u".,.... ~,",til"LI'"NOI".v,.,~"" :-'....,...1.5440_0.0000_t.JUO_600.00 ...,....15.60._0.00 _._.tzU.11 ._.._ "Z '.'.5UO S Z.'UI .J.ozn '00.00 PI.20 0.00 U19.n ..:.J ..'.I7IS.'-:i.8610,.,.un 600.00 12.11 0.00·'UI.U ;.;..4.~::.t.SUO.!.~.0.i"',.:_t.~'70.....~'OO.00·.".60 ..0.00 ::.121341'1' I . l.~t j , ~·l~:.~~,rr----"'C.J ~ J 1______.l.i "--:;J,J .,.---. l J ·r---:t Cj .._..,...IUleo SlIVlUI IIC -....'111101 ""UU ""ULUI AUtl.'OW"AU'NOU,,'tt '01112 CAIU.1192.'ICC"""un 4'"-'U"TI"'"IU'U!,U,t.3020 ... WE'UNT,'.3440 lI"'.IIIU,1.00tOO .,..."'II 52000 LI___"00.0'lUST'_.93'0000.,....n",..cOl",o.oooo,n Itu.,. II".II ILI'.-..0.00 'T ~I".TIN'CONIITIONCI... at tono LI (2'n -'a eEl.'.0.00 IN ICI.O.OO'IF lIND ••-0.00 1'._16000 IJI U'AT .-60 ••1.',,-0.00 IN ICE.".00 'IF .IINI.IC-O.OO ._.__.. U tlOOO LI (2,AT SZ Dn.,.1.S0 IN Jell.1.00,.,IINI ••-0.00 to•.fI"'...lei .I....If ....~~•..Ut::!..TlIUO"ULIJ I ITI .,... ,IN'SF ".10Rll lin U'.IU'cn t -60 0.00 0.00 JOO 1It.29"JUJ 5ttl not to.55_.2 .._.:_-60._.0.00 .._25.00 ..,....oo ..........t.UJ.,,~.",,_._..11 n _..1366.25.02.__. .J'n,."0 1.00 ..00 '",29.10'"'91 .tlooo.t.III St.,... 4'It 0.00 2.30 .00 .U'.lO·501t·510'un to.OI u t'•••nON'AL ·,ii.i·""......,...L Cl.I"ICT.'.A'f~"'!""tIOI.J n.~.uPP.I ..IU"O IT_TI"'.O"...--,..,.,....._•._-..u.'.''''',UT ,"'..,." '._~....'~~.....~,r:~.......~.... 10.Wf WN ."'LOW '0Il,e'1''II.L LI'".~I"T ll'"RO~lr.,••,." ,....t...,.....'·.3HO ,-"".0.0000 ""1f"""5UO _."0.00._nt.l9 _._.0.00.__ .",.:t.5HO ',2.1U1 ,.ozn 150.00 nZ.19 0.00 !,.••1115 ..2."'0 ,'.''''0 no.lOo tn••o 0.00.;.t.sua.~0.14".:.t.5810 ."0.00 ,,'.lO .0.00 U""".Ln tUS.S2 U2I.52 Ul6.f) 1'21.11I 'U.co ''''Iui.lie ~IA,I ,nlloll 1I1'.lIn .0DUlU. ALA ••*'OV.I AU'HO.t"11'01182 calli.Ust.5 U"IL AUI ",,,-"u,.....u"nu.1.4240 U 1tIIIH"1."'Oll/",.llAI 1.19'00 ••111 1"1 4'500 LI.............."OD.O'lLAn.tonoooo "1,TE"'.CO.".0.0000101 IDU.' .,....400.00 n II".IN ILI'.-0.00" ~I"I'I.I CONII'IOIC.). A)15219 LI C2)AT ~60 Ifl•••0.00 I.Ice,0.00 ,.,1111','-0.00 ~,)_.2J1'0 II el)AT -60 "1.',0.00 IN ICE,25.00 "'.ItINI,.-0.00 C)IS150 II C2).,32 ••1.',t.SO I.ICI,1.00 ,.,Itl.',.-0.00 c ........ Ico .,......'\.0.'.U"'.·IU.11111 •.iU.i.~IA •..c...TI"'IGUnl. ,.N PI,~n '.NOln AlII U'.'UIt 1 ·60 0.00 0.00 .00 '.2.21 ..,218 un,.,nl2_I ~.:~._~:;g ...2::g:-:::~:::~:;~~~"":::::.:::::..,..'6 0.00 2.SO .00 '.00 'au suo '031 cn HOIIIOIIUII TlIIIIOI .~I"1T .t II lonlllllli Cl)I"EC'I'I A"I.'I 'IN,IOIl""_cst_uppn.SUP'OI'-Tl...O.".._._."_........__.._....,•._ :Ut''ANIII'In . I n • (5. 5'-01.".51 '1.41to.11 10.·II'ItN III lIM ,oll,e".••••l;....",&;.,,,'LI'""nUl.VII".'".t.1.'''0 0.0000 .........1.'570 ...........200.100 Z.U 0.00 T;"":I ':'!!"1.'310~Z.9661 ",.nn ZOO.OO "-".'6 -0.00 .'_.'.'7."52 I.'U'7.17U ZOO.OO I."0.00 .;.;4 .:.t.7370.::O.ln,"1.""100.00 .'.00 0.00 "";... '....~:~.,.J:__.It,;.=.. .~ ·l l J ''-'''--'.·l J UNtU.l FT 399.n,,,.n",.u 400.16 ,.....-.-.11-"\""",I.c-r-::";.L:"')'.r-::J ,.u:-Jl.",t!.,,.i "~.cr:J ,'CJ r-,..z.) _.........•.IUtCO luucn .IC -....""1.0""'FlUI "nULUI AU".,O"U .UTHOI.n uloeru C.lli.'5".'~C".L ACI',.",·".'TI"-tIA"ITI ••'.4240 ." VEt,HT,'.'510 lll'T,AltAI 1."'00 ".N ITS'46500 LI .........."01.0'lun.,'0110000 'II.n",.cor".0.0000101 'eu., n".•"kn.-0.00 FT C -...J I 1.0 L.".'.'"CO"IITIO"""A)'52"~'(2)_T -60 I~'.'.0.00 .N ICI.0.00 'I'"'N',••0.00.,._uno LI 12"A'-60 tEG.,#O.OO.IN .CE.21.00 ,.."INt ••-0.00 U uno LI .2J AT 52 "I.','41st .N ICI.1.00,.,lIND,.-0.00 1f0._"N'•.IU.".".It ~li ••::~.n"'UNICLIU I ITI ,IN,'IF-'T t--II0lUI AV'UP.IUP UJ 1 -'0 0.00 0.00 .00 ~'.11 ·n276 un,'UU'35.0' ...2.---.-60 ..o.oo_.n.oo .....00 ~'''''.:..,....1",.__..,.,n_.11946 _40.92 ...•._.__ S'52 '.50 l.tOO .00 ...1'.'"2i5U U"2 ZZUS ..... .4''6 0.00 2.30 .00 n.95 6626 6US 6641 14.36 Ct)ttUItONUL "'''11'0 Ii'...-.....- .'.•i.ii..,At i'.0'"1.''' (n l"EunE .VEIlUI trl..OI_e n~u,pn .10,,."'_.1"'110"..._.....00....._..._ ...."TUIUT,In 'f , '.," 'io~"~..'"_.A·,-W"",,'"LOW ,..IITen,....i...U""'.L 'L~'"~I/'T LII'T "Ollt.VEIT.'T 'T...._,_,."'0_O.OOOG .....1.7370 _300.00 _'.12 __0.00 '''.36 ...._ 2 •'.15'0 ;.2."61 ,.""300.00 1.11 0.00 '''.56' S ..:1.1952 .2..'."'.1145 300.00 n.n 0.00 ",." 4 t.n,o 0.272''.7SI3 300.00.H."0.00 eOO.50 _.I.ICO I"VICII IIC •.1.1 •'INI.O.M/.II.I ~O.UlUI ALU'A POIlII AUTIOU""/OI/n c...... I --'o CAllI,"S'.'leMll .CI.'4'"-NA'T'.-I ••NETE ••t.4240 INVErIM',f.l"0 11"'..'IA.1J1"OO s.r..,..4'300 II......_.._..''0 D."flLAn,10noooo '11.~.TE"'.CO.",0.0000'01 !DII., 1'••-'00.00 rt .....III ILIV.-0.00" llNtTINI CO.I.TIO"(I" At 'S,7'II eZI aT -'0 II ••••0.00 rN ICI.0.00 'I'V'.D•••0.00 ..I»-_251SO IA (U.AT -60 I,ll.',.0.00 ....ICEl.25.00 PI,VIND,..-0.00 ._ U ..15150 LI (It AT ""I.','.to II ICE',1.00'1f IU.',..-0.00 i ~.~.•0..:·_."N,..:,let........I._~tAt :"1..'nlllONlCl"•ITS ,.N'1f .1(,:;".MORII AWl UP.Sill'(n "-60 0.00 0.00 .00 ',,:.14.10,;'-,9U.9464 '411'20.41 ......Z.__.60_0.00 __u.OO._.00..,......;......!16~un'._.un7._.15211 _'2.11 ..-.-__ .S ..52 '.SO 1.00 .00·'r'26499 ,,.25010 uno.lUto '0.50 4"16 G.OO.2.50 .00 U.Ot I'"6'155 6160 13 ..so ...........:....-....I.~~•. ct.11011101'"'.11101 (2 ••"ICT1VI AVI'.S'""'0.rC5t....,,'1lt IU"OIt.TT.U ..IION·1 ,.,..,..--- ~.(4),ANIIlIT I.'.~'"· .."•I ..-...-.~....~'---"'_.'._......_.~---.. Lr--\, :r---._~t :.,;l ..,,) ,r---"l\,,)en cn ~. , j ~; J ~,~.,....-,-,,~.~'W"J "r::-:J '[7:"1 "c::J -rr-l rr:1 l ,.,;~11",)L,,,,""J r.o:-'"....I ..ICO IUVICU INC -I •••"".101 ,,',un "otULUI •alUlA 'OVU AU'."OU".U 108112 c••.".,,,t.,Kellll .U."'"•....u...IU".,EIU '.'''0 IN ""IMT't.1310 Ll/",U'.t'."'00 "IRI .",U500 LI _...00._.._."01.0.luna .,onoooo.,..,n",.cor",0.0000'08 ,."•• ......1000.00 "II".I"ILl'..O~oo", \ c...... i.......... LI-ITI".CO".1T10N(I', A""zr'LI CI'AT ·80 1.1••,0.00 I'ICI,0.00 'I'V,,,,,k-O.OO _1'._15150 LM el,U ..-80 IrI.',.0.00 IN IU.11.00 PI,Vlft.,.-0.00 ..~.__e'ZJ'~O LI CI,AT J2 .f•••,1.10 I'Icr.'.00 ....Vlft ••k-O.OO ....."O.'~'""'."IU,.VUI Ie .0'£....~~~..T"'IIGNSnl'I It",1ft "If ","ORII _ve UP.I"n, •-60 0.00 0 ..00 .'00 ~SO ..,,·?ttl ruo 1245 15." .......-1_-60 _.0.00 _".00_.00...........U.10..l..tl0OS_.UOU._15t"~..ZI.U ._._r S :52 '.'0''.00 '.00 .,41.*_~.2504'2S"0-15]6''0.4' ;.'86 0.00 2.50 .000 31.27 I1n 'If"SlZZ 12." '..'"(,,oiJlolni.··'rN.io"_.~......_.···.d"iT C)ii ·ioVlui". u'I'nc Tr VI AflUIl n ...OI w-,ULU'''ett .•u,'''~'-fl'''IOI "_'I'••_.__.__.,__.___ Il C4J,'Aftlnf .I.'.""i:L~~~·',·~<j~..~"'~.I'.~' II ~........::..&...:.:......_............ •••..'VI ,'"••LOll "III'H"....L Uft"I.L .. .L."T .L8I'T,Lit"IIOIttI.VUT."" :":!r."""t~'.'370."."...0.0000._.'.'37a _.,...500.00,...30.22 ._.0.00 __._'001·.1S __ t.'.2 .~1.7]10 '··1.9661 '.4]78.~OO.OO 53.tO·0.00 IOClt.n . '.!~.1.1932 .2.949J ';'.1145 100.'00 4ZelZl 0 ..00 'OtZ.1S •.oo:.4 .i,I.7"0 •.a·o.zn•..:'.."15 ..'00.00,.31.2'....0.00 '005.4Z _---I CO "ltVlCIl ••C ..-.III •nll.IOII ."IUt "OIUlIU' 'ALU..'0....AU'"On,'1"01111 CAlli."".1 I£RIL AC.1t '4'"-"."111-'IAnl"lt''.4240 I. WEIIN'.1.,srOLl/"••IIA.t.'9600 ".N I".46300 LI _....~_..."00.0'.un,.tottOOOo ,...U"'.COE",0.0000'01 Itfl.'.,,,_._.. ,'ANe UOO.OO "II'P.III 'LI'.-0.00" 0.00 ,.,MI ••,1-0.00 25.00 'I'MINt,.-0.00 1.00 'I'lINt,1-0.00 c..... I --' N ',...---, \..,I ' "u"nul CO.D"IOIIC,.. ·AI '5Z'9 111 (ZI AT -60 t'I.'.0.00 III Ie,. ,1).,.,.25150 .....eU.n.-60 .••I ••,..O..oo JlUEI.. CI .1"50 II C21 A'S2 ••••••'.50 .11 ICE, '.'•#-.""d'.•""J •lC, .1I0.·,..U"',,.lei ".......1 ...J.i._.•AI.L:..·.TI••UNULI'lin ,IN 'IF '\.fT·.,d,HOIU A"UP.SUP CSI ,-60 0.00 0 ..00 .00 4'~'"61U 6111 6UI 15.92 _l~-60..~.0.00 ,,;".00.......00......'••IO~.'"16_non ..12n4 ...26.,,-. i '"]Z '.50'1.00 .00 ~'.'or ,;:'22"Z uno.'5U''0.61 .•.6 0.00 2.50 .00 ,r~o,"61 1"1 166''2~24 C1',IIO"'.L '1.'loi'·~··_······~__·~····.ii ..·i'c",'ii'ii"••INi "~_._"_0' U,..,eCTln AVIUI.,......,..en...U'PER .au"o ITJIIIII.II ._..---::---_...__...--.-..--__._..__~ ,UJ''ANIEIIT IAI ':;"".' !,''.~....~~.~~. ......~.:.:.~..-~-~.~..:....!.~.;._. '0.ltV MM It.LOM ,.un".•••.L UII"R.L"lin ,&111fT ..,,,NGIU.VUT."" ~t.__t.'S10~.0.OOOO........1.75'O~600.'00.__49.21 ._.O.OO~nO••14 __ :..1.n1O··2.9661 .,.un'.600.00 ".10'0.00 1204.14......,...- ,'.1nl·2.94".,,_"n 600.00 61.01 0.00 nOS.'4 ~.•.'~.1.'''0 :.0.212'...,.rUJ ..600.00 ".OS ..0.00 n06 ... r---,', ,...-,~I'~r---j -r--I,..,J -c-1 .c:n .~~.)~'\'...I,.,,<", C:J,~ l '.:--u.(-J -J, ,...,.._tu.CO ''''flcn INC -SAl'TEN.IOJl "."UU ""ULU' ·ALA.,A 'OIl.AU'MO.r"n/Ol'" c..... I..... t" fAILl1 155'.'IC'IL AC'.,.",-"AIfIN-.rA~I'I••1.42'0 IN wrIIW'.1.75'0 ll/'T...EA.'."600 "1M Rfl.46S00 LI__."0'.0'I!un.touoooo ......n",.co.".0.000Ot08 "11.'..._.... .,AN-noo.oo "'lfPie III nn.-0.00" LIMaTINI CON.ITtONt.t • •t 1Il"LI el,.'-60 '.1•••0.00 IN tCI.0.00 P"WIN'••-0.00 It ....25150 LI ULAT -60 .n.''''~o.OO.IN lICE._25.00 'IF ........-0.00 CI 15"0 LI C2t A''2 ~'.'.'.50 IN ICf,1.00 PI'"IND ••-0.00 10•..fI"'•.·tCi '_"IIU'..K ...1h.·tA.L;f~.nll.""ULI)I ItTi ,IN PIP "'."IIOltll AYG UP.,UP en 1 -60 0.00 0.00 .00 '-,'4.4':·S8n 5161 595'u •., ......2._-60.0.00 --Z5.00 __00...-,-!6.17_t1206 __t nos __IU04 .._24.15 ...._._ r S .'n 1.'0 '.00 ..00 .,.,,~.12'02 uno.Z5641 1t.01 •.4'"6 0.00 2.150 .00 ft."UOS '4"""12.02· -----_._..._...__... I.'.•"J .~..• .,,'"',• •I ~..".Ii..,;~'..,J.:."""_,•.••.•.1· •••"'"N lit LOW POINTt"•.'••••L UNI'It.L L8/,t ~I'"Lit""~It.YERT.IT .T ...,..t~'.'!7Q.",.",..0.0000 '.1370 "0.00 _.14.40._0 ..00 .._n"__ :.-.1.1570'2.96"J.4511 no.oo 86e161 0.00 .'''.Be S·.'.1952"1.9495 '.1741'no.oo ft.",0.00 un.56 4:::.1.7570-:':.0.'12'...t."1S .no.ao.ft_"0.00 "14.24. ..__,IIA'CO nltvlu,nc -1A1'U""'"."11111 NODULUI AUIIA """AUTHO""UIOI'" CAlL ••"10 ICCI'lL ACllt 1.,"~C"UKAIt·'1.~e'll.1.'020 IN IIIIIMTI 2.0750 Ll/".U.AI Ie'''sao .1.""'II 51000 LI.....-.__..MOI.O'lun•.'''0000 'II.n",.c.e".0.0000115 11.1.' .,....400.00 n I."....'Ln..0.00" L.~ITI"I CO.'ITIO...... A)1'PSO ~(2)AT -60.1.1.'#OJOO I"Ice"0.00 'I'lit••"1-0.00 I)._.2UOO LI (U AT -6G lEI.'.0.00 ...ICI"25.00 PI,II -0.00 ""_ C)15500 LI (2)AT .32 11'1.'.I.SO ••Itl.1.00""II '-0.00 C "'.J I...... ,f:o .;16...,I'. ......':..T'"'.IItl.,,"'.IC ...;-.."._"1 "J,.l',.....0""U) ,ttl '1',i .n .,MOln UI U,..IU' t -60 0.00'0.00 .00 ·Z.4t·~.16111 uno-16ns_.,~T--;~.-~:~g_...z::gg ....:g:~::::7l:~;~-'--;;~~;'"''~;::; •86 0.00 2.50 .00·?16 1410 54"SU. ....-. C1.HO.lrON'AL """01 .~...T .J .1 .OVII..... en ,'UCflVI nlUI."...... .ULU"l!Il1 .•UPPOlf__n ._...-___,..__.__, .UJ .""11 If .AI ., I ItT, (]) 13.0' SI.OOn.46 10.64 -"'0-._- UN"".Ln'99."._....._ '99.11 400.00 400.21 .+:I, I t'r .~'..'... .. 10.1 IIV ""1111 LOW ,O"Tcrn u .... ."""'.L.",U","OUI.vur.IT_..._z.01JO~O.OOOO .....,.Z.0"0_200.00_~.2.47.~0.00 ,,::z.ono·S.ll"'••500 .ZOO.OO 4.06 0.00 '.,J ;',••ns·'.0610 1.440'·200.00 ••••0.00 4.1.0150.0.50'1 .1.0'"200.00.'.16 .O.00 l~l_~~,,!.'.,,:t,",;\-~il, l..r----JI,..,J I .. 'C"J .r---"'.~! ) .r--', ·1 "'~<-J ..~ ___."_.•Iueo 1 ..f1CIt INC -"'••"IU.O"II"un ""ULUI .UU~POIIf'1I .U'''OIlIT'"lOlli' C.ltl.1110 RC".L _CI~'4'"-CHUR.II-1._""'••1.6020 •• II.,'"T.1.0"0 LII'T,A.!A.1."300 ,I.N.RT,."DOD LI....__..."OD.or.III ..TI.....•6'0000'....n ..'.COlf'l o.oooo,n tlu•• I'AI-600.00,t In..II fLn.-0.00 FT , I LI".T."I CONI.TION"'. At '6130 ~I 'Z'_T -60 1'1.'.OJOO IN ICI.0.00 'I'liN',.-0.00 1'._2"00 Lt..elf..AT .-60 1181.'"o.oo.IN .lel.".00 ,.,III"t,ac-o.oo _ c'"SOO"I ez,AT 3Z 11 ••';".50 ."ICI.'.00 'I'III"',.-0.00 1I0•..tt..,•.ttl IItNt I .....l..al':~·.·~.""IIONlULi'I 1IT1 . ,IN .",."1t01l1l US UP.IUP en t -60 0.00 0.00 .00 ,.";:'~:t eU6 16.30-1613.53.0Z _2...--eo "O.004.U.OO_.00_~I""_2:f!t105~':"."'U._21131 41.4'-_ 3'U 1.50 1.00 .00.15.""'a!USI U59.24485 ".01 4 fI6 0.00 2.30 AD ."..UZ UU 1U1 un 14.21 U'"O'RlIO"TAL Ttl'-noi'.~....,....._....-i.l"iT"u i.iOflill'" CZ'."ICT.'••'.II.lr I.NtION .f 5)_"'U.11"".'-_'.11'10"....-....__-.--__...__.._...tu t.N""T tAl :.:.~. _..-:..~ NO .....II¥11M III Law POiNTfPT'....L UIIIU.L LI"T ~II'T UII'T "011'1.'PIIT."" .:.'__2.0150 _0.0000 ........2.0"0 __300.00 __I.n .__0.00 _..__.,,,•.,__,_- I '.0110'.3.3511'5.9300 300.!00 I .."0.'00 '''.45 3 '.863"'.0680 1.4401 300.00 '1.81 0.00 600.0' .4 I.ono ._.0.3011 2."16 300.00 t 3.02 0.00 600.46 .'-:'~.~~~ICI I ....,~.-r..~~-.•.__'...,-..__...._ UIO./U _.__....''''CO .uVlee.IIIC -IA.',nUIOI IIIPUIt IIODULU.L: ';';IILAtIA POIlIt AU'HOII" ~'.•... C.ILI."'0 ICIlIL AC.I 1.",·CIUI •••tl~~eTI'1 '.6020 r. IlEIIHT,Z.0750 LII'T,.'EA.'.5'300 ••IN I",,tOOO LI _-..--"OD.Of I'UITL.'690000.'''.,_fllII'.COlfF.O.OOOotts 'DU.'..._.,__. "AI.100.00'T DI.'.II I~I'..0.00" o...... I..... 0'1 '..h I·.~L~~ LIII',••,CO.DITI0~CI.' A''6150 LI (Z).,-60 •••••,0.00 I.ICI.0.00 ,.,liN.,••0.00 _......25100 LI CZI .n -60 Dn•••_o.oo IN lef•.21.00 ,.,lUND.It-O.OO .__ ..CI ISSOO LI en AT 52 .11.'_'.50 II lei.'.00 PI'IIINt ••-0.00 ..",•'Ii:.~,.O~::':;'·tlll'~u.Itl IIUD ...I ._.~...~'TI....O.UL.'I .TI._. ,IN ,.,~.n '.'"1I0.U .VIi U'.IUP en t -60 0.00 0.00 .00 ~u.n·,tUU tun 11272 22.10 ~Z~_-60.......0.00.,..zJ.oo_.oo~.t.I9._..t1S40 ........11165 _.._t7610_34.15 __ •i J.;'52 '.SO 1.'00 .00·:1lI.i··".60 ~un5 USDO-uno so.z' ~~o:'4 '6 0.00·z.,o .00 .U.'S6 'no,7146 ""14.0' ~,.\..'~..'~-.,.-.'.:.............,..,.-._._.. ft)..0.1I0.TAII n"IOI'-U"IT CJ II .0....1•• U'."EeTIIVl AVIIA8f '11'.'1 .' ~::}~;:::~i~u:::n_TlI'101l._,,;,:?,,1.-'-'-:"""------:---~"-_._--_.----._ ',',.."'.;;'.'l: ',~'':~:.=....,~I~......,'~.....;~,....".._,.,._.~.01._..... .0."V ""W'lOll 'Olllnn).•...L U"".L ,.U"T,LIIfT....lfT HOIiI.VIIT.:IT FT ~t.;...2.0"0-r-0.OOOO ........2.07S0~.•OOelOO_.14."..........0.00 ..._._100.'':-,-_ '.,i 2 'z.ono ..,'.'511',.1.9500 ',400.00 H."0.00 10D.t! .""",".'.86SJ ,.'.0610 ...U07 :,400.00 26.'0 0.00 1e0.t6 ;.;.~.4·':~J.I.07JO;"':'~OdO".,_~.~I.O'"...400.00..n.t..0.00.10'.46 ,"---"; I ! f--:l I .,,.-..., '"J, r-J:\ r:-:---....IUICO tlllYlCU IIIC . -UI'n"lIn .."UU "ODULUI ALAII.""11 AU,NOlllt,11/01/12 C.ILI.1710 IC-IL ACI.""9 ·CNU••II·."AN!T'••1.6020 t_ Wfll"',2.0'~0 Llt'T,AIIEAI 1.51S00 '11""II ,tooO II _..."08.0'ILAna "90000 ,","",.cor".0.'00001"nn . II".I'ILI'.-0.00" ~"'-'--"-'- Lt"nUI cort ••fIOUU. A'16"0 LI (2'AT -60 .rc••,0.00 I"ICI,0.00 ,.,VINt,I-OJOO_It'..'5500 III (un .-'0 .n.F,..O.OO I"ICI,2S.00 ,.,IU"o,te-O.OO ·U znoo IA UJ AT U en...1.50 ...ICI,1.00'.,",,,,,1-0.00 .."e.~..tIN'•.lei II""I[..l~.-•.~:!·,"".UII.«Ut I I" ,I",..,;.n '..NOIIII AVe;U'.IU'(n 1 -60 0.00 O.00 .'00 ,:.so.~·,!8647 1668 11109 t ,.01 .....2 __-60 ..0.00 __11.00.__.00 ~2.":...-..'5058 _...U100 _..U1I6 ..Z9.1I._._. ;.,3 32 t.50 1.00'.00 •'.41.66 .znn ."'00-2U"'O.". •16 0.00 z.".00'51.".801 .ns .a",5." ·en NOItlO"Ut.""tlO""....-,_.-.-.L,Rn d ..'01111"1'" ·(2'.FFEC'IVE UIIA"""Uo"r-Ut_u,,,lt ..IU,,.''-Tl''1I0''_---.-__.........._.._.. ~.e.".'."nM'IAI . "0.v,VM ~.LOV '01"'('"••••L .'"',,'''L'I'"Lit"NOUI..,nt."