HomeMy WebLinkAboutNatural Gas and Electric Power Alternatives for the Railbelt 1981I
I
.,
I
I
I
I
I
I
I
l
r
NATURAL GAS AND ELECTRIC POWER:
AL~ERNATIVES FOR THE RAILBELT
By
GREGG K. ERICKSON
For
The Legislative Affairs Agency
Alaska State Legislature
March, 1981
Libr~ry
c~~ee c.~f t'~~
FILE CA BINET
1"--
1.0
1"--
C'\1
C'\1
0')
0
0
0
1.0
1.0
1"--
M
M
NATURAL GAS AND ELECTRIC POWER:
ALTERNATIVES FOR THE RAILBELT
By
GREGG K. ERICKSON
For
The Legislative Affairs Agency
Alaska State Legislature
March, 1981
ARLIS
Alaska Resources Libran· & Information Services
Librarv Building. Suite 111
321 f Providence Drive
Anchorage, AK 99508-!614
FOREWORD
This study could not have been completed without the assis-
tance --and in some cases, the forbearance --of many in-
dividuals. Foremost among these are Mark Wittow and Brian
Rogers, who provided encouragement and moral support when it
was most needed.
Ward Swift was generous in sharing his hard won knowledge of
the gas situation in Cook Inlet. Lois Kramer provided indis-
pensable assistance in making convoluted sentences more under-
standable, and in other important ways, as did Constance
Barlow. Frederick Boness, who prepared the appendix on the
Fuel Use Act, and Arlon Tussing were the author's sources
for many useful. insights.
For important lessons long ago taught, in this and other areas,
a special debt to Dale Teel is acknowledged. Like the others;
he bears no responsibility for the conclusions presented here.
The work which follows was scheduled for.completion some months
ago. Though the delay is regrettable, the result has been
fortunate: It has allowed the author to use and build upon the
work of the many other consultants to the House ~r Al~rna
tives Committee .. More importantly, the issues raised by the
Susitna proposal remain very much before Alaska's decision-
makers, and the questions addressed here are, as the lawyers
say; more "ripe" than they would have been.
INTRODUCTION
This study was commissioned by the House Power Alternatives
Committee of the Alaska Legislature to review the "economic,
technical and political feasibility of future development of a
natural gas-based electrical economy in the Railbelt area of
Alaska."[l] Although not specifically mentioned in the con-
tract under which it was prepared, an underlying purpose of
this report is to assist the legislature in its consideration
of the proposed Susitna hydroelectric project, and Railbelt
energy needs generally.
Other i~vestigators have reviewed the potential of natural gas
as an alternative to Susitna. All have concluded that natural
gas is not a "realistic alternative" for "equivalent power
supplies".[2] I agree completely. The Susitna project will
presumably produce power for centuries, whereas the life of
Alaska's known gas resources, at any reasonably projected rate
of consumption, are measured in decades.
But posing the question in terms of alternatiyes for "equiva-
lent power supplies" evades the issues of real concern to
policy-makers, whether they are already convinced that Susitna
should proceed, or still harboring doubts about the project.
In either case, the first real issue of concern is whether
there is likely to be sufficient natural gas physically avail-
able to meet Railbelt power needs between now and 1995 or 2GOO.
To this question my answer is an only slightly qualified "yes."
The second real issue is what must be done to assure that the
physically available gas will actually be provided to power
producers when they need it, and at prices they (and their
C . customers) can afford to pay.
Here the answer is not so simple, but this much is certain:
During the next 20 years the lowest possible energy costs will
not be approached unless there is a substantial realignment of
the decentralized and largely uncoordinated decision-making
that has guided Railbelt power development in the past.
These are the issues to which this study is addressed. In
analyzing them I have assumed that questions of natural gas
availability and price will remain central to Railbelt power
planning through the end of this century. There is no doubt
that this will be the case if Susitna (or a very large coal-
fired generation facility) is not built. Even if the decision
to go ahead with Susitna is made this year or next, it is still
prudent to carry the analysis to 2000, since long completion
delays on construction projects of Susitna's magnitude are
certainly possible. In any event, the policy conclusions I
-2-
have reached would not be much different if th.e analysis had
been cut off at 1995,, or even 1993: There is plenty of gas,
even und·er very conservative assumptions, but a substantial
rethinking of the state's role is ne~essary if it is to be made
available for Railbelt power needs on a timely and economical
basis.
-3-
I.
In compaiisbn with ~ny i~~s6riible pioj~~ilon of in-state demand
for energy, Alaska's natural gas resource base is immense. The
annual consumption of all electrical utility natural gas users
in the Railbelt accounts for a little over one percent of the
remaining proved reserves of non-associated gas in the Cook
Inlet Area.[3] Even if the Railbelt's entire electricity pro-
duction came from natural gas, it would not exhaust the known
Cook Inlet resource base until the year 2071.[4]
Looking at the question of physical availability another way,
electrical energy that may be produced annually by the combined
Watana and Devil Canyon Dams of the Susitna Project could also
be produced for 37 years with existing reserves of non-associated
gas in the Cook Inlet Basin.[S]
Inclusion of the North Slope gas reserves moves these calcula-
tions out of the impressive, into the mind-boggling: The
state's royalty share of the gas moving from Prudhoe Bay in the
proposed gas pipeline would be sufficient to supply the Railbelt's
entire electrical energy requirement (apart from existing coal
and hydro capacity), and have enough left over to meet the
requirements of an as yet unbuilt natural gas distribution
system for Fairbanks.[6]
.:.4-
.These rather startling figures do not prove tha:t natural gas
will actually be available for power generation well into the
next century, but they do show the relative magnitudes of
Alaska's natural gas supplies. If enough natural ~as is not
available to meet the region's electric power needs between now
and 2000, the reasorts will not include physical unavailability
of natural gas; they will relate instead to factors such as
competitive demands for gas that could push prices too high to
compete with other generation modes, or federal policies that
could forbid the use of gas for making electric power. These
are important considerations, but before turning to them, a
more rigorous discussion is necessary of the expected magnitude
of Railbelt energy needs and the quantities of gas available to
meet them.
II.
According to the Alaska Oil and Gas Conservation Commission the
Cook Inlet Region contains a little more than 3.7 trillion cubic
feet (Tcf)* of "estimated remaining recoverable reserves."[7]
*I have denominated natural gas in trillion cubic feet (Tcf)
when discussing reserves, in billion cubic feet (Bcf) when
considering flows (as in "2 Bcf daily pipeline through-put"),
in thousand cubic feet (Mcf) in relation to prices, and in
cubic feet (cf) when considering output ratios (as in "15.5
cubic per KWh) . · ··.
-5-
Throughout this study I have used the slightly higher (3.9 Tcf)
figure published by the Battelle group,[8} since the latter
includes the gas wliich has been '''rented''. fo oil producers for
reinjection, and which is clearly a relevant part of the
resource base. The Battelle figures, like those of the Oil and
Gas Conservation Commission, are very conservative.[9]
Conservative figures are appropriate for this type of analysis,
where an over-estimation could lead to serious problems. This
is particularly true since recent discoveries and additions to
known reserves have not kept pace with withdrawals for local
consumption and export. Exploratory drilling in the southern
part of the Cook Inlet area on offshore federal leases, as far
as is publicly known, has been discouraging.
On the other hand, officials of the Pacific Alaska LNG Associ-
ates, which hopes to export Cook Inlet gas in liquefied form to
California, a project about which I will have much to say
later, argue that it is foolish to assume that no further
discoveries of gas will be made in the Cook Inlet Basin, and
suggest that additional discoveries have already been made in
several areas which are not reflected in the official reserves
figures. [10]
The critics of the current official reserves figures are almost
certainly ri~ht: More gas has been discovered than the reserves
'-6-
owners have publicly announced. More will continue to be
discovered. Moreover, the state intends in May, 1981, to offer
leases on more than 200 tracts scattered about the region, and
reports that industry iriterest is higher than expected. Still,
no one can say with any reasonable certainty how much addi-
tional gas will be discovered. In any event, the reserves are
already so large in relation to local energy needs that their
expansion is not very significant from the standpoint of
physical availability. Indeed, as I will show later, the
growth of Cook Inlet reserves might actually make it harder for
local utilities to obtain commitments of gas to serve their
customers.
Assessing the significance of North Slope gas reserves presents
a different problem. The state estimates that between 33.5 and
37.8 Tcf of gas are physically available in the Prudhoe Bay
area. Of this amount, 29.0 Tcf are essentially certain to be
recoverable if and when a pipeline is built to the rest of the
U.S.[ll] Available on the North Slope does not mean available,
even physically available, for generating electricity, however.
If the Alaska Northwest pipeline is built, these reserves will
become physically available in the Railbelt area. But it is
clear that this will not happen unless most of the gas is
destined for markets outside Alaska. Nevertheless, even a tiny
percentage of this gas stream would be a very large increment
-7-
to the Railbelt's energy resources. Moreover, as discussed
below, it could have a most dramatic impact on energy prices
throughout the region.
Unfortunately for Alaska energy consumers, construction of the
pipeline is far from certain, requiring power planners to
assume that in the worst case only Cook Inlet gas will be
available.
I II.
The uncertainties surrounding natural gas reserves are
mirrored --and perhaps magnified --on the other side of the
supply/demand equation. Fortunately, much recent investigation
has been devoted to elucidating the components and determinants
of Railbelt energy demand over the period between now and the
year 2000.[12]
All investigators agree on one key point --any prediction of
Railbelt needs beyond the next five to ten years is extremely I .
uncertain. The range of possibility is wide, stretching from
possible decreases in consumption to growth rates well above
the national average, the latter being associated with sub-
stantial increases in population and economic activity, coupled
with continued low energy prices.
-8-
Despite their uncertainties, the demand studies show very
clearlf that the Cook Inlet gas resource is more than adequate
to meet any conceivable Railbelt power needs between now and
the year 2000, even if one chooses to plan for the highest
possible growth scenario.
Assume, for example, that-the "high" estimate of Railbelt power
demand published by Goldsmith and Huskey, which calls for
growth at a compounded rate of almost 6 percent annually is
closest to the mark.[l3] Assume also that an Anchorage/Fairbanks
powerline intertie is completed in 1984, allowing all Fairbanks
power needs save those met by existing coal plants to be
supplied by gas-fired equipment. Assume also that no new hydro
projects, such as Bradley Lake, are constructed. And lastly,
assume that only minor improvements in the efficiency of gas
usage are associated with this almost fourfold increase in
energy production from gas.
The demands on the gas resource under this most extreme of
scenarios come to 1.69 Tcf, or only 42 percent of the proven
Cook Inlet reserves of 3.93 Tcf.
Interestingly, the same assumptions applied to the Goldsmith
and Huskey "low" case (which "projects" a compounded electri-
city demand growth rate of four percent per year) is not that
different a scenario: 1.35 Tcf, or 34 percent of proven Cook
Inlet reserves would be required.
