HomeMy WebLinkAboutAPA1124BRADLEY LAKE ~
HYDROELECTRIC POWER
PROJECT
FEASIBILITY STUDY
VOLUME 1
REPORT
OCTOBER 1983 A Stone & Webster Engineering Corporation
~-ALASKA POWER AUTHORITY_ .....
CONTRACT No. CC-08·3132 14500.14-H-(D)-1
BRADLEY LAKE
HYDROELECTRIC POWER
PROJECT
FEASIBILITY STUDY
VOLUME 1
REPORT
OCTOBER 1983 & Stone & Webster Engineering Corporation
...___ALASKA POWER AUTHORITY_ ....
COPYRIGHT, 1983
ALASKA POWER AUTHORITY
THIS DOCUMENT CONTAINS PROPRIETARY INFORMATION OF THE ALASKA POWER
AUTHORITY AND IS TO BE RETURNED UPON REQUEST. ITS CONTENTS MAY NOT BE
COPIED, DISCLOSED TO THIRD PARTIES, OR USED FOR OTHER THAN THE EXPRESS
PURPOSE FOR WHICH IT HAS BEEN PROVIDED WITHOUT THE WRITTEN CONSENT OF
ALASKA POWER AUTHORITY.
CERTIFICATIONS
BRADLEY LAKE HYDROELECTRIC POWER PROJECT
FEASIBILITY STUDY
The technical material and data contained in this report and its
Appendices were prepared under the supervision of the following indi-
viduals and organizations:
Volume 1 -Report
Appendix-C -Transmission
Line Analysis
Appendix A -Geotechnical
Studies
Appendix B -Phase I Feasibility
Study, Final Report
Appendix D -Transmission Line
System
Appendix E -Instream Flow
Assessment
~~
Theodore Critikos
Deputy Project Manager
Stone & Webster Engineering Corp.
--i?&D~
Rohn D. Abbott
Partner
Dryden & LaRue Consulting Engineers
Mic ael R. Joyce
Project Manager
Woodward-Clyde Consultants
This study
supervision
Principal-n-Charge
Stone & Webster Engineering Corp.
VOLUME 1 -
VOLUME 2 -
VOLUME 3 -
BRADLEY LAKE HYDROELECTRIC POWER PROJECT
FEASIBILITY STUDY
REPORT
APPENDICES
APPENDIX A
APPENDIX B
APPENDIX C
APPENDICES
APPENDIX D
APPENDIX E
GEOTECHNICAL STUDIES
FEASIBILITY STUDY -CONSTRUCTION
FACILITIES
TRANSMISSION LINE ANALYSIS
FEASIBILITY STUDY OF TRANSMISSION
LINE SYSTEM
BRADLEY RIVER INSTREAM FLOW STUDIES
TABLE OF CONTENTS
VOLUME 1 -REPORT
1 . EXECUTIVE SUMMARY.
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
1.10
1.11
1.12
INTRODUCTION
BRADLEY LAKE FEASIBILITY STUDY
RECOMMENDED PLAN .
PRINCIPAL FEATURES OF RECOMMENDED PLAN
ALTERNATIVES . . . . . .
TECHNICAL CONSIDERATIONS .
ENGINEERING AND ECONOMIC EVALUATIONS
ENVIRONMENTAL ANALYSES
PROJECT SCHEDULE . . . .
PROJECT COST ESTIMATES . .
POWER STUDIED AND ECONOMIC EVALUATIONS
FINDINGS AND RECOMMENDATIONS
2. INTRODUCTION . . .
2.1 PROJECT LOCATION AND SETTING.
2.2 BACKGROUND AND PAST STUDIES
2.3 THE BRADLEY LAKE FEASIBILITY STUDY.
2.4 STUDY METHODOLOGY AND APPROACH.
2.5 STUDY PARTICIPANTS.
2.6 REPORT ORGANIZATION
3 . RECOMMENDED PLAN
3 . 1 GENERAL .
3.2 PRINCIPAL FEATURES OF RECOMMENDED PLAN.
3.2.1 Access Facilities ...
3.2.2 Dam and Spillway. . .
3.2.3 Construction Diversion ..
3.2.4 Permanent Outlet Facilities
3.2.5 Intake Channel ..
3.2.6 Intake Structure.
3.2.7 Gate Shaft.
3.2.8 Power Conduit .
3.2.9 Powerhouse.
3.2.10 Substation and Transmission
3.2.11 Construction Camps. . .
3.2.12 Buildings Grounds and Utilities
3.2.13 Middle Fork Diversion
4. ALTERNATIVES INVESTIGATED.
4.1 GENERAL
4.2 DAMS.
1-1
1-1
1-2
1-3
1-3
1-6
1-8
1-9
1-10
1-11
1-12
1-12
1-17
2-1
2-1
2-2
2-4
2-5
2-7
2-8
3-1
3-1
3-1
3-1
3-2
3-4
3-4
3-5
3-5
3-5
3-6
3-6
3-7
3-7
3-8
3-8
4-1
4-1
4-1
TABLE OF CONTENTS (Cont'd)
VOLUME 1 -REPORT
4.3 SPILLWAYS ...... .
4.4 CONSTRUCTION DIVERSIONS
4.5 INTAKES .... .
4.6 GATE STRUCTURES ... .
4.7 POWER CONDUIT AND SURGE SHAFT
4.8 POWERHOUSE AND TAILRACE
4.9 TRANSMISSION FACILITIES
4.10 CONSTRUCTION CAMPS ..
4.11 MIDDLE FORK DIVERSION
5. TECHNICAL CONSIDERATIONS
5.1
5.2
5.3
5.4
GENERAL ....
PROJECT GEOLOGY
5.2.1 Scope of Investigations.
5.2.2 Geologic Conditions ..
5.2.3 Seismotectonic Setting .
5.2.4 Seismic Design .....
HYDROMETEOROLOGY . . . . . . . . . . . . . . . . . . . . . .
5.3.1 General ..... .
5.3.2 Basin Description.
5.3.3 Climatology.
5.3.4 Hydrology ..
SURVEY CONTROL. . .
6. ENGINEERING AND ECONOMIC EVALUATIONS
6.1 GENERAL CONSIDERATIONS .....
6.2 ASSESSMENT OF PRINCIPAL FEATURES.
6.2.1 Power Tunnel Development ..
6.2.2 Economic Power Tunnel Diameters.
6.2.3 Middle Fork Diversion.
6.2.4 Dam Type ........ .
6.2.5 Turbine Types ...... .
6.2.6 Plant Capacity and Project Economics
6.2.7 Reservoir Operating Levels
6.3 PROJECT OPERATION ...
7. DETAILED PROJECT DESCRIPTION
7.1 ACCESS FACILITIES .. .
7.1.1 General .... .
7.1.2 Barge Basin and Dock
7.1.3 Access Roads ..
7.1.4 Airstrip ....
7.1.5 Emergency Access .
4-1
4-2
4-3
4-3
4-3
4-3
4-4
4-4
4-4
5-1
5-1
5-1
5-1
5-3
5-8
5-9
5-13
5-13
5-13
5-14
5-16
5-21
6-1
6-1
6-4
6-4
6-6
6-7
6-8
6-9
6-13
6-13
6-15
7-1
7-1
7-1
7-1
7-5
7-10
7-10
TABLE OF CONTENTS (Cont'd)
VOLUME 1 -REPORT
7.1.6 Permanent Maintenance.
· 7.1.7 Alternatives
7.1.8 General Geology.
7.2 DAM AND SPILLWAY. .
7.2.1 General ..
7.2.2 Dam and Spillway
7.2.3 Hydraulics .
7.2.4 Selection of Dam Height.
7.2.5 Geology and Foundation
7.2.6 Access . .
7.2.7 Alternatives
7.3 CONSTRUCTION DIVERSION.
7.3.1 General. . .
7.3.2 Diversion Tunnel
7.3.3 Permanent Outlet Facilities.
7. 3. 4 Hydraulics . . . .
7 'l c:: ~.~~,~-~
I • ...J • -1 0\::.V.l.VQ:f • • • • • •
7.3.6 Structures and Appurtenances
7.3.7 Access
7.3.8 Alternatives .
7.4 POWER CONDUIT SYSTEM.
7.4.1 General ..
7.4.2 Power Conduit.
7.4.3 Hydraulics .
7.4.4 Transient Analysis
7.4.5 Geology. .
7.4.6 Access . .
7.4.7 Alternatives
7.5 POWER PLANT .
7.5.1 General. .
7.5.2 Basic Data .
7.5.3 Tidal Considerations
7.5.4 Turbines and Generators.
7.5.5 Powerhouse Arrangement
7.5.6 Electrical Equipment
7.5.7 Mechanical Equipment
7.5. 8 Geology. . ...
7.5.9 Access . . . .
7.5.10 Powerhouse Alternatives.
7.6 SUBSTATION AND TRANSMISSION .
7.6.1 General. . ..
7.6.2 Transmission Line Analysis
7.6.3 Powerhouse Substation ...
7.6.4 Transmission Lines •
7.6.5 Kenai Peninsula-Anchorage Transmission Line.
7.6.6 Alternatives .
7-10
7-11
7-11
7-14
7-14
7-14
7-17
7-18
7-19
7-22
7-22
7-25
7-25
7-25
7-26
7-27
7=29
7-29
7-30
7-30
7-32
7-32
7-32
7-39
7-40
7-42
7-51
7-51
7-52
7-52
7-53
7-53
7-54
7-55
7-58
7-62
7-64
7-64
7-65
7-66
7-66
7-66
7-68
7-69
7-72
7-72
TABLE OF CONTENTS (Cont'd)
VOLUME 1 -REPORT
7.7
7.8
7.9
CONSTRUCTION FACILITIES
7.7.1 General ....
7.7.2 Staging Areas.
7.7.3 Camp Areas .
7.7.4 Borrow and Waste Area Access
7.7.5 Construction at Dam Site
7.7.6 Construction at Powerhouse
7. 7. 7 Water Supply . .
7.7.8 Sewage Disposal.
7.7.9 Electric Power .
7.7.10 Other Facilities
BUILDING GROUNDS AND UTILITIES.
7. 8. 1 General. . . . .
7 .8.2 Staffing . . . . . .
7.8.3 Maintenance Facilities
7.8.4 Operations Equipment .
7.8.5 Residential and Office Facilities.
7 .8.6 Water. . . . . ..
7.8.7 Wastewater Treatment and Disposal.
7.8.8 Fire Protection. . . .
7.8.9 Project Physical Security.
7.8.10 Solid Waste Facilities
7.8.11 Other Facilities
MIDDLE FORK DIVERSION
7. 9.1 General. . ..
7.9.2 Recommended Plan
7. 9. 3 Geology. . . . .
7.9.4 Technical Details.
7.9.5 Dam, Gates and Conduit
7.9.6 Access ...
7. 9. 7 Alternatives
8. ENVIRONMENTAL ANALYSIS
9.
8.1 GENERAL . . .
8.2 MITIGATIVE STUDIES AND EVALUATIONS.
8.2.1 Instream Flow Studies.
8.2.2 Access to Project Site
8.2.3 Martin River Borrow Site
8.2.4 Waterfowl Nesting.
8.2.5 Moose Migration. .
8.3 IMPACT ADJUSTMENTS. . . .
8.3.1 Elimination of Alternative Structures.
8.3.2 Additional Project Features.
LAND AND LAND RIGHTS .
7-74
7-74
7-74
7-75
7-77
7-77
7-78
7-78
7-79
7-80
7-'80
7-81
7-81
7-81
7-81
7-82
7-82
7-83
7-83
7-84
7-84
7-84
7-84
7-85
7-85
7-85
7-86
7-86
7-88
7-88
7-89
8-1
8-1
8-2
8-2
8-4
8-4
8-6
8-7
8-7
8-7
8-8
9-1
•
TABLE OF CONTENTS (Cont'd)
VOLUME 1 -REPORT
10. PROJECT SCHEDULE AND CONSTRUCTION CONTRACTS.
10.1
10.2
10.3
10.4
10.5
GENERAL. . . .
ENGINEERING AND DESIGN
CONSTRUCTION SCHEDULE.
CONTRACTS. . .
10 .4 .. 1 General Civil Contract
10.4.2 Powerhouse Contract ..
10.4.3 Transmission Line Contract
SUPPLY ORDERS ..
11. PROJECT COST ESTIMATES
11. 1 PROJECT COST ESTIMATE SUMMARY.
11.2 COST ESTIMATES FOR ECONOMIC ANALYSIS
12. POWER S~UiliES AN~ ECONOMIC EVALUATION.
12.1
12.2
12.3
12.4
INTRODUCTION . . . . .
METHODOLOGY. . . . .
12.2.1 Electrical Generation Expansion Analysis System.
12.2.2 Life Cycle Cost. . .
12.2.3 Generation Expansion Optimization with EGEAS
12.2.4 Bradley Lake and Susitna Energy Dispatch
ECONOMIC PARAMETERS AND DATA . . .
12.3.1 Reference Case Railbelt Load Projection.
12.3.2 Reference Case Fuel Price Projections ..
12.3.3 Existing Railbelt Generation System ..
12.3.4 Future Railbelt Electric Generation Alternatives
12.3.5 Sensitivity Studies.
RESULTS. . ..... .
12.4.1 Reference Case .
12.4.2 Sensitivity Studies.
12.4.3 Evaluation of Selected 90 MW
Bradley Lake Project
13. FINDINGS AND RECOMMENDATIONS
13.1
13.2
FINDINGS . . . .
13.1.1 Introduction
13.1.2 Technical Findings
13.1.3 Costs and Economics . . .
RECOMMENDATIONS. . . . . . . .
14. BIBLIOGRAPHY
10-1
10-1
10-1
10-2
10-3
10-3
10-4
10-4
10-4
11-1
11-1
11-1
12-1
12-1
12-2
12-3
12-5
12-7
12-9
12-10
12-11
12-13
12-14
12-15
12-16
12-17
12-18
12-20
12-22
13-1
13-1
13-1
13-1
13-3
13-4
VOLill1E 1 -REPORT
Table No.
1.3-1
5.3-1
5.3-2
5.3-3
5.3-4
5.3-5
6.2-1
6.2-2
6.2-3
6.2-4
7.1-1
7.1-2
7.4-1
7.4-2
7.4-3
7.4-4
7.4-5
LIST OF TABLES
TITLE
Technical Data
Project
Bradley Lake Hydroelectric
Bradley River Flows at Lake Outlet
Adjusted for Nuka Glacier Switch
Middle Fork Flows at Diversion Dam
Estimated Average Monthly Flows -Lower Bradley
River
Bradley River Flows at Lake Outlet
Adjusted for Nuka Switch and Glacier Balance
Change
Bradley River Flows at Lake Outlet
Adjusted for Nuka Switch and for Trend of Glacier
Wasting.
Manufacturer's Turbine Data (3 sheets)
Manufacturer's Generator Data (6 sheets) ~
Preliminary Annual Energy -GWH
Reservoir Elevations Sensitivity Analyses -90 MW
Pelton -Two 45 MW Units
Design Windspeeds (mph) At Sheep Point,
Kachemak Bay, Alaska
Design Wave Characteristics
Chugachik Island
Sheep Point and
Hydraulic Transient Analyses -Francis
Type Turbines
Hydraulic Transient Analyses -Pelton
Type Turbines
Rock Core Properties Greywackes, Graywacke/
Argillite (Cataclastic), and Tuff
Rock Core Properties -Massive Argillite
Rock Core Properties -Foliated Argillite
VOLUME 1 -REPORT
Table No.
7.4-6
7.4-7
7.4-8
7.4-9
8.2-1
11.1-1
ii .2-i
11.2-2
11.2-3
11.2-4
11.2-5
12.3-1
12.3-2
12.3-3
12.3-4
12.3-5
12.3-6
LIST OF TABLES (Cont'd)
TITLE
Rock Gore Properties -Chert
Rock Core Properties -Fresh & Altered
Quartz Diorite -Terror Lake Tunnel
Tunneling Conditions
Portal
.List of Thin Sections
Fault & Fracture Zones,
Proposed Habitat Maintenance Flows for Project
Planning Purposes
Feasibility Study Cost Estimate -90MW Preferred
Plan (Summary sheet plus eleven back-up sheets)
Cost Estimates of Study Alternatives
Hydroelectric Plant O&M Costs
Transmission Line O&M Costs Bradley Lake
Powerhouse to Proposed Homer Electric Line
230kV Anchorage/Soldotna Transmission
Line Cost
Transmission Line O&M Costs -Anchorage/Soldotna
230kV Transmission Line
Economic Evaluation Parameters
Sherman H. Clark NSD Case Forecast -S'ummary of
Input and Output Data
Projected Peak and Energy Demand (NET) -Sherman
H. Clark NSD Case
Railbelt Peak Demand and Energy Projection (NET)
-Sherman H. Clark NSD Case
Historical Anchorage and Cook Inlet
Peak Demand
Historical Anchorage and Cook Inlet
Energy Requirements
VOLUME 1 -REPORT
Table No.
12.3-7
12.3-8
12.3-9
12.3-10
12.3-11
12.3-12
12.3-13
12.3-14
12.3-15
12.3-16
12.3-17
12.4-1
12.4-2
12.4-3
12.4-4
12.4-5
LIST OF TABLES (Cont'd)
TITLE
Load Projection (Net) Sherman H. Clark NSD Case -
Separation of Anchorage -Cook Inlet Load Into
Anchorage and Kenai Peninsula
Fuel Price Projections
Scenario (2 sheets)
Sherman H. Clark NSD
Total Generating Capacity within the Railbelt
System -1982
Existing Generating Plants in the Railbelt (5
sheets)
Thermal Generation Plant Parameters, 1983 Dollars
New Hydroelectric Generation Alternatives -Plant
Parameters
Bradley Lake Hydroelectric Project Plant Costs
Susitna Hydroelectric Project Plant Costs
Railbelt Peak Demand and Energy Projection (NET)
-DOR 50% Scenario (July 1983)
Fuel Price Projections -DOR 50% Scenario (July
. 1983)
Levelized Fuel Costs (1988-2037)
Alternatives to Bradley Lake -Present Worth Cost
of Optimum Expansion Plans
Bradley Lake without Susitna Present
Costs and Savings for Different Bradley
Capacities -Total Railbelt Expansion Plans
Bradley Lake without Susitna Present
Costs and Savings for Different Bradley
Capacities -Kenai Peninsula Expansion Plans
Worth
Lake
Worth
Lake
New Generation Capacity Added Base Case
(Thermal Plants Only) -Sherman H. Clark NSD Case
New Generation Capacity Added -60MW Bradley Lake
Project -Sherman H. Clark NSD Case
VOLUME 1 -REPORT
Table No.
12.4-6
12.4-7
12.4-8
12.4-9
12.4-10
12.4-11
12.4-12
12.4-13
12.4-14
12.4-15
12.4-16
12.4-17
12.4-18
12.4-19
LIST OF TABLES (Cont'd)
TITLE
New Generation Capacity Added -90MW Bradley Lake
Project -Sherman H. Clark NSD Case
New Generation Capacity Added 135MW Bradley
Lake Project -Sherman H. Clark NSD Case
Generation by Fuel Class -Base Case (New Thermal
Plants Only) -Sherman H. Clark NSD Case
Generation by Fuel Class 90MW Bradley Lake
Project -Sherman H. Clark NSD Case
Expansion Plan Summary Base Case (Thermal
Plants) -Reference Case Load
Expansion Plan Summary 90MW Bradley Lake
Project -Reference Case Load
Bradley Lake with Susitna -Present Worth Costs
and Savings for Different Bradley Lake Capacities
-Total Railbelt Expansion Plans
Bradley Lake with Susitna -Present Worth Costs
and Savings for Different Bradley Lake Capacities
-Kenai Peninsula Expansion Plans
Expansion Plan Summary 90MW Bradley Lake
Project with Susitna -Reference Case Load
Railbelt Generation Expansion Plans -Sensitivity
Analysis to Railbelt -No-Growth Case
New Generation
(Thermal Plants
Sensitivity Case
Capacity
Only)
Added
0%
Base Case
Load Growth
New Generation Capacity Added -90MW Bradley Lake
Project -0% Load Growth Sensitivity Case
Generation by Fuel Class -Base Case (New Thermal
Plants Only) -0% Load Growth Sensitivity Case
Generation by Fuel Class -90 MW Bradley Lake
Project -0% Load Growth Sensitivity Case
VOLUME 1 -REPORT
Table No.
12.4-19
12.4-20
12.4-21
12.4-22
12.4-23
12.4-24
12.4-25
12.4-26
12.4-27
12.4-28
12.4-29
12.4-30
LIST OF TABLES (Cont'd)
TITLE
Generation by Fuel Class -90 MW Bradley Lake
Project -0% Load Growth Sensitivity Case
Expansion Plan Summary
Plants) -No growth Case
Expansion Plan Summary
Project -No Growth Case
Base Case (Thernal
90 MW Bradley Lake
New Generation Capacity Added Base Case
(Thermal Plants Only) -DOR SO% Case (July 1983)
New Generation Capa~ity -Added 90MW Bradley Lake
Project -DOR 50% Case (July 1983)
Generation by Fuel Class -Base Case (New Thermal
Plants Only) -DOR SO% Case (July 1983)
Generation by Fuel Class 90MW Bradley Lake
Project -DOR 50% Case (July 1983)
Expansion Plan Summary -Base Case
(Thermal Plants) -DOR 50% Case
Expansion Plan Summary -90MW
Bradley Lake Project -DOR 50% Case
Capital Costs and Average Annual Energy -90MW
Bradley Lake Project Feasibility Stage and
Selected Values
Selected 90MW Bradley Lake Project without
Susitna -Present Worth Costs and Savings
Expansion Plan Summary -Selected 90MW Bradley
Lake Project -Reference Case Load
VOLUME 1 -REPORT
Figure
5.3-1
5.3-2
5.3-3
5.3-4
5.3-5
6.1-1
6.1-2
6.2-1
6.2-2
6.2-3
6.2-4
6.2-5
6.2-6
6.3-1
6.3-2
7.3-1
7.3-2
7.4-1
LIST OF FIGURES
TITLE
Annual Flow Duration Bradley Lake Outlet -
Adjusted for Nuka Glacier Switch Only
Annual Flow Duration -Middle Fork
Annual Flow Duration -Lower Bradley River
Annual Flow Duration Bradley River -with Glacier
Mass Balance Adjustments
Annual Flow Duration Bradley River -with Glacier
Wasting Trend Removed
Assessment of Principal Features -Bradley Lake
Project
Preliminary lnstream Flows
Economic Diameter Analysis -Power Conduit -90MW
Plant
Alternative Concrete Gravity Dam Concept
Energy Evaluations -Francis and Pelton Turbines
Comparative Evaluations -Francis and Pelton
Turbines
Alternative -90MW Francis Unit Powerhouse
(Sheet 1)
Alternative -90ffi{ Francis Unit Powerhouse
(Sheet 2)
Streamflows -Bradley River at Bradley Lake
Recommended Instream Flows
1979 Inflow -Outflow Hydrographs
Diversion Tunnel Flood Routing
Hydraulic Transients -Francis Units
VOLUME 1 -REPORT
Figure
7.4-2
7.4-3
7.4-4
7.4-5
7.4-6
7.4-7
7.4-8
7.4-9
7.6-1
7.9-1
12.2-1
12.2-2
12.2-3
12.4-1
12.4-2
12.4-3
LIST OF FIGURES (Cont'd)
TITLE
Hydraulic Transients -Pelton Units
Thin Section Petrographic Examination -Graywacke
Thin Section Petrographic Examination -Massive
Argillite
Thin Section Petrographic Examination -Foliated
Argillite
Thin Section Petrographic Examination -Cherty,
Foliated Argillite
Thin Section Petrographic Examination -Tuff
Thin Section Petrographic Examination -Quartz
Diorite
Thin Section Petrographic Examination -Quartz
Diorite
Alternative SF6 Substation
Hydraulic Rating Curves -Middle Fork Diversion
Typical Bus Bar Cost
Stages in EGEAS GeneTation Expansion Analysis
Bradley Lake Dispatch By EGEAS
Sherman Clark NSD Case
DOR 50% Case (July 1983)
Sherman Clark NSD Case -Selected 90MW Plant
VOLUME 1 -REPORT
Plate No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
LIST OF PLATES
TITLE
Location Map
Overall Project Features
General Plan
Access Facilities
Access Channel and Barge Basin
Dock Structure Details
General Arrangement
Structures
Dam, Spillway and Flow
Concrete Faced Rockfill Dam -Sections and Details
Spillway -Elevation and Sections
Construction Diversion -Sections and Details
Intake Channel and Gate Shaft
Details
Power Conduit -Profile and Details
Sections and
90MW Pelton Powerhouse -Plans and Sections
Sheet 1
90 MW Pelton Powerhouse -Plans and Sections -
Sheet 2
Powerhouse Substation and Bradley Junction
Middle Fork Diversion -Plan and Profile
Middle Fork Diversion -Elevations and Details
Project Design Floods and Reservoir Area
Capacity Curves
Reservoir Regulation
Diversion Discharge
90MW Plant with Fish
VOLUME 1 -REPORT
Plate No.
20
21
22
23
LIST OF PLATES (Cont'd)
TITLE
Reservoir Regulation -90MW Plant without Fish
Diversion Discharge
Rating Curves
Main One Line Diagram
Project Schedule
1
EXECUTIVE
SUMMARY
1. EXECUTIVE SUMMARY
1. 1 INTRODUCTION
The role that Bradley Lake Hydroelectric Project will play in meeting the
electrical needs of the State of Alaska has been under study for some
time. Study of the Bradley Lake Project was initially authorized by the
Federal Government in 1962 and since then, many studies and evaluations
have been performed by the U.S. Army Corps of Engineers (COE) to determine
the technical and economic feasibility of developing the power potential of
Bradley Lake. The State of Alaska became directly involved in 1981 when
the Alaska Legislature appropriated funds to initiate construction of the
project. In 1982 the Legislature authorized the Alaska Power Authority to
assume the development of the project, and in October 1982, the Power
Authority's Board of Directors authorized pursuing design and construction
of the project by the Power Authority.
Shortly after assuming the responsibility for the Bradley Lake Project, the
Power Authority issued a Request for Proposal in November 1982, soliciting
professional services for the engineering and design work of the Bradley
Lake Hydroelectric Project. Stone & Webster Engineering Corporation (SWEC)
was selected as the Architect/Engineer and this selection was approved by
the Board of Directors on March 14, 1983. The Powe-r Authority contract
with SWEC, dated April 20, 1983 required that, prior to the initiation of
engineering and design, a feasibility study be performed to re-evaluate the
technical and economic feasibility of the project. These efforts were
designated as Phase I -Feasibility Study, and had the following objectives:
o Ascertain the technical feasibility of the project in sufficient detail
to eliminate all major uncertainties.
o Select the most attractive size plant and scheme of development for the
Bradley Lake Hydroelectric Project.
1-1
o Determine the role that a Bradley Lake Hydroelectric Project will have
as a power development in the overall energy plans for the State of
Alaska and evaluate the economic merits of the project as compared to
alternative generation in the State.
1. 2 BRADLEY LAKE PROJECT FEASIBILITY STUDY
Beginning in April 1983 SWEC organized the scope of work of the Feasibility
Study under· the following work tasks:
o Data Collection
o Review of Data
o Technical Review Board
o Conceptual Design of Common Items
o Conceptual Design of 60 MW, 90 MW and 135 MW Plants
o Evaluation of Construction Facilities
o Quantity Development and Construction Cost
o Power Study and Economic Analysis Approach
o Geotechnical Investigations
o Instream Flow Studies
o Transmission Lines
o Selection of Preferred Plan
o Feasibility Report
All of the above work tasks
collection and review process
were pursued
resulted in a
to completion. The data
thorough understanding of
previous work ana identified areas requiring further investigation.
Previously identified areas of concern were evaluated and feasible
solutions pursued. Conceptual engineering and design efforts permitted the
assessment of previous concepts and the implementation of new innovative
ideas. Geotechnical work resolved foundation uncertainties and hydrologic
and instream flow studies substantiated the energy capabilities of the
development. Cost and economic evaluations confirmed the economic merits
of the Bradley Lake Hydroelectric Project.
1-2
1 . 3 RECOMMENDED PLAN
The recommended plan developed for the Bradley Lake Project would use water
stored at the lake and the effective pressure head between the lake and
Kachemak Bay to generate electricity. A dam, at the outlet of the lake,
will impound water and raise the lake. level thereby increasing the
effective generating head. Additional water is provided with the diversion
of natural flows from the Middle Fork drainage basin to Bradley Lake.
Stored water is conveyed to the generating facilities through a concrete
lined tunnel and a buried penstock power conduit. The power generating
facilities are housed within an above ground enclosed powerhouse located at
the eastern shoreline of Kachemak Bay. Two separate and parallel
transmission lines, each about 20 miles long, connect the project to a
transmission line to be constructed by others. Table 1.3-1 gives a summary
of the salient Technical Data for the project development.
1. 4 PRINCIPAL FEATURES OF RECOMMENDED PLAN
Access Facilities
The prime access to the site during construction of the project and later
during project operation will be by water using an access channel and barge
basin. Additional acces.s is provided by an airstrip located in the
vicinity of the powerhouse. Helicopter pads are also located at key areas
within the Project boundaries. Access roads are provided to serve the
project during construction and permanent operation. Three road networks
have been established: one network serves the airstrip, powerhouse, dock,
staging area and lower camp; a second network will connect the lower camp
to the upper camp and continue to the dam area; and a third network will
allow access to a construction borrow area.
Dam and Spillway
A concrete faced rockfill dam with an ungated concrete gravity spillway is
to be constructed at the outlet of Bradley Lake. These structures will
impound the natural inflows and allow raising the present lake level by
1-3
about 100 feet to elevation 1,180. The dam crest is set at elevation 1,190
and the total top length is about 605 feet. The maximum dam height above
its foundation is about 125 feet. Upstream and downstream cofferdams are
provided for construction of the main dam.
The reservoir impounded by the dam will contain an active storage of about
284,000 acre-feet at normal operating pool elevation 1, 180 with a surface
area of about 3,820 acres.
An ungated concrete gravity overflow spillway is located over the bedrock
saddle formation at the right abutment area of the lake outlet. The
spillway has an ogee set at elevation 1, 180 with a crest length of 165
feet. The length of the spillway including abutments is approximately 230
feet. The spillway is designed to pass the Standard Project Flood, as well
as the Probable Maximum Flood.
Construction Diversion
Diversion of the natural outflow from Bradley Lake during construction of
the main dam and other structures at the lake outlet will be accomplished
by a horseshoe shaped tunnel excavated through the right rock abutment,
approximately 100 feet east of the lake outlet. The 470 foot long tunnel
will discharge into the large natural pool downstream of the main dam. A
concrete intake portal will be constructed with provisions for steel
bulkhead gates.
Permanent Outlet Facilities
Permanent outlet facilities will be incorporated into the construction
diversion tunnel. The outlet facilities will serve as low level outlets
providing for emergency drawdown of the reservoir and diversion of flows to
the Bradley River for fish habitat. Flows will be controlled by
hydraulically operated slide gates.
1-4
Intake Channel
Stored water is conveyed to the power tunnel intake structure through a 50
foot wide by 360 foot long intake channel. The channel is located at the
left bank area and allows the reservoir to be drawn to elevation 1060.
Power Gondui t
The power conduit includes all water passage structures that are used to
bring water from Bradley Lake to the Kachemak Bay Powerhouse. From an
intake structure provided at Bradley Lake, a 18,820 feet long, 11 foot
diameter underground power tunnel connects Bradley Lake to the powerhouse.
Located about 800 feet downstream of the intake structure is a circular
shaped gate shaft which contains two hydraulically operated gates for
emergency closure of the power conduit. The concrete and steel lined
tunnel connects to a buried steel penstock at the tunnel portal near the
powerhouse. The steel penstock then bifurcates into 8 feet diameter steel
br~ches leading to the hydraulic turbine generating units. Each branch is
equipped with a spherical valve located immediately upstream of the units.
Powerhouse and Tailrace
The powerhouse is located near sea level on the eastern shore of Kachemak
Bay. The powerhouse will contain two Pelton hydraulic turbine generating
units having a combined rating of 107 MW. Each unit is capable of
generating 45 MW at minimum head with a nominal operating speed of 300
rpm. The powerhouse substructure is constructed of reinforced concrete
which is enclosed with an insulated steel superstructure. The tailrace is
an excavated trapezoidal unlined channel approximately 100 feet long
extending from the powerhouse into the tidal flats.
Substation and Transmission
The substation is located adjacent to the northeastern end of the
powerhouse and is rated 115,000 volts, 3-phase, 60 Hz. It contains the
main power transformers, circuit breakers, disconnecting switches, and line
takeoff towers.
1-5
Power from the Bradley Lake substation is carried via two parallel 115 kV
transmission lines.-These lines are constructed using wood pole, H-frame
structures and aluminum conductors, steel reinforced. Each line is
designed to transmit the full output of the plant, in the event one line is
lost. The Bradley Lake lines are connected to another 115 kV transmission
line which transmits power between Soldotna and Fritz Creek. The
connection to this line, at a location called Bradley Junction, is about 20
miles from the power plant.
Middle Fork Diversion
The Middle Fork Diversion is located approximately one mile northeast of
Bradley Lake in an adjacent basin, and provides seasonal diversion of water
into Bradley Lake. The diversion scheme consists of a 20 feet high
embankment dam and 1,900 feet of 6 feet diameter steel conduit. Other
features include a spillway and bypass conduit which will be used initially
for construction diversion and later to divert the natural winter flows
downstream into the Middle Forko
1. 5 ALTERNATIVES
In arriving at the selection of the Recommended Plan of development, it was
necessary to review the previous studies and to appraise various design
alternatives in order to develop the most economical and sound plan of
development. The major alternatives considered in the study are as follows:
Dam and Spillway
The following dam and spillway configurations were reviewed and considered:
o Concrete gravity dam incorporating a concrete spillway section
o Concrete gravity dam with a separate ungated spillway dam
o Rockfill dam with a side channel spillway
o Rockfill dam with a separate ungated spillway dam
o Double curvature arch dam
o Roller compacted concrete gravity dam
o Concrete faced rockfill dam with a separate spillway
1-6
The recommended plan includes the concrete faced rockfill dam with a
separate ungated spillway dam.
Construction Diversion
Various diversion schemes were analyzed. These included tunnel
arra~gements through the right and left abutments at the lake outlet and
also buried conduit through the main river channel. A tunnel alignment
through the right abutment with diversion flow discharging into a natural
stilling pool was judged the best and included in the Recommended Plan.
Power Conduit
The previous COE concept of the intake located at the right bank of Bradley
Lake was reviewed for applicability. As an alternative, intake located on
the left bank was analyzed and found feasible. From this location three
alternative power tunnel alignments to the powerhouse were investigated.
All three alignments utilized deep settings with concrete lined tunnels and
buried steel penstocks. The COE concept had included a higher set tunnel
with an exposed surface penstock along the hillside above the powerhouse.
The lower setting for the tunnel and buried penstock was determined to be
the most desirable alternative.
Powerhouse
The COE had previously investigated above and underground powerhouses and
concluded that the above ground arrangement would be the most economical.
SWEC concurred and investigated the above ground powerhouse only. The COE
powerhouse arrangement included three generating units whereas SWEC adopted
the more conventional and economical two unit arrangement as an alternative.
Middle Fork Diversion
The COE had previously investigated a steel bin wall dam, concrete gravity
dam, and a timber buttress dam for diverting the Middle Fork flows. To
maximize use of natural materials in the area, SWEC analyzed two variations
1-7
of rockfill dams: a concrete faced rockfill and a steel sheet pile cut-of£
rockfill. The latter was judged the most attractive scheme and was
included in the Recommended Plan.
1. 6 TECHNICAL CONSIDERATIONS
The project's regional geologic setting and the hydrologic influences of
its environment largely dominated the spectrum of technical considerations
addressed in the study. These two areas substantially controlled the
engineering and economic feasibility of the more salient features of the
project.
Geology
The Bradley Lake Project is located in an area of the Kenai Mountains which
is composed primarily of mildly metamorphosed argillite and graywacke
rock. These rocks have been uplifted and deformed from past seismotectonic
activity and shaped by continuous erosional processes.
The two major geologic features within the project site are informally
known as the Bradley River and Bull Moose Faults. Although no direct
evidence of recent activity along these or regional faults is known, all
are considered capable of independent earthquake generation. Statistical
analysis of the magnitude of historical ground motion from earthquakes
indicates that earthquake accelerations ranging from 0. 3g to 0. 75g should
be used in the final design of the major surface structures. Evidence
gathered to date has not revealed any geologic features with potential for
ground displacement at the main dam or powerhouse. Although the potential
for ground shifting associated with large earthquakes exists along the
power tunnel alignment at the two major faults, it would be possible to
repair any resulting damage.
Hydrology
The intensity and seasonal distribution of storms producing precipitation
within the Bradley Lake drainage basin reflect the maritime climate of the
1-8
region. The runoff response from rainfall precipitation, which is
influenced largely by the geologic conditions, exhibits a rapid rise in
s_treamflow, with little flow going into groundwater storage. Recorded
streamflow data at the Bradley Lake outlet consequently reflects the
maritime influences and geologic conditions of the basin. Analysis of
these data indicate that highest streamflows occur during May through
October. Snow and glacial melt water contribute a substantial portion
during the spring and summer months and rainfall contributes to streamflow
during the fall months. Flood peaks during this period have exceeded 5,000
cfs, however, streamflows during the drier winter period, seldom exceed 75
cfs.
To account for possible future changes in streamflows and its effect on
power production of the project, the historical streamflow record required
several adjustments for glacial influences. Initial adjustments were made
to the first half of the records to reflect Nuka Glacier runoff being
·;._\,;
redirected into the Bradley Lake drainage basin. Other adjustments were
then made to the entire record to reflect both historical and potentia 1
climatic effects of the glaciers on streamflow. Although these adjustments
resulted in noticeable yearly fluctuations in streamflow in comparison with
the initial adjustments, the overall effect of the more conservative
glacial adjustment on annual energy production was found to be a reduction
in generated energy of less t~an 2 percent.
The Probable Maximum and Standard Project Floods as developed by the COE
were used in this study without modifications.
inflows of 31,300 cfs and 14,400 cfs, respectively.
1. 7 ENGINEERING AND ECONOMIC EVALUATIONS
The floods have peak
Various engineering studies and economic analyses were conducted in
selecting the most attractive scheme of project development. In pursuing
this goal, previous work and findings were reviewed and new ideas and
concepts developed in the preliminary stages of the feasibility study. A
screening process was established which identified the more promising
alternatives and project features for further evaluation. These
1-9
evaluations included engineering and operating considerations as well as
cost comparisons and economic appraisals.
A list of alternatives and project features used in comparative evaluations
together with the sequence in which they were studied follows.
o Use of Tunnel Boring Machine for power tunnel excavation
o Economical power tunnel diameter
o Francis or Pelton turbine/generator equipment
o Middle Fork Diversion facilities
o Rockfill vs: concrete gravity main dam
o Plant capacity
o Bradley Lake reservoir operating levels
These features as well as the alternatives, which affect the economic
benefits of the project, were
matrix developed of energy
evaluated using computer simulations and a
potential versus alternatives. Economic
benefits were then computed and compared with estimated costs together with
engineering and environmental considerations to arrive at the preferred
plan for development of the project.
1 . 8 ENVIRONMENTAL ANALYSES
The Bradley Lake Hydroelectric Project is in an area of high peaks,
glacier, wildlife and sub-alpine terrain. The area is inhabited by a
diversity of wildlife species. Although the site itself is free of human
habitation, the project can be constructed with minimal impact and will
provide benefits serving the population of the Kenai Peninsula and the
developing area of south central Alaska.
The Corps of Engineers' (COE) environmental studies identified the effects
of developing the Bradley Lake Project on biological and sociojcultural
resources, and addressed these in its Final Environmental Impact Statement
(FEIS) issued in August 1982. Areas of environmental concern, identified
in the FEIS, are slow releases for downstream fish habitat; resolution of
access to the project; rehabilitation of the Martin River borrow area; ...... ....;_ ..... _.
plans for developing waterfowl nesting; and assessment of moose mig~ations.
1-10
Since the SWEC Recommended Plan is essentially similar to the COE's
preferred plan for Bradley Lake, there should not be other unresolved
issues or impacts. In fact, the SWEC Plan reduces the environmental
impacts with the following elimination.s:
o The 2800 foot long above ground penstock extending from the powerhouse
to the tunnel portal.
o The two mile access road from the powerhouse to the tunnel portal.
o Surge shaft and associated access road.
o Exposed steel penstock and bridge as required for the power tunnel
crossing over the Bradley River.
Further, and as part of this feasibility study, instream flow studies have
been conducted to assess downstream fish habitat; means of access to the
project were re-assessed; pla~s are being considered for developing
waterfowl nesting and for the rehabilitation of the Martin River b2Frow
area; and a program for studying moose migrations is being planned, ~or
early implementation. Data from the instream flow studies show that fish
habitat at the lower Bradley River can be maintained by regulating river
flows or even improved. The re-assessment of providing project access, by
means other than the preferred plan, showed that alternatives would either
present greater environmental impacts, cost more, or both. Mitigation of
waterfowl nesting and for the Martin River borrow will be developed as part
of the license application effort to the Federal Energy Regulatory
Commission (FERC). The assessment of moose migratory habits has been
authorized and will be implemented as part of other project development
efforts.
Some further assessment and environmental evaluation work may be required
in relation to the proposed transmission line and upper camp area.
1 . 9 PROJECT SHCEDULE
The Project Schedule extends over a five year period with the initial
construction activities dependent on the award of a FERC License. Receipt
of the FERC License is anticipated in May 1985, with commercial operation
1-11
of the units scheduled for October 1988 and completion of the project by
the end of 1988. Should award of the FERC License be delayed, seasonal
scheduling problems will ensue, and the project schedule including the
commercial operation dates, will be delayed.
The engineering and design is scheduled to commence in February 1984,
coincidental with the submittal of the FERC License Application to the
Regulatory Commission. The construction schedule for the Bradley Lake
project is predicated on three major construction contracts (1) General
Civil Contract; (2) Powerhouse Contract and (3) Transmission Line
Contract. Several major equipment supply contracts such as hydraulic
turbines, generators, governors, powerhouse crane, gates, valves, pumps and
electrical accessory equipment will be awarded separately to support
engineering-design needs and delivery dates to meet the required
construction erection schedule.
1. 10 PROJECT COST ESTIMATES
The Overnight Cost Estimate for the preferred 90 MW plan is $283,019,000.
This cost includes: direct material, labor, and construction equipment;
engineering and design cost; cost for the management of construction;
Owner's cost including previous expenditures realized for project studies
and development; land and land rights cost; all risk insurance; and a
contingency of 25 percent. The Overnight Cost Estimate refelcts cost as of
July 1983.
1.11 POWER STUDIES AND ECONOMIC EVALUATION
The objectives of the power study and economic evaluation of the Bradley
Lake Project were to identify the economic advantages or disadvan:tages of
the Project for the Railbelt and to select the preferred plant capacity.
Several variations in Railbelt generation expansion plans were evaluated.
Separate analyses were performed for generation expansion plans using
thermal power plants (gas-fired combined cycle, gas-fired combustion
turbine, and coal-fired steam turbine), the Susitna Hydroelectric Project
combined with thermal plants, and the Bradley Lake Project (with and
1-12
without Susitna) for the three proposed project capacities of 60MW, 90MW,
and 135MW. Also, sensitivity studies were performed to determine the
effect of variations in the Railbelt load growth rate on the economic
performance of the Bradley Lake Project.
The primary tool used in this evaluation was a computer program developed
for the Electric Power Research Institute. This program, Electric
Generation Expansion
automatically develop
Analysis System,
electric generation
provided
expansion
the capability
plans based on
to
the
characteristics and costs of alternative generation sources, existing unit
characteristics and retirement dates, and electric load data. The total
present worth cost for each generation expansion plan was determined, with
the lowest cost plan being the optimum.
This computer program was also used to perform a two-area analysis where
reserve sharing and economy interchange were modeled between the Kenai
Peninsula and the remainder of the Railbelt. This analysis was used to
apportion costs between the two regions and to evaluate the effect of
transmission limitations between Anchorage and the Kenai Peninsula on the
present worth costs of the generation expansion plans. An assessment of
the differences in transmission costs associated with generation expansion
plans including and not including the Bradley Lake Project was essential to
the power study.
The primary data source for the study was the Harza-Ebasco Susitna FERC
application of July 1983. Information derived from this document included
items such as fuel prices and escalation rates, new generation
alternatives, Susitna characteristics, and existing generation units in the
Railbelt. The Reference Case Railbelt electric load forecast used in the
Bradley Lake study was also derived from this source. The Reference Case
forecast, titled "Sherman H. Clark Associates NSD Case," has an average
annual compound load growth rate of about 2. 8 percent for the period 1983
through 2007.
The power study and plant capacity selection were based on Bradley Lake
capital costs and average anual energy values developed during the
1-13
feasibility stage evaluations.
following:
These plant parameters included the
Bradley Lake
Capacity, MW
* Includes IDC.
60
90
135
Capital Cost,*
Millions 1983$
275.70
287.95
303.50
Average Annual
Energy, GWH
330.5
345.4
356.6
The power study evaluations indicate that the Bradley Lake Project is
economically beneficial for the Railbelt at any of the three proposed plant
capacities, both with and without the presence of Susitna. The optimum
capacity for Bradley Lake is dependent on and sensitive to the projected
load growth rate for the Railbelt. The differences in present worth cost
between the three proposed capacities for alternative load growth
projections are relatively small.
For the Reference Case load projection, the 90MW Bradley Lake Project shows
the largest net benefit for the Railbelt without the presence of Susitna,
while the 60MW and 90MW Bradley Lake Projects exhibit approximately equal
benefits when Susitna is present. The Reference Case present worth costs
for the cases without Susitna are as follows:
Present Worth, Millons 1983~
Total Railbelt Kenai Peninsula
Bradley Lake Savings Due to Savings Due to
Capacity, MW Total Cost Bradley Lake Total Cost Bradley Lake
0 (Base Case)* 5,832 904
60 5,517 315 605 299
90 5,464 368 599 305
135 * 5,535 297 695 209
*Includes 230 kV Anchorage/Soldotna transmission line.
1-14
For the total Railbelt, the Bradley Lake savings range from 5.1 to 6. 3
percent of the base case present worth cost. The savings for the Kenai
Peninsula alone (taking into account reserve sharing and economy interchange
with the rest of the Railbelt) varied tram 23.1 to 33.7 percent of the base
case. The Reference Case present worth.costs for the cases including Susitna
are as follows:
Present Worth, Millons 1983~
Total Rail belt Kenai Peninsula
Bradley Lake Savings Due to Savings Due to
Capacity, MW Total Cost Bradley Lake Total Cost Bradley Lake
0 (Base Case)* 5,724 674
60 5,548 176 531 143
90 5,549 175 523 151
135 * 5,658 66 624 50
*Includes 230 kV Anchorage/Soldotna transmission line.
With Susitna, the Bradley Lake savings range from 1. 2 to 3. 1 percent for the
total Railbelt and from 7.4 to 22.4 percent for the Kenai Peninsula alone.
Two sensitivity cases were evaluated to determine the economic impact on
Bradley Lake if the Railbelt electric load growth is less than the Reference
Case. The two cases included an assumed load growth of zero percent per year
(with the Reference Case fossil fuel price projections) and a load growth and
fossil fuel price projection titled "DOR 50% Case."
For the no-growth sensitivity study, the 1983 Railbelt electric load was
assumed to remain constant for the study period. The present worth costs,
for the total Railbelt without Susitna, are as follows:
1-15
Present Worth~ Millions 1983~
Bradley Lake Savings Due to
Capacity, MW Total Cost Bradley Lake
0 (Base Case) 3,194
60 2,966 228
90 * 2,990 204
135 * 3,010 184
*Includes 230 kV Anchorage/Soldotna transmission line.
The 60MW Bradley Lake Project is the preferred capacity under a no-growth
scenario.