_t z.ono......,..o.ooOO __Z.O~o._500.00 .._30.03 __..0.00 ''''.2.0150,3.3US .3.9300 SOO.OO JZ."0.00 ,'S .,.ans .S .0610 I.U01 'JOO.OO 41.66 0.00 .~._2.0150 .~.o.sOft:..2.091'SOO.OO 31.".0.00 ,.... ~.t·......::.;... .. .._~-'.; U""I.L "'"100t.lt.. tOC1.It tOOZ.11 1003,49 ......_IUleo "II'ICII .INC •1A1''UIION ""rnl "OIULUI :aullt.PO""tU'HOUt'""O'"Z C.ILI'"10 KC"IL ACI',.,"·CHUK.'·IIANETII'1.6020 IN "UCHT,z.ono LI"'.UU,,.snoo I"N .u,11000 LI •...._._.•._."OD.Of fUU,.."90000 P",UIlIP.COEfF,O.OOOOIU lin.,. I'.N.1200.00 "••,••IN ILI'.-0.00" LINt'r".CON ••TIONe.», AI "150 LI eZI AT -'0 .r••••0.00 IN ICI.0.00 P••VIN.,K-O.OO .IL.25500""1Z»If -60 "I.',.0.00.11I .CE.21.00 ,..IUfIIl,.-0.00 ·C»ZUOO LI CU AT 52 '0 II IIC!,1.00 PI'"IND,.-0.00 c....., I...... ex> ·10•..'If".lei "III'Ie ..•.:..:IAt .:....:-•.'"I"ONULI.,IN'.,.n ..\>,II0llU "VI UP.SU, t -'0 0.00 0.00 .GO ,41.'"7614 1101 717' _2-,.-..~60._0.00 __25.00_.•00._51.10.i.'5871 _.U'U ...14071 5 ]l 1.10 1.00 .00 A '0...~,.uu,Z"OO.2515' 4 16 0.00 2.50 .00 5'.01 "54 6674·6'S4 It)'1"110.'",i...,ol ....-....,.....-i..'lii'ci .1 10'••••". CI.,"ICTI,E A'I~.'I 11 •••0._U'UP,aI IUP'OIt_'"'''ON_.._~..___~.._,-_ I CU 'AN.n,lA, I ITIen.s.n Z,••O .•_..-._. 50.66 ".24 . .,", .,f'.-iio~L "'''--',,""'~...t.LOll POlinn...••L UU't.L LI/.,LI'"LI/'T 110111.,rl'.'T 'T ~''""'\'r2.0150"''t'':'"0.0000__'.0"0.......-600.00 __48.11.__. 0 •.00._..:.U04.64 _','a "Z.O"O ..~5.S'"S.'SOO·600.00 ,t.10 0.00 1204.64 1 .'.Ins 5.06'0 I.U01..00.00 60.11 0.00 120S.'. ·•.·,.ono ..:o.sort _I~O"'._600.00 .51.'0.0.00 1l0'." ------------...--....-._.'" .. ;.r---". ~_.\.)..rrr-',f'J r---'1.J ·..~ \,,,) ,r--:'I,t.'J',',,01)'c=J 'c--J ,....---, ;;r-\,J ,.........-"l )_."J .-----"'..J I ,...-_"__IIUSCO IUUUI INC •1A1'TeNIiON ",,,...""UlUS(. ,AlAtU '0111'AU'HOUn '''011111,. tAil'.,no ke"ll At ..I.",-CHUUI·tlunll.I.'OZO 1M NUCHTI 2.0150 LI/'T.nUt 1.5noo "1"usa 51000 LI ,...........,.__._."OD.or.PLAITI ..9690000.PlI•.UN'.COIF'.o.oooolnnu.,, .'AN.'SOO.OO "'1".IN fll'.-O.OO'T LI"I'I'"CONDITION(I". ••"B50 &.1 (Z)AT -'0 'Ia.,.0.00 IN ICI.0.00 ,.,"IN••·••O.OO _I)_'5500 ..LI (Z).n -'0 .n•••.0.00.IN ICI•.21.00 ,.,."I"'•••0.00 "C)2"00 LI CZ)AT JI ••I.F.'.50 IN ICf,1.00 's,"I"'••-0.00 :·.....0.·::"",...ICI ..."UI,'..It.~·:l~:~"i•.~.J!.TlN,IONUll)I ITI .,.<.. ,IN,.,'.n .:MOln "n UP.IUP (5) .,-60'0.00 0.00 .00 ;J.,;IJ..SI·~~1030 '0111 1205 u.ft ~.z_••o_a.oo_u.OO __.00-f!'.4S.;;...t2'".__.13'03 _13321 ...2••U._ \..J ..,.,32 '.'50 8.00 .'00 ::,",..."...2'U'..15S00-260n '1.0'" .,.'6 0.00'·'.50 .00 ".".4IS·.,..,.,.13JO'... ·~·th··ItO,noN'."Tllllroii'",_--·.iiRii ct'ii l.ni••NI.2)."'CTIVI An...",,,...... !'.I:C.3LU"U .•UP'OtlLYU...N,.ii.'-----..._.._....._-_.......-....-..,.__ 't'U'.TANlIlT '.1 ",;'~. ;~j'~i ..~,~~..... . .lJ~I'•...·Wi:ti;.na ~.....'~~~'.:..a ...:._~i..:...:_...~1 ..... NO~"'M ••LOW 'Ol~(")••••L UN'T ••L,LI/"~I/"~I'"NORII.VrIT..,'T~:t __,.0"O~0.0000....,....2.01'50........_3'0.OO_.I3.:"__0.00 _1511.11 __ ',/I ,.:I.ono ....,'J.SS1l '.,S.'300 .".no.oo .,.45.'0.00 .15ft.". 4'."J ,"'.Ins.S.O"O·I.UO'.150.00 94."0.00 "U." .~........~.1.0'50,:..:,..O.50lt .:._.1.0""....."0.00 "•.,...0.00 UU.09 [ [- ['~ [ c- -." r- L' nu E B C C· G [ [ [ L L_ e 08.0 FIGURES TABLE 0-8 LETTER S'tMBOLS BC -line charging MVAR at 1.0 per unit voltage G -generati on E -equivalent of the local area system GL -Galbraith Lake (150 miles south of the North Slope) OM -Prospect Camp (150 miles north of Fairbanks) FB -Fairbanks HE -Healy DC -Gold Creek MP -Midpoint R -resistance in per unit on a 100 MVA base X -reactance in per unit on a 100 MVA base 08-1 2560B AL T£RNATIVE A r .0025 x .0485 BC 315 1 1..0121 .0210 500 "VA EACH FIGURE 0-1 NORTH SLOPE GAS FEASIBILITY STUDY EBASCO SERVICES INCORPORATED E ONE LINE SCHEMATIC WITH IMPEDANCES 1400 MW capacity at Prudhoe Bay. 500 kV transmission system. 345 kV intertie in parallel between Fairbanks and Anchorage. intermediate 138 tV bus at Fairbanks ALASKA POWER AUTHORITY .05 200 "VA r .0063 x .0716 . BC 114 NCHORAGE 138 ....I-HE 345 .0211 I500 MVA .0046 1750 MVA GEN. '* -.0093 -.0111 -.........L.I_ -.0093 FAIRBANKS 500 Notes '*'200 MVAR -35 MVAR50Percentseries compensation For letter symbols.see Table 0.8 ----1...--........-O'!500 -..----..41-GL500 1 750 MVA EACH nc. C B o D, B '--_. [ [ [ C.ftJ L~_ [ n L [ {] ·b -n._·._b ____L --p [ _.J [-' '..._- ·-:'1 -[ ;-_1 -L [ -r -r -r r r -r .L :T~ F_L * -.0086 1.0121 * * 1 .0186 NORTH SLOPE GAS FEASIBILITY STUDY ONE LINE SCHEMATIC WITH IMPEDANCES 1400 MW capacity at Prudhoe Bay;500 kV transmission system;345 kV intertie in parallel between Fairbanks and Anchorage; no intermediate transformation at Fairbanks. FIGURE 0-2 DC 50u--,,,,_ ALASKA POWER AUTHORITY 1·0TAP 1 ANCHORAGE 345 r .0063 138 mi x .0716 BC 11~ - - * * FAIRBANKS 500 -.0093 -.0093 - ***r .0025 r .0046 x .0485 -.0093 100 mi x .0519 E BC 315 BC 83 lJ1 500 195 mi **-.0093 1_.0093 ALTERNATIVE AA !2m *200 MVAR -35 MVAR 50 Percent series compensation For letter symbols.see Table 0-8 _.. .._GL 500 1 -.0091~I·oT~ 1 I Th -.0057 .:°62.99 TAP NORTH SLOPE 345 * * I NORTH SLOPE GAS FEASIBILITY STUDY .945 .964 .952 DC 500-4""--"'- .935 LOAD FLOH No generation at Prudhoe Bay.Normal system configuration. ALASKA .POWER AUTHORITY ANCliORAGE 345 1.00 I I 1.~]~ t 109 *242 CASE AAI 1.02 ** ~AtRBA'KS 500t1311m ~ *200 MVAR**35 MVAR 50 Percent series compensation For letter symbols.see Table D-8 .- L_ C. o 6 C U [ ....- [ Lt__-' U"FIGURE 0-3 [...__...........__E_B_A_SC_O_S-E-R-VICES INCORPORATED [ ,-e r-~-: r [-- [-:- [ p- u [ [ [ ["' -,' [., hj [" .' L..J t: :_J L :_--J ,[ r r T' -r T" T 'r~ r.LJ * r1 I I FIGURE 0-4 NORTH SLOPE GAS FEASIBILITY STUDY DC 50o-----.....~ LOAD FLOW No generation at Prudhoe Bay.One line segment open north of Fairbanks. EBASCO SERVICES INCORPORATED ALASKA POWER AUTHORITY ANCHORAGE 345 1.00 CASE AA2 1.021].~.t 113 * FAIRBANKS 500 Notes .,.200MVAR -35 MVAR 50 Percent series compensation For letter symbols.see Table D-8 .' 7010 I II INORTHSLOPE345.970 - ~CASE AA3 s-']132 J!,"SANKS SOD 1.027]152 }52 ]120 IS,fI32 ~1.013 ~---'t U9 R- **-1319 I"=';; ~.---......~()\500 II FIGURE 0-5 NORTH SLOPE GAS FEASIBILITY STUDY LOAD FLm~ No generation at Prudhoe Bay.One line segment open north of Devil's Canyon. EBASCO SERVICES INCORPORATED ALASKA POWER AUTHORITY ANCHORAGE 345 - .993 * '*I-OPEN DC 500- '** I IrI I NORTH SLOPE 345 Notes 'It 200 MVAR -35 MVARSOPercentseries compensation For letter symbols.see Table 0-8 [ [ c c ; G [ [ [ L..•_. U [ T' --r --r [' T' 'f-. :-_.' L' A .l,_~ r -' .-,..; -~[ [ L [ '..I ["- ,.-_..-. .F' [ .'j [, ......:-J -L [-- -.-'.: _.1 L, i FIGURE 0-6 NORTH SLOPE GAS FEASIBILITY STUDY LOAD FLOW No generation at Prudhoe Bay.One line segment open ~orth of Devil 's Canyon. less one reactor. EBASCO SERVICES INCORPORATED ALASKA POWER AUTHORI.TY • 951 I 3.2l t 317 .5t t138 .5t t138 ANCHORAGE 345 1.00NORTHSLOPE345.968 Notes *200 MVAR -35 MVAR 50 Percent series compensation For letter symbols.see Table D-8 CASE AA4 1 flRBANKS 500 1.044 1 1 }344 }27 t235 1.004 f3~0 1.058 i129 ****ot t49~ E (If 500 ** OPEN 1.087 ~* .**.918 * OPEN T ** DC 500 .949 i1l8- * I IIT 1- * I I FIGURE D-7 NORTH SLOPE GAS FEASIBILITY STUDY DC 500-41-__.....- No generation at Prudhoe Bay.The 345 IcV intertie opened at Anchorage. EBASCO SERVICES INCORPORATED LOAD FLOW - ALASKA POWER AUTHORITY OPEN 1.074 ANCHORAGE 345 ** ~ *200 MVAR*'*35 MVAR 50 Percent series compensation For letter symbols.see Table CASE AA5 FAI RBANKS 500 1 I I 1 I r _t 109 *'*t286 II I r I NORTH SLOPE 345 C··· --- (j C C,- E C~ [ L _ Ci__ GL__ L n- L -- [ c-- [: r~­ [- [" [- F-- w ·C L ..[' ..-., .L .c [, ~~ L~: -; _'"._,J; [--.. _4 .C L~~, ·c __.:oJ -~ ,~t -f' T~ :r -r: J T- ~r: !:....J I I FIGURE 0-8 NORTH SLOPE GAS FEASIBILITY STUDY LOAD FLOW No generation at Prudhoe Bay.The 345 kV intertie opened at Anchorage.less one reactor. EBASCO SERVICES INCORPORATED 1.055 -t 104 **- GL 500 DC 500 - * ** ALASKA POWER AUTHORITY Notes *200 MVAR -35 MVAR50Percent series compensation For letter symbols.see Table 0-8 CASE AA6 1 flRBANkS sob 1 1 1 r ll09 *-t329 E I IJr_~T..--~1.148 3~d t306 NORTH SLOPE 345 •-~A~NC~H~ORA~GE~34~5---"---"'- * * r I I FIGURE D-9 NORTH SLOPE GAS FEASIBILITY STUDY DC 500 -4t---.....~ LOAD FLOW No generation at Prudhoe Bay.One line segment opened north of Galbraith Lake. EBASCO SERVICES INCORPORATED ALASKA POWER AUTHORITY ANCHORAGE 345 E I 11 CASE AA7 1.02 * * .970 FAIRBANKS SOD]131"]131 Notes *200 MVAR -35 MVAR 50 Percent series compensation For letter symbols.see Table D-8 f«·.91 ]1:: ]'441 I NORTH SLOPE 345 .957 n L CL * I I FIGURE 0-10 NORTH SLOPE GAS FEASIBILITY STUDY DC 500 --4....---4t-- LOAD FLOW No generation at Prudhoe Bay.One line segment opened north of Galbraith Lake.less one reactor. I;AASC~SI;AVICI;S INC~AP~AAn;D ALASKA POWER AUTHORITY ANCHORAGE 345NORTHSLOPE3451.058 Notes *200 MVAR -35 MVAR50Percent series compensation For letter symbols.see Table Q..8 'CASE AA8 FAIRBArnCS 500 1.034]2l']23'1 1 1 r t183 **-~390 E 1.035 CI4 500 ~*l273 100741 ~.041 *279 ~70 J I I r FIGURE 0-11 LOAD FLOW 1400 MW generation at Prudhoe Bay. Normal system configuration. EBASCO SERVICES INCORPORATED ALASKA POWER AUTHORITY. NORTH SLOPE GAS FEASIBILITY STUDY LOSSES= 76.6 MW ANCHORAGE 345 1.00 a E 1073 121 ~t 17 CP.SE AA9 1.0~~ 187 1T43I Notes *200 MVAR-35 MVAR 50 Percent series compensation For letter symbols.see Table D-8 ~t---..-OM 500 .996/Z1.4 FAIRBANKS 500 1.001 I 700]f233 I_lE 07 NORTH SLOPE 345 1.016/38.7 LL [ 8 C [ G [ '._o. [ ~~~ ~. [ -r Li [ ~Ii C't:, _...._1 '.c '._8 -~~ [ ~·r ··.~··f-·.. ..:::..:i- ,E, [' ~~t~ -1' -r: ·T; l~ -r * r ,.. I I 4/8 ill 18 NORTH SLOPE GAS FEASIBILITY STUDY FIGURE 0-1:2 LOAD fLOW 1400 *generation at Prudhoe Bay.One line segment out of service north of Fairbanks. EBASCO SERVICES INCORPORATED DC 500 ----4....---41- ALASKA POWER AUTHORITY 1 LOSSES- 93.6 MW ANCHORAGE 345 1.00~ 181 JIi 35 CASE AAIO - - ** .993 114.1 * GL 500 .991~ FAIRBANKS 500 133~105 ,.. 1364 f t208 OM 50~990~ 682 ttl04 -lLL...__ ~ *200 MVAR**35 MVAR 50 Percent series compensation For letter symbols.see Table 0-8 I I 10J242 I_18 H NORTH SLOPE 345 1.015/46.5 * r II NORTH SLOPE GAS FEASIBILITY STUDY FIGURE 0-13 DC 500 --411----1...- LOAD FLOW 1400 ,..,generation at Prudhoe Bay.One line segment out of service south of Prudhoe Bay. EBASCO SERVICES INCORPORATED ALASKA POWER AUTHORITY 1 LOSSES= 99.5 MW 1050 1t7 ANCHORAGE 345 1.00~ CASE AAll E r:A1 _KS 500 .ggO~ill187]48 187 t t55 FB 345"'---"'- 1.00/12.1 123 ~tz3 *- Notes *200 MVAR -35 MVAR , 50 Percent series compensation For letter symbols.see Table D--8 --l...--.......-(lot 500 .957~ [ L U, C C i rJ.,13 [ C L l.;_ L \L __ [ [ ,-- L [ [ [ n LJ fl L .n l C C ",! L L ....J [ _",.J [ -eJ L .-J -[ i--' L r~ ·L 913}[S9 1.018 1 I I 1400 MW generation at Prudhoe Bay.One 500 kV line segment out of service south of Fairbanks. NORTH SLOPE GAS FEASIBILITY STUDY FIGURE 0-14 DC 500 !"""""4I....--...:tt--.921~ LOAD FLOW EBASCO SERVICES INCORPORATED ALASKA POWER AUTHORITY LOSSES= 88.7 MW 1061 t fSI 441 ~t38 ANCHORAGE 345 1.00~ 179 ** E * CASE AA12 FB 345 .........__.._l.OO~~'184 t12- * * FAIRBANKS 500 LDOl~1 21]12 2171 Notes *200 MVAR -35 MVAR 50 Percent series compensation For letter symbols.see Table 0-8 -.....------lIt-OM 500 -e_--...........GL 500 I I 1 I I NORTH SLOPE 345 1.015~ r 892 ~t 65 L&J U-6: L&J (I) u..o81 148 FIGURE D-15 LOAD FLOW 1400 MW generation at Prudhoe Bay. One 500 kV line segment of service north of Anchorage. EBASCO SERVICES INCORPORATED ALASKA POWER AUTHORITY NORTH SLOPE GAS FEASIBILITY STUDY LOSSESE 84.1 ANCHORAGE 345 1.00L!L CASE AA13 1.009~~1'8A.KS 500 Notes '*200 MVAR -35 MVAR 50 Percent series compensation For letter symbols.see Table D-8 NORTH SLOPE 345 I I I I I .7]52 [- ~- [ [ [- [ [ r1....----"" r L. [ 6, C C i C [ [ L L i ~_o [ [ L [ [ [ [ r~ b,..~ [ , [ .J .L j -~j L I ••j L [ r~ r "[ t' [~ f'""!:--= r L- J I I I fiGURE 0-16 NORTH SLOPE GAS FEASIBILITY STUDY DC 500 ,~.......... .9 LOAD fLOW 1400 MW generation at Prudhoe Bay.One of the 500-345 kV transformers out of service at Fairbanks. EBASCO SERVICES INCORPORATED E I073t t80 LOSSES·76.5 MW ANCHORAGE 345 1.00~ CASE AA14 ALASKA POWER AUTHORITY **..v •.- ** 1.01 L1!.1 357]1" }44. * FAIRBANKS 500 1 * I I J I I NORTH SLOPE 345 Notes *200 MVAR -35 MVAR 50 Percent series compensation For letter symbols.see Table 0-8 -"---4~GL 500 ** ** I:::: 600 MVA ** r .0077 x .0864 BC 138 r .0076 x .0864 BC 138 FIGURE 0-17 EBASCO SERVICES INCORPORATED ......,.,..-...** NORTH SLOPE GAS FEASIBILITY STUDY ONE LINE SCHEMATIC WITH IMPEDANCES 1400 Krl capacity at Prudhoe Bay;two SOD kV transmission line circuits between Prudhoe Bay and Fairbanks and three 345 kV transmission line circuits between Fairbanks and Anchorage. ALASKA POWER AUTHORITY _.02581 r- TAP=1.0 -.0216 MP345I I II I .·I-.0258 ANCHORAGE 138 FAIRBANKS 3451--..l'-...._T_A_P=_1_._O...----4~ ALTERNATIVE B 1500 ttVAITA:1.0 ~ .0062 r .0018 x .0373 -.0109 1500 MVA FB 138 BC 242 .025 400 MVA r .0018 x .0373 BC 242 NORTH SLOPE 138 Notes *200 MVAR**75 MVAR 50 Percent series compensation For letter symbols.see Table 0-8 -.0111 .0046 1750 MVA,.014 750 TAP=l.OMVA_.._.._...._...._.._ \'- L [ C C 6 L [ [ [ L [ [ r= '-' nL ".! -[ or or [ r ~[ 1 r'·. I.,~, [ .~~., [ o[ of b.J 'L-.....; J~. L ••1 L. I _...,:.,;J .[ ...;J [ .1.015 o I ~191 Fa 138 1.00 ** FIGURE 0-18 NORTH SLOPE GAS FEASIBILITY STUDY LOAD FLOW No generation at Prudhoe Bay.Normal system configuration. i 146 EBASCO SERVICES INCORPORATED ALASKA POWER AUTHORITY L;SES-1.8 I I I 1.8 ~t 444 .6t t 148 ANCHORAGE 138 1.0L1L CASE B1 .~ 198 FAIRBANKS 345 -4~--""~--"'---"'­1.0246,!, * r-..1.P-Io18~.lt-l-.0....3}s.>------I ~131 NORTH SLOPE 138 .953".3 Notes *200 MVAR -75 MVAR50Percent series compensation For letter symbols.see Table 0-8 1.011 -4~--"'-(JII 500 -CASE 82 674 ..------;-.-1 I •~~---- 30 r L c- [- [ [ [ [ L n L.i .999 I I LOAD FLOW FIGURE D-19 NORTH SLOPE GAS FEASIBILITY STUDY 1400 MW generation at Prudhoe Bay. Normal system configuration.Generator bus voltage 1.05 p.u. EBASCO SERVICES INCORPORATED ALASKA POWER AUTHORITY LOSSES=Ji 110.3 t E 1040f t43 347.f 14 ANCHORAGE 138 1.0~ 1.027.. NORTH SLOPE 138 l.017~ ~ *200 MVAR -75 MVAR 50 Percent series compensatio ft For letter symbols.see Table D-8 c- o, c c [~ [ C i _" L 6 t .~ [ . CASE B3.~ .~CaQ-140 [ [ '[ CL 'C C..,.J [. ,.J C '.c.J [j __1 [ _.::.J [ .....-1 l ...J L,, .:...-.1 [ [ .[ [ n' .~ ....'r"P1>** II NORTH SLOPE GAS FEASIBILITY STUDY FIGURE 0-20 LOAD FLOW 1400 MW generation at Prudhoe Bay. Nonnal system configuration.Generator bus voltage 1.00 p.u. EBASCO SERVICES INCORPORATED ALASKA POWER AUTHORITY ANCHORAGE 138 1.00L2- 673~f19 f19 1Z5t t 16 FAIRBANKS 345 -4'-__~~__-4I...f ..._ .995/19.9 ~.