HomeMy WebLinkAboutAPA423\Y
Prepared by;
[i]
SUSITNA HYDROELECTRIC PROJECT
TASK 12-PUBLIC AND AGENCY PARTICIPATION
LJli&IY
}UtSC.A oepf OF fl!l( ...
23~R~k
Nd~ AI ... M1 .. 1 ..
SUBTASK 12.03
AGENCY CONSUL TAT ION
MARCH 1982
"'-----ALASKA POWER AUTHORITY __ ____.
/'""'
-
-
-
.-
.-
-
-
Prepared by:
[ii]
SUSITNA HYDROELECTRIC PROJECT
TASK 12-PUBLIC AND AGENCY PARTICIPATION
SUBTASK 12.03
AGENCY CONSULTATION
MARCH1982
U.S. De:part:moot of the Interior
..
ARLIS-
Alaska Resources
Library & Information ServiCe
Anchorage, Alaska
L...------ALASKA POWER AUTHORITY __ __,
....
-I
-'
ALASKA POWER AUTHORITY
SUS ITNA HYDROELECTRI CPROJECT
AGENCY CONSULTATION REPORT
TABLE OF CONTENTS
Page
1 -ORGANIZATION OF CONSULTATION PROGRAM . • . • • • . . • • . • .. • • • • • • . • • • • • 1-1
1.1-Formal Consultation ..................................... 1-1
1.2 -Informal Consultation vi a the Steering Committee . .. . . .. • 1-3
1.3-Authorities Contacted ........•.................•........ 1-3
1.4-Correspondence ...•...............•..................•... 1-3
TABLES
APPENDIX A -AGENCIES CONTACTED FOR INFORMATION DURING PREPARATION OF
THE SUSITNA ENVIRONMENTAL REPORTS
~"""' APPENDIX B-1 -FORMAL AGENCY COORDINATION CORRESPONDENCE
-
-
-
APPENDIX B-2 -FISH AND WILDLIFE MITIGATION REVIEW GROUP CORRESPQNbENCE
APPENDIX B-3 -STEERING COMMITTEE CORRE:SPONDENCE
APPENDIX B-4 .:. MISCELLANEOUS CORRESPONDENCE
ARLIS
. Alaska Resources
Llbrary & fnJonnatJon Servtces
A.ncbma&e. Alaska
-
AGENCY CONSULTATION REPORT
....., LIST OF TABLES
r
~·
r
/'"'"'
I
I
r-
1
-
Number Title
1.1 Formal Agency Coordination List (Original)
1.2
1.3
Original List of Reports and Groups to Which Reports Were/
Were To Be Sent
Original List of Agencies and Reports Received (To Be Received)
1.4 Formal Agency Coordination Expanded List
1.5 Expanded List of Reports and Groups to Which Reports Were/
Were To Be Sent
1.6 Reports, Data Sent, and Purpose
1.7 Members of the Susitna Hydroelectric Project Steering Committee
1.8 Dates and Purposes of Steering Committee Meetings with the
Power Authority and/or Its Consultants
1.9 Agencies Invited and Those Which Declined To Be on the Fish
and Wildlife Mitigation Review Group
i ..
-
r
1-,
-!
r
-
AGENCY CONSULTATION REPORT
This report describes the various processes uti 1 i zed and committees estab 1 i shed
to provide agency input into the studies and discussions associated with the
Susitna Hydroelectric Project. This agency consultation and resulting agency
input was requested and provided on both an informal and formal basis as
described below. For a discussion of general public participation in the
project, refer to Appendix D of the Feasibility Report.
In addition to this agency consultation· described, a large number of agencies
were contacted for information during the preparation of the environmental
report. The list of these agencies is included as Appendix A.
1 -ORGANIZATION OF CONSULTATION PROGRAM
Consultation with the regulatory agencies was conducted on both a formal and in-
formal basis as described below. Formal consultation was conducted with the
agencies as required by the regulations of the Federal Energy Regulatory Com-
mission (FERC) and was done primarily vi a correspondence. Informal consultation
was done primarily via numerous meetings and was conducted to provide an infor-
mation flow between the Alaska Power Authority (APA), its consultants, and the
agencies to insure agency input into project planning and decisions making.
1.1 -Formal Consultation
(a) Regu1atorz Requirements
The FERC regulations pertaining to applications for license under Part I of
the Federal Power Act require in 18 CFR Part 4, Subpart E, Section 4.41,
that applicants for 1 icenses consult with local, state, and federal natural
resource agencies prior to filing of their license application. Accord-
ingly~ the Alaska Power Authority (Power Authority} formulated a plan to
con su 1 t with these agencies.
The process utilized by the Power Authority was based upon circulation of
reports on the various aspects of the projects to the agencies and a
written request for agency comments. The reports circulated were interim
reports in specific study areas (fisheries, wildlife, etc.) as discussed
below, as well as planning decis1on reports {access road, transmission line
corridors, etc.}. In addition, prior to initiation of project studies, the
Plan of Study and revisions were circulated. Finally, results of the fish
and wildlife mitigation efforts were circulated under this formal program
via meetings and correspondence with the Fish and Wildlife Mitigation
Review Group.
(b) Organization
The organization and implementation of the Formal Agency Coordination Pro-
gram has been -a dynamic process modified because of agency input. The
I:
original organization is explained below, followed by an explanation of the ~
revised organization.
{i) Original Organization
Agency Groups
Subject areas for coordination were selected based upon those re-
quired by the FERC regulations. These were water quality and use;
fish, wildlife, and botanical; historical and archaeological;
recreation; aesthetics; and land use. State, federal, and local
agencies having jurisdiction over resources in each of these sub-
ject areas were then p 1 aced in the appropriate group of agencies
which would receive reports concerning these subjects. A general
category was also added to include agency involvement with policy
decisions. Table 1.1 lists the agencies originally included in
each of these groups.
-Reports Circulated
A list of the reports and the groups to which they were sent ap-
pears in Table 1.2. Because of overlapping jurisdictions (one
agency present in more than one group), several agencies received
reports on different subjects. Table 1.3 lists by agency the
reports received.
{ii) Revised Organization
Initial circulation of these reports resulted in feedback from the
agencies concerning the organization of the formal agency coordin-
ation program. Following several meetings between the Power
Authority and the agencies, the program \'las revised. The revisions
included:
An expansion of the number of groups;
An expansion of the number of agencies within each group; and
- A decrease in the number of reports for which formal comments were
requested and, instead, simply providing reports for information
as backup documents to reports on which comments were requested.
Table 1.4 lists the revised subject groups and the agencies within
each group. Table 1.5 lists the reports to be received by each
group, and Table 1.6 reports date circulated and purpose (informa-
tion or comment). This revised program exceeds the consultation
required by FERC but was implemented to insure that all agencies
received adequate information.
1-2
-
i
·~
j
I
.I
-I
-
I""'
i
-
r
r
-
(c) Fish and Wildlife Mitigation Review Group
Throughout the Susitna Hydroelectric Project studies, technical mitigation
p 1 anni ng has been conducted by the Power Authority and its consultants to
reduce impacts to fish and wildlife recources. To insure agency input into
this process, a Fish and Wildlife Mitigation Review Group was established.
The purpose of this group was to review fish and wildlife mitigation
options presented to them and provide comments on priority and practicality
of their opt ions. Agencies invited to be on this committee and those who
accepted are 1 i sted in Tab 1 e 1. 9.
1.2 -Informal Consultation vi a the Steer·i ng Committee
The Susitna Hydroelectric Project Steering Committee was established in 1980 as
a mechanism to insure agency interaction in project progress and decision
making. The first meeting was held in July 1980 and meetings continue to date.
Originally envisioned as a formal process, it was decided the committee would
function as an informal body with official agency comment addressed vi a the
Forma 1 Agency Coordination Program.
The committee consists of representatives of state and federal agencies as
listed in Table 1.7. Table 1.8 lists the dates of meetings between the Power
Authority and the Steering Committee and the purpose of these meetings.
1.3 -Authorities Contacted
Appendix A of this report lists individuals from federal, state, and local
agencies as well as other institutions and organizations who were contacted
regarding the Susitna Hydroelectric Project Environmental Studies Program.
These individuals were consulted between October 1, 1979, and January 15, 1982.
Arranged by environmental report section, the names listed include:
(a) Those contacts made by TES and/or TES subcontractors for input re 1 ated
specifically to that report section;
(b) Those contacts made by TES and/or TES subcontractors, the information from
which, while pertinent to a different envjronmental report section, was
also applicable to the section in question; and
(c) Contacts made byTES, TES subcontractors, Acres, or the Power Authority
applicable to the Susitna Environmental studies in general.
The nature of these contacts range from requests for data to inquiries concern-
ing the environmental studies procedures. These lists are not intended to in-
clude those contacts made with other members of the Environmental Studies Team,
although some project personnel are listed because of the capacity in which they
were consulted.
1.4 -Correspondence
r-Appendix B contains correspondence with the resource agencies that has occurred
during the course of the study. This correspondence appears in chronological
order and is divided into four sections:
l-3 r
I 1
-Formal Agency Coordination Correspondence;
-Fish and Wildlife Mitigation Review Group Correspondence;
-Steering Committee Correspondence; and
-Miscellaneous Correspondence.
1-4
I~
l!lll!i,
-J
<'
'""' '
-
r
r
'
TABLE 1.1: FORMAL AGENCY COORDINATION LIST (ORIGINAL)
Water Quality and Use Group
Mr. John Katz
Alaska Department of Natural Resources
Pouch M
Juneau, Alaska 99811
Colonel lee Nunn
District Engineer
Alaska District
U.S. Army Corps of Engineers
P.O. Box 7002
Anchorage, Alaska 99510
Mr. John Spencer
Regional Administrator
Region X
u.S. Environmental Protection Agency
1200 Sixth Avenue
Seattle, Washington 98101
Fish, Wildlife, and Botanical Group
Mr. Robert McVey
Direc~or, Alaska Region
National Marine Fisheries Service
NOAA
P.O. Box 1668
Juneau, Alaska 99802
Mr. Ernest W. Mueller
Commissioner
Alaska Department of Environmental
Conservation
Pouch 0
Juneau, Alaska 99801
Mr. Keith Schreiner
Regional Director, Region 7
U.S. fish and Wildlife Services
1011 East Tudor Road
Anchorage, Alaska 99503
cc: Mr. Alan Carson
Division of Natural Resources
Alaska Department of Natural
Resources
Pouch 7-005
Anchorage, Alaska 99510
cc: Judy Swartz
U.S. Environmental Protection
Agency
Mail Stop 443
Region X EPA
1200 Sixth Avenue
Seattle, Washington 98101
cc: Mr. Ron Morris
Director
Anchorage Field Office
National Marine Fisheries
Service
701 C Street, Box 43
Anchorage, Alaska 99513
Mr. Ronald 0. Skoog cc: Mr. Thomas Trent
State of Alaska Commissioner
State of Alaska Department of fish and Game
Support Building
Juneau, Alaska 99801
Department of fish and Game
2207 Shepard Road
Anchorage, Alaska 99502
I i
TABLE 1.1 (Cont'd)
Historical and Archeological Group
Mr. John E. Cook
Acting Regional Director
Alaska Office
National Park Service
540 West Fifth Avenue
Anchorage, Alaska 99501
Ms. Lee McAnerney
Department of Community and Regional Affairs
Pouch B
Juneau, Alaska 99811
Mr. Robert Shaw
State Historic Preservation Officer
Alaska Department of Natural Resources
Division of Parks
619 Warehouse Avenue, Suite 210
Anchorage, Alaska 99501
Recreation Group
Mr. John E. Cook
Acting Regional Director
Alaska Office
National Park Service
540 West Fifth Avenue
Anchorage, Alaska 99501
Mr. John Katz
Alaska Department of Natural Resources
Pouch M
Juneau, Alaska 99811
Mr. Lee Wyatt
Planning Director
Matanuska-Susitna Borough
Box B
Palmer, Alaska 99645
Aesthetics and Land Use Group
Mr. Roy Huhndorf
President
Cook Inlet Region, Incorporated
P.O. Drawer 4N
Anchorage, Alaska 99509
Mr. John Katz
Alaska Department of Natural Resources
Pouch M
Juneau, Alaska 99811
cc: Mr. Larry Wright
National Park Service
1 011 East Tudor Road
Suite 297
Anchorage, Alaska 99503
cc: Mr. Alan Carson
Division of Natural Resources
Alaska Department of Natural
Resources
Pouch 7-005
Anchorage, Alaska 99510
cc: Mr. Larry Wright
National Park Service
1011 East Tudor Road
Suite 297
Anchorage, Alaska 99503
cc: Mr. Alan Carson
Division of Natural Resources
Alaska Department of Natural
Resources
Pouch 7-005
Anchorage, Alaska 99510
cc: Mr. Alan Carson
Division of Natural Resources
Alaska Department of Natural
Resources
Pouch 7-005
Anchorage, Alaska 99510
-'
-5
-.
-I
-
r
r
r
'
-
-'
TABLE 1.1 (Cont'd)
Aesthetics and Land Use Group (cont'd)
Mr • John Rego
Bureau of Land Management
Anchorage District Office
4700 East 72nd Avenue
Anchorage, Alaska 99507
General
Ms. Wendy 1'4olt
Office of Coastal Management
Division of Policy Development and Planning
Pouch AP
Juneau, Alaska 99811
I i
TABLE 1.2: ORIGINAL LIST Of REPORTS AND GROUPS TO
WHICH REPORTS WERE/WERE TO BE SENT
Report
Plan of Study and Plan of Study Revisions
Development Selection Report
1980 Annual Environmental Summary Report
1980 Annual Reports
Fish Ecology
Big Game
Birds and Non-Game Mammals
Furbearers
Plant Ecology
Land Use
Socioeconomics
Cultural Resources
Recreation
Instream Flow Study Plan
Transmission Line Corridor Screening Report
Fish and Wildlife Mitigation Policy
Feasibility Report
1981 Final Phase I Reports
FWB = Fish, Wildlife, and Botanical
ALU = Aesthetics, Land Use
HA = Historic and Archaeological
R = Recreation
WQ = Water Quality
G = General
Group
A11
A11 -
A11
FWB
FWB
FWB
FWB
FWB
ALU
HA
HA
R
WQ, FWB, G
A11
FWB
A11
A11
-
-
-
-
-
-
r
-I
r
r
TABLE 1.3: ORIGINAL LIST OF AGENCIES AND
REPORTS RECEIVED (TO BE RECEIVED)
Agency
Alaska Department of
Natural Resources
Alaska Department of
Fish and Game
Alaska Department of ·
Environmental Conservation
Alaska Department of
Community and Regional Affairs
Report
Plan of Study
Plan of Study Revisions
Development Selection Report
1980 Annual Environmental Summary Report
Instream Flow Study Plan
1980 Socioeconomic Annual Report
1980 Cultural Resources Annual Report
1980 land Use Annual Report
1980 Recreation Annual Report
Transmission Line Corridor Screening Report
fish and Wildlife Mitigation Policy
Feasibility Report
Final Phase I Reports
Plan of Study and Plan of Study Revisions
Development Selection Report
1980 Annual Environmental Summary Report
lnstream Flow Study Plan
1980 Fish Ecology Annual Report
1980 Big Game Annual Report
1980 Birds and Non-Game Mammals .'\nnual Report
1980 furbearers Report
1980 Plant Ecology Report
Transmission Line Corridor Screening Report
Fish and W.ildli fe Mitigation Policy
Feasibility Report
Final Subtask Reports
Plan of Study
Plan of Study Revisions
Development Selection Report
1980 Annual Environmental Summary Report
Instream Flow Study Plan
1980 Fish Ecology Annual Report
1980 Big Game Annual Report
1980 Birds and Non.-Game Mammals Annual Report
1980 Furbearers Report
1980 Plant Ecology Report
Transmission Line Corridor Screening Report
fish and Wildlife Mitigation Policy
Feasibility Report
Final Subtask Report
Plan of Study
Plan of Study Revisions
Development Selection Report
1980 Annual Environmental Summary Report
1980 Socioeconomic Annual Report
1980 Cultural Resources Annual Report
Transmission Line Corridor Screening Report
Feasibility Report
final Subtask Reports
TABLE 1.3 (Cont'd)
Agency
Division of Policy Development
and Planning Office of Coastal
Management
Mantanuska-Susitna Borough
Cook Inlet Region, Inc.
U.S. Environmental Protection
Agency
U.S. Army Corps of Engineers
National Marine Fisheries
Service
Report
Plan of Study
Plan of Study Revisions
Development Selection Report
1980 Annual Environmental Summary Report
Instream Flow Study Report
Transmission Line Corridor Screening Report
Feasibility Report
Final Subtask Reports
Plan of Study
Plan of Study Revisions
Development Selection Report
1980 Annual Environmental Summary Report
1980 Recreation Annual Report
Transmission Line Corridor Screening Report
Feasibility Report
Final Phase I Reports
Plan of Study
Plan of Study Revisions
Development Selection Report
1980 Annual Environmental Summary Report
1980 Land Use Annual Report
Transmission Line Corridor Screening Report
Feasibility Report
Final Phase I Reports
Plan of Study
Plan of Study Revisions
Development Selection Report
1980 Annual Environmental Summary Report
Instream Flow Study Plan
Transmission Line Corridor Screening Report
Feasibility Report
1981 Final Phase I Reports
Plan of Study
Plan of Study Revisions
Development Selection Report
1980 Annual Environmental Summary Report
Instream Flow Study Plan
Transmission Line Corridor Screening Report
Feasibility Report
1981 Final Phase I Reports
Plan of Study
Plan of Study Revisions
Development Selection Report
1980 Annual Environmental Summary Report
Instream Flow Study Report
1980 Fish Ecology Annual Report
1980 Big Game Annual Report
1980 Birds and Non-Game Mammals Annual Report
1980 Furbearer Report
1980 Plant Ecology
Transmission Line Corridor Screening Report
Fish and Wildlife Mitigation Policy
Feasibility Report
1981 Final Phase 1 Reports
-
-·
-
-
-
-' '
!"'"'
I
r
-
TABLE 1.3 (Cont'd)
Agency
U.S. Fish and Wildlife
Service
National Park Service
U.S. Bureau of Land
Management
Report
Plan of Study
Plan of Study Revisions
Development Selection Report
1980 Annual Environmental Summary Report
Instream Flow Study Plan
1980 Fish Ecoloyy Annual Report
1980 Big Game Annual Report
1980 Birds and Non-Game Mammals Annual Report
1980 Furbearer Report
1980 Plant Ecology Report
Transmission Line Corridor Screening Report
Fish and Wildlife Mitigation Policy
Feasibility Report
1981 Final Phase I Reports
Plan of Study
Plan of Study Revisions
Development Selection Report
Instream Flow Study Plan
1980 Annual Environmental Summary Report
1980 Socioeconomic Annual Report
1980 Cultural Resources Annual Report
1980 Recreation Annual Report
Transmission Line Carr idor Screening Report
Feasibility Report
1981 Final Phase I Reports
Plan of Study
Plan of Study Revisions
Development Selection Report
Instream Flow Study Report
1980 Annual Environmental Summary Report
1980 Land Use Annual Report
Transmission Line Corridor Screening Report
Feasibility Report
1981 Final Phase 1 Reports
TABLE 1.4: AGENCY COORDINATION EXPANDED LIST
Water Quality and Use Group
Mr. Max Brewer *
Office of the Director
Special Assistant for Alaska
U.S. Geological Survey
218 East Street
Anchorage, Alaska 99501
Mr. John Cook **
Acting Regional Director
Alaska Region
National Park Service
540 West Fifth Avenue
Anchorage, Alaska 99501
Mr. John Katz
Alaska Department of Natural Resources
Pouch M
Juneau, Alaska 99811
Mr. Robert McVey *
Director, Alaska Region
National Marine Fisheries Service
NOAA
P.O. Box 1668
Juneau, Alaska 99802
Mr. Ernest W. Mueller *
Commissioner
Alaska Department of Environmental
Conservation
Pouch 0
Juneau, Alaska 99801
Colonel Lee Nunn
District Engineer
Alaska District
U.S. Army Corps of Engineers
P. 0. Box 7002
Anchorage, Alaska 99510
Hr. John Rego
Bureau of Land Management
Anchorage District Office
4700 East 72nd Avenue
Anchorage, Alaska 99507
Mr. Keith Schreiner *
Regional Director, Region 7
U.S. Fish and Wildlife Service
1011 East Tudor Road
Anchorage, Alaska 99501
Mr. Ronald D. Skoog *
Commissioner
State of Alaska Department of Fish & Game
Support Building
Juneau, Alaska 99801
cc: Mr. larry Wright
National Park Service
1011 East Tudor Road
Suite 297
Anchorage, Alaska 99503
cc: Mr. Alan Carson
cc:
cc:
Division of Natural Resources
Alaska Department of Natural
Pouch 7-005
Anchorage, Alaska 99510
Mr. Ron Mlrris
Director
Anchorage Field Office
National Marine Fisheries
Service
701 C Street, Box 43
Anchorage, Alaska 99513
Mr. Bob Martin
Alaska Department of
Environmental Conservation
437 East Street, 2nd Floor
Anchorage, Alaska 99501
cc: Mr. lenny Carin
U.S. Fish and Wildlife Service
Western Alaska Ecological
Service
733 West 4th Avenue
Anchorage, Alaska 99501
cc: Mr. Thomas Trent
State of Alaska
Department of Fish and Game
2207 Spenard Road
Anchorage, Alaska 99502
* Added at the suggestion of the Susitna Hydro Steering Committee.
**Added as a result of specific agency request.
-
""""'
""""
-
~
I"''">
r
'
-
-
-
-
r
I
TABLE 1.4 (Cont'd)
t~r. John R. Spencer
Regional Administrator
Region X
U.S. Environmental Protection Agency
1200 Sixth Avenue
Seattle, Washington 98101
cc: Ms. Judy Swartz u.s. Environmental Protection
Agency
Mail Stop 443
Region X EPA
1200 South 6th Avenue
Seattle, Washington 98101
Fish, Wildlife, and Botanical Group
Mr. Max Brewer *
Office of the Director
Special Assistant for Alaska
U.S. Geological Survey
218 East Street
Anchorage, Alaska 99501
Mr. John Katz
Alaska Department of Natural Resources
Pouch M
Juneau, Alaska 99811
Mr. Robert McVey
Director, Alaska Region
National Marine Fisheries Service
NOAA
P.O. Box 1668
Juneau, Alaska 99802
Mr. Ernest W. Mueller
Commissioner
Alaska Department of Environmental
Conservation
Pouch 0
Juneau, Alaska 99801
Mr. John Rego *
Bureau of LandManagement
Anchorage District Office
4700 East 72nd Avenue
Anchorage, Alaska 99507
Mr. Keith Schreiner
Regional Director, Region 7
U.S. Fish and Wildlife Service
1011 East Tudor Road
Anchorage, Alaska 99503
cc: Mr. Alan Carson
Division of Natural Resources
Alaska Department of Natural
Pouch 7005
Anchorage, Alaska 99510
cc: Mr. Ron Morris
Director
Anchorage Field Office
National Marine Fisheries
Service
701 C Street, Box 43
Anchorage, Alaska 99513
cc: Mr. Bob Martin
Alaska Department of
Environment a! Conservation
437 East Street, 2nd Floor
Anchorage, Alaska 99501
cc: Mr. Robert Bowker
U.S. Fish and Wildlife Service
Western Alaska Ecological
Service
733 West 4th Avenue
Anchorage, Alaska 99501
Mr. Ronald 0. Skoog c c: Mr. Thomas Trent
State of Alaska Commissioner
State of Alaska Department of Fish and Game
Support Building
Juneau, Alaska 99801
Department of Fish and Game
2207 Spenard Road
Anchorage, Alaska 99502
* Added at the suggestion of the Susitna Hydro Steering Committee.
I!
TABLE 1.4 (Cont'd)
Mr. John Spencer *
Regional Administrator
cc: Ms. Judy Swartz
U.S. Environmental Protection Agency
1200 Sixth Avenue
Seattle, Washington 98101
U.S. Environmental Protection
Agency
Mail Stop 443
Region X EPA
1200 Sixth Avenue
Seattle, Washington 98101
Historic and Archaeological Group
Mr. John Cook
Acting Regional Director
Alaska Region
National Park Service
540 West Fifth Avenue
Anchorage, Alaska 99501
Ms. Lee McAnerney
Department of Community and Regional Affairs
Pouch B
Juneau, Alaska 99811
Mr . John Rego *
Bureau of Land Management
Anchorage District Office
4700 East 72nd Avenue
Anchorage, Alaska 99507
Mr. Robert Shaw
State Historic Preservation Officer
Alaska Department of Natural Resources
Division of Parks
619 Warehouse Avenue, Suite 210
Anchorage, Alaska 99501
cc: Mr. Larry Wright
National Park Service
1011 East Tudor Road
Suite 297
Anchorage, Alaska 99503
cc: Mr. Alan Carson
Division of Natural Resources
Alaska Department of Natural
Resources
Pouch 7-005
Anchorage, Alaska 99510
Mr. Ronald 0. Skoog * cc: Mr. Thomas Trent
State of Alaska Commissioner
State of Alaska Department of Fish and Game
Support Building
Juneau, Alaska 99801
Mr. Lee Wyatt**
Planning Director
Matanuska-Susitna Borough
Box 8
Palmer, Alaska 99645
Department of Fish and Game
2207 Spenard Road
Anchorage, Alaska 99502
Recreation Group
Mr. John Cook
Acting Regional Director
Alaska Region
National Park Service
540 West Fifth Avenue
Anchorage, Alaska 99501
cc: Mr. Larry Wright
National Park Service
1011 East Tudor Road
Suite 297
Anchorage, Alaska 99503
* Added at the suggestion of the Susitna Hydro Steering Committee.
**Added as a result of specific agency request.
-
-
-
-
-
J -
r
-
,...
f
I I;'
-I
TABLE 1.4 (Cont'd)
~1r. John Katz
Alaska Department of Natural Resources
Pouch M
Juneau, Alaska 99811
Mr. Robert McVey *
Director, Alaska Region
National Marine Fisheries Service
NOAA
P.O. Box 1668
Juneau, Alaska 99802
Mr. Keith Schreiner *
Regional Director, Region 7
U.S. Fish and Wildlife Service
1011 East Tudor Road
Anchorage, Alaska 99503
cc: Mr. Alan Carson
Division of Natural Resources
Alaska Department of Natural
Resources
Pouch 7-005
Anchorage, Alaska 99510
cc: Mr. Ron Morris
Director
Anchorage Field Office
National Marine Fisheries
Service
701 C Street, Box 43
Anchorage, Alaska 99513
Mr. Ronald 0. Skoog * cc: Mr. Thomas Trent
State of Alaska Commissioner
State of Alaska Department of Fish and Game
Support Building
Juneau, Alaska 99801
Mr. Lee Wyatt
Planning Director
Matanuska-Susitna Borough
Box B
Palmer, Alaska 99645
Department of Fish and Game
2207 Spenard Road
Anchorage, Alaska 99502
Aesthetics and Land Use Group
Mr. John Cook **
Acting Regional Director
Alaska Region
National Park Service
540 West Fifth Avenue
Anchorage, Alaska 99501
Mr. Roy Huhndorf
President
Cook Inlet Region, Incorporated
P.O. Drawer 4N
Anchorage, Alaska 99509
Mr. John Katz
Alaska Department of Natural Resources
Pouch M
Juneau, Alaska 99811
Mr. John Rego
Bureau of Land Management
Anchorage District Office
4700 East 72nd Avenue
Anchorage, Alaska 99507
cc: Mr. Larry Wright
National Park Service
1011 East Tudor Road
Suite 297
Anchorage, Alaska 99503
cc: Mr. Alan Carson
Division of Natural Resources
Alaska Department of Natural
Resources
Pouch 7-005
Anchorage, Alaska 99510
* Added at the suggestion of the Susitna Hydro Steering Committee.
**Added as the result of specific agency request.
TABLE 1.4 (Cont'd)
Mr. Keith Schreiner *
Regional Director, Region 7
U.S. Fish and Wildlife Service
1011 East Tudor Road
Anchorage, Alaska 99503
Mr. Ronald 0. Skoog * cc: Mr. Thomas Trent
State of Alaska Commissioner
State of Alaska Department of Fish and Game
Support Building
Juneau, Alaska 99801
Mr. Lee Wyatt**
Planning Director
Matanuska-Susitna Borough
Box B
Palmer, Alaska 99645
Department of Fish and Game
2207 Spenard Road
Anchorage, Alaska 99502
Socioeconomic Group*
Director of Planning
Fairbanks North Star Borough
520 5th Avenue
P.O. Box 1267
Fairbanks, Alaska 99701
Mr. Roy Huhndorf
President
Cook Inlet Region, Incorporated
P.O. Drawer 4N
Anchorage, Alaska 99509
Mr. John Katz
Alaska Department of Natural Resources
Pouch M
Juneau, Alaska 99811
Ms. Lee McAnerney
Department of Community and Regional Affairs
Pouch B
Juneau, Alaska 99811
Mr. Michael Meehan
Director, Planning Department
Municipality of Anchorage
Pouch 6-650
Anchorage, Alaska 99502
cc: Mr. Max Dolchak
Executive Director
Cook Inlet Native Association
670 Firewood Lane
Anchorage, Alaska 99502
cc: Mr. Alan Carson
Divis ion of Natural Resources
Alaska Department of Natural
Resources
Pouch 7-005
Anchorage, Alaska 99510
Mr. Ronald 0. Skoog * cc: Mr. Thomas Trent
State of Alaska Commissioner
State of Alaska Department of Fish and Game
Support Building
Juneau, Alaska 99801
Mr. Herb Smelcer, President
General Manager
AHTNA Corporation
Drawer G
Copper Center, Alaska 99573
Department of Fish and Game
2207 Spenard Road
Anchorage, Alaska 99502
* Added at the suggestion of the Susitna Hydro Steering Committee.
**Added as a result of specific agency request.
-'
~I
~,
-
111'1!\
I
-
-
-
TABLE 1.4 (Cont'd)
Mr. Lee Wyatt
Planning Director
Matanuska-Susitna Borough
Box B
Palmer, Alaska 99645
Geological and.Soils Group *
Mr. Max Brewer
Office of the Director
Special Assistant for Alaska
U.S. Geological Survey
218 East Street
Anchorage, Alaska 99501
Mr. John Katz
Alaska Department of Natural Resources
Pouch M
Juneau, Alaska 99811
Mr. David Haas
State-Federal Assistance Coordinator
State of Alaska
Office of the Governor
General
Division of Policy Development and Planning
Pouch AW
Juneau, Alaska 99811
Ms. Wendy Walt
Office of Coastal Management
Division of Policy Development and Planning
Pouch AP
Juneau, Alaska 99811
cc: Mr. Alan Carson
Division of Natural Resources
Alaska Department of Natural
Pouch 7-005
Anchorage, Alaska 99510
* Added at the suggestion of the Susitna Hydro Steering Committee.
I I
TABLE 1. 5: EXPANDED LIST OF REPORTS AND GROUPS TO WHICH
REPORTS WERE/WERE TO BE SENT
REPORT GROUP*
Instream Flow Study Plan
Draft Fishery Mitigation Plan
Draft Wildlife Mitigation Plan
Final Phase I Reports:
(a) Fish Ecology
(b) Wildlife Ecology
(c) Plant Ecology
(d) Birds and Non-Game Mammals
(e) Furbearers
(f) Land Use
(g) Socioeconomics
(h) Cultural Resources
( i) Recreation
Land Status Report
Interim Report on Seismic Studies
Final Report on Seismic Studies
Geotechnical Exploration Report on 19BO Studies
Geotechnical Exploration Report on 19B1 Studies
Water Quality Report
Water Use Report
River Morphology
Sociocultural Report
Environmental Evaluation of Access Plans
Engineering Evaluation of Access Plans
*ALU
FWB
HA wa
R
SE
GS
G
= Aesthetics, Land Use
=Fish, Wildlife, and Botanical
= Historic, Archaeological
= Water Quality = Recreation
= Socioeconomic
= Geology and Soils
= General
R, ALU
WQ, FWB, R, ALU
WQ, FWB, R, ALU
WQ, FWB, R
WQ, FWB, R
FWB, ALU
FWB, R
FWB, R, SE
ALL
FWB, R, ALU, SE, G
HA, SE
R
R, ALU, SE, GS
GS
GS
GS
GS
WQ, FWB, R, ALU
~Q, FWB, R, ALU, SE
WQ, FWB, R, ALU, GS
FWB, HA, R, ALU, SE
WQ, FWB, HA, R, ALU, SE, GS
WQ, FWB, HA, R, ALU, SE, GS
Note: These reports and groups were added to those listed in Table 1.2.
Groups refer to those listed in Table 1.4.
-
-
"""' I
-
-
TABLE 1.6: REPORTS, DATE SENT, AND PURPOSE
~· PRIOR TO
DOCUMENT 03/15/82 03/15/82 04/01/82 04/15/82 04/30/82 PURPOSE*
Plan of Study X FC
r""' Plan of Study -Revision 1 X FC
1980 Summary Environmental Report X I
i '
1980 Annual Environmental Reports:
(a) Fish Ecology X I
(b) Plant Ecology X I ,.... (c) Big Game, Birds, and Non-Game X I
Mammals, Furbearers
(d) Land Use X I
(e) Socioeconomics X I
1""" (f) Cultural Resources X I
! Transmission Line Corridor Screening
Report X FC
Development Selection Report X FC
!""'
Initial Fish and Wildlife Mitigation
Policy X FC
(Revised Mitigation Policy) X FC
Instream Flow Study X FC
Feasibility Report X FC
""""
Draft Fishery Mitigation Plan X FC
Draft Wildlife Mitigation Plan X FC
Phase I Environmental Reports:
(a) Fish Ecology -ADF&G X I
(b) Wildlife Ecology -ADf&G X I
I""" (c) Plant Ecology X I
(d) Bird and Non-Game Mammals X I
(e) Furbearers X I
(f) Land Use X I ,.. (g) Socioeconomics X I
(h) Cultural Resources X I
(i) Recreation X FC
Land Status Report X I
!""" Interim Report on Seismic Studies X I
final Report on Seismic Studies X I
Geotechnical Exploration Report on
1980 Studies X I
Geotechnical Exploration Report
~ 1981 Studies X I
Water Quality Report X I
Water Use Report X I
River Morphology Report X I ,_. Sociocultural Report X I
Environmental Evaluation of
Access Plans X I
Access Route Selection Report X I
*FC = formal Comments Requested
I = Provided for Information Only
-
r
l
TABLE 1.7: MEMBERS Of THE SUSITNA HYDROELECTRIC
PROJECT STEERING COMMITTEE
State Agencies
Alaska Department of Fish and Game
Alaska Department of Natural Resources
Alaska Department of Commerce
Alaska Department of Environmental
Conservation
Other
federal Agencies
U.S. Fish and Wildlife Service
U.S. Geology Survey
National Park Service
National Marine Fisheries Service
U.S. Bureau of land Management
Environmental Protection Agency
Heritage Conservation and
Recreation Service
Arctic Environmental Information and Data Center
Note: U.S. Army Corps of Engineers, Alaska Division of Policy Development and
Planning and Matanuska-Susitna Borough were invited but declined to sit
on the Steering Committee.
-
-
, I
' I
,..,,
i i
1 ;
-
TABLE 1.8: DATES AND PURPOSE OF STEERING COMMITTEE
MEETINGS WITH APA AND/OR ITS CONSULTANTS
DATE
June 1 2 , 1980
July 17, 1980
November 5, 1980
Apri113, 1981
October 20, 1981
December 2, 1981
January 20, 1982
PURPOSE
Objective of Committee and Introduction
to Project
Federal Energy Regulatory Commission and
State License Process, Instream Flow
Studies
Evaluation of Alternatives to Susitna
Alternatives, Access Road Evaluation, and
Comments on Environmental Studies
Access Road Evaluation
Explanation of Agency Comment Requests
from APA
Environmental Studies and Concerns,
Fisheries Mitigation
I i
State. Agencies
TABLE 1.9: AGENCIES INVITED AND THOSE WHICH
DECLINED TO BE ON THE FISH AND
WILDLIFE MITIGATION REVIEW GROUP
Alaska Department of Fish and Game
Alaska Department of Natural Resources
Federal Agencies
U.S. Fish and Wildlife Service
National Marine Fisheries Service
U.S. Bureau of Land Management
Environmental Protection Agency
U.S. Geological Survey u.S. Army Corps of Engineers
Status
Agreed
Agreed
Agreed
Agreed
Agreed
Agreed
Declined
Declined
-i
-
-
r"·
I
f
APPENDIX A
AGENCIES CONTACTED FOR INFORMATION
DURING PREPARATION OF THE SUSITNA
ENVIRONMENTAL REPORTS
.f""\
\
!"""
I
I
··!""">
!
APPENDIX A
AGENCIES CONTACTED FOR INFORMATION
DURING PREPARATION OF THE SUSITNA
ENVIRONMENTAL REPORTS
The following list names individuals frorn federal, state, and local agencies as
well as other institutions and organizations who were contacted regarding the
Susitna Hydroelectric Project Environmental Studies Program. These individuals
were consulted between October 1, 1979, and January 15, 1982. Arranged by
environmental report section as they appeared in Volume 2 of the Feasibility
Study, the names listed include:
(1) Those contacts made byTES and/or TES subcontractors for input related
specifically to that report sectiori;
(2) Those contacts made byTES and/or TES subcontractors, the information from
which, while pertinent to a different environmental report section, was
also applicable to the section in question; and
(3) Contacts made byTES, TES subcontractors, Acres, or the Alaska Power
Authority applicable to the Susitna Environmental Studies in general.
The nature of these contacts ranges from requests for data to inquiries con-
cerning the environmental studies procedures. These lists are not intended to
include those contacts made with other members of the Environmental Studies
Team, although some project personnel are 1 i sted because of the capacity in
which they were consulted.
-
·-
Report on Fish, Wildlife, and Botanical Resources
FEDERAL AGENCIES
United States Department of Agriculture
Agricultural Stabilization and Conservation Service
. -Lola Britton: File Manager
Forest Service, Institute of Northern Forestry
-Joan Foote: Biologist .
-Fred Larson: Research Forester
-Vic VanBa11enberghe: Wildlife Biologist
-Leslie Viereck! Principal Plant Ecologist
Pacific Northwest Forest and Range Experimental Station
-Robert Ethi nat on: Director
Soil Conservation Service
-Weymeth Long: Director of State Office
-Sterling Powell: Physical Engineer, Water Resource Specialist
United States Department of Commerce
National t4arine Fisheries Service
-Robert McVey: Director
-Ronald Morris: Supervisor
-Bradley Smith: Fishery Biologist
United States Department of Defense
Army Cold Region Research Environmental Laboratory
-Jerry Brown: Chief, Environmental Research Branch
Army Corps of Engineers, Alaska District
-Loran Baxter: Civil Engineer
-Richard Borcetti: Biologist, Permit Processing
-Phillip Brna: Biologist
. -James Caruth: Chief of Regulatory Functions
-Jack Ferri se: Civi 1 Engineering Technician Compliance Investigator
-Col. Lee Nunn: District Engineer
-Lt. Col. J. Perkins: Deputy District Engineer
United States Department of Energy
Alaska Power Administration
-Fredrick Chiei: Deputy Regional Representative
-Robert Cross: Administrator
-Donald Shira: Chief of Planning
Federal Energy Regulatory Commission, Division of Licensed Projects
-Ronald Corso: Director
-Paul Carrier: Engineer
-Donald Clarke: Staff Counsel
-Thomas Dewit: Landscape Architect
-Quentin Eds.on: Chief, Environmental Analysis Branch
-Julian Flint: Supervisor, Engineering Project Analysis Branch
-Peter Foote: Fishery Biologist
-Donald Giampaoli: Department Director
I I
-Mark Robinson:
-Dean Shumway:
-Gerald Wilson:
Environmental Biologist
Chief, Conservation Section
Chief, Project Analysis
United States Department of the Interior
Bureau of Land Management
-Patrick Beckley: Chief, Branch of Lands and Minerals
-Louis Carufel: Fisheries Biologist
-Ann Dawe
-Art Hosterman: Chief, Branch of Biologica1 Resources
-Paula Krebs: Remote Sensing Specialist
Steve Leskosky: Environmental Planner
-John Rego: ·Geo 1 og i st
-Mike Scott: Fisheries Biologist
Gary Seitz: Environmental Coordinator
-Page Spencer: Remote Sensing Specialist
-Steve Talbot: Ecologist
-Dick Tindall: Anchorage District Manager
Bureau of Mines
-Bob Ward: Chief, Environmental Planning Staff
Fish and Wildlife Service
-Mike Amaral: Endangered Species Biologist
-Skip Ambrose: Endangered Species Biologist
-Bruce Apple: Fisheries Biologist
-Dale Arhart: Staff Biologist
-Keith Baya: Assistant Director for the Environment
-Robert Bowker: Field Supervisor, Western Alaska Ecological Services Unit
-Carl Burger: Research Fisheries Biologist, Advisor, Radio Telemetry
Project
-Bruce Conant: Wildlife Biologist/Pilot
-Lenny Corrin: Fish and Wildlife Projects Coordinator
-Dirk Derksen: Waterfowl Biologist
Gregory Konkel: Habitat Evaluation Coordinator
-Donald McKay: Wildlife Biologist
-Dennis Money: Endangered Species Coordinator
-John Morrison: Supervisor, Biological Services Program
-Mel Munson: Program Supervisor. Land and Water Program
-A. Palmisana: Research Chemist
-Wayne Regelin: Research Biologist
-Mel Schamberger: Habitat Evaluation Procedures Group Leader, Biological
Services Program
-Keith Schreiner: Region Seven Director
-Gary Stackhouse: Fish and Wildlife Biologist 9 Federal Projects/Technicial
Assistance Coordinator
-Mike Thompson: Fisheries Biologist
-John Trapp: Marine Bird Management Project Leader
-Dave Waangard: Research Fisheries Biologist -
-Richard Wilmot: Fisheries Research Project Leader
Geological Survey
-Derrill Cowing: Hydrologist
-Gary Hickman: Area Director
-Robert Lamke: Chief, Hydrology Section
-Bob Madison: Hydrologist. Water Quality Specialist
Heritage Conservation and Recreation Service
-William Welch: Supervising Outdoor Recreation Planner
-j
\ __ .I
~~
I
\
~ '
r
Nation a 1 Park Service
-Brailey Breedlove: Landscape Architect
-Terry Carlstrom: Chief of Planning and Design
-Ross Cavenaugh: Fisheries Biologist
-Carl Stoddard: Park Ranger
United States Environmental Protection Agency
-John Spencer: Region X Administrator
Environmental Evaluation Branch
-Judi Schwartz: Environmental Protection Specialist
Environmental Impact Statement Review Section
-Elizabeth Corbyn: Chief, Environmental Evaluation Branch
-Dan Sternborn: Team Leader
STATE AGENCIES
Alaska Department of Commerce and Economic Development
-Charles Webber: Cammi ssi oner
Alaska Power Authority
-Bruce Bedard: Inspector, Native Liaison
-David Wozniak: Project Engineer
Divi sian of Energy and Power Development
-Heinz Noonan: Economist
Alaska Department of Community ·and Regional Affairs
-Lee McAnerney: Commissioner
Alaska Department of Environmental Conservation
.. Ernst Mue 11 er: Commissioner
-Robert Flint: Region II Program Coordinator
-Rikki Fowler: Ecologist
-Robert Martin: Regional Supervisor
-David Sturdevant: Management and Technical Assistant Ecologist
-Dan Wilkerson: Special Projects Planner
-Steve Zrake: Environmental Field Officer
Alaska Department of Fish and Game
-Ronald Skoog: Commissioner
Division of Boards
-Robert Larson: Biologist~ Division Director
Division of Commercial Fisheries
-Dennis Haanpaa: Assistant Regional Supervisor
-Alan Kingsbury: Regional Research Supervisor
Divi sian of Game
-Paul Arneson: Biologist
-Gregory Bos: Game Biologist IV
-Bruce Cambell: Waterfowl Biologist
-Jack Oidrickson: Game Biologist
-Sterling Eide: Regional Supervisor
-David Johnson: Game B i a 1 ogi st
-Herbert Melchior:. Game Biologists III
-Lee Mi 11 er: Fish and Game Tecnni ci an V
-Sterling Miller: Game Biologist III
-Suzanne Miller: Statistician. Biometrician III
-Kenneth Pitcher: Game Biologist
-Karl Schneider: Research Coordinator
-Charles Schwartz: Biologist II
-Jerome Sexton: Game Biologist II
-Dan Timm: Game Biologist III, Chief Waterfowl
-Elroy Young:· Game Biologist III
Division of Habitat Protection
-Richard Logan: Chief
-Thomas Arminski: Regional Land Specialist
-Dimitri Bader: Lands Coodi nator, Habitat Bi ol ogi st
-Phil Brna: Habitat Biologist II
-Richard Cannon: Habitat Biologist III
-John Clark: Assistant Chief·
-Devany Lehner-Welch: Habitat Biologist II
-Don McKay: Habitat Biologist III
~ Marguerite Paine: Habitat Biologist II
-Frances VanBallenberghe: Habitat Biologist III
-Carl Yanagawa: Regional Supervisor
Division of Sport Fisheries
-Kevin Delaney: Fishery Biologist II
-Christopher Estes: Fishery Biologist III, Susitna Aquatic Studies
-Larry Heckart: Fishery Biologist IV
-Michael Mills:. Senior Fisheries Biometrician III
-Thomas Trent: Regional Supervisor, Susitna Aquatic Studies Coordinator.
Vice-Chairman of Susitna Steering Committee
-Kyle Watson: Clerk IV, Susitna Hydroelectric Aquatic Studies Staff Roster
Subsistence Division
-Ronald Stanek: Resource Specialist II
A1 aska Department of Natura 1 Resources
-Robert LeResche: Commissioner
Division of Forest Land and Water
-Ted Smith: Director
-Mary Lou Harle: Water Management Officer
Division of Lands
-Dean Brown: Southcentral District lands Officer
-Michael Franger: Special Projects Officer
Division of Minerals and Energy
-G1en Harrison: Director
Division of Parks
-Jack Wiles: Chief
Division of Research and Development
-Linda Arndt: Land Management Officer
-Christopher Beck: Planner III
-Al Carson: Deputy Director
-lloyd Egg an: Assist ant Analyst II
Divison of Water Resources
-Brent Petrie: Chief
-Richard Stern: Historian, Research and Planning
Alaska Department of Revenue
-Linda Lockridge: Records and Licensing Supervisor, Fish and Game Licensing
Division
-Hazel Nowlin: Administrative Assistant, Administration Services
.....
'
~,
~\
l
r-
1
I
\
t j
r
-'
Alaska Department of Public Safety
Division of Fish and Wildlife Protection
-Col. Robert Stickles: Director
-Wayne Fleek: Region III Commander
-Lt. Rod Mills: Administrative Officer
-Lt. Col. Tetz 1 aff: Deputy Director
A 1 ask a Department of Transportation
-Jay Bergstrand: Transportation Planner IV
-Cathy Derickson: Transportation Planner
-Reed Gibby: Transportation Planner
· Brock University
~nstitute of Urban and Environmental Studies, St. Cathari nes, Ontario, Canada
-Fikret Berkes: Director
Canadian Territorial Agencies
Northwest Territories Fish and Game Branch, Yellowknife, Northwest Territories
-Bruce Stevenson: Research Co-ordinator
Office of the Governor
Division of Policy Development and Planning
-Frances Ulmer: Director
University of Alaska
-Rose ann Dunsmore: Graduate Student
-Tony Gharret: Professor
Agricultural Experiment Station
-Willi am Mitche 11: Head Agronomist
Arctic Environmental Information and Data Center
-Mr. Becker: Climatologist
-Chuck Evans: Research Associate, Wildlife BiDlogist
-Richard Hensel: Game Biologist
-William Wilson: Fisheries Biologist
Geophysical ·Institute
-Ken Dean: Remote Sensing Geologist
-Ian Hutchison: Professor of Physics
-T. Osterkamp: Professor of Physics
Museum
-David Murray: Her5ari urn Curator
LOCAL AGENCIES
Matanuska-Susitna Borough
Borough Office
-Lee Wyatt: Acting Borough Manager, Planning Director
OTHER INSTITUTIONS, ORGANIZATIONS AND INDIVIDUALS
Institutions and Organizations
Battelle Pacific Northwest Laboratories, Richland, Washington
-Lester E. Ebechardt: Terrestrial Ecology Section
Chick a loon Vi 11 age
-Jess Landsman: President
Colorado State University
Department of Fishery and Wildlife Biology
-Gustav Swanson: Professor and Department Head
Cook Inlet Aquaculture Association
-Floyd Heimback: Director
-Thomas Mears: Biologist
-Thomas Wa Jker: Economist
Cook Inlet Region, Incorporated
-Agnes Brown: Executive
-Lynda Hays: Shareholder and Community Relations Coordinator
-Robert Rude: Senior Vice-President
-John Youngblood: Executive Director
Fairbanks Environmental Center
-Jeff Weltzin: Energy Coordinator
HDR Sciences, Santa Barbara, California
-Ken Reed
Hal mes and Narver
-James Pederson: Susitna Project Manager
Idaho Cooperative Wildlife Research Unit
-Dudley Reiser: Fisheries Biologist, Private Consultant
Keua1 Village
-James Shoalwolfer: President
Kni katnu Incorporated
-Paul Theadore: Chief
L.G.L. Alaska, Incorporated
-David Roseneau: Biologist
National Museum Canada
Museum of Natural Hi story
-George Argus: Associate Curator, Vascular Plant Section
Ninilchik Native Assodation, Incorporated
-Arno 1 d Orhdh off: Chief
Ni ni 1 chi k Vi 1.1 age
-Arnold Orhdhoff: President
Norsk Hydro, Sweden
-Iver Hagen: Public Relations
Northern Prairie Wildlife Research Center, Jamestown, North Dakota
-Al Sargeant: Wildlife Research Biologist
Sagehen Creek Field Station, California
-Wayne Spencer: Biologist
-William Zielinski: Biologist
Sa1amatoff Native Association, Incorporated
~Andy Johnson: President
Seldovia Native Association, Incorporated
-James Segura: Chief
Susitna Power Now
-E. Dischner: Executive Director
Tyonek Native Corporation
-Agnes Brown: President
United Fishermen of Alaska
-Rodger Painter: Executive Director
University of Cal gary, Alberta, Canada
-Dr. Stephen Herrero: Faculty of Experimental Design and Department of
Biology
University of Montana
School of Forestry
-Dr. Charles Jonkel: Director, Northern Border Grizzly Bear Project
-
r
University of Uppsala, Sweden
-Dr. Hugo Sjors: Professor of Ecological Botany
Individuals
-Ron Long: Trapper
-Mary Kay McDonald: Trapper
Cleo McMahon: Pilot, Hunter in Upper Susitna Basin
-Don Newman: Trapper
-Dorothy Palzin: Deshka Resident
-Carol Resnick: Tsusena Creek Resident
-Philip Roullier: Indian River Resident
-Robert Scheufele: Talkeetna Resident
-Leroy Shank: Trapper
-Robert Smith: Tsusena Creek Resident
~ Roger Smith: Trapper
-Glen Wingkte: Trapper
Report on Historic and Archeological Resources
FEDERAL AGENCIES
United States Department of Agriculture
Soil Conservation Service
-Sterling Powell: Physical Engineer, Water Resource Specialist
United States Department of Defense
Army Corps of Engineers, Alaska District
-Col. lee Nunn: District Engineer
-Lt. Col. J. Perkins: Deputy District Engineer
United States Department of Energy
Alaska Power Administration
-Fredrick Chiei: Deputy Regional Representative
-Robert Cross: Administrator
-Donald Shira: Chief of Planning
Federal Energy Regulatory Commission, Division of Licensed Projects
-Ronald Corso: Director
-Paul Carrier: Engineer
-Donald Clarke: Staff Counsel
-Thomas Dewit:· Landscape Architect
-Quentin Edson: Chief~ Environmental Analysis Branch
Julian Flint: Supervisor, Engineering Project Analysis Branch
-Peter Foote: Fishery Biologist
-Donald Giampaoli: Department Director
-Mark Robinson: Environmental Biologist
-Dean Shumway: Chief, Conservation Section
-Gerald Wilson: Chief, Project Analysis
United States Department of the Interior
Bureau of Land Management
-Mike Brown: Historian
-Louis Carufel: Fisheries Biologist
-Art Hosterman: Chief, Branch of Biological Resources
-Ray Leicht: Archeologist
-Steve Lesko sky: Environmental Planner
-John Rego: Geologist
-Gary Seitz: Environmental Coordinator
Bureau of Mines
-Michael Brown: Chemist
-Bob Ward: Chief, Environmental Planning Staff
Fish and Wildlife Service
-Dale Arhart: Staff Biologist
Heritage Conservation and Recreation Service
-Janet McCabe: Regional Director
-Charles McKinney: Consulting· Archeologist
-Gail Russell: Interagency Services Division
-William We1ch: Supervising Outdoor Recreation Planner
-Larry Wright: Review Section Chief, Federal Projects -
;
,?'
/""'>.
I
I )
r
I '{~
r
,.....
!
I
National Park Service
-Brailey Breedlove: Landscape Architect
John Cook: Regional Director
Gail Russell: Staff, Interagency Service Division
Carl Stoddard: Park Ranger
Howard Wagner: Associate Director of Professional Services
United States Environmental Protection Agency
Envi ronmenta 1 Impact Statement Review Section
-Elizabeth Corbyn: Chief, Environmental Evaluation Branch
STATE AGENCIES
Alaska Department of Commerce and Economic Development
-Charles Webber: Commissioner
Alaska Power Authority
-Bruce Bedard: Inspector, Native Liaison
Division of Energy and Power Development
-Heinz Noonan: Economist
Alaska Department of Community and Regional Affairs
-Lee McAnerney: Commissioner
Alaska Department of Environmental Conservation
-Robert Flint: Region II Program Coordinator
-David Sturdevant: Management and Techni ca 1 Assistant Ecologist
-Dan Wilkerson: Special Projects Planner
Alaska Department of Fish and Game
Division of Sport Fisheries
-Michael Mills: Senior Fisheries Biometrician III
-Thomas Trent: Regional Supervisor, Susitna Aquatic Studies Coordinator,
Vice-Chairman of Susitna Steering Committee
Alaska Department of Natural Resources
-Robert LeResche: Commissioner
Division of Forest·Land and Water
-Mary Lou Harle: Water Management Officer
Division of Lands
-MichJ:l Franger: Special Projects Officer
Divisic~ of Parks
-Chip Dennerlein: Director
-Jack Wiles: Chief
-William Hanable: State Preservation Officer
-Doug Reger: State Archeologist
-Robert Shaw: State Historic Preservation Officer
Division of Research and Development
-Linda Arndt: Land Management Officer
-Al Carson: Deputy Director
Office of the Governor
Division of Policy Development and Planning
-Frances Ulmer: Director
University of Alaska
Arctic Environmental Information and Data Center
-William Wilson: Fisheries Biologist
OTHER INSTITUTIONS. ORGANIZATIONS AND INDIVIDUALS
Institutions and Organizations
Cook Inlet Region~ Incorporated
-Lynda Hays: Shareholder and Community Relations Coordinator
-Robert Rude: Senior Vice-President
Fairbanks Environmental Center
-Jeff Weltzin: Energy Coordinator
Land Field Services~ Incorporated
-P. J. Sullivan: Representative
Susitna Power Now
-E. Dischner: Executive Director
Individuals
-Glenn Bacon: Consulting Archeologist
A I
r :
Y;
Report on Socioeconomic Impacts
FEDERAL AGENCIES
United States Department of Agriculture
Economics~ Statistics, and Cooperative Services
-Paul Fuglestad: Agricultural Economist~ Natural Resource Economics
Division
Farmers Home Administration
-Delon Brown: Chief Researcher
Soil Conservation Service
-John 0' Neil: Coordinator
-Sterling Powell: Physical Engineer, Water Resource Specialist
United States Department of Defense
Army Corps of Engineers, Alaska District
-Col. Lee Nunn: District Engineer
-Lt. Col. J. Perkins: Deputy District Engineer
Army Corps of Engineers, Portland District
-Ruth Love: Sociologist
United States Department of Education
-Lee Hays: Facilities Planner
United States Department of Energy
Alaska Power Administration
-Fredrick Chiei: Deputy Regional Representative
-Robert Cross: Administrator
-Donald Shira: Chief of Planning
Federal Energy Regulatory Commission, Division of Licensed Projects
-Ronald Corso: Director
-Paul Carrier: Engineer
-Donald Clarke: Staff Counsel
-Thomas Dewit: Landscape Architect
-Quentin Edson: Chief, Environmental Analysis Branch
-Julian Flint: Supervisor, Engineering Project Analysis Branch
-Peter Foote: Fishery Biologist
-Donald Giampaoli: Department Director
-Mark Robinson: Environmental Biologist
-Dean Shumway: Chief, Conservation Section
-Gerald Wilson: Chief, Project Analysis
United States Department of Housing and Urban Oevel opment
-E. Robinson: Area Economist
United States Department of the Interior
Bureau of Land Management
-Louis Carufel: Fisheries Biologist
-Gary Henn i gh: Socioeconomic Speci a 1 i st
-Art Hosterman: Chief, Branch of Biological Resources
-John Rego: Geologist
-Gary Seitz: Environmental Coordinator
-Charles Smythe: Socioeconomics Specialist
Bureau of Mines
-Bob Ward: Chief, Environmental Planning Staff
Fish and Wildlife Service
-Bruce Apple: Fisheries Biologist
~ Dale Arhart: Staff Biologist
Geological Survey
-Robert Lamke: Chief. Hydrology Section
National Park Service
-Brailey Breedlove: Landscape Architect
-Joanne Gidlund: Public Affairs
United States Department of Transportation
Federal Railroad Administration, The Alaska Railroad
-Fred Hoefler: Traffic Officer
United States Environmental Protection Agency
Envi ronmenta 1 Impact Statement Review Section
-Elizabeth Corbyn: Chief, Environmental Evaluation Branch
STATE AGENCIES
A 1 ask a Department of Commerce and Economic Deve 1 opment
-Charles Webber: Commissioner
A1 ask a Power Authority
-Bruce Bedard: Inspector, Native Liaison
-Nancy Blunck: Coordinator
Divfsi on of Energy and Power Development
-Heinz Noonan: Economist
-David Reume: Economist
Alaska Department of Community and Regional Affairs
-Lee McAnerney: Commissioner
-Edward Busch: Senior P 1 anner
-Lemar Cotton: Planner II I
-Sylvia Spearon: Assistant Planner
-Richard Spitler: Planner
-Mark Stephens: Planner
Alaska Department of Environmental Conservation
-Jim Allen: Sanitarian
-Robert Flint: Region II Program Coordinator
-Rob.ert Martin: Regional Supervisor
-D~n Wilkerson: Special Projects Planner
-Steve Zrake: Environmental Field Officer
A 1 ask a Department of Fish and Game
Division of Commercial Fisheries
-Dennis Haanpaa: Assistant Regional Supervisor
Division of Game
Gregory Bos: Game Bi ol ogi st IV
-Sterling Eide: Regional Supervisor
-Lee Miller: Fish and Game Technician V
-Sterling Miller: Game Biologist III
-Jerome Sexton: Game Bi o 1 ogi st I I
-Dan Timm: Game Biologist III~ Chief Waterfowl
·""' 'i
,-
1
Division of Sport Fisheries
-Christopher Estes: Fishery Biologist III~ Susitna Aquatic Studies
-Larry Heckart: Fishery Biologist IV
... Michael Mills: Senior Fisheries Biometrician III
-Thomas Trent: Regional Supervisor, Susitna Aquatic Studies Coordinator.
Vice-Chairman of Susitna Steering Committee
Subsistence Division
-Ronald Stanek: Resource Specialist II
Alaska Department of Labor
Administrative Services
-Neil Fried: Labor Economist
-Greg Huff: Labor Economist
Division of Research and Analysis
-Chuck Caldwell: Chief
-Rod Brown: Supervisor of Research, Administration Services
-Cal Dauel: Labor Economist
-Neil Fried: Labor Economist
-Steve Harrison: Labor Economist
-Chris Miller: Labor Economist
-Sally Sadler: Labor Economist
-Dave Swanson: State Demographer
-James Wi 1 son: Labor Econorni st
Alaska Department of Natural Resources
-Robert LeResche: Commissioner
Division of Lands
-Mi~hael Franger: Special Projects Officer
-Robert Loeffler: Associat~ Lands Planner
Division of Parks
-Jack Wiles: Chief
Division of Pipeline Surveillance
-Elstun Lauesen: Socioeconomic Officer
Division of Research and Development
-Linda Arndt: Land Management Officer
-Al Carson: Deputy Director
-Carol Larsen: Public Information Officer
-Robert Loeffler: Associate Planner
-Steve Reeves: Chief, Land and Resources Planning Section
Alaska Department of Revenue
-Linda Lockridge: Records and Licensing Supervisor, Fish and Game Licensing
Division
-Hazel N.owlin: Administrative Assistant, Administration Services
-Wi 11 i am Yankee: Economist II
Alaska Department of Public Safety
Division of Public Safety
-Michael Dekreon, State Trooper
-Lt. Rhodes: State Trooper, Deputy Commander Detachment B
Division of Fire Protection
-Dave Taylor: Fire Protection Engineer
Division of Fish and Wildlife Protection
-Co1. Robert Stickles: Director
-Wayne Fleek: ·Region II I Commander
-Ms. Lobb: Clerk
-Lt. Rod Mills: Administrative Officer
-Lt. Col. Tetzlaff: Deputy Director
Alaska Department of Transportation
-Jay Bergstrand: Transportation Planner IV
Cathy Derickson: Transportation Planner
Reed Gibby: Transportation Planner
William Humphrey: Transportation Planner I
Richard Quiroz: District Environmental Coordinator
Eugene Weiler: Traffic Data Supervisor
Alaska State Housing Authority
-Wi 11 i am Foster: Admi ni strat ive Officer
Glennallen State Trooper Post
-Robert Cockrell: 1st Sergeant
House Power Alternatives Study Committee
-Hugh Malone: Committee Co-Chairman, District 13
Office of the Governor
Division of Policy Development and Planning
-Frances Ulmer: Director
University of Alaska
-Lydia Selkreg: Professor of Resource Economics and Planning
Arctic Environmental Information and Data Center
-Barbara Sokolov: Senior Research Analyst, Library Science
-William Wilson: Fisheries Biologist
Institute of Social and Economic Research
-Lee Gorsuch: Director
-Scvtt Goldsmith: Assistant Professor of Economics
-Lee Huskey: Associ ate Professor of Economics
Urban Observatory ,
-Richard Ender: Assistant Professor of Public Administration
LOCAL AGENCIES
City of Glennallen
-Sheldon Spector: Magistrate
City of Houston, Alaska
-Elsie 0 1 Brien: City Clerk
City of Palmer
-David Sou1ak: City Manager
City of wa::. I 11 a
-Earling Nelson: City Clerk
Copper River School District
-Dr. Krinke: Superintendent
Fairbanks North Star Borough
-Philip Berrian: Planning Director
Community Information Center
-Karen Fox: Research Analyst
1!1!1111
I
-
~' I
I
,i
,.,
'
-
r
I
r
(""'
I
Matanuska-Susitna Borough
Land Management Department
-Steve Van Sant: Borough Assessor, Division of Land Assessment/Director of
Land Management
Planning Department, Borough Office
-Rick Feller: Planner
-Claud Oxford: Engineer
-Vern Roberts: Finance Director
-Rodney Schull ing: Planning Director
-Alan Tesche: In-house Authority
-Lee Wyatt: Acting Borough Manager, Planning Director
Schoo 1 Di strict
-Mr. Monty Hotchkiss: Business Manager
-Kenneth Kramer: Superintendent
Municipality of Anchorage
-Charles Becker: Economic Development Director
-Shawn Hemme: Assist ant P 1 anner
-Michael Meehan: Director of Planning
-Bruce Silva: Demographer
-Barbara Withers: Regional Economist
Valdez Police Department
-Police Officer
OTHER. INSTITUTIONS, ORGANIZATIONS AND IND_IVIDUALS
Institutions and Organizations
Ahtna, Inc.
-Lee Adler: Director
A 1 ask a Ho spit a 1
-Head Nurse
Alaska Miners• Associati.on
Battelle Pacific Northwest Laboratories, Richland, Washington
Jeff King: Senior Research Engineer
-Michael Scott: Senior Research Engineer
-Ward Swift: Economist
Ben Marsh and Associates
-Nancy Cole: Assistant Property Manager
Chickaloon Village
-Jess Landsman: President
Cornmun i ty Council Center Federation of Corrmun ity Schoo 1 s
-t>1ary Amouak: Representative
-Margaret Wolfe: Representative
Cook Inlet Aquaculture Association
-Floyd Heimback: Director
-Thomas Mears: Biologist
Cook Inlet Region, Incorporated
-Agnes Brown: Executive
-Lynda Hays: Shareholder and Conmunity Re 1 at ions Coordinator
-Robert Rude: Senior Vice-President
-Marge Sargerser: Land Manager
-John Youngblood: Executive Director
Copper River Housing Authority
-Thea $melcher: Housing Director
Copper River Native Association
-Billy Peters: Health Director
Copper Va 11 ey Electric Association
-Daniel Tegeler: Office Manager
Copper Valley Views
-Reporter
Darbyshire and Associates
- Ralph Darbyshire: President
Doyon Corporation
-Doug Williams: Land Planner
Fairbanks Borough Community Information Center
-Karen Fox: Research Analyst
Fairbanks Chamber of Commerce
-Robert Dempsey: Chairman, Economic and Development Committee
Fairbanks Environmental Center
-Jeff Weltzin: Energy Coordinator
Fairbanks Town and Village Association for Development, Inc.
-Art Patterson: Planner
Fairbanks Visitor and Convention Bureau
-Karla Zervos: Executive Director
Frank Moo1in and Associates, Incorporated
-Mike Finnegan: Project Control Manager
Guide License Review Board
High Lake Lodge
-John Wilson: Resident Manager
Ho 1 mes and Narver
-Karl Hansen: Project Engineer
-James Pederson: Susitna Project Manager
Insurance Service Organization, San Fransisco, California
-Gary Morse: Customer Service Representative
Keual Vi 11 age
-James Shoalwolfer: President·
Knikatnu Incorporated
-Paul Theadore: Chief
Matanuska £1 ectri c Assocati on, Incorporated
-Bud Goodyear: Pl1bl ic Information Officer
-Ken Ritchey: Manager, Engineering Services
Matanuska Telephone Association
-Graham Ro 1 stad: Chief Engineer
-Donald Taylor: Traffic and Equipment Engineer
Ninilchik Native Association, Incorporated
-Arno 1 d Orhdhoff: Chief
Ninilchik Village
-Arnold Orhdhoff: President
Norsk Hydro, Sweden
-Iver Hagen: Public Relations
Northwest Alaskan Pipeline Company
-Susan Fisson: Director, Socioeconomic Analysis
-Virginia Manna: Research Analyst
Overall Economic Development Program, Incorporated
-Russell Cotton: Project Development Coordinator
-Dona 1 d Lyon: Executive Director
-
~I
-.
f
-I
-i
-
-
Pa 1 mer Ch a'Tlber of Commerce
P a 1 mer F i re H a 11
-Daniel Contini: Fire Chief
Palmer Valley Hospital
-Valerie Blakeman·: Administrative Secretary
-Ann Demmings: Nurse
-Rae-Ann Hickling: Consultant
. Public Power Supply System, Richland, Washington
-Alice Lee: Coordinator
Puget Sound Power and Light Company
-Terry Galbraith: Public Relations Officer
Quebec Hydro Center, Quebec, Ontario
-Mr. Savignac: Counsel
R. W. Beck and Associates. Seattle, Washington
-Richard Flemming: Principal Scientist
-Ron Melnifokk: Socioeconomic Coordinator
Sa 1 amatoff Native Association, Incorporated
-Andy Johnson: President
Seldovia Native Association, Incorporated
-James Segura: Chief
Stephen Braund and Associates
-Stephen Braund: President
Susitna Power Now
-E. Dischner: Executive Director
Trapper Creek Community Council
-David Porter: Member
-Gail Robinson: Member
Tri-Va11ey Realty
-Lois Dow: Associate
Tyonek Native Corporation
-Agnes Brown: President
-Nurse
Valdez Community Hospital
-Nurse
Va 1 dez Vanguard
-Reporter
Yukon Wildlife Branch
-Ralph Archibald: Biologist
Individuals
-Harold Larson: Agent for Alaska Railroad at Gold Creek, Trapper
-Bradford Tuck: Economic Consultant ·
-Wi 11 i am Workman: Socioeconomic Consultant
Report on Recreational Resources
FEDERAL AGENCIES
United States Department of Agriculture
Forest Service~ Institute of Northern Forestry
-James Tellerico: Landscape Architect
United States Department of Commerce
National Marine Fisheries Service
~ Bradley Smith: Fishery Biologist
United States Department of Defense
Army Corps of Engineers, Alaska District
-Loran Baxter: Civil Engineer
-Col. Lee Nunn: District Engineer
-Lt. Col. J. Perkins: Deputy District Engineer
United States Department of Energy
A 1 ask a Power Admi ni strati on
·Fredrick Chiei: Deputy Regional Representative
-Robert Cross: Administrator
-Donald Shira: Chief of Planning ~
Federal Energy Regulatory Commission, Division of Licensed Projects
-Ronald Corso: Director
-Paul Carrier: Engineer
-Donald Clarke: Staff Counsel
-Thomas Dewit: Landscape Architect
-Quentin Edson: Chief, Environmental Analysis Branch
-Julian Flint: Supervisor, Engineering Project Analysis Branch
-Peter Foote: Fishery Biologist
-Donald Giampaoli: Department Director
-Mark Robinson: Environmental Biologist
-Dean Shumway: Chief, Conservation Section
-Gerald Wilson: -Chief, Project Analysis
United States Department of Housing and Urban Development
-Debra Pevlear: Neighbor Volunteer and Consumer Protection Official
United States Department of the Interior
Bureau of Land Management
-Lee Barkow: Planner, Easement Identification Branch
-Patrick Beckley: Chief, Branch of Lands and Minerals
-Stanley Bronczyk: Chief, Easement Identification Branch
-Louis Carufel: Fisheries Biologist
-William Gabriell: Leader, Special Studies Group
-Art Hosterman: Chief~ Branch of Biological Resources
-Peter Jerome: Landscape Architect
-John Rego: Geologist
-Gary Seitz: Environmental Coordinator
-
'~
r
-J.
-
-i
-Dick Tindall: Anchorage District Manager
~Richard Tobin: Recreationa1 Planner
Bureau of Mines
-Michael Brown: Chemist
-Bob Ward: Chief, Environmental Planning Staff
Fish and Wildlife Service
-Bruce Apple: Fisheries Biologist
-Dale Arhart: Staff Biologist
-Keith Baya: Assistant Director for the Environment
-Dona1d McKay: Wild1ife Biologist
-Gary Stackhouse: Fish and Wildlife Biologist, Federal Projects/Technicial
Assistance Coordinator
Geo 1 ogi ca 1 Survey
-Robert Lamke: Chief, Hydrology Section
Heritage Conservation and Recreation Service
-Janet McCabe: Regional Director
-Wi 11 i am We 1 ch: Supervising Outdoor Recreation Planner
-Larry Wright: Review Section Chief, Federal Projects
National Park Service .
-Brailey Breedlove: Landscape Architect
-Terry Carlstrom: Chief of Planning and Design
-Ross Cavenaugh: Fisheries Biologist
-John Cook: Regional Director
-Carl Stoddard: Park Ranger
-Howard Wagner: Associate Director of Professional Services
United States Environmental Protection Agency
Environmental Impact Statement Review Section
-Elizabeth Corbyn: Chief, Environmental Evaluation Branch
STATE AGENCIES
Alaska Department of Administration
Division of General Services and Supplies
-Bill Ower: Contracting Officer
Alaska Department of Commerce and Economic Deve 1 opment
-Charles Webber: Commissioner
Alaska Power Authority
-Bruce Bedard: Inspector, Native Liaison
Division of Energy and Power Deve 1 opment
-Heinz Noonan: Economist
Alaska Department of Community and Regional Affairs
-Lee McAnerney: Commissioner
Alaska Department of Environmental Conservation
-Ernst Mueller: Commissioner
-Robert Flint: Region II Program Coordinator
- R ikki Fowler: Eco 1 ogi st
-Robert Martin: Regi anal Supervisor
-David Sturdevant: Management and Technical Assistant Eco 1 ogi st
-Dan Wilkerson: Special Projects Planner
-Steve Zrake: Environmental Field Officer
A 1 ask. a Department of Fish and Game
Division of Game
-Dan Timm: Game Biologist III, Chief Waterfowl
Division of Habitat Protection
-Phil Brna: Habitat Biologist II
-Carl Yanagawa: Regional Supervisor
Division of Sport Fisheries
-Michael Mills: Senior Fisheries Biometrician III
-Thomas Trent: Regional Supervisor. Susitna Aquatic Studies Coordinator,
Vice-Chairman of Susitna Steering Committee
A 1 ask a Department of Natural Resources
-Robert LeResche: Commissioner
Division of Forest Land and Water
-Ted Smith: Director
-Mary Lou Harle: Water Management Officer
-Raymond Mann: Land Management Officer II
-Debbie Robertson: Land Management Officer II
Division of Geological and Geophysical Survey
-Roy Merritt: Geologist
Division of Lands
-Frank. Mielke: Chief
-Jim Fichione: Land Management Officer
-Michael Franger: Special Projects Officer
-Joe Joiner: Land Management Officer
Division of Minerals and Energy
-Glen Harrison: Director
Division of Parks
-Jack Wiles: Chief
-Ronald Crenshaw: State Park Planner
-Liza Holzapp1e: Park Planner
-Al Miner: Student Intern
-Doug Reger: State Archeologist
-Sandy Rabinowitz: Park Planner
-Robert Shaw: State Historic Preservation Officer
-Larry Snarsky: District Manager
-Vicky Sung: Park Planner
-Larry Wilde: District Manager
Division of Research and Development
-Linda Arndt: Land Management Officer
-Wi 11 i am Beatty: Planning Supervisor, Land Resources
-Christopher Beck: Planner III
-Al Carson: Deputy Director
-Randy Cowart: Planner V
-Ronald Swanson: Land Management Officer, Policy Research Land Entitlement
Unit
Division of Transportation and Public Facilities
-Joh-n Mi 11 er
Alaska Department of Public Safety
Division of Fish and Wildlife Protection
-Col. Robert Stickles: Director
-Wayne F1 eel<: Region I II Commander
-Lt. Rod Mills: Administrative Officer
-Lt. Col. Tetzlaff: Deputy Director
_j
_J
-
-
-
r
I
r
I
r
l
r
-
r
I"""
I
L
Alaska Department of Transportation
-Jay Bergstrand: Transportation Planner IV
-Cathy Derickson: Transportation Planner
-Reed Gibby: Transportation Planner
Office of the Governor
Division of Policy Development and Planning
-Frances Ulmer: Director
-David Allison: Policy and Planning Specialist
University of Alaska
Arctic Environmental Information and Data Center
-Chuck Evans: Research Associate, Wildlife Biologist
-William Wilson: Fisheries Biologist
LOCAL AGENCIES
City of Houston, Alaska
-Elsie O'Brien: City Clerk
City of Palmer
-David Soul ak: City Manager
Fairbanks North Star Borough
-Paula Twelker: Planner II
Matanuska-Susitna Borough
Borough Office
-Rick Feller: Planner
-Rodney Schulling: Planning Director
-Lee Wyatt: Acting Borough r~anager, Planning Director
~ OTHER INSTITUTIONS, ORGANIZATIONS AND INDIVIDUALS
r
r
r
I
I
l
Institutions and Organizations
Ahtna, Inc.
-Robert Goldberg: Attorney
-Douglas MacArthur: Special Projects D-irector
Chickaloon Village
-Jess Landsman: President
Cook Inlet Region, Incorporated
-Agnes Brown: Executive
-Lynda Hays: Shareholder and Community Relations Coordinator
-Robert Rude: Senior Vice-President
-John Youngblood: Executive Director
Fairbanks Environmental Center
-Jeff Weltzin: Energy Coordinator
Keual Village
-James Shoalwolfer: President
Knikatnu Incorporated
-Paul Theadore: Chief
Knik Cancers and Kayakers
-Bruce Stanford: Member
Land Field Services, Incorporated
-P. J. Sullivan: Representative
Ninilchik Native Association, Incorporated
-Arnold Orhdhoff: Chief
Ninilchik Village
-Arnold Orhdhoff: President
Norsk Hydro, Sweden
-Iver Hagen: Public Relations
Salamatoff Native Association, Incorporated
-Andy Johnson: President
Seldovia Native Association, Incorporated
-James Segura: Chief
Susitna Power Now
-E. Dischner: Executive Director
Tyonek Native Corporation
-Agnes Brown: President
Individuals
-Bob Brown: Owner of Bob's Service Unlimited
-
OII!!IJ
I
l
11!'11;
i
-
-
.,
.J
-
-
r
r
-!
I
I
r
!
1""1
! I
..... I I
Report on Aesthetic Resources
FEDERAL AGENCIES
United States Department of Agriculture
Soil Conservation Service
-Sterling Powell: Physical. Engineer, Water Resource Specialist
United States Department of Commerce
National Marine Fisheries Service
-Ronald Morris: Supervisor
-Bradley Smith: Fishery Biologist
United States Department of Defense
Army Corps of Engineers, Alaska District
-Col. Lee Nunn: District Engineer
-Lt. Col. J. Perkins: Deputy District Engineer
United States Department of Energy
Alaska Power Administration
-Fredrick Chiei: Deputy Regional Representative
-Robert Cross: Administrator
• Donald Shira: Chief of Planning
Federal Energy Regulatory Commission, Division of Licensed Projects
-Ronald Corso: Director
-Paul Carrier: Engineer
-Donald Clarke: Staff Counsel
-Thomas Dewit: Landscape Architect
-Quentin Edson: Chief, Environmental Analysis Branch
-Julian Flint: Supervisor, Engineering Project Analysis.Branch
-Peter Foote: Fishery Biologist
-Donald Giampaoli: Department Director
-Mark Robinson: Envirtinmental Biologist
-Dean Shumway: Chief, Conservation Section
-Gerald Wilson: Chief, Project Analysis
United States Department of Housing and Urban Development
-Debra Pevlear: Neighbor Volunteer and Consumer Protection Official
United States Department of the Interior
Bureau of Land Management
Lee Barkow: Plann~r. Easement Identification Branch
-Patrick Beckley: Chief, Branch of Lands and Minerals
-Stanley Bronczyk: Chief, Easement Identification Branch
-Louis Carufel: Fisheries Biologist
-Art Hosterman: Chief, Branch of Biological Resources
-Peter Jerome: Landscape Architect
John Rego: Geologist
-Gary Seitz: Environmental Coordinator
-Richard Tobin: Recreational Planner
Bureau of Mines
-Bob Ward: Chief, Environmental Planning Staff
Fish and Wildlife Service
-Dale Arhart: Staff Biologist
National Park Service
-Brailey Breedlove: Landscape Architect
-Terry Carlstrom: Chief of Planning and Design
-Ross Cavenaugh: Fisheries Bi ol ogi st
-Howard Wagner: Associate Director of Professional Services
United States Environmental Protection Agency
Environmental Impact Statement Review Section
-Elizabeth. Corbyn: Chief~ Environmental Evaluation Branch
STATE AGENCIES
Alaska Department of Administration
Division of General Services and Supplies
-Bill Ower: Contracting Officer
Alaska Department of Commerce and Economic
-Charles Webber: Commissioner
Division of Energy and Power Development
-Heinz Noonan: Economist
Alaska Department of
-Lee McAnerney:
-Edward Busch:
-Lemar Cotton:
Community and Regional
Commissioner
Senior Planner
P1 anner Il I
Development
Affairs
Alaska Department of Environmental Conservation
-Ernst Mueller: Commissioner
Robert Flint: Region II Program Coordinator
Rikki Fowler: Eeologist
David Sturdevant: Management and Technical Assistant Ecologist
Dan Wilkerson: Special Projects Planner
Alaska Department of Fish and Game
Division of Habitat Protection
-Carl Yanagawa: Regional Supervisor
Division of Sport Fisheries
-Thomas Trent: Regional Supervisor~ Susitna Aquatic Studies Coordinator,
Vice-Chairman of Susitna Steering Committee
Alaska Department of Natural Resources
-John Katz: Cornmi ss i oner
-Robert LeResche: Commissioner
Division of Forest Land and Water
-Raymond Mann: Land Management Officer I I
-Debbie Robertson: Land Management Officer II
Division of Lands
-Michael Franger: Special Projects Officer
-Joe Joiner: Land Management Officer
Division of Parks
-Jack Wiles: Chief
-Ronald Crenshaw: State Park Planner
-Liza Holzapple: Park Planner
-I
-'
-
-· I I
-
....
Divi sian of Research and Development
-Linda Arndt: Land Management Officer
-William Beatty: Planning Supervisor, Land Resources
-Al Carson: Deputy Director
-Randy Cowart: Planner V
-Ronald Swanson: Land Management Officer, Policy Research land Entitlement
Unit
Alaska Department of Public Safety
Division of Fish and Wildlife Protection
-Col. Robert Stickles: Director
-Wayne Fleek: Region I II Commander
-Lt. Rod Mills: Administrative Officer
Alaska Department of Transportation
-Jay Bergstrand: Transportation Planner IV
Office of the Governor
Division of Policy Development and Planning
-Frances Ulmer: Director
-David Allison: Policy and Planning Specialist
University of Alaska
Arctic Environmental Information and Data Center
-Chuck Evans: Research Associate, Wildlife Biologist
-William Wilson: ·Fisheries Biologist
LOCAL AGENCIES
City of Houston Alaska
-Elsie O'Brien: City Clerk
City of Palmer
-David Soulak: City Manager
Matanuska-Susitna Borough
Borough Office
-Rick Feller: Planner
-Claud Oxford: Engineer
-Rodney Schu11ing: Planning Director
-Lee Wyatt: Acting Borough Manager, Planning Director
r OTHER INSTITUTIONS, ORGANIZATIONS AND INDIVIDUALS
Inst ituti ens and Organizations
,.....,
I Ahtna, Inc.
-Robert Goldberg: Attorney
-Douglas MacArthur: Special Projects Director
Cook Inlet Region, Incorporated
-Lynda Hays: Shareholder and Community Relations Coordinator
-Robert Rude: Senior Vice-President
Fairbanks Environmental Center
-Jeff Weltzin: Energy Coordinator
Land Field Services, Incorporated
-P. J. Sullivan: Representative
Norsk Hydro, Sweden
-Iver Hagen: Public Relations
Susitna Power Now
-E. Dischner: Executive Di~ector
~
I
-
-
-
r
-I
-r
I
Report on Land Use
FEDERAL AGENCIES
United States Department of Agriculture
Economics~ Statistics~ and Cooperative Services
-Paul Fuglestad: Agricultural Economist, Natural Resource Economics
Division
Soil Conservation Service
-Sterling Powel1: Physical Engineer, Water Resource Specialist
United States Department of Defense
Air Force
-Major Fred Haas: Blair Lakes Range Officer, Deputy Director of Operations
and Training
Army Corps of Engineers, Alaska District
-Loran Baxter: Civil Engineer
-Jeanne Bradley: Constructfon Inspector
-Col. Lee Nunn: District Engineer
-Lt. Col. J. Perkins: Deputy District Engineer
United States Department of Energy
Alaska Power Administration
-Fredrick Chief: Deputy.Regional Representative
-Robert Cross: Administrator
-Donald Shira: Chief of Planning
Federal Energy Regulatory Commission, Division of Licensed Projects
-Ronald Corso: Director
-Paul Carrier: Engineer
-Donald Clarke: Staff Counsel
-Thomas Dewit; Landscape Architect
-Quentin Edson: Chief, Environmental Analysis Branch
-Julian Flint: Supervisor, Engineering Project Analysis Branch
-Peter Foote: Fishery Biologist
-Donald Giampaoli: Department Director
-Mark Robinson: Environmental Biologist
-Dean Shumway: Chief, Conservation Section
-Gerala Wilson: Chief, Project Analysis
United States Department of Housing and Urban Development
-Debra Pevlear: Neighbor Volunteer and Consumer Protection Official
United States Department of the Interior
Bureau of Land Management
-Lee Barkow: Planner, Easement Identification Branch
-Patrick Beckley: Chief, Branch of Lands and Minerals
-Stanley Bronczyk: Chief, Easement Identification Branch
-Mike Brown: Historian
-Louis Carufel: Fisheries Biologist
-William Gabriell: Leader, Special Studies Group
-Art Hosterman~ Chief~ Branch of Bi ol ogi cal Resources
-Steve Leskosky: Environmental Planner
-John Rego: Geologist
-Gary Seitz: Environmental Coordinator
-Tom Taylor: Cartographer, National Mapping Division
-Dick Tindall: Anchorage District Manager
Bureau of Mines
-Michael Brown: Chemist
-Bob Ward: Chief. Environmental Planning Staff
Fish and Wildlife Service
-Bruce Apple: Fisheries Biologist
-Dale Arhart: Staff Biologist
-Keith Baya: Assistant Director for the Environment
-Donald McKay: Wildlife Biologist
-Gary Stackhouse: Fish and Wildlife Biologist. Federal Projects/Technicial
Assistance Coordinator
Geological Survey
-Raymond George: Acting District Chief, Water Resources Division
-Robe-rt Lamke: Chief, Hydro 1 ogy Section
Heritage Conservation and Recreation Service
-Larry Wright: Review Section Chief. Federal Projects
National Park Service
-Brailey Breedlove: Landscape Architect
-Terry Carlstrom: Chief of Planning and Design
-Ross Cavenaugh: Fisheries Biologist
-Carl Stoddard: Park Ranger
-Howard Wagner: Associate Director of Professional Services
United States Environmental Protection Agency
Environmental Impact Statement Review Section
-Elizabeth Corbyn: Chief, Environmental Evaluation Branch
STATE AGENCIES
Alaska Department of Administration
Division of General Services and Supplies
-Bill Ower: Contracting Officer
Alaska Department of Commerce and Economic Development
-Charles Webber: Commissioner
Alaska Power Authority
-Bruce Bedard: Inspector, Native Liaison
Division of Energy and Power Development
-Heinz Noon an: Economist
Alaska Department of
-Lee McAnerney:
-Edward Busch:
-Lemar Cotton:
Community and Regional
Commissioner
Senior Planner
Planner II I
Affairs
Alaska Department of Environmental Conservation
-Ernst Mueller: Commissioner
-Robert Flint: Region II Program Coordinator
-Rikki Fowler: Ecologist
-Robert Martin: Regional Supervisor
-I
I
j
~I
-
I
. ·i
-.I
-
r-
'
r
r
l '
-' '
-David Sturdevant: Management and Technical Assistant Ecologist
-Dan Wilkerson: Special Projects Planner
-Steve Zrake: Environmental Field Officer
Alaska Department of Fish and Game
Division of Game
-Karl Schneider: Research Coordinator
Division of Habitat Protection
-Thomas Arminski: Regional Land Specialist
-Phil Brna: Habitat Biologist II
-Carl Yanagawa: Regional Supervisor
Division of Sport Fisheries
-Thomas Trent: Regional Supervisor, Susitna Aquatic Studies Coordinator,
Vice-Chairman of Susitna Steering Committee
Alaska Department of Natural Resources
-John Katz: Commissioner
-Robert LeResche: Commissioner
Division of Forest Land and Water
-Ted Smith: Director
-Mary Lou Harle: Water Management Officer
-Raymond Mann: Land Management Officer II
-Debbie Robertson: Land Management Officer II
Division of Lands
-Frank Mielke: Chief
-Dean Brown: Southcentral District Lands Officer
-Jim Fichione: Land Management Officer
-Michael Franger: Special Projects Officer
-Joe Joiner: Land Management Officer
Division of Minerals and Energy
-Glen Harrison: Director
Division cf Parks
-Jack Wiles: Chief
-Ronald Crenshaw: State Park Planner
-Liza Holzapple: Park Planner
-Al Miner: Student Intern
-Doug Reger: State Archeologist
-Robert Shaw: State Historic Preservation Officer
Division of Research and Development
-Linda Arndt: Land Management Officer
-Wi 11 i am Beatty: Planning Supervisor, Land Resources
-Christopher Beck: Planner III
-Al Carson: Deputy Director
-Randy Cowart: Planner V
-Dale Sterling: Historian
-Ronald Swanson:· Land Management Officer, Policy Research Land Entitlement
Unit
Division of Transportation and Public Facilities
-John Miller
Alaska Department of Public Safety
Division of Fish and Wildlife Protection
-Col. Robert Stickles: Director
-Wayne Fleek: Region I II Commander
-Lt. Rod Mills: Administrative Officer
-Lt. Col. Tetzlaff: Deputy Director
Alaska Department of Transportation
-Jay Bergstrand: Transportation Planner IV
-Cathy Derickson: Transportation Planner
-Reed Gibby: Transportation Planner
Office of the Governor
Division of Policy Development and Planning
-Frances Ulmer: Director
-David Allison: Policy and Planning Specialist
University of Alaska
Arctic Environmental Information and Data Center
-Chuck Evans: Research Associ ate, Wildlife Bi ol ogi st
-William Wilson: Fisheries Biologist
Geophysical Institute
-Ken Dean: Remote Sensing Geologist
-Ian Hutchison: Professor of Physics
Geology Department
-Steve Hardy: Geologist
Museum
-Robert Thorson: Geologist
LOCAL AGENCIES
City of Houston, Alaska
-Elsie O'Brien: City Clerk
City of Palmer
-David Soul ak: City Manager
City of Wasi 11 a
-Earling Nelson: City Clerk
Fairbanks North Star Borough
-Paula Twelker: Planner II
Matanuska-Susitna Borough
Borough Office
-Rick Feller: Planner
-Claud Oxford: Engineer
-Rodney Schull i ng: PT anni ng Director
-Lee Wyatt: Acting Borough Manager, Planning Director
School District
-Mr. Hotchkiss: Business Manager
-Kenneth Kramer: Superintendent
OTHER INSTITUTIONS, ORGANIZATIONS AND INDIVIDUALS
Institutions and Organizations
Ahtna, Inc.
-Lee Adler: Director
-Robert Goldberg: Attorney
-Douglas MacArthur: Special Projects Director
~
I
~
I
j
~ \ '
,....
I
i.
l '
I
,.,..
' !
-Chuck McMahon: Pilot~ Hunter, Trapper, Fisherman in Upper Susitna Basin
-Cleo McMahon: Pilot~ Hunter in Upper Susitna Basin
-Tom Mercer: President of Denali Wilderness Treks, Bush Pilot, Dog Musher
-James Moran: Pilot~ Partner in Tsusena Lake Lodge
-Mrs. Ken Oldham: Co-owner of High Lake Lodge, Guide, Bush Pilot, Author
-Sutch Potterville: Sportfish Biologist in Upper Susitna Basin
-Andy Runyon: Pilot~ Hunter
-Roberta Sheldon: Partner in Sheldon Air Service~ Talkeetna Resident
-Judy Simco: ·Hunter, Trapper
-Kathy Sullivan: Owner of Genet Expeditions
-Minnie Swanda: Widow of Master Guide, Talkeetna Resident
-Jake Tansy: Native Hunter and Trapper
.. Bob Toby: Game Biologist, Hunter
-Lee and Helen Tolefson: Subsistence Trappers/Hunters, Talkeetna Residents
-Mrs. Oscar Vogel: Hunter, Trapper, Stephan Lake Resident, Widow of Master
Guide
-Jeff Weltzin: Devil Canyon Backpacker
-Ed Wick: Talkeetna Resident
Chickaloon ViJ 1 age
-Jess Landsman: President
Cook Inlet Aquaculture Association
-Floyd Heimback: Director
Cook Inlet Region, Incorporated
-Agnes Brown: Executive
-Lynda Hays: Shareholder and Community Relations Coordinator
-Robert Rude: Senior Vice-President
-Marge Sargerser: Land Manager
-John Youngblood: Executive Director
Fairbanks Envi ronmenta 1 Center
-Jeff We1tzin: Energy Coordinator
Holmes and Narver
-James Pederson: Sus itna Project Manager
Keual Village
-James Shoalwolfer: President
Knikatnu Incorporated
-Paul Theadore: Chief
Mahay•s Riverboat Service
-William Carrera: Guide
Ninilchik Native Association, Incorporated
-Arnold Orhdhoff: Chief
Ninilchik Village
-Arnold Orhdhoff: President
Norsk Hydro, Sweden
-Iver Hagen: Public Relations
Northwest Alaskan Pipeline Company
-·Susan Fisson: Director, Socioeconomic Analysis
Palmer Valley Hospital
-Valerie Blakeman: Administrative Secretary
-Rae-Ann Hickling: Consultant
Sal amatoff Native Association, Incorporated
-Andy Johnson: President
Seldovia Native Association, Incorporated
-James Segura: Chief
Susitna Power Now
-E. Dischner: Executive Director
Tyonek Native Corporation
-Agnes Brown: President
Individua 1 s
-Warren Ballard: Game Biologist, Hunter
-Dennis Brown: President Akland Air Service
-Verna and Carrol Close: Owners of Talkeetna Roadhouse
-Mike Fisher: Pilot, Talkeetna Resident
-Jim and Vonnie Grimes: Pilots, Owners of Adventures Unlimited Lodge
-Pete Haggland: President of Alaska Central Air, Pilot
-Paul Hall and: Owner-Manager of Evergreen Lodge, Boater
Cliff Hudson: Owner/Pil at of Hudson • s Air Taxi. Ta 1 keetna Resident
-John Ireland: Alaskan Sourdough. Murder Lake Resident
-Dave Johnson: Manager, Oenal i State Park·
-Dorothy Jones: President of Talkeetna Historical Society~ Representative-
elect of Mat-Su Borough Assembly
-Frenchy Lamoureux: Hunter, Trapper, Wife and Mother of Big Game Guides
-Don Lee: Manager Stephan Lake Lodge, Pilot
-
1'111'11
-'
r
r
r
\ '
APPENDIX 8~1
FORMAL AGENCY COORDINATION CORRESPONDENCE
r
n l
r 1
I""':
) I -
rT
1.'
\' '
Al Carson
State of Alaska
UNITED STATES
DEPARTMENT OF THE INTERIOR
GEOLOGICAL SURVEY
Water Resources Division
733 W. Fourth Ave., Suite 400
Anchorage, Alaska 99501
July 27, 1981
Department of Natural Resources
323 E. Fourth Avenue
Anchorage, Alaska 99501
Dear Mr. Carson:
RECEIVED
.!UL 3 J 1981
ALASKA POW!::: .~.:..::-:-iOkiTY
I have reviewed the Draft Development Selection Report for the proposed
Susitna Hydroelectric Project as requested in the APA transmittal of
June 18, 1981. The review was limited to the evaluation process used
by Acres, the relative impacts of several alternative development plans
of Susttna hydroelectric resources, and the conclusion that the Watana-
Devil Canyon plan is the preferred basin alternative.
There were no problems involved in understanding the selection process
used by Acres and there were enough data and inform~tion presented to
compare the final candidate lalternative) plans. The relative impae:ts
of the candidates were presented in an understandable and credible manner.
Although enly a qualitative evaluation of impacts is presented (pending
reports of on-going studies}, a reasonable conclusion is that the Watana-
Deyil Canyon plan is the preferred candidate for Susitna hydroelectric
development.
\
cc: David 0. Wozniak, Project Engineer, APA, Anchorage, AK I
(
United States Departmept of the Interior
NATIONAL PARK SERVICE
IN REPLY REfER TO:
1201-03a
ALASKA STATE OFFICE
334 West Fifth Avenue, Suite 250
An.:horagc, Alaska 99501
AUG 5 1901
RECEIVED
/\UG ? 1981
N..ASKA POWER AUTHORITY
Mr. David D. Wozniak
Susitna Hydro Project Engineer
Alaska Power Authority
333 West 4th Avenue, Suite 31
Anchorage, AK 99501
Dear David:
In response to your request I have reviewed the Draft Devel-
opment Selection Report for the Susitna Project. Based upon
the information presented in the report, I would judge the
evaluation process to be satisfactory. However, I would not
want to recommend or otherwise comment on a preferred basin
alternative prior to the completion of ongoing studies which
will further quantify the anticipated environmental impacts.
I assume the final report will reflect a more precise com-
parison of environmental impacts for the dam sites under
consideration. ·
An additional item of interest which should perhaps be
included in the final report is a comparison of the expected
life of the project for each alternative dam site considering
the effect of silt accumulation in the reservoirs.
Thank you for the opportunity to review the report. The
above comments are my own and should not be interpreted as
representing the official position of the National Park
Service.
Sincerely,
J \\_ '. wL 1-ifcwJ {) Y) (_' ) If 'v\,_
Larry . Wright ·
Outdoo Recreation Planner
Save Energy and You Serve A me rica!
' i
~
'
~
L=;JHJ;
;i~:H~
~~;!
