Loading...
HomeMy WebLinkAboutAPA614.rr·. h:., ' . • -11 ' : ' ~·r . ,- , .,.~, ( ll ll. ~ ~ .( ~ .. 'L '{, L 'L l ·l c. ·l 1., l L L .. _ L ~ I , . I I ~ I I J Prepared by: 1 j~IR ' .______. I f/;r/2 Z.ft -E-rJ 11-J~ c cD Rev~---t ~ 1-fe-rJ/2.1 C t+W fft\ffZJ.t.;.EB'ASCo Susitna Joiilt Ventwe Document Number Pfease Return To DOCUMENT CONTROL SUSITNA HYDROELECTRIC PROJECT DRAFT SUPPLEMENT TO 1HE FEASIBILITY REPORT fEBRUARY ]983 I .. _j -----AL,l\SKA POWER AUTHOR lTY __ ___. I I. APA 614 Supplement to the Feasibility Report Prepared by Acres Draft This copy is incomplete. The beginning of the table of contents is missing. Section 10.6(c) is blank (perhaps intentionally). The document ends with Figure 10.6 although the table of contents lists chapter 11, chapter 12, and volume 2 (plates). r.-1·.· '· ! ' 'I f l ·;-·r· l.," ., Iil I J[ I l 1 L ' •• TABLE OF CONTENTS (Cont'd) 4.9 -Relationship to Current Lane Stewardship, Uses and Pl ans •• a .................. ,. ......... ; •••••••• 4.10 -Se 1 ect ed Access Pl an ................................ . 4.11 -Selected Pccess Plan ................................ . 5 -REFINEMENT OF SUSITNA DEVELOPMENT ··················~······· 5.1 -1982 Geotechnical Design OJnsiderat ~ Jrts .............. . 5.2-1982 Hydrologic Consideration ......................... . 5. 3 -Selection of Project Flows ............................ . 5. 4 -Main Da11 Alternatives -~.'1tana •••••• ., •• fl .............. . 5. 5 -Refinement to General Arrangenent .................... . 6 -TRANSMISSION FACILITIES ··2·······~························~ 6 .. 1 -Introduction ......................................... . 6.2-1982 Design Considerations ••••••••••••••••••••••••••. 6. 3 -Transmissio .. Lfne Route ••••••••••••••••••••.••••.•••.• 6. 4 -Reii s ion to Selected Transni ss ion Systen .............. . 7 • PKOJECT OPERATION 7.1 -Introduction 7~2 -Modification 7.3 -Revisions to • • • • • • 0 • • ~ • • • • ~ • • • • • • • • • • • • • • • • • • • • • • • • • • to Flow Reg i1·ne ............................. . Project ~er at ion Pl an ••..• ·• •••••••.•••• 8 ~ EST IMATES OF COST •••• ~ •••• ~ .. o ••• .flo ........ , .................... . 8.1 .. Introduction ..................... " •••.•••••.•••••••••. 8. 2 -Revision to Project Cost Estimate ................... . 13. 3 -Mit i g at ion OJ st s •..........•. , .•..• ~ ................. . 8.4 .. Other lllsts ....•• , .• .,..e•••••···"····················· 8. 5 -Cash Flow and Manpower Loading Requirements eo ........ . 8.6 .. Contingency •• , ...... , ................................. . 9 -DEVELO~ ENT SCHEDULE ........................................ . 9.1 -Introduction ....................... · .................... . 9. 2 -Revised Watana Schedule .............................. . 9.3 -Revised Devil Can~'On Schedule •••••••••••••••••••••••• 10 -ECONOMIC, MARKETING, AND FINAM: IAL EVALUATION •••••••••• ae. 10 .. 1-Intl .. oductiC;l ·····················••n••············· 10. 2 -Cost of Power Projection ............................ . 10.3 -Implications of SB25 •• ( ............................... . 10.4-Capital Cost Escalation •••• a~~ ............... 8 .... .. 10.5 -Review of Risk Analysis .......................... H. 11 - R ES PONS E TO C G1M ENTS ..••••••••••••••••••..•• e ••••••••••••• 11.1 -Introduction ······•••L••···············•o••••······ 11.2 -Resource Agency Comments ........... a •••• " ••• 8 •••••••• 11.3 .. Public Cornnent ··········"'········"·······.,········· Page ..BtE OF CONTENTS -"':".'., 12 -CON:LUSIONS AND RECCMt1ENDATIONS ""~'". 12.1 -Conclusions " "II.~.. 12.2 -R~CI1I!l1endat ions e ".." "u 0 ..".." "".. VOLLME2 -PLATES iI1\ L'I, tft; t., '1 ~ff 'r J' r 'I ; III ,t ri~t...· r~i.·:~~i i ~~J'"j t •". '.f ' ,I ',I ~..,'.•.;-"Q . ",,;';c'~_,;",,,__~~,;;,,,._,~,-,,----.-...--~- This supplenent to the Feasibil ity Report has been prepCired by kres ,American Inco"'JX\rated (A:res)for the Al aska Power Authority (the Power Authority)under the tenns of Rev ision 4 to the Agreement,dated December 19,1979 s to conduct a feasibil ity study and preparatian of a 1 icense appl ication to the Federal .Energy Regul atory Commission (FERC)• The original reasibil ity study was undertaken in accordance with the Pl an of Study (POS)for the Susitna Hydroel ectric Praj ect,which was first issued to the Ptttharity in February,1980 and subsequently re- vised four times since the original issue to account for scope changes and publ ic~federal and state agency com~ents and concerns. A draft of the FERC 1 icense appl ic ation was ri 1 ed with FERC on rbvenber 15,1982.Similarly a draft of ExhibitE -EnvironmerV',al Studies for the FERC 1 icense was submitted to'the various State and Federal agencies for r~v iew and comment"C',mmentsreg ard ing thi s draft were received during the month of December and January with the final sub- mittal of the FERC 1 icense appl ication in February 1983 • The Fe as i bil ity Report was issued for pUblic rev iew and comment on MarCh 15,1982 (Acres 1982.a).SUbsequ~nt to that time ongoing\\()rk continued in the ar'eas of: hjd ro1a 9Y -environmental studies -survey and site facilities -geotechnical exploration -design develofJT1ent -transm ission line -cost estimates and schedul es -FERC licensing -marketing and financing As a result of this ongoing \\ark,changes,CilJditions and modifications have been male to the original Feasibil ity ~eport.This Supplemental Report is intended to provide an update of information through January 1983"A comprehensive env ironmental study has been submitted as Exhibit E to the .FERC 1 icensc.Since extensive ongoing studie.s con- tinue to be done in this area,no slJpplenent to Volune 2 -Environ- mental Studies of the original Feasibility Report has been prepared for thi $SUbmittal.Readers interested in the env ironmental stud ies to include environmental impact ..and recommended mitigation measures are requested to consult Exhibit E to the FERC 1icense. This report ;s intended a~a suppl ement to the March Feasibil ity Report and shoul d be used in reference to'that doc unent. 1.1 -General 1 -INTRODUCTION HII f I J!""',.. f I I -l ,1.. 1 1 11....I,, t .'[4' "J. -ItJ 1 t 1 (j ,f\J} .~ t. 1 , ;1 !';~~ 1, ':t -"'r,'"." ...1• Section 3 ..Scope of Work This section outl ines the scope of \It()rk undertaken in each of the tasks Section 4 ..Access Road s Section 4 is a detail ed discussion of the acces~)road al- ternative studies and the final access recommendation . Section 5 -Ref;nement of $us;tna Oevelopnent ' This section presents the refinement to the Susitna Devel ... opnent based on work carr;ed out from March to December, 1982 Task 72 ..Access Pl an Task 73 ""Hydrologic Studi~s Task.75 -Geotechnical Studies T('~sk 76 -DesignDev elopnent T~\sk.77 -Env ironnental Studies Task 78-Transmission . Task 79 -Construction Cost Estimates and Schedule Task 80 -Li censing Task 81 -Mar'-~et i ng &Fi nance Task 82 -Publ ic Participation Program These ongoing studies have resulted in some modifications to the design and developnent schemes for the Susitna Hydroel ectric Proj ect as set forth in the March Feas.ibility Report.Details of these changes are presented in the preceedinu section.The principal changes to the Feasibil ity ReJX)rt are in the are~:iof access ~env ironmental and trans- mission.In addition,changes have al so been mooe in the hj(irologic fi ow reg ime of the dans to minim;;re dOlNnstreCJl1 env ironnental impacts. These mod ifications have resulted in redesign of the intake structures which are presented in Vo 1 une 2 of thi s submittal" 1.3 ..Organization of the Supplemerr'e]Report The suppl anent to the Feas'ih i1 ity Report is presented in 12 sections. Section 1 -Introduction A bri ef summary of the proj ect background and a general in- troduction to the reJXlrt Section 2 -Summary This section provides a slJJ1mary of the results of Sections 4 thru 10 1.2 ~Objectives-Scope The objective of the \l«Jrk perfonned from March 15 through Dec ern ber 1982,was to continue ongoing stud ies and submit the draft FERC 1 icense appl ication.The work has been undertaken in a series of t~sks which are: l "-~ 1~'1 {;'l -.~ *~..,.:" .I -I l' ~t 1 ;1 'Ii HI t • ,ir Il',# : \1 I ,t (I ..~t{~ ~···i."•f i -,! Section 6 ..Transmission Faci1 ities Section 6 addresses the recommended transmission routing for the Susitna.Developnent Section 7 -Proj ect cperation Thi.s section pres\~nts the revised flow regim.e for the Susitna Develor:ment Section 8 -Estimates of Costs This section presents the revised project cost estimate which incorporates the changes in the design scheme Section 9 ..Developnerrc Schedul es Section 9 presents the rev ised proj ect schedul e to refl ect principally the changes in access routing Section 10-Economic,Marketing and Financial Eval uation This section presents the revised economic and financial evaluation for the Susitna Developnent Section 11-Response to Comments This section addresses comments and responses to various pub1 ic and private queries regarding this project Section 12-Concl usian and Recommendations This section presents the main concl usions of the feas- i b i1 ity study 1 ~'l.11 •-I 1 il.'n.r J ,I I .1,, I I l. 1! 1 'I 1 ."'"f ,;r; .',I 1 'i,] l~ ( '~ ..,...,~ t ••'"__j' -'"., I I . .'..f•..'.• I .I I ..I,• '.[I ...,,..,lIo'· 1\. I •~" (b)preparation of Y4 eports on 91"'0 undwater analyses,sed i'1ent ati on and post project esturine affects. (c)further ref;ne energy and minimun flow requi rements for dO\\11stream fisheries. (d)prepare groundwater report with groundwater contours of the stUdy 51 aughs.,gro undwater so urces and groundwater inflow rates" (f)continue reservoir and instream flow stud ies to enabl e the project impacts to be assessed and a mit ig at;on pl an to beadoptEld • 3.1 -Introduction The scope of\',Qrk undertaken from the.March 15,1982 submittal of the Susitna Hydroelectric Feasibil tty Report to present is set forth in Amendment No.4,dated September 27,1982~The principal technical tasks undertaken during thi s period incl uded: -Access Pl an -Hydrologic St ud ies -Geotechnical Explorations -Design Developnent -Env ironnental Stud ies -Transmission -Construction Co st Estimates &Schedul es -Licensing -Marketi.ng and Fi nance 1.2 -Access Plan The March 1982 Feasibil ity Report recommended an access pI an which,for reasons of project schedule,would necessitate the construction of a pioneer road prior to the F~C I icense being issued..Subsequent to the issuance of the Feasibility Report,this cOilcept was found unacceptable by the var;ous rev iewi n9 agenc ies. Consequently,this study involved the development of a new access criteria and the developnent of additional access alternatives within the three potential corridors detailed in 1981 studies.The objective was to del in~ate the most responsive pl an in each corrider and to subject these pl ans to a multi -disci pl inary assessment and campari son to ultimately arrive at the most acceptable route.Results of this study are presented ;n Secti on 4. 3.3 -Hydrology Studies Work performed under this subtask involved: (a)the continued collection of basel ine c1 irnatic,water qual ity,sed- iment,discharge,ice,thermal,groundwater,stage and snOW creep data • 3-OBJECTIVES ~'} L1 I ~1• l~'l J 2 1 ?•.''fl··•. ~.I, 4 U.. C Jl,., (j '. '1 I I, I. I 1 1, t. 1J If:• ,I', t· 'J"'" <t,~ /:-;~?' ....._1 Introduction_. . Work under this progrCJTl involved: -conducting a reconnaissance Level 1 survey along the proposed transmission corridor from Fairbanks to Healy,Willow to Anchorage,and Watana dansite to the Interti e -conduct a Reconnaissance Levell sUirvey at the "newll segment of the proposed access route on the north side of the Susitna Ri v er,from Dev i1 Can}')n to the Pal~ks Hi ghway ...conduct archaeological eval uationsl of areas to be impacted by geotechni cal testing •access roads •construction haul roads •intake structures' •transmission line routing • The principal objective of the environmental studies were to con- tinue coordina;:ion among env ironmental study subtasks and subcon- tractors,establish and maintain reporting schedules,continue i nformalagency contact,and pr fJare Exhibit E for the FERC license appl ication. (b)Cultural Resource Investisations 3.4 -Geotechnical Exploration To perfonn the following tasks for: •perfonn additional soil drill ing and testing in the Watana Rel ict Channel •prepare an anendment to the 1980-81 Geotechnical Report o develop the scope of a 1982 winter program and •prepare necessary'contracts to perform the work. (a) 3.5 ..Desi.g"Oevelo~ment Update The scope of this subtask involves the continued updating of various design aspects of the proj ect with particul ar attention directed to those design changes necessary to meet changing environmental criteria and improve appl ication.Particul ar areas tn be addressed are: 3.6 -Environmental Studies t '1 I 1, J I I 1 • I l' !i j '.~l ~1 ·t -~I "1 to ,~1 4 ·:1 • I I I t I~, I( ·L l 1'.. I I 1, 1 [ '" I • .1. 1 'It • -conduct Reconnaissance Level 2 survey on the Tsusena Creek "cat trail II from the Watana Camp area to the mouth of the Tsusena Creek '".. -prepare the cultural resource components of the FERC 1 icense. (c)LandOwnership and Acquisition To further define 1and oMlership and acquisition in connection with access road and transmission line corridor and ass;st in preparation of Exhibit G for the FERC 1 icense appl ication • Cd)Land Use Analysis -Mitigation of Aesthetic Impact To further assess aesthetic impacts and develop a draft pl ~J1 for- mitigation of impacts of the Projeet on the aesthetic resources of the Upper Susitna River Basin. (e)Recreation Plannin~ To develC'p specific proposed sites for recreation facil ities to incl ucle cost and schedul es for developnent of the facil ities. (f)Aquatic Impact Assessment. To analyze and interpret ava:n abl e basel ine knowl edge of the Susitna River aquatic system and exanine and present in model s and reJX)rts the impacts on fi sheryresources of hydroel ectric developnant in the Upper Susitna Basin.Work undertaken during this period incl uded: -coord ination with the Al aska Department of Fi sh and Game,Su Hydro Study Group on the fishery and aquatic habitat studies and other groups and agencies involved in assessing impacts on fishery. -assemble an information managenent program to collect and. compile avail able knowledge of the Susitna River aquatic system rel ating specifically to the exanination of proj ect impact on fi shery reso urcas • ...construction of a c'yr1CJnic model of the Susitna River Basin which will be used to develop quantitative relationships between aquatic habitats and resources pursuant to various hydro operational scenarios. ...establish a format,schedule,and content of periodic briefings on aquatic study,analysis and impact assessment efforts to the Al askan reso urce ag enc i es .. ., " I ~Ii':"',.....4;..• " i 0' J ~-I .(. ·-1 , "I .' 1 I .,("i, It. ;1 •t r'I·'..1 ... ,~l 1. I. 'i I I 1 • (9)Eisherjes Mitigation Planning To develop a mitigation plan con.sisting of quantified mitigation options for each phase of the proj ect as well as to 'identify deficiencies and prioritize studies needed to fulfill the quan- tificationrequirements of the mitig ation pl an. (h)Fisheries Mi-':..,t1.ation Planning The primary objective of the fisheries mitigation pl anningeffort was to develop a mitigation pl an consisting of quantified mitiga- tion options.for each phase of the project with the ultimate goal of providing the mitigation docunents required by the FERC for license approval. (i)Susitna Hatchery S itinQ,Study To determine if it is appropriate that consideration be given to the feasib 11 ity of s.iti.ng an en.hancenent hatchery to i.nsure mai n-- tenance of the existing stocks at or above their present popula- t io n 1eve 1s• (j)Wil dl ife and Habitat Impact Assessment &Miti9!tion P1anni !!9. To continue with ongoing data collection,workshop and field studies,prepare supporting reference docllI1ents,assess various project impacts,and develop final comprehensive mitigation plans for incl usio";n FERC 1 icense application .. (k)Transmission Line Survey To locate the centerol ine of the transmission 1 ines to incl ude width and location of right-af-way. -define all points of intersection (P.l.)along the centerline by measuring the station for-each P.1.and its bearings -provide information r'egarding the transmission equipment and appurten ance -prepare drawings and docunentations as required to meet the FERC requirements for 1 icense appl icati on 3.7 -Cost Estimate Update To upd ate proj ect cost estimate in connection with the el imination of the pioneer road and the selected access route,and other plan~;ng and design changes for inclusion in the FERC 1 icense appl ication. }..8 -Update Engineering/Construction$chedule To update construction schedules in connection with the el imlrtation of the pi.oneer road and the sel ected access route and other Pl ann;09 and design changes for inclusion in FERCl icense application. --J ,~I(:; "f.:i ~{ ~.q ~'l .~t.. I 1 .I HI , ~l1~ '11if· "11 ~ "l • I 1 I { I .' 1., I J ... 3.9 -Pr~£!ration of FERC L'icense Aeplication To prepare and coordinate all engineering and support activities necessary for the preparation 'of the FERC license appl ication. 3.10 ....Marketing and Finance Marketing and finance work was directed to: -further review A..,Tussing -s draft relXlrt II Al askaEnergy Planning Studies~;hold meeting to resolve~utstanding differences.bet...een Tussing-s and Acres reports on Susitna projec,t risk analysis;and' prepare appropriate responses;and -to resolve issues concerning sources and extent of financing and annual r.evenues as the basis for prepari ng appl icabl e portions of Exhibit 0 - ,'t'~4'!''111'1') J 4.2 -Background The original Plan of Study proposed that a single access route would be selected by May 1981,to be followed by a.detajled environmental inves .. t igati on..' Early in the stud,Y,three main access corridors were identified.Plans developed within these three corridors were evaluated on the basis of available information')comments and concerns of varicusstate agencie.s, and recommendations from the Susitna Hydroelectric Steering Committee (SHSC).'After an initial evaluation,the decision 'was made to assess all three alternative .corridors in more detai 1 throughout 1981 and re- cOlTlllend a selected route later in the year~"1lis assessment included environmental studies,engineering studies,aerial photography,and geologic mapping of all three alternative routes. In March of 1982,the AT aska Power Authority presented the results of the Susi tna Hydroe 1ectri c Feasi bi 1i ty Report to the pub 1ie,resource agencies and organizations.This report recorrmended an access plan which,for reasons of project schedule,would have necessitated the construction ofa pioneer road prior to the FERC license being issued. The construct i on of a.pioneer road,however,was cons;dered unaccept- able by the resource agencies and the plan was discarded. Consequently,the evaluation criteria were refined and additionalac- cess alternatives were develop~d.The most responsive plan in each of the three corridors was identified and subjected to a rllulti-discipli ... nary assessment and compari son.After cons iderat i on of these a lterna... tives,the AlaSka Power Authority Board of Directors formally adopted the Denali-Nurth plan,Plan 18,as the Pr.oposed Access Plan in September 1982. 4.3 -Objectives Throughout the development,evaluation and selection of the access plans.,the foremost objective was to provide a transportation system that would support construc.tion activities and allow for the orderly deve 1opment and mal ntenance of si te fac;1i ti es. 4.1 -Introduction 4 -ACCESS PLAN This section describes the development of alternative access plans from the original Acres Plan of Study of February 19S0 through to the final selection of the proposed,access plan as approved by the Al aska Power Authori tyBoard afO;rectors in September 1982.The main body of this section i.s concerned with the access planning studies which have.taken place subsequent to the issuance of the Susitna Hydroelectric Project Feasi'bi 1ity Report in March 1982 (Acres 1982a).In the 1atter part of this section,the modifications and improvements that have been made since the selection of the proposed plan in September 1982 alAe dis- cussed.In addition,the general guidelines that have been developed for roadway construction and mining of borrow sites are described. .. I 1 il• '1~~ ~1 I i 1•I 1 .1 t 1 1 . 1 '..j\ :1 J () ,-". ,. ..'.•..I,... "." 't:.-~.. '-'-.~..•.." - side of the Susitna River. CorridQf.2 "!'l From the Parks Hi gh'Hay to the Watana damsite vi a the south side of the Susitna River. Corridor 3 -From the Denali Highway to the Watana damsite., Meeting this fundamental objective involved the consideration not only of economics and technical ease of development but also many other di- verse factors~Of prime importance was the potenti al for impacts to the environment,namely impacts to the local fish and game populations .. In addition,since the Native villages and the Cook Inlet Region will eventually acqUire surface and subsurface rights,thei r interests were recogni zed and taken into account as were those of the lccal corrmuni- ties and general public• Wi th so many different factors i nfl uenci ng the choi ce of an access p'lan,it is evident that no one plan will satisfy all interests..The aim during the selection process was to consider-all factors in their proper perspective and produce a plan that represented the most Favor- able solution to both meeting project-related goals and minimizil:g im- pacts to the environment and surrounding colmtunities .. 4.4-.Existing Access Fac;lities The proposed Dev;1 Canyon and Watana dams~tes "are located approximately 115 mi les northeast of Anchorage and 140 mi les south of Fairbanks.The Alaska Railroad,which links AnChorage and Fairbanks,passes within 12 mi les of the Devi 1 Canyon damsite at Gold Creek.The George Parks High\'fay (Route 3)parallels the Al aska Rai Iroad for much af its route, although betweel~the communities of Sunshine and Hurricane the highway is rQuted to f ~e west of the rai Iroan,to the extent that Go ld Creek ;s situated approximately 16 mi les south of the intersection of the r ai I road and highway.At Cantwe 11,51 mi I es -north of Go Id Creek;the Denali Highway (Route 8)leads easterly approximately 116 miles to Paxson where it;ntersects the Richardson Highway..To the south,the Glenn Highway (Route 1)provides the main access to Glenallen and intersects the Ri chardson Hi ghway which leads south to Valdez..A location map with the proposed access route is shown on Figure 4.1. 4 ..5 ...Corridor Identification and Selectio'1 l'heAcres Plan of Study,February 1980,identified three general corri- dors 1eadi ng from the.ex i st i ng transport ati on network to the damsi tes. This ne·!twork consi stscf the George Parks Highway and the Alaska Rai lroac\to the west of the damsi tes and the Denali Hi ghway to the north.The three general corridors are identified on Figure 4.2 .. Corridor 1 ..From the Parks Hi ghway to the Watana damsite v'j a the north- .'. The access road studies identified a total of .eighteen altarnative plans within the three corridors.The alternatives were developed by laying out routes on topographical maps in accordance wi thaccepted road and,r.ail dS§~9n criteria~Subsequent.field investigations resula tau 1n minor modifications to reduce environmental impacts and improve ft 1i gnment ...1 !.\J.i,a 1 1A I" :i' •J. :1 '1'.~ ·i- ! I 1 ,! .t ·1 t 1 J • I, 1 J '}f.•·,1 ] 11 I I~I _3\,,_"~I i-~__;,,;._~_c,.......,~~,~~.L;...-~_:.;.~-i_·-;'·:-,-:~<':><JL~E· 1tr;';;":_;->::~~:-,,~;~:-::';;~;"?}).~~- -?/<" t During.eva~uation'of these access plans,.input from the public, resource agenc;es.,and Nat;ve organizations was sought and their response resulted ;n an expansion of the or;gi na 1 1i st of eight alternative plans to eleven.Plans 9 and 10 were added asa suggestion by the Susitna Hydroel ectr;c Steeri ng Committee as a means of limit;ng access by hc.Jing raj 1 only access as far as the Devi 1 Canyon damsite to reduce adverse envi ronment ali mpacts ;n and around the project area. Plan 11 was added as a way of provi di ng access from on 1y one rna;n terminus,Cantwell,and thus alleviate socioeconomic impacts to the other communities in the Railbelt (principally Gold Creek,Trapper C.~eek,Talkeetna and Hurricane). Rcri h-oad des;gn paranteters util i zed were as fo llows: -Maximum grade of 2.5 percen\:.; -Maximum curvature of 10 degrees;and -Loading of E-72. ..Max i mumgr ad e of 6 pat"!;anti -Maximum curvature o'rs degrees; -Design loading of80k axle and 200 k total during constTuction; and -Design loading of HS~20 after ",.Qnstrueti{'t"i·~ l1H~p~eliminary desigR ~~~iteria adopted for access road and Fail a1ternatives were selected on the basis of s;mil~r facili-ties provided for oti'!er remote pr-ojectsof this nature.Basi,,,:f'Qo.dwayparar1'!eters ,,-,are a'"fo 1 ll'\~.,e ~l~-';'-4~_~_~_t l \IN;:j. f,} I J 1 ':~l , '{ III1 A 'J 1 .i I l' '! j Minimize risks to project schedule; -Minim;ze en,,;ronmental impacts; A description of each of the eighteen alternative access plans') toget~er with a breakdown of casts,is given in Table 4.1 4.7 -Evaluation of Plans ()- The refined criteria used to evaluate the eighteen alternative access plans were: No pre-license construction; -Pravi de ;ni t i a1 access wi tnin one year; Provi de access bet.ween site.s dur;og project operation phase; -Provide access flexibility to ensure project is brought on-11ne within budget and schedule; -Minimize total cost of access; -Mi nim;ze in;ti al ;n'l2stment requi red to prav;de access to the Wattna damsite; Studies of these eleven access plans culminated in the production Clf the Acres Access Route Selection Report (Acres 1982d)which recommendHd Pl an 5 as the route which most closel}satisfied the selection critel-- i a.Pl an 5 starts from the George Parks Hi ghway near Hurricane and traverses along the Indian River to Gold Creek.From Gold Creek t,e road continues east on the south side of the Susitna River to the Devil Canyon damsit~,crosses a low level bridge and continues east on the ~9r-th side of the Susitna River to the Watana damsite.For the project to remain on schedule,it would have been necessary to construct a pioneeerroad along this route prior to the FERC license being issuec. In March of 1982,the Al aska Power Authority presented the results of the Susitna Hydroelectric Feasibility Reports of which Access Plar 5 was a part,to the pub'!ic,agencies,and organizations.During Apr'il, comment was obtai ned relative to thefeasibi lity study from th ase groups.As a resu 1t of these COrmtents,the pi oneer road concept :'las ~lim;nated,the evaluation criteria were refined,and six additional access alternatives were developed. During the evaluation process,the Alaska Power Authority staff formu- 1ated a further plan,thus i ncreasi ng the tot a1 number of plans under evaluation to'ei ghteen •This subsequently bee arne the pl anreccrrmeflded by Power Authority staff to the Power Authority Board of Directors,and was formally adopted as the Proposed Access Plan in September :.982 (Acres 198Ze). •• H,•...Iu I •, ~..'.'.. 'Il\••• ..'"'".,..,t ~4 fJ'f ~ Residents of the Indian River and Gold Creek communities are generally not in favor of a road access near their communities.Plan 1 was dis- carded because Plans 13 and lA achieve the same objectives without im- pacting the I~dian River and Gold Creek areas. Pla.n 7 was eliminated because it includes a circuit route connecting to both.the George Parks and Denal i Hi ghways..Thi s ci rcuit route was considered unacceptable by the resource agencies since it aggravated the control of pUblic access.' The abi lity to make full use of both rai 1 and road systems from south- central ports af entry to the rai lhead faci lity provides the project management with far greater flexibi lity to meet conti ngenci es,and control costs and schedule.Limited access plans utilizing an all rail or rail link £ystem with no road connection to an existing highway have less fleixfbility'and would impose a restraint on project operation that could result in delays and significant increases in cost.Four plans with limited access (Plans 8,9,10 and 15)were eliminated because of this cDnstraint~ -Accomnodate current land uses and plans; Accommodate Agency preferences; -Accomnodate preferences of Nati ve o'rgani zati ons; -Accommodate preferences of local cOlmlunities;and -Ac cOlllliodate pub lie concerns. All eighteen plans were evaluated using these refined criteria to de- term;ne the most responsi ve access plan in each of the three basic corr;dors..An exp 1anati on of the cr;teri a and the plans whi ch were subsequently eliminated is given below. To meet the overall project schedule requirements for the ~Jatana devel- opment,it is necessary to secure initial access to the Watana damsite within one year of t'he FERC licenSe:being lssued.The constraint of no pre-license construction resulted 1n theelim;nation of any plan in which irdtial access could not be completed within one year.This con- st rai nt 1eo to the el im;nat i on of the access plan submi tted in the Susitna Hydroelectric Project Feasibility Report (Plan 5)and five other plans {2,8,9,10,and Il}. Upon completion of both the Watana and Devi 1 Canyon dams,itis planned to opst':&te and maintain both sites from one central location (Watana). To facilitate these operation and maintenance actiVities,access plans with a road cnnnection between the sites were considered superior to those plans without a road connection.Plans 3 and 4 do not have access between the sites anc.:were discarded .. i,......... ~'!' ~,_._- ~J:'==-- t ':r "I .'~ ~I £1 I U 1 II, IJ i 'I 'I, I .1 1 1 , l [ * 1 u ••Jf The seven remai ni ng plans.found to meet the select ion criteri on were Plans 6 i1 11,13, 14, 16,17 and 18.Of these,Plans 13,16,and 18 in the North,South,and Denali corri dors,respect i vely,were .se lected as being the most responsive plan in each corridor.The three plans are descri bed be 1ow and the route 1ocat ions shown in Fi gures 4.3 through 4.5. This route originates at a railhead in Cantwell,and then follows the existing Denali Highway to a point 21 miles east of the junction of the George Parks and Denali highways.A new road would be constructed from 4.•8 -Descrie.tion of Most Responsive Acc.ess Plans . Plan 13 "North"{see Figure 4.3} This plan utilizes a roadway from a railhead facility adj.acent to the 13eorge Parks Highway at Hurricane to the Watana damsite following the north side of the Susitna Ri vel".A spur road seven rni 1es in length would be constructed at a later date to service the Devil Canyon development.Travelling southeast from Hurricane',the rQ-:.lte passes through Chul itna Pass,avoids the Iodi an Ri ver and Gold Creek areas, then parallels Portage Creek at a high elevation on the north side. After 'crossing Portage Creek the road cO\ltinues at a high elevation to the Watana damsite.Access to the south side of the Susitna River at the Devil Canyon damsite would be attained via a high leve.l suspension bridge approximately one mile downstream from the Dev;1 Canyon darn. This route crosses mountainous terrain at high e.levations and includes extensive sidehill cutting in the region of Portage Creek. Construction of the road,however,would not be as difficult as Plan 16,the So uth route .• Plan 16 ·'South (see Fi gure 4"l.q IThi s route generally para 11 el s the Susi tna Ri vet,traversi og west to east from a railhead at Gold Creek to the Oe'!il Canyon damsite,and continues following a southerly loop to theWatana darnsite.To achieve i nit;a1 access within one year,a temporary low level crossing to the north side of the Susitna River is required approximately twelve miles downstream from the Watana damsite.This would be used until comple- tion of a permanent high level bridge.In addition,a connecting road from the George Parks Highway to Devi 1 Canyon,with a major high1evel bridge across the Susitna River,is necessary to provide full road access to either site.The topography from Devi 1 Canyon to \~atana is mountai nous and the route i nvo 1ves the most di fficu 1t construction of the three plans,requiring a number of sidehill cuts and the construction of two major bridges.To provide initial access to the Watana damsite,this route presents the most difficult construction prob 1ems of the three routes,and has the highest potent i al for schedule delays and related cost increases. Plan 18 uDenali-North"(see Figute 4.5)----------- f I. t'""1 I "1 ~ .~~ I ~J 1 ·fIz~ ,1 :J ! ,I ~~l ,<•,j 1 I .--", I, J 287 335 326 Di scounted Total 368 416 437 Total 127 104 213 .......... *• ........ Watana Estimated Total Cost ($x 106 ) Devil CanyonPlan North (13)241 South (16)312 Denali-North (18)224 (a)Costs -Costs; -Schedule; Environmental issues; -Cultural resources; -Socioeconomics/Community preferences; -Preferences of Native organizations; -Relationship to current land stewardships,uses and plans;and -Recreation. The relative cost of the three access alternatives is presented in Table 4.2"This table outlines the total costs of the three plans with the schedule constraint that initi al access must be completed within one year of receipt of the FERC license"Costs to complete the access requirement for the Watana development only are also shown"The.costs of the three alternative plans can be summarized as fo 1lows: this point due south to the Watana dam$ite.The majority of the new road would traverse relatively flat terrain which would allow construction using side borrow techniqL!es~resulting in 'a minimum of di sturbanc,e to areas away from the all gnment ..Thi sis the most eas i 1y . constructed route for init;alaccess to the Watana site.Access to the Devil Canyon development would cons~ist primarily of a raj lroad extensi on from the ex;sti og Al aska Rai lroad at Go Id Creek to a rai lhead f ac;1i ty adjacent to the Dev i 1 Canyon camp area.To pravi de access to theWatana damsite and the existing highway .system,a connecting road would be constructed from the Devi 1 Canyon rai lhead following a northerlY loop to the Watana dams;tee Access to the northside of the Susitna River would be attained via a high level suspension bridge constructed approximate ly one m;1e downstream from the Devi 1 Canyon dame In genera],the alignment crosses terratn with gentle to moderate slopes which wOl}ld allow roadbed construction without deep cuts. 4.9 -.f.2!!!parisonofthe.Selected Alternative Plal!§. To detenni ne whi ch of the three access plans best accommodated both project related goals and the concerns of the resource agencies,Native organizations,and affected communities,the plans were subjected to a multi-disciplinary evaluation and compari.son.Among the issues addressed in this evaluation and comparison were: J J J J r;.- fl t l, .J :1\-• Il' I i 1 f t ..W'..J 6 months 9 months 12 mOriths Denali-North North South Schedule The costs a.'"e ;n terms of 1982 doll ars and i ncl ude a 11 costs asso- ciated with design,construction.,maintenance,and logistics. Discounted total costs.(present warth as of 1982)haye been shown here for camp ari son purposes to deli neate the di fferences in timing of expenditure. For the deve 10pment of access to the Watana si te,the Denal i-North Plan has the least cost and the lowest probability of increased costs resulting from unforeseen conditions..The North Pl an ~s rafi~ed second.The North PI an has the lowest over'all cost .whi le the Denali -North has the hi ghes't.However,a 1arge port i on of the cost of the Denali-North PI an would be incurred more than a decade in the fut~re.When conve'rtingcosts to equivalent present value, the overall costs of the Denali-North and the South pI ans are simi lar. The schedule for providing initial access to the Watana site was given prime consideration since the cost ramifications of a schedule delay are highly significant.The elimination of pre- license construction of a pioneer access road has resulted in the severe compression of on-site construction activities in the 1985 ...86 period.With the present overall project scheduling;· should diversion not be completed prior to spring runoff in 1987, dam foundation preparation work would be delayed one year,and hence cause a delay to the overall project of one year.It has been estimated that the resultant increase in cost would likely be in the rang~of 100-200 mil1i on do 11 ar.s.The access route that assures t.le qui ckest camp 1et i on and hence the ear Ii est del i very of equipment and materials to the site has a distinct advantage.The foretasted construction periods for initial access,including mobilization,for the three plans are: It is evident that with the Denali-North Plan site activities can be supported at an earli er date than by either of the other routes.Consequently,the Denali-North DIan offers the highest probability of meeting schedule and hence the least risk of project delay and increase in cast.The schedule for access in relation to diversion is shown for the three plans in Figure 4.6. (c)Environmental Issues EnVironmental issues have played a major role in access planning to date.The rna;n issue is that a road will permit human entry into an area which is relatively inaccessible at present,causing both direct and indirect impacts.A summary of these key impacts with regard to wildlife,wildlife habitat,and fisheries for each of the three a lternative.access plans is out lined be low. (b) j J ! IIJt:. .J t '] Wildlife and Habitat () - 1.Hurricane to Devil Can.l9.!!.:This segment is composed "i1most ent ire lyOf prodTICtive.mi xed forest ,ri pari an, and wet 1ands habi tats important to moose,furbe.arers, and birds..It inc 1udesthree areas where slopes of over 3D percent will l'"equireside-hill cu.ts,all above wetland zones vulnerable to erosion related impacts .. 2.Gold Creek to Devil Can1grr:This segment is composed Of mixed forest and wetfana habitats,but includes less wetland habitat and fewer wetland habitat types than the Hurricane to Dev;1 Canyon segment..Al though thi s segment contains habitat suitable for moose,black bears,furbearers and birds,it has the least potential 'for adverse impacts to wi ldlife of the five segments considered. 3.Devi 1 Can on to Watana (North Side):.The following comments app y to oth the Dena l-North and North routes.This segment traverses a varied mixture of forest,shrub,and tundra habitat types,generally of medium to low productivity as wildlife habitat.It crosses the Dev;1sand Tsusena Creek drai nages and passes by Swimming Bear Lake which contains habitat suitable for furbearers. The three selected alternative access routes are made up of five di stinct wi ldlife and habitat segments: 4.Devi 1 Canyon to Watana (South Side):This segment is 1iT9'h1y variea=with respect toli'aE"itat types,containing complex mixtures of forest.,shrub,tundra"wetlands, and ripari an vegetation.The western portion is mostly tundra and shrub,with forest and wet 1ands occurri ng along the eastern portion in the Vicinity of Prairie Creek,Stephan Lake,and Tsusena and Deadman Creeks. Prairie Creek supports a high concentration ot'brown bears and the lower Tsusena and Deadman Creek areas support lightly hunted concentrations of moose and black bears.The Stephan Lake area supports high densities of moose and bears.Access development in this segment would probably result in habitat loss or a 1terati on,increased hunti ng,and human-bear conflicts. 5.Denali Highway to Watana:This segment is primarily composed of·ifiFU6 and tundra veget ati on types,wi th little productive forest habitat present.Although habitat diversity is relatively low along this segment, thf:southern portion along Deadman Creek contains an important brown bear concentration and browse for moose.This segment crosses a peripheral portion of (i) J J J J I J J f 1 i.] :1 •1 ~l #...."'"';!, !~ 1-].- r·.~.' Q Segments 1 and 3 Segments 1,2,and 4 Segments 2,3,and 5 North South Dena I i-North' ........ All three alternative routes WQuld have direct and indirect impacts on fisheri~s.Direct impacts include the effects on water qual ity and aquatic habitat whereas ;ncreased angling pressure is an indirect impact..A qualitative com- parison of the fishery impacts related to the alternative plans was undertaken.The parameters used to assess im- pacts a long each route inc 1uded the number of streams crossed,the number and length of lateral transits (i ..e., where the roadway parallel s the streams and runoff from the roadway can run directly into the stream),the number of watersheds affected,and the presence of res;dent C\,nd al1adromous fish • Fisheries. •,t Table 4.3 summarizes the three alternative access plans with respect to potential adverse impacts on wildlife and their supporting habi~at. The North route has the least potenti al for creating ad ... verse i.mpact s to wj 1d life and habi t at for it traverses or approaches the fewest areas of productive ha~itat and zones of species concentration or movement.The wildlife impacts of the South Pl an can be expected to be greater than those of the North Plan due to the proximity of the route to Prairie Creek,Stephan Lake,and the Fog Lakes,which current Iy support hi gh dens;ti es of moose and black and 'brown bears.In particular,Prairie Creek supports what may be the highest concentrat i on of brown bears in the Susitna Basin.The Denali-North Plan crosse~the periphery of the ~le lchi na cari bou range and movement zone between the Denali Highway and Susitna River.In addi'tion,this route has the potential for disturbances to brown and black bear concentrati ons and movement zones in the Deadman and Tsusena Creek areas..Overall,however,the potential for adverse impacts with the Denal i-North Pl an is simi 1ar to the South Plan. () the range Jf the Ne lchi na caribou herd and there is evidence that as herd size increases,caribou are like- ly to migrate across the route and calve in the vicini ... ty..Although it is not possible to predict with any certainty how the physical presence o~the road itself or traffi c wi 11 affect car;bou movements,popul ati on size or productivity,it.is likely that a variety of site-speclflc mitigation measures will be necessary to protect the herd. These segments combine,as illustrated below,to form the three alternative access plans: (i i ) ... • 1~ { 1 ~;;n r,;.,;:..-; I ) 1 ,j' 11IIIIIIII_:.,4 ri ~'t .._)- Devi 1 ca~~on to Watana (South Side):The portion between -t~e Sus;tna "R1 vel'"crosslng and Devil CanY2n requires nine steam crossings,but it is unlikely that these contain significant fish populations.The portion of this segment from Watana to the Susitna River is not expected to have any major direct impacts, however,i ncre.ased ang ling pressure in the vi ci ni ty of Stephan Lake may result due to the prOXimity of the access road.The segment crosses both the Susitna and the Talkeetna watersheds.Seven miles of cut into banks of greater than 30 degress occur in this segment .. Hurricane to Devil Canyon:Seven stream crossings wil1- be required along ffiis route,including Indian River which is an important salmon spawning river.Both the Chulitna Ri vel'"watershed and the Susitna Ri vier flatershed are affected by thi s route.The increased access to Indi an Ri vel'"wi 11 be an i mpol"tant i ndi rect impact to the segment •Approximate ly 1~a m;1es of cuts into banks greater than 30 degressoccur along this route requi r;ng erosi on contro 1 measures to preserve the water qual i ty and aquati c habitat. 30 1d Creek to Devi 1 CanY.Q!!:Th is segment .cro.sses si x streams and is expectedto have minimal direct and indirect impacts.Anadromous fish spawning is likely in some streams but impacts are expected to be minimal. Approximately 2.5 miles of cuts into banks greater than 30degress occur in this section.In the Denali-North Plan,this segment would be railroad whereas in the South Plan it would be road. Devil Canyon to Watana (North Side,North Plan):This segment crosses 20 streams anal ateral1y transl'ts four rivers for a total distance of approximately 12 miles. Seven mi les of thi s 1ateral transit parallels Portage Creek which is an important salmon spawning area. Dev.i]Canyon toWatana (North Side,Denali-North Plan): The cl fference between th is segment and segment 3 described above is that it avoids Portage Creek by traversing through a pass four mi 1es to the east"The number of streams crossed is consequent 1y reduced to 12,and the number of lateral transits is reduced to two with a total distance of four miles. - 5. 3. 2. 4. 1. The three access plan alternatives incorporate combinations .of seven di stinct fishery segments. 1., i] ~ ~ '] "11 ~f. :1 l", 'I~ ;\. J J ~ I f.. I ':i- 1"'; 1 1 '1 :'t Segments 1 and 3 Segments 1,2,and 5 Segments 2~4 t 6 and 7 'e''F North South Denali -North The Denali-North Plan is likely to have a significant direct and indirect impact on gra.ylin9 fisheries given the number of str\:am crossi ngs,1atera 1 tY'ansi ts,and watershed affected.Anadromous fisheries impact will be minimal and wi 11 only be significant 'along the rai lroad spur between Gold Creek and Devil Canyon. The South Plan is likely to create ~~ignificant direct and indirect impacts at Indian River,which is an important salmon spawning river.Anaciromous fisheries impacts will occur in the Gold Creek to Devil Canyon segment as for the Denali-North Plan.In addition,indirect impacts may occur in the Stephan Lake area. The North Plan,like the South Plan,may impact salmon spawning activity in Indian River.Significant impacts are likely along Portage Creek due to water quality impacts thr'ough increased erosion and due to 1ndirect impacts such as increased angling pressure. With any of the selected plans,direct and indirect effects can be minimized through proper engineering design and pru- dent management.Criteria for the development of borrow sites and the design of bridges and culverts together with mitigation recommendations are discussed in Exhibit E of the PERC License Application. 6.Denali Hiahwayto Watana:The segment from the Denali Hi ghway to "the Watanadamsite.has 22 stream crossings and passes from the Nenana into the Susitna \l/atershed. Much of the route crosses or is in proximity to seasonal grayl i ng hab i tat and runs para11 el to Deadman Creek for nearly ten miles.If recruitment and growth rates are low along this segment,it is unl ikely that resident populations could sustain heavy fishing pressure.Hence,this segment has Cl high potential for .impacting the local grayling population. 7.Denali Highway:Th@ Denal~H;ghwi~Y from Ca~twell to t~tana access turnoff wl11 requlre upgradl n9..The upgrading will involve only mi.nor tealignment and neg- ligible alteration to present strE!!am cro~5ings.The segment crosses 11 streams and 1at.er-al ly transits two rivers for a total distance of five miles ..There is no anadromous fi sh spawn;ng in thi s segment and 1itt le direct or indirect impact is exoected. The three al ternati ve access routes c"re compri sed of the following segments: ij 1 1 '1 J I l ;)1 ·',..,.1 J 1 f • 1'; i .~.;L~ ,1 ] '4~.•I i Ito I I I ~ ·f ( { (d)Cultural Resources A level one cultural resources survey was :ondwcted over a large portion of the three access plans.The segment of the Denali- North Pl an between the Watana damsite and the Denali Hi ghway traverses an area of high potential for cultural resource sites. Treeless areas along thi s segment lack appreci able soi 1 desposition,making cultural resources visible and more vulnerable to secondary impacts.Conmon to both the Denali-North and the North Plan is the segment on the north side of the Susitna River from the Watana damsite to where the road parallels Devi 15 Creek ... This segment is also largely treeless~making it highly vulnerable to secondary impacts.The South Plan traverses less terrain of archaeological importance than either of the other two routes. Seve.al sites exi.st alo.ng the southerly Devil Canyon to Watana segment;however,since much of the route is forested,these.sites are less vulnerable to secondary impacts. The ranking from the least to the highest with regard to cultural resource impacts is South,North,Denali-North ..However,impacts to cultural resources can be fully mitigated by avoidance,protec- tion or salvage;consequently,this issue was -not critical to the selection process. (e)Socioeconomics/Community Preferences Soc;oeconomi c impacts on the Mat-su Borough as a who 1e would be 'simi1ar in magnitude for all three plans.However,each of the three plans affects future socioeconomic conditions in differing degreesi n certain areas and communities.The important differences affecting specific communities are outlined be1ow~ (i )Cantwe 11 The Denali-North Plan would create significant increases in population,local emp1o}11lent,business activity,housing and traffi c.These impacts result because a rai Ihead f aci 1i ty WOU 1d be 1oc ated at Cantwe 11 and because Cantwell would be the nearest community to the Watana damsite.Both the North and South Plans would impact Cantwell to a far lesser extent. (i i )Hurri cane The North Plan would significantly impact the Hurricane area,since currently there is little population,employ... ment,bus;ness act;vity or hous;ng ...Changes in soc;oecono- mic.indicators for Hurricane would be less under the South Plan and considerably less under the Denali-North plan. -J. ~~......-., - 'f --'''"'"'''''"''t, i·$ ~j f tr' (iii)ill.E.E.er Creek and Talkeetna Trapper Creek would experience slightly larger changes in economtc i nd i c ators wi th the North pl an th an under the South or Denali-North Plans.The South Plan would impact the.Talkeetna area slightly more than the other two plans. (iv)Gold Creek With the South Plan,a rai lhead fac;lity would be.developed at Gold Creek creating a significant increase in sociQ- economi c i nd i cators in this area.The Denali -North Pl an includes construction of a railhead facility at the Devil Canyon site which would create impacts at Gold Creek,but not to the same extent as the South Pl an.Mi nimal impacts would result in Gold Creek under ~he North Plan. The responses of people whQwill be affected by these potential changes are mixed.The people of Cantwell are generally in favor of some economic stimulus and development in their community .. Some concern was expressed over the potential effects of access on fish and wi ldlife resources,but with stringent hunting regulations implemented and enforced,it was considered that this problem could be successfully mitigated.The majority of residents in both Talkeetna and Trapper Ci'eek have i'fldicated a strong preference to maintain their general lifestyle patterns and do not desire rapid.uncontrolled change.The Denali-North Plan would impact these ~reas the least.The majority of 1andholders in the Iodi an Ri ver subdi vi si on favor retenti on of the remote st atus of the area and do not want road access through thei r 1ands.Thi s and other feedback to date indicate that the Denali- North Plan will come closest to creating socioeconomic changes that are acceptable to or desired by landholders andresi dents in the potentially impacted areas and communities • (f)Preferences of Native Organi zations Cook Inlet Region Inc.(CIRI)has selected lands surrounding the impoundment areas and south of the Sus;tna Ri ver between the damsites.CIR!has offici a 1lyexpressed a preference for a plan prov;di ng road access from the George Parks Hi ghway t.o both damsitesa.long the south side of the Susitna Ri ver.The Tyonek Native Corporation and the CIRl village residents have indicated a s im;1ar preference.The South Pl an provi des fu 11 road access to their lands south of the Sutina River and thus comes closest to meeting these desires.The AHTNA Native Region Corporation presentl y owns 1an.d border;ng the Denali Highway and they, together with the Cantwell Vi 11 age Corporation,have expressed a preference for the Dena 1i ..North Pl an.None of the Nat;ve organ;.. zations support the North Plan. ~J ; ~! I • I Ii' I l ( .( ( ( ~ rl .... ,.~ • ..... m• 'C Following meetings~discussions,and evaluation of various access plans,it became evident that recreation plans.are flexible enough to adapt to any of the threesel ected access route~;.No one route was identified which had superior recreational potenti,al as soc;a- ted with it.Therefore,compatibi 1ity with recreational aspects was essentially eliminated as an evaluation criterion. By prOViding public access to a now relatively 'inaccessible,semi- wi lderness area.,conflict may be imposed with wi Idlife habitats necessitating an increased level of wildlife and people management b.\'the vari ous resource agenci es. In general,however,none of the plans will be in major conflict with any present federal,borough,or Native management plans~ Recreati on(h) 4.9 -Summary of Final Selection of Plans In reachi ng the deci sian as to whi ch of the three alternat i ve access plans was to be recommended,it was necessary to evaluate the highly comp 1ex i nterp 1ay th at exi sts between the many issues i nvo 1ved. Ana lys;s of the key issues descri bed ;n the preceedi ng pages i ndi cates that no one plan satisfied all the selection criteria nor accommodated a 11 the concerns of.the resource agenc;es,Nat;ve organi zati ons and public.Therefore,it was necesary to make a rat;onal assessment of tradeoffs between the sometimes confl i cti ngenv;ronment a1 concerns of impacts on fisheries,wildlife,socioeconomics,land·use.,and r ecreat i on a.l opportuni ties on the one hand,wi th project cost schedule,construction r;sk and management needs on the other ~With a1; (g)Relationshi.e.to Current Land Stewardships?Uses and Plan§. Much of 1and requi red for fJroject deve lopment has been or may be conveyed to Native organizations.The remaining lands are gene- rally under state and federal control.The South Plan traverses more Nat i ve-se 1ected 1ands than eithe~of the other two routes, and although present ~and use is low,the Native organizations have expressed an int~rest in potentially developing their lands for mining,recreation,forestry,or residential use • The other 1and management plans that have a 1arge beari ng on access development are the Bureau of Land Management f s (BLM) recent dec;s;on to open the Dena 1i Pl anni ng B10ck to mi neral exploration,and the Denali Scenic Highway Study being initiated by the Al aska Land Use Counci 1.The Denali Hi ghway to Deadman Mountain segment of the Denali-North Pl an would be compatible with BLMJs plans.During the construction phase of the-project?the Denali-North Plan could create conflicts with the development of a Dena 11 Seen i e Hi ghway;however,after C~Jnstruction,the access road and project faciliti'es could be incof"porated into the overall scenic highway planning. ~ 'I f '"jt .~ • 'J ] :1 ''1.,~','"~,l l .. 1\1'j 'l: I 1 I t' .' t ·f. { I ( Delays in the supply of materials to the damsite,caused by either an interrupt ion of serv;ce of the rai lway system or the Susi tna River not being passablG during spring breakup,could result in significant cost impacts.These factors,together with the realization that the South Plan offers no specific advantages over the other two plans in any of the areas of envi ronment a I or soc;a I concern,led to the South Plan being eliminated from further considerati on. The South route,Plan 16,was eliminated primarily because of the construction difficulties associated with building a major low level crossing 12 miles downstream from the Watana damsite.This crossing would consist of a floating or fixed temporary bridge which wou1ci need to be removed prior to spring breakup during the first three years of the project (the time estimated for comple- t i on of the permanent bri dge)..Th is waul d resu 1tin a seri ous interruption in the flow of material!to the site.Another draw- back is that floating bridges require continual maintenance and are generally subject to more weight and dimensional limitations than permanent structures. A further 1imi tati on of thi s route·is that,for ,the fi rst three years of the prcject,all construct i on work must be supported solely from the railhead facility at Gold Creek.This problem ari ses because it wi 11 take an estimated three years to comp 1ete construction of the connecting road across the Susitna River at Devil Canyon to Hurricane on the George Parks Highway.Limited access such as this does not provide the flexibility needed by the project management to meet cont i ngenei es and contra 1 costs and schedule.. (b)Schedule Constraints The choi ce of an acces s pI an thus narrowed down to the North and Dena 1i-North Pl ans.0f the many issues addressed dur;ng the evaluation process,the issue of "schedule"and II sc hedule ri skU was determi ned as bei ng the most i mportanti n the fi na I se1 ecti on of the recoi:.dtended pI an. Schedule plays such an important role in the evaluation process because of the spec;al set of conditions that exi st in a subarctic environment.Building roads in these regions involves the consi- deration of many factors not found elsewhere in other environ- ments.Specifically,the chief concern is one of weather and the these factors in mind,it should besmphasized that the primary purpose of access is to provide and maintain an uninterrupted flow of materials and personnel to the damsite throughout the life of the projectc Should this fW1damental objective not be achieved,significant schedule and ~udget overruns will occurc (a)Elimination of I~South Plan u Z! '] I I I 1 ;{ .'( , Ifl ! { .....J If diversion is not achieved prior to spring runoff in 1987,dam fC"undation preparation work will be delayed one year,and hence, cause a delay to the overall project of one year. Cost Impacts- consequent short durat i on of the construct;on -season.The roads for both the North.and Denali -North pl ans wi 11,for the most part, be constructed at elevations in ex-cess of 3,000 feet.At these elevations,the likely time available for uninterrupted construct ion ina typi ca 1 year is 5 months,and 'at most 6 months. The forecasted construction period for initial access,including mobilization,is 6 months for the Denali-North Plan and 9 months for the North Plan..At first glance,a difference in schedule of 3 months does not'seem great;however,when considering that only 6 months of the year are available for construction,the additional 3 months become highly significant,especially when read in the context of the li ke 1y schedu]e for issuance of the FERC 1;cense • The.date the FERC license will be ·issued cannot be accurately determined at this time,but is forecast to be within the first ni:1E months of 1985.Hence,thE interval between licensing and tile scheduled date of diversion can vary significantly,as shown graphically 1n Figure 4.6.This illustrates that the precise time of year the 1i cense is issued is cri tical to the construct;on schedul e of the access route 7 for if de 1ays in 1i cens;ng occur, there is a riSk of del ay to the project schedule to the extent that river diversion in 1987 will be missed.The risk of delays increases: --p""" -The later the FERC 1i cense is issued;and -The longer the schedule required for construction of initi al access. The increase in costs result;og from a one year del ay have been estimated to be in the range of 100-200 million dollars.This ;ncrease i ncl udes the fi nanc;al cost of ;nvestment by spri ng of 1987,the fi nanci al costs of reschedul ing work for a one year del ay,and rep 1acement Power costs. (d)Conclusion The Dena 1i-North Plan has the highest probab i 1i ty .of meeti ng schedu 1e and 1east ri sk of increase in project cost for two rea- sons.First,it has the shortest construction schedule (six months).Second,a passable route could be constructed even under winter conditions since the route traverses relatively flat terT'"a;n almost its entire length.In contrast,the North route is mount ai nous and invo 1vesextensi ve si dehi 11 c utt i ng,especi all yin the Portage Creek area.Winter construction along sections such as this would present major problems and increase the probability of schedule delay. (c) 1 J "1• j , ,111 1i.~. ..'l J] -- .';.1 • ..'\6;;?Z\\..'w··.··'1, ....1.- -(e)Plan Recommendation (b)Portions of the"access road between the Denali Highway and the Wat ana damsi te wi 11 tr averse fl at terrai n.In these areas,a berm type cross section will be formed with the crown of the road being II two to three feet II above the e1ev at i on of adj acent ground.st eep side slopes would present an unnatural barrier to migrating caribou,exaggerate the visual impact of the road itself,and aggravate the problem of snow removal.To reduce these problems, the side slopes wi 11 be flattened using excavated peat materi al and rehab;litated through scarification and ferti lization~ (c)The chief fisheries concern was the proximity of the proposed route to Deadman Creek,Deadman Lake,and Bi g Lake.For a di s- tance of approximately 16 miles the road parallels Deadman Creek, which contains good to excellent grayling populations.To allevi- ate the proh 1em of potent i ali ncreased ang 11 ng pressure.,the road was moved one half to one mi le west of Deadman Creek. (d)The preliminary,reconniassance level cultural resourc~survey conducted on the proposed access route located and:ocumented sites on or in close Jf0ximity to the right~of-way and/or poten~ tial borrow sites.The nUmbel'"of these sites that will be di- rectly or indirectly affected will not be known until a more detailed investigation is completed.However,indications are that all sites can be mitigated by avoidance,protection,or sa Ivage .. Fo11 vwing approval of the recorrmended plan by the Alaska Power Author;ty Bo ard of Di rectors in September 1.982,further studi es were conducted to optimize the route location,both in terms of cost and m;nimt zi og impacts to the envi ronment.Each of the spec;ali st sub- consultants was asked to review the proposed plan to identify specific problem areas,develop modifications and improvements,and contribute to drawing up a set of general guidelines for access d'evelopment.The results of this review are capsulized below. (a)An important red fox denning area and a bald eagle nest were identified close to the proposed road alignment~so consequently the road was rea 1i gned to create a buffer zone of at 1east one ha lf mi le between the ~~oad and the si tes. It is recommended that the Denali-North route be selected so as to ensure completion of 1nitial access to the'Watana damsite by the' end of the first quarter of 1986,for it is considered that the risk of 5i gni fi cant cost overruns is too high with any other route. 4.10 -Modifications to Reconmended Access Plan 1 l I 1 1 #"t'.. 1 ~i '] Il') 1 1 ifilt. ! (e)The conrnunity that will undergo the most growth and socioeconomic change with the proposed access plan is Cantwell~.Subsequent to the selection of this access plan,the residents of Cantwell were so 1i ct ted for their comments and suggestions.Thei r responses resulted in the following modifications and recommendations: (i)The plan was modified to 'include paving the road from the railhead-facility to four miles east of the junction of the George Parks anrj Denal'i Highways..This will eliminate any probleal1 with dust and flying stones in the residential district. (ii)For safety reasons,it is recomTlertded that: -Speed restrictions be irnpoC)ed along the above segment; ~A bike path be provided along the same segment,since the school is 'adjacent to the access road;and 6 percent 5 degrees SOk axle,200 k total HS ...20 - '~_.P-- j' ik t,P-'""'J -Maximum grade -Maximum curvature -Design load;ng: .during construction .after construction The main concern of the Native organizations represented by GIRl is to gain access to their land south of the Susitna River.Under the proposed access plan,these 1ands wi 11 be accessi b1e by both road and rail,the railroad being from Go 1d Creek to the Devil Canyon damsite on the southside of the Susitna River.After com- pletion of the Watana dam,road access will be provided across the top;of the dam to Native l;ands"Similarly,a road across the top of the Devi 1 Canyon dam wi 11 be constructed once the main works at Devi 1 Canyon are completed..In addition,alternative road access will be available via the high level suspension bridge one mile downstream from the Devil Canyon dam. From an environmental standpoint,it is desirable to limit the number of people in the project area in order to minimize impacts to wildlife habitat and fisheries..In comparison with a paved road,an unpaved road would deter some people from visiting the area and thus create less of an impact to the environment.An un- paved t"oad would also serve to maintain as much as possible the wilderness character of the area.An evaluation of projected traffic volumes and loadings confirmed that an unpaved gravel road wi th a 24 ft runn'j ng surf ace and 5 ft wide shou 1der waul d be adequate. For the efficient,economical,and safe movement of supplies,the following design parameters were cho~sn: . -Improvements be made to the i ntersecti on of the George Parks and Denali Highways including pavement markings and traffic signals. (h) (f) (g) J "I /,1 i 11 1 I t 1 J~ ~-] ~"t J] tfl 'I ] ~1 'Ill.1.'" 1 A!1 mater;al sites.should be developed in phases by aliquots, and part;ons of thesi te which are more sansi t i ve from an environmental standpoint should bel eft until last; Adhering to these grades and curvatures,<the entire length of the road would result in excessively deep cuts and extensive fills i.n some a.reas,and could create serious technical and environmental problems.