---........~~500 .975 .964 ..........--.-..4~GL 500 NORTH SLOPE 138 .972~ !ill! *200 MVAR -75 MVAR 50 Percent series compensation For letter symbols.see Table 0.8 ." 250 t t 92 . FB 138 1.0~ FIGURE 0-21 LOAD FLOW 1400 MW generation at Prudhoe Bay. One line segment out of service south of Prudhoe Bay.Generator bus voltage 1.05 p.u. EBASCO SERVICES INCORPORATED ALASKA POWER AUTHORITY NORTH SLOPE GAS FEASIBILITY STUDY LOSSES= .132.8 • •.-r-~~---­ 27 663 I t 56 125 t i 42 FAIRBAtlKS 345 ~~---411""---411~--""""1.00~358 ~t 9 ." .992 663 CASE 84 - -..~---ll'-~500.961~ Notes '*200 MVAR -75 MVAR50Percentseries compensation For letter symbols.see Table D-B 700 f l286 t 571 NORTH SLOPE 138 1.012/55.3 ."." 681 t ~61 MP~51 I I.997~ GL 500 1361't123 .945/36.7 .:.r.JPEN .".".".".".944 c [ r [ [ co; [ n L.J [ o c C FJti C [ l Iit__ [ -r~ L .[ .J L .-! [ p-LJ _.J L, ~..i L.1 l- I_,...J L .J L .J [ r~ T~ .~ T' l L .J [~ .j r L.- .J ** ** - OAD FLOW FIGURE 0-22 NORTH SLOPE GAS FEASIBILITY STUDY 1400 MW generation at Prudhoe Bay. One line segment out of service south of Prudhoe Bay.Generator bus voltage 1.00 p.u. ALASKA POWER AUTHORITY MP~51-I f 1101 t J56 ANCHORAGE 138 1.0~ 660 ~t120 tI20 125t t 89 FAIRBANKS -345 ~.........._ .977/20 * • 250 t f 190 6Q-98 . .FB 138 CASE 85 ,..-----....t I.~ t 508 NORTH SLOPE 138 •964~ ~...--......~GL 500 .910/37.9 ~.....--......~lJ1 500.935~ ~ 'It 200 MVAR -75 MVAR 50 Percent series compensation For letter symbols.see Table D.8 1358 t t225 '" "'''' 513 ~t80 513 +t 80 1.006 FIGURE 0-23 250 t J 57 ,.Fe 138 1.00~ 1400 MW generation at Prudhoe Bay. One line segment out of service north of Anchorage. LOAD FLOW EBASCO SERVICES INCORPORATED ALASKA POWER AUTHORITY NORTH SLOPE GAS FEASIBILITY STUDY CASE 86 •t>---- 125 t t 33 FAIRBANKS 345 -4"'--~l----"'---""- 1.000m.366 ~t 13 *'" -.....--...-()l 500 .....r~* ......t----..-GL 500 Notes *200 MVAR -75 MVAR 50 Percent series compensation For letter symbols.see Table D-8 C L [ o C b L [ [ L 6 [ [ [ [- [ [' [ [ n L) r T~ [' T'· T~' I~ L -r·_":j_i ** 400 MVA TAP-l.O r .0076 x .0864 BC 138 .0258 ~AP-l.O~.0167 MVA EACH ** .025 F.B 138 167 mi r .0077 x .0864 167 mi BC 138 FIGURE 0-24 NORTH SLOPE GAS FEASIBILITY STUDY .025 EBASCO SERVICES INCORPORATED ONE LINE SCHEMATIC WITH IMPEDANCES 1400 fill capaci ty at Prudhoe Bay i two 765 kV transmission line circuits between Prudhoe Bay and Fairbanks and three 345 kV transmission line circuits between Fairbanks and Anchorage. ALASKA POWER AUTHORITY I I ANCHORAGE 13 t t 1500 MVA 1750 MVA .0046 l.066 TAP *FAIRBANKS 345 ~""---"---"----4""- OM 765 * r .0005 x .0138Be700 150 mi **- ** r .0005 x .0138 BC 700 - 150 mi r .0005 x .0138 BC 700 150 mi * --l....--'"'""'4I~GL 765 ALTERNATIVE C Notes *200 MVAR -75 MVAR50Percent series compensation For letter symbols.see Table D-8 .02 750 !"IVA EAC.H-"'-"'_~.....,j"""'''''NORTH SLOPE 138 ------------- - .987 - ot ~186.FB 138 1.00~ - LOAD FLOW FIGURE 0-25 NORTH SLOPE GAS FEASIBILITY STUDY 1.014 No generation at Prudhoe Bay.Normal system configuration. EBASCO SERVICES INCORPORATED ALASKA POWER AUTHORITY t I 1.025j151 ANCHORAGE 138 1.00&' MP 345 .ill1_88 0 °I I 1.033/-.4 I I I 190 LOSSES=1.6 '* *FAIRBANKS 345 ""'""4.---_..o4l~--_..o4l~--......_ 1.023/-.4 * * * '* CASE Cl '* '*'* * ~43 NORTH SLOPE 138 1.013~ 1.026 .-.ol....--.-.ot....GL 765 1.033 -''It---~~OM 765 Notes *200 MVAR -75 MVAR 50 Percent series compensation For letter symbols,see Table D-8 E C [ D C L [ [ L C [ [, [ c [ [ [' [ n LJ ........ NORTH SLOPE GAS FEASIBILITY STUDY 250 t ~1~ Fa 138 0 FIGURE 0-26 LOAD FLOW 1400 MW generation at Prudhoe Bay. Normal system configuration. i 10 EBASCO SERVICES INCORPORATED ALASKA POWER AUTHORITY 3sa+t 21 693 ~i 118 125t l82 ANCHORAGE 138 1.00i1l * *FAIRBANKS 345 1.02/20 O!'!765 }.... 1.042~ CASE ·C2 Notes *200 MVAR ....75 MVAR 50 Percent series compensation For letter symbols.see Table 0-8 350 t ~134 l536 NORTH SLOPE 138 1.092~ 696t t 181 1.001I1'002 NORTH SLOPE GAS FEASIBILITY STUDY 250t t 3 fB 138 .00Li.e.J FIGURE D-27 1400 MW generation at Prudhoe Bay. One 765 tV line segment south of Prudhoe Bay out of servi ce. LOAD FLOW EBASCO SERVICES INCORPORATED ALASKA POWER AUTHORITY LOSSES=t 20 82.4 ~ 1068 t f 3 356 +~1 ANCHORAGE 138 1.00LQ. CASE C3 t 640 NORTH SLOPE 138 1.086~ Notes *200 MVAR**75 MVAR 50 Percent series compensation For 1etter symbo 1s.see Table D-8 *690 J t 9 125t l 1 *FAIRBANKS 345 l693tt76 1.00~4 OM 765 1.OO.@.:.!** ** 366 ~t 24 1.004 **~3451 I .'f** 695 1~103 1.001~t 5 366 ~t 40 *z *******L&Jn-o E_ C [] C '_. C C [ C L U L _ [ [ [ [- [ [ [ L nu. ]~ r --[ oJ-- ! r-- -f~ of' L.o, * r .0077 x .0864ec138 ** HVDe TERMINAL AND FAI RBANKS LOAD COMPOSIT EQUIVALENT HP 345 167 mi FAIRDAMKS 345 ALTERNATIVE D * r L 167 mi AflCHORAGE 138 !!ill!. *75 MVAR No series compensation For letter symbols.see Table D-8 r .0076 x .0864 BC 138 .0167 600 ~IVA ALASKA POWER AUTHORITY NORTH SLOPE GAS FEASIBILITY STUDY ONE LINE SCHEMATICS WITH IMPEDANCES 1400 MW generation at Prudhoe Bay;HVDC transmission between Prudhoe Bay and Fairbanks and three 345 kV transmission line circuits between Fairbanks and Anchorage. FIGURE D-28 1;9ASCO SI;RVICI;S INCORPORATED [ [ [ [ [ L _..-! [ ___J J L [ *** MP 345 1.035~.1 .1 f t 31 CASE D1 HVDC TERMINAL AND FAIRBANKS LOAD COMPOS IT EQUIVALENTott107 FAIRBArlKS 345 l.OOLJ [ r··- [ [- r'L' [ [ [ rr 6_ ** FIGURE 0-29 NORTH SLOPE GAS FEASIBILITY STUDY No power transfer between Fairbanks and Anchorage.Nonna 1 system confi guration. LOAD FLOW EBASCO SERVICES INCORPORATED ALASKA POWER AUTHORITY ANCHmL\GE 138 1.O~ ~ *7S MVAR No series compensation For letter symbols.see Table D-8 [ {' [ [ [ [ [ I' L ..i *** 350 t la.63 MP 345--4.----...---....- •97J.al.6 E HVDC TERMINAl AND FAIRBANKS LOAD t COMPOSIT EQUIVAlENT 193 FAIRSAr 345 l.QQS.9 CASE 02 GENERATION 1400 MW HVDC LOSSES 70 MW FAIRBANKS 250 MW TO ANCHORAGE lOBO MW [ [. C D ~ 1_; E,; ,.I L L ---j L_.J C__J [ * •991l!.3 FIGURE 0-3C NORTH SLOPE GAS FEASIBILITY STUDY * LOAD FLOW 1400 MW capacity It Prudhoe 81Y.HVDC transmission between Prudhoe 8ay and Fairbanks.Normal system configuration. EBASCO SERVICES INCORPORATED ALASKA POWER AUTHORITY * 340 1020 t 183 3401f61 ANCHO~\GE 133 1.0~ AC LOSSES-60.3 MW !!!?ill. *75 MVAR No series compensation . For letter symbols,see Table 0-8 * * FIGURE 0-31 NORTH SLOPE GAS FEASIBILITY STUDY LOAD FLOW 1400 MW generation at "Prudhoe Bay;HYDC transmission between Prudhoe Bay and Fairbanks and one 345 kV line segment out of service north of Anchorage. * EBASCO SERVICES INCORPORATED ALASKA POWER AUTHORITY 500 J tl54 500l t 154 .970 G.9 5c OPE"l CASE D3 1000t 405 ANCHORAGE 138 1.04 349 I t 40 349 t ~40 .936 £J4.5 349l f40MP345~.-......_ HYDC TERMINAL AND FAIRBANKS LOAD COMPOS IT EQUIVALENT 1080 l t 318 FAIRBANKS 345 1.00 L'53.4 360.t 106 AC LOSSES &80.4 ~ *75 MVAR No series compensation For letter symbols.see Table 0-8 GENERATION 1400 MW HVDC LOSSES 70 MW FAIRBANKS 250 MW TO ANCHORAGE 1080 MW [ r~'- [ r1 L [ C- C~ [~. r L- iENERATION 1400"" IVDC LOSSES 70 ,.., :AIRBANKS 250 ,..,o ANCHORAGE 1080 ,.., CASE 04 HVDe TERMINAl AND FAIRBANKS LOAD COMPOS IT EQUIVALENT l080l1242 FAIRBANKS 345 1.05LJ].5 360l t81 351 ~*38 1.006aD.7 •MP 345----4.----.----..- * [. -r ...[ r: c [: [' -r .I.,..' [' C..J-' .[.. -< ~.:,.;: [-'_. r-' .J _J [, ..J [ , [ ._J C •._1 L .~ F * .997 L:3.3 * NORTH SLOPE GAS FEASIBILITY STUDY FIGURE 0-32 1400 MY generation at Prudhoe Bay;HYDC transmission between Prudhoe Bay and Fairbanks.Normal system configuration; voltage raised by 5S at Fairbanks. LOAD FLOW EBASCO SERVICES INCORPORATED * ALASKA POWER AUTHORITY 1024 t t74 341 ~l25 ANCHORAGE 138 1.0 4.. AC LOSSES •56.2 Notes ..75 MVAR No series compensation For letter symbols.see Table 0-8 ** FIGURE D-33 NORTH SLOPE GAS FEASIBILITY STUDY EBASCO SERVICES INCORPORATED LOAD FLOW 1400 MW generation at 'Prudhoe Bay;HVDC transmission between'Prudhoe Bay and Fairbanks.One 345 ltV line segment out of service north of Anchorage;voltage' raised by 5~at Fairbanks. OPEN1 CASE D5 ALASKA POWER AUTHORITY 3501160 MP 345 ~.-....._ 0.981LJZ.7 10011298 ANCHORAGE 138 HYDC TERMINAL AND FAIRBANKS LOAD ~COMPOSIT EQUIVALENT 1330-250= 1080 Net 332 At LOSSES 74.1 Notes *75 MVAR No series compensation For letter symbols.see Table D-8 GENERATION 1400 MW HYDC LOSSES 70 Mtl FAIRBANKS 250 Mtl TO ANCHORAGE 1080 Mtl c: o o [ G [ [ c: L [ r: L [ [ [ r [ [ [' r w" [J L [ J [ -~-j [ C i b_J 400.MVA.02 Fa 138 .02 r .0077 x .0864 Be 138 r .0076 x .0864 BC 138 ....r.lrY"'** MP 345 ~....--~.... -.0258 TAP-l.O ANCHORAGE 138 -.0195 FAIRBANKS 345 --It-__-4....__-4.....T_A_P._1_.0~~ AL TERNATI VE E * * * r .0068 x .0778 BC 124 150 IIi r .0068 x .0778 BC 124 r .0068 x .0778 BC 124 T -.0228 .0228 N..ATAPal.0 ~~~~.0133 I ~rs'~AJ.~AP..99 tHRTH SLOPE 138 !!2!!!. *100 MVAR -75 MVAR 50~series compensation For letter symbols.see Table 0-8 ALASKA POWER AUTHORITY NORTH SLOPE GAS FEASIBILITY STUDY ONE LINE SCHEMATIC WITH IMPEDANCES 700 MW capacity at Prudhoe 8aYi 345 kV transmission system with series compensation FIGURE 0-34 EBASCO SERVICES INCORPORATED [ .~.J L '~J [ i -j [ ** .987 i 137 FIGURE 0-35 LOAD FLOW No generation at Prudhoe Bay.Normal system configuration. EBASCO SERVICES INCORPORATED ALASKA POWER AUTHORITY NORTH SLOPE GAS FEASIBILITY STUDY MP 345~"'--.-...4"'- ~ 72 t 73 t 60 FAIRBANKS 345 ~'---....04~--....04~---41"'­ 1.015L3 * ~119 FB 138 1 0i:.,.3 CASE E1 1.001 .942 .98 .999 OM 345 1.009 .990 .951C.z .I IGEN.LOSSES=1.0J:.9~0 Ito t142 .023 .1 0 I I tUB NORTH SLOPE 138 .94262 ArlCHORAGE 138 1.oCllP., ~ *100 MVAR **75 MVAR 501 series compensation For letter sYlllbols.see Table D-8 [ [' [- [ [ [ l~ ,~ nL (J C o o L C G [ C [ ( c r l [ [ -[ f' [ 10PER 1.076 1.lsi FAIRBANKS 345 ......-__-4~f---+---....- 1.015 114 * CASE E2 1.0 .986 ~..... 147 1.024 .5 [ f' L." * FIGURE 0-36 I NORTH SLOPE GAS FEASIBILITY STUDY No generation at Prudhoe Bay.One 1i ne segment opened north of Fairbanks. LOAD FLOW EBASCO SERViCeS INCORPORATED ALASKA POWER AUTHORITY NCHORAGE MP 345 ....t---.........- GEN..980 ,1:.9~to -tIM sLol ..,o I ~ *100 MVAR**75 MVAR 50S series compensation For letter symbols.see Table 0-8 1.00 FIGURE 0-37 LOAD FLOW No generati on at Prudhoe Bay.one line segment opened north or Fairbanks with the loss of an additional reactor. EBASCO SERVICES INCOR~ORA TED I I ALASKA POWER AUTHORITY NORTH SLOPE GAS FEASIBILITY STUDY o I fZ07 Fa 138 2 t l25 3.21 t 263 t106 -."'r"Ir'"**_ MP 34>~..---...- ANCHORAGE 138 LOSSES= 4.26 • 1.061 * 1.056 CASE E3 .976 OPEN 1.109 ~ 251 J:'1.0~ J II NORTH SLOPE 138 1.019 . 1.lZ8 !2!!!. *100 MVAR ..75 MVAR 50~series compensation For letter symbols.see Table D-8 C· C o o C G [ ,. [ C '-'.. C C [ [ c. [ C" [ [:- F·' Li. C .[J..:..-. ~ _._1 [ C__J L...•.....'0 .cj [ L L, .~ L _i [ , r L, --r "[ -~ --Co 1" [ [ fl L * - .995 63 t tZ5 125 t j 481"FB 138 LOOLl}.2 FIGURE 0-38 NORTH SLOPE GAS FEASIBILITY STUDY LOAD FLOW 700 MW generation at Prudhoe Bay. Normal system configuration. 259 254 l i 50 MP 345 1.014Lz..M"---"- 327 ~ FAIRBANKS 345 ~"'---4~--~~---4~ 1.006L1!.1 ...- 1 * ALASKA POWER AUTHORITY CASE E4 1.00JLu.5 ()I 345 .995 1.05&.4 JiI~LOSSES-t~76 l.~700 ,t 231 E 67.3 68 3S~98 I }S6 SOO t fll3 ZS4 ~tS7 NORTH SLOPE 138 1.021~ANCHORAGE 138 1.0~ ~ *100 MYAR -75 MYAR 50~series compensation For letter s1lllbols.see Table 0-8 - I FIGURE D-39 NORTH SLOPE GAS FEASIBILITY STUDY LOAD FLOW 700 MW generation at Prudhoe Bay. one line segment out of service south of Prudhoe Bay. EBASCO SERVICES INCORPORATED ALASKA POWER AUTH.ORITY 317 I 254 MP 3450-01.._--liliii4i.- 1.00~3 FAIRBANKS 345 •99Sm·8 * ~ 57 * CASEE5 1.004 4+- 57 OPEJi 700 t GEN.1.0s~.0 IItLOSSES=c-;if'159 -.-700 t 276 £85.7 . •9~OPEN~.1229 I 700 IZZ9 489 t t 96 Z4~t 48 NORTH SLOPE 138 1.017L!§.5 ANCHORAGE 138 1.0& 1.041 ~ *100 MVAR -75 MVARSOSseries compensation For letter symbols.see Table D-8 C fJ C " C G [ [ [ ,. C [ n L .- [ [ [ [ r~ [ [ fw r: L c [ b [, ."'"" E .; [ L ** ** r .0076 x .0864 BC 138 r .0077 x .0864 BC 138 ALASKA POWER AUTHORITY I I-·~58 .0167 .0167 600 HVA "'P 345 .....,...--.......... ANCHORAGE 138 * AL TERNATIVE F 1500 MVA .0087 r .0018 FB 138x.0373 IC 242 .0087 .025 .025 400 "'VA **TAP-I.0 FAIRBAPU<S 345 r .0018 x .0373 BC 242 r .0018 x .0373 BC 242 NORTH SLOPE 138 ~....__~~(J1 500 ~.----4~GL 500 Notes *200 MVAR -75 MVARSOlseries compensation at the 345 tV line only For letter symbols.see Table D-8 NORTH SLOPE GAS FEASIBILITY STUDY ONE LINE SCHEMATIC WITH IMPEDANCES 700 MW capacity at Prudhoe BaYi 500 kV transmission between Prudhoe Bay and Fairbanks and 345 kV transmission with series compensation between Fairbanks and Anchorage. FIGURE 0-40 .J IL... 1 DO - .986 10025 LOAD FLOW FIGURE D-41 NORTH SLOPE GAS FEASIBILITY STUDY No generati on at Prudhoe Bay.normal system configuration. EBASCO SERVICES INCORPORATED ALASKA POWER AUTHORITY t Z16 FB 138 ~91 .MP34S ..........--........ 1.0~5 ANCHORAGE 138 1.00 LOSSES-}if 1.4 155 E t303 t 1S1 .999 * * * CASE Fl 1.042 --tt---....to-(J4 500 1.039 ........ 139 1.0Z8 .....jl-__....--.GL 500 J I I NORTH SLOPE138 .999 Notes *ZOO MVAR -75 MVAR SOS series compensation It the 345 tv line only For letter symbols.see Table D-8 Ru c: C o o C B C L [ [ L L [ .. [ C' C' [ [ [' [ [ [j [j L •.[ L ., [ [ .J f' L ._....J W__.:1 .[ .f] L ~T~ O[ l~~ T- t' T~ : 0[' T1 b I l123 Fa 138 1.~.9 .995 63 t l64 ** FIGURE D-42 NORTH SLOPE GAS FEASIBILITY STUDY LOAD FLOW 700 MW generation at Prudhoe Bay. Norna 1 system configuration. ALASKA POWER AUTHORITY 270 Ji 54 1.022 CASE F2 * 344---~ 78 *. FAIRBANKS 345 1.016&.8 .0Iam·6 (If 500 346t 478 275 1l20 * MP 345 1.01aLz...9 Gl 500 348 t ~1.01~.8'77 6 1.0sa5.4 JiI~LOSSES-t 73, t 253 E 35.7 J 3~0 l_03_I206 539 t f12l 210 ~t 60 NORTH SLOPE 138~03 ANCHORAGE 138 1.0~ Notes *200 MVAR -75 MVAR501series compensation at the 345 kV line only For letter symbols.see Table 0.8 ** .9961.009 125 t t ~138 NORTH SLOPE GAS FEASIBILITY STUDY FIGURE D-43 LOAD FLOW 700 ~generation at Prudhoe Bay •one line segment out of service south of Prudhoe Bay. EBASCO SERVICES INCORPORATED ALASKA POWER AUTHORITY MP 345~.-__..