I
!"""'~.
r
.~;,.:..:;...~--,.~.,/ 1' b ~~~~...;,.nr. Ster 1 ng R. Os orne
r=r-=~~.:;::..,+r..,.-ttn1 ttd States Department of the
, eological Survey ~~~~Z4onservation Division
~~~~~~~-.0. Gox 2967
~rr-~~~--~orti3tirl, Oregon 972GB
Interior
September 4, 1981
P5700.11.87
T.1129
SusHna Hy·Jrce1ectric Project
Reoorts
Hr-::::.:~=-----ihis is in rcferznc2 to your lc-:ter dated A:Jc!.:st 11. ~-~e \·:ill be pleased
1:--1~~..,.,...,.--~o aC:J your office to 't~H: :::ailir:c list for 11 Rc.;t;-'crt".
ur Client) t:1-: ;_1askc 0c:·:er .t.utr.crit~/, reruire~ that \·.'e ur.cert~ke on 1-1'!~"""=---t-:...-~ H~:....-_;_;..,.._4·heir behalf both fcr:-:-.1 ar:J i:~~-:-GI'i·al cnordination •:Ji::.r· all fec..~cral and
1--!0....,_-----<~ta te aQ-=i·n::i ~s ti·:a:~ i 12;';;; ~ C:i \~c.cJc i ntE:res t in the: SL!S it! ta cro,i ~ct. This
~~=--_,f course is .:::i~c fJ. r~:r:•t)ir2ne:J~t a-:-the FERC: Lic2r:sin"' rrocr:ss. As part
1:--1~----...:.Jf this ;;recess ~''e 0re conrdinatinr; Hith yc-ur !·nct·,o~~:::·~e offio: throuah
l---rl'l7"f'~;::z:::;;;__-H: r •. K.c>~:srt D. LaP:l-.e ~ 1.·iL0 h:ts c. i rt:: ~·-.iy ~~c"i v~d ~nc: .c:J:-; ::~:nteu on v~ ri ous
docuffients as t~1cy· i 1il ve.-~1e~n rro.Juced.
1-1:-------Hy co:~y cf this letter I •::ill r'?r.t.:·~st r:r. :::avid ~~oz:-:i:!: of the Alaska
,..--------:.t· m:.;er Authority to add j!cur office to th.~ r;~ai1in~ list for ap:.:rcrriate
+=----~reject rt:ports anc nE~·;slcttc.rs.
r
! i
,..,
I i
!
I
JDL/jmh
xc: D. Wozniak (APA} ---
J. G. Harnock,__.......--
%y,
Jo~n D. Lawrence
Project i~«naqe) ..
Mr. Ronald 0. Skoog
Commissioner
._;;;··<.--~ • ~
' ., -·
RECEIVED
r !OV 1 3 1981
~ovemoer 9, 1961
P5700.06
Araska Dept. of Fish & Game
Sport Fish/Susitna Hydro
State of Alaska Department of Fish and Game
Juneau, Alaska 99801
Dear Mr. Skoog:
Susitna Hydroelectric Project
Development Selection Report
As you know, Acres .American Incorporated is under contract to the Alaska
Power Authority to conduct a feasibility study and prepare a Federal Energy
Regulatory Commission {FERC) 1 icense application for the Susitna Hydro-
electric Project. The scheduled date for submission of the app.lication is
in June of 1982.
Federal law and FERC regulations require that the reports supporting the
FERC application be prepared in consultation with Federal and State agen-
cies having managerial authority over certain project aspects. This coor-
dination must be documented in the license application.
A great deal of coordination has taken place at agency staff levels by dir-
ect participation in studies or oy participation in committees and task
groups. This input,. however, has been primarily by staff and may_ not nec-
essarily reflect the views of the agency. For this reason~ we are conduct-
ing a parallel formal coordination process by requesting agency comments on
'"key study outputs. The plan of study was the first document coordinated in
this manner. Over the next year, there will be several more. This parallel
process will affect the other coordination activities of the study.
At this time, we request that the Department of Fish and Game review the
attached Report, "Development Selection Report .. , particu1arly in the areas
impacting on the "fish and game resources.
ACRES AMERICAN INCORPORATED
Consu:;::~g Engineers
The Libo;-•!y Ban1< Building_ Main at Court
Sulfalo N~.-. York 1~202
;::"'-•--r p• --·~.c~ ·-,. .. _.-_...___._.-=-~-------------------
-
r
( 'I
-' ) i
n
i I
Geve1opment Se1ection Report -2 ~ovember 9, 1981
Your prompt attention to this matter will enable us to continue planning
the best possible develo~ent for all interests. A response within thirty
days of receipts waul d be greatly appreciated. Please send a copy of your
comments to:
Mr. Eric Yould, Executive Director
Alaska Power Authority
333 West 4th Avenue
Anchorage, Alaska 99501
JDL/MMG:jgk
cc: Eric Yould, Alaska Power Authority
Very truly yours,
Z&-~vn ~.-<VI d4/
.fohn D. Lawrence
Project Manager
Mr. Thomas Trent, Department of Fish & Game
ACRES AMERICAN INCORPORATED
..
..
WILLETT
WI TTl:
BERRY
HAYOEN
LAMB
LAWRENCE
SINCLAIR
VANOERBUFIGH
p ,......
.........,
CARLSON
F.FIET.Z
JEX
LOWFIEcY
SINGH
HUSTEAO
BOVE
CHASE
/
r -=?:~-.f
1 .,. 7"'\ · .... ,. I ! .
-· --
Mr. John Rego
Bureau of Land t1anagement
701-C Street
Anchorage, Alaska 99501
Dear Mr. Rego: .··•
November 9, 1981
P5700. 11.75
T.1258
Susitna Hydroelectric Project
Transmission Corridor Report
As you know:~~ Acres Amer~can, Incorpor-ated is under contract to the Al ask·a
Power Authority to conduct a feasibility study and prepare a Federal Energy
Regulatory Commission (FERC) license application for the Susitna Hydro-
electric Projecta The scheduled date for submission of the application is
in June of 1982.
Federal 1 aw and FERC regulations require that the reports supporting the
FERC application be prepared in consul tat ion with Federal and State agen-
cies having managerial authority over certain project aspects. This coor-
dination must be documented in the license application •.
A great deal of coordination has taken place at agency staff 1 evels by dir-
ect participation in studies or by participation in committees and task
groups. This input, however, has been primarily by staff and may not nec-
essarily reflect the views of the agency. For this reason, we are conduct-
ing a parallel formal coordination process, by requesting agency comments
on key study outputs. The plan of study was the first document coordinated
in this manner. Over the next year, there will be several more. This par-
allel process will affect the other coordination activities of the study.
At this time, we request that the Bureau of Land f"'!anagement review the
attached Report, "Transmission line Corridor Screening Closeout .Report",
particularly in the areas of aesthetics, land use, and land management.
ACRES AMERICAN INCORPORATED
... ·~ . ..1 • • ....... .
j •.. • '·
-.
J
' I ...
n
' I f i l. I
,.,...
I~ ,
f1
> I
\ I
' c I
n
, I
n
; i
\ i
!, I
i' I
..
Development Selection Report -2 November 9 ~ 1981
Your prompt attention to this matter will enable us to continue planning
the best possible development for all i·nterests. A response within thirty
days of receipts would be greatly appreciated. Please send a copy of your
comments to:
JUL/MMG:jgk
Mr. Eric Yould, Executive Director
Alaska Power Authority
333 West 4tn Avenue
Anchorage, Alaska 99501 ·
Very truly yours,
fiJ,1 ) oVI~ t/Lveb:
._4,AJ John 0. La'wrence
tT · ~reject Manager
cc: Eric Yould, Alaska Power Authority / ·.
ACRES AMERICAN INCORPORATED
,. .; -" ~
#
. WILLETT
WITTE
BEARY
HAYDEN
LAMB
LAWRENCE
SINCLAIR
f")-#'1\·· .. ~;-:a
;3\:. ;·j:.·~ i
~~::-~;
Mr. Keith Schreiner l
R
u
1
egional Director, Region 7
.S. Fish and Wildlife Serv:ice
011 E. Tudor Road
A nchorage~ Alaska 99503
November 9, 1981
P5700. 11.71
T.l268
Susitna Hydroelectric Project
Transmission Corridor Report
VANOERBURGH D ear Mr. Schreiner:
:(~
CARLSON
FRETZ
JEX
LOWREY
SINGH
HUSTEAD
BOVE
CHASE'
__./
->-:~~ _,.-
A s you know, Acres American, Incorporated is under contract to the Alaska
ower Authority to conduct a feasibility study and prepare a Federal Energy
egulatory Commission (FERC) license application for the Susitna Hydro-
lectric Project. The scheduled date for submission of the application is
n June of 1982.
p
R
e
i
F
F
c
d
ederal law and FERC regulations require that the reports supporting the
ERC application be prepared in consultation with Federal and State agen-
ies having managerial authority over certain project aspects. This coor-
ination must be documented in the license application.
A great deal of coordination has taken place at agency staff levels by dir-
ct participation in studies or by participatio.n in committees and task
roups. This input, however, has been primarily by staff and may not nec-
ssarily reflect the views of the agency. For this reason, we are conduct-
ng a parallel formal coordination process, by requesting agency comments
e
g
e
i
on key study outputs. The plan of study was the first document coordinated
in this manner. Over the next year, there will be several more. This par-
allel process will affect the other coordination activities of the study.
At this time, we request that the U.S. Fish and Wildlife Service review the
attached Report, "Transmission Line Corridor Screening Closeout Report",
particularly in the areas impacting on the fish and wildlife resources.
ACRES AMERICAN INCORPORATED
]. ,~'(: ~· ... J ; .. ':~-~[:: '._,
~ . I
' \
( ]'
n l I I ,
l i
~
I I ' ' ' I
""l'
I
n ·, I
: .1
n
t I
-i I
\ I l .
,..,.,
( !
' I
j I
{j
' I
i I
( i
;
Development Selection Report -2 November 9, 1981
. .
Your prompt attention to this matter will enable us to continue planning
the best possible development for all interests. A response within thirty
days of receipts would be greatly appreciated. Please send a copy of your
comments to:
JDL/NfviG:jgk
Mr. Eric Yould~ Executive Director·
Alaska Power Authority
333 West 4th Avenue
Anchorage, Alaska 99501
Very truly yours,
;Ct~ctf!fj J/;u..:lx
_..4AV John D. Lawrence
I'~ . Project Manager
cc:·Eric You1d, Alaska Power Authority(~-------
ACRES AMERICAN INCORPORATED
c·
r.. ·. :-~";::_,--;1:~11
~~
~------,
i I
' I I --~--.. -.211 I
t " " t I . :-. ; : ~ ~
. . ,.,-...... :
... , .~ ~.
-· ·-.. ------
Mr. Robert Shaw
State Historic Preservation Officer
Alaska Department of r~atural Resources
Division of Parks
619 Warehouse Avenue, Suite 210
Anchorage, Alaska 99501
Dear Nr. Shaw:
November 9, 1981
P5700·. 11.74
T.l263
Susitna Hydroelectric Project
Transmission Corridor Report
As you. know, Acres American, Incorporated is under contract to the Alaska
Power Authority to conduct a feasibility study and prepare a Federal Energy
Regulatory Commission (FERC) license application for the Susitna Hydro-
electric Project. The scheduled date for submission of the application is
in June of 1982.
Federal 1aw and FERC regulations require that the reports supporting the
FERC application be prepared in consultation with Federal and State agen-
cies having managerial authority over certain project aspects. This coor:...
dination must be documented in the license application.
A great deal of coordination has taken place at agency staff levels by dir-
ect participation in studies or by participation in committees and task
groups. This input, however, has been primarily by staff and may not nec-
essarily reflect the views of the agency. For this reason, we are conduct-
ing a parallel formal coordination process, by requesting agency comments
on key study outputs. The plan of study was the first document coordinated
in this manner. Over the next year, there will be several more. This par-
allel process will affect the other coordination activities of the study.
~
At this tirne, we request that the State Historic Preservation Officer review
the attached Report, 11 Transmission Line Corridor Screening Close.out Report 11 ,
part.icular1y in the areas impacting on cultural resources. ~
ACRES AMERICAN INCORPORATED
c ... :: J!: . .; ;::, .. ···': •. -
Ti;•, ' :: ·:, :·, ."·· :• ..
'J.;" ,. . ·~ • I '!.
fl.: •. ·.·
. .. ' .. ·,
: . ;_ "" :. : ::,: ·: -
______ fl!"·· -... : . .. I. -.• ~ • . • .. . '
-
:"""['
I i
(
( I -
r"""' .
~-
!
( !
Development Selection Report -2 November 9, 1981
Your prompt attention to this matter will enable us to continue planning·
the best possible development for all interests. A response within thirty
days of receipts waul d be greatly appreciated. Please send a copy of your·
comments to:
JDL/MMG:jgk
·Mr. Eric Yould, Executive Director·
Alaska Power Authority
333 \>lest 4th Avenue
Anchorage~ Alaska 99501
Very truly yours,
/Jnu!J.Iu; tfuctu
John D. lawrence
Project Manager
cc: Eric Yould, Alaska Power Authority ) ,L~
Mr. Alan Carson~ Alaska Department of Natural Resources/ ·
//
.·
ACRES AMERICAN INCORPORATED
...,
....!
.-"
...
WIL.L.ETT
WITTE
BERRY
HAYOEN
L.AMB
l.AWRENCE
SINCT...AIR
' . ----------
lA .
1"1.
1'1 ,,
U'
"
John Katz
aska Department of Natural Resources
uch M
neau~ Alaska 99811
November 9. 1!:181
P5700. 11.74
T.l260
Susitna Hydroelectric Project
Transmission Corridor Report
VANOERBURG!-l{ ar f-1r. Katz:
k
!'--
CARLSON
FRETZ
JEX
LOWREY
SINGH
HUSTEAO
aove
CHASE
--·/
/
/ _,.
~
-'?
ll
f"
.~:l ...
lfl
. I"" •
t-
,.· . u
e
you know~ Acres American~ Incorporated is under contract to the Alaska ·
wer Authority to conduct a feasibility study and prepare a Federal Energy
gul atory Commission (FERC) 1 icense application for the Susitna Hydro-
ectric Project. The scheduled date for submission of the application is
June of 1982.
deral law and FERC regulations require that the reports supporting the
RC application be prepared in consu1tation with Federal and State agen-
es having managerial authority over certain project aspects._ This coer-
nation must be documented in the license application.
.... ~.
great deal of coordination has taken place at agency staff levels by dir-
t participation in studies or by participation in committees and task
oups. This input, however~ has been primarily by staff and may not nec-
sarily reflect the views of the agency. For this reason, we are conduct-
g a parallel formal coordination process, by requesting agency comments
::l
t!~ ;r
II key study outputs. The plan of study was the first document coordinated
in this manner. Over the next year, there will be several more. This par-
allel process will affect the other coordination activities of the study.
At this time, we request that the Department of Natural Resources review the
~ i
....
i
attached Report, "Transmission Line Corridor Screening Closeout Reportn, -
particularly in the areas of water quality and use, aesthetics and land
use~
ACRES AMERICAN INCORPORATED .
;:.;: -.f:· . ' ' : ~ .. ; .
. ··-': · ... ·._-· ... · . • :. • ·. . I
-· '
,411!'!1, .,
,-
-
-
<""'r>
i
i
...., ,,
I
£':
t :"'--"
!:.' !
n ~~ I
• I
I. ' ~
r-1': r ,
\'!
,.
i I
L I'
ti'
i. I
. ,
Development Selection Report - 2
November 9, 1981
Your prompt attention to this matter will enable us to continue planning
the best possible development for all interests. A response within thirty
days of receipts would be greatly appreciated. Please send a copy of your
comments to:
JDL/f'.1HG: j gk
Mr. Eric Yould, Executive Director
Alaska Power Authority
333 West 4th Avenue
Anchorage, Alaska 99501
Very truly yours,
J;.,-.,utft~t t/ud: ·
.Jj.fft/ John 0. Lawrence
1 Project Manager
cc: Eric Yould, Alaska Power Authority :-J /:.
Mr. A 1 an Carson, A 1 ask a Department of Natura 1 Resource/ ,:::z...:.
ACRES AMERICAN INCORPORATED
..
..
Wtl-I.ETT
WlTTE
BERRY
HAYDEN
l.AMB
LAWRENCE
SINCLAIR
VANDERBURGH
_...,
~ r'--··
CARLSON
FRETZ
JEx·
LOWREY
SINGH
HUSTEAO
BO'«E
CHASE
/ •' .-:-7. d~· .r.
Mr. John E. Cook
Regional Director
November g_ 1981
P5700.11.91
T .1261
Alaska Office ·"""'
National Park Service
540 West Fifth Avenue
Anchorage, Alaska 99501 ·~
Susitna Hydroelectric Project
Transmission Corridor Report ,-,
Dear Mr. Cook:
As you know, Acres American, Incorporated is under contract to the Alaska
Pm.,er Authority to conduct a feasibility study and prepare a Feder a 1 Energy
Regulatory Commission (FERC) license application for the Susitna Hydro-· · ~
electric Project. The scheduled date for submission of the application is
in June of 1982. ~
-· Federal law and FERC regulations require that the reports supporting the
FERC application he prepared in consultation with Federal and State agen-
cies having managerial authority over certain project aspects. This coor-
dination must be documented in the license application.
A great deal of coordination has taken place at agency staff levels by dir-
ect participation in studies or by participation in committees and task
groups. This input, however, has been primarily by staff and may not nec-
essarily reflect the views of the agency. For this reason, we are conduct-
ing a parallel formal coordination process, by requesting agency comments
on key study outputs. The plan of study was the first document coordinated
in this manner. Over the next year, there will be several more. This par-
allel process will affect the other coordination activities of the study.
At this time, we request that the National Park Service review the attached
Report, 11 Transmission Line Corridor Screening Closeout Report 11 ; particularly
in the areas of history and archeology, and recreation. ~1
ACRES AMERICAN INCORPORATED
,.
-'·
r
I
0
,...., ,,
)'
\_,_
Development Selection Report - 2 November 9, 1981
Your prompt attention to this matter will enable us to continue planning
the best possible development for all interests. A response within thirty
days of receipts would be greatly appreciated. Please send a copy of your
comments to: ·
f.1r. Eric. Yould, Executive Director
Alaska Power Authority
333 West 4th Avenue
Anchorage, Alaska 99501
JO(.JMMG:'j gk
Very truly yours~
;OoJO Vlu;-f/u.LTv
John ·o. Lawrence
Project Manager
cc:. Eric Yould, Alaska Power Authority ~
Mr. Larry Wright, National Park Service 1 · ·
ACRES AMERICAN INCORPORATED
...
,,
WILl.ETT
WITTE
BERRY
HAYDEN
LAMB
LAWR.ENCE
SINCLAIR
VANDER BURGH
..... ..-.
'-' r--
CARL:.SON
FRETZ
JEX
LOWREY
SINGH
HUSTEAD
seve
CHASE
~~
Region a 1 Administrator
Region X
U.S. Environmental Protection Agency
1200 South Avenue
Seattle~ WA 98101
Dear Sirs:
November 9~ 1981
P5700. 11. 91
T.l267
Susitna Hydroelectric Project
Transmission Corridor Report.
As you know, Acres ftrneri can~ Incorporated is under contract to the Alaska
-
-.
J
Power Authority to conduct a feasibility study and prepare a Feder a 1 Energy -'t
Regulatory Commission (FERC) license application for the Susitna Hydro-
electric Project. The scheduled date for submission of the application is
in June of 1982.
Federal law and FERC regulations require that the reports supporting the
FERC application be prepared in consultation with Federal and State agen-
cies having managerial authority over certain project aspects. This coor-
dination must be documented in the license application.
A great deal of coordination has taken place at agency staff levels· by dir-
ect participation in studies or by participation in committees and task
groups. This input, however, has been primarily by staff and may not nec-
essarily reflect the views of the agency. For this reason, we are conduct-
ing a parallel formal coordination process, by requesting agency comments
on key study outputs. The plan of study was the first document coordinated
in this manner. Over the next year, there wi 11 be several more. This par-
allel process will affect the other coordination activities of the study.
At this time, we request that the Environmental Protection Agency review the ~
attached Report, 11 Transmission Line Corridor Screening Closeout Report 11 ,
particularly in the areas impacting on land, water, or air quality. -'
ACRES AMERICAN fNCORPORATED
T·· ... :
-
-\
i. ,,
I
I , .
Development Selection Report - 2
November 9 ~ 1981
Your prompt attention to this matter will enable us to continue planning
the best possible development for all interests. A response within thirty
_days of receipts would be greatly appreciated. Please send a.copy of your
comments to:
JDL/MMG:jgk
Mr. Eric Youl d, Executive Director
Alaska Pow~r Authority ·
333 West 4th Avenue
Anchorage, Alaska 99501
Very truly yours,
}J.e> IJ'ffiAj f!/tA/if~
John 0. Lawrence
Project Manager
cc: Eric Yould, Alaska Po~er Authority . /~
Judy Swartz, U.S. Env1ronmental Protect1on Agency_/-
ACRES AMERICAN INCORPORATED
WILLETT
WITTE
BEARY
HAYDEN
LAMB
LAWRENCE
SINCLAIR
VANOE~SURGH
rJ
1----,
CARLSON
FRET%
JEX
LOWREY
SINGH
HUSTEAO
aove
CHASE
_/
'-' __./;/ /_
-·
-
November 9. JqRl -,
Mr. Lee McAnerney
State Archeologist
Department of Regional Affa:irs
Pouch B
Juneau, Alaska 99811
P5700.ll.92
T.1262
Susitna Hydroelectric Project ~,
Transmission Corridor Report
Dear f.1r. McAnerney: -~
As you know, Acres American, Incorporated is under contract to the Alaska
Power Authority to conduct a feasibility study and prepare a Federal Energy ~
Regulatory Commission {FERC) license application for the Susitna Hydro-
electric Project. The scheduled date for submission of the application is
in June of 1982.
federal law and FERC regulations require that the reports supporting the
FERC application be prepared in consultation with Federal and State agen-~~
cies having managerial authority over certain project aspects. This coor-
dination must be doct.rnented in the license application. -A great deal of coordination has taken place at agency staff levels by dir-
ect participation in studies or by participation in committees and task
groups. This input, however, has been primarily by staff and may not nec-
essarily reflect the views of the agency. For this reason, we are conduct-~
ing a parallel formal coordination process, by requesting agency comments
on key study outputs. The plan of study was the first document coordinated
in this manner. Over the next year, there will be several more. This par-~
allel process will affect the other coordination activities of the study.
At this time, we request that the Department of Regional Affairs review the ""'"'1;
attached Report, 11 Tr ansmiss ion Line Corridor Screening Closeout Report",
particularly in the area of history and archeology.
~I
ACRES AMERfCAN INCORPORATED
. "
-!
I
r
I
c.
! ;
Development Selection Report - 2 November 9, 1981
Your prompt attention to this matter will enable us to continue planning
the best possible development for all interests. A response within thirty
days of receipts would be greatly appreciated. ·Please send a copy of your
comments to:
JDL/HMG :j gk
Mr. Eric Yould, Executive Director
Alaska Power·Authority
333 West 4th Avenue
Anchorage, ·Alaska 99501
Very truly yours,
J[J~1 c'fiLt t!iu~
John D. Lawrence
Project Manager
1""' cc: Eric Yould, Alaska Power Authority c../:.__--;--
ACRES AMERICAN INCORPORATED
,
I
'
!
:
;
·.
.
'
:
,
'
Wtt.L.ETT
WITTE
BERRY
HAYDEN
l..AMB
I..AWRE;NCE
SINCLAIR
. I
I , "'':. '·: :1 ~~~
J
I
!
I
. -----.,
r. Rooert McVey
irector, Alaska Region
ational Marine Fisheries
OAA
.0. Box 1668
uneau, Alaska 99802
Service
November Q_ 1981
P5700.11.92
1.1266
i
' j
VANDERSURGH
Susitna Hydroelectric Project
Transmission Corridor Report
-~ "l -..1 ..__.
CARLSON
FRETZ
JEX
LOWREY
SINGH
HUSTEiAD
BOVE
CHASE -
~ /
:;~ . .-:/"' £.r
('
!
i
ear Mr. ·Me Vey:
s you know, Acres ftmerican, Incorporated is under contract to the Alaska
ower Authority to conduct a feasibility study and prepare a Federal Energy
egul atory Commission (FERC) license application for the Susitna Hydro-
lectric Project. The scheduled date for submission of the application is
n June of 1982.
ederal law and FERC regulations require that the reports supporting the
ERC application be prepared in consultation with Federal and State agen-
ies having managerial authority over certain project aspects. This coor-
ination must be documented in the license application.
great deal of coordination has taken p1 ace at agency staff l eve 1 s by dir-
ct participation in studies or by participation in committees and task
roups. This input, however, has been primarily by staff and may not nec-
ssarily reflect the views of the agency. For this reason, we are conduct-
ng a parallel formal coordination process, by requesting agency comments
on key study outputs. The plan of study was the first do~ument coordinated
in this manner. Over the next year, there will be several more. This par-
allel process will affect the other coordination activities of the study.
At this time, we request that the National Marine Fisheries Service review
the attached Report, .. Transmission Line Corridor Screening Closeout Report",
~
1
]
~
jJ
-
·particularly in the areas, impacting on the marine resources. ,.,
ACRES AMERICAN INCORPORATED
• J ; ~ ~: : • . ·: ":. •. ! ~-. ~!
• ~ •• 1
r r-,·
!, .
t
~
\; ;
Development Selection Report - 2 November 9, 1981
Your prompt attention to this matter will enable us to continue planning
the best possible development for all interests. A response within thirty
days of receipts would be greatly appreciated. Please send a copy of your
comments to:
Mr. Eric Yould, Executive Director
Alaska Power Authority
333 West 4th Avenue .
Anchorage, Alaska 99501
JDL/MMG:jgk
cc: Eric Yould, Alaska Power Authority
Very truly yo~rs,
AJO'IJ~-'f Nt/)_-tu
John D. lawrence
Project Manager
Mr. Ron Morris, National t4arine Fisheries
.•
ACRES AMERICAN iNCORPORATED
.
,ce
.R
"'· oL lee Nunn
istrict Engineer
IJ . S. Army Carps of Engineers
nchorage District
.0. Box 7002
nchorage, Alaska 99510
November 9, 1981
P5700.11.73
T.l269
\sURGH
Susitna Hydroelectric Project
Transmission Corridor Report
!
'N
'
Jo
I
L
I
)
i
I
I
I .
:-c.r
:
~I ear Col. Nunn:
1'1.
s you know, Acres Prnerican, Incorporated is under contract to the Alaska
ower Authority to conduct a feasibility study and prepare a Federal Energy
egulatory Commission (FERC) license application for the Susitna Hydro-
lectric Project. Tne scheduled date for submission of the application is
n June of 1982 .
"' .
r-
n
ederal law and FERC regulations require that the reports supporting the
ERC application be prepared in consult at ion with Federal and State agen-
tes having managerial authority over certain project aspects. This coor-
ination must be documented in the license application.
;::I
great deal of coordination has taken place at agency staff levels by dir-
ct participation in studies or by participation in committees and task
roups. This input, however, has been primarily by staff and may not nec-
ssarily reflect the views of the agency. For this reason, we are conduct-
a
h, .
lOg a para1lel formal coordination process, by requesting agency comments
on key study outputs. The plan of study was the first document coordinated
in this manner. Over the next year~ there will be several more. This par-
allel process will affect the other coordination activities of the study.
At this time~ we request that the U.S. Army Corps of Engineers review the
attached Report, ''Transmission Line Corridor Screening Closeout Report'\
particularly in the areas impacting on land and water quality.
ACRES AMERICAN JNCORPORATED
<.. · .. ·· 1 l: -;.
• • • ~~ . • • • . ... !
( ... ·
"· ~ _, '·.
)
"" i
,in
~0 .,
~
~1,/l
~~
,...,
:::s ._co
!-., :::s
;II)
II) ,
"' ~
~
I
r"".
'
r
. I
'
~'
!
. ' i (
'
' ' '
uevelopment Selection Report - 2 November 9~ 1981
Your prompt attention to this matter will enable us to continue planning
the best possible development for all interests. A response within thirty
days of receipts would be greatly appreciated. Please send a copy of your
comments to:
Mr. Eric Yould, Executive Director
Alaska Power Authority
333 West 4th. Avenue
Anchorage~ Alaska 99501
JOL/MMG: j gk
cc: Eric Yould, Alaska Power Authority
ACRES AMERICAN INCORPORATED
Very truly yours,
/ . :1~ , . ·11 ic !;'t til l / ' • j"'.J{ )t /. ~ 1 ~ ... l,£.t,.
John D. lawrence
Project Manager
i"
:;
H
!-'
.:·
,
WlLLE1'T
WITTE
BEARY
·HAYDEN
LAMS
LA-WRENCE
SINCLAIR
.. ·-----·· . -.
November 9~ 1981
P5700.11.92
T.1264
I
(
r. Ernest W. Mueller
ommissioner
laska Department of Environmental Conservation
uneau, Alaska 99801
Susitna Hydroelectric Project
Transmission Corridor Report
VANOERBURGHI ear Mr. Mueller: ·
1-.
-
CARLSON
FRETZ
JE'X
LOWREY
SINGH
H-USTEAD
savE
CHASE
//
,_ / ..... / .
I
J
s you know, Acres American., Incorporated is under contract to the Alaska
ower Authority to conduct a feasibility study and prepare a Federal Energy
egulatory Commission (FERC} license application for the Susitna Hydro-
lectric Project. The scheduled date for submission of the application is
n June of 1982.
ederal law and FERC regulations require that the reports supporting the
ERC application be prepared in consultation with Federal and State agen-
ies having managerial authority ov.er certain project aspects. This coor-
ination must be documented in the license application.
great deal of coordination has taken place at agency staff levels by dir-
ct participation in studies or by participation in committees and task
roups. This input, however, has been primarily by staff and may not nec-
ssarily reflect the views of the agency. For this reason, we are conduct-
ng a parallel formal coordination process, by requesting agency comments
n key study outputs. The plan of study was the first document coordinated
in this manner. Over the next year, there will be several more. This par-
allel process will affect the other coordination activities of the study.
At this time, we request that the Department of Environmental Conservation
'~
~
I
J
review the attached Report, .. Transmission Line Corridor Screening Closeout ~
keport11
., particularly in the areas impacting on the air, land~ and water ~
quality.
ACRES AMERICAN INCORPORATED
:· ..•.• !: .-l~~ ..... --·~~ :.· ~-:: ::• -· .•
;J .·•· ; • .. Y:·· •:_~ ~~·
!" .... : .... ; •• •4 .... • • • ..,. ~ ... • 1-. . /
r-
1 ··:
l
((""',
I
I
1~
i t
\ 'I
~-
-
...
-
Development Selection Report - 2
Nov e.rnb er 9 ~ 1981
Your prompt attention to this matter will enable us to ~ont~nue planning
the best possible development for all interests. A .response within thirty
days of receipts would be greatly appreciated. Please send a copy of your
comments to:
JOL/NMG:jgk.
Mr. Eric Yould, Executive Director
Alaska Power Authority
333 West 4th Avenue
·Anchorage, Alaska 99501
Very truly yours,
· .. jJ'?u Yl'j !!lud£
· . ~tv John D. Lawrence --r Project Manager
cL!----cc: Eric Yould, Alaska Power Authority
Mr. Bob Martin, Alaska Department of Environmental Conservatio/)
.. ~. : ~ ...
. ·
ACRES AMERICAN INCORPORATED
Wll.L.ETT
WITTE
BEARY
HAYDEN
l.AMB
l.AWAENCE
$1NCL.AIA
VANDERBURGH
' i-1 r
. r-' 1"-.J
CARLSON
FRETZ
.!EX
L.OWREY
I SINGH
HUSTEAD
sove
I CHASE-"-
/
...!, .---·;?·/ . -
Hr. Tom Barnes
Office of Coastal Management
Division of Policy Development & Planning
Pouch AP
Juneau, Alaska 99811
Uear Mr. 'Barnes:
November 9. 1981
P5700.11.92
T.l257
Susitna Hydroelectric Project
Transmission Corridor Report
As you know, Acres American~ Incorporated is und-er contract to the Alaska
Power Authority to conduct a feasibility study and prepare a Federal Energy
Regulatory Commission (FERC) license application for the Susitna Hydro-
electric Project. The scheduled date for submission of the application is
in June of l982.
Federal 1 aw and FERC regulations requir_e that the reports supporting the
FERC application be prepared in consultation with Federal and State agen-
cies having managerial authority over certain project aspects~ This coor-
dination must be documented in the license application.
~I
A great deal of coordination has taken place at agency staff levels by dir-~
ect participation in studies or by participation in committees and task
groups. This input, however~ has been primarily by staff and may not nee-"""""~'
essarily reflect the views of the agency. For this reason, we are conduct-
ing a parallel formal coordination process~ by requesting agency comments
on key study outputs. The plan of study was the first document coordinatea ~
in this manner. Over the next year, there will be several more. This par-
allel process will affect the other coordination activities of the study.
At this time, we request that the Office of Coastal Management review the
attached Report, "Transmission Line Corridor Screening Closeout Report 11
,
particularly in the areas affecting coastal management.
ACRES Ar~r1ERICAN INCORPORATED
...
... t, . -· . ;.. . ·-.·
......
),
r
i
$
-
<!"""'
I
I
i '~·· ~
I'
'·
Developnent Selection Report - 2
November 9, 1981
Your prompt attention to this matter will enable us to continue planning
the best possible development for a11 interests. A response within thirty
· days· of receipts would be greatly appreciated. Please send a copy of your
comments to:
JDL/f-.'!MG:jgk
Mr. Eric You1d, Executive Director
Alaska Power Authority
333 West 4th Avenue
Anchorage, Alaska 99501
Very truly yours,
· · i£1tJO tjj;,,.t · ti!Lvic j\i l
~ John D. Lawrence
"' Project Manager
cc: Eric Yould; Alaska Power Authority
·~ ~
Mr. Ernest W. Mueller
Conmissioner
Alaska Department of Environmental Conservation
Juneau, Alaska 99801
November 19, 1981
P5700.11.92
Sus itna Hydroe 1 ectri c Project .Aii\.
Fish and Wildlife Mitigation Policy
Uear Mr. Mue 11 er:
As you know, Acres American, Incorporated is under contract to the Alaska
Power Authority (APA) to conduct a feas ibi 1 ity study and prepare a Federal
Energy Regulatory Corrmission {FERC) license application for the Susitna
Hydroelectric Project. The scheduled date for submission of the application
is in June of 1982.
Federal law and FERC regulations require that the reports supporting the
FERC application be prepared in consultation with Federal and State agen-
cies having managerial authority over certain project aspects. This coor-
dination must be documented in the license application.
A great aeal of coordination has taken place at agency staff levels by dir-
ect participation in studies or by participation in committees and task
groups. This input, however, has been primarily by staff and may not nec-
essarily reflect the views of the agency~ For this reason, 1Ne are conduct-
ing a parallel formal coordination process, by requesting agency comments
on key study outputs. The plan of study was the first document coordinated
in this manner. Over the next year, there will be several more. This par-
allel process will affect the other coordination activities of the study.
At this time, we request that the Alaska Department of Environmental
Conservation review the attached Fish and Wildlife Mitigation Pol icy, which
has been developed by APA, the resource agencies and Terrestrial
En vi ronmenta 1 Speci a 1 is ts.
ACRES AMERJCAN INCORPORATED
..,
.I
.4
r-:
I
-.
Fish and Wildlife Mitigation_ Policy
Page 2
November 19, 1981
Your prompt attention to this matter will enable us to continue planning
the best possible development for all interests. A response within thirty
days of receipts waul d be greatly appreciated. Please send a copy of your
,-... · comments to me and to:
!
·r-.
r
L ..
-I
t
Mr. Eric Yould, Executive Director
Alaska Power Authority
JDL/MMG:jgk
En c.
333 West 4th Avenue
Anchorage, Alaska 99501
cc: Bob Martin
(letter only)
ACRES AMERICAN INCORPORATED
Very truly yours,
~ J)\ /.,.,_ ~ /.1'-1 b
John D. Lawrence
. Project Manager
(
W
ill
. .
Mr. Robert McVey
Director, Alaska Region
National Marine Fisheries Service
NOAA
P.O. Box 1668
Juneau, Alaska 99802
Dear Mr. McVey:
November 19, 19~1
P5700.11.91
Susitna Hydroelectric Project
Fish and Wildlife Mitigation Policy
As you know~ Acres American:, Incorporated is under contract to the Alaska
Power Authority (APA) to conduct a feasibility study and prepare a Federal
Energy Regulatory Commission (FERC) license application for the Susitna
Hydroelectric Project. The scheduled date for submission of the application
is in June of 1982.
Federal law and FERC regulations require that the reports supporting the
FERC application be prepared in consultation with Federal and State agen-.
cies having managerial authority over certain project aspects. This coor-
dination must be documented in the license application.
A great deal of coordination has taken place at agency staff levels by dir-
ect participation in studies or by participation in committees and task
groups. This input, however~ has been primarily by staff and may not nec-
essarily reflect the views of the agencyv For this reason, we are conduct-
ing a parallel formal coordination process, by requesting agency comments
on key study outputs. The p 1 an of study was the first document coordinated
in this manner. Over the next year, there will be several more. This par-
allel process will affect the other coordination activities of the study.
At this time~ we request that the National Marine Fisheries Service review
the attached Fish and Wildlife Mitigation Policy, which has been developed
by APA, the resource agencies and Terrestri a1 Environmental Speci a 1 i sts.
ACRES AMERICAN INCORPORATED
~ ·" Lit ~rty s~ "'k Buil::.rg r:.a.n a1 Ce:url
~ :·I
~.
I
; J
~I
.~
I
r
I
r
r
~
l
I'
~·
I
(
,.,.,.,
I
,•.
Fish and Wildlife Mitigation Policy
Page 2
November 19, 1981
Your prompt attention to this matter will enable us to continue planning
the best possible development for all interests. A response within thirty
days of receipts would be greatly appreciated. Please send a copy of your
comments to me and to:
Mr. Eric Yould, Executive Director
Alaska Power Authority
JOL/MivJG:jgk
En c.
333 West 4th Avenue
Anchorage, Alaska 99501
cc: Ron Morris
(letter only)
ACRES AMERICAN INCORPORATED
Very truly yours,
~ ]), 1.--<r~/.-M-b
John D. Lawrence
Project Manager
Mr. Keith Schreiner
Regional Director, Region 7
U.S~ Fish and Wildlife Service
1011 E. Tudor Road
Anchorage, Alaska 99503
Dear Mr. Schreiner:
• November 19, 1981
P5700 . .11.91
Susitna Hydroelectric Project
Fish and Wildlife Mitigation Policy
As you know~ Acres American, Incorporated is under contract to the Alaska
Power Authority (APA) to conduct a feasibility study and prepare a Federal
Energy Regulatory Commission (FERC) license application for the Susitna
Hydroelectric Project. The scheduled date for submission of the application
is in June of 1982.
Federal law and FERC regulations require that the reports supporting the
FEHC application be prepared in consultation with Federal and State agen-
cies having managerial authority over certain project aspects. This coor-
dination must be documented in the 1 icense application.
A great deal of coordination has taken place at agency staff 1 evel s by dir-
ect participation in studies or by participation in committees and task
groups. This input~ however, has been primarily oy staff and may not nec-
essarily reflect the views of the agency. For this reason, we are conduct-
ing a para11e1 formal coordination process, by requesting agency comments
on key study outputs. The plan of study was the first document coordinated
in this manner. Over the next year, there will be several more. This par-
allel process will affect the other coordination activities of the study.
At this time, we request that the U.S. Fish and Wildlife Service review the
attached Fish and Wildlife 1-titi gati on Pol icy, which has been developed by
APA, the resource agencies and Terrestrial Environmental Specialists.
ACRES AMERICAN INCORPORATED
Eu~~a!o. r:<:.-. York 14202
II. • 1 1 , ... 1-•·. •• ~ ,
/'~
I
~·
;
-
+""" -
A r
~
,i
,r
' i
Fi~h and Wildlife Mitigation Policy
Page 2
-=
November 19, 1981
Your prompt attention to this matter will enable us to continue planning
the best possible development for all interests. A response within thirty
. days of receipts would be greatly appreciated. Please send a copy of your
comments to me and to;
JDL/MMG:j gk
Enc.
Mr. Eric Yould, Executive Director
Alaska Power Authority
333 West 4th Avenue
Anchorage, Alaska 99501
Very truly yours,
John D. Lawrence
Project Manager
ACRES AMERICAN INCORPORATED
Mr. Ronald Skoog
Conmissioner
State of Alaska Department of Fish and Game
Juneau, Alaska 99801
November 19, 1981
P5700.11.92
-i I
Susitna Hydroelectric Project ~
Fish and Wildlife Mitigation Policy
Dear Mr. Skoog: ~
As you knows Acres Jlmeri cans Incorporated is under contract to the Alaska
Power Authority (APA) to conduct a feasibility study and prepare a Federal
Energy Regulatory Corrmission (FERC) license application for the Susitna
Hydroelectric Project. The scheduled date for submission of the application
is in June of 1982.
Federal law and FERC regulations require that the reports supporting the
FERC application be prepared in consultation with Federal and State agen-
cies having managerial authority over certain project aspects. This coor-
dination must be documented in the license application.
A great deal of coordination has taken place at agency staff levels by dir-
ect participation in studies or by participation in committees and task
groups. This i npot, however, has been primarily by staff and may not nee-
essarily reflect the views of the agency. For this reason, we are conduct-
ing a parallel formal coordination process, by requesting agency comments
on key study outputs. The plan of study was the first document coordinated
in this manner. Over the next year, there will be several more. This par-
allel process will affect the other coordination activities of the study.
At this time, we request that the State of Alaska Department of Fish and
Game review the attached Fish and Wildlife Mitigation Pol icy, which has been
developed by APA, the resource agencies and Terrestrial Environmental
Specialists.
ACRES AMERICAN INCORPORATED
~·,
.·
~""""'
I
l '
,....
i
r
Fish and Wildlife Mitigation Policy
Page 2
November 19~ 1981
Your prompt attention to this matter will enable us to continue planning
the best possible development for all interests. A response within thirty
days of receipts would be greatly appreciated. Please send a copy of your
comments to me and to:
Mr. Eric Yould, Executive Dire·ctor
Alaska Power Authority
JDL/MMG:jgk
En c.
333 West 4th Avenue
Anchorage, Alaska 99501
cc: Tom Trent
(letter only)
ACRES AMERICAN INCORPORATED
Very truly yours,
~ J). !, .. ~ /.;ffr;,
John D. Lawrence
Project Manager
WILLETT
WITTE
!
BERRY
I') .. .....-'1
Ill\{ 'I -1.~ ~
/ l_!~q_
v' ~~-,.A-,
LAMS I
LAWRENCE
l.S.I~R
y 'f"ANI GH -r......--
-K
CARLSON
FR.ETZ
JEX
LOWREY
SINGH
I v I~ ~
' l/ ~
HU~
aove
CHASE
I--,__
~
11~~
Mr. David Haas
Office of the Governor
November 24~~ 1981
P5700.11.92
T.1297
~Division of Policy Development and Planning
Pouch AW
Juneau, AK 99811
Dear Mr. Haas:
~r/
Susitna HYdroelectric Project
Formal Agency Coordfnat1on
As discussed yesterday. I am enc1os1ng a list· of all people
within state and federal agencies to whom we are sending
Susitna Hydroelectric Project Reports. The list is keyed to
explain who gets which reports. We are attempting to insure
that each agency has the opportunity to review reports dealing
with resources or issues for which it has jurisdiction.
If I can be of further help, please let me know.
Sincerely,
~awren~
Project Manager
JDl:d1p
Enclosure
xc: Alaska Power Authority
~I
SUSITNA HYDROELECTRIC PROJECT
REPORTS CIRCULATED FOR FORMAL AGENCY COORDINATION
r
' I ,
~ l
NI.MJER KEY
LWIL.l.ETT ....f VITTE
i ERRY -;1
Plan of Study 1
-f"' ' 1980 Envi ronmenta 1 SUIIIIIary Report 2
-( iAYOEN
!LAMB
1980 Fish Eco 1 ogy Annua 1 Report 3
J..L.AWRENCE
1 iiNCL.AI R iJ. fANDERBURGH ·,
~R~ON
1980 Plant Ecology Annual Report -4
1980 Big Game Annual Report 5
1980 Furbearer Annual Report 6
I FRETZ.·.
~ex ·
!; OWREY J INGH
I
1980 Birds and Non-Game Manrna1 Annual Report 7
1980 Land Use Annual Report 8 •
~r
~~-! .HUSTEAO
LBOVE
1980 Socioeconomic Annual Report 9
1980 Cultural Resources Annual Report 10
Transmission Line Cocridor Screening Report 11
CHASE
1.
~ Development Selection Report 12
1981 Final Subtask Report 13
Draft Feasibility Report 14
( .'
'·
Regional Administrator
Region X
U.S. Environmental Protection Agency
1200 South Avenue
Seattle, WA 98101 ·
Col . Lee Nunn
District Engineer
U.S. Army Corps of Engineers
Anchorage District
P.O. Box 7002
Anchorage, Ala~ka 99510
Mr. Keith Schreiner
Regional Director, Region 7
U.S. Fish and Wildlife Service
1011 E. Tudor Road
Anchor age, A 1 ask a 99503
Mr. Robert McVey
Director, Alaska Region
National Marine Fisheries Service
NOAA
P~O. Box 1668
Juneau, Alaska 99802
Mr. John E. Cook
Regional Director
Alaska Office
National Park Service
540 West Fifth Avenue
Anchorage, Alaska 99501
Mr. John Rego
Bureau of Land Management
701-C Street
Anchorage, Alaska 9950
Mr. Larry Wright
National Park Service
1011 E. Tudor Road, Suite 297
Anchorage, Alaska 99503
Ms. Judy Schwarz
U.S. Environmental Protection Agency
Ma i1 Stop 443
Region X EPA
1200 South 6th Avenue
Seattle, Washington 98101
Mr. Ron Morris
Director, Anchorage Field Office
National Marine Fisheries Service
701 C Street
Box 43
Anchorage, Alaska 99513
Reports sent/to be sent
1, 2, 11, 12, 13, 14
1, 2, 11,. 12~ 13, 14
1, 2, 3, 4, 5, 6, 7, 11,
12, 13, 14
1, 2, 3, 4, 5, 6, 7,
11, 12, 13, 14
1, 2, 9, 10, 11, 12, 13~ 14
1, 2, 8, 11, 12, 13, 14
1, 2, 11, 12, 13, 14
1, 2, 11, 12, 13, 14
1, 2, 11, 12, 13, 14
" .l J!
,-., . \
-
-I
!"""'
t""'
I
Mr. Ronald 0. Skoog
Commissioner
State of Alaska Department of Fish and Game
Juneau, Alaska 99801
Mr. Ernest W. Mueller
Convnissioner
Alaska Department of Environmental Conservation
Juneau, Alaska 99801
Mr. Lee Wyatt
Planning Director
Matanuska-Susitna Barough
Box B
Palmer, Alaska 99811
Mr. Tom Barnes
Office of Coastal Management
Division of Policy Development & Planning
Pouch AP
Juneau, Alaska 99811
Mr. Roy Huhndorf
Cook Inlet Region Corporation
P .0. Drawer 4N
Anchor age, A 1 ask a 99509
Mr. Thomas Trent
State of Alaska
Department of Fish & Game
333 Raspberry Road
Anchorage, Alaska 99502
Mr. Bob Martin
Alaska Department of Environmental Conservation
437 E. Street, 2nd Floor
Anchorage, Alaska 99501
Mr. Alan Carson
Alaska Department of Natural Resources
323 East 4th Avenue
Anchorage, Alaska . 99501
Ms. Lee McAnerney
Commissioner
Department of Community & Regional Affairs
Pouch B
Juneau, Alaska 99811
Mr. Robert Shaw
State Historic Preservation Officer
Alaska Department of Natural Resources
Division of Parks
619 Warehouse Avenue, Suite 210
Anchorage, Alaska 99501
Mr. John Katz
Alaska Department of Natural Resources
Pouch M
Juneau, Alaska 99811
Reports 'Sent/to be sent
1, 2, 3, 4, 5, 6, 7, 11,
12, 13, 14
1r 2, 3, 4, 5, 6, 7, 11,
12, 13, 14
1, 2, 11, 12, 13, 14
1, 2, 11, 12, 13, 14
1, 2, 8, 11, 12, 13, 14
1, 2, 11, 12, 13, 14
1, 2, 11, 12, 13, 14
1, 2, 11, 12, 13, 14
1, 2, 9, 11, 12, 13, 14
1, 2, 9, 10, 11, 12, 13,
14
1, 2, 8, 11, 12, 13, 14
WIL.L.ETT
WITTE
BERRY
_L
,'.\, ~~{:u.-1'
L.AMB
: t..AWRENCE
•' SINCL.AIR
••
VANOERBU~GH
~ [,
,j
: CARL.SON
i FFIE'TZ ·
I JEX
I L.OWREV I
SINGH
-...,. l'"w
_f_
HUSTEAD
save
'·]( .11. """'"'r-= .1
J(.( p ~ ............ ./
CHASE
'i
~,c
Mr. Tom Trent
A1 aska Department of Fish and Game
2207 Spenard Road
Anchorage, AK 99503
November 25, 1981
P5700.11.92
Te lJQl
Dear Mr. Trent: Susitna Hydroelectric Project
Report Review
As you discussed with Michael Grubb on November 24, 1981,
I am enclosing the following Sus1tna Hydroelectric Reports
which were also sent to Mr. Skoog for ADF&G review and
convnent:
l. 1980 Environmental SWIIIlary Report
2. 1980 Big Game Annual Report
3. 1980 Fish Ecology Annual Report
4. 1980 Plant Ecology Annual Report
5. 1980 Furbearer Annual Report
6. 1980 Bird and Non-Game Annual Report
As you suggested we will in the future send reports both to
Mr. Skoog and directly to you.
MMG:dlp
xc: E. Yould/APA
R. Skoog/ADF&G
Enclosures
Sincerely,
John D. Lawrence
Project Manager
_)
JAY S. HAMMOND, Governor
"""'·
'
OFFJICB OJF TEtE GOV8RN'OR
DIVISION OF POLICY DEVELOPMENT AND PLANNING
GOVERNMENTAL COORD!NA TION UNrT
' December 2, 1981
Mr. John D. Lawrence
Project Manager, Susitna Hydroelectric Project
Acres American Incorporated
The Liberty Bank Building, Main at Court
Buffalo, New York 14202
Dear Mr. lawrence:
POUCH AW (MS-0165}
JUNEAU, ALASKA 99871
PHONE: f907) 465-3562
RECEIVED
DEC 7 1981
( This letter should clarify a telephone conversation we had on November 23, 1981
~! and the role of this office in reviewing subsequent materials relating to the
1. , Susitna Hydroelectric Project.
Our office recently received copies of correspondence addressed to To~ Barnes,
formerly of the Alaska Office of Coastal Management (OCM). We conduct Alaska
----------~Co_astal Management Program {ACMP) consistency reviews for OCM as well as unified
ate responses on many major projects •. Thus, OCM notified us of this correspond-
ce. In this regard, we•d first like to inform you that Ms. Wendy Wolf has
placed Tom Barnes at OCM and will handle any future reviews of the Susitna
oposal for OCM.
ALASKA POWER
ruTHORITY
_j_ USJTNA
FILE "P5700 P .r .J/.9? Sg U~="'''"'c NO for future reviews, we would like to receive a mailing list of all agencies P -d;/5-q ·c ntacted and a copy of the particular report. We waul d 1 ike to do an i nforma-
1 : ·anal review of the feasibility study when it is available. We would expect
.z['lj .] g I t at an Environmental Impact Statement (EIS) would also be prepared for this
12 ~ ~ jar project and that we would conduct an ACMP consistency review of it. If :~~~~. § I, _~d u do prepare such an EIS, we would like to coordinate the mailing of such
~ -~~cument with you to simplify our review procedures. We would, of course, like
,-1'.-~?-·:~ :____! know if there won • t be an EIS.
. I ·/f -· . .. -rr· c -~~) :---p
·-li ~~
! f~:c,.G. } :~ .0: I
i -~-::?!\!;·-~ .;; ~-;-; --:-r----_, : i J p 3 f ,_,,, 1---:_l~li?GHl/
ease advise us if you can clarify any of the review process and if you
ve any questions. _ ·•
Sincerely,
ilu~ /v'. /J~v>
David W. Haas
State-Federal Assistance Coordinator
-g· -._!_~2-I_E,~ f SNT !~j -. Dt•J L l ~ !=h: ~~ 1----" : Eric Youl d, APA
-j"·---r __ l
: r I :-~~~~--
;-,-I
-~-.. -1 -c ~~---
WII..LETT
WITTE
BERRY
HAYDEN
t.AMB
LAWRENCE
SINCLAIR
·bJ· ·.·":, >.'..;. ~· I --' ·-.. _ ~ .. ;:-r ---... -'~ -.
•
M r. Ernest W. Mueller
ommissioner c
1\
"\
J
laska Department of Environmental Conservation
uneau, Alaska 99801 -
December 4, 1981
P5700.11.92
T.l325
VANDER BURGH
,..... (~
CARLSON
FRETZ
JEX
LOWREY
SINGH
HUSTEAD
BOVE
CHASE·
///.---
~ -...-t:/(~
~
r-
.}
~
I'
~
n
ear Mr. ·Mue l1 er:
Susitna Hydroelectric Project
Document Transmittal Form
nclosed· is a document transmittal form which should have accompanied our
ackage dated November 10 containing copies of the Development Selection
eport and its appendices. The document transmittal form is part of a
ewly-implemented procedure at Acres which is intended to verify the arrival
f documents shipped via various carriers and thus alleviate as quickly as
ossible any problems which may arise due to documents being misplaced
uring transit.
f you have any questions, please do not hesitate to calL
Sincerely yours,
~Yn~c€-L--
~John D. Lawrence
Project Manager
JEM/jh
Enclosures
cc: Mr. Bob Martin f.;l. /?
Alaska Dept. of Environmental Conservation
ACRES AMERICAN INCORPORATED
Co..,~uH.ng E.,gineers
r~e liberty ean'-Building. M;.•n at Ct!url
=-~~~aio Nc .. ·• York i4202
~I
...,
:1.' l .11
~'
,.l:YIL.l..ETT
-i IITTE
r-'·1
EI'I:RY
-;r
'--. .• AYDEN
LAMB
.I..L._AWAENCE
~ 'INCLAIR J, ANDERBURGH
'=f ·.
-; ...:ARLSON
I FRETZ
,./o.I,EX p OWREV
_\_ INGH
::!HUSTEAD
1 eave
~·
I CHASE
~--~
r-i
~ /.0
~_/.,'/
/
r
r
'
Mr. Lee Wyatt
Planning Director
Matanuska-Susitna Barough
Box B
Palmer, Alaska 99645
Dear Mr. Wyatt:
---~--
December 4, 1981
P5700,11.92
T .1330
Sus itna Hydroelectric Project
Document Transmittal Form
Enclosed is a document transmittal form which should have accompanied our
package dated November 10 containing copies.of the Development Selection
Report and its appendices. The document transmittal form is part of a
newly-implemented procedure at Acres which is intended to verify the arrival
of documents shipped via various carriers and thus alleviate as quickly as
possible any problems which may arise due to documents being misplaced
during trans it.
If you have any quest ions, please do not hesitate to call.
JEM/jh
Enclosures
ACRES AMERICAN INCORPORATED
Ccnsu•tir.g El'lg.neers
Tt:e Liber:y 9a"k BuJd:n; l.~a·l'l a1 Cour!
;!u~'a!o. r-:e:• Yorl. H202
Sincerely yours,
~e.Yn~
~John D. Lawrence
Project Manager·
Wll.LETT
WITTE
BERRY
HAYDEN
LAMB
LAWRENCE
SINCLAIR
~
~
N
1
'
r. Robert McVey
irector, Alaska Region
ational Marine Fisheries Service
OAA
.0. Box 1668
uneau, Alaska 99802
December 4, 1981
P570D.11.91
T .. 1323
VANOERBURGH
,...-r -~-
CARLSON
FRETZ
JEX
LOWREY
SINGH
! HUSTEAD
I BOVE
I
I
CHASE
',
1
I
/
...;;.;. ,/ (-
ear Mr. McVey:
Susitna Hydroelectric Project
Document Transmittal Form
nclosed is a document transmittal form which should have accompanied our
ackage dated November 10 containing copies of the Development Selection
eport and its appendices. The document transmittal form is part of a
ewly-implemented procedure at Acres which is intended to verify the arrival
f documents shipped via various carriers and thus alleviate as quickly as
ossible any problems which may arise due to documents being misplaced
uring transit.
f you have any questions, please do not hesitate to call.
JEM/jh
Enclosures
cc: Mr. Ron Morris, Director (,;1 h
Sincerely yours,
~<;o;J~e-R. -r John D. Lawrence
Project Manager
Anchorage Field Office National Marine Fisheries Service.
ACRES AMERICAN INCORPORATED
n.e Llb!:rty e2nk Buildmg r.la:n at Court
-
j
__ _}
,,-, · .. J
,
j
-
....
I
'"
WILLETT
J..:NlTTE _, ,&RAY
-'
r H' ;AVOEN
1-i' .. AMB
LAWRENCE
~r·r-r~
) I · . i i, :,,-
j .,J n
i.l..._ ..... ~
,
.,,
e
~1
r. John E. Cook
gional Director
aska Office
~a
4
n
tional Park Service
0 West Fifth Avenue
chorage, Alaska 99501
December 4, 1981
P5700. ll • 91
T. 1328
~INCLAIR
~· (ANOERBURGM·
t~LOON
FRETZ
IJEX
_,._OWREY
-{ iNGH
I
r-~ F\, lUSTEAD aove
l r -i -·, .;HASE
I
-r --': ,/
.d -z_ ./',.,
~'
-
re
rn
'=a Jje
b
!r
II
j..U
_rl
1
ar Mr. Cook:
Susitna Hydroelectric Project
Document Transmittal Form
closed is a document transmittal form which should have accompanied our
ckage dated November 10 containing copies of the Development Selection
port and its appendices. The document transmittal form is part of a
w1y-implemented procedure at Acres which is intended to verify the arrival
documents shipped via various carriers and thus alleviate as quickly as
ssible any problems which may arise due to documents being misplaced
ring trans it.
you have any questions, please do not hesitate to call.
Sincerely yours,
9C~~
~John D. Lawrence
Project Manager
JEM/jh
Enclosures
cc: Mr. Larry Wright
National Park Service
I ~~ -~ I
I
ACRES AMERICAN INCORPORATED
WILL.ETT
WITTE
BERRY
HAYDEN
LAMB
LAWRENCE
SINCLAIR
,
Regional Administrator
egion X R
u
1 s
.S. Environmental Protection Agency
200 South Avenue
eattle, WA 98101
December 4, 1981
?5700. 11.91
T.l320
VANDERBUFIGH
,_ ('•
CARLSON
FRETZ.
JEX
t..OWREY
' SINGH I
·,
I
HUSTEAD
I BOVE
I
' CHASE
---
p ear Sirs:
Susitna Hydroelectric Project
Document Transmittal Form
K
nclosed is a document transmittal form which should have accompanied our
ackage dated November 10 containing copies of the Development Selection
eport and its appendices. The document transmittal form is part of a
ewly-implemented procedure at Acres which is intended to verify the arrival
f documents shipped via various carriers and thus alleviate as quickly as
ossible any problems which may arise due to documents being misplaced
II'
..,
D1
-1 uri n g transit.
f you have any questions~ please do not hesitate to call.
JEM/jh
Enclosures
cc: Ms. Judy Swartz
Sincerely yours,
~~~ P. John D. Lawrence
Project Manager
U.S. Environmental Protection Agency
ACRES AMERICAN INCORPORATED
Cc.nsul!in'g Engineers
The Libe:rry Bank Bui!c·ng. ~.~am at Court
Bu"'<'O New Yor~ 1~202
,
' .··~·
. .-,. : ,.~
j
J
,
j
,"""!
" I WIL.L.ETT
r-r"WITTE
r::: · SE~RY
1
I
I
R,....,. HAYDEN
ti..AMS
I L.AWRENCE
'I
. \ -
•
r. Ronald 0. Skoog
ommissioner
laska Department of Fish and Game
uneau, Alaska 99801
December 4, 1981
P5700. 11.70
T. 1324
[f'NCL.AIR
VANOERSURGH
~/
r· j CARLSON
!FRETZ
I JEX
:[.LOWREY SINGH
,.
I
,....!
I L HUSTEAD
[SOVE
I
l[
iJ tCHASE
I
[p-I_
n
...
r
\
t
r
.
'
C"; .. {I
_.I
f
~
t
[
l
ear Mr. Skoog:
Susitna Hydroelectric Project
Document Transmittal Form
nclosed is a document transmittal form which should have accompanied our
ackage dated November 10 containing copies of the Development Selection
eport and its appendices. The document transmittal form is part of a
ewly-implemented procedure at Acres which is intended to verify the arrival
f documents shipped via various carriers and thus alleviate as quickly as
ossible any problems which may arise due to documents being misplaced
uring transit.
f you have any questions, please do not hesitate to call.
Sincerely yours,
YLW?~
~John D. Lawrence
Project Manager
aEM/jh
Enclosures
I ) ,, ')
cc: Mr. Thomas Trent J -. • l
State of Alaska Dept. of Fish & Game
ACRES AMERICAN INCORPORATED
-• :-. • ... .:: ~ -. : .... _ :~ -: ~ ~ ·_. F
WILLETT
WITTE
BERRY
HAYDEN
LAMB
LAWRENCE
SINCLAIR
VANOERSURGH
r-.r
r-!.,_
CARLSON
FRETZ
JEX
L.OWR.EY
SINGH
HUSTEAD
BOVE
CHASE
/•/
(!... --/ ----1! .....
/.
~
L._j'
f -t ... :~ i : . -: . : :
j._a.....,.LioiiM-:..;,...1
'
Mr. Keith Schreiner
Regional Director, Region 7
U.S. Fish and Wildlife Service
1011 E. Tudor Road
Anchorage, Alaska 99503
Dear Mr. Schreiner:
December 4, 1981
P5700. 11 • 71
T.1322
Susitna Hydroelectric Project
Document Transmittal Form
Enclosed is a document transmittal form which should have accompanied our
package dated November 10 containing copies of the Development Selection ·
Report and its appendices. The document transmittal form is part of a
newly-implemented procedure at Acres which is intended to verify the arrival
of documents shipped via various carriers and thus alleviate as quickly as
possible any problems which may arise due to documents being misplaced
during trans it.
If you have any questions, please do not hesitate to call.
JEM/jh
Enclosures
ACRES AMERICAN INCORPORATED
Sincerely yours,
~~~~
tf»'-John 0. Lawrence
Project Manager -
I""!\
\
r
I
I WILLETT
-!""'WITTE
1 · '3E.RRY
"'l·
I
I
_j HAYDEN
-ll LAM9
I LAWRENCE
,} ... "
f r~ .... ,._ ,_~~~
'
Mr. John Katz
~
j
laska Department of Natura 1 Resources
ouch M
uneau, Alaska 99811
December 4, 1981
P5700. 11.74
T. 1329
ANDER BURGH
~NCLAIR
~ALSON
I FRETZ
IJEX
!"':""LOWREY
t SINGH·
L ,
I
~r l t • HUSTEAD
JBOVE
I
.''' ., !CHASE
I
lr~~
rt , ~
I(.,.' .._ ~ ---C/
r
....
ear Mr. Katz:
Susitna Hydroelectric Project
Document Transmittal Form
nclosed is a document transmittal form which should have accompanied our
ackage dated November 10 containing copies of the Development Selection
eport and its appendices. The document transmittal form is part of a
ewly-implemented procedure at Acres which is intended to verify the arrival
f documents shipped via various carriers and thus alleviate as quickly as
ossible any problems which may arise due to documents being misplaced
uring transit. ·
f you have any questions, please do not hesitate to call.
JEM/jh
Enclosures
J"i
cc: Mr. Alan Carson '~\·1
Alaska Dept. of Natural Resources
ACRES AMERICAN INCORPORATED
Sincerely yours,
~·~&-e__
~· John D. Lawrence
Project Manager
Wll.l..ETT
WITTE
BEARY -
HAYDEN
I..AMB
l..AWAENCE
SINC1.AIR
L_·_.J
------...
'
,
,.1 r. Robert Shaw
)
'l
tate H-istoric Preservation Officer
l ask a Department of Natural Resources
ivision of Parks
19 Warehouse Avenue~ Suite 210
nchorage~ Alaska 99501 ill
December 4, 1981
P5700. 11.74
T. 1326
VANDER BURGH
-r -l.
CA.Al.SON
FRETZ
JEX
LOWREY
SINGH
HUSTEAD
BOVE
CHASE
/ ,.' :. ' ""//.--({/
h, ear Mr. Shaw:
Susitna Hydroelectric Project
Document Transmittal Form
nclosed is a document transmittal form which should have accompanied our
ackage dated November 10 containing copies of the Development Selection
eport and its append ices. The document transmittal form is part of a
ewly-implemented procedure at Acres which is intended to verify the arrival
f documents shipped via various carriers and thus alleviate as quickly as
ossible any problems which may arise due to documents being misplaced
uring trans it.
f you have any questions, please do not hesitate to call.
JEM/jh I")..\\
Enclosures
cc: Mr. Alan Carson
Alaska Dept. of Natural Resources
ACRES AMERICAN INCORPORATED
Sincerely yours,
~77JC6'L£-~
~John D. Lawrence
Project Manager
-
,_w
l
1-·.-12 ,
,j
-
.,
.....
i
r
I WILLETT
..!.WITTE
~ ,BERRY .
I
J
~ HAYDEN r, LAMB
I LAWRENCE
~INCLAIR
:
,
Mr. John Rego
B
7
A
ureau of Land Management
01-C Street
nchorage, Alaska 99501
December 4, 1981
P5700,11.75
T. 1331
·+ VANDERBURGH
Susitna Hydroelectric Project
Document Transmittal Form :-!{;
R CARLSON
1'FRETZ
IJEX
~OWREY
NGH
I
.J. 8 HUSTEAD
1'sove
I
i:HASE
I
..,.1..
~ /-;,,;
.-/
!"""
I
I
r
l
l"""
I
I
~ ear Mr. Rego:
,... nclosed is a document transmittal form which should have accompanied our
ackage dated November 10 containing copies of the Development Selection
eport and its append ices. The document transmittal form is part of a
ewly-impl emented procedure at Acres which is intended to verify the arr iva 1
f documents shipped via various carriers and thus alleviate as quickly as
ass ible any problems which may arise due to documents being misplaced
p
R'
II
D
n,
fl uring transit.
f you have any questions, please do not hesitate to call.
JEM/jh
Enclosures
ACRES AMERICAN INCORPORATED
Consult,n; ·Eng.necers
Tt;e Liberty eank Bui!ci.ng. l!.ain at Court
a ... _·~ a to_ Ne\·; Yorfl 1.:202
Sincerely yours,
t1C"77JSI3~ r-John D. Lawrence
Project Manager
WILLETT
WITTE
BEARY
HAYDEN
LAMS
LAWRENCE
SINCLAIR
VANDER BURGH
~ .. ·.~-----1 -'·:..;a ~;--... ------1
· .. l.soN .,
'~;.;,.H __ ---1
1-----1 ~~ . .__, -·---~· ~~~ .·:::'1li'~ . .-=eA':"":o~--;
'~;--...;
'~:u. '*•··-----t
' .. ''!111-------l
·!
. ·'.'l ·-------1
. _...-;.':" _.~---/"
;~/.
L--__ j
,
Cal. Lee Nunn
District Engineer
U.S. Army Corps of Eng i n·eer s
Anchorage District
P.O. Box 7002
Anchorage, Alaska 99510
Dear Col . Nunn:
·December 4, 1981
P5700. 11 . 73
T. 1321
Susitna Hydroelectric Project
Document Transmittal Form
Enclosed is a document transmittal form which should have accompanied our
package dated November 10 containing copies of the Development Se1ection
Report and its append ices. The document transmittal form is part of a
newly-implemented procedure at Acres which is intended to verify the arrival
of documents shipped via various carriers and thus alleviate as quickly as
possible any problems which may arise due to documents being misplaced
during transit.
If you have any questions, please do not hesitate to call .
JEM/jh
Enclosures
ACRES AMERICAN INCORPORATED
Consu'itmg Engineers
The Liberty Bank 6uildll>g. Main at Court
Buffalo. New York 14202
Telepho.,e 716-BS:i-i525 Telex 91-6423 ACRES SUF
Sincerely yours,
~· 7:JJ~.a.£-
~John D. Lawrence
Project Manager
-
,
.~ ,
.
'j
,
J
"'"!
!
r
l
[:: WILL.ETT
WITTe
BERRY
I ..
I, HAYDEN
I L.AMB r L-AWRENCE
SINCLAIR
~r
1f
~i
0
hu
,
. Tom Barnes
fice of Coastal Management
vision of Policy Development & Planning
X AP
neau, Alaska 99811
December 4, 1981
?5700.11.91
T. 1332
I VANOERBURGH
I r( '
[ '• CARLSON
I FRETZ r· JEX
LOWREY
SINGH
I
I
1 HUSTEAD
I sovE r
'l CHASE
l
[:
/ /v':'
EJ .,..&"'(/
r
\
r-
1
r
r
i
l
r
i
e
n
1 a
Je
e
( f
0
I.U
14=
ar Mr. Barnes:
Susitna Hydroelectric Project
Document Transmittal Form
closed is a document transmittal form which should have accompanied our
ckage dated November 10 containing copies of the Development Selection
port and its appendices. The document transmittal form is part of a
wly-implemented procedure at Acres which is intended to verify the arrival
documents shipped via various carriers and thus alleviate as quickly as
ssible any problems which may arise due to documents being misplaced
ring transit.
you have any questions, please do not hesitate to call.
Sincerely yours,
9C-·~
pz... John D. lawrence
Project Manager
JEM/jh
Enclosures
ACRES AMERICAN INCORPORATED
c~~.s~!J ·~;~Eng :r.eers
JAYS. HAMMOND, GOVERNOR ~
DEPARTMEIWT OF N&nJRAL RESOIJRCES 619 WAREHOUSE DR., SUITE 210 111'111
ANCHORAGE, ALASKA 99501 ..
(.
\O.J11 LH
DIVISION OF PARKS PHONE: 214-467< ALASKA POWER
AUTHORITY
RECEIVED . SUSITNA ~
F; .,·oo
DEC 14 1981
ACRES AmtJIJliiut m~UHf'ORATED
'------~:.....~~~~~~~~ .. , ,,..,. . " •r
: .;:\. c:;.j~ ......... ~ 1~\.i -:'1
December 4, 1981 P:~l;;t)
Re: 1130-13
John D •. Lawrence
Project Manager
Acres American, Inc.
The Liberty Bank Building, Main at Court
Buffalo, New York 14202
Dear Mr. Lawrence:
~ ~ J ___ ..}
~
We have reviewed the 1980 reports by the University of Alaska Museum de Tiflg -s NT-
with the cultural resources of the Susitna Hydroelectric project area. Th ~
report documents the survey activities conducted during 1980 which adeq *
accomplish the tasks outlined in the proposed work plan. The sampling
designed on the basis of geomorphic features and known use areas seems
surpassed our expectations of site incidence in the area. The report s
that the first level inventory was very competently conducted and recor
The second year activities as outlined in the procedures manual was acco
plished in the 1981 field season according to information gained throug
verbal communication with the principle archaeological investigators.
understand that the field research strategy was changed slightly from th~·!--1...,...:=--\
expected due to information gained during 1980. These changes appear tOUJ.aJL.e.---.:.-~..;
more directly addressed problems which surfaced during the course of analysis
of the 1980 data. A final review of the 1981 results and reports will have to
await receipt of that document.
We feel that the steps taken thus far in the cultural resource management of
the project have been excellent and one of the few instances of adequate lead
time. We would like to make the observation that the work thus far is only
preliminary to the work yet needed for the Susitna Hydroelectric project.
Reconnaissance and testing of yet to be examined areas should continue. The
clearances of specific areas of disturbance provided as additional survey by
the Museum should indicate the continued need for clearances of ancillary
projects which could affect cultural resources. Also, a formal mitigation
plan for those sites to be affected by the project must be formulated. Once
definite decisions on the route of access to the project area from existing
road systems are made, those access routes and material sites must be examined
for conflicts and needs for mitigation. Issuance of a permit by the Federal
Energy Regulatory Commission should and probably will include provisions
specifying under federal law the need for such protection.
-
~ .. ;~
-
-
-
-(
John D. Lawrence
December 4, 1981
Page 2 -
If you have any questions regarding our comments contained here, please call
us. We look forward to receiving the report on 1981 field work.
Sincerely,
Chip Dennelein
Director
By:
ll
. Shaw ~
Preservation Officer
cc: Dr. E. James Dixon
Curator of Archaeology
University of Alaska Museum
University of Alaska
Fairbanks, Alaska 99701
Eric Yould
Executive Director
Alaska Power Authority
333 W. 4th Avenue
Anchorage, Alaska 99501
DR:clk
October 6)1981
Mr.Eric P.Yould
Executive Director
Alaska Power Authority
3334 West 5th Avenue
Anchorage)Alaska 99501
Dear Mr.Yould:
,
UNITED STATES DEPARTMENT OF COMMEF=lCE
National Oceanic and Atmospheric Administration
Natior:.:::.:Ib.::'ine Fisheries Service
P.O.Eo::::1668
Juneau~Alasr~99802
RECEIVEO
OCT 15 1981
AlASKA POW~At)IW}~lf",.
-
Involvement of this agency with efforts by others to explore the
potential for hydroelectric development on the Susitna River dates
back to 1973.In 1974)we had contracted Environaid for a study titled
"A Hydrologic Reconnaissance of the Susitna River Below Devil IS Canyon")
and more recently we have been a participant on the Susitna Steering
Committee.
We appreciate the opportunity presented in your letter of September 25,1981
to extend our participation by becoming a member on the Susitna Fisheries
Mitigation Task Force,Review Committee.I have directed Brad Smith of
our Environmental Assessment Division (EAD})Anchorage Field Office to·
represent National Marine Fisheries Service (~MFS)on this important com-
mittee.Mr.Smith will fully participate on the Review Committee and be
res pons ible for d ra ft i ng the recommended N!"lFS I pos it ion.
Please continue to send official correspondence through our Regional
Office.Delays in NMFS response time associated with our routing of
your materials to and from the Anchorage EAD Field Office could be
reduced if you would provide a courtesy copy of correspondence dir-
ectly to Mr.Smith.
Should you have further questions regarding Mr.Smith1s involvement)
please contact Ron Morris,the supervisor of the Anchorage EAD Field Office:
Bradl ey K.Smith and Ronald J.Morri s
National Marine Fisheries Service
Federal Building &U.S.Court House
701 C Street,Box 43
Anchorage,Alaska 99513
Phone:(907)271-5006
Sincerely)
)Jl.0~V'N-V---at '\',(Robert W.tkVey
Director)Alaska Region
I I
REPLY TO
ATTENTION OF':
NPAEN-PL-EN
DEPARTMc..NT OF THE ARMY
ALASKA DISTRICT.CORPS OF ENGINEERS
P.O.BOX 7002
ANCHORAGE.ALASKA 99510
1 3 OCT \98\
QC120 1981
-
Mr.Eric P.Yould
Executive Director
Alaska Power Authority
334 West 5th Avenue
Anchorage,Alaska 99501
Dear M~ul-d:
This is in response to your letter of 25 September 1981 concerning Corps of
Engineers participation in the Upper Susitna River Basin Fisheries Mitigation
Review Committee.
Unfortunately,the continued funding and manpower constraints under which we
must operate make it necessary for me to decline your invitation.However,we
will provide the reviews required for the issuance of per~its under our
regulatory program.
If I can be of further assistance,please contact me directly.If further
details are desired by your staff,contact can be made with Mr.Harlan Moore,
Chief,Engineering Division at 752-5135.
2"Z?~-""-----
LEE R.NUNN
Colonel.Corps of Engineers
District Engineer
JA Y S.HAMMOND,GOYERNOR
/
SUBPORT BUILDING
JUNEAU,ALASKA 99801
DEPART)IE'T OF FISH :\~D GA .1IE
OFFICE OF THE COMMISSIONER
October 23,1981
Mr.Eric P.You1d
Alaska Power Authority
334 West 5th Avenue
Anchorage,Alaska 99501
Dear Mr.You1d:
Thank you for your invitation to place a member of my staff on the
committee being established to review mitigatory recommendations for the
Susitna Hydroelectric project.I have designated Mr.Carl Yanagawa,
Regional Supervisor for the Habitat Division,to sit as our represent-
ative on the review committee.
-l
I anticipate that Mr.Yanagawa will work closely with the other members
of the committee,and with Tom Trent and Karl Schneider,to develop
sound policy recommendations for Su-Hydro.
Mr.Yanagawa's office is in the Fish and Game building at 333 Raspberry
Road and he can be reached at 267-2138.
Sincerely,
-
1 .Ronald O.Skoog
-+d"t Commissioner
J---(907)465-4100
-I
u.s.
REPLY TO /S 443....TTN Of:M·
.~I.'.
ENVIRONMENTAL PROTECTION AGENCY
REGION X
1200 SIXTH AVENUE
SEATTLE,WASHINGTON 98101
it E CE I V E 0
Orr ...,
""""..-
AlASM pnl'ILR~..Il,;AUT11"';'7•LII.\'
Eric P.Yould,Executive Director
Alaska Power Authority
534 West 5th Avenue
Anchorage,Alaska 99501
DearMr~~
RECEIVED
OCT 3 n 1531
ALASKA POWER AUTHORITY
The Environmental Protection Agency (EPA)accepts your invitation to
participate on the Review Committee for the Fisheries Mitigation Task
Force on the hydroelectric development of the Upper Susitna River Basin.
EPA generally relies on the state and Federal fish and wildlife agencies
for the technical input and evaluation on such task forces.However,I
feel that we may be able to provide as a member of the Review Committee,
a different perspective which may help your efforts.Because of our
limited resources both in staff and travel money,our participation will
have to be somewhat limited.
I have designated Ms.Judi Schwarz as our formal contact for the activi-
ties of this Review Corrmittee.Ms.Schwarz is in the Environmental
Evaluation Branch in our Seattle Office and has had primary contact with
the Susitna project through our EIS review responsibilities.She can be
reached at (206)442-1285.I have also asked Jim Sweeney,Director of
our Alaska Operations Offi~e to provide support in this effort because of
his proximity and knowledge of the unique Alaska conditions.His tele-
phone number in Anchorage is (907)271-5083.
We look forward to actively participating on this Review Committee.Any
information you can send us on the activities of the wildlife mitigation
task force would be appreciated.
Thank you for giving us the opportunity to become actively involved in
this important development.
c c:Jim Sweeney
,P--
;
i .,"
",I....._.
December 1,1981
-'
OFFICE OF THE COMMISSIONER
11.Y S.HAMMOND.GOVERNOR
POUCHM
JUNEAU,ALASKA 99811
PHONE:(9 a7)4 65 - 2 40 0
""'"!
I
t
i
J~
-
..r--,
lO·J9LH
Mr.Eric Yould
Executive Director
Alaska Power Authority
334 West 5th Avenue
Anchorage,AK 99501
Dear Eric:
This letter is in response to your September 28,1981 letter
offering an opportunity for DNR participation on the mitigation
review committee for the proposed Susitna Hydroelectric
Project.
Al Carson of the Division of Research and Development will
be our representative for the committee.He can be reached
by phone at 276-2653.
Thanks for providing us with the opportunity to participate
in this important endeavor.
Sincerely,
~z
Commissioner
cc:"Reed Stoops
---ALASliA POWER AUTHORITY
334 WEST 5th AVENUE·ANCHORAGE,ALASKA 99501
RECEIVED
DEC 14 1981 December 9,1981
-Phone:(907)277·764-'
(907)276·0001
ACktl)I\ltl.c.nlli#\ft llttiUltl'UttATED
Mr.Keith Schreiner
Regional Director,Region 7
U.S.Fish &Wildlife Service
1011 E.Tudor Road
Anchorage,Alaska 99503
Dear Mr.Schreiner:
'-
A member of your staff advises me you did not receive
my letter of September 25,1981,inviting your participation
to the Susitna Hydroelectric Project mitigation Review
Group.Let me hasten to repeat the invitation.
-
ALASKA POWER
AUTHORITY
SUSfTNA
FILE P5700
./1
SE(JUENCE NO.
;=;c:?/~
Integral to our study of the potential effects of
hydroelectric development of the Upper Susitna River Basin
is the formulation of fisheries mitigation plans.To that
goal,a Fisheries !-1itigation Task Force,in two parts,is
being formed.One part will be a core group of the
principal investigators.Their task will be to identify and
address impacts,and develop appropriate mitigation plans.
A Second group will act as a review committee commenting on
the efforts of the core group.
You are invited to be a member of the Revi.ew Committee.
If you agree,your role would be to work in concert with
other concerned agencies to assess the adequacy of the
impact predictions and associated mitigative planning.In
addition to reaping the benefits of your expertise,your
participation would also fulfill key consultation
requirements outlined in the Federal Energy Regulatory
Commission (FERC)regulations and in the provisions of the
Fish and Wildlife Coordination Act.
A similar structure was established early this year for
wildlife mitigation.An early objective will be to
reorganize into one-common review committee for mitigation,
overviewing separate core groups for fisheries and wildlife.
You might consider this when you appoint your organizational
representative.
-
-
,-"
r
i
\i
r
r
Dear
I am enclosing for your review the following reports prepared by the
Alaska Department of Fish and Game for the Susitna Hydroelectric
Project:
1.Fi na 1 Draft Report ,Adult Anadramous Fi sheri es Proj ect
2.Resident and Juvenile Anadramous Fish Investigations on the Lower
Susi tna Ri vet
3.Aquatic Habitat Investigations.
These reports are provided for your information only;they are not part
of our formal Agency Coordination Program.Comments are not requested
but will certainly be accepted.
Sincerely,
!1 I ._------_.-.__.._-
r"1r.A1 Carson
Division of Research &Development
Department of Natural Resources
323 East Fourth Avenue
Anchorage,Alaska 99501
-.
Mr.Gary Stackhouse
U.~.Fish &Wildlife Service
1011 East Tudor Road
Anchorage,Alaska 99502-------~M2r..::..:..:..C~a:-:r;.;lRyT:a~n~a~g:-:a~w~a~.::..=..~=--------------------------J~-
Regional Supervisor for Habitat Division
Al ask a Department of Fish &Game
333 Raspberry Road
Anchor age,A1 ask a 99502
Ms.JUdl Schwarz
Environmental Evaluation Branch
U.S.Environmental Protection Agency
Region X
1200 Sixth Avenue
Seattle,Washington 98101
~
i
-
-
December 18,1981
P5700.11.91
T.1355
Ms.Janet McCabe
Area Di rector
u.S.Geo 109i ca 1 Survey
1011 E.Tudor
Suite 297
Anchorage,AK 99501
Dear Ms.McCabe:Susitna Hydroelectric Proj~ct
Fish and Wildlife Mitigation
Review Group
In September of thi s year the Al aska Power Authority (APA)invited you or
a member of your staff to participate in a Fish and Wildlife Mitigation
Review Group for the Susitna Hydroelectric Project.To date,APA has
received no response.
The first Review Group meeting is to be held January 20,1982,at 10:·00 a.m.
at the offices of APA.Please inform APA if you will be attending this
meeting and if you wish to participate in future mitigation planning efforts.
If so,we will ·send material for your review prior to this meeting.
Thank you.
Sincerely,
t '
."",I .
MG:adh
cc:APA
ACRES AMERICAN INCORPORATED
Kevin Young
Environmental Coordinator
Mr.Carl Yanagawa
Regional Supervisor for Habitat Division
Alaska Department of Fish &Game
333 Raspberry Road
Anchorage,Alaska 99502
Dear Mr.Yanagawa:
December 18,1981
P5700.11.92
T1360
...'-
--I
1
-
As a member of the group establ ished to review fish and wildl ife mitigation
recommendations on the Susitna Hydroelectric Project,I request your atten-
dance at a meeting on January 20,1982,at 10:00 a.m.,in the office of the
Alaska Power Authority.In the first week of January,I will forward for -your review,a prel iminary outl ioe of project operations,impact issues,and
mitigation options as prepared by our design teem and the fish and wildlife
mitigation technical core groups.I would appreciate receiving by January
30,1982,any written comme.nts you may have regarding our approach,results,-
or evaluations to date.
Following the preparation of the Feasibility Report,which will contain more
detailed information on project operations and our evaluation of these oper-
ations,.an opportunity will be provided for you to perform a more thorough
review.
If you have any questions relating to this meeting or the proposed functions
of the review group,please contact Mr.Dave Wozniak of APA or myself at
716-853-7525.
Sincerely,
Kevin Young
Susitna Environmental Coordinator
MG/jk
ACRES AMERICAN INCORPORATED
Consulting Engineers
The Liberty Bank Building.1.lam at Court
Sulfa/o.Ne':.Yor""14202
J.'
Telex S1·6~23 ACR.~S S\JF
Ot~er Offices:CC!..:""It'a,r.lD·P,:~sbwgh.PA:Rarei;)!".NC;Was~jr.gl0n.DC
~.
-
December 18,1981
P5700.11.91
T1361
-
Ms.Judi Schwarz
Environment a1 Eva 1 uat ion Br anch
U.S.Environmental Protection Agency
Region X
1200 Sixth Avenue
Seattle,Washington 98101
Dear Ms.Schwarz:
As a member of the group established to review fish and wildlife mitigation
recommendations on the Susitna Hydroelectric Project,I request your atten-
dance at a meeting on January 20,1982~at 10:00 a.m.~in the office of the
Al aska Power Authority.In the first week of January~I will forward for
your review,a prel iminary outl ine of project operations~impact issues~and
mitigation options as prepared by our design team and the fish and wildlife
mitigation technical core groups.I would appreciate receiving by January
30~1982,any written comments you may have regard ing our approach,results,
or evaluations to date.
Following the preparat ion of the Feasibil ity Report,which will contain more
detailed information on project operations and our evaluation of these oper-
ations~an opportunity will be provided for you to perform a more thorough
review..
If you have any questions relating to this meeting or the proposed functions
of the review group,please contact Mr.Dave Wozniak of APA or myself at
716-853-7525.
Sincerely~
f.eVI ....Y<.>w"".;//"1&
Kevin Young
Susitna Environmental Coordinator
MG/jk
ACRES AMERICAN INCORPORATED
Consulting Engineers
The Liber::;S<ln~aUjJ~lng ~.~a;n al Court
Bul!alo.Ne....Yor~H202
Tele;>hone 71e·El53·7:'25 Te!ex 91 ·E~:<3 ,t..CRES aUF
Other O'Lees:Colu:r.t.ia.r.~O:P,tls!;urgJ'l.PA·Raleigh.NC Washir.~lon.DC
Mr.Bradley Smith
Environmental Assessment Division
National Marine Fisheries Service
Federal Building &U.S.Court House
701 C Street,Box 43
Anchorage,Alaska 99513
Dear Mr.Smith:
December 18,1981
P5700.11.92
T1363
-
As a member of the group establ ished to review fish and wildl ife mitigation
recommendations on the Susit.na Hydroelectric Project,I request your atten-
dance at a meeting on January 20,1982,at 10:00 a.m.,in the office of the
Alaska Power Authority.In the first week of January,I will forward for
your review,a preliminary outline of project operations,impact issues,and
mitigation options as prepared by our design team and the fish and wildlife
mitigation technical core groups.I would appreciate receiving by January
30,1982,any written comments you may have regarding our approach,results,
or evaluations to date.-
Following the preparation of the Feasibility Report,which will contain more
detailed information on project operations and our evaluation of these oper-.~
ations,an opportunity will be provided for you to perform a more thorough
review.
If you have any questions relating to this meeting or the.proposed functions
of the review group,please contact Mr.Dave Wozniak of APA or myself at
716-853-7525.
Sincerely,
j:::e v '"1.y".I "'J I /"1 b
Kevin Young
Susitna Environmental Coordinator
MG/jk
ACRES AMERICAN INCORPORATED
Con~ullmg Engineers
The Lib(;rly Bank SuiJa,r.g.Il.ain at COLlrt
Telex 91·6':22 ACRES aUF
)
-
.....
,t
....
December 18~1981
P5700 .11.91
T1364
Mr.Al Carson
Division of Research &Development
Department of Natural Resources
323 East Fourth Avenue
Anchorage~Al aska 99501
Dear Mr.Carson:
As a member of the groupestabl ished to review fish and wildl ife mitigation
recommendations on the Susitna Hydroelectric Project,I request your atten-
dance at a meet ing on January 20,1982~at 10:00 a.m.,in the office of the
Alaska Power Authority.In the first week of January~I will forward for
your review,a prel iminary outl ine of project operations,impact issues,and
mitigation options as prepared by our design team and the fish and wildlife
mitigat ion techn i cal core groups.I woul d apprec i ate recei v ing by January
30,1982,any written comments you may have regarding our approach,results,
or eval uat ions to date.
Following the preparation of the Feasibility Report,which will contain more
detailed information on project operations and our evaluation of these oper-
at ions,an opportunity wi 11 be prov ided for you to perform a more thorough
review.
If you have any questions relating to this meeting or the proposed functions
of the review group,please contact Mr.Dave Wozniak of -APA or myself at
716-853-7525 .
Sincerely~
Kevin Young
Susitna Environmental Coordinator
MG/jk
ACRES AMERICAN INCORPORATED
Cons~I1:"~E:og,r.eers
T!1.:Lfberly e~~;.;e:",~!jn""9 r.~ain at Court.
euf~alo.'.JewYor~'~202
December 18,1981
P5700.11.91
T1359
Mr.Michael Scott
District Fisheries Biologist
U.S.Bureau of Land Management
4700 East 72nd Street
Anchorage,Alaska 99507
Dear Mt.Scott:
As a member of the group establ ished :~o review fish and wildl ife mit igation
recommendations on the Susitna Hydroelectric Project,I request your atten-
dance at a meeting on January 20,1982,at 10:00 a.m.,in the office of the
Al aska Power Authority.In the first week of January,I will forward for
your review,a preliminary outline of project operations,impact issues,and
mitigation options as prepared by our design team and the fish and wildlife
mitigation technical core groups.I would appreciate receiving by January
30,1982,any written comments you may have regarding our approach,results,
or evaluations to date.
Following the preparation of the Feasibility Report,which will contain more
detailed information on project operations and our evaluation of these oper-
ations,an opportunity will be provided for you to perform a more thorough
review.
If you have any questions relating to this meeting or the proposed functions
of the review group,please contact Mr.Dave Wozniak of APA or myself at
716-853-7525.
Sincerely,
Kevin Young
Susitna Environmental Coordinator
MG/jk
ACRES AMERICAN INCORPORATED
Con~Ulhng Engineers
The Liberty eanl<BUilding ~J.ajn al Court
8u~falo.r,ew Yor~1~202
-
Telex 91'6~23 ACRES BUr
-
II""'!
I
December 18,1981
P5700.11.91
T1362
Mr.Gary Stackhouse
U.S.Fish &Wildlife Service
1011 East Tudor Road
Anchorage,Alaska 99502
Dear Mr.Stackhouse:
As a member of the group establ ished to review fish and wildl ife mitigation
recommendations on the Susitna Hydroelectric Project,I request your atten-
dance at a meet ing on January 20,1982,at 10:00 a.m.,in the office of the
Alaska Power Authority.In the first week of January,I will forward for
your review,a prel iminary outl ine of project operations,impact issues,and
mitigation options as prepared.by our design team and the fish and wildlife
mitigation technical core groups.I would appreciate receiving by January
30,1982,any written comments you may have regarding our approach,results,
or evaluations to date.
Following the preparation of the Feasibility Report,which will contain more
deta i1 ed informat i on on project operat ions and our eva 1 uat ion of these oper-
ations,an opportunity will be provided for you to perform a more thorough
review.
If you have any questions relating to this meeting or the proposed functions
of the review group,please contact Mr.Dave Wozniak of APA or myself at
716-853-7525.
Sincerely,
{::z V I -..It-,.,.1J 1/"1 .(;,
Kevi n Young
Susitna Environmental Coordinator
MG/jk
ACRES AMERICAN INCORPORATED
Cons\Jlt,ng Engineers
The Liberly Bank Builclng.t.1ain at CCiurt
eu'~alo.New YOfk"H202
Te!ephone 716·653·7525 Te'ex 91·6~23 ACRES eUF
ro .......,..t"'."_"~"r ....L .........·.....An c·••,.~.,........0"C"_I ..:_...~,,...-"r...~"";.........,..,,,,,,,nr
Busitna Hydroelectric Project
Fish and Wildlife Mitigation
Review Group Meetin?,
January 7.1982
P5700.".70
T.1395
Mr.Carl Yanagawa
Regional Supervisor for Habitat Division
Alaska Department of Fish &Game
333 Raspberry Road
Anchorage ..Alaska 99502
Dear Hr.Yanagawa:
Enclosed for your review:
1)Sus1tna Hydroelectric Project Fish and Wildlife f1it1gat1on Policy.
2)Draft Analysis of Hildl1fe i'1itiqation Options.
3)Draft Analysis of Fisheries Mitigation Options.
These documents will be d1scus~ed at the Fish and Wildlife Mitigation Review
Group Meeting to be beld at 9:00 a.m.(note change of time from letter
of Decembar 13,lS81)on January ZQ,1932 at the office of the Alaska
Power Authority,334 West 5th AvenUE.Anchorag~I hope you will be
able to attend the meeting'.
S'fncerely yours t
Kevin R.Young
Susitna Environmental Coordinator
MHG/jmh
Enclosures
-
-
..,
I
-
""lI
I
-~
" --RECEIVED
I DEC l 4 1981 -
1D S.. I' a WIE I $1J&¥[ @W W~§J$~~ I M.Ja.A POWER .A.!.Irne~
.IZl e. 4ll+ AYEioHJE __ -
~~---·
DEP..~RTME~iT OF NATVBAL 11£SOIJRCES
/XVfS1Q'IOF RESEARCH&IJE.'tiEl.OVENT
('.
~ember 9, 1981
Eric Yould~ Ex~~ive Director
Alaska ~r Authority
333 west 4th Avet~ue, Suite 31
Anchonge, AA 99501
Dear Mr. Yould:
.
Several state and federal agencies. in recent weeks have beEn asked to··
formally reviev and proYide ~ts on several doc:uraents relating to
the proposed Susitna Hydroelectric Project. Although the Susitna Hydro~
electric Steering Caanittee 1s an organization that is designed to pro-
vi.de info.rma.l advice and CQDi!eflt on matters pertaining to the Susitna
Hyljroelectric Project, JDOSt nf the steering ctzmittee members receiveii
the formal agency response ~t that was sent to t.r.e agency directors
ami c0ii1llissior.ers by Acres. lt is primarily because of that fact that the
steering coamittee feels that it is appropriate and necessary to send
ALASKA Po ER a letter to you at this time with respect to the Alaska Power Authority's AU<HoRt~ re--quest for formal agency coorcfir,ation and review on elements o:f the Susit:na
SUS11:N.A H,ydroelei:tric Power Project.
FILE PJJOO JAs a result of concerns exj>ressed t;y ~rs of the stwring <;Qil!Olittee, we
· convened a !Sei.!ting on Oece:lber 2. 1981 of the steering CC~RRittee w1 th
EQUENCE ~-;_;Robert Mchn and Dave Wozniak of the Alaska Power Authority att...onding.
; d/8::> , fAt this steering cCI!lnittee ~ting, ;se were provided with our first gH~se
' ' of how the Alaska Power Authority intends to conduct ti".;e fon:;al consultation
':i and coordination required for this proje<:t. The formal coordination process
that is proposed in t."le August 12:., 1981 At=res doc~~nt to Eric Yould. subject~
~susitna Hydroelectric Project Formal Coordination Plan•~ is conceptually
·1 ~z.w J-fappropriate but incomplete and deficient. The following are proble:Ja areas
· --1 in the proposed fon:-al coordination plan as described above:
SNT
l
\
1.. The formal coordination pian as proposal by Acre-s has not been
formally or informa11y discussed and reviewed with the agencies
from which the P~r Authority requires responses. This is pro·
bably th€ rr-~st significant obje-ction we have Yith the approach of
Acres. The contractor sent letters to heads of state and federal
age,rcies requesting specific ~~ts on detailed studies and
reports associated with the Susitr~ Hydroelectric Project without
having a COR~lete understanding of the responsibi1ities and concerns
of agencies.
2. Se;.~ of the re;x>rts 'foihic..h agencies will be requested to fol"n2Ily
respond to will not be prec~-te-d by the reJevant data and study
findings f:"'CC )thich the s~ry report and forca.1 agency coar.ents
should be based. An obvfous e.xa..r:;p1e is tr~ revi~ of the 1981
draft annual re?Qrts is required 2 months after the draft feas1-
bil ity report reYiew. _
-
-
-..
-
-
-
-
-
-
-
-
-
-
-..
1-
l
-
-c-
1 i-
1
-~
i
j 1-
-
-
~
3. The proposed formal ccordination plan, as described in the AIJ9ust
12, 1981, doctarent fraa Acres to APA does not accurately describe
all the parties and agencies who should receive certa.fn doc\IE!\ts.
The steering cta~ittee feels tt-.at the formal COOS"lltation process should proceed
in a racre coordinated and organized fashion in order to avoid unnecessary
c:cns~ caused by the problems we r~Ave fdentified abaft. ie offer·'tfle
following suggestions and ccmnents:
l. we recaiEf.!nd that the APA, as soon as possible, convene a formal
meeting w'ith agencies to establish the schedule and the prcc.ess for
formal coordinition for this project. In light ef the proposal to
have a ooaplete draft feasibility plan avai1ab1e on March 15, 1982,
we urge that the Power Authority convene this D5!eting and get this
ara.tter sorted out with the agencies before January 1, 1982.
z. The formal coordination list that will te used ft>r this project
needs to be reviewed and approved by ager.cy representatives to
ensure that it is ca;plete and cor::prehensive. Attached to this
letter please find a series of additions to the 8/12/81 Acres
list.