-9-
Goldsmith's work is the current conventional wisdom on Railbelt
power demand; more importantly, it is ·the only rigorous study
of the subject. This, and my desire to be conservative, is
the reason I use it here without modification, even though I
believe he will (once again) revise his "projections" down-
ward.[l4] A four percent compounded growth rate over the next
20 years is substantially above what I judge to be the lowest
reasonable growth scenario.
The details of these calculations are given, with perhaps more
precision than they deserve, in Appendix A. The point that
they make is not dependent on precision: There is much more
gas in the Cook Inlet area than Alaskans themselves can rea-
sonably expect to consume in the next two decades, even allowing
for profligacy in resource use and population growth beyond a
boomer's wildest expectation.
The data already adduced to support this view are so nearly
self-evident that it would be redundant to say more on the
question of physical availability were it not that several
respected experts have apparently reached exactly the opposite
conclusion. Goldsmith and O'Connor are typical.
State royalty gas, from both Cook Inlet and Prudhoe
Bay, is insufficient to meet total projected instate
gas requirements throug~ 2000. In addition, total
present Cook Inlet reserves are not sufficient to
meet total Cook Inlet gas market demand through 2000
as projected. [15]
-10-
Part of the problem with this approach is semantic: Goldsmith
and O'Connor use the phrase "instate requirements" to include
exports of liquefied natural gas (LNG) from facilities not yet
constructed. This is a substantial amount --1.2 Tcf over 20
years. [16]
Apart from the semantic confusion over what constitutes an
"instate demand," the real problem with using_ the Goldsmith.and
O'Connor study (and similar studies) for policy purposes is
that it contains a fundamental inconsistency --the assumption
that exports will grow and that reserves will not. Total Cook
Inlet "demand" is difficult to determine from their figures,
but it appears that they project about 7.0 Tcf over the 20 year
period, or about 180 percent of existing reserves. Obviously
this is an impossibility; without ·at least a doubling of
reserves the Goldsmith/O'Connor demand scenario has no chance
at all of coming true.[l7]
IV.
Although sufficient natural gas is physically available in the
Cook Inlet basin to meet the Railbelt's electricity and gas
utility needs until well beyond the year 2000, the question of
whether the power producers and gas utilities would be able to
purchase it is another matter. The barriers to acquisition of
the gas might be directly economic, in the form of prices too
-11-
high to pay, or in the nature of arrangements under which the
resource has been locked up with contracts that dedicate the
known reserves to competing purchasers.
Long term contracts are common in the natural gas business.
Moving gas to distant markets, whether by pipeline or LNG
tanker requires large fixed investments. The same applies to
almost all uses of gas as a feedstock for chemical manufacture,
such as ammonia synthesis. Investors require certainty of
supply before they will finance facilities that would be
worthless, or nearly worthless without it.
About 60 percent of the natural gas reserves in Cook Inlet are
dedicated to specific.purchasers under contracts of this sort,
of which .68 Tcf is committed to Alaska utilities.[l8] Thus,
if the utilities were to use gas for essentially all Railbelt
power production during the next 20 years, they would require
an additional .67 Tcf to satisfy the "low" demand scenario,
and an additional 1.01 Tcf to satisfy the "high" demand
scenario.
According to preliminary data from Battelle, 1.85 Tcf of the
Cook Inlet area's proven reserves are currently uncommitted
more than enough to meet even the "high" demand scenario.
~12-
Even the fact that gas reserves are currently uncommitted
doesn't necessarily mean that they will be available. Pro-
ducers-will try to get the-best deal possible when they nego-
tiate the sale and dedication of their gas. How good a deal
that is depends on several factors, the most important of which
are the number of potential purchasers that want the gas, and
how badly they want it.
The competitors for Cook Inlet gas are therefore worth sur-
veying in some detail. At the top of the list are those users
which already have invested in facilities that require an
uninterrupted gas stream if they are to continue earning
profits for their owners. These are (apart from the local
utilities) the ammonia/urea manufacturing plant and the LNG
facility (which ships gas to Japan), the two of them located at
Nikiski on the Kenai Peninsula.
The aggregate requirements of the two plants from 1980 to 2000,
assuming current levels of output, comes to about 2.3 Tc£.[19]
Battelle's tabulation of existing contractual commitments
indicates that only about 32% of this "requirement" (.73 Tcf)
has thus far been secured by contracts with producers.[20]
Individually, the ammonia/urea plant has a commitment from its
supplier (Union/Marathon) for about a 9-year supply, and the LNG
plant, which supplies the T6kyo gas and electric utilities, has a
-13-
commitment equal to only a little over 3 years' output.
Between the two of them, the existing facilities will require
about 1. 57 Tcf of additional commi tmen·ts to· keep themselves
operating through the year 2000. If they get that amount
(assuming no new discoveries or extensions of existing fields)
there will only be .28 Tcf of uncommitted reserves left to meet
local power and utility requirements, not even enough to
satisfy the .67 Tcf required for a gas-based electrical economy
through 2000 under the "low" demand scenario.
There are at least two good reasons to expect that these two
plants will be able to obtain the commitments they require to
keep operating between now and at least the mid-1990's. The
first is directly economic. Both plants were built many years
ago (1966 for the fertilizer complex, 1968 for the LNG plant),[21]
and the original capital costs of both have presumably been
long since recovered or written off.
The owners of these facilities have a strong incentive to make
sure their requirements are met; they have essentially no
alternative apart from scrapping the plants. This alone is
sufficient reason to expect them to be very aggressive com-
petitors for future gas commitments.
Another reason for expecting that the LNG and ammonia/urea
plants will obtain the commitments they need to keep operating,
-14-
is that they are owned by Cook Inlet gas producers. It is no
accident that the majority of gas used by each comes from the
field in which the parent company holds a-major interest~[22]
In both cases the facilities were initially developed by pro-
ducers as an outlet for gas which was then an essentially
unsalable by-product of oil exploration. In both cases they
currently take a product for which it is illegal to charge
market prices, and transform it into a product.which is not so
regulated. [ 23]
I have made no quantitative estimate of how high Inlet gas
prices would have to ascend before these vertically-integrated
producers would foresake their own facilities in favor of other
purchasers. At some price they would obviously be willing to
do that .. Between now and the time they run out of their
current dedications of gas, that price is not likely to be
reached.
In my judgment, Alaska's power planners (and the proponents of
Susitna) are justified in assuming that the additional 1.57 Tcf
necessary to keep these plants operating at current levels
through the year ZOOO will, in fact, gorto them, and will be
unavailable for in-state use for power generation.·
Where, then, can policy makers expect the 1.35 to 1.69 Tcf
necessary to support a natural. gas-based electrical economy to
be found?
-15-
As noted earlier, .69 Tcf is already dedicated to Alaska util-
ities, reducing the requirement to between .67 and 1.01 Tcf.
Existing and expected ·contracts-between the LNG and -ammonia/
urea facilities and their producer/owners will generate an
additional .1 Tcf in royalty gas, which presumably will be
available for local gas and electrical utilities, leaving
between .57 Tcf (under the "low" scenario) and .91 Tcf (under
the "high" projection) necessary to assure that natural gas can
be counted on to provide for the major part of the Railbelt's
-
electrical needs between now and the year 2000.
Where this gas comes from depends almost entirely on what
happens to the state's two long-pending, gas~related construe-
tion projects, the facility proposed by the Alaska Northwest
Gas Pipeline Company to carry gas from the North Slope to
South 48 markets (hereinafter, Northwest), and the Pacific
Alaska Associates LNG Plant (PacAlaska).
If the Northwest pipeline is operational by 1990 then the vast
(in comparison with Railbelt power needs) supply of royalty gas
which it will make available at Fairbanks, will supply whatever
power requirements cannot be more economically met from other
sources.
If the-Northwest Pipeline is not constructed, dispositionof
PacAlaska becomes the critical element. If the LNG project
-16-
does.not go forward, producers' commitments-of 1 Tcf (more or
less) to that project will expire,[24] leaving more than suf-
fh:ierit~ gas-t0 meet even the ''high" pr0j-e~ti0n~ of power demand.
If (in the worst case) Northwest does not go forward and Pac-
Alaska does, then a real shortfall would appear. In the ex-
treme case the "deficit" could be as much as 38% of the total
requirements for a gas-based electrical economy in the Railbelt
between 1980 .and 2000.
v.
Since the PacAlaska and Northwest projects clearly are crucial
elements in the Railbelt gas supply, the two of them deserve a
closer look. As originally filed with the Federal Power Com-
mission in 1974, the Pacific Alaska LNG Company (now Pacific
Alaska Associates) proposed to ship Cook Inlet natural gas to
Southern California, to provide gas to its principal sponsor,
Southern California Gas Company. The shipments were to start
at a level of 73 Be£ per year, and later incre~se to twice that
amount.[25] The project, however, encountered early regulatory
and environmental review difficulties. Moreover, the reserves
commitments that the sponsors (later including Pacific Gas and
Electric Company) were able to obtain from Cook Inlet producers
fell far short of the amount necessary to secure financing for
the project.
-17-
At this writing, most of the environmental objections (which
were largely to the regasification facility in California) and
regulatory .difficulties-have been reso1ved,-but the proj-ect
seems further than ever from completion. In early 1981,
Pacific Gas and Electric Company withdrew its commitment to
assist in the project's financing.
Southern California Gas Company continues to support the pro-
ject, though it admits that additional partners will now be
necessary. Major oil companies holding gas reserves in Cook
Inlet have been approached, but no commitments have been forth-
coming. An additional problem is that "Phase I" is no longer
considered by the sponsors to be economically viable by itself.
According to them, if the facility is to go forward it must now
be, on the basis of the full 146 Bcf annual output.[26]
The reasons for the declining fortunes of the PacAlaska project
are significant, since they throw light on important factors
which will very likely continue to influence out-of-state
demand for Alaska gas. These are:
1. The largely unexpected (to the utilities) ability of
consumers to reduce gas consumption in response to
higher prices.
-18
2. The increase, and expected in.crease, in South 48
and Canadian gas supply offerings, at least partially
in. response "to -those same price increases.
3. The failure of Cook Inlet gas reserves to grow as
rapidly as projected.[27]
In my judgment, the probabilities of the PacAlaska project
going forward depend on the discovery of the necessary additional
reserves in Cook Inlet, and a tightening supply situation in
South 48 gas markets. Since the project's successful implemen-
tation could be one of the worst things that could happen' from
the point of view of preserving Alaska's ability to meet
in-state power needs from relatively low cost fuel sources, ·the
result is paradoxical: Discovery of substantial additional gas
resources in Cook Inlet will make it more difficult to meet
southern Railbelt power needs in the interim period between now
and whenever Susitna comes on line.
This difficulty will be of little long-term significance as far
as "availability" is concerned if the Alaska Northwest Gas
Pipeline is constructed as proposed, annually bringing almost
100 Bcf of state royalty gas through Fairbanks.[28] Indeed,
this royalty gas stream would be suffi~ient, by itself, to meet
-19-
almost all of the Railbelt's electricity requirements. For
example, even urider Goldsmith's "high'" case, I calculate that
the royalty stream from the Northwest project would exceed the
requirement for fuel for electrical generation through 1998.[29]
VI.