-04"" 1.0ILz.9 340 1.001 6 *340~f4 FAIRBANKS 345 1.00JLl5 * .97W.3 (Jol 500 345 1f15 .94~.3 Gl 500 NORTH SLOPE 138 343 f f8 345 1~15 690 1t 30 CASE F3 UJ U->a:: L&J *(1) ~ ~°1 GEN.1.05/60.3 LOSSES=~ 700 J t 359 E 42':J158 700JI 30.1 1__1 308 533 t {91 266 l t46 ANCHORAGE 138 1.0~ ~ *200 MVAR -75 MVAR50~series compensation at the 345 tv line only For letter symbols.see Table D-B D b B f)'tj C b C I- e c c c,_ C [ r-~'.. [ [ c [ [' [ Ruef,D.M.,1981.Experiences with Contaminated Insulators Under Arctic Conditions.SOHIO Alaska Petroleum Company. .. Commonwealth Associates,Inc.,1981.Anchorage-Fairbanks Transmission Intertie Route Selection Report. Transmission Line 0.9.0 REFERENG£S Electric Power Research Institute (EPRI),1982. Reference Book:345 kV and Above;2nd Ed. ~. [ C· C· [ [- [ l~Commonwealth Associates,1978.Model for the Ready Definition and ~---------------A/YPl'oxfmifte-Comparfson-of-Alternative-Hi gft -Yoftage -fransm1ssi onnSystems.DOEIET15916-1.. Ld .. r- L c c c [; L [, L [ L,. [ 25608 09-1 I I I I I I I I I I I, I I I I I oo APPENDIX E APPENDIX E FAIRBANKS RESIDENTIAL/COMMERCIAL GAS DEMAND FORECASTS JANUARY,1983 El.l BASE YEAR ENERGY CONSUMPTION ••••••••••• El.2 THE CONDITIONAL DEMAND FOR NATURAL GAS IN ••••• FAIRBANKS TABLE OF CONTENTS ... .. . . . . . . . ... ... ..E-35 E-6 E-17 E-l. .. . .. REFERENCES • • • FAIRBANKS RESIDENTIAL/COMMERCIAL GAS DEMAND • FORECASTS E2.0 El.O n L c o u [ G,. [ [' "' [, [ [ Ei i Tab 1e Number E-1 LIST OF TABLES TITLE FAIRBANKS NORTH STAR BOROUGH ESTIMATED 1981 ENERGY CONSUMPTION DELIVERED ENERGY, SELECTED END USES E-7 E-2 FAIRBANKS NORTH STAR BOROUGH ENERGY E-15 PARAMETERS USED IN THIS STUDY E-3 FAIRBANKS NORTH STAR CONDITIONAL GAS DEMAND E-23 POPULATION GROWTH AT 1 .43% E-4 FAIRBANKS NORTH STAR CONDITIONAL GAS DEMAND • •E-24 POPULATION GROWTH AT 2.30% E-5 PRESENT VALUE ANNUAL SAVINGS IN EXCESS E-29 OF $600 E-6 DELIVERED ENERGY,PEAK DEMAND MONTH E-34 r=L [ [ b [ -, " [ [~ [ [ [~, r'L __ [ r L~ [ C f ~ [ fj [ [ '-- L, L [ E1.0 FAIRBANKS RESIDENTIAL/COMMERCIAL GAS DEMAND FORECASTS The potential residential and commercial demand for natural gas in the Fairbanks area is dependent on the price competitiveness of natural gas with respect to No.2 distillate fuel oil and propane in space heating and water heating markets,and its price competitiveness with propane and electricity in cooking markets.The potential demand of natural gas as a cooking fuel is estimated to be less than 5.0 percent of the total potential demand for natural gas even if the gas were to fUlly displace bottled propane in commercial cooking applications. The forecasts of potential gas demand have been made conditional on the gas achieving discrete percentages of the total market for heating and cooking energy (10 percent,25 percent,40 percent,and 100 percent displacement of fuel oil and propane in heating and of propane in cooking).The size of the total market to which these p~rcentage~have been app1 ied has,in turn,been projected to grow at a 1.43 percent annual average rate from 1981 for the low growth forecast,and at a 2.30 percent annual average rate for the medium growth forecast.These growth rates are the rates of Fairbanks population growth implied, respectively,by Battelle's (1982)low forecast of the demand for electricity in the Railbelt area,and Acres American's (1981)medium forecast of Railbelt electricity demand. The prices at which residential and commercial users would have a minimum financial incentive to convert from fuel oil to natural gas for heating purposes have been derived.These "consumer breakeven"prices are basea upon the assumption that the maximum discounted payback period for consumers is 5 years.At the 1982 price of No.2 distillate,$1.22 per gallon,the calculated consumer breakeven prices are $9.58 per MCF for residential heating and $9.94 per MCF for commercial heating.In real terms,these prices,will rise annually at approximately the real (inflation free)rate of increase of fossil fuel prices in general.If this rate is the 2.0 percent real rate assumed by Battelle (1982)and Acres (1981),by the year 2010 the breakeven prices (in 1982 dollars)will have reached $16.68 per MCF (residential) and $17.31 per MCF (commerci al). E-1 3088A The presence of calculated break even prices is necessary for the forecasting of natural gas demand.However,breakeven price data and price elasticity data are insufficient for such a forecast in this case.These price and e1 astici.ty data are insuffici.ent because the. situation involves a new product (natural gas)competing with an existing product (e.g.,distillate oil,propane).Additional factors influence consumer demand including:1)consumer perceptions of the two products;2)consumer inertia;3)initial and/or unusual incentives offered by suppliers of the competing fuels based upon their calculated present worth of achieving certain market shares;and 4)other less defined factors.Because of these unquantified factors,conditional demand estimates have been forecast;and these are based upon price ana1ysi s alone. If natural gas is priced below the consumer breakeven level,users will have an.increased financial incentive to shift from fuel oil.For every 10¢by which the price of gas falls below the breakeven level, residential users will realize approximately $81.00 (in 1982 dollars) in additional savings (present value)over the estimated cost of conversion.If there is any s~gnificance to numbers like $500,one might expect extensive inroads against fuel oil to begin to be made if gas is priced below breakeven to cover conversi on costs and to achi eve this level of savings (measured as the excess of the present value of annual cash savings over conversion costs). One must recognize that the producers and suppliers of fuel oil are likely to respond to the intrusion of natural gas by either lowering the price of No.2 distillate or by offering other incentives.While the intensity of reaction by oil suppliers cannot be forecasted,it cafl be assumed that suppliers are capable of at least offsetting the price advantage that natural gas has traditionally enjoyed based on its reputation as a "clean"fuel.Therefore,the above calculation of consumer breakeven prices correctly ignores the fact that many . consumers might be willing to pay a premium for such natural gas properties. E-2 3088A 'r I (' L 'r r' [ ·f r-=Lj C L rL.-, [ L [ [ [ L L, L [ The conditi onal demand projecti ons derived are sumari zed below. DELIVERED GAS,BCF PER YEAR 1985 2010 c [ [. r: [ [ r'- L>, MARKET GROWTH @ 1.43 PERCENT 1O~of Ma rket 25~of Market 40~of Market 1OO~of Market MARKET GROWTH @ 2.30 PERCENT 10~of Market 25~of Market 40~of Market 100~of Market 0.510 1.275 2.039 5.098 0.527 1.319 2.110 5.274 0.727 1.818 2.908 7.720 0.931 2.328 3.726 9.314 r L C' n c [r b l ..... b L L co "" ,- rL These values represent the annual demand for delivered gas conditional upon the percentage of market penetration indicated,where the total market,defined in terms of effective MMBtu·J/is set equal to 100 percent of commercial and residential heating energy requirements plus 29 percent of residential cooking energy requirements.The delivered gas demand values were calculated based upon different thermal efficiencies for oil and gas fired units. .The demand for gas would not be constantly distributed throughout the year.Based on an appraisal of normal monthly heating degree day.s in Fairbanks,and an assumed indoor temperature setting of 65 0 Fahrenheit, approximately 16.6 percent of annual Fairbanks heating energy is !I Effective MMBtu·s are delivered MMBtu·s adjusted for the fuel burning efficiency of heating units and cooking units.For example, if oil burners are 65 percent efficient,one delivered MMBtu equals 0.65 effective MMBtu·s.. E-3 3088A 1/hI.'consumed in January,the peak month for demand.-Althoug coo~lng energy requirements may be more evenly spread across the year,the relatively small size of cooking demand,less than 5.0 percent of the total,suggests rather strongly that an apportionment of total demand according to the conductive heat transfer formula will yield a good .estimate of peak monthly demand.Use of this method implies the following peak monthly demand (January)for natural gas in Fairbanks. DELIVERED GAS,BCF PER PEAK MONTH Janua ry Janua ry 1~5 2mo MARKET GROWTH @ 1.43 PERCENT 1.0%of Market 25%of Market 40%0 f Ma rket 100%of Market MARKET GROWTH @ 2.30 PERCENT 0.085 0.212 0.338 0.846 0.121 0.302 0.483 1.207 r~ ..,r f' C f [ r L 3088A E-4 1/Heat loss is proportional to the indoor-outdoor temperature differential and inversely proportional to the insulation factor. At an indoor temperature setting of 65°Fahrenheit,relative monthly heating degree days is the appropriate measure of relative monthly heat loss. Peak daily demand duri ng the month of January can reasonably be estimated as 0.0322 (1/31)of the monthly demand times a factor that allows for extremes of cold.Between 1961 and 1982,the highest number of January heating degree days recorded in Fairbanks was 3002 (in January 1971).The January average was 2384.The ratio of the two (1.26)when multiplied by 0.0322 yields an appropriate measure of peak daily demand when their product is in turn multiplied by peak monthly demand.Thus,peak daily demand equals 0.0406 times peak monthly demand. --,..J [ L L L..., [ t, L L L { C...: 0.155 0.386 0.619 1.546 0.087 0.219 0.350 0.875 10%of Market 25%of Market 40%of Ma rket 100%of Market 3088A E-5 The daily peaks are given in the following text table. 0.005 0.m2 0.020 0.049 0.006 0.016 0.025 0.063 0.003 0.009 0.014 0.034 0.004 0.009 0.014 0.036 10%of Market 25%of Market 40%0 f Ma rket 100%of Market 10%of Market 25%of Market .40%of Market 100%of Ma rket MARKET GROWTH @ 2.30 PERCENT MARKET GROWTH @ 1.43 PERCENT DELIVERED GAS,BCF,PEAK DAILY January January 1~5 2mO Peak hourly demand,defined as 0.0417 (1/24)times peak daily demand is quite small.For example,in the maximal case of 2.30 percent growth and 100 percent market penetrati on,the peak hourly demand is only 0.0026 BCF,or 2,600 MCF. Finally,it is useful to note that any expansion of the Fairbanks steam district heating system could reduce the demand for natural gas below the estimates given above.On the assumption that the district heating system supplies only commercial and government users,the implied reduction is at most 15.0 percent of the estimates given above,since commercial use of gas is projected to be at most 15.0 percent of total demand. [ r c- [ [' [' [ r~ \~ E1.1 BASE YEAR ENERGY CONSUMPTION Table E-1 presents base year,1981,residential and commercial energy consumption estimates for the Fairbanks area.The estimates represent "delivered"energy,that is gross energy volumes mea~ured at the input ,' to the various energy-us'ing devices beiOng powered.These estimates reflect the quantity of energy that must be produced and supplied to the marketplace. For all Fairbanks residential and commercial users combined,the estimates show that fuel oil and propane supplied appraKimate1y 65 percent of the 1981 delivered energy used for space heating and water heating.Coal,wood,electricity,and steam supplied 1.8 percent,20.5 percent,8.0 percent,and 1.9 percent,respectively. Because the appropriate end use surveys have never been made, residential use of propane 1n lighting and appliance applications in Fairbanks cannot be separately enumerated.Fairbanks consumers use propane for space heating,water heating,powering vehicles,and energizing lights and appliances.!!Faced with this difficulty,it is assumed that propane accounts for 14.1 percent of the energy used for residential lights and appliances in Fairbanks.The resultant 1981 total residential consumption of energy for this end use,258 billion Btu's,results in an implicit per capita consumption for lighting and appliances that is consistent with national averages.21 !!A survey detailed enough to yield more accurate estimates of consumption by fuel and end use in Fairbanks was beyond the scope of thi s work. !I Using a July 1,1981 Fairbanks North Star population of 51,569 persons drawn from [3],estimated per capita consumption for lights and appliances comes to 5.0 MMBtu in 1981.The few national estimates we have seen place this figure between 5.0 and 5.5 MMBtu.See,for example [8],p.75. E-6 3088A ~r -r T' r r~ 'r' [' f' L b "r'...:.J ,C, ,.L ·"b··.:-.:- ~ L ,[ 'L .-J L ~ [ SPACE AND WATER HEATING Fuel Oi1/Propane**3,043,752 22.041 467,368 3.384 Coal 97,127 5,582 0 0 Wood 1,109,815 59,990 0 0 Electricity 322,071 94,366 108,974 31,929 Steam ******101,263 104,395 Other 163,591 TOTAL 4,736,356 677 ,605 LIGHTS AND APPLICANCES Propane 36,334 0.402 75,073 0.830 Electricity 221 ,511 64,902 149,000 43,656 TOTAL 257,845 224,073 2665B ***Less than 0.1%of residential total **Conversion to units from MMBtu·s at fuel oil rate Conmercia1 MMBtu'S Units*MMBtu'S Units* E-7 Residential TABLE E-1 FAIRBANKS NORTH STAR BOROUGH EST1MATED 1981 ENERGY CONSUMPTION DELIVERED ENERGY,SELECTED END USES and Propane --Millions of Gallons --Tons --Cords --Megawatt Hours --Thousands of Lbs.Per Year *Fuel Oil Coal Wood £lec tri city Steam [ [ Dc c· [; , L' 1;. [ L __ [. L::.._ C L [ [ r~ [~- [ [ C' [~.. P L~ Residential Space Heating and Water Heating:The estimates in Table E-1 were constructed in four steps: Step 1:According to the Fairbanks North Star Borough Community Research Center,University of Alaska Extension,Engineer AKe1 Carlson has estimated that the statistically average residence in the Borough would use 1,500 gallons of No.2 distillate fuel oil per year for space heating and water heating purposes if fuel oil were the fuel exclusively employed.Given that there were 22,751 occupied residences in the Borough on average during 1981,!!that oil furnaces have an efficiency of 65 percent,and that a delivered gallon of No.2 distillate contains 0.138MMBtu's,the implied total 1981 North Star Borough residential space heating requirement,measured in .. effective MMBtu's,is 3,070,000 MMBtu's. Step 2 Based upon a survey conducted by the Interior Woodcutters Association,and cross-checked with two additional surveys (see the discussion below),it was assumed that in 1981 this total space heating market was distributed among the available fuels in the following manner:63.8 percent,fuel oil and propane; 25.3 percent,wood;9.6 percent,coal;and 1.3 percent,other. 1/This is 5.97 percent more than the 21,469 units shown in the 1980 Census of Housing,the same percentage increase over the Census implied by the Borough's 1981 population estimate of 51,569 persons.