<From an engineering standpoint,it is advisable to avoid deep cuts because of the PQtentialslopestabi lity problems, especi a 11 yin permafrost zones.A1so,deep cut sand 1arge fi 11 s are detri mental to the envi ronment for they act as a barri er to the migration of big game and disrupt the visual harmony of the wi lderness sett i og.Therefore,in areas where adheri ng to the aforementioned grades and curvatures involve extensive cutting and filling,the design standards will be reduced to allow steeper grades and shorter radius turns. This fleXibility of design standards provides gl~eater latitude to "fit"the road withi 0.the topography and thereby enhance the vi sual qual ity of the surround;og 1andscapl~.For reasons of driver safety,the design standards will in no instance be less than those applicable to a 40 mph design speed. (i)One of the most important issues associ ated with the construction of the access road is the development of borrow sites"Potenti al impacts can be mitigated through selective siting of borrow sites and the use of state-of-the-art gravel removal techni ques.After close consultation with fish and wildlife,recreational,aesthe- tic,and cultl!ralresource spec;ali sts~the following gUi,delines were developed to ensure that any impacts are minimized. ..Active floodplain and streambed locations should be avoided; In locating borrow sites 1 first p\v-iority is to be given to well-drained upland locations,and second priority to first- level terrace sites; -First-level terrace sites should be located on the inactive side of the floodplain and mined by pit excavation rather than by shallow scraping; If \'#et processing is required,water withdrawal and di scharge locations should be carefully sited to minimize fish and wi lcrtife disturbance.Drawdown in overwintering pools used by fi sh or aquat i c mamma'l s and any di sturbances to spawn;ng areas is to be avoided.In addition,water intake structures should be enclosed in screened boxes;1 I f J J '"I '1 '] ] "f] :1 I J. 1111 '\ 1ft 'I 1 !l' 1 d -Watana Access Access to the Watana damsite will connect with the eXisting Alaska Rai lroad at Cantwell where a rai 1head and storage fact 1i ty occupying 40 acres will be constructed o This facility will act as a transfer po;nt frt1m rai 1 to road transport and as a storage area for a two-week backlJp supply of mater;a1s and equipment.From the rai 'head faci lity the road wi 11 follow an exi sting route to the junction of ,the Geor'ge Parks and lDenali Highways (a distance of two mil~s)i then~ro\ceedin an easterly diY'ection fora distance of 21 ..3 m;es along the Denali Highway~Anew road,41~6 miles in 1ength,wi i 1 be con~;tructed from th is poi nt due south to the Watana campsite ..On ~:Ol'1pletion of the dam access to Native lands on the south side of the!Susitna River will be provided from the Watana campsite,with th~road crossing along the top of the dam. This will involve the construction of an additional 2.8 miles of road,brihging the total length of new road to 44 ..2 miles • The majority of the new road will traverse relatively flat terrain invo 1 ving only isolated sections of cut and fill.Where it is not possible to locate thEl road on sidehi 11 slopes of gentle to moderate steepness,-the road wi 11 be formed us;ng side borrow techniques;with the crown of the road be;ng two to three feet above the elevation of adjacent ground.By balancing cut and rirl and usi ng si de borrow techni ques,the need for borrow materi a 1 from pi t s and consequent di sturbance to areas away from the a11 gnment wi 11 be mi nimi zed. It has be~n estimated that it wi 11 take apprOXimately six months to secure initial access with an additional year for completion and the upgr adi ng of the Dena li Hi ghway sect;on. (a) ..For rehabilitation purposes,sites should have irregular boundaries,including projections of undisturbed,.vegetated terra;n ;nto the si tee Where pondi ng wi 11 occur,as in ri rst- level terrace'sites,islands of undisturbed vegetated terrain should be left within the perimeter of the operational site;and Organic overburden,slash,and debris stockpiled during cleaning should be distributed over the excavated area prior to fertili- zation.The rehabilitation of sites is to be completed by the end of the growing season irrmediately following last use. The mod i ficat ions and i mprovem.ents·to the proposed access plan, together with the general gu;del i nes that have been developed for roadway construction and mining of borrow sites,have been fully incorporated into the draft FERC License Application.A more detailed description of specific mitigation plans is given in the relevant sections of Exhibit E of the Application. 4.11 -Descrietion of ~os.~d Access Plan :J .-J'...,,;' > ':l« 1'1Ii- '11"'" ,II 'I i • 1 I I I J 1 1 J .. r tr, .-', !• --I r -I r TI 1 . iJ• '] , i 1 PI. I ~l.·. I 1 '1 [.·'1·,.1 l . t 1 fl :l t I 1 I 1 I I (b)Devil Canyon Access Access to the Devi"l Canyon deve lopment·wi 11 consi st primD.ri 1y of a railroad extension from the existing AJask~Rai.lroad at Gold Creek to a railhead and storage fati lity adjacent to the Devi 1 Canyon camp area.To provide flexibi lity of access,the rai lroad extension will be augmented by a road between the Devil Canyon and Watana damsites. (i)Rail Extension Except for a 2-mile section where the route traverses steep terrain alongside the Susitna River,the railroad will c 11mb steadi ly for 12,,2 mi 1es from Go Id Creek to the railhead facility near the Devil Canyon camp.Nearly all of the route traverses potentially frozen,basal till em side slopes varying from flat to moderately .steep.Several streams are crossed,requi ri og the construct i on of I ar-ge cu 1verts..However,where the rai 1road crosses Jack Long Creek,small bridges will be built to minimize impacts to the aquatic habitat.In view of the construction conditions,it is estimated that it will take eighteen ~c~ths to two years to complete the extension. Connecting Road From the rai Ihead faci lity at Devi 1 Canyon,a connecti.ng road will be built to a high level suspension bridge approximately one mile downstream from the damsite..The route then proceeds in a north easterly direction,crosses Devil Creek and swi ngsround past Swimming Bear Lake at an elevation of 3500 feet before continuing;n a south easterly direction through a wide pass..After crossi.ng Tsusena Creek,the road continues south to the Watana. damsite •.The overall length of the road is 37.0 miles. In genera l,the ali gnment crosses good soi I types with bedrock at or near the.surface.Erosi on and thaw settlement should not be a problem since the terrai.n has gent 1e to moderate slopes whi ch wi 11 allow roadbed construction without deep cuts.The connecting road wi 11 be bUt It to the same standard and in accordance with the design parameters used for the Watana access road. However,as is the case for the Watana damsite access road, the design standards will be reduced to as low as 40 mph in areas where it is necess ary to m;n-,mi ze the ext ent of cutt i ng and fi 11 i ng.The affected areas are the approache.s to some of the stream crossings,the most significant being those of the high level bridge crossing the Susitna River downstream from Devil Canyon. ,) .. -......-~ .. "I--; .. ~• 228 Sheet 1 of 1 ...Revis ton:E, 180 420 12 107* 16 J o o I 6 ROAflIAY:OEHALI JHGlIWAY TO W';TAHA~ RAIL:GOLD CREEK TO DEVIL CANYON ON SOlJTII srDE (if SU~iTNA.CONNEC- TlNG ROAD ON HORlI' SIDE Of SUSITNA. ••.-.,~.-.,,~~.-.'".:.?J ••~-!'.,.,...""..•."...,.....-,0·'.-._:.-:'Jc:~·,·,....-'-"'·!..c •~• .~.............. 2 1 81 160 8 216 2-3 3-4 '384 ----=' 5 ROArJfAY:PARKS HIGHWAY TO DEVil CANVON OH SOUTH SIDE OF SUSITNA. DEVIL CANYON TO VAlAHA ON HORTII SlOE OfSUStTHA. ..--- 1 356 228 5 123 65* 16 2-3 oo .---~ 4 ROAilrIAV:DE HAL I HIGHWAY TO WATANA. RAIL.GOLD CREEK TO i)fVIL CANYON ON sOUnt SI Of OF SUS- IINA.NO CONNEC- TING ROAD. ...... "'-...-- 392 1 91* 1 228 157 2-3 1 i ~.-.......................-- 3 ROAlMAY:DENALI HIGIIWAY TO "'AlANA. PARKS IIIGHWAY TO DEVIL CANYON ON SOUTH SIDE OF SUSITNA.NO CONN- ECTI NGROAD. ~-_. Table 4.1 ..Access Plan Costs ................. 2 RAlt:GOLD CREEK T\~DEVIL CANYON &win ANA ON SOUTH SIDE OF SUSITNA. ~..-~ 1 ROAot~AY :PARKS III GHWAV TO DEV.ll CANYON ,.WAlANA ON SOUTH SIDE OF 5USITNA. *Includes upgrading 21 miles of the Denali Highway -~ r;: Major (~·1000 ft) IUnor (dOOO ft) PtAN DESCRIPTION mleage Road RaU Oesigl1 and Construction CostUx!,000,000 ) Maintenance Cost U )(1.000.000) logls Ucs Cost U J(J .000,030) Total Cost ($x 1.000.000 ) Construction Schedule for Innial Access (Years) Construction Schedule for Full Access (Vears) Bridges .....l!I>..._oLJ!>.__ f'" , l L·j .•.•..........:! I \~ I 'tit .;'-~~~"".,..•••..,...j ".~.,..,,._A~,.,........1 ..•'.,.,,_....p _._.1.=,","....."",....."'"-'---=........"'"-'-....-.........="'"-'-'"-' J ~.. ''1\1--- 61 12 ROADWAV:PARkS HI GHlIAY TO DEVil CANVON fiHD WATMA ON NORTH SIDE OF StlSfTNA. ,-• ..-- 172 .121 U 7 258 225 441 359 1 2 2-3 3-4 0 I I 2 Revision:E Sheet 2 of 3 "''iI.J ~.,-- 114* II ROAWAY:DENALI HIGHWAY TO NATANA. CONNECTING ROAh BETWEEN "ATANA AND DEVIL CANYON ON NORTHSIDE Of 5U51TNA. ...----- lO RAIL:GOLD .CREEK TO DEVIL CANYON ON SOUTH SIDE OF 5U5ITNA. ROAlXIAY:DEVIL CANYON TOWATANA ON SOUTHSIDE OF SUSITNA. ....At,;.....-"../ii.!< '-........"""--.- 56 36 16 Ui 126 136 6 6 216 214 348 356 3 2 3 J 0 2 1 . 1 9 RAIL:GOLD CREEK TO DEVIL CANYON ON SOUTH SlOE OF SUSITNA. ROAIlIAY:DEVIL CAI.VON TOWATAHA ON NORTU SIDE OF SUSITH1,. Table 4."..('Cont'd) ~-;I;,,'......,."Ja •l-.....,--'......i"""-"";' 69 8 ROADWAY:GOLD CREEK TO DEVIL CANYON ON soum S1 DE Of SUSITNA. DEVil CANYON TO WATANA ON NOR TIl SI DE Of SUS ITNA. 215 III 9 7 228 216 452 340! I 2-3 3 3 I .0 1 I .~............... 132,* •Il)cludes upgrading 21 miles of the Denali HIghway 7 ROADWAY:OENAU •HIGUtIAY TO WATAWA. PARkS HIGHWAY TO DEVil CANYON ON SOUTH SIDE Of SUS IT"".£OIm- ECTING ROAD ON NORTH S10E Of SUSIT"". --~-- Road Rail HaJor (>1000 tt) Minor «1000 ft) ~ DESCIlIPTIGN PLAN Hilea!{e Design and Construction Cost ($x 1.000.000) l 0 9 t s tt cs CostU)t !:000 .000) Maintenance CostU)(1.000.000) Construction Schedule for Int tlaJ Access (Years) Construction Schedule for Fu 11 Access (Years) Bridges Total Cost (Sx l~OOO.OOO) XI::!:",!",!" '. t I I '. .. .........:!.~!.i .,\ w..~ *.•...••"1_"·,i,itl!. 18 ROA()i~AY :DEHAlI HIGIiWAY TONI\TAHA. CONNECTING ROAD TO DEV.IL.CANYON Off HORTU 5VDE Of 5US- ITNA.RAIL:GOLD CREEK TO DEVil CAN- YON ON $OUTU SI DE OF 5U5fTHA. 102*97* 14 14 200 188 12 II 227 227 439 426 I 1 3-4 3 1 I I 1 Revision:E Sheet]of 3 •-...-~-MC-",a, J1 ROADWAY:DENALI HIGlIWAY TO WilTANI\. CONNECTING ROAD TO DEVIL CANYON ON SOUTH SIDE Of SUS~ ITNA.RAil:GOLD CREEk TO DEVIL CANYON ON SOUTH SIDE OF SUSITHA. :!!#m.-i3...',.......@;,4~ ] 2 2 69 10 1 216 382 156 16 ROA()IAY:GOLD CREEK TO "ATANA ON SOUTH SlOE Of SUSIU'A.COHN- ECTING ROAll TO DEVIL CANYON AND PARKS InGl.~AY. ...~~::q 15 RAIL/ROAlIIAY:GOLD CREEk RAIUlOAD EXTENSION.ROADWAY: TO DEVIL CANYON AND WATANA ON SOUTtl SlOE Of 5U5fTNA. ---- Tab 1e4.1 - (Con t •d) ....~....~....~.tl~....4 ~r ,'i!'mM",i!'ll 64 49 1 1 174 128 9 Ii 215 215 398 349 1 1 3-4 ] 2 1 2 I ~ 1.4 RAIt/ROAOOAlf:GOLD CREEK RAILROAD EXTENSION.ROAI.»IAY: TO iDEVll CANYON AND WATANA ON SOUTtI SIDE OF SUSJTNA.CONNEC- T.ING ROAD TO PARKS HIGHWAY. ~'!""--" '] 3 1 1 2 115 223 345 ~ 59 13 ROADl4AV :PARKS HlrulWAY TO WATANA ON NORTH SlOE OF SUSlTt~A WITH BRANCU ROAD TO SOUTH BANK AT DEVil CANYON. ~,..-- HaJor(~'lOCO ft) Hinor (/1000 ft) PLAN DESCR1PTlDN MIleage Road Rail Ha"nteoance Cost U )(1.000.000) LOt}ls ti csCos t ($x.1.~OOO ,000 ) ..IncJudes upgrading 21 roUes of the Denali Iltghway Total cost (Ix ..000,000 ) Com.tructloo Schedule for Initial Access (Years) Oe~19o and Cons tructi 00 Cos tU)(1,000,000) Construction Schedule for fun Access (Vears) 8rjdg~s ..~..~:;'".....~ ... i L1;, I,! I).., I rt -.., ~"''''".,....,....·._~'....h_·'~.'-'iii .'•...-",'.-----"~::::.""'''''-'-'''.'~;J''''...J<.<~.,.,~..._.,-,~._-•."",,-,'.,"~'-. 'I :':~'" ~,::.....0 ~~> '.W, !o,'4'J 91 14 11 u II 168 221 <131 426 ,. 'A,~ PLAN,18 COMBINED :I ~ I 213 -1 ....,.~~~&i~ J PLAIi 16 I DENALI-MORTII DEVIL I C/llllI~E~- .~A~A1IA-T DEVIL CANYON ~ANYON....~•o 69 61 36 0 0 0 !4 0 156 82 106 101 216 127 100 3 10 4 7 104 382 213 2U 0 3"II 0 -.p.~~.'"...~ ~.':(). ......~AI!l!I\. 23 360 r- TABU 4:.2 -ACCESS PLAN COSTS INITIAL ACCESS WITHIN ONE YEAR o 1 J ~-~ 23 241 I 121 HORTII PLAN 13 I.SOUTHl~ATANA l DEvll·-l,co;~·;~~~--.'-'''~'~;~~A .. CANYON .__4 • _'" J.-_5Z.__~~..1 59 I 69 .1 0 °0 0 95 20 115 I 156 118 ·1 105 I 223 I 115 5 2 7 I 7 218 127 3115 218 r---r-";'.t'u...,. Road Rail DESCRIPTION __'_,_'._s . .,.~ ~. Mileage Construction Schedule for fUll Access (Years) 1-----•.-- *Includes upgrading 21 lines of the DenaH IUghway __JL'~' .---_-_.-_.---------.-__•.----'----_.._.----.....-..-_.,..' -'.u ·••_.._..·•·u "',"__..0-:_,.___,.•'.~. tog is tJcs Cos tU)(1.OOO,O~()r-. liaintenance ($)(1.000.000)r-... SUbtot'l) fix 1.000.000)r"-- IllIpactof Accelerated SchedUleU~1.000.000) To ta I U )(1.000.000) ~._"._..~-----...._.-._._--I ---..-_.__._-- Construction Schedule for Inlttal Access (Years) --•._._···_·_·..··_·_......_...·•••u •.••__._....._._ Construction Cost U )(1,000.000) ..,._-_-----~--~..__..___..__-"""'--.'.-.--,.. ,..",,_..~ k,I. II , I 'il II'~,...e,-",:,jjl~t'1:i *'ill-IA.:---...-!!..~_ct-~ Avoids Prairie Creek concentrattcm area. •..... ---¥.;.1 iii .~ .' ~, ; ..·:jjr:~~ peni U,:.flortft.lli11 . "~iis:o:'~m~ Sheet 2 of 2 Near severt)den sttes we$t of Tsusena Creek. Traverses 'mportint south-fact ng slopes. Removes ftIOreforest thaI';North Route but less than south Route. Crosses Deadman Creek concentraUon:Jrea. Avoids PratrteCreek concentration area. Avoids Fog Lalces-Stephan Lake eartbo-- ranqe. Crosse5 cartbou ringeand moveQ~nt cor- rldorbetween Denali Highway and Susitna Rtver4 Traverses IMPortant south-facing slopes. Removes less forest than South Route but more than North Route • Avol4sFog Lakes-Stephan take wetlands. Highestpotenthl for sec:ondury effects throughpubHc access andrecreattonal development. 'f.#>iii.:l:iit~ftT;r:~ii. SoutU!§l Table 4.3 (Cont'd) ~~•I:"'''·<,;j!,~...~~4;;t;~ Avoids caribou range and movement between Denali Highway and Susitna River. Removes greatest anlOunt of fo ...est. Fewer south-facing slopes are travers~d. Remov2sgreatest amount of forest. Near Prat rie Creek concentration area; crosses movement torrldorhetween Prairie Creek and Susttoa River. • Avoids Deadman Creek area. Near severa)den sites west of Tsusena Creek. Hear Fog Lakes-Stephan Lake caribou e-anges. Fewer 50ulh-'faclngslopes are traversed. Near Fog takes-Stephan Lake wetlands. -Potenttal for secondary effects through pUblic access less tbanOenalt-North Route but greater than H~rth RQute. High potentia!for secondary effects through recreational development of hnds south of Susttna Rher. f~...~VO\_~ !,- Horth (13t Avoids Deadman-Creek con(;entratrion area. Traverses important south-fitcing slopes. Least amount of forest is removed. Avoids den sites. Avoids caribou o-ange and movement cor- rtdorbetween DenaH Jltghway and SusHna River. Avoids fog Lakes-Stephan Lake caribou range. Traverses Imporhnt south-facing·slopes. '...·ast amount of forest h removed. Avoids Fog lakes-Stephan lak~area. Least potential for secondary effects through puhl f c aCCess and recreational deve lopment. Issue Black Bears Brown Bears Caribou Hoose Secondary Effects: l OJ U";: .I !,! 1 ~ II I -. '} "f ~. '1 :2f HEl.... 5 ...REFINEMENT OF SUSITNA DEVELOPftENT -.'tI .~... 5.1 ...1:982 Geotechnical Oesi21!Sonsideration! The purpose of this section is to update the Feasibility Report (Peres!/! 1982a)based on theresul ts of the geotechnical investigations per.., formed during the 1982 slInmer field season. Detail s of the geotechnical progran are provided in the 1980 ..81 Geo- technical Report (Pcr.es,1982b)and"the 1982 Suppl anent to the 1980-81 Geotecht:1ical Report (Peres,1982c).The reader shoul d refer'to these reference reports for a comprehensive understanding of the site geo- technical conditions.Infor mation provided in the following sections is aSLmmaryof that pray ided in these referenced reports. (a)Geotechnical Explorations . The objective of the geotechnical progr<Jll,was to detennine the surface and subsurface geology and geotechnical conditions for the feas.ibl ity stud ies'of the proposed Susitna Hydroel ectric Proj ect, incl ud ;ng the access roads and the transmission lines.1111 s was accompl ished by a comprehensive program of field exploration,geo- technical eval uation,and dan $tud ies over more than three years, ccmmencing in early 1980.The scope of the geotechnical proaran was increased in 1982 in terms of additional field work under P4nendment 3 and 4 to respond to concerns raised by the Power Authority·s External Review Board.The following subsections dis .... cuss the objectives of the 1982 explorations performed. (i)f982 Field Program Stud ies performed during the 1930-81 investigations rai sed a nunber of questions regarding the Watana Damsite,the .Watana Relict Channel,Borrow Site 0,and the Fog Lakes Rel ict Channel.The objective of the 1982 geotechnical exploration program was to suppl ement the resul ts of the previous investigations by perfonning additional detailed explorations of the particular areas of concern.Tnese explorations cons;sted of: -Watana Damsite To map the: •Extent of geologic features identified in previous in- vestigations to incl ude Shears,al teration,and frac- turezones; Bedrock cond itions in the upstream and dO'mlstream por- t a1 are.as;and ·Geology of "The Fins"and II Fingerbusteru shear zones, w:_FH;;"5iib'iiili tt f -11 ",J ;:1 ] J J J[ .' it, "-• fl J 'I f ~ 1 f ! f ...Watana Relict Channel 11'O'itermlne: •Channel geometry; '"Stratigraphy of the channel sed iments ; •Continuity of stratigraph~c sequence; •Material properties; G Ground water cond it i cns ; •Permafrost condit-ions; ...Borrow Site 0 TO'Q"etermine :' •Mater;al properti as; •Stratigraphy; •Material quantities; •Ground water conditions; •Per'mafrost cond it.ions; ...Fog L~kes Relict Channel To aeteronne: •Channel g~metry; ·Strat igraphy of the channel sed iments; ·Ground water conditions; •Permafrost conditions; (b)Watana Site This section summarizes the resul ts of the 1982 geotechnical ex- plorations for the Watana Damsite,Watana Rel ict Channel/Borrow Site D~and Fog Lakes ReI iet Olannel.Each of these areas is dis- cussed separately below.Detailed descriptions of the geology at the Watana site are given in the 1980-81 Geotechnical Report (Acres,1982b)and the 1982 Supp'i anent to the 1980-81 Geotechni cal Report (f1cres,1982c)" (i)Watana Damsite- The Watana.Damsite refers to the main dan area,as well as, the upstream and dO\\fl streem cofferd an and portal areas" -Geo 109i cC onditi ons "Overburden_. The 1982 study found no significant differences ;nover burden thickness or mater;al t.yp~s from those prey i- ously reported.A map showing the top of bedrock sur- face contours and the type and distribution of surfi- cial sediments is shown on Figure.5.1.This map is based on additional seismic refraction surveys and geo- log ic mappi n9 " •Bedrock Li tho 1o9t No significant additional information,pertaining to bedrock 1 ithology was found during the 1982 investiga- tion.A geologic map.,showing bedrock 1ithology,;s shown on Figure 5.2. 'ijjM''i' ~'1' t :' ,'1 f '~ J ;~{t ~ 'I If.. r IIi ·!J 'IJ .J J I' l f f t.. -Bedrock Structure~ .Joints The addit.ion of more than 500 joint measurements to the statistical joint plots has resulted in minor changes to the average orientations and dips of the four joint sets fa ll1d at the si te.Tab 1e 5.1 is a SLmmar y of joint orientations for the overall dansite area as well as the specific areas of the proposed upstre~and dO\W1strean portal s.Joint plots of the dansite area are in the 1982 Suppl anent to the 1980-81 Geotechnical Report (Peres 1982c).Plots for the upstre~and down- strean portal areas are on Fi gures 5.3 and 5.4.Sets I and II remai n the maj or sets with Sets II I and IV be;ng minor,although locally pronounced.-Set I trends northwestward with high apgl e to vertical dips and is the most prominent set.Set I parallels most di3con .. tinuities at the site.Set II trends north eastward and is best developed upstrean of the dan center 1 jne. Set II i.s parallel to frac"ure zones in thi s area.Set III joints trend northward ~~ith moderate to steep dips to east and west.Set II I is not present i nthe up- streamoortal area;however,it ;s well developed in the dOWJ~stream portal area where it paral1 el s shear and fracture zones.Set IV joi'nts are generall y d isconti n,· uous and appear to be due to stress relief.Orienta- tions ara quite variable,bJJt many trend east-west with shallow to moderate dips to the north and south.These :Ioints are discontinuous and appear to be rel ated to stress rel ief from gl aci al un load 'lng. The Susitna River is joint controlled in the daTIsite area.Upstream of the d an center 1 ine,the ri ver par- allels Set II joints"Near the dan centerline it is contro 11 ed by both Sets I and II;and in the downstream area it is control 1erJ by shear and fracture zones rel ated to Set T joints. .Shears"Fracture Zones,and Alteration Zones.v :-.- These features are defined in the PcresReports 1982a and 1.982b.A geologic map showing the extent of these features is shown on Figure 5.3.5i gn;f1 cantgeo log ic features are discussed beloW. Structural Features Three geologic structures preVi- ously identified in the dansite as having potential impact on C;'1 il design are "The Fi ns ll t "Fi ngerbuster", and a wide,hydrothermally altf:red zone.liThe Fins" and UFi ngerbuster~1 were explored in more detail during the 1982 field season.The following paragraphs are a sunmary of the findings"No explorati.ons were per- for-med in thear.ea of the left bank alteration zone .. it'•., ..'P.: f ·;- .~. , ,; 1 r r 1 ] ~1[ 'f .I ~[ 1........• I 1 ~ I r., 'I ( t I Ii • I 1 f• f t f t t t L liThe Fins'~15 shown inrel ation to the dansite on Figur.e 5.2 and in detail on Figure 5.3 This is located on the north bank near the present pl armed location for the upstrean cofferdan 'and diversion portal s'Recon- naissance mapping in this area indicated major shears underlying a series of deep gull ies separated by intact rock ribs.Detail ed mappirlg showed that most struc- tural discontinuities c.rosscut the gull ies rather than lie within them.IilheFins"is an area of major shears,fracture zones,.and alteration zones of various orientations.The strongest trend of these disconti n- uities is northwest-southeast parallel to Set I joints and northeast-south\'i!st parallel to Set II joints. Minor shears were al so found trending at various orien ... tations.The north\\est trending strlJcturesare near- vertical to vertical and consH;t of shears,fracture zones,and al teration zones from less than 1 foot up to 10 feet wide..The most significant of these features are found upstrean of the prOpOsed portal.area..The northeast trending structures consist of fracture zones which are discontinuous and only occur downstream of the proposed portal cuts.These features are up to 6 feet wide and dip moderately south eastward,~o\'4ards the river,to vertical.A series of low ang~e (less than 45·)shears dipping towards the river were mapped primari 1y above the p~rta]area.These shears may cause rock stab;l ity problens during excavation. uThe Fi ns"structure trends generallY from 300 0 .to 310·.To the so uthwest,the structure trend acposs the Susitna River beneath the upstream cofferdan and is exposed to a 1imited extent on the so uth bank.To the north\liest,liThe Fins H is inferred to correlate with a hydrothennally altered zone on Tsusena Creek .. The /I Fi ngerbuster~''is an area of shears,fract,ure zones,and al terat ion zones wil;ch are best expo sed.on the north bank of the Susitna River in the area of the proposed do~stream diversion and .tafl race portal C!' (Figure 5.4).Exposure show t\ttO strong trends of dis- continuities:north'rEst ...southeast and north-south. The north\'Est trending discontinuities consist pi";... marily of shears and associated alteration zones par- allel to Set I joints.Thesestruetures are up to 2 feet wide.Rel ated to the north\'Est trendingstruc ... tures are areas of open j:Jints and loose unstabl erock. Large blocks of detached rock are sl unpingalong the intersection of Sets I,III,and IV joints.The most significant of these areas occurs in the proposed exca- vation area for the spillway fl ip-bucket. The north trending discontinuities are primarily frac- ture zones with minor shears which parallel Set I joints.An exception to this ;s a major shear zone .....!'l.t ....• ,"'r ~it I •r r ,l( ·~r •I, ••• 1 If I {.. *,1 r i 1 r ~ f I r I.. i f ...1 (i ; ) labelled GF7Q,which corresponds with the andesite porphyr y/diorite contact.Th i s feature is up tg 30 feet wide;however,most of the north trending structures are less than 5 feet wide. The main trend of the IIFingerbuster"is northwest- southeast..To the southeast,the II Pi ng.er-buster ll is prroj ected beneath the river and tentative]y carrel ated with shears on the south bank.The extent to the n!orth~st is uncertain due to lack of bedrock exposure. -Groundwater Conditions Resul ts of the 1982 geotechnical explorations support the findings and conclusions set forth in the Feasibility Report (Peres 1982a)except for the depth of water It:::ve]s on the right abutment.The prey lousl y reported (Peres 1982b)ground water level s of 110 to 280 feet deep were erroneous and should read 110 to 150 feet..In addition, geologic mapping revealed additional springs on slopes at the overburden/bedrock contacts (Fi gure 5.2). -Permafrost Conditions.-- The i nterpretat i on of the permafro.st reg ime ~.t the d an- site remains unchanged from tnat presented in the Feasi- oil ity Report. ...Permeability ....."".. The 1980"81 geotechnical investigations confirmed the COE IS (1978)interpretation of the existence of a buriedrel ict channel on the north side of the dansite.The major paten ... t;a1 prob 1ems assoc i ated wi th th i s re lict channel are: -e,~eaching of the reservoir rim resulting in catastrophic fail ure of 'the reservoir;and ...Sub surfac;eseepag ere~ul ti n9 in potential downstream poi p_ i~g and/or lOss of energy. - As a result of these potential p}'"Oblens a supplemental geo- technical investigation was undertaken in 1982 .to define this feature in !llore. detai 1 • ... Loc~tion and ConfiguratiQ.!! '- The Watana Relict Channel is located between the present course of the Susitna River and Tsusena Creek and fills an area from the emergency spillway 1ocation to Deadman Creek. Borrow Site 0 is lo(;ated in the southeast quarter of the channel and overlies the major portion of the inlet area near the Susitna River.. The location of the channel is sho\«1 on the top of bedrO\.'k map (Figure 5.6). The orientation of the re1 ict channel is some~a't irregu- 1 ar but overall it trends north \Est sc utheast. Max imllll overburden thickness of 450 feet. -Geology Twelve stratigraphic units have been delineated in the Watana Relict Channel/Borrow SiteD area (Fig.ute 5.7). These units were differentiated by their physical charac- teristics, as identified in the field, and by their m~te­ rial properties. These characteristics and pro9erties were used to identify the basic modes of deposition which are described on Figure 5. 7.. The sedimentE in the relict channel are interpreted to be Quaternary (Table 5.1) in age and are primarily glacial or glacially related in origin. The oldest sediment in the relict channel are unconsolidated boulders, cobbles and gr·avels (Unit K) found in the deepest part of the thalweg (Figure 5.8). Following deposit·ion of this Unit K, a major gl acittl ada. vance deposited the basal till (Unit J). It is 1 ikely that during this time the Susitna Ri't'er was blocked from its old channel. and forced south to its present day courses. As this glacier retreated a paragl aci5l envi- . ronment. of pond(~ 1 akes and braided streams developed and deposited Unit J'. Further glacial retreat accompanied by 'l minor readvance is shown by the deposition of Unit I. Following deposition of Unit I, the ar·ea experi-.. eneed an interglacial stade which resulted in the erosio\, of the Jnit r surface. Strecm channels cut into this surface and later· becane fi 11 ed with Unit H all uv itm. At the close of th~ interglacial stade, a new ice front advanced <tcross the area depositing the Ge:nse basal till of Unit G'. As melting occurred, a preglacial environ- ment devel opad. Dr~'!riage of the mel twaters appears t;o have been blocked,resul ting in the formation of glacial lakes at or near the ice margin. The varied clays and silts of Unit G were deposited in these lakes. Further retreat of the glacier resulted in the draining of the 1 akes, erosion of the uppar Unit G, and the eventua 1 depositioN of the outwash silty sar.ds and gravels of Units E and F) ''1'., -?ermafrost Conditi ons During the 1980-82 geotechni!::al investigation,a l'ev~sw of the site and regiunaJ qeology w~s undertaken to determine i'f there were any othet plac.~s in tht!Watmu;reseY'voir where bedrock dropped below maximun ~ool elevation.The results of that study i t1d icatad that bedrock drops below A perched water tab 1e ex ists,1ocall y,on top of the impervious Unit G,&nd possibly on top O!Units M,I and J.Pe.nneability testing indicates an average val ue of 10-3 ani sec for more gravel 1y mater;al s,GoJ:d 10-4 to 10-4 an/se-:for t i 11 sand 1ac ustrine depo sits. After retreat of thegl ~cier the area was again subjected to an interglacial period •.During this time,erosion ttJok pl ace resulting inso-rface streamflows and inceptio.n of 1 akes in lowl and areas.Unit 0 all uv iLIII and Unit DI lacustrine clays and silts were deposited at this time. Ou·~ing this time a minor readvance of the 91 acier occur- redin the so utheaste~i'1 portion of the fbrrow 5i te 0 area which s"esulted in the deposition of the I,hit M basal till..At the endo·f the O/D~interglacial,glaciers again advanced,re\l«)rJC1!ng the upp(':;rsed iments of Units 0, GI,'E and F.Later,the glacier bec~e stagnated result- ing,in the in-place mass wasting of the ice and deposi- tion of the ice disintegration Unit C.~ltwater from this ice ,nassresulted in locally re\l,Ork<ing of Unit D• Thi s mass wast;og of thi s last ice mass resul ted in the formation of the nummockykriob-and-.kettl e features \\fIich form tn,e pre~~nt topography.Recent geologic events in the area are confined to post glacial erosion and frost heav ing,as r~presented by Unit AlB. ~Groundwater Conditions The groundwater regime in the relict channel is complex and poorly understood due to the presence of intermittent permafrost,aqu;c 1 ud es,perc hedwater t.?Jl es and confi ncd aquifers..Based on drill iog it appears that possible artesi an or confi ned water tab1 es ex is);in Units Hand J I while several other units appear to be unsaturated. Dr'ill ho 1e samples ami ground temperature envelopp.s from thermistor installations indicate that permafrost in the Watana Rel ict Channel/Parrow Site 0 area ;s primarily freezi ng temperature water rather than so,id phase ice •. Maximun observed depth of permafr'Ost ;s about 40 feet. Most of the visible ice is confined to the annual frost zone (averaging 10 to 15 feet deep)in Units C,D,E and F;afld ttJ Units G,GI and H in permafrost zones.Average gro und 'temperature at depth,with the except;on of sev- er<al 'f~ozen shallow holes,range o.Soc to abo ut 1.Soc .. (;;i )FJq,L akt.:s Re11 ct Channel_....--., I!;f :i~ lII' . 'l 'f t t 1 I f I I I f { '['t ,.r~. ,f ~t i; ,',"T .~~r ll~ "~.f' l l ~-, J l' 'f r ~ l I l I 1 r • reservoir level in several areas on the south bank of the Susitna River in the area of Fog Lakes (Figure 5.9). Preliminary seismic refraction surveys were undertaken in this area during 1'981 with supplanental refraction sur- veys performed in 1982 (kreSl 1982c). •Location and Conti gurati,on The location of the Fog Lakes Rel iet O1annelis shn\tl1 on Fi gure 5 '~9~The rel ict channel 1ies between the bedrock high of the'proposed Quarry Site A and the hill s of the Mount Watana area approximately seven miles to the east . For discussion purposes,the relict channel can be divided into three sect~ons,the west,centra1 and east sections.The west section 1 ies bet\\een the bedrock high of Quarry A and the bedrock high qf the central section. The bedrock surface in this area appears to be a series of ridges and vall eys.Three of these vall eys (from 200 to 800 feet wide)fall tlelow reservoir level. The central secti on f;X tends for approx im atel y 4.5 mil es east-west..Bedrock in this area is reI atively shallow with the majority of the section having bedrock surface above maximtm pool level. The east section of the channel is the largest with a width of from 6000 to 7000 feet wide~Thi s section of the channel consists of a broad area of bedrock above Elevation 2000 flanking a steep sided bedrock gorge trend northeast-so uthwest • -Geology Based on seismic refraction surveys and 1 imited soil out- crops ~three types of sed iments were del ineated in the Fog Lakes Re 1 ict 01 arlne 1: .Surficial deposits •Poorly consol idated 91 acia1 sediments,and •Well consolidated glacial sediments The surficial deposits generally varies fram 0 to 40 feet and overl ies bedrock and the g1 acial units.The 91 acia1 sediments range up to a max imun thickness of 580 feet with seismic velocities from 4,300 to 10,000 feet per second.Th~higher velocity material may be partially to cemp]etely frozen,.Outcrops of g1 acial sediments are rare.Only till was obserVed in out crop,however it ;s likely that other types of glacial ~nd/orglacially­ re1 ~ted sed iments 9i simil aT to the Watana He 1 ict01anne 1 , may be present. Bedrock in the relict channel area.consi sts of the Creta- ceous argil1 ite and graywacke on the west sid e and Triassic mel avolcanic rock to the east (Figure 5.5).The contact between these tMl un its ;s the Ta 1keetna Thr ust FaUltwnose 1ocationand:trend is nearly coincident with the main thaI weg of -the Fog Lakes Rel ict01annel • r __r_ f) ...'