It is the independent completion of one major project (PacAlaska)
and the non-completion of the other (No.rthwest), that presents
Railbelt power planners with the only potential problem with
natural gas availability. The probabilities of Northwest or
PacAlaska being complete by a certain date are matters about
which even well informed observers are likely to disagree.[30]
In any event, few of those observers are anxious to hazard
their public reputations on an explicit probability estimate
for this kind of event.
Neither am I. Unfortunately, this analysis requires such
estimates, though --thankfully --no great precision is neces-
sary to provide policymakers and power planners with reliable
insights. Using plausible "high" and "low" estimates of the·
projects' prospects for completion indicates that the chance of
a gas "availability" problem developing (due to completion of
PacAlaska and non-completion of Northwest) is somewhere between
three and 18 percent, with the most reasonable range of prob-
ability being between six and nine percent.
-20-
The process by which I arrived at this judgment is shown in
Figures 1 and 2, and isn't the least complicated. To each
project. I assign an "optimistic" and a "pessimistic" prob-
~bility estimate, thereby bracketing a %one of reasonable
expectations about each. In the case of Northwest I consider
it unreasonable to give the project less than a 40 percent
chance or more than a 70 percent chance of being completed by
1990. For PacAlaska the parallel "pessimistic" and-"optimistic"
estimates are 10% and 30%.
Readeri with different views of what is reasonable should
substitute their own estimates,· and work through the calcula-
tion. It isn't difficult. The exercise will show that any-
one's definition of reasonable probabilities for these projects
will lead to conclusions not far different from my own.
Since the only adverse outcome is the conjunction of two dis-
creet events (completion of PacAlaska and non-completion of
I Northwest), the risk factor is determined by multiplying the
two ·individual probabilities by each other. For·example, the
completion probability for PacAlaska of 10% (.10), shown in
figure 1, is multiplied by the Northwest non-completion prob-
ability of 60% (.60) to arrive at the 6% (.06) probability in
that case of an nunfavorable" .railbelt gas supply situation in
the 1990's.
-21-
FIGURE la
ASSUMPTIONS:
1. Optimistic assessment of Northwest's chances
2. Optimistic assessment of PacAlaska's chances
Probability not true: Probability true:
30 /o
>/
Probability .true:.· // "·~ Probabi~ity not
Sc')o //PACAlask~ 1r,~D /o
.-~c.oo:mplete by 19;_.p;
~ ? / . ',""' . /
"...,/'
Probability
0-"'1 ) /O
----~//
liNFAVORABLE Olfl'COMES
Probability
21 /o
7D /o
true:
Probability
7o /b
r---------_/
FAVORABLE OUTCOMES
-22a-
FIGURE lb
ASSUMPTIONS:
1. Pessimistic assessment of Northwest's chances
2. Pessimistic assessment of PacAlaska's chances
Probability not true: Probability true:
t:.o ~~ ¥o7~
_./ '-......_
Probability true: // ··· .. ,""' Probability not
/ D -;~. /PACAlaska "" .·
· complete by 19~>----,
' .? / ''y/
true:
Prohahi 1 i ty Prohab i1 i ty Probability
. ..-:..
b /:·
·---·-~//
UN!:/\ VORA.BLE Olfl'COMES FAVORABLE OUTCOMES
-22b..:
. FIGURE Za·
ASSUMJ>TIONS:
1. Pessimistic assessment of Northwest's c.hances'
2. Optimistic assessment of PacAlaska's chances
Probability not true: Probability true:
~oc;t~ LID ~o
./ .... ,"'
Probability true: // '-,, Probability not true:
3 0 c 7D // PACAlaska -,""'-, /' , , 7D /o
~mplete by 19~>----'--,
' ? / """v/
Probability Probability Probability
18 ~·~ " ....
I :AVORJ\BLl: OUTCOMES
/B . 8~%
-23a-
FIGURE 2b
ASSUMPTIONS:
1. Optim:lstic assessment of Northwest's chances
2. Pessimistic assessment of PacAlaska's chances
Probability not true:
3D%
/
Probability true: /// ·,~ Probability not
ID/o, / PACAlaska -~ /0/6
. ~mplete by 19_;.p;
'"'? / v
Probability
3 /c,
\. .
-· ---·-""'//'-------/
l JN I :I\ VORJ\BLE OUTCOMES
-. / . (. ' ...:...,· /r,
_,/ / ~
Probability
21%
Probability true:
?o%
true:
Probability
~------------~1
FAVORABLE OUTCOMES
.:.z3b-
Of the four cases shown, the first two (Figure·l) are the most
relevant, since their assumptions (optimistic-optimistic, and
pessimistic-pessimistic) reflect the fact that both projects
.will tend to be hurt or enhanced by many of the same factors.
For example, an increase in domestic demand -or a less than
anticipated increase in domestic natural gas supply -would
tend to enhance the prospects of both. The cases shown in
Figure 2, on the other hand, assume that the major determinants
of projects success differ between the two.
Obviously there are some factors that will influence one pro-
ject and not the other, such as the discovery of additional
reserves in Cook Inlet. But these seem far less important than
those which are common to both. In any event, the cases illus-
trated in Figure 2, show that though the confidence interval is
widened (from three ~erc~ntage points in·the first instance to
14.5 percentage points in the second), the midpoint estimate of
an adverse outcome is not much affected by the assumption of
causal independence, shifti'ng from a 7.5 percent probability
to a 10.5 percent probability.
To be conservative, and to avoid any uncalled for appearance of
precision, I conclude that there is about a 10 percent chance
that construction of PacAlaska in conjunction with the non-
construction of the Northwest pipeline will create a problem of
physical availability.
-24-
A 10% chance is a small but not negligible probability. The
consequences of the· adverse availability situation that would
exist in the event PacAlaska is constructed and Northwest isn't
would not be disastrous. Substantial royalty gas would remain
available for power generation and gas utility use. This gas,
with that· already dedicated to Chugach Electric Association
(CEA) and the Anchorage gas utility, would make it possible to
meet the demands of the "low" growth scenario in their entirety
through 1994, or the requirements pf the "highi' scenario through
1991. After that, however, the deficit would be very large,
ranging from 70 percent to 81 percent of annual requirements
for a gas-based electric ec6nomy.[31]
Under the worst circumstances, the gas turbines from which most
of the·region's electricity would be coming, would be converted
to middle distillate fuel oil, and consumers· in the entire
Railbelt would pay somewhat more for their electricity.
This would be a situation not much different from that experi-
enced today by power consumers in Fairbanks, where oil-fired
gas turbines account for 55% of installed generating capacity;[32]
the prices they pay for electricity are two to three times as
high as those paid in Anchorage, but this is still well below
the prices paid by most other consumers in Alaska and in many
parts -of the U.S.[33] .Moreovet, the prices currently paid
-25-
for electricity in Fairbanks may not be that much different
from the prices (in real terms) that all Railbelt consumers
could be paying for Susitna-generated power in the 1990's.
Before moving to the much more interesting -and difficult -
task of analyzing future gas prices, it is necessary to address
the possibility that the use of natural gas by Railbelt utilities
will be prohibited by federal law, through end-use controls of
the sort contained in the Powerplant and Industrial Fuel Use
Act of 1978 (hereinafter, FUA).
VII.
In its 1979 review 6f the alternatives to the Susitna Project,
the Corps of Engineers concluded that:
"The primary reason for not considering natural gas-
fired·generation as the alternative to Susitna hydro-
power development is not gas availability, but
nat1onal energy policy. The Powerplant and Industrial
Fuel Use Bill of the National Energy Act of 1978
clearly indicates that the intent of the Administra-
tion and Congress is to strongly discourage the use of
natural gas for electrical generation."[34]
Even in 1979, a careful reading of FUA should have raised
doubts about the clarity and strength of federal policy in this
area. As noted in the analysis of FUA co11:tained in Appendix C,
most of the language in both the act and the regulations issued
under it are taken up with the exemptions from its general
prohibitions. For example, all .existing powerplants iii Alaska
-26-
are given a special blanket exemption from its provisions.
With r~~pect to ne~ facilities, one observer has cataloged 14
separate grounds for permanent exemptions, including "lack of
capital" and inability to meet·state and local environmental
standards.[35]
-' Appendix C lists the specific g'rounds which are likely to be
most relevant for Alaska utilities when they seek their exemp-
tions. Although environmental constraints may be sufficient by ·
themselves to require ari exemption, I believe it more probable
that Alaska exemptions to use natural gas will be obtained by
either showing that a coal is not available in sufficient
quantities, or that power from a coal plant would sufficiently·
exceed the cost of power from a plant using foreign oil.[36]
The current federal administration's well-known aversion to the
kind of market tinkering that ~nd-use controls represent is
another reason to doubt that they will be imposed in any
meaningful way, at least in Alaska. N~ither does the mood of
' ' the 97th Congress appear particularly receptive, and substan-
tial amendments weakening the Act are likely --if it is not
repealed outright.
Finally, the most compelling rea.son to believe that exemptions
will be available for new Alaska power plants is that the
utilities will largely be able to say, truthfully, that absent
.:.27-
the. ability. to add new natural gas-fired turbines they will be
unable to carry their peakloads (the "lights out" argument).
Even the smallest coal-fired plant that could be built in the
sout.hern Railbelt area would require six years or more to bring
on line.[37] Without new natural gas-fired turbines, any
significant load growth in the interim simply won't be served.
Although exemptions from FUA will almost certainly allow
natural gas to be used for power generation, there is an im-
portant provision of the act which may tend to concentrate the
exemptions in the hands of the larger utilities, particularly
Chugach Electric Association (CEA), which is Alaska's largest
utility.[38] Except for "peakload powerplants" where failure
to use natural gas would create environmental problems, FUA
requires the utility to demonstrate
that there is no alternative supply of electric
power which is available within a reasonable
distance at a reasonable cost without impairing
short run or long run reliability of service and
which can be obtained by the petitioner, despite
reasonable good faith efforts. [39]
Under this section, and the associated regulations, it doesn't
matter·that power to be purchased is also.generated by natural
gas.
The .exact impact of this provision on Alaska is not yet clear,
but it is possible that a large utility with some excess
capacity could prevent ot~er interconnected utilities from
-28-
adding any new gas-fired-generators, even while the'larger
utility is expanding its own gas-fired plant.· Municipally
owned electric utilities have protested the regulations· imple-
menting this part of FUA, arguing that they would force the
mun:lcipal· companies to give up generation and become simply
distributors for the large, predominantly privately-owned
utilities.
The Railbelt electric utilities contemplating the expanded use
of natural gas have no doubt already made ~lans for how to deal
with this aspect of FUA. Since it could have substantial
implications for the institutional pattern of po~er develop-
ment, it deserves more intensive study by anyone with respon-
sibility for the coordination· of Railbelt power development.
VIII.