(The Eie1son Reservation Census subarea is excluded from these figures.)In effect it is assumed that the Census .undercount (recognition of which would cause us to raise the number of estimated occupied residences)and the existence of vacant housing units (recognition of which would cause a reduction in the number of estimated occupied residences),cancel each other.The June 1981 Fairbanks Housing Survey conducted by the Federal Home Loan Bank of Seattle showed only an overall 3.3 percent vacancy rate for the area. E-8 3088A r r r r~ r r t, r L [ L r [ [' [ [ [' L f ~ r: L Step 3 Employing average equipment thermal efficiences of 65 percent for fuel oil heaters,55 percent for woodstoves,60 percent for coal burners,and 100 percent for electric heating units, estimates of delivered energy by fuel type for residential space and water heating were obtained.These are presented in Table E-l. Step 4 At MMBtu conversion factors of:0.138 MMBtu/gallon for fuel oil;17.4 MMBtu/ton for coal;18.5 MMBtu/cord for wood;and 0.0034 MMBtu/kWh for electricity,the MMBtu'estimates of delivered energy by fuel type were converted into unit estimates,(also shown in Table E-ll.!! Commercial Space Heating and Water Heating:The 1978 Fai,rbanks Energy Inventory [5b]tabulateq the number of businesses and the square footage of office·space'for each of eight commercial industries.For these eight industries,estimates of heating energy used were also provided.Inita11y,the list of industries appears incomplete with respect to all types of units encompassed by what would be defined as the Iconmercia1"sector.2/For purposes of ultimately determining the demand for natural gas in commercial heating,a comprehensive inventory of buildings is needed.This requirement is also considered in the 1978 Energy Inve~tory: "Data regarding numbers and types of businesses,as well as the commercial building specifications,are necessary for the initial analysis of the commercial sector.Such !/These conversion factors are fairly standard but will differ dependent upon how one calculates them.In the case of coal and wood,the estimates of MMBtu/ton and MMBtu/cord are taken from [5a].The estimate for wood is the mean for dry birch and dry spruce. 2/The eight.industries are:Hotels &~otels;Restaurants &Bars; Wholesale Trade;Retail Trade;Shopping Centers;Auto Sales & Service;Other Services;Entertainment. E-9 3088A raw data are available through a cooperative effort by the Borough Planning Department,the Borough Environmental Services Department, and the State Department of Transportation,based on Borough Assessor's records.The intent is to locate each building within the Fai rbanks area in order to project new development,ai r qual i ty,traffic,etc.Si nce these data a1 so 'inc1 ude the square footage of each building,it can be used for energy planning as well.II . A diligent attempt was made to include all nongovernment,non- residential,nonmanufacturing buildings in the data base.Since the total number of businesses for which 1978 energy consumption was estimated totalled 1,823 and since the total number of nongovernment, nonmanufacturing Fairbanks North Star labor reporting units listed for the third calendar quarter of 1978 by the Alaska Department of Labor was only 1,210;it appears that the 1978 report ,was comp1ete.l!For these reasons,the 1978 Fairbanks Energy Inventory estimates have been. accepted as the best avail ab1 e estimates of commercial sector energy consumption at a point in time in Fairbanks. The same report provided estimates of both delivered heating energy and effective heating energy used in the Fairbanks commercial sector in 1978 [5b,Table 25].The total of 528,000 MMBtu of effective heating energy,when divided by the Borough square foot estimate of space, yielded an average for 1978 of 0.175 t+1Btu of effective heating energy required per square foot of commercial office space. The estimates of delivered energy used in 1981 shown in Table E-1 were then constructed in six steps. !!A IIreporting unit ll is a place of business at which at least one worker is a salaried employee.Multiple locations for a given firm count as multiple reporting units.Many buildings contain more than one labor reporting unit.On the other hand,some reporting units are housed in more than one building. E-10 3088A -r r r T~ [ L. [ f~ LJ [ [ b • j L [.., ----, .x' r' [ ._J L._. L .-.J [ [ r--, L [ [ r> r- nc,o c c [ c C ! r~.·.13 tc ... [ ,-- L c- E Step 1 Estimates of the total commercial square footage to be heated in 1981 were made for each of the eight industries covered by the FNSB in the year 1978.For each industry these were defined to equal 1978 square footage plus the estimated change in square footage between 1978 and 1981,where the change was based on the estimated percent change in the number of establishments reported oy the Alaska Department of Labor for that industry.ll Step 2 The 0.175 MMBtu per square foot of effective heating energy used was reduced by ten percent to allow for increased conservation and reduced temperature settings.21 Step 3 A 1981 estimate of effective heating MMBtu·s used in the commercial sector was constructed by'mu1 tiplyi ng the adjusted per square foot heating requirement by the estimate of total square feet to be heated.The result came to 514,000 MMBtu·s. Step 4 As discussed below,59.1 percent of the 1981 commercial sector heating requirement (effective MMBtu·s)was estimated to be satisfied by burning fuel oil,21.2 percent by electricity, and 19.7 percent by steam district heating. Step 5 Employing average heating efficiencies of 65 percent for fuel oil heaters-and 100 percent for district steam heating and electric heating,the MMBtu requirement estimates of delivered energy were obtained,and they are shown in Table E-1. 11 See [7].The Department of Labor data are not as yet available for 1981.For all eight lIindustries"we defined the 1980-81 percent change to equal 2.0 percent. 21 There are no good estimates of this effect in Fairbanks.However, given the large.number of energy audits conducted there,failure to allow for at least some reduction in heating requirements per square f90t since 1978 would likely be a more serious analytical error than an assumption of ten percent. E-11 3088A Step 6 At MMBtu conversion factors of:0.138 MMBtu/ga110n for fuel oil;0.0034 MMBtu/kWh for electricity,and 0.970 MMBtu/thousand pounds for steam,the MMBtu estimates of delivered energy by fuel type were converte~into unit estimates (also shown in Table E-1). Lights and Appliances:According to data by the Alaska Power Administration and published in [4],total residential electricity sales by GVEA and FMUS in 1981 came to 159,000 megawatt hours.!!The electricity consumption estimate of 65,000 MWh for residential lights and appliances is the 1981 residential sales total less our estimate of 94,400 MWh for heating. The 43,700 MWh estimate of e1 ectricity consumed in the commerci a1 sector for lights and appliances is the North Star Borough1s pUblished 1978 estimate plus an increment of 8.5 percent.The 8.5 percent increment is the 1978-1981 percent change in commercial sector square footage estimated above,in Step 1. Direct estimates of the amount of propane used in the residential sector to fuel lights and appliances could not be obtained.Available national and Alaska estimates of the delivered energy used per capita to power residential lights and appliances suggest an average of between 5.0 and 5.5 MMBtu per person per year.2/The estimate was set at the MMBtu level which brought Fairbanks total residential delivered energy use for lights and appliances to 5.0 MMBtu per person per year.The resultant 36,300 MMBtuls of propane energy (402,000 gallons),comes to 14.1 percent of the total residential delivered energy estimated to have been used in 1981 for lighting and appliance app1 icati ons. !!GVEA -Golden Valley Electric Association,FMUS -Fairbanks Municipal Utility System. 2/The Kake end use survey led to estimates of 5.4 MMBtu per capita for Kake.National estimates also are in this range,for example, [8],p.75. E-12 3088A r ·C r: ~. [ [' [ nL f' L [ [ [ [ .c L [ L -' C [ The similarity of the estimated percents using fuel oil is notable as shown in the text table. The estimate of commercial propane use is the Borough's 1978 estimate [5b,p.45]with the value for cooking uses increased by the estimated 1978-1981 employment growth in the industrial category "eating and drinking places"(11.5 percent).!/ All three of these surveys were designed solely to estimate the percent of Fairbanks residences which used each of several fuels for primary and supplemental purposes.2/Noneof the surveys attempted to measure total consumption of each fuel type by end use. BATIELLEY 66.5 8.8 15.2 3.0 4.0 2.5 FCAC 61.2 22.7 9.6 1.8 1.3 5.7 WOODCUTTERS 63.3 25.3 L8 1.3 0.5 0.2 PERCENT OF SURVEYED RESIDENCES USING FUEL AS PRn~ARY HEATING SOURCE 1981 E-13 The 1978-1980 published Alaska Department of Labor rate with an added 2.0 percent assumed for 1981.Alaska Department of Labor [7]..' The Battelle survey also requested information on fuels used to power lights and appliances. Weighted average of responses for space heating (85 percent weight)and water heating (15 percent weight). 2/ 3/ 3088A Fuel Oil Wood Electricity Coal Propane Other Estimating Fuel Shares:Heating:There have been three residential end use energy surveys conducted recently in the Fairbanks North Star Borough:(l)a 526 response survey conducted by the Interior Woodcutters Associ ati on [6J,(2)a 616 response survey conducted by the Fairbanks Consumer Advocacy Committee and tabulated in (5d];and (3)a 408 response survey conducted by Battelle Northwest as part of the Rai 1be1 t El ectric Power A1 ternatives Study. II [ [ o c C ! . L [ L , L; [ I [ Weighting each set of survey results by their relative number of responses yields the following estimates of percent of Borough residences using each fuel for primary heating:fuel oil (63.3 percent),wood (19.9 percent),electricity (10.5 percent),coal (1.9 percent),propane (l.2 percent),other (3.2 percent). For purposes of this study,it was assumed that these percentages also represent the respec-tive shares of the residential heating requirement (effective MMBtu·s)satisfied by each fuel type. No direct 1981 information is available for the commercial sector.The FNSB 1978 Energy Inventory [5b,Table 25]showed that commercial sector heating requirements were then supplied as follows:59.1 percent,fuel oil;21.2 percent,electricity;and 19.7 percent,s~eam.Since 1978 ..the average commercial price of electricity (¢/kWh)in Fairbanks has gone from 5.5¢/kWh to 8.5¢/kWh,while the price of fuel oil has risen from 55¢to $1.22 per gallon.!!Thus,the relative price of commercial electricity has declined by approximately 30 percent.In spite of this drop in relative price,electricity as a source of commercial heating energy remains over twice as costly per effective MMBtu as fuel oil in Fairbanks (Table E-2).The high 1981 relative price of electricity argues against there having been an increase in e1ectricity·s share of commercial heating between 1978 and 1981, despite the decline in re1~tive electricity prices over that period. Further,since 1978 there has been an annual average 2.5 percent decline over this period in total electrical energy generated by GVEA and FMUs.2/Faced with this eVidence,and in the absence of direct data,the share of space heating and water heating energy requirements met by electricity has been held constant at the 21.2 percent estimated by the Fairbanks North Star Borough for 1978. !!Price quotes are taken from [5aJ. 2/Alaska Power Administration [4j. E-14 3088A [~ r- ---,j. ['- L- e;..• [' f- e- f'. L., C L [ [ r b.~ C L [ I [ C, C [ TABLE E-2 FAIRBANKS NORTH STAR BOROUGH ENERGY PARAMETERS USED IN THIS STUDY Natural No.2 Oi 1 Gas'Coal Wood E1 ectricity Propane Steam Units Gallons 'MCF Tons Cords kWh Gall ons I ,000 Ibs MMBtu's/Unit .138095 1.02 17.4 18.5 .003413 .090476 0.970 Heating Efficiency*.65 .75 .60 .55 1.00 .70 1.00 Unit Prices**(1982)1.22 62.50 96.25 .109 1.24 6.50 Prices Per Efficiency MMBtu 13.59 5.99 9.46 31.93 19.58 6.70 *Efficiency of wood burning predicated on FNSB estimates for airtight stoves. **Price Source:liThe Energy Report,II August 1982,Fairbanks North Star Borough Community Research Center No.2 Oil -January 1982 through August 1982 monthly mean;August 1982 =$1.216 Coal -Augus~1982,wholesale price per ton,2 tons delivered Wood -August 1982,dry,split,delivered,mean of birch and spruce Electricity -August 1982,1,000 kWh,mean of GVEA and FMUS commercial and residential (rate with cost of power adjustment for GVEA) Propane -July 1982 Steam -July 1982 E-15· 26658 According to Keith Swartz of the Fairbanks Municipal Utility System, 152.3 million pounds of steam were sent into the district heating system in 1981.Indications are that the 1981 steam sales to the commercial market are not significantly different from the steam sales to the commercial sector in 1978.11 The 1978 estimate for steam heat as a percent of the total co~ercia1 heating market,ther~fore,also has been held constant at 19.7 percent.The resultant 104.4 million pounds of delivered steam heat,allowing for line losses and other users,is consistent with the 1981 total FMUS production of 152.3 million. Since fuel shares must sum to 1.0,retention,of the 1978 electricity and steam shares of commercial heating requirements implies retention 'of the fuel oil share,59.1 percent. Relative Prices:Information ~n the various energy parameters used in this study (Btu content,heating efficiency),recent 1982 unit prices for each fuel as delivered and the equivalent prices per effective heating MMBtu for each fuel,is presented in Table E-2.The latter prices are defined as the unit prices divided by K,where K is defined as the product of the efficiency factor and the MMBtu's per unit.No natural gas prices are presented because natural gas is not now commercially available in Fairbanks. Two points are 'worth noting. (1)All fuels identified,except electricity,are fossil fuels. Electricity itself is 100 percent fossil fuel generated in Fairbanks (fuel oil and coal). 11 Commercial consumption has accounted for over one-half of all the .steam generated for heat by FMUS.Thus one wou1 d expect that signiflcant changes in commercial consumption would appear as significant changes in total consumption.In 1978,FMUS received payment for 130 million pounds of steam.Allowing for transmission losses this figure is not greatly out of line with 1981's 152.3 million pounds of steam produced. E-16 3088A '-r r r: f' r~ [ L f' ,L" f~ ~l:_~ :6' '[ 'L ..,I C" _.--~ -,j [--.---, ,r' [ _I L__J L .......j L -.J :[ I --. [ r [ [ f. [ [~ [' ~;-' c [ IJ C· C E E L ....