3. R.e'iiew of the proposed F .E.R.C. regulations in volr.se 46 number 219
of the Federal Register dated 11/23/Sl identified a list of infonua-
tion categories to be include<! in Exhibit E. etcparinq these re-
qufn;g,ents to the 9/12/81 proposed coordination pian, ..e find the
followir~ agency review categories missing:
i) SocioecG:'KSic s~~ies
ii} Alterr~tive dEsigns, locations and energy sources
Hi} Geological and soils studies
We agree wi~~ the APA epproach of requesting early for~l re~i~ ar~ comroents
on policy related doet.Eients that are re~uired in o-rder ~ put the project
proposal together. For e~le, the re-qw=st for review of the fish and wi1d-
1ife mitigation policy before the specific mitigation proposal for the project
is sul:rnitted to agencies for revi~ and cCGiilE!nt.
In sumr.ary. the me:nbers of the steering cc::nittef! found u'le proposed fonr.a1
coordination plan to be revealing and useful to better u~rstand how ag-encies
~111 have to respond in order to meet the needs of APA. •e are particularly
encourage<i t!) s~ that t.rze instreas1 fl<itr~ study plan is p1armed to be available
for review and c~t by agencies in Oecerber of 1981~ Since this is such a
critical el~nt of the Susitra Study P1an, this deserves attention and re-
sponse f~ the agencies as soon as possible •
•
_)
-" -
c-_
.. -
--
t.-
..I
J
lhe steering cca1ittee hopes that you wilT find the-'"~ caanents and~
tions useful anci constructive ar.d is anxious to continue to. provide infon=al
review and advice ta the Power AutbCJrity. .J
Sincerely yours,
ru~
Al Carson, Chainean
SiJsitna Hydroeleetric Steering Coa!littee
AC:db
cc: Steering Cc&rit"...ee
Reed Stoops
Quentin Edson, Director, Division of Environmental Anaiysis, F.E.R.C.
A .. Starker leopold
•
' ...
-'
..J
.I
-
...
! ...
..
I
' ..J
l
• ..J
-
' ...
..1
' ..1
..
-
• --
,.
··-(.·
-
t.-
. 12/9/81
Reccanended additions to the 8/12/81 agency coordination list for Susitna
Hydroelectric Project.
Welter Qualfty and Use
Alaska DKR, OF & 6
• DEC· .
u.s. Anror~ Corps of Engineers
• EPA, HPS
• F & WS~ GS
• BLM,lttfS
AEIDC
Fish, Wfldlife and Botanical
?_
Alaska Of & G
. • DEC
• DtCR
U.S. F & WS, GS·
" ~S~ EPA
• BLM
AEIOC
Historical arid Archeological
Alaska ONR {SHPO), Of & G
• OCRA
U.S.. NPS
• BUt
AEIOC
Recreation
Alaska DHR, Of & G
U.S. NPS
• F & WS, r~S
Mat-Su BOrough
AEIDC
Aesthetics and Land Use
Alaska ONR, OF & G
U.S. BLM, F & WS, NPS
CIRI
AEIOC
General
OPOP., OOf, Governor's Office
'
~
, ....
~
,r
Mr. David Haas
WIL.L.ETT ..
WITTE ..
BERRY \
r
,.. ,., t
~CIM'f" f/"'--S.
LAMB l ,,
L.AWRENCE'
-ta
iff
1v
a
te-Federal Assistance Coord1nat6r
te of Alaska
ce of the Governor
sion of Policy Development
d Planning
lout hAW 17~ ,_ au, Alaska 99811
December 9, 1981
P5700.11.92
T.1338
SINCL.AI_B 11Aar Mr. Haas: Sus1tna HYdroelectric Project
H
.o.. (~·'
·~t-:l-)c.: Fonnal Agency Coordination
lt. '' /_ ~
CA-RLSON
/ _, s
FRETZ
JEX )
L.OWREY
SINGH
~./'I/ I
~"'IV l q
HUSTEAD
BOVE
.. )
w111 hopefully address the issues raised in your letter of December 2,
•
We will send future correspondence to Ms. Wendy Wolf at the Alaska Office
of Coastal Management. Thank you for notifying us of change in personnel.
We will send you copies of all future reports issued formally for agency
review. MY letter to you of November 24. 1981 listed all recipients
and the reports they w111 receive.
This formal agency review process we are conducting is for several
purposes. Although we have had many meetings with agency personnel, we
....
...
-
....
-
-
-
.,.j
....
....
CHASE .,.j have been informed their views do not necessarily represent those of their
agencies. To insure concerns of the agencies are addressed and incorporated, ,
l
1. h -~ ~
./V..,.
where possible, into project planning and to receive agency input on the
studies, we have implemented this formal process whereby project reports
are sent to agency Commissioners and/or Directors. In addition, the
Federal Energy Regulator,y Commission requires documentation of agency input
\
into project planning and mitigation.
4) The Feasibility Report will be issued by the Alaska Power Authority (APA).
By copy of this letter, I will request you be placed on the distribution
11st.
5) The Environmental Impact Statement for this project will be prepared and
issued by the Federal !gengy Regulatory Commission, on the basis of a
license application to be submitted by APA, should a decision be made to
do so by the state. If you wish to coordinate mailing of this document,
I suggest you contact Mr. Quentin Edson, Chief of the Environmental
Division in Washington, D.C.
-
IIIII
-
IIIII
-
-
-
:., . -r
( ..
-
-
-c.
Mr. David Haas December 9, 1981
page 2
I hope this clarifies matters. If.Y.you have further questions, please
call.
MMGJJmh
cc: E. Yould, APA
Sincerely,
~
John D. Lawrence
Project Manager
c·
•• ..• I
' I
U. S. E N V I R 0 N M E N T A l P R 0 T E C T I 0 N A G E N C Y
~~,1EO S7".ot1':
. ~IS' REGION X
~ .......
< fili..A "G ~~~ ~ (!) ~ "(" 1-~ 0~
1200 SIXTH AVENUE
SEATTLE, WASHINGTON 98101
RECEIVE_D
DEC 2 8 1981
ACRES Alili.tUiiiifi I:~GDRrDRAifn
-4( PRO"t~v"'"'
REPlY TO M/S 443 ATTN OF:
DEC 2 11981
John D. Lawrence
Acres American, Incorporated
The Liberty Bank Building
Main at Court
Buffalo, New York 14202
SUBJECT: Susitna Hydroelectric Project, Summary Annual Environmental
Report-1980 and Transmission Line Corridor Screening Report
Dear Mr. Lawrence:
Thank you for sending us the above reports for our review. We have also
received the Development Selection Report and will be forwarding our
comments to you on that report before the end of December.
ALASKA PowER We appreciate the extensive coordination effort and the opportunity to
AUTHORITY • • SUSITNA rev1ew and comment on Sus1tna reports as they are prepared. I further
--------1 appreciate your attempts to ensure that the views of the Agency are
FILE P5700 adequately reflected in this process. While we have been coordinating
· with the Susitna Interagency Steering Committee, our budget restrictions
SEQUE~CE NO. have limited our active participation more than I would like. In this
F. ..J..J/1 regard, it would be extremely helpful to us if you could provide us an
, I. !overview of your consultation plan and the schedule for future reviews. !z ~ ~ ~This will better enable us to give you timely comprehensive comments on ig ~ != ~;:; the various segments of the study, with the overa11 project perspective
'U :n "" • • d 1 -z : o-... 1 n m1 n I .... -~ -•
I ~c:..v I EPA is particularly interested in information on wetland mapping, water
Ll-' 1.:.:..::._ quality and water quantity modeling and project alternatives. The 1980 ~~-~-~ Environmental Report appropriately points out the interrelationships and
t JVG importance of these areas to wildlife survival and downstream fish
1
-~" --ecology. ~owever, i~ does not cover EPA's areas _of interest directly.
-j-p 5 We waul d 11 ke to rev1ew the reports on these subJects when they are
~~~flf--avail able.
----·--· MRV
L=J""HRC
I f-1--1 '--~-: I -
-
IIIII
-
-
IIIII
-
IIIII
-
-
IIIII
IIIII
-
IIIII
IIIII
-
-
-
-
-
i
-
-
-
-c
-
_)
2
We support the emphasis in the Environmental Report and related studies
on identifying ways to minimize the environmental impacts of the Susitna
project. In particular, selection of the access route and type of access
is an issue with long term environmental consequences which offers many
opportunities for minimizing impacts. EPA supports the concept of
minimizing impacts by use of a single corridor for both access and trans-
mis.sion needs, as pointed out in Doth the Transmission Line Corridor
Screening Report and the Environmental Report. We encourage you to
incorporate these kinds of suggestions from agencies and the Steering
Committee into the project selection, construction and operation plans.
Such commitments will certainly positively influence reviews of any FERC
license application.
We have some concerns with the conclusions about the Centr.al Study area
in the Transmission Line Corridor Screening Report. There appear to be
different opinions on the environmental consequences of selecting Corri-
dor 1 versus Corridor 14. We feel that additional areas should be
included in future studies of the central corridor, to provide a broader
data base from which such conclusions can be drawn. More specifically,
in this area, Corridor One (ABCD), which roughly follows the south side
of the Susitna River, is the recommended corridor based on Acre•s techni-
cal, economic and environmental criteria. Corridor 14 (AJCD) follows the.
same route as Corridor 1 from Gold Creek to Devils Canyon, but crosses to
the north side of the Susitna River for the section from Devils Canyon to
the Watana dam site. Corridor 14 has technical and economic ratings as
high as Corridor 1, but was not recommended because of environmental and
land use conflicts in segment CJ. On solely environmental grounds, it
appears that an access route similar to Corridor 14 is preferred to
Corridor 1 by Doth Terrestrial Environmental Specialists, Incorporated
(Environmental Report page 73 and 82) and the Susitna Hydroelectric
Steering Committee (letter from Al Carson, Chairman, to ·Eric Yould, dated
November 5, 1981.) Therefore, the areas of the central corridor to be
further studied should include the north side of the river between Devils
Canyon and the Watana dam site to encompass segment CJA as well as
segment CBA.
One reason for the different conclusions regarding the environmentally
preferable route between Devils Canyon and the Watana Dam site may be the
Environmental Report•s and the Steering Committee•s identification of the
most environmentally sensitive areas, which then have the highest priori-
ty to be avoided. It may be desirable to use a similqr approach during
the more detailed route selection studies, especially in areas where
wetlands must be crossed. Identifying and then avoiding primary and
secondary impacts to the most valuable wetland habitats should be an
important part of the more detailed studies of all three transmission
study areas.
c
3
We appreciate the opportunity to review this report. Please contact me
or Judi Scpwarz, of my staff, if you would like to discuss our comments.
We can be~eached at (206) 442-1266 and (206) 442-1096, respectively.
Eric Yould, Alaska·Power Authority
Al Carson, Department of Natural Resources
-
-
-
-
....
-
-
-..
..
-
-
-
-
-
-
..
-
-
-
-
-
-
-
-
-
-
-
__ )
~¥&¥~ @~ &~&~rK\&
DEPT. OF ENVIRONMENTAL CONSERVATION
Mr. Eric P. Yould
Executive Director
Alaska Power Authority
334 West 5th Avenue
Anchorage, AK 99501
Dear Eric:
_)
RECEIVeD
JAYS. HAM~ ~~R¥%}
~SKA POWER AUTHORITY
POUCH 0 -JUNEAU 19111
December 21, 1981
The Department of Environmental Conservation has been contacted by
Acres American requesting formal coordination and review on five
Susitna Hydroelectric Project documents. These requests were
received in October and November, 1981. There apparently is some
confusion as to what exactly was being requested. In his letter
of November 16, 1981, Mr. John D. Lawrence of Acres clarified the
situation and extended the review period to 45 days. On December 2,
1981, the Susitna Hydroelectric Steering Committee met with
Mr. Dave Wozniak of your staff. Dave presented-the Acres coordina-
tion plan. This document, plus Dave Wozniak's briefing, provided
a clearer understanding of what we must do to be responsive to the
needs of APA for the Susitna project.
As noted by the steering committee's letter to you on December 9,
1981, there are several problem areas with the formal coordination
process outlined by Acres. We are particularly concerned that DEC
was not inclutled in the water quality and use group. Since DEC sets
State Water Quality Standards and regulates water quality throughout
Alaska, I feel our inclusion on the water quality review group is
necessary.
Review of the coordination plan leads me to recommend that it would
be useful for APA and the appropriate agencies to design a single
continuing process for review and comment on the Susitna Hydro-
electric Project. Since we are dealing with a State-sponsored
project, I believe it is appropriate and timely that the State
agencies and APA also determine the funding and personnel needed
for these efforts. Our contacts for this matter are Bob Martin or
Steve Zrake of our Anchorage Regional Office. They can be reached
by phone at 274-2533.
Commissioner
__ ) ----..., _ '-' ..L I i~ u
United States Department of the Interior l
FISH AND WILDLIFE SERVICE
1011 E. TUDOR ~D.
RECEIVED]
IN REPLY REFER TO:
WAES
-
ANCHORAGE, ALASKA 99503
(907) 276-3800
DEC 21 1981 ] J -
7-~ • Eric Yould
ACRES 11. •••...... .,;~ .i 4 iuuuairORATED
r
~
· --.J E1 • D" t -,1 ~ xecutJ. ve ~rec or
-· !J ,_] 1-Ah.ask.a Power Authority
i-~ li l9.fo31!h:;.:~~ !~::: 99501
-15 DEC l~~1 -
: ~.. ~ j ~Drar Mr. Yould:
i.·=:: ~o';::;; ... ~-= ! __ ~ _, -Tpe u.s. Fish and Wild~ife Service (FW~) has been contacted by A~res American
! !7 ·-l Jt ...... n~garding formal coordJ.nation of certaJ.n aspects of the feasibilJ. ty study for ~---.[/_Y-~ile Federal Energy Regulatory Commission (FERC) license application for the _.
r----i~r1 sitna Hydroelectric Project. To date four document packets have been sub-
~ _:_ · -:--m tted to us for formal review. These are the 1980 Environmental Studies
~--:---·1_1---..Abnual Reports, Transmission Line Corridor Screening Report, Development 1---~ -~. J sklection Report, and the Fish and Wildlife Mitigation Policy.
. ~. ,, L I
1--------
1 1 ! Initially, some confusion arose over these requests. In his letter of
~-~--r.~·\l~bvember 16, 1981, Mr. John D. Lawrence (Acres) identified the sources of !-:-.--·. --~--dmfusion, explained which documents were to be reviewed and extended the
~--.---~-1 cbmment period to 45 days. While we appreciate this clarification, we feel a
J-~bre formal and explicit plan for formal coordination of the Susitna Project
-~hst be developed. Mr. David D. Wozniak of your staff addressed the Susitna
,.._ ., -_~:__liydroelectric Steering Committee on this subject at their meeting of _ --i---~ _ ____pecember 2, 1981, and presented th7 coordination plan developed by Acres
:~·~ -~f?-/J1..1etter of August 12, 1981, from John D. Lawrence to Eric Yould).
1 ! • _ /~Mr. Wozniak's briefing was very beneficial to our understanding of this pro-
----c~ss; however, we feel it is important that the Alaska Po~er Authority (APA)
understand the position of the FWS on this issue. The FERC regulations
(Federal Register Vol. 46, No. 219, November 13, 1981) require a FERC license
application to document coordination with federal resource agenci~s in the
Exhibit E. These agencies must be afforded a minimum of 60 days for review
and comment. As such we disagree with the 45-day comment period suggested by
your contractor. Additionally, there are several deficiencies within the
-
..,;
...
-
...
-
Acres coordination plan which concern us; the first of these being the fact _,
that no formal discussion as to this coordination has occurred. Thus,the
contractor arbitrarily decides which documents are of concern to a particular /JJSr~· agency, and what level of coordination will take place. Formal contact should-
(~ work to insure that all agency concerns and consultations are met so as to JJJL comply with the intentions of the FERC regulations. With the exception of [1;1~~~ certain policy statements (e.g. Mitigation), the Acres plan calls for formal _, ~~. (~ ~agency input before necessary background reports and data are available. An
~~)/ obvious example of this is found in the formal coordination plan-product list
;Qe/
hie
-
-
-
,..
-·
-
-
-
-
-
-
-
-
-
-
-
(attached to the aforementioned letter dated August 12, 1981) ~here the Draft
Feasibility Report ~ill be released for agency revie~ t~o months prior to
release of the 1981 Annual Reports. It is unrealistic to assume that
m2aningful comment can be generated in the absence of such information.
We believe a meeting should be arranged by your office to define the objec-
tives of the required coordination and to develop a plan suitable to both the
APA and the federal resource agencies. In the interim ~e ~il attempt to
respond in a timely manner to all appropriate project documents, but ~ill
~ithhold comment on those documents which must be supported or clarified by
the results of other studies.
Sincerely,
Actirn! ~2!.::0£~
cc: FWS/ROES, WAES
Quentin Edson, Director, Div. of Env. Analysis, FERC
NMFS, EPA, NPS, BLM, USGS, ADEC, ADF&G
Carson/ADNR
Lawrence/Acres American
_) UNITED STATES DEPARTMENT OF COMMERCE
National Oceanic and Atmospheric Administration
NationaZ Marine Fisheries Service
P.O. Box 1668
Juneau, ALaska 99802
December 23 , 1981
Mr. Eric Yould, Executive Director
Alaska. Power Authority.
333· W. 4th Avenue
Anchorage, Alaska 99501
Dear Mr. Yould:
.REC~lVI:D
DEC 3 11981
tu:ASKA P9WS1 AUTH0RJ1Y
The·National Marine Fisheries Service has been contacted
by ACRES American regarding formal coordination of certain aspects
of the feasibility study for the Federal Energy Regulatory Commis-
sion (FERC) 'license application of the Susitna Hydroelectric
Project. To date four (4) documents have been submitted to us
-
-
-
-
-..
for formal review. These are the 1980 Annual Reports, Transmission -
Line Corridor Screening Report, Development Selection Report and
the Fish and Wildlife Mitigation Policy.
Initially, some confusion arose over these requests. In
his letter of November 16, 1981, Mr. John D. Lawrence (ACRES)
identified the sources of confusion, explained which documents
were to be reviewed and extended the comment period to 45 days.
While we appreciate this clarification, we feel a more formal and
explicit pl~n for formal coordination of the Susitna Project must
be developed. Mr. David Wozniak of your staff addressed the
-
--
Susitna Hydroelectric Steering Committee on this subject at their
meeting of December 2, 1981, and presented the coordination plan
developed by ACRES (letter of August 12, 1981, from John D. Lawrence•
to Eric Yould}: Mr. Wozniak's briefing was very beneficial to
our understanding of this process, however we feel it is important
that the Alaska Power Authority understands the position of the -NMFS on this issue. The PERC regulations require a FERC license
application to document coordination with concerned federal agencies
under Exhibit E. Agencies must be afforded a minimum of 60 days -for review and comment. 18 CFR §4.4l(f) (46 FR 55926, 55937;
November 13, 1981}. We interpret this requirement to apply to
each document submitted to us for consultation, including in
particular the drafts of Exhibit E and the license application
itself. Moreover, we expect that while there may be documents
which can be reviewed by us in less than 60 days, there are very
likely going to be instances where we will need more time than
that in order to perform a thorough review.
One reason we expect to be accorded longer than 60 days
for consultation in some instances, is that formal agency input
is often to be solicited before necessary background reports and
-
-
-
-. ~'•
. ' ;;; r. ,, .
. · \. ~"!-.. .... ~
\ -.:. ~. I
••• ~>' -
-
-
-
-
._
-
-
-
-
-
-
-
-
-
-
_)
2
data are available. An obvious example of this is found in the
formal coordination plan-product list, where the Draft Feasibility
Report will be released for agency review two months prior to ··
release of the 1981 Annual Reports. It is unrealistic to assume
that meaningful comment can be generated in the absence of such
information.
We are also concerned about another apparent deficiency
in the proposed coordination plan. The decisions as to how
coordination is to proceed are left to the contractor, who has
discretion to decide which documents are of concern to a particular
agency, and what level of coordination will take place. This
approach has the potential for having the concerns of some agencies
overlooked, and we would urge ·that the contractor make a special
effort to insure that the consultations are as inclusive as
possible.
We believe a.meeting should be arranged by your office
to define the objectives of the required coordination and to
develop a plan suitable to both the APA and the federal resource
agencies. In the interim we will attempt to respond in a timely
manner to all appropriate project documents, but will withhold
comment on those documents which must be supported or clarified
by the results of other studies.
c··
-r:-) ......
Ci
C'.J'
'"'-· N -
L7619{ARo-P)
Mr. Eric Yould, Executive
A1aska Power f~thor1ty
33~ W. fifth Avenue
Ar~horage, Alaska 9?.SQ1
De!r Mr. Yculd:
Director
·-· -:;_ L---,:._,_ .:.---·
RECEIVED
JAN 0 4 1982
...
ACR .. .; ·•~'-···~;•j• !n~urtrORATED ...,
8 0 DEC 1987
..,;
ALASKA .. WEI
AUTHORITY
SUSIT'i'JA ---
FILE P.,..i'OC
SEQUENI '~ N
-c9 d/(11 f.,/
z! :i I ~ 'I QIC: C:
In response to a HcvEUlber 16, 1931 letter frc-m tht: J'\cr~s American lnc. P ~~~: ~ l
:-:ar,ager, Hr. John D. La\trcnce, we have the followin-g ccnnaents concerning ~ :~-_:_
Susitn.~ project rep.orts. The reports reviewed include: 19SO Environment l!_l_~c __ Su:~1ary Report {V~y 19Bl)i Transnission Lfne Corridor S~reening Report (S pt~~.-
1?:J1}; and the Developr;;c-nt ~lection Report (October 19dl). I ; :r-.o,
-ljQ'-·--
Provision for cultural resource ider.tificat1or: and maoa~Jtrnent appe:ars to t·~:;: -b,v .. ---
arpropriate and ad~quate. f,lso. it would appear that recrr:mtior. is be1ng --~_:1 ;~d-
ad~qudtcly a.:!dressed bv the o1ann1 nry process. ------:·:-
J · · I PG '
to be very ad.:ouate. This a~ency does net recor.r.cnd a. particular basin p wQr s '1 r, l
c~!Vttlopr:.-errt plan. Eot~~ver~ we do note on pa~e D-26 that the tunnel schffi~ 1js,-o\~ .-~-
recogniz<;c t;y th~ report as be1n~ enviro~enta11y surericr, aild 'r.=ould prc::fet1ve 1rv,·R"·r-
oany of the resuurc~ values curr~nt1y assoc1~ted with the Devil Canyon. rii'H-Rc, 1-
-~-
It ~ould be helr.ful to ttm reildcr 1f an index could be 1nclu.1ed with each 1-1-1--...-:-
nport cr per:1ap$ rrcpared s~r;,arate1y for the entir!! series of project re:!ct!ts.l t
~-;~ look fcr'rlard to th-e op;Jortun1ty to r~v1-::w scbs~quent prc,jcct re;:orts. ___,_! __ ~~-_._
audition to t•cfr.g 1t~ciudt:d 1n th.: historical an<: archeological, ~nd recrt: n \
SrOIJj:S id~l~t.1fi€J fer fan·~l COOrdinatiOn 2 thiS ~·~~ncy Should perhil!)S alS f"' Fl~~,!
inc1udt.:c \dthin the water quslh.y and us;?~ zesthetics and 1and use srouns ~as fie-·---
~r(! bte:rt:st~c in project relctcc recreation 1:~:~;t~cts Uiat w1i1 occur ~ithin an<! ...,
l:f:ycnd the: project bnur.dar.'l.
Sh.c:;rdy~ ...
'! r;/ Douglas G. C""arnoc~ ...
~ ACting;:(:~ i<A1d D1r<:·ctor
c:.. ·1 · · r· i .. •• J\ .-;~r.a .-.e:"I Oo~ ~ ~ -.c
c:'l ..-s.. cc: ..,.
~ .:o·,;. D. Lin;r.:~;c::. ;t.cre$ k·•.:r1c.::r. 1.-.c •• ~a-J liberty Gank ~uildit~g. ~uffttlo, :-:a:
Yv rl.: it.~'.)? -
-
G .. ,...,.~~,· .. ·.-'-·'
JA fi ~~;;0~~--~:t;RNIJ~I
j ~·\~ 0 l\ 1 ~'-'
-/
/ -"' . ~?-
•• l'\ \ tS.Rt~ Mfi.R'\~hi• h ......... .
~lT&lT[ @~ &~&~~~
-
-
-
DEP.-\RT~It:~T OF FISII_-\,1) G.-\nl-:
December 30, 1981
Mr. John D. Lawrence
Project Manager
Acres American, Inc.
OFFICE OF THE COMMISSIONER
The Liberty Bank Building, Main at Court
Buffalo, New York 14202
Dear Mr. Lawrence:
P.O. BOX 3-2000
JUNEAU, f:LAS/fA 99802
PHONE: ~ 907) 465-41 DO
)l,·' (~
The Alaska Department of Fish and Game has reviewed the 11 Susitna Hydroelectric
Project Fish and Wildlife Mitigation Policy 11 dated November 1981 and has several
comments to offer. The Department is drafting a mitigation policy approval we
---____ . int~d to use for all hydroelectric projects throughout the State. We
-' ALAsKA Po~p~re1~iate your effort but feel our parallel effort is the alternative we select
'' AurHo~1 tb ta e. In the interim, however, I have provided comments to your document
SUSI_~_r:i-fla.:t.... an be used to improve your policy as drafted.
-;J FILE P5700 I ~_gji.Milri c Comments
J
:---=--\ -~CQ!Jj;'['r:-fHJ ; -lt--~~.,).:.:v~~-~~Section 1 -Introduction
~0 ~~~ ~-l ; ;' 1n thi~ section which reads as follows, we recommend inclusion of the
,.., , r' ,; "" underl1 ned phrase. tJ I~···.. .',! -~ l <1~!-:-;-.~~.-;-=-I·A ma~date of the ~laska Power Authority (APA) charter is to develop
_
1
_J __ -..... · ;_ ·. · 'Supp 1 1 es of e 1 ectn ca 1 energy to ~eet the present and future needs of the
I ~1 I ptate of Alaska. APA also recogn12es the value of our natural resources
.-:---·.-::-:--~nd accepts the responsibility of insuring that the development of any new -;-· -
0
-projects is as compatible as possible with the fish and wildlife resources
-~.~-~,,...~., · nd he habitat that sustains them) of the State and that the overall
-[----~~~' cts of any such projects wi 11 be beneficia 1 to the State as a whole .
.,...,...,
1
_ . ... iin this regard APA has prepared a Fisheries and Wildlife ~1itigation Pol icy
__ . "for the Susitna Hydroelectric Project as contained herein.11
-=1=> ··-~-~ 1Comment: The primary goal of mitigation is to avoid, minimize, rectify,
1 1 1 :. : . :reduce or compensate for impacts on fish and wildlife habitats.
,-.. '---i
-
1
-.. 2.---Section 2 -Legal t~andates -~=! ·:~In thi~ section which reads as follows, we suggest inclusion of the
. _l_r~; ... .,:._,: ...,_· _ unJerl1 ned phrase:
.. I : : (.2" ~:.,__ -• j-~--· --11 ~r
-,-~--·-;
' I ]Afii£1-i
-~ .. , .• l J
• I . -
Mr. John D. Lawrence -2-December 30, 1981 -
"There are numerous state arid federal laws and regulations that ~
specifically require mitigation planning. The mitigation policy and plans
contained within this document are designed to comply with the collective
and specific intent of these legal mandates. Following are the major laws ..
or regulations that require the consideration (and eventual implementation)
of mitigation efforts."
Comment: Consideration of mitigation is not an end in itself, the
implementation of mitigation is the eventual goal and obligation which the
APA must meet under the terms of State and Federal law and regulation.
-
-3. Section 2 -Protection of Fish and Game
4.
In the first paragraph, first sentence, that reads as follows, we suggest ..
the underlined phrase be inserted:
The Alaska state laws pertaining to the disturbance of streams important to_.
anadromous fish address the need to reduce (or prevent) impacts on fish and
game that may result from such action.
Comment: Avoidance as well as minimization of impacts is also of concern
to AOF&G.
Section 2 -Federa 1 Energy Regula tory Commission, 2nd paragraph
We suggest the paragraph include a statement which indicates measures of
mitigation as well as facilities for mitigation be described. To describe
only facilities suggests that only engineering solutions for mitigation are
considered. It will be necessary to describe any measures for mitigation
that may involve, for example, in-kind replacement of habitat or avoidance
of impact alternatives.
Comment:·· For this statement to be an accurate portrayal of FERC
regulation, this addition is suggested.
..
..
-..
...
5. Section -3.3 Implementation of the Mitigation Plan
In the first paragraph of this section, it is stated that, "Prior to
implementing the plan; an agreement will be reached as to the most
efficient manner in which to execute the plan."
Comment: It should be stated with whom this· agreement is to be reached.
Perhaps suggestions can be worked out with the Su Hydro Steering Co~mittee .
Also it is stated in the second paragraph of this section, "Realizing that
a mitigation monitoring team will be necessary to insure the proper and
successful execution of the mitigation plan, part of the plan will detail
the structure and responsibilities of such a monitoring body."
Comment: APA should be aware that this monitoring body or its functions
will not supersede individual agency mandates.
..
-
...
..
...
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Mr. John D. Lawrence -3-December 30, 1981
6. Section 3.4 Modification of the Mitigation Plan
In the second paragraph of this section which reads as follows, we suggest
the insertion of the underlined phrases:
11 The mitigation plan will be sufficiently flexible so that if data secured
during the monitoring of fish and wildlife populations and habitats
indicate that the mitigation effort should be modified, the mitigation plan
can be adjusted accordingly. This may involve an increased effort where
impacts failed to materialize as predicted. Any modifications to the
mitigation plan proposed by the monitoring team will not be implemented
without consultation (and approval of) appropriate state and federal
agencies and approval of APA. The need for continuing this monitoring will
be reviewed periodically. The monitoring program will be terminated when
the need for further mitigation is considered unnecessary.11
Comment: APA approval alone does not supersede the mandates of state and
federal agencies to assure that mitigation to be performed is prudent and
feasible and in concert with what is known about project impacts.
7. Section 4 -Approach to Developing the Fish and Wildlife Plans
The third paragraph of this section reads as follows:
11 Following the identification of impact issues, the Core Group will agree
upon a logical order of priority for addressing the impact issues. This
will include ranking resriurces in order of their importance. The ranking
will take into consideration a variety of factors such as ecological value,
consumptive value, and nonconsumptive value. Other factors may be
considered in the ranking if deemed necessary. The impact issues will also
be considered in regard to the confidence associated with the impact
prediction. In other words, those resources that will most certainly be
impacted will be given priority over impact issues where there is less
confidence in the impacts actually occurring. The result of this dual
prioritization will be the application of mitigation planning efforts in a
logical and effective manner. The results of the prioritization process
will be sent to appropriate state and federal resource agencies for review
and comment.11
Comment: The Department of Fish and Game does not consider what appears to
be a subjective r·anking of resources in their 11 0rder of importance 11 to be a
satisfactory approach to addressing impact issues. There is no substitute
for a factual assessment of data voids, studies to fill these voids, and a
rational approach to impact assessment based on factual evidence. Ranking
as suggested here only supports this Oepartment 1 S long-time conviction that
adequate information to make reasonable impact analysis and mitigation plan
development cannot be done in the time frame established for the FERC
license application by the Legislature and APA.
The fifth paragraph of this section states:
'i· _ ... ~·-·
...
Mr. John D. Lawrence -4-December 30, 1981 ..
"Mitigation for each impact issue wi 11 be considered according to the types~
and sequence identified by the CEQ (Figure 2). If a proposed form of
mitigation is technically infeasible, only partially effective, or in
conflict with other project objectives, the evaluation will proceed to the
next form. All options considered will be evaluated and documented. The ...,
result of this process will be an identification and evaluation of feasible
mitigation options for each impact issue and a description of residual
impacts. 11
.,.
.., Comment: The statement in the second sentence of this paragraph, 11 0r in
conflict with other project objectives, .. indicates equal consideration of
fish and wildlife values would not be given in the mitigation planning
effort conducted by Acres American, Terrestrial Environmental Services and
APA. It is doubtful that any fish and wildlife impact issue would not be
in conflict with APA's primary objective to construct the Su Hydro Project, ..
and automatically mitigation alternatives would generally fall into the
compensatory realm of mitigation defined in Section 3.5. This Department
will closely examine the products of the impact evaluation and mitigation
planning effort to be sure equal consideration is given to fish and
wildlife resource values and that summary and arbitrary dismissal of
feasible mitigation alternatives which may be in conflict with 11 project
objectives .. is not the primary factor in arriving at a mitigation plan.
Paragraph 7 of this section states:
"Additional items that may be addressed by the Core Group include an
identification of organizations qualified to execute the mitigation plan
and recommendations concerning the staffing, funding and responsibilities
of the mitigation monitoring team ...
...
..
-..
Comment: The Core Group may make its recommendations, but agencies such as •
this Oep~rtment with a direct responsibility for the management of fish and
wildlife resources will in accord with its resource management and
protection responsibilities, make its own recommendations to define
staffing or funding levels and responsibilities for the mitigation
monitoring team. It is our view that APA and its subcontractors do not
have oversight on mitigation alternatives or means of implementation.
Mitigation and the final approval of its acceptability lies with this
Department and other resource agencies with similar mandates. It will be
the obligation of APA to implement mitigation plans in accord with the
approval of these agencies. In addition, it appears that the "mitigation
review group .. is responsible for "informal agency review and comment 11 on
the proposed mitigation options. This informal review is "considered by
APA and the Core Group prior to the preparation of ... mitigation plans."
However, the option being reviewed (informally) by the mitigation review
group are those developed by the Core group in Step 2. This needs to be
clarified.
In paragraph 8 of this section it states:
...
..
-
...
...
-
-
-
-
-
-
-
-
-
-
-
-
-
-
',
Mr. John D. Lawrence -5-December 30, 1981
11 During the implementation of the plan, which will include both the
construction and operation phases of the project until further mitigation
is deemed unnecessary, the mitigation monitoring team will review the work
and evaluate the effectiveness of the plan (Step 5). To accomplish this
goal, the monitoring team will have the responsibility of assuring that the
agreed upon plan is properly executed by the designated organizations. The
team will be provided with the results of ongoing monitoring efforts. This
will enable the team to determine in which cases the mitigation plan is
effective, where it has proven to be less than effective, and also in which
cases the predicted impact did not materialize and the proposed mitigation
efforts are unnecessary. The monitoring team will submit regularly
scheduled reports concerning the mitigation effort, and where appropriate,
propose modifications to the plan.11
•
Comment: It should be resolved now as to who pays for the participation by
agencies in the mitigation monitoring team. The APA should state its
commitment to funding participation by agency team members or mitigation
study groups.
General Comments
1. This Department does not believe adequate opportunity will be afforded the
natural resource agencies to evaluate or review mitigation plans due to the
accelerated nature of APA's schedule.
2.
To date, for example, the Fisheries Mitigation Task Force Review Group has
not been afforded an opportunity to assess ongoing impact assessment and
mitigation plans being developed by Terrestrial Environmental Services.
Also, the Department has relayed to the APA on numerous occasions our
concern that a more extended period of fisheries studies needs to be
performed before adequate impact analysis is made and thence feasible
mitigation alternatives developed.
A section outlining the membership and relationships of the Mitigation Task
Force, and Core Group will need to be included.
I am interested in obtaining a copy of a plan that clearly sets out the
schedules for formal review of specific products by appropriate agencies in
-order that this Department can adequately respond in a timely and responsible
manner to APA.
-If you have questions, please do not hesitate to contact us.
Sincerely,
~~-Skoog -J' mmlSSloner
United States Department of the Interior RECEJVEb
IN REPLY REFER TO:
FISH AND WILDLIFE SERVICE
1011 E. TUDOR RD.
JAN 12 1982-
.WAES ANCHORAGE, ALASKA 99503
(907) 276-3800
ACRES AiiiJUCAM wcaarar ·am
c
Mr. Eric Yould
Executive Director
Alaska Power Authority
333 W. 4th Avenue
Anchorage, Alaska 99501
Dear Mr. Yould:
3 0 DEC 198t
This letter responds to a request by John Lawrence of Acres American that the
Fish and Wildlife Service (FWS) review the Fish and Wildlife Mitigation Policy
for the Susitna Hydroelectric Feasibility Study. The request was made by
letter dated November 19, 1981. Our review of the Alaska Power Authority's ·
(APA) Policy Statement has been undertaken in light of the FWS Mitigation
Policy (Federal Register Vol. 46, No. 15, January 23, 1981). We have enclosed
a copy of our Mitigation Policy and havepreviously transferred a copy to your
subcontractor, Terrestrial Enviromental Specialists, Inc. (see enclosed letter
dated 4 June 1981). By maximizing consistency between the two policy
-----------ftatements, avoidance of policy disagreements between the APA and the TivS can
~SKA POWER e accomplished. Long-term benefits would accrue throughout the process
UTHORtTY • 1 d . h d . f j . . . . . . . 1 d d . f . ~USJTNA nc u 1ng w en an 1 pro ect m1t1gat1on mon1tor1ng 1s 1n p ace an mo 1 1ca-
, ions to ongoing mitigation could be evaluated under one policy.
ILE P5700
~ II riefly, the Service's mitigation policy reflects the goal that the most
2UENCE NO important fish and wildlife resources should receive the greatest level of
F. ',.:;$ ' i tigation when the environment of a particular area is changed. The Floi'S
• policy divides the mitigation planning process into three components: (1)
i=
!/)
5 ~resource category determinations; (2) impact assessment; and (3) mitigation
recommendations. By creating four resource categories, the FWS can vary the
degree of mitigation it recommends according to the value and scarcity of the
1---1 habitat at risk. u C·ri
Our resource category, " •.• determinations will contain a technical rationale
consistent with the designation criteria. The rationale will: (1) outline
the reasons why the evaluation species were selected; (2) discuss the value of
the habitats to the evaluation species; and (3) discuss and contrast the
relative scarcity of the fish and wildlife resource on a national and
~---4ecoregion section basis." (F.R. Vol. 46, No. 15, p. 7658). Special con-
----llioi'RV
-'-i-
HRC
sideration would be given to notable, " ... aquatic and terrestrial sites
including legally designated or set-aside areas such as sanctuaries, fish and
wildlife management areas, hatcheries, and refuges, and other aquatic sites
such as floodplains, wetlands, mudflats, vegetated shallows, coral reefs,
riffles and pools, and springs and seeps." (F.R. Vol. 46, No. 15, pp.
7658-7659). In the aforementioned sites, the mitigation goal to which the
~ ---4 Service would strive for is either no loss of existing habitat value (Resource
Category 1) or no net loss of in-kind habitat value (Resource Category 2).
--(FILE
...
..
...
--
-
-
...,
...
...
...
... ,
-
-
-
-
-
-
-
-
-
-
-c
-
-
-
-
-
-
-
-
-
-
·Mr. Eric Yould Page 2
The Service intends to recommend mitigation where a biological change
constitutes an adverse impact. Our evaluation of project impacts and
recommended mitigation would be based, to the extent applicable, on the
Service's Habitat Evaluation Procedures and Instream Flow Incremental
Methodology. Both of these methodologies have been suggested to APA and its
consultants on several occasions. It should be recognized that streamlining
the mitigation process can be accomplished by conformance between the
Service's and an applicant's impact assessment techniques. The larger the
proposal, the greater the potential savings in time. This idea was a
principal behind the formulation of our mitigation policy and adoption of
official evaluation procedures.
In accordance with our mitigation policy, "The Service may recommend support
of projects or other proposals when the following criteria are met: (1) they
are ecologically sound; (2) the least environmentally damaging reasonable
alternative is selected; (3) every reasonable effort is made to avoid or
minimize damages or loss of fish and wildlife resources and uses; (4) all
important recommended means and measures have been adopted with guaranteed
implementation to satisfactorily compensate for unavoidable damage or loss
consistent with the appropriate mitigation goal; and (5) for wetlands and
shallow water habitats, the proposed activity is clearly water dependent and
there is a demonstrated public need." (F.R. Vol. 46, No. 15, p. 7659).
Specific comments:
1.0 Introduction: This section should include a discussion of the need to
adequately assess the environmental resources of the study area to
determine the environmental compatibility of a proposed project and to
evaluate mitigation to adequately reduce or avoid negative impacts to
environmental resources, including fish and wildlife resources, so that no
net loss of habitat value occurs.
2.0 Legal Mandates: It should be recognized that the intent of the specified
laws and regulations is that project-related adverse biological impacts be
fully mitigated. In addition, that a plan be developed, acceptable to the
resource agencies with mandated fish and wildlife management responsi-
bilities, and implemented as a component of the proposal.
2.2 National Environmental Policy Act (NEPA): It is the responsibility of the
lead federal agency, the Federal Energy Regulatory Commission (FERC), to
fully comply with NEPA.
2.3 Federal Energy Regulatory Commission: Regulations for, ""Application for
License for Major Unconstructed Projects and Major Hodified Projects,··
(F.R. Vol 46, No. 219, November 13, 1981) were adopted December 14, 1981.
References in your policy to FERC regulations should reflect this. It
should be recognized that within the Exhibit E, "The applicant must
provide a report that describes the fish, wildlife, and botanical
resources in the vicinity of the proposed project; expected impacts of the
project on these resources; and mitigation, enhancement, or protection
measures proposed by the applicant. The report must be prepared in
consultation with the state agency or agencies with responsibility for
these resources, the u.s. Fish and ~ildlife Service, the National Marine
Fisheries Service (if the proposed project ~ay affect anadromous,
estuarine, or marine fish resources), and any state or federal agency with
c
Mr. Eric Yould
cc: FWS-ROES, WAES
Quentin Edson, FERC
NMFS, EPA, NPS, BLM, USGS, ADEC, ADF&G
Carson/ADNR
Lawrence/Acres American
~
Page 5 -
-
...
..
...
'!Ill
-
-
--
-
...
...
-,
-
-
-
-
-
-
(
-
I • LASKA .l"OWER
AUTHORITY
I -SUSITN.I.
I ~ILE .p·/.~~
;SEQUENCE NO.
~ / 6,.. £ ~·._?,, s
..J ~
e I '
lz~ ~
(" "': ~ u:
. " 1-I l .;; ~ !::
---------------------------------~-
December 31, 1981
Mr. John D. Lawrence
Acres American, Inc.
900 Liberty Bank Building
Main at Court
Buffalo, New York 14202
Dear Mr. Lawrence:
UNITED STATES DEPARTMENT OF COMMERCE
National Oceanic and Atmospheric Administration
National Marine Fisheries Serviae
P.O. Bo:c 1668
Juneau~ Alaska 99802 RECEIVED
JAN 0 4 1982
A&RtS A~H.iU&Ati lNC\liWURAiED
We have received your letter of November 19, 1981, requesting the comments
of the National Marine Fisheries Service (NMFS) on the Fish and Wildlife
Mitigation Policy for the Susitna Hydroelectric Project. Having reviewed
the statement we offer the following comments.
The statement adequately reflects the intent of such a mitigation policy
and presents an accurate overview of those legal mandates which require
mitigation to be considered in designing hydroelectric projects. We
have several specific comments dealing with the operation of the proposed
mitigation plan, which follow.
3.1 Basic Intent of the Applicant
The last paragraph states that this methodology outlines a
process for resolving conflict between the Power Authority and
resource agencies. We do not feel this has been satisfactorily
accomplished within the general policy statement (Sec. 3) and
suggest additional effort be made to establish such a conflict
resolution methodology.
3.2 Consultation with Natural Resource Agencies & the Public
-r: :=j u I !:
--.--1-
Realizing that Section 4, step 3, development of an acceptable
mitigation plan, is to be completed by March 1982, we assume that
steps 1 and 2 of the same section are by now substantially completed.
Yet, contrary to the second sentence of 3.2, 11 During the early
stages of planning, representatives of state and federal agencies
will be encouraged to consult with the applicant and the applicants
representatives, as members of the Mitigation Task Force.11
,
_Li,D~~N .
i A'"yn ~ -~.·~·-·--. ICAD I
-,_r-zj -j~<~; , -
--~-~-:-.a· '.<.1:-~t
--~-J Ps
--,.--j i,.-pGH
=-=~--EN s_: ~--
SNT
-1'"--~---
=1--J;:; ~t-·
--!~j_= {Jf&'h= ..
-1 t/ . !·-~.,,!'"
> ,-•.·~···· ' · .••. -:J -........ . -1--·-.• ·
-I _j~i=l-1-FILE,-
we have yet to be contacted regarding the status of this impor-
tant element, and the Mitigation Task Force review committee has
not met as of this date.
3.3 Implementation of the Mitigation Plan
We are pleased to see the plan include provisions for post-
construction monitoring of mitigation measur~ and opportunities.
·. ' '4' 1 ......
'-· \ I ; ·. ' \
'' ., :\.
j ··~·· •• ·-· .•J
'• -~--:;
\
The applicant should note, however, that such a provision will
be integral to the mitigation plan and the associated costs should·
be included with the license application, and not 11 resolved through
parties after the mitigation plan is complete." This is supported
in the FERC regulations, 4.41 (F)(3)(iv)(D), which require
Exhibit E to contain an estimate of the costs of construction,
operation, and maintenance of any proposed facilities or imple-
mentation of any (mitigation) measures.
3.4 Modification of the Mitigation Plan
4
The last sentence, dealing with termination, should state that
termination of any mitigation measure stipulated in the FERC
license will require an amendment to that license.
Approach to Developing the Fish and Wildlife Mitiqation Plans
Paragraph 3, sentence 6. Change 'will' to 'may', as priority will
be assigned both by the likelihood of impact and sensitivity of
the resource.
Paragraph 5, sentence 2. The fact that a form of mitigation is in
conf1 i ct with project objectives or only partially effective should
not prevent it from further consideration. Such a statement strains
the term "reasonable alternatives" and does not comply with the
spirit or intent of the National Environmental Policy Act.
Paragraph 7. As outlined, no formal agency input into the mitigation
plan will occur prior to application to FERC. FERC regulations
require Exhibit E to contain a report describing proposed mitigation
measures, prepared in consultation with state and federal resource
agencies. The process described here falls short of this required
consultation. We suggest formal agency review of the draft fisheries
and wildlife mitigation plans occur prior to license application.
We appreciate this opportunity to comment.
Sincer~ly, -~ 1 ~
'· )r~ 9/c;e_;>.·~
. ~-. ,.
~ Robert W. McVey
1 Dire~tor, Alaska Region
j /
v····
..
-
-..
..
Wi
..
--
~
..
'!
...i
.,.;
Will
"""
--
...
-
-
-
'(
-ALASKA POWER.
-UTHORITY
USITNA
FILE P5700
. }-; c
UNITED STATES DEPARTMENT OF COMMERCE
National Oceanic and Atmospheric Administration
National Marine Fisheries Service
P.O. Box 1668
December 31, 1981 Juneau, Alaska 99802
Mr. John D. Lawrence, Project Manager
ACRES American Incorporated
Consulting Engineers
The Liberty Bank Building Main at Court
Buffalo, New York 14202
Dear Mr. Lawrence:
R ~\-='P' ,,_0
·-·---C:. I V t:.
JAN 0 4 1982
ACR;;..; .m;c.:uii~tu htbUit~ORATED
We have received the Susitna Hydroelectric Project Environmental Report
prepared by Terrestrial Environmental Specialists (TES). We have limited
our review of this series of documents to those concerning the fisheries
studies, i.e., the Summary Annual Report and Fish Ecology Annual Report.
The presentation of 1980 work done by TES towards assessing the impacts
of development and operations of the project on the fishery and proposing
measures to minimize or mitigate adverse impacts was reviewed without
substantial comment, as much of it was very preliminary. Also, no
review was made of the 1980 fish ecology program due to delay in pub-
lishing the detailed procedures manual. In addition to the lack of
substantial information presented in these reports, we believe the timing
of this review request mak~s an in-depth agency review inappropriate.
The main benefit derived from this review would have been to allow changes
or redirection of efforts to be made in the 1981 field studies. However,
as of this date, the 1981 environmental studies have been completed.
We look forward to receiving the 1981 Environmental Studies Annual Reports,
as these documents should provide the basis for our review of the draft SE~ENCE NO.
/--)L:?.:: 1_ 1 Feasibility Report.
<=I I ;:! .J j Sincerely,
:)-a:: <t ~ ~ -1---r.J') !:: / / i(j~-~-_1 --------~-;?k~ -~
-!~! r;c~ ' . ~o-bert . McVey -~~::f--;J+( Dires;t: r, Alaska Region 1c.o.o1~ \___..-/
~ J DG Il-l\
-~~1/f =I-=! J P-S I -p ~~~GHi___j
j ENS -Tsti-:r-·-
-'-1--
1M RV F 1 DWL --:---~-
--1-----~HRCI ,._ e -hv_;_.\
-p:::r..:~:::~-J.-_~-~ . ---jk.:i;..;
---:---~ \f. ·,: ~+-.--:_I/{ ~ ----l-1-t '/A----r---[:_ ~--=.
I ·J
) i\1'' ;~ 0/f_/
:':;_~~.~~.
·• -'="· ,.
U. S. E N V I R 0 N M E N T A L P R 0 T E C T I 0 N A G E N C Y
~~\1€.0 St-4J". REGION X ~~~IS' ~ . s u ~~~ z 0
1200 SIXTH AVENUE
SEATTLE, WASHINGTON 98101
~ ~
'1-J: •• l
-1( PR01~c..
REPLY TO M/S 443 ATTN OF:
DEC 2 1 1981
John 0. Lawrence
Acres American, Incorporated
The LiDerty Bank Building
Main at Court
Buffalo, New York 14202
RECEIVED
DEC 2 8 1981
ACRES iuru:itiLiJtt• Vj~JRriJRATE~
(
SUBJECT: Susitna Hydroelectric Project, Summary Annual Environmental
Report-1980 and Transmission Line Corridor Screening Report
Dear Mr. Lawrence:
Thank you for sending us the above reports for our review. We have also
received the Development Selection Report and will be forwarding our
comments to you on that report before the end of December.
ALASKA PowER We appreciate the extensive coordination effort and the opportunity to
AUTHORITY • •
SUSITNA rev1ew and comment on Sus1tna reports as they are prepared. I further
~ appreciate your attempts to ensure that the views of the Agency are
FILE P5790 adequately reflected in this process. While we have been coordinating
· .. ,. ·-'/ with the Susitna Interagency Steering Committee, our budget restrictions
St:QUEi'\CC: NO. have limited our active participation more than I would like. In this r d.J/1 regar~, it would be extrem~ly helpful to us if you could provide u~ an
I ~ · =ioverv1ew of your consultat1on plan and the schedule for future rev1ews.
z1:~! ~ 1 1This will better enaole us to give you timely comprehensive comments on
~ . : ~ \: I the ~ari ous segments of the study, with the overall project perspective
"'i_;l ~ ~ 1n m1nd.
·=I~::·:_I __ EPA is particularly interested in information on wetland mapping, water
1..:._. ,._.~j __ quality and water quantity modeling and project alternatives. The 1980 I r: ·_r; 1 , Environmental Report appropriately points out the interrelationships and
-i~·--:-;I . importance of these areas to wildlife survival and downstream fish
-~;1 r, ecology. However, it .does not cover EPA's areas of interest directly.
-· ~-J" 5-J We ~oul d 1 ike to review the reports on these subjects when they are
-:!rcHI ava1l able.
-·-~-----~-::: !1 s
-·-·---1--~ : r I
-l-1---
; _ll;,-;~~ \~ ,. ---
-·-1----'H",...j -~-~-~ J>Mt6+ --:~-
v
/
--
-
...
-
...
..
..
...
..
.,
J
....
-
.J
_,j
...
-..
-
-
-
-
-
-(
-
-
-
-
-
-
-
-
2
We support the empnasis in the Environmental Report and related studies
on identifying ways to minimize the environmental impacts of the Susitna
project. In particular, selection of the access route and type of access
is an issue witn long term environmental consequences wnicn offers many
opportunities for minimizing impacts. EPA supports the concept of
minimizing impacts oy use of a single corridor for both access and trans-
mission needs, as pointed out in ootn the Transmission Line Corridor
Screening Report and the Environmental Report. We encourage you to
incorporate tnese kinds of suggestions from agencies and the Steering
Committee into the project selection, construction and operation plans.
Sucn commitments will certainly positively influence reviews of any FERC
license application.
We have some concerns with the conclusions aoout the Central Study area
in the Transmission Line Corridor Screening Report. There appear to be
different opinions on the environmental consequences of selecting Corri-
dor l versus Corridor 14. We feel that additional areas should be
included in future studies of the central corridor, to provide a broader
data base from which such conclusions can be drawn. More specifically,
in this area, Corridor One (ABCO), which roughly follows the south side
of tne Susitna River, is the recommended corridor based on Acre's techni-
cal, economic and environmental criteria. Corridor 14 (AJCD) follows the
same route as Corridor 1 from Gold Creek to Devils Canyon, out crosses to
tne north side of the Susitna River for the section from Devils Canyon to
the Watana dam site. Corridor 14 nas tecnnical and economic ratings as
high as Corridor 1, but was not recommended because of environmental and
land use conflicts in segment CJ. On solely environmental grounds, it
appears that an access route similar to Corridor 14 is preferred to
Corridor 1 by Doth Terrestrial Environmental Specialists, Incorporated
(Environmental Report page 73 and 82) and the Susitna Hydroelectric
Steering Committee (letter from Al Carson, Chairman, to Eric Yould, dated
November 5, 1981.) Therefore, the areas of the central corridor to be
further studied should include the north side of the river between Devils
Canyon and -the Watana dam site to encompass segment CJA as well as
segment CBA.
One reason for the different conclusions regarding the environmentally
preferable route oetween Devils Canyon and the Watana Dam site may be the
Environmental Report's and the Steering Committee's identification of the
most environmentally sensitive areas, wnicn then have tne highest priori-
ty to be avoided. It may be desirable to use a similar approach during
the more detailed route selection studies, especially in areas where
wetlands must be crossed. Identifying and then avoiding primary and
secondary impacts to the most valuable wetland habitats should be an
important part of the more detailed studies of all three transmission
study areas.
(
3
We appreciate the opportunity to review this report. Please contact me
or Judi Scnwarz, of my staff, if you would like to discuss our comments.
at (206) 442-1266 and (206) 442-1096, respectively.
Eric Yould, AlasKa Power Authority
Al Carson, Department of Natural Resources
--
-
---
...
-
-
...
-
-
-
--
-
-
-
-
-..
I WILLETT
1-l WITTE
1-BERRY
. . I'
1\l'_i LhA //~~ I , _!_ I u -n
1-·' L " ~-r..J..rJd!}.
~~AMB "! _I.J
I LAWRENCE ~
1-';INCLAIR
1-IIANOERBURGH 4= J.
~.-.,'-.
I
t-::ARLSON _]
Ti"RETZ ..
jJEX "'
.
January 4, 1981
P5700. 11.91
T.1390
g1
John R. Spencer
anal Administrator s. Environmental Protection Agency
on X ~
~a
ea
"a ~g
..:
0 Sixth Avenue
ttle, Washington 98101
r Mr. Spencer; Sus1tna Hydroelectric Project
Formal ABency Coordination
_ ·-OWREY _jp
k you for your letter of December 21, 1981; your constructive
gestions are very much appreciated. I will attempt to respond
the issues you raised:
_ liNGH -I
I-I
1--tUSTEAO
lBOVE
I
-
--,.eHASE
I
r-'
t-1--L'.
1.. ...r,{__-( .·
/ -
-
1. I am enclosing a description of our formal agency coordination
plan, indicating which agencies will receive which reports.
Regarding schedule, EPA will be receiving the following
reports on or around the following dates:
2.
a} Fish and Wildlife Mitigation Options -January 1982
b) Instream Flow Study Plan -February 1982
c) Susitna Feasibility Study -!~arch 1982
Under separate cover you will be receiving an invitation to
attend a meeting in Anchorage on January 21, 1982 explaining
our Formal Agency Coordination Program.
Wetland mapping has been conducted as part of the study.
For your information, I am enclosing the 1980 Plant Ecology
SuiTillary Report and a set of vegetation maps. All \'letlands
within the proposed impoundment zones (including a one half
mile buffer) and \'tithin known borrow area \'Jere mapped, utilizing
the new U.S. Fish and Hildlife Service Classification (Cowardin
et. al. 1979).
C'
Mr. John R. Spencer January 4, 1982
page 2
3. · Project alternatives are discussed in the Development Selection
Report which you have received and will be disoussed further
in the Feasibility Study.
4. Water quality issues and water quantity modeling results will
be found in the Feasib1,1ty Study.
5. Following selection of the access route, the transmission line
corridor in the central study area has been expanded (as
indicated on page 7-4 of the Transmission line Corridor Screening
Report) to include a larger area on the north side of the Susitna
River. This will result in a single corr4dor being used for
both the access route and the transmission line corridor. This
was done both to eeduce impacts via access and to avoid the
large wetland areas on the south side of the Susitna River.
6. Transmission line routing studies are currently being conducted.
Wetlands is a parameter in the selection process. I think you
can appreciate, however, it will not be possible to avoid all
wetlands in the area, simply because there are so many.
Again, thank yod for your comments. If you have further questions, please
let me know.
~1MG/jh
cc: E. Yould, APA
Sincerely yours,
~·
John D. lawrence
Project Manager
-
-
-
...
j
.,
J
•• .,J
j
;
-' ,
1 ...
'f
.J
)
J
...
...
...
-
....
-·
-
-
-
...,..
.....
-
-
-
.. _
-
.....
......
~! r
L. ~~"
Mr. Ernest W. Mueller
Co11111issioner
January 8~ 1982
P5700.11.92
T1415
Alaska Department of Environmental Conservation
Juneau, Alaska 99801
Dear Mr. Mueller:
Susitna Hydroelectric Project
Formal Agency Coordination Program
As you are aware, Acres American has, on behalf of the Alaska Power
Authority, instituted a Formal Agency Coordination Program for the Susitna
Hydroelectric Project. This program has apparently resulted in some
confusion among various agencies as to its intent and scope.
To resolve this, a meeting has been arranged for 10:00 a.m. on January 21,
1982~ at the office of the Alaska Power Authority, 334 West 5th Avenue,
Anchorage. The purpose of this meeting will be to explain the rationale,
intent, scope, and regulatory requirements for this program.
If you feel you could benefit from this meeting, your attendance is welcome.
MMG/jgk
ACRES AMERICAN INCORPORATED
C.,-:,n.~ut~~""'1 E:v:;.nee~s
i· '.; L~::~".!'!f' e~!".~ 2:.;·:; .. I'J ·: ~. :'": r-:t c. ~"t
8-;:":-s>:>. ~:t::. Y'J:"' ..,.:;:.2
~ --_<•:r ·.:::~e 7 ~~~:;.:,"".~.:.--:_.:_,-~ "7 • .. : • .;.• ~ .. • .:~.;: -. ;...::;;r::; £;:;F
c ...
Sincerely yours,
John D. Lawrence
Project Manager
. .. , .... ,.. "1'-' __ .._..
[] '
'
.
Mr. Robert Shaw
State Historic Preservation Officer
Alaska Department of Natural Resources
Division of Parks
619 Warehouse Avenue, Suite 210
Anchorage, Alaska 99501
Dear Mr. Shaw:
January 8, 1982
P5700 .11. 92
T1420
Susitna Hydroelectric Project
Formal Agency Coordination Program
As you are aware, Acres American has, on behalf of the Alaska Power
Authority, instituted a Formal Agency Coordination Program for the Susitna
Hydroelectric Project. This program has apparently resulted in some
confusion among various agencies as to its intent and scope.
Tp resolve this, a meeting has been arranged for 10:00 a.m. on January 21,
1982, at the office of the Alaska Power Authority, 334 West 5th Avenue,
Anchorage. The purpose of this meeting will be to explain the rationale,
intent, scope, and regulatory requirements for this program.
If you feel you could benefit from this meeting, your attendance is welcome.
MMG/jgk
ACRES AMERICAN INCORPORATED
Cc:,n-su:::r.:; Er:J ..... ~ers
7· ~~::::~~..-~:r::-: e·,J·~--_; ~~r; · ·.""" ;:.;t c...-.t..r-t
~.~''"' 'J i~'"':. Y0~ ... ~-!;r.;2
:(:·:.·~·r·• .. -;·;;.~ 7'_2~ r~:·•_., -.~.;..::?; .·.( ;::: -~::: _:
r .. ~, ·' ·~~ .... ~-::~ ;.;. . -.. ....: .. ::;·
Sincerely yours,
John D. Lawrence
Project Manager
-
...
..
...
-..
-
-
..
-
.,
-
....
...,
-
...
-
-
-
-
-
-
.......
-
-
.....
-
'
......
-
~
.....
-
-
,. r~ --F-' .-·
~ ; .
! . ~
Mr. Ronald 0. Skoog
Commissioner
January 8, 1982
P5700 .11. 70
Tl414
State of Alaska Department
Juneau~ Alaska 99801
of Fish and Game
Dear Mr. Skoog:
Susitna Hydroelectric Project
Formal Agency Coordination Program
As you are aware, Acres American has, on behalf of the Alaska Power
Authority, instituted a Formal Agency Coordination Program for the Susitna
Hydroelectric Project. This program has apparently resulted in some
confusion among various agencies as to its intent and scope.
To resolve this, a meeting has been arranged for 10:00 a.m. on January 21,
1982, at the office of the Alaska Power Authority, 334 West 5th Avenue,
Anchorage. The purpose of this meeting will be to explain the rationale,
intent, scope, and regulatory requirements for this program.
If you feel you could benefit from this. meeting, your attendance is welcome.
MMG/jgk
ACRES AMERICAN INCORPORATED
CO:"''SYl~i"''g E--.;;.'1te!'S.
T~e :..~t:::~t:,· ~.:· !\ 5v'·: ..... ,.., ·.~":.<!"! ~t C·:q.;rt
~u!fQ,O. r-:(-:. ·~··~·~ ~.:-2'J2
; ~:··-·:)~.;:,.;-;~ :~:-.:..--~ /.·~ T•_ '·:.--(.o:~-6..:2'"· ;.":__ ::r_,:. bGF
.-·: ,·.
Sincerely yours,
John D. Lawrence
Project Manager
fDl . .
I • .. ~.. l
Mr. Robert McVey
Director, Alaska Region
National Marine Fisheries Service
NOAA
P.O. Box 1668
Juneau, Alaska 99802
Dear Mr. McVey:
January 8, 1982
P5700.11.91
Tl411
Susitna Hydroelectric Project
Formal Agency Coordination Program
As you are aware, Acres American has, on behalf of the Alaska Power
Authority, instituted a Formal Agency Coordination Program for the Susitna
Hydroelectric Project. This program has apparently resulted in some
confusion among various agencies as to its intent and scope.
To resolve this, a meeting has been arranged for 10:00 a.m. on January 21,
1982, at the office of the Alaska Power Authority, 334 West 5th Avenue,
Anchorage. The purpose of this meeting will be to explain the rationale,
intent, scope, and regula tory requirements for this program.
If you feel you could benefit from this meeting, your attendance is welcome.
MMG/jgk
ACRES AMERICAN INCORPORATED
C::;"'~w-:~·"""g Er:gtneers
r~·:-e Litr:r:y e:;r,:.; ~t.nf~_!.ng_ ~.~a'n 2t C:-...:n
8:...'4'a:., NP:J Y0r~ i~~·o2
:-~f,.:-;:.r.c-~ t~r:;-2::"J.~:::2: T._~::.:~. -::~-.;: . .;~."~ : ..... _~::::; 2LiF
~~: p. :· ~: • -::· . -.. -~
Sincerely yours,
John D. Lawrence
Project Manager
-:)c
..
-
-..
...
..
-
...
-
..,j
•
-
.,
...
till!
...
-
...
-
-
-
"
.......
-
11:;:-L
-
-
.....
-
r r ,.. ,,., -
,,
.... L. ~--..
Mr. Keith Schreiner
Regional Director, Region 7 u.s. Fish and Wildlife Service
lOll E. Tudor Road
Anchorage, Alaska 99503
Dear Mr. Schreiner:
January 8, 1982
P5700 .ll. 71
Tl410
Susitna Hydroelectric Project
Formal Agency Coordination Program
As you are aware, Acres American has, on behalf of the Alaska Power
Authority, instituted a Formal Agency Coordination Program for the Susitna
Hydroelectric Project. This program has apparently resulted in some
confusion among various agencies as to its intent and scope.
To resolve this, a meeting has been arranged for 10:00 a.m. on January 21,
1982, at the office of the Alaska Power Authority, 334 West 5th Avenue,
Anchorage. The purpose of this meeting will be to explain the rationale,
intent, scope, and regulatory requirements for this program.
If you feel you could benefit from this meeting, your attendance is welcome.
MMG/jgk
ACRES AMERICAN INCORPORATED
Cwr.:::_..:• ~-; E;~; ·-~~-·s
-~~ L~~!:'~ .. ~.::.;-;.. S·J· -~ '· r'! ;:t C-~urt
3u~!~.l~":l r-:;:.: .. Yt;· ... • .!2 .. 2
r ...... : ·...:; .... ..-_:: ; ~ r: -~ ~ --= -;-._.·:A. _ _.;.c..:c;, . .:..c~.::s b:.~F
·-: (;'' .-.· ,-.. . . .. :-· ....... -. ,:..;.,.-.. ·.---.. ·_;:· ·.~
. Sincerely yours,
John D. Lawrence
Project Manager
o•t. r .. , --... ~
~1
l
!
Co 1 • Lee Nunn
District Engineer
U.S. Army Corps of Engineers
Anchorage District
P.O. Box 7002
Anchorage, Alaska 99510
Dear Col.. Nunn:
January 8, 1982
P5700.11
Tl409
Susitna Hydroelectric Project
Formal Agency Coordination Program
As you are aware, Acres American has, on behalf of the Alaska Power
Authority, instituted a Formal Agency Coordination Program for the Susitna
Hydroelectric Project. This program has apparently resulted in some
confusion among various agencies as to its intent and scope.
To resolve this, a meeting has been arranged for 10:00 a.m. on January 21,
1982, at the office of the Alaska Power Authority, 334 West 5th Avenue,
Anchorage. The purpose of this meeting will be to explain the rationale,
intent, scope, and regulatory requirements for this program.
If you feel you could benefit from this meeting, your attendance is welcome.
MMG/jgk
ACRES AMERICAN INCORPORATED
::,:::.:.:·::-g Er.g~nr::~·s
~..,'= _:b(:rtf Bon~ 9udc.:.~:; ·.~-::. n Gt Cc:...rt
3:.;;":;;:o r~r::: Yor<{ ~.:CG2
~t:~':r;.:-i~e ~~-;.:.~~3-~~..:. T·~·\:'--r~_L..:_..::2~-ACHES. ELJF
r·:;,. ·":. ':r' ;.•,...,! ••:.· ··:· ,;,. __ ::-;! ~,.-, .• -••
Sincerely yours,
John D. Lawrence
Project Manager
---
-
-
...
...
.,.
-
-·
.,.;
-
~
-
-
....
...
•
•
-
-
-
-
--
-
-
-
-
-
-
-
-
-
-
......
EJ .
. .
.
.
Regional Administrator
Region X
January 8, 1982
P5700.11.91
T1408
U.S. Environmental Protection Agency
1200 South Avenue
Seattle, WA 98101
Dear Sirs:
As you are aware, Acres
Authority, instituted a
Hydroelectric Project.
confusion among various
Susitna Hydroelectric Project
Formal Agency Coordination Program
American has, on behalf of the Alaska Power
Formal Agency Coordination Program for the Susitna
This program has apparently resulted in some
agencies as to its intent and scope.
To resolve this, a meeting has been arranged for 10:00 a.m. on January 21,
1982, at the office of the Alaska Power Authority, 334 West 5th Avenue,
Anchorage. The purpose of this meeting will be to explain the rationale,
intent, scope, and regulatory requirements for this program.
If you feel you could benefit from this meeting, your attendance is welcome.
MMG/jgk
ACRES AMERICAN INCORPORATED
C::·~ _t;·~·-; Er.g neers
-:..·:::"~r~; SCJ1k 8u.L· ··.g ·::_:,r :":! c:~_:!
:;...;··;
1 .J : ~(';:. Y":'~< :.1''12
: .... ;)r~_ ... r: i~t.-~;_,.,:.;: .·; r ...... ·.~·, ~~ ... ::-:· ?·~~::.:::: ~~F
r .•. ~'""''·._._ c~ ·~ . -. ;· ... _,,
Sincerely yours,
,/-/
•..
John D. Lawrence
Project Manager
-
' \
\
I :
Mr. John Rego
Bureau of Land Management
701-C Street
Anchorage, Alaska 99501
Dear Mr. Rego:
January 8, 1982
P5700.11.75
Tl413
Susitna Hydroelectric Project
Formal Agency Coordination Program
-
-
-
--..
As you are aware, Acres
Authority, instituted a
Hydroelectric Project.
confusion among various
.American has, on behalf of the Alaska Power
Formal Agency Coordination Program for the Susitna -
This program has apparently resulted in some
agencies as to its intent and scope.
To resolve this, a meeting has been arranged for 10:00 a.m. on January 21,
1982, at the office of the Alaska Power Authority, 334 West 5th Avenue,
Anchorage. The purpose of this meeting will be to explain the rationale,
intent, scope, and regulatory requirements for this program.
-
...
If you feel you could benefit from this meeting, your attendance is welcome. --
MMG/jgk
ACRES AMERICAN INCORPORATED
c :.-· <4 :.-·; =· ~· ... _ .. ,; ~
···~ .... ·:,.r·:: ~~ .. ~ =:;. . ·; •• C,·.-·!
. .. . , . . _: ~ :;
·-.
't •.• ._ . • • . ~ ~;.' '.
'· ~ ...... ~,
'
.. -··. ·~·-
Sincerely yours,
John D. Lawrence
Project Manager
,.. ..... _-
... :-:~'ili;. -~:·7·];;;·<~
-
-
-
-
-
-
-
-
-
c --. . -. -. -~ .C-Jilt. .~-a;n .ww.& L 1 __ . . t L-.5.¥ ·.---~~-=---
-·----------------
-
-
U.S.
~'"£:0 sr~ ...) .,~ ~· ~ ~..r.
:s l..,;.ll 0 ~~~ 7.. I \!) ~ ~
1-0~ ~-i ... ~
l. PR01~C.
!~~y J?, M/S 443
4 FEB 1982
ENVIRONMENTAL PROTECTION
REGION X
1200 SIXTH AVENUE
SEATTLE, WASHINGTON 98101
Kevin R. Young
Acres American Incorporated
The Liberty Bank Building
Main at Court
Buffalo, NY 14202
AGENCY REC::i'/'E.~
FEB 8 lS8Z
ACRES AMOOW UlCURPOMHi
Subject: Susitna Hydroelectric Project Fish and Wildlife Mitigation
Policy and Draft Analyses of Mitigation Options ·
Dear Mr. Young:
Al POWER
Thank you for sending us copies of the above papers for our review. From
conversations with Mike Grubb, of your staff, we understand that Acres
American has decided that further work is necessary on the mitigation
options papers before agency comments will be solicited. Therefore, this
letter will·address EPA's comments on the mitigation policy paper only • . IORITY
-31TNA
F'. ~ P5700
. I I. qJ; -
~ lPS
_,_-jiP(; H
-~-
_,_ 1 ENS
' SHT
OWL
In general, we believe that the overall mitigation approach is good. In
particular, the ~se of the CEQ definition of mitigation encourages the
most satisfactory types of mitigation to be considered first. This is
reflected in Figure 2, Option Analysis. The establishment of a long-term
monitoring plan and acknowledgment that the mitigation plan will be
changed if necessary is also commendable.
We do have some concerns about implementation of this policy, especially
over the next year while the mitigation plan for the FERC license appli-
cation is still being developed. Some issues and mitigation measures must
be incorporated into the preliminary engineering and design stages of the
projects and, from our review of the Acres American reports, we are aware
that this is being done. One good example is spillway design to avoid
nitrogen supersaturation. However, there are a great many other issues
where the agencies and the public do not have sufficient information yet
on the impacts to judge either how much mitigation will be needed or what
sort of mitigation might be successful. For example, EPA will not have
any pre-and post-project water quality data unti 1 the feasibility study
is circulated (letter from John D. Lawrence to John R. Spencer, January 4,
1982.) Development of an option analysis which reflects the possible suc-
cessful mitigation measures for the entire range of potential impacts,
including the worst case, appears to be a useful step at this time.
Ho1·1ever, the agencies and the public may have difficulty evaluating the
l__;
. '
adequacy of a mitigation plan until more impact information is available.
EPA would have been faced with this situation in reviewing the fishery
mitigation plan if Acres American had wanted our comments at this time.
We have one other suggestion for your consideration. Because of the
location and magnitude of the impacts, new mitigation methods or methods
new to this region of Alaska may eventually be identified. Because it
will be several years before the mitigation plan is finalized, it may be
possible to test the feasibility of some of these ideas before mitigation
itself must start. Such an approach may have long-term environmental and
economic benefits.
Some additional minor comments are presented in the attachment.
We look forward to reviewing the option papers. If you would like to dis-
cuss our corrments, Judi Schwarz of the Environmental Evaluation Branch may
be contacted for more information. She can be reached at {206) 442-1096.
Sincerely,
~t .. l oq1J :O~eal, Director
Environmental Services Division
··'<':
cc: A1 Carson, DNR
Dave Wozniak, APA
-~ to .....
,.,
-
-
-
-
-
-
-
-
h;.~ -
-
....
··.<4 -
~
-
..,.I
...
.I
...,
-
--
...
....
-
-
...
..
...
( ··-
-
-
--
I (
'\ /
Susitna Fish and Wildlife Mitigation Policy
Attachment
FERC Regulations
For your infonnation, FERC published the new regulations on license
applications on November 13, 1981. The section of fish and wildlife
mitigation can be found at 46 FR 55938. FERC has made some wording
changes, but the substance is essentially unchanged.
Definitions
The policy statement refers to a Mitigation Task Force, a Mitigation
Review Group, and a Core Group of the Mitigation Task Force. The com-
position and method of selection of each group should be described •
..-'
r rrr~ ~ . h,..
i ~ .. ~ r.~
! ~ . f:. .. ·1·.: d~
''"' • .;bo;i....f
Colonel Lee R. Nunn
Department of the Army
Alaska District, Corps of Engineers
P.O. Box 7002
Anchorage, AK 99510
February 19, 1982
P5700.11.92
Tl519
Dear Colonel Nunn: Susitna Hydroelectric Project
·Plant Ecolagy·Report·
Thank you for your letter of February 1 regarding your review of the
...
...
...
-
-
...
...
following reports: Environmental Summary Annual Report -1980, Development •
Selection Report, and Transmission Line Corridor Screening Close Out Report.
As a result of your comment concerning wetlands, I am enclosing for your •
information a copy of the 1980 Plant Ecology Report which more specifically
addresses the wetlands issue. Also enclosed is a copy of the vegetation
and wetlands maps which are referred to in the+r report. ~
+A~
Thank you again for your letter.
MG:ccv
Enclosures
cc: E. Yould -APA
ACRES AMERICAN INCORPORATED
': -·-·:: ... ~· -; =~.;; --:-::":,
-~ ~~~--~t,· e~ .... J; r: .... ·:: .. -; ·.~:; r-.:1! ~I' ... n
=~··::·-: r.':·:. v-:,; .... ·~::::::-
-~ r:-:·. ,.~ ;·-:.-~:.-:.:-~~~:. ~(·~;: .. <?~-.:.:~~ . .:.c;=..:s auF
~erely,
John Lawrence
Project Manager
-:.··~-~c..~· c.~:~ c:· ... -: J ".'D F.:~:.:~,~~ P..:. ~a~·:: :;:--c_~~_.c. ·.·:a:.. .... '"'.::c ... , DC
-
...
...
...
-
-
-
-
-
--
-
i7
i-~
I
fv
I
~ .....;:
!
~
'--
,,
--
--
--
-
-
...
WILLETT
ITTE
::RRY ....
A.YOEN
LAMB ' r n
• Gary O'Neal, Director
vfronmental Services Division
February 23, 1982
P5700. 11. 91
T.1526
~ ~-. ~ -· .... -
NCLAIR l . S. Environmental Protection Agency
gfon X ANDER BURGI-( e -
Yi)v ~ c,...,
,.-vh h v
-"RLSON
FRETZ
JEX
)WREY
NGH
p ;...! ,_~ J...L"'\
-.JSTEAO
BOVE
-CHASE
/
1-
I' 00 Sixth Avenue
~ attle, Washington 98101
a r Mr. 0 I rtea 1 : L.~' Susitna Hydroelectric Project
Fish and Wildlife HitfQation Policy
.h
F i
ank you for your letter of February 4, 1982 regarding the Susitna
sh and \~ildlife Nitigation Policy.
r~
tlhl
wfll be discussing Hitfgation further in early liarch meetings with
e Core and Review Groups and attempting to focus in on the major
pact issues and define further studies necessary to develop adequate
tigation. You will be invited to this meeting.
inl
r, 1
T cJC ank you again for your comments.
~'!MG/jh
cc: E. Yould, APA
J. Spencer, EPA
Sincet;eJ_y,
&---
John D. lawrence
Project ~anager
February 23, 1982
P5700. 11. 91
T.l424
~ r ._ .. ~-·-.~#-,_
-
WILLE"TT
WI TIE
BERRY
II HAYDEN
LAMB
Z, LAWRENCE
SINCLAIR
Mr. Robert W. McVey
r 11
~ a1
.I
I Ul
, ei
' I
ctor, Alaska Region
nal Marine Fisheries Service
Box 1668
u, Alaska 99802
Mr. McVey: . . Susitna Hydroelectric Project
Fish and Wildlife Mitigation Policy
nk you for your December 31, 1981 response to our request for
VANDERBURGK or nts on the Susitna Fish and Wildlife Mitigation Policy. I have
need to your comments in the order in which they were presented. "'~
t. f:.-roc."f, -
•1
• · Basic Intent of the Applicant
CARLSON
FRETZ
JEX l Ul
LOWREY tpJ
SINGH . ij
('~ /1 ,.,....;~v!JY
pproach to resolving fish and wildlife mitigation conflicts between
nd the.resource agencies is outlined in Step 3, Section 4, of the
ation Policy. As stated, it basically involves revie\'! and coli'"ltent
e F1 sh and Wildlife Hitfgation Review Group representing the
1 '/,~
_ STEAD
BOVE
CHASE
r'P~
.I
rl
a gE
-1= I
.
,) 4
...
"";:;(
n ::>1
hf,
rce agencies. In addition, although not specifically stated
r policy, any draft mitigation plans will be submitted to resource
ies for fonnal corrment and review prior to the submission of a
license application. Our policy w111 be modified to include this.
Consultation with Natural Resource Aqencies and the Public
on 4, Step 3, Development of an Acceptable mtigation Plan, \•:ill
e completed by r·~arch of 1982. Ho"'ever, mitiqation options \'rill
sessed and preferred options to~ether with their technical f~axi.
bility and potential effectiveness will be presented in the March 1982
Feasibility Report.
The first meeting of the Mitigation Review Group will occur in March.l982.
An invitation will be sent to Bradley Smith as a represen!ative of your
agency. This meeting will provide the resource agencies with an opportunity
to discuss, \llith the f.iitigation Core Groups, the various mitigation options
presently being considered. The details of a draft mitigation plan will
be completed subsequent to the Feasibility Report and prior to the FERC
license application.
3.4 -Modification of the Mitiqation Plan
We agree that the termination of any mitigation measure stipulated in
the FERC license .,.,auld require FERC approval. In regards to the mon-
itoring program, we anticipate that the FERC license will allow for
-
-
-
-
1 ..
j
J
J
J
, ..
~
.J ,
J
-
-
-
-
-... -
-
-
-
-
-
....
-
-
-
Mr. Robert W. McVey February 23~ 1982
page 2
the termination of the monitoring program when the need for further
mitigation is considered unnecessary. We have modified the policy to
state termination would be subject to FERC approval.
4.4 -Approach to Developing the Fish and Wildlife Mitigation Plans
Paragraph 3~ sentence 6~ refers to the functioning of the Mitigation
Core Group which will be concentrating its efforts towards resources
most likely to be impacted. ·
Paragraph 5, sentence 2. This sentence is contained under Step 2 en-
titled "Option Analysis Procedure". The intent of this procedure is
to consider each impact issue and to review all practicable mitigation
options within the intent of the National Environmental Policy Act.
If a mitigation option that avoids an impact is identified which is
technically feasible, effective, and not in conflict with any other
project objectives, the need to address other alternatives was not
considered necessary. The intent of sentence 2, paragraph 5, was to
state that if such an option does not exist, we will proceed to evaluate
other options. 11 All options considered will be evaluated and documented.
The result of this process will be an identification and evaluation of
feasible mitigation options for each impact issue and a description of
residual impacts."
The selection of which options are to be further considered in the de-
velopment of an acceptable mitigation plan is addressed under Step 3.
Paragraph 7. Mitigation options will be forwarded to the Fish and
Wildlife Mitigation Review Group allowing for agency review and cormnent.
In addition~ our mitigation policy will be modified to reflect our
intent to have the draft mitigation plan formally reviewed by agencies
prior to application to FERC.
I appreciate your comments and trust our response satisfies the concern
you have expressed.
KRY/jmh
ACRES AMERICAN INCORPORATED
Sincerely,
~~~~
John D. Lawrence
Project Manager
....
WILLETT
WITTE
BERRY
\.1 r:. .,.., ...... ~ " ....
~ ,. --... HAYDEN
LAMB rll
Ronald 0. Skoog
issioner
February 23, 1982
P5700.11.92
T. 1527
.t ';" .. .;.,
C... LAWRENCE J: •
ka Department of Fish and Game
Box 3-2000
-A:t
'1..
t:
SINCLAIR
VANDERBURG~ Ul au, Alaska 99802
/
X 6.o'wl£, V"f o: r,1r.-Skoog: Sus1tna Hydroelectric Project
Corrments on F1 sh and Wi.l dl1 fe -P~
CARLSON
FRETZ
JEX
LOWREY
SINGH
..~STEAO
BOVE
CHASE
L r-:c
1.1~
rr
Jn
ri
flO.
[e
.
., ur
~ ust
-' .
t-11tigation Pol icy ·
Hr. Skoog:
ppreciate receiving your corm1ents on the "Susitna Hydroelectric
ect Fish and Wildlife t·11t1gation Policy" dated December 30, 1981.
ddition to addressing your comments in our revised edition of the
cy, I have elected to respond directly to the concerns you have
ed. My comments are organized in the order presented in your
mber 30 letter.
Section 1 -Introduction
definition of fish and wildlife resources included the habitat which
ains them but for clarification we will include the phrase "and the
tat that sustains them" as you recommended.
Comment: We accept the CEQ definition and priority sequence for
mitigation.
2. Section 2 -Legal ~~ndates
We accept that the implementation of mitigation is the eventual goal
and will include the phrase ''and eventual implementation" as you reconncnded.
-Comment: APA is committed to implement appropriate mitigation plans.
-3. Section 2-Protection· of Fish and Game
To broaden the perxpective of the first sentence 1n the first paragraph
we will substitute the word mitigate for reduce. The definition of
mitigate in this context being avoid, minimize, rectify, reduce or
-
-
-
-
-
...
...
-
-
...
...
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Mr. Ronald 0. Skoog
compensate for impacts.
February 23, 1982
page 2
Comment: Avoidance of impacts will be the first mitigation option explored.
4. Section 2-Federal Energy Regulatory Commission, 2nd·paragraph
We will add the phrase "measures and" in the last line of this paragraph.
Comment: This addition meets your request.
5. Section 3.3 -Implementation of the Mitigation Plan
It is our intent to reach an agreement~ through FERC, with those resource
agencies having the mandate to approve the mitigation plan and the implementation
specific agencies have not been stated since it is not considered appropriate
for APA to define other agencies mandates. -It is also considered inappropriate
to discuss such agreements through an informal group such as the Susitna
Hydro Steering Committee.
Comment: APA accepts that the proposed monitory body or its function would
not supersede individual agency mandate. In fact such.monitoring
may be conducted through agencies fulfilling their mandates.
6. Section 3.4 -Modification of the Mitigation Plan
APA intends to work with the appropriate state and federal agencies during
implementation of the plan, including any modifications. The Federal
-. Energy Regulatory Commission must approve any modification to mitigation
stipulation in the license. It is anticipated FERC would not approve these
modifications without first consulti~g with the appropriate agencies. -
-
-
-
-
-
-
Comment: It was not intended to imply APA approval superseded the mandate
of state and federal agencies.
7. Section 4 -Approach to Developing Fish and Wildlife Plans
Third paragraph:
The intent of the ranking of resources is 11 0rder of importance was to
direct mitigation efforts towards those resources where, even without an
extensive data base, it is predicted the greatest impacts would occur.
As an example, the concentration of the fisheries mitigation efforts
has been towards the anadromous fisheries between Talkeetna and Devil
Canyon, as this is an important reserve and there is higher potential for
impact in this section than further downstream.
ACRES AMERICAN INCORPORATED
..
Mr. Ronald 0. Skoog February 23, 1982
page 3
Comment: The delay in the license application will permit a more detailed
mitigation plan to be developed.
Fifth paragraph:
Comment: The intent of this procedure is to consider each impact issue
and to review all practicable mitigation options within the
intent of the National Environmental Policy Act. If a mitigation
option that avoids an impact is identified which is technically
feasible, effective and not in conflict with any other project
objective, the need to address other alternatives was not
considered necessary. The intent of sentence 2, paragraph 5
was to state that if such an option does not exist, we will pro-
ceed to evaluate other options.
No mitigation options will be arbitrarily dismissed. As stated
in the policy, "All options will be evaluated and documented.11
The policy will be revised to make this clear.
Paragraph Seven:
Comment: FERC requires APA to prepare a mitigation plan prepared in
consultation with appropriate resource agencies. This plan
will be based on recommendations from the core groups and
review and comment from the agencies via the Fish and Wildlife
Mitigation Review Group and the formal agency review process.
Subsequent to the FERC filing, the plans will be reviewed by
FERC and other agencies and an acceptable plan finalized. It
is not APA 1 s intent that the mitigation planning be in conflict
in any way with the management and protection responsibility
of any agencies.
Paragraph Eight:
Comment: The Susitna project is being prepared by a state agency. As
such, it wou 1 d be premature to commit funding for· i nvo 1 vement
of other agencies at this time.
General Comments
1. The three month delay in the license application will permit agency
review and input to the mitigation plan.
2. The Policy will be revised to include a description of purpose of
the core and review groups. You w.ill be receiving a letter with
the Feasibility Report outlining what reports will be sent to your
department.
ACRES AMERICAN INCORPORATED
-
-
..i
...
-
IIIII
-
-
-
...
.,
IIIII
.,
...
~
...
-
...
-
-
-
-
-
-
-
-
-
-
-
Mr. Ronald 0. Skoog February 23, 1982
page 4
We very much appreciate your comments on the policy and hope my responses
are satisfactory. If you have any questions, please call.
MMG/jh
ACRES AMERICAN. INCORPORATED
:jJ.:Sinc~Jely yours,
/ /
/..'% ? /~~....--:7-z__.--~-~hn D. Lawrence
Project Manager
I
I
I
..
WILLETT
WITTE
BERRY I
'
M
" ..
-.... ~AYDEN u
LAMB l,
'-'-t:AWRENCE " SINCLAIR '
VANDER BURGH n,
..,., K. To,)tJI-. .
"' f">, ,..,,. \1.~-~
CARLSON T'
FRETZ
JEX '-\I
LOWREY ~-
SINGH ~,
l
-; .iTEAO' ~~
-tsOVE
1
<. ~()0\1<.¥ f-J
I
CHASE
• Melvin A. Honson
t1ng Assistant Regional Director
S. Fish and H1ldlffe Service
11 E. Tudor Road
chorage, Alaska 99503
ar Mr. Manson:
February 24, 1982
P5700.11.71
T.l528
Susitna Hydroelectric Project
:; ~-.
v" Fish and H1ldl1fe ~1itioation Policy
ank you for your letter of December 30, 1981, co~enting on the Fish
d Wildlife· Mitigation Policy for the Susitna Hydroelectric Feasibility
udy. We appreciated receiving a copy of the F&HS f·1itigation Policy
d your explanation of it.
will attempt to aespond to each of your comments, numbered as in
ur letter.
0 Introduction:
This section was purposefully kept short so that the policy would not
be overbearing. He do not feel it necessary to discuss the issues
you mentioned, as they are covered in detail in the Feasibility
Report. At the suggestion of the Alaska Department of Fish and Game,
we have added the phrase "~ristl and \•Jildlife resources of the state".
2.0 Legal Mandate:
-
, _ ____..
The entire policy and particularly sections 3 and 4 explain that
APA intends to develop and impler.~nt a mitigation plan in coordination
with the agencies \'lith mandated fish and wildlife mitigation
responsibilities. ·
2.2 National Environmental Policy Act:
Since FERC is a federal a9ency, they are covered by the staeement
"Federal agencies shall to the fullest extent possible~.
..
-
... · ....... --
...
...
....
...
..
-
....
....
...
...
WJI•
...
...
-
IIIIi
-
-
-
-
-
-
-
-
-
-
-
-
-
Mr. Melvin A. Monson February 24, 1982
page 2
2.3 Federal Energy Regulatory Commission
The policy will reflect the fact these regulations were adopted.
Exhibit E will be prepared as described in the regulations.
2.4 Fish and Wildlife Coordination Act
Reference to FERC has been incorporated.
3.1 Basic Intent of the Applicant
The statement 11 The FERC will resolve any disputes which APA and the
agencies cannot resolve .. has been added.
3.2 Consultation with Natural Resource Agencies and the Public
3.3
A section explaining the mechanism for coordination with the agencies
has been added to the beginning of the policy. The agencies will be
involved in the plan both prior and subsequent to FERC filing.
Implementation of the Mitigation Plan
The implementation of the mitigation plan is recognized by APA to
be its responsibility.
3.4 Modification of the Mitigation Plan Paragraph 2
It is recognized any modification to or termination of the mitigation
efforts would be subject to FERC approval. It is assumed FERC would
consult with the agencies during this process.
4.0 Approach to Developing the Fish and Wildlife Mitigation Plan Paragraph 3
The intent of this paragraph was to direct mitigation efforts towards
those resources where, even without an extensive data base, it is
predicted the greatest impacts would occur. As an example, the
concentration of the fisheries mitigation efforts has been towards the
anadromous fisheries between Devil Canyon and Talkeetna, as this is
an important resource and there is a higher potential for impact
in this section than further downstream.
Paragraph 5
The intent of this procedure is to consider each impact issue and to
review all practicable mitigation options within the intent of the
National Environmental Policy Act. If a mitigation option is
identified that avoids an impact, is technically feasible, effective
and not in conflict with any other project objectives, the need to
address other alternatives was not considered necessary. The
ACRES AMERICAN INCORPORATED
..
Mr. Melvin A. Monson February 24, 1982
page 3
intent of sentence 2, paragraph 5 was to state that if such an
option does not exist, we will proceed to evaluate other options.
As stated in the policy, "All options will be evaluated and docu-
mented ... The policy will be revised to make this clear.
Paragraph 7
This paragraph has been expanded to include the Fish and Wildlife
Mitigation Review Group involvement in the plan's development.
Paragraph 9
Your statement has been incorporated.
Paragraph 10
We agree with your statement. The FERC must approve any modification
to mitigation stipulations in the license. It is anticipated FERC
would not approve the modifications without first consulting with
the appropriate agencies.
Thank you again for your time. If you have any questions regarding my
responses, feel free to contact me.
MMG/jmh
cc: E. Yould, APA
K. Schreiner
ACRES AMERICAN INCORPORATED
Sincerely yours, q;;/
u:~~ ~~D. Lawrence ·
Project Manager
..
...
...
..
...
...
...
..J
-
..J
...
..J
.J
....
..l
..J
...
.....
-
-
-
-
-
-
-
-
-
-
-
.....
-
-
-
w )1,1, »/ uL!du
~,-~r"'"""' ..
•'
£ i...---~·--·
Mr. Douglas G. Warnock
Assistant Regional Director
Alaska Region
National Park Service
540 West Fifth Avenue
Anchorage, Alaska 99501
Dear Mr. Warnock:
~1arch 1, 1982
P5700.11
T. 1425
Susitna Hydroelectric Project
I thank you for your December 30, 1981 response to our request for
review and comment on Susitna project reports forwarded to your agency.
I am pleased that you are satisfied to date with our cultural resource
identification and management, recreation planning and Development
Selection evaluation process.
In regards to the review of subsequent reports we are receptive to
including your agency in the water quality and use, aesthetics and land
use groups if you consider this information beneficial in performing
your formal review of project related recreation impacts. We are entlosing
the 1980 Land Use Annual Report.
KRY I jmh
Enclosure
xc: Eric Yould, APA
ACRES AMERICAN INCORPORATED
,. -; ::~~ ·:.:e-~s
-:-. t;;. ·:::_•:: =~-!.-E. .... ·; .. 2 •. ~ .• -:· ~·:
::. ...... ;: ·!·,_.:.. .. £ ~ t;
~D7~rely yours, £ /2vv~t-A---z~--;'~
(,_A. .ioh~o. Lawrence
Project Manager
..: :.£. ._.. -~ f·· -·:..:::.. :; ..JF
~
Ms. Lee McAnerney
Department of Community and
Regional Affairs
Pouch B
Juneau, Alaska 98111
Dear Ms. McAnerney:
February 25, 1982
P5700 .11. 92
T .1533
Susitna Hydroelectric Project
Agency Coordination Meetings
As an agency representative of the Historical and Archeological Group
r~v1ewing the Susftna Hydroelectric Project you are invited to a meeting
on the morning of ~arch 15, 1982 in the offices of Acres American Inc.,
1577 "Cn Street, Suite 305, Anchorage, Alaska. The purpose of this meeting
w111 be to review the results of the Phase I archeological studies, assess
mitigation options and discuss future study programs.
If you have any questions relatfng to these meetings, please contact
Mr. Vern Smith of Acres
1
at (907) 276-4888.
KRY/1jr
Sincerely,
John D. Lawrence
Project t4anager
..,
-
..,
-..
...
....
...
..
...
IIIII
...
...
..,
..,
...
....
....
-
-
-
-
-
-
-
-
-
-
r~r. !'.oy Huhndorf
Pre;;ident
Cook Inlet Region, Incorporated
P .0. Crawer 4R
Anchorage, Alaska 99509
Dear Mr. Huhndorf:
re~ru!ry 25, 1922
P5700 .11.50
T .1537
Sus1tna Hydroelectric Project
A~ency Coordination ~eet1ngs
As a member of the Aesthetics and Land Use Group reviewing the Susitna
Hydroelectric Project you are 1nv1ted to a meeting on tha afternoon of
~~arch 15, !932 1n the offices of Acres Arnerfcan Inc •• 1577 8 C" Street.
Sufte 305, Anchorage, Alaska. The purpose of this neet1ng w111 be to
discuss the results of the Phase I studies and to review the alt~rnative
and proposed recreation plans.
If you have any questions relating to these ~eetfngs, please contact
Nr. Vern Smfth of Acres at (907) 276-4388.
KRY/ljr
Sincerely,
John D. Lawrence
Project ~~ana ger
Mr. ~efth Schreiner
Regional Director. Region 7
U.S. rtsh and ~!fldlffe Service
lOll E, Tudor Road
Anchorage, Alaska 99503
Oear Kr. Schreiner:
February 25, 19?2
?5700 .11. 71 '
T .1537
Susftna Hydroelectric Project
Agency Coordination Meet1nos
~i a rnanbcr of the A~tthatfcs/Land Use and ?.~cr~atfon Croups revf~~ing the
Susftna ~ydroelectric ?roject you are invited to a m!etinq on the afternoon
of ~arch 151 1932 in the offices of Acres Am~rfcan Inc., 1577 "CM Street,
Suit! 305, Anchoraae, Alaska. The purpose of this meeting will be to discuss
the results of the Phase I stuc1es and to review the alternative and pro-
posed recreation plans.
If you h~ve any questions relating to these meetings, please contact
nr. Vern Smith of Acres at {907) 276-4888.
KRY/ljr
Sincerely,
John D. LaHrence
Project ~<:lnager
....
..
...
....
..
,.,
...
..I
..
....
-
flllll
..,
,.,
...
..
-
....
-
..._
-
-
-
-
-
-
-
-
.....
-
-
-
-
-
-
Mr. Ronald 0. Skoog
Commissioner
State of Alaska
Department of Ffsh and Game
Subpart Building
Juneau, Alaska 99801
February 25, 1982
P5700.ll.92
T .1531
Dear Mr. Skoog: Susitna Hydroelectric Project
Agency Coordination Meeting~.
As an agency representative of the Historical and Archeological Group
reviewing the Susftna Hydroelectric Project you are invited to a meeting
on the morning of March 15, 1982 fn the offices of Acres American Inc.,
1577 "C" Street, Suite 305, Anchorage. Alaska. The purpose of this meeting
will be to review the results of the Phase I archeological studies, assess
mitigation options and discuss future study programs.
As a member of the Recreation and Aesthetics/Land Use Groups you are also
invited to a meeting at the same location on the afternoon of March 15, 1982
to discuss the results of the Phase I studies and to review the alternative
and proposed recreation plans. ·
If you have any questions relating to these meetings, please contact
Mr. Vern Smith of Acres at (907} 276-4888.