In recent years the prices of natural gas and electricity in
the Southern Railbelt have been among the lowest in the world's
developed countries. Gas rates in Anchorage are below those ·in
every major city in the U.S. Anchorage electricity costs are
the third lowest,[40] and in all probability will s6on be the
lowest. Barring unforeseen developments in technology or
government regulation, these remarkably low relative prices can
be expected to cnntinue over the coming two decades .
.,.zg-
The Cook Inlet area's low energy prices have resulted from the
fortuitous conjunction of abundant natural gas and a remoteness
from major energy markets. .. If natural gas or any other fuel is
to have value, it must be transported to where the consumers
·are. The differential between its price near where it is
available and where it can be sold is a·function of that trans-
portation cost.
If costs.of transporting a fuel are high, as is the case with
natural gas; the differential will be high. If the energy fuel
is both dense and fluid, as oil is, the costs of moving it to
where it can be used are relatively low, and the differential
between prices in producing and consuming areas is similarly
low~ This explains why natural gas has historically tended to
displace oil in those areas near oil and gas production (the
Southwest U.S., Alberta), and why oil has tended t.o retain the
markets distant from those areas (Northeastern U.S., Eastern
Canada).
The principal has been working in Alaska over the past twenty
years. In Cook Inlet we ship the oil to California and use
the gas here.
Forces entirely apart from economics can distort or even re-
verse these facts, but only at great economic cost. The fe-
deral government may say that Alaska gas cannot be used in
-30-
Ala~ka, and thereby make additional gas available in states
that have more. congressional clout, but the economic welfare of
the nation as a whole will be reduced. No amount of posturing
will. make it otherwise.
The best illustration of how this principal will work in the
future is found in the Northwest Gas Pipeline. If-gas prices
are deregulated, Alaska North Slope (ANS) natural gas will not
be salable in the South 48 unles~ it is priced, on a btu basis,
-
at levels competitive with alternate fuels, possibly coal, but
more likely heavy (residual) oil. At current U.S. prices for
. . .
heavy oil ($33-42 per barrel, depending on location and sulfur
content "[41]) this implies a maximum delivered price for ANS
·gas in the $5.25-6.75 per Mcf range. If natur~l gas is not
deregulated, there may be a sufficient volume of low cost gas
flowing under old contracts ·to allow a rolled-in price forANS
gas of up to $9 per Mcf in i986 when it first reaches the South
48 markets. This is the expectation of the project's
chairman.[42] Although the price in 1986 could be much lower
than this, perhap~ as low as $3.00 per Mcf, hardly anyone
expects that it would be salable at a higher price.[43]
If ANS gas reaches South 48 markets in 1986 at a price of $9
per Mcf, its price in Fairbanks will be . its well-
head price plus the proportionate cost of transporting it 14
percent of the d{stance to those markets.[44] Under the
-31-
Nc;~:tural Gas Policy Act of 1978, the well-head price cannot be
more than $-1.45 per Mcf, wit·h escalation for. inflation after
1977. North Slope gas, unl.ike most categories, would remain
subject to this limit even after the phase-out of other gas
price controls in 1985.
An average inflation rate over the 1977-1986, period of 10
percent wtiuld establish a ceiling price of $3.42 per Mcf,
leaving .5. 58 per Mcf to be collected by the pipeline in tariffs
($9.00~$3.42 = $5.58).
Most observers believe that there is no way the producers (and
the state) will be able to collect the permitted ceiling
price[451, .but even if this was possible, the $4.20 per Mcf,
price in Fairbanks of North Slope Gas would still be a tremen~
dous bargain. For example, the equivalent price in today's
(1981) dollars is $2.61 per Mcf, or $2.47 per million btu[46].
Golden Valley Electric Association is currently paying $6.42
per million btu for fuel oil for their combustion turbines,
over 2.5 times as much.[47]
If, as some suggest, the well-head price of ANS gas will ap-
proach zero, and the transportation costs of ANS gas to South
48 markets can pe "levelized" at about $4.00 per Mcf in 1986
dollars[48], the 1986 gas price in Fairbanks could be an
amazing $.56 per Mcf, (14 percent of $4.00), or $.35 per Mcf in
1981 dollars.
-32-
Using current generation equipment at Fairbanks, gas priced at
$2.61 per Me£ (1981 dollars) could produce power at about 3.3¢
per KWh. At $0.35 per Me£ the electricity generating costs
would be 0.9¢ per KWh.[49] By way of comparison, most calcu-
lations of power costs from the Susitna Project place it in the
5¢ to 7¢ per KWh range at the busbar, assuming that the capital
costs of th~ project would need to be paid back through power
revenues.
The same principles which, if the Northwest Pipeline is built,
will make ANS gas relatively inexpensive in nearby Alaska
markets also govern the sale of Cook Inlet gas. Cook Inlet gas
must meet or equal the price~ of competing fuels in its major
markets~ To achieve this, its price in Alaska can be no higher
than the difference between those prices and the costs of
moving Cook Inlet gas to those markets.
The logical markets are, of course, Japan and California. The
prices t~at must be met in thdse markets are closely if not
directly related to the·prices of 6il.
The cost of moving Cook Inlet gas to Japan or California will
be higher than the costs of moving ANS gas to its markets,
since the distances are comparable, the volumes lower, and the
technology (liquification verses pipeline) more expensive.
Unless these conditions change in some fundamental way, the
-33-
differential between· world oil prices and gas prices (on a btu
basis) in ·Cook Inlet will be greater than the differential
between·. the ANS gas well-head price and its price in South 48
markets.
Other forces will.no doubt effect how this principle will work
in practice. Transportation cost to Japan will be less since
less expensive foreigri ships may be used, but approvals for
future foreign exports of gas may be difficult to obtain.
Exports of LNG to the U.S. West Coast may be economically
viable, but impossible due to the lack of a receiving terminal,
its construction being blocked by environmental objections.
The owners of the existing ammonia/urea plant and the existing
LNG facility may be able to pay more for Cook Inlet Gas,
because their fixed costs are close to zero.
A more serious distortion of the underlying economics could
come if the Cook Inlet producers perceive that the only way to
market large quantities of Cook Inlet gas is to commit it all
to a single major project. PacAlaska is this sort of project,
which is why I devoted so much attention to it earlier in this
study.
The odds of PacAlaska being constructed within the next few
years have become increasingly slim. Nevertheless, the project
-34-
could continue to cast a shadow on Railbelt gas availability
for many years, even if the producers decline, as they have
thus far, to provide the necessary financial backing. The gas
purchase contracts between PacAlaska and the producers, covering
between .8 and one Tcf, have become subject to unilateral
cancellation by the producers (and thus are not properly
counted a~ dedications). Yet they have not been canceled.[SO]
The most plausible explanation is that the producers simply
have not had any other offers.
The lack of other offers is not surprising. Natural gas prices
in the United States are in a state of flux as the nation
moves, haltingly, toward a less regulation-oriented energy
market. Alaska utilities are not in any immediate supply
problems, and further long-term commitments to purchase gas
would probably be imprudent if they involved any significant
requirements to purchase specified quantities. The economic
environment is too uncertain; if Susitna is built the utility
that agreed to take-or-pay for a large quantity of gas in 1995,
even at favorable prices, could find itself in a very difficult
position.
Moreover, the state is increasingly perceived as a credible
guarantor against adverse supply contingencies. A project
exporting large quantities of Cook Inlet gas could make it
difficult for the Anchorage gas utility to obtain additional
-35-
reserves, but it would also generate, as I noted earlier,
substantial royalty gas flows, the disposition of which will be
determined as much (if not more) by politics as by economics.
Readers will note ~hat my discussion of Cook Inlet gas prices
has been cast in general rather than specific terms. This is
appropriate, since the difference between Pacific Basin oil
prices and Cook Inlet gas prices is the only overall principle
that should govern policy thinking· in this area. To be specific
is to be misleading, as Alaska policy-makers have indeed been
misled by the calculation of how much Cook Inlet gas and
electricity prices will increase if PacAlaska is constructed. [51]
All these calculations have assumed, explicitly or implicitly,
that a particular future pricing structure has validity because
it can be found written down in a contract or a statute.
The calculation of how a particular contractual arrangement
will work is useful and important, but is no substitute for
analysis of the underlying economic and political forces, even
if the results of that analysis must be presented in general
terms.
Battelle has made preliminary estimates of future Cook Inlet
gas prices, assuming that any new contracts for additional gas
by Alaska utilities will have to meet the prices that producers
supplying the existing LNG facility will receive. This
-36-
calculation is misleading since it ignores (1) the fact that no
new arrangement for sale of LNG could be made on terms anywhere
as favorable to the producer, and (2) the political barriers to
any increase in LNG shipments to Japan.[52]
The calculation leads us further astray by assuming a com-
pounded increase in real, constant dollar oil prices (to which
the LNG price is contractually tied) of four percent annually
over a 20-year period. An increase in real terms of this
magnitude is plausible, but so is an increase of only one
percent. The difference is significant --$4.59 per Mcf with
the Battelle assumption versus $2.52 with the one percent
assumption--and policy makers should be aware of it.[53]
Finally, legislators need to know the significance of the
numbers. An estimate for the year 2000 of a price of $4.59 per
Mcf (in 1981 dollars) looks pretty high, but it is in no way
inconsistent with the principle described earlier in this
section: If world energy prices incre~se at a rate of four
percent compounded, then a gas price of $4.59 per Me£ would be
about one-third of what just about everyone else in the developed
nations would be paying for energy. It would be, as I said at
the beginning of this section, a "remarkably low relative
[energy price]."
-37-
·Further,· gas at $4.59 per Mcf could produce electricity
(assuming 11,000 btu per KWh) at about 5.5¢ per KWh and deliver
it to the residential·consumer at about-8¢per KWh, a price not
that much different from what fully costed Susitna Power would
sell for.
JX.
The construction of the PacAlaska project, or some other scheme
designed to use large quantities of Cook In~et gas, is the
only major threat to continued availability of reasonably priced
gas in the Cook Inlet area. So far, th~ stite has actually
supported the P~cAlaska proposal, looking ahead perhaps to the
economic activity and resource revenues it will create.
I have made no analysis of these prospective benefits, but on
the surface they appear very small in relation to the problems
the project could create. The construction of the project,
particularly the necessary network of gas-gatheri~g pipelines,
would create a short ·and --by recent Alaska standards --small
construction boom.· After that, the employment.impact would be
minimal. R~source revenues would also be minor, probably not
·more than a few tens of millions dollars per year, due to the
l:ow well-head value and the fact that much of the gas would
come from federal leases.
38.,-
If it wishes to discourage the project, there are a number of
steps the state could take. Firstly, its earlier statements
to the Federal Power Commission (now PERC) supporting the
project could be withdrawn, pointing out that the failure to
develop additional reserves, delay in the Susitna and Northwest
projects, and increasing local gas demand have materially altered
the situation. The state could also reiterate its intention to
take in kind any state royalty gas which is generated by sales
to PacAlaska.