--~ L, L [ (2)Given the very high relative price of electricity as a heating fuel,and the fact noted above that its relative price was even higher four years ago,it seems reasonable to assume that residential and commercial users of electricity for space and water heating purposes are either ignorant of the price d;sadvantage they face,or have some other reason for preferri ng electricity as an energy source for heating. The following analysis and the projection of the conditional demand for natural gas as a space heating and water heating energy source is based on the assumption that the demand for natural gas is determined by its price sUDstitutability for fuel oil.The real price assumptions used by Battelle Northwest [2]and Acres American [1]assume for all real fossil fuel prices except coal to escalate at 2.0 percent per year, with coal prices escalating at 2.1 percent per year.Under these price escalation assumptions,1982 relative prices remain essentially unchanged throughout the forecast peri od,wi th the excepti on of prices relative to electricity.However,even if real electricity prices are assumed to remain constant,fuel oil prices per effective MMBtu remain 26 percent lower than corresponding electricity prices in the year 2010. E1.2 THE CONDITIONAL DEMAND FOR NATURAL GAS IN FAIRBANKS At this time,the minimum required price for natural gas,delivered to residential and comercia1 users in tairbanks,has not been determined.That price is a function of the wellhead price of gas,the cost of conditioning the gas,the cost of transporting it to Fairbanks, and the cost of distributing it within Fairbanks.It is based upon the ability of system owners to achieve an acceptable rate of return on their major capital investments.The purpose of this analysis, therefore,is to estimate the demand for gas,conditional upon price. These conditional gas demand forecasts are formulated under each of two sets of economic assumptions.The first set includes those assumptions buttressing Battelle Northwest's "low"electricity demand projection of E-17 3088A February 1982,while the second set includes those which buttress Acres Americanls 1982 Il middle ll projection.lI With respect to the e1ec tri city demand components,both the Batte11 e H1 OW II and the Ac res I IImiddl ell forecast are products of the Rai1be1 t Electricity Demand model,developed by the University of Alaska for the Rai1be1t Electric P"ower A1 ternati ves Study. For the foreseeable future,the increasing demand for electrical items, such as new office equipment,electronic games,and electrical appliances,has apparently convinced Battelle and Acres to forecast an increasing per capita demand for electricity in A1aska l s Rai1be1t.In contrast,it would be wholly inappropriate for us in this study to project an increasing per capita demand for fuel oil or natural gas. The relative price assumptions discussed the end of the proceeding chapter indicate that one cou1 d not "reasonably project more than a small fraction of the demand for premium fuels to be for purposes other than space heating or water heating.2/ Rising fossil fuel prices have induced a reduction in effective heating energy requi rements across the Uni ted States.Such conservati on does not appear to have reached its technological limits.For this reason, this study does not simply adopt the rates of per capita increase in electricity consumption and apply them to natural gas d~mand.Instead this study derives the underlying Battelle and Acres rates of Fairbanks population growth and makes natural gas consumption projections a function of constant unit consumed/person values. 1I See [1]and [2]. 2/The potential demand for gas in Fairbanks will be estimated from the point of view of its SUbstitutability for other fuels in specific end uses.If natural gas were available in Fairbanks,it undoubtedly cou1 d fuel some decorati ve 1ights and be used as a cooking fuel in some kitchens.However,demand from these sources is likely to be either very small relative to the demand for gas as a heating fuel and unlikely to increase in per capital terms. E-18 3088A [ ,_J C .~..l [J ..)' C '-~ L _c·....,; ,[ ,"J {, lJ ,-[ ,,,,...j [ 3088A E-19 The data bases to which these two equations were fit are the six sets of simulation results given on pages 3.8 and 3.13 of the Battelle report [2];and the nine sets of simulation results given in appendiX Table A3 through all of that report.!! Because the R2 values were very high,the results of this study are consistent with the earlier work.2/In particular,the rate of population growth (annual average)in Fairbanks that is consistent by this definition with the Battelle 2.2 percent rate of growth in Six Observations .7237*Rai 1belt E1 ectricity Demand (14.2)%Change x 100 1980-2010 =-.0326 +.9299*Rai1be1t Pop. (-7.6)(6.0)%Change x 100 1980-2010 R2 =.9954 Nine Observations =-.0192 + (-9.6) R2 =.9991 Fairbanks Pop. %Change x 100 1980-2010 Railbelt Pop. %Change x 100 1980-2010 (1) 1/Alaska Economics,Incorporated calculated the 30-year compound annual average percent changes from the pUblished simulation results and then ran the indicated regressions. 2/Although statistically significant,the constant terms in these two equations are quite sma],l (2/100 of a percent and 3/100 of a percent).The implied elasticity of Rai1be1t electricity demand with respect to Railbe1t population growth is (a)constant and (b) equal to 1.38.This statement was verified by running regression 1 in reverse.This analysis was performed even though the .999 R2 and near zero intercept assured the result. (2) Approximating the Rai1be1t Model:The Battelle and Acres studies focused on the Rai1be1t as a whole.The Acres study,in particular, provided relatively little detail for Fairbanks:In order for this study to be confidently based on rates of Fairbanks population growth that are consistent with the Battelle and Acres rates of growth of Rai1be1t electricity demand,it was necessary to develop a mathematical Dridge between the forecasted rate of growth of electricity demand in the Rai1be1t and the forecasted rate of Fairbanks population growth. The equations that accomplish this are given below.(All percent changes are thirty-year compound annual averages,t-statistics in parentheses.) [ "Lo_ e E C '. [ b [ J [ I.e..._ [ I r-1 l-e [-- __J. [0 [~ [ [' [- c- F Lr· Rai1be1t electricity demand is 1.43 percent.When 2.2 is SUbstituted into the right-hand side of the first equation above,and the result is SUbstituted into the right-hand side of the second equation,the figure 1.43 is determined.Similarly,the rate of population growth in Fairbanks that is consistent with the 3.5 percent Acres rate of growth of Railbe1t electricity demand is found to be 2.30 percent. Framework for Analysis:The relative price analysis leads to the conclusion that the potential cOllll1ercia1 and residential demand for natural gas in Fairbanks is limited to 1}use as a substitute for fuel oil in space heating and water heating;2}use as a SUbstitute for electricity and propane in cooking;and 3}some incidental uses. Accepting that the small quantity of gas that might be used to fire gas lamps can be ignored,the relative magnitude of the demand for cooking. can be compared to the magnitude of demand for heating. According to the U.S.Department of Energy,a modern gas cooking range for the home uses between 6 MMBtu's and 13 MMBtu's of fuel per year, depending on its efficiency.The same source records that in 1980, approximately 29 percent of U.S.households that had modern ranges used' natural gas and the remaining 71 percent used electricity.!!With natural gas prices scheduled for complete decontrol,it is reasonaole to conclude that the niitionalaverage price of natural gas to residential and commercial users will rise relative to the price of electricity.If so,the present 29 percent market penetration nationally may be an upper limit for the foreseeable future,especially when one considers the growing attractiveness of combination electric range-microwave ovens. !!"Estimate of Average Annual Energy Consumption of Gas App1 iances,II Consumer Products Efficiency Branch,U.S.Department of Energy,also (same source)"Estimate of Average Annual Energy Consumption of Electric App1iances." E-20 3088A ~[ 'r T~ T' '"[ r l~ Ft=o (J ~ [' .-cj--' -[ _., r; r~ __..1 h\-" .[ L ._..i [' ••.1 L ~J L [' [, [ [ L [~ L f ~, r~ L [ fj 6 C E [ L ~.-~ L [ [ Unless the Fairbanks price of natural gas relative to electricity is unusually low,possiblY much lower than it has been nationally,one would not expect gas ranges to account for more than 29 percent of the home cooking units in Fairbanks.The only change in this market relationship would result from a major innovation not yet made,or that a Fairbanks preference biased in favor of natural gas for nonprice reasons.!!The market penetration could be lower for natural gas than the estimated 29 percent.The Department of Energy's estimated 825 kWh consumption per year for a low efficiency conventional e1ec.tric range in Fairbanks costs approximately $82.50 per year to operate today.Even if gas were free,the cash savings that could be achieved by switching from an electric range to a gas range would not be SUbstantial. The demand for gas as a commercial cooking fuel may be more price sensitive,because the commercial volume of cooking fuel required per user year is much greater than for home cooking.Based on the available data and conversations with commercial suppliers of eqUipment,it appears that propane is presently the preferred commercial cooking fuel in Fairbanks.The 1978 Borough survey,for example,estimated that 85 p'ercent of the effective commercial cooking MMBtu's were supplied by propane.2/On the assumption that this percentage is correct,we define the maximum volume of natural gas that would be demanded for commercial cooking in Fairbanks to be equal to 85. percent of the projected demand for effective commercial cooking energy.Because this volume is quite small relative to the potential - demand for gas in space heating and water heating (75,000 delivered MMBtu's for commercial cooking in 1981 compared to nearly 3.5 million MMBtu's for space and water heating)commercial cooking demand amounts !!If the penetration percentage was 29 percent of the modern ranges, it would clearly be no larger as a precent of all home cooking units. 2/See [5b]. E-21 3088A to something approaching rounding error in these projections of the total demand for natural gas.!! Fi nally,it shou1 d be noted that the total 1981 max·imum potenti a1 demand for gas ~s a commercial and residential cooking fuel (delivered energy)amounts to·137,800"MMBtu's or approximately 135,000 MCF.2/ This is only 4.6 percent of the estimated 1981 maximum potential demand for gas as a heating fuel (approximately 3.1 BCF).Because this percentage is so low,it is clear that the potential of natural gas as a heating fuel is the critical factor in detennining the overall demand in Fairbanks. The Conditional Demand for Natural Gas:The 1981 maximum potential demand for natural gas is defined as the estimated volume of fuel oil and propane used in space heating,·water heating and cooking measured in effective MMBtu's,and adjusted to delivered Btu's based upon efficiency correction. Tables E-3 and E-4 present conditional forecasts of the demand for delivered gas in Fairbanks (a)if it is priced so as to penetrate 10 percent;(b)25 percent;(c)40 percent;and (d)100 percent of the total heating and cooking fuel market;(i.e.,1981 combined fuel oil/propane share).Maximum potential demand for the low growth scenario in the year 1981+t is defined in Table E-3 as 1981 maximum !!The 3 million MMBtu's is the sum of the 1981 commercial and the 1981 residential demand for fuel oil and propane for space and water heating,see Table E-1. 2/We have added 75,073 (commercial)and 62,679 (residential).The residential estimate is the product of the 1981 number of occupied residences (22,751),the factor .29 representing gas cooking penetration,and an average 9.5 r+1Btu per year gas usage per rang~. The 9.5 MMBtu consumption estimate is the mean of the Department of Energy's gas range estimate of 6-13 MMBtu per year. E-22 3088A .L ......J L L.J b Lr' L f .j L ~~ L .-J [ I TABLE E-3 FAIRBANKS NORTH STAR CONDITIONAL GAS DB~AND POPULATION GROWTH AT 1.43% (Delivered Energy) 1985 1990 1995 2000 2005 2010 10%of Market Residential (MMBtu)439512.8 471849.7 506565.8 543836.0 551612.9 626804.6 Commercial (MM8tu)80488.0 86409.9 92767.4 99592.7 106920.2 114786.8 Sum (MMBTU)520000.9 558259.6 599333.2 643428.7 690768.6 741591.4 Residential (MCF)430894.9 462597.8 496633.1 533172.5 572400.4 614514.4 Commercial (MCF)78909.8 84715.6 90948.5 97639.9 104823.7 112536.1 Sum (HCF)509804.8 547313.3 587581.5 630812.5 677224.1 727050.4 25%of Market Residential (MMBtu)1098782.1 1179624.3 1266414.4 1359590.0 1379032.1 1567011.6 Commercial (MMBtu)201220.0 216024.7 231918.6 248981.8 267300.5 286966.9 Sum (MMBTU)1300002.2 1395649.0 1498332.9 1608571.8 1726921.4 1853978.6 Residential (HCF)1077237.4 1156494.4 1241582.7 1332931.4 1431000.9 1536285.9 Commercial (MCF)197274.6 211788.9 227371.1 244099.8 262059.3 281340.1 Sum (MCF)1274511.9 1368283.3 1468953.9 1577031.2 1693060.2 1817626.0 40%of Market Residential (MMBtu)1758051.4 1887398.9 2026263.0 2175344.0 2206451.4 2507218.6 Commercial (MMBtu)321952.1 345639.5 371069.7 398370.9 427680.8 459147.1 Sum (MMBTU)2080003.4 2233038.3 2397332.7 2573714.9 2763074.3 2966365.7 Residential (MCF)1723579.8 1850391.0 1986532.4 2132690.2 2289601.5 2458057.4 Commercial (MCF)315639.3 338862.2 363793.8 390559.7 419294.9 450144.2 Sum (MCF)2039219.1 2189253.3 2350326.2 2523249.9 2708896.4 2908201.7 1981 Fuel Oil/Propane Share of Market Residential (MMBtu)2834857.8 3043430.7 3267349.1 3507742.2 3557902.9 4042890.0 Comme rc i a1 (101MB tu )475684.2 510682.3 548255.5 588593.0 631898.3 678389.9 Sum (t'l1BTU)3310542.0 3554113.0 3815604.6 4096335.2 4397720.4 4721279.8 Residential (MCF)2779272.4 2983755.6 3203283.4 3438962.9 3691982.4 3963617.6 Commercial (MCF)466357.0 500669.0 537505.3 577052.0 619508.2 665088.1 Sum (l1CF)3245629.4 3484424.5 3740788.8 4016014.9 4311490.6 4628705.7 E-23 2665B TABLE E-4 FAIRBANKS NORTH STAR CONDITIONAL GAS DEMAND POPULATION GROWTH AT 2.30% (Delivered Energy) 1985 1990 1995 2000 2005 2010 lOt of Market Residential (MMBtu)45478704 509549.7 570906.2 1)39650.7 654362.7 802969.9 Commercial (MMBtu)83285.2 93313.9 104550.1 117139.3 131244.4 147047.9 Sum (t1~Btu)538072.6 602863.6 675456.3 756790.0 847917.4 950017.8 Residential (MCF)445870.0 499558.6 559711 .9 627108.6 702620.6 787225.4 Commercial (MCF)81652.2 91484.2 102500.1 114642.4 128671.0 144164.6 Sum (MCF)527522,2 591042.7 662212.0 741951.0 831291.6 931390.0 251£of Market Residential (MMBtu)1136968.4 1273874.3 1427265.4 1599126.9 1635906.8 2007424.7 Commercial (MMBtu)108213~1 233284.7 261375.2 292848.2 328111.0 367619.8 Sum (MMBtu)1345181.6 1507159.0 1688640.7 1891975.1 2119793.6 2375044.5 Residential (MCF)1114674.9 1248896.4 1399279.8 1567771.4 1756551.6 1968063.4 Commercial (MCF)204130.5 228710.5 256250.2 287106.1 321677.4 360411.6 Sum (MCF)1318805.4 1477606.9 1655530.1 1854877 .5 2078229.0 2328475.0 401£of Market Residential (MMBtu)1819149.5 20381~8.9 2283624.7 2558603.0 2617450.8 3211879.5 Commercial (MMBtu)333141.0 373255.5 418200.3 468557.1 524977.5 588191.7 Sum (I+\B~u)2152290.5 2411454.4 2701825.0 3027160.1 3391669.8 3800071.2 Residential (MCF)1783479.9 1998234.2 2238847.7 2508434.3 2810482.6 3148901.4 Commercial (MCF)326608.8 365936.8 410000.3 459369.7 514683.9 576658.5 Sum (MCF)2110088.7 2364171.0 2548848.1 2967804.0 3325166.4 3725560.0 1981 Fuel Ofl/Propane Share of Market Residential (I+\Btu)2933378.6 3286595.7 3682344.8 4125747.3 4220639.5 5179155.6 Commercial (MMBtu)492215.8 551485.0 617891.0 692293.2 775654.3 869053.2 Sum (!flBtu)3425594.4 3838080.7 4300235.8 4818040.5 5398195.5 6048208.9 Residential (MCF)2875861.4 3222152.7 3610142.0 4044850.3 4531903.2 5077603.6 Commercial (MCF)482564.5 540611.6 605775.5 678118.8 760445.4 852013.0 Sum (t~CF)3358425.9 3162824.3 4215917.5 4723569.1 5292348.6 5929616.5 E-24 2665B ,--~ ," '-------..!j ,." r-jJ 3.088A E-25 given a delivered price of $1.22 per gallon for distillate. !I In turn,the 1981 maximum is defined by the combined share of fuel oil and propane. 