The second sensitivity study using the July 1983 "DOR 50% Case" was performed
for only two generation expansion plans. These plans without Susitna
included a base case (new thermal plants) and a case with the 90MW Bradley
Lake Project plus thermal plants. The results are as follows:
Case
Base*
90MW Bradley Lake
Present Worth Cost
Millions 1983$
3,461
3,305
* Includes 230kV Anchorage/Soldotna transmission line.
Under the "DOR 50% Case," the installation of the 90MW Bradley Lake Project
results in a present worth savings of about $156 million for the total
Railbelt.
Last~y, an evaluation was performed for the selected 90 MW Bradley Lake
Project to determine the economic effect of changes in the feasibility stage
values for plant capital cost and average annual energy. After selection of
the 90 MW plant as the preferred capacity, detailed reviews of the plant
capital cost and average annual energy were performed by SWEC. As a result
1-16
of these reviews, the 90 MW plant capital cost was increased from $287.95
million to $300 million (1983 dollars including IDC), and the average annual
energy was increased from 345.4 GWH to 369.2 GWH. The 90 MW Bradley Lake
Project was reevaluated with these revised parameters under the Reference
Case load and fossil fuel price projections. The resulting present worth
costs (without Susitna) are as follows:
Present Worth, Millions 1983$
Savings Due to
Total Cost Bradley Lake
Base Case
90 MW Bradley Lake Project
5,832
5,455 377
As before, significant life-cycle savings result by using the selected 90 MW
Project in place of thermal generation alternatives for the Railbelt. The
selected 90 MW Project present worth cost is slightly lower than the;: value
associated with the feasibility stage plant, indicating that the increase in
capital cost is more than offset by benefits from the additional average
annual energy generated.
1. 12 FINDINGS AND RECOMMENDATIONS
Findings
The major aspects of developing the Bradley Lake site have been reviewed and
analyzed during this Feasibility Study. Conceptual design drawings have been
developed, alternative designs evaluated, construction costs estimated, and
the cost benefits of the three sizes of plants measured against alternative
types of generation. The results are reflected in the Recommended Plan. The
main findings are:
o The 60 MW, 90 MW, and 135 MW Pelton plants produce about the same average
annual energy, however, based on given load growth criteria, the 90 MW
plant is the most economical choice for developing the project.
1-:17
o The level Bradley Lake should be ·raised some 100 feet for added
benefits. Of the three maximum operating levels of the lake studied,
elevation 1170, 1180 and 1190, elevation 1180 was judged as the most
attractive.
o The most economical method to raise the level of Bradley Lake, is to
construct a concrete faced rockfill dam at the mouth of the lake and a
separate concrete ogee spillway at the right abutment.
o The power tunnel between Bradley Lake and the powerhouse can be bored
with a tunnel boring machine and/or conventional techniques which are
both technically feasible.
o Geotechnical considerations and findings show that acceptable foundation
and rock conditions exist at the locations of proposed project structures.
o The Pelton type turbine is preferred, mainly because of lower project
costs and the ability to follow greater fluctuations of peak power
loadings.
o An above ground powerhouse containing two generating units is preferred.
o The Middle Fork Diversion, used to divert seasonal flows into Bradley
Lake, is economically viable.
o Diversion for construction is technically feasible by a tunnel through
the right·abutment. Also, this tunnel can be converted into a permanent
outlet facility for downstream releases after construction.
o Land and land rights should pose no problems for construction of the
Bradley Lake Hydroelectric Project, as the majority of the project lands
were withdrawn in 1966 by Public Land order 3953 for the purposes of
development of the project. The withdrawal included about 40,000 acres
of Federal lands, whereas the project reservoir and structures require
approximately 4,500 acres with the remaining used for protection of the
watershed.
1-18
o The power plant output should be transmitted over a two circuit 115 kV
transmission line system with each line capable of handling the full
plant load. The selected 90 MW plant will not require another
transmission line between Soldotna and Anchorage as the existing 115 kV
line is capable of providing reserve sharing and economy interchange
between Anchorage and the Kenai Peninsula.
o The project can be developed in a manner that is responsive to
environment and impacts and known environmental concerns can be resolved
o The project cost estimates and the economic evaluation shows that:
o The Recommended Plan of the 90 MW can be developed at an estimated
overnight cost of $283,019,000, July 1983 price base.
o Economic evaluations of th~ 90 MW installation shows that the
Bradley Lake is economically beneficial for the Railbelt, both with
and without the presence of the proposed Susitna Hydroelectric
Project.
Recommendations
Based on the above findings it is recommended that:
o The project be developed using two Pelton hydraulic turbines to generate
a minimum of 90 MW, a concrete faced rockfill dam, a machine bored
concrete lined tunnel, the Middle Fork diversion and a two circuit
parallel transmission line.
o To avoid lengthly delays and subsequent potential cost increases, the
Power Authority should proceed with the Bradley Lake Project by
initiating the preparation of a FERG License Application.
o Unresolved environmental concerns and issues should be addressed during
the early stages of FERG License Application preparation.
1-19
TECHNICAL DATA
BRADLEY LAKE HYDROELECTRIC PROJECT
(Based on Recommended Plan of Development)
PROJECT FEATURES:
Reservoir
Elevation of existing lake surface, feet
Elevation of normal full pool water surface, feet
Elevation at minimum operating pool, feet
Elevation at emergency drawdown, feet
Elevation at Spillway Design Flood, feet
Area of reservoir at full pool, acres
Area of reservoir at minimum pool, acres
Initial active storage capacity, acre-feet
. M<iitional storge tor emergency generation, acre-feet
Bradley Lake Dam
Sheet 1 of 3
1,080
1,180
1,080
1,060
1,190.6
3,820
1,568
284,150
31,200
Type
Length, feet
Height of maximum section, feet
Top of dam elevation, feet
Concrete Faced Rock Fill
605
125
1,190
Bradley Lake Spillway
Spillway type
Spillway crest elevation, feet
Gross spillway length, feet
Spillway crest length, feet
Power Tunnel
Length, (concrete & steel lined), feet
Nominal Diameter (lined) , feet
Intake invert elevation, feet
Unga ted Ogee
1,180
230
165
TABLE
18,820
11
1,030
1.3-1
Liner
TECHNICAL DATA
BRADLEY LAKE HYDROELECTRIC PROJECT
(Based on Recommended Plan of Development)
Steel liner & Penstock
Type
Outside Diameter, feet
Length, feet
Material
Min. Yield Strength, psi
Penstock
Length, feet
Outside diameter at portal feet
Material
Min. Yield Strength, psi
Diameter of Bifurcation, feet
Powerhouse
Plant, KVA (Nameplate rating)
Number of Units
Type of Turbine
Turbine Rating at 1130 feet rated net head, Hp
Rating of Generating Unit, KVA (nameplate)
Maximum Operating Pool Elevation, feet
Minimum Operating Pool Elevation, feet
Maximum Tailwater Elevation, feet
Minimum Tailwater Elevation, feet
Centerline Turbine Runner Elevation, feet
Bottom of Turbine Chamber, feet
Unit Spacing, feet
Project Generation
Sheet 2 of 3
Embedded
11
2,400
AS'IM A710.
85,000
135
11
AS'IM A7l0
85,000
8.0
112, 6Q_O
2
Pelton
73,900
56,300
1,180
1,080
11.4
-6.0
15.0
-6.0
43.0
Flow regime is Bradley River, Middle Fork diversion, and releases for
fish habitat.
Yearly firm energy
Average annual energy
TABLE
334.1 GWH
369.2 GWH
1.3-1
Sheet 3 of 3
TECHNICAL DATA
BRADLEY LAKE HYDROELECTRIC PROJECT
(Based on Recommended Plan of Development)
Switchyard and Transformers
Type
Generator Bus
Type
Rating
Enclosure
In powerhouse
Outside powerhouse
Main transformers
Number
Rating
Circuit Breaker
Number
Type
Rating
Line number
Type
Voltage, kilovolts
Transmission Line
Conductor size, KCM, ACSR; "Dove"
Overall length overhead section, miles
Conventional
Copper conductor
Non-segregated
Phase
15000 volts; 3000 amps
Continuous; 80,000 amps
Momentary
Ventilated
Enclosed; weatherproof
2
33~ 8/4-5/56. 3 MVA
Three phase, 60 Hz
3
Oil
1200 amps
2 parallel
H-Frame
Wood Pole
115
556.5
20
Tailwater Data For Powerhouse
BEAR COVE BEAR COVE BRADLEY
MLLW MSL PROJECT
TIDES DATUM DATUM DATUM --
HT 25.00 15.39 11.37
MHHW 18.17 8.56 4.78
MHW 17.60 7-99 + 3.87
MSL 9.61 o.oo 4.02
MLW 1.61 -8.00 -12.02
MLLW o.oo -9.61 -13.63
LT -6.00 -15.61 -19.63
Unless otherwise noted, all elevations given are based on project datum.
"----------TABLE 1.3-1
2
INTRODUCTION
2. INTRODUCTION
2. 1 PROJECT LOCATION AND SETTING
The proposed Bradley Lake Hydroelectric Power Project would be located on
the Kenai Peninsula, about 105 miles south of Anchorage, Alaska. Bradley
Lake, with a natural elevation of about 1080 feet, is located in the Kenai
Mountain range. Geographically, Bradley Lake is about 27 miles northeast
of Homer, Alaska. Access to the project site is limited at present to boat
at high tide, or helicopter.
The Kenai Hountains, above an elevation of 3, 000 feet, have been eroded by
glaciers and form rather rough terrain characterized by cirques, horns, and
deep U-shaped valleys. Above this elevation, the mountains are covered
principally by glaciers, except for scattered peaks which protrude above
the ice. Valley glaciers are present in the upper reaches of most valleys
and in some ~ases are a major source of water for rivers,. lakes and streams
on the lower Kenai Mountain slopes .
The Bradley Lake area, with steep sloped reliefs reaching 4,300 feet, is
dominated by the lake and gorge of the Bradley River. The lake is about 3
miles long and varies from 0. 2 mile to about 1. 2 miles in width. The
maximum depth of the lake is about 268 feet. Except for the southeast
portion of the lake, where Kachemak Creek and the Nuka Glacier flow into
the lake, the land rises abruptly from the lake shore, with some portions
nearly vertical.
Bradley Lake inflow is derived principally from rainfall and snow melt with
some contribution from glacier melt of the Kachemak and Nuka glaciers.
Outflow from the lake flows northwestward into the Bradley River. The
river flows in a gorge which is between 725 feet and 1,200 feet deep and up
to 750 feet wide. The river channel passes through several very narrow
reaches, which include rapids and waterfalls, before reaching the
floodplain and tidal flats of Kachemak Bay.
2-1
The project site area is considered to be located in a major earthquake
region, with recorded earthquake magnitudes of 6. 0 -6. 9 on the Richter
Scale. Several historical earthquakes have occurred within a radius of 500
miles of Bradley Lake.
The area of the Kenai Peninsula is strongly influenced by the maritime
climate that prevails along coastal regions adjacent to the Gulf of
Alaska. Cool summers and moderate winter temperatures prevail, with
occasional winter intrusions of cold Arctic air masses. Fog, rain, and
clouds occur frequently in the area and gusty, turbulent winds are common
in the upper basin and near Kachemak Bay. Precipitation is light during
late winter and early spring, and increases to maximum amounts from August
through December, varying with geographic location and elevation.
Precipitation in the lower elevations is predominately rain with upper
elevations receiving snow. The project area is moderately forested with
white spruce, birch, aspen, and willow along the areas adjacent to Kachemak
Bay. Areas above an elevation of about 1,000 feet have very _little growth
and are essentially barren. The entire Kenai Peninsula area has been
classified as being generally free from permafrost.
The waters of Kachemak Bay are subject to tidal fluctuations of up to about
23 feet. Although some ice forms, the bay is essentially open. Bradley
Lake surface waters begin to freeze by early winter and ice cover stays on
the lake till late April or early May. Ice thickness varies as a mixture
of slush and solid ice, with an estimated solid ice thickness of about 28
inches.
The Bradley Lake area encompasses several fish and wildlife habitat areas.
The area has a high diversity of species and the Fox River Flats,
comprising the estuarine areas of the Fox, Sheep, and Bradley Rivers, at
the head of Kachemak Bay, has been designated as "critical habitat area".
2. 2 BACKGROUND AND PAST STUDIES
Many studies and evaluations have been performed over the years to
determine the technical and economic feasibility of developing the Bradley
Lake drainage sy_stem into a hydroelectric power project. Most of this work
2-2
was conducted by the Corps of Engineers (COE) and various
architect/engineering firms subcontracting to the COE. The bibliography
contained in this report provides a listing of the studies previously
performed on the Bradley Lake development.
Study of the Bradley Lake Project was initially authorized by the Federal
Government in 1962. Engineering, design, economic and other studies were
undertaken by the COE. The results of the COE findings and recommendations
are presented in a series of Design Memoranda, culminating with the
issuance of the General Design Memorandum No. 2 in February, 1982. This
later memorandum was issued in two volumes, Volume 1, "Main Report" and
Volume 2, "Appendices". The COE studies and findings concluded that the
Bradley Lake Project is technically feasible, and economically attractive.
The COE recommended the development of a project with 135 MW of capacity,
utilizing three Francis type hydraulic turbine units to generate up :to an
average annual energy of about 356 GWH. This installation was pref~,rred
over two other alternatives studied, namely a 60 t·fW and a 90 t·fW plant.
Substantial work was accomplished by the COE and its subcontracting firms
in collecting base line data relating to both environmental and technical
aspects of the recommended project. The environmental efforts resulted in
the preparation and issuance of a Final Environmental Impact Statement,
dated August, 1982. The COE had reached the milestone for initiating
definitive engineering-design; however, due to lack of funding, work on the
project could not continue to completion.
The involvement of the State of Alaska with the project commenced in 1981
at which time the Alaska legislature appropriated funds to initiate
construction of the project. Later, in 1982, the state legislature
appropriated additional funds, and authorized the Alaska Power Authority to
assume the development of the project. The Power Authority's Board of
Directors, in October 1982, authorized the design and construction of the
project by the Power Authority. Federal legislation deauthorizing the
project was passed in December, 1982.
Additional studies were performed by the Power Authority on costs, project
economic and other factors to further assess project feasibility. Key
2.-3
studies included cost estimates by the firm of Ebasco Services, Inc., and
project-economic assessments by the firm of R.W. Beck and Associates, Inc ..
2. 3 THE BRADLEY LAKE FEASIBILITY STUDY
Shortly after assuming the responsibility for the Bradley Lake Project, the
Power Authority issued a Request for Proposal (RFP) -APA-83-R-027, on
November, 1982, soliciting professional services for the engineering and
design work of the Bradley Lake development essentially as recommended by
the COE. Stone & Webster Engineering Corporation (SWEC) was selected and
this selection was approved by the Power Authority Board of Directors in
March 1983. The SWEC contract with the Power Authority required that,
prior to the initiation of definitive engineering-design work, preliminary
conceptual engineering-design studies be performed to re-evaluate the
technical and economic feasibility of the project. These efforts were
designated as Phase I -Feasibility Study and had the following objectives:
o As~ertain the technical feasibility of the project in sufficient detail
to eliminate major uncertainties.
o Re-evaluate the previously studied installations with respect to
capacity, energy and costs, and select the most attractive plant and
scheme of development.
o Determine the role that a Bradley Lake power development will have in
the overall energy plans of the Power Authority and evaluate its
economic merits in comparison to alternative generation mixes.
The study was to consider the impact of the project on: (1) the entire
Railbelt electrification plan, (2) its affect on the Anchorage-Kenai
Peninsula area, and (3) its implication on the Kenai Peninsula alone. The
study was to consider "with or without Susitna" project scenario and
various mixes of fossil fueled generating plants and transmission line
arrangements.
The scope of services of the study included resource assessment, field
surveys, and hydrologic, glacier trending, geotechnical, environmental,
2-4
engineering-design, cost, and economic evaluation studies necessary to
assess project feasibility. A specific objective of the study is to select
a preferred installation that best responds to the energy needs of the area
or areas to be served.
This report documents and summarizes the Phase I Feasibility Study efforts.
2. 4 STUDY METHODOLOGY AND APPROACH
The Bradley Lake Feasibility Study included the following Scope of Work:
o Data Collection Compiled data developed by others which are
applicable to the study and distribute these data.
o Review of Data -Reviewed the information compiled, noted applicable
areas and communicated and exchanged this information with pr9ject
pers<?nnel.
o Technical Review Board -The project Technical Review Board contributed
to conceptual development and assessed applicability of project
concepts.
o Conceptual Design of Common Items -Conceptualized engineering of items
that are common to the 60, 90 and 135 MW installations, including
preparation of preliminary drawings.
o Conceptual design of 60, 90 and 135 MW Plants -Engineering-design
efforts for the conceptual development of powerplants using two
turbine-generator units for each size of plant. Each installation were
developed for Francis type turbine units and Pelton type turbine units
and conceptual arrangement drawings were prepared for costing efforts.
o Evaluation of Construction Facilities -Performed technical evaluations
and determined costs of key facilities required to support construction
activities as well as those facilities needed for permanent plant
operation of the project.
2-5
0 Quantity Development and Construction Cost Performed
take-off of the various installations and alternatives.
cost estimates for comparative assessments and for use in
evaluation studies.
quantity
Developed
economic
o Power Study and Economic Analysis Approach -Considered modelling of
base and alternative generation-transmission line power development
scenarios to explore the role and economic feasibility of Bradley Lake
on the Railbelt area, the Anchorage-Kenai Peninsula and on the Kenai
Peninsula alone.
o Geotechnical Investigations -Collected geotechnical data and performed
field explorations to support project evaluation.
0 Instream Flow Studies Collected technical . and scientific data
relating to affected fish habitat areas of the Bradley River.
o Transmission Lines -Developed conceptual engineering/design and cost
estimates for transmission line systems associated with project
development.
o Selection of Preferred Plan -Evaluation of data and study results to
select a recommended installation.
0 Feasibility Report Prepared this report to present findings,
conclusions, and recommendations.
All of the above activities were pursued to completion. The data
collection and review process resulted in a thorough understanding of
previous work. The review process identified areas requiring further
investigation. Previously identified areas of concern were evaluated and
feasible solutions pursued. Conceptual engineering and design efforts
permitted the assessment of previous concepts and the implementation of new
innovative ideas for project development. Geotechnical work resolved areas
of major uncertainties; specifically in the development of the power tunnel
and dam. Hydrologic and instream flow studies substantiated the energy
2-6
capabilities of the development. Cost and economic evaluations confirmed
the feasibility of the Bradley Lake Hydroelectric project.
The goal of the above described feasibility study was to arrive at a
selection of the most attractive plant size and scheme of development.
This was achieved, and Stone and Webster recommended a 90 MW plant, with
two Pel ton type hydraulic turbines, be the selected scheme of development
for the Bradley Lake Hydroelectric Project. The Overnight estimated cost
·of this selected scheme is $283,019,000. The scheme of development
includes a concrete faced rockfill dam, a machine bored tunnel, the Middle
Fork diversion and a scheme for augmenting flows for aquatic habitat. The
recommended scheme does not require a Soldotna/Anchorage transmission line
as the existing 115 kV line is capable of providing reserve sharing and
economy interchange between Anchorage and the Kenai Peninsula for the 90 ~M
Bradley Lake installation.
2.5 STT-~Y PARTICIPANTS
Assisting SWEC in studying the feasibility of the Bradley Lake Project were
the following Alaskan firms who contributed to the study work in the areas
indicated:
o Woodward-Clyde Consultants -Performance of instream flow studies and
evaluation of aquatic habitat flow requirements.
o Shannon & Wilson, Inc. -Geotechnical data collection and analyses.
o R&M Consultants, Inc. -Performance of engineering-design studies and
cost development relating to the various construction and civil
facilities of the project.
o Dryden & LaRue Consulting Engineers -Engineering and design studies
and cost development of electrical transmission lines.
2-7
2.6 REPORT ORGANIZATION
This report is arranged under the following main headings:
1. Executive Summary
2. Introduction
3. Recommended Plan
4. Alternatives Investigated
5. Technical Considerations
6. Engineering and Economic Evaluations
7. Detailed Project Description
8. Environmental Analysis
9 . · Land and Land Rights
10. Design and Construction Schedule
11. Cost Estimates
12. Power Studies and Economic Evaluation
13. Findings and Conclusions
14. Bibliography
In Section 1, the Executive Summary provides a synopsis of the engineering
and economic evaluation studies that led to the selection of the optimum
scheme of developing hydroelectric power at Bradley lake. Section 2
describes the background, location, setting, previous studies and the Stone
& Webster Feasibility Study Program on the Bradley Lake Hydroelectric
Project. Section 3 details the Recommended Plan and Sections 4 through 12
describe the technical, environmental and economic findings as well as the
cost estimates and proposed construction schedule for building the
project. Section 13 presents the conclusions and recommendations.
Reports prepared by SWEC and its subcontractors are included in the
appendices. Pertinent data collected for the feasibility study are listed
in the bibliography, Section 14, at the end of the main report.
2-8
3 . · RECOMMENDED PLAN
3.1 GENERAL
The recommended plan for development of the Bradley Lake Project uses water
stored at the lake and the effective pressure head between the lake and
Kachemak Bay to generate electric energy. A concrete faced rockfill dam is
proposed at the outlet of the lake to impound water and increase the
available generating head. Additional water is provided with the diversion
of natural flows from the Middle Fork drainage bas in to Bradley Lake.
Stored water is conveyed to the generating facilities through a concrete
and steel lined tunnel and a buried penstock power conduit. The power
generating facilities are housed within an above ground enclosed powerhouse
located at the eastern shoreline of Kachemak Bay. Two separate and
parallel transmission lines, each about 20 miles long, connect the project
to the transmission line to be constructed by Homer Electric Association.
Plates 1, 2 and 3 show the location, overall features, and general plan of
~he project, respectively.
3. 2 PRINCIPAL FEATURES OF RECOMMENDED PLAN
3. 2.1 Access Facilities
The prime access to the site during construction of the project and later
during project operation will be by water using an access channel and barge
basin located northwest of Sheep Point. Additional access will be provided
by an airstrip north of the powerhouse and helicopter pads located at key
areas within the Project as shown on Plate 4.
The access channel and barge basin areas, shown on Plate 5, are formed by
dredging to a bottom elevation -14. The access channel, basin and dock is
capable of accommodating seCj.-going barges and tugs. Barge movements based
upon a 10 feet draft could be accomplished on 99 percent of all high tides,
or on 49 percent of all hourly tidal stages. The barge basin will allow the
barges to rest on the bottom during the low tide cycle. The dock 200 feet
3-1
by 50 feet. A reciprocating off -loading ramp is provided for
roll-on-roll-off unloading operations. A small section of the basin will
allow sheltered anchorage for a limited number of small boats.
Access roads are provided to serve the project during construction and
permanent operation. Three road networks, as shown on Plate 4, have been
established. One network consists of a 2.5 mile, 28 feet wide, two lane
road and serves the airport, powerhouse, dock, staging area and lower
camp. The second network consists of a 5.7 mile, 28 feet wide, two lane
road that will connect the lower camp to the upper camp and continue on to
serve the dam area. The third network is a 1.4 mile long construction type
temporary access road that will allow access to the Martin River delta
borrow area. Fill-borrow sections of this temporary access are 18 feet
wide, one lane travelway while graded portions have a 28 foot wide, two
lane, travelway. A contemplated one lane road to the surge shaft area will
not be required under the recommended plan.
ln general the roads are cut and fill. Surfacing gravel material will come
from the Martin River borrow area. Culverts and bridges are provided as
required. A portion of the road between Sheep Point and the Powerhouse is
located in the tidal mud flats and will be used as a retention dike for the
disposal of dredged material from the access channel and barge basin.
Special rip-rap armor is provided along this section of access road for
wave protection and slope stability.
3.2.2 Dam and Spillway
A concrete faced rockfill dam with an ungated concrete gravity agee shaped
spillway is to be constructed at the outlet of Bradley Lake. These
structures will impound the natural inflows and allow raising the present
lake level by about 100 feet to elevation 1,180. The rockfill dam
structure occupies the main river channel near the lake and has a crest set
at elevation 1, 190 and a total top length of about 605 feet. The maximum
dam height above its foundation is about 125 feet. A plan and details of
the proposed dam are shown on Plates 7 and 8, respectively.
3-2
The rockfill material needed to construct the dam are quarried from a rock
knoll that is located near the left abutment, upstream of the proposed
dam. This excavation also facilitates the development of the intake
channel. Material excavated for the preparation of dam foundations and for
the spillway will be partially used in cofferdam development with the
excess material placed in suitable areas along the left bank or in the main
dam.
An upstream cofferdam is being provided to block off lake flows during the
construction of the main dam. The cofferdam is a rockfill embankment
structure with filter and impervious material dumped at its upstream face
to seal off water. The structure, which has a crest height at elevation
1,100 is located immediately at the iake outlet. Material for its
construction will come from the quarry area and from material removed for
the preparation of the main dam foundation area.
A similar type cofferdam structure is provided downstream to block off
water from entering the construction area during lake diversion. .This
structure is designed to be incorporated into the embankment of the main
dam.
The reservoir created behind the dam will impound an active storage of
about 284,150 acre-feet above a normal minimum operating pool at elevation
1,080. At the full normal operating pool of elevation 1,180, the reservoir
has a surface area of about 3,820 acres.
to elevation 1,060 for maintenance of
The reservoir can be drawn down
structures and for additional
emergency generation. The additional active storage gained is about 31,200
acre-feet.
Minimum and selective reservoir clearing is being considered, as necessary
for operation of the plant.
The ungated concrete gravity overflow spillway is located over the saddle
formation at the right abutment area of the lake outlet, Plates 7 and 9.
The spillway has an ogee set at elevation 1,180 with a crest length of 165
feet. The overall length of the spillway including its adjacent concrete
3-3
abutments is approximately 230 feet. The spillway is designed to pass the
routed Probable Maximum Flood under a discharge head of about 10 feet and
the routed standard Project Flood under a discharge head of about 5 feet.
3.2.3 Construction Diversion
Diversion of the natural outflow from Bradley Lake during the construction
of the main dam and other structures at the lake outlet will be
accomplished by a horseshoe shaped tunnel excavated through the right rock
abutment approximately 100 feet east of the lake outlet, Plate 7. The 22
foot diameter unlined tunnel will be 470 feet long and discharge into the
large natural pool downstream of the main dam. The intake portal will be
constructed of reinforced concrete with provisions for a steel bulkhead.
The tunnel invert will slope downstream on a hydraulically steep slope from
elevation 1, 078 at the inlet portal to elevation 1, 074 at the tunnel
outlet, Plate 10.
Construction of the tunnel will be by conventional drill and blast
techniques, with the initial heading advancing from the downstream end.
Steel sets installed at the portals will be embedded in concrete as
protection against the relatively high flow velocity when discharging the
design flood.
After the main dam and power tunnel intake are completed the steel bulkhead
gates will be installed in the intake portal and construction of the
permanent outlet facilities within the tunnel will be completed including
partial concrete lining of the downstream tunnel section.
3.2.4 Permanent Outlet Facilities
Permanent outlet facilities will be incorporated into the construction
diversion tunnel. The outlet facilities will serve as low level outlets,
and provide for emergency drawdown of the reservoir and for diversion of
fish habitat flows to the Bradley River.
The facility will consist of a concrete plug, 30 feet long, constructed
about 260 feet downstream of the portal, with two 3.5 feet high by 5.5 feet
3-4
wide conduits formed within the plug. Each conduit will be controlled by
two hydraulically operated slide gates. The two downstream gates will
control the outflow during normal operations and the two upstream gates
will serve as guard gates during emergencies. A hydraulic power unit and
suitable air-oil accumulator will be provided to operate the gates, Plate
10.
3. 2. 5 Intake Channel
Stored water is conveyed to the power tunnel intake structure through an
intake channel. The channel is about 50 feet wide and 360 feet long and is
located at the ·left bank area. The channel is excavated down to elevation
1, 030 and allows the reservoir to be drawn down to elevation 1, 060 for
maintenance of structures and for an additional 20 feet of active storage
for emergency generation. Rock traps are being provided along the channel
invert and in front of the intake structure to collect fallen and ice
carried rocks, Plates 7 and 11.
3. 2. 6 Intake Structure
An intake structure is located at the downstream end of the intake
channel. The intake is excavated in rock as an extension of the upper end
of the power tunnel. The excavation is suitably shaped and concrete lined
for proper hydraulic performance. Removable steel trash racks installed at
the inlet, preclude floating debris from entering the power conduit, Plate
12.
3.2. 7 Gate Shaft
A vertical gate shaft is being furnished along the power tunnel alignment.
The gate shaft is a concrete lined 22 feet circular shaft about 173 feet
high, Plate 12. Two hydraulically operated slide gates are being provided
to serve as emergency shut-off gates for flow shutdown and for unwatering
the tunnel for maintenance. One gate is considered active during such an
emergency while the second serves as a backup. The passive gate is used
for servicing the active gate. The gate shaft will be dry and provisions
3-5
are -made within the structure for in-place maintenance of the gates.
Access to the gate shaft is from the road serving the dam.
3 . 2 . 8 Power Conduit
The concrete lined power tunnel conduit is approximately 18,860 feet long,
and connects the intake structure to the turbine generating units. The
nominal tunnel flow diameter is 11 feet. Starting from the intake, the
power tunnel consists of a 950 feet long horizontal tunnel that connects to
a 810 feet long shaft, inclined at 55° from the horizontal. A 38 feet long
bend is provided at each end of the shaft. The power tunnel continues for
about 14,450 feet to the beginning of a concrete and steel lined tunnel
section that is about 2400 feet long and extends to the tunnel portal near
the powerhouse. An exposed, girder reinforced, steel "roll-out" penstock
section is provided near the portal. From this point on, the power conduit
consists of a 135 feet long steel penstock section that bifurcates into two
flow_ lines, one for each of the two turbine generating units. The penstock
section is encased in concrete and buried below grade for most of its
length. A surge shaft w·ill not be required for the power tunnel conduit.
Material excavated from the tunnel will be used either for airfield fill or
for upgrading access road surfaces. The arrangement of the power conduit
is shown in Plate 12.
3.2.9 Powerhouse and Tailrace
The powerhouse is located just above sea level on the northeast shore of
Kachemak Bay. The powerhouse will contain two Pelton turbine generating
units having a combined rating of 107 MW. Each unit is capable of
generating 45 MW at minimum head with a nominal operating speed of 300
rpm. The powerhouse, penstock, bifurcation, and power tunnel portal are
situated on an excavated rock bench at elevation 40. The powerhouse is
constructed of reinforced concrete with an insulated steel superstructure.
The tailrace is an excavated trapezoidal, unlined channel approximately 100
feet long extending from the powerhouse into the tidal flats. The
discharge from the turbines will flow across the tidal flats to connect
with Kachemak Bay. Excavated material will be used in the construction of
a laydown area and a switchyard adjacent to the powerhouse excavation along
3-6
the shoreline of the tidal flats. Plates 13 and 14 show plans and details
of the powerhouse arrangements.
3.2.10 Substation and Transmission
The substation is located adjacent to the northeastern end of the
powerhouse., It is rated 115,000 volts, 3-phase, 60 HZ, and contains the
main power transformers, line and tie circuit breakers, disconnecting
switches, coupling capacitor voltage transformers, and line take-off
towers. Conventional, oil-filled, outdoor equipment is utilized for power
circuit breakers, and power transformers. The disconnecting switches are
manually-operated, vertical-break units. Each generator is connected to a
three-phase power transformer, power circuit breaker and then to a 115 kV
transmission line. Between the two outgoing lines there is a normally
closed power circuit breaker. This allows power in the Soldotna-Fritz
Creek transmission line to flow through the Bradley Lake substation. The
-.1'Jt
· substation is designed to transmit the full output ·of the Bradley -Lake .,..
Plant, during maintenance of or failure of one of the line breakers. Plate
15 shows the general plan of the substation.
Transmission of the power from the Bradley Lake plant is via two, parallel
115 kV transmission lines. These lines are constructed utilizing wood
pole, H-frame structures and aluminum conductors, steel reinforced (ASCR).
Each line is designed to transmit the full output of the plant, in the
event one line is lost. The Bradley Lake lines are connected to a 115 kV
transmission line which transmits power between Soldotna and Fritz Creek.
The connection to this line, at a location called Bradley Junction, is
about 20 miles from the power plant. A typical wood pole transmission line
structure and the Bradley Lake Junction arrangement are shown on Plate 15.
3. 2.11 Construction Camps
Two construction camps are planned to accommodate personnel during project
construction. The lower camp area is located on the right bank of Battle
Creek, approximately one mile southeast of Sheep Point. The upper camp is
located near the upper dam access road about one mile west of the Bradley
Lake outlet. The area is designed to accommodate 240 beds and the upper
3-7
camp 210 beds. Each camp will have housing, dining, recreation, offices,
utilities, sewer, and other support facilities. The lower camp area will
also be used as the site for the permanent housing facilities to be
constructed for the plant operation and maintenance personnel. The camps
will be operated by the contractor during the project construction and will
be sized to also provide facilities for visiting personnel,
Authority's Construction Manager and Engineering support
and the Power
staff. The
general location for these construction camps is shown on Plates 3 and 4.
3.2.12 Buildings, Grounds and Utilities
Permanent buildings and grounds will be limited to those required to
support operation and maintenance of the Project. These facilities are
located at the lower construction camp site area and consist of four
residences provided for supervisory and operations and maintenance
personnel and their families. In addition, a bunkhouse will be provided
for maintenance personnel in the event of major maintenance. The permanent
facilities will be totally selfcontained with water and sewage facilities,
electric service from the powerhouse station service system, and a standby
electric generator. The permanent facilities will also include a
warehouse, a fully equipped machine shop, and a storage yard each sized to
support anticipated project material, spare part storage, and maintenance
requirements.
The powerhouse and powerhouse substation will also be self-contained with
fire, water and sewage facilities, station service power service, a standby
electric generator, and station batteries for emergency power to critical
equipment and controls.
Microwave and other means of communications will be provided from Homer to
the powerhouse and other key project facilities.
3.2.13 Middle Fork Diversion
The Middle Fork Diversion is located approximately one mile northeast of
Bradley Lake in an adjacent basin, and diverts up to 450 cfs of water into
Bradley Lake during May through October. The diversion consists of a small
3-8
rockfill embankment dam and 1, 900 feet of 6 feet diameter steel flow line.
The rockfill darn is approximately 20 feet high and has a steel sheet pile
central cut-off wall. The dam will be constructed of material excavated
from the 30 feet wide, 12 feet deep, and 210 feet long chute spillway
located in the right abutment.
A 6 feet diameter steel pipe will be used initially for construction
diversion and later as a low level outlet to pass the natural winter flows
downstream into Middle Fork. An entrance sluice gate and manual operator
is provided for closure of the low level outlet. Also, a 6 feet diameter,
steel pipe is provided to serve as the main diversion conduit into Bradley
Lake. A closure sluice gate and manual operator is located at the pipe
entrance. The pipe is buried for its total length to allow animal passage
over the pipe and to preclude damage from snow creep and avalanche. The
entrance sluice gate· for the main diversion conduit will be fully opened
during May through October and closed from November through April.
The plan and profile of the Middle Fork diversion and details of the
recommended rockfill dam structure and its appurtenances are show:p. on
Plates 16 and 17~ respectively.
3-9
4
ALTERNATIVES
INVESTIGATED
4. ALTERNATIVES INVESTIGATED
4.1 GENERAL
A large number of alternatives were investigated during the study. In
addition, reviews were made of concepts developed under studies by the COE
and others. The alternatives studied in the selection of the preferred
plan are briefly discussed in this section and in greater detail in the
report section describing the specific features of the plan.
4.2 DAMS
The following types of dams were considered:
o Concrete gravity dam with a flip bucket spillway positioned at its
central monolith section.
o Concrete gravity dam with an ungated concrete gravity spillway in the
right abutment saddle.
o Concrete double curvature arch dam in the immediate vicinity of t!le
lake outlet.
o Roller compacted concrete gravity dam.
o Concrete faced rockfill dam.
Preliminary engineering evaluations and, when appropriate, engineering
analyses were conducted on the above dam types· to select the best two
alternatives for more in depth engineering and cost analyses. The two dam
types considered in depth were the concrete gravity dam and the recommended
concrete faced rockfill dam.
4. 3 SPILLWAYS
Due to the topographical and geologic features at the site, the only
practical locations for a spillway to handle the Design Floods would be
4-1
either the left or right abutments or a design incorporating the spillway
into the main dam at the lake outlet. The dam type and location also
affect the selection of the spillway location, type, and design details.
Side channel spillways were extensively studied by the COE in conjunction
with rockfill dams. The COE also investigated a spillway within the main
central section of a concrete gravity dam. The present study investigated
and recommends an ungated agee type spillway located in the right abutment
saddle.
Two types of spillways were investigated by the COE, an uncontrolled free
discharge agee shaped crest and a gated spillway. The gated spillway was
abandoned due to the higher capital and maintenance cost as well as
operational constraints. SWEC agrees with this conclusion and only
investigated the uncontrolled agee spillway.
4.4 CONSTRUCTION DIVERSIONS
The diversion concepts reviewed in this study considered major engineering
and cost factors affecting overall project development. These factors
included the impacts of alignment. and arrangement on the power tunnel,
intake structure, cofferdams, spillway, construction ease, and the
accessibility during and after construction. In addition, hydrologic,
hydraulic, and environmental factors were considered for the various
schemes studied.
Previous studies conducted by the COE and others were the basis for the
initial review. Several other diversion schemes were analyzed and
reviewed. These included tunnel arrangements through the right and left
abutments at the lake outlet, and a buried conduit through the main river
channel. Variations in each of these schemes were also reviewed. An
alignment through the right abutment with the diversion flow discharging
into the large stilling pool was judged the best in terms of the above
considerations and is the recommended concept.
4-2
4.5 INTAKES
Previously identified intake structures studied by the COE were reviewed
and, in addition two new intakes were investigated. These were:
o A bellmouth intake in combination with a channel excavated within the
cofferdammed area.
o A bellmouth intake in combination with a channel developed as part of
the quarrying operations required for the rockfill dam.
The latter of the two is the preferred concept.
4. 6 GATE STRUCTURES
Gate structures considered by previous studies were reviewed. The
preferred·gate structure, consisting of a concrete lined circular·shaft and
housing two hydraulically operated slide gates also was studied.
4. 7 POWER CONDUIT AND SURGE SHAFT
Three alternative power tunnel alignments, connecting the left bank of the
river channel to the powerhouse were investigated. The three power tunnel
alignments considered utilize a deeply set concrete lined tunnel and
eliminate the exposed penstock. Because of topographic relief, the surge
shaft location was fixed to that identified under previous studies.
4. 8 POWERHOUSE AND TAILRACE
The COE had previously investigated both above and below ground
powerhouses, and pressure and non-pressure tailraces for the below ground
powerhouse and concluded that an above ground arrangement would be most
economical. SWEC concurred with this COE finding and investigated only
above ground powerhouse arrangements. Conceptual powerhouse arrangements
were developed for Francis and Pelton types turbines for 60 MW, 90 MW, and
135 MW capacities. Two unit powerhouse arrangements were considered in the
4-3
powerhouse arrangements to take advantage of the resulting cost economy.
In all cases the powerhouse was located so that the tailrace arrangements
considered were founded on rock.
Variations considered for the Francis powerhouse included machines with and
without synchronous by-pass valves and a power tunnel with and without a
surge shaft.
4. 9 TRANSMISSION FACILITIES
A transmission line corridor other than that proposed by COE was studied
and is the recommended corridor discussed within this report. In addition,
two separate transmission lines that would connect the Kenai Peninsula to
Anchorage were evaluated.
4.10 CONSTRUCTION CAMPS
The COE had previously looked at several camp sizes with alternatives of
road and wat~)r access from Homer and concluded that a construction camp
alternative would be most economical. SWEC concurs and considered the use
of a single camp to be located near the mouth of Battle Creek and a two
camp scenario which has a lower camp near the mouth of Battle Creek and an
upper camp on the plateau west of Bradley Lake. Each camp considered would
provide services to support construction activities. Permanent project
buildings were investigated only in the lower camp site area.
4. 11 MIDDLE FORK DIVERSION
The COE had previously investigated a steel bin wall dam, concrete gravity
dam, and a timber buttress dam with buried or above ground steel diversion
pipes. SWEC concurs with the COE' s recommended buried steel d-iversion
pipe. To make the maximum use of material natural to the diversion site,
two additional dam types were considered: concrete faced rockfill dam and
a rockfill dam .with a steel sheet pile cut-off. The concrete faced
rockfill alternative was selected for development along with a spillway
4-4
excavated in right abutment. The steel sheet pile cut-off rockfill
alternative was developed with a side channel spillway located in the right
abutment.
4-5
5
TECHNICAL
CONSIDERATIONS
5. TECHNICAL CONSIDERATIONS
5.1 GENERAL
Two main areas of technical considerations are identified as having a major
impact on project feasibility. These are project geology and
hydrometeorology. The geologic conditions found at the project area
substantially control the engineering and economic feasibility of
structures such as the dam, tunnels and powerhouse. Hydrometeorologic
conditions relate primarily to the energy producing capability of the
project and also affect the engineering design and economics of the main
project structures. A good understanding of conditions and limitations
regarding these two technical aspects is important in the development of
engineering concepts and project economic evaluations.
A third but less critical technical consideration was identified during the
course of the study. This consideration relates to the horizontal and
vertical survey control which establish the physical interrelationships of
the project structures. This consideration was found to have a minimal
impact on project feasibility but it did point out the need for developing
an accurate horizontal and vertical survey control network for the project.
These technical considerations are discussed in greater detail below.
5 . 2 PROJECT GEOLOGY
This section outlines the current scope of investigations, geologic
conditions at the site, the seismotectonic setting of the site and seismic
design guidelines. The major portion of work in defining geologic
conditions was performed by Shannon & Wilson (S&W), Fairbanks, Alaska,
subcontractors to SWEC. Details of site geologic conditions are included
in their report, Appendix A of this report.
5. 2. 1 Scope of Investigations
Previous investigations of the site
subcontractors, and the U. S. Geological
5-1
by the COE,
Survey (USGS) ,
their various
acting at the
request of the COE, were available for study and use in the current
investigations. These previous studies were of sufficient detail to allow
the current program to focus on specific areas rather than the site area as
a whole. The scope of current investigations is as follows:
o Review of existing data accumulated by the COE, their subcontractors,
and the USGS. These reports are listed in the "Bibliography" section
at the end of this section of this report. This work was performed
jointly by SWEC and S&W personnel.
o Reconnaissance geologic mapping, including aerial photograph
interpretation, and field checks of previous work were conducted by
S&W, assisted by SWEC personnel. Work was concentrated at the dam
site, powerhouse site and, particularly, along the tunnel alignment.
Where necessary for overall understanding of conditions in the area,
selected off-site locations were visited.
o Four borings and one test pit were made by S&W. Three borings
recovered rock core; at the left abutment area of the dam and along the
tunnel alignment at its projected intersection with the Bradley River
and Bull Moose Faults. The fourth boring was made in soil in the
general location of the barge basin; both disturbed and undisturbed
samples were taken for laboratory testing. Results of these activities
are outlined in following sections describing the geology of individual
project facilities.
o Laboratory tests of soil samples from the boring in the barge basin
area were made by S&W and are outlined in Section 7.1.8.
o Laboratory tests of selected portions of rock core were made under the
direction of Dr. A. J. Hendron of the Technical Review Board, Atlas
Copco Jarva, Inc. and The Robbins Company. The results are presented
in tabular form in Section 7. 4. 5 .
o Petrographic examination of selected portions of rock was done by
SWEC. Results are included in Section 7.4.5.8.
5-2
o A final report, Bradley Lake Hydroelectric Power Project, Geotechnical
Studies; August, 1983, was prepared by S&W and is included as Appendix
A.
o SWEC Geotechnical personnel provided input to the feasibility level
design efforts detailed in this report.
5.2.2 Geologic Conditions
This section is divided into a brief synopsis of the regional geologic
setting and a more extensive outline of the general site geologic
conditions.
5. 2. 2. 1 Regional Geologic Setting
The portion of the Kenai Mountains in which the Bradley Lake Project -~rea
-is located is composed of mildly metamorphosed rocks of upper Mesozoic Age,
informally named the McHugh Complex. These rocks are thought to have been
deposited in deep water on the continental margin. The rocks have been
uplifted, deformed, and shaped by erosional processes. Accentuated by
glacial and colluvial influences, the local topography is dominated by
conspicuous lineaments that are surficial expressions of a complex network
of faults or major joint sets that are the result of the activity of the
seismic region in which the area lies.
The Kachemak and Nuka Glaciers, along with several smaller alpine glaciers,
feed meltwater into the Bradley-Lake drainage. The proposed reservoir will
reach to within approximately 1. 5 miles of the Nuka Glacier and 2. 5 miles
of the Kachemak Glacier. Although they do not have extensive rubble at
their termini, their meltwaters contain a significant amount of glacial
rock flour, which is responsible for the cloudy condition of the water in
Bradley Lake.
An expression of the primary tectonic influence on the project area is
found in the Gulf of Alaska, where, about 185 miles southeast of Bradley
Lake, the axis of the Aleutian Arch-Trench occurs sub-parallel to the
5-3
prevalent NE-SW strike of the prominent tectonic features found around
Bradley Lake and the surrounding region.
Immense compressional forces generated by the plate tectonics activity in
the Kenai Region have resulted in deformation of the upper crust materials
of the Kenai Peninsula in the form of folding, jointing and faulting. Of
the several major regional fault systems that express this deformation, two
faults are found in the vicinity of the Bradley Lake Hydroelectric Power
Project. The Eagle River Fault crosses through the southeastern portion of
Bradley Lake, and the Border Ranges Fault forms the northern front of the
Kenai Mountains and flanks the northwest portion of the project area
passing beneath the length of Kachemak Bay. Two other locally major faults
cross the proposed tunnel alignment, the Bradley River Fault and the Bull
Moose Fault. Like the Eagle River and Border Ranges Faults, the Bradley
River and Bull Moose Faults strike in the general NE-SW direction that is
characteristic of the regional tectonic grain, and they have been suggested
to be extensions -of the--Bo-rder Ranges Fault. Togertliei -with. several -other
randomly oriented faults, these lineaments create much of the topographic
features found in the Bradley Lake project area.
5.2.2.2 Site Geologic Conditions -General
The project area is underlain by weakly metamorphosed sedimentary strata of
the McHugh Complex. This bedrock is locally mantled by unconsolidated
glacial, alluvial, and colluvial deposits and, below tree line, is
generally obscured by vegetation and soil cover. The McHugh Complex in the
project area is comprised primarily of weakly metamorphosed graywacke,
argillite, and cherty argillite. Locally these rocks are intruded by
dacitic dikes.
The graywacke, argillite, and cherty argillite of the McHugh Complex have a
complex distribution as a result of their intense deformation and
structural juxtaposition. Recognizable bedding planes and marker beds are
generally absent or masked by tectonic foliation. Many contacts appear to
be tectonic rather than depositional, and individual lithologic units
commonly are discontinuous over short distances. Many of the thicker
lithologic units either pinch out or are truncated within a few hundred
5-4
feet along their trend, whereas the thinner units often can be traced no
more than a few feet to few tens of feet. Consequently, projection of
lithologic units and rockmass characteristics from surface exposures
laterally into areas where the rock is obscured and vertically into the
subsurface is necessarily speculative.
5.2.2.3 Lithologic Units
For the purpose of this evaluation, the bedrock has been subdivided into
five lithologic units based on their distinctive rockmass properties.
These units are graywacke, massive· argillite, foliated argillite, foliated
cherty argillite, and dacite intrusives. The sedimentary classifications
represent further subdivisions of the graywacke and argillite units
utilized in earlier studies. The general characteristics of these bedrock
units are discussed below.
The gray-..;acke is highly indurated, dark gray to dark greenish gray,· yery
fine to medium grained, weakly metamorphosed sandstone. Fine, irregular
quartz and calcite veins are locally common in the graywacke. The unit is
massive with little or no evidence of bedding except for lenses or detached
remnants of beds of foliated argillite and cherty argillite that locally
occur within the unit. The graywacke is relatively resistant to weathering
and generally underlies the more prominent hills in the project area.
