HomeMy WebLinkAboutAPA501ALASKA STATE DOC
CHAKACHAMNA HYDROELECTRIC PROJECT
INTERIM FE .ASIBILITY ASSESSMENT REPORT
VOLUME I
SECTIONS 1-10 1
APPENDIXES TO SECTI S 4.0 & 8.0 .
I
BECHTEL CIVIL & MINERALS INC .
ENGINEERS -CONSTRUCTORS
MARCH 1983
:'
; .
'
=-----ALASKA POWER AUTHORITY _ ___J
[
l
L
r
[
r
c
u
c
[
c
lZ
~
~
[ ......
0
[
N c.o co
0
0
0 u 0
LO
LO ......
M
(Y)
Mr~H~fl\u£, ALII SKA ~~A.R.L.l.~
ALASK .. <\ h SO&R t9M~ r tt.a.ny
U.S. DEPT. u:rr -:r:NTITIRlOR
CHAKACHAMNA HYDROELECTRIC PROJECT
INTERIM FEASIBILITY ASSESSMENT REPORT
VOLUME I
SECTIONS 1-10
APPENDIXES TO SECTIONS 4.0 & 8.0
BECHTEL CIVIL & MINERALS INC.
ENGINEERS-CONSTRUCTORS
MARCH 1983
~-ALASKA POWER AUTHORITY _-----J
1 92'~
v. I
(
L
ALASKA POWER AUTHORITY
ANCHORAGE, ALASKA
CHAKACHAMNA HYDROELECTRIC PROJECT
INTERIM FEASIBILITY ASSESSMENT REPORT
MARCH 1983
VOLUME I
TABLE OF CONTENTS
Section
1.0 INTRODUCTION
2.0 SUMMARY
3. 0
2.1 Project Layout Studies
2.2 Geological Studies
2.3 Environmental Studies
2. 3 .1
2.3.2
2. 3. 3
2. 3. 4
Hydrology
Aquatic Biology
Terrestrial Biology
Human Resources
2.4 Economic Evaluation
2.5 Technical Evaluation and Discussion
2.5.1
2. 5. 2
2.5.3
2. 5. 4
Chakachatna Dam Alternative
McArthur Tunnel, Alternatives A & B
Chakachatna Tunnel, Alternatives C &
Alternative E
PROJECT DEVELOPMENT STUDIES
3.1
3.2
3.3
3.4
3.5
Regulatory storage
Chakachatna Dam
McArthur Tunnel Development
3. 3 .1
3. 3. 2
Alternative A
Alternative B
Chakachatna Tunnel Development
3. 4 .1
3.4.2
Alternative C
Alternative D
McArthur Development-Recommended Alternative E
3.5.1
3.5.2
General
Water Releases and Fish Passage
Facilities
i
Page
1-1
2-1
2-1
2-3
2-5
2-5
2-6
2-7
2..:8
2-10
2-11
2-11
2-11
D 2-13
2-14
3-1
3-1
3-2
3-4
3-4
3-18
3-19
·3-19
3-25
3-26
3-26
3-28
Section
3.5 McArthur Development-Recommended Alternative
(cont'd)
3. 50 3
3.5.4
3.5.5
3.5.6
Upstream Migrants Facility
Downstream Migrants Facility
Conveyance Channel
Outlet Structure
3.6 Transmission Line and Submarine Cable
3.7 References
4.0 HYDROLOGICAL AND POWER STUDIES
4.1 Introduction
4.2 Historical Data
4.3 Derived Lake Inflows
4.4 Synthesis of Long-Term Lake Inflows
4.5 Power Studies
4.6 Results
4.7 Variations in Lake Water Level
5.0 GEOLOGIC INVESTIGATIONS
5.1 scope of Geologic Investigations
5 .1.1 Technical Tasks
5 .1. 2
5.1.1.1
5.1.1.2
5.1.1.3
5.1.1.4
5.1.1.5 •
Schedule
5.1.2.1
5.1.2.2
5.1.2.3
5.1.2.4
5.1.2.5
5.2 Quaternary Geology
Quaternary Geology
Seismic Geology
Tunnel Alignment and Power
Plant Site Geology
Construction Materials
Geology
Road and Transmission
Line Geology
Quaternary Geology
Seismic Geology
Tunnel Alignment and Power
Plant Site Geology
Construction Materials
Geology
Road and Transmission
Line Geology
ii
E
~-
I
I
t
Page
(--·
i
\__
r' -
3-31 I
3-32 l
3-39
3-39 r '
\
I
l_
3-43
3-44 I -
l
4-1 [~ 4-1
4-2
4-3 l " 4-4
4-16
4-19 L 4-23 L
5-1
5-l [
5-l r~ 5-2
5-4 r
5-6 L
5-6 r 5-7 . "
5-7 L
5-7
5-8 L
5-8
5-9
r -
L
5-9
5-9 [
r ~
L
I
I
f'
r-
L
f t:
-
t
1
t
l
[
section
5.2.1
5.2.2
5.2.3
Glaciers and Glacial Geology
5.2.1.1
5.2.1.2
5.2.1.3
5.2.1.4
5.2.1.5
5.2.1.6
Regional Glacial Geologic
History
Project Area Glacial
Geologic History
Barrier Glacier
Blockade Glacier
Other Glaciers
Implications with Respect to
Proposed Hydroelectric
Project
Mt. Spurr Volcano
5.2.2.1
5.2.2.2
5.2.2.3
Alaska Peninsula-Aleutian
Island Volcanic Arc
Mt. Spurr
Implications with Respect to
Proposed Hydroelectric
Project
Slope Conditions
5.2.3.1
5.2.3.2
5.2.3.3
5.2.3.4
Chakachamna Lake Area
Chakachatna River Valley
McArthur River Canyon
Implications with Respect to
Proposed Hydroelectric
Project
5.3 seismic Geology
5.3.1
5. 3. 2
5.3.3
Tectonic settiny
Historic seismicity
5.3.2.1
5.3.2.2
Regional Seismicity
Historic Seismicity of the
Project study Area
Fault Investigation
5.3.3.1
5.3.3.2
5.3.3.3
5.3.3.4
Approach
Work to Date
Candidate Significant
Features
Implications with Respect to
Proposed· Hydroelectric
Project
iii
Page
5-10
5-10
5-14
5-20
5-30
5-36
5-39
5:...40
5-40
5-42
5-49
5-51
5-51
5-52
5-54
5-55
5-56
5-56
5-60
5-60
5-61
5-73
5-73
5-74
5-81
5-94
Section
5.4 References
6.0 ENVIRONMENTAL STUDIES-SUMHARY
7.0
6.1 Environmental Studies -1981
6.2
6 .1.1
6 .1.2
6 .1. 3
6 .1.4
Environmental Hydrology
Aquatic Biology
Terrestrial Vegetation
Human Resources
and Wildlife
Environmental Studies -1982
6. 2 .1
6.2.2
Environmental Hydrology -1982
Aquatic Biology
6.2.2.1
6.2.2.2
6.2.2.3
6.2.2.4
6.2.2.5
6.2.2.6
6.2.2.7
Sockeye Salmon
·chinook Salmon
Pink Salmon
Chum Salmon
Coho Salmon
Dolly Varderi
Rainbow Trout
EVALUATION OF ALTERNATIVES
7.1
7.2
7.3
Engineering Evaluation
7 .1.1 General
7 .1. 2 Chakachatna Dam
7 .1. 3 Alternative A
7 .1.4 Alternative B
7 .1. 5 Alternatives C and D
7.1.() Alternative E
Geological Evaluation
7.2.1 Chakachatna Dam
7. 2. 2 Alternative A
7.2.3 Alternative B
7.2.4 Alternatives c and D
7.2.5 Alternative E
Environmental Evaluation
7.3.1
7. 3 0 2
7.3.3
7.3.4
Chakachatna Dam Alternative
McArthur Tunnel Alternatives A and
Chakachatna Tunnel Alternatives
C and D
Recommended McArthur Tunnel
Alternative E
iv
B
Page
5-95
6-1
6-1
6-1
6-3
6-6
6-8
6-10
6-10
6-11
6-13
6-15
6-21
6-22
6-22
6-24
6-24
7-1
7-1
7-1
7-2
7-2
7-4
7-6
7-7
7-8
7-9
7-:-11
7-11
7-12
7-14
7-14
7-15
7-20
7-23
l :
[ I
[
•.
I
t
i l
\
1 •
[
L
[
t
[
[
L
L
t
Section
7.3.4.1
7.3.4.2
7.3.4.3
Potential Effects on
Aquatic Biota 7-23
7.3.4.1.1 Construction of
the Chakachamna
Hydroelectric
Project and
Related Facilities 7-24
7.3.4.1.2 Operation of the
Chakachamna Hydro-
electric Project
and Related
Facilities 7-32
7.3.4.1.3 summary of
Potential Effects 7-52
Potential E£fects on
Botanical Resources 7-55
7.3.4.2.1 Direct Habitat
Loss 7-55
7.3.4.2.2 Indirect Habitat
Alteration 7-56
7.3.4.2.3 summary of
Potential Effects 7-58
Potential Effects on Wildlife
Resources and Habitats 7-59
7.3.4.3.1 Direct Habitat
Loss 7-61
7.3.4.3.2 Indirect Habitat
Alteration 7-61
7.3.4.3.3 summary of
Potential Effects 7-65
7.4 Project Risk Evaluation 7-68
7.4.1
7.4.2
7.4.3
7.4.4
7.4.5
7.4.6
7.4.7
7. 4. 8
Lake Tapping
Tunnel Alignment Rock Conditions
Underground Powerhouse Site
Barrier Glacier
Blockade Glacier
McArthur Glacier
Mt. Spurr Volcano
Seismic Risk
v
7-68
7-69
7-71
7-71
7-73
7-74
7-74
7-78
Section
7.4.9
7.4.8.1
7.4.8.2
Lake Clark-Castle Mountain
Fault
Bruin Bay Fault
Faults in Chakachatna Valley
7.5 References
8.0 CONSTRUCTION COSTS AND SCHEDULES
8.1 Estimates of Cost
8 .1.1
8.1.2
8.1.3
8 .1. 4
8.1.5
8 .1. 6
Power Tunnel
Underground Powerhouse and Associated
Structures
Tailrace Channel
Switchyard
Transmission Line and Cable
Crossing
Site Access and Development
8.2 Exclusions from Estimates
8.3 Construction schedules
9.0 ECONOMIC EVALUATION
9.1 General
9.2 Parameters for Economic Evaluation
9.3 Cost of Power from Alternative Sources
9.3.1
9.3.2
9.3.3
9.3.4
General
Constructiou Cost
Operation and Maintenance Cost
Fuel Cost .
9.4 Value of Hydro Generation
9.5 Economic Tunnel Sizing
9.6 Economic Tunnel Length
10.0 COORDINATION
10.1 Introduction
10.2 Human Resources
10.2.1
10.2.2
Meeting, December 10, 1981
Response
10.3 Biological Studies
10.3.1 Meeting, December 11, 1981
10.3.1.1 Response
vi
r~
l~
Page
[
7-78
7-79 l~
7-80
7-80 l '
8-1
8-1 ['
8-6
r-· 8-9
8-10
8-11 [
8-11
8-11 L 8-16
8-16
9-1 [~
9-1 [ 9-2
9-2
9-2 r~
9-3 L
9-4
9-4 [
9-6
9-12 L 9-15
10-1
10-1 L
10-1
10-1
r ,,
10-4 L
10-4 L
10-4
10-10 L
[
[
L
L
[
L
L
t
section
10.3.2
10.3.3
Correspondence
U.S. Fish·and Wildlife Service
APA Response
Alaska Department of Fish and Game
APA Response
National Marine Fisheries service
APA Response
Meeting, December 9, 1982
Response by National Marine
Fisheries Service
Response by u.s. Fish and Wildlife
Service
10.4 National Park Service
10.4.1 Lake Clark National Park
10.5 Northern Alaska Environmental Center
10.5.1 Correspondence
10.5.1.1 Response
APPENDIXES
Appendix to section 4.0
Appendix to S~ction 8.0
vii
10-10
10-21
10-23
10-34
10-35
10-38
10-39
10-49
10-51
10-54
10-54
10-58
10-58
10-58
Table
2.1
4.1
4.2
4.3
4.4
4.5
4.6
6.1
6.2
6.3
7.1
7.2
7.3
7.4
VOLUME I
LIST OF TABLES
Project Data, Alternative E
Lake Chakachamna Inflows
Inflows to the Lake in CFS
Monthly Peak Power Demands Used in
Power Studies
Provisional Minimum Releases for Instream
Flow in Chakachatna River Downstream· from
Chakachamna Lake Outlet for Use in
Power Studies
Power Plant System Constraints for
Alternative Project Developments
Power Studies Summary
Species List and Drainage of Occurrence
August-September 1981
Species Composition and Relative Abundance
of Mammals Identified Withiri the Study Area
for Each of the Habitat Types
summary of Estimated Salmon Escapement by
Waterbody and Drainage for 1982
Cost of Energy
Natural and Alternative B Regulated Mean
Monthly and Mean Annual Flow at the
Chakachamna Lake Outlet
Natural and Alternative D Regulated Mean
Monthly and Mean Annual Flows at the
Chakachamna Lake Outlet
Natural and Alternative E Regulated Mean
Monthly and Mean Annual Flow at the
Chakachamna Lake Outlet
viii
Page
2-16
4-11
4-15
4-17
. 4-18
4-20
4-21
6-4
6-7
6-14
7-3
7-18
7-22
7-40
[
f-
L
[
L
L
[
r-
L
L
[
L
[
[
[
L
L
L
L
t
Table
7.5
7.6
9.1
9.2
9.3
Estimated Escapement of Important Fish Species
in the Chakachatna River System by Waterbody
classified by Potential Effects of Decreased
Flow of Water from Chakachamna Lake
Estimated Escapement of Important Fish Species
in the McArthur River System by vvaterbody
classified by Potential of Increased Flow
of water
New Contract Gas Price (AML&P)-Anchorage
Coal Fired Plant, Cost of Generating Power
at 50% Load Factor
Sheet 1 of 2
Sheet 2 of 2
Combined Cycle Plant, Cost of Generating Power
at 50% Load Factor
Sheet 1 of 2
Sheet 2 of 2
ix
7-43
7-49
9-5
9-8
9-9
9-10
9-ll
r·
i
L
r·
L
[
L
L
L
L
Figure No.
1-1
3-1
3-2.
3-3
3-4
3-5
3-6
3-7
3-8
3-9
3-10
3-11
3-12
3-13
4-1
4-2
4-3
4-4
4-5
5-1
VOLUME I
LIST OF FIGURES
Title
Location Map
McArthur Tunnel, Alternative A-1
McArthur Tunnel, Alternatives A-2 & E
Chakachatna Tunnel, Alternatives C & D
Gate Shaft Section, Sheet 1
Gate Shaft Sections, Sheet 2
McArthur Power Development, General Arrangement
Chakachatna Power Development, General
Arrangement
Chakachamna Lake Outlet, General Arrangement
Upstream Fish Passage Facilities, Plans and
Section
Upstream Fish Passage Facilities, Sections
Downstream Fish Passage Facilities, Instream
Release Structure
Outlet Fish Passage Facilities, Plan and
Sections
Transmission Line, Route Location
Hydrometeorological Station Locations
Hydrometeorological Stations, Periods of Record
Chakachamna Lake, Stage -Area and Storage
Alternatives A and B -Lake Level Variations
Alternatives C and D -Lake Level Variations
Quaternary Geology Site Locations
X
L Figure
~ 5-2a
r 5-2b
L 5-3
5-4
r ~ 5-5
L 5-6
[ 5-7
[
5-8
[ 5-9
c 8-1
8-2
E 8-3
[ 8-4
9-1
L 9-2
[~ 9-3
[
L
r ' L
-
No. Title
Glacial and Volcanic Features in the
Chakachamna -Chakachatna Valley
Glacial and Volcanic Features in the
Chakachamna -Chakachatna Valley
Plate Tectonic Map
Major Earthquakes and Seismic Gaps in Southern
Alaska
Historic Earthquakes of all Focal Depths in
the Site Region from 1929 through 1980
Historic Earthsuakes of Focal Depth Greater
than 20 Miles in the Site Region from 1929
through 1980
Historic Earthquakes of Focal Depth Less than
20 Miles in the Site Region from 1929 through
1980
Seismic Geology Investigation Sequence
Map Showing Locations of Candidate Significant
Features in the Project Study Area
Access Roads
Project Schedule, Alternatives A and B
Project Schedule, Alternatives C and D
Project Schedule, Alternative E
Economic Tunnel Diameter
McArthur Tunnel Economic Length
Chakachatna Tunnel Economic Length
xi
INTRODUCTION
r
f"
r
[
L
r~
l '
[
L~
r,
L
[
r 3
~
[
L
6
[
l-
r
I
I
L
1.0
ALASKA POWER AUTHORITY
ANCHORAGE ALASKA
CHAKACHAMNA HYDROELECTRIC PROJECT
INTERIM FEASIBILITY ASSESSMENT REPORT, MARCH, 1983
INTRODUCTION
This report has been prepared in accordance with the
terms of Contract 82-0294 dated August 3, 1981 between
the State of Alaska/Department of Commerce and Economic
Development/Alaska Power Authority and Bechtel Civil &
Minerals, Inc. in connection with services for performing
interim feasibility assessment studies of the Chakachamna
Hydroelectric Project. As its title indicates, the
report is of an interim nature. It is based upon
previously published information regarding the project,
and on data acquired and derived during a study period
extending from the fall of 1981 to December 1982. Its
objectives are to summarize the information derived from
the studies, to provide a preliminary evaluation of
alternative ways _of developing the power potential of the
project, to define that power potential, and to report on
the estimated cost of construction, and to provide a
preliminary assessment of the effects that the project
would have on the environment.
The initial engineering, geological, and environmental
studies were conducted during the fall of 1981, and the
findings of these studies were summarized in an interim
report dated November 30, 1981. Although the data
1-1
collected and study period up to that time were rather
limited by the short time base, some rather clear
indications emerged as to the manner in which it was
considered that development of the project should proceed.
One aspect that became evident was that a much more
extensive and populous fishery uses the waters in the
project area than had been earlier realized or
anticipated. This led to an amendment of the above
mentioned contract in which the requirements for
completion of the feasibility report and application to
the Federal Energy Regulatory Commission for a license to
construct the project were deleted from the scope of
work. Continuing studies of the fishery in the waters of
the project area were authorized as were the development
of conceptual designs for fish passage facilities at the
outlet of Chakachamna Lake plus the preparation of
estimates of their construction costs and those of the
McArthur tunnel assuming that it could be excavated by
tunnel boring machine.
As may be seen by reference to Figure 1-1, Chakachamna
Lake lies in the southern part of the Alaska Range of
mountains about 85 miles due west of Anchorage. Its
water surface lies at about elevation 1140 feet above
mean sea level.
The project has been studied and reported upon several
times in the past. The power potential had been
estimated variously from about 100,000 kw to 200,000 kw
firm capacity, depending on the degree of regulation of
the outflow from Chakachamna Lake and the hydraulic head
that could be developed.
1-2
r ,
I -
r-
L_
[
~
[
L
[
[
L
L
t I
L
L
[
l
L
Two basic alternatives can be readily identified to
harness the hydraulic head for the generation of
electrical energy. One is by a twelve mile tunnel more
or less parallel to the valley of the Chakachatna River.
This river runs out of the easterly end of the lake and
descends to about elevation 400 feet above sea level
where the river leaves the confines of the valley and
spills out onto a broad alluvial flood plain. A maximum
hydrostatic head of about 740 feet could be developed via
this alternative.
The other alternative is for development by diversion of
the lake outflow through a ten mile tunnel to the valley
of the McArthur River which lies to the southeast of the
~ lake outlet. A maximum hydrostatic head of about 960
feet could be harnessed by this diversion. Various means
of development by these two basic alternatives are
discussed in the report on the basis of the present
knowledge of the site conditions.
The 1982 environmental studies confirmed the importance
of the fishery using waters in the project area and
expanded the data base concerning it. The basic elements
of the recommended mode of development were conceived,
these being for development via the McArthur River with a
concrete lined machine bored tunnel and with fish passage
facilities that would permit fish to ascend into the lake
or to travel downstream from the lake into the
Chakachatna River. Three samples of rock collected from
the surface, two from the general vicinity of the
proposed power intake site at Chakachamna Lake and one
from near the powerhouse site by the McArthur River, were
tested in The Robbins Company laboratory at Kent,
Washington. The results indicated that the rock sampled,
1-3
would be suitable for boring, but since the test data
from samples taken at the surface can sometimes be
misleading, and since no geological studies have yet been
performed along the planned tunnel alignment, it must be
assumed at the present time that the tunnel can be bored
and additional geological studies will be needed before
it can be firmly recommended that the tunnel be bored by
machine. The rock test data was used for guidance in
estimating the cutter penetration rate in assessing the r
estimated cost of excavating the tunnel by boring machine. ··
r ~
For the assessment of environmental factors and I .
geological conditions in the project area, Bechtel
retained the services of woodward-Clyde Consultants. (_
1-4
L
L
L
[
[
t.
l
I I~-
i
j
L
!
l
V/C/IJITY .MAP
4 0 4 B
SCALE t" = 4 MILES
IJOT/:5:
1.) TOPOGRAPHY IS FI'I.OM USGS
C(UAORA.UGLE MAPS
Z.}VERT!CAL DATUM IS MEAN LON.:R.
LOW WATER
3.) HOI'I!Zo.UTAL GR/0 IS UNIVERSAL
TRANSVERSE MERCATOR PROJECT/0~,
19Z7 NORTH AMERICAJJ DATUM
SUMMARY
l ~
l ~
l ~
i
l ~
r,
I
b
2.0 SUMMARY
2.1 Project Layout Studies
The studies evaluated the merits of developing the
power potential of the project by diversion of water
southeasterly to the M~Arthur River via a tunnel about
10 miles long, 'or easterly down the Chakachatna Valley
either by a tunnel about 12 miles long or by a dam and
tunnel development. In the Chakachatna Valley, few
sites, adverse foundation conditions, and the nearby
presence of an active volcano made it rapidly evident
that the feasibility of constructing a dam there would
be questionable. The main thrust of the initial
studies was therefore directed toward the tunnel
alternatives without consideration of raising the lake
level above the present outlet channel invert, taken
as El. 1128, and a minimum drawdown of the water level
to El. 1014.
Two alignments were studied for the McArthur Tunnel.
The first considered the shortest distance that gave
no opportunity for an additional point of access
during construction via an intermediate adit. The
second alignment was about a mile longer, but gave an
additional point of access, thus reducing the lengths
of headings and also the time required for construc-
tion of the tunnel. Cost comparisons and economic
evaluation nevertheless favored the shorter 10 mile
25 foot diameter tunnel.
The second alignment running more or less parallel to
the Chakachatna River in the right (southerly) wall of
the valley afforded two opportunities for intermediate
2-1
access adits. These, plus the upstream and downstream
portals would allow construction to proceed simulta-
neously in 6 headings and reduce the construction time
by 18 months less than that required for the McArthur
Tunnel. Economic evaluation again favored a 25 foot
diameter tunnel running all the way from the lake to
the downstream end of the Chakachatna Valley.
If all the controlled water were used for power
generation, the McArthur Powerhouse bould support 400
MW installed capacity, and produce average annual firm
energy of 1752 GWh. The effects of makiny a provi-
sional reservation of approximately 19% of the average
annual inflow to the lake for instream flow require-
ments in the Chakachatna River were found to reduce
the economic tunnel diameter to 23 feet. The in-
stalled capacity in the powerhouse would then be re-
duced to 330 MW and the average annual firm energy to
1446 GWh.
If a small rock dike were to be constructed at the
outlet of the lake and the maximum lake level is
raised to the natural maximum, El. 1155, this would
allow 72 feet lake drawdown to accommodate fish
passage facilities. If the tunnel diameter remained
23 feet to avoid excessive losses, then the installed
capacity in the powerhouse would be 330 MW and the
average annual firm energy 1301 GWh. The reduction in
firm energy is due to tl1e lesser vqlume of regulatory
storage contained within the narrower range of lake
level needed for gravity operation of the fish passage
facilities.
2-2
,-
l
[
f ,
I
l,
f
~-.
L
r '·
I I
L
i ·:
.
L
f
L
L.-=-t
G
L
t
"'-L'
L
[
2.2
For the Chakachatna Powerhouse, diversion of all the
controlled water for power generation would support an
installed capacity of 300 MW with an average annual
firm energy generation of 1314 GWh. Provisional
reservation of approximately 0.8% of the average
annual inflow to the lake for instream flow require-
ments in the Chakachatna River was regarded as having
negligible effect on the installed capacity and
average annual firm energy because that reduction is
within the accuracy of the present study.
The reasoning for the smaller instream flow releases
considered in this alternative is discussed in Section
2.5.3.
Geological Studies
At the present level of study, the Qu?rternary Geology
in the Chakachatna and McArthur Valleys has been eval-
uated and the seismic geology of the general area has
been examined though additional work remains to be
done next year. General observations as they may af-
fect the project are as follows:
The move of ice of the Barrier Glacier toward the
river may be gradually slowing. However, no material
change in the effect of the glacier on the control of
the Chakachamna Lake outlet is anticipated.
The condition of the Blockade Glacier facing the mouth
of the McArthur Canyon also appears to be much the
same as reported in the previous USGS studies.
2-3
There does not appear to be any reason to expect a
dramatic change in the state of growth or recession of
either of the above two glaciers in· the foreseeable
future.
Surface exposures on the left (northerly) side of the
Chakachatna Valley consist of a heterogeneous mix of
volcanic ejecta and glacial and fluvial sediments
which raise doubts as to the feasibility of damming
Chakachatna River by a dam located downstream of the
glacier.
The rock in the right wall of the Chakachatna Valley
is granitic, and surface exposures appear to indicate
that it would be suitable for tunnel construction if
that form of development of the project were found to
be desirable.
No rock conditions have yet been observed that would
appear to rule out the feasibility of constructing a
tunnel between the proposed locations of an intake
structure near the outlet of Chakachamna Lake and a
powerhouse site in the McArthur Valley. It must be
noted, however, that in the vicinity of the proposed
powerhouse location in the McArthur Canyon, the
surface expdsures indicate that rock quality apppears
to improve significantly with distance upstream from
the mouth of the canyon.
The Castle Mountain fault, which is a major fault
structure, falls just outside the mouth of the
McArthur Canyon and must be taken into account in the
seismic design criteria of any development of the
2-4
r
'
( '
I I
c
L
t
c
L
I l.
[_
r
r
L
[
[
lj
r .
l "
2.3
2.3.1
project whether it be via th~ McArthur or Chakachatna
Canyons. Other significant seismic sources are the
Megathrust Section of the Subduction Zone and the
Benioff Zone.
Environmental Studies
Hydrology
Field reconnaissances were conducted in Chakachamna
Lake, several of its tributary streams, the
Chakachatna and McArthur Rivers. Records of mean
daily flows were initiated in mid-August 1982 at the
site of the previously operated u.s. Geological Survey
gage site and in the Upper McArthur River downstream
from the powerhouse location. Data collected and
developed are typical of glacial rivers with low flow
in late winter and large glacier melt flows in July .
and August.
The water level in Chakachamna Lake when measured in
1981 was elevation 1142 and is typical of the
September Lake stage records in the 12 years preceding
. the major flood of August 1971. Lake bottom profiles
were surveyed at the deltas of the Nagishlamina and
Chilligan Rivers, and the Shamrock Glacier Rapids.
Reaches of the McArthur and Chakachatna Rivers vary in
configuration from mountainous through meandering and
braided. All except the most infrequent large floods
are mostly contained within the unvegetated flood
plan. Sedimentation characteristics appear to be
typically those of glacial systems with very fine
suspended sediments and substantial bed load transport.
2-5
2.3.2 Aquatic Biology
Field observations identified the following specie~ in
the waters of the project area:
Resident: Rainbow trout
Lake trout
Dolly Varden
Round Whitefish
Pygmy Whitefish
Anadromous: Chinook salmon
Chum salmon
Coho salmon
Eulachon
Longfin smelt
Artie grayling
Slimy sculpin
Ninespine stickleback
Threespine stickleback
Pink salmon
Sockeye salmon
Dolly Varden
Rainbow smelt
Bering cisco
Salmon spawning in the Chakachatna River drainage and
its tributaries occurs primarily ~n tributaries and
sloughs. A relatively small percentage of the 1982
estimated escapement was observed to occur in mainstem
or side-channel habitats of the Chakachatna River.
The largest salmon escapement in the Chakachatna
drainage was estimated to occur in the Chilligan and
Igitna Rivers upstream of Chakachamna Lake. The
escapement of those sockeye in 1982 was estimated to
be approximately 41,000 fish, or about 70 percent of
the escapement within the Chakachatna drainage.
Chakachamna Lake is the major rearing habitat for
these sockeye. It also provides habitat for lake
trout, Dolly Varden, round whitefish, and sculpins.
2-6
f .
I
f L
(
\
(
L,
L
I
\'..
J
b
L~
l_
f
·_
..
2.3.3
In the McArthur River over 96 percent of the estimated
salmon escapement occurred in tributaries during
1982. The estimated escapement of salmon of all
species was slightly greater in the McArthur than the
Chakachatna drainage. Other anadromous fish including
eulachon, Bering cisco, longfin smelt and rainbow
smelt have been found in the McArthur River.
The contribution of salmon stocks originating in these
systems to the Cook Inlet commercial catch is
presently unknown. Although some commercial and
subsistence fishing occurs, the extent to which the
stock is exploited is also not known.
Rearing habitat for juvenile anadromous and resident
fish is found throughout both rivers, although the
waters within the Chakachatna River canyon below
Chakachamna Lake and the headwaters of the McArthur
River do not appear to be important rearing habitat.
There appears to be extensive movement of fish within
and between the two drainages, and seasonal changes in
distribution have also been noted.
Terrestrial Biology
On the basis of their structural and species composi-
tions, eight types of vegetation habitats were deli-
neated. These range from dense alder thickets in the
canyons to vast areas of coastal marsh. The riparian
communities are the most prevalent varying from rivers
with emergent vegetation to those with broad flood
plains scattered with lichen, willow and alder.
2-7
2.3.4
Evaluation of wildlife communities in the project area
identified seventeen species of mammals. Moose,
coyote, grizzly bear and black bear ranges occur
throughout the area.
Birds also are abundant, fifty-six species having been
identified with the coastal marshes along Trading Bay
containing the largest diversity.
None of the species of plants, mammals and birds that
were found are listed as threatened or endangered
although in May 1981 it was proposed that the tule
whitefronted goose, which feeds and may nest in the
area, be considered for threatened or endangered
status.
Human Resources
These studies were organized into the following six
elements:
Archaeological and historical resources
Land ownership and use
Recreational resources
Socioeconomic characteristics
Transportation
Visual resources
Many contacts were made with both State and Federal
Agencies and native organizations, as well as a
limited reconnaissance of the project area.
2-8
r
r\
r.
r
). I
I
'
f
r L.
f
1
'if L'
L
r
\~
l
(-
t
[~:
[-_
[_
{-.
[
L.~
No known cultural sites have been identified and the
field reconnaissance indicates that the proposed sites
for the power intake and powerhouses have a low po-
tential for cultural sites.
Land owners in the area comprise federal, state, and
borough agencies, Native corporations and private
parties. Land use is related to resource extraction
(lumber, oil and gas), subsistence and the rural resi-
dential village of Tyonek.
Recreational activity takes place in the project area,
but with the exception of Trading Bay State Game
Refuge, little data is available as to the extent or
frequency with which the area is used.
Regional data on population, employment and income
characteristics are relatively good. Employment level
and occupational skill data are limited and need to be
developed together with information on local employ-
ment preferences.
Transportation facilities in the area are few and
small in size. There are airstrips at Tyonek and on
the shoreline at Trading Bay. A woodchip loading pier
is located near Tyonek. Several miles of logging
roads exist between Tyonek and the mouth of the
Chakachatna Valley; many of these roads and bridges
are being removed as timber activities are completed
in specific areas. The Chakachatna River was bridged
near its confluence with Straight Creek until 1982.
There is no permanent road linking the project area
with any part of the Alaska road system.
2-9
2.4
The project area's scenic characteristics and prox-
imity with BLM lands, Lake Clark National Park and the
Trading Bay State Game Refuge make visual resource
management a significant concern.
Economic Evaluation
The studies demonstrate that the project offers an
ecomonically viable source of energy in comparison
with the 55.6 mills/kWh which is the estimated cost of
equivalent energy from a coal fired plant, apparently
the most competitive alternative source. Taking that
figure as the value of energy, the Chakachamna Hydro-
electric Project could begin producing 400 MW at 50%
load factor (1752 GWh) in 1990 at 37.5 mills/KWh if
all stored water is used for power generation. If
approximately 19 percent of the water is reserved for
instream flow release to the Chakachatna River, the
powerplant could still produce 330 MW at 50% load
factor (1446 GWh) at 43.5 mills/KWh, which is still
significantly more economical than the coal fired
alternative. Assuming that the power tunnel were to
be machine bored, if the maximum pool level of the
lake is raised to .El. 1155 and can be drawn down to
El. 108 3, the powerplan t will produce 3 30 HW ( 13 01
GWh) at 44.·5 mills/KWh with 45% load factor. In all
the cases above, the powerhouse would be located on
the McArthur River. A powerhouse on the Chakachatna
River as described in the report is barely competitive
with the alternative coal fired source of energy.
2-10
r
r
r
r
I
r
[
f
l
r
[
r
L
L
r
/, L
r
i L~
2.5 Technical Evaluation and Discussion
2.5.1
2.5.2
Several alternative methods of developing the project
were identified and reviewed in 1981. Based on the
analyses performed in 1982, the most viable
alternative has been identified for further study.
That is Alternative E in which water would be diverted
from Chakachamna Lake to a powerhouse located near the
McArthur River.
Chakachatna Dam Alternative
The construction of a dam in the Chakachatna River
Canyon approximately 6 miles downstream from the lake
outlet, does not appear to be a reasonable alterna-
tive. While the site is topographically suitable, the
foundation conditions in the river valley and left
abutment are poor as mentioned earlier in Section 2.2.
Furthermore, its environmental impact specifically on
the fisheries resource will be significant although
provision of fish passage facilites could mitigate
this impact to a certain extent.
McArthur Tunnel Alternatives A, and B
Diversion of flow from Chakachamna Lake to the
McArthur Valley to develop a head of approximately 900
feet has been identified as the most advantageous as
far as energy production at reasonable cost is
concerned.
The geologic conditions for the various project facil-
ities including intake, power tunnel, and powerhouse
appear to be favorable based on the limited 1981 field
2-11
reconnaissances. No insurmountable engineering pro-
blems appear to exist in development of the project.
Alternative A, in which essentially all stored water
would be diverted from Chakachamna Lake for power
production purposes could deliver 1664 GWh of firm
energy per year to Anchorage and provide 4QO MW of
peaking capacity. Cost of energy is estimated to be
37.5 mills per KWh. However, since the flow of the
Chakachatna River below the lake outlet would be
adversely affected, the existing anadromous fishery
resource which uses the river to gain entry to the
lake and its tributaries for spawning, would be lost.
In addition the fish which spawn in the lower
Chakachatna River would also be impacted due to the
much reduced river flow. For this reason Alternative
B has been developed, with essentially the same pro-
ject arrangement except that approximately 19 percent·
of the average annual flow into Chakachamna Lake would
be released into the Chakachatna River below the lake
outlet to maintain the fishery resource. Because of
the smaller flow available for power production, the
installed capacity of the project would be reduced to
330 MW and the firm energy delivered to Anchorage
. would be 1374 GWh per year. The estimated cost of
energy is 43.5 mills per KWh. The cost estimate
included an allowance for facilities for downstream
flow release and for passage of fish at the lake
outlet. Layouts of these facilities were not
prepared. Obviously, the long term environmental
impacts of the project in this Alternative B are
significantly reduced in comparison to Alternative A.
2-12
r· 'L
,. r L.
l t
f
I l .
l
[
L
[
2.5.3 Chakachatna Tunnel Alternatives. C and D
An alternative to the development of this hydro-
electric resource by diversion of flows from
Chakachamna Lake to the McArthur River is by construc-
ting a tunnel through the right wall of the
Chakachatna Valley and locating the powerhouse near
the downstream end of the valley. The general layout
of the project would be similar to that of Alterna-
tives A and B for a slightly longer power tunnel.
The geologic conditions for the various project
features including intake, power tunnel, and power-
house appear to be favorable and very similar to those
of Alternatives A and B. Similarly no insurmountable
engineering problems appear to exist in development of
the project Alternative C, in which essentially all
stored water is diverted from Chakachamna Lake for
power productiori, could deliver 1248 GWh of firm
energy per year to Anchorage and provide 300 MW of
peaking capability. Cost of energy is estimated to be
52.5 mills per KWh. While the flow in the Chakachatna
River below the powerhouse at the end of the canyon
will not be substantially affected, the fact that no
releases are provided into the river at the lake
outlet will cause a substantial impact on the
anadromous fish which normally enter the lake and pass
through it to the upstream tributaries. Alternative D
was therefore·proposed in which a release of 30 cfs is
maintained at the lake outlet to facilitate fish
passage through the canyon section into the lake. In
either of Alternatives C or D the environmental impact
would be limited to the Chakachatna River as opposed
to Alternatives A and B in which both the Chakachatna
2-13
2.5.4
and McArthur Rivers would be affected. Since the
instream flow release for Alternative D is less than
1% of the total available flow, the power production
of Alternative D can be regarded as being the same as
those of Alternative C at this level of study (300 MW
peaking capability, 1248 GWh of firm energy delivered
to Anchorage). Cost of power from Alternative D is
54.5 mills per KWh.
The cost of energy from Alternative D is 25% greater
than that for Alternative B and E and is close to the
cost of alternative coal-fired resources. Therefore,
it was decided to concentrate further studies on the
McArthur River alternatives.
Alternative E
In the development of Alternative B, no specific
method was developed for release of instream flows
into the Chakachatna River immediately downstream from
the lake outlet, and no specific facilities were
developed for the passage of upstream and downstream
migrant fish at the lake outlet. Instead a lump sum
cost allowance was provided to cover these items for
Alternative B •.
However, in Alternative E which is a refinement of
Alternative B, development by tunnel to the McArthur
River, specific facilities for providing instream flow
releases and fish passage facilities were developed
and incorporated into the proposed project
structures. To facilitate the arrangement of these
facilities, it became evident that a more limited
reservoir drawdown was essential. The range of
2-14
r·
r
I
L
[
I
L
L
l
L
f~
L
L _ _:
reservoir level adopted was maximum level El. 1155
near the historical maximum level, and minimum level
El. 1083 to permit gravity discharge of witer through
the facilities at the lowest operating water level.
With this operating range in the reservoir and with an
installed capacity of 330 MW, the project can produce
1301 GWh per annum at a 45% load factor. If a 50%
load factor were to be retained, the installed
capacity of the powerhouse would reduce to
approximately 300 MW, which would reduce the overall
project cost by about 5-10%. However, at this stage
of the project development, such a refinement was not
considered warranted, and the same installed capacity
as developed for Alternative B was retained for
Alternative E, i.e. 330 MW. Significant project data
for Alternative E are set forth in Table 2-1.
Alternative E is also based on the power tunnel being
driven by a tunnel boring machine which resulted in a
significant reduction in cost compared with conven-
tional "drill and shoot" methods previously adopted
for Alternatives A through D. In addition, the power
tunnel profile in Alternative E was modified to a
uniform grade from the intake at Lake Chakachamna to
the powerhouse in the McArthur valley. The estimated
cost of energy is 44.5 mills per kWh.
It should be noted that the significant saving in
tunnel cost for Alternative E, as compared with
Alternative B, is offset by the increased cost of the
fish passage facilities and slightly lower energy
production, thereby yielding a firm energy cost
slightly higher for Alternative E than for Alternative
B.
2-15
TABLE 2-1
RECOMMENDED ALTERNATIVE E
PROJECT DATA
Chakachamna Lake
Maximum water level, natural conditions, (ft.)
Minimum water level, natural conditions,
approx. (ft.)
Surface area at elevation 1155 (sq. mi.)
Total volume at elevation 1155 (Ac. ft.)
Drainage area (sq. mi.)
Average annual inflow, 12 years (cfs)
1,155
1,128
27
Correlated average annual inflow, 31 years (cfs)
4,483,000
1,120
3,606
3, 7 81
Reservoir Operation
Normal maximum operating water surface
elevation (ft.)
Normal minimum water surface elevation (ft.)
Active storage (Ac. ft.)
1,155
1,083
1,105,000
Dike
Type
Length, (ft.)
Crest elevation (ft.)
Maximum height (ft.)
Volume (Cu. yd.)
Spillway
Type
Crest elevation (ft.)
Discharge capacity (cfs)
Power Tunnel
Type
Diameter, internal (ft.)
Hydraulic capacity (cfs)
Surge chamber (Dia. x Ht. Ft.)
2-16
Overflow rockfill
600
1,177
49
250,000
Free overflow
1,155
55,000
Circular, concrete lined
24
7,200
48 X 450
r ~ .
I
r ~
(
l
r ~
L
L
L
{
L
l
!. L
r -
i
[
[
[
TABLE 2-1 (cont'd)
Penstock
Number/Type
Diameter, internal (ft.)
Concrete linea
Steel lined
Powerhouse
Type
Cavern size (L x W x H Ft.)
Turbines
Generators ·
Unit output (MW)
Maximum net head (ft.)
Minimum net head (ft.)
Maximum discharge (cfs)
Distributor centerline elevation (ft.)
Installed capacity (MW)
Average annual firm energy (GWh)
Average annual secondary energy (GWh)
Load factor
Fish Passage Facilities
Maximum release (cfs)
Minimum release (cfs)
Fish passage tunnel (L x W x H Ft.)
Economic Parameters
Estimated total cost $ billion
Cost of energy (mills per kWh)
Cost per installed kW ($)
Construction period (Mos.)
" , ..,
!-Circular, concrete lined
4-Circular, steel lined
24
10
Underground
250 X 65 X 130
4 Vertical Francis
Synchronous
82.5
938
866
7,200
190
330
1,301
290
.45
1,094
343
7800 X 18 X 20
1.31
44.5
3,985
76
PROJECT
DEVELOPMENT
STUDIES
r
i
I .
L
r·
L
[
b
I L.
L :
L
[
3.0
3.1
PROJECT DEVELOPMENT STUDIES
Regulatory Storage
The existing stream flow records show a wide seasonal
variation in discharge from Chakachamna Lake with 91
percent of the annual discharge occurring from May 1
through October 31 and 9 percent from November 1
through April 30 when peak electrical demands occur.
The storage volume iequired to regulate the flow h~s
been-reported to be in the order of 1.6 million acre-
feet (USBR, 1962). The elevation of the river bed at
the lake outlet has been reported as 1127-1128 feet
(Giles, 1967). This elevation is thought to have
varied acco~ding to the amounts and sizes of solid
materials deposited in the river bed each year by the
melting toe of the glacier, and the magnitude of the
annual peak outflow from the lake that is available to
erode the solid materials away and restore the river
channel.
The above-mentioned volume of regulatory storage can
be developed by drawing down the lake by 113 feet to
Elevation 1014. The original studies performed in
1981 adopted such a reservoir operating range in
developing project alternatives A, B, C and D.
However, when the 1982 studies for development of
suitable fish passage facilities at the lake outlet
were initiated, it became evident that a lake drawdown
to El. 1014 was not suited to the provision of such
facilities. Therefore a modified range of reservoir
operating level was adopted as discussed below.
3-1
3.2
If the maximum lake level is raised to El. 1155 and 72
feet drawdown is considered, then a regulatory storage
of 1,105,000 acre-feet is provided with increase in
head. Although previous studies of the project have
discredited the possibility of locatiny a control
structure at the lake outlet because its left abutment
would have lai11 on the toe of the Barrier Glacier, it
is believed that a relatively low dike with 27 feet of
hydraulic head plus freeboard could be constructed and
maintained at this location. This is discussed
further in Section 3.5.1.
The Barrier Glacier ice thickness was measured in 1981
by the USGS using radar techniques. The data has not
yet been published but verbal communication with the
USGS staff has indicated that the ice depth is
probably 500-600 feet in the lower moraine covered
part of the glacier near the lake outlet. Thus it
would appear that the outlet channel from the lake may
be a small gravel and boulder lined notch in a deep
bed of ice.
Chakachatna Dam
The possibility of gaining both storage and head by
means of a dam on the Chakachatna River was first
posed in 1950 by Arthur Johnson (Johnson, 1950) who
identified, though was unable to inspect, a potential
dam site about 6 miles downstream from the lake outlet.
Three years later, during the 1953 eruption of Mount
Spurr, a mud flow descended the volcano slopes and
temporarily blocked the river at this location,
backing it up for about 4 miles until it overtopped
the debris dam. At this location, the river today is
3-2
r .
t
I .
[ :
f -
r·
r
L
[
L
t::
r
L
I_
r -
I
l
r -
r:
1-
L
r -
h
[
f -
r L
f
L
I l -
still backed up almost 2 miles despite the occurrence
of the August 1971 lake breakout flood estimated to
have peaked at about 470,000 cubic feet per second
(Lamke, 1972). This flow is about twenty times larger
than the maximum daily discharge that occurred during
the 1959-1972 period of record.
Examination of aerial photographs taken after the 1953
eruption between 1954 and 1981 indicate that subse-
quent mud flows, though of smaller magnitude, may have
occurred but probably did not reach the river. Th~
source of this activity has been Crater Peak, an
active volcanic crater on the southerly flank of Mount
Spurr. It lies directly above and in close proximity
to the postulated dam site and thus poses serious
questions on the safety of this site for construction
of any form of dam. At this location, generally from
about 6 miles to 7 miles downstream from the lake
outlet, the river is confined within a canyon. Both
upstream and downstream, the valley substantially
widens and does not appear to offer any topographicaly
feasible sites for locating a dam.
Within the canyon itself, conditions are rather
unfavorable for siting a dam. Bedrock is exposed on
the right abutment, making this the most likely site
for a spillway, but the rock surface dips at about
40-degrees toward the river channel. At this
location, the peak discharge of the probable maximum
flood calculated according to conventional procedures
would be in the order of 100,000 cubic feet per second.
The crest length of a spillway would have to be in the
order of 200 feet and siting it on the steeply dipping
3-3
3.3
3.3.1
right abutment rock surface would be difficult and
costly.
surface examination-of the left abutment conditions,
as discussed in section 5.2.3.2 of this report,
indicates that they consist of deep unconsolidated
volcanic materials. These would require a deep
diaphragm wall or slurry trench cutoff to bedrock,
or an extensive upstream foundation blanket to control
seepage through the pervious materials lying ou this
abutment. ·very high costs would also be attached to
their construction.
The presence of the volcano and its potential for
future eruptions accompanied by mud flows as well as
pyroclastic ash flows is probably the overriding
factor in discrediting the feasibility of constructing
a dam in this canyon location. Consequently, this
concept has been temporarily set aside from further
consideration at the present stage of the studies, and
the main thrust has been directed toward development
by gaining regulatory storage by drawiny down the lake
water level and diverting water from a submerged
intake in Chakachamna Lake through a tunnel to the
McArthur river, or through a tunnel to the mouth of
the Chakachatna Valley, as discussed in the next two
sections of this report.
McArthur Tunnel Devlopment
Alternative A
Initial studies have been directed toward development
by means of a tunnel to the McArthur River that would
3-4
f
\
[
!
[
L
L
r~
L
L
L
L
L
l
L
[
I
[ '
l .
( .
L
L
L
L
maximize electrical generat~on without regard to
release of water into the Chakachatna River for
support of its fishery. Two arrangements have been
studied, the first being a tunnel following an
alignment about 12 miles long designated Alternative
A-1 and shown irr Figure 3-1. This alignment provides
access for construction via an adit in the Chakachatna
Valley about 3 miles downstream from the lake outlet.
As discusssed in section 9.0 of this report, the
tunnel would be 25 feet internal diameter and concrete
lined throughout its full length.
The second tunnel studied is designated Alternative
A-2 and follows a direct alignment to the McArthur
Valley without an intermediate access adit as shown on
Figure 3-2. As further discussed in Section 9.0 of
this report, this tunnel would also be 25 feet
diameter and concrete lined.
Although the tunnel for Alternative A-1 is about 1 mile
longer than that for Alternative A-2, it would enable
tunnel construction to proceed simultaneously in four
headings thus reducing its time for construction below
that required for the shorter tunnel in Alternative
A-2. Nevertheless, the studies show that the
economics favor the shorter tunnel and no other
significant factors that would detract from it have
been identified at this stage of the studies. There-
fore the direct tunnel route was adopted and all
further references in the report to Alternative A are
for the project layout with the direct tunnel shown on
Figure 3-2.
3-5
Typical sketches have been developed for the arrange-
ment of structures at the power intake in Chakachamna
Lake and these are shown on Figure 3-4 with typical
sections and details on Figure 3-5r Similarly, lay-
outs have been developed for structures located beyond
the downstream end of the tunnel. These include a
surge shaft, penstock, manifold, valve gallery, power-
house, transformer gallery, access tunnel, tailrace
tunnel and other associated structures as shown on
Figure 3-6.
For Alternative A, the installed capacity of the power-
house derived from the power studies discussed in
Section 4.0 of this report is 400 MW. For purposes of
estimating costs, the installation has been taken as
four 100 MW capacity vertical shaft Francis turbine
driven units.
It is to be noted that the layout sketches mentioned
above and those prepared for other alternatives con-
sidered in this report must be regarded as strictly
typical. They form the basis for the cost estimates
discussed in Section 8.0 but will be subject to re-
finement and optimization as the studies proceed. For
example, the lake tapping for the power intake is laid
out on the basis of a single opening about 26-feet in
diameter. This is a very large underwater penetration
to be made under some 150-170 feet of submergence, and
the combination of diameter and depth is believed to
be unprecedented. In the final analysis, it may prove
advisable to design for multiple smaller diameter
openings: The information needed to evaluate this is
not available at the present time.
3-6
.[ \\
--I
f -
I ~
[ -.
f
f ~
l
L
f_ .
[
L
L
L
L
L
l
l
l
---
!.) 7"0POGRAPHY IS FROM U 5 G 5
QVAORAIVGt..e hfAPS.
Z.) COAiiOVR IIV7"ERVAL IS 100
FEET.
3.) Vt:.RrtCAt.. 0AitM1 IS MEAN
SEA LEVEL.
4.} HORIZONTAl. GRID IS UNIVeRSAL
TRANSVERSE MERCATOR PROJECTION,
1927 NORTH AMERICAN DATUM.
5.) SEE FI6Uf1ES 3·4 AND 3·5 FOR6ATE
SHAFT DETAILS AND F16f/RE 3·ti FOR
SUR6E TANK, PENST()CK AND POWER·
HOfiSE GENERAL ARRANGEMENT.
-1000 1000 2000 FEET
YERTfCA.L ,SCALE 15=~~1;;;;;;;;;;;;;:-;1
100 .00. 200t00 300 tOO
PLAN
SLOPE
25.'H<>~SeSH<:>S TUNNEl..
24 1 C/I(GUi.AR TUi.//.Jec.;.
.I
ALT. A-2
PROFILE
400tOO
~;ooo:
(TYPIC_., L} . ALT-• E. @)
<!ciao•
SECTION
500t00 600 tOO
,vor£ s:
1.) TOPO~RAPHY 15 FROM USGS
QUAOR.4AJGLE MAPS
z.) COI..ITOUR. 11../TERVAL IS 100 ;:'!HiT
7.) VeR TIC-"rL DATUM IS MEAN SEA LEVEL.
4) HORIZONTAL GRIO IS 1/NIVERSAL TRAINSIVERSEI
MERCATOR PROJECTION, 1927 NORTH
AMERICAN DATUM.
5.) SEE I'/6URE5 3·4 AND :J-5 FOR GATE
SHAFT PETAILS AND F16URE 3-<D FOR
5//R6E TANK, PENSTOCK AND POWERHOUSE
6ENERAL ARRANGEMENT.
l
l
J
l
J
I
)
J
J
__j
-----
MAX. POOL EL. /!55. 0
sz APPROX. PRESENT CHANNeL /NVei'"T AT LAKE' OUTLET EL. /12d.O
MIN. W. 5. cL. /08.3. 0
,{
Stt_L
Bl/LKHEAO 6ATIE ~ I
TRAI-!5/TIOA.I __ LJ
5 ECTIOA.JAL E L E 1/A T!01V
I'
I'
WHEEL EO
L..:ER6ENCY 6ATE
·I TRANSITION
No. DATE REVISION
ALASKA POWER AUTHORITY
ANCHORAGE, ALASKA
CHAKACHAMNA HYDROELECTRIC PROJECT
GATE SHAFT SECTION
SHEET-I
BECHTEL CIVIL & MINERALS, INC.
SAN FRANCISCO
DESIGNED DRAWNPRtrCHARO CHECKED l.IUJ
DRAWING No. REV.
FIGURE 3-4
£'L.. VARt~-5
~----~Z~8~!~o_· ____ j
5ECT!OAJ
L-----,--,-,..-;i;;=---,-~ . ..-i, • •, E L,._ ----'9-'-'/ Z=._,G_
-~~~~~~~--~~·~·: ~E~L~·~9~0~8-'-'.0~
5 E C T I 0 1)--:1
1
_ .. ®
~"" ~o
• T!.IAJIJEL AAIO SHAFT
t I' . ( --------~
I I \..1
I
I
I
I
I
I
I
I
-~-· /~··· ..
SECTION
El.... 'IIZ.o.
0/,~CC";-!OA.i
OF F'i...OI</ )
---
TUAJAIEL. AAJO SHAF'T
VARIES
5ECTIOAJ 5 E C T I 0 IJ
5ECTIOIJ
---__ _J_ --
5E.CT/OIV
CHARGeR
...
-GATE HOIST
ROO
STORAGE
No. DATE REVISION
ALASKA POWER AUTHORITY
ANCHORAGE, ALASKA
CHAKACHAMNA HYDROELECTRIC PROJECT
GATE SHAFT SECTIONS
SHEET-2
BECHTEL CIVIL & MINERALS, INC.
SAN FRANCISCO
DESIGNED
REV.
FIGURE 3-5
CO/JCRE.TE
p L A A/
SECT/0/LJ 00~==~'!""""'!""""80~iiiiiiiiiiiil160 FEET COIJC.RET"f: PI...UGS < <
", ../'<:...?" v
TEMPORARY CO/JST"R!l::.TIOAI~ 1
-;,~C::io;:~~!~v~0~n'A/.'le~~ ' ''
"i/JO TUR81NE LeVEL OF
S(IRGC SHAFf
5ECTIO/LJ
MACH/A/I:=. HALL.
ACCE5S 7UN/JEL
£L. /120.0
SFCTJQ)J
PENSTOC!<
I I
I 0
I
.SECTION
'
~ UMITS £1-. /90.0
REVISION
,..-P.l. £L. !92.0
~~~~~====~==~~~=====~~~~~~~~~~~====~~~tt~~YhL----~~~----~~~~~~~1 ALASKA~~~~~~THORITY
_j -----
PoweR TuNNE:L CHAKACHAMNA HYDROELECTRIC PROJECT A'-T· e o;.~,_y
McARTHUR POWER DEVELOPMENT
GENERAL ARRANGEMENT '
SAN FRANCISCO 5FCT!'J!VAL. ELEVAT/OAJ BECHTEL CIVIL & MINERALS, INC.
DESIGNED
SO 80 160 FEET
REV.
FIGURE 3-6
I
[ :
l '
L
L
k
[
[
L_
I"
L
r L~
In similar vein, ~he penstock is shown as a single
inclined pressure shaft descending to a four-branched
manifold at the powerhouse level with provisions for
emergency closure at the upstream end.· Again, this is
a very large pressure shaft, but the combination of
pressure and diameter is not Ul~recedented in sound
rock. Other considerations, such as unfavorable
hydraulic transients in the manifold, or operational
flexibility, may support the desirability of construc-
ting a bifurcation at the downstream end of the tunnel
with two penstocks, each equipped with an upper level
shutoff gate, provided to convey water to each pair of
turbines in the four-unit powerhouse. such an
arrangement would cost more than the single penstock
shaft.
Turbine shutoff valves are shown located in a valve
chamber separated from the powerhouse itself. Optimi-
zation studies should be made in the future to evalu-
ate whether these valves can be located inside the
powerhouse at the turbine inlets, or whether a ring
gate type instaliation inside the turbine spiral cases
might be preferable.
The powerhouse is shown as an underground installation.
This appears to be the most logical solution for
development via the McArthur River because of the
steep avalanche and rock slide-prone slopes of the
canyon wall. For the same reason, the transformers
are shown in a chamber adjacent to the powerhouse
cavern. A surge chamber is shown near the upstream
end of the tailrace tunnel. It may prove more
advantageous for this relatively short tailrace tunnel
3-17
3.3.2
to make it freeflowing in which case the tailrace
surge chamber would not be required.
The object of the above comments is to point out some
of the options that are available. The arrangement of
structures shown provides for a workable installation.
Because of the limited engineering studies performed
to date, it is not to be regarded as the optimum or
most economical. Optimizdtion will be performed at a
later date. The layout is a workable arrangement that
gives a realistic basis on which to estimate the cost
of constructing the project, and a separately identi-
fied contingency allowance is provided in the estimate
to allow for costs higher than those foreseen at the
present level of study.
Alternative B
This alternative considers what effect a tentative
allocation of water to meet instream flow require-
ments in the Chakachatna River would have on the
amount of energy that could be generated by Alterna-
tive A which would use all stored water for energy
generation. The tentative instream flow schedule is
discussed in section 7.3.2 of this report. For diver-
sion to the McArthur River, and reservation of water
for instream flow releases, the tunnel diameter would
be about 23 feet. Based on the power studies dis-
cussed in Section 4.0, the installed capacity of the
powerhouse would be reduced to 330 MW. The tunnel
alignment and basic layout of structures generally is
the same as that shown for Alternative A in Figure 3-2.
The diameters of hydraulic conduits and the dimensions
of the 330 MW powerhouse would be smaller than for the
3-18
[
•
L
L
r L
[
f .
I 1 .
h L
L
L
L
3.4
3.4.1
400 MW powerhouse in Alternative. A and appropriate
allowances for these are made in the cost estimates.
When the various alternative arrangements of the
project were developed in the 1981 study, no specific
plan had been developed for the provision of releases
of flow into the Chakachatna River immediately down-
stream from the lake outlet nor for the provision of
fish passage facilities at the lake outlet for upstream
and downstream migrants. It was recognized that
suitable structures would be difficult to develop and
would be very expensive. It was also planned that,
due to the presence of the glacier at the lake outlet,
the fish passage facility would have to be constructed
inside a tunnel within the massive rock mountainside
forming the right side of the lake outlet. Since no
plan for such facility had been developed at that
stage of the studies, a provisional allowance of $50
million was shown in the estimate for fish passage
facilities.
During the second phase of the study in 1982, the
concept of fish facilities and operation of the lake
has been further developed for this alternative and it
is described at the end of this section as Alternative
E, the recommended alternative.
Chakachatna Tunnel Development
Alternative C
The initial studies of this alternative focused on
development of the power potential by means of a
tunnel roughly paralleling the Chakachatna River
3-19
without release of water for instream flow require-
ments between the lake outlet and the powerhouse where
the water diverted for power generation would be
returned to the river. The tunnel alignment is shown
on Figure 3-3.
This alignment offers two convenient locations for
intermediate access adits during construction. The
first is about 3 miles downstream from the lake outlet
in the same location as discussed in section 3.3.1
above for Alternative A. The second adit location is
about 7 miles downstream from the lake outlet. The
total tunnel length in this arrangement is about 12
miles and the adits would make it possible for
construction of the tunnel to proceed simultaneously
in six different headings.
The arrangement of the power intake is essentially the
same aud in the same location as for Alternative A as
shown on Figures 3-4 and 3-5. The tunnel is also 25
feet internal diameter, concrete lined, and penetrates
the mountains in the right wall of the Chakachatna
Valley. The arrangement for the surge shaft, pen-
stock, valve gallery, powerhouse and asssociated struc-
tures is similar to that for development via diversion
to the McArthur River but is modified to fit the topo-
graphy and lower head. The layout is shown on Figure
3-7. The head that can be developed in Alternative c
is roughly 200 feet less than in Alternatives A and B
and the installed capacity in the powerhouse is only
300 MW as determined from the power studies discussed
in Section 4.0 of this report.
3-20
r I
\
L
L
I'
!
l '
[
[
L
L
r,
L
P L A AJ
2000 0 2000 4000 FEET
'"'"' ;;;o;! I I
_j
J
VARIES
S E C T / 0 N .@).
(TYPICAL.)·· ~··t1 o"
lOOt CO 200 +CO 300+00 400+ 00
2000
VERTICAl.. SCALE:. t000.~=~==~1000lii.iiiiiio;o2000~ . FEET
500 + 00 600+ 00
1.) TOPOGRAPHY IS FRONI USG.S
QUAORA<IGI..E MAPS.
2.) CO.VTOUR 11./TERVAI.. IS /00 FEET
,.) VERTICAl.. DATUM IS MEA.V SEA LEVEl..
4) HOIVZOIJTAI.. t:i>RIO IS U.VIVERSAI..
TRAIJSVcRSE MERCATOR PRo../ECTIO.V,
/92.7 AIORTH AMERICAAI OATUM.
~)SEE FI(:,URES ;-4-Al./0 3-5 FOR
GATE SHAFT OETAII..S A.VD FIGURe
;1-C. FOR SI/RGG TAAJK., PE.VSTOCK.
ANO POWERHOIISE GENERAl.. ARRAN6EMEN T.
:t
1
J
:SECT!OAI
j
SURGE SHAFT
r;oo.o
E:l... 1!20.0
'
! I ·~
I I TIOIJ ', ~---,.,
&
~
COIJ'CI':£ T£.
'
/
/
/
/
/ /
Pt_UG~/ /
/ /
.~·.r
/
/
/
p
coucR=.re Lt . .v~.::;
L A N
-----r""""T"---Y
/
/
/
/ /
/ /
/
/ /
/ /
/ /
/ /
/
CHAMBER / /
/ /
/ /
/ /
,
0 t
-=5--=E:........:::C::......:.....T.....:.!____;;:_O_AI--"-------"@
., <f. UAJITS EL. >8?.0
'
P.L.EL. '87.0 ~-:~--~''~~~,-~;~::;-:;~~============~========~~~~~a ~ ~~--~L-~--~~~------~~~~-----
5ECT!O!VAL ELEVATIO!V
80 160 FEET
5ECT!OA...I
STEEL.
L IAIE.R
5ECTIOA..J
No. DATE REVISION
CHAKACHAMNA HYDROELECTRIC PROJECT
CHAKACHATNA POWER DEVELOPMENT
GENERAL ARRANGEMENT
BECHTEL CIVIL & MINERALS, INC.
SAN FRANCISCO
DESIGNED DRAWN PRiTCHARD CHECKED
DRAWING No.·
FIGURE 3-7
I ~
I ~.
l.
3.4.2
For purposes of estimating the present costs of con-
struction, the powerhouse is taken as being located
underground. If this Alternative were to be pursued,
future studies would be made to determine if economy
can be attained by locating it outside on the ground
surface. Comments made in Section 3.3.1 regarding the
layout sketches for the McArthur powerhouse in
Alternative A apply equally to the powerhouse and
associated structures for the Chakachatna Powerhouse
considered in Alternative C.
Alternative D
Studies of this alternative take account of the effect
on electrical generation of reserving water to meet
instream flow requirements in the Chakachatna River.
The tentative water release schedule is less than that
condidered for development by power diversions to the
McArthur River as discussed in section 7.1.5 of this
report.' The reason for this is that in the lower
reaches of the river, downstream from the proposed
powerhouse location, the river flow will include those
waters that were diverted for electrical generation.
These lower reaches of the river are probably more
important to the fishery than the reach of the river
between the lake outlet and the proposed powerhouse
location. This probability is suggested, though not
fully confirmed, by observations made of fish runs
during the 1981 and 1982 field studies. These have
indicated that the Chakachatna River, between the lake
outlet and the proposed location of the powerhouse,
serves primarily as a travel corridor for fish passing
through the lake to spawning areas furth~r upstream.
The river itself, in this reach does not a~pear to
offer much in the way of suitable spawning and
juvenile rearing habitat. On the other hand,
3-25
3.5
3.5.1
significant numbers of fish and spawning areas were
observed in the lower reaches of the river downstream
from the proposed powerhouse locations. Consequently,
the tentative instream flow releases are ~mall when
compared with those considered for development via
power diversions to the McArthur River, as discussed
in Section 7.1.5 of this report. The tunnel diameter
for development of the power potential via the
Chakachatna Tunnel with provision for instream flow
releases, is 25 feet, the same as that mentioned in
section 3.4.1 without such releases. The installed
capacity in the powerhouse also remains the same at
300 MW. The layout sketches shown in Figures 3-3 and
3-7 for Alternative C are equally applicable to
Alternative D as are the comments set forth in
Sections 3.3.1 and 3.3.2 regarding the layout sketches
for de-velopment via the McArthur River.
McArthur Development -Recommended Alternative E
General
This alternative is basically similar to Alternative
B, but modified to include water release facilities
into Chakachatna River, fish passage facilities at the
lake outlet and modification of lake operating levels
to accommodate these facilities. The power tunnel
would have a 24-foot internal diameter circular
section and the diameters of other hydraulic conduits,
the powerhouse arrangement, sizing and location will
be the same as described for Alternative B except as
shown in Figures 3-2 and 3-6. It is to be noted
that the emergency closure gate located at the head of
the penstock in Alternative B cannot be retained in
3-26
I
L
r
the layout for Alternative E. This results in a loss
of a certain amount of operating flexibility to the
extent that the penstock, upstream of the valve
chamber, cannot be dewatered for inspection without
dewatering the power tunnel. Likewise, in the event
of a failure in the valves or the conduits upstream of
the valves, the whole station would have to be shut
down and the tunnel dewatered, before the rupture
could be repaired.
The operating range of the lake will be modified. The
maximum level will be taken as the historical maximum
evidenced by a white mark on the rock slopes of the
lake shoreline at approximately El. 1155. A wide
rockfill dike will be construdted at the lake outlet
from the spoil material available from the spillway
excavation described below to raise the lake outlet by
approximately 27 feet. The reservoir level control
will be established by an unlined spillway channel at
El. 1155 excavated into the rock on the right side of
the outlet. The layout is shown in Figure 3.8. The
lake level operating range will be 72 feet down to El.
1083 rather than the 113 feet that was previously
available in the studies for Alternatives A through
D. The power tunnel intake level is maintained at the
level previously used to provide even greater
submergence to reduce potential problems of attracting
downstream migrant fish into the power tunnel. Most
flood waters will be released via the unlined spillway
channel cut through the granite in the right
abutment. This unlined channel has a capacity of
55,000 cfs, and will therefore handle all flood
releases up to 55,000 cfs. Flows greater than this up
to the presently estimated probable maximum flood of
3-27
3. 5. 2
100,000 cfs will pass both through the spillway and
over the rockfill dike. It should be noted that the
maximum peak discharge in the period of -record of 1959-
1971 was 23,400 cfs if the "dam-break" type of flood
which occurred in August 1971 is disregarded. Future
studies of the required spillway size may indicate
that a reduction in size below the 55,000 cfs capacity
may be possible.
It is considered that since overtoppin~ of the rock
dike will be a very infrequent occurrence, repair of
the dike after such an event would be an acceptable
maintenance procedure. such repair can be scheduled
in the spring before the lake rises to the level of
the dike in July or August. Periodic maintenance will
also probably be re~uired to repair damage to the dike
caused by movement of the ice in the toe of the
glacier.
water Releases and Fish Passage Facilities
To provide instream releases into the Chakachatna
River and arrange for both upstream and downstream
migration of fish between the river and the
Chakachamna Lake, a concept for a conveyance system
was developed which consisted basically of fish
ladders at the upstream and downstream ends of two
interconnecting channels located in a tunnel. The
system is a gravity flow system and does not rely on
any pumping for its operation. The layout is shown in
Fig. 3-8. The facilities will be located in the right
bank granitic rock abutment to provide a secure
structure protected against avalanches and rockfalls
and to minimize the length of the tunnel. A deep
3-28
f
l
L.
L
L
L
L
[
L
I
L
L
f
N
1
Access Re>Ao
H2.GJ1,ooo +
!NLGT SITE PLA IV
1" ... zoo'
+
f
CHAI(AC"HAMAIA
/.AI(£
OUTLET SITE PLAN
I"= zoo'
pfeOJE.CT I(.EY PL,AAJ
, •• 'lfX)()'
"'=-d T .,..
GRAPHIC a::ALE FEET
, ... 2000'
~ d ; r
GRAPHIC SCALE FEET
, ... 200'
No. DATE REVISION BY
ALASKA POWER AUTHORITY
ANCHORAGE, ALAIIKA
CHAKACHAMNA HYDROELECTRIC PROJECT
CHAKACHAMNA LAKE OUTLET
GENERAL ARRANGEMENT
BECHTEL CIVIL & MINERALS, INC.
SAN FRANCISCO
DESIGNED DRAWN CHECKED
DRAWING No. REV.
FIGURE 3-8
I
b
r l,
f:
I l ..
3.5.3
approach channel will be excavated in the alluvial
deposits on the right side of the lake outlet to
convey water from the lake to the fish release
facilities located in an excavated cavern in the right
abutment near the lake outlet.
Upstream Higrants Facility
The facility for upstream passage of adult migrant
fish would consist of a conventional fish ladder with
overflow weirs having 1 foot difference in elevation
between each pool. Alongside each tier of ladder
pools is a water supply chamber that serves a 10 foot
interval in the range of lake level. Each pool in a
given tier would have a gated connection to the water
supply chamber, so that for a given lake level, the
gate leading to the pool whose water level is 1 foot
lower than the reservoir would be open, thus letting
water run from the supply chamber into the ladder.
All other gates between the supply chambers and pools
would be closed. As the lake level changes, the gates
would be manipulated accordingly. At this stage it is
assumed that these gates would be operated manually
although it would be possible to automate their
operati6n, with the selection of "open" gat~ tied to
lake level. A control gate is also shown between each
water supply chamber and the lake. Fish ascending the
ladder would rise through the pools until they reached
the one receiving water from its supply chamber. The
fish would then pass into the supply chamber and exit
into the lake through the control gate opening. This
upstream migrant structure would be constructed in an
underground chamber excavated in the rock mountainside
3-31
3. 5 o4
adjacent to the existing natural lake outlet. The
·concept is shown in Figures 3-9 and 3-10.
Downstream Migrants Facility
The facility for downstream passage of out-migrants
and for provision of minimum downstream flow releases
is shown in Figure 3-11. The concept consists of
three, 15 feet wide fixed wheel type gates stacked one
above the other. The proposed mode of operation is
that when the water level is between El. 1155 and El.
1127, the top gate would be lowered the amount
necessary to discharge the desired amount of water
that would plunge into a stilling basin and return to
the river through the discharge tunnel. The middle
and bottom gates would be closed. When the lake level
falls to.El. 1127, the top gate would be raised above
the water surface and the middle gate would be lowered
to discharge the desired amount of water. As the
water level descends below El. 1001, the middle gate
would be raised and the lowest gate would take over
the control of discharge. This gate will be
progressively lowered below the invert of the outlet
channel as the lake level falls. Manipulation of the
gates would be in the reverse sequence during the
condition with a rising lake water level. The depth
of flow in the stilling basin immediately downstream
from the gates is relatively shallow in order to
prevent entrainment of air at depths and pressures
which could result in nitrogen saturation harmful to
the fish.
3-32
f
.I ~
[ 0
r .
l"
l~~
L
r·
f .
["
r
('
L
L
L
l
J
J
l
)
J
J
-J
J
----....__
//H;
11$3NAX. WL. .,
1126MIN.WL
l/2f!' NAK. IV" -1116 M!H. WL
~~~~~~~~~~~~m-~
(~ PLAN EL/154 -EL/115
,~ ... u:~'
~ OE.Nt:rT£$ Dlll~CT/ON OF WArE/if FI.()W
R6u-'RES DENDTE WAre£. $VIi!.PACE Et..EVArtoN I# FE£T MSL.
PLAN ££./184-£t. 1115
t'• ,~,
ACCESS TVNNEL SECTION
(T"yi",~L DDWN5rREAM FNI>M
INTC/l"£T/CIN W/rN /JVST1/i!GA~
FLDW NELEA~E ,CLV,ofi!F)
11•101
(C·OOZ)
IllS MAl!. IVl.-.
li06HIN. Wt
1/0SHAJI Wt -10$'6 llfN,W£
I0!15AIAX. Wl.
101» A/IN• WL. ...
PLAN EL. 1114-£L.I095
11 •tt:J1
PLAN EL .. 1085
~~~~~/
10.
No. DATE
CIRAPHIC ICAU NIT , ... , ..
REVISION
ALASKA POWER AUTHORITY
ANCHORAGE, ALASKA
CHAKACHAMNA HYDROELECTRIC PROJECT
UPSTREAM FISH PASSAGE FACILITIES
PLANS AND SECTION
BECHTEL CIVIL & MINERALS, INC.
SAN FRANCISCO
DESIGNED DRAWN CHECKED
ENGRSUPV PROJENGR APP"D • DRAWING No. REV.
FIGURE 3-9
Rt:JCk MOUNTA/11/SIDC
AV. .St.aPe ,oPP.eox . ..fo"
)
Clfi/KACII.IJMNA LAKE'
l
SECTION
) /11 =/01
)
j
No. DATE
SECTION
111 -10 1
•• 10
GRAPHIC SCALI FliT r•w
REVISION
..
ALASKA POWER AUTHORITY
ANCHORAGE, ALASKA
CHAKACHAMNA HYDROELECTRIC PROJECT
lPSTREAM FISH PASSAGE FACILITIES
SECTIONS
BECHTEL CIVIL & MINERALS, INC.
BAN FRANCISCO
DESIGNED CHECKED
ENGRS...V _, • DRAWING No. REV •
FIGURE 3-10
MAX-Poot... E-L. /ISS
MIN. ~£.. Et.../083
Q· ••• ' -
"'
,,
... -==-
'---MAINTENANCE f"LOOR I
{(
(!I
------++-r_eL./074). E-1-'" ":_~----+----
. : I . ·-l-+--
. I I
----~---~~-----------:: •.·
SECTIONAL PLAN
t"= to'
INTeRCONNeCT/foJG-,;
Access 'TUNNet.
10 10
GR~HIC SCALE FEET
, ... 10'
No. DATE REVISION
20
ALASKA POWER AUTHORITY
ANCHORAGE, ALASKA
CHAKACHAMNA HYDROELECTRIC PROJECT
DOWNSTREAM FISH PASSAGE FACILITIES
INSTREAM RELEASE STRUCTURE
BECHTEL CIVIL & MINERALS, INC.
DESIGNED CHECKED
ENGRSUPV Al'P'D • DRAWING No, REV.
FIGURE 3-11
f '
E
L.
h
l
L
L
3.5.5
3.5.6
Conveyance Channel
~oth upstream and downstream migrants will travel in
separate channels located in a common tunnel. The
upstream migrants would utilize a 6' x 4' channel
dimensioned for the fish ladder discharge of 40 cfs.
The out-migrants would use the main channel 18' x 7'
dimensioned for maximum required mcinthly release minus
the flow in the small channel. (This maximum
downstream release as presented in Section 4 has been
set tentatively at 1094 cfs.) The small channel would
be located at one side of the tunnel above the main
channel with a road access provided on the other
side. A typical section of the tunnel is shown in
Fig. 3-9. Both channels would be free flowiny with
freeboard provided. Only the main channel which has a
maximum velocity of 8 feet/sec., would be fully lined
to reduce head loss. In order to keep velocity in the
small channel for the upstream migrants at 2
feet/sec., the floor of the channel would have a
slightly less gradient than the large channel and 5
drops of 1 foot each will be provided at regular
intervals down the tunnel.
Outlet Structure
A ladder is required at the downstream end of the
tunnel to provide a means for the upstream migrants to
reach the upper trausportation channel inside the
tunnel. This ladder will be partially submerged at
high releases since the river level rises by an
estimated 4 feet when the discharge from the facility
is increased from the minimum flow of 343 cfs to the
maximum of 1094 cfs. Another 6 ft vertical rise in
3-39
the ladder is provided to accommodate the difference
between the water surfaces in the two channels in the
tunnel so that a total of 10 ladder pools would be
provided. A horizontal submerged screen would allow
the out-migrants to reach the main discharge channel
while its presence and a velocity of around 1/2 ft/sec
through the bars would prevent the large fish from
entering the main tunnel discharge channel. The
attraction flow coming down the ladder would be 40 cfs.
The layout is shown in Figure 3-12.
A floating ice barrier installed in the approach
channel just upstream of the fish passage facility
will prevent most of the ice from passing into and
through the facility during the breakup period.
However, as a precaution, since it will be very
difficult to ensure the complete elimination of the
entrance of ice into the facility, it is planned to
remove a stoplog barrier which normally diverts the
flow through the horizontal screen,. thus allowing the
flow and ice to continue straight into the side outlet
channel and the Chakachatna River, and thereby by-
passing the horiiontal screen through which the flow
normally passes. This should be an acceptable
procedure because the upstream migrants do not travel
upstream until after breakup occurs.
A small rockfill dike will be constructed across the
river channel just upstream of the downstream entrance
to the outlet facility so that the upstream migrants
will be prevented from entering the section of the
river between the fish facility and the lake outlet.
Any small inflow into the river between the lake
3-40
i ~
L
I
L
1
J
J
_j
J
•••
VE.IJICI.E ACCESS TUIJ/JEI.
L 7/
SE.CT/0/JAL PLAJ.J A
t''.o.to 1
SECTIOIJ 8
f'•ID 1
SE.CT/0/J C
/11 • 10 1
10
No. DATE
10
GRAPHIC ICALI PEIET
, ... 10'
REVISION
2D
ALASKA POWER AUTHORITY
ANCHORAGE, ALASKA
CHAKACHAMNA HYDROELECTRIC PROJECT
OUTLET FISH PASSAGE FACILITIES
PLAN AND SECTIONS
BECHTEL CIVIL & MINERALS, INC.
SAN FRANCISCO
DESIGNED DRAWN CHECKED
ENGRSUPV PROJ ENGR APP'D
DRAWING No. REV.
FIGURE 3-12
['
I
r
l -
outlet ahd the fish facilities outlet will filter
through the rock dike.
3.6 Transmission Line and submarine Cable
At the present stage of the project development
studies, no specific evaluation has been made of
transmission line routing. Whether development should
proceed via the proposed McArthur or Chakachatna Power-
house locations, it is assumed for the purposes of the
costs estimates that the transmission lines would run
from a switchyard in the vicinity of either powerhouse
site to a location in the vicinity of the existing
Chugach Electric Association's Beluga Powerplant. The
general routing of the proposed lines is shown on
Figure 3-13. At Beluga, an interconnection could be
made through an appropriate switching facility with
the existing Beluga transmission lines if a mutually
acceptable arrangement could be negotiated with the
owners of those lines. This would enhance reliability
of the total system, but for purposes of this report
no such interconnection has been assumed. Beyond
Beluga, it is assumed for purposes of the estimate,
that the new transmission lines for the Chakachatna or
McArthur Powerhouses would parallel the existing trans-
mission corridor to a terminal on the westerly side of
Knik Arm and cross that waterway by submarine cables
to a terminal on the Anchorage side. Beyond that
point, no costs are included in the estimates for any
further required power transmission installations.
In the project alternatives thus far considered, the
cost estimates are based on power transmission via a
pair of 230 KV single circuit lines with capacity
3-43
3.7
matching the peaking capability of the respective
power plants. Optimization studies to determine
whether transmission should be effected in that manner
or by a single line of double circuit towers should be
performed in the future.
References
Giles, Gordon c., April 1967.
Barrier Glacier Investigations and Observations
in Connection with water Power Studies. USGS
rough draft report.
Jackson, Bruce L., March 1961.
Potential Water Power of Lake Chakachamna, Alaska.
USGS open file report.
Johnson, Arthur, January 1950.
Report on Reconnaissance of Lake Chakachamna,
Alaska. USGS.
Lamke, Robert, March 1972.
Floods of the Summer of 1971 in south-Central,
Alaska. USGS open file report.
United States Bureau of Reclamation, 1952.
Reconnaissance Report on the potential
Development of water Resources in the Territory
of Alaska.
.
United States Bureau of Reclamation, 1962.
Chakachamna Project, Alaska. status Report.
3-44
r L
f
L
L
\
_j
J
-<'
·i'
...
"' J " <
I
j
+
4 0 4 8 MILES ~~~'I;;;;;;;;;;;;;;;;;;;!
SCALE : 100= 4 MILES
1.) TOPOGRAPHY IS FROM USGS
QUADRANGLE MAP.S
Z.}HORIZONTAL (JRIO IS UNIVERSAL·
TRAJ.ISVERSI: MERCATOR PROJEi.C7"/0IJ,
19Z7 IJORTH ANIEi.RICA!J DATUM.
!J.)VERT/CAL OATUM IS MEAN LOWER
LOW WATER.
,.
r,
I
L
~ -
l '
1 'b
L
[
r~
United States Department of the Army, Corps of
Engineers, 1950
survey report on Harbors and Rivers in Alaska.
Interim Report No. 2, Cook Inlet and Tributaries.
3-47
HYDROLOGICAL
AND
POWER STUDIES
\ -
r .
I i l_/
4.0 HYDROLOGICAL AND POWER STUDIES
4.1 Introduction
River flow records from a gaging station are usually
accepted as the best indicator of future runoff from a
drainage basin. The longer the period of record is,
the more reliable it is assumed to be in forecasting
future runoff. For Chakachamna Lake, the records of a
gage located near the lake outlet cover only a
relatively short period of time, May 1959 to September
1972. During that time some periods occurred during
which flow rates were not obtained, reducing the
continuous record to a period dating from June 1959 to
August 1971.
There are no records of inflow to Chakachamna Lake,
and since that information is needed to perform
reservoir operation and power studies, inflows were
calculated for the continuous period of record by
reverse routing of outflows and making appropriate
adjustments for changes in water levels. Calculated
inflows for the 11 calendar years 1960 through 1970
were used in the power studies conducted during 1981
for Alternates A, B, C and D.
I
In order to develop a longer series of inflows to
Chakachamna Lake, the lake inflows were statistically
correlated with hydrometeorological records from other
stations. Using the resulting correlation, inflows
were calculated to produce a total period of 31 years
of recorded and synthesized records. That 31-year
sequence was used to determine the energy-generating
potential for the recommended project, Alternative E,
during the studies conducted during fiscal year 1982.
4-1
4.2 Historical Data
Hydrometeorological data from several stations in the
Cook Inlet Basin were used for the derivation and
extension of estimated lake inflow records.
Streamflow records included the following furnished by
U. s. Geological Survey:
Station No.
15294500
15284000
15284300
15292000
Description
Chakachatna River near Tyonek
(the lake outlet gag e)
Matanuska River near Palmer
Skwentna River near Skwentna
Susitna River at Gold Creek
Gaging Station No. 15294500 is located on the right
bank of the Chakachatna River close to the outlet of
Chakachamna Lake. The gage records include 13 years
and 5 months from May 21, 1959 to September 30, 1972.
The gage however, was destroyed by a lake outbreak
flood on August 12, 1971 and the records between that
date and June 20, 1972 are estimated rather than
recorded flows. Thus, the period of actual record
extends only from May 21, 1959 to August 12, 1971 and
from June 20, 1972 to September 3 0, 197 2.
Furthermore, during that period, several of the
winter-month flows were estimated because of icing
conditions and instrument failure. Inaccurate winter
records are not a serious engineering concern, because
only ll% of the average annual flow normally occurs
during the seven months from November through May.
4-2
,,
(
[
[
L
L
L
r·
L
L
L
!"'
r
l
~~
r~
[j
bi
L
L~
~ -
L
f
I__
{
L
L,
L
4.3
+n addition to the streamflow data, records of the
water surface elevation at Station No. 15294500 were
also obtained from the u. S. Geological Survey in
Anchorage.
Available meteorological data consist of daily
temperature and precipitation data obtained from the
U. S. National Oceanic and Atmospheric Administration,
National Climatic Center, Ashville, N.C. for stations
at Kenai, Anchorage, and Sparrevohn.
The locations of these three meteorological stations
are shown on Figure 4-1. A bar chart showing the
periods of record for these stations is plotted on
Figure 4-2.
Derived Lake Inflows
Chakachamna Lake with its surface area of about
26-square miles stores runoff and provides natural
regulation of flow to the Chakachatna River. In order
to derive a record of inflows to the lake, the
regulating effects of the lake were removed from the
outflow records using a reverse routing procedure
which uses the basic continuity equation
It -ot = L1s
Where
It is the inflow volume during month t
Ot is the outflow volume during month t
6 s is the change in lake storage during month t
For all practical considerations, the Chakachatna
River near Tyonek gage is, in effect, located at the
lake outlet and field observations confirmed that gage
4-3
4.4
readings closely represent the lake water-surface
elevation. Hence, it was assumed for the reverse
routing computations that the two were the same.
Evaporation, seepage and other losses of water from
the lake were assumed to be small and effectively
compensated for by direct precipitation onto the lake-
surface.
The lake stage-storage curve used in the computations
is shown on Figure 4-3. This is based on data
measured by the USGS and recorded on the USGS maps
Chakachatna River and Chakachamna Lake Sheets 1 and 2,
dated 1960.
Average monthly inflows were calculated for the period
June 1, 1959 through August 31, 1971, and are
presented in Table 4-1. The calculated inflows for
the 11 calendar years January 1, 1960 through December
31, 1970 were used in the power studies for Alternates
A, B, C and D of the project layouts during 1981.
Synthesis of Long-Term Lake Inflows
In order to develop a long-term estimate of
energy-production, methods for extending the inflow
record were investigated. Transposition of records
from other rivers in the region, correlation with
meteorological data from nearby long-term stations,
and combinations of both, were studied using
regression analysis.
4-4
J l
r (
I
I .
r~
[~
l ,
l
[_
i_
'~ ! .
.,--,.,,
• '-SPARREVOHN
::r:: ....::
t:l
!;d
0 ~
1-zj ~ t""o H O!;d :,. <;') no i 1 .. 1> .. c::: >t"' ~ ~0 J ( . ; He;) ~ ~ OH i ; ; zn ; I Ul~ ...... .
! • I
Ul
~ i I
~ I ~ I
H I • 0 I 5 z
--.--,.
Chakachatna River Jun 59 Sept 72
At Lake Outlet ]·
Matanuska River May 49 -Sept 73
At Palmer I J
Susitna River Aug 49 Sept 80
At Gold Creek
Skwentna River Oct 59 Sept 80
Near Skwentna
Temp. & Precip. Aug 48 Dec 80
At Kenai
Temp. & Precip. Nov 53 De·c 80
I At Anchorage
Temp. & Precip. July 51 Dec 70
~
!:=' At Sparrevohn
~
~~
~1-i
tzj Ht>:l
I
00 H !:='~
I -~ tllO 1960 1970 t"' 1950 1980 00
tzjC')
~ H
I '~ ~ ·--~
N
0
~til ~
1-i
H
0 z
til
~
~
r:tl
~
~
r:tl
(/)
~ ~
I ~ ~
II ~ ~ i'
)
z
0
H
E-1
·~ :>
r:tl
~
r:tl
\
AREA IN THOUSANDS OF ACRES
~8 26 24 22 20 18 16 'l4 12
1260
1210
1160
1110
·r-----J -
'
1060
10 8 6
--~
~
4
I
1
i . I
r
2 6
' -~-t----
i
// \ 1010r---;-----+------r----;-~~------~---~---+4----~---4-----+------~~4-----+~~ CAP<C~0 I \
960~--4-----+------~~4-----+----~--4----+---4-~---4----~------~---4-~~~~
910 ' //. i . . i. i \AREA
i y" ""~i 860~--~----+------r----4-----+-----r----4-~-+~--~--4-~-+------~---4-----+---~
s1o / "'K v I ~~-... ~~ •
760 ' ~
0 1000 2000 3000 4000 5000 6000 70.00
CAPACITY IN_ THOUSANDS_ OF __ ACRE-:FEET .
CHAKACHAMNA
LAKE
AREA & CAPACITY DATA
ELEV. AREA CAPACITY ·
M.S.L. · IN ACRES ACRE FEET . -
760 0 0
765 810 2,025
770 1,300 7,300
780 2,690 27,200
800 5,670 111,000
20 7,320 241,000
40 8,270 397,000
60 9,280 572,000
80 10 ;400 769,000
900 11 ,590 988,000
20 11 '960 1,224,000
40 12,320 1,467,000
60 12,650 1,717,000
80 12,980 1,973,000
1000 13,280 2,236,000
20 13,520 2,504,000
40 13,740 2,776,000
60 13,960 3,053,000
80 14-,170 3,335,000
1100 14,390 3,620,000
20 14,620 3,910,000
.40 16,100 4,218,000
42 16,780 4,250,000
60 18,250 4,572,000
80 19,900 4,953,000
1200 22,956 5,382,000
20 24 '1 04 5,852,000
40 26,038 6,354,000
CHAKACHAMNA LAKE
LAKE STAGE-AREA AND CAPACITY
FIGURE 4-3
~-
1
TABLE tt..: 1
LAKE CHAKACHAMNA INFLOWS (cfs)
YEAR JAN FEB "'AR APR MAY JUN JLY AUG SEP OCT 'IIOV DEC MEAN
1959 9459. 1031\llo 11731. 3662. 13 70. 654. 5 08.
1%0 400. 307. 267. 393. 3637 0 61137. 11209. 9337. 3145. 1'139. 799. 870. 3220.
l%1 1\11. 589. 470. 346. 1 ~ 81. 7983. 12808. 10699. 6225. 1586. 6lt3o 696. 3767.
1962 633. 541. 4 71. 47(1. 1265. 7925. 13149. 10411. 55'12. 1197. 1!63. 613. 359C.
1%3 496. ~·'i 7. 315. 337. 1801. '1735. 13249. 12208. 58'17. 2056. 930. 710. 3587.
1964 364. 435. 332. 477. 11130. 8093. 10700. 117'}8. '1246. 12'15. 909. 662. 3lt2tt.
1965 41q. 219. 331. 398. 1286. 3490. 13C46. 10516. 10802. 2114. 597. 466. 36'11. ""' 1966 31l8o 336o 350. 410. 11!93. 8072. 10303. 997'1. 6608. 1953. 910. 313. 3'1~9. I
I-' 1967 531. 449. 304. 1180. 2'130. 8761. 14931. 15695. 6191. 2040. 1215. 571. '1473.
I-' !968 534. 510. 467. 630. 2996. 71:100. 13117. 11257. 27"93. 976. 689. 612. 3532.
1%9 485. 486. 500. 652. 19'1'1. 9271. 12510. 7297. 2793. 3057. 1215. 5'11. 3396.
1970 497. 5 04. 550o 899. 2265. 670'J. 10360. 7966. 2734. 1359 •. 7'12. 460. 2"129.
1971 394. 441. 513. 1275. q ·] 63. 12672. 13f.95. 16680.
MEAN 5il2o 431. 413. '597. 2241. 71138. 12261. 11215. 5049. 1699. 664. 585. 3606.
Examination of the inflows to Chakachamna Lake in
Table 4-1, indicated that, for this watershed, the
hydrological year (water year) should be defined as
the period from May to April to minimize the overall
basin-storage effects. The majority of the lake
inflow, 93% of the annual runoff volume, occurs during
May through October, while flow recession starts in
November. Flows recorded at the lake outlet from
November to May were, in general, estimated by USGS
personnel using personal judgment because ice cover
prevented proper functioning of the stage recorder
during that period. The accuracy of the recorded
winter streamflow is, therefore, questionable, but
estimated total outflow volume during the low-flow
winter months is thought to be reasonable. Because of
their different hydrologic characteristics, it was
decided that regression analyses should be performed
separately for the periods, May to October, and
November to April. In so doing, the less-accurate
monthly-flow estimates for the winter period would not
unduly influence calculations for flows during the
remainder of each year.
The initial selection of independent variables to be
used in the regression analyses was based on the
lengths of the available hydrometeorolog ic records in
the region, as well as the potential physical
relationship with the inflow regime of Lake
Chakachamna. Since Chakachamna Lake is glacially-fed,
\
a heat-input index, such as monthly degree-days above
32°F recorded at Kenai and Anchorage, could be an
important independent variable. Monthly streamflow
records from nearby watersheds which are considered to
have hydrologic characteristics similar to that of the
4-12
r '
r ! r
[
L
L
r
i
l
r,
Chakachamna basin were also incorporated in the
study. These include the streamflows of Matanuska
River at Palmer, Susitna River at Gold Creek and
Skwentna River near Skwentna. In addition, monthly
precipitation at Kenai and Anchorage were also
considered. The final selection of the independent
variables used for the lake-inflow synthesis was based
on the results of the preliminary analyses.
The final regression analyses were performed
systematically using different combinations of the
pre-selected independent variables in a step-wise
regression-analysis program (Bechtel TM 750). The
regression equations obtained were evaluated on the
basis of probable physical relationships to
topographic, meteorological and hydrologic conditions
as well as the computed level of statistical
significance of the correlation. It was found that
for both the high and low-flow periods, May to October
and November to April respectively, the monthly
streamflow records for the Matanuska River at Palmer
correlate well with the historical monthly Chakachamna
lake inflows. The regression equations obtained were:
May-October:
November -April:
QLake = 595.0 + 0.8967 QPalmer
Q k = 265.3 + 0.4597 Qp 1 La e a mer
Correlation coefficients for these two regression
equations were found to be 0.89 and 0.40 respectively
and are well within the 95 percent significance
level. However, the Matanuska gage was discontinued
in September of 1973. Another set of regression
equations was therefore required for the flow
synthesis for the period after September 1973. New
4-13
correlation studies were performed. It was found that
recorded streamflows for Skwentna River near Skwentna
were a good substitute for those at the Matanuska
gage. The regression equations obtained were:
May -October: QLake = 674.67 + 0.5233 QSK
November -April: QLake = 283.27 + 0.2690 QSK
The correlation coefficients for these two regression
equations were found to be 0.73 and 0.45 respectively
and are well within the 95 percent significance level.
The correlation coefficients for the regression
equations for the low-flow season are relatively low.
This was to be expected, because, as discussed
earlier, streamflow values for this period were known
to be inaccurate since they had to be estimated by
personnel from the U.S. Geological .Survey on the basis
of regional streamflow aata and/or personal judgment
because of frequent malfunctioning of gages during
winter. However, the streamflow volume in this period
represents only about 7 percent of the total annual
runoff volume. Because the operation study used
monthly flow volumes, inaccuracies inherent in the
flow synthesis for the winter months do not
significantly affect the overall accuracy of the study
and the respective regression equations are therefore
regarded as acceptable for use in the derivation of
the long-term streamflow record. Table 4-2 presents
the lake inflows synthesized by using these equations
and the reverse-routing procedure. The 31 year
sequence of inflows includes the June 1959 through
August 1971 inflows calculated by reverse-routing of
outflows plus the May 1949 through May 1959 and the
4-14
l
[
{
[
[
[
[
{
[
t
r
L
L
L
L
PROJECT 14879001
INFLOVJS TO THE LAKE IN CFS
YEAR MAY JUNE JULY AUG
1 4513. 10728. 15220. 11615.
2 2055. 8572. 13194. 10548.
3 3801. 10719. 13095. 8831.
4 2027. 8204. 12575. 9431.
5 3992. 13247. 13355. 10808.
6 3434. 9002. 12091. 12046.
7 2193. 6826. 12996. 9983.
8 2936. 7475. 14601. 10235.
9 4393. 14817. 13149. 10405.
10 2496. 9930. 10163. 8691.
11 3120. 9459. 10388. 11731.
12 3637. 6837. 11209. 9337.
13 1881. 7983. 12808. 10899.
14 1265. 7925. 13149. 10411.
15 1801. 4735. 13249. 12208.
16 1830. 8093. 10700. 11798.
17 1286. 3490. 11633. 11929.
""" 18 1893. 8072. 10303. 9974. I
1-' 19 2030. 8761. 14931. 15695.
lJ1 20 2996. 7808. 13117. 11257.
21 1948. 9271. 12478. 7297.
22 2265. 6789. 10360. 7986.
23 4063. 12672. 13695. 16680.
24 3468. 8228. 13490. 9263.
25 2131. 7457. 8850. 7809.
26 4215. 6248. 6781. 6159.
27 4784. 10649. 10889. 6802.
28 5283. 8587. 8304. 6494.
29 5335. 19864. 13898. 11224.
30 5387. 7917. 10146. 7865.
31 6776. 8514. 8958. 9157.
MEAN 3201. 8996. 11928. 10147.
MAX 6776. 19864. 15220. 16680.
MIN 1265. 3490. 6781. 6159.
[ !
TABLE 4-2
-'
CHAKACHAMNA PROJECT OPERATION STUDY
H/H,H&CF,BECHTEL CIVIL&MINERALS INC .. SF.
·ALASKA POWER AUTHORITY
ALTERNATIVE E: MCARTHUR SHORT TUNNEL. WITH
SEPT OCT NOV DEC JAN
6305. 2689. 802. 636. 542.
4521. 1761. 569. 532. 495.
8635. 3216. 842. 699. 630.
3562. 2712. 865. 642. 523.
4505. 2002. 629. 550. 527.
6075. 2787. 755. 619. 578.
5068. 1988. 595. !332. 504.
5940. 2053. 583. 565. 569.
6910. 2707. 793. 562. 569.
3452. 1896. 526. 483. 426.
3662. 1370. 654. 508. 400.
3145. 1439. 799. 870. 877.
6225. 1586. 843. 696. 633.
5542. 1197. 863. 613. 498.
5847. 2086. 930. 710. 364.
4246. 1245. 909. 662. 419.
10802. 2114. 597. 466. 388.
6608. 1953. 910. 313. 531.
6191. 2040. 1215. 571. 534.
2793. 976. 689. 612. 485.
2793. 3057. 1215. 601. 497.
2734. 1359. 742. 460. 394.
5075. 3181. 1090. 736. 581.
5012. 2396. 679. 514. 495.
2794. 2527. 740. 623. 558.
6850. 3059. 909. 530. 498.
5107. 3136. 814. 622. 544.
4947. 3917. 1058. 1055. 1044.
6059. 3709. 922. 700. 609.
4513. 3258. 708. 701. 597.
4572. 4471. 1412. 882. 762,
5177. 2383. 828. 621. 551.
10802. 4471. 1412. 1055. 1044.
2734. 976. 526. 313. 364.
-J
DATE 11783 PAGE 3
FISH· RELEASES
FEB MAR APR AVEYR CALYR
488. 493. 541. 4548. 1950
472. 450. 631. 3650. 1951
495. 467. 510. 4328. 1952
477. 477. 641. 3511. 1953
472. 458. 541. 4257. 1954
507. 466. 487. 4071. 1955
475. 449. 496. 3509. 1956
536. 505. 598. 3883. 1957
510. 489. 675. 4665. 1958
468. 44'3. 526. 3292. 1959
307. 267. 393. 3522. 1960
589. 470. 346. 3296. 1961
541. 471. 470. 3753. 1962
357. 315. 337. 3539. 1963
435. 332. 477. 3598. 1964
219. 337. 398. 3405. 1965
336. 350. 410. 3650. 1966
449. 384. 880. 3523. 1967
510. 467. 630. 4465. 1968
486. 500. 652. 3531. 1969
504. 550. 899. 3426. 1970
441. 513. 1275. 2943. 1971
531. 492. 479. 4940. 1972
492. 480. 586. 3759. 1973
526. 501. 554. 2923. 1974
485. 485. 489. 3059. 1975
524. 498. 625. 3750. 1976
773. 606. 606. 3556. 1977
537. 509. 558. 5327. 1978
562. 547. 713. 3576. 1979
718. 647. 810. 3973. 1980
491. 465. 588. 3781.
773. 647. 1275. 5327.
219. 267. 337. 2923.
4.5
September 1971 through April 1979 inflows calculated
from the regression equations.
Power Studies·
During the 1981 project studies four basic alternative
project layouts were developed and designated
Alternatives A, B, C and D as described in Section 3.3
of this report. Power studies also performed during
1981 for these four alternates were based on the ll
complete calendar years (January l, 1960 through
December 31, 1970) of Chakachamna Lake inflow .set
forth in Table 4-l. During the 1982 studies, the
recommended Alternative E, also described in Section
3.3, was developed, as was the 31 year sequence of
inflow to Chakachamna Lake which was used during the
1982 power studies for each of the alternatives A
through E. The power operation studies were performed
to determine generated firm and secondary energy, flow
releases, and the fluctuations in the wate.r surface
elevation of Chakachamna Lake for a range of installed
capacities for each of the five project alternatives.
The studies were made using a computer program that
performs sequential routing of the derived monthly
inflows while satisfying power demands, projected
in-stream flow require~ents, and physical system
constraints. Power demands were in accordance with a
plant load factor of 0.5, and the monthly variations
in peak demand listed in Table 4-3. As advised by
APA, these demands are those being used in the
evaluation of sources of power alternative to that of
the Chakachamna Hydroelectric Project.
The in-stream flow requirements, listed in Table 4-4,
represent provisional minimum monthly flows to be
4-16
r
\
I
(
L
r.
lc
TABLE 4-3
MONTHLY PEAK POWER DEMANDS USED IN POWER STUDIES
MONTH
January
February
March
April
May
June
July
August
September
October
November
Decemb~r
MONTHLY PEAK DEMAND
(Percent of Annual Peak Demand)
92
87
78
70
64
62
61
64
70
80
92
100
Source: Susitna Hydroelectric Project Development Selection
Report Appendix D, Table D.l (Second Draft, July 1981)
4-17
•
TABLE 4-4
PROVISIONAL MINIMUM RELEASES FOR INSTREAM FLOW IN
CHAKACHATNA RIVER DOWNSTEEAM FROM CHAKACHAMNA
LAKE OUTLET FOR USE IN POWER STUDIES
MONTH MC ARTHUR TUNNEL CHAKACHATNA TUNNEL MCARTHUR TUNNEL
DEVELOPMENT DEVELOPMENT DEVELOPMENT
ALTERNATIVE B ALTERNATIVE D ALTERNATIVE
(CFS) * (CFS) (CFS) *
January 365 30 365
February 343 30 357
March 345 30 358
April 536 30 582
May 1,094 30 1,094
June 1,094 30 1,094
July 1,094 30 1,094
August 1,094 30 1,094
September 1,094 30 1,094
October 365 30 365
November 365 30 365
December 360 30 363
* Criteria used to determine fish instream flow release:
April through September -1094 cfs or inflow to lake
whichever is less
October through March -365 cfs or inflow to lake
whichever is less
4-18
E
r
L
r
r-
L
L
l
r L
L
L
L
r
{
[ ~
L
[
[
r-
E
[
L
E
r
4.6
released into the Chakachatna River near the lake
outlet as further discussed in Sections 7.3.2 and
7.3.3 of this report.
The physical system constraints, set forth in Table
4-5, are the overall plant efficiency, tailwater
elevation, and head loss for the hydraulic conduits.
In the power studies water was drafted from lake
storage whenever the monthly inflows were insufficient
to meet the power demand. It was assumed that spill,
or discharge of water from the lake into the
Chakachatna River in excess of the tentative instream
requirements would occur whenever the lake water level
exceeded elevation 1,128 feet, for alternatives A
through D, and 1155 for alternative E. The secondary
energy -is that which can be generated by plant
capacity in excess of that needed to meet the load
carrying capability, using water which otherwise would
have spilled.
For each of the alternatives considered for
development of the projecti a range of installed
powerplant capacities was tested in order to establish
the installed capacity that would make the most use of
all water available for power generation without
drawing the lake level below a given minimum
elevation. This minimum was taken as elevation 1,014
feet for alternatives A through D and elevation 1,085
for alternative E respectively. The lake was assumed
to be full at the beginning of each run.
Results
The results of the power studies listed in Table 4-6
show that, on the basis of the 11 calendar years of
4-19
TABLE 4-5
POWERPLANT SYSTEM CONSTRAINTS FOR
ALTERNATIVE PROJECT DEVELOPMENTS
ALTERNATIVE PLANT PLANT AVERAGE HEAD LOSS IN
EFFICIENCY FACTOR TAILWATER HYDRAULIC CONDUITS
(%) ELEVATION (FT.)
(FT.)
A 85 0.50 210 0.0000024 X Q2
B 85 0.50 210 0.0000024 X Q2
c 85 0. 50 400 0.0000028 X Q2
D 85 0.50 400 0.0000028 X Q 2
E 85 0.45 210 0.0000024 X Q2
Note: Q = Flow in cubic feet per second.
4-20
[-
[
r
[
[
r
[
r
r
L
r
L
L
r--'·
l. ' J .-
TABLE 4-6
POWER STUDIES SUMMARY
Development Installed Average Annual Energy Average Annual Flow
Alternative Capacity F1rm Secondary Power D1version Provisional
A
B
c
D
E
Note:
.(MW) (GWh) (GWh) (CFS) Instream (CFS)
400 1752 153 3322 0
330 1446 124 2701 679
300 1314 139 3230 0
300 1314 130 3239 30
330 1301 290 2274 685
Period of record January 1, 1960 to December 31, 1970
Average annual inflow to Chakachamna Lake 3547 cfs (2.6 million AF)
Alternatives A, B -Development via McArthur tunnel
Alternatives C & D -Development via Chakachatna tunnel
Period of record May 1, 1949 to April 30, 1979
Average annual inflow to Chakachamna Lake 3781 cfs (2.7 million AF)
Alternative E -Development via McArthur Tunnel
-
Power diversion flows are the flows needed to meet firm energy requirements.
inflow, and with the parameters used in the studies,
the optimum development via the McArthur Tunnel could
support a powerplant of 400 MW installed capacity when
all controlled water is used for power generation as
in Alternative A. At 50% plant factor, this provides
an average annual 1,752 GWh of firm energy. The
provisional instream flow requirements of Alternative
B discussed in Section 7.3.2 of this report represent
about 19% of the average annual flow in the
Chakachatna River during the period of record. If
that amount of water is reserved for instream flow,
the installed capacity of powerplant that could be
justified at the McArthur River would be reduced to
330 MW and the firm average annual energy would be
1446 GWh.
For development via the Chakachatna tunnel, the optimum
power development using all controlled water for power
generation, Alternative c, would have an installed
capacity of 300 MW and firm annual average energy
would be 1314 GWh for a 50% plant factor. The
provisional minimum instream flow reservations in
Alternative D, discussed in Section 7.3.3 of this
report, represent less than 1% of the average annual
flow during the period of record. Thus, the installed
capacity and firm energy in Alternative D for
practical purposes would remain the same. There would
however be about 15% reduction in the amount of
secondary energy that could be generated.