2/See the previous section. 3/Since the ~ooking component is less than 5 percent of the total. Residential Conmercia1 $9.58 per MCF $9.94 per MCF Based on the energy parameters presented in Table E-2,assuming different heating efficiencies,a $600 conversion cost,a 3.0 percent real discount rate and a required five year payback period (recovery of conversion costs),the 1982 delivered prices at which consumers would be financially indifferent between gas and No.2 distillate as heating fuel are: Whether a reasonable forecast of the actual demand for gas in any single year should be set equal to zero,10 percent of maximum,25 percent of maximum,40 percent of maximum,or 100 percent of maximum, is a function of the price set for gas relative to the price set for its primary competitor as a heating fuel,No.2 disti11ate.3/This requires a comparison of the two prices on an efficiency adjusted, MMBtu basis,with an allowance for the cost of conversion of heating units from fuel oil to natural gas.In addition,one must also allow for any financial constraints that may prevent consumers from taking advantage of lower priced gas {should it indeed be lower priced},for any willingness to pay a premium for I c1ean"gas,and for the inevitable effect of inertia. potential demand times the factor {l.0143)t.!I Maximum demand,as presented in Table E-4 for the medium growth scenario,employs the factor (1.023)t.The two annual average percentage rates of growth, 1.43 percent and 2.30 percent,are the rates of Fairbanks population growth discussed previOus1y.2 [ [ I o g [ E [-~ -- [ L, L·.~.··.-.- [ [ [ [ r [ [ [ n ~ In other words,at these prices users would have no financial preference for one or the other fue1.1/At gas prices below these $9.58-$9.84/MCF,gas is economically attractive.Because the typical household in Fairbanks requires 135 MMBtu·s of effective heating energy per year and the typicai commercial establishment requires 264 MMBtu's per year,2/the typical commerci al'user wou1 d recover conversi on costs more quickly than would the residential user for a given set of gas and distillate prices.Consequently,the IIbreakeven ll price of natural gas for the representative commercial user is higher than it is for the representative househo1d.3/ Because real fossil fuel prices are assumed to escalate at a 2.0 percent rate in the Battelle and Acres studies,the projected real co~sumer IIbreakeven··prices of gas a1 so esca1 ate at thi s rate.In any year,1982+t,the constant dollar (1982 $)consumer breakeven prices are (1982 $/MCF): 9.58*(1.02)t Residential 9.94*(1.02)t Commercial !I The formula for this calculation is (ignoring conversion costs): breakeven price.of gas =1.22*(Btuga*Effga)/(Btufo*Efffo);where 1.22 is the price per gallon of fuel oil and where Btuga = MMBtu/MCF =1.02,Btufo =MMBtu/ga11on =.138,Effga =.75,Efffo =.65. 2/The per residence figure is the Borough·s/Alex Carlson's 1,502 gallons of fuel oil converted to MMBtu·s and adjusted for 65 percent efficiency (that is 1502*.138*.65).The per establishment figure is the total effective 1981 MMBtu·s required as calculated in Section 4.4.1.2 (514,000)dividea by the estimated 1981 number of establishments (1,947). 3/Conversion costs vary considerably.The $600 estimate was obtained by Alaska EConomics,Inc.,as an average of three estimates kindly provided by different plumbing/heating firms. E-26 3088A [ [ i[ "0 L -I C .1 .t:. .j L..; L___J 1.: -_.j [ [" ["" [ [ [ [ [ f L,> [ [ U l L \ E Co. L L L. i [ These become (1982 $/MCF): CONSUMER BREAKEVEN GAS PRICES* (1982 $/MCF) 1985 1990 1995 2000 2005 2010 Residential 10.17 11.23 12.40 13.69 15.11 16.68 Commercial 10.55 11.65 12.86 14.20 15.68 17.31 *1982 $/MCF at which gas is estimated to breakeven with No.2 distillate priced at 1982 S/ga11on =1.22*(1.02)t,where t is the number (year-1982).These prices allow for conversion costs of $600*(1.02)t.That is,they assume conversion costs escalate at a 2.0 percent real rate also.Breakeven prices would be slightly higher if conversion costs accelerate only at the rate of inflation. Lumpy Demand:Virtually all of the pUblished gas demand studies derive price and income demand elasticities by applying statistical methods of estimation to historical data bases.These studies employ nonzero gas· sales over the entire period for which the data are available.No studies have been found that analyze the price and income responsiveness of gas demand over a transition period during which natural gas is at first unavailable,and then enters the marketplace. This renders previous empirical estimates of the price and income e1 astici ti es of gas demand unusabl e for our purposes.Were a gas service to be formed in Fairbanks,and a new equilibrium between gas and other fuels established,one could reasonably turn to previous '.analyses to obtain insigh.ts as to how the equilibrium shares of the market wou1 d change wi th changes in relati ve fuel prices and real income.The interest in this study lies in determining 1)the price at which gas become competitive;2)in suggesting a reasonable upper limit to the quantity of gas that could be sold;and 3)in providing at least some guidance as to how much of a share gas would garner of the potential Fairbanks market if it were priced at different percentages below consumer breakeven levels.Tables E-3 and E-4,and the consumer breakeven prices presented above satisfy the first two of these interests •.Of necessity,our discussion of the third will be somewhat limited and rather conjectural. E-27 3088A The introduction of a new product is almost always preceeded by a detailed marketing research effort.It almost always sparks some form of response from competitors (in this case,principally the producers and suppliers of fuel oil).Because the content and success of an initial natural gas advertising campaign,and the extent to which the competition would be prepared to lower prices or engage in counter-advertising cannot be predicted,a definitive estimate of the share of the market that gas might capture cannot be made.lI What can be presented are estimates of the 1982 present discounted value of the five-year annual savings that would accrue to commercial and residential users of gas for every 10¢by which the price of gas falls below the consumer breakeven level,assuming fuel oil is the competition.The results are shown in Table E-5. Reading from Table E-5,if residentially sold gas is priced approximately 62¢per MCF below consumer breakeven,that is at $8.96 in 1982 assuming a $1.22 per gallon price of fuel oil,the typical residential user would realize a present value savings of $500 in excess of the estimated $600 conversion'cost.If there is any marketing magic to round numbers like $500 and $1,000,it might be reasonab1 e to expect that gas wou1 d achieve significant inroads agai nst fuel oil if it were priced to save residential users $500 over the cost of conversion (say 10 percent of the total market),and might be expected to approach dominance (say,40 percent of the total market)if the savings reached $1,000 in excess of conversion costs ($1.24 below breakeven or $8.34IMCF if fuel oil is $1.22 per gallon). !!For reasons of corporate security,Fairbanks producers and suppliers of fuel oil would be ill advised to identify and to quantify their potential competitive responses. E-28 3088A r "[' r f' f" [ [ r L L [ G [; C C [ ~, L ~.J [ ~_.i [ r [. L [~ [ r~ [' r I,.d [ C D, C [j ~ ~ L L [ I t TABLE E-5 PRESENT VALUE ANNUAL SAVINGS IN EXCESS OF $600 Discount*Residential Commercial .10 80.70 158.04 .20 161.40 316.08 .30 242.10 474.12 .40 322.80 632.16 .50 403.50 790.20 .60 484.20 948.24 .70 564.90 1106.28 .80 645.60 1264.32 .90 726.30 1422.36 1.00 807.00 1580.40 1.10 887.70 1738.44 1.20 968.40 1896.48 L30 1049.10 2054.52 1.40 1129.80 2212.56 1.50 1210.50 2370.60 1.60 1291.20 2528.64 1.70 1371.90 2686.68 1.80 1452.60 2844.72 1.90 1533.30 3002.76 2.00 1614.00 3160.80 2.10 1694.70 3318.84 2.20 1775.40 3476.88 2.30 1856.10 3634.92 2.40 1936.80 3792.96 2.50 2017.50 3951.00 2.60 2098.20 '4109.04 2.70 2178.90 4267.08 2.80 2259.60 4425.12 2.90 2340.30 4583.16 3.00 2421.00 4741.20 *The discount is the amount in dollars that natural gas is priced below the consumer breakeven price for gas. E-29 3088A These statements are,of course,speculative.Furthermore,one must expect some competitive response from fuel oil producers and suppliers.Nevertheless,one can reasonably conclude the following (all prices are 1982 prices). 1)Natural gas should be no higher priced than consumer breakeven if one expects it to have a viable market. 2)In all likelihood,gas would need to be priced below $9.00/MCF (1982 price)to obtain a significant market share,unless Fairbanks users have a strong preference for IIc 1ean ll gas.!/ Similar statements SUbstituting prices raised at approximately the same percent per year as competing fuels can be made for any year in the forecast period.2/ Returning to Tables E-3 and E-4 these statements can be translated into BCF quantity values.Assuming a price of fuel oil of $1.22/ga110n in 1982, 3)If gas were priced at approximately $9.00IMCF (1982 price)and rose in price at the same rate as the price of competing fuel s, and if this were to lead to gas garnering 10 percent of the total market,gas demand would be approximately 0.5 BCF in 1985,rising to 0.7 BCF in the year 2010 -Battelle 1I10w";or in the Acres IImidd1e ll case,0.5 BCF in 1985 rising to 0.9 BCF in the year 2010. !I We implicitly assume in our breakeven calculations,that potential price reductions by fuel oil dealers are 1a~e enough to offset the price advantage gas enjoys as a IIc 1ean ll fuel. 2/We say lIapprox imate1 y ll because the appropri at~rate of esca1 ati on is slightly less than the rate·of increase of competing fuel prices if conversion costs escalate more slowly than that rate. E-30 3088A [ .~[ -r 'r' -[ T- r rJ L= E ,,[ .'[ ..n c•J LJ•...1 [ L •J .J~ C -01-) C 5)If gas were priced so as to completely displace fuel oil and propane as heating and cooking fuels,demand would be !/ 4)If the gas price were to be set at approximately $8.34/MCF,and rose in price at the same rate as the price of competing fuels,and if this were to lead to gas obtaining 40 percent of the total market,gas demand woul d be approximately 2.0 BCF in -1985 rising to 2.9 BCF in the year 2010 (Battelle)or in the case of the Acres results,2.1 BCF in 1985 rising to 3.7 BCF in the year 2010. [~ [- c- [ [ [ [- n- y Battelle low Peres middle Finally, DELIVERED BCF 1985 2010--- 3.2 4.6 3.4 5.9 3088A 6)The total market (all fuels)if garnered by gas would amount to Monthly Peak vs.Total Annual Demand:In the absolute,and as a percentaye of the annual total,monthly'heating degree days in Fairbanks average:2/ Battell e low Ac res mi ddl e DELIVERED BCF 1985 2010---5.1 7.3 5.3 9.3 E-31 As shares of the total market these would be 64.5 percent (residential heating/cooking)and 59.1 percent (commercial heating/cooking)• National Oceanic and Atmospheric Administration.2/ 1/ [ [ oT o [ l G f.".L I L L L l ~_ [ Heat loss per unit of time between a structure and the outside is directly proportional to the temperature differential and inversely proportional to the amount of insulation between the two.In a uniformly insulated structure,we have approximate1y:l/ 1866 2337 13.0 16.3 549.211 3.8 1.5 ~[ r [' [' r [ [ r~ L DEC JUNE NOV MAY OCT 1234 8.6 APRIL 1083 7.6 618 4.3 SEPT 1720 12.0 MARCH AUG 304 2.1 1890 13.2 FEB 2384 16.6 JULY 148 1.0 JAN Heating Degree Days %of Total Heating Degree Days %of Total where k is a thermal conductivity constant that declines as the structure~s insulation increases; T1 is the mean daily outside temperature in degrees; T2 is the mean daily inside temperature in degrees; L is the length of the path travelled by the heat. Applying this formula one can approximate month to month consumption of heating energy by defining July requirements as a reference level and calculating relative heat loss from the formula above based on the percentage difference between the number of heating degree days in a given month and the number of July heating degree days. 11 See Lunde,Peter J.,Solar Thermal Engineering,(John Wiley and Sons,New York)1980,pp.18-19,or one of many similar texts. E-32 3088A [ [ C L [ [ L L L L [ C [j I C C ! . L C [ L [ i _ L This yields the percentages given above. Applying these monthly fuel requirement percentages to our annual projections of natural gas demand we derive the monthly peak demands for methane (delivered MCF)shown in Table E-6.!