KRY/ljr
cc: Mr. Thomas Trent
State of Alaska
Department of Fish and Game
2207 Spenard Road
Anchorage, Alaska 99502
Sincerely,
John 0. Lawrence
Project Manager
~,r. Robert McVey
Director, Alaska Region
Plat1ona1 l".arine Fisheries Service
NOM
P.O. Box 1668
Juneau, Alaska 99802
February 25, 1982
PS 700.11.92
T .1535
Dear Mr. McVey: Susitna Hydroelectric Project
Agency Coordination Meetings
~ --
As a representative of the Recreation Group revfewfng the Susitna Hydro-
electric Project you are invited to a meeting on the afternoon of f-1arch 15,
19S2 in the offices of Acres American Inc., 1577 "C• Street, Suite 305,
Anchorage, Alaska. The purpose of this meeting will be to discuss the
results of the Phase I studies and to review the alt2rnative and proposed
recreation plans.
If you have any questions relating to these meetings, please contact
~1r. Vern Smith of Acres at (907) 276-4888.
KRY/ljr
cc: Mr. Ron ~orris
Sincerely,
John D. Lawrence
Project Manager
Director. Anchorage Field Office
~lat1ona1 Marine Fisheries Service
701 "C 11 Street
Box 43
Anchorage~ Alaska 99513
...i
-
IIIII
---
IIIII
.,
...
.,
.,
....
.,
...;
-
...,
...,
-
-
-
-
-
-
-
-
-
-
-
-
Mr. John E. Cook
Acting Regional Director
Ala5.k& Offfce
National Park Service
540 West Fifth Avenue
Anchorage, Alaska 99501
Dear Mr. Cook:
February 25, 1982
P5700 .11. 92
T .1532
Susitna Hydroelectric Project
Aqency Coordination Meetings
As an agency representative of the Historical and Archeological Group
reviewing the Susftna Hydroelectric Project you are fnvfted to a meeting
on the morning of March 15, 1982 in the offices of Acres ~~erican Inc.,
1577 "c• Street, Suite 305, Anchorage, Alaska. The purpose of this meeting
will be to review the results of the Phase I archeological studies, assess
mitf~ation optfons and discuss future study programs.
As a member of the Recreation and Aesthetics/Land Use Groups you are also
invited to a meeting at the same location on the afternoon of P4rch 15, 19822
to discuss the results of the Phase I studies and to review the alternative
and proposed recreation plans.
If you have any questions relatfn9 to these meetings, please contact
Mr. Vern Smith of Acres at (907) 276-4888.
KRY/ljr
cc: Mr. Larry Hright
Nation a 1 Park Service
lOll E. Tudor Road, Suite 297
Anchorage, Alaska 99503
Sincerely,
John D. La\'/rence
Project Manager
l~;»i-J
[
1'1~ r" t-;; :_; ~ , i:~!. L~r . '· . L~ ~~t...,
Mr. Al Carson
Division of Research & Development
Department of Natural Resources
323 East Fourth Avenue
Anchorage, Alaska 99501
Dear Mr. Carson:
-
February 26, 1982
P5700.11. 74
T. 1539
Susitna Hydroelectric Project
Fish and Wildlife Mitigation
As discussed through Vern Smith of our Anchorage office, meetings to re-
view fish and wildlife mitigation efforts are scheduled for March 11 and
12, 1982 in the offices of Acres American, 1577 C Street, Suite 305,
Anchorage, Alaska.
As these meetings are expected to be in the form of technical workshops,
a complete day on each of the topics of fish and wildlife is considered
necessary. Proposed agendas are enclosed. I will also forward, within
the week, updated information packets addressing fish and wildlife im-
pact issues and mitigation options.
As fisheries issues are being discussed on a separate day from wildlife
issues, please feel free to have different technical personnel attend
each of the meetings if you consider it appropriate.
As we consider these meetings to be an important component in improving
the coordination between your agency and our fish and wildlife mitigation
core groups, your attendance is encouraged.
If you have any questions relating to these meetings please contact my-
self or Vern Smith (907-276-4888).
Sincerely,
Kevin Young
Environmental Coordinator
KRY:dlp
Enclosures
ACRES AMERICAN INCORPORATED
c~-·.c;!!•ng E~g·r.ee·s
Tr....: :..:::~r:J 8~"\k !: ... i'::.~g :.~a~ ::t ':l)ur!
E...:":-.~j. ~;0·:: Vc·•. ~.:2:-2
-~::::---~~':;';e.::; .. --:~;. i£-·(;, ~"-·:.!~:; ;.cF-::s e.vF
~.·~ ,._. G·H ::.E:s cc·_-: a r:::> ::-.··:.:.. _,j .... ;..,~ ?a:-:·;:"'1 :~: ·::c.-; ... ~~~:.~ DC
...
...
...
..
---
-
-
...
---
..,
..,
.,;
--
-
-
-
....
-
-
-
-
-
-
-
-
-
~1r. Ty :::; 11 i plane
State ~istoric Preservation Off1cer
Alask~ Oepartw~nt of Natural Resources
Division of Parks
619 ~arehouse Avenue, Suite 210
Anchorage. Alaska 99501
~~rch 2, 1982
;'~700.11.92
T.1534
Dear Hr. Shaw: Sus1tna Hydroelectric ?reject
Aoency Cc~rdinat1on f~etin~s
As an agency representative of the Historical and Archeological Group
reviewing the Susitna HyJroelectric Project you are invited to a meeting
on the mon1ing of r~arch 15, 1982 in the offices of Acres .A~merican Inc. •
1577 aC" Street~ Suite 305~ Anchorage~ AlAska. The nurnose of this
meeting ~ill be to review the results of the Phase I archeolo1ical
studi~s. assess r.:itiqaticn option~ and discuss futu~ study nrcor,lr..s.
If you have any questions relating to these reetinos~ r1ea~~ contact
Mr. Vern Smith of ~ere~ ~t (907) 276-l~~u.
KRV:dlp
cc: rr. ,'\liln Cnr~on
Sincerely,
John D. Li'!'.Jrence
Project filana11Ar
Divisicn of nes~arch ; lr~elo~mcnt
De~artn~Cnt of r;atur:tl Re50;JrCCS
Pouc!'l 7-:105
Anchcra~e, Alaska 9~511
3JN30NOdS3~~0J d00~9 M3IA3~ NOI1~9I1IW 3~IlOliM ON~ HSI~
2-8 XION3dd~
-
-
-
-
-
-
-
i
' -I " -' r. . .,
l -; -
._; ..
,
f
SUSITNA WILDLIFE MITIGATION TASK FORCE
NOTES OF MEETING
January 30, 1981
Anchorage, Alaska
Compiled by: Edward T. Reed
Wildlife Ecology Group Leader
Terrestrial Environmental
Specialists, Inc.
The meeting was commenced at 9:00 a.m.
i -I·
Mr. Reed presented a brief out1ine (attached) describing the
_organization and functioning of the task force. At the request of Mr.
Carson, the word "procedures" {Purpose of the Task Force, Item #1) was
changed to "options".
-
\._
\,
' .
(
~
)
~
r
'
i .•
I
f
r
fc
J
~
. ": :·;~~: ,i'2:, : ~~ c'~~;c}r0"P: ~· }_ ; \,L,;' ~ ~-:<:· • _ ::; • : .;''7: , _ . _ '.< , ~ ,. -~Pi -.· ... ""'-~-
.
• i
~ ..
-2-
~o dual role of Mr. Schneider as a representative of AOF&G was
:cussed by Sc~neider,_ Trent, Reed, Lucid, Carson, and Wozniak. A
concensus was reached that Mr. Schneider's participation in the core
group was appropriate due to his technical participation on the $usitna
Study Team as leader of the big game studies. All official responses
from ADF&G as a participant in the review group will be handled by Mr.
rrent, who will consult with Mr. Schneider on technical matters. This
arrangement was satisfactory to the meeting participants.
I
There were no comments concerning information on the outline pertaining
to the Role of the Core Group, the Role of the Review Group, or the
Role of the Task Force Coordinator.
i
1 Mr. Carson raised the issue of whether or not members of the review
1 group should be required to prepare a written discussion of concerns,
1-issues and policy statements. Mr. Carson felt that it was the
! . responsibility of TES to prepare such material for review and comment
'' by the review group. Following discussion of this issue, it was agreed
· that the Task Force Coordinator would draft a policy statement
• incorporating agency concerns and submit it to the review group for
, comment. It was suggested that agency concerns could be better
t identified through personal interviews with representatives of each
~ agency. TES and Acres will consider this approach.
~ • "( ! Mr. Wozniak questioned whether or not all appropriate agencies were
J included in the mitigation task force. The involvement of the U.S.
~ Corps of Engineers, the Environmental Protection Agency, and the
j National Marine Fisheries Service were raised. TES and Acres will keep t these agencies in mind as the task force proceeds, althou9h Mr. Reed
1 indicated that the participation of these agencies may be either i premature at this point in time, or be more appropriately included in 1 the fisheries mitigation effort. Mr. Wozniak also raised the question
f of involvement by special interest groups. Mr. Reed and Dr. lucid
I responded that the concerns of special interest groups were more
J appropriately coordinated through the Power Authority's public
i participation program. TES will prepare a list of agencies and/or
i groups that may be considered for consultation in the future if f pertinent issues concerning such groups develop.
t
I
I
i
It was discussed, and generally agreed upon, that there are limitations
to the level of detail of mitigation planning that can be performed
within the Phase I time frame. Dr. lucid, Mr. Reed, and Mr. McMullen
pointed out, nevertheless, that to comply with FERC regulations, the
. 1 icense application must represent a commitment on the part of the
1 applicant and that identification of "options" may not be sufficient.
l
~
..,
J
J
.J
_,
..,
\ ....
...
l
( .J
t. -
) c " _..,
-r
' -j
I
;_IJ (
7
(
( ~-I ~
' I -,
r
-
I
--~
--; I
-..
--
-,~
; ~--"-_,......._.-: .. -.--
.-.::.:,._--.)~·· -• taS decided that individual review group members will address all
~espondence to the APA, with a copy being sent directly to Mr. Reed,
-;. ~ti 11 back-channel a copy to Mr. Young at Acres. Mr. Wozniak
1rized the Task Force Coordinator (Mr. Reed) to represent the core
--?UP and correspond directly with members of the review group. ·Mr.·
~~requested written confirmation of this authorization from Mr.
{!:-;ng. ~1r: Young indicated that Acres would provide the requested
· ~;cumentat 1on.
-I ! Following discuss ion, it was agreed that Mr. Reed would reevaluate the
j ;chedule outlined on the handout. Mr. Carson requested that a meeting
i-ce held following preparation of a pol icy statement and review by the
f review group members.
f ·-~. Stackhouse indicated that the USFWS had recently (within the past
week) published a statement of mitigation policy in the Federal
Register. Mr. Reed thanked Mr. Stackhouse for this information and
-indicated that the pol icy statement would be reviewed at the earliest
possible date.
-~ followin~ discussion it was decided that the core group should first
prepare a mitigation policy, and following review, proceed with the
preparation of a mitigat1on plan. ---·:
Stackhouse stated that cost effectiveness of mitigation plans is an
;-.. nportant concern of the USFWS.
i
r
1.
l
L t
f r
i ~ t
E
I
i.-
'
i:-
i
._
; l~
The question was raised by Or. Lucid as to whether the applicant had
any responsibility to enhance a resource, as opposed to avoidance of
impacts or compensation. It was agreed that TES, in its mitigation
planning, would "identify enhancement opportunities" and stop there.
The subject of compensation of impact on one species (e.g. moose) by
enhancement of another (e.g. salmon) was mentioned. No agreement was
reached on the validity of this concept.
The question of whether or not the review group should have a chairman
was raised. Mr. Reed expressed concern that some details may be lost
if one person was responsible for compiling and possibly summarizing
agency comments. Mr. Carson also advised against the appointment of a
chairman at this time. For the present time, the idea of a review
group chairman was dropped;
Mr. Reed requested that a list be prepared with the name~ mailing
address, and phone number of all review group members. This list was
completed and is attached.
The meeting was~ adjourned at approximately 11:15 a.m.
b.}_§~ ... _,;¥Z:_;f7 ... • ~ ..,.s ' ;;_< 4-.. ce _xz cw ---
. ~ , .,.. . , e:£1::: =<:~~·;,~3~~;~l~:: :,:~ ~ ~ · ~'?S' :_ -......,...,~_,.
., .
J
f i
( ,,
I!
)
1 c
1""
f
! II i j
f ,. II '
. '
l/
J '
I -l":
I
! -;i I . ] -• ~f
' l • ~~
1 • i ~
-I
~l
~
i • 2f ~ ~
~ ;
; .,
I
;.. -... 1
-~i
"'v..-:-t: ko• ·~
-
j
-!
··:.
.. -.' . ./.; .. , ..
-·
,
•. ~.' ... -"_ .. ~ i
f~
~ .... "' -;r~·~-·-.......
PARTICIPANT
Edward Reed
Joseph McMullen
Vincent Lucid
Robert Krogseng
Richard Taber
Jay t·1cKendr i ck
'Ni 11 i am Co 11 ins
Brina Kessel
Steven McDonald
Ph i 1 i p G i p son
Karl Schneider
Thomas Trent
Kevin Young
David Wozniak
Bruce Bedard
Alan Carson
Mike Sec tt
Gary Stackhouse
Bruce App ie
\,
SUSITNA WILDLIFE ~HTIGATION TASK FORCE
MEETING OF JANUARY 30, 1981
ANCHORAGE, ALASKA
LIST OF PARTICIPANTS
REPRESENTING
Terrestrial Environmental Specialists,
Terrestrial Environmental Specialists,
Terrestrial Environmental Specialists,
Terrestrial Environmental Specialists,
Terrestrial Environmental Specialists,
University of Alaska
University of Alaska
University of Alaska
University of Alaska
University of Alaska
Alaska Department of Fish and Game
Alaska Department of Fish and Game
Acres American, Inc.
Alaska Power Authority
Alaska Power Authority
Alaska Department of Natural Resources
United States Bureau of Land Management
United States Fish and Wildlife Service
United States Fish and Wildlife Service
Inc.
Inc.
Inc.
Inc.
Inc.
..
....
...
_,
1
.J
_,
-
..,;
., ..
(
l
) ..
~ -r
I :...,
:-I l ~ t~
l =r:
I ' \ ~.:r
•
-,J
'
-..
-
-....
-
• .• f
... --~
{
./ -l. • I -/ J.-:.~1 Err E s L r t a RECEIVF=D J UN 1 7 tSB1
~ ... .__ ..
• -.,._ ---.Jf ,... • "-I f~:~\::nVfrOnmEn La
'c?/;:;.;:;.:=.:-~· ~ • [ • .!.. • ~-'Sh-PECla lSLS~ InC. --==~:.--~~ •J fLO.\ 9CX 388 PHOENIX. N.Y. \3135 (J!SI695·72Z8
-
~
-
A tSKA POWER I MEMO
tUTHORITY -SUSITNA
f .E P57QO
• 1,. ac -~QUENCE NO.
r lu 1/' a
~~ lct: !O.
ai
~
t-
Ill
0
..J < t: z
TO Members of the Susitna Wild~ife Mitigation Task Force
FROM: Edward T. Reed, Task For~e Coordinator ~-
DATE: June 16, 1981; 218.683
RE: Comments concerning the preliminary policy outline.
Enclosed please find another copy of the preliminary outline for the
wildlife mitigation policy statement. I have inserted review comments
that have been received todate. The comments have been plac~d
immediately following the appropriate item. In the case of those
comments that pertain to an entire section, they follow the last item
of each section. In most cases, comments have been transcribed
verbatum, although some comments had to be extracted from the
correspondence and minor editorial changes were made.
It should be noted that this was a detailed outline and some of the
comments would have been unnecessary if a fleshed out text version was
available for review. It was impossible to totally explain all of the
j~~ deta~ls and ramifications of each item within the context of an
~~ outl1ne.
Please review the comments made by other task force members and be
prepared to discuss possible adjustments to the policy statement. As
noted in my memo of May 8, 1981, the next meeting of the mitigation
~8LE 1 Jtask force will be held at 9:00a.m. on Monday, June 29th, in the Acres
Anchorage Office. Hopefully a final version of the pol1cy statement
can be agreed upon during that meeting and we can move forward with a
discussion of how best to develop a mitigation plan based upon the
policy statement.
-
'1 "
~
I !i II
L
1 -BACKGROUND
1.1 -The Need
WILDLIFE MITIGATION
A STATEMENT OF POLICY
PRELIMINARY OUTLINE
Included will be a general discussion of the value of the
environment and why it is necessary to reduce or avoi~ negative
impacts while still permitting reasonable energy development.
Comment
USF&WS:
This section should include a discussion of the need to
adequately assess the environmental resources of the study
to determine the compatibility of the proposed project and
evaluate mitigation to adequately reduce or avoid negative
area
to
. impacts to environmental resources, including fish and wildlife
resources, so that no net loss of habitat value occurs.
1.2 -Legal Mandates
The Federal Energy Regulatory Commission regulations, the Fish
and Wildlife Coordination Act, and the National Environmental
Policy Act will be discussed, as well as a consideration of the
role of state and federal natural resource agencies whose task it
is to protect and manage wildlife resources.
1.3 -Definition of Mitigation
This will be the 5 part NEPA definition.
...
..
...
_,
,.
..l
..
' J
...
~ ..
..,
wli
..
.,J
...
-
-
...
-
-
-
-,' ' \
... :--
-
-
-
-
-
,.._
-
2 -GEHERAL ?OLICIES TO BE CARRIED OUT BY THE APPLICANT
2.1 -Basic Intent of the Applicant
(a) The goal of the applicant is to strive, within the bounds of
feasibility and reasonable costs, to minimize the negative
impacts of the Susitna Project and compensate for
unavoidable losses of wildlife and wildlife habitat.
Comment
USF&WS:
The~ of the applicant should be to develop a plan to fully
mitigate unavoidable impacts which would result from the
construction and operation of the project with full compensation
for unavoidable losses to fish and wildlife resources.
(b)
Comment
USF&WS:
The success of the mitigation effort will be considered the
difference between impacts without mitigation and impacts
with mitigation. A "no net loss of habitat value" will
serve as the benchmark for measuring both the success of the
mitigation effort and project impacts.
Success of the mitigation effort should be assessed through
comparison of habitat value of the study area with the project,
including the mitigation plan, vs. without the project, over the
project life. No net loss of habitat value, as determined by
pre-and post-project studies is the goal. Acceptable habitat
evaluation procedures (such as the Fish and Wildlife Service's
Habitat Evaluation Procedures and Instream Flow Methodology)
should be used to accomplish this goal.
McMullen:
"No net loss of habitat value" looks good, but it must be decided
how to assess habitat value. Also, are with and/or without
project scenarios going to be considered?
Gipson:
Good statement.
(c) The applicant will provide assurances that the agreed upon
mitigation plan will be a stipulated part of the
construction and operation plans of the project and will be
executed by either the applicant or any other organization
charged with managing the project.
Comment
USF&WS:
The mitigation plan should be developed by the applicant, in
coordination with the state and federal resource agencies. The
plan, as agreed upon by the coordinating agencies, should be
submitted by the applicant to the Federal Energy Regulatory
Corrmission (FERC) as a component of the application to be
incorporated into the license.
2.2 -Input From Agencies and the Public
(a) The applicant will provide opportunities for the review and
evaluation of concerns and recommendations presented by the
public as well as by federal and state agencies.
Comment
USF&WS:
Additional review and evaluation of the project will be provided
through formal agencies comments in response to state and/or
federally administered licensing and permitting programs.
(b) Agency comments and recommendations will be provided by
those members of the Mitigation Task Force that represent
agencies, while the concerns of the public and special
interest groups will be coordinated through other means.
..
.. ...
~
J
-
-
...
..
..
...
...
--
-
..
-
---..
-
-
-
....
·-
Corrrnent
Gipson:
You mcy wish to _spell out how input will be obtained from the
public and how to weight the recommendations from individuals,
interest groups, and governmental agencies.
McMullen:
One of the comments at the Steering Committee meeting was that
the agency representatives in many instances cannot "officially"
represent their agency.
2.3 -Avoidance and Reduction of Impacts
(a) During the feasibility studies (prior to FERC license
submittal) and the subsequent preparation of preliminary
~-engineering specifications (following FERC license
submittal), the applicant will take into consideration, and
where practical {both from the standpoint of actual
feasibility as well as cost), incorporate recommendations to
avoid and/or reduce negative impacts on wildlife resources.
,_
~l
""'
.... :
-
Comment
USF&WS:
The project, including mitigation found to be acceptable to the
state and federal resource agencies, should be evaluated in
regard to reasonable cost; not with and without the mitigation
plan. The total cost of mitigation then becomes part of the
total project cost.
(b) Also considered under this policy will be operation
stipulations that can be implemented to reduce negative
impacts on the wildlife resource. Recommendations for
operation stipulations will be provided to the design
engineer during both the feasibility studies and the
preliminary engineering phase as appropriate •
~
Comment
USF&WS:
Construction and operating stipulations to reduce negative
impacts to fish and wildlife resources should be evaluated during
the feasibility studies. Stipulations found acceptable by the
coordinating agencies should be incorporated into the mitigation
plan submitted as part of the license application.
2.4 -Compensation for Unavoidable Losses of Wildlife Resources
(a) Where biologically feasible and cost effective management
techniques are available, the applicant will institute
management efforts to compensate for unavoidable impacts.
Comment
USF&WS:
Compensation for unavoidable losses to fish aod wildlife
resources should be in accordance with a plan developed by the
applicant, in coordination with state and federal resource
agencies. The plan, found acceptable to the coordinating
agencies should be submitted to FERC for incorporation into the
project license. The compensation plan, a component of the
overall mitigation plan, should be the result of a habitat
evaluation, utilizing a procedure judged acceptable to the state
and federal agencies with primary responsibility for fish and
wildlife resources.
(b) Where possible, compensation will be of an in-kind nature.
Comment
USF&WS:
This applies to both wildlife species as well as
habitats.
In-kind compensation where "possible"; should be mutually
' determined by the applicant and the coordinating state and federal
agencies, prior to licensing.
..
..
..
.,J
"" ..
...
.,.;
..
...
--
...
-
•fill
..,
-
..,
-
...
--
-
...
"..:
-
-
....
~
2.5 -Geog;aphic :CJverage of the Wildlife Mitigation Policy
(a) In res:~cd to both impact avoidance and compensation, the
mitigat~:on policy will address all wildlife species
utilizinag the impoundment zone and other project related -'
Comment
USF&WS:
areas (ee.g., borrow sites), as well as the riparian zone
downstre=am to Talkeetna •
Determination of the extent of impacts attributable to the project
needs to be ac:complished. Formulation of a mitigation plan cannot
proceed until the extent of the impacts, both direct and indirect,
has been identified.
McMullen:
If key or target species are used to evaluate habitat values then
this may requ~re rewording.
Gipson:
What treatment will be given to access roads, power line rights-
~f-way, and pcssible buffer zones around the impoundments?
(b) Downstre~m from Talkeetna to Cook Inlet the primary
mitigation effort will be directed towards any impacts that
might occur in regard to riparian habitats.
Comment
USF&WS:
The mitigation effort should be directed at reducing impacts where
they are identified, addressing all primary and secondary impact
areas, for all project features .
Taber:
It seems probable that 100% mitigation above the dam will not be
feasible, so mitigation below the dam may be one of the next best
choices. If a broad view of what "below the dam" consists of is
maintained, then more mitigation options will be available than if
the view is narrow.
2.6 -Establishment of Priorities
(a) Although all wildlife species will be considered (including
big game species, non-game species, and furbearers), it will
be necessary to identify the "key" or "target" species and
establish some order of priority in regard to the development
of a mitigation plan.
Comment
McMu11 en:
If key or target species are used to evaluate habitat values then
this may require rewording.
{b) In order to prepare a mitigation plan that can be
Comment
Gipson:
successfully implemented while at the same time placing
mitigation efforts in perspective, certain wildlife species
and/or habitats will be given priority in mitigation planning
based on: 1) importance of the species/habitat both to
Alaskan residents and the ecosystem; (2) availability of
practical mitigation measures; (3) species with special
status, such as threatened or endangered; (4) estimated costs
required to execute mitigation measures. This list of
criteria is not organized in any priority order.
Possibly something should be added to indicate that some
ecological criteria will be used to establish priorities, in
addi~ion to human values. For example, those species that
contribute significantly to total energy flow through the system
(small mammals and nesting birds) and/or those species that make
up the bulk of animal biomass (again small mammals) should be
considered important.
McMullen:
These criteria could be easily expanded to be utilized in the
generation of relative value indicies.
..J
..
...i
.,j
~
....
...
,J
...
...
-
-
-
-
...
-
_,
-
...
....... ,_? .... --7"" ... ~>:;-. ~ ..... _ ..... _.
-
-
-
......
-
-
-
( -
-
-·
-
-
-
' l ~-
--.---~---
USF&WS: (pertains to 2.6 in general)
Since all wildlife species are to be considered, ''key" species
should be chosen so that they represent particular segments
{guilds) of the community. Species which provide guild
representation and are also conside~ed "important" by the resource
agencies and/or public should be given priority. Species which
are federally listed as threatened or endangered, or proposed for
listing, must be handled separately in accordance with Section 7
of the Endangered Species Act. The practicality of the mitigation
plan developed, in regard to the concerns of the applicant and
coordinating agencies, would be demonstrated through its
acceptability to these agencies.
2.7-Impact-Related Versus Non-Impact-Related Lands
(a)
(b)
To the greatest extent possible, mitigation measures will be
implemented on or immediately adjacent to the area where the
impact takes place.
Where this is not possible, priority will be given first to
suitable areas as close as possible to the area of impact.
(c) As a last resort, areas totally removed from the impact area
will be considered for mitigation efforts.
Comment (pertains to 2.7 in general)
USF&WS:
Statements apply to both direct and indirect impacts.
Schneider:
In sections 2.7 and 2.8, you emphasize mitigation close to the
impact area even to the point of enhancement of a different
species rather than move to a more distant area. The problem is
in definition of such terms as "reasonable proximity". Users of
wildlife are fairly mobile and tend to greatly favor one species
over another. This, combined with practical considerations, might
make it difficult to stick with the policy.
\
I ha\.en't given this a great deal of thought, but an alternate
appr~~=h might be to direct mitigation measures at the animal
pop~-===ion or subpopulation impacted when this is clearly
feas-7zle.
When :=Tie feasibility of this approach is in doubt, perhaps
miti~~ion measures should be directed at user groups. A series
of aT~:rnate mitigation masures could be drawn up and submitted
for pUJblic review.
The pc~nt is that the public might agree with your policy, but
disac~:e with your plan when they see what it means in reality. -Why nc= recognize that the issue is complex and subjective from
the s~rt?
2.8 -In-Ki~d Compensation Versus Availability of Areas Suitable For
Mitic3tion
(a) In the event that suitable areas for in-kind compensation
for a particular species/habitat do not exist within
reasonable proximity to the impact area, the first priority
will be to compensate for such loss by enhancement of a
different species and/or habitat that is close to the impact
area.
(b) If compensation by means of a different species proves
impractical or unacceptable, in-kind compensation in areas
totally removed from the impact area will be considered.
Comment (pertains to 2.8 in general)
Schneider:
See comment under 2.7.
-
-
-
...
~
.,
-
" .... ..
...
...
--..
...
...
..
...
t '
..il
-
.....
""::.;
-
·-
-
.._..
'-
-
\,_
2.9 -land Ownership
(a) Interviews will be conducted with private owners as well as
pertinent state and federal agencies to preliminarily identify
land use policies or ownership that may act as constraints on
mitigation efforts.
(b) Where no land use constraints have been identified, the
analysis of mitigation alternatives will proceed based on
biological factors.
(c) Following review by agencies and private landowners for
compatibility with land use policies, the mitigation plan will
then be reassessed and adjusted as necessary in order to
insure that proposed actions can be legally and practically
executed. Where mitigation opportunities exist, the applicant
will work closely with land management agencies to insure the
successful implementation of the plan.
2.10 -Restoration of Disturbed Areas
Comment
USF&WS:
The applicant will consider various options (e.g. regrading and
revegetation, permitting natural invasion and succession, etc.)
in the reclamation of areas that will be disturbed by project
activities such as borrow areas and construction camps.
Restoration of disturbed areas should be in accordance with a plan
developed by the applicant, in coordination with the state and
federal resource agencies. The plan, found acceptable to the
coordinating agencies should be submitted to FERC for incorporation
into the project license.
L
McKendrick:
I would emphasize that the revegetation, etc., of borrow areas be
coordinated with land use policies of owners. Also, considering
such areas as prospective browse production sites may be feasible,
if there is any soil available after excavation. They may be
considered potential sites to compensate for browse losses in the
impoundment areas.
Heavy grass seeding will probably retard natural succession of
browse species. We really need to examine some of the myriads of
highway and seismic disturbances to see if we can identify
successional sequences and bypasses and develop some reasonable
scheme in habitat formation for this region.
2.11 -Nuisance Animals
Comment
USF&WS:
In order to avoid altering the natural behavior of animals
resident to the project area, rules designed to prevent, or
reduce nuisance animal problems will be established. Procedures
will also be formulated to relocate problem animals.
A plan, found acceptable to the coordination agencies, should be
developed and submitted to FERC for incorporation into the project
license.
Schneider:
Relocation is generally a poor policy as animals usually return or
cause problems in other areas. Animals can be captured only under
permits issues by the Commissioner of Fish and Game. He will set
policy on this issues, not APA.
Gipson:
Other possibilities may be: 1) strict garbage control and
disposal, 2) fencing of semi-permanent camps, 3) education
programs for workers to prevent feeding and harassing wild animals
in order to reduce impacts and conflicts with people.
....
-
...
...
..
'e'l
....
• ...
-
...
-
.,1
IIIIi
~
-
-
-
-
-
..,._
-
-
.....
_(
.....
.....
-
'-
-
-
L
~
2.12 -Access
(a) Since the potential impact of increased human access on
wildlife is a major concern, measures will be considered and
the most appropriate ones implemented to reduce impacts on
wildlife as a result of improved access.
(b) This will include access policies during both the
construction and operation phases of .the project.
Comment (pertains to 2.12 in general)
USF&WS:
\
A plan~ found acceptable to the coordinating agencies, should be
developed and submitted to FERC for incorporation into the project
lic~nse.
2.13 -Hunting
(a) Acknowledging that sport hunting is an important component
of the Alaskan lifestyle and economy, it will be
incorporated as a major component in mitigation planning .
(b) Hunting rules and/or recommendations to insure the safety of
project personnel and_the public will be considered .
(c) For obvious reasons, any policy determination concerning
hunting must be integrated with access policy and the
applicant will consider both access and hunting policy in a
coordinated manner.
Comment (pertains to 2.13 in general)
USF&WS:
This section should be expanded to include other forms of wildlife
recreation as well, e.g., bird watching, photography. A plan,
found acceptable to the coordinating agencies, should be developed
and submitted to FERC for incorporation into the project license.
Gipson:
I would like for you to include trapping and fishing in this
section if you feel they are appropriate for inclusion.
Schneider: ·
Replace "sport hunting" with "hunting and trapping". Many
Alaskans would interpret your wording to exclude subsistence
hunting. This issue is both difficult to define and highly
emotional. There is no need to raise it here. Obviously, we want
to preserve all legal hunting and trapping options.
Any hunting rules or policies other than those instituted by an
employer on their employees are the responsibility of the Board of
Game. APA can make recommendations as can any group or
individual, but it is up to the Board of Game to examine all
factors and set regulations for dealing with pro~lems.
IIIIi
...1
IIIIi
-
•
.,.J
...
..t
Reed: •
( It may be that this section is not appropriate at all for
i
'
inclusion with a wildlife mitigation policy effort and may be
better sui}ed for prime consideration under the recreation
planning portion of the Susitna study effort; although
coordination between recreation planners and the wildlife
mitigation group is certainly necessary.
2.14 -Responsibility For Implementation of the Mitigation Plan
Comment
USF&WS:
(a) Prior to the initiation of construction an agreement will be
reached for determining responsibility for implementation of
the mitigation plan.
Responsibility for implementation of the mitigation plan rests
with the applicant. Any agreements entered into by the applicant
for the delegation of direct implementation authority for the
mitigation plan would need to include stipulations to prevent
deviation from the accepted plan.
....
..
,.J
-
IIIJ)
-
-
-
....,
-
-
.__
-
.......
-
-
-
-
......
-
-
......
t
.....
Reed:
Due to wording there is some confusion between 2.14 (a) and 2.1
(c). The intent of the wording in 2.1 (c) was to indicate that
the applicant (APA) was ultimately responsible for seeing that the
mitigation plan is executed as agreed upon. The purpose of 2.14
(c) was not to indicate that any organization other than the
applicant would have ultimate responsibility, but to indicate that
an agreement would have to be reached as to exactly who (ADF&G,
USF&WS, TES, etc.) would actually execute the plan. A rewording,
or further explanation is needed to prevent a misunderstanding
between these two items.
{b) Realizing that a mitigation monitoring team will be
necessary to insure the proper and successful execution of
the mitigation plan, part of the plan will detail the
structure and responsibilities of such a monitoring body.
Comment
USF&WS:
The mitigation monitoring team should include representatives of
the applicant, FERC, and the state and federal agencies with
designated responsibility for fish and wildlife resources. The
financing, composition, and plan of study should be agreed to by
the prospective participants during the formulation of the
mitigation plan as a component of the mitigation plan to be
submitted to FERC for incorporation into the license.
2.15 -Modification of the Mitigation Plan
(a) As part of the mitigation plan a monitoring program will be
established, the purpose of which will be to monitor
wildlife populations during the construction and operation
of the project in order to determine the effectiveness of
the plan as well as to identify problems that were not
anticipated during the initial preparation of the plan.
(
(
-----·--------....... ---~~
Comment
USF&WS:
See comments above (2.14.b).
Gipson:
This section, 2.15 (a) is good.
(b) The mitigation plan will be sufficiently flexible so that if
adequate data secured during the monitoring of wildlife
populations indicate that the mitigation effort should be
modified, the mitigation plan can be adjusted accordingly;
this may involve an increased effort in some areas where the
original plan has proven ineffective, as well as a reduction in
some cases where impacts failed to materialize as predicted.
Comment
USF&WS:
Any modification to .the mitigation plan should be coordinated with, and
agreeable to, the state and federal agencies with designated
responsibility for fish and wildlife resources.
General Comments
McKendrick:
Bill Collins and I both received and read the Preliminary Outline.
Generally, it appears acceptable and comprehensive.
Wozniak:
We have no comments relative to the version of the Mitigation Policy
outline transmitted to us by Ed Reed's memo of May 8, 1981. (Note:
The APA did review an earlier version and provided suggestions and
comments that were incorporated into this review version).
Gipson:
This is a well written outline. You may want a section treating use of
4-wheel drive vehicles and snow machines.
Wlli
-
..,;
-
•
...
...
....
-..
--
.,.;
..
-
Jill
,.;
-
....,
..
•
-
-
-
-
-
-
-
-
\o-
-
USF&WS:
We appreciate the opportunity to review the preliminary outline
"Wildlife Mitigation: A Statement of Policy". We have done so in
light of the Fish and Wildlife Service•s Mitigation Policy (copy
attached) and have provided comments which are consistent with that
policy.
\,
(
(_
:rerrestrial ~nvironmental
RECE1VED JUt 2 7 i90'\ ...
-.-·Specialists, inc. ~.C. I BOX 318 PHOENIX. N.Y. 13131 (3151591•7121
-
-
-
MEMO -
TO: Members of the Susitria Wildlife Mitigation Task Force -FROM: Edward T. Reed, Task Force Coordinator
DATE: July 24, 1981; 218.730 ...
RE: Meeting notes -
Enclosed please find a copy of the notes of the June 29, 1981 meeting of
the wildlife mitigation task force. I have compiled these notes based on
my interpretation of the comments made during the meeting. If you feel
that I missed any major items or misunderstood certain statements please
...
let me know and I will prepare a revised version of the notes. I am now
moving forward with the preparation of a draft policy statement anr.~-sK_A_P_o_wE-R~
development of a decision making methodology. You will be receivi g AUTHOHITY
copies of these as they are completed. SUSITNA .
·,.;
'\'":;
;,.
,.. .
' <
,-. . ~ ·..-' ..
• !
(, (.· ---
Fll~-~0 ,_.
SEQUE;'\JC~ ·;J:-i-
' I . . I I
Z ~ tn I ..J l
0 I 11:: 0: i <!: ;::12 f-1~!-~ .~ 6 ~ I
-, ""O'CWj:=-----1
.. ~-j--i-
,-J! c A :; i' ,. II li:lJo-::;; ~; .
,.¥ .... ~t~~ ~' l ~:·~-~~ lf
-· ----· -j _l
E:l.l' I I .... =:_j s ;. ~-~ -'~-~-~:'·~: =-1 ' M ~'/I . -. r=-~--'--1 -'~!_/'
-[./A'Y'". Jfra · _:::t . .., <
-!-~+/' ·1,1-( I
~:J-;--,' --f-
-
-
r
SUSITNA WILDLIFE MITIGATION TASK FORCE
NOTES OF MEETING
June 29, 1981
Anchorage, Alaska
Compiled by: Edward T. Reed
Wildlife Ecology Group Leader
Terrestrial Environmental
Specialists, Inc.
The meeting was commenced at 9:00 a.m. A list of participants is
attached.
Mr. Reed gave a brief introduction and description of ·..mat had taken
place since the last meeting. He then asked if the participants would
like to make any general comments concerning the policy outline prior to
beginning a detailed discussion of the items contained within the
outline.
Mr. Wozniak requested that the purpose of the meeting be to move towards
a finalized statement as the next product.
~
Mr. Trent stated that although the policy addressed federal regulations, ~-~ '~~-~
there are state regulations concerning mitigation in draft form, and the
mitigation effort should stand prepared to include the intent and
approach presented in those state regulations. He also indicated that
the state regulations would use the five basic forms of mitigation as
defined by NEPA, but will go further in stressing the priority of the
forms. He indicated that the new regulations would be incorporated
under Title 16 law. Mr. Trent also suggested that a matrix type
approach be developed to be used in reviewing the various forms of
mitigation that might be used on the Susitna Project.
.
-l,
-". ;; ...
.)
. ,. 'f ,...._..,.,
~-
-2-
Mr. Trent said that for the purpose of developing mitigation policy it
would be advisable to involve the personnel responsible for the
fisheries mitigation effort. Mr. Schneider agreed that the policy
statements for both fish and wildlife should be basically the same. Mr.
Wozniak also indicated that this would be preferable. Mr. Wozniak then
requested that Mr. Reed take the appropriate steps to obtain the
involvement of the fisheries group. Mr. Reed agreed to contact the
appropriate fisheries personnel and request that they accelerate the
~
establishment of a fisheries mitigation task force and be provided with
information pertaining to the policy statement currently being prepared
by the wildlife task force.
A discussion took place concerning the level of mitigation planning that
. .
would be available for inclusion with the FERC license application
versus what will have to follow during Phase II. Mr. Wozniak warned
that Phase II should not serve as a convenient excuse for not having
critical portions of the application prepared for the projected
submittal date. Mr. Carson indicated that a commitment to the process
that would be used throughout the mitigation effort should be an
important item for the application. Since the discussion indicated that
·it a minimum~ it will be possible to have prepared a policy statement,
Jn approach to mitigation, and an outline of the olan~ Mr. Reed asked
representatives of the U.S. Fish and Wildlife Service if that level of
~ffort would satisfy their review needs as stipulated under the Fish and
Wildlife Coordination Act. Mr. Stackhouse replied that in the absence
of a complete, detailed mitigation plan~ they (USF&WS) would not be able
to make a final recommendation.
Mr. Schneider ~uggested that the next step should be the development of
a process, or methodology, to be used in making mitigation decisions.
This suggestion was received favorably by the other participants.
In reviewing the meeting to this point, Mr. Reed and Mr. Wozniak agreed
that the next steps should be to expand the outline to a draft policy
statement, prepare a decision making methodology, and develop an outline
of the plan.
...
...
-
...
IIIIi
-
...
-
...
...
-
-
-
-
-
-
-
-
...
·-
--
-
-
.....
-
i
"~--
-3-
At this point it was agreed to review the policy outline, item by itemt
commenting on the information and determining which items are
appropriate for a policy statement and which items might be more
suitable for inclusion in other sectio~~ The following notes are
organized by items co.rrespondinQ'tO".the outline.
'-......_
L1 -Mr. Trent indicated that there is a need to study the resources
and for the APA to commit to mitigation. He suggested substituting ..
"mitigate" for "reduce or avoid."
1.2 -Mr. Trent reiterated the need to take into consideration state
·policies and regulations. Mr. Carson suggested consideration of the DNR
Instream Flow Bill and the Coastal Zone Management Group.
1.3 -Mr. Trent suggested that the remaining items discuss mitigation
collectively rather than identifying only certain forms of mitigation.
2.1
(a) -Mr. Trent said that a compromise position is needed somewhere
between the phrases "agreeable to all agencies" and "feasible and
reasonable." Mr. Carson suqaested removinQ the phrase "feasible and -~ --. --· -
reasonable." Mr. Trent suggested using a phrase such ast "to strive to
_ mitigate the negative impacts." Mr. Schneider mentioned that rea 1 ity
should be kept in mind when defining the intent. ·
(b) -Mr. Wozniak indicated that there was no problem with this item but
felt that it should be removed from the policy statement and
incorporated at a diff~rent point in the mitigation plan. Mr. Carson
agreed.
(c) -Mr. Wozniak indicated that this item would be part of the license
and indicated that an associated goal would be to reach an agreement
between the resource agencies and the applicant.
'~
, ,._,
·-
A-
-·~
~-
-4-
2.2 -Mr. Carson discussed the roles of the APA and the resource
agencies as they pertain to public input. The possibility of agency
personnel being available at public workshops to present the position of
their respective agencies was discussed. Mr. Wozniak liked the idea of
agency personnel being available during public meetings.
2.3
(a) -Mr. Carson reiterated a previously expressed concern about the
wording of this· item. Mr. Wozniak remarked that the agencies and the
,.
APA are polarized in regard to this item. Following discussion it was
agreed that what is needed is a rewording that will provide the agencies
with stronger assurances~ while at the same time not totally committing
the APA.
(b) -It was agreed that this item is too specific for a policy
statement and might be more appropriately incorporated into a
"methodology .. section.
2.4 -Mr. Trent suggested that the forms of mitigation be combined under
a more general category. It was agreed that this section should be
removed from the policy statement and placed elsewhere.
2.5 -Mr. Stackhouse expressed interest in how the coverage would be
defined. It was agreed that this section may also be more appropriately
covered in a subsequent portion of the mitigation plan.
2.6 thru 2.13 -It was agreed that these sections would also be more
appropriately addressed in other portions of the mitigation plan.
2.14-Mr. Wozniak indicated that the APA is in agreement with this item
and has no problem with the wording. Mr. Carson felt that 2.14(b)
should be reworded to include the ~rd "funding .. and suggested the
following wording," ... part of the plan will detail the structure,
funding, and responsibilities •.• " Mr. Wozniak felt that this may be a
problem at this time and indicated that funding arrangements are an
itemthat would have to be negotiated at a later date. Mr. Wozniak also
felt that is was a good idea for the agencies to provide a commitment to
cooperate in this effort.
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
/
!
,~
·-
. ~ ----. ~---,. ~ .........
-5-
2.15 -Mr. Wozniak stated that the APA is in agreement with this item
and has no problem with the wording.
Mr. Carson expressed the opinion that the mitigation effort was going
well and he was pleased with the approach being taken so far·.
The meeting was adjourned at approximately 11:30 a.m.
PARTICIPANT
Edward Reed
leonard Carin
Gary Stackhouse
David Wozniak
Brina Kessel
Thomas Trent
Joseph McMullen
Karl Schneider
Ph i1 i p Gipson
Alan Carson
Robert Krogseng
Jay McKendrick
SUSITNA WILDLIFE MITIGATION TASK FORCE
MEETING OF JUNE 29~ 1981
ANCHORAGE~ ALASKA
LIST OF PARTICIPANTS
REPRESENTING
Terrestrial Environmental Specialists~ Inc.
United States Fish and Wildlife Service
United States Fish and Wildlife Service
Alaska Power Authority
TES/University·of Alaska
Alask\a Department of Fish and Game
Terrestrial Environmental Specialists, Inc.
Alaska Department of Fish and Game
TES/University of Alaska
Alaska Department of Natural Resources
Terrestrial Environmental Specialists~ Inc.
TES/University of Alaska
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
....
-
-
-
-
-
-
-
-
-
-
-
Ms. Jud1 Schwan
Environmental Evaluation Sranch
January 7, 1982
P5700. 11.91
T.1396
u.s. Env1ron~ental PRotection Agency
Region X
lZOO Sixth Avenue
Seattle, Washington 98101
Dear Ms. Schwarz:
Enclosed for your revi&~tt:
Sus1tna Hydroelectric Project
Fish and W1ldl1fe M1t1gat1on
Review Group >~et1ng
1) Susitna Hydrc£:1ectric Project F1sh and ~~i1dl1fe nit1ga-t1on Pelky.
2) D1t1ft Analysis of !~1idl1fe tiitigat1on Options.
3) Draft Annlys1s of Fisheries r~1t1gat1cn Options.
These documents will be disr.uss~d at the Fish and ~1ld11fe M1tioat1on
Review Group ~eet1ng to t~ t•::::d ::t ~:00 a.n. (not~ chan~e of tiY..~ freD
letter of December lS, lS~l) c:·, .:'::nu~ry ZO, 1982 at the office of t:-,c
Alaska Power Authority. 3.3·~ ~:c::;t. Eth Avenue, Anchorage. I hope ycu
will be able to attend th! neetin~.
Sincerely your!,
Kevin R. Young
Susitna Environmental Ccord1n~tor
Mf-~G/jmh
Enclosures
---------------... .,....... ..... ..-:.~. :Z:S!!&!!UL. :::::Z:._ .. S -~ .,.,..,... ,-.__~-ad
t!r. Gary Stackhouse u.s. Fish and ~11dlife Service
lOll East Tudor Road
Anchorage, Alaska 99502
Dear Mr. Stackhouse:
Enclosed for your review:
-~
January 7. 1982
P5700.11. 71
T.1394
Susftna Hydroelectric Project
Fish and ~1ldlife Mitigation
Review Group Meeting
1) Susitna Hydroelectric Project Fish and Wildlife t·~1t1gation Policy.
2) Draft Analysis of l!ildlife f11tigation Options.
3) Draft Analysis of Fisheries f·\itigation Options.
These docurr.ents \'till be discussed at the Fish and rfildlffe mtfgatfon Review
Group f·~ect1ng to be held at S:CO a.m. (note chan']e of tim~ from ictter
of Decen:~ct~ 1ft 1981) on January 28. 1~82 at the office of the P.ia~:-.:a
Poi'ier Author1 ty, 334 t!est 5th Avenue, Anchorage. I hope you will be
able to attend the w~etfng.
Sincerely yours,
Kevin R. Young
Susitna Environmental Coordinator
Mf-!G/jmh
Enclosures
-
-
-..
..
....,
...
..
..
...
-
...
--
...
...
..
...
...
--··---·-__:_~ -~~---------· ~'L--=---_-_"_..-:~mr-~-.--~-...:::.=s:::=-~ ---·* ss -------~,----------------
-
-
-
-
-
-
-
-
-
-
-
-
_l
~r. ~1chael Scott
District F1sh~r1es Biologist
U.S. 3ureau of land }~nagenent
4700 East 72nd Street
Anchor~~et Alaska 99507
Dear Mr. Scott:
Enclosed for your review:
J~nuary 7. 1982
P5700.11.75
T. 1393
SusitnA Hydroelectric Project
Fish and Wildlife M1t1'lat1on
Review Grou~ Meetin~ -
1) Susitna H.:tr:!roelectric Proj~ct Fish and ~!11dl H"c t~it1r:5:1on Po1 icy.
2) Or~ft Aiialysis of H1ldl1fc n1t10ation 0pt1on~.
3} Draft Analysis of Fisheries Hit1qa.t1on Ortions.
These docurr.ents w111 b~ d1SCI!!:$1;;G et the Fish and Wildlife ~~1":1~"<"ti,n Revic'~ ""rou~'~ Pant1" nn to ~-..,. l-.ol .j "'t \'": · r•r• " r. fnot" C'-l"r.ae Of t1r'"' ~ .. ,..,..., .. , .-, .... .._,.,.,.. \_!
0
• • ,·__. • .,. • _. L;"'"" lie_. • (.I. _ • -~ ,.J -' • , • \ -:1 _. 1 •· . t_ , I U. i -. , (
of Dccec-.ber Hl, l?Bl) on January 20, 19S2 at the effie~ of tb~ r-1"~;:1
Pm·:er Authority, 334 \-:est 5th Avenue, Anchorage. I hope you will be
able to attend tht: r;'!Cetin~J.
Sincerely yourst
Kevin R. Younq
Sus1tna Env1ronr.cntal Ccordin~tor
~~G/jmh
Enclosures
-=-------""""'~·~--=--"-~·-----~-~-.,.... . '"':;-·' -~ ............... ..,.....,_..,..~~~~----------------·
Mr. Bradley ~ith
January 7, 19g~
P5700.1l.91
T.1392
Environmental Assess~nt Division
National ~arine Fisheries Service
Federal Building & U.S. Court Bouse
701 "en Street, Box 43
Anchorage, Alaska 99513
Dear Mr. Smith:
Enclosed for your rev1ew:
Susitna ~:ydroe1ectr1c Project
Fish and Wildlife Mitigation
r.cview Grou£_ f.!eetinq
1) Susitna lly~roclectr1c Project Fish and F1ld11fc r~it1~at1cn Policy.
Z) Draft f\nalys1s of ~:ildlife t:itfgl!t1on Options.
3) Draft Analysis of Fisheries t·4it1r,ation Options.
These docu~ent~ will be discus~cd ?.t the Fi~&: and \.'11c11fc i,~1tir,=<1on ~:.:vie~·!
(;roup r.1eetfng to be h~ld at CJ:OC a.:::. (~ote chan')e of ti::':e fro:"'. k:t.tti'"
of Dece!"l'ber lfl, 1981) on Jar.uzry 20! 1982 nt the office of the ~laskJ
Power Authority, 334 Hest 5th Avenue, Anchorage. I hop~ you w111 be
able to attend the meeting.
Sincerely yours,
Kevin R. Youn11
Sus1tna Environm.::ntal Coordinator
~iG/jmh
Eoclosures
...
..
-
...
.,;
...
--
..I
...
..
-
_.
-
-
-
-..
-
_ :z::::z::-"'1"51&::: w "'::.· ·:: n , ·: ... -,. ~~--.~ · ---~· ---z-<·-·" ·---·-·-:-:==--zsw: 'SZt"F: _........_ ___ ~
-
-
-
-
-
-
-
-
...-;
-
-
-
·-
-
-
-
Mr. A 1 Carson
Division of Research & Development
Department of Natural Resources
323 East Fourth Avenue
Anchorage. Alaska 99501
Dear Mr. Carson:
Enclosed for your review:
January 7, 1982
P5700.11.74
T.1391
Susitna Hydroelectric Project
Fish and Wildlife Mitigation
Review Group Meeting
1) Sus1tna Hydroelectric Project Fish and ~ildlife Mitigation Policy.
2) Draft Analysis of ~·Ii1d11fe H1t1gat1on Options.
3) Draft Analysis of Fisheries Mitigation Options.
These docur:1ents will be discussc;d at the Fish and Wildlife f~itigation Review
Group Heeting to be held at 9:CJ a.~. (note change of time from let~cr
of December 18. 1931) on January 2C, l~~Z at the offfce of the Alaska
Power Authority, 334 V:est 5th Avenue, Anchorage. I hope you will be
able to attend the meeting.
Sincerely yours.
l~:vi n R. Young
Susitna Environmental Coordinator
MHG/jmh
Enclosures
.. :~:,~~\:. c
i
Ms Judi Schwarz
Environmental Evaluation Branch
U.S. Environmental Protection Agency
Region X
1200 Sixth Avenue
Seattle, Washingtoh 98101 ·
Dear Ms. Schwarz:
February 26, 1982
P5700.11.92
T.l544
Susitna Hydroelectric Project
Fish and Wildlife Mitigation
' '·
As discussed through Vern Smith of our Anchorage office, meetings to re-
view fish and wildlife mitigation efforts are scheduled for March 11 and
12, 1982 in the offices of Acres American, 1577 C Street, Suite 305,
Anchorage, Alaska.
As these meetings are expected to be in the form of technical workshops,
a complete day on each of the topics of fish and wildlife is considered
necessary. Proposed agendas are enclosed. I will also forward, within
the week, updated information packets addressing fish and wildlife im-
pact issues and mitigation options.
As fisheries issues are being discussed on a separate day from wildlife
issues, please feel free to have different technical personnel attend
each of the meetings if you consider it appropriate.
As we consider these meetings to be an important component in improving
the coordination between your agency and our fish and wildlife mitigation
core groups, your attendance is encouraged. ·
If you have any questions relating to these meetings please contact my-
self or Vern Smith (907-276-4888).
'Sincerely,
Kevin Young
Environmental Coordinator
KRY:dlp
Enclosures
"""
..
...
...,
..
....
...
-
t!"
...
---
..I
-
...
--
-
-
-
-· -"
-
-
-
.. _
-
--
-
--
-
-
,_
qeqr~ Huli!O
. ... . • ..C:'-':\-~-
Mr. Al Carson
Division of Research & Development
Department of Natural Resources
323 East Fourth Avenue
Anchorage, Alaska 99501
Dear Mr. Carson:
-
February 26, 1982
P5700.11.74
T. 1539
Susitna Hydroelectric Project
Fish and Wildlife Mitigation
As discussed through Vern Smith of our Anchorage office, -meetings to re-
view fish and wildlife mitigation efforts are scheduled for March 11 and
12, 1982 in the offices of Acres American, 1577 C Street, Suite 305,
Anchorage, Alaska.
As these meetings are expected to be in the form of technical workshops,
a complete day on each of the topics of fish and wildlife is considered
necessary. Proposed agendas are enclosed. I will also forward, within
the week, updated information packets addressing fish and wildlife im-
pact issues and mitigation options.
As fisheries issues are being discussed on a separate day from wildlife
issues, please feel free to have different technical personnel attend
each of the meetings if you consider it appropriate.
As we consider these meetings to be an important component in improving
the coordination between your agency and our fish and wildlife mitigation
core groups, your attendance is encouraged.
If you have any questions relating to these meetings please contact my-
self or Vern Smith (907-276-4888).
Sincerely,
Kevin Young
Erivironmental Coordinator
KRY:dlp
Enclosures
ACRES AMERICAN INCORPORATED
C-:--~-~!,,~~ Er.g·~.ee·s
it...: :..::::.-:.:r:; B~,;.;, 2 ... 1'::.~g :.~.1·n :::t C:·ur!
::_-":;·~. ~-.-~·:; Yc·~-~..:?~-2
--=~~~--=-'"''= r~c-:::~--:-2: 7~'.:: .... 9·-r:~~: MCRES CU~
(j· .. ~·· o•: . .:.&s. Cc .... -.:::a r.::J ; .:·:.:-... rgr. P~ ?aLc:1gh ~-~;: '.'.'as~··ng:o:: DC
Mr. Michael Scott
District Fisheries Ciologist
U.S. Bureau of Land Management
4700 East 72nd Street
Anchorage, Alaska 99507
Dear Mr. Scott:
February 26, 1982
P5700. 11.75
T. 1541
Susitna Hydroelectric Project
Fish and Wildlife Mitigation
As discussed through Vern Smith of our Anchorage office, meetings to re-
view fish and wildlife mitigation efforts are scheduled for March 11 and
12, 1982 in the offices of Acres American, 1577 C Street, Suite 305,
Anchorage, Alaska.
As these meetings are expected to be in the form of technical workshops,
a complete day on each of the topics of fish and wildlife is considered
necessary. Proposed agendas are enclosed. I will also forward, within
the week, updated information packets addressing fish and wildlife im-
pact issues and mitigation options.
As fisheries issues are being discussed?on ~ separate day from wildlife
issues, please feel free to have different technical personnel attend
each of the meetings if you consider it appropriate.
As we consider these meetings to be an important component in improving
the coordination between your agency and our fish and wildlife mitigation
core groups, your attendance is encouraged.
If yo~ have any questions relating to these meetings please contact my-
self or Vern Smith (907-276-4888).
Sincerely,
Kevin Young
Environmental Coordinator
KRY:dlp
Enclosures
--
-
~
..,
-
....
..tti
11!111
-
-
..,
...
-'
-
--
._;
-
-
~
-
-
-
-
-
-
-
-
Mr. Carl Yanagawa
February 26, 1982
P5700. 11. 70
T. 1543
Regional Supervisor for Habitat Division
Alaska Department of Fish & Game
333 Raspberry Road
Anchorage, Alaska 99502
Dear Mr. Yanagawa: Susitna Hydroelectric Project
Fish and Wildlife-Mitigation
As discussed through Vern Smith of our Anchorage office, meetings to re-
view fish and wildlife mitigation efforts are scheduled for March 11 and
12~ 1982 in the offices of Acres American, 1577 C Street, Suite 305,
Anchorage, Alaska.
As these meetings are expected to be in the form of technical workshops,
a complete day on each of the topics of fish and wildlife is considered
necessary. Proposed agendas are enclosed. I will also forward, within
the week, updated information packets addressing fish and wildlife im-
pact issues and mitigation options.
As fisheries issues are being discussed on a separate day from wildlife
issues, please feel free to have different technical personnel attend
each of the meetings if you consider it appropriate.
As we consider these meetings to be an important component in improving
the coordination between your agency and our fish and wildlife mitigation
core groups, your attendance is encouraged.
If you have any questions relating to these meetings please contact my-
self or Vern Smith (907-276-4888).
Sincerely,
Kevin Young
Environmental Coordinator
KRY:dlp
Enclosures
Mr. Gary Stackhouse
U.S. Fish & Wildlife Service
lOll East Tudor Road
Anchorage, Alaska 99502
Dear Mr. Stackhouse:
February 26, 1982
P5700.11.71
T. 1542
Susitna Hydroelectric Project
Fish and Wildlife Mitigation
As discussed through Vern Smith of our Anchorage office, meetings to re-
view fish and wildlife mitigation efforts are scheduled for March 11 and
12, 1982 in the offices of Acres American, 1577 C Street, Suite 305,
Anchorage, Alaska.
As these meetings are expected to be in the form of technical workshops,
a complete day on each of the topics of fish and wildlife is considered
necessary. Proposed agendas are enclosed. I will also forward, within
the week, updated information packets addressing fish and wildlife im-
pact issues and mitigation options.
As fisheries issues are being discussed on a separate day from wildlife
issues, please feel free to have different technical personnel attend
each of the meetings if you consider it appropriate.
·As we consider these meetings to be an important component in improving
the coordination between your agency and our fish and wildlife mitigation
core groups, your attendance is encouraged.
If you have any questions relating to these meetings please contact my-
self or Vern Smith (907-276-4888). •
Sincerely,
Kevin Young
Environmental Coordinator
KRY:dlp
Enclosures
...
-
...
'!IIIIi
....
...
-
..,;
...
--
-
wJ
...
-
.,;
-
-
-
-
-
... :
-
-
-
,_
.....
Mr. Bradley Smith
Environmental Assessment Division
National Marine Fisheries Service
Federal Building & U.S. Court House
701 C Street, Box 43
Anchorage, Alaska 99513
Dear Mr. Smith:
February 26, 1982
. P5700.11.91
T. 1540
Susitna Hydroelectric Project
Fish and Wildlife Mitigation
As discussed through Vern Smith of our Anchorage office, meetings to re-
view fish and wildlife mitigation efforts are scheduled for March 11 and
12, 1982 in the offices of Acres American, 1577 C Street, Suite 305,
Anchorage, Alaska.
As these meetings are expected to be in the form of technical workshops,
a complete day on each of the topics of fish and wildlife is considered
necessary. Proposed agendas are enclosed. I will also forward, within
the week, updated information packets addressing fish and wildlife im-
pact issues and mitigation options.
As fisheries issues are being discussed on a separate day from wildlife
issues, please feel free to have different technical personnel attend
each of the meetings if you consider it appropriate.
As we consider these meetings to be an important component in improving
the coordination between your agency and our fish and wildlife mitigation
core groups, your attendance is encouraged.
If you have any questions relating to these meetings please contact my-
self or Vern Smith (907-276~4888).
Sincerely,
Kevin Young
Environmental Coordinator
KRY:dlp
Enclosures
l I
i-1r. Al Car5on
~arch ?. , 1 ~82
P5700. 11.74
T .15C1
1.1i v·i siun of ?t~SI~::rd: .~ OevelO!"\ff!ent
:;qn :--!7'le;,t of :{a tura l Resources
Pouch 7-0CS
Ar.choraqe, Alaska 9?501
Dear Mr. Carson: Sus1tna Hvdroelectr1c Project
Fish and ~11dl1fe Mitigation
Rev1 ~\'1 Group t1.eet1 ng
rnclosed for your 1nfo~t1on a~:
1. The Susit~a Hydroelectric Project Fish
and Wildlife M1t1gat1on Policy {P.evised)
2. Wildlife H1t1qat1on Cpt1ons {Revised}
3. Fisheries ~ti~~t1on Options (~evised)
Please rev1c\·J these c!ocum~nts pr1~r to the meeting of the
F1sh and N1ld11fe ~·~1til':~t1C!l Reviet~ Grou~·on ~4arch lJ, 1932
at 8:30aM i~ th~ Jf~1ccs of Acres American, 1577 c Street~
.A.nchoratje. I,Je will discuss the Policy and Wildlife ~•1tiga
t1on Options on the 10th and the Fisheries mtigat1or. Op-
tic-us on tlle 11th, as referred to in t!1e invitation l~tter
of February 26, 1932.
Thank yolJ very much.
KRY:dlp
Enclosures
Sincerely~
Kevin Y"auntJ
Sus1tna Environmental
Coordinator
..
-
"""
~
...;
.J
IIIIi
...
~
..
1 ..
..
...
..
-
...
...,
Ifill
-
.....
-
-
......
.._
-
-
-
.....
•j
Mr. Sradley Smith
,...arch 2. 1982
P5700. 11 • 91
' T.1549
Environmental Assessment D1v1sfon
ltational fA.arine Fisheries Service
Federal Building & U.S. Court House
701 c Street. Box 43
Anchorage. Alaska 99513
Dear Mr. Smith: Susftna Hydroelectric Project
Fish and Wildlife Mitfg~tion
Review Group Meeting
Enclosed for your information are:
1. The Susftna Hydroelectric Project Fish
and Wildlife ~11t1gatfon Policy {Revised)
2. lt!flc!lffe ~11ifgation Options (Revised)
3. Fisheries Mftfgatfon Options (Revised)
Please review these documents prior to the meeting of the
Fish and Wi1dlifc ~litit)ation Review Group on ~Jarch 10, 1922
at e: 30 am 1 n the offices of Acres !l.mericnn. 1 577 C ~treet.
Anchorage. ~fe Hill discuss the Policy and Wildlife t~itiaa
tion Options en the lOth and the Fisheries !~t1qaticn Op-
tions on the 11th, as referred to fn th(' 1nv1tation 1ettP.r
of Fet~Jary 25, 1~32.
Thank you very r-:uc~.
KRY:dlp
Enclosures
Sincerely,
K~v1n Ycun']
Susitna Envirn~ner.ta1
Coordinator
,..._
:.tr. ~11chae1 Scott
01strict Fisheries Biologist
U.S. Bureau of Land Management
4700 East 72nd Street
Anchorage, Ala!ka 99507
Dear Mr. Scott:
March 2, 1932
P5700.11.75
T .1550
Susitna Hydroelectric Project
F1sh and Wildlife Mitigation
Rev1~ Group Meet1n~
Enclosed for your information are:
1. The Sus1tna Hydroelectric Pro.ject Fish
and Wildlife M1t1gat1on Policy {Revised)
2. 1~!1ldlife ~1t1qat1on Options (~ev1sed)
3. Fisheries M1t1gat1on Options {Revised}
Please rr.v1e~ these documents prior to the ~etinq of the
Fish and Wildlife ''itigation Revie\'1 Group on March 10, 1982
at 8:30 am in the offices of Acres AMerican, 1577 C Street,
AnchoraQe. We will di~cuss the Policy and Wildlife t~1tf~a
tion Options on the lOt~ and the Fisheri~s P.itiqntion o~
t1ons on the llth, as referred to in the invitation letter
of February 26, 19BZ.
Thank you vP.ry MUch.
KP.Y: dl p
Enclosures
Sincerely,
~~vin Your:~
S:; $ i t11J E :~vi r')!v·::e~ ta 1
Coorcinator
. ,~
...
...
...
..
-
. .,.i
....
..
--..
.,.,
..,
--
...
-
..,
-
~
-
-
-
......
-
~
-
""
.,_
......
-
Mr. C!rl Yanagawa
March 2, 1982
P5700. 11. 70
T.1552
Regional Supervisor for Habitat D1v1s1on
Alaska Deoartment of Ffsh ~ Game
133 Raspberry Road
Anchorage. Alaska 99502
Dear Mr. Yanagawa: Sus1tna Hydroelectric Project
Fish and W11dlffe Mitigation
Review Group ~~eting
Enc1osec for your 1nfo~tion ~re:
1. The Sus1tna Hydroelectric Project Fish
and Wildlife Mitigation Po11cy (Revised)
2. Wildlife r-11t1q~t1cn 0!')t1ons (Revised}
3. Fisheries Mitigation Options (Revised)
Please revie\1 these.' docul"1er.ts prior to the meetir.:1 of the
Fish and liild11fto i~1tiqnt1on Rev1~<~ Ciroup on ~~rch H\ P::l2
at 3: 31) ai:': in the offi c~s o~ Acr:!s Ji.~ri can. 1577 C Street.
Anchorage. We \·rill discus~ the l'o11cy and Hi1dl1fs ~it1(71'!
t1on Options on th~ 10th !~d t~~ Fisheri~s Mitigation n~
ticns on the llth, as rcferr2n to in th2 1nv1tation l~tt~r
of February 25, 19B2.
Th~nk you vc·ry rr:Jc:h.
KRY:dlp
Enclosures
Sincerely.
Kevin Yo~nl~"~
Sus1tna En vi ronr.en1:a i
Coordi r.at.Jr
r
ail a.raa an Iii ----~-==:---------------------------------------
Ms. Judi Schwarz
March 2,-1982
P5700.11.92
T.15~3
Environmental Evaluation Branch
~~'li1 Stop 443 u.s. Environmental Protection Agency
Re!]iOn X
1200 Sixth Avenue
Seattle, Washington 98101
Dear Ms. Schwarz: Susitna Hydroelectric Project
Fish and Wildlife Mitigation
Review GrouE ~~etinq
Enclosed for your 1nfcrmation arc:
1. The Susitna Hydroelectric Project Fish
and Wildlife Mitigation Policy (Revised)
2. H1ldlife Mitigat1cm Options {~ev1sed)
3. Fisheries Hitigntion Ortior.s (Pev1s~d)
Pl~ase revi~·1 the$e dc-c•Jr.tents prior to the me4?t1nq of th;:
Fish and ~H1d11fe M1tirJ~t1on Pevie~;J Grouo on H1r~h D. 1~:j2
at 3:30 am in t~e office! of . .o.cres ~~.,~rice.n, 1577 C Str."'~t,
Anchorage. He ~ill discuss the Policy and Vil~life ~1ti~~
t1on Options on the lOth and the Fisheries M1tiq~tion On-
tions on the 11th, as referred to it~ trr·.= ir.vitat i.:n 1 ett~r
of February 25. l?B2.
Thank you very much.
K~Y=dlp
Enclosures
Sincerely,
Kevin Y0:.m.,
Susitn~ Enviro~~Pntal
Coordina-+:or
I 4
...
....
..
-..
-.I
...
-
-
~
-
~
-
.,;
•
""' -
.,
-
'
.......
....,_
-
-
-
-
-
-
.....
"' -
-
-
-
-
'·•
Mr. Gary Stackhouse
U.S. Fish & ~1fld11fe Service
1011 East Tudor Road
Anchorage, Alaska 99502
Dear Mr. Stackhouse:
~.arch 2. 19eZ
P5700. 11.71
T .1551
Sus1tna Hydroelectric Project
Fish and Wildlife Mitigation
Review Grou~ Meet1nq
Enclosed for your information are:
1. The Sus1tna Hydroelectric Project F1sh
and Wildlife Mitigation Policy (Revised)
2. Wildlife Mitigation Options {Revised)
3. Fisheries }litigation Options (Revised)
Please review these documents prior to the meetin~ of the
Fish and ~lildlife M1t1ryat1on Review Group on ~~rch 10, 1982
at 8:30 a~ in the offices of Acres Ar~erican~ 1577 C Street,
Anchorage. ~e ~ill discuss the Policv and Wildlife Miti~a
tion Oot1ons on the lOth and the Fisheries ~iti~ation Or-
tions on the 11th, as referred to in the invitation lette~
of February 26, 1g3~.
Thank you very much •
KRY:dlp
Enclosures
Sincerely.
Y.evin Y~ur;
Susitna Envi rt:'m-,c:rtal
CoordinJtor
I ~
SUSITNA HYDROELECTRIC PROJECT
FISH AND WILDLIFE MITIGATION REVIEW. GROUP MEETING
March 10, 1982
Held at the Offices of Alaska Power Authority, Anchorage
Attendees: See attached list.
The meeting followed the attached agenda. The revised Fish and Wildlife
Mitigation Policy was discussed. Agreement was reached on all areas where
further revisions were suggested. The policy will be modified and circulated
to the review group members by April 15, 1982.
Ed Reed and Karl Schneider presented the results of the wildlife baseline
studies and impacts prediction. Attendees were provided with the sections of
the Feasibility Report addressing these issues.
General mitigation options were discussed. HEP was not dismissed but
questioned as to its validity to big game species in Alaska. It was agreed
some kind of habitat evaluation, in addition to population studies would have
to be conducted. TES has developed a habitat analysis method (used on the
access road studies) and this may be modified and used. The question of
land set aside was also discussed but no decision reached.
Ed Reed suggested, for discussion purposes, the option of APA funding a
permanent research station in the Upper Susitna Basin. It was agreed this
was an option but should be considered only if other options (avoid, reduce,
etc.) fail, i.e. it would be used on out-of-kind compensation.
Studies for Phase II to quantify impacts and for mitigation planning were
reviewed with Attachment A forming the basis for discussion. The BLM burn
in the Alphabet Hills may not proceed dur to lack of burn plan being written
and possible requirement for an archaeological clearance. APA may contact
BLM to determine how a go decision could be reached.
•
•
...
-
--
"''t
...
-
..,
,..)
""' ..
...
--
--
-
------------------------------
--------------------------
------------------------
-
------------------------------------
-----------------------"§.77· ?':~on ?T??'di'FF;f?W (! ~-, ----
<) f _L. rv:·-,~ r> h/ -, 1'\J --:g C?f -----
s ;;:7_ ~---/-;;? _.--
----~-------------------~---,-f-J-r-cd;;;:t-v---------,_~---r.-rr-v-~xv ~(/ 1 --
_-!J_p_;;:;_l 0? -----pr-1"?-#'71/,/7/6/( ~)
~..J:i"sNi:i;)-33L -s~f?oS5fj-'n?r:rpNVJ..-----~a·T:JT3wvq-JrrltJkJ ___ -
--------------
5 /'f) ;i g ()
sc-")~~n
Cf CJ-t"\ J ~ · JnT.;-c~---~
·_"?sYio"'\->t""?·uJ s 7 -ks~cv-_
~'-\J ~ ...... ~~T ---
----------------.--(}J ') g -~o-:>5' o({~[lJ-------_
---s.;;~L .!:f?i?s:9o?;t __ ror-------
YAC?jj(?_d' ruocz ---
~ ~ 3V-_ -~~--os-"'i\J--Y\1 ______ -
-S-=:1\i\J fJ-Hl\ ws CS:\!252)
----------
------------------------------------------
~.r("/:Z-#1,/ f'F':~"-'-Y_iJ'-:1 J,./ -e:gfe-rjr__,_--------------
d I" ,. I CJ ""'"'I (\ a;i ? I/ pI I ""\ ,.. ... J, ~ ~l.J -
Issue No.
6
8
9
20
Wtldltfe Affected
Upper basin moose
Brown bear
Wolf
Upstream furbearers
ans bfg game except
Oall sheep.
r r ' f r {
ATTACHMENT A
Sus Hna liydroe lectric Project
Wildlife Mitigation
___ l!igh Priority Issues
Impact
Habitat loss
Spring foraging habitat
loss.
llabitat loss. Food
base reduction.
Increased human activity
from access road and
construction camps.
Mitigation Options
Compensation via habitat
management; burning,
crushing, logging. land
set aside.
Out-of-kind. land set
aside.
Maintain food base.
land set aside. Oo
nothing.
Construction period:
Prohibit public access,
prohibit worker off-site
activity, restrict
traffic.
Post-construction
period: Restrict
public access, prohibit
ATV traffic, monitor
wildlife populations.
Studies Under Consideration for 4/82 Through 6/83
To Quantify Impacts
Drowse availability,
productivity, and utili-
zation, winter census of
impoundment zone.
Spring census of impound-
ment zone. Census of
salmon feeding bears,
Oev t1 Canyon to
Talkeetna.
Territory mapping of
packs in immediate
project area.
For Mitigation Planning
Assessment of OlM expert-
menta 1 burn. ldenti fy
downstream and upstream
areas for habitat manage-
ment.
Issue No. Wildlife Affected
2 Pine marten.
3 Cliff-nesting raptors.
4 Bald eagle.
7 Black bear.
11 Caribou.
12 Oownstre~u beaver.
13 Downstream moose.
r {
Susitna llydroelectric Project
Wildlife Mitigation
Hedium Priority Issues
Impact t·11tlgatlon Options
llabita t 1 oss. Out-of-kind for other
furbearers. land set
aside.
Nesting habitat loss. Recreation planning,
clearing operation
scheduling, air traffic
restrictions, artificial
nest platforms.
Feeding habitat loss, Preservation of tall
nesting habitat loss. trees, artificial nest
platfonus, reservoir
stocking.
Habitat loss. Out-of-kind to moose,
out-of-kind to other
species, land set aside.
t11 gratory route Monitor movements,
Interference. protect new calving
grounds.
Reduction In slough Operation.
habitat.
Habitat alteration via llabitat manipulation.
change In plant
succession, reduction
in winter browse.
Studies U~der Consideration for 4L82 Through 6L83
To Quail! if1'Jilll!il<:t~ For Mitigation Planning
Population estimate.
Downstream survey.
Population estimate of
Impoundment zone;
census of salmon feeding
bears, Dev 11 Canyon to
Talkeetna.
Continued monitoring of
movements.
Downstream habitat
utilization surveys.
WInter surveys of down-Identify areas appropriate
stream populations. for habitat manipulation.
Wildlife Mitigation
Medium Priortty Issues {cont}
Issue No.
15
17
22
23
Wildlife Affected
Caribou.
Furbearers, birds, and
sma 11 man•na 1 s, big
game except Oall sheep.
Upper basin wildlife.
Big game, raptors,
swans.
·r
Impact
Watana clearing -
migration interference.
llabi tat loss due to
access roads, borrow
areas, construction
camps.
Unauthorized fires.
Air traffic disturbance.
Mitigation Options
Clearing schedule, uncut
travel lanes.
Camp design, restoration
and revegetation, ne~t
boxes.
Worker education, fire
fighting facilities.
Altitudnal restrictions,
seasonal restrictions.
Stud les Under Consideration for 4/82 Through 6/83
To Quantify Impacts For Mitigation Planning
ffiue No. Wildlife Affected
Mink and river otter.
5 forest and riverine
bird and sma 11 manuna 1 s.
10 Dall sheep.
14 Upstream big game.
16 Red fox, wolf, black
bear, brown bear.
18 Upstream big game
except Dall sheep.
19 Moose and caribou.
21 Red fox. and wolf.
r
Susitna Hydroelectrid Project
Wildlife Mitigation
Impact
llabitat loss.
llabitat loss.
Partial inundation
of mineral lick.
Disturbance from
clearing operations.
Illegal feeding and
improper garbaoe
disposal.
llabttat loss from
borrow areas.
Vehicle collision.
Rabies introduction,
feral dog packs.
Low Priority Issues
Mitigation Options
Out-of-kind, stocking
of reservoir.
land set aside.
Monitor use, replace
lick.
Schedule of clearing
operations.
Worker education, camp
design.
Restoration and re-
vegation.
Worker education, road
design (pullouts),
temporal driving
restrictions.
Prohibition of dogs,
regulation of dogs.
r
Studies Under Consideration for 4/82 Through 6/83
To Quantify Impacts for Mitigation Planning
3JN30NOdS3~~0J 3311IWWOJ 9NI~331S
E-8 XION3dd\t
-
-
-
-
-
-
-
... ~
j
-
-
-
-
-
-
-
-1-\LI-I~M t'Ui'ltK 1-\U I tiUKi I l ~
June 3, 1980
The Honorable lee McAnerney
Corrmissioner
Department of Community and
Regional Affairs
Pouch B
Juneau, Alaska 99811
Dear Commissioner McAnerney:
The Alaska Power Authority through its consultant, Acres American
Incorporated, is in the early stages of a 30-month feasibility study of the
proposed Sus1tna Hydroelectric Project. Because of the magnitude of this
study, effective interagency coordination will be best accomplished through
formation of a Sus1tna Hydroelectric Steering Committee. The function of
this committee would be to prov1de_coord1nated exchanges of information
between the Alaska Power Authority and interested resource management agencies.
Through this exchange, the concerns of all agencies involved would be identified
early and hopefully prevent unnecessary delays in the progress of the feasi-
bility study, application for the Federal Energy Regulatory Commission license
to construct, and Environmental Impact Statement review.
As proposed, the Steering Committee would be composed of representatives
of resource agencies with responsibi11t1es pertaining to the Susitna Hydro-
electric Feasibility Studies and/or the project's environmental consequences.
~·Je therefore invite your agency's participation.
· The committee would provide for interagency coordination through joint
rev1e~l of project related materials and development of more informed and
uniform positions representing all resource interests. tJe believe this will
provide a more efficient process of information exchange.
Proposed objectives for this committee are to:
1. Revimi and comment on study approaches throughout each phase of the
planning process;
2. Insure that the biological and related environmental studies, their
timing, and technical adequacy are planned, implemented, and conducted
to provide the quantitative and qualitative data necessary to:
(a) assess the potential impacts to fish and wildlife resources, and
(b) provide the basis for mitigation and compensation of resource
1osses which will result from the project;
-~-
{ "\
! J
l I
I \' I ., .·· ...
F
~~
-,.1f.~
-~~ -
··comnissioner ·Lee f~CAne~J.~
June 3, l98f\
Page Two
3. Provide a forum for continued project revis'il of all aspects of the
studies, for a timely exchange of information, and for reconmendat1on of
study redirection. should the accomplishment of spec1f1c objectives be
in jeopardy;
,·
4. · ~1on1to~ compliance of the studies with all state and federal laws~
regulationsn Executives Orders, and mandates as they apply to fish a~nd
wildlife resources; .and
5. Provide unified agency commer&ts from the corrrn1ttee to the Po~1er Auth!Grityo
Should your agency elect to .pG\rt1c1pate 1n the conmfttee, we recormnend
that your representative have a technical background enabling him to comnent
on the adequacy and approach of ongoing and future feasibility studies. and
be able to speak-knowledgeably on the policies and procedures of your agency
with respect to the review of tha Federal Energy Regulatory Cormrfssion 11cense
application for the project and the subsequent Environmental Statement (ES).
The first Susitna Hydroelectric Steering Committee_ meeting will be held
at the Alaska Power Authority, 333 West 4th Avenue~ Suite 31. Anchorage,
Alaska on June 12th at 9:00 AM. Attached is a sheet tolith a description of
the agenda for this first meeting. Your attendance 1s encouraged.
Attachment:
as noted
Sincerely,
EY.1e P. You1d
Executive Director
·-----::::::::-
;
-
-
~1r. Harry Hu 1 sing
District Chief
e
Department of the Interior
U. S. Geological Survey
ALASKA PO\o/ER AUTHORITY e
June 3, 1980
-Water Resources Division
218 "£11 Street
-
-
-
-
-
-
-
-
-
Anchorage, Alaska 99501
Dear Mr. Hulsing:
The Alaska Power Authority through its consultant, Acres American
Incorporated, is in the early stages of a 30-month feasibility study of the
proposed Sus1tna Hydroelectric Project. Because of the magnitude of this
study, effective interagency coordination will be best accomplished through
formation of a Susitna Hydroelectric Steering Committee. The function of
this committee would be to provide coordinated exchanges of information
between the Alaska Power Authority and interested resource management agencies.
Through this exchange, the concerns of all agencies involved would be identified
early and hopefully prevent unnecessary delays in the progress of the feasi-
bility study, application for the Federal Energy Regulatory Commission license
to construct, and Environmental Impact Statement review.
As proposed, the Steering Committee would be composed of representatives
of resource agencies with responsibilities pertaining to the Susftna Hydro-
electric Feasibility Studies and/or the project's environmental consequences.
We therefore invite your agency•s participation.
The committee would provide for interagency coordination through joint
reviev of project related materials and development of more informed and
uniform positions representing all resource interests. We believe this will
provide a more efficient process of information exchange.
Proposed objectives for this committee are to:
1. Review and comment on study approaches throughout each phase of the
planning process;
2. Insure that the biological and related environmental studies, their
timing, and technical adequacy are planned, implemented, and conducted
to provide the quantitative and qualitative data necessary to:
(a) assess the potential impacts to fish and wildlife resources, and
(b) provide the basis for mitigation and compensation of resource
losses which will result from the project;
/,,· /~
',,;::" ··-) / ,"
,_..., .· i ? /: / \ \ , .. I
\'"_) (~;' I
"-----../
.:1ft': fiarry lftilsing
June 3, 1980
Page Two
3. Provide a. forum for continued project review of ali aspects of the
studies. for a timely exchange of information, and for recommendation of
study redirection, should the accomplishment of specific objectives be
in jeor"lrdy;
4~ ·Monitor compliance of the studies with all state and federal 1aws,
regulations., Executives Orders, and mandates as they apply to fish and
wildlife resources; and ,
5. Provide unified agency conmtents from the corrm1ttee to the Power AuthOt'itY-
" .
Should your ag~ncy elect to participate in the comnittee, we recontnend
that. your representative have a technical background enabling him to conment
on the adequacy and a(Jproach of ongoing and future feasibility studies, and
be able .to speak knowledgeably on the policies and procedures of your agency
with respect to the revie\'1 of the Federal Energy Regu1atory Conm1ss1on license
application for the project and the subsequent Environmental Statew~nt (ES).
. The first Susftna Hydroe1ectr1c Steering Cotmlittee meeting w111 be he1d
at the Alaska Power Authority, 333 West 4th Avenue? 5u1te 31, Anchorage,
Alaska on June 12th at 9:00 Ar~. Attached is a sheet~ with a descfltption of
the agenda. for this first meeting. Your attendance 1s encouraged.
Attachment:
__ .. as noted _·
Sincerely,
Eric P .. You1d
Executive Director
-
-
-
-
-
-
-
~· ........
.)
.. ...... .)
-
-
-
-
-
-
-
-
41t ALASKA POWER AUTHORITY 4lf
Colonel Lee R. Nunn
U. S. Army Corps of Engineers
Alaska District
Post Office Box 7003
Anchorage, Alaska 99510
Dear Colonel Nunn:
June 3, 1980
The Alaska Power Authority through its consultant, Acres American
Incorporated, is in the early stages of a 30-month feasibility study of the
proposed Susitna Hydroelectric Project. Because of the magnitude of this
study, effective interagency coordination will be best accomplished through
forr~tion of a Susftna Hydroelectric Steering Committee. The function of
this committee would be to provide coordinated exchanges of info~~tfon
bet~een the Alaska Power Authority and interested resource management agencies.
Through this exchange, the concerns of all agencies involved would be identified
ear1y and hopefully prevent unnecessary delays in the progress of the feasi-
bility study, application for the Federal Energy Regulatory Commission license
to construct, and Environmental Impact Statement review .
As proposed, the Steering Committee would be composed of representatives
of resource agencies with responsibilities pertaining to the Susitna Hydro-
electric Feasibility Studies and/or the project•s environmental consequences.
We therefore invite your agency's participation.
The committee would provide for interagency coordination through joint
review of project related materials and development of more informed and
uniform positions representing all resource interests. We believe this will
provide a more efficient process of information exchange.
Proposed objectives for this committee are to:
1. Review and comment on study approaches throughout each phase of the
planning process;
2. Insure that the biological and related environmental studies, their
timing, and technical adequacy are planned, implemented, and conducted
to provide the quantitative and qualitative data necessary to:
(a) assess the potential impacts to fish and wildlife resources, and
(b) provide the basis for mitigation and compensation of resource
losses which will result from the project;
,·
/----...........
-~ ,;~
/ / ' . I
/ ;_ ( -t::;)
'·., .__,)
----------------------------~---------------·---------------------·---~--··--·--
Colonel Lee R. Numi
June 3, 1980
P·age Two
3. Provide a forum for continued project revie\'1 of a11 aspects of the
studies. for a timely exchange of information, and for reconunendation of
study redirection, should the accomplishment of specific objectives be
in jeopardy;
4. ~tonitor compliance of the studies with all state and federal laws t
regulatit "S, Executives Orders, and mandates as they apply to fish and
wildlife resources; and
5. Provide unified agency conments from the committee to the Power Authority.
Should your agency elect to participate 1n the committee, we recorrmend
that your representative have a technical background enabling him to comment
on the adequacy and approach of ongoing and future feasibility studies, and
be able to speak knowledgeablY on the policies and procedures of your agency
with respect to the revia1 of the Federal Energy Regulatory Comm1.ss1on license
application for the project and the subsequent Environmental Statement {ES).
-·
The first Susitna Hydroelectric Steering Corranittee meeting ~1111 be held
at the Alaska Power Authority, 333 vlest 4th Avenue, Suite 31, Anchorage,
Alaska on June 12th at 9:00 AM. Attached is a sheet with a description of
the agenda for this first meeting.. Your attendance is encouraged.
-Attachment:
as noted
Sincerely~
Eri _,.. ·.p -.\1---'! d .._ • lUU I
Executive Director
-
-
-
-
-
--.,
j
-
-
-
-
-
-
-
....
e
r·1r. Bob Bowker
U. S. Fish and Wildlife
Service
733 West 4th Avenue
Anchorage, Alaska 99501
Dear l~r. Bowker:
,·,.._,,.....,,.._,\ • v .• ,_l\ ,,-._;, .. ~v ...... ~ 1 e
June 3, 1980
The Alaska Power Authority through 1ts consult~nt, Acres American
Incorporated, is 1n the early stages of a 30-month feasib11ity study of the
proposed Sus1tna Hydroelectric Project. 13ecause of the magnitude of this
study, effective interagency coordination will be best accomplished through
fo1~tion of a Susitna Hydroelectric Steering Committee. The function of
this committee vrould be to provide coordinated exchanges of information
between the Alaska Pm:er Authority and interested resource management agencies.
Through this exchange, the concerns of ali agencies involved would be identified
early and hopefully prevent unnecessary delays in the progress of the feasi-
bility study. application for the Federal Energy Regulatory Commission license
to construct, and Environmental Impact Staten~nt review.
As p~·oposed, the Steering Corrrn1ttee ,,·tould be composed of representatives
of resource agencies with responsibilities pertaining to the Susitna Hydro-
electric Feasibility Studies and/or the project,s environmental consequences.
'rie therefore invite your agency's participation.
The committee \'Jou1d provide for interagency coordination through joint
revie~ of project related materials and development of more informed and
uniform posit1ons representing all resource interests. We believe this will
provide a IIlOre efficient process of information exchange.
Proposed objectives for this committee are to:
1. Revie\'1 and co11100nt on study approaches throughout each phase of the
planning process;
2. Insure that the biological and related environmental studies. their
t1m1ng, and technical adequacy are planned, implemented, and conducted
to provide the quantitative and qualitative data necessary to:
(a) assess the potential impacts to fish and wildlife resources, and
(b) prov1de the basis for mitigation and compensation of resource
losses which will result from the project;
..
i
i
?!")/ 7 J
cJ //I ·~ r
_I_.,
J.· "-<::. j. j.f£• .
;:·
I ~.· .f .
--·· ~ -. ----Page Two 0 e
3. Provide a forum for cont1nued project reviet~ of all aspects of the
studies, for a timely exchange of information, and for recommendation of
study redirection, should the accomplishment of spec1f1c objectives be
in jeopardy;
4. Mon1tor comp11ance of the studies with all state and federal laws,
regulations, Executives Orders, and mandates as they apply to fish and
wildlife resources; and
5. Provide unified agency comments from the committee to the Power Authority.
Should your agency elect to participate 1n the corrm1ttee, we recommend
that your representative have a technical background enabling h1m to corrrnent
on the adequacy and approach of ongoing and future feas1b111ty studies, and
be able to speak know1edgeab1y on the policies and procedures of your agency
v;ith respect to the rev1e\v of the Federal Energy Regulatory Commission license
application for the project and the subsequent Env1ron~~nta1 Statement (ES).
The first Susitna Hydroe1ectr1c Steering Committee meeting w111 be held
at the Alaska Po·der Authority, 333 Hest 4th Avenue, Suite 31, Anchorage.
Alaska on June 12th at 9:00 AM. Attached 1s a sheet with a description of
the agenda for this first meeting. Your attendance is encouraged.
AttZlchment:
a5 noted
·~.-
S1ncerely,
Eric P. Yould
Executive D1rector
~~-::~j!:;-·;@t·-??tM&aaiiit?ii&WWWE iiiiRf,
...
-
IIIII
...
..,
...
...
..;
..,
....
-
....
..
.....
-
..
....
-
-
-
-
-
-
-
-
-~. -
-
-
-
.....
1-\r. John Rego
Energy Specialist
-
Bureau of Land Hanagement
4700 East 72nd Avenue
Anchorage, Alaska 99507
Dear Hr. Rego:
i\Lil;:.i\1-<. t'vi'iu\ A\.J I hUi\1 I ( e
June 3, 1980
The Alaska Power Authority through 1ts consultant, Acres American
Incorporated, is 1n the early stages of a 30-month feas1b111ty study of the
proposed Sus1tna Hydroelectric Project. Because of the magnitude of this
study, effective interagency coordination w111 be best accomp11shed through
for[nation of a Sus1tna Hydroelectric Steering Committee. The function of
this committee would be to provide coordinated exchanges of information
between the Alaska Power Authority and 1nterested resource management agencies.
Through this exchange, the concerns of a11 agencies 1nvo1ved l'tould be identified
early and hopefully prevent unnecessary delays in the progress of the feasi-
bi1ity study. application for the Federal Energy Regulatory Commission license
to construct~ .and Envil·onmenta1 Impact Statement revie'lt.
As proposed, the Steering Committee \·tould be composed of representatives
of resource agencies with responsibilities pertaining to the Susitna Hydro-
e1ectric Feasibility Studies and/or the project 1 S environmental consequences.
~le therefore invite your agency's participation.
The co:nmittee ~-Jou1d provide for interagency coordination through joint
revie'.i of project related materials and development of more ·informed and
uniform positions representing all resource interests. We believe this will
provide a mm~e efficient process of informution exchange.
Proposed objectives for this committee are to:
1. Review and comment on study approaches throughout each phase of the
planning process;
.,
'-· Insure that the bio1og1ca1 and related environmental studies, their
timing, and technical adequacy are planned, implemented, and conducted
to provide the quantitative and qua11tat1ve data necessary to:
(a) assess the pot2ntia 1 impacts to fish and ~oli ld1 He resources. and
(b) provide the basis for mitigation and compensat1on of resource
losses which w111 result from the project;
r) __ ,
/-.3 / / .
.. >
•·:;d@-~ .IJ:·L~·"'""'UUM:&Si&ii-!1!!
J {~-
-.
' .
. .
··~. ;
I"B9C 1\'10
3. Provide a forum for continued project review of all aspacts of the
studies, for a t1mely exchange of information, and for recommendation of
study redirection, should the accomplishment of sp~cific objectives be
1 n jeopardy;
4. r1onitor compliance of the studies with all state and federal laws.
regulations, Exacutives Orders, and mandates as they apply to f1sh and
wildl1fe resources; and
5. Prov1 de unified agency ccm:nents from the committ~e to the Pov1er Authority.
Should your agency elect to participate in the committee. \1e rccomnend
that your representative have a technical background enab11ng h1m to comment
on the adequacy and approach of ongoing and future feas1bi11ty studies, and
be able to speak knowledgeably on the policies and procedures of your agency
with respect to the rev1ew of the Federal Energy Regulatory Commission license
application for the project and the subsequent Env1ronmental Statement (ES).
The first Sus1tna Hydroelectric Steering Conm1ttee meeting \-t11l be held
nt the Alaska Power Authority, 333 West 4th Avenue, Su1te 31, Anchornge,
A1aska on June 12th at 9:00 A/'·1. Attached is a sheet \'lith a descr1pt1on of
the agenda for tt11s first meeting. Your attendance is Gncouraged.
Attachment:
as noted
Sincerely,
Eric P. Yould
Executive D1rector
...
...
...
-
-
-
----
~
-
-
-
-
-
-
...... ,
-
-
.. c:::
-
-
-
ALASKA POWER AUTHORITY
·It
The Honorable Robert E. LeResche
Commissioner
Department of Natural Resources
Pouch !-1
Juneau, Alaska 99811
Dear Commissioner LeResche:
;-
June 3, 1980
The Alaska Power Authority through its consultant, Acres American
Incorporated, is in the early stages of a 30-rnonth feasibility study of the
proposed Susitna Hydroelectric Project. Because of the magnitude of this
study, effective interagency coordination will be best accomplished through
formation of a Susitna Hydroelectric Steering Committee. The function of
this conunittee would be to provide coordinated exchanges of information
between the Alaska Power Authority and interested resource management agencies.
Through this exchange, the concerns of all agencies involved would be identified
early and hopefully prevent unnecessary delays in the progress of the feasi-
bility study, application for the Federal Energy Regulatory Commission license
to construct, and Environmental Impact Statement review •
As proposed, the Steering Committee would be composed of representatives
of resource agencies with responsibilities pertaining to the Sus1tna Hydro-
electric Feasibility Studies and/or the project's environmental consequences.
He therefore invite your agency•s participation.
The committee would provide for interagency coordination through joint
revie'rl of project related materials and development of more informed and
uniform positions representing all resource interests. We believe this will
provide a more efficient process of information exchange.
Proposed objectives for this committee are to:
1. Review and comment on study approaches throughout each phase of the
planning process;
2. Insure that the biological and related environmental studies, their
timing, and technical adequacy are planned~ implemented, and conducted
to provide the quantitative and qualitative data necessary to:
(a) assess the potential impacts to fish and wildlife resources, and
(b) provide the basis for mitigation and compensation of resource
losses which will result from the project;
..... __..--~,
.-/' ( ~ ', '~--. ? / \ _;, , I
'\ I
"----'/
comniss1oher Robert E. LeResche
June 3~ 1980
Page Two
3. Provide a forum for continued project revie\t of all aspects of the
studies, for a timely exchange of information, and for recommendation of
study redirection. should the accomplishment of specific objectives be
in jeopardy;
4. Monitor comPliance of the studies with a11 state and -Federal 1awsJ
regulations~, Executives Orders, and mandates as they apply to fish and
wildlife resources; and
5. Provide unified agency comments from the committee to the Power Authority.
Should your agency elect to participate 1f.l th.e corrmittee, we recomnend
that your representative have a technical background enabling hitn to comnent
on the adequacy and approach of ongoing and future feasibility studies, and
be able to speak knm!l1edgeab1y on the policies and procedures of your agency
\'lith respect to the re:view of the Federal Energy Regulatory Comm1ss10., license
application for the project and the subsequent Env1ronmenta1 Statew~nt (ES)_
The first Susitna Hydroelectric Steering Committee meeting w111 be held
at the Alaska Power Authority. 333 West 4th Avenue~ Suite 31~ Anehorag~!'
Alaska on June 12th at 9:00 AM. Attached is a ~heet with a description of
the agenda for this first m~eting. Your attendance is encouraged.
Attachment:
as noted
cc: A1 Carson
Sincerely,
Eric P. Yould
Executive Director
> '1.1 ' > .,__·>I._'\ •"-.." I
Mrs. Frances A. Ulmer _... ' ,, June 3, 1980 _,_.,.--
-~--~~~-·-----~
-..
-
-·
-
-
-
-
-
.......
-
-
-
.....
r~irs. Frances A. Ulmer
Director
Division of Policy Development
and Planning
Office of the Governor
Pouch AD
Juneau, Alaska 99811
Dear Hrs. Ulmer:
June 3, 1900
The Alaska Power Authority through 1ts consultant, Acres American
Incorporated, is in the early stages of a 30-month feasibility study of the
proposed Susitna Hydroelectric Project. Because of the magnitude of this
study, effective interagency coordination will be best accomplished through
for~ation of a Susitna Hydroelectric Steering Committee. The function of
this committee would be to provide coordinated exchanges of information
bet\'1een the A 1 aska Power Author1 ty and 1 nterested resource management agencies.
Through this exchange, the concerns of all agencies involved would be identified
early and hopefully prevent unnecessary delays in the progress of the feasi-
bility study, application for the Federal Energy Regulatory Commission license
to construct, and Environmental Impact Statement review.
As proposed, the Steering Committee would be composed of representatives
of resource agencies with responsibilities pertaining to the Susitna Hydro-
electric Feasibility Studies and/or the project•s environmental consequences.
We therefore invite your agency•s participation.
The conr.1ittee would provide for interagency coordination through joint
review of project related materials and development of more informed and
uniform positions representing all resource interests. He be11eve this will
provide a nrore efficient process of information exchange.