A bolder and potentially much more effective way to discourage
the project and possibly achieve other objectives would be a
state.purchase of substantial Cook Inlet reserves. The acqui-
sition of, say, .5 Tcf or more by direct sale or through a trade
for North Slope gas, would assure that Railbelt consumers would
be protected.
The terms of such an arrangement would need to be examined
carefully; it could be that the conditions necessary for a
nutually attractive deal between the current owners and the state
are not present. The Alaska Power Authority, or some other state
entity, should be directed to determine the mutual interests
and the alternative methods of acquiring additional Cook Inlet
gas, and the potential benefits of doing so.
-39-
The issues raised by the state's possible role in the Northwest
project go far beyond the effects that project will have on the
Railbelt power situation. This impact seems, however, to have
received little analysis. As I have shown here, that impact is
likely to be dramatic, and should be considered carefully as
the state evaluates its posture toward the Northwest project.
A third area that this study has identified as requiring partic-
ular state attention relates to the marketability of Susitna
power in the face of potentially very low cost gas. If Susitna
power is to be essentially given away, its marketability will
not be a probiem,[54] but if there is to be a charge for
Susitna power, planners need to be aware that it may be diffi-
cult or impossible to sell to utilities that have lower cost
alternatives. If the Susitna project is financed by a more or
less conventional use of capital markets~ this won't be a
problem: the bond purchasers will insist that the region's
utilities commit to take the power. With full state funding of
the project now a possibility, if not a likelihood, the question
needs to be carefully examined.
Finally, my work on this study has emphasized the truth of what
other investigators have pointed out many times before: The
uncoordinated and decentralized system of power planning and
development that has served the Railbelt remarkably well over
the years is probably not suited to the needs of the next 20
years.
-40-
If Susitna is built, the region's generation capacity, and the
decisions relating to it, will be centralized as a matter of
course, though the institutional arrangements for bringing that
about are still unclear. The utilities, essential partners in
any such arrangement, are in no hurry to surrender their indepen-
dence and freedom of action.
If Susitna is not constructed, or if its construction is
delayed, the role of the state in power planning and development
is also bound to increase, as an increasing share of generation
fuel is obtained from royalty sources.
It is too early to say what sorts of institutional rearrangements
are possible or appropriate. But it is clear that the utilities
will find themselves increasingly involved with the state
government, and vice versa. Both parties should plan for the
new relationships that will engender.
-41-
NOTES
1. "Rail belt" as used here include-s the Fairbanks North Star
Borough, the Matanuska-Susitna Borough, the Municipality
o£ Anchorage, and the Kenai Peninsula Borough. The terms
"southern Railbelt" or "Cook Inlet Area" refer to the
latter three jurisdictions, and the electricity distribu-
tion and transmission grid centered on Anchorage. The
southern Railbelt and Fairbanks area electricity grids are
not now interconnected.
2. Corps of Engineers, Southcentral Railbelt Area, Alaska,
Supplemental Feasibility Report (February, 1979),
Appendix -Part II, p. 71.
3. Consumption was approximately 47.3 billion cubic feet
(Bcf) in 1979, on a reserves base of 3.933 trillion cubic
feet (Tcf). Both figures are from Battelle Pacific
Northwest Laboratories, Cook Inlet Natural Gas, Future
Availability and Price Forecasts, Comment Draft Workin
Paper No. 1.1, pp. 3.4, 3.11 Fe ruary, 1981 T e
Battelle data differ slightly from those published else-
where. Other sources are Goldsmith, Scott, and O'Connor,
Kristina, Alaska Historical and Projected Oil and Gas
Consumption (January, 1981), and Alaska Power Administration,
Reg1onal Summary, unpublished data sheets, (March, 1980).
For other sources for reserves figures, see notes 9 and
11, infra. ·
4. The efficiency of natural gas used for electrical genera-
tion is assumed at 15.5 cubic feet (cf) per kilowatt/hour
(KWh) {see Appendix B). The total 1979 Railbelt elec-
tricity production for utilities and national defense was
2.7895 x 109 KWh (from Alaska Power Administration,
op. cit.).
5. The project would annually produce 6.9 x 109 KWh. The
natural gas required to produce this amount of electrical
energy is 106.95 Bcf, assuming the efficiencies of existing
equipment (see note 4, supra).
6. The calculation assumes that the state's royalty share
would be 91.25 Bcf annually. Current (1979) electrical
energy needs would require 43.2 Bcf per year (using
assumptions in Note 4, supra and Appendix A). A Fairbanks'
gas utility would presumably require less than the 14 Bcf
taken for gas utility uses in Anchorage in 1979.
-42-
7. Aiaska Oil and Gas Conservation Commission, 1979 Statistical
Report, as quoted in Goldsmith and O'Connor; ~ Cit.
8. Battelle, Op. Cit., p. 3.4.
9. For other estimates, see Sweeney, et al, Natural Gas Demand
and Supply to the Year 2000 in theCoOl< Inlet Basin of
South-Central Alaska, (Stanford Research Institute, November,
1977) Table 18, p. 38. Sweeney reports six different
estimates of "potential additional resources of natural-
gas in Cook Inlet." They range from 6.7 Tcf to 29.2 Tcf.
10. Personal communication, William L. Cole, (Vice President,
Southern California Gas Company) 6 February 1981.
11. Van Dyke, William D., Proven and Probable Oil and Gas
Reserves, North Slope, Alaska, (Alaska Department of
Natural Resources, September, 1980), p. 10.
12. Crow, Robert, et al, An Evaluation of the ISER Electricity
Demand Forecast(Energy Probe, June 1980); Goldsmith, Scott,
and Huskey, Lee, Electric Power Consumption for the
Railbelt (Institute of Social, Economic and Government
Research, June, 1980); Love, James, et al, Energy Alt·erri.a-
tives-for the Railbelt (Alaska Center-for Policy Studies,
August, 1980); Tuck, Brad, A Review of Electric Power
Demand Foreca·sts and Sug estions for Improving Future
Forecasts Univers1ty o Alas a, Anc orage, May 1980 ;
Goldsmith and ~'Connor,~ Cit.; ~a!t~lle Pacific North-
west Laborator1es for the-Alaska D1v1s1on of Energy and
Power Development and the Alaska Power Authority, Alaskan
Electric Power: An Anal sis of Future Requirements and
Supply Al ternat·1ves or t. ·e Ra11 elt Reg1on 1978 .
13. Goldsmith and Huskey, ~Cit.
14. Compare the projections contained in Goldsmith's 1977
study, "Alaska Electric Power Requirements," Review of
Business and Economic Conditions, (University of Alaska,
June, 1977), with those in Goldsmith and Huskey, Op. Cit.
15. Goldsmith and O'Connor,~ Cit., P. 41 (Emphasis supplied).
16. Ibid., p. 34. Their exact figure for LNG exports is
4.96 Tcf. They use the Oil and Gas Conservation Commis-
sion's estimate of proved reserves, 3.766 Tcf (p. 39).
17. The stated purpose of the Goldsmith and O'Connor report
is satisfaction of the requirements of AS 31.05.183(d):
(d) Oil or gas taken in kind by the state as its
royalty share may not be sold or otherwise disposed
of for export from the state until the commissi.oner
-43-
determines that the royalty-in-kind oil or gas is
surplus to the present and projected intra-state
domestic and industrial needs. The commissioner
. shall make public, in writing, the specific findings
and reasons on which his· d-etermination is based an-d
shall, within 10 days of the convening of a regular
session of the legislature, submit a report showing
the immediate and long-range domestic and industrial
needs of the state for oil and gas and an analysis
of·how these needs are to be met. [Emphasis supplied]
Their report, however, contains no "analysis of how these
needs are to. be met." Indeed, on the face of it one would
conclude, absent massive new discoveries or the shipment
Prudhoe gas to Cook Inlet, that they simply cannot "be
met." If there are additional new discoveries, allowing
· the·LNG exports to come to fruition then the available
royalty gas will (assuming discoveries are at least
partially on state land) increase as well. The report
ignores this fact. Indeed, if the necessary reserves are
discove~ed on state land the royalty gas available would
approach one Tcf.
18. The contracts are summarized in Battelle,~ Cit., p. 3.4.
Unless otherwise indicated, the information on contractual
dedications is from this material.
19. This figure is calculated from Goldsmith and O'Connor,
~Cit., p. 6., based on their data for the 1979 consump-
tion-or-these plants. Using the Battelle preliminary
data for 1979 would have given a slightly lower amount,
2.2 Tcf. Goldsmith's estimated 1980 consumption figures
for the LNG facility (based on the "first nine months of
the year") indicate a substantial reduction (from 64 Be£
to 50 Be£. To be conservative, I have ignored this re-
duction.
20. Battelle's preliminary estimates detail the existing
contractual commitments as follows in (Tcf):
Anchorage Gas Utility
Chucagh Electric Association
Collier Carbon & Chemical
Pacific Alaska LNG
Phillips/Marathon LNG (to Japan)
Reinjection for Enhanced Oil Recovery
.368
.310
.499
.829+
.231
.106
21. Erickson, Gregg, "The Natural Gas Industry in Alaska,"
Alaska Review of Business and Economic Conditions,
(~eb, 1967).
-44-
22. Phillips Petroleum Company and Marathon Oil Company are the
owners of the LNG facility, the principal supplier of
which is the north Cook Inlet field, the principal owner
of which is Phillips, with a smal].er interest held __ by
Marathon :---Additional gas (31 percent of 1979 consump-
tion) comes from the Kenai field, major owners of which
are Marathon and the Union Oil Company.
The ammonia/urea facility is owned by Collier Carbon and
Chemical Company, a wholly-owned subsidiary of Union. Its
major supplier is Union/Marathon's Kenai Field, with
additional gas (13 percent) coming from the McArthur River
Field,-owned largely by Union.
23. The sale price of LNG in Japan is not subject to U.S.
regulation, although its export from the U.S. requires
f€\deral approval. The current authorization expires in
1984, but could be extended. If a terminal is available
to receive it, the LNG could also be shipped to the U.S.
West Coast. · ·
24. PacAlaska officials state that they currently have "just a
shade over 1 Tcf under contract" in Cook Inlet (William
Cole, personnal communication, February 6, 1981). Battelle
(Op. Cit., p. 3.4) has identified contracts which call for
delivery of .829+ Tcf. What was described as a typical
example of these contracts was supplied to me by Southern
California Gas Company. It contains provisions which, in
effect, allow cancellation if PacAlaska has not obtained
its FPC Certificate and arranged financing commitments for
its project by July 1, 1979. This date has been amended
three times, most recently in the fall of 1978, when the
optiori-to-cancel date was changed to June 1, 1980. This
date is, of course, long past; according to James Schroeder,
managei of supply acquisition for Southern California Gas
Company (personal communication, March 12, 1981), the
options to cancel have not yet been exercised. ·
25. Pacific Alaska LNG Co~pany, A lication
of Pub 1 i c Con v en i en c e and N e-=-c,...e""=s-=s,....1-,.:;:t:-y---.,r:t.-o=--:L'r-._--.----:;--...---
C6mmission], November, 1974.