/ Improved Efficiency:The results of this study are premised in part on average heating efficiencies of 65 percent for fuel oil burners and 75 pecent for gas burners.Improved efficiency can be achieved for both types of units.If heating efficiency improves,delivered energy requirements decline.If one wishes,one can multiply our forecasts of delivered MMBtuls by the factor (.75/Effga)to obtain an I'adjusted ll efficiency forecast,where Effga is some alternative estimate of gas heating efficiency. !!Cooking energy is spread in the same proportions as heating energy,a minor lIerrorll given our estimate of cooking demand relative to the total (about 5%). E-33 3088A January,1985 January,201 0 Battelle IILow" 10%of .Market 117,255 167,222 25%of Market 293,138 418,054 40%of Market 469,020 668,886 1981 Fuel Oil/Propane Share 746,495 1,064,602 100%of Market 1,172,550 1,672,215 Acres l'-1i dd1 e" 10%of Market 121,330 214,220 .25%of Market 303,325 535,549 40%of Market 485,320 856,879 1981 Fuel Oil/Propane Share 772,438 1,363,812 100%of Market 1,213,300 2,142,198 3088A TABLE E-6 DELIVERED ENERGY,PEAK DEMAND MONTH .(MCF) E-34 [ . I [ .1 r C 1 L ; b, L L L ~j [ [' [ r~- r'--.~- [' [ r~- , [ f', L-" J [ [ [ i C [ i G L [. [ L ( [ E2.0 REFERENCES [l J Alaska Power Authority,IISusitna Hydroelectric Project, Feasibility Report,11 Volume 1,1982 (prepared by Acres American,Inc.). [2].Battell e Pacific Northwest Laboratories,IIRai 1be1 t E1 ectric Power Alternatives Study:Evaluation of Rai1be1t Electric Energy Plans,1I February 1982 (prepared for the Alaska Office of the Governor)• [3]COllUllun;ty and Regional Affai rs,A1 aska Department of,Al aska Taxable 1981,(Di.vision of Local Government Assistance). [4]Energy,U.S.Department of,Alaska Power Administration,Alaska Electric Power Statistics;1960-1981,7th edition,August 1982. [5]Fairbanks North Star Borough,Community Research Center: (a)The Energy Report,August 1982. (b)1978 Fairbanks Energy Inventory,July 1979. (c)Community Research Quarterly,Summer 1982. (d)The Energy Report,June 1982. [6]Interior Woodcutters Association,IIFue1 Wood Utilization'in The Fairbanks North Star Borough,II report of a survey conducted November 1981 through January 1982. [7]Labor,Alaska Department of,Statistical Quarterly,1978:3 and 1980:3 (Research and Analysis Section). [8]Resources for the Future,Energy in Americals Future,(John Hopkins Press,Baltimore),1979. [9]Revenue,Alaska Department of,Petroleum Production Revenue Forecast,Quarterly Report September 1982 (Division of Petroleum Revenue). E-35 3088A J J I I . I II I I' I I I , J I , I I I I I II 10o APPENDIX F [ I \-.. APPENDIX F OFFICE OF MANAGEMENT AND BUDGET DRAFT REPORT COMMENTS AND ASSOCIATED RESPONSES F-l Conceptual While this report provides substantial amounts of new data and technical information,it does not constitute a feasibility level analysis of the North Slope natural gas alternative.A feasibility study generally includes a cost-of-power analysis,based on a plan of finance,and a comparison with alternatives.While the information provided is extensive,such comparisons are not and cannot be made.As such,the study more closely fits the definition of a reconnaissance level analysis. Given the aforementioned,a second issue may be most appropriately addressed at the next stage of analysis. This study has as its focus an electric generation facility based on North Slope natural gas which is to supply the entire Railbelt electrical demand. This concept follows the Susitna plan of completely displacing existing facilities based on Cook Inlet natural gas.The size of any element of the Railbelt supply network will depend on its relative competi- tiveness.There is no justification for assuming that anyone supply source must be capable of deliv- ering the-entire load.In fact,it appears that a major drawback to Susitna is that it is too large and too in~lexible.An optimal supply system will RECEIVED U~'f 17 1983 ENVIROSPHERE COMPAN' SEAT'flE Ebasco Draft Final Report Harch 29,1983 465-3573 DATE: FILE NO. SUBJECT: Robert Mohn Alaska Power Authority Anchorage Gordon Harrison,Associate Director TELEPHONE NO: Division of Strategic Planning Ronald D.Ripple ~~v..R Division of Strategic Plannig Office of Management and Budget The work performed thus far by Ebasco Seryices Inc. on the use of North Slope natural gas for Railbelt electrical and heating end-use adds significantly to the data bank on Railbelt alternatives and to alternative uses of North Slope natural gas. My review will address conceptual issues first and then technical issues. MEMORANDUM TO FROM: THRU: L C [ [.' [ [~ [ '" Au i C ',. [ ! fj , L C C; b C I [ L \ L Eb.:lsCO Draft -2-March 29,1983 take into consideration the relative competitiveness of all s\lpply sources and balance the size of each" element on this basis.Cook Inlet natural gas is close to the primary load center,plentiful,and likely to very competitive with North Slope natural gas for Railbelt electricity.Therefore,it does not appear reasonable to eliminate Cook Inlet natural gas fired genera.tion out-of-hand. Technical 1.As discussed during our recent phone conversation, the transmission line costs appear excessively high.I understand that these costs are being reviewed and an independent estimate has been s~licited. 2.The Alaska Power Authority economic parameters call for the use of a 3.5%real discount rate, not 3.0%. 3.The text implies that the cost figures have been discounted back to 1982.~ey have been discount- ed to 1983.While it is in fact 1983,for comparability,the 1982 figures would be useful, and the tables do not represent the text.The one year discounting differential makes about a 3%difference.This'is well within the 15% contigency applied to most cost elements.How- ever,the transmi ss ion--rIiies,wh ich account for the bulk of the costs in the North Slope genera- tion alternative,have no contigency attached. 4.Given the unusual nature of the transmission line from the North Slope,i.e.,the length,terrain and conditions,it would seem appropriate to attach a contigency factor'to this element. 5.The handling of transmission line 0 &M is curious. First,the annual average cost is approximately 1%of the total construction-cost.There is no justification provided for using the 1%factor. Second,it is noted that "Actual 0 &M costs should be less initially,and increase with F-2 [ r L [ r ~ [ C [ [. L ...J I,,t; [, L ...1 L L [ .J F-3 time."(po 2-32).However.Ebasco uses a flat average annual cost.This has the tendency to increase the present value of costs relative to a stream of costs which increase over time. 6.Why was the 1260 psi pipeline scenario ch~osen? This follows the ANGTS design.but justification is not given.The TAGS design calls for an oper- ating pressure o~1660 psi.In the TAGS report (p.13)it is noted that while the higher pressure line required thicker wall pipe the reduced diameter lead to less weight per mile in pipe. Presumably less steel will imply less cost. This should be looked into. Harch 29.1983-3-Ebasco Draft 7.Chapter 4 values for natural gas consumption in 2010 for a combined cycle facility show a 20 Bcf/ year savings over the simple cycle in Chapter 2. At an unescalated price of $1 per mcf the saving over the entire period is about $98 million.in 1982 dollars discounted at 3%.This is a subst- antial saving.Moreover.in non-discounted dollars.the savings in 2010 and beyond is $20 million annually.Why then is the simple cycle chosen for the North Slope? 8.The relative capital costs between locations seem out of line.Reference Table B4-2.Both the North Slope and the Kenai location can make use of barged.modular units which are constructed in the 10wer-48 at lower labor and materials cost.Fairbanks.on the other hand.cannot make use of modular construction.The materials mus"t be shipped from the lower-48.transported overland and construction performed at the Fairbanks site.Given this difference.it is surprising that the Fairbanks facilities are the least costly.especially when compared to Kenai. [ [ [ [ [ [ [ fl ~:. C f'..:b [ ; L L. L r L i.; [ Please feel free to contact me if you have any questions. cc:Lennie Boston George Matz 9.Errors in representation of natural gas prices still remain in Appendix.B.Reference p.B4-1 •. The $5.50 export price is the Japan landed price, not an ex-Alaska price.Also,Battelle's $5.92 per MMBtu is for Fairbanks,not Anchorage. Ebasco Draft -4-March 29.1983 r r [ r [ T [ rL ru F-4 .6 [ [ ;1, Ii,I-'. C-, L .~! C [ 1_ ~ [ I r [ [~. [ [ [ [ rLJ, RESPONSES TO OFFICE OF MANAGEMENT AND BUDGET QUESTIONS CONCEPTUAL We concur that this study does not constitute a feasibility level analysis.The purpose of the study was to select the most appropriate types of facilities for utilization of North Slope gas,to optimize their scale and general configuration,and to estimate facility costs at a reconnaissance level.The system studies undertaken were designed .to complement this purpose,not formulate a complete power supply system for the Rai1belt.The facilities described in this study will be time phased and incorporated into comprehensive power supply plans in the course of other power planning activities.These other activities are not being limited to a single supply source and are not dismissing Cook Inlet natural gas. TECHNICAL 1)Ebasco's transmission line cost estimates reflect the unique project setting and the system stability and reliability required. The line will represent the major electrical service for the entire state.Heavy duty towers (48 ton)and associated equipment were required based upon high wind loadings (up to 130 mph),extreme radial ice loadings (1.5 inches),and reliability requirements. These design specifications were confirmed based upon discussion' withARCO electrical engineers and their Prudhoe Bay experience (ARCO operates 75 miles of 13.8 kV lines in this arctic environment).Such specifications significantly increase costs. The environmental and topographical constraints in the Kenai to Anchorage transmission system required a submarine cable crossing near Turnagain Arm.This served to increase the 1ine's cost. Several construction factors also raised costs,inclUding the, extreme remoteness of much of the routes,the very narrow time window for construction,and compressed construction schedules due to climatic conditions. 4045A F-5 The Power Authority has solicited an independent cost estimate which will be reported as an addendum to this study. 2)Current Power Authority economic parameters do use a 3.5~real discount rate.A real discount rate of 3.0~was however previously utilized by Acres American Inc.in their Susitna Hydroelectric Project Feasibility Studies and by Battelle Pacific Northwest Laboratories in their Railbelt Electric Power Alternatives Study. The 3.0%rate was therefore utilized in this study to facilitate an economic comparison with these previous efforts. 3)Discounting back to a specified year is a matter of convention. Two conventions exist regarding whether the beginning or end of the year is used as the point of cash flqw occurrence.We used the end of year convention.The statement of the problem implies a realization of the answer,and as noted,the difference (3%)is well below the contingency included in each cost estimate. 4)A l5~contingency is included in the transmission line cost estimates.It is factored into each bid line item cost.Please refer to the notes cited in each table. 5)Based on Ebasco's experience,the one percent value is suitable and appropriate for these transmission systems.It is derived from Ebasco's transmission line experience and an analysis of recent cost data supplied·by several local Alaskan utilities.It should be noted that the effect on present value from the average annualization of transmission line O&M costs is insignificant. 6)ANGTS was chosen as the convention because it is the proven, licensed ~echnology.The Trans Alaska Gas System proposes some unique design features which will have to be evaluated during detailed engineering. 4045A F-6 r c [ [: r" r [ [ fJ L r.•.lJ n C C.. [i .J [~, L l, [ [ f-.~···.·I r [ [ [ L [ F' L o [ D, G c 1J [ L l L L._ LL I '-.--- i 7)Simple cycle is favored because of the added comp1eKity of operating boilers on the North Slope with attendant water supply, water treatment,water chemistry control and other more specialized maintenance requirements of the higher temperature steam cycles. In addition,spare parts requirements increase due to the addition of the steam turbine cycle and other equipment.It was,thus,felt that the technical advantages of the simple cycle unit outweighs the slight economic edge of combined cycle.This decision is explained in Appendix 8. 8)Factors such as water requirements and emissions standards (e.g., nitrogen oxides)cause variations in capital expenditures at different locations.A water supply and water injection system to control nitrogen QKides was assumed for the Kenai location.These... systems were not included in the Fairbanks plant due to ice fog problems.Please refer to our discussion of air quality concerns in Chapters 4.0 and 6.0. 9)The discussion of natural gas prices presented in Appendix 8 (Page 84-1)briefly summarized our rationale for choosing the price range utilized in our sensitivity analysis,i.e.,$0.00 through $5.50 per MMBTU.The sensitivity analysis was performed to support our recommendation of the most appropriate technology for each stUdy location.There is no error in'representation.The $5.50 cited is a direct quote from one of our contacts listed in Appendix A.If this price is the Japan landed price as suggested it makes little difference to the discussion.The Governor's Economic Committee report estimates LNG shipping costs at $1.00~BTU in 1988 dollars Which would be $0.66 in 1982 dollars when using the Committee's reported economic parameters.SUbtracting $0.66 from $5.50 yields $4.84.The $5.92 is for Fairbanks and not Anchorage.The text has been corrected on this point.To further justify our range and our recommendations,the following LNG costs are cited in the Governor's Economic Committee report (see pages 43,44 and 45 of the Economics Section);calculated 1982 values are also presented for compari son. 4045A F-7 F-8 4045A In addition it should be noted that the majority of North Slope gas which is reinjected has a negative wellhead price.The value (delivered cost)of the small amount sold to Alyeska varies somewhat in time but was about $1.86/MMBTU when the report was written. In light of the above cited prices it could possibly be argued that the price range used in our sensitivity analyses should have been expanded to include negative values and values greater than $5.50. To do this,however,would not have increased the utility of the analysis as the combined cycle technology was always favored when natural gas prices were above about $1.50/MMBTU. ~'-, E [ [ C t L L L L .L L J [ [ [ --i [ [ ~ [ f i..- 6; $5.94 to $7.91 $3.95 to $5.27 Phase 1 System LNG Tariffs South Alaska ($/MMBtu) $4.67 to $6.16 $3.11 to $4.10 Total System LNG Tariffs South Alaska ($/MMBtu) 1988 1982