\......... ~~.,""} () "".'tf .sj*t Two potential sources (Borrow Site 0 and H)of impervi- ous ,semi-perv lOUS core mater;a1were prev iously.identi- fi r;<i (Peres,1982c)..In 1982 ex plor at;on of Borrow Site D ~onsis ted of geologic mapping,drilling and laboratory test ing •Resul ts of thi s investig ati on showed that most stratigraphi c.units above Un itG are suitabl e borrow material;with Unit ElF eXhibiting the most consistent SUitable properties.Total volllJ1e of borrow mater;&11s about 180 million cubic yards over an area of 1130 acres with an excavated depth of 100 feet.The borrow mate", rials consist of nonJ:flastic silty to silty gravelly sands Permafrost conditions are 1 ikely to be sporadic through- out the area,as evidenced by the ex istence of typical pennafro~t features which incl ude bl ack spruce,hummocky tundra,perched ponds on hi.'1s and ski n flows"Hi gher seismic velocities of sediments at depth indicate par- tially to completely frozen material. ...Groundwater Conditions The groundwater table in the area appears to be rel a- tively shal10w t as evidenced by poor surface drainage and nunerous ponds,1 akes and bags.Drainage of the area is toward the Susitna River to the north and Fog Creek to the so uth.Groundwater grad ients are expected to be steep in the Susitna drainage area and very low toward Fog Creek. -Permafrost Conditions ...Rock Fill Materi a1 Long-term freeze thaw durabil ity testing was compl eted in 1982""The rock samples from Quarry Site At consisting of andesite,showed a maximlJt1 loss after 150 cj1:1es (jf just ov~r 2 percent.It is concluded that Quarry Ais a good source of thennal and water-deterioration resistant rock, for construction material however~reactivity tests on the andesite should be performed to determine its su:ita- bil ity for concrete aggregate. No further direct exploration or testing was conducted in Quarry B.However,mapping in the area related to the Watana Re 1 iet O1anneJ confirmed the prey 10 us concl usionG regard ing the gsneral unsUitability of this site. ""Core Mater;al . (iv)Constructi on Materi al Invest i gat ion Investigation of quarry and borrow sites continued during 1982,however the emphasis on this ~rk was in Borrow Site O.Detailed discus,sion of these sites is presented in Acres Report 1982b .. /[' l'f 'fIf j 1'f r I j ~. ;C J[', t", i t t , t 1 j' ; ;, I 1 •• f ~ { I f,,. I 'l o ...Granul arMater;al (ii )Groundwater.Condit;ons Grc und water re ad i ng s dur i n9 1982 cont i n ued to sho w a se a- S-0nal f1.uctuation;n t~e t\\O north abutment ho 1es (BH-1 and BH ..2)wlth the.1evel 1n BH~l fluctuating from about 50 to 150 vertical feet below the surface,.andBH ...2 show;ng Thermaneter read iogs indicate that a significant portion of the borrow materials are below freezing in the natural state,however t no temperature below ~~2'C has been detected.In addition,1 ittle eVidence;Of iC~was observed in the bar;ng.Based on the above,~~~ttt~f 'ost is not con- sidered to be a problem in borrow site ~4,f·elopnent. No work with the exception of continued therm1s~orread­ ings,was perfonned in Borrow Site H.These readings sho\Ed that in all but one ho 1e,the temperatur'es below the active zone are about +l·C • derived from ice disintegration,all uv ial outwash deposits (Units C,0,ElF);and local zones of till (UnitM)and 1acustrine d~po sits (Unit 0 I)"Detai,1 ed materi al proper- ties for Borrow Site 0 are i'1cluded in kres Reports 1982 and 1981c • This section summar;~es the results nf the 1982 geotechnical in- vest;9 ati ons for theOev;1 Canyon d ansite.The \-tJrk during this time involved completion of 1aboratory testing of quarry gnd con- crete aggregate material begun in 1981,and reading Of bct~ehale instrunentation installed in 1980-81 far groundwater and tempera- ture monitoring at the dansite.Detai1eddi'scussions of the re... sul ts of thi s work are in Peres 1982c Repor~.• (f)GeOlogic ~onditions No geologic investigations were dO'ne at the Devi1 Canyon dal1S1.te in 1982 • Granular material for fil tel'",shell s and concrete aggye- gate will come primarily fran Borrow Sites E and I.Work in these areas consisted of geolo,gic mapping of surficial deposits and completion of 1 aboratory testing.Mapping did not reveal any conditions vilich would change the data asslIT1ptions or reserve calculations presented in h::res Report 1982c. Freeze-thaw tests perfonn~on aggreg ate from the Borrow . Si tes E ar.d I showed losses of 2.3 to 7.8 percent after 140 cycles.The results of the·absorption,soundness and abrasl0n tests show that the aggregate meets the appl i- cable st;,mdards for general strt.etural and dan ~onstruc­ tion.Reactivity test results of the aggregate with c~ent show negl ig ib 1e adverse re.activ ity .. De v;1 Canyo n Sit e-(c) I t 1 -t • 1 1.. I '.t'-I' ·~f~" 1 ; ;'f .1t:" ,1 -' water levels equal to or slightly exceeding the carlar ele-. vation of the hole.Until fail ure (jf the BH piezometer near the lake on the south bank,the readings indicated water levels varying 'only a few f~et from lake level. Permafrost Conditions. Gran u1 ar mater;al s wi 11 come from Borrow 5i te G and po s- sibl y Quarry Si te K (Peres,1982b).Sampl es from both areas were tested for suitab i1 ity as a construction mater;al . -Granu'ar Material This area wa~l identified as the source for all concrete aggreg ate,grout sand')and til ter gravel s and sands.The resul tsof general aggregate suitability tests show that the materials are well within the limits for general con- struction use in concrete,and tnelow absorption.and high aorasion resistance indicata prohable suitability -Borrow Sits G The~istor readings in SA-1,BH-2 and BH-3 during 1982 con- firm the prey iaus data presented in the 19B0-81Geotech- nieal Report (/~:res 1982b).No permafrost 'was fOll1d in either the bedrock or surficial material at or arollld the dansite.The depth of annual frost penetration in bedrock is about 10 to 18 feet:l with the deepest frost penetration being in May and June.Depth to zero annual amplitude ranges from 40 to 100 feet. (iv)Permeability rt>additional data pertaining to rock permeabil ity was gathered during 1982.The interpretation presented in the Acres 1982b Report remains unchanged. (v)Devil Can~~Reservoir Geolog,l: Geolag ic mapping was perfonned in the upper reaches of the pY"oposed Dev il Can~n reservoir as part of the Watana dan- site area regional mapping.This area is discussed in Section 5.1(b )8 (vi)Construction Material Investisation Construction material investigation during 1982 was 1 imited to the completion of laboratory testing begun during 1981 of granul ar materials for filters,.shells and aggregate. No further i nvesti 9 ation for core mater;al for the saddl e dam was undertaken. (iii) • t t . f 1 ··-r cst 'f J -r J T r 1 ':~r l 'r :1 l:r T T l ;1.'{ for general aggregate use ·in toads,fil ters,and rel ated uses.The freeze ...thaw durabil ity tests show only moder- ate losses up to 150 eyel es. Petrographic analysis of the various material types in Borrow Site G indicate the mate:~'ial near river level to have a more favorable compositi'on and quality than the mater;ql in the upper t~rraLe..Chemical reactivity tests to detennine the effect of fre\!s11 icates on concrete were rll1 on thi slower 1evel mat.~~ri al ..Resul ts ;nd icate the aggregate may have an adt{E'tse silicate reaction. Based on these test resul ts Borro,w Site G appears suit- abie for all uses at the dansite. -QuarrY ,5 ite K- Laboratory testing of granodioritl;frQ'lI Quarry Site K consisted of freeze-thaw dtIrabil ity tests.The tests results showed an 8 percent loss after 150 cycles \Wlich is generally considered unacceptab1e.However,these samples,which were obtained frcm a surface exposure, were weathered and not representai:i.ve of cl ean,fresh quarry rock .. r~fb;'--. I 6 }' ! Ir , ~,..'0 •i.,P',.4 :..~"• .'•~"=>I •'(\.........1 'lt4 '\'~:.........:.....v tl;'t> .'r.'9 ~.'"-.• ~~..;;- (; The se1 ection of a concrete face rockf;ll dan at Watana \Il)uld ini ... ti ally appear to offer economic and schedul e advantages \'them com- pared toa conventional impervious-cor'e rockfi11 dan.For exanpl e,one of the primarY areas of concern with the ea.rth·..core rockf;11 d ail ;s the contro 1 of water content for the core mat-t~ri a1 and the avail able construction period during each summf~~".The core material will have to be protected against fr-ost penetration at the end af each season and the are:a cl eared and prepal'"ed to receivenewmaterialaftereac;h winter.On the other hand,rack- fill materials can be worked ctlmost year-round and the quarrying and pl acing/compacting opera,tiions are nit affected by f~ain and onl y marg ina11 y by wi nter wei.ither.. The concrete facerockfi11 dan \\()ul d al so requi re less fo und ation preparation~since the critical foundation contact area is much less than that for theimpervious.··core/ro.ck foundation contact. The side slopes for faced rockfill could probably be on the order of 1.5:H to 1:or steeper'as compi!red to the 2,.5 and 2.0:H to 1: for the earth-core rockfi]l.This \l«Juld allow greater fle.xibil ity for layOut of the other facilities,in particular the upstream and downstream portal s of thfa diversion tunnel s and the tailrace tun- nel portals.The diversion tunnf:ls could be shorter,giving fur'- thersav i ng s in cost and sc hed u1 f~. However,the height of the Watana DamaS currently proposed is'885 feet,some 70 percent higher than the highest concrete face rock- fill dan built to date (the 525 ...foot high Preia Dam in Brazil com- p]eted ;n 1980).A relY iew of concrete face rockfi 11 dans i i1d i- cates that increases in he.ight have been typically in the range of 20 percent;for excmpl e,Paradel a -370 feet campl eted in 1955; Alto Anchicaya -460 feet completed in 1974;Areia -525 feet com- pleted in 1980.A1 though rect~nt compacted rockfi 11 danshavr~gen- erally perfonned well and rOf;kfill dan ;s inherently stablr:!even with severe leakage through the face,a·one""'step increase in he.ight of 70 percent over ex ist iog structures ;swell beyPnd pre.- cedent .. In addition to the height of the dan,other factors.wh ic.h are bejUnd precedent incl ude the seismic and climatic conditions at (b) (a)I ntroduct i on Assessment between an embankment type and a.concrete arch type dan for Watana was presented in Secti on 9.8 of Acres 1982a Repov't. Subsequent to the submittal of the Fea.sibi1 ityReport,questions arose regarding the potential feasibil ity of a concrete faced dan at Watana in lieu of an emban~anent type..A compari son of these tWJ dan types for Watana are presented in the following sect;e)n. Concrete Face Rockfi 11 Type 0 am ...-...:':~ 5.4 ...t~ain Dam Alternatives -Watana ~..~~~.:a.- r f' r t 1. I 1 l I t. 1 I { l I '-11 /1 ·~r 1r j Lt l!_._~- . ",,~...I ",'.~.,'';."--,.\-'"'.,_..... ...""'"">~'I II·...".'.~~,;0}.--~...-eo Q £r •, . I -..410'"-."-l$,g, •~•."....Q ..fJ-""• \•q~"(ll.I •tt-~•.....I 'it''"<l''',"•.."'..~• .<f li ...~~~~.."I.,c}).•/.1'-4 r'' •..."¥.I -.;;• This section describes refinements made to the general arrange.. ments of the Watana <mdDev i1 Canyon projects since the presenta- tion of the Susitn,a Hydroelectric Project Feasibil tty Report (Peres 1982a).Changes have been made in the follOWing areas: ...'watana proj ect power and outl et facil ities intakes; ...DEN 11 Canyon prqj ect power intake; ...Dlav;l Can}On project mai n sptll way gates; ...Devil Canyon project compensat.ion flow discharge pipe;and ..Dev.n Can.tQJl main access road • Introduction.(a) in the reservoir ~'dch \\Quld take many years and involve severe eco- nomic penalties from loss of generat'ing capacity. NO concrete face rockfill dan has yet been bui 1t in an arcti c env iron- ment.The dra~own at Watana is in excess of 100 feet.and the upper section of the face sl ab will be subjected to severe freeze/thaw c,}(:1es .. Al though the face rockffll dan appears to offai'"schedul E'advantages, the overail gain in impoundment schedule V«Juld not be so significant .. With the earth..core rockfill dan,impoundment can be allowed as the dan is constrtXte;d..This is not the case for a concrete face rockfil1 since thfa ccmcrete face s1 ab is nonnally not constructed until all rockfil1 has been placed and construction settlene11t taken place.The sl ab is then poured ill continuous strips from the foundation to the crest.fIost recent high faced rockfill dans al sa incorporate an imper- vious earth fill cover over the lower section to minimize the risk of excessive leakage through zones which,because of their depth below norma"water level,are difficult to repair.Such a zone at Watana might cover the lower 200 to 300 f~et of the sl ab and require ccmsidel"- able volt.mes of impervious fill,none of which could be pl aced until all othw:-const.ruction \\Qrk had been completed.This work ~uld be on the critical path with respect to impoundment and,at the same time,be subject to interference by wet weather. The t'~types of dan 'l\ere not casted in detail because cost was not considered to be a controlling factor.It is of interest to note 1 how- f~ver,that similar alternatives were estimatec.for the LG 2 project in norther'n Quebec and the concrete face a1ternat iv e was estimated to be about 5 per cent.cheaper!However,the managel"'s,on the recommendation of their consul tants ,decided against the use of a concrete face rock- fill dan for the required height of 500 feet in that environment. In sunrntlry,a concrete face rockfi 11 dan at Watana is not considered appropriate as a firm recommendation for the feasibil it.y stage.of developnent of the Susitna proj ect because of: ~.The 70 percent increase in height over p~ecedent;and .•The possible impacts of high seismicity and cl imatic conditions. 5.5 ...Refinements to .Gen~Ylal Arrangement {, t t t I I t l I t 1 f t 'I ] f 'f J l r r 1 :J J /, U t .~ ,~ 1.."~~:- The Upper Susitnd River basin Interim Feasibility Report,;Jrepared by the Corps of Engineers (COE)(U.S ..Corps 1975). The Corps of Eng;neers report conS;s~...ed ~;mari ly of an eval uation of alternative corridor locations to aid in the selection of,those \'ilich ma,ximized reliability and minimized costs.Utilizing aerial photo- g~·aphs and existing maps,general corridors connecting the project site with k"chorage and Fairbanks were selected.This study was general in nature and was int.ended only to demonstrate project feasibil ity. The IECO/RW.tL\repott uti 1i zed the COE report as background informati on for both econc.,~1ic feast b i lity determi nat;on and route se 1ecti on.The carr;dar sel e.:ted by IECO/RWRA was very simi 1ar to that sel ected by the CUE wi th further defi niti on.The route se 1ected was based on shortest length,access;\)n ityand environmental compatibility"The report also presented a detailed economic feasibility study for the Anchorage- Fairbanks transmission ';htertie. -Tht~Economic Feasibility Study for the Anchorage-Fairbanks Intertie, prepared by International Engineering Company,Inc.,and Robert Retherford Associ ates..(IECO/RWRA 1979). 6.1 PREVIOUS STUDIES 6 -TRANSMISSION FACILITIES The major topics covered;n the transmission studies include: t -Electric system studies; -Transmission corridor selection; Transmission route selection; ....Transmission towers t foundations and conductors; -Substations;and -Oi spatchcenter and communications. The main body of this section is concerned with the transmission studies that have taken pl ace subsequent to the issuance of the Susi tna Hydroelectric Project Feasibility Report in IvJarch 1982 (Acres,1982). These studies inci uded a reassessment of the transmission line corridor with,n the Central Study J1rea,and a ~andacquisition analysis in the NorttB:'-f'{h Southern and Central study areas;the purpose of \'tIich was to fin~··~·;;'.e the alignment,and determine the legal descriptions of the rjght'i '·of-way.The ways in which these studies hav.e affected each of the six major topics mentioned above are discussed in the folloWing sections. The tw~~reviously published reports which contain the most information relevant to the transmission line studies are: Thtssection describes the development of transmission facilities from the ori gi nal Acres ,American Incorporated Pl an of Study of February 1980 through to the fi ling of the FERC LicenseApp1i cat;on in February 1983. r J 'I ~1.... J r '1 I...'I.~,Ii<ll" ;''f I r 1 1 ';j ,'1 f ,W't-i' Deve]opment of the proposed Susitna project requires a transmission systsm to del iver electric power to the Railbelt area.The pre- construction of the intertie system will result in a corridor and route for the Susitna transmission lines betwe~n Willow and Healy.Therefore three areas were identi fied as needing further study: -Northern study area,to connect Healy with Fairbanks; .•Central study area,to connect theWatana and DeVil Canyon damsites With the intertie; Southern stUdy area ~to connect Wi 11 ow wi th Anchorage. The identification of candidate corridors was based on the considera .... tion of previous studies,existing data,aerial reconna;ssanceand limited field studies...Corridors 3 to 5 miles wide,Which met the criteria di scussedin paragraph (a)below,were then selected in each of the three study areas • These two reports together wi th the various subtasl<reports pUbl ished by Acres since the Pl an of Study of February 1980 served as the data ,base for the Susitna Hydroele:ctric Project Feasibility Report of March 1982,to 'w'ilich this report is a supplr.rnento 6.2 -E1~ctri c Systems Studie! SUbsequent to the pUbl ication of the Feasibi 1tty Report in March 1982 (Acres I-g82a)the route of the Inter-tie between Willow and Healy has been finalized.As a result of this the transmission system has under- gone the fa 11 owi n9 changes: At the time the Feasibility Repot-t was published the intertie inter- connected wi:ththe Susi tna transmi ss;on system at Devil Canyon.St nce then the interti e has been re-routed to the extent that it now passes approXimately eight miles to the west of the Devil Canyon damstte. Studies indicated tha"tthe optimum arrangement for connecting to the int~rtie was to construct a.sWitching -station on the south bank ter- races of the Susitna River at approximately river mile 142.The loca- tion of this station,referred t~as the Gold Creek Switching Station ll together with the location of the intertie and other project features is shown on Fi gure 6.1.A si ng1 eli ne di agram and pI an of the swi tch- yard is Il'"esented in Figure 6.2. Following a land acquisition analysis conducted in the latter half of 1982 the .transmission line routing was finalized,and the lengths of the various line sections recalculated.Thus Table 14.3 of the Acres Feasibility Report (Acres 1982a)summarizing the transmission system characteristics has been revised to include the~e updated mileages and the additional sWitching station at Gold Creek.These revisions are presented sentedi n Table 6.1 Figure 14.1 of the Feasibi 1ity Report,showi ng the confi guration of the recommended system was also changed according'ly and is presented as Pi gure 6.3. 6.3 -Corridor Identification and Selectionot_ [1',--• ·~IlIJ4 i 1 1 1 I 1 I 1 1 f.'~ I "~f ·r i :r - Environmental i.t1ventory tables were then camp;1ed for each cor- ridor selected,listing length,number of road crossings,number of river and creek crossings,topography,soils,land ownershipl status,existing and (l"'oposed development,eXisting rights-of-way, scen-ic qual ity!recreation,cultural resources,vegetation,fish, birds,furbearers,and bi g game.These tabl es and a more thorough' discussion of the technical,economic,and environmental criteria in Table 6.2 above,are included in the Acres,Transmission Line Corr;dor Screeni ng Closeout Report of September 1981.(Acres 1981) In addition to these criteria,each corridor was screened for re- liabili.ty.Six basic factors were considered: -Elevation:Lih~slocated at elevations below 4000 feet will be less exposed to severe.wind and ice conditions wtrich can inter- rupt service" -Aircraft:Avoidance of areas near aircraft landing and take- off operations will minimize the risk of power failures. Stability:Avoidance of areaS susceptible to land,ice,and snow slides will reduce the chance of power failures- Selection Criteria= The objective of the corridor selection conducted by Acres was to select feaSible transmission line corridors in 'each of the three study areas,i ..e."northern,central and southern.Technical" economic,and environm~ntal criteria were developed to select potential corridors within each of the throee areas.These cri-. teria are listed in Table 6.2. Based on this analysis 22 corridors were selected;three in the southern study area,15 in the central area,and four in the northern study area.Three of the corridors in the southern study area run in a north-south directi'1n,while one runs northeast to Pellli1er,then northwest to Willow.Corridors in the central area are in two genera 1 categories:those runni ng from the Watana damsi te west to thei nterti e,and those runni n9 no~th ~o the Denali Highway and the Chulitna River.Corridors in the northern study area rtfn either west or east to bypass the Al askan Range, then proceed north to Fairbanks~The location of these corr'idors is shown in the Feasibil ity Report.(Acres 1982a) Screeni.ng Criteri a The sel ected corridors Vlere then subjected to a further eval uat;on to determine \'Ilich ones met the more specific technical,economic, and environmental criteria described in Tabl e 6.3.The rational e for the selection of these criteria is explained in the Closeout Report of September 1981.(Acres 1981) (a) (b) '1 I.. 11 [ f ( f. I Jr' f. I 'r 11 *,.a J f 1 1. 1: ~. ,.', o p ".=-.1 Corridor (2)ADFC Corridor (1)ABCD Corridor (1)ABC -Southern Study Jlrea -Central Study J.\rea -Northern Study Area Descriptions of these corridors and reasons for the rejection ofs::e other corridors are discussed in section 2.F of Exhibit B (Acres 1983). More detail on the screen;ng Pi'"ocess and the spec i fi c techn;cal t economic and enVironmental ratings of each alternative ;s ineluded in Chapt~r 10,Exhibit E of the FERC License Application (Acres 1983)•. However,at the time the Feasibility Report was published the routing of the~oposed access road between the damsites was u'1decided.The location of the access road is of major importance in relation to the transmission line within the Central study area!>both in terms of economics and environmental impact.Therefore,follOWing the selection of the Denal i ...North Pl an as the proposed access route in September 1982 the transmission line corrid!Jr alternative.s in the centr al study area were reassessed. (c)Selected Corridprs In the Feasibility Report (Acres 1982a)the selected transmission cor- ridor consi sted of the followlng segments: -Topography:Lines located in areas with gentle relief will be easier to construct t repair,and mai ntai n in operati on .. ...Access;!,.i nes located in reasonabl e proximity to transportation cor- ridors will be more quickly accessible and,;therefore,more '1aickly repaired if any failures ,Jccur. The screening criteria and reliability factors for each cOl"ridor were evaluated uti'iZi ng topographic maps,aerial photos $I aerial ov'er- flights t and published mate'r'ials.EachcQrridor was then assigned four ratings (one.each for tectmical,economic,and emvironmental consid- erations,and one over'all summary rating).Ratings we're defined as follows; From the technical point of view,rel iabil ity was the main objective. An environmentally and ccanomica"J ly sound corridor was rejected if it would be unreliable.Thus any line which received an F technical rating was assigned a summary rating of F and eliminated from fur'ther consi derat ion. Similarly,because of the critical importance of environmental con- si derati ons,any coy"ridor \'il;ch rece;ved an Frati n9 for environmental impacts was assi gned a summary rat;ng of F,and el im;nated from considerat;on • A ..recommended C -acceptabl ~but not Il"'eferred F -unacceptable i If 1 'f rff' • ·f I I I I r f f r Similarly,because of the critical importance of environmental con- siderations)any corridor M1ich received an F rating for environmental impacts was assi gnld a summary rati ng of F,and el imi nated from consi derati on. - t¢lIi,,-V"'1 "j Corridor (2)ADFC Corridor (1)ABCD Corridor (1)ABC -Southern Study ftrea -Central Study /.\rea -Northern Study ,Area Oeser;pti.ons of these co\"ridQrs and reasons 'for the rejection of the other corridors are discussed in section 2.F of Exhibit B (Acres 1983). More detail on the screening process and the specific technical, economic and environmental tatings of each alternative is i''lcluded in Chapter 10,Exhibit E of the FERC License Application (Acres 1983)•. However.,at the time the Feasibility Report \Vas pUblished the routing of the proposed access road between the ~amsites was undecided"The location of the access road is of major importance in relation to the transmission line wlthin the Central study ar~>~,both in terms of economics and environmental impact~Therefore,"following the selection of the Denali-North Pl an as the proposed access route in September 1982 the transmission lin~corridor alternatives in the central study area were reassessed. (c )Sal ected Corridors In the Feasibility Report (Acres 1982aj the selected transmission cor- ri dor consi sted of the fo 11 owi ng segments: A -recommended C ~acceptable but not preferred F -unacceptable From the technical point of view,reliability was the main objective ... An environmentally and economically sound corridor was rejected if it would be unreliable.Thus any line Which received an F techn'5cal rating was assigned a summary rati ng of F and el iminated from further consi derat ion. -Topography:Lines located in areas with gentle relief will be easier to construct,repair,and maintain in operation. -Access:Lines located in reasonable proximity to transportation cor- ridors will be more qUickly accessible and,therefore,more quickly repaired if any failures occur. The screening criteria and reliability factors for each corridor were eval uat-"d uti 1 i zing tQPographi c maps,aeri a1 photos,aeri a1 ov'er- flights,and published materials.Each corridor was then assigned four ratings (one each for technical,~.onomic,and environmental consid- erations,and one overall summary rating).Ratings were defined as follows~~l[ J -'I ~r 1l' 'I I f { r f f , r. I -Ec:onomi c.- Segments ABC and AJC link Watana With Devil Canyon and,similarly, segments CD and CF 1 ink Devil Canyorwith the intertie. ..'..... ... ~_.l."· .. - Of the 15 corridorsorigi nally considered in the central study area,11 were found to be unacceptable sin~e they had an overall rat;ng of I Fl.The four remaini ng corrfdors were then subj ected to a more detailed evaluation and comparison to determine.Which corridor most closely satisfied the screening criteria. 6.4 -Corridor Reassessment:Central Study Area The four corridors identified as being acceptable in terms of the ~echnical,economic,(!nd environmental crite"'ia described in the Feas .. ibility Report (Acres 1982a)are corridors one,three,thirteen anc fourteen.The four corridors are comprised of the following segments -Corridor One ABCD -Corridor Three AJCF -Corridor Thirteen ABCF Corridor Fourteen AJCD ,.....".,--(', Pt',though both segments are routed be10w 3000 feet;n el ev ati on ,I segment SF crosses more ruggedi'exposed terrain With a maximut:1 ~l evation of 2600 feet.Segment CD on the other hand,tr aver seSi A four wheel drive trail is already in existence on the south side 'f the Susitna River between Gold Creek and the proposed location of tle rai 1head facil ity at Devil Canyon.Therefore the need for new roads along segment CD,both for constructi on and operati on and.mai 11- tenance,is significantly less than for segment eF,wtnchrequiros the construction ofa pioneer road.In addition the jroposed Gold Creek to Devil Canyon railroad extension will also run parallel 1:0 segment COo Another primary economic aspect considered was tte 1ength of the corridors.However,si nee the lengths of segments CD and CFare 8.8 miles and 8.7 miles respectivelYJ this was not a sig- n;ficant factor.Amonqst the secondary economic considerations is that of topography.~egment CF crOSses more rugged terra;nat a higher elevation than :egment CD and would therefore pr'Qve more dif- ficult and costly to construct and maintain.~lence,segment CD was considered to have a higher overall economic rating. -Technica'- In order to more directly compare the four corridors a ITel iminary route 'lias selected in each of the segments.These routes are shown in F1gure 6.4.On closer examination of the two routes between Dev;1 Canyon and the intertte,the route in segment CD was found to tie superior to the route in segment l.Ffor the following reasons: T,~ If ~l ] l I l I 'f f t( I f r !, J r r !I r flatter terrain and has a maximum elevation of 1800 feet. The dis- advantages of segment CF are somewhat offset however. by the Su.sitna River crossing that wi 11 be needed at ri v.er· mi 1 e 150 for segment CD. Overall the technical difficulties associated with the two segments may be regarded as being similar. -Environmental One of the main concerns of the various environmental groups and agencies is to keep any form of access away from sensitiv.e ecological areas previously inaccessible otner tha~ oy foot. Creating a pioneer road to construct and maintain a transmission line along segment CF would open that area up to all terrain vehicle and public use, and thereby 1ncreas2 the potential for adverse impacts to the environ- ment. The potential for environmental impacts along segment CD would be l)"esent regardless of \lilere the transmission line was built sinca thet'e is (\n existing four trileel drive trail., together with .the pro- posed railroad extension in that area. It is clearly desirable to restrict environmental impacts to a single common corridor; for that reason, segment CD is preferab1e to segment CF. Because of pJtential environmental impacts and econom·ic ratings, segment CF was dropped in favor of segment CD. Consequently, corridors Three (AJCF) and Thirteen (ABCF) were eliminated from further consideration. The two corridors remaining are therefore corridors One (ABCD) and Fourteen (AJCD). This reduces to a comparison oj alternate routes in segment ftBC on the south side of the Susitna Ri vel"} and segment AJC on the north si dee These routes were then scrt~ened in accordance with the criteria set out in the Transmission Line Corridor Screening Closeout Report of September 1981 (Acres 1~31). The key points of this evaluation are 0Utlined below: -Economic ~-. .....,...---- For the Watana development, two 345 kv transmission lines will be constructed from Twatana through to the intertie. When comparing the relative lengths of transmissi·on line, it was found that the southern route utilizing segment ABC was 33"G miles in total length compared to 36.4 miles for the northern route using segment AJC. A1though at first glance a difference in length of 2.8 miles (equil- a 1 ent to 12 tmvers at a spacing of 1200 feet) seems si gni fi cant, other factors were taken into account. Segment ABC contains mostly woodland, black ~oruce in segr.tent AB. Segment BC contains open and vmodland spruce forests, low shrub, anti open and closed mixed forest in about equa 1 amounts. Segment AJC, on the other hand, contains significantly less vege~ation and is composed predominantly of 1 ow shrub and tundra in segment AJ and ta 11 shrub, 1 ow shrub and open m·ixed forest in segment JC. Conseque.