Where exposed, the rock is fresh to slightly weathered and strong.
Moderately to widely spaced, partly opened to very tight joints are typical
on vertical exposures of the graywacke.
The massive argillite is a strongly indurated, dark gray to dark greenish
gray, weakly metamorphosed siltstone to very fine grained sandstone. It is
a fine-grained eq~ivalent of the graywacke and has similar rockmass
properties. Exposures of this unit are fresh to slightly weathered,
massive and typically have moderately to widely spaced joints.
A weakly metamorphosed tuff was identified in a thin section from a sample
taken from a location just northwest of hill 2070. Tuff was also
identified in a thin section of a sample of graywacke taken from a location
5-5
midway between hill 2070 and the surge tank. The COE classified a thin
section sample from their boring DH-11 as a "volcanic graywacke".
It is difficult to make any firm statement regarding the distribution of
the tuff because it can only be positively identified in thin section. It
appears to be present within both the graywacke and the massive argillite.
Twenty-two thin sections of various rock types, many selected because of
their anomalous megascopic appearance, were examined with only two samples
identified as tuff, and only two field occurrences were noted. It is
likely that it is a minor component of the overall rock mass. Thin section
analysis (see Figure 7 .4-7) indicates that it was deposited in water and
could simply be considered a sub-type of the graywacke, that is, a
"volcanic graywacke" as classified by the COE.
The foliated argillite and foliated cherty argillite are differentiated
solely on the abundance of chert within the rock. For this evaluation we
have considered the argillite to be 11 chertyn if interlayered.and lenticular
chert exceeds about 10 percent of the outcrop. The argillite is a dark
gray to black, weakly metamorphosed siltstone and very fine sandstone.
Chert occurs throughout the rock (in various percentages) typically as
discontinuous layers and elongated nodules. Foliation is predominantly a
shear foliation that has developed along the regional structural trend.
Jointing is not frequently expressed in outcrops of the foliated argillite
but where present the joints are typically widely to very widely spaced and
very tight. Outcrops of the foliated argillite are fresh to slightly
weathered.
Two dacite dikes were observed in the map area. One is known from a single
small outcrop of the exit portal, whereas the other is exposed to the east
near the middle of the tunnel alignment. The eastern dike trends
northeasterly to easterly across the regional structural trend, cutting
across both graywacke and argillite units. It is about 30 to SO feet wide
and can be traced to the northeast of the tunnel alignment where it dips
nearly vertically. The dacite is a light greenish gray, porphyritic rock,
is typically slightly weathered in outcrop, and appears to be slightly more
resistant to erosion than the units it intruded. It is a massive rock with
S-6
widely spaced, very tight joints. Its strength and other rockmass
properties appear to be similar to the massive argillite and graywacke.
Overburden ranges from a few tenths of a foot to 15 or more feet thick and
consists of sands and silts covered with a thick mat of organic, mossy
material. In some cases the organic material is the only covering.
The unconsolidated sediments in the Bradley Lake area consist of glacial
outwash and till, river and tidal flat deposits, and talus rubble. These·
sediments are dominated by clasts of graywacke and argillite which vary
depending on the composition of the source area. The tills and talus
deposits are composed of gravel to boulder size clasts of subangular to
angular graywacke and flaky gravel to cobble size argillite. These clasts
are in a matrix of gravel, sand, and silt. Graywacke dominates the coarse
fraction of these deposits, while the argillite appears to dominate the
fine gravel and sand-size fraction.
5. 2. 2. 4 Structure
The most prominent structural elements in the project area are the
pervasive, closely-spaced shear foliation in the argillites, and the
complex structural distribution of bedrock units. The area is complexly
deformed by the pervasive shearing, by two major fault zones, and by
numerous smaller faults in a variety or orientations. The significance of
folding in the project area is not apparent because; a) well-defined marker
horizons and bedding are lacking, b) vegetative cover obscures much of the
rock, and c) the bedrock units are complexly distributed.
The Bradley River and Bull Moose faults are the most significant faults in
the project area. These faults zones are high-angle structures that trend
N5°E to N20°E and extend for at least a few miles outside the project
area. Several smaller high-angle faults and a few low-angle faults have
also been identified in this and previous studies. The high-angle faults
tend to fall into two general sets: those subparallel to the Bradley River
and Bull Moose .fault zones and those at about 90° to these larger
structures. Only a few minor low-angle faults have been noted.
5-7
,
Jointing is present in all the rocks in the area although it is generally
best developed in the graywacke. Joint orientations are highly variable.
Joint surfaces are generally relatively smooth, and range from very tight
to open cracks about 2 inches wide. Joint spacing is highly variable,
ranging from a few inches in local areas to several tens of feet in other
areas. Generally at least three joint sets at high angles to one another
can be found, resulting in a blocky rockmass.
A number of well developed linear topographic depressions cross the project
area. A few of the most pronounced and continuous of these lineaments are
recognized as faults, but the origins of many of the others are not readily
apparent. Most of the lineaments are probably the surface expression of
either faults or series of closely spaced joints. Rock exposures along the
lineaments are commonly absent, and colluvial or glacial deposits obscure
the evidence needed to determine the nature of these features.
5. 2. 3 Seismotectonic Setting
The primary cause of seismic activity in southern Alaska, including the
site area, is the stress imposed on the region by the relative motion of
the Pacific and the North American lithospheric plates at their common
boundary. The Pacific plate is moving northward relative to the North
American plate at a rate of about 6cm/yr. causing the underthrusting of the
Pacific plate. This underthrusting results primarily in compressional
deformation which causes folds, high-angle reverse faults, and thrust
faults to develop in the overlying crust.
The boundary between the plates where the underthrusting occurs is a
northwestward-dipping megathrust fault or subduction zone. The Aleutian
Trench marks the surface expression of this subduction zone and is located
on the ocean floor approximately 185 miles south of Bradley Lake. The
orientation of the subduction zone is inferred along a broad inclined band
of seismicity, referred to as the Benioff Zone, that dips northwest from
the Aleutian Trench, and is approximately 30 miles beneath the Bradley Lake
Site. Historically (1899 to date), eight earthquakes ranging between 7.4
and 8.5 Richter magnitude have occurred within 500 mi of the site.
5-8
12eat earthquakes (surface wave magnitude M 8 or greater) and large s
earthquakes (greater than M 7) have occurred historically throughout the s
region and can be expected to occur in the future.
Bradley Lake is situated on the overriding crustal block above the
subduction zone and between the Castle Mountain fault to the north and the
Patton Bay-Hanning faults to the southeast on Montague Island; all of these
faults have documented Holocene or historic surface ruptures. Because of
the active tectonic environment, activity is probable on other faults, such
as those found near or on the project site, which are also located in the
overriding crustal block and between the known active faults mentioned
above.
Two faults of regional extent occur at or near the site. The Border Ranges
Fault trends southwest beneath Kachemak Bay and the Eagle River Fault
crosses the southeastern portion of Bradley Lake at about the same trend.
\fuile no direct evidence or recent activity along these faults is known in
the site area, recently-defined data indicates recent activity on the Eagle
River Fault near Eklutna (125 mi NE of the site.) Given the tectonic
setting, it is reasonable to consider these faults potentially active.
In addition to the nearby regional faults, the site is crossed by two large
local faults, informally called the Bradley River Fault and the Bu~l Moose
Fault, and a number of probable smaller faults. The dominant trend is
northeasterly, paralleling the regional trend. The larger local faults,
particularly the Bradley River, are probably capable of independent
earthquake generation while any of the local faults could probably move in
sympathetic response to earthquakes generated by the regional faults.
It is therefore concluded that the site will probably experience at least
one moderate to large earthquake during the life of the proposed project.
The possibility of ground rupture exists but is much less subject to
prediction.
5 . 2. 4 Seismic Design
Based on previous studies and evaluations, supplemented by data and
considerations of this study, it is recommended that design maximum
5-9
earthquakes include a magnitude M 8.5 at 30km directly below the site and s
a magnitude M 7.5 on either the Border Ranges or Eagle River Fault at s
their closest approach to the site (less than 3km or 1. 8 mi). Possible
ground displacement is addressed in the final portion of this section.
Seismic exposure analysis, for a 100 year duration, for the site yields the
results tabulated below:
Exceedance Probability
50%
30%
10%
Maximum Horizontal Acceleration
0.37g
0.43g
0.58g
The controlling feature for this evaluation is the Aleutian Megathrust; in
its absence, acceleration levels would be reduced about 0.10 to 0.16g.
The values given above are considered to be as accurate as available data
allows. It m~st be recognized that historical data, except for very large
events, is sparse beyond about 100 years ago and instrumental data is
available for less than the past 75 years. Recommendations for probable
design acceleration values, given below, are based on general economic
considerations for the project and on the consideration that seismic
failure of even a major project facility would not result in a
life-threatening situation for any existing or projected population. All
major project facilities will be founded on or excavated in rock and design
acceleration values given below-are for horizontal acceleration in rock.
o Dam -0. 75g. Loss of the dam for the operational project would mean
temporary loss of the project and a major reconstruction expenditure.
However, by the very nature of the dam type selected, although it might
be damaged and leak, the dam would still remain in place and retain the
reservoir impoundment. The acceleration of 0. 75g corresponds to an M s
7.5 shallow crystal event with a recurrence probability of less than
10% in 100 years. This envelopes the more probable megathrust
5-10
event of M 8.5 s (approx. 0 .55g) with a 100 -year recurrence
probabilility of 10%. This is a relatively short significant duration
event (25 sec) and, as such, has less effect on massive structures such
as a dam. Current studies at the dam site have not revealed any
structures with potential for ground displacement.
o Intake Structure/Gate Shaft -0. 75g. These structures are considered
to be critical installations with respect to seismic shock resistance.
Seismically-induced damage to the intake channel (rockfall) or the dam
(leakage) would not prevent water from entering the power shaft/tunnel
system should the closure gate become inoperative. The
diversion/low-level outlet facilities are at an elevation above that of
the power tunnel intake and could not be used to lower the water level
below that of the intake. Reconstruction under such conditions could
be costly. A design level of 0. 75g represents a conservative value,
since it is based on the postulated shallow crustal fault event.
However, since the gate shaft and intake structure integrity are
significant during and after a major seismic event and represent a
moderate expenditure, in comparison to overall cost, it is recommended
that the maximum acceleration value be considered in final design for
these structures.
o Power Tunnel, including Steel Liner/Shafts No acceleration value
assigned. Fully embedded installations tend to react in concert with
the surrounding rock mass, unless actual rupture and displacement of
the rock mass occurs. It has been assumed that the Bradley River and
Bull Moose Faults are capable of independent earthquake generation,
implying surface and subsurface rupture potential, and are also capable
of rupture in response to events on adjacent, larger faults. Thus, the
largest potential displacements, up to 300 em (10 feet) have been
postulated on these faults; the probability is very small for this
case. Smaller faults are not considered capable of independent
earthquake generation and any displacement on them would occur as a
response to forces produced by events on larger faults. The range of
potential displacement for minor faults is assessed as from 20 em (0.6
feet) to 100 em (3 feet). Should displacement occur, it is anticipated
5-11
The probability of this event is not to exceed about 120 em (4 feet).
in the range of about 2X10-4 for a 100 year interval. The most
probable event (in 100 years) has been es.timated at 4X10 -3 with a
displacement of only 20 em (0.6 feet).
It is considered to be impossible to design to withstand or accommodate
rock mass rupture. In the absence of safety-related considerations, it
is recommended that no consideration other than those consistent with
normal tunnel design be applied. There are undoubtedly a number of
minor faults which also intersect the tunnel facilities; no special
design features are necessary for reasons stated above. Should rupture
occur, provisions for access for repair equipment has been included in
the form of a roll-out section in the steel penstock, adjacent to the
powerhouse. A tunnel bypassing the offset section could then be driven.
o Powerhouse -not to exceed 0.35g. There is a 50% chance that the site
win experience horizontal bedrock acceleration up to about 0. 35-0. 4g
during a 100 year interval. This represents a commonly-accepted level
for an operating-basis earthquake. An earthquake design for 0. 35g,
using normally acceptable stresses and operating requirements commonly
results in the ability of the structure(s), equipment and systems to
safely sustain higher earthquake accelerations at increased but
0
acceptable stress levels and operating extremes. If a higher
recurrence factor is considered acceptable during final design, an
acceleration value less than 0. 35g could be utilized. The depth of
bedrock was the primary geotechnical concern at the powerhouse site. A
hand-dug test pit confirmed the presence of bedrock at shallow depths.
Also, faults, and even joint swarms, which have strong topographic
expression throughout the site area, were not found to occur at the
powerhouse site. If faulting is present, it is minor. Given the above
condition$, it is recommended that the powerhouse, and ancillary
facilities required .for continued operation, be designed for this level
of shock.
Other Project Facilities -not to exceed 0.35g. These include such
facilities as accommodations for operation personnel, barge access
5-12
channel and basin, shop, warehouse, oil and water storage tanks,
structures housing sluice and intake gate controls, and bridges. For
final design purposes, it may be desirable to evaluate the possible
costs of repairs as opposed to initial construction costs for various
levels of seismic design. Many structures of conventional design and
proper construction can withstand accelerations in the 0. 2-0.35 range
while sustaining only moderate, repairable damage. If a higher
recurrence factor is considered acceptable during final design, a
design value of less than 0. 35g could be utilized. Given a probable
recurrence interval of several tens of years, it may not prove economic
to design non-critical facilities to totally withstand the effects of
major seismic events. It is also considered that minor project
facilities cannot practicably be designed to accommodate ground
rupture. It should be noted that failures in soils such as those found
in and immediately adjacent to Kachemak Bay are practically unavoidable
at the peak accelerations considered for this site. Such failures
~~~;
Gould-result ci.n slope failures in the access-cha.."llel and barge "Qas in
side slopes, and differential settlement of the air strip. These are
possibilities which must be considered in evaluation of the project.
5.3 HYDROMETEOROLOGY
5.3.1 General
The COE conducted extensive studies of the hydrologic and climatologic
characteristics of the Bradley Lake drainage basin. The results of their
studies are contained in their "Design memorandum No. 1, Hydrology," dated
June 1981, and "General Design Memorandum No. 2, Volumes 1 and 2," dated
February 1982. In general, all data as reported therein, except as
described below, provided the basis for developing the criteria used in the
present study.
The following sections summarize the important hydrologic parameters
gathered by the COE and SWEC' s subcontractor R&M Consultants, Inc. (R&M),
and utilized in this study. Where appropriate, summaries are provided to
describe changes to the COE's baseline data or to indicate where additional
future data development and studies are required.
5-13
5. 3. 2 Basin Description
The Bradley Lake Project is located within the Kenai Mountains
approximately 27 miles northeast of Homer, Alaska. The project utilizes
water stored in Bradley Lake which is situated about 1, 080 feet above
Kachemak Bay in an ice-free subalpine valley.
The basin above the lake consists of rugged and precipitous rocky slopes
interspersed with various forms of low vegetation and other growth. Higher
elevations are characterized by barren slopes with most of the land
features carved from the various glaciers within the basin. The Nuka and
Kachemak glaciers are the two largest glaciers providing runoff into
Bradley Lake. The drainage area above the lake outlet is 56.1 square miles
of which approximately 36 percent is covered with glaciers.
The Middle Fork diversion facility which will divert streamflow into a
tributary of Bradley Lake is located about a mile north of Bradley Lake.
The physiographic features of the basin are similar to the Bradley Lake
basin. The drainage area above the point of diversion is 10.1 square miles
with about 29 percent of the basin covered by glaciers and permanent
snowfields.
5. 3. 3 Climatology
5.3.3.1 General
The Bradley Lake basin is influenced by a maritime climate with associated
cool summer and ~moderate winter temperatures. Average annual temperature
has been estimated as 35°F. Fog, rain, and clouds are characteristic of
the basin with high winds frequently occurring.
Until 1980, no climatological records were available for the Bradley Lake
basin. Climatological data used in previous studies were developed through
correlation and regression analyses (Jf nearby basins on the Kenai
Peninsula. The following summarizes the results of these studies.
5-14
5. 3. 3. 2 Precipitation
Precipitation within the basin is greatest during the August through
December period with the smallest amounts occurring from January through
July. Most storms occur in the fall and early winter months and move in a
northeasterly direction from Kachemak Bay with the greatest amounts of
precipitation occurring in the higher elevations of the basin (1. 5 inches
per hour).
5 . 3 . 3 . 3 Snow
Snowfall ,is greatest in the upper elevations of the basin which contributes
materially to the volume of the larger glaciers producing runoff during the
summer months. First snows usually occur in October and extend through
early May with the heaviest accumulation occurring during December and
January.
5.3 .3 .4 Ice
Lake ice thickness of 17-28 inches was estimated by the COE and should have
minimal impact on project operation. Future studies should address the
effects of ice formations near the power conduit intake channel and its
impacts on wildlife migratory patterns in the upper reaches of the
reservoir. Ice and snow accumulations on project structures and the
transmission lines will also have to be addressed, however, these effects
are not insurmountable from a design standpoint. Ice accumulations within
Kachemak Bay and the areas subject to tidal influences are also expected to
be minimal with no affects on project operations or access.
5 . 3 . 3 . 5 Wind
Wind data at the site has been gathered since August 1979. The COE' s
analysis of the limited data indicates that highest winds occur from
October through April with several speeds exceeding 70 MPH during this
period. The 100 year return period speed has been estimated as 115 MPH in
the area with the predominate direction of the winds toward the northwest.
5-15
Wind speed, direction, duration, frequency, and seasonal distribution are
the major factors which will have to be reviewed in future studies as all
these factors could be significant in the design of the various project
structures. The wind criteria developed in the final design studies will
determine the spectrum of various wave characteristics to be expected in
Bradley Lake at the damsite by which final freeboard requirements for the
main dam will be set. More directly, wind characteristics will determine
the criteria to be used in final design of the transmission lines,
powerhouse superstructure, and other structures. The present study did not
analyze these wind characteristics in detail due to the limited amount of
data available. Should final engineering and design studies proceed in the
near future, the wind data developed at that time will be thoroughly
reviewed.
5.3.4 Hydrology
5.3.4.1 Runoff
The runoff response from precipitation in the Bradley Lake watershed is
influenced greatly by the geologic conditions of the basin. Due to the
limited amount of soil cover overlying bedrock, almost all of the runoff
reaches the streams and tributaries of the basin with very little flow
going into groundwater storage. Mean annual runoff exceeds 90 percent
during the May through October period which is characteristic of the
basin's maritime influence. Runoff contributions from snowmelt usually
occur in May and June, with intense rainfall contribution to the maximum
runoff during August through October.
Glacier contributions to runoff are dependent on seasonal and long term
temperature and precipitation variation. Their affects are discussed
further on and a detailed discussion can be found in R&M's report included
as Appendix B of this report.
5-16
5 . 3. 4. 2 Streamflow
Streamflow records at the Bradley Lake outlet are available from October
1957 to the present, however, records for the Middle FoLk flows and Upper
Bradley River were not started until October 1979.
As stated above, higher streamflows occur in the May through October period
as a result of snowmelt and intense rainstorms during the summer and fall
periods. Maximum mean daily discha~ges during this period have exceeded
5,000 cfs.
Typical low flows during the November through April period range from 20
cfs to about 250 cfs with higher flows seldom exceeding about 750 cfs in
November. Flows in the drier December through April periods seldom exceed
20 to 75 cfs.
5 .3.4.3 Streamflow Adjustments --Po~ver Studies
Adjustments to the historical streamflow records (October 1957 through
September 1982) were required to reflect potential future inflows to
Bradley Lake for use in predicting expected power and energy generation
from the project. A detailed description of the methodology used to
establish the adjusted streamflows is included in Appendix B. Only a
summary of results is presented herein.
Initial streamflow adjustments of the historical records were made to
reflect switching of the Nuka glacier runoff from the Nuka River to the
Bradley River after 1970. The results of this analysis indicate that the
COE' s estimate of flow adjustment during this period was too conservative
by a factor of about 50 percent. Instead of the 46 cfs annual runoff added
to the 1957 through 1970 period, this most recent analysis indicates that
an additional 43 cfs of streamflow over the COE's estimate would have been
available. The additional 43 cfs was therefore added to the COE's
tabulated flows over the 1957-1970 period and distributed on a monthly
basis in accordance with the pattern estimated by the COE. The revised
monthly flows are shown in Table 5.3-1 and an annual flow-duration curve is
presented in Figure 5. 3-1.
5-17
5.3.4.4 Middle Fork Streamflows
Middle Fork monthly streamflows were developed on the basis of the above
adjusted Bradley River Streamflows (Table 5. 3-1) for the period of the
Bradley Lake record. Because an additional two years of monthly flow data
at the Middle Fork Diversion were available since the COE' s analysis, the
Middle Fork flows presented herein represent a refinement over that used by
the COE. A description of the methodology used to establish the Middle
Fork flows is included in Appendix B. Table 5. 3-2 shows the adjusted
monthly flows used in this study and Figure 5. 3-2 shows the mean annual
flow duration curve.
5.3.4.5 Lower Bradley River Streamflows
Monthly flows were also developed for the Lower Bradley River for the
unregulated portion of the drainage below the Middle Fork Diversion and
Bradley Lake outlet. Tnese flows are ·shown on Table 5. 3'-3. --The purpose of
these estimates was to determine the contribution that these flows would
have in meeting the target flows established by the instream flow
assessments for aquatic habitat enhancement. Although these flows are not
used directly in determining the potential power output of the project they
do contribute in minimizing the amount of water which may have to be
diverted out of Bradley Lake to satisfy minimum instream flows for aquatic
habitat. An annual flow duration curve for the above conditions is shown
in Figure 5. 3-3.
5.3.4.6 Bradley River Glacial Adjustments
To account for possible future changes in the flow regime of the Upper
Bradley River due to glacial influences, studies were conducted to
determine their affects on runoff production. Aerial photos of the
glaciers within the basin were used in estimating an equivalent water
thickness loss of 14 + 18 feet averaged over the glaciers between the
period 1952 and 1979. Although the glaciers have retreated in this time
period, the upper mass of the glaciers has actually increased, which is
consistent with other glaciers in the area.
5-18
The total loss of water equivalent in the glaciers was then distributed
over the previously adjusted historical Bradley Lake streamflow record
using a runoff precipitation model which was calibrated for other glaciers
of Alaska. Monthly distribution of the annual loss was distributed to the
months of June through September using a thawing degree-day index. The
revised streamflow record which represents a condition where the glaciers
are neither gaining nor loosing water from storage in any given year is
shown in Table 5.3-4. An annual flow duration curve for the above mass
balance adjustments is shown in Figure 5.3-4.
The above flow scenario represents a condition on the conservative side in
terms of available streamflow for power production. Should climatic
conditions similar to the historical records occur in the future then flows
in Table 5.3-4 would be representative. However, a small change in
climatic conditions in the future could cause the glaciers to return :to a
state similar to that at the beginning of the period of record. In q,rder
to reflect this possibility, Table 5. 3-5 has been prepared to indicat~~ the
streamflow record wherein year-to-year variation in glacial mass caused by
differences in climatic conditions occurs. This represents a condition
wherein only the trend of long term glacier wasting is removed. The annual
flow duration curve for this record is shown in Figure 5.3-5.
A detailed description and methodology of the above glacial adjustments to
streamflow can be found in Appendix B.
5.3.4. 7 Floods
Flood peaks usually occur between June and September with most floods in
early summer caused by snowmelt and those in August and September from
rainfall. Characteristics of the geologic conditions of the basin, most
flood hydrographs are characterized by typically skewed distribution of
discharge with a fairly steep rising limb and asymmetric recession limb.
The COE analyzed the flood characteristics of the basin and developed a
flood frequency curve based on the historical records. Their analysis
included adjustments of the annual flood peaks during the 1958 through 1970
5-19
period to account for the Nuka Glacier runoff switching from the Nuka River
to the Bradley River. It has been shown above that their estimate of this
adjustment was too low which would tend to underestimate the discharge for
a given return period flood. In addition, it appears that their analyses
used the recorded discharges at the lake outlet which would be lower than
the actual inflow into the Lake due to the regulation effects of surcharge
storage. However, it has just recently been found (August 1983) that the
Nuka Glacier runoff has switched back again to the Nuka River with a
diversion of flow between the Nuka and Bradley Rivers similar to that which
occurred in the 1958 through 1970 period. It therefore appears that the
COE's estimate of the flood frequency is acceptable for the runoff
conditions now being experienced in the basin. Should this condition
continue into the construction period of the Project, it would obviously
reduce the expected flood peaks which the diversion tunnel would have to
pass. A small diversion dike or an improvement to the outlet channel
flowing to Bradley Lake will have to subsequently be developed near the
termirnis of Nuka. Glacfer to ins-ure th.e glacier runoff is directed into
Bradley Lake, as all power and energy values reported herein are based on
this condition.
5.3.4.8 Probable Maximum and Standard Project Flood
The COE conducted a fairly extensive study
characteristics of the Bradley Lake drainage basin
of
in
the hydrologic
determining the
Probable Maximum Flood. The methodology and approach used by the COE was
reviewed by SWEC and appears thorough. The Probable Maximum Flood (PMF)
inflow was determined for Bradley Lake both with and without Middle Fork
Diversion, however, it was shown that the Middle Fork Diversion's
contribution to the peak PMF inflow was only about equal to its maximum
diversion capacity of about 450 cfs.
The PMF study conducted by the COE is discussed in their "Design Memorandum
No. 1 11 entitled "Hydrology" dated June 1981 and in "Design Memorandum No.
2 11
, "General Design Memorandum" dated February 1982. However, the results
reported in these references are not the same. The COE stated that the
peak flow of the Standard Project Flood (SPF) reported in their design
5-20
memorandum was about equal to the estimated 100 year flood. Because the
Probable Maximum Precipitation (PMP) used in deriving the SPF was a fixed
ratio (50%) of the PMP used in deriving the PMF, the streamflow routing
parameters were revised to increase the peak flood discharge of the PMF and
the SPF. The revised PMF and SPF hydrographs were therefore included in
the COE later issued General Design Memorandum No. 2. Plate 18 shows the
COE's updated hydrographs which were used in the present study to size the
spillway.
5. 3. 4. 9 Sedimentation and Evaporation
The COE 's analysis of sedimentation in both Bradley Lake and Middle Fork
indicated suspended sediment concentrations were so low so as not to
present any long term sedimentation problems.
Evaporation from the lake surface during project operation was also found
to be minimal. Since the historical streamflow records used in developing
the power generation estimates already reflect the effects of evaporation,
no adjustments to recorded streamflows are required.
5 . 4 SURVEY CONTROL
The project datum used in this report is based ·on Alaska State Plane
Coordinate System Zone 4, which is referenced to the North American datum
of 1927 (NAD 27 /Clark Spheroid of 1866). The project vertical datum is
based on an assumed datum for this project which was initiated by using the
scaled elevation of control point referred to as JEFF at 26.24 feet. Later
observations by National Oceanic and Atmospheric Administration (NOAA)
placed the local project datum origin for Mean Sea Level (MSL) 4. 02 feet
lower. The Mean Lower Low Water datum (MLLW) origin is 9. 61 feet lower
than MSL origin or 13.63 feet lower than the project datum origin.
The differences between project elevations referenced and used by this
study and MSL or MLLW can be equated as follows:
MSL elevation =
MLLW elevation =
Project Elevation+ 4.02 feet.
Project Elevation+ 13.63 feet.
5-21
Recent field surveys performed by R&M in conjunction with field study
efforts showed further horizontal and vertical discrepancies between
previously published coordinate values of monumented stations as discussed
in Appendix B. Horizontal shifts varying from 0. 502 feet to 1. 68 7 feet
feet were noted. Similarly vertical position shifts of + 1.170 feet to +
4. 719 feet were determined. The study recognized these discrepancies.
However, since the relative value of elevations would be within i 2.5 feet,
it was decided to only consider the 4. 02 feet correction for reference in
the study. Future efforts must include a new, stronger control network for
project use in definitive engineering and design work.
In addition to the above discrepancies, it was also observed during the
course of field work that certain areas of the topographic maps utilized in
the COE study were not accurate. Although the discrepancies would not
impact the results of this study, it is recommended that more accurate maps
of selected areas be prepared for future engineering-design.
5-22
:tear
1958
1959
1960
1961
1962
1963
1964
1965
1966
1967
1968
1969
1970
1971
1972
1973
1974
1975
1976
1977
1978
1979
1980*
1981*
1982*
* Recorded
BRADLEY RIVER FLOWS AT LAKE OUTLET
ADJUSTED. FOR NUKA GLACIER SWITCH
DRAINAGE AREA = 56.1 SQUARE MILES
MONTHLY,ANNUAL MEAN DISCHARGE, IN CUBIC FEET PER SECOND
Oct Nov Dec Jan Feb Mar Apr Hay Jun Ju1 Aug Sep
175 577 111 79 42 32 74 389 1' 378 1,410 1,692 446
275 102 60 33 25 22 33 308 1,055 1,052 1,041 419
187 94 60 39 35 24 33 593 900 1,166 1,094 572
249 144 179 199 107 42 30 436 948 1,361 1,166 1,258
347 116 71 55 31 22 39 177 852 1,101 881 500
269 317 127 113 87 67 45 231 781 1,512 1,481 1,228
562 94 108 75 63 40 33 87 841 1,227 1,597 1,151
477 140 85 64 50 55 75 131 655 1,153 1,227 1,756
595 165 10 39 32 31 41 150 966 1,146 2,162 1,819
525 64 43 35 31 29 36 253 910 1,241 1,562 1,802
231 224 136 99 91 105 62 307 739 1,140 1,287 513
211 13 41 35 35 34 43 310 1,673 1,543 1,065 723
1,900 211 239 118 116 109 103 331 895 1' 324 1,410 740
197 382 76 45 36 31 31 115 641 1,394 1,262 507
376 108 55 32 20 17 17 141 517 1,172 1,378 1,019
413 123 56 34 26 24 28 128 600 918 870 908
575 173 50 32 23 19 23 227 551 860 1,000 1,501
346 224 112 55 43 34 30 355 1,035 1,068 864 850
424 118 52 39 32 26 41 206 813 1,107 1,153 1,293
420 414 312 326 306 178 119 354 995 1,653 2,049 646
407 70 37 34 40 42 56 291 755 1,081 1,182 959
572 161 104 43 30 27 31 290 712 1,004 1,883 1,357
1,173 411 85 67 81 74 58 326 936 1' 332 1,304 897
779 150 110 233 160 170 310 788 908 1,490 1, 643 885
298 251 98 52 73 45 37 138 677 1,107 904 1,780
Annual
587
371
403
512
351
525
494
490
604
506
415
489
631
396
406
346
421
420
443
652
415
521
564
640
456
L_ ________ ---..,... ____ __...;. _________ __.;,. __ TABLE 5.3-1
Year Oct
1958 59
1959 34
1960 23
1961 31
1962 35
1963 34
1964 42
1965 48
1966 45
1967 53
1968 29
1969 35
1970 143
1971 25
1972 38
1973 41
1974 43
1975 43
1976 42
1977 42
1978 41
1979 43
1980** 98
1981** 51
1982** _].§.
Average 46
MIDDLE FORK FLOWS AT DIVERSION DAM
(Based on ratios developed for Bradley River Flows
adjusted for Nuka Glacier Switching*)
Nov Dec Jan Feb Mar Apr May Jun Jul
64 6 6 5 4 4 14 126 214
10 8 4 4 2 4 14 93 113
9 8 4 4 2 4 21 90 152
9 9 15 9 5 4 15 85 204
12 8 6 5 2 4 10 85 121
35 6 8 7 5 4 11 78 227
9 12 6 8 5 4 5 84 160
8 10 7 6 4 4 . 7 66 150
10 8 4 5 4 4 8 87 149
6 5 4 5 3 4 11 91 161
25 7 7 7 7 4 14 74 148
7 5 4 4 4 4 14 151 231
13 12 9 9 8 4 12 90 172
42 9 5 5 4 4 6 64 209
11 7 4 3 2 4 8 52 152
7 7 4 4 2 4 7 60 101
10 6 4 3 2 4 10 55 95
25 6 6 5 4 4 12 93 117
12 7 4 5 2 4 9 81 122
46 16 24 24 12 4 12 90 248
7 5 4 5 5 4 13 76 119
10 12 5 5 3 4 13 71 110
35 9 5 5 4 4 14 85 208
8 5 17 9 7 4 24 92 211
.21 _JJ. _7 _9 _5 4 8 _.21_ 144
19 8 7 6 4 4 12 83 162
* Nuka Glacier Basin switching assumed to occur after 1970.
** Recorded monthly averages •
Aug Sep
188 47
127 43
137 60
157 107
110 53
163 147
176 138
166 149
238 155
172 153
174 54
133 76
190 78
170 53
186 122
109 109
125 128
108 102
144 110
225 68
160 115
207 115
180 115
183 88
113 136
162 101
..___ ________ TABLE 5.3-2
ESTIMATED AVERAGE MONTHLY FLOW
LOWER BRADLEY RIVER
Year Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
1958 125 190 40 36 23 28 65 113 182 103 63 53
1959 51 50 24 32 23 19 29 110 177 99 52 50
1960 52 5.1: 29 36 25 20 28 115 186 104 58 63
1961 52 42 41 75 37 22 44 112 181 104 59 99
1962 55 53 27 34 24 22 39 115 185 99 55 38
1963 49 55 25 44 61 90 30 104 167 102 47 54
1964 61 20 24 38 29 16 13 149 240 115 61 50
1965 60 71 27 23 15 29 40 115 186 120 54 88
1966 59 23 13 27 26 18 24 125 202 113 74 94
1967 75 57 34 35 21 13 16 107 172 102 56 69
1968 48 123 48 45 32 18 38 105 169 94 41 33
1969 42 27 15 24 17 13 16 87 141 91 38 30
1970 270 58 46 49 45 52 43 94 152 98 46 47
1971 47 76 22 29 21 16 16 112 180 104 67 48
1972 50 33 29 39 27 18 17 71 114 87 34 58
1973 64 32 18 13 11 10 16 66 148 92 35 43
1974 41 30 22 17 13 12 21 97 135 53 22 52
1975 66 59 29 16 13 11 11 80 213 139 40 66
1976 80 30 20 15 13 11 22 87 184 106 35 117
1977 105 100 74 107 80 41 33 114 202 144 97 36
1978 107 32 14 14 15 12 15 99 180 82 34 41
1979 133 56 52 28 18 13 27 96 151 82 69 39
1980 156 175 52 23 36 24 29 127 215 131 104 76
1981 134 45 28 112 61 52 42 205 160 120 61 45
1982 ....2§. ~ 2. ...1:2. ~ 20 18 _2.2. 139 ..11 ~ --22
Average 82 62 32 37 29 24 28 107 174 102 53 60
* Unregulated area below Bradley Lake damsite and Middle Fork Diversion.
~----------------TABLE 5.3-3
Year
1958
1959
1960
1961
1962
1963
1964
1965
1966
1967
1968
1969
1970
1971
1972
1973
1974
1975
1976
1977
1978
1979
1980
1981
1982
BRADLEY RIVER FLOWS AT LAKE OUTLET
ADJUSTED FOR NUKA SWITCH AND GLACIER BALANCE CHANGES
DRAINAGE AREA = 56.1 SQUARE MILES
MONTHLY AND ANNUAL MEAN DISCHARGE, IN CUBIC FEET PER SECOND
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
775 577 111 79 42 32 74 389 1,430 1,470 1,750 475
275 102 60 33 25 22 33 308 1,070 1,080 1,070 436
187 94 60 39 35 24 33 593 990 1' 320 1,230 651
249 144 179 199 107 42 30 436 1,160 1,650 1,440 1,440
347 116 71 55 31 22 39 177 937 1,220 1,000 541
269 317 127 113 87 67 45 237 560 1,120 1,090 944
562 94 108 75 63 40 33 87 769 1,140 1,510 1,090
477 140 85 64 50 55 75 131 625 1,100 1,180 1,710
595 165 70 39 32 31 41 150 596 660 1,690 1,480
525 64 43 35 31 29 36 253 820 1,110 1,430 1, 730
231 224 136 99 91 105 62 307 585 929 1,060 416
277 73 41 35 35 34 43 310 1,080 820 466 308
1,900 211 239 118 116 109 103 331 771 1,170 1,250 660
197 382 76 45 36 31 . 31 115 862 1,750 1,670 710
376 108 55 32 20 17 17 141 484 1,120 1, 320 987
413 123 56 34 26 24 28 128 760 1,150 1,090 1,030
575 173 50 32 23 19 23 227 309 530 652 1,250
346 224 112 55 43 34 30 355 1,280 1,450 1,250 1,090
424 118 52 39 32 26 41 206 777 1,050 1,100 1,260
420 414 312 326 306 178 119 354 1,350 2,100 2,550 927
407 70 37 34 40 42 56 291 670 966 1,050 889
572 161 104 43 30 27 31 290 739 1,050 l' 930 1, 390
1,170 411 85 67 81 74 58 326 936 1' 332 1' 304 897
779 150 110 233 160 170 310 788 908 1,490 1,643 885 ~
298 251 98 52 73 45 37 138 677 1,107 904 1,780
Annual
604
379
441
591
382
417
468
475
465
510
358
295
588
495
391
407
324
523
428
784
382
533
564
640
456
'---------------------------TABLE 5.3-4
Year
1958
1959
1960
1961
1962
1963
1964
.1965
1966
1967
1968
1969
1970
1971
1972
1973
1974
1975
1976
1977
1978
1979
1980*
1981*
1982*
*Recorded
BRADLEY RIVER FLOWS AT LAKE OUTLET
ADJUSTED FOR NUKA SWITCH AND FOR TREND OF GLACIER WASTING
DRAINAGE AREA = 56.1 SQUARE MILES
MONTHLY AND ANNUAL MEAN DISCHARGE, IN CUBIC FEET PER SECOND
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
77 577 111 79 42 32 74 389 1, 340 1, 360 1,640 422
275 102 60 33 25 22 33 308 1,030 1,020 1,010 402
187 94 60 39 35 24 33 593 879 1,130 1,060 553
249 144 179 199 107 42 30 436 915 1, 320 1,130 1,230
347 116 71 55 31 22 39 177 833 1,070 853 491
269 317 127 113 87 67 45 237 765 1,480 1,450 1,210
562 94 108 75 63 40 33 87 813 1,190 1,560 1,130
477 140 . 85 64 so 55 75 131 635 .1,120 1,193 1,720
595 165 70 39 32 31 41 150 942 1,110 2,130 1,800
525 64 43 35 31 29 36 253 885 1,200 1,520 1,780
231 224 136 99 91 105 62 307 720 1,110 1,260 501
277 73 41 35 35 34 43 310 1,650 1,520 1,040 708
I 1,900 211 239 118 116 109 103 331 858 1,280 1, 360 H6
197 382 76 45 36 31 31 115 619 1, 360 . 1,220 487
376 108 55 32 20 17 17 141 500 1,140 1, 350 1,000
413 123 56 34 26 24 28 128 576 884 838 890
575 173 50 32 23 19 23 227 534 837 975 1,480
346 224 112 55 43 34 30 355 1,010 1,020 821 821
424 118 52 39 32 26 41 206 792 1,070 1,120 1,270
420 414 312 326 306 178 119 354 947 1,590 1,980 608
407 70 37 34 40 42 56 291 888 1,460 1,610 868
572 161 104 43 30 27 31 290 651 1,060 862 1,750
1,173 411 85 67 81 74 58 326 936 1, 332 1, 304 897
119 150 110 233 160 170 310 788 908 1,490 1,643 885
298 251 98 52 13 45 31 138 677 1,107 904 1,780
Annual
573
363
394
500
344
517
484
480
595
536
408
482
618
386
398
337
414
408
434
634
407
509
564
640
456
..____---------------------------TABLE 5.3-5 ___,
(I)
I&.
(.) .
3: 0
...I
I&.
...I < :::;) z z <
w
~ < a: w > <
•
500
400
300
200
% EXCEEDANCE
ANNUAL FLOW DURATION
BRADLEY LAKE OUTLET
ADJUSTED FOR NUKA GLACIER SWITCH ONLY
.___---------FIGURE 5.3-1~
en u.
(.'I . s:
0
...1 u.
...1 < ~ z z <
w
0
<C a:: w > <
50
40
30
% EXCEEDANCE
ANNUAL FLOW DURATION
MIDDLE FORK
AT MIDDLE FORK DIVERSION DAM
..___--------FIGURE 5.3-2 ~
100
90
80
Cl.l 70 u.
(,) .
3: 60 0
-' u.
...1 < ~ 50 z z <
w
0 40 < a: w > < 30
20
10
0
0 10 20 30 40 50 60 70
% EXCEEDANCE
ANNUAL FLOW DURATION
LOWER BRADLEY RIVER
80 90 100
'-----------FIGURE 5.3-3 ____.
en u.
(.) .
3:
0 ... u. ... < ::I
2
2 <
w
c:J < a: w > <
500
400
300
% EXCEEDANCE
ANNUAL FLOW DURATION
BRADLEY RIVER
WITH GLACIER MASS BALANCE ADJUSTMENTS
------------FIGURE 5.3-4
en u.
(J .
3:
0
-' u.
-' c(
:::::1 z z
c(
w
(!I
c(
a: w > c(
800~--------------------------------------~
700
600
500
400
300
200
100
20 30 40 50 70 80 90 100
% EXCEEDANCE
ANNUAL FLOW DURATION
BRADLEY RIVER
WITH GLACIER WASTING TREND REMOVED
...___ ________ FIGURE 5.3-5 ____.
6
ENGINEERING
AND
ECONOMIC
EVALUATIONS
MANUFACTURERS TURBINE DATA Sheet 1 of 3
30 MW UNITS -VERTICAL SHAFT MACHINES
------------------------FRANCIS TURBINES--------------------------------------------------PELTON TURBINES------------------
DATA
PRICES: millions (1)
Two Turbines
Installation
Two Inlet Valves
Installation
Two Bypass Valves
Installation
Two Governors
Installation
TOTAL INSTALLED
RATINGS:
Rated Power, MW
Rated Flow, CFS
Rated Head, FT
Sync. Speed, RPM
Specific Speed (Engl.)
Runaway Speed, RPM
No. of Jets (Pelton)
Submergence of Runner
ALLIS
CHALMERS
incl.
incl.
incl.
incl.
0.24
incl.
incl.
incl.
$4.64
30.00
342.00
1112.00
900.00
28.10
at c.l., ft -12.40
DIMENSIONS: (Ft.)
Runner Throat Diameter
Runner O.D.
Runner Height
Spiral Case Inlet Dia.
Overall Width of
4.17
Spiral Case 11.85
Draft Tube Depth from
c.l. 10.20
Total Draft Tube Depth
from min. TWL 22.60
Draft Tube Outlet
Width 8.32
Head Cover O.D.
Distributor Height
WEIGHTS: (lbs)
Runner
Spiral Case
Total Turbine Weight
Hydraulic Thrust
COMMENTS
DOMINION
ENGINEERING SULZER
WORKS, LTD. BROS., INC.
$5.05
1.10
1.50
0.20
0.75
0.10
incl.
incl.
$8.70
34.25
1112.00
900.00
30.00
1360.00
-19.00
3.50
5.20
1.90
3.66
13.90
11.35
30.35
8.90
5,900
21,000
95,000
94,000
$1.67
0.32
0.75
0.075
0.70
0.05
$3.565
30.00
419.00
1112.00
900.00
30.00
1520.00
-46.00
3.10
4.20
1.50
3.30
11.55
9.60
55.60
6.70
5.40
0.62
14,000
42,000
120,000
74,500
(1) FOB jobsite unless otherwise noted
*Will not
produce
rated power
at min. head.
KVAERNER
BRUG A/S TOSHIBA
$1.73
1.25
0.89
0.20
0.63
$4.70
30.00
353.00
1112.00
720.00
22.80
1135.00
-22.00
3.12
5. 31
1.80
2.95
12.55
21.40
43.40
7-90
0.55
$2.70
0.76
o.8o
0.25
incl.
incl.
incl.
incl.
$4.51
34.00
399.00
1112.00
600.00
20.00
1067.00
-10.50
6.30
1.74
3-71
15.83
10.83
21.33
13.45
8.53
9,330 5,800
13,120 22,000
120,000
40,000
NISSHO IWAI ALLIS
(FUJI) CHALMERS
$5.25
Price
incl.
incl.
includes incl.
Gen. and is incl.
FOB Japan.
No installa--
tion or
freight.
30*
348.00
1112.00
720.00
22.40
1280.00
-15.00
3.50
5.80
2. 30
2.90
14.40
10.34
25.34
8.40
6.36
0.61
5,820
39,000
90,200
incl.
incl.
$8.64
30.00
360.00
6.00
6.75
SULZER
BROS. ,INC.
$1.90
0.32
0.75
0.75
0.70
0.05
$4.47
30.00
427.00
1100.00
360.00
660.00
6.00
+12.50
6 .• 55
8.33
4.27
32.27
17.85
5.35
13.41
14,100
64,000
190,000
*Will not
produce
rated power
at min. head.
KVAERNER NISSHO IWAI
BRUG A/S (FUJI)
$2.70
1.35
0.89
incl.
0.63
incl.
$5.57
30.00
352.00
1100.00
400.00
705.00
6.00
+7.50
6.09
7.87
4.25
31.25
19.00
11.50
12.50
14,800
33,000
$6.06
Price includes
Gen. and is
FOB Japan.
No installa-
tion or
freight.
30*
354.00
1100.00
400.00
5.10
730.00
6.00
+8.00
5.97
8.20
4.27
27.80
14.50
6.50
12.00
11,550
34,000
247,700
L------~------------:---------------TABLE 6.2-1
MANUFACTURERS TURBINE DATA Sheet 2 of 3
45 r-1W UNITS -VERTICAL SHAFT MACHINES
----------------------------FRANCIS TURBINES-------------------------------------------------PELTON TURBINES------------------
DOMINION
ALLIS ENGINEERING SULZER KVAERNER NISSHO IWAI ALLIS SULZER KVAERNER NISSHO IWAI
DATA CHALMERS WORKS, LTD. BROS., INC. BRUG A/S TOSHIBA (FUJI) CHALMERS BROS. ,INC. BRUG A/S (FUJI)
PRICES: millions (1)
Two Turbines $5.070 $6.30 $1.90 $2.175 $3.90 $6.66 incl. $2.60 $3.383 $7.65
Installation incl. 1.20 0.34 1.347 1.10 Price incl. 0.34 1.444 Price includes
Two Inlet Valves incl. 1.90 1.03 1.128 1.20 includes incl. 1.03 1.128 Gen. and is
Installation incl. 0.25 0.10 0.34 Gen. and is incl. 0.10 incl. FOB Japan.
__ T_w~-~yp_g~~-Yalve::; _Q. 25_!3_ 0.95 0.234 incl. FOB Japan. No installa-
Installation incl. 0.12 incl. .No-Ins taiia---fion-or--
Two Governors incl. incl. 0.80 0.715 incl. tion or incl. 0.80 0.715 freight.
Installation incl. incl. 0.05 incl. freight. incl. 0.05 incl.
TOTAL INSTALLED $5.328 $10.72 $4.22 $5.600 $6.54 $11.61 $4.92 $6.670
RATINGS:
Rated Power, MW 46.80 52.50 45.00 45.00 51.00 45* 45.00 45.00 45.00 45*
Rated Flow, CFS 533.00 622.00 530.00 597.00 521.00 639.00 530.00 530.00
Rated Head, FT 1112.00 1112.00 1112.00 1112.00 1112.00 1112.00 1100.00 1100.00 1100.00
Sync. Speed, RPM 720.00 720.00 720.00 600.00 514.00 600.00 300.00 300.00 360.00 327.00
Specific Speed (Engl.) 28.00 30.00 30.00 23.30 21.00 22.90 5.10
Runaway Speed, RPM 1100.00 1220.00 950.00 917.00 1060.00 550.00 640.00 600.00
No. of Jets (Pelton) 6.00 6.00 6.00 6.00
Submergence of Runner
at c.l., ft -12.40 -19.00 -46.00 -22.00 -13.10 -15.00 +14.30 +9.20 +8.20
DIMENSIONS: (Ft.)