Proposed objectives for this committee are to:
1. Review and comment on study approaches throughout each phase of the
planning process;
2. Insure that the biological and related environmental studies, their
timing, and technical adequacy are planned, implemented, and conducted
to provide the quantitative and qualitative data necessary to:
(a) assess the potential impacts to fish and wildlife resources~ and
(b) provide the basis for mitigation and compensation of resource
losses which will result from the project;
.. ,1
/
-::::=:::-"""'
-(\ \ I 7 i ~
Mrs. Frances A. Ulmer~
June 3, 1980 w
?,age Two -
~3. Provide a forum for continued project revicH of a11 aspects of the
studies, for a timely exchange of information, and for recommendation of
study redirection, should the accomplishment of specific object1ves be
in jeopardy;
4. f·1onitor compliance of the studies Nith all state and federal laws,
regulations, Executives Ot·ders, and mandates as they apply to fish and
wildlife resources; and
5. Provide unified agency comments from the committee to the Power Authority.
Should your agency elect to participate 1n the committee, we recommend
that your representative have a technical background enabling him to comment
on the adequacy and approach of ongoing and future feasibility studies, and
be able to speak knowledgeably on the policies and procedures of your agency
with respect to the review of the Federal Energy Regulatory Commission license
application for the project and the subsequent Environmental Statement (ES).
The first Susitna Hydroelectric Steering Committee meeting will be held
at the A1aska Power Authority, 333 Uest 4th Avenue, Suite 31, Anchorage,
Alaska on June 12th at 9:00 .~·1. Attached 1s a sheet with a description of
the agenda for this first meet1ng. Your attendance 1s encouraged.
Attachment:
as noted
cc: Office of Coasta 1 f·1anagement
Sincerely,
Eric P. You1d
Executive Director
..
...
....
..
-
...
.,.,
-
...
-
....
..
-
--
.,.,
.,
-
.,....-~
-
-
.....
.....
.....
-
-
-
-..-
-
-
-
41t ALASKA POWER AUTHORITY e
June 3, 1980
The Honorablr Ronald 0. Skoog
Commissioner
Department of Fish and Game
Subpart Building
Juneau, Alaska 99801
Dear Commissioner Skoog:
The Alaska Power Authority through its consultant, Acres American
Incorporated, is in the early stages of a 30-month feasibility study of the
proposed Susitna Hydroelectric Project. Oecause of the magnitude of this
study, effective interagency coordination will be best accomplished through
formation of a Susitna Hydroelectric Steering Committee. The function of
this committee would be to provide coordinated exchanges of information
between the Alaska Power Authority and interested resource management agencies.
Through this exchange, the concerns of all agencies involved would be identified
early and hopefully prevent unnecessary delays in the progress of the feasi-
bility study, application for the Federal Energy Regulatory Commission license
to construct, and Environmental Impact Statement review.
As proposed, the Steering Co~~fttee would be composed of representatives
of resource agencies with responsibilities pertaining to the Susitna Hydro-
electric Feasibility Studies and/or the project's environmental consequences.
We therefore invite your agency's participation.
The committee would provide for interagency coordination through joint
review of project related materials and development of more informed and
uniform positions representing all resource interests. He believe this ~·Jill
provide a more efficient process of information exchange •.
Proposed objectives for this committee are to:
1. Review and comment on study approaches throughout each phase of the
planning process;
2. Insure that the biological and related environmental studies, their
timing, and technical adequacy are planned, implemented, and conducted
to provide the quantitative and qualitative data necessary to:
(a) assess the potential impacts to fish and wildlife resources, and
(b) provide the basis for mitigation and compensation of resource
losses which will result from the project;
1/je nonorab! e i\una 'i t1 0. Skoog
_ June 3t 1980
page T~'IO
3. Pro vi de a forum for continued project revi e\'1 of a 11 aspects of the
studies, for a timely exchange of 1nfonnat1on, 4nd for recmrnnendation of
study redirection. should the accompl'tshment of specific object1ves be
in jeopardy;
.,
4. ~1onitor compliance of the studies \'lith all state and federal laws,
regulations, Executives Orders, and mandates as they apply to fish and
wildlife resources; and
5. Provide unified agency conrnents from the committee to the Po\'ler Authority.
Should your agency elect to participate in the comn1ttee, we reconmend
that your representative have a technical background enabling him to conment
on the adequacy and approach of ongoing and future feasibility studies, and
be able to speak knowledgeably on the policies and procedures of your agency
w1th respect to the review of the Federal Energy Regulatory Commission 11cense
app1ication for the project and the subsequent Environmental Statement (ES).
·rhe first Sus1tna Hydroelectric Steering Committee meeting '11ill be held
at the Alaska Power Authority, 333 \iest 4th Avenue, Suite 31, Anchorage,
Alaska on June 12th at 9:00 AM.. Attat:hed is a sheet with a description of
the agenda for this first meeting. Your attendance is encouraged.
c
Attacnment:
as noted
cc: Tom Trent
CONCUR:
RA~1 (7.._
TJH ..
/J:f)z_, 7
DWB ...AL.£ l.)
'
Sincerely,
Eric P .. Yould
Executive Director
-
"'
......
..._.
......
-
....
-
-
-
-
"-
-
~1r. Lee A. Wyatt
Planning Director
~!atanuska-Susitna Borough
Box B
Palmer, Alaska 99645
Dear Mr. ~Iyatt:
ALASKA POWER AUTHORITY e
June 3~ 1980
The Alaska Power Authority through its consultant, Acres American
Incorporated, is in the early stages of a 30-month feasibility study of the
proposed Susitna Hydroelectric Project. Because of the magnitude of this
study, effective interagency coordination will be best accomplished through
fonnation of a Susftna Hydroelectric Steering Committee. The function of
this committee would be to provide coordinated exchanges of information
between the Alaska Power Authority and interested resource management agencies.
Through this exchange, the concerns of all agencies involved would be identified
early and hopefully prevent unnecessary delays in the progress of the feasi-
bility study, application for the Federal Energy Regulatory Commission license
to construct, and Environmental Impact Statement review.
As proposed, the Steering Committee would be composed of representatives
of resource agencies with responsibilities pertaining to the Sus1tna Hydro-
electric Feasibility Studies and/or the project's environmental consequences.
He therefore invite your agency's participation •
The committee would provide for interagency coordination through joint
review of pra.·~ct related materials and development of more informed and
uniform posit·ions representing all resource interests. We believe this ~'1111
provide a more efficient process of information exchange.
Proposed objectives for this committee are to:
1. Review and comment on study approaches throughout each phase of the
planning process;
2. Insure that the biological and related environmental studies, their
timing, and technical adequacy are planned, implemented, and conducted
to provide the quantitative and qualitative data necessary to:
(a) assess the potential impacts to fish and wildlife resources, and
(b) provide the basis for mitigation and compensation of resource
losses which will result from the project;
.,/
·fitr.. Lee A. 1-lyatt
June 3, 1980
Page T\"lO
3. Provide a forum for continued project review ·of all aspects of the
studies, for a timely exchange of information, and for recotm'~ndation of
study redirection, should the accomplishment of specifi~ objectives ba
fn jeopardy;
4. rionitor compliance of the studies \•J1th all state and federal la\IIS,
regulations, Executives Orders, and mandates as they apply to fish and
wildlife resources; and
5. Provide unified agency cements frorn the committee to the Power Authority.
Should your agency elect to participate in the committee, we rt1c.omm~nd
that your representative have a technical background enabling h1m to comment
on the adequacy and approach of ongoing and future feasibility studies, and
be able to speak knowledgeably on the policies and procedures of your agency
\'lith respect to the reviell/ of the Federal Energy Regulatory Conrnission license
application for the project and the subsequent Environmental Statement (ES} ..
The first Susitna Hydroelectric Steering Comn1ttee meeting will be held
at the Alaska Power Authority, 333 Hest 4th Avenue, Suite 31, Anchorage,
Alaska on June 12th at 9:00 AM. Attach~d is a sheet with a description of
the agenda frr ':his first meeting.. Your attendance is encouraged.
Attachment:
as noted
Sincerely.
Eric P. Yould
Executive Director
---~ . .::·
-
......
-
-
-
-
.....
fl.Lf\~M 1-'Uvlt.K AU l rilm.l i i e -
June 3, 1980
The Honorable Ernst W. Mueller
Colmlissfoner
Department of Environmental Conservation
Pouch 0
Juneau, Alaska 99811
Dear Commissioner Mueller:
The Alaska Power Authority through its consultant, Acres American
Incorporated, is in the early stages of a 30-month feasfb11fty study of the
proposed Susitna Hydroelectric Project4 Because of the magnitude of this
study, effec~ive interagency coordination will be best accomplished through
formation of u Susitna Hydroelectric Steering Committee4 The function of
this committee would be to provide coordinated exchanges of information
between the Alaska Power Authority and interested resource management agencies.
Through this exchange, the concerns of all agencies involved would be identified
early and hopefully prevent unnecessary delays in the progress of the feasi-
bility study, application for the Federal Energy Regulatory Commission license
to construct, and Environmental Impact Statement review.
As proposed, the Steering Committee would be composed of representatives
of resource agencies with responsibilities pertaining to the Susitna Hydro-
electr-ic Feasibility Studies and/or the project's environmental consequences.
~-Je therefore invite your agency's participation •
The committee would provide for interagency coordination through joint
revie~1 of project related materials and development of more informed and
uniform positions representing all resource interests. We believe this will
provide a more efficient process of information exchange.
Proposed objectives for this committee are to:
1. Review and c~~ent on study approaches throughout each phase of the
planning process;
2. Insure that the biological and related environmental studies~ their
timing, and technical adequacy are planned, implemented, and conducted
-. to provide the quantitative and qualitative data necessary to:
-
-
-
-
(a) assess the potential impacts to fish and wildlife resources, and
(b) provide the basis for mitigation and compensation of resource
losses wh1ch will result from the project;
'f/he Hono~able Ernst W. Mueller
·June 3, 1980
Page T\'/o
3. Provide a forum for continued project reviel~ of all asoects of the
studies, for a timely exchange of information~ nnd for'reconmendation of
study re~ir"ection~ shou1d the accomplishmant of specific objectives be
in jeopardy;
4. Nonitor compliance of the studies with all state and federal laws~
regulations, Executives Orders, and mandates as they apply to fish and
\'li 1 d1 ife resources; and
5. Provide unified agency comments from the committee to tho Power Authority.
Should your agency elect to participate in the committee, vte recommend
that your representative have a technical background enabling him to corm1ent
on the adequacy and .approach of ongoing and future feasibility studies, and
be able to speak knowledgeably on the policies and procedures of your agency
vlith respect to the review of the Federal Energy Regulatory Commission license
application for the project and the subsequent Enviromr.ental Statement (ES).
The first Susitna Hydroelectric Steering Committee meeting ~1111 be held
at the Alaska Power Authority. 323 !J~~t .;l;j, nvt:nue, ~u11:e 31, Anchorage,
Alaska on June 12th at 9:00 ~~-Attached is a sheet \·J1th a description of
the agenda for this first sr.seting. Your attendance is encouraged.
Attachment:
as noted
cc: Dave Sturdevant
Sincerely,
Eric P. Yould
Executive Director
-
~
-
......
-
-
-·
-
-
-
-
-
~ ALASKA POWER AUTHORITY ~
Mr. Rona 1 d r·torri s
National Marine Fishery Service
701 11 C" Street
Box 43
Anchorage, Alaska 99513
Dear Mr. f·1orri s :
June 3, 1980
The Alaska Power Authority through its consultant, Acres American
Incorporated, is fn the early stages of a 30-month feasibility study of the
proposed Susitna Hydroelectric Project. Because of the magnitude of this
study. effective interagency coordination will be best accomplished through
formation of a Susitna Hydroelectric Steering Committee. The function of
this committee would be to provide coordinated exchanges of information
between the Alaska Power Authority and interested resource management agencies.
Through this exchange, the concerns of all agencies involved would be identified
early and hopefully prevent unnecessary delays in the progress of the feasi-
bility study, application for the Federal Energy Regulatory Commission license
to construct, and Environmental Impact Statement revieN.
As proposed, the Steering Committee would be composed of representatives
of resource agencies with responsibilities pertaining to the Susitna Hydro-
electric Feasibility Studies and/or the project's environw~ntal consequences.
lie therefore invite your agency's participation.
The committee would provide for interagency coordination through joint
review of project related materials and development of more informed and
uniform positions representing all resource interests. We believe this \<'1111
provide a more efficient process of information exchange.
Proposed objectives for this committee are to:
1. Revi e~<~ and co1m1ent on study approaches throughout each phase of the
planning process;
2. Insure that the biological and related environmental studies, their
timing, and technical adequacy are planned, implemented, and conducted
to provide the quantitative and qualitative data necessary to:
(a) assess the potential impacts to fish and wildlife resources, and
(b) provide the basis for mitigation and compensation of resource
losses which will result from the project;
if• .Rona 1 d ~1orr1 s
june 3 , 1980
page T~to
3. Provide a forum for continued project revie\'f of a11 aspects of the
studies, for a timely exchange of information, and fo~ recommendZtt1on nf
study redirection, should the accomplishment of specif1<:object1ves be
in jeopardy;
4. t-tonitor compliance of the studies \'lith all state and federal laws~
regulations, Executives Orders, and mandates as they apply to fish and
\vi1d1 ife resources; and
5. Provide unified agency com'Tlents from the committee to the Power Authority.
Sh-ould your agency elect to participate in the committee, \'Ie recommend
that your representative have a technical background enabling him to comment
on the adequacy and approach of ongoing and future feasibility studies, and
be able to speak kno\vledgeab1y on the policies and procedures of your agency
\'lith respect to the revie\'1 of the Federal Energy Regulatory Corrrn1ssion license
application for the project and the subsequent Environmental Statement {ES)1!
The first Susitna Hydroelectric Steering Comnittee meetingw111 be held
at the Alaska Power Authority, 333 Hest 4th Avenue, Suite 31, Anchorage"
Alaska on June 12th at 9:00 Ar,1. Attaehed is a sheet \~ith a description of
the agenda for this first meeting. Your attendance 1s encouraged.
Attachment-:
as noted
Sincerely~
Eric P. Yould
Execut·t ve Oi rector
1.,,·. wi1v·c I ..... , ·.-·-,~ _ _Ju _____ _J.J.'-_. .....
. ~ ( . e ALASKA POWER .. AUTHORITY -···=--
....
-
-
-
-
.......
-
-
-
-
-
Mr. Dave Hickok, Director
Arctic Environmental Information
and Data Center
University of Alaska
707 A Street
Anchorage, Alaska 99501
Dear t1r. Hickok:
,June 3, 1980
The Alaska Power Authority through its consultant, Acres American
Incorporated. is 1n the early stages of a 30-month feasibility study of the
proposed Susitna Hydroelectric Project. Because of the magnitude of this
studys effective interagency coordination will be best accomplished through
formation of a Susitna Hydroelectric Steering Committee. The function of
this committee would be to provide coordinated exchanges of information
beu~een the Alaska Power Authority and interested resource management agencies.
Through this exchange, the concerns of all agencies involved \'tOuld be identified
early and hopefully prevent unnecessary delays in the progress of the feasi-
bility study, application for the Federal Energy Regulatory Commission license
to construct, and Environmental Impact Statement reviffi~.
As proposed, the Steering Committee would be composed of representatives
of resource agencies with responsibilities pertaining to the Susitna Hydro-
electric Feasibility Studies and/or the project•s environmental consequences.
He therefore invite your agency•s participation.
The committee would provide for interagency coordination through joint
review of project related materials and development of more informed and
uniform positions representing all resource interests. ~!e believe this wi11
provide a more efficient process of information exchange.
Proposed objectives for this committee are to:
1. Review and comment on study approaches throughout each phase of the
planning process;
2. Insure that the biological and related environmental studies, their
timing, and technical adequacy are planned, implemented, and conducted
to provide the quantitative and qualitative data necessary to:
(a) assess the potential impacts to fish and wildlife resources, and
(b) provide the basis for mitigation and compensation of resource
losses which will result from the project;
,•w. t.la'!'e n re:;.'O~
June 3, 1930
Page T\'IO
3. Provide a forum for continued project review of al1 aspects of the
studies, for a timely exchange of information, and for recommendation of
study redirection, should the accomplishment of specific objectives be
in jeopardy;
4. Monitor compliance of the studies with al1 state and federal laws,
regulations, Executives Orders. and mandates as they apply to fish and
wildlife resources; and
5. Provide unified agencr comments from the committee to the Power Authority ..
Should your agency elect to part1c1pata 1n the conmittee, we recommend
that your representative have a techn1<:a1 background enabling him to comment
on the adequacy and approach of ongoing and future feas1b111ty studies, and
be able to speak-knowledgeably on the pol1c1as and procedures of your agency
\·lith respect to the revie1 of the federal Energy Regulatory Comn1ssion license
application far the project and the subsequant Environmental Statement {ES).
The first Sus1tna Hydroelectric Steering Committee meeting \11111 be held
at the Alaska PO\tJer Authority, 333 t~est 4th Avenue. Suite 31. Anchorage,
Alaska on Jum 12th at 9:00 AM. Attached is a sheet with n description of
the agenda for this first meeting. Your attendance is encouraged.
p, ttachment:
as noted
Sincerely,
Eric P. Vou1d
Executive Director
-----~-----_.__._...--,.
The c~~ittee would provide for interagency coordinati on throu gh joint
r eview of project r elated materials and development of more informed and
uniform po sitions representing all resource interests .We believe this will
provide a mo re efficient process of informati on p.xchange.
As propo sed. the Steering Committee HOuld be compose d of repres entatives
of r esource agencies with responsibilities pertaining to the Susitna Hyd ro-
ele ct ric Feasibility Studies and/or the project's environment al conseque nces.
We t herefore inv ite your a ~~ncyls partici pati on.
Th e Alaska Pow er Authority th roug h its consultant.Acres Ame ri can
Incorporated.is i n the early stages of a 3D-month feasibil ity study of t he
pr op osed Susi t na Hy droelectric Project .Because of t he ma gnitude of this
s tudy.effective interagency coordination will be best accomplished thro ugh
forr.4 t ion of a Susitna Hyd roelectric Steering Committee.The function of
t his cOQmit tee woul d be to provide coordinated exch~nges of inforoation
between the Alaska Power Authority and interested r esource ma nageme nt agencies.
Th rough t his exchan ge.the concerns of all agencies involved would b~i dentified
earl y and hope fully prevent unnecessary delays in thp.progress of the fe~si
bil ity s tudy.application for t he Federal Ener gy Regulatory C o~ission license
to con struct.and Environmental Impact Statement r~view.
J une 4 .1980
throughout each phase of the
assess t he po tential i mpacts t o fi sh and wildl ife r escurces.and
provide th e basis for mitigation and compensat ion of resource
l osses which will result from the pro fect;
(a)
(b )
Review and comment on study approaches
planni ng process;
Proposed objectives for this committee are to :
(nsure that the biological and related environmental studies.their
ti ming.and technical adequacy are planned. i mplemented.and conduc ted
to provide the qua nt itative and qua li tative data necessar y to :
1.
2.
Dear Sir :
Director
En viro nmental Pro tection Ag ency
U.S.O epa r~nt of Ener gy
Alas~a Ope rations Offi ce
70 1 -c-Street
Anchor age .Alaska 99 513
...Environmen i a:i .Ji.ro~t.L-:------I _"...I>-- •-,,-.,.ALAS KA POWER AUTHOR ITY
!
I
(
L
I
i
I
I
I
I
I
I
!
I
I
I
I
;t.-·ordliC:n ~a 1 Pro c~ct1 on Agency
IJ/le 4, 1980
lage Two
3. Provide a forum for continued project revieN of a11 aspects of the
studies. for a timely exchange of information, and for recormnendation of
study redirection, should the accomplishment of specif1e objectives b~
in jeopardy;
4.. ~1onitor compliance of the studies Nith all state and federal laws,
regulations~ Executives Orders~ and mandates as they apply to fish and
vii 1dli fe resources; and
5.. Provide unified agency comments from the committee to the Power Authority.
Should your agency elect to participate 1n the comnittee. we recorrmend
that your representatiVP have a technical background enabling h1m to conment
on the adequacy ;lr~ appr'-lch of ongoing and future feasibility studies, and
be able to speak knowledg~'bly on the policies and procedures of your agency
with respect to the rev1e\t~ of +he Federal Energy Regulatory Commission 1 icense
app1 ication for the project and t••~ ~ubsequent Environmental Statement (ES),.
The first Susitna Hydroe1ectric Stee..-ing Committee meeting will be hel'd
at the Alaska Power Authority, 333 West 4th Avenue, Suite 31, Anchorage.
Alaska on June 12th at 9:00 Af·1. Attached is a sheet with a description of
_ the agenda for this first meeting. Your attendance 1s encouraged ..
Attachment:
as noted
Sincerely,
Eric P. You1d
Executi~e Director
..... ~
~
! '
-
I"""
!
r
-
,..-..
r
Area Director
Heritage Con$ervation &
Recreation Service
Department of the Interior
1011 East Tudor Road
Anchorage, Alaska 99507
Dear Sir:
ALASKA POWER AUTHORITY
June 4, 1980
The Alaska Power Authority through 1ts consultant, Acres American
Incorporated~ is in the early stages of a 30-month feasibility study of the
proposed Susitna Hydroelectric Project. Because of the magnitude of this
study, effective interagency coordination \'lill be best accomplished through
formation of a Susitna Hydroelectric Steering Committee. The function of
this committee would be to provide coordinated exchanges of information
be't't~een the Alaska PO\"'er Authorf ty and interested resource management agencies.
Through this exchange. the concerns of all agencies involved would be identified
early and hopefully prevent unnecessary delays 1n the progress of the feasi-
bility study~ application for the Federal Energy Regulatory Commission license
to construct, and Environmental Impact Statement review.
As proposed. the Steering Cotmn1ttce would be composed of representatives
of resource agencies with responsibilities pertaining to the Susitna Hydro-
e1ectric Feasibility Studies and/or the project 1 s environmental consequences.
~Je therefore invite your agency's participation.
The committee would provide for interagency coordination through joint
review of project related materials and development of more 1nfonned and
uniform positions representing al1 resource interests. He believe this will
provide a more efficient process of information exchange.
Proposed objectives for this committee are to:
1. Revi e~-v and comment on study approaches throughout each phase of the
planning process;
2. Insure that the biological and related environmental studies, their
timing, and technical adequacy are planned, implemented, and conducted
to provide the quantitative and qualitative data necessary to:
(a) ass~ss the potential impacts to fish and t<dld1ife resources, and
(b) provide the basis for mitigation and compensation of resource
losses which will result from the project;
···r·/)\rea Oi rector
/
.-June 4, 1980
Page Two
_./'
(·--}
\__; •
3. Provide a forum for continued project review of all aspects of the
studies, for a timely exchange of information, and for recommendation of
study redirection, should the accomplishment of specific objectives be
in jeopardy;
4. Monitor compliance of the studies with all state and federal laws,
regulations, Executives Orders, and mandates as they apply to ffsh and
wildlife resources; and
~. Provide unified agency comments from the committee to the Power Authority.
Should your agency elect to participate in the committee, we recommend
that your representative have a technical background enabling him to comment
on the adequacy and approach of ongoing and future feasibility studies, and
be able to speak knowledgeably on the policies and procedures of your agency
with respect to the review of the Federal Energy Regulatory Commission license
application for the project and the subsequent Environmental Statement (ES}.
The first Susitna Hydroelectric Steering Committee meeting will be held
at the Alaska Power Authority. 333 West 4th Avenue, Suite 31, Anchorage,
Alaska on June 12th at 9:00 AM. Attached is a shegt with a description of
the agenda for this first meeting. Your attendance is encouraged.
r ... ttachment:
as noted
Sincerely,
Eric P. Yculd
Executive Diractor
-
IIIII
....
....
-
-
-
..,
...
...
...
-
-
...;
-
-.J
..
-
-
-
-
REPLY "0
ATTENTnJN OF:
-e DEPARTMENT OF THE ARMY
ALASKA DISTRICT. CORPS OF ENGINEERS
P.O. BOX 7002
ANCHORAGE, ALASKA 99510
NPADE 1 2 J \.! :! 1980
Eric Yould, Executive Director
Alaska Power Authority
333 W. 4th Ave., Suite 31
Anchorage, Alaska 99501
Dear Mr. Yould:
RECEIVED
\ ;'• ~.\ ' \ ',' '. . 6 ...... ,...,. '. , ~ · !\J 1. _: -u·, ~-
J.JASKA POWER AUTHORITY
I refer to your invitation to participate in the Susitna Hydroelectric
Steering Committee expressed in your 3 June 1980 letter. At the present
time we are unable to participate in the committee due to severe funding
and personpower constraints. I envision that the committee, to properly
perform its objective, will in fact have to delve in detail into many
complex engineering and environmental concerns. This would require a
considerable effort of a senior staff member with possible advisory
action by others in the District.
Should funds and personpower become available at a later time we will
reconsider your kind offer. However, we will continue to provide the
necessary reviews required for the issuance of permits under our
regulatory program.
If I can be of any further assistance, please do not hesitate to contact
me directly. If further details are desired by your staff,
Mr. Harlan Moore, Chief, Engineering Division, can be contacted at
752-5135.
Lt Colonel, Corps of Engineers
Acting District Engineer
'·
d
r
:1 r TH\E:
DATE:
9:00 Ai·1
'1!1!'!!\ ..., • • \L.\SiiA P0\\'1-:1{ ,\l'TBOIOTY
SUSIHlA HYDRO STECRii:G COi·\1-\lTf!E i-:l:Tli:;c;
June 12, 1980
PL/IC[: Alaska Power Authority
333 West 4th Avenue, Suite 31
Anchorage, Alaska 99501
1\GENDA:
1. A discussion and outlining of the purpose and objectives of the
Susitna Hydro Steering Conm1ittec.
3.
·i .
A review by Acres An1erican of the procedural aspects of the FERC
license application, the ES review processes, and their perspectives
on the procedural mileposts for this project.
A discussion of the proposed FERC license a~plication and ES review
process by the Steering Committ12e and an assessr:11:nt of the ugencies
vie•..;s and mandates to review and co1;ment upon tt1e rroposcd project.
A revie\v of the S.usitna Hydro fcusibility lusks by ,\crc~s ;\r:1crican
with discussion of FERC's possible requirements for study, technical
standards, and land or environmental study subJects l'lhich must be
er.1pha sized.
5. A discussion by the Steering Conm1ittce of the cross study task or
interdisciplinary aspects of the Susitna llyJro feasibility studies.
6. Steering Comnittee discussion of a proposed agenda for the July
meeting involving representatives of FERC.
·:·~,.··~ -
...
-
-
...
..
-
-
-
-
-
-
....
...
-
-
-
-
-
...
s :i _ _L_
-· \' · .... ..,
-=>-::tcr.-e
5 '"".::/ s I'
~:~L
S rr -:l S V'\
~ I 't ...
·. ' .... .'\ --///.? ·o 5?Fu?·'l-'
'
L.-:' -.. ~-·. '
' .l.-?~~ '/r~/~~// /? --/
r.· : '
·"'7),· .·
!f.../,'1 ...
' . '
l
l
....
-
-
-
e
t4r. Ron Corso
Federal Energy Regulntory Commfss1on
400 1st Street, H.V.
\Jush1ngton, 0. C. 20427
Dear Mr. Corso:
-
June 13. 1980
Pursuant to prev1ous d1scuss1on 1;1ith Hr. Quinton Edson. we request FERC
presence 1n Anchorage to discuss various 1icensing aspects of the Sus1tna
Hydroelectdc Project. Th1s v1s1t could be 1n conjunct1on with your staff's
plans for vfs1ting the. Tyee lake site.
The need for the meet1ng fs evfdenced by the strong ur~1ng for such a
sess1on by the state and federal agencies who hnve an interest in the project.
It 1s the consensus of all involved that a face-to-face meeting w1th FERC is
needed at th1s early stage of the study process to insure that proper work
effort 1s planned especially 1n the env1ronmenta1 and fisheries programs.
The ~eeting ~111 constitute the second convening of the Susitna Interagency
Stecr1ng Cor.mt1ttee. Acres American wi11 be represented and prepared to discuss
the f1sher1es and 1n-stream flow study programs 1n deta1l. In our opinion,
the t 11:11 ng for a ~::eet i ng ~Hh your staff 1 s 1dea 1.
\ic wuld 1H.e to plan on a two-day sess1on either before or after your
st~ff's v1s1t to Tyee lake. ~e a~ait your response and recommended meeting
dates. ~e w111 ndjust to your scheduie.
Th~nk you for your cont1nued assistance 1n gu1ding us at this early but
cr1t1ca1 stage of project plann1ng.
Sincerely,
FOR THE EXECUTIVE DIRECTOR
Robert f\. 14ohn
Director of Eng1neer1ng
cc: John Lawrence
Concur:
EPY ---T J~·1 t .. ---
···' ' . ...
-
....
...
..
-
...
-..
...
-..
-
-
...
-
JAY S.HAMMOND,Governor
.-- --'-
June 17.1980
•~~[~~~(W ~
OFFICII!OF TAil 60VIlR:'i'OR
DIVISION O f POLlCY DEVELOPMENT AND PLANNING
Mr .Er ic P.Yo uld
Execut ive Direc tor
Al aska Power .uthor t ty
333 We st 4th Avenue,Suite 31
Anc horage.Alaska 9950 1
Dear M r .::\~~Ul d :..'
!,
•/
POUC H A D
JUN EA U,A LA SKA 99 8 "
PHONE :465 ·35/2
f-'RECEIVED
?)111JUN 2 0 19 80
WSf..A poWER AUTHORI TY
I,
Th ank you fo r t he not i fic ati on re gardi ng t he f orm a tion of a Susi tna
Hydro el ect ri c Steering Comm i t t ee . As you kn ow Divi si on of Po li cy
Devel opmen t a nd Planni ng (DPDP)has an i nteres t in t he many fa cets and
imp l ica ti ons of a pr ojec t l ike t he proposed Susi t na Hydroele ct ric Proj ect.
I apprecia te t he oppo rtu nity to be i nvolv ed wi th the re source ma nageme nt
conce r ns t hr ou gh pa rtici pa tion on t he Stee ring Com mit tee .
As t he Off ic e of Co as ta l Ma nagem ent (OCM) has the most j i r ect re s our ce
manaqera ent re sponsibil iti es within OPDP .lam r equ est i ng ocr-I be t hi s
ag ency 's r epresentat ive on t he St ee r i ng Com mittee.
I bel i eve OCM wi l l be able t o keep you i nf ormed abou t the cas t a 1 managem e nt
consistency proce ss a nd how it mi ght effect th e Susi t na Proj ect .Murr ay
Wa lsh ,Co or dinat or of OC M and Bi l l Ross ,De put y Co or di nator,wi l l be th e
c ontact persons fo r OCM/DPOP.As t elephoned t o you r office on J une 10, 1980 ,
no one wa s able t o attend th e f i rst meeti ng of th e Ste eri ng Comm i t t ee but I
as k th at you keep OeM i nfo rm ed of any s ubsequ ent meet i ngs .
Thank you for your i nvi tati on t o DPO P t o be d member of t he St ee r ing
Comm t ttee.
Si nc[re1r .
e ,M,
Fran Ulm er
Di rector
c c;Mur ray ~a l s h ,OCM
-.~
•
Mr. Lee A. Wyatt
Planning Dieector
Matanuska-Susitna Borough
Box B
Plarner~ Alaska 99645
Dear Mr. Wyatt:
•
July 7, 1980
The A 1 ask a Power Authority, acting on beha l f of the resource
management agencies, would lfke to inform you of the second Susitna
Hydro Steering Committee meeting. At the request of the various agencies,
we have rr.a/" arrange:ll"tents for representatives of the Federa 1 Energy
Regulatory ~ommission to be present at the meeting 1n order to answer
technical questions. The subject of the first day of thfs two day
session w11l consist of a discussion of the general technical aspects of
the FERC and state licensing process whereas the second day w111 specifically
address the Susitna fisheries and fn-stream flm'l studies programs.
In additfon to the above topics. an election of a committee chairman
wiH take place (please be thinking of prospective candidates for nomination}.
and the guidelines for the committee 1 s organization will be established.
The first days session of the second Susitna Hydro Steering Committee
meeting will be held at the ACC Lucy Cuddy Center on July 17th at 3:00 a.m.
The second day•s session will be held at the Federal eui1ding, Room C-105
on July 18th at B:30 a.m. Attached is a sheet w1th a description of the
meeting agenda. Your participation is encouraged.
Attachment
Concur:
EPY
TJM~
RA~1--r,-
~
Sincerely.
Erie P. Youl d
Execut1ve D1rector
Additional identical letters sent to the following people (see attached
1ist):
/
(n!')?):;77.761\\
(:IOl)2(6·2715
"l\I~J.\Slil\1~~)\,rnSUi l\~J'I'Dn~pn~~ri'l{,;/
j ....
Jf'
~w£sr .""AVE"U,.SUITE )1
-J'
july J,lC)HO
'"'"'Mr.Ronald Morris
National Harlnc Fis!ll'I"Y SCl'vice
70'\"e"Street
Anchorage,Alaska 99513
Dc~r Mr.Morris:
The i\laska flowC'!"!\uthority,ileting on [JVhdl;01 th:i'(";Ol~!'U:
mana Semcllt agencies,"lOuld like to inform you :If \h0.sr.conc:')lISitl~a
Hvdro Steering Committee meeting.i\t the rcqu,·,~~t.of the vd'ious c\(Jcnci(::::,
''"'~hc.ve made arrangements for representatives l)f thc:iede;",l![I;c:r'gy
Eegulatory Commission to be present tit the mecl.ir\(]in oreler to (lnj"lp'r
technical Questions.The subject of the first.dt"of this l\'i()day
s es s ~()n vii lie 0 n sis t 0 f a.dis cvss ion 0 f t h1::9 r.ncr il 1 tr.ch 11 i C (~!1 J S P f:C t s 0 f
the FERC and state licensing process wherells th(~sQcond Oi\j I"lill specifiCr111y
addre5s the Su~itnd f~sher~es and in-stream flOl'i studies progl'illris.
In addition to the above topics,an election of a committee chilirr:io:.;f\
will t a k e pIa ce (p 1 e ase bet h ink i n9 0 f pro s pee ti vee c1 ndid J t e 5 for"no ID ina t ion),
and the guidelines for t:le committee's organization will be est.ablished.
,:110'-,
The first days session of.,the second Susitna dyc1ro Steering Committee:
meet~ng ~ill be held at the~ACC Lucy Cuddy Center on July l7tllat 8:00 a.m.
The secorid day1s session w11t/~e held at the Feder"l building,Room (.·105
on July 18th at 8:30 a.m.'·',Attached is'a sheet ".lith :)desci1ptioil of thf:
meeting~~enda.Your particfp5tion is encouraged.
Sincerely,
L\~~~
Er fer.Yo l:1d
EY.ecutivp.Director
I\t tachment
r
•
Hr. Ron Corso
Federal Energy
Regulatory Commission
400 1st Street. N.W.
~lashington, 0 .C. 20427
July a. 1980
To follow up on the discussions which have transpired over the last
few weeks between members of your staff, Acres American Incorporated,
and the Alaska Power Authority, we have attached a copy of the agenda
for the July 17th and 18th meeting of the Susftna Hydro Steering Committee.
It is our understanding that Mark Robinson and Dean Shumttay of your
staff will be available for th1s meeting, and Hill be able to discuss
those aspects of the licensing process that relate to their area of
expertice. They need not attend the a:oo a.m. to 9:30 a.m. session on
the first day and need not stay for the full duration of the second day.
~e understand that Acres is arranging a field trip to the Susitna River
for them on July 16th.
~!e hope that the attached agenda meets with your app·rova l and look
for\':ard to seeing f.lark and Dean in Anchorage later this month.
Attachment
Cpmcur
EPU{ TJM_J __
Sincerely.
-!
Robert A. r,~ohri
Oirector of Engineering
...
-
-
-
-
-
-
-
-
-
___.
-
-
-
-
-
-
-
-
• •
..\B,..\SiiA I•OWER AlT'I'IIOI{ITl'
MEMO TO: John Lawrence
Project Manager
DATE: July 8, 1980
FROM:
John,
Acres American Incorporated
The Liberty Bank Building
Main at Court
Buffa 1 o, New York / 14202
I I . ~ ~ Donald W. Baxter,
1
P.E. ~
Project Engineer -' ·
Alaska Power Authqri~·~ /_
333 West 4th Aventie, : u Yt~
Anchorage, Alas-kal-· 5~ ·
SUBJECT: Susitna Hydro
Steering Committee
Attached for your information is a copy of a letter sent to Mr. Ronald Morris
of the National Marine Fisheries Service announcing the second Susitna f~dro
Steering Committee meeting. Identical letters were sent to the following
agencies:
U.S. Fish & Wildlife Service, (Bob Bowker)
Department of Fish & Game (The Honorable Ronald 0. Skoog, Commissioner)
Bureau of Land Management, (John Rego, Energy Specialist)
U.S. Geological Survey, (Harry Hulsing, District Chief)
U.S. Heritage Conservation & Recreation Services, (Bill Welch)
Corps of Engineers, (Colonel LeeR. Nunn)
Environmental Protection Agency, (Director)
Department of Natural Resources, (The Honorable Robert E. LeResche,
Commissioner)
Department of Environmental Conservation, (The Honorable
Ernst W. Mueller, Commissioner)
Office of Costal Management, DPDP, (Murray Walsh, Coordinator)
Department of Community and Regional Affairs, (The Honorable
lee McAnerney, Commissioner)
University of Alaska/Arctic Environmental Information and Data
Center, (Dave Hickok, Director)
Matanuska Susitna Borough, (Lee Wyatt, Planning Director)
Division of Economic Enterprise, (Dick Eakins, Direc~or)
This entire effort has been coordinated with members of your staff,
the FERC, and us. The public has been invited to attend the first day's
session and a copy of the associated newspaper advertisement is also
attached.
·(:.' i:•
s r.
r
1'
/
I " " AL.:\SiiA PO\VI~U .\(T'J'IIOI~I'I'l'
We feel optimistic that as a result of this meeting many of the
questions that have arisen among the various resource management agencies
will be answered. Hopefully a clearer definition of the course of
action to be taken with respect to the in-stream flow studies program will also be obtained.
cc:
Jim Gill
John Hayden
Kevin Young
...
...
....
..
-
-
...
-..
...
..
-
-..
-
-
-
-
....
-·
-
·_1 -1~ -~1
'i
...,.
-
-
-
-
-
-
-
-
,, .. .,.. > ..,
l s t Da v
Date:
Time:
a e -.\1."\Sii.\ PO\l'ED~ Al:TUOHITl'
SUSITNA·HYDRO STEERING COMMITTEE MEETING
July 17, 1980
8:00 J.m.
Place: ACC Lucy Cuddy Center
2nd Oa y
Date:
Time:
July 18, 1080
8:30 a .rn.
PlacQ: r c d e r a l i1 u i 1 d i n g , R o om C - l 0 5
I;G[ llOA
1st Day Topics
~:00 a.m. -9:30a.m.
o Election of a committee chairman
o Discussion of the committee's organization
o Any other items of concern
9:30a.m. -5:00p.m.
o General technical overview of FERC licensing process
o Discussion of general technical license requirements
for hyroelectric projects (both FERC and State)
a Discussion of Susitna specific technical license
requirements (both FERC and State)
Zr1J Gay Topics
8:30a.m. -5:00p.m.
a Potential changes in Susitna River hydrology due to
hydroelectric development
o Details of hydrology-water quality monitoring program
a Details of the ADF~G fisheries program
o Development of fisheries impact predictions and mitigation
plan
o 1·1odifications incorporated into the study program in order
to accomodate the in-stream flow studies
e Discussion of details on in-stream flow studies
~-~
-~-"-
e 411)
SUSITNA HYDRO STEERING COMMITTEE MEETING
July 17th & 18th, 1980
Al Carson
Bob Lamke
Bill Hilson
Bil1 Welch
Pat Beckley
John Rego
Bob Bowker
Rickki Fowler
Gary Stackhouse
Lee Wyatt
Jim Sweeney
Heinz Noonan
Dave Sturdevant
Dick Eakins
1•1urray Walsh
larry Kimba 11
PERSONS NOTIFIED OF THE MEETING
Department of Natural Resources
U.S.G.S. -W.R.D.
AEIDC-University of Alaska
Heritage Conservation & Rec.
BLM
BLM
U.S. Fish & Wildlife
Environmental Conservation
U.S. Fish & Wildlife Service
Mat-Su Borough
Environmental Protection Agency (US)
Energy & Power Development
Environmental Conservation
Div. of Economic Enterprise
(send twix via 277-1936)
Office of Coastal Management
Comm. & R~g. Affairs (Div. of Comm. Plann1ng;
279-5577
271-4138
279-4523
277-1666
344-9661
B44-9661
271-4575
274-5527
276-3800
745-4801
271-5083
276-0508
465-2636
465-2018
465-3540
279-8636
...
...
...
....
....
...
...
....
...
...
-
-
...
...
-
-
-
-
-
J ' ~ ...,_ : ! . . , \ \ r i
--1 1 -._; '--: l ~-1 .:) '__) ,) '·....,'' ; -' : . t
\ • J ~
•_.../ I
I )'. \ ' ~; -.. .I --2 ~ i l. _l } ~ ' \ ---•, ' -
900S-·\t2
-<.,"~~t)~ '"'-0~-~--'S'b\o :r\1 ">4
"'"'~' ws ~~~a 2. n '! 0 3 'f:) J \ ol::.
1 )\I'IV-"5 ~ \~\)\,~~ 1':-'1~\} 't'~'~'\"''14.-
~C.l ~ , ,,b -I; h[·
\
\
. \
c3oa~ Jl(~ o(
-.f\ "<
fO..Sbb ·~\jb)U\j
i , ~~ ~ ~~rr~ St:~ LLsS-hL t'
~~ . :It}~~--~
CJi' j.,~~ £<f..<Z-I ~_5o -~/r~
I
\
,. . " ·.' ' .
r?4tf /'f~ .1 \?W"'tf ~ l_ 2:
. b¥'1!1 L.,..,>I?W
'il8bb" ~bt 1 ~N~s-
( n.iff9 I ¥\r.ll.' t.e'2f I ~'4-\(~ '"f+t">OS J
L '2 .. fS-hL t' 'V') ("') O:J ~ l( .'7..1
:. ---.._,_·\~~·~ ... ' .....
·, . i --
.....-; .. .........
), . : ......_
-
0 ~f'nnd
~ ~vrti"V..IJ)
C) f. f:J '--59 h t ~"'0 t'\ ~ ~ s ,..,., "'(J r-+~ '-'!> ~ l.( > · f Jro
c · ,..--r,::~.~r-.'/(' :JX f/
.-J.(t/ .J. '/Yl; rrL , ;..-/v fll ·-u
/'7•
r· ... ~... . ' .~ / .. ..:::.... . ; ._ ... I 1 .....
,_./.:,...--;~ .. -:-/'/;-/
/ ~_ ..
c~., .... .3 1,~")::>
_., ~51'(") I 1'9.
-
·s \"'~
( 7J tt ) l? ) ---"r' "? ~-A" .. tr ,,. ....... ., ~~ -4 lr\o'tA.. .-.. :J ....... .I
-
J "'..(~ ...... "·~-/(' .. .J '.'·f'"' fl -
-
-
-
-
-:
-·
-
....
-_r::csL-rss (9JL)
,... ).. /V I' Q1b'::jdf'E_
.JJ -:r.!la..t s. .L. '1,.. ~ ...LV' f'l/ ww
OQb JU'ns
,., (Y/C"?, "l: ;;JI f'l b' fl.. )d .. "tt:?> e1 7
... ::;, r' o I' d.. · cr r-J 17 5 .s'J:I '2.100{1
-1 -e
~.L.?;:,~~ J.' !.\.!:a 'tti
( :J :Jf\1 'JJ'IJ(1 ") • G:_ f"HI l
-
-
-
~
Mme e
LJ?'~ g/7~
!?of; /~?~;/~e
t<' i l L ~ LAC.. 't' UO..'"'-J
b 0 ''"' (1\ c. \<',c\
---;;;:::._ ~s
f\J C C{ r s~ """'-
0 '-~; . , ,__\ -' .. I
~ 1 • ~ 1 '\ _ .----.r -(~
~ }\!
-
-
-
-
-
-
-
Dat.r<. s~~
.A/ ' .... --/ ~-...:.,.. ----;v_..,_. {)c~..,.. ' _, . I __., I -~ '\
:[ N\""",K R.o~t.I\.S.a,)
Dt2iP•• L . 2£~
\_);,.:ed~
Zob K!foc.seJJc.
C._:;c.0~ y ,5-r Ji-r:;-If ho l--'SC--
-g_!t:; W L {/J A }1-1-i
·t;':K~-p s \"\ \\~
~j" '1?0 (.)
II~~
/_
--:::·_.· ! -/1 .. ··.r"/-·
--I .
j I ll'\ ~f._.~/\10 fY'A IV
LOYQM kkr
L.; ~-=.._ ·. \,, ...,.. \.'
_;.:.
'\ '--i.... •'-: i~~l
···-----
4 ~;,1-,7/?7 /Bb
(!IV-CJ;V/-e~ Q1"\~ hCJ
:: :;::> .....
/.::7.0 //
/7/ /7
-_.-(. :/._.
11 ~::-:rj) (
L\,.S F \A.).:;,
,;.~-r-G
tJN~
·~I -. -. -' •\" c..__ .... : I '
I ·,~ 'I •. _/' ~
ADEC
.AA-J:
fEI?.L
F6!Zc_
Te:S
TE5
us FtJS
\E"j
1--, M V"S
QSLm
-/~~'h.~ \
/, I /! I /':' -/ ;-·? <' • ' ( . /I. ·' ;' /' . /' ,
{_A_ (_)! A
~/Cf-5S1/
4br--L636
(7 ~~) 853-75JS"
202/"37f.D-90f.(:
:;J..Ol.-:5719-J 90S
bq5"-7 Z--Z-0
?>i'i ;.g'"~-::· .:=·==-="1--~
J.7C.-SOS7'
cl'J&,-39CO
&!:s1 I &5 -~--t5(13
'2-i l-soot;
3-iY 9to(o'
;2~/ -'+2-q.+ j ,.. '
-·) -v' ,, ,',., /
/ ~ :" (. --
A_c:~G"S A!Yl~Rt(;:JN :1/0-4~88
,--Cer~. ol &:J;nr?~Y> 7.~.&-~<1-b'~
j, -, ·"-1 , , -. c_. 1 c' , , \ \ Ct ._ ) __ I i..::.' · l 'l '-t-4-
i'c~:''-·--~<.~_-.:_,,.,n,er...:.c, Ucu\-:'Jtr..>l'r't,_,,,l~-J{P"-, ......... \·)· D<..\.\:'.!,Jpr·•1c-t.d--"') 70 -C._..,S-C·~C~
fill,-_______ !i!III!IIPIIIII! __ !JII!!!IIl_ Rll!ll!!!!~!ll!lllllll------------.;_------,_
2nd Day
Date:
Time:
e e
ALASiiA POWER AUTIIORITY
SUS ITNA HYDRO STEERING C0~1MITTEE r1EETTNG
July 18, 1980
8:30 AM
Place: Federal Building, Room C-105
AGENDA
2nd Day Topics
8:30a.m. -5:00 p.m.
• Potential changes in Susitna River hydrology due to
hydroelectric development
• Details of hydrology -water quality monitoring program
• Details of the ADF&G fisheries program
• Development of fisheries impact predictions and mitigation
plan
t Modifications incorporated into the study program in order
to accomodate the in-stream flow studies
• Discussion of details on in-stream flow studies
..
....
-
...
-
...
..
wi
..
...
-
-
-
-
-
-
...
-
--
~;(,~~w, .. ,~~· -"--~------_;]t t-'" ~-'---
~ ~;---.. ~-~-~~. -~-
............
--~ ...
~-;.~;c: :../ C_..-~ , ,.J •• i /
Cj~#
t}NO
"J'dl=t:i.
~~3=:1
?t!-7-d
-... I l !
L'l :; c:r
I
Y'IPtT//~?/
l.-7J?-TOI?/)j •/')7 tt-T/'?-1
~:;,_ \· _; ·--:· : / ' ,. • /-' /(---f V "-I
~ I ' --·. _-\ - ' J
f!Yr1A/ ~ 2£:.7~7od
1-LL\ UJS Cl\!~'23.
~-., \..ui 'v..i ~
) :ycu XJ 7 q c..?.;J
' v
.... ~?/· --:··.-~ ___ ~; ~~~--~1/ ~:
08/?1/L-
.;;W"-7 '"'~0fJ <?1"71 Ovt.5//r--
W' _)
---------
...,
I
l
l
l
"'""
' l
l
l
l
J
l
l
. l
....,
l
l
l
l
l
l
l
""'--
U.S. ENYIR&MENTAL PROTECTION AeeNCY
REPLY TO
ATTN OF:
Mr. Eric P. Yould
Executive Director
Alaska Power Authority
ALASKA OPERATIONS OFFICE
Room E535, Federal Building
701 C Street
Anchorage, Alaska 99501
16 JUL i980
333 West 4th Avenue, Suite 31
Anchorage, Alaska 99501
Dear Mr. Yould:
RECE:{.VeQ·
JUL 1 .. 1980 ~
Al.ASKA POWER AUTHo~
The Alaska Operations Office has scheduled a retreat with the Alaska,
Department of Environmental Conservation staff and will be unable to
have an individual from our staff attend the Susitna Hydro Steering
Committee meeting. We are very interested in the project and sorry we
are unable to attend.
Please notify our office of the next scheduled meeting and send, if
available, the minutes of the July 17 and 18 sessions.
)
-
Mr. W. James Sweeney, Director
U.S. Environmental Protection
Agency
Room E535, Federal Building
701 "C" Street
Anchorage, Alaska 99501
Dear ~1r. S\'leeny:
July 28, 1980
Thank you for your letter regarding the Susitna Hydro Steering
Committee meeting of July 17 and 18. I am sorry to hear you ~Jere
unable to attend as it was a very informative meeting. The Steering
Committee has, as a result of the meeting. evol'led into an organization
independent of the Power Authority and acting in a review and advisory
capacity to the Power Authority. It is now run wholly by the various
State and Federal agencies. Al Carson of the Alaska Department of
natural Resources has taken the responsibility of chairman for the
cor.~ittee and Tom Trent of the Alaska Department of Fish and Game is
acting as his assistant. I will see to 1t that your agency is retained
on the mailing 1 ist for the committee. Unfortunately, no meeting minutes
r:ere taken although a tape recording is ava11able at the Power i\uthority.
I appreciate your continued interest in the committee and encourage
your participation at future meetings.
Eric P. Yould
Executive Director
Alaska Power Authority
333 West 4th Avenue
Suite 31
Anchorage, Alaska 99503
Attention: Eric Yould
RECEPIEQ
,·. •: .: '\'WQ
• • . ~~ ~-~. •. 1 • ) l..;
/.J..ASKA POWl:::! AUIHORlTY!
August 21 , 1980
P5700 .11
T.375
Dear Eric: Susitna Hydroelectric Project
Distribution of TES Procedures
Manuals
Enclosed please find copies of the TES Procedure Manuals as requested
by yourselves and the Susitna Steering Committee. A distribution list
is attached.
Since Mr. Al Carson, Chairman of the Steering Committee is out of town
until August 27, the distribution list for the committee is based on
the key contact list as supplied by Don Baxter on July 18, 1980. Please
advise if any changes are made in distribution.
KY:pg
Enclosures
Sincerely,
\'
J. D. Lawrence
Project Manager
-
...
...
-
-
-
-
-
-
•
•
•
•
•
DISTRIBUTION:
Copies of all procedure manuals to:
APA -E. Yould, R. Mohn
USF&W -Don McKay
DEC -Dave Sturdevant
ADF&G -Tom Trent
ADNR -Al Carson
BLM -John Rego
AEIDC -Chuck Evans
Copies of Fisheries Manual:
NMFS -81 ad Smith
Copies of Manuals for Subtasks 7.05, 7.06, 7.07 & 7.08:
HCRS -Larry Wright
~--_,_ ----r---~---------~--•• ~ --~---~
MEMORA"DUM • State of Alaska
TO:
FROM:
DEPARTMENT OF NATURAL RESOURCES
DIVISION OF RESEARCH & DEVELOPMENT
SUSITNA HYDRO ELECTRIC
STEERING COMMITTEE }ffiMBERS
(See Distribution List)
DATE.
FILE NO
TELEPHONE NO
-·· --. ' ,..... ~
h. l:: G r.; I V L [)SUBJECT
Steering Committee Chairman
TI1e purpose of this letter is two-fold:
September 4, 1980
279-5577
Summary of 7/17
and 18 Meetings
and Review of
Procedures Manuals
1. To summarize the major points discussed in the July 17 & 18
meeting of the Susitna Hydro Electric Steering Committee.
2. To transmit to you copies of the Acres American contractor's
field manuals which describe in detail how they will conduct
studies during the 1980 and 1981 field season.
The first item of business on July 17 was discussions and decisions
leading to the appointment of a chairman. Those in attendance
agreed that Al Carson, Department of Natural Resources, would serve
as chairman of the Steering Committee with Tom Trent, Department of
Fish and Game, serving as Assistant Chairman. There were two
representatives from the Federal Energy Regulatory Commission
(FERC), Mr. Dean Shumway and Mark Robinson. A considerable amount
of time was spent by Messrs. Shumway and Robertson explaining the
role of FERC in the proposed Susitna Hydro Electric Project. The
rest of the morning meeting was devoted to contractor briefings
about the studies included under Task VII (environmental studies)
for the Susitna plan of study. Two significant items were identified
by this review. First, it was obvious from the comments from the
agency representatives, contractors, and subcontractors present
that the agencies were unable to provide a detailed critique of the
plan of study. This is because the widely circulated plan of study
did not have adequate detail regarding methodology, approach, or
scope of the proposed studies to enable the reviewer to make reasoned
or useful comments on these matters. Acres American and their
subcontractors stated that this level of detail would be found in
their yet to be published field manuals which describe in detail
the work that the contractors will be doing in the 1980 and 1981
field seasons. The Steering Committee members will be provided
with copies of these field manuals for their review when they are
available. The significance of this is that the studies that are
being accomplished under the Susitna plan of study for the field
year of 1980 are being carried out without benefit of review,
comments, or approval by the various state and federal agencies.
Second, was a concern regarding how the socio-economic studies
being conducted under the Susitna plan of study related to the fish
02 ·00 1 A( Rev.! 0/19)
..
-
-
-
..
•
•
•
;'P"«<ii"T lj e . Susitna Hydro. __ ctr~c ... 2 • ,_,September 4, 1980
and game impact concerns identified by agency representatives. It
was agreed that the Steering Committee will meet with the socio
economic consultants to learn how these studies relate.
The meeting on July 18 was devoted exclusively to reviewing in
detail and discussing the studies that are necessary in the FERC
filing concerning fisheries, hydrology, and instrearn flow. The
most significant issue which appeared from these discussions was
the need to insure that mitigation for fish, wildlife and other
environmental values are integrated into the project designs, etc.
rather than being an add-on or appendage at a later date.
The second purpose of this letter concerns review of the field
manuals. Accompanying to this letter you will find copies of the
field manuals to be used by the Acres American subcontractors for
carrying out various studies as discussed in a general way within
the Susitna plan of study documents. Please carefully review these
manuals giving proper emphasis to those studies which are included
within your field of expertise and your agency's authority and
responsibility. The intent is to have alL the Steering Committee
members review these manuals and forward your review comments to
me. I will then synthesize these comments into a draft letter from
the Steering Committee to APA. Then we will meet to review and
finalize the letter. For the sake of convenience and saving time
in synthesizing comments, please place your comments and concerns
within the appropriate framework as discussed here: The review of
the field manuals is intended to detail problems or concerns within
the following six areas:
1. Hhat is the appropriateness and utility of the studies, i.e.,
do the studies attempt to answer the questions that need
answering in light of the proposed Susitna Dam?
2. The scope of the studies, i.e., is the methodology approach
and techniques properly formulated to provide valid and germane
answer(s) which will apply directly to the proposed Susitna
Dam?
3. The study approach and methodology, i.e., does the approach
and methodology discussed in the manuals result in findings
and recommendations which are or will be scientifically valid?
4. H01.; do the subtasks of the studies "hang together" to give a
comprehensive picture of the impact of the project?
5. llow do the various disciplines (e.g., fisheries, seismology,
engineering, recreation) study findings and recommendations
affect the other disciplines? The answer to this question
1vill identify the hierarchy of values that will be attached to
various components of the project when the "trade offs" decisions
are made.
--"-,·, ~/
·-~ ... Susitna Hydro f,l,_ectric • ...
3 September 4, 1980 •
6. wnat other issues and concerns did you discover while reviewing
these manuals that need the attention of the Steering Committee?
Please provide me your writ ten reviet.; comments no later than close
of business, Friday, September 26, 1980. If you have questions,
comments or revisions on the matters discussed in this letter,
please contact me at 279-5577.
cc: E. Yould, APA
Distribution List
Don McKay
U. S. Fish and Wildlife Service
733 W. 4th, Suite 101
Anchorage, AK 99501
Tom Trent
Alaska Dept. of Fish and Game
333 Raspberry Road
Anchorage, AK 99502
Al Carson
Alaska Dept. of Natural Resources
323 E. 4th Avenue
Anchorage, AK 99501
John Rego
Bureau of Land Management
Anchorage Di~trict Office
4700 E. 72nd ·Avenue
Anchorage, AK 99502
Bob Lamke
U.S. Geological Survey
\~ater Resources
733 West 4th Avenue, Suite 400
Anchorage, AK 99501
Bill Wilson or Chuck Evans
Arctic Environmental Information
and Data Center (U of AK)
707 "A" Street
Anchorage, AK 99501
•
•
•
•
II
•
•
I
Susitna Hydro 4t)ctric
~
Dave Sturdevant
4
Department of Environmental Conservation
Pouch "O"
Juneau, AK 99811
Larry Wright or Bill Welch
Heritage Conservation and Recreation Service
lOll East Tudor Road, Suite 297
Anchorage, AK 99503
Brad Smith or Ron Morris
National Harine Fisheries Service
701 "C" Street, Box 43
Anchorage, AK 99513
41teptember 4, 1980
' --...... .
'~
--·-:~,;:_~~-. .. ~ -:-::-;;_ .... • .. "LASKA PrnER AIJrHORITY
Susitna Hydro Steering Ccmnittee
c/o Al Cars en
Alaska Depart:rielt of I~atuml Resources
323 East 4th Avenue
.Anchorage, Alaska 99501
Dear Al:
--
Septedber 3, 1980
Last~ we fm:warded to you for distrl.but:ioo. to the Susit::na
Hydro St:erring Coo.nrl..ttee. copies of the ernr.irOI'li!E'ltal procedures nmruals
applicable to POS Task 7, as prepared by Terrestrial&~
Specialists. Inc. (TES) . These manuals should answer many of the questions
relating to the details of our Plan of Study. tore ~d appreciate it if
yOJJ: ca:mittee would review and camBlt en these manuals at its earliest
convenience. He will then prepm:e written responses to in..y canrents re-
ceived. If in follcw.ing dds process there are still outstanding questions
that require detailed teclxrlcal responses, ~·Je ~·till be pleased to have
the appropriate prir.clpal investigators make a presentation to your camrl.ttee.
T.E.S. wishes to maintain positi~ c.ootrol aver t.lwse m:muals, and
\,;c ~ul.d like to faci 1 i tate that wish. The attache!d forms mip,ht be use-
ful to you tcMards that goal. .
Trusting this procedure rooets with your approval.
FOR 'lliE EXEaJITVE DIBECTClt
cc: J. Lawrence
J. Gill
Enclosures: As stated
IJJ:et
CDNCUR:
EPY· ) ~\~
TJM: v/
00:
Sincerely,
Robert A. Hohn
Director of F.ngir.eerlng
-
...
....
--
...
-
--
...
...
..
-
--..
-
-
.,;
,.
-
-
-
-
-
~-.·~)' ;_~1:·;·6~.~-, ,_
-~.:.·~··
:!!'-
.:~:~ .
i · ..
SUBTASK
7.05
7.06
7.07
7.08
7.10
7.11
7.11
7.11
7.12
7.14
-e,
ALASKA POWER AUTHORITY
RECORD OF RECEIPT OF
ENVIRONMENTAL PROCEDURE MANUALS
COPIES ASSIGNED TO -------
TITLE
Socioeconomic Ana 1 ys is ........................... .
Cultural Resources Investigation ................. .
Land Use Analysis ................................ .
Recreation Planning .............................. .
Fish Ecology-Impact Assessment and Mitigation ...
Wildlife Ecology-Furbearers .................... .
Wildlife Ecology-Big Game Impact Assessment
and Mitigation ................................... .
Wildlife Ecology-Birds and Non-Game Mammals .....
Plant Ecology .................... -...... ·. ·. · · · · · ·
Access Road Analysis ............................. .
COPY #
-
-
-
-
-
-
J-COPY
.... SUSITNA STEERING COMMITTEE ~
Record Of Distribution Of
Environmental Procedure Manuals
SUB-COPY
K TITLE " RECIPIENT TASK TITLE il -. -~ -. IT
JS sacra-
ECONOMIC
ANALYSIS
)6 CULTURAL
RESOURCES
INVEST!-
GATIONS
J7 LAND USE
ANALYSIS
JS RECREATION
PLANNING
.0 Fi~:-i i:COL-
OG"y !i4P:;CT
ASSESSMeNT
:\NO
M!TIGATIOII
PLA;1N ING
;o
!l.
113
/4-
I ;c,
/<7
;_j_
21
2?
9
/0
/Z
/4-
;')
L~
1'7
18
11
/0
Jl
IZ..
1<1-
~~
1'7
;'f
i 21
lzz
!0
!Z.
13
14
;)"'
/~
17 1/B
12~ I
/I I
/Z, i
/3
14 I
i /)!
' I /d
' I
co . .c·_.: .. · ;?(",,) (~ ,.,..~~. ~A··1A.A•'0'~·~j
!
I 7.11 YJILDLI FE
ECOLOGY
-FURBEARERS
7.11 WILDLIFE
ECOLOGY -
BIG GAME
IMPACT
ASSESSMENT
AND MITI-
GATTON
PLANNING
I 7 .11 WILDLIFE
ECOLOGY -
l
I
-I
BIRDS AND
NON-GAME
MAMMALS
7.12 PLANT
ECOLOGY
7.14 ,JCCESS
ROAD
MIAL '!3 :s
I J /
;z
n
14-
;)
!&
!9 z;
zz
q
!0
;2.-
/3
;r'
/~
I?
18
Ji
/I
I /Z I . ~~I
t7
l~r I ~~~/I
13
;4-
/)
!C.
17 i
;1
z; !
lz3 I
! )(J i ,24
:/r!
~
" ' I -1 I
12 "!.-t
i -z. ~ I
' l z·?--'
; ,: <:' '
,.2G I
;~~/;.~,:.:-t::· ,_.j:.< > .,.4.7~'
RECIPIENT
-
-
~
,._
-
.....-
......
-
.......
._.
!
l """''r.,ll '1 'l j i1
\ .,J :, I .0 ' , i i :> I
j -:1 .. , j •· I
_: ~.) .. l~~}J l
... ;·0;
~. '\ :' . ;
.-·"
n ~ c; C.:: IV ED October 23, 1980
OCT 30 1980
'J.j.ASKA PCWE.:<. A0iHORITY
Susitna Hydroelectric Project
Meeting with Susitna Hydroelectric
Steering Committee
Dear Member of the Susitna Steering Committee:
A meeting has been arranged for the afternoon of November 5, 1980 where
we will have an opportunity to discuss some of the preliminary aspects
of our planning studies. To promote as productive a meeting as possible,
I have enclosed information we have developed to date. As this information
is in a preliminary form I expect that some inconsistency exists.
However, I feel your input can be best utilized at this early stage
when concerns and recommendations can be easily incorporated.
I encourage your constructive criticism and would appreciate it if you
would jot your ideas down on the enclosed forms prior to our meeting.
I look forNard to seeing you on November 5.
Sincerely, /1/: ~ :./, /) fi ·";n_... ---:· < -:::.::._~0 . //-~c:::-"~
Kevin YoungC 0
Environmental Coordinator
ACRES AMERICAN INCORPORATED
,-:: . .;n3ur;1ng ::1.;pr.eers
-...,e _!:Jerty 3ank au~la,r<;. \ia.1n .;;: Court
3u;:a!o Ne~.v ~crk 1.!2 1J2
~~~e:J~c~e ?:-:5·353-7525 T -:-~B:< 3 ·~ --3.:.23 ~.CMES 3UF
e
~u~u~ @~ m~m~~m
UEI•.\UT~IENT 01• ~ATIJH.~I. UJ<:Sf)(Jilf:Es
DIVISION OF RESEARCH & DEVELOPMENT
~ovember 21, 1980
Eric Yould nr:C~IVED
-I /A r i HAIIIIOIID. GOYflltOI
323 E. 4TH A VENUE
ANOtORAGE, ALASKA 99501
2 79-5577
Executive Director
Alaska Power Authority ; \OV 2 i;, 1980
333 W. 4th Avenue, Suite 31
Anchorage, AK 99501
Dear Mr. Yould:
AU.':.::i'' PC'N".:..: r-. .J • .-. ...., .. lTY
The purpose of thls letter is to provide you with the Susitna Hydro
Steering Committee review comments regarding the procedures manuals
which d~scrlbe the Task 7 studies being done under the contract between
APA and Acres American. As you know the Susitna Hydro Steering Committee
is composed of representatives from state and federal agencies and the
University of Alaska. Function of this committee is to provide co~rdinated
exchanges of information between APA and the interested resource
management agencies.
The Steering Committee met with representatives from Acres American
and its subcontractors on July 17 and 18, 1980. The purpose of thls
meeting was to review the environmental studies portion of the contract
with Acres American and their subcontractors. It soon became apparent
that the subcontractors were unable to provide the Steering Committee
members with an adequate level of detail concerning the scope and
methodology which would be used to carry these studies out. The Acres
American representative stated that the level of detail that we were
looking for would be found in their yet to be published procedures
manuals. We agreed that it would be appropriate for Acres American to
provide copies of these procedures manuals to members of the Steering
Committee for their review and comments. The following procedures
manuals were provided by Acres American for our review:
Subtask 7.05 Socioeconomic Analysis
Subtask 7.06 Cultural Resources Investigation
Suhtask 7.07 Land Use Analysis
Subtask 7.08 Recreation Planning
-
-
"""'
-
....-
•
-
-\", ..
...
-
-
-
•
~
-
.,
-
-
~
/ 1/
/
-
-
._
-
-
-
-
-
-
-
-
-
Eric Yould • 2 Nc .. mber 21, 1980
Subtask 7.10 Fish Ecology Impact Assessment and Mitigation Planning
Subtask 7.11 Wildlife Ecology (Big Game Impact Assessment and Mitigation
Planning, Fur Bearers, and Birds and Non-Game Mammals)
Subtask 7.12 Plant Ecology
Subtask 7.14 Access Road Analysis
The following agencies were provided copies of the procedures manuals
and have responded with review comments: Alaska Department of Environmental
Conservation, Alaska Department of Fish and Game, Alaska Department of
Natural Resources, U.S. Geological Survey, National Marine Fishery
Service, Heritage Conservation and Recreation Service, U.S. Fish and
Wildlife Service, and the Arctic Environmental Information and Data
Center. The following is a synthesis of the comments from these
agencies. Appended to this letter are copies of the written comments
which were received from those agencies identified above.
SUBTASK 7.05 SOCIOECONOMIC ANALYSIS
Review of the procedures manuals indicates that this study may not
address the indirect but highly significant impact of construction and
operation of the project on residents living in the region. The boom
that occurred during the construction of the Trans-Alaska Oil Pipeline
(TAPS) gives us an insight into the sorts of impacts that may be
expected. For example, traffic congestion, strip development of small
communities, stores out of necessary goods and materials because of
accelerated demand by construction. In order that the socioeconomic
impact studies may be more comprehensive and address these sorts of
impacts we make the following seven recommendations:
1.
2.
3.
4.
Local and regional recreational facilities and opportunities
should be assessed to determine the ability of those facilities
to handle additional users in light of increased demand.
The study should address the probability of additional
industrialization of the region as a result of power from the
project. Then the study needs to assess the impacts and
socioecomomic implications of industrialization scenarios that
would be driven by this project.
The study should address the cost and availability of products
and services. This should also address the inflationary impacts
that are usually associated with a boom type cyclical expansion
such as construction of a project of this magnitude may cause.
The study should address the cultural opportunities and how they
may be affected in both positive and negative ways by the proposed
project.
·1·,··· ~;;;L
!~· .. ,,
v
···~~
-I \
Eric Yould tJ 3 N~mber 21, 1980
5.
6.
7.
The study needs to address the implications of the project on a
composition of the people who live in the region. An obvious
first step would be to establish baseline survey data in the
preconstruction era so that we know what the population composition
is in this area before construction begins.
An assessment of the changes in the sociopolitical structure of
the region that could be expected result from the change in the
economy as a result of construction an operation and subsequent
developments that would be driven by this project.
The analysis does not address the impacts of.the project on users
of fish and wildlife resources. I refer you here specifically to
memos included in the Department of Fish and Game review submittal
which indicate that Acres and others deemed it inappropriate for
the Department of Fish and Game to carry these studies out.
However, in our review of all the studies identified above we
find that neither Acres American nor any of other of the sub-
contractors have included this important issue in their plan of
work. The scope of the analysis does not include any work designed
to mitigate the project impacts on fish and wildlife.
SUBTASK 7.06 CULTURAL RESOURCES INVESTIGATION
Although this study was not formatted or laid out in a way similar to
the others the review comments indicate that the approach in the scope
and methodology proposed is appropriate and sufficient for the task at
hand.
SUBTASK 7.07 LAND USE ANALYSIS
The following comments were made:
l.
2.
3.
The scope of the land use analysis needs to be expanded so that
the downstream impacts all the way to salt water are adequately
addressed. As an example of a downstream impact which is not
included but needs to be addressed is the issue of navigability
on the Susitna River below the proposed dam.
There is no apparent linkage or coordination between the land use
analysis and the socioeconomic and recreational studies.
APA should seriously reconsider the decision that has been made
to delay future lan~ use analysis. The contractors state that
data from other disciplines may be needed to "fine tune" this
study. However, we can assume most of these values or issues and
get on with one of the most critical studies that could provide
data to be used in making the decision as to whether Susitna
should be built or not. It is recommended that APA consider the
use of scenarios to describe future land use with and without the
project.
-
-
...
,..,
..
...
-
-
-
IIIII
-
.,;
-
-
...
...
-
-
-
·-?
"' -. _/
~~
......
-
-
-
......
-
-
.......
-
Eric Yould ,, 4 NJilmber 21, 1980
A recommended way to begin addressing downstream impacts is to
become informed about the work currently being done in this area
by local, state, and federal agencies. This will help to eliminate
any duplication of work. Once APA is aware of what studies
agencies have done the APA contractors can be tasked to synthesize
the existing studies and complete only additional studies needed
to complete the scenarios.
SUBTASK 7.08 RECREATION PLANNING
1.
2.
Scope of the recreation planning appears to be incomplete. The
total thrust of the study appears to focus on recreational opportunities
in the impoundment area with the obvious underlying assumption
that Susitna Dam will be built. What is absent is any sort of
assessment of the proposed project impacts on existing recreation
navigation and land use in the river valley above, within, and
below the proposed project. There is no question that we have to
carefully plan for reservoir recreation development assuming
there is a project. It is also obvious that the compelling need
that needs to be met today is a valid and accurate determination
of existing recreational values so that this decision can be
factored into the ultimate decision as to whether Susitna should
be built or not. An equally important result would be identification
of those values for mitigation which will be required if the
project is built.
This study needs to include a documentation of the flowing water
resources and uses that would be impacted by the project •
3. This study needs to document the existing upstream uses of Susitna.
SUBTASK 7.10 FISH ECOLOGY IMPACT ASSESSMENT &~D MITIGATION PLANNING
1.
2.
3.
It is acknowledged that none of the reviewers had a comprehensive
picture of how this task will be carried out. The reason is the
Department of Fish and Game will be actually doing much of this
work as a subcontractor to Acres American and has not had the
staff or the resources necessary to put together its procedures
manual for this facet of the work. The comments given below
should be qualified with acknowledgement of this fact.
The contractors need to broaden their scope of mitigation concepts
tha are included in the studies. There are other options available
for mitigation planning above and beyond what is included ln the
procedures manual as it is now written. I refer you to the
detailed comments made by ADF&G.
We recommend that an assessment of effectiveness of mitigation
used on other projects to reduce impacts also be studied before
we determine what sorts of mitigation techniques will be applied
to the proposed Susitna project. The reason for recommending
this is to enhance the probability that the mitigation we apply
to the Susitna project will be successful.
.. ~~·
I I
' .. ,
Eric Youfd \. 5 N~mber 21, 1980
4. Table 2 should be amended to identify the issue of the effect of
the project on rearing, fish passage and egg incubation in the
Susitna River from its mouth upstream to the proposed dam site.
s.
6.
7.
The mitigation alternatives should include a cost benefit analysis
in phase 2.
There is a lack of adequate participation by resource management
agencies in the impact assessment or mitigation planning as
proposed in this procedures manual.
The water quality subtask within this study needs further review
regarding the extent of data required and details about timing of
the data collection.
SUBTASK 7.11 WILDLIFE ECOLOGY
A. Big Game Assessment and Mitigation Planning
1.
2.
This study does not describe the methodology that will be
used for assessing impacts to be mitigated. The procedures
manual discussion of formation of a mitigation team and a
series of meetings and conferences as a methodology is
inadequate.
The scope of mitigation concepts needs to be broadened in
this study. The National Environmental Policy Act (NEPA)
defines mitigation in five different ways:
a. Avoiding impact all together by not taking a certain
action of parts ~f an action.
b. Minimizing impacts by limiting the degree or magnitude
of the action and its implementation.
c. Rectifiying the impact by repairing, rehabilitating, or
restoring the effected environment.
d. Reducing or limiting the impact over time by preservation
and maintenance operations during the life of the
action.
e. Compensating for the impact by replacing or providing
substitute resources for environments.
Since the Sustina project will be subject to an environmental
impact statement the Alaska Power Authority should
assure that the contractors preparing the application
adequately address all aspects of mitigation in order
that the submittal will be adequate for the E.I.S.
------·-·--·------~-------
--
...
-
-
...
..
.....
IIIII
..,
..
-
"""
~
•
....
-
-
...
-
-
-
-
...,.,
-
.: ~·~
~ ,, /I
""''" . . ~ -
Eric You'd \ .•. 6 No~mber 21, 1980
B. Wildlife Ecology -Fur Bearers
1. Scope of these studies needs to be extended to salt water.
2.
3.
4.
The reason is the proposed Susitna hydropower project will
have impacts all the way to salt water.
This manual does not acknowledge the need for mitigation for
these living resources. It is recommended that the procedures
manual be revised to reflect the need for mitigation for fur
bearers.
The manual describes surveys which will be done only in the
winter. The seasonality of this approach will result in
certain data biases and lack of data for the intervening
months.
The studies state that radio collaring of animals will be
done. How will the radio collar data be used?
C. Wildlife Ecology -Birds and Non-game Mammals
1. The scope of these studies needs to extend to salt water.
2. The procedures manual falls to acknowledge the need for
mitigation of birds and non-game animals. It is recommended
that the procedures manuals be revised to reflect this need.
General comments on wildlife ecology procedures manuals.
There is a compelling need to integrate the wildlife and the
plant ecology studies so that the end results are meaningful and
useful to the decisions which will be made. Each of these study
elements should apply appropriate quantitative methodologies to
evaluate animal habitats. The methodology used may depend on the
characteristics of the species or group of species they are
dealing with. Whatever method is adopted, it must be biologically
justifiable and provide a relative estimate of the habitat value
per area unit for the study area.
SUBTASK 7.12 PLANT ECOLOGY
l. The scope of these studies needs to be expanded from the dam site
all the way to salt water. The reason for this is that construction
and operation of the dam will impact vegetation to that extent.
2. There needs to be a high level of integration and coordination
between the plant ecology, hydrology, and the wildlife impact
assessment studies. This is because a great part of the wildlife
impact mitigation will be based on vegetation.
-~r
/.!
/-
/' ---
/'
/
--,
Eric Yould 'II 7 N~mber 21, 1980
3. The definition of wetlands used for classifying habitats should
be compatible with data already collected in the Susltna Basin by
the cooperative study underway with DNR, ADF&G, and SCS. We
recommend that the classification system developed by the U.S.
Fish and Wildlife Service and described in "Classification of
Wetlands and Deep Water Habitats of the United States" (FWS/OBS79/31)
be considered as the wetland classification for these studies.
SUBTASK 7.14 ACCESS ROAD ANALYSIS
l.
2.
3.
The analysis of alternatives does not indicate whether stream
crossings will be reviewed to determine extent of icing and
adverse environmental impact as a result of crossing these streams.
Stream crossing and structures should be designed to avoid creating
icing and erosion problems.
This analysis should include assessing the effects of an increase
in fishing due to newly opened road access as part of its scope
of work.
There is an obvious linkage between access roads for this project
and land use/ fish and wild life studies. Review of the manuals
does not indicate that the appropriate process or mechanism is in
place to see that this occurs.
GENERAL COMMENTS
It is the consensus of the Steering Committee that each study task
procedures manual should include two maps:
1.
2.
A map that delineates the boundaries of the specific study tasks
described in the respective manual.
A second map delineating the overall study area, ie from the
mouth of the Susitna River to the Denali Highway.
SUMMARY
In conclusion, the above comments should be considered as summary
comments designed to flag the most significant and compelling issues
which require correction or rectification in order to assure that the
procedures and approaches used in the studies will yield the answers
necessary to make the most informed and best decision regarding the
proposed Susitna project. The Steering Committee members believe the most
compelling need is for a well-conceived process to improve the linkage
and coordination of the various studies. This is particularly true in
several of these studies where one element is dependent upon findings
of other studies. An example is the need for fisheries impact mitigation
to be built upon the assessment of the existing fishery resources and
the instream flow/hydrology studies. The recognition of the sequential
nature of this process is lacking in the procedures manuals reviewed.
-
-
-
-
...
-
-
-
-
-
""'
-
-
...,
.....
-
-
-
-
-
-
-
-
....... i.
~
~ ~;
~l
~~
---~ ~,
··t
_J f_J.~ .;l
-._J ;.~
\·~
·~·gt!i ···lw 'f·>·wl .. e·• , . ., ------......
Eric Yould e 8 Niltmber 21, 1980
l~e also would like to emphasize the importance of the relationship
between the ultimate design of the procedural manuals and a particular
study product; that product being identification of and development of
mitigation measures for the human and natural resources being studied.
We have recommended several times above that mitigation be added or
broadened in scope on a resource by resource basis. This concern is
based on our collective experience in assessing the adequacy of the
mitigative features of countless environmental statements; they are
often very weak in this critical area. As the mitigation efforts may
be a key to assessing the feasibility of this project and a key to the
success of the environmental statement that may follow, we urge you to
integrate "mitigation" into all systems designed to assess human and
natural resource impacts.
Sincerely,
OJ~
Al Carson
Chairman Susitna Hydro Steering Committee
cc: Steering Committee Members
Reed Stoops
~---...
MEMORAN~UM Statl of Alaska
DEPARTMENT OF NATURAL RESOURCES
DIVISION OF RESEARCH & DEVELOPMENT
TO SUSITNA HYDRO ELECTRIC
STEERING COMMITTEE MEMBERS
(See Distribution List)
DATE: October 29, 1980
FILE NO
QL TELEPHONE NO:
FROM AL CARSON suBJECT November 5, 1980 Meeting
Steering Committee Chairman
There will be a meeting of the Steering Committee at 8:30A.M. on Wednesday,
November 5, 1980 at the University of Alaska Anchorage Campus Center
Executive Conference Room. The Campus Center is located approximately 3
blocks east of the corner of 36th Avenue and Lake Otis off Providence.
Attached is a sketch showing the location of the conference room on the
lower level.
The purpose of this meeting is:
(1) To finalize Steering Committee review comments on the
procedures manuals used by ACRES and their contractors.
(2) To comment upon ACRES approach to identification of
power alternatives in the railbelt. Attached please
find a packet of information for your review before
the meeting.
(3) To identify any other tasks or actions that the members
of the steering committee wish.
The 8:30 A.M. to Noon session will be devoted to items 1 and 3. The 1:00
to 5:00 P.M. session will address item 2.
Please give this meeting your highest priority for 11/5/80. Your partic-
ipation is vital if our effort is to be successful.
DISTRIBUTION LIST
Don McKay
U. S. Fish & Wildlife Service
733 W. 4th Ave., Suite 101
Anchorage, Alaska 99501
Tom Trent
AK Dept. of Fish & Game
333 Raspberry Road
Anchorage, Alaska 99502
John Rego
Bureau of Land Management
Anchorage District Office
4700 E. 72nd Avenue
Anchorage, Alaska 99502
02·00 1 A( Rev.l 0/79)
il..;:..;...:l'/L.:D
OCT 30 1980
f~l<A POWER AUinUklfY
1/
-
-
-
-
-
-
-
-
-
--
...
-
-
-
-
-
-
-
-SUSITNA HYDRO ELECTRIC
STEERING COMMITTEE MEMBERS
DISTRIBUTION LIST CONTINUED
Bob Lamke
U. S. Geological Survey
Water Resources
733 W. 4th Ave., Suite 400
Anchorage, Alaska 99501
Bill Wilson or Chuck Evans
Arctic Environmental Information
and Data Center (U of A)
707 "A" Street
Anchorage, Alaska 99501
Dave Sturdevant
Dept. of Environmental Conservation
Pouch "0"
Juneau, Alas~a 99811
Larry Wright or Bill Welch
Heritage Conservation and
Recreation Service
1011 E. Tudor Road, Suite 297
Anchorage, Alaska 99503
Brad Smith or Ron 'Morris
National Marine Fisheries Service
701 "C" Street, Box 43
Anchorage, Alaska 99513
Attachments
bee: R. Stoops -R&D
D. Wozniak -A.P.A.
e
October 29, 1980
Page 2
r
0
:E
!'T"1
::0
r ,...,
< r1i r
"'f.,.
:;:j E -
I
!' ::
"' z.
•
-rr-u ~
0
L Fl~
:IJl!I[J
...J1
2 ,., ~
<:> :: c > > 'Z.
1\ >
i
-
-
-
-.
.,.. ¥'' m=rrn=r .... , .............. -_ ......... _.;,_.. ··. ,_;_ ... .
·~-~.:·~:~[::}'~?.;}~ ~:-_:f?~:· :~:;:., ~::~.:
' . ·. -··
~-·.~:·~~:<c.:~~;:-~~-~~~··~ .. '
: -. ··-· · ....
.: ... ~-~ ~~:];f!/:·~~~-;~:;.~_Z;~i~:~li.::: :.
r,••,
'. ·.. . .. · .
.. ~ .. ·. .
' : ... _. .. :-.. '. ~ .. :-. . . . . .. .... ' .
-::::-~::' .. :'·~·;.~·· .. -~~~--· ... : .. ~--~
··-: :-.:~. _., ',
....... :-~ .... · .. :~ ~,
1) M(J~
9-1-.::f{}/;1
---!..V
.:;! (/ t
-y ~.::/(] 1/
/Ice i/
~dv
; r r :=n-/ -.... ._--v
\ I
L lSS-bL'
) hSO-n.)_,£
J c::?E -JrL&
;f,sv-}/JF
-zj ?!. -(_ L-c
H/) L -9 ( Z:.
~ ~<p.*-qt.~
:> oas -J t ""2.
_', L _c, I~ -I l \.'
199 f, -lrj, ~
.JJ?b-*
,,
,,,,_t~ f
'l ~ CJ?. -59h
~~~-S~S/} g [Jp-JLZ
r~ ~ ubf~o rytM(S{{ ~
~--
""""0 s-.} ~ J ) \:}
~-~ 8 (;J-:Jr/dQJ..~)~'l:j;)
......u>'J~7?'ry' ~"" ;, -· ; v C>
--'7/?J{/.Y ;?_) I ~f:j/
([yf/(dfl >~/ 7 t>J /) J.. c ~ ~ (!_
;;;y1r1"'Z.oM q <J1t-.VC . .
/.-'..-/C./ .. ' ~/U}I I /·" ... -·. I;.-;;
A~r;r.;;e -L-Vd
f1'12/'3_L5"t;>t ?)flf(
~""-0 1\_1 \.A.&-I \
JH9.'Yr1 )iVY7
f ~ ry·~p..n?-f S on i?([
v~ h ~ o g 1 s f I( ~·w."""~J ~'"'~+& 0-.1\~ ht/
. .............. -~~<----.... ... ---..... ~ ....... "-~·'...;
. -·· ,·· .. ·.. -:
........
. -~.::_.-·"'·~.:~.·.:·· ':. ~-.........
~~f~~~~-;¥~~~-
.... , .... ,. --
-
-
• •• •• --+
C-
,r li . ' . . -. I
. .·t :. , I ----=··;.!:,_ ~.o...l..iior..J ---------. I .
I ., ~T?:"...,
t j·• ,.J .J
I ~· .. ' ·, '>\ , .. ,-4., =~ •
I ,ii''·J:i ;;'! I •·J•~· : .• ..:·;
Mr. Al Carson
Chairman, Susitna Hydro Steering Committee
Department of Natural Resources
619 Warehouse Drive
Suite 210
Anchorage, Alaska 99501
November 14, 1980
P5700.11.74
T.546
Dear Al: Susitna Hydroelectric Project
Steering Committee Review of Potential
Hydroelectric Development Sites
Thank you for the opportunity of meeting with the Steering Committee
on November 5, 1980. I personally found it disappointing that my
objective of establishing a workshop atmosphere where the members of_
the Steering Committee could have a positive input into our selection
of candidate hydro sites did not materialize. However, I realize
that our objectives for this comoonent of the Susitna studies may not
have been adequately explained. ·In this regard I have attached a
further explanation of our objectives as prepared by Robert Mohn of
APA.
I have accepted your suggestion that the most efficient means of obtaining
input from the Steering Committee is to 1) identify in-house the short
list of candidate sites we propose for further study; 2) present this
list to the Steering Committee for review and comment, and 3) incorporate
these comments into our final selection and review.
Presented on Table 1 is our short list of candidate sites proposed for
further study. As mentioned on November 5 it is essential for planning
purposes to retain 4-6 sites within each of the size categories listed.
These sites were selected from the list presented on Table 2. Table 2
represents sites that have passed through our rough economic and
environmental screening. Although I realize that the Steering Committee
disagreed with our rough screening criteria it is my opinion that using
this criteria allowed us to eliminate the least environmentally acceptable
schemes.
.~.·:~·1~5 .u~:Ct=:~C/'\~-~ ~: .,-:C::L=-·".::-' .. -::J
• ~· ·~ ,., •• : •. J
=": ·• . r "'! ' .-. • ....., • • • ~ •
•: ~:... ~· •.· ·---~·::...:---.. , .. , ":::..."1 : .. :
-)
....
...
-
....
-'
-
11111111
...
...
...
IIIII
-
IIIII
...
-
...
IIIII
...
-
.·. -
-
-
-
-
-
-(-
-
-
......
Mr. Al Carson
Chairman, Susitna Hydro Steering Committee
November 14, 1980
page 2
I would appreciate receiving the Steering Committee's review and comments
on the sites presented in Table 1. If for any reason you find that any
of these sites are totally unacceptable, I request that you recommend
a replacement of similar size from the sites listed in Table 2. This
replacement is essential so that we can retain 4-6 candidate sites in
each size category. Information relating to location and design para-
meteNfor each site was included in the information packets distributed
prior to our November 5 meeting.
Trusting this approach meets with your approval.
KRY/jmh
Attachments
.·,c.~:.:.;~~ .. ~~;-_:: .... ! ··;""";~.,?(~:-:..-\ .·..:.:
Coordinator
' •' .
(.
TO:
FROM:
ALASKA POWER 1\.UTJIORITY
Susitna Steering Committee
Members
-~/ Robert A. Mohn tvro/
Director of Engineer(ng
Alaska Power Authority
MEMORANDUM
DATE:
SUBJECT:
November 25, 1980
Environmental screening
of hydroelectric
sites
There has been some measure of frustration and disappointment on all sides
associated with the attempt by Acres American to solicit input from the Steering
Committee at the committee's last meeting. It seems to me that an important
factor in the lack of success may stem from misunderstanding or uncertainty
about this exercise in relation to an 11 alternatives study 11
•
As you probably remember, the original Acres plan of study (POS) called for
a study of alternatives to Susitna as the primary element of Task 1. Information
about alternatives was to be developed, a screening mechanism was to be employed
to narrow the range of acceptable options, and the Susitna project was to be
compared against the preferred alternative. This work was to be conducted in
parallel with the detailed studies of the Susitna project, and its goal was to
formulate several optimized 11 Without Susitna 11 plans. In other words, Task 1 was
meant to be a thorough search for a plan that would be preferable to Susitna
development. ·
The Power Authority requested supplemental funding to adequately fund Task
1 after some early criticism of the funding level and study scope. The requested
$1.3 million was appropriated but with the caveat that the alternatives study
would be performed by someone other than Acres. The Governor•s 4-person policy
review committee (Ulmer, Lehr, Quinlan and Conway) selected Battelle to do the
work.
The elimination of Task 1 from our study plan left a significant hole.
This was the case because information that was to be developed in Task 1 was
critical to the formulation of the preferred Susitna basin development plan and
to the economic evaluation of the Susitna plan. River basin planners cannot
formulate an optimal Susitna plan without knowing what the remainder of the
Railbelt power system components are likely to be, and the economic analysts
cannot evaluate benefits and costs without having a ''without Susitna 11 plan to
compare to.
So, the Power Authority and Acres responded to the termination of Task 1 by
augmenting the design development work in Task 6~ This permitted .the Susitna
study to stay on track by incorporating that portion of Task 1 needed for Susitna
plan formulation. The objective of this work is not to formulate an optimal set
of alternatives; that is being done by Battelle. Instead the purpose is to
gather information about likely components of a future Railbelt power system as
a frame of reference for Susttna project formulation.
...
..
-
....
....
-
-
....
-..
-
-
-
-
-
-
-
-
-
-
-r ..__
-
-
-
-
-
-
-
....
-
ALASKA POWER AUTHORITY
MEMORANDUM
TO: Susitna Steering Committee
Members
DATE: November 25, 1980
It is in this gathering of information about likely system components and
in establishing the frame of reference that your assistance has been sought. To
reiterate, the exercise is in support of Susitna project formulation; it is not
meant to replace the Battelle alternatives study or be the final word on alter-
natives.
,_
John D. lawrence
Project Manager
Acres American, Inc.
•
900 Liberty Bank Building
Main at Court
Buffalo, New York 14202
Attn: Mr. Kevin Young
Dear Kevin:
• ALASKA POWER AUTHORITY
November 25, 1980
Reference is made to your letter of November 14, 1980 to the Susitna
Hydroelectric Project Steering Committee about hydro sites.
\·le concur with your approach of corresponding directly ~'lith Mr. Carson.
He will both distribute the listing and collate any findings thereto.
Mr. Mohn prepared the additional explanation of the task 6.32-6.36
objectives and it was forwarded to the Steering Conunfttee with your
letter. I am attaching a copy of that explanation to your files. If
Mr. Carson chooses to respond directly to you it would be appreciated if
you would provide us with copies of his responses.
Attachments: As stated
cc: J. Gi 11
Sincerely,
David Wozniak
Project Engineer
CONCUR:
RN1
-~~~1~~~J181iiiifli"iiiiiWJk...s•~·-·II!I!W!I!!!IIiiii!IA!in!EWilll1I!IIICBCIWII _____ c:.,. ________________ _
..
..
-
...
-
...
...
...
...
--
...
...
...
-
-
....
-I
-
-
-
-
-
-
-
-
-
-
~ ----,'
"''
ALASKA Pm~ER AUTHORITY ·t
' \
t-k. Al Carson
State of Alaska
Department of Natural Resources
323 E. 4th Avenue
Anchorage, Alaska 99501
Dear Al:
t' ~ t
ttovember 26, 1980
Thank you for your efforts in pulling together the Susitna Hydroelectric
Steering Committee review of the Task 7 Procedures Hanuals. I have fonnally
forwarded ~he comments to Acres Americans Inc., with instructions to act prompt-
ly on the h~CO!Tillendations. I anticipate the vast ma.jority will be considered
by the end of the year, with the remainder addressed shortly thereafter. I am
planning on giving a report on their disposition at the next convening of the
committee, which I am assuming will be 1n February, 1981.
Once again, thanks to you and your committee members.
FOR THE EXECUTIVE DIRECTOR
cc: Don HcKay
U. S. Fish & Hildl ife Service
733 H. 4th Ave., Suite 101
Anchorage, Alaska 99501
Tom Trent
Alaska Department of Fish & Game
333 Raspberry Road
Anchorage, Alaska 99502
John Rego
Bureau of Land fr1anagement
Anchorage District Office
4700 E. 72nd Avenue
Anchorage, Alaska 99502
Bob Lamk.e
U. S. Geological SurJey
Hater Resources
733 W. 4th Ave.7 Suite 400
Anchorage, Alaska 99501
Bill Wilson or Chuck Evans
Arctic Environmental Information
and Data Center (U of A}
707 '1 A" Street
Anchorage, Alaska 99501
S1ncere1yt
David Hozniak
Project Engineer
CONCUR
RM-1
/: / "
,(>.
{_ Mr. Al Carson
November 26, 1980
Page 2
Dave Sturdevant
•
Departme~t of Environmental Conservation
Pouch "0 11
Juneau, Alaska 99811
Larry Wright or Bill Nelch
Heritage Conservation and
Recreation Service
1011 E. Tudor Road, Suite 297
Anchorage, Alaska 99503
Brad Smith or non Horri s
National Marine Fisheries Studies
701 "C" Street, Box 43
Anchorage~ Alaska 99513
• ..
-
-
IIIII
-
...
..
IIIII
...
...,
-
...
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-·
-
-
-. 't
~7
-
-~
Hr. John Lawrence
Attn: Kevin Young
Acres ~merican, Inc.
•
900 liberty Bank Building
Main @ Court
Buffalo, New York 14202
Dear Kevin:
ALASKA. POWER AUTHORITY •
rlovernber 26' 1980
Attached is the finished version of the Susitna Hydroelectric Steering Com-
mittee findings to the Task 7 Procedures Manuals. A ~rork1ng draft was presented
to us during the November 5, 1980 meeting; this version incorporates comrnents made
at that meeting. AS you \-till see, it differs from that \10rking draft fn minor
detail only. Also attached are agency source documents, resources previously un-
available to us.
As I surrrnarized to the Steering Corrmittee at the flovcmber 5 meeting, the
Power Authority considers the majority of the comments to be reasonable~ help-
ful. and worthy of immediate incorporation. He accordingly solicit your posi-
tive approach to accommodation of the Steering committee comments and recommend-
ations.
I suggest we very quickly address the acceptable recommendations and then move
on to focus our energies on those that require deta11ed evaluation. To insure we
are in agreenEnt, I suggest you advise us on a point by point basis those comments
you recommend accepting, with narrative as to method of incorporation. In separate
correspondence. advise us of those comments for which you have reservations, and
your recommendations thereto. In view of the fact that we have been privy to the
Steering Committee thinking since early November. you should be able to do this
\·tell befors the Christmas Holidays. Such a timetable Hill hopefully facilitate
early resolution of all the comments in time for a report to the Steering Commit-
tee at their next convening.
FOR THE EXECUTIVE DIRECTOR
Attachment: As noted
Sincerely,
Oavi d ~lozn1 ak
Project Engineer
cc: J. HaydeL. Acres Buffalo w/o attachment
J. Gill~ Acres, Anchorage, w/o attachment
CONCUR
RAM
A. Carson, Department of Natural Resources, Anchorage, w/o attachment
r~ark Robinson, FERC, 825 N. Capitol" St., NE, Washington, D. C. 20426
MFR: Next convening tentatively scheduled for Februrary, 1981.
-I
(
..
-...--. ~ ---' ---t.-"
! ·-'.-
_; :J'U ~ G
. -;::' \ r.::: : il!-
;. ,_
:I~ :, .. I i
\':::../ ;_j
r· r ·--.-tin (J
, l ! • \ ; ~ ..... ...i J '; / ' '!.
I j \' ' ' I j\
i ~: ' : : : ·-~ ·, · ... •. : , · "'·. I 1J \
i -~ ' • . ..• I .... ·. I I. ' \ \ I ...., I
U ~ ~:..,; Ll .::j 'J w !..J u
I
I JAY .t HAIIIIDIID, 'l!Y£11101
I
..
-I i
t
DEP.\.IlT~IENT ot· .NATUR."I .. Rt:SOURCES
j 323 E. 4TH A VENUE
DIVISION OF RESEARCH & DEVELOPMENT j ANCHORAGE, ALASKA 99501 ..
December 11, 1980
Don McKay
U. S. Fish & Wildlife Service
733 W. 4th Ave., Suite 101
Anchorage, Alaska 99501
Dear Mr. McKay:
279-5577 ...
....
-
-
-
.. Enclosed please find a 11/14/80 letter from Kevin Young of Acres American
concerning review of potential hydroelectric sites. You will recall that we
discussed this with Mr. Young during our afternoon session on November 5, 1980.
There is also a memorandum from Robert Mohn of the Alaska Power Authfr~t~~h~R .
describes why A.P.A. has contracted ACRES to do this task. A:..:rnoR:rv ·,r-~ SUSITNA '. ·
Please review the documents as explained in Mr. Young's letter and ~~~~ P5?~ ;
your comments to me either in writing or by phone by December 31, 19180. ..·1\.74 .... ;-j
------------.. .. i l
Sincerely,
~~
Al Carson, Chairman
Susitna Hydro Steering Committee
Enclosures
cc: Eric Yould -A.P.A.