-:t ly, the amount of clear- i ng associ a ted with segment AJC is considerably 1 ess than with I 1r I ~i I t( ! I o " From the.Jrevious analysis,it is evident that there.are no sig- nificant differences between the two routes in terms of technical difficulty and economics.The deciding factor therefore reduces to the environment.a 1 impacts.The access road routi og between Watana and Devil Canyon was selected because it has the least potential for creating adverse impacts to wildlife,wildlife habitat and fish- eries.Similarly,segment AJC~within which the access road is located~is environmentally less sensitive than segment ABC,for it traverses or approaches fewer areas of productive habi tat and zones of species concentration or movement.The most important considera- tion,however,is that for ground access during operation and main- tenance,it wi 11 be necessary to have some form of trai 1 along the transmission line route.This trail would permit human entry into an area \tlich is re'latively inaccessible at present,causing both direc:t and indirect impacts.By placing the transmission and access road within the same general corridor as in segment AJG,impacts wi 11 be confi ned to that one corri dor.If access and tr ansmi S5;on are placed in separate corridors,as in segment ABC~environmental impacts woU11 d be far greater.. Segment AJC is thus considered superior to segment ABC.Conse- quently,co~;ridor One (ABCD)was eliminated and Corridor Fourteen (AJCD)selected as the proposed route. ----(' The route along segment AJC traverses generally moderately -51 oping terrai-nrangi ng in he;ght from 2000 feet to 3500 feet with 9 mil es of the route bei.ng at an elevation in excess of 3000 feet.Route ABC traverses more rugged terrain,crossing several deep ravines and ranges in elevation from 1800 feet to 2800 feet.In general there are advantages of reliability and cost assoicated with transmission lines routed under 3000 feet.The nine miles of route AJC at ele- vations in excess of 3000 feet wi 11 be sUbject to more severe wi nd and jce loadings than route ABC,and the towers will have to be designed accordingly.However~these additiona~costs will be offset by the constl"'uctiQn and maintenance (l"oblems with the more rugged topography and major river and creek crossings of route ABC .. The technical difficulties associated with the two segments are therefore considered similar. -Environmental segment ABC.,resulting in savings not only during constr'uction but also during periodic recuttinge Additional costs would also be in- cury'ed wi thsegment ABC d.ue to the increased spans needed to cross the Susitna River (at river mile 165.3)and two other major creek crossings.In summary,the cost differential between the two seg- ments waul d Jr0bab ly be marginal. -Technical l "1 ~t I [ , I r .' f r 'f l .oif J II .1 I r 1 I r ,..I. I I .a .. Corridor (2)ADFC Corridor (14)AJCD Corridor (1)ABC (a)Studies erior to publication of Feasibility Report The route sel ection methodology followed in Section 14.3'of the Feasibility Report (Acres 1982a)resulted in the development of recommended routes for .each of the three study areas.The data base used in this analysis was obtained from: . -An up-to-date 1and status study; -Ex i sti ng aeri a1 photographs; -New aerial photographs produced for selected sections of the previously recommended transmission line corridors; -Environmental studies including aesthetic considerations; -Climatological studies; -(ieotechni cal exp 1orat ion; -Additional field studies;and -Public opinions 6~6 -Route Selection Many specific routing constraints were identified during the pre- 1'fmi nary screen';ng,and others were determi ned dur i ng the 1981 field investigations.These constraints were collated,placed on a base map,and a route of 1east impact se 1ected. (b)Studies subseg~ent to publication of feasibility ree.Q.t1 The original corridors which were three to five miles in width were narrowed to a half mile and,after .final adjustment,to a fi na 1i zed route wi th a defi ned r1 ght -of..way. As discussed earlier the routing of the transmission line corridor in th~central study area was changed so that it shares the same general corridor as the access road between the dams and the railroad extension between Devil Canyon and Gold Creek.The final A more detailed explanation of the screening and final selection process,~'#ith particular reference to environmental constraints is given in Chapter 10 of Exhibit E,of the FERC License Application (Acres 1983). -Southern Study Area -Central Study Area -Northern Study Area 6.5 -f.inal Corridor Selection Table 14.6 of the Feasibility Report .(Acres 1982a)which gives.the summary:of ratings for each of the three corridors was revi sed fol- low;ng the chQnge to the Jroposed transmission line corridor in the. central study area,the revised table is presented as Table 6.4. The transmission line corridor J:resented 'in the FERC License Applica- tion thus changed to: f I "I i i I ,.1 :~ 11( I I f I f f f f ~;] ! 6.7 -Towers,Foundat;ons and Conductors The types of towers,foundati ons and conductors to be ut 11 i zed in the transmission system have not changed since the publication of the Feas- ibility Report.In general hinged-guyed x-configuration toweY's,of the type selected for the intertie,will be usedCl Guyed pole-type struc~ tures wi 11 be used on larger angle and dead end structures ;and a These right-of-way Widths were developed assuming the following parameters: -height from tower cross arm to ground 85 feet -horizontal phase spacing 33 feet ..level terrain (less than 10°~lape.)e Uuring final design these right-of-way widths may viiry slightly where difficult terrain is encountered or the need for special tower structures dictate. --,'" 190 feet 300 feet 400 feet 510 feet 1 tower 2 towers 3 towers 4 towers alignment within this section was chosen to parallel the access road and railroad extension to the maximum extent possible.so as to minimize the mileage of new acceSs trail development.It is also desirable to minimize the number of bends in the corridor"to keep "the number of special structures and therefore the cost to a min- imum.With both these objectives in mind the selected alignment, as shown on Figure 6.1 represents the optimum al ignment of the transmi s5i on line based onexi st i ng da'ta. In the latter half of 1982 a land acquisition analysis was con~ ducted alo09·thel ength of the tl"ansmi ss i on line carr i dar,the purpose of 'ntlich was to identify arEof..lS where land acquisitior\would present a problem.Additional environmental studies identifying environmentally sensitive ar~eas were also undertaken.These studies have resulted in the al ignment being refi ned along the Northern and Southern corridor stubs to the extent that most of the land.acquisition (roblems,and environmentally sensitive zones have been avoi ded. The selected transmission line route for the t:,ree study areas is presented in Exhibit G of the FERC License Application (Acres 1983).This route will be subject to Some minor revision during the final design phase once the detailed soils investigations and engineering design are completed. (c)Right-oT-way Pre1 1m;nary studi es have i ndi cated that for a hi nged-guyed XC'O configuration tower the following right-of-way widths should be sufficient.,if , ,( 1 of. ( .~ ( f I f "~l "i "I ~"~ .' :F iti"~.. 'f :r. ~.[ , (il 1f I it j'n I t Select:gwttle Nl.iaf• locate in 12!~iaity to axistinq tr8n8Pa1'tatian =rridars tr.1 r-=iUJ:ata maint:8I'IMC!t ~t'ePUl's. MtnilitUlt \fie..c=oainlp. AvcUd I1lQUft~·at.... t.acata in ~raximi.ty to existing l:ran~rtatian =1"1"idDrs CO ['lJduc:ac;~tn.:tian COtIts. .. Camect lIfil:h Interti..near Geld C:o....Willow. and ","J;y.Cannect Healy to F'airfJ.....CQn_ IWCt Wllla..,CO-Aftcnargge. Avo.id .....tainault ana•. Selection Minimize.-Adit ~• M1ni.-Ua·sucn an•.to ~clearing c=sts. H1nimUa'~'ttltticnt"equ.i~SfMCial d..j.qntI•. A'Joi.d ftxistinq Or'proposed'dlNelaplld areu& P~ralle.l. Avaid h..vily l:inaered are••• Avoid pri~ate lands,wildlife refug...p~~ Select gentlll raliaf. " Criteria• EJ,.,Cian ReJ.iar Acr:Mra. . TlJJDend At.. OJNe:l.OF Int t:xistinC;Tran_;saicn R1gnt-af~." una.Statua r~~ Veqtltatian Type 1.T~icaJ. -'Pr~ z.~ -;tt':_~ r ( r rJ 'r... r I TABU:'§:+'SUMMARY OF SCREENING RESUL rs --" 1 R A T I N G SCorridort::nv.lean.Jeeh.Suwntary -Southr,.1"n study Are., (1)AbC'C C C C-(2)AIFC A A A A(3)AUt:r C A F'(;-Cantal stucty Are.' <:'(1)ABeD C'..c:"c:(2)....8£CD r C C r(3)A.JCF C C C C(4)ASCJHI F'F'F'~(5)ASECJHI.F'F'F'F'(6)CSAHI F'C F'F'(7)CEBAHI r F'C F'(8)CSAG F'F'C F'(9)CEBAG F F'C F'(10)CJAG F'F'C F'(11)CJAHI F'C C F'(12)JACJHl F'F'C F'(13)ABCT G c c=.c:..(14)AXD,~A ,..A-(tS)ABECF c C F' •-Northem Study Area *(1 l-ABC A A A A(2)ABCC c A C C(3)A£IX:F'C F'F'(4)AU F'C F'r A -r~-C =acceptable but nat p:efer~'i F'-unaccapttlble- *Indicsi:etl selected corridor. r flf[ii .I ... t t. t l4,,, 1 t L. II '.~~r .... "r' " ..: r '1 :f 'J 1 'l ''1 "f':i~. !, ~..bi;, This section describes the process used for derivation of construction costs and discusses the Code of Accounts established~the basis for the estimates,and the various assumptions made.in arriving at the esti- mates.For genera 1 Cons;stency wi th pl anni n9 studi es,a 11 costs deve1op':d for the project are in January 1982 dollars. The total cost of the Watana and Devil Canyon projects is summarized ;n Table 8.1~A more detailed breakdown of cost for each development iz presented in Tables 8.2 and 8.3. 6.1 -Construction Costs 8 -ESTIMATES OF COST -Access Plan 18 replaced Plan 5 (see Section 4); -Intake quantities were revised; -All work was reestimated on the basis of IO-hour shifts; -The di scussion of operation and maintenance costs wa,s rewritten and Table 8.5 was added to show the breakdown of costs;and -The cash flow curves were revised and Table 8.6 was added. This section,originally included as Section 16 in the March 1982 issue of the Feasibi lity Report,presents estimates of capital and operat.ing costs for the Susitna Hydroelectric Project,comprising the Watana and Devi 1 Canyon develojJments and associ ated transmission and access faci 1- ities,which have been updated as a result af on-going studies.-The costs of design features and facilities incorporated into the p~oject to mitigate environmental impacts during construction and operation are identified.Cash flow schedules,outlining capital requirements during planning,construction,and startup are presented.The approach to the derivation of the capital and operating cost estimates is described. ..Changes Which have been-made in the Watana cost estimate include: Access Plan 18 replaced Plan 5 (·see Section 4); All workl eadi ng up to diversion was recasted for an acceleratedschedule; -Storage facilities were provided at Cantwell,and an item for operation and maintenance of these facilities was added to theestimate; -Mater;al prices were revised to reflect the larger transportationroute; -Qu ant i ties were revi sed for the i nt ake and spi llway; -All work,other than noted above,was estimated on a basi s of 10 ...hourshifts; -Construction power was re-estimated based on direct generation atsite;and Contingencies were evaluated for each account . Ch anges whi ch have been made in the Dev i1 Canyon cost est i mateinclude: ill'- f'•I :I ,r 'f 'f ~f" .r. i •tr"',r- .......r r .,{ rt;;>~~.., L',,' L, L Lj.•.".."", It. ~-.-J L t.._( (a)Code of Accounts Further subdivision within these groupings was made on the basis of the various types of work involved,as typically shown in the fa 11 owi ng ex amp 1e: Production Plant Reservoir,Dam,and Waterways Main Dam Main Dam Structure Excavati on Rock Costs for engineering and admi n1 str at ion. Descdltt ion Costs for structures~equip- ment,and fac;lities necessary to produce power. Costs for structures,e4 ui p- ment,and facilities necessary to transmit power from the sites to load centers. Costs for equipment and fac;li- ties required for the operation and maintenance of the produc- t ion and transmi ssi on pI ant. Co sts th at are cOlTInon to a number of construct i on act i vi- ties.Fa r t his est i mat e,on 1y camps and electric power costs have been included in this group.Otherindirect costs have been included in the costs under producti on,trans ... mission,and general plant 'costs. Group-' Production Plant Indirect Costs Transmission PI ant General PI ant Estimates of construction costs were developed using the FERC for- mat·as outlined in the Federal Code of Regulations,Title 18 (Code of Federal Regulations 1981). The estimates have been subdivided into the following main cost groupings; Overhead Constructi on Co sts -Group: -Account 332: -Main Structure 332.3: -Element 332.31: -Work Item 332.311: -Type of Work: IJl" 1:[. " 'I J~f: I 1[I1!c. HIt•• 1" L t L t I',, L L L ') ";l ,4 ~ ',~r 'f J- 'r'ii. T T 1· ~.-.. 1, r ~I I L,- Ll• l r 1 l L l(;.',.j {b)'&proach to Cost Estimating The estimating process used generally included the followingsteps: -Collection and assembly of detailed cost data for labQr~mater- i al,and equipment as well as information on productivity,eli .. matic conditions,and other related it~s; -Review of engineering drawings and technical information with regard to construction methodology and feasibility; Production of detailed quantity takeoffs from drawings in accor .. dance with the previou~ly developed Code of Accou(1ts and item 1i sti ng; Determi nat i on of di rec t uni t costs for each major type of work by development of labor,material,and equipment requirements; development of other costs by use of estimating guides,quota- tions from vendors,and other information as appropriate; -Development of construction .ndirect costs by review of labor, material equipment,supporting facilities,and overheads;and Deve lopment of construct ion camp size and support requi rements from the labor demand generated by the construction direct and 'j ndi rect costs. The above steps are discussed in detail in the following: (c)Cost Data Cost information was obtained from standard estimating sources, from sources in Al aska,from quotes by major equipment suppliers and vendors,and from recent representative hydroelectric pro- jects.Labor and equipment costs for 1982 were developed from a number of sources (Alaska 1982;Caterpillar 1981)and from an analysis of costs for recent projects performed in the Alaska environment. It has been assumed that most contractors will work an average of two 10-hour shi fts per day,6 days per week.Due to the severe compression of construction activities in 1985-86,it has been assumed that most work in thi s peri ad wi 11 be on two 12-hour shifts,7 days per week. The 10-hol:r work shift as,~umpt;on provides~for high utilization of construction equipment and reasonable levels of overtime earnings to attract workers.The two-shift basis generally achieves the most economical balance between labor and camp costs. _.__~l' 1 ,'f',(" r 'f'.. :r I" f ·r I t f 1.: t "t t f f I L 1 Co~,struct i on ~~ui pment costs were obtai ned from vendors on an FOB Anchorage basis with an appropriate allowance includeq for trans- portation to site.A representative list of construction equip- ment requi red for th~pr~ject w.as assemb 1ed as a bas i s for the estimate.It has been assumed that most equipment would be fully depreciated over the life of tht~project.For some activities such as construction of the Watana main dam,an allowance for major overhaul was included rather than fleet replacement.Equip- ment operati ng costs were estimated from i ndustl'·y source data, with appropri ate modi fi cat ions for the remote nature and extreme climatic environment of the site;Alaskan labor rates were used for equipment maintenance and repair.Fuel and oi 1 prices have been based upon FOB site prices. Information for pe\"manent mechanical and electrical equipment was obtai ned from vendors and manufacturers who prov;ded gu;de 1i ne costs on major power pl ant equi pment •. The costs of materi a1s requi red for site construct;on were esti ... matt.d on the basis of suppliers'quotations,with allowances for ~rlipping to site. (d)Seasonal Influences on Productivity A review of climatic conditions,together with an analysis of experience in Alaska and in northern Canada on large construction projects was undertaken to determine the average durati on for var- ious key activities.It has been projected that most aboveground activities will either stop or be curtailed during the period of December and January because of the extreme cold weather and the associ ated lower productivity.For the main dam construction activities~the following assumptions have been used: -Watana darn fill-a-month season;and -Devil Canyon arch dam -a-month season. Other aboveground activities are assumed to extend up to 11 months depending on the type of wo'."k and the criticality of the schedule. Underground activities are generally not affected by climate and should continue throughout the year. Studies by others (Roberts 1976)have indicated a 60 percent or greater decrease in efficiency in construct,ion operations under adverse wi nter conditt ons.Thet"efore,it is expected that most contractors would attempt to schedule outside work over a period of 6 to 10 months. Studies performed as part of this work programi ndicate that the general construction activity at the Susitna damsite during the months of Apr;1 through September wou 1d becomp.arab 1e wi th th at in the northern sections of the western United States.Rainfall;n the genera 1 reg10n of the site is moderate between m;d-Apri 1 and - .'h t'I <• 1111.9_t " -Mobil i zati on; ..Techni ca 1 and supervi sory personnel above the 1evel of trades foremen; ..All vehicle costs for supervisory personnel; -Fixed offices,mobile offices,workshops,·storage faci 1itles, and 1aydown areas,inc ludi nga 11 servi cas; General transportation for workmen onsite and offsite; -Yard cranes and floats; ..Utilities including electrical power,heat,water,artd com- pressed air; Indirect costs included the following: mid ...Octoberranging from a low of 0.75 inch precipitation in April to a high of 5.33 inches in August.Temperatures in this period range from 33°F to 66°F for a twenty-year averagt!.In the five- month peri ad from November through March,the temperature ranges from 9.4°F to20.3°F with snowfall of 10 inches per month. (e)Construction Methods The,construc.t i on methods assumed for deve 1opment of the est;mate and construet ion schedul e are generally consi dered as normal and in line with the available level of technical information..A conservati ve approach has been taken in those areas where more detailed information wilT be developed during subsequent investi- gation and engineering.programs"For example,normal dri l1ing, blastin'g,and mucking methods have been assumed for all under- ground excavation.Also,conventional equipment has been con- sidered for major fi 11 and concrete work..Various construction methods wereconsi dered for several of the major work i terns to determine the most economically practical method.For example,a comprehensive evaluation was made of the means ofexcavatiflg materi al from Borrow Site E and the downstream river for the Watana dam shells.A comparison of excavation by dragline, dredge,backhoe,and scraper bucket methods was made,with consideration given to the quantity of materi al avai lable, distance from the dam,and location in the river or adjacent terraces. (f)Quantity Takeoffs Detai led .quant i ty takeoffs were produced from the engi neeri ng drawings using methods normal to the industry.The quantities developed are those lis'i:ed in the detailed summary estimates in Appendix C of the Feasibi lity Report (Acres 1982a). (g)Indirect Construction Costs Indirect construction costs were estimated in detail for the civil construction activities.A more general evaluation was used for the mechanical and electrical work~{ [ t ,r~ 'r T' 'I T" r f ·f ,. l.t-J It 'I ~1' L, l I I 1 1 ,.l ·t'~\I.I·--'J'....?~.•....•....."••.'.•i1........J\1".'.••.. 11 f - rJ'eo<........f· I t ~ ;"'-",,]---,'. -Financing of progress payments has been estimated for 45 days, .the average time between expenditure and reimbursement; -Holdback would be limited to a nominal amount; -Small tool s; -Safety program and equi pment ; ..Financing; -Bonds and securities; -Insul'"ance; -Taxes; -Permits; -Head office overhead; -Contingency allowance;and ...Profit. -Project all-risk insurance has been estimated as a contractor's i ndi rect cost for thi s estimate,but it is expected that thi s i nsu rance wou 1d be ca rri ed by the owner;and -Contract paekaging would provide for the supply of major mater- ials to contractors at site at cost.These include fuel,elec- tric power,cement,and reinforcing steel. In devel opi ng,contractor's indi rect costs,the foll owi ng assump- ti ons have been made: -Mobilization costs have generally been spread over construction items; ...No escal at;on allowances have 'been made,and therefore any ri sks associated with escalation are not included; 8.2 ..Mitigation Costs As discussed in previous sections,the project arrangement includes a number of features designed to mitigate potential impacts on the natur- al environment and on residents and communities in the vicinity of the project.In addition,a number.of measures are planned during con- struction of the project to mitigate.similar impacts caused by con- struction activities.The measures and facilities represent more costs to the project than'woUld normally be reqUired for safe and efficient operati on of a hydroel ectri c development.These miti gation costs have been estimated at $153 million and have been summarized in Table 8.4. In addition,the costs of full reservoir clearing at both sites have been estimated at $65 million.Although full clearing is considered good engineering practice,it is not essential to the operation of the power facilities..These costs include direct and indirect costs., engineering,administration,and contingencies. JI ( 1 { 1 n( J ,1 I,: f., I I t l L; L, !",e. : -~,!'L~·b !G1 ...~) J,n~ J' I -i l'-'''''''-~ Engineering and Project Management Construction Management .Procurement A number of mitigation costs are associated with fac;lities s improve- ments,or .other pro~rams not directly related to the project or located outside the project boundaries~These would include the following items: .Owner's Costs -Caribou barriers; Pi sh channe 1s; -Fish hatcher;eSj Stream improvements; ...Salt licks; -Recreat;ona'i faci lit;es; -Hah1tat management for moose; -Fish stocking program in reservoirs;and -Land.acquistion Ct;ist for recreation. Iti s anticipated that some of these features or programs wi 11 not be requi red during or after constructi on of the project.In this regard, a probability factor has been assigned to each of the above items,and the estimated cost of each reduced accordi ngly.The estimated cost _'!' these measures has been covered in the cor ~ruction contingencyo A number of studies and programs wi 11 be required to monitor the impacts of the project on tf,e envi ronment and to deve lop and record various data during project cm~struction and operation.These int~lude the following: -Archaeological studies; -Fisheries and wildlife studies; -Right-of-way studies;and -Socioeconomic p~anning studies. The costs for the above work have been estimated to be included in the owner's costs under project overheads. 8.3 -Engineering and Administration Costs Engineering has been subdivided into the fol"lowing accounts for the purposes of the cost estimates: -Account 71 -Account 76 The total cost of engineering and administrative activities has been est;mated at 12.5 percent of the tot a1 constructi on costs,inc 1udi O:i r ! '1 1.1 il~ if 1:~ .1 ~ (1 ,i ., f I. t of I 1f I I( -Feasibility studies,including site surveys and investigations and logistics support; -Preparat;onof a license application to the FERC; -Techni cal and admini strat i ve input for other federal,state,and local permit and llcense applications; Overall cQordination and adm)nistration of engineering,con- struction management,and procurement activities; Overall planning,coord"ination,and monitoring activities related to cost and sCrtedule of the project; -Coordination with and reporting to the Power Authority regarding all aspects of the project; -Preliminary and detailed design; Technical input to procurement of construction services,support services,and equipment; -Moni tori ng of construct i on to ensure conformance.to desi gn requirements; -Preparati on of startup and acceptance test procedures;and -Preparation of projt:!ct operating and maintenance manuals. ConstrLlcti on Management Costs Construction management costs have been assumed to include: -Initial planning and scheduling and establis'.ment of project procedures and organization; -Coordi nati on of onsite contractors and constructi on management activities; -Administration of onsite r.ontractors to ensure harmony of trades,compliance with applicable regulations,and maintenance of adequate site securi.ty and safety requirements; '"Development,coordinatir,m,and monitoring of cOnstruction schedules; -Construction cost control; -Material,equipment,and drawing ccntro1; -Inspection of construction and survey control; -Measurement for pajment; -Startup and acceptance test for equipment and systems; Compilatibn of as-constructed records;and ~Final acceptance. (a)Engi neeri 09 and Project Management _Costs These costs include allowances for: (b) contingencies.This is in general agre~ment with experience on projects simi 1ar'in scope and complexity.A detai led .breakdown of these costs ;s dependel"'t on the organizational structure established to undertake design and management of the project~as well as more defini- tive data relating to the scope and nature of the various project components.However,the main elements of cost included are as follows: r 1 'rI 1. .L '1' II .-; I L f : I 1 1 I t L, I " I J ~f J f' 'r ~~.~ti' ",J ·-f .f I •(:' ) l'r,1 f ( 11. ll. 11 4..' f f 1_ !• L. I 1 1 1 I I ~'."".,~) _. Procurement costs have been assum~d to include: -Establishment of project procurement procedures; -Preparation of nontechnical procurement documents; -Solicitation and review of bids for construction ser'vices,sup- port ser,,;ces,permanent equi pment,and other i temsrequi red to complete th~project; -Cost administration and control for procurement contracts;and Quality assur'ance services during fabrication or manufacture of equipment and other purchased items. (d)Ownerfs Costs Owner's costs have been assumed to include the fo'lowing: ,-Administration and coordination of project management and engineering organizations; -Coordination with other state,local,and federal agencies and groups having jurisdiction or interest in the project; -Coordination with 1nterestedpublic groups and individuals; -Reporting to legislature and the public on the progress of the project;and -Legal costs (Account 72). 8 ..4 -Qperation,Maintenance,and Replacement Costs The fac;lit1es and procedures for operation and maintenance of the project are described in Section 15 of the Feasibil,ty Report (Acres 1982a)0 Assumptions for the:ize and extent of these faci Tities have been made on the basi s of experi ence at large hydroe lectri c developments in northern climates.The annual costs for operation and maintenance for the Watana development have been estimated at $10 million.When Devil Canyon is brought on-line~these t:osts increase to $15.2 million per annum.Interim replacement costs have been estimated at 0 ..3 percent per annum of the capital cost. The breakdown in Table 8.5 is provided in support of the allowance used in the finance/economic analysis of Susitna Hydroelectric Power Development.It is based on an operating plan involving full staffing of power p1ant and permanent town 5i te support with a total of 105 personnel at Watana with another 25 when Dev;1 Canyon comes on-line. Thi s prov;des manned supervi sory staff on a 24-hour,3-shi ft basi sand maintenance crews to handle all but major overhauls.Overhauls would involve contracted labor for which a nominal allowance has been allowed ..It recognized that major overhauls are normally unlikely in the fi rst 10 years or more of plant 11 fee In earli er years,thi s a1~owance \I.as a prudent provi s1 on for unexpected startup costs over and above those covered by warranty_ .. ,., ~............', .~' t r lt 'j \.¢'1iriP o ii U 'I' , I I······~~~~·-:~--dt d-' - ~'-.-.t;;- The cash flow requirements for construction of Watana and Devi 1 Canyon are an essential input to economic and financial planning studies.The basis for the Cq,$n flow are the construction cost estimates in Januar'y 1982 doll ars and the construction schedu 1es presented inSect ion 9. with no provision being made as s,lch for escalation.Tne cash flow estimates were computed on an annual basis and do not include adjustments for advanced pa}f11ents for mobilization or for holdbacks on construction contracts.The results are presented in Table 8 ..6 and Figures 8.1 through 8.3.The manpower loading requiremerlts were developed from cash flow projections.These curves were used as the basis for camp loading a"d associated soc';oeconomic impact studies .. All costs presented in this section are at January 1982 levels~and consequently include no allowance for future cost escalation.Thus, these costs would not be truly representative of construction and procurement bid prices because provision must be made in such bids for continuing escalation of costs and the extent and variation of escala- tion that might take place over the lengthy construction periods involved.Economic and financial evaluations discussed in Section 18 of the Fe.asi libi lity R-eport take full account of suc;,escalation at appropri .ate ly assumed rates. 8.7 -Cash Flow and Manpower Loadi ng Regui rements The allowance for contracted services also covers he li.copter oper-at ions and ac~ess road snow clearing/maintenance. Allowances have also been made for environmental mitigation as well as for a contingency for unforeseen costs. Estimates for Susitna have been based both on original estimate and actual experience at Churchill Falls.It should be realized that alternative operating plans are possible which::::1iminate the need for permanent townsite fac;lit;es and rely on more remote supervisory sys-~ terns and/or on operations/maintenance crews transported to the plant·on rotating shift basis.Cost implications of these alternatives have not yet been examined .. 8 ..5 - A11 owance for rund~,Used Our;09 Construction At current high levels of interest rates in the financial'marke~11ace~ AFDC wi 11 amount to a si gn;fi cant element of fi nanci ng cost for the lengthy periods requir\~d for construction of the Watana and Devil Ca,nyon projects..However,in economic evaluations of the Susitna pro- ject,the low real rates of'interest assumed wOt!ld have a much reduced impact on assumed project development costs..Furthermore~direct st'ate involvement in financing of the Susitna project will also have a signi- fi cant impact on the amount ~if any,of AFDC.For purposes of the feasibi lity study,therefore,the conventional practice of calculating AFDC as a separate line item for inclusion as part of project construc- tion cost has not been fo 11 owed.Provi 'Si ons for AFDC at appropr;ate rates of interest are made in the economic and financi al analyses descril?ed in Section 18 of the Feasibi lity Report (Acres 1982a) 8.6 -Escalation tl.• II .. 'I t l I • I 1 l 1 f l 1. ,•fi I I tt .r, 11 ··..7 L 'f ( ':Al ~1 ··f t '1 i I if tI t 1 t t t t 8.8 -Contingencl . An 'overall contingency allowance of a.pproximately 15 percent of.con- struction costs has been included in the cost estimates..Contingencies have been assessed for each account and range from 10 to 20 percent. The contingency includes cost increases which may occur in the detailed engi neeri ng phase of the project after mOre compt"'ehensi ve 5i te investigations ~nd final designs have been completed and after the requiremfmts of various concerned agencies have been considered.The contingency estimate also includes allowances for inherent uncertainties in cost of labor,equipment and materials,and for unforeseen conditions wh·h.~may be encountered during construction. Escalation in costs rf'Je to inflat'jon is not included.No allowance has been included for costs associated with significant delays in project imp 1ementat ion. 8.9 -Previously ConsttuctedProject Facilities An electrical intertie between the major load centers of Fairbanks and Anchorage is currently under constructio"..The line will connect exi st i n9 transmi ss i on systems at Wi 11 ow in the south and Healy in the north.The intertie is being built to the ~ame standards as those pro- posed for the Susitnaproject transmission lines and will become part of tbe licensed project.The line will be energized ini'tially at 138 kV in 1984 and wi 11 operate at 314·5 kV after the Watana phase of the Susitna project is complete. The current estimate for the completed intertie is $130.8 million .. 8.10 -Check estimate by EBASCO An independent check esthnate was undertaken by EBASCO Servi ces Incor- porated.The estimate was based on engineering drawings.,technical information,and quantities prepared by Acres..Major quantity items were checked.The EBASCO cheek estimated capjtal cost was approxi- mately 7 percent above the Acres estimate. A meet;ng was held with the Power Authority,EBASCO,and Acres to rev;ew di fferences in the esti mates.It was genera 11 y poss i b1e to recanci le the differences and it was concluded that no major changes were required in the feasibility Report Estima~e .. J r• I' II' f l l~ £ If, ", I l .. ~'htgory ProductIon Plant Transmission Plant General Plant Indirect Tota I Constructf on Overhead C~n$tructfon TOTAL PROJECT TABLE 8.1:SUMMARY OF COST ESTIMATE January 1982 Dollars 5 X 10 6 Watana Dev f I Canyon Tatal •$2,293 $1,069 $3,362' 456 105 561 5 5 10 429 212 64T 3,183 1,391 4,574 398 174 572 $3,581 $1,565 $5,146 1 \~ I I _I'_ 15 ~- "t .~;:~.~~~ REMARKS JOB NUMBE.R .P5700.00 FilE NUMSER P5700.14.09 SliEET__1 OF 5 BY O~E _ cHKO JRP DATE 2/82 ....~Mi.· 2,293 ./ ~ F9&:lslblllty TOTALS (x 106 ) $ I-- t!·£LQ! 21 "", 14 ./ 51 ......V 66 214 '_987 .... 306 ""," 74 "" 1,547 % [., .~ he 106 ) s AMOUNT ~e_/", ~'''''" TYPE OF ESTIMATE APPROVED BY JOl ;...•.~,""Il\ •~i;iJl.,L'l WATANA TABLE 8.2 •LIfu;JIf,~f!\g._~-;~.-~ SUM-MARY '!".,.=. ALASKA POWER AUTHORITY ".".".0 .. DESCRIPTION PROJ£CT SUSiTNA HYDROELECTRIC PROJECT CLIENT ESTIMATE ~:f$5'.