Runner Throat Diameter 4.33 3-90 3-83 4.25 8.10 7.84 6.77 7.28
Runner O.D. 5.22 6.40 5.24 6.36 7.40 1.00 10.00 9.00 9.84
Runner Height 2. 30 2.20 2.25 2.10 2.70
Spiral Case Inlet Dia. 4.43 4.53 4.30 3.60 4.46 3.50 5.58 5.10 5.20
Overall Width of
Spiral Case 14.82 17.20 14.65 16.97. 18.86 17.55 37-75 33-91
Draft Tube Depth from
c.l. 12.80 14.05 12.00 23.03 13.06 12.94 20.83 23.30 16.00
Total Draft Tube Depth
from min. TWL 25.20 33.00 58.00 45.03 26.16 28.00 6.56 14.10 7.80
Draft Tube Outlet
Width 10.40 11.00 8.40 9.30 16.40 10.30 16.40 14.75 14.70
Head Cover O.D. 6.70 10.10 9.02
Distributor Height 0.78 0.69 0.75
-~IG_H'J.'~: <1!>!3)
Runner 10,000 20,000 fl,TBo 9,550 -·rn-,700-Z6,0UO ra;so·o--zl-~ ro·o-
Spiral Case 28,000 60,000 21,870 33,000 59,500 41,200 54,500
Total Turbine Weight 155,000 160,000 180,000 175,000 360,000 362,200
Hydraulic Thrust 150,000 117,000 60,000 134,200
COMMENTS *Will not *Will not
produce produce
(1) FOB jobsite unless otherwise noted rated power rated power
at min. head. at min. head.
TABLE 6.2-1
MANUFACTURERS TURBINE DATA Sheet 3 of 3
67.5 MW UNITS-VERTICAL SHAFT MACHINES
---------------------------------FRANCIS TURBINES---------------------------------------------PELTON TURBINES------------------
DATA
PRICES: millions (1)
Two Turbines
Installation
Two Inlet Valves
Installation
Two Bypass Valves
Installation
Two Governors
Installation
TOTAL INSTALLED
RATINGS:
ALLIS
CHALMERS
incl.
incl.
incl.
incl.
0.30
incl.
---------
incl.
incl.
$6.35
Rated Power, MW 67.50
Rated Flow, CFS 770.00
Rated Head, FT 1112.00
Sync. Speed, RPM 600.00
Specific Speed (Engl.) 28.10
Runaway Speed, RPM
No. of Jets (Pelton)
Submergence of Runner
at c.l., ft -12.40
DIMENSIONS: (Ft.)
Runner Throat Diameter
Runner O.D. 6.26
Runner Height
Spiral Case Inlet Dia. 5.32
Overall Width of
Spiral Case 17.80
Draft Tube Depth from
c.l. 15.35
Total Draft Tube Depth
from min. TWL 27.75
Draft Tube Outlet
Width 12.50
Head Cover O.D.
Distributor Height
WEIGHTS: (lbs)
--Runnel"'
Spiral Case
Total Turbine Weight
Hydraulic Thrust
COMMENTS
---
DOMINION
ENGINEERING
WORKS, LTD.
$8.20
1.40
2.50
0.32
1.25
___ Q_.l5 -
incl.
incl.
$13.82
77.00
lll2.00
600.00
30.00
910.00
-19.00
5.25
7.80
2.80
5.49
20.75
17 .oo
36.00
13.36
- -i6,i{j(J-
40,000
235,000
220,000
(1) FOB jobsite unless otherwise noted
SULZER
BROS., INC.
$2.20
0.39
1. 34
0.11
KVAERNER
BRUG A/S
$2.89
1.44
1.40
incl.
0.28
TOSHIBA
$5.50
1.40
1.63
0.46
incl.
NISSHO IWAI
(FUJI)
$8.47
Price
includes
Gen. and is
FOB Japan.
ALLIS
CHALMERS
incl.
incl.
incl.
incl.
SULZER
BROS. ,INC.
$3.20
0.39
1. 34
0.11
-___ .Jncl_. ________ incl~--_ .N~_i_l'l_st-.alla .... ______ --_ -----------
0.90
0.05
$4.99
0.78 incl. tion or
incl. incl. freight.
$6.79 $8.99
67.50
941.00
1112.00
600.00
30.00
1010.00
-46.00
4.70
6.30
2.80
5.00
17.70
14.50
60.50
10.20
8.00
0.94
67.50
795.00
lll2.00
514.30
24.50
820.00
-22.00
4.69
7.45
2.91
4.40
17.96
26.00
48.00
10.90
0.89
76.50
890.00
1112.00
450.00
22.50
809.00
-17.10
8.50
2.54
5.40
22.05
15.52
32.60
19.36
11.65
--3CJ-,CH)0
75,000
200,000
169,000
--:t3,J.20-- - - -~5 ,-ono-
34,020 49,000
80,000
*Will not
produce
rated power
at min. head.
250,000
67.5*
784.00
lll2.00
514.00
24.00
910.00
-19.00
5.10
8.20
3.00
4.24
21.10
15.85
34.85
13.00
10.84
0.90
--ra,-goo--
85,500
258,000
194,000
incl.
incl.
$16.47
0.90
0.05
$5.99
67.50
240.00
6.00
10.10
67.50
962.00
1100.00
257.10
5.00
470.00
6.00.
+17. 30
9.14
ll.70
6.56
45.71
25.30
20.12
-4-o,auo
180,000
500,000
*Will not
produce
rated power
at min. head.
KVAERNER
BRUG A/S
$4.21
1.54
1.40
incl.
NISSHO IWAI
(FUJI)
$10.50
Price includes
Gen. and is
FOB Japan.
No installa-
--___ tion-or-
0.78
incl.
$7-93
67.50
795.00
llOO.OO
277.00
5-37
490.00
6.00
+11.10
8.80
11.52
6.25
46.45
28.50
18.70
freight.
67.5*
797.00
1100.00
257.00
4.90
470.00
6.00
+10.00
9-35
12.80
6.40
43.85
19.00
9.00
18.00
-- ----3-4,-5-00 - - --lf?' 15-0 - - - ---- - - - - - -- - - -- -
66,200 82,600
596,000
L..-----~-----------~-------TABLE 6.2-1
MANUFACTURERS GENERATOR DATA Sheet 1 of 6
---------ALTERNATIVE 1. 33334 KVA 720 RPM VERTICAL FRANCIS-----------
DATA GE Co. TOSHIBA SIEMENS-ALLIS HITACHI AVERAGE
Price - 2
units $3.60 $3.10 $2.26 $5.00 $3.50
(millions of $)
· -±nsta·l-la-t-ion .. ---l-.-3-3-·------. -0-.-1-7--·-.. ·o-.-79-·-N;A-· --------
Total Price 4.93 3-87 3.05 5.00 4.20
FOB Point Jobsite Japan Jobsite Jobsite Jobsite
Efficiency 100% 97.7 97.6 97.6 97.2 97.5
at Percent 75% 96.8
Load 50% 95.7
25% 92.2
Overall Height/in 252 240 184 295 243
Overall Diameter 180 232 260 145 204
(in)
Total Weight/lbs 210,000 310 '900 320,000 265,000 276,000
Size of Largest 144xl44xl32 9lxl73x90 No data 150xl50xl00
Piece/in. (stator sect) (stator)
Weight Largest 80,000 52,900 160,000 90,000 95,725
Piece/lbs (1) (stator sect) (stator sect) (rotor/shaft)
Location of Above Above Above Above Above
thrust bearing,
above or below
rotor
Notes:
(1) In most cases, the weight of the largest piece is a shipping weight.
For maximum crane lift, use 40% of total weight for vertical units. (Rotor weight)
For maximum crane lift, use weight of largest piece for horizontal units.
-----ALTERNATIVE 2. 50000 KVA 600 RPM VERTICAL FRANCIS---
GE Co. TOSHIBA SIEMENS-ALLIS HITACHI AVERAGE
$5.30 $4.10 $3.22 $5.80 $4.60
. --r.;-9·6-· --r.o·o------ - - -r:-rT ---------------------- -N/A
7.26 5.10 4. 35 5.80 5.63
Jobsite Japan Jobsite Jobsite Jobsite
97-7 97.8 97.6 97.5 97.65
97.1
96.2
93.4
290 256 198 315 265
240 256 285 180 240
380,000 443,100 400,000 370,000 400,000
204xl20xl00 106xl97xl02 No data 175x87xl05
(stator sect) (stator)
66,000 75,000 200,000 60,000 70,000
(stator sect) (stator sect) (rotor/shaft) (not incl.
S.A.)
Above Above Above Above Above
~----------~----------------~----------------~~----TABLE 6_2-2
MANUFACTURERS GENERATOR DATA Sheet 2 of 6
-----ALTERNATIVE 3. 75000 KVA 514.3 RPM VERTICAL FRANCIS-------------
DATA GE Co. TOSHIBA SIEMENS-ALL IS HITACHI AVERAGE
Price - 2 units $6.00 $5.50 $4.26 $6.90 $5.66
(millions of $)
Installation 2.22 1.40 1.49 N/A
Total-El"-ic e - - -
... -... 8.22------.. -6.-90 - -.. - -5. 7-5---6.-90 - - -- -----6.-95--
FOB Point Jobsite Japan Jobsite Jobsite
Efficiency 100% 98.0 97.9 97.6 97.6
at Percent 75% 97.2
Load 50% 96.4
25% 93.7
Overall Height/in 280 244 222 335
Overall Length/in
Overall Diameter 260 287 306 205
(in)
Total Weight/lbs 454,000 613,000 640,000 595,000
Size of Largest 204xl05xl30 106xl97xl02 No data 205xl0 3xl20
Piece/in. (stator sect) (stator)
(stator)
Weight Largest 88,000 75,000 320,000 100,000
Piece/lbs (1) (stator sect) (stator sect) (rotor/shaft) (stator)
Location of Above Above Above Above
thrust bearing,
above or below
rotor
Notes:
(1) In most cases, the weight of the largest piece is a shipping weight.
For maximum crane lift, use 40% of total weight for vertical units. (Rotor weight)
For maximum crane lift, use weight of largest piece for horizontal units •
Jobsite
97.77
270
245
575,000
90,000
Above
--ALTERNATIVE 4. 33334 KVA 720 RPM HORIZONTAL
GE Co. TOSHIBA SIEMENS-ALLIS HITACHI
$3.40 $2.90 $2.20 $4.50
1.23 0.70 0.77 N/A
.. -4.6-J--- ----~·-60 2.-9-7-. --4.~0--
Jobsite Japan Jobsite Jobsite
97.7 97.7 97.6 97.3
252 232 226 295
180 15lt 146 155
210,000 154 '000 No data 245,000
144xl44xl32 53xl8lxl54 No data 195xl00xl55
(stator sect)
80,000 46,300 160,000 65,000
(stator sect) (stator sect) (rotor/shaft) (stator)
FRANCIS--
AVERAGE
$3.25
.... -3--9-3
Jobsite
97.6
96.9
95.9
92.5
251
158
203,000
88,000
.__ _____________ ......__ __________ TABLE 6.2-2-----
MANUFACTURERS GENERATOR DATA Sheet 3 of 6
--------ALTERNATIVE 5. 50000 KVA 600 RPM HORIZONTAL FRANCIS----------
DATA GE Co. TOSHIBA SIEMENS-ALLIS HITACHI
Price - 2
units $5.00 $3.80 $3.00 $5.20
(millions of $)
Installation 1.85 0.95 .1.05 N/A
----------6.85 4.75 4.05 5.20 Total Price
FOB Point Jobsite Japan Jobsite Jobsite
Efficiency 100% 97.7 97.9 97.6 97.6
at Percent 75% 97-3
Load 50% 96.4
25% 93.7
Overall Height/in
Overall Length/in 290 268 232 310
Overall Diameter 240 173 166 180
(in)
Total Weight/lbs 380,000 181,000 No data 345,000
Size of Largest 204xl20xl00 63x20lxl73 No data 230xl05xl80
Piece/in. (stator sect) (stator)
Weight Largest 66,000 53,900 200,000 100,000
Piece/lbs (l) (stator sect) (stator sect) (rotor/shaft) (stator)
Location of
thrust bearing,
above or below
rotor
Notes:
(l) In most cases, the weight of the largest piece is a shipping weight.
For maximum crane lift, use 40% of total weight for vertical units. (Rotor weight)
For maximum crane lift, use weight of largest piece for horizontal units.
AVERAGE
$4.25
5.21
Jobsite
97-7
275
190
302,000
74,000
(stator)
--ALTERNATIVE 6. 75000 KVA 514.3 RPM HORIZONTAL
GE Co. TOSHIBA SIEMENS-ALLIS HITACHI
$5.70 $5.20 $4.00 $6.20
2.11 1.30 1.40 N/A
7.81 6.50 5.40 6.20
Jobsite Japan Jobsite Jobsite
98.0 98.0 97.6 97-7
280 311 250 325
300 197 186 215
454,000 205,000 No data 550,000
210xl05xl30 7lx228xl97 No data 230xl25x215
(stator sect) (stator)
88,000 57,300 320,000 165,000
(stator sect) (stator sect) (rotor I shaft) (stator)
FRANCIS--
AVERAGE
$5.28
6.50
Jobsite
97.82
97.4
96.6
94.0
293
302,000
100,000
(stator)
L..--------------------'----------...----TABLE 6.2-2
MANUFACTURERS GENERATOR DATA Sheet 4 of 6
---------ALTERNATIVE 7. 33334 KVA 327.3 RPM VERTICAL PELTON----------
DATA GE Co. TOSHIBA SIEMENS-ALLIS HITACHI
Price - 2
units $4.20 $3.50 $2.75 $5.50
(millions of $)
Installation 1.55 0.85 0.96 N/A
Total Price 5.75 4.35 3-71 5.50
FOB Point Jobsite Japan Jobsite Jobsite
Efficiency 100% 97.5 97.5 97.5 97.3
at Percent 75% 96.8
Load 50% 95.8
25% 92.7
Overall Height/in 210 213 212 270
Overall Diameter 280 283 300 215
(in)
Total Weight/lbs 300,000 381,400 400,000 430,000
Size of Largest 250xl25x75 7lxl6lx83 No data No data
Piece/in. (stator sect)
Weight Largest 50,000 33,100 200,000 No data
Piece/lbs (1) (stator sect) (stator sect) (rotor/shaft)
Location of Above Below Above Above
thrust bearing,
above or below
rotor
Notes:
(1) In most cases, the weight of the largest piece is a shipping weight.
For maximum crane lift, use 40% of total weight for vertical units. (Rotor weight)
For maximum crane lift, use weight of largest piece for horizontal units.
AVERAGE
$4.00
4.83
Jobsite
97-5
226
270
378,000
42,000
Above
---ALTERNATIVE 8. 50000 KVA 240 RPM VERTICAL
GE Co. TOSHIBA SIEMENS-ALLIS HITACHI
$5.50 $5.00 $3.45 $6.70
2.04 1.20 1.20 N/A
7.54 6.20 4.65 6.70
Jobsite Japan Jobsite Jobsite
97.6 97-7 97.4 97.6
220 228 224 285
330 339 360 295
420,000 566,600 560,000 700,000
300xl50x70 79x20lx94 No data No data
(stator sect)
80,000 48,500 280,000 No data
(stator sect) (stator sect) (rotor/shaft)
Above Below Above Above
PELTON---
AVERAGE
$5.18
6.27
Jobsite
97.6
97.3
96.4
93.7
240
331
561,000
Above
&...-----------------------------TABLE 6.2-2 ___.
MANUFACTURERS GENERATOR DATA Sheet 5 of 6
--------ALTERNATIVE g. 75000 KVA 276.9 RPM VERTICAL PELTON-----------
DATA GE Co. TOSHIBA SIEMENS-ALLIS HITACHI
Price - 2 units $6.40 $6.40 $4.70 $7.70
(millions of $)
Installation 2. 37 1.60 1.65 N/A
Total Price 8.77 8.00 6.35 7-70
FOB Point Jobsite Japan Jobsite Jobsite
Efficiency 100% 97.9 97-9 97.6 97.8
at Percent 75% 97.5
Load 50% 96.7
25% 94.2
Overall Height/in 250 272 236 295
Overall Length/in
Overall Diameter 300 339 360 255
(in)
Total Weight/lbs 570,000 758,400 600,000 900,000
Size of Largest 290xl45xl00 95xl97x95 No data No data
Piece/in. (stator sect)
Weight Largest 90,000 54,000 300,000 No data
Piece/lbs {1) (stator sect) (stator sect) (rotor/shaft)
Location of Above Below Above Above
thrust bearing,
above or below
rotor
Notes:
(1) In most cases, the weight of the largest piece is a shipping weight.
For maximum crane lift, use 40% of total weight for vertical units. (Rotor weight)
For maximum crane lift, use weight of largest piece for horizontal units.
AVERAGE
$6.36
7. 71
Jobsite
97.8
263
313
707,000
Above
---ALTERNATIVE 10. 33334 KVA 327.3 RPM HORIZONTAL
GE Co. TOSHIBA SIEMENS-ALLIS HITACHI
$4.00 $3.20 $2.60 $4.90
1.48 0.80 0.91 N/A
5.48 4.00 3.51 4.90
Jobsite Japan Jobsite Jobsite
97.5 97.6 97.6 97.4
210 295 250 315
280 197 210 235
300,000 187,000 400,000 375,000
250xl25x75 45x228xl97 No data 280x80x235
(stator sect) (stator)
50,000 55,100 200,000 120,000
(stator sect){stator sect) (rotor/shaft) (stator)
PELTON--
AVERAGE
$3.68
4.47
Jobsite
97.5
97.0
96.0
93.0
268
231
317,000
100,000
L--------------~.;,....__ _____________ TABLE 6.2-2 ___,
MANUFACTURER'S GENERATOR DATA Sheet 6 of 6
-------ALTERNATIVE 11. 50000 KVA 276.9 RPM HORIZONTAL PELTON---------
DATA GE Co. TOSHIBA SIEMENS-ALLIS HITACHI
Price - 2 units $5.10 $4.70 $3.40 $5.90
(millions of $)
Installation 1.90 1.20 1.19 N/A
Total Price 7.00 5.90 4.59 5.90
FOB Point Jobsite Japan Jobsite Jobsite
Efficiency 100% 97.65 97.8 97.6 97.6
at Percent 75% 97.3
Load 50% 96.6
25% 94.1
Overall Height/in
Overall Length/in 240 354 250 335
Overall Diameter 310 220 272 265
(in)
Total Weight/lbs 390,000 212,000 540,000 575,0b0
Size of Largest 270xl35x80 59x252x220 No data 310xl00x265
Piece/in.
Weight Largest 75,000 61,700 270,000 155,000
Piece/lbs (1) (stator sect) (stator sect) (rotor/shaft) (stator)
Location of
thrust bearing,
above or below
rotor
Notes:
(1) In most cases, the weight of the largest piece is a shipping weight.
For maximum crane lift, use 40% of total weight for vertical units. (Rotor weight)
For maximum crane lift, use weight of largest piece for horizontal units.
AVERAGE
$4.78
5.85
Jobsite
97.7
295
267
430,000
....__ ____________ TARI F A?-?
PRELIMINARY ANNUAL ENERGY -GWH
2 UNITS EQUAL SIZE 3 UNITS EQUAL SIZE
OPERATING
GENERATING HEADWATER NCMINAL PLANT RATING AND UNIT TYPE NCMINAL PLANT RATING AND UNIT TYPE
FLOW REGIME POOL ELEVATION FRANCIS PELTON FRANCIS
60 MW 60 MW
Mid.Fork Fish Div. Max. HW Min. HW FIRM SEC AVG.AN. FIRM SEC AVG.AN FIRM SEC AVG.AN
With Without 1170 1081 304.6 19.3 323.9 329.9 19.2 349.1
Without With 1170 1081 280.9 25.2 306.0 296.7 21.2 317.8
With With 1170 1081 280.9 35.9 316.7 304.1 26.5 330.6
80 MW 90 MW
With Without 1170 1081
Without \-lith 11 7n 1081 ..A...A.I""'
With With 1170 1081 312.3 31.3 343.7 285.6 45.5 331.1
90 MW 90 MW 120 MW
With Without 1170 1081 333.9 28.2 362.1 332.0 29.7 361.6
Without With 1170 1081 291.8 30.7 322.5 298.2 31.8 329.9
With With 1170 1081 304.5 35.5 340.0 308.2 37.3 345.5 313.4 44.13 357.4
135 MW 135 MW 135 MW
With Without 1170 1081 282.5 39.0 321.5 333.2 37.2 370.4 334.6 36.4 371.0
Without With 11'(0 1081 239.2 41.9 281.1 299-3 39.1 338.3 292.5 38.6 331.1
With With 1170 1081 255.0 48.1 303.1 309.2 47.5 356.6 306.9 46.2 353.1
BASIS OF RESULTS:
1. Bradley River flows from Corps of Engineers' Design Memo Number 2,
Tables 7 -1.
2. Middle Fork flows, unregulated basin flows and fish diversion flows
(30 cfs min./150 cfs max.) based on preliminary estimates •
.....__---------------------------TABLE 6.2-3
MAX HW
1170
1170
1180
1180
1190
1190
RESERVOIR ELEVATIONS SENSITIVITY ANALYSES
90 MW PELTON -TWO 45 ·Mw UNITS
MIN HW
1081
1060
1081
1060
1081
1060
PREL~INARY GENERATING FLOWS
WITH MIDDLE FORK
(30 CFS MINi150 CFS MAX)
AVERAGE ANNUAL ENERGY --GWHRS
FIRM SECONDARY AVG. ANNUAL
308.2 37.3 345.5
313.5 33.1 346.6
318.4 32.6 350.9
323.6 27.8 351.4
328.3 27.3 355.5
333.8 18.6 352.4
'-----------------------T A r:n r= a 1'\_ .A __
MIDDLE FORK
INPUT
•1170, 1081 MAX,
MIN HWEL
• FRANCIS, PEL TON
ALL CAPACITIES
__.. • CAPITAL COST
.-----... .,.. • ENERGY BENEFIT
TUNNEL BORING ECONOMIC POWER
MACHINE TUNNEL DIAMETER
INPUT INPUT
• GEOTECHNICAL • DIAMETERS
DATA • 60, 90, 135 MW
•COST PLANT CAPACITY
• POWER TUNNEL r-+ • ENERGY LOSS COST
ARRANGEMENT • CAPITAL COST
ALTERNATIVES METHODOLOGY
• UTILIZE TBM • MINIMIZE TOTAL • CONVENTIONAL
METHODS COST
DECISION DECISION
• UTILIZE TBM • 60 MW-10FT
• 90 MW-11FT
•135MW-12 FT
NOTES:
1. ECONOMIC EVALUATIONS BASED ON
MAXIMUM VALUE OF BENEFITS LESS COSTS
2. FLOW REGIMES
01 =BRADLEY RIVER, WITH MIDDLE FORK,
WITH FISH DIVERSIONS
02 =BRADLEY RIVER, WITH MIDDLE FORK,
WITHOUT FISH DIVERSIONS
03 =BRADLEY RIVER, WITHOUT MIDDLE
FORK, WITH FISH DIVERSIONS
r-+
01,02 FLOWS
ALTERNATIVES
• CONSTRUCT
• ABANDON
DECISION
• CONSTRUCT
TURBINE TYPE
INPUT
• 1170, 1081 MAX,
MIN HWEL
• FRANCIS, PELTON
ALL CAPACITIES
• 01, 02, 03 FLOWS
• ENERGY BENEFITS
• CAPITAL COSTS
ALTERNATIVES
• FRANCIS
• PELTON
DECISION
• PELTON
DAM TYPE
INPUT
• CAPITAL COSTS
DAMS AND
ASSOCIATED
STRUCTURES
ALTERNATIVES
• CONCRETE
GRAVITY
• ROCKFILL
DECISION
• ROCKFILL
r-.
,,
PL~NT CAPACITY
I
INPUT
• 1 1'71li, 1081 MAX,
MIN HWEL
• Hp'W REGIME 01
• PELTON TURBINES
AL!L CAPACITIES
• TdTAL ESTIMATED~
CAPIITAL COST
• EN:ERGY BENEFITS
• ECpNOMIC
~~~~~~~~~O~ODE L
ALT~RlNATIVES
• 6oMw
• 90MW
• 13SMW
DECISION
• 90 jvlw
~,J
RESERVOIR
OPERATING LEVELS
INPUT
• FLOW REGIME 01
• 90 MW PELTON
• ROCKFILL DAM
• TOTAL CAPITAL
COST
• ENERGY BENEFITS
ALTERNATIVES
• MAX HWEL 1170,
1180, 1190
• MIN HWEL 1081,
1080, 1060
DECISION
• MAX HWEL 1180
• MIN HWEL 1080
RECOMMENDED
DEVELOPMENT
PLAN
• 11' POWER TUNNEL
ARRANGEMENT
SUITABLE FOR TBM
EXCAVATION
• 90 MW PEL TON
PLANT
• MIDDLE FORK
DIVERSION
FACILITY
• ROCKFILL DAM
• MAX HWEL 1180
• MIN HWEL 1080
i •
ASSESSMENT OF PRINCIPAL FEATURE~· -BRADLEY LAKE PROJECT
.____ __________ .....;... ____ FIGURE 6.1-1-
(I) u.
(.)
150
130
110
s: 90
0
..J u.
70
50
30
1-
t-
t-
-
t-
~
I I
JAN FEB
I I I I I I I I I
MAR APR MAY JUN Jl:JL AUG SEP OCT NOV DEC
TIME-MONTHS
PRELIMINARY INSTREAM FLOWS
·---FIGURE 6.1-2
6.0
5.9
5.8
50 MIL ENERGY
CAPITAL COST INCREASED 20%
5.7
en z
0
...I 5.4 ..0 ...I 0~ :iE ~ 0 . ~ 1-en ~ 0 5.3 ~ (J
...I
<( 70 MIL ENERGY ::I z
2
<( 5.2
...I
<(
1-
0
1-
5.1
5.0
50 MIL ENERGY
4.9
4.8
9 10 11 12
STEEL LINER DIAMETER-FT.
NOTE:
COST OF CAPITAL BASED ON
3.5% INTEREST FOR 50 YEARS
ECONOMIC DIAMETER ANALYSIS
POWER CONDUIT -90 MW PLANT
~--------------------------------CI~I 10~
1-
I
a '>--t_j
\_EXCAVATE
TO EL.1070'\
BRADLEY LAKE
MAXIMUM OPERATING W.S. EL.118d
MINIMUM OPERATING W.S. EL.1080'
--
T.O.DAM"\
DRAINAGE
GALLERY
EL.1085'
'DAM
i
rEL.1165'
7.1 J10
EL.1065'
EL.1070'
5'
VARIES
MAXIMUM GRAVITY SECTION
NOTE:
NORMAL W.S.
DRAINAGE
GALLERY
EL.1085'
ELEVATIONS SHOWN ARE ON
PROJECT DATUM. ,
MEAN SEA LEVEL DATU~~= PROJECT
DATUM PLUS 4.02 FT.
,.,. 50. 000' ,,_,,
GRAPHIC SCALE 1"•~'-0~
0 20' 40' pr.·.·--I
SCALE IN fEET
EL 1070
VARIES
MAXIMUM SPILLWAY SECTION
0 20' 40'
M" ..... 1
SCAlE IN FEET
AlTERNATIVE
CONCRETE GRAVITY
DAM CONCEPT
400 ~------------------------------------------------------------~
D---a PELTON
e e FRANCIS
380
360
.; 340 ...
:X:
3: AVERAGE ANNUAL e,
> e, a: 320 w z w
...1
<(
::;, z
2
<( 300
I FIRM
280
260
240 ~--~------~------~-------...1~------~------~------~------~
60 so· 100 120 140
NOMINAL PLANT RATING-MW
NOTE:
CURVES BASED ON EQUAL SIZE UNITS
MAXIMUM HW EL 1170.
MINIMUM HW EL 1081.
BRADLEY RIVER FLOWS FROM CORPS
OF ENGINEERS DESIGN MEMORANDUM
NO. 2 TABLE 7-1
WITH MIDDLE FORK FLOWS
WITH FISH DIVERSION FLOWS
160
ENERGY EVALUATJONS
FRANCIS AND PELTON TURBINES
180
---------FIGURE 6.2-3---....~
160 r---------------------------------------------------~
z
0 140 :J
...1
~
~
~ en 120
0
(.)
...1
·c:t
1-a::
;3 100
en en w
...1
en
!-
u.
~ 80
w
,a:l
Q w
1-<t
~
~ 60 en w
o---o PELTON
ee---ee FRANCIS
-o-----------o 2UNITS cY"'
40 ~--~------._ ______ ._ ______ ~------~------~------~
60 80 100 120 140
NOMINAL PLANT CAPACITY · MW
NOTE:
NET BENEFITS DO NOT INCLUDE COST OF 230 kV
ANCHORAGE INTERTIE TRANSMISSION LINE REQUIRED
FOR PLANT CAPACITIES ABOVE 90 MW.
COMPARATIVE EVALUATIONS
FRANCIS AND PELTON TURBINES
160 180
"----------FIGURE 6.2-4
! l UNIT
I
33'-o" 34'-o·
EI::RUNNER
EL--17\
TYPICAL CROSS SECTION
• , .. 20' , I
SCALE IN FE£T
[T.O.RAIL EL.40.5'
rEL.20'
10'-ci'
(MIN.) r
UtiiT 2
LONGITUDINAL SECTION . , ..
e
SCALE IN FEET
NOTE:
ELEVATIONS SHOWn \i<E ON
PROJECT DATUM.
...
I
MEAN SEA LEVEL DATUM~PROJECT
DATUM PLUS 4.02 FT. i
I
( UNIT1
I
48'-o"
BRIDGE CRANE
ALTERNATIVE
[T.O.RAIL EL40.5'
rELc10'
90 MW FRANCIS UNIT
POWERHOUSE SHT. 1
FIGURE 6.2-5
UNIT 2 UNIT 1
=o
-~
UNITS
I
PLAN-FLOOR EL. 20'
0 , .. ,.. ....... I
SCALE IN FEET
UNIT 2 q UNIT 1
2<0-o" 37'-o' 35'-o•
331-01
' 37'0" 27'-0'
! !
PLAN-FLOOR EL-10' ...
SCALE IN FEET
=o
-~
UNITS
·-. .i
~:.i. .. :
GENERATOR
BUS VAULT
UNIT 2
25'-o"
,_
PLAN-FLOOR EL. 2' . , .. ,..
N I
SCALE IN fEET
EQUIPMENT DATA
1 GENERATOR 14 SPHERICAL VALVE CONTROL
2 CONTROL PANELS 15 SPHERICAL VALVE ACCUMULATORS
3 GENERATOR BREAKER 16 UNIT SERVICE WATER PUMPS
4 GENERAlOR POTENTIAL 17 FIRE PUMPS
TRANSFORMER 18 AIR COMPRESSORS
5 NEUTRAL TRANSFORMER 19 AIR DRYER
6 DIESEL GENERAlOR 20 AIR TANK
7 STATIC EXCITATION 21 WATER PURiFICATION EQUIPMENT
8 GOVERNOR ACTUATORS 22 WATER TREATMENT
9 GOVERNOR OIL ACCUMULATORS 23 DOMESTIC PUMPS
10 GREASING UNITS 24 JOCKEY PUMP
11 MOTOR CONTROL CENTERS 25 HOT WATER HEATER
12 480V LOAD CENTER 26 OIL SER\RATOR
& 480 V SWITCHGEAR 27 SEWAGE TREATMENT MODULE
13 BATTERY 28 AIR RECEIVER
29 UNIT/STATION SUMP
30 DIRTY WATER SUMP
UNIT1
NOTE:
BATIERY
ROOM
ELEVATIONS SHOWN ARE ON
PROJECT DATUM.
MEAN SEA LEVEL DATUM= PROJECT
DATUM PLUS 4 •. 02 FT.
ALTERNATIVE
90 MW FRANCIS UNIT
POWERHOUSE SHT. 2
FIGI JRI= A ~-R
800~------------------------------------------------~
700
600
300
200
• I
II ..
II .,
It
II
I I
I I
I I
I I
I
I
I AVERAGE 484
. -------\-
---~----------------\-
' AVERAGE 476_j
---MEASURED WITH BASIN
ADJUSTMENTS
----CORRECTED FOR ESTIMATED
GLACIER INFLUENCE
100~~--------~--------._--------~------_.--------~
1960 1965 1970 1975 1980
WATER YEAR (OCT-SEPT)
STREAMFLOWS -BRADLEY RIVER AT BRADLEY LAKE
------------FIGURE 6.3-1
Cl)
u.
0
~
..J u.
150
130
110
90
70
50
30
1-
1-
1-
1-
1-
1-
1-
I I
JAN FEB
I I I I J I I I I
MAR APR MAY JUN JUl. AUG SEP OCT NOV DEC
TIME -MON"f:I-IS
RECOMMENDED INSTRIEAM FLOWS
'---------------'-·----FIGURE 6.3-2
7
DETAILED PROJECT
DESCRIPTION
7. DETAILED PROJECT DESCRIPTION
7.1 ACCESS FACILITIES
7 .1.1 General
The permanent access facilities for the recommended plan, shown on Plates
4, 5, and 6, include the access channel and barge basin, airstrip, and
project roads including:
o Airstrip to powerhouse
o Powerhouse to lower camp (via barge basin and staging area)
0
0
Lower camp to upper camp areas
Upper camp to dam (via intake gate shaft,
construction diversion tunnel)
spillway, and
A temporary road will be constructed between the lower camp and the Martin
River material borrow site. This temporary road will be used during
project construction but will be later removed and the surrounding terrain
rehabilitated. Parking, lay down and storage areas will be used for
helicopter access. Access to the Middle Fork Diversion dam will be by
helicopter only. Under the recommended plan it was determined that
satisfactory operation of the turbine units would be achieved without the
need for a surge shaft. Therefore, the access road needed for the
development of the surge shaft has been eliminated.
The feasibility level engineering and design studies and the costs
developed for the permanent access facilities were prepared by R&M and are
given in greater detail in Appendix B of this report.
7 .1. 2 Barge Basin and Dock
Movements of heavy, bulky equipment, construction material and parts to the
Bradley Lake Project site can be accomplished economically and with a
minimum of social and environmental impacts by waterborne transportation.
7-1
Barge transport allows material and equipment to be prefabricated, largely
~reassembled or modularized at the manufacturer's or fabricator's shop
which accelerates field installation. To accommodate the use of sea going
barges to support the project construction a small harboring facility or
barge basin is required at the project site. Homer, strategically located
at the mouth of Kachemak Bay is approximately 27 miles from the project
site and would serve to refuel, and provide shelter and services to sea
going barges and tugs enroute to and from the project site. Kachemak Bay
is characterized from Homer by "deep water" for 15 1/2 miles, shallow
conditions for 3 miles, and tidal mud flats for the final 1 1/2 miles to
the project site. To accommodate barge traffic, improvements in the 1 1/2
miles approaching the project are required. These improvements include
dredging to a depth sufficient to allow sea-going barge and tug traffic;
channel markings; barge docking and off loading facilities; and a materials
lay down area. In addition, the inclusion of small boat facilities within
the barge basin are desirable for construction, and maintenance and
operations personnel use.
In Kachemak Bay, prevailing winds are from the north during winter and
southwest during summer. Summertime windspeeds from the southwest were
found to be 35 to 65 percent higher at Sheep Point than at Homer due to
funneling effects of the terrain surrounding Kachemak Bay. Wintertime
windspeeds were considered equivalent at Sheep Point and Homer since the
wind direction does not promote a funneling effect. Table 7. 1-1, Design
Wind Speeds at Sheep Point, presents 1 and 12-hour duration winds for
exceedance intervals of 2, 5, and 50 years. The summer southwest winds are
relatively strong and have a duration which can affect off loading
operations. SWEC concurs with the COE that a barge basin sheltered from
southwesterly winds is required. Waves associated with the predominant
winds were estimated and are presented in Table 7.1-2. Design wave heights
are shown at frequency intervals of 2, 5, and 50 years for Sheep Point and
Chugachik Island. Tidal exceedance curves were generated by the COE based
on 1982 predictions of the Seldovia Station. These curves were
together with the wave estimates. Wave estimates by the COE
studied
may be
conservative with regard to the actual frequency of occurrence due to
differences between assumed and actual tidal elevations caused by
?-2
continuous tidal fluctuation. Additional study is required to confirm this
observation. Observations of Landsat photography and conversations with
tug captains familiar with Kachemak Bay conditions led the COE to the
conclusion that floating and shore-fast ice should not impact winter
shipping movements to the project site. Bottom-fast ice may be produced in
the shallow channel which would connect the bay and the barge basin. The
bottom-fast ice may be produced by increased formation of frazil ice and
adherence in the channel resulting from greater fresh water flows into the
Bay from power generation, or the growth of surface ice lenses between high
tide periods during extreme cold weather.
The operational considerations for the barge basin-dock facilities involve
two aspects; barge and tug sizes, and material and equipment
movements across the dock. A design barge of size 250 ft.
beam by 10 ft. draft, and design tug of size 90 ft. length
by 10 ft. draft, were selected based on standard Alaska
quantities
long by 76
by 30 ft.
practice.
and
ft.
beam
The
handling of material and equipment during barge unloading and loading
operations involves roll-off, pass-pass, and crane lift operations.
Roll-off operations involve movement of wheeled or tracked vehicles from
the barge via a reciprocating off-loading ramp to an earthen ramp rising to
the staging area. Pass-Pass operations include barge off-loading via two
fork lift trucks, one working on the barge deck passing the load to the
other on the dock. The dock fork lift truck would transport the load to
the staging area. Crane-lift operations would supplement and support
roll-off or pass-pass unloading operations.
Channel excavation on the tidal mud flats is probably not feasible
in-the-dry due to the soft silty clay, sandy silt and clayey silt deposits
which predominate. Excavatio~ by either barge mounted clam-shell or
hydraulic suction dredging during tidal periods when sufficient water is
available to float the dredge is anticipated.
Sedimentation in the access channel and barge basin was studied, but
insufficient data exists to make an accurate quantitative determination of
the sedimentation rate. A quantitative refinement of the rate of
sedimentation in the access channel and barge basin is required which
7-3
should include water sampling and tests at the various tide stages,
developing a sedimentation model for predicting sedimentation rates and
maintenance requirements, a study of the potential for channel side slope
erosion, and the effect of the tidal currents as a source of bed load
sediments.
The COE published "Bradley Lake Hydroelectric Project Final Environmental
Impact Statement 11
, August 1982, which identified that marine mammal, and
waterfowl are the most affected life forms by the construction of the
access channel and barge basin. The FEIS indicates that any dredge
disposal areas on the tidal flats are to be redeveloped into waterfowl
habitat at an appropriate time during construction and that such a measure
would enhance the nesting habitat of the tidal flats which is currently
non-productive due to periodic tidal submergence. During the first year of
construction, to accommodate migrating shorebirds, all dredging, dock, and
road construction on the tidal flats would cease from May 1 through 15, in
accordance with U.S. Fish and Wildlife service recommendations. The
recommended dredge spoil disposal area. is located between the powerhouse
access road northeast of Sheep Point and the shoreline. The disposal area
results in the-loss of approximately 40 acres of sedgegrass vegetation.
The spoil will be contoured and seeded to enhance waterfowl nesting habitat
as discussed in the FEIS. The details of the disposal area have not been
developed. Agency consultation and further study of the dredge spoil
disposal area will be conducted during the preparation of the FERC License
Application.
The access channel from Kachemak Bay to the barge basin has a 200 ft.
bottom width. This selection is based on a 1/2 knot tidal current. A
turning basin width of 350 ft. was chosen to accommodate the length of the
longest barge (up to 343 ft.) using the project facility. To accommodate
10 ft. draft barge movements on 99 percent of all high tides, , or 49
percent of all hourly tidal stages, dredging would be to bottom elevation -
14. Due to the depth and extent of the "shallows 11 at the head of the Bay
near the Project site, deepening be~ond elevation -14 would require
impractically large dredging quantities to improve the functional value of
the barge facility.
7-4
In order to provide crane hook coverages to most of the design barge deck
surface area, dock dimensions of 200 ft. length by 50 ft. width are
provided. The dock is of timber pile supported deck construction, Plate
6. This type of dock has several advantages including:
o Short construction time
o Constructed of readily available material
o Allows phased construction
o Environmental impacts are limited
A reciprocating barge off-loading ramp is provided to allow roll-off barge
unloading through the full tide cycle. The ramp is 68 ft long and 20 ft
wide and is a single span bridge resting on one end upon the barge deck and
pivoting on the shore end on a pile supported concrete abutment. Above the
pile supported abutment is a concrete log surface ramp having a maximum 15
percent grade up to the staging area at elevation 18. The small .J:>oat
launch ramp is built of granular material placed in the barge basin: and
surfaced with concrete logs. The ramR has a maximum 15 percent grade up to
the staging area at elevation 18.
The staging or laydown area, and dock access roads are constructed of well
compacted graded granular borrow material placed upon the tidal mud flat
north of Sheep Point. These soil pads are to be built north of the slough
oriented east to west at Sheep Point. A 100 ft long, single lane bridge
crosses over the slough to connect the barge basin facilities and the lower
camp to powerhouse access road.
7.1.3 Access Roads
The access roads required to support construction of the major project
structures and later operations and maintenance are as follows:
o Airport to Powerhouse
o Powerhouse to Lower Camp (via barge basin and staging area)
o Lower Camp to Upper Camp
o Upper Camp to dam (via intake gate shaft, spillway and construction
diversion tunnel)
7-5
The general layout plan which shows the interrelationships of the access
roads and project structures is shown on Plate 4. Typical road
cross-sections are included in Appendix B. The recommended road types
should allow required access and permit economical construction of the
~pro-j-e-ct~stru-ctures~. ~A~two----l~an-e~ro-a-d~tn-a-h~i~gh_t_r_a_f~f-i-c-are-a-ancl.~s-ingle-1-ane
road in a low traffic area is warranted. The road to the surge shaft will
not be required under the preferred plan.
Critical data considered in the conceptual design of the recommended road
system were as follows:
Two Lane Single Lane
0 Design Speed, mph 20 20
0 Lane Width, ft 12 12
0 Shoulders, ft 2 2
0 Horizontal Curves
(Minimum Radius), ft. 100 100
0 Sight Distances, ft. 150 300
o Vertical Curves
To be calculated in accordance with State of Alaska DOTPF Highway
Preconstruction Manual Procedure 11-10-5. Value dependent on design
speed and grade difference. Note: "K" value for a single lane two
direction road is four times that for a two-lane road.
o Grades
Desirable 10%
Maximum 14%
o Super elevation
Not to exceed 6%
o Cross Slope
0.02 foot per foot
7-6
o Clearing and Stripping
5 ft from edge of cut slope or 10 ft from toe of fill
o Surfacing
2.in. minus gravel
o Culverts
'24 in minimum CMP
Construction of the access roads is important in order to allow the
movement of equipment, men and material throughout the project site. To
permit the earliest commercial operation dates for the project, it is
necessary to construct the roads in one season. To accomplish this
schedule the roads must be constructed concurrently, and in the case of the
road between the lower camp and the dam, from several staging locations
enroute with helicopter support to accelerate progress.
The development of an airstrip is proposed under the recommended plan. The
location of the airstrip as recommended by the COE, north of the powerhouse
is a good general location. Further study indicates that approximately
1000 ft of road savings are possible on the airstrip access road length by
locating the landing strip 500 ft closer to the powerhouse location with a
runway alignment of 23/5, and locating the parking apron in a natural bay
on the southern one third of the landing strip. The access road to the
airstrip from the powerhouse has an overall road width of 18 ft allowing
single lane traffic. An 18 feet road width provides suitable and
economical access to the airstrip. The alignment follows the coastline
utilizing slight cuts and associated benching. This alignment minimizes
the opportunity for settlement, which could be significant in the tidal
clay areas in the adjacent mud flats; and takes full advantage of the
higher natural ground relief to reduce the embankment material.
The access road from the powerhouse to the lower camp will be subject to
high traffic volume during construction and is a two-lane road. Overall,
the alignment suggested by the COE is satisfactory. The changes in the
alignment that have occurred have to do with setting the powerhouse and
7-7
tunnel portal, and relocation of a section of road northeast of Sheep Point
to incorporate the barge basin dredge spoil disposal area. The road design
elevations provide 0. 5 ft of freeboard for the fifty year design wave.
Armor is provided to prevent roadside slope deterioration on the Kachemak
Bay side. At this time there is insufficient soils information available
for determination of expected settlement in those portions of the access
road which are located on the tidal clay deposits in the mud flats.
Settlements as large as 2 ft in those areas underlaid with deep fat clay
can be expected and further settlement analysis prior to final design are
required. Conservative borrow quantities have been assumed, but it should
be noted that 2 ft of settlement represents an increase of nearly 25
percent in borrow quantities. The magnitude of the expected settlement is
related to the soil properties, layer or bedding thickness, real or
apparent preconsolidation and the loads imposed. Further consolidation
testing and field determination of the layer thicknesses of the fined
grained soils will be necessary prior to the road embankment design. The
use of Martin River borrow material for the road bed embankment has been
assumed for cost estimating purposes. Ground surveyed topographic mapping
with cross-sections constructed at 100 ft intervals were used to establish
reliable embankment quantity take off data for cost estimating purposes.
The access road from the lower to the upper camp will be subject to high
traffic volume during construction of the construction diversion, main dam,
spillway, and power conduit intake works. A two-lane road is recommended.
The road is a combination of cut and fill type of construction. The lower
section road bed along the tidal flats will be constructed with borrow
material from the Martin River. The steeper relief sections will be almost
entirely of cut construction to establish road benches and switchbacks in
rock and then surfaced with selected Martin River borrow gravel. This
access road is heavily forested between the lower camp and approximately
elevation 1500. The route is characterized by steep side slopes and
shallow soils over bedrock. Large quantities of rock excavation are
required, but much of this excavated material can be used in the fill
portions of the road, and excess cut material can be placed in areas
designated as disposal areas or at switchbacks and turnouts. Based upon
preliminary examination no avalanche hazards have been identified, but more
7-8
investigation is required. It is anticipated that this road would be
constructed in stages to allow early access to the dam site. The initial
stage would be a single lane pioneer road which would be subsequently
improved to the final two lane road. To expedite road construction several
work areas would be established along the road route to allow accelerated
cutting and grubbing and later rock excavation.
The access road from the upper camp to the dam will be subject to high
traffic volume during construction of the main dam, spillway and power
conduit intake works. A two-lane road is recommended. This road is of cut
and fill construction, and surfaced with selected Martin River borrow
gravel. The route traverses intermittent areas of exposed bedrock,
colluvium, talus, till, and some areas of peat bogs at the lakes and
undrained depressions. Bedrock cuts will be required, and the excavated
material used in fill embankment sections with excess material hauled to
local designated disposal areas.
A temporary haul road is required to transport granular fill, select
gravels and concrete aggregate from the Martin River borrow area. The COE
proposed alignment is reasonable and the location of the bridge crossing
Battle Creek was not changed. After crossing Battle Creek the route stays
clear of the outwash fan by following higher terrain to the east. The
route continues crossing a rather large tidal flat drainage slough where
use of a drainage culvert is possible. No rip rap protection or gravel top
course are included. The top of the road has been located at elevation
12. The terrain on alluvial fans from Battle Creek and Martin River is
approximately elevation 12, and leveling and grading along the road route
will suffice for a temporary roadway surface. A single lane road is
recommended in the fill/borrow road section where the natural relief is
below elevation 12, all other sections of the road would have two lanes for
travelway. Maintenance would be provided on a need basis.
7. 1. 4 Airstrip
An airstrip is included as part of the project works to allow fixed wing
access to the project. The landing strip is located north and adjacent to
7-9
the powerhouse site with a runway alignment of 23/5 as shown on Plate 4.
The layout is consistent with the COE except that a parking apron is
located in a natural bog on the southern one third of the landing strip.