Kevin Young -ACRES
; :..~;h·!_i;?.;;::l: uo. ' ;
.. -~~ ---~--·---...--•
;' ~-'··:~ ! t3 ! t t'
',._ .. I -I -· '-·~· ;, ~ l ~ ~
~ :::; i3 I z r . . ! -·-·-'-·: I i i:H·".'·/i-· .
:-:r.;.:~ ~~;_.--::;:: . :---:~~~-~f..,
! :l(c: ~: · .' : ;·1 t 1 {·,
!-·."'c ·; ,· .:-: ~·-r ,/ .--~-~ L?:/L:.. 1
--~IYv-
.---·. : :·.:_~-·~·-.~ _J. / .
---·, 3 . . ·:' ~~ ___ ? / (
• '5•,;.....;-"!"j· ::: .
-: -· ..• ~ ~.....!..!_;, ..
. ::: ~l T l l
-~!~'-_::;_~'. :_! -~
I !".-!~VI-1-
·-;-:-H-F~cj·-:
:=l'ICc.f:~.t<X i t',lf{-
:_~4~~s~1!'11'7.
I I ~.--=-:-;
,--. -~(17-. I I ; /;' .-·-:-~-' ; ! 1 I I • ----.;:;-~· :·.ci-;:--l,r: ,:-·/ . r71: . ._._
J/
!
-
-
-(
-
-
-
-
-
-
-
~
' ..: i -
"' --·~
.....,
-.-,., ,.~ ~ .. ~ ~
',.;. I/ It\
I '
'· ' ·,-\ I .j'
--. ,-; . ; ·_ '. j (""'\ \
... •• --...J -...._ ,_. ·,_;., w u
I
I
I JAYS. HAMMOIIO, GOY£11101
DEP~,RT~tENT o•· NATURAl .. R .. :SOURCES
I
I
' I
I
DIVISION OF RESEARCH & DEVEL~MENT /
December 11, 1980
Tom Trent
AK Department of Fish & Game
333 Raspberry Road
Anchorage, Alaska 99502
Dear Mr. Trent:
323 E. 4TH A VENUE
ANCHORAGE, ALASKA 99501
279-5577
Enclosed please find a 11/14/80 letter from Kevin Young of Acres American
concerning review of potential hydroelectric sites. You will recall that we
discussed this with Mr. Young during our afternoon session on November 5, 1980.
There is also a memorandum from Robert Mohn of the Alaska Power Authority which
describes why A.P.A. has contracted ACRES to do this task.
Please review the documents as explained in Mr. Young's letter and forward
your comments to me either in writing or by phone by December 31, 1980.
Sincerely,
m~
Al Carson, Chairman
Susitna Hydro Steering Committee
Enclosures
cc: Eric Yould -A.P.A.
Kevin Young -ACRES
.,; I
r
c
----,... ~ ...,
; . :I I \ .. : : !1 . -; :I\ '\ , ~
,.. ' ' I ' ---·-,__ :·_: ·,_l i.J\..
DEP..\.IlT~IENT o•· NATURAl .. a•:SOURCES
DIVISION OF RESEARCH & DEVELOPMENT
December 11, 1980
John Rego
Bureau of Land Management
Anchorage District Office
4700 E. 72nd Avenue
Anchorage, Alaska 99502
Dear Mr. Rego:
l .
I
I I JAY .t HAIIMDitD, SDVCIItDI
1
I
I
i
l
/ 323 E. 4TH A VENUE
f ANCHORAGE. ALASKA 99501
279-5577
Enclosed please find a 11/14/80 letter from Kevin Young of Acres American
concerning review of potential hydroelectric sites. You will recall that we
discussed this with Mr. Young during our afternoon session on November 5, 1980.
There is also a memorandum from Robert Mohn of the Alaska Power Authority which
describes why A.P.A. has contracted ACRES to do this task.
Please review the documents as explained in Mr. Young's letter and forward
your comments to me either in writing or by phone by December 31, 1980.
Sincerely,
Gil~
Al Carson, Chairman
Susitna Hydro Steering Committee
Enclosures
cc: Eric Yould -A.P.A.
Kevin Young -ACRES
...
...
-
...
...
-
...
...
....
-
-
-
...
..,
...
-
....
-
-
j/
-
-
-c
-
-
-
-
-
-
-
-
--~-!""""! -_; 'I ; I \
' .:·i~ ! ~~ \
!J ~Lu
UEP~'RT~IENT o•· NATURAl~ RESOURCES
DIVISION OF RESEARCH & DEVELOPMENT
December 11, 1980
Bob Lamke
U. S. Geological Survey
Water Resources
733 W. 4th Ave., Suite 400
Anchorage, Alaska 99501
Dear Mr. Lamke:
I
I
I JAY .S. HAIIIIOIIO, GOY£11101
I 323 E. 4TH A VENUE I ANCHORAGE. ALASKA 99501
279-5577
Enclosed please find a 11/14/80 letter from Kevin Young of Acres American
concerning review of potential hydroelectric sites. You will recall that we
discussed this with Mr. Young during our afternoon session on November 5, 1980.
There is also a memorandum from Robert Mohn of the Alaska Power Authority which
describes why A.P.A. has contracted ACRES to do this task.
Please review the documents as explained in Mr. Young's letter and forward
your comments to me either in writing or by phone by December 31, 1980.
Sincerely,
Gl~
Al Carson, Chairman
Susitna Hydro Steering Committee
Enclosures
cc: Eric Yould -A.P.A.
Kevin Young -ACRES
(
.._.: ~ -
.. ~'7 .. -,
__; ·/: }l\ \ 1 , •.
·A i~\ : : \ '. ! ,....,, ·, _. ~ uw •.4
DEJ•.tJlT~IENT Ot' NATURAl .. RESOURCES
I
l
I
I
!
I
l
I
JAYS. HAMIIOIID, S0'(£11101
DIVISION OF RESEARCH & DEVELOPMENT' /
323 E. 4TH A VENUE
ANCHORAG£., ALASKA 99501
December 11~ 1980
Bill Wilson or Chuck Evans
Arctic Environmental Information
and Data Center (U of A)
707 11 A11 Street
Anchorage, Alaska 99501
Dear Messrs. Wilson & Evans:
J
279-5577
Enclosed please find a 11/14/80 letter from Kevin Young of Acres American
concerning review of potential hydroelectric sites. You will recall that we
discussed this with Mr. Young during our afternoon session on November 5, 1980.
There is also a memorandum from Robert Mohn of the Alaska Power Authority which
describes why A.P.A. has contracted ACRES to do this task.
Please review the documents as explained in Mr. Young's letter and forward
your comments to me either in writing or by phone by December 31, 1980.
Sincerely,
())~
Al Carson, Chairman
Susitna Hydro Steering Committee
Enclosures
cc: Eric Yould -A.P.A.
Kevin Young -ACRES
...
...
..
atl
..
..
..
..
--
...
-
--
~
-..
-
-
-
-
-
-
-(
-
-
-
-
-
-
:~ ... -\
~--.t,· !-.:.\
~\ :-;\ J·j\
.. : .. : ~-: ' ··--w ·...,....; w
!
i
I
I JAY .t HAMM0/10, &O'fCI/tOI
l ; ltEP.~RT~IENT o•· .NATURAl .. RESOURCES /
DIVISION OF RESEARCH & DEVELOPMENT /
December 11, 1980
Dave Sturdevant
Department of Environmental
Conservation
Pouch non
Juneau, Alaska 99811
Dear Mr. Sturdevant:
323 E. 4TH A VENUE
ANCHORAGE, ALASKA 99507
279-5577
Enclosed please find a 11/14/80 letter from Kevin Young of Acres American
concerning review of potential hydroelectric sites. You will recall that we
discussed this with Mr. Young during our afternoon session on November 5, 1980.
There is also a memorandum from Robert Mohn of the Alaska Power Authority which
describes why A.P.A. has contracted ACRES to do this task.
Please review the documents as explained in Mr. Young's letter and forward
your comments to me either in writing or by phone by December 31, 1980.
Sincerely,
OJ~
Al Carson, Chairman
Susitna Hydro Steering Committee
Enclosures
cc: Eric Yould -A.P.A.
Kevin Young -ACRES
c·
.---.-,......._-n n i\ ....-r"'I"'9Q . ;..":l c::-:J n ....... --1 r' :' ,.., ' ; " \ : : ,1, \ r \-~ : v(· ~ ·, . ~ -; f : ' \ ; I L. . ! ~ : I ' I :'. \ I I I. • ' . . ' ,, u~ 1 j \ ~; ! ...,; ': ; 1 ~ ~ i I..J l i' ! J 1 \.\ l 1\,\ ,_J \ \0 u-u u Lb ~:::v u LnJ t.= Lr\J \:}) u u u-u
DEJ•.\UT~IENT o•· ~ATURAI .. Rt:SOURCES
DIVISION OF RESEARCH & DEVELOPMENT
December 11, 1980
Larry Wright or Bill Welch
Heritage Conservation and
Recreation Service
1011 E. Tudor Road, Suite 297
Anchorage, Alaska 99503
Dear Messrs. Wright & Welch:
I
f
I JAY 1 HAMMOND, GD'ICIItOI
I
I
I 323 E. 4TH AVENUE
ANCHORAGE. ALASKA 99501
279-5577
Enclosed please find a 11/14/80 letter from Kevin Young of Acres American
concerning review of potential hydroelectric sites. You will recall that we
discussed this with Mr. Young during our afternoon session on November 5, 1980.
There is also a memorandum from Robert Mohn of the Alaska Power Authority which
describes why A.P.A. has contracted ACRES to do this task.
Please review the documents as explained in Mr. Young•s letter and forward
your comments to me either in writing or by phone by December 31, 1980.
Sincerely,
01~
Al Carson, Chairman
Susitna Hydro Steering Committee
Enclosures
cc: Eric Yould-A.P.A.
Kevin Young -ACRES
..,
-
-
...
..,
...
-
...
....
-
...
-..
...
-..
-
-
-
-
-
-
-
-C.
-
-
-
-
' .
-;;,::, c:-;:J /A\ c:-;:: p ~ ! I ' ! I . . . -~ ' ! I I {1 I ; ! ~
r9 U /rJ U l.S
C'-~--::::
• ' ~ i 1 I 1: ;! ·~ ~ i i I -' '~0 u
r1 n ~~ ,~ ~ /7 :; /.~\ !i !'\ i\ :i·( (;\\
tn' u'\' \ :: f I\ I '• ··-, ·_: '., j' .. ' ·,
l I..._." \ j \ -u lbLJ\j 0 u ui.ru
/
J f JAr S. HAIIMOIID, GDYCIIIOI
I.DEI~'IlT~IENT 014 NATURAl~ a•:sOURCES I 323 E. 4TH AVENUE
DIVISION OF RESEARCH & DEVELOPMENT
December 11, 1980
Brad Smith or Ron Morris
National Marine Fisheries Service
701 "C" Street, Box 43
Anchorage, Alaska 99513
Dear Messrs. Smith & Morris:
I ANCHORAGE, ALASKA 99501
279-5577
Enclosed please find a 11/14/80 letter from Kevin Young of Acres American
concerning review of potential hydroelectric sites. You will recall that we
discussed this with Mr. Young during our afternoon session on November 5, 1980.
There is also a memorandum from Robert Mohn of the Alaska Power Authority which
describes why A.P.A. has contracted ACRES to do this task.
Please review the documents as explained in Mr. Young•s letter and forward
your comments to me either in writing or by phone by December 31, 1980.
Sincerely,
~~
Al Carson, Chairman
Susitna Hydro Steering Committee
Enclosures
cc: Eric Yould -A.P.A.
Kevin Young -ACRES
.. ..
(_
'r(
i
--~ i _,.:.~; •• ..li. _ _;_,._~ --------.
-, '1F'~"' I
I' J .• ~ :j ~ !'
j :·;i~~'l·{--11'
. --.,. ,, . :.,~:-.1
Mr. Al Carson
. '
Chairman, Susitna Hydro Steering Committee
Department of Natural Resources
619 Warehouse Drive
Suite 210
Anchorage, Alaska 99501
November 14, 1980
P5700. 11.74
T.546
Dear Al: Susitna Hydroelectric Project
Steering Committee Review of Potential
Hydroelectric Development Sites
Thank you for the opportunity of meeting with the Steering Committee
on November 5, 1980. I personally found it disappointing that my
objective of establishing a workshop atmosphere where the members of_
the Steering Committee could have a positive input into our selection
of candidate hydro sites did not materialize. However, I realize
that our objectives for this component of the Susitna studies may not
have been adequately explained. In this regard I have attached a
further explanation of our objectives as prepared by Robert Mohn of
APA.
I have accepted your suggestion that the most efficient means of obtaining
input from the Steering Committee is to 1) identify in-house the short
list of candidate sites we propose for further study; 2) present this
list to the Steering Committee for review and comment, and 3) incorporate
these comments into our final selection and review.
Presented on Table 1 is our short list of candidate sites proposed for
further study. As mentioned on November 5 it is essential for planning
purposes to retain 4-6 sites within each of the size categories listed.
These sites were selected from the list presented on Table 2. Table 2
represents sites that have passed through our r.ough economic and
environmental screening. Although I realize that the Steering Committee
disagreed with our rough screening criteria it is my opinion that using
this criteria allowed us to eliminate the least environmentally acceptable
schemes.
~ ·-.·:: ,·\ ::.s . , ... Ct-: IC _:,~! : .' . ,--:;: ;:: ~=· · .. ~· ~~ .·::;
·: ._·_: ·: t~ -.:-!
:; :... •r: ''"' . .._.-, ~ .
•: -_·:.
.... "" ........ ·-=··=
-..
...
-
-
-
-
-
-
.,.;
-
-
-
-
-
-
-
--
.. ·.
..,_~
....
t
.......
-
-
-
-
-
Mr. Al Carson
Chairman~ Susitna Hydro Steering Committee
November 14, 1980
page 2
I would appreciate receiving the Steering Committee•s review and comments
on the sites presented in Table 1. If for any reason you find that any
of these sites are totally unacceptable~ I request that you recommend
a replacement of similar size from the sites listed in Table 2. This
replacement is essential so that we can retain 4-6 candidate sites in
each size category. Information relating to location and design para-
meteNfor each site was included in the information packets distributed
prior to our November 5 meeting.
Trusting this approach meets with your approval.
KRY/jmh
Attachments
. \'-·~ ....;.~ . ' ... ..:.:· .·-~: .. : . ·-: ... ,;rJ· . .:;~ ... ,· ~:
Coordinator
,
/
/ . ' .. -
Tab 1 e I
Candidate Sites for Future Study
.....
Size <25 MW 25-100 MW >lQQ MW -
Tustumena Snow Chakachamna
Allison Creek Hicks Johnson
Silver Lake Cache Browne
r Strandline Lake Keetna Land ....... -Talkeetna-2 Tokichitna
Lower Chulitna
-
.......
-
-
. . .. -
......
Table 2
Sites Passing Rough Screening
Size <25 MW 25-lOO·MW >100 MW
Strandl i ne L. Whiskers Snow Lane -Lower Beluga Coal Kenai Lower Tokichitna
Lower Lake Cr. Chulitna Gerstle Yentna
Allison Cr. Ohio Tanana R. Cathedral Bluffs
(~ Grant Lake Lower Chulitna Bruskasna Johnson
McClure Bay Cache Kanti shna R. Browne .....
Upper Nellie Juan Greenstone Upper Beluga Tazilna
Power Creek Talkeetna 2 Coffee Kenai Lake -Silver Lake Granite Gorge Gul kana R. Chakachamna
Solomon Gulch Keetna Klutina -Tustumena Sheep Creek Bradley Lake
Skwentna Hick's Site
...... Talachulitna Lowe
-
-
-
......
0-~-0,.
-
-
,._
~
-
-
-
-
-
-
-
......
-
~ . -_;.t· ,;· ·;·r· r··i'. .... l"" ·-. ·' • . . ~~ ·..'!t;.l ' •• -. '.,. p!~ ~ t :), . . '·. . .· .. ,...,_ ,. ·1--.,,,.!1 ~. 'Jl'tf ,, ·' ,'-'~~f:*-lh:O:";' 't · ··••t"l.Fc >"'''"": !<'AlASKA
POWER AUTHORITY-~
ttti) -~-:~n :'' ·''' r~•.1.l . v ....
• I '
~ ;;..,.
... ·. ·~
Robert E. LeResche, Comm1ss1oner
Alaska Department of Natural Resources
P.!uch·M (Mafl Stop 1000)
Juneau, Alaska 99811
Dear Comm1ss1oner LeResche:
January 2, 1981
· ;~ •• 1.:,Your organization has been cooperating extensively with the Power Author1ty
in assess1ng:the potential effects of hydroelectr1c development of the Upper Su-
s1tna River ;B.asin.-:.Several different vehicles have been used; meetings, corres-:
pofldence, ·at\d Su"51 tna Hydroelectric Project Steering Camlittee act1viti es. We
feel that the results reflect close consultat1on and coordination between our or-
ganizations.
As the study has progressed, more and more items requir1ng consultation have
emerged, and the future w111 requ1re a still higher level of involvement. This
anticipated level of activity. plus the fact that the Federal Energy Regulatory
Commission (FERC) and the Fish and W11dl1fe Coord1nation Act require documentation
of such consultations. suggests 1t fs now appropriate to be more formal in our ex-
changes. Accordingly. we advance this suggested procedure to you for your concur-
rence and/or suggestions for modification.
~
In general, we propose a two step process. The first step will consist of
consultation with the Sus1tna Hydroelectric Project Steering Committee. That
body ~ill perform evaluations and structure recommendations. The Power Authority
w111 consider these recommendations and formulate a position. Upon completion of
these actions, the results w~ll be processed through your agency for formal con-
currence.
This represents a sl1ght expans1on of the original concept under which the
Steer1ng Committee was structured; the Committee was to act primar11y as an ad-
visory bo~' to the study team while ~econdar11y facilitating agency involvement
1n the study effort. Member agencies were to be represented by senior staffers of
skills appropriate to the matters under consideration. This was considered to be
advantageous as it would facilitate responsiveness by virtue of being relatively
independent of procedural impediments, while still reflect1ng to a substantial de-
gree the agency v1ewpo1nt.
This proposal hopefully preserves those advantages within an expanded role by
permitt1ng attainment of interagency concensus with a relatively low level of in-
put and a h1gh degree of flex1bi11ty. It also permits the various agencies to
tailor their part1c1pat1on to the spec1f1c needs. Finally, the second step of re-
ferral of Steering Committee de11berat1ons for formal agency concurrence meets regu-
latory and statutory requirements.
~ ... .,..\
-~:
. I -~ ~-.. .... ~ .... .,. ,. ' ~ .. ·1· .. )....,._, l ~~' . . ' ' -~:u:u;4j!!T;!~~; .. '1 • : . ___ ;, , -~ .. , : . _ . . e· ... ~1~~-~··. ,-.;:..,';., l ·~''. •. . . ~it~;.~,:....f-ll;:~-<:·~----~, ... ~=' . ' ' ' . . =~·;..;.;? • ''"~ii~'''"""~~i·.:;t~,_ . .. . > ; ' .' \. • • • j~;tf~o/t~ .. ~~·~:;~J.c~ . :i ·~·· ~ ~ ' .,.
·;~''H",t:t,~·-""'"\ol"\•t,.\·,1;~-~ • •il '•r ; a~~.: .. =~?i'.:i':):}~.\: ..;!~ ••• :~~~~~~~ii:: ,_ . ' ' ' <
.. ,: .. ::,~:.:;·:::~. rran:_ces 'A. · U.l100r i pi rector
· ,::;·.c::~ ~--·:::-"'otf1ce'.·of, the·· Governor : " . '
;:::<~.~::<~?·;:.;~:~:·oivfsH)n ~of ·t>oH cy De vel oprrent and Planning
· .,~~:_,··(._::.;i:Poucn~'~J\0 '(IQ·n ;' sto{>' of64} 't' .
-~/·-·,._':~£Juneau· ·Arnska:,-.-:998lr· ·. · .
. . , . .. .:,::;. ::.;~~:..-:,;~ ': .. ·.: '~ ·;' ·.; • ~: •. . . •. ~ ;f : . I'
·;i;: e ...
January 2, 1981 -
...
...
,(~ · '···-oear' Fran· .. · '· · 1' ' · : ·• i~ ' _:,,>}~~!'::..~f.t.~"t~~;.~::• ·'·:, .. ·; .. ..:; ,._ : ·: :-~:::<. ....... . . . . ....
·-~··' · ·· ~~~~.-·~.{~·.:~:rne~Pmrer. )\Uth0r1ty.1S<sttidy1ng and assessing the potential effects of hydro-:
: -::eH~ctr1c·~evelopmeritilf the:'Upper'Sus1th4 River Gas1n. Acccmp11shment of that :
-.:. -''til'sk:'~'riecessftiti!i·::consuftbl1on :and coordination with var1ous Federal, State and 1'!-
·-., --~· .. cal::~pl-ganfiat1oos·,:.incluCi1o9 ymirs •. · ·-· .
~ .. -:.~;i1t~~r;t::: ~:-:;.\.>/.· ::;;-;: :\~:·;~ >::.:::::~·~u~~~ ~ft < .. : .. ,c' ·. . · .
. ~ -~~.··; ~'?:;':+''!l?As: the.:.stUd,y";~astprog~sse<ftrarire ar\q_, more items requiring consul tat1 on ha~
_/·'·~emerged,·'and;:tfle:~Jutui'i!w111'requ1re:i.st1l1 h1gher level of 1nvo1vement. This:··:
::~:·antldpated/1·&-ver~:·ot!~'i:t) ~rtY. iP,1~i ~li~ . .'fa~t that tho federa 1 Ener9y Regulatory · ·:
. <Commission> {FERC}."and .·the, fish and--Wildlife Coord1 nation Act require docume-ntat1tW -•-'of.'~uch·:consul'titfPris;.'suggests;~.H is now appropriate to establiSh a formal pro-
· .. :cedure for'our d)ritacts~ ~~.\Accordinglh 'we· advance the following plan to you for·
. , .. your:·con.~ul'T,ence .. ~iid/9r: sugges1;~ons. for~ mod1f1cat1on. .
· · ·--:: · . ' ;_·.·: . .:::,: :~~· :~~<·;~''f;·\ ~: i;'i~~t: 1' r; ·H~ Ur~· >;i:, ;i 1 l~l\:;-; : · . -~
· . , In gener~l .:;· w.e. :P.roMStJl. tW,t)i.~tept P,~e$s. The f1 rst step w111 cons 1st of<:",
c.onsu1tat1oo .w1t~. [l~~:>~!fS~.tri~,;~~t~l~~J~ Project S~ering Ccmn1ttee. That. i), '.'
.. >~ody ~111 ~.r1.9.~:!'1~W.~.~19~~:,~P~i~t~ur!.:econmen9~tion~. The Power Autho.r1tY~.·:
· .~· -. -:~will ~onsfder ~.~he!!''\re~·~~t~~n.t:a"'9Jrprmo1ate a pos1t1on. Upon c~letion: .~~ "·:4
., ·. ··. ·these act 1 ons ~ ,ithei resu1 ts ;;~1 11 ;: bi ~ p~ssed through the mppropr1 ate organ1 zat19n~ •
' , ~·· ·for'·forma 1·:!conci.tr+enee~···,: .~ li ~;: ·: · .. · i .. , .. ·: ~ -.··.:..:~ .. ''." .:,: ... :: :.~·;~~ .,·: ~->~:: ;·,: 'i.; ' '
.. ·· ..... '1 req~st )'()ur.'written: concur+~nee \11th th1s proposal J or. if you have other '
. .t~ghts" on .. t~' ~tter., ... ~;),.e ahx1ou~ :~ ~xplore them with you. -
•: c ) f I i' . ' , ?I:. i ·it;~ ~.: ' !
1 .. -. ·~~-·· · S1nce'N!ly ~-. ,
/', {,
---. ~ --) ( I d l ------~ ~ ' I -·~·\
E r1 c P . You 1 d '
Executive 01rector
' ~~
,.···' .. _ .. ,...
~~ • ., I ,. . . ' cc: · B111· Welch. U •. S. HCRS:~· · · ..
Larry ·wr1gh~~ ·o., ·s~ -HeRs :
Jim Thomson, U.S. H~'Rs. . . ~ . . -~ ~~ ' ;
Sent to:
Alaska Department of Community and Regional Affairs
Alaska Department of Commerce &·Economic Development
Office of the Governor, Division of Policy Development and Planning
Matanuska-Susitna Borough ·
Environmental Protection ~gency, Region 10
Alaska· District, Corps of Engineers
. U. S. Geological Survey ·:·.:··,.
At t~_ch!lle n t . # 2
~-
. ~;':;!~~:-
;· t ~
;._ . ~.
:.·' .. (. ,.. . . ~ ..
~:l~~:-... : ·;.:::~.{
'. ~;,.:: .. :~ ., .~ !> ··:; t• ;_ ""• ...,,·1/··
.. ! ' g·
-
...
.-·CONCUR: . -·:.
ow -RAM.
EPY', '
.....
...
-
.-.
-
-
Agency
ADC&RA
ADC&ED
DPOP
EPA
COE
USGS
MAT-SU -AOF&G
ADEC
AONR
NMFS -BLM
HCRS --·usFWS
'-
-
-
....-
Attachment #3 .....
. : ~l;
.:._/
e:.-
~ : : : !-:
AI.~ASiiA J•O\VER AIT1'1101{11,Y
RESPONSE SUMt·1ARY
Respond?
Yes
Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
No
Yes
Yes
Yes
Yes
Comment
Abstain
Concur
Suggest A-95 Procedures
Concur w/option preserved
Does not wish to participa
Concur
Concur
Concur
Concur, w/option preserved
Concur, w/option preserved
Concur
Concur, w/option preserved
·t
ft'' ... :: ••• ._,~·.::
United States Department of the Interior -
FISH AND WI LDLII:E StR V ICL
Western Alaska Ecological Services
733 W. 4th Avenue, Suite !01
Anchorage, Alaska 99501
RSCEIVo..,
IN REPLY REFER TO:
( 9 0 7) 2 71-4 57 5
.' ;~ N 1 9 19 i
...t,
ALASKA POWER AUTHOR!
Eric P. Yould
Executive Director
Alaska Power Authority
333 W. 4th, Suite 31
Anchorage, Alaska 99501
Dear Me Yould:
.1 € t f ... U~81
( .-;.J
t_) \
The U.S. Fish and \.Jildlife Service (FWS) has received your letter of
2 January 1981 proposing that the agencies comprising the Susitna Hydro-
electric Steering Committee provide fonnal concurrence to positions
developed by the Alaska Power Authority (APA) in response to committee
recommendations. We concur with your proposal. However, in the event
that we disagree with APA's position, we reserve the option of providing
a fonnal response indicating what is required for HJS concurrence.
Sincerely,
;{J-/~~-
Field Supervisor
cc: AOES
-
IIIIi
..
....
-..'
..
...
-
...
...
-
-
..
....
...
-
-
-
-
-
-
-
-
$¥m¥~ 2lill~ ~~~~~u~-~~ JAY S. HAMMOND, CoYernot
DEPT. OF COMMUNITY & REGION.t\.L AFFAIRS / POUCH 8 I
OFFICE OF THE COMMISSIONER I JUNEAU, ALASKA 99811
PHONE: (907} 465-47-00
Mr. Eric P. Yould
Executive Director
Alaska Power Authority
333 West 4th Avenue, Suite 31
Anchorage, Alaska 99501
Dear~~ld:
JanuaDJ 20, 1981
RECEIVED
Jf\N261981
).JASKA POWER AUTHORITY
Thank you for your letter of January 2 regarding hydroelectric developnent
of the upper Susitna River Basin.
I have no additional ccrcments on this project at this tirre. I do wish
the Alaska Power Authority much success in the Susit.11a Hydroelectric
Project and all other projects APA is involved with.
Please accepts my regrets -I always seem to have conflicts at APA meetings.
Sincerely,
~
Lee McAnerney
Comnissioner
J
08-H2LH
~U&U~ ~'@if &~&~~&:)
Ut:t• :\ RT.'t1 •:~'f 0 ... ('O,.~U t:Dt(··: ~\
1-:('0~0lllt..' IU·:\' .. :I..OI•!'ti<:NT
JAY S, HAMMOND. GO'IERIIOR
OFFICE Of rHE COIIJI/SSJONER I JUNEAU, A LASKA 99811
Phone: 465-2500
Mr.. Eric Yould
Executive Director
Alaska Power Authority
January 21, 1981
RECEIVED
'.1.N 2? 1981
ALA.SK,\ PO'l/Li; ;\U [}-10t!ITY
333 West 4th Avenue, Suite 31
Anchorage, Alaska 99501
Dear Eric:
I am in receipt of your letter dated January 2 requesting
a response from me on your proposed procedures for consulta-
tion. Please be advised that I concur with the two step
process presented in your letter to me.
CRW/mh3/20
/
Sincerety,
I
/ (. i '. " >' ~ .-vC< · ·-------· .
Ch~rles R. W~bber
Commissioner
...
...
...
-
...
...
...
...
....
...
...
-
-
...
...
\1111111
-
...
-
-
-
-
-
-
-
-
-
-'
-'
/
/
--~· ...
'
..... ,
~~:
~ -;.~ .
·. ~~_:._:: -
I
I
i
/'
. r· ... ,. :"-.":;
'';'~
/"
·" _./ 'II
~If'~ ;r r-e rTI!l
1
r-e r~ r1 w ~ 1~( i.\\ ~ u t;J u l1 lliJ lf ~ lb /)~\ \~) [j \\ I ' I
JAYS. HAMMOND, GOVERNOR
IH~I':\Il'r:Ut-::~T 01·' 1:1SII ,\"U (~.\ lU: !
OFFICE OF THE COMMISSIONER I SUBPORT BUILDING
' JUNEAU. ALASKA 99801
January 22, 1981
Mr. Eric P. Yould, Executive Director
Alaska Power Authority
333 West 4th Avenue
Suite 31
Anchorage, Alaska 99501
Dear Mr. Yould:
p.ECEIVE.D
~ ,-· G
\ \:..0
I. l9 ~l
;;..AS:<.;.. ?0\'i-;' ;.J :r-\ORIT'f
The Alaska Department of Fish and Game has considered your January 2
proposal for an agency consultation process by th~ Altiska Power Authority
(APA) through the Susitna Hydro S teer:ing Comrni t tr~e. The process for
evaluation and recommendation by stnff of this 2gency, and the form~l
agency concurrence action of APA's developed p0sition is acceptable to
this Department.
I suggest APA work further with the Stccrinr, Committc.:c to f lnalizc the
details of the implementation of your propos~d coordination/consultation
process at their next meeting. The Steerir.g Committee should be able to
do much in the future to eliminate dupJtcation of coordination and
consultation effort, on both our parts, for the Susitna Hydroelectric
Project.
SincGi,~
Ronald 0. Skoog
Commissioner
(907) 465-4100
cc: A. Carson
UNITED STATES
-· ;:::'.}
DEPARTMENT OF THE INTERIOR
GEOLOGICAL SURVEY
Water Resources Division
733 West Fourth Avenue, Suite 400
Anchorage, Alaska 99501
Eric P. Yould
Executive Director
Alaska Power Authority
333 West Fourth Avenue, Suite 31
Anchorage, Alaska 99501
Dear Eric:
January 26, 1981
I -·· ..
We concur with the two-step process of interagency consultation and
coordination in studying the potential effects of the proposed hydro-
power ~evelopment of the upper Susitna River basin outlined in your
letter of January 2, 1981.
The Water 'Resources Division has no regulatory functions, so formal
concurrence with your agencies actions is not within our field of
authority. However, we can assist in advisory capacities. The Geologic
Division expertise may also be available for consultation. The Conservation
Division is the only Geological Survey division with regulatory authority
and they have a section that handles hydropower developments.
Sincerely yours,
)
) : /. //
fl. / / f ·r( -·-. /'....___ __ .· ·t· ~J '/' ';··-~ . ;"'~---I . / ;.--'-/'/ . ·/
Ra mond S. Georae
Acting District~Chief
...
..
•
•
•
....
-.
-·
/
/
/' ., .... ,.
;_ ;-.•
,,, ;ti(JY ' ;_::f·· --\ ::;:.·
. ..J '" .,..,_~ lttrQ· • .,. ..
U niied States Department of the Interior
BUREAU OF LAND MANAGEMENT
Anchorage District Office
4700 East 72nd Avenue
Anchorage, Alaska 99507
2920
' ~ -~. ;rt-O;j!
(OI~l~~
t-1r. Eric Yould
Alaska Power Authority
333 West 4th Ave., Suite 31
Anchorage, Alaska 99504
Dear Mr. Yould:
JAN 3 0 1981
llt.:C~IVED
f'; 21981
/\:..<\SKA PO'/.'~:: ·~ ::-.:~::: fY
This is in reply to your letter dated Janu;1ry :2, l9Sl, questioning the
official nature of the suggestions given during meAtings with the Su.sitna
Hydroelectric Project Steering Committee.
All statements made at these meetings witl1 the Steering Committee are at a
working level and arc not to be construed ns nLM's official stn11d or
policy.
All official Bureau policy and positions conct~r11i.ng thP Susi.tn;l Project
will originate from this office in writing '.vith my si?>,nnturc or th(~ signa-
tur0 of an acting District Manager.
~reJ~
Richard W. Tindall
District Manager
.·
--:~-~~~~r
·.· . ~; . : ... ~ ; : ~
,,:DEPARTMENT OF THE Ah:,VfY
REPLY TO
ATTENTION OF:
NPAEN-PL-EN
Mr. Eric P. Yould
Executive Director
Alaska Power Authority
ALASKA DISTRICT. CORPS OF ENGINEERS
P.O. SOX 7002
ANCHORAGE, ALASKA 99510
RECEIVED
FEB L;l9Sl
t.JJ>..SKA POWER NJIHCRIT'f
333 West 4th Avenue Suite 31
Anchorage, Alaska 99501
Y'c:..
Dear ~~uld:
Tl1is is in resp:>nse to your letter of 2 .January 1981 concerning
consultation with the Corps of Engineers on your study of the Upper
Susitna River Basin.
FE 8 0 G 1981
As stated in our letter to you of 12 June 1980, 1ve are unable to
participate in the Susitna Hydroelectric Project Steering Committee
because of funding and manpower constraints, and we vJill only be able to
conduct the necessary reviews required for the issuance of permits under
our regulatory program.
I vJOuld suggest that the seeping process prescribed in the regulations of
the Council on Environmental Quality (see 40 CFR 1501.7) be initiated.
This process, which would involve the Federal Energy Regulatory
Commission (FERC), would help to define the scope of issues to be
addressed and to identify the sig1ificant issues to be analyzed in depth
in tile Environmental Impact Statement (EIS). 1he Corps could participate
in the seeping process and, possibly, become a cooperating agency with
FERC in the preparation of the EIS.
If further details are desired by your staff, Mr. Harlan Moore, Chief,
Engineering Division, can be contacted at 752-5135.
Sincerely,
£_.
LEE R. NUNN
Colonel, Corps of Engineers
District Engineer
-
...
...
...
...
...
...
...
...
...
-
...
-
...
-
-
-
-
...
l. -'~fd States Department ofr:-_~t-'Ie Interior
--.;,'t:i:-1.01 ~17, ,_, HERITAGE CONSERVATION AND RECREATION SERVICE
--~1-.
!i
-
-
-
' .,
jl
ALASKA AREA OFFICE
1011 E. Tudor, Suite 297 Anchorage, Alaska 99503
IN REPLY REFER TO:
A800
1201-03a RP
Mr. Eric P. Yould
Executive Director
Alaska Power Authority
333 West 4th Avenue, Suite 31
Anchorage, Alaska 99501
Dear Mr. Yould:
Tde.(907) 277-16()6
FEB 4 1991
REC~IVED
1 C 3 6 1981
ALP.SY:A PCV/:R /;IJTHOR!TY
i.Je concur witb your recommendation of January 2, 1981, concerning the
expanded role of tbe Susistna Hydroelectic Project Steering Committee.
However, we would remind you that we also ll;lVe '-1 separe1te coordination
~md review function ,1ssociatcd t-Jith the 1 iccnsc appl ic<1tion Exhihi t R.
Thank you for the opportunity to consider and comment on the proposal.
Sincerely,
/-:' I I 1 I -/I I ( / Ct t:-f
j~net McCabe
RegionAl Director
U.S. E t~::·.~:'o N MENTAL P R 0 T E C TIc,:-: i : < G EN C Y
~~;~~;.; ':~··:1
"''~~o sr,.,.,
..:>"" ~.J>
i ~ ~ s~~ ~ '(
-:;. ~
«'1--.p '""~L PRO't.G
REGION X
1200 SIXTH AVENUE
R E. c ~E!Airti 0: ' w A s H I N G T 0 N 9 8 1 0 1
r· I= ',\ .;·) 1 (I 0\ \ .... _, ~~ ll.
REPLY TO •
ATTN Of: M/ s 443 'h':J·,·:x.: .. rov·: .... ~ ,.-·"·--'!<:f't
FEB 0 5 1981
Eric P. Yould, Executive Director
Alaska Power Authority
333 West 4 Avenue, Suite 31
Anchorage, Aiaska 9950i
Suoject: Sus1tna Hydroelectric Project Coordination ~rocedures
Dear Mr. Youlo:
Tnank you for your letter proposing a two-step process tor the coordina-
tion required under the Federal Energy Kegulatory Commission regu1at1ons
and the Fish and Wildlife Coordination Act. We basically concur with
your proposals. However, we may have further comments on the issues
dealt with in this coordination process once more intormation on each
subject is available and the comoined etfects of tne project become more
visible.
lt is our understanding that so far the Susitna Hydroelectric Project
Steering Committee has worked on the procedures manuai for the 1981 f1eld
studies and is now in the process of starting up a subcommittee to deal
with possible mitigation for w1ld!ife impacts. Other issues, 1ncluding
possible mitigation for fisheries impacts, are to be deait with iater
when more information on the resources to be affected w1ll oe available.
We would like to be kept informed of both the steering comm1ttee and
subcommittee meet1ngs and agendas so that we can participate more
actively when items affecting tPA's areas of responsibiiity or expertise
wil 1 be considered. For now, most of our involvement will have to De by
letter ana tetepnone due to personnel and travel constra1nts. With1n our
limitations, we will try to be as responsive and nelpfui as possibie.
~PA's coordinator for this project wil 1 continue to be Judi Schwarz, of
my staff. She can be reached at (2u6) 442-12B5.
We look forward to working with you in the future. It we can De of
assistance, please do not hesitate to ask.
Sincerely yours,
a~~w:tt t&dr
El1zaoeth Corbyn, Cnief
Environmental Evaluation ~ranch
-
...
...
...
...
...
...
..
-
-
-
-
...
-
-
-
-
-
-
.-
/
l _//
~··
-
-
-
-
--~ ~(·•'""''~ ·riJ· ._, ;, ~. 'r#Yj
'"-4ltrl 0!.
f'T;, :: . "".! ..... L• <.. !~'"',
Mr. Eric P. Yould
Executive Director
Alaska Power Authority
333 Wes+ 4th Ave. Suite 31
Anchorag~, Alaska 99501
Dear Mr. Yould:
~
U.S. DEPARTMEIV. --~~ COMMERCE
National Oceanic .., . .J Atmospheric Administration
Nationa[ Marine Fisheries Service
P. 0. Box Z668~ Juneau 1 Alaska 99802
lll:CL:IVED
I_·; l () 1981
;,~ .. \~::.-.. r-:-;.·~:_. ·: ··-;;.~! r'(
We have received your letter of January 2, 1981, regarding the
involvement of the National Marine Fisheries Service (NMFS) in the
planning and study of the proposed Susitna River Hydroelectric Project.
We recognize the need for a "higher level of involvement" on the
part of our agency, not only due to certain procedural requirements
but the fact that the proposal has reached a more advanced stage of
study. To this end we have been participating as a member of the
Steering Committee since July. 1980. We feel this involvement
affords us the opportunity to evaluate project studies and provide
any input we may feel is necessary.
Regardless of our status with the Steering Committee, we feel formal
agency concurrence with all policy matters and deliberations should
be obtained and therefore, agree with the process you have suggested.
Sincerely~/,) , , ~,
~c ' z· ,~[L J ---.--~ -/. /~
~-
Robe t W. McVey ~
Dir,tor, Alaska fle9ion ~
I
/
..
•· t:
!'
L.
~
i.
I
IIi
:. ~ ~
:, ~:
F~
I
I
I
bt
: ~ ~ ,,
.,-. , ...
:
f .
._
: .~:~.
L:::·
-~ I
I
' '
I
i ......
H·· ·:~~:
. -_:·l!:.:~;:~: · ;:~;;:~ ·: :::; j]i{::::-~fi~~~0Ilill~illilli. T~IiW;~~~~~l.:~~~i±!ci1;}~;;r~s~ .. ·;:_::·:·_·-~;~:2~2 :;;,: ~~-c: -·: ~:::~:::~:~: :~~~~~~1,~t1W!
01·A3l.H
. ·-~ .·
·!
e ~--' 1
~~~ 16\ II rc rrr rc ~ n ~ ~ n \ N I JAY s. H~ONO, GovomO< .. ~ U ~ U l_S ~ U i;;j l1 fl-t1 ~--lf\. J~\ I
' J
I
I OFFICE OF TilE GOVERNOR
DIVISION OF POLICY DEVELOPMENT AND PLANNING
POUCH AD
JUNEAU. ALASKA 99811
PHONE: 465·3573
February 19, 1981
~1r. Eric Yould
Executive Director
Alaska Power Authority
333 West Fourth Avenue
Suite 31
Anchorage, Alaska 99501
Dear Eric:
l . -C '._ I \' ~ D
FEB 26 1981
J'.,LA.S':'J'-'fQ\'Y-·· •·~, .. ~,,iiY
On January 3, you sent a letter referring to consultation and coordination
with various federal, State and local organizations in the study and assess-
ment of potential effects of hydroelectric development in the Upper Susitna
River Basin. Your letter requested my concurrence with your plan or
suggestions for its improvement.
Frankly Eric, the paragraph in your letter that describes your plan is
somewhat brief and general, making concurrence rather difficult at this time.
I agree, however, that the study being undertaken is one that should have
a very high level of involvement by interested State and federal agencies as
well as potentially affected local communities.
I suggest that a more detailed description of the workings of the Susitna
Hydroelectric Project Steering Committee be provided. What may also be
appropriate is the use of your public participation staff to serve a state
government coordination as well as a public involvement function. The
staff could document and disseminate the proceedings of the steering
committee to a wider governmental audience. Such communication could occur
prior to formal Authority position formulation and smooth the process of
required formal concurrence with such positions.
As for meaningful involvement of State and federal agencies in your assessment,
I am enclosing a copy of Administrative Order No. 55, describing the Major
Project Review (MPR) process. This process might be appropriate for the
Steering Committee. The process described can be used by any unit of State
government and is designed to ensure that appropriate State agencies are
involved in analyses from the outset and that each assessment is highly
issue oriented. The technique can be used to involve federal agencies and
the public as well.
..I
....
...
-
-
...
...
...
...
IIIII
...
-
-
-
-
-
-
...
.~·;/ •'!'!·
-~ •.
·~· .
....... . :_-
/
'
-
-
-
-
Mr. Eric Yould e -2-e February 19, 1981
The MPR questions can be modified as needed and a schedule can be prepared
that indicates points at which cooperators are to tie in to the process. We
generally include a public review draft in the time line for an analysis.
We have also found that it is essential to the success of the MPR process for
the lead unit to be able to sufficiently detach itself from its own project
goals and objectives to administer the analysis in a neutral and objective
fashion. One solution is, of course, to have the analysis administered by a
separate agency.
Eric, I hope that at least some of these ideas are useful tci you. From your
letter, we are not too certain as to what involvement process you had in mind.
Please let me know if we can be of any assistance.
Sincerely,
Frances A. Ulmer
Enclosure
'-
Sta.-cc: of Alask.a -~~=~nistrative Order No.: ss-e ...
S;.;bject: State ~lajor ?rojec;; ?.e·.•ie·-· ?recess
L1~ce::-the au-cho:ity of Art. III, Seccio::s l c.;:d 2L; o£ trJe J..lasLa Co::sti-_,
:ution, and AS 44.19.880, and given ;::"le need fer-ti.r:Jr-ly, consistent, and
thorough evaluation of proposed ~ajor pro ects or ac~ivities, I order
that tt follouing revie~ process be inst tuted: -
l. Certain projects, because of thei:-sta;:e·-·ide oT regional significancE '
\.:ill be designated byrne as ;:;;ajar p-zojects subjec'C to a l:.C.jcr ?roject.i
Revie'-' .
2.
;),
' t.;,
~·
. c.ny state agency to \.."hich I assig!i tne lead res?onsibili-cy for
conducting a >:ajor Project Rev:!.e·~· st-,all ;ne?are 2.r:c subwit to oe
the infor.:.a-.:io:~ co~tained on t;1e ?roject .!.,:ic.l;·sis Su:::::-Jar:·· S!-leet
( . .:..ttachment ;..) · .. :ithin 10 6ays of t·r,e .:ssig~ei'l't.
By the assigned date, the lec.6 agency s~all :renare and subsit to
me a preli~i~ary ?rojec~ Analvsis ~~ic~ add~~~ses :he evaluation
factors S?ecified by ~e (At:ach~en: 3).
r~~e~iately upon receipt cf :he :re:~~~~ar~ ::-:-o i e c;: .~. T: 2. l \ • s :. s 1 tne
Division of ?olicy DeveloJ~ent a~~ Planning (,J?:)?) Office of -che:
GO\'ernor, sha.2..l fo:-._·c.!'C i::fo:-=c.~io::2..l cc;:.:.es Lo ecc;; cf:e::::ed or
i!ite.reste.d gO\lE.':":-LIIer:~al c~e.~c;·. =:: L·:-je c.ss2..~::~::c. Ccl.es c.cc~. c.gency
s~all sub~i: to D?D? its revie~ and cc~5ent.
During the period of agency reviev cf the preli2inary ?ro~ect
Analvsis, the Public ?oru~ or D?J?, in consu:i2tlon vith t~e lead
shc:ll conduct one or cere ?ublic ~ee:in~s in t . ."'1e c:.ffected
...
-
...
IIIII
-
...
c:genc:y,
area(s) for -che pu ryose on the project . -. . . ... . o:c rece::.v::.ng ?UCl::.c cc:::t:Jer.ts
' ,... .....
I •
or c:ctions.
By the assigned date, D?D? shc.ll 5 ' '~ ... ,.-, i ~ ..... ........ -~ in '-":':itins to t:r;e iead
agency, c. su!:.:nar;:. of the revie·~· zlong ·~·ith :-eco;:;::enda<:ior:s for the
final Pro~ect Analvsis.
3;-. the .:ssigned date, che leac agency, i;-; co~jl.!nc"C.io:-. ·~-i'C.h D?D?,
shall prepare a7'ld subrr.it to r:~a, ir: ·-7iti"-g a:1d verbc.}ly, a final
version of the ?roiect .-L.nal,·sis. Tne ?ro"1ec-c .:.,T'1ah'sis si-,all include
...
...
-
dissenting \'ie\..'S, recc::::::e<lcc.tio;-:s :or fur-c·ne:: acc.ion znd, · .. ··nere -
" c.
appropriate specific ~onciitions or ;:;i;:ig.:-cic~ measures necessary
for state approval of :he project or ac-cion.
No desig~aced ~ajor projecc or c.c:~c~ ~:ll
completion of the process described above,
~aiver of necessity has been obcained ~roD
be ap?roved ~ricr to the
u 11 less 2. ? r : c r · ... -:itt e :1
D~.
9. Tr.e revie·-· S?ecifieci i:~ c.r1is crc:er .c':.;:l~ ~E: coorcin.:ote~ ·-·it'n proce-
dures contained in AS '6.:5, ~nvirc~~e~l.2l ?roc~ciure Cocrdinc.tion
Act, and ot~er sta-ce revie~ p:oce~sE:s, c.s z~?l:cable.
-l-
-
-
-
...
-
-z--
-
-
-
-
-
-
-
-
-
-
-
. -
-
I -
! .;
/:!~
/
I
/
I
~I
/ ,.~:
....
• . ' .~. t t c c ·~. ~; e: n: .-. • -S ~::.::-..: :-y She u
S T .L:T::: ~-~!_j 0 ~ ?? O.J:: C T .!~,· _:_:_ ·~· S ~ ~ ....
?:oiect Title -Desc:i<;tion
3rie:f· description of
~~cl~di~£ loc.:tion of
scope, nc.ture, and
?r-oject, esc.i:::c.tec
ob~e:::ives
s::c:rt c~JC
o£ p!"ojecr.
c c::-, ::J ~ e t ion
o :-c. c. t 1 en ,._..
C.cte,
e.sti-.:c.ted cost of project, stc.c.e in-ceres;: ir: projecc:.
St.:te Action Recuested/Recuired
:r:::-::-.::.ts sougrH, ·oy agency; resou:-ces necessa.:-y; p~·:>lic f2cilities
co~S'Lruc'Led; r.line:al or other rights, co:or.:c.c:.s, le2ses, etc. .
Lec.d ;..;£enc:·
:a be
Leaci ~gency responsibility, inclu~ing de~i~~a:ed ~e:sc~ :es?~nsi~le for
?:eject A~c.lysis.
~~e~cv ?c.rticicatic~
.,
..
.,
....
O:~e: c.gencies and indivi~uals assi&ne~ to t~e ~:o~ect analysis e~fort ....
anc tnelr resoonsibilities. ?rcpcsec cc~t:act~al ~sslstance.
~sti~ate6 Cc~~letion Dates ...
~--li-i~-~)' nrnJ"ect t--lvsis ( ;-y~ ,. .:., 1::: -~··-oJ.C..., "' .. ._.. otiC:. .; --,_,C..-_.
~ .... ,.....,_ ~ . ' ~.:o\•e:no::-s c:ssJ..gr-e;en )
~ce:~c'' -nd "\.!"lie "Pev'e"-' ( ~-··~ • • =: • _. C:. ~ • ....., --o'l. J... --I.... C..'-: :-C:7. -;) __ .,,,..,.,, ___ ,, p,..o'cc-_i-,2.·
• _ t: ~ ...:.. J ~-- ' 1 C. • _-... • • _;; ._ L -J
Sl.!~~arv Report ( ~avs . ---'
Agency and ?~blic Reviel :: :-c:::
?i.:-,c.l ?:-oject .~.~alysis ( 6c:ys I! C:: Su::.;:2.7:y ~-~o--) J\C.-J.. t...
....
....
...
....
..
-
-
-
V)l .. ~
1-
0 ,_,
u
oO
c
0 ,_,
••J :l
•IJ
/
.d
·-· u
llJ
0
1--
·1 ..
<J~
~ ...
J
u .,-
··:
l) .::
(.)
u
ld
... ,'c,'"'
'
.--
•U c
0
VI
l-
(j)
0.
ru ,_,
t-:-)
•<J
(_)
L
1\1
U.
'" UJ
I ..
c:
·u
UJ
1-'
•U
>. ..
UJ
c
(\}
C.H
lU
_()
·a
::1
0 ::;:
Vl
OJ
01 c
IU
.c
u
~J
IU .. c:: ·--...:;..
""'--~
' . ;;;~
_,_,
u
<U . ..,
0
L
()_
OJ
.f: ,_,
.,_
0
(\) .,_
llJ
.. c
.jJ
L
llJ -· 0 .....
Ul U)
r: tU
1U Vl
.:-:'. tU
u, _c
•U 0 ..
''(
ll)
.• J c
c 0
tiJ .,-·u _,_,
•,--•\.J
Vl I-
OJ QJ
I-0 ..
0
.iJ
c ·o
<U c
L IU
~-
::1 c
u 0 .,....
1-_,_,
0 u ,,_ :J
1-
<IJ .f..J t=: Vl
0 c
u 0 c u
}
0
·1-l
"1.:.1
(1)
·1-J
u
l]J
0.
)(
UJ
VI
(I)
LJI
·= <\)
.t::
u
L..:
LJ
,_,
•U
,-
:J
0 ..
0
CL
YJ
c
nl
~J
c:
CIJ , ..
_;.,
0
n ..
E:
UJ
OJ .. c
_, J
UJ
L
1\J
.iJ
•U .c:
N
..... _,_,
u
OJ .,,
0
1-
0 ..
w
.C.: _,_,
'= 0
!.. .. ,,_
_,_,
r-
::1
Vl
Ill
1....
J
>-.
J)
·o
()J
Cl ..
~J
u
u
0
tU
_{)
0 ,_,
u
llJ _,_,
u
lll
(.1_
)(
l}J
(\)
I.
Ill
U)
JJ
0 .,,
'1-
0
c
0
.j.J
!....
0
n.
0
1....
0 ..
-IJ
flj
.c :c
otJ
J
.....
Ul
c
flJ
.::.L
VI
Ill
"'-(
.jJ
c
llJ
I-
I-
::1
u
)
J
>--,
-1-'
,-
Ill
t:..:
n
VI ,,,
til
VI
Ul
_L)
(_) .,--,
\lJ
VI
dl
.L:
·I·J
,._
()
VI
u
·t·J
'"
1-
Qj
-1-'
u
•tJ
\-
Ill
.. C:
u
OJ
.. C
.jJ
tll
1-
ll.J
-1-'
Ill
.C ---
.t:l
('·
-~
t
CIJ
.tJ
(._))
c::
0
,--
(~
<I!
-1 J
I
1-'
I.
()
.c:
vi
>,
1 ..
Cl
L.J I
Ill
I'
•U
u
ll) c.:
0 .. ,.....
-IJ
•U
t)
::J
u
u
0
.-
UJ
>
UJ
.,-
_\t.
VI
J
r-· >) ... ....
,--
n
Ill ,_,
VI
l)
r:
0
1._
CJ
L!
UJ
c
:.-)
L
l)l
c:
u
0
.j.l
I)) ,_,
::J
.. 0
1-
-1_,
c
0
u
jJ
u
OJ .. -,
0
L
I)_
UJ
.c
-I.J
VI
OJ
0
(~
{q
J
-J..i ,-..
::J
V)
Qj
J_
0 _,_,
-u
Ql
·I J
u
L]J
n.
)(
UJ
<II
1-
nJ
tfl
I I
l)
Ill t, ..
~ I ·-
UJ
())
u
I-
D ..
r· c
(JJ
1-'
I
01
c:
0 ,-
1-
0
_,_,
1-
0 .. c:
vi
~J
•<J .. c
=~
('·
-1-1
u
Ul .. ,
0
1....
()_
(\)
.. c
.j.l
I~
0
I-.,_
Ill
.C _,_,
_,_,
u
1]1
11-.,_
·0
Tl
~-1
()
5:
_c
L)
.L-.:
::,:
,_.
V1
/(
UJ
VI
_:..~
u
0 ,-
.. 0 ·a
IU
0
I-
llJ
·IJ
IU
~
·1-'
V) ··-c:
c: ·o
Jl)
-1--'
•d .c :.:c
, ..
J
1'-·
·I-'
u
UJ
·r)
0
I-
D ..
ICJ .,_
0
>,
·I-'
.. 0 ··-
V)
IU
Ill ,,_
u .,-
I~
0 c
0
u
(\)
J
0
c
QJ
f()
.-,........
UJ :.:.:
>
-1--'
c :J
f::
t'
L..J
J
1-
0
.... ~~, _,_j
r-.,-
0
•U
,--
IU
"'
>, ,.
>U
:J cr
I] I
_c.:
·IJ
c
·a
OJ .. ,J
u
UJ
0.. )<
Ul
OJ
1--
IU
VI
OJ
01
c
Ill ..c.
u .,J
Ill .c
('-.
VI
OJ
•r-,_,
LJ
IU
'I-
1-
0
V)
(\1
LJ
::..--
~
Ill
Vl
VI -u
0
0
01
r-
IO _,_,
c
Ill r= c
1-
l\J .-
0
01
L
0 ,,_
·cr
c:
Ill
I~
liJ -a
J
>, _,_,
.J.-1
Ill
o<J
Ill
L.'l
Ill
.,,
Ill
I'
I_)
<!>
r:\
;...:
<J)
1•1
t::
u
IJ
-,_,
l:
0
u
("J\
c
VI :-,
()
.c
c:: ··-
Vl
Ill
LJ> c
IU
.. c
(..)
liJ
~
..:(
'"'
<'-·
,-....
>-, _,_,
.,.....
,--
IU
;:J
u·
tll
u
-r-
1-
n..
J
I])
.,..J
tl.J
1-
-u
c
IU
·I J
r: :-.)
n r::
ttl
LJI
(\)
·u
IIJ
·I J
Ll
(jJ
(\.
>(
UJ
OJ
~
•U
1./1
Ill
U>
c
IU
..L:
u
c
0
·1--'
f\)
,--
:J
0..
0
0 ..
r-
•U
u
0
-jJ
1\J
.. C:
I'')
_,_,
•U
:J
(\.
0
D ..
lJJ
L
-c
I'·
VI
IJ
c
"J
1 ..
lJI
1:
l:..:
't'J
UJ
·-· u
<II
(L
~_;;
'1--
(_)
l./1
u
IJ
VI .,-
~
UJ
·I··'
u
o<)
I-
I\)
.L:
u
tlJ
C.H
c
"' . ..:.-:
LJ
.,_
0_
~· .jJ
u
,-.,_
c
0
u
ll!
,--
, ..... ,
1-'
"' I)) .,
\..
CJ
Ill
:~J
.u
·1-1
l·..:
Ill
u
II·-
l-:-.
(n
VI
Ill
VI
:J
H)
u
0
·1-'
·o
!II
.,.J
u
Ill
0.
:.<
(I)
VI
Ill
t_J\
c
IU
.c:
u
('·
Tl
!.II
.,.)
u
Ul
CJ_
;,(
(])
V1
c:
u
1-'
•U
I)_
~)
( J
l)
0
•ll
·= 0
·I-)
·u ,,,
.,,)
I~
1.)
I-··-
·I>
c:
l]l
IC:
Ill
lJ
/\)
0 ..
VI .,.-
·u
V)
Vl
c:
ttJ
r-
0.
QJ
V)
;J
""1."1
.:_:
"'
,~.
Vl f •
IU ll1
.JJ )'
.n .,.
t:
''-' u
til
1/)
.\i
c::
•\l
f ) .l.: ·= l_J
til '" 1:0: 1"02
Ill
01 01
f\J c: c: -r-
ltj .fJ
E '" I-
-'-UJ
~-' c.:
): QJ o en
t_ 1
01 '" :i c
1\l tlJ
u >
0 Q1
L.
Ql
1-'~
'lJ .,
:J u o-c
H 1\J
Q c
\1 ·r-·o
::l 1-
::l 0
,.
~::,:~oc
. ::~
1
til
.c
.,J
·n
I-
"' :c
t) _,_,
<If
"l."J
<II
iJ
•'-'
1-'
lf)
·u
r.
•V
.u
L}
0 ......
·•-' c
UJ
1::
·1-'
r:
IU
lf)
u
J)
: l
~-
lf)
.....
•ll ..c: :.-c
tO
I
f'-·
~J
u
Q1
''I
0
1-
0..
·o
UJ
V)
0
0..
0
L
0...
·-.......
1
1\l
u
lf)
lt_
"--
1
OJ
·1-'
•tJ
.tJ
V1
'•--
0
til
u
L.
•t.J ,-
"' _I)
·I·'
Ill ..:.:
<II
.C
·I-.)
c:
()
UJ
IU
..c
·I-'
u
Ul .,-)
0
I-
D.
Ul
.c
·•-'
·u
:::1
~ _;..
·1--'
u
Ul
'1-
'1-
UJ
·1-'
IU
. .c
--'-
('-·
lll
1:;
·1-'
1-
(IJ
:::-
0
vl
(JJ
:J
c:
uJ
:::-
UJ
' ~
Vl
:::J
lf)
1-
UJ
>-
VI
OJ
1---
::J
IJ
u r:
UJ
0.
><
()/ .-
1\)
u
0 .-
u
r:
''-'
1
.c.: •
.JJ .. -
'>
I
f'-•
·u v1
<II 01
·J-1 •r
rl.l LJ ··-u V1
0 .£1
V) :J
VI lll
<U
.C:
1/l ()
Ul :"J
IJI
·u
'I··
VI 0
.f. I
:J ·I J v' r:
Ul
Ul 1-'
IJ :,(
1LJ OJ
·1-'
Vl tlJ
.c .,J +J
u Vl
·.-
()_ ·1-'
1:0 •'-'
1---
0
·..c:
"J.
0
.jJ Vl .,-u ,,_
.-
f).
X l'·
UJ ~..J
LJ
IU OJ
L ··>
UJ 0
.c t_ _,_. 0.
<JI Ill
I-.c
..:( ·1-'
0-1
)
1
c
0
-I-'
IU
1'-l
·I-'
::::1
(IJ
u
L
:J
()
v'l
tll n:
1/l
I'~ .,-
·I--'
c:
IU ....
0
r:l.
>,
L .,J
VI
:.1
·u
L:
Ill
()
1. . .. ,
0
vl
01
l.
c
0
tiJ
_..
1\J
.c
·1-'
u
(\J
.,-·)
0
I-
Ll.
Ill
.L:
~J
........ .-··->-
·1-'
1..1
QJ
··-,,_
OJ
·1-'
1\)
_t~
-~~
1/l
I-
OJ
;-
OJ
1-
L ·.-
c.:
I·' .-::J
lf)
<II
L
1-'
t.l
Ul
.• -J
I)
I.
1.1.
'" _l· ~
·I J
::..::
('-·
vi
tll
:::1
1\)
>
UJ
u
L
:::1
0
VI
UJ
L
I-
ll)
.C:.
·I-'
0
1.
0
I
C'·
ul
·1-'
c
UJ
EJ-·• ··-E
0
u
UJ
u
:J
0
v.
(lJ
L
1
L
Ill .c
·I>
~
()
1/l r:
0
·I·' ,,,
::-' r 1.
0
0.
(lJ
'I-
·o
·,·--. _;..
'\':)
c:
1\)
...c:
VI
·r-
'1-
·1-'
u
(lJ
'1-
'1-.. ,
~-'
u
OJ ... ,
0
L
Cl.
(!)
.c
·1-'
r-.,...
_.,:
('-.J
(]J
-P
1\J c
c.
E
!...
01
·I-'
I
(Jl
r.
0
I.
(_)
E
L
OJ
,J
I
·IJ
~
()
.C
VI
tll
.D
Ul
·I-'
u
llJ
'1-.,_
UJ
OJ
U'l
QJ
.c.
~J
........
.,-
:,:
f'-•
·1-'
11..1
·1-' .,-
.0
rt.J
...c:
1
1\.J
())
0.
E
1\J
~j
,_
0
lt ..
I'-•
VI
<II
u
. 1-
:J
0
V)
Ill
1--
OJ
u
c.:
([I
·1-'
V)
VI
.[)
:J
1/l
·1-'
u
(!) ,,_
'I-
I\)
.JJ
u
llJ
''I
0
1....
()_
Ul
...c:
+-'
,--
:!:.
(•')
ls ..
0
r::
0
.,_ ..
1\J
u
0
Vl
·u
t/l
ill
u
Ul
Cl.
Lll
.,_
0
VI
Vl
()
lf)
c
1....
UJ
·I-'
·I-'
t\J o_
c::
0
.jJ
tU
}....
01
E
c
lll
OJ
01
r::
1\J
.C
u
,~.
·o
UJ
·I-'
u
(]I
0.
)0:
<U
"' OJ
01 c::
10 ..c:
u
>~
~J
..0
1\J
.,-
•\)
:>-
1\J
I
1-
<'!'''
,.-
•r-
:;.:
·n
Ill r::
I,_
OJ
·u
::, .-
HI
u
.,_
lJ
ljl
r: •.
VI
1....
0
·o
lll
.• J
ll)
c
01
VI
(JJ
·o
-1-'
u
OJ
'I-.,_
ILl
-1-'
u
QJ .,,
0
L
0..
(II
.c
.tJ
··-=~
-:J·
J
('-•
VI
.tl
<II
l-
oU
u
c
IIJ
u
VI
1-
0
,-·-
•d
1-
0 ...... .,.J
<U
Ill
L
u
UJ
1....
·o
IIJ ... c
lll
1....
Ul
··-· rtJ :::,:
u ··-t_
0
·1-'
1/l
.c.:
I
>
-I J
<U
:1
0
,........
.u
·I·' .-:
Ill r= 1:
u ,,
., -
l: ,,,
c
1'~ t::
0
L
·.-
> c:
(].I
Ul
.c
·I J
c
0
·I-'
u
OJ .,-,
t)
n.
"' .C
I·'
'•-·
0
VI
·1-'
u
Ill
'1-
'1-
\]I
·o
'" ··-· 1\J o.·
u
·.-
-1 J
c:
1\J
Ul
.J" .....
(II
~-
1\l
·1-'
Ill
..1.-:
f'-·
'" u
1\l
.--:.)
n.
0
[l.
Ill .l=
4-'
1,_
0
>,
·1-'
QJ .,_
0\)
VI
L
0
.c:
·I J
<lJ
til
..c
1.
u .-
,.-
··-
IU
>
l.
:I
VI
tJI
(_:
., -
I.
d
I J
t:
I)
l:
•II
,J
I
"' I: r:
u
l
~
c:
OJ
1..
0
'I·
lll
c
l)
Ul
>
0
l.
Cl.
til
.c:
·I J
UJ
l-
It)
.,.)
•tJ
.c
l'-1
I
f'-•
0
L
.jJ
c:
0
u
::,
·1-'
........
ttJ
::l o·
·u
c
ttJ
I
I
N
... ,
~\~
'.t
.. /:
i
•'
1.· 'Joes tJ project involve techno1og~c" c.'"'"~ c---""-·· _,,, 1 r ... ":::n .... ::: 1, 7~nc.r:cic.l,
or economic fc·c~crs ~·hl'c'n 'nc"\'E c:· h~lc'n ~c~~~c.e r: urc----· . . I.
• ' -\.; '; ' -u 1 I ;:: 1 ·-::. I jj ";: y Q r I i 5 f,
2. To what extent is the existing dc.tc. b2se 2aecu2te to answer the
c.bove questions?
j~ r".rP ~hpro_ E.X7P-,nc"1 -~·::.c-TorS (e G r·""l'on-·1 ~ ~ "" . . l) , -•-•-I <..: • ._;., ICL. C Ul Jn~oEinC."C.iOI\c
which fig~re prominently in the success o~ fc.ilure of the project?
1. Are there econo~ically feasible c.nd soci211y c.cceptc.ble
alternatives for accomplishing ~ne cbjec:~ves of the project?
2. ~hc.t wsu1d be the i~olicc.tions 07 nc~-c.~J~DV21 of t~e project?
l Is the proposed project or c.cticn cc:7i~c.~·~ole v:~th lc:::c.l c.n0 s2te
p1c.ns or policies?
2. 'n1hc.t permits, licenses and/or gove.rnment:..l (stc.te, locc.i c.nd./or
federc.l) epprovc.ls are necessary?
3. What 1s the timetable for vc.rious st~ges of the project?
flexible is this schedule?
4. ~hat mitigation measures or stip~1~tions cEn b~ ide~tified to
minimize the conf1~cts or probl~~s iden~~fi~d above?
-3-
. n rE~rn rn
1 r~.c.! ~ ~"~. t~ u t ~ n e ~ ft~;tE~u;
·c:..;_:_;..-
Mr. Eric P. Yould
Executive Director
Alaska Power Authority
333 West 4th Avenue
Suite 31-
Anchoragt, Alaska 99501
Attention: Dave Wozniak
(?~
-:......-
nLC~lVCD
MAR ? 1931
;,v::;::r., ro·., ..;,; "J .. ·.~,mY
February 24, 1981
P5700. 11
T. 730
Dear Dave: Susitna Hydroelectric Project
Steering Committee Comments
Enclosed is Acres response to the Susitna Hydro Steering Committee comments.
Please review and identify if further clarification is required. We are
presently in the process of reviewing potential program modifications.
Areas under consideration include:
- a lower Susitna Boater User/Navigation Survey
-estuary studies
-advancement of Phase II socioeconomic studies
-Lower Susitna vegetation, moose, furbearer studies
-recreation components of Subtask 7.05, 7.07, 7.08, 7.10, 7.11 and 7.14
-sociocultural studies
We will submit our recommendations with support documentation in the near
future.
KRY /l j r
Enclosure
ACRES AMERICAN INCORPORATED
,, ,., •· :1t; t::).; · :.•e: s
.[ (·<:, ::.·
f•;("'' ·~·\·
,'!,. ··, ·! ( ; . ; ~' ': :. ' '
".!'.; r:: .l:!
Sincerely,
,/ /
/,/ '''
/(, /'j 7, ''. ,( Vl..-"1.. / .( /~: . . ..
c John D. La\·lrence
Project Manager
~
'/
..
...
...
...
..;
'1111111
..
...
-
-
...
..
....
....,
-
-
...
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-....
-
-
...... .... f~. ~~.;.~~ ;·
In response to the Susitna Hydro Steerinq Committee's review of the TES pro-
cedure manuals we submit the following:
Introduction
We appreciate the time and effort expended by all the members of the Steering
Committee in their review of our procedure manuals. In general our responses
are (!"irected towards each of the specific comments as presented in the
sythesis prepared by t·1r. Al Carson. Comments presented in the introduction
and conclusion are addressed first As appropriate our response to some comments
are combined to present a clarification reqarding subtask interactions.
General Comments
1 ) In defense of our subcontractors it was not our understandino that the
purpose of July 17, 1980 meeting was to review the environme~tal studies
but rather to compare the requirements of FERC to other federal and state
government permitting agencies. In this context an overview of our
environmental progra~ was presented. We concur that in some of the more
controversial areas i.e. socioeconomics, adequate study details were not
avai1ab1e.
The offer was then extended, and agreed to by the Steering Co1nmittee, that
procedure manuals be made available for review.
2) As the Steering Committee have stated "the most compelling need is for a
well-conceived process to improve linkage and coordination of the various
studies." \·Je concur that this is essentiol and have expended consideJ'able
effort in this direction. Some misunderstanding rnay have precipitated
from the review of the procedure manuals as these manuals were prepared
as practical subtask-specific documents designed for (1) exchange of
prr)()ram design details (2) control of adherence to the study program
(3) and assurance of continuity in the event of changes in project per-
sonne 1.
Our coordination efforts will concentrate on the following areas:
1) interaction among study participants
2) informal interaction with government agencies to acqujre insight
into concerns and general policies
3) formal interaction with government agencies to allow input and
review of study design, development selection, project desiqn and
mitigation planning ·
4) interaction with the public in the form of information supply and
input into the decision making rrocess
Documentation of coordination to date will be included in the environmental
annual reports to be available in April 1981. In addition we have requested
TES to prepare an outline of their coordination process which will be supple-
lnented by Acres and supplied to the Steering Committee for review if desired.
1
··7 *'·--WW~~.o.~.;wi&&ll• wai ..... ¥!71~~ .. -..... --··------
~ -... : ':.:_~ .;_";.·
3) An area of primary concern appears to be the extent of effort directed
towards studying the Lower Susitna Basin between Talkeetna and Cook Inlet
during the Phase I period.
Our approach to date as outlined under Subtask 3.10 of our POS is "to
estimate the flow regime, sediment regime and morphological characteristics
of the lower Susitna River under natural conditions and (prepare) a
preliminary determination of morphological imracts which could result
from flow regulation and sediment trapping at the Susitna Project."
"A preliminary evaluation of the potential morphological changes, and
impact on the river characteristics due to flow regulation will be made
during the early part of 1981. If considered necessary at this stage, an
expanded field data collection and study rrogram aimed at evaluating
impacts in more detail will be developed in conjunction with the DNR and
presented for consideration to APA."
It is our opinion that the results of this study are necessary before
the merits of any detailed downstream studies can be fully assessed.
It is obvious that we require a more comprehensive understandin~ of the
resource agencies concerns, the reasons for these concerns and the study
approach they would like us to adopt. To facilitate this TES during the
month of March 1981 will contact the respective agencies directly, to
discuss these and any other concerns that ~ay exist.
2
...
...
...
....
...,
...
...
-
-
...
-
-
...
...
-
"""
...
-
-
-
;;::--
....
-
-
-
-
-
-
-
-
-
-
...... ... ...:..:....:--
7.05 Socioeconomic
Although major projects like the Trans-Alaska Oil Pipeline provide justification
for the need of adequate preproject soicoeconomic analysis, care r1ust be taken
in making direct comparison as to the types of impacts associated with a large
centralized project such as Susitna vs a transie~t type construction associated
with a pipeline. Susitna should produce a relatively self contained, controlled,
centralized work camp established for a 10-15 year period. For this reason a
first step in our socioeconomic program, through a review of other similar
type projects, is to identify the most probable types of impacts to be antic-
ipated. Our studies will then concentrate on these areas of most probable
impact .
We have, however, for some time been considering the need to advance some of
the Phase II socioeconomic studies into Phase I. The extent of changes in
scope and timing of our studies will be discussed in more detail with the
Steering Comr:1ittee and FERC followinq their review of these responses.
To present a clarification as to the comprehensiveness of our socioeconomic
prcgram a listing of categories and variables being incorporated into our
socioeconomic profiles is attached (Exhibit 1). This listin9 is refered to
in our response to the seven Steering Committee comments.
Comment 1:
Local and regional recreational facilities and opportunities should be
assessed to determine the ability of those facilities to handle additional
users in light of increased demand.
Resronse:
Recreational facilities will be addressed on two fronts within the
context of the Socioeconomic Analysis during Phase I. ~ark Package
2 entails development of a detailed socioeconomic profile, the
methodology for 1vhich is described on pages 7-10 in the Procedures i,1anual.
" ... The profiles will include ... public facilities, availability,
ad e q u a cy , an d c o s t. . . " . T h i s i n c 1 u de s pub 1 i c r e c rea t i on fa c i 1 it i e s . To
the extent applicable in Phase I, this analysis will address the ''ability
of those facilities" at local and regional levels to handle additional
users" as suggested by t:;e Steering Committee.
.1\dditiCJally, we have become aware of a special study currently undentay
by Mat-~u Borough, the results of which will be considered as an aid in
our analysis. Recreational categories and variables to be investigated
are sho1vn in Section VIIlExhibit I.
Comment 2:
The study should address the probability of additional industrialization
of the region as a result of power from the project. Then the study
needs to assess the impacts and socioeconomic implications of indus-
trialization scenarios that would be driven by this project.
3
...... ~
;~ '-<t .. .:·
Response:
In our evaluation of the economic base we will be developing a profile
oft~-major basic industry components. (Exhibit I section V) We will
review potential incentives for industrial develop~ent created by stable
energy availability and assess the socioeconomic implications of having
these incentives materialize.
Comment 3:
The study should address the cost and availability of products and
services. This should also address the inflationary i~pacts that are
usually associated with a boom type cyclical expansion such as con-
struction of a project of this magnitude may cause.
Response:
The availability of products will be addressed under the headings of
wholesale trade, retail trade, services etc. as indicated in Exhibit I
section V. The cost and relationship of cost to income will be addressed
through our assessment of the Consumer Price Index, income and employment
patterns (Exhibit I section VI).
Comment 4:
The study should address the cultural opportunities and how they may
be affected in both positive and negative ways by the proposed project.
Response:
Our present study addresses cultural opportunities under the categories
of:
1) Community organizations, social interaction, entertainment
etc. (Exhibit I section II)
2) Public services -parks, recreation, libraries, education.
(Exhibit I section IV)
3) Recreation -Exhibit I section IV)
-
..
...
~
-
-
...
-
-
-
-
-
-We do appreciate, hmvever, through your comments and comments from the general
public that cultural aspects, especially at the local level, are not being fully
addressed. \.Je are preparing the details of a program to respond to this and .-
will present it to the Steering Committee an outline of our scooe as soon as
it is available.
Comment 5:
The study needs to address the implications of the project on a com-
position of the people who live in the region. An obvious first step
would be to establish baseline survey data in the preconstruction era
so that we know what the population composition is in this area before
construction begins.
4
-..
-
-
-
-
-
~
-
-
-
-
-
-
-
>.;::-
-
-:--;
.,._~
Response:
As stated in the procedure manual, a purpose of Phase I socioeconomic
studies is to "identify and describe the existing socioeconomic conditions
and to determine which are most likely to be impacted by the Susitna
Hydroelectric Project". Sections I and II of Exhibit I identify the
categories for which secondary data on the composition of the people
who live in the region will be collected. The adequacy of this data base
will be reviewed prior to making any decisions regarding program modi-
fications.
Comr.1ent 6:
An assessment of the changes in the sociopolitical structure of the region
that could be expected (to) result from the change in the economy as a
result of construction ... (and) operation and subsequent developments that
would be driven by this project.
Response:
Our study efforts are directed towards an assessment of the socioeconomic
changes that could result from the project. In this context we will be
assessing impacts on local govern~ent services, revenues and expenditures.
In our opinion, however, an assessment as to changes in the sociopolitical
structure of the region resulting from these socioeconomic changes would
be very speculative, not cost effective and beyond the requirements for
a license application.
Comment 7:
(a) The analysis does not address the impacts of the project on users of
fish and wildlife resources.
(b) I refer you here specifically to memos included in the Department of
Fish ~d Game review submittal which indicate that Acres and others
deemed it inappropriate for the Department of Fish and Ga~e to carry
these studies out.
(c) However, in our review of all the studies identified above we find
that neither Acres American nor any of other of (sic) the subcontractors
have included this important issue in their plan of work.
(d) The scope of the analysis does not include any work designed to mitigate
the project impacts on fish and wildlife.
Response:
(1) Due to the sequential nature of our studies the analysis of the impacts
of the project on users of fish and wildlife resources cannot be accom-
plished until the impacts on the resources themselves have been identified.
As indicated in the procedure manual, work packages 8 and 9 dealing with
these topics \'li 11 be performed in detail during Phase I I.
(2) We did deem it inappropriate that ADF&G, cr any other permitting agency
conduct the impact assessment and mitigation planning components of our
study. To do otherwise would have compromised the legitimacy of agency
objectivity during license review. However under all the components of
our study we intend to provide a format for review and consideration of
all potential concerns from appropriate State and Federal agencies
5
Ala.
(3) Refer to response 1.
.... \:.;~:) ..
(4) Fish and wildlife mitigation is not considered as a socioeconomic com-~
ponent of our study but is addressed in detail under Subtasks 7:10 and
7:11 as indicated in the procedure manuals.
Subtask 7.06 CulturaJ Resources Investigation
Comment:
Although this study was not formatted or laid out in a way similar to
the others the review comments indicate that the approach in the scope
and methodology proposed is appropriate and sufficient for the task at
hand.
Response:
No comment.
Subtask 7.07 Land Use Analysis
Corrment 1:
(a) The scope of the land use analysis needs to be expanded so that the
downstream impacts all the way to salt water are adequately addressed.
(b) As an example of a downstream impact which is not included but needs to
be addressed is the issue of navigability on the Susitna River below the
---
...
....
~
...
proposed dam. _.
Response:
(a) As stated in our procedure manual our study area for land use is con-
centrated in the Upper Susitna Basin and extends downstream as far as
Gold Creek. In our opinion the majority of land use impacts directly
related to a Susitna development will occur in this area. Certain land
use components outside this study area are being addressed as part of
our socioeconomic, fisheries and wildlife studies.
(b) As you are aware concern has been raised regarding recreational navigation,
and riverine based recreational/land use activities in the section of the
river between Talkeetna and Cook Inlet. We are in the process of
assessing these concerns and foresee the possibility as an extension to
our fisheries and hydrology studies a program to identify: 1) access
to the river by water, air and land and 2) movement within the river
itself. Any such study would provide input into the land use, recreation,
socioeconomic and fish/wildlife resource utilization components of our
study. The details ___ of any such ' program modification W"nl be submitted
to the Steering committee for review as soon as available.
Comment 2:
There is no apparent linkage or coordination between the land use
analys1s and the socioeconomic and recreational studies.
6
...
...
-
~
-
-
-
-
-
-
-
-
......
-
-
..... ~ . '
·~~
Response:
There is a definite linkage and coordination between land use, socio-
economic, recreation, hydrology, and fish and wildlife components of
our study. Although this coordination exists at the study team level
it is bvious that a lack of communication does exist between the study
team and the resource agencies.
Throughout the remainder of the Susitna studies we will be exerting
considerable effort to bridge this gap and will be soliciting your
advice on means of establishing efficient avenues of communication.
Comment 3:
APA should seriously reconsider the decision that has been made to
delay future land use analysis. The contractors state that data from
other disciplines may be needed to "fine tune" this study. However,
we can assume most of these values or issues and get on with one of the
most critical studies that could provide data to be usect in making the
decision as to v1hether Susitna should be built or not. It is recommended
that APA consider the use of scenarios to describe future land use with
an<i h'ithout the project. A recommended way to begin addressing dovm-
stream impacts is to become informed about the work currently being done
in this area by local, state, and federal agencies. This will help to
eliminate any duplication of work. Once APA is aware of what studies
agencies have done the APA contractors can be tasked to synethesize the
existing studies and complete only additional studies needed to comolete
the scenarios. ·
Response:
We accept the Steering Committee's recommendation that we review and
synthesize the information available from existing studies being con-
ducted by local, state and federal agencies. This has been accomplished
to some extent by our socioeconomic, land use and recreation consultants
however, we will ensure, through additional contact, that all available
information has been acquired. Once obtained vJe will assess the applica-
bility of these studies to the Susitna Project, incorporate the infor-
mation into our studies as appropriate and determine if additional studies
during Phase II are required.
We do, however, identify the need for a recognition of the differences
in objectives and scope between a Susitna Project Environmental Assess-
ment study and studies conducted by agencies under their mandate of
over a 11 Sus itna Basin Resource i'~anagement.
Subtask 7.08 Recreation Planning
Comments:
1. Scope of the recreation planning appears to be incomplete. The total
thrust of the study appears to focus on recreational opportunities in
the impoundment area with the obvious underlying assumption that Susitna
7
.... '----> .... ' .J
'.::...;.'
Dam will be built. What is absent is any sort of assessment of the
proposed project impacts on existing recreation navigation and land
use in the river valley above, within, and below the proposed project.
There is no question that we have to carefully plan for reservoir rec-
reation development assuming there is a project. It is also obvious
that the compelling need that needs to be met today is a valid and
accurate determination of existing recreational values so that this
..
'IIIIi
...t
decision can be factored into the ultimate decision as to whether Susitna
should be built or not. An equally import~nt result would be identification _.
of those values for mitigation which will be required if the project
is built.
2. This study needs to include a documentation of the flowing water
resources and uses that would be impacted by the project.
3. This study needs to document the existing upstream uses of Susitna.
Response:
We have made a clear distinction between 1) FERC requirements for the
development of a recreation plan within the project boundaries and
2) an overall assessment of recreation resources and impacts on these
resources.
Subtask 7:08 responds directly to FERC requirements and is directed
towards a reservoir recreation plan that would be i~plemented if a
Susitna development is approved. Thus the study focus is on recreational
opportunities in the impoundment and surrounding area and does assume
that the plan would only be implemented if the Susitna dam is built.
T f .. ~~t·.. ~~d h . he assessment o ex1st1ngt'/eC'reation resources" an t. e 1mpacts upon
them are addressed under appropriate subtasks, specifically 7:07 -
Land Use Analysis and 7:05 Socioeconomic.
Subtask 7:10 Fish Ecology Impact Assessment and Mitigation Planning
Conment 1:
It is acknowledged that none of the reviewers had a comprehensive
picture of how this task will be carried out. The reason is the
Department of Fish and Game will be actually doing much of this work
as a subcontractor to Acres American and has not had tl1e staff or the
resources necessary to put together its procedures manual for this facet
of the work. The comments given below should be qualified with ac-
knowlAdgment of this fact.
Res pen se:
ADF&G have made substantial progress in their fisheries data collection
program. The present emphasis is to establish the basis of their
program and to implement the field studies. Following this, detililed
procedure manuals will be prepared and should be available for Steering
Committee review by April 1981.
8
IIIIi
-
..,
-
...
-
....
-
-
...
-
...
-
-
-
-
-
.._..
-
-
.....
-
-
..-. .~
·2~· '~;t:.'
Comment 2:
The contractors need to broaden their scope of mitigation concepts that
are included in the studies. There are other options available for
mitigation planning above and beyond what is included in the Procedures
Manual as it is now written. I refer you to the detailed comments made
by ADF&G.
Response:
We view mitigation planning as a dynamic process and are prepared to
consider any additional options available. As a means of obtaining
agency· input and review we plan to establish a fisheries mitigation task
force similar to that organized under Subtask 7. 11 .
Comment 3:
We recommend that an assessment of effectiveness of mitigation used
on other projects to reduce impacts also be studied before we deter-
mine what sorts of mitigation techniques will be applied to the proposed
Susitna project. The reason for recommending this is to enhance the
probability that the mitigation we apply to the Susitna project will
be successful.
Response:
The intent of our review and evaluation of mitigation measures used
on other projects is to assess their effectiveness and to determine
their applicability to the Susitna Project.
Comment 4:
Table 2 should be amended to identify the issue of the effect of the
project on rearing, fish passage and egg incubation in the Susitna
River from its mouth upstream to the proposed dam site.
Response:
It is our intent to address these issues and Table 2 will be ammended
accordingly.
Comment 5:
The mi~igation alternatives should include a cost benefit analysis in
Phase li.
Response:
The costs associated with recommended mitigation 1·1ill be identified in
Phase I with actual cost-benefit analysis considered in Phase II.
9
--'-.:..__.._,.• '< ~. ~ -Comment 6:
There is a lack of adequate participation by resource management agencies -'
in the impact assessment or mitigation planning as proposed in this
Procedures Manual.
Response:
See response to comment 2.
Comment 7:
The water quality subtask within this study needs further review
regarding the extent of data required and details about timing of the
data collection.
Response:
R&M Consultants has prepared a Procedures Manual for the water quality
program. Review of this document may provide the required details about
timing and data collection.
Subtask 7.11 Wildlife Ecology
A. Big Game Assessment and Mitigation Planning
Comment 1:
This study does not describe the methodology that will be used for
assessing impacts to be mitigated. The Procedures Manual discussion
of formation of a mitigation team and a series of ~eetings and conferences
as a methodology is inadequate.
Response:
The methodology for impact assessment and mitigation was not developed
in detail because it was believed that a more effective program could
be prepared following the collection of data in 1980. Rather than
develop more than a general approach, it was considered to be preferable
first to gain an understanding of the relative population levels of
various species and also identify critical habitat types. In this
manner a detailed approach to impact assessment and mitigation will
be prepared based on at least a preliminary understanding of the wild-
life/habitat realtionships operative in the project area. The Procedures
Manual will be amended as soon as approach details are finalized.
,
10
t" --:: ... --.·~--... ---... -........ .,_.~ -~---~· .. v ---~-~·' . -·--··
..t
-
....
...
....
-
-
-
-..
-
""' -
-
.,
..,
-
-
-
-
-
.....
·-
-
--
-
._.
·-
.......
.. l: :..; . ~
Comment 2:
The scope of mitigation concepts needs to be broadened in this study.
The National Environmental Policy Act (NEPA) defines mitigation in five
different ways:
a. Avoiding impact all together by not taking a certain action ... (or)
Darts of an action.
b. Minimizing impacts by limiting the rlegree or magnitude of the action
and its implementation.
c. Rectifying the impact by repairing, rehabilitating, or restoring
the ... (affected) environment.
d. Reducing or limiting the impact over time by preservation and main-
tenance operations during the life of the action.
e. Compensating for the impact by replacing or providing substitute
resources ... (or) environments.
Since the Susitna project will be subject to an environmental impact
statement the Alaska Power Authority should assure that the contractors
preparing the application adequately address all aspects of mitigation
in order that the submittal will be adequate for the E.I.S.
Response:
B.
To date we have concentrated our mitigation efforts on approaches a) and
b) (avoiding or minimizing impacts) through providing environmental
input into development selection and preliminary desig~. This approach
will be expanded to include approaches c, d and e following development
selection.
l~ildlife Ecolog,z-Furbearers
Comment 1:
Scope of these studies needs to be extended to salt water. The reason
is the proposed Susitna hydropower project will have imr.acts all the
way to salt water.
Response:
The scope of the furbearer studies that concern aquatic furbearers
(e.g. muskrats, beaver, and river otters) have already been extended
on a limited basis downstream to the Delta Islands. At the present time
there does not appear to be justification for extendin0 the study effort
any further downstream. Should the results of Phase I indicate that
further extension is in order, it will be proposed for Phase II.
Comment 2:
This manual does not acknowledge the need for mitigation for these
living resources. It is recommended that the Procedures Manual be
revised to reflect the need for mitigation for furbearers.
11
.-. '~
Response:
Although mitigation was not mentioned in the Procedures Manual, it will
certainly be addressed in the furbearer studies. In order to strengthen
the interdisciplinary coordination concerning mitigation, the Principal
Investigator of the furbearer studies has been added to the mitigation
task force as described in the Big Game Procedures Manual.
Comment 3:
The manual describes surveys which will be done only in the winter. The
seasonality of this approach will result in certain data biases and lack
of data for the intervening months.
Response:
As indicated on page 12 of the Furbearer Procedures Manual, field
activities will be conducted throughout the year and are not restricted
to the winter months. Some of the survey activities that are being
conducted during the non-winter months include locating fox dens,
collecting furbearer scats, and monitoring of radio-collared animals.
Comrnent 4:
The studies state that radio collaring of animals will be done. How
will the radio collar data be used:
Response:
Radio telemetry data will be used to determine the home range size of
key furbearers. This information, in conjunction with the vegetation
maps, will enable the generation of an estimate of how many animals the
area can normally support. The radio telemetry data are also being
used to determine seasonal distribution and habitat utilization of key
furbearers.
Note Concerning Furbearer Procedures Manual:
Since it was impossible, prior to the initiation of these studies,
to est blish soecitlc techniques that would be highly effective in
sampling the furbearers, ~any of the techniques outlined in the Procedures
Manual have been modified following the first field season. An amend-
ment to the furbearer manual 1vill be produced in spring, 1981, and will
reflect the refined approach that is now being used.
C. \~ildlife Ecology-Birds and Non-game Mammals
Comment 1:
The scope of these studies needs to extend to salt water.
12
...
...
...
-
...
-
...
-
...
...
-
IIIIi•
-
....
-
-
...
...,
-
..._,
-
-
-
.......
-
-
-
""'
-
.....
....,_.
;;·
---~
Response:
At the present time, bird and non-game mammal studies are being conducted
as far downstream as Sherman. With the exception of a bald eagle nest
survey, there are no studies planned for this discipline downstream of
Talkeetna. Insufficient data exist to support the conclusion that major
terr~strial impacts will take place downstream from Talkeetna. At the
present time, the expenditure of funds to study birds and non-game
mamnals in this area does not appear warranted. Should the results of
the Phase I hydrology studies indicate that major changes in terrestrial
habitat are likely to occur, an intensive Phase II program will be imple-
mented.
Comment 2:
The Procedures Manual fails to acknowledge the need for mitigation of
birds and non-game animals. It is recommended that the Procedures
Manuals be revised to reflect this need.
Response:
Although mitigation was not mentioned in the Procedures Manual, it will
certainly be addressed in the birds and non-game mammal studies. In
order to strengthen the interdisciplinary coordination concerning mitigationi
the Principal Investigator for bird and non-game mammal studies has been
added to the mitigation task force as described in the Big Game Procedures
Manual .
General Comments on ~iildlife Ecolog..Lf!ocedures i·1anuals
Comment:
There is a compelling need to integrate the wildlife and the plant
ecology studies so that the end results are meaningful and useful
to the decisions which will be made. Each of these study elements should
apply appropriate quantitative methodologies to evaluate animal
habitats. The methodology used may depend on the characteristics of
the species or group of species they are dealing with. Whatever method
is adopted, it must be biologically justifiable and provide a relative
estimate of the habitat value per area unit for the study area.
Response:
The assessment of impacts will be based to a very large degree on
project-related disturbance of wildlife habitat. Although the inter-
relationships between the plant ecology studies and the various wildlife
studies were not emphasized in the Procedures Manuals, there has been,
and will continue to be, a highly coordinated effort between Subtasks
7.11 and 7.12 .
13
,.....
·~~..::;...
Subtask 7.12 Plant Ecology
Comment 1:
... .,<:,! .. ~; ..
The scope of these studies needs to be expanded from the dam site all the
way to salt water. The reason for this is that construction and operation
of the dam will impact vegetation to that extent.
Response:
Under Phase I, the present intent is to extend certain of the plant
ecology studies downstream to Delta Islands. The degree and extent of
impact downstream, especially below Delta Islands, has not as yet been
defined. The impact downstream will depend, to a considerable degree,
on the facility design and hydrological information which is not currently
available or not finalized. For this reason, it was initially decided that
it would be best to wait until the extent of hydrologic impact is known
below the Delta Islands, before specific vegetation studies are performed
for this region. If studies are warranted below Delta Islands, then they
would be proposed for Phase II.
Comment 2:
There needs to be a high level of integration and coordination between
the plant ecology, hydrology, and the wildlife impact assessment studies.
This is because a great part of the wildlife impact mitigation will be
based on vegetation.
Response:
We agree that a high level of integration and coordination between the
plant ecology, hydrology, and the wildlife impact assessment studies
is needed. The need for this integration and coordination is stated in
several places in the Plant Ecology Procedures Manual. There is a major
section entitled "Input Required From Other Sources" in v;hich subsections
entitled "Hydrology" and "Wildlife Information" are included. The need
for coordination among disciplines is also stated in several of the
Wildlife Procedures Manuals and was discussed in detail under the response
to the general comments under Subtask 7.11 Wildlife Ecology. In summary,
we believe that the need for coordination has been recognized from the
outset. We feel that we have fulfilled this need to date and plan to
continue to do so throughout the study.
Comment 3:
The definition of wetlands used for classifying habitats should be
compatible with data already collected in the Susitna Basin by the
cooperative study underway with DNR, ADF&G, and SCS. We recommend
that the classification system developed by the U.S. Fish and Wildlife
Service and described in "Classification of Wetlands and Deeo Water
Service Habitats of the United States" (FWS/OBS79/31) be considered
as the wetland classification for these studies.
14
--
....
-
-
-
-
-
-..
-
-
...
..
-
...
-
.....
-
-
-
.....
-
-
-
.....
-
l~,-
.....
........
;-·
: ~.:.--ii~;J
Response:
The classification system developed by the USF&WS for wetlands and
deepwater habitats will be used for the wetlands mapping effort. There
has been some coordination with the SCS concerning wetlands and there
are p~ ns for additional coordination with ADF&G and DNR.
Subtask 7.14 Access Road Analysis
Comment 1:
The analysis of alternativei does not indicate whether stream crossings
will be reviewed to determine extent of icing and adverse environmental
impact as a result of crossing these streams. Stream crossing and
structures should be designed to avoid creating icing and erosion
problems.
Response:
Stream crossings are an important part of the access route environmental
analysis and will definitely be considered in routing and later in impact
and mitigation planning for the selected route. Included in impact
assessment and mitigation planning will be analysis of designs to avoid
potential ice dam problems during break-up, and associated erosion
problems. Consideration will also be given to minimizing erosion
problems. Consideration will also be given to minimizing impacts
associated with actual construction of bridge facilities and culverts,
i.e. habitat disturbance and erosion potential .
Comment 2:
This analysis should include assessing the effects of an increase in
fishing due to newly opened road access as part of its scope of work.
Response:
The analysis will include assessing the effects of an increase in
fishing due to newly opened road access. The potential impacts on
the fish community and habitat from a biological standpoint will be
addressed under Subtask 7. 10, Fish Ecology Studies, and the recreational
impacts or conditions resulting from increased access to this area will
be handled under Subtask 7.07, Land Use Analysis. In like manner, other
environmental subtasks (e.g. vegetation, cultural resources, wildlife)
wiil deal with increased access as it affects these specific disciplines.
Comment 3:
There is an obvious linkage between access roads for this project and
land use/fish and wildlife studies. Review of the manuals does not
indicate that the appropriate process or mechanism is in place to see
that this occurs .
15
...-.. ~
'-;~_;;: · .. : ~ ~~ /
Response:
Subtask 7.14 (Access Road Environmental Analysis) is essentially a
coordination subtask for this specific project component since it has
obviously far-reaching impacts. The Procedures Manual states that
the actual analysis is to be done by Principal Investigators within
each environmental subtask. A major coordination effort was felt to
be necessary due to the interplay of roles between APA, Acres, R&M, TES,
AOF&G ·nd the various environmental subcontractors. To this end,
correspondence exchange and maps and information exchange has occurred
since April,· 1980. In November, a meeting was held in Anchorage at
which time representatives of APA, Acres, R&~1, TES, ADF&G, and other
environmental subcontractors discussed various alternative routes.
Information exchange continues on a daily basis, and will continue
through route selection and preparation of the FERC application.
General Comments
Comment:
It is the consensus of tte Steering Committee that each study task
Procedures Manual should include two maps:
1. A map that delineates the boundaries Jf the specific study tasks
described in the respective manual.
2. A second map delineating the overall study area, i.e., from the
mouth of the Susitna River to the Denali Highway.
Response:
1. Maps of specific study areas would certainly be useful. In several
subtasks, part of the work performed during the first year was a
determination of the appropriate study area. Such maps are thus
planned for the 1980 Annual Reports and will be incorporated into
the respective Procedures Manuals with the next required amendment
to each manual.
2. A composite map showing the relationship of specific study areas
will be presented in our summary annual report.
16
...
-..
...
111111
-
....
·"""
-
...
...
...
.,
•
-
-
-
.....
-
·r~··
'
-
-
-
-
-
....
-
--
-
'~~
: ~· :'-:;.( ~:; ~:~::· ~ ~-~.: ~ ~~ .~ ~ ;: ~:: --'-'' ·-·--~~'·. ,,. - -::.. [.
,... '-. ·,~_;/
I. POPUL.!iTION
A. Population levels
8.
l. His.torical
2. Present
3. Projected
4. Component of Change (births, deaths,
in-out migration)
Ethnicity, Culture, Religion
C. Population Distribution (city, borough,
state) by:
1: Age
2. Sex
3. Race
4. Occupation (general)
5. Education
a . Ret i red , 1v age , s a l a r y
b. Sector, activity
c. Employment
D. Population Density
C' '-. ramily/Household Characteristics
Extent
2·. Marital Status
3. Migration patterns
a. mobility/stability
b. point of origin
c. out/in migration
4. Length of Residence
a. in house
b. in community
c. in state
5. Place of work (com~uting distance)
F. Attitudes Toward Chance/Economic DRvelooment
J .
G. Projections
Each of these categories and variables will be addressed to the extent
that data and information allow and to the extent that they are relevant
for the purposes of this analysis.
Jr / . I
s . I l !. -~Jl!SIUG ~ .....
\~ ':.;.· -A. Historical Info {growth rate)
6. Type -l. Sinole familv -"' 2 . Mu 1t i -f ami 1 y
3. Mobile nome -4. Recreation Facilities
5. Trcnsient Facilities ,, -* Variables to be considered for above
a. number of units -b. quality
c. cost/prices
d. vacancy rate -
c. Vacancy Rate ...,
D. Status
l. Renting -2. Buying
3. Own
4. Other ....
r: .... Land availability
.....
F. Zoning/Building Regulations (&patterns)
.,J
G. Financial Climate (incentives/disincentives)
..;
H. Real Estate Activity
1. Sales
2. Construction ..
3. Plans
,.,_
I. P.;jections
-
-
_,
-
-
... ,.., .• , .,..:f.\.·· y. ? .• Cf.' : ... r, ·.
, .,
j \'.
-
-
-
-
-
-
-
-
-
-
e e
?UBLlC S::?.\'IC~S & GO\'ER:;:·iEJiT R::\'C:r;u:
A. Government Structure/Oraanization
1. Towns -
2. Cities
3. Boroughs
B. Government Services
1. Water Supply and Treatment
2. Waste Water Treatment
3. Solid Waste Disposal
4. Police Protection
Legal System (courts, retention facilities)
6. Fire Protection
7. Health Care (including Social Services)
8. Parks and Recreation
9. Libraries
10. Education (day care, vocational, others)
11·. Public Transportation
12: Roads and Highway System
13. Telephone Service/Communication
14. Electric Power Service
* Variables to be considered for above
a. Service area
b. Usage fi~gures
c. Deployment patterns (distances/response
times)
d. Capacity figures
e. Condition/quality
f. Relevant standards
g. Occurrence rates
h. Plans for expansion
i. Government expenditures
C. Tax Base and Revenues
1. Taxes
a. persnnal
i. rates
ii. base
b. industry
i . rates
i i . base
c. Sales
i. rates
ii. hase
d. other
--
-
-
-
-
-
,..
,..
-
-
,..
,..
-
-
-
(~4~JPd2J 5u~MO~~oq) +qap +uawu~a~o8 · ·£
saJ~nos anuaAa~ ~a4+0 ·z
."'l
.J
/ . /,/, /~-
-
-
-
-
e e
\'. :~:.:~c.:-:IC s..:.SE
A. General Description (History and Area Trends)
8. Total Work Force
C. Emp 1 oyment r~u 1 tip l i er
D. Output Multiplier
E. Major Basic Industry Description
l. Construction
? 1-". . ~· ·11n1ng
3. Agriculture
4~ Timber and re1ated products
5. Manufacturing
6. Fishery
7. Oil and gas
8. Transportation
i. Ra i 1
ii. Air
iii. Motor transport
i v. t<lar in~
9. Public Utilities
l 0 . C orrrn u n i .cat i on s
ll. \~holesale trade
12. Retail trade
13. Finance, insurance, real estate
14. Services
15. Public Administration (Federal, State, Local)
16. Tourism
* Variables to be considered for above
a. history
b. statistics (present sales, prod. , etc.)
c. employment
1. labor force
2. percent of total work force
3. payroll
4. average wage rate
d. resource base (land use)
e. service area
f. usage figures
g. capacity
h. condition/quality
i. product value
j. ~arketing patterns
k. relative to state and U.S.
1. future out1ook
-
-
-
-
-
-
-
--
-
-
-
SUO .L Sn lJUOJ • J .. -
, '
. ' ~. . ..
J e ... '"''"" -,--.-·.~-.. ,, ' & • ) :-:._,· ........ r-.r..:;;~.,:ur..l.!!'!!"l . ._ .=Dor 1 ncome
A. Historical Labor Changes
B. [;np 1 oy.nent
l. Present Profile (e~plo~ent by sector)
a. absolute
b. pE:rcentage
2. t1ultip1iers
a. bcsic industry to
b. export trade sector
c. services
3. Length of work week
4. Seasona 1 i ty
C. Occupational Staffing Patterns by
l. Sector/Industry
2. Ethnicity
3. Sex
4. Unemployment
5. Percentaae of work force
6. Wages (selected occupations)
D. Working Conditions and Absenteeism
E. Union Presence
F. Unemplo~ent for Area
1. Age
2. Sex
3. Race
G. Income
l. History
2 . Per Cap i t a I n come
a. General
b. Sex
c. Ethnicity
3. Source
a. Wages/sa1aries
b. Social Security
4. Subsistence income (moderate standard of living)
5. Consumer Price Index (CPT)
H. Projections
·v'":V ,7;. ,,
#' ~ I " ;
J l •• LA.:;G USE e e
A. Historical/General
..
8. Land Tenure (ownership) -c. Existing
1. Forestry
2. Aoricu1ture
3. Hining
4. Timber
-
5. Native Lands
6. Federal -
7. State
8. Parks -9. Oil and Gas
10. Unexp l cited Natura 1 Resources
11. Industry/Co~ercial
12. Urban -
13. Rural
14. Residential
15. Military
16. Transportation
..
*Variables to be considered for above -
a. acres
b. value -c. ownership
d. management plans
e. historical trends f. percentage of total
-
-D. Population Density -E. Land Use Plans and Control 1. Public
2. Private -3; t1un i c i p a 1 it i es
4. Borough -5. Flood plains
r: Projections I • -
-
-
-
-
·Tlir'-' r.
-
-
-i
\'~;I. ;.~ :~.~~~.1 I CN e
A. Utilizing Fish & Wildlife ?.esources
1. Sport Fishery
a. All species
2. Wildlife
a. Caribou
b. Moose
c. Black Bear
d. 6 rown Bear
e. Mountain Goats
f. Sheep
g. Wolverine
i. Waterfowl, Birds
j. Other Furbearers
•
* Variables to be considered for above
1. Historical
2. Present
a. area (acres and location)
b. effort (visitor days/# of visitors) -
c. Success (harvest)
d. Resident (pt. of origin/% of total)
e. Non-Resident (gen. geo. pt. of origin/
%of total)
f. Species (stats relative to State)
g. Subsistence (personal consumption/
business)
h. Trophy
i. Management Plans
i. Reaulations
ii. Re~enues (tota1/•elative to
state/flow of money)
iii. Enforcement (ways/numbers/capacity)
8. Not Related to Fish & Wild1ife Reserves
1. Water Sports (canoe, kayak, rafting)
a. Historical
b. Area
1. effort
2. resident/non-resident pt. of or1g1n
2. Land Sports (hiking, picnicing, climbing)
a. Historical
b. Area
1. effort
2. resident/non-resident pt. of origin
C. Other
-=:-::::::::~::: , __ ,, ___________ _
-
-
-
-
-
-
-
-
-
--
-
-
-
-
•
(#) SJaUMQ pu~l ·~
($/#) SJaUMQ a6p01 "[
($/#) SJ012Jado PPl .J~'!/ ·z
(S/#) sap~n~ ·t
ssau~sne pa+etac
( • • 1"0-·, • ~ ~ T I ~u ,.Ji .:,;. •"
-~t i,;
1. "'~
.
.
. .
;/
I
/ ,,,,
...... ~ jy~. ,,
~·. ,.
-
-
-
-
-
-
-
-
-
··"~~~'t w· ... -;; ~~~~rG\&~ I
ot:PT. oF I~N\'IUON~It:NTt\1., coNst:n\';\TION /
JAYS. HAMMOND, GOVERNOR
. ./
~,U~U[ @~
I POUCH 0 -JUNEAU 91811
I
March 2, 1981
Mr. Eric P. Yould
Executive Director
Alaska Power Authority
333 West 4th Avenue, Suite 31
Anchorage, Alaska 99501
Dear Mr. Yould:
, ...
r'. ~-
I •
J:;>·· , ..
J ..... ~)
.~. \
.'.t :~
\ ','{
Your letter of January 2, 1981 proposes to expand the function
of the Susitna Steering Committee from that of an advisory
body to the study team to one of performing evaluations and
structuring recommendations. I am happy to offer the resources
of this agency to serve in that capacity to a reasonable
extent.
It is not clear to us, however, precisely what may constitute
"items requiring consultation," as the only substantive
matters to come before the Steering Committee have been
review of the field procedures manuals regarding Task 7 of
the Plan of Study, and review of the preliminary screening
of poten~ial hydro sites. Apparently, a more direct link
with the Power Authority is anticipated, rather than simply
with the study team, since your letter indicates that Steering
Committee recommendations will be considered by the Power
Authority. We will look forward to additional information,
at an appropriate time, concerning matters that may be
brought before the Steering Committee, and the action requested
of the committee.
Bob Martin will be the representative of this agency to the
Steering Committee as of this date. Bob is the new supervisor
of ADEC's Southcentral Regional Office. Bob will receive
whatever support he needs from Dave Stu~devant, who has been
our representative in the past a9d-who will~ntinue as
Bob's alternate. r \
-~--\ ~--u cuk-------
1.. 1....-A_..... --t-. v /E~i..--MtYeller
Commissioner
cc: Deena Henkins, EQM
Bob Martin, SCRO
, e
~¥&¥[ @~ &~&\~~& JAY S. HAMMOIIO, GOr£11101
J)EJ•,.\UT~IENT o•· ~ATIJRAI. lli<:SOUilf~ES
.,
l
\
01 VISION OF RESEARCH & DEVELOPMENT
March 24, 1981
Eric Yould, Executive Director
Alaska Power Authority
333 W. 4th Avenue, Suite 31
Anchorage, AK 99501
Dear Mr. Yould:
323 E. 4TH A VENUE
ANCHORAGE, ALASKA 99501
279-5577
r...:.J..:.I J..:_O
.. ··') 0 . 19°1 :, . ·.~ ·~, \ .'-. ~ 0
J.J.J..S'f..A PO'I'{r;.R AUH-\OR\T'l
The purpose of this letter is to call to your attention the lack of
response from Alaska Power Authority (A.P.A.) to detailed review
comments that the Susitna Hydro Steering Committee made on the Susitna
Hydro Project plans of study. These comments and recommendations were
transmitted in a letter dated November 21, 1980. I request a response
from A.P.A. which identifies when the Steering Committee will have an
opportunity to review the modifications that will be made in studies
to meet the concerns that were raised in our November 21, 1980 letter.
With the 1981 field season beginning very soon, changes in the plans
of study will have to be accomplished quickly.
Sincerely yours,
OJ~
Al Carson, Chairman
Susitna Hydro Steering Committee
cc: Susitna Hydro Steering Committee Members
R.E. LeResche
Reed Stoops
-
-
IIIII
...
-
...
-
-
-
..I
...
-
-
-
-
-
-
-
-
• j, ·,
-
-
....
-
-
-
-
-
-
-
~·.
-
-..:-
ALASKA POWER AUTHORITY · ... ·
Hr. Al Carson
Chairman, Susitna Hydro
Steering Committee
Alaska Department of Hatural Resources
323 East 4th Avenue
Anchorage, Alaska 99501
Dear Mr. Carson:
t-1arch 25. 1981
I regret that it has taken so long to react to the Steering Coomittee's
suggestions on improving the Susitna hydroelectric project environmental plan
of study. It took a number of months for Acres and its subcontractors to de-
ve1op and transmit their set of responses and plan of action. The Power
Authority received that transmittal on March 2, 1981. We have not been able
.!.' -·~
to make any final decisions on scope changes, however, for h~ reasons. First~
Acres has not yet provided the program modification suggestions in any detail
of scope or cost. Secondly, the Power Authority has had to \r~aft for other
program components (such as Tasks 4 and 5) to be evaluated for necessary scope
changes. It 1s only in revi~ing the entire first year program that we can
identify a~s for improvement~ assess their cost impact~ evaluate their re1a-
tive merit and established priorities among the myriad comp~ting needs.
The Power Authority wi 11 have prepared 1 ts set of recommended scope changes
and resultant supplementary budget request by Aprfl 3, 1981. It remains to be
seen whether all, none or a portion of the supplemental funds will be forthcom-
ing.
I have requested previously that you organize a Ste~ring Committee meeting
for eiti1er April 13. 14, or 15. At this meet1ngJ we w111 present our proposed
program modifications~ which I trust you will find go a tong way toward satisfy-
ing the Committee's concerns. In preparation for that meeting, I have attached a
copy of the Acres response to the Steering Committee comments. The detailed re-
co~T~ndaticns~ while not contained in the attachment. will be presented at the
Steering Committee meeting.
FOR THE EXECUTIVE DIRECTOR
.1\ttachinent: As stated
cc: Susftna Hydro Steering COfml1ttee Hembers
with attachment
Sincerely.
Robert A. ~iohn
Director of Engineering
lit , ,. .... ~: o::·
. ~~&¥~ @W ·&~&~l~r~APR 6 i981 t ·. · .. ·; ,"".,.,·"'-,.,
\ .;', ,•.
,.._.,,..· ...
JAr .t HAIIIIOIID. GOYfliiOI
.....
U.IH•AUT!\1 ENT cu: .NATIJil.-\14 llt:SOIJ llC~f:S
AlASK:A POWal
AUTHORilY
SUSITNA
FILE P5700 J-f • Lt: '?
SEQUENCE NO.,
F I { I 7~' k
z'<_i . ·~ r::l ~ 0 .,. --~ ~ c-..... ...., ~
< -~ i 0 ~ ·I \/)J_~_G
iBJB
IJKL
:~~~-
! ~:PB 1
-~---'
:c:RI I
-f---
:H&N --
FIAA
APA
wee
TES
-I-"&M -"'OF&G
7 f-aurr.-"'7 ·;;;( . -ccx..
'
DIVISION OF RESEARCH & DEVELOPMENT
·:--:.
323 E. 4TH A VENUE
ANCHORAGE, ALASKA 99501
279-5577 -
March 26, 1981 ~-.---~ ...
Eric Yould Rf::C~IVED -
·u:) 2 -.. 1981 .. !. ... ·" . .....
Executive Director
Alaska Power Authority
333 West 4th, Suite 31
Anchorage, AK 99501 />J..}SY-A POW~R AUiHORITY
Dear Mr. Yould:
The purpose of this letter is to transmit to you the findings and
recommendations of the Susitna Hydro Steering Committee in response to
APA's request for input and recommendations on the selection of an
access road to the Susitna Hydro Dam sites. On March 6, 1981, Alaska
Power Authority staff, contractors and subcontractors provided several
agency representatives with a briefing and a request for comments in
order to make a determination for surface access to the dam sites. It
was requested that our comments be provided to APA by March 23, 1981.
As a result of comments and concerns expressed by agency representatives
at the March 6 meeting, I agreed to convene the Susitna Hydro Steering
Committee in order to identify and coordinate the concerns of those
agency representatives regarding access to the Susitna Hydro sites.
The Susitna Hydro Steering Committee met on Friday, March 20, 1981.
We spent the afternoon discussing various issues and concerns surrounding
access to the dam sites with the subcontractors to Acres American. As
a result of these discussions and review of the pertinent documents,
·report studies, etc., the Susitna Hydro S,teering Committee makes the
following comments and recommendations:
1. The Steering Committee representatives recommend coordination
between the decision about access road routes and transmission
line routes. Until this issue was raised by a Steering Committee
member at the March 20 meeting there had been little discussion.
The documents reviewed indicate that this was not a criterion for
establishing potential access routes.
2. There needs to be a systematic decision-making process explicitly
laid out for determining an access route for the Susitna dams.
This decision-making process should be straight forward so that
agency participants can understand and effectively participate in
establishing proposed access routes. There needs to be a broad
range of criteria established for determining the acceptability
or nonacceptibility of various route alternatives. Information
provided by Acres and their subcontractors to date indicates that
-
....
..
~
....
..
--
-
-
-
-
-
-·
-
-
-(
-
-
-
-
Eric Yould 2 March 26, 1981
3.
4.
s.
the criteria used to determine access_roads were eight in number
and are roadway and railroad technical design parameters exclusively.
It is the recommendation of the Steering Committee members that
there are numerous other criteria which are critical and need
consideration along with the technical road and railroad design
parameters. I would refer you to an attached document entitled
"Suitability for Raul Roads" to give you an example of a more
comprehensive lists of criteria that need to be incorporated in
any decision with respect to access to the dam sites.
There needs to be a clearer explanation and understanding of the
decisions regarding the timing of building access roads vs. FERC
approval for the project. We were advised by subcontractors that
the timing depends on which access mode and route is determined.
The time of construction and design of these routes varies from
one to three years. The agencies on the Steering Committee need
to have a better understanding of how these facts and assumptions
interrelate to each other in order to make informed recommendations
to APA.
There are numerous specific decisions that will be required
regardless of which access mode and route is ultimately determined
the most appropriate. The location and development of these
facilities could significantly affect the preference and recommendations
from agencies. For example, identification of gravel sites,
spoil sites, stream crossings, construction camp service and
maintenance facilities will be needed. The members of the Susitna
Hydro Steering Committee unanimously felv that it was important
and necessary for APA to provide an understanding of how these
decisions will be made and how a quality control system will be
in effect to ensure that tasks are accomplished in accordance
with approvals and designs.
The Susitna Hydro Steering Committee members in reviewing the
March 6 and 20 meetings and discussing with subcontractors have
determined that data gathering planned for this summer should be
carried out on several access routes in order to make the final
decision as to which one is most acceptable. To make a determination
on a specific route with the lack of data/information that we are
currently dealing with and then send researchers and data gatherers
into the field this summer to gather site specific data on only
one route is of questionable utility and logic. The primary
reason why this is questionable is because unless comparable data
on several of the prime routes is provided, the agencies will be
unable to provide comments as to which route is most acceptable.
In summary, we see the gathering and analysis of data on several
proposed routes as the rational basis for making a determination
as to which access route should be ultimately chosen.
In summary, the Steering Committee wishes to ~phasize that it is
willing and anxious to work cooperatively and expeditiously with APA
in identifying and res'olving the numerous questions which need to be
:'< ~--~: -~~:. :; ; ~ :.
::·~r~::L=·-= ~
.. ,. r:
'
!<\
')
;J
'· .. .. .. ...... __ _
)E±;;:~::
r. ..
:"
!
~
~
L. ____ _
:.: ... . . ..
·l ~~ c ·1 ·,,
i~
ii
b
.1 ..;
·~ .>.L,_ __ _
.. ~!i. :: ::::~ .
. ~~!~:·~~ ~
fo r;
;I
~~
~~
~
i!
~~
!.!-:.,.. --
. /!}}f,',' :::!!/i
" .. ,.
r
~
:,..t ,.
.. · ..
-i
-:':'~
. :; : = .. : ~-~ J:
·-
f
~
r,.,~---
·<·· ·-~·::~~~~·:1:i· ; . ~ ...,; : ..
·:
Eric Yould 3 March 26, 1981
answered in order to make rational decisions with respect to access to
Susitna Hydro sites. Once you and your staff have had an opportunity
to review this letter, I would appreciate an opportunity to sit down
and discuss the specifics of these comments in further detail.
Sincerely yours, m
Al Carson, Chairman
Susitna Hydro Steering Committee
cc: Susitna Hydro Steering Committee Members
R. E. LeResche
Reed Stoops
-
....
....
...
....
...
...
...
...
..J
....
-
...
.,
-
-
....
-
-
L
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-1 ..... -,·· ·.-( .. : :)
<;.;-' "'~'" 1\.LASii.A _PO\VER 1\UTIJt)RI'l,Y
333 WEST 4th AVENUE· SUITE 31 ·ANCHORAGE, ALASKA 99501 Phone: (907) 277-7641
(907) 276-2715
,1\pri l 8, 1981
i-1r. A 1 Carson
Alaska Department of Natural Resources
323 E. 4th Avenue
Anchorage, Alaska 99501
Dear A 1:
This letter is addressed to you in your capacity as Chairman of the Susitna
Hydroelectric Steering Committee. I want to provide the Committee with some in-
formation, and solicit Committee approval of a recommendation.
To recap some past events and discussions last year, a reassessment of the
Steering Committee role was performed. A proposal to slightly alter the Commit-
tee charter emerged from that reassessment and was sent to a number of resource
management agencies. Due to differences between the agencies, an abbreviated
version was sent to some. Copies of both letters are attached.
Of 14 agencies contacted, 12 answered, 4 basically agreed with the proposal,
5 agreed with emphasis on the option to formally comment separately from the
Steering Committee route, one posed an alternative, and t~·/0 in essence abstained.
From this, I conclude acceptability of the proposal to slightly alter the Steering
Committee role. Now, to close the loop, I would like to ask the Committee proper
to move to incorporate the change.
I would appreciate it if you would include this subject as an agenda item for
the Apri 1 13, 1981 Committee meeting.
FOR THE EXECUTIVE DIRECTOR
15 Attachments:
1. APA Letters (2)
2. Response Summary Sheet
3. Response Letters (12)
,aJ}dj
'oavid D. Wozniak
Project Engineer
cc: Phil Hoover, Acres-Columbia w/attachments
1.
AGENDA
Susitna Hydro Steering Co::unittee }1eeting
April 13, 1981
Response to November 1980 Steering Committee comments on Task 7
studies; APA, Acres, and subcontractors.
2. Response to March 26, 1981 Steering Committee comments to APA on
access roads; APA, Acres, and subcontractors.
3. Role of Steering Committee; APA and committee members.
4. Alternative power study and Steering Committee; committee members.
5. Other items; committee members.
•
•
•
•
•
-
-
-
-
-
-
-
-
-
-
-··
ALASKA POWER AUTHORITY ...
t·1r. Bi 11 Law1 "nee
Anchorage Operations Office
Environmental Protection Agency
710 C Street
Anchorage~ Alaska 99510
Dear Mr. Lawrence:
April 15, 1981
Attached is a mid-point report on Susitna Hydroelectric Project. It is
forwarded for your infOrmation in respo"se to your earlier expression of in-
terest w1th1n the context of the Susitna Hydroelectric Project Steering
Comrn1ttee.
I have asked Mr. Allan Carson. the Chainnan of that coomfttee~ to forward
meeting minutes to you and to ensure that you are advised of scheduled meetings ..
FOR THE EXECUTIVE DIRECTOR
Attachment: As noted
cc: Allan Carson w/o attachment
'\
\
}
Sfncerely,
David o~ Hozn1ak
Project Engineer
CONCUR:
DW
RAM
-)
TO:
FROM:
-:~::: :·~ -_ __;_)
ALASKA POlVER AUTUORITY
MEMORANDUM
For the Record \ DATE: May 1, 1981
David D. Wozniak~ SUBJECT: Steering Committee Mailings
5~(
On April 23, 1981, copies of the APA mid-~e~ report and the Plan of Study
were hand carried to USGS and AEIDC. Copies of the mid-year report were
earlier mailed to other members of the Steering Committee. With this
action, all member of the Steering Committee either possess or have access
to both documents.
..I
...
..
....
...
-
.,.;
..
wi
..
..,;
-
-
-
-
-
-
-
-
-
-
-
.....
-
-
-
-
-
-·
-
-
-
-
......
ALASKA POWER AUTHORITY
Mr. Gary Stackhouse
U. S. Fish & Wildlife Service
1101 E. Tudor Road
Anchorage, Alaska 99501
Dear Gary:
April 15, 1931
Attached is a copy of our report to the legislature as promised by rne
earlier this week. I am also sending a copy to Bruce Apple.
Bruce tells me he has a copy of the Plan of Study. Since these are an
endangered species. I would appreciate it if you would share his copy as
you structure your shopping list of areas of concern.
FOR THE EXECUTIVE DIRECTOR
Attach!!!ent: As noted
Sincerely,
David 0. Wozniak
Pro.ject Engineer
CONCUR:
ow
RAM
··.!
-~ ' .
·,;·· ALASKA POWER AUTHORITY
! ;_~f}
Hs. Judy Schwartz
Environmental Evaluation Branch
Hail Stop 443.
Region 10. EPA
1200 6th Avenue
Seattle, Washington 98101
Dear Ms. Schwartz:
Apr11 15 , 1981
Attached is a mid-point report on Susitna Hydroelectric Project. It is
forwarded for your 1nfonnat1on fn ·response to your earli~r expression of in-
terest within the context of the Susitna Hydroelectric Project Steering
CO!ml1ttee ..
I have asked Mr. Allan Carson, the Chairman of that committee, to forward
~eting minutes to you and to ensure that you are advised of scheduled meetings.
FOR THE EXECUTIVE DIRECTOR
Attachment: As noted
cc: Allan Carson w/o attachment
Sincerely.
David o. Wozniak
Project Engineer
...
-
-
-..
IIIII!
wl
---
wi
-CONCUR·
ow
RAM -
-
-
..
.,;
-
-
I WILLETT
NITTE
-LAMB ~
~AYPE.N-Y II
SfBERRY _:1 --'")
t.; (__~V.• = ~ .....
I
I 1
~ (.' HJJ, .r-1 ~ I& GILL /vfcJj< lc/
rLOWREY
w~ETZ
__...,~ ~ ·~ -I HUSTEAD
t-1 BOVE
f-
T
1 CHASE
1-
[ . .,.:
I
'-
---;t.; i/'
·-
-
-
-
Mr. Al carson, Chairman
usitn& Hydro Steering Com1ttee
.laska Department of Natural Resources
,23 East 4th Avenue
Anchorage, AK 99502
May 4, 1981
P5700.11.74
T.871
Dear Mr. Carson: Sus1tna Hydroelectric Project
Access Road Studies
acknowledge receipt of your letter of March 26, 1981, to Eric
culd, APA. Pl'esently, I am 1n the process of reviewing your COJR-
ments and recoanendat1ons. I appreciate the Steering Colllnittee•s
illinqness to work cooperatively with APA in identifying and
resolving the numerous questions relating to access roads and other
spects of the Sus1tna studies.
·e are presently developing a systematic decision-making process
that can be utilized for access road selection and for other
major decisions that will be made as part of the Sus1tna studies.
The decision has been mde to obtain air photos on all three
major access corridors, thus, eliminating the necessity of an
·arly decision fer a preferred corridor.
Our decision as to which corridor or corridors will receive detailed
stuQy will not be made until we complete our evaluation of overall
objectives, selection criteria, and data base. The Steering
Committee will be given the opportunity to review our selection
process and recommendations prior to us making a final decision.
Trus t1 ng th1 s meets with your approva 1.
Sincerely,
Kevin R. Young
KRY:db
~ ..... ~ :.r J; ~~
~U&U[ @~ &~&~~& JAr i HAMMOND, GOV!IIIOI
Utit•~\llT!UENT CU-' ~."-TIJR..:\1 .. R•:sotJil(~f:S
DIVISION OF RESEARCH & DEVELOPMENT
323 E. 4TH A VENUE
ANCHORAGE, ALASKA 99501
279-5577
May 8, 1981 nECEIVED
i lf',•/ 1 ·.: 1981
.. " , I r'
Eric Yould
Executive Director
Alaska Power Authority
/.J.ASKA POWER AUTHORIW
333 W. 4th Avenue, Suite 31
Anchorage, AK 99501
Dear Eric:
The Susitna Hydro Steering Committee has reviewed the Alaska Power
Authority's March 1981 Mid Report to Governor Hammond and the Alaska
Legislature. Specific comments from the Steering Committe members
regarding this report are provided below. In general, however, the
Committee was disappointed that APA did not permit our review of this
report prior to its circulation, as several members have discovered
factual errors in several locations in the text, and most have reservations
about conclusions reached by APA regarding environmental feasibility.
Dave Wozniak has assured me that, in the future, the Steering Committee
will be included as reviewers of all APA documents of this nature on
the Susitna Project,. and in particular I have been assured that the
Steering Committee members will be provided an opportunity to comment
upon the draft of the final feasibility report to the Governor and
Legislature scheduled for March, 1982.
The following are specific comments on the 1981 Mid Report:
1. There appears to be a great deal of misunderstanding on the
part of the External Review Panel (and perhaps others associated
with this project) regarding both the scope and the completion
date for the feasibility studies. The feasibility studies
currently underway will not, as we understand it, terminate
in mid-1982 when the Application for License is filed with
FERC (assuming the decision is made to file). Feasibility
studies will in fact continue for several more years in
order to gather sufficient environmental or other information
with which a reasoned decision can finally be made whether
or not to construct (FERC staff alone will require a great
deal more information than will be available in 1982 with
which they can prepare a draft environmental impact statement).
The March 20, 1981 letter signed by five members of the
External Review Panel refers to " ... feasibility studies ..•
completion in April, 1982" and " ..• present studies, supplemented
by appropriate additional investigations, to their 1982
completion date." While "Phase I" may end in 1982, "Phase
...t
.,
..
-
j
J
j
J
1
I .,
j
1
i
..i
-
'Iliff
-
-
-
....
--
-
-
-
: -~ ·7 .
-
-
-
-
-
-
-
-
Eric Yould
2.
2 Ma· ., 1981 ~:~,' .. ...;,.....-
II" will continue for several more years, as we perceive it.
We suggest you make this point clear both with the External
Review Panel and with the Governor and Legislature. We also
suggest that, via your public participation activities, the
public be fully and accurately informed about the length of
time required to (a) determine whether or not to apply for a
FERC license, (b) finally determine project feasibility, and
(c) obtain a FERC license and actually begin construction.
The Steering Committee is of the opinion that the report is
too much of a "sales document" rather than a balanced assessment
of what is known to date regarding Susitna feasibility. For
example, it is stated on page 7-6 "whether positive or
negative the overall change in the Cook Inlet salmon fishery
will probably be slight." Recognizing the paucity of supporting
data the committee feels this conclusion, and others like it
in the Environmental Implications chapter, are premature.
3. Individual Steering Committee members have found technical
errors in various places in this report. Rather than enumerate
these detailed comments at this time, you may expect comments
from individual Steering Committee members or their agencies
in the near future.
Finally, I have been informed that the External Review Panel plans to
convene in Alaska in the near future. I request an opportunity for
the Steering Committee to meet with the Panel, perhaps when they are
briefed on this year's field studies. Also, in order to keep members
of this External Review Panel appraised of future Steering Committee
concerns and technical comments on the Susitna studies, we feel it
appropriate to circulate to Panel members letters, memoranda, etc.
generated from the Steering Committee. We believe the Panel members
would benefit from Steering Committee comments, particularly since
they might not otherwise have an opportunity to gain insights into
state and federal agency scientific/technical, regulatory, and public
interest concerns.
I hope you find these comments constructive. We will provide Mr. Wozniak
a detailed outline of steering committee interests and concerns regarding
the Plan of Study at our May 28 meeting.
Sincerely,
ili
Al Carson
Chairman
cc: Dave Wozniak
Steering Committee Members
~ e
ALASKA POWER AUTHORITY
Mr. Al Carson
Cha1rnmn
Sus1 tna Hydroelectric Steering.
Coomittee
Department of Na tura.l Resources
323· E. 4th Avenue .
Anchorage. Alaska 99501
Dear Al:
June 2s 1981
'.f.. f -
Thank you for your letter dated May a. 1981 concerning the 1981 Mid Report
and associated matters. Regretfully, heavy travel coomitments within the
office have slowed this response somewhat. Nonetheless, 1t is important
tt1at the points raised by your letter be addressed.
_,
-..
..
..
-
....
.. Our current schedule calls for the publishing of a very well developed
draft of the final feasibility study report by March 15, 1982. I reaffirm
our c~itment to provide this draft to you and fellow members of the
Steel 'ng COOJnittee for review~ I think there 1s some confusion. however. •
concerning other doctanents to be reviewed. In principle, the Power
Authority welcomes the Steering Committee review of our various efforts.
Unfortunately, we have not yet agreed as to the 1tem5 worthy of Steering
Coomittee review. As I have noted to you on several occasions. we would
like to interact with the Committee rather than continue the intermittent.
somewhat adversary contacts that have characterized our past discussions.
If we are to be truly interactive, your cont~ibut1on to defining the areas
-
~
of interaction is essential. to that objective. Jet me repeat my suggestion ~
that the Steering Committee. ~ti1iz1ng the Plan of Study as its guideline, ..
identify specific areas and/o~ events and the associated degree of depth
with which they wish to be involved. Given a clear understanding of
expected areas of interaction, the problem of Steering Coomittee review
or nonreview of the Mid Report might not have occurred.
Insofar as future project milestones are concerned, the effort currently
in progress, Yar1ously callec:L 11 feas1b111ty Study~~ and/or "Phase I", has
as major objectives. detennining the technical and economic feasibility
of the proposal. and, if feasible, generating the data necessary for a
Federal Energy Regulatory Comfss1on {FERC) license application. This
step is bounded by a Power Authority contract with Acres American, Incn
a contract which terminates in mid-1982. That date ts consistent with a
-
-
...
...
-
-
...,.
~
L.
L:·
\ -
1
1.-
-
'-
-
.....
-
-
-
-
-
page Two e • legislatively mandated Power ~uthority recommendation to the Governor
and Legislature by Apr11, 1982 on project continuation or abando~t.
The underlying assumption is that sufficient information will be available
by that time to make a reasoned and reasonable judgment on whether or not
to submit the license application. (Please note that this 1s not a
decision to "bu1ld 11 or "not bu1ld 11
, a point I will address further on.)
Strictly speaking then, the 11 Feas1bility Study" will 1n fact terminate
in mid-1982, by virtue of the contract terminating.
If the mid-1982 decision is tO continue with the Susftna Hydroelectric
Project proposal, we will enter a period frequently referred to as
Phase II. It would be characterized by submittal of the FERC license
application, commencement of detailed engineering development, and contin-
uance of a substantial amount of 1nvest1gations of the project area,
including such subjects as fish resources. By mid-1984, 1t 1s anticipated
the license application, as su~lemented and modified bt the contfnuin?
investiTations, will be approv • Given FERC approvaland a number o
other, esser regulatory approvals), the question of build or not build
will then be referred to the State government, where a decision on con-
struction will emerge through .the political process.
Re<:ent discussions with the EXternal Review Panel suggests that they are
very clear on this sequence of events, and th1 s same concept, {although
worded slightly differently) was advanced in the Mid Report. Accordingly,
I must conclude that both the panel and the publ fc have been fully and
accurately infonned about the project flow. Certainly, there was no intent
to be anything less than accurate, and intimations to that effect warrant
strong objection.
I regret your letter arrived too late to accommodate a joint convening of
the Steering Com1ttee and th~ External Review Panel. As a partial accom-
modation to your request for such a joint convening, please let me note
that the meetings of June 3-5,. 1981 are open to the public, and members
of the Steering Comtittee are more than welcome to observe the proceedings.
(The Committee was made aware of this last week.} We agree brtth your
suggestion that the External Review Panel be kept appraised of Steering
Committee concerns and technical comments, and have no objection whatsoever
to circulating letters, memoranda!J etc., generated by the Steering COiflllittee.
However, a review of such material indicates the only data generated by
the coa~a1ttee to date are conments to the procedures manuaals, a letter
concern 1 ng the access propos a 1 s, and your May 8, 1981 1 etter. F1 na 11 y,
with respect to a joint converi.1ng, we are certainly agreeable. I think
we need further discussion to 4ef1ne format and attendance; for example,
I am not sure that our geotechnical representative would gafn greatly from
cooments advanced by the natural sciences C001ilun1ty. Perhaps we will
want to focus our efforts on the environmental representative, Dr. Leopold.
Further, to be efficient (substantial expense fs involved in bringing the
·. V~ii"'" i>.-
Page Three
panel members to A1aska and pay1ng their per diem) as \il:'e11 as ·t<t-. ,'i"_t ...
1 run suY'e you ,.,n 1 want to give some thought to the structuring ~~m .
content of your fom.al presentations. I would 'l>te1~~ continued dial
on this subject.
CONCUR: RAt4
EPY
Sincerely,
David D. Hozn1ak
Project r'1anager
-
,.
; ~:· ·;
-
-
-
-
-
-
-
.....
-
-
-
,_.
·--· ---------~· .. --.
0 f\
~lT&~[ @W ~~~~~~ JAr S. HAMIIOitO, GOYfflltOI
nEt•.\JtT~IENT o•· ~..\TUR.-\1. RJ<:SOIJilf~ES
DIVISION OF RESEARCH & DEVELOPMENT
June 5, 1981
Eric Yould
Executive Director
Alaska Power Authority
333 W. 4th Avenue, Suite 31
Anchorage, AK 99501
Dear Mr. Yould:
323 E. 4TH A VENUE
ANCHORAGE, ALASKA 99501
279-55 77 RECEIVED
JUN-9 1981
-~l<A POWER AUldORITY
The purpose of this letter is to transmit to you a proposed revision
in your June 3, 1980 letter stating the role and objectives of the
Susitna Hydro Steering Committee. The Steering Committee members feel
the following more accurately describes the role and function of the
Committee.
"The Alaska Power Authority through its consultant, Acres American
Incorporated, is carrying out a 30-month feasibility study of the
proposed Susitna Hydroelectric Project. Because of the magnitude of
this study, effective interagency coordination will be best accom-
plished through formation of a Susitna Hydroelectric Steering Committee.
The function of this committee would be to provide coordinated exchanges
of information between the Alaska Power Authority and interested
resource management agencies. Through this exchange, the concerns of
all agencies involved would be identified early and hopefully prevent
unnecessary delays in the progress of these feasibility study, appli-
cation for the Federal Energy Regulatory Commission license to construct,
and Environmental Impact Statement review.
As proposed, the Steering Committee would be composed of representatives
of resource agencies with responsibilities pertaining to the Susitna
Hydroelectric Feasibility Studies and/or the project's environmental
consequences. We therefore invite your agency's participation.
The committee would provide for interagency coordination through joint
review of project related materials and development of more informed
and uniform positions representing all resource interests. We believe
this will provide a more efficient process of information exchange.
Proposed objectives for this committee are to:
1. Review and comment on study approaches throughout each phase of
the planning process;
l
f
/
/
!
2.
3.
4.
2 J~ 5, 1981
Provide a forum for continued project review of all aspects of
the studies, for a timely exchange of information, and for recom-
mendation of study redirection, should the accomplishment of
specific objectives be in jeopardy;
Comment on compliance of the studies with state and federal laws,
regulations, Executives Orders, and mandates as they apply to
fish and wildlife resources; and
Provide unified steering committee comments to the Power Authority.
Should your agency elect to participate in the committtee, we recommend
that your representative have a technical background enabling him to
comment on the adequacy and approach of ongoing and future feasibility
studies, and be able to speak knowledgeably on the policies and procedures
of your agency with respect to the review of the Federal Energy Regulatory
Commission license application for the project and the subsequent
Envirorunental Statement (ES)."
If you have comments or suggestions concerning these proposed revisions,
please advise.
Sincerely,
rn~
Al Carson
Chairman
Susitna Hydro Steering Committee
cc: Steering Committee
•
•
•
•
..
-
-
•
..
•
-
-
-
-
-
..
-
-
~
-
-
.....
-
-
-
-
..,_.
-
e ALASKA POWER AUTHORITY e
June 18, 1981
Dear Susitna Hydro Steering Committee r·1ember:
Enclosed is a copy of the Draft Development Selection Report for the pro-
posed Sus1tna Hydroelectric Project. The primary purpose of the studies
su:rmarized in the report was to formulate the optimal Susitna Basin plan of
develo~nt. Acres has concluded that the ~Jatana-Devil Canyon bto-dam plan
is the preferred approach for developing the basin's hydroelectric potential.
Further, Acres recommends that planning and engineering studies be continued
on this b~o-dam development concept.
We are soliciting your comments on the evaluation process used by Acres, on
their delineation of relative plan impactst and on their conclusion that
the Watana-Oevil Canyon plan is the preferred basin alternative. The parts
of the report addressing economic comparisons with a thermal plan arc not
pertinent to the formulation of an optimal basin plan, and they can be
ignored for the time heing. The issue of economic feasibility will be
addressed more comprehensively in the draft feasibility report scheduled
for Harch 1982 and in the. l3attelle \vork.
The Power Authority places a high value on the Steering C~uittee input.
Please take the tirr~ to review this very crucial and significant report~
and provide us \'lith your comments. Ideally, there will be a c0tm1ittee
oeeting fn July wherein unified committee comments can be formally trans-
mitted. However, if a meeting doesn't materialize, cmr.ments by August 3,
1981 are solicited.
Enclosure: as noted
Sincerely,
David D. Wozniak
Project Engineer
cc: Ward Swift, Battelle {w/attach)
Phil Hoover, Acres, Columbia (w/o attachl
John Lawrence, Acres. Buffalo (w/o attach)
MFR: Same letter sent to attached list
:f
:·
e -AI.~ASiiA t•O\VI~R AU'l'IIOR11.'Y
SUSITNA HYDRO STEERING COMMITTEE
Bob Lamke
U. S. Geological Survey
It! a ter Resources
733 W. 4th Avenue, Suite 400
Anchorage, Alaska 99501
271-4138
John Rego
Bureau of Land Management
Anchorage District Office
4700 E. 72nd Avenue
Anchorage, Alaska 99502
344-9661
Brad Smith
National Marine Fisheries Studies
701 "C" Street, Box 43
Anchorage, Alaska 99513
271-5006
William J. Wilson
Arctic Environmental Information &
Data Center, (U of A)
707 A Street
Anchorage, Alaska 99501
279-4523
A 1 Carson
State of Alaska
Department of Natural Resources
323 E. 4th Avenue
Anchorage, Alaska 99501
279-5577
Tom Trent
Alaska Department of Fish and Game
2207 Spenard Road
Anchorage, Alaska 99503
274-7583
Larry Wright
Heritage Conservation and
Recreation Service
1011 E. Tudor Road, Suite 297
Anchorage, Alaska 99503
276-1666
Lenny Carin
U. S. Fish and Wildlife Service
733 W. 4th Avenue, Suite 101
Anchorage, Alaska 99501
271-4575
Gary Stackhouse
U. S. Fish & Wildlife Service
lOll E. Tudor Road
Anchorage, Alaska 99501
276-3800
Bob Martin
Department of Environmental
Conservation
437 E Street
Anchorage, Alaska 99501
274-2533
Mr. Bill Lawrence
Anchorage Operations Office
Environmental Protection Agency
701 C Street
Anchorage, Alaska 99513
271-5083
Judy Schwarz
Environmental Evaluation Branch
Mail Stop 443
Region X, EPA
1200 6th Avenue
Seattle, Washington 98101
(206) 442-1285
""""
-
-
IIIIi
..
..
-
...
-
..,;
wtl
-
-
-
...
-
-
-
-
--
·--~
"
'.:::"
....
-
-
-
.... ,
-
-
~ ALASKA POWER AUTHORITY
Al Carson, Chairman
Susitna Hyclro Steering Ccmrnittee
Department of Hatura1 Resources
Division of Research & Deve1or.mcnt
323 E. 4th Avenue
Anchorage, Alaska 99501
Dear A1:
June 18, 1981 .
(\
The wording of the proposed revision to the S!.!s1tna Hydro Steering Cmrmittee
role and objectives advanced in your letter of June 5, 1981 is fine. I
would now like to see it formally adopted by the Steering Committee. Sub-
sequently. I will "close the 1oop 11 with the various agencies origina11y
involved by issuing to them the revised ~rd1ng.
On a re 1 a ted 1 ssue, more work needs to be done by the cor.r.~i ttee on 1 ts
composition. Not only 1s 1t cumbersome to have a large inactive me~J~rship,
that sort of situation has a high potential far errors of ommission and
~arrassment. I again urge a concensus on establishment of an active
~~eobersh1p. plus some accommodation for the fnactive members.
(1) Attachelent:
A1 Carson letter, June 5, 1981
S1ncerc1y •
David 0. Wozniak
Project Engineer
cc: Ph11 Hoover Acres/Columbia (w/attach)
Kevin Young Acres/Buffalo (w/attach)
CONCUR: RAM
e .... ALASKA POWER AUTHORITY
.. :..,:_."
Mr. l.iob Lamke
U. S. Geological Survey
Water Resources
733 W. 4th Avenue, Suite 400
Anchorage, Alaska 99501
Dear Mr. Lamke:
-.. __ .
July 28, 1981
It would appear that we w111 not have a formal Sus1tna Hydroelectric
Steering Committee meeting prior to August 3, 1981, the target date for
your comments on the Development Selection Report (my letter of June 18,
1981, copy attached). Accordingly, I would very much appreciate it if you
would send me your comments ~Y August 7. 1981 at the latest.
FOR THE EXECUTIVE DIRECTOR
Attachment: as noted
Sincerely,
David D. Wozniak
Project Engineer
..!
"ff.
~
IIIIi
-..
-
-
wJ
"'tJ
-..
...
"""
...
...
...
..,
...
-----.-·--_,
-::::
-
-
.~IEMORANDUM
ro: Dave Wozniak
Project Engineer
Alaska Power Authority
333 W. 4th Avenue, Suite 31
Anchorage, Alaska 99501
State of Alaska
DAH.
FILE NO
TELEPHONE NO.
July 29, 1981
02-I-81-ADF&G-7.0
02-V-Acres-1.0
._FROM: Thomas W. Trent REcEIvED SUBJECI: Review of Draft
Development Selection
Report -Su Hydro
Project
-{'
-
......
v
-
-
._.
...
-
-
......
Aquatic Studies Coordinator
Su Hydro Aquatic Studies i\~G ~ 1981
Anchorage
"JWKA POWER AUTHORITY
I've reviewed the draft Development Selection Report for the Susitna
Hydroelectric Project and mY comments are as follows:
Page 1-4 (g) Ta~k 7 -Environmental Studies
Comment: I recommend the words in the last sentence i.e., large game
be changed to £i[ game.
Page 8-26 Environmental Comparison -2nd paragraph - a statement regarding
enhancement potential for anadromous fish and, the statement on page 8-
27 Environmental Comparison, 2nd paragraph.
Comment: A general observation addressed to these specific sections, is
that development of the environmental comparisons has undoubtedly been a
subjective process. The statements made really don't provide any detailing
of the hows, whys, and rationale for the conclusions drawn. I believe
we can accept a subjective process for evaluating the environmental
merits or deficiencies of a particular dam scheme, but it would have
been a helpful process for Acres to involve ADF&G, USFWS and others in
such an analysis to discuss alternative positive/negative impact possibilities.
I think this would have led to a healthy exchange of ideas. The exposure
of the fish and wildlife or other resource agencies to the same design
or operational schemes laid out to the Acres environmental review team
may have led to conclusions which were the same or potentially quite
different from the Acres analysis of the situation.
To sum up, we can't argue with Acres report since we don't know the
background information used to support their rationalizations or the
experience of the individuals involved in the report preparation that
drew the conclusions on fisheries .
cc: S. Zrake -DEC
B. Wilson -AEIDC
G. Stackhouse -USFWS
R. Lamke -USGS
A. Carson -ADNR
)7 .fl01 I R .. v <;/'7<;1
C·
~
.• ~"'""'"'~' •mormoflon and Dora Center 707 A Street PHONE f907J 279-4523
Anchorage, Alaska 99501
UNIVERSITY OF ALASKA RECEIVED
August 4, 1981 :' 1 If"\ C" 1981 . . . .J ..)
ALASKA POWER AUTHORITY
Dave Wozniak
Alaska Power Authority
333 W. 4th AVenue, Suite 31
Anchorage, AK 99501
Dear Dave:
Per your request to the members of the Susitna Steering Committee, I
have quickly reviewed the Development Selection Report prepared by
Acres. In general I found it logical in approach and complete in re-
gards to the relevant factors one should evaluate when reducing multiple
options.
I have only the following specific comments:
1.
2.
The location and environmental effects of developing borrow
material sites is not well documented and incorporated into
the first part of the report. Enormous qunatities would be
required for most of the dams, and the removal, stockpiling,
and transport of this material could be a significant factor
influencing the decision-making process.
Significant efforts are currently being expended in environ-
mental study of this region, the results of which are not yet
available. Factoring this new knowledge into the decision-
making process could have influenced the nature of the final
scheme; or is the current environmental study effort geared
only toward the effects of the "selected plan (page 9-1)" and
not for input to the overall selection process? In general I
found the environmental effects of the alternative options
addressed very superficially.
I hope my comments are of interest.
WJW/g
cc: Al Carson
Sincerely,
-L. /' }1(_ ~ L L
('
'· ./ ? ,_ ·~ . )/' '-!_>,,
William J. Wilson
Supervisor, Resource and Science
Services Division
Senior Research Analyst in Fisheries
~
,;
•
.....
.. _,
....
-
-
,
""' -
...;
-
•
...,.
-
-
.....,
IIIII
~~~~[ @W -
(J ~ @
,-... .. \ ' . { ( \ . ' ;
i Q\ I I ~ \ ~:. :·: ) : : uJ t..:.::J 1.1 u _ _ ..
/
l
I
I
I
437 E Street
second Floor
Anchorage, AK 9950:
Ut-:J•T. OiF t:~'\.IUO~~I&-:~1L\.iL 4'0.:'i~fEJ'iq_\·/~Tfla~~~;
j
I
'
P 0. Box 1207
Soldotna. Ata~ka 99669
(907) 262 5210 -
-
--
(
-
-
-
~
-
-
-
-
-
-
'jLH
i
\'OUTIIC!NIA'/.1 mr;·r•·,.; ;.
-...... ' r. _ ~-1
I . r-
;_;,\..1
lSR1
;::_L,:.;~.:... ,, . ..; .. -·· •• ..: . ~ • .J.~t r;
Dave Wozniak
Project Engineer
Alaska Power Au~hority
333 W. 4th Avenue, Suite 31
Anchorage, Alaska 99501
Dear Mr. Wozniak:
r-:
'~
P 0. Box i064
Wasilla. AtasY.a 99687
(907) 375·5038
August 14, 1981
We have reviewed sections 7 and 8 of the Susitna Hydroelectric Project
Development Selection Report (second draft June 1981). We find that the
plan selection methodology used in section 8 meets the objectives of
determining an optimum Susitna Basin Development Plan and of making a
preliminary assessment of a selected plan by an alternatives comparison.
The increased emphasis over previous analyses of the environmental
acceptability of the alternatives is good.
At this time, this Department does not endorse any particular plan. We
would, however, recommend the Steering Committee openly discuss the
Watana Dam -Tunnel option because of its reduced environmental and
aesthetic impact.
Thank you for the opportunity to review this document. We appreciate
your effort in soliciting Su-Hydro Steering Committee involvement. If
you have any questions regarding these comments please contact Steven
Zrake of this office.
cc: Steve Zrake
Dave Studcvant
Al Carson -DNR
BH/SZ/mn
Sincerely,
_fi~rlhd::-
Bob Hartin
Regional Environmental Supervisor
. ~ ' I·•·: ~ .. ,
(
l
fi\J ~ v <-v\,H
~~ .,-.,1; .:It-.
~·.-· ... 4' • I•• ·. ~ Cl
i ~ .. (d_yf.l~il71C .-.... F-
1 f"'li \ t _. n ' i i
n rs n .... ~ 'ii7 rt . -' . ~ I < ~,.. I~~-7 '
i:
' I,
i
1:
i· ~ .. \;
l
i~ i ..
~--c. . .
~ .
l t
I
I
!
I t i
If
l ~ r~
i "'
I;
;:
; •.. r E· ~~
!....:.
I. ''· !. ,._
!' .. ...
t
::!.· !=. r
·~ iii: ~-...
~~
~1
~~
]·
~.
~ f! If) ~ i~
I> I l tl 1 i n 'it , ..._ u~ ~ ~
fLit::: ~u
f \ • • &' ' ..... -~ 1A1 n u\ ~, ·i ' lu.\ -'\ fi ' • "\ I ' trJbU\1~ u~u-u
DEr.uiT...'\IEI\T OF ~&:TIJILU. BESGIJB.£ES
(JNI!JiliDN()FRES:£Ai!IDI&~'T
.. eabei"' 5. nlil
Ml'>; Er-ic 1ta14.,. Executive iHrK.t«
Ala$1a t\wu ~icy m 11es.t. fourth Avemae
~" Al.uta 99501
Dear Plr + You.ld:
111-ta•• -=:samt
:=£ 4111 AVi:..''fvt
~~g;. ~A#A ~~ tl~
R"E.C t;nt E.D
!l~f/'\ .! *r-1\ lV..J-1 \1-..:: ~· -.;.~
~~~i:V.!t ~ .. ,,.,~.,.., ~ &~-" J'lliltl"-"'\.lo-
,';/
The pu.~e of ttrb 1e-ct-...,-is to t~t. to the Alaska Power Authority
{APA} ~ts ~ the Sus'ftr.a ~lectric Steer'iM Caft!ilit~~ (Sl-;St) ccn-
c.enrtng m.~s ~ls far access ta the ~-t"''pQsed SuSitr.a. Rivru-d. sit€S-
These ~~s are in TeSponse "to information providi!d the snsc !rca two 4CC@:S.S
rv~te tseetlngs with MA ~A their-c~tra-ctfirs and tbe ~ts ~red. by /IPA
c:ontnctors and distribtrted during tnese ~;tin9s.. At the Octobet 20!! 1981
~ting APA ~YMUd SHSt: ~ts by ~v--..rer 6, 196l.. T.lti! S.li.SC ;;ppr&ia-tes
the fact that APA c-ontinwl:"j det..anoo CQr.S1de.'P<lti¥n and ~...udies ¥f s.ev~~1 i9;e$S
roote C?ti~'1<s tu~i:i ~ rather tlwi f0Cll31ng o.-1 a :single ~..~: ..
...
....
...
-
..,
-
.,
-
...,;
-The SiiSC r~iew identified four anus.s of ~rn t.r.at 12rited ~tf"""ii.>~-_ )~~.::i
Thu~e four 41'-e: I ,.,._ ~-~
,
.1.&
'! £..~
3 ...
.6 ~ ..
t s~_ s Ti.,.,.
A critique of ~~ studies of ~cess rout~ llltrirh prQvic-e for ~·~"E ,.j~ivj,.
t--i~n of !'~ ...... ~ i -/, 1 1 .... t.n · -...R:. • t .-.rr. ,.....£-
1 __ ;.., ..... ..,I;,.;
Tt.e relatiQ:llShi? between t1j!JJ~ {}f a-~c.es~ n:.ute con=:.truct"}sm .i!ndi~-"Y~ :<:, ;t
t:" -~ ... D .. -.11 --• ,..i:"!"..-J" \ I .. ... I .. ; ~ ; J • ~ .5I , ~i!l tn-'!f'""''D" Ji~tHat.cr.t ~\S:Si~i \r'-~! d~pn:>¥4.. t\lf' ~-r·~ -'""'
·z ~ ::S...,;
The. re-lationship of access route_ d-::Cision ar.d ~eS of· ~~~s:~ to l1g 2 ~ -·
re•ltana.l 1ii.fld use manags:rart pcihc.1es. ,..;: ; ,
Thf! "iSS.ut.~ resultant from land status ana 1ar.d o.nership
th :'1~ .... .,-eed i -""' . lt! , ~ ...,......... pro ... ec ~,. ..
-
f / I · ·v, :-.. ~ . . ... ... -.tffec:t.&1 t¥ -.ocr~ ~-
~ ~ 'F"':i-i '!' ~~ i ; -
The assessment of O]n"idor rnu-"'"~ ~1t...~.at1ves should.~ ~Br.Jati?-1¥ -Je1bh -;:;~:J•
the: pot~tial ~cts af be~ sit'T~ anrl ac.ce~s Ui t...~e sites. arid tr~.s~ -~ ~-l
-~=--· "'i" frl · t:"' ,. •r> ~.-. ..____,...;..4-· ......h.: 1. ~ • -~•1T +-..:.-l 1., ~=-...t.. c-~..,,~~lQll I tH-~\.•'1 roo rng.. R\.ve..J;.l 'w\.io l ~i.ii.JJ"S -ucn ~er,e ~ ¥¥0 T or-I,.( -<P•i:· ~· po .... i"" . ..;;
in .regaid to these athe3" pr!l,jc-~t access needs ~1d 'be highly des1rab-la f,~!!iF. "·-:
"'~1· (:.: ""''" .. • ... .; .. -t i ; "'-"" .... Iu •• ~:!iio111g ._r.w::na... ~c i = ~RI-4
·,'
• ;;o-:..a. i : ·;::;--..
1;-·TE.s
~ i. ··~-~~
~-~ , :::~
~-,,.._. __
! ---
. , r -
I
.~:c-•. : . ~
\ --~ -.... • 0
.c
r-
~
i
' i-.
f '-
t
f·i ,. ,,
~1-r: r· fi u n--,, r i .
!·-tr· ! .....J.•
L I .
~-i f~
(
I .. -1· ~
I r ,;-
!= ~;
&" ., ..
~;.:· g:_
i'·
t(· H ·-
H~oo¥·; ~
~!
f~
·' tl lj-
n 1-~
J-;~
~;-... ~ ·~
il
i'· n-,1
iJ
J' ~~ F-.. •·· ~·
f~
t 1!-
j: r r-
..
rne access prefe~es: ~ressed below pertain tD the ~emrral ioc.tt1oos
c;ited. for tbe corridors and ~re based uoo."l the envirot'111efit41 diit.\ :1nd t:Q1'lr.lte
sions ccnUined envil"''f''2rtta1 documents ~ for SUbUsk 2. .. 10.
Acc~s Road Asses~t. It does I'JI)t. ~t. our -~t o a part.1cu1ar
I~ 1 e-\flde corridor~ as presented ..
The SHSC ~s wit.'~ the Terrestrial fmril"QPPl!eeltal Specialists~ loc. ~i
tiQn that 4a:ess via thf! Alaska Ralli"Caf.f to Gold Creek is envif'ORil!Bltaliy pre:-
ferabla... bUroad access to at least Devil ynyon lDild alleriate tile need for
• s1491ng area a't &114 ~ and the consequent m..tn 4Ctivity~ bnd ~ .. fuel
Siiills.-r ~--:4 other ispacts on the Gold ~ &..""ea... we rec.ogn1.zed that • s"bginq
~n!il. at Devil CAnyon would be required in inY ~-The: use: of tiris U"M. as t.~
tenaiAUs cf a. raili'oiirl ~rs to lllilke ~ QTei}t deal of se!'".S.e... AddiUonaH:;. we
feel Ulii't the~ sidf; ~e "fnJII ~ld Creek to DevH Caaycn is preferable
since • trail clready eJ:ists t!1a e. FniB Devil ~ tc watana. ~ prrler &
route on the north side of tile Susi~ fiver... At Ute October 20 .. 1.9ll ~t;1~
ttE SJ& lillS 1aror1101 ;,y ~~r. tlilvtd wozntak ot PPA ta&-e ~ 1!!lel"e lllll) {2)
~itiona.l r.1t1road rcul:.ei110de op-tions (a total of 10:} • If feas1!tle tee ~
a-ally prefer • n11 liOd2 of access to md vithin tile project site.
The Sh'SC ide:nt1fi~ three {3} tnV.1~tai1y sen-si'tive iTeaS that s.houid
~ avoided~ rnose a~: .
1. The rouus frra the Denali Hiqhvay.
2. Tl'E rnu.te -crossir...g the lrAi1an River and t.hroi.i9h wet.larnts t.o the Parls
tHg~y7
3? The roo...t+...e e-n t.~ sooth side of the Susit..""-4 River tnlil!i Devils Cdnyon tc
the propos.E!d &a tar.a dillm site.
ln eva1uat'if19 thr. access f'0'4~ selection proc€'ss u.r..dert4ken by t.~ APA ana
tts contr'a~I.Drs,. t."'.e Steering Caimittee questions the validity of the power-on-
1 ine. 1n 1993 ass.~tion/mandat~. Tl·i@ "Ve' ve got to burry up and put in it mad
tQ meet the !993 deadlir.el'! ~proac.'I appears~ 1i"tm OJrrenth available reptJ~\-5
ar.d the briefings received by the Susitn.a liydr-~Iectr-ic St.eerin9 Carmi tt.c."".-: e-n
OcUiber 20~ 1981 ~ to point "t!..~rd the necessi"ty of a pion~..-rr.,h,"'-d cvnst:J-~...u:ted
b£fo.---e d ftRC 1 icense 1s gr~nted, or se1ect1tn1 of an l!p~nmtly env1rormenu11y
UR~c-n+~hla ~~-11· ~in~~u ~r---r ~·~A iN~ c-'t'~\r' .... k1~ -P !~f~..J aa~J ! WV4r~a
Local utiiities a~ net apprtUichinq c-c.>tstructicn of .1 project the magnitude
of S~sitr..a in 1993 as a for~on~ conclusion ar!il are ~kif!z3 cont1ngt:-:r.-ey pl~ns to
met projected power r~-d:i~ Gas and coal g~ented p==wer options are bein9
e.x£"~i~-OO~ ln add1 t1cn. ff!asibO i b studies are Cll •• e.nt1v hef~ undertaLcn by
the U~S. /;my em,;. of. E.nq ir.eers ar.d t.~ A0A at nt..E-~:'"tlUS~ pnt.entia1 ~dF"..;-alectric
generati~1 ~ites. T~ ¥~ttel1P ~ ~1 -t ~ ~'+~; P~.er A1t~~ti¥e Study sr~~Jd
provide "lnslaht in1:o addit1o"-1 n A.s SuCh;; Hi! oe!ieve
s..i~W• t.'M: lSS.J 'cicadi ir~~ fer-y'O'!tf!r-cn-1 ir:-e f, ~ Su.Sit.rs ~~ no-t: t--e tr...a"t fire and
i~erati ve. Thus tJLa: ~~t.SC da~es not be 1 i eve tri€! 1.993 d.e.ad.l i r:=e sttOu 1 d c.ons~-a n
tJ~ ov~an decision ~raking proc~s atrd the or-derly pro-gress of various stud es
an project feasibility and ardrorEaita 1 im-pacts. Peniiittir.:g citid r£So-rJrce
a~e-f'.cie~. \r,\:.Iud11f9 fffiC. sfi-O".Jid be &J=-scted to 1tnk a pioneer r-oa4 to tnc:
OveJ""a 11 ;rroj e-c.t *
,, ~:':.. --~--
'" -f;tl . . ' • -tt. ~·r <= G' . ~ ~ • .) .,
.,C'
f
{:
'• ,.
!•
' \) q
..
!
i
l
t
i
i
l . ~
!.! lj . ' t~ i,.... ...
j { u·
I• !1 n I;
f~
~ ": r;
d f:
1!
(:'
Pu.b11c at-tess to the d....~ sites and through the Upper Susitrn1 l'a Hey is
COiftPl~ and a contruv(•rs1a1 subject anrl -.e believe this issue Sthau1d be 9ivet1
thorough enlua.t1on in the route selection process. Hmf COJ'I~tructioo,..related
..I
access is obUined to a ~reat extent de~ines the project·re-1ated wildlife and
soc1~i~ i~cts. The APA has bea-n soliciting the views of 1oca1 residents .J
(T41keetna. Trapper Creek .. etc.} in reg~rd to the ~ccess que~ticn. The m.ijorit.y
of resfdents 'llmnt to minimize i~ct.s t.o both their c('mnllnity an<1 tt.e Upper l
Su.sitna VaHey_ The APA has solicited the views of the·state .2r.d federal r-esource J
&lgencies. 1t has been the pn?.dOPlinant v1~ of these agencics:r which represent
public intere$t~ on a state or national level, that project.-related ~i1dl He
impAets should be limited to the gxiiiUR extent practicable. In addition .. the
APA has expressed the desire toe:~iurtz~ the option~ for future public access.
we· beliaye that these views mesh, K~i:r:ir~Y 1mgact..s and maximi.ting options tor
future publiC iCCS.$S can be i1Chi~.Ved t>y J:rljj;iCking,.. to the e..xteftt ?QSSible7 the
status quo. for examc>Jc. to provide ful1 public Access through a road systen,
fo~loses the iuture-optiQn of maintaining the existing character of the Upper
Susitna Valley ..
Use of rcl'H as the access mde increases the pet.entia1 for ma.nag~nt and
contro 1 of S(lcioecanmt i c and envirorrnentaJ impacts.. ~ h;~i zed nil use provides
for the following advanta9es over road ~c~ess:
l, ~1nta1ns a ~imum range of future decisiQn options9
2. ProYid~~ fo~ control of work~~ 1mpacts on ioc~l c~Jn1t1e$ and wild-
life.
.._
,} ..
4,
5.
Oecreeses the pctentia1 of hazar~ous ~~terinl $pi11s due to adverse
~ts~r condition$ and ~ltiple ~andliny~
Disturbance to ~1ldiife adjac~nt to the route c~n be more easily
~;ontro 11 ed ..
Di~t access r\ght-of-way ~lat.~ habitat losses can b;! si<)ni ficant1y
HmH.cU ..
Briefly tr~ land status of the proj~t area has not changed significantly
within t.'1e l.:st year.. There al~ several ~pJex pro01B!'.s c.onc.crrdnq Tand status
that r~ve t~cn brought to your attention by BL~-
ihank ycu fur the Ol)port.uoity tQ -review ar:.d Ceiritrrent on the AcGe~~ Road
A~scss.ment doc~-ents.. We look forw~rd to rc.ace1 vi o-~ the final ver.~i.Q.n of these
doct:r.ent:i after Nove11ber 15, 198L and anticipate prov1d1rrg addit'iofla1 reco.rn-
~-'€:nrlatfons into th1 s ded s i Ofi-ti1aking proce$s ..
s i i'tcere !y 7
f"\ ~ 0-\.J..l \~ ...
fl.l Garsonl C.hai'f"i!'.an
Susi~~ Hydro~Iectric
Steerifi9 Cc~it~~~
ce: o_ Yozn1a~. APA
Steerirrq C~nii tt~ ~-'tl-nt:-el·s
R. Stoov~
..,)
t
.J
i
j
..
J
J
' .J
I
,.i
l
J
~ ...,
J
J
~
.J
7
J
..
IIIII
-
-
-
-
• f:i·
t·;., _,.;
~'
fi.
i,;· ..... :·;
~::-:
:~~
--.~
~i
---l~
e e
AGENDA
SUSITNA HYDROELECTRIC STEERING COMMITTEE
Date: December 2, 1981
Time: 1:00 p.m.
Place: Alaska Department of Natural Resources Conference Room
l.
2.
1:00 -2:30 p.m. S.H.S.C. response to ACRES request for formal
agency comments on elements of Susitna hydroelectric proposal.
SHSC and D. Wozniak, A.P.A.
2:45 -3:30 p.m. S.H.S.C. response to information request from
Birch, Norton, Bittner, and Monroe. SHSC and J. Lowenfels.
3. 3:30-4:00p.m. Other SHSC business.
. .,.
1 e e
,/ ~U&U~ @~ ~~~~~~ I JAruwoND.UWIN~
r:.~ DHJ·~\IlT.\IENT o•· NATUR..\1. RI<:SOlJRf:Es I
! :~'
;, . 323 E. 4TH A VENUE ~ DIVISION OF RESEARCH & DEVELOPMENT I ANCHORfG~;:;1.f'F~ t99501
~1, ....
t ..
~-t:~
-~ ...
December 9, 1981
Mr. David Wozniak
Alaska Power Authority
334 West 5th Avenue, 2nd Floor
Anchorage, Alaska 99501
Dear Mr. Wozniak;
~ !~:C 11 1~}~·; t
'-'·'-J-;~:~::;\ ~1 0VJEf\ i\U j; ;:.,. ; i t
The Susitna Hydroelectric Steering Committee (SHSC) would like to receive
additional information from your office regarding the status and progress of
the Mitigation Task Force. As you know, preparation of an adequate Federal
Energy Regulatory Commission (FERC) license application requires that Exhibit
E identify the proposed measures to mitigate impacts or to protect and en-
hance the resources. We believe coordination of this vital study item
should occur early and on a continuing basis. I am aware that the APA has
also recognized this need by creating two Mitigation Task Force core groups
composed of principal investigators and a Mitigation Review Committee com-
posed of representatives of various concerned agencies. While several mem-
bers of the Review Committee sit on the SHSC, they have received no informa-
tion on the progress of either core group. Additionally, the Fish and Wild-
life Mitigation Policy recently developed by APA for the Susitna Hydroelec-
tric Project stresses the need for close coordination. Although no time
schedule is established in this mitigation plan, it is obvious that steps 1
and 2 (identification of impacts, ranking of impacts and identification and
review of mitigative alternatives) should be substantially completed by now
if step 3 (development of an acceptable mitigation plan) is to be achieved
by the March 15, 1982 draft feasibility report deadline.
Therefore, I am requesting that you provide any applicable information
regarding the Mitigation Task Force groups and their progress to date. The
minutes from past meetings would be particularly helpful here. As the SHSC
is eager to discuss these concerns, I believe a short briefing may be most
effective. I will be contacting you to arrange for such a meeting, hopefully
during the week of 12/13/81.
Sincerely,
ru~
Al Carson
Chairman, Susitna Hydroelectric Steering Committee
AC:db
cc: Steering Committee
R. Stoops
Quentin Edson, F.E.R.C.
IIIII
..;
-
..;
...,
-
-
-
-
....
.....
-
-
...,
....
-
-
-
-
--------------------------~---------· -·-
ALASKA POWER AUTJI()RITY
334 WEST 5th AVENUE· ANCHORAGE, ALASKA 99501 Phone: (907) 277·7641
(907) 276·0001
r-.
~-
r ALASKA POWER
AUTrtORITY
SUS'ITNA
r FILE P5700
. II _
1
3EQUENCE NO.
F, d/75" ..
I
:1~1 ~ ..J > I --o: < ~·.o t---I~ 11) 1-(J. • -..... ~~, 3 ~
------·
I : [" ': .V
·--~--F f
VJ •t
--=~=/ c~_~J i xt.:. J !_; ·;
r-1 ;;(J' -:,~·---'-----
1
J? -: --;I P:; H 1-· ! E::s :·_
I c-• 'T ---~~·~ L I
C-1----i-
1 M R'J
--,-.-·~--
1
r·. R~ ----r--1 ~ J ;=
!-~1-
Mr. Al carson
Alaska Depar1::IIent of
Natural Resources
Research and Develo:prent
555 Cordova
Anchorage, Alaska 99501
Dear Al:
December 10, 1981
RE:CE:iVED
DEC 14 1981
ACn .. .., ........ uuna~ uu;ul(rORATED
In late November, 1981 you approached rce with sane concerns
relative our on-going effort to solicit formal coordination on various
aspects of the Susitna Hydroelectric Project. This led to a series of
rceetings between ourselves and the Susi tna Hydroelectric Project
Steering Committee. To broadly summarize those events:
1. Acres Arrerican Incor}X)rated, acting for the Fewer Authority,
has ccmmenced circulation for formal coordination certain
building blocks of the studies that will form the basis for a
project licensing recommendation.
2. In rrost instances the agency heads (addressees of the formal
requests for coordination) referred the request to staff for
analysis. Alrrost without exception the staff involved also
had been serving on the Susi tna Hydroelectric Project Steering
Carmittee. largely due to this relationship, the individual
agency staff members elected to use the Steering Comnittee
structure as a vehicle to discuss their formal coordination
conce.r:ns. As a result of multiple interactions between the
Steering Cornnittee and the Fewer Authority, a number of issues
have been clarified and options for agency response to the
Acres request for formal coordination have been identified.
The Steering Carmittee has S1.li'Ilt'arized its conce.r:ns as folla.-vs:
1. In same cases, the documentation of field study results is not
available coincident with the request for agency comment on
aspects of the project.
2. There has been no decision made yet by the Pa.-ver P..uthority,
the State legislature and the administration as to whether
there will be an application to the FERC for the construction
of the project.
. )
C.
'
Mr. Al Carson
December 10, 1081
Page 2
3. Sare of the agencies are concerned al:out responding to bits
and pieces of the prq;:osed project without being able to
evaluate the ~tire prq:osal.
To clarify the Pc:Mer Authority intentions relative the request for
fo:r:roal coordination, it is appropriate to look to basic intentions and
objectives. The present and proposed FERC regulations clearly encourage
pre-application coordination; First, to assure that the project
planning process has taken into account policies and guidelines of
local, state and federal agencies, and second, to assure that the
applicant has solicited agency carrrents and concerns and has atterrpted
to address them. Specifically, the proposed FERC regulations
(anticipated to be in effect by tirre of license application, July 1,
1982) require a request for formal coordination from agencies, provision
of up to of sixty ( 60) days response tirre to those agencies, and
-
-
-
--
-
inclusion of applicant response to agency formal carrrents in the license ..
application. Therefore, one rrajor purpose for the request currently
circulating is to canply with FERC regulations.
The Pc:Mer Authority is anxious to acccmn::::date agencies and the
Steering ~~ttee in the decision process. We have demonstrated this
-
in the past and wish to continue that policy. Our requests for fo:rma-1 •
coordination are very much intended to accarnodate consideration of
agency cc::mtEnts in the fonm1lation of the project and in the decision
process leading to the Power Authority project licensing recommendation. ..
Clearly, our ability to use ccmrents in this fashion is very much a
function of when we receive them.
.
In response to regulatory require.rrents, and to our best judgerrent
of when agency cornrent will be rrost productive we :perforce must persist·
in our requests for formal coordination. We hasten to add, ha..;ever,
-
that we willingly accept interim ccmrent, informal carrrcnt, or any other -
variant that gets the information to us in a tirrely fashion. Be.:mwhile,
we will attenpt to make available pertinent dcx:urrentation of field
studies as early as possible so as to assist your review.
I hope this StliTTt'a.I'Y assists you and your colleagues in deciding heM
to respond to our requests for formal coordination. If other facets to
this action emerge, I would welcome an opportunity to further discuss
them with you.
-
-
. 1 .. 7?Jtt~~-FOR THE EXECUI'IVE DIFECIOR
DaVJ.d D. I·JoznJ.ak f
Project Engineer -DI:X'l/blm
cc: John Lavrrewnce, Acres Arrerican, Buffalo -
-
_)
ALASKA POWER AUTIIORITY
334 WEST 5th AVENUE· ANCHORAGE, ALASKA 99501 RECEIVED Phone: (907) 277-7641
(907) 276-0001
r
'
ALASKA 'POWER
AUTHORITY
SUSlTNA
.... FILE P5700 . II
~ ai
a: a: t:O 1-L~ ~ U')
« 0
. .
--
--
--
--
-
. -
-'= -
.
Mr. Al Carson
Depart::Irent of Natural Resources
Division of Research and
Developrent
555 Cordova
Anchorage, Alaska 99501
Dear Al:
DEC 21198i
ACRt~ 1\mc.rtnintt linaJKrORATED
December 15, 1981
I am in receipt of your letter of December 8, 1981 soliciting (on
behalf of the Susitna Hydroelectric Project Steering Committee)
additional infonnation concerning the Mitigation Task Force. · I am happy
to canply, in part because it affords rre an OpiJOrtunity to correct sorre
apparent misconceptions.
First, while I have no objection to Steering Ccmnittee
participation on our mitigation planning, I am sarewhat surprised. As
was made clear early on, mitigation planning (and specifically the
Mitigation Task Force Review Group activities) is being don~ within the
formal coordination and consultation framework of the Fish and Wildlife
Coordination Act and F. E. R. C. Regulations. By contrast, the Steering
CamrrQttee has worked vigorously to remain informal commentators to the
Sustina Hydroelectric Project pro!JOsal. If the Steering Carrnittee
elects to join us in mitigation planning, it should ~ understood that
we will t..reat their participation as "formal". That in turn leads to
other minor procedural concerns, such as what to do about dua~
~ representation, etc.
Second, you misjudge slightly our timetable on mitigation planning.
We are just nCM in the midst of ide.ntification of impacts. Physical
constraints have led to this t:i.rretable: Field studies had to be
corrpleted and sumna.rized, hydrology data form.Ilated so that pc:wer
generation simulation (which leads to water release/stage information)
could be done, etc. We have by no rreans fully seeped impact yet, but we
are rapidly advancing.
~'lliich leads rre to the key I?Oint; when will an assessrrent be
possible? The most comprehensive will appear in the draft feasibility
rei?Ort, to be published March 15, 1982. A less canprehensive, but
[_
-)
...
nonetheless fairly rigorous, assessrrent will be provided to the Review
Group when they convene January 20, 1982. I know you are a rrember of .
that Review Group. You should be receiving your fonnal invitation very -'
soon, if not by now. I suggest Steering Conmittee involvement, if any,
be subsequent to that convening.
FOR THE EXECUI'IVE DIRECTOR
Dr:W/blm
cc: John Lawrence, Acres Arrerican (w/cy of carson letter)
Quentin Edson, F .E.R.C.
I .;
...
...
...
...
-
....
IIIIi
i
j
i
J
~
.J
...i
..J
1
J
J
J
J
IIIIi
-
-
-
-{
-
-
-
-
-
ALASKA POWER AUTHORITY
334 WEST 5th AVENUE· ANCHORAGE, ALASKA 99501
Mr. A 1 Carson
State of Alaska
Department of Natural Resources
323 E. 5th Avenue
Anchorage, Al?ska 99501
Dear Al:
December 17, 1981
-'
Phone: (907} 277-7641
(907) 276-0001
Just a quick note to advise you we will be meeting with the Cook
Inlet Acquaculture Association on January 21, 1982, 5:30p.m. in the
Kenai Borough Building. This meeting will also be open to other special
interest groups and the public, who will be notified via direct mailing
and newspaper notices. We will be discussing the probable impact of the
Susitna Hydroelectric Project to the anadromous populations.
You might want to pass thi~ information to your colleagues on the
Steering Committee. Your, as well as their, attendance would be welcome.
FOR THE EXECUTIVE DIRECTOR
ODW:mlj
cc: R. Mohn, APA
N. Blunck, APA
J. Lawrence, Acres.
s./7rely1 .~ /
/~
J.(avid D? Wo;niak
Project Manager
I
I
--e
I
I ~¥&¥~ @W &~~~~& JAY S. NAMMOIID, GDY£11101
ltEJ•~\IlT~IENT 01-' NATlJRAI. lli<:SOIJRf~F.S I Pouch 7-005
~ ANCHORAGE, ALASKA ~ Dl VISION OF RESEARCH & DEVELOPMENT
276-2653
January 14, 1982 ', r: ?" ... ~: 1 \/ r: o
1 /\f"~ t '~ 1;:~~~2
Dave Wozniak
Project Manager r 1 __ '· :',:\ r'c\~:En NJTHORirr
Alaska Power Authority
334 West 5th Avenue
Anchorage, AK 99501
Dear Dave:
Per our earlier discussion, this memo identifies the topics the Steering
Committee members believe to be of mutual interest to Dr. Leopold and
ourselves.
I want to Pmphasize that the Steering Committee members recognize that
Dr. Leopold s role on the External Review Panel is oversight in nature.
Thus, the Steering Committee members will be leading the discussion on
the topics listed below. Our objective is to review what we believe to
be the most important Susitna Hydro-related issues in Dr. Leopold's area
of interest and expertise.
The issues and brief descriptions follows:
1.
2.
3.
4.
5.
Fish and Wildlife Studies. Discussion of scope, timing and current
status in relation to Susitna hydro feasibility decision making
schedule.
Fish and.Wildlife Mitigation. Current status and summary of miti-
gation Review Group meeting of 1/20/82 (I understand that Dr. Leopold
will attend 1/20 meeting).
Instream Flow Studies. Relationship to mitigation, downstream
impact assessments and power generation-related flow regimes.
Access to Proposed Dam Sites. Implications of route alternatives
and public access on caribou, moose, and waterfowl.
External Review Panel's
schedule, and products?
Committee to continue a
level?
Role in the Future. \mat are plans,
Is it useful for Dr. Leopold and Steering
dialogue? If yes, at what frequency and
..
..
9951\1'
....
-
...
...
IIIII
...
...
...
...
...
..,
-
-
-
...
-
--
-
-
-
-
-
-
-
-
e
Sincerely,
eft~
Al Carson, Chairman
Susitna Hydro Steering Committee
cc: Steering Committee Members
Reed Stoops
•
2 January 14, 1982
3JN30NOdS3~~0J Sn03N~ll3JSIW
P-8 XION3dd~
-
-
-
-
-
-
.....
-
-
-
-
-
,
~i-.._ ,. . .,~ .~ .,.
( .
I \ ... -: ...... ~~~~ ;,, -f:··~· ....... ~~ '{' ;;.~;... -· .... ~ :~,
• I .:-:." •• \i-\
~-
RECEIVEO·ocr t 0 1~79
·~·~
RECE1\ SO
' . ' I...
H~. ~--)~\ \L:J~Jl ~ '\~1 •\
'-.,-:;.·~. . ~ ~ ........ '9.' ·.{;.:----/
UNlT~D Sf.A'f£S
DEPARTMENT OF THE iNTER tOR
FISH A~D WtLDLIF~ SERVICE
•::.~ D 2 7 \~j ... =il ...... _. . "'" ,,.,.;
i...
L
!
, I
~
L
1
t I
I...
-
-
....
I...
.....
-
.....
....
-
101 'l (: H,ib()ft if (l
··"~ ... -.,~~!..~~~~r $}~\ j'l,J¥{~ Aur~..Ci;ll!
ltH:;Ef't.\' REFElt Yo· ANCHOR A~!:, ALASKA ~SS03
rn.i
~.r. £ri~ P~ Yould
n~~cutiv~ Director
Ala~~ P~r AuthQr.ity
i'07) 276 3BOO
~ 4 SE? 197'9
333 WCJ;t 4th .hvr.mu:~ .s~.Ji.te 31
}~cl~orase. Alaska 995~1
D~r Mr .. Yould.:
'We we~e inf.o't"rned ll:r you-r l~ttllt:' o-f AtiP.\l~t 28. 1979, th~t th93-Alas
Po~~ ~thQ~ity (APA) is pr~paring an application for license to
Federal Energy Regulatory Ccm~~~ioa (PERC) for tb~ propo~cd nyd
electric Pu~er D~eiupment w1th~ th~ Uppe~ SUH~tna R1ver ~ia,
Aiaska. The purpt)!Se u£ dll~ let:ter lis tu ;:-oint out federal fi:;h
vildlife ~~pon~tbiliti~ and to insur~ adequate conside-ration ot
fillh and \r'l.id1.lfe tter.ou~cc: lo~z prevention 7 Tllit.ig~tion~ r.o;'3}lcn~R
tion~ and enh.ance~ut throughcut the piaun..Lng ad de(:Lfi.un-cak.i.n~
proees!l ~.lWJHlci3tc<1 'tl'f th th~ S!.J~d.tT~ prc,j~ct.
Th~ J>t't;l-applic.atio~ pleP.Jll.Cf; pe~1od as8oc1ati!f.i with the propoiSed
SWiit:::a HytL · !!lcc:tric Paver DOL'!£!1cp~nt i1; v~ry c:r.it:'ical t;.·m~idr:rri
the magn1tud_ of tbe p~ojectt limited !::x.i.rlting data £o.r £i.eh oind
vildlife re.$0 ·. ct:~, ;i~d ~urtt of effort required for the filing f,)
iJ. 'o;t;.ll"'t<-i)r:c~iv ... · applic.stion for license with PERC. ·m··-aaa·:!.tion,
c~prebensive o.-. l.y p).~tminp. ia -reqt.li$:!.tn tn thQ ~n~if\ninn f)f an .
n~ • ..-1 .. "' .;.. '"" .... ' • -• ~ en"';l. ... oomt:nt.os.ly ~Hmnn :proji!-c;..,. llnn op,.tm:u ~1~e o;. the pl;:1nn1.ng pe-r ..
th~-reby min:hrizing the potential for delay in tbe proce2sin~ of
n~c:!:,O;;;ry ~rnrit and lic~ns~ ~~plic~tion~ r.tnd CG'l:l!Plrir-JF. -.;fth Vi'l
~nvi~o~ntal r~i~~ r~quirem~nt~.
Fede:c~ s.sencic:l' in'7ol.vc.d in the ~nalyd~ aod/or ~pproval of a
nu:-ieder~l ~:t.t~r-~elated project have -cauy r~$puo~ib1l~ti.ee un•Jer
various E7;ecutive Orders (EO}? l~,s~ and roliciea t•:t pr~vent •Jnd
rrltir,ate i.mp~i;tS to ftsll ~nd "i'i.J.dli fc rr.~:a:n.tr~c:~, ~.; .-,11 ;;~ ~o
~nh~ncc t'hosc: 't'C~Q'.lr~f;\:i. To i:Jnntify nnd imn::-c: n:c:og-ni tion of
directivi!e of u!..r'..u~t: i.-:~pot<taoce and r~1e,1ance to the prot~~tiod of
fish ~nd ~ildlif~ r~s~urcea, ~ liat th~ follovio~ and includ~ a
brief su~ry of ~esures r~quil~~:
(1) 'l'1l~ !:;l!:lil sud \-lildl1fe C<.:>ordi.Dat1on Act, draft Uc.!.fom
Pro£:'.e:dur€'e for C~)!.!lflli-~m('4?., Hay 18, 1979, st.~ndardif.:+:<et
p-ruc~uren ~nd int~ra~emcy rel~t!.o~hi?iJ V.> .tn~•.J.~et "that
w1.1dl! f~ ('•Jn8~f"\'fttion j_lj f1J]1y ('!.i".;n~i~~rnd .:;nd wt'!i eh¢d
eque11y •J::tth other prc:j.::-ct fe.atur~s in ag~ncy d~·::isicn
!.nlikin.g ~roc?ea~e by int ~g. ra ti nF. ~u ::'!h C.Qnsid~:tratir.:n'3 i:nto
Fl LE l:f..t: tt
--= .. --.,----·-----------------··--·-·-............ ····-· .... ·-·· .......... ·-..... -·.
~-· ..... -;:-
.-~.
~~ i:~ !~
~ ~~-ts= <--
i~.=._
; ~.·-
!"~}~
~t~
~:~-~
~ -~-:
J--:~~
~ ·-'"~ ;:.;.:.
~ ;~::
: ~~:·.
~i~~
=··---·--~ :--:-;:";
P .. ~~~
·1 . -"'-
c
n+4 ~r1C.F. LOULQ t'-R~E' ~
proj~ct planning, National Environmental Policy Act (NEPA)
complianc~ proc~duree} finsncial and @conom1c ~na!yses.
author~z~tlou doeu~ut~. aud project ~pl~me~t~tion."
{2) The t.t:>\Jnc::d.1 o~ ~m:rtro~Trtn1 Qt1nli.t.y' :.o (C~"}) P.cgul3tion~
i.or lmJ:'le:cetltiog the l'roce<iural Prov"i.e.it•na <>f th~ Hational
~ro~~ntil"l Pt:1J iq ~t. (40 CJ!P.., Part:; 1500-lSUB., .July
)0, 1979) ~pecifie~ p:uvi~io~ re~uiri~g ~he ~uteg~atlon
of the lfEPA p.roce.sa into ~rly pl<JTJ1'1illS,. the int.f;:gr:at'inn
of NEPA requirements with other ~nviTQ~nt~l r~vi~ ~nd
consultation rtsquir~snt~, ami th~: n.sc of tbe ~.-:opina
llrQCGJ;~.
(3) Section 404 uf the cle~ Water Act of 1977 and resulting
final rules for i~l~ntiltinn of the ~egula~or)• permit
prcgr~ of ~he Corp~ of Engiu~r~ (33 CFR. P~rta 32Q-329~
Jnly 19t i977) requ~re~ that a Department of ths Army
p~rmit(s) be QDt~i~ed fg~ ccr~,in ~trccture~ or wu~k in ur
aff~~tin& w~tr.rs of th~ Unit~d StaLe~. The ~ppl~catiuo(s)
for such u pe~it(») ~ill be ~uJect t~ revi~w by wildlife
~gencieSa
{4) ~ecut1.ve Ord~I 11990 (~tlend~) -...~~ i_::;,yt)ed ''in order t:u
avoid to the c:,;tQnt pn::z;ible th~ long-te!."m and s-h{lrt-terlli
ad"Ve~,;e izlpact.!f a.ssoc:lat=ti with the destr.Jction or modi.-
f~c~tion o£ wetiaode a~d to avoid direct or ind~rc:ct
support of n~ construction in wetl~nd~ ~~&rever th~r~ is
~ pr~~ti~~ble ~lt~rn~t!vet" acd Exeeutiv~ Or~~r 11985
(Flooilpla.t:~.s) ~a::s 1asued ''tQ av«:lid tn t.ha c:xt.ent po~~ible
the lo~-term ~nd ~hort-term adverse ~paete associated
with the Qct:np.ancy and oodifl.cation of floodplitins itTld to
avoid direct ._nd indirect !6u}.)port of floodplain de-ve.Iop-
l'~~nt vne~e-... rcr th~re its a practicable slt.;:..rn~tiv~ .. u All
.. feQ.er.U a.genc:ies are responsi'hlEt t9 ~o-mply vith thesoe ro• !;
in the plariu.log aad .u~cieion•!!>alcing p-:;-Q~::u.;s;.
(5) §hi!r,tion 7(c) or the .E.-ld~.cgered SpE-e.i~s Act., 87 ilt11t. 884,
as,; ;:r.;cn.ded., requirei:S FEXC to ask th~ SP.-c-r~t~ry qf the:
lllter.ior. ac-till& tnrnugh th~: u .. s .. .Fish .-:2nd \iilc111.fe Se.rvic~,
vhether ~:-.· liz:st.et.l or propos!?d er.danJ'l~r~..d or tht.c:1tcn~d
upecies ~y be present in th~ ~r~~ of the Su~itua Hydro-
electric. P~r Project. !! the Pieth .and \,lfld1.ifc S~rvice
;u;:i·o?it;C!!C that nuch species !:lay b~ Pt'C~~tlt in thf! area o!
the project, Fi::E.C 1a .r~qu:b:ed b=; S~c;t-i.o1l i (c:) to conduct a
.Biologic<~l As!:H•.a~~nt t-o identlly any liate-.i or proposoo
enden~et't.td or thrcntcncd sp~c.1ee which areo. li"k~ly to be
affect~~ by tn~ ~on~tn1ction prcjeet. TI1~ asse3srr~nt j~
to lm ccm~plcted 'With1o 180 days, unll':las a time ~~xtcn~iou
i!s T.:J.ltually agreed Uj)L"~n. -
·---.... ------------·---------_..,__. ___ ,_~--.... ·---··~-.... _ ....... .
·.·:·-·
~~:
IIIIJifJ':~:
~ ~~~!
.·~.:.ti ... ·~.;;~:
·r"
I
~
j
~
I -
I...
I...
I ....
~
....
-
-
-
-
-
-
-
.-\.
----
Mr. Brie P. Yould ~J.'IP.~ 3
R"Cl c,:m:~t~~ct for physic~l Ct)li,.;tru~ tion tlBY b~ entet''-=0 i.nt.o
and no phy:iical. cooatru~t·h:>n my bcgi.Il unt11 the fiit:llngic~l
Aas~ss.me.nt i.I:' t;~leted. lo tn~ ~vr.nt th~ coue1~1ons
d~a~ from thr. Biologlca1 .~se~~~n~ ~re that l~~t~J
endangert:d or thr~ateoed sr-~cin~; arf.! l.!.k~ly to 0.~ aff~ctcd
'by thee cuuetl:uction projc:c.t 1 FEE.C is rerg.Jired hy Section
7(a) to initi~tc the t!u~aultation pro~c.~~.
(n) W~te~ Reaourcas r~~ncilt Pr1~tipl~ ~nd St~ndarrlx !u~
r1s.i'n1n~ Wat~r and lielated l..and K'it:;Ol.Jr::e,; (18 CJ?.R. Part
704, Apr:n l,. 1978) -we.r~ eetah!ishcd for pli!11ll.l.c.g the V-9c:l
etf the w~ter and r~lat.l;!d. J.;:nd ~esources :;,f the United
St~tes to ach.iev~ objaetivc"~ deten:!ined coop;;r,"ltively,
through th~ c~ordin.~~ed ~etiou~ of the red~r~l,. St~tct and
local sov~rnr~nt~; private euterpri~a ~d o~g~zations.
and individ~a~~4 Th~se priocip)a~ in~lude providing th~
basi~ for pl~nirg of federal ~nd feder~lly a~s~ated·vat~r
and lao..! r~eo~rrc@~ progr.ms a11d pro.)~c.ts and f::dar~l
licensing ~~tiviti~ as listed in the Stand~rds.
Lt iB our understandi~g tb~t you~ ~g~ucy has contr~ctad with three
independent ~onstll t~nt fi~ £or ~&ch to ~:IOIV.ttlop .:~ ao1:1preh~~ive
plan of StlldY (POS) to io.t:1ud-e biological ~tndieJ; a:ti!iuciated ~1th
tnt.: Su~itna project and that from th~ three :tnd~pe.ildent POSts ;.Jnd
th~ exietiog Co~8 of F.ngineer~· Plan of S~udyy ~n ultimat~ compre-
11en!51ve f'OS >7111 bs OP.'li.'\T~Q. The i1Ct1ona ilo?C€SSS!'Y t" cv.nply with
th~ .sl;>ov~d list~d lawa~ policiea, and F.O'~ dcmon.st~ate the neceasity
for clo~~ con~u1tat1oo ~th f6G~r~1 ~d st~te wii&ii£~ a~~ncie~
thr-oughout. project planning, a-nd ~pler..t:nlat.iotl.
lt i,; i.:mpef~tive thst coonH n.;~t~d plan:-;ing b;:: 1u1 tlet~:i nC".-"--:f. th .-:11
appruprlate partii?B, ~nd that ~mch pl~Wli~f; includ~ thn convcni:ng nf
~~0?1Dg mBetin?.~ tn include pd~tlcipstion by st~t~ and f~d~r~l
wildlif~; :~g<!ncie:l. 'Ih~ purpose of th~ s-cnping r.sE:~tl.ug.s should
includ~: Q<;"aloping a c:::..~p.rehensi\l£1 POS ~h1 c::.h i:1,;•..:res full w11dlifP.
;ogency parti(:ipation thnmghout ~ad1 ph~tH! of the. pl~nnina and
re,dt:Y proceaaee; de-t€\mi.n'lng ~ .. hu~ at:~~ tho?. f~-•::l9rc1 <tnn !.;ti'tt~
vJ.ldlife ~geocl.es or the :app1 iclint:'! \.till underta'k~ r.nd fl'\"t!r.~cc the
required stt1dtc~ i1r..d iuveatlgstions; i.nF,l!ing ~.cl~qu.:lte ~•ld timely
funding of thos~ p~rfor'C.to; th(?! ~tuitic:~; and !!~tabll.ehing f!!i.ltll~lJy
;)Cr.Qpt.able tal:}:.et dates for th~ initi:Hluil t!Dd C-O'!l!'Jl~tic::n. of ~t.udit:f:J..
ThE< adh.::rcnce to th~a~ ~u~esti•)nt!~ -.:i11 im;ure that <S:.le·~uat~ infor-
.. ~ti-c~ !:~ colle-ct~.d to (<n~b1e the dt:teri:rlnation of project ii'llpactu
,;1nd develop ~~l!:l'.IT'ttJ;; t.o pre,•ent~ m.iti~et~?., .snd .-::cmpcns~ te for fi.sh
aud ~ildlifo lo~~en~
; .......... -~~ ~~a·......-:.~--·-,.~·--~~~ .. :lt-·--······
I-!.;a ·--r~ (..t~A .C-e. :....;.&;;
i~4 i~ ~~ l-~ (~ r= ~~ t2 li ~~ ~~ ~ ·~ 2~ s~ ~ fii ~ .~ f--= II ~ m~!
~ . ~ ~ Mf! ·~ r= ~~ ~ ~ tm~ ~~ •!>':-·~~ ~~
~~ •,.,;"' -~=-~ f.P..::> ~~ .. : t~~ !l~
{.~ ~ ~~~ ~., ~ .,._,_
1"""-~ ,,.....
~ ;
.~-..;.;:: i~
ii j"tn~
II
~~~ F~
ti
ll.~ ~~~ , .. -~
ftj
!~
? ~~~.:~
t.~ ! ;::"'>.:
-'."'-· j
(
•
:~r:}!~:·~;:~~-,. :~·· :.~
., t: I•·A···. ;; ' •. -1.
Hr. Eric P. Yould i'e.~e 4
'K~ lonk f:,TV~rd tn wor'kina clos'!'-1: w-1. th yoJJr a~~ncy and oth~rs
tnvolv~ in th'i~ ~tlJdY~ .tZnd trust that this lsttEtr l¥111 serv~ as;
nutic£: of the tiec~~~lt).' i!C>r early in\'Ulv~t:mt o£ ~nd can~l)lt;lti.lJn
~~th ~ildlife ag~ncies.
cc: AOES 9 W~
irF.RC,. lJa;;hinaton
ES, ~sbi.ngt-tln
OEC 1 Waifb.i.ljgt.on
Cf:+ ADF&G. Andlol"age
Si, .. !"lCar~ly -?our"' ··; . . ""' i' -4 I ~ /•t i /} ...... / -r: 1 .... -/ I « / --.,. -I I / flv U' -'"'!'--#/-·-..,t' I'll:!-?'? ..., 3 -l -·. A .. .L..-Yn .... 1 ('"A... , ( 1·-(,.l{~'}r ) a_.-~:·0 ,:roamtt! ....,. ... ; l.'r'lc.ciioT .. .--t""-~· -. ~ ·--~-·· ~·· ----v .