~~~ PRODUCT ION PLANT land &Land Rights 5 . Waterwhee Is,Turbl nos &Gensrators D."••• Powerplant Structures &Improvements "••••••••ll'•••• Accessory Electrical Equipment .,."1lI •••••1lI . Reser vol r,Dams &Waterways ••••••••••••••••••••••"' . Subtotal ••••••••0.'••,••e a ••••••0 ••.•••••••••••••••••••"'••••••••••••••••• Miscellaneous Powerplant Equipment CMachanlcalJ . Roads &Railroads 0 ""0. Cont 'Agency .Je •••lie •••••••••••••••.,•••••••••••••••e •••••••••••••••••••• TOTAL PRODOOT I ON PLANT 'II e .. 1!;Jl.2:.':". A~III- No. 331 330 332 334 333 336 335i II l '" I \~? "I~9~.lIl!l!!li b- e,J!.~-"""".~ REMARKS JOB NUMBER P5700.00 FILE NUMBER P5700.14.09 SHEET 2 OF 5 BY DATE CH KO JRP DATE---""2/"'"'"S--Z- oMJ'kil. ..56 ../ 2,749 2,293 ...~. TOTALS (x 106 ) $ s ~"!!'IJ.~~ he 106 ) AMOUNT ~,... ,11,aLh A PPROVEO BY JDt TYPE Of ESTIMATE feasibility 'a!dA,." Wt\TANA TABLE 8.2 ~~-~~~ SUMfAARY ,C;:"\:.;\~~:·;;:::t~'~¥~;~~:~~!;1!7;~';.7 ;;~::~,~<;;:{.()\::t;;::~~}~"r,;?i.t~~ ••••••'•••,••&•••$•••••••:•••••••5 ••0 •••••••••••,•••• it!'_":'"' t\LASKA POWER t\UTHQRITY ~ DESCRIPTION PROJECT SUSITNA HYDROELECTRICffiOJECT CLIENT ESTIMATE ~:-L.:;",:" land &Land Rights . Overhb';;~Conductors ,&Devices ••••••••••••••••••". Scbtora I ••:••_.'_•••••c •••'••••••ee ••0-•••••••••••••••0.,•••••••••••••••••••• ContIngency .0 ••••••••••••••••••••••e"...."••aa,•.,•••••••'••6-.G •••0 ••••••• TOTAL BROUGHT fORWARD TRANSMISS WNPLANT Substatlof.,6 S\#Jtchlng Station Structures &I~rovements ••••'l ••"•••••• Steel Towers &Fixtures ,. Roads &Trails &. SUbstaTion &SWitching Station equipment . TOTAL TRANSM I 5S I ON PLt\NT '. iI:"'~.;..' No. I1111. 353 350 352 356 354 359 I ~f .., l'7')!-I J UJ'.f !-·L--~-:.::r~ fe,I 1 ,f12.-...iif8l!$l' ,..I} 2/82 .. ~~I~ojO ....!!:f.'!I. REMARKS JOB NUMBER P5700.00 fiLE NUMBER P5700.14.09 SHEET 3 OF __5 ~DUE __--_ CH KD JRP "DATE .~"'l!'l~ 2,749 f"':...,l'!l',:!,!! TOTALS Fe8s I bl Iity (x 106 ) $2,754 s ,:; !!"'*"'!\"""'1tl'!:!,!,!,~:'!l.. (x 106 ) $-I I 'neluded under 330 Included under 331 Included under 399 II II ..II "II II II "" It II II "I I /5 I $5./ AMOUNT TYPE Of ESTIMATE APPROVED BY JOl ~~... 1.!.'!':Jl?~" .............~~ TABLE 8.2 WATANA ..l'IJ-:!£~'~.~f"!"""":' DESCRIPTION SUMMARY •••o ••••••••••o ••••-•••••••••••••••••m••e ••~•••••• i:':""'".. •••••~.c •••••••••••••••••••••••o.o ••••••••••a«••••• ALASKA POWER AUTHORITY SUS 'TNA HYDROElECTR Ie PROJECT .t"'_.".' .. PROJECT CLIENT ESTIMATE L.:" Offlce Furnlturo/Equlpment •••••••••e •••••••••••••e ,. Land &land Rights .,••~••••••••••••••••$•••••••••••••• GENERAL PLANT Structures &I rJllrovements •••••••••••,l.. Laboratory Equ I pment 0 "tl.••••0. Stores Equlpmeot ••••e . TOTAL BROUGHT FORWARD CoIl'll'ltJO I cnT Ions Eq u I pment ~"II .. other Tangible Property "••(••••••••••••••••o.e •••••••••••••• Transportation Equipment . Tools Shop &Garage Equipment . Mtsce II anElOUS Equ I pmant II.,•••••••••••••••••11 .. TOTAL GENERAL PLANT Power-operated Equ I pment ••.,•••"....0 ••••••.,•••••••II •••••••.••••0 •••••••~ 1:::.~~. 'No. A~III. ·:u· i ..J \ .'',,---- ) ;. 389 390 391 392 I I 393 I 394~ 395 396 397 398 .399 " ;> Construct'.on Equ I pment e 0 ••.•• III~•I"..j\$$li$,. .J ~.~; REMARKS See Nota J08NUMBER P5700,OO filE NUMBEA P5700.14.09 SHEET._..4 OF 5 8Y .......DATE _ CHKD JRP DATE 2/82 See Note See Note See Note Sae Note .~~ 429 3,183 2,754 (("''On "J!l TOTALS (x 106 ) $ $ s ~~ 56 373 .e·~,!·_~ (x 106 ) $ AMOUNT TYPE OF ESTIMATE fe~slbility APPROVED BY JOl _.- .e::.:_L~ 4---'-,.,~....... '.~"P"l TABLE 8.2 WATANA *'JtmWE..,,~/!.f:"'"",P1£q~It'''''''ZRt SUMMARY •••G ••••••••••••••••G •••••••••••••••••••••••••••• ~ ALASKA POWER AUTHORITY eo ,• DESCRIPTION PROJECT SUS ITNA HYDROELECTRIC PROJECT CLIENT ESTIMATE ~ Super I ntendence II ~lo .. laborExpense ••••••••.•'~••0 '!It ••••••0 06 •••••0<8 a tI •••••••••• I,nsurance .'•••.••••••••••e ••'•••••0 oe •••••It ••••••••••t)••••••••••••••,ee ••• Camp &Conmlssary •••••"'•••••"',0 . Fees •••••••••••••.•••••It •••••••••,8 ••••••••••••••••••0-•••••••••'••••••••• T6mporar~!Construction facll.tles 5000 •••••""'..,.. Subtotal ••'•••••'••••0 ••••••••l'0'••,a ••••••.,Ott 8 ••••'.oS ••••• Note:~St5 Under accounts 61(1 62,64#65, 66,and 69 are line I uded I n the appropr Jate direct costs I Istad above. TOTAL BROUGHT fORWARD INDIREGTCOSTS ConTingency •••••'•••••••••••".....oe •••••••••••••••••e •••••••••••••••e •• TOTAL CONSTRUCTION COSTS TOTAL I NO I REeT COSTS It .. Ae·..... A~III- No. t7 I 'll···..I,t :,','\ '•.••••,',-,,~-,'_·~·~_·"~"~C~~' ....".....;',"--:*'~. ) ..., tL,j,lJi'ii4j l!~-,",IS' ~' ... ......!I\!.'\'ll'!II: c) ... ~ REMARKS JOB NUMBER P5700 Q 00 ---"f FILE NUMBER P5700.14.09 SHEET 5 OF 5 BY DATE .__ CHKD JRP DATE 2/82 Included In71 Not app"cable Included,In 71 Not Included Not Included . ,.'dAZb" 398 3,183 3,581 t·Bli±9l TOTALS (x 106 ) $ $ l"'l*1""'"!tt~!U'e'L'lI ~i' AMOUNT (x 106) TYPE OF ESTIMATE Feasibility AP~ROVED BY JOL .......- t4":d£':t"'l TABLE 8.2 WATANA . '"'".-.....--....~M.~I f!H!c"'.~,~~~ SUMMARY ~ ALASKA POWER AUTHORITY ~ Expenses '"It . ..••..o····················..•.....~....~•.~o .....•.~..G •••••:••••• DESCRIPTION PROJECT SUSITNA HYDROELECTRIC PROJECT CLIENT ESTiMATE ~ :0.......,"'" OVERHEAD CONSTRUCTION COSTS (PROJECT INDIRECTS) Engineering!Admlnlstnstlon ••••••••••••••••"' "''•••I $398 legal TOTAL CONSTRUCTION COSTS BROUGHT fORWARD •••••••••••••••••••••••••••••• Interest •••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••• Administrative &Genera.l Expenses ••('. Taxes Earn I ngs/Expenses Our I ng Construct I on ••••••••••co . Total Overhead c . TOTAL PROJECT COST of. l~'__• No. Alia 71 72 75 I 76 J 77 "':' 80 " '0 ! ·ul,"{ ,.:.--J'i~~__.._.~ ;11 ;., "~_.~'J D __...6.,' ,:;: ~,'o,J::::l REMARKS '"'08 NUMBER P5700 ..00 FILE NUMBER P5700.14.09 . SHEET 1 OF __' ~D~E ~_ CUKO JRP DATE 2/82-- ~l .j l":""'j TOTALS (x 106 ) jH"',,"'m'eo.",h";:.j AMOUNT (x 106 ) $22 72 646 42 14 12. 119- 927 142 I $1,069 --....\~:!'~""~ ............... '~~ TABLE 8.3 DEV IL CANYON TYPE OF ESTIMATE Feasibility APP-ROVED BY JDL ... ~yMP~!ll'\.~~~ SUMMARY r-- ALASKA POWfR AUTHORITY ~ DESCRIPTION PROJECT SUSITNA HYDROELECTRIC PROJECT CLIENT ESTIMATE L " Accessory EJ e.ctrl ca I Eq u I pment It . land &oland Rights . -Su'btoT.al •••••••'.,•••••••_••g ••••••••••••'•••••'••• Waterwheels,Turbines &Ganerators 9 •• PRODUCTION PLANT ConT I ngency e . Powerp tanT Structur~s &llJYlrovements . HI scellaneous Power~'ant Equ!pment(Mechanl CD I)... Reservoir,Dams &.Waterways ••••11I .. Roads &.Railroads Q "•••••••• TOTAL PRODUCTION PLANT ~.. 11 I!:~'... No. A~IRI r? 333 336 332 334 330 331. 335 • f} I I U·( .'.'.:i "-j;)'--:;-f 1~~, } ~I J I I "".....' .~\!'ilii~~ .'j raaC';;;:Jl!lil".-.n~_,'Ne:.kll\ ._~REMARKS InclUded II"IWatana Estimate Included!nWatana EstllYlDte JOB NUMBER P5100.0Q. FILE NUMBER P51QQ.14.09 SHEET 2 OF_.....5c...·_ BY.DATE _ CH KD .JRP DATE 2/82 /' ti;ii";:>il'j 105 • 1,609 ~'!'!!!!"!I" TOTALS h(106 ) $ $1,174 $ , ~ 7 /' '" 34 ..... 21 ,/ 91/', 14 :::::. 29 .." (1""1 AMOUNT (x 106 ) $ TYPE OF ESTIMATE feasibility I~ APPROVED BY JOb _ ~. j~,~I TABLE 8.3 DEVIL CANYON .,:•••'J-;""~,":'.:0~7~7"'-~'~.,;+.il·,;I?~:~"(~I~,~~~~~"~.~~::~.;~.:~. ~~.{€"·h.j~~ SUM.MARY ••••••'•••••••••••••••••••o •••••••~a ••••••'.ft ••• •••••••••••••••••••••·•••••e •••••••••••~•••••••••• ro- ALASKA ..eOWE~UTHOR ITY ~ DESCRIPTION PROJECT SUSITNA HYDROELECTRIC PROJECT CLIENT ESTIMATE ~ SubstatIon &SWitching Station Equipment ••'. SUbst-at I on &Sw Itch I n9 Stat Ion Structures A I ~rovel¥'lents $<I .. Land 4.land Rights "'.". Overhead Conductors &£)evlcas . Steel Towers ~FIxtures ••••••••••••,'-.. TOTAL BROUGHT FORWARD TRANSMISSION PLANT Roads &Tra ll:5 •••••••••••••••0 •••c·.-:•••e •••••••.••••••••••••••• Contingency G •••••••••••••••••••,.,••••••••,•••••••••••~'•••••••••••e ••-••••• SUbtotal •••••••ee _._•••.C\tri ••••0 ••att ••••0 O ••••••8:•• TOTAL TRANSMISSION PLANT ~".~ NCt. A~I(I 350 352 l353 354 356 359 CJ ( L··1i'-.-T~-"-.'.'.".e;':".{~~'/,.~~~T -~~~ o':l,.~:,1 l ~"'I._.....",!,Ill;_J ~. 1·· I I I 1#1,f • •....11'"~' ... ~ :",'~J IncludEJd under 330 In~luded under 331 Inc IudEJd under 399 II II ..... II II n It .... ".. II .. REMARKS JOB r.UMSER P5700,OO FllENUMBER P5700.14,09 SHEET 3 OF~ flY ..,.DATE _____. CHKO JRP DATE 2/82 l::'"~~~~ 5 1,114 !Io'~i TOTALS F8~S It>I II tv (x 106 ) $1,179 s $ .. ~ 5/ -bt ~ (x 106 ) AMOUNT • i),...•...,,1 ,",...' TYPE Of ESTIMATE APPROVED BY JOL ~...~.~~ TABLE 8.3 DEVil CANYON .. .~..r--~"......r- SUMMARY •••~-••e •••••••••••••••••••••••••••••••5 •••••••.....'~.••......'.........................•.•~.. •••••••••••••~•••-••••••••~•••••••••••o ••~•••••• •••••e •••••••••o •••••••••••••••a ••••••c •••••••••• •••••••••••••O •••••G ••O •••••~•••••••••••••••••••••• .~ ALASKA POWER AUTHORITY '" ~ !.,. DESCRIPTION PROJECT SUS lTNA BYDROELECTR IC PROJECT CLIENT ESTIMATE z.....-.- Landa.Land R;ghTs "'Ii ••••••••••••••••••I S Off Ice furniTure/Equipment •••••"•••••••••••••••••••••~. TOTAL BROUGHT FORWARD GENERAL PLANT StrYctures &Improvements ••••••••••o ••••••••••••••••••••••••~••••••••• ST()r'esEqulpment . Other Tangible Proparty.,•••••~,:..,•••••••••• laboratory EqUipment •••{<. Transpor'i"aTlonEquJ pment e •••••••••••••••••••••••••••••• Tools Shop'"Garage EqUipment . Power Operated EqUipment COmmunications EqUipment MI~~ellanEJousEqu.1 pment ,TOTAL GENERAL PLANT I l..t..! No. 111(1 -.;) .. 389 390 391 392 I 393 I 394~ ~ 395 396 397 398 399 .1 ............." • ~(,4~' We ~ REMARKS • ... .,,..,....,,~, --~....-<----...----------- JOB NUMBER P57(iJ.QO FilE NU"'SER P5100.14.09 SHEET 4 OF 5 BY'DATE CH KD JRp DATE 2/82 • See Note Ssetklte See Nota See Note See Note See Note ,I ... ~.._;.... ~j• 212 1,179 1,391 r-..., TOTALS (x 106 ) $ $ $ ~~ 28 184 184 (x 106 ) AMOUNT $ o TYPE OF ESTIMATE feoslbl "ty APPROVED&Y JOl ,.,.....-----".......f~ I ....,-....~ TABLE 8 ..3 OEVllCANYON ~~ .Q,••••••••••••.~•••••••••••Q -.-f .,.~',1......... SUMMARY' ~ ALASKA POWER AUTifllRlTY ~~ '- ..... •d':~'""~..,~,'• "",..'...~....';... J ~p,",t I .... PROJECT SUSITNA HYDROELECTRIC PROJECT CLIENT ,~ t· Temporary Construci{on FacJlltles ••••••••~. TOTAL BROUGHT FORWARD .~a oo .. I NOlRECT COSTS Construction Equ I prnen't <I ''.. Labor Expanse •"',eo c•••"O •••• Camp &.Corrmlssary ••••••••••••"'11 ••• Insurance 00.0 •••••••' Superintendence ,.. Fe as '••••e_•••••••eo •••••••••••••••••••••a "'OG ••••ft.••••_,ct ••a ••••••••••.,•• Note:Costs undEtr accounts 61,62"64,65,66,and 69 are Included In the appropriate dh'oct costs listed above .. Subtotal "•••••••••••••••_a ••e _••••••eo.\I ••••••1)._•••-••'-'•••'••••••_••c •,8 ••••• Cont1ngancy e.-~•••eo -••••«••••••••50 ••••••••e.t.t ••• TOTAL INO IREeT COSTS .•••;)ow •••••••••••••".".. TOTAL CONSTRUCTION COSTS No.I DESCRIPTION I of I-..._._ 41111- 61 62 65 63 64 r I ...--.-------,.ESTlMATE 66· -'69 l ~_.-."..~..._~.1 '-U':"~ll,I ',';, .-.,,:--..._----._..-.---.~~ I If .,.. c I,: IJ r . ~J.,~,~:, REMARkS ...,....,..., Incl Uded)n 11 Not AppllCDbla Included.In 11 Not Included Not InclUded " -.~--..-' 1,391 1-14 1,565 ... ~ TOTALS (x 106 ) s $ :-....i ~ AMOUNT Cxl06,' $.114 TYPE OF ESTIMATE -!~I bl t ltv Ati3PROVEO BY JOL " . ~"'-*"'-11'" ,~ I .....,'~~ .~.........~ i ...,.......... ~-..•..••'"'\'~;:".t:1 fit "__.f...i.:..... 9""•.1 ~..'""~.:......'\• '- SUMMARY --- ALASKA FOWER AUTHORITY SUSITNA HYDROELECTRiC PROJECT """l~ PROJECT CLIENT ESTIMATE -----.,.... DESCRIPTION Eng'nee.'lng &.,"ti . legal !,Kpenses is ••••Oo ••:.a ,.a ~.••e •••••c •••••••$••••••••••••••11 ••• TOTAL ':;ONSTRUCT ION COSTS BROUGHT fOOWAHD oe u et oe h ••• OVERHE!,,':)CONSTRUCTION COSTS (PROJECT IND.RECTS) Admlnlstraflv~&General Expenses c,.. I nterast •••,••••'fa •••-:•••GO,.O .••••.••••••••••••••••••••••••• Taxes'"•••••••••D,.,•••.••••••••~~.,'$••••••••••••••••••••••••••••••••••••0'. Earnings/Expenses ()urlng Construction . Tota'Overhead Costs . TOTAL PROJECT COST ••••••~o •••• N ..I. .4;lll 71 72 75 76 11 80 r TABLE '8.3 -I -""""Ii DEVIL CANYON '<",,~ , y I } I Divkllg~NYON------ 14,600 47,100 1,600 NA 600 NA i"\2..300 1,000 4,100 2,000 400 200 lOa 100 18,400 NA 10,200 9,,000 800 500 85,600 27,400 17,100 5,500 102,':'00 32,900 12,800 4,100 115,500 37,000 152,500 WATA~ S X 10 . S1.8TOTAl TABLE 8.4:MITIGATION MEASURES -SlM4ARY OF COSTS INC~PORATEO IN CONSTRUCTION COST ESTIMATES COSTS !NCORPORATED IN CONSTRUCTI ON EST IMATES Ou1"le't Facl I !1'les Main Dam a1'DevIl Canyon Tunnel Sp I II ~ey a1'Wa1'ana Res'torat f on of Borrow ArM 0 RasToratlon of Borrow Area F Res1'oraflon of Camp and Village Restora1'I on of Construct fon SITes Fencing around Camp Fencing around Garbage Dls90sal Area MUI1'llevel Int~ke Structure CampFac I I 11'les Assoe I ated with trying to Keep Workers OUT ofLoca I Colml,"~ties ResTorat I on of Haul ~ds TOTAl9QNSTRUCTION Engineering 12.5% TOTAL PROJECT l 'f) l~ 1 irJ T' 'Ii J L, ~'l (i'I~ 200 .~. 2,420 480 200 1,000 500 Subtoto'l $4 g BOO '---'"'.J 30 $41'600 500 480 E)(pense Items ;~ DEV It CANYON DEVil CANYON ($~OGJs Omitted) --, 120 1,920 labor .~,~~'~, 400 900 8aO 1,000 900 6,320 ~t . Subtotal $10,000 $10,400 ~...~~ 990 900 340 WATANA Expense 'tems .~ WATANA ($0.00's Oml tted) 540 5,330 Labor '-'.. TABtE 8.5 SUMMARY OF OPERATING AND MAINTENAt\'CE COSTS ~--\c,--~...........,... Power and Transmission Opar.atlonl Maintenance Cont~acted Services f) Permanent Townsite Operations Allowance for Environmental Mitigation Contingency Additional Allowance from 2002 to Replace COmmunity Facilities Total Operating and Maintenance Expenditure Estimate Power Development and Transmission FacilitIes D f':> " " ,. I,l " I.~ }" ~ I"Ifl'.•• I t I .~,~t~,"."~J •....L~J~~) .~..... 'I~"'~ ~-......, "'~--:-~-::-~--...,..-,-----".''"','~.....-¥~--_.-••",\..\~:;;;";:,¥;-;;,",,,,,,g.~...,,,,,,~.;M'i Itt '"0,",.Ii:~""o;t~~.~~~-{,"::.:~' ~ , ~~ \1 ~~...,. ,i~ ~ . ~ 1 '1108/82,REVISED OCVIl CANYON CASH flOW TABLE 8.6 SUSITNA HVDROELECTRICPROJECJ Watana &lkvil Canyon Cumul~tive &Annual Cash flow ~..~ 27.6 27.6 27.6 12.9 40.5 40.5 28.7 69.2 69.2 48.5 117.7 117.7 198.6 316.3 516.3 282.7 599.0 599.0 294.1 893.1 893.1 361.4 1260.5 1260.5 436.5 1697.0 1697.0 624.9 2521.9 2321.9 4.9 6J1 ..1 2928.1 4.9 29j}.0 48.1 475.3 3355.3 53.0 3408.) 68.9 221 ..4 'S07.8.121.1 3629.7 64.6 1j8.0 lS01.2 186.5 3167.7 65.2 65.2 251.7 3a52.9 115.8 1'15.8 361 ..5 3948.1 204.2 204.2 571.1 4152,9 295.1 295.1 866.8 4l 148.0 281.0 281.0 1141.8 4729.0 242.8 ·'242.8 H90.6 4971.8 156.7 156.7 1541..3 5128.5. 17.7 17.7 1.565.0 S146~2- 1565.0 5146.2 ~.''~.,( DEVIL CANYON COffiINED I WATANA OEVIl CANVUN COMBINED JANUARV 1982 DOLLARS -IN MILLIONS ANNUAL CASH flOW A CUMULATIVE CASH flOW (TO END OF YEAR) "-,~ 27.6 12.9 28.7 48.5 198.6 282.7 294.1 367.4 436.5 624.9 606.2 427.2 152.5 73.4 WATANA 3561.2 -- TOTAL YEAR (j 1981 82 03 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 2000 2001 2002 i 1 I I LL! ,,; ;','""i"'",,,-.'._------_....-....~.-" ;> I,I " r \; II~ I"I I 1 \ I"I _.---" At both sites the period for construction of the main dam -is critical; other activities are fitted to the main dam work.A study of the front end requi rements of Watana cone 1uded that i ni ti al access work shoul d commence immedi ately after receipt of license and be completed in the shortest possible time to permit a SUfficiently rapid bui Idup of man- power and equipment to meet construction requirements. During development of the final project arrangement and preparation of the cost estimates (Section 8),the preliminary schedules were modified and refined.As Astimating data were developed,the producti on rates and construction durations were calculated.Networks were developed for the main construction activities and the durations and sequences of act i vi.ties determi ned.The overa 11 schedu 1es were.modi fi ed to sui t. !J This section,originally included as Section 17 in the March 1982 i-ssue of the Feasi bi 11 ty Report (Acres 1982a),descri bes the deve lopment schedules prepared for both Watana and Devi 1 Canyon to meet the on-1 i ne power requirements of 1993 and 2002,respectively.These schedules have been updated as a result of on-going studies;they span the period from 1983 until 2004.Schedules for the development of both Watana and Devi 1 Canyon are shown in Figures 9.1 and 9 ..2.,The main elements of the project have been shown on these schedules,as well as some key interrelationships.For purposes of planning,it has been assumed that ~1<:.:ense will be awarded by December 31,1984. Revisions to the Watana schedule include the following: The pioneer road was replaced by Denali Access Plan 18.Work prior to receipt of the FERC license was eliminated; -Activities leading up to diversion were revised for an accelerated schedule;and The pre-construction of one ci rcuit of the permanent transmi s5i on line from Gold Creek was.eliminated. 9.1 -mparation of Schedules Preliminary schedules were first developed by estimating the durations of the main construction activities and arranging these in logical se- quence..Some act i vityadjustments were then made to reduce excessi ve demands on resources,such as underground excavation or concrete plac- i n9.The preliminary schedules were then used as a basi s for the prep- aration of cost estimates.The schedules were also revie'l/ed for over- all campatability with major constraints such as licensing,on-line power requirements,and reservoir filling. Revisions to the Devil Canyon schedule include the following: ""Denali Access Plan 18 \vas i ncorporated,and the start of access construction was advanced accordingly. 9 -DEVELOPMENT SCHEDULES f if ~ 1 ~f~ r~ 'I I 'f 1 J 1 l' l ; f j r -April 1985 ..April 1985 -JUly 1985 I l ._...".~-"~'" Access Initial road access to the site is required by October 1,1985~ Certain equipment wi 11 be transported overland during the pre- ceeding winter months so that an airfield can be constructed by July 1985.This effort to complete.initial access is required to mubilize labor,equipment,and materials in 1985 for the construction of site facilities and diversion works. Site Facilities Site facilities must be developed in a very short time to sup- port the main construction activities.A camp to house approx- imately 1,000 men must be constructed -during the first 18 months.5i te constructi on roads and contractors'work area h ave to be started.An aggregate processi ng plant and concrete batching plant must be operational to start diversion tunnel concrete work by Apri 1 1986.At site,power generati ng equtpment must be i nsta 11 ed in 1985 to supp ly pOwer for camp and construction activities. Initial access road Site faci lities Diversion (i i) Comnencement of construction: Commencement of conrnercial operations: Completion of construction: Four of six units ready -January 1994 Six units ready -JUly 1994 9.2 -Watana Schedule Four of six units -January 1994 Six units --July 1~94 The Watana schedules were developed to meet two overall project can-strai nts: -FERC license would be issued by December 31,1984;and -Four units would be on-line by the end of 1993. The critical path of activities to meet the.Qverall constraints was determined to be through site access,site facilities,diversion and main dam construction.In general construction activities leading up to di versi on in 1987 are on an acce 1erated schedu 1e whereas the remaining activities are a normal schedule.These are highlighted asfo11ows: .. ·f'"1'. #1"'" [' I 1. r r r''. ~f t, I ! I l" \ 1460 1865 2050 2185 (feet) Reservoir El evati on (feet) -- 1660 1810 1950 2130 2210 Fi 11 Elevation October 15 9 21 34 47 59 62 ,.- ,~~/>. ;' \/ M r¥''. Acc umu 1ated Quantity (yd 3 X 10 6 ) ~ '<I' 6 12 13 13 12 3 Quantity (yd3x 10 6 )Year The progress of work in the main dam is critical throughout the period 1986 through 1992.Mobilization of equipment and start of site work must begin in 1986.Excavation on the right abut- ment,as well as river alluVium under the dam core,begins in 1986.During 1987 and 1988,dewatering,excavation,and foun- d at;on treatment must be camp 1eted ;n the ri verbed area and a substantial start made on placing fill.The construction sche- d ul e is based on the fa 11 owi ng progr am: 1987 1988 1989 1990 1991 1992 1993 The program for fi 11 pl ac;ng has been based on an average six months season.It has been developed to provide high utiliza- tion of construction eqUipment .required to handle and process fi 11 mater;al s .. ,Construction of diversion and dewatering facilities,the first major activity,should start by mid-1985..Excavation of the portal:::<1t1d tunnels requi res a.concentrated effort to allow comp]et';Jn of the lower tunnel for river diversion by October 1986.The upper tunnel is needed to handle the spring runoff by May 1987.The upstream cofferdam must be placed to di vert riverflows in October 1986 and raised sufficiently to avoid overtopping by the following spring • Main Dam (v)lei llways and Int akes These structures have been scheduled for completion one season in advance of the requirement to handle flows.In genera.l,ex- cavation for these structures does not have to begin unti 1 most of the excavati on work has been campl eted·for the'rna;n dam. (i v) (i i n Diversion fr" f . ~; f t, I- f. 1 :r 1 J .~r~ 'r~ f' r 'r. ! L I I 1 (vi)Powerhouse and Other Underground Work.! The first four units are scheduled to be on 1i ne by 1ate 1993 and the remaining two units in early 1994.Excavation of the access tunnel into the powerhouse complex has been scheduled to start in late 1987.Stage I concrete begins in 1989 with start of installation of major mechanical and electrical work in 1991.In general~the underground works have been scheduled to level resource demands as much as possible. (vii)Transmission Lines/Switchyards Construction of the transmission lines and switchyards have been scheduled to begin in 1989 and be completed before com- missioning of the first unit. (vi ii)General ~iJ ....._...._i; .1 i ~;r. Four units -October 2002 The Watana schedule requires that extensive planning,bid sel- ect i or,'and commitments are made before the end of 1984 to per- mit work to progress on schedule during 1985 and 1986.The rapid development of site activities requires commitments,par- ticularly in the areas of access and site facilities Liorder that construction operations have-the needed support. Main access -April 1992 Site facilities -June 1994 Diversion -June 1995 Four units •October 2002 The schedule has also been developed to take advantage of pos .. sible early reservoir filling to the minimum operating level by October 1992"Should this occur,power could possibly be gen- erated by the end of 1992. 9.3 -Dev;1 Canyon Schedule. Commencement of construction: Completion of construction: COllJ11encement of commercial operations: The Devi 1 Canyon schedul e was developed to meet the on-1 i ne power re- quirement of all four units in 2002.The critical path of activities was determined to follow through site facilities,diversion and maindamconstruction. t " r ~r T. r T r ro. J_ I f 1 I i (v)~pi llways and Intake The spillway and intake are scheduled for completion by the end of 2000 to permit reservoir filling the next year. (vi)E.Qwerhouse and.Other UndergroEndWorks Excavati on of access into tht~powerhouse cavern ;s schedul ed to begin in 1996.Stage I concrete begins in 1998 with start of installation of major mechan'ilcal and electrical work in 2000. Transmi 5si on Lj nes /Swi tchyarE! (i)Access The additional transmission facilities needed for Devil Canyon have been scheduled for completion by the time the final unit is ready for commissioning 'fnlate 2001. It has been assumed that site access facilities built to Watana wi 11 ex;st at the start of construction.A ,road wi 11 be con- structedconnecti og the Devil Canyon sf te to the Watana access road including a high level bridge over the Susitna River down- stream from the Devil Canyon dam.At the same time,a railroad spur wi 11 be constructed to permi trai 1 road access to the south bank of the Susitna near Devil Canyon.These activities will be completed by mirl-1994. (if)Site FacilitiQs Camp facilities should be started in 1994.It has been assumed that bui 1di ng$can be sal vaged from Watana.Site roads and power coul d at so be started at thi s time •. (iii)Diversion Excavati on and cQa:reti og of the si ng1 e diversi on tunnel shoul d beg;n in 1995..Ri ver closure al'd cofferdam constructi on wi 11 take place to permit start of dam construction in 1997. (i v)Arch Dam The construction of the arch dam will be the most critical con- struct;on activity from start of excavati on in 1996 unti 1 top- pi ng out in 2001.The concrete program has been based on an average 8-month pI aci ng season for 4-1/2 years.The work has beenschedul ed so that a fairly constant effort may be mai n- tained duri ng thi s peri ad to make best use of equi pment and manpower. (vi i ) T r r 'T ,: 'r· r 'f 1. f / J ~II,,'"S';'.. ~. 1 ,,_~1'f ~~_-.:.....:_:....-,-'.-_....._..~.. (viii)General The development of site facilities at Devil Canyon begins slow- ly in 1994 with a rapid acceleration in 1995 through 1997. Within a'short period of time,construction begins on most major civil structures.This rapid development is dependent on the provision of support site faci lities which should be Com- pleted in advance of the main construction work. 9~4 -History of Existing Project An i nterti e is planned to perm;t the economi c interchange of up to 70 megawatts of power between major load centers at Anchorage and Fai r- banks.Connecting to existing transmiss;onsystems at Willow in the south and Healy in the-north,the intertie will be built to the same standards as those prOposed for the Susitna project transmi 5S;on sys- tem •.It will be energized ini,tial1y at 138 kv.Subsequent to Con .... struction of the Watana project,the intertie \.'Ii 11 be incorporated into the Susi tna transmi 5si on system .and wi 11 operate at 345 kV. Construction of the intertie is scheduled to begin in March 1983.Com- p1eti on and in;t i a1 operat ion is planned for September 1984,we 11 in advance of the anticipated date for receipt of a FERC licefise on December 31,1984. .. ..HtU!__"" iI " l:J.. {I T' • I t !, 'r If 'r or .~r ,J 'f it .~f t _...__..t-' ,<_"-f - Finally,there were severa.l issues raised in reviews of the Feasibility Report.These issues inc 1uded the assessment of Watana,Devi 1 Canyon, and Chakachamna as single projects and an alternative staging from the recommended pl an.They are:. -The impact of changing probabilities in the multivariate sensitivity analysi s; The purpose of th is sect i on is to document the changes and further .:Itudies which have taken place since the publication of the Fe.asibility Report (Acres 1982).There have been few changes in the financial studies presented.For the FERC license application,a calculation for the cost of power was made and a fi nanci n9 plan was selected as the most probable. In August,a report reviewing the Feasibility Study from a financial purview was published by Arlon Tussing and Associates.The findings of this report prompted a reassessment and update of several underlying factors in the financial and risk analyses.The results of those con- siderations are presented in Subsection 10.5. The third area of updat"e is in the generation planning studies whic~ formed the basis of the project economic analysis.Or:te critical factor of change is in the change in the cost of the projects.The impact of the cost change on the economic and financial analyses has been addressed. 10.1 -Introduction.. 10 -ECONOMIC',MARKETING,AND FINANCIAL EVALUATION Simi l.ir to project costs,a change in the proposed project operation has been made s·ince the Feasibility Report.The change resulted from mitigation studies involving the maintenance of downstream flows for fishery spawning.As a result of the operation change,the energy produced by the plant and the monthly d.istribution has changed.The impacts or this shift on project economics have been reviewed. The primary tool used for generation planning studies is the General Electric Optimized Generation Planning (OGP)simulation model.Version 5 of the model was used for the feasibi lity report analysis.In May 1982,GE released Version 6 of the program.The changes in the program and its impacts on study results have been checked and documented in Subsection 10.6. A discussion of p~rcent reserve margins; -Annual system cost components;and -Delay of the project. The following subsections address each of the areas mentioned i ndivi dua Jly. 1 ·r, or r r 'f r L l l' 1: ,r li_ j. I .._.._-....._IiI'I.'·.....__.~ The financing of the Susitna project is expected to be accomplished by a combination of direct state of Alaska appropriations and revenue bondsi ssued by the Power Authority.It is expected that ~lroject costs for Watana through early 1991 (estimated at $3.0 billion in 1982 dollars)will be funded from such state appropriations.Jhcreafter, completion of Watana is then expected to be financed by issuance of approximately $0.9 billion {1982 dollars)of revenue bonds.On the assumpti on of 7 percent annual i nfl at i on from 1982 to the end of con- struction,the $0.9 billion in 1982 dollars will have a then current money value of approximately $108 million as detailed in Table 10.1. These annual par amounts do not exceed the Author;tyl sest imated annual addition debt capacity for the period 1991 to 1995. The revenue bonds are expected to be secured by project power sal es contracts,other available revenues,and by a Capital Reserve Fund (funded by a state appropri ation equal to a maximum annual debt ser- vi ce)and backed by the "moral obl i gat;on ll of the state of Al aska.At the i ssuanceof the first revenue bonds for Watana,expenditures of state appropri ati ons are expected to have funded SUfficient construc- tion progress S"that subsequent construction risks will be relatively sma 11. 10.2 ...Cost of Power One requirement of Exhibit D of the FERC license application was for an annual cost to be presented.As a two-stage (W.atana and Devi 1 Canyon)development with varying levels of energy output and the assumption of ongoing inflation (at 7 percent per annum),the real cost of Susitna power will be continually varying..As a consequence!no simple,single-value real cost of power can be used.For the purposes of the application,the following cost was adopted. Table 0.7 hl Exhibit 0 (Acres 1983)gives the projected year...by-year projection ener~y levels on the first line and on the second,the year-by-year unit cost of power-in 1982 dollars.Costs are based on power sales at cost assumihg 100 percent debt-fi nance at 10 percent interest.This is seen to result in a rea't cost of power of 122 mills ;n 1994 (first "normal"year"of Watana)falling to 73.95 mills in 2003 (the first "normal"year of Watana and Dev;1 Canyon).The real cost of power would then fall progressively for the whole remaining life. The cost of power given in Table 0 ..8 in Exhibit D (Acres 1983)is designed to reflect as fully as possible the economic cost of power for purposes of broad comparison with alternative power options..It is, therefore~based on the cap.ac i ty cost whi ch wou ld ari se if the project were 100 percent debt-fi nanced at market rates of interest.It does not reflect the price at which power will be charged into the system. 10.3 -Financing Plan In the Feasibi lity Report,several plans were presented for financing the Susitna project.At this time,one plan has emerged as the most likely.This plan is presented in the FERC license application (Acres 1983). I t '. ·r·;'~ ;'. ( Sf , ~r 1 T l. r',.. J ~rl!u. r't.. .{ J I , o \ 1 I \ I 1 I I \ 1to I f ' Percent Chan9,L (1.8) 5.7 0.37 (66) 85 19 3,581 1,565 5,146 License Application Estimate Change CJ .........0 1,480 5,127 Feasibility StUdy Estimate 3,647 Devil Canyon Total The completion of the Sus;tna project by the bui ldi 09 of Dev;1 Canyon is expected to be financed on the same basis requiring (as detailed in. Tab 1e 10.1)the issuance of approximately $2.2 bi 11 i on of revenue bonos (in 1982 dollars)over the years 1994 to 2202. Summary f;nanc;;a 1 statements based on the assumption of 7 percent i ofl at;on and bond fi nanci ng at a 10 percent interest rate and other estimates in accordance with the above economic analysis are given in Table 10.2. Watana Due to the relatively minor changes in the cost estimate,no changes have been made in the fi nancia1 analysis.Si nee the Watana project cost has decreased and it is the more critical project to finance, and,since it is the first to be constructed,the Change would in theory make financing easier.However,due to the minimal change in numbers,the impact on the financial projections is insignificant. 10.4 -Change in th~Cost Estimate As discussed in Section 8,the cost estimate has been revised to reflect adjustments to the project made since the feasibility report. The following summarizes those estimate changes. Januar)1982 $xl0 6 The actual interest rates at whi ch the project wi 11 be fi nanced in the 1990s and the related rate of inflation evidently cannot be determined with any certai nty at the present time. A material factor will be secur;ng tax exempt status for the revenue bonds.Th i s issue has been extens i ve ly rev;ewed by the .Power Author- ity·s financial advisors,and it has been concluded that it would be reasonable to assume that by the operative date the relevant require- ments of Section 103 of the IRS code would be mete On this assumption, the 7 percent inflation and 10 percent interest rates used in the analysis are consistent with authoritati ve estimates of Data Resources (U.S.Revi~w July 1982)forecasting a CPI rate of inflation 1982-1991 of approximately 7 percent and interest rates of AA Ut i 1ity Bonds (nonexempt)of 11.43 percent ;n 1991 droppi ng to 10.02 percent in 19958 ~r­ 'r''" f r 'f ~. If r.' r " ;fI:.t ,ro " f I t ~ I I 1 j !