Alternatives A through D cannot firmly support the
capacities determined from the 11 years of inflow
during the 1981 studies and the recommended
Alternative E cannot firmly support 330 MW at 50%
plant factor due to two consecutive dry years
(1973-74) that occur during the 31 years of
4-22
[~ -
[ ~~
f
(
[
l .
r
[_
[ '
r·
['
r:
r .
[ ~
L
I
L
r
l
l_
r
r
~
r
[
r~
[
r
r
[~
[
t
[~
t
[
r
L
l~~
L
[
4.7
correlated lake inflow. These two years do not occur
in the 11 calendar years (1960-1970) of inflow used in
the 1981 power studies for Alternates A through D and
some additional analyses should be made in future
studies of the project. Using the 31 years of inflow,
and 330 MW installed capacity, Alternate E could
produce 1301 GWh at 45% load factor.
Variations in Lake Water Level
The variations in lake water-surface elevation
calculated at the end of the month during the course
of the power studies for each of the five alternatives
and cases listed in Table 4-6 are shown in the
computer output included in the Appendix to Section
4.0, and are also plotted in Figures 4-4 and 4-5.
4-23
I; l-·.
I-
w w u.
z
2
0
~ ~
_J
w
uJ
'{.
<f.
_J
ll40
IIZO
[\
., 100
1080 ~
10~0
\040
IOZO
IOOO
I9G:.O
v
n ~· ~
~ \ \• ... ;
6>\
I
~ ~ ~A {\ C\'
'
I
I
'
I
\ ~\
\, \ \ I ~; ~ I I \\ I v ~I
\ . ' v
-.J \ I
\1
'?> t;.+ ~5 (Q(p ~7 ~8
C ALE."-! DAR YEAR
. ------AL\E..RNAT\VE. A
A.LTE.RNAT\VE. e
-,
n n
\~
\\ ··-;~ \ I I \J \\
~
1970
t-w w u.
z
z
0 -~ :>
ill
..J
u1
w
~
<(
_I
----l r--:
l,
I \40
r\ f\ .~ A ~ D n n II 2.0 -----1-----t-----
I\
II oo
1080 t
10~0 \ \ \ \ \ ~ \ l040 'J \ ~ '
l020
rooo+---~r----+----~----+-----~---4----~----4-----+---~
19<00 ~I ~2 ~3 ~4 ~5 ~~
CALENDAR Yt=:AR
ALTERNAT\V E. C
------ALTE.RNAT\Ve. 0
61 1970
----.
!
GEOLOGIC
INVESTIGATIONS
r :
I ~
L
b
t
L
L
L
L
5.0
5.1
5 .1.1
GEOLOGIC INVESTIGATIONS
Scope of Geologic Investigations
Technical Tasks
The scope of the geologic investigations planned for the
Chakachamna Hydroelectric Project Feasibility Study
' includes five technical tasks:
(1) Quaternary geology,
(2) Seismic geology,
(3) Tunnel alignment and powerplant site geology,
(4) Construction materials geology, and
(5) Road and transmission line geology.
These tasks were identified and scopes defined so that,
upon completion of the investigations, the information
needed to assess tpe potential impact of a range of
geologic factors on the feasibility of the proposed
project will be available. If the Chakachamna Project is
judged to be feasible, additional geologic investigations
will be required subsequent to the feasibility study in
order to provide the detailed information appropriate for
actual design.
At the feasibility level, it is appropriate to gather
information regarding the general character of the
geologic environment in and around the project area, with
particular attention to geologic hazards and the geology
... .
5.1.1.1
of specific facilities siting locations. The Chakachamna
Project, as presently conceived, does not include
facilities such as large dams that would increase the
risks associated with geologic hazards that are naturally
present in the project area. The geologic tasks were
planned in recognition of the above and were designed to
focus on geologic factors that may influence the
technical feasibility, the operating reliability, and/or
the cost of the proposed project.
The work on the geology tasks began in August 1981 but
the majority of the work will take place in future
feasibility level investigations. This report includes a
summary of the work planned for the geologic investi-
gations (Section 5.1.1) and the schedule for each geology
task (Section 5.1.2), summaries of the work completed for
the Quaternary geology (Section 5.2) and seismic geology
(Section 5.3) tasks, and some preliminary commentary on
geologic conditions in the project area in Section 7.0.
The commentary and any tentative conclusions presented
here are subject to revision as the project work
continues in the future.
Quaternary Geology
The Quaternary geology task was designed to include an
assessment of the glaciers and glacial history of the
Chakachamna Lake area, an investigation of the Mt. Spurr
and associated volcanic centers, and a study of the slope
conditions near sites proposed for project facilities.
A study of the glaciers was judged to be appropriate
because:
5-2
r
L
r ·l__.
[
t=
I
L
r
\.. -
L
L
(1}
( 2)
movement of the terminus of Barrier Glacier
influences the water level in Chakachamna Lake
and any structures to. be built near the lake
outlet;
the possibility that changes in the terminal
position of Blockade Glacier could alter the
drainage at the mouth of the McArthur River
Canyon; and
(3) questions regarding the influence of other
glaciers in the study area on the size and
hydrologic balance of Chakachamna Lake.
In addition, knowledge of the ages of geomorphic surfaces
is important to the assessment of possible seismic
hazards and such knowledge depends on an understanding of
the glacial geology.
The simple presence of Mt. Spurr, an active volcano, at
the eastern end of Chakachamna Lake provides a clear
rationale for investigating the volcanic history and
potential volcanic hazards of the project area. Of
particular interest is the possibility that lava flows or
volcanic mudflows (a possibility increased by the glacier
ice on Mt. Spurr) could enter the lake and produce large
waves, an increase in lake level, and/or a change in
conditions ~t the lake outlet or on the upper reaches of
the river. In addition, the possible impact of a dark,
heat-absorbing layer of volcanic ejecta on the glaciers'
mass balance, and thus the lake's hydrologic balance is
of interest.
5-3
5.1.1.2
Chakachamna Lake, Chakachatna River Canyon, and McArthur [.
River Canyon are all bordered by steep slopes that may be
subject to a variety of types of slope failure. A large
landslide-into the lake could change the usable volume of
water stored in the lake and could alter conditions at
the proposed lake tap and at the natural outlet from the
lake. Potential outlet portal and surface powerhouse
sites in the river canyons are all on or immediately
adjacent to steep slopes. Both the integrity of and
access to these facilities could be impaired in the event
of landslide and rockfall activity.
Because of the concerns indicated above, the Quaternary
geology task was designed to investigate the timing and
size of past glacial fluctuations, the frequency and type
of volcanic activity, and the slope conditions in order
to provide an estimate of possible future events that
could influence the costs and operating performance of
the proposed hydroelectric project. In addition, this
task should provide information regarding the possibility
of the project destabilizing the lake outlet by producing
or allowing changes in Barrier Glacier.
Seismic Geology
The seismic geology of the Chakachamna Lake area is of
interest because southern Alaska is one of the most
seismically active areas in the world. Potential seismic
hazards of direct concern to the proposed hydroelectric
project include surface faulting, ground shaking,
seismically-induced slope failure, lake seiche, and
liquefaction. Specifically, the seismic geology task was
designed to investigate the possibility of active faults
in the immediate vicinity of the proposed facilities, to
5-4
r ~
I
I ·,
I .
I .
i
L
L
,
~ !
l_
L
L
l
t
L~
t
c
I
L
t
L
[
assess the location and activity of regional faults
(e.g., Castle Mountain, Bruin Bay), and to estimate the
type and intensity of seismic hazards that may be
associated with these faults and with the subduction zone.
The seismic geology investigations were planned to maxi-
mize the use of existing information by following a
sequence of subtasks that become increasingly site
specific as the work proceeds. The primary elements in
the sequence are:
0 literature review
0 remote sensing imagery analysis
0 field reconnaissance
0 low-sun-angle air photo acquisition and analysis
o detailed field studies
The data produced by the above sequence is required to
assess directly the surface faulting hazard and for input
to the probabilistic assessment of ground motion para-
meters.
In order to develop approximate ground motion spectra for
the various elements of the project, existing ground
motion information developed for other projects in
southern Alaska will be reviewed and modified, as
appropriate. A simplified evaluation of the liquefaction
potential of the transmission line alignment should also
be carried out.
5-5
5.1.1.3
5.1.1.4
Tunnel Alignment and Powerplant Site Geology
The scope of work for this task should be based on the
need to assess the feasibility of constructing a lake tap
in Chakachamna Lake, a long tunnel, and a powerhouse as
the primary components of the proposed hydroelectric
development. Because of the steep mountainous terrain
above the tunnel alignment, the tunnel feasibility study
should be planned around the mapping of bedrock exposures
in the mountains and production of a strip map; drilling
would be limited to the powerhouse site during the feasi-
bility investigations. The strip map should focus on
those bedrock characteristics that determine the
technical and economic feasibility of tunnelling.
Geophysical techniques should be used to assess the lake
bottom bedrock and sediment characteristics at and near
the proposed lake tap and subsurface conditions at the
proposed powerhouse site.
All reasonably possible surface powerplant and outlet
portal sites are on or adjacent to high, steep slopes.
Hazards such as landslides, rockfalls, and avalanches,
which are a particular concern in seismically active
areas, should be assessed during the feasibility study.
Construction Materials Geology
The proposed Chakachamna Hydroelectric Project will, if
constructed, require aggregate for concrete, road con-
struction, and construction of the transmission line. In
addition, rockfill will be required for the low dike at
the lake outlet and boulder rip-rap may be required at
the outlet portal and outfall from the powerhouse. This
task should be planned to yield information about
potential
5-6 .
r
L
f .
!
( .
I •
l .
1 .
r .
( -
\
{
r:
r.
I"
'
f .
t
\~
(_
r ' ~-.
l"
\~
l
\
I
'
1
l
{
c
r'
L
~\
h
r
t
L
(
L
5.1.1.5
5 .1. 2
5.1.2.1
aggregate sources at the powerhouse-outlet portal site,
along the road, and along the transmission line alignment.
Road and Transmission Line Geology
Geologic considerations will be important in the
assessment of the road and transmission line routes.
This task will use aerial photograph analysis and
reconnaissance-level field studies in order to provide
information on the general character of the alignments.
The task plans should give particular attention to river
crossings, which may be subject to large floods, and to
wetland areas where special construction techniques may
be required.
Schedule
The 1981 geologic field program did not commence until
late August that year and was therefore relatively
limited in scope, covering only the Quaternary geology
and part of the seismic geology tasks. Future
investigations should concentrate on the remaining
geologic tasks as discussed below.
Quaternary Geology
All of the Quaternary geology field studies were either
of a regional nature or directed at targets that would
not vary as a function of final configuration of the
project facilities. Therefore, it was possible to
complete the field work planned for this task. Some
additional review of unpublished data, such as that held
by the u.s. Geological survey in Fairbanks, and
discussions with geologists who have worked in the
5.1.2.2
5.1.2.3
Chakachamna area remain to be completed. Although
several important implications with respect to the
proposed hydroelectric project have been identified and
some tentative conclusions may be drawn~ additional
analyses and discussions are needed before the
conclusions can be finalized.
Seismic Geology
As discussed in Section 5.1.1.2, the seismic geology task
is des~gned around a sequence of investigations, each of
which builds on the preceding ones. Because of this
characteristic, the seismic geology task demands a
certain amount of elapsed time and cannot be speeded up
by adding additional staff.
During 1981 it was possible to complete the literature
review, analysis of existing remote sensing imagery,
field reconnaissance, and the acquisition and initial
analysis of the low-sun-angle aerial photography. The
detailed field studies and ground motion assessment will
be conducted during future feasibility study work.
Tunnel Alignment and Powerplant Site Geology
No field investigations were conducted for this task in
1981 because the various tunnel alignment locations and
configurations to be studied were not identified prior to
completion of the 1981 field season. All of the geologic
and geophysical investigations planned for this task
should be completed during future feasibility study work.
5-8
l
f
I" '
I
I
r
1
(
l '
l,
l.
l
f L
5.1.2.4
5.1.2.5
5.2
construction Materials Geology
The work for this task will be conducted during future
feasibility study work.
Road and Transmission Line Geology
The work foi this task will be conducted during future
feasibility study work.
Quaternary Geology
The Quaternary, approximately the last 2 million years of
geologic time, is commonly subdivided into the
Pleistocene and the Holocene (most recent 10,000 years).
Although the Pleistocene is generally equated to the
glacial age and the Holocene with post-glacial time, such
a distinction is less clear in southern Alaska where the
mountains still contain extensive glaciers.
The Quaternary was a time of extreme and varied geologic
activity in southern Alaska. In addition to the
extensive glacial activity and associated phenomena, the
Quaternary was also a time of mountain building and
volcanic activity. The products of these and other
geologic processes that were active during the
Quaternary, and are still active today, are broadly
present in the Chakachamna Lake area. Although the
geologic investigations for this feasibility study
consider a broad range of topics that fall under the
general heading of Quaternary geology, this task was
planned to address three specific topics:
5-9
5.2.1
5.2.1.1
(1) glaciers and glacial geologyi
( 2 ) Mt. Spurr volcano; and
( 3 ) slope conditions.
In addition, the seismic geology task (Section 5.3) is
designed to focus on Quaternary and historic fault
activity and seismicity and is highly dependent on an
understanding of the ~lacial history o~ the area for
temporal data.
For the Quaternary geology task of the Chakachamna study,
field work consisted of a twelve-day reconnaissance
during whi~h all three primary topics of interest (above)
were studied. When combined with information available
in the open literature and that gained through
interpretation of aerial photography, the field
reconnaissance provides a basis for assessing the
potential impact of the glaciers, volcano, and slope
conditions on the proposed hydroelectric project.
Glaciers and Glacial Geology
Regional Glacial Geologic History
At one time or another during the Quaternary, glaciers
covered approximately half of Alaska (Pewe, 1975).
Previous investigations have demonstrated that the Cook
Inlet region has had a complex history of multiple
glaciation (Miller and Dobrovolny, 1959; Williams and
Ferrians, 1961; Karlstrom, 1964; Karlstrom and others,
1964; Trainer and Waller, 1965; Pewe and others, 1965;
5-10
r~
l .
(
\
[
L
L
t
Schmoll and others, 1972). The current understanding of
the region's glacial history is based on interpretation
of the morphostratigraphic record in association with
relative and absolute age dating and other Quaternary
studies. The complex history is recorded in glacial,
fluvial, lacustrine, marine, and eolian sediments that
have been studied primarily in their surface exposures
where they can be associated with specific landforms.
Although more recent work has led to modification and
refinement of Karlstrom's (1964) history of glaciation in
the Cook Inlet region, that work still provides a good
general overview and, except where noted, serves as the
basis for the following summary.
On at least five separate occasions during the
Quaternary, the glaciers in the mountains that surround
Cook Inlet have expanded onto the Cook Inlet lowlands
where they coalesced to cover much or all of the lowland
with ice. Evidence for the two oldest recognized
glaciations (Mt. Sus{tna, Caribou Hills) consists
dominantly of erratic boulders and scattered remanants of
till at high elevation sites around the margins of the
lowland. Evidence for the next glaciation, the Eklutna,
includes moraines and till sheets that demonstrate the
coalescence of ice from various source areas to form a
Cook Inlet piedmont glacier. The available evidence
suggests several thousand feet of ice covered virtually
all of the Cook Inlet lowland during these early
glaciations.
The next two glaciations, the Knik and the Naptowne,
correspond to the Early Wisconsin and Late Wisconsin
glaciations of the midwestern United States,
respectively. Thus, the Naptowne glaciation of the Cook
5-11
Inlet region correlates, in general,. with the Donnely
(Pewe, 1975) and McKinley Park (TenBrink and Ritter,
1980; TenBrink and Waythomas, in preparation) glaciations
reported from two areas on the north side of the Alaska
Range. During the Knik and Naptowne glaciations ice
again advanced onto the Cook Inlet lowland, but the ice
did not completely cover the lowland as it apparently did
during the earlier glaciations. Even at the glacial
maxima, portions of the lowland were ice free; such areas
were commonly the sites of large ice-dammed lakes that
have been studied in some detail (Miller and Dobrovolny,
1959; Karlstrom, 1964).
The maximum ice advance during the Naptowne glaciation is
recorded by distinct end moraine complexes located near
the mouths of the major valleys that drain the Alaska
Range and by moraines on the Kenai lowland. The moraines
on the Kenai lowland are of particular interest because
they were, at least in part, formed by the Trading Bay
ice lobe, which originated in the Chakachatna-McArthur
rivers area and advanced across Cook Inlet at the time of
the Naptowne maximum. Karlstrom (1964) reported on these
features on the Kenai lowland in some detail.
Karlstrom (1964) used a combination of radiocarbon dates
and relative-age dating techniques to develop a
chronology for the Cook Inlet glaciations. According to
Karlstrom, the Naptowne glaciation continued, although
with decreasing intensity, past the Pleistocene-Holocene
boundary (generally taken as being near 10,000 years
before present [ybp]), through the Climatic Optimum, to
the beginning of Neoglaciation (see Porter and Denton,
1967). Recent work on the north side of the Alaska Range
has produced a well-dated chronology for the McKinley
5-12
(
!
r (,
L
L
{
L
L
L
r·
l
c
r
L
L
t-
Park 9laciation (TenBrink and Ritter, 1980; TenBrink and
Waythomas, in preparation). That chronology shows major
stadial events at:
(1) 25,000-17,000 ybp (maximum advance at about
20,000 ybp);
(2) 15,000-13,500 ybp;
(3) 12,800-11,800 ybp; and
(4) 10,500-9,500 ybp.
Recognizing the differences in ice extent and other
factors between the Cook Inlet region and the north side
of the Alaska Range, the TenBrink chronology is probably
reflective of the timing of the primary Naptowne stadial
events. Dates from the Cook Inlet region proper have yet
to yield such a clear picture, probably because of the
greater complexity of the condition~ and thus the record
there.
Following the Naptowne glaciation (about 9,500 ybp by
TenBrink's chronology, as late as 3,500 ybp according to
Karlstrom, 9164), glacial advances in the Cook Inlet
region have been limited to rather small-scale
fluctuations that have extended only up to a few miles
beyond present glacier termini. Karlstrom (1964)
referred to these Neoglacial advances as the Alaskan
glaciation, which he divided into two distinct periods of
advance (Tustumena and Tunnel) and further subdivided
into three and two short-term episodes, respectively.
According to Karlstrom (1964) these Neoglacial events
range in age from approximately 3,500 ybp to historic
fluctuations of the last several decades.
5-13
5.2.1.2
Two points of particular interest regarding Neoglaciation
in Alaska emerged from the literature review:
( 1)
( 2)
the idea that " the youngest major advance
typically was the most extensive of the
Neoglaciation" (Porter and Denton, 1967, p. 187),
and
Karlstrom's (1964) suggestion that, at least in
the mountains around the margins of the Cook
Inlet region, there was no distinct hiatus
between the last small Naptowne readvance and the
first Neoglacial advance.
These points will be addressed in the following section.
Project Area Glacial Geologic History
The reconnaissance-level investigations conducted for the
Chakachamna study confirm the general picture for the
project area presented by Karlstrom (1964). The area
examined during the field reconnaissance is indicated on
Figure 5-l. Although a rather broad area was included in
the study area, most of the field work took place in the
Chakachamna Lake basin, along the Chakachatna River, and
on the southern slopes of Mt. Spurr.
Most of the study area was covered by glacier ice during
the maximum stand of the Naptowne-age glaciers. Based on
Karlstrom's (1964) work, it would appear that only high,
steep slopes and local elevated areas were not covered by
Naptowne ice. Within the area examined in the field, the
upper limit of Naptowne ice is generally clearly defined,
particularly in the area between Capps Glacier and
5-14
l
f
I
(
I
I
f
I
r
l
r
f
(
(
L
(
!
l -
f
L
{
t
l
1
\
I
/
I' I
)
\ l'
r
I
J
''-
J
I.
J
J
I
' .I
------=---
EXPLANATION
PLACE NAMES AND LOCATIONS WITHIN THE QUATI:RNARY GEOLOGY
RECONNAISSANCE AREA INVESTIGATI:D BY WOODWARD-CLYDE
CONSULTANTS DURING THE 1981 FIELD SEASON.
10 15
SCALE IN MILES
r
r
1
l
[
[
f
h
[1
[
f:
c
L
L
L
L
Blockade Glacier, at and east of the range front (Figure
5-l). In this area lateral moraines produced during the
maximum stand of Naptowne ice (25,000-17,000 ybp) are
distinct and traceable for long distances; younger
Naptowne lateral and terminal moraines are also present.
The largest area that was not buried by Naptowne ice and
which was observed during field reconnaissance is located
high on the gentle slopes east of Mt. Spurr, between
Capps Glacier and Straight Creek. The two older surfaces
(Knik and [?] Eklutna) observed in this area (Figure 5-l)
correspond well to the ideas presented by Karlstrorn
(1964).
Not only are moraines marking the Naptowne maximum
present, but a large number of moraines produced during
subsequent stadial advances or recessional stillstands
are also present. These features demonstrate that even
at the Naptowne maximum, ice from Capps Glacier and other
glaciers to the north did not coalesce with ice corning
from the Chakachatna canyon, except possibly near the
coast. The Chakachatna ice and that issuing from the
McArthur River Canyon and Blockade Glacier did join,
however, to produce Karlstrorn's (1964) Trading Bay ice
lobe. That ice lobe covered the alluvial flat that, at
the coast, extends from Granite Point to West Foreland.
From the present coast, the Trading Bay lobe (according
to Karlstrorn, 1964) extended across Cook Inlet to the
Kenai lowland.
The complex of moraines located between Blockade Glacier
and the Chakachatna River area allow one to trace the
slow retreat of Naptowne ice. As the Trading Bay lobe
retreated westward across the inlet and then across the
Trading Bay alluvial flats to the mountain front,
5-17
separate ice str~ams became distinct. As the Naptowne
ice continued to retreat up the Chakachatna Canyon more
and more individual glaciers became distinct from one
another. For example, Brogan Glacier (informal name,
Figure 5-l), separated from the Chakachatna River by a
low volcanic ridge, produced a recessional sequence that
is independent of that formed by ice in the Chakachatna
canyon. Such a sequence of features is less distinct or
absent for the other glaciers between Brogan Glacier and
Barrier Glacier.
Within the Chakachamna Lake basin, the evidence of
Naptowne and older glaciations is largely in the form of
erosional features and scattered boulders. Naptowne-age
till apparently occurs only in isolated pockets within
the lake basin and its major tributary valleys. The
Naptowne-age surfaces in the basin are mantled with a
sequence of volcanic ashes that averages two to three
feet in thickness. The solids are typically developed on
these volcanics rather than on the underlying
glacially-scoured granitic bedrock or till.
In contrast to the erosional topography that
characterizes the Naptowne and older surfaces within the
Chakachamna Lake basin, Neoglacial activity produced
prominent moraines and outwash fans. Neoglacial features
were examined at or near the termini of the following
glaciers;
(1) all glaciers along the south shore of the lake
from Shamrock Glacier to the lake outlet;
(2) Barrier Glacier;
5-18
1
/
I
\
f '
r
[
L
r~
L ~
['
l
L
c
r
L
L
f
L~
r
I
r
r
\
r:
l
L
L
L
( 3)
( 4)
( 5)
Pothole and Harpoon Glaciers, where they enter
the Nagishlamina River Valley;
all of the glaciers that flow to the south,
southeast, and east from the Mt. Spurr highland
(Alice Glacier to Triumviarte Glacier, Figure
5-l); and
Blockade Glacier.
The Neoglacial history of several of these glaciers is
discussed in more detail in Sections 5.2.1.3 through
5.2.1.5. The Neoglacial record is of particular
importance to an assessment of possible glacier
fluctuations over the next several decades.
Returning to the two points raised at the end of section
5.2.1.1:
(1) In most cases observed in the study area, it appears
that the latest Neoglacial advance was an extensive
or more extensive than earlier Neoglacial advances.
This is in agreement with the Porter and Denton
(1967) general conclusion for southern Alaska.
(2) Karlstrom•s (1964) chronology suggested a continuous
sequence of decreasing glacial advances leading from
Naptowne to Neoglacial time. In most parts of the
study area it was not possible to assess this
suggestion. However, the morainal sequence produced
by Brogan Glacier (Figure 5-l) and the difference in
the topographic characteristics of those moraines
suggest that there was little, if any, hiatus
between the youngest Naptowne moraine and the oldest
Neoglacial moraine.
5-19
5.2.1.3 Barrier Glacier
Barrier Glacier originates in the snow and ice field high
on the slopes of Mt. Spurr. From there it flows down a
steep, ice-carved canyon to the shore of Chakachamna Lake
where its piedmont lobe forms the eastern end of the lake
(Figures 5-2a, 5-2b). Barrier Glacier is of particular
interest to this study because the glacier forms the
eastern end of the lake and influences the size and
character of the outlet from the lake.
Barrier Glacier was described by Capps (1935) in his
report on the southern Alaska Range and was considered in
several reports on the hydroelectric potential of
Chakachamna Lake (Johnson, 1950; Jackson, 1961: Bureau of
Reclamation, 1962). Giles (1967) conducted a detailed
investigation of the terminal zone of Barrier Glacier.
Most recently, the U.S.G.S. investigated Barrier Glacier
as a part of a volcanic hazards assessment program at Mt.
Spurr (Miller, personal communication, 1981).
Giles' (1967) investigation of Barrier Glacier was the
most comprehensive to date and was specifically designed
to assess the possible impact of the glacier on hydro-
electric development of Chakachamna Lake, and vice
versa. That work, which took place between 1961 and
1966, included mapping of the lake outlet area and
measurements of horizontal and vertical movement and of
ablation on various portions of the glacier. Those
measurements indicated that:
5-20
r
I
[
l
L
r~
L
r ·L
L
r
L
\
J
I
I
\
' I ,,
I
\
J.
,,
t'
" ,\
J·
1
Jl
I
}
c
~ : ..
' I
WOODWARD-CLYDE CONSULTANTS
\ ... \
\
.·, ,.
,--·
I I
I '
I ' I..... •• I
L
L_,
( 1 )
( 2)
horizontal movement is in the range of 316 to 125
ft/yr on the debris-free ice and ~8 to 1 ft/yr on
the debris-covered lobe of ice that forms the
southernmost component of the glacier's piedmont
lobe complex; and
surface elevation changes were generally small
(+0.8 to -2.9 ft/yr), but ablation on the
relatively debris-free ice averaged about 35
ft/yr in the terminal zone.
Giles (1967) identified five ite lobes, two on the
debris-covered ice and three on' the exposed ice, in the
terminal zone of Barrier Glacier. Examination of color
infrared aerial photographs for the current study
suggests that he defined topographic, but not necessarily
glaciologically-functional lobes or ice streams. For
example, on the debris-covered portion of the piedmont
zone, Giles identified two lobes on the basis of a deep
drainage that cuts across that zone. On the air photos
it is clear that the drainage in question parallels and
then trends oblique to the curvilinear flow features
preserved in the debris mantle. The drainage does not
appear to mark the boundary between two ice streams.
Giles (1967) concluded that the level of Chakachamna Lake
is controlled by Barrier Glacier, specifically by one
900-ft wide portion of debris-covered ice along the
river; that zone reportedly ~dvances southward, into the
. river channel, at a rate of about 25 ft/yr. Although the
rate of ice movement was apparently relatively constant
throughout the year, the low stream discharge in the
winter allows the glacier to encroach on the channel but
the ice is eroded back during the summer. Thus, Giles
5-25
suggested that there is metastable equilibrium in the
annual cycle. The annual cycle appears to be super-
impos-ed on a longer-term change such as that suggested by
Giles' measurements.
Observations made during analysis of the color infrared
(CIR) aerial photographs and during the 1981 field recon-
naissance lead to general agreement with the conclusions
produced by previous investigations. Nonetheless, the
CIR air photos and extensive aerial and ground-based
r
I
I ~
\
observations have allowed for the development of several r
apparently new concepts regarding Barrier Glacier; those
new ideas may be summarized as follows:
(1) All of the moraines associated with Barrier Glacier
are the products of late Neoglacial advances of the
glacier and subsequent retreat. The large, sharp-
crested moraines that bound the glacier complex on
the eastern and a portion of the western margin
(Figure 5-2a) mark the location of the ice limit as
recently as a few hundred years ago (maximum
estimate) and perhaps as recently as the early to
middle part of this century. Cottonwood trees,
which are the largest and among the oldest of the
trees on the distal side of the moraine are
approximately 300 to 350 years old based on tree
ring counts on cores collected during the 1981 field
work (location of trees on Figure 5-2a). Those
dates provide an upper limit age estimate. The
vegetation-free character of the proximal side of
the moraine and the extremely sharp crest suggest an
even more youthful ice stand.
5-26
r
L
r L
r
L
r~
L_
I
l
f I
L
l
( '
L
(2) When Barrier Glacier stood at the outermost moraine
(no. 1 above), the terminal piedmont lobe was larger
than that now present and probably included a
portion that floated on the lake; the present river
channel south of the glacier could not have existed
in anything near its present form at that time. The
extent of the piedmont lobe, as suggested here, is
based on interpretation of the flow features
preserved on the debris-mantled portion of the
terminal lobe and the projected continuation of the
outermost moraine (no. 1 above).
(3) The most recent advance of Barrier Glacier did not
reach the outermost moraine. It appears that the
flow of ice was deflected westward by pre-existing
ice and ice-covered moraine at the point where the
glacier begins to form a piedmont lobe. This pulse
was responsible for the vegetation-free zone of till
that mantles the ice adjacent to the debris-free ice
and for the large moraines that stand above the
delta at the northeast corner of the lake.
(4) The presently active portion of Barrier Glacier has
the same basic flow pattern as that described in no.
3, above, but the terminus appears to be retreat-
ing. The flow of ice is deflected westward as it
exits the canyon through which the glacier descends
the slopes of Mt. Spurr. The flow pattern is
clearly visible on and in the debris-free ice and is
further demonstrated by the distribution of the
distinct belt of volcanic debris present along the
eastern margin of the glacier.
5-27
( 5) All of the above may be combined to· suggest that the
large debris-mantled (ice-cored) lobe that forms the
most distal portion of the glacier complex, and
which borders the river, is now, at least in large
part, decoupled from the active portion of the
glacier. This interpretation in turn suggests that
the movements measured by Giles (1967) are due to
adjustments within the largely independent debris-
mantled lobe and to secondary effects transmitted to
and through this lobe by the active ice upslope.
(6) In spite of the fact that disintegration of the
debris-mantled lobe is extremely active locally, the
lobe appears to be generally stable because remnant
flow features are still preserved on its surface.
The debris cover shifts through time, thickening and
thinning at any given location as topographic
inversion takes place due to melting of the ice and
slumping and water reworking of the sediment. It
appears that the rate of melting varies as a
function of the thickness of the debris cover, with
a thick cover insulating the ice and a thin cover
producing accelerated melting. Removal of the
covering sediment along the edge of the river leads
to slumping and exposure of ice to melt-producing
conditions. Thus the distal portion of the debris-
mantled lobe that borders the river is one site of
accelerated melting. Other areas of accelerated
melting are concentrated along drainages that have
developed within the chaotic ice-disintegration
topography.
·s-2s
[
{ i.
l
[
[
r'c
L
L
r
r
L
{
L~
L
L
[ I
r
f\
(
k
L
L
(7) There is no ice now exposed along the lake shore or
around the lake outlet, at the head of the
Chakachatna River, as was the case as recently as a
few decades ago (Giles, 1969). These areas are
rather uniformly vegetated and the debris mantle
over the ice appears to be relatively thick compared
to areas where accelerated melting is taking place.
These areas appear to be reasonable models of what
to expect when melting of the ice and the associated
sorting and readjustment of the overlying debris
have produced a debris cover thick enough to
insulate the ice.
(8) If the debris-mantled ice lobe is functionally
decoupled from the active ice, as suggested above,
the move of ice toward the river is likely to
gradually slow in the near future. The Giles'
(1967) data suggest that this slowing may be
underway; the 1971 flood on the Chakachatna suggests
that the ice movement is still occasionally rapid
enough to constrict the river channel, however.
Nonetheless, it appears likely that, barring a
dramatic or catastrophic event, the degrading
portion of the ice lobe along the river will slowly
stabilize to a condition similar to that along the
lake shore. This will probably lead to a channel
configuration som~what wider than at present but the
channel floor elevation is unlikely to change
significantly. This scenario ass.umes that the
discharge will remain relatively similar to that
today. If discharge increases, then a channel
deepening, as suggested by Giles (1967), may occur.
If discharge decreases, the available data suggest
that the outlet channel is likely to become more
5-29
5.2.1.4
narrow and perhaps more shallow as the
debris-covered ice continues to stabilize (see
Section 7.0).
(9) Over the long term the possible changes along the
uppermost reaches of the Chakachatna River, where
the lake level is controlled, are potentially more
varied and more difficult to predict. One reason
for this is that the longer time frame (i.e.,
centuries vs. decades) provides an increased
probability for both dramatic (e.g., marked warming
or cooling of the climate) and catastrophic (e.g.,
large volcanic eruption) events. In this regard, it
should be noted that Barrier Glacier and the lake
outlet appear to be within the zone of greatest
potential impact from eruptions of Mt. Spurr volcano
(see Section 5.2.2).
Post and Mayo (1971) listed Chakachamna Lake as one of
Alaska's glacier-dammed lakes that can produce outburst
floods. They rated the flood hazard from the lake as
nvery lown unless the glacier advances strongly. The
1971 flood on the Chakachatna (Lamke, 1972) was
attributed to lateral erosion of the glacier terminus at
the lake outlet. This flood may have, in fact, been
triggered by waters from an outburst flood at Pothole
Glacier, a surging glacier (Post, 1969) in the
Nagishlamina Riv~r Valley (Section 5.2.1.5).
Blockade Glacier
Blockade Glacier (Figure 5-l) originates in a very large
snow and ice field (essentially a mountain ice cap), high
5-30
[
r
r t
[
[
r L
L
L
r
L
L
L
L
[
[
[.
r·
(
h
L
r .
r l.
in the Chigmit Mountains south of Chakachamna Lake. This
same ice cap area is also the source of several of the
glaciers that flow to the south shore of Chakachamna Lake
(e.g., Shamrock, Dana, and Sugiura Glaciers; Figure
5-l). Blockade Glacier flows southward out of the high
mountains into a long linear valley, which trends NE&SW
and which is apparently fault controlled (Section 5.3).
Once in th~ linear valley, Blockade Glacier flows both to
the northeast and to the southwest. The southwestern
branch terminates in Blockade Lake, which is one of
Alaska's glacier-dammed lakes that is a source of
outburst floods (Post and Mayo, 1971). The northeastern
branch of the glacier terminates ~ear the mouth of the
McArthur River Canyon and melt water from the glacier
drains to the McArthur River.
Blockade Glacier is of specific interest to the
Chakachamna feasibility study because one of its branches
does terminate so near the mouth of the McArthur River
Canyon, and a likely site for the powerhouse for the
hydroelectric project is in the lower portions of the
canyon (Section 3.0). Changing conditions at the
northeastern terminus of Blockade Glacier could
conceivably change the drainage of the McArthur River to
a degree that may influence conditions in the canyon,
i.e., at the proposed powerhouse sites in the canyon.
Blockade Glacier has not been the subject of previous
detailed studies such as those for Barrier Glacier
(Section 5.2.1.3). Observations made during the 1981
field reconnaissance covered the lower-elevation portions
of the source area and both terminal zones, but were
concentrated around the northeastern terminus, near the
McArthur River.
5-31
At its northeastern terminus Blockade Glacier is over two
miles wide. Over about half of that width (the northern
half) the glacier terminates in a complex of melt -water
lakes and ponds that are dammed between the ice and Neo-
glacial moraines. The melt water from the lake system
drains to the McArthur River via one large and one small
river that join and then flow into the McArthur about 2.5
miles downstream from the mouth of the McArthur River
Canyon. A complex of recently abandoned melt water
channels formerly carried flow to the McArthur at the
canyon mouth. A small advance of the ice front would
reinstitute drainage in these now dry channels.
Melt water issuing from the southern half of the ice
front flows to the McArthur River in braided streams that
cross a broad outwash plain. Whereas the northern
portion of the terminus is very linear, the southern
portion includes a distinct lobe of ice that is more than
a half mile wide and protrudes beyond the general ice
front by more than three-quarters of a mile. Another
notable characteristic of this zone is that the Neo-
glacial moraines, which are so prominent to the north,
have been completely eroded away by melt water along the
southern margin of the glacier.
On the basis of the above observations and the report
that Blockade Lake produces outburst floods (Post and
Mayo, 1971), it appears that the distinct features in the
southern portion of the northeast terminal zone are
present because this is the area where the outburst
floods exit the glacier front. The broad outwash plain
and the removal of the Neoglacial moraines are probably
both due to the floods; the vegetation-free (i.e.,
active) outwash plain is much larger than the size of the
5-32
,~
l
t
r
r
r
[
[
L
L
( '
f
L
L
L
L
~
r -
[ .
r
[
f
L
l
r
L
L
melt water streams would suggest. The distinct lobe of
ice that protrudes beyond the general front of the
glacier probably marks the location of the sub-ice
channel through which the outburst floods escape.
The outermost Neoglacial moraines ~resent near the
northeastern terminus lie about three-quarters of a mile
beyond the ice front. With the exception of the distinct
ice lobe, the general form of the ice front is mirrored
in the shape of the Neoglacial terminal moraines. The
outermost end moraine, which stands in the range of 20 to
40 ft above the surrQunding outwash plain (distal) and
ground moraine (proximal), is in the form of a continuous
low ridge with a gently rounded crest. Three oi four
less distinct and less continuous recessional moraines
are present between the ice and the Neoglacial maximum
moraines. Distinct glacial fluting is present in the
till in this area.
The Neoglacial end moraine can be traced to a distinct,
sharp-crested Neoglacial lateral moraine that is
essentially continuously present along the glacier
margins well up into the source area for Blockade
Glacier. The proximal side of the lateral moraine is
steep and vegetation-free, suggesting ice recession in
the very recent past. The crest of tne lateral moraine
stands about 40 or 50 ft (estimate based on observations
from the helicopter) above the ice along the lower
~ortions of the glacier.
A readvance of Blockade Glacier's northeastern terminus
on the order of one-quarter to one-half a mile would
reestablish drainage through the abandoned channels near
the mouth of the McArthur River Canyon. such a change is
5-33
unlikely to significantly impact conditions within the
canyon but would disrupt facilities (e.g., roads) on the
south side of the McArthur River, immediately outside the
mouth of the canyon. The glacier will have to advance
about three-quarters of a mile before conditions in the
canyon are likely to be seriously affected. An advance
of a mile and a half would essentially dam the mouth of
the canyon and would flood a major portion of the lower
reaches of the canyon, including the sites under con-
sideration for the powerhouse. Such a glacier-dammed
lake would likely produce outburst floods.
There is no evidence that any of the Neoglacial a~vances
of Blockade Glacier were extensive enough to dam the
McArthur River Canyon. The outmost of the Neoglacial
moraines lies at least one-quarter of a mile short of the
point where ice-damming of the canyon would begin, how-
ever. Outwash fans on the distal side of the moraine may
have produced minor pending in the lowermost reaches
observed in the field and on the color infrared air
photos suggest that the last time that Blockade Glacier
may have dammed the McArthur Canyon was in late Naptowne
time, approximately 10,000 years or more ago.
The only reasonable mechanism that could produce an
advance of Blockade Glacier that would be rapid enough to
impact on the proposed hydroelectric project is a glacier
surge; a surging glacier could easily advance ~ mile or
more within a period of a few decades. Evidence for
surges in the recent past might include an advancing
glacier front in an area where glaciers are generally in
recession and/or distorted medial moraines or long-
itudinal dirt bands on the glacier surface (Post, 1969;
Post and Mayo, 1971). It is clear that Blockade
5-34
r-
r
'-
L
['
rc
[
L
['
r
r L
[
L
L
{
r:
L
[
r
k
L
Glacier's recent history has been one of recession, as is
the case for all other glaciers examined during the 1981
field reconnaissance. There are many distinct longitudi-
nal dirt bands and small medial moraines visible on the
surface of Blockade Glacier. If one or more of the indi-
vidual ice streams that comprise Blockade Glacier had
recently surged, such activity should be reflected in
contortions in the dirt bands and medial.moraines.
Visible deformation of the surface features on the
glacier is very subtle and not suggestive of recent
surging of even individual ice streams in the glacier.
Thus, there is no evidence of a general surge of Blockade
Glacier in the recent past.
In summary, it appears that Blockade Glacier began to
withdraw from its Neoglacial maximum within the last few
hundred years. At that maximum stand, melt water drain-
age joined the McArthur River at the canyon mouth and
outwash may have produced some ponding and sediment
aggradation in the lower reaches of he canyon, but the
glacier was not extensive enough to have dammed the
canyon. surging is the most reasonable mechanism that
could produce a future advance large enough and rapid
enough to impact on the proposed powerhouse sites in the
McArthur Canyon. No evidence suggestive of surging of
Blockade Glacier was identified during this study.
Currently, melt water is carried away from the canyon
mouth. Even markedly accelerated melt water production
from Blockade Glacier is unlikely to change this
condition or to have a negative impact on the proposed
hydroelectric project.
5-35
5.2.1.5 Other Glaciers
In order to get a reasonably broad-based sense of the
glacial record and history of recent glacier behavior in
the Cakachamna Lake region, the field reconnaissance
included aerial and ground-based observations of a number
of the glaciers in the region in addition to Barrier and
Blockade Glaciers~ Those glaciers included:
(1) Shamrock Glacier, Dana Glacier, Sugiura Glacier, and
First Point Glacier along the south shore of
Chakachamna Lake (see figure 5-l for locations);
(2) Harpoon Glacier and Pothole Glacier in the
Nagishlamina River Valley;
(3) Alice Glacier, Crater Peak Glacier, and Brogan
Glacier on the slopes of Mt. Spurr, above the
Chakachatna River;
(4) Capps Glacier and Triumvirate Glacier on the eastern
slopes of Mt. Spurr; and
(5) McArthur Glacier in the McArthur River valley.
Post (1969) surveyed glaciers throughout western North
America in an effort to identify surging glaciers. Four
of his total of 204 surging glaciers for all of western
North America are in the Chakachamna study area (Figure
5-l). Three, including Pothole Glacier and Harpoon
Glacier, are located in the Nagishlamina River Valley,
tributary to Chakachamna Lake, and one, Capps Glacier, is
on the eastern slope of Mt. Spurr. surface features
5-36
[
[
1 l_
I
l"_
l. -
l
l.
indicative of surging are clearly visible on the color
infrared aerial photographs used in this study and were
observed during .field reconnaissance.
Specific observations pertinent to an understanding of
the glacial history of the area include:
(1) All of the gl~ciers listed above appear to have only
recently withdrawn from prominent Neoglacial
moraines, which in most (if not all) cases mark the
Neoglacial maximum advance positions of the
glaciers. These moraines and younger recessional
deposits are generally ice-cored for those glaciers
in groups 1 through 3 (above), but have little or no
ice core in groups 4 and 5, which terminate at
slightly lower elevations.
(2) Ponding and sudden draining of the impoundment
upstream of the Pothole Glacier (a surging glacier)
end moraine complex in the Nagishlamina River valley
may be an episodic phenomena that can produce
flooding in the lower portions of that valley and
thus a pronounced influx of water into Chakachamna
Lake. Published topographic maps (compiled in 1962)
show a small lake U}:Jstream of the end moraine, which
with the exception of a narrow channel along the
western valley wall, completely blocks the
Nagishlamina River Valley. That lake is no longer
present bu~ there is clea~ evidence for its presence
and the presence of an even larger lake in the
recent past. Features on the floor of the lower
Nagishlamina River Valley suggest recent passage of
a large flood. such a sudden influx of water into
5-37
Chakachamna Lake could produce sign{ficant changes
at the outlet from the lake. It may be that the
1971 flood on the Chakachatna River (U.S.G.S., 1972)
was triggered by such an event, the stage having
been set by the slow increase in the level of
Chakachamna Lake in the years prior to the flood
(Giles, 1967).
(3) Only glaciers south and east, and in the immediate
vicinity at Crater Peak on Mt. Spurr retain any
evidence of a significant cover of volcanic ejecta
from the 1953 eruption of Crater Peak. On both
Crater Peak Glacier and Brogan Glacier (see Figure
5-l) the ice in the terminal zone is buried by a
thick cover of coarse ejecta. The volcanic mantle,
where present, appears to be generally thick enough
to insulate the underlying ice. The ejecta cover on
Alice Glacier is surprisingly limited. Areas where
the volcanic cover formerly existed, but was thin
enough so that its presence accelerated melting,
have probably largely been swept clean by the melt-
water. In any case, the only areas where there is
now evidence that the dark volcanic mantle has or is
producing more rapid melting is on the margins of
the thickly covered zones on the two cited glaciers.
(4) Highly contorted medial moraines on Capps Glacier,
Pothole Glacier, and Harpoon Glacier suggest that
several of the individual ice streams that comprise
those glaciers have surged in the recent past. No
comparable features were observed on any of the
other glaciers in the Chakachamna study area.
5-38
{
L
L
r
I
l
L
L
L
r l_,
' k
l
r -I -
I
5.2.1.6 Implications with Respect to the Proposed Hydroelectric
Project
Implications derived from the assessment of the glaciers
in the Chakachamna Lake area, with respect to specific
project development alternatives, are included in Section
7.2 while project risk evaluation is disucssed in Section
7.4. General implications, not directly tied to any
specific design alternative, may be summarized as follows:
(1) In the absence of the proposed hydroelectric
project, the terminus of Barrier Glacier is likely
to continue to exist in a state of dynamic equilib-
rium with the Chakachatna River and to produce
small-scale changes in lake level through time; the
terminal fluctuations are likely to slow and
decrease in size in the future, leading to a more
stable condition at the lake outlet.
(2) If development of the hydroelectric project or
natural phenomena dam the Chakachatna River Valley
and flood the terminus of Barrier Glacier, the rate
of disintegration is likely to increase. If the
level of the lake is raised, the rate of calving on
Shamrock Glacier is likely to increase.
(3) If hydroelectric development lowers the lake level,
the debris-covered ice of Barrier Glacier is likely
to encroach on and decrease the size of ~he river
channel; a subsequent rise in lake level could yield
conditions conducive to an outburst flood from the
lake. A lowering of the level of Chakachamna Lake
will also cause the stream channels that carry water
from Kenibuna Lake and Shamrock Lake into
5-39
5.2.2
5.2.2.1
Chakachamna Lake to incise their channels, thereby
lowering the levels of those upstream lakes over
time.
(4) There is no evidence to suggest that Blockade
Glacier will have an adverse impact on the proposed
hydroelectric project or that the project will have
any effect on Blockade Glacier.
(5) Glacier damming of the Nagishlamina River Valley may
result in outburst floods that influence conditions
at the outlet from Chakachamna Lake.
(6) With the exception of Shamrock Glacier, the terminus
of which may be affected by the lake level, there is
no evidence to suggest that the proposed project
will influence the glaciers (other than Barrier
Glacier) in the Chakachatna-Chakachamna Valley.
Changes in the mass balance of the Glaciers will
influence the hydrologic balance of the lake-river
system, however.
Mt. Spurr Volcano
Alaska Peninsula-Aleutian Island Volcanic Arc
Mt. Spurr is an active volcano that rises to an elevation
above 11,000 ft at the eastern end of Chakachamna Lake.
Mt. Spurr is generally reported to be the northernmost of
a chain of at least 80 volcanoes that extends for a
distance of about 1,500 miles through the Aleutian
Islands and along the Alaska Peninsula; recent work has
identified another volcano about 20 miles north of Mt.
_Spurr (Miller, personal communication, 1981). Like Mt.
5-40
r
[
[
[ ~
. i~
r·
[-.
[
['
[
l_
[
r
l~
l
l
L
L
Spurr, about half of the known volcanoes in the
Aleutian Islands-Alaska Peninsula group have been
historically active.
The volcanoes of this group are aligned in a long arc
that follows a zone of structural uplift (Hunt, 1967),
and that lies immediately north of the subduction zone at
the northern edge of the Pacific Plate. The volcanoes on
the Alaska Peninsula developed on a basement complex of
Tertiary and pre-Tertiary igneous, sedimentary, and
metasedimentary rocks. The pre-volcanic rocks are poorly
exposed in the Aleutian Islands. At the northern end of
the chain, such as at Mt. Spurr, the volcanoes developed
on top of a pre-existing to~ographic high. Mt. Spurr is
the highest of the volcanoes in the group and the summit
elevations generally decrease to the south and west.
The Alaska Peninsula-Aleutian Islands volcanic chain is,
in many ways, similar to the group of volcanoes in the
.Cascade mountains of northern California, Oregon,
Washington, and southern Bri~ish Columbia. In general,
both groups of volcanoes developed in already mountainous
areas, both consist of volcanoes that developed during
the Quaternary and include historically active volcanoes.
In both areas the volcanic rocks encompass a range of
compositions but are dominantly andesitic, and both
groups contain a variety of volcanic forms. The Alaskan
volcanoes include low, broad shield volcanoes, steep
volcanic cones, calderas, and volcanic domes. Much of
the present volcanic morphology developed in late-and
post-glacial time.
5-41
5.2.2.2 Mt. Spurr
Capps ·(1935, p. 69-70) reported, "The mass of which the
highest peak is called Mt. Spurr consists of a great
outer crater, now breached by the valleys of several
glaciers that flow radially from it, and a central core
within the older crater, the highest peak of the
mountain, from vents near the top of which steam some-
times still issues. One small subsidiary crater, now
occupied by a small glacier, was recognized on the south
rim of the old, outer crater."
Subsequent work has shown that Capps' observations were,
in part, in error. The error is specifically related to
the suggestion that the peaks and ridges that surround
the summit of Mt. Spurr mark the rim of a large, old
volcanic crater. Why Capps had this impression is clear
because as one approaches the mountain from the east or
southeast, the view strongly suggests a very large
crater; such a view has suggested to many geologists that
Capps was correct in his observations. It is only when
one gets up on the mountain, an opportunity made
practical by the helicopter, that it becomes clear that
most of the "crater rim" consists of granitic and not
volcanic rocks. The most recent and comprehensive report
on the distribution of lithologies present on Mt. Spurr
is found in Magoon and others (1976). The u.s.
Geological Survey plans to issue an open file report on
Mt. Spurr in 1982 (Miller, personal communication, 1981).
Field work aimed at assessing the potential impact of
volcanic activity from Mt. Spurr on the proposed hydro-
electric development at Chakachamna Lake was concentrated
in the area bounded by the Nagishlamina River on the
5-42
L
['
L
L
[
L
I
L
l
L
L
r
f
k
L
r L_
L
west, the Chakachatna River on the south, a north-south
line east of the mountain front on the east, and the
Harpoon Glacier-Capps Glacier alignment on the north
(Figure 5-l). Most of the observations at the higher
elevations were from the helicopter: landing locations
high on Mt. Spurr are few and far between and many of the
steep slopes are inaccessible to other than airborne
observations. It was possible to make numerous surface
observations in the Nagishlamina River and Chakachatna
River valleys and on the slopes below 3,000 ft elevation
to the south and southeast of the summit of Mt. Spurr.
Observations made during the 1981 reconnaissance indicate
that the Quaternary volcanics of Mt. Spurr, with the
exception of airfall deposits, are largely confined to a
broad wedge-shaped area bounded generally by Barrier
Glacier, Brogan Glacier, and the Chakachatna River
(Figures 5-l, 5-2a and 5-2b): the distribution of
Quaternary volcanics north of the summit, in areas that
do not drain to the Chakachamna-Chakachatna basin, was
not investigated.
The bedrock along the western margin of Barrier Glacier
is dominantly granite. The only exception observed
during the field reconnaissance, which focused at
elevations below about 5,000 ft, was an area where the
granite is capped by lava flows (Figure 5-2a). East of
Barrier Glacier the slopes above about 2,000 ft consist
of interstratified lava flows and pyroclastics, which are
exposed in cross section. The slopes of Mt. Spurr in
this area are not the product of triginal volcanic
deposition but are erosional features. Thus, it is clear
that the volcanics once extended farther to the south and
southwest into what is now the Chakachamna Lake basin and
5-43
Chakachatna River Valley. The lower slopes immediately
east of Barrier Glacier and south of Mt. Spurr consist of
a broad alluvial fan ~omplex.
Between Alice Glacier and the mountain front, the upper
slopes of Mt. ·spurr, where not buried by glacier ice or
Neoglacial deposits, expose interbedded lava flows (often
with columnar jointing), pyroclastic units, and volcanic-
lastic sediments. As is the case near Barrier Glacier,
most of the slopes in this area are steep, often near
vertical erosional features that expose the volcanic
sequence in cross-section. The primary exception to this
is found on and adjacent to Crater Peak where some of the
slopes are original depositional features.
Crater Peak was the site of the most recent eruption of
Mt. Spurr. That eruption, which took place in July,
1953, was described by Juhle and Coulter (1955). The
1953 eruption produced an ash cloud that was observed as
far east as Valdez, 100 miles from the volcano; the
distribution of ejecta on Mt. Spurr demonstrates that
virtually all of the airborne material traveled eastward
with the prevailing winds. The thick debris cover on
Crater Peak and Brogan Glaciers (Figure 5-2b) is largely
the product of this eruption.
Any lava that issued from Crater Peak in 1953 was limited
to the slopes of the steep-sided cone. The eruption did
produce a debris flow, which began at the south side of
the crater where volcanic debris mixed with water from
the glacier that reportedly occupied the crater (Capps,
1935) and the outer slopes of the cone began to move
downslope toward the Chakachatna River. The debris flow,
which was probably more a flood than a debris flow
5-44
f
L
[
{
L
L
L
L
[
(
(
F
L
L
L
L
L.
[
initially, eroded a deep canyon along the eastern margin
of Alice Glacier, through the Neoglacial moraine complex
at the terminus of Alice Glacier, and through older
volcanics and alluvium adjacent to the Chakachatna
River. When it reached the Chakachatna River, the debris
flow dammed the river and produced a small lake that
extended upstream to the vicinity of Barrier Glacier.
The dam was subsequently partially breached, lowering the
impoundment in the Chakachatna Valley to its present
level. Evidence for the high water level includes
tributary fan-deltas graded to a level above the current
water level and a "bath tub ring".of sediment and little
or no vegetation alon~ the suuthern valley wall.
East of the 1953 debris flow, the Chakachatna River flows
through a narrow canyon within the broader valley bounded
by the upper slopes of Mt. Spurr on the north and the
granitic Chigmit Mountains on the south. The southern
wall of the canyon (and valley, as whole) consists of
glacially-scoured granitic bedrock. With the exception
of remnant deposits of the 1953 debris flow that are
present against the granitic bedrock (Figure 5-2b), the
1981 reconnaissance yielded no evidence of volcanic or
volcaniclastic rocks on the southern wall of the
Chakachatna Valley. The northern wall of the
Chakachatna Canyon exposes a complex of highly weathered
(altered ?) andesitic lava flows, pyroclastics,
volcaniclastic sediments, outwash, and in one location,
what appears to be an old (pre-Naptowne) till.
Although the general late-Quaternary history of the
Chakachatna River Valley is reasonably clear, the details
of that history are very complex and would require an
5-45
extensive field program to unravel. The
observations made during the 1981 reconnaissance
suggest the following:
(1) Late-Tertiary and/or early-Quaternary volcanic
activity at Mt. Spurr built a thick pile of lava
flows, pyroclastics, and volcaniclastic sediments on
top of a granitic mountain mass of some considerable
relief.
(2) Interspersed volcanic and glacial activity occurred
during the Pleistocene, with alternating periods of
erosion and deposition. The width of the valley at
Chakachamna Lake is maintained downstream to the
area of Alice Glacier (Figure 5-2a). From that
point to the mountain front, where the same broad
valley form seems to reappear, the overall valley is
plugged by a complex of volcanic (and glacial)
deposits. This, along with the volcanic cliffs high
on the slopes of Mt. Spurr, suggests that volcanics
once largely filled what is now the Chakachatna
Valley, that glaciers then eroded a broad, U-shaped
valley (such as is still present in the lake basin),
and that subsequent volcanic activity produced the
bulk of the deposits that form the valley "plug".
(3) The age of the volcanics in the "plug" is not
clear. Some of the characteristics of the basal
volcanic rocks exposed along the river suggest some
antiquity. For example, many lava flows are so
deeply weathered (or altered ?) that the rocks
disintegrate in one's hand. These volcanics appear
to be overlain by outwash and may be interbedded
with till, which is also deeply weathered
5-46
L
L
L
r
L
L
L
L
[ .
[
j"
r··
r
k
l.
L
L_
(altered?). These and other features suggest that
at least some of the volcanics in this area were
deposited in pre-Naptowne time. Glacial deposits,
including moraines, a large area of kame and kettle
deposits,and glacier-marginal lake deposits
interpreted to be a late-Naptowne age overlie
portions of the volcanic valley plug. [See Section
7.2 for discussion of implications with respect to a
darn in the Chakachatna Canyon.]
In contrast, it is difficult to understand how the
apparently easily eroded volcanics in this area
survived the Naptowne-age glaciers that filled the
Chakachatna Valley and were large enough to extend
across Cook Inlet (Karlstrorn, 1964)~ In addition,
there are many landforms, such as volcanic
pinnacles, that clearly are post glacial as they
could not have survived being overriden by glacier
ice. Such landforms demand the removal of several
tens of feet of volcanics over large·areas.
Although the evidence is conflicting and an unambig-
uous interpretation difficult, it does appear that
much of the volcanic valley plug is of pre-Naptowne
age. The basis for this conclusion is most clearly
documented by the presence of outwash on top of
volcanics, a sequence exposed at several sites in
the canyon. The outwash is capped by a three-to-four
foot thick cap of volcanic ash (many discrete
depositional units) as is typical of Naptowne-age
surfaces in the area. Just how these volcanics
survived the Naptowne glaciation is not clear.
5-47
(4) Following the withdrawal of the Naptowne ice from
the Chakachatna River Valley, Holocene volcanic
activity, glacial activity, and fluvial and slope
processes have produced the present landscape.
Most, if not all of the present inner canyon,
through which the Chakachatna River flows, appears
to be the product of Holocene downcutting by the
river.
Given that many of the details of the Quaternary history
of Mt. Spurr are not well understood, it is nonetheless
clear that Mt. Spurr is an active volcano that may
produce lava flows, pyroclastics, and volcaniclastic
sediments in the immediate vicinity within the life of
the project. Airfall deposits can be expected to
influence a larger area. Considering the size and type
of volcanic events for which there is evidence at Mt.
Spurr and the present topography, the area of interest to
the proposed hydroelectric project most likely to be
affected is the area between Barrier Glacier and the 1953
debris flow. The topography of the valley plug volcanics
appears to afford some, but certainly not total
protection to the canyon portion of the river valley; an
example of this "protection" is provided by a second
debris flow produced in 1953 that was prevented from
reaching-the river by intervening topography on the
valley "plug".
The types of volcanic event judged to be most likely to
impact the Chakachatna River Valley in the near future
are:
5-48
f
I ~
[
L
[
[
L
r·
L
[,
r-
L
[
5.2.2.3
(1) 1953-type debris flows which could inundate a
portion of the valley and re-darn the river,
(2) lava flows, which could enter and darn the valley, and
(3) large floods that would be produced by the melting
of glacier ice during an eruption.
Post and Mayo (1971) suggested that melting of glacier
ice on Mt. Spurr during volcanic activity may present a
serious hazard. Significant direct impact on Barrier
Glacier would demand a summit eruption that included the
flow of hot volcanics at least into the upper reaches of
the glacier or the development of a new eruptive center
(such as Crater Peak) west of the present summit. Of
course the character of the volcanoes in the Aleutian
Island-Alaska Peninsula chain make it clear that a very
large event (i.e., a Mt. St. Helens--or even a Crater
Lake-type event) is possible at Mt. Spurr; such an event
has a very low annual probabilty of occurrence at any
given site, however.
Implications with Respect to the Proposed Hydroelectric
Project
The potential impact of Mt. Spurr on the proposed
hydroelectric project will, in part, vary as a function
of the project design (see Sections 7.2 and 7.4), but
some potential will always exist because of the location
of Mt. Spurr relative to Chakacharnna Lake and the
Chakachatna River. The amount of negative impact on the
project is clearly a function of the size of volcanic
event considered; larger events, which would have the
greatest potential for adverse impact, are, in general,
5-49
less likely to occur than smaller volcanic events. Some
general possibilities that might be associated with low-
to medium-intensity events (such as a Crater Peak event
or slightly larger) include:
(1) Damming of the Chakachatna River by lava or debris
flows, with the most likely site being in the
vicinity of the 1953 debris dam. Flooding of the
terminus of Barrier Glacier may increase the rate of
ice melt and possibly alter the configuration of the
current lake outlet. Any project facilities on the
valley floor of the upper valley would be buried by
the flow and/or flooded.
(2) Flooding of the Chakachatna River Valley as a result
of the melting of glacier ice on Mt. Spurr during an
eruption. Project facilities near or on the valley
floor would be flooded.
(3) Accelerating the retreat of Barrier Glacier due to
the flow of hot volcanic debris onto the glacier.
In the extreme, Barrier Glacier could be eliminated
if enough hot material flowed onto the ice. A less
dramatic scenario could include destabilization of
the lake outlet due to accelerated melting in the
terminal zone of Barrier Glacier. In contrast, a
large lava flow at the present site of Barrier
Glacier could replace the glacier as the eastern
margin of the lake, providing a more stable dam than
that provided by Barrier Glacier.
Each of the design alternatives (Section 3.0) includes a
lake tap in the zone between the lake outlet and First
L
L
L
[
[
[
t:
L
L
Point Glacier. Although it is generally true that a site L.
5-50
L
L
5.2.3
5.2.3.1
L
r
L -
farther from Mt. Spurr is less likely to be subject to
volcanic hazards than a site closer to the volcano, there
is no apparent reason to favor one particular site in the
proposed zone over any other site in that zone. A large
eruptive event, apparently substantially larger than any
of the Holocene events on Mt. Spurr, would be required
before the proposed lake tap site would be directly
threatened by an eruption of Mt. Spurr.
Slope Conditions
The Chigmit Mountains, south of Chakachamna Lake and the
Chakachatna River, and the Tordrillo Mountains, to the
north, contain many steep slopes and near-vertical
cliffs. This landscape is largely the product of
multiple glaciation during the Quaternary, including
Neoglaciation which continues in the area today. The
proposed hydroelectric project is likely to include
facilities in the Chakachamna Lake basin and either or
both of the McArthur and Chakachatna River valleys. Any
above-ground facilities in these areas will be on or
immediately adjacent to steep slopes, and thus subject to
any slope processes that may be active in the area.
Because of this fact, the 1981 field reconnaissance
included observations of slope conditions in the areas of
interest. Future field work should include detailed
assessment of bedrock characteristics, such as joint
orientations, that influence slope conditions.
Chakachamna Lake Area
Chakachamna Lake sits in a glacially overdeepened basin
that is generally bordered by steep slopes of granitic
bedrock that was scoured during Naptowne and earlier
5-51
5.2.3.2
glaciations. Locally, such as along the southern valley
wall west of Dana Glacier (Figure 5-2a), distinct bedrock
benches are present. In other areas, the slopes rise,
with only minor variation in slope, from the lake level
to the surrounding peaks. All principal valleys along
the southern side of the lake presently contain
glaciers. The principal valleys tributary to the north
side of the lake, the Chilligan and Nagishlamina, are
larger than those on the south side of the lake and are
currently essentially ice-free, although their present
form is clearly the product of glacial erosion.
No evidence of large-scale slope failures of the slopes
in the Chakachamna Lake basin was observed during the
1981 field reconnaissance. Most of the slopes are
glacially-scoured bedrock and are essentially free of
loose rock debris, although talus is locally present.
The orientation of joint sets in the granitic bedrock
varies somewhat from area to area. In many areas a near
horizontal out-of-slope joint set is present, but it
tends to be poorly expressed relative to more
steeply-dipping joints. Field work indicates that this
and cross-cutting joints have formed boulder-size pieces
and small slabs that produce rockfall as the only common
type of slope failure for which any evidence was found.
This condition is apparently most pronounced along the
southern valley wall, between Sugiura Glacier and the
lake outlet.
Chakachatna River Valley
The Chakachatna River, from its origin at Chakachamna
Lake to the mountain front, flows through a valley that
is rather variable in its form and characteristics along
5-52
r
L
l
l
its length and from side to side. Throughout the valley,
the south side consists of steep glaciated granitic
bedrock slopes that_rise essentially continuously from
the river to the adjacent mountain peaks. All major
tributary valleys on the southern valley wall, many of
which are hanging valleys, now contain glaciers. The
comments regarding slope conditions on the slopes above
the lake (Section 5.2.3.1) apply to the southern wall of
the Chakachatna River Valley.
The north side of the valley differs from the south side
in virtually every conceivable way. On this side bedrock
is volcanic, and glacial and fluvial sediments are also
present. In the westernmost portion of the valley, the
river is bordered by the Barrier Glacier moraine and
alluvial fans; steep volcanic slopes above the alluvial
fans are subject to rockfall activity. Between Alice
Glacier (the area of the 1953 debris flow) and the valley
mouth, the river flows through a narrow canyon, the north
side of which consists of a variety of interbedded
volcanics, glacial deposits, and fluvial sediments
(Figure 5-2b). The north canyon wall has been the site
of several landslides that range in size from small
slumps to large rotational slides. Such activity is
likely to continue in the future. Its impact will most
frequently be limited to the diversion of the main river
course away from the north canyon wall; there are several
examples of this now present in the canyon. A large
landslide, which appears to be unlikely giveri the height
of the slopes, could completely dam the canyon; partial
damming with temporary ponding appears to be a more
likely possibility.
. 5-53
5.2.3.3
Volcanic activity on Mt. Spurr could directly influence
conditions along the Chakachatna River (Section 5.2.2),
or could, by slowly altering conditions along the north
wall of the canyon, have a secondary impact on the valley.
McArthur River Canyon
The McArthur River Canyon is a narrow, steep-walled
glaciated valley. A possible powerhouse site has been
identified along the north wall of the canyon (Section
3.0) and the following comments specifically refer to the
north wall of the McArthur River Canyon. The valley
walls, which consist of granitic bedrock, expose a
complex of cross-cutting joint sets and shear zones. The
character and dominant orientations of the joints and
shears vary along the length of the canyon and the
character of the slopes also varies, apparently in direct
response.
Except near the canyon mouth, there is no evidence of
large-scale slope failure and rockfall is the dominant
slope process. Between the terminus of McArthur Glacier
and Misty Valley (Figure 5-l) the joint sets are of a
character and orientation such that rockfall has been
active and the bedrock on the lower slopes on the north
valley wall are uniformly buried beneath a thick talus.
The vegetation on the talus suggests that the bulk of
talus development took place some time soon after de-
glaciation and rockfall has been less active recently.
The slopes between Misty and Gash valleys (Figure 5-l)
consist of glacially-scoured bedrock that is essentially
talus free, suggesting little or no rockfall in this area.
5-54
[
L
[
[
L
L
L
L
L
L
L
f'
t
t
[
Li
L
L
L
l
t
5.2.3.4
From Gash Valley to the canyon mouth, the granitic ·
bedrock appears to become progressively more intensely
jointed and sheared and thus more subject to rockfall and
small-scale slumping. Talus mantles the lower slopes in
much of this area. A large fault zone (Section 5.3) is
present at the canyon mouth. The fault has produced
intense shearing over a broad zone that is now subject to
intense erosion and is the site of several landslides.
Implications with Respect to the Proposed Hydroelectric
Project
As in the case for volcanic hazards, there is no apparent
reason with respect to slope conditions to favor one site
over any other in the zone between the lake outlet and
First Point Glacier for the lake tap. Rockfall appears
to be the only potential slope hazard in that zone; there
was no evidence observed in the field to suggest other
types of slope failure.
As indicated on Figure 5-9, the Castle Mountain fault
(Section 5.3), which is a major fault, crosses the
McArthur River just outside the canyon mouth (Section
7.4) where the granitic bedrock has been badly shattered
by fault movement. Surface examination reveals that the·
rock quality progressively improves with distance
upstream from the canyon mouth and the best quality rock
lies between Gash Valley and Misty Valley (Figure 5-l),
beginning about 1-1/2 miles upstream from the powerhouse
location presently shown on the drawings. This location
is based on economic considerations alone, without taking
account of the higher excavations costs that would be
associated with the poorer quality rock. A critical
evaluation of the rock conditions in this area should be
5-55
5.3
5.3.1
included in future studies and a site should be selected
for drilling a deep core hole.
A powerhouse· site at or immediately outside the canyon
mouth, as has been considered in other studies, is likely
to be in the fault zone and subject to fault rupture as
well as high ground motions. In addition, facilities
outside the canyon will be in Tertiary sedimentary rocks
and glacial deposits, not granite.
Seismic Geology
Tectonic Setting
The active faulting, seismicity, and volcanism of
southern Alaska are products of the regional tectonic
setting. The primary cause of the faulting and seismic
activity is the stress imposed on the region by the
relative motion of the Pacific lithospheric plate
relative to the North American plate along their common
boundary (Figure 5-3). The Pacific plate is moving
northward relative to the North American plate at a rate
of about 2.4 inches/year (Woodward-Clyde Consultants,
1981 and references therein). The relative motion
between the plates is expressed as three styles of
deformation. Along the Alaska Panhandle and eastern
margins of the Gulf of Alaska, the movement between
plates is expressed primarily by high-angle strike-slip
faults. Along the northern margins of the Gulf of
Alaska, including the Cook Inlet area, and the central
and western portions of the Aleutian Islands, the
relative motion between the plates is expressed by the
underthrusting of the Pacific plate beneath the North
American plate. At the eastern end of the Aleutian
5-56
L
L
f'
[
[
["
L
l
L
L
L
l
L
i.
------
.... ,,
EURASiAN\\
\
\
PlATE \
150
NOTES
1. Base map from Tarr (1974).
2. After Packer and others (1975). Beikman (1978),
Cormier (1975), Reed and Lamphere (1974),
Plafker, and others (1978)._
PACIFIC.
180
····-------·---······-···-------------------------·--··-·· ------~---··--····-···--------------------'--------~-
AMERICAN
PLATE
Yakutat
Block
150
PlATE
WOODWARD-CLYDE CONSULTANTS
LEGEND
f~t:ff~:~ wrangell Block
.... Relative Pacific Plate Motion
----Plate Boundary, dashed where inferred
A A A Shelf Edge Structure with Oblique Slip
---Intraplate Transform or Strike-Slip Fault
No. DA.Tf. REVISION
ALASKA POWER AUTHORITY
CHAKACHAMNA HYDROELECT~~ROJECT
Plate Tectonic Map
BECHTEL CIVIL & MINERALS, INC.
SAN FRANCISCO
DRAWING No. REV.
Figure !?-3
' l
L
J '
L
r~
L
f:
L
L
Islands, the relative plate motion is expressed by a
complex transition zone of oblique thrust faulting.
The Chakachamna Lake area is located in the region where
the interplate motion is producing underthrusting of the
Pacific plate beneath the North American plate. This
underthrusting results primarily in compressional
deformation, which causes folds, high-angle reverse
faults, and thrust faults to develop in the overlying
crust. The boundary between the plates where under-
thrusting occurs is a northwestward-dipping megathrust
fault or subduction zone. The Aleutian Trench, which
marks the surface expression of this subduction zone, is
located on the ocean floor approx~mately 270 miles south
of the Chakachamna Lake area. The orientiation of the
subduction zone, which may be subdivided into the mega-
thrust and Benioff zone (Woodward-Clyde Consultants,
1981), is inferred at depth to be along a broad inclined
band of seismicity that dips northwest from the Aleutian
Trench.
The close relationship between the subduction zone and
the structures within the overlying crust introduces
important implications regarding the effect of the
tectonic setting on the Chakachamna Lake Project. The
subduction zone represents a source of major earthquakes
near the site. Faults in the overlying crust, which may
be subsidiary to the subduction zone at depth, are
sources of local earthquakes and they may present a
potential hazard for surface fault rupture. This is of
special concern pecause the Castle Mountain, Bruin Bay,
and several other smaller faults have been mapped near to
the Chakachamna Lake Hydroelectric Project area
5.3.2
5.3.2.1
(Detterman and others, 1976; Magoon and others, 1978).
Future activity on these faults may have a more profound
affect on the seismic design of the project structures
than the underlying subduction zone because of their
closer proximity to proposed project site locations.
Historic Seismicity
Regional Seismicity
Southern Alaska is one of the most seismicially active
regions in the world. A number of great earthquakes
(Richter surface wave magnitude Ms 8 or greater) and
large earthquakes (greater than MS 7) have been recorded
during historic time. These earthquakes have primarily
occurred along the interplate boundary between the
Pacific and North American plates, from the Alaskan
panhandle to Prince William Sound and along the Kenai and
Alaska Peninsulas to the Aleutian Islands. Among the
recorded earthquakes are three great earthquakes that
occurred in September 1899 near Yakutat Bay, with
estimated magnitudes Ms of 8.5, 8.4, and 8.1 (Thatcher
and Plafker, 1977). Ground deformation was extensive and
vertical offsets ranged up to 47 ft. (Tarr and Martin,
1912); these are among the largest known displacements
attributable to earthquakes. Large parts of the plate
boundary were ruptured by these three earthquakes and by
twelve others that occurred between 1897 and 1907; these
included a magnitude Ms 8.1 event on 1 October 1900
southwest of Kodiak Island (Tarr and Martin, 1912; McCann
and others, 1980) and a nearby magnitude Ms 8.3
earthquake on 2 June 1903, near 57° north latitude, 156°
west longitude (Richter, 1958).
5-60
(
L
r l ~
[
r
J
\
L
L
I
L
r .
f
I ~
[
L:
L
h -.-'
c
E
l
b
r
L
L
5.3.2.2
A similar series of major earthquakes occurred along the
plate boundary between 1938 and 1964. Among these
earthquakes were the 1958 Lituya Bay earthquake (Ms 7.7)
and the 1972 Sitka earthquake (Ms 7.6), both of which
occurred along the Fairweather fault system in southeast
Alaska; and the 1964 Prince William Sound earthquake (Ms
8.5), which ruptured the plate boundary over a wide area
from Cordova to southwest of Kodiak Island and which
produced up to 39 ft. of displacement (Hastie and Savage,
1970). Figure 5-4 shows the aftershock zones of these
and other major earthquakes in southern Alaska and the
Aleutian Islands. The main earthquakes and aftershocks
are inferred to have ruptured the plate boundary in the
encircled areas.
Three zones along the plate boundary which have not
ruptured in the last 80 years have been identified as
"seismic gaps" (Sykes, 1971). These zones are located
near Cape Yakataga, in the vicinity of the Shumagin
Island, and near the western tip of the Aleutian Chain as
shown in Figure 5-4. The Yakataga seismic gap is of
particular interest to the project because of its
proximity to the site region. The rupture zone of a
major earthquake filling this gap has the potential to
extend along the subduction zone to the north and
northwest of the coastal portion of the gap near Yakataga
Bay.
Historic Seismicity of the Project Study Area
The historic seismicity within 90 miles of the project
area, approximately centered on the east end of
Chakachamna Lake, is shown in Figures 5-5, 5-6, and 5-7.
The earthquake locations are based on the Hypocenter Data
-s-t=il
File prepared by NOAA (National Oceanic and Atmospheric
Administration, 1981). The Hypocenter Data File includes
earthquake data from the u.s. Geological Survey and other
sources and represents a fairly uniform data set in terms
of quality and completeness since about 1964.
Based on Figures 5-5, 5-6, and 5-7 and data available in
the open literature, the seismicity of the project area
is primarily associated with four principal sources: the
subduction zone, which is divided into two segments--the
Megathrust and Benioff zone (Woodward-Clyde Consultants,
1981,; Lahr and Stephen, 1981); the crustal or shallow
seismic zone within the North American Plate; and
moderate to shallow depth seismicity associated with
volcanic activity. The seismic sources are briefly
discussed below in terms of their earthquake potential.
The Megathrust zone is a major source of seismic activity
that results primarily from the interplate stress
accumulation and release along a gently inclined boundary
between the Pacific and North American plates. This zone
is the source area of many of the large to great earth-
quakes, include the Ms 8.5 1964 Prince William Sound
earthquake, which ruptured along the inclined plate
boundary from the eastern Gulf of Alaska to the vicinity
of Kodiak Island. The maximum magnitude for an
earthquake event along the Megathrust zone is estimated
to be Ms 8.5 (Woodward-Clyde Consultants, 1980, 1981).
The Benioff zone portion of the subduction zone is
believed to be restricted to the upper part of the
descending Pacific plate, which lies beneath the North
American plate in southern Alaska. This zone is the
source of smaller magnitude and more continuous
5-62
J
l .
l
c
t'
L
r.
L
l :
r-
L
r
L
L
110" I&G"
LEGEND
01964
-::
I
l.
ISO"
I
. J
NOTE
1. Modified after Davies and House (1979)
WOODWARD-CLYDE CONSULTANTS
~ ---~--
--·-----· -· --·---
Location and year of major
earthquake; rupture zones
including aftershock areas
are outlined
Inferred direction of motion
of Pacific plate
Trench axis
Approximate transform plate
margin
No. DATE REVISION
ALASKA POWER AUTHORITY
ANCHORAGE, ALASKA
CHAKACHAMNA HYDROElECTRIC PROJECT
Major Earthquakes and
Seismic Gaps in Southern Alaska
BECHTEL CIVIL & MINERALS, INC.
SAN FRANCISCO
OESION£0
ENGR SUI"V
I
!
l
1
J
I.
I
j
j
-154.00
62-08
62.00
-153-00
(!)
•MT. STONEY
-152-00
• SNOWCAP MOUNTAIN
GOLDPAN PEAK •
61 .oo
I'J
TURQUOISE LAKE
60.50
I'J. C) C)
C) MT. SPURR
I'J C) I'J C) $
0
C'l )f_OCKADE LAKE
C)
I'J I'J
I'J I'J
• REDOUBT VOLCANO
I'J C)
I'J
I'J I'J
-150-00
C) 52.08
~ 62.00
I'J
I'J
(!)
(!)
FIR& ISLAND
C) C)'>Jjf
C)
5 I -00
C)I'J
I'J (!)(!)
('JI'J I'J
C)
(9 (9
(9 (!) I'J
C) C) <!>
rP C) KENAI
5 C) I'J
60.50 C) I'Ja:::'l STERLING
I'J~I'J
I'J I'Jr:~~N ~L:ND
C)Q2) ~ (!) I'J C) I'J C) I'J mC)
60.33 ~~----------+---~~--=---~----~I'J------~--+-~~~~~~------~----4---~--~~~---+------------~~~------~~60-33
I'J
C) [!]SKILAK LAKE
"' -154 ·00 -153-50 -153-00 -152-50 -152-00 -151-50 -151-00 -150-50 -
150
"
00
WOODWARD-CLYDE CONSULTANTS
0 5 10 15 20 Miles
e-+3
E3 E3 F3
0 5 10 15 20 25 Kilometers
NOTE
LEGEND
REPBRTEO MAGNITUDE
CJ s.o
C) 7-0
C) 6.0
C) 5.0
C) 4-0
(9 3.0
"' 2-0 I .0 & No Reported Magnitude
INTENSITY <Y XII
<Y XI
<2)x v IX
~ VIII
~ VII
~
~
VJ
v
1. Magnitude symbol sizes are shown on
a continuous nonlinear scale
No. DATE REVISION
Historic Earthquakes of All Focal Depths
in the Site Region from 1929 Through
1980
BECHTEL CIVIL & MINERALS, INC.
Figure -5-5
1
j
\
J
]
]
J
)
_j
J
J
J
50 -150-00
-ts1
4_·_oo _________ -_15~3_-_so _________ -_15~3--_o_o ________ -~1~52~-~s~o ________ -~1~52~-~o~o ________ -_1~5rt.-4so ______ :-1~5~1~-o~o~--------~1 ~·5~0~--~m~--t52.os 52.08 )-u
52.00
51 .so
51 .oo
50.50
+ +
C9
+C)
(1)
• MT. STONEY. [!)
[!)
CJl!'l
[!)
[!)
+ +C)
• SNOWCAP MOUNTAIN
+
C9 [!)
[!) ~ C6 [!) ~
[!). C) (1)
C) MT. SPURR
GOLDPAN PEAK • [!) [!)
[!)
(1) c®C9
m@ + [!)~ C) ct-~ [!) ~[!) [!)(9 SKWENTNA • -'-Z:.J [!)
@
+C)
C) C)[!)[!)~~
cB [!) [!) [!)
[!)
C)
[!)
+ [!) till
!'l ,..!Je
MT. SUSITNA [!)
(!);+
BELUGA LAKE
[!) C)
[!) [!)
[!) C) [!) [!)
[!) [!)
[!)
Fl RE ISLAND [!) [!)
HAMNA LAKE[!)
KENIBUNA LAKE [!)
(1) ~ "))
C)
~ [!) C) C)
+
[!)
TURQUOISE LAKE
[!) [!)
C)
C)
[!)
[!)
[!)
[!)
[!)C) + [!) C) +
"<'J Jf,_OCKADE LAKE
~
[!)
[!) [!)
[!)
[!) [!) [!)
C)
[!)
[!)
[!) [!)
[!)
[!)
0 REDOUBT VOLCANO [!) (ld [!) C) [!) [!) A~IN !SLAND
[!)
[!)
C)
[!) [!)
[!)
(9(9 [!)
[!)
[!)
[!) (1)
C)
C) C)
KENAI
• C) [!)
(D STERLING
[!)[!)u [!)
[!)
52.00
51 .so
61.00
C)
50.50
-$-C) (!) [!) • :f[!) ~ C) +
C) C9 C)~ C) [!) [!) C) : [!) rn mc:J c:J [!)SKILAK LAKE
~~~----------+---~~~(9~--+-----~------~-+~~~~~~--~~~[!)~--~~~--~~~--~~~------~~~~------~~50.33 50.33 :r [!) -150.50 - 1 50.00
.j, -154.00 -153-50 -153.00 -15?.fi[1 -1fi?.[1[1 -151-50 -151-00
0 5 10 15 20 Miles
,......_.. I
WOODWARD-CLYDE CONSULTANTS 0 5 10 15 20 25 Kilomet~rs
LEGEND
REPORTED MAGNITUDE
"' .
[']
8.0
7.0
5.0
s.o
4.0
3.0
2.0
I .0
No Reported Magnitude
INTENSITY
~XII
~XI
~X v IX
<:> VIII
~ VII
~
~
VI
v
NOTE
1. Magnitude symbol sizes are shown on
a continuous nonlinear scale
No. DATE REVISION
ALASKA POWER AUTHORITY
ANCHORAGE, ALASKA
CHAKACHAMNA HYDR_Q_HECT_RLG_P.ftQJECT
Historic Earthquakes of Focal Depth
Greater Than 20 Miles in the Site
Re ion from 1929 Throu h 1980
BECHTEL CIVIL & MINERALS, INC.
DESIGNED
ENGR SUPV
REV.
Figure 5-6
\
I
l
J
l
J
j
J
52.08
52.oo
51 .so
51 .oo
50.SO
-154.00 -153.SO -1S3.00 -1S2.SO -1S2.00
+ + (!l
(!]
• MT. STONEY
C)
-+
• SNOWCAP MOUNTAIN
(!] • MT. SPURR
GOLD PAN PEAK •
+
~NALAKE
KENIBUNA LAKE
+ +
;J
BLOCKADE LAKE
TURQUOISE LAKE
+ REDOUBT v6LCANO •
-1S1 .so -1S1 .oo -1SO.SO -JSr'l.rJO
1-tj2 .cc
cl +C) (')(')
62.00 + ~ (')
~sKWENTNA
(!] (!] ~ (')C) (!]
(I)
(!]
0 @
(')
C) (!]
WILLow•
(!]
(I)
C)
(!] (!]
C)
@ (f) b 1 . so
MT. SUSITNA • (!]
(I)
BELUGA LAKE
C)
FIRE ISLAN~
C)
(!) -r61 -00
~i (')
(') '(... ,~\...
coo
60.50
-1-
50 · 33-1St;4--;.o;-;;o~----_--:-_ 1-:-sl--3 --=. 5-0-----_-
1
-!
53
___
0
_
0
-----_-!
5
-+
2
-.-'i[l--f----_::=-+-------+-+-----+-------:-±-:-::------:::_--;-1 :Jso~8ri 33
0 5 10 15 20 Miles
WOODWARD·CL YDE CONSULTANTS 0 510152025 Kilometers
LEGEND
REPGRTED MAGNITUDE
C) 8.0
C) 7.0
C) 6.0
C) s.o
Q) 4 .o
(') 3.0
"' 2.0
1 .o & No Reported Magnitude
INTENSITY
~ X I I
v XI
<Y X
<2> I X
<0> VI I I
<2> VII
~ VI
~ v
NOTE
1. Magnitude symbol sizes are shown on
a continuous nonlinear scale
No. DATE FIE VISION
ALASKA POWER AUTHORITY
ANCHORAGE, ALASKA
CHAKACHAMNA HYDROEL~CU:H_CJROJECT
Historic Earthquakes of Focal Depth Less
Than 20 Miles in the Site Region from ·
1929 Throu h 1980
BECHTEL CIVIL & MINERALS, INC.
Figure 5-7
l :
J'
I
{
L
L'
r
L
earthquake activity relative to the Megathrust zone. No
earthquakes larger than about Ms 7.5 are known to occur
alony the Benioff zone and therefore, a maximum magnitude
earthquake cf Ms 7.5 is estimated for th5s zone
(Woodward-Clyde Consultants, 1981).
The primary source of earthquakes in the crustal or
shallow seismic zone is movement along faults or other
structures due to the adjustment of stresses in the
crust. As shown in Figure 5-7, the historic seismicity
of the cr,~stal zone withiT'l 8. larrH; rr:trt of the ;_)tOj':O'ct-
study area is low. The data base used to compile the
historic seismicity of the crustal zone for this study
has no re~orded earthquakes i~ the viciT'lity of
Chakachamna Lake.
The majority of the recorded earthquakes shown in Figure
5-7 are located along the eastern and southern margins of
the project study. area. Most of these events have not
been correlated or associated with any known crustal
structures, with the possible exception of one event that
is associated with the castle Mountain fault. As
discussed in Section 5.3.3.3, the Castle Mountain fault
is one of the two major faults present in the project
study area. It passes within a mile or less of the
proposed project facilities in the McArthur River
drainage and within 11 miles ?f the proposed facilities
at Chakachamna Lake. Evidence for displacment of
Holocene deposits has been reported in the Susitna
lowlands, in the vicinity of the Susitna River (Detterman
and others, 1976a). Although a number of recorded
earthquakes are located along the trend of the castle
Mountain fault (Figure 5-7), only one event, an Ms 7
earthquake in 1933, has been associated with the fault
5-71
(Woodward-Clyde Consultants, 1980b) .. A maximum magnitude
earthqua~e of Ms 7.5 has been estimated for the Castl~
Mountain fault (Woodward-Clyde Consultants, 1981).
Further studies are needed to assess the possible
association of other historic earthquakes shown in Figure
5-7 with candidate significant features identified in the
fault investigation phase of the project study.
Because of the proximity of the project site to active
volcanoes of the Aleutian Islands-Alaska Pehinsula
volcanic chain, including Mt. Spurr which is located
immediately northeast of the Chakachamna Lake, volcanic-
induced earthquakes are considered a potential seismic
source. Active volcanism can produce small-to-moderate
magnitude earthquakes at mqderate-to-shallow depths due
to the movement of magma or local adjustments of the
earth's crust.
Occasionally, severe volcanic activity such as phreatic
explosions or explosive caldera collapses may be
accompanied by significant earthquake events. Because
such large volcanic events are rare, there is little data
from which to estimate earthquake magnitudes that may be
associated with them. However, because of the
similarities in characteristics of the Mount St. Helens
volcano to those of the Aleutian chain (including Mt.
Spurr), it is reasonable to assume that earthquakes
associated with the recent Mount st. Helens eruption of
May 1980 may also occur during future volcanic activity
of Mt. Spurr and others in the Aleutian chain. The
largest earthquake associated with the Mount St. Helens
explosive eruption that occurred on 18 May 1980 had a
magnitude of 5.0. Numerous smaller earthquakes with
5-72
r
[ :
t
i '
~-w
r
L.
' ' \' l
l
l
l '
r·
f '
f'
f-
5.3.3
5.3.3.1
magni~udes ranging from 3 to 4 were recorded during the
period preceding the violent rupture of Mount St. Helens
(U.S. Geological survey, 1980).
As part of a volcanic hazard monitoring program, the u.s.
Geological survey has been operating several seismograph
stations in the vicinity of Mt. Spurr to assess its
activity. Data acquired by these stations are not
presently available but will be released in 1982 as an
Open-File Report (Lahr, J. c., personal communication,
1981).
Fault Investigation
Approach
The objectives of the Chakachamna Lake Hydroelectric
Project seismic geology task are:
(1) to identify and evaluate significant faults within
the project study area that may represent a
potential surface rupture hazard to project
facilities and
(2) to make a preliminary evaluation of the ground
motions (ground shaking) to which proposed project
facilities may be subjected during earthquakes. In
order to meet the specific task objectives and to
provide a general assessment of the seismic hazards
in the project area, the seismic geology study was
designed and conducted in a series of sequential
phases (Figure 5-8).
5-73
5.3.3.2 Work to Date
The study phases reported here include review of
available literature, analysis of remotely sensed data,
aerial field recpnnaissance, and acquisition of low-sun-
angle aerial photographs.
Information of a geologic, geomorphic, and seismologic
nature available in the open literature was evaluated to
identify previously reported faults and lineaments that
may be fault related within the pr~ject study area.
Geologists presently working in the area or familiar with
the study area were also contacted. The locations of all
faults and lineaments derived from the literature review
and discussions with other geologists were plotted on
1:250,000-scale topographic maps.
Lineaments interpreted to be fault related were also
derived from the analysis of high-altitude color-infrared
(CIR) aerial photographs (scale 1:60,000) and Landsat
imagery (scale 1:250,000) of the study area outlined by
the 30-mile diameter circle on Figure 5-9. These
lineaments were initially plotted (with brief annotation)
on clear mylar overlays attached to the photographs and
images on which they were observed. The lineaments were
then transferred and plotted on the 1:250,000-scale
topographic maps. The faults and lineaments identified
from the review of the available literature and
interpretation of CIR photographs and landsat imagery
comprise a preliminary inventory of faults and lineaments
within.the study area.
The faults and lineaments in the preliminary inventory
were then screened on the basis of a one-third length
5-74
r
\ .
[;
L
[
l
L
r
[
L
b
REVIEW AVAILABLE
LITERATURE
REMOTE SENSING
INTERPRETATION
APPLY LENGTH-DISTANCE SCREENING CRITERIA
WOODWARD-CLYDE CONSULTANTS
ACQUIRE AND ANALYZE
LOW-SUN-ANGLE AERIAL PHOTOGRAPHY
MD. DATE REVISION
ALASKA POWER AUTHORITY
ANCHORAGE, ALASKA
CHAKACHAMNA HYDROELECTRIC PROJECT
Seismic Geology Investigation Sequence
BECHTEL CIVIL & MINERALS, INC.
SAN FRANCISCO
CHECKED
..... 'D -
DRAWING No. AEV.
Figure 5-8
l
-~
-J
-l
')
-]
)
J
J
1
J
1
J
J
J
_1
J
--~,-~
~
-o
"'
EXPLANATION
- -• ]. Candidate lignif~e~nt fault or lineament. dashed
where approxlmatl!ly located, dotted where
concealed, queried where lccatlon uncertllln
or inferred 0 Project Study Area. Reconnaissance assessment
of surfsce fa~lt rupture by Woodward-Clyde
Coi"'SSJitantJ during 1981 field IUSOI'I
~ Anm discuaed In Section 5.3.3.3
10 15
SCALE IN MILES
r.
[ ·_
~
r:
~-
L
[
L
r L
length-distance criterion to select those faults and
lineaments within the study area that potentially could
produce surface rupture at sites proposed for
facilities. The length-distance criterion speGifies a
minimum length for a fault or lineament and a minimum
distance from the project site for a fault or lineament
to be retained for further study. For example, a fault
or lineament that trends toward the project site and has
an observed length of 10 miles would be selected for
further study if it was less than 30 miles from the
project site. A fault or lineament with the same trend
and same length, but at a distance of greater than 30
miles from the project site would not be selected for
further study.
The one-third ler~th-distance criterion used is based on
the empirical data that suggest that fault rupture rarely
occurs along the full length of a fault (except for very
short faults) during an earthquake (Slemmons, 1977,
1980). The length-distance criterion also takes into
account
(1) the possibility of surface rupture within or near to
the project site occurring on faults that may be
identified only in areas remote from the project
site, but which in actuality may extend undetected
to the project site, and
(2) the fact that at greater distances from the project
site, only longer faults would have the potential of
producing rupture at the site.
Regional faults in southern Alaska that are known or
inferred to be active but are distant from the project
5-79
study area were not evaluated for surface rupture
potential. These faults, because of their activity, were
considered to be potential seismic sources and therefore
were evaluated in terms of their potential for causing
significant ground motions at the project site.
The faults and lineaments selected for further st~dy on
the basis of the length-distance criterion or because
they appeared to be potential sources of significant
ground shaking wer~ transferred to 1:63,360-scale
topographic maps for use during the aerial reconnaissance
phase. During the aerial reconnaissance, the faults were
examined for evidence (geologic features, and geomorphic
expression) that would suggest whether or not youthful
activity has occurred. The lineaments were examined to
r-
t
r
l
[
L
assess: ( ·
(1) whether they are or are not faults, and
(2) if they are not faults, what is their origin. For
those lineaments that were interpreted to be faults
or fault-related, further examination was made to
look for evidence that would be suggestive of
youthful activity.
After the aerial reconnaissance evaluation of the faults
and lineaments, each feature was classified into one of
three categories:
(1) a candidate significant feature;
(2) a non-significant feature; or
(3) an indeterminate feature.
5-80
l
L
L
I
L
l.
L
r
[
l
L
[
t
[
l
L
L~
[
5.3.3.3
candidate significant features are those that at some
point· along their length, exhibit geologic morphologic,
or vegetational expressions and characteristics that
provide a strong suggestion of youthful fault activity.
Non-significant features are those, which on the basis of
the aerial reconnaissance, apparently do not possess
geologic, morphologic, or vegetational characteristics
and/or expressions suggestive of youthful fault activity;
it was possible to identify non-fault-related origins for
many features in this category. Indeterminate features
are those lineaments that posses some ~eo1ogic,
morphologic, or vegetational characteristics or
expressions that suggest the lineament may be a fault or
fault-related feature with the possibility of youthful
activity, but for which the evidence is not now
compelling.
Candidate Significant Features
The candidate significant and indeterminate features
identified during the first four phases of this task will
require further study in order to evaluate their
potential hazard to the proposed project facilities.
These features occur in three principal areas, which are
designated Areas A, B, and C (Figure 5-9) and are
discussed in the following sections. The features
presented in each area are discussed in terms of their
proximity and orientation with respect to the nearest
proposed project facility, previous mapping or published
studies in which they have been identified, their
expression on CIR photographs, and observations made
during the aerial reconnaissance phase of the study.
5-81
Area A
Area A is bounded by Mt. Spurr and the Chakachatna River
and Chakachamna Lake and Capps Glacier (Figure 5-9).
Four candidate significant features, SU 56 and CU 50, CU
52 and SU 150, are located within this area.
Feature CU 50 is a curvilinear fault that trends roughly
east-west and extends from the mouth of the Nagishlamina
River to Alice Glacier, a distance of about 5 miles. The
western end of the feature is approximately 2 miles north
of the lake outlet. CU 50 was initially identified on
CIR photographs and is characterized by the alignment of:
(1) linear slope breaks and steps on ridges that project
southward from Mt. Spurr, east of Barrier Glacier,
with
(2) a linear drainage and depression across highly
weathered granitic rocks west of Barrier Glacier.
During the aerial reconnaissance, disturbed bedded
volcanic flows and tuffs were observed on the sides of
canyons where crossed by the feature east of Barrier
Glacier. These volcanic rocks are mapped as primarily
being of Tertiary age, but locally may be of Quaternary
age (Magoon and others, 1976). The possibility of the
disturbed volcanic rocks being of Quaternary age suggests
that CU 50 may be a youthful fault. The dense vegetation
west of Barrier Glacier prohibited close examination of
the fault in the granitic terrain.
CU 50 is classified as a candidate significant feature on
the basis of its close proximity to proposed project
5-82
l :
(~
[ :
[:
[~
l'
{
[ -
l
r L~
l:
[ .
[-
r,
l
l
r ,
I -
r ~
r
L
L
L
L
L
facility sites and because it appears to displace
volcanic rocks that may be Quaternary in age.
Feature cu 52 is a composite feature that consists of a
fault mapped by Barnes {1966) and prominent morphological
features observed on CIR photographs. The feature tends
N63°E and extends along the mountain front from Capps
Glacier to Crater Peak Glacier, a distance of about 7.5
miles {Figure 5-9). The southwestern end of this feature
is approximately 8 miles from the outlet of Chakachamna
Lake. Along the northeastern portion of CU 52, from
Capps Glacier to Brogan Glacier, the feature is defined
by a fault that separates Tertiary granitic rocks from
sedimentary rocks of the Tertiary West Foreland formation
{Magoon and others, 1976). The southwestern segment,
from Brogan Glacier to the Crater Peak Glacier, which
extends the mapped fault a distance of 3 miles, was
identified on the basis of aligned linear breaks in
slope, drainages, and lithologic contrasts. During the
field reconnaissance, a displaced volcanic flow was
observed at the southwest end of the feature. Over most
of its length, the fault was observed to be primarily
exposed in bedrock terrain; youthful lateral moraines
crossed by the fault did not appear to be affected.
This fault is considered to be a candidate significant
feature because of its prominent expression in the
Tertiary sedimentary and volcanic rocks crossed by the
fault and because of its close proximity to the proposed
project facilities. In addition, the fault may extend
farther to the west along the mountain front than was
observed on the CIR photographs or during the brief
reconnaissance. If such is the case, it may connect with
feature CU 50.
5-83
Feature SU 56 consists of two segments, a fault and a
lineament. The combined feature trends N78°E and can be
traced from the toe of Barrier Glacier to the edge of the
mesa like area between the Chakachatna River and Capps
Glacier, a distance of about 11 miles (Figure 5-9). The
western extent of the fault segment is unknown, but if
the lineament segment, defined by a linear depression
across the toe of Barrier Glacier is associated with the
fault, it may extend into and along the south side of
Chakachamna Lake, very near the proposed lake tap.
SU 56 was recognized on the CIR photographs on the basis
of the alignment of morphologic and vegetation features:
a linear depression across the piedmont lobe of Barrier
Glacier; a narrow linear vegetation alignment across the
alluvial fan east of and adjacent to Barrier Glacier;
small subtle scarps between Alice and Crater Peak
Glaciers: and a prominent scarp and possibly a displaced
volcanic flow between Crater Peak and Brogan Glaciers.
During the field reconnaissanc~, all of the character-
istics observed on the CIR photographs could be
recognized with the exception of the vegetation alignment
east of Barrier Glacier. At two locations along the
feature, between Alice and Brogan Glaciers, displaced
volcanic flows and tuffs were observed. At both
localities the sense of displacement was down on the
south side relative to the north side. The amount of
displacement could not be measured due to the rugged
terrain at the two locations. At the eastern end of the
fault, near Brogan Glacier, the fault is on trend and
appears to connect with one of seven faults observed in
ridges along the eastside of Brogan Glacier where Barnes
(1966) mapped two prominent bedrock faults.
5-84
l
[
r
L~
{
[ .
f
l
r--
l
i .
I
L
{
L
[
Feature SU 56 is classified as a candidate significant.
feature because:
(1) it displaces volcanic rocks that may be of
Quaternary age;
(2) the linear depression across the toe of Barrier
Glacier is on trend with the fault; and
(3) the westward projection of the feature would pass
very close to the proposed project facilities along
the south side of Chakachamna Lake.
Feature SU 150 is composed of a series of parallel
west-to-northwest-trending faults mapped by Barnes
(1966). These faults are located on the Sou~hwest side
of the mesa-like area between Brogan and Capps Glacier,
approximately 12 miles east of the outlet of Chakachamna
Lake (Figure 5-9). These faults are exposed east of
Brogan Glacier along a nearly vertical canyon wall that
is deeply eroded into Tertiary sedimentary rocks mapped
as the West Foreland formation (Magoon and others, 1976).
During the aerial reconnaissance, five additonal faults
were observed along the wall of the canyon, south of the
two faults mapped by Barnes (1966). Displacement on
these faults, as well as on the two mapped by Barnes
(1966), appears to be on the order of a few feet to a few
tens of feet, with the south side up relative to the
north side. An exception to this is the southernmost
fault, on which the displacement appears to be relatively
up on the north side. During the aerial reconnaissance,
the faults could not be traced for any appreciable
distance beyond their approximate length of 2 miles
5-85
mapped by Barnes (1966). The southernmost fault, which
is on trend with Feature SU 56, is probably an extension
of that feature.
The series of faults associated with Feature SU 150 are
included in this report as candidate significant features
because of the probable connection of the southernmost
fault in the series with Feature SU 56, which consists of
morphologic features that are suggestive of youthful
fault activity.
Area B
Area B includes the Castle Mountain fault and several
parallel lineaments (SU 49, SU 84, and CU 56, Figure
5-9). The Castle Mountain fault is one of the major
regional faults in southern Alaska. It trends northeast-
southwest and extends from the Copper River basin to the
Lake Clark are~, a distance of approximately 310 miles
I
[
!
t
r
L
f
r·
I
(Beikman, 1980). The Castle Mountain fault crosses the ['
mouth of the McArthur River Canyon near Blockade
Glacier. The Castle Mountain fault is reported to be an
oblique right-lateral fault with the north side up
relative to the south side (Grantz, 1966; Detterman and
others, 1974, 1976a, b).
The Castle Mountain fault is a prominent feature for most
of its mapped length. The segment northeast of the
Susitna River is defined by a series of linear scarps and
prominent vegetation alignments in the Susitna Lowlands
and lithologic contrast in the Talkeetna Mountains
(Woodward-Clyde Consultants, 1980; Detterman and others,
1974, 1976a). Between the Susitna and Chakachatna
Rivers, the fault is less prominent but is marked by a
5-86
L
L
L
r·
[
L
L
f
h
L
L
L
series of slope breaks, scarps, sag ponds, lithologic
contrasts, and locally steeply dipping, sheared
sedimentary rocks that are generally flat to gently
dipping away from the fault (Schmoll and others, 1981;
Barnes, 1966). Southwest of the Chakachatna River,
toward the Lake Clark_area, the Castle Mountain fault is
well qefined and expressed by the alignment of slope
breaks, saddles, benches, lithologic contrasts between
plutonic and sedimentary rocks, shear zones, and a
prominent topographic trench through the Alaska-Aleutian
Range Batholith (Detterman and others, 1976b).
Displacement on the Castle Mountain fault has been
occurring since about the end of Mesozoic time (Grantz,
1966). The maximum amount of vertical displacement is
about 1.9 miles or more (Kelley 1963; Grantz, 1966). The
maximum amount of right-lateral displacement is estimated
by Grantz (1966) to have been several tens of miles along
the eastern traces of the fault. Detterman and others
(1967 a,b) cited 10 miles as the total amount of right-
lateral displacment that has occurred along the eastern
portion of the fault and about 3 miles as the maximum
amount of right-lateral displacement that has occurred
along the western portion, in the Lake Clark area.
Evidence of Holocene displacement has only been observed
and documented along a portion of the Castle Mountain
fault in the Susitna Lowland (Detterman and others, 1974,
1976a). During their investigation, Detterman and others
(1974) found evidence suggesting that 7.5 ft. of dip-slip
movement has occurred within the last 225 to 1,700
years. The amount of horizontal displacement related to
this event is not known. However, Detterman and others
5-87
(1974) cited 23 ft. of apparent right-lateral displace-
ment of a sand ridge cro~sed by the fault. Bruhn (1979),
based on two trench excavations, reported 3.0 to 3.6 ft.
of dip-slip displacement, with the north side up relative
to the south side, along predominately steeply south-
dipping fault traces. He also reported 7.9 ft. of
right-lateral displacement of a river terrace near one of
the trench locations.
On the CIR photographs, the Castle Mountain fault is
readily recogpizable on the basis of the alignment of
linear morphologic and vegetation features. The most
notable features were observed in areas where bedrock is
exposed at the surface and include: the prominent slope
break that occurs along the southside of Mount Susitna
and Lone Ridge; the prominent bench across the end of the
Chigmit Mountains, between the McArthur and Chakachatna
Rivers; and the alignment of glacial valleys in the
Alaska Range, one of which is occupied by Blockade
Glacier. In areas covered by glacial deposits, the
expression of the Castle Mountain is more subtle and is
dominantly an alignment of linear drainages, depressions,
elongated mounds, and vegetation contrasts and alignments.