The airstrip will be designed to meet Federal Aviation Administration
criteria for Utility Stage 1. The airstrip geometry is 2,200 ft long with
the centerline grade at elevation 16. The runway will be gravel surfaced
and will accommodate helicopters and approximately 75 percent of all gross
weight fixed wing aircraft under 12,500 pounds. The selected type of
airstrip appears adequate for the foundation materials, but like the roads
in the tidal flats further geotechnical investigations are required to
determine in situ consolidation.
7.1.5 Emergency Access
Permanent Emergency Access throughout the project will be by helicopter
because landing is possible along roads; parking, lay down and staging
areas; and adjacent to each project structure. All-terrain vehicles
including a snow cat are provided with the operations equipment to permit
all weather emergency access, but these would be used as the means of last
resort in view of helicopter speed and accessibility.
7. 1. 6 Permanent Maintenance
The permanent operations and maintenance personnel are provided with
construction heavy equipment as part of the plant operations equipment and
will be able to perform normal and routine maintenance to the roads and
airstrip. In the event of a major landslide, sedimentation of the access
channel and barge basin, or other major unlikely event, the services of a
contractor will be required.
7 .1. 7 Alternatives
Alternatives for permanent site access facilities developed by the COE were
reviewed and other alternates were studied. Detailed discussions of the
alternatives are presented in the report prepared by R&M, included as
Appendix B of this report.
7-10
7 .1. 8 General Geology
This section includes a discussion of conditions at the Barge Basin, along
Access Road alignments, and at the airstrip.
7 .1. 8.1 Barge Basin
The boring performed in the area of the proposed barge basin, SW 83-3, was
advanced ·using rotary wash techniques with'a Simco 2400 drill rig. Samples
were obtained at the base of the advanced casing with either a 3" O.D.
thin-wall sampler (Shelby Tube), or a 2" O.D. split-spoon sampler driven by
a 140-pound hammer falling 30 inches onto the drill rods (Standard
Penetration Test). Torvane shear tests and pocket penetrometer tests were
performed on each Shelby Tube in the field. In addition to the sampling of
Boring SW 83-3, vane shear tests were performed at two depths in the
finegrained material.
An additional shallow boring, numbered SW 83-3A, was drilled adjacent to
Boring SW 83-3 specifically to obtain Shelby Tube samples from zones
interval of Boring S\v 83-3. All of the samples obtained from the barge
basin location were sealed and returned to S&W' s Fairbanks office for
laboratory testing.
The potential stability of the soils in the vicinity of the proposed barge
basin was evaluated by a laboratory testing program on samples from the
single boring location in that area. These soils consist of soft to stiff
silty clay and clayey silt overlying silty and clayey sands.
The sensitivity of the fine grained soils was calculated from the results
of natural and remolded field vane shear tests, laboratory Torvane tests,
and unconsolidated-undrained triaxial compression tests.
Details of the laboratory tests are available in Appendix A. In general,
sensitivity ratios between 3.0 and 8.6 were measured. In one case, a value
of 1.2 was obtained. This may be anomalous since the water content of the
7-11
remolded sample was 3% below the natural content. Triaxial test
(unconsolidated/undrained) maximum unit stresses (20% strain) were as
follows:
Undisturbed Remolded
5 psi 3.5 psi
13.5 psi 5 psi
18 psi 7 psi
Plastic limits ranged between 17% and 23%, while liquid limits ranged
between 24% and 32%.
It appears that soil conditions are adequate to accommodate the proposed
Barge Basin under normal conditions. It should be noted that it would
probably be impossible to prevent slumping of this material if subjected to
the forces of a large or major seismic event.
The test results from soils in the vicinity of the proposed Barge Basin,
while suitable for evaluation of feasibility, should not be used for design
purposes. In addition to possible variation of soil types between
locations in the tidal flat deposits, not all representative soil types may
have been sampled or tested at this given location.
7. 1. 8. 2 Airstrip
Soil conditions at the airstrip are anticipated to be similar to those at
the Barge Basin, described above. Since the site is somewhat closer to the
mouth of the Bradley River, slightly coarser-grained materials may be
encountered. No subsurface exploration has been done at this location.
7 .1.8.3 Access Roads
In general, road alignments on side slopes will involve near-total or total
excavation in slightly weathered to fresh rock with only a few feet of soil
cover. In valley bottoms and similar low points, glacial and/or alluvial
soils up to several tens of feet thick may be encountered; in places these
7-12
may be covered by swamp-like peat deposits. While the glacial and alluvial
soils should provide adequate subgrade conditions, it may be necessary to
completely remove peat and associated organic deposits and replace them
with a suitable fill. Roads constructed on or adjacent to the tidal flats
of Kachemak Bay will encounter conditions similar to those described for
the Barge Basin, above.
7-13
7 . 2 DAM AND SPILLWAY
7 .2.1 General
A concrete faced rockfill dam has been selected by the project team as the
most technically and economically suitable structure for increasing the
storage capacity of the Bradley lake reservoir.
Geologic investigations were conducted along the axis of the proposed dam
and its abutments. The findings of these investigations indicate that the
site conditions are favorable for construction of the rockfill dam. The
proposed dam has an upstream concrete face and the conceptual design has
been conservatively developed to resist all expected loads.
An ungated concrete gravity ogee spillway will be located within the saddle
of the right abutment and founded on bedrock. It has been designed to pass
the Probable Maximum Flood without overtopping the main dam.
7.2.2 Dam and Spillway
A plan of the main dam, spillway, and associated structures is shown on
Plate 7. The layout and conceptual details of the dam and spillway are
shown on Plates 8 and 9, respectively.
The axis of the recommended dam is approximately 520 feet downstream of the
lake outlet. This location and the axis orientation were selected to best
utilize existing topographical features and to minimize rockfill quantities
for the embankment structure. The selected location also makes effective
use of previously obtained geologic data and allows for the development of
the embankment within the restricted area of the river. The axis
orientation offers good alignment for the upstream toe slab, and results in
toe slab construction without excessive three dimensional discontinuities.
In addition, the alignment balances the upstream and downstream road access
requirements for construction of the dam.
7-14
The dam has a crest 18 feet wide, 610 feet long, at elevation 1190 and a
height above the lowest average foundation level of 125 feet.
The rockfill embankment section conceptual design is conservatively
de"<aloped with selected zoned material to withstand hydrostatic, ice,
earthquake, and other external loads. The dam is developed using three
zones of material compacted to form upstream and downstream embankment
slopes of 1. 6H: 1V. Zone 1, forming the upstream face of the rockfill,
consists of selected 6 inch minus material. This zone is placed in 15 feet
wide horizontal layers of one foot lifts and is compacted with heavy steel
drum vibratory rollers. Zone 2 forms a highly pervious drainage band at
the base of the central section of the dam. This zone is composed of
selected 6 inch to 24 inch material placed in 3 foot lifts and compacted
with vibratory rollers. Zone 3 is quarry material placed in 18 inch lifts
and compacted with vibratory rollers. Material placement within this zone
will be such as to direct the better quarry material to the upstream.,,half
of the zone. Larger or oversized material will be pushed to the downstream
face. A total of 362,000 cubic yards of rockfill is required in the dam.
Use of the proper material gradation in these selected zones, coupled with
controlled placing techniques, proper spreading and compacting, and
controlled use of water to improve workability results in an embankment
that is stiff and able to withstand the forces on the dam with minimum
deformation. The gradation of the material within the selected zones
distributes contact forces with smaller size material occupying the voids
between larger rock pieces locking both into position. At the same time
adequate space is provided within .the rockfill to assure high permeability
for the drainage of surplus water.
The upstream face of the dam consists of a parapet wall, concrete face
slabs, and toe slabs. The concrete parapet wall, extending 4 feet above
the dam crest, is provided with a curved upstream surface to act as a wave
deflector.
7-15
The impervious upstream face is formed by a series of reinforced concrete
slabs. Central face slabs have been conceptually designed as 50 foot wide
monoliths. Abutment face slabs are narrower and articulated to provide
freedom of movement and to accept greater deflections. The slabs are
conceptually designed to have a nominal thickness of 12 inches at the top,
near the parapet, varying uniformly to a maximum thickness of 18 inches at
the lowest elevation of the dam. Concrete toe slabs are constructed to
connect with the face slabs and to form the watertight closure between the
upstream heel of the embankment and its rock foundation. A grout curtain
is placed under the toe slab for a seepage cutoff in the bedrock.
Approximately 8,900 cubic yards of concrete are needed in the construction
of the upstream face slab of the rockfill embankment dam. This is about 11
percent of the amount that would be required for a concrete gravity dam.
The smaller quantity of concrete reduces the quantity of aggregate material
that would have to be taken from selected borrow areas at the Hartin River
Delta.
The rockfill embankment is developed in an essentially continuous
operation. Haterials for its construction are readily available from
quarry sources adjacent to the structure. Concrete mixes particularly
suitable for cold and harsh environments will be used in the construction
of these members, offering excellent resistance to freeze-thaw action, ice
buildup, and strains resulting from seasonal temperature variations.
An ungated concrete gravity ogee spillway is located on the saddle feature
approximately 150 feet to the right of the main dam and along the same
general alignment. The overall length of the spillway including abutments
is approximately 220 feet of which 165 feet is provided for the overflow
crest. The height from foundation level to the crest varies from SO feet
at the central portion to about 15 feet at the left.
The spillway is founded on bedrock with its concrete gravity abutments
. keyed into the adjacent rock. It is estimated that approximately 17 feet
of overburden and weathered rock will be removed in the central portion
with the excavation tapering to either side. A 30 feet deep grout curtain
will be developed along the spillway below foundation level and extend
westward from the right abutment to the main dam. For added safety, a
drainage system is provided downstream of the grout curtain. The system
consists of vertical drain holes drilled into foundation rock, a collector
pipe, and a lateral pipe discharging seepage into the spillway chute.
Also, provisions are made to access the drain holes for cleaning or
re-drilling.
The spillway is similar to the COE's design with rounded abutments and an
upstream sloping face. The crest is shaped and contoured to produce a
gradually accelerating flow on the basis of a 10 feet design head.
The spillway chute directs the discharge onto the exposed rock and into the
large natural pool downstream. Erosion of the soil cover will occur,
however, once the soil mantle is removed little erosion should occur in the
exposed bedrock. A concrete training wall is located on the left side to
direct the discharge away from the diversion tunnel outlet. The spillway
chute is divided into two sections, a downward sloping section on the left,
55 feet wide, and a llO foot wide section on the right. This avoids
unnecessary rock excavation and helps in dissipating the energy of the
flow. Although flow velocities could be high as the flow is directed
across the toe of the main dam into the streambed, heavy rip rap armor is
placed in this area to avoid serious erosion. In addition, the cost
estimate contains funds for model testing this aspect and includes an
allowance to cover the cost of providing additional energy dissipating
devices.
7.2.3 Hydraulics
Hydraulic aspects of the recommended spillway are basically the same as
I . those in the COE s report. The 165 foot long ogee shaped free flow crest
will be capable of passing the routed Probable Maximum Flood and Standard
Project Flood with 10.6 and 5.6 feet heads respectively, assuming the
powerplant and permanent outlet facilities are inoperable.
7-17
Although the crest elevation has been raised 10 f·eet above the GOE' s, the
effect of the increased surcharge storage of the lake at the higher
elevation on the outflow discharge was found to be negligible. The flood
routings are shown on Plate 18.
PMF Flood routings were also made assuming one half of the total powerplant
hydraulic capacity would be available in one case, and in addition, the
full capacity of the permanent outlet facilities above elevation 1185 lake
level in another case. The results indicate a decrease in the routed peak
outflow about equivalent to the total assumed additional hydraulic capacity
available, with corresponding decreases in maximum lake levels. These
results are not utilized, however, as they are considered as additional
freeboard safety factor for the dam.
Future studies should investigate the hydraulic aspects and structural
stability effects of shaping the crest on the basis of a design head less
than 10 feet. This would increase the discharge efficiency of the
spillway, but at the expense of increased loads due to pressure reduction
on the downstream side at heads exceeding the design head. The effect on
structural stability however, is expected to be minimal.
7. 2. 4 Selection of Dam Height
Wave analyses were made to determine the freeboard requirements of the dam
under the simultaneous occurrence of waves induced by 70 mph winds, normal
maximum water level, and the passing of the Standard Project Flood (SPF).
A significant wave height of 4 feet was computed for a sustained wind speed
of 70 mph over a fetch distance of 1. 6 miles. The run-up induced by this
wave on the upstream face of the dam combined with set up in the reservoir
was estimated to be 7.5 feet. This produces a required freeboard
allowance, when combined with the SPF surcharge level, of 14 feet above the
spillway crest level. The crest of the dam was set 10 feet higher than the
spillway crest with a 4 feet high wave deflector wall on the upstream face
to provide the estimated freeboard. Maximum water level attained during
passage of the Probable Maximum Flood was checked to ensure it was within
the selected freeboard.
7-18
The above criteria are less severe
b~lieved to be too conservative.
than that used by the COE which is
The combined probability of the
simultaneous occurrence of the high winds aligned in the direction of the
dam along the critical fetch, occurrence of a flood equivalent to twice the
flood of record, and the maximum reservoir elevation is considered to be
small. The reservoir regulation studies show that maximum reservoir
elevation will occur predominantly in August and September, prior to the
expected maximum winds. Available wind data, although limited at the site,
indicates higher wind speeds in the October through April period during
which time the reservoir is expected to be ice covered.
Obviously, the subject of freeboard requirements is subject to the
uncertainties of many combined events. The data currently being gathered
at the site should be thoroughly reviewed in determining the final
freeboard requirements. Analysis of the data should remove some of the
uncertainty and result in a more economical structure.
The recommended maximum operating pool level, which has been set equal to
the spillway crest elevation of 1180, when added to the estimated freeboard
requirements of 14 feet, results in a freeboard elevation of 1194 feet.
Since a 4 feet high wave deflector wall will be provided on the upstream
face of the dam, the dam crest elevation was set at elevation 1190.
7.2.5 Geology and Foundation
Previous investigations indicate that the location of the proposed dam and
intake is in an area underlain by graywacke and argillite. The U.S. Corps
of Engineers have previously conducted investigations in the general area
of the dam. Field checks confirm conditions delineated by the previous
studies. Efforts for this study have been concentrated in the proposed
intake area which differs from that considered by the COE.
The current axis alignment is upstream of the COE alignment and varies from
it by about 25 to 100 feet.
7-19
Since the
conditions
current alignment is close to
at this alignment are nearly
that investigated by COE,
identical. Conditions and
recommendations described below are derived primarily from previous studies
supplemented by field observations during this investigation.
Damsite exploration by the COE included eight holes spaced along the dam
axis. Drilling exploration indicated an alternating sequence of argillite
and graywacke along the entire dam axis. Preliminary studies indicate
generally good overall rock quality. Two 45° angle holes were drilled, one
on the river's left bank and one in the right saddle, with lengths of 249.9
and 201.7 feet respectively. Vertical holes at· the left abutment, left
saddle, left knob, and right dam abutment and saddle penetrated 248. 3,
133.0, 246.9 and 75.1 feet of rock respectively. One short vertical hole
(60 feet) was drilled in the middle of the river.
The right or east abutment at the damsit·e is a continuous outcrop of
massive graywacke, exhibiting poorly developed bedding, in association with
thin lenses of cherty a~gillite. Bedding generally dips at high angles to
the west with a strike of about N 10° E-W. Well developed joints are
present; spacing varies from less than 1 feet up to 10 feet. The two major
joint patterns strike N 60°-70° E and N 45°-55 W. The first has a
predominant dip orientation of 65°-75° SE. Dip angles of these joint
systems form an "X" and appear evenly divided between 60°-70° NE and
60°-70° SW with a few steep dips of 80°-84° NE and SW. Accessory joints
are of minor importance. Overburden appears shallow, with observed depths
of 5 feet or less.
A number of minor shear zones or joint swarms were observed in the general
area. The largest of these is located on the north flank of the left
abutment knob, approximately 150 feet SW of the downstream end of the small
rock island. This fault strikes N 4° E and dips vertically. The shear
zone ranges from 1 to 15 inches wide and contains a small amount of clayey,
silt gouge. A crevice 15 inches to 3 feet wide is eroded 5 to 6 feet back
7-20
from the face of the rock. A possible continuance of the shear zone exists
on the river side of the left abutment knob. This zone is a linear feature
about 3 feet wide at the top, tapering to a soil-filled depression 2 feet
wide. This feature also approximately follows a minor joint trend and has
a strike of N 23° E and dips ·between 48°-59° SE. This fault is a minor
structural feature and is not considered to influence the proposed location
or design of the dam.
Investigations in the right abutment saddle (spillway location) indicate
17+ feet of talus and overburden overlying moderately jointed, fractured
graywacke. Weathering effects persist to the bottom of COE hole DH-33,
(75 .1 feet). Polished, grooved, and straited bedrock· surfaces are present
and are typical of areas recently vacated by ice. The right abutment
appears to be satisfactory for the planned dam and spillway.
Overburden on the left abutment appears generally shallower than on the
..
right abutment and varies from 0.5 to 2.5 feet on the average. COE drill
hole DH-35, drilled in 19 81, indicates a depth of 9. 4 feet of overburden.
Unconsolidated materials appear in the saddles of both abutments. These
materials include talus, sand, gravel, and topsoil.
The left abutment is composed of a more argillaceous graywacke that
contains thin beds of argillite and argillite-graywacke conglomerate.
Aligned, pillow-shaped pieces of graywacke, in a boudinage structure, have
been observed in exposed outcrops 600 feet to the south. COE drilling logs
from DH-5 and DH-16 show alternating argillite and graywacke units and
graywacke with various percentages of argillaceous material. Observed
jointing is similar to that of the right abutment, with major joints
cutting through bedding planes, striking N 55°-80° W and dipping 80° SW to
vertical. Minor localized joints strike N 74° E with dips of from 78°-83°
SE. The left abutment rock conditions are also considered to be
satisfactory.
The dam will be founded on bedrock composed chiefly of alternating
sequences of argillite and graywacke. The in situ rock visible at the
surface in the damsite area is all moderately hard to hard and is
7-21
considered quite adequate to support a rockfill dam. Surficial weathering
is generally confined to the upper few feet of rock; however, staining on
joints and fractures in the rock are potential leakage channels from the
reservoir and provision must be made for seepage control. A grout curtain
is required beneath the toe slab of the dam to control underseepage.
7 .2.6 Access
Access to the dam is provided by the road that connects the upper reservoir
area to the lower campsite, staging, and powerhouse areas. This road is
aligned to also provide access for the gate shaft, described elsewhere in
the report, and to other structures at the upper reservoir area.
Access to the spillway will be across the crest of the rockfill dam and
through a rock cut at the right aubtment. Access across the spillway agee
has been eliminated. Elimnation of this access way and its required
support structures results in improved discharge characteristics, lower
maintenance, reduces the likelihood of structural and flow blockage
problems from icing conditions, and reduces the overall cost for developing
the spillway.
7 .2. 7 Alternatives
The study considered the feasibility of developing a retaining dam using
concrete gravity, rockfill, roller compacted concrete, and a double
curvature arch dam. Preliminary study findings and conclusions were
presented to the Power Authority and preferred alternatives were selected
for further refinement and cost development.
The roller compacted concrete dam structure was eliminated because of
unknowns in the development of a suitable structure that would· provide
watertight construction and adequate resistance across the rolled jointing
planes to resist the seismic loads associated with the area as well as
anticipated construction difficulties due to climatic conditions. The
double curvature concrete arch dam was eliminated because of ecnomics. The
arrangement of the concrete gravity dam is shown by Figure 6.2-2.
7-22
The two types of dams considered for detail evaluation were a concrete
gravity dam and a concrete faced rockfill dam. Each type was investigated
for a storage pool at elevations 1170, 1180, and 1190 project datum.
Design criteria affecting dam stability, dam configurations, and
engine·ering details for each dam type and size were developed and used in
conceptual designs. Engineering sketches showing layouts of likely
arrangement and physical dimensions of each dam type were prepared and used
for quantity estimates. Cost estimates were made for each dam type and
size using conceptual arrangement corresponding to each of the three
different storage pool levels studied.
Spillway layouts applicable to either a concrete gravity dam or a concrete
faced rockfill dam, as evaluated under previous studies, were reexamined.
Alternative arrangements for the development of a suitable spillway
structure were also formulated and conceptualized. Technical and economic
evaluations were made between these alternatives and the previ?~sly
suggested spillway layouts. Study findings were discussed with the Power
Authority and the preferred spillway concepts were selected for further
refinement and cost development. Spillway layouts reexamined consisted
of: 1) a side channel type spillway at the left abutment; 2) a side
channel type spillway at the right abutment; and, 3) a spillway that would
be constructed as an integral part of the dam. The first two types of
spillways would be developed in conjunction with the construction of a
rockfill embankment dam, while all three types would be suitable with a
concrete gravity dam. Alternative spillway concepts developed under this
study considered the construction of a concrete gravity chute type spillway
at the right abutment saddle or the possible development of a fuse plug as
a spillway. These spillway concepts would be applicable for both the
concrete gravity and rockfill dam.
Comparative direct cost estimates of the concrete gravity dam and the
concrete faced rockfill dams, with an overflow spillway at the right
abutment, showed a $4 million to $6 million differential in favor of the
rockfill. The cost of the concrete faced rockfill dam with an ungated
concrete ogee spillway at the right abutment was found to be the lowest of
all the alternatives that were studied. The concrete faced rockfill dam
7-23
was therefore selected in the preferred scheme based upon this cost
advantage, timing for construction and material needs.
7-24
7. 3 CONSTRUCTION DIVERSION
7.3.1 General
Bradley Lake flows need to be diverted or handled in a manner that allows
for the construction of the main dam and other associated structures within
the river channel near the lake outlet. Diversion concepts perviously
identified and their relationship to the development of other water
conveyance and control structures were reviewed. Alternative concepts
representing independent modes of flow diversion were identified and
studied. The ability for providing a suitable permanent low level outlet
and controlled flow releases was also studied. Environmental and
construction attributes were evaluated and conceptual designs prepared for
costing and economic comparisons.
7.3.2 Diversion Tunnel
The recommended method for diverting Bradley Lake flows, during the
construction of the main dam and other related structures, is by a short
tunnel constructed through the right abutment. This concept allows for
passage of flows, as they occur naturally within the drainage system, and
does not require the lowering of Bradley Lake. Also, the diversion allows
for the development of a low level outlet for controlled flow discharges
during the life of the project, as may be required for maintenance or for
downstream aquatic habitat.
The diversion tunnel is an 18 foot nominal horseshoe shaped tunnel about
470 feet long and is shown by Plate 10. The tunnel is constructed during
the late fall/early winter period and is advanced from the downstream
portal towards Bradley Lake using drill and blast techniques. This
construction time period is selected so that the diversion works. can be
made operational by the spring of the following construction year.
The horizontal alignment of the tunnel has been selected such that both
portals can be made accessible to construction, and to respond to
restraining conditions imposed by other nearby structures developed in the
7-25
adjacent areas of the river channel. The vertical alignment is established
to provide the desired flow characteristics while minimizing cofferdarnming
needs at the portals. Only the downstream and upstream portal areas will
be lined prior to diverting flows. This is done to provide structural
support and protection from erosion by flow velocities. The upstream
lining is constructed as an extension of a concrete intake portal that is
designed to accept steel stop logs for closure of the diversion tunnel.
About 8, 300 cubic yards of material will be excavated from the diversion
tunnel and its portals. Excavation for the upstream portal will be spoiled
in the lake adjacent to the portal area. Material excavated from the
downstream portal will be used to improve the construction working area at
this portal. Tunnel excavation will be spoiled in designated waste areas
near the vicinity of the dam.
Subsequent· to the need for construction diversion, the tunnel will be
closed off and completed with the construction of a concrete plug and by
concrete lining the invert and tunnel sides up to the spring line,
downstream of the concrete plug. The low level outlet with its flow
regulating gates is constructed as part of the concrete plug as described
herein. A grout curtain plane is developed around the concrete plug to cut
off seepage flows. The plane is oriented to connect with or complement
similar grout cut off systems developed as part of the spillway and dam
structures. The tunnel between the concrete plug and the concreted
upstream portal section is left unlined. The steel stop logs are removed
when the concreting is completed and the diversion tunnel becomes a low
level outlet. A heavy grillage or other protective device is provided at
the outlet of the tunnel to prevent large animals from using the tunnel as
a habitat area.
7.3.3 Permanent Outlet Facilities
The permanent outlet facilities and fish bypass system is constructed as
part of the diversion tunnel concrete plug. The low level outlet consists
of two 3.5 feet wide by 5.5 feet high sluicing conduits built at the tunnel
invert and extending the full length of the concrete plug. Each sluicing
7-26
conduit is provided with two hydraulically operated slide gates. Within
each sluiceway one gate is considered active and is operated to regulate
flow. The second gate is used in an emergency and if maintenance is
required to the active gate.
7.3.4 Hydraulics
The diversion scheme developed in this study is based on the need to safely
pass the routed peak discharge of a flood which could reasonably be
expected to occur during the time period which the diversion facilities
would be in operation.
The COE study utilized the 1979 flood of record as the inflow design flood
for its diversion scheme. This flood had an average daily peak discharge
of 5210 cfs and an instantaneous peak discharge of 6200 cfs. An inspection
of the COE flood frequency curve indicates a flood of this magnitude would
.'\'
have a probability of being equaled or exceeded of about 10% in any given
year on the average.
The Construction sequence developed in the present study will require the
diversion tunnel to be operational for a period of up to two years. The
1979 flood would therefore have a probability of occurring in this two year
period of about 20 percent. Stated otherwise, there is a 80 to 90 percent
chance that a flood with a peak discharge of 6200 cfs would not be exceeded
during the required diversion period. Based on this, past experience and
judgement, and the relatively short period of recorded flows used in
evaluating the probabilities, the 1979 flood was chosen as the design flood
for construction diversion.
The 1979 flood flows were recorded at the lake outlet under natural stream
conditions. Because of this it was necessary to adjust the recorded
discharge hydrograph to reflect the regulation effect df the lake in
determining the actual inflow. This adjustment was made by reverse routing
the recorded outflow hydrograph and smoothing the resulting estimated
inflow hydrograph shape until it resulted in the recorded hydrograph when
rerouted through the lake. The estimated inflow and recorded discharge at
7-27
the lake outlet are shown in Figure 7. 3-1. An maximum inflow of 6800 cfs
was estimated to cause the 6200 cfs to result at the lake outlet with a
lake level at elevation 1088.5.
The inflow hydrograph thus obtained was then routed by the lake through the
diversion tunnel to determine the peak discharge and surcharge level of the
lake. The results of the routing are shown on Figure 7.3-2. It can be
seen that the peak inflow is attenuated considerably from 6800 cfs to 4000
cfs but the lake level surcharges to elevation 1096.5 reflecting the
smaller discharge capability of the diversion tunnel over the natural lake
outlet.
Based on this surcharge level, the top of the upstream cofferdam and the
bottom of the lowest excavated bench for the dam quarry were set at
elevation 1100 providing 3.5 feet of freeboard.
From a hydraulic standpoint, a large range of tunnel sizes could be
constructed tvhich would pass the design flood. The only practical
differences between the different sizes would be the level the lake would
rise to provide the hydraulic head required to pass the peak discharge.
Smaller size tunnels would result in excessively high lake surcharge levels
which would require very high cofferdams at the lake outlet. The selected
tunnel size will satisfy the hydrologic criteria and result in a reasonable
size cofferdam.
The diversion tunnel was sized to pass the routed peak discharge of 4000
cfs under open channel flow conditions.
To minimize tailwater encroachment and provide additional construction work
area at the outlet portal a small pilot channel will be excavated in the
downstream river bed which will lower the water level in the large natural
stilling pool about 3 feet. The stream channel rating curve is. shown in
Plate 21 and is based on the COE rating curve adjusted for at the lower
flows to reflect the lower water levels in the channel.
7-28
Permanent outlet facilities will be incorporated as part of the diversion
tunnel after construction. The two sluice conduits within the concrete
plug of the diversion tunnel were sized on the basis of providing a minimum
flow to satisfy instream flow requirements and provide sufficient flow
capacity for reservoir drawdown. The facilities are capable of passing
about 150 cfs at the minimum operating lake elevation of 1080 and a maximum
flow of 2750 cfs at the maximum elevation 1180. Flow through the conduits
will change from open channel to orifice flow at a discharge of about 300
cfs with a small hydraulic jump occurring upstream of the plug at the lower
discharges. The rating curve for the permanent outlet facilities is shown
in Plate 21 and represents the flow capacity with both sluice gates fully
open.
7.3.5 Geology
The construction diversion tunnel will be excavated in the right abutment,
passing beneath the left edge of the spillway structure. The tunnel and
portals will be located wholly in massive graywacke with occasional thin
lenses of cherty argillite. This is a sound rock presenting favorable
tunneling conditions. Major joint orientations are also generally
favorable, intersecting the alignment at about 35°-45° and ?5°-85°; dip
angles range from 60° to vertical. Joint spacing ranges from one to. ten
feet; in relation to the tunnel diameter (19 ft horseshoe) this will yield
somewhat blocky ground conditions. A few minor, high-angle shears or
faults are anticipated but are not expected to exceed about 1. 5 feet in
width and are not expected to require any unusual support techniques. In
summary, geologic conditions for the diversion facility are considered to
be favorable.
7.3.6 Structures and Appurtenances
A sluice gate control and equipment house is provided at ground level near
the vertical projection of the diversion tunnel's concrete plug. This
structure contains the hydraulic power pack unit and the air-oil
accumulators needed to actuate the sluice gate hydraulic cylinders. Both
manual and automatic gate control is provided. Manual control is available
7-29
from a control panel within the house as well as from a portable hydraulic
pump at the hydraulic cylinder area. Automatic control is available from a
control panel in the gate house or from the main powerplant. Telemetering
equipment are provided to receive control signals and transmit gate
position data to the powerplant. Electrical power is provided by long life
batteries and a propane generator. The air-oil accumulators are sized to
allow for one close-open-close cycle of the active gate and one
close-open-close cycle of the emergency gate, before recharging is required.
The proposed generator is used to recharge the batteries and to operate the
hydraulic power pack pump motor. Also, this unit will be used to provide
electric power for lighting the tunnel area, as may be required for
inspection and during maintenance. Electrical, control, communication, and
hydraulic line systems are brought from the sluice gate control house to
the gate area and the tunnel through a suitably sized hole drilled to
connect the two structures.
7 .3. 7 Access
Access to the construction diversion tunnel and low level outlet sluice
gates is provided across the crest of the downstream cofferdam. Access
within the downstream tunnel section is by a steel walkway suspended from
the tunnel crown and braced against the spring line. Access to the sluice
gate control house is from the crest of the main dam. The upstream stop
log structure is accessible from the lake by. use of a barge facility. The
tunnel section, upstream of the concrete plug can be accessed either
through the sluiceways, with the steel stop logs in place, or through the
sluiceways and reservoir area, when the power pool is drawn down to its
minimum emergency level at elevation 1,060.
7.3.8 Alternatives
The COE investigated two alternative diversion schemes to their recommended
plan of bypassing the natural inflow through the power tunnel and returning
it to the stream through a branch tunnel downstream. One alternative
consisted of diverting water through a portion of the existing lake outlet
7-30
channel while constructing the dam in the dry streambed behind cellular
cofferdams. This was abandoned due to excessively high cofferdam
requirements. SWEC agrees that this scheme is impractical. The other
scheme studied by the COE involved a pressure tunnel through the right
abutment and this was also discarded due to excessive cofferdam heights.
SWEC agrees that a pressure tunnel would not be feasible at this site. The
COE recommended diversion scheme was also discarded in this study since it
is an integral part of the power conduit arrangement which has been
abandoned for other reasons.
Several other diversion schemes reviewed in this study included tunnel
arrangements through the right and left abutments at the lake outlet, and a
buried conduit through the main river channel. Arrangements through the
left abutment with variations in details were abandoned due to interference
with other structures, impacts on the construction schedule, and excessive
costs. The buried conduit scheme through the main river channel was also
discarded due to excessive costs, technical difficulties in constructing a
suitable inta~e structure, and excessive cofferdam heights.
An alignment through the right abutment was judged the best in terms of
satisfying both temporary diversion capabilities and permanent low level
outlet requirements. Initial concepts included analyzing 16 and 18 foot
diameter horseshoe shaped fully.lined tunnels. The 16 foot diameter tunnel
was abandoned because it was judged too small to ensure proper hydraulic
performance while passing the design flood and resulted in larger cofferdam
sizes which would encroach on the available construction working areas for
the permanent structures. The 18 foot diameter fully lined tunnel was
found acceptable in meeting the various criteria and was initially
adopted. However, further studies indicated that use of an initially
unlined tunnel for diversion during construction would enhance construction
scheduling needs and would be more economical. Partial concrete lining of
the tunnel would be done subsequent to diversion. This concept was
subsequently adopted for the recommended plan.
7-31
7 . 4 POWER CONDUIT SYSTEM
7.4.1 General
The power conduit is defined as the water passage structures that are used
to bring water from the Bradley Lake to the turbine-generator units. These
structures include the intake channel, the power intake, the gate shaft,
the power tunnel and steel liner, and the penstock.
Previously identified concepts were reviewed and new concepts developed for
study. The new concepts considered relocating the power conduit intake to
the left abutment area, straightening the power tunnel alignment, and
placing the majority of the tunnel at a level which provides over 1000 feet
of rock cover for resisting the internal pressures.
The merits of lowering the tunnel to eliminate the long exposed penstock
along the mountain slope were evaluated. The feasibility of using a tunnel
boring machine was investigated arid economic analyses were performed to
determine hydraulic losses and economic diameters of the water flow conduit
sections.
Hydraulic transient analyses were performed to determine pressure
characteristics and surge shaft requirements under full load rejection and
acceptance conditions. Consideration was given to
underground surge chamber. These studies and economic
alternative turbine types concluded that a surge shaft is
suppress hydraulic transients under the preferred plan.
a pressurized
comparisons of
not required to
The water conveyance structures forming the power conduit are described in
detail in the write-up which follows.
7-32
7.4.2 Power Conduit System
7. 4. 2. 1 Intake Channel
The intake channel developed for the preferred plan is excavated as part of
the rockfill dam quarrying operations. The channel is approximately 360
feet long and 50 feet wide at its base. The channel connects the power
tunnel intake structure and Bradley Lake and is shown on Plates 7 and 11.
During construction of the channel and other power conduit structures,
water would be blocked from entering the work area by a rock plug; a large
unexcavated rock section at the lake end of the channel. An invert at
elevation 1,030 is selected and allows drawing the reservoir down to
elevation 1, 060, as may be required for maintenance of the dam or for
additional generation under emergency conditions. This minimum drawdown
elevation is selected to provide adequate submergence of the intake
structure and for keeping the water flow velocity in the channel to JL.less
than 1 fps during full power generation. The low velocity reduces
hydraulic losses; minimizes the attraction of waterlogged debris; and,
allows for the build up of an ice layer which is desirable to preclude the
development of frazil and anchor ice within the channel. Rock traps are
being provided along the length of the channel and in front of the intake
structure to retain loose rocks that may fall from the excavated slop~s or
may be transported by ice. About 74,000 cubic yards of material will be
excavated to form the intake channel. Of this, over 52,000 cubic yards
will be used as part of the dam rockfill. Of the remaining 22,000 cubic
yards, about 12,500 cubic yards of excavation is from the rock plug
cofferdam. Most of this material will be excavated in a manner that will
place the material in the lake area adjacent . to the channel to form a
protective rock-mantle along the lake shoreline. The remaining excavation
will be spoiled in waste areas designated in the vicinity of the dam.
7 .4.2.2 Intake Structure
The intake is a concrete lined structure shaped to form a gradual
contracting transition, varying from a rectangular shape at the intake
channel to a full circular section where it connects with the upper section
7-33
of the power tunnel, Plate 12. The intake is formed by a 490 cubic yard
excavation along the side of the intake channel. The total transitional
length of the intake is about 42 feet. Removable trash racks are provided
at the inlet to prevent floating debris from entering the power tunnel.
The total gross area of the trash racks is about 460 square feet, resulting
in an average velocity through the trash racks of less than 3 pfs, at full
power flow.
The trash racks are supported in guides at the sides of the intake
structure and by a vertical concrete pier located at the upstream center of
the structure. The trash rack guide system is designed to accept steel
stop logs should the need arise. Access to the trash rack is by barge from
the lake, at high reservoir levels, or directly by crane from the adjacent
quarry benches, when the reservoir is drawn below elevation 1, 100. The
entire intake is submerged below the minimum emergency drawdown pool of
elevation 1,060 to prevent air entrainment during generation. However, it
is recommended that hydraulic model tests be performed of the intake
channel and the intake structure to determine acceptable flow conditions.
7 .4.2.3 Gate Shaft
Emergency closure of the power conduit is provided by two hydraulically
operated slide gates located in a gate shaft. The gate shaft, shown on
Plate 11, is a vertical, concrete lined, circular shaft with an internal
diameter of 22 feet.
The shaft is located over the tunnel alignment, about 800 feet downstream
of the intake portal. The top of the shaft is at elevation 1203 feet and
the shaft extends into the ground for about 173 feet, to the invert of the
power tunnel. The shaft will be developed by raised boring and slashing.
About 2,500 cubic yards of material excavated to form the shaft will be
spoiled in the waste areas designated in the vicinity of the dam.
The concrete lined shaft will form a dry well for the two hydrauLically
operated slide gates and other equipment. The gates, each 9 feet wide by
11 feet high are installed in tandem. The downstream gate is considered
7-34
the active gate and will be used in the event of an emergency to close off
flow in the power tunnel. The upstream gate is considered passive and is
primarily used when there is a need to service the downstream gate. Both
gates will be used when maintenance of the power tunnel conduit is
required. An access way is provided downstream of the active gate to allow
entrance to the power tunnel. Suitable venting is also provided on the
downstream side of each gate to vent the water passages to above ground
level. Access to the hydraulic cylinders and gate area is provided by
spiral stairs or other suitable means.
A platformed area is provided at elevation 1170 for major maintenance to
the gates. This platform is made from structural steel shapes with grating
and checkered plate covering. Access to the gates and to the maintenance
platform is through openings at the top of the gate shaft structure. An
equipment platform, of similar construction, is provided at elevation
1190. This platform will support the equipment needed to control, mon~tor,
and operate the gates such as: a control panel for manual and remote ,gate
operation; long life battery and propane generator; the hydraul:i,c power
pack and air-oil accumulators; and, other telemetering and communications
equipment. Separate air-oil accumulators are provided for each gate.
These are sized to allow one closeopen-close cycle before recharging is
required by the hydraulic power pack. The propane generator is sized to
provide the power needed by the power pack for lighting within the gate
shaft during maintenance and for recharging the battery. Access to the
gate shaft from the outside is provided by a concrete stairwell, leading to
the equipment platform, and by a steel stairway that connects the two
platformed levels.
7 .4.2.4 Power Tunnel
The power tunnel is an 11 foot nominal diameter, concrete lined, circular
conduit as shown on Plate 12. Starting at the intake, the tunnel extends
horizontally downstream for about 950 feet to a 38 feet long bend that
connects to a 810 feet long concrete lined shaft inclined at 55° with the
horizontal. A similar bend connects the inclined shaft to the main power
tunnel. The main power tunnel is 16,850 feet long and includes a 2, 400
7-35
feet concrete and steel lined section. The invert of the tunnel at the
downstream portal is set at elevation 42 feet. The vertical alignment of
the main tunnel was limited to a grade of 1 foot in 600 feet for safety of
personnel during mucking operations and to enhance the productivity of its
excavation. A minimum of one foot thick concrete lining is used throughout
the entire tunnel length, including the steel lined section, the inclined
shaft, and the upper horizontal section. Reinforcing is provided within
the concrete lined sections along the lengths crossing known faults and at
the lower and upper bends. The steel lined section of the tunnel is not
reinforced.
The power tunnel is developed by drill ·and blast techniques, raised boring
techniques, and by the use of a tunnel boring machine (TBM), as
appropriate. The main power tunnel is advanced from the downstream portal
located near the powerhouse area. The first 100 to 300 feet is excavated
by the drill and blast method. This is done to enhance the construction
schedule and to develop a good headi~g for the TBM. The heading is
supported by steel sets and rock bolts. The remaining tunnel length, up to
and just beyond the lower elbow; is excavated with the TBM. Fault
crossings may be excavated by the TBM or conventional drill and blast
methods, depending on the rock conditions encountered. It is anticipated
that rock bolting and/or use of steel sets will be required at the fault
areas. Some rock bolting may be required in the remaining length of the
tunnel for safety reasons. The area at the lower elbow is to be enlarged
to accommodate equipment during mucking operations for the inclined shaft.
The inclined shaft is developed by the raised bore method. Under the
present concept, a pilot hole is to be drilled from ground surface, at an
inclination of 55° with the horizontal, to intercept the upper end of the
main tunnel near the lower bend. This pilot hole is enlarged to a suitable
diameter and serves as an opening for the torque shaft of the raise boring
machine. The shaft is then excavated by a series of reaming operations
using increasingly larger size raise bore bit assemblies, until the desired
excavated diameter of about 13 feet is reached. The full 13 feet excavated
diameter is carried up to and just beyond the projected intersection of the
inclined shaft and the upper horizontal tunnel. This intersection area is
then excavated and shaped to form the upper bend of the power conduit.
7-36
About 89,300 cubic yards of material is excavated from the main power
tunnel, the bends and the inclined shaft. This material will be spoiled as
fill in the construction of the airstrip, or as road topping on the
powerhouse access road or both.
The upper horizontal tunnel section of the power tunnel is developed using
drill and blast methods and connects the intake structures and the inclined
shaft. Material excavated from this section will be spoiled in the
designated waste areas, near the dam or may be used in the dam.
7.4.2.5 Steel ~iner and Penstock
The 11 feet outside diameter steel liner will be approximately 2,400 feet
in length. Preliminary data and discussions with steel and penstock
fabricators indicate that the steel lining can be constructed from high
strength steel plates such as ASTM 517 or ASTM A710. An investigatio_p. of
these materials showed that the A710 steel, with yield strengths of better
than 85,000 psi and other desirable characteristics, can be considered for
use. The steel liner has been · conceptually designed to satisfy the
following conditions:
o The steel liner will be terminated within the tunnel at a point where
the rock cover around the liner is about one half of the transient
pressure head.
o The steel liner will be checked against possible buckling failure from
an external hydrostatic pressure equal to the height of rock cover
above the liner. Required shell thickness shall be based on the Amstutz
theory of failure, assuming 0. 03% initial gap and a minimum safety
factor of 1.2.
o The maximum hoop stress will be limited to 50 percent of yield
strength, assuming no support is provided by the concrete and rock.
Using the above criteria, shell thickness varying from 3/4 inch to 1 inch
were calculated for the steel liner, resulting in a total material weight
7-37
of 1, 380 tons. In the final design, detailed analyses will consider the
assistance of the surrounding rock mass for resisting the internal pressure.
The interior of the steel liner is painted with an acceptable paint system.
The steel penstock section begins at the downstream end of the steel liner
and terminates at the upstream end of the spherical valve of each turbine
unit. The penstock consists of a roll-out section, a reverse bend section,
a straight pipe section, a reducing wye, two reducing bends and two
cylindrical shells connecting to spherical valves. The overall length of
the penstock is about 135 feet. The roll-out section is about 11 feet
long. It is stiffened by two end girders which also serve as the sliding
supports of the section. The roll-out section is coupled to the steel
liner and downstream penstock by specially designed high pressure
couplings. The roll-out section is provided to allow for access into the
tunnel section, should major maintenance be required. A man-door is
provided on the side of the roll-out section for routine inspections of the
tun...TJ.el.
The wye section is of the internal splitter design. This eliminates the
heavy external reinforcements and results in reduced hydraulic losses. The
wye configuration results in two outlet branches each 8 feet in diameter.
These outlets are connected to the corresponding units spherical valves by
an 8 feet diameter straight penstock section, a reducing bend with an
outlet diameter of 5 feet, and a 5 feet diameter straight section that is
about 25 feet long. The wye and other downstream penstock members are
conservatively sized to withstand the maximum internal transient pressure
with an allowable hoop stress equal to less than 40 percent of yield.
Both the interior and exterior surfaces of the penstock, including the
roll-out section are painted with an acceptable paint system. Also, the
penstock sections, downstream of the roll-out section, are encased in
reinforced concrete. Part of this concrete encasement is provided by a
large thrust block at the upper bend of the penstock designed to resist
hydrostatic and dynamic loads. In addition to concrete encasement, the
penstock sections downstream of the thrust block are placed in a rock
7-38
trench cut below the yard grade of elevation 40. This type of construction
affords protection of the penstock from the elements and other factors,
improves the aesthetics of the project, and more importantly eliminates the
possibility of vibrations along the penstock length.
7. 4. 3 Hydraulics
The power conduit system consists of the intake channel, intake structure,
gate shaft, and pressure tunnel. The intake channel will be excavated in
rock and has been sized to maintain average flow velocities of less than 1
fps under full power operation at the minimum drawdown level elevation
1060. This low velocity will result in negligible hydraulic losses in the
channel. When the lake level is drawn below elevation 1100 all flow will
be constricted to the 50 foot wide intake channel. Although velocities
will be quite low there is the potential for eddy formation within the
channel due to the oblique flow condition from the lake into the channel.
To ensure satisfactory hydraulic performance under those conditions, a
physical hydraulic model of the flow phenomenon will be conducted. The
cost of this study is included in the estimate.
The intake structure is of a conventional type with an bellmouth shaped
roof and uniform transitioned side walls. It has been sized to maintain
average velocities of about 3 fps at full power output. This low velocity
will result in relatively minimal hydraulic losses within the intake and
across the trash racks. Vortex formation at the intake should not occur
under normal power operations. The intake invert has been set 30 feet
below the minimum drawdown elevation of 1060 which is based on past
experience in a large number of projects. However, as an added safety
factor, the physical model discussed above will include the intake
structure to study vortex formation under adverse conditions.
The gate shaft structure will house the rectangular slide gates with a
smooth transition from the circular pressure tunnel. Losses in this
section will also be minor. Other minor losses will occur in the various
bends of the power tunnel and penstock.
7-39
Of the total hydraulic losses in the system, the largest will occur due to
friction. It has been estimated that the combined friction and minor
losses will vary between less than one foot under minimum power operation
to about 55 feet under maximum power generation. The hydraulic losses are
calculated ·as : H1 = 3.22 x 10-5 (Q 2 ), where H1 is the loss in feet and Q is
the flow in cubic feet per second.
7.4.4 Transient Analysis
Transient studies were performed for each project capacity studied, 60, 90,
and 135 MW; and each type of turbine, Francis or Pelton. The objective of
these studies was to determine the maximum and minimum pressures in the
power conduit during full plant load rejection and load acceptance, and
identify surge facility requirements. The transient analysis was performed
using the SWEC Hydraulic Transient Analysis Program HY-001. The power
conduit arrangement varied with each type of turbine and capacity which
required that each type of turbine and capacity be analyzed as an
individual case.
For the purposes of the transient analysis the Francis turbine runner was
set at elevation -6. The power conduit was 10, 11, and 12 feet in diameter
for capacities of 60, 90, and 135 MW, respectively. The following is a
description of the modeled power conduit:
A-B
B-C
C-D
Segment
D-E
E-F
F-G
Description
Powerhouse --2 units
Steel penstock
Steel and concrete lined tunnel
Concrete lined tunnel
Surge tank
Concrete lined tunnel
Concrete lined inclined shaft
Concrete lined tunnel
Intake (invert elevation 1,040)
Length
200 feet
2,600 feet
1,700 feet
12,950 feet
850 feet
650 feet
During initial computer runs, varying surge tank diameters and orifices
diameters in the riser shaft to the surge tank were tried. Transient
pressures were reduced upstream of the surge tank, but remained high
downstream in the steel lined tunnel section and penstock. Synchronous
bypass valves were added to the computer model upstream of the turbine
scroll case and the transient analysis was repeated; the transient
pressures were significantly reduced downstream of the surge tank. Figure
7.4-1 shown the maximum transient pressure gradient and Table 7.4-1 shows
the respective maximum and minimum pressures at various powerhouse
capacities, synchronous bypass valve sizes, and wicket gate opening and
closure times. There was no water column separation indicated during
either full load acceptance or reJection for the cases depicted in the
Table 7 .4-1. The full load acceptance was modeled at minimum headwater
elevation and the full load rejection at maximum headwater elevation.