~r I r I I I \ L I \ 1 1 1 ·:;::: World Oil Prices:long-term future of world oil prices. -Alaskan Fossil Fuel Prices:market prices versus opportunity values, linkage between coal and oil prices,and linkage between gas and oil pri ces . ...Reliability of Susitna Construction Cost Estimate:construction cost estimates,and risk analysis • This document,"Alaska Enerl~Y Planning Studies -Substantiative Issues ·7dld Effects of Recent Events"(the rev i ew),covered four reports sub- mitted to Alaska state agencies including the draft Susitna Hydro- electric Project Feasibility Report. After pUblication of the review~a commentary responding to comments was prepared.This subsection is a summary of the key comments and responses. ...Financing Issues:real discount and interest rates. These issues are i dent i fi ed as those requi ri ng further treatment to deal with apparent misunderstandings and need for further comment aris- i n9 from the revi ew.The summary here presents the ;ssue and commen- tary in support of the feasibility report relative to the issues. (a)Jjorld Oil Prices,Long Term The rev;ew asserts that oi 1 pri ce forecasts are tc j'high and suggests that real (i,r;:lation-adjusted)prices will continue to be below 1982 levels for the remainder of the century. Price fQrecasts used ill the feas;bi lity r.eport were adopted from the Battelle Alternatives Study.Nonetheless,an updated check of forecasting was done to confirm or indicate.the necessity for changes in the oi 1 price base used in the feasibi lity report..The l~esu 1ts of the survey of forec asts is presented in Tab 1e 10.3. . Tbis summary confines itself to the review only of the feasibi lity report study and related d at a..It does not respcnd to the comments made in the Review on data developed by Battelle and the Institute of Social and Economic Research~University of Alaska. The review commentary deals with: 10.5 ...Comments from IIReview Report ll After publication of the Feasibility Report,a report entitled "Alaska Energy Pl anning Stud;es ...Substanti ati ve Issues and the Effects of Recent Events·"a'review by A.R.Tussing and G.K.Ericson,was pre- pared for the Division of Poli.;y Development and Planning,Office of the Governor of the State o~Alaska. r 1 I 'r r ,. •~,,\R •• \,\ ,..ajint·.*~ Alaskan Fossi]Fuel Prices (i)Market Pri ces Versus.Q.e.eortunity Val u~~. An issue rai sed by the revl ew N~S ,the assessment of prob~ ab 1e future costs of fossi]fue 1s for generati on in the Railbelt from local coal or gas sup~ty conditions. 80th the Feasibility Study and the Battelle study reviewed the prior studies made of Beluga coal costs and wo,'"ldwide coal production cost estimates.The use of prOduction The forecasts used in the report are in close agreement with those of all the major forecasting organizations shown in Table 10 ..3. The forecasts are all of recent date and take into account all recent trends .. Thus,one piece of evidence cited in the review is that Data Resources,Inc.(uRI)now forecasts a decli ne in .Europe's oi 1 con- sumption during the rest of this century,while today there is an excess oi l-producing capacity in the world..Such part;al analysis cannot lead to the conclusion that oil prices will decline over the nextZO years.This requires.consideration of the future levels of oil demand outside Europe:worldwide supply!d;mand con- ditions,etc",DRI,taking all s'.Jch factors into account,supports the position taken in the report with a forecast of 2.8 percent growth in real terms. A second factor cited by ti1e review is the scaling down of oi 1 price projections by the Al aska Department of Revenues in its Petroleum Production Revenue Forecast.The state's forecasts made in the spring of 1982 point tu declining real oil prices through 1998.Of the numerous eminent authorities engaged in long ....term energy forecasting,this alone is cited by the review. Table 10.3 summarizes all the major forecasts for comparison with the report's base case scenario of2 percent real e.scalation, bounded by ]ow and high seenar;os of 0 percent and 4 percent, respectively.Of the 16 authorities surveyed,only one presented a ca~e with long-term declining real oil prices. Although a wide range of oil prices isref]ected in these projec- tions,it is clear that with the single qualification already noted they are all calling for positive real growth in world oil prj ces over the long-term hori zon requi red for power p1ann;ng studies.The Report did not,however,exclude the possibi lity of zero real gtowthin oil prices;it merely assigned it a lower possi bi li ty of 25 percent compared wi th the 50 percent probabi 1i ty ass;gned to the 2 percent growth case.It is Aetes'assessment that the review does not present a case for rejecting this assess ... ment (anct the s;mi 1ar forec ast s shown in Tab 1e 10.3)and effec- tively asslgning 100 percent probability to the zero growth scena- rio. (b) t i -r> T r r T... 'f r I l :(\r II.. '"0, rfi,~.." j'. "~ ~ ~~,b ~r~ I 1 I I' I Regardless of whether Cook Inlet gas prices do or do not equal opportunity values~the \\:"!sults of the Susitna pUblic benefit-cost analysis would not be altered.In fact,it is • costs for natural gas and coal would be wholly appropri ate and desirable fof the financial analysis of a power project from the nart"ow perspecti ve of pri vate i nvestqrs or owners. As a public project,however,Susitna ~hould be,'and was, appr ai sed from the poi nt of view of·the st ate as a \~ho 1e and valued the fossil fuels at its opportunity cost in terms of potential exports. It is forth;s reason that Acres supported the net-back approach in which the value of coal and natural gas in Alaska was deter-mined as the c.l.f.(landeC:)price in the most likely (East Asian)market less the cost of transpor- t ation from Al aska to that market. Linkage..Between Coa land Oil Prices The review is critical of the approach whereby Uboth con- tractors have deduced their price assumptions for Railbelt coal and gas wholly from forecasts of oil prices in Japan ./1 The statement may be misleading as,in fact,it is the real growth rates in co~l and gas export prices that are esti- mated,in the most likely case,to equal real rates of world oil price escalation.Base period (1982)oppor'tunity va lues of coal and gas were determined (as shown above) independent lyof oil prices.In the most likely \base) case,it forecasts that there would be no change in rela- tive prices;that is,the 1982 price ratios among oil,gas, and coal would be maintained during the planning period. This estimation is supported by forecasts of coal and natural gas prices provided in the report.A moving average ~f coal/oil price.ratios exhibits relatively little fluctuation over the a-year period.(There is an estimated pt"obabi lity of over 65 pel'"cent that the rati 0 is 0.42 .=.0.04_) Linkage Between Gas and 0;1 Pri ces The emphasi s of the cri ti c;sm of Feasi bi lity Report assump- tions relating to natural gas is centered on the fact that the current price of Cook Inlet natural gas is signifi- cantly below the ~opportunity value"suggested in the report,and that thi s price is not expected to increase to levels in line with the opportunity value,.It is main- t ai ned th at "Cook In let gas pri ces wi 11 be est ab Ii shed largely on the basis of factors local to the region,"and thus,these prices wi 11 be insulated from the effects of WCftld price movements. (i i) T j f I r l ri I f J • 1L --p: t'· T ~r ·r 7f I' ·1 ! JI only the opportunity values which are of relevance,and the Cook Inlet domestic gas prices at any point in time should not be an issue of any concern in all analysis of net economic benefits .. ThiS resu.lts solely from the fact that,if export markets exi st for LNG at the pri ces whi ch have been determi ned in the Report,then it must be assumed that the rational gas producer in Alaska would select the opportunity to receive the highest price that is offered for the gas .. (c)ReIi abi lity of Susitna Constructio.r Cost Estimates (i)Construction Cost Estimates A third area of concern expressed in the review was the reli- ability of the project capital cost estimate..The concern appears to be based on generalizations stemming from the Umega project U experience of the last decade... Thi s quest;ani ng does not appear to be founded eHl any detailed data or experience of hydroelectric power develop- ment engineering and construction..The only specific mega projects cited to justify allegations of umisplaced specif- icity,subjectivity,and over..optimism~institutional blind spots,and ur~der allowance for noncomp 1et 1on ll in the Acres construction cost estimate are the Trans Alaska oil pipeline and the Washington Public Power Supply System nuclear reactor program..It is Acres'vi ew that nei ther of these projects has any practical bearing on a site-specific~basically conventional engineering hydroelectric.power development such as Susitna where ~he project estimate has been as extensive, evaluated and ass"lgned as high a coniidence level as in the Susitna case. Cost-estimate revi ew on a ri sk basis was conducted in the Feasibility Report by relating to a list of pro"iects compiled by an external source.It is recognized that this approach did not include.major hydroelectric projects in northern areas,nor did it reflect the Acres experience in project cost..estimati ng..To provi de further support for the project cost-estimate,Acres'experi ence on a project simi 1ar to Susitna was reviewed.Table 10.4 provides in detail a review of Acres'Churchi 11 FaTls Hydroelectri.c Power Project esti- mate versus outcome. Two estimates of costs are given.The first,for 1963,is in the nature of an early stage feasibi lity estimate,whi 1e the second,for 1968,1 s a fi naT pre-contract estimate broadly comparable in confidence level to that produced in the . Susitna Feasibility Report..It is seen that,reduced to "'-,-" "..-It'....,..« t f'I I 1 l' I l. l' I I Il c I Q \ \ 1 I I --------,---'I "~ ':';"."' o I, I, \, 100.0 Percent of 1963 Estimate 488.2 1963 Dollars 563.3 489.5 100.3 665.6 467.8 95.8 ~' 488.2 $Millions Current 0011 ars "':1 _....._-'-,. The project budget provided for a conti ngency allowance of $41 million,i ..e.,approximataly 8 percent of the base construction cost estimate and a provision for escalation of $102 million based on a rate of 4.5 percent per annum,con- stant over the construction perioda (2) 1963 Estimate (i ncl • cont i ngency )(1) 'I ~~6 Estimate (i neL, con\.1 rigt:i!CY)(2) Completion Cost NOTE:(I),1963 Estimate was for 10 X 4~0 MW Units;1966-68 Estimate and Actual was for 11 x 475 MW Units. Comparable purchasi\1g power (1963 dollars),the 196~estimate is at variance from the final cost by 4.2 percent.This favorable (negative)variance has to be viewed,furthermore, in light of the fact that between 1963 and 1968 there was an increase from 10 to 11 in the number of hydroelectric units and an incre~se in the rati ngof all generators from 450 rlW to 4i5MW. TABLE 10.4 COMPARISON OF ACRES ESTIMATE AND ACTUAL COST REDUCED TO COfvlMON (1963)LEVEL The Churchill Fa 11 s Power Development in Labrador,Newfound- land,is a 5,225 MW development in a ~"emote area.It is com- parable to Susitna as a giant hydroelectric project.It will be noted that in place af the single large dam which creates the operating head and storage reservoir for Watana,a large 'number of fill structures were bonstructed at Churchill Falls wi th an aggregate 1ength of over 42 mi 1es and YO 1ume of more than 40 million cubic yards.Construction work spread out over 2,500 square mi 1es of reservoir'area was inherently more di ffi cul t to control than a concentrated development area such as Watana. ,Other examples of estimate/final cost comparisons uphold Acres record of performance on maj or hydroel ectri c power projects in northern latitudes and at remote sites. ,r f 'ri I f f 1,( [ I • I I r.II i I 1 1 ! \ } I r f \. ------"J --J~ \) (d)Real Discount and Interest Rates rhe review took issue with the standard methodology by which Acres derived the 3 percent ,,"eal discount rate used in the cost/benefit analysis in the feasibility report (Section 18.3 to 18.21)and argues for ~.5 percent as the appropriate rate. The 3 percent discount rate was derived from two sources.First, it was given as a guideline for economic evaluation by the Depart ... ment of CORl11erce of the State of Al aska.The second source was the generally accepted stlJdiessummarized on page 18.4 of the Feasibility Report. It is clearly possible to que,stion the standard methodology giving rise to this parameter..Her'e,as in other parts of the study, however,it was study pol icy to avo,;d unnecessary controversy.by not quest i ani ng accepted meth Jdo logy Of gu ide1i nes un less the alternative approaches materially affected Acres·conclusions. A more preci seapproach is that of determi ni ng the Project Speci- fic Rate (PSR).This is done by first estimating the weighted a verage interest cost of project borrowi ng and the opportunity interest cost of any funds provided by the sta'(.~of AJ aska ,with the wei ghti ngs be;n9 the proportions of these tWQ types of capi- tal.This weighted average is then converted into a real discount rate (approximately)by deducting the relevant rate of inflation. The interest rates used would be those obtained at the time that. the capital is to be raised and the rate of inflation,the long- term rate expected over the 1ife of the borrow;ng.- On the basis of the DRI forecasts and on the assumpti on that the oppor-tuni tY cost of state-provided funds ;s the interest rate forecast for federal government securities while the project borrowing;s in th~form of tax-exempt bonds (see Table 18.22 in the Feas i bil ity Report),the wei ghted averaged i nterestrate with the state appropriation of $2.3 billion can be determined.The DRI forecast i nterest rat~on federa 1 funds and on tax-exempt bonds,both over the relevant capital raising periods and unweighted~are 10.4 percent and 8.1 percent,respectively.This gives a weighted average PSR of 9.1 percent in money terms. The long-term forecast rate of CPI i nfl at i on from 1985 to 1995 (again as given by ORr)varies between 7.1 (1985-90)and 6.5 per- cent (1990-95).No forecast ;sg;ven for the post..1995 peri odC) The implied real rate of interest relevant to the cost benefit at a long-term inflation rate of 6.5 percf"nt is,therefore,approxi- mately 9.1 -6.5=2.6 percent..At these rates of inflation, therefore,this alternative methodology,using DRI data,does not support a higher discount rate than.the 3 percent di scountrate used.in cost/benefit.analysis carried out for the.feasibil ity study and dealt with in the report. f, ~ '". .ir I I 'T ( ,,r ,if ..,. ',l "'[ 'l l ~ r 1 ( tl l { ,, ,~I f !I ' ' '. l~ ~ , I i ' i •-' ,r nJ ,, ~ t t t t t L l t I' The position taken in the review is that the discount rate should be that at which tne project is financed. This is the PSR approach just described. As such, it produces a 1 ower (not higher) rate than that used in the Acres analysis. The r'evi ew suggests, however, that the appropriate rate is 4. 5 perce~nt on the ground~ that this is the DRI forecast of rea 1 inter·est rates on corporate bonds* in 1992. Si nee the project is not being financed by corporate bonds but by tax-exempt bonds and by the state of Alaska, it cannot be argued that this 4. 5 percent has any relevance. The relevant tax~exempt and federal bond rates consistent with the 4. 5 percent corporate bond rate give the result outlined above. We would also note t~jat the DRI 4.5 percent real interest rate on corporate bond$ is very much higher-than the Wharton . or Chase forecasts cr: indeed any of the other main forecasting agencies. These are generally in the range of 3-2.4 percent. If these fore- casts, rather than the DRI forecast.used above, are accepted then, taking into account the advantages of tax exemption, the 3 percent discount rate used for the Susitna cost/benefit analysis is con- servative in that the appropriate PSR should be signif1icantly lower. This became apparent in the course of the Acres analysis but was not pursued, since it rrerely had the effect of reinforcing rather than controverting the conclusions reached. In summary, it appear~ to Acres that the review is mistaken as to the outcome of the methodology which it proposes a.nd that, cor- rectly stated, this methodology (which Acres stresses is only an approximation) gives a result whjch would argue that the discount rate promulgated by the Alaskan Department of Conr.merce and used by Acres is too high, not too low. 10.6 -Generation Planning . /~fter circulation of the feasibility rep'Ort, several items of work were accomplished in response to questions and comments. These involved the follnwing areas of analysis: -Multivariate analysis -sensitivity of load probability; -Changes to the generation planning model; -Impacts of project changes; and ... Other issues. Each of these areas is exp 1 ored i ndi v;i dually in the fo 11 owing text. (a) Multivariate Analysis -Sensitivity of Load Probability To account for variance in forecasting, the economic analysis was approached an a probabilistic basis, Several key variables were chosen; a r~nge of low, medium, and high varia~le values were *Using the CPI t1nd not IPD the rate is 4. 0 percent. ~~r 'J ' r . r . '[ ' .. ' I • I I I l ! . ' ' ', I ,~ t ;' ' i ,, I,~·- rr '[ t t ' t j ' r l f I J F t _,;...:~- (b) estimated; and probabilities were assigned to each value. A pro- bability tree was constructed with each combination of variables assigned a resultant probability. The original analysis is dis- cussed in more detail in Section 18 of the feasibility report. The rrulitvariate sensitivity analysis analyzed the four variables: load forecast, alternatives capital cost, fuel cost escalation and Susitna capital cost; assigning a range of probabilities to each. Some concern has been expressed regarding the likelihood of the probability distribution being different from the assumed ... base case" of 0.20, Oe60, and 0.20 for the low, medium, and high load forecast scenarios. A recalculation of the probabilities was made using the distribution 0.60, 0 .. 30, and 0.10. Tables 10.5 and 10.6 summarize the calculation for the non-Susitna and Susitna trees. The resu1 ts of the analysis show that the expected va 1 ue of net benefits is $971 million. This is a result of the difference in the non-Susitna and Susitna plans ($7,624 -$6,653 = $971)a Compared to the base case multivariate analysis, the $971 million expected value is approximately 33 percent less than the base case value of $1s450 million. Figure 10.1 plots the net benefit curves. Changes to the Generation Planning Model · In May 1982, General Electric released Version 6 of the OGP Pro- gram. Version 5 of the program \vas used as the primary tool for the generation planning studies for the feasibility report;. Several changes were made to the program in Version 6 in response to user comments. i"hese include a possible 30-year study period (replacing 20), more options for maintenance scheduling, and increased program flexibility. Two changes particularly relevant to the Susitna analysis are the possibility of economic over- building (adding units on an accelerated schedule) and carryover of excess hydropower from wet months to dry months., The 1 atter gives a more favorable (and accurate) value to the potential hydro energy produced by the project* In order to test the impact of these terms on the results of the generation planning, the base case, with and without Susitna; was reanalyzed with OGP-6. Table 10.7 summarizes the results. The results were reduced to a long-term cost in a manner identical to the feasibility report. The revisions in the program had no impact on the non-Susitna case. For the with-Susitna case, the increased value of the hydro energy increased net benefits by about 5 percent. (c) Impact of Project Changes (d} Other Issues After completion of the Feasibility Report, several cr1mments were raised wh1ch required additional study or expla,nat~on. Those issues are presented in the following paragraphs. (i) Discussion of! Percent Reserve Margin In planning system electrical need, there are a f1umber of methods that can be used to measure a syst,:m 1 s rtf:l i abi 1ity and determine the need for the addition of capacity. It is common utility practice to plan to a statistical measure of reliability: loss of load probability (LOLP) in conjunction with some minimum percent reserve margin... Corrputati on of LOLP involves probabilistic forced outage rates, planned maintenance, peak load~ and reliable energy considerations .. LOLP is commonly expressed "3 a loss in days per year or 3 in some systems, hours per year depending on the size of individual units in the operating system. Percent reserve margin can also be calculated ·in a varietY of WiiV:S relatino capacity, load, contracts for power (1xchtmge-, and the 1 a~gest units on the system to a s 1 ng 1 e· mee.sure of av ai l- ab i e capacity. (i w Percentreserve.=capacity -load in the peak monthload (December in the Railbelt 5Y'stem) As previ ous ly mentioned,the system model exam;nes the available Unl-C$for addition in a year When reliability is not met<:In the first year of the study,1993,the units a vai 1abl e for the non-5usitna pl an are 20Q,.MW coal,2QO"'M\~ .. Therefore,the calculation of percent reserve in this context is independent of the "nsed ll for capacity which is determined by the LOLP criterion. Alternatively,the OGP model can plan to a percent reserve marg;n andca1cu late LOLP after expansion has been made. However,this option was not exercised due to the variety of methods for computing percent reserve and the difficulty in arriving at a consensus cn a reliable percent reserve due to the system size. An alternative method of calculating reserve margins i nvol ve::i subtracti og the largest unit of capacity out of the total available system capacity.Other methods sub ... tract the largest II s tringU of 'tntertied units from the total capac;ty to arri ve at a reserve marg;n.'In any case, the percent reserve is merely a simple statistic of avail- able capacity to meet load regardless of llact5 of God u and forced outages. Table.10 ..8 summarizes the two sets of statistics for the medium load forecast base non-Susitna and $usitna pl ans. The planning criteria were LOLP less than 0.10 days per year,and percent,reserve was c:alculated using the noted equationt>Figure 10.2 plots percent reserve versus time for the two pl ans.Thefollowi ng paragraphs di ~cuss the variations among plans. In model i n~the A'I askan Rai 1bel t System forgenerati on planning studies,the LOLP criteria of 0.1 day per year was used as the "trigger point U for capacity addi.tions.In other words,in every year,the OGP model cal cul ates the system reliability LOLP without any additions.If the system as it exists violates the LOLP criterion of 0.1 day/year,the model then.examines combinations of available .alternative unit capacity additions that would meet this rel i abi 1 ity criterion.From these alternati ve system mi xes,the least cost (or producti on cost optimal choi ce) is selected and the system is operated for the following y.ear.At this time,the percent reserve margin is calcula... ted for that year using the equation: t. t. l I \ t r t l e :r' -. ,<r 'I' ,(. '{I 't ,.f tt 11 i _ lIt 1[1. It i ", ------.--:--=.J~----"---.-- ()c, ,.-. Susitna Combined Cycle NGGT other Hydro Diesels Susitna NGGT SusitnaNon-Susitna Coal NGGT Coal Combined Cycle NGGT Other Hydro Diesels f t ti ......'-"--"'-' O&M: I nvestment Costs: In year 2010,the non-Susitna plan has a calculated LOLP of 0.099 indicating that criterion is nearly violated in that year.This LOLP corresponds toa percent reserve of 32.5 percent,which i.ndicates the level of capacity installation over LOLP needs.In both plans the percent reserve is always above this level ,varying as the various size units clre installed. combined cycle,70-MW gas turbine,and lO-MW diesel units. Of these,a single 200-MW unit meets the LOLP criterion in the most cost-effective manner.In the Susitna pl an,the Watana project added in a single stage is 680-MW,which is considerable for that particular year;however,asl cad grows and existing units ret'ire,percent reserve decreases. No other un;ts are needed in the system.In year 2002, additional capacity is needed.The Susitna plan adds the 600-MW Devi 1 Canyon proJ ~ct whi ch agai n raj ses the percent reserve. The non-Susitna plan has the capability to add only small increments of capacity rel ati ve to the Susitna prOject. The addition of 200-MW or smaller units meets reliability criteria w1th a smaller reserVE margin.As Susitna is added in 600+MW;ncrements to ta~:e advantage of its full energy potential,the reserve margi n becomes very large. Much of the reserve margin capacity sets idle from 1993 on. (ii)Annual System Costs Each year the OGP model dispatches available energy genera- tion to meet load.Table 10 ..9 shows the annual energy dispatch .in GWh by generating unit type for the two plans. Figure 10.3 shows the annual system costs plotted for the two plan1!.This figure represents the initial cost of the Watana project having hi gher system cost during the first few years,remai ni ng about the same duri ng the years 1996 to 2001,and showing significant savings in the years 2003 to 2010 • . (iii)Annual System Cost Components The annual ~y.stem costs consi st of a number of components : 1 \ 'r rr· ~ 1 {~. j I '] t~ .~ f it I ~.:J 1it I 1[; fii \I [, J t. l. Tables 10.10 and 10.11 list the annual yearly costs by com.. ponents for the non-Susitna plan and the Susitna plan. Figures 10.4 and 10.5 depict the components graphically. The most dramat i c compari son is the portion of Susttna investment cost versus the coal investment.and fuel cost components in the non-Susitna plan. Figure 10.6 plots the annual system long-term costs for both plans during the 1993 to 2010 system modeled period and the 2011 to20S1 economic extension period. Di scussi o"n of Delay of Project The Railbeltsystem technically needs capacity installation in December 1992 to meet the LOLP rel i ab i 1i ty cri teria. However,Acres has started the study in 1993,suggesting that the December 1992 peak would be met by extend;ng one or two retiring units unti 1 major new units are on lim!in January of 1993.Delaying Watana Stage One to 1994,there- fore,poses a problem,since it is necessary to have some type of capacity in 1993 .. Two impacts occur when a Susitna project stage is delayed. First,there is an increase in fuel costs during the year of del ay to make up generati on not prov;ded by Sus;tna. rOY"example,with .Watana,in 1993~fuel costs are $25 mil iion.Without Watana and using two new natural gas tur- bines,fuel costs are $128 million in 1993.Second,there is a decrease in Susi tna investment cost present worth. For example,$100 invested in 1993 is $76 in 1982 doliars'. One hundred dollars invested in 1994 is $74 in 1982 dollars at a 3 percent discount rate. The lowest production cost alternative in 1993 is a200-MW coal unit.However,this unit followed by the largeWatana project in 1994 is only used one year,hardly a justifica- tion for building a large plant.Alternatively,two 70-MW gas turbines can be installed in 1993,run to meet peak until Watana comes on line,then used as standby until the 1ater years.TId s system plan (C3)is shown in Tab 1e 10.14.This plan reduces net benefits approximat.ely 4 per- cent toS1,133 million. Delaying both stages of the Susitna plan one year results in essenti any the same net benefit as the previous case. This plan C4 has a long-term cost ·of $7~165 million.HO\'I" ever,it must be compared to a without ..Susitna plan which· GT Natural Gas .CC Natural Gas Coal GT Natural Gas CC Natural Gas Oi 1 Fuel Costs: (i V) ;~:r~ '[ I .I j :n .' t ,{ 'J;i tI ,.. Iit ~~. 1f t ~ ·'l. t 1 L t, ti.l t t t l t l (1)When comparing Watana-onlY project plans with the base case alternative plant it is necessary to compute the long-term cost to year 2043 when Watana is i nsta11 ed in 1993 (medium-load case)and 2045,when Watana is installed in 1995 (low-load case). (2)When a Susitna plan installs a 200-MW coal plan in the planning horizon,it is necessary to add in the cost of a Beluga transmission tie in the year it is added, calculated in 1982 dollars.This cost was estimated as $53.5 mi 11 ion (from the upper 1imit capital cost report,July 1981),and is added to the long-term cost. has been extended to year 2053 rather-than 2052,since the Susitna project 1ife is 50 years from the year Devil Canyon is installed.This modification makes the non-Susitna plan LTC $8,299 million;therefor"!,net benefits are $1~134 mi 11 ion. Delaying both stages of the project two ·years (plan C5) increases fue 1 costs in years 1993,1994,.2002!and 2003 due to dispatching of thermal units to meet load •.Again, the net impact is partially offset by the decrease in pre- sent worth of Susitna costs and the net benefits are $1,130 million,4 percent less than the base case. (v)Watana Project Alone Pursuing only th-e Watana projections examined in 'the medium-and low-load forecast cases.Table 10.13 summa- rizes these plans. Under the medium-load forecast,the Watana only project was tested at two i nsta 11 ed ca pac;ti es :680 MW and 1,020 MW. A1though the larg~r capacity plan displaced sorr~additional capacity and since no additional average or firm energy is associated with these units,the net effect is a negative benef;t of $102 mi 11 i on.The second stage of Watana was capital cost ~f the $58.8 million. The low-load forecast plan shows a negative net benefit of $96 million for the Watana-only scheme. Twa notes on the calculation of net benefits and long-term cost: (vi)Alternative RailbeltHydro Assessm~nt Previously,the Development Selection Report'(DSR)examined various alternative developments of the SusitnaBasin.The Watana/Devi 1 Canyon select;on was chosen as the 1east ..cost, r t i . !I I ' 1. t I • l I lJ 1 t ·'fI.. rr . .~ 'I! ,r f :t it 1IfI I. It I t ..~-_...-~"r-"--~...._.."..l. 0 i •_'t ~.. $5,761 Devil Canyon $2,203 Watana 3,558 Devil Canyon 2,585 2,264 Hatana 4,208 3,130 6,793 5,394 $5,725 $4,094 1,631 ~ 6,79S 5,394 'I,..,."- t Total Watana 3,459 2,631 Devi 1 Canyon 3,334 2,763 Total Watana Devi 1 Canyon BUild~ng Devil Canyon first inc\"'eases the cost compared to . a 1ater stagi ng because of addi ti ana 1 adjustments of transmission,intakes,diversions,cofferdams,access roads,and site facilities~ Reverse stag;ng of the Susitna project has SOffi2 un;que cost implications!'!First~the possibility exists that the Dev-;1 Canyon project caul d be on 1;ne sooner than 1993,perhaps as early as 1ate 1991.This situati on was not modeled;however,in the without-Bradley Lake case it may reduce the long-term cost and increase net benefits over the val ue presented here.Secondly,the ;nteri m years between Devi 1 Canyon (1993)and Watana (2002) require additi anal capacity to be added.Five.70-MW gas turbi nesare needed to supply energy to the system o Capital Cost (including IDC)impacts of Devil Canyon first foll\owed by Watana are summarized below: 1982$x 10 6 Total energy impacts of Devil Canyon first compared to WatanalDevil Ganyo~are as fullows: Ava;1 abl e Energy.....,~·_G~W;.;..h _ long-term generat;on pl an.Thi s assessment rev;ews some of the possible alternatives,using the same criteria as the Susitna feas;bi 1 ity study and updated data on the hydro- power al ternat;yes.Generat;on pl ans were developed for the fo 11 ow;ngscenari os and 1cng-term co~ts compared to the base case without ..Sus;tna plan. ..DeY;1 Canyon -Watana ..Chakachamna -Dev;l Canyon ..Chakachamna ..Watana -Watana only -De'l;1 Canyon only -ChakachamnaonlY ..Devil Canyon -Watana- ... t t '\t t l ~:l~~ t.:- r~j • '1. tt1 II1 ~( t '{ I 41 I) t f j L With tl~~::addition of Chakachamna in 1993,'Devil Canyon can most effect;vely be staged in 1997 with further expansion of Beluga coal units in 2003 and 2010.Six 70-MW gas turbines are added in the post-2000 period. The total1ong-term cost (1993-2051)of this plan is $8,186 million as shown in Table 5~ Note that this is a tally of available energy Which is sli ghtly greater than usabl e energy by year 2010... The 330 MW Chakachamna hydroelectric project was also examined in the DSR.Two updated generation plans--one with theChakachamna project in 1993 followed by Devil Canyon,the other Chakachamna fallowed byWatana--were analyzed under the same parameters as the feasibility study base case.Capital costs and energies were p';"ovi ... ded by Bechtel,Alternative "B II with average annual energy of 1,492 GWh,firm energy of 1,374 GWh and a tapi- tal cost of $1,450 million including IOC and transmission costs. The Chak~lchamna -Watanageneration plan was staged as 1993-2000 respectively,since Watana alone isa larger energy project than Dev;1 Ca nyon.Additi ona 1 capacity added are three 70~MWgas turbines and a 2QO-MW combined cycle unit..This plan has a 1993 ..2051 long-term cost of $8,241 million,with negative net be'nefits of $4 million When compared to the base case non-Susitna plan. The possi bi 1it~of a Chakachamna-Oevi 1 Canyon-Watana or Chakachamna-Watana-Devil Canyon plan was examined;how- ever,the excess capacity and en.argy provided in these scenarios,given the medium load forecast,are over 1,000 GWh and were,therefore,not modeled as such. -Single Hydro Project Developmen!