Based on interpretation of the CIR photographs and aerial
reconnaissance observations, three lineaments (SU 49 and
portions of su 84 and CU 56) are believed to be traces or
splays of the Castle Mountain fault. Lineament SU 49 is
approximately 4 miles long, trends northeast, and is on
line with the segment of the fault mapped between Lone
Ridge and Mount Susitna (Figure 5-9). SU 49 was
identified on the basis of the alignment of linear
drainages and saddles on a southeast-trending ridge with
a vegetation contrast in the Chakachatna River flood
5-88
l '
(
L
r
l
r~
r~
L
L
L
r
L
L
{
L
plain and by a possible right-lateral affect or the east
facing escarpment along the west side of the Chakachatna
River.
Lineament SU 84 partially coincides with the mapped trace
of the Castle Mountain fault southwest of Lone Ridge. At
the Chuitna River, the mapped trace of the Castle
Mountain fault bends slightly to the north (Figure 5-9)
whereas lineament SU 84 continues in a more southwesterly
direction. Features along SU 84 that make it suspect are
the alignment of an elongate mound on trend with steeply
dipping sedimentary rocks exposed along the banks of the
Chuitna River and the eroded reentrant along the high
bluff on the northeast side of the Chakachatna River
(Nikolai escarpment).
Lineament CU 56 is located east of Lone Ridge; it trends
N70°E, is 7 miles long, and is an echelon to the mapped
trend of the Castle Mountain fault. CU 56 was identified
on the CIR photographs on the basis of the alignment of
linear drainages and depressions and vegetation contrasts
and alignments. Duririg the aerial reconnaissance, a
broad zone of deformed sedimentary rocks was observed on
the location where CU 56 crosses the Beluga River. This
locality coincides with a zone of steeply dipping
sedimentary rocks mapped by Barnes (1966).
Area C
Area C is located south to southeast of the proposed
project facilities sites, along the southeastern side of
the Chigmit Mountains between the North Fork Big River
and McArthur River (Figure 5-9). Three prominent north-
east trending parallel features, SU 16, SU 22, and SU 23,
5-89
are located in this area. SU 16 is an inferred fault
that transverses both granitic bedrock and glacial
deposits. su 22 and SU 23 are primarily confined to the
granitic bedrock terrain.
Feature SU 16 is the longest of the three northeast-
southwest trending features located in ARea C. This
feature extends from approximately the intersection of
the McArthur and Kustatan Rivers southwestward across a
broad bench and along the northeast trending segment of
the North Fork Big River, a distance of about 25 miles
(Fiyure 5-9). SU 16 may extend even farther to the west
if it follows a very linear glacial valley that is
aliyned with the northeast trending segment of the North
Fork Big River. The northern end of SU 16 approaches to
within 10 miles of the proposed project facilities in
McArthur RiYer area.
SU 16 was identified on the CIR.photographs and aerial
reconnaissance on the basis of the alignment of elongate
low hills, linear depressions, vegetation contrasts,
prominent slope breaks, and a lithologic contrast that
form the broad bench like area between the North Fork Big
River and Kustatan Rivers. The southwestern segment of
the feature is defined by the alignment of a linear
portion of the North Fork Big River and a linear glacial
valley north of Double Peak. Duriny the aerial
reconnaissance, no distinctive evidence, such as
displaced lithologic units or bedding or scarps, was
observed to confirm that SU 16 is actually a fault.
Nonetheless, morphologic features that were observed
suggest that SU 16 is a fault and that it may be a
youthful fault.
5-90
do
f
I
[
t
[
r .
t
L
L
r
l -
L
L
L
j
L
SU 16 is included in this report as a candidate
significant fault because the morphologic features
observed on the CIR photographs and during the aerial
reconnaissance strongly suggest that it is a fault and
may be a youthful fault.
Features SU 22 and SU 23 (Figure 5-~) are both northeast
trending linear to curvilinear faults that parallel one
another at a distance of about one mile. Feature SU 22
can be traced from about the McArthur River southwestward
to Black Peak, a distance of about 16 miles. Feature SU
23 is approximately 8 miles in length and extends from
Blacksand Creek southwestward to the north Fork Big River
area. The northeastern ends of the two features (SU 22
and SU 23) approach to within 8 miles of proposed project
facility sites in the McArthur River area. Both features
were recognized on CIR photographs and are defined by the
alignment of prominent linear troughs that are partially
occupied by small lakes and ponds, scarps, slope breaks,
benches, and saddles.
During the aerial reconnaissance, the two features could
be readily traced across bedrock terrain (mapped as
Jurassic to Cretaceous-Tertiary granitic rock; Magoon and
others, 1976) on the basis of their morphologic
features. Slicken-sided and polished surfaces were
observed at several of the scarps and slope break
localities examined; sheared zones were also observed
during the reconnaissance. The southwestern portions of
both features are located in very rugged terrain and are
poorly defined due to the highly jointed granitic rocks
that are present along this segment.
5-91
At the northern end, in the vicinity of Blacksand Creek,
SU 23 appears to splay out with one trace trending tow~rd
SU 22 and one trace trending toward SU 16 (Figure 5-9).
SU 22 also appears to die out in the vicinity of
Blacksand Creek, although there was a subtle tonal
alignment observed on the CIR photographs on the north
side of the creek that suggests it may extend across
Blacksand Creek toward the McArthur River.
SU 22 and SU 23 are included as candidate significant
features because their prominent expression.suggests that
they are major structures and that they may be associated
with SU 16 which is considered a fault with possible
youthful activity.
Area D
Area D (Figure 5-9) includes the Bruin Bay fault, which
is one of the major regional faults in south~rn Alaska.
The Bruin Bay fault is a northeast-trending, moderate-to-
steeply-northwest-dipping reverse fault that extends
along the northwest side of the Cook Inlet from near
Mount Susitna to Bechalaf Lake, a distance of about 320
miles (Detterman and others, 1976b). The fault
approaches as close as approximately 30 miles south to
southwest of the proposed project facilities at
Chakachamna Lake and approximately 20 miles of the
project facilities in the McArthur River.
The northern. segment of the Bruin Bay fault, from about
the Drift River area to Mount susitna, is projected
beneath surficial deposits from its last bedrock exposure
north of Katchin Creek. The projection is based on a
prominent linear depression across Kustatian Ridge,
5-92
r·
l
!
L
l
L
f"
I
L
L
L
alignment of linear lakes and ·depressions in the lowland
area west and north of Tyonek, and highly disturbed and
faulted Tertiary sedimentary rocks along the Chuitna and
Beluga River (Detterman and others, 1976b; MagQon and
others, 1976; Schmoll and others, 1981). To the south of
Katchin Creek, where the fault is exposed in bedrock
areas, the trace of the fault is commonly marked by a
zone of crushed rock a few to several hundred meters wide
and saddles or notches (Detterman and others, 1976b).
The sense of displacement along the fault is reverse with
the north side up relative to the south side (Magoon and
others, 1976; Detterman and others, 1976b). Detterman
and Hartsock (1966) reported left-lateral displacement of
6 miles or less has occurred along the fault in the
Iniskin-Tuxedni region, southwest of the study area. The
youngest unit reported displaced by the Bruin Bay fault
is the Tertiary sedimentary Beluga formation (Magoon and
others, 1976). No displacement of Holocene surficial
deposits between Katchin Creek and the probable junction
of the fault with Castle Mountain fault near Mt. susitna
has been observed or documented (Detterman and others
1976b; Detterman, personal communication, 1981).
During the analysis of the CIR photographs, several
subtle to prominent discontinuous lineaments were
identified along the projected trend of the Bruin Bay
fault across the McArthur and Chakachatna River flood
plains near the Cook Inlet, and along the lowland area
west of Tyonek. The lineaments were examined during the
aerial reconnaissance and no displacement or disturbed
Holocene deposits were observed. Several of the
lineaments, however, did coincide with disturbed or
faulted sedimentary rocks of the Beluga formation exposed
5-93
5.3.3.4
along the Chuitna and Beluga .Rivers. Further work is
needed to assess whether the glacial and/or fluvial
deposits overlying the sedimentary bedrock have been
faulted or disturbed.
Although no evidence has been observed or reported that
would indicate youthful fault activity along the Bruin
Bay fault, several of the lineaments observed on the CIR
photographs are suggestive of youthful fault activity.
On the basis of the lineaments along the projected trace
of the Bruin Bay fault, and the fact that the fault is
suspected to intersect with the Castle Mountain fault,
the Bruin Bay fault is considered for this report to be a
candidate significant feature.
Implications with Respect to the Proposed Hydroelectric
Project
Based on the results of the work to date a preliminary
assessment can be made regarding the potential surface
faulting hazards and seismic sources of ground motion
(shaking) with respect to the proposed project site.
(1) Within the study area, faults and lineaments in four
areas have been identified for further evaluation in
order to assess and better understand their
potential effect on project considerations. For
example, if feature SU 56 is an active fault, its
trend is toward the area proposed for the lake tap
and the extent and activity of this feature clearly
require evaluation.
prove to be capable
both ground shaking
project area.
Several of these features may
of producing earthquakes, thus
and surface rupture in the
5-94
1 '
l '
f
!
l
r l .
I
L
l
L
L
r~
,-
~-
~-
~ ~
( -
[ ~
f ~
L
L
t
L
r:
r
L
L
[
J -
L
r-
5.4
(i) The Castle Mountain fault is located along the
southeast side of the Chigmit Mountains at the mouth
of McArthur Canyon. Although no displacements of
Holocene deposits have been observed or reported for -
the segment of the Castle Mountain fault between the
Susitna River and the Lake Clark area, the fault is
considered an active fault on the basis of the
reported displacement of Holocene deposits east of
the project area in the vicinity of the Susitna
River.
(3) Based on a review of the available literature and
detailed studies conducted for major projects in
southern Alaska there are three potential seismic
sources that may have an effect on the project
site. These include: the subduction zone, which
consists of the Megathrust and Benioff zone; crustal
seismic zone; and severe volcanic activity. The
Castle Mountain fault (crustal seismic source) and
the Megathrust segment of the subduction zone are
expected to be the most critical to the project with
respect to levels of peak ground acceleration,
duration of strong shaking, and development of
response spectra. (see Section 7.4).
References
Barnes, F. F., 1966, Geology and coal resources of the
Beluga-Yentna Region, Alaska: u.s. Geological Survey
Bulletin 1202-C, 54 p.
Beikman, H. M., compiler, 1974, Preliminary geologic map
of the southeast quadrant of Alaska: U.S. Geological
5-95
~-~
I
survey Miscellaneous Field Studies Map MF-612, scale
1:1,000,000. l
Beikman, H. M., compiler, 1980, Geologic map of Alaska: r~
u.s. Geological Survey, scale 1:2,500,000.
Bruhn, R. L., 1979, Holocene displacement measured by
trenching the Castle Mountain fault near Houston,
Alaska: Alaska Division of Geological and Geophysical
surveys, Geological Report 61, 4 p.
Bureau of Reclamation, Chakachamna Project Alaska -
Status report March, 1962: Bureau of Reclamation, Alaska
District Office, Juneau, Alaska, unpublished report, 21 p.
Capps, s. R., 1935, The southern Alaska Range: u.s.
Geological Survey Bulletin 862, 101 p.
Detterman, R. L., and Hartsock, J. K., 1966, Geology of
the Iniskin-Tuxedni Region, Alaska: u.s. Geological
Survey Professional Paper 512, 78 p.
Detterman, R. L., Plafker, G. Hudson T., Tysdal, R. G.,
and Pavoni, N. 1974, Surface geology and Holocene breaks
along the Susitna segment of the Castle Mountain fault,
Alaska: u.s. Geological survey Miscellaneous Field
Studies Map MF-618, scale 1:24,000.
Detterman, R. L., Plafker, G., Tysdal, R. G., and Hudson,
T., 1976a, Geology and surface features along part of the
Talkeetna segment of the castle Mountain-Caribou fault
system, Alaska: u.s. Geological Survey Miscellaneous
Field Studies Map MF-738, scale 1:63,360.
5-96
,-
1._-
r-
L
l
L
L
Detterman, R. L., Hudson, T., Plafker, G., Tysdal, R. G.,
and Hoare, J. M., 1976b, Reconnaissance geologic map
along the Bruin Bay and Lake Clark faults in Kenai and
Tyonek quadrangles, Alaska: u. s. Geological Survey
Open-File Report 76-477, 4 p., scale 1:250,000.
Giles, G. c., 1967, Barrier Glacier investigations and
observations in connection with waterpower studies: u.s.
Geological Survey, unpublished report, 61 p.
Grantz, Arthur, 1966, Strike-slip faults in Alaska:
U.S. Geological survey Open-File Report, 82 p.
Hastie, L. M., and Savage, J. c., 1970, A dislocation
model for the Alaska earthquake: Bulletin of the
Seismological Society of America, v. 60, p. 1389-1392.
Hunt, c. B., 1967, Physiography of the United States: w.
H. Freeman and Co., San Francisco, 480 p.
Jackson, B. L., 1961, Potential waterpower of Lake
Chakachamna, Alaska: U. s. Geological Survey Open-File
Report, 20 p.
Johnson, A., 1950, Report on reconnaissance of Lake
Chakachamna (sic), Alaska: U. S. Geological Survey Open-
File Report, 8 p. plus plates.
Juhle, w., and Coulter, H., 1955, The Mt. Spurr eruption,
July 9, 1953: Transactions, American Geophysical Union,
v. 36, no. 2, p. 199-202.
Karlstrom, T.v., 1964, Quaternary geology of the Kenai
lowland and glacial history of the Cook Inlet region,
5-97
Alaska: u. s. Geological Survey Professional Paper 443,
69 p.
Karlstrom, T. v., Coulter, H. w., Jernald, A. T.,
Williams, J. R., Hopkins, D. M., Drewes, H., Huller, E.
H., and Candon, w. H., 1964, Surficial Geology of
Alaska: U. s. Geological Survey Miscellaneous Geologic
Investigation Map I-557, scale 1:1,584,000.
Kelley, T. E., 1963, Geology and hydrocarbons in Cook
Inlet Basin, Alaska, in Childs, D. E., and Beebe, B. w.,
eds., Backbone of the Americas Symposium: American
Association of Petroleum Geologists Memoir 2, ~· 278-296.
Lahr, J. c., and Stephens, c. D., 1981, Review of
earthquake activity and current status of seismic
monitoring in the region of the Bradley Lake
Hydroelectric Project: U. s. Geologica Survey Report,
prepared for the Department of the Army, Alaska District,
Corps of Engineers, 21 p.
Lamke, R. D., 1972, Floods of the summer of 1971 in
southcentral Alaska: U. s. Geological Survey, Water
Resources Division, Alaska District, Open-File Report, p.
30-31.
Magoon, L. B., Adkison, w. L., and Egbert, R. M., 1976,
Map showing geology, Wildcat Wells, Tertiary plant fossil
. localities, K-Ar age dates, and petroleum operations,
Cook Inlet area, Alaska: u. s. Geological Survey Map
I-1019, scale 1:250,000.
McCann, w. R., Per~z, o. J., and Sykes, L. R., 1980,
Yakataga Gap, Alaska: Seismic history and earthquake
potential: Science, v. 207, p. 1309-1314.
5-98
L
r
l_
Miller, R. D., and Dobrovolny, E~, 1959, Surficial
geology of Anchorage and vicinity, Alaska: U. s.
Geological Survey Bulletin 1093, 128 p.
National Oceanic and Atmospheric Administration, 1981,
Hypocenter Data File Period of Coverage 1929 to 1980:
Environmental Data Services, Boulder, Colorado.
Pewe, T. L. Hopkins, D. M., and Giddings, J. L., 1965,
The Quaternary geology and archeology of Alaska: in
Wright, H. E. and Frey, D. G., eds., The Quaternary of
the United States, Princeton University Press, Princeton,
p. 355-374.
Pewe, T. L., 1975, Quaternary geology of Alaska: u.s.
Geological Survey Professional Paper 835, 145 p.
Plafker, G., 1969, Tectonics of the March 27, 1964,
Alaska Earthquakes: u. s. Geological Survey Professional
Paper 543-I, 74 p.
Porter, s. c., and Denton, G. H., 1967, Chronology of
Neoglaciation in the North American cordillera: American
Journal of Science, v. 265, p. 177-210.
Post, A., 1969, Distribution of surging glaciers in
western North America: Journal of Glaciology, v. 8, no.
53, p. 229-240.
Post, A., and Mayo, L. R., 1971, Glacier dammed lakes and
outburst floods in Alaska: U. s. Geological Survey
Hydrologic Investigations Atlas HA-455.
5-99
Richter, C. F., 1958, Elementary seismology: San
Francisco, Freeman Press, 768 p.
Schmoll, H. R., Szabo, B. J., Rubin, M., and Dobrovolny,
E., 1972, Radiometric dating of marine shells from the
Bootlegger Cove clay, Anchorage area, Alaska: Bulletin,
Geological Society of America, v. 83, p. 1107-1114.
Schmoll, H. R., Yehle, L. A., Gardner, C. A., 1981,
Preliminary geologic map of the Congahbuna area, Cook
Inlet Region, Alaska: U. s. Geological Survey Open-File
Report 81-429, 8 p.
Schmoll, H. R., Pasch, A. D., Chleborad, A. F., Yehle, L.
A., and Gardner, c. A., in press, Reconnaissance
engineering geology of the Beluga Coal resources area,
south-central Alaska, in Rao, P. D., ed., Focus on
Alaska's Coal '80, Conference, Fairbanks, Alaska,
Proceedings: Fairbanks, University of Alaska, School of
Mineral Industry MIRL Report No. 47.
Slemmons, D. B., 1977, State-of-the-art for assessing
earthquake hazards in the United States; Part 6: Faults
and earthquake magnitude with Appendix on geomorphic
features of active fault zones: u. s. Army Engineering
Waterways Experiment Station, Vicksburg, Contract No.
DACW 39-C-0009, 120 p.
Slemmons, D. B., 1980, Letter toR. E. Jackson, Nuclear
Regulatory Commission, dated 5 November 1980 and errata,
dated 4 December 1980, in San Onofre Nuclear Generating
Stations Units 2 and 3, Safety Evaluation Report,
NUREG-0712, Appendix E, p. El-E28.
5-100
~~
[
f .
L
l
L
l
rl
I
! 1-.
r L;
L
L
L
Sykes, L. R., 1971, Aftershock zones of great earth-
quakes, seismicity gaps, and earthquake prediction for
Alaska and the Aleutians: Journal of Geophysical
Research, v. 76, p. 8021-8041.
Tarr, R. s., and Martin, L., 1912, The earthquakes at
Yakutat Bay, Alaska in September 1899: U. s. Geological
Survey Professional Paper ·69, 135 p.
TenBrink, N. w., and Ritter, D. F., 1980, Glacial
chronology of the north-central Alaska Range and
implications for discovery of early man sites:
Geological Society of America, Abstracts with Programs,
1980, p. 534.
TenBrink, N. w., and Waythomas, c. F., in preparation,
Late Wisconsin glacial chronology of the north-central
Alaska Range - a regional synthesis and its implications
for early man settlements.
Thatcher, w., and Plafker, G., 1977, 1899 Yakutat Bay,
Alaska Earthquakes: Seismograms and Crustal Deformation
(Abs.): Geological Society of America Abstracts with
Programs, v. 9, p~ 515.
Trainer, F. w., and Waller, R. M., 1965, Subsurface
stratigraphy of glacial drift at Anchorage, Alaska: U. s.
Geological survey Professional Paper 525-D, p. Dl67-Dl74.
u. s. Geological survey, 1980, Volcano Log: Mount St.
Helens, 1980, Spall, H., (ed.), in Earthquake Information
Bulletin: u. s. Geological Survey, July-August 1980, v.
12, no. 4, p. 142-149.
5-101
Williams, J. R., and Ferrinas, 0. J., 1961, Late
Wisconsin and recent history of the Matanuska Glacier,
Alaska: Arctic, v. 14, no. 1, p. 83-90.
Woodward-Clyde Consultants, 1978, Offshore Alaska seis~ic
exposure study: Prepared for Alaska Subarctic Operators'
Committee (ASOC), March, 1978, v. 1 through 5.
Woodward-Clyde Consultants, 1979, Reconnaissance Geology,
Bradley Lake Hydroelectric Project: Contract No. DACW
85-79-C-0045, Department of the Army, Alaska District,
Corps of Engineers, 65 p.
Woodward-Clyde Consultants, 1980a, Seismicity Study
Bradley Lake Hydroelectric Project: Contract No. DACW
85-79-C-0045 Modification PODOl, Department of the Army,
Alaska District, Corps of Engineers, 35 p.
Woodward-Clyde Consultants, 1980b, Interim Report on
Seismic studies for susitna Hydroelectric Project for
Acres American Incorporated: Alaska Power Authority,
Susitna Hydroelectric Project, Subtask 4.01 through 4.08.
Woodward-Clyde Consultants, 1981, Draft Report Bradley
Lake Hydroelectric Project Design Earthquake Study:
Contract No. DACW 85-79-C-0045 Modification 0005,
Department of the Army, Alaska District, Corps of
Engineers, 53 p. ·
5-102
(
I
I
i
f .
l
I
L
L
L
r
' .
L
f
!
l
( .
1 .
L
L
D
ENVIRONMENTAl
STUDIES
r
l .
6.0
r-
I .
l
6.1
6.1.1
ENVIRONMENTAL STUDIES -SUMMARY
Environmental studies were conducted within the
Chakachatna and McArthur River drainages during both
1981 and 1982. The 1981 studies included investigations
of the hydrology, aquatic and terrestrial biology and
human resources of the area. These studies were limited
in scope due to the short-time frame which was available
for conducting field investigations. Studies conducted
in 1982 emphasized aquatic biological investi~ations
(seasonal sampling) , but also included supplemental
hydrological studies. The following section presents
summary information for each of the 1981-19B2 studies.
The complete detailed reports for the environmental
studies are presented in the APPENDIX to Section 6.0 in
Volume II of this report.
Environmental Studies -1981
In 1981, two environmental reconnaissance level surveys
were conducted in the project area. The first was
conducted in August to document the presence of sockeye
salmon (Oncorhynchus nerka) in the project waters, and
to survey the site in preparation for the fall field
reconnaissance. The second investigation, conducted in
mid-September, involved two weeks of field data
collection. Coincident with these studies were ongoing
reviews of the literature and discussions with key
agency and native corporation personnel.
Environmental Hydrology
Hydrology field studies were conducted for Chakachamna
Lake, several of its tributary streams, and the
6-1
Chakachatna and McArthur Rivers. The hydrologic field
data collected included measurements of discharge taken
at eight study locations, a water level survey of
Chakachatna Lake, a wetland/river level survey taken in
a channel of the Noaukta Slough, and a characterization
of channel pattern and configuration including the
composition of bed and bank materials.
Office evaluations were also conducted to synthesize
hydrologic data at eight study locations. Data that
were developed included mean monthly flows, mean annual
flows, flood flow frequency, and low flow frequency. In
addition, using the Montana Method, preliminary instream
flow recommendations for maintaining fisheries habitat
were calculated on a monthly basis for the outlet of
Chakachamna Lake.
The field data collected from the various streams were
typical of glacial rivers, with low flows in late
winter, large glacier melt flows in July and August, and
annual peaks due to fall rains. The reaches of the
McArthur and Chakachatna Rivers vary from mountainous
through braided and meandering streams. All except the
most infrequent large floods are contained within the
unvegetated flood plan. Sedimentation characteristics
in the streams appear to be typical of glacial systems
with very fine suspended sediments and substantial bed
load transport. The water level of Chakachamna Lake
(measured in September) was 1,142 feet which was typical
for the lake in September based on 12 years of past
records.
6-2
r-
r
i_
J
1
(
f
L
f \L
L
L
6.1.2 Aquatic Biology
Two reconnaissance level surveys were conducted in
Chakachamna Lake, and in the Chakachatna,.Chilligan and
McArthur Rivers and tributaries. The first reconnais-
sance occurred during 17-18 August and consisted of
aerial observations of the ~roject area.
The second reconnaissance, conducted 15-28 September,
involved the collection of data from areas identified
during the initial survey. This effort employed both
field sampling and visual observations. The major
objectives of this reconnaissance were to identify the
fish species and life stages during the fall, to
identify potential critical fisheries habitats in the
system, and to provide information on the species
composition of fish and their habitat use occurring at
different times of the year.
A total of 14 species of fish were collected from the
waters of the project area including all five species of
Pacific salmon found in Alaska (Table 6.1). Some of the
streams flowing into Chakachamna Lake contained large
areas used by sockeye salmon for spawning. Substantial
numbers of sockeye were found in the Igitna and
Chilligan Rivers, and there was some evidence of
potential sockeye spawning in Chakachamna Lake.
Juvenile sockeye salmon used Chakachamna and Kenibuna
Lakes as nursery habitat. Lake trout (Salvelinus
namaycush) , Dolly Varden (Salvelinus malma) , round
whitefish (Prosopium cylindraceum) and slimy sculpin
(Cottus cognatus) were also found in Chakachamna Lake.
Side channels and tributaries of the Chakachatna and
McArthur Rivers contained salmonid spawning sites and
6-3
Table 6.1 Species list and drainage of occurrence August-September 1981.
Species
pygmy whitefish
round whitefish
Dolly Varden
lake trout
rainbow trout
pink salmon
chum salmon
coho salmon
sockeye salmon
chinook salmon
arctic grayling
slimy sculpin
threespine stickleback
ninespine stickleback
Prosopium coulteri
Prosopium cylindraceum
Salvelinus malma
Salvelinus namaycush
Salmo gairdneri
Oncorhynchus gorbuscha
Oncorhynchus keta
Oncorhynchus kisutch
Oncorhynchus nerka
Oncorhynchus tshawytscha
Thymallus arcticus
Cottus cognatus ·
Gasterosteus aculeatus
Pungitius pungitius
1 Includes Lake Chakachamna and Middle River
,-........-. --
Drainage of
Chakachatna
Riverl
+
+
+
+
+
+
+
+
+
+
+
+
+
+
Occurrence
McArthur
River
+
+
+
+
+
+
+
+
+
+
+
+
f
I
r
L
c
8
L
b
t
f
l
(
L
(
L
numerous fish were observed using them. These habitats
were also used as juvenile rearing areas. The Noaukta
Slough, a heavily braided reach of the Chakachatna
River, was used extensively as a nursery area by
juvenile fishes, particularly coho (Oncorhynchus
kisutch) and sockeye salmon. Juvenile pygmy whitefish
(Prosopium coulteri) and Dolly Varden were also abundant
in the slough. The intertidal ranges of both river
systems do not contain suitable habitat for salmonid
spawning or juvenile rearing.
Lake trout appeared to occur only in Chakachamna Lake,
while Dolly Varden were ubiquitous throughout both the
Chakachatna River and McArthur drainages. Rainbow trout
(Salmo gairdneri) were collected only in the lower
portions of the drainages. Round and pygmy whitefish
were found in most areas of the drainages, although
pygmy whitefish were not found in Chakachamna Lake or
drainages abo~e it. Slimy sculpin were found throughout
both systems and in tributary streams. Sticklebacks,
however, were only found in backwater areas and among
vegetation, usually in the lower reaches of the rivers.
Only a single grayling (Thymallus arcticus) was observed
in a side channel in the upper Nagishlamina River, and
none were collected or observed at any other location~
It was clear that most of the species found inhabit both
drainages.
In general,
two primary
sport fish.
the fish in this area may be classified into
groups, forage fish, and commercial and
Forage fish in the project area include
threespine stickleback (Gasterosteus aculeatus),
ninespine stickleback (Pungitius pungitius), slimy
sculpin, pygmy whitefish, and round whitefish.
6-5
6.1.3
Although the round whitefish is probably not used as a
subsistence species in these drainages, it is eaten by
lake trout and other species of fish. Sport and commer-
cial fishes include pink (Oncorhynchus gorbuscha) , chum
(Oncorhynchus keta), sockeye, coho and chinook salmon
(Oncorhynchus tshawytscha) , and Dolly Varden, lake
trout, rainbow trout, and grayling.
Terrestrial Vegetation and Wildlife
The objective of the terrestrial component for the
environmental study was to characterize the vegetative
and wildlife communities within the project area.
Because this project would affect the lands and waters
of both the Chakachatna and McArthur drainage systems,
qualitative data were collected throughout the study
area and vegetation and wildlife habitat maps were
prepared so that areas of a sensitive or critical nature
could be identified.
Previous investigations conducted in the general area by
the Alaskan Department of Fish and Game (ADF&G) and the
U.S. Fish and Wildlife Service (USFWS) have concentrated
on documenting waterfowl utilization of the coastal
marshes of Cook Inlet. In addition to annual aerial
surveys of the Trading Bay State Game Refuge performed
by the personnel of ADF&G, personnel of USFWS have
conducted aerial swan surveys encompassing the lands in
and adjacent to the refuge. Although the main purpose
of these surveys has been to census waterfowl,
information has also been gathered on bald eagle nest
sites, moose calving grounds, and the occurrence of
Beluga whales near the McArthur River.
6-6
J-
r
f
/
1
(
L
l
f t
r
r
{
J
L
-l ~: -· -
Table 6.2 The species composition and relative abundance of mammals identified within
the study area for each of the habitat types. (!=Abundant J=Common 5=0ccasional)
grizzly bea.r
black bear
gray wolf
coyote
moose
barren ground caribou
wolverine
mink
river otter
beaver
muskrat
red squirrel
tundra redback vole
tundra vole
porcupine
dusky shrewb
harbor seal b
beluga whale
Species
Ursus horribilis
Ursus amer1canus
Canis lupus
Can1s latrans
Alces alces
Rangifer arcticus
Gulo luscus
MU'Stela vison
Lutra canadensis
Castor canadens1s
Ondatra z1bethica
Tamiasciurus hudsonicus
Clethrionomys rutilus
Microtis oeconomus
Ereth1zon dorsatum
Sorex obscurus
Phoca v1tul1na
Delphinapterus leucas
a Upland Alder Thicket (UAT) ;
High Altitude Riparian CHAR);
Black Cottonwood Riparian (BCR);
Coastal Marsh Riparian (CMR);
Black Spruce Transitional (BST);
Resin Birch Bog (RBB);
Willow Thicket Riparian (STR); and
Black Spruce Riparian (BSR).
Habitata
UAT HAR BCR CMR BST RBB WTR BSR
3
1
5
3
5
5
5
5
1
3
1
1
3
3
1
5
5
5
5
5
3
3
3
3
3
5
3
1
5
3
5
3
3
5
3
3
3
3
3
3
5
1
3
5
3
5
5
5
5
5
5
3
3
5
3
5
3
3
3
3
3
3
5
3
3
5
5
5
3
3
3
3
3
3
.5
3
5
3
3
5
b sighted offshore near the mouth of the McArthur River.
6.1.4
During the 1981 studies, eight types of vegetation
habitats were delineated based on their structural and
species composition. These ranged from dense alder
thickets in the canyons to vast areas of coastal marsh.
The riparian communities were the most prevalent,
varying from rivers with emergent vegetation to those
with broad floodplains scattered with lichen, willow and
alder.
Evaluation of wildlife communities in the project area
identified sixteen species of mammals (Table 6.2).
Moose, coyote, grizzly bear and black bear occur
throughout the area. Birds also were abundant,
fifty-six species having been identified, with the
coastal marshes along Trading Bay containing the largest
diversity.
None of the species of plants, mammals and birds that
were found are listed as threatened or endangered,
although in May 1981 it was proposed that the tule
white-fronted goose, which nests immediately south of
the study area, be considered for threatened or
endangered status.
Human Resources
These studies were organized into the following six
elements:
Archaeological and historical resources
Land ownership and use
Recreational resources
Socioeconomic characteristics
Transportation
Visual resources
6-8
r
{
[_
!
(
I:
I
L
I
~ L
t
Contacts with both state and federal agencies and Native
organizations, and a limited reconnaissance of the
project area were made during the 1981 studies. No
known cultural sites were identified and the field
reconnaissance indicated that the proposed sites for the
power intake and powerhouses have a low potential for
cultural sites.
Land owners in the area comprise federal, state, and
borough agencies, Native Corporations and private
arties. Land use is related to resource extraction
(timber, oil and gas), subsistence, and the rural
residential Village of Tyonek. Recreational activity
occurs but little data is available to the extent or
frequency with which the area is used.
Regional data on population, employment and income
characteristics are relatively good. However,
employment level and occupational skill data are
limitedand need to be developed together with
information on local employment preferences.
Transportation facilities in the area are few and small
in size. There is an airstrip on the shoreline at
Trading Bay and a woodchip loading pier near Tyonek.
Several miles of logging roads exist between Tyonek and
the mouth of the Chakachatna Valley. The Chakachatna
River is bridged near its confluence with Straight
Creek. There is no permanent road between the project
area and any part of the Alaska road system.
Because of the project area's scenic characteristics and
its proximity with BLM lands, the Lake Clark National
6-9
6.2
6.2.1
Park and the Trading Bay State Game Refuge, visual
resource management is a significant concern.
Environmental Studies -1982
The 1982 environmental studies included both
hydrological and aquatic biological investigations with
primary emphasis on the latter. The.hydrologic studies
were conducted during the fall of 1982 (August and
October); aquatic biological studies were conducted
seasonally, with the major sampling effort occurring
during the summer and fall periods.
Environmental Hydrology
The objective of the 1982 environmental hydrology
studies was to collect baseline data to assist in future
evaluations of the physical process of the Chakachatna
and McArthur River systems, and facilitate the
correlation of these processes with fish and wildlife
habitats.
During August, two recording gages capable of recording
river stage and water temperature were installed, one on
the Chakachatna River near the lake outlet, the other on
the McArthur River downstream of the powerhouse
location. Staff gages were installed at an additional
15 sites and were periodically monitored. In October,
discharge measurements and water surface profiles were
made at 12 gage stations, and a generalized sediment
characterization made for the various stream reaches.
Manning's equation was used in the hydraulic analyses to
establish preliminary rating curves.
6-10
J
(
l
I.
!'
r·.·.
r
\ .. '
~-
L
1 , -
L
L
L'
,, l , I
f'
I ~
(
"
l
1 \
t
L
( .7
L\
F
[
~
L
L
L
{
f
L
[~
6.2.2
Overall, the discharges at gauge site No. 6 in the lower
Chakachatna River, downstream of the fork which
discharges into the Noaukta slough but above the split
with the Middle River, correlated reasonably well with
the discharges at the Chakachatna River recording gage
at the lake outlet. The flows averaged about 17 percent
of the flow at the lake outlet. The average discharge
at the lake outlet during the study period was
significantly less than the average for the 13 years of
U.S.G.S. records, with August flows well below average.
A September rainstorm resulted in a short duration flood
flow in the upper McArthur River with a peak flow of
about 4500 cfs. This discharge is estimated to have _a
recurrence interval of about 25 years.
Mean daily water temperatures in the Chakachatna River
at the lake outlet ranged from 8°C in August to 6°C
in October. Water temperatures in the McArthur River at
the rapids exhibited large diurnal variations in August;
temperatures varied from 3.0°C to 9.5°C in a
six-hour period. Temperatures in the McArthur River
from mid-August to mid-September averaged 1.6°C less
at the powerhouse than at the recording gage.
The Chakachatna and McArthur River systems are glacial
and thus carry fine glacial silts through much of
theopen water season. The main channel substrate of
these river systems appears to be quite unstable.
Aquatic Biology
The 1982 aquatic biology studies concentrated on the
fishery resources of the study area. Two series of
programs were conducted, one during the winter and
6-11
spring, the other during the summer and fall. The
winter-spring studies were designed to extend the data
base on seasonal habitat use and distribution of fish,
to identify the time spring spawning migration begins,
and to examine for the presence of outrnigrants. The
summer-fall studies were directed at investigating both
the adult anadrornous fish, and the resident and juvenile
anadrornous fish in the study areas. A separate pro9rarn
for sampling the fisheries in Chakacharnna Lake was also
conducted during the summer-fall studies.
A variety of methodologies were utilized to sample and
count fish in the study area during the 1982 program.
Selected sampling techniques included the use of fyke
nets, minnow traps, seines, hook and line,
electrofishing, and gill netting. Hydroacoustic
sampling was used to examine the relative distribution
of fish in Chakacharnna Lake.
A total of 18 fish species were identified and/or
collected during the 1982 studies, including four
species not collected in 1981: Bering cisco (Coregonus
laurettae) , longfin smelt (Spirinchus thaleichthys),
rainbow smelt (Osrnerus rnordax and eulachon (Thaleichthys
pacificus). The species of commercial, subsistence and
sport interest utilizing the Chakachatna and McArthur
River systems included sockeye, chinook, pink, churn and
coho salmon, Dolly Varden and rainbow trout. Summary
information for these seven species is presented below.
Detailed analyses o~ the 1982 studies are presented in
the APPENDIX to Section 6.0 in Volume 2 of this report.
6-12
r
r l"
r
!
r
f
J
{
1
J
L
t
l:
L
r--
1 '
[ '
~--
[
L
L
L
6.2.2.1 Sockeye Salmon
Sockeye salmon adults probably enter the Chakachatna and
the McArthur Rivers in early July. Sockeye first
appeared on the spawning streams on July 22, 1982.
Spawning continued through the first week of October in
various parts of the system and few spawning sockeye
were present past early October.
The timing and duration of sockeye-runs varied with
location. Runs in the McArthur River tributaries peaked
earlier than most of those on the Chakachatna River.
Spawning adults were present in the Chilligan River and
sloughs at station 17 longer than at other sites.
Sockeye escapements were estimated for all identified
spawning areas and are presented in Table 6.3. The
largest estimated escapement was for the Chilligan
River:. 38,576 sockeye. A total of 41,357 sockeye
(total of the Igitna and Chilligan River escapements)
were estimated to spawn above Lake Chakachamna. Of the
other sockeye estimated to spawn in the Chakachatna
drainage, 1788 spawned in sloughs or side channel
spawning areas receiving slough flow. In the McArthur
drainage, of the 34,933 fish, 98.1 percent of the
estimated sockeye espapement occurred in tributary
streams. Overall, 44.7 percent of the total estimated
escapement of sockeye occurred in the McArthur drainage.
Sockeye which are spawned in the Chilligan and Igitna
Rivers, rear in Chakachamna and Kenibuna Lakes. The
Chakachatna River across from Straight Creek, the
Noaukta Slough, and portions of the lower McArthur River
also appear to be used as rearing areas. Juvenile
6-13
~
I
1-'
~
Table 6. 3 Summary of estimated salmon escapement by waterbody and drainage for 1ga2.
CHAKACHATNA RIVER DRAINAGE
Chakachatna
Straight Bridge Chakachatna Chakachatna Straight Creek
Creek Side Channels Canyon Tributary lgitna Chi 11 igan Straight Clearwater Drainage
Species Mouth and Sloughs Sloughs (C1) River River Creek Tributary Total
Sockeye
Salmon 203 1,193 392 238 2,781 38,576 0 254 43.637
Chinook
Salmon 0 0 0 0 0 0 0 1,422 1,422
Pink
Salmon 0 59 . 279 0 0 0 0 7,925 8,263
Chum
Salmon 152 1,482 121 165 0 0 0 0 1,920
Coho
Salmon 76 1,560 608 183 0 0 0 172 2,599
-----------------------------------------------------------------------------------------------------------------------------------------------------
MCARTHUR RIVER DRAINAGE
Species McArthur Canyon Stream 13X Stream 13U 12.1 12.2
Sockeye
Salmon 666 5,416 1,213 16,711 6,085
Chinook
Salmon 0 452 1,633 0 22
Pink
Salmon 60 4,225 5,402 8,499 1,566
Chum
Salmon 1 0 23 4 0
Coho
Salmon 1,182 1,378 32 2,000 46
Note: Figure 6. 30 shows locations in Chakachahla Hi ver c.rainage.
Figures G. 30, 6. 47 and 6. 48 shmv locations in McArtlmr Hiver drainage.
-I
Streams Drainage
12.3 12.~ 12.5 Total
2,512 2,328 0 34,933
0 0 0 2,107
4 18 3 19.777
0 0 29
89 0 0 4,729
~,.,,:::::,_.._.._,
( -
~
\ I
(~
r:
t
t
[~
t
[ :
[_
sockeye appear to rear in the system from as short a
time as their first summer to as long as their third
year (age II+) prior to migrating to the sea.
6.2.2.2 Chinook Salmon
Based upon 1982 observations, chinook salmon adults were
entering the river systems prior to late June. Chinook
spawning was first observed in the study area on July 17
at Stream 13U in the McArthur system, but spawning could
have started as early as the end of June. Spawning
adults were observed as late as August 25.
The largest estimated escapement for chinook salmon
occurred in Stream 13U in the McArthur drainage (1633
fish) and the second largest in the clearwater tributary
to Straight Creek (1422 fish) (Table 6.3). All chinook
spawning observed during 1982 occurred in tributary
streams. The majority of spawning occurred within the
McArthur drainage.
Chinook salmon juveniles rear in fresh water from as
short as three months to well into their third year of
life. Juvenile chinook salmon collected in the study
area ranged in age from 0+ to II+. Chinook salmon
juvenile rearing areas consisted of spawning streams
(Streams 13U and 19) , low velocity side channel and
slough areas (stations 17, 15 and 13) and many areas
within the Noaukta Slough. Chinook outmigration may
start as early as June and appears to continue into the
fall.
6-15
r
Fish collected are listed by method and sampling location. Locations 1
of the sampling stations are as follows: I
Station r
Number Location Map ·coordinate r 1 Confluence of Chakachatna River
with McArthur River R. 14 w.' T. 10 N.
1D McArthur River R. 14 w •• T. 10 N.
2 Lower Chakachatna River R. 14 w.' T. 11 N. ' ' 3 Lower Chakachatna River R. 14 w •• T. 11 N. l J
4 Upper Middle River R. 14 w •.• T. 11 N.
5 Lower Middle River R. 13 w •• T. 11 N. [ 6 Chakachatna River above
Middle River R. 14 w .• T. 11 N.
6A Chakachatna River above ,.
Middle River R. 14 w.' T. 11 N. r
8 Upper Nouakta Slough R. 14 w.' T. 11 N.
.,
9 Lower Nouakta Slough R. 14 w .• T. 11 N.
10 West Nouakta Slough R. 15 w.' T. 11 N. r 11 Lower McArthur River R. 14 w.' T. 10 N.
12 McArthur River above
Noaukta Slough R. 15 w.' T. 11 N. L 13 Upper McArthur River R. 16 w.' T. 11 N.
14 Lower McArthur Canyon R. 16 w .• T. 12 N.
15 McArthur Canyon R. 17 w .• T. 12 N.
16 Upper Noaukta Slough R. 14 w.' T. 12 N. f' 16A Upper Noaukta Slough R. 14 w •• T. 11 N. \ .
17 Chakachatna River at DNR Bridge R. 14 w.' T. 12 N.
17D · Chakachatna River Below 17 R. 14 w.' T. 12 N. L 18 Straight Creek R. 15 w .• T. 12 N.
19 Clearwater tributary to
Straight Creek R. 14 w.' T. 12 N.
19A Clearwater tributary to [ Straight Creek R. 14 w .• T. 12 N.
20 Chakachatna River across
from Straight Creek R. 15 w .• T. 12 N. L 21 Chakachatna River across
from Straight Creek R. 15 w.' T. 12 N.
22 Chakachatna River at base L of canyon R. 15 w .• T. 13 N.
23 Chakachatna River in canyon R. 15 w.' T. 13 N.
24 Chakachatna River in canyon R. 16 w.' T. 13 N.
25 Chakachamna Lake R. 17 w.' T. 13 N. l 26 Nagishlamina River delta R. 18 w •• T. 13 N.
27 Chakachamna Lake N. Side R. 18 w •• T. 13 N.
28 Chakachamna Lake S. Side R. 18 w .• T. 13 N. ,
29 Kenibuna Lake outlet R. 20 w •• T. 13 N. '
30 Chilligan River R. 20 w.' T. 13 N. L
31 Neacola River R. 21 w •• T. 12 N.
32 Igitna River R. 21 w.' T. 12 N. l 33 Another River R. 21 w .• T. 13 N.
Streams 12.1 through 12.4, 13X R. 15 w.' T. 11 N.
Streams 12.1 through 12.4 R. 15 w.' T. 12 N. ~ .
Stream 12.5 R. 14 w.' T. 11 N. L Stream 13U R. 15 w.' T. 11 N.
Stream 13U R. 16 w .• T. 11 N.
L
6-16
0 2 3 4 5
mile$
D Recording Gauge Location
0 Staff Gauge Location B Sampling Station
0 Sampling Station Only
FrGURE
LOCATION AND IDENTIFICATION
. . OF 1982 SAMPLING STATIONS
....
16 _(· .. :
~·. 14 13 18
.. .• • ----~·· .. ---~:~t~· ...... ,..,._
--~!Ja·
~ ..:.·
L~ ....
[ -
r~ ~ ' -' ~
r·
L
r··
~ ~--;
[
~
8
t.
E 16
l ~ Figure 6.47
L~ ~ Milling Areas Sockeye Milling Areas·
MILES -N-Streams 13X. 12.1,
0 1/2 ~ 12.2, 12.3
1982
l_
r L._
I
~ Figure 6.48
8 Milling Areas
'. ~
MILES Sockeye Milling Area
0 1/2 !r~ at Stream 13u I~ 1982 ....
--
l.
l.
6.2.2.3 Pink Salmon
Pink salmon were first observed milling in ·fresh water
in late July (July 22) and first observed in the
spawning streams on July 31. Pinks continued to be
observed in the McArthur and Chakachatna River
tributaries until mid-September with peak counts made in
August.
In Cook Inlet, pink salmon runs in even numbered years
are generally larger than runs occurring during odd
numbered years. Since 1982 was an even year, larger
than average escapements were expected. However,
preliminary commercial catch data indicate that 1982 had
a lower than average run for an even-numbered year.
Estimated escapements for the various water bodies in
the system are shown in Table 6.3.
The vast majority of pink spawning occurred in tributary
streams. In the Chakachatna drainage, 4.1 percent of
the 8,263 estimated pink escapement for that drainage
occurred in sloughs and side channels, and in the
McArthur drainage less than 0.3 percent of the estimated
pink escapement occurred in sloughs or side channels.
The majority of the total estimated pink escapement,
70.5 percent or 19,777 fish, occurred in the McArthur
drainage. No pinks spawned above the sloughs at the
base of the Chakachatna River Canyon.
Emergent pink salmon fry probably move directly down
river to the sea. Rearing in fresh water may be for a
period as short as one day, and thus, no rearing areas
were identified during the 1981 and 1982 studies.
6-21
6.2.2.4 Chum Salmon
Chum salmon were in the spawning streams on August 25
and were found at most spawning areas by September 1.
The total estimated spawnings escapement for both the
Chakachatna and McArthur River drainages was 1949 fish,
which was less than any of the other four salmon species
(Table 6.3). The majority of these fish (77 percent -
1481 fish) spawned in the sloughs at station 17 on the
Chakachatna River. Over 90 percent of the estimated
escapement occurred in sloughs or areas receiving
upwelling flow
In early June, chum salmon fry had moved into lower
portions of the river sy~tems and smelts were found at
collecting stations near the mouth of the McArthur
River. By the end of June, only a few smelts were
collected near the mouth of the McArthur River,
suggesting that the peak downstream migration had
occurred. Because of the relatively short rearing
period of chum salmon in freshwater, no specific rearing
areas were identified during the 1981-1982 studies.
6.2.2.5 Coho Salmon
Coho salmon were first observed in fresh water in
mid-August. At that time fairly large numbers of coho
were observed milling at the mouths of streams on the
McArthur River. Coho were observed on spawning streams
on September 1 and peak numbers were observed in mid to
late September in most water bodies. Spawning was still
in progress when the study was concluded in late October
and may have continued under the ice in the Chakachatna
Canyon sloughs.
6-22
f
l
r
[
1 L
L
f
L
L
The majority (64.5 percent) of the estimated total coho
escapement for the study area occurred in the McArthur
River. In the McArthur system, 75 percent (3547 fish)
of the estimated escapement of 4729 coho occurred in
tributaries (Table 6.3) The other 25.0 percent took
place in side channel and slough areas. Spawning
occurred in both tributaries and sloughs. The majority
(86.3 percent) of the estimated escapement of 2599·coho
in the Chakachatna drainage were observed in sloughs and
side channels receiving upwelling or slough flow. No
coho were observed spawning above the Chakachatna C~nyon
sloughs.
Yolk-sac fry and emergent fry were found in spawning
areas in the study area in late March. Coho juveniles
may remain in fresh water for up to four years. Coho of
up to age II+ were common in the Chakachatna and
McArthur River systems. Juvenile coho salmon were among
the more widely distributed fish present in the study
area below the lake. Coho juveniles were generally
abundant in tributaries, the Noaukta Sough, and areas in
the lower portions of both rivers. Observed increases
in the abundance of coho in the Noaukta Slough, lower
river systems and upper McArthur River probably repre-
sented a combination of movement to overwintering
habitat and outmigration. The outmigration of some coho
was confirmed by the collection of smolts in the lower
portions of the rivers. Coho smolts were collected in
the Chakachatna and McArthur River systems from early
June into October.
6-23
6.2.2.6 Dolly Varden
Dolly Varden was the most widely distributed species
collected in the study area and was found at almost
every site at which fish were collected. They
numerically dominated collections·made below Chakachamna
Lake. Dolly Varden may be resident or anadromous; both
types are probably present within the study area. Dolly
Varden were obsereved spawning from July 31 through
October in the Chilligan River.
During late October, sexually mature upstream migrants
were still being collected in the lower portons of the
river systems, and Dolly Varden spawning was still
occurring. Dolly Varden spawning was also common in the
McArthur River and its tributaries during October. Some
upstream migrants which spawned in the McArthur River
were observed entering the river systems from the Middle
River and then moving through the Chakachatna River.
Dolly Varden juveniles were widely distributed in the
river systems. They were collected from every river
sampled, including the the Neacola and Another Rivers.
Juvenile (ages I+ to II+) appear to be common throughout
the river system with larger, older fish, including age
III+, more abundant in the Noaukta Slough and lower
portions of the river. Dolly Varden appear to move
freely within and between the two river systems.
6.2.2.7 Rainbow Trout
Rainbow trout were regularly collected in portions of
the lower river systems and tributaries. Rainbow trout
·6-24
(
f
L
r
r-
f
L
l
L
L
r
r
L
r'
r·
[ '
r
f '
[
[
L
[
[
~
L:
L
L
L
L.
were collected most frequently in October when large
numbers had moved into the lower river system.
Little is known about the spawning of rainbow trout in
the Chakackatna and McArthur River systems and few
rainbow trout under 10 em (4.0 inches) were collected.
The distribution of rainbow trout in the Chakachatna
River appears to be limited to areas below the
Chakachatna River Canyon. During the summer and fall of
1982, juvenile rainbow trout wer~ collected in the
Straight Creek clearwater tributary (19) , in the
McArthur River (Stations 13, and 11) and in the lower
Chakachatna River (Stations 3, 4, and 6). Rainbow trout
are a resident species and therefore rear in freshwater
throughout the year. Based upon tag return data,
rainbow trout appear to move freely within and between
the middle and lower portions of both river systems.
6-25
EVALUATION OF
ALTERNATIVES
t
L
b
t
L
L·
L
L·
[
7.0
7.1
7 .1.1
EVALUATION OF ALTERNATIVES
Engineering Evaluation
General
The figures quoted in this section of the report for the
estimated cost of energy are considered to be
conservative for two basic reasons, the first being that
in the power studies for Alternatives A, B, C and D, the
maximum lake level was taken as elevation 1128 which had
been reported as the approximate invert elevation of the
natural lake outlet channel. The natural maximum lake
water level is reported to have been at about elevation
1155 and the records show that the lake rose to that
level or within about 5-feet of it each year. No credit
has been taken in the calculations for any additional
energy that would accrue from the higher heads that would
temporarily be available when the lake water level
exceeded elevation 1128. There is also the possibility
that once diversion of water for power generation begins,
the outlet channel may choke and its invert may rise
above its present elevation thus creating a higher head
for power generation. If the maximum water level is
taken, as elevation 1142, the installed capacity for
Alternative B would increase from 330 MW to 350 MW and
the average annual energy would rise·by 6% from 1446 GWh
to 1533 GWh.
The second reason which applies to Alternatives A, B, C,
D and E, is because of the realistic approach taken to
estimating the cost of constructing each of the
alternatives. Analyses were made of bids received for
7.1.3
projects involving similar types of construction and the
unit prices used in the estimates are consistent with
those that have been received in recent competitive
bidding in cases where the analyses have permitted such
comparisons to be drawn. Furthermore, although the
estimates make allowances for certain lengths of the
tunnels where production may slip and costs may increase
due to adverse rock conditions, an overall 20%
contingency allowance over and above the estimated cost
of construction, engineering and construction management
has been included in arriving at the estimated total
project costs.
Chakachatna Dam
On the basis of what was seen in surface exposures during
reconnaisances of the Chakachatna Valley, little
encouragement could be found for pursuing a course based
on the concept of siting a dam anywhere in the valley
downstream from the lake outlet. Although the
possibility has not been completely ruled out, it is
considered most unlikely that justification for siting a
dam here could be confirmed.
Alternative A
This alternative, which would take all controlled water
from Chakachamna~Lake for the generation of electrical
power in a powerplant located in the McArthur Valley, is
the most advantageous identified by the present studies
when regarded strictly from the point of view of power
generation. As may be seen by reference to Table 7-1,
the powerplant would have the maximum installed capacity
(400 MW) , and would yield the maximum average annual firm
7-2
f
L
L
L
l
L
[
L
r
L
L
L
L
TABLE. 7-1
COST OF ENERGY
Alternative A B
Installed capacity-MW 400 330
Annual generation-GWh J. 7 52 1446
Deduct 5% for transmission
losses and station service-GWh 88 72
Firm annual energy-GWh 1664 1374
Capital cost including roc
at 3% -$Billions ( 1) 1.5 1.4 5
Annual cost 3.99% including
interest, amortization and
insurance for SO-year
project life -$Millions 59.9 57.9
Net cost of energy -Mills/kWh 36 42
O&M -Mills/kWh 1.5 LS
Total cost of energy -Mills/kWh 37.5 43.5
(1) Excluding Owner's costs and escalation.
7-3
c D E
300 300 330
1314 1314 1301
66 66 65
1248 1248 1236
1.6 1.65 1.32
63.8 65.8 52.7
51 53 43
1.5 1.5 1.5
52.5 54.5 44.5
7 .1.4
energy (1664 GWh) at the lowest unit cost (37.5 mills per
kWh). It is considered that these figures can safely be
regarded as conservative for the reasons set forth in
Section 7.1.1 above.
This alternative would provide neither instream flow
releases n-or fish passage facilities at the lake outlet
and should, therefore, be regarded as a hypothetical case
giving the theoretical maximum energy potential that
could be developed.
Alternative B
This alternative follows the same basic layout as that
for Alternative-A, but approximately 19% of the average
annual flow of water into Chakachamna Lake, during the
period of outflow gauge records, would be reserved for
release into the Chakachamna River near the lake outlet,
to satisfy the tentative minimum instream flow require-
ments discussed in Section 7.3.2 of this report. This
would cause the installed capacity to be reduced from
400 MW to 330 MW. The average annual firm energy would
reduce to 1374 GWh at a unit rate of 43.5 mills/kWh.
This is 16% higher in cost than for Alternative A but is
still significantly less than the 55.6 mills/kWh which is
the estimated cost of energy from the most competitive
thermal source, a coal fired plant, as discussed in
Section 9.4 of this report. Alternative B has the
advantage that instream flows ar~ provided in the
Chakachamna River for support of its fishery and based on
the tentative amount of water reserved for these instream
flow requirements, the project would still be an
economically viable source of energy.
7-5
7.1.5
Alternative B does not include a design concept for a
fish passage facility that would maintain a means of
entry into and exit from Chakachamna Lake for migrating
fish but an allowance for the cost of one was included in
the estimate. A concept was developed in the 1982 studies
and is discussed below in Section 7.1.6, Alternative E.
Alternatives C and D
Both of these alternatives would divert water from
Chakachamna Lake to a powerplant located near the
downstream end of the Chakachamna Valley. For
Alternative C, all controlled water would be used for
power generation. For Alternative D, water required to
meet the instream flow releases discussed in Section
7.3.3 of the report would not be available for power
generation. This water amounts to 30 cubic feet per
second average annually, which is less than 1% of the
total water supply. Being that small, it can be ignored
at the present level of study.
As may be seen from Table 7-1, the installed capacity for
both Alternatives C and D would be 300 MW. The average
annual firm energy would be 1314 GWh at 52.5 mills/kWh
for Alternative C and 54.5 mills/kWh for Alt~rnative D.
The installed capacity and energy that would be generated
by Alternatives C and D are significantly less than in
the case of both Alternatives A and B, and the cost of
energy is significantly higher. Alternatives C and D are
inferior in comparison with Alternatives A and B as
sources of hydro power. At 55.6 mills/kWh, energy from a
coal fired plant would be only marginally more expensive
than the energy that could be generated by implementing
Alternatives C or D.
7-6
r
f
[
L
f
l~
l .
I .
7 .1. 6 Alternative E
This alternative incorporates all the principal features
of the power facilities for Alternative B. In addition,
fhe normal maximum oprating water level in Chakachamna
Lake would be raised to El. 1155, which is reported as
the high lake water level under natural conditions, by
constructing an overflow rockfill dike in the natural
outlet channel. The dike will provide an artificial
barrier such as the natural barriers that have built up
in the past for various periods of time before they were
washed away during the passage of lake outbreak floods •.
The artificial barrier would be protected against
overtopping by an unlined spillway channel excavated in
rock on the right abutment. Material excavated to form
this channel would be used to construct the dike. The
discharge capacity of the channel would be in the order
of 50,000-60,000 cfs but future studies of flood
hydrology are needed to establish the appropriate
capacity. Flood discharges exceeding the designed
channel capacity would be discharged over and through the
rockfill dike.
Since the only foundation available for a dike at this
location is the glacial deposited rock and gravel which
undergoes small movements, intermittent maintenance will
be required. This could be performed each year, or as
required, during the spring while the lake level is drawn
down below the level of the dike foundation.
The normal operating range of lake level will be 72 feet,
from El. 1155 to El. 1083 •. This will support a capacity
of 330 MW at 50% load factor except for 1-month during
7-7
7.2
7.2.1
the 31 year extended hydrological record, or a true firm
capacity of 330 MW at 45% load factor throughout the
entire period. The average. annual firm energy will be
1301 GWh at a unit cost of 44.5 mills/kWh. Facilities
will be provided for the discharge of instream flow
releases to the Chakachatna River, and for the upstream
and downstream passage of fish into and out of the lake
over the full operating range of lake water level.
Geological Evaluation
Chakachatna Dam .
Although suitable dam sites might appear to exist in the
canyon like topography along the Chakachatna River about
six miles downstream from Chakachamna Lake, the geologic
characteristics of the canyon suggest that construction
of a major dam there is unlikely to prove feasible, and
if such construction is attempted, it is likely to be
very costly and a complex engineering problem for the
reasons discussed below.
As discussed in-Section 5.2.2, there is a marked
difference in the bedrock from one side of the
Chakachatna Canyon to the other. The south side of the
canyon consists of a steep ~all of glaciated granite,
which appears to be well suited for a dam abutment. In
contrast, the north wall of the canyon exposes a complex
of geologic units dominated by lava flows, pyroclastics,
and volcaniclastics, but including outwash and fill. If
the ideas presented in Section 5.2.2.2 are basically
correct, the volcanics may overlie alluvium below the
present valley floor; both the volcanics and the alluvium
7-8
r
L
l :
L
L
L
I
L
L
[
L
r
t
L
I L
L
L
L
7.2.2
rest on granitic bedrock at an unknown depth below the
valley floor. In addition to specific adverse foundation
conditions suggested by deposits found on the north
valley wall (e.g. high permeabilities, low strength), the
chaotic charact~r of those deposits would make the
prediction of foundation conditions at a given site-very
difficult.
Any impoundment in the Chakachatna Canyon will be subject
to the volcanic hazards associated with Mt. Spurr
(Section 5.2.2.2). The youthfulness of Mt. Spurr, as a
whole, and the fact that it has been active in historic
time suggest that continued eruptive activity should be
factored in as a design consideration for any facilities
in the Chakachatna Canyon.
Alternative A
On the basis of the observations made during the 1981
field program, it is possible to comment on several
geologic factors that may influence consideration of
Alternatives A, B and E,_ (see also Sections 5.2.1.6,
5.2.2.3, 5.2.3.4, and 5.2.3.3.).
(1) Although any lake tap site between the lake
outlet and First Point Glacier would be subject
to impact from a very large eruption of Mt.
Spurr, no site in that area is likely to be
disturbed by Crater Peak type events (Section
5.2.2.2).
(2) The bedrock characteristics pertinent to
tunnelling have not been specifically studied;
7-9
( 3)
this should be a subject of future study.
General observations in the Chakachatna Canyon,
aerial observations of snow-and-ice-free bed-
rock exposures between the Chakachatna and
McArthur canyons, and general observations in the
McArthur Canyon suggest that bedrock conditions
are likely to be well suited to tunnel
construction, with the exception of the lowermost
portion of the canyon, near the Castle Mountain
fault. The Castle Mountain fault, which has had
Holocene activity along at least part of its
length, is present near the mouth of the canyon
and has apparently disrupted the bedrock (shears,
intense jointing) in the lower reaches of the
canyon. For any project facilities constructed
in the fault zone, there would be a risk
as~ociated with fault rupture; large ground
motions would likely occur during an earthquake
on the fault. One of the design alternatives
presented in this report include facilities in
the fault zone, as it is now known. Additional
work is needed in future explorations of this
area.
Slope conditions above both the proposed lake tap
site and outlet portal site are generally similar
in that there is no evidence of large-scale slope
movements in the recent past and rockfall appears
to be the dominant slope process. Talus at the
base of the slope at the proposed outlet
portal/powerhouse site (Figures 3-1, 3-2)
suggests a significant amount of rockfall
activity in post-glacial time.
7-10
r .
l
L
[
L
L
L
L
7.2.3
7.2.4
(4) As discussed in Section 5.2.1.4, a significant
advance of Blockade Glacier could disrupt
drainage in and near the lower reaches of the
McArthur Canyon. There was no evidence
identified during the 1981 field work to suggest
that such an event is likely in the near future.
Alternative B
The comments in Section 7.2.2 apply to this alternative,
also.
Alternatives C and D
On th~ basis of the observations made during the 1981
field program, it is possible to comment on several
geologic factors that may influence consideration of
Design Alternative C (and D); see also Sections 5.2.1.6,
5.2.2.3, 5.2.3.4, and 5.3.3.3.
(1)
( 2)
In this alternative, both ends of the
hydroelectric system would be subject to the
volcanic hazards associated with Mt. Spurr.
Comment No. 1 for Alternative A (Section 7.2.2)
applies here, also. Volcanically-induced
flooding is judged to be the volcanic hazard most
likely to affect the outlet portal/powerhouse
site (Figure 3-3) in the Chakachatna canyon.
On the basis of general observations (i.e., not
observations specifically designed to assess
tunnelling conditions), the granitic rock types
that predominate in the area of the proposed
7-11
7.2.5
tunnel alignment (Figure 3-3) are generally well
suited for tunnelling. Local zones of intensive
weathering, alteration, or extensive jointing and
shearing may provide poor tunnelling conditions.
(3) The slopes above both the lake tap and outlet
portal sites consist of glaciated granitic
bedrock. No evidence of large-scale slope
failure was observed during the 1981
reconnaissance field work. Rockfall appears to
be the dominant slope process.
Alternative E
The comments regarding the power facilities in Section
7.2.2 apply equally to this alternative. The following
comments apply to the fac~lities proposed to be located
in the general vicinity of the lake outlet.
(1) The inlet portal for the structures required for
instream flow releases and fish passage
facilities will be located in glaciated granitic
bedrock. No evidence of large-scale slope
failure was observed in this area.
(2) The spillway channel will be excavated in the
same glaciated granitic bedrock.
(3) The approach channels to the fish passage
facilities and spillway will be excavated in
fluvial sediments deposited in a fan to the south
of the lake outlet.
7-12
f-
r -
\
I
I.
f '
l
I
! '
i t
r ,
I l ~
~~
r~
l
t
l ~
{\
' 1 't_;
~
L
/,-
~-~
~\
l
r \
I c
L
rl
L
L
7.3
( 4)
( 5)
(6)
Tunnelling conditions for the fish passage flumes
and instream flow releases will be as described
in Section 7.2.4 (2) for the power tunnel in
Alternatives C and D.
The outlet structure and lower part of the fish
passage flumes downstream from the tunnel portal
will be constructed as a· cut and cover structure
in outwash materials and alluvium.
The left abutment and river channel section of
the dike will be constructed on debris covered
glacial ice. The right abutment will be on
glaciated granitic rock.
Environmental Evaluation
The preliminary environmental overviews presented in the
following sections for each project alternative are based
on data obtained from agency personnel, available
literature, and the information collected during the 1981
and 1982 field programs. Although a complete evaluation
of all influences of each alternative is not included in
this section, the anticipated major effects of each
alternative are presented. These potential effects
should not be considered definitive, and are only
included at this time to facilitate comparisons of the
alternatives. The recommended Alternative E is discussed
in more detail and the effects on aquatic and terrestrial
biological resources are identified.
7-13
7.3.1
,-
Chakachatna Darn Alternative
If a darn was constructed and operated on the Chakachatna
River, it is likely that substantive adverse impacts
would be inflicted on fish of the Chakachatna drainage.
A fish passage facility, somewhat similar to that
described for Alternative E, would be necessary to
preserve stocks of anadrornous fish which spawn above
Chakacharnna Lake. If such passage was not provided the
41,000 sockeye which are estimated to spawn above the
lake (Section 6.8.3) and their contribution to the Cook
\
!
Inlet Fishery would be lost. The Dolly Varden population · l
which migrate to and spawn in tributaries above
Chakacharnna Lake would also be lost. If passage was (
maintained impacts to those populations could be similar
to Alternative E. 1'
Siting of the darn at the mouth of the canyon would result f
in the loss of slough spawning habitat for coho, pink,
sockeye, and churn salmon and Dolly Varden in that area
( Section 6 • 8 • 3) •
Due to the water quality alterations in the river down-
stream from the darn, the use of some fish migratory and
rearing habitat may be reduced. This, in turn, could
adversely impact Cook Inlet commercial fishery resources.
If a large decline in the lake fishery occurred, wolves,
bears, and eagles would probably migrate to lower
elevations, thus increasing the density of animals in the
remaining forage areas. Other large mammals that
ordinarily utilize the Chakachatna River canyon for
migration to and from summer and winter range would
7-14
'
r;
l
r
L
l~
r·
(
c
I
L
r \
L
f
c
~
b
7.3.2
probably also be impacted. Since the canyon area
upstream from the dam would be flooded, a high quality
visual resource will be affected by the loss of the
white-water reach of the river. In addition, fluctuating
Chakachamna Lake water levels associated with all
alternatives will impact the scenic quality of the lake
shoreline. If the lake levels are raised so that the
tributary deltas are inundated, additional juvenile
rearing and spawning areas may be created for resident
lake fish, (primarily lake trout) and anadromous fish if
passage past the dam is maintained.
Although fishing and hunting access to the lake by
wheeled airplanes would be reduced, access by float plane
will be unaffected.
Construction impacts due to this alternative would be
more extensive than other alternatives where less area
would be affected and where the need for such large
volumes of construction materials is not required.
Although the impacts from this alternative may be severe
in that a major fishery could be adversely affected or
lost, many of the impacts, including the damage to the
aquatic resources, potentially could be mitigated,
primarily through the installation of appropriate fish
passage structures.
McArthur Tunnel Alternatives A and B
Through the implementation of Alternatives A or B, the
impacts resulting from construction and logistical
support activitie~ would be very similar. In these
alternatives, although the major impacts most likely will
7-15
be inflicted on local fish and wildlife, human and visual
resources will also be affected. For example, with
increased access to the McArthur Canyon and Chakachamna
Lake, important visual resources as well as fisheries and
wildlife habitat may be degraded.
Once in operation, the increased flows in the McArthur
River may result in changes in water quality and
alterations in the chemical cues that direct anadromous
fish to their spawning grounds. This could cause
additional losses of spawning adults through or reduce
the productivity of spawning areas through crowding and
redd superimposition. Although the possibility also
exists that the population of salmon will increase in the
McArthur River, predation may also increase. If large
mammals begin to concentrate in these high density fish
areas, sport and subsistence hunting pressure .will
probably also increase.
The major difference in these McArthur tunnel alter-
natives is that in Alternative A, no water would be
provided in the upper reaches of the Chakachatna River,
while in Alternative B, some flow would be maintained.
Alternative A would likely result in a total loss of the
population of sockeye salmon which spawn upstream of
Chakachamna Lake. The estimated escapement of sockeye
upstream of the lake was 41,000 fish during 1982. This
would also cause the loss of their contribution
(presently unknown) to the Cook Inlet fishery. In
addition, because no maintenance flows would be provided
below the lake, the spawning, rearing and migration of
salmon and resident fish in the Chakachatna River
drainage would likely be significantly and adversely
affected. Estimated escapement of salmon ~elow the lake
7-16
r
\
f
' !
\
r
t
r
t ~
l
l
(
lJ
{
E
E
t
\i
L
L
is over 16,000 fish (Section 6.8.3) which could be lost.
In Alternative A there is a significant potential to
drastically reduce the populations of salmon which are
represented by the estimated escapement of over 57,000
salmon in the Chakachatna drainage.
Alternative A provides no fish passage to and from the
lake. The sockeye salmon and Dolly Varden which spawn
above the lake would not be able to ascend to the lake
unless the lake level exceeded the present channel invert
(El. 1128) by at least 1 ft at the lake outlet. Down-
stream migrants could not pass from the lake unless the
water was at this level or if they passed through an
outlet structure which would provide the mitigative
flow. The impact of this alternative without provision
for a fish passage structure could be substantial.
Alternative B would provide for year round flow releases
to the Chakachatna River (Table 7.2). The amounts of
instream flows selected are approximately 30 percent of
the average annual flow during May through September and
between approximately 10 percent of the average annual
flow during the winter months, October through March.
April flows are intermediate. These flow quantities are
very tentative and the final recommendations regarding
flows to be released to mitigate potential adverse
impacts will be based on further studies to be performed
in the future, and may be greater or less than the values
presented herein. The implementation of Alternative B
should inflict less adverse impact on the fish which
7-17
Table 7.2 Natural and Alternative B regulated mean monthly and mean
annual flow at the Chakachamna Lake outlet.
Month
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Mean
Annual
Flow
Mean Monthly Flows
Natural
(cfs)
613
505
445
441
1,042
5,875
11,950
12,000
6,042
2,468
813
1,206
3,645
Regulated a
( cfs)
365
343
345
536
1,094
1,094
1,094
1,094
1,094
365
365
360
679
a Regulated flows were estimated using the Montana Method as
described in Section 6.2.2.1
7-18
r-
,
r
I
' ',
l
!
(
'
l
f
(
\..
r
L
l
l
(.
\
r
l
l
r;
I
L
L
f
L
L
spawn and rear below the lake, than Alternative A. The
severity of adverse effects upstream of the lake would
depend on reservoir operation and the mitigative measures
taken. While no specific design concept was developed
for fish passage facilities that would permit fish to
pass into and out of the lake, an allowance was included
in the estimates for the cost of one. The influence on
the human resources will probably also be less severe
since the commercial fishery will probably not be as
heavily impacted, but the impact due to the loss of a
portion of the lake tributary spawning could be
substantial.
While the impacts related to Alternative A affecting
local resources would be difficult to mitigate and
significant changes in both the distribution and
abundance of fish and wildlife populations would almost
certainly occur, the impacts resulting from Alternative B
would be less severe primarily through the installation
of fish passage structures and maintenance of adequate
downstream discharge.
It should be noted, however, that while not directly
stated, the loss of spawning areas, and juvenile habitat
due to any of the project alternatives will most likely
eventually manifest itself as a decline in the population
of adult fish as well. In addition, since eggs, fry, and
juveniles of all species provide food (prey) for other
species, losses of spawning and nursery areas will almost
certainly result in eventual reductions in the standing
crop of their predators. For example, losses of juvenile
sockeye salmon in Chakachamna Lake would probably also
result in an overall decline in lake trout.
7-19
7.3.3
Potentially, one of the more substantial influences to
important floodplain riparian habitats and wildlife
distributions from the McArthur alternatives is the
disposal of large quantities of waste rock in the
McArthur valley. Without proper site selection,
stockpile design, and erosion control, this dispos~l
could significantly alter valuable riparian habitats,
detrimentally affect w-ildlife species that rely upon
these habitats. Moose, ptarmigan, small mammals, and
passerine birds would be most likely affected from
substantial floodplain habitat alterations.
Chakachatna Tunnel Alternatives C and D
and
Through the implementation of Alternatives C or D, the
impacts resulting from logistical support or construction
activities would be similar. However, since all
activities are restricted to the Chakachatna flood-plain
in these alternatives, the resources in the McArthur
drainage will not be affected. Although impacts on the
wildlife populations may occur, significant impacts will
occur to the fisheries. Since access to Chakachamna Lake
will be increased, sport and subsistence fishing pressure
may increase. With the road, campsite and disposal site
for rock excavated from the tunnel, all located in the
Chakachatna canyon, an important visual resource will be
modified. In addition the presence and activity
associated with these facilities may impede large mammal
movements through the canyon temporarily during
construction of the project. Depending upon facility
locations and activity levels, large mammal movement
patterns may also be affected during project operation.
7-20
I
\
1
(
\
~
!
(
\
l
{
'~
c
[
r
v,.
r
\
L__
'. --~ ~
~
6
\ '·
c
L.
[
L
During the pre-operational phases, the fishery in the
Chakachamna drainage will probably only be impacted to a
small extent over a relatively short term. Above the
powerhouse, the impact on the Chakachatna River and
Chakachamha Lake fishery will be dependent on whether
flows are maintained and fish passage facilities
provided. Alternative c· does not allow for these
mitigative measures. Therefore, the impacts to the
fishery in or above the lake, and thus the wildlife and
commercial fishery in the surrounding area will be
similar to that inflicted through Alternative A. Since
Alternative D does provide flows (Table 7.3) and
migratory passages, the impacts would be similar to those
described for Alternative B, but with substantially less
adverse impact below the powerhouse due to the higher
flows released by that facility.
Within the project area, some resources will be affected
no matter which alternative is chosen. This is parti-
cularly true of scioeconomic, land use, and transport-
ation characteristics. Through the implementation of
mitigative measures, it may be possible to offset many of
the adverse impacts. However, the mitigation technniques
outlined will probably not restore the environment to
pre-operational condition.
7-21
Table 7.3 Natural and Alternative D regulated mean monthly and mean
.annual flows at the Chakachamna Lake outlet.
Honth
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Mean
Annual ·
Flow
Mean Monthly Flows
Natural
(cfs)
613
505
445
441
1,042
5,875
11,950
12,000
6,042
2,468
1,206
1,206
3,645
Regulated a
(cfs)
30
30
39
30
30
30
30
30
30
30
30
30
30
a Regulated flows were assumed to be sufficient minimum flows to
maintain migratory passage as described in Section 6.2.2.1.
r
\
~ ..
r
r
(
(
C.
r
r
\_.
r
c
7.3.4
7.3.4.1
Lj
l\
f_r
Recommended McArthur Tunnel Alternative E
This section presents an identification of some
potential effects of . the recommended project
alternative, Alternative E. The identification of
effects is based upon data developed during the course
of studies carried out during 1981 and 1982. This
evaluation addresses the potential effects of project
construction and operation on the aquatic, wildlife
and botanical resources of the site area. Evaluations
of potential effects on aquatic habitats and aquatic
biota are based upon hydrological and fisheries
studies conducted during 1981 and 1982. Evaluations
of potential project effects on terrestrial biota are
based on 1981 reconnaissance data. The larger data
base available on the hydrology and fishery resources
of the study area allowed a more detailed examination
of potential effects on these resources.
Potential Effects on Aquatic Biota
Construction and operation of the proposed Chakachamna
Hydroelectric Project will result in changes to the
aquatic habitat and associated fishery resources in
the McArthur and Chakachatna Rivers, Lake Chakachamna,
and tributaries upstream of Lake Chakachamna, such as
the Chilligan and Igi tna Rivers. This section
examines potential effects of project Alternative E on
the aquatic biota.
In this section the term "impact" refers to both
direct and indirect effects on fish and aquatic biota,
including the utilization of aquatic habitats
resulting from project-induced changes in the physical
characteristics of the environment. Impacts on the
fishery can be either beneficial or adverse.
7-23
The description of anticipated effects presented below
is a generic identification of changes to fish habitat
and direct effects on the fishery likely to occur
during the construction and operation of thjs project.
It is based on available baseline information on the
biology of the fishery resources found in the McArthur
and Chakachatna systems, identification of potential
changes in physical characteristics, and the effect of
habitat alterations from similar activities as found
in the literature.
7.3.4.1.1 Construction of the Chakachamna Hydroelectric Project
and Related Facilities
The construction effects that could potentially result
in changes to the fishery resource fall into three
major areas of construction-related activity:
o Effects of permanent or temporary alterations to
water bodies (i.e., dewatering, alteration of flow
regime, or alteration of channels);
o Changes in water quality associat~d with
alterations to the water body, or with effluent
discharges and hazardous material spills; and
o Direct effects of the construction activities
(i.e., use of chemicals, noise, heavy equipment
operation, etc.).
Alteration of Water Bodies. Few alterations of water
bodies are expected during the construction phase of
the project. However, alterations may be associated
with the following construction activities:
7-24
r
J
r
\
{
J
\
(
I
r
(
r
L
r~
r l. I
( .
r • L.
o Installation of bridges or culverts for roads and
r·ights-of-way;
o Re-routing of runoff from camps and materials
storage areas; and
o Re-routing of flow in areas of near-stream or
in-stream construction.
Bridges and/or culverts will need to be installed to
prov~ae road access over streams and other waterways.
Properly designed bridges and culverts, installed so
as to prevent perching and high water velocities
should have few adverse impacts on waterways. During
construction or installation of the bridges/culverts,
some local increases in turbidity and localized
disturbance would be expected, but these should be of
relatively short duration. Potential impacts of
temporary increases in turbidity on aquatic biota are
discussed under water quality (below).
Alteration of waterbodies resulting from the
logistical support activities associated with the
Chakacharnna Hydroelectric Project will most likely be
small in areal extent although the specific extent and
potential for impact will be dependent upon the period
of construction and the mitigative measures used.
Re-routing of runoff from camps, materials storage
areas and construction sites is expected to affect
small areas, primarily in the McArthur River canyon.
The re-routing is expected to primarily involve
re-routing of surface run-off, where silt and soluble
materials would otherwise be carried into the
waterbody. Some re-routing of in-channel flows may be
necessary to allow construction activities in certain
7-25
site areas. Presently, there are insufficient data to
identify the extent of these areaso For example, in
the McArthur River canyon in-channel re-routing may be
necessary to allow the construction of the powerhouse
and tailrace, and disposal of tunneling spoils. Such
re-routing should only affect a small area in the
immediate area of construction. The resul tin_g impacts
could include a potential loss of some spawning and
rearing habitat and some degradation of downstream
habitats. The extent of this loss cannot be
determined at this time. The channel structure in
this immediate area does not appear to be very stable,
and therefore the significance of the loss is unclear.
The re-routing of flow in some construction and camp
areas may be permanent.
Changes In Water Quality. There are a variety of
water quality impacts that could potentially occur
during construction. These generally involve the
discharge of silt-laden waters from various areas and
effluents. Peters (1979) noted that under present
environmental legislation and by use of current
engineering practices, most impacts due to such
discharges can be mitigated, if not eliminated
altogether.
Silt-laden waters from collected run-off and from
excavation of facilities, could represent a
considerable source of silt and turbidity to the
river unless they are held in detention ponds before
being discharged. Spoils will be disposed of or
stored at the headwater area of the Chakachatna and
McArthur Rivers. Spoil at the upper McArthur River
canyon will result from tunneling and powerhouse
excavation. Much of this will be used for construc-
tion of river training works needed to protect the
7-26
l
; J t
~
t
~r t
(
~~
I
!
l
f L
L
r \_
(
\
1
r·,
l
{,
b ·,
t\
[:
f
\
[·
t /
l ..
L
powerhouse tailrace.channel from erosion and damage by
the river. The disposal area for excess spoil will be
located so as to avoid significant adverse effects.
Spoils in the Chakachatna drainage would include
materials removed from the spillway channel, gate
shaft excavation, fish passage facilities and tunnel
excavation. Some spoil will be used to construct the
outlet structure dike, while the excess will be
disposed of in location yet to be determined and
selected so as to minimize adverse environmental impact.
Disposal areas will be diked, and run-off controlled
to· minimize sediment discharge into waterways. Sett-
ling ponds will be used for sedimentation of suspended
silts prior to discharge to reduce potential impacts.
The prim~ry change in water quality that may occur
from construction is increased turbidity. This may be
produced by increased erosion associated with disposal
of tunnel spoils and construction activities. Tur-
bidity originating from run-off and construction is
often associated only with actual clearing activities
and rainfall events. The increases in turbidity in
the Chakachatna disposal area would occur near maximum
lake levels (El. 1140). Increases in turbidity would
vary with the ·type, extent and duration of construction
activity, but would be expected to be local in nature
and of relatively short duration.
Increased turbidity can reduce visibility and decrease
the ability of sight-feeding fish (e.g. salmonids)
to obtain food (Hynes, 1966 and Pentlow, 1949). In
addition, salmonids may avoid spawning in turbid
waters (Dehoney and Mancini, 1982), and many fish,
particularly older life-stages, may completely avoid
waters containing high turbidity. However, the
turbidity increases in mainstem areas of the
7-27
Chakachatna and McArthur Rivers would be expected to
have a lower potential for adverse effect on fish due
to the naturally high turbidity levels found in these
water bodies.
Siltation (sedimentation) is often associated with
construction activities. There is a considerable
amount of literature dealing with the effects of
siltation on aquatic biota (Burns, 1970; Shaw and
Maga, 1943; Ward and Stanford, 1979), particularly the
effect of siltation on salmonid spawning and
incubation. A general conclusion reached by a review
of the literature (Dehoney and Mancini, 1982) is that
siltation and turbidity impacts have their greatest
adverse effects on eggs and larval fish. In general,
siltation can cause a significant loss of incubating
eggs and pre-emergent fry in redds. This is generally
a result of interference with water and oxygen
exchange in redds. Upwelling flow in affected areas
may tend to reduce such impacts by reducing the amount
of sediment which settles into the redd.
Release of suspended materials can also affect other
water quality parameters including dissolved oxygen,
BOD, trace metals, and pH (Pierce et al., 1970).
The production of concrete for construction of the
fish passage facility and powerhouse may result in the
r~
\
r
,.
l
1
J
l-
,(
\ )
(
t-
l
l
production of concrete hatching waste. Peters (1979) (
points out that the discharge of this waste, if ~-
untreated, could lead to detrimental effects on fish
populations and habitat. A particular problem with
this waste is its high pH (10+) and the need to
neutralize it (pH 7) prior to discharge. It is
expected that this waste will be treated as required
by the anticipated project NPDES permit.
7-28
t
L
~ ..
t
L
(
\
('
\
During· peak construction activity, facilities to house
workers will be located primarily in the McArthur
floodplain. The housing and supply storage area will
occupy 20 to 30 acres. Due to the presence of a large
construction force in the area, sanitary waste will
need to be treated and discharged. The extent of
treatment of sanitary waste, its volume, and the point
of discharge will control the extent of potential
impact. Wastewater effluents can affect BOD, and
therefore the dissolved oxygen, pH, nutrients, trate
metals, and buffe-ring capacity of the receiving water.
Such effluents can thus affect the water quality of
the fish habitat (USEPA, 1976; AFS, 1979; Hynes,
1966).
Hazardous materials may also be used during
construction activities of the project. Although
hazardous material spills are generally of short
duration, they may have severe impacts depending upon
the substance spilled. A number of factors will
affect the severity of a spill on fish:
o The toxicity of the substance spilled,
o The duration and frequency of the spill,
o The quantity spilled,
o The fish species present,
o The fish life stages present,
o The season (time), in which the spill occurred, and
o Mitigation and clean-up provisions.
Any substance used around the site, or waste produced
on-site, could potentially be spilled directly into a
waterbody. In general liquids used in large
quantities and over greater areas, including fuels and
lubricating oils, would be more likely to be involved
7-29
in spills. Diesel oil, for example, will be used and
stored in large quanti ties on-site. In general,
spills will be most serious if they occur in areas of
high biological (e.g., spawning) activity and are not
dissipated quickly, or if a large area is affected.
As in the case of siltation and turbidity, the less
mobile life stages are most likely to be adversely
affected, since older juvenile and adult fish can
usually leave an affected area. Good engineering
practices, and a thorough spill control plan should
greatly reduce the potential for such impacts.
Direct Construction Activities. Direct construction
activities include activities that can be expected to
occur throughout the construction of the project.
These activities, for the most part, will be confined
to specific areas.
During construction, some of the first activities to
occur will include the construction of access roads,
clearing of construction areas, stockpiling of
construction materials and fuel, movement of heavy
equipment, and construction of support facilities.
Activities associated with support facility
construction will include cutting and clearing in
areas near several streams.
The removal of ground cover during this project will
be minor but may locally increase the potential for
greater run-off, erosion, increased turbidi~y and
increased dissolved solids (Likens et al., 1970,
Boreman et al., 1970 and Pierce et al., 1970). The
extent of impacts can be minimized through the use of
mitigative practices to control erosion and related
sedimentation and turbidity.
7-30
r
r
I
f
,~
\
l
r \
l
(
L
( l
('
l
I ~
l/
f'
-,
r
~
~~ ._,-
bi
[,
The removal of bank cover may locally increase the
exposure of fish to terrestrial predators and lead to
a decrease in their populations (Joyce et al, 1980).
There are no plans for regular operations of heavy
ma,chinery in streams. The primary use of heavy
machinery would be during the re-routing of flow. The
extent of potential impacts due to siltation and
turbidity should be short-term and dependent upon the
extent of machinery operation and the type of
substrate in the s_treams affected (Burns 1970).
Smaller substrates tend to be more affected (Burns,
1970). However, if water velocities are sufficiently
high, the deposition of suspended sediments may not
occur locally, and the effects could be minor (Shaw
and Maga, 1943).
Current construction plans do not require in-stream
blasting.
As part of the construction activities, water will be
diverted from the streams in the construction area to
be used for dust control, drinking water,
fire-fighting water, sanitary water, concrete
batching, and wet processing of gravel among other
uses. The diversions will probably be accomplished by
pumping from local stream segments and intakes will be
screened and designed to use very low velocities to
avoid fish impingement and entrainment.
Operation of the camps will also result in increased
access to an area that has previously experienced
relatively little fishing pressure. The areas
potentially affected would be those stretches of the
McArthur River and its tributaries that are easily
accessible by foot from the camp.
7-31
7.3.4.1.2 Operation of the Chakachamna Hydroelectric Project and
Related Facilities
Potential impacts of the operation of the project
(Alternative E) are expected to occur to the aquatic
biota through:
o Changes in aquatic habitat,
o Direct effects on aquatic biota, and
o Effects on fish passage into Chakachamna Lake.
Effects are expected to vary between waterbodies and
can be evaluated separately for the following:
o Chakachamna Lake and tributaries,
o Chakachatna River, and
o McArthur River.
Hydrological alterations are discussed first, and are
then followed by the effects of those alterations on
the aquatic biota.
Chakachamna Lake and Tributaries. Chakachamna Lake
will be affected by a 72 ft annual water level
fluctuation during proposed project operation. The
maximum proposed reservoir level of 1155 ft is near
the maximum historical lake level: this level will
occur seasonally under post-project conditions.
Ninimum reservoir levels will be approximately 45 ft
below pre-project minimum levels. Such a drawdown
will expose lake shoreline and stream deltas which are
normally inundated. Lake levels will vary in
Chakachamna Lake and will result in increased
inundation of lakeshore and delta areas during high
reservoir levels; dewatering of submerged shoreline
would occur during periods of drawdown.
7-32
I
L
t
r ~ .•
r
L
' \
r
L
r
\
r ~
I
1 t
The project effects on the water quality of Lake
Chakachamna may include increased suspended sediment
and turbidity concentrations near tributary mouths.
The potential sediment inflow from the tributaries is
discussed below.
The channel gradient of the Chakachamna Lake
tributaries will be affected by the drawdown and
fluctuation of the reservoir level. -Maximum water
levels will cause inundation of the lower reaches of
streams which are not normally affected; minimum water
levels will expose the entire stream delta surface and
the upper portion of the steep delta front. Resulting
changes in stream gradient will be progressive and
sequential. These will likely be similar at the
mouths of all tributaries, but to different degrees.
The anticipated changes due to seasonal minimum
reservoir levels include:
o Dewatering of over 7 mi 2 of delta area;
o · Increase in stream gradient and accompanying
erosion where the stream flows down the front of
deltas;
o Development of new deltas;
o Eventual channel degradation at the tributary
mouths to near the lowest regulated reservoir
level; and
o Degradation upst·ream as far as is required for the
stream to reach equilibrium between the streamflow
regime during low reservoir levels and the
materials through which it is flowing; possibly
7-33
resulting in localized rapids during the low water
period, if erosion resistant materials are reached.
Maximum reservoir levels can cause deposition of
stream-borne sediments in those reaches of stream
affected by backwater from the reservoir. Some of the
deposited sediments would likely be eroded as the
reservoir level drops through the winter.
flows may remove the rest of the deposits.
Break-up
According to the proposed reservoir operation
schedule·, the reservoir will be at maximum level
during September and drawn down to lower levels over
the winter with a minimum level occurring during April
or May.
Habitat Effects -The operation of the reservoir
should have effects on the fish rearing habitat within
the lake. During open water, juvenile sockeye, lake
trout, round whitefish and Dolly Varden are found
throughout the lake with many fish found offshore
along steep drop-offs and just under the ice in
winter •. It is unclear what the effect of changing
water levels may have on winter water temperatures or
habitat use, particularly near shore.
At high reservoir levels (during October and November)
lakeshore areas may be used as spawning habitat by
lake trout. After reservoir levels drop, incubating
eggs and fry may be exposed to freezing or
dessication. Relatively immobile invertebrates which
reproduce in shoreline areas may also be affected.
There are, presently, insufficient data to assess the
impact of such effects on lake trout populations and
standing crop of benthic invertebrates, although the
effects could be substantial.
7-34
r
r
!'
[
f
1
J .
l "
r
{
c
( ~
r l
r t.
r ,
t
f ~
'--_.
{'
L
l/
L
r .
[
L
Lake levels will be near minimum level at break-up, at
which time the principal movement of fish consists of
emergent fry moving from their tributary rearing areas
to the lake. It is not expected that the high
gradients to the lake will adversely affect these
migrants.
During the period in which sockeye salmon and Dolly
Varden spawn in tributaries above the lake, reservoir
levels will be greater than pre-project lake levels.
This will potentially result in lake water flooding
downstream areas of the Chilligan River and the
Kenibuna Lake/Shamrock Lake rapids. The effect of the
lake water on the utilization of the lower areas of
the Chilligan River is not presently known but there
is some evidence (which follows) that this may not be
an important effect. The area at the mouth of the
river contained a low density of spawning sockeye
compared to areas further upstream. It was used
extensively as a milling area. During September 1982,
lake water inundated the area without apparent impact
on either sockeye or Dolly Varden spawning. Adverse
effects would be expected if flooding of the lower
Chilligan River resulted in increased siltation which
could affect hatching success (see Water Quality,
above).
Direct Effects -The lake-tap (or multiple lake-taps)
will withdraw water at approximately El. 974. The
submergence depth would vary between 109 ft and
181 ft. Fish that are entrained into the lake tap
would be exposed to turbine passage at the powerhouse
and most would be expected to be killed by the
turbines, or during passage through the pressure
7-35
differential between the depth of the lake-tap and the
power plant. Juvenile sockeye and both juvenile and
adult lake trout, Dolly Varden, and round whitefish
may be vulnerable.
Hydroacoustic observations of fish distribution in the
lake have indicated that most fish were detected well
above the depth of the lake tap. During the winter,
over 99 percent of fish were detected in the upper
50 ft of the water column. During September, 1982
over 88 percent of the ~ish detected were in water at
least 60 ft above the proposed lake-tap (at that time
of year it would have been located at 181 ft) with no
fish detected below 161 ft. Thus, potential loss of
fish due to the lake tap based upon current data
would be relatively low. However, additional seasonal
information would be needed to quantify potential
losses.
Fish Passage -Chakachamna Lake -Alternative E
includes a fish passage facility which is designed to
permit upstream migrants to ascend from the
Chakachatna River to the lake and to allow downstream
migrants to pass from the lake to the Chakachatna
River. The fish passage facilities are described in
Section 3. 5. Detailed design of the fish passage
facility and its hydraulics has not been completed.
The upstream passage facility consists of a pool and
weir fishway constructed in an underground facility at
the lake outlet, and is connected to the Chakachatna
River downstream of the facility by a tunnel and
smaller fishway. Downstream migrants will be passed
through a wheel gate into a stilling basin and from
there into a tunnel which connects with the
Chakachatna River downstream. A grate at the
7-36
I
r
r
L
I
r·
(
f'
I ,
l
1
. '
f I L
L
( =
! 'L-
downstream end would prevent the entrance of upstream
migrants into this facility.
The facility is composed of components found in a
variety of existing fish passage facilities.
Presently, there are insufficient data available to
assess the potential effects of this facility on
migrating 'fish in a quantitative manner.
Sockeye salmon and Dolly Varden would be expected to
use this facility, as both have been observed to spawn
above the lake. Escapement estimates of sockeye
indicate that (based upon -1982 data), over 41,000
sockeye (possibly more depending upon yearly
variation) would need to successfully pass through the
facility to migrate upstream. Since the percentage of
the run successfully reaching the Chilligan and Igitna
Rivers is not known, the true extent of the sockeye
salmon re~ource can only be estimated. From 10 to
more than 100 times as many sockeye can be expected to
migrate downstream due to the normally higher
production of young fish (Foerster 1968). A smaller
number of downstream Dolly Varden would also be
expected to pass through the facility. If the
facility works as planned the impact to the sockeye
run should be low.
If the facility did not successfully allow the
migration of sockeye both upstream as adults and
downstream as juveniles then some part of the
estimated adult spawning population would be expected
to be lost, as well as a portion of its presently
unknown contribution to the Cook Inlet fishery. As
design details are determined, the fish passage
facilities will need to be re-assessed in a more
detailed fashion.
7-37
The release of water from Chakachamna Lake into the
McArthur system could potentially result in impacts to
fish which would normally spawn in Chakachamna Lake
and tributaries above it. While the "homing" of
salmon is not completely understood, the orientation
of upstream migrants to olfactory cues originating in
natal streams has been considered to be a principal
factor (Hasler, 1971). Fish entering the system
through the Middle River should not be affected by the
McArthur release. Fish entering the system through
the mouth of the McArthur River may· encounter
olfactory cues from flows entering the McArthur River
at the confluence of the lower Chakachatna with the
McArthur River, from the confluence of the Noaukta
Slough with the McArthur River, and from water
discharged from t~:te tailrace of the power plant
located in the McArthur canyon. Fish that entered the
Chakachatna River either at the lower river
confluence, or the Noaukta Slough would be following
what is hypothesized to be the present migratory
pathway and would not be expected to be significantly
affected by the other power plant discharge; some
delay due to confusion may occur. There is a
potential for some of the upstream migrants to be
attracted to the tailrace in the McArthur canyon.
Since the fish could.not migrate further upstream into
Chakachamna Lake, three basic scenarios could develop:
o The fish could back down the system until they
detect alternate olfactory cues (i.e., at the
Noaukta Slough) and then migrate up the Chakachatna
River,
o The fish could mill in the tail ,race until sexually
matured and then back down the system until
alternate cues were detected, or
7-38
r
l
[
r
L
L
[
'
l
(
r .\
L
(
'-
o The fish could spawn in the McArthur Canyon.
The significance of a delay in migration is not
presently known. However, the spawning of large
numbers of lake tributary origin sockeye in the
McArthur River canyon area could result in low egg
hatching success due to high densities of spawning
fish and resulting redd superimposition, the use of
poor spawning habitat, or females not spawning (Bell
1980). In addition, the rearing habitat in the
McArthur canyon is probably less suitable for sockeye
salmon than in Chakachamna Lake. Thus, if increased
spawning occurred in this area, rearing would probably
be less successful.
Chakachatna River. Water releases will be made to the
Chakachatna River below the fish passage facility.
The quantity of the actual releases is not presently
known, and will be based upon future studies.
However, preliminary release flows have been estimated
as a starting point for analysis {Table 7.4). Such
flows constitute a relatively small percentage of
pre-project annual flow. Tributary inflow downstream
from the lake contributes relatively small quantities
of flow compared with pre-project flows at the lake
outlet. However, depending upon the time of year, the
tributary inflow may substantially increase
post-project flows downstream of the release
structure. Historical low flows will be substantially
reduced by project operation during October through
March. Ten percent of the average annual flow is
considered to be the minimum for short-term survival
of fish and other aquatic organisms {Tennant, 1975).
However, in this system, post-project releases from
January through April may be less than 10 percent but
7-39
Table 7.4
Month
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Mean
Annual
Flow
Natural .and Alternative E regulated mean monthly
and mean annual flow at the Chakachamna Lake
outlete
Natural
(cfs)
613
505
445
441
1,042
5,875
11,950
12,000
6,042
2,468
1,206
813
3,645
a Regulated
(cfs)
365
357
358
582
1,094
1,094
1,094
1,094
1,094
365
365
363
6 85
aRegulated flows were estimated using the Montana Method as
described in Section 6.2e2.1.
7-40
I
\
\
\
t
~.
t
~ .
l
(
[
1
r·
L
(
\
l
(
L
L
L
still represent between 60 and 122 percent of
pre-project average monthly flows, respectively.
Flood flows would be modified in the regulated flow
regime. Chakachatna River flood flows would be
smaller in magnitude than past events, but would
exhibit a greater variation around a mean flood value
due to the relatively small influence of Chakacharnna
Lake on the post-project river system. The seasonal
distribution and hydrograph shape of the annual floods
may shift from the mid-summer, long duration floods
under the natural flow regime, toward a fall, short
duration flood more typical of basins without the
storage effects of lakes and glaciers.
The sedimentation characteristics of the Chakachatna
River system will change with the regulated flow
regime. Sediment transport will decrease in response
to decreased flows.
The configuration of certain stream reaches would
likely change as a result of the flow alteration
associated with the project. The mountainous reaches
on the Chakachatna River would retain a single channel
steep gradient condition, although it would be
carrying less flow. Split channel reaches would
likely assume more of a meandering configuration. The
braided reaches above Straight Creek and in Noaukta
Slough would likely become more stable and the flow
would be carried by fewer channels which are
characteristics of a split configuration. The lower
reaches of the.Chakachatna and Middle Rivers would
likely retain their meandering configuration.
Ice formation and breakup processes will also likely
be affected by. the project. The evaluation of the
7-41
nature and extent of these effects requires further
study.
Mainstem Habitats -The physical effects of the
proposed flow reductions are described above. The
mainstem habitats appear to be currently used as
migratory pathways, rearing areas for sub-adult and
resident fish, and there appears to be a small amount
of side channel spawning associated with areas of
upwelling or slough flow. Table 7.5 lists estimated
escapements of fish species for water bodies in the
Chakachatna River drainage, classified as to whether
the waterbody is likely to be affected by the reduced
mainstem flow. The tributary water bodies are not
expected to be significantly affected by reduced
flows.
Side channels in the Straight Creek mouth area and at
station 17 are expected to be most affected.
Observations during 1982 have indicated that these
areas will probably not be dewatered or perched. The
observations have indicated that turbid mainstem
overflow, which is present in these areas during
higher flows, would be absent. Without the co~er
provided by this. turbid flow, fish spawning in these
areas may be more vulnerable to predation. Side
channel spawning in both areas represents less than
50 percent of observed spawning at each site. Depth
of water at entry points to side channels at
station 17 would be expected to be shallow and may
adversely affect fish entry.
Based upon 1982 observations, the milling areas at
Tributary C1 and at the mouth of the Chakachatna
Canyon Sloughs would be significantly less turbid than
at present. This may also increase potential
7-42
[
r
··i.-
r
L
f L
L
L
--{ ·rT· ,...,._....-,
' '
Table 7.5. Estimated escapement of important fish species in th~ Chakachatna River system by waterbody classified by
potential effects of decreased flow of water from Chakachamna Lake.
Species
1 Sockeye
Salmon
Chinook 2
Salmon
Pink 3
Salmon
Chum 4
Salmon
Coho 5
Salmon
Dolly 6
Varden
1 Fig. 6.132
2 Fig. 6.134
3Fig. 6.136
4 Fig. 6.137
5Fig. 6.138
6 Fig. 6.141
X = Used as
POTF:NTIAI.I.Y AFFECTED WATERBODIES
More Affected Less Affected
Chakachatna
Straight Bridge Chakachatna Chakachatna
Creek Side Channels Canyon Tributary
~Iouth and Sloughs Sloughs ICll
203 1,193 392 238
0 0 0 0
0 59 279 0
152 1,482 121 165
76 1,560 608 183
X X X
and Sections 6.8.3, 6.8.6.1-.5
and Sections 6.8.3, 6.8.6.1-.5
and Sections 6.8.], 6.8.6.1-.5
and Sections 6.8.3, 6.8.6.1-.5
and Sections 6. 8.], 6.R.6.1-.5
and Section 6.8.6.6
f;pawning areas.
POTENTIALLY NON-AFFECTtD ~·IATERBODIES
Straight Creek
Igitna Chilligan Straight Clearwater
River River Creek Tributary
2,781 38,576 0 254
0 0 0 1,422
0 0 ·o 7,925
0 0 0 0
0 0 0 172
X X X
vulnerability to increased predation. The extent of
the potential increase in vulnerability to predation
of spawning adults at these sites will need to be
assessed after more data are collected.
There are a number of fish species which use mainstem
and side channel areas as rearing habitat. The effect
of decreased flow on the availability and suitability
of this habitat can not be determined at this time.
While decreased flow will decrease the wetted
perimeter and therefore the area of a stream, the
decrease is not linearly proportional to the decrease
in flow (Tennant, 1975). Additional sources of
inflow, including sloughs and tributaries such as
Straight Creek, should result in somewhat increased
flow downstream of the outlet structure. The .
additional water sources (Straight Creek, various
sloughs, and unnamed tributaries) will reduce effects
of the decrease in upstream releases. In areas where
pre-project water velocities ~re too great to contain
suitable rearing habitat, decreased velocities could
potentially increase suitable habitat. Presently,
there are insufficient data to evaluate all expected
change.
Decreased flows during winter may cause changes in the
ice conditions and also result in decreased
overwintering habitat. The actual nature and extent
of effects cannot be determined from available data
but a significant decrease in mainstem overwintering
habitat is likely during the early winter.
Sloughs -Observations made during March and October
1982 have indicated that flow in sloughs located in
the Chakachatna River canyon and at station 17 appear
to be independent of river flow. It is not expected
7-44
r·
I '
f
(
c
[
L
c
r
L
L
I -
(
that reduced flow in the river will have an adverse
effect on these waterbodies. This will need to be
confirmed through more detailed study. The
overwintering habitat in sloughs should not be
affected by reduced flow in the mainstem of the river.
Downstream migrants originating in the Chakachatna
drainage may require high seasonal break-up flows to
trigger their migration; proposed post-project
discharges may not be sufficient to trigger this
behavior. However, post-project releases during April
and May are greater than pre-project flows and
depending upon the timing of outmigration may be
sufficient to trigger the downstream movement. Data
collected during 1982 suggest that outmigration of
chum salmon and some sockeye occurs during late May
and early June. Collections made during the summer
and fall and in the Susitna drainage suggest
downstream migration and smoltification of coho,
chinook and sockeye salmon continues throughout the
summer and fall.
Some data in the literature indicates that swimming
activity, downstream migration, and smoltification of
some species may also be controlled by photoperiod
(Lorz, 1973; Godin, 1980). If the outmigration is
photoperiod controlled, high break-up flows would not
necessarily be required. Overall, available data do
not suggest that an adverse effect would be expected
on stimulation of downstream migration.
McArthur River. The McArthur River \'lill receive flows
from the powerhouse ranging from a minimum of
approximately 4600 cfs in July to a maximum of
approximately 7500 cfs in December. Present flows in
the upper McArthur River near the powerhouse are
7-45
estimated to average about 600 cfs in July and 30 cfs
in December. Thus, flows in this upper section will
be substantially increased by the operation of the
project during the entire year. The relative
magnitude of increase will be less downstream of its
confluence with the Blockade Glacier channels.
Post-project summer flow in the McArthur River
downstream of its confluence with the Noaukta Slough
will be less than pre-project conditions due to the
substantial decrease in flow through Noaukta Slough.
Floods on the McArthur River upstream of Noaukta
Slough would be increased by the operation of the
project. The amount of increase will be roughly
equivalent to the modification of the base flows upon
which the floods are superimposed. That is, the
source of the flood waters remains unchanged, but the
flow in the McArthur River as the flood begins will be
greater. The relative increase in flow would decrease
in a downstream direction along the McArthur River.
Below its confluence with Noaukta Slough, the McArthur
River would likely experience a reduced flood
magnitude. This is due to the decrease of inflow from
Noaukta Slough during the summer as compared with the
inflow under pre-project conditions. Noaukta Slough
contributes a greater mean daily flow to the McArthur
River from mid-June through mid-September under
pre-project conditions than the maximum that will be
diverted to the McArthur River for power generation
during project operation.
The upper McArthur River will experience increased
sediment transport loads due to the larger discharges
in the channe 1 • The upstream reaches will likely
scour the channel bed to reduce its gradient. In
addition, bank erosion will likely increase its rate
7-46
r
r
l
I'
\_
f .