The Pelton turbine runner was set at elevation 14, 15, and 16 feet, an~ the
power conduit w~s 10, 11, and 12 feet in diameter, for capacities of 60,
90, and 135 MW, respectively.
modeled power conduit:
The following is a description of the
Segment Description Length
Powerhouse --2 units
A-B Steel penstock 200 feet
B-C Steel and concrete lined tunnel 2,600 feet
C-D Concrete lined tunnel 14,650 feet
D-E Concrete lined inclined shaft 850 feet
E-F Concrete lined tunnel 650 feet
Intake (invert elevation 1,040)
The power conduit was modeled without a surge tank with needle valve
opening times of 35 and 60 seconds and closing times of 60 seconds. The
computer rs results indicated acceptable transient pressures exist in the
pow~r conduit under these cases. The needle valves are commonly equipped
with a hydraulic cylinder operated deflector which deflects the jet from
the Pelton runner during the load rejection. Once the jet is deflected the
7-41
needle valve can be closed at a gradual rate such as 60 seconds. Figure
7. 4-2 shows the maximum transient pressure gradient and Table 7. 4-2 shows
the respective maximum and minimum pressures at various powerhouse
capacities, and needle valve opening and closure times. There was no water
column separation experienced during either full load acceptance or
rejection for the cases depicted in the Table. The full load acceptance
was modeled at minimum. headwater elevation and the full load rejection at
maximum headwater elevation. The transient results indicate that a surge
tank is not required.
7 .4.5 Geology
This section includes outlines of geologic conditions at the Intake
Structure and for the various segments of the Power Conduit System; these
subdivisions are based on geologic terrain rather than design elements.
Also included are the results of laboratory tests on selected rock cores
and an outline ·of the results of petrographic examination of the various
rock types present. Details of geologic conditions are available in
Appendix A.
7 . 4. 5. 1 Intake Area
Surface reconnaissance reveals that the rock is comprised of complexly
mixed graywacke and foliated argillite with less than 10 percent chert
nodules and layers. The contacts between the graywacke and argillite
roughly parallel the foliation in the argillite, which typically trends N-S
to N20°E and dips steeply. Several small faults and joint sets are
present. These features have been described in some detail by
Woodward-Clyde (1979) and Dowl Engineers (1983) as part of their
investigations for the left abutment of the dam. No faults are known to
intersect the currently proposed location for the intake portal.
An east-northeast-trending topographic lineament, which passes near the
proposed location of the intake portal, was suspected to be the surface
expression of an east-northeast-trending rockmass discontinuity. This
lineament is the gully between Hill 1270.7 and Hill 1525.6. About 1, 000
7-42
feet to the west of Bradley River the lineament merges with an
east-trending fault mapped by Woodward-Clyde (1979). Directly east across
Bradley River, it trends into the vicinity of two small covered areas which
are probably the surface expression of joints or small faults. The
lineament also parallels an east-trending fault located about 250 feet to
the north on the east side of the river, and a series of lineaments, of
unknown origin, to the southwest.
Boring SW83-2, oriented S6°W and angled at 45°, was made to define
subsurface conditions causing the prominent lineament. The boring was
oriented to cross the lineament described above and encountered 28.4 feet
of colluvium and 126. 9 feet of bedrock (20. 1 feet and 89. 7 feet vertical
depth). Bedrock is primarily graywacke with varying amounts of associated
argillite; the overall rock mass fabric appears to be cataclastic in
origin. Close to very close jointing was encountered in portions of the
boring; no indications of significant faulting were found.
Since the feature sampled by Boring SW83-2 is the most prominent lineament
in the Intake area, it is considered that the Intake facilities should not
encounter any significant faults or shear zones. Several minor shears have
been previously mapped in the Intake area (Woodward-Clyde, 1979). These
are well exposed and are not known to exceed one to two feet in width.
Several of these may be expected to cross the Intake channel but are not
considered significant to construction or operation of the facil'ity.
Geologic conditions arEa considered to be satisfactory for construction of
the proposed Intake facilities.
7 .4.5.2 Bradley Lake to Bradley River Fault Zone
This easternmost section
interbedded gray-wacke and
of th~ tunnel alignment is
argillite. Because of their
been mapped as a single unit
percent massive graywacke and 35
these rock types have
approximately 50 to 65
under lain by
complex mixing,
comprised of
to 50 percent
argillite. The argillite is commonly foliated and occurs as interbeds and
pockets that range from less than a foot to as much as 100 feet thick.
7-43.
Jointing is more apparent along this section of the tunnel alignment than
further to the northwest. Several lineaments also cross this section of
the tunnel alignment at various orientations. It is suspected that some of
these features may be faults, but there is generally insufficient rock
exposure to determine whether they represent faults or major joints. One
pair of parallel lineaments, located about 1, 700 feet northwest of the
intake structure is particularly suggestive of a fault zone. Their origin
is uncertain; if they are the surface expression of a fault, the zone may
contain highly fractured and crushed rock up to about 200 feet wide along
the proposed tunnel alignment.
7 .4.5.3 Bradley River Fault Zone
At a distance of approximately 3, 900 feet from the intake, the tunnel
alignment crosses the Bradley River Fault zone. The main trace, can be
followed for several miles along a trend of about N15 °E. The fault is
mantled by colluvial and glacial deposits, but is believed to be nearly
vertical because of its linear topographic expression. Exposures elsewhere
along the Bradley River Fault have suggested that the main fault trace can
have a gouge zone of finely pulverized material that is up to 50 feet wide,
with sheared argillite extending another 50 to 75 feet on either side (Dowl
Engineers, 1983).
The Bradley River Fault zone was explored by boring SW83-2, which was
drilled perpendicular to the fault trace at an orientation of N75°W and at
an angle of 45°. Drilled to a depth of 262.3 feet, the boring penetrated
two shear zones at 47.4 62.0 feet and 138.0 175.6 feet, possibly
representing branches of the fault.
From the surface to a drilled depth of about 30 feet, loose gravelly sands
with cobbles and boulders were encountered above bedrock. Striations
observed on a cobble suggested that these materials are, at least in part,
glacial.
Beginning at the top of bedrock, shear-foliated cherty argillite was
encountered, and encompassing the two shear zones, continued to a drilled
7-44
depth of about 197 feet. This rock is closely jointed to locally very
closely jointed.
Below a depth of 197 feet, alternating zones of graywacke and chert were
encountered, with local zones of cherty argillite and foliated argillite.
Joint spacings in these materials increase to moderately widely spaced
joints when argillite materials are not significantly present.
It is possible that additional shear zones exist to the east of the upper
one encountered in boring SW83-2. The material observed in similar zones
is predominantly brecciated argillite rock
Locally the rock has been reduced to fault
fragments in a clayey silt matrix.
containing clasts of chert.
gouge consisting of breccia
The cherty argillite adjacent to the shear zones is generally very closely
jointed and the argillite faces adjoining shear planes are extremely
: ·~
slickensided, often containing crushed rock fragments as breccia and goug~.
The amount and sense of displacement along the Bradley River Fault zone is
not well established. Slickensides rake from 0 to 30° along the fault
suggesting a vertical component of up to 400 feet associated with the i,OOO
feet of apparent horizontal displacement. Horizontal offset of a dacite
tends to confirm this.
7 .4.5 .4 Bradley River Fault Zone to Bull Moose Fault Zone
Northwest of the Bradley River Fault zone, the tunnel alignment crosses the
highest elevations and best exposed bedrock along its route. This area is
underlain predominantly by foliated argillite, with lesser amounts of
massive _argillite, graywacke, and a single dacite dike. Much of the
foliated argillite contains nodules and thin discontinuous layers of chert
comprising about 10 to 20 percent of the volume of the rock. A few massive
lenses of very closely fractured chert up to 10 feet wide were also found
interspersed with the foliated argillite in this area. . The foliation in
the argillite and cherty argillite strikes from N-S to N20°E and typically
dips greater than about 75 degrees. The dacite dike, although not exposed
7-45
on the alignment itself, appears to cross the proposed tunnel alignment
along a N80°E trend with a nearly vertical dip. For tunneling purposes
this rock will probably behave similarly to the massive argillite or
graywacke.
Bedrock outcrops along this segment of the tunnel alignment tend to be
widely to very widely jointed. Hundreds of short, linear, soil-filled
depressions can be seen in this area, many of which are presumably the
surface expression of bedrock joints and/or minor faults. Unfortunately,
however, without better rock exposure it is not possible to distinguish
which of these features are faults or joints.
Larger lineaments, also common in this area, present the same problem for
attempts to define their structural significance. A series of lineaments,
occupying an area about 1,000 feet wide, located east of and subparallel to
the Bull Moose fault zone are possibly the surface expression of smaller
faults associated with the main fault trace, but exposures are insufficient
.to conclusively determine their origin. In spite of relatively good rock
exposure in this area, it was not possible to determine conclusively
whether these represent minor faults or prominent joint sets. In either
case, exposures limit the width of these apparent discontinuities, at the
surface, to less than about 10 to 15 feet where they cross the tunnel
alignment.
7 .4.5.5 Bull Moose Fault Zone
The main trace of the Bull Moose fault zone is located approximat~ly 9,800
feet northwest of the tunnel intake. It is expressed as a narrow,
topographic notch with a 200-foot-high, steep west wall. This area is
densely vegetated and rock is exposed only in small isolated outcrops. No
exposures of the crush zone in the fault were found, but relatively
undeformed rock on either side of the main fault trace indicates that this
zone must locally be less than about 50 feet thick.
The tunnel alignment crossing of the Bull Moose Fault was explored with
boring SW 83-4. Drilled at an orientation of N80°W and an inclination of
45°, this boring was carried to a depth of 206.2 feet.
7-46
Bedrock was encountered after only 4. 2 feet of penetration, and the shear
zone of the Bull Moose Fault was encountered at a drilled depth of about
146 feet. Random alternating zones of graywacke, argillite, and chert, as
well as mixtures of these lithologies were logged within the depth explored.
The shear zone of the Bull Moose Fault was encountered from a depth of
about 146 feet to 154 feet in the boring (horizontal width of 6 feet). The
brecciated argillite and graywacke in this zone is locally sheared to silty
sand and zones of clayey gouge. The rocks adjacent to the shear zone,
argillite above and chert below, are highly fractured from considerable
shear deformation.
The vertically projected location of the shear zone encountered in boring
SW83-4 is consistent with the mapped location of the fault trace for a
near-vertical fault plane.
7.4.5.6 Bull Moose Fault Zone to Powerhouse Site
The bedrock exposure is much more limited along this segment of the tunnel
alignment than it is to the southeast. This is particularly true to the
northwest of the possible surge tank location where forest and soil cover
mantle all but a few small isolated rock outcrops. The available exposures
indicate that this section of the tunnel alignment is underlain
predominantly by foliated and massive argillite. Cherty argillite and
graywacke crop out in relatively small amounts, although boring data
indicate that these rock types are more common than their surface exposure
suggests. The predominance of argillite is also indicated by natural
outcrops visible 1000 -1500 feet southwest of the tunnel alignment in a
gully which roughly parallels the alignment.
The recognizable structural trends in this area conform to those elsewhere
along the tunnel alignment. Foliation in the argillites is consistently
oriented at N-S to N20°E. Jointing is widely to very widely spaced in most
exposures, with a dominant strike of N75-85° North.
7-47
7. 4. 5. 7 Laboratory Rock Testing
Selected portions of N-size rock cores recovered from COE borings were
tested to define general rock strength properties and, more particularly,
to ascertain the feasibility of driving the tunnel using a tunnel boring
machine (TBM). Various tests were conducted by Dr. A. J. Hendron, member
of the Project's Technical Review Board, and by TBM manufacturers Atlas
Copco Jarva, · Inc. and The Robbins Company. In addition to this current
data, the results of previous tests by the COE are included. The results
of the tests, grouped by rock type, are shown on Tables 7. 4-3 through 7. 4-8.
Several tests on rock from APA's Terror Lake Hydroelectric Project (Kodiak
Island, AK) are included for comparison with Bradley Lake rock types. A
tunnel is currently being successfully driven at Terror Lake using a TBM.
It should be noted that the fabrics of rock types (with the possible
exception of the dacitic dike rock) from Bradley Lake differ from that of
the quartz diorite of Terror Lake. The various testing agencies conducted
different types of tests and direct comparisons of results are difficult.
In the case of the tests conducted by the TBM manufacturers, some test
methods and all interpretation methods are proprietary.
In summary, it is seen that among the major rock types the graywacke tends
to yield the highest unconfined compressive strengths (up to 34,975 psi)
and generally the greatest hardness (various methods). In decreasing
order, following graywacke, are graywacke/argillite mixtures, massive
argillite, foliated cherty argillite, and foliated argillite, which yields
unconfined compressive strength in the range of 8000 -6500 psi and Total
Hardness as low as 68. Chert, in large, discreet masses is very uncommon
and is the only rock type judged as "abrasive" for TBM tunneling purposes.
Unconfined compressive strengths for chert were fairly low, 6800 -11, 120
psi (one at 22,730 psi), reflecting both macro-and microscopic in situ
fracturing; Total Hardness ran as high as 204.4. In comparison, Terror
Lake quartz diorite (including even sericitized specimens) tested from
22,800 to 26,050 psi with Total Hardness from 106 to 133 (one at 74.8).
Typical values for the majority of Bradley Lake specimens are very similar
to values obtained from Terror Lake samples.
7-48
Advance rates for a TBM have been estimated as outlined below:
Rock Type Rate (ft/hr) Estimated Tunnel Length (ft)
Graywacke,
Graywacke/Argillite 6-8 4300
Massive Argillite 8:-10 5000
Foliated Argillite 10-12 3500
Foliated, Cherty
Argillite 8-10 3790
Chert 3.0-5.75 50
It should be noted that tunnel lengths may not correspond exactly to those
given in a similar table on page 43 of Appendix A. The lengths above have
been slightly revised based on petrographic data unavailable at the time of
issue of Appendix A.
Tunnelling conditions for fault zones, fracture zones, and at portals,
where drill and blast techniques and temporary steel sets would be used,
are shown in Table 7. 4-8.
It is concluded that the use of a TBM for tunnel excavation is technically
feasible at the Bradley Lake site. However, to support the definitive
engineering and design, the characteristics of the fault formations should
be determined at tunnel depth.
7. 4. 5. 8 Petrographic Examinations
Thin sections were taken of selected surface specimens and portions of rock
core samples. The primary purpose of these examinations was to provide a
check on the megascopic field classifications assigned to various rock
types during surface mapping. In a few cases, the examinations provided
7-49
clarification for rock types of uncertain origin and classification.
General characteristics of the major rock types were established by
rigorous petrographic analysis and the remainder of the samples identified
by sight under the petrographic microscope. A list of samples, their
locations and their classifications are included in Table 7. 4-9. Analysis
sheets for the major rock types -graywacke, ma.ssive argillite, foliated
argillite, cherty foliated argillite, and tuff (or volcanic graywacke) are
included as Figures 7.4-3 through 7.4-7. Also included and shown by
Figures 7.4-8 and 7.4-9, are analyses of quartz diorite and
hydrothermally-altered quartz diorite from the Terror Lake project. As
outlined in the section above, these samples were tested to provide a
comparison of strength properties with rocks from the Bradley Lake area.
With the exception of one rock type, the tuff or volcanic graywacke, thin
section examination confirmed megascopic field classification of rock
types. The tuff had been identified in the field as an anomalous rock type
but, because of its fine-grained nature,_could not be positively classified
by megascopic examination. Microscopic examination positively identified
its volcanic origin but also established its grain-size distribution and
probable mode of deposition as essentially the same as that of the
graywacke, thus the alternate term, volcanic graywacke.
Certain conditions, applicable to the general geologic setting of the site
area, were noted in the thin sections. These include:
o Pervasive alteration of feldspar, particularly plagioclase, to sericite.
o Pervasive but low-level chloritization.
o Development of cataclastic textures in virtually all clastic rock
types. The degree of development roughly corresponds to grain size,
with the finer-grained rocks showing more pronounced development.
Petrographic examination has confirmed the validity of rock type
classifications made by megascopic examination during the current field
mapping program. In addition, the postulated cataclastic origin of major
7-50
rock mass and structural features is reflected at the microscopic level;
taken together, it would appear that the areas has been subjected to
repeated deformation.
7 .4.6 Access
Access to the power conduit is
powerhouse. Access within the
available from the area adjacent to the
power conduit is through the roll-out
section, the mandoor at the roll-out section or the man access way at the
gate shaft. The roll-out section affords access to large equipment should
major repairs be needed within the power conduit. Mandoor access is
principally for general inspection.
7.4.7 Alternatives
Several alternative power conduit alignments were identified under previous
t~
studies by the Corps of Engineers and dismissed for valid technical and
economic considerations. The power conduit alignment selected by the COE
was reviewed under this study and a comparative evaluation was made to the
alignment recommended by this report. The comparison showed substantial
savings and other construction environmental improvements resulting from
the following:
o Use of the tunnel boring machine.
o Elimination of the exposed side hill penstock.
o Elimination of the hillside access road to the high tunnel portal.
o Elimination of the access and haul road to the bridge crossing at the
upper Bradley River.
o Elimination of the bridge crossing.
o Elimination of the access adit to the power tunnel.
o A reduction of the power conduit length.
Because of the above, the decision was in favor of the preferred alignment
presented by this report.
7-51
7 . 5 POWER PLANT
7.5 .1 General
The powerhouse is located near sea level on the southeastern shore of
Kachemak Bay at approximately N2,112,430,E327,100. The relief at the
powerhouse site rises steeply from the tidal flats near elevation 10 to
elevation 1400.
The powerhouse and power tunnel portal are situated upon an excavated rock
bench at elevation 40. This excavation has an oblonged triangular
arrangement as shown on Plate 13. Local excavations below elevation 40 are
required to contain the powerhouse substructure, the steel penstock, and
the bifurcation and thrust block. The excavated material would be utilized
to form a construc.tion laydown area and switchyard in the tidal flats
adjacent to the powerhouse excavation.
The powerhouse is approximately 138 feet long, 66 feet wide and 112 feet
high. The powerhouse substructure is constructed of reinforced concrete
detailed to be integrally keyed into the surrounding bedrock. The Pel ton
turbine, inlet penstock, and manifold are entirely housed within the
reinforced concrete portion of the structure. An insulated structural
steel superstructure is above elevation 40 housing the generators and
bridge crane. The bridge crane runway is comprised of steel columns and
girders which also serve as the main structural members for the powerhouse
superstructure. The powerhouse plans and elevations are shown on Plates 13
and 14.
The powerhouse has two main operating floors, the turbine floor at
elevation 23 and generator floor at elevation 40. Local spherical valve
pits are provided below the turbine floor at elevation 5 to house the
spherical valves and hydraulic cylinders. Access to the turbine chamber
can be obtained from the spherical valve pit via a steel mandoor.
A 16 feet wide tailrace deck is provided downstream of the powerhouse
7-52
superstructure to provide access to the turbine chamber through a deck
hatch should major maintenance be required.
A tailrace channel will be excavated downstream of the powerhouse through
the tidal flats to allow a free discharge of generating flows to the
Kachemak Bay.
7 .5.2 Basic Data
Plant, KVA (nameplate rating)
Number of Units
Type of Turbine
Turbine Rating at 1130 feet rated net head, Hp
Rating of Generating Unit, KVA (nameplate)
Maximum Operating Pool Elevation, feet
Minimum Operating Pool Elevation, feet
Maximum Tailwater Elevation, feet
Minimum Tailwater Elevation, feet
Centerline Turbine Runner Elevation, feet
Bottom of Turbine Chamber, feet
Unit Spacing, feet
7 .5.3 Tidal Considerations
112' 600
2
Pelton
73,900
56,300
1,180
1,080
11.4
-6.0
15.0
-6.0
43.0
The powerhouse setting and tailrace configuration are based upon the
following range of tides developed by the COE:
Highest Tide (estimated)
Mean Higher High Water
Mean High Water
Mean Sea Level
Mean Low Water
Mean Lower Low Water
Lowest Tide (estimated)
7-53
Elevation
Based on
Project Datum
11.37
4. 78
3.97
-4.02
-12.02
-13.63
-19.63
Of particular concern at the powerhouse is salt water intrusion and the
resulting corrosion problems for steel and other metals. To avoid direct
salt water contact with the Pelton turbine runner, the runner is set at
elevation 15, 3. 6 feet above the estimated high tide level. Tailwater
depression will be used to maintain free runner discharge. The tailrace
deck has been set at elevation 23 with a 3.5 feet high concrete parapet
wall. This will provide 15 feet of wave run-up at high tide. This setting
also prevents the manifold and penstock from coming in direct contact with
the salt water intruding during high tide periods. Cathodic protection is
provided to protect steel and other metal components from accelerated
corrosion that are near or in the salt water interface.
7.5.4 Turbines and Generators
The turbines selected for the preferred plan are 6 jet Pelton vertical
shaft type units direct coupled to the generators rated for a net head of
1130 feet at 300 rpm. The generating unit nominal rating is 45 MW at full
6 jet gate and at the minim~~ gross generating head of 1065 feet. The best
point efficiency rating of the turbines was set at a rated head 10 feet
above the weighted average net generating head. The 10 feet upward
adjustment was made to better represent anticipated turbine
conditions for years other than the critical period operation.
operating
The rated
net head was also used in determining maximum full gate horsepower of the
turbine. The Pelton unit is accessible and removable through the turbine
chamber and tailrace hatch without requiring the dismantling of the
generator. Needle valves are equipped with jet deflectors and hydraulic
operators.
Each of the two generators is rated 56300 KVA, 13800 volts, threephase, 60
HZ, 0.95 power factor, 300 rpm. The generators are of the vertical shaft,
suspended type with a guide and thrust bearing located above the g.enerator
rotor, and a guide bearing below the rotor. Generator insulation is class
B or better. Winding temperature rise is 7 5 °C over a maximum ambient air
temperature of 40°C. The stator winding is wye-connected, and the winding
neutral is grounded through a transformer-resistor arrangement to limit
7-54
line-to-ground fault current. The generator is completely enclosed and
equipped with a-C0 2 fire protection system. The generator excitation is
provided by a static exciter, which consists of a three-phase transformer,
rectifier and voltage regulator. Power for excitation is taken from the
generator terminals.
7.5.5 Powerhouse Arrangement
The powerhouse location was selected to assure that the powerhouse
substructure would be located on rock and to take advantage of the natural
coastal relief in order to minimize the overall excavation required to
accommodate the powerhouse, penstock and tunnel portal. Field topographic
surveys were conducted at the proposed powerhouse site to accurately depict
the relief.
Of particular importance was the interrelationship of the powerhpuse,
penstock, and power tunnel and portal in determining the overall excavation
size. In order to fully support the construction efforts, continued access
is required to the power tunnel and portal throughout the construction
schedule. Normal minimum distances around the powerhouse were increased
from 40 feet to 100 feet to improve access to the tunnel portal during
powerhouse and penstock construction. In addition, a lay down and storage
area at elevation 20 is provided adjacent to the powerhouse excavation to
support the powerhouse, penstock, and power tunnel construction
activities. This lay down area will increase the staging area available to
the construction contractors by 1. 2 acres and will later be used to site
the powerhouse substation.
The initial construction activities to establish the power tunnel portal
and initiate tunneling operations with the TBM are very critical to the
project schedule. Therefore, the construction of the powerhouse has been
delayed until the intense tunneling effort is essentially over. The
powerhouse and penstock excavation will be established at the same time
that the initial powerhouse elevation 40 bench open cut excavation is
established. These excavations will be back-fiLled with granular material
7-55
to increase the staging area available to the tunneling contractor. The
powerhouse contractor will remove the granular material during the
construction of the powerhouse and penstock.
In sizing the powerhouse structure, the 90 MW Pelton generating equipment
was evaluated to determine the key factors which affect the internal
powerhouse layout. These are:
o Manifold and Turbine Chamber
o Spherical Valve Dimensions and Orientation
o Generator Overall Dimensions
o Size and Location of the Auxiliary Electrical and Mechanical Equipment
o Control Room Size
The manifold and turbine chamber dimensions are
dimensions obtained from turbine manufacturer inquiries.
contained and may be operated when the other unit
representative of
Each unit is self
is dewatered for
inspection or maintenance. The manifold is downstream of the spherical
valve and is equipped with needle jet valves and nozzle deflectors to
control flow to the Pelton runner. The manifold is of high strength welded
steel construction and is embedded in a minimum of two feet of reinforced
concrete. The upper turbine chamber is steel lined and hydraulically
shaped to provide a free water discharge from the Pel ton runner buckets.
The turbine chamber ·will be pressurized by air to depress the water surface
level during periods of high tailwater resulting from tides. An air
recovery system was considered but was not pursued due to the relatively
short tailwater channel between the turbine chamber and the draft tube
gates. This aspect should be investigated further during the final design
phase and generating equipment selection.
Accessibility to the turbine chamber for periodic inspection and
maintenance on the Pel ton runner, needle jet valves, and subcomponents is
provided. Turbine inspection can be performed through the spherical valve
pit into the turbine chamber via a 3 feet wide and 5 feet high water-tight
mandoor. This means of access also serves as a second means of egress from
7-56
the turbine chamber during periods of major maintenance and allows for air
circulation during welding operations in the turbine chamber. The normal
access for major maintenance will be through an access hatch provided at
each unit and located in the elevation 23 tailrace deck. This access
hatch has a 10 feet wide and 16 feet long clear opening, which is sized to
accommodate the removal of the turbine runner. The turbine chamber floor
is at elevation -6 requiring staging to provide vertical access to the
turbine equipment located at elevation 15. The tailrace access hatch is
oriented to allow a 9 feet by 15 feet by 17 feet staging to be lowered in a
single piece. The staging would be equipped with rollers and a jacking
table for runner installation and dismantling in the event of major
maintenance.
The spherical valves, hydraulic operator, power units, and accumulator, are
representative of dimensions obtained from manufacturers. Each valve has a
self-contained hydraulic operator which has an accumulator tank size~:: to
permit a close-open-close cycle, without recharging, in the event of total
power loss (station service, emergency diesel generator and battery). The
power unit and accumulator tank are located on the elevation 23 floor with
the spherical valve and hydraulic ram in the valve pit. The valve pit has
been sized to permit access on each side of the spherical valve body for
complete visual inspection and maintenance. Access is provided into the
pit by a ladder on the operator side of the valve and 6 feet of headroom is
provided under the penstock downstream of the valve body to permit access
to the other side of the valve. A sectional covered hatch is provided over
the valve pit in the floors at elevation 23 and 40 to permit bridge crane
access to the valve pit.
The largest generator manufacturers' dimensions were used to layout the
powerhouse. This is a conservative approach and allows a powerhouse
arrangement to be developed at the conceptual stage which can accomodate a
variety of generator manufacturers dimensions. During the final design
phase, definitive manufacturers dimensions will be available and may allow
the overall dimensions to be reduced. To ease installation of the
generator, a powerhouse layout was developed which permits the stator and
7-57
rotor to be delivered to the project site fully assembled. The powerhouse
door adjacent to the assembly bay is· 30 feet wide and 20 feet high. The
powerhouse bridge crane has been sized to accommodate both the stator and
rotor lift.
The size and location of the auxiliary electrical.and mechanical equipment
is based upon actual project experience. Space is allowed around the
equipment to permit installation and maintenance access, and allow space
for egress. The floor plans at elevation 23 and 40 are shown on Plates 13
and 14.
The size and location of the control room is based upon actual project
experience. Space is allowed around the control panels and consoles to
permit installation and maintenance, and allow two doors, one exterior and
one interior, for egress. Space has been allowed for office desks, files,
and cabinets within the control room. Restroom facilities are provided
adjacent to the control room.
7. 5. 6 Electrical Equipment
The one-line diagram for the plant, of key electrical equipment and their
arrangement, is shown on Plate 22. There are two main power transformers,
located in the substation, one for each generator. The transformers are
each rated OA/FA/FA-33. 8/45/56.3 MVA, three-phase, 60 HZ. ·The high voltage
winding is rated 115,000 volts, grounded wye, and the low voltage winding
i~ rated 13,800 volts delta. The transformers are oil-immersed, with a
self-cooled rating, and two stages of forced air cooling. The generator
circuit breakers, potential transformers and generator surge protection are
contained in 15 kV metal-clad switchgear cubicles. The generator breakers
are rated 3000 A continuous, 1000 MVA interrupting capacity, and include
(6) 3000/5 amp current transformers. Each generator is provided with (4)
11400-120 volt single phase potential transformers for metering, relaying,
and synchronizing. The potential transformers are fused on the high and
low voltage sides and are drawout type. Protection for each generator
consists of three 15 kV lightning arresters and three surge capacitors
mounted in a switchgear cubicle. Each of these protective devices are
7-58
connected between the generator terminals and the powerhouse ground
system. Each of the switchgear groups associated with a generator is
located adjacent to the generator on the operating floor level. The
generators are connected to the switchgear, and then to the transformers
via copper conductor, three-phase, non-segregated phase bus. The bus is
rated 15000 volts, 3000 amps continuous, and 80,000 amps momentary. The
portion of the bus in the powerhouse is ventilated, and the outdoor portion
is fully enclosed and weatherproof.
Station service power is provided by a double-ended load center. There are
two dry-type transformers, rated 450 KVA, 13.8 kV-480V, threephase, 60 HZ.
Each transformer is connected to the generator terminals through a 15 kV,
current limiting, fused disconnecting switch and via 15 kV shielded
cables. One transformer is connected to Generator No. 1 and the other
transformer is connected to Generator No. 2. Due to the use of generator
breakers, both station service transformers are normally energized, , .. even
'~z.,_
during generator shutdown. The station service switchgear is 600V class
drawout type arranged in two main buses. Each bus is provided with an 800
amp, electrically operated main circuit breaker, with an 800 amp normally
open tie breaker between the buses. The tie breaker closes upon loss of
voltage on either bus. Each transformer and main breaker is capable of
carrying full station service load, in the event one transformer fails.
Each main 480V bus has a sufficient number of manually operated switchgear
type feeder breakers and potential transformers.
Starter, contactors, and feeder breakers are contained in several motor
control centers located strategically throughout the power plant. The
motor control centers are rated 480V, three-phase, 60 HZ. Combination
starters are provided for motors, each starter consisting of a molded case
circuit breaker, a 3-pole contractor, and 3 overload relays. Molded case
feeder breakers, single and three-phase, are provided for protection of
feeders for lighting panels, electric heaters, and other equipment.
The Bradley Lake is to be designed as an unattended plant, normally
operated from a remote location. However, complete control facilities are
also provided for local operation at the plant. Remote control and
7-59
indication is via a microwave communication system. A supervisory, control
and data acquisition system (SCADA) is provided to furnish plant control
and receive plant operational data at the remote location. The SCADA
system is a computer-based system
located at a dispatch center, and
consisting
a remote
of a master control unit
terminal
station. In addition, a second remote terminal unit
unit at the power
is located at the
reservoir gate house to start the propane generator and remotely operate
the gate and receive gate position and reservoir level data. Local control
consists of vertical, duplex panels, with control and indication on one
side, and protective relaying equipment on the other.
Direct current power for control, relaying and emergency power and lighting
is provided by a 125 volt, 60-cell, 200 amp-hr storage battery and battery
charger. A separate 48-volt and uninterruptible power supply (UPS) is
provided by the SCADA, microwave, and other critical electrical equipment
power requirements. The batteries are located in a separate and well
ventilated room, which includes an emergency eyewash sta~ion. The UPS and
battery charger is located outside the battery room.
The plant telephone system consists of an initial quantity of 12 telephones
located throughout the plant, with provision for an additional 4
telephones. Included are connection to three outside lines, with provision
for the addition of three lines, and plant paging. The telephone system is
designed to operate from 120 V .A. C. 60 HZ, power and will be completely
automatic. The off-site communication consists of a microwave system.
This system will provide channels for remote control of the Bradley Lake
plant from a dispatch center to be determined later, and also for telephone
communications. The microwave system is designed to transmit data voice,
and control information between the Bradley Lake power plant and Homer
which is the nearest point in the communication system of the Bradley Lake
plant that is controlled from a point in Anchorage. Communication between
Homer and Anchorage will be via existing systems. Microwave is also used
to provide control communication and data collection between the powerhouse
and the reservoir dam. Where line-of-sight between two points in the
system is not available, a passive "billboard" reflector is provided.
7-60
A diesel driven generator is provided in the power plant to supply a
station service power under emergency conditions. The generator is rated
250 KW, 480V, three-phase, 60 HZ. It is installed in a separate diesel
generator room in the powerhouse. Provisions include air in-take, diesel
engine exhaust, a day fuel tank, and a large fuel storage tank. Control
features are provided to start the diesel engine and automatically connect
it to the station service system, in the event normal station service power
is lost. Other features include a 12 volt battery, cooling equipment,
brushless excitation, voltage regulator, and an automatic transfer switch
rated 480V, three-phase, 60 HZ, 400 amp. A small propane-fueled engine
generator is provided at the gate house and the diversion tunnel control
house at the reservoir dam. Each generator is rated 5KW, 240V, single
phase, 60 HZ. It is equipped with automatic control, a 12 volt battery,
equipment for remote starting and stopping, and a battery charger. The set
is operated remotely from the powerhouse.
Corrosion protection of steel structures and copper grounding gride in the
powerhouse and substation is provided by .cathodic protection equipment.
The equ-ipment consists of electronic rectifiers to produce a DC voltage of
the required magnitude and polarity, and several sacrificial anodes
strategically located.
Electrical power is provided to several outlying areas such as the
permanent village, the domestic water pump house, and the barge docking
facilities. This power is provided to these areas via a wood pole line
along the access road. Power is furnished at generator voltage of 13.8 kV,
30, 60 HZ. A pad-mounted transformer rated 300 KVA, 13.8 kV-480V, 30 60
HZ. A pad-mounted transformer rated 300 KVA, 13.8 kV-480V, 30, 60 HZ is
installed at the village to provide power to the residences, the storage
warehouse and domestic water pump house. In addition, a 300 KW diesel
generator set is installed at the village to provide power during
emergencies. At 75 KVA, three-phase, 60 HZ, 13.8 KV-480V pad-mounted
transformer is located at the barge docking facilities, and energized by
the 13.8 KV pole line.
7-61
7 . 5 . 7 Mechanical Equipment
The turbine will have an actuator-type governor located in a cabinet
mounted on floor elevation 23. The governor actuator air-oil accumulator
tanks are located adjacent to the governor cabinets.
an oil-pressure, pilot operated distributor valve,
The governor will be
actuator type with
solid-state electrically controlled speed responsive elements.
The spherical valves are 5 feet in diameter and hydraulic operated. The
valves and operating mechanism are located in the valve pit at elevation
5. The hydraulic power unit and accumulator tanks are located on floor
elevation 23. The accumulator tanks are located adjacent to the hydraulic
power units and have a reservoir capacity for one close-open-close cycle
without recharging.
A 115 psig air depression system is provided which will depress the
tailwater water level to elevation 6 when there are higher tide water
levels. Pressurized air is injected into the turbine chamber via embedded
wall jets. An ·air receiver, air dryer and filter, two 40 hp air
compressors, and four air accumulator tanks are provided on floor elevation
23. There is also a by-pass air manifold provided, which interconnects
with the station air system and the air depression system, yet allows each
to be isolated for inspection and maintenance.
A 115 psig station air system is provided to supply air tools used for
operations and maintenance. Air ports are provided at strategic locations
throughout the station. This system includes one 30 hp air compressor and
a single air accumulator tank.
A 50,000 gallon concrete water tank is provided to serve as the powerhouse
source of domestic water for potable, fire and cooling water. The.tank is
located on a bench adjacent to the tunnel portal. · Booster pumps are
provided at floor elevation 23 to boost water pressure throughout the power
station.
7-62
The water treatment and potable water system includes a treatment module,
purification equipment, holding tank, water softener, demineralizer, hot
water tanks, storage tank, and necessary distribution. This equipment is
located on floor elevation 23.
Two fire systems , water and C0 2 system are provided. The water system
includes two 200 gpm booster pumps located at floor elevation 23 to boost
station water pressures throughout the fire piping distribution system.
This system utilizes the 50,000 gallon domestic water tanks as the primary
source of water, and penstock and tailrace are used as the back-up or
secondary source. The co 2 system is confined to the generator in the event
of an electrical fire. The system includes two banks of eight to ten high
pressure co 2 tanks will control unit and injectors located in the generator
cover.
The station unwater system consist of two 500 gpm single stage ver:t;:ical
:<;<"
lift pumps and piping discharging to tailwater. The pumps are connect~d by
a <?9,mwon··~manifold wit?-isolation gate and check valves provided to dewater
eac,h turbine chamber, and allow one pump to be dismantled f·· : maintenance.
The unwatering sump is connected to the dirty water sump by a common line
which would allow the dirty water pumps to back-up the station unwatering
pumps in the event of pump failure or vise versa. All station dirty water
is routed to the station dirty water sump. Two 100 gpm pumps are provi~ed
which route dirty water to the oil separator and returns water to the
station unwater sump.
A 48 feet span, 150/25 ton powerhouse bridge crane is provided. The bridge
crane is of conventional arrangement. The crane is used for unit assembly,
erection and maintenance.
Two 12 feet by 17.5 feet draft tube gates are provided for turbine chamber
dewatering. These gates are of conventional design and would weigh
approximately 4 tons each.
A conventional heating and ventilation system is proposed which would be
designed to accommodate the minimum recorded temperature of -20°F. A
special ventilator will be provided for the auxiliary diesel generator room.
7-63
A sewage treatment module will be provided in the powerhouse which will be
designed for continued plant service and. will discharge treated material
into the tailrace. The module would provide primary, secondary and
tertiary treatment.
7.5. 8 Geology
The proposed powerhouse location is situated on a topographic bench above
the Kachemak Bay tidal marsh. This bench is underlain by rock at shallow
depth as indicated by exposures along the shoreline bluffs. However, with
the exception of the bluff exposures and outcrops along a stream 500 feet
to the south, the bedrock is almost completely covered by a veneer of
soil. Based on these exposures and previous borings drilled to the south
along the stream channel, the powerhouse site appears to be underlain by
fractured argillite and lesser amounts of fractured graywacke. A dacite
dike also occurs in the area and was seen only at a single exposure
observed near alternate Francis unit portal location.
A hand-dug test pit was located in the area of the portal for the alternate
Francis powerhouse. Shallow bedrock was confirmed at this site below about
1 to 2 feet of overburden material. The dacite bedrock encountered in the
test pit is similar to other outcrops of dacite dike rocks observed in the
Bradley Lake project area. Although the lateral extent of this material at
the powerhouse site is not known, its width should not be expected to be
great.
Although the rock is typically fractured, it is considered satisfactory as
a foundation material for the powerhouse. Higher cut slopes, such as above
the power tunnel portal, may require some slope protection to control
nuisance-level ravelling.
7.5. 9 Access
Permanent access to the powerhouse will be provided by road from the
permanent camp, barge bas in, and airport. In the event of emergency a
7-64
helicopter can be landed adjacent to the powerhouse near the powerhouse
substation in the lay down area.
7.5.10 Powerhouse Alternatives
The Corp of Engineers previously studied a shallow underground powerhouse
with an underground penstock and pressure tailrace with surge chamber and
an above ground powerhouse with an open rip-rap tailrace. The underground
powerhouse was more expensive and was not preferred.
Only an above ground powerhouse was considered based upon the previous Corp
of Engineers findings. A total of six two-unit powerhouse arrangements
were developed; three capacities, 60 MW, 90 MW, and 135 MW for Pelton or
France turbine generating equipment. Sketches were prepared for each
arrangement in order to accurately depict quantities and form the basis for
the preparation of cost estimates and economic analysis. All the
powerhouse arrangements were technically feasible but the 90 MW Pelton
arrangement was economically preferred.
7-65
7. 6 SUBSTATION AND TRANSMISSION
7.6.1 General
Transmission of the. power from the Bradley Lake plant is over two parallel,
wood pole, 115 kV lines, about 20 miles long. These lines will tap into a
new transmission line to be built by Homer Electric Association between
Fritz Creek and Soldotna. The powerhouse substation is located adjacent to
the powerhouse, as close as possible to minimize the bus connection between
the generators and the step-up transformers. Because of the wide range in
power plant outputs studied, it was deemed prudent to perform a
transmission line analysis to determine a suitable line voltage. The
voltage selected is 115 kV.
7.6.2 Transmission Line Analysis
The Bradley Lake plant represents a substantial addition to the generating
capability of the Kenai Peninsula. The existing transmission system in
this area has already reached its maximum capacity without the addition of
Bradley Lake. Therefore, it became imperative to perform a transmission
line analysis to determine transmission requirements when Bradley Lake
becomes operational. SWEC performed this study and details of findings are
given in Appendix C of this report. A similar study was made previously by
the Alaska Power Administration and is included in the COE General Design
Memorandum No. 2 for Bradley Lake. The purpose of the present study is to
determine the suitable operating voltage for the transmission lines from
Bradley Lake and to determine if the existing transmission line system will
be capable of economically transmitting the additional power generated by
Bradley Lake.
As a result of the analysis the following conclusions have been reached:
0 Two parallel 115 KV, 3-phase, full
reliably transmit the power from
peninsula transmission system.
7-66
capacity lines are required to
the Bradley Lake plant to the
o For Bradley Lake plant outputs up to and including 90 MW, a second
transmission line between Anchorage and Soldotna is not required.
o For Bradley Lake plant output of 135 MW, a second transmission line,
preferably rated 230 KV, is required between Anchorage and Soldotna.
For maximum reliability, this transmission line should be installed
over a different route than the existing Anchorage to Soldotna line. A
suggested route would be similar to the existing gas pipeline route,
with a submarine cable crossing Turnagain Arm, at the east end of
Chickaloon Bay. The requirement for a second transmission line between
the above two points is based on a substantial portion of the power
from Bradley Lake being exported to Anchorage on a normal basis.
o By the year 1995, a new switchyard will be required at Kasilof to tie
the two Diamond Ridge-to-Soldotna lines together. This will "stiffen"
up the system and increase its transmission capability.
The Anchorage/Kenai Peninsuia transmission systems were modeled on a
computer. The computer program·used for this purpose is the Electric Power
Research Institute (EPRI) Transient Midterm Stability Program. Updated
transmission line data was introduced into the computer representing about
25 buses on the Kenai Peninsula. The Anchorage area was represented .• as a
single bus. Included were all generating facilities in Anchorage and the
Kenai Peninsula areas. Peak load flows for the years 1983 to 2003 were
determined using data developed for the Alaska Power Authority, by
Harza-Ebasco in July 1983. Several load flow cases were simulated on the
computer to determine their effect on the lines, such as losses and voltage
levels. Most of the load flows were for the 135 MW plant, during the year
1988. Some 135 MW plant load flows were simulated for the years 1995 and
2003. The effects on the system, stability, losses and bus voltages were
determined by simulating several different transmission line outages.
The peak load forecasts for the years 1983 to 2003 were obtained from the
Harza-Ebasco Susitna FERC License Application dated July 1983. The load
forecasts were based on the "Sherman H. Clark Association NSD Case", which
listed the Anchorage Area peak load forecasts for each year. Based on
7-67
historical data, it was determined that the Kenai Peninsula loads were
approximately 15% of the Anchorage area loads. This value was used for the
load flow studies. For individual bus loads within the Kenai Peninsula
transmission ·system, Exhibit A1 of the "Feasibility Study of the
Soldotna-Fritz Creek Transmission Line", June 1983 by Gilbert/Commonwealth
was used. Individual bus loads were assumed to increase uniformly at the
same rate as the overall Kenai forecasted loads.
The results and conclusions of the load flow studies are based on the
following assumptions:
(1) The present transmission system will be expanded to include a new 115
kV line from Fritz Creek to Soldotna prior to commercial operation of
the Bradley Lake Plant.
(2) Existing generating capacity at Bernice Lake is 70 MW and is 15 MW at
Cooper Lake. No other generation, other than Bradley Lake will be
installed through the year 2003.
(3) Acceptable line losses are 10% and acceptable bus voltages are 90% of
rated.
(4) Bernice Lake will not normally generate power after Bradley Lake is
built, but will provide reserve power for emergencies.
A power flow diagram was developed for each load flow case. These are
shown in the detailed report of the Transmission Line Analysis found in
Appendix C.
7.6.3 Powerhouse Substation
The substation, shown by Plate 15, is designed in a unitized arrangement.
Each generator is connected to a separate step-up transformer, which in
turn is connected to a line circuit breaker, then to a transmission line.
In addition, the substation contains voltage transformers to measure line
voltages, vertical break disconnecting switches and the transmission line
7-68
steel termination towers. The power transformers are furnished with water
spray fire protection and oil spill collection systems. A tie circuit
breaker is connected between the two 115 kV circuits. This breaker is
normally closed to allow power in the Soldotna-Fritz Creek transmission
line to flow through the Bradley Lake substation. The substation is
designed to transmit the full output of the plant with the loss or removal
of one of the two line circuit breakers. Conventional outdoor equipment is
utilized in the substation. The power transformers are oil-immersed,
tripled rated, OA/FA/FA-33. 8/45/56.3 MVA, three-phase, 60 HZ, HV 115 kV
grounded wye, LV 13.8 kV delta. Winding rise is 65°C above an average
ambient of 30°C. The circuit breakers are oil immersed, 121 kV class,
3-pole 1200 amp. continuous, 40,000 amp. interrupting. The disconnecting
switches are 115 kV, 3 pole, 1200 amp continuous, manually operated, with
grounding switches. There are six single phase coupling capacitor voltage
transformers rated 115 kV to 115 volts, with dual secondaries. Because of
the close proximity of the substation to a body of salt water, all outdoor
equipment bushings and substation insulators are extra creep design. A
copper ground grid is embedded in the substation which is connected to the
substation steel work, the steel fencing, and to the powerhouse grounding
system. The surface of the substation consists of crushed rock.
7.6.4 Transmission Lines
The transmission facilities for the Bradley Lake project consist of two
parallel 115 kV three-phase lines. The proposed routing of the lines is
shown on Plate 2. The lines originate at the powerhouse substation and
terminate at a location called Bradley Junction, where the two lines tap
into a new line to be built by Homer Electric Association (HEA) between
Fritz Creek and Soldotna. This new (HEA) line will be in place before the
. Bradley Lake plant becomes operational. The feasibility study relating to
the transmission line systems associated with the Bradley Lake development
was prepared by the firm of . Dryden and LaRue and is contained in this
report as Appendix D.
The selection of the line routing was based, in general, on the COE
original routing, with some minor changes. These changes are the result of
7-69
some geological investigations and determinations of private land
ownership. The selected routing avoids the southern boundary of the Kenai
National Moose Range, and minimizes private property crossings. In
addition, the selected route minimizes the visual impacts of the line and
its right-of-way clearing. The selected routing also avoids soft muskeg,
swamp and mud areas where line maintenance would be difficult.
The design of the lines is based on National Electric Safety Code, grade
"B" construction, and· the Design Manual for High Voltage Transmission
Lines, REA Bulletin 62-1, revised August 1980. The structures consist of
single circuit H-frame wood poles, as shown in Plate 15. The poles are 80
feet long, with embedment from 10 to 14 feet, depending on the soil
conditions. The average span between structures is 1000 feet. The selected
conductor is 556.5 KCM, ACSR, code name "Dove".
The two lines from the plant connect into the Homer Electric Association
Fritz Creek line to Soldotna, at Bradley Junction. At this location, there
are three independent, manually operated disconnecting switches. The
switches will normally be set so that all power in the Fritz Creek/Soldotna
line will flow through the Bradley Lake powerhouse substation. In an
emergency, the switches at Bradley Junction can be operated to isolate the
Bradley Lake plant lines and close the gap in the Fritz Creek/Soldotna line
to allow power in that line to bypass the Bradley lake plant substation.