§. Three single developmant cases were examined under this topic:Watana,DeVil Canyon,or Chakachamna alone. Table 10.15 summarizes energies,capital costs,and long-term casts for each of these scenarios.Long-term costs are computed for 50 years of the project. The results of the generation plans for the base case - i4atana/Devi 1 Canyon and the reverse stag;ng Devi 1 Canyonl Watana are.summarized in Table 10.12.Long-term costs in the latter increase by 4 percent over the Watana first case reducing net benefits to $896 million.. -Chakachamna -Susitna I i, ,'p I 1 ( •"'(1 .."Ii ..} """"'~'.I ",) U 1 rf i .. ,[ ,t.- t t l \ L l t t, _..,-.a :........---------.....--..~...•-.. ,I -- 412.6 371.1 139.0 922.7 1982 ~»urchasi ng Power_. 3166.9 90.8 148.0 160.3 138.5 380.8 438.6 458.8 393.9 34.5 2244.2 318.6 348.2 330.9 321.8 '564~9 872.3 243.3 3000.0 Actual 784.7 754.9 294(,6 1834.2. 211.6 368.9 427.7 39504 1163.0 1432.3 1604.7 1473.5 137.8 7214.9 403.7 472.]' 479 ..7 499.5 938.3 1550.4 462.4 4806.7 (i .9049.1 ......... _"5,"_·_'. II .. .. TABLE 10.1:FINANCING REQUIREMENTS -$MILLION FOR $3.0.BILLION STATE APPROPRIATION $Million Interest Rate 10% Inflation Rate 7% Total Susitna Bonds 2000, '"~ 2 Total Devil Canyon Bonds 1994 Revenue Bonds 5 Ii 6 II 7 II 8 II 9 .. Total Watana Bonds 1990 Revenue Bonds 1 II 2 II 3 .. Total State Appropriation 1985 State Appropriation 86 .. 87 .. 88 .. 89 .. 90 11 91 II --~-~~-~~~~~-~~~~-~---~-~---~~--~.__..-~------~~~~~-~-----~------,-~-----~--~-~- r L L L •'f"' r U f. t..'i t f r 1 I I, t L f ''P s.'I"~,~;, .I :-f I ~ r ·r i +3 ..4 +1.9 .1('5.3 +1.7 +1.8 +1 ..7 above +3 -0.5 +2.0 +2.8 Forecast Trend (percent) Spring 1982 Spring 1982 Febru~ry 1982 Summer 1982 Spri ng 1982 Sunmer 1982 Spring 1982 Date of Forecast- TABL,E 10.3 SUMMARY OF ~~JOR FORECASrS OF OIL PRICE TRENDS . *The 10 models are:Gately-Kyle ....Fischer (New York Univ.),lEES ...OMS (U.S. Dept.of Energy),IPE (M.I.T.),Salant ..ICF (U.S.Federal Trade Commission and rCF,Inc.),ETA-MARCO (Stamford Univ.),Wall (u.S.Dept.of Energy and Environmental Analysis,Inc),Kennedy-Nehring (Univ.af Texas and the Rand Corp.),·OILTANK (Chr.Michelsen Institute),Opeconomics (BP Co.Ltd.),OIlMJIR (Energy God Power Subcommittee,U.S.House of Representatives). Dr"'.F.Fesharak i, Resource Systems Institute East-West Centre,Honolulu Ontari 0 Hydro Energy Model i ng Forum, World Oil Report* -average of 10 models -range of 10 models Energy Mines attd Resources Canada US Energy Information Administration Date Resources Inc. Source I nte,'nat i ona 1 Ener gy Agency ..Low -Hi {jh I r, I, .J ..T :l.. tl rf I J r J f!J {, I. I f I. I t [ [ L, L ·r ,. ~.r .r 1 T. TABLE 10.5"- 1.00 MULTIVARIATE SENSITIVITY ANALYSIS,LONG-TERM COSTS AND PROBABILITY,NON-SUSITNA TREE (1982~) $x 10 ..11 R&nk (Low-Long-Term Cumulative [ncremer.taT Cumulative ,Highl 10 Cost Probab i1itx pro.babilitx LTC LTC ~J:W .... 1 T27 4412 .03 .03 132.36 132 2 T24 4590 .09 .12 413.10 545 3 T21 4856 .03 ,,15 145.68 691 4 T1a 5489 .G15 .165 82.34 173 5 TI5 5661 0045 .21 254.75 1.;028 6 T12 5991 .015 '.225 89.87 '\11t".J..,•-,:;) 7 T26 6101 ..06 .285 366,,06 ~~484 8 T23 6878 .18 .465 1,2,3$.04 2,722 9 T09 7184 .005 .47 35.92 2,758 10 T06 7313 .015 .485 109.70 2,868 11 120 7460 .06 .545 4'47.60 3,315 12 T03 762 t1 .005 .55 38.12 3,354 13 T17 7915 .03 .58 237.45 3,591 14 TI4 8238 809 .67 741.42 4,332 15 T25 8492 1003 ,,70 254.76 4,587 16 T22 8746 .09 ..79 787.14 5,374 17 TIl 8858 .03 .82 265.74 5,640 18 T19 9253 .03 .85 277.59 5,918 i9 T16 10321 .015 ..865 154.82 6,072 20 T08 10503 .01 .875 105.03 6,177 21 TI3 10637 .045 .92 478.67 6,656 22 T05 10859 .,03 .95 325.77 6,982 23 TID 11272 01':".965 169~O8 7,151",; 24 T02 11569 .01 .915 115.69 7,267 25 T07 13742 .005 .980 68.71 7,335 26 T04 14194 .015 .995 212.91 7,548 27 TOI 15058 .005 I.OOe 75~29 7,624 1.000 11 LTC -lQng-term costs Using probability distributions: tow Load Forecast 0.60 Medium Load Forecast 0.30 High Load Forecast 0.10 I L l L •If .1 ,J 'I f 1: ~ JJ r"'Ill f l. 1; 1. 11'. t f~ 'y- ·'r ,r '{.I 499 1,535 L,797 2,346 2,900 3..141 .3.4~2,-"", 3,931 4,058 4,320 4)585 4,606 4,670 .. 4,691 4,856 4,995 5,334 5,420 5,598 5,777 5,787 5,817 5,827 5,877 6,027 6,121 6,172 6,17~ 6,199 6,205 6,228 6,297 6,321 6,350 6,437 6,467 6,482 6,528 6,543 6,556 6,596 6,609 6,618 6,644 6,653 498.,87 1!l036.26 262.22 548.,73 553059 24·1..39 291,47 498.75 126.34 262 ..16 264.83 21.26 63.97 21045 164.95 138.53 339.44 86.06 177.39 179'l42 9.,98 30.03 10.06 49.96 150.25 94.17 50.34 6.66 20.04 6.71 23.06 69.35 23.23 Z8.84 87.82 29.35 15.19 45.66 15.29 13.14 39.97 13.35 8.56 26.01 8.69 ,,09 .27 .,315 .,405 .495 .5325 .5775 .6525 .67125 .70875 .74625 "74·925 ~75825 .76125 ..78375 .8025 .8475 .85875 .88125 .90375 .905 .90875 .91 0916 .934 .94525 .95125 .952 .95425 .955 .9575 .9650 .9675 ..9705 .9795 .9826 ..9840 .9885 .99 .99125 .995 .99675 .997 .99925 1.0000n 11 Cumul at i v!a I ncr ement aT Cumu 1at i ve Probabjlity LTC LTC 1) ! '1:< r:-I' 1f ,,--f -(f I, i II ..,,".! TABLE 10.6:MULTIVARIATEA SENSITIVITY ANALYSIS LONG-TERM COSTS AND PROBABI~ITY,.~USITNA TREE 11 U~ing probability disttibuticns: L,ow Load Forecast 0.60 Medium Load Forecast 0.30 Hi gh load Forecast 0.10 1.00 (1982~) $x 10 Rank (Low-Long-:Term ±li.9h)10 Cost Probability ~-.~ 1 545 5543 .09 2 S42 5757 .1.8 3 536 5821 .045 4 S39 6097 .09 5 533 6151 .09 6 544 6437 .0375 7 S30 6477 .045 8 541 6650 0......~.1'0 9 ~35 6738 .0187~ 10 S38 6991 .0375 11 $32 7062 .0375 12 '527 7087 .003 13 S18 7108 ..009 14 509 7151 0003 15 543 7331 .0225 16 S29 7388 .01875 17 S40 7543 .045 18 534 7650 .01125 19 537 7884 .0225 20 531 7974 .0225 21 S26 7986 .00125 22 S17 8008 .00375 23 508 8050 .00125 24 524 8326 .006 25 S15 8347 .018 26 S28 8371 .01125 27 506 8390 .006 28 S25 8886 .00075 29 S16 8908 .00225 30 507 8951 .00075 31 $23 92Z",.0025 32 S14 9247 .0075 33 505 9290 .0025 34 521 9614 .003 35 S12 9158 .009 36 503 9784 .003 37 522 10126 .0015 38 S13 10~.:f7 .0045 39 S04 10190 .0015 40 SZO 10514 .Q0125 41 511 10658 .00315 42 S02 106B3 .00125 43 519 11414 ,,00075 LJ.A S10 115S8 .00225 45 SOl 11584 .00075 L.OOOOO r f l t . t L --;r )'. '.r·I .' r ,~f .'I' I II l[ I -I~ I 1 1 \ 1,176 Net Benefit 8,238 7,062 Long-Term Cost 1993-2001 3,943 5,025 1982 Present Worth of System .Costs $x 10 6 Estimated 2011-2051 - 1/ 2010- Annual 491 385 TABLE 10il7 COMPARISON OF BASE CASES REVISED OGP-S PROGRAM 3.,213 3,19 Cumulative Costs 1993-2010OGP-5 Non-Susitna 3,213 491 5,025 8,238 .._- Susitna 3,066 384 3,929 6,995 1,243 v OGP-6 Non ..Susitna Susitna 11 2010 annual cost is projected 41 years at 3%and present worth 26 years'to 1982 at 3%to arrive at the 2011-2051 estimated present worth. 'r 'r l ''[ J !r 4 r t 11. 1.-II • f 'f " '{ l . [ ,f { ( L ( L l Q ,'"~~' .. ,;,."",.... '~! ~.,~......~~~~;..-- .. ~ -Air "'-' ~"I !\~~ - ".--..)r'.. '~_';"';---'--.......,---......._.,. ..-......--.- capacity-load load _~,'~--.l _ ~ !........-.,.. ,-,p'-'..~'''i'.,."","'~"';,:i;-.~"i'1~.;/:(r~~~'ill'~~"!lfi:~A2#"r~t wela', ;."".','',IV"',,'._''_,"(J 0 '~'C'::. ,- ~~...~ ....-..- ~ TABLE 10.8:PERCENT RESERVE -MEDIUM LOAD FORECASt l / ~ 1/Ascaiculated in peak month:%reserve :: ~~---r~ i ~_ ~ 1 ;l2J"'0'··1.I''::I,:.'"..".J 1 '.';) '': Non-Susitna Susitna Peak Total Total Load Capability LOLP Capabil ity lOLP ~jMW}(~1W)%Reserve days/years ~,%Reserve days/year 1993 947 1373 45.0 0.063 1853 95.1 •0.000 1994 965 1542 59 ..8 0.027 1822 88.8 9.000 1995 983 1495 52.0 0.077 1714 80.5 0.000 1996 1003 1624 61.9 0.059 1704 69.9 0.000 1997 1023 1620 58.4 0.084 1630 59.4 0.000 ttl 1998 1044 1635 56.6 0.092 1575 50.8 0.001 1999 1064 1635 53.6 0.055 1515 48.0 0.002 2000 1084 1591 46 ..8 0.059 1531 41.~0.015 ~2001 1121 1661 48.2 0.038 1531 ,36.6 0.032it' 2002 1158 1608 38.9 0.,062 2079 19.5 0.000 2003 1196 1625 35.9 0.087 2026 69.4 0.001 2004 1233 1695 37.5 0.057 2027 64.4 0.001 2006 1323 1794 35.6 0.049 1939 52.7 0.017 2006 1323 1194 35.6 0.052 1917 44.9 0.068 2007'1377 1994 44.8 0.023 1981 44.3 0.025 ,2008 1430 1968 31.6 0.066 2032,42.1 0.029 2009 1484 2037 31.3 0.051 2031 36.9 0..050 2010 1537 2037 32.5 0.099 2102 36.8 0.025 }< -;NG NG OTHER Year COAL '6T CC OIL HYDRO SUSITNA TOTAL 19~13 140 0 578 0 631 3387 4736 1995 183 "2 719 0 631 3387 4922 2,000 I'239 83 1129 0 631 3387 5469 2002 0 0 0 0 631 5222 5853 2005 3 0 0 0 631 5539 6428 2.010 ,53 6 616 0 631 6485 17~1. ..~ u ...".f, ~~/ •J ............,..._-........-,.,'-....~r~.---..-"'\ .~ <;; .~-- TABLE 10.9:o..NNUAL ENERGY DISPATCH 11 ....."...'.~..~ l/Mec!im LOiDd Forecast. NON-SUSITNA PLAN (GWh) SUSITNA PLAN (GWh) NG NG Year Coal 6T CC OIL HYDRO TOTAL, 1993 1758 610 1733 4.0 631 .4736 1995 2887 226 1117 0.6 631 4922 2000 3983 68 787 0 631 5469 2002 4236 95 891 0 631 5853 2005 4283 300 1214 .0 631 6428 2010 5486 434 1240 0 631 7791 ~.~.~ ;.oI!l; ~~..{ (,; 1i ;f c f '~ ( l o 1 .J <f~i oj I kJC:'·1 '«I i?'<:\.~..'!D"·"c:'~; f.·'~~~~J,1 ,; ",,'1 ~~'~ (\, t~ -.--~"-'-~",,o,.llO:,),,'>,::;4i"'~""'4"",m:<l(~M!.•$JIIillUQ;;!L.1:iliJlllWr,;T-...,->0,-,-'.-:' .'_D ..'-, ",.-"<..) /' -~-~-~~__.•,c:.__,__:__c··",_.\,)T'"__0 ..."'" ....".:...,............,...'" ~,~,,~,.~~~'~.~ CJ ,c;.~~-"-.,, \> TABLE 10.10:COMPONENTS OF ANNUi\L CGSTS -NON·..SUSITNA PLAN JJ_~_l • 11 Medium Load Forecast l~-••••"un"""...J r Coal Coal Coal NGGT NGGT NGGT NGCC NGCC OIL Year'~INV OIM Fuel INV OIM Fuel O/M ~Fuel O/M&fuel TOTAL , 1993 44.2 6.6 36.7 0 5.1 26.2 6.4 '41.0 3.9 176.~1 Cum.44 ..2 50.8 87.5 87.5 92 ..6 118.8 125.2 172.2 176.1 1995 13.9 12.1 61.6 0 2.7 10.4 5.5 37.3 3.4 206.9 Cum.73.9 86.0 147.6 174.6 150.3 160.7 166,.2 203.5 206.9 2000 114.2 18.4 100.5 6.4 ~2.2 4'11I6 5.1 40.4 3.2 295.0 Cum.114.2 132.6 233.1 239.5 241.7 246.3 251.,.4 291.8 .295.0 2002 114.2 19.3 109.0 9.8 2.6 6.7 5.6 45 ..8 3\93 316 ..4 Cum.114.2 133.5 242.5 252.3 254 ..9 261.0 267 ..2 ,313.0 3I6e3 2005 114.2 20.0 111.4 24.3 5.0 25.2 6.8 62.0 3.5 372.4 ,Cum.114.2 134.2 254.6 269.9 214.9 300.1 306.9 368.,9 372.4 2010 152.8 29.1 150.8 32.0 I 7.1 38.3 7.5 69.5 3.9 491.( Cum.152.8 181.9 332.7 364.7,371 ..8 410.1 417.6 487.1 .491.0 . :0 ,~--,.."_.,........,.,~~~~.~ '( \ ..~... ( !: j.i.... \ , " '.11> " I I I ;;I.,,.""",-o--~'=~_"f.r',ji'~:_.lii "~-,._:'1 ..iIi-,1., >;;'.~. ~~~~. . .~~..... .~'''- -~iiI'io,~.....~..,"'....~~~.~-~ -:.-J. TABLE IO.lIz COMPONENTS OF ANNUAL COSTS -SUSITNA PLAN 11 1 Medium Load Forecast .(Million $) Other Susitna Susitna Hydro NGGT Thermal Coal NG Year Investment O/M DIM lov DIM Fuel fuel Total 1993 199.1 12.2 288 0 7.3 .4.7 20'.4 246.5 Cum.199.1 211.3 214.1 ,214.1 221.4 226.1 .246 ..5 1995 199.1 12.7 2.9 0 707 6.4 265·9 255.9 Cum.199.1 211.8 214.7 214.7 222.4 228.8 255.9 2000 199.1 14 ..1 3.2 0 8.8 7~8 59.6 292.6 Cum.199 ..1 213.2 216.4 I 216.4 225.2 .233.0 292116 -. 2002 294.0 22.4 3,,3 0 5•.3 0-0 325.0 Cum.294.0 316 ..4 319.7 319.7,32-5tO "325.0 325,,0 I 2005 294.0 23.8 3.5 0 5.2 0.7 16.0'343\J2 Cum.294.0 317,,8 321.~321.3 326,,5 327.2 343.2 ,, ,2010 I 294.0 26.2 3.9 lL,9 7.1 1.9 39.7,385.3 Cum.294.0 320.2 324.1 336.0 343.1 345.6 385.3 ~~~.~.~. iie t 1 e " ,I ld t --............,..~~__-_<l<£·-4--~ f ,I ;. 7,230 4,131.1 $1,130 7,165 4,026.9 $1,134 3,.964.5 7,105 $1,133 3,943.0 7,062 $1,176 TABLE 10.12:SUSITNA PROJECT DELAYED- 8,238 8,299 C4 8,360 C5 2010-2051=10.2336 (A,C,C3) 2010-2052 =10.3598 (C4) 2010~2053 =10.4824 (C5) Net Benefit Long-Term Cost f./Factors: Bas~Case Base Case Non-Susitna Susitna Susitna Q.elayed A C C3 C4 C5 OGP 10 L9J9 L9K3 LOW9 L2W5 L2W7 1/ DATES:WATANA/DC 93/2002 94/2002 94/2003 95/2004 ADDITIONS 4 Coal 3 GT's 3 GT I s 3 GTis 3 GT's 9 GT's 2007 1993*1993*1993* 200B 1993*1993*1993* 2010 2010 2010 2010 $x 10 6 (198 2 PW) 1993 -2010 $3,212.8 $3,199.4 $3,140.1 $3,137.9 $3,09ge2 2010 Cost 491.0 385.3 387.4 388ct7 394.1 2/ 2010 to 20XX Cost-5,02407 1/Dates modeled are from 1993 through 2010 in all cases. [ l '(.. 'f .;1- '.~ tl f( • I I f( [ ~'''''f J, [ [ ( i ,r-.IIiL 491.0 385.3 479.8 485 ..5 404.3 3591>5 394.2 3,212.8 3,119.4 3,295.3 J 2,639.9 2,881.9 2,805.93,344.4 8,238 7,062 7,571 8,313 6,878 6,650 6,447 'c;:. ''C' .~,'!~'"~' L4R7 680··-MW' Watana 6,470 (96)(Ii) .. ~ .. e...."""!'.:3 L9K7 228{C) 23 10.4824 9.~'J67 680MW 95 680MW 95 600 MW 04 200 MW B 280 r~w 6T 6,650 l~gD "to ............. I -<e'!!i .;(. .~ Low Load: to 2054 to 2045 6,878(C) 6,374 (D) L195 400 MW B 200 MW N 560MW 6T-- Low Low Forecast--------0.0..---1280 MW Non-Susitna Susitna ~ ·U ~Q "e.=.,.....".. 1020 MW Watana 27 8,340 (102)(A) fj"'U tEt::=§ L671 680 MW 93 340MW 02 400 toI~B 350 MW 6T ~;._-_."."",..."1 0 reE :;, 680 MW 93 400 MW B 420 MW 6T 27 8,232 7,598 (9)(B) ~;::::l _.....__...._~.Wt tMld Iroo ~\1!!'''' TABLE 10.13:WATANA PROJECT ALONE 1280 MW-·680 MW Susitna Watana Medium Load Forecast -19K3 L189 7,062 ~;$ 1,176(A) 680MW 93 600 MW 02 210 MW 6T -~ tq-1 Q -'!""";-~----"-'F-.:v:--""""""T?,T1:~"'--:r--:-~~'~~~>,~"""'"':~•."h','",:r~-:"''"''1%"':'':'i~~"".Aj''..~~l',n~~~IIl!.,,il~IIIJiIIol.!JUa I...,.....;!"'., \,1.-",o '0 t= Non-Susitna r...llJC'i L9i9 600 MW B 200MW N 630 MW 6T 8,238(A) 7,589(B) ~;t~"~~ lq..3~ ,,:*,'""~ .. ~.,It''~ -> ~:c OGP 10 System Totals ." t:=~ 11 2010 yearly- 1993-2010 LTC$tS2 .1 Hi 111 ons ~ Net Bemefit 21 Transmissi on- 11 Economic Factors:Medium Load: to 2051 10.2336 to 2043 8.9119 2/$53.5 in 2005 =$27 1982 PW -2010 =$23 1982 PW ~ ". ". 4 til ;. l.t I"~;:~.J -a,;t},) 8.If.'\',.,..... ~~v ler~ ~ $8,241 ($4) $3,259.9 486.7 4,98007 Chakachamna Watana L309 C/93 WIOO 200 CC 210 61 ...~...... e:::"..~"c:::j' $8,186 $51 $3.206.6 486.6 4.979.7 Chakachamna DC L2Z3 C/93 '$;0 ,DC/97 &c ~ 400 Coa1 4 F ,) 420 G1 {'"$'C = '"':Oil ~. c;;:......""_,.,"'.,••,~~"'vpg;,~¥T:,lIi ...."'!fl'·:;;;;;"f)ifI.....ii!$4'1J1iN i .",,1••II11II111_1-'21111 u,ttCifi';. c>•;.I~~~~~:~ e;;; $3,168.3 407.8 4,173.3 .~ $7,341 $986 DC/93'(;0,) \~/02 ~8 () 350 G1'.~.Kfli.:"~'"•ui.' L5 ·J '··"~':~.L ~ Devi 1 Canyon Watana '~. --...~.....-... it ,,'"() -;~l!tY~_,:{~~-_~,,;.....;,_..'~,'''':\.4>;:_\':!.>~'J-:;;,;..,1::::-~..7:.+-f!: ,'l!!lWA"'1'r.:::::= $7,062 $11l176 $3 11 119.4 385.3 3 11 943.0 L9K3 Watana Devil Canyon W/93 h~0 DC/02 I}V Z10 G1 '2.•': "~~{.,'"1>\,<' !.\'"\at 1 TABLE 10.14:ALTERNATIVE GENERATION PLANS t=:;.r:.:::: 5,024.7 $8,237 $3,121.8 491.0 L9J9 800 Coal 560 61 ~( Non-Susitna Plan t'::=:;-; Net Benefit 2011-:2051 $x 10 6 j1982l 2010 Case 1993-2010 10 Long-term cost (1993-2051) System Mix (Added capacity only) ~-.~.==) 0," ,,'>L1:~...c,.;:! ,',--'--'!~0 ! )':.;:<~ -".e",••' <:/ .'" $7,271 $1,450 L9EI 330 MW 1993 1492 GWh 1374 GWh $317) Chakachamna- ..1:.,-' $7,656 $2,203 L6I1 'p"ev;1 Canyon 600 MW 1993 2589 GWh ~~~.,~~ ':JC C 1 L189/ 2631 GWh Watana 680 MW./ 1993/ 3459 GWh $4,094 $7,571 TABLE 10.15:SINGLE HYDRO PROJECT JEVELOPMENTS $x 10 6 (19821 . Average Energy Firm Energy Capacity Available 10 Case-- Capital Cost (including IDC and transmission) Long-term costs (1993-2042) Net Benefits compared to flon-Susitna pl an LTC (1993-2042)of $7~589 million 1',:,.',,m.1 '",".,~I In I) 10 ~n 'u u• '0l.~_ I ~:ID,I ."J IJI Uc II fJ ! II' 1 ~. U U a r..;.} Robert Retherford Prepared for the Al aska: ...·••·H,if" International Engineering ~"'mpany Inc.1979. Associates.Economic F~""asib lity Study. Power Authori'Ey.-, REFERENCES Al aska Agreements of Wages and Benefits for Construction Trades. January 1982. Caterpillar Tractor Co.,Caterpillar Performance Handbook.1981. Code of Federal Regulations,Title 18.198L Conservation of Power ana water"Resources,Part 1 and 2.Washington,D.C.,&:>vernment Pri nt i ng Offi ce. Acres Anerican Incorporated.1981.Susitna Hydroel ectric Proj ec.t. Transmission Line Corridor Screening Closeout Re!3or1:.Prepared for the 11\1 arraPOwer AU£ffority.- •1982a.Susitna H.}(.Iroelectric Project,Feasibility Re!?2!:!.---~Prepared for the Al aska .Power Authority. ·1982e.Susitna Hydroelectric Project.Access Plan Recommenda- --tion Report.Prepared for the Alaska Power Authority."WO_ ·1983.Susitna Hydroelectric Proj ect.FERC License Appl i ca- --ti on.Prepared for the Al aska Power AUi:hority • ",\P •1982a.Susitna Hydroelectric Project,Transmission Line Cor- --r"idor Screening Closeout Re!?2!:!.Preparedfor tne ATa'SkT1'o\'ter ~uthorlty.! •1982b.Susitna Hydroelectric Project.1980-81 Geotechnical -......,..!i.~port.Prepared for the Al aska Power Autnorlty. •1982c.Sus itna Hydl'oe 1ectri c Proj ect.1982 S uppl ement to the ---'1980...81 Geotechnical Report.Prepared for fhe Al aska Power == ~y. •19820.Susitna Hydroelectric Project.Subtask 2.10 -Access ---:'Route Selection Report.Prepared for the A~'I'-:as~k~a--=P~o-we-r~A~u"l'"'th:-o-r~i-:-t;a- :JI'",."~rtPW:f/iiiIi'"''j!"'"'".---_iItlL. ,,.,.;,-" 11 '0 n i I '01 ~n < '11 'G' ~O 11 ~:10 .!~J U IJ I J,) fJ J] U tI. U I ~ r n: ~ \ r-.. ! fl~ l I I l l 'f) 1 I i I ·m n· ·m m SEE INSET __ ~ n :j) i.- u- I, , . 'fJ 11 i IJ j 1.1 ~ m IJ tl LOCATION MAP ~ . Jj ll FJGURt: 4 .I r. "~.~ ¥111 ~-.:r ~~_,.-~-~--..........,._---- ~ ........ ------· I I ' {I ; I I I I I ;I ~. li I 't l ! >I unM:NCI':: u• IIW''·-U!!Gs,J:zso,ooo ~~It~:OO.AIIIJ, ALt!KA AU~NM~:~~:~:_-~_0_R_s ___________________ Ff~G~UR~E~4~.2~~~~~!J!~~· --~··-----.-.111!111"'-~---'""1'""" .......... -----·--....... --.................. I ~ ,...--------··-----·-· ------------------~ , ·n In ·a T-~~ '".'•.· · .. hJ ~] ,.. ~C---H--~ Jl ·----:_y-~~ .. r:.l lr~ n ~ ~! tJ J It /J l ll I] lJ T111• TM8 .... ACCESS PLAN !3 (NORTH) "SUSITNA HYDROELECTRIC PROJECT ALTERNATIVE ACCESS PLAN" Ft$URE 4.3 ~-----------:.... --____________________ __, fJ u ~-,,_ ..... ~-·~~--~·----,--_,, _____ ,,,, __________ ::, .. " _____________ _... ______ __.,--,··' " TU r:t~t~; ~· c ~\ ,, f;. ., f,c a o I f l loo I II· F ]. . I l ·· fl · ACCESS PLAN IS (SOUTH) tJ "SUSITNA HYDROELECTRIC PROJECT lJ ALTERNATIVE ACCESS PLAN 11 I . u . FIGURE 4. 4 ~~~m\ \ ~------~~--------·-----------...01 ) I ~. I ' ,. '' .. :·;-· I . -------_----·------~_-----~==--· -~-_--__ · _-_-_~·_·--·-_----=-·~_--=· =------------_----_---_--_--.. -=_--_·-_-_-_·····--_~--_--_~--~l· .. . !:_~_-~ Q; n . -...J.:A-1"P ·o ·-~---._ TI 1 ... ·n ,.e g ~· ~~~~~~~~~~~~ ·g ·--~::t-==~9'~l:::.~~~~-<"~~~IJ'..-+--+- u u I tJ tJ t • tJ u tJ u ' ... . .. .,., ACCESS PLAN 18 (PROPOSED) "SUSITNA HYDROELECTRIC PROJECT AL TERNAT1VE ACCESS PLAN II ':::.: f, 1:-J; ... f .: --_,_,.·· •o , ... I\ I· I. l i ! ' 1 l' ,. I( 0 ( ! . FIGURE 4.5 \ ~ltmJ \. , '-----------~~-------------------.-.Jl:i ' •b ~n ·n ll I ·:n .i n I ·n l~Jl :!O ' '[j t] .u Ll I fJ ~J [J u tJ TIME FRAME FOR EXPECTED ISSUE OF FERC LICENCE DIVERSION CONSTRUCTION INITIAL ACCESS CONSTRUCT! PLAN 18 ( DEN ALl -NORTH ) PLAN 13 (NORTH ) PLAN 16 (SOUTH) NOTES; .. ... . ..,..,... __ ·---... SCHEDULE FOR ACCESS AND DIVERSiON 198S I I 1 ACCESS REQUIRED NO LATER THAN I TtiiS DATE TO I SUPPORT DIVERS CONSTRUCTION llllllllllllllll I . -· . -:. . · ~ ( I) I I ) Wllllli!l!!ll ACTIVITY START COULD BE DELAYED AND OIVERS:ON STILL MET. ( q LATEST START DATE OF CONSTRUCTION ACTIVITY • I I I I I I l I . I I I l I l I. I I I I I r I I l l \ (I 1- LEGEND __. rltC)POUDIIOI\i) •••••• P!IOPOstD MILIIOA%1 _, ________ _ ICOO "00 tJ 1400 !! 1300 ! ltOO liDO ~ I DOD toO eoo ...... ~ ·'"lo+~.'-~:,~ .... -.,, CUT ' SECTION TYPICAL 'SIOEHILL SCALE 8 .... ft·~ao· 100' IIJIEAK--1 [IMIIN[ TUMIAIIOOND ~NT WELL -PLAN FACILITY AT RAILHEAD ~tAlE A SUSITNA RIVER £lRIDGE HIGH lEVEL ICALI c HIGH oo WDIIKSHOI' CJ TYPICAL RAILROAD CROSS SCAl[ I BO RROW' SECTION TYPICAL 'SIDE SCALE I ......... _ ... _,.. __ ,_.,._ .. ___ ... ---... t o oo -~ ru:';, tNCtt•l> rt£Tl t D L -T£r:T SCAl D lOO 400 ft INCH • 700 rEEfl SCALE C ~ F[I;T ~ ltiHCH·~run SCAlE 8 . roo F[r:T ~~ 0 toD_=a If INCII •100 rt:~, seALt Art~-· ~-- \. .~ f. ., n l ] FIGURe 6; _~.-::l 4·rff . ..--~'~.-(.",..- V v ____---------------r:"~il .I i ! 1 I LEGEND'I! ~'RAILROAD EXTENSlf ______PROPOSED ACCES~ ROAD ! ----PROf'OSED TRANSMISLINE' ; ---....INTERTIe , VK*~~}:,?j;J IMl'OUN'ClMENT AREA' 11)-=r/ 1~ SCALE ~4 8 MILESr .~ ,) ) • J'C~, )\1 1'~~' )"-..'p-v' j' ...,,-' ~~..CONSTRUCTION,VILLME ...;f £\5' .//~//WATANA CAMPSITE ~p(J~.~!!~~/. :/;.- J~('-p. "'1h"Y "~~',r."",\......~.:. ....~.:;'*~..... ~~. J I" I ( ......_,....~..- '1,,~~ -~~'--_."....~~'_..>-_:_--'......"...:;.~~~~, D ® "'-- '~ /.'~l'IfI/"'J'~./·.~.'\ ,!.•, •••• )l #'•~,• (, {'-. o CnEI!Il j\ /'--'~, I CONSTRUCTION VILLAGE /CONSTRUCTION CAMP I, "(" I•I i I... I I I l I I ,J~ "~;';;"~:'-i••;~..::~'''':~:-'- PROPOSED PROJECT FEATURES .....-~_I " oG) ~ ~.~i.·,~~~,..;.,.~_..'.__"','."".~..""_.'", i I'.. Li:1 . '~':"'-~1 .l'1 ,. I .1 'J([ "1'1 ji I I ~I I""~"1 I 'Il'I jl 1(41 .;•Q'""~.. •.'••• .,"• ••t •_.~(.,.'.•'.-•.'•_~.• ••..• .• ,;.II ~.. ~ FIGURE 6.2 ,,[LAY'BUILDIN, MICIIOWAVE TOWEIt ot} TO D£VIl..•.•~.,.. 'j ITOitAGE GUILDI"' Jm.~,- .~ o o ICO lO(1 rUT SClol£AE -'_.iiiIIl n'NCtt."OO'££TJ lOO'..r/" SWITCHYARO PLAN SCALE A "., III .1'--j~:L Ii---- REWOVE '"FUTURE ESTE" LFI ~ 4---..,,- UTE" Lf2 f~d 'lr1LLOW Ltll HI..... ~- GOLD CREEK SWITCHYARD SINGLE LINE DIAGRAM AND PLAN 11.1 otH:...T.,HI " I .--.,---. u .nAHA SINGLE LINE DIAGRAM -----,II I I I I I ....-~-------I-T-... I " I.e.I', ili JI,' ''1'."'H>'T u I I UI 11I,'T', (·-i:-.....~H:•..,-,n,'f' l . I ' \i I =t=i=-.--T-r '=l-~t.---:--~-L-r-·--+--.J I I I,,"-I (.-~--{ <.-11:"i (.4~., f , I I I I I IuL4 Il(VlL Il(VIL CANTON C""YDM IfUTU"EI IrUTU"[' ,"'--4_I-. .1.1,s 'T' I I'"I II-i/-J.-I'-' 'lrILLOW LWt .1.1 .-1 II rl~~H LI 'lrATANA 4----...: H>- C:J 'FUTUlIII WII.LOW LIr, I I I I I Ic·"-i c·--...t.., ---r-,;~~;;;;-----rT------![~~ "IIJlt:TUlIIII I "L W 111 L.-+-!t-.~"T..!I-.• , 1"'1'II . 'I IrJIT I \ --.--l-J.----_L _ o Jf !!..;i •...'•.~.';,(i •".li.•i;'..~_:,,".~.~.:=;.,.'C',~...--...0.:"':~__,.....-....\-:t._,~~"~..;;~...:..."",,__~0".'J.'.'"_."_._-~~_._.~~.......•.....................).4 !.,roo "..:....:'r ;.-,.~I ::;::~'...J ~·nnr-'..·?...~..-'CM---&r-": ",;If I I ..;,.;~.~.:•.ii·1 !.. !'j~LI ti dcc~"~~1 'f ":J.11, "I :1',II;1. """1 j "I.11.,:H ,~:1 I \~~:-'......".l.,,,') " • I >.~';':;: ,-:;' .:;: I £LA' [ f SfATIC VAIl i COWI'£NSIoT1lll i F"'e>ORE ~, r~-------- I,, i I -~HAI~OA""SI ._..-~---·_~71 f L', "E"OVE II,UTUltE SHIINT IIE'CrOft GOLD CREEK '115111'2, ~ -'993 ---2002 6.II 170 MW UNITS 1 :Z'OMYA".""D-'"WV .. ~ i.......~I --.. 1'.M'LES LWlI 1'__I-1-1"--r--.I II: I r1, I .I-f" 1 I1 , 1 I'-. I I _~~_, I I ~I,J..I r I :J I t... 1 I I,I I I, I '~-~-t --...--ILS ,L4 8 .lIlESIL, I I~-------------------------,I,I I I r-t ---f ~~21":-LLAfIClIf 1I-~--~-J-.----__~-__JII:I I :•",,,,..--.-,,,CCb",," ,~-.I ._.._.I I"I ." ·.I 'r-1',"-1" l.-i .........f-- DEVIL -~..,.._t.I f---'I ",,,CANYON ••••••'._I 1 I ,I .-~--i ....-t I I I I :1:I ;"":I :&;I"t'I.••.,.••,IrI I . I I'II-~-.!----~-L---4-L_'__II\I •..I.-..v---t I , .- .-.4.J'16?M.l\'o~m:~.J UNIVERSITY ""C"OR~GEI ------_.., ---------., I I I I I I ~.!J.w.! '"onl1.1 ,_J l, I I I I r l ,rLl L ~.r.'1'r-I ..~L AIjI;HORAGC MUfjlCIPAL UGHT a POWEll LUI II wILEs LIll KNIK ARM LUI RAILBELT345 KV TRANSMISSION SYSTEM SINGLE LINE DIAGRAM ~~~M:~I - 15 N"IIll ~315-115lCV 4..MILD I I 250 IlVA ,~_w:_..~~.'451Z30·l!lIlCV J'-,.r .'--.., I , I I(1 1 r Ln l1T". ,.-J r r----,u:t •.__"'I I J••,I ~i I I I ~ SHUlIT 't'-I l.H""",.'.__L ~-"""."~r~~•.'__...:.,iJU.:::lIltcNN£'uC;ii:'£----Et.!L ·..rT"1.J--r-,{J----t •J-o-..._.+1'~A111l •--.J I __L I 'I" .,r~~G WI 15';VA ... ll.OW 315'1!81lV L I I I I I" I I ,')0 ,~;"~_,.,=---.....,;;~;c.~~~.~..."'~.-;......;....:.._.~__....:::-_~......:__~.....~.,._,......;,,_~_.........._.......~..........._......~,-_.",,:_.._~.~«. :1 .•~__""~!'l"'!'!••.-~_••,="!,,,_.--------:'~•.__. .~I ·:'\~I r! \!~,nl'11 'i >1 I~ll H- I ~'II I I I I (J enLIJI-::>oII: Z.o I-U) tJ)-:eenz ~... LLI>-~.«za:: IJJ ~:..J <C ~ l.IJa::: <C >-C .~t-en .J <ta: I-z iLl c.:> • • •; l .. ,j·",......"'lf ill.,.n,~---,f].-·0[g!~ I ~n JJ IJ ;IJ ~.r 1[.[J..•·~',:.I . ,'JJ tJI• J] lJ 11 ~j, lJ :a lJ• ·lJ I t:!:l _......_.. ..•.:1";-_:,.~';.. G ~ (I 3:o... 'lL. :r (/) cf U... cf :;) Z Z cf 800 700 300 1997 '-----1 100 1996199519941993199219911990 :~;~;~;~;~;~;~~~~~;~;;;~:~:- YEARS 19891988 ...._--..........-.. 196719861985198419831get ~""<;<maWfffWIiE«:;&f.i1f.WJi%lffi[#.:;:mHMM'l!P~'~"!','i'~r"~"@"1!i~I*~.$fWl!@I@lj$;~tiJF;iWl1~Il!j*@jl&'lHf.mm I L J 0o 500 4000 3500 I---~I I I I I-"I .'-1~-t-~+---+~-+~~~-2I""'~::+I I I I I I I 600 (/) a:: 4 -'-' SOO g r-r----t----t--r--+-+-__m...---L~L-lJ~40'j 3000 2000 1000 ~o ..Iu. %en 4u IIJ Z 2 ..I -'i II)a:.c ..I...oa ~2500 IIJ 1500 >~ ..I ~ :I! ::l U WATANA DEVELOPMENT ..CUMUlATIVE AND ANNUAL CASU FLOW •.••::L.JANUARY,1982 DOLlARS JPD[(I FIGURE B.I IIUnl] .,:~'~r-'._"""'_-_.",.._~~~-~-~":~::>....:.";,~~.'-.-~-'_._-'>-----','-'-',',-_._::,"'-"",...~.....,--.':-'"'_i'--~.,._.',",--~:~--'----'~...;:;...~~--•+~:.,<.".t':'..';:",."-,~-~.~_.~.,._--,_.,~.. I,'}:"r-l'"~~_.t······ '...·..•.•:..:1..<I'«<< <<..<".I.'::'·.:•..•:••.••.•..••.'.•.•,,\I ''E _i "<I!'' ~'I~l,,:~j~~;:..~ .?l!I ,,;<~t H:I;:.,-');fi ~·_;:tJ,:_r ~.~11 '.Ii I '.~:"I T...~--,'l ; H ' jj ,11· ;1. I I I I' I I I I I I I I I •_I'~:~...'----...0 ~..._;".•• "",)-\••<bi! ," ft ~~~~ FIGURE 9.2 4CO -CD II: oct -'..J: 300 0 0 .... 0 CD Z 0 :J 200 ..J ~- 3l: 0 ..J.... :r '00 CD 0< 0 ..J oct:::>z %< 0 2003200220012000'99919971998 YEA.RS ....,..,-_.. CUMUL*'VE CASHIFlOW=:J,~ 1996 ~~~~I.ill'''~ DEVIL CANYON DEVELOPMENT CUMULATIVE AND ANNUAL CASH FLOW JANUARY,1982 DOLLARS 19951994'9931992 .__.hWWi1.?tmW*~~~z~llt••1'1~.-- o 500 1000 1500 2000 ~ it 1&1>i=, ~ ::2' 2 ::2o :I: :l'o 0lI II: ~... -'co ILo CDzc :J ..J :I :-:; "~~-~~,,>,-<'A ,,';~~£~{f~~~<~_'~~~~..mi,il ....~_._..-! ; ,r-"l -:::;::,:;:,:;'---- ",.-...-.~,,._4"'......_=C::rz=::::III ._M.r-_ ,I I ;'1.;. 1 ,I i :\1 I "II Io'I-'I~, .~,:\,,:'1:,1 ".',',····~;jl •.'-.,>':k'.i< ,';..".'....~;1\_ ~i~~, '.:t""""1;,t~.:i r:1 m ••11 " ~ II ~,~t oil ......~~.....; [jjJ -_..--_...r--,....I •..;•••1 (i l&oo en Zo ..J ::! :::IE it:o .J lL ::z:en octu ..J<:::t Z Z oct FIGURE 8.3 ...,:.'..':':',:''''':.'1'...~~:-",,;.,'~~.~,,,-~,~.,,~,,.,,,,,,,,- 1350 600 550 500 (IIa: 450<..J ..Joo 400 350 300 250 50 o 2002 20032000200'19991997199B19951996:~94199319921991 ___....:.:.__.~:~.;:.-......::.:.....__,.,-~.__;.:.....,.~...',.,..~.~,,_,i~J.L.~...:.[- 1990 ......:.......-.;..'" 1989 \,) YEAR.S SUSITNA HYDROELECTRIC PROJECT CUMULATIVE a ANNUAL CASH FLOW ENTIRE PROJECT JANUARY.1982 DOLLARS 1988198719861984198519831982 500 6500 1500 ~~""";'.~~';';l.......--~~.•~~. :~:~;:~;;~;;~;~~;:'.'._._.'._.'.. 6000 I I I I I I I I ~';';'n;';';';':.;.;.:..........1 1 I I I I I I I I ••00 -I 1 I I I I I I :11 " ",:, ~I I I I I I ~1 ~~~~~ '••~~Ww.V 4500 :•....::."/1 1 I 1!4000 I 11.lf _~~/Y,:.I; :::::::::.::::::::::::::::::::~::;:::::;::::::::::::::::::::::::::::.:::::::::::::::::./~~C MULATI~E CAt FLOY '000 I I I ~llllllllllll{$",@<I'lji'lllj'--'~~~I•• .~.'B I_IPI __B__II~ .......,¥il .•"tt.PPANA 4f4 ,"a'-_-" :1 c ~~.....~",.,;-ii>:"!:"~'-".•~__";T --...,~ ¥fi.'1.~i ....--.T"....='=r-'r .".•.:'" ~}I I.. '~~l~1i[I Lt,},'Ji:;;;;11 •'\.•1 rll jl O'J I ~,~]I "'11'll I II i II I Dill ~]I I I I I I I I .d_~.,-~~ ~,~-~~~e I ""• " ~ 13 10 I corn:lI0.0ll,I I I I _''''n'.............''.....: 011 I 1 I I ,j,r •.J...:. ~I I I I ~1 'd .TAU ..,'..IMTWua.:..,.."~IItA"1\......,,'Ymll. It IIAIN 0.-11 '"A'"'''~)'lii~"K'.'~)1l.'lo)'li ~ :'..:: ~ II, I:Z, ~ (llI 10. oJ 0: 0' ~ 01 13: I~ 1994 ,l;-t ""'"0 ••--.~.•_~.;"'"."',•..- 19931992. ._--_..._~-- "'ua 1!iS1 ...•..,. 19!1O ~~1. /:J1l9 ...""",~-,:~~::-~::-""~",,~,,,,~~~~:;...~~I---':;~~"-'~--T-"'":~~~~~-+----;'~~~:::7 D 1901t1917 ~.olJ'W""""'''''''''~''I ...~,............, 1986 ""- ~.......... •$dU.-.,.................-.....:. 1985_.........- "8411113oe.s.t:RlPTlcm CIS ell lI'2l""f1.~ACC£U ~srt1!i FAOUTl[S 07 011 DlVElI_TUNMELlI 041 MAIN ACCUS CIS ~'I iii II, ':,Ij,y 'i:?', I! :'f~·~..,;_~~jol'".;"~...-~"·,~_"":"~-_,,,,,,,,""'~,~~"~,.;';"';·~~..,..lh,~*.JiO,,:>t"".F"~.;....-,"";~_~i.-;:..;......"~~~~,~,..,.."",,,,~....1>1Hj _.," "'11:.J: ~~U 11'I Sttlnlnfllllll,IIIHII,,'n ""ll.IWWtII.IUMWnWIl lDtnltl1Wllff.!t~m It••a'.lt ..........,. '4 IS, • 1 1 II I I ,I - "1t""NU"ItI,"lflltnmnll"rtntH"~"'"'tllm"l" - r"~lnl'tMfI1ltl""fltlm4'"'."''"~.....''i .......,•••••'tR .•III.' tMlrll.'IlRIIUJIJ IDI••••••••• " 21), 21 1' 2% 23 24 ;1 I ~II 51 1\l!l8lHE J G(ItEllATOlIS •,~ 33 :: j I \I I I I I I I I I J -~T-"·- I f'--'- is ;f( ~. 'I ~ ~I !;1 '41.~'~"':"~""..1 ,..1~i~1 .,.J >';•."J:11"'...;,,,"J',,'.'::{ ,:::,'cll WATANA CONSTRUCTION SCHEDULE ,...~.aea··/p"ca.rtal ___'lit ••C"¥A'nOII"~.noc,,"A",,1lIT"""".,....~.CC*CItl.T'C •••,.~._CM4-e:AI./IUcTatc:AL ---"",OUIII,."", FIGURE 9.1 [jj] ........."...i'o.,.. --------rl '"'Itt'1997 19M J~zooo 2001 2002 2005 -. ,... I. T t I i- i -t..._..t-~ ...."............,........... --.",... •IiI'.. 1 U.l.J•.u -. I .""""".,.,...,..., ..........."""'""'"""' ..........'a•• .."'"'............. .....mmtmlll1lnat •1U~1IIlIt'_ ...,........-.:,.. .,.........'''"..... *.....- ......."",..... _...=l:i....l..nH ...::.-.. .i.I.,.,•.~,.r.r"I r I j .,.,.,.... RmltmUflUfmHI1U11.j ,,8._. MUIINMIfI"lItiflilln' -.a,JY I ...._1lI IIf.&lJF_I ..1NIMt..........H~'t",....lttntUI _""iJ....J;,.,;.~......,._~... I I J,••••t.f.f•••••J.,.'.I!I.iat •••,.,~(~~'i-.'••ID'··..,1 , ....c .....1 I:I ""'ItH4IMtNfN1nIm8'...........~~IftUtHII..... ~LUftY/~.t !mFrs.1 I I I I §-~MM=~~1I11b f 0J i ;;.~Ft ~_.~- l' I I I I I·--~--·-~~'~------ I··~_.••~_>_ 'o>i=,"'" "-I I I I I I~--·-~--,. I I I J .._...,,~_..LEGEND r""A 'CQ'"IPAt:UtW:I ""rullllllll"IJC.....fiOWffOL'CA'f1O'II11lIJTMIr[ ......."",R.I.r ~COIICfIIO"a .,.,.,.,LolCH .....a::lUn.fDTJIICAl. --_.."'OUtc:MIIrJlff ._-._.I -~'---_. DEVIL CANYON CONSTRUCTION SCHEDULE ,_._,-_... FIGURE 9.2 Iii "\...: ••,..;,~<-_.,.,........."..".....;..."',---,,..'._,--..--""'..;,.;.~~_;,--<-_.__:__~~"Cv_.,__,~.""~~~,";,,,,,,~__~·.,,_·~.,_.__.~.....,,~llt ,-,,~_,Q_~.._..:,~-~.~~-,_.__....~-,..-,-"~-''-"_._.----,~,---_.....""".--,..-~~-",,._--'...............~.-"'---'-'-_._-,""~~~'~'.._*~...~ -~ ~~/."., ". '/V v / LOW LOAD FORECAST BIAS /V.V./ //./ /£'BASECASE .I V // // /V . ~V ./".~~- . \'I ~:·(.iU._.~1~ 550045003500 ,,!,_...It(-~~,~.~ ~5001500 ,........"",,, "!if ~,Ziit ..;;;:::-::::il:i NET BENEFIT $x106 (1982 $) . '.;;~".,-2\ll •,~.::»oC;I;/ (500)0 500 !rL.···-l (1500) ;':....1f·-::} (~500) t,··'·:'i (3500)(4500) .2 1.0 ~"tt ,,~ .1 .8 .9 )-.7 t- -l ~.•6 £Don:::a...5 w>1-.4 <:( -l ::> ;E .3 ::>o f~~ r ,1 ; .-, J I itt?JI~r"TP~,~-_""lr~" SUSITNAMULTIVAHIATE SENSITIVITY ANALYSIS CUMULATIVE PROBABILITY VS.NET BENEFITS I FIGURE 10.1 ] 20;0 FlGURE 10.2 SUSITNA PLAN 2005 MEDIUM LOt\DFORECAST 2000 YEAR J 1995 PERCENT RESERVE VS.TIME 10 • 1990 20 40 30 90 80 70 z 60 (!)a: <[ :E lIJ>a: lIJen LU 50a: n U L 't "j 1,. I I I• ... 2.0102005 MEDIUM I_OAO FORECAST- 2000 YEAR NON SUSITNA PLAN ANNUAL COSTS 1995 YEARLY 1990 150 500 200 250 300 400 450 350z 9 ..J :E I- (,t) o (,J ~a eel 1.&.1,.. t It l [ L I I,FIGURE 10.3~------~:-.--.-._......--.~-_:.-:.:.:.:.:.:.':.:.-:.~:.:.:.:.:.:.:.-::.:.-:-::-:.:.:.:.-::.:.:.:.:.:.-=-----_....:..:.=.:.:.;.;:.,.;:.:.:.:;...,.----I '..-............."'l.'"-..._.."~'. 1·.":1 II L~{t iI,r I j j 1 I i j 1 t J -~il i i 1 l- I j "I I Ii -~ ..+4---COAL FUEL COSTS ~-----COAL 0 &M 20102005 YEAR 2000 CC oaM OTHERS NON-SUSITNAF'LAN MEDIUM L.OAD FORECAST 1993 176.1 e=rllllf-NG 0 a M100 2.00-l-------------fZ 500-1-------------------491.0 -.-..---------~ ••11II---OTHERS: (OIL/HYDRO) MN\N\J"'----CC NG FUEL COST -!J'J Zo ..J ..J-~ ~3ao+-------i29i5~.0~---~I.---i I- CIJo (.) ..Joct ::l Z Z ~ .....---_._---.,,_.---------------------------, '0 o u u u, u ,~ I ,..•FIGURE 10.4.'..''-:===::::::=========:::===::::====:::::;:::::::=~_~....:-:".±_~.~.~..~.~"';""-------J......,:. •_------____'w...'** ... r ., [':-'j. ~:J I . I .' 'C'" ..'I t' ·u·;---.j. j- ....... t I [.. i, ..'~I [.,'- :,1 1 ;J L C r; .lb • 385.3 343.2 111111 FiaUREIO.5 325.0 o '-~ 1I .".,.......',' I ~- SUSITNA PLAN MEDIUM LOAD FORECAST 400-+-------------------------------------1 500~-----------"".----l .Z-___"",~_"..""_.....•.,"'"'",.,-......~_.-'-'-~~~...........fiIoioI;.--..."..~~~...-.......-..-....--....,.---"II ~lioo;.,,-......................-...... ..~~~"..".....,.cfc ....,...'~-'-T -.....,...~,...........~~1 .....=...•,.&~'..:r-~----...... r'l IL, [~ f"!O' [ [, t [~ I Ii i ~ [_.~ .''J. ,~ r [ r, t~ T 'C 1[ .. i[i _: f r~ .~ I .(1 2050 . . / ,V -/ /". / ". NON-SUSITNA PLAN ~/ I V /" //' /' /' / .£/ ·.SUSITNA PLAN./ ./ / / V / /. /, MODELED PLAN Ij/. ~Vi , ¥ ,ECONOMIC EXTENSION I ....... . II 1 ,I /J / / / ......./ ~:. FIGURE 10.6 1000 2000 o 1990 2000 2010 2020 2030 2040 YEAR MEDIUM (.OAD FORECAST-LONG TERM COSTS 3000 6000 7000 9000 8000 fJ)...fJ)o (J :E LlJ...~5000 rn ~ ~ Q. I.IJ ~4000 .J ;:):e=: ;:) (.) [ 1 [, It 1 fI'i'\ , i: f'\:g'~ i 1J~' IT [: 1[~ ,\..' R(,'" '+.J '[' 'c: '[-' ~[ L f[ i [ ,[ ,