NMFS1-BL.'i. A.Di~R, Axlc:hores.e
ADEC, EPA. SCS, USGS, ~,cnor~R~
i~ p .. -,
tf! ~~· . --: -~·
{~' t~ ~~ ~~t! i~ -1 ~ ~:
-~· -~~.
1"'-=-'' ~~: ~: j~:
)li-~: .... ~ ~~!
'' I ~~ ~; '• -i· ::~:~.~: · ~ · :if .. :~~. r~ i~ m.fhi~~ ;.}::t ;i .. :!~:;};.Jr· -:~~In~::~ ~;~:-g! ;~~ r~ :~r;:· · u c; ~{!~ :~:, '"1~! ... .~i.:~! : i;. ···~=~·-(·: i ·r, r~· t· . .. ±. 1.,
t"(•··'";~:.~ : !:··r~f-;· ~-i· .: ·~ r-~-..
....
..
...
....
,
IIIIi
-
...
IIIIi
...
-
-
-
-c
-
-
-
-
-
-
-
Ill L:~ ~-· . -' .... , . ( ;
l· _,,n~-r~ ~-;'~n ~·:. f'...__ '---\•.
r:'1i1 -~ I
l ;: 11:1~ l-I October 16, 1979
:P5477_lfi
Federal Energy Regulatory Conmission
Bureau of Power ·
Division of Licensed Projects
825 North· Capitol Street, NE
Washington, DC 20426
Attention: Mr. Ronald A. Corso
Dear Ron,
Deputy Chief, Division of
Licensed Projects
Susitna Hydroelectric Project
I appreciated your call October 10 regarding the September 24 letter
from Gary Hickman, Department of the Interior Fish and Wildlife Service,
to Eric Yould of Alaska Power Authority. Although the State will not
make its decision on the Corps· or Acres until November, we have already
had some useful "scoping 11 discussions with ADF&G, NMFS, FWS and ADNR.
At Eric's request, I am forwarding herewith for your comment, a draft of
a proposed response. Please call if you have any suggested changes.
JDL:pbf
Enclosure
ACRES AMERICAN INCORPORATED
c ·'"·' .,
'· • ·:•t
:; .• 1--~. -~ • -~ :;
.:, ..
Sincerely,
·} /:.,~·:.
I' p .
Sohn D. Lawrence
Project Manager
J --
(
'-
Mr. Gary Hickman
Area Director
United States Department of
the Interior
Fish and Wildlife Service
1011 E. Tudor Road
Anchorage, AK 99503
Dear Mr. Hickman: Susi·tna Hydr.oel ectri c Project
Thank you for your letter dated September 24 concerning federal fish and
wildlife responsibilities for FERC licensing of the Susitna Project. We
wholeheartedly concur that all activities related to licensing of the
project require careful planning and coordination with all local, state
and federal agencies involved. We also agree that the environmental base-
line studies, and the ensuing assessments and development of appropriate
investigation, compensation and enhancement measures are of particular
concern. We fully intend to address these matters in as comprehensive and
thorough a manner as possible either through the Corps of Engineers or our
consultants, Acres American Inc. Selection of the Corps or Acres is
anticipated in November.
Some preliminary seeping meetings have already been initiated on our behalf
by Acres American Inc and Terrestrial Environmental Specialists Inc with
the Alaska Departments of Fish and Game and Natural Resources, the U.S. Fish
and Wildlife Service and National Marine Fisheries Service. We have also
been in touch with Ron Corso of the FERC to solicit his views on the approach
we should take in obtaining the necessary licenses for the project. It is
our understanding that a key factor in the license application will be a
valid demonstration to the FERC that all involved agencies have been consulted
and that plans for compliance with the appropriate regulations have been
agreed. We have every intention of meeting this requirement to the complete
satisfaction of FERC. Referring to the list of ·regulations in your letter
we have been advised by Mr. Corso as follows:
{1) Fish and Wildlife Coordination Act: FERC's own regulations will
govern for federal licensing of the Susitna Project.
{2) CEQ Regulations: FERC's own regulations will govern for federal
licensing.
(3) Section 404 of the Clean Water Act: compliance is necessary.
(4) Executive Order 11990 (Wetlands), and Executive Order 11988
{Floodplains): FERC's own regulations are expected to govern
in the case of Susitna.
(5) Endangered Species Act: compliance is necessary.
-
...
...
...
...
-
...
....
-
....
....
...
-
--
-
-
-
-
-
-
.....
c
-
-
-
-
._.
-
-
,.
- 2
(~) Water Resources Council, Principles and Standards: these only apply
for federal projects, and would not apply if the state selects a
private consultant to undertake the Susitna Feasibility Study.
You should also be aware that we are planning to directly involve the
ADF&G, ADNR, and possibly other state and federal agencies in appropriate
areas of study. We will gladly keep you informed of progress in all
aspects of the study which are subject to your jurisdiction and look for-
ward to a close and mutually productive relationship.
Sincerely yours,
Eric P. Yould
Executive Director
--··\ ~-:---~:; ~-. c;--~ ,_.~-.:
~ Jl 1 k .... '
I l ~
. ..... ~ I . ~ " ...._, "-• I.___..J
1'\ ;--;:::~
\\ 'i ! ;.;
~/ J
r-. r· ,_, ,.-......
I\ il ; I {\(•''.:. I: . · o~ , : ,., , , , I,,\ \,'
i U \ ( ' 1 L; \ "\ \
iJ'J t.S ~ ;' -,~ '\::::)
(i ,r: ,
i i ( I·' I .. : r',' ! :.. \ U I, ....... I \.J _ .. ~~
. 1 I
""rtEf\ltCQ ~ r-"' , ~ ~-·1 , ~CJ .~ t: ' : :') ~ ._ ..... ·--
; ·JAYS. HAMMOND~ GOVERNOR
i
I
! -D;gp;u~~HE~'T OF ~..:'!i';t"':li~ RESOURCES
DIVISION OF PARKS
! 619 Warehouse Dr., Suite 210
Anchorage, Alaska 99501
,..~
J -.~
;'!S-
-~'t
~>
~ i · .. t i
January 28, 1980
Re: 1121-19
Jim Pedersen CD.J: /h&N
3201 C Street, Suite 201
Anchor~ge; Alaska 99503
Jear Mr. Pcder3~~:
~~@@~[ID
RfLD JAN 3 1 1980
....
..
...
-
...
.....
-T'~.i-; 1.·:•':':-.'!r is to t .... tm.·.:.::";t>. .;h2. a-~ ":ment reached between yourself and
.y .. ::. •7 ~ '-"''3 . r:Ln7, ·:::cr,':t;·,":.t ~ . .::..~ ':: .~ base camp and airstrip near the
··.:l; ~·..t s.-,h.:-: · c~ on ~:,~~ c,, · . ~;-~ Rii.·~r. The base camp location described
cis in the.<:';: ~1f u.::0 :n~!,; ··f .::;e ~of Section 27, T32N, llSE, Seward ·< .;
...
meridian appears to :;e -..:.~;<;~i.!" of any archaeological or historic sites. _ o-_
We confirmed with Glenn Bacon, who is knowledgeable in the area, that ~ __ . '}.; }r_ •
the probability of encountering such sites is low. The proposed ai:t;:~ _ ~
strip is a different matter. It is further from the area Bacon . ;:,c.yUt.r':CC: :. : 1
examined and in a more likely terrain. For that reason we would : ;/:...::::-/ ·. -_// _
recommend an archacoloeicql survey to ~nsure avoiding impacts on s~~hl ~ I .,
Dti;st
.... T.;: I ... ' sites o 'a:. a:-I ::! • :-0 I ;.. ' ::::_
'-~I Cl) I -~~·~1 0 ~ I -.. --~· .... · ...... ,.. ... ·~-
: i vfjJ, :--. i J "
r-1--... _j_ / ·
c ~ ., '-· ·-i' ~ --t./7r,· .!:' (./ 1 • J ") ~ !~i J
·-r-;?S.'.~
-:-1--Y"~. ! 1 JPS(:/ ,..,;
r--:-~1 ..._J I I . ~u·~#'
·-.-1-.;;.. i :#'• L ,
: I 1 ENS · _,_, I
; I iSr/T-_.
-. -!-!---!-: j:J'.VL• . . ' .·-::-·-· --~-
SJn-: !rely,
/?
I // "!// , y !r . " . ,. / ~ . --.·--
di / // //~~. '"' /·!·," 1, :'-' '··.·A •. ··;....---·-. 1"~~--,.; ~ ...... ;./, vor .v., .,
i>;i 1 1 r,1 ,,1 S. ·Han;:-,l:Jl ':!
3c 't.:, HJ. 31· ·Jri c 2 ¥ •• • ~:~ ;-; i~ .rat i •. -.l1 :_;;: fi.r-er
..
.. ==·c ....
-
/ -
-
Mr. Paul Carrier
Division of Licensed Projects
.WARNOCK ~~
~;.: .·-r, -.:~-.-;~ ~;: o:. ... _ \ ,t...,.. i!.. • • \. ...
~· -~.: -_.
Februar,y 15, 1980
P5700.~1-
il,.~·~
7 ::BELIUS c!?
f1ce of Electric Power Regulation
t:!eral·.Energy Regulatory Coomission
5 North Capital Street · -
sh1ngton, DC 20426 )BSON '·a f PHILCOX
,__ -9IPPEY rt...
JCKER
mJRRAY ~s
_PECORA ff _ \HADUR 1o t...
~I •,Jne,:" ,__...,. I' If tf r 12
f--1 r t
('0
f-cot
!-
1--
I-
1-.. ·'
t: I:. II
ar Mr. Carrier: Susitna ijYdroelectric Project Study
discussed in our meeting on February 11, 1980, enclosed is a copy
the Plan of Study for the Susitna Hydroelectric Project. It would
appreciated if you could pass this copy along to Hr. Springer and
• Corso for their infonnation. Any cotm1ents you would have with
gard to future licensing considerations w111 be appreciated.
ank you for taking time to meet with me. I look forward to
ordfnating developr.~nt of the license application with you as the
udy progresses.
Very truly yours,
tPI)~
-l
I
Hils Philip M. Hoover
Staff Engineer
J • ~
. /~llt; ..
cl. .·
~·CQUENCE Nu l :;;J/? l -cc:~awrence ~ , . i . I . '·
-.--;:EI Q) I I -I -_, -"" '1: a: ' ~ .
=? ~ li='
·-
-
.._
• -1/l -
;.' ~ 1 a 1 ~
• I ' ·--:·-! nrw ~
__ ,_, ~.......-:<, __
: ; J ... ~ r~r·
• -J-·_-__ , __ ..,
. ' , C.A J , I -·---. ·-·~---Iff' ___..: -~~ . -·:-.l:...s -_· -_ . .'. ,
-,-4---~t
-~-16--: , ~PST
--~~~----l _JI. I
· ENS : --1---l-L-l-1 SNT I
l i 0 vV L ,___l-1-----1
' M F< ··j .
r-' ---~ --: __ ,
'-! RC 1
r---
1
!---
----i
I ' I
J tt >-~·
-i
l
--I
I
WARNOCK
~. Ron Corso
Acting Director, Division of Licensed Projects
Office of Electric Power Regulation
825 Marth Capital Street
Washington, D.C. 20426
""-"&"'·-:'-.,.,_,<': •..
-
March 11, 1980
PSiCC. // . .g-~ ...
...
..
DEBELIUS DE ar Mr. Corso : Susitna Hydroelectric Project 1 HOBSON
PHILCOX Tt e· purpose of this letter is to confi~ the meetins scheduled for 9:00
SHIPPEY
TUCKER
MURRAY
PECORA
BAHADUR -~./
-~
a.
cc
mf
'J(
n
St
01 .. ..
II
tf
"' ._.,
j;_,
.....
....
-~-
m. Tuesday. April 8, 1980 at the above FERC office address to discuss the
tential 1ic(;nse ap~1ication fer the Sus1tna Hydroelectric prcject; This
eting 1s arranged as a result of discussions between ~. Paul Carrier of
ur staff and t·1r. Phi 11 p Hoover of Acres.
e Sus1tna ~roject team will be represented at the meeting by the study
onsor: the Alaska PnwPr Ar~hor1ty and by Acres American Incorporated, the
ime contractor for the study. In addition to you and Mr. Carrier, it
uld be appreciated if FERC representatives fran the environmental and
gal specialities could attend, as well as any others who have c~ents on
e subject Plan of Study.
r pri;:ary ~:opi c of i;lter~st at the m~cti ng will co FERC s·~aff reac'ti on to
e Susit:t.a FOS. Any cor.1r.;.;:~1t!: resulti!li:J fran your revie\1~ reldtive tu vur
eparation for a lict:rtsc ap~11cation Si.ll:x:littal, r.i1l be appreciated. In
dition, we HOt.:ld also like to discuss the followinq topics:
The p1.ans to subr.:it a 11ct:nse dppi ication prior to ~o:nph:tion of certain
key iilonitcrin<J st~dies;
The extent of study participation by the Alaska Depart!'1ent of Fish and
Game and any implications on their potential (future) role Js Jn
1 ntervenot· ~
-The i:~pact on nun-F~~er·al Jeve1:Jjl:l~:lt of the Corp::; of ::i1gine~rs'
Congressional authorization fo:--Phas~ I Study of ~In:: Su~~-~ila oro.J..!Ct.
The ii.1pJcts of tl1e pendit•'J llt!W r·egul at ions :--eqar·uiuy app1 ications for
majm· i)roj ect!;.
-The positive .anJ ;legaUve aspects of 1icensing tht: iutlivitlual J:;-oject
coo.pon::.:nts separately or collectively (e.!J. sequential license applica-
tions for each of t\·10 dar.rs vs. a single project application).
Ycur cooperation in providing assistance in this early stage of project
dcvelOJ:Jllent is appreciated. ~Jt: look fon'lard to meeting with you and your
staff on Apri1 e.
Pf':!!/1 s
cc: Paul Carri~r. F~RC
Cric Yould, APA
Very truly yours.
John o. Latrrence, P. E.
Project :-~imager
...
J
" J
J
...
J
' J
l
j ..
~
-
-
..,;
...
Blind copies to: J. Hayden, P. Tucker, C. Debelius, E. L. Baum, Project Files ..
-
-
-
(
.....
-
-
-
-
I J L
I
I I l r • .. ~_.__._ ~
Mr. Dale Arhart
Division of Ecological Services
Fish and Wildlife Service
18th and C Streets, NW
Washington, D.C. 20240
Dear Mr. Arhart:
March 31, 1980
P5700. 11.71
Susitna Hydroelectric Power Study
Meeting with FERC
As discussed in our telephone conversation, the subject meeting with
FERC will be held at their Washington office on April 8, Room 3401,
941 North Capital Street. Attached is a letter sent to Mr. Ron Corso
of FERC confirming the meeting.
Thank you for your interest. We hope to see you at the meeting.
...
PMH/ls
Enclosure
/
ACRES AMERICAN INCORPORATED
Sincerely, :
6.-. I' I II, I (/! .'/ / I
1/ f/,£-"-{ '.~i'-,{'?-.A/1 t-· I I
Philip M. Hoover
Civil Engineer
•· •-: .'rj
AWJCA pOWBL
AtmiORIT'f
SUSITNA
Fll 0:: "'5700
/1.1 I
---
' NO. '
I 1-3-_2S
z ~ 0 ~I e i=
<(
c. ~
1--
'
JGW
-:,. ---0-C'N,.-:-0_
!!"\ .......... -..:. ..... ~: / =--···--CAf1 I
/ JDG I
-/ ""T•·r ~\.0Jr\
p·~--l p· .. ,
J-o-' <f ~" ~ 1: ~
R :i '-1 < 1.' ( -::n -;
I
I --..-.~-------.... -~.A
..
..._ C~ns_!~-~7 E . .,;:·neers -..._ ~u.rt::f. ALE -
S1.:te 323 Tr!! Clarl( 5'-'ilding
c:•~,-.:: 1. r.·-,··,ta"d 21c~~
-:--• .::,. :...· ~:: ::~~-s-:·2 ~:_: \·.r::s'"' n~tcn Ltr-e 301-~9-5-5595
r" · r,.... ,,,. [h/' -•,,. p,!~~bur~*'1 PA r.:a·e.ah NC \·:~-;hrnntnn nr.
L-
c
L, .... ·. ~-J
~ r· 1., ... ~: '· Pi : •• , t..C
h~H ltl
Mr. Ron Corso
Acting Director, Division of Licensed
Office of Electric Power Regulation
825 North Capital Street
Washington, D.C. 20426
Dear Mr. Corso:
March 11, 1980
Projects
Susitna Hydroelectric Project
The purpose of this letter is to confirm the meeting scheduled for 9:00
a.m. Tuesday, April 8, 1980 at the above FERC office address to discuss the
potential license application· for the Susitna Hydroelectric project. This
meeting is arranged as a result of discussions between r·1r. Paul Carrier of
your staff and Mr. Philip Hoover of Acres.
The Susitna project team will be represented at the meeting by the study
sponsor, the Alaska Power Authority and by Acres American Incorporated, the
prime contractor for the study. In addition to you and Mr. Carrier, it
would be appreciated if FERC representatives from the environmental and
legal specialities could attend, as well as any others who have comments on
the subject Plan of Study.
Our primary topic of interest at the meeting will be FERC staff reaction to
the Susitna POS. Any comments resulting from your review, relative to our
preparation for a license application submittal, will be appreciated. In
addition, we would also like to discuss the following topics:
-The plans to submit a license application prior to completion of certain
key monitoring studie~;
-The extent of study participation by the Alaska Department of Fish and
Game and any implications on their potential (future) role as an
intervenor, ~
-The impact on non-Federal development of the Corps of Engineers'
Congressional authorization for Phase I Study of the Susitna project.
-The impacts of the pending new regulations regarding applications for
major projects;
-The positive and negative aspects of licensing the individual project
components separately or co11 ectively (e.g. sequential 1 icense appl ica-
tions for each of two dams vs. a single project application).
Your cooperation in providing assistance in this early stage of project
development is appreciated. We look forward to meeting with you and your
staff on April 8.
PHH/1 s
cc: Paul Carrier, FERC
Eric Youl d, M'A
ACRES AMERICAN INCORPORATED
Consullong Engoneers
Suote 329. Th~ Clark Buildong
Columboa. P.~;Jrylana 210.:.:
Telephone ~01·992-S300 Washongton Lone 301·596·5595
Otner 0 11 ·CC'S eu~f.1tO NY PlfTco .... ,,,,,., PA Q~r,.,,..,.., PI.Jr" ,., ..... ~ ........ --1"'\,...
Very truly yours,
John D. Lawrence, P.E.
Project Manager
-
-
lllil
....
..
-..
....
....
--
....
....
--
-
....
-
-
·-~ .
t" -·
-
-
-
-
Mr • .Jim Gill
Acree Aa!r.f.crm, I:ac.
2201 SpeDard Bead
Arv:bon1ge, Alaska 99503
Dear Jim:
AJ.ASKA PaD. AUIHORI'IY
R ~CI:'IIfr--: ~ ":'"·) 1 9 ~oao C I...:. I ~ ~-_ v :_ 1 I , !..;
Septe•i er 12~ 1980
-I a attachmg a letter fmm AmR. requesthlg tbey be kept advised
of tillY data gatlced relad:ve to nav1gat1.cn use of the SusitDa River
and its tdbnt:ades. r.m }'Q1 please alert yocr subcaatractots to this
raqueat! We wen] d l:ike to acu•w »date it to tbe rraxtnun extent pcsai-
ble.
Putther, AJDl bas requesbed a copy of the t1AF prcposal. for a study
-rega:r:d1ng DaVigad..cn uses. I uMelstaad it was sd:Jnitted dimctly to
YQ1. Can ya.1 please pmv1de a CDPY to Atm. either dimctly cr through
us. '1'baDk )Q1.
-
-
-
-
-
FOR '.mE f2ID rrlVE DIRECI'OR
l ~: Aim. Letter. Augaat 29. 1980
cc: ~ Iam!ace
Sizxmely.
Rebert A. 1tim.
I · ,-~ ~ •' . C:;Q-;'/rR -\._·-~· ·,-' • c.
'( l S ~' .:. 'T '·~ ~ i-----_,
1 F· -' ~-",:no I '--~·" I '---I :3:::c ~ _;_-... .:.. .,)_
i-------------
1 -,
r z ..., -:; 1 . ..-.. -~ ~ .:"(
!~ ~ i
! < -_? I ' -::: I ?----. ---
1-r.'\.-'"'~~ &~~?~·-:_--:--_____ I· xc.: . I
----__ J
~ . . ~
-. ·-I !(?;)~fz,~
l ; _:::. l
1=@~~ ---1
i
i-· ! ---
j-___ L·
[-i '.1 -~ ----
~---
;--~ ------i
:-i :---• I
) l~i"'lli"·-j --, I
(
~ . I ~ ..... . ·~ ...
J:ti~m
Mr. Ronald Corso
Director
RECElVED APR 1 4 i980
Division of Licensed Projects
Office of Electric Power Regulation
825 North Capital Street
Washington, D.C. 20426
Apri 1 9, 1980
Dear Ron: Susitna Hydroelectric Power Study
Enclosed is an additional copy of the Susitna Hydroelectric Project Plan of
Study as requested. Speaking for the study team, the cooperation of the
FERC Staff in reviewing the POS and discussing pertinent pre-application
issues in our meeting of April 8, 1980, is greatly appreciated.
PMH:kh
bee: E. L. Baum
Very truly yours,
~
Philip M.
Licensing
AL.-1.:: '~A POV!::R
r.·_·T~·)RITY
c:,·-~--... I ~ <.1:;, I 1\: ,..., -,
FILE P570Q:tr
Hoover 1 -· ,~ .{ _
Coord in atr!;E~. U L:N~E. f'!G. i ·-,. --/I . ')· s i -, I
L :~~, ~ l ~I 1
0 -_' c: ' ,_,_
:-.0 ,_ =
-I 1 'fJ ' (.) ::, -
<{~~~ 0
-
...
.....
-
-
-
-
...
-..
IIIIi
-
-,-,-.---·-. I J c " -' 1=~15~:.-.·~· .. ~----).~-. ./•;
1 1
C. '----r:;t /.:;._. I /
_r. \ , ~;~_ri~·
ACRES AMERICAN INCORPORATED
Consultong Engoneers
Suote 329. The Clark Suildong
co:umboa. r.~ar>·land 210~4
Telepnone 301-992-5300 \'/asn.ng:on Lone 301-595-5595
Ott'ler ()~·~,.,~ Rt~":l''"' "'v o ............. -• "" ,..,_,_ ... -.. .
_', __ '_ JPS ·----~ '
,L~ lit -,:-, ____ 11 i , -'I , 1_1_:=:1_ s ! . --~ :-:: ·;~~= =-~ _I ,L.·.,L· I ~-: ·. ~-_--i __ j I ~ ;·n ~: v : · ~-:-~--;::·[ -~ ---1
~-i --'·--i
-~-----~--'
--..
---------· --...
-'--____ : ---l
. . I I
---;=-~-~ ------1
+--' ---
/,./
_,
-
-
-
-c
-
-
-
-
-
1·K2LH
. . -v-
~~&~[ @~ &~&~~~
DEP,\HT.:t!ENT OF FISU AND Gi\ ll1E
May 28, 1980
Rf.G'D MAY 3 0 19a)
Mr. James H. Pedersen
Project· Manager
CIRI/H&N
3201 "C" Street, Suite 201
Anchorage, Alaska 99503
Dear Mr. Pedersen:
f1~ l 0 U f~HSU
ALASKA POWER 1
AUTHORITY
.L4Y S. HAMMof!o. G~J~iJtlA
FILE~
SEOCENCE NO .
FG-80-II-12
.df/:2 ~"3 {)
<=i
I
7Zfi D£0-lc.:
f 1
I iWCC
!TES
'R&M
AOF&G
f-A.~ 1/ ._ __
The Alaska Department of Fish and Game has reviewed the Governmental
Permit/Plan Review Documentation for the Susitna Hydroelectric Feasibii~ lFIL~
Study Program to address activities of a general concern to this agencY.~·---
and those which also require approval from this Department in accordance --
with Alaska Statute 16.05.870. Our comments on study activities follow:
GENERAL COMMENTS
Hunting Activities
The Game Division in Region II has expressed a concern about the potential
for impact on the wildlife assessment studies by hunting activities in
the Watana camp area. The Game Division has stated, "It is evident that
a large impact on game and furbearers may be expected in the Susitna
drainage study area if persons involved in feasibility studies or in
support of such studies are allowed to hunt and trap without restriction. ·
Such recreation hunting in inself would not necessarily be harmful
except insofar as it impacts the wildlife studies being conducted by the
Department and the University. Hunting and trapping activities by the
large number of people based at Watana camp will result in changes in
animal distributions and abundance and would therefore severly bias the
results of the wildlife assessment studies. In addition, it is likely
that hunters and trappers would take some animals which have been
marked or radio-collared at great expense, further impacting the coherence
of the studies, especially in the vicinit~ of the camp~ We suggest that
· the APA 1mpose a camp restr1ct1on on hunt1ng and trapp1ng by personnel
using any of the feasibility study facilities within 15 miles on either
side of the Susitna from Gold Creek to the Tyone River."
c
J~ Pedersen -2-5/28/80
Employees of Acres-American or their subcontractors should also be
informed of the regulations contained in SAAC 81.120 General Provisions.
The following methods and means of taking game are prohibited: (3)
by the use of helicopter or rotocraft in any manner including the
transportation either to or from the field of any game or parts of
arne, hunters, or huntin ear, or an e ui ment used in the ursuit
of game; ... and also subsection 5 by use of an airplance,
snoMnachine, motor-driven boat or other mothorized vehicles for the
purpose of driving, herding, or molesting game; and that the definition
of "taking" includes harrassment by aircraft.
Aircraft Traffic
APA/Acres should assure that aircraft engaged in point to point
travel maintain a minimum elevation of 1,000 feet above ground level,
weather conditions permitting. Ed Reed of TES has offered to have the
TES employee stationed at Watana Camp complete a log of all· helicopter
activities at a lower elevations than this so that foci of disturbance
can be related to animal activitiesL All contractors and subcontractors
should be required to participate in maintaining this log. Beyond
question, the level of helicopter activity which will occur in connection
w,ith the feasibility studies will impr;1ct game populations, especially
·carnivores; the objective of these restrictions is to both minimize the
impact and document it so that it can be evaluated.
Solid Waste ~1anagement
We suggest that all garbage generated by the field camps should be
incinerated and buried within a strongly fenced enclosure to minimize
tts attractiveness to Wildlife, especially bears.
REVIEW OF STUDY ACTIVITIES
Aerial and Land Surveying p~4-p.8
No comments, recommendations or AS 16.05.870 requirements.
Hydrological Studies p.9-p.l2
No comments, recommendations or Title 16 permit requirements.
Environmental Studies p.l3
No comments, recommendations, or Title 16 permit requirements.
G-eotechnical and Seismological Investigations.
It has been indicated that explosives may be used for some tasks in this
study program. Use of explosives within one-quarter mile of the Susitna
River and its tributaries must be approved by the Department of Fish and
Game. Before this approval can be secured, more information showing the
approximate location, charge size, and proposed dates of explosive
detonations must be provided to this Department.
..
...
...
-
-..
-
-
-
-
...,
.,.,
-
-
...
-
-
-
-
-
-
.....
..,..
'-
-
-
-
-
.-J. Pedersen -3-5/28/80
In accordance with AS 16.05.870, exploratory drilling and other activities
related to this work are subject to the following requirements:
1. There shall be no fuel or petroleum products stored within 100 feet
of the Susitna River and its tributaries.
2. All mobile equipment shall be refueled at least 100 feet from the
vegetated bankline of the Susitna River or its tributaries. Non-
mobile equipment used in the course of drilling over river ice may
be refueled on the river ice but extreme care should be taken to
avoid spillage of petroleum products.
3. Drill cuttings shall not be disposed in the Susitna River or its
tributaries.
4. Sedimentation from core drilling over ice of the Susitna River
shall be minimized by casing each drill hole from the riverbed to
the ice surface •
5. Discharge water from permeability tests shall not be introduced
directly into flowing waters of the Susitna River or its tributaries.
6. Tracked or wheeled vehicles or equipment shall not be operated in
the flowing waters of the Susitna River or its tributaries.
7. Each water intake equipment structure must be centered and enclosed
in a screened box which must be constructed to prevent fish entrapment,
entrainment or injury. Screen mesh may not exceed one-fourth inch.
Pursuant to 6AAC 80.010(b), the conditions of this permit are consistent
with the standards of tl1e Alaska Coastal Management Program.
This letter constitutes a permit issued under the referenced authority,
must be retained onsite to be valid and expires December 31, 1981.
Please be advised that our approval does not relieve you of the responsibility
to to secure other permits, State, Federal or local. You are encouraged
to contact the Anchorage Permit Information and Referral Center, 338
Denali Street, Room 1206, telephone 279-024, if you are in doubt about
other required permits.
Failure to abide by permit stipulations and requirements is a misdemeanor
punishable by a fine of not more than $1,000 and/or six months in jail.
Sincerely,
cc: John Rego -BLM
Robert Bo\'1ker -USFWS
Kyle Cherry -ADEC
Larry Dutton -ADNR
RECEIVED J UN 1 G 1930
ALASiiA I•OlVEli{ AU'l,II()I{I'I,Y
333 WEST 4th AVENUE· SUITE 31 ·ANCHORAGE, ALASKA 99501 Phone: (907) 277·7641
(
...... ,
Mr. Ron Corso
Federal Energy Regulatory Commission
400 1st Street, N.W.
Washington, D. C. 20427
Dear Mr. Corso:
(907) 276-2715
June 13, 1980
Pursuant to previous discussion with Mr. Quinton Edson, we request FERC
presence in Anchorage to discuss various licensing aspects of the Susitna
Hydroelectric Project. This visit could be in conjunction with your staff's
·plans for visi~i.ng the Tyee Lake site.
. . The n~~d for. the meeting 1 s evidenced by the strong urging for such a
session by the,state and federal agencies who have an interest in the project .
. ,, .:: .. It:-is the consensus of all,._involved that a face-to-face meeting with FERC is
sKAPOWER -rieeded.at.this early stage.of·the study process to insure that proper work
urHoRtTY ~ffortds·planned especially in the environmental and fisheries programs.
UStTNA J]he meeting. will constitute the second convening of the Susitna Interagency
E .p 5700 ~Steering Conuni ~t.ee. Acres. Arneri can wi 11 be represented. and prepared to discuss
-._.u___:_t~e;fisheries anq,..in-stream;flow study programs in detail. In our opinion,
...
-
-
-
-
..
-
-
-
-
the:timing for·a::·meetirig.·with your staff is ideal. '
~ .-o-o?.zi:\' ,/'·: ~~-.:-~(;J'l'·d·::·f·i·k;~:·to pl~:~,;,}~~C~ :two-day session either before or after your
I ai. ·( ...JsFaff's··visit.to\Tyee Lake~·:.we. await your response and recommended meeting
':· .....
. ::;d~tes ... We~will,.adjust to your.,schedule.,·
. 1-I ... , . :·; ...... ·. .. . . .... ., · ......... ,. . . JL ~ .. ~·-·::·.~·r;;~·llk:~:::;~Jt'i6:r you~. c~'rit·i;J.J·~~---~ssistance in guiding·.us at this early but
J~S-~.-S..1it1ca1,st.ag::··o_~,:.~:oject planning.,
'\ ..... -I .. , . , . , . ,.,. , .: !,·.,.. . . . . ,, '.1 ~r . , .. ,.. .. .
,.. r ·r.-~1 •. ·, I .·: '· • I·,//;,, .. I • ' •I· I; r f ': • ·.,,
::-: ' ·~:-:j --:.'..,. --'' , : ';:•; ~·, · .. '·. 1•11 ,; ·•I~~:"'; ' ,, I
~~ L~~:,! ·-:-~oR rHE'1E:xEcilfr"V'E'.: ·or REcToR .. :
): J '/V.~-! ._· -~ ' .·I . ·.:;:;···.:.;!o',::._·, .. ;--·Sh:·.:· ..... ; ,,
' J.? ':) I ' I . '· .. ·: .. '.!· .. · :"•(!1:,,' " '''·i ):,;~;~~!~=:~ .·. ~ .· :-·:;,;::..(:£S{;_:: ·,.
:; ;~_i!ij cJ1L .. Joh,.~, ~·~~.~~~·
1 o··NL I· . ,, ..... ··•··"' II~~~~~--.' ·; .......... .
~~---~-~ t:" ~.el(. ,...,-__::___!~
'K "'-~· -~-yy·:J' --
: I
Sincerely,
I /;
r/ tf . · .:J. ·.. / . /} 1 ;{,7!~ /(:""~?·;;.~.
Robert"A: Mohn
D1rect6r of Engineering
,,,.,
·,,
.. }' :·:!/!''· ........ ;:
'"
. :~·:::· ·.,
''.
...
-..
-
-
...
-·---, ! I
;.N\1<:. !=
FILE -
~·f--.IJ·.c. I ---r--, __ •• 4""!1n
r
l WILLETT
_I WITTE
': ' LAMB _, ,..,
I BERFIY IJ
I f..-. ~ /
~ ""'A-n y f ...;z;,
l'h:l 1/n'ilil-u•· f
I
I # // r "'GILL ~F.., ~
:r LOWFIEY / /
t: FRETZ
,{: r"
"'-
: HUSTEAD
l BOVE
L r CHASE
I r
I
t r·
I"""· :
Mr.
Ina
Dean Shul!lfay
August 27, 1980
P5700.11.88
• T.386
"--!ral Energy Regulatory Commission
North Capital Street 825
OLP 4th Floor
Was
De a
As
pro
fin
pro
In
to
You
hintton, D.C. 20426
r Dean: Susitna ~droelectric Project
Distribution of Environmental
Procedures Manuals
part of our Susitna Hydroelectric study program we have prepared
cedures manuals for the major environmental subtasks. Enclosed please
d a complete set of anuals prepared to date.a As modifications in our
cedures occur, you w111 be supplied with revised editions.
addition, nine (9) sets of these procedures manuals have been sent
the Susitna Steering Comnittee for review.
r review and c011111ents on these procedures manuals w6uld be appreciated.
Sincerely,
KRY/jmh
Attachment
r.
~~m~~ ®~ ~~~~~~
ltEI~\IIT~IENT o•· ~.,TifH,\14 n•:SOifllf:ES
DIVISION OF RESEARCH & DEVELOPMENT
August 29, 1980
Eric Yould
Executive Director
Alaska Power Authority
333 W. Fourth Avenue
Suite 31
Anchorage, AK 99501
Dear Mr. Yould:
RECEIVED
A!.AS:V\ POW::~ AUTHORITY
JAY i HAMIIOIID, GOYEIIIDI
323 E. 4TH A VENUE
ANCHORAGE, ALASKA 99501
279-5577
At the Susitna Hydro Steering Committee meeting held on July 18, 1980,
the navigation user needs study as it relates to instream flow studies
was discussed. At that time it came to our attention that personnel
from the University of Alaska completed a pro osa uct this
work, however, or u getary and project scheduling purposes it has
been determined not to conduct this study at this tim~. Staff of TES
indicated to my staff that the possibility exists, pending further
hydrologic studies and continuing development of instream flow studies,
that data on navigation user needs for instream flow purposes may be
gathered in the future as the feasibility studies continue.
I would like to request that your office and that of Acres, TES, and
their subcontractors keep my department abreast of development of data
gathered relating to navigation uses on the Susitna River and its
tributaries. Additionally we would appreciate receiving a copy of the
initial proposal written by the U. of A. staff to conduct such a data
gathering effort. This will aid us in the review of any developments
in this area of study, which this department believes should be
conducted as part of the overall feasibility studies.
Sincerely,
ill
Allan Carson
Deputy Director
cc: Mary Lu Harle
...
-
...
,1
J
J
J
J
J ,
.J
1
~
-
.,
.,
-
-
-
-
-
....
-
-
....
(,
-
-
'-
/ Mr. Robert Shaw
State H1stor1c Preservation Officer
State of Alaska
' Department of Natural Resources
Division of Parks
619 Warehouse Avenue
~chorage, AK 99501 .. -.
Dear Mr. Shaw:
/
May 4, 1981
P5700.11.74
T.868
Susitna Hydroelectric Project
Cultural Resources Invest1qat1on
In response to your request during our meeting of April 7, 1981, I am
forwarding a copy of the Susitna Procedures Manual for the Cultural
Resources Investigations. In addition, I have enclosed a copy of the
Cultural Resources section from our Plan of Study.
I trust this will aid 1n your continued review of our proqram. Any
specific questions on this component of our study should be referred to tw. Lewis M. Cutler of Terrestrial Environmental Specialists, RO .sox 388,
Phoenix, NY 14135.
KY:adh
Enclosures
~""' ,~
Yours truly,
Ke3in Young
Environmental Coordinator
1-.t
WIL.L.ETT
WITTE
BERRY
l"r
t HI·; "').'H \ ,t:
.:2::.]) c. · I 'I'J. 1 1-_....,., .,y
'N ""Ll..iHI!
L.AMif I' ....,_,
• Mark Robinson
deral Energy Regulator.y Commission
0 1st Street, N.W.
shington, D.C. 20427
SINCL.AIR -~ ar Hark: ~I
VANDER BURGH
July 22, 1981
P5700.U.88
T.990
Susitna Hydroelectric Project
Environmental 1930 Annual Reoorts
~,-~
,_
,.~ discussed I am forwarding copies of our Sus1tna 1980 Annual Reports.
CARL.SON
FRETZ
JEX
L.OWREY
SINGH
HUSTEAD
BOVE
CHASE
./ 1,· .:...
"'lh
f"
c
. 1
tk:l
JCK
L"<l
e scope and objectives of the various subtasks under which these reports
re prepared are outlined in our Plan of Study which you already have
cppy of. ·
though we are not seeking a fonnal review at this time, any cor:vnents you
ve would be very much appreciated.
Sincerely,
Y/ljr Kevin Young
Environmental Coordinator
closure
.. ,.. . . P. Hoover (AAI) -
0. 14ozni ak (APA).
..
...
..
...,;
-
-
...,;
-
...,;
-
-
...
--
-
-
-
-
-
-
-
-
-
1~7LH
~¥&V[ @~ &~&~~& I JAyS. HAMMOND. GOVERio'DR
I
Df~I•:\UT :Uf-~-'T Of' t'ISII :\ 'U (.,\.TiE I 333 RASPBERRY ROAD
ANCHORAGE, ALASKA 99502
September 10, 1981
Jim Gil:
Acres American, lnc.
2207 Spenard Road
Anchorage, AK 99503
Dear Jiz:::.:
344-0541
Our Fairbanks office received a complaint from a moose hunter about
disturbance of moose by helicopters north of the Watana Camp during
the first week of September. Apparently, helicopters that appeared to
be flying point to point were seen to periodically drop down to lower
altitudes as though they were looking at animals. He did not identify
the helicopters, but there is a fair chance they were from the camp.
~-,
I
j/, 7 {.
. l C:<.-:f 1 _ I t1 / ,.; ;; )
··~ --2:::
.,..~
The same hunter complained about a Cessna 180 which I have determined X
to be one of our chartered aircraft that was radiotracking bears.
The hunter felt that these activities were causing moose to move to
lower elevations into more timbered areas. We have no evidence to
support this impression, but it is certainly possible to disrupt
animals enough to spoil an expensive hunt.
Some conflict with hunters are unavoidable, but we should try to
minimize them. We plan to try to avoid flights on popular hunting
days such as opening days and major weekends. It would be useful if
you would remind helicopter pilots of the problem and request that
they maintain sufficient altitude to avoid disturbing animals except
when their work or safety dictate otherwise. In particular, they
should resist the natural tendency to go take a closer look at
animals.
Sincerely,
~./?;/ -"-/"
Karl Schneider
Game Biologist IV
! x~
' '·
/
. I
_,....·~/
•• J ":_-.~~. _,.,.,.
,/
;..
. /1 •
Mr. Karl Schneider
State of Alaska
Department of Fish & Game
333 Raspberry Road
Anchorage, Alaska 99502
Dear Karl:
RECEIVED SEF 2 9 1981
September 21, 1981
P5700. 11 . 70
T596A
In response to your letter of September 10, 1981, we have re-
emphasized to Mr. Granville Couey the necessity for minimum
distrubance to wildlife in the areas mentioned, and that the
minimum altitudes be maintained by all aircraft.
Mr. Couey is fully aware of all restrictions and has reaffirmed
~that the helicopter pilots and other people we charter with are
-~lso aware of these conditions.
Your point about opening days and major weekends will be fully
considered for next year should the same level of helicopter
activity take place.
Unfortunately, activities were at a rather high level at this
time and I'm sure some hunters were unaware of the activities
going on in that area. We have asked APA's Public Affairs Office
to consider providing information to the public regarding the
activity in the area so that guides and hunters would be informed.
VTS/ja
\. cc .--. Buffalo~
APA -b. Wozniak
,_JQurp~~ I ~~~~~("' /~a~~;-D. Gi-11
Resident Manager
ACRES AMERICAN INCORPORATED
IIIII
-
-
--
--
-
-
111111
111111
-
-
-
-
-
-
-
-
-
......
-... ":-..._
hL£ ,.,,-...-~ ... -· '
: './ ~i..-1 ~t:~:. ~ """'0 ,_u
::..s~
Septerr1hcr 29. l:iB.J
l\·U .OVI.-11. U·.lTtR 'tO TH( PtiDLIC ;a L.Afifif. trf(D Hl m .. t HfHJtLSl lD AGIJiC1ES
A«D OR6ANIZATIOuS
On February· -1. ~9fl0i-i'..f'. fric 'Y.Qu1dw Executive Direct.m~ of the
Alaska i-'owcr Au Ulor1 t.,\•. prcvared a 'fDNiH"d1 ng le t.tcr-1 nt.n~cJuc:i ng Ute
oewHcd f'lan ot· Stud..\' for the Susitn~ t(ydroe Jc.ctrfc Project. He nuted
at the ti~ that the. pian did not. purmanently fix· thP. m~nnet'' in whieh
the pt-npo&ed work would be ~ceom;Jli'shed ano~expressed hts des.i rN~ Ui~t
your as~1s.t.ZJnc~ -wbuld contt--ibute tQ its st.C'cHS~v hiq~ro\"l~ll!!nt •
The Pt"'je-ct. 1' e.am has uc..aen he·avi ly engaged during t.ne pa~t ni r.c .
m:mth~ in aeccnHJ•Hs-hi.n!J. tJua man.v 'task~ ~nd stlhtas~s \~h~ch together w'i i1
ult.-·hnEtte1y 1 ei:~d tu tc~e bilsis upQn M!hich Uu: S~t.c of Al askil c.nn rr-Jlke iln
---..
1 nfornu:'{l deci 3i on as 'to whether 1 t. eroil or simulti r~roc.eed with the Sus i L.na .
Hydt"''electric Pt"'ject.... Con&troct.ion vf il camp was completed in hsn11 1980 ·
[; ---
DP.iJf' the Watana CilUA" s-1 w... Ficl a crews have nPP.rated-$i nee then f runt: Un:
lt<\tana Cafl:Ql b.nu from a number of nt .. her-10C.(l1' .. 1"<ms. ltur•orhmt tnfunr!!!-titm
has b~en and continue..'i to b~ collected. W..:-kmm m~t:h nr:Jre now about
the geology~ hydro logy, s.c1 Stf.t) logy. environment~ ilnd espP.ci ally about
the concerns and i ntcres ts of the pub 1 i c._
-. . Even whil~ the wmi:. h~s progf"tlssc~, Lr-lc Youla•s p-ru~tic d~1res
..... ::"'A PO'.~'::ii h~-.:e been t'eal1zed. A numher of 1n~orumt du;n9es: have been made to the
.-,-... -J~.7Y nhn. lh1s vo1unm ductlml!nts the r·evisions an.d briefly de-scribes their
· js.;Tr;~ genesis. Om;Q a-gain .. your coreful t-evie111 and ~m~n\.s n"'l•ld he \'('r)f
··· :-, :=~;n rn~ch appreciated. I ~i nee~ ly hopC! ycu wi11 tilkt! the t iln'i! to ~ddt'-eSS -... · -:-~ u.., '1-hem· to; • ,_._7_0\[
-··~ I-... --t-··---· ~
-i
E ....: I :~ <t n t: .
M~ •· nancy Blunck
Pubhc P8.rticip.otion Officer·
Alt'-Sk" Power Authority
333 !lest <1-th Avenue~ Suite 31
f,l-ldtot'age. i\1 i1Ska g9.501
,/ ..._ 3 Z I
...._ ~-~ -· --=--1 On beh~.lf of the enth"'e Project learn, J \'inJ)t. t,o ~xp;~-&;;. Oul~ t\''precft'-
. .,---t.'i~n fot· the $trr.mg intet--es.t you fli)Ve cxpr"Cs~·c-tJ to d~t..l!. _ \4ith your
~A.'G·'--as~~"r.1st.ance:r tJ•e txw1s.ed p1an wtli c.ont1nu~ to .b~ i2: dymumc docum=nt.
/ . Sfncere1y .. ' ;-A _, <.__;_4. Zj
~G :_:
::-~! s
-_._j
·; L ..
:--~·.-,-r ·_:; __ ,
·' r l . ~ ~. ---.
I ' ___ j
---,-1
-:-1 __ ,__J
' ___ / _____ _
. -
~ / r .:-t /
---............. ,;
' ,I
'I
~j -_,
Jonn n. t.aW:rence
.Pr-oj l"C:t. t1antrgcr-
~ .-.. '1 r'
~ -~
_ ••. , t . ~ ~
·'
~~--
/ '
··' ..... .~ r . • '~
...-
0 ..
~-
c.
(
_)
NOTES OF MEETING
DATE: April 6, 1981 PROJECT.NUMBER: AAI 218
LOCATION: DNR, Division of Minerals and Energy Management; 703 W. Northern
Lights Blvd., Anchorage
ATTENDEES: Glenn Harrison, Director; Division of Minerals and Energy
Management. J.O. Barnes, R.J. Krogseng, TES
SUMMARY OF DISCUSSION:
Mr. Barnes gave a short presentation summarizing the history of the Susitna
Project and the role of Acres and TES in the present studies being conducted
for the Alaska Power Authority. ·
Mr. Harrison responded that his divisions main interests involved coal, oil
and gas and that he foresaw few problems that ~he Susitna project would
cause in his areas of interest.
Mr. Harrison felt that the project 11 Sounds good 11 and was well thought out.
Mr. Harrison also commented that it would be good, as far as his division
was concerned, to have some roads built into the Susitna area.
Mr. Harrison stated that he appreciated the meeting and that he would like
to be.kept informed on a periodic basis.
. ~---=--~--.---:-~·-.--·----=---·--.
Prepared
..
-
-
..,j
-
...
-
...
"' -
-
-
-
-
...
-
-
-
-
-
...
-
·-
NOTES OF MEETING
DATE: April 6, 1981 PROJECT NUMBER: AAI 218
LOCATION: Alaska Department of Transportation, Aviation Building, Anchorage
ATTENDEES: Jay Bergstrand, DOT, Area Planner; J.O. Barnes and R.J. Krogseng,
TES
SU~~RY OF DISCUSSION:
Jeff Barnes outlined the history of the Susitna Project and Acres and TES's
role in the present studies. Mr. Bergstrand was familar with the project
and had been present at some of the Susitna project meetings. -. c_, Mr. Bergstrand requested a copy_ of the Environmental Annual Reports, and
-
-
-I
-
he was referred to Nancy Blunck 1 S office at APA.
Mr. Bergstrand asked about transmission line high voltage effects~ fish
passage problems around the dams; what was planned for disposing of the
timber in the impoundment areas, and was burning being considered as a
mitigation measure for moose?
Mr. Bergstrand was particularly interested in the planning process for Access
Roads, Transmission Line routes and transportation corridors. He showed us
proposed routes for new roads in the Lower Susitna Basin and we discussed
where they would cross the proposed transmission lines.
Mr. Bergstrand requested more info~ation regardi~g the~mpact and amount
of flying activity during the study and construction periods the Susitna
Project would have on the Talkeetna Airport. This information would be
used to ascertain if the state would have to provide more services at the
Talkeetna airport. ( A lette~ requesting this information was sent to
Mr. Brownfield of Acres on April 16, 1981).
(,;·
Page 2
Mr. Baya inquired about the status of legislatiY.e funding to cover the rest
of Phase I studies and the tran~ition period.
· Mr. Baya wanted to know if any incremental instream flow work was being done
on the Susitna River by the state.
Mr. Baya feels that more attention needs to be paid to instream flow impacts,
the effects can be far-reaching: He pointed out that the move of the state
capitol, urban growth of Anchorage and the Mat-Su, the proposed causeway to
Point MacKenzie, all could cause serious impacts and need to be considered in
a regional planning effort. · He also pointed out the need to recognize the
secondary impacts that a large supply of hydroelectric power would cause.
Mr. Baya pointed out that the Fish and Wildlife Service will be asked by the
Secretary (of Interior) to respond with comments during the FERC review process •
The F&WS also has the requirement to coordinate fish and wildlife view points
from the different agencies. Mr. Baya feels that the Susitna project has moved
forward too far without funding for Fish and Wildlife Service participation.
He would like to have a man assigned full time to the Susitna project to
monitor the studies and keep him up to date because in the near future he will .
have to ask himself "can I sign off on that?"
...
...
....
...
-
-
....
....
...
...
Mr. Baya feels that the APA needs to find a way to get the F&WS actively involved ....
They need money to finance a staff position (approximately $50 -60,000 a man
year). Normally when the Corps of Engineers have a project they would give the ...
F&WS money every six months through an allocation transfer.
Mr. Baya commented that recent cutbacks have caused problems and will probably
result in a reduction in staff. In spite of these problems Mr. Baya said "we
want to help plan a sound program •••.. we don't want to be obstructionists."
" •.. but ~ithout funding for a full time position it will be virtually impossible
to completly review the study in a short period of time.
Mr. Baya commented that in projects in the Lower 48 states they have found that
often they had not looked far enough down the road to be aware of all of the
impacts. For instance, along the Mississippi River the State of Mississippi
is losing 16 miles of Delta every year, because river channelization is dumping
sediments in deep water instead of spreading them over the delta areas.
...
...
-
-
-
-
-
-·
-
t·
-
-
-
-
-
-
_)
NOTES OF MEETING
DATE: April 6, 1981 PROJECT NUMBER: AAI 218
LOCATION: DNR Office, 323 East 4th Ave., Anchorage
ATTENDEES: Mr. Ted Smith, Director, State Division of Forrest, Land & Water
Management, ADNR. Mr. J.O. Barnes, Mr. R.J. Krogseng, TES
SUMMARY OF DISCUSSION:
Jeff Barnes outlined the history of the S~sitna Project and TES's role in the
studies.
Mr. Smith had recently talked to Brent Petrie (now of APA) about the Susitna
project and he appreciated the briefing and the concerns shown for his departments
interests.
Mr. Smith expects to get re-1 ief from the Legislative mandates which he feels
are causing many of the problems in the state land disposal program.
Mr. Smith feels that the access roads for the Susitna Project will help to
open up and provide access for more state disposal lands.
Mr. Smith strongly feels that the Alaska Power Authority should file applications
for water rights as soon as possible to both reserve the water rights and to help
DNR plan. {Alaska has recently adopted a water rights law similar to that of
Montana and other Western states). He also would like to see applications
from APA designating approximate routes for access roads and transmission lines
so they can be included in DNR's planning at the earliest p~ssible date.
Prepared by ~~~--,z __
()
-)
NOTES OF MEETING
DATE: April 7, 1981 PROJECT NUMBER: AAI 218
LOCATION: State Parks Headquarters, 619 Warehouse Avenue, Anchorage
ATTENDEES:· Jack Wiles, Robert Shaw, Doug Reger, Alaska State Parks; Kevin
Young, Acres; Jeff Barnes, Lew Cutler, R.J. Krogseng, TES.
SUMMARY OF DISCUSSION:
Mr. Barnes gave a short presentation covering the history of the Susitna
Project and the role played by Acres, TES, and other subcontractors in the
present study for the Alaska Power Authority.
Mr. Shaw and Mr. Reger requested a copy of the Plan of Study and the Archaeology
Proc~dures Manual. (Mr. Cutler will go over the Annual Report with Mr. Reger
on the 8th of April).
Mr. Wiles was concerned that if the State Parks Department would be the manager
around the reservoir area, how. big was the area going to be, or would it just
be the 200 foot buffer strip.
Mr. Reger wanted to know what was~the FERC application. He also wanted to know
if the FERC people would consult with·his staff office. He also commented that
they hadn't been involved up till now.
Mr. Shaw wanted to know what the overall construction schedule would be.
Mr. Wiles inquired about the status of the-access road and what the present
plans were.
It was also established that artifacts that came from native owned ground are
usually placed in the University of Alaska Museum to be held in trust for the
natives.
All attendees agreed that the Susitna Project "sounds good'' and they were
satisfied with the planning that had gone into the. studies.
-
-
...
....
...
...
-
-
-
-
....
...
-
·-
-
-
-
-
-
-
-
-
-c·-_
-
-
I....
-
-
-
-
.....
NOTES OF MEETING
DATE: April 7, 1981 PROJECT NUMBER: AAI 218
LOCATION: USF&WS, Tudor Road, Anchorage
ATTENDEES: Keith Baya, Assistant Area Director F&WS; Kevin Young, Acres;
J.O. Barnes and R.J. Krogseng, TES.
SU~~RY OF DISCUSSION:
Mr. Baya was recently assigned to Alaska so Mr. Barnes's presentation covered
the history of the Susitna Project, the role of Acres and TES in performing the
studies for the Alaska Power Authority, and an outline of the studies in
progress to help bring Mr. Baya up-to-date on the project~
Mr. Baya appreciated the briefing on the project and commented that he would
like to see the Susitna River studied all the way down to the esturary to be
sure there were no unforeseen problems. He acknowledges that effects on the
lower river may be difficult to measure.· He also felt that another question
that will arise is "why isn't it like other hydro projects?"
Mr. Baya felt that the NEPA decision making process should be followed.
Mr. Baya believes that the Sus·itna study is going to be one of the major studies
for the next few years. He feels that the Fish and Wildlife Service needs to
be involved in these studies and that his people have some expertise, but they
need to be on the ground to be able to see -and -s-u~)ervi se the studies~--If_:_--"-
they are not included Mr. Baya believes the .. ----FERC coordination may take
longer than felt politically wise or timely."
Mr. Baya expressed an interest in what studies were planned for the coming year.
If there is an early June tour for Starker Leopold, Mr. Keith Baya would.like
to be included.
Mr. Baya wanted to know.if Habitat ~valuation Procedures (HEP) were being used
in the studies. He felt that it may be necessary to do a HEP analysis ·later on.
. Mr. Baya inquired about Dr. B. Kessel's Avian and Small Mammal Studies and what
was scheduled for the summer field studies.
( ..
(
_)
Page 3
Mr. Baya also commented on the EIS that will be written on the Beluga Coal
fields in the next few months, and how they plan to build a model to help
figure out what (data) is driving the system •. They also will be looking
at the question of whether it would be better to build a port at Tyonek or
' haul the coal by railroad to Seward.
-..
-
...,
-
...
...
, -
....
-
'99 ~-.... 1 F.. , ::=; ---~-
-
-•
-
-
-
-.
-
-
-
-
-
-
-
_)
NOTES OF MEETING
DATE: April 7, 1981 PROJECT NUMBER: AAI 218
LOCATION: Department of Community & Regional Affairs, 225 Cordova,
Building B, Anchorage
ATTENDEES: Ed Busch, Senior Planner; Lamar Cotten, Associate Planner;
Kevin Young, Acres; J.O. Barnes and R.J. Krogseng, TES.
SUMMARY OF DISCUSSION:
Mr. Barnes gave an overview of the history of the Susitna project, Acres
and TES's involvement in the present studies and our reason for talking r} to people from their department.
-
-
-
-
-
-
._
Mr. Busch was aware of the steering committee through Al Carson. r~r. Busch's
department provides planning·assistance to communities upon request. The
Department also has a management program. One of their programs provides
coastal zone management for the Matanuska-Susitna Borough. This could
extend up the Susitna River.
Hr. Busch's office has had sporadic involvement with the Susitna project.
He was on the review committee on contractor selection and also attended
some of the workshops.
Mr. Busch voiced some concerns that his office has about planning for the
Susitna project. He feels there will be a number of impacts on local
governments, and he wanted to know if their concerns had been considered?
Mr. Busch believes that the-Matanuska-Susitna Borough will bear the brunt
of the impacts (positive and negative) caused by the Susitna project. A
major problem will be providing increased services.
Mr. Busch wanted to know if the access roads would be kept open after the
project was finished and who will maintain them. He also wanted to know,
if the railroad is built, has anyone considered the impact to Talkeetna
caused by people driving to Talkeetna, parking and taking the train?
Mr. Busch.recommended that TES do community profiles on the towns and villages
that would receive most of the impact. As a minimum he suggested community
profiles on Talkeetna, Cantwell, Paxson and Gold Creek. · A ·comnunity p;o-file
is a collection of information with photos and a map of the community.
(examples were provided). The profiles have been costing $10-11,000 to produce
with the majority of the expenses going for per diem expenses and cartography.
c··
PAGE 2
(Northwest Gas Pipeline Company produced some of the examples).
Mr. Busch pointed out that if a village is incorporated into a second class
city (such as Talkeetna) they are able to have more input in planning and
governing themselves. For the smaller villages the State Legislature is
the governing body, with the actual planning done by Mr. Busch's department.
Wildlife planning is done by the AOF&G,and the Matanuska-Susitna Borough
provides the schools. Mr. Busch does not speak for the Borough unless he
has been requested to do so.
Mr. Busch feels the number of construction workers has been under-estimated,
as an example, the Alyeska pipeline was under-estimated.
Mr. Busch recommended that a permanent construction camp be built for the
project. The temporary camps built for the pipeline are still being used
and it would have been cheaper in the long run to build permanent camps.
Mr. Busch commented that people from Frank Orth and Associates have talked
to personnel in his office.
Mr. Busch also pointed out that the only way his office gets involved is
when they have been asked to by the community.
~--·-~
ltit:f-C:::=fyff~~reilig:--TTES
...
...
...
~
--
...
1
....
---
IIIII
-
-
-..
-
-
-
-
-
-
-
-
_)
NOTES OF MEETING_
DATE: April 8, 1981 PROJECT NUMBER: AAI 218
LOCATION: Department of Public Safety, Division of Fish and Wildlife
Protection, 5700 E. Tudor Road, Anchorage
ATTENDEES: Colonel Robert J. Stickles, Director; Lt. Col. Tetzlaff, Capt.
Wayne Fleek, Lt. Rod Mills, Department of Public Safety; Kevin
Young, Acres; J.O. Barnes and R.J. Krogseng, TES.
SUW~RY OF DISCUSSION:
Mr. Barnes presented an overview of the history of the Susitna project and
the part played by Acres and TES in the present studies being conducted for
the Alaska Power Authority.
(-... Col. Stickles-requested that his department receive copies of the annual
-
-
-
-
-
-
-
-
-
-
reports for Fish, Big Game and Access Roads.
Col. Stickles asked what effect the dams would have on the flow of the Susitna
River below Talkeetna.· He also wanted to know what water temperature changes
may occur. He was ve~ interested in the possible effects the project would
have on moose and caribou. Col. Stickles also wanted to know how many miles
of access roads were planned.
Col. Stickles wanted to know what ice effects were expected in the impound-
ment area and also the effects expected in the downstream reaches of the river..
He also wanted to know what the construction time table was and when it would
start. He needed this information to help plan for the placement of officers.
He will probably assign an officer to Chulitna when construction starts.
Capt. Fleek asked about the amount of helicopter useage during the studies.
He also wanted to know where the transmission line routes would be and if
there would be access roads along them.
Capt. Fleek wanted to know how many people would .be living near the dams for -
maintenance and operation of them.
Capt. Fleek wanted to know if the impoundment areas were going to be logged.
He also was concerned that i~e shelving might cause caribou crossing problems.
Capt. Fleek corrrnented on t~e large number of bear in the area and wanted to
know if we had had any bear problems-. He also requested that Fish and
Wildlife Protection Division be sent the results of the Mitigation Committee.
Their division would like to be in on mitigation planning.
c·
)
PAGE 2
All agreed that Protection Division's greatest concern would be the access
provided· to the area. They wanted to know if a landing strip was going to
be built. They would also be interested in getting.permission to store
extra gas for their helicopter at Camp Watana later on.
Lt. Mills said that they could tell us the number of guides using the area,
and he agreed to send Krogseng a list of the guides and their best guess on
the number of hunters using the area.
-· ~-:---. -·
Reported by
..
..
_,
...
...
...
..
...
...
...
_,
..
-..
TES ...
-
-
-
...
-
-
c
..... ~
-
-. (
-
-
NOTES OF MEETING
DATE: April 8, 1981 PROJECT NUMBER: AAI 218
LOCATION: Department of Energy, Federal Building, Anchorage
ATTENDEES: Fred Chiei, Deputy Regional Representative; Kevin Young, Acres;
J.O. Barnes and R.J. Krogseng, TES.
SUMMARY OF DISCUSSION:
Mr. Barnes made his presentation covering the history of the Susitna project
and the role of Acres and TES in the present studies being conducted for the
Alaska Power Authority.
Mr. Chiei appreciated being kept informed on the status of the project.
Mr. Chiei commented· that his office is an off-shoot of the Secretary•s.office
and that he deals primarily with energy'policy•.
Mr. Chiei noted that the FERC people operate out of his office when they are
in town,.while the FERC engineers operate out of San Francisco. He also
commented on the need for energy planning.
Mr. Chiei said that his office tries to stay out of the states territory in
energy matters, although a lot of things have not surfaced yet. He prefers
it to be more of a state project and is happy to see state funding for it.
Mr. Chiei commen"t:ed that hydroelectric_ projects_!i.ke th~Susitna PJ_£>j_~ct.
release energy like coal, oil and_gas t~at can be shipped elsewhere in the
U.S. which helps to distribute the country's energy more evenly.
Mr. Chiei said that he doesn't see any problems at this point and periodic
reports (like this meeting) would be sufficient. He would also be interested
in seeing the development scenario when it is developed.
-Mr. Chiei would like to receive information from Acres on the Tidal Power
Study.
-
-Reported by 6, yr -,-r r-
7
.,,
-
(_,
_)
NOTES OF MEETING
DATE: April 8, 1981 PROJECT NUMBER: AAI 218
LOCATION: National Park Service, 540 West 5th Avenue, Anchorage
ATTENDEES: Howard R. Wagner, Associate Director, Carl Stoddard, Terry
Carlstrom, Ross Cavenaugh, National Park Service; Kevin Young,
Acres; J.D. Barnes, R.J. Krogseng, TES.
SU~~RY OF DISCUSSION:
Mr. Barnes outlined the history of the Susitna project and the role Acres
and TES have in the present studies being conducted for the Alaska Power
Authority.
Mr. Cavenaugh asked how the Fish and Wildlife studies fit into the overall
planning process. He also asked what was being done about cultural res9urces.
Mr.Cavenaugh also wanted to know what effect the project would have on the
proposed Denali Scenic highway.
Mr. Wagner said that he would be very interested in the transmission line
route, especially where it is near the park (Denali). If the route passes
through park boundaries, the right-of-way approval may need congressional level
approval. They want to keep the transmission line out of the park.
. .
Mr. Carlstrom wanted to know what range of considerations or options were
available. He conrnented that access could be a direct ·problem. The Denali---
National Park is only on the west side of the Parks highway, but the trans-
mission line would have a direct impact on the land across the road. He
also wanted to be sure that someone was looking at indirect impacts caused
by the project.
Mr. Wagner also commented that USGS would soon have 1:250,000 scale maps with
the.new park boundries marked on them.
Reported by: ~;;gpFng , rEs
-..
..
....
--
-
~
...
..
....
~
....
-
-
-
--.
-
-)
-
-
-
(_;
._
-
-
,-
-
-
-
-
NOTES OF MEETING
DATE: April 8, 1981 PROJECT NUMBER: AAI 218
LOCATION: U.S. Anny ~orps of Engineers, Elmendorf AFB, Anchorage
ATTENDEES: Lt. Col. Perkins, Deputy District Engineer; Kevin Young, Acres;
J.O. Barnes and R.J. Krogseng, TES.
SUNMARY OF DISCUSSION:
Mr. Barnes briefly covered the role of Acres and TES in the present studies
of the Susitna project being performed for the Alaska Power Authority.
Lt. Col. Perkins stated that the Corps has no funding for any work on the
Susitna project.
Lt. Col. Perkins strongly feels that the state should be asking the Corps;
What permits will -be required? The state should also inquire about getting
one blanket permit for the project.
Lt. Col. Perkins wanted to know if we knew what permits would be needed, in
particular any section 404 classification of wetlands would be filled in.
He recommended that the head of his environmental group be contacted.
Lt. Col. Perkins also noted that the access roads will require permits to
cross wetlands; also any dredging or filling that is required. Permits will
also be required for constructing the transmission lines, especially if access
roads are built.
Lt. Col. Perkins pointed out that it takes a minimum of 200-220 days to process
a permit, and if there are any objections they may have to be resolved in
Washington, which will require even more time.
~
(,
_)
NOTES OF MEETING
DATE: April 9, 1981 PROJECT NUMBER: AAl 218
LOCATION: NOAA National Marine Fisheries Service, Federal Building,
Anchorage
...
-
...
AJTENDEES: Ronald Morris, Supervisor, Anchorage Field Office, Brad Smith, •
NOAA Fisheries Biologist; J.O. Barnes and R.J. Krogseng, TES.
SUMMARY OF DISCUSSION:
Mr. Barnes gave a presentation covering the history of the Susitna project
and the role of Acres and TES in the present studies being conducted for
the Alaska Power Authority.
Mr. Morris and Mr. Smith are both members of the Susitna Hydro Steering
Committee and they will coordinate their work with the state fisheries
people.
Mr. Smith will be in contact with Dr. Dana Schmidt of TES concerning the
fisheries studies.
Mr. Morris asked about dam design features and said that he will be in contact
with NOAA engineers in the Oregon office.
Mr. Morris said that they appreciated the contact.
..,
...
...
'IIIII/I
wJ
....
...,
...
...
..,j
..,
-
Reported by ¢: ~· ?r.
R. J. frOSsenTEs •
....
...
-
-...
_)
NOTES OF MEETING
DATE: April 9, 1981 PROJECT NUMBER: AAI 218
LOCATION: Alaska Department of Environmental Conservation, 437 E. Street,
Anchorage
ATTENDEES: Bob Martin, Regional Environmental Supervisor, Steve Zrake, DEC;
-Kevin Young, Acres; J.D. Barnes and R.J. Krogseng, TES
-
-
(_,
.....
-
.....
~
-
-
-
-
-
-
SUMMARY OF DISCUSSION
Mr. Barnes outlined the history of the Susitna Project and the role of Acres
and TES in the present studies being conducted for the Alaska Power Authority.
Mr. Martin asked what impacts or changes were expected on water quality or
air quality. He also wanted to know if the studies were long enough to
establish a proper baseline ~eriod.
Under socioeconomic, Mr. Martin wanted' to know if we had studied power genera-
tion needs. He was referred to the ISER study.
Mr. Martin wanted to· know if the studies would continue after the FERC applica-
tion has been made. Mr. Martin also wanted to know "why the FERC application
date was set so soon". As an example, Mr. Martin wanted to know why the
decision on the access road had to be made so soon; he wasn't even "comfor-
table .. with how the three routes had been selected. He stated that his
department would like to keep access down because it would be easier to manage.
The Department of Environmental Conservation's interests in the Susitna area
are administered out of Mr. Martins Anchorage office. His major point of
contact is the Susitna Hydroelectric Project Steering Committee.
DEC's direct regulatory responsibility is waste water, drinking water, and
solid waste disposal. DEC also has an interest in instream activities.
Mr. Martin recom~ended applying for a variance to build the construction
camps to provide for drinking water and waste water and solid waste disposal.
Mr. Martin feels that the major impacts of construction activities are going
to be the access roads and the locations of construction camps.
Mr. Martin said that it may be easier to have just one transportation corridor.
As an example, in transportation and handling of fuel~ accidents are bound
to happen, like a truck may roll off the road. He feels that it is important
to avoid as many critical habitat areas as possible.
c·
_)
Mr. Martin was also interested in the water quality studies. He feels it is
very important to get a complete water quality series before road construc-
tion starts. He wants to be able to measure construction effects, such as
the run off into streams.from road building.
Mr. Martin is also interested in the .smaller feeder streams that would be
impacted by roads. He feels that 2-3 years .of data from studies would be
sufficient.
....
...
-
...
Mr. Martin expressed a concern about communities along the river disposing ~
of wastes in the Susitna River.
Mr. Martin was especially concerned about the fuel transportation and storage ...
system and the amount of fuel that would be used in a large project like
Susitna. He feels it is necessary to plan to avoid or minimize accidents ....
or spills.
Mr. Martin commented on the need to maintain ecological integrity through
land use and public use planning, and to have a voice in other areas that
he can't regulate. He wants to see rational land use development, something
that doesn't interfere with habitat.
Mr. Martin also wants to see more attention paid to using energy alternatives
such as Retherford's recommendation to use electricity to run pipeline pumps
instead of using oil or gas.
Mr. Martin strongly recommended building a centralized constructiun camp.
He also recommended building where the permanent facilities will be located.
Mr. Zrake wanted to know if under sociocultural impacts we were looking at
' .
individual desires too? He also wanted to know if this would cover the trans-
mission line too.
Mr. Martin stated that DEC does .not have any studies in progress that affect
.,
...
-
-
......
..
...
. '
Susitna. They are working on a wetlands study with specific Alaska guidelines. ..
...
..,
...I
-
-
-
...,_
...
....... (''·. _,
-
NOTES OF MEETING
DATE: April 9, 1981 PROJECT NUMBER: AAI-218
LOCATION_: U.S. Fish and Wildlife Service, Tudor Road, Anchorage, Ala~ka
ATTENDEES: Mel Munson, Chief Ecologi~al Services; Gary Stackhouse, F&WS;
Kevin Young, ACRES; J. 0. Barnes and R. J. Krogseng, TES •
SUMMARY OF DISCUSSION:
Mr. Barnes outlined the history of the Susitna Project and the role of Acres
and TES in the present studies being conducted for the Alaska Power Authority.
Mr. Munson asked what ADF&G's role was in the studies. He also wanted to
know·what the time frame was for all of the studies and when the EIS came . .
into the picture. Mr. Barnes.outlined the FERC process and where the dif-
ferent parts fit in.
Mr. Munson wanted to know if we had a preliminary permit for the project. He
-felt that it was important that the state file soon.
-
...
ln 1952 Mr. Munson looked at 20 different proposed dams for River,Basin Studies.
Devil Canyon and Watana Dams were part of that study. At that time he did not
find any salmon in ·the upper Susitna River.
Mr. Munson wanted to know if ADF&G was looking at winter moose range in the
( study area. From personal experience in the area, he felt that the south
-
-
-
-
-
facing slopes on the north side of the canyon from half way between Devil Can-
yon to Watana were important to the moose population during the winter.
Mr. Munson has watched caribou swim the river in many different places in the
· Watana area, they appear to get out any place they can get up the canyon wall.
Mr. Munson commented that during peak numbers of carioou he has seen 6-8000
caribou on Mt. Watana alone. Also during peak numbers be has watched them
crossing the Susitna River where many trying to swim the river would be carried
do~m-stream and drown. He has seen hundred$ of dead caribou washed up on shore.
Mr. Munson wanted to know.what was planned to mitigate for losses of moose habi-
tat. He also .commented that he opposed the Denali Dam because it would flood a
highly productivity area.
c
_)
Mr. Munson also wanted to know if we were looking at the area above the
Tyone River.
Mr. Young outlined the various darn schemes that had been considered and why
the Devil Canyon -Watana scheme had been selected. Mr. Munson commented
that it was a good choice.
Mr. Munson said that one of the things he was interested in was what we were
going to do to mitigate for lost moose habitat. He felt that there was a
need for habitat development on upper Watana Creek. Mr. Munson also suggested
burning, cutting or even sprigging willows as things to consider on Tsusena
Creek.
Mr. Munson was interested in the mitigation task force and its review group,
although he commented that there is not much you can do for caribou.
Mr. Stackhouse asked · what the status of the mitigation policy was. He
-
-
-
...
....
...
..
-
hoped the group would be able to produce a policy for APA. Mr. Stackhouse •
also wanted to know what the basis for mitigation would be, was it going to be
based on an acre. for an acre or an animal for an animal? .. •
Mr Stackhouse also asked about the vegetation analysis that was being per-
formed;he was concerned that the studies be of a high enough quality to be
able to use HEP (Habitat Evaluation Procedures) on the vegetation studies at
a later date.
Mr. Stackhouse wanted to know if any hydraulic changes were expected in the
river or if any-icing problems were anticipated. He was also concerned about
the possibility of ·any vegetation changes.
Mr. Stackhouse felt there was a possibility of some problems ·below Devil Can-
yon and he wanted to know. if are-reg darn was going to oe put in. Mr. Stackhouse
wanted to know what the planned construction periods for the dams were going
to oe, and if the Devil Canyon Coffer Dam would oe big enough to serve as a
daily re-reg dam.. .
·Mr. Munson asked about the expected water quality for the Susitna River between
Devil Canyon and Talkeetna. He commented that it probaoly would have similar
conditions to that found in Tazlina Lake. Mr. Munson wated to know if any
-
..,;
..J
-
-
-
-
-
-
-
-
-
-
.....
.....
(:
-
~
enhancement of the fisheries was expected, like in Kenai or Skilak Lake.
Mr. Munson would like to receive a copy of R&M's Hydrology Report. He was
interested in their prediction of.winter ice conditions.
Mr. Stackhouse commented that he felt that one of the biggest·problems in the
study was the fact that AOF&G hadn't published a procedures manual for the
fisheries study yet. He was also concerned that one person from ADF&G wore
two hats; he worked on the Susitna project and was also involved in the state
permitting process.
Mr. Stackhouse was very concerned that APA had not filed a preliminary permit
yet. ·He commented that withput the permit the F&WS has no official position
to initiate a formal seeping process under their normal NEAPA-FERC procedures.
Mr. Munson commented that under standard conditions the state and federal
-F&WS work together on Exhibit S.
-Mr. Stackhouse pointed out that they need to tie in with the work being done
-
-
on transmission corridors and they also need to work with the Steering Committee.
Mr. Stackhouse feels that time is the over-riding factor in the studies. For
instance, if a railroad is constructed for the access method, it would cost
~ an extra year.
-
-
-
Mr. Munson summed up his comments on a recreational standpoint by pointing out
that the reservoirs were not going to be good for fishing; that the Devil
Canyon reservoir would provide some recreational boating, but that the main
uses for the reservoirs would be to provide access for hunting.
I
Mr. Stackhouse commented that he would like to see a copy of the instream flow
studies.
Prepared by_4~~~~~rJ~---
c
NOTES OF MEETING
DATE: April 9, 1981 PROJECT NUMBER: AAI 218
LOCATION:
AITENDEES:
Bureau of Land Management, District Office, Anchorage
Art Hosterman, Lou Carufel, Gary Seitz, Bob War?~_John ~ego,
BLM; Kevin Young, Acres; J.O. Barnes and R.J. Krogseng, TES
SUMMARY OF DISCUSSION
-
-
...
...
Mr. Barnes made a presentation covering the history of the Susitna Project and •
the role of Acres and TES in the present studies being conducted for the
Alaska Power Authority. He also covered the studies and reports that are -
being prepared as part of the study.
Mr. Seitz wanted to know if-FERC was responsible for the EIS. He also wanted
to know if FERC would be asking BLM for permits or when BUM would get a chance
to outline their re~uirements.
Mr. Rego wanted to know if FERC would be the lead agency. The present permit
is good for three (~) years of studies. .After that construction permits would
probably be necessary.
Mr. Rego stated that he would like to see all three access routes studied;
the Denali route north, the south route to Devil Canyon and the north service
road between both dams. He commented that their Mr. Beckley has built a lot
of roads and that he ought to take a look at the different routes.
Mr. Hosterman wanted to know "what are the biggest problems?" Also, what is
the role of the State Fish and Game Department in the studies. He also wanted
to know about Cultural Resources and how they were being·taken care of. Mr.
Hosterman also asked about Human Resources and the Natives and their interests.
Mr. Hosterman wanted to know if induced seismicity caused by the weight
of the dam and reservoir was being considered. Also asked the question of
how much permafrost was in the area and whether or not it was being studied.
The group also felt that public participation in study changes was a good idea.
It was also felt that "if you are going to do one right this is the one."
Prepared by ,C. .. r· ?
R.J. rogs
..
..
...
-
..,.;
-
--
-
-
....
-
-
-
-
-
......
·-
t
-
-
.,._
-
f
\
-
-
-
-)
NOTES OF MEETING
DATE: April 9, 1981 PROJECT NUMBER: AAI 218
LOCATION: Alaska Department of Fish & Game, 333 Raspberry Road, Anchorage
ATTENDEES: Carl Yanagawa, Regional Supervisor, Habitat Protection; Kevin
Young, Acres; J.O. Barnes and Robert J. Krogse~g?_}ES
SUrWARY OF DISCUSSION:
Mr. Barnes gave a short presentation outlining the history of the Susitna
project and the role of Acres and TES in the present studies being conducted
' for the Alaska Power Authority.
Mr. Yanagawa outlined the state permit system in which Mr. Trent is still the
State Coordinator for the Department of Fish and Game for permits, although
Mr. Yanagawa issues the permits. Mr. Trent gathers the data and other informa-
tion that Mr. Yanagawa uses to issue the permits. The normal procedure is for
Mr. Yanagawa to get a consensus from the different departments to help make
the final decision .
Mr. Yanagawa commented that he is presently short-handed in his department. He
has a position number but no funding for it.
Mr. Yanagawa had some questions about the access roads. He especially wanted
to know when the road was going to be used. He said the Department .of Fish
and Game would be prepared to make recommendations and trade off in regards
to the access roads, but they did not have any real hang-ups about them.
As a result of a decision made in Juneau in March, Mr. Yanagawa will not be a
member of the Steering Committee. The policy of the department is that Mr.
Trent is the coordinator for ADF&G. The coordinator helps make the departments
decisions. Mr. Trent is the only one who can raise official questions on the
Susitna project.
Drawing from his pipeline experience, Mr. Yanagawa commented that this was the
wrong job for a total preservationist, because sometimes you just have to get
in and do your best to find the best route or method available and go with that,
that not everything will be pertect. He recommended getting in and looking at
routes early. Sometimes a problem can be solved by just moving the road 20 feet
left or right.
(
...
Mr. Yanagawa also feels that you need to keep asking yourself ••;f you spend •
another million dollars, how much more information are you going to get .. ?
He also feels that it is important to make everyone aware of the assumptions .-
that you are making up front.
Mr. Yanagawa also feels that you need to pick a starting place, because you
cannot wait for all the answers to come in before you start.
Also, drawing on his experience in building the pipeline, Mr. Yanagawa
recommended forgetting about building a constrcution camp for temporary use
and go ahead and design for permanent use, because you will save money in
the long run.
""'
-
--
-
... Prep~red by~{:*?;~~~~---, -
.,.,
..
--
-
-
-
-
-
-
-
-
-
-
"'?--c-
-
-
......
-
-
-
-
-
-~
NOTES OF MEETING
DATE: April 10, 1981 PROJECT NUMBER: AAI-218
LOCATION: University of Alaska, Arctic Enviromental Information and Data
Center, 707 A Street, Anchorage, Alaska 99501 (907) 279 -4523
ATTENDEES: William J. Wilson, Fisheries Biologist AEIDC; Kevin Young, Acres;
J. 0. Barnes and R. J. Krogseng, TES.
SUMMARY OF DISCUSSION:
Mr. Barnes gave a short presentation covering the history of the Susitna
Project and the role Acres and TES have in the present study being con-
ducted for the Alaska Power Authority.
Mr. Wilson was the project Leader for the Terror Lake project on Kodiak Is-
land, and he discussed his experience in filing the FERC license application.
Mr. Wilson was concerned about the slow start by ADF&G on the fisheries study.
He felt that FERC's irmnediate reaction will probably be to reject the application
and_ask for more information. He also felt that organizations like nsusitna
Now .. should be aware of this and be expecting the request for more information.
Mr. Wilson feels that some of the fishery' study tasks will requ~re alot of
work, because some drainages in the Susitna basin do not have very much that
is known about them •
Mr. Wilson also commented that the instream flow studies may be a problem,
because there is not much expertise available capable of doing the studies.
On the Terror Lake Project Mr. Wilson said that they used joint participation
where USGS, F&WS and AEIDC crew members walked the streams together to pick
out the study sites, because you can't pick them off from a map. Mr. Wilson
feels that you have to know what the project is going to do to the stream
flows and that incremental instream flow studies will give you that flexi-
bility.
Mr. Wilson commented that FERC would like to see an agreement between State
and FeDeral agencies over policies and requirements.
c.
_)
As a member of the Susitna Hydroelectric Project Steering Committee, Mr.
Wilson is concerned about the lack of information on what is going on.
He felt that it took too long to hear back on the Steering Committee•s
comments on the procedure manuals, and that Acres should have responded
sooner. Mr. Wilson also felt that the Steering Committee .should have seen
the access road report earlier. He feels that preliminary information
should be made available to the Steering Committee qS soon as possible.
Mr. Wilson feels that Acres should publish more data in a "this is what we
found .. format and not just "this is what we conclude".
....
...,
..t
-
.,.
...
Mr. Wilson feels that the Steering Committee should be a competent and helpful • . .
sounding board for the project. He feels that the Steering Committee can help
save steps by pointing out pitfalls and other regulation mandates that need .-
to be complied with as part of their advisory capacity. The Steering Committee.
cannot play a part in policy decisions, but they can give feedback on what
was discussed to both sides.
As part of a University of Alaska policy, Mr. Wilson would like to see more
knowledge made available to the public. He would also like to see a centra-
lized depository or library of information on the project that would make
available the procedures manuals, maps, _photos, charts, diagrams, and reports
from the project.
--..
..
Mr. Wilson is also interested in seeing an informal Steering Committee meeting •
at Acres to provide an opportunity to open a dialogue with the Acres engineers.
l1lfl(i
-
Prepared by JC.. "7 ,_
R.J.O'Kro _
...
-
-
-
-
-~
-
NOTES OF MEETING
DATE: April 10, 1981 PROJECT NUMBER: AAI 218
LOCATION: Alaska Division of Natural Resources, 323 East 4th Avenue, Anchorage
ATTENDEES: Al Carson, Deputy Director, Division of Research and Development,
DNR; Kevin Young, Acres; J.O. Barnes and R.J. Krogseng, TES
SUMMARY OF DISCUSSION:
Mr. Barnes summarized the ideas and concerns that had been expressed during
the series of meetings with the various agencies.
The primary request from those who were also m~mbers of the Steering Committee
was the request to get information to the Steering Committee in time for them
-~ to review it before the meeting.
-
-
-
-
' -
-
Also high on the list was the desire for a central depository at the library
where all of the information would be available to more people.
Not everyone was knowledgeable about access roads; more information has to be
distributed to get people up to speed. It should also be understood that some
areas are incremental, that some minor impacts may work together to cause a
major impact. It is also felt that it is important to send out the criteria
on objectives that are to be used in making decisions to the Steering Committee
members and ask for their comments on the fitness of the criteria.
It is also important to get the ground rules set up before a dispute has started
in order to avoid tunnel vision or having people argue about different parts of
a question.
There is still some confusion on how the FERC process works. It also appears
necessary to get docketed or to put in a preliminary license application which
will also authorize the Fish and Wildlife service to become involved in the
study.
Mr. ~arson said he would be willing to help reinforce any concerns such as
engineering disputes that may arise.
c
..
Mr. Carson commented that he liked his meeting with APA~ Acres and TES. He
felt that it was open and not defensive. He also said that he is willing to
start having Steering Committee meetings for discussion of problems, instead
of fighting over problems.
Mr. Carson would like to see a copy of the Acres and TES monthly progress
reports sent to the Steering Committee because it provides an overview of
what is happening.
Mr. Carson said the Steering Committee would like to know the decision making
-..
-
-
...
time lines. They also would like to know when studies and reports come in. •
Mr. Carson said that a criti~al need which he feels needs attention is the
need for an understanding of technical, engineering, and socio-economic in-
formation, fe.d together in a holistic. approach to the whole problem. He
said that we need to inter-mesh ideas before people such as engineers have a
vested interest in their design.
Mr. Young explained how he works closely with the design engineers to bring
~nvironmental and social concerns into the design at an early stage to try
to avoid future problems.
Mr. Carson commented on the need to get input from the Steering Committee
members before certain design milestones are reached.
...
-
-
-
-..
Mr. Carson said he would like to see EIS seeping procedures and activities used ..
in solving some of the problems. _,
Another suggestion Mr. Carson made was for Acres and TES to touch base with
the Steering· Committee with a conceptual type outline. To ask the Steering -
Committee members "do you think this wilJ do it?11 "will it achieve our
purpose?.. He feels it is important to make sure you are using the right process -
before you go out and do all the work.
Mr. Carson also commented that enlightened engineers are better to work with
than biologists.
-
-
---
-•· ;~::•=,·¥; *' -... ! : ·-m· ~ -.. ... o-c ----s
-
;
-
-
-
_::-
r •
j
April 9 , 1981
P5700.11.88
T.813
§~:::;;~· Ronald Corso, Director 8 ;~ fvision of Hydroelectric Project Licensing
....... ederal Energy Regulatory Corm~ission vv , tj2S North Capitol St., Hail Stop 208 RB
( r~_k, ·Iashington, DC 20426
p;..,..:-:..-:-.-:-~ar Mr. Corso: Sus1tna Hydroelectric Project
FERC License AE£licat1on .
~ " . . ~he purpose of this 1 etter 1 s to conf1 nn the arrangements and agenda for
4rHusTeAo he Susitna project meeting set for 9:00a.m., Tuesday, April 21, 1981, +~-··-t the FERC office. This date and time were established by Mr. Carrier
· -f your staff and Mr. Hoover of Acres, in coordination with other Susitna
tudy team members and the Alaska Power Authority. The purpose of this
t-t--=:-:-:-::-::----i., ... eting is to bring the FERC staff up to date on study progress suring
~~~::=:lthe year since our last meeting, discuss project development selection,
n-~ nd address several issues of licensing concern.
.....
-
-
-
-
I pur proposed fonnat for the meeting is to provide initially about a
..: r I ~me-hour presentation for FERC staff's benefit. This presentation will
robably consist of a 30 minute slide display to update FERC staff with
the Plan of Study progress to date. followed by a 30 minute review of
highlights of activities in 1980 in regard to Susitna Basin development
selection, environmental studies and other relevant issues. We hope to
provide appropriate hand-outs prior to the latter review. Following
this presentation we can answer any staff questions or elaborate on any
specific topics. Finally, we would like to discuss several areas of
specific concern including:
-The politive and negative aspects of licensing each Susitna project
component separately versus a single application
-The expected form and timing of the new requlations for major
unconstructed projects and impacts on the Susitna application
-The extent of inclusion of transmission lines in the project application
.
c
Mr. Ronald Corso
Bederal Energy REgulatory Commission
April 9, 1981
Page 2
-Specific data requirements for support of license application (e.g. access
roads, camp facilities, topographic maps, etc.).
-The sufficiency of the prelicensing study coordination to date.
We expect to have representation of three to four members of the Acres
study team and one or two representatives of the Authority. It would
be appreciated if you could arrange for appropriate members of the FERC
staff to attend. We understand that the meeting ~11 be in the Hydro-
power licensing Division Offices at 400 First Street.
Should you have any comments or questions regarding the meeting or agenda,
please do not hesitate to call.
S1ncerel,Y,
.A/ ~~ Pr·1H/1s/1jr John D. Lawrence
_ _ Project Manager
cc: --Mr. Paul Carrier, FERC ,
) above address) \, \ L ..---Mr. Eric P. Yould. APA _ --\ \6\~ l
I
""
,.,;
-..
~
J
J
J
j
J
J
,
J
-
...
-
-
-
-
-
-
-
1/ry
/
• Ronald Corso, Oirecaor
Apr11 16, 1981
P5700.11.88
T.830
deral Energy Regulatory Commission
0 1st Street, N.H.
sh1ngton, D. C. 20427
ar Mr. Corso: Susitna Hydroelectric Project
Info~ation Package
have pleasure in fon~arding herewith 3 copies of an information
ckage for perusal by your staff for our meeting April 21.
look fon~ard to an interesting and productive meeting.
JOL/jmh
Attachment
Sincerely,
~ Lattrence
Project r~anager
(
~u~u~ ®W ~~~~~~
DEPARTMENT OF NATURAL RESOURCES
DIV/Siav OF FOREST, UWD AND WATER MANAGEMENT
September 24, 1981
John D. Lawrence
Project Manager
Susitna Hydroelectric Project
Acres American Incorporated
900 tiberty Bank Bldg.
Main & Court Streets
Buffalo, New York 14202
Dear Mr. Lawrence:
Ct:JVEO SEP 2 3 '981
JAY .t HAMMOND, GOYIRNOR
323 E. 4TH A VENUE
ANCHORAGE. ALASKA 99501
PHONE: (907} 279-5577
ALASKA POWER
AUT<lOP.ITY
SUSITNA
--~-~--1
FlU: P57CO
In response to your request for Water Rights Research for Susi.tna River
Basin, my staff has completed an extensive search of our computer files
of water rights filed in that area. Attached is a township list of the
areas searched. A complete listing as of September 21, 1981 is also
attached. Computer files are updated monthly, and this search used
. ;: ,-·~,'
SEQ.LSNCE IW. ,~-1/ )[
~I' I • • 7:! ~ i s ...J n · c: c::: cr: ~' ~ \ ~ : ~' :J ' =
-•-'----1--· -'---~---·_r;;·: ; . ·_: ~-·/ -__ ' __ _\
a file which was last updated on September 10, 1981. More complete
information on any of these files is available at our Southcentral
District Office located at 323 East Fourth Avenue, Anchorage, Alaska,
phone (907) 279-5577. We are glad to be of asssitance in this matter.
Sincerely,
THEODORE G. SMITH, Director
)JJ_L~ fl ~£~~~-
! ; . : :. '1 ' i-'~ F ---\ -~· ;j BY: DEAN N. BROWN, Chief
i-'f:-~:-··_ -~.-~~ Water Management Se t ·
! · Cf'"(_> {Cf';; C lOn ,-,-.· .--·\ __ _
! ; ; ·' ·. ' i-i-I. PG cT --·
t\ ·=:-;.·.!.~F~-=·
' ' -. \ -·--1· -·-! I ~-' I
' ! J.J • ·-'. _,_;. --1-! : \~ ;:: '·/ I !
-:-.. ' ;:-_-·, --
1 • p ;~ :_. I -'--c_; --~L._Jl_~ ;__ . J : ; ~--\ I~' t"L ' I ' _J/.' J -~~-'~--~~~-i ~~-0
-~-v. . --
: F;!...;. ; I
/
..
...
...
...
j
j
1
J
J
J
1
.J ,
.J
-
...
..
-
-
-
...
-
-WATER RIGHTS RESEARCH FOR SUSITNA RIVER BASIN
TOWNSHIP LIST
For each river named, numbers in first column indicate township north,
and numbers in the second column indicate range west, of the Seward
..... meridian, unless otherwise noted .
Susitna Fish Creek Montana Kroto-TraEeer
14 7,8 17 5 24 4 20 6 -15 7,8 18 5 25 2,3,4 21 6
16 6,7
17 6,7 Alexander Skwentna Yentna
18 6 17 8 17 18 18 7
19 5,6 18 8 18 18 20 8
. 20 5 19 8,9 19 19,20 21 8-10
..... 21 4,5 20 19 22 12
22 4,5 Wi 11 ow 21 11-15,19 23 11,12
23 4,5 20 2,3 22 10,11,14-24 12 '13
24 5 19 1,2,4 18 25 13,14 -25 5 26 14 ( 26 5 Kashwitna ~ 27 14,15 ' I 27 5 22 1,2,3,1E 3 18,19 28 14 .... 28 4,5 24 19,20
29 4,5 Sheep Talkeetna
30 3,4 23 3 Little Willow 26 1,2,3,4 .._ 31 2,3 24 2,3 20 4 27 1,2,3,1E
21 3
-Kahi 1 tna Chulitna Tokositna Chulina
22 8 30 5,6 . 29 6 27 4
23 8,9 31 4,5 28 6,7
24 9 32 3,4 ..... 25 9,10 33 2,3
26 10 22S llW F
27 10 21S 10, llW F
28 10 20S lOW F
-
-
-
(
RECEIVED
NOV 13 1981
ACRES AMffilCiiN JUCORrORA TED
ITINERARY FOR TES AGENCY
CONTACT MEETINGS (Seco nd Series)
Tuesday, 13 October, i981
0900 Division of Natural Resou r ces, Lan ds -Ted Smith~ Minerals-
Glenn Harrison
1030 Department of Community and Regio nal Affairs; Ed Busch, Lamar
Cotten
1330 Department of Transportation; Jay Bergstrand
1500 National Park Service; Terry Carlstrom, Carl Stoddard
Wednesday, 14 October, 1981
0900 State Parks; J ack Wiles, Doug Reger and others
1030 Corps of Engineers; L/C Perki ns
AUSKA POWC:il
AUTHOiliT Y
S U S iTN A
FILE P570Q
. 11 .3<:>
1330 DPS, Fish & Wildlife Protection; Col. Stickles and others ~· SEQlJ£,1JC ::: ~;o . F d-/t'(;
I I I 1500 U.S. Fish and Wildlife Service; Keith Baya, Mel Munson andli ·athe(ls ·-:..: -~
Thursday, 15 October, 1981
0900 Bureau of Land Management; Bob Ward, John Rego and othe rs
1030 Alaska Department of Fish and Game; Carl Yanagawa
1330 NOAA, Marine Fis heries; Ron Morris, Brad Smith
1500 U.S. Department of Energy; Fred Chiei
Friday, 16 Octob er, 1981
., 0 ·::: <: •
~ ~ = ~ ~ ~ ..:
-I
·' I .... j c~c-I p -~
l_l_ £"--!
I c; '!I ~--· -, !" .: ' .• -I
0900
1030
1330
1600
I ".i ~~
Arctic Environmental Information and Data Cente r; Bill Wils~--·
Alaska D t t E . t 1 C t · B b M t . 1=~~-.u].'/_ ~epar men nv1ronmen a onserva 1on; o ar 1n _!~,)\~ _
Div ision of Natural Resources; Al Carso n I · =~=~=-Mat-Su Borough Planning Department; Rodn ey Schulling l _j ~·
--, ~I L :: j -
RECEIV~~D
NOV 13 1981
ACRES AMERJ£Afi lf~CORPOilATED
ITINERARY FOR TES AGENCY
CONTACT MEETINGS {Second Series)
Tuesday, 13 October, 1981
0900 Division of Natural Resources, Lands-Ted Smith; MineraJs-
Glenn Harrison
1030 Department of Corrrnunity and Regional Affairs; Ed Busch, Lamar
Cotten
1330 Department of Transportation; Jay Bergstrand.
1500 National Park Service; Terry Carlstrom, Carl Stoddard
-·-----Wednesday, 14 October, 1981 ALASKA POWER
AUTHORITY
0900 State Parks; Jack Wiles, Doug Reger and others SUSlTNA
FILE P5700
1030 Corps of Engineers; L/C Perkins . I I. 30
1330 DPS, Fish & Wildlife Protection; Col. Stickles and others, I SEQUS!'lC~ NO. . ;::; r:J-/C'~
t I .
1500 U.S. Fish and Wildlife Service; Keith Baya, Mel Munson andl~i~th~s! ,
'i n · c: ~ ;:: ~ < :-: $? ;:: t ~
. t.' =: ~ • -= < !.:' ,;:... = Thursday, 15 October, 1981 ·-· ·--.. ~-· -··
0900
1030
1330
1500
.
~--·-· Bureau of Land Management; Bob Ward, John Rego and others ' : ~ --...,_: -.. --
~. ·~ i ' . ·---~ i -l/"t! l h --• ·A~... , -·-:'ll,l ~----·. --·-· ...... '"--l
~
Alaska Department of·Fish and Game; Carl Yanagawa
NOAA, Marine Fisheries; Ron Morriss Brad Smith !. ,'") ' •
,--~·-• t n < -:;-.-~ --·
• ' * • ;
~-j-, E :·! .--! --·-
1-:-; <! ·i r -. --
t • -
U.S,. Department of Energy; Fred Chiei
Friday, 16 October, 1981 ~'"-"-1 .-..... , .~~~· -. -
it :r·.''-'
0900
1030
1330
1600
,..._,_ --l ! ' :.1 ~~ '. l .
Arctic Environmental Information and Data Center; Bill Wilslfl]-.. ::..--· t-·-. ,· ~ ·~. ---
Alaska Department Environmental Conservation; Bob Martin }-~~·~~y_ _: l vi"" I )1 •'\1 ., ' I \-<-·::" I Division of Natural Resources; Al Carson
Mat-Su Borough Planning Department; Rodney Schulling
1
-j-; . : ---:1
_! -t'::?./ t_J
J ~!LE I