~
t~
' \
t
L
r
r
{
r
l
( '
[~I
L
[
[
~
f -
b
b
[
L
Li
L
[
and areal extent as a result of the increased flow.
Flood discharges in mid-September 1982 caused bed
scour and bank erosion, and transported
quanti ties of sediments along its channel.
magnitude of this short-duration event
large
The
was
approximately 50 percent greater than those expected
on a daily basis under post-project conditions.
The increased post-project flows in the McArthur River
are not anticipated to cause significant changes in
channel configuration. However, some meandering
reaches, especially toward the upstream end, may
assume split channel characteristics. Further
analysis is required to ascertain the effects on
channel configuration, of the increased sediment
transport into the lower reaches of the McArthur
River.
The ice processes in the McArthur River will also
likely be affected by the project. Ice formation may
be reduced or possibly eliminated by the increased
quantity and temperature of flow. Evaluation of these
effects requires further study.
Turbidity in· the McArthur River canyon would be
expected to increase during the winter months.
Pre-project winter flow in that area appears to be
derived from upwelling and is clear. Water from the
powerhouse tailrace would be expected to have a higher
turbidity as is normally found in Chakachamna Lake.
Turbidity in the lake varies with depth during certain
times of the year but is generally similar to that
measured near the powerhouse location in the McArthur
River. Below the McArthur Canyon, flow from the
Blockade Glacier channel is also turbid and therefore
7-47
effects below the confluence of that channel should be
minimal.
Mainstem Habitat -Mainstem areas of the McArthur
River appear to be used as migratory pathways for
sub-adult and residential adult rearing, and for
spawning in the McArthur River canyon.
Table 7.6 lists escapement estimates of major species
that spawn in the McArthur River drainage by .
waterbody. The only area in which spawning habitat of
these SI;?ecies is likely to be affected is in the
McArthur canyon. All other listed areas are
tributaries. Spawning habitat in sloughs and side
channels of the McArthur canyon occur upstream of the
powerhouse tailrace. It is unlikely that these areas
will be significantly affected. Based upon 1982
escapement estimates, a relatively small percentage of
spawning salmon will be vulnerable to changes in
mainstem flow. Some fish that normally spawn above
Chakachamna Lake may be attracted to the powerhouse
tailrace which may affect spawning adults of McArthur
origin (see above) •
The redistribution of substrate in the powerhouse area
may also affect spawning. Presently, there are
insufficient data to determine if the effect would be
beneficial or adverse to the availability of habitat
to spawning adults.
Eulachon spawn in the lower reaches of the McArthur
River mainstem, below the Noaukta Slough. Flow
alterations are not expected to affect spawning of
this species because during the period of eulachon
spawning, the continued post-project McArthur River
7-48
['
I
l
[
[
r
f_
L
{
L
---,,....,_.,-..,
L i .. _I ,' ~: ,__....,
Table 7.6. Estimate escapement of important fish species in the McArthur River system by waterbody cla~sified by
potential of increased flow of water.
POTENTIALLY AFFECTED AREA
Species McArthur Canyon Stream 13X Stream 13U
Sockeye
666 5 5,416 6 1,213 6 Salmon
Chinook
07 452 7 1,633 7 Salmon
Pink
60 8 4,225 8 5,402 8 Salmon
Chum
19 09 23 9 Salmon
Coho
1,182 10 1,378 10 3210 Salmon
Dolly
Varden X X X
X= Probable Spawning areas.
1 Based on 6 day stream life Table 6.35, Section 6.8.3.
2 Based on count of live and dearl fish Table 6.34, Section 6.8.3.
3 Based on 6 day stream life Table 6.36, Section 6.8.3.
4 Based on peak on total counts Table 6.37, Section 6.8.3.
5 sasPd on 10 day stream life Table 6.38, Section 6.8.3.
6 Fig. 6.132
7 Fig. 6.34
8 Fig. 6.36.
9 Based upon 10 day strea~ life Table 6.37.
10 Based upon 10 day stream lifP TAble 6.38.
POTENT!.l\LLY NON-AFFECTED AREAS
Streams
Comb1ned 12. 1 12.2 ) 2. 3 12.4
27,636 6 16,711 1 6,085 1 2,512 1 2,328 1
22 7 ;122
10,090 8 8,499 3 1;566 3 43 18 3
59 44 14
2,137 10 2,ooo 5 46 5 89 5
X Y. X X X
--.
12.5
33
X
and Noaukta Slough flows are expected to be similar to
pre-project flows.
Increased post-project flows will occur above the
Noaukta Slough confluence on the McArthur River. The
lower post-project flows below the Noaukta Slough
confluence during June through September should not
~ave a significant effect on fish passage. It is not
clear at this time if the upstream migrants above the
slough will even be exposed to significantly higher
velocities than they are exposed to by pre-project
flows. This will need to be assessed in the future.
Pre-project water temperatures in the vicinity of the
proposed powerhouse location have a wide diurnal
variation during the open water season. The discharge
of Chakachamna Lake water during operation would tend
to stabilize the temperatures. Water temperatures at
the proposed lake tap depth were as follows:
March 2.1°C
August 6.5°C
September 6.2°C
The temperature of discharged water should be fairly
constant and should reduce diurnal variation and
maintain temperatures closer to optimal ranges for
spawning and incubation for many of. the species
present (Bell, 1980).
There are a number of fish species which use mainstem
habitats in the McArthur River for rearing habitat.
Presently, the effect of changes in the flow regime in
different reaches of the river at different times of
year cannot be determined. Changes in wetted
perimeter, depth and velocity for different areas will
7-50
[
[
f
[
L
t
[
[
f
L
[
L
L
L
affect the overall total suitable area for each
species and lifestage. Thus, suitable habitat may
increase, decrease, or remain the same. This will
also need to be assessed.
Increased f lmv in the McArthur canyon ·from the
powerplant discharge may affect available
overwintering habitat in the McArthur drainage. Data
collected during 1982 indicate that the McArthur
canyon and areas below it (station 13) may be used as
overwintering areas. Increased flow and depth may
increase the overwintering area available ..
Insufficient data are available to assess such
changes.
Water discharged from the powerhouse will probably be
warmer than water of HcArthur origin; 2 .1 °C, as
compared with 1.2°C, respectively, during March 1982.
This may result in greater metabolic activity by fish
and other aquatic biota during the winter, and result
in more rapid incubation and earlier emergence times
for McArthur canyon fish. Such emergence times would
be similar to those found in the Chakachatna River.
It is unclear from present data whether this will have
an adverse effect.
Increased post-project turbidity during the winter
months should not have a significant adverse effect on
fish in the McArthur Canyon. Turbidity levels should
be similar to those measured in this area during the
spring through fall, and it would be expected that
fish are well adapted to them.
There may be a potential for the discharge of dis-
solved gases at levels greater than 100 percent of gas
saturation at the powerhouse. Water discharged at the
7-51
powerhouse, entrained at lake tap depths of more than
100 ft, will undergo a pressure change of more than 3
atmospheres. The change in pres~ure will reduce the
amount of gas that the water will hold thus creating
the potential for supersaturation to occur. Evidence
of a potential for supersaturation was detected during
sampling in September 1982. If supersaturation occurs
it could have adverse effects on fish in the immediate
area of the discharge unless mitigative measures are
taken. (Merrell et al. 1971; Blahrn et al. 1975,
Fickeisen and Schneider, 1976, Bell, 1980).
Sloughs -Some sloughs in the immediate vicinity of
the tailrace of the powerplant may become inundated
and water velocities may increase. These changes may
affect the suitability of these habitats. The extent
of such changes cannot be determined at this time.
Tributaries -No significant changes would be expected
in McArthur River tributaries due to post-operational
flows based upon current data.
7.3.4.1.3 Summary of Potential Effects
Potential effects of the proposed project alternative
on the aquatic biota will vary depending upon
waterbody and location. Potential effects of
construction are likely to be limited in extent and of
short duration.Effects may include:
o Local increases in turbidity, unlikely to affect
fish significantly due to already high ambient
levels;
7-52
I
r
i
['
l
L
L
L
L
L
['
o Local increases in siltation and possible
degradation of some spawning habitat;
o Local clearing of banks with some increases in
water temperatures;
o Re-routing of flow with potential redistribution or
loss of existing habitat; and
o Potential spills of materials, which although of
brief duration may adversely affect biota.
Operational effects differ according to the waterbody
considered.
include:
Potential changes in Chakacharnna Lake
o Potential loss of some lake trout spawning area and
fry;
o Seasonal variation in available rearing habitat;
o Flooding of the downstream area of the Chilligan
River and some loss of spawning habitat through
siltation;·and
o Potential fish loss through turbine passage.
The successful operation of the fish passage facility
will be necessary for the continuation of the
population of sockeye salmon which spawns above
Chakacharnna Lake. Insufficient data are available to
properly assess the operational characteristics of the
current design.
Flow reductions in the Chakachatna River will
potentially have significant effects on mainstem and
7-53
side channel habitats. There are insufficient data to
assess potential changes in the suitability of habitat
and the net loss or gain of rearing habitat. Some
potential effects that can be identified include:
o Decrease in cover provided by turbid water in some
side channel spawning areas downstream of sloughs;
o Decrease in cover in some side channel milling
areas downstream of sloughs;
o Potential changes in distribution of fish with
changes in habitat; and
o Potential loss of some overwintering habitat.
Potential effects of the increased water release in
the McArthur River include:
o Potential mis-cueing, straying, and/or delay of
fish that normally spawn above Chakachamna Lake
through the release of olfactory cues at the
McArthur powerplant tailrace;
o Potential loss of some spawning habitat in the
McArthur River canyon;
o Potential habitat changes in upper reaches of the
McArthur River; the specific nature and extent of
such changes cannot be determined at this time;
r
t
f
o Potential decrease in temperature variation in the {_
upper McArthur River resulting in more optimal
temperatures for spawning and incubation of some
species; and
7-54
c
L
L
r
~·
I
I
f
L
L
L
7.3.4.2
o Potential release of gas supersaturated water which
could adversely affect fish in the immediate
vicinity of the tailrace.
Potential Effects on Botanical Resources
The development of a hydroelectric power project at
Chakachamna Lake, will result in changes in the
distribution and species composition of vegetative
communities. Based upon current designs for
Alternative E, these changes would occur over a
relatively small portion of the project area. Changes
that do occur may be beneficial or detrimental to the
biota depending upon the type of changes as well as
the location, duration and magnitude of change.
7.3.4.2.1 Direct Habitat Loss
Construction of a rockfill dyke and fish passage
facility in the upper Chakachatna River canyon and a
powerhouse in the ~lcArthur River canyon will
necessitate the removal of vegetation over a
relatively small area. The powerhouse and fish
passage facility will be primarily underground, thus
minimizing surface disturbance. The rockfill dyke
will be sited in the upper reach of the Chakachatna
canyon where the floodplain is unvegetated and the
canyon walls and glacial moraine support Sitka alder
and willow which are abundant throughout the project
area. The areal extent of vegetation removal during
road, camp, airstrip, and borrow pit development is
not yet known because the location and size of these
facilities have not been sufficiently defined.
7-55
7.3.4.2.2 Indirect Habitat Alteration
The most notable changes in the distribution of
vegetation will likely occur in the lower McArthur
River ·and Chakachatna River canyons. In the lower
McArthur canyon, increased flows emanating from the
tailrace and the deposition of excavated materials
within the floodplain near the powerhouse may reduce
the extent of riparian vegetation. In the Chakachatna
canyon below the dyke, reduced flows may e:nable
riparian vegetation to become established within what
is now the active floodplain. In time, if these
riparian thickets do expand, additional habitat for
moose, songbirds and furbearers may be provided.
Disposal of materials excavated from the power tunnel
and fish passage facility will be stockpiled in the
floodplain above the dyke. When the dyke is completed
and the lake level raised to an elevation of 1155 ft,
this disposal area, as well as portions of the lake
shore will be flooded. In the area subjected to the
annual fluctuations of lake water levels, portions of
the Nagishlamina, Chilligan and other smaller lake
tributary deltas will most likely realize a change in
their vegetative cover~ Vegetation may recede due to
inundation and shoreline destabilization. However,
such changes are expected to influence only a small
area since under pre-project conditions, the lake
level only occasionally reaches elevations at or
near 1155 ft. Above the high water level, the shore
may also develop a different species composition; one
more representative of early seral stages and wetter
soil conditions (Newburg and Malaher, 1972) • The
anticipated changes in riparian and shoreline
vegetation cannot be further refined until
site-specific, field verified, habitat maps have been
prepared and the operating reservoir levels better
defined.
7-56
f'
L
L
L
t-
r
k
L
L
( '
Downstream from the McArthur and Chakachatna canyons,
the influence of altered flows, either increased or
decreas~d, on riparian vegetation will depend upon the
direction and magnitude of channel migrations and the
amount of floodplain area removed from the influence
of flood events. Based upon current information, the
McArthur River channel above Noaukta Slough has been
naturally migrating and some rechanneling has occurred
in the slough under normal flow conditions. Sustained
higher flows in the upper McArthur River may result in
.accelerating this migration. The extent of channel
migration is also dependent upon floodplain substrate
and bank composition. Until information is available
on these parameters, the speed, direction, and
magnitude of migration in the upper McArthur River
cannot be assessed. The influence of reduced flows in
the Chakachatna River and Noaukta Slough may be to
reduce the frequency arid magnitude of rechanneling in
the slough and to remove portions of the now active
floodplain from the influence of flood events. Based
upon current information, it is not possible at this
time to estimate the location, extent or timing of
· revegetation.
The influence of wind or vehicle-generated dust
emanating from cleared areas, roads, and borrow pits
may influence the vegetative community composition in
the immediate vicinity of these facilities.
Accumulations of dust may accelerate the rate at which
snow melts (Drake, 1981) and affect the growth of
cottongrass and mosses (CRREL, 1980) • The extent of
vegetation changes due to accumulations of dust will
be dependent upon the methods and level of effort
exerted to reduce dust.
7-57
Off-road use of vehicles in the project area may
affect vegetation depending upon the type of vehicle,
the time of year, and soil moisture conditions
(Sparrow et al., 1978). Currently, no policy exists
to control or permit off-road use of the site.
To assess the influences on vegetation of constructing
and maintaining a transmission line, the vegetative
species composition, transmission line design, and
construction and maintenance techniques will need to
be established. Since this information is not
currently available, the effects of a transmission
line on vegetation cannot be evaluated.
7.3.4.2.3 Summary of Potential Effects
Potential effects of the proposed project alternative
on the botanical resources will vary depending upon
location. Small areas adjacent to project facilities
will be influenced by the construction and operation
of the project. Such influences may include:
o Increases in bank erosion along the upper McArthur
River due to increased channel migration;
o Increases in the extent of riparian vegetation in
areas removed from the active floodplain by reduced
flows in the Chakachatna River;
o Altered distributions of vegetation along the lake
shore and deltas due to higher, fluctuating lake
levels; and
f'
l .
f
L
o Reductions in vegetative cover and changes in L
species composition in areas cleared for the roads,
airstrip, and borrow pits. l~
7-58 [
l~,
f'
l
r·
l
(
I
f ' ,,
L
t
L
h
h
L
(
b-~
L
• L
[
7.3.4.3
Although it is likely that these vegetation changes
will occur, the extent of the change is less than that
typically associated wi tli. the development of a
hydroelectric project. This is because designs for
this project have incorporated a lake tap rather than
a reservoir and thus:
o Considerably less vegetation needs to be cleared;
o Effects of change in albedo should be negligible;
o The incidence of fire and vegetative disease. should
be reduced since it will not be necessary to
stockpile large amounts of cleared vegetation; and
o The amount of wind-generated dust should be less
since a much smaller area will be cleared.
Vegetation in the project area has been dramatically
changed through prior development. Roads provide
unrestricted access to the lower portions of the area,
extensive timber harvesting has greatly reduced the
vegetative cover over a large area near the
Chakachatna River, and an underground pipeline has
been sited on the shore of Trading Bay. It is
unlikely that the development of the Chakachamna Lake
hydroelectric project would influence vegetative
communities to the extent of these prior developments.
Potential Effects on Wildlife Resources and Habitats
The construction and operation of the Chakachamna Lake
Hydroelectric project will affect the wildlife
resources of the area. One means by which wildlife
may be affected is through habitat loss ·due to
facility siting. Because the area actually occupied
7-59
by a facility is usually small when compared to the
total area encompassed by a particular habitat type,
unless a facility is sited within a·special use area
(e.g. calving, nesting, or molting areas), the loss of
a small amount of habitat is usually not critical to
the future viability of a population.
A second means by which the biological-resources may
be affected is through habitat alteration. In this
case, some phase of development is usually responsible
for altering the physical or vegetative conditions.
Examples of this include the alteration of river
hydraulics, lake morphology, coastal sedimentation,
and biological community dynamics. Often when such
changes occur, the existing wildlife resources respond
with changes in species composition, diversity, and
distribution.
The third type of habitat change may occur as a result
of an influx of support services. Typically this
equates to an increase in the local human population,
increases in traffic levels (including air and
ground), and increases in noise. These conditions may
result in decreased use of adjacent areas by wildlife.
Regardless of which type of habitat change occurs, the
response of wildlife will vary with the time of year
and the species involved. If the habitat lost is of
minor importance and the extent is small, wildlife
populations may only abandon or discontinue their use
of the affected habitat while remaining in the general
vicinity. However, the effect on population levels
may be severe if habitats used for important life
functions are rendered unusable by intense activity,
or large scale habitat loss or change. These
important areas include the land and water used for
7-60
[
r
f
l
['
l .
r-,
l
r·
L
L
L
r~
L-
L
~
L
b
t
L
L
L
[
breeding, nesting, calving, staging, wintering and
denning.
7.3.4.3.1 Direct Habitat Loss
Through development of the Chakachamna Hydroelectric
Project, direct habitat losses due to facility siting
will occur with construction of the dyke, disposal
areas, powerhouse, fish passage facility, camps,
roads, airstrip, port and docking facilities, and
borrow pits. The influence of this habitat loss on
wildlife populations should be negligible. The dyke
will be sited at the outlet of Chakachamna Lake; an
area that receives little use by birds and mammals.
The powerhouse and fish passage facility will be
located in the McArthur River and Chakachatna River
canyons, respectively. Because these facilities will
be primarily underground, relatively small quantities
of surface habitat will be lost. Although the exact
size and precise location of the remaining facilities
have not been determined, each will occupy a
relatively small amount of habitat in an area that is
not considered to be essential to any species of bird
or mammal. It is assumed that development of disposal
areas in both the McArthur and Chakachatna floodplains
will result in the largest habitat loss, and greatest
disturbance to birds and mammals.
7.3.4.3.2 Indirect Habitat Alteration
Chakachamna Lake. Habitat alteration and disturbance
due to the construction and operation of the project
could influence the distribution of some wildlife
populations. In the vicinity of the lake above the
dyke, fluctuating water levels may have several
implications. As the lake level is lowered during the
7-61
winter, ice along the shore will most likely fracture,
eventually resulting in a zone of broken ice that may
prevent some large mammals from venturing out onto the
frozen lake surface. Moose, bears, wolves, and small
mammals are the primary inhabitants of the lake shore
during winter. However, the degree to which these
mammals use the frozen lake surface will need to be
established. During the ice-free period, a variety of .
birds and mammals use the shore of the lake. The
higher, fluctuating water level during this period may
alter small areas of shoreline habitat but should not
significantly influence the· overall use of the shore
by these wildlife.
Chakachatna and McArthur River Canyons. Construction
activities occurring in the Chakachatna River and
McArthur River canyoni may influence the apparently
limited use of the canyons by mammals and birds. The
canyons are used by eagles, bears, furbearers, moose,
and passerine birds. Near the construction sites,
increased levels of noise from heavy equipment and
blasting may discourage eagles, moose and bears from
using adjacent areas (Roseneau et al., 1981, McCourt
et al., 1974). However, other mammals, including
furbearers and small birds appear to have a higher
tolerance for human disturbance and may not
substantially alter their distributions (Penner, 1976,
Clark and Cambell, 1977). This influence of noise and
disturbance on wildlife populations in the canyons
should be limited to the construction period.
Chakachatna and McArthur River Floodplains. Below the
canyons, wildlife activity is more abundant and
diverse. In these areas, a variety of wildlife
species could be influenced by construction
activities. Due to increased levels of noise and
7-62
,.
r .
l
[
l
l
r .
l
r
L
L
L
L
r ,
L
L
L
r
disturbance, sensitive species such as moose, grizzly
bears, gray wolves, eagles, and swans may discontinue
their use of the affected area (Roseneau et al., 1981,
McCourt et al., 1974, Hampton, 1981). Other species,
including coyotes, ducks, and other small birds, are
more tolerant of disturbance and will probably not
alter their distribution (Penner, 1976, Gallop et al.,
1974, Schweinsburg et al., 1974, Ferris, 1979). If
avoidance of a construction area occurred it would
most likely be temporary with individuals returning to
the area soon after noise and activity levels
subsided. However, if areas used by wildlife for
imp~rtant life functions are abandoned, a decrease in
the abundance of some local species may be noted. To
evaluate which species may be affected and to what
extent, it will be necessary to establish the use and
importance of the Chakachatna and McArthur floodplains
to wildlife.
The alteration of habitat and wildlife distributions
below the canyons during the operation of the project
may be evident as a result of changes in the
vegetation communities or as changes in the abundance
or distribution of prey (particularly anadromous
fish). Changes in the distribution of vegetation (as
described under Potential Effects to Botanical
Resources) will probably not result in significant
changes in the distribution of wildlife populations.
Channel migration along the upper McArthur River and
rechanneling in Noaukta Slough may erode relatively
small areas of riparian vegetation. This may displace
a few individuals, but overall abundance of a wildlife
population in the project area should not be
significantly changed. Likewise, a small increase in
the abundance of floodplain riparian vegetation along
the Chakachatna River will probably not result in a
7-63
significant change in wildlife species diversity or
abundance in this drainage. The anticipated changes
may be more clearly defined by acquiring information
on the extent of channel migration, revegetation, and
the use of riparian areas for denning, wintering,
breeding, and calving.
It is unlikely that minor changes in anadrornous fish
abundance and distribution (described in Section 7.1)
will have a significant effect on the distribution of
either birds or mammals. Several species of wildlife
feed on anadromous fish. Although bears and eagles
are the most visible, mink, harbor seals, and beluga
whales also consume fish originating in the
Chakachatna or McArthur drainages. The degree to
which these species will be affected can be evaluated
by investigating the anticipated changes in fish
distribution or abundance and the reliance of wildlife
on this resource (Miller and McAllister, 1982). Based
upon the anticipated change in anadromous fish
abundance and the opportunistic nature of the wildlife
species involved, no significant change in the
abundance or distribution of wildlife is currently
expected to occur in either the Chakachatna or
McArthur drainage as a result of this project.
Increased access to the area will affect wildlife
populations by two means; increased disturbance from
construction activities, and increased local hunting
(sport and subsistence) pressure. By utilizing the
existing road network for construction and operation
in the Chakachatna drainage, only a slight increase in
vehicle-related disturbance to wildlife should occur.
However, through the construction and use of two road
extensions to access the McArthur drainage and
Chakachatna canyons, there will likely be a short-term
7-64
L
f
L
l
L
[
L
L
L
reduction in the use of areas adjacent to these roads
by species that are sensitive to traffic, particularly
moose, bears, wolves, eagles, and swans (Roseneau
et al., 1981, McCourt et al., 1974, Hampton, 1981,
Goddard, 1970, Elgmark, 1976, Carbyn, 1974). The
extent of this influence will depend upon the location
of moose wintering and calving grounds, the location
of brown bear, black bear, wolf, and wolverine denning
sites, and the location of swan and eagle nesting,
brood rearing, and fall staging areas. Future studies
will be needed to identify the locations of these
important habitats and to allow for more definitive
assessments.
Whether local wildlife populations are influenced by
increased hunting pressure will depend upon the
magnitude of the hunting increase and the level of
road access allowed. Currently no policy affecting
access of the project area has been outlined.
The influence on wildlife of constructing and
maintaining a transmission line and the likelihood of
bird collisions or electrocutions with the lines will
be dependent upon the species inhabiting the area,
transmission line design, and construction and
maintenance techniques. Until this information is
available, these effects cannot be assessed.
7.3.4.3.3 Summary of .Potential Effects
Wildlife populations within the project area may be
influenced during the construction and operation of
the facility. The direct loss of habitat by facility
siting will most likely not significantly affect the
abundance or distribution of any wildlife population.
7-65
Habitat alteration, however, may result in some minor
changes which include the following: [
0 Reduced access
caribou to the
for moose,
frozen lake
wolves,
surface
bears, and
during the
winter due to fractured ice along the shore;
o Reduced utilization by sensitive species (such as
wolves, moose, bears, eagles, and swans) of the
areas near the construction sites, camps, and roads
due to increased levels of noise and disturbance;
o Increased hunting pressure on large mammals and
birds allowed by the presence of road extensions to
the Chakachatna canyon and McArthur drainage; and
o Increased mortality of birds due to collisions or
electrocutions from transmission lines.
Although these changes are likely to occur, the
magnitude of the influences are less than those
usually associated with the construction and operation
of a hydroelectric facility. This is because designs
for this project have incorporated an underground
powerhouse, and a lake tap rather than a reservoir and
thus:
o Potentially important habitat, including large
mammal migration routes, moose wintering and
calving areas, bear and furbearer denning and
feeding areas, and bird nesting areas do not have
to be inundated to create a reservoir;
o The disturbance associated with clearing large
expanses of land will be absent; and
7-66
L
l
[
L
L
r
L
l
L
L
L
b
t
L
L
L
L
t
o Surface noise and disturbance associated with the
construction of a dam will be significantly
reduced.
Wildlife distributions within the project area have
been influenced in the past by large scale timber
harvesting, road construction, relatively high levels
of hunting . pressure, and the construction of an
underground pipeline on the shore of Trading Bay. It
is unlikely that the development of the Chakachamna
Lake project would influence wiidlife populations to
the extent of these prior developments.
7-67
7.4
7.4.1
Project Risk Evaluation
Development of the project would be attended by a number
of risks associated with the physical layout of the
project structures and natural phenomena occurring within
and adjacent to the project area. Some of these could
directly impact the cost of constructing the project
while others could either impair its output or .add to the
cost of maintaining the designed energy generation and
peaking capability. Typical among these aspects are the
following:
Project Layout
Lake tapping
Tunnel alignment -rock conditions
Underground powerhouse site
Natural Phenomena
Barrier Glacier
Blockade Glacier
McArthur Glacier
Mt. Spurr, Volcano
Lake Clark -Castle Mountain Fault
Faulting in Chakachatna Valley
Bruin Bay Fault
The above items are treated individually in the
paragraphs that follow.
Lake Tapping
At this stage of the project studies, it has been
necessary to presume that a location can be defined by
exploration where the rock conditions will b~ suitable
7-68
I
I
r ,
I
[
L~
f:
L
l
[
L
L
L
l
L
L
I ,
1"
I_'
6
t
L
L
L
L
L
7.4.2
for constructing the lake tapping. Based on examination
of rock conditions above the lake water level, the above
presumption seems to be reasonable but a significant
amount of exploration will be required to define suitable
rock. Furthermore, as far as it has been possible to
ascertain from reviewing the technical press, the
combination of diameter and depth needed for the
Chakachamna Lake tapping is without precedent and
considerable modification of.the tentative arrangement,
developed as shown for preliminary estimating purposes on
Figure 3-4, may be necessary before an acceptable design
concept is reached. Specifically, the length of the
final plug may need to be increased or multiple smaller
diameter openings may be required to penetrate from. the
underground excavations out into the lake. The length of
the chamber between the bottom of the intake gate shaft
and the lake may need to be increased. Factors such as
these cannot be finally determined until some design
phase subsurface exploration has been performed.
Tunnel Alignment Rock Conditions
As set forth in Section 7.2.2, bedrock characteristics,
as they may affect tunnelling conditions, have not been
specifically studied within the scope of studies thus far
completed. No geological mapping has been done along the
proposed tunnel alignment. However, aerial observations
of rock exposed along the tunnel alignment and in the
walls of the Me Arthur canyon lead to the indication that
suitable tunnelling conditions should be encountered.
This expectation needs to be qualified to the extent that
the rock overlying about 25% of the length of the tunnel
is concealed by glacial ice and its surface features
cannot be seen. The depth of rock cover and ruggedness
7-69
of terrain over the tunnel alignment virtually rule out
the practicability of conducting any subsurface
explorations at tunnel grade, except in the vicinity of
the upstream and downstream ends~ The depth of cover
exceeds 3000 feet over about 40% of ·the tunnel length and
it exceeds 2000 feet over about 66% of the length.
(Figure 3-3). With such depths of cover, ground water
under high pressure could be encountered where the tunnel
penetrates permeable fissures or water bearing joints.
Some dramatic changes in relief occur at several
locations along the tunnel alignment. These could _give
rise to the presence of troublesome stress concentrations
particularly, for example, where a deeply incised
U-shaped valley runs perpendicularly to the major
principal stress of the in-situ bedrock stress field.
Furthermore, due to the nearby presence of the Castle-
Mountain-Lake Clark fault and the depth of cover over
much of the tunnel alignment, there is the possibility
that in-situ rock stresses may be high and that rock
bursts may be a factor to contend with during excavation
of the tunnel.
High pressure ground water and adverse rock conditions
are factors which could add to the cost of constructing
the power tunnel. The great depth of rock cover prevents
exploration at tunnel grade except near the two ends. In
the absence of exploration over so much of the tunnel
length, more water at high pressure, and more highly
stressed rock than anticipated, might be encountered
during construction of the tunnel, and in that case, the
constructed cost could exceed the cost that was estimated
at the present stage of the investigations.
7-70
r .
\
r
I.·
L
L
r
( .
!
L
A' .,
L
J
l
l .
[
L
7.4.3
7.4.4
Underground Powerhouse Site
Final determination and confirmation of the location of
the underground powerhouse site should preferably await
design level exploration, the construction of an
exploratory adit and laboratory and in-situ measurement
of the engineering properties of the rock. The walls of
the McArthur canyon afford good rock exposures and allow
a more ~eaningful assessment to be made of the rock
quality than any number of drill holes. There is again,
however, the nearby presence of the Lake Clark-Castle
Mountain fault and the possibility that high in-situ rock
stresses may occur near the fault. If so, rock bursts
could occur during excavation of the powerhouse cavern
and associated underground excavations.
Barrier Glacier
This is the glacier that contains Chakachamna Lake and
controls its water level. It descends the southerly
slopes of Mt. Spurr to the Chakachatna Valley, which it
crosses, and thrusts against the steep face of the
Chigmit Mountains that forms the south wall of the
valley. During the summer of 1981, the U.S. Geological
Survey conducted some measurements of ice thickness in
connection with an evaluation of the volcanic hazards
posed by Mt. Spurr. Many of the field data are still in
raw form, but in the floor of the Chakachatna Valley, the
thickness of ice in the Barrier Glacier was believed to
be in the order of 500-600 feet (Mayo, u.s.G.S.
Fairbanks, verbal communication, 1982). The depth of
water in Chakachamna Lake is about 300 feet.
7-71
The natural outflow from the lake discharges via a
channel eroded through the glacial ice along its contact
with the mountain wall on the south side of the valley.
The channel is armored with large boulders which are
carried along by the glacial ice and are deposited in the
channel as the ice melts. Over the years, the channel
bed apparently aggrades, and the lake water level rises
until there develops a combination of circumstances that
produces an outbreak flood which erodes the channel bed
and lowers the lake water level. The last known event of
this nature took place on or about August 11, 1971. The
flood peak was estimated to be in the order of 470,000 cfs
and the lake level dropped about 14 feet. (Lamke 1972).
Only unsubstantiated reports and fragmentary evidence
exist of previous outbreak floods. It is, however,
rather evident that these would be cyclic events having
uncontrolled and indeterminate periods, and that the lake
outlet is in a state of changing equilibrium that among
other things is strongly affected by the rate at which
the Barrier Glacier advances towards the south valley
wall, and the annual runoff from the watershed area
discharging into the lake.
No evidence of surging has been reported in Barrier
Glacier though Pothole and Harpoon Glaciers, nearby to
the north, have both been identif~ed as surging glaciers
(Section 5.2.1.5). Barrier Glacier has, however, gone
through various cycles of advance and retreat in recent
time, and may reasonably be expected to continue to do so
in the future. The extent to which such cycles might
affect the lake level, and thus the amount of regulatory
storage available for power generation, cannot be
predicted with certainty.
7-72
('
\
I
r
r
r
r t
f
L
J :
{~ . -
[
L
(
L
[ -
r
I
L-
L
(_
r
7.4.5 Blockade Glacier
This glacier is fed by large snow fields high on the
southerly slopes of·the Chigmit Mountains to the south of
the McArthur canyon. At about 1700 feet elevation, the
glacier splits into two forks, one flowing southwesterly
and the other northeasterly towards the McArthur River.
The glacier impounds Blockade Lake beyond the terminus of
the soutwesterly lobe.· As set forth in Section 5.2.1.4
of this report, Blockade Lake is the source of outburst
floods that discharge into the McArthur River.
The present terminal moraine of the northeasterly flowing
lobe of Blockade Glacier lies within about 1-1/2 miles of
the mouth of the McArthur canyon. If the Blockade
Glacier were to advance during the life of the project,
it is conceivable that the morainal material could also
advance toward the McArthur River and cause the river bed
to aggrade downstream of the mouth of the canyon. This
could cause a rise in tailwater level to occur at the
power plant site with the extreme consequence being a
flooding of the powerhouse if a channel were not
mechanically excavated through this material.
As summarized in the closing paragraphs of Section 5.2.1.4
of this report, Blockade Glacier's recent history has
clearly been one of recession, and it is believed that it
began to withdraw from its most recent maximum advance
within the last few hundred years. At that maximum
advance, melt water from the glacier joined the McArthur
River near the canyon mouth and outwash may have caused
some aggradation of the river bed in the lower reaches of
the canyon. Surging of the Blockade Glacier is
7-73
7.4.6
7.4.7
considered to be the most likely mechanism that could be
expected to produce an advance of the glacier· that might
impact on the proposed McArthur powerhouse site. No
evidence suggestive of recent surging was, however,
observed during the field studies.
The possibility that climatological changes and
consequent changes in mass ice balance may trigger
surging of the Blockade Glacier during the life of the
project is a remote possibility that cannot be forecast
or evaluated with any degree of certainty.
McArthur Glacier
The terminus of this glacier lies in the McArthur canyon
about 5 miles upstream from the proposed powerhouse
site. An advance of the glacier over that distance would
endanger the tailrace channel and portals of the tailrace
tunnel and access tunnel to the underground powerhouse.
Such an advance would, however, involve almost doubling
the existing length of the glacier and is, therefore,
most unlikely to occur. Since the Blockade and McArthur
glaciers are fed by adjacent snow fields, a change in
sno~ supply needed to cause a five mile advance in the
McArthur Glacier would create an even greater problem due
to advancement of the Blockade Glacier.
Mt. Spurr Volcano
The summit of Mt. Spurr rises to elevation 11,070 feet
above sea level and lies about 7 miles northeasterly from
the outlet of Chakachamna Lake and 7-1/2 miles from the
proposed power intake site. The intake could be located
7-74
t '
[
\
r
r
(
l
f
( '
(-
L
L
l
J
'-J
l
L
1 (, _____ _
l
I
f h'
further to the west to increase its distance from the
volcano but this would increase the length and cost of
the power tunnel, and also the difficulty and cost of
access to the intake site along the. precipitous mountain
slopes on the south side of the lake.
Mt. Spurr's last major eruption occurred on July 9,
1953. It ejected a large ash cloud which reached an
altitude of approximately 70,000 feet,.darkened Anchorage
and deposited about 1/4 inch of volcanic ash on the city
(Juhle and Coulter 1955).
The source of the eruption was reported to have been
Crater Peak, a subsidiary vent at 7575 feet altitude on
the southerly slopes of the volcano. The
eruption triggered a mud slide that dammed the
Chakachatna River about 6 miles downstream from the
outlet of Chakachamna Lake. The river backed up nearly 5
miles, overtopped the dam and has since partially eroded
its way down through the debris. Abundant evidence
exists along the northerly slopes of the Chakachatna
Valley of a long history of violent volcanic activity.
Large deposits of mud flow materials and pyroclastic
breccias occur for several miles along its length.
Examination of aerial photographs taken in 1954, 1957 and
1978 suggest the possibility that some minor mud flows
may have occurred on the slopes below Crater Peak since
the 1953 eruption.
The u.s. Geological Survey undertook a limited
micro-seismic study of the Mt. Spurr area during the
summer of 1982. The results have not yet been published
but they are planned to be the subject of a report
scheduled to be released during 1983.
7-75
Mt. Spurr is regarded by some volcanologists to be
similar, in several respects, to Mt. St. Helens in the
State of Washington whose May 18, 1980 eruption
devastated a 200 square mile area. In the path of the
main blast, devastation of forest land was complete as
far as 18 miles from the crater.
Present technology for predicting volcanic activity is
limited to the short term, and there is no way to
forecast when Mt. Spurr will next erupt, or whether it
might erupt during the life of the project. A catas-
trophic blast, such as occurred at Mt. St. Helens is a
rare event but of course cannot be ruled out at Mt. Spurr.
As discussed in Section 5.2.2.2 of this report, the
general direction of a future blast at Mt. Spurr is
expected to be in the southeasterly quadrant, or directly
across and down the Chakachatna Valley. The proposed
power intake site on Chakachamna Lake could be an area of
ash deposition. It could also be affected by a large
landslide or mudflow, or by hot blasts from pyroclastic
flows if such were to occur, and the evidence is that
these have occurred in the past, particularly in the
Chakachatna Valley.
While future events similar to the 1953 Crater Peak
eruption would probably have little effect on the ability
of the power facilities to continue in operation, they
could readily put the fish passage facilities out of
service. Another mud flow could dam the river below
Crater Peak thus causing it to back up and flood the
proposed structure at the downstream end of the fish
passage facilities. The reduced flow in the Chakachatna
River would not have the same erosive power to cut its
7.-76
I c
!
r
l
l
' .i
!
l
J ' "
{
t.
L
r~ t J
l
r 1
L
r
L
l_
L
way down through the debris dam and it could well become
necessary to mechanically excavate a channel through the
debris to lower the water level and return the fish
passage facilities into operation. A catastrophic event
of the Mt. St. Helens type, if directed towards the lake
outlet and intake structure, could have very serious
consequences and possibly bury both the upstream and
downstream ends of the fish passage facilities, and the
power intake, beneath a massive mud flow. The tremendous
amounts of heat released by pyroclastic ash flows could
melt ice in the lower parts of the Barrier Glacier and
interfere with the glacier's ability to continue to
contain Chakachamna Lake.
The powerhouse and associated structures in its vicinity
would probably not be significantly affected by volcanic
activity at Mt. Spurr because they are shielded from the
direct effects of a volcanic blast by the high mountains
between the Chakachatna and McArthur Valleys. Depending
on wind direction at the time of the eruption, ash
deposition is probably the main effect that would occur
near the powerhouse site and this could lead to temporary
interruptions in power supply. Similar outages could be
caused by ash accumulating on transmission line
insulators.
Volcanic events are risks that would be associated with
development of the project. The probability of major
events occurring during the project's life is small, but
the probability or effects on the project cannot be
predicted with certainty.
7-77
7.4.8
7.4.8.1
Seismic Risk
The site lies within a zone of high seismic risk. As set
forth in Section 5.3.3.3 of this report, potential
seismic sources which may affect the project site are the
subduction zone, faults in the crustal seismic zone and
severe volcanic activity. The Lake Clark-Castle Mountain
fault (crustal source) and the megathrust segment of the
subduction zone are considered the most critical with
respect to peak ground acceleration and duration of
strong shaking at the site. The maximum probable or
operating basis earthquake for the site, defined as the
earthquake that can reasonably be expected to occur
during the life of the project has not yet been defined.
The probability that the vibratory ground motion of the
operating basis earthquake will be exceeded during the
life of the project can be calculated by using generally
accepted techniques. Thus, the seismic risks associated
with the site can probably be submitted to more rational
risk analysis than can the risks associated with
glaciology or volcanism, principally because much more
data is available on the frequency of occurrence of
seismic events in the region than is available on the
frequency of significant volcanic ~vents from Mt. Spurr
or the frequency of aberrations in glacial activity at
the site.
Lake Clark -Castle Mountain Fault
This is a major regional fault that has been traced for
over 300 miles. (Magoon et al 1976). It extends from
its northerly end near the Copper River basin about 120
miles to the northeast of Anchorage (Figure 5-9), to the
7-78
i"
}
r .
t
I . ~
}
l -
r .
~
~~
{~
l .
..
l )
L:
1
l~
I .
l-
1 .
t
L
(
L
L
L
7.4.8.2
southerly end in the Lake Clark area. It crosses the
McArthur Canyon at the canyon mouth where a prominent
rift can be seen in the mountainside. The northerly
parts of the Lake Clark-Castle Mountain fault have been
extensively studied and evidence of recent displacement
has been documented near the Susitna Valley. Less is
known about the southerly portion of the fault but it is
considered to·be capable of causing a large earthquake
and of experiencing significant displacement during the
life of the Project. For this reason, and for reasons of
improvement in rock quality with distance from the fault,
the proposed powerhouse is shown as being upstream from
the mouth of the canyori, although this results in some
head not being developed.
At least one crossing of the fault by the power trans-
mission line cannot be avoided; this will be in the
vicinity of the mouth of the McArthur Canyon. The
powerhouse switchyard also would be in this vicinity.
Thus, some of the transmission towers and switchyard
structures would be subjected to very strong shaking in
the event of a major earthquake on the fault near the
McArthur Canyon. Underground structures will probably be
less vulnerable to damage than surface structures. The
structures can be designed to withstand the strongest
lateral forces expected to occur, but it is not possible
to design against significant displacement in the
foundation at any given structure site. Consequently
structures should not be located in the fault zone.
Bruin Bay Fault
This is one of the major regional faults in Southern
Alaska. In the vicinity of the project site, it is
7-79
7.4.9
7.5
inferred to occur.more or less parallel to the Cook Inlet
coastline about 20 miles southeast of the mouth of the
McArthur Canyon (Figure 5-9). But, its trace in that
area is obscured by glacial diposits and its relation-
ship to the Castle Mountain Fault is not known.
Faults in Chakachatna Valley
Four features which may be significant to the Project
have been identified in the Chakachatna Valley (Figure
5-9), and are discussed in Section 5.3.3.3 of this
report. Based on the 1981 geologic investigations which
were limited to study of remote sensing imagery and of
aerial (helicopter) observations, it was concluded that
these features include faults which may offset Holocene
deposits (less than about 2 million years old); also, one
of the features trends toward the site of the proposed
power intake structure. Further study of the Project
should include evaluation of the age and extent of
faulting which is related to these features, in order to
better assess the potential for fault displacement at or
near Project structures.
References
Juhle, Werner and Coulter, Henry, 1955, The Mt. Spurr
Eruption, July 9, 1953: American Geophysical Union,
Transactions, Vol.36, Number 2, Pages 199-202.
Lamke, Robert D., 1972, Floods of the Summer of 1971 in
South-Central Alaska: U.S. Geological Survey Open
File Report.
Magoon, L.B., Adkison, W.L., and Egbert, R.M. 1976, USGS
Map No. 1-1019 Showing Geology, Wildcat Wells,
Tertiary Plant Fossil Localities, K-Ar, Age Dates
and Petroleum Operations, Cook Inlet Area, Alaska.
7-80
1
r
L
L
1 \
I l ,
r .
L.
{_
l.
CONSTRUCTION COSTS
AND SCHEDULES
8.0
8.1
CONSTRUCTION COSTS AND SCHEDULES
Estimates of Cost
Estimates of construction costs have been prepared for
the following alternatives for project development:
Alternative A -400 MW McArthur tunnel development
Alternative B -330 MW McArthur tunnel development
Alternative C & D -300 MW Chakachatna tunnel
development
Alternative E -330 MW McArthur tunnel development
The estimates are based on schedules of quantities of
materials and equipment needed for the major features
of each alternative to the extent permitted by the
drawings for Section 3.0 of this report. In some
cases, quantities were proportioned from the
construction records of other projects bearing
significant similarity of structures and conditions
expected to be encountered during construction of the
Chakachamna Hydroelectric Project. Unit prices
developed for this and other projects involving
similar types of construction and from analyses of
bids received for the construction of similar types of
projects in Alaska, adjusted as necessary to reflect
January 1982 price levels, were then applied to the
schedules of quantities to arrive at the estimated
costs set forth in the Conceptual Estimate Summaries,
sheets 1 of 2 and 2 of 2. The summaries show the
8-1
co
N
CHAKACHAMNA HYDROELECTRIC PROJECT
CONCEPTUAL ESTIMATE SUMMARIES-SHEET 1 OF 2
ESTIMATED COSTS IN THOUSANDS OF DOLLARS
ALTERNATIVES A
LAND AND LAND RIGHTS Not included 0
POWER PLANT STRUCTURE AND IMPROVEMENTS
Valve Chamber 5,600
Underground Power House 26,200
Bus Galleries 200
Transformer Gallery 4,600
Valve Chamber and Transformer 400
Gallery -Access Tunnel
P. H. Access Tunnel 13,500
Cable Way 800 --51,300
RESERVOIR, DAM AND WATERWAYS
Reservoir 100
Intake Structure 10,400
Intake Gate Shaft 13,200
Fish Facilities -
Dike & Spillway -
Access Tunnel
-At Intake 21,600
-At Surge Chamber, No.3 6,600 -
-At Mile 3, 5, No. 1 0
-At Mile 7, 5, No.2 0
Power Tunnel 626,800
Surge Chamber -Upper 12,900
Penstock-Inclined Section 18,000
-Horizontal Section and Elbow 6,700
-Wye Branches to Val,ve Chamber 13,200
-Between Valve Chamber & Power House 800
Draft Tube Tunnels 1,900
Surge Chamber-Tailrace 2,400
Tailrace Tunnel and Structure 10,300
Tailrace Channel 900
River Training Works 500
Miscellaneous Mechanical and Electrical 7,100 --753,400
A, B -McArthur development, high level tunnel excavated by drilling and blasting
C, D -Chacackatna valley development excavated by drilling and blasting
E -Me Arthur development, low level tunnel excavated by boring machine
B c D
Not included 0 Not included 0 Not included 0
5,500 5,600 5,600
25,200 26,200 26,200
200 200 200
4,300 4,300 4,300
400 400 400
13,500 13,500 13,500
800 800 800 -49,900 -51,000 --51,000
100 100 100
9,300 10,400 10,400
12,400 13,200 13,200
---
---
19,100 21,600 21,600
5,900 8,900 8,900
0 20,800 20,800
0 14,500 14,500
580,400 7 12,500 712,500
11,000 12,900 12,900
16,500 15,400 15,400
6,000 6,700 6,700
11,900 12,100 12,100
600 800 800
1,700 1,900 1,900
2,400 2,400 2,400
9,600 10,300 10,300
700 900 900
500 . 500 500
6,100 5,700 5,700 --694,200 --871,600 --871,600
E
Not included .
5,500
25,200
200
4,300
400
13,500
800
49,900
100
9,300
17,600
85,400
9,100
0
5,900
0
0
447,800
18,900
0
6,000
11,900
600
1,700
2,400
9,600
700
500
6,100 --633,600
:-:!":'
CHAKACHAMNA HYDROELECTRIC PROJECT
CONCEPTUAL ESTIMATE SUMMARIES-SHEET 2 OF 2
ALTERNATIVES
ESTIMATED COSTS IN THOUSANDS OF DOLLARS
A
TURBINES AND GENERATORS 67,900
ACCESSORY ELECTRICAL EQUIPMENT 11,200
MISCELLANEOUS POWER PLANT EQUIPMENT 8,600
SWITCHYARD STRUCTURES 3,600
SWITCHYARD EQUIPMENT 13,800
COMM. SUPV. CONTROL EQUIPMENT 1,600
TRANSPORTATION FACILITIES
· Port 4,600
Airport 2,000
Access and Construction Roads 59,600 -66,200
TRANSMISSION LINE & CABLE CROSSING 63,200
TOTAL SPECIFIC CONSTRUCTION COST AT 1,040,800
JANUARY 1982 PRICE LEVELS
ENGINEERING & CONSTRUCTION MANAGEMENT 124,900
SUBTOTAL 1,165,700
CONTINGENCY@ 20% 233,100
ESCALATION Not Incl.
INTEREST DURING CONST.@ 3% PER ANNUM 111,900
OWNER'S COSTS Not Incl.
ALLOWANCE FOR FISH PASSAGE FACILITIES -
TOTAL PROJECT COST AT 1,510,700
JANUARY, 1982 PRICE LEVELS
USE 1,500,000
A,.,B -McArthur development, high level tunnel excavated by drilling and blasting
C, D -Chacackatna valley development excavated by drilling and blasting
E · -Me Arthur development, low level tunnel excavated by boring machine
4,600
2,000
59,600 ---
B c D
57,900 54,500 54,500
9,500 9,000 9,000
7,300 6,900 6,900
3,600 3,600 3,600
12,500 12,100 12,100
1,600 1,600 1,600
4,600 4,600
2,000 2,000
44,100 44,100
66,200 50,700 50,700
63,200 56,500 56,500
965,900 1,117,500 1,117,500
115,900 134,100 134,100
1,081,800 1,251,600 1,251,600
216,400 250,300 250,300
Not Incl. Not Incl. Not Incl.
104,100 101,400 101,400
Not Incl. Not Incl. Not Incl.
50,000 -50,000
1,452,300 1,603,300 1,653,300
1,450,000 1,600,000 1,650,000
E
57,900
9,500
7,300
3,600
12,500
1,600
4,600
2,000
59,600
66,200
63,200
905,300
108,700
1,014,000
203,000
Not Incl.
97,400
Not Incl.
Under
Reservoir
Item
1,314,400
1,314,000
following estimated project costs excluding owner's
costs and escalation:
Alternative A $1.5 billion
Alternative B $1.45 billion
Alternative c $1.6 billion
Alternative D $1.65 billion
Alternative E $1.32 billion
The above costs include a 20% contingency added to the
specific construction cost plus engineering and
construction management, and interest during
construction. The costs for Alternatives B and D
additionally include a provisional allowance of $50
million for fish passage facilities at the lake
outlet. Costs for Alternative E include a constant
grade tunnel from powerhouse level at the McArthur
River to the base of the intake gate shaft at
Chakachamna Lake, and pending the completion of
geological studies of the tunnel alignment, the
assumption is made that this tunnel will be driven by
a boring machine. Included also in Alternative E is
the estimated cost of proposed fish facilities at the
Chakachamna Lake outlet as described elsewhere in this
report and shown on drawings. The estimated project
costs are considered to be conservative because of the
conservative assumptions made regarding the amount of
rock support required in the underground excavations.
For all of the alternatives, the principal structures
consist of the following:
o Intake structure at Chakachamna Lake with
underwater lake tapping, and control gate shaft.
8-4
r
\
I
\.. -
{
l_
r l_
f
L
{ __
0
0
0
0
0
0
0
0
0
0
Concrete lined power tunnel with constructiop
access adits.
Surge chamber and except for Alternative E,
emergency closure gates at the downstream end of
the power tunnel.
Underground concrete lined pressure penstock and
manifold.
Concrete and steel lined penstock branches
leading to a valve chamber and the turbines.
Four unit underground powerhouse with exploratory
adit (to become the ventilation tunnel) and main
access tunnel.
Underground transformer vaults and high voltage
cable gallery.
Tailrace tunnel and surge chamber.
Tailrace outlet channel and river protection
works.
High voltage cable terminals and switchyard.
Transmission lines to northerly shore of Knik Arm.
o High Voltage submarine cable crossing of Knik Arm.
In addition, for Alternative E the following principal
structures are included:
8-5
8.1.1
0 Concrete lined surge shaft connecting surge
chamber and downstream end of power tunnel.
o Rockfill dike at Chakachamna Lake outlet.
o Spillway at lake outlet.
o Fish passage facilities at lake outlet for both
upstream and downstream migrants.
Power Tunnel
The cost of constructing the power tunnel is the
dominant feature, representing more than half the
estimated cost of constructing each alternative.
Detailed evaluations were made of all operations and
the direct costs considered necessary to construct the
25-foot diameter concrete lined power tunnel for
Alternatives A, C and D, using both rubber tired and
rail haulage equipment. The difference in cost
between the two was found to be small. Thus, the
choice of haulage equipment will probably be
determined by other considerations such as for
example, whether excavation and concrete placement
would be scheduled by a Contractor to take place
concurrently in a given tunnel heading. This can be
accomplished if necessary in a 25-foot diameter tunnel
with either rail haulage or rubber tired equipment.
The estimated cost of constructing the 23-foot
diameter tunnel required for Alternative B was first
proportioned from the estimated unit costs per lineal
foot for constructing the 25-foot diameter tunnels for
Alternatives A, C and D using the same construction
8-6
r
I
ll
r
f '
l .
r~
' "
r·
L L~
L
L
[_
methods of drilling and blasting. These costs are
indicated in the summary schedule for Alternative B at
the end of this chapter as $580,400,000.
For Alternative E, an alternative method of driving
the tunnel by a boring machine was considered as well
as a modification of the profile of the tunnel using
uniform grade from near the base of the intake shaft
to the powerhouse. Two surface samples of rock
collected from the general vicinity of the power
intake site at Chakachamna Lake and one sample
collected from the surface in the vicinity of the
powerhouse site near the McArthur River were tested
for compressive strength, indentation, point load,
quartz content and cutter penetration rate at The
Robbins Company laboratory in Kent, Washington.
Although test data obtained from surface samples can
sometimes be misleading when compared to comparable
data obtained from fresh rock samples taken at depth,
the data were used with appropriate conservatism to
estimate the rate of penetration of a tunnel boring
machine working in this rock. The use of a boring
machine for ex9avating showed a saving in costs of
$126,700,000. Changing the grade of the tunnel showed
an additional saving of $5,000,000. The total cost of
constructing the tunnel was thus reduced from
$580,400,000 to $448,700,000. This cost was used in
the summary schedule for Alternative E, the
recommended alternative.
Tfie estimated tunnel construction costs are based on
the following items:
8-7
o Excavation for Alternatives A, B, C and D would
be by conventional drilling and blasting
generally with full face excavation, drilling·
12-foot depth rounds. Allowance is included for
a nominal length of tunnel where the depth of
rounds might have to be reduced, or where top
heading and bench techniques might have to be
used temporarily, if less favorable ground
conditions are encountered.
0
0
0
Excavation for Alternative E would be by a boring
machine to 27-foot boring diameter which after
lining would be hydraulically equivalent to the
23-foot diameter horseshoe for Alternative B
driven by conventional methods. The rate of
advance was estimated at 50 feet per day
calculated on the basis of a similar project in
similar rock formation. Assumptions for support
were conservatively left the same as for the
conventionally driven tunnel, although it is
realized that some savings would probably result
in actual operation. Also, sections of the
tunnel may be left unlined because the boring
machine provides a smoother excavated surface
than conventional methods, thus reducing tunnel
friction losses.
The assumptions are made that 25% of the tunnel
length would require steel rib support, 25% would
be supported by patterned rock bolts and 50%
would be unsupported.
Chain link mesh for the protection of workmen
from rock falls is provided above the spring line
over the full tunnel length.
8-8
r
(
[
l
r
I
\
l .
L
[
r t .
f
L
[
t
L
F
L
L
r-
L
L
L
8.1.2
0
0
Estimated excavation costs include provision for
handling and removing 2000 gallons per minute of
groundwater inflow in each tunnel heading.
Excavation and concrete lining would proceed on a
3-shift basis, 6 days per week.
o Construction access adits would be located near
the upstream and downstream ends of each tunnel
alternative. In addition two intermediate adits
would be provided for Alternatives C and D.
Underground Powerhouse and Associated Structures
For purposes of the current estimates, the powerhouse
has been taken as an underground installation for each
alternative, with a high pressure penstock shaft and
low pressure tailrace tunnel. The estimates o£ cost
are based on the following conditions:
o All excavation and concrete work would proceed on
a 3-shift, 6 days per week basis.
o The powerhouse cavern, valve chamber and tailrace
tunnel would be excavated by top heading and
bench.
o The penstock and surge shafts would be excavated
first by pilot raise, then by downward slashing
to full diameter.
o Excavation for the horizontal penstock and
manifold, access tunnel, cable gallery and draft
tubes would be full face.
8-9
8.1.3
o Chain link mesh is provided for protection of
workmen over the upper perimeter of all
excavations exceeding 12 feet in height.
o All permanent excavations would be supported as
determined necessary by patterned rock bolts.
o Allowance is included for lining the upper
perimeters of all caverns, chambers and galleries
required for permanent access and those housing
vulnerable generating or accessory equipment with
wire mesh reinforced shotcrete (this may only be
needed locally according to rock conditions
exposed during construction) •
0
0
0
Excavation of an exploratory adit, and a program
of core drilling and rock testing will precede
and confirm the suitability of the site for the
underground powerhouse complex during the design
phase and the costs thereof are included in the
estimates.
The costs included for the major items of
mechanical and electrical equipment are based on
current data with added allowance for delivery
and transportation to the powerhouse site.
Installation costs are also included.
Costs of mechanical and electrical auxiliary
equipment and systems, control and protective
equipment are included.
Tailrace Channel
The estimates include a monetary allowance for the
construction of an outlet channel and river training
8-10
r
1
r
f t
[~
r:
[
l ~
f
I
l ~
r ,
t ~
l
L
r-
L
L
L
L
8.1.4
8.1.5
8.1.6
works to protect it from damage during floods in the
river. Details of such requirements are not well
defined at the present stage but it is contemplated
that extensive use would be made of rock spoil from
excavation of the powerhouse complex for these
purposes.
River gravels excavated from the tailrace channel
would be processed and used to the maximum extent
possible for concrete aggregate.
Switchyard
In each alternative, due to space limitations, the
switchyard would be located outside the mouth of the
canyon on gently sloping land and an appropriate
allowance is included in the estimates for their cost.
Transmission Line and Cable Crossing
Field data acquisition has not been performed and
information regarding construction conditions is
limited to aerial observation of the proposed
transmission line alignment and cable crossing. The
cost allowed in the estimate for the transmission line
is based on experience and includes the estimated cost
of the submarine cable crossing to a dead end
structure on the Anchorage Shore of Knik Arm.
Site Access and Development
The estimates include costs of constructing access and
support facilities needed for construction of the
permanent works. These would consist basically of the
following installations:
8-11
0
0
0
0
Unloading facility on tidewater at Trading Bay,
complete with receiving and warehousing
provisions, bulk cement and petroleum fuels
storage plus a small camp for operating staff.
Gravel surfaced all-weather access roads to
construction sites (Figure 8-1). It has been
assumed that where existing roads are suitably
located, permission to use them could be
negotiated with their owners in exchange for
improvements that would include widening them to
full two-way traffic roads. Bridges and culverts
would be provided at all streams and water
courses and where needed for drainage. Year-
round maintenance costs are included throughout
the construction period.
An aircraft landing facility with a runway of
sufficient length to handle aircraft up to DC-9
and 737 types, and ground support facilities.
For Alternatives A, B and E, major construction
camps would be located outside but close to the
mouth of the McArthur Canyon to accommodate
workers employed on the downstream heading of the
power tunnel, the powerhouse and associated
structures. A second camp for workmen employed
on the upstream heading of the power tunnel and
intake works would be provided just east of the
Barrier Glacier on the northerly side of the
river. This camp will also be used for
construction of the lake outlet works and fish
facilities for Alternative E.
8-12
[
1
L
r
l
[,
[
(
L
l
L
l
L
L
j
~-J
J
_j ---
.J
J
NOT£S:
1.) TOPOGRAPHY IS FRO-+! USGS
(;VAORAAJGLE MAPIS
'Z.)HOI?/ZONTAi. (;RIO IS l/NIVERSAi.
TRAAJSVcRSE MECATOR
PR.OJECTIOA/1 1927 A/OR.TH AMERICAAI
DATUM. 1
3)VERTICAI. OAT/1M IS MEAN /.OWER
i.OW WATER.
L€6£1...10
----EXISTIAJG ROAD TO 13E
/MPROVcO
----EXISTIAIG ROAD
-----Aiel</ ACCESS ROAD
0 4 MILES
SCALE : 1'= 2 MILES
o For Alternatives C and D the main construction
camp would be located outside the mouth of the
Chakachatna Canyon for workers employed on the
downstream heading of the power tunnel, the
powerhouse and associated structures and also for
the second intermediate access adit to the power
tunnel. A second camp for workers employed on
the upstream heading of the power tunnel, intake
works and headings driven from the first
intermediate access adit to the power tunnel
would be located east of the Barrier Glacier.
o The construction camps would be self-contained
with all needed support facilities which would
include water supply sewage treatment, solid
waste disposal, catering and medical services.
o Electrical power during construction is provided
for on the assumption that diesel driven
equipment would be used.
o Major compressed air facilities would be required
for the excavation work and their cost is
provided for in the estimates •.
o Camps needed to accommodate transmission line
workers would be light weight "fly camps". Much
of the line work would be undertaken in winter
and would be avoided during waterfowl nesting
periods.
As construction work approaches completion, all
temporary facilities will be dismantled and removed
from the site, which will be restored insofar as is
8-15
possible to its original condition, and the cost of
such demobilization and site restoration is included
in the estimates.
8.2 Exclusions from Estimates
8.3
The estimates of construction costs do not include
provision for the costs of the following items:
o Owner's administrative costs.
o Financing charges.
b Escalation (Estimated costs are "overnight costs"
at January 1982 price levels.
o Land and Land Rights.
o Water Rights.
o Permits, licenses and fees.
o Switchyard at the Anchorage transmission line
terminal.
Construction Schedules
Typical construction schedules are shown on Figure 8-2
for Alternatives A and B, on Figure 8-3 for Alterna-
tives C and D, and on Figure 8-4 for Alternative E.
These schedules have as their beginnings the existing
schedule for completion of the project feasibility
study and preparation of the application to the
Federal Energy Regulatory Commission (FERC) for a
license to construct the project.
8-16
r
[
r-
f-=
L
["
[
[
l
L
L
r·
L
L
1983 1984
DESCRIPTION
ENGINEERING
Feasibility Study
FERC License
Exploration Program -Pioneer Road I
Intake Exploration Program I
Engineering Design
PROCUREMENT-TURBINE/GENERATOR
CONSTRUCTION I
Mobiliza·::ion and Wate~ /Sewage Plant --
Trading Bay Port and Facilities
Airstrip
Access Roads & Camps-Intake
Access Roads & Camps-Downstream Tunr~~! I
-·---· --··-·------.. -·~:,..-:~-
Access Roads & Camps-Powerhouse
Access Tunnels -Intake
Access Tunnels-Downstream
Access Tunnels-Powerhouse
~
Power Tunnel -Excavation
Power T.unnel -Concrete
~
Upper Surge Chamber
Intake Gate Shaft .
Intake Tunnel and Lake Tap
Powerhouse Complex
Lower Surge Chamber
Penstock and Manifold
Tailrace Tunnel Top Heading & Bench
Tailrace Canal
River Training Works
Switchyard
Transmission Line
Demobilization and Site Restoration
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT SCHEDULE
ALTERNATIVES A AND 8
1985 1986 1987 1988
-
!
I ---' --I
·I :N ~J. b~I:J EM
[I
'+ !....; ·;..;; el ~ ~-.. .. lllii I i
I I I ! I -I .l
f'T
1 I
i I
!_1 1'\. __ . ..J I ·-
' I,..._
IF I
r i t--)
~
ll' I
-I I
I
1
--r-. ,i
I
1::. ~l IV
-~ -
-1-------!---
-
1989 1990 ! 1991 1992 1993 1994
I
I I
i I -~ -r--H 1-~ 1-
I I
!EI ~s R M'."i -.JitJG I i I .
I 1
' I I I ' !
T
f
I t ~ f
I ! lj
I I
I .
j_ I I i I
I I I I .. I I I
I
. I
I
I • ]
I lA .l[U 'Ill_ ;:::,_ ur L Ni
'fl" -I 'f' [/
HO' ~( Rt it A~ ~'f. ~ AI I Jl" /
--
~ --~ ---~ ~ --
--
~ !-----~ :--~ i-
FIGURE 8-2
I
1
I
1
DESCRIPTION
ENGINEERING
Feasibility Study
FERC License
Exploration Program-Pioneer Road
Intake Exploration Prograrr.
Engineering Design
PROCUREMENT-TURBINE/GENERATOR
CONSTRUCTION
Mobilization and Water/Sewage Plant
Trading Bay Port and Facilities
Airstrip -
Access Roads & Camps-Intake & P.H.
Accec;s Tunnels-lntak~ ---------·--
Access Tunnels-Mile 3.5
Access Tunnels -Mile 7.5
Access Tunnels-Downstream
Access Tunnels -Powerhouse
Power Tunnel--" Excavate
Power Tunnel-Concrete
Upper Surge Chamber
Intake Gate Shaft
Intake Tunnel & Lake Tap
Powerhouse Complex
Lower Surge Chamber
Penstock and Manifold
Tailrace Tunnel Top Heading & Bench
Tailrace Canal
River Training Works
Switchyard
Transmission Line
-~
Demobilization & Site Restoration
1983
..
.
I
I
I I
!
'·
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT SCHEDULE
ALTERNATIVES C AND D
1984 1985 1986 1987
'
~
I
H3F. F~B E V1E
v
I
I
I ~t ,...., ~ l
~ ~
I
l . .:; !.J . I i\ r-.·
I I I I I I I
i ! r-· I Ill !
'J· -I 1:1 ' I!',, i. F-i-~ I
l i 11 ,-I i
·--~ I
I . i ,. I I I [•.,_ r 1-I
I I
I I
' r : ;
I t
II E c v
i
I
.
I p... . "' l 1-1-l
1-
l
1988 1989 1990 1991 1992 1993 1994 .,-
1-~ ~ 1-1--~ ~ ~ I I
' E! PS Rl M I I.,G I I
n
' I
!oooJI! ... f-jo. I
r
I
I
I j I l
~
I
I
o;
I I I i '
l I I
I
f
~-! I I f
i
I
I I
;
l
~I L lJt\ ll ~ ( NLI N.E -.
""'
[,-1,;
:::< N IA~LS IS" LA T JP. II'
,_
~ 1-~
1-1-1-~ ,_
1-1-1-. 1-~ 1-1-
1-1-
1-. .. • 1-~ --""' -1-
FIGURE 8-3
1983
DESCRIPTION
ENGINEERING
Feasibility Study
FER C License
Exploration Program -Pioneer Road
Intake Exploration Program
Engineering Design I -
PROCUREMENT-TURBINE/GENERATOR I
CONSTRUCTION
Mobilization and Water/Sewage Plant
Trading Bay Port and Facilities
Airstrip
Access Roads & Camps-Intake I
Access Roads & Camps-Downstream Tunnel --
A:ce~ Roads & Ca.r.ps -·Po·;,~::~~~.··.: I I .
Access Tunnels-Intake
Access Tunnels-Downstream ..
Access Tunnels -Powerhouse
Fish Facilities
Chakachatna Dike and Spillway ~
Power Tunnel -Excavation
Power Tunnel -Concrete I I
Upper Surge Chamber
Intake Gate Shaft
Intake Tunnel and Lake Tap
Powerhouse Complex
Lower Surge Chamber
Penstock and Manifold
Tailrace Tunnel Top Heading & Bench
Tailrace Canal
River Training Works
Switch.yard
Transmission Line
Demobilization and Site Restoration
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT SCHEDULE
ALTERNATIVE E
1984 1985 1986 1987
\7
f
v
I I I I
I I
I I ;
' :N GF. FAB ·
I I I II
I
1:± j 1-""-· """' I. I I
I I I I
I\
! II
-~! ~ ' I I I i : : I I
I
1. I ~ -J
I I
I I
I I ! ,;
I
1988 1989 1990 1991 1992 1993 ~ 1994
I
I I
' I T
------1--~ -. ~ -
I
8M EDS RE M1 ~'-' r I~ G I
I I I I
~ i-1-. I
i '·
I I I
I I '
I I
I I
l i
I I L I !
I i I
I f I ' .
I I
I I I ; I I I
I
II
I
I
I .
I I
p Lt u Nl 10 N .I 1\ It::
I ,
; I 1 ~ I \17
" :> c~ v c )I\ CF E E ~s y s "A R u v
~
I
.... """ -
i----. .... ---~
-~ """'! ------
-...
.... .... ---• ...... -
FIGURE 8-4·
The assumption has been made that the license
application would be submitted to FERC March 1, 1984.
Assuming also that the FERC licensing process
continues in much the same manner as it does at the
present time, an early step will be the preparation of
an environmental assessment of the project by FERC
staff. This generally takes about 12 months following
which is a 60-day period for review and comment by
interested agencies. Thus, by the end of April, 1985,
it should have become clear whether there are any
outstanding unresolved issues. If there are not, then
it would be possible to forecast with reasonable
certainty that the FERC license would be issued in
early 1986, in which event there would not appear to
be any reason why the construction of access
facilities and camp installations could not commence
by June 1, 1985. In order to provide adequate lead
time to commence design and prepare plans and
specifications for the construction of access
facilities, design engineering of the project would
need to commence at the beginning of 1985.
Noting that there is a possibility that FERC might
also require completion of an exploratory adit and
rock testing program at the powerhouse site before
issuing the project license, June 1, 1984 would appear
to be a logical time to commence that program. Making
an early start in the manner described above would
permit the plant to commence commercial operation a
year earlier than if the design of the project and
construction of infrastructure did not commence until
after the FERC license had been issued.
Construction of the power tunnel lies on the critical
path for completion of development via the McArthur
River in Alternatives A, B, and E. For conventional
excavation methods assumed for Alternatives A and B
the schedule was based on tunnel excavation
advancement at an average rate of 26 feet per day in
each heading. At that rate, excavation would be
completed in approximately 3-1/2 years.
For excavation by boring machine assumed for
Alternative E the schedule was based on net
advancement of 50 feet per day from one heading at
which rate the excavation would be completed in
approximately the same time.
Placement of the concrete lining would proceed
generally concurrently with the excavation. Total
construction time for the tunnel is thus 50 months and
the first unit in the powerhouse could be started up
by August 1, 1991.
As discussed above a saving in time might be effected
if any sections of the tunnel can be left unlined as a
result of smoother boring machine excavation and
reduction of rock shattering.
For development via the Chakachatna River in
Alternatives C and D, the ability to provide two
intermediate construction access adits enables the
tunnel construction to be completed within 32 months,
or 18 months less than for the McArthur tunnel.
Timely delivery of the turbines and generators, and
construction of the powerhouse complex becomes more
critical. Assuming an early start on site access and
8-24
l
L
l
L
L
r
L
,_"
L
['
development as described above for Alternatives A and
B, the first unit in Alternatives C and D could be
started up by February 1, 1990, or 18 months earlier
than would be the case with Alternatives A, B and E.
R-?1:\
ECONOMIC EVALUATION
,~~
l
l
r
l' ~
I
f
r~
1 ~
L
t
L
r
t
L
l
L
L
[
9.0
9.1
ECONOMIC EVALUATION
General
During the initial project studies carried out in 1981,
an evaluation was made of the economic tunnel diameter
and economic tunnel length for the four basic alternative
schemes developed at that time, Alternatives A, B, C & D
(described in Section 3). This economic study was made
using tunnel costs calculated for tunnel excavation by
conventional drill and shoot methods. Subsequent studies
performed in 1982 indicated that cost savings will be
achieved if the tunnel would be driven by tunnel-boring
machine. Alternative E is based on tunnel boring machine
excavation. These studies are discussed in Section 8.
No re-examination of the economic tunnel diameter or
length has been made using these modified tunnel costs,
but any change in economic diameter or length of tunnel
is considered to be small.
Determination of the economic tunnel diameter involves
comparing the construction costs of tunnels of varying
diameters, with the present worth of the difference in
power produced over the life of the project as a result
of the changes in hydraulic loss in the tunnel as the
diameter is varied. The economic tunnel length is
determined from an economic balance between the cost of
increasing the tunnel length to develop additional head
on the powerhouse, and the present worth of the additional
power produced by the higher head over the life of the
project.
It should be noted that these economic evaluation studies
were based on economic parameters prevailing in 1981.
These parameters which include capital costs of thermal
generating plants and fuel costs for both coal and
natural gas have, of course, now been superseded. In
9-1
9.2
9.3
9.3.1
future studies, the influence of updated economic
parameters on the economic tunnel diameter and length
should be made.
Parameters for Economic Evaluation
Alaska Power Authority has developed the following
parameters for economic analyses of hydroelectric
projects.
Inflation Rate
Real Discount Rate
Economic Life of Hydroelectric Projects
Economic life of thermal plants
(conventional coal fired or
combined cycle)
0%
3%
50 years
30 years
In sizing the various project elements, i.e., tunnel
diameter and length, the value of power generated by the
hydroelectric project has been considered equal to the
cost of the equivalent power generated thermally by coal
fired plant or by natural gas fired combined cycle plant.
As agreed with APA, in order to arrive at a project cost
which can be readily compared with that for the Susitna
Project a 50% plant factor has been used for determining
the installed capacity of the power plants discussed in
this report. Future studies should copcentrate on
refining the preferred plant factor for the project.
Cost of Power from Alternative Sources
General
To ensure uniformity of data between the various
feasibility studies of hydroelectric projects which are
currently in progress, including the Susitna
Hydroelectric Project, APA requested that the following
9-2
r-
\
I
i
l
l
f .
f
l
} -
!-
' l
I
k
I
(
L
L
9.3.2
sources be used for the development of cost of power from
alternative thermal generation:
(1) Acres American Incorporated report "Susitna
Hydroelectric Project" Task 6 Development Selection
Report, Appendices A through I, July 1981 for
construction cost of coal fired and combined cycle
thermal plants.
(2) Battelle Pacific Northwest Laboratories, for the
cost of operation and maintenance and fuel for coal
fired and combined cycle thermal plants. Data on
these items were obtained during a visit to
Battelle's office on September 1, 1981.
Construction Cost
(a) Coal fired thermal plant:
The Acres American report referred to above develops
the construction cost of a 250-MW coal fired thermal
plant at Beluga in 1980 dollars to be $439,200,000
direct construction cost and $627,650,000 total cost
including 16% contingency, 10% for construction
facilities and utilities and 12% for Engineering and
Administration, but not including interest during
construction. This total cost corresponds to
$2510/kW. Including interest during construction at
3 percent per year for a 6 year construction period,
the total cost amounts to $2706/kW. (This differs
but little from the $2744/kW value given in Table
B.l3 of the Acres Report apparently because of some
rounding of numbers in the Acres calculation and
apparently slight difference in cash flow during the
construction period.)
9-3
9.3.3
9.3.4
(b) Combined Cycle Plant
The Acres American report also develops the
construction cost of a 250-MW combined cycle plant
in 1980 dollars to be $121,830,000 direct
construction cost and $174,130,000 total cost
including 16% contingency 10% for construction
facilities and utilities and 12% for Engineering and
Administration, but not including interest during
construction. This corresponds to ·$697/kW. When
interest during construction is added at 3 percent
per year, the total cost is $707.5/kW.
Operation & Maintenance Cost
Data obtained from Battelle is summarized below for 1980
price levels.
(a) Coal-fired Thermal Plant
Fixed Operation and Maintenance $16.71/kW/year
Variable Operation and Maintenance 0.6 mills/kWh.
Escalation above general inflation rate 1.9% until
year 2012 with no escalation after 2012.
(b) Combined Cycle Plant
Fixed Operation and Maintenance $35.00/kW/year
Variable Operation and Maintenance 0 mills/kWh.
Escalation above general inflation rate 1.9% until
year 2012 with no escalation after 2012.
Fuel Cost
Data obtained from Battelle is summarized below for 1980
price levels
9-4
r
r
l
[.
r:
I
l
f {
l
L
r
L
L
[
[
r
L
~ -
L
L
(a) Coal from Beluga
Fuel cost $1.09/mill. BTU
Escalation above general inflation iate 1.5% until
year 2012 with no escalation after 2012.
Heat Rate 10,000 BTU/kWh.
(b) Natural Gas -Combined Cycle Plant
The natural gas prices as estimated by Battelle for
the future years are given in Table 9-1.
Heat rate 7500 BTU/kWh.
TABLE 9-1
NEW CONTRACT GAS PRICE (AML&P)-ANCHORAGE
Year Gas Price
$/Mill BTU
1980 1.08
1981 1.08
1982 1.09
1983 1.09
1984 1. 09
1985 1. 09
1986 1.35
1987 1. 56
1988 1.65
1989 1.89
1990 2.11
1991 3.62
9-5
9.4
1992
1993
1994
1995
3.74
3.86
3.98
4.11
Forecast escalation after 1995 = 3% per year until the
year 2012, and no escalation thereafter.
Value of Hydro Generation
The value of the hydro generation is established by
determining the cost of generating power from alternative
sources. For the purpose of this study an analysis has
been made of the cost of alternative coal-fired and
combined cycle genera~ion, using the basic cost data
presented previously in Section 9.3.
The annual cost of interest, depreciation and insurance
for the alternative thermal plants were calculated on the
following basis:
Interest
Depreciation (30 year life)
Insurance
Annual Charge on
Capital Cost
3.0%
2.1%
0.25%
5.35%
Based on an arbitrary selection of 1990 as the in-service
date for the Chakachamna Project and examining a fifty
year period, equal to the economic life of the hydro
plant, and using the unit costs for thermal generation
discussed above, comparative costs were prepared for each
year of the 50 year period of the cost of generating
power at 50% load factor by each of the two alternatives,
r
[
f'
l-
l
I
L
conventional thermal using Beluga coal and combined cycle ~~
L
9-6 [
r
L
[
L
["
L
r-
·-'"'
[
k
L
L
L
[ '
using gas. These annual costs over the 50 year period
were then used to determine their present worths at the
first year of generation taken as 1990. The calculations
were performed on a cost per kWh basis and are presented
in Tables 9-2 & 9-3 for the conventional coal fired and
combined cycle cases respectively.
The levelized annual cost of generation by a coal fired
plant using Beluga coal is calculated to be 55.60 mills
per kWh compared with 75.21 mills per kWh for the
combined cycle plant, based on 50% load factor
generation. The higher cost for the combined cycle plant
is due primarily to a higher initial fuel cost, a much
higher escalation on the cost of fuel, and somewhat
higher operation and maintenance cost. Taken
collectively these more than offset the much lower annual
charge on the capital cost of constructing the combined
cycle plant. The cost of power produced by the coal
fired plant was therefore adopted as the alternative for
establishing the value of hydro generation.
The capital cost of a hydro plant which gives a levelized
annual cost over the 50 year life equal to the levelized
annual cost of the coal fired thermal plant of 55.60
mills per kWh, based on 50% plant factor, and including a
credit of 5% less installed capacity required in a hydro
pl~nt because of the reduced system reserve requirements
with hydro generation, is calculated to be $6,117 per
kW. This total cost includes contingency, construction
camp facilities, engineering, and construction management
and interest during construction.
9-7
TABLE 9-2 ( Sheet 1 o f 2 )
COAL FIRED PLANT
COST OF GENERATING POWER AT 50% LOAD FACTOR
Amortization Present
Year & Insurance O&M Fuel Total Worth
1 33.02 5.32 12.65 50.99 49.50
2 33.02 5.42 12.84 51.28 48.34
3 33.02 5.52 13.03 51.57 47.19
4 33.02 5.63 13.23 51.88 46.09
5 33.02 5.74 13.43 52.19 45.02
6 33.02 5.84 13.63 52.49 43.96
7 33.02 5.96 13.83 52.81 42.94
8 33.02 6.07 14.04 53.13 41.94
9 33.02 6.18 14.25 53.45 40.96
10 33.02 6.30 14.46 53.78 40.02
11 33.02 6.42 14.68 54.12 3 9 .1'0
12 33.02 6.54 14.90 54.46 38.20
13 33.02 6.67 15.12 54.81 37.32
14 33.02 6.79 15.35 55.16 36.47
15 33.02 6.92 15.58 55.52 35.64
16 33.02 7.06 15.82 55.90 34.84
17 33.02 7.19 16.05 56.26 34.04
18 33.02 7.33 16.29 56.64 33.27
19 33.02 7.47 16.54 57.03 32.52
20 33.02 7.61 16.79 57.4 2 31.79
21 33.02 7.75 17.04 57.81 31.08
22 33.02 7.90 17.29 58.21 30.38
23 33.02 7.90 17.29 58.21 29.49
24 33.02 7.90 17.29 58.21 28.64
25 33.02 7.90 17.29 58.21 27.80
946.54
NOTE: Escalation rates above the general escalation rate are as
follows.
Amortization & Insurance -Nil.
Operation & Maintenance -1.9% for first 22 years only.
Fuel -1.5% for first 22 years only.
9-8
r ,
l
r
1
r
I
L
f
l_
L
L
L
r~
{ .
l '
L
[
~
[
r.
L c
l
L
TABLE 9-2 (Sheet 2 of 2)
COAL FIRED PLANT
COST OF GENERATING POWER AT 50% LOAD FACTOR
Amortization
Year & Insurance O&M Fuel Total·
Fwd.
26 33.02 7.90 17.29 58.21
27 33.02 7.90 17.29 58.21
28 33.02 7.90 17.29 58.21
29 33.02 7.90 17.29 58.21
30 33.02 7.90 17.29 58.21
31 33.02 7.90 17.29 58.21
32 33.02 7. 9 0 17.29 58.21
33 33.02 7.90 17.29 58.21
34 33.02 7. 9 0 17.29 58.21
35 33.02 7.90 17.29 58.21
36 33.02 7. 9 0 17.29 58.21
37 33.02 7.90 17.29 58.21
38 33.02 7. 9 0 17.29 58.21
39 33.02 7. 9 0 17.29 58.21
40 33.02 7.90 17.29 58.21
41 33.02 7.90 17.29 58.21
42 33.02 7.90 17.29 58.21
43 33.02 7.90 17.29 58.21
44 33.02 7.90 17.29 58.21
45 33.02 7.90 17.29 58.21
46 33.02 7. 9 0 17.29 58.21
47 33.02 7.90 17.29 58.21
48 33.02 7.90 17.29 58.21
49 33.02 7.90 17.29 58.21
50 33.02 7.90 17.29 58.21
Equivalent Levelized Annual Cost = 55.60 mills/kWh.
9-9
Present
Worth
946.54
26.99
26.21
25.44
24.70
23.98
23.28
22.61
21.95
21.31
20.69
20.08
19.50
18.93
18.38
17.84
17.32
16.82
16.33
15.85
15.39
14.94
14.51
14.09
13.68
13.28
1430.64
r -
t
TABLE 9-3 ( Sheet 1 of 2 ) ~-
COMBINED CYCLE PLANT
COST OF GENERATING POWER AT 50% LOAD FACTOR r ,
\ I
Amortization Present
[ Year & Insurance O&M Fuel Total Worth
1 8.64 9.64 21.1 39.38 38.23
2 8.64 9.82 36.2 54.66 51.52 [ 3 8.64 10.01 37.4 56.05 51.29
4 8.64 10.20 38.6 57.44 51.03
5 8.64 10.39 39.8 58.83 50.75 l 6 8.64 10.59 41.1 60.33 50.53
7 8.64 10.79 42.33 61.76 50.22
8 8.64 11.00 43.60 63.24 49.92
r 9 8.64 11.21 44.91 64.76 49.63
10 8.64 11.42 46.26 66.32 49.35
11 8.64 11.64 47.65 67.93 49.07
12 8.64 11.86 49 •. 08 69.58 48.80
l_ 13 8.64 12.08 50.55 71.27 48.53
14 8.64 12.31 52.06 73.01 48.27
15 8.64 12.55 53.63 74.82 48.02
[ ~ 16 8.64 12.78 55.23 76.65 47.77
17 8. 6 4 13.03 56.89 78.56 47.53
18 8.64 13.28 58.60 80.52 47.30
19 8.64 13.53 60.36 82.53 47.07 r 20 8.64 13.78 62.17 84.59 46.84
21 8.64 14.05 64.03 86.72 46.62
22 8.64 14.31 65.95 88.90 46.40 l ~ 23 8.6 4 14.31 65.95 88.90 45.04
24 8.64 14.31 65.95 88.90 43.73
25 8.64 14.31 65.95 88.90 42.46
1195.92 [
NOTE: Escacalation rates above the general escalation rate are as [ -
follows.
Amortization & Insurance -Nil. r
l '
Operation & Maintenance -1.9% for first 22 years only.
f
Fuel -1.5% for first 22 years only.
f
l
f '
\ -
L
9-10 ' ' L
L
L
L
TABLE 9-3 (Sheet 2 of 2)
COMBINED CYCLE PLANT
COST OF GENERATING POWER AT 50% LOAD FACTOR
Amortization
Year & Insurance O&M Fuel Total
26 8.64 14.31 65.9 5 88.90
27 8.64 14.31 65.95 88.90
28 8.64 14.31 65.95 88.90
29 8.64 14.31 65.95 88.90
30 8.64 14.31 65.95 88.90
31 8.64 14.31 65.95 88.90
32 8.64 14.31 65.95 88.90
33 8.64 14.31 65.95 88.90
34 8.64 14.31 65.95 88.90
35 8.64 14.31 65.95 88.90
36 8.64 14.31 65.95 88.90
37 8.64 14.31 65.95 88.90
38 8.64 14.31 65.95 88.90
39 8.64 14.31 65.95 88.90
40 8.64 14.31 65.95 88.90
41 8.64 14.31 65.95 88.90
42 8.64 14.31 65.95 88.90
43 8.64 14.31 65.95 88.90
44 8.64 14.31 65.95 88.90
45 8.64 14.31 65.95 88.90
46 8.64 14.31 65.95 88.90
47 8.64 14.31 65.95 88.90
48 8.64 14.31 65.95 88.90
49 8.64 14.31 65.95 88.90
50 8.64 14.31 65.95 8 8. 90
Equivalent Levelized Annual Cost = 75.21 mills/kWh.
9-11
Present
Worth
1195.92
41.22
40.02
38.86
37.72
36.63
35.56
34.52
33.52
32.54
31.59
30.67
29.78
28.91
28.07
27.25
26.46
25.69
24.94
24.21
23.51
22.82
22.16
21.51
20.89
20.28
1935.25
9.5 Economic Tunnel Sizing
The economic diameter of the main power tunnel has been
investigated by comparing the incremental cost of varying
the tunnel diameter with the incremental value of the
difference in power produced as a result of such
variation in tunnel diameter. For the same powerhouse
flow, increasing the tunnel diameter reduces the head
losses in the tunnel thereby increasing the total head on
the powerhouse with a consequent increase in power
production.
In establishing the variation in estimated tunnel
construction cost it has been assumed that the tunnel
will be fully concrete lined with the typical horseshoe
section shown in Figure 3-2 and would be excavated by
conventional drill and shoot methods. Future studies
should evaluate the merits of a nominally unlined
tunnel. It should also be noted that when the method of
driving the tunnel by tunnel boring machine was examined
in 1982, no attempt was made to refine the economic
tunnel diameter.
For the case of Alternatives A & C with no water release
to meet instream flow requirements in the Chakachatna
River (i.e., all controlled water being diverted for
power production purposes) , Figure 9-1 shows the plot of
estimated tunnel construction cost and value of power
production with variation in tunnel diameter. This curve
shows that the economic diameter of a concrete lined
tunnel is 25 feet. In Alternative B, with the flow
diverted to a powerhouse sited on the McArthur River, but
with water reserved for instream flow requirements in the
Chakachatna River a separate study to establish the
economic diameter was not made. Instead, as an
approximation, the tunnel diameter was selected such that
9-12
t
[
L
( :
r· l
[ -
[
[
[
l
f
I
70 r--.-----~-.-------.--------~------~----~~--~
L 601---+-----+------+----+------~-------1-------l
L
l
[ ~
\\ /TOTAL COST
50 r---~7------r---_, ________ +-----1-------1---~
~
: 40 t---\~--"'---~f------+------+----t------1-------1 ~ )~
~ 30 '-----'~t: ~ '\\_ANNUAL COST -$29.29 x 10 6 ~ ~~
~ ~ J ..... --'V
20 t-------t-~!~ ~+--.---a-~--+---+-------t-------1
I ------'~ .,__--+OPTIMUM TUNNEL DIA. 25'
_.....Er-\,_TUNNEL COST ~
10 ~--+-----+------+--~~+--4---1----~-----4 ......_~~,_POWER LOSS COST
r----._
T----~-~~11"--
0 ~--~---~---~----~-~--L---~---~
17 18 20 22 24 26 28 30
TUNNEL DIAMETER -FEET
ECONOMIC TUNNEL DIAMETER
FIGURE 9-1
r'
~~
I ~
l'
I '
L
L
[
t:
[
L
L
[
k
L
r ,
h
l
L
{'
L
9.6
the velocity of flow through the tunnel with the
generating units operating at full output and at full
level at Lake Chakachamna would be the same as that
obtained under these same operating conditions in
Alternative A for which the economic diameter had been
calculated. This approximation gives a 23-foot horseshoe
tunnel.
In the case of Alternative D where only an average
release of 30 cfs flow is maintained below Chakachamna,
Lake, the 25 foot diameter tunnel was retained, since the
powerhouse flow differs by less than 1%.
In the case of Alternative E developed in 1982, based on
driving the tunnel by tunnel boring machine, a 24 foot
diameter circular tunnel was selected. This is
hydraulically equivalent to the 23 foot diameter
horseshoe shaped tunnel in Alternative B. If future
geologic studies confirm the suitability of the rock for
machine boring, the economic tunnel diameter should be
re-evaluated.
Economic Tunnel Length
For both basic alternative developments by diversion to
the McArthur River or downstream along the Chakachatna
River, an examination has been made of the economic
tunnel length. As the powerhouse is moved do_wnstream to
develop additional head, the power tunnel becomes longer
and hence more costly. The economic tunnel length is
therefore determined from an economic balance of
estimated tunnel construction cost and value of power
produced. Based on the value of the hydro generation as
discussed in Section 9.4, the present worth of the power
produced by 1 foot of head when all controlled water is
9-15
used for power generation is equal to approximately
$3,500,000 which corresponds to $139,000 annually over
the 50 year life of the plant at 3% rate of interest.
The economic balance includes consideration of the
additional estimated tunnel construction cost by
increasing the tunnel length, additional powerhouse cost
to develop the power produced from the additional head
and the value of the additional power generated by the
additional head developed. The additional head is based
on the increased gross head due to the lower tailwater
obtained by extending the tunnel less the increased
friction head loss in the longer tunnel.
Figure 9-2 and 9-3 show respectively the plots of the
economic tunnel length for the development via the
McArthur River and down the Chakachatna River. The final
selected tunnel lengths and corresponding powerhouse
locations are shown in Figures 3-2 and 3-3.
9-16
(
L
[-
r· L
r·
L
[
l
I
L.
120
100
\0
0
.-4 >< (/)-
~ 80
~
~ > ~
A
:ij
H 60 en
0
t.J
~ en
::;J
0 ga
~ 40
0 p,. -o-l
~
~
20
0
35
~I L_Li]_---'--'
-'-"
--c:;;UAL REVENUE
~
l L-j
,.
-. .J l __ ----_ __)
~ / GENERATED FROM POWER
I
/' I
$88x10 6 r_MAXIMUM ANNUAL POWER ~VENUE =
~ -\ ,.
I .... -.A::
T v \_ -NET ANNUAL REVENUE
I GENERATED FROM POWER
I q> v OPTIMUM TUNNEL LENGTH•S3,400'
/
I" ... -._, '-TUNNEL/POWERHOUSE COST ,. -,.....,
-"' ._,
40 45 so 55 60 65
TUNNEL LENGTH-FT x 1000
70
-
75
McARTHUR TUNNEL
ECONOMIC LENGTH
FIGURE 9-2
-----,
J
120
~
100
"' 0
..-4 >< 0
~ 80
~
~
~
f-4
Ul 60 ·o u
~
Ul ·5
~
~ 40
p., -...:I
v ..--
ANNUAL REVENUE
GENERATED FROM POWER-\ ~
~ ~ OPriMIZAriON Npr POSSIBLE -TUNNEL~
LENGTH LIMITED BY TOPOGRA~ AT
~ CA ~ON MOUTH .
___..E " -
NET ANNUAL REVENUE ~ GENERArED FROM~ ~
~ -
-, ._
---·--~ -~ ...... ---
20· -' \__TUNNEL/POWERHOUSE COST
0
45 50 55 60 65 70 75 80 85
CHAKACHATNA TUNNEL TUNNEL LENGTH-FT X 1000 ECONOMIC LENGTH
FIGURE 9-3
r----": r--_____.,., ("'""""' ,......._..., ,............., r----"j ~ .~ -,..-...--==-~-----=:-
COORDINATION
r ~
L
L
[
10.0
10.1
10.2
10.2.1
COORDINATION
Introduction
During the course of the project studies, coordina-
tion with various interested parties was conducted
via informal contacts, written communication, and
formal meetings in order to afford these parties an
opportunity to make their interests in the project
known and to enable the Power Authority to respond
to questions and concerns ·about various aspects of
the project. In this section of the report, copies
of correspondence and meeting notes are reproduced to
demonstrate coordination between the Power Authority
and interested agencies.
HUMAN RESOURCES
Meeting -December 10, 1981
Representatives of u.s. Bureau of Land Manangement,
National Park Service, and the Alaska State Archae-
ologist were invited to attend a meeting with repre-
sentatives of Bechtel, woodward-Clyde Consultants on
December 10, 1981. A copy of the meeting notes pre-
pared by Bechtel, Woodward-Clyde Consultants follows.
10-1
CHAKACHAMNA HYDROELECTRIC PROJECT
JOB No. 14879
MEETING NOTES
DATE: December 10, 1981
LOCATION: Business Park, Anchorage, Alaska
PARTICIPANTS:
Name
Bob Loder
David Cornman
Hike Joyce
Chuck Holmes
Dave l1obraten
Bailey Breedlove
Organization
Bechtel
Bechtel
loloodward-Clyde Consultants
Subcontractor to Woodward-Clyde Consultants
Anchorage District Office of the
Bureau of Land Management
National Park Service
John Isaacs Woodward-Clyde Consultants
SUBJECT: Human Resources Scoping Meeting.
Representatives from Bechtel Civil and Minerals and Woodward-Clyde Consultants
(WCC) presented a summary of the proposed 1982 Human Resources studies and the
results of the 1981 reconnaissance program to representatives of the Anchorage
District Office of the Bureau of Land Management (BLM) and the National Park
Service (NPS). The State Archaeologist was unable to attend the meeting.
An introduction describing the project, team organization, and potential
development schemes was provided by Bob Loder. This included conceptual
design and locations of the project alternatives. Mike Joyce presented a
general overview of the environmental program, followed by Jon Isaacs, who
discussed the 1981 Human Resources reconnaissance and the 1982 work program.
The agency representatives each had received a copy of the 1982 proposed work
plan prior to the meeting. At the conclusion of the presentations, the agency
representatives were asked to supply oral and subsequently written comments
expressing their concerns with the proposed hydropower project and the proposed
human resources work plan for 1982.
The major concerns expressed-orally at this meeting are listed below:
BLM
o mineralization of the area, and potential resource extraction
should be investigated.
o impacts on fish and wildlife resources are likely to be the
big issue; economic impacts on the Cook Inlet fishery should
be determined.
10-2
L
[-
[
[ .
L
f
L_
,,
L
L
E
[
L-
r-
b
L
L
L
NPS
o with regard to permits, it is likely that no permits for 1982
studies within the power site withdrawal will be required. Out-
side of the withdrawal, permits will be required for activities
involving significant surface disturbance, such as drilling
or road construction.
o input from Cook Inlet Region Inc. (CIRI), Tyonek Native Corpora-
tion (TNC) and the State of Alaska should be solicited.
o maps conveying land to the Native corporations and state should
be checked for road and powerline easements.
o concerning project construction and operation, waste disposal
from tunnel construction will be an issue of concern. BLM would
have no problems with road construction within the power site
boundaries.
o use of the project related roads and where they might put use
pressure are of concern, particularly in the vicinity of Chaka-
chamna Lake, where Lake Clark National Park could be affected.
o the potential drawdown of Lake Kenibuna by the project needs
to be investigated.
o interest was expressed on Mt. Spurr's influence on the project.
o potential effects to salmon runs entering Lake Clark National Park
(Kenibuna Lake) will be investigated.
o potential impacts to the project from glaciers and volcanic activity
were noted.
o situation problems similar to those anticipated on Susitna, may
occur on the Chakachamna Project.
In addition to these comments, several questions where asked about the
biological (winter fish distributions, peregrine falcon) and engineering
(tunnel construction) aspects of the project.
10-3
10.2.2
10.3
10.3.1
Response
The concerns expressed by these agencies were noted
and used for guidance in the planning and conduct of
project studies. Fish and wildlife aspects were
taken up with their respective Federal and State
Agencies. Initial contacts were made with Cook Inlet
Region, Inc. (CIRI) and Tyonek Native Corporation (TNC}.
An attempt to schedule a meeting with TNC was unsuccessful
but future meetings are planned. Contacts and a meeting
also took place with the National Park Service and the
Superintendent of Lake Clark National Park.
Biological Studies
Meeting -December 11, 1981
A meeting was convened on December 11, 1981 between
representatives of Alaska Department of Fish and Game,
National Marine Fisheries Service, u.s. Fish and Wild-
life Service and representatives of Alaska Power au-
thority, Bechtel and Woodward-Clyde Consultants. The
purpose of the meeting was to solicit and discuss
verbal comments on proposed 1982 biological studies for
the Chakacharnna Hydroelectric Project. A copy of the
meeting notes prepared by Bechtel, Woodward-Clyde is
reproduced on the following pages.
10-4
I -
l:
\
l
l-~
f-~
F
[
r~
[
r~
L
r ~
l_
l :
L
L
L
L
[
L
L
CHAKACHMNA HYDROELECTRIC PROJEC1·
JOB 14879
MEETING NOTES
DATE: December 11, 1981
LOCATION: Business Park, Anchorage, Alaska
PARTICIPANTS:
Alaska Department of Fish & Game
Carl Yanagawa
Don McKay
Ken Tarbox
Kelly Hepler
Larry Heckart
Paul Ruesch
Ron Stanek
Tom Arminski
Bechtel
David Cornman
Bob Loder
SUBJECT: Chakachamna Agency Seeping Meeting
National Marine Fisheries Service
Brad Smith
U. S. Fish and Wildlife Service
Dave Ferrel
Alaska Power Authority
Eric Marchegiani
Woodward-Clyde Consultants
Mike Joyce
Larry Rundquist
Paul Hampton
Braxton Dew
Wayne Lifton
Jon Isaacs
Representatives from Alaska Power Authority (APA), Bechtel Civil and Minerals,
and Woodward-Clyde Consultants (WCC) presented a summary of the proposed 1982
biological studies and the results of the 1981 reconnaissance efforts to repre-
sentatives from the Alaska Department of Fish and Game (ADF&G), National Marine
Fisheries Service (NMFS), and U.S. Fish and Wildlife Service (FWS). The purpose
of the meeting was to discuss and solicit verbal comments on proposed biological
studies for the 1982 Chakachamna Hydroelectric Project.
10-5
An introduction describing the project, its project team organization,
and potential development scheme was provided by Eric Marchegiani, Bob
Loder described the conceptual design and locations of the five project
alternatives and Mike Joyce introduced the environmental presentation.
The Woodward-Clyde task leaders (hydrology, aquatic, and wildlife bi-
ology) then briefly described the results of the two reconnaissance
efforts in 1981 and the proposed studies for 1982.
The agency representatives each had received a copy of the 1982 proposed
work plan prior to the meeting. At the conclusion of the presentations,
the agency representatives were asked to supply oral and subsequently
written comments expressing their concerns with the proposed hydropower
project and the proposed environmental work plan for 1982.
Che major concerns expressed orally at this meeting are listed below.
0
0
Were the five reaches selected for Instream Flow Gauging
chosen only on the basis of hydrologic information or was
fishery information also used?
Both hydrologic and fisheries data were used to select
the number and location of critical reaches.
Will one year of work be sufficient to accurately assess
the instream flow requirements?
One year should be sufficient because of the amount of
data gathered in previous hydrologic and fisheries studies
that can be compared to our data. Also, the IFG model will
be verified after the initial July data are available.
However, !f critical data deficiencies are identified, measures
will be taken to resolve such deficiencies.
o If only five critical reaches are chosen for the Instream
Flow studies, will that information be sufficient to assess
the impacts to the entire fishery?
10-6
l
L
L
0
[
[
L
0
L 0
I
b
[ 0
L
L
Because the critical reaches include the major spawning,
rearing, and migration areas, and the areas that could
potentially be influenced the most by the project, we feel
that the data gathered will provide enough information
to assess impacts. In addition, if future studies indi-
cate that more critical reaches are needed, we will consider
including them.
Will the distribution of age and size classes as well as
the intra-areal movements of juveniles and residents be
investigated?
Through the diverse nature o~ the collecting gear and the
number of sample sites, age and size class distribution
will be investigated. Local movements of residents and juve-
niles within the study area will not be directly addressed,
because data collected through other aspects of the program
(maintenance of habitats) will be sufficient to assess
project influences on local movements.
Since the winter low flow periods are a critical time of
year, will the winter studies be sufficient to evaluate the
effects of altered discharge on the fish populations?
At this time we feel that the sampling effort planned for
the winter will be sufficient to assess the effects of
altered discharge on the fish populations.
Local fisherman and the resource agencies are perhaps most concerned
about the cumulative effects of the Chakachamna and other Upper
Cook Inlet projects on commercial fisheries.
The comment was noted.
Are the Habitat Evaluation Procedures being applied and what, if
any, changes in the program are anticipated?
The Habitat Evaluation Procedures are being applied. Only two
changes are anticipated.
10-7
0
1)
2)
The change in habitat units over the life of the
project will not be calculated because the potential
effects of other nearby developments (Beluga Coal
fields, timber harvesting, and offshore oil develop-
ment) cannot be accurately assessed.
Because the models describing the habitat preferences
of the evaluation species are based on a generalized
niche concept, changes will be made, where necessary,
to make the models more applicable to the preferences
of the species in the study area.
Are the transmission line corridor and road right-of-ways
going to be investigated?
Both will be evaluated by all disciplines after the general
routes have been determined.
o Are any environmental studies planned for the marine or
intertidal zone?
The possibility of spawning, rearing, and migration areas
in the intertidal zone will be investigated. The species
composition and distribution of birds and mammals in the
intertidal zone will also be investigated. No studies are
planned at this time for the marine environment.
o What facilities are planned for the coast?
0
At this time, the only proposed development of the coast
will be a dock and an airstrip near Granite Point.
Will the results of the 1981 investigations be available
for agency review?
10-8
[ :
L_
L
k
L
L
L
L
0
0
0
In January 1982, the results of the environmental studies
as well as a complete project description will be sent
to the agencies.
Will a more detailed 1982 work plan be available that
describes the functions that will be performed by subcontrac-
tors, who the subcontractors are, and what the approximate
level of effort is for each sub-task?
A new work plan will not be prepared. However, a list of
subcontractors and their obligations will be sent to the
agencies along with a schedule of the approximate level
of effort apportioned to each sub-task.
Will an Agency Task Force approach be instigated to coordi-
nate agency input to mitigative measures?
If the agencies choose that approach, APA, Bechtel, and
Woodward-Clyde are willing to work with the Task Force.
When, where, and how many public meetings are planned?
No specific times, dates, places, or numbers have been
determined. However, due to the special interest of the
people in Soldotna, one of the meetings may be held there.
The representatives from the agencies agreed to submit further written
comments after they had reviewed the results of the 1981 investigations
and reviewed the preliminary project designs. They will each submit
comments to their supervisor and one letter from the head of each agency
will be submitted to the APA.
10-9
10.3.1.1 Response
The responses to the questions raised at the meeting
are set forth in the meeting notes preceding this
paragraph, immediately after each question.
10.3.2 Correspondence
The following pages display reproductions of corres-
pondence received from the following agencies:
o u.s. Fish and Wildlife Service,
March 5, 1982, March 26, 1982
o Alaska Department of Fish and Game,
February 18, 1982
o National Marine Fisheries Service,
February 18, 1982
This correspondence relates to the 1982 work plan which
was distributed to the agencies prior to the December
11, 1981 meeting as well asto the proposed project
development. The comments received from the fishery
agencies in these letters were taken under advisement
and as guidance in defining and executing the final 1982
work plan. The implementation of many of the agencies'
suggestions however, has had to be deferred until later
studies. Responses by the Power Authority to the letters
from the agencies immediately follow the letters from
each agency.
10-10
r -
I
r~
)
I
i •
I
[
i
I .
r
I
\.
L
[;
L
L
r
L
8
L
t
L
c
L
fi~ L
l
United States Department of the Interior
IN REPLY REFER TO:
WAES
Mr. Eric P. Yould
Executive Director
Alaska Power Authority
FISH AND WILDLIFE SERVICE
1011 E. TUDOR RD.
ANCHORAGE, ALASKA 99503
(907) 276-3800
0 5 MAR 1982
333 West 4th Avenue, Suite 31
Anchorage, Alaska 99501
Dear Mr. Yould:
Re: Chakachamna Hydroelectric Project
1982 1iork Plan, Environmental Studies
This letter transmits to the Alaska Power Authority (APA) comments and recom-
mendations of the U.S. Fish and Wildlife Service (FWS) relative to the 1982 1iork
Plan, Environmental Studies for the Chakachamna Hydroelectric Project. Our
comments are based on a review of the 1982 Work Plan in conjunction with a
review of the Chakachamna HYdroelectric Project Interim Report dated November
30, 1981, and forwarded to us on January 9, 1982, and coordination meetings
between APA, its consultant, FWS, the Alaska Department of Fish and Game
(ADF&G), the National Marine Fisheries Service (NMFS), and other interested •
parties.