26. "Alaska-California LNG Project Suffers Two Major Setbacks,"
Western Energy Update (16 January 1981), p. 19; William L.
Cole, personal communication, 6 February 1981.
27. The judgments presented here for the declining fortunes
of the PacAlaska project are my own. See, however, Pacific
Gas and Electric Company, Long-Term Resource Planning,
1981-2000 (December, .1981), and the Western: Energy Update
Article (supra).
-45-
28. This assumes pipeline through-put of 2 B~f per day, which
is what Alaska Oil and Gas Conservation Commission orders
currently permit. I do not assume that the 2.4 Bcf per
day through-put which has been approved by the Federal
Energy Regulatory Commission will be allowed.
29. I calculate that the 1998 requirement, under the assump-
tions given in Appendix A, not counting Anchorage's gas
utility requirement, is 89.2 Bcf. The royalty stream
would be 91.3 Bcf.
30. See, for example, Tussing, Arion, and Barlow, Connie,
·Marketing and Financing Supplemental Gas: The Outlook
For, and Federal Polic Re arding, S nthetic Gas, LNG,
an Alaska Gas Un1versity o A as a, 1978 , an , y the
same authors, The Alaska Highwa Gas Pi eline: A Look at
the Current Impasse Leg1slat1ve Agency, January,
1979).
31. These figures are based on the following assumptions with
respect to royalty gas:
(1) Production from the North Cook Inlet field for the
existing LNG plant and/or the ammonia/urea facility
will yield 5 Bcf/year of royalty gas throughout the
entire period;
(2) An additional 2 Bcf/year of royalty gas will be
available from other fields serving these two plants,
commencing in mid-1988; and,
(3) PacAlaska's gas stream will yield 15.8 Bcf/year of
royalty gas, based on an annual input gas requirement
of 160 Bcf and an average royalty rate of 9%~
32. Alaska Power Administration, QE...:_ Cit. (note 3, supra).
33. The least expensive residential block rate for use (over
1500 KWh/mo.) in the Golden Valley Electric Association's
Fairbanks service area is 7.46¢/KWh. The comparable rate
in Chugach Electric Association's Anchorage Service Area is
2.00¢/KWh. The November 1980 average unit cost of elec-
tricity to U.S. residential consumers was 5.61¢/KWh,
according to the Monthly Energy Review (Energy Information
Administration February, 1981).
34. Corps of Engineers, Op. Cit. Part 1, pg. 26.
35. Cavanaugh, H.A., "How to Get a Fuel Use Act 'Cost-Test'
Exemption," Electrical World (May 15, 1980), pp. 33-36.
-46-
36. There is an "Alice.-in-Wonderland" quality in FUA and its
regulations as they apply to Alaska that is remarkable,
even in these days. One .can only ponder the possible re-
levance to public policy of the costs that Chugach Electric
Associatiori would incur if it decided to generate its
power using Saudi or Indonesian ~rude oil.
37. For a discussion of the coal alternative, see Erickson,
Gregg, and Boness, Fred~rick, Alaska Coal and Alaska Power,
Alternatives For Susitna (Legislative Affairs Agency, May,
1980).
38. CEA is also the largest Rural Electrification Administration
(REA) cooperative in the United States.
39. PL 95-620, "Powerplant and Industrial Fuel Use Act of 1978",
Sec. 213(c)(l).
40. Battelle, Op. Cit., note 3, supra, p.2.3
41. Oil and Gas Journal (March 9, 1981), p. 283.
42. Foster Associates, Inc., Foster Report No. 1291 (1980), p.9.
43. See Tussing, Arlon, "Only State Financial Aid Can Save The
Natural Gas Pipeline," Anchorage Daily News, (March 28,
1981), p.E-2.
44. I assume that.the average distance from wellhead to U.S.
city gate would be 3,239 miles, and that .the gas going to
Fairbanks would travel just under 14 percent of this dis-
tance (450 miles), paying therefore, just under 14% of the
tariff, in accordance with the meth6d established by the
Federal·Energy Regulatory Commission (FERC). Federal
'Energy Regulatory Commission, Determination of Incentive
Rate of Return, Tariff, and Related·Issues, Docket RM-78-12,
(June 8, 1979)·p. 194. The "dekatherm per mile" method
chosen by FERC is the same result as an."Mcf per mile"
tariff, as long as the quality (btu content) of the gas
removed at all offtake points is the same.
45. See Tussing, Op. Cit., note (4.2), su~ra; Chomski, Joseph M.,
Testimony to the JOlnt Natural. Gas P1 eline Committee
(Alas a Legislature, Marc 11, 1981 , p. ; "Alas a Ga$
Pipeline: Will it End in Limbo?" Business Week
(March 30, 1981) p.48.
46. This assumes a 10 percent inflation rate ov~r the 1981-1986
period. ANS gas is assumed to contain 1056 btu per tf,
FERC, Op. Cit.
-47-
47. Mr. Hob Huffman, Ge.neral Manager, Golden Valley Electric
Association (personal communication, 30 March 1981).
48. Tussing, Arion, "Project Costs and First Year Gas Prices
[for the Northwest Pipeline]" March 22, 1981 (personal
communication), and supra, note 43; Chomski, QE..:_ Cit.
49. This assumes a base loaded heat rate of 11,000 btu per KWh
(Huffman, supra, note 47) ·, using the existing regenerative
cycle turbines. Some modifications to the. facilities
would be necessary. The figure given here includes ~n
arbitrary 0.5¢ per KWh for non-fuel generating costs.
SO. See note 24, supra.
51. Kreinheder, Jack, Memorandum "Pacific LNG Project, Re-
search Request No. 30 1' (House Research Agency, February
29, 1980); Battelle,-~ Cit., supra, note 12, p. 6.37.
52. Swift, Ward, personal communication, (March 16, 1981). As
rtoted, the estimates are specifically identified as ten-
tative. Though I am critical of the Battelle work for the
policy implications it gives, the work itself is extremely
valuable, and I have relied on it extensively.
53. The four percent figure is my calculation, from the 1980
wellhead price. (Battelle, ~Cit., note 3, sutyd.) and
the year 2000 estimated well~ price (Swift, I 1 .).
Annual rate = [LN($4.59/$2.06)]/20. --
54. Giving Susitna power away would have many perverse effects,
and in the long run would adversely affect the interest
of both the power consumer and the state as a whole. In
any event, giving it away is not necessary to assure its
marketability, or to transfer major benefits to Railbelt
power consumers.
-48-
Appendix A
HCM MUGI GAS WOULD IT TAKE
TO MEEI' RAILBELT ENERGY NEEDS FROM NOO UNI'IL 2000?*
"I.a.v" Demand Scenario ''High'' Demand Scenario
YEAR
1980
1981
1982
1983
1984
1985
1986
1987
1988
1989
1990
1991
1992
1993
.19%
1995
1996
1997
1998
1999
2000
annual
projected electricity
requirerrents
(KWh X 106)
1907
1975
2044
2f12
2765
2868
2927.
2989
3052
3114
3176
3323
3470
3616
3763
3910
4132
4354
. 4577
4799
5021
TarAL GAS ~uiRED·
*For metlx>dology, see next page.
annual
narural gas _
· requirements
(Bcf)
45.7
46.9
48.1
49.2
. 55.3
56.9
57.8 .
58.8
59.8
60.7
61.6
63.9
66.1
68.2
70.3
72.4
75.6
78.7
81.8
84.8
87.8
1.35 Tcf
annual
projected electricity
requirerren.ts
(KWh x 1 o6)
1907
2061
2215
2368
3227
3445
3589
3732
3876
4019
4163
4463 .
4764
5064
5365
5665
5943
6221
6500
6778
7056
annual
natural gas
.requirerren.ts
(Bcf)
45.7 .
48~3
50.9
53.4
62.8
66·3
68.5
70.7
72.8
74.9
77.0
81.5
85~9
90~2
94~4
98.6
102
106
110.
113
1-1-7-.
1.69 cf
The values .in this Table were derived for the 1980-83 period as foll.CMs:
TG%= [D~ (a) + GAM-GRH] [E-(n-1980) (.125)] -+UGD (1.02) (n-1979)
and for the 1984-2000 period by
TG% = [Il.t\Fn(a) + GRM-<MG-GFC-GRH] [E-(n-1980) (.125))+ UGD (1.02) (n-1979)
where
TGDn = Total Anrual Natural Gas Required in Year n.
= The projections ("High" or "l.cM") for Anchorage electric utility sales
fran Goldsmith and Huskey, Electric Paver Consumption For the Railbelt
(June 1980), p. 53. Unear interpolation was used to provide data points
for years between those for which projections were published.
DAFn = The projections (''High" or "!..aN") for Anch::>rage plus Fairbanks electric
utility sales, fran Goldsmith and Huskey, Ibid.
GAM = Armual military generation in the Anchorage area, assumed constant at 1979
level (134 X 106 KWh) •
GRM = Anrllal military generation in the Railbelt, assurred constant at 1979 level
(334 x 1 o6 KWh).
GFC = ~al coal fired generation by Fairbanks area utilities, asstii"red constant
at 1979 level (311 x 106 KWh).
GMC = Anrual military coal fired generation, assurred constant at 1979 level
(178 x 106 KWH).
GRH = Anrual Railbei t hydro generation' asstii"red constant at 1979 level (200 X 1 o6
KWh) •
. a = Adjustment factor for transmission and distribution losses (asSUired to be
. 1.0925).
E = Gas firerl generation efficiency factor of 15.5 cf/K.Wh. (The calculation
reduces this at a rate of • 125 cf/¥Jiln/year.)
UGD = Anrual gas utility demand in 1979, asstii"red to have been 14.04 x 109 cf.
(The calculation escalates this by 2 percent each year)
n =Year
APPENDIX B
Table B-1
UITLITIES' SOill'HCENTRAL NET ENERGY FIDM GAS
AND CALCULATED EFFICIENCY
From Gas Total Percent Gas Use
YEAR (KWh X 106) (KWh x 1 o6). From Gas (Bcf) .
1979 1837.5 2150.4 85.5 28.924
1.978 1696.6 2052.3 82.6 24.431
1977 1544.6 1920.7 80.7 23.534
1976 1473.8 1723.0 86.5 22.204
1975 1246.3 1499.6 83.1 19.619
1974 1049.1 1267.8 82.7 17.117
1973 973.1 1169.9 83.2 15.683
1972 748.2 1033.7 72.4 12.780
1971 612.6 956.1 64.1 9.980
1970 503.4** 804.4 62.6 *
1965 128.9** 451.3 28.6 *
1960 -o-251.5 -o--0-
* Not available.
**By calculation, using 16.29 cf/KWh.
·Sources --
1960-1970:
1971-1976:
1977-1978:
1979:
SNeeney, ~ Cit., Note 9. .
Alaska Power Administration, Alaska Prner Statistics (July, 1977)
Energy Infonnation Administration, Annual Report of Power Production,
Consup!ption and Capacity, (July, 1980). · ·
Alaska Power Administration, .9E!_ Cit., Note 3.
Efficiency Factor
(CF/KWh)
15.40
14.40
15.24
15.07
15.74
. 16.31
16.12
17.08
16.29
*
*
-o-
Plant
M L & P (1)
M L & P (2)
CEA (Knik)
CEA (Beluga)
CFA (Bernice)
CEA (Inter.)
Table B-2
PLANT EFFICIENCIES FOR ELECITRCITY
FROM NATURAL GAS
I
(January to November, 1979)
Energy Generated Fuel Use
(KWh X 103) (Me f)
243,803 4,451 ,522
171 ,768 2,504,042
23,618 698,007
1 ,092,253 15,063,858
76,013 1 ,769,195
17' 134 705,622
1 ,635,589 25,192,246
Source: Utilities' Monthly ReEort, (FERC Fonn 4)
Efficiency
(.cf/KWh)
17.47
14.58
29.55
13.79
23.27
41.18
15.40
APPENDIX C LAW OFFICES
To:
From:
Date:
Re:
. PRESTON, THORGRIMSON, ELLIS & HOLMAN
420 L STREET -SUITE 404
ANCHORAGE. ALASKA 99501
(907) 276-1969
MEMORANDUM
Gregg Erickson
Fred Boness ~
December 31, 1979
Powerp1ant and Industrial Fuel Use Act of 1978
Introduction
This memorandum contains a general analysis and
summary of the Powerplant and Industrial Fuel Use Act of
1978 ("Act"). The discussion contained.herein is based on a
review of the Act, conference report, final and proposed
regulations issued under.the Act (and accompanying analysis),
and an Environmental Impact Statement prepared after passage
of the Act (April 1979). Additional sources of information
which could have been, but were not consulted, are the
congressional hearings held prior to passage of the Act and
statements made on the floors of the House and Senate and
reported in the Congressional Record. I have not reviewed
these sources because I believe they are likely to contain
little additional information towards understanding the
basic policies embodied in the Act.· Such sources are
generally most useful only when one is focusing on specific
provisions of the Act. Also not addressed in this memorandum
are the disincentives.to the use of natural gas as a fuel
for power generation created py the Natural Gas Policy Act
of 1978 and the Public Utilities Reform Policy Act of 1978.
Finally, we should point out that there are likely to be
proposals next year from both the Carter Administration and
various industry groups advocating modification of the Act.
The specific language to be adv~nced by the Administration
and others is not yet available; and, therefore, is not
included in this memorandum. (Reports in the energy literature
referring to these-proposals are attached) ~ ·--· -·-· --
The discussion which follows addresses both the
substance of the .Act and the procedures under which it is
carried out by the Economic Regulatory Agency of the Department
of Energy. After a brief discussion of the Act's appli-
cability to several classes of facilities, the remainder of
the.discussion focuses only upon new electric powerplants.
The Basic Principles and Procedures.
The basic purpose of the Act is to require existing
powerplants and major fuel-burning installations (MFBI) to
switch from the use of natural gas or petroleumto coal or
other alternative fuel, and -to prohibit newly construc·ted
powerplants or MFBI's from using gas or petroleum as.a
primary fuel. The Act does this by creating separate rules
and requirements for the following four types of facilities:
1) new electric powerplants; 2) existing electric power-
plants; 3) new major fuel burning installations; and 4)
existing major fuel burning installations. Under the Act,
n.ew electric powerplants may not use natural gas or petroleum
as a primaryenergy source and no new electric powerplant
may be constructed without the capability to use coal or
other alternate fuel as a primary.energy source. (Sec.
201)~* Likewise, no new major MFBI may use natural gas or
petroleum as a primary energy source for boiler·fuel. (Sec.
202). Also unqer the Act, existing electric powerplants may
not use natural gas as a primary energy source after January
1, 1990 and in the case of certain electric powerplants,
before 1990. (Sec. 30l(a)). Where coal is available, the
Secretary is authorized to issue orders prohibiting the use
of gas or petroleum by existing electric powerplants. (Sec.
30l(b)). The prohibitions relating to existing electric
powerplants do not apply to Alaska. (Sec. 104). Finally
under the Act, the Secretary is authorized to prohibit the
use of petroleum or natural gas as a primary energy source
in existing MFBI's if he makes certain findings. (Sec.
302). This provision does apply to Alaska but is not analyzed
here.
Although the prohibitions in the Act are unequivocal,
there are numerous grounds for temporary and permanent
exemptions from these prohibitions. Indeed, most of the
language in both the Act and the regulations promulgated
* Simplifying somewhat, a new electric powerplant is
one for which construction or acquisition had not begun on
or before November 9, 1978 and consists of a stationary
(which under the regulations can include certain types of
portable) electric generating unit and has a design capability
of consuming any fuel at an input rate of 100 million Btu's
per hour or greater. A smaller unit can also be a power-
plant if it is aggregated, at the same site, with other
units which together use at least 250 million Btu's per
hour. (Sec. 103 (a) (7) and (a) (8) and Part 500. 2). Section
citations refer to the Act; Part citations refer to the
regulations in 10 CFR.
-2-
under the Act relates to the exemptions, not to the pro-
hibitions. Temporary exemptions for new powerplants may be
granted for a period of up to five years in most cases, and
in a few limited situations, for up to ten years. (Sec.
2ll(e}). A permanent exemption is for the life of the
facility. However, the Secretary i-s authorized to grant
both temporary and permanent exemptions upon such terms and
conditions as he deems appropriate; and this may include a
review of the circumstances upon which the exemption is
based. (Sec. 214(a)). Any exemption may be terminated if
the holder of the exemption fails to comply with the terms
and conditions contained in it. (Part 503.12). We note
here that a exemption may be granted exempting a utility
only from the gas or petroleum use prohibition. In that
case, a new powerplant authorized to burn gas or petroleum
may nevertheless be required to possess the capability to
use coal or any other alternate fuel as a primary energy
source. ·
The Secretary has adopted, by rule, a comprehensive
procedure for parties* to follow in seeking exemptions from
the prohibitions of the Act. Proposed rules applicable to
new powerplants and MFBI's were first issued on November 17,
1978. (43 F.R. 53974). Hearings were held in February on
those proposed rules, and on May 17, 1979 ERA issued final
interim rules.** The November proposal had contained a
general requirement that to obtain any exemption the applicant
had to submit a comprehensive report, called a Fuel's
Decision Report, which report presented, analyzed, and
ultimately rejected for specific.reasons, a wide range of
alternatives to the applicant's proposed use of natural gas
or petroleum as a primary fuel in its proposed new power-
plant. The rules adopted in May retained the Fuel's Decision
Report requirement, but reduced the amount of information
* In most instances, it would seem the party which
will apply for an exemption will be the utility which wants
to build and own the powerplant.
** That is, the rule is final but ERA will continue
to receive comments and may ma~e changes as a result of such
comments.
-3-
which the report must contain.* The format for the report,
as well as the generalized contents of a FDR, are described
in 10 CFR Part 502 (44 F.R. 28974, attached).
After the Secretary receives a request for exemption
and supporting documentation, he is required to publish a
notice in the Federal Register and allow any interested
persons to comment thereon. (Sec. 701). The Secretary is
also authorized to require any person subject to the Act to
"submit such information and reports of any kind or nature
directly to the Secretary necessary to implement the provisions"
of the Act. (Sec. 711). In the regulations, it appears the
Secretary will utilize this provision to require various
types of reporting.
The Act contains both civil and criminal enforce-
ment provisions. Any persons who willfully violate the
Act, or any rule thereunder, is subject to a fine of not
more than $50,000 and imprisonment for not more than one
year or both. (Sec. 722). Civil remedies include payment
of a penalty of up to $25,000 per violation, with each day
being a separate violation. For powerplants granted an
exemption, the Secretary may assess civil penalties of up to
$10/barrel of petroleum and $3/MCF of natural gas used in
operation of the powerplant in excess of that authorized by
the exemption. (Sec. 723). Also, the Secretary, or any
aggrieved person, may bring a civil action for injunctive or
equitable relief. (Sec. 724 and 725).
Exemptions
As noted above, the Act authorizes both temporary
and permanent exemptions. Temporary exemptions are for
situations where the new powerplant cannot immediately
comply with the prohibition against use of natural gas or
petroleum but will be able to do so after some period of
time. (A simple example would be where sufficient coal
* The peak load exemption and the emergency exemption
(discussed in the next section) do not require a FDR. The
applicant is required only to certify a particular (and
limited) use of the plant to qualify for these exemptions.
By the terms of the Act, the petitioner need not rule out
the use of alternative fuels to qualify for these exemptions
and thus need not submit a FDR.
-4-
supply is. not available when the plant comes on line but
will be available later.) Generally the grounds for, and
standards applicable to, temporary exemptions are the.same
or almost the same as for permanent exemptions. In the
following discussion, we address principa).ly permanent
exemtions. The-most-significant difference is -that there
are two alternative cost tests, a "general cost test" and a
"special cost test," available for applicants seeking a
temporary exemption. An.applicant seeking a permanent
exemption has no choice of cost tests; he must use the
"general cost test".
In addition to the specific grounds discussed
below for an exemption, the Act establishes a number of
general requirements which must be met before any applicant
may receive a permanent exemption.* (Sec. 213). These are
as follows:
1) The applicant must demonstrate that the use of
a mixture of natural gas or petroleum and coal or other
alternate fuel is not economically or technically feasible.
Under the Act and regulations, "mixture" includes both
simultaneous and alternate use of gas or petroleum and coal
or other alternate fuel in the same unit. (Sec. 103(28)).
An applicant demonstrates that it cannot comply with this
mixtures requirement by assuming it is going to use a
mixture and then showing that by making such use, the
applicant would qualify for a "lack of alternate fuel"
(which includes a cost test), "site limitation",. "environmental
requirement", "inability to obtain capital"/, or "State or
local requirement" exemption, or by showing that use of a
mixture is not technically or economically feasible due to
design or special circumstances (which circumstances are not
defined in the regulations). (Part 503.9).
2) If ERA makes a site specific or generic finding
that fluidized bed combustion of alternative fuels is
economically and technically feasible, then the Secretary
may deny all permanent exemption requests unless the applicant
demonstrates that with the use of fluidized bed combustion,
applicant would qualify for one of the exemptions listed in
1) above. (Part 503 .10). **
3) The Secretary may not grant a permanent exemption
* Except that general requirements "1)" and "2)" in the
text above do not apply to the "mixtures" exemption and the
"peak load powerplant" exemption and general requirement
"3)" above does not apply to the "cogeneration"·and "peak
load powerplant" exemptions.·
** The Secretary has not made such a finding and thus,
at least for now, this requirement seems unimportant.
-5-
for a new powerplant if there is available to an applicant a
supply .of electric power 11 Within a reasonable distance at a
reasonable cost without impairing short-run or long-run
reliability of service 11
• (Sec. 213(c)). The discussion of
this P!"O_yi_s_:ign in. the preamble to the· May 17 regulations
suggests that t.1irs requireme-riE -is quTEe -trouoTesonfe to -many
utilities. It appears several municipalities alleged the
requirement would force municipal systems to become merely
distributors of power rather than generators of power. (44.