The COE envisioned electrically operated load break switches, remotely
operated, at Bradley Junction. Because of its remote location, this design
would be difficult to accomplish. A source of power would be needed to
operate the switches, communication and control equipment.
The need for remote control of the equipment at Bradley Junction can be
investigated further at a later date.
Due to the inaccessibility of a large portion of the transmission lines to
normally utilized maintenance vehicles, maintenance costs for the lines
will be relatively higher than that for other, more accessible lines. Much
of the equipment required for line maintenance will be used only for
emergency repairs, and will be used rarely for normal operations. Roads
7-70
are not practical and environmentally not desirable or even allowed. The
line will be patrolled and even repaired by helicopter. All terrain
vehicles CATV's) will be used to maintain parts of the line, using the
right-of-way for access. The structures are designed to be installed and
maintained by helicopter. Storage space is provided at the Bradley lake
plant for various items of line maintenance equipment and supplies.
The recommended transmission line right-of-way and clearing limits have
been determined on the basis of the following:
o Construction of two, 115 kV, 3-phase transmission lines simultaneously
and side-by-side.
o Minimum width necessary to maintain proper clearance between lines and
to the edge of the clearing due to high winds and falling line
structures.
o Minimum width necessary to allow clear cutting removal of all major
foliage directly under the line and within limits that might threaten
line interference in the future.
0 Minimum width necessary to allow selective cutting of
timber adjacent to the line to eliminate danger trees
across the power lines or structures.
the tallest
from falling
o Minimum width necessary to provide favorable blending of the
right-of-way with natural surrounding environment.
This determination indicates a clear cutting width of 225 feet along the
right of way. To prevent 100 foot high trees from interfering with the
line, a selective cutting width of 325 feet will be required. Only the
tallest danger trees will be selectively cut in this additional area beyond
the clear cut right-of-way.
7-71
7.6.5 Kenai Peninsula-Anchorage Transmission Line
Two transmission line routes are investigated that would connect the Kenai
Peninsula to Anchorage. These investigations were for the purpose of
developing costs for use in the economic evaluation studies. One route
follows the existing 115 kV line and the second route examined a line that
follows the existing gas line to Chickaloon Bay and crosses Turnagain Arm
with submarine cable. The study efforts and findings for this transmission
line are given in Appendix D of this report.
7.6.6 Alternatives
An alternative 115 kV substation consisting of gas insulated equipment,
utilizing sulphur hexafluoride (SF6) gas under pressure as the insulating
medium was also investigated. See Figure 7. 6-1. The entire equipment for
this substation is installed in a weather proof enclosures at the factory
and shipped to the jobsite as a modular unit. The complete module is
approximately 15 feet wide by 30 feet long by 12 feet high, and the weight
I
including all equipment, is about 25 to 30 tons. Outdoor installation of
the gas insulated equipment was investigated. However, because of the
adverse effect on the gas insulating medium by low temperatures expected at
the project location, it was decided to utilize an enclosed substation.
The gas insulated substation (GIS) arrangement is more costly initially
over a substation utilizing conventional equipment. However, the GIS
substation requires only a fraction of the space needed by the conventional
equipment and can be installed with a minimum of time and on-site labor.
In addition, the modular GIS substation can be completely checked and
tested in the factory, thus minimizing field testing and delay during
initial plant operation. The enclosed substation protects the HV equipment
from the elements and reduces the cost of maintenance. The substation
equipment includes a line breaker for each line, and a tie breaker
connected between each line. Each breaker is equipped with disconnecting
switches to isolate the breakers during maintenance and repair. Included
are current and potential trans formers to measure line currents and bus
voltages. The tie breaker is normally closed to allow power in the
Soldotna-Fritz Creek transmission line to flow through the Bradley Lake
7-72
substation. The substation is designed to transmit the full output of the
plant with either the loss of or removal of one of the two line circuit
breakers. A copper ground grid is embedded in the substation surrounding
the power transformers and the substation module. This grid is connected
to the substation steel work, all equipment enclosures, and to the
powerhouse grounding system. Connection of the 115 kV GIS equipment to the
power transformers is through a GIS bus passing through the substation
module wall, and the use of SF6-oil transformer bushings. The 115 kV power
is brought out of the substation module via SF6-to-air insulating bushings
which are connected to the overhead transmission lines. The modular
substation includes all controls for the breakers and motor-operated
switches, wired and tested for proper operation in the factory.
control cabinets are installed inside the module.
These
Alternative types of transmission lines from the Bradley Lake project to
the Homer Electric Association line were not investigated during ... this
';..~'
study. However, buried and submarine cable alternatives were considered by
the COE. These alternatives were dismissed by the COE as being too costly
or impractical.
7-73
7. 7 CONSTRUCTION FACILITIES
7. 7. 1 General
The recommended project requires the development of facilities for access
to and within the project area during construction. Also, facilities for
housing of personnel and for storage of construction and operational
equipment are provided. Whenever possible, facilities required during
construction will be so located and designed that they may be used as
permanent facilities to serve the long term needs of the project.
Facilities not needed for long term project use will be removed and the
affected grounds reasonably restored to allow for the reestablishment of
natural conditions. Permanent access facilities have been identified and
are discussed in Section 7.1 of this report.
Essentially all constructio1_1 facilities will be developed under the first
construction contract and will include: development o.f staging areas and
camp sites; domestic water supply and sewage disposal and/or treatment
plant; housing for permanent plant operations personnel and construction
manager and engineering support staffs; field laboratory testing,
warehousing, and garaging structures. Also to be provided under the first
construction contract are the essential services to these facilities
including heating, water, sanitary disposal systems, and electricity. The
key facilities and services to be provided are described in greater detail
in the following paragraphs.
7. 7. 2 Staging Areas
Two staging areas
approximately 150
are planned
feet by 350
development of the barge bas in
for
feet
the
is
project. A small staging area
being provided
access way. The area is
as part of the
located at the
terminus of the barge basin and will serve as a temporary laydown area for
off loading personnel, equipment, and supplies needed for project
development. This area will become the permanent staging area of the
project after completion of construction.
7-74
The second and main staging area for construction needs is to be located at
the south side of Sheep Point. This area is presently sized as 600 feet by
1, 000 feet. However, further study of construction and scheduling needs
for equipment and material should result in a reduction to the staging area
requirements. This area will serve as laydown and storage area for each of
the contractors on the project and for the construction manager's needs in
storing of equipment and supplies. Temporary warehousing and garaging
facilities as well as diesel electric power facilities and fuel needs will
be located here. In addition, the laboratory testing facilities could be
located in this area.
7 . 7 . 3 Camp Areas
Two camps of modular construction are proposed for the project. The
two-camp concept locates the work force closer to the area ~f construction
activity. Approximately half of the work force will be working on the dam,
';;;
upper tunnel work, upper access roads, the Middle Fork diversion, and upper
reservoir area. The other half would b~ working on construction efforts
closer to the lower camp, such a lower access road construction, the power
tunnel, the pov1erhouse, and the transmission line. The main advantages of
splitting the camps are safety of personnel, shorter travel time, increased
job accessibility, and better production and efficiency for the
construction efforts, particularly during inclement weather. The
disadvantages are additional costs, duplication of utilities, and the early
establishment of the upper camp site before access roads are built. The
evaluation and studies for the camp sites are discussed in greater detail
in Appendix B. Reconnaissance and map interpretation have identified an
acceptable location for the lower camp site and a suitable location for the
upper camp site.
The lower camp area reviewed was that previously identified by the COE in
Design Memorandum No. 3. The camp area is located within the floodplain of
Battle Creek, approximately 1, 000 feet southeast of the main staging area
and near the proposed access road serving the upper dam site. Unvegetated
overflow channels are found throughout the east end of the camp area;
however, soil borings show excellent foundation material. The positive
7-75
aspects of
proximity
floodplain.
the site, the foundation conditions, flatness, size, and
to the work area offset the fact that site is within the
This negative aspect is further offset with the location and
properly design road section that acts to protect the site from floods.
This site is planned for development to accommodate about 240 beds.
Suitable housing and recreational facilities will be provided for the
crafts. In addition, office and housing facilities are being provided for
the needs of contractor's management staff and for staff personnel of the
Construction Manager and Engineering Support Services. Messing facilities
are being provided to accommodate all personnel using the camp site,
including Owner's personnel housed elsewhere. All of the lower camp site
facilities can be mobilized by landing craft or barge, then skidded in with
a cat or driven in by truck.
Several locations were investigated near the dam for a suitable upper camp
site. The only suitable site located is about 1. 2 miles due west of the
dam near the proposed access road. The site has 4.6 acres of land under 20
percent slope, an apparent water supply, and an area for a sewage lagoon
that drains away from the water supply. However, shallow soil conditions
present some problems in site development and it is likely that sanitary
effluents will need to be trucked to the lower site facilities for
disposal. Also, because of difficult early accessibility to the site area,
all mobilization must be by helicopter for site development and early use,
until the access road is completed. The upper camp site is planned for up
to 210 bed capacity. The camp will serve also construction and management
staff activities associated with work in the dam area, within the
reservoir, and most likely for work on the Middle Fork diversion. Offices,
recreational, and messing facilities are provided.
As previously stated, office and messing facilities for Owner's personnel
are provided at each camp area, as appropriate. However, it is planned to
use the permanent plant housing accommodations as sleeping quarters for
Owner's personnel. In addition, a project liaison office will be
established in Homer to serve the needs of the Owner and its Construction
Manager. Permanent plant warehousing, garaging, and other facilities will
7-76
be installed under the first construction contract for early use by the
Owner and its Construction Manager.
7. 7.4 Borrow and Waste Area Access
Access roads to borrow areas will be either by fill embankment sections or
grade cut-fill sections. One major access road has been identified for the
project. This is a 1.4 mile road for borrow from the Martin River Delta
area. The road alignment previously identified by the COE was reviewed and
was determined to be reasonable and used under this study. The road will
begin near the lower camp and extend in a westernly alignment to borrow
areas at the Martin River Delta. This is considered a temporary access
road and will be removed and the surrounding terrain rehabilitated. Its
development would consist of essentially leveling and grading the terrain
of alluvial fans at about a grade contour of elevation 12 feet. Because of
its temporary nature no rip rap protection or gravel top course are
provided in its construction. A bridge crossing is required at Battle
Creek. That portion of the access road requiring fill/borrow has been
assumed as a one lane road. The graded portions of the road are developed
as a two lane travelway.
Other borrow access roads identified are those relating to the rock
quarrying operations for the rockfill dam. These roads are essentially in
rock cut and become part of the quarry operations. The roads are within
the reservoir area and will be essentially inundated by the increased
reservoir height.
Waste areas will be located as close as possible to the work so as to
minimize their impact and the need for access roads.
7. 7.5 Construction at Dam Site
The preferred plan places the dam and other adjacent project structures
within the compact river channel area near the outlet of Bradley Lake.
This consolidates construction activities within a small area. The major
construction efforts at the dam site are: the dam and its spillway; the
7-77
diversion tunnel; the power tunnel intake channel and intake structure; and
the gate structure and adjacent tunnel and inclined shaft.
Construction facilities at the dam site will consist of office trailers, a
small concrete hatching plant, and the short roads needed to access the
various construction activities. Construction activities and access roads
relating to the placement of dam fill material, the concrete facing, the
intake channel and intake structure, and the power tunnel work will all be
located within the reservoir and eventually these structures will be under
water when the reservoir is raised. The construction access road, placed
downstream of the dam and used to develop the diversion tunnel, will be
refurbished and used as a permanent access to this structure. The gate
shaft is located near the main access road for the dam and requires only
little additional work for its development. Similarly, bridging of Bradley
River, needed for the construction of the diversion tunnel, would be
removed prior to constructing the dam.
7.7.6 Construction.at Powerhouse
Under the preferred plan the excavations required for the power tunnel
portal and the powerhouse are combined into one single excavation.
Excavated material is placed in the tidal flats adjacent to the shore to
create laydown and work areas for construction, including an area for
onsite office trailers and the diesel generating equipment needed for
powering the tunnel boring machine and for lighting this area. After
construction these laydown areas would serve the permanent plant. One area
will be used for development of the plant substation and the other will
form an access area for plant maintenance needs.
7. 7. 7 Water Supply
The first construction contractor will be required to develop the water
system for the project needs. The water supply for domestic water will be
designed to provide the domestic flow demand of the construction camp or
the fire flow demand, whichever is greater. For the lower camp, the water
supply will be from surface runoff or underground sources. Water treatment
7-78
facilities will be provided to assure good quality and safe potable water.
It is anticipated that ground water treatment will consist only of
chlorination; however, surface water may require more extensive
treatment, including sedimentation and filtering. It is more likely that
wells will be developed for the water supply. The water system for
construction needs will be designed so that it can also serve the long term
needs of the permanent plant. Water for construction will be similarly
collected and treated only to the extent required for good concrete
development. Domestic water sources will be developed in full compliance
with applicable regulations.
Domestic water needs for the upper camp will be from the lake adjacent to
the camp or other nearby lakes. The water supply will be sized to provide
either the domestic needs of the camp or fire fighting needs, whichever is
greater. It is anticipated that the water treatment will be by filtration
and chlorination. It is doubtful that a ground water source can be
developed for the upper camp area. Water for construction will be from
Bradley Lake. Some treatment by filtering may be required to remove
suspended material.
7. 7. 8 Sewage Disposal
The first construction contractor will be. required to develop the sewage
collection system and connect it to the appropriate facilities. Waste
water will be placed in an aerated sewage lagoon. Effluent will be
discharged into Battle Creek or some other point acceptable to the
controlling agency.
Because it is likely that suitable sewage treatment facilities cannot be
developed at the upper camp site, it is planned to provide a series of
holding tanks to retain waste material. The waste material will be trucked
to the lower camp sewage facilities for treatment and disposal. Additional
field investigations are needed to better define sewage handling for the
upper camp.
7-79
7.7.9 Electric Power
Electric power for construction and domestic needs will be under the
responsibility of the first construction contractor. This contractor will
be the first on site, will require the greatest· amount of electrical energy
and will be responsible for the establishment and operation of all camp
facilities. It is anticipated that about 5 to 6 MW of capacity will be
needed at the lower construction area. Of this, 2 to 3 MW will be required
by the tunnel boring machine, about 1 MW for the lower camp and
miscellaneous housing, warehouse and garaging facilities, and about 1 MW
for lighting of the main storage and construction areas. Additional diesel
generated power will need to be provided at the upper camp and construction
area. It is anticipated that about 2 MW of capacity will be needed to
serve these facilities. Adequate fuel supply and reserves will be provided
to allow for 2 weeks of operation without refueling. Fuel storage will be
developed in full compliance of State and Federal requirements.
7.7.10 Other Facilities
Facilities for storage of explosives will be provided at appropriate and
safe locations in full compliance with State and Federal requirements.
7-80
7. 8 BUILDINGS, GROUNDS AND UTILITIES
7.8.1 General
The remote Bradley Lake Project site will have air or waterborne access
only. The plant will be computer controlled and remotely dispatched via a
microwave link. A resident staff will be required to perform daily
operation functions and routine maintenance.
The project site is relatively close to Homer, but because of limited
access, onsite facilities and operations equipment must be provided to
perform all necessary maintenance and repair.
The permanent buildings, grounds and utilities required are located near
the lower construction camp adjacent to Battle Creek. Family residences
are provided for each of the permanent onsite personnel. In addition, a
twelve man bunkhouse with kitchen facilities is provided in the event more
personnel are required onsite during periods of major maintenance.
7. 8. 2 Staffing
The permanent resident staff will consist of a plant supervisor and three
maintenance-operators. Additional maintenance personnel would be assigned
to the site during periods of major maintenance on a temporary basis.
Dispatching will be performed remotely by the operating utility. Since the
area utilities presently have 24 hour dispatch coverage, no additional
dispatch personnel are required.
7. 8. 3 Maintenance Facilities
The following maintenance facilities are provided:
o 10,000 square feet warehouse and machine shop
o Outside fenced-in storage area
o Outside fenced-in parking area for operations equipment
o Fuel storage -underground tanks for gas and diesel fuel
7-81
One of the construction warehouses will be left in place as part of the
permanent building facilities. This warehouse will be remodeled to include
4000 square feet of bin and rack storage, 2000 square feet for the machine
shop, and the remaining floor area will be open for laydown work and
vehicle maintenance. Additional tool and small part storage is provided on
the generator floor of the powerhouse.
Designated outside fenced-in parking and storage areas are provided. A
6000 square feet fenced-in gravel surfaced area is provided adjacent to the
warehouse, to park the operations equipment. Outlets for resistance
heaters would be provided at each parking space. A 6000 square feet
fenced-in gravel surfaced storage area is provided also adjacent to the
warehouse. Bulk outdoor storage racks are provided for material storage.
Fuel storage will utilize underground tanks of 10,000 gallon capacity, one
each for gasoline and diesel fuel.
7. 8. 4 Operations Equipment
A comprehensive list of operating equipment was made available to the
Alaska Power Authority. Included are heavy road and building maintenance
equipment, machine shop equipment and maintenance equipment for each
project structure. The capital cost of this equipment is included in the
project cost estimate and a sinking fund is included in the annual
operations and maintenance budget estimate for future equipment replacement.
7.8.5 Residential and Office Facilities
The residential facilities are as follows:
3 -three bedroom houses (permanent personnel quarters)
1 -four bedroom house (supervisors quarters)
1 -twelve bed bunkhouse with kitchen facilities (temporary personnel
quarters)
The permanent houses will be architecturally blended into the timber
adjacent to the lower construction camp site and above the flood plain.
7-82
Each residence will be separated from each other and the warehouse,
bunkhouse and other permanent camp facilities, to permit some seclusion and
privacy. The office facilities are part of the control room in the
powerhouse. A small office and conference room will be included in the
bunkhouse. Due to the site's isolation, facilities will be incorporated
into the permanent residences for long term subsistence. Fireplaces and
wood stoves would also be provided for back-up heating. A stand-by diesel
generator is provided in the event of power loss. Telephone communication
will be provided via microwave link.
7 .8.6 Water
Surface or well water resources can be developed to provide domestic water
for the construction camps and permanent camp. To be conservative, water
treatment facilities are based on a surface water source. Well water would
simply require chlorination. The domestic water would be furnished as part
of the contract which develops the construction camps. Each residence,
bunkhouse and warehouse has a 200 gallon capacity domestic water storage
tank. A separate domestic water system is provided at the powerhouse
including extensive treatment facilities. The powerhouse domestic water is
also used for generator equipment cooling. Drinking water at the dam,
intake gate shaft, and other locations will be transported with personnel.
7. 8. 7 Wastewater Treatment and Disposal
Aerated lagoons are provided for the lower construction camp, but may be
too far removed from the permanent camp facilities to be retained. A
conventional septic tank and drain field is therefore provided for each
permanent residence, bunkhouse, and warehouse. Effluent will be
transported from the upper construction camp to the lower construction camp
facilities for treatment. The powerhouse has a self-contained sewage
treatment module. The treatment and disposal method will comply with
applicable Federal and State standards, and the applicable permits will be
obtained. Portable toilets will be used at other site locations.
7-83
7. 8. 8 Fire Protection
Each structure will be furnished with a minimum of two means of egress.
Emergency lighting and smoke alarms will be provided in each structure.
Fire water will be provided by the domestic water system supplemented by
surface water at the permanent camp. The powerhouse has two fire
protection systems, one water and the other carbon dioxide. Hand fire
extinguishers are provided in each building.
7.8.9 Project Physical Security
Vandalism and theft after construction are not anticipated due to the
remoteness of the project site. However, steel doors with dead bolt
security locks will be provided for the exterior doors of all project
structures. Chain link fencing with two top barb wires will surround the
powerhouse substation and designated project storage areas.
these fenced areas will be through locked gates.
7. 8.10 Solid Waste Facilities
Access into
Solid waste disposal will be in accordance with applicable Federal and
State requirements. Several methods of disposal are under consideration,
including incineration, local sanitary land fill operated by project
personnel, and containerization and transportation of solid waste to a
suitable disposal site. The local sanitary land fill operated by project
personnel may be the most economical but additional study is required. All
necessary permits will be obtained.
7 .8.11 Other Facilities
Site Power will be provided by the station service facilities at the
powerhouse. Standby diesel generators are provided at the permanent
building area and powerhouse for emergency and start-up power. Small
propane generators and batteries are provided at the intake gate shaft and
diversion gate house for power.
7-84
7. 9 MIDDLE FORK DIVERSION
7 . 9. 1 General
The Middle Fork Diversion is located approximately one mile north of
Bradley Lake in an adjacent drainage at elevation 2,200 on the Middle Fork
stream. The Middle Fork Diversion facilities consist of a small dam,
spillway, and two diversion lines. One line is provided for initial
construction efforts to bypass natural streamflows, and subsequently to
serve as a permanent outlet for downstream releases. The other main
diversion line conveys water to Marmot Creek, a tributary to Bradley Lake.
The interbasin diversion facility which will be operational· from May
through October, provides additional water to the Bradley Lake reservoir
and increases the energy benefits for the project approximately 1,000 KWHR
for every acre-foot diverted.
7. 9. 2 Recommended Plan
The recommended plan for developing the Middle Fork Diversion is a small 20
foot high rockfill dam with a sheet pile cut-off wall and an excavated
channel spillway in the right abutment. The main diversion line and low
level outlet intake works are integral with the dam. The low level outlet
serves as a temporary diversion during construction of the dam, spillway,
and main diversion flow line intake. Both the main diversion line and low
level outlet are 6 foot diameter steel pipes with face mounted manually
operated intake sluice gates.
The main diversion line is approximately 1, 900 feet long and is buried
along its entire length with a slope of 0.6 percent. The terrain along the
proposed alignment is typically exposed bedrock, and "drill and shoot"
excavation techniques are required. The pipeline bedding and cover
material is shot rock from the excavation.
The low level outlet is located. in an excavated rock trench on the left
bank. The low level outlet pipe invert is located approximately 3 feet
below the natural stream channel bottom elevation to permit streamflow
7-85
diversion during the dam and spillway construction and allow the reservoir
to be lowered for intake sluice gate inspection. It also serves as a
permanent outlet for downstream releases during the November through April
period.
The intake for the main diversion line and the low level outlet is a
reinforced concrete structure with a platform for the manual operators at
elevation 2,212. The intake works encases the 6 foot diameter pipes and
provides anchorage for the intake sluice gates and operators.
The spillway is a 30 feet wide channel located in the right abutment. The
material excavated for the spillway will be used for the dam rockfill. A
30 feet wide, 4 feet high concrete wier with crest at elevation 2, 204 is
located in the spillway channel at the dam axis. The spillway channel is
excavated in bedrock and is not lined. The Middle Fork Diversion concept
is shown on Plates 16 and 17.
7 .9.3 Geology
The bedrock in the area between the Middle Fork Diversion and Marmot Creek
is predominantly graywacke with argillite interbeds. Much of the proposed
route is covered with talus and muskeg swamps, which prevented a detailed
assessment of geologic conditions. Overburden depths vary from less than 1
foot to over 15 feet as determined by seismic refraction surveys by
others. Gravel and/or sand footings may be required for diversion pipe
supports. For such support systems, the bedrock structure should not
present any stability problems. This information is derived from COE data;
the scope of this current study did not include further investigation of
this area.
7 . 9. 4 Technical Details
The hydraulic rating curves for the spillway and main diversion line are
shown on Figure 7. 9-1. The main diversion line can pass 450 cfs into
Marmot Creek without spillway discharges occurring at the diversion dam.
The spillway can pass about 1,600 cfs at pool elevation 2,210 which exceeds
7-86
the 100 year design flood discharge with no flow in the main diversion line
and 2 feet of freeboard on the dam crest. The main diversion line can pass
an additional 6 70 cfs if operational with the pool at elevation 2, 210.
Should streamflows exceed 1,600 cfs (or 2,300 cfs if the line is
operational), the water level will continue to rise until the dam is
overtopped at pool elevation 2,212 which corresponds to a spillway flow of
2, 600 cfs. The combined capacity of the spillway and main diversion pipe
at pool elevation 2, 212 is approximately 3, 400 cfs. This represents about
85 percent of the PMF peak flow as determined by the COE. Should the
diversion dam be overtopped little damage is anticipated to either the dam,
flow lines, or the downstream river section, and it is not justified to
design the structures for larger and more improbable design flows. The
main diversion line and low level outlet will be vented downstream of the
intake sluice gates.
Field observations indicate
streambeds are cut into rock.
that the Middle Fork and Marmot Creek
The spillway channel is excavated in rock
and directs discharges into the natural streambed downstream of the dam
toe. The low level outlet discharges water onto a concrete apron and into
the natural streambed also downstream of the dam toe.
The COE expected some limited erosion of the tundra and soil cover below
the outlet of the main diversion line. This appears reasonable based on
field observations in this locale and the Marmot Creek streambed.
The COE field observations indicated that snow remained in the diversion
area well into August but that snow slide areas were not evident. SWEC
concurs with the COE that a buried pipeline is the most reliable means to
convey diverted waters to the Bradley Reservoir during the May to October
period. Snow is likely to drift and pack itself against an exposed
pipeline resulting in large external loads from snow creep. Technically
the buried pipeline offers the best solution.
Operating the main diversion line from May to October will limit ice
formation in the diversion pipeline or low level outlet. The reinforced
7-87
concrete intake structure, rockfill dam, and reinforced concrete spillway
weir offer suitable ice resistance.
7.9.5 Dam, Gates, and Conduit
The rockfill dam will be approximately 140 feet long and 20 feet high with
a central sheet pile cut off wall embedded in a rock key. along the dam
axis. A 15 feet deep grout curtain seals the foundation rock below the
concrete key. The 6 feet diameter diversion pipes are encased in
reinforced concrete at the rock key and the sheet pile is embedded in the
encasement. At each end of the dam the sheet pile is embedded in concrete
keyed into the abutment rock.
The concrete spillway weir, 4 feet high . and 30 feet long, is also keyed
into the foundation rock, and the 15 feet deep grout curtain along the dam
axis is continued under the weir and into the right abutment. The spillway
weir crest is 8 feet below the top of the dam.
The main diversion line consists of a common intake structure with the low ·
level outlet) a 6 feet entrance sluice gate with manual operator, a 1,900
feet long, 6 feet diameter, 3/8 inch thick steel pipe buried throughout its
length to preclude snow creep damage, and a screened outlet. The low level
outlet consists of a intake structure common with the main diversion line,
a 6 feet entrance sluice gate with a manual operator, a 6 feet diameter 3/8
inch thick steel pipe embedded in the dam, a screened outlet to prevent
entry, and a concrete apron downstream of the outlet.
7 .9.6 Access
Access to the Middle Fork Diversion during construction will be by
helicopter. Sky cranes will be used to transport personnel, material, and
construction equipment. Two helicopter trips will be required to the
Middle Fork Dam each year for operations and maintenance, one trip in May
and one in October. The trip in May will be required to open the Main
Diversion flow line sluice gate and close the low level outlet sluice
7-88
gate. The October trip will be required to close the diversion gate and
open the low level outlet gate.
The COE studies concluded that an access road to the Middle Fork Diversion
is not recommended. SWEC concurs with this recommendation, however, remote
telemetry to control the sluice gates or monitor Middle Fork flows as
recommended by the COE, will impose an additional operations and
maintenance expense which is considered unwarranted.
7. 9. 7 Alternatives
The COE considered several types of diversion dams and conveyance
alternatives. The COE concluded that an uncovered trapezoidal channel
would be blocked by snow and ice for parts of the planned operation period
between May and October and that it would not be feasible to keep the
channel free to pass the required discharge. Also, the COE studied an
·;'5 .•
above ground pipel~ne and concluded it would be uneconomical to design the
pipe to resist the large forces exerted by the snow cover. The COE
concluded that a buried pipeline is the best method for conveyance of
diversion flows from the dam to the Bradley Lake drainage basin. SWEC
reviewed the various conveyance alternatives and concurs with these
conclusions.
The COE developed timber dam, concrete dam, and a metal binwall dam
alternatives at Middle Fork. SWEC developed two additional alternatives:
A concrete faced rockfill and a central sheet-pile cutoff rock fill dam.
The rockfill dams utilize rock available at the dam site. Haterial
excavated from the spillway is utilized for the dam rock fill. Due to the
remoteness of the Middle Fork Dam durability and ability of the dam to
resist the elements is of prime importance. A substantial dam, as proposed
by SWEC, offers better durability to weather and other severe factors, such
as snow and ice that will be present at the site, and is preferred. The
central sheet-pile cutoff rockfill dam offers better internal drainage
within.the dam, eliminates concrete work, and is technically preferred.
7-89
DESIGN WINDSPEEDS (MPH) AT SHEEP POINT
KACHEMAK BAY, ALASKA
Exceedance Interval (~ears)
Orientation Duration (hours) 2 5 50
210° -260° 1 57 62 68
(summer) 12 47 52 63
300° -30° 1 32 36 47
(winter) 12 21 26 36
(1) After Corps of Engineers, NPS, Design Report Access Channel and
Moorage Basin Facilities.
'----------TABLE 7 .1-1--.~
DESIGN WAVE CHARACTERISTICS (1
SHEEP POINT AND CHUGACHIK ISLAND SITES
KACHEMAK BAY, ALASKA
Freguenc~ (~ears2
Wave 2 5 50
Location Origination Hs (ft) T (sec) Hs (ft) T (sec) Hs (ft) T(sec)
Sheep 250°AZ 4.4 4.3 4.7 4.5 5.1
Point 270°AZ 3.5 3.8 3.8 3.9 4.1
315°AZ 2.0 2.8 2.4 3.1 2.9
.
Chugachik 240°AZ 6.1 5.3 6.7 5.6 7.4
Island 260°AZ. 5.9 5.3 6.5 5.5 7.2
360°AZ 2.2 3.0 2.5 3.2 3.1
(1) After Corps of Engineers, NPS, Design Report Access Channel and Moorage
Basin Facilities.
(2) H (ft) =wave height s
T (sec) = wave period
4. 7
4.1
3.4
5.8
5.7
3.5
""------------TABLE 7.1-2-----.~
POWER
HOUSE
CAPACITY
(MW)
60
90
135
TYPE OF
EVENT
Load
Acceptance
Load
Acceptance
Load
Rejection
Load
Rejection
Load
Acceptance
Load
Acceptance
Load
Rejection
Load
Rejection
Load
Acceptance
Load
Acceptance
Load
Rejection
Load
Rejection
HGL = Hydraulic Grade Line
SYNCHRONOUS
BYPASS
BYPASS VALVE
SIZE (FT)
Valve
Closed
Valve
Closed
2.5 Diameter
65 Sec.
Closure
3.0 Diameter
65 Sec.
Clos.ure
Valve
Closed
Valve
Closed
3.0 Diameter
65 Sec.
Closure
3.5 Diameter
65 Sec.
Closure
Valve
Closed
Valve
Closed
4.0 Diameter
65 Sec.
4.5 Diameter
65 Sec.
WICKET
GATE
CLOSURE
TIME
(SEC)
5
5
5
5
5
5
HYDRAULIC TRANSIENT ANALYSIS
FRANCIS TYPE TURBINES
WICKET
GATE
OPENING
TIME
(SEC)
10
SURGE
TANK
DESCRIPTION
WATER
SURFACE
ELEVATION @
SURGE TANK
(FT)
HGL
PT "A"
POWERHOUSE
(FT)
621
HGL
PT "C"
END OF
STEEL LINER
(FT)
827
HGL
PT "D"
SURGE
TANK
BELOW
ORIFICE
964
HGL
PT "E"
BOTTOM OF
50° SHAFT
(FT)
995
HGL
PT "F"
TOP OF
50° SHAFT
(FT)
1,105
HGL
PT "G"
HEADWATER
LEVEL
(FT)
1,081 15 ft. Tank I.D.
5 ft. Orifice
964
(min) ---------------No Water Column Separation
20
10
20
10
20
15 ft. Tank I.D.
5 ft. Orifice
15 ft. Tank I.D.
5 ft. Orifice
15 ft. Tank I.D.
5 ft. Orifice
15 ft. Tank I.D.
5 ft. Orifice
15 ft. Tank I.D.
5 ft. Orifice
15 ft. Tank I.D.
5 ft. Orifice
15 ft. Tank I.D.
5 ft. Orifice
20 ft. Tank I.D.
6 ft. Orifice
20 ft. Tank I.D.
6 ft. Orifice
20 ft. Tank I.D.
6 ft. Orifice
20 ft. Tank I.D.
6 ft. Orifice
963
(min)
1,149
(max)
fm<>v) 'I.U"'""'-"
932
(min)
930
(min)
1,149
(max)
(max)
924
(min)
922
(min)
1,101
(max)
(max)
810 938 967 1,035 1,047 1,081
---------------No Water Column Separation
1,478 1,425 1,247 1,251 1,222 1,170
No Water Column Separation ------------
1,284 1,282
No \~ater
544 777 933 976 999 1,081
No Water Column Separation ------------
754 907 935 . 1,023 1,038 1,081
No Water Column Separation ------------
1,517 1,449 1,256 1,267 1,231 1,170
No Water Column Separation ------------
l, 318 1, 308
No Water Column Separation ------------
442 711 924 955 978 1,081
No Water,Column Separation ------------
675 863 926. 1,010 1,026 1,081
No Water Column Separation ------------
1,422 l, 383 1,215 1,270 1,232 1,170
No Water Column Separation ------------
1,223 1,218
No Water Column Separation ------------
...__ ____________ _.; _____________ TABLE 7.4-1
POWER NEEDLE
HOUSE TYPE VALVE
CAPACITY OF OPENING
(MW) EVENT TIME (SEC)
60 Load 35
Acceptance
Load 60
Acceptance
Load
Rejection
90 Load 35
Acceptance
Load 60
Acceptance
Load
Rejection
135 Load 35
Acceptance
Load 60
Acceptance
Load
Rejection
HGL -Hydraulic Grade Line
HYDRAULIC TRANSIENT ANALYSIS
PELTON TYPE TURBINES
HGL
NEEDLE HGL PT "C"
VALVE PT "A" END OF
CI,.OSING POWERHOUSE STEEL LINER
TIME (SEC) (FT) (FT)
629 668
(min) --------
768 803
(min) --------
60 1,407 1, 379
(max) --------
543 586
(min) --------
699 740
(min) --------
60 1,479 1,443
(max) --------
437 482
(min) --------
606 653
(min) --------
60 1,599 1,547
(max) --------
HGL HGL
PT "D" PT "E" HGL
BOTTOM OF TOP OF PT "F"
50° SHAFT 50 0 SHAFT HEADWATER
(FT) (FT) LEVEL
1,021 1,051 1,081
No Water Column Separation --------
1,046 1,063 1,081
No Water Column Separation --------
1,196 1,183 1,170
No Water Column Separation --------
1,005 1,042 1,081
No Water Column Separation --------
1,036 1,058 1,081
No Water Column Separation --------
1,204 1,187 1,170
No Water Column Separation --------
981 1,030 1,081
No Water Column Separation --------
1,021 1,051 1,081
No Water Column Separation --------
1,216 1,193 1,170
No Water Column Separation --------
L------~----------~----------TABLE 7.4-2
ROCK CORE PROPERTIES
GREYWACKES, GREYWACKE/ARGILLITE (CATACLASTIC), AND TUFF
Rock Type
(Or Notes)
Sample
No.
Testing(l) Unit Weight
Agency (lb/cu ft)
Gywke/Arg
Greywacke
Greywacke
Greywacke
Gywke/Arg
Greywacke*
Greywacke*
Greywacke*
Gywke/Arg
Gywke/Arg
Gywke/Arg
Greywacke
Greywacke
Greywacke
Greywacke
Gywke/Arg
Greywacke
Gywke/Arg
Greywacke*
Greywacke*
Gywke/Arg
Greywacke
Greywacke
0.224
0.224
Gywke/Arg
Greywacke
Greywacke
Greywacke
S-4
S-5
S-6a
S-6b
J-2
J-3
J-5
J-6
4-l (2)
5-2 (2)
5-"3 (2 )
6-2 (2)
6-3 (2)
7-l
7-2 (2 )
8-10
8-11
9-9
ll-46
12-2
13-31
14-7
16-2 (2 )
2260
2260
R-4
R-6
R-3
R-1
s
s
s
s
J
J
J
J
c
c
c
c
c
c
c
c
c
c
c
c
c
c
c
R
R
R
R
* Probable Tuff or Tuff/Greywacke
(l) S -A. J. Hendron for SWEC
C -u. s. Army Corps of Engineers
J -Atlas Copco Jarva, Inc.
R -The Robbins Co.
(2) From Dam Area
(3) 0 = Least, 6 = Most Abrasive
171
171
172
174
172.8
170.9
170.9
172.8
173.4
171.6
171.6
172.8
172.2
170.9
173.5
170.9
172.2
170.9
172.2
No Test
No Test
168.7
169.0
Unconfined
Compressive Total
Modulus of
Elasticity
(Exl06psi)
Poissons
Ratio (u)
Splitting
Tensile
Strength
Point
Load
(psi)
Shore Chercher(3)
Strength (psi) Hardness (psi) Hardness Abrasivity
12,763
10,168
32,825
34,975
No Test
10,295
No Test
8990
14,900
10,500
10,000
31,200
35,600
26:600
30,000
33,200
30,900
26,800
20,400
11,500
17,200
29,400
34,100
No Test
No Test
12,943
24,413
110.39
108.86
149.84
153.51
Estimated:
10.07
7.22
9.58
11.24
13.80
9.77
10.10
11.14
10.79
10.35
9.45
9.50
10.10
10.43
10.37
0.285
0.375
0.245
0.267
0.355
O_?f-.7 ----· 0.267
0.228
0.249
0.248
0.235
0.265
0.257
0.224
0.224
Tunnel Length Involved -4300 ft
Penetration Rate -6-8 ft/hr
Delay Time -N/ A
1600
860
No Test
1770
2070
No Test
2400
2320
1950
2820
1650
No Test
1900
2180
2260
10.0
6.1
9.1
8.0
7.9
No Test
No Test
8.4
73.4
72.1
73.0
73.1
Temporary Support -Selectively located, 3/4 in. diameter,
3.0
2.0
2.4
3.2
6 ft long, mechanically -anchored rock bolts. Two bolts
per 4 lin. ft; 215 bolts total
~------------------------~~--------------~----TABLE
Abrasion
Hardness
5.1
5.4 -
5.85
6.3
7.4-3 ___,
Rock Type Sample Testing(!) Unit Weight
(Or Notes) No. Agency (lb/cu ft)
S-1 s 171
H-lA s 170.5
H-lB s 169.5
H-2 s 169.4
Moderately H-3 s 169.7
Siliceous
V. Weak J-1 J
Foliation
J-8 J
Slightly J-11 J
Cherty
V. Weak R-9 R 165.5
Fo11iation
R-10 R Not Tested
Slightly R-7 R Not Tested
Cherty
(l) S -A. J. Hendron for SWEC
C -u. S. Army Corps of Engineers
J -Atlas Copco Jarva, Inc.
R -The Robbins Co.
(2) From Dam Area
(3) 0 = Least, 6 = Most Abrasive
Unconfined
Compressive
Strength (psi)
8,266
18,958
19 '718
12,733
25,820
6,670
8,700
Not Tested
15,784
19,993
Not Tested
ROCK CORE PROPERTIES
MASSIVE ARGILLITE
Modulus of
Total Elast~city Poissons
Hardness (ExlO psi) Ratio (u)
56.73
86.82
85.28
57.40
81.23
..:
Estimated:
Tunnel Length Involved -5000 ft
Penetration Rate -8-10 ft/hr
Delay Time -N/A
Splitting
Tensile Point
Strength Load Shore
(psi) (psi) Hardness
38.6
76.4
71.4
74.8
71.7
7.3
10.0
4.8
No Test
No Test
5.0
Temporary Support -Selectively located, 3/4 in. diameter,
Chercher(3)
Abrasivity
2.2
2.4
2.2
6 ft long, mechanically -anchored rock bolts. Two bolts
per 4 lin. ft; 250 bolts total
Abrasion
Hardness
2.16
3.11
2.95
2.06
3.50
....____-..,..------:----------------~----------TABLE 7.4-4
Rock Type Sample Testing(l) Unit Weight
(Or Notes) No. Agency (lb/cu ft)
A few Ch-llA s 168
Calcite Veins
CH-llB s 168
S2 s 169
9-10 c 169.7
10-13 c 166
Highly J-4 J
Cherty
40% J-9 J
Argillite
70% J-10 J
Argillite
Highly R-11 R No Test
Cherty
40% R-5 R 162.7
Argillite
70% R-8 R No Test
Argillite
Chert S-3 s 165
Nodules
(No dacite
Tested)
(l) s -A. J. Hendron for SWEC
C -u. s. Army Corps of Engineers
J -Atlas Copco Jarva, Inc.
R -The Robbins Co.
(2) From Dam Area
(3) 0 = Least, 6 = Most Abrasive
ROCK CORE PROPERTIES
FOLIATED ARGILLITE
Unconfined Modulus of
Compressive Total Elasticity Poissons
Strength (psi) Hardness (Exl06psi) Ratio (u)
6,661 92.53
5,038 68.65
FOLIATED, CHERITY ARGILLITE, INCLUDING DACITE
2,943 54.67
12,500 7.20 0.119
9540 4.67 0.265
No Test
3915
No Test
No Test
6,945
No Test
4,204 67.28
Estimated:
Tunnel Length Involved -Foliated Argillite,
Penetration Rate -Foliated Argillite, 10-12
Splitting
Tensile Point
Strength Load Shore Chercher ( 3)
(psi) (psi) Hardness Abrasivity
86.3
69.2
69.2
910
1,180
6.8 4.8
4.0 3.8
4.8 2.2
5.9
3.2
No Test
69.6
3500 ft; Folia ted, :Cherty Argillite, 3790 ft
ft/hr; Foliated, Cherty Argillite 8-10 ft/hr
Delay Time -N/A
Temporary Support -(Both Units) Selectively located, 3/4 in. diameter,
6 ft long, mechanically -anchored rock bolts. Two bolts
per 4 ft; 365 bolts total
Abrasion
Hardness
2.16
2.7i
2.57
4.8
L...-.-------------------------r---TABLE 7.4-5
Rock Type Sample Testing(l) Unit Weight
(Or Notes) No. Agency (lb/cu ft)
CH-llD s 167
CH-llE s 168
CH.:..llF s 169
CH-llG s No Test
CH-11H s 167
CH-lli s 168
J-7 J
R-2 R 169.5
(1) S -A. J. Hendron for SWEC
C -U. S. Army Corps of Engineers
J -Atlas Copco Jarva, Inc.
R -The Robbins Co.
(2) From Dam Area
(3) 0 = Least, 6 =Most Abrasive
ROCK CORE PROPERTIES
CHERT
Unconfined Modulus of
Compressive Total Elasticity Poissons
(Exl06psi) Strength (psi) Hardness Ratio (u)
11,121
7,570
9,215
No Test
6,897
8,416
No Test
22,729
199.34
181.04
204.41
171.76
185.39
204.33
Estimated:
Tunnel Length Involved -50 ft.
Penetration Rate -3.0-5.75 ft/hr
Delay Time -N/ A
Splitting
Tensile Point
Strength Load
(psi) (psi)
8.2
8.4
Temporary Support -Selectively located, 3/4 in. diameter,
Shore Ch erch er ( 3)
Hardness Abrasivity
98.3
92.0
91.4
91.2
94.4
99.2
4.4
6 ft long, mechanically -anchored rock bolts. Two bolts
per 4 ft; 6 bolts total
Abrasion
Hardness
11.3
9.6
14.5
8.8
11.8
15.5
.___ ____________ __;,.__,;,.=·-~--.. ---------TABLE 7.4-6 ___,
Sample Testing(!) Unit Weight
Rock Type No. Agency
Altered A Station s
Quartz 242+71
Diorite B Station s
Test
242+11
Fresh A Station s
Quartz 241+59
Diorite B Station s
241+59
C Station s
241+59
A1 tered SR-1 s
Quartz Station
Diorite 224+64
Fresh Hr-1 s
Quartz Station
Diorite 239+30
HR-2S s
Station
239+30
(1) S -A. J. Hendron for SWEC
C -u. S. Army Corps of Engineers
J -Atlas Copco Jarva, Inc.
R -The Robbins Co. ·
(2) From Dam Area
(3) 0 = Least, G = Most Abrasive
(4) Not Corrected for L/D 2
(1b/cu ft)
No Test
162.22
165.98
164.98
166.11
No Test
165.2
165.1
ROCK CORE PROPERTIES
FRESH & ALTERED QUARTZ DIORITE
TERROR LAKE TUNNEL
Unconfined Average(5) Distance
Compressive Total Penetration Penetrated
Strength (psi) Hardness Rate( ft/hr) (ft)
No Test 106.59 No Data
22,809.1<4 > No Test No Data
22,598.3(4 ) 106.4 7.1 35
22,008.8<4 > 119.31 7.1 35
23,178.4<4 > 121 7.1 35
No Test 74.82 14.2 57
26,055 123.05 8.4 42
22,682 133.27 8.4 42
(5) Average Shift Penetration Rate, Includes Machine Down Time
Splitting
Tensile Point
Chercher(3) Strength Load Shore Abrasion
(psi) (psi) Hardness Abrasivity Hardness
43.3 6.06
No Test No
85.26 6.51
88.69 6.64
83.04 7.25
84.8 6.17
94.6 7.94
91.7 7.52
'----------------..;...__----------TABLE 7.4-7
Rock Type
and/or Conditions Length (ft)
Fault Zones
Bull Moose 100
Bradley River 250
Fracture Zones
Lineaments 200
Random 200
Gouge/Breccia
Bull Moose 15
Bradley River 30
Random 15
Portal, D/S 50
TUNNELING CONDITIONS
FAULT & FRACTURE ZONES, PORTAL
Penetration Delay
Rate ( ft/hr) Hardness Time (days) Temporary Support
N/A N/A 5 2/3 Sets, WF 4xl3
N/A N/A 12 2/3 Sets, WF 4xl3
N/A N/A 10 2/3 Sets, WF 4xl3
N/A N/A 10 2/3 Sets, WF 4xl3
N/A N/A 2 Full circle sets,
N/A N/A 5 Full circle sets,
N/A N/A 2 Full circle sets,
WF 5xl9
WF 5xl9
WF 5xl9
Drill & Blast 130 N/A Full sets, WF 4xl3
Remarks
Probably primarily fractured,
cherty, foliated argillite.
He-steel -#8 @ 12 in. each
way.
Breccia w/Gouge Matrix
Gouge
Gouge
'-----------------~----------TABLE 7.4-8 ___,
LIST OF THIN SECTIONS
Section No. Coordinates Depth (ft) Classification
S-1 N2,103,760 E343,580 11.9 Massive Argillite
S-1 N2,103,760 E343,580 18.4 Foliated Cherty Argillite
S-3 N2~111,580 E328,110 82.3 Foliated Cherty Argillite
S-4 N2,103,760 E343,580 38.0 Mi~ed Graywacke/Argillite
S-5 N2,103,760 E343,580 54.0 Graywacke
S-6A N2,103,780 E342,760 17.3 Graywacke
S-6B N2,103,780 E342,760 19.0 Graywacke
M-1 N2,106,720 E366,200 Surface Foliated Cherty Argillite
M-2 N2,106,930 E366,200 Surface Tuff
M-3 N2,108,770 E331,450 Surface Graywacke
M-4 N2,109,420 E330,730 Surface Chert
M-5 N2,111,800 E327,910 Surface Dacite
M-6 N2,112,670 E328,110 Surface Graywacke
CH-11 N2,109,720 E330,400 18.2 Chert
CH-11A N2,109,720 E330,400 168.7-177.9 Foliated Argillite
CH-lli N2,109,720 E330,400 168.7-177.9 Foliated Argillite
H-1 N2,111,580 E328,110 255.5 Massive Argillite
H-2 N2,112,090 E327,430 61.0 Massive Argillite
H-3 N2,111,580 E328,110 243.0 Massive Argillite
D-16I N2,108,900 E331,350 Surface Graywacke
D-36B N2,101,461 E343,083 Surface Dacite
D-37 N2,106,870 E335,650 Surface Tuff
SR-1 Sta. 242+71
Terror Lake Tunnel Quartz Diorite
HR-7 Sta. 239+30
Terror Lake Tunnel Altered
Quartz Diorite
TABLE 7.4-9
7~~~--------------------------------------------~----------.