The FWS appreciates the opportunity to participate in developing the biological
program for the Chakachamna Hydroelectric Feasibility Study. We feel that the
1982 Work Plan has provided an outline for some of the basic biological studies
that will be required to address the effects of the Chakachamna Hydroelectric
Project on fish and wildlife resources. We are providing comments specific to
the 1982 Work Plan to identify the information we believe is essential to
identify fish and wildlife resources of the project area, determine potential
impact of the project upon those resources, evaluate alternatives to the pro-
posed project, and formulate mitigation/enhancement measures. Our comments are
as follows:
GENERAL COMMENTS
As presently conceived, the scope of studies presented in the 1982 Work Plan
will not provide the data necessary to meet the study objectives as identified
on Page 1. Thorough interagency coordination and comprehensive planning of
biological studies is needed to insure an adequate information base for the
preparation of environmental exhibits for submittal to the Federal Energy
Regulatory Commission (FERC). Formal state/federal interagency coordination can
best be initiated by application for a FERC preliminary permit. Advantages in
applying for a preliminary permit include the early identification of all
involved agency concerns as well as establishment of a formal relationship with
10-11
Page 2
the FERC. The identification of agency concerns early in the planning process
can prevent delays in processing the application for license and preparation of
an Environmental Impact Statement (EIS). Under the FERC licensing process, the
applicant may be required to collect additional data if the environmental
exhibits are found to be inadequate by state and federal resource agencies.
To date, there has been only brief reconnaissance-level field investigations
conducted late in the 1981 field season. We understand that field studies are
scheduled to terminate in November 1982 and that, three months later, a feasi-
bility report and FERC license application are due. Considering the complexity
of the Chakachatna and McArthur River systems, the lack of basic qualitative
fishery resource data, and the magnitude of the potential impacts to these
resources which would result from hydroelectric development, the approximate ten
months allocated to field studies and three months allocated to the analysis of
the results of these studies is insufficient to adequately assess the effects
this project would have on fish and wildlife resources. The impact of this
proposed project upon both the Lake Clark National Park and the Trading Bay
State Game Refuge adds to the complexity of the assessment.
A list of literature cited should be added to the work plan to facilitate the
use of references cited.
Specific Comments
Environmental Hydrology
Regime Observations (Page 2)
We are pleased with the scope of study of this section, but question how the
regime characteristics identified on pages 3 and 4 can be adequately assessed in
a single remaining field season. As related to salmonid spawning habitat, a
more detailed discussion is needed to show how characteristics of side channels
and high water channels, tributary characteristics, and bed scour, degradation,
and aggradation within the Chakachatna and McArthur River systems will be
assessed. The timing and level of field effort to accomplish this need to be
identified. The use of aerial photographs should not be used as a substitute
for ground-level observations incorporating physical parameter measurements.
The erosion studies proposed for the lake tributaries need to be explained in
further detail.
Hydrology (Page 4)
We feel that reliable flow data is obtainable, in light of the 13 years of
record by USGS, for the Chakachatna River. We are concerned, however, that
representative flows for the McArthur River may not be. An assessment of
groundwater inflow through side channels and sloughs, again in relation to
salmonid spawning habitat, is needed. The evaluation of winter flow charac-
teristics needs expansion. The expansion should include the methodologies and
study site locations as well as an assessment of the correlation between these
sites and fish over-wintering habitat.
10-12
r ~
I
I
(
(
i
(
~:
(
l
[ :
(
r
t
L
L
L
f '
l
L
Page 3
We are concerned that the level of effort needed to assess the flow requirements
for the maintenance of the Noaukta Slough and Trading Bay wetlands will not be
met. This portion of the hydrology program needs expanson. Additionally, a
water-quality program needs to be developed and the timing and level of effort
identified.
Instream Flow Investigations (Page 5)
We have contacted the FWS Cooperative Instream Flow Group (CIFG), Ft. Collins,
Colorado, for input into this portion of the 1982 'vork Plan. Their comments,
once received, will be forwarded to you for consideration into your study
design. We are pleased that the IFG Incremental Methodology will be applied.
However, there appears to be a limited data base to support the selection of the
study sites identified in the study plan. Prior to application of the
incremental methodology, a qualitative understanding of morphologic, hydraulic,
and biologic characteristics of the two rivers must be obtained. The seasonal
distribution and habitat utilization of fish species as well as the seasonal
flow patterns and channel structure must be known before study sites can be
selected.
There are a number of anadromous and resident fish in this system. A good
qualitative understanding of relative abundance, seasonal habitat requirements
and distribution should be obtained for all key species. However, for appli-
cation of the incremental methodology, and development of habitat suitability
criteria we suggest that target species be selected in consultation with
state/federal resource agencies for detailed analysis.
We are concerned about the timing of the instream flow studies. These studies
are generally conducted in two phases. During phase I a qualitative under-
standing of the biologic, hydraulic, and morphologic characteristics of a system
is obtained. From this information a phase II study plan is formulated. The
river is subdivided into relatively homogenous segments and study sites are
selected for detailed analysis. Relationships of existing fishery resources are
reviewed and target species are selected for use in the analysis. Phase II
includes the collection of hydraulic calibration data, computer modeling of
study sites, development of habitat suitability criteria and analysis of pro-
jected effect. Since the tasks in phase II are dependent on the results of
phase I studies, we do not believe these two phases can be undertaken concur-
rently.
We refer you to An Assessment of Environmental Effects of Construction and
Operation of the Proposed Terror Lake HYdroelectric Facility, Kodiak, Alaska,
Instream Flow Studies, prepared by Arctic Environmental Information and Data
Center, University of Alaska, March 1981, as a good example of an Alaskan
application of instream flow techniques which required two full field seasons to
obtain.
Finally, there areno data to substantiate the 19% provisional reservation of the
average annual inflow to Chakachamna Lake, as presented in the Interim Report
and derived by the Montana Method, to meet the instream flow requirements for
fishery resources in the Chakachatna River. Because of the apparent importance
of side channel habitats, the Montana Method may not be appropriate for applica-
tion to the Chakachatna River. The instantaneous and seasonal flows necessary
to sustain this resource should eminate from the instream flow studies planned.
10-13
Page 4
Aquatic Biology
Macroinvertebrates (Page 7)
While the effort presented in this section is commendable, we consider the
forage studies to be of lesser priority than the fish studies. Accordingly, the
primar,y objective should be conducting adequate fish studies. The timing and
study site locations involved in the macroinvertebrate investigations should be
identified in the study plan.
Fish (Page 9)
In general, we feel that the fish studies presented in this section are ont' of
the stronger portions of the overall 1982 \vork Plan. Our major concern is ~.!J.a t
one field season will not be adequate to gather the necessar,y field data to
adequately assess species presence, composition, and distribution; spawning
habitat; migrator,y pathways; juvenile rearing habitat; and general habitat
utilization. This may be further complicated by the fact that 1982 represents
an even-year pink salmon run in Cook Inlet and returns could be substantial.
The use of hydroacoustics in identifying these parameters needs further
explanation and expansion. We suggest the possible use of radio-tagging
techniques to further identify migratory pathways and spawning habitats. The
¥WS, Fisheries Research Center, Alaska Field Station, has successfully applied
this technique in chinook salmon investigations on the Kenai River.
Additionally, the Alaska Department of Fish and Game has applied the technique
to assess chum, coho, and chinook salmon habitat in the Susitna River. It is
particularly applicable in systems where visibility is a limiting factor.
I Spawning (Page 9): It is necessary to identify the relative importance of
different types of spawning habitats throughout the Chakachatna and McArthur
Rivers and their relative contribution to the total production of the system.
We are interested in the relative importance between mainstem and side channel
habitats and an evaluation of incubation success in these habitats. We are
particularly interested in the side channel habitat in the Chakachatna River
which may be affected by reduced flows. Identification of spawning habitat in
Chakachamna and Kenibuna Lakes and their tributaries is needed.
Migration (Page 11): The assessment of migratory pathways should be focused on
those areas to be impacted by the project. It is important to identify the
relative importance of the various migratory routes. A more detailed discussion
of the sampling site locations and timing involved in this effort is needed.
Habitat Utilization (Page 12): We feel that the adequate assessment of over-
wintering habitat is critical in regard to minimum flow requirements. A
description of how and where this will be accomplished is lacking in this
section.
Community Analyses (Page 13): A further explanation of what this section will
contribute to the overall analysis of fishery resources in the Chakachatna and
McArthur River systems is needed.
Impact Assessments (Page 13): It is essential for the FERC permit application
to include a comprehensive mitigation plan developed in consideration of but not
limited to the following: 1. Developing fish pathways at the mouth of
10-14
( .
I
(
l
\
(
\
c
t
c
r
[ ..
r
(
L
f
\.
l
L
,~
l
~~
l
r
(
r·
(~
l
b
[
r
1_
b
l
[
Page 5
Chakachamna Lake to maintain outmigration and adult escapement, 2. use of
artificial spawning channels to mitigate the loss of spawning habitat, 3.
maintenance of migrational pathways to the tributaries of Chakachamna and
Kenibuna Lakes after lake drawdown, 4. mitigation for the loss of spawning
habitat along the lakeshores •.
Temperature: The 1982 Work Plan lacks completely a section on the assessment
of temperature regimes in the river and lake systems. We suggest a program be
developed to address this issue and that the impacts of altered temperature
regimes be assessed. A temperature model needs to be prepared.
Wildlife Biology (Page 14)
We are pleased that a HEP analysis is proposed. As an integral part of HEP,
we encourage you to make use of a state/federal interagency team to select
indicator species and technically assist in the application of HEP. In so
doing you will insure that the perspectives of all agencies are included in
the process, thus increasing the acceptability of the product. One indicator
species, preliminarily chosen, the tule goose, has never been found to nest in
the area. Its usefulness as an indicator species is questionable. We suggest
that the project boundary be reevaluated to encompass not only the total land
and water areas where direct impacts could occur, but where secondary impacts
due to human encroachment and construction activities resulting in wildlife
displacement are expected. Specifically, proposed construction camp sites,
access road alignments, transmission corridor alignments, proposed airstrips,
and tidewater facilities need to be assessed closely for potential impacts to
wildlife migration routes as well as loss of potentially important feeding and
cover habitat types. We would like to see a comparison, based on quantified
I habitat units, of the relative impacts ·of alternative access routes and
alternative project designs on wildlife resources.
The mapping of vegetative habitat types should cover the entire area of pro-
ject influence to a scale of 1 inch per mile. The scale should be expanded to
4 inches per mile in areas of significant alteration. We recommend this
expanded scale be used to map all riparian and wetland habitat types. We are
particularly concerned about potential impacts to the trumpeter swan popula-
tion in the project area (143 swans reported in 1980). Potential conflicts
between migration routes and transmission corridor alignments for swans and
other waterfowl species need to be identified early. Additionally, potential
impacts to nesting pairs of swans should be examined carefully.
Other important considerations include the identification of bear denning
sites and moose and caribou calving grounds which may be within the project
boundary. Particular attention should be focused on field investigatons of
riparian habitat and the extensive wetland complex of Trading Bay in regard to
the high use by wildlife these areas receive.
While the Wildlife Biology portion of the 1982 Work Plan identifies these
concerns in general, it fails to adequately describe the timing and level of
effort to be applied to comprehensively evaluate them. Additionally, we are
concerned about the disposal site location for talus material from power
tunnel excavation and the location of a barge facility in the tidelands of
Trading Bay. Alternative locations for these project features need to be
identified and relative impacts assessed.
10-15
Page 6
Endangered Species
As required by the Endangered Species Act (87 Stat. 884, as amended), the
FERC, or their designee, should formally request a list of threatened or
endangered species from this agency. If the list indicates that these species
are present in the project area, FERC is required under Section 7(c) to con-
duct a Biological Assessment. This assessment would identify any listed or
proposed threatened or endangered species and discuss potential project
related impacts. The assessment is to be completed within 180 days after
receipt of the official list, unless a time extension is mutually agreed
upon. No contract for physical construction may be entered into and no
physical construction may begin until the Biological Assessment is completed.
If the conclusions drawn from the Biological Assessment indicate that endan-
gered or threatened species are likely to be affected by the construction
project, FERC is required by Section ?(a) to request formal consultation.
Conclusion and Recommendations
The results of the 1982 field investigations will provide some of the baseline
data necessary for impact assessment. We feel this data will be qualitative
in nature with refinement possible only after additional study and analysis.
The compressed time-frame of the feasibility study as currently proposed,
however, does not allow such analysis. To date, there has been little effort
given to the development of impact assessment and mitigation strategies. As
planning and studies continue, we feel a more comprehensive and formal coor-
dination process should be established and implemented between APA, the con-
sultant, and the resource agencies. Also, there has yet to be developed a
forum for public input. It is obvious that there has not been adequate time
allocated for environmental studies to be conducted which are comensurate with
the magnitude and complexity of the potential impacts associated with the
Chakachamna Hydroelectric Project.
Accordingly, we recommend:
1. That an Interagency Task Force be established in order to technically
assist in the terrestrial habitat and instream flow analyses,
coordinate and review the results of further environmental studies,
assess impacts, and formulate mitigation proposals;
2.
5
that the APA apply for a FERC prelimina~ permit to initiate formal
interagency coordination;
that the time-frame for the scope of the environmental studies
associated with the feasibility study be expanded and that the 1982
field season be utilized to collect adequate qualitative baseline
biological data of sufficient scope;
that a revised Work Plan for environmental studies, based on the
expanded time-frame, be formulated and reviewed by the Interagency
Task Force;
that appropriate procedures be developed for coordination between
resource agencies and the APA to include coordination meetings with
sufficient lead time to allow for information exchange and project
review; and
10-16
~
I
(
{ j
\ .
~··
r
l'
(,
!
(
"--?-'
L
(
L
c
r
l
r ~-
u
t
~
l.
l
[!
Page 7
6. that a forum for meaningful public input be established.
Finally, we can see no advantage in presenting an application to FERC, which
will be reviewed by FWS, that does not contain an adequate assessment of
project impacts to fish and wildlife resources and a comprehensive mitigation
plan. Submission of environmental exhibits under such a compressed time-frame
can only hinder the designing of an environmentally sound project.
Accordingly, the FWS recommends the license application be delayed until
sufficient biological data are available.
We look forward to continuing to work closely with the APA in the future to
develop and implement a mutually acceptable feasibility study. We encourage
your consultants to now contact our Western Alaska Ecological Services Field
Office for technical assistance in planning for the application of HEP and
Instream Flow methodology.
cc: FWS-ROES, WAES, CIFG
ADF&G, NMFS, EPA, ELM, USGS, NPS,
ADEC, ADNR
Mike Joyce, Woodward-Clyde
FERC, Washington, D.c.
10-17
United States Department of the Interior
IN RE?L Y REFER TO:
WAES
Mr. Eric Yould,
Executive Director
Alaska Power Authority
334 W. 4th Avenue
Anchorage, Alaska 99501
FISH AND WILDLIFE SERVICE
Western Alaska Ecological Services
733 W. 4th Avenue, Suite 101
Anchorage, Alaska 99501
(907) 271-4575
c 'r r -c-'
Re: Chakachamna Hydroelectric Project,
1982 Work Plan, Environnfental
Studies
Dear Mr. Yould:
This letter transmits to the Alaska Power Authority (APA) comments and recom-
mendations of the U.S. Fish and Wildlife Service (FWS) Instream Flow and
Aquatic Systems Group, Fort Collins, Colorado, relative to the 1982 Work Plan,
Environmental Studies for the Chakachamna Hydroelectric Project. Previous FWS
comments relative to the 1982 Work Plan, Environmental Studies, were forwa,rded
to you on March 5, 1982. The enclosed comments are specific to the instream
flow and hydrologic aspects of the 1982 Work Plan.
I
We look forward to continuing to work closely with the APA in the future to
develop and implement a mutually acceptable feasibility study. We encourage
your consultants to contact our Western Alaska Ecological Services Field
Office for technical assistance in planning for the application of Instream
Flow methodology for this project.
Enclosure
cc: FWS-ROES, WAES, CIFG
ADF&G, NMFS, EPA, BLM, USGS, NPS
Mike Joyce-Woodward-Clyde
FERC-WDC
Sincerely,
Field Supervisor
1e-1s
/ '
I
(
r
\_ -
J
\
I
(_
\_
[-
(
\
\
L
J,
\.
J
[
f '
\ ' ..
-
f
\ I
L
1
f -
t.
L
United States l)epartment of the Interior
FISH ANil \Vll.lll.IFE SERVICE
OFFICE OF BIOLOGICAL SERVICES
Western Energy & Land U~e Team
Drake Creekside Building
262 5 Redwing Road
Fori Collins, Colorado 805 26
Instream Flow and Aquatic Systems Group
March 12, 1982
Mr. Dave Ferrell
Western Alaska Ecological Services
733 W. 4th Avenue, Suite 101
Anchorage, AK 99501
Dear Mr. Ferrell:
IFG 206
As per your letter of February 1, 1982 and your phone conversations with
Clair Stalnaker, I have reviewed the Interim Report on Chakachamna
Hydroelectric Project and the work plan for the environmental studies.
My initial reaction is that there is not enough information in the
environmental work plan on which to base any comments. For instance,
there is no information on water temperature aspects in the interim
report and no mention of water temperature in the environmental work
plan. I will return to the work plan later.
first, let us look at the interim report; the purpose of the report was
to provide a preliminary evaluation of the proposed project. Consequently,
all elements of the proposed project could change before construction.
The Tennett (Montana) method was used to obtain some idea of the instream
flows which are needed in the various streams. It is interesting that
the Bechtel staff have assumed rivers of the northern great plains are
representative of glacial rivers in Alaska. It is not inappropriate to
use a technique that uses a fraction of the natural flow in the stream
as an initial estimation of the instream flow needs. The fraction
should be developed for similar geomorphology and biological conditions.
In the case of the Chakacharnna project; data fnr co~stal 0rcgon, Was!Jington,
;tttd llr ( L.lr:lt Colultl(d 11, ll!t Wl'l.l 1111 Al1wku, could ltitVl' l>et·ll \l!ll'd l() dl've I <•!'
the hydrograph multipliers to estimate the instrenm flow needs.
If it is assumed all the information available about the fisheries
aspect of the project area are covered in the report, then there is a
major lack of basic data on the existing conditions which, in my opinion,
10-19
makes it difficult to develop .:1 \o.•ork plan for environmental studies. /\t
this point, I can only outline a few of my major concerns; these arc
1. There appears to be no element in the \.Jork plan to study the
streams above the lake -they should be studied.
2. The channel streams flowing into the lake are likely to change
as a result of lowering the lake level -this aspect is very
important and must be studied.
3. T~mperaLu~e as~e~Ls shou:d be studied.
4. The Chakachatna river channels do~~stream of the lake and the
McArthur river channels are almost certain to change as a
result of the project; an engineering study is required.
5.
6.
What habitat criteria are to be used to relate the fish species
to the physical habitat; are new criteria data to be collected?
It is difficult for me to comment on the site selection
because of the lack of information but the proposed sites do
not include the channels below Noaukta Slough. I suspect the
proposed project will have an impact on the channels below
Noaukta Slough.
I would like to know just what "community analysis" is as described on
page 13 of the work plan and how it fits in with other elements of the
work plan.
If I were doing the project planning, I would consider ~electing only a
few sites this year for instream flow studies and spend most of the
effort obtaining a clear picture of the system. The following year
would be used for the more detailed studies. This way I would soon have
information on the instream flow needs on which to base future planning
studies and have the type of information needed for the final analysis
some time later.
I hope these comments are of use to usc -unfortunately I can do little
more because of the lack of information in the environmental work plan.
Sincerely,
Robert Hilhous
Hydrologist
10-20
(
l
I
\
I
(
\
f'
[
l l
r
[
c
f
c
L
B
L
[
L\
{_;
L
L
r
L
ALASKA POWER AUTHORITY
334 WEST 5th AVENUE· ANCHORAGE, ALASKA 99501
RECEIVED
DEC 2 1982
R. T. LODER
Mr. Keith Schreiner
Regional Director·
U.S. Fish & Wildlife Services
1011 East Tudor Road
Anchorage, Alaska ~503
Dear Mr. y?rJfn~~:
November 26, 1982
Phone: (907) 277-7641
(907) 276-0001
Please reference your agency's letter of March 5, 1982, concerning
Chakachamna Hydroelectric Project 1982 Work Plan, Environmental Studies.
The Alaska Power Authority appreciates the detailed comments your agency
has provided, but due to severe budget restraints we have not yet been
able to implement most of those. The Power Authority through our
consultant, Bechtel/Woodward-Clyde, has collected fishery data during
this past summer and fall. Your agency personnel visited the proposed
project area while Woodward-Clyde was actually collecting this data
during August 1982.
We would like to invite you and your staff to a meeting at 9:30
A.M. on December 9, 1982, in the new Federal Building, National Weather
Service, 5th floor, East Conference Room. The purpose of the meeting
will be to present information collected during the summer and fall and
answer questions on an informal basis concerning the resource in the
area. I have attached an agenda for the meeting.
We have requested additional funding for the FY 84 budget year in
order to complete the feasibility study. Once legislative approval has
been acquired, a new work plan for environmental studies will be
developed taking into account concerns previously expressed by your
agency and others. It is our intent to coordinate this plan with the
concerned agencies.
Thank you for your continued participation in our planning
activities.
cc: .Robert.Loder, Bechtel
Wayne Lifton, Woodward-Clyde
Kenneth Plumb, FERC
z:·.ly~
Eric P. Yould
Executive Director
Gary Stackhouse, U.S. Fish & ~Jildlife Service
Lenny Carin, U.S. Fish & Wildlife Service
Attachment: Agenda 10-21
I
ATTACHMENT A
TENTATIVE AGENDA FOR DECEMBER 9 MEETING
Chakachamna Hydroelectric Project
I. Opening Remarks Eric Marchegiani
Purpose of Meeting:
Provide Background to New Personnel
To Receive Agency Input
To Keep Agencies Informed
II. Description of Project Eric Marchegiani/Bob Loder
Engineering Studies to Date
Fish Passage Facility Concepts
III. Environmental Studies Wayne Lifton
FY 1982
FY 1983 -scope, general objectives
Hydrology L. Rundquist
Aquatic Biology Wayne Lifton
10-22
r
\
J
\ .
f~
L
L
r~
X, •
~r
r~
r
r /
f
L
t:·
L
[
L.
~-
L
1-
0,·
L
[
L
L
DEP.-\RT:'tiE~T OF FISH .-\~D G:\llt:
February 18, 1982 .
Alaska Power Authority
334 W. 5th Avenue
Anchorage, Alaska 99501
OFFICE OF THE COMMISSIONER
Attention: Mr. Eric P. Yould, Executive Director
Gentlemen:
JAYS. HAM MONO, GOVERNOR
P.O. BOX 3·2000
JUNEAU, .AJ-.A$KA41 ~~802
PHONE: '1-b!:>-UU
f\J .. A..~ 1 1982
'AJ:}SXA POWER AUTHORrTY
Re: 1982 Chakachamna Hydroelectric Project Study Plan Review, Interim Report
Engineering and Geological Studies (November 1981), Woodward-Clyde
Environmental Study Work Plan (December 1981)
The Alaska Department of Fish and Game has reviewed the proposed 1982 Chakachamna
Hydro Study Plan and submits the fo 11 owing corrments:
1982 Environmental Study Work Plan
We are concerned that the remaining one year of study may prove to be
insufficient as very little is currently known about the fish and wildlife
resources within the project area. In addition, the study plan does not specify
the effort devoted to each task or expected sequence of events and from all
appearances the 1982 effort looks to be an overly ambitious undertaking. As we
have said in the past, we are willing to provide specific direction towards
development of studies if you desire our assistance. Please find comments
specific to portions of the 1982 Study Plan enclosed.
In addition, please feel free to contact us if you have any questions or
corrments.
Sincerely,
cc: c. Yanagawa R. Logan
R. Andrews A. Kingsbury
R. Redick s. Eide
L. Trasky D. Daisy s. Pennoyer R. Roys
R. Somerville J. Fall
10-23
1 1982
ALASKA POWER AUTHORilY
10.1 Engineering Studies
Para. 1
Engineering studies should also address development of structures to
reduce or eliminate fish entrainment in the power tunnel or turbines.
If' elevated thermal regimes are anticipated, multilevel intakes for
both water diverted for generation and that to provide instream flows
should be considered.
10.1.1 Hydrological Studies
Para. 1
In addition to synthesizing Chakachamna Lake outflow data, we believe
it necessary to determine the percentage of flow in the Chakachatna
system contributed from tributary streams, wetlands, and groundwater
with respect to specific stream reaches. This will reveal the
significance of lake outflow regulation in reaches where lowered flows
may limit habitat. It would be wise to analyze the McArthur system in
much the same manner but with respect to augmented flows. Flow
augmentation may result in morphological changes, changes in habitat
suitability and possible thermal effects.
Para. 2
10-2 4
r~
\
r
I
\
't
f \ :
r
r
L
r
t,_
{
1
L
1
r l ~
r'~ ·
L
r
r
L
l
t'
[.
[
L
,~
t
r~ • r
L-
L
r~
b
L
[
L
In addition to making predictions with respect to Chakachamna Lake
thermal regimes, it will also be necessary to predict changes in
thermal regimes (which would affect salmonid incubation rates) in both
McArthur River and Chakachatna River. Both systems have reaches in
which spawning occurs that will be affected by lake releases or power
diversions. We suggest that recording thermographs be placed in stream
reaches where spawning might be impacted. This information along with
Chakachamna Lake thermal modeling, meteorological data, and
hydrological data can be used in a predictive stream thermal model.
10.1.3 Reservoir and Fish Passage Facilities
Para. 1
In addition to passing fish in and out of Chakachamna Lake, provisions
must be developed to allow fish to migrate in and out of tributaries to
the lake. It appears that during operation, the lake water surface
elevation will never reach currently existing levels and may drop in
excess of one hundred feet below existing levels. This will
effectively isolate tributaries with respect to fish migrations.
10.1.4 Power Intake and Tunnel
Para. 1
Consideration should be given to design these features to prevent
entrainment of fish.
10-2 5
10.1.5 Underground Powerhouse Complex
Para. 1
Since the tailrace discharge will be located in an identified spawning
area, it should be designed to prevent habitat degradation. It may
even be possible to design this feature to increase the quantity of
spawning habitat available and help to offset habitat losses elsewhere.
10.1.6 Transmission Line and Submarine Cable Crossing
Para. 1
Alignment selection and construction logistics should be coordinated
with the environmental effort to determine the least detrimental
alternative.
10.1.7 Access Roads and Construction Facilities
Para. 1
Campsite selection, road alignments selection, and construction should
' be coordinated with the environmental effort to determine the least
detrimental alternatives.
10.1.8 Cost Estimates and Construction Schedule
10-2 6
t
r-
\
)
\
I
l
.f.
r
L
r
\ \
1
\
t•
t
{
L
l
\._.
['
[
[:
( I, .
\ ..
Para. 1
Construction scheduling should strive to minimize environmental impacts
by avoiding disturbances to fish and wildlife during sensitive periods
(spawning, calving, etc.).
1982 Work Plan -Environmental Studies, Woodward-Clyde Consultants,
December 8, 1982.
ENVIRONMENTAL HYDROLOGY
Regime Observations
Para. 1
Will these regime observations ultimately re~ult in a detailed
predicti6n of potential morphological and sedimentation changes arrived
at through modeling or will predictions be subjective in nature?
Hydrology
Para. 1
What is the rationale for those locations? Have they been chosen with
respect to influx· of tributary waters, channel configuration, fish
habitat, etc.?
10-2 7
Will the gauges be operational for more than one year (1982) or at
least one water year?
Will synthetic data be developed for these gages whose period of record
equals that used to determine generating capacity, reservoir operation,
etc.?
Para. 3
Will any attempt be made to quantitatively assess the significance of
the selected wetlands?
In addition to the above questions, we are concerned that hydrological
studies of the scope necessary to provide an adequate assessment of
hydrologic-hydraulic impacts cannot be completed during the 1982
season. We assume that the gauge network has.not been installed at
this time nor have transects been located or surveyed. If these tasks
are accomplished this spring and summer, the studies will have to be
extended till at least summer 1983 to get one water year of data and
that is a very minimal amount.
Instream Flow Investigations
Para. 1
Are the five study sites considered representative or critical reaches?
It is our understanding that the critical reach approach should be
10-2~
f~
J
\
r
I .
t
I .
1 \~.
('
t
l
c
f:
r~
L
r
G
[
[
t
t
l
L
L
L'
applied to reaches whose physicgl or chemical characteristics limit the
fishery resource. With the current knowledge we have of these systems,
. we suspect that the sites should be treated as representative reaches
with the possible exception of Chakachatna Canyon which could be a
limiting' factor with respect to migrations.
Para. 3
With respect to the location of the transects, it is our understanding
that two considerations are paramount: 1) a rigid channel; and 2)
biological pertinency. Changes in channel shape and whether the
location is at a hydraulic control are secondary considerations.
In addition, it would be advantageous to have a resource interagency
team review transect selection.
Office Analysis
Will the bed and bank erosion analysis of the McArthur River be a
subjective effort or will it involve use of a sediment transport model.
The analysis should be applied to Chakachatna River also. Operation of
the project will attenuate peak events which probably move great
amounts of sediment through the system. Without these events, there
may be significant morphological changes.
~Jith respect to the instream flow investigations, although not
specified in the study plan, we assume that the IFG-3 model will be
10-2.9 ..
used to determine weighted usable area (WUA) once habitat suitability
curves have been developed.
AQUATIC BIOLOGY
Macroinvertebrates
How will impacts to macroinvertebrates be predicted?
Fish
Para. 1
Will this characterization and quantification of habitat effort be
coincident with the instream flow effort?
Spawning
Para. 1
If spawning areas have yet conclusively identified, might it not be
premature to have already selected IFG methodology study sites which
are to be representative of spawning areas?
Pertaining to the statement that hydro-acoustic techniques will be
tested to estimate spawning density, if this technique proves
10-30-
f~
l
r·
\
J '
\-:
L
J
\.-
l"-·
. r
r
r
~~
('
[~
[/
r·
[,
E,
[.
r~
t
r f
c
L
r.
L
successful, will a full scale program be started? What will the
program involve and who will be contracted to conduct it?
Para. 9
We believe that recording thermographs would be installed in selected
spawning areas to provide additional data needed to determine if
detrimental thermal impacts will result. Temperature probes should be
installed to record temperatures of both surface and intragravel flows.
Para. 10 & 11
Are migration pathways addressed through the IFG methodology in a
representative or critical reach study site?
With respect to out-migrant monitoring, properly designed, this program
could indirectly enumerate smelts and provide one way of quantifying
the contribution of the McArthur and Chakachamna systems to the Cook
Inlet fisheries to establish levels of mitigation necessary. The
Department currently conducts a smolt out-migrant study on the Kasilof
River that could serve as a model for the Chakachamna program.
Habitat Utilization
Para. 4
10-31
As mentioned earlier, it would be wise to review establishment of
proposed habitat transects with an interagency team.
Fish Populations
Para. 1
If it becomes apparent that the project will significantly impact the
fisheries resources of these systems, it would be wise to continue fish
population studies for several year·s. Otherwise there will be no data
regarding numbers of fish on which to base levels of required
·mitigation.
Impact Assessment
Para. 2
We suggest that an interagency team be established to propose and
review mitigation measures and to identify areas where further study
might be indicated.
WILDLIFE BIOLOGY
Wildlife
Para. 2
10-32
r
r
f
l
l
-f
f._
r
r·
\_
r
( /
L
t
l.
J
l_-
L
L
l'
f
i''
r
L
f'
c
f'
f_
l ~
t
r:
{o
L
8
L
h
f
l
L
L
.(
What is the reason for reevaluating the 1981 species selection? Are
there other relevant criteria than the three mentioned here that must
be considered. If so, what are they?
Habitat Suitability
Will the existing U.S. Fish and Wildlife Service Alaska models be used
to derive HSI or will the consultant develop his own?
Impact Assessment
Rather than departing from the standard HEP analysis because of the
uncertainty of future development, we suggest development of three
scenarios that describe varying levels of impact to the area and use
them to complete the HEP analysis. We believe that there is currently
enough information for development of these scenarios.
10-33
f ALASKA POWER AUTHORITY
334 WEST 5th AVENUE· ANCHORAGE, ALASKA 99501
RECEIVE:D
DEC 2 1982
~I. LODfR
The Honorable Ronald 0. Skoog,
Commissioner
Alaska Department of Fish & Game
Subpart Building
Juneau, Alaska 99801
Dear Commissioner Skoog:
November 26, 1982
Phone: (907) 2n · 7641
(907) 276-0001
Please reference your agency•s letter of February 18, 1982,
concerning Chakachamna Hydroelectric Project 1982 Work Plan,
Environmental Studies: The Alaska Power Authority appreciates the
detailed comments your agency has provided, but due to severe budget
restraints we have not yet been able to implement most of those. The
Power Authority through our consultant, Bechtel/Woodward-Clyde, has
call ected fishery data during this past summer and fall. Your agency
personnel were invited to visit the proposed project area while
Woodward-Clyde was actually collecting this data during August 1982.
We would like to invite you and your staff to a meeting at 9:30
A.M. on December 9, 1982, in the new Federal Building, National Weather
Service, 5th floor, East Conference Room. The purpose of the meeting
will be to present information collected during the summer and fall and
answer questions on an informal basis concerning the resource in the
area. I have attached an agenda for the meeting.
t4e have requested additional funding for the FY 84 budget year in
order to complete the feasibility study. Once legislative approval has
been acquired, a new work plan for environmental studies will be
developed taking into account concerns previously expressed by your
agency and others. It is our intent to coordinate this plan with the
concerned agencies.
Thank you for your continued participation in our planning
activities.
cc: Robert Loder, Bechtel
Wayne Lifton, Woodward-Clyde
Kenneth Plumb, FERC
Sincerely,
k!·"-\~
Executive Director
Carl M. Yanagawa, Alaska Department of Fish & Game
Don McKay, Alaska Department of Fish & Game
Phi Byrna, Alaska Department of Fish & Game
Attachment: Agenda 10-3 4
[
[,
{
l
I
\
L
c
L
------------
r "l"-
'
r
1 ,,
1
r~
r·
['
L~
L
L
c;
r~
I
t
t'
b
L ~-
L
[ '
-~
-------------------------------·---------------
February 18, 1982
Mr. Eric P. Yould
Executive Director
Alaska Power Authority
333 West 4th Avenue, Suite 31
Anchorage, Alaska 99501
Dear Mr. Yould:
U.S. DEPARTMENT C J:OMMERCE
National Oceanic and -,;maspherlc Admlnl•tr•tlan
NationaZ Marine Fisheries Service
P. 0. Box 1668~ Juneau~ Alaska 99802
RE(iElVED
We have received the Chakachamna Hydroelectric Project Interim Report -
November 30, 1981, and the 1982 Work Plan for Environmental Studies
Associated with this project. We have completed our review of both
documents and offer the following comments.
The Interim Report, according to your letter of January 8, 1982, is
being distributed in order to provide additional data on which to base
comments regarding the 1982 Environmental Studies Work Plan. Accordingly,
we have limited our review of this document only to those sections perti-
nent to the Environmental Studies program, sections 6 and 10. Section 6
provides a summary of those reconnaissance-level surveys conducted
during the 1981 season. Although little dataareprovided, this section
identifies areas that appear to be important to fisheries resources
and discusses gaps in available knowledge. Section 10 (describing the
1982 studies) and the 1982 Environmental Studies Work Plan both target
upon these important areas. However, we feel some caution should be
used in basing future studies heavily on the results of the 1981 work.
Paragraph 6.3.4 states that these surveys were of "limited duration" and
provide only a limited "look" at these river systems. The extent of
pink salmon spawning and the location of such spawning within the
Chakachatna River are unknown. The same is true for coho within this
system. Only limited survey work occurred on rivers tributary to
Kenibuna Lake or within Kenibuna Lake itself. The strength of the
1981 salmon runs may not have been representative, as even year runs of
pink salmon in upper Cook Inlet are larger than odd year runs. It will
be important for 1982 study efforts to remain flexible in order to fully
understand the fisheries resources of the project area. The 1982 Work
Plans presented to us do not have this flexibility or sufficient scope
to adequately assess impacts or identify necessary mitigative measures.
We have made some specific comments on both documents, which follow.
10-3 5
2
Inter;-im Report
10.1.3 Reservoir and Fish Passage Facilities
The report states that studies will be conducted regarding fish passage
into and out of the reservoir. The Environmental Studies Work Plan does
not identify these studies. What type of research is being discussed
here?·
10.3 Environmental Studies
This paragraph implies that current minimum flows were based on field
research on fisheries. These preliminary releases were developed using
a percentage of mean flow (the Montana Method) and do not necessarily
meet the needs of the fishery resources within the system.
1982 Work Plan -Environmental Studies
General -We do not believe the proposed studies are of sufficient scope
to achieve the stated objectives of providing data to accurately prepare
environmental exhibits for the FERC application, assess project impacts,
describe existing conditions or develop mitigation measures. At this
time we are most concerned with identification of waters within the project
area which support habitat utilized by fish, evaluation of altered flov1
to fishery habitat and the impact of altered temperature regimes. The
1982 fish survey sites should increase our understanding of the relative
value of project waters as habitat. We are pleased that instream flow
group (IFG) methodologies are being proposed to assess changes in habitat
values. However, we believe that a proper application of this system
requires considerable effort beyond that which is presented in the
work plan. Input from several areas is required in order to apply the
IFG methodology. It will be necessary to know the distribution of fish
species within the system, to select target species and life stages,
and to correlate this information with additional input concerning hydro-
logy and project operations. We realize that much of this description
would be too detailed to be included in a general work plan. However, as
this study element is critical to impact assessment and mitigation planning,
we believe a separate scope of work should be prepared and circulated for
comment which deals with the IFG methodology as it applies to the Chakachamna
project studies. The work plan does not adequately address the issue of
altered temperatures. We suggest that the upcoming studies allow for this
important issue. Continuous recording themographs may be valuable at sites
which may be impacted by thermal changes. Will a temperature model be
prepared?
The Work Plan fails to discuss how mitigative measures will be developed
for inclusion into the license application. We suggest early coordination
between the contractor and resource agencies on this issue. A mitigation
policy similar to that being developed for Susitna would be valuable.
Page 4, paragraph 5. The criteria used in selecting these wetlands for
study are not mentioned. Are these areas assumed to be representative of
the wetlands within the area of impact or of a special value as habitat?
10-36
r
r
[
c
[
l
L
f
L
L
f
\
L
r
L
t
r
h
L
L
[
3
Page 7, paragraph 2. The instream flow investigations will provide
necessary data on the impacts of flow regulation. Based on preliminary
information presented by Woodward-Clyde it appears that sloughs or
side channels in the upper McArthur and in the Chakachatna River below
Str~ight Creek are important spawning areas: Man~ of these channels may
be 1mpacted by altered flows and should be 1nvest1gated using in-stream
flow methodology. The Work Plan is not clear on whether these sites
will receive special attention, but states that new sites will be studied
using IFG-2 methodologies. We feel that some new sites (such as side
channels utilized by spawners) should receive the IFG-4 methodology to
more closely assess project impact.
Page 7, Aquatic Biology: The work plan does not describe what work is
planned for further limnological investigation of Lake Chakachatna or
Kenibuna. Water quality parameters, depth profiles and plankton tows
are some things that should be considered.
Finally, we must express our concern with regard to the project schedule.
It is unlikely that any study effort, regardless of its thoroughness,
could properly identify the fishery and related impacts within a 10
month period (February to November). The fact that liti;le information
currently exists for these systems adds to this concern, as much work
will be needed to gather basic reconnaissance-level data. We suggest
the timing of the FERC license application and the scope of environ-
mental studies for this project be reconsidered with an aim at insuring
a thorough understanding of the resources and a professional assessment
of project related impacts and mitigation opportunities.
We appreciate this opportunity to comment at this time.
Sincerely,
--C)..~ 77 £i:.'7--l~ ~ob,rt w. McVey
~ector, Alaska Region
10-37
a Zi&WX&G&
;
I
ALASKA POWER AUTHORITY
334 WEST 5th AVENUE· ANCHORAGE, ALASKA 99501
RECEIVED
Phone: (907) 277-7641
(907) 276-0001
DEC 2 1982
R. T. LODER
Mr. Robert W. McVey
Director, Alaska Region
National Marine Fisheries Service
P.O. Box 1668
Juneau, Alaska 99802
Dear Mr. McVey:
November 26, 1982
Please· reference your a-gency•s letter of February 18, 1982,
concerning Chakachamna Hydroelectric Project 1982 Work Plan,
Environmental Studies. The Alaska Power Authority appreciates the
detailed commer.ts your agency has provided, but due to severe budget
restraints we have not yet been able to implement most of those. The
Power Authority through our consultant, Bechtel/Woodward-Clyde, has
collected.fishery data during this past summer and fall. Your agency
personnel visited the proposed project area while Woodward-Clyde was
actually collecting this data during August 1982.
We would like to invite you and your staff to a meeting at 9:30
A.M. on December 9, 1982, in the new Federal Building, National Weather
Service, 5th floor, East Conference Room. The purpose of the meeting
will be to present information collected during the summer and fall and
answer questions on an informal basis concerning the resource in the
area. I have attached an agenda for the meeting.
We have requested additional funding for the FY 84 budget year in
order to complete the feasibility study. Once legislative approval has
been acquired, a new work plan for environmental studies will be
developed taking into account concerns previously expressed by your
agency and others. It is our intent to coordinate this plan with the
concerned agencies.
Thank you for your continued participation in our planning
activities.
cc: ''Robert Loder, Bechtel
Wayne Lifton, Woodward-Clyde
Kenneth Plumb, FERC
~=Y·y\ \ JA
Eric P. Yould ~
Executive Director
Ronald Morris, National Marine Fisheries Service
Brad Smith, National Marine Fisheries Service
Attachment: Agenda 10-3 8
r
r
L
L
{
1
k
L
L
L
10.3.3 Meeting -December 9, 198.2
Representatives of the agencies listed below were
invited to attend a meeting in Anchorage, Alaska on
December 9, 1982:
o u.s. Fish and Wildlife Service
o Alaska Department of Fish and Game
o National Marine Fisheries Service
o National Park Service
o Alaska Department of Natural Resources
o Northern Alaska Environmental Center
At this meeting, representatives of Alaska Power
Authority, Bechtel Civil & Minerals, Inc., and Woodward-
Clyde Consultants presented a summary of results of the
1982 engineering and environmental studies performed on
the project. A copy of the meeting notes is reproduced
on the following pages.
10-39
AI~ASKA POWER AUTHORITY
CHAKACHAMNA HYDROELECTRIC PROJECT
MEETING NOTES
DATE: December 9, 1982
LOCATION: Anchorage, Alaska
SUBJECT: Chakachamna Project Review Meeting
PARTICIPANTS:
Alaska Power Authority
Eric Marchegiani
Bechtel
Bob Loder
Dave Cornman
Woodward-Clyde
Wayne Lifton
Larry Rundquist
Mike Joyce
National Park Service
Larry Wright
Alaska Department of
Natural Resources
Karen Oakley
Alaska Department
of Fish and Game
Ken Tarbox
Bruce King
Phi 1 Brna
Kevin Delaney
Jim Faro
Gary L iepitz
U.S. Fish and
Wildlife Service
Lenny Carin
Gary Stackhouse
National Marine
Fisheries Service
Brad Smith
NAEC
rriC Meyers
Representatives from Alaska Power Authority, Bechtel Civil and Minerals 9 f
and Woodward-Clyde Consultants (WCC) presented a summary of results of the
1982 engineering and en vi ronmenta 1 studies perfonned on the Chakachamna
Hydroelectric Project to local, state, and federal agency personnel. The L
purpose of the meeting was to provide background information to new agency
personnel, to infonn all present of new project data, and to receive agency
inputs regarding study results and future project plans. l"
10-40
t L
t
L
c
f'
L
L
[-.-
-
t
h
L
L
L
Eric Marchegiani," Alaska Power Authority, initiated the meeting by
introducing those present. A 61-page handout was distributed containing
detailed drawings of conceptual fish passage facilities of 1982 fisheries
data and other relevant information. Eric then reviewed principal project
events which have occurred since the last project review meeting,
December 11, 1981. In addition, Eric reviewed the Power Authority requests
for funds and the funds appropriated, by the Legislature, for Chakachamna
Project since 1981. The FY 83 budget made it possible to investigate fish
passage into and out of the lake, enumeration of the fishery resources, and
an evaluation of a reduction in the cost estimate due to utilizing a tunnel
boring machine. The Power Authority has requested $2.9 million for FY
1984, to carry the project through out Federal Energy Regulatory Commission
(FERC) licensing.
Bob Lode·r, Bechtel, briefly reviewed the engineering studies performed to
evaluate various dam and tunnel alternatives for developing the Chakachamna
Lake hydro resource. These studies were reported in the 1981 Interim
Report. These engineering and cost studies showed that a Chakachamna Lake
tap and tunnel diversion to the adjoining McArthur River was the most
attractive alternative for power development. A preliminary capital cost
estimate of $1.2 billion was arrived at assuming the use of tunnel boring
machines.
Loder then provided a detailed review of the fish passage facility concepts
developed in 1982. Facility structures and operation were described on
large multi-colored wall drawings. Seasonal passage for downstream and
upstream migrant fish is provided at all projected lake operating levels.
Fish passage facilities consist of a one mile long divided tunnel from the
lake outlet to a point downstream on the Chakachamna River, a multi-level
spiraling fish ladder for upstream migrants, and two alternative lake out-
let facilities for downstream migrants.
Wayne Lifton (WCC) presented a brief overview of environmental studies
performed to date on the project. Larry Rundquist (WCC) then sulTVTlarized
the results of the 1982 hydrologic studies conducted in August and October.
Gage 1 ocati on·s were i 11 ustrated. The data base for recording gages on the
Chakachamna and McArthur Rivers was provided in overhead presentation,
along with a su!TVTlary of the staff gage data base. A general. description of
flow distribution and sediment characteristics was given based on field
observations and preliminary data.
Lifton then presented the preliminary results of the 1982 fisheries program
with a slide presentation illustrating the 24 sampling stations. Study
emphasis was placed on the Chakachamna River. Fish habitat, habitat utili-
zation, and spawning were investigated. Fyke nets and other gear were used
in rivers and streams and gill nets, seines, and shocking were used on the
lake. The results were summarized in figures (overhead presentation of
graphs) representing each sampling station. Preliminary presentation of
graphs) representing each sampling station. Preliminary escapement esti-
mates were provided in the handout. It appears that only Sockeye and Dolly
Varden are found in streams above Lake Chakachamna.
10-41
The major questions and concerns voiced at the meeting are listed below:
Genera 1:
* Eric Marchegiani -The total cost estimate is based on the Power
Authority's economic parameters. Do not compare these costs with
those on the Susitna Project, unless they utilize the same
parameters in an economic comparison.
Fish Passage Facilities:
*
*
*
*
*
*
*
Would someone be on site to control the gates?
The system can operated manually or by aut~matic sensors.
Has this system been used elsewhere in an automatic mode?
An existing reservoir in Oregon acconmodates similar change in
water level. A ladder is conventional, however, the water supply
chambers and openings to the reservoir are unconventional.
Has a gated system been used before?
Not sure, need to find out. This is not exotic change from what
has been used in the past. The most different feature is the
one-mile-long tunnel.
Is there an auxiliary water system to achieve 1,000 cfs?
That is part of the downstream migration system, and will be
discussed later.
Will a dark tunnel make avoidance probable?
The tunnel could be lighted if necessary.
Could this create maintenance problems?
There will be vehicular access. Someone would check facilities
on a regular basis. The powerhouse operator would check water
levels and gates.
Will the water temperature be regulated in the lower outlet?
No, not as planned. It just takes water from the channel.
r z
{ '
L
r
\. ..
L
r,
[
f L
t
f
L
Water taken from the lower depths would be colder. Thermocline i
may cause fish to pool up. t
[
10-42
t
L
*
*
*
*
*
*
*
*
*
Would this be a year-round operation?
Yes.
How will ice and debris be handled in the system (i.e., at the
grate)?
We would probably provide means of eliminating ice and debris at
the intake.
After November 1, no fish will be going upstream.
Ice is an issue that has to be dealt with in the design of the
facilities.
What is the depth of the power tunnel intake?
Approximately 150 feet below normal lake level and below lake
level in the spring.
Will downstream migrants find the power outlet or lake outlet
{attraction)?
Intake must be designed so they do not fined the power intake.
What is the possibility of varying temperature in the McArthur?
Have not addressed this problem yet •.
Explain the dyke. Where does it terminate?
Protective device for design of fish channel. Channel has to be
excavated to allow water entry at daylight level.
What is cost estimate of tunnel?
Do not know yet, but there is an advantage of a totally gravity
system {pumps are another option). The water level variation was
raised to accoiTITlodate the gravity system. (1,195 feet to 1,095
feet).
Will slough habitat be modified downstream?
This is another aspect which will be addressed later.
Fisheries Studies:
* Explain the graphs.
Live fish counts were made on weekly basis. Counts were plotted
versus consecutive days. Area under curve: fish-days, these are
divided by the amount of time the fish were in stream and result
in estimated total number of live fish per stream.
10-43
*
*
*
*
*
*
*
*
*
Essentially, the same technique was used on Susitna. This
information was supplemented with electroshocking, netting, and
ground counts. Data gaps did occur during the September storm.
How many people counted fish?
Two.
How did you cover the area?
Helicopter was equipped with special bubble windows. Overflights
were made as slow and as near to the ground as possible.
Were there fish at streams you could not monitor?
We counted every stream in which spawning fish were found and
some where there were no fish.
Were you aware of when runs began?
We took the helicopter out once a week for the entire schedule,
essentially since mid-July.
It is hard to understand how two people did all that.
Actually, five or six people were in the field. I am just
covering spawning right now.
Will count data be presented?
Each count will be recorded. The hydroacoustic survey was
conducted during the fall to count juvenile distribution in the
lake (overhead presentation). We were eventually weathered out.
What is the distribution at 100 feet? What do the nine and
twelve mean?
Number of fish per m3 x 10 3 • Fish were gel"era lly found deeper
than previously expected, to 100 feet. The numbers are ten foot
depths intervals. Fish were shore-oriented.
Did you find any lake trout?
Yes, quite a few.
Did you identify any areas where lake trout were concentrated?
We identified large concentrations of lake trout in 1981.
10-4 4
f
[
[
{_'
( t-
r
t
f
1
l
f -
l
l
r
L
L
f
\
r~
. .
r·
1'
r~
I
l
r
L
c
[
t
L
*
*
*
*
*
*
*
How many Dolly Varden were there?
They are residents and primarily caught by gear which gives
relative abundance, so can only estimate.
Are Dolly Varden the most abundant?
Maybe, hard to say, lots of slimy sculpin, pygmy whitefish, etc.
Also, lots of juvenile sockeye in lake.
Are escape estimates minimum numbers and did you only count
clearwater streams?
Clearwater counts were great. We feel. very confident in those
areas. When streams clouded up as in September, counts were much
less reliable. Many cloudy areas-side channels were countable
and counts were corrected by ground truthing.
Any spawning in mainstream indicated or seen?
Mainstream areas do not seem to be used. The water was too
turbid, substrates were bad for spawning. Only fish we found in
mainstream were not ripe or were spawned out (migrants).
When was fyke netting started?
August 6.
What was your recovery on tagged adult fish?
Not counting Dolly Varden, under 150 Petersen tagged salmon.
Of all species?
No, primarily sockeye, coho, and chums, with some pinks.
General Discussions:
Eric Marchegiani, Power Authority, explained the process for future project
funding. A discussion ensued on the need to develop a detailed plan of
study for full feasibility early in 1983 prior to continuance of plan11ed
field studies. A two-step approach to agency review was suggested:
1) Identify program elements and set priorities,
2) Provide detail on agreed upon list of programs and priorities.
Eric Myers (NAEC) expressed concern regarding the FERC licensing process on
the Susitna Project and an apparent lack of commitment to adequately study
Chakachamna as an a 1 ternative to Susitna. Eric Marchegi ani assured every-
one that the Power Authority is committed to evaluating Chakachamna as an
element of an alternative to Susitna as required for FERC licensing. In
addition, the Power Authority is pursuing a detailed feasibility study of
10-45•
Chakachamna as an independent project as indicated by its request for
$2.9 million for the Project in FY 84.
Eric Marchegiani, Power Authority, concluded the meeting, indicating that
the next report will be out by the end of February. There will be a June
Addendum to cover winter and spring work. Please review the fish and
bypass system and provide your ideas to us. We will meet to discuss plans
·for spring and winter.
10-4 6
! L
I
\
L
[
[
F c
[
f
h
L
L
[_
Distribution of December 9, 1982
Meeting Summary
The Honorable Esther Wunnicke
Commissioner
Department of Natural Resources
Pouch M
Juneau, Alaska 99811
cc: Mr. Robert Loder, Bechtel, San Francisco
Mr. Wayne Lifton, Woodward-Clyde, Anchorage
Ms. Kay Brown, Div. of Minerals & Energy Mgt., DNR, Anchorage
Ms. Karen Oakley, Div. of Minerals & Energy Mgt., DNR, Anchorage
Mr. Roland Shanks, Director, Div. of Research and Development
Mr. Robert W. McVey, Director
Alaska Region
National Marine Fisheries Service
Post Office Box 1668
Juneau, Alaska 99802
cc: Mr. Robert Loder, Bechtel, San Francisco·
Mr. Wayne Lifton, Woodward-Clyde, Anchorage
Mr. Brad Smith, Nat'l Marine Fisheries Service, Anchorage
Mr. Ronald Morris, Nat'l Marine Fisheries Service, Anchorage
Mr. Keith Schreiner
Regional Director
1011 East Tudor Road
Anchorage, Alaska 99503
cc: Mr. Robert Loder, Bechtel, San Francisco
Mr. Wayne Lifton, Woodward-Clyde, Anchorage
Mr. Lenny Corin, U.S. Fish & Wildlife Service, Anchorage
Mr. Gary Stackhouse, U.S. Fish & Wildlife Service, Anchorage
Commissioner
Alaska Department of Fish & Game
Subport Building
Juneau, Alaska 99801
cc: Mr. Robert Loder, Bechtel, San Francisco
Mr. Wayne Lifton, Woodward-Clyde, Anchorage
Mr. Carl Yanagawa
11r. Don McKay
Director
National Park Service
540 West Fifth Avenue, Room 201
Anchorage, Alaska 99501
cc: Mr. Robert Loder, Bechtel, San Francisco
Mr. Wayne Lifton, Woodward-Clyde, Anchorage
Mr. Larry Wright, National Park Service, Anchorage
10-47
10.3.3.1 Response
The National Marine Fisheries Service and u.s. Fish
and Wildlife Service replied to the Power Authority's
invitation to comment on the proposed conceptual designs
of the fish passage facilities for the Chakachamna Lake
outlet as described at the December 9, 1982 meeting.
Copies of the NMFS February 1, 1983 letter and u.s.
Fish and Wildlife Service March 9, 1983 letter are
reproduced on the following pages. Their suggestions
have been taken under advisement but time does not
permit action by the Power Authority at this juncture.
Present plans provide for an addendum to this March
1983 Interim Feasibility Assessment Report to be issued
as rapidly as possible after the spring studies have
been completed in June 1983. The Power Authority's
response to NMFS and u.s. Fish and Wildlife Service
suggestions will be addressed in that addendum.
10-48
f
l
f
I
r ..
\ .
I .
k
{
f l_
l
L
t
l~'
.. -
r-:.
L
L
L
February 1, 1983
Mr. Eric Marchegiani
Alaska Power Authority
334 W. 5th Avenue
Anchorage, Alaska 99501
Dear Mr. Marchegiani:
UNITED STATES t._..-'ARTMENT OF COMMERCE
National Oceanic and Atmospheric Administration
NationaL Marine Fisheries Service
P.O. Bo:r; 1668
Juneau, ALaska 99802
:0 FILES:
~roject 0 General 0
R f;~F lrM£ ~Q __ v_or. ___ -------
1. ~..!§ate Entered ----=----=
f -
0 7 1983
ALASKA POWER AUTHD8Jrt
The National Marine Fisheries Service has reviewed the Summary of Fish
Passage Facility Design Concepts and Preliminary Results of fY 1982-83
Fish Studies -Cha·kachamna Hydroelectric Project, Bechtel/Woodward
Clyde, December 1982. Our Fish Facilities Division has developed
comments specific to the conceptual passage designs, and we are
forwarding these for your consideration prior to completion of the
February report. We will be able to provide a more complete.analysis of
fishways design when operational concepts are finalized. The proposed
fish passage structures appear feasible, but we believe relatively high
mortality will occur with respect to out-migrants.
1. The turn pools at all ladder turns are too short. The interior
ladder wall at all turns should extend at least 8 feet upstream and
downstream from the adjacent weirs. The exterior wall would of
course e~tend further than 8 feet.
2. All adult fish ladders and channels must be lighted to encourage
fish movement. Natural light or artificial light can be used.
Access for artificial lighting maintenance is required.
3. The upstream passage facility shows a ladder with 60 pools. For
this orifice-overflow type of ladder to function properly the water
surface in the pools should be controlled to provide 1.0 ft. of head
on the weirs, plus or minus 0.1 foot. The document does not explain
how the water level in the ladder will be controlled during periods
when the forebay elevation is above or below an even-foot elevation.
It is assumed flow would be controlled by throttling the inlet con-
trol gate to the appropriate water supply chamber. Proper operation
of the ladder will require faultless operation of all 60 gates to
the individual ladder pools and all inlet gates to the water supply
chambers. This will require good access for frequent gate inspec-
tion and O&M. No method of access is indicated.
4. The ladder exits must be sufficiently removed from the downstream
migrant facility to prevent adult fish from falling back downstream.
10-49
/
5. Both schemes for juvenile passage appear to have potential for high
fish losses. Scheme A might be modified to avoid the turbulent
plunge pool which would exist, particularly when either of the top
two drum-type gates are operated. The drop of up to 80 feet ± into
the basin shown would be very hazardous for fish, since they would
be subjected to extreme turbulence with associated pressure fluctua-
tions and shear forces prior to exiting through the tunnel. High
injury and mortality rates can be expected. Continuous smooth
spillway crests downstream of each gate to a standard spillway
stilling basin, and a smooth gradual transition to the tunnel would
be an improvement.
Scheme B has more potential problems than Scheme A. These are:
(1) More mechanical equipment is involved, therefore more chance for
malfunction. (2) The entire flow is not near the surface where it
would aid fish outmigration. {3) Fish may not readily sound to the
depth required to exit through the tunnel, after they pass over the
flow control plate. (4) Fish passing through the two 7 ft. x 4.75
ft. tunnel discharge control gates can be expected to.suffer high
mortalities, based on experience at other projects of even lower
maximum heads. (5) Some fish can be expected to exit the forebay
through the two low level bypasses, particularly if lower forebay
elevations exist during outmigration, and flow conditions in the
bypass conduits could be damaging to fish.
6. The proposed breakwater in the lake could result in downstream
migrants not finding the lake outlet so readily. The location and
length of the breakwater and its relationship to shoreline
topography should be co~sidered very carefully to avoid anadromous
fish passage problems. ]The approach channel to the lake outlet
should be designed with consideration to maintaining adequate
velocities to move fish to the outlet structure.
7. The proposed power outlet from the lake to the powerhouse will
apparently be located considerable distance from the fish passage
facilities. No information is given as to the magnitude of the
power discharges. Power discharges can be expected to detract from
the limited outmigrant attraction provided by the fish passage
facilities, reducing their effectiveness in maintaining fish runs.
Should you have any questions regarding these comments, please contact
our Anchorage Field Office at 271-5006.
SinceQ~ 914~
)«:lbeft W. McVey
•1 o;yector, Alaska Region
l /
10-5 0
~
r·
[
L
l
L
L
I
L
L
L
United States Department of the Interior
r INREPLVREFERTO:
FISH AND WILDLIFE SERVICE
1011 E. TUDOR RD.
['
L
\
r L
L
L
L
WAES
ANCHORAGE, ALASKA 99503
(907) 276-3800
Eric P. Yould, Executive Director
Alaska Power Authority
334 West 5th Avenue
Anchorage ,'Alaska 99501
Dear Mr. Yould:
0 9 MAR 19bj
The Fish and Wildlife Service has reviewed the report prepared for you on
the Chakachamna Hydroelectric Project by Bechtel/Woodward-Clyde in
December 1982 entitled, A Summary of Fish Passage Facility Design
Concepts and Preliminary Results of FY 1982-83 Fish Studies. Our
comments below are specific to the conceptual fish passage structures
illustrated in the report and do not address the fishing studies.
Previous letters, dated 5 March, and 26 March, 1982, provide comments
which are still pertinent to the on-going fish and wildlife studies.
The followin~ comments are presented in the order of the sketches
contained in the Bechtel/Woodward-Clyde report:
Drawing No. SK-C-001.
1. The proposed reduction in discharge at the lake outlet may accelerate
the lakeward movement of Barrier Glacier toward the proposed approach
channel and passage facility structure. According to U.S. Geological
Survey measurements made during 1961 through 1966, this glacier
advanced several feet per year at measuring stations located near the
river bank at the lake outlet.
2. Anticipated flows in the vicinity of the rock-fill fish barrier
should be determined.
Drawings No. SK-C-002, SK-C-003.
1. Fishway pools numbered 1105, 1125, and 1145 should be at least ten
feet long, consistent with the design of the other fishway pools.
2. Provision for an access walkway along the top of the fishway pools
and natural or artificial lighting should be provided.
10-51
3. The proposed fishway is ·a weir type (six foot by ten foot pools) with
split Ice Harbor type baffles. Each fishway pool would have the
standard bottom orifice plus an additional gated opening in the
outside wall of each pool to compensate for the anticipated 60 foot
fluctuation in lake level. We recommend the following design
parameters for the fi shway baffles:·
Weir crest height =
Weir overflow width =
Orifice size =
Fishway flow =
6 feet
3 feet
18 inches x 18 inches
27 cubic feet per second (with 12
inch head on baffle)
4. Gate operating mechanisms for the 60 gated openings in the fishways
are not shown. We understand gate operation would be automatic,
using sensors which open and close designated gates, and would
compensate for changes in lake level. Due to the large number of
gates, we anticipate operation and maintenance problems. Reducing
the extent of lake fluctuations during the upstream migration period
would reduce the number of gated openings required.
5. The fishway pool size is dependent upon the design population of fish
to be passed. The design population will need to be established and
fishway pool size should then be adjusted accordingly.
Drawing No. SK-C-004.
1. The downstream migrant facility should draw flow from the surface of
the lake as indicated on this drawing. However, the passage of ice
through this system will be a problem during the winter and spring.
2. The drop from the upper gate into the plunge pool can be decreased by
utilizing an orifice or gate at the entrance to the discharge tunnel.
Drawing No. SK-C-005.
1. Scheme 8 may not provide sufficient flow from the surface of the lake
to be effective for downstream migrants. The establishment of
adequate lake releases is essential to assure that the system
maximizes outmigration to the estuary.
Drawing No. SK-C-006.
1. It appears that the adult fish "fall backs" from the lake will be
trapped by the horizontal grating proposed at elevation 1072 in the
outlet structure. This potential problem could be avoided through
use of an angled vertical screen or rack in lieu of the horizontal
grating. This angled rack would also serve to guide upstream
migrants to the fishway.
10-52
[
[-
L'
[
r:
[
L
L
L
l
L
L
t
[
L
L
L
L
L
We hope that these comments are helpful as Bechtel/Woodward-Clyde
continues to refine the initial passage facility concepts. If you have
any questions regarding our comments, please contact Leonard P. Gorin
(907-271-4575) at our Western Alaska Ecological Services field office.
Sincerely,
cc: FWS-WAES
ADF&G, NMFS, EPA, Anchorage
10-53
10.4 National Park Service
10.4.1 Lake Clark National Park
The copy of the January 12, 1982 Power Authority letter
to Mr. Paul Haertel, Superintendent of Lake Clark
National Park is reproduced on the following three pages
to illustrate the nature of coordination effected with
the National Park Service.
l
(
-L
r -
t
r-
l~
k
l
L
l
r
L
l
L
10-54 L
[
[
[
b
[
l
L
f L
L
ALASKA POWER AUTHORITY
334 WEST 5th AVENUE· ANCHORAGE, ALASKA 99501
Mr. Paul Haertel
Superintendent of Lake Clark
National Park Service
U. S. Federal Building
Anchorage, Alaska 99501
Dear Mr. Haertel:
January 12,
Phone: (907) 277-7641
(907) 276-0001
We are presently undertaking a feasibility study of the proposed
Chakacharnna Hydroelectric Project. The study cormenced in August 1981
and is scheduled for completion in early 1983.
The project area is located approximately 60 miles west of
Anchorage. The water storage reservoir for the proposed hydro:p::Mer
project would be existing Chakacharnna Lake, a 23 square-rrile lake fo!:1'l"ed
in a steep valley behind a glacial rroraine. CUrrent studies have
identified several alternative arrangerrents for the project. The
alternative with the greatest power potential involves a lake tap
leading through an 11 mile transrrountain diversion tunnel to a power
plant on the McArthur River. Such a diversion of flCJIN nay have
significant environrrental impacts in the McArthur River and in the
Chakachatna River, the outlet stream fran Chakachamna Lake. These two
rivers are knam to have runs of anadrarous fish. The planned project
construction for any of the alternative layouts presently under
consideration does not involve any construction activities within the
boundaries of Lake Clark National Park. HCMeVer, as stated above, the
project operation nay affect the fish and wildlife in the Chakachatna
River basin including part of the National Park by diversion of water
fran the Chakachatna River and by seasonal lc:Mering of the level of
Chakacharnna Lake.
The work being perfomed in the feasibility study includes an
assessrrent of the envirornrental :inpa.ct of the project construction and
operation. To evaluate the influence of the project on the fish and
wildlife populations of the area it is necessary to include in this
evaluation those resources within the National Park, specifically
Kenibuna Lake since a portion of the anadrcm:::ms fish run passing through
Chakacharnna Lake enters Kenibuna Lake.
At this tine, the 1981 environrrental studies field program (aerial
and ground reconnaissance of the general study area) has been carnpleted.
The first overview was conducted in August with the oojectives being to
dOCUITEI1t the presence of sockeye salrron in the major project waters and
to survey the site in preparation for the fall reconnaissance. The
second investigation was carried out in mid-September and involved two
10-55
~) ,b
"' Mr. Paul Haertel
January 12, 1982
Page 2
weeks of field data collection. The objectives of the effort were to
obtain sufficient info:rnation and understanding of the project site and
its resources to allCM for the design of rrore detailed 1982 studies, and
to assess, in a preliminal:y nature, the overall feasibility of the
conceptual designs of the project alternatives. In this 1981 program,
no activities were performed within the National Park.
Since part of the 1982 field program will occur within Lake Clark
National Park, we are requesting that a special use penni t be authorized
for the envirol1I'lEI1tal investigations. Specifically, we are requesting
that the follc:Ming nonconsunptive activities be authorized in the
National Park:
0 fly over and land near the Igitna, Neacola, Another, and
Chilligan Rivers using a helicopter;
0 use a rrotorized raft on Kenibuna Lake;
0 use standard surveying techniques and depth sounding equiprent ~
and
0 conduct vegetation surveys.
In addition, we request that the folla.;ing consunptive, yet
nondestructive, activities be authorized in the National Park:
0 the collection of stream and lake substrates to assess stability;
0 the use of fyke nets, electroshocking equiprent, and seines
(adults captured by these techniques will be released);
0 the limited use of gill nets along the steep banks of the lake
shore. If used, the gill nets will be set for short periods of
time to prevent excessive losses.
There will be no canping or similar activities associated with
these above activities. A schedule for these activities is attached.
The \rork described above \rould be perfo:rned for the Authority by
Bechtel Civil and Minerals, Inc. and their envirol1ITEI'ltal subcontractor
Woodward-clyde Consultants. Subsequent to these studies, we do not
anticipate any further investigations within the Lake Clark National
Park.
If you have any questions or if you require additional info:rnation
on any phase of this program, please contact ne.
Sincerely,
Attachrrent: Schedule
t:f~!E-
0
cc:
'( . ~. . . . ~--~ ' ~ . -... . ·•t
~ T. ·Loder,. Bechtel·.
........ · .• : ... ·; . . .. -. ~f . ..: .. ~ ... . . . . . J
10-56
r-
\
[
l
~···
L
L
L
[
L
[
r
f
L
l
L
L
L
(
ALASKA POWER AUTHORITY
Table 1. Tentative Schedule for Activities to be Conducted .within Lake
Clark National Park
Fish Aerial
Schedule* and Ground SUrveys
31 .Ma.y-2 June X
21-23 June X
12-14 July X
2-4 August X
23-25 August X
13-15 September X
4-6 O:tober X
Activity
Wildlife Visual
Reconnaissance
X
Hydrology
Habitat
Pararreter
Measurerrents
X
X
*Activities should only require one day during each schedule period.
10-57
10.5
10.5.1
10.5.1.1
Northern Alaska Environmental Center
Correspondence
A copy of a December 13, 1982 letter received from
Eric F. Myers of the above referenced agency is repro-
duced on the following eight pages.
Response
A copy of the Power Authority's reply, dated December
30, 1982, is reproduced on the two pages following the
reproduction of Mr. Myer's letter.
10-58
r -
L.
L
L
I.
~~
L
r~
L
L
L
·r
L
[
b
L
b
L
L
L
L
I
L
L
. .
Northern Alaska Environmental Center
833 Gambell Streeet -Suite B
Anchora?-e, Alaska 99501
Mr. Eric Yould
Executive Director
Alaska Power Authority
334 West 5th Avenue
Anchorage, Alaska 99501
Dear Mr. Yould:
-I r
(907) 277-6814
13 December 1982
!,B ~ C J: 1 y JH~ J
r·r:c ..;_ l 6]982
~ fOWER AUT'HOMf1
I am ~rriting to ex'!)ress forma-lly my great concern about the
progress and adequacy of the Lake Chakachamna feasibility
studies. As you well know, the Chakachamna project is the
·most significant and likely hydro alternative to Susitna and
a compr-ehensive evaluation of this potential hydro option is
central to the on going Railbelt power studies. Without the
commitment of the APA to undertake and execute the necessary
investigations to assess project feasibility at the level of
detail required for preparation of a FERC license application,
the APA will preclude meaningful consideration of the Chaka-
chamna option.
As a result of attending the recent December 9, 1982 inter-
agency briefing on the status of the Chakacpa~a studies, it
is apparent that the APA is not honoring its nublic commitment
to continue the Chakachamna investigations in a substantive
and timely fashion. It is now evident that the FY 83 funding ·of
$800,000 allocated by the APA Board to the Chakacharnna studies
is entirely insufficient to address the outstanding questions
about project feasibility and that this will have the effect
of discounting the viability of the Chakachamna option as part
of the FERC Susitna proceedings.
The Northern Alaska F.nvironmenta.l Center has, over the past
three years, repeatedly cited the need to move forward 'I:·Iith
the Chakachamna investigations in an appronriately ag~ressive
fashion so that the Chakachamna and Susitna outions can be
considered on an equal basis. That is why last June I urv.ed
the APA to allocate the full $3.3 million necessary to under-
take the ful~. scope of feasibility studies required to assess
the Chakachamna site. At that June Board meeting you represented
that $800,000 ~10uld be sufficient to continue the evaluation of
the Chakacr.amna option. At the December 9 interagency meetinr,,
hmvever, APA project manager Eric Harcher.iani ~ade repeated
reference to "budgetary constraints" and the fact that he has
not "had the level of funding necessarv to sunport" a feasi-
bility level report. The ~orthern Alaska Environmental Center
continues to be deeply concerned that a lack of commitment on
the part of the APA to conduct the appro~riate engineering,
10-59
Mr. Yould, p.2
geotechnical, and environmental studies of the Chakachamna
site will result in_a prejudiced evaluation of Railbelt elec-
trical options. Precisely the situation we had hoped to avoid
is pow being realized.
The limited work done by Bechtel and Woodward-Cl_ Je has accom-
olished little more than confirm the fact that Chakachamna is
very attractive economically (relative to Susitna) and that
the site supports ~ significant fishery resource (as does the
Susitna). The work by Bechtel/Woodward-Clyde, however, will not
yield a level of assessment necessary for preparation of a FERC
license application as stated by Mr. Marchegiani, nor will the
Bechtel/Woodward-Clyde work provide a sufficient basis for
comparing the relative economic and evironmental merit of these
projects as required for the FERC/NEPA-EIS process. It seems
inescapable that the submission of a Susitna license applica-
tion in the first quarter of 1983 (as presently planned) would,
on its face, be deficient in this t.·egard.
The Northern Alaska Environmental Center shares your oft stated
concern for the potential fishery impacts that could attend de-
velopment of the Chakachamna site, as we are concerned with the
myriad impacts that would be associated with development of the
Susitna basin. Neither of these projects should enjoy blind
support and both must be carefully evaluated as part of a com-
prehensive Railbelt power planning effort. It is lamentable that
some p~rceive the more modestly scaled 330MW Chakachamna project
as a t~reat to Susitna. Especially at a time when electrical
demand'projections are dropping dramatically and future load
growth is clouded with great uncertainty, such a narrow perspec-
tive contributes little to the need for cautious consideration
and prudent planning to develop an optimal supply strategy for
the Railbelt. As you well appreciate, the questionable need
for a massive project like Susitna requires careful evaluation
of more flexible capacity supply strategies which could include
a combination of short-term benefits from combined cycle combus-
tion turbines using natural gas and long-term benefits from s
more modestly scaled hydro project like Chakachamna.
For these reasons we formally ask the APA to defer filing of the
Susitna license application in February so that (1) detailed
evaluation of the Chakachamna option may be included in the
application and (2) the fishery and wildlife impacts that would_
be associated with either project may be better understood. We
ask, moreover, that the APA i~nediately dedicate the necessary
financial and personnel resources to upgrade the Chakachamna
study effort to that of a true feasibility study and so that
the 1983 field season may be as productive as possible. At a
very minimum, this should start with the convening of an inter-
agency steering committee for the Chakachamna project analogous
lQ-60
I
I
[
~~
l
[
l
r·
l
L
L
[
r·
[
b
[
L
L
·l
L
Mr. Yould, p.3
to the Susitna Hydro Steering Committee.
In the absence of such action on the part of the APA to insure
a thorough analysis of Railbelt power alternatives, we feel
that vou will jeopardize the Susitna license application and
subjL_t the entire process to unecessary delay.
The Chakachamna Alternative
The Northern Alaska Environmental Center has not been alone in
its effort to draw attention to the need to carefully consider
more modestly scaled power options such as Chakachamna as an
integral aspect of formulating a responsible plan to meet future
Railbelt power requirements. Indeed, the External Review Panel
of international experts retained by the APA to provide an in-
dependent assessment of the Susitna project, in formal testimony
to the APA Board, strongly recommended that your agency identify
viable power alternatives in the event that (1) Susitna is delayed
or (2) the demand forecasts change. Precisely the latter circum-
stance has emerged with current Battelle energy projections for
the year 2010 as much as 447. lower than the ISER forecasts used
by Acres in its development selection analysis which led to the
adoption of the Watana/Devil Canyon scenario. See Table 1.
This advice was reflected in the letter sent by the APA to the
State legislature (April 26, 1982). which recorrnnended that the
qhakachamna and North Slope gas alternatives be thoroughly in-
vestigated. The APA Board specifically indicated that FY 83 costs
to continue the Chakachamna feasibility studies was on the order
of $3.3 million.
The Policy Review Committee, charged with the responsibility of
managing the Battelle Alternatives to Susitna study, concurred
with these assessments and also supported FY 83 funding to assess
the Chakachamna optic~ in detail along with additional investi-
gation of the North Slope gas and Beluga coal options. ·
More recently, the Division of Budget and Management noted cer-
tain deficiencies in the FY 83 studies respecting the APA staff
descision not to undertake necessary geotechnical studies. The
Division of Budget memo (August 19, 1982), distributed to the
full Board by Dr. Ronald Lehr, noted that the limited scop~ of
the FY 83 Chakachamna studies "may result in a (Susitna) FEP-C
license application next spring which is neither complete nor
adequate."
Funding
As you know, when the legislture adjourned, it had appropriated
$25.6 million for the continuation of the Susitna/Railbeltpower
studies. At the June 24, 1982 APA Board meeting consideration
10-61
Mr. Yould. p.4
was given to the issue of submitting a FERC license applicati9n
including the role that the Chakachamna feasibility study played
in the overall evaluation of Railbelt power options. I myself
took the opportunity at that time to make a statement to the
Board and urged. that the full $3.3 million necessary for the
Chakachamna studies be dedicated to that purpose from the $25.6
million available. To my great disaoointrnent it was your
recommendation to the Board that only $800,000 be allocated to
the Chakachamna investigations. It was your contention that
$800,000 was sufficient to carry the studies forward. As noted
in the recently prepared APA FY 84 budget proposal relative to
the Chakachamna project, the "FY 83 funds are coming from the
Susitna funds since Chakachamna is considered as an alternative
to the Susitna Project." The budget document goes on to state
that the FY 83 ($800,000) phase of investigation "will see a
threshold level of environmental investigation and additional
engineering studies to confirm the construction cost estimate
and cost of power."
It is not clear to me what a "threshold level" of evaluation means
in light of the data that has been gathered by Bechtel/Hoodward-
Clyde and which was presented at the December 9 interagency meet-
ing. Clearly, the project is still economically attractive, in
fact even more so now than when Acres did their feasibility work
on Susitna as a result of downward revisions in capital cost
estimates by about $0.22 billion due to the ability to use state-
of-the-art tunnel boring technology. As for the environmental
work --which has focused exclusively on the fishery ---there
is little to be concluded 9eyond the fact that the McArthur and
Chakachatna drainages support a significant fishery resource on
the basis of very limited escapement data. The "threshold" level
of data developed by Bechtel and Woodward-Clyde has confirmed the
fact that the Chakachamna alternative is as much (if not more) of
a Railbelt power alternative due to (1) downward revisions in
expected capital costs and (2) downward revisions in expected
load growth.
The Need for Additional Investigations
At this point, the Northern Alaska Environmental Center is very
concerned that the Chakachamna studies be expanded substantially
in scope. We urge that the APA immeadiately commit the financial
resources preseptly at its disposal toward the development of a
comprehensive f~asibility study of a quality and detail equal to
the Susitna studies. The scope of investigations should include
a--much more detailed examination of the Chakachatna tunnel alter-
native, especially in light of the recent findings regarding
tunnel boring technology. (While the Chakachatna tunnel alter-
native may not be as attractive as the McArthur tunnel scenario,
it offers the distinct advantage of perha~s avoiding altogether
impacts to the HcArthur drainage.) It is imperative that this
effort be initiated immediately and aggressively so that the
Chakachamna hydro option can be considered on a parity basis with
10-62
,-
f
f -
1-
1
I
l
L
L
r
I.
r
l'
r .·
~
r
L
L
J L
L
Mr. Yould, p. 5
Susitna. It was clearly evident from the comments made by the
resource agency personnel at the December 9 meeting that there
is a great amount of work to be done between now and the point
when we could achieve such a level of comparability.
This is particularly disturbing in looking back thrnugh the
November 1981 Interim Report on the Chakachamna stu .. ies which
was very explicit about the fact that the consultant was pro-
viding services "for performing a feasibility study and for pre-
paring an application for a FERC license to construct" the
Chakachamna project. The "1982 Work Plan -Environmental Studies"
circulated by the APA to the resource agencies almost exactly
one year ago was equally explicit with regard to the overall
objective being to prepare the necessary environmental exhibits
to accompany an APA license application. Unfortunately, this
"paper commitment" has not been supported monetarily.
As currently planned, Bechtel/Woodward-Clyde will issue their
findings at the end of February and the study at that point will
not be of sufficient quality to make a clear determination about
project feasibility. It is perhaps not entirely ironic that the
same month is targeted for submission of the Susitna FERC license
application. Further work on the Chakachamna feasibility study
will then be dependent upon the vagaries of legislative appro-
priation during a time when increasing political pressure is
being orchestrated to "pour concrete."
The Need for a New Plan of Study
I do not mean to imply that even an unlimited budget for the
Chakachamna studies as of last June could have yielded a com-
pleted feasibility study by "late winter of 1983" as was pro-
posed in the "1982 Work Plan -Environmental Studies" document.
The 1982 Work Plan was deficient in many regards, as pointed out
in the comments prepared by ADF&G (February 18, 1982), USF&WS
(March 5, 1982; March 12, 1982) and NMFS (February 18,1982)
much remains to be done to work out a comprehensive Plan of Study
to identify and execute essential field studies. However, a '
larger budget last June and resolve on the part of the APA to
initiate the necessary interagency processes would have advanced
the studies much further than they are today.
With the limited funding, the 1982 Work Plan and agency comments
were "set aside" (to use Mr. Marchegiani's words) and a scope of
work negotiated between the APA and Bechtel/Woodward-Clyde with-
out the a · ro riate involvement of other resource agency personnel~
the resu t is that whi e we o know somewhat more about the project
site, a great deal of money and, more importantly, time has been
wasted.
Based on the limited information currently available, the 330MW
Chakachamna project still appears to be very attractive economically
10-63
·.
Mr. Yould, p.6
with an estimated capital cost of approximately $1.23 billion
(Bechtel/October 1982 Progress Report). As you noted in re-
cent remarks to the Alaska Environmental Assembly (November 13,
1982) the Chakachamna project is very competitive with Susitna
and qui.te possibly the more attractive economic choice. This
is pa1 ~cularly so because a project the size of Chakachamna
would not be vulnerable to the uncertainties of load projections
(ie., we can reasonably assume the need to replace 330MW of
thermal capacity but cannot necessarily assume the need for all
1600MW' s offered by Susitna). While you have acknowle.dged the
economic merit of Chakachamna, you have expressed great concern
for the fishery impacts that could attend development of the
project. This sentiment is reflected in the Acres feasibility
reoort where Chakachamna was not included in the "base case"
pl~m because "it may have a substc.>.ntial fishery impact" and
because "studies to date have been insufficient to determine
expected capital costs with precision" (Acres/Summary Report,
March 1982, p. 7). Notwithstanding the substantial expenditures
by APA to Acres, the same general observations may be made about
the Susitna project.
The Susitna related fishery resource is only dimly understood
at this point with only the initial phases of a basic 5-year
study program complete. Recent correspondence to your agency by
USF&WS (October 5,. 1982) and NMFS (October 15, 1982) describes
the more important fishery issues that remain entirely unresolved.
The fact that the 1982 (second year) field data will not be in-
cluded in the license application highlights further the severe
limitations to our current understanding of the potential impacts
to the Susitna basin fishery. More succinctly, at present the
Federal and State resource agencies are only now in the process
of describing the existing resource and are far from understanding
the impacts associated with post-project conditions.
Respecting confidence in the Acres capital cost estimates for
Susitna, the fact that an independent cost estimate by Ebasco
yielded a $0.36 billidn disparity clearly indicates that the .
"precision" of Acres Susitna cost estimate is somewhat suspect.
Finally, I would note that the minutes of the June 24th APA Board
meeting reflect your comment that "Susitna must be the best alter-
native before the FERC will issue a license." It is our hope
that the FERC process will, in fact, insure that the Chakachamna
alternative is investigated adequately and the best Railbele~Power
alternative developed. To that end, we urge the APA to defer its
Susitna license application and move forward immediate} y with
expanded Chakachamna studies so that these two major alternatives
may be considered on a comparable basis.
Sincerely,
L1-.~~
Eric F. My'ers
10-64
r
r
I .
[ .
L.
L
r
\
r i
l.
L
I
l
[~
r.
f
f'
{
r,
[
r
L
r.
L
L
L
L
L
L
Mr. Yould, p. 7
cc: APA Board
USF&WS
NM.FS
ADF&G
ADNR
Susitna Hydro Steering Committee
Quentin Edson, FERC
Sierra Club
Alaska Center for the Environment
Trustees for Alaska
Governor Sheffield
10-65
Year
1980
1985
1990
1995
2000
2005
2010
Notes:
Table 1
DECLINING LOAD GROWTH
PROJECTIONS
''Medium'' Load Growth
1980 1982
ISER1 Battelle2
2790 2551
3570 3136
4030 4256
5170 4875
6430 5033
7530 5421
8940 6258
Projections /GWh
Revised
Battelle3
2551
3000
3391
3884
4010
4319
4986
1. Used by Acres for generation planning studies for development
selection; Acres feasibility study Table 5.6.
2. Battelle "base case" ; Battelle Comment Draft Table A.l2.
3. Revised Battelle forecast; Prologue Table 3 (Draft).
10-66
J
( '
I
1
i
r
l
t
L
L
l
J l
{
L
{
i L
I
L
L
L
(
ALASKA.POWER AUTHORITY
334 WEST 5th AVENUE-ANCHORAGE, ALASKA 99501
~ECEIVED
JAN 4 1983
Mr. Eric F. Meyer
Northern Alaska Environmental
833 Gambell Street
Suite B
Anchorage, Alaska 99501
Dear Mr. Meyer:
Center
Phone: (907) 277-7641
(907) 276-0001
December 30, 1982
Please reference your letter of December 13, 1982 in which you
suggest the Alaska Power Authority defer the filing of the FERC license
on Susitna.
We will not defer the filing of the Susitna FERC license
application. The Power Authority believes the studies being done on the
Chakachamna project to date are more than sufficient to fulfill all FERC
requirements for the study of alternatives for Susitna license
application. Furthermore, the Chakachamna project is not itself an
alternative to Susitna, but rather an element of a larger alternative
scenario that includes coal and natural gas fired generation.
Over $1.8 million has been invested by the Power Authority and the
Governor's office in evaluating the ChakaGhamna hydroelectric potential.
Neither the Susitna Feasibility Study nor the Battelle Alternatives
Study found the Chakachamna project to be the preferred Railbelt power
generation alternative. At the same time, however, the potential for
eventual contrary findings was recognized. New information on
Chakachamna costs, Susitna costs, or load forecasts could conceivably
reverse the findinQs. Therefore, additional work to explore money
saving construction concepts was deemed advisable. The necessary funds
were taken from the Susitna appropriation. A FY 82 study plan was
drafted which addressed the primary area of concern affecting
feasibility: project cost. Fishery impact was also deemed important, as
mitigation measures (minimum flows and fish passage) could potentially
impact project output and cost.
The current program has three major components: 1) fish passage
into and out of the lake, 2) enumeration of the fishery resource, and 3)
the applicability of tunnel excavation by means of a tunnel boring
machine. (This possibility represents the source of the greatest
uncertainty in the cost estimate.)
The fish passage facility analysis has involved the development of
a structure which would permit passage of fish at various lake levels
with gravity flow. In order to provide gravity flow through the
facility, the project would require a small 50 foot rock filled dam at
10-67
' .
,
Mr. Eric F. Meyer
December 30, 1982
Page 2
the outlet of the lake. This structure would probably require
cont}nuous maintenance due to the movement of the Barrier Glacier.
The fishery enumeration program has collected data continuously
between July and November. In addition, there will be a winter survey
and a spring survey. The program will estimate the seasonal
distribution, habitat abundance, and numbers of fish. ·The estimate of
fishery impact will be updated based on this additional data. Further
work such as an instream flow assessment would be required to fully
evaluate project impacts and mitigation measures, but such impact work
cannot effectively begin until a year of base line data collection is
accomplished.
As you are aware, a representative rock sample has been acquired
near the McArthur power house site and has been sent to the Robbins
Company Testing Laboratories in Seattle, Washington. The Robbins
Company has reported that the rock is similar to the rock found at the
Kerckhoff project in California, where a 24 foot diameter tunnel boring
operation has been in satisfactory progress during the past year. The
test data from the rock analysis has generated information which was
utilized to estimate the cost of using a tunnel boring machine rather
then the conventional drill and blast method. The estimate has reduced
the cost of the project by app!oximately $200 million.
In summary, the Alaska Power Authority has pursued the Chakachamna
Project with the appropriate diligence, given that studies to date have
shown it not to be the preferred Railbelt power generation alternative.
The current studies are more than adequate to fulfill all FERC
requirements for the study of alternatives.
cc: · Robert Loder, Bechte 1 .
Wayne Lifton, Woodward/Clyde
Kenneth Plumb, Secretary, FERC
William Wakefield, FERC
Charles Conway
10-68
Sincerely,
I _._·~·· ~ .
Eric P. Yould
Executive Director
r·
\
1
l
r
!
(
\ -
[
L
[,
r
'\ I
(
(
L~
APPENDIX TO SECTION 4.0
POWER
STUDIES
-
PRCJEr.T l41\7CJC01
INSTALLED CAPACITY: 4[0000. KW
ANNUAL FLANT FACTGP: .s
OVERLGAC fACTOP! 1.00
PLANT EFFICIE~cy: .850
FRJCTIC~ LCSS COEFFICIE~T: .000002370
r-.oN TliL Y L OA.D FACTORS!
.q2C .870 • 7{<. c .700 • 640 .620
I rH T I AL LAKE STGRAGE !4033200. AC-FT
MINir~UI' LAKE STCRAGf 0. AC-FT
MAXIMUM LAKE STORAGE !4033200. AC-FT
.610-
--(..--.,
CH~KAChAMNA PNUJECT CPfRATION STUDY
1·/1< ,II~ r::r , ll [ (' f, TEL C 1 V I L & r~ 1 N [ R A L S 1 N C • , SF •
~LASKA POWER AUTHORITY
ALTERNATIVE A! MCARTHUR S~bRT TUNNELt W/0 FIS~ RELEASES
.640 ... 7 00 .• aoo .92[1 1.000 ··----·---·-·--· .
DATE 110581 PAGE.
f)
rj
<)
•)
0
PROJECT }qf!7<J001
(' RFSERVCIP STVntf[-fLfVATIU~-IP[A!
C~AKAC~AMNA PROJECT OPERATION STUDY
1:/1~ oii&CF ollECI!TEL C 1 Vll&MINERALS INC. tSF •
ALASKA POWER AUTHORITY
ALTERNATIVE A: MCARTI'UR SHORT TUNNEL• W/0 FIS~ RELEASES
DATE 110581 PAGE 2
(' 0 AC-FT FffT ACFE
c • 7f.C. c •
202'i. 7 F. r:. • A I 0 •
730 0. 77 c:. 130C.
27200. 1f'· ('. 2£.-9 0.
lllOCO. F2Ga 5f,70.
241000. 10:' C • 73?t.
3<J7CO 0. 1'40. A270.
572COC. P~fJ. 921l0.
7f>9800. 880. toqoo •.
'Jflf,~CO. 9CC. 11590.
12240CC. 92C. 11960.
14!'7~00. S4 [I e 1232~.
17170CO. <J f 0. 12!':50.
l'iBDOC. 9ectl 1?980.
?2~.6000. 1 0 c 0. L'.?P.O.
. 2504COO. 1020. 13520 •
2776000. 1 c 4 0. 13740.
3G!'l3000. 1 a 11 o. 13%0.
333~000. lCBC. 14170.
3f2COOD. 1 1 c 0. 14390. (·
3S1COOO. 1120. 14620.
(' 4033200. 112€. 15212.
Tf. ILWATER -FLO\.! RFLAT!O;Sf!P:
(
( Fr.ET CFS
210. 0.
( 21 c. 100000.
MOI'nHL Y fqNJI'UM INSTRFAI' FLOIIS IN . CF S : ..
(
0. Q. 0 • o. 0. 0.
r ~ONT'-IL Y DIV[RSJC~ RfQUIREMENT<; IN CF S:
~. o. D. r. .• c 0 D •
f~ONTiiL Y RLSERVC\IP EV~PCRATJ(JN JrJ P!C li[S:
0. a. [·, 0. o. 0.
·r t.
r--...
0. 0.
0 0 0.
0. 0 •
o.
0.
G •
0.
c.
0.
-I
t)
0.
i)
·-· ,. ~ ·~··--· ··-.. .. ·------·-· ·····
0
0. 0.
0
c. 0.
0
0. 0.
0
0
,.__,
PROJECT 1'1!~7'J!l()l
lr\FLOWS T0 THJ: LtKE II\ CFS
YEAR JP! Fff' ~lA f.t APR
I ,, r o • :'.C7. 267. 3'33.
? fi77. :.P.CJ. 47G, 346.
3 633. ~ '• 1 • 4 71 • 470.
4 4<;8. 3~7. 315. ·"3 7.
5 364. 4~5. 33 2. 477.
6 419. :;> 1 s. 337. 3'.18.
7 3 :~ 8. .33E. 350 • 'tl 0.
A 5:" I • 44'.1, 384. RSO.
9 5~4. 51 0. 467. 630.
1 0 4fl5. 4e6. 500. 652.
11 497. 5 04. 550. 899.
r-'E~N 511 • 430. '104. 536.
r-'AX 877. ~P.Y. 550. 1'99.
Mil'! 364. 21S. . 26 7. 337.
Ct:Lr~CI AMI\;A PROJE.CT OPERATION STUDY
I /!'oH-"CF ofi[Cf.Tfl CJVJL&MJN[RIILS INC.,SF.
n~St<~ POWER I•Ult'f1RITY DATE 110581
~L HPI\Al IVE A: I'CARlt'UR SHORT TUNNEL• W/0 FISt-RELEASES
,.. f· y JUN JUL AUG SEP OCT NOV
3(-37. C:e:n. 11209. 9337. 3145. 1439. 799.
1 H\1, 7'>83. 12808. 10899. 6225· 1586. 843.
12t5. 7925. 13149. 10411. 5542. 1197. 863·
11'.~1. 4 735 •·-13:;>49 •. -· 12208 •. . 584 7. -· .2056·--·· 930. -·---·-
1 P.3 0. 8093~ 10700. 11798. 4246o 1245. 909.
1286. 3490, 13046. 10516. 10802. 2114. 597.
1 Bc;J3. 8 0 7,2. l!i303. 9974. 6608. 1953.· 910.
2030. 8761. 14931. 15695. 6191. 20'10. 1215.
299f:. 7808. 13117. 11257. 2793. 976. 689.
1948. -----9271 •. ---12510. .7297 •. 2793. .. 3057 .• ___ 1215·
22£-.5. 6789. 1C360. 7986. 2734. 1359. 742.
2076. 7251. 12307. 10671. 5175. 1729. 883.
363 7. 9271. 14931. 15695. 10802· 3057. 1215.
1265. .3490. .10303. 7297 •. 273'1. 9.76. ·-. 5'H•
PAGE 3 t:t
0
DEC ,AV[YR CAL YR .-,
870. 3220. 1960
696. 3 76 7. 1961
613. 3590. 1962 f)
710. 3587. 1963
662. 3'124. 1964
'166. 3641. 1965 ()
313. 3'159. 196E>
5 71. '1'173. 1967
612. 3532. 1968 I)
5'11. 3 396. 1969
'160. 2929. 1970
I)
592. 35'17.
870. 4473. f)
313. 2929.
I)
. t
0
'l
. i')
.:)
0
•,)
_) I
J
')
'"" C liA 1': II CI'A "1\/\ PROJECT OPERIIT!ON STUDY 0
fc/1!,1\&CF o[lECI-'TEL ClVILK~INERALS JrjC., SF. .. , PROJECT 111 117 9 C D 1 ALA.SKA POIJER ~U Hl(lR IT Y DATE 110581 PAGE 4
0
lllTfRNJITIVE A: MCARHiUR SHORT TUNNElt IUO FISt-RELEASES
~, POIJER R£l[ II SF II\ CFS
')
-, YEAR J AI~ FER MAR APR MAY JUN JUL AUG SEP OCT NOV DEC AVEYR CAL YR
')
3P.J~. ~I'P.G, ~356. 299?. 2793. 2635. 2530. 2597. 3079. 3282. 3910. '1288. 3246. 1%0
2 4014. 31< 7 7. 3443. 3149. 294 1. 2771. 2591. 2597. 2851. 3282. 3910. 4288. 3310. 1961 • 3 4 r 1 4. 3P77. 3536. 3149. 2941. 2771. 2656. 2659. 2851. 3282. 3911. 44 03. 3338. 1962 0
4 4CJ4, 3f77. 3536. 3149. 2941. 2845. "656. 2659. 2851. 3282. 3910. 4288. 3334. 1963
') 4 (1 1 4 • ~f•7f. ~536. 3149, 2941. 2771. 26~·6· 2659. 2851. 3282. 391lo 4403. 3338. 1964
6 4 c 1 ,, • ?.t:-77. 3536. 3149. 294 1. 21145. 2724. 2724. 2851. 3282. 3910. 4288. 3 34 5. 1965 0
7 4 0 I 4. 31!77. 3536. 3149. 2941. 2771. 2656. 2659. 2851. 3282. 3910. 4288. 3328. 196f
II 4014. 3A77. 3536. 3149, 2941. 2771. 2591. 2597. 2851. 3282. 3910. 4288. 3317. 1967
9 4014. 3P.76. 3444. 3149. 2f.f>5. 2771o 25';11. 2597. 2851o 3282. 3911· 4403. 3313. 1%8 0
10 4014. 3fH7. 3536. 3149. 2941. '2771.---2591. 2659. 2851. ---3282. -3910. 4288. 3323. 1969
1 1 4014. 3877. 3536. 3149. 28(,5. 2771. 2656. 2659. 2920. 3363. 4013. 44 05. 3352. 1970
' t)
t'EAN 3996. ~A~9. 3503. 3135. 291 4. 2772. 2627. 2643. 2878. 3289. 3920. lf330. 3322.
fJAX 4014. 3t77. 3536. 3149. 2941. 2845. ~724. 2724. 3079o 3363. 4013. 4405. 3352. f)
~IN ?;(\ 13. 3 (, !' 0. 3356. 2992. 2793. 2635. -2530. 2597. __ 2851. .3282. 3910 •. ... 4288. 3246.
')
r)
0
c)
·-·· -~·-· -·-·-. ---.. ---· -··-----· --
1)
<.)
L)
0
0
0
0
i
r~ ,-_.,, .-----. ~ --~~ ----~-,--:-:--._ ~-, :-------,..;::---=-. I
, ____ ..-------~. ,.-~--, -------r~/
"
PROJECT 14£179[01
., SPILL II\ ffS
YEAR JAN fEB ~lA R
o. 0 • 0.
;> 0. 0. 0.
3 0. 0. o.
4 0. 0. o.
'i 0. 0. o.
6 0. Q. o.
7 0. 0. o.
H 0. 0. o.
9 o. G • o.
1 0 o. 0. 0 •·
11 o. 0 • 0.'
f~E AN 0. 0 • o.
I' AX 0. 0. (1.
MIN o. c. 0 •·
--J ,--]"-'\,
·I, I :.
CHAKACI·Af'·NA PROJECT OPERATION STUDY
f-./lltllf.CF tB[Cj,Hl C I V Il & MIN FR A L S INC.,SF.
ALASKA P OIJER f•UTf'OR I TY
IILTrfiNATIVf A: MCARTHUR SHORT TUNNEL• W/C FISI-RELEASES
APR r·:A v JUN JUL fiUG SEP OCT
0. r.. o. 1417. 6740. 66. o.
0. o. o. o. 2437. 3374. o.
0. 0. o. o. 12l!8. 2691. o.
o. o. 0. o. ...-. 0 •· 23l!2o o.
0. Q. 0. 0. 87'1. 1395. o.
0. o. o. o. o. 3l!4l!. o.
0 • 0. 0. 0. 0. 1882. o.
0. o. o. o. 10188. 33'10. o.
0. 0. o. o. 4580. o. o.
0 •·" o. -·-o. -· 0 •. 0 •. o. . ·---· --0 •. __ :.
0. 0. 0. o. o. o. 0.
0. o. o. 129. 2370. 161l5. 0.
0. o. o. ll!17. 10188. 3l!'l4o 0.
o. o. '0 ... o. .. .. o •. 0 •· ,._ .. o •. ·-· .
.---..
DATE 110581 PAGE 5
NOV DEC AVEYR CALYR
o. o. 685. 1960
o. o. 'IBl!o 1961
o. o. 328. 1962
. .. o. o. 195. 1963
o. 0. 189· 196l!
o. 0. 287. 1965
o. 0. 157. 1966
o. o. 1127. 196 7
o. o. 382. 1968 . ... _.o. o. o. 1%9
o. o. Oo 1970
o. 0. 34 9 •.
o. 0. 1127. ')
,,_0. o. o.
0
0
f I I)
(' C 11 A K A C tl A M N A PROJECT OPERATION STUOY 0
h/HoH&CFoBECHTEL. ClVIL&MINERALS If,c •• sF.
<'l'
PROJECT 14879001 AUISK~ POIJER 1\UTHORITY OA TE 110581 PAGE 6
f)
ALTERNATIVE A: MCARTHUR SHORT TUNNELo 11/0 FISt-RELEASES
('
FJSti RELEASE IN CFS
0
-·-·---·---·-···
(' YEAR JAN FEf1 fJAR APR MAY JUN JUL AUG SFP OCT NOV DEC AVEYR CALYR ')
1 o. 0. o. o. o. 0. o. o. o. o. o. o. o. 1960
2 o. o. o. o. 0. 0. o. o. o. o. o. 0. o. 1961 (I 3 o. c. o. 0. o. o. o. o. o. o. 0. 0. o. 1962 )
4 0 0 0. o. 0. o. ------0. o. o. o. 0 0 --. o. o. o. 1963
('·
5 0. 0 • o. 0. 0. 0. o. o. o. o. . 0. o. o. 196'1
6 0. 0. o. 0 • o. 0. o. 0. o. o. o. o. o. 1965 ')
7 0. c. 0. 0. 0. o. o. o. o. 0. o. o. o. 1966
('
R 0. 0. o. 0. o. o. 0. o. o. o. o. o. o. 1967
9 a. ~ . 0. 0. 0. o. o. o. o. o. o. o. o. 1968 0
1 0 0. 0 • o. 0. o. o. o. ·-0 •. o. 0. ·--· .. ___ o •.. o • o. 1969
,. ' 11 0 • 0. o. 0 • 0. 0. o. o. o. o. o. o. o. 19 70 0
I'EIIN 0. 0. o. 0. Q" o. o. o. 0. o. o. o. o.
fJAX 0. c. o. 0. o. o. o. o. o. o. o. o. o. ')
I'. IN 0. o. o. o. ~. .. o. .. 0 •· 0 •· .o. o .• __ o ...... 0. o.
r)
0
0
0
··----· ------.---·
l)
0
C)
Q
0 !
0
0
~--,.-~-...... ,..._:;;.;;:-..\ ,----~~-,..__., ,--...., .....--;.;.~. ,--..........-·--_,--~ F"'~' ~-~ ....-~, '~ _,.,..~f
~()
r--~-. ,---1 I
PRCJECT l4R79C01
', NET EVt.FORAT ION IN AC-FT
'\ YEAR J~N FEE MAR
1 0 • 0. 0.
' 2 0. 0. o.
3 0. 0. o.
4 0. 0. o. -
1 5 0. 0 • o.
6 0. 0 • o.
7 o. 0. 0.
ll 0. 0. o.
'? 0. 0 • o.
I 0 0. 0. o.
11 0. 0. o.
i"UN 0. 0. o.
~AX ~. 0 • 0.
~IN o. 0. o.
.r-t; ,, I
C I! A I<~ C I· A I~ N A
~·.,I.:.
PROJEC1 OPERATION STUDY
l1 /II ol! 1'. C r , fl E C In E L CJVIl&r'.INERALS INc •• sr.
ALASKA POIJER AUTHORITY
AlTERNATIVE A: MCARTJ-IUR SIIOR T TUNNEl, W/C FIS~
APR MAY JUN JUl AUG SEP
Q. 0. 0. o. 0. o.
0. o. o. 0. 0. o.
0. o. 0. o. 0. o.
o. -c •· --Co--0. -· c. ... ···-0.
0. 0. o. o. 0. o.
0. o. c. 0. 0. o.
0. o. 0. 0. 0. o.
0. 0. 0. 0. o. c.
0. 0. 0. 0. 0. o.
0. o. ·--0. o. o. o.
0. o. 0. 0. 0. o.
0. o. o. 0. 0. o.
0. 0 • 0 • 0. 0. o.
o. 0. 0. 0 •. . . c. 0 •.
DATE uo5el
RElEASES
OCT NOV DEC
0. o. 0.
o. o. 0.
0. o. 0.
---Co-.... ---0. 0.
0. o. o.
0. o. o.
o. o. 0.
o. o. o.
o. o. 0.
o. ---C.·-···-·· o.
0. o. 0.
o. o. 0.
0. o. o.
o.-___ o. 0 •
PAGE
AVEYR
o.
0 •.
o.
o.
o.
o.
o.
o.
o.
c.
o.
o.
0.
o.
7
CALYR
1960
1961
1962
1963
196lf
1965
19'66
1%7
1968
1969
197 0
•.!I
; .
f)\
:_)
J
0
r ,
(
(!
(
(
(
'
PRCJECT
E.O.P.
YEAP.
2
:3
" 5
6
7
8
9
1 0
11
MEAN
r• A)(
MIN
14B79C01
STORAGE IN
Jt~i
31'23~~].
3331718.
3317673.
32743'39.
3336069.
3278243.
33062'34.
3314404.
33539~·0.
3246131.
33189~0.
3354649.
3fl23331.
3246l:'ilo
ACKf.-FT
FF£l I"AR APR
3f.?'i312. ~4~'i~85. 3284714.
3149100. 2966291· 279'i474.
3132389. 2943921. 27fl4482.
3071lF.97. 2880837. 271348'1.
31~8121. 2941106. 2782084.
3075077. 2878370. 2714647.
310%25. 2913717· 2750708.
3124011. 2930194. 2795151.
31E031E. 297727(,. 2827358.
:'1057793. 2871108. 27224'39.
3131 !"'32. 2947'382. 2814070.
31E2~85o 2971835. 2817152.
3£'2')312. 3439385. 3284714.
3057153. 2871108. 2"713484.
CHAKACI'M1NA PROJECT OPERATION STUDY
h/lloll&CF oOECIITEL CIVIU.MINERALS INc •• sr.
ALASKA POIIER AUTHORITY DATE 110581 PAGE 8
J1l TE P ~!AT IV [ A: MCARTHUR SHORT TUNNELt 11/0 FJSI' RELEASES
MAY JUN JUL AUG SEP OCT NOV DEC AVEYR CAl YR
~~~6f.37o ~58EE51. 403:"200. 4033200. 4033200. 3<;19884. 3734772. 3524610. 3698241. 1960
2734289. 304'1413. 3672605. 4033200. 4033200. 3'i28923. 37'16429. 3525568. 3413767. 1961
21:81421. 2988093. 3633277. 4033200. 4033200. 3905004. 372365'1. 340:0595. 3388909. 1962
2643365. 2755850.-3407174. 3994312. 4033200. 3557822. .. 3780505. .3560504. 33'10029. 1963
2713763. 3030432. 3525033. 4033200. 4033200. 3907956. 37293'13. 3499297. 338913'1. 1964
2El2861o 2651264. 3285913. 3765014. 4033200. ~5!:1388. 376'1256. 3529253. 3295790. 1965 f)
21:86245. 300H65. 3471855. 3921630. 4033200. 3951'189. 3772981. 3528571. 3370665. 1966
2739128. 3095546. 3854284. '1033200. 4033200. 3556838. 3796480. 3567933. 3'136697. 1967
2F35420o 31351'12. 3782341. 4033200. '1029735. 3887950. 36962'17. 3463126. 3431838. 1968
2661418 •.. 3041!183 •. 3658052. 3943232. 3939767. 3S25938._376557~ • . 3535188. 336'1574. 1969
2777185. ~OH272o 3489967. 381750'1. 3806440. 3!:83224. 3'188577. 3246018. 329'1813. 1970
2765612· . 3032137. 361~427. 3967354. '1003776 • 3907856. 3727166. 3'197333. 3402223.
3~36637. 351lH51. 403~200. 4033200. 4a332oo. 3%1388. 3796'180. 356 7933. 3698241.
2f']?8blo ::·651264. 3285913. 3 7(,50 14. 3806440. 3~1!322'1 .• 3'188571 .• 3246018. 3294813.
r)
{)
0
0
0
0
----· ___,_
' '
'"
.,
CHI·I':Act'AMI\A PROJECT OPERATION STUDY
li /11,1 i &r: F , [1 E C liTE l CIVJL&~IJN(RALS INC.,SF.
' PROJ[(T 141l7'3G01 /\LASKA POwER AUTHORITY DATE 110 581 PAGE <;
~LTERNATJV[ A: f·1CARTIIUR SI!OR T TUNNEL, 1.1/C FIS~ RELEASES
lolA l[R BALANCE
' H AR J f. ~J rEf' I'AP. APR I'AY JUN JUL AUG SEP OCT NOV DEC AVEYR CALYR
0. 0. 0. 0. 0. 0. 0. 0. 0. o. 0. 0. 0. 1960
2 c • ~ . o. 0. 0. o. o. o. o. 0. o. o. o. 1961
3 o. ( . c. 0. 0. 0. 0. 0. o. 0. o. 0. o. 1962
4 0. 0. o. 0 0 o. . ... 0. u •. o •. o. 0 ...... c·O • o. o. 1963
5 0. c. o. 0 • c. 0. 0. 0. o. 0. o. o. o. 1964
6 0. 0. 0. 0. o. o. o. 0. o. 0. o. 0. o. 1965
7 0 • o. 0. 0. 0. o. 0. 0. o. 0. o. 0. o. 1966
fl 0. c. D • 0. o. o. c. o. a. 0. o. 0. o·. 1967
9 0 • c • c. 0. 0. 0. 0. o. o. 0. 0. o. o. 1968
10 0. 0. o. 0. o. 0. o. o. .. 0. .0 .... o. o. o. 1969
11 o. 0. o. 0. o. 0. 0. o. 0. o. o. 0. o. 1970 f)
MEAN o. 0. 0. o. c. o. o. 0. o. 0. 0. 0. o.
I' AX 0. 0. 0. 0. o. o. 0 • o. o. o. o. 0. o.
f'I,[N (). o. o. o. 0 •. ............ o .• o ... . __ .... o .• -· . 0. . ............ 0 .... -. .. ..... ..0. o. o.
r)
0
0
·.)
,')
0
)
0
I'
!'• l.lif. ~A CHAMNA PROJECT OPfRATION STUDY 0
1·/IJeli&CF oi3ECIHEL CIVIL&I'H<ERI\LS INc •• sr.
('•
PRCJECT 141\7~<·~1 ALASK~. POWER ~UTI-lOR IT Y DATE 110581 PAGE 1 0
0
HTERNAT!VE A: HURTI'UR SHORT· TUNNEL, 11/0 FISI-RELEASES
POWER II\ ~11oJ C• ')
('•
YEAR J~.N f[[l MAR APR 1'-l~Y JUN JUL AUG SEP OCT NOV DEC AVEYR CALYR
)
2 11 0 0 ~27o 203. 103. 1f-7o 162. 159o 167. 183. 209. 24 0. 261. 200o 1960
;> 240. 227o 203o 11'3. 167. 162. 159. 167. 183. 209. 240. 261. 200o 1961 C• 3 24Co 227. 203. 183. 167. 162. 159. 16]. 183. 209. 240. 261. 200. 1962 ' )
4 240. 227o 203. 183. 167. ····· 162 ............ .... 159 • .... __ .... 167 •. 183 • 209. --240. 261. 200. 1963
5 240. 227. 203. 183. 167. 162. 159o 167. 183. 209. 240. 261. 200. 1964 c 6 240. 227o 203. 183. 1C: 1· H:2. 159. 167. 183. 209. 240. 261. 200. 1965 0
7 240. 227o 203o 183. H. 7 0 162. 159o 167. 183. 209. 240. 261. 200. 1966
ll 240. 227o 203. 1e3. 167o 162. 159. 16 7 •· 183. 209. 240. 261. 200. 1967 ('-9 240. 227. 203. 1e3. 167e 162. 159. 167. 183. 209. 240. 261. 200. 1968 0
1 c 240. 227. 203. 183. 167. 162. ... ··-159.-. -... 16 7 • .183. ·---· 2 09. 2!1 0 • 261. 200. 1969
(• 11 240o 227o 203o 1133. 16 7. 162. 159. 167. 183. 2 09. 240. 261. 200. 1970
0
~·E ~N 2 4 0 ·-2~7. 203. 183. 167. 162. 159. 167. 183. 209. 240. 261. 200.
(• I-' AX 240. 22 7. 203. 1P.3. 1107. 162. 159. 167. 183. 209. 240. 261. 21i0o C)
~lIN ('40. 227. 203. 183. 16 7. 162. 159. 167. 183. .. 209 •. --24.0. .. 261. 200 •
C• r)
(' I)
C· 0
0
c t)
0
i,)
()
0
0
0
----. ---..., ,----._, ...... ~ . ,_;~
,,..., __
~-;:---..., --........... ,......~ ......... --_'? ,____q
r---"-.....,_..,, r:,.,........ _........_..,;,_,., .-....__.,
'
.rr-t· !!
-'·
~ C flAK A Cl' ~ NtJ A PR(;J[CT OPERATION STUDY
1-/ll,fii;Cr ollECI,TEL CIVJL&MINERALS INC.oSF.
. ' PRCJECT 14117'3001 AlftSKJ\ POWER ~UTIICRITY DATE 110581 PAGE 11
ALTERNATIVE A: MCAR TI'UR SHORT TUNNELo W/0 FISt-RELEASES
-, UiERGY IN ~!loll'.
YEAR J f.rll rEP MAl'\ APR ~\A y JUN JUL AUG SEP OCT NOV DEC TOTYR CALYR
171\5£..0. 157'H:?. 1513811. 131478. 124216. 11f452. 118393. 124216. 131478. 155270. 172800. 191!087. 1756299. 1960
;> 178~;(-0. 152515. 151388. 131471lo 124216. 116452. 11P.393. 12'1216. 131'178. 155270. 172800. 194087. 1750852. 1961
3 171l~~Q. 1~·251~. 1513f./1o 13147!1. 124216. 116452. 118393. 124216. 131478. 155270. 172800. 19'1087. 1750852. 1962
4 17B!if>O. 15?515. 15138R. 131478. 124216. 116452. .118393. 124216. 131478. 155270o_._172800o. 19'1087. 1750852. 1963
5 178%0. 1579~2. 1513f:'(l. 1314 78. 12421(,. 11645?. 118393. 1?4216. 1.31478. 1!:5270. 172800. 194087. 1756299. 1964
6 '1785(,0. 152~15. 1~13fl.ll. 131478. 12'1216. 116452. 11P393. 124216. 131478. 155270. 172800. 194087. 1750852. 1965
7 17R%0. 152~1~. 1~1388. 13147Ao 124216. 1H452o 11E'393o 124216. 131478. 155270. 172800. 194087. 1750852. 1966
A 17A5!oO. 152515. 1~1388. 131478. 124216. 116452. 11£<393. 121!216. 1314 78. 155270. 172800. 19'1087. 1750852. 1967
9 178560. 15791'?. 1!:13811. 131478. 124?16. 116452. 111'393. 124216. 131478. 155270. 172800. 194087. 1756299. 1%8
1 0 178560. 152.515. 151388. 131478. 124216. 11(,452 •. 118393. 124216 •. . 131478. 155270 .• -~-172800. ..191! 0 8 7. 1750852. 1%9
11 1785€:0. 152515. 1~131\8. 131478. 124216. 116452. 118393· 124216. 131'178. 155270. 172800. 19'1087. 1750852. 1970
OlEAr. 1 785(:0. 154f'CO. 151381l. 131478. 124216. 116452. 118393. 12'1216. 131'178. 155270. 172800. 19'1087. 1752338.
I" AX 178~f0. 1579E2. 1~1388. 131478. 124216. 116452. 118393. 124216. 131478. 155.270. 172800. 194087. 1756299.
"'I< 178560. 15?515. 151388. 131478. 124216. .116'152 .• -.118393 •.. 12'1216 • 131'178 •. .1552.7.0 .• __ 172800 .• .19'1087. 1750852.
(_)
r')
0
\..)
0
('
('
('
('
c·
(
(
(
(
(
(
(
(
c
(
PRCJECT 14f75801
REMAINI~G SPILLS I~ CFS
YEAR
1
2
lf
5
6
7
p.
9
1 0
11
I', A X
MltJ
J~N
0.
0.
c 0
o.
c 0
0.
0 0
0 0
0 0
0.
c.
G o
~ .
0 0
FEP.
0 0
0.
0.
0.
c 0
0 •
O·o
0.
0.
0.
0 0
c 0
r o
G •
I'AR
0.
o.
o.
o.
0 0
o.
o.
c.
0 0
o.
0 0
o.
Q.
o.
-
Cllf•KACf'A~1NA PROJECT OPERATION STUDY
h/Holf&CFoBECiiTEL CIVIL&MINERALS INCetSFo
~LASKA POWER ~UTIIORJTY
ALTERNATIVE A: ~lCAR.TIIUR SHORT TUNNELt W/0 FISI-RELEASES
APR
0 •
0.
0 •
0.
0.
Oo
0.
0.
0 o'
o.
r •
Q •
c II
0.
!-.......__
MAY
o.
o.
o.
0.
0.
o.
o.
0.
o.
0.
0.
r •
c.
(; .,
-
JUN
o.
0.
0.
.. 0.
o.
0.
0.
o.
0.
0.
0.
o.
0 •
G •
JUL
0.
0.
o.
c ....
o.
o.
0.
o.
0.
0.
0.
o.
o.
o.
AUG
3170.
o.
o.
.0 •
o.
o.
0.
6619.
1011.
o.
o.
982.
6619.
.o .•
SEP
0.
38.
o.
o.
o.
108.
o.
It.
o.
0 •.
o.
108.
.. o.
OCT
0.
o.
o.
0.
0.
0.
o.
o.
o.
.. ......... ··-0 ..... ..
o.
o.
o.
.0 .......
DATE 110561
NOV
0.
0.
o.
... 0.
o.
o.
o.
o.
o.
.0.
o.
o.
o.
.... 0 .......
DEC
0.
o.
0.
o.
o.
o.
0.
0.
o.
0.
o.
o.
o.
0 •
PAGE
AVEYR
26'to
3.
o.
o.
o.
9.
o.
552.
84o
o.
o.
83.
552.
o.
------..,
12
CALYR
1960
1961
1962
1963
1964
1965
1966
1967
1968
1969
1970
")
')
'),
')
0
0
0
0
0
..---, r"'1"'""""''
' •. I -~-
I"'
.,
C tlf, K A C f' AM N A PROJECT OPERATIOtJ STUDY
1/H,H&CFoBfCiiTEL CIVIL&MINERALS JNc.,sr.
PRCJECT 14117%01 ALASKA POIIER AUTIIORITY DATE 110581 PAGE 13
1
HTERNATIVE A: MCAR TI!UR SHORT TUNNELo 11/0 FIS~ RELEASES
.. , AVERAGE GENE~,q lr·'' Iri rll-.! DLR HJG SP 1L L S
YEAR J r.N r fP MAR APR M~-y JlJN JlJL AUG SEP OCT NOV DEC AVEYR CAL YR
0 • 0 • o. 0. 0. 0. 256. 400. 188. o. 0. 0. 70. 1960
;> 0. 0. 0. G • ~ 0. 0 0 327. 400. o. o. o. 61. 1961 v •
:z. 0. Q. o. 0. 0. 0. o. 253. 358. o. o. o. 51 • . 1962 0
4 " 0. o. n 0 • ·---0 •· 0 ... o. 336 •. 0.--..... o. o • 28. 1963 v. v.
!) 0. 0. 0. 0. 0. o. o. 229. 275o 0. o. 0. 42. 1964
6 o. 0. 0. 0. o. 0. 0. 0. 400. 0. o. o. 33. 1965 f)
7 0. c • 0. 0. o. o. o. o. 306. o. o. o. 25. 1966
8 o. 0. 0. o. o. 0. o. 400. 400. 0. o. 0. 67. 1967
9 c • 0. 0. 0. 0. 0. 0. 400. o. o. o. 0. 33. 1968
l 0 0. a. o. o. o •. ·-0 0-------. o. 0"" Oo ..... 0 •. -· . .... 0. 0 • o. 1969
1 1 o. o. 0. 0. 0. 0. 0. o. o. o. o. 0. o. 1970 f)
MEAN o. 0. a. o. o. 0. 23. 183. 242. o. o. o. 37.
t-:A~ 0. c. c. 0. 0. o. 256. 400. 400. 0. o. 0. 70.
MIN 0. 0. 0. o. c. 0 • 0. ..... 0. o • .. o .•. __ . __ o. ·-o. o •
0
0
<)
<)
,)
0
''
:1 CI'-~KACt'AM~;A PR('J£CT OP[RATION STUOY 0
~ll!tii!:CF oBECtiTEL CIVlLKMINERALS INC.,SF. .. , PROJECT l41l79f'Ol ALAS I': A POWER AUTHORITY DATE 110581 PAGE 14
" 0
AlTERNATIVE A: MCARTIIUR SHORT TUNNELo 11/0 FIS~ RELEASES
~~ SL:RPLUS n;r R G v lfl I' loll;
f)
~ ·----· -------------------------------------.
~\ YE~.R JAN FEr. MAR APR MAY JUN JUL AUG SEP OCT NOV DEC TOTYR CALYR
0
1 0. 0. o. 0. 0. o. 72279. 173384. 4167. 0. o. 0. 249830. 1960
~, 2 0. 0. o. 0. o. o. o. 1187117. 156522· o. o. o. 275269. 1961
3 0. 0. o. 0. o. o. o. 64330. 126l!89. o. o. o. 190819. 1962 0
4 0. 0. o. o. o. . 0.-···-·-· ··-···-0 •·· -----0 •··-110265 •. . 0. --. . .. 0 • 0 • 110265. 1963
.. , 5 o. o. o. 0~ o. 0. 0. 46308. 66163. o. o. 0. 112ll71. 1964
6 o. 0 • o. 0. o. 0. o. o. 156522. o. 0. o. 15.6522. 1965 ()
7 c • 0. o. 0. o. o. 0. 0. 88832. o. o. 0. 813832. 1%6
A 0. 0. o. 0. 0. o. 0. 173384. 156522. o. o. o. 329906. 1967 0 9 0. G • 0. I 0. c. 0. o. 17338l!. o. o. o·. 0. 173 384. 19613
1 0 0 •. 0. o. 0. o. (). 0. o. o. 0 ·-·-··· ··-0. --·-· o. o. 1969
11 0 • 0 • o. 0 • 0. 0 •. o. o. o. 0. o. 0. o. 1970 0
t'EMJ o. n o. 0 • [', 0. 1':571. 68140. 71J680o 0. 0. o. 153391. ...
I-' AX 0. 0. 0. 0. 0. 0. 7:>279. 173384. 156522. o. o. 0. 329906. (j
~qN 0 0 0. ::. o. c. . o •· 0 • .. 0 •. o. ... 0 •. _o • 0. o.
r)
i)
-··---------······· -------·---------·
0
<)
. -· ---------------·--. --· ---. ----------------~ -·----------------·
0
0
i.)
()
Q
0
0
,.._.__ ,__~~ ,....,....-, ,..--., ~-""-; ~ r--r---.., ~. ~
~~ ,--.,..,~ --,.......,.__
I
FPUJECT l487~r21
INSTALLED CAF&CilY: J3~JOD. KW
ANNUAL PLANT fAClfk: .~
OVERLOAC FACTrR: 1.00
PLANT EHICIE''CY:
FAICTIC~ LOSS CCfFFICIENT! .0000~2!70
f'ONTIILY L(IAO FfiCTOPS:
C~ft~AC~AM~A PROJFCT OPERITION SiUDY
1:/!:,P<.rr oi3ECHTEL C1Vll&MlNEF\ALS HIC .. sF.
ftLAS~A PG4ER AUTPORITY
-
01\H 110581
I.LHHI.AT!Vf: F.: f'CAI<Tt!UR SHORT TUt~f~EL• WITH Fist-RELEASES
.920 oA70 .760 o7CD o64D o620 .610 .640 .7rD .800 · .920 1.000
l~lTJAL LAKE STCRAGE :4033200. AC-FT
MINIMUM LAKE STCRAGE Oo AC-FT
MAXIMU~ LAKf STCRAGE :4033200. AC-FT
-
PAGE
0!
0
').
l)
•).'
r)
0
0
0
PROJECT l4079u01
RFSERVOIR STORAGE-ELEVATJOf\-AREA:
AC -F T FFET ACRE
0. 760. 0.
2025. 76">. a 1 o •
7300. 770. 1300.
27200. 7AC. 2690.
lll.COC. I' GO. 5670.
24l~OC. f2Go 7320.
397000. r3 4 r. 0270.
57?~00. 1'1'>0. '?2130.
76'.?COG. f<" c 6 104CC.
9f11'COQ. '! c 0. 11590.
1224000. t;=?O. 119f0.
14E-7000. 1)40. 12320.
1717CCO. r:: (: (l 0 12(,~(..
1573000. 9 f~ (I • 12'180.
223HCO. 1000. 13?.110.
25Q4QOO. 1 n c. 13520.
2771'000. 1 H O. 13740.
3053000. 1~60. 139E-Oo
3335['00. 10110. 14170.
3f2C;OOO. 110 0. ]11390.
3C.lncco. 112Go l4n20.
'1033200. 11?fo 1521?.
TIIIUJAHP-FL0\.1 PFLA Tl fi\SI'J P:
FFET CFS
210. o.
210. 100000.
MONTHLY f~H~HHH1 INSTRf.H FLOWS IN CFS:
CHAKACHAMNA PROJECT OPERATION STUDY
I' /II til & C F , 0 E C tHE L C I V ll & M HJ ERA L S INC. , SF •
ALASKA POI.JER AUTIIORITY DATE 110581
ALTERNATIVE A: MORTI!UR SIIORT TUNNEL, WITH F IS~ RELEASES
365o 3f5o 3f5o 1Q54o 1094o 1094o l094o 1094o 1094o ~f5o 365o 365o
MONTI'LY DJVERSJUf\ R[QUIREIIEr:TS IN CFS:
o. 0. c • 0. 0. 0.
MONTIIU R[_S[RVOIR I"VAPCRATION IN INCHES:
0. ~. (I. G •
,-_,.._
'
0. o.
0. 0. c. 0. 0. 0.
0. o. 0. 0. o. o.
I')
PAGE 2 ,
")
~
f)
f)
I)
')
')
f)
I)
')
·)
.)
.)
)
J
J
,J
0
0
~ .--...--, .-...-:
''
r-~ ,.._._,, ,-,
' '
Cllf. Kf.CI·AMNA PROJECT (lP[RATJON STUDY
Ulloii&Cf oBECiiTEL CIVIL&MINERALS INC.oSF.
PRCJfCT 1'tl!7 <; i' 0 1· ALASKA PO~J[R AUTHORITY
ALTEiiNATIVE o: 11CAR H'UR SHORT TUNNELo WITH
INFLOWS TO n;r LIIKE II\ CFS
YEAR J~N rE£1 ~AR /IPR I'AY JUN JUL AUG SEP
' 1 4ro. 307. 267. 393. :,(..j7. 6837. 112C9, 9337. 31'15.
;> 877. SP.9. 470. 346. 1 f r 1. 7983. 12A08, 10899. 6225.
3 6.13. 5 41 • 4 71. 470. 12t-::5. 7925. 13149. 10'111. 55'12.
lj '• ') (!. ~!:7. 315. 337. l 8 0 I • lj 735. 1~249. 12208 •. 5847.
5 3Glt. 4:.'!5. 3.32. 4 77. 11'.30. 8093. 1£'700. 117'Hl, 4246.
6 419. 21'3o 3.37. 398. 1256. 3'190. 130'16. 10516. 10802.
7 3 '~ e • ~3(,, 350. 410. 18'J3. 1'072. 1(~03. 997'1. 6608.
8 5~1. 4'15. 384. BllO, 203C. f:l761o 14931. 15695. 6191.
9 534. "10. '167. 630. 2996. 7AOB, 1:3117. 11257. 2793.
1 0 4h!'l. 4F.f':. 500. 6!32. 1'340. . 9271. 12510. 7297 • 2793.
11 4'-;7. c04o 550. E'?'l, 22F.5. f.789. 10360. 7986, 2734.
I'[ AN 5 11 • 4~0. '10'1. 536. ~C7f.. 7251. 12307. 10671. 5175.
f'AX 877. 5P.9. 550. 899. 3(:37. 9271. 14931. 15695. 10802.
!'IN 364. 219. 267. 337. 1265. ·-349 0. 10303. 7297. 27~4.
--. ..._,
I
DATE 110581
FIH RELEASES
OCT NOV DEC
1'139. 799. 870.
1586. 843. 696.
1197. 863. 613.
2056. 930. 710.
1245. 909. 662.
2114. 597. 466.
1953. 910. 313.
2040. 1215. 571.
976. 689. 612.
3057. ---1215 •. 5'11.
1359. 742. 460.
1729. 883e 592.
3057. 1215. 870.
. 976. 59.7 .•. -313.
f)
PAGE 3
f)
0
AVEYR CALYR
')
3220. 1960
3767. 1961
3590. 1962 f)
3587. 1963
3424. 1964
3641. 1965 I)
3459. 1966
4473. 1967
3532. 1968 ')
3396. 1969
2929. 1970
0
3547o
4473. 0
2929.
t')
()
()
()
()
,)
0
0
Q
0 i
I
!
0 I
I
0 I
I
-)
CI'I,KACLMit~A PRG.JECT OPERATION STUDY
I n:,H.CF.flECtiTfL CIVIL&MIHRALS INC.,SF.
.. , PRCJECT 1 11 117<1 ( pI nASK/1 P OI·!ER AUTI!GH I TY DATE 110581 PAGE 4
Al TEI<t•!A T I VE E: .f·,CARTiiUR SHORT TUNNEL, \IIJH F I Sl-RELEASES
-, POWER RELEf.S[ lrJ CFS
YEAR J f· N FEP fo:AR APR ~;A y JUN JUL AUG SEP OCT NOV DEC AVEYR CALYR
1 31 C 11 o ::>sc;e. 2739. 2448. 2232. 2160. 2075. 2130. 2335. 2682. 3180. 3475. 2630. 1 '36 0
2 32£.0. 3 1 ~ 1 • 21109. 2573. 234 5. 226'3. 2125. 2130. 2335. 2682· 3180. 3475. 26'34. 1 '361
3 32f-O. 3 1 ~ 1 • 280'3. ;:>5 73. 2 3'• 5. 2269. 2125. 2180. 2335. 2682. 3180. 3475. 2699. 1962
4 32(, 0. 3151. 2809. 2573. ~345. 2269 •. ---217 7. 2180 •··· .2335. -2682o-318 0 •. 34 75. 2703. 1963
5 3260. 3151. 2809. 2573. 2 34 5 e 2269. 2177. 21/lOo 2335. 2682. 3180. 34 75. 2103. 1964
6 32r;o. 3151. 2809. 25 73. 2345. 2328. 2231. 2232. 2336. 2682. 3180. 3475. 2717. 1965
7 3 2 (, 0 • j 151. 21l09. 2573. 23'15. 2269· 21 77. 21110· 2335. 2682. 3180. 3475. 2703. 1966
8 3?. (· 0. 31!'1. 2809. 2573. 2 34 5. 2269. 2125. 2130. 2335. ·2682. 3180. 3475. 2694. 196 7
9 32"0· 3072. 2809. 2573. 23'15. 2213. 2125. 2130. 2335. 2 682. 3180. 3564. 2!:91. 1'368 1)
1 0 32(.0. 31~1. 2881. 2573. 240 6 •. ·--2269 ... ·-· 2125 •. . 2180 ... 2390 • --27116.----3180 .•.. ... 3564. 2127. 1969
11 326C. 31!:1. 21!81. 2573. 2345. -2269. 2177. 2232. 2390. 2813. 3260. 3658. 2 751. 1970
~EAN 32'16. 3130. ?.815. 2562. 23'1 0. 2260. 21'19. 2171. 23'15. 2699. 3187. 3508. 2701.
~AX 3 2 (, 0 • :'.1 ~ 1 • ;>lllll. 2573. 24G6. 2328. 2231. 2232. 2390. 2813. 3260. 3658. 2751. f)
fo:IN 31C'I. 2CJSL!. 2739. 2'1'18. 2232. 2160. 2 0 75 •. 2130 ... 2335. ... 2 682. --3180 •. 3475. 2630.
i)
,)
IJ
r---.
~,
PRCJECT 14!!7'lC01
SPILL II\ CFS
YEAR JAN f[fj "AR
1 c. 0 • 0.
;> 0. 0. o.
3 0 0 0 • 0.
4 0 0 0. o.
5 n. 0. o.
f, 0. u. o.
7 0. 0. o.
8 0 •. o. o.
9 Q. c • 0.
10 n. 0. o.
11 o. 0 • c.
I'EAN 0. 0 • 0.
r-'AX c. 0. o.
~~ J N o. 0. o.
--','! I
r-l, J -'
Cllt,KAChAMNA PllCJECT OPERATION STUDY
~llloi!&CFoBECHTEL CIVIL&MINERALS lNCetSF.
ALASKA POIIER AUTHORITY
AlTERNATIVE A: ~'CARTIIUR SfiOR T TUNNEL, WITH
. --·---------
APR MAY. JUN JUL AUG SF.P
0. 0 0 o. 836. 6113. o.
D • o. o. 0. 2062. 2796o
0. 0. 0. 0. 1218o 2113.
c. o. o. .o. o. 201:5.
0 • o. o. o. 831. 8-17.
o. o. 0. o. o. 3180.
0. o. 0. 0. 0. 1321.
o. c. o. o. 9736. 2762.
0. 0 • 0. 0. 4288. > o.
0. G. > 0. 0. 0. o.
0. c. o. 0. 0. o.
0. c. 0. 76o 2206. 1368.
0 • 0 0 0. 836. 9736. 3180.
0. o. . o. o • > 0. o.
'
-.
DATE 110581 PAGE 5
FIS~ RELEASES
I '
f")
I f")
I I)
OCT NOV DEC AVEYP CAL YR
f)
o. o. o. 579. 1960
0. o. 0. '106o 19.61
o. o. o. 278. 1962 0'
-0. >--0. o. 172. 1963
0. o. o. 137. 196'1
o. o. 0. 265. 1965 f)
o. o. 0. 110. 196 6
o. o. o. lOifle 1967
0. o. o. 357. 1968 f)
0 ·--->>> 0. 0. o. 1969
o. o. 0 0 o. 1970
')
o. o. o. 30'\o
0. o. o. 1041. 0
o. __ a. o. o.
1)
')
c)
.-)
•)
\)
0
()
Q
0
0
0
()
('. PRCJECT 14879001
(.• I' J Sli RELEASE JN CF5
('· YEAR JAN FEE f'AR
1 365. 307. 267o
C· 2 3~5e 365. 365o
3 3(·. 50 .3f.5. 365o
4 3f.5o ~57. -315.--
c 5 3!J4o 3f:5e 332o
(, 3F5o 219. 337.
7 365o 3~(: 0 350o
C'· !' 3f.5. 365. 365.
9 3fi5o .365. 365.
1 0 3€-5" 3(:5. 365.
(' 11 3&5. 3E~o 365o
MEAN 365. 343. 345o
( f'AX 3f-.5 0 3f:5o 36!'io
MIN 364. 219. 267o
('
(
J
CIIAKACI\/l~lt\/1 PROJECT OPERATION STUDY
f./lloH&C:F,nECHTEL CIVIL&~1lNERALS INC.,SF.
~LASKA POWER AUTHORITY DATE 110581
ALTERNATIVE B: MCARTIIUR SHORT TUNNELo WITH FIH RELEASES
APR MAY JUN JUL AUG SEP
393o
1094. 1094. 1094. 1094. 1094.
1094. 1094. 1094. 1094. 1094.
··---33 7 0 ............. .} 0-9 4 o -----·1 0.94 o----1-09 4-o----· -10.94 •-·-----1 0 9 4 •--
477o 1094o 1094o 1C94o 1094o 1094o
398.
41 0.
1'80.
630o
1094. 1094. 1094. 1094. 1094o
1C94o 1094e 1094o 1094o 1094o
1C94. 1094. 1094. 1094. 1094.
1094. 1094. 1094. 1094. 1094.
652o ··· 1094o ------l094e------1094o----·---.. 1094o-----l094o
899. 1094. 1094. 1094o 1094. 1094o
5~6.
899.
337.
1094o
1094o
1094.
1094.
1094.
1094.
1094o
1094.
1094.
1094o 1094o
1094.
10.9 4.
OCT NOV DEC
365. 365. 365.
365. 365. 365.
365. 365. 365.
.... 365·----'--· .365.------365.
365. 365. 365.
365. 365. 365.
365o 365o 313o
365o 365o 365o
365. 365. 365.
----365.----365. ·-----365.
3~5. 365. 365.
365. 365.
365. 365.
365..... . 36.5 •.
360.
365.
.. 313.
PAGE 6
AVEYR CALYR
658.
667.
677.
662 •
675.
657.
664.
71-2.
(:91.
693.
713.
679.
713.
657.
196 0
1961
1962
1963
1964
1965
1966
1967
1968
1969
1970
--
0
I)
0
f)
0
,)
-.
CHAKACI·M~NA PROJECT OPERATION STUDY 0
1./1~ oi!F.CF eBEChTEL CIVIL&~PJERJILS INC.,Sf.
PROJECT 14A7Y001 AL~.SI<A P 0 ~~ E R AUTHORITY DATE 110581 PAGE 7
I")
AL TEiiNATJVE fl: MCARH:UR SHORT TUNNELo \.liTH f!S~ RELEASES
NrT EVA FOR AT I 'HJ H! AC-FT
0
-'
YEAR ,Jf>N FEP. MI.R /,PR MAY JUN JUL AUG SEP OCT NOV DEC AVEYR CALYR
0
0. u • 0. 0 • 0. 0. o. 0. o. 0. o. o. o. 1960
2 a. 0 • 0. 0. o. o. 0. 0. o. 0. o. 0. o. 1961
3 0. c • 0. 0. 0. 0. 0. 0. o. o. o. 0. o. 1962 0
4 c. c • o. 0. o. . o. 0 .... ··-0. o • . o. o. 0 • o. 1963
5 0. r • e. 0. 0. 0. 0. 0. o. 0. o. 0. o. 1964
6 0. 0. 0. 0. 0. o. o. o. o. o. 0. o. o. 1965 0
7 0. D • o. 0. o. 0. 0. 0. o. o. o. o. o. 1966
8 0. 0. o. o. o. o. o. o. o. o. o. 0. o. 1967
9 e. 0. o. 0. o. 0. o. 0. o. o. o. o. o. 1968 0 '
10 o. 0. o. o. c. ... o." 0 •· o. o • ... 0 ....... ... 0 ·-· 0 • o. 1969
11 0. 0. 0. o. 0. 0. o. 0. o. o. o. o. o. 1970 ()
MEAN 0. 0. 0. 0. 0. 0. 0. 0. o. 0. o. o. 0.
~lAX 0. 0 • o. 0. o. 0. o. 0. o. o. o. o. o. r')
IHN 0. c. o. o. c. 0. o. 0. o. -0. ·-... 0. 0. 0 •
1)
')
<)
'.J
i)
0
0
0
()
0
Q
0
~,
Cf'AKAct•AMNA PR('JECl OPF.RATION STUDY
f'll:oH&CF,OECHTEL CIVILUIINERALS INCooSF.
~, PROJECT 14137'JU01 ALASKA P0~1 ER ~UTHORITY DATE 110581 PAGE fl
HTE~NATJVE o: fo'CARTHUR SHORT TUNNEL• II I T11 FISI-RELEASES
-~ E.O.Po STORAGE Ih. AC:RE-FT
'• YE 1\R JAN FF[i MAR APR "'A y JU.N JUL AUG SEP OCT NOV DEC AVEYR CALYR
31:4 4 41' 6. 36720~1. ~50~609. 3357932. 3~770!'!4. ~59C235. 4033200. 4033200. 4016273. ~51 7430 o 3754049. 35714 03. 3722577. 1960
'I 2 3402437. 3239t>e5. 3073650. 2920553. 2824773. 309%75. 3689300. 4033200. 4033200. 3543396. 3782633. 35£19288. 3469332. 1561
3 3405319. 324C1C1. 3073928. 2920830. 2787174. ~051H:25. 3669218. 403320(!. 4033200. 3<;;19477. 3759904. 3561456. 3ll55203o 1962 1)1
4 33£91116. 315ll1<;;:'i. 3021502. ·286£1358. 2767700. 2849328o-~462870o--ll012209o-ll033200o 3 c;; 7 2 2 9 5 •. 3 816 7 0 9 •. 3624225. 3415984. 1963
-·5 3't237'37. 3246581. 3(!73891. 2920753. 2821878. 3103326. 3560138. 4033200. 4033200. 3522428. 3765593. 3570158. 3456249. 1964
I . 6 3."H30?-0o 3158037 • 30253H>o 2872242. 2739877. 2743529. 3341621. 3783716. 4033200. 3975861. 3800460. 35<;; 2974. 3373358. 1965 I)
7 3393940. 32H':i47. 3046256• 2893152. 275El110. 307e308o 3510710. 3922686. 4033200. 3965961. 3809186. 3595489. 3438829. 1966
-8 34V!J247o 3234C:20. 3063397. 2910300. 2e23682. 3144879. 386!'!042. 4033200. 4033200. 3971311. 3832684. 3631653. 3495793. 1967.
\ 9 3441617. 3273230. 31 061)1 ().. 2953713. 2926492. 3194307. 3802931. 4033200. 3995328. 31!68016. 3698073. 349'1111Jo 3482320. 1968
1(l 33\11049. 3132755. 2963905. 2810801.-2715393. 3066938o~363R240o . 31185616. 384lt473. ~841176 • .3702533. 3494213. 3366lt25o 1969
11 3301Ril1. 3134~<;1. 2968811. 2 8,15 7 0 7. 27lt35lt9. 2947400. 3383303. 3669834. 3625181. 3513341. 3341792· 31:22697. 3214007. 1970
I'E AN 3423817. 325320P.. ~083737. 2931311. 2£'47790. 3075723. 3632416. 3952114. 3973968. 3851881. 3733056. 3531607. 3444552.
r'AY 31"14411 6. 36720~1. 3503609. 3357932. 3377054. 3590235. 4033200. 4(!33200. 4033200. 3975861. 3832684. 3631653. 372<'571.
r'IN ?,3n1 04'Jo 31327!)5. 2963905. 2810801. 27153911. £743929. 3341621. 3669834. 3625181. 3513341. 33417.92. 3122697. 3214007-o
i)
.J
J
-
r--
l -
FRCJECT ]4!179 11(•1
WATER f'HANCF
YEAR JJIN
0.
2 c •
3 0.
4 0.
5 o.
f. 0.
7 a.
!l o.
"' 0.
1 0 o.
1 1 c •
I'[MJ 0 •
"AX 0 •
MIN 0.
F[P "AR APR
c • 0. o.
c. o. 0.
0 • 0. 0.
0. o. 0.
~ ~. c. ' .
0 • o. 0.
c. o. 0.
0. o. 0.
0 • o. 0.
0. o. o.
0. c. 0.
0. 0 0 0 •
0 • o. 0 •
0 •. o. o.
-
CH~ K /1CH A 1·1NA PROJECT f.PERATION STUDY
1-./li t>!&CF • BECIH EL CIVIL&MJNERALS If\c •• sF.
ALASKA POt.'[R ~UTIIOR I TY
tll EP. ~~,q I VE P.: ~'CARTI'UR .SHORT TUNt\EL o WITH F IS!-
I~ A Y JUN JUL AUG SEP
0. o. o. 0. o.
c. o. o. 0. o.
o. 0. o. 0. o.
o. o. o. o. o.
o. 0. 0. 0. 0.
o. 0. o. 0. o.
0 • o. o. 0. o.
G • o. o. 0. o.
o. 0 • 0. 0. o.
o. c. o. o·. o.
0 0 0. o. o. o.
0. 0. o. 0. Oo
0. o. 0. o. o.
0. 0. o. 0. . 0 •.
'1
DAH 110581 PAGE <;
0
RELEASES
')
OCT NOV DEC AVEYR CALYR
')
o. o. o. D • 1960
o. o. 0. o. 1961
0. 0. 0. o. 1962 f)
o. o. 0. o. 1963
o. o. 0. o. 196lf
o. o. 0. o. 1965 f)
o. o. o. o. 1966
o. . 0. 0. 0. 1967
o. o. 0. c. 1968 1')
c. .. 0 •. 0. o. 1969
o. o. 0. o. 1970
f)
o. o. o. o.
0. o. o. 0. r')
.0. ...0. . 0. o •
1)
() !
()
C)
·"J
0
0
0
0
I
0 .,
I
0 I I
i
0
.,
(\ Cllf,K ACI'AMN!I PROJECT OPERATION STUDY
h/Htli&CFtBECHTEL CJVIL&MINERALS INC.,SF.
(\ PPCJECT l4H7°l':Ol ALASKA P 0 ~I[ R AUTHORITY DATE 110581 PAGE 1 0
~LTEPNATIVE o: ~~CARTIIUR SIIOR T TUNt;EL • Ill T I' FIH RELEASES
(' PGIIF:P · Ifl ~·u
(' YEA f.: ~ f-N Ff[] fJAR APR MIIY JUN JUL AUG SFP OCT NOV DEC AVEYR CALYR
1 '·' P. • 1 e 1 • 16/lo 151. 138. 133. 131. 138. 151. 172o . 19·8o 215o 165. 1960
( ·, ;> 1 (.q:~. 1 !' 7 0 lE R. 151 • 1~8. 133. 131. 138o 151. 172o 198. 215. 165o 1961
3 1 f_) Be !P7. 168. 151. 138. 133o 131. 138. 151. 1 72 0 198o 215. 165o 1962
4 }';fl. lll7. 16Ro . 151. 1 ~. P.. 133 • 131o. .. --138 •... 151o . .... 1.72o ·-· 1.98 ...... . 215. 165o 19(>3
( 5 1Cf'o 1 [• 7. 11'-ll. 151. 13P.. 133. 131o 138. 151. 172. 198o 215o 165. 1961f
6 l"B. 1E 7. 16P.. 151. 138. 133. 131. 138. 151o 172. 198. 215. 165. 1965
7 1"8. 1 P. 7 • HA. 151. 13A. 133. 131o 138. 151. 172. 198o 215. 165. 1966
c ·. il 1'38. 1P7o 16!l. 151 • L\1•. 133. 131. 138. 151. 172o 198o 215. 165. 1967
0 1 '3 r.. lEI. 168. 151. 1 ~-8. 133. 131 • 138. 151. 172. 198o 215. 165. 1968 f)
1 0 . 1 '.1 8. I P 7 • 16{1. 151. 1 ~'I'. 133. 131. 138. 151. . 172. ---198a 215. 165 • 1969
, .. 11 l':iB o Je7. 1 (, 8. 151. 1 ?· E • 133. 131. 138. 151. 172. 198. 215. 165. 1970
I'[AfoJ 1 r, !l. 11'7. 168. 151 • 1~0. 133. 131. 138. 151. 172. 198o 215. 165.
,.,
I'. AX 1 "8. 1 p 7. H. e. 151. 138. 133. 131. 138. 151. 172. 198. 215. 165. •")
I': IN 1 C) H. 11'7. 1f>B. 15lo 138. 133. . 131 0 138 • 151o 172o 19.8. 215. 165.
()
J
J
.-......----,,
---.
' ,
CI!AKACHAMNA PROJECT OPERATION STUDY
1·1 H oil & C F o f3 E C liTE L . C I VI L & ~H N ERA L S JNCaoSF.
PRCJECT 14l!79COI ALASKA P 0 ~IE R AUTHORITY DATE 110581 PAGE 11
ALTERNATIVE B: MCARHIUR S~IORT TUNNELt WITH F IH RELEASES
UJERGY II\ MWII
Yf AR JAN ff[' fiAR APR Mr, v JUN JUL AUG SEP OCT NOV DEC T.OTYR CALYR
1 I" 731 2. 13o:1r. 124895. 108470. 1n2478. 96073. 97674. 102478. 108470. 128097. 142560. 11:0122. 1448947. 196(1
2 14731?. l?:f'2S. 1?4895. 10€470. 102478. 96073. 97674. ·102478. 108470. 1:18097. 14?560. H0122. 1444453. 1961
3 147312. 12~:E25. 124895. 10e410. 102478. 96073. 97674. 102478. 108470. 1:18097. 142560. H 0122 • 1444453. 1962
4 147312. 125(:2!;. 1?4895. 108470. 102478. 96073.-. ...... 976 74 ··-. 102'178 •. 108'170. 1:18097..-1'12560 .•. .11:0122. 1'144453. 1963
5 (47312. 13031!!. 124895. 108470. 1C2478. 96073. 97674. 102478. 108470. 128097. 142560. 160122. 1448947. 1964
(, 147312. 125(·2:. 124895. 108470. 102478. 96073. 97674. 102478. 108470. 128097. 1'12560. 11:0122. 1444453. 1965
7 1 117312. 12 5 I' 2!: • 124895. 108470. 102478. 96~73. 97674. 102478. 108470. 128097. 142560. 160122. 1444453. 1966
8 14731:1. 125f25. 1?4895. 101!470. 102478. 96073. 976 74. 102478. 108470. 128097. 142560. 16 0122. 1444453. 1967
9 147312. 130318. 124895. 108470. 102478. 9(,073. 976 74. 102478. 108470. 128097. 142560. 11:0122. 1448947. 1968 .--)
1 0 147312. 125f.~=. 124895. 10fl470o 102478. 96073. 'J767'1o 102478. -108470~ 128097. ... 142560 •. H 0122 • 1444453 • 1969
11 147312. )?~ f2~ 0 124895. 101'470. 102478. 96073. 97674. 102478. 108470. 128097. 142560 •. 11:0122. 1444453. 1970
MEAN 147312. 1?7050. 124895. 108470. 102478. 96073. 97674. 102478. 108'170. 128097. 142560. 11:0122. 1445679.
I" AX 147312. 13G31E. 124!!95. '108470. 102478. 9'6 0 7 3. 97674. 102'178. 108470. 128097. 142560. H0122o 1448947.
M u• 147312. 1?5f25. 124895. 108470. 102478.--9607.3 •. ___ 97674. -102478 •. 108470. 128097 .• --1'12560. . H 0122. 1444453.
:)
i)
i.)
0
0
0
0
0
0 CHAK ACI,At·;NA PROJfCT GPfRATlON STUDY ;,
f-/II, li&CF ·,BE CtqfL CIVIL&MINF:RALS INc •• sr.
(\ PRCJECT 14!'79001 ALASK~ POWER AUTHORITY DATE 110581 PAGE 12 ~
ALTERNATIVE I' : MCARTI'UR SIIOR T TUNNEL • WITH F I Sl' RELEASES
(' REMAINHG SPILLS H CFS ~
('\ YFAR JAN f E t~ fJAR ~PR MAY JUN JUL AUG SFP OCT NOV DEC AVEYR CALYR ,
0. c • o. 0. c. 0. o. 3189. 0. 0. 0. 0. 266. ,196 0
r· 2 Q. 0. o. o. 0. 0. o. o. 66. 0. o. 0 •. 5o 1961
3 0. 0. o. 0. 0. o. o. o. o. o. o. o. o. 1962 I)
4 o. 0. o •. 0. c.' ' .o •· -·---· 0. . --· _____ .. o •·-.. ... -·-.. 0. _, 0 ........ o. ,o 0 o. 1963
[' 5 0. 0. o. 0 • o. 0. 0. o. o. 0. o. 0. o. 1964 I)
6 o. 0. o. o. o. o. Oo 0. 445. o. o. 0. 37. 1965
7 0~ 0. 0. 0. o. o. o. 0. o. o. o. 0. o. 1966
("· R c. 0. o. o. c. 0. o. 6812. 32. o. o. 0. 570. 1967 ')
9 0. 0. o. 0 • o. 0. 0. 1364. o. o. o. 0. 114. 1968
10 o. o. o. 0 •·-. o. . . 0 ... o. 0 .. 0. .. .. 0 ...... o. 0. o. 1969
11 c. 0. o. o. 0. o. o. 0. c. o. o. 0. o. 1970 0
MEAIIJ 0. 0. 0. 0. o. o. o. 1033. 49. o. o. o. 90.
MAX c. 0. o. o. 0. o. o. 6812. 445. 0. o. o. 570o 1)
MIN 0. 0. o. 0. o. . .... -.... 0 ..... ' ' 0. .... _. ... 0 .. o. .. o. -· ...D • .. -o. o.
t)
0
0
'.)
0
0
0
0
~)
'
J
~ ,......._.., ,..---.. ~ ,.....---~ ___a,
,.........-, ___, ....--._ ---~
I !
PRCJECT 14!i79001
AVERAGE GENERATlCI\ II\ t'W DURING SPILLS
YEAR JAN fEE' r-AR APR
1 0 • c • 0. 0.
2 0. 0 • 0. 0.
3 0 ~ 0 • o. 0.
4 c. 0. a. 0.
5 0. 0 • o. 0.
6 0. 0 0 c. 0.
7 0. 0 • o. 0.
F. c 0 0. o. 0.
Q c. 0 0 o. 0.
1 a 0. 0 • o. o.
11 0. o. 0. 0.
MEMJ 0. o. 0. o.
r-'AX 0. 0 • o. 0.
MIN o. o. o. 0.
-.--
CHAKACHAMNA PHQJECT OPERATION STUDY
1-/Holt&Cf,BECETEL CIVIL&MINERALS H\C. oSF.
ALASKA POlJER ~UTHORJ.TY
~LTERNATIVE n: ,_,CARTiiUR SHORT TUNNELo t.IITH
MAY JUN JUL AUG SEP
0. 0. 190. 330. o.
0. 0. 0. 275. 330.
0 0 0. 0. 222. 290.
o. 0 •. . 0. 0. 287 •
o. o. o. 196. 205.
Oo 0 • 0. o. 330.
0 0 o. 0. 0. 238.
0. 0. 0 • 330. 330.
c. o. o. 330. o. o. .0. o. -0. ----0.
0. o. 0 • o. o.
o. o. 1 7. 153. 183.
0. o. 190. 330. 330.
a. o. 0. o. o.
DATE 110581
FIS~ RELEASES
OCT NOV
o. o.
o. o.
o. o.
o. .. 0. o. o.
o. 0. o. o.
o. o.
o. o. o. _____ ..... 0 .•.
0. o.
o. o.
o. o. . o. __ o •.
PAGE
DEC AVfYR
0. 43.
0. 50.
0. 43o
o. 24o
0. 33.
0. 27.
0. 20.
0. 55.
0. 27o
o. o.
0. o.
o. 29.
o. 55.
o • o.
13
CALYR
1960
1961
1962
1963
1964
1965
1966
1967
1968
1969
1970
___,
I
0 CHAKACf'AM~A PROJECT OPERATION STUDY
,
hllltii&CF 9 £1ECHTEL C!VIL&~IJNERALS INC.,SF.
r• PRCJEC T 14879~01 ~LASKA POWER AUTHOR 1 TY DATE 11051!1 PAGE 1'1 I')
ALTERNATIVE p: I"ORTHUR SHORT TUNNEL, WITH F 1 s~ RELEASES
('I SURPLUS fNFRGY II\ "l.JJ! ')
('I y[JIR JMI FER MAR AFR MAY JUN JUL AUG SEP OCT NOV DEC TOTYR CALYR ')
1 0 • 0 • o. 0. c. 0. 43738. 143042. 0. 0. 0. 0. 186780. 1960
~. ? o. c. o. 0. o. o. o. 102145. 129130· o. o. o. 231275. 1961
' 3 r. 0 0 o. 0. o. 0. 0. 62388. 100187. o. o. o. 162575. 1962 ')
4 o. 0. ··-··· 0. ······ .. o .•. -· ··----0. ···-·----0 -----·-0. --· ---0----9 7 9 4 6 •·· ···---·----0·----· ·-·· o .• ---··-·· ... 0 •· 97946. 1963
~, 5 o. 0. o. 0. o. o. o. 43608. 39391. o. o. o. 82999. 196'1
~ 0 • 0. o. 0. o. 0. 0. 0. 129130. 0. o. 0. 129130. 1965 !')
7 0. 0. 0. o. o. 0 0 c. 0. 63069. o. 0. 0. 63069. 1966
8 0 • 0. 0. 0. o. 0. o. 143042. 129130. o. o. 0. 272173. 1967
9 o. o. o. 0. o. 0. 0. 143042. o. o. Oo 0 •. 143042. 1968
I
L
()
1 0 0. o. o. .o. o. .. 0. 0 •.. 0 •·· . 0 • . .. o.-.... o •. o. o • 1969
11 0. 0 • o. 0. o. 0. o. o. o. 0. 0. o. o. 1970 0
f'EAN 0. 0. o. 0. 0. 0. 3976. 57933. 625'14. 0. o. 0. 12'1'154.
"AX o. G • o. 0. 0. 0. '13738 •, 143042. 129130. 0. 0. 0. 272173. ')
MIN o. 0. o. 0. c. ... . 0 •.. o. o • o. .... 0. -··· __ o • o. o.
')
Q
()
0
·)
\)
0
J
I
,....,.----, "), ,,'·.
-
PROJECT lll117900t
~ rn :rr;; r:-:--; :-: r-:--
CHAKACHAHNA PROJECT OPERATION STUDY
tt/H,HI!.CF,Bf.CHTEL CIVILI!.MINERALS INC,,SF.
ALASKA POWER AUTHORITY
,....--, -
DATE
ALTERNATIVE Ci CHAKACHATNA TUNNEL, WITHOUT FISH RELEAS~S
3231!3 PAGE
INSTALLED CAPACITY! 300000: KW ~
ANNUAL PLANT FACTUR: :s
.OVERLOAD FACTURj
PLANT EFFiciENC~I
1,00
• BSit
FRICTI!Jtl Lnss COEFFICIENT! ,OOOOU21l00
MONTHLY LOAD FACTURSi
·• 920 ,B7o :7eo ~700 :biiO ,620
INITIAL LAKE STDRAGE I 11033200, AC•FT
MINIMUM LAKE STORAGE 12423ooo. AC•FT
MAXIMUM .LAKE STORAGE 111033200, AC•FT
•• b I 0 ,ouo ~700 ,600 :q20 1'. 0 0 0
' """
' ""
PROJECT lt1A7QOOt
RESERVOIR STORAGE•ELEVATIUN•ARfAI
AC•FT FEET ACRE
o, 7b0, ().
202'5, 7oS. 81 0.
7300, 770, 1300,
27200, 780, 2b90,
I It ou 0. ooo. Sb7o.
2Uiouo, U20. 7J20.
397ooo. 640. 8270,
572ooo, 860, 9280,
7b9ooo. 880, 10400.
98Booo, 900, 11590,
122Uooo, 920, 119oo.
Jllb7ooo. 940. 12320.
1717ooo. 9b o.. l2b50.
l97:sooo. 980. 12980,
223l,(l00. I 00 0., 13280,
25011000. 1020. 13520.
2776ooo, !OliO, I :\7/J U •
lo53ooo. lObO, 139bO,
333Sooo, 1080. 1111 7 ().
3o20ooo. II 00, IIJ390,
Hloi;loo. i 120. lllb20.
4033200. 1128. 15212.
TAILWATER•FLOW RELATIUNSHIPi
n.ET CFS
IJOO, o.
uuo. 1uoooo.
MONTHLY I~ IN I MUM HIS T REAM FLOWS IN
0. 0. 0. 0. 0.
HUNTHL.Y DlVEF<SIUN R EQU 1 R Et1EN T S IN
0. o. 0. 0. o.
MmHHLY RESERVOIR EVAPORATION HI
... . 0 ··-· ··--Q • -...... 0 • . 0. 0.
CfS!
o. o.
CfSI
0. o,
It~CHES i
o. o,
CHAKACHAMNA PROJECT OPERATION STUDY
H/II,H&CF,BECHTEL CIVIL!I.MINERALS INC,,SF,
ALASKA POWER AUTHORITY DATE 32383
ALTERNATIVE Cs CHAKACHATNA TUNNEL, WITHOUT FISH RELEAS~S
0. 0. o. 0. 0.
0. 0. o. 0. 0.
---0. -·--·-·--0 ~------·-Q •.. ----· 0. ·-· .. __ 0_. ·-.
2
.....--.....--, -r~ TIT· """T-. .,-. r:-r:; ~ --------, -----, ~ I !
CHAKACHAHNA PROJECT OPERATIOI~ STUDY
H/H,H&CF,BECHTEL CIVILI!.MINERALS INC,,SF,
PROJECT 14879001 ALASKA POWER AUTHORITY DATE 32383 PAGE 3
ALTERNATIVE Cl CHAKACHATNA TUNNEL, WITHOUT FISH RELEASES
INFLOWS TLJ THE LAKE Itl CFS
YEAR JAN FEB MAR APR HAY JUNE JULY AUG SEPT OCT NOV DEC AVEYR CALYR
I 1100~ 307, 2b7, 393. 3o37. 6837~ 11209·, 9337. 31115, lliH. 799, 870, 3220, 19b0
2 877, 589, 1170, 3116. 1881. 7983~ 12808, 10899. 6225. !566, 8113. o96. 376 7. I 961 3 633. 5111, 1171, 117 0. 1265, H25. 131119. 10tll1, 55112, 1197. 863, b 13. 3590, 1962
Q 1198: 357, 31 5. 337. 18ot. 11735~---132119. 12208. 58117. 2056, 930. 710 1 3587, 1963 5 3bll. 4 35 1 332, 477. 1830, 8093. 10700, 11798. ll2llb. 12115. 909. (;,62, 311211. 19611
b 1119: 219, 337. 398, 128b, 3~9o: 13046. 10516, 108021 211ll. 597. t1o61 36411 1965 7 38~, 336. 350, 1110 1 1893. 8072. 10303. 9'Htl, boOB, !9531 910, 313, 31159, 1966
8 531 • 11119. 3811, 8801 2030, 8761~ 111931. 156951 6 19 1 I 20110. 12!5, 5 '11. 111.1731 1967
9 5311~ 51 0. 1167, 630. 2996, 7808' 13117. 11257, 2793. 97&, o89 1 612, 3532, 19bA
10 11Bs. 486, 5oo. o52. !9118, 9271:_ ··-12 51 0. 7297, 2793 I 3057, 1215, 541 1 3396, 1969
11 IJ97: SOli, 550, 899. 2265. 6789'. 10360. 7986 1 27311. 1359. 742, llbO, 2929, 1970
MEAN 511: 430, 4011, 536 1 2076. 7251: 12307, 10671, 5175. 1729. 883, 592, 351J7,
MAX an: 589, 550, 891). 3o37. 9271~ 111931. 15695. 10802, 3057. 1215. 870, 11473. MIN 3611, 219, 2b7, 337, 12b5. 31190. 10303. 7297, 2734. 971.1, 5971 313 1 29291
PROJECT 148790oi
POWER RELEASE It~ CFS
YEAR JAN FEB MAR APR
I 367,: 3567. 326o. 2903.
2 3Q3Q: 3o28, 33811. 3!11.
3 3939. 3628. 3384. 3 I 1 1 ,
IJ 3939: 3831. 3508. 3 I I 1 ,
5 3939~ 3628. 3384. 3!11.
b 3939. 3831, 3508. 3 Ill ,
7 3939~ 3831. 3508. 3 I I 1 o
8 3939, 3828. 3381, 3 I II • q 3939. 3828. 33811. 31 11.
I 0 3939: 3831. 3508. 3 Ill ,
I I Hlb. 3828. 3384, 3!1 I ,
f1EAN 39111: 380b. 31U8, 3o92,
MAX 3939: 3631. 3508, 31 I I ,
MIN 3673. 3567, 326o. 2Q03.
CHAKACHAHNA PROJECT UPEHATION STUOY
rl/H,H~CF 0 HECHTEL CIVIL~HINERALS INC,,SF,
ALASKA POWER AUTHORITY
ALH::RNATIVE Cl C~AKACHATNA
HAY JUNE JULY
2o3b. 2550~ 2429.
2821. 2726~ 2507.
2Q23. 2727. 2507.
2924. 2825'. 2590.
2821. 2727: 2590.
2921.1. 2825. 2bBO.
2'123. 2727~ 2590.
2821. 272b, 2507,
21:!21. 2726. 2507,
2'124.
2821.
2727~
2726.
2507,
2507.
285 I. 27 28 ·• 2538.
2921J. 2825~ 2680.
2b3b. 2550. 2tJ2q.
,...---,
,I
TUI·JNEL,
AUG
21178,
21179.
211791
2556,
2556,
2638,
2556,
2479,
21179.
2555,
2556,
2528,
2638.
21178,
WITHOUT
SEPT
2725.
2725,
2725 •.
2725,
2725,
2725,
2725,
2725,
2725.
2725.
2725,
2725,
2725,
2725.
-'
DATE 32363 PAGE.
.....
FISH RELEASES
.....
OCT NOV DEC ~VEYR CALYR ....
3!4b. 3H8, 1118 7 1 3 It 3, IQbO
3!46, 3798. 11!87. 3221. !961
3IIJ6, 3796. 1Ji83, 3229. IQ62 ' -311J6. 3798, 4187, 3262, !9b3
3146, 3798, IJ187, 3231.1, !9b4
:311J6. 3798, 4!87. 327b. !9b5 ~ ....
3146. 3798, 4!87, 3253, 19bb
311J6, 3798, 1Jt87, 32 21. !9b7
314b. 3-80 0. IJ31J3. 3234, 19b8 , ....
311J6. 3670. tq87. 32Jb. !9b9
32118. 3800. IJ343. 32(19, 1970 ....
3156. 37B7, 1.1215. 3230,
321J8. 3800, ll31J3 0 3276. .....
3IIJ6. 3o7o. 1!183. 3113.
...,:
.....
_,
....
-r---: -rr_, ,......._ rrr:r: ~ rn m r-: ~ ~ ......--~ .----, ---"] -----1 -, --, l l I ) j
CHAK ACHM1NA PJWJECT OPERATION STUDY
PROJECT I4AHOOt
H/H,tt&CF,f:!EC:HTEL CIVIL&MINERALS
ALASKA POWER AUTHORITY
INC:,,SF.
DATE 32383 PAGE 5
IlL TERN AT I VE C I CHAKACHA TtiA TUNNEL, WITHOUT FISH RELEASES
SPILL IN CF"S
YEAR JAN FEB MIIH APR HAY JUNE JULY AUG SEPT OCT NOV DEC AVEYR CALYR
t 0~ 0, 0, 0. 0. 0~ 2177', oB59, 420. 0, 0. 0. 788. lq60 z o, 0, 0. / 0. o. 0. 0. 3.3b5. 35oo. 0. 0. 0. 572, lqbt
3 o, 0, 0. 0 I 0. 0' 0. 2292. 2817, o. 0. 0 1 42b. lq&z
4 9, 0. 0. 0 I 0. o' 0 1 221. 3122, o. 0. 0. 2791 19o3
5 0 1
... I'
18b2, 1521. 0~ 0. 0. 2132, 1964 o, 0. 0. 0. 0. 0,
b o, 0. 0, 0 1 0. 0 •• 0. 0 I 44071 o. 0. 0 1 367, 19&5
7 0. 0. 0. 01 o. 0 •• o. o. 27q1. 0. 0 1 0. 233. lqbb
8 o: 0. 0. 0, 0. o: 0. 11212. 34ool 0. o. 0. 1223. 19&7
9 0. 0. 0, 0. 0. 0. f), 5433. b8, 0 1 0. 01 1.158, \908
1 0 , o. 0, I)' 0. 0~ o. o. o. o. o. 0. (l. lqoq o,
II o. 0. 0, Q I o. o. 0, 0 I 0. o. 0. 0. 0. 1970
tiE AN o: 0 1 0, 0 0 0, 0~ 198, 2840, 2010. 0 0 o. 0. 421.
MAl( o: 0. 0. 0 I 0. o: 2177. 11212. ll407. 0. Oo 0 0 1223,
~11 N o: 0. 0. 01 0. o: 0. o. o. o. o. 0 a 0.
CHAKACHAI'1NA PROJECT OPERA TIUN STUDY .....
H/H,H&CF,Hf.CHTEL CIVILI!.MINERAL.S INC.,SF.
PRUJfe T IIIA7900l ALASKA POWER AU fHOR I TY DATE 32383 PAGE b
""' ALTERNATIVE Cl CHAKACHA HlA TUNNEL., W!THUUT FISH RELEASES
Fl Slf RELtt\SE IN CFS
......
YEAR JMI FEB MAR APR HAY JUNE JULY AUG SEPT OCT NOV OE.C AVF.Yil CALYR
n~ o' ....
l 0. 0. u. 0. 0. 0. 0. o. 0. 0. 0. 19b0
2 (l. u. o. Q. 0. 0 •• o. 0. 0. o. 0. 0. 0' 19b1
3 0~ u. 0. o. 0. o' 0. 0. o. 0. o. 0' 0. 19"2 l
0~ ....
/J o, 0. o. o, o. 0. 0. 0. 0. 0. 0. 0. 1963
5 o, u. o. 0. o. o' 0. o. o. 0. 0. 0. ll. !9bLI p
b 0. o. (). o. o. o. (). 0. 0. 0. fJ • 0 1 0. !965 .
""' 7 0 •• 0. I). 0. 0. o·. o. 0 1 0. 0. 0. 0. 0. l9bb
8 o: 0. 0. o. 0. 0 ·• 0. 0 1 0. 0. 0. 0. 0. !967
9 n~ o. I). 0, 0. o: 0. o. 0. 0. o. 0. 0. 19b8 , -1 0 0. 0. o. o. 0. 0 ·• 0. o. o. 0. o, 0. 0. 1969
11 o: 0. 0. 0. 0. 0 ·• 0. o. 0. 0. 0. 0. 0. 1q1o . -~IE AI~ I)·. 0. 0. 0. 0. o: 0. o. o. 0. o. 0. o.
MAX o: o. 0. (l. 0. o: o. 0. 0. o. 0. 0. 0.
MIN 0 •• 0. 0. 0. o. o·. 0. o. o. 0. 0. 0. 0.
--
-
----,
......--• I
r-: r: -~ r--ern-: rn rn m -r-j ·:--::1 ,..----..., ' --J i ' ' j
CHAKACHA11NA PROJECT OPERATION STUDY
HIH,H&CF,BECHTEL CIVII.I!.MINERALS INC., sF.
PROJECT ltiR79UOl ALASKA POWER AUTHORITY DATE :3236:3 PAGE 7
ALTERNATIVE C I CHAKACH/ITNA TUNNEL, WITHllUT FISH RELEASES
,NET EVAPURATIOtJ HI ACooFT
YEAR JAN fEB MAH APR HAY JUNE JULY AUG SEPT OCT NOV OE.C AVEYR CALYR
I o: 0. 0, o. o. 0~ o. 0. o. 0. o. 0. 0. tq&o
2 o, 0. 0. o. o. o, o. o. 0. (). 0. 0 0 (). lqb1
3 o. 0. 0, o. 0. 0. o. o. 0. Q. 0. 0. 0. lqb2
4 0~ 0. 0, 0, 0 •. 0~ 0. o. o. 0. o. 0. 0. lqbJ
5 0. 0. 0, 0. o. o. 0, o. 0. 0. 0. 0. 0. iqb/.1
b
,
0. 0. o. o. 0~ o. o. o, 0. o. 0. 0. lq&S Or 7 o, o. 0, o. 0. o, 0, o. o. 0. o. 0. o. lqbb
8 0. 0. 0, o, o. o. o. o. 0. 0. 0. 0 0 o. 1%7 q 0~ 0. 0. 0, 0, 0~ o. 0. o. o. o. 0. o. 1%8
I 0 o, 0. 0. 0. 0, o. 0, 0 I o. o. 0. 0. 0. lqbq
I I o. 0. 0. 0, o. o. 0, 0 I o. 0. 0. 0. (). 1q7o
fiE AN o: 0. 0. o. 0. 0~ o. 0. 0. 0. 0. 0. 0 •
MAX 0~ 0. 0. o. 0. 0~ (). 0. 0. o. 0. 0, 0. MIN 0. 0. 0. 0, 0. 0. o, o. 0. o. 0. 0. 0.
PROJECT 148l900J
E0 Q,P, STORAGE IN ACRE•fl
YEAR JA~-j FEB MAR APR
I 38lt93J: 3bl.!ll415. 1459987. 331oooo.
2 33<;7525~ .3i77o21. ;?998461J, 2833'11:11.
3 331lJQ8o. Jlo0911, ?981815. 2824690.
lj . 33o7o0ll~ Jit1Jo56, ?9!832/J, 2753265.
5 J3{!1B.7~, 3l6bb90, 2(j790II8, 2822339,
b 331 II q I. 5110578, 29!5599, 2754189.
7 33j2ioo: J'i3798f;. 2943606, 2763110,
8 Hqo21 i~ 3iS2532, 29&6270. 283551J2.
9 3379757. 3186665, 30095113, 2861'1H.
10 3272B4t~ 3087057, 2902100, 2755605.
t 1 34o8b30. 32211007, 301197b6. 29t8t7t,
~lEAH 338ot011: 319&849, 3011520. 2859<121.
to~ AX 3!lJtll53: .501111415, ~1159967. 3310b0b.
MIN 327?.8 111. 3087057, 2902100, 2753265,
CHAKACHAHNA PROJECT OPERATION STUDY
H/H,H&CF,BECHTEL CIVIL&MINERALS r~c.,sF.
ALASKA POWER AUTHORITY
ALTERNATIVE Ci CHAKACHATNA TUNNEL, WIHiOUT
MAY JUNE JULY AUG SEPT
3372125. 3b27219: 11033200, 4033200. 403'5200 0
277blb3. 301:18<171~ 37?23&1:1, 4033200. 4033200.
21227.3b. 3032053. 3bBb391, /1033200, 4033201).
26611231. 2797895' • 31l53292. uo332oo. IJ033200,
27bliJOb. 3080719:· 357fl11l2, /l0.33200. IJ033200.
2o53470. 2693051. 33301JbO, 38148&4. IJ0332oo.
2719771. 3037835~ 3512089, 3966230. IJOH2oo.
278b90b. Jjilb007~ 3'1o99LIO. 4o332o·o. IJ033200 •·
2872700. J!7So911, 313271189. 11033200, IJ0332oo.
2u95Ho.
2883985,
JoBS 1 99~. 37oo27o.
ll2574q. 3608&17.
J991B3o. 3995875.
39q2S21. 3943055.
2811753, 3080890'. 36&94!1, 39951140. 4021&12.
3372125. 3b27219' 110332011, 4033200. 11033200.
2653470. 2b93051~ 3330llb0. 38!118611. 39qJo5s.
r--!'1. •, i J ~!
DATt 32383
FISH RELEASES
OCT NUV
3928218, 3749757,
3937256, J7bi1J14,
3913338, 373Rb85 I
396&156, 37951J90,
39!6289, 3 7 11'137 4.
39b9722. 377921l 1.
395'1822. 3787967.
3965172 • .38!11165.
38997119. 371/JbOB.
399oJ79.
382b882,
38Qt1274.
3b4t18(j5,
3933907. 37&1106.
3990379, 381.142711,
3826862. 3b41l895.
DEC
3545788,
351l67116,
35!9172.
3581683.
3527616.
35SOIJ32 1
J5ll9749.
3589111.
3485208,
3620075.
340&148,
3538339.
3&20075,
3110&1118,
~I
J
PAGE. 8
AVFVR CALYR
3714137, 1960
31A3B9o7, 1961
34!5Bo6. 1962
3Jb(j918, 11163
3417181. 1964
3326333 0 1965
3311713'1. 1966
311642'1&. 19&7
3456781. 1968
3411711!, 196q
311152o2. 1970
3438863.
371111J7.
332&333,
.---r-::. r--' ~ ...._ r:-r: -r--: ~) ~ .....-, ...---.., ,...___.., ~ ---, ---.., ~ 'I. ) J J
CHAKACHAHNA PROJECT OPERATION STUDY
PROJECT IQA7900t
HIH.H~CF,HECHTEL CIVIL&HINERALS XNC 0 ,SF,
ALASKA POWER AUTHURITY DATE 32383 PAGI: 9
ALTERNATIVE Cl CHAKACHATNA TUNNEL, WITHOUT FISH RELEASES
E,O.P. LAKE LEVEL I tJ FEET
YEAR JAN FEB MAR APR ~lAY JUNE JULY AUG SEPT OCT NIJV O!:C AVEYR CALYR
I 110()~ II o 0, 1080, lObO, 1080. 1100~ 1120. 1120. 1120, I 12 0. 1100, lOBO, I09B. 19bO
2 lOBo. lObO, I 0 II 0 • to4o, 1 OliO. lObO. 1100. 1120. 1120. 112 0. 11 0 0. lOtiO, 101!0. ICh,J
J to8o: lObO, I 011 o. lo4o, 1020, 1o11o: 1100. 1120. 1120, 1120. 1100. 1 o8 o. 1077. 191.12 q 10oo, lObO. !Olio. 1(120. 1020, 1 Oil o. _ ·-·-1 0 8 0 •. 1120, 1120, I 12 0 • I 10 0 • 1080, 1072, 19b3
5 lOBo, lObO. I Oil 0, J(lilO, 1020. lObO~ 1080. 1120. 112 0. 1120. II 0 0. lotio. 1 0 77. I 9bl~
b lObO. lObO. 1 0 ll 0. 10201 1020. 1020. lObO. II 0 0. 1120, 1120. 1100, 1080. 10671 19bS
7 lObo: I ObO. !OliO, 1040, 1020. I OliO~ 1080. 1120, 1120 I 1120. 1100. 1080, 1073, !9bb
8 1080~ lObO. I Oil 0, iolio, 1 0 II 0. lObO~ 1100, 1120. 1120. 1120. 11 (tO, 1080, loao. 19b7 q lOBO. I ObO • !OliO. !OliO, I OliO. lObO. 1100, 11201 1120, 11110, II 00 • loBO, 107B. !9b8
. 1 0 lObo: lObO. 1 Oil 0, I021J. 1020. .lObO~ . ...1100,. 1120 •. 1120, 1120. II 0 0 I 1100. 1 0 7 7. 19b9
1 I lOBO. lObO, 10110. I (JII 0 I 1040. lObO. 10801 1120, 1120. 1100, 11 0 01 1080, 1077, 1970
MEAN to7s: IObli, 104Q. !03b 0 I 033. 1 oss·. 1091 • 1118. 1120. 111 b. 1100. 1082. 1076,
MAX II 00: 11 0 u. lOBO. lObO, 1060. 1100: 1120, 1120. 1120. 112 0. 1 I 0 0 • 1100, 1098.
!'liN lobo: lObO, I 0110. 1021)1 1020. 1 o2o'. lObO. 1100 0 1120. 1100. 1100, 1060, 1 0 b 7.
.. ·
CHAKACHM1NA PROJECT OPERATION S TIJDY
H/H,tl&Cf 1 BECHTEL CIVIL&MJNERALS INC 1 ,SF 1
PROJECT l4EIHOO-t ALASKA POWER AUTHORITY DATt: 32363 PAGE I 0
ALTERNATIVE C I CHAKACHIITNA TUIINEL, WITHUUT FISH RELF.:ASES
WATER BALANCE
YEAR JAN FEB MAR APR NAY JUNE JULY AUG SEPT OCT NOV DEC AVEYR CALYR
I 0~ 0. 0. o. n. 0 •• o. a 0 a. o. o. 0. 0. IQbO
2 n. 0. 0. 0, o. 0 ·• 0. o. 0. I). o. 0. 0. I qb I
3 n~ 0. 0. o. 0. 0 •• 0. o. 0. a. 0. 0. o. 1q112
4 o, 0. o. 0, 0. 0 ·• o. 0. 0. o. 0. 0. 0. lqbJ
5 0. 0. o. 0. 0. a: 0, 0. 0. 0, 0. 0. 0. lqbtj
b 0~ 0. 0. 0. 0. a·. 0. 0. 0. 0. 0. a. 01 IQbS
7 o, 0 0 o. 0. 0. a·. o. 0, o. 0. 0. 0. o. lqbb
8 a. 0. 0. a. 0. 0 ·• 0. 0. 0. a. 0. 0. 0. lqb7
q o: o. 0. 0. a. 0~ o. o. 0. 0. a. 0. 0. 1%8
I 0 a. 0. 0. o. a. ---0 r 0. a. a. 0. a. (I • 0. lqbq
1 I a: 0. 0. o. 0. 0. a. o. 0. 0. o. 0. 0. 1q7o
}lEAN . 0. o. o. 0. 0. 0 • • 0. 0. 0. 0. 0. 0. 0.
MAX o, 0. o. o. 0. o: IJ. 0 I 0 •. 0. 0. 0. o.
MIN o. 0. 0. I) 1 0 •. --0: 0. o. 0. 0. 0. 0. 0.
-
~--,
~ ~' -rr-: -tm. 7'1· n-· rr:rr\ ~· ---.. -, -., -----,, ,----, ~, ~ " --' ' ----
CHAKACHAI1NA PROJECT OPERATION STUDY
H/H,H&CF,BECHTEL CIVIL&MINERALS INC,,sF. ·-PROJECT lll137900t ALASKA POWER AUT HOIU TV DATE 32383 PAGE 1 I
ALTERNATIVE C I CHAKACHATNA TUNNEL~ IHTHUUT FISH RELEASES
POWER Hl l~w
YEAR JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT NOV OEC AVfVR CALYR
I iso~ I 7 0. 153. 13 7. 125. 121~ I 1 9 • 125. 137. 1S7. 18 0. 19b, 15 0. 19b0
2 tBo, I 7 o. I 'B • I 3 7, 125. 121~ 11 q. 125. 137. 1S7. I B 0 • 19b. 15 0. I 9o I
3 18 n. I 7 0. 153. 137. 125. I 21 • 11 q. 125. t 37. 15 7. 180. t9b. 15 0. 19b2
II lBO~ 1 7 0. 153. I 3 7. 125. 121 ~-. . 11 q. 125 •. . 13 7. 1S7. 18 Q 1 19b. 15 0. 1%3
5 18 0. I 7 0. 153. 13 7. I 25. 12 I • 11 q. 125. 137. 157. 180, 19b. ISO. 1%11
b 1ao: I 7 0. I 53. 137. 12S. 121~ 119, 12S. 13 7. 157. 18 0. t9b. I 5 (l • !9oS
7 IBo, 1 7 0. 153. 137. 125. 121, 11 q. 125. 137. 157, teo. 19b. 150, 19bb
8 tao, I 7 0. 153. 137. 125. 121. 11 9. 125. 137. 157. 180. t9a. It; 0 , 19b7
9 IBo, 1 7 0. IS 3, 137. 125. 12 1 •• II 9. 125, 13 7. 157, tao. 19b. IS 0 • 1%8
I 0 lBO I 7 0. 153. 137, 125 •. 121'. 119. 125. 137, 15 7. 180, !96. IS 0. 19&9
. . .. . ' 11 tB 0. 170. 153. 137, 12S. . 121 ~-t 1 q. 125, 13 7. 157. 180. t9b. ISO, 1970
I~EAN lao: I 7 0. 15 3. 137. 125. 12 !'. 11 9. 125. 137. 157. I 8 0. 19b, ISO.
HAX 180~ I 7 0. 153. t37. 125. 12 1 ·• I I q • 125. 1371 157. I B 0 • t9b. I 'i o.
HIN tBO. I 7 0. I 53. 13 7. 125. 12 !'. 119. 125. 137. 157. 18 0. 19b. 15 0.
...
CHAKACHAHNA PROJECT OPERATION STUDY loo
H/H,HI!.CF,BECHTEL CIVIL&MINERALS HJC.,sF.
PROJECT IIIA7900l ALASKA POWER AUTHORITY DATE 32383 PAGE 12
ALTERNATIVE Ct CHAKACHATNA TUNNEL, WITHOUT FISH RELEASES
EtJERGY IN MWH ...
YEAR J AtJ FEU MAfl APR HAY JUNE JULY AUG SEPT OCT NOV DEC TOTYR CALYH
....
I I B92o: I !84 7 I • ! I 3Stl I • 98oo'l, Cl31c:..2. 67339'. 88795, 93162. 98609. 1161152. 129600. 1455&5. !317224, 19b0
2 1~3920: 111138b, 1135111. 91lo09. 93ib2. 137339' 88795. 931b2. 98b09. II 61152. 129bOO. 11~5565 • 13131]9, 1901
3 1 B92o. IIIJ386, 113'541. 98u09, 93162. 87339~ 88795, 931b2. 98b09, 11 6 II 52. 129600, 145565, 1313139. 1962 .....
II I 33920~ IJIJ38b. 11 35'11. 98609, 93Jb2. 1!7339~ 88795, 931b2. 98609, 11 bll52. 12'l6QO, 145565, 13!3139. 1963
5 1 B92o, I !84 71 • I 13541. 98609, 931o2. ll733'l 1!8795. 93162. 98609. 1161152, 129600, IIJ556S, !3172?.1.1. 1964
6 I 'B920. llld8b, I I 35111 • 98u09, 93tu2. 117339~ 88795, 93162, 98609, 11bil52. 129600, 11J5Sb5 1 1313139, 19&5 .....
1 1 B92o~ j !IJ 386. 1135111. 96uo?. ?31o2. 87339~ 88795. 931&2. 98609, 1161152. 129600, 145565 1 1313139, !9b6
8 133920, 114386. II 3541. 98uiJ?, 93162. 1!7]39 88HS. '131 b2. 98609, 11bll52, 129bOO, 145565. 1313139. 19b7
9 1B92o. I t8tl 71 • I I 3511 I • <lauot:J, 931o2. 87339: 88795, 931b2, 98609, llb'~52. 1296oo. 145565, 1317221.1. 19b8
I 0 133920~ I 11J 38b. 1135ll 1. 98o09, 93162. 8733<1' •. -88795. 93162. 98b09, 11 biJ52~ 129600. ltJ5565, 1313139. 1969
1 I 133920. IIIJ386. 1135lll. 98609. 93162. 87339'. 8879'3. 93162. 981,09, lloll52, 129b00 0 1115565, !3131l9. 1970
I·IEAN 1 j3no: 115Soo. l135ll 1. 98u09. 9311J2. 137339'. 88795. 93162, 98609, 11bll52. 129~00. 1115565, 1311.1253.
114 X 133920: l 18ll 71. I I 3511 I. 981:>0'1, 93162. 87339' 88795. 93162. 98609. l16ll52. 129600. 1115565, 1317221.1. MIN ll3920. I IIJ 386. 1135111. 98609, 931o2. 87339: 88795. 93162. 98609. 1l6ll52. 129600. 145565. !313139,
;:-r-,
"
PROJECT 14A79ooi
ENERGY DEfJCIT IN H:~H ..
YEAR JAN FEB MAR ..
I 0~ 2 0.
0. 0. o. 0. .. 3 0~
1.1 o, s o,
~ b 0.
0 1 o.
0 1 01
0. 0.
0. 0,
7 o: 0. o.
8 o:
' 9 0.
0 I 0,
0. 0.
I 0 0~
II o.
0. 0. o. o.
tiE AN 0 •• 0. 0.
IH)( o: 0. 01
MIN o: 0. o.
~
r/1
;
rl
,
,
"
-r: .1, )' Ml"", ~ : I 1
C HAK AC HAf1N A PROJECT OPERATION STUDY
~l/H ,Ji&Cf, BECHTEL CIVILIJ.HINERALS INC.,Sf,
ALASKA POWER AUTHORITY
ALTERNATIVE Cl CHAKACHATNA TUNNEL, WITHOUT
APR HAY JUNE JULY AUG SEPT
o. 0. 0~ n. o. 0.
1), 0. 0. o. o. 0.
0 I o. o: n • 0 0 0. o, o. o. 0, o. 0.
o, o. 0~ 0, o. 0. o. o. 0. o. 0. 0.
o. 0. 0~ 0, 0. o.
Q, 0. 0~ o. o. 0. o. o. 0. o. 0. o.
o. o. 0~ o. o. o.
o. 0. 0. o. o. o.
0, 0. 0 ·• o. o. 0.
0 I 0. o'. 0. o. 0.
o. o. o: 0. 0. 0.
DATE: 32383 PAGE 13
F'l SH RELEASES
OCT NOV DEC TOTYR CALYR
0. 0. 0. 0. 19b0
0. o. 0 0 01 !9bl
I). 0. 0. o. !9b2
0. 0. 0. 0. t9bl
0. 0. 0. 0 1 19bll
o. o. 0. 0. 19b5
0. 0. 0. 01 19bb
0. o. 0. 0 1 19b7
0. 0 1 0. 0. 19b8
o. o. o. o. 19b9
o. 0. 0. 0 0 1970
0. o. 0 0 0.
o. 0. 0. 0.
o. o. o. o.
...
CHAKACHAMNA PROJECT OPERA TIUN STUDY ....
I1Ja?90oi
H/H,H&CF,BECHTEL CIVIL&MINERALS INC.,SF.
PROJECT ALASKA POWER AUTHORITY DATE 32383 PAGE IIJ
......
ALTERNATIVE Cl CHAKACHATNA TUNNEL, WITHOUT FISH RELEASES
AVERAGE GEtJERAT IllrJ IN HW IN MONTHS UF SPILLS
YEAR JAN FEB HAR APR HAY JUNE JULY AUG SEPT OCT NOV DEC AVEYR CALYR
._,
o; I 0. o. 0' o. o·. 23b·, 300. lbO, 01 0. 0. sa. 19b0
2 o, 0. o. 0. 0. o: 0. 299. :soo. 0. 0, 0. so. 19bl
3 o, 0. o. 0, o. 0~ 0. 21JQ, 282, 0. o. o. IJIJ, 191>2 ....,
q o, 0. 0. 0, o. o .. 0. lll2, 297, 0. o. 0. 37. 19b3
5 o, 0. 0. o. o. o. o. 226, 211>. 0. o. o. 37, 19bQ
b 0. 0. 0, o. o. 0~ 0. o. 300, 0. 0 1 0. 25, 19&5 -'
7 0~ 0. o. ()' 0. o. o. o. 280, 0. o, o. 23, 19bb
8 (I • o. 0, o. o. 0~ o. 3oo, 300, 0. 0. 0. 50, 19b7
9 o: 0. o. o. 0. o: o. 300, 1142, o. 0. 0. :57. t9b8
1 0 o, 0, 0, 0, 0. o. 0, 1), 0. 0. o. o. 0. 19b9
1 I 0. 0. o. o. o. 0 ·• o. o. 0 0 0. 0. 0. 0. 1970
I·IEAN o. 0. o. "· o. 0 ·• 21 1 lbS, 207, o. 0 0 0. 33.
MAX 0~ 0. o. o. 0. o' 23b. 300, 300. 0, 0. 0. sa.
MIN 0. o, o. o. 0. . 0 ·• o. 0. 0. 0. 0. 0. 0.
-
::ITT· :...-----, -, --,
C HAK ACHAt1 NA PROJECT OPERATION STUDY
H/H,H&CF,BECHTEL CIVIL&MINERALS lNC.,SF,
PROJECT 148HOOt ALASKA POWER AUTHORITY DATE 32383 PAG!: 15
ALTERNATIVE Cl CHAKACHATIIA TUNNEL, WITHOUT fiSH RELEASES
SURPLUS EtlfHGY IN t1i'IH
YEAR JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT NOV DEC TOTYR CALYR
" I 0~ 01
2 o, 01 , 3 o. 0 I
0. 0. 0. 0 ·• 8bb81. 130038. lb51CI 0 o. 0. 0. 233238. 1960
o. 0. 0. 0~ o. 129139. 11 73CI 1 1 0 ·• 0. 0. 211b530. 19ol
0. o. 0. 0 ·• 0. 88.H 9. 1o112o11, 0. 0, 0 I 1CI2S83, !962
II 0~ 0,
5 0. o. o. 0, Q, o: 0, 12317. l15ll29. o. 0. 0. 1277llb. 19o3
0, o. 0, o. 0. 7llbb0o 5&822. 0. 0 0 0. 1311182, !9btl , 0 0~ 01
7 o, 01
8 0; o.
,; 9 o, o.
1 0 o, 01
11 0. 0.
0. 0. 0, 0~ o. o. 117391, 0. 0. 0 1 117391. !96'5
0. 0. 0. o. o. 0. 103318. lj. o. 0 0 103Jt8, tlloo
0. 01 0. o: o. 130038 0 117391. 0. o. 0. 21171130, 1907
0, o. o. 0~ o. 130038, 3oH, 0. 0, 0. 133&71, 19o8
0 0 o, 0. o, o. Oo 0 0 0. Oo 0 0 0. !9b9
0 I 0. 0. 0, 01 o. 0. 0. 0 I 0 0 0 1 !970
,;
MEAN 0 •• 01 0 I 0 I 0 ·• o: 7880. 631111. b8378. o. 0. 0. 13CI399,
, ~1AX 0~ 0 1
MIN o • 0 I
o. 0, 0~ 0~ 8bb81. 130038. 117H1. 0. 0. 0. 21171130.
o. o. 0. 0.' Oo o. o. o. 0 0 o. 0.
.,
,;
J
,;
J
,;
.I
.J
;·
,
-,
I
,
PROJECT 14B790oi
RE"1AlNlNG SPILLS
YEAR JAN
I o:
2 o:
3 o.
4 0~ 5 o,
b 0.
7 0~
8 o,
9 0.
1 0 o: 11 0.
MEAN ,
0.
MAX , o, MIN o.
IN CFS
FEll MAR
0. 0.
0. 0.
0. o.
0. 0.
0. 0.
0. 0.
o. o.
0. 0. o. 0,
0. o.
0. 0,
0. o.
0. 0,
0. 0.
r--
APR
o.
0.
0,
0,
o.
o.
o.
o. o.
0. o.
0,
0,
0,
--,,
CfiA K II C H MIN A PROJECT OPERATION STUDY ...
H/~,H~CF,HECHTEL CIVIL&~IINERIILS INC,,SF.
ALASKA POWER AUTHORITY DATE. 32383 PAGE lb
...
1\LTERNATIVE Cl CHAKACHI\TNA TUNNEL, WITHOUT F'I SH RELEASES
MAY JUNE JULY AUG SEPT OCT NOV DEC AIIEYR CALYR
0. 0 ·• o. 3470. o. 0. 0. 0. 289, !9&0 o. o· o. o. 3211. 0. 0 I 0. 27, 19&1 o. o: 0, 0. 0. 0, o. 0. 0. 1902
0. 0~ 0. 0 0 0. o. o. 0. 0. 1903
0. 0. o. 0. o. 0. 0. 0. 0. 19bll
0. 0~ 0. 0. 1232, o, 0. 0. ln3, 19b5
o. o, 0. o. 0. 0. 0. o. o, 19b6
o. o, 0. 7823, 290, 0. 0. o, b7b, 19b7
o. 0. o. 20lll!, 0, 0, 0. 0. I 7 0 • 1968
o. -0~ 0. o,. 0. o. o. 0. 0. i9b9
0. 0. o. 0 0 0. 0. o. 0. 0. i'HO
0. o: o. 1212, 1b8, 0. 0. 0. 1 t 5 •
0. 0~ 0. 78ia3. 1232. IJ. 0. 0, l:l7b,
0. _o. -o. o, 0. 0. o. o, 0.
.-~
·r:T:·
PROJECT lllA790nj
INSTALLED CAPACiTYi lOOOOo: KW
ANNUAL PLANT FACT()RI :s
OVERLOAD FACTORj 1,00
PLANT EFFICIENcvi ,6So
FRICTION LOSS COEFFICIENTs :ooooo2aoo
M'ONTHLY LUAD FAcrw~si
~920 ,a7o :7ao .700 :b40 ,620 :oto
IIIITIAL LAKE STORAGE :110332001 t\C .. FT
HINIHUM LAKE STOfUGE a2ll23boO, AC,.FT
MAX Jr-1Ut1. LAKE STORAGE 111033200, AC"FT
'~I '· ,"'M"""'"\j ,~ ~ ,,] I LJ
CHAKACHAHNA PROJECT OPERATION STUDY
HIH,H&CF,BECHTEL CIVIL&HINERALS INC,,SF,
ALASKA POWER AUTHORITY DATE 32383
ALTERNATIVE 01 CHAKACHATNA TUNNEL, WITH FISH RELEASES-
~o11o ·• 7oo ,600 •• 920 1:ooo
,,I
PROJECT J1lA)900 I
RESERVOIR STURAGE•ELEVATION•AREAI
AC•rT FEET ACRE
0. 7t10, o.
2025. 765. 810,
7~oo, 770. !300,
27200, 780, 2b90 .•
Ill o oo, 600~ Sb7o.
2 1llooo. 820 .• 7320.
3q7~oo, 811 o.. 8270,
572ooo. 8bO,. ?280,
7b9~oo. 88 0 .• I ~IJ o o .•
98Booo, 900, 11590,
12211~(10. 920 ·• 11%0,
11Jo7ooo, 9110, 12320.
1717noo, 9b0, 1?b50.
1 973ooo, 980, 12980,
223bnoo, 100 0. 13280,
2So4ooo. 1o2o~ 13520.
2776000. I OliO~ I 3740,
305Jnoo, lObO, 139bO,
lBSooo. lll80, IIJ I 7 0 ~
3t~2onoo. II 00, 11J390.
H1onoo, I 12 0 ·, lllb20.
11033200, 1128. I <;212,
TAILWATER•FLOW RELATIONSHIP 1
FEET CFS
'100. o.
400, 1onooo,
MONTHLY l~lNIHUH IIJS THE AM FLOWS IN
30, 30~ JO, 30, 30,
MONTHLY DIVERSION RE:QUIREI·lf:'NTS IN
0. 0. 0. 0. 0.
MONTHLY RESERVoiR EVAPOflATION HI
o,_ _n, .o. 0. 0 0
'~
CFSI
30, JOe
CfSI
0. 0.
!IJCHES i
0. 0 •.
CHAKACHAHNA PROJECT UPERATIUfJ STUDY
tt/H,H&CF,BECHTEL CIVILIJ.MINERALS INC,,sF.
ALASKA POWER AUTHORITY
ALTERNATIVE D! CHAKACHATNA TUNNEL, WITH FISH RELEASES
3 () ·•
0.
0 •.
30, 30, 30, 30,
0. u. 0. 0,
,_ .. 0. .. ·-q L .. ___ ,_0 ·, o.
.~· ,.....__..._
r
DATE 32383 2
.....--r-"-"' -r--' .·:r:c: ~ -·ri'T":· ,,.,...__ ..--. ~ r----=-.. -----=, .-, ~.,...., ,.....___-.,
'• I '. \_-i~l < ! I ~-,, ..
CHAKACHA~NA PROJECT OPERATION STUDY
H/H,H&CF,BECHTEL ClVlL&MINERALS INC 11 SF 1
PROJECT lllA790oi ALASKA POWER AUTHORITY DATE. 32383 PAGE J
ALTERNATIVE Dl CHAKACHATNA TUNNEL, WITH FISH RELEASES
INFL(l;o~S TO THE LAKE I IJ C F S
YEAR JAN FEB MAR APR ~lAY JUNE JULY AUG SEPT OCT NOV DEC AVEYR CALYR
1 40(); 307, 2b71 3931 3o37. bB3 7 ·• 11209, 93 371 31115, 1439, 799, 870, 32?.0, !9b0
2 617, 589. IJ70, 31161 18 81 • 7'183~ 12808, 108991 622'5, 1586, 8113. &96. 37o7, 1Qb1
3 b3J. Slll • 4 71. 4701 12b5, 7925. 13149, 104111 55421 1197. 863. o131 35'lO, 19b2
Ll tt98~ 357, 315, 3371 1801~ 4735~. 132491, 12208, S8tt7, 2056, 930, 7 I 0, 35871 19b3
5 Jot~. 435, 332. u771 1830, 8093. 10700, 11798. 42Libl 12LIS, 909, bb2. 3LI2LI, 19btl
b Ul9: 219, 337, 3981 128b. 3ll90~ I 3 Oil b. 1051&. 10802, 21 JL( 597, Llbb, lbiJ 1. !965
7 388 3Jb, 350, IJ 1 0 • 1893. 8072. 10303, 99741 bbOB 1 1953, 9 I 0, 31 3 1 34S9, !9bb . r 6 531 1 41J9, 36ll, a6ol 2030. B7bl~ 11J931. 15&95, 61911 201JO. 12151 5711 4473, 1907
9 SJIJ, 5 I 0, 4671 ol01 299b, 7aoa: 131171 112571 27931 91b, -b89 1 b121 3532, 1968
1 0 IJ8S, 4Bb, 500, b521 !9LI8, 9271: 12510, 7297, 27931 3057, 121 51 SIJ1, 3Hb 1 19&9
11 U97. 50/J, 550, 8991 22b5, b789: 103&0, 798&1 273/J, 1359, 742, Ub0 1 29291 1'HO
MEAN S I i: Ll30, IIOLI, 53b, 207&, 7251: 123071 10671. 51751 1729, 883, 592, 35u7,
MAX 817~ 569, 550, 89'll 3b37. 9271: 111931, 156951 10802. 3057. 1215, 870. L147J.
. MIN 3b1J. 219, 2b7, 3371 1265. 3li90. 10303, 7297. 2734. 91b, 5117. 313. 29?.9,
41
-ill CHAKACHAMNA PROJECT OPERATION STUDY
H Iii, H & C F 1 13 E C H TEL C I V I L & MINERALS INC.,SF.
PROJECT 14879001 ALASKA POWER AUTHORITY DATE 32:583 PAGE
ALTERNATIVE Dl Cl'iAK ACHA PIA TU~INEI., HITH FISH RELE.ASES
POWER RELEASE HJ CFS
YEAR JAN FEB MAR APR MAY JUNE. JUI.Y AUG SEPT OCT NOV DEC AVEYR CALYR
I 3673: 3567. 3266, 2903. 2726, 2550'. 21129. 2478. J07b, 31 Lib. 3798, tq 87. 31sn. 1%0
2 3939: 3828. 3384. 3 1 i I • 2821. 2727: 2507. 21l79. 2725. 31116, 3798. tl!ll7. 32.? I • lllbl -3 3ClH, 3828. 3381. 3 111 • 2923. 2727. 2506. 2555, 2725. 3146. 37Cl8, 10113. 321J8. lllh2
" . 3ClH~ JIB I. 3508. 3 Ill • 292/l. 2825~ 2591. 2556, 2725. 31116. 37Cll:l. tlt87. 3262, 1Clb3
5 3Cl3Cl, 3828. 3 381. 3 I I I • 2Cl23. 2727, 2590. 2556. 2725, 3146. 37Cl8, 4187, 3243. lllbll
..; b 393Cl. 3831. 35o8. 3 I 1 I • 29211. 2825. 2680. 2o3B. 2725, 31116, 3798. tq87, 3271J. 1965
7 3Cl3Q~ 3831, 3'508. 3 I I I , 29211. 2727~ 2'590. 2556. 2725, 31116. 3798. tq87. 32'53, lllbb
6 3939, 3831. 3'508. 311 I , 2821. 2727, 2507. 21l79. 2725, 3146. 3798. 1118 7. 3232, 1 Cl6 7
..; 9 393Q. 3828. 3384 • 3 I 1 l , 2821. 272o. 2507, 21179, 2725. 31116, 3800, 113113, 32311, t9bll
1 (I 3939~ 3831. 3508. 3 1 1 1 • 29211, 2727: 2507, 2555, 2725, 31116. 37ll8. llj87, 3247, lqbq
1 I 3939. 3828. 3l811, 3 I I 1 • 2821. 2726. 2590 • 25So. 2811, 32119, 3800. 113118, 32611, lll70 .., Hts: 2728 •• 11EAN 3806, 3112ll. 3oll2, 2868. 254o. 2535, 2765, 3156. 3799, 11230, 3239,
-MAX 3Cl3Q~ 3831. 3508. 3 1 I l , 2Cl2LI. 2825~ 2680, 2638, 3076. 324Cl. 3800. 43118. 327b,
MIN 3673. 35o7. 32bb. 2Cl03, 2726. 2550. 2429. 2478. 2725. 3146. 3798. 4187. 31 so.
-
,,..........~) . .---.., ~~·......_, .-----
' l/ ---l
J
,r--, r-", ,......--u-,! -1'TG ·-r"-\ .......-.., ·1TGJ· ,......_, --~ ----...-..... -_.,..,.___,..,_~ ~ ~-~ \ " \,I ' '. I J ; : ' -· J
C HAK AC HAf~NA PROJECT OPERATION STUDY
H/H,H~CF,HECHTEL CIVIL&MINERALS iNc.,sF,
PROJECT lt1a7qool ALASKA POrlER AUTHORITY DA H. 32383 PAGE 5
ALTERNATIVE Di CHAKACHATNA TUNNEL, WITH FISH RELEASES
SPILL Itl CFS
YEAR JAIJ FEB MAR APR MAY JUNE JULY AUG SEPT OCT NOV DEC AVEYR CALYR
I 0~ 0. 0. o. o. o' 1882. b6.2q. 3q. o. 0. 0. 72q, tQbO r 2 0. (I. 0. o. 0. 0. o. lOtiO, lt170 1 0. 0. 0. Su3, lqbl
3 0~ 0. 0. 0, 0. o' 0. 18qb, 2787, 0. 0. 0. :SQO, lqb2
4 Q, 0. 0. 0. 0. o' 0. 0. 2820, 0. o, 0. 235, lqb3
s . r 14381 ltlqi. 0 ·• 0. 0. zuu. lqbU o, 0. 0. 0 I o. o, 0.
b o, 0. o. o. 0. o, o. o. 4042, o. 0. 0. 337, tqbs
7 0. o. o. 0. o. o. o. 0. 2425, 0 ·• 0. 0. 2o2. !Qbb
a ,
0. 0. o. o. o' o. 10757, 343b, o. o, 0. 111\3, lqb7 o. q 0. 0. o. 0. 0. o· 0 .• 5108. 38, 0. 0. 0. 42q, lqb8
I 0 0~ o. o. 01 o. o' o. 0 •. o. o. o. 0. 0. IQbq
I 1 o. 0. o. 0. o. 0~ 0. 0 I 0 1 o. 01 0. 0. 1q1o
MEAN .. 0. o. o. o. 0 0 o' 171. 2b42, 18b8. 0. 0. 0. Jqo.
MAX o: 0. 0. 0 I 0. o: 1882. 10757. 4011?. o. 0~ 0. 11 A 3,
MIN ,
0. 01 o, 0. . ' .. --·-0~. o. o. 0. o. o. 0. 0 I o.
CH AK ACHAMN A PROJECT UPER A TI UN STUDY
H/H,H&CF,BECHTEL CIVIL&MINERALS INC,,SF,
PROJECT Jll.A7900I ALASKA POWER AUTHORITY DATE 32383 PAGE b ...,
ALTEHNATIVE Dl CHAKACHATNA TUNNEL, WITH FISH RELEASES
FISH RELEtsE IN CFS ...,
YEAR JMI FEB MAR APR MAY JUNE JULY AUG SE.PT OCT NOV DEC AVEYR CALYR ....,
I 3o: 30, 30. 30. :so. 30~ 30~ 30, 3o. 30. 3o. 30, 30, l9b0
2 30. 30. 30, 30, 30. 3o, 30. 30. 30, 30. 30. 30, 30. 19b 1
3 30~ 30, 30, 3o. 30. 3 0' 30 ·• 30, 30, 30, 30, 30. 30, 19b2 . ....,
Ll 3o, 30, 30, 30, 30. 3o, 30. 30. 30, 30, 30, 30. .30 • 19b3
5 3or 30. 30. 30. 30. 30. 30, 30, 30, 30. 30, 30, 30, 19bLI
b 3o, 30. 30, 30, 30. 30' 30, 30, 30, 30~ 30. 31), 30. 19b5 ....,
7 3o, 30. 30, 30, 30. 3o' 30. 30. 30, 30, 30, 30, 30, !9bb
6 3o, 30. 30. 30. 30. 30: 3o. 30, 30. 30, 30. 30, 30, !9b7
9 3o, 30, 30. 30. 30, 30~ 30, 30. 30, 30, 30, 3o. JO. !9b8 -I o. lo, 30. 30. 30. 30. 30 •.. 30, 30, 30, 30. 30, 30, lO, 19b9
1 1 3o. 30, 30, 3o. 30, 3o: 30 ·• 30, 30. 30, 30, 30, 30. 1970
' -HEAN 3o: 30, 30. 30, 30. 3o: 30 ·• 30. 30, 30, 30. 30. 30.
MAX 3 0 ~ 30, 30, 30, 30. 30' 3 0 ·• ·30. 30. 30, 30, 3o .• JO.
MIN 3o. 30, 30, 30. 30. 30: 30~ 30, 30, 30. 30. 30, 30. -
....
-
-
~' . ..--~ ~. ~----
(
r--_..._ r--:r--r-:r: ~ (1i tTr:1 ,.._. ~· ~ --·~ -------. ----, ----. __,
l I \_ ,: l L I-~) ''-" J )
CHAKACHAt1NA PROJECT OPERATION STUDY
H/H,H~CF,BECHTEL CIVILM.MINERALS INC,,SF.
PROJECT 1487900t ALASKA PO~IER AUTHORITY DATE 32363 PAGE 7
ALTERNATIVE Dl CrlAKACHATNA TUNNEL, WITH FISH RELEASES
,NET EVAPORATION IN AC•FT
YEAR JAN FEB MAH APR HAY JUNE JULY AUG SEPT OCT NOV DEC AVE.VR CALVR
I 0~ o. 0. 0 1 0. 0~ 0, o. 0. 0. 0. 0. 0. 1%0
2 o, o. 0. o. 0. o, o. o. 0. 0 ·• o, 01 01 19bl
3 o. o. o. 0. 0. o. o. o. 0 1 0. 0. 0 0 0. !9b2
ij -.
0. 0. o. 0. 0~ 01 o. o. 0. o. o. 0. 19b3 o,.
5 0. 0. 0 1 0. 0. 0. o. o. o. 0 0 0. 0. 0. l9bU
b ' 0. 0 1 0 1 o. o' 01 ·o • 0 ~ o. 0. 0. 0. !9b5 o,.
7 o .. 0. 0 1 01 o. o" o. o. 0. 0. 0. o. 0. !9bb
8 o, 0 I 01 ()I o. o: o. o, 0. 0. 0. 0. 0. 1%7
q o, 01 o. 0 I 0. o: o. o. 0. 0. 0. 0. o. !9bll
I 0 o, 0. o. o. 0. 0~ o. o. 0. o. 0 I 0. 0. !9b9
II o. 0. 0. o. 0. 0. o. o. 0. 0. 0 1 0. 0. !970
~1EAN '. 0. 0. o. 0 I o. o: o. o. 0. o. 01 0. 0.
HAX ()~ 0. o. 0. o. o' 0. (). 0. o. o. 0. 0.
MIN o. 0. o. 01 o. 0~ 0. o. o. 0. 0. 0. 0.
PROJECT lll87900t
E,O,P, SlUR AGE JN
YEAR JAN
I 38J0088:
2 335020b~
3 33lblbl.
4 ... . 32904bO~ ...
5 33c;us57,
b 33uJ872.
7 33?4781:
8 33]2892~
9 3372438,
10 32~552?:
II 337!807.
MEAN 33757o7:
MAX 38 ~ 11 oaa;
MIN }2&5522.
ACRE•FT
FEB
3biJOBllll,
3Jb81.>3b,
315192&.
3Q958t15,
Jt57b45,
311)!593.
3i29000.
3i43387,
3179840,
Jii7Bo72,
3185517.
3184755,
3bi.I08114.
3078072,
MAR
31154572,
2987&35,
29711&8,
2697bb8,
29&831.11,
"?904769,
293297&,
?9491152,
;?998b54.
}.89!270,
1009435,
299t>903,
3451!572.
289!270,
,,..::.,...,...
i
APR
33031.106,
282t34b,
2612258,
2730844,
26098471
271.115751
27704951
28149391
281l92b5,
2711Jj90,
287ou52,
284Jo201
3303tJOb,
2730811/.j 1
CHAKACHA~NA PROJECT OPERATION STUDY
H/rl,H&CF,AECHTEL CIVIL&MlNERALS INC,,Sf.
ALASKA POWER AUTHORITY DATE 32383
ALTERNATIVE Dl CHAKACHATNA TUNNEL, WITH I'ISH RELEASF.S
MAY JUNE
3357590. 3&10899:
27&17oll.
2700459.
3072&87~
3015991.
2o599u&. 2771825~
2740789. 30'58318,
2o39nto. 267&807,
27o525ll. 3021533',
27o'ltJ59. 3!2173&~
2858!81. 3tS8Ho.
2&81330.
28401121.
30b8954~
307999o,
27921131. 305977&:
3357590, 3&!0899~
2b39(l10. 2o7o80?_.
JULY
403320(1,
J70il237.
3668577.
3 'l25 34 5.
3555lbb,
3312371,
3119391.12.
l8638211.
380931.10,
3b82t8!.
3555938,
3647&117·.
4033200,
3312371.
AUG
tln33200,
4033200,
4033200,
4017005.
40332001
37911930.
39118239.
40332001
4033200.
3971897,
3887997,
39835701
40332001
37949301
-I
SEPT OCT NOV DEC
tlll33200, 392&373. 37tlb127, 351J03111,
11033200, 3'1351112. 375778tl, 351ll272,
4033200, 39111193, 373505&, 3503872,
40332001 ]9t;,t1311, 379J8b0 1 3571;)209,
110332001 39!4/llllll 374071~11. 3522!111,
11033200. 3967877, 3775&\21 J5llll957.
40332001 3957978, 3781J337 1 35114275,
4033200, ]9&33271 3607835, 3583o37 I
11033200 I 38979011, 37!09791 31.179733.
3971Jt5bl 3966816, 381!321l. 3585281,
3861o2o. 37&3544. 3579772. 3338880.
110111053, 39211498, 37119221. 3523&88,
4033200. 39&7877. 38!1324·, 3585281,
3881o2b, 37&35111.1, 35797721 3.5388801
,...:---:
PAGE: ll
AVEYR CALYR
37091'51, 19b0
3430&10, I 9b 1
340b71lO, 19b2
335451J3, !9b3
3II073bbl !9bll
33lb38!1 19b5
3387tb7, !9bb
3452&57. !9&7
311484b0, 19o8
33933331 t9o9
33bli215, 1970
3424bOb 1
3709151.
33!b38!1
-~ I
r--. -"" ;----. -CT:: f!1 r:r [1T; , ... ._ ,...__ ---"! ------· -· ~--=-...., ----' J -; -·
CHAKACHAMNA PHOJECT OPERATIOM STUDY
I 'll\7900 t ~l/H,ti&CF ,BECHTEL CIVIL&MINERALS INC,,SF.
PROJECT ALASKA POWER AUTHORITY DATE 323!!3 PAGE 9
ALTERNATIVE Dl C rl A K A C H A Tl'l A TUNNEL, WITH FISH RELEASES
E,I),P, LAKF. LEVEL JIJ fEET
YEAR JAN FEB MAR APR MAY JUNE JULY AUii SEPT OCT NOV DEC AVE'fR CALYR
I II 0 0 ~ I I 0 0 • 1080, 1noo, 1080. 1080~ 1120, 1120. 1120, II 2 0 • I I 0 0 • lo8o. 1097. ICJbO
2 1080. I OoO, I 0 tl 0. 1 o4 o. 1020. lObO. 11 0 0. 1120. 1120. I I 2 0. I I 0 0, lOBO, 1078, 1% I
3 1080~ lObO, I 0 tl 0. I (Ill 0. 1020. IO'lO~ I I 0 0, 1120. \120, I 12 0 • II 0 0, 1()80, 1077, 1962 u 1000. lObO, 1040. 1020, 1020, 1020, 1080, 1120. 1120, 1120. II 0 0, I 0 8 0, I o 7 o, 19b3 s 108o: lObO, I 0 tl 0, 1 olt o, 1020, lObO~ 1080, 1120, 1120, I I 2 0 , II 0 0, I 0 8 0, I 071, 19btl
0 lObO. IOoO. 1040, 1020. 1020. 1020. lObO, 1100, 1120. 1120, 1100, 1080, 1067, 1%5
7 10oo: lObO, 1040, I 0 2o) 1 1020. 1040: 1080, 1120, 1120, 11201 11001 1080, 1072, 19bb e lObo: lObO, 1040, I 0 4 0 I 1020. looo: 1100, I 12 0, 1120. 1120, I I 0 o, I 0 b 0 I I o 7 7, 1%7 q 1080. lObO, 1040, I 0 tj I) I I 0 /J 0, IOoO. 1100, 1120, 1120, 1100, I I 0 0 I 10&01 1078, 1%8
I 0 lObO~ I OoO, 1040, 1020, 1020, lobo: I I 0 0, 1120. 1120. I 12 0, II 0 0 • lOBO, 107~. 1%9
I I 1080. IOoo. I 0 4 0, 1o'lo. I o 110. I OoO •• 1080, II 0 0, 11 0 0. II 0 0 • 1080, lOBO, 1072, !970
tlE AN 1 o73: IOo4, 104tl, 1oJS, 1029. 1051~ 1091, Ill b. 11 18. I II b, 1098, 1080, I 0 7 b •
MAX ti 0 0 ~ II 0 0. 1080, IOoO, 11180, 1 oso·. II 2 0. 1120, 1121). 1120, 11 o o • 1 oa o. I 097.
MIN 1000. lObO, 1040, 1020, 1020. I 020'. IOoO, 110 Q 1 1100, 11 0 0. 1080, lOBO, 1067,
CHA K ACHA 11N A PROJECT OPE RAT ION STUDY
H/ti,H&CF,BECHTEL CIVIL&MINERALS INC,,SF,
PROJECT I487900J ALASKA POwER AUTHORITY DATE 32363 PAGE. I o
ALTERNATIVE 01 CHAKACHATNA TUNNEL, 'IIITH FISH RELEASES
WATER BALANCE
YEAR JAN FEB HAR APR MAY JUNE JULY AUG SE.PT OCT NOV DEC AVF,YR CALYR
I 0~ 0. 0. o, o. 0~ . n. 0, 0. 0. 0. 0. 0. 19b0
2 o, 0, 0 0 o, 0 ·• o. o. 0. 0. 0. 0. o. 0 1 I 9b I
3 o, (I. 0. o. o. o· 0. o. 0. 0. 0 0 0. 0. 1962
/J o, 0, 0. o, o. o' o. 01 o. 0. 0. 0. 01 19b3 , .
5 o, 0. o. o, o. o. 0, 0. 0. 0. 0. 0. 0 1 19bll
b o, 0. 0. o. 0 ·• o' o. o. 0. o. 0. o. 0. 19b'5
7 o, 0. 0. o, 0. o' o. 0 I 0. o. o. 0. 0. t96b
8 0. o. 0. 0 I o. 0 •• o. o. o. 0. o. 0 1 0. !967
9 o: o. o. o. o. o' 0, o. 0. o. 0. 0. 0 I t9b8
I 0 Q, 0. o. o. 0. o' o. o. 0. 0. o. o. o, !9b9
II 0, 0~
.. ,
0. 0. o. 0, 0 1 1970 0. o. 0, o. o. o.
~1EAN '. o. 0 1 o. 0. 0. o' 0. o. o. o. 0, 0. Q 1
HAX o'. o. 0, o. 0~ o' o. o. 0. o. 0. o. 0.
MIN o: 0, 0, f o. 0. Oo 0 0 o. o, o. o. o. 0.
-.----.,
j ,.._.......,
' I
~ ~ I -r-. -rrr:: ~ ·~ err; ;r-. r--t----, ~ ~ -=---, ---, --~ ~ ----y .J
CHAKACHAMNA PROJECT OPERATION STUDY
H/H,H&CF,BECHTEL CIVIL&HINERALS INC,,SF.
PROJECT 141\7900l ALASKA POwER AUTHORITY DATE:: 32363 PAGE:: I 1
ALTERNATIVE Dl CHAKACHA HIA TUNNEL, WITH f 1 S~i RELEASES
POWER IN Mw
YEAR JAN FEll HAR APR HAY JUNE JULY AUG SEPT OCT NOV OE:.C AVEYR CALYR
I lBO~ I 7 0, 153, t37, 125, 121~ I I 9, 125. 137. 15 7. 180. I 9b, 1 c;o, 19b0
2 lBO, 170, 153, t37. 12S. 121, 11 q. 125. 13 7. IS 7, 18 0. t9b, 1501 19bl
J lBO. 1 7 0. IS3. tH. 125, 121. 11 q. 125, 13 7. 157, I 8 0. t9b, I c; 0, !9b2
4 tao: I 7 0, IS 3, 137. 12S, 121~ II 9, 125, 137, 1 s 7 ·• 180, t9b, 150, 19b3
5 lBO. 1 7 0. 15 3. I 37. 12S. 121. 11 q. 12S, I 3 7', !57, I f.\ 0. t9b, ISO, 19bU
b tllo: 1 7 0. !53. 137, 125. 121~ 11 q. 125, 137, !57, 180, 19b, 15 0. 19b5
7 tBo, 170. 153, 137. 12S. 121, I 1 q, 125o 137. I 57. I 80. t9b. 1'50. lqbb
8 )Bo, 170. 153, !37. 125. 121, II q, 125, 137. IS 7, !80. I 11b, 15 0. lqb7
q tllo, 170, I 53, 137. 125. 121, II q • 125, 137. 157, lBO I I 9b I I so I !9b8
I 0 tao, 170, 153, 13 7. 125, 121, I I 9, 1251 137. I 57, lf.\0, t9b, I '50 I 19t>Q
II lllO. 170. IS3, 1 3 7. 12S. 121. II 9, 125, 137, IS 7. 180, 19b, 150, 197!\
MEAN llln: 170 1 153. !37 0 125, 121 •• 11 q. 125. 137. IS 7, lBO, I 9b, I 'iO,
MAX !Ill): I 7 0, !53, 137 0 125. 121' 11 '1. 125, 137, IS 7. 180. lqbl 1 c;o.
ri I"' 1t1o. I 7 0, IS3, 13 7. 125. 121~ II 9, 12So 137. lS 7. 180, t9b, I SO,
CHAKACHAHNA PROJECT OPERATION STUDY ..
lt187900J
H/H,H&CF,BECHTEL CIVIL&MINERAL.S INC.,SF,
PROJECT ALASKA PO~ER AUTHORITY DATE 32383 PAGt 12 ..
ALTERNATIVE Dl CrlAKACHAHIA TUNNEL., WITH FISH RELEASES
ENERGY IN MWH
YEAR JAil FEB MAR APR MAY JUNE JULY AUG SEPT OCT N()V DEC TOTVR CAL yR
1 1 ~H2o'. I I 8t171. 1135111. 98t~09, 931b2. B73H: 88795, 93162, 986()9, II bll52. 129bOO, 1t1556S, 13172?11, 1960
2 13H2o: I tll386 • II 3541, 98oOq, 931b2. 97339: 88795. 93162, ?8oo9, II btl 52, 129600, 1t155b5, 1313139, 1961 3 133920. 111131:\6. II 3541, 98o09, 931b2. 87339. 88795, 931b2. 9B6o9, II 61152, 129600, 1ll55b5, 1313139, 19b2
II 133920~ li43Bo. II 35111. 96609, 931o2. 87339~ 88795, 93162, 98609, 11b452, 129bOO, i11~5b5, 1313139, 1903
5 I B92o, U8t171, II 3541, 98609, 93162. 87339, 88795, 93162. 986o9, 1161152, 129600, 1115565 1 13172?.11, 1964
6 1~3920. 111138b, 113541, 98o09 1 93162. 87339. 88795, 93162. 986o9, 116452, 1296oo. 1ll5565 0 !313139, 1905
7 I ~392o: 114386, 113541, 98t.09, 93162. 87339: 88795. 931o2. 98oo9, 11bll52. 129bOO, 145565, 1313139, l96b
8 1 B92o: 1111386, 113541, 98o09, 93to2, '37339' 88795, 93162, 9R6o9, 11b452, 129600, 145565, 1313139, 1967 9 IH920. I 18il71, 113541, 98b09. 9311.12. A7339: 88795. 93162, 96oo9, 116452, 129boo. 1115565, 13172?4, 1908
10 133920~ ii438b, 113541, 98o09, 93lb2, 87339' 88795, 931o2. 986()9, 116452, 129bOO, !1155b5 0 !3!3!39, 1969
II IJ3Q20. 114386, 113541. 98o09, 93162, 87339~ 88795, 93162. 98609, 116452. 1296oo. 145565, 1313139, 1970
~lEAN 13392o: 115500, 113541, 98o09, 931o2. 87339: 88795, 93162, 98609, 116452, 129bOO, 145565. 1311l253.
MAX 133921')~ I 18 t17 1 • II 3541, Q8o09, 93lb2. Fl7 33<1~ 88795·. 93162. 9B6o9. 1lb452~ l29bOO. 145565. 13172?11,
H!N 133920. i!4386, 1135111. 96609, 931o2. 87339. 86795, 93162. 98609, 116452. 1296oo. 145565. 1313139.
~ ,..__., r--r-; -rrr: 7ll --rr:; .-. __, ---. -'1 ~ ~ I
' '·
CH/IKACHA~NA PROJECT OPER/ITIUtJ STUDY
14A7900J
H/H,H&CF,HECHTEL CIVIL&MINERAL.S INC.,SF,
PROJECT ALASKA POWER AUTriURI TY DA Tl 32383 PA(;t 13
ALTERN A Tl VE D I CHAKACHATNA TUNNEL., WITH HSH REL.E.ASES
ENERGY DEFICIT ytJ MWH
YEAR JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT NOV DEC TOTYR CALYR
I 0~ 0. 0. o. 0. 0~ o. 0. 0. o. o, 0. 0. !9b0
2 o, 0. 0. 0, 0 ·• o· 0. o. 0. 0. 0. 0. 0. l9bl
3 o, 0. 0. o. 0. o' 0. 0. 0. o. 0. 0. 0. !9b2
lj o. 0. o. 0. . o. o·. 0. o. 0 • o. 0. 0. 0 I 19b3
5 0~ 0. 0. 0 1 o. o· o. o. o. 0. o, 0. 0. 1Qb4
b 0. 0. 0. 0. o. 0~ 01 0. 0 1 0. o. 0 0 0. !9bS
7 o: 0. 0. o. 0. 0 ·• o. 0. 0. 0. 0. o. 0. 1966
6 o. 0. 0. 01 0, o: 0. 0. 0. 0-. 0. 0. o, !967
9 0. 0. o. o. o. o. 0 -· 0. 0. 0. o. 0. 0. !96A
I 0 0~ o. 0. o. 0. 0~ 0 •. o. 0. 0~ 0. 0. 0. 1969
II o. 0. o. 0. o. o. o. o. 0. 0. 0. 0. 0. 1970
~lEAN . 0. 0. Q I 0. o: 0. (). 0 0 o. 0. o. 0. 0.
MAX ()~ 0. 0. 0, 0. o' 0 ·• o. o. o. 0. 0. 0.
MIN o. 0. 0. 0 0 o •. 0: _. 0. o. o. o. 0, 0. 0.
CHAKACHAMNA PROJECT OPERATION STUDY
tus79ooi
H/H,H&CF 1 BECHTEL CIVIL!IMINERAL.S INC.,sF. PRUJEC T ALASKA POWER AUTHORITY DATE 32383 PAGE ItA
ALTERNATIVE Dl CHAKACHATNA TUNNEL, WITH FISH RELEASES
AVERAGE. GEfJ('RAT I 0/J IN M~ IN MONTHS UF SPILLS
YEAR JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT NOV DEC AVEYR CALVR
I 0~ 0. o. o. o. o' 221. 300, IIH • 0~ 0. 0. ss. 19b0
2 o, 0. 0. o. 0. o' o. 282. Joo. 0. o. 0. a9. t9bl
3 C>, o. 0. o. o. 0 •• 0. 227, 281), 0. 0. 0. 112. 1962
lj o, 0. 0. o. o. o· o. o. 282. 0. 0. 0. z.s. 1963 s o, 0. o. o, 0. or o. 204. 214, 0. o. 0. 35, l9bt.l
b o, 0. o. 0. 0. o: o. Q I Joo. o. 0. 0. 25, ICI65
7 o, 0. (l. o. o. o' o. o. 262, 0. 0. 0. 22, 196b
8 o. 0. 0. o. 0. 0 ·: 0. Joo. Joo. o. 0. 0. so, 19b7
q o; 0. o. 0. 0. o' 0. 300, 140, 0. 0. (j • 37. 19b8 p
I 0 0. 0. 0. 0. o. o, o. o. o. 0. 0. 0. 0. 19b9
l I o: o. 0 • 0. o. o. 0. o. o, 0. 0. 0 1 0. 1970
MEAN . ,
0. o. o, 0. o·. 0. 20, 11.17. 202. 0. 0. 0. 31.
MAX 0~ 0. 0. o, o. 0~ 221 ~ 3oo. 300, 0 ·• 0. o. ss.
MIt~ 0. 0. 0. o. 0. .o. 0. o. 0. 0. 0 0 0. f),
-.~ ,,.....__...,
... r--. r""""-r-: r-: ~-~ ,--, rn r;r: ,-----,., ____, -~ .---, -----., .....--...
'
---, ~ ~. ,J j
~ ., C HAK h C HA f1NA PROJECT OPERATION STUDY
H/H,H&CF,HECHTEL CIVIL&MINEflALS INC.,SF.
PROJECT 1liRHOOt ALASKA POWER AUTHOHI TY DATE 32383 PAGE 15
""" ALTERNATIVE Dl CHAKACHAHIA TUNNEL., WITH FISH RELEASES
SURPLUS EI~ERGY IN M;-4H
""'
YEAR JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT NOV DlC TUTYR CALYR
""" I 0~ 0. 0. 0. 0. 0 ·• 75427. 130038. 2679. 0. 0. 0. 2081llll, 19&0
2 o, 0. 0. o. o. 0~ 0. 1lb782, 117391. o. 0. 0. 2.341711, 19bl
3 0. 0. o. 0. 0. 0. 0. 75918. I03lbb. 0. I). 0. 1790AU, 19b2
ll 0~ 0. 0. 0. 0. 0~ o. o. 101131)8, 0. 0, Oo !Oil368o 1Qb3
5 0. 0. 0. 0. o. o. o. 58541. 5572Uo 0. o, 0 0 111126So 19bll
b
, o. 0. o. 0. 0~ o. o. 11739 l. o, o. o. 117Hto !965 o,
7 o, o. 0. 0, o .. 0. o. o. 89921. o. 0. 0. 8992lo l9bb
8 o, Oo o. 0. o. 0 ·• Oo 13110.38. 117391o 0. o, 0. 2471130, 1967
q o, 0. o. 0. 0. o: o. 130038o 2535. o, o. 0 0 1325730 19b8
I 0 o, o. o. 0. 0 ·• o' o. Oo 0. 0. 0. 0. (). 1Qb9
11 0. 0. 0, Oo o. 0~ 0. 0 0 0. 0. 0. 0 0 0. 1970
HEAN o: 0. o. 0. o. o' b857. 56305. b4597, o. o. 0~ 1297'59,
MAX o: o. o. 0. 0. o: 751127. 130038. 117391, 0. 0. 0. 21171l30,
MIN o. 0. o. 0. o. 0 •. 0. 0. o. 0. 0. 0. 0 0
C HAK ACH A f1NII PROJECT OPERATION STUDY
H/H,H&CF,BECHTEL CIVIL&MINEHALS INC 11 SF,
PROJECT lii87900i ALASKA POWER AUTHORITY DATE 32363 PAGt I 6
ALTERNATIVE Di CHAKACHATNA TUNNEL, WITH fiSH RELfASf.S
RE~tAINlt!G SPILLS IN CFS
YEAH JAN FEB MAR APR HAY JUNE JULY AUG SEPT OCT NOV DEC AVEYR CALYR
0. 0, 0. 0. 0. 0 •• o. 311'10, 0. 0~ 0. 0. 2fl7, !960
2 o: 0. 0. o. o. o' o. 0. 2911. o. 0. 0. 25. I 96 I
3 o. o. 0. o. 0. 0·. o. o. 0 0 0. 0. 0. 0. 19&2
4 0~ o. o. o. o. o· o. o. 0. o. 0. o. 0. jQb3 r 5 o, 0. o. o. 0. o, o. 0. 0. o. 0. 0. 0. t96ll
0 o. o. o. o. o. o. 0. o. Bo7, o. 0. 0. 72, !965
7 o: 0. 0. 0. 0~ o: o. 0. 0. o. o. 0. 0. t9bb
8 o, o. o. 0. o. 0~ o. 73b8. 2oo, o. 0. o. b3b, 19&7
9 0 • 0. o. o. 0. o. 0 .• 171 q. o. o. o. 0. ill3, t9bB
I 0 . o. o. o. 0. 0~ o. 0. o, o. o. o. o. !969 o,
11 0. 0. 0. o, 0. o. o. 0. 0. 0. o. 0. 0. 1970
t1EAN o: 0. o. 0, 0. o: o. 1139. 129, 0 ·• 0. 0. I Ob,
MAX 0~ 0. o. o. o. 0~ o. 73oB. 8o7, 0. o. o. b3b,
MIN 0. 0. o. o. o. 0. o. o. 0. 0. o. 0. o.
-,--,
I ' ,
-,-
PROJECT l41l79001
INSTALLED CAPACITY: 330~00. KW
ANNUAL PLANT FACTOR: .45
OVERLQAE FACTOR: 1.00
PLANT EFFICIENCY: .850
FRICTIQN LOSS COEFFICIENT: .000002370
STARTER CAPACITY: 50~0. CFS
TOLERAII!EE! • 010 PERCENT
MONTHLY LOAD FACTORS:
,,.....,.-, ._. I J
,.,...,_,
'J '· I " ~· I~ ,,,
CHAKACHAMNA PROJECT OPERATION STUDY
H/tt,H&CF,OECHTEL CIVIL&MINCRALS INC.,SFo
ALASKA POWER AUTHORITY DATE 32483
ALTERNATIVf E! MCARTIIUR SHORT TUNNEL, WITH FISH RELEASES
.640 .620 .610 .640 .700 .BOO .920 1.000 .920 .A70 .780 .700
INITIAL LAKE STORAGE !4'177500. AC-FT
MINIMUM LAKE STORAGE !3377750. AC-FT
~AXIMUM LAKE STORAGE :4477500. At-FT
-..,
J
--,
i
PAGE
) . -
CHAKACIIAMNA PROJECT OPf.RATION STUDY ( IIIHtii&CFoOECHTEL CIVIL&I-1INERALS INC.,SF.
PROJECT 14879001 ALASKA POWER AUTHORITY DATE 3?.483 PAGf 2
ALTERNATIVE E: MCARTHUR SHORT TUNNEL• WITH FISH RELEASES
RESERVOIR STORAGE-ELEVATION-AREA!
AC-F T FEET IICRE
0. 76 0. 0 0
2C25. 76!). 810.
7300. 770. 1300.
27200. 780. 2£,90.
lllO'JO. 809. 56 70.
241 J ao. 820. 7320 0
397~oo. P.4 0. 8270.
572~('0. 86 0. 9280.
769030. 880. 1 D 4 O'J.
9AI_lSOt'. 9CO. 1159:1.
1224000. 920. 119€-:J.
1467000. 94 0. 12320.
17170GD. 96 0. 1265::1.
197301)0. 981). 12980.
2236000. 1CGO. 132110.
25~4~('0. 1['20. 13520. -2776800. 1040. 1371t0.
3G53ilOO. 1 06 r. 13%0.
333500C. 1 08 0. 14170.
36200CO. 1100. 14391).
391GOOt'. 112 c. 14620.
42180()~. 114 0. 1610('.
425')()~0. 114 2. 16788.
447751)C. 1155. 17842. -TAILIJATER-FLOII RELATIONSHIP:
.....
FU:T CFS
21'J. lJ: •
21~. 100000.
110NTHL Y MI IJH1UM INSTREAM FLOWS IN CFS:
1 a 9'1. 1 G9 4, 1 0 9 4. 1094, 1 0 9 4. 36 5. 365. 365. 36 5. 365. 365. 1 09 4.
MONTHLY DIVERSION REQU IR [11ENTS IN CFS: .....
0. ' J • 0. G • o. 0. o. 0. o. 0. 0. 0. .....
f10NTIILY HE~ERVOIR EVAPOKATilitJ IN lNCtlES:
:_;;._ 0. a. 0 0 a • a. 0. o. 0. o. 0. o. 0.
ltJ ,---. -,...----~---:---,.....--,...._._., '--"l ,....~, ,....._......, ,.............., .----..; ~ .------, -.... -----1 I i
PROJECT 148'{9('01
l~FLO~S TO T~E LAKE IN CFS
YEAR
1
2
3
4
5
6
7
r.
9
lG
11
12
13
14
15
16
17
lS
19
2C
21
22
23
24
25
26
27
28
29
30
31
~lAX
MIN
MAY
4513.
2055.
38J1.
2027.
3992.
3434.
2193.
2936.
4393.
24%.
3120.
3637.
1flfl1.
1265.
18;)1.
Ul3il.
1286.
189.3.
20.30.
2996.
1948.
2265.
4~63.
3468·
2131.
4215.
4 784.
5283.
5335.
5387.
6776.
32G1.
6776.
12E.5.
JUIH:
10728.
8572.
10719.
8 2 04.
13247.
9002.
6826.
74 75.
14R17.
9930.
9459.
6A37.
7983.
7925.
4735.
8093.
3490.
8H2.
8761.
78(18.
92 71.
6789.
12672.
8228.
7115 7.
6248.
10649.
8587.
19 !l64 •
7917.
8514.
8991;.
19R64.
3490.
JULY
1522 o.
13194.
13 095.
12575.
13355.
12091.
12996.
14601.
13149.
1Qlf.3.
10388.
1120<1.
12808.
1314 0..
13249.
1070G.
11633.
1(1303.
14931.
13117.
12478.
1Q360.
13 69 5.
13'190.
A 851).
6 781.
1~889.
8 3 04.
13898.
lfll'16.
8958.
11928.
1522 Q.
6781.
AUG
11615.
10548.
8831.
94 31.
1 (lfl 08.
12046.
9983.
10235.
1 0 4 05.
8691.
11731.
9337.
1 0 8 99.
10411.
12208.
11798.
11929.
99 74.
15695.
11257.
7297.
7986.
16680.
9263.
7 8 09.
6159.
68 02.
64 94.
112 24.
7865.
9157.
10147.
16680.
6159.
,:r;
CHAKACHAMNA PROJECT OPfRATION STUOY
Hllloii&CF.BECIITEL CIVIL&MINERALS INC.,SF.
ALASKA PO~ER AUTHORITY OATE 32483
ALTERNATIVE E: MCARTHUR SHORT TUNNELo Wlltl FISII RELEASES
SEPT
6305.
4 521.
8635.
3562.
45~5.
6075.
5068.
5 94 0.
6910.
3452.
3662.
3145.
6225.
5542.
5847.
4 24 6.
10802.
6608.
6191.
2793.
2 793.
2734.
5075.
5012.
2794.
6850.
5107.
4 94 7.
6G59.
4513.
4572.
5177.
10AG2.
2734.
OCT
2689.
1761.
3216.
2712.
2002.
2787.
1988.
2053.
2707.
1896.
13 70.
1439.
1586.
1197.
2086.
12 45 •.
2114.
1953.
2040.
976•
3057.
1359.
3181.
2396.
2527.
3059.
3136.
3917.
3709.
3258.
4471.
2383.
4471.
976.
NOV
802.
5b9.
842.
865.
629.
755.
595.
583.
793.
526.
654.
799.
843.
863.
930.
909.
597.
91 !l.
1215.
689.
1215.
742.
1090.
679.
740.
909.
814.
1058.
922.
706.
1412.
828.
1412.
526.
DEC
636.
532.
699.
642.
550.
619.
532.
565.
562.
4 83.
5 08.
8 70.
696.
613.
710.
662.
466.
313.
5 71.
612.
601.
460.
736.
514.
623.
53!).
622.
1055.
700.
7 () 1 •
882.
621.
1055.
313.
JAN
542.
495.
63n.
523.
52 7.
578.
504.
569.
569.
426.
400.
877.
633.
498.
364.
419.
388.
531.
534.
485.
497.
394.
581.
495.
558.
. 498.
544.
1 04 4.
6J9.
597.
76 2.
551.
FEfl
488.
472.
495.
477.
472.
507.
475.
536.
51'Jo
468.
307.
589.
541.
357.
435.
219.
336.
449.
510.
486.
504.
441.
?31.
492.
526.
485 •
524.
773.
537.
562.
718.
4 91.
773·
219.
MAR
4 9 3.
450.
467o
4 7 7.
458.
466.
4 4 Q.
505.
489.
'14 9.
26 7.
47C.
471.
315.
332.
33 7.
35 ['.
384.
467.
50 C..
55-).
513.
492.
480.
?01.
41'5.
498.
606.
5 (l "'· 547.
64 7.
647.
26 7.
APR
541.
631.
510.
641.
541.
487.
4 96.
598.
6 75.
526.
3 9.).
346.
4 70.
337.
4 77.
398.
410.
88~.
63~.
6 52.
899.
12 75.
4 79.
585.
554.
4 89.
6 25.
6 es.
558.
713.
810.
588.
12 75.
337.
PAGE 3
AV[YR CALYR
4 54 8.
3 65 0.
4 32 8.
3 511.
4 ;:>57.
4 0 71.
35C9.
381'3.
4 665.
3292.
3522.
3 296.
3 75 3.
3539.
359P..
34£!5.
3651).
3 52 3.
4465.
3 531.
3426.
2943.
4940.
3 759.
292 3.
3 059.
3 75 0.
3556.
5327·
3576.
3973.
3 781.
5 32 7.
2923.
1950
1951
1952
1953
1954
19~5
1956
1957
1958
1959
1960
19n
1962
1963
1964
1%5
1%6
1967
1968
1%9
1970
1971
1972
.!.97~
1974
1975
1976
1977
1978
1979
1980
PROJECT l41i79C01
POWER RELEASE IN CFS
YEAR
2
3
4
5
6
7
8
9
H
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
2H
29
3~
31
MEArJ
r~A X
MIN
MAY
183 11.
1962.
1968.
1961.
1952.
1966.
19<;2.
1970.
1959.
196 0.
1971.
1976.
197a.
1975.
19E 2.
1972.
1984.
1977.
1973.
1962.
1 9fl6.
195 7.
1973.
1951.
19<;13.
19(11.
1949.
1947.
1931.
1943.
1938.
1959.
1986.
lo34.
JUNE
1756.
1879.
1867.
lflAO.
1842.
1874.
18136.
1887.
184Co
11>.69.
1879.
1892.
18A9.
1898.
1917.
1891.
1927.
1896.
1889.
18713.
lll99o
1881.
1862.
lf.64o
lllllq.
1&78.
1846.
1850.
1794.
1849.
1836.
Hl70.
1927.
1756.
JULY
1712.
1 782.
1 766.
1 7 8 7.
173 7.
1 781.
1796.
1 78 8.
1 731.
1 7131.
1 79 0.
lilt' 9o
1 795.
18 02.
183 0.
180 5o
1852.
1811.
1 78 3.
1 7 85.
18 0 c.
18 0 3.
1 75 4.
1771.
1813.
1 816.
1 758.
1776.
1 716.
1 7 71.
1 76 3.
178 3.
1 !!52.
1 712.
AUG
lll10.
1813.
1 f< 19.
1818.
1813.
1808.
lll22.
1814.
1814.
le.23.
1820.
1B42e
1 A 19 o
1826.
1843.
1832.
1868.
1845.
1796.
1811.
18 37.
1844.
1793.
1818.
1860.
11!78.
1826.
18 33.
1811.
1823.
1818.
1 826.
11178.
1 793.
C II AKA C H A r1 N A P R 0 J E C T 0 PER A Tl 0 N STUDY
Hllltli&CF, BECHTEL C I VIL&MINfRALS INC. oSF.
ALASKA POWER AUTHORITY D~.TE 32483
ALTEHNATIVE E: MCARTtiUR SHORT TUNNELo WITH FISII RELEASES
SEPT
2004.
2010.
199 5.
2014.
2 011.
2005.
20!l8o
2005.
2002.
2014.
2014.
2016.
20:l4.
2007.
20!)6.
2012.
1 9fl7.
20C3.
2004.
2 01 7.
2017.
2 01 7.
2008.
2 0 J9.
2 02 0.
2029.
2GJ8.
2009.
2r05.
2 011.
2 01 0.
2009.
2 02 9.
1 98 7.
,____, I
OCT
2311.
2315.
2309.
2311.
2314.
2311.
2314.
2314.
2311.
2315.
2317.
2317.
2316.
2318.
2314.
2318.
2314 ..•
2315.
2314.
2322.
2312.
2321.
2309.
2313.
2318.
2310.
2309.
2306.
2307.
23 09.
2303.
2313.
232 2.
2303.
'-r
NOV
2682.
2693.
2681.
2681.
2690.
268;:>.
2690.
2689.
2682.
26 91.
2696.
2695.
::>693.
;:>697.
2687.
2696.
268q.
26P9o
2686.
2704.
2679.
2700.
2680.
2685.
2691.
2681.
2682.
2680.
2681.
2682.
26 78.
2688.
;>704.
2678.
DEC
2954.
2970.
2953.
2953.
2965.
2954.
2966.
2965.
2954.
2969.
2974.
2969.
2967.
2973.
2959.
29 72.
2965.
2964.
2957.
2983.
2949.
297q.
2950.
2960.
2966.
2953.
2954.
2948.
2952.
2 954.
2945.
2961.
2983.
2945.
JAN
2740.
2756.
2738.
2739.
2752.
2740.
2753.
2751.
2741.
2756.
2761.
2751.
2752.
2759.
27 116.
2758.
2753.
2751.
2744.
2768.
2735.
2766.
2735.
2747.
2752.
274 0.
2740.
2728.
2737.
2 74 0.
2728.
274 7.
2768.
2728.
FEn
2614.
2631.
2612.
2613.
2626.
2614.
2628.
2625.
2614.
2631.
2638.
2622.
2625.
2634.
2622·
2633.
2629.
2626.
2618.
2643.
2610.
2642.
2609.
26 21.
2625.
2614.
2614.
2598.
2611.
2613.
2600.
2621.
2643.
2598.
HAR
2360.
2376.
2359.
2360.
2372.
2360.
2374.
2370.
2361.
2377.
23114.
2.~68.
2371.
2381.
2369.
2380.
2376.
2372.
2365.
238 7.
235&.
2386.
2356.
2367.
2371.
2361.
2361.
2343.
2357.
2:'i59.
2345.
2367.
2387.
2343.
APR
213'1.
214q.
2133.
213'1.
2145.
2135.
2147.
2143.
2135.
2150.
2157.
21'11.
2144.
2154.
21'13.
2153.
2149.
2146.
2139.
2159.
2130.
2157.
2130.
2141.
2144.
2135.
2135.
2117.
2131.
2133.
2119.
2141.
2159.
2117.
PAGE 4
AVEYR CALYR
2243.
2278.
2267.
2271.
2268.
2269.
2279.
2277.
2 21i 2.
2 27 8.
2 284.
2283.
2279.
2285.
22R5.
2285.
2291.
2283.
2272.
2285.
2276.
2288.
2263.
2270.
2285.
2280.
2265.
22<;1.
2253.
2265.
2257.
2 27 4.
2291.
2 24 3.
1950
1951
1<;52
1953
1954
lq55
1956
1957
1958
1959
1960
1961
1962
1963
1964
1965
1966
196 7
1968
1969
1970
1971
19 72
1973
1974
1975
197&
1977
1978
1979
198l'
..
...
...
....
-
r--
\ ·-1
PROJECT 14!:179C01
SPILL Ill CFS
YEAR
2
3
If
'j
6
7
8
9
1 n
11
12
13
l'i
15
lli
17
18
19
20
21
22
;:>3
24
25
26
27
28
29
30
31
MEAN
·~r. X
MIN
1585.
0.
0 •
0.
0.
0.
0.
0.
0 •
0.
c •
0.
0.
0.
0.
0.
0.
0.
0.
(\.
0.
0 •
o.
0.
0.
0.
o.
0.
0.
0.
0.
51.
1505.
0 •
JUNE
7878.
0 •
(I •
0.
0.
0.
0.
3 •
0.
0.
a •
0.
0.
0.
o.
a •
~ 0.: •
~ .
0.
c.
0.
0.
0 •
0 •
0 •
a.
0.
0.
6592.
0.
0.
'167.
7871l.
0.
JULY
12'114.
77'J.
3074.
o.
7508.
40'1.
o.
731.
8312,
o.
o.
c.
o.
0.
o.
o.
c.
a.
153 3.
471.
o.
0.
5219.
2584.
o.
Do
3215.
0.
11088.
802.
1436.
1921.
12414.
(1.
JIUG
8711.
7641.
5918.
63 78.
79 01.
914 4 •
6028.
7327.
7'1 97.
52 38.
7217.
2€61.
(,926.
58 03.
'1180.
55 42.
575.
2 R 09.
12805.
8352.
2567.
1P.66.
13793.
6351.
0 •
0 •
3882.
2695.
8319.
4948.
6245.
5791.
13793.
0.
I~ -' ' ,,
CIIAKACIII\I'NA PROJECT OPERATION STUDY
HI H , H & C F , [l E C Ill E L C I VI L& M I N E. R A L S 1 tl C • , SF •
ALASKA POI.IER AUTHORITY DATE 32403
AL TE.RNATI VE E: MCAR TtiUR SHORT TUNNELt !.II TH F I Sit RELEASES
SEPT
3207.
1417.
55'1 6.
454.
140().
2976.
1966.
2841.
3814.
34 4.
554.
35.
3127.
2441.
2747.
1140.
7721.
3511.
309 3.
0 •
0.
a.
1973.
19~9.
o.
l!J7.
2DJ5.
184 4.
2%0.
1408.
1468.
2 Q[l 0.
7721.
0.
OCT
13.
o.
542.
36.
0.
111.
0.
0 •
31.
().
0.
o.
0.
().
0.
0.
0.
o.
0.
I).
7 2.
0 •
507.
0.
0 •
384.
462.
1246.
1~37.
584.
1803.
220.
1803.
0.
NOV
1),
o.
(1.
0.
c.
o.
o.
o.
o.
o.
o.
0.
o.
o.
o.
o.
o.
o.
0.
0.
o.
0.
a.
o.
0.
o.
:~.
0.
0.
o.
o.
c.
o.
o.
DEC
0.
o.
0.
0.
0.
() .
0.
0.
o.
0.
0 •
0.
0.
0.
0.
0.
o.
0.
o.
0 •
0.
0.
0.
().
c.
o.
0.
o.
0.
0.
0.
c.
0.
0.
JAN
0.
0.
0.
0 0
0 •
o.
0.
0.
o.
o.
0.
0.
o.
o.
1).
0.
0.
o.
0.
0.
0.
0.
0.
0.
0.
0.
a •
0.
0 •
o.
0.
Q.
0.
0.
FEO
0.
0.
I) •
0 •
0.
o.
0 •
c.
o.
0.
0 •
0 •
0.
0.
I) •
0 •
0.
0.
0 •
() .
0.
o.
0 •
0 •
0.
0.
o.
o.
c.
a.
0.
0.
0.
0.
MAR
0.
o.
c.
().
a.
~.
0.
o.
o.
').
0.
o.
().
o.
o.
o.
o.
1}.
c.
~.
n.
o.
0.
('.
~.
c.
a.
c.
().
Q.
o.
o.
o.
0.
APR
0.
0.
() .
0.
0.
I) •
0 •
().
~.
0.
o.
0.
D •.
0 •
c.
().
'J •
().
0.
0 •
0.
0.
(I.
c.
c.
0.
0.
0.
0.
no
0 •
a.
0 •
0.
PAGE 5
AVEYR CALYR
2 817.
819.
125 7.
572.
14!ll.
1 05 3.
666.
9~8.
1638.
465.
648.
241.
83B.
li87.
577.
557.
691.
52 7.
1453.
735.
220.
155.
1791.
904.
0.
4 1 •
79 7.
'182.
2500.
li4 5.
913.
871.
2817.
Q.
1950
1951
1952
1953
1954
1955
1956
1957
1958
1959
1%0
1961
1962
1%3
1964
1%5
1%6
1%7
19(.,8
19h9
197G
1 ':.'7 I
1972
1973
1974
1975
1970:.
1977
1978
1979
19f\C
PROJECT 1'1879001
FISH RELEASE IN CFS
YEAR
1
2
3
" 'i
6
7
P.
9
1C
11
12
13
1'1
15
1S
17
lb
19
20
21
22
23
2'1
25
26
27
2Jl
29
30
31
MEAN
MAX
MIN
MAY
1G94.
1 ()9 4.
1 09'1.
109'1.
1 09'1.
lC9'1.
109'1.
1~94.
1 ;9 4.
1~94.
1094.
10'?4.
1094.
1094.
1 094.
1094.
1 1)94.
1094.
11)'? 4.
1 09 4.
1094.
1094.
1;j94.
1 ()94.
1 G9 4.
1894.
1 Q94.
1C94.
1094.
1 094.
1C94.
1 094.
1 094.
1094.
JUNE
1G94.
1 G94 •
1 0 94.
1 0 94.
1 c 94.
1094.
1 0 94.
1094·
1094.
1 Q94.
1094.
1094.
1 0 94.
1094.
1 094.
1 094.
1 n 94.
1 c 94.
1C94.
1 c. '?4.
1 094.
109'1.
1C94.
1 ~94.
1 Q94.
1G94.
1 0 94.
1C94o
1 Q 94.
1 ~ 94.
1 a 94.
1 (194.
lU94.
1 ~ 94.
JULY
trl94.
1 09 4.
1 09 4.
1 C9 4.
1 0'? 4.
1 ~9 4.
1 (194.
1 09 4.
1 09 4.
1 09 4.
1 094.
1 094.
1 0 94.
1 G94.
1 ~9 4.
1 09 4.
1 09 4.
1 09 4.
1 09 4.
1 Q94.
1 09 4.
1 0 9 4.
1 il9 4.
1 () 'J 4.
1 094.
1 094.
1 09 4.
1094.
1 09 4.
1 09 4.
1 0 9 4.
1 09 4.
1 094.
1 ()9 4.
AUG
1 G 94.
1 [.94.
1 094.
1C94.
1 ~ 94.
1 G 94 •
1 ':'94.
1 ')94.
1 G 94.
1 f: 94.
1 a 94 •
1 ~94.
1 0 94.
1 'J 94.
1 r. 94.
1 2 94.
1(94.
1 () 94.
1 0 94.
1 ~ 94.
1 0 94.
1 (194.
1 ~ 94.
1 Q91J.
1 094.
1 094.
1 G 94.
1 ~ 94.
1 :t94.
1 c 94.
1 0 94.
1 c 94.
1 (' 94.
1 J 94.
CIIAKACHAMNA PROJECT OPERATION STUDY
H/1-ftii&CF ,BECHTEL C I VIL&MINERALS INC •, SF •
/\LASKA POWER AUTHORITY DATF: 32483
ALTERNATIVf. E: MCARTf\UR SHORT TUNNEL, IIITH FISH RELEASES
SEPT
109'1.
1 094.
1 09 4.
1094.
1G94o
1 094.
1 n9 4.
1 094.
10Q4.
1 094.
1 094.
1094.
1 094.
1094.
1094.
1 C94.
1 094.
1094.
1 094.
1 C94.
1394.
10'J4o
1094.
1 094.
1 ~94.
1094.
1 09 4.
1 094.
1 Oq4 •
1 094.
1 094.
1 094.
1094.
1 09 4.
I
,..--'---,
OCT
365.
365.
365.
365.
365.
365.
365.
365.
365.
365.
365.
365.
365.
365.
365.
365.
365.
365.
365.
365.
365.
365.
365.
365.
365.
365.
365.
365.
. 365.
365.
365.
365.
365.
365.
NOV
365.
3 65.
365.
365.
365.
365.
365.
365.
365.
365.
365.
365.
3f.5.
365.
3 65.
365.
365.
365.
3'S5.
365.
365.
365.
365.
365.
365.
365.
365.
365.
365 •
365.
365.
365.
365.
365.
DEC
365.
365.
365.
3&5.
365.
365.
365.
365.
365.
365.
365.
365.
365.
365.
365.
365.
365.
313.
365o
365.
365.
365o
365.
365.
365.
365.
365.
365.
365.
365.
365.
363.
365.
313.
JAN
36~.
3&5.
365.
365.
365.
365.
36 5.
365.
365.
365.
365.
365.
365.
3&5.
364.
365.
365.
36 5.
36 5.
365.
365.
365.
365.
365.
365.
365.
365.
365.
36 5.
365.
365.
365.
365.
364.
FEB
365.
365.
365·
365.
365.
365.
365.
365.
365.
365.
307.
36'1.
365.
357.
3&5.
219.
336.
365.
365·
365·
365.
365.
365.
365.
365.
365.
365.
365.
365.
365·
365.
357.
365.
219.
MAR
365.
365.
365.
3 6 5.
365.
365.
365.
365·
365.
365.
26 7.
365.
365.
315.
332.
33 7.
35 0 0
365.
365.
365.
365.
365.
36'1.
365.
365.
365.
365.
365.
365.
365.
365.
351l.
365.
26 7.
APR
5'11.
6 31.
510.
641.
541.
487.
4 96.
598.
6 75.
526.
393.
346.
4 70.
337.
477.
398.
410.
880.
630.
6 52.
8 99.
1 0 94.
4 79.
586.
554.
4 89.
625.
6 06.
5~8.
7 13.
810.
5112.
1 (J 94.
337.
PAGE 6
AVEYR CALYR
61l3.
691.
681.
692.
68 3.
679.
68 0.
68 8.
695.
6!1 2.
f.5ll.
66 7.
678.
662.
675.
657.
669.
707.
691.
693.
713.
73 0.
678.
68 7.
685.
679.
690.
689.
6A5.
698.
7 06.
6fl5.
730.
65 7.
195~
1951
1952
1953
1954
1.955
1956
1957
1Q58
1959
191'>C
1961
1962
196:3
1964
1%5
1966
1%7
1'?6A
1969
197!)
1971
1972
1973
1974
1975
1':'76
1977
1978
1979
1980
''
~
j
PROJECT 1'+879C01
oNET EVAPORATION IN AC-FT
YEAfl
1
?
3
'+
'i
6
7
8
9
1 0
1 1
12
13
1'+
15
16
17
18
19
2J
21
22
23
2'+
25
26
27
:>8
29
3C
31
MEAtJ
MAX
MIN
MAY
c.
') .
o.
().
0.
(l •
0 •
0.
Q.
0.
0.
0.
0 •
0.
0.
0.
0 •
0.
0.
0 •
0.
0.
0.
c.
0 •
0.
0.
c.
0.
c.
D •
0 •
0 •
0 •
JUNE
().
Q •
0 •
0.
0 •
0.
0 •
0.
0.
0.
0 •
0.
0 •
0.
0.
0.
0.
D •
0.
0.
G • ,
0.
0 •
0.
0.
c.
(l •
0 •
0.
0 •
Q.
D.
0.
0 •
JULY
0.
0.
o.
o.
o.
0.
o.
o.
G.
o.
o.
o.
0.
0.
o.
0.
D • o.
0.
o.
o.
o.
o.
o.
o.
o.
o.
o.
o.
c.
o.
D.
o.
o.
AUG
0.
0 •
0.
0.
0.
0.
0.
0.
0.
0.
0.
o.
o.
0.
o.
0.
0.
0.
0.
0.
~ .
o.
0.
0.
0.
0.
0 •
c.
0.
0.
0.
0 •
0.
0.
,~. .. , 1. j ' '
"'
CHAKACHAMNA PROJECT OPERATION STUDY
H/HoH&CFoAECIITEL CIVIL&MINERALS INCotSF.
ALASKA POWER AUTHORITY DATE 32'183
ALTEKNIITIV[ E: MCARTHUR SHORT TUNNELt WITH FlSit RELEASES
SEPT
0.
o.
o.
0.
0 •
0.
0 •
0.
0.
0.
0.
o.
0 •
0.
0 •
0.
0 •
0.
0.
0.
o.
0.
0.
0.
0.
0.
0.
0.
0.
0.
o.
0.
0.
0.
OCT
0.
o.
0.
0.
o.
0.
0.
0.
0.
0.
0.
0.
o.
0.
0.
o.
0.
0.
0.
o.
o.
0.
0.
o.
0 •
0.
0.
o.
0.
0.
0.
0.
0.
0.
NOV
o.
0.
o.
o.
o.
0.
o.
o.
o.
o.
o.
o.
o.
0.
0.
o.
o.
o.
o.
0.
o.
o.
0 •.
o.
c.
o.
0.
o.
o.
o.
o.
o.
o.
0.
DEC
() .
0.
0.
0.
0.
0.
0.
0.
0.
o.
0.
0.
0.
0.
0. o.
0.
0.
0.
o.
0.
0.
0.
0.
0.
0.
o.
o.
0.
0 •
o.
o.
o.
0.
JAN
0 •
0.
0.
0.
o.
o.
0.
0.
0.
0.
o.
0.
0.
0.
o.
0.
0.
0.
o.
0.
0.
0.
o.
0.
o.
IJ.
0 •
0.
0.
o.
0.
o.
o.
0.
FEB
0.
0.
0 •
().
0.
0.
o.
().
0.
0.
0.
o.
0.
o.
o.
0.
0.
c.
0.
0.
o.
0.
0.
0.
o.
0.
0.
0.
0.
o.
0.
0.
0.
0.
o.
"· 0.
o.
c.
c.
o.
c.
o.
o.
o.
D.
a.
o.
o.
o.
c.
').
o.
a.
o.
o.
o.
o.
o.
o.
o.
1).
o.
c.
~.
o.
o.
APR
0.
0.
0.
3.
0.
') .
0.
0.
0.
0.
o.
0.
0.
0.
0.
o.
0.
0 •
0.
0.
0.
[' .
0.
0.
0.
0.
a •
o.
0.
0.
0.
(1 •
0.
0.
-
PAGE 7
AVEYR CALYR
o. 1950
o. 19'il
o. 1952
c. 19 53
o. 1954
r. 1955
o. 1Q56
o. 1957
:~. 1958
o. 1959
o. 1960
o. 1961
0. 196?.
o. 1963
0. 1964
o. 1965
0. 1966
o. 1967
o. 1966
0. 1969
o. 1970
c. 1971
o. 1972
o. 1973
o. 1974
0. 1975
(). 1976
:1. 1977
a. 197B
0. 19 79
o. 1980
Q.
o.
0.
PROJECT 14879C01
E.o.p. STORAGE IN ACRE-FT
YEAR ~1A Y JUNE JULY AUG
1 4477500. 4477500. 4477500. 11477500.
2 35~172RO. 3A'!C445o 4477500. 4477500.
3 3575%1. 4037?06. 4477500. 4477500.
4 3561561. 3872769. 4468818. 4477500.
5 3671l513. 4292[86. 4477500. 4477500.
6 3576621. 3935657. '14 7750 3. 4477500.
7 35634il6. 3792268. 441~665. 4477501).
8 3534480. 3801875. 4477500. 4477500.
9 3f-46696. 43531109. 4477500. 4477500.
10 35P.1877o ~.996422. 4444553. 4477500.
11 3531794. 3917746. 4379145. 4477500.
12 3520005. 3749135. 4259863. 4477500.
13 3504%5. 3802458. 4412330. 4477500.
14 3449689. 3743212. 4373660. 4477500.
l"i ?.·427032. 3529642. 4164483. 4477500.
16 34£19171. 37931)96. 4272757. 4477500.
17 3399476. 3427392· 3961509. 447750').
18 34603r7. 3762715. 4217620. 4477500.
19 341l6753. 383Cb84. 4477500. 4477500.
20 3589145. 3876930. 4477500. 447750C.
21 3404028. 3777592. 4366893. 4477500.
22 3595992. 3822934. 4281846. 4477500.
23 355324 7. 4131416. 4477500. 4477500.
24 3669439. 3983032. 44 7750 o. 4477500.
25 3523781. 37900Q4. 4155425. 4453961.
26 3633198. 3828135. 4 0 66131. 426211A.
27 . '3722292. 418ln04. 4477500. 4477500 •
28 3754042. 4089818. 4423913. 4477500.
29 31l59593. 4477500. 4477500. 4477500.
30 37831~.7. 407914G. 4477500. 11477500.
31 3858416. 4190670. 44 7750 o. 4477500.
~1EAN 3611904. 3943038. 4381455. 4469793.
MAX 4477500. 447750D • 4'177500. 44775GO.
IHN 3339476. 3427392. 3961509. 4262118.
CHAKACHAMNA PROJECT OPERATION STUDY
H/H,HS.CF,BECHTEL CIVIL&MINERALS INCotSFo
ALASKA POWER AUT IIOR IT Y DATE 3 24 83
ALTERNATIVE E: MCARTHUR SHORT TUNNELt WITH FISH RELEASES
SEPT OCT NOV DEC JAN FEB MAR APR
44775Cl0o 4477500. 4343937. 4178902. '1021409. 3Afl3070. 3745820. 3618830.
44775(10. 4420969. 4272884. 4100551. 3q39069. 3798899. 36581)01. 3530102.
4477500. 44775'30. 4346329. 4185300. 4033252. 3890484. 3751712. 3624782.
4477500. 4477500. 4347705. 4183166· 4024470. 3885551. 3747341). 362!1366.
4477500. 4435854. 4291513. 4120550. 3961305. 3821397· 3681259. 3553606.
4477500. 4477500. 4 341126. 4175085. 4019690. 3882394. 3743466. 3616452.
4477':JfJO. 4434989. 42~8605. 4116489. 3955768. 3810939. 3670121. 354 2351.
4477500. 4439004. 4291944. 4121916. 3965287. 3829002. 369186 o. 3564316.
447751)1). 4477500. 43433911. 4173860. 4017892. 3880744. 3743219. 3616202.
4477500. 4429.~07. 4278737. 4103451. 3937736. 3797327. 3656348· 3528432.
4477500. 4396818. 4253567. 4079480. 3911849. 3760115· 361349q. 341l5129o
4477500. 4401080. 4266546. 4115051. 3977393. 31144210. 3705083. 3577675.
4477500. 4410160. 4278352. 4116247. 3963506. 3827479. 3688216. 3560635.
4477500. 4386133. 4255271. 4087709. 3926248. 3779949. 3633568. 3505411.
44775CO. 4441042. 4314758. 4154012. 3985169. 3838383. 3692693. 3565157.
4477500. 438%98. 4261018. 4096569. 3930333. 3784082. 3637751. 3509638.
4477500. 4442771. 4 296588. 4120495. 3952648. 3806661. 3661)597. 3532726·
4477500. 4432827. 43C5262o 4123035. 3964069. 3822909. 3678212. 3550527.
4477500. 4438201. 4328934. 4159771. 4001459. 3859198. 3720060. 3592806.
44585P.O. 4353391. 4211779. 4043551. 3880715. 3740634. 3602136. 3473645.
445851.!0. 4477500. 4361l638. 4201814. 4041746. 3904523. 3771048. 3644315.
4455056. 4373491. 4235260. 4057948. 3889667. 3747179. 36 09563. 3491978·
4477500. 4477500. 4 361162. 4202599. 4047738. 39J7217o 3770185. 3643444.
4477500. 4460189. 4319090. 4146270. 3985373. 3846862. 3708384. 3581010.
4434923. 4425319. 4287507. 4121009. 3963688. 3826825. 3689411. 3561842.
4477500. 4477500. 4350336. 4171l901. 4018605. 3880068. 3742288. 3615262.
4477500. 4477500. 4344654. 4178842. 4021391. 3880166. 3743191. 3616174.
4477500. 4477500. 4359248. 4220394. 40944il4. 3972776. 3843551. 3717551.
44775no. 4477500. 4351114. 4190204. 4036918. 39H486. 3765440. 3638650.
4477500. 4477500. 4338314. 4177313. 4023122. 3888934. 3755092. 3628197.
44775C·O. 4477500. 4380421. 4231118. 4087815. 3958563. 3831711. 3705592.
4474182. 4442521. 4311!129. 4143925. 3986443. 3847033. 3708091. 3581058.
4477500. 4477500. 4380421. 4231118. 4094404. 3972776. 3843551. 3717551.
4434923. 4353391. 4211779. 4043551. 3880715. 3740634. 3602136. 3473645.
,......--
/'
PAGE 8
AVEYR CALYR
4221420. 195Q
41)50058· 1951
4112885. 1952
4095354. 1953
4105715. 1954
4100041· 1955
4045300. 1956
4056015. 1957
41~0485. 19'iA
4059099. 1959
4023679. 1960
4030920. 1961
4043279. 1962
4007987. 1963
4':'05(,14. 1964
4009876. 1965
3962988. 1966
4022707. 1967
4070855. 1968
4()15459. 1969
4074515. 197G
4CD3201. 19 71
4127251. 1972
4u94346o 1973
4C19474. 1974
4044170. 1975
4133143. 1976
4159016. 1977
4177575. 1978
4131939. 1979
4179525. 19PO
4()74964.
42?1 1120.
3962988.
'-'
\,p
'-
...
'-
.....
-
-
-
~~
J
-l
PROJECT 14879001
E.O.Po LAKE LEVEL IN FEET
YEAR
1
2
3
4
5
6
7
8
9
1 0
11
12
13
1'1
15
16
17
18
19
20
21
22
2~
24
25
26
27
28
29
3P
31
f1E AN
MAX
MIN
MAY
1155.
1096.
1097.
1C96.
11u4.
1 09 7.
1096.
1C':'4.
1102.
1097.
1ti9q,
1 093.
1092.
1 QA 8.
1086.
1 091.
1085.
1 089.
1091.
1 098.
1 08 5.
1 ac: a.
1 095.
1103.
1 093.
1101.
1107.
1109.
111 7.
1111.
1116.
1 099.
1155.
1085.
JUNE
1 155.
1119.
1128.
1117.
11'14.
1122·
1112.
1113.
11'18.
1126.
1121.
1109.
1113.
1108.
1 Q 9'1.
1112.
1086.
1110.
1115.
1118.
1111.
111 q.
113".
1125.
1112.
111'1.
1138.
1132.
1155.
11 31.
1138.
1122.
1155.
H86.
-
JULY
115 5.
115 5.
1155.
1155.
115 5.
1155.
1151.
1155.
1155.
1153.
114 9.
.114 3.
1151.
11 q 9.
1137.
11'1 3.
112 3.
114 n.
115 5.
115 5.
114 9.
1 14 4.
1155.
115 5.
113 6.
113 a.
1155.
115 2.
115 5.
1155.
1155.
114 9.
115 5.
112 3.
llUG
1155.
1155.
1155.
1155.
1155.
1155.
1155.
1155.
1155.
1155.
115!:i.
1155.
1155.
1155.
1155.
1155.
1155.
1155.
1155.
1155.
1155.
1155.
1155.
1155.
115'1.
1143.
1155.
1155.
1155.
11 55.
1155.
1155.
1155.
11 q 3.
CIIAKACHAMNA PROJECT OPERATION STUDY
11/lloti&CF oi3ECIITEL C I VI L&MI NERALS INC, oSF o
ALASKA POIIER AUTHORITY
-
DATE 32'183
ALTERNATIVE E: MCARTHUR SIIORT TUNNEL, WITH FISH RELEASES
SEPT
1155.
115 5.
1155.
11 !:·5.
1155.
1155.
1155.
1155.
1155.
1155.
1155.
1155.
1155.
1155.
1155.
1155.
115 5.
1l!:i5.
1155.
115'1.
115'1.
1154.
1155.
1155.
1153.
1155.
1155.
1155.
1155.
1155.
1155.
1155.
1155.
1153.
OCT
1155.
1152.
1155.
1155.
1153.
1155.
1153.
1153.
1155.
1152.
1150.
1151.
1151.
115 0.
1153.
1150.
1153.
1152.
1153.
1148.
1155.
11'19.
1155.
115'1.
1152.
1155.
1155.
1155.
1155.
1155.
1155.
1153.
1155.
11'18.
NOV
11'17.
1143.
1148.
1148.
1144.
11'17.
11'14.
1144.
11'17.
114'1.
1142.
1143.
114'1.
1142.
11'16.
11'13.
11'15.
11'15.
11 q 7.
11'10.
1149.
1141.
1148.
1146.
114'1.
1148.
11'17.
11'18.
1148.
1147.
11'19.
1145.
1149.
1140.
DEC
1137.
1132.
1138.
1138.
11 3'1.
1137.
1133.
113'1.
1137.
1133.
1131.
1133.
1133.
1132.
1136.
1132.
113'1.
113'1.
1136.
1129.
1139.
1130.
1139.
1135.
113'1.
1137.
1137.
11 q 0.
1138.
113 7.
1141.
1135·
11'11.
1129.
JAN
1127.
112 2.
1128.
1127.
1123.
1127.
112 3.
112'1.
1127.
1122.
112 0.
112'1.
1123.
1121.
1125.
1121.
1123.
1124.
1126.
1118.
1129.
1119.
1129.
1125.
1123.
1127.
1127.
1132.
112A.
1127.
1132.
1125.
1132.
1118.
FEB
1118.
1112.
1119.
1118.
111 q.
1118.
1113.
111 q.
1118.
1112.
111 0.
1115.
111'1.
1111.
1115.
1111 •
1113.
111'1.
1116.
1108.
112 0.
1109.
112 0.
1116.
111 q.
1118.
1118.
112'1.
1119.
1119.
1123.
1116.
1124.
1108.
MAR
11G<l.
11('3.
1109·
1109.
1104.
1109.
11 C3.
1105.
11 o a.
11 Q ~.
11 0 0.
1106.
1B5.
1101.
1105.
1101.
110 3.
1104.
110 7.
1 09 9.
111 0.
1 09 9.
111 o.
11 0 6.
1105.
1108.
1108.
1115.
1110.
110'1.
1115.
110 6.
1115.
1099.
APR
11:30.
1 0 94.
1101).
1100.
1 0 95.
11 G 0 •
1 0 95.
1096.
1100.
1 0 9'1.
1n91.
1C97o
1096.
1092.
1096.
1C92.
1094.
1095.
1 0 98.
1090.
1102.
1091.
1102.
1 c 97.
1 () 96.
11(10.
11 0".
11 rn.
11 Ql.
11 ('1 •
11 06.
1097.
1107.
1090.
-J
PAGE 9
AVEYR CALYR
113'1.
1128.
113 2.
1131.
1132.
1131.
1128.
1128.
1134.
1129.
1126.
112 7.
1128.
112 5.
1125·
1126.
112 2.
1126.
112 9.
1126.
1130.
1125.
1133.
1131.
1126.
1128.
113'1.
1135.
1136.
113 4.
1137.
113 (1,
113 9.
112 2.
1950
1'151
1952
1953
1954
1955
1'156
1957
1958
1959
196G
1'lfi1
1962
1963
196'1
1965
1966
19£:7
1968
1969
1970
1"'71
1972
1 '17~
197'1
1975
1976
1977
1978
1979
1980
PROJECT 14879001
~/A HR 8Alf.NCE
YEAR
1
2
3
4
5
6
7
II
9
1 J
11
12
n
14
15
16
11
18
19
20
21
22
23
24
25
26
27
28
29
3il
31
~1EAN
I~ AX
MIN
0.
o.
0.
0.
0.
0.
0 •
c.
'J •
c.
c •
0.
u •
0.
0.
:J.
0.
(l.
0.
().
0 •
J •
0.
0.
0.
0.
0 •
0.
0.
o.
G •
0.
0.
0.
JUNE
c •
0.
;} .
0.
0 •
0.
v •
0 •
0.
Jo
0.
a •
n.
0.
c •
0.
(.
0 •
o.
a •
0.
2 •
0.
0 •
!; •
c •
0.
0.
" . .
c.
0.
0.
0 •
JULY
o.
a.
Q.
o.
0.
a.
n.
c.
0.
o.
Q.
~.
~ •J.
a.
1).
o.
~.
o.
0.
o.
o.
J.
o.
a.
c.
o.
0.
o.
o.
o.
o.
Q.
1).
o.
AUG
Q.
0.
0.
G •
0 •
0.
0.
0.
0.
0.
0.
0 •
Q.
0.
0.
(J •
0.
0.
o.
0.
(l •
c.
0 •
0.
0.
0.
0.
:J •
0.
o.
0.
0.
0.
0.
CIIAKACHAI1NA PROJECT OPERATION STUDY
1-f/IJ,II&CF ,BECIITEL C IVIL&IH NERALS INC. oSF •
ALASKA POWER AUTIIURITY DATE 324f\3
ALTERNATIVE E: MCARTHUR SHORT TUNNEL. WITH FISH RELEASES
SEPT
0.
0.
Q.
o.
0.
0.
0 •
0.
0.
0.
o.
0.
0.
0.
Q •
0.
0.
0.
0 •
0.
o.
0.
0.
0 •
() .
0.
o.
0.
0.
c.
o.
a.
o.
0.
OCT
I ,__.....,
0.
0.
0.
0.
(!.
0.
o.
0.
0.
0.
() .
0.
0.
I) •
0.
o.
o.
o.
0.
0 •
0.
0.
0.
o.
0.
0.
0.
0.
c.
0.
0.
0.
0.
0.
NOV
0.
0.
0.
o.
o.
'lo
r.
0.
0.
0.
o.
o.
().
o.
o.
0.
0.
o.
o.
o.
o.
0.
o.
o.
o.
o.
o.
0.
o.
o.
o.
o.
0.
o.
DEC
0.
o.
0.
0.
0.
0.
c.
0.
0.
0.
0.
:J.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
o.
0.
0.
0.
0.
o.
0.
0 •
0.
0 •
C' •
0.
JAN
0 •
0.
o.
o.
o.
0.
().
0.
0.
0.
0.
0.
0.
0.
0.
o.
o.
o.
0.
0.
o.
o.
a •
0.
0 •
0.
0.
0.
0.
(! •
0.
0.
0.
0.
FER
(l.
0.
0.
0 e
0.
a • o.
0.
0.
o.
0.
0.
0.
0.
0.
0.
o.
0.
0.
0.
o.
0.
0.
c.
0.
o.
I) •
o.
0 •
G • o.
0.
D •
c.
~1AR
a.
Oo
a.
9.
Ct.
(1.
n.
o.
flo
().
o.
o.
().
:J.
o.
o.
0.
o.
o.
o.
o.
o.
o.
o.
0.
o.
0.
!!.
0.
o.
0.
APR
0.
0.
0.
0.
c.
(l •
() .
D •
0.
0.
' c •
['.
0 •
0 •
0.
0.
0 •
(l.
0.
0.
c •
r.
0.
().
G •
0.
o.
0.
0.
D •
0.
0.
0.
0.
PAGE 1 0
AVEYR CALYR
o. 1950
o. 1951
o. 1952
c. 1953
o. 1':'54
o. 1955
o. 1956
c. 1957
o. 1956
0. 19 5<;1
o. 19£',{1
o. 1961
0. 1962
IJ. 1963
o. 196'1
c. 1965
o. 1966
!1. 1967
0. 19611
o. 1969
o. 1970
c. 1971
o. 1972
o. 1973
o. 1974
['. 19 75
o. 1976
o. 1977
o. 1978
o. 1979
0. 1980
0.
().
0 •
r:--
PROJECT 14879001
POI.IfR IN !'.IJ
YEAR
1
2
3
4
5
6
7
ll
9
10
11
12
13
14
15
If,
17
1!'
19
2Q
21
22
23
24
25
26
27
28
29
30
31
MEAN
~lAY
124.
124.
124.
12 4.
124.
124.
124.
124.
12 4 •
124.
124.
124.
124.
124.
124.
124.
124.
124.
124.
124.
124.
124.
124.
124.
12 4 •
12 4.
124.
124.
124.
124.
124.
124.
12 4 •
124.
JUNE
120.
120.
120.
120.
12 a.
12 0.
12C.
12!).
12!).
120.
12 0.
120.
120.
12G.
12 G.
120.
120.
12 0.
1?.0.
12 c.
120.
12 0.
120.
12J.
12 u.
12 G.
1 2 0 •
120.
12~-
120.
12 0.
120.
12 0 •
12G.
JULY
118.
1 ll'l.
llll.
118.
118.
118.
118.
118.
11!3.
118.
118.
11 e.
118.
118.
llll.
118.
11/l.
118.
118.
118.
118.
11/l.
118.
118.
118.
118.
111'..
118.
118.
118.
118.
11P..
1 18.
liP..
AUG
124.
124.
124.
124.
124.
124.
124.
124.
124.
124.
124.
124.
124.
124.
124.
124.
1 24 •
124.
124.
124.
124.
124.
124.
124.
124.
124.
124.
124 •
124.
1 24 •
124.
124.
1 24.
124.
CHAKACHAMNA PROJECT OPERATION STUDY
HllltltF.CF, OECIITEL C I VIL&MINERALS INC. oSF.
ALASKA POIJER AUTHORITY
,------.,
DATE 32483
ALTERNATIVE E: MCARTHUR SHORT TUNNELo IIITH FIS'I RELEASES
SEPT
136.
1~6.
1~6.
136.
136.
13 6.
136.
136.
136.
136.
136.
136.
136.
136.
136.
1:'16.
1:"6.
136.
136.
136.
136.
136.
136.
13 6.
13 6.
1~6.
136.
136.
136.
136.
136.
1~6.
136.
OCT
155.
155.
155.
155.
155.
155.
155.
155.
155.
155.
155.
155.
155.
155.
155.
155.
155.
155.
155.
155.
155.
155.
155.
155.
155.
155.
l!:i5o
155.
155.
155.
155.
155.
155.
155.
NOV
178.
178.
17A.
178.
178.
178.
178.
178.
178.
178.
178.
178.
1 "/8.
178.
178.
178.
178.
178.
178.
178.
178.
178.
178.
178.
178.
178.
17B.
178.
178.
178.
178.
17!!.
178.
178.
DEC
194.
194.
194.
194.
194.
194.
194.
194.
194.
194.
194.
194.
194.
194.
194.
194.
194.
}94.
194.
194.
194.
194.
194.
194,
194.
19'1.
194.
194.
194.
194.
194.
194.
19'1.
194.
JAN
178.
178.
178.
178.
17 8.
178.
178.
178.
178.
178.
178.
178.
17A.
178.
178.
17 8.
178.
17P..
178.
178.
178.
178.
178.
178.
178.
178.
178.
178.
178.
178.
178.
17Ao
17A.
178.
FEB
16°.
169.
169·
169.
169.
169.
169.
169.
169.
169.
169.
169.
169.
169.
169.
169.
169.
169.
169.
}1;9.
169.
169.
169.
169.
169.
169.
169.
169.
169.
169.
169.
169.
169.
169.
MAR
l!:il.
151.
151.
151.
15!.
l!'il.
151.
151.
15 1 •
151.
151.
151.
151.
151.
151.
151.
151.
151.
151.
151.
l!'ilo
151.
151.
151.
151·
151.
151.
151.
151.
151.
15 1.
151.
151.
151.
APR
13o•
136.
136.
136.
136.
136.
1 ~6.
1~6.
136.
136.
136.
136.
1~6.
136.
136.
136.
136.
13&.
136.
136.
136.
1~6.
136.
136.
136.
1~6.
136.
136.
136.
136.
136.
136.
1~6.
136.
PAGE 11
AVEYR CALYR
14 9.
14 9.
14 9.
14 9.
14 9.
14 9.
149.
149.
}4 9.
}4 9.
149.
149.
14 9.
14 9.
14 9.
14 9.
14 9.
14 9.
149.
149.
149.
149.
14 9.
149.
14 9.
14 9.
14 9.
149.
}4 9.
14 9 ~
149.
14 9.
14 9.
14 9.
195(l
1951
1952
1953
1954
1 <;>55
1956
1957
195fl
1959
196(1
1961
1962
1963
1964
1965
1966
1967
1968
1969
197C
1':?71
1972
1973
1974
1975
1976
1977
1978
1979
19AQ
/ '
CliAKACHAMNA PRO.JECT OPERATION STUDY ' H/Hoii&CF,BECHTEL C!VIL&MINERALS INCotSF.
PROJECT 141'79G01 ALASKA POIJER AUTIIORITY DATE 32483 PAGE 12 t.
AL TERNA Tl VE E: MCARHiUR SHORT TUNNELt IJ!Tii FISII RELEASES
ENERGY IN MtJH (
YEAR NAY JUNE JULY AUG SEPT DC T NOV DEC JAN FEB MAR APR TOT Y R CALYR \'
1 92:?30. e."' 'J tj f. • Fl7907. 92;'30. 97623. 115288. 1:?8304. 144110. 132581. 113242. 112405. 9762:'J. 1300008. 195()
2 922.30. 86466. 87907. 9223!1. 97623. 1152fl8. 128304. 144110. 132581. 113242. 112405. 97623. 1300008. 1951 f 3 <12230. 86466. 87907. 92230. 97623. 11!i:?88. 121l304o 144110. 132591. 117287· 112405. <17623. 1304C52. 1°52
4 92230. 86466. 87907. 92230. 'J7623. 115288. 12ll304. 144110. 132581. 113242.· 112405. 976?.3. 1300008. 1953
5 92230. e6466. li7907. 92230. 97623. 1152fl8, 128304. 144110. 132581. 113242. 112405. 97623. 130('008. 1954 r 6 92230. 86466. 87907. 92230. 97623. 115288. 12B3G4, 144110. 132581. 113242. 112405. 97623. 1300008. 1955
7 92230. 8641',6. 87907. 92230. 97623. 115?.88. 1?.P304o 144110. 132581. 117287· 112405. 97623. 1304052. 1956
B 92230. 86466. 87907. 9223C. 97623. 115288. 128304. 144110. 132581. 113242. 11240!i. 976?.3, 1300008. 1957 r: 9 9223C. 86466. 117907. 92230. 97A23o 115?.88. 1 ?.83C4. 144110. 1325111. 113242. 1124C5. 0762-~. uoooos. )90:,8
10 9?.23:1. 86466. l:l7907. 92230. 97623. 115288. 1211304. 144110. 132581. 113242. 112405. 97623. 13000~8. 1959
1 I 92?.30. 86'166. 87907. 92230. 97623. 115288. 12El304. 144110. 132581, 117287· 112405. 97623. 13t'4052· 1960 ("
12 92230. 136466. fl7907. 92230. 97623. 115288. 128304. 144110. 132581. 113242. 112405. 9 76 ;:>3. uooooa. 1961 ·.J
13 92230. El6466. 87907. 92230. 97623. 115288. 12£1304. 144110. 132581. 113242. 1124:!5. 97623. 1300008. 1%2
14 92;:>30. 86466. f179D7. 92230. 9 7 62 3. 115i88. 128304. 144110. 132581. 113242. 112405. 97623. 1300008. 1963 ro, 15 92230. El6466o P.7907. 9223G. 97623. 1152118. 12£\304. 144110. 132581. 117287. 112405. 97623. 1304 052. 1964
16 92230. 86466. P79H • 92230. 97623. 115288. 128304. 144110. 132581. 113242. 112405. 97623. 1300008. 1965
17 92230. 86466. 87907. 92230. 97623. 115288. 128304. 144110, 13f>581. 113242. 112405. 976;:>3. 1300008. 1966
("'_. 1!! 92230. fl6466. 87907. 92230. 97623. 115288. 128304. 144110. 132581. 113242. 112405. 97623. 1300008. 1967
19 92230. 86466. fl7907. 92230. 97623. 115288. 128304. 144110. 1325131. 117287. 112405. 97623. 1304 052. 1968
20 92230. £16466. 87907. 92230. 9762:'J. 115288. 128304. 144110. 13251l1. 113242· 112405. 97623. 1300008. 1969 r; 21 92230. 86466. 87907. 92?30. 97623. 115288. 1?.8304. 1'14110. 1325A1. 113242. 112405. 976?3. 1300008. 19 7 0
22 ');:>230. 86466. 879(!7. 92230. 97623. 115288. 128304. 144110. 132581. 113242. 112405. 97623. 1300008. 19 71
23 92230. 86466. 87907. 922:')0. 97623. 115288. 128304. 144110. 1325131. 117287. 112405. q 76 23. 1304052. 1972
24 92230. 86466. 87907. 92230. 97623. 115288. 12El3t'4. 144110. 132581. 113242. 1124Q5. 97623. 130 o oo a. 1973 f)
25 9?.230. 86466. 87907. 9;:>?30. 97623. 115288, 128304. 144110. 132581. 113242. 112405. 97623. 13000J8. 19 74
26 92230. 86466. El7907. 92230. 97623. 115288. 12U3u4. 144110. 1325131. 113242. 11240!i. 97623. 130000fl. 1975
27 92230. 86466. 873u7. 92230. 97623o 115281!. 12P304. 144110. 13?.!iA1, 117287· 112405. 97623. 1304052. 1976 0
28 92?.30. 86466. 87907. 92230. 97623. 115288, 128304. 144110. 132581. 113242. 112405, 97623. 1300008. 1977
2'1. ':1;:>230. 86466. 87907. 92230. 97623. 1152/lA, 128304. 144110. 132581. 1U242, 112405. 9 76 23. Boooaa. 1978
31 92230. 86466. 87907. 92230. 97623. 115288. 12fi304. 144110. 132581. 113242. 11240'io 97623. 1300008. 1979 r;
31 92230. 86466. 87907. 92230. 97623. 115288. 128304. 144110. 132581. 117287. 1124C5. 97623. 1304 052. 1980
MEAN 92230. El6466. 87907. 92230. 97623. 115288. 128304. 14411fJ. 13251ll. 114286. 112405. 976?.3. 1301051· (j
~lAX ';12230. 86466. 87907. 92230. 97623. 115288. 128304. 144110. 132581. 117287. 112405. 97623. 130'1052. c MIN 92230. 86466. 87907. 922jQ. 97623. 115288, 128304. 144110. 13251l1. 113242. 1124[15. 97623. 1300fJQ8.
,._
'"
~~
1"_.~
r· ·~
(> .
,-----, ~ ~
·~·· • -~ '1 I ,....___., ,.---., ~~-···-. .., .. ,.--,_. -.~.---...---.
-----: -r---· ,......---. ,....-I :-,...--
r~
PROJECT 14B79Q01
ENERGY DEFICIT I~ M~H
YEAR
1
2
3
4
5
6
7
8
9
1 J
11
1 2
13
14
15
16
17
16
19
2C
21
22
23
24
25
26
27
28
29
30
31
MEAN
f1AX
~11 N
MAY
c.
~ .
0.
n " .
0.
0.
c •
0.
c.
0.
0.
0.
0 •
o.
c.
o.
0.
().
0.
0 •
~.
0.
0 •
o.
o.
0.
c.
0.
0 •
0.
0.
() .
o.
0 •
JUNE
0.
0 •
n " .
0 •
0.
0.
~ .
0.
(I •
(! 0
0 •
(l •
0.
o.
0.
0 •
0.
~ .
0.
0.
0.
() .
a •
0.
0.
() .
0.
o.
:I.
~.
a •
~.
o.
0.
JULY
o.
0.
~.
o.
c.
o.
c.
o.
r:.
o.
CJ.
('.
o.
o.
o.
o.
a.
o.
0.
c.
o.
~.
o.
o.
o.
9.
a.
o.
o.
0.
0.
J.
c.
AUG
0.
0.
0 •
c.
0.
o.
0.
c •
c.
0.
0.
0.
0.
o.
o.
o.
0.
() .
0.
c.
0.
!) •
(!.
0.
0.
0 •
0.
0.
0.
0.
!!.
0.
0.
0.
C:HAKACHAMNA PROJECT OPERATION STUDY
ltll-ltii&CFoBECitTEL CIVIL&MINERALS INC.,SF.
ALASKA POUER AUTHORITY
-
DATE 324 0.5
ALTERN A T I V E E : M C A R 1 H U R S H 0 R T TUNNEL • W 1 T II F I S fl R E LEA S E S
SEPT
0.
0.
0.
0.
0 •
0.
0.
0.
c.
0.
0.
:I.
I) •
::~.
0.
0.
0.
0.
o.
c.
0.
o.
0 •
0.
o.
0.
0.
0.
o.
0.
0 •
0 •
I) •
0 •
OCT
0.
0 •
0.
o.
0.
a.
0.
0.
().
0.
0.
0.
0 •
0.
0.
0.
0.
0.
o.
0.
0.
0.
0.
0.
o.
0.
o.
0 •
0.
0.
o.
() .
0.
0.
NOV
o.
o.
0.
0.
o.
o.
o.
0.
o.
o.
o.
o.
o.
o.
o.
o.
o.
0.
o.
o.
o.
o.
o.
0.
o.
o.
o.
o.
0.
o.
o.
o.
0.
o.
DEC
o.
o.
0.
0.
0.
o.
0.
0.
0.
o.
o.
0.
o.
0.
o.
o.
o.
0.
0.
0.
o.
(1.
0.
0.
o.
0.
0.
0.
o.
o.
o.
o.
0.
0.
JAN
0.
0.
0.
0.
0.
o.
0.
0.
o.
0.
0.
0 •
o.
o.
0.
0.
0.
0.
o.
0 •
o.
0 •
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
FEB
0.
0.
0.
::~.
0.
o.
c.
0.
0.
0.
c.
c •
c •
0.
o.
o.
0.
c.
0.
0.
0.
0.
0.
0.
0.
o.
0.
0.
0.
c.
0.
0.
c.
0.
MAR
o.
o.
'J.
o.
o.
a.
o.
['.
I).
o.
a.
o.
o.
o.
o.
o.
o.
c.
o.
o.
a.
o.
o.
o.
a.
o.
1).
a.
IJ.
IJ.
'J.
').,
o.
0.
APR
0.
0.
0 •
D • c.
0.
0.
" . .
() .
0.
0.
c •
c.
t'.
0.
Go
0 •
c.
0.
0.
') .
0 •
!) •
o.
0.
0.
0.
0.
0.
a •
0.
0.
0.
0.
--
PAGE 13
TOTYR CALYR
o. 1950
o. 1951
o. 1952
o. 1953
o. 1954
o. 1955
o. 1956
o. 1957
o. 1958
o. 195~
0. 1%0
o. 1961
0. 1962
0. 1963
o. 1%4
0. 1965
o. 1%6
o. 1967
o. 1968
0. 1%9
o. 1970
o. 1971
o. 1972
o. 1973
o. 1974
o. 1975
(1. 1976
!). 1977
(). 1 S'78
o. 1979
o. 198iJ
0.
o.
o.
..
"'
PROJECT 141:1791JD1
AVERAGE GU:ERAT 10~! IN MIJ ItJ t10NTIIS OF SPILLS
YEAR
1
2
'I
5
6
7
8
9
1 0
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
2 T
28
29
3Q
31
MEMJ
MAX
".IN
MAY
2.31 •
0.
0.
o.
~.
0.
0.
0.
a •
o.
0 •
e.
c.
c.
a •
0.
0.
0.
() .
0 •
a.
0.
() .
0.
0.
G.
0 •
0 •
c •
c •
0 •
7.
231.
0.
JUNE
33D.
0.
0.
0.
c.
0.
0.
0.
o.
0.
0.
0.
0.
a •
0.
0.
0 •
(l •
(I •
0 •
G •
J.
0.
J.
c •
0.
c •
0 •
330.
o.
0 •
21 0
330.
:J •
JULY
33 G.
17'.?.
32 ~ .•
o.
3 3 0.
14 7.
('.
11 a.
33 ~.
a.
o.
o.
~.
0.
a.
?.2 4.
152.
o.
c.
33 0.
294.
o.
o.
330.
o.
33 ~.
1 7 4.
216.
124.
33 ().
~.
AUG
330.
330.
:~ 30.
330.
330.
330.
33ilo
3 30.
330.
330.
330.
317.
3 3C.
330.
330.
330.
165.
314.
330.
330.
297.
2 50.
330.
330.
0.
0.
33:J.
3 05.
330.
330.
330.
2 98.
33().
0.
CllAKACHAMNA PROJECT OPERATION STUDY
ll/JI,II&CFtflECHTEL CIVILUHNERALS !NC •• SF.
ALASKA POWER AUTHORITY DATE 32483
IILTERNATJV[ E: MCARTHUR SIIORT TUNNEL, WITH FISH RELEASES
SEPT
330.
231.
330.
166.
230.
330.
267.
326.
33!l.
159.
173.
u n.
330.
299.
320.
212.
330.
330.
330.
o.
0.
0.
268.
264.
o.
144.
271).
259.
330.
230.
234.
--
231.
330.
0.
~ ' I ,
OCT
156.
o.
191.
157.
0.
163.
0.
0 •
157.
0.
0.
0.
0 •
0.
0.
0.
0.
0.
o.
o.
160.
o.
189.
0.
0.
181 •
186.
2'38.
2 24.
194.
275.
80.
275.
o.
NOV
o.
o.
o.
o.
o.
o.
o.
o.
o.
o.
o.
o.
o.
o.
o.
Q.
Q.
o.
0.
o.
o.
o.
o.
0.
0.
o.
o.
o.
o.
o.
o.
o.
o.
o.
DEC
0.
0.
0.
o.
0.
0.
0.
0.
o.
o.
0.
o.
0.
0.
o.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0 •
0.
o.
o.
0.
() .
o.
o.
o.
o.
JAN
0.
o.
o.
o.
0.
0.
o.
o.
o.
o.
0.
0.
0.
0.
0.
0.
0.
o.
0.
o.
o.
0.
o.
o.
0.
0.
o.
0.
0.
0.
0.
o.
0.
0.
FEB
o.
0 •
0.
0.
0.
0 •
0.
0 •
0 0
0.
0.
0 •
() .
0.
IJ •
o.
o.
0 •
0 •.
c.
0.
0 0
0.
0.
0.
Oo
0.
0 •
0 u •
0.
0.
0.
0.
0.
MAR
' :JO
~.
().
o.
0.
(t.
~.
o.
0.
0.
o. , .
o.
o.
0.
J.
o.
o.
Q.
0.
0.
n.
c.
o.
o.
(1.
o.
9.
J.
o.
a.
J.
APR
0.
0.
o.
0.
0.
0.
D •
!) a
o.
o.
(1.
'J •
a •
0.
0.
0 •
c. .o.
0.
0.
a • o.
o.
a.
:J.
D.
0.
a.
c.
0.
a.
0.
0.
PAGE 14
AVEYR CALYR
142.
61.
91lo
54.,
7 4.
81.
50.
69.
96.
41.
,, 2.
38o
55.
'52.
51f.
4 5.
41.
5'to
74.
4 0.
3e.
21.
'13.
7'l.
0.
27.
93.
67.
129.
77.
as.
63o
14 2.
0.
1950
1951
1952
1953
195'1
1955
1956
1957
1958
1959
196r
1961
1962
1963
1964
1965
1966
1967
1968
1969
1970
1971
1972
1973
1974
1975
1976
1977
1978
1979
198(
PROJECT 1487~001
SURPLUS fNERGY IN Hllli
YEAR
1
2
4
5
6
7
8
9
10
11
12
13
14
15
1€:
17
18
19
20
21
22
23
24
25
26
27
28
29
3"
31
MEAN
MAX
MIN
~1A Y
79356.
0 •
0.
0.
0.
0.
(I.
0 0
c.
0.
0.
0.
0.
0.
0.
0.
0 •
0.
0.
0.
0.
'l.
0.
0.
0.
IJ •
0 •
0.
a.
3.
0.
JUNE
151134.
0.
0.
0.
IJ •
0.
c •
0.
c.
0.
3.
a.
0 •
0.
0.
0.
0.
0.
0.
0.
0 •
0.
c •
c •
0.
c.
0 •
c •
151134.
0.
0 0
JULY
] 57613·
40191.
155008.
c.
157613.
21737.
o.
38512.
157613.
0.
Jo
a.
o.
0.
0.
c.
o.
o.
78505.
25 2 9 5.
o.
c.
157613.
130615.
o.
o.
157613.
o.
1 ~7613.
41236.
72645.
2560. 9751. 49981.
79356. 151134. 157613.
o. o. u.
CHAKACHAMNA PROJECT OPERATION STUDY
H/HtH&CFtBECilTEL CIVIL&MINERALS lNCotSF.
ALASKA PO\IER AUTHORITY
-
DATE 32483
ALTERNATIVE E! MCART1-'UR SHORT TUNNEL• \liTH FISil RELEASES
AUG
153290.
153290.
153290.
153290.
153291).
153290.
153290.
153290.
153290.
153290.
153290.
143566.
153290.
153290.
153290.
153290.
30253.
141059.
153290.
153290.
128560.
93760.
153290.
153290.
0.
3.
153?90.
135D36.
153290.
153290o
153290.
SEPT
139977.
6A462o
139977.
21985.
67686.
139977.
94971.
137231.
139977.
16654.
2€i832.
1 776o
139977.
117943.
132724.
55134.
139977.
L'i9977.
139977·
0.
0.
o.
95310.
92257.
0.
5914.
96 861.
891C7o
139977.
6fl074.
70933.
135416. 81279.
153290. 139977.
0 • i).
OCT
723.
0.
27030o
1871.
0 0
5615.
Oo
0.
1621.
.. o.
!) •
o.
o.
0.
0.
0.
0.
0.
o.
0 •
37 3 2.
0 0
25283.
IJ •
0.
19192.
23036.
621)23.
51639.
29126.
89677.
10986.
89677.
0.
NOV
o.
o.
o.
o.
o.
o.
0.
o.
o.
o.
o.
o.
o.
0.
c.
0.
o.
o. o.
o.
o.
o.
o.
0.
o.
0.
o.
o.
o.
o.
0.
o.
0.
o.
DEC
0.
0.
0.
0.
0.
0.
0.
() .
0.
() .
0.
c 0
o.
0.
0.
0.
0.
0.
0.
0.
IJ •
0.
0.
0.
0.
0.
0.
o.
!' •
0.
0.
0.
0.
o.
JAN
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
(I.
0.
0.
0.
0.
0.
0.
0.
0.
o.
o.
0.
o.
0 •
0.
0.
0.
0.
0.
0.
o.
o.
0.
0.
FEB
0.
c.
0 •
0.
o.
o.
0.
c.
0.
c •
0.
0.
0.
c.
IJ •
IJ •
0.
o.
0.
0.
0 0
0.
0.
c.
0.
o.
0.
0.
0.
0.
0.
0.
0.
() .
MAR
o.
':'.
o.
o.
o.
0.
o.
~.
0.
11.
o.
o.
0.
o.
D • o.
9.
o.
o.
o.
0.
c.
o.
c.
o.
o.
o.
o.
o.
o.
Oo
0 0
o.
PAGE 15
APR TOTYR CALYR
O. 682G93.
o. 261942.
o. 475305.
o. 177146.
o. 378589.
o. 320619.
o. 248261.
o. 3290~3.
Oo 452502.
o. 1E>99q4.
c. 180121.
o. 145342.
o. 2932;7.
o. 271233·
o. 286014.
o. 208424.
o. 170231.
o. 201036.
o. 371773.
o. 178585.
o. 132293.
o. 93760.
0. 431496.
o. 376162.
~. 0.
a. 25107.
o. 430801.
o. 2fl6166.
o. 653654.
o. 291726.
o. 386546.
o. 289973.
3. 682093.
0. 0.
19:.()
19 51
1952
1953
195q
1955
1956
1957
1958
1959
1961)
1961
1962
1963
1964
1965
1%6
1967
1968
1969
1970
1971
1972
1973
1974
1975
1976
1977
1978
1979
1980
PROJECT 14879001
REMAINING SPILLS IN CFS
YEAR
1
2
3
4
5
6
7
8
9
1D
11
12
13
14
15
16
1 7
18
19
2Q
21
22
23
24
25
26
27
21l
29
30
31
MEAN
~~A X
MIN
rH Y
0 •
(l •
0.
0.
o.
0.
Q •
G •
0 •
a •
o.
0 •
0 •
\1 •
() .
0.
a.
0 •
0.
n -. a.
0.
0 •
(l •
0.
0 •
C' •
0.
c.
('.
0.
~ .
!!.
0.
JUNE
4742.
a •
0.
c.
u;
0.
0.
0.
0 •
c.
J •
0.
0 •
0.
0 •
0 •
a •
0 •
0 •
c.
0 •
c.
c.
3.
c.
J •
a •
0.
3494.
0.
0 •
266.
4742.
~.
JULY
9239.
o.
4 353.
o.
(l.
G •
5151.
o.
c.
o.
o.
a.
['.
o.
o.
o.
a.
o.
a.
0.
2082.
o.
~.
a.
81.
D •
7917.
o.
93 0.
9 239.
a.
AUG
5629.
4562.
?845.
33 G4.
4 822.
6060.
2959.
4 249.
4419.
2169.
4145.
0.
3A53 •
2 736.
1126.
2482.
0.
0 •
9709.
5271.
o.
o.
1069'1.
3277.
i) •
() .
816.
Q.
5238.
11179.
3171.
3 0 78.
1069'1.
0.
CHAKACHAMNA PROJECT OPERATION STUDY
HIHtlf&CF,BECHTEL CIVIL&MINERALS INC.,SF.
ALASKA POWER AUTHORITY DATE 32483
ALTERNATIVE E: MCARTHUR SHORT TUNNEL, WITH FISH RELEASES
SEPT
308.
o.
2638.
0.
0.
78.
0.
0.
913.
0.
o.
1),
228.
0 •
a.
o.
48~5.
611.
194.
0.
o.
0.
Do
0 •
a.
0.
0 •
o.
62.
Q.
0.
317.
48;)5.
().
I
~
OCT
0.
0.
0.
o.
0.
0.
o.
a •
o.
0.
0.
0.
IJ •
0.
o.
0.
0.
o.
0.
0.
0.
0.
0.
o.
0.
0.
0.
0.
0.
c.
0.
0.
0.
0.
NOV
o.
o.
0.
o.
o.
o.
o.
o.
o.
o.
o.
o.
o.
c.
o.
o.
o.
o.
o.
0.
o.
o.
0.
o.
o.
o.
o.
0.
o.
o.
o.
o.
0.
a.
DEC
0.
0.
0.
0.
0.
c.
0.
0.
0.
:J •
0.
0.
0.
0.
0.
o.
0.
0.
0.
o.
o.
J.
() .
0.
0.
0 •
0.
0.
0.
IJ •
0.
0.
0 •
0.
JAN
0.
0.
0.
0.
0.
o.
0.
0.
0.
0.
o.
0.
0.
o.
0.
o.
~.
o.
0 •
0.
o.
o.
0.
o.
o.
o.
0.
o.
0.
D.
o.
o.
o.
0.
FEB
o.
(:.
0.
0.
0.
0.
0.
0.
0.
0.
0 •
0.
0.
0.
0.
0.
o.
0.
0.
0.
o.
0.
0.
o.
o.
0.
0.
0.
0.
0.
0.
0 •
0 •
0.
M.AR
o. o.
a.
o.
0.
().
o.
o.
0.
o.
o.
~.
o.
o.
o.
o.
o.
o.
a.
(!.
o.
a.
o.
0.
c.
c.
o.
a.
:l.
o.
o.
0.
o.
0.
APR
0.
0 •
I).
0 •
0.
0.
C' •
0.
0.
o.
0 0
().
0 •
0.
c.
0.
0.
o.
c.
0.
~.
0.
0 •
0 •
0.
0.
0 •
a.
0.
0.
0.
0 •
0.
0 •
PAGE 16
AVEYR CALYR
l6GO.
380.
457.
275.
u. 5.
512.
247.
354.
874.
181.
34 5.
0.
340.
228.
94.
2~ 7.
400.
51.
82 5.
439.
().
o.
1 065.
273.
0.
0.
75.
0.
1393.
157.
264.
38 3.
1 66 0.
0.
1950
1951
1952
1953
1954
1955
195~
1957
1956
1959
1960
1961
1962
1963
1964
1965
1966
1967
1968
1969
1970
19 71
1972
1973
1974
1975
1976
1977
1978
1979
1981?
(_,
''
APPENDIX TO SECTION 8.0
ESTIMATE
SUMMARIES
~ "'. ~' ' r--"'1 r-r-. ,..~ ,--, ~·I, j.,l 1:. Ljl ,~. ·._ ' j ~II' I :l) ~..J J -,,) ( '
CHAKACHAMNA HYDROELECTRIC PROJECT
CONCEPTUAL ESTIMATE SUMMARIES-SHEET 1 OF 2
----.
ESTIMATED COSTS IN THOUSANDS OF DOLLARS
ALTERNATIVES A
LAND AND LAND RIGHTS Not included 0
POWER PLANT STRUCTURE AND IMPROVEMENTS
Valve Chamber 5,600
Underground Power House 26,200
Bus Galleries 200
Transformer Gallery 4,600
Valve Chamber and Transformer 400
Gallery -Access Tunnel
P. H. Access Tunnel 13,500
Cable Way 800 --51,300
RESEk'IOIR, DAM AND WATERWAYS
Rerar•oir 100
lntal:_.; Structure 10,400
lma.kf. Gate Shaft 13,200
Fisn Facilities -
Dike & Spillway -
Access Tunnel
-At Intake 21,600
-At Surge Chamber, No.3 6,600
-At Mile 3, 5, No. 1 0
-At Mile 7, 5, No.2 0
Power Tunnel 626,800
Surge Chamber -Upper 12,900
Penstock-Inclined Section 18,000
-Horizontal Section and Elbow 6,700
-Wye Branches to Valve Chamber 13,200
-Between Valve Chamber & Power House 800
Draft Tube Tunnels 1,900
Surge Chamber -Tailrace 2,400
Tailrace Tunnel and Structure 10,300
Tailrace Channel 900
River Training Works 500
Miscellaneous Mechanical and Electrical 7,100 --753,400
A, B -McArthur development, high level tunnel excavated by drilling and blasting
C, D -Chacackatna valley development excavated by drilling and blasting
E -Me Arthur development, low level tunnel excavated by boring machine
B c D
Not included 0 Not included 0 Not included 0
5,500 5,600 5,600
25,200 26,200 26,200
200 200 200
4,300 4,300 4,300
400 400 400
13,500 13,500 13,500
800 800 800 -49,900 -51,000 --51,000
100 100 100
9,300 10,400 10,400
12,400 13,200 13,200
---
---
19,100 21,600 21,600
5,900 8,900 8,900
0 20,80() 20,800
0 14,500 14,500
580,400 12,500 712,500
11,000 12,900 12,900
16,500 15,400 15,400
6,000 6,700 6,700
11,900 12,100 12,100
600 800 800
1,700 1,900 1,900
2,400 2,400 2,400
9,600 10,300 10,300
700 900 900
500 500 500
6,100 5,700 5,700 --694,200 --871,600 --871,600
J
E
Not included
5,500
25,200
200
4,300 I
400
13,500
800 ---49,900
100
9,300
17,600
85,400
9,100
0
5,900
0
0
447,800
18,900
0
6,000
11,900
600
1,700
2,400
9,600
700
500
6,100 --633,600
-~: -, I rrr:;
CHAKACHAMNA HYDROELECTRIC PROJECT
CONCEPTUAL ESTIMATE SUMMARIES-SHEET 2 OF 2
.--.
ALTERNATIVES ESTIMATED COSTS IN THOUSANDS OF DOLLARS
A
TURBINES AND GENERATORS 67,900
ACCIESSORY ELECTRICAL EQUIPMENT 11,200
MISCELLANEOUS POWER PLANT EQUIPMENT 8,600
SWITCHYARD STRUCTURES 3,600
SWI1'CHYARD EQUIPMENT 13,800
COMM. SUPV. CONTROL EQUIPMENT 1,600
TRANSPORTATION FACILITIES
Port 4,600
Airport 2,000
Access and Construction Roads 59,600 --66,200
TRANSMISSION LINE & CABLE CROSSING 63,200
TOTAL SPECIFIC CONSTRUCTION COST AT 1,040,800
JANUARY 1982 PRICE LEVELS
ENGINEERING & CONSTRUCTION MANAGEMENT 124,900
SUBTOTAL 1,165,700
CONTINGENCY @ 20% 233,100
ESCALATION Not Incl.
INTEREST DURING CONST.@ 3% PER ANNUM 111,900
OWNER'S COSTS . Not Incl.
ALLOWANCE FOR FISH PASSAGE FACILITIES -
TOTAL PROJECT COST AT 1,510,700
JANUARY, 1982 PRICE LEVELS
USE 1,500,000
A, B -McArthur development, high level tunnel excavated by drilling and blasting
C, D -Chacackatna valley development excavated by dri!ling and blasting
E -Me Arthur development, low level tunnel excavated by boring machine
4,600
2,000
59,600 --
B c D
57,900 54,500 54,500
9,500 9,000 9,000
7,300 6,900 6,900
3,600 3,600 3,600
12,500 12,100 12,100
1,600 1,600 1,600
4,600 4,600
2,000 2,000
44,100 44,100
66,200 50,700 50,700
63,200 56,500 56,500
965,900 1,117,500 1,117,500
115,900 134,100 134,100
1,081,800 1,251,600 1,251,600
216,400 250,300 250,300
Not Incl. Not Incl. Not Incl.
104,100 101,400 101,400
Not Incl. Not Incl. Not Incl.
50,000 -50,000
1,452,300 1,603,300 1,653,300
1,450,000 1,600,000 1,650,000
E
57,900
9,500
7,300
3,600
12,500
1,600
4,600
2,000
59,600
66,200
63,200
905,300
108,700
1,014,000
203,000
Not Incl.
97,400
Not Incl.
Under
Reservoir
Item
1,314,400
1,314,000
ALTERNATIVE A
ESTIMATED COST
-,-.---.
HAJ/APD
PREPARED BY
MF
CHECKED BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTERNATIVE A
NO. DESCRIPTION
POWER PLANT STRUCTURE
Valve Chamber
&
M-i"". \1 I 11)
IMPRC
Excavation & Supports
Concrete & Reinf Steel
l"'"i1 ',, ' -t '
,----""'
J
ESTIMATE SUMMARY
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT AMOUNT COSTS
VEMENTS
10,500 CY 270 2,835,000
6,520 CY 410 2,673,200
Struc. Steel & Misc.Meta s 52 TON 1,800 93,600
Round-Off (1, BOO)
Underground Powerhouse
DewaterinJ;t LS 4,100,000
Excavation & Supports 64,000 CY 155 9,920,000
Drilling-Percus.& Rotary 15,000 LF 30 450,000
Concrete & Reinf.Steel 14,200 CY 630 8,946,000
Struc. Steel & Mise Metals 330 TON 5,300 1,749,000
Architectural LS 1,000,000
Round-Off 35,000
•.
Bus Galleries Between Power
house fl. Transformer Vaults
--·
Excavation fl. Supports 200 CY 825 165 ,000
Concrete 120 CY 290 34,800
Round Off ioo
H&CF CSE 623 13-801
---· >
14879-001
JOB NO.
NOV. 1981
DATE
SHEET 1 OF 15
TOTALS REMARKS
5,600,000
Entire Underground Complex
2 11
-3"~
26,200,000
200 000
--···
-~ ~ '!i I , ' ,
HAJ/ APD e ESTIMATE SUMMARY 14879-001
PREPARED BY JOB NO.
MF NOV. 1981
CHECKED BY DATE
CONCEPTUAL CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT SHEET 2 OF 15
TYPE OF ESTIMATE
ALASKA POWER AUTHORITY
ALTERNATIVE A PREPARED FOR
NO. DESCRIPTION QUANTITY UNIT UNIT AMOUNT TOTALS REMARKS COSTS
Transformer Gallerv & Tunne s
Excavation & Supports 13,000 CY 280 3,640,000
Concrete & Reinf Steel 900 CY 460 414,000
Struc Steel & Misc.Metals 130 TON 3,800 494,000
Round Off 52,000
4,biJU,IJUU
Valve Chamber & Transformer
Gallery-Access Tunnels
Excavation & Supports 1.500 CY 250 375.000
Concrete 60 CY 290 17 400
Round-Off 7,600
400.000
Powerhouse Access Tunnel
Portal Excav.& Protection 56.000 CY 10 560 000
Portal Cone.& Reinf.Steel 1.000 CY 570 570 000
Tunnel Excav.& Supports 24 000 CY 300 7 200 000
Tunnel Concrete 900 CY 290 261 000
Tunnel Misc. Metals 30 TON 11 000 330.000 -
Subsurface Exoloration
Mobilization LS 1 500 000
Exploratory Adit 1,000 LF 1.800 1.800 .ooo
Core drilling 5,000 LF 140 700.000
Helicooter Service LS 600 000
Round-Off (?1 000)
__ l}_,?QO.OOO
rt6CF CSIE 523 13-80)
-~ . ' . --. .--.
)
ESTIMATE SUMMARY
HAJ/APD 14879-001
PREPARED BY JOB NO.
MF NOV. 1981
CHECKIED BY DATE
CONCEPTUAL CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT SHEET 3 OF 15
TYPE OF ESTIMATE
ALASKA POWER AUTHORITY
ALTERNATIVE A PREPARED FOR
NO. DESCRIPTION QUANTITY UNIT UNIT
COSTS AMOUNT TOTALS REMARKS
f!S~blP Wav
f!nnt'r~f'~ F. RPinF StPPl 1 000 r.v 700 700 000
Mia! Me~als & Cab 1 f' Sun. 26 TON 5 100 132 600
p,.. ... ,.. PAn<>la
Rnun.-1. -Off (32 .600)
800.000
TnTAT PnTJF.R PT.4.NT s I'll IRF. TMP-IJVI':Mtt:NTS 151.300.000
iS.CF CSE 523 13-801
-
HAJ/APD ESTIMATE SUMMARY
14879-001
PREPARED BY JOB NO.
MF NOV. 1981
CHECKED BY DATE
CHAKACHAMNA HYDROELECTRIC PROJECT CONCEPTUAL PROJECT SHEET 4 OF 15
TYPE OF ESTIMATE
ALASKA POWER AUTHORITY
ALTERNATIVE A PREPARED FOR
l NO, DESCRIPTION QUANTITY UNIT UNIT AMOUNT COSTS TOTALS REMARKS
'RF.~F.UUOlR nAM ~ WATF.RWAVS
Doao ..... ,of yo
t.J .. t-.. ..-T.•nr.,.l RPrn..-1'\ino LS 100.000
Tnt-:alr"' St-THr t-11re
~it-o F.vnlnY"<tt"inn
Mnld 1 i .,.,.t--f nn ILS 150 000
rn .. o fiY'-t11ina 5,000 ILF 80 400 000 .
J.l,:>]irnnt-""r SPrv-fr,:> l.S 150 000
TunnA] Rvr"'" F. ~· onnn'l"t'<:l 12,000 ICY 470 5 640 000
T,...,.,, •1 f'nn<" li. 'Ro-fnf' ~t-<><> 100 r.v 350 35 000
T.alr<>-T:an fR-ln::1l RnHnil) 'LS 3 000 000 L 26'
1>1 o><"<> ~· DA.nn•ro To.nn r.nn<' 600 lev 700 420 000
n-fu-f.,o r .. ,...,. 60 I DAYS tl.O .ooo 600.000
Rnnnn:Off 5 000
10 400.000
Intake Gate Shs..ft
Sh::~ft-F.xr<>u 1. ~llnnnrtA 10 000 CY 360 3 600 000
Mso<HI Su..-fsor"' F.vr<>: 50 000 lev 30 1 500 000
ennrl'"ete & R~inf Steel 5. 700 •r.v 890 5 073 000
MiAr Met:tlA.GateA li. Hni ~t-244 I TON 2.500 3.050 000
Rnt~nii-Off (23 000)
13 200 .non
1Cf CSE 523 {3~0)
-_______.,
M""'l"""l ["'7'"1, : •I, I 1', ,
' I, ' ' c '"
HAJIAPD
PREPARED BY
MF
CHECKED BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTERNATIVE A
NO. DESCRIPTION
Access Tunnel at Intake
Portal Excav. & Protectio
Tunnel Excav.& Supports
Tunnel Cone. & Reinf.Stee
Round-Off
Access Tunnel at Sun!e Cham
Portal Excav & Protectio
Tunnel Excav.& Suooorts
Tunnel Cone. & Reinf.Stee
Groutin2 Contact & Pressu
Wateri£ht Bulkhead & Fram
Rounrl-Off
Power Tunnel
Excavation & Suoports
Concrete
Grout"inP C.nntact & Pressu
Round-Off
H&CF CSE 523 13-801
ESTIMATE SUMMARY
CHAKACHAMNA HYDROELECTRIC PROJECT
er
re
~e
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT AMOUNT COSTS
6.000 CY 50 300.000
72,000 CY 295 21 240.000
200 CY 500 100,000
(40.000)
6.000 CY 35 210,000
17 000 CY 295 5,015,000
2,000 CY 420 840,000
2.500 CF 58 145,000
27 TON 13,800 372,600
17.400
53.400 LF 8.800 469,920,000
410.000 CY 334 136,940,000
370.000 ~E 54 19,980,000
(40,000)
.~ --
14879-001
JOB NO.
NOV. 1981
DATE
SHEET 5 OF 15
TOTALS REMARKS
'
21,600,000
6,600,000
626,800,000
--~--····~----··
T .....,
I -
HAJ/APD
PR~PARED BY
MF
CHECKED BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTERNATIVE A
NO. DESCRIPTION
Snrll~ f'h<>-~er -Unn~r
F.xr~nr::.t"inn & Snnnnrt~
Conl:'ret:~ & Rein£ ~t"o:><>l ·
F.art:hwnrkR & F<>nrino
Round Off
PenRtnr"k-Tnrl inerl SPrf"inn
F.xr.<au::.tinn & Snnnnrt"~
Concrete & Reinf. Steel
GroutinP Contact & Pres
Round-Off
Penstock-Horizontal Sectio
F.xcavat:ion & Suonorts
CnncrPtP S Reinf Steel
Groutinfl -Contact
Round-Off
!ICF CSE 623 13-801
r-: L,, _j -
ESTIMATE SUMMARY
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT AMOUNT COSTS
35 500 ['X 200 7,100.000
6 100 r.v 880 5,368,000
15 000 CY. 27 405,000
27.000
27.000 CY 280 7,560,000
12.000 CY 845 10,140,000
lsure 6 200 CF 52 322,400
(22,400)
h & Elbow
14,000 CY 310 4,340,000
6.000 CY 365 2,190,000
3.000 CF so 150,000
20,000
TOTALS
12,900,000
18,000,000
6,700,000
-,
J
14879-001
JOB NO.
NOV. 1981
DATE
SHEET 6 OF 15
REMARKS
Heliport, Storage, Work Area
--·
---' ' ~
I. ,,J
HAJ/APD
ESnMATE SUMMARY 14879-001
PREPARED BY JOB NO.
MF NOV. 1982
CHECKED BY DATE
CONCEPTUAL
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT SHEET 7 OF 15
TYPE OF ESTIIIIIA TE
ALTERNATIVE A ALASKA POWER AUTHORITY
PREPARED FOR
NO. DESCRIPTION QUANTITY UNIT UNIT AMOUNT TOTALS COSTS REMARKS
P~nAt-ne_k-Wv@ Rr;=-nrh<>a t-n V;; il ve Chamber
Excavation & Supports 10_.000 CY 440 4.400 000
Concrete & Reinf. Steel 7,200 CY 608 4.377.600
Steel Liner 850 TON 5.000 4.250 000
Grouting-Contact 3,000 CY 50 150,000
Round-Off 22.400
13,200,000
Penstock ·Between Valve Char her & Powerhow e
Excavation & Supports 1,000 CY 440 440,000
Concrete & Backfill 600 CY 550 330.000
Round-Off 30,000
800,000
Draft Tube Tunnels
Rock Bolts & Grout 19,000 LF 27 513,000
Concrete & Reinf. Steel 3,300 CY 425 1,402,500
Round-Off (15 ,500)
1,900,000
Sur~e Chamber -Tailrace
Excavation & Suooorts 5,000 CY 480 2 400.000
···--.
&CF CSE 523 (3-60)
·---\
HAJ/APD
PREPARED BY
MF
CHECKED BY
CONCEPTUAl.
TYPE OF ESTIMATE
ALTERNATIVE A
NO. DESCRIPTION
Tailrace Tunnel & Structures
Coff~rdam & D~wat~rin12:
Portal Excav & Protecticn
Concrete & Reinf Steel
lJ<>lln.•<tv Brid 12:e
Stooloszs & Hoists
_TunnPl Exrav & SnnnortR
J.llu~:t_ li'~ ........ "ltion
Round-Off
Tai1rarP Ch::~nnPl
Ch<~nn~~>l Exravat:ion
River Traininll Works
River Bed Deepening
Mech & E1ec.
,...,......--,
, , I >
r-,-
~ , I : .
ESTIMATE SUMMARY
r--:
''
CHAKACHAMNA HYDROELECTRIC PBO.JECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT AMOUNT COSTS
LS 2.000,000
2.000 CY 65 130,000
1 200 CY 600 720,000
LS 65,000
81 TON 8.500 688,500
25 000 CY 260 o ,SOD ,000
4.000 CY 50 200 000
(3 .500)
100.000 CY 9
50.000 . CY 10
LS
TOTAL RESERVOIR, DAM AND Wl TERWAYS
S.CF CSE 523 IJ.80I
-
14879-001
JOB NO.
NOV. 1981
DATE
SHEET 8 OF 15
TOTALS REMARKS
10,300,000
900,000
500,000
7 100 000
753,400,000
-
HAJ/APD
"REPARED BY
MF
:HECKED BY
CONCEPTUAL
"YPE OF ESTIMATE
ALTERNATIVE A
NO. DESCRIPTION
Turbines & Generators
Turbines
Generators
Round-Off
Accessorv Electrical Enuint ent
Equipment
Misc. Power Plant Eauinmen
Crane Bridee
Other Power Plant Eauiu.
Switchvard Structures
Earthworks
Concrete & Reinf. Steel
Struc. Steel & Misc.Meta s
Round-Off
CF CSE 523 13-801
ESTIMATE SUMMARY
CHAK!CUAMNA HYDROELECTRIC PROJECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT AMOUNT COSTS
4 EA 9,93o,oop 39 '720 ,000
4 EA 7,050,00) 28,200,000
{20,000
LS
l EA l 100.000
LS 7,500,000
15,000 CY 25 375 000
3,800 CY 640 2.432 000
225 TON 3,500 787,500
5,500
TOTALS -
67,900,000
ll,;wu ,uuu
8,600,000
3,600,000
-,,
J
14879-001
JOB NO.
NOV. 1981
DATE
SHEET 9 OF 15
REMARKS
-·
HAJ/APD
PREPARED BY
CHECKED BY
CONCEPTUAL
-'
TYPE OF ESTIMATE
ALTERNATIVE A
NO. DESCRIPTION
Swi..tchvard Eauinment
TrAne~fnrmPrA lOS MVA
11" it: & T · i "" Breakers
C::..,i rrh<><> & T.i oht:n Arrest
'1~0 KV C.::1bles
Cont:rnlA & Metr'2 Eauio.
Rnttnri Off
Communic::1tion ann Sunv
C.nntrnl F.n dn
I&CF CSE 623 (UOI
rs
!:Tl -
I '
I
I
!, I
ES~ATE SUMMARY
I
I
I
I
I ' CHAKACHAMN~ uknROELECTRIC PROJECT
1 n
I :I PROJECT
ALASKA\ P~WER AUTHORITY
1
REPARED FOR I ~
QUANTITY I ', UNIT U 1NI~ COSTS AMOUNT
I
I
I
I
,,
II
5 EAi [152000 5,760,000
7 EA] 206..000 1,442,000
30 EA 37,00 1,110,000
18 000 LF / 140 2,520,000
LS ( 3,000,000
I' 132 ,OOG)
/
LS
--
14879-001
JOB NO.
NOV. 1981
DATE
SHEET 10 OF 15
TOTALS REMARKS
13 .~uu ,uuu
l,buu;uuu
----
--r-~ -r-! I. "
ESTIMATE SUMMARY
HA~[APD 14879-001
PREPARED BY JOB NO.
MF NOV. 1981
CHECKED BY DATE
CONCEPTUAL CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT SHEET 11 OF :t,5
TYPE OF ESTIMATE
ALASKA' POWER AUTHORITY
ALTERNATIVE A PREPARED FOR
NO. DESCRIPTION QUANTITY UNIT UNIT AMOUNT TOTALS REMARKS COSTS
TRANSPORTATION FACILITIES
Port Facilities
Causeway 19,600 CY 80 1,568,000
Trestle Piles so TON 11,300 565,000 L = 150 LF, g)l2 , t = ~
Trestle Struct. Steel 110 TON 3,500 385,000
Trestle Reinf. Cone. 150 CY 700 105,000
Facilities -Allowance LS 2,000,000
Round-Off (23,000)
4,600,000
Airport
Earthwork 54,500 CY 16 872,000
Culverts 1,000 LF 65 65,000
Subbase & Base 55,000 CY 14 770,000
Building -Allowance LS 300,000
Round-Off (7,000)
2,000,000
!ICF CSE 523 I:HIO)
-
HAJ/APD
PREPARED BY
MF
CHECKED BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTERNATIVE A
NO. DESCRIPTION
Arri!>RR & ConRtruct.ion Rn::u\s
Mil<> 0+00 t-n lR+OO
F.strt"hwnrlt-
f'.nlu.,.rt"a
Rridl1f'>R
SuhhAR<> li. R<~Rf>
n ....... ;~ lla.fl
R"'nair F.-viqt.in11 Rn::arf
C::nn.., l<'<>n""'"'
Round~Off
M.flo IA+-00 t-n 1'i+l)O
li'art-hwnrk<>
Culverts
Snhh,a<u~ E. R~se
Guard Rail
Rf'>nair li'-viqt-fnu Rnarf
Snow Fenr~'>R
Round Off
Mi.lP 1'\-1-00 t-n 1q+OO
F.::arthwork
r.ulu.,.rts
RrirloP
Suhh;se E. R::~ '""'
C:nard R,ai 1
SnnY F~nC.PR
Rnunrl-Off
H6CF CSE 623 (3-801
ESTIMATE SUMMARY
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT AMOUNT COSTS
175 000 CY 6.60 1,155,000
1 500 LF 65 97,500
1 400 SF 150 210,000
85.400 CY 15 1,281,000
1 200 LF 25 30,000
95.000 LF 10 950,000
5 000 LF 35 175,000
1,500
1 465 000 CY 6.60 9,669,000
3.600 LF 80 288,000
165 000 CY 15 2,475,000
13 .ooo LF 25 325,000
16 000 T.F 10 160,000
1.000 LF 35 35,000
482000
445.000 CY 8.30 3,693,500
1 000 LF 80 80,000
9 000 SF 150 1,350,000
38 000 f'.V 15 570,000
10.000 LF 27 270,000
2,000 T.F 35 /0,000
133 ,500)
-
TOTALS
36 n-;i r.MP
3,900,000
48"~ CMP
13,000,000
48"r/J CMP
6,000,000
-J
~
i
14879-001
JOB NO.
NOV. 1981
DATE
SHEET 12 OF 15
REMARKS
--
ESTIMATE SUMMARY
HAJ/APD 14879-001
PREPARED BY JOB NO.
F NOV. 1981
CHECKED BY DATE
CONCEPTUAL CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT SHEET 13 OF 15
TYPE OF ESTIMATE
ALASKA POWER AUTHORITY
ALTERNATIVE A PREPARED FOR
NO. DESCRIPTION QUANTITY UNIT UNIT AMOUNT COSTS TOTALS REMARKS
Walkwav To Gate Shaft
Earthwork 1 200 CY 20 24 000
Guard Rail 1 000 LF 25 25 000
BridRe 200 SF 150 30.000
Riorao 100 CY 35 3.500
Round-Off 17.500
100,000
Access Road to MacArthur Valley
FArthwork 545,000 CY 7 3,815,000
Culverts 2,400 LF 75 180.000 36"~ and 48"~ CMP
BridRe Imorovements 9,000 SF 70 630,000
Subbase & Base 105,000 CY 15 1.575,000
Guard Rail 6,000 LF 25 150,000
Snow Fences 3,000 LF 35 105.000
Round-Off 45,000
6,500,000
Access Road to Tailrace runnel
Earthwork 56,000 CY 8 448,000
Culverts 100 LF 80 8,noo 48"¢ CMP
StthhliA~ & RaA~ 2,500 CY 20 50,000
Guaril R.Ril 600 LF 25 15,000
Round-Off (21,000)
500,000
--
HIIICF CSE 523 13-601
~ .. ----,
J
ESTIMATE SUMMARY
HAJ/APD 14879-001
PREPARED BY JOB NO.
MF Nov. 1981
CHECKED BY DATE
CONCEPTUAL
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT SHEET 14 OF 15
TYPE OF ESTIMATE
ALASKA POWER AUTHORITY
ALTERNATIVE A PREPARED FOR
NO. DESCRIPTION QUANTITY UNIT UNIT AMOUNT TOTALS REMARKS COSTS
Access Road to Downstream 1.', ~er Tunnel
Earthwork 215 000 CY 9.80 2.107.000
Culverts 800 LF RO 64.000 48"gl CMP
Brid2e 3 000 SF 150 450.000
Subbase & Base 10,000 CY 21 210.000
Guardrail 9 000 LF 32 28R,OOO
Snowshed & Slide Fall 1 000 LF ROO 800 000
Round-Off (19.000)
3,900,0()0
TeiDDorarv Construction Roadl3
Earthwork 61~000 CY 6 366.000
Culverts 600 LF 80 48.000 48"gl CMP
Bridge 3 000 SF 150 450 000
Guardrail 2,000 LF 25 50,000
Round-Off (14.006)
900,000
Road Maintenance
SuiiDller Season 45 MO 150,000 6,750,000
Winter Season 30 MO 600,000 1R,OOO,OOO
Round-Off 50.000
24,ROO,OOO
TOTAL ACCESS & CONSTRUCTION RC lADs 59,600,000
IIIICF CSE 523 (3-801
--j --c. I
ESTIMATE SUMMARY
HAJ/APD 14897-001
PREPARED BY JOB NO.
NOV. 1981
CHECKED BY DATE
CONCEPTUAL CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT SHEET 15 OF 15
TYPE OF ESTIMATE
ALASKA POWER AUTHORITY
ALTERNATIVE A PR EPARED FOR
NO. DESCRIPTION QUANTITY UNIT UNIT COSTS AMOUNT TOTALS REMARKS
Transmission Line
Clear & Grub 82 MI 225.()00 18,450,000
Tranczm-faaion Line 82 MI 343 000 28 126.000
Submarine Cable 21 MI 792,000 16,632,000
Round-Off (8,000)
63,200,000
TOTAl~ SPECIFH"! IJN:-i" "I< "()N ( hs'T'
A'!' .TANTTA"RY 1 Qs:l? PRTr.R T.RVRT~ 1,040,800,000
--
----
H&CF CSE 523 (3-801
ALTERNATIVE B
ESTIMATED COST
r-"' --' '
HAJ/APD
PREPARED BY
MF
CHECKED BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTERNATIVE B
NO. DESCRIPTION
POWER PLANT STRUCTURE & IMPRC
Valve Chamber
Excavation & Supports
Concrete & Reinf Steel
~~· ~J' ,, , I 11 ;
ESTIMATE SUMMARY
...-
.. 1
CHAKACUAMNA HYDROELECTRIC PROJECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT AMOUNT COSTS
VEMENTS
10,000 CY 275 2_, 750,000
6,520 CY 410 2_~673,200
Struc. Steel & Misc.Meta s 52 TON 1,800 93,600
Round-Off (16,800)
Underground Powerhouse
Dewatering LS 4,100,000
Excavation & Supports 58 900 CY 168 9,895,200
Drilling-Percus.& Rotary 12 700 LF 27 342,900
Concrete & Reinf.Steel 13 100 CY 630 8,253,000
Struc.Steel & Mise Metals 300 TON 5 300 1,590,000
Architectural LS 1,000,000
Round-Off 18,900
Bus Galleries Between Power
house & Transformer Vaults
...
Excavation & Supports 200 CY 825 165,000
Concrete 120 CY 290 34,800
Round Off 200
IIICF CSE 623 IJ.80I
14879-001
JOB NO.
NOV. 1981
DATE
SHEET 1 OF 15
TOTALS REMARKS
5 soo.ooo
Entire Underground Complex
2"-3"0
25,200,000
200.000
r--·
I '
rrn
HA'J/ APD
PREPARED BY
MF
CHECKED BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTERNATIVE B
NO. DESCRIPTION
TransfoTmer Gallerv & Tunnf"
Excavation & Supports
Concrete & Reinf Steel
Struc Steel & Misc.Metals
Round Off
Valve Chamber & Transformer
Gallery-Access Tunnels
Excavation & Supports
Concrete
Round-Off
Powerhouse Access Tunnel
Portal Excav.& Protection
Portal Cone.& Reinf.Steel
Tunnel Excav.& Supports
Tunnel Concrete
Tunnel Misc. Metals
Subsurface Exploration
Mobilization
Exploratory Adit
Core drilling
Helicopter Service
Round-Off
H&CF CSE 523 13~01
-I
ESTIMATE SUMMARY
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT AMOUNT COSTS
lls
11,960 CY 290 3.468 400
830 CY 460 381,800
120 TON 3,800 456.000
(6 200)
1,500 CY 250 375.000
60 CY 290 17.400
7.600
Sb,UOU CY lU 560.000
1,000 CY 570 570,000
24,000 CY 300 7 200,000
900 CY 290 261,000
30 TON 11,000 330,000
LS 1,500,000
1,000 LF 1,800 1,800,000
),000 LF 140 700,000
LS 600,000
(21.000)
14879-001
JOB NO.
NOV. 1981
DATE
SHEET 2 OF 15
TOTALS REMARKS
4,300,000
400,000
-
13,500,000 ·----
--
HAJ/APD
PREPARED BY
MF
CHECKED BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTERNATIVE B
NO. DESCRIPTION
CahlP Wav
r.nn<'_TE!.t"E!. F. RPinF StPPl
MiA!! Metals & Cable Suo.
Pnrt. ppno>la
Ronnel -Off
TOTAl. POWF.R PLANT ~-I'K ITRF.
I&CF CSE 523 (3-601
-• I ' • , __ 1
ESTIMATE SUMMARY
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT
COSTS AMOUNT
1,000 CY 700 700,000
26 TON 5 '100 132,600
(32,600)
rMPKUVt.;Mt.;N' ,S
-· ....•. \
,,1
14879-001
JOB NO.
NOV. 1981
DATE
SHEET 3 OF 15
TOTALS REMARKS
800,000
49,900.000
r--•. \ ,,
HAJ/APD
PREPARED BY
MF
CHECKED BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTERNATIVE B
NO;
Jl)l'l
DESCRIPTION
'1"""1'""7"1 U I : J
·o DAM t. tJATF.Rt.r.t\.YS
ll<>a<>.-.,rt-1.-
l.J<>t"<>.-T.<>u<>l n. ~inn
Tnt-<>k<> Strurt-_ure
~-It-<> F.vnln.-,.t-inn
M..,.l.-fl-f.,.,t-i..,.n
rn.-<> nrill-fno
UQli,..nnt-o.-Sp.-u-fl'<> --.-
Tunn<>l 1l'Yl"AU li. Sunnn.-tA
T .. nnAl f'nnl' ~ llt>-fnf' C:t-Pf"o
T.<>lr<>-TAn (lH n"'l Rnun.-l)
'01 ~,..~ s..' n. Taonn f'nn,.
niuinn ,., .........
Rnuntf-nf'f
Intak,:a l!<~.t~ ~h<>f't
Sh::~ft-F.XC'::IU F. Snnnnrt-"'
M::IRI'I s,.rf::~rP Rxr::~"
r.onrr~t-P li. RP-Inf StPPl
Mi Rr Met.:=ll"' l!<\ t.eR li. Hf)i ~ ...
Rnun..t-Off
HIIICF CSE 523 13-60)
-. I ,
ESTIMATE SUMMARY
14819-001
JOB NO.
NOV. 1981
DATE
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT SHEET "· 4 OF 15
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT COSTS AMOUNT TOTALS REMARKS
LS 100,000
IT.S 150,000
5.000 LF 80 400,000
lt.~ 150 000
10.000 r.v 510 5.100,000
90 ("'{ 350 31 500
LS 2,500,000 L 26'
550 lr.v 700 385 000
60 I DAY~ 10.000 600,000
(16,500)
9.300,000
10 000 CY 360 3 600 000
50 000 lr.v 3(] 1.500 .ooo
5,200 :r.Y 890 4,628,000
220 ITnN 12,200 2,684,000
(12,000)
12 400 000
-
-
HAJIAPD
PREPARED BY
MF
CHECKED BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTERNATIVE B
NO. DESCRIPTION
Access Tunnel at Intake
Portal Excav. & Protecti01
Tunnel Excav.& Supports
Tunnel Cone. & Reinf.Stee
Round-Off
Access Tunnel at Surge Cham
Portal Excav & Protectio
Tunnel Excav.& Sunoorts
Tunnel Cone. & Reinf.Stee
Groutimz Contact & Pressu
Wateright Bulkhead & Fram
Round-Off
Power Tunnel
Excavation & Supports
Concrete
.Groutinl! C.nntart &. Pre!'l!'ltl
Round-Off
I&CF CSE 623 (3-80)
-
ESTIMATE SUMMARY
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT
COSTS
6.000 CY tiO
60.000 CY 312
170 CY 500
AMOUNT
300 000
18.720 000
85 000
(5.000)
er
6 000 CY 35 210 000
14 000 CY 317 4 438 000
1 700 CY 420 714.000
e 2 260 CF 58 131 080
27 TON 13,800 372.600
34.320
53.400 LF 8.372 447.064.800
348,000 CY 334 116 232.000
fp 317,000 CF 54 17 118.000
(14.800)
TOTALS
19.100 000
5,900,000
580 ,400_,000
-I
14879-001
JOB NO.
NOV. 1981
DATE
SHEET 5 OF 15
REMARKS
---
r--· ' '
HAJ/APD
PREPARED BY
F
CHECKED BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTERNATIVE B
I
NO. DESCRIPTION
Sura~ r.hamb~r -Uoo~r
'IO'v .... ..,., . ..,t::inn Ji. Snnnnrf'Q
r.nnr.ret~ & RE>inf .StP.Pl ·
F.&~.rthworks Ji. lt'Pnl'in<>
Round Off
PPnaf'nl"k-Tnrl ino.-1 SPt'f'inn
lt':vr!>vatinn Ji. Snnnnrf'l'l
Concrete & Reinf. Steel
Groutin~ Contact & Pres
Round-Off
Penstock-Horizontal Sectic
"'"'" .... '\tion & Sunoorts
Conr::rete $ Reinf_. Steel
r.routin~ r.ontact
Round-Off
,cf CSE 523 (3-801
ESTIMATE SUMMARY
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
UNIT QUANTITY UNIT COSTS AMOUNT
2'l c;oo r:v 227 5,788,500
5 500 r:v 880 4,840,000
15.000 r.v 27 405,000
(33 ,500)
24 000 CY 306 7,344,000
10 500 CY 845 8,872,500
lsure 5 500 CF 52 286,000
(2,500)
n & Elbow
12 000 CY 334 4,008,000
5 100 CY 365 1,861,500
2.600 CF 50 130,000
500
TOTALS
Heilnort
11 000 000
16,500,000
6,000,000
---..
)
14879-001
JOB NO.
NOV. 1981
DATE
SHEET 6 OF 15
REMARKS
Storage Work Area
-..
--1
'
HAJ/APD
PREPARED BY
MF
CHECKED BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTERNATIVE B
NO. DESCRIPTION
Penat"oc..k.-Wve Br~nrh<=>a to V~
Excavation & Supports
Concrete & Reinf. Steel
Steel Liner
Grouting-Contact
Round-Off
Penstock Between Valve Chan
Excavation & Supports
Concrete & Backfill
Round-Off
Draft Tube Tunnels
Rock Bolts & Grout
Concrete & Reinf. Steel
Round-Off
Surge Chamber -Tailrace
Excavation & Supports
I&CF CSE 523 (3-60)
----, -'Tr,,
' ' ' ., ' '
ESTIMATE SUMMARY 14879-001
JOB NO.
NOV. 1982
DATE
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT SHEET 7 OF 15
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT AMOUNT TOTALS REMARKS COSTS
11 ve Ch:~mhP.r
9 000 CY 480 4.320.000
6 100 CY 608 3.708.800
700 TON 5 000 3 500.000
7 000 CY 56 392,000
(20,800)
11, 900,_000
her & Powerhou~e .
850 CY 440 374,000 -
500 GY 550 275.000
(49.000)
600,000
15.000 LF 29 435,000
2,975 CY 425 1,264,375
625
1,700,000
5 000 CY 480 2,400,000
----.
--\
HAJ/APD
PREPARED BY
MF
CHECKED BY
CONCEPTUAl.
TYPE OF ESTIMATE
ALTERNATIVE B
NO.
:rrn
DESCRIPTION
Tailrace Tunnel & StructurEs
Cofferdam & Dewaterim!
Portal Excav & Protectic n
Cnncretf'! F. Rf'!inf Steel
Walkwav Bridtze
St-nnlnaa & Hoists
Tunnel Exl'av F. Snnnorts
Plucz Excavation
Round-Off
Tailrace r'l><:mn"! 1
r.h .. nnal ...,,.,.,.. .. "\tion
River Trainimz Works
River Bed Deepening
Mech & Elec.
,-:-r-:; ~. i l I )'
ESTIMATE SUMMARY
CHAKACHAMNA HYDROEI.ECTRIC PRO.JECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT AMOUNT COSTS
LS 2.000 000
2.000 CY 65 130,000
1 200 CY 600 720 .ooo
LS 65,000
81 TON 8,500 688,500
20 000 CY 290 5.800.000
4.000 CY 50 200,000
(3 ,500)
80.000 CY 9 720 .ooo
(20,000)
50,000 CY 10
LS
TOTAL RESERVOIR, DAM AND WJ TERWAYS
rCF CSE 623 l3.fiOI
,-----.., --
14879-001
JOB NO.
NOV. 1981
DATE
SHEET 8 OF 15
TOTALS REMARKS
9,600,000
700,000
500,000
6,100,000
694,200,000
...
---. --l
HAJ/APD
ESTIMATE SUMMARY 14879-001
PREPARED BY JOB NO.
MF NOV. 1981
CHECKED BY DATE
CONCEPTUAL CHAKACHAMNA HYDROELECTRIC PRQJECT
PROJECT SHEET 9 OF 15
TYPE OF ESTIMATE
ALASKA POWER AUTHORITY
ALTERNATIVE B PREPARED FOR
NO. DESCRIPTION QUANTITY UNIT UNIT AMOUNT TOTALS COSTS REMARKS
Turbines & Generators 330 MW
Turbines 4 EA 8,480,001 33,920,000
Generators 4 EA 6,00(\001 24~000,000
Round Off T2lf,OOO)
':J 1 .~uu ,000
Accessorv Electrical Eouiot ent
Eouioment LS ~,':JUU,UUU
Misc. Power Plant Eouiomen
Crane Brid2e 1 EA 930,000
Other Power Plant Eouiu. LS 6,370.000 7,300,000
Switchvard Structures
Earthworks 15,000 CY 25 375,000
Concrete & Reinf. Steel 3,800 CY 640 2 432 000
Struc. Steel & Misc.Meta s 225 TON 3,500 787.500
Round-Off 5 500
3,600,000
.
loCF CSE 623 I:HIOI
...---
l -~ ~ ~ ~. ~.,· ',' 1,---,1 : ~ j ',I J•.l i l t I ) l. I I I: .
HAJ/APD
PREPARED BY
QJJ
f61
CHECKED BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTERNATIVE B
NO. DESCRIPTION
Swit:~hvard EQuioment
TransfnrmP.rs 105 MVA
Unit & Line Breakers
_Switches F. T.i ohtn.Arrest~ rs
210 KV Cables
Controls & Metr 1 2 EQuio.
Rn m~ O-ff
t r:ommunication and Su12v
Control F.nnto -
H&CF CSE 623 (3-60)
ESTIMATE SUMMARY
CHAKACHAMNA HYDROELECTRIC PROJECT
QUANTITY
5
7
30
18,000
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
UNIT UNIT AMOUNT COSTS
EA 1,030,00 5,150,000
EA 185,00 1,295,000
EA 34,00 ) 1,020,000
LF 130 2,340,000
LS 2,700,000
(5,000)
LS
·.
-
14879-001
JOB NO.
NOV. 1981
DATE
SHEET 10 OF 15
TOTALS REMARKS
12,500,000
1,600,000
·-··-
----
HAJ/APD
PREPARED BY
___,
''I __.
,--,
l
ESTIMATE SUMMARY
14879-001
JOB NO.
NOV. 1981
CHECKED BY DATE
CONCEPTUAL CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT SHEET 11 OF 15
TYPE OF ESTIMATE
ALASKA POWER AUTHORITY
ALTERNATIVE B PREPARED FOR
NO. DESCRIPTION QUANTITY UNIT UNIT AMOUNT TOTALS REMARKS COSTS
~SPORTATION FACILITIES
Port Facilities
Causeway 19,600 CY 80 1 'if\R 000
Trestle Piles 50 TON 11 300 565 000 L = 150 LF !612" t = ~"
Trestle Struct. Steel llO TON 3_.500 385 000
Trestle Reinf. Cone. 150 CY 700 JO'i .000
Facilities -Allowance LS 2 000 000
Round-Off (23 000)
4.600.00
Air~>.ort
Earthwork 54_ 500 CY 16 872,000
Culverts 1.000 LF 65 65,000
Subbase & Base 'i'i.OOO CY 14 770,000
Building -Allowance LS 300,000
Round-Off (7 ,000)
2,000,000
H&CF CSE 523 IJ.80l
---
..---
I
HAJ/APD
PREPARED BY
MF
CHECKED BY
CONCEPTUAL
--
TYPE OF ESTIMATE
ALTERNATIVE B
NO. DESCRIPTION
Ac.c.ess & Construction Roads
Mil~ 0+00 to 18+00
Earthwnr1c
Culverts
Brid11:es
Snhh:tRP . & Base
Guard Ra-f 1
RPnair ExiRtina Road
~nnw 'J;',:>nrPR
Round-Off
MilP 1R+00 to ~'\+On
F.:n·rhwnr1cl'l
Culverts
S: 1hhaRE". &_ BasE".
Guard Rail
Reoair Existim~ Road
Snow Fences
Round~Off
MilE". 1'i+OO tn 19+00
F.art-hwork
Culverts
Rrid~:>P.
Suhha!;l.P. & R::tRP
Guard Rail
Snnw FPnC.E".R
Rnnnrt-nff
.. &CF CSE 623 13-801
1
---
ESTIMATE SUMMARY 14879-001
JOB NO.
NOV. 1981
DATE
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT SHEET 12 OF 15
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT AMOUNT TOTALS REMARKS COSTS
175.000 CY ~. 60 1 155.000
1,500 LF 65 97 soo 36"0 CMP
1,400 SF 150 210 000
85,400 CY 15 1 281 000
1 200 LF 25 10_.000
95,000 LF 10 950 000
5,000 LF 35 175 000
1 500
3.900.000
465,000 CY 6.60 9 669 000
3,600 LF 80 288_.000 48"¢ CMP
165,000 CY 15 2 475 000
13,000 LF 25 325 000
16,000 LF 10 160 000
1,000 LF 35 35,000
48,000
13 000 000
445,000 CY 8.30 3 693 500
1,000 LF 80 80_,000 48"0 CMP
9.000 SF 150 1 350 000
38,000 CY 15 570 000
10,000 LF 27 270 000
2,000 LF 35 70 000
(33 500)
6.000.QDQ
----
HAJ/APD
PREPARED BY
MF
CHECICED BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTERNATIVE B
NO. DESCRIPTION
Walkwav To Gate Shaft
Earthwork
Guard Rail
BridR:e
Rio rap
Round-Off
Access Road to MacArthur
Earthwork
Culverts
Brid2e ImProvements
Subbase & Base
Guard Rail
Snow Fences
Round-Off
AcceRs Road to Tailrace
Earthwork
Culverts
SnhhAAP & Base
Guard Rail
Round-Off
H&CF CSE 523 13-801
ESTIMATE SUMMARY
CHAKACHAMNA HYDROELECTRIC PROJECT
QUANTITY
1 200
1 000
200
100
Valley
545,000
2 400
9,000
105,000
6 000
3 000
runnel
56.000
100
2.500
600
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
UNIT UNIT AMOUNT COSTS
CY 20 24 000
LF 25 25 000
SF 150 30,000
CY 35 3.500
17.500
CY 7 3.815.000
LF 75 180,000
SF 70 630,000
CY 15 1 575.000
LF 25 150,000
LF 35 105 000
45,000
CY 8 448,000
LF 80 8,000
CY 20 50,000
LF 25 15,000
(21,000)
-
14879-001
JOB NO.
NOV. 1981
DATE
SHEET 13 OF 15
TOTALS REMARKS
100,000
36"~ and 48"~ CMP
6,500,000
4R"~ CMP
500,000
-··
---·-) --i -I
HAJ /APD
ESTIMATE SUMMARY
14879-001
PREPARED BY JOB NO.
MF Nov. 1981
CHECKED BY DATE
CONCEPTUAL
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT SHEET 14 OF 15
TYPE OF ESTIMATE
ALASKA POWER AUTHORITY
ALTERNATIVE B PREPARED FOR
NO. DESCRIPTION QUANTITY UNIT UNIT AMOUNT TOTALS COSTS REMARKS
Access Road to Downstream p, ~er Tunnel
Earthwork 215,000 CY 9.80 2,107,000
Culverts 800 LF 80 64,000 48"~ CMP
Brid2e 3,000 SF 150 450,000
Subbase & Base 10,000 CY 21 210,000
Guardrail 9,000 LF 32 ·L81r,OOO
Snowshed & Slide Fall 1,000 LF 800 800,000
Round-Off (19z000)
. J,YUU,UUU
Temoorarv Construction Roads
Earthwork 61,000 CY 0 366,000
Culverts 600 LF 80 48 000 48"~ CMP
Brid2e 3,000 SF 150 450,000
Guardrail 2,000 LF 25 50,000
Round-Off (14.000)
900 ,ooo.
Road Maintenance
SuDDDer Season 45 MO [TSO',OUU 6,750,000
Winter Season 30 MO 1600,000 18,000,000
Round-Off 50,000
24,800,000
ITOTAT AC.C.F.SS & DNS' 'K.ITC.TION RO lDs 59,600,000
kCF CSE 523 13-801
HAJ/APD
PREPARED BY
MF
CHECKED BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTERNATIVE B
__.,
J
,-,-, ~
:1,, .I L
ESTIMATE SUMMARY
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
NO. DESCRIPTION QUANTITY UNIT UNIT AMOUNT COSTS
Transmission Line
Clear & Grub 82 MI 225,000 18,450,000
Transmission Line 82 MI 343,000 28,126,000
Submarine Cable 21 MI 792,000 16,632,000
Round-Off (8!000)
TOTAL SPECIFIC CONSTRUCTION
COST AT JANUARY 1982 PRICE
LEVELS
16CF CSE 523 13-801
-
TOTALS
bj, zuu ,-uou
-gO,) , ~uu, uuu
-)
14897-001
JOB NO.
NOV. 1981
DATE
SHEET 15 OF 15
REMARKS
ALTERNATIVE C
ESTIMATED COST
HAJ/APD
PREPARED BY
MF
CHECKED BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTERNATIVE C
NO. DESCRIPTION
POWER PLANT STRUCTURE & IMPRC
Valve Chamber
Excavation & Supports
Concrete & Reinf Steel
-,,_
ESTIMATE SUMMARY
CHAKACUAMNA HYDROELECTRIC PRQJECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT AMOUNT COSTS
VEMENTS
10,500 CY 270 2,835,000
6,520 CY 410 2,673,200
Struc. Steel & Misc.Meta s 52 TON 1,800 93,600
Round-Off tl 2 ~UU)_
Underground Powerhouse .
Dewatering LS 4,10U,OOO
Excavation & Supports 64,000 CY 155 9 920 000
Drilling-Percus.& Rotary 15,000 LF 30 45_0 LOlli)
Concrete & Reinf.Steel 14,200 CY 630 8,946,000
Struc. Steel & Mise Metals 330 TON 5,300 1,749,000
I Architectural LS 1,000,000
Round-Off 35,000
Bus Galleries Between Power
house & Transformer Vaults
Excavation & Supports zoo CY ~Z) 165,000
Concrete 12.0 CY 290 34,800
Round Off 200
t&CF CSE 623 (3-801
TOTALS
:>,bUU,OUU
26,200,000
200 000
--1
14879-001
JOB NO.
NOV. 1981
DATE
SHEET 1 OF 16
REMARKS
Entire Under~round Com~lex
2" - 3 "0
--or---' '
HAJ/ AP'D ESTIMATE SUMMARY 14879-001
PREPARED BY JOB NO.
MF NOV. 1981
CHECKED BY DATE
CONCEPTUAL CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT SHEET 2 OF 16
TYPE OF ESTIMATE
ALASKA POWER AUTHORITY
ALTERNATIVE C PREPARED FOR
NO. DESCRIPTION QUANTITY UNIT UNIT AMOUNT TOTALS REMARKS COSTS
Transformer Gallerv & Tunne lls
Excavation & SupQorts 11,960 CY 290 3.468.400
Concrete & Rein£ Steel 830 CY 460 381,800
Struc Steel & Misc.Metals 120 TON 3,800 456,000
Round Off (6 ,200)
4,300,000
Valve Chamber & Transformer
Galler~~Access Tunnels
Excavation & Supports 1,500 CY 250 375,000
Concrete 60 CY 290 17,400
Round-Off 7,600
400,000
Powerhouse Access Tunnel
Portal Excav.& Protectio~ 56,000 CY 10 560 000
Portal Cone.& Reinf.Steel 1,000 CY 570 570 000
Tunnel Excav.& Supports 24,000 CY 300 7 200 000
Tunnel Concrete 900 CY 290 261 000
Tunnel Misc. Metals 30 TON 11,000 330 000
Subsurface Exploration
Mobilization LS 1 500 000
Exploratory Adit 1,000 LF 1,800 1 800 000
Core drilling 5,000 LF 140 700,000
Helicopter Service LS 500 000
Round-Off (21 000) -13 500 000 .. -.... ---····
loCF CSE 523 IJ.80)
--=l ---,...-.-,..
I
ESTIMATE SUMMARY
HAJ/APD 14879-001
PREPARED BY JOB NO.
MF NOV. 1981
CHECKED BY DATE
CONCEPTUAL CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT SHEET 3 OF 16
TYPE OF ESTIMATE
ALASKA POWER AUTHORITY
ALTERNATIVE C PREPARED FOR
NO. DESCRIPTION QUANTITY UNIT UNIT
COSTS AMOUNT TOTALS REMARKS
r.ahlP Wav
rnn .... retP t. R ... ~nf St-P ... l 1_.000 CY 700 700,000
Mi ~ Metals & C::th le Sun. 26 TON 5,100 132,600
P'lrt-P<>n ... la
R.,und-Off (32,600)
800.000
TOTAl POWRR PLANT STRl IKI': TMP~I 'J'<: 51,000,000
HLioCF CSE 523 13-60)
-
HA!/APD
PREPARED BY
MF
CHECK EO BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTERNATIVE C
NO. DESCRIPTION
RF.S .. :WUI .R OAM & I.JATF.Rt.J<\YS
Doaorunir
LJ..,t-or Louol RPf'nril~1117
Tnt-alco ~t-rnf'fo\lTP!
C::-lt-o Rvnlnr,.t-inn
Mnh-11-1'7ot-inn
f'nro n ..... , 1 ino
HP1if'nnt-or ~pruif'P
'l'unnP1 Rvf'aV. & Snnnort.R
'l'unrtol f'nn~"> F. RP~nf StPP
l<>lc<>-TJ'In fFinJ'Il Rnnnil)
D1 "'~'"' ~ n. ToYnn f'nnl'
n-cu~nD f'ro •. Y
Rnund-Off
Tnt-.,lc<> r.J'It-P Sh.,ft
Sh<:~ft-F.vr<>u F. Stnnnrt-!';l
Ma!';ll'l Surf:~rP F.x~~"
f'rmrrPh> 1.. ~f>inf C:t-ool
Mi Rf' Mf>t:~l"' r.atf>R & Hoi .t
~nnnn-Off
H&CF CSE 623 13-60)
ESTIMATE SUMMARY
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT
COSTS AMOUNT
LS
,J.S 150,000
5,000 ILF 80 400,000
ILS 150,000
12,000 CY 470 5,640,000
100 :cr 350 35,000
ILS 3,000,000
600 lr.v 700 420,000
60 I DAYS 10,000 600,000
5,000
10,000 CY 360 3 600.000
50,000 CY 30 1,500,000
5,700 r.v 890 5,073,000
244 lmN 12,500 3,050,000
(23.000)
TOTALS
100,000
L 26'
10 400 000
13 200 000
--·-'
14879-001
JOB NO.
NOV. 1981
DATE
SHEET 4 OF 16
REMARKS
~
J
-1""<.....,-
'.1 I .•
HAJ/APD
PREPARED BY
MF
CHECKED BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTERNATIVE C
NO. DESCRIPTION
Access Tunnel at Intake
Portal Excav. & Protectio
Tunnel Excav.& Supports
Tunnel Cone. & Reinf.Stee
Round-Off
Access Tunnel at Sur2e Cham
Portal Excav. & Protectio
Tunnel Excav.& Suooorts
Tunnel Cone. & Reinf.Stee
Groutinll Contact & Pressu:
Rlimnd~Off
H6Cf' CSE 623 13-801
n-T:J -J -.
ESTIMATE SUMMARY
CHAKACHAMNA HYDROELECTRIC PROJECT
er
·e
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT
COSTS
6 QOO CY 50
72 000 CY 295
200 CY 500
6.000 CY 55
23 000 CY 323
2.300 CY 420
3.400 CF 58
AMOUNT
300 000
21 240.000
100,000
(40.000)
330,000
7.429.000
966,000
197.200
(22,200)
-
-
14879-001
JOB NO.
NOV. 1981
DATE
SHEET 5 OF 16
TOTALS REMARKS
21,600,000
8 900,000
---~ ~!"!':
•. , I , ,,
HAJ/APD
PREPARED BY
MF
CHECKED BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTERNATIVE C
NO. DESCRIPTION
Access Tunnel at Mile 3. 5 No.1
Portal Excav & Protection
Tunnel Excav & Supports
Tunnel Cone & Reinf Steel
Grouting-Contact & Pressure
Round-Off
Access Tunnel at Mile 7. 5 No.2
Portal Excav & Protection
Tunnel Excav & Supports
Tunnel Cone & Reinf Steel
Grou tine-Contact & Pressure
Round-Off
Power Tunnel
Excavation & Supports
Concrete
Groutine-Contact & Pressure
Round Off
H&CF CSE 523 (3-80)
~
"' -.I
ESTIMATE SUMMARY
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT AMOUNT COSTS
6.000 CY 53 318,000
68,000 CY 297 20,196,000
500 CY 430 215,000
1,125 CF 58 65,250
5,750
6.000 CY 54 324,000
45.000 CY 298 13 '410 ,000
1.600 CY 420 6 72 ,000
2.300 CF 58 133,400
(39 ,400)
67 000 LF 7,698 515,766,000
514.000 CY 334 171,676,000
464.000 CF 54 25,056,000
2,000
-
14879-001
JOB NO.
NOV. 1981
DATE
SHEET 6 OF 16
TOTALS REMARKS
20,800,000
14,500,000
712,500,000
-"~~"·
-11 "' --
HAJ/APD tlJ ESTIMATE SUMMARY
PREPARED BY
14879-001
JOB NO.
MF NOV. 1981
CHECKED BY DATE
CHAKAC~A HYDROELECTRIC PROJECT CONCEPTUAL PROJECT SHEET 7 OF 16
TYPE OF ESTIMATE
ALASKA POWER AUTHORITY
ALTERNATIVE c PREPARED FOR
NO. DESCRIPTION QUANTITY UNIT UNIT AMOUNT COSTS TOTALS REMARKS
Surfl~ ChamhPr -Unn~r
Rxr::aua.tion I. ~unnnrt-a 35 500 f'V 200 7,100,000
Conr.rete._ & Reinf ~t-AAl · 6,100 r:v 880 5,368,000
R::trthworks & FPnc-ino 15,000 r:v 27 405,000 Heliport, Storage, Work Area
Rnnnii-Dff 27.000
12,900,000
PPnRt"nrk-Inel in~d SPrt"inn
F.xr::au::at"inn I. ~unnnrt-a 23.400 -CY 271 6,341,400
Concrete & Reinf. Steel 10,500 CY 837 8;7ss,5oo
GroutinR Contact & Pres Iaure 5,000 CF 52 260~000
Round-Off 10.100
15-;-z!CJO ,DUO
Penstock-Horizontal Sectio n & Elbow
F.xrstvation & Suooorts 14.000 CY 310 4. 340_z_QOO
Concrete S Re:fnf Steel 6 000 CY 365 2 190~000
Grm•tinR -Contact 3 000 CF 50 150_. 000
Round-Off 20.000
6,700,000
~IICF CSE 523 IJ.801
-\ -~· ,,, -,, .!
II ESTIMATE SUMMARY
HAJ/APD
PREPARED BY
CHECKED BY
CHAKACHAMNA HYDROELECTRIC PROJECT
CONCEETIIAI, PROJECT
TYPE OF ESTIMATE
ALTERNATIVE c ALASKA fQWER AUTHORITY
PREPARED FOR
NO. DESCRIPTION QUANTITY UNIT UNIT AMOUNT COSTS
P<>nat"n,.L--tJv.,. Rr:>nl"h<=>a t"n V::< lve Chamber
Excavation & Suooorts 10 000 CY 432 4,320,000
Concrete & Reinf. Steel 7,200 CY 608 4,377,600
Steel Liner 650 TON s.ooo 3,250,000
Grouting-Contact 3,000 CY so 150,000
Round-Off 2 400
Penstock Between Valve ChaE her & Powerhom e
Excavation & Suooorts 1 000 CY 440 440.000
Concrete & Backfill 600 CY 550 330.000
Round-Off 30.000
Draft Tube Tunnels
Rock Bolts & Grout 19 000 LF 27 513 .ooo
Concrete & Reinf. Steel 3.300 CY 425 1,402,500
Round-Off (15 500)
Sur£e Chamber -Tailrace
Excavation & Sunnorts 5 000 CY 480
ISICF CSE 623 13-801
--:
'
14879-001
JOB NO,
NOV. 1982
DATE
SHEET 8 OF 16
TOTALS REMARKS
12.100 .ooo
800,000
1,900,000
2,400 000
HAJ/APD
PREPARED BY
MF
CHECKED BY
CONCEPTUAl.
TYPE OIF ESTIMATE
-\
ALTERNATIVE C
NO.
-
DESCRIPTION
Tailrace Tunnel & StructurEs
Cofferdam & n .. ,.u:•t-F!rinll
Portal Excav & Protect!( n
Concrete & Rein£ Steel
WAl.kwav Brid2e
_Stoolo.IZ.s & Hoists
Tunnel F.xC'aV. & Sunnorts
Pluo Excavation
Round-Off
Tailrace r.h<>nno:>l
Ch<>nnP 1 E.xc.avation
River Traininl! Works
River Bed Deepening
Mech & Elec.
."T""'"7'.
.J I , '
,.-.-
)
ESTIMATE SUMMARY
CHAKACHAMNA HYDROEI.F.CTRTC PRO.IECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT AMOUNT COSTS
LS 2,000,000
2 000 CY 6S 130,000
1 200 CY 600 720,000
LS 6S 000
81 TON 8,SOO 688,SOO
2S 000 CY 260 6,SOO,OOO
4,000 CY so 200,000
(3 ,SOO)
100,000 CY 9
so ,000 CY 10
LS
TOTAL RESERVOIR, DAM AND Wl TERWAYS
IIICF CSE 623 13-801
14879-001
JOB NO.
NOV. 1981
DATE
SHEET 9 OF 16
TOTALS REMARKS
10 ,300,000
900,000
soo,ooo
S,700,000
871,600,000
--
-
HAJ/APD
PREPARED BY
MF
CHECKED BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTERNATIVE C
NO. DESCRIPTION
Turbines & Generators
Turbines
Generators
Round-Off
Accessory Electrical Eouion ent
Eauioment
Misc. Power Plant Eauinmen
Crane Brid2e
Other Power Plant Equip.
SwitC'.hvard Stru£'tures
Earthworks
Concrete & Reinf. Steel
Struc. Steel & Misc.Meta s
Round-Off
IIIICF CSE 623 13-801
,..---,
I
ESTIMATE SUMMARY
...----.
I.
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT
COSTS AMOUNT
4 EA 7~970 00 ) 31,880,000
4 EA 5,660,00 22,640 ,ooc
(20 ,00(
LS
1 EA 900 ,OOt
LS 6 ,000,00(
15,000 CY 25 375,00(
3,800 CY 640 2 '432 ,00(
225 TON 3,500 787,50(
5 ,50(
,-.--.-,,
14879-001
JOB NO.
NOV. 1981
DATE
SHEET 10 OF 16
TOTALS REMARKS
300 MW
I)
54,500,000
9,oou,uuu
6 ;gn-u ,ooo
3,600,00(
-
ESTIMATE SUMMARY
1JAJ/APD 14879-001
PREPARED BY JOB NO.
MF NOV. 1981
CHECKED BY CHAKACHAMNA HYDROELECTRIC PROJECT DATE
CONCEPTUAL PROJECT SHEET 11 OF 16
TYPE OF ESTIMATE
ALASKA POWER AUTHORITY
ALTERNATIVE C PREPARED FOR
NO. DESCRIPTION QUANTITY UNIT UNIT AMOUNT TOTALS COSTS REMARKS
Sw:lt:rhvard Eauioment
Tr.<>nqfnrmPrR lOll MVA 5 EA 1~010,00 5,050,000
Unit & Line Breakers 7 EA 180,00( 1,260,000
Swit-rh~s & Li.2htn Arrestc rs 30 EA 33,00 990,000
210 KV Cables 18,000 LF 12C 2,160,000
Controls & Metr 1 2 Eauip, LS 2,630,000
llnnn..1 Off 10,000 . 12,100,000
f'nmm Suov Cont-rol Eaui.o. LS 1,600,000
H&CF CSE 523 IJ.BOI
--
HAJ/APD
PREPARED BY
~
" I : ;
ESTIMATE SUMMARY
14879-001
JOB NO.
NOV. 1981
CHECKED BY DATE
CONCEPTUAL CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT SHEET 12 OF 16
TYPE OF ESTIMATE
ALASKA POWER AUTHORITY
ALTERNATIVE C PREPARED FOR
NO. DESCRIPTION QUANTITY UNIT UNIT AMOUNT TOTALS REMARKS COSTS
~SPORTATION FACILITIES
Port Facilities
Causeway 19 600 CY 80 1 568 000
Trestle Piles 50 TON 11 300 565 000 L = 150 LF, ~12", t = ~II
Trestle Struct. Steel 110 TON 3 500 385 000
Trestle Reinf. Cone. 150 CY 700 105 000
Facilities -Allowance LS 2,000,000
Round-Off (23 000)
4,600,000
Airport
Earthwork 54 500 CY 16 872,_000
Culverts 1,000 LF 65 65,000
Subbase & Base 55 000 CY 14 770 .ooo
Building -Allowance LS 300,000
Round-Off (7 ,000)
2,000,000
H&CF CSE 523 (3-801
-_ .... --,I
HAJ/APD
PREPARED BY
F
CHECKED BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTERNATIVE C
NO. DESCRIPTION
Ac.c.ess & Construction Roads
Mile 0+00 t"n UUOO
Ra 1work
C.u1verta
Bridtzes
~ .. hh<:~A<> & Base
11u.R rd R.R i 1
Renair Existintz Road
Snnw li'"'"""'"'
Rnnncl ... Off
Mil P 1 R+OO to 15+00
F..Rrt"hwnrlc!'l
Culverts
Subbase & Base
Guar_d Rail
Renair Existin~ Road
Snow Fences
Round-Off
Mile 35+00 to 39+00
Earthwork
C.nlverts
Rrirlo<>
Suhhase &. Base
r.n;~ rei RH i 1
Snow Fences
Rnnnd-Off
iACF CSE 523 !3-801
-
ESTIMATE SUMMARY 14879-001
JOB NO.
NOV. 1981
DATE
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT SHEET 13 OF 16
'ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT AMOUNT TOTALS REMARKS COSTS
175,000 CY 6.60 1,155,000
1,500 LF 65 97,500
1,400 SF 150 210,000
85,400 CY 15 1,281,000
1~200 LF 25 30,000
95,000 LF 10 950,000
5,000 LF 35 175,000
1,500 3,900,000
1,465,000 CY 6.60 9,669,000
3,600 LF 80 288,000 48"rP CMP
165,000 _cy_ 15 2,475,000
13,000 LF 25 325,000
16,000 LF 10 160,000
1,000 LF 35 35,000
4R 000
13,000,000
445,000 _ey 8.30 3,693,500
1,000 LF 80 80,000 48"~ CMP
9,000 _SF 150 1,350,000
38,000 CY 15 570,000
10,000 LF 27 270,000
2,000 _LF 35 70,000
(33 ,500)
6,000 000
---
HAJ/APD
PFIEPAFIED BY
MF
CHECKED BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTERNATIVE C
NO. DESCRIPTION
Walkwav To Gate Shaft
Earthwork
Guard Rail
Brid2e
Riorao
Round-Off
Access Road to Tailrace T1
Earthwork
Culverts
Subbase & Base
Guard Rail
Round Off
H&CF CSE 523 13-601
-
ESTIMATE SUMMARY
CRAKACHAMNA HYDROELECTRIC PROJECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT
COSTS AMOUNT
1,200 CY 20 24,000
1,000 LF 25 25,000
200 SF 150 30,000
100 CY 35 3,500
17,500
nnel
56,000 CY 8 448,000
100 LF 80 8,000
2,500 CY 20 50,000
600 LF 25 15 ,o-o-u
(21 ,000)
-
14879-001
JOB NO.
NOV. 1981
DATE
SHEET 14 OF 16
TOTALS REMARKS
-100,000
4ti"¢l CMP
50U,UUU
HAJ/APD
PREPARED BY
MF
CHECKED BY
~
' -~I
ESTIMATE SUMMARY
CHAKACHAMNA HYDROELECTRIC PROJECT
CONCEPTUAL PROJECT
TYPE OF ESTIMATE
ALASKA POWER AUTHORITY
ALTERNATIVE C PREPARED FOR
NO. DESCRIPTION QUANTITY UNIT UNIT AMOUNT COSTS
Access Road to Downstream p, Mer Tunnel
Earthwork 215.000 CY 9.80 2.107 000
Culverts 800 LF 80 64,000
Bridlle 3,000 SF 150 450.000
Subbase & Base 10,000 CY 21 210,000
Guardrail 9,000 LF 32 288,000
Snowshed & Slide Fall 1.000 LF 800 800,000
Round-Off (19,000)
Tem_porarv Construction Roada
Earthwork 61,000 CY 6 366,000
Culverts 600 LF 80 48,000
Br:Lda.e 3,000 SF 150 450.000
Guardrail 2,000 LF 25 50,000
Round-Off (14,000)
Road Mllintenance
SulllDDer Season 36 MO 120,000 4,320,000
Winter Season 24 MO 480,000 11,520,000
Round-Off (40,000)
TOTA T AfY~F~~ 1\, rnNs ·~ I IN l loAn~
HACF CSE 523 (3-601
TOTALS
48",6 CMP
3,900,000
900,000
15,800,000
44_,100 000
.-----,
I
14879-001
JOB NO.
Nov. 1981
DATE
SHEET 15 OF 16
REMARKS
·-···· .
PREPARED BY
HAJ/APD IJJ. ESTIMATE SUMMARY
14897-001
JOB NO.
MF NOV. 1981
CHECKED BY DATE
CONCEPTUAL CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT SHEET 16 OF 16
TYPE OF ESTIMATE
ALASKA POWER AUTHORITY
ALTERNATIVE C PREPARED FOR
NIO. DESCRIPTION QUANTITY UNIT UNIT AMOUNT TOTALS REMARKS COSTS
Transmission Line
Clear & Grub 70 MI ~25 000 15 750,000
Transmission Line 70 MI ~44 000 24.080,000
Submarine Cable 21 MI ~92 000 16 632,000
Round-Off 38,000
56,500,000
TOTAL SPECIFIC CONSTRUCTION C OST
AT JANUARY 1982 PRICE LEVELS 1,117,500,000
H&CF CSE 523 (3-601
ALTERNATIVE D
ESTIMATED COST
-
HAJ/APD ESTIMATE SUMMARY
14879-001
I'REPAPJED BY JOB NO.
MF NOV. 1981
CHECKED BY DATE
CONCEPTUAL CHAKACUAMNA HYDROELECTRIC PROJECT
PROJECT SHEET 1 OF 16 .
TYPE OF ESTIMATE
ALASKA POWER AUTHORITY
ALTERNATIVE D PREPARED FOR
NO. DESCRIPTION QUANTITY UNIT UNIT AMOUNT TOTAlS REMARKS COSTS
POWER PLANT STRUCTURE & IMPRC VEMENTS
Valve Chamber
Excavation & Supports 10,500 CY 270 2,835,000
Concrete & Reinf Steel 6,520 CY 410 2;073,LOO-
Struc. Steel & Hisc.Heta s 52 TON 1,800 ~.01JCJ
Round-Off Tiz""BOU"J
:>,bUU,UUU
Umt_er_ground Powerhouse
Dewatering LS 4,100,000 Entire Underground Como lex
Excavation & Supports 64,000 CY 155 q Q20 000
Drillina-Percus.& Rotarv 15,000 LF 30 h.'lO 000 2 11
-3"0
Concrete & Reinf.Steel 14,200 CY 630 8.946.000
Struc.Steel & Mise Metals 330 TON 5,300 1. 749 .ooo
Architectural LS 1,000,000
Round-Off 35.000
26,200,000
Bus Galleries Between Power
house & Transformer Vaults
Excavation & Supports 20U CY 825 165,000
Concrete ·uu CY Z9U 34,800
Round Off .200.
200 000
--H6CF CSE 623 13-801
~I ~I .----.,.I
-J j
HAJ/APD ESTIMATE SUMMARY 14879-001
PREPARED BY JOB NO.
MF NOV. 1981
CHECKED IIY DATE
CONCEPTUAL CHAKACHAMNA HYDROELECTRIC PROJECT
SHEET 2 OF 16 PROJECT
TYPE OF ESTIMATE
ALASKA POWER AUTHORITY
ALTERNATIVE D PREPARED FOR
NO. DESCRIPTION QUANTITY UNIT UNIT AMOUNT TOTALS REMARKS COSTS
TranAfnrm~r GallerY & Tunne ls
Excavation & Supports 11.960 CY 290 3 468.400
Concrete & Reinf Steel 830 CY 460 381,800
Struc Steel & Misc.Metals 120 TON 3,800 456,000
Round Off (6,200)
4,300,000
Valve Chamber & Transformer
Gallery-Access Tunnels
Excavation & Supports 1,500 CY Z50 375,000
Concrete 60 CY 290 17,400
Round-Off 7,600
400,000
Powerhouse Access Tunnel
Portal Excav.& Protection 56,000 CY 10 ' 560 000
Portal Cone.& Reinf.Steel 1,000 CY 570 570 000
Tunnel Excav.& Supports 24,000 . CY 300 7 .200 000
Tunnel Concrete 900 CY 290 261.000
Tunnel Misc. Metals 30 TON 11,000 330.000
Subsurface Exploration
Mobilization LS 1 500 000
Exploratory Adit 1,000 LF 1,800 1 800 000
Core drilling 5,000 LF 140 700,000
Helicopter Service LS 600 000
Round-Off (21 000)
13.500 000
16CF CSE 623 13-801
-~ \ '
HAJ[APD IIJ PREPARED BY
MF
CHECKEID BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTERNATIVE D
' NO. DESCRIPTION
C'.Ah 1'" Wav
C'.nnrr'"l-'" I. RPinf SI'!F>'"l
Mi.JIC..ME!.I'.RlR & r..Ahlo Sun
Port' PAn.,.la
Round-Off
TOTAl PnURA PT.ANT c;:TAJ I' IIIli(
!IICF CSE 523 13-80)
-I
ESTIMATE SUMMARY
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT
COSTS AMOUNT
1 000 CY 700 700,000
26 TON 5,100 132,600
(32.600)
I Ml"lliiV!t:MJo:NTS
r-. --
TOTALS
800.000
51,000,000
14879-001
JOB NO.
NOV. 1981
DATE
SHEET 3 OF
REMARKS
16
.---]1' '-ll
lj
,;
[I
·-\
HAJ/APD
PREPARED BY
MF
CHECKED BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTERNATIVE D
NO. DESCRIPTION
Rl ITR nAM I. UATF.RUAV~
.. ......
Uai"AP T.auAl RAronr,Jina
Tnt-alrA ~l"rnrot-nrA
~it-A F.xnlnrAt'inn
Mnhili'J'At'inn
,...,.,...,. nr.f 11 ina
u .. l.f,.,. .......... c:: .......... a
Tnnnal F.xrau I. ~nnnn1'"t'A
Tunnal l'nnl' I. RA.fnF ~t-AA
T..Air,:>-TAn (FinAl Dnunrl\
Pl aro,:> I. n. rr~ ...... r ....... .,.. -.
niuina r.,...,.w
Rnnnd:::nff
Tnt-Air.,. r.At-.,. ~hAft-
Shaft' F.xl'au.l. c:: .............. ,...,
MAA~>~ ~nrf::tl'l'l F.xP::ttr
C. I !t~ & RPinf ~t'PP1
MiAr MPt'AlA r.At-PA I. Hni
Rnnn,J. -nf f
HS.CF CSE 623 tJ.aOI
~ ..
-·-;--1
, 'I
~~~j
;I
;J
ESTIMATE SUMMARY
14879-001
JOB NO.
NOV. 1981
DATE
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT SHEET 4 OF 16
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT AMOUNT TOTALS COSTS REMARKS
LS 100 000
ILS 150.000
5,000 ILF 80 400.000
II.s 150.000
12,000 ,CY 470 5,640,000
100 lev 350 35.000
II.S 3,000,000 L = 26'
600 ir.v 700 420.000
60 I DAYS 10.000 600.000
5,000
10,400 000
10 000 CY 360 3,600.000
50,000 lr.v 30 1.500 .ooo
5,700 lr.v 890 5,073 000
244 I TON 12,500 3,050,000
(23 .000)
13 200 000
-
UAJlA!D
P'AEP'AAIED BY
MF
--. l~' -· I !"'''""["'·.
(, L> , \"TJj
ESTIMATE SUMMARY
,..---,
'
CHECKED BY CHAKACHAMNA HYDROELECTRIC PROJECT
CONCEPTUAL PROJECT
TYPE OF ESTIMATE ALASKA POWER AUTHORITY
ALTERNATIVE D PREPARED FOR
NO. DESCRIPTION OUANTITY UNIT UNIT AMOUNT COSTS
Access Tunnel at Intake
Portal Excav. & Protectio 6 QOO CY 50 300 000
Tunnel Excav.& Suooorts 72.000 CY 295 21.240.000
Tunnel Cone. & Reinf.Stee 200 CY 500 100.000
Round-Off (40.000)
Access Tunnel at Sur2e Cham er
Portal Excav. & Protectio1 6.000 CY 55 330.000
Tunnel Excav. & SuoDorts 23 000 CY 323 7.429.000
Tunnel Cone. & Reinf.Stee 2.300 CY 420 966.000
GroutinR Contact & Pressm ·e 3 400 CF 58 197.200
Round.-Off (22,200)
I
'
I
HaCF CSE 623 IJ.801
-.,
TOTALS
21,600,000
8,900,000
~.
·'
14879-001
JOB NO.
NOV. 1981
DATE
SHEET 5 OF
REMARKS
16
:.-.---
\ -. :--""!· ;,. , .I I -: 'l
ESTIMATE SUMMARY
HAJ/APD 14879-001
PREPARED BY JOB NO.
MF NOV. 1981
CHECKED BY DATE
CONCEPTUAL CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT SHEET 6 OF 16
TYPE OF ESTIMATE
ALASKA POWER AUTHORITY
ALTERNATIVE D PREPARED FOR
NO. DESCRIPTION QUANTITY UNIT UNIT AMOUNT TOTALS REMARKS COSTS
Access Tunnel at Mile 3. 5 No.1
Portal Excav & Protection 6.000 CY 53 318.000
Tunnel Excav & Supports 68,000 CY 297 20,196,000
Tunnel Cone & Reinf Steel 500 CY 430 215,000
Grouting-Contact & Pressure 1,125 CF 58 65,250
Round-Off 5,750
20,800,000
Access Tunnel at Mile 7. 5 No.2
Portal Excav & Protection 6.000 CY 54 324,000
Tunnel Excav & Supports 45,000 CY 298 13,410,000
Tunnel Cone & Reinf Steel '1.600 CY 420 672,000
Groutin2-Contact & Pressure 2 300 CF 58 133,400
Round-Off (39.400)
14,500,000
Power Tunnel
Excavation & Suooorts 67.000 LF 7.698 515.766,000
Concrete 514 000 CY 334 171,676,000
Grouting-Contact & Pressure 464,000 CF 54 25,056,000
Round-Off 2,000
712,500,000
H&CF CSE 523 (3-80)
r-
HAJ/APD
PREPARED BY
MF
CHECKED BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTERNATIVE D
NO. DESCRIPTION
Sur~e r.luam~P-1" -Unner
Rvt>.au.afoinn ~ Sunnnrt-A
Conl:'.rP-I'P-& RPinf .StP-el·
EartJ>unrlra ~ Fenrina
Round-Off
PenAI"nrlr-Tnt>1in .. t1 So ... l"inn
F.xr . .RvAt-inn I. "'· ·t-A
Concrete & Rein£: Steel
Groutin2 Contact & Pres
Round-Off
i
I
I Penstock-Horizontal Sectio
I
Excavation & Sunnorts
Concrete S Reinf Steel
_Grout-ina -C'.nnt-::u~t
Round-Off
HIICF CSE 623 3-801
-.r-n ~-' \1 I ',
ESTIMATE SUMMARY
CHAKA~A HYDROELECTRIC PROJECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT AMOUNT COSTS
3'l.500 r.Y 200 7,100.000
6.100 r.Y 880 5,368,000
15.000 C'.V 27 405,000
27.000
23.400 CY 271 6,341,400
10,500 CY 837 8,'788,500
sure s.ooo CF 52 260,0uu
10 2 100
n & Elbow
14.000 CY 310 4 .340~00
6.000 CY 365 2,190.000
3.000 CF so 150.000
20.000
___..., -J
14879-001
JOB NO.
NOV. 1981
DATE
SHEET J OF 16
TOTALS ~EMARKS
Heliport, Storage, Work Area
12,900,000
15-;4U"O , OUO
6,700,000
-'---'"" ! ern -j J
HAJ/APD tlJ ESTIMATE SUMMARY 14879-001
I'AEPAAED BY JOB NO.
MF NOV. 1982
CHECKED BY DATE
CHAKACHAHNA HYDROELECTRIC PROJECT
r.nNCEElliAI, PROJECT SHEET 8 OF 16
TYPE OF ESTIMATE
ALTERNATIVE D ALASKA fOWER AUTHORITY
PREPARED FOR
NO. DESCRIPTION QUANTITY UNIT UNIT AMOUNT COSTS TOTALS REMARKS
P""nal"n,.lr-t.lv,. Rr.an,.h~g to V~ II ve r.h .., ... har
Excavation & Supports 10 .ooo CY 432 4,320,000
Concrete & Reinf. Steel 7.200 CY 608 4,377,600
Steel Liner 650 TON 5,000 3,250,000
Grout inK-Contact 3,000 CY so 150,000
Round-Off 2,400
12,100 000
Penstock ·Between Valve Chan ber & Powerhouf e
Excavation & Supports 1 000 CY 440 440.000
Concrete & Backfill 600 CY 550 330.000
Round-Off 30.000
800,000
Draft Tube Tunnels
Rock Bolts & Grout 19 000 LF 27 513 .ooo
Concrete & Reinf. Steel 3.300 CY 425 1,402,500
Round-Off (15,500)
1,900,000
SurRe Chamber -Tailrace
Excavation & Suooorts 5 000 CY 480 2 400 000
ii!ICF CSE 523 IJ.801
.-..-, -I .!
HAJ/APD
IEPARED BY
fECKED lilY
CONCEPTUAl.
rPE OF ESTIMATE
ALTERNATIVE D
NO. DESCRIPTION
Tailrace Tunnel & StructurEs
Cofferdam & Dewaterimz
Portal Excav & Protecticn
Concrete & Reinf Steel
UallrwJtv Bride
St"nnlnoA & Hoists
Tunnel Exc.av. & Sunoorts
P1n~ .... _ ...... .,.tion
Rmm.d-Off
Tailrace r.lumnP 1
r.h ......... 1 Excavation
River Tr11inina Works
River Bed Deepening
Hech & E1ec.
-,~ . I ) ~' l, I'!:
ESTIMATE SUMMARY
CHAKACHAMNA HYDROEI.ECTRIC PROTECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT AMOUNT COSTS
LS 2.000J_OOO
2,000 CY 65 130,000
1,200 CY 600 720.000
LS 65,000
81 TON 8,500 688,500
25,000 CY 260 6,500,000
4,000 CY so 200,000
(3,500)
100,000 CY 9
50,000 CY 10
IS
TOTAL RESERVOIR, DAM AND WJ TERWAYS
ICF CSE 523 13~01
14879-001
JOB NO.
NOV. 1981
DATE
SHEET 9 OF 16
TOTALS REMARKS
10,300,000
900,000
500,000
5,700,000
871,600,000
.--
HAJ/APD
PREPARED BY
MF
CHECKED BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTEIRNATIVE D
NO. DESCRIPTION
Turbines & Generators
Turbines
Generators
Round-Off
Accessorv Electrical Eouior M!nt
Eauioment -
Misc. Power Plant Eouioment
Crane Brid2e
Other Power Plant Eouio.
Switchvard Structures
Earthworks
Concrete & Reinf Steel
Struc. Steel & Misc.Meta s
Round-Off
i6CF CSE 623 IJ..80I
,~,
,, I I
ESTIMATE SUMMARY
CHAKACUAMNA HYDROEI.ECTRIC PROJECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT AMOUNT COSTS
4 EA 7,970.00 31.880 ,ooc
4 EA 5,660,00 22,640,00(
t20 .00(
LS
1 EA 900 ,00(
LS 6 .ooo.ooc
15.000 CY 25 375,001:
3,800 CY 640 2 '432 ,ooc
225 TON 3,500 787,50(
5 .50(
14879-001
JOB NO.
NOV. 1981
DATE
SHEET 10 OF 16
TOTALS REMARKS
300 MW
)
54,500,000
9,000,000
b,~uu,uuu
3,600,00f
·-
UAJ/APD
PREPARED BY
CHECKED BY
CONCEPTUAL
TYPE OfF ESTIMATE
_ __,
I
ALTERNATIVE D
NO. DESCRIPTION
Swit:rhv~trd Eauipment
Tr.sanafnrmerA 10.5 MVA
Unit: & l,tne Breakers
Swi t.rheA & l.t ti!htn .Arrest•
230 KV C.stbleA
Controls & Metr'R Eouio.
Rnnnti Off
C'.nmm Suov C.nnt:rol Eauin.
H&CF CSE 523 IUOI
rs
ESTIMATE SUMMARY
CIUUtACHAMNA HYDROELECTRIC PROJECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT AMOUNT COSTS
5 EA [l.OlOPO-( 5,050,000
7 EA 1R0,00f 1,260,000
30 EA 33,00( 990,000
18,000 LF 12( 2,160,000
LS 2,630,000
10,000
LS
-. .-, :-lJ:
I
14879-001
JOB NO.
NOV. 1981
DATE
SHEET 11 OF 16
TOTALS REMARKS
12,100,000
1,600,000
-' '
,~ --
"
ESTIMATE SUMMARY
HAJ[APD 14879-001
~REPARED BY JOB NO.
NOV. 1981
CHECKED BY DATE
CONCEPTUAL CHAKACHAMNA HYDROELECTRIC PROJECT
12 16 PROJECT SHEET OF
rYI'E OF ESTIMATE
ALASKA PQWER AUTHORITY
ALTERNATIVE D PREPARED FOR
NO. DESCRIPTION QUANTITY UNIT UNIT AMOUNT TOTALS REMARKS COSTS
~SPORTATION ~ACILITIES
Port Facilities
Causeway 19 .600 CY 80 1 568 000
Trestle Piles so TON 11_._300 565.000 L = 150 LF. 012". t = ~II
Trestle Struct. Steel 110 TON 3.500 385.000
Trestle Reinf. Cone. 150 CY 700 105.000
Facilities -Allowance LS 2.000.000
Round-Off (23.000)
4,600,000
Airport
Earthwork 54.500 CY 16 872,000
Culverts 1,000 LF 65 65,000
Subbase & Base 55 000 CY 14 770 000
Building -Allowance LS 300,000
Round-Off (7 ,000)
2,000,000
81CF CSE 523 (3-801
-
HAJ/APD
I"REPARED BY
MF
CHECKED BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTERNATIVE D
NO. DESCRIPTION
Al"l!@AA & ConAtrul!tion Roads
I Mil@_ 0+00 to 1~0
Eart-hwnrlr
Culv@rtA
RritlaPA
Subbaae & Baae
n, .. ,..,f Da.fl
RPnAir F.viAtinll Road
~nnw Jf'o~>nt'o~>a
Round-Off
Milo~> 1~0 t'n 1'i+OO
Ji'arrhunrlra
Culverts
Subbaae & Baae
Guard Rail
Renair Exiatinll Road
Snow Fences
Round-Off
Mi 1 e 1'i+OO to 1Q+OO
Earthwork
Culverts
Bridal>
C:: .hh,.cu> & RaAP
Guard Rail
Snow Fen,.~>a
Round-Off
IS.CF CSE 623 IJ.80I
..,....-ro, ": c
---,
' !
~ ,J I , ,
ESTIMATE SUMMARY
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT AMOUNT COSTS .
175 000 CY 6.60 1.155,000
1 500 LF 65 97,500
1,400 SF 150 210,000
85,400 CY 15 1,281,000
1.200 LF 25 30.000
95,000 LF 10 950,000
5,000 LF 35 175,000
1.500
1.465 .ooo CY 6.60 9.669,000
3,600 LF 80 288,000
165,000 C.Y 15 2,475,000
13,000 LF 25 325,000
16,000 LF 10 160,000
1,000 LF 35 35,000
48.000
445,000 CY 8.30 3,693,500
1,000 LF 80 80,000
9,000 SF 150 1,350,000
38,000 C.Y 15 570,000
10,000 LF '),7 270,000
2,000 LF 35 70,000
(33 ,500)
......---,,
TOTALS
3,900,000
13,000,000
6,000__1000
-,
14879-001
JOB NO.
NOV. 1981
DATE
SHEET 13 OF 16
REMARKS
48"~ CMP
48"~ CMP
____...,
)
~ I
ESTIMATE SUMMARY
HAJ/APD 14879-001
ftAEPAAED BY JOB NO.
MF NOV. 1981
CHECKED IIY DATE
CONCEPTUAL CUAKACHAMNA HYDROELECTRIC PROJECT
PROJECT SHEET 14 OF 16
TYI"E OF ESTIMATE
ALASKA POWER AUTHORITY
ALTERNATIVE D PREPARED FOR
NO. DESCRIPTION QUANTITY UNIT UNIT AMOUNT COSTS TOTALS REMARKS
WAlkwav To Gate Shaft
Earthwork 1,200 CY 20 24,000
Guard Rail 1,000 LF 25 25,000
Bridae 200 SF 150 30,000
RiPrap 100 CY 35 3,500
Rnnnd-Off TT.~
100,000
Ac£!e&s Road to Tailrace T nnel
F.&rthwork 56,000 CY 8 448,000
r.nlverts 100 LF 80 8,000 48''¢1 (.;Mf'
Subbase & ]3ase 2,500 CY 20 50,000
Guard Rail 600 LF 25 15,000
Round Off (21 2000)
500,000
H!rCF CSE 523 13-801 ___ I
' ' d
ESTIMATE SUMMARY
HAJ/APD 14879-001
P'AEPAFIED BY JOB NO.
Nov. 1981
CHECKED BY DATE
CONCEPTUAL
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT SHEET 15 OF 16
TYPE OF ESTtMATE
ALASKA POWER AUTHORITY
ALTERNATIVE D PREPARED FOR
NO. DESCRIPTION QUANTITY UNIT UNIT AMOUNT TOTALS COSTS REMARKS
Access Road to Downstream P1 ~er Tunnel
Earthwork 215 000 CY 9.80 2.107 000
Culverts 800 LF 80 64.000 48 11 ,S CMP
Brid2e 3,000 SF 150 450.000
Subbase & Base 10,000 CY 21 210.000
Guardrail 9,000 LF 32 288.000
Snowsbed & Slide Fall 1,000 LF 800 800.000
Round-Off (19,000)
3,900,000
Temoorarv Construction Roads
Earthwork 61,000 CY 6 366,000
Culverts 600 LF 80 48,000
Brid2e 3,000 SF 150 450,000
Guardrail 2,000 LF 25 50,000
Round-Off (14.000)
900,000
Road Maintenance
SuDJDer Season 36 MO 120,000 4,320,000
Winter Season 24 MO 480,000 11,520,000
Round-Off (40.000)
15,800,000
TOTAl Af'('Ji'~~ ~ ('()N~'l'RTT(''f'T()N J loAns 44,100,000
HIIICF CSE 523 (3-801
-
HAJ/APD
PREPARED BY
MF
CHECKED BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTERNATIVE D
NO. DESCRIPTION
Transmission Line
Clear & Grub
Tr811Amission Line
Submarine Cable
Round-Off
TOTAL SPECIFIC CONSTRUCTION C OST
AT JANUARY 1982 PRICE LEVELS
H6CF CSE 523 13-801
:oor--'"! -1 J
ESTIMATE SUMMARY
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT AMOUNT COSTS
70 MI ~25.000 15.750 .ooo
70 MI t344 ooo 24 080 000
21 MI ~92,000 16,632,000
38,000
-
14897-001
JOB NO.
NOV. 1981
DATE
SHEET 16 OF 16
TOTALS REMARKS
56,500,000
1,117,500.000
ALTERNATIVE E
ESTIMATED COST
r---
l
HA:J/APD
PREPARED BY
MF
CHECKED BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTERNATIVE E
NO. DESCRIPTION
POWER PLANT STRUCTURE & IMPR<
Valve Chamber
Excavation & Supports
Concrete & Reinf Steel
-c 'l ' ~,
\, i I.:,
ESTIMATE SUMMARY
CRAKACHAMNA HYDROELECTRIC PROJECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT .AMOUNT COSTS
VEMENTS
10,000 CY 275 2,750,000
6,520 CY 410 2.673.200
Struc. Steel & Misc.Meta s 52 TON 1.800 93,600
Round-Off (16,800)
Unclerground Powerhouse
Dewatering LS 4.100 .ooo
Excavation & Supports 58 900 CY 168 9,895,200
Drilling-Percus.& Rotary 12 700 LF 27 342,900
Concrete & Reinf.Steel 13 100 CY 630 8,253,000
Struc. Steel & Mise Metals 300 TON 5 300 1,590.000
Architectural LS 1,000,000
Round-Off 18,900
Bus Galleries BetweenPower
house & Transformer Vaults
Excavation & Supports 200 CY 825 165,000
Concrete 120 CY 290 34,800
Round Off 200
H&CF CSE 623 (3-80)
~,
14879-001
JOB NO.
NOV. 1982
DATE
SHEET 1 OF 20
TOTALS REMARKS
5 ,500_~000
Entire Underground Complex
2"-3"0
25,200,000
200.000
,.,..--,
'I , -rn ....----.,
l j r---, -
HAJ/ APD
PREPARED BY
~
ra.srJ
MF
CHECKED BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTERNATIVE E
NO. DESCRIPTION
Transformer Gallerv & Tunne tl.s
Excavation & Supports
Concrete & Reinf Steel
Struc Steel & Misc.Metals
Round Off
Valve Chamber & Transformer
Gallery-Access Tunnels
Excavation & Supports
Concrete
Round-Off
Powerhouse Access Tunnel
Portal Excav.& Protection
Portal Cone.& Reinf.Steel
Tunnel Excav.& Supports
Tunnel Concrete
Tunnel Misc. Metals
Subsurface Exploration
Mobilization
Exploratory Adit
Core drilling
Helicopter Service
Round-Off
H&CF CSE 623 (3-80)
ESTIMATE SUMMARY
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT AMOUNT COSTS
11,960 CY 290 3.468.400
830 CY 460 381.800
120 TON 3,800 456 .ooo.
(6 ,200)
1,500 CY 250 375.000
60 CY 290 17.400
7,600
So,OOO CY ~o-560 000
1,000 CY 570 570,000
24 ,00_0_ CY 300 7.200,000
900 CY 290 261,000
30 TON 11,000 330,000
LS 1,500,000
1,000 LF 1,800 1,800,000
5,000 LF 140 700,000
LS 600,000
(21.000)
-,
14879-001
JOB NO.
NOV. 1982
DATE
SHEET 2 OF 20
TOTALS REMARKS
4,300,000
400,000
13,500 ,OOQ_ ----
-.r=-:. ----~
ESTIMATE SUMMARY
HAJ/APD 14879-001
PREPARED BY JOB NO.
MF NOV. 1982
CHECKED BY DATE
CONCEPTIJAL CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT SHEET 3 OF 20
TYPE OF ESTIMATE
ALASKA POWER AUTHORITY
ALTERNATIVE E PREPARED FOR
NO. DESCRIPTION QUANTITY UNIT UNIT AMOUNT TOTALS REMARKS COSTS
r.Rhl~ Wav
r.nnC'rPf"P F. RPinf ~f"PPl 1,000 r.v 700 700,000
Mi~ Metals1LC.ahle._5up. 26 TON 5,100 132,600
Pnrf" P~mPl!'l
Round-Off (32,600)
BOU,OUO
TOTAl. POtJF.R PLANT ~TRTJr.TITRF. TMPRCi\TEMF.N'"S 49,900,000
.
~&CF CSE 573 13-80)
HAJ/APD
PREPARED BY
MF
CHECKED BY
-' :1 rrn.
CONCEPTUAL
TYPE OF ESTIMATE
ALTERNATIVE E
NO. DESCRIPTION
RRstt:KvllfR nAM & WA'l'RRWAVS
n.,.,.,,..,ni.-
lJah>r T.PvPl R<>rnrtHnu
Tnt-a lro _St:ruc. t"UrP'
Sit-"' Rxnlnrs:at-inn
Mnhili7:s:at"inn
f'n'l"'<> nri 11 i'nu
Uolirnnt-.,..-C::o,.vir<>
'1'""""'1 Rxrs:au F. Sunnnrf"A
'l'unn<>l r.nnr F. RPinf St"<>P
TnLoo-'t't>n (l<'in'll Rnnn..l\
D1n 1.. n.,. ... ,.. .. ~ 'l'omn r'nn,..
ninino r .......
Rnnnrl-()ff
----. . .. --.... -.. -· -~ . -...
--·· .. .. .. --···· ....
-··· . --~J ~----------------------------
'· J --. ------
. ·-··--------. --· . ... _ .. j .
----------·-----------
H&CF CSE 623 (3-80)
r-r--,
l I
-)
ESTIMATE SUMMARY
14879-001
JOB NO.
NOV. lgfp
DATE
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT SHEET 4 OF 20
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT
COSTS AMOUNT TOTALS REMARKS
LS 100 000
I,S 150.000
5.000 LF 80 400.000
T.~ 150 000
10.000 cr· 510 5,100,000
90 r.v 350 31.500
T.S 2,500,000 L 26'
550 r.v 700 3R5 000
60 nAYS 10 000 600.000
(16,500)
9.300.000
J
I
i
' . -..... --l --·----· ... ·-----· -· . _.J .... -
l l -----..
I l --.. I· . . -----
,-
HAJ
PREPARED BY
MF
CHECKED BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTERNATIVE E
NO. DESCRIPTION
Intake Gate Shaft
Excavation & Sunnorts
Mass Surface Excavation
Concrete & Reinf. Steel
Mise. Metals Gates & Hois
Access Road
Round Off
.
H&CF CSE 523 (3-80)
~-~1 _......,
; .
ESTIMATE SUMMARY
CHAKACHANMA HYDROELECTRIC PROJECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT AMOUNT COSTS
360 LF 17 50( 6 300 000
50 000 CY 3( 1 500.000
5 200 CY 89( 4 628 000
220 TONS 12 20( 2 684 000
1. 25 MI o.ooo.o )Q 2.500.000
(12 000)
14879-001
JOB NO.
NOV. 1982
DATE
SHEET 5 OF 20
TOTALS REMARKS
17 600.000
r--"1--· ~
' 1 --,
l
ESTIMATE SUMMARY
RAJ 14879-001
PREPARED BY JOB NO.
MF NOV. 1982
CHECKED BY DATE
CHAKACHAMNA HYDROELECTRIC PROJECT
CONCEPTUAL PROJECT SHEET 6 OF 20
TYPE OF ESTIMATE
ALASKA POWER AUTHORITY
ALTERNATIVE E PREPARED FOR
NO. DESCRIPTION QUANTITY UNIT UNIT AMOUNT TOTALS COSTS REMARKS
Fish Passage Facilities
Approach Channel
Channel Excavation 1,040,000 CY 11.30 ll. 7 52.000
Slope Protection 90.000 CY 28.00 2 520.000
Round (zz ooo)
14,250 000
Upstream Portal
Excavation in Rock 64 500 CY 30.00 1.935.000
Rock Bolts -Ch LK Mesh LS 544 500
Dewatering During Construct LS 50 000
Fence 400 LF 45.00 18 000
Round 2 500
2 550 000
H&CF CSE 523 (3-80)
-.
HAJ
PREPARED BY
MF
CHECKED BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTE RNATIVE E
NO. DESCRIPTION
Upstream Fish Passage Facilit\
Excavation & Support
Concrete & Reinf. Steel
Misc. Metal, Gates & Crane
Electrical & Instrumentatior
Round Off
Downstream Fish Passage
Facility
Excavation & Support
Concrete & Reinf. Steel
Misc. Metal. Gates & Crane
Electrical & Instrumentatior
Round Off
Access Tunnel
Excavation & Support
Concrete & Reinf. Steel
Misc. Metal
Electrical -Lighting
Round Off
H&CF CSE 523 (3-80)
ESTIMATE SUMMARY
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT AMOUNT COSTS
16,550 CY 1 -"l 1)_, 2, 697,650 .
5.880 CY 759 4,462,920
LS 1,786,300
LS 200,000
(3' 130)
8,900 CY 191 1,699,900
2,600 CY 635 1,651,000
LS 2,283,000
LS 100,000
(3, 900)
122,500 CY 303 37,117,500
22,800 CY 573 13,064,400
LS 405,000
LS 231,000
(7, 900)
,_
TOTALS
9,150,000
5,730,000
50 810 000
_,
I
14879-001
JOB NO.
NOV. 1982
DATE
SHEET 7 OF 2Q
REMARKS
r--
'
ESTIMATE SUMMARY
HAJ 14879-001
PREPARED BY JOB NO.
MF NOV. 1982
CHECKED BY DATE
CONCEPTUAL
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT SHEET 8 OF 20
TYPE OF ESTIMATE
ALASKA POWER AUTHORITY
ALTERNATIVE E PREPARED FOR
NO. DESCRIPTION QUANTITY UNIT UNIT AMOUNT TOTALS REMARKS COSTS
Fish Passage Facilities
Excavation & Support 6 600 CY 53 349.800
Concrete & Reinf Steel 740 CY 778 575.720
Misc. Metal Gate etc. LS 434 650
Round Off (l7o)
1 360 000
Chakachatna River
Flow Regulation
River Bed Deepening 10.000 CY 9.5( 95.000
Rip-Rap 1 000 CY 35. oc 35.000
130,000
Access Road LS 300.000
Access Tunnel to Fish
Passage Facilities
Portals Excavation 700 CY 93 65.100
Tunnel Excavation & Sunnort 3 350 CY 314 ___ _l,Q?1 ~Q.QO
Round Off 3 .ooo_
1 120_.000
Total Fish Facilities 85 400 000
H&CF CSE 523 (3-80)
_,
I -~. ~
'I ·-'I I I, I
RAJ
PREPARED BY
MF
CHECKED BY
CONCEPTUAL
TYPE OF ESPMATE
ALTERNATIVE E
NO. DESCRIPTION
Chakachata Dike and Spillway
Excavation & Slooe Protect'
Concrete & Reinf. Steel
Timber Bridge
Dike
Round Off
on
Access Tunnel at Surge Chamber
Portal Excavation & Protect ion
Tunnel Excavation & Suooorts
Tunnel Concrete & Reinf. St eel
Grouting Contact & Pressure
Watertight Bulkhead & Frame
Round Off
~ H&CF CSE 52.:; (3-80)
---: ! ~I
'·'-J "'
,.-....-,
1
ESTIMATE SUMMARY
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT AMOUNT COSTS
280 000 CY 29.50 8 260 000
1 100 CY 325 357 500
2 200 SF 150 330 000
250 000 CY 0.75 187 500
( 35 '000)
6.000 CY 35 210.000
14 000 CY 317 4,438,000
1 700 CY 420 714.000
2,260 CF 58 131.080
27 TON 13 800 372.600
34 320
-
14879-001
JOB NO.
NOV. 1982
DATE
SHEET 9 OF 20
TOTALS REMARKS
9,100,000
5,900,000
r--•
I. rr---:.· .. ~
HAJ/APD
PREPARED BY
MF
CHECKED BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTERNATIVE E
NO. DESCRIPTION
Power Tunnel TBM
Excavation & Supports
Concrete
Grouting
Round Off
H&CF CSE 523 (3-80)
,.....-,
' ;
ESTIMATE SUMMARY
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT AMOUNT COSTS
53,400 LF 6 110 326,274,000
267 000 CY 341 91 047 000
540 000 CF 56. 4C 30 456 000
23 000
.
--
TOTALS
447 800 000
~
'
14879-001
JOB NO.
NOV. 1982
DATE
SHEET 10 OF 20
REMARKS
-· -
HAJ/APD
PREPARED BY
MF
CHECKED BY
CONCEPTUAL
TYPE OF ESnMATE
ALTERNATIVE E
-( ]
NO. DESCRIPTION
Surge Chamber -Uooer
Excavation & Suooorts
Concrete & Reinf Steel
Earthwork & Fencing:
Round Off
Penstock -Horizontal
Section
Excavation & Supports
Concrete & Reinf. Steel
Grouting -Contact
Round Off
H&CF CSE 523 (3-80)
~ ( ' ;
____,
. I
ESTIMATE SUMMARY
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT AMOUNT COSTS
27 100 CY 353 9 566 300
10.000 CY 893 8 930 000
15 000 CY 27 405.000
(l 300)
12,000 CY 334 4 008,000
5 100 CY 365 1 861 500
2,600 GF 50 130.000
500
14879-001
JOB NO.
NOV. 1982
DATE
SHEET ll OF 20
TOTALS REMARKS
18.900 000
6,000,000
---:1 -
HAJ/APD
PREPARED BY
MF
CHECKED BY
CONCEPTUAl.
TYPE OF ESTIMATE
ALTERNATIVE E
NO. DESCRIPTION
Pe.n.at-nrlr-Wvi=! 1\T!>nrho:>a t-n v..,
Excavation & Suooorts
Concrete & Reinf. Steel
Steel Liner
Grouting-Contact
Round-Off
Penstock ·Between Valve Char
Excavation & Supports
I Concrete & Backfill
Round-Off
Draft Tube Tunnels
Rock Bolts & Grout
Concrete & Reinf. Steel
Round-Off
Surge Chamber -Tailrace
Excavation & Sunnorts
I&CF CSE 523 (3-601
,.....--,,
ESTIMATE SUMMARY
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT AMOUNT COSTS
ilve Chamber
9 000 CY 480 4 320.000
6 100 CY 608 3.708.800
700 TON 5 000 3.500 000
7_,000 CY 56 392,000
(20 ,800)
her & Powerhow e
850 CY 440 374.000
500 CY 550 275.000
(49 000)
15.000 LF 29 435,000
2 975 CY 425 1,264,375
625
5 000 CY 480
TOTALS
l"l,900,000
600,000
1,700,000
2,400,000
-J
14879-001
JOB NO.
NOV. 1982
DATE
SHEET 12 OF 20
REMARKS
---··-
-r-1
" J ---. -.
HAJ/APD
ESTIMATE SUMMARY 14879-001
PREPARED BY JOB NO.
MF NOV. 1982
CHECKED BY DATE
CONCEPTUAl.
CHAKACHAMNA HYDROELECTRIC PRO.JECT
PROJECT SHEET 13 OF 20
TYPE OF ESTIMATE
ALASKA POWER AUTHORITY
ALTERNATIVE E PREPARED FOR
NO. DESCRIPTION QUANTITY UNIT UNIT AMOUNT TOTALS REMARKS COSTS
Tailrace Tunnel & Structures
C:nfferdRm & DP.wRterinl! LS 2.000.000
Portal Exeav & Prntecticn 2.000 CY 65 130,000
Concrete & Reinf Steel 1.200 CY 600 720 .ooo
Walkwav Brid!!e LS 65,000
StnnlntrA & Hoists 81 TON 8,500 688,500
Tt~nnPl ExrRv F. ~nnnnrtR 20 000 CY 290 5.800.000
P1ua """'""'•'l.tion 4 000 CY 50 200,000
Round-Off (3 .500)
9,600,000
TailraeP. f'h<>nn~l
C:hannel Exe:tv:ttlon 80.000 CY 9 720.000
(20.000)
700,000
River Traininrz Works
River Bed Deepening 50,000 CY 10 500,000
Mech & Elec. LS 6 '100~000
TOTAL RESERVOIR. DAM AND WJ TERWAYS f>J3 6nn nn0
--
i&CF CSE 623 (3-80)
--r-)
; I . -i rrr ~' r---"1
.,}
HAJ/APD
PREPARED BY
MF
CHECKED BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTERNATIVE E
NO. DESCRIPTION
Turbines & Generators
Turbines
Generators
Round Off
Accessorv Electrical Eouiot ent
Eouioment
Misc. Power Plant Eouiomen
Crane Bridge
Other Power Plant Eouio.
Switchvard Structures
Earthworks
Concrete & Reinf. Steel
Struc. Steel & Misc.Meta s
Round-Off
H&CF CSE 523 13-601
ESTIMATE SUMMARY
CHAKACHAMNA HYDROELECTRIC PROJECT
QUANTITY
4
4
1
15.000
3,800
225
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
UNIT UNIT AMOUNT COSTS
EA 8,480,00( 33,920,000
EA 6,00(\00( 24,.000,000
(20 ,000)
LS
EA 930,000
LS 6,370 000
CY 25 375,000
CY 640 2 432.000
TON 3,500 787.500
5.500
-
14879-001
JOB NO.
NOV. 1982
DATE
SHEET 14 OF 20
TOTALS REMARKS
330 MW
5/,900,000
Y,SOO,OOU
7,300,000
3 600.000
--l
fiAJ/APD
PREPARED BY
CHECKED BY
CONCEPTUAL
TYPIE OF ESTIMATE
ALTERNATIVE E
NO. DESCRIPTION
Switr.hvard Eauipment
'T'.-<mRfnrmPrR 105 MVA
llnit & Line Breakers
Switl'heR F. T.f ohtn. Arrest<
210 KV Cables
f:nntrols & Metr'2 Eauin.
Rnunrl Off
r:nmmunicatinn and Sunv
Control Eauin
H&CF CSE 623 13-80)
~.
~ :
~
'J ll .. : I -' l
ESTIMATE SUMMARY
CIUUKACHAMNA HYDROELECTRIC PROJECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT
COSTS AMOUNT
5 EA 1,030,00 5,150,000
7 EA 185,00 1,295,000
rs 30 EA 34,00) 1,020,000
18,000 LF 130 2,340,000
LS 2,700,000
(5 .000)
LS
14879-001
JOB NO.
NOV. 1982
DATE
SHEET 15 OF 20
TOTALS REMARKS
-12,500,000
1,600,000
---··
llJ HAJLAPD
PREPARED BY
CHECKED BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTERNATIVE E
NO. DESCRIPTION
~SPORTATION FACILITI~
Port Facilities
Causeway
Trestle Piles
Trestle Struct. Steel
Trestle Reinf. Cone.
Facilities -Allowance
Round-Off
Airport
Earthwork
Culverts
Subbase & Base
Building -Allowance
Round-Off
HS.CF CSE 623 IHIO)
ESTIMATE SUMMARY
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT AMOUNT COSTS
19,600 CY 80 1 ')08 000
50 TON 11.300 565 000
110 TON 3 500 385 000
150 CY 700 105 .000
LS 2 000 000
(23 000)
54 1500 CY 16 872,000
1.000 LF 65 65,000
_55 ()()() CY 14 770,000
LS 300,000
(7_,_000)
-
TOTALS
4 nOO.OO
2_,000~000
14879-001
JOB NO.
NOV, 1982
DATE
SHEET 16 OF
REMARKS
L = 150 LF, i!S12", t = k" ?
,..._
!
20
HAJ/APD
PREPARED BY
MF
CHECKED BY
CONCEPTUAL
TYPE OF ESTIMATE
-( -f .I !"""-~" /,I : ;,
ALTERNATIVE E
NO. DESCRIPTION
Af"'rPAQ F. C:nnRtrnrtion Road"
Mil .. fH.OO t-n lR+OO
RArt-hwork
C:nlvo:>rt-R
RricllleR
~nhhRRP F. BRRR
n ...... .t R<>i1
RPn<llir RviRt-ino RnRrl
~nnt.r Fo:>nr"Pa
Round-Off
Milo lA-1-nO t-n 1'\-1-00
l<'art-ht.Jnrlra
Culverts
Subbase & Base
r.na.rd Rail
RPnsdr Rxi Rtinu RoRd
Snow Fences
Round-Off
Milo:> 1'\-1-00 t-n 1Q-I-OO
RArthwork
r.uluPrt-!:1
Hri<loP
~nhhR.!'Ie & R<llaP
nnArn R:~il
Snow F .. nrPa
»no.nrl. -nf f
i&CF CSE 523 (3-80)
-~I
ESTIMATE SUMMARY 14879-001
JOB NO.
NOV 1 QR?
DATE
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT SHEET 17 OF 20
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT AMOUNT TOTALS REMARKS COSTS
175,000 CY 6 60 1,155.000
1,500 U<' 65 97 500 36 11 0 CMP
1.400 Sli' 150 210 000
85,400 CY 15 1 281 000
1 200 LF 25 :m.noo
95,000 LF 10 950 000
5.000 LF 35 175 000
1 500
1.Q00.0()()
1,465,000 CY 6.60 9 669 000
3,600 LF 80 288 000 48 11 (6 CMP
165,000 CY 15 2 475.000
13,000 LF 25 325 000
16,000 LF 10 160 000
1,000 LF 35 35_.000
48,000
13 000 000
445 000 CY 8.30 3 693 500
1,000 LF 80 80,000 48'~ CMP
9,000 SF 150 1 350_,000
38,000 CY 15 570 000.
10,000 LF 27 270 000
2,000 LF 35 70,000
. (33 500)
6.000 non
--
--l
HAJ/APD il ESTIMATE SUMMARY
14879-001
PREPARED BY JOB NO.
MF NOV ]qR?
CHECKED BY DATE
CONCEPTUAL CHAKACHAMNA HYDROELECTRIC PROJECT 18 OF 20 PROJECT SHEET
TYPE OF ESTIMATE
ALASKA POWER AUTHORITY
ALTERNATIVE E PREPARED FOR
NO. DESCRIPTION QUANTITY UNIT UNIT AMOUNT COSTS TOTALS REMARKS
Walkwav To Gate Shaft
Earthwork 1,200 CY 20 24 000
Guard Rail 1.000 LF 25 25 000
BridRe 200 SF, 150 30 000
Rio rap 100 CY 35 3.500
Round-Off 17.500
100,000
Access Road to MacArthur Valley
Earthwork 545 000 CY 7 3,815,000
Culverts 2,400 LF 75 180.000 36"~ and 48"95 CMP
Brid2e Improvements 9,000 SF 70 630,000
Subbase & Base 105,000 CY 15 1.575.000
Guard Rail 6 000 LF 25 150,000
Snow Fences 3 000 LF 35 105.000
Round-Off 45,000
6,500,000
AcceRR Road to Tailrace unnel
F.arthwork 56,000 CY 8 448.000
Culverts 100 LF 80 8,000 48"95 CMP
SnhhRR~ &. BaRe 2,500 CY 20 50,000
Gn;~ rd Ra i1 600 LF 25 15,000
Round-Off (21,000)
500,000
~IIICF CSIE 523 (3-801
H.hJ /MD
'REPAREO BY
MF
:HECKED BY
,-,
I,
ESTIMATE SUMMARY
CHAKACHAMNA HYDROELECTRIC PROJECT
CONCEPTUAL PROJECT
YPE OF ESTIMATE
ALASKA POWER AUTHORITY
ALTERNATIVE E PREPARED FOR
NO. DESCRIPTION QUANTITY UNIT UNIT
COSTS AMOUNT
Access Road to Downstream P ~er -Tunnel
Earthwork 215,000 . C'{ 9.80 2,107,000
Culverts 800 LF 80 64,000
BridRe 3,000 SF 150 450,000
Subbase & Base 10,000 CY 21 210,000
Guardrail 9,000 LF 32 288,000
Snowshed & Slide Fall 1,000 LF 800 tiUU,UOU
Round-Off -~19 !000)
-
Temoorarv Construction Roads
Earthwork 61,000 CY 6 366,000
Culverts 600 LF 80 48 000
Brid~e 3,000 SF DU 450,000
Guardrail 2,000 LF 25 50,000
Round Off (14.000)
Road Maintenance
Surmner Season 45 MO 1150 ,uuu 6,750,000
Winter Season 30 MO 600,1IUD 18,000,000
Round-Off 50,000
ITOTAT. Ar.rJO:ss IV r.oNSTRUCTION R01 DS
CF CSE 523 13-80)
~:
TOTALS
3 ,9DIT,UUU
900,000
24,800,000
59,600,000
-J
. 48''~ CMP
48"~ CMP
-
14879-001
JOB NO.
NOV. 1982
DATE
SHEET 19 OF 20
REMARKS
HAJ/APD
PREPARED BY
MF
CHECKED BY
CONCEPTUAL
TYPE OF ESTIMATE
ALTERNATIVE E
-l'
NO., DESCRIPTION
Transmission Line
Clear & Grub
TranBil!isaion Line
Submarine Cable
Round-Off
TOTAL SPECIFIC CONSTRUCTION
COST AT JANUARY 1982 PRICE
LEVELS
I&CF CSE 623 (3-80)
ESTIMATE SUMMARY
.~
)
CHAKACHAMNA HYDROELECTRIC PROJECT
PROJECT
ALASKA POWER AUTHORITY
PREPARED FOR
QUANTITY UNIT UNIT
COSTS AMOUNT
82 MI 225,000 18,450,000
82 MI 343,000 28,126,000
21 MI 792,000 16,632,000
(8~000)
14897-001
JOB NO.
DATE
SHEET 20 OF 20.
TOTALS REMARKS
()] ,:wu ,uuu
905,300,000
ARLIS
Alaska Resources
Library & Information Services
PUlchorage,Alaska