F.R. 28961). To satisfy this requirement, an applicant for
an exemption must show (among other things) that he has
solicited contracts to purchase power from other sources
(including nonutility sources) within and contiguous to his
electric region, and that he is unable to purchase a firm
supply for a cost that is less than 10% above the annualized
cost of generating power .from his proposed gas or petroleum
fired plant during the first year of operation of the
plant. (Part 503.6). This requirement could result in .the·
use of older, less efficient gas or oil burning' plants being
used to generate electricity for sale to applicants who wish
to build newer, more efficient facilities. There is, however,
little flexibility for avoiding this result because the
requirement to consider purchased power as an alternative is
an express provision of the Act. (Sec. 213(c)). ERA has
recognized this possible outcome. (See 44 F.R. 28961).
4) An applicant must also demonstrate that it
cannot satisfy the alternative fuels requirement by locating
its facility at a reasonable alternative site. (Part 503.11).
After an applicant has made a showing that he has
satisfied all the general requirements for an exemption, he
must then demonstrate that he can satisfy the requirements
for a specific exemption. The grounds for specific exemptions
are as follows:
1) The Secretary must gr_ant a permanent exemption
if he finds that an applicant has demonstrated that, despite
diligent good-faith efforts, an adequate and reliable supply
of coal or other alternate fuel for use as a primary energy
source will not be avilable for the first 10 years of the
usefut life of the proposed powerplant; or such alternative
·fuel is available only at a cost which substantially exceeds
the cost of using imported petroleum as a primary energy
source during the useful life of the powerplant. (Sec.
212(a) (1) (A)). This exemption specifically requires that
the applicant consider the use of coal. It also requires
assessment of other alternate fuels, which are defined to
include electricity, coal, solar energy, petroleum coke,
shale oil, uranium, biomass, municipal, industrial, or
agricultural waste, wood, renewable and geotheormal energy
-6-
sources, and any fuel derived from an alternate fuel. (Part
500.2). A petitioner is not required to consider all of.
these · al terna ti ves, 'but only those which are reasonable ·
given his particular circumstances. (44 F.R. 28951). Under
the regulations, the applicant demonstrates that such supplies
are not avai:lable -by submi-E:t-ing~evidence t-hat he has sought ·
at least five bids· from suppliers who could reasonably be
expected to provide an adequate and reliable supply of the
quality _and quantity of alternate fuel needed during the
first 10 years of the new powerplant. (Part 503.31).
To obtain an exemption on th~ ground that the cost
of using alternative fuels substantially exceeds the cost of
using imported petroleum, an applicant must demonstrate that
the cost of the alternative fuel is at least 1.3 times
gre<;iter than the cost of using imported oil taking into
consideration capital costs and annual operating and main-
tenance expenses. The cost of using imported oil and the
alternative tuel are each discounted to present value before
the comparison is made. The procedures and formulas (including
a sample calculation) used for making these calculations are
set out in Part 503.5 of the re.gulations which also explain
the different standards applicable to permanent and temporary
exemptions. ·
2) A second basis for a mandatory exemption is
where there exist specific site limitations which do not
permit the use of coal or other alternate fuel as a primary
energy source. (Sec. 212(a) (1) (B)). Site limitations
include matters such as lack of transportation facilities
f()r alternate fuels, inadequate room for handling or storage
facilities, lack of adequate and reliable supply of water,
and similar matters. (Part 503.22).
3) The Secretary must grant an exemption .where an
applicant shows that compliance with the prohibitions would
cause him to be in violation of applicable environmental
requirements. (Sec. 212(a) (1) (C)); or where the use ·of coal
or other alternate fuel would not allow the applicant to
obtain adequate capital for financing of such powerplant.
(Sec. 212(a)(l) (D)).
In each of the above instances, the applicant must
demonstrate that he has attempted to overcome the difficulty
requiring him to seek exemption·· by considering alternative
sites for the powerplant; and that such alternative sites
also would require an exemption. (Part 503.11).
4) The Secretary, in his discretion, may grant an
exemption where the proposed powerplant could use coal or
another alternate fuel supply but for the existence of a
state or local requirement (other than a building code, a
.;..7-
:nuisance, or a zoning law).* Before an applicant can
qualify for an exemption under this provision, he must
demonstrate th~t he has considered obtaining a variance from
the Stat_e or local requirement or that none is available.
He must -a-1-so--demorrstrate·that--a-lternative sites are not
available which would avoid the problem and that granting
the exemption would be in the public interest and consistent
with the purposes of the Act. (Part 503.36).
5) The Secretary may grant a permanent exemption
where an applicant is proposing to construct a cogeneration
facility and he demonstrates that the economic and other
benefits of cogeneration are obtainable only if he uses
petroleum or natural gas or both in the proposed facility.
(Sec. 212(c) and Part 503.37).
6) The Secretary must grant an exemption if the
applicant demonstrates that the powerplant will use a
mixture of petroleum or natural gas and coal or other
alternate fuel as its primary energy source, provided the
amount of petroleum or natural gas used is the mininum
required to maintain plant reliabi.li ty. (Sec. 212 (d) and
Part 503.38).
7) The Secretary is required to grant an exemption
for a powerplant which would be used only for emergency
purposes. (Sec. 212(e)). · Under the regulations, emergency
is described as an instance where the utility would be
required to curtail noninterruptible supply to its industrial
customers. (Part 503. 39) •.
8) The Secretary may grant a permanent exemption
where the applicant demonstrates that the exemption is
necessary to prevent impairment of reliability of service;
and the applicant is not able to make the demonstrations
that he is entitled to a permanent exemption based on lack of
. alternate fuel supply, site limitations, environmental
requirements, inability to obtain adequate capital, or due
to certain State or local requirements in time to prevent
the impairment of service •. (Sec. 212(f)). In demonstrating
its eligibility for an exemption under this provision of the
Act, the applicant is required to use the "loss of load
probability technique." (Part 503.40). The regulations
emphasize that the Secretary's authority to grant such an
exemption is discretionary and that he reserves the right to
deny the exemption even if an applicant presents a case which
* If the State or local requirement is an environmental
requirement,it is treated under the exemption provision
discussed above.
-8-
meets the objective criterion set out in the regulation.
Furthermore, the regulations make clear that stringent terms
and conditions will be attached to this exemption which will
allow operation of such powerplant only for the purpose of
preventing an impairment of reliability of service, and for
riQother purpose. ·
9) An applicant may obtain a mandatory exemption
from the Secretary to use petroleum in a powerplant if a
petitioner certifies that such powerplant is· to be operated
solely as a peak load powerplant. *· (Sec. 212 (g)) • The
applicant may use natural gas in a peak load powerplant only
if the Administrator of the Environmental Protection Agency
certifies to the Secretary of Energy that use of coal or an
available alternate fuel by such powerplant will cause or
contribute to a concentration of a pollutant for which a
national ambient air quality standard is or would be exceeded.
(Part 503.4l(a) (2) (ii)). Under the regulations, a utility
must report annually on the use of its peak load powerplant;
and. if it exceeds the amount of use authorized by the
Secretary, the applicant is subject to various penalties.
(Part 503.41 (d) and (e)).
. 10) The Secretary may grant· a permanent exemption
for intermediate load powerplants provided a rather long
list of specific conditions are met; which list includes:
1) that the powerplant to be constructed and operated will
replace no more capacity than existing electric powerplants
which use natural gas or petroleum as a primary source; 2)
that the powerplants be owned by the same person; and 3)
that the net heat input rate for the new powerplant will be
maintained at or less than 9,500 Btu's per kilowatt hour
throughout the useful life of the new powerplant. (Sec.
212(h)). Essentially, this exemption allows for· the replacement
of inefficient powerplants using natural gas or petroleum as
a primary source with more efficient plants using natural
gas or petroleum, but only under limited circumstances.
(Part 503.42).
Preliminary Conclusions and Recommendations
1) It appears there do exist grounds under·which
any of the utilities along the Railbelt might qualify for a
permanent exemption from the requirement of the Act to use
* A Fuel Use Report is not necessa:ty.to obtain this
exemption.
-,-9-
. .
coal or Other alternate fuel. Such grounds might include
{a) lack ·of alternat;e fuel supply for the first 10 years of
the useful life of the facility; {b) lack of .alternate fuel
at a cost which does not substantially exceed the cost of
. imported oil; {c) site limi_tations (_this seems less likely);
{d) inability to comply with applicable environmental
requirements, and {e) inability to use alternative fuel
because of a State or local requirement.
·It should be noted that some of these exemptions
are based on ·economic factors and some are based on legal or
political constraints. Generally, where the exemption is
based on economics, the Secretary must gra:nt an exemption.
Where theconstraint is legal or political, the Secretary's
obligation to grant an exemption is sometimes mandatory -as
in the case of environmental constraints, and sometimes
discretionary -as in the case of State or local require-
ments. Finally, states or localities. can influence the use
or non-use of coal by the pollution standards they adopt.
California's air quality standards are the best example of
this.
2) A caveat to the above is that a surplus of
electric power by one utility may be regarded as an alternate
power supply for another utility which wants to build a new
powerplant. The requirement of the Act and regulations to
_consider surplus power as an alternate fuel before being
entitled to an exemption should be carefully analyzed in the
context of Alaska utilities. I suspect it has significant
consequences for the interplay between the existing {and
competing) utilities. The creation of interties among the
systems may also effect significantly the availability of
excess power as an alternate fuel source.
3) This memorandum is based entirely on the paper
record. I strongly recommend discussions with ERA officials
and Congressional staff responsible for the Fuel Use Act.
For example, it would be useful to know why Alaska is exempt
from the prohibitions applicable to existing powerplants but
not those applicable to new facilities, {Chugach Electric
representatives probably could explain this too) • Di~cussions
with program admi.nistrators most likely will turn up many
·nuances in the statute and regulations which one does not
glean from a mere reading of them. There are also many
questions not addressed in the regulations but which must be
dealt with by the agency on a regular basis. These include
such things as: To what extent may one utility use the work
submitted by other utilities? What kinds of "terms and
conditions" are being attached to permanent exemptions based
-10-
on cost or lack of alt~rnative fuel? Is the agency requiring
~~assessment periodically?
4} If it is possible to develop a plan or series
of options, (some of}.which may be prohibited by the Act, by
begi:iming discussioits now with D.C. ~dministrators and
Congress, it may be possibl~ to obtain legislation necessary
to allow.implentation of a plan at the time amendments to
the Act are considered in Congress next year.
5) The fact that _natural gas (or fo;r'that·matter
dom~stic petroleum} is available and less costly to use.
than either coal or foreign petroleum plays no direct.role
in determining whether a ut~lity may receive an exemption to
· use that gas or petroleum. It is only the delivered cost.
of imported petroleum which is relevant for cost comparisons •
. (Part 503.5(b} and (d) (2)}.
Attachments
;_ :u-