6
5
(I)
LL 4 CJ
0
0
0 ...
~
...I
LL
ESTIMATED INFLOW
(FLOOD OF RECORD 1979)
I \
II ', RECORDED FLOW
AT LAKE OUTLET
I \
I \\
I \
I I /--...._.,, ,.
I , '"-... .... i I ~----------,, ' 111 LAKE ELEVATION '~ ... ' ........._ ~ ~, ------~ ~ 1 '-"--.,, .. -...; ----
TIME-DAYS
1979 INFLOW-OUTFLOW HYDROGRAPHS
1-u.-·~ Z:::>
Ot--<( ~c
>t-WCJ
...Jw w...,
wO ~a:
<(e:.
...I
~-------------------:-FIGURE 7.3-1
81~-----------------------------------------------r---------,
(I)
LL u
8 o. 4 .....
~
...1
LL
11 ........ ....---_,
, ... '-.. ·. ,. ~ . I '' LAKE ELEVATION!
I -----~, I
'i ~
' ' ' ' I
INFLOW
(FLOOD OF RECORD 1979) I ,.
I
I ,
I
I
I
' ! ~~UTFLOW
I
I
/
/
TIME-DAYS
DIVERSION TUNNEL FLOOD ROUTING
' '
18
::!:
::::>
1-
<( c
1-u w ..,
0 a:
!!::.
1-
LL . z
0
1-
<(
> w
...1 w
1,088 w
~
<(
...1
1,086
'------~------------:--FIGURE 7.3-2---
1600
1400
1200
1000
~
::::>
~800
0
1--w
(3600
0::: a...
..__
~400
IJ...
I z
0
~ 200
::> w
_j w A
0-
q SURGE SHAFT
1-----
t---------~ rTOP OF SURGE TANK --f-------EL.1339'
"'-'' ,_1 [90MW PLANT
l
',, "~~ '~ 60MW PLANT t;=_-=.-_ ___ [ MAXIMUM
. I--~ ---~-----=.-=-
L135 MW PLANT --=--= I
STEEL CONC.
I &. CONC. LINED
LINED
I I
I
I
I
I
I
~D (INVERT EL 120')
c""\ IL
I
if8 ......,...
~ l'i' ~ 2? [) 't!.UNIT RUNNER
POWERHOUSE
& SYNCHRONOUS
BYPASS VALVE
HYDRAULIC GRADE LINES
--=--==-=--=-==--=--\ MAX.W.S. EL.1170'
l
F MIN.W.S.EL.1081 1
(INVERT
k_BRADLEY LAKE EL.1025') ~
LG (INVERT EL.104d)
INCLINED
SHAFT
........
'
L-E (INVERT EL. 3601
)
VERTICAL SCALE: 1''= 200' HYDRAULIC TRANSIENTS
HORIZONTAL SCALE: 1"=2000' FRANCIS UNITS ...__ _____ __::..:...=..=.. _ ____.;.. ___ ...:....:....::::..:::::~~=----------FIGURE 7 .4-1-__.
1600~----~--~-~--=-~~------------------------------------~--------------------------r-------/135 MW PLANT
r----------~----c::O MW PLANT
f--1400.....,____----r~=--=--~-~==-=-~-~-~~~~~~~~--~~~~-----------------------------;-_ __ -------------./!MAXIMUM ,~ ------HYDRAULIC
"-60MW PLAN;:---=----~~ADE 1200------t-------r-----~--------------------------~--=~~-=-~~~-~~~~~:~s~~-~-~,----~M~A~x~.w~.s~E=L.~11~7~o' __
STEEL CONC E
1
& CON C. L1 NED (INVERT MIN. W.S. EL.1081'
1000~----~-L_I~N~E~D_. j-------------------------------------~E~L~~~0~25~'~)-tr=~ll~B~RA~D~LE~Y~L~A~K~E~--~~
- F (INVERT EL.1040• )
:2:
::) ~800------r-----~t-------------------------------------------4-------------
o
1--w
(3600 ~ ------t------t----------------------------------------~-------------
INCLINED
SHAFT 0...
1-~AOO------~------t-------------------------------------------~----~--------
I..L .........
I z ~200------1~~-;:i------~====~~,_~~~======--~-----------------------------~ .~s c~ _
~__...,..__......__......__......__......tl D (INVERT E L. 360 I)
w
0· --j~~~~~~·~uN~I~T~R~U~N~N=ER~--------------------------------------------------
"-..r-A
---f---' POWERHOUSE
VERTICAL SCALE: 111= 200' HYDRAULIC TRANSIENTS
HORIZONTAL SCALE: 1··=2000' PELTON UNITS -------~..:.::...=.....--=-.:....:...:... _ __._ ___ __:_::::~~~~-------FIGURE 7.4-2 ____...
Project: BRI'IOLE"< LAI<.f: \-l'<o{'.or,•s.L~:N"-PRo-ltc<:.T
Location: \\.~-..\..\~>.1 Vr;.~INSuLI'I,A\\. ((::IPPHo~-NS1°'\~·, W1so·1s')
Coordinates: N'2.,10\:,,900 E3?:>1 1 350
Specimen No.: 0 -\Gl
Description of Sampling Point: Du•<:.Ro?
Thin Sect ion No. D-\Gl Date: "\ jl?../8:,
MACROSCOPIC DESCRIPTION OF SAMPLE
Degree of Weathering: \lEt~.'< SLIGH\ 10
SL\G\-\1
Structure : I'J\1\SSI\! r:_
Discontinuities : wiG{"-_ 10 \11--R'I w101: ..}C>IN\
S\"1'1<:..1 t-..}G
RESULTS OF ROCK PROPERTY TESTS
GENERAL REMARKS: t-.lON f-
GEOLOGIC DESCRIPTION
Rock Name: Gr'-r--': Will ~~-<E
Petrographic Classification:
s~R\<:.1\I"Z.I'.C, (ju~>.n:n.<:>o;:=t-;.LOS"~'HIC::. 1
\Jf~R'l'fiN~(},~"-1>-1'1'--1) 1 \::JI"l,.<HO\'\'ii..CY .. ->11:\(. 1
Q, ,,,, '( L.J 1'1<:.1<.. r,. ..
Geologic Formation: t..l\c. 1-\lJG'r\
Co\-'\PLr,.x"
QUALITATIVE DESCRIPTION
Texture: C..Lt-151 IC.. 1 GRI'IINS ~
\OOx
Sketch [81 Photomicrograph 0
\-\1'\\RI")( ~ODI\-\\':.D ~'( St:.RI<:..\\ r~ ( \ MINERAL COMPOSITION 'JI":>ui'I'-\:~,-Tit11'11"t. J
i;L \ '"-_ 1"\. I>, 1'10 ~ 1'1 <::__ \ U.J c_, f.>,::, t::.f_\-'\f.NI) 1------,---.,.-------.r---,------.--------1
Suc,l--\1 OE\J\-_LOP\"\1"'-WI a\-~~
OR\f..\JII-..0 ~-~~RIC. or-<:.~1P,C.Li>t::,.\IC
C>RIG.\1-)
Fracturing: NON~
Alteration: Sf.:R.IC.I\1--z..t~noN ci'
l'l'.l.DSP~fl..S l:l C.otlr\0~1 \J'F-\1--'t
1-'\INO(l. <:_'HLOR\' 1'-.f'\\10~
Matrix: \JR\\--\1'\R\L'I CL.l~'\· 'S11..t-.
\'1.1'1\ERI?-.L 0~ lOG S\-\1'\LL 1'1
Sn.r-_ ICJ 1'.'---LO'--'-) oi"\1<-PIL
\D\·.~\1\-\CI'-\\IO\-.).
Maior % Minor
qui'IRI "L '2..0 C-..LOti.I"TF..
PLA(,ICC.LP,tlt'. 30 C.L.~'I'-SIU.
':) (.{t,\C.I \ E 30 \<-fEL.D':>"I'I\1.
SIGNIFICANCE TO
ROCK ENGINEERING
Cr:np,<-L.~>~~''"-'FPI\"!>1<..1<.., s
%
'2.
5
\'j
IN:lu\' \'1<..1 RN 'T L'< a ..-~\J ~"·'-'--'1''' a
10 'SI<>I-JI'\'IC.C'>N"I:L'{ I N\'1..'-l<-."-'"-"-
~rc\-11';'1\0R uNOI".R L.OC>.tl.
s~t\.IC.\"'"I<.t>.·not-.) \-11:\S ~(l\''\l"-.W\-11'\'T
lul'.l\l<f-.IJt;_t) 't~E. {l..~c_~ I 1-J
C:.G\'\\'1>.0-.\SON IG 1'>,\-.l \Jl'-li;L.II".RI'.t>
\-'1;1'1-,l'.N\ Ro<:.k.
Acces. %
\'\uscoVI\1:: <. I
Grain Size/
Distribution
o. '2. -
O.OG2S
O .Q62.5-
Q.OO?>q
<0.00'3,9
%
lO
2.5
5
REPORT OF PETROGRAPHIC EXAMINATION
FIGURE 7.4-3 -
Project: B\1..1\D'-1'-'1 lf\1-<.E \-\'it~Rot:Lr~c:.11l-'C. \::>~>-o.lr~(..T
Location: K E Nl\1 Pr-.tJ IN S\JLI'I, 1\ ~ (!\~ 'O'Ra~. N 5'i0 4(0\l/ ISO' so'
Coordinates: ~ 2.\Cl-:)110 , E 3'\'2.1100
Specimen No.: S-\-1
Description of Sampling Point: 0\-\ '3 5 (u~I\C..E. ),
APPR())(.. Dr-.l""l\-\·11 .'2. ~t . (01-..K (\1'-.t"~A,LEr-1 '510"-l
Thin Section No. S·\·1 Date: '1.}\ /'Oo
MACROSCOPIC DESCRIPTION OF SAMPLE
Degree of Weathering: 1-ll,r~"&\-\ "to \Jt:.\'1..'-l S\...IG.H,.
Structure: 1\1\1'1.5'51\JE.
Discontinuities: OC.Ct'\S\ONI\\.1 IR.Rt:.GULI\1' ,CALU\~-
GEOLOGIC DESCRIPTION
Rock Name: MI\SS\'1/E. ~RGoii..\.11E
Petrographic Classification:
C:. HL oR 1117.\::t:) \ S11-, '1, QuAI\."" z.
f\~uiLL\"t E
Geologic Formation: "l\1\c.\·h.lGH
Co""~">'-f,_)(11
QUALITATIVE DESCRIPTION
S \"l.E 1-\~111..1 Y.
Pl. PIC:. l<lC..\.."' s 'e. --r-t:r-C~~±n
lOx.
Sketch [8] Photomicrograph 0 Texture: CLA~11C.-GP...P.IW/MfHP.IX/
c EME Ni. Vt:. ~'I SLIC.~'T c 1\ \C.I.I\S "TIC 1--------------------------t
MINERAL COMPOSITION (1.1,~\J<:\L t:':l11l-\l'IT~)
0 ll. \(;.N 'TI1 i I 0 1\l 0 ~ S \L 1 · ~ n. S:. ~ 1\ II.. 'T \C. L'f~S 1------,...-~r-----,.--_;,-'--.;;_:__;_.;_;_i-'-----1
Ma"or %
QUAI'-1' "l. 50
C.HI.ORI1 E I 5
CL"'(-Sn.£.* 1 5
Minor
\(· tE \..0 :5~t.R
PLII>GIOC:LI\SE.
%
10
'2.
Acces. %
Sp,u~;.nE (?) 5
C 1\L C.l'T E. 3
Ml\r.,\.n:nn<:~) <..I
f\LI.¥-0 fR~C.TU~"-5 UP lO I .O'N\'mi..U\OE) ~0\N\1~<:;-Fracturing: IR\l-..t;.C.\.1\..I'III..l"<..Jt>.\/1!.'1'')1
RESULTS OF ROCK PROPERTY TESTS
\JNI"T w~,<;Tt,.-nt \"<>/!iii~
'\_.u.. -'a 1. <0 <0 \" s i
HR-3e .G
HA-1..\G.
SHORE \-\f>.RONES~-53.~
1-\.T-oG.I
loNe:.nuo 1 NC»L LVP..vr:. VE.I..OC:I\ '{ '!) '2.000 f s't
A)CI~~>L \..oAo-\l,l"r~ \"'rfs~c...
GENERAL REMARKS:
C.r-.\..(..\"T~-e.l\..1.}(..\'f'l': V\1...1...'1:;0 j UP 'TO
\""om U. • .I\OE. \-{(;,f.\L.r.O.
Alteration: MOOEI'AIE AL"'fi'RA\\<:IN
O'f MIC..t:\ ':i f\\-..10 C.l...ll'i 1\J\IN\-.Il..f.lLS iO
C 1-\l.O Q.l i£.
Matrix: vtt.R'l I"INt:. SII.."T !'\No ~\..1'\'l·S\'Lii
P!\(\.:TIC.I..\!.'5 I.UI"'I' H C.l,\l.OR11'E. l·'\\WO'I\
f.H'\OUI-l'iS 0~ C.l>1\l!.CHJf'l<.n_ou~ \'\lqt";R\~1.
~\-..!CjC!l.. \,Qf>.l'rlllf'_ 1'\ll.'l'i. \"1\.<>CA~I..,'(
l\-l<:..l.uOt<.D.
SIGNIFICANCE TO
ROCK ENGINEERING
SI..IG Hl' A I-ll ~O'ill.I:>PIC: ~\'.WI>.\1\0t>..
\JN0\'.(1. L.CI'tO \5 ~t>-OC.I\11>\..f.
SHOUI...O "'"'-0 C:,I;.Nf';t>.f\-\.'-'( ~Q\JI"
1:\11-\t'.~:S\ONP\\. (>M'\'1:\C.I..t'~S 101-11'.~
~\..1'\Si~O OR C.t>.u.S~"-0
REPORT OF PETROGRAPHIC EXAMINATION
FIGURE
Grain Size/
Distribution
mm
"> 0 .1
0 .1·0.05
.os·o.oo
<o .oos
%
5
5
1S
15
7.4-4
Project: BRP>o t..t",.'{ \...r>."'r~ \4.'1ot-..c;\';.c_~t..'r>--'"-1?(\<:>.)t",_._,.
Loca tion: \\r~\J I\1 f\~..:>1 N~\.>'-" ,1\t< (~?~t>.,o)l.. N 5'1°4.G. ·,W I so" so')
Coordinates: N'2,10'1 1l'LO E. 3 '60 140C>(APPf>.-O")(.)
Specimen ·No. : C.\-\-ll A
Description of Sampling Point: C.o~t: \=ROM
BOR\\.JG D\-\-\\) \<Oe..l-\\1.'1 t1.D~f>\H
\Nli:.I"\\IP.L
Thin Section No.(_\-\-\IA Date:O.j\4{63
MACROSCOPIC DESCRIPTION OF SAMPLE
Degree of Weathering: tRI:.~~
St r ucture : OI'S\IIJ<:..TL\' \-O'-'t<'~'-0 <9 AO•'"'
()\= '00" ~
Discontinuities: i Z AIJDOM.L '<-atur:NTLO, t::..l'l'-'-""-
t=\LLr._o I'Rt>,<:..-ru P..t",<; UP 10 \""'""' ''"''"-"'-.
RESULTS OF ROCK PROPE RTY TESTS
\..)t-.>I T W~I C,I-\T -\ ~~ lb fc;t3
"ju..-~c;G) I f>S·,
1-fR-55 .\
\-\1'\-'2..6'2.
SI-IORI"_ \-1 c>.~I..ON I;.'S'S -'ijG . '3
H 1 · "''Z.. 53
Lot->C,I1'\JOIIJAl..l..j(',vl'_ \Jr-..t..OC:..I't'i (<;) 'l.OOO"s·· r~\)I.IAl.. Lol\tl ' lB,'H!> '\\fs
GENERAL REMARKS: Roc..\<. \'S NoTic.r,r>,t>l...'i :St.lscr-.Pll~'-r~
\o t.U I"c~lh i,\1_\~C. t..JI-\1"-_!<.t-. Sf-:..1"-.t--.> 1\\ T""-0•~1\.'l'fH. E .
GEOLOGIC DESCRIPTION
Petrographic Classification:
S T;.ll, I<:_ I, l "l. I'. 0 1 S l L, '( ~~ Q... (,.I I_ L I\ t"~
Pn.e:.\<> ~--''<'-"'...,1'"-
Geologic Formation: •· Me 1-\ u '-> 11
C. OMI''-f'-)<..
11
QUALITATIVE DESCRIPTION
\OQ'l<.
Sketch [81 Photomicrograph 0
Texture: C.. L P. '::>\\C.-PRO \O~'il.cNn: IC.I---------------------------1
Ct>~il'\c.'-Asl•c.. ri\BRi c. SIR<HIGI....Y
01:.\/1:.1...0 P 1:: D.
Fracturing: NuME-o..ou s t'II<:..P.o ~<:..o1'1c:..
I'RPIC:..\I..ll"\.l'..S < 0.0\wt'M WID!:: 01"\.\l:t-.!i"-D
GF..t-J"-RI>.L.L.'I I IJ <kF-o•r.~"o.t::..Tiolo) or. IH£
C. 1'1 I (>, <:.. '-1>. S i I C. F PI~ Rl C A tv 0 S I' &>,<:..E. 0 0, l·
(). 5 'IVt'M. Oc..c...I'\S\01-ll'\\.. SW/'111..1"\S ())'
"C!>Rr-. I 01'.()" ~RI\<:. \U Rl=: 'S SPA<:.f~'O 0 .Ool1...,...,
f'R\\"\1'\Q..'I C.<JI-\I'.SION U~Uf.\LL.'I 1-\P.I~)TP.INI'-tl.
Alteration: e.o1J-:;1 or-.n..f:IG'-"'-
3 1'.RIC \1 IJ..f1 "1.10"-'> ov \-\-.\..0-0 ~A T!..:\ j .:SLIC.~\T
\0 \.lf-_{'l...'( ::5 \.....\.C, ~ll C:H\.D [\\ "'T \1....~ TI O t--l j
\'o s~ 101.. -y ::; o\'\ r~ 1<. "<>'-ltv 11'1'2.1\ ,,o >-)
Matrix: VR 1 h f:\11..1 '--'1 c:.t..f.\ ·r . ~ '..,_~"~
f'!\R"tlL\...'1:.~ TOU SMC'IL.L \0 C>l:.
101;.\-.l"l.\"1\-,C . 'So\-\1:. (;RI'IP\-1\\ 'E "'\.JO /OR
0\~I:R C.P.R~a"-'P.<:.f':.ClU':II-'IF\i'f;.l\11'\1..
\o;:, \'I<.Ot",r..,>OL"t \,>C>..,V:_s r-.1-JT
MINERAL COMPOSITION (\J1sur-.'-£.51\t-'1 ~"'-)
Maior % Minor % Ac ce s. %
PL.AGIOC.LA'Sl: 35 (HLORITI:. '2. PYt<.li \:. <l
~F..RIC.1 1 I; 2.0 Qu~R., • I S ...
CLAY· Sn.~:. 2.() C.(>.\.. C I \l!: ~
\<: f F.LD SPAll? 5
SIGNIFICANCE TO
ROCK ENGINEERING
Grain Size/
Distribution
<;) 1-\CULP \-_)(,1-\l()\\ S"t\ .. 0\JCI...'Y Q.\-
f.\1-JI:IC>"t;Rcf'IC. D~:I'ORt-11\\10~ O.OG'2.5
Gr~1-1 ll.'J\OR \.J "'o ~".R. t...c. 1>. o . Sp.t-.N<>1H o. Ot<. 25-
?t~n..~>.'-'-~":'-,.o r-"''-'""-rlolo) s~<ou'-o o .oo<t
\:It'~ ~IC.I-.>I'fl<:..r..>-.l'TL'< Lt'·-S'S \H!>N (Q,QO'\
H 'I lkllt-r \.JOI'l..t-\1'\L i o \1-\'i'. GRI\1 \.J .
8_\":_l>\:I~IHJ<..I'_ '" t.ur,_,.,'t-\.-~ii,.ING
~1'\'1 GK N0'\10.1\~\..'< \..'r,::ll'1Hf\~
~11-\1'-11-1'\0t::..l-<-\ ''""~"-"" "'' ,,..,., -:;n r:.
%
\0
10
1.0
REPORT OF PETROGRAPHIC EXAMINATION
FIGURE 7.4-5-
Project: '2>Rr.O'-t:.'l L~<~<ll \-\yon.oa'-11.<:-.t~.'c f-l(l,oJ~•"-"'~
Location: \<.'f.\..1"'' ?r~N'"'~u'-"'· ~\\ (Pii>?l\o'1..N5'\0 '\IO,V.JIS0°50')
Coordinates: N C..,ll\ ,100 £ ~ 2.&, S2.Cl (Ai>Pil.o){.)
Specimen No.: S -3
Description of Sampling Point: BaRil') C. D" -\3
~ (W\"ri..O X. ~ 'L . ~-\-~t. 0'1'.1'"'11-\
Thin Section No. S-3
MACROSCOPIC DESCRIPTION OF SAMPLE
Degree of Weathering: \-R~S\-\
Structure: WELL ·l)l:V"-L OPE. o FLU)( 10 N Sli\UC:TURE
01~?\1-)t,@ G0°:!: i POf\f\\'(R,QC.U'-!.TS CJ"' <:..1-\i-RT Uf' 10
\C).,...,...)( Sc_.,., IN I',N Flri..GILI...It't 1-\('!l"f!l,l)(.
Discontinuities: .)o\N'l>t-..>.c, '~~'~R't c..Lo :.r-_ P.l...ol')c,
Fl.u~IG"-1/1-c<..lr.>.\loN \JAt-1011\lC. i t...liOic -ro'll;.R'\' "--I Of~
@ CJ\H~ct:l. ()~lrcNTI">''"'"-~ ~ j OC..C..PI~IC.NFIL <:_1).\..<:..i,\'..~II...Lil'IC."S
RESULTS OF ROCK PROPERTY TESTS
UN11Wr-.IC>\\"T-\~S \'o[~\3
'\.u.-'\,'2..04ps;
HP. · 30.1
1-!A-<\.B
~1-<0I'.E 1-\Rb.cr-.r-.JS • <0'\.<0
1-h-<Dl.ZS
LONC>P \) OINO.L w P.\Jf. \)r,LOC.l 'n ® 2.000"'s; A-..of.\l..lor..o. I <O,ISq nt~·c
GENERAL REMARKS: Fl<.(1TUi<.F.':) INOIC.I)"l"l'll'_ Q~
:it'.'lt'~X\~1... i-.1'1:5C01~~ Cl \-\)l".t-"<:lfl..I:-H'I\\()1(\,
GEOLOGIC DESCRIPTION
Rock Name: C.Hr:tl.:n, \-c'-ll>l\r-..o
f.:\1,(,11...1...\"( f-:.
Petrographic Classification:
GR ~PH I 1 I(. I CHE R I'Y ,i=>II.011)\'\'{L 0\l\\IC
ARGILI...Il r:..
Geologic Formation: ·· M.c.. \-\ u C.\-1
Coi-IE''-t'.. )("
QUALITATIVE DESCRIPTION
C:l.l\'1. :n ~r~
~I~'R 't \C..I..t'. S (>,IJ ~
Q.tl..l'-l'\H'(t=_
10')(
Sketch [8J Photomicrograph 0
Texture : c L f.\~,. 1 <:.. -~ \\(),. o ~'< Loun, ~ ~ 1----------------------------i
IN\~:.n.Nt>,L. \'r-.)(.\Ufl..r. o~ ~'o\\-.tl..t
Po cq:> .... '( ft-0 <:._I... PI::.,. ~ I :) ~LL.Q 1 Rl 0 'i!.L!'I':i1)C:~ __ M_I_N_E_RA...-L_C_O~MP __ o_s_I_T_I_O_N....-(_v_. S~t.>_A_L_£_s_1_•_..__"'_,..,...t.-')'------l
Gl\rH.H.)LI'\R t'\> , .... ,_ \-\tC.f\o-10 <:..P.'i~1o·
C.!l,'<S"l"PII...'-1 t-1 E Sl ~r-. Lt'_\Jti\...
\'<,I',C:.t'-'l':STC.I...'-.1 "t.'l"~t> \-l'l'l'lt:nOI-\Ol\.\'1-<IC •
Gt!.ll\1-.)VI.IHL ') UIH>..I"L I :s \'fl..t'.::I'I":.IU'T.
Fracturing: l-l\<:.1'-<::>·f'l\.r::.c:.-ruR~'S AR~
Q(H'\ >\C N 1 U ::IU I>.L\. '/ [:>,LON Co "( \-1 ~
'r-1\~RI<:. c\" \\-\'!'-~RC.\I....L.I-...r~ ~-'"''"'1< i
L\-.S-:l <:.<lYI\-\01-.) 1"-RI;. RI>.~Q0\-\1...'1 •
Ot:l.ltckl\t=..\J \"t'-1\C:..\URt'-'.i lt.J\\HIIJ
C:..\-\ li.fl... T \:'CoR \'1-\ '( RO<:..Lt\:) 'l ~. \'\o:s T
\-\1..1\CO.:HJ ()..('~ l SHU"-! SC.'t\_t-,. CI'_C,\"\,.T',_n.
Cl \-'rlt=..!\L.I \..l C, .
Alteration: NoN'=. \1\S\SL'€. l• 1'5
f>R<>OI\I~L.t< 1H!\\ sc'I-\'E. c..c.\..lt.TITv.-_•ns
01= "TI-tF. ~A1Rl)( 1-\P\'lt'.I:\.IF\I...'S 1-lr.>.\l'r~
(3r,.l=.t-..J {\L'lER'I'-0 i3l.lT \'-<I:S \'S 1-\l'oS\<.1"-:.C
G'\ 1\-1~ \41<:;1-1 ~r,_n.c..r~~.ni\<;;E o'l= <;;tU'I~I-IITt.
lkl Trll~ Mf'\1 ft.'¥ (:st:.r:. ~r-:.t.cw \. \-\•Ncn
Sr:.R\<:.11'\,. 1'\'l'\r.,_lL 1"~-'-t>'Sl'l'{l..(~).
Matrix: C:'-r-n :5\~r~ ?AR>IC.'-':.~ lac.
SI-\.1'\\..L 'lroR"-li.'SI.J~L \01\"-.l"(I\-\C.f\110\..l .
t.,. 1 :s '~'":. s 1:n·\t\ "t ·t'. c \ H \>I • f.\iL. '1-:.r>.::, -r
60°/o 01' "11·\\S \--.'1'\"Tt·-:.n.IP.\.. \S
G. R!\ \' H 1\ ~ { <: 1\RP.>o>-J\'1 ,r~ou ';; \-\I'll. 1'-:. R\1~ L.
Ma'or
c~l'.ti.."T
Cu•.y·S n. E
% Minor
SS quM~'l"L
35
% Acces.
C ALC.\1 E.
SURIC\ "1E.
%
\
2.
SIGNIFICANCE TO
ROCK ENGINEERING
Grain Size/
Distribution
Pnoei.,~~._t", S'\'!>,c 1-l<:,
1'\NI!i<l"tf\oi'IC. C~.H('\\1\0I'l
I.H-lD\':."LI..C~t). C:.\-\I"..R"l
\J 11-.1 ~uf.V\<:.\T-.1--)l:l....'l
:5 \'Ill. LL \'OR~'I'\';1\.0C:.'-!'~'t,
f.\~ \c 'r\t>.~li. 1...\1,'-1'. on.
C:~~;.v_, Pc~-500'l<\~
I'IWRCc::.LA'5l.S 5())( 5
5-2..
2. -\
<.I
Stq· Cu\'i < o.o102S
NC t'.F!':!; t..T 0>-1 \-\1\TR.I )(
t:.Y,C..J:>,\lf.\110N Trcc::~wqv~;..
I.J '-"1 H'\fl, ~ n ,., ~dv (, 1 ... 0 11-1 £ R
~\\ou'-o ~l'i. cr,_,"-''-"''-'~n
I) \I 1'1.1>.\RI '1-1-\l'l\~-..11.1 P.'-
\"~'f"\-.R\1\-..'i.
<o.2
%
'30
15 ...,
3
35
\0
REPORT OF PETROGRAPHIC EXAMINATION
FIGURE 7.4-6
Project: Bru:.,t)L1"~'( LA I('\:. \hol"-.or~Lt:..c...,~tc. p,,a.)l'.(."T
Location: \<.EN !I. I Pr. ~,(', ~UU'I. p., \( (Atf'tt_QY,. N5'1 6 ~~·.wlsa· so'
Coordinates: N IOG810 , E ~:)S~SO (Mf'\"l,ox..)
Specimen No.: 0 · 3 I
Description of Sampling Point: OuT C.'{'..()P ,
lUI-.lOI"\P, C:.CN 0\\10 t0 S
Thin Section No. D· 31 Date: 8}31/83
MACROSCOPIC DESCRIPTION OF SAMPLE
Degree of Weathering: SL\G\-H 10 NON.(;.
Structure: Mt>.SSI\/E.
Discontinuities: l.IJIOt:.L'f' '5f>AC.F..D JOit-.)Tt'-!G
RESULTS OF ROCK PROPERTY TESTS
NONE MI'\OE
GENERAL REUARKS:
GEOLOGIC DESCRIPTION
Rock Name: TufF
Petrographic Classification:
C\.ILOR\\I"Z..\' .. 0 R\4'{01...\\\C:. C.R~~"TI'>.L
Tut=F
Geologic Formation: ''N\c \-\uc.\-4
CoMPLE"X. ••
QUALITATIVE DESCRIPTION
Texture: P'(ROC..L A '5 \1 c.; ff\o~~~'-'I
D f-I"G ~ \ l: t;: 0 I N 1.>.:1 ~:>, l: "'-(1.
Fracturing: COt-·HtON L'( ASOU'T
0.04m'm W\t>E:, '5P/H .. EO \, '2.mYJoo
C..~L0\\1., E l=\\.\ .. f.b; C.O"'-t'\Ot-lL'(
Su~-P!>oR.~LLr'-L
Alteration: ~L\GI-\1 \<AoLIN-
\'T\7..1~1\0N OF FSLU~P11R)
E'1.1n.N51\I\:. <::.."'-OR\\1 1...1=\\\0~
()l= \--\1C.IliS ~ C..Lf\'1-~\'Z .. f. ~P."-lt<:.L.t':.'S
Matrix: G~'-.1\:.R.~LL.'( \00 H\..lE-
GRII>\\t-.)~0 \a BE \llS\GLEj
W\-\~R ~ \) \ Sl ~ L. ~ -C..\.\LOP-.\"t;E)
f"'-.Lt>'SP!=\R 1 1\NO qu~\\.\"Z..
lOx
Sketch [81 Photomicrograph 0
M:(NERAL COMPOSITION-~'i V\'!IUI>oL E.'STII-11\"1'\!
Ma or %
fEI...I)'S f> 1'1~ 40
l '5~NAl>l W~ ~)
QUAI\H. '2..0
Minor
1-\o~~i!"E'.~l>'E
Bto'TI'T'l.
c \-11..01'>1,. t',
SIGNIFICANCE TO
ROCK ENGINEERING
%
'2.
4
30
Tl-ln IJV~l'.l\.0\l~ C:.'rl\.01'\.1,"'--
no~OI':.D "'-\C:.(I..O \<1'\.f\C:."tVt>..tVS
I'Rol!oAI!ol...'l S't' .. t>..V'F-.. \0 LOLU~l'l. \.\-\'1;
Acces. %
MAIOI.ti!.Tlll':.? 4-
CI\LC.I"t 1\; £..1
Grain Size/
'Distribution
%
2.5
0\1'1':.1\.11>\..L !oT'('..,..,lo.luT\-1 ft\.U9t,r>.1lf\.~. C) .5 ..... "1
li-lt'-:_ '1'1''-.'I'~St\t.)C:.'ft. oF to. '1'1'\.'r-.. 'fl\t\li.F.IJ -\o
QRI\",\.l"ti'I"TIO~ P,\'\ONC. "'\Ht'~
FRI'IC:.'TUI'\.'1'\.S WILL ~{\..()O~"e\..'1
0 .I..,...,
~t'~ 1\\:.Fl..t',<:."':\"-_0 Il-l ~NI::i<J"t'I\Ut'I<:.~(Q.\.,..'M
1:!>'1':.\-lll.\JICI'\.. ll).J~t'~R LoAO.
\5
'2..5
REPORT OF PETROGRAPHIC EXAMINATION
..___---------------FIGURE 7.4-7
Proj ec t: lr:.R.C\o~>, Ll\\<.1:. \--\'loll.o"-Lt=..C.\\1-.IC Prt..o~IOC.T
Location: Koc'''l-< LSLI\"->o, P. \-<
Coordinates: S-rr'.. 230.+ 30
Specimen No . : 1-1 R-\
Description of Sampling Point: TuNN~L
Thin Section No. \-\R-\ Date:o.,;c;,;s:,
MACRO SC OPIC DESCRIPTION OF SAMPLE
Degree of Weathering: I-I<..E.S\-1
Stru c tur e : MI"-SSI\/'1'.
Discontinuities: (E~f\MINt:.ll.. l-IAS No• St=.t-:..N
(\ 0 c. I< I 1\:1 0 u I c. \1... 0 ? )
RESULTS OF ROCK PROPERTY TESTS
UNI"tW\'i\C,\-\1-\((,f0,\105,\IOG .\ l'o/'if3
<)_u.-'2.?. I 5 'i '0 . ~ ; 2 '2.. '0 0 '0 . e. i '2. "?. • \1 ~A psI
1-\R-41 .1,4<;,.3,".-5 .3
1-\ 1'1 -C0 . 5 I 1 <0 .G.4-1 \ • 'l. 5
'SHot>-'t.\-\1\1'-,Cl->~.:;3-85.£._~ I e,~.lO"\ 1 '0~.0<2,.
\-1-t-\O<:.."r l \1"\.3\ I \1..\.~,
LoN<; IT uOIN"'-W t>o'Vr-:.. \J"'u:><.l"t'f@ 1.ClDO 1H>i f\-x,,.L lo(.l,o-
' 4 I '0 '0 '-i I 4 'I"\ '0 i I 5 ' I 4 '5 flt Is ~c:.
GENERAL REMARKS: STI'\\N\:.0 \-OR \-(-\"r:.Lt:>~\"rq,;
C P.LLEQ "\-\t~Rn Roc.\<..",
GEOLOGIC DESCRIPTION
Petrographic Classification:
fiNf,-GRPI\~t;.O, SLIC.Hl\..'(
'::,t.C.r<:1<.1-r 1-z..t:.o,Qu~R,..,_ 0\l::>t>,\\ t:
Geologic Formation: NOT
I<NClWN (p,JURI\'i>'SI<: Lt,nl\.\.)11 \'lt:)
QUALITATIVE DESCRIPTION
Texture: 1-\'(PIO\ot-\oR'<'I-\IC-
G.RI>.NUL.I"'R i MUC.I-{ .;:,r-\1-\'r,.
p LI\G. \0 C.\..P, ~ ~ 1-:. 'H\ I C) I> :S C:. ROW,-H
7:.01:-JINC,.
Fracturing: NoN~ VIS I~'--"-1~ \WN.
S\:.C.II()N (qur'\1'-....I'L \-:..~1-\1~\\S
\o.Jf.\\.11'.'1 \Cl<.TINC.TlDI-.J \"'t>IC.t\T\VE.
()\' PI\'SI OR ~f'..\".51'.~\ S'tp,11jl~)
Alteration: SLIGHT •o "-\coERI'II't
SfiR\C.IT\'l.ATION Of 'PLI\(,\C>C:.'-~S~
Matrix: NONIO:
2.0x
Sketch~ Photomicrograph 0
MINERAL COMPOSITION (VIS\}r->.Lt:O;·p\-'\~>~H.)
Maior % Minor
P\.I~C.\OC.LI\~f. 45 K-f U.L.t> S\'1<11.
l-&oo•c.l ~ \J A I' 'I"'L 2.5
SIGNIFICANCE TO
ROCK ENGINEERING
%
5
SouNo 0-.0<:.I((. M<"\'1 1:,\;. l.lN\)V:R
'5\R\:. S'S P.NC fcl'(>.. CONTI11c--.l
'-CIC..'r<.~Q -IN ~~L.\<:.\ S\Rv-3S .
MC1'1 ~"-<:.aN ;5.10'-\1.\:.~
SLJ'C.J\:.<:.1 \C) :J?f'IL.'-.\NC:> If
511'-\".'&Sl:C \CI j;, SIJ~\'\C.tt'ctllll'
\-11(',\-\ 1...\-_'V\-:.L.
Acces. %
1-\oll.'->'C>'-f,lol>t:. <I
\:>lo.-,-.-~;. \0
S"RIC.\\'f:. \5
Grain Size/
Distribution
z..o-1.0
1.0 ·0-5
<o.s
%
'l.5
GO
IS
REPORT OF PETROGRAPHIC EXAMINATION
FIGURE 7.4-8 -
Project: '"''~'oR \....IAKI:: \-hon..oi= ... Lt:.C\1'..1<: ?r:to.:~t::c.T
Location: \-\oo1P.Y< l SL~A~o, 1-\ K
Coordinates: S-u~. '2.42.+11
Specimen No.: SR-\
Description of Sampling Point: luNNEL
Thin Section No. SR-I Date: C\fl/ e>~
MACROSCOPIC DESCRIPTION OF SAMPLE
Degree of Weathering: S\...\~'r\\ •o t"'.:oo~1l.C\\t.;
0<::.C:R510Nl">\.. IRON 0~\0'C. S\1'1\NI"NC. OI:S"3E\'\U.ll\"IX:"O
T\-\1\.UU(,"()I.)\" j PO'::>S \IZ>Lc 1-<.i>,QLIN\\li ... A'li<.J~ 0\'-r{" ... LO:S.'I'I'\RI;>:\
Structure: \v\ r-.cos 1'-1 ~
Discontinuities: Jo,N,-ING l'-lr<W'I <::.L()~t--liN c:.o\'-..f:.
'SI~hPL.t:._ Ev.r.>.t\1"1-l~R ~r-.5 NQ\ S"fX.~ "9-,()<:._\< ~~ (;\.)1"-t;\0"-
RESULTS OF ROCK PROPERTY TESTS
UN\\l.Jt::l<:.•.--1\-IG.'2..2. lb/tt:3
'tu." '2. '2.,'e()"\ .\pSI
Hp,-4~.3
\-l. ~-<0.0(0
S\-\on..~: \-\r.:o.n..'O~t--~':0-12. .0+
\-\1 -\010 . 5 "\
LoNe,, "T u mN ~'~'-\Nf.I\JE. \JEI...O<..\i 'I' @ '2.000 p:s \ Cl ~~~I... \....ol'\o-
14,000 n{se<::.
GENERAL REMARKS:CRLLIC.o''Sor-,Roc:.K''. S11\1l\JH>
\"OR \<.·f'~L.'OSPPIR
GEOLOGIC DESCRIPTION
Petrographic Classification:
rl\-.1~ C.Ri?I\N\= ... 0 I sr~R\<;..\\ n.t~o
Qu~>~~ , ... D1ctt..•l:t.
Geologic Formation: NoT KNOuJN
(A 0u•'.r.>.":;~u::. l"->\1'-US\\J"f.)
QUALITATIVE DESCRIPTION
\<.-ftoLD 5PA~ _jlMS~:::..<·-"'
(_ «:,,-l'>•t-:~t'..O l
K· "'" \.O'if'P.~ (~\1\11-H.O)
B1<n lli.
Sketch [81 Photomicrograph D
Texture: ~ '< ~ 1 0 ,o '"'-oRt'\-11 <::. • GQ.A'-lu'-An. i l-----__:---------------------1
~Lt<C>I()C.I...~S'I: C.CH-\HOt-lLY \::.)<.1-l\~1\'5
u\l.~\.01\-\ 'LON\ N G
Fracturing: N()Nt; "'~'t!>'-t''-IN''"~
"St':.C.\\0-..I. ( Q'->1\\-..,"T'"L 'f .. 'y..~\\'!1\"T'S CUI"o'-.11"~'(
\::."t.\lo.l<..\IOt-.1 \NO\C.\-,'"tl'-'t''-0\-~\'>":;\
OR Pt>.t"~~i-..Ni S\{'o,r>.>N .)
MINERAL COMPOSITION
Ma or % Minor
PLP.~IOC.LP.':.\:. ~~ K-H.LO ~PI\
(Sool<::.)
QuM•,:n. '2.5
SIGNIFICANCE TO
(Vt':>\.JI'ILI:.<:.<It'll'l,.r-..)
%
'5
Acces. %
Bt~111E. \0
SE.l'..IC.I l E. 2.5
li\-\.Ot-.1\'l \:. .(.\
~Jl\QL\N ("?) -<:.I
Grain Size/
Distribution
Alteration: M<:~o~\'l.f.l>'i:.L.~ ~'h\'t'.l\:ls 1 -u~ ROCK ENGINEERING mm ~--------------------------~~~~~------~
%
SI' ... QIC\\ \L..I>.\101--) C>F PL.f\(;1()"-.LI>t~t:.
P.C.C.Qt-\,~Ptt-.11{;.\) '1?.'< \S'ER'< l-\INOR
~ ~(JL\ N \\\'2...1'<\\C>N .
Matrix: ~oNt:.
Si::I'-.\C.\\\'l...flo\\ON HI~~ "'-.)'I=_P,~t;O 2..0 -\.0
\1·\\S S'PttC.It-tt>.N 1"-' C.<>t-'PI\RISON \.D-0.5
\Q I'Rt' ... l\-1, U"-l(\L\'I=.P.,\'-.0 f>I\Rt'.\oJT <Q .5
\-1.1'1.\t'~t\lr>.L. l~r>r...-.1''-t=.\-\R-\ ). So .. "
'ii1\\.,~SS Rlii..L\t'.'i' \-I.~S ?P.o~P.\~'-Y
OC.C.URR\".0 l-'l::l 1'1 R\c.S\JL\ ~l=
lui<I~\1·\V .. \'\.lf\JG f-\'t--10 C>.L\t"-..Rr\l•D~.
'2.5
55
'2..0
REPORT OF PETROGRAPHIC EXAMINATION
FIGURE 7.4-9
--------~-------------+-----------+------~~~·
\POWERHOL'SE-,
\.
UNITS
LCHAIN-LINK
FENCE
TAILRACE
FLOW
PLOT PLAN-SF6 POWERHOUSE SUBSTATION
0 ,.. ...
PI I
ICAU IN FEET
16' WIDE
GATE
(TYP).
TAKE-OFF
TOWER
NOTE:
ELEVATIONS SHOWN ARE ON
PROJECT DATUM.
MEAN SEA LEVEL DATUM= PROJECT
DATUM PLUS 4.02 FT.
ALTERNATIVE
SF6 SUBSTATION
FIGURE 7.6-1
2.212 r--------Jr----2~~~~;;~-----=::::::::::;;;iiiii1 '---DAM CREST
2,210
-2,208
:E
::l
~ 0 2,206
1-
0 w ..,
0 a:
0.. -I-
LL
2
0
~ > w
...1 w
...1
0
0
0..
2,194
DIVERSION PIPE
COMBINED CAPACITY OF SPILLWAY
AND MAIN DIVERSION PIPE
800 1,000 1,200 1,400 1,600 1,800 2,000 2,200 2,400 2,600
FLOW-CFS
HYDRAULIC RATING CURVES
MIDDLE FORK DIVERSION
------------------FIGURE 7.9-1
8
ENVIRONMENTAL
ANALYSIS
8. ENVIRONMENTAL ANALYSIS
8.1 GENERAL
In considering the development of a major project, regardless of type, in a
remote environment, it is impossible to present a plan that will not have
some degree of impact. The impact severity depends on project type,
magnitude, and location. It is therefore necessary to study and evaluate
the long term benefits, as well as the impacts the project will have on the
environment, the region, and its people.
The Bradley Lake hydroelectric project will provide benefits and serve the
developing area of southcentral Alaska and more specifically the Kenai
Peninsula. The project location, on the eastern slopes of Kachemak Bay,
places the project in an area of remarkable peaks, glaciers, wildlife, and
subalpine terrain which have a high aesthetic quality. The project area
has a high wilderness quality with a high diversity of wildlife species,
and is reasonably free from physical encroachment.
In studying the project, the COE conducted environmental studies and has
identified the affects of project development on biological and
sociojcultural resources. Involvement of concerned agencies and the people
of the region allowed for communication, consultation, and exchanges of
information on issues affecting the people, the environment and the project
itself. These studies and communication programs have been the means and
basis by which the COE prepared and issued a Final Environmental Impact
Statement (FEIS) on August~ 1982, responsive to the development of the
COE's preferred Bradley Lake Hydroelectric project.
A review of the FEIS showed the following major areas of controversy and
unresolved issues:
o The volume and scheduling of mitigative flow releases from project
storage necessary to protect aquatic habitat in the lower Bradley River.
8-1
o The resolution of access to the project area.
o The development of plans for mining gravels and for the rehabilitation
of the Martin River borrow site.
o The development of a plan to establish waterfowl nesting and feeding
habitat in the area of the dredge spoil site.
o Assessment of moose utilization of the area above Bradley Lake.
The preferred Bradley Lake development, as proposed by this report, is
essentially similar to the preferred concept presented and addressed by the
COE. However, under the present plan, concepts have been introduced that
will result in lower impacts to the environment and studies have been
initiated that will provide the information, as needed, for the resolution
of the above issues.
8.2 MITIGATIVE STUDIES AND EVALUATIONS
8. 2. 1 Instream Flow Studies
Under the present scope, the Alaska Power Authority authorized the
performance of an instream flow study with the purpose of assessing the
Bradley River aquatic system to determine a flow regime which will support
salmon spawning and rearing habitat. This study was performed in
consideration of mitigative measures of project impact to the Bradley River
fishery habitats. In addition, the economic feasibility of the Bradley
Lake project could be realistically evaluated, reflecting proposed flow
releases. This study was performed by the firm of Woodward-Clyde
Consultants (WCC). Details of the study and the findings are presented in
Appendix E of this report.
8-2
The method used for the instream flow study was the incremental methodology
developed by the U.S. Fish and Wildlife Service (USFWS) Instream Flow
Group. In designing an appropriate study approach, it was necessary to
address several issues before estimates of acceptable flow regimes could be
prepared. Key among these issues was the need to know whether: (1) any
mainstream spawning occurred in the river; (2) salt water intrusion under
reduced flows would progress further upstream and potentially effect
spawning and rearing habitat; and (3) stream channel characteristics would
allow favorable fish spawning habitat under reduced flow. The study
program and methodology was presented to an interagency group attended by
state and federal resource agencies, the Alaska Power Authority, SWEe and
wee. The study addressed fishery resources of the Bradley River, slough
and tributary habitat, mainstream habitat, and both the spawning and
rearing attributes of the river system.
In determining the instream flow required to maintain salmon production in
the lower Bradley River, the information gathered from incremental analysis
of habitat was combined with: seasonal distribution and habitat utilization
data for targeted species; streamflow estimates for natural and
post-project conditions; and potential changes in salinity and water
temperature regimes to determine a proposed flow regime, shown on Table
8. 2-1. The salmon species considered in the study were pink, chum and
coho. Habitat requirements vary with season of the year, fish species, and
life history stage. The Bradley River presently provides limited habitat
for these species, and many of these habitats will be lost under
post-project operation. However, there is a high potential for utilization
of replacement habitat that would become available if appropriate
streamf~ows are provided, with indications of improving production in
spawning areas of the Bradley River.
----------------
The flow regimes selected and shown on Table 8. 2-1 provides effective
spawning and rearing habitat which are in excess of natural conditions. The
instream study showed that post-project operation should not result in
material temperature variations. Similarly, the selection of appropriate
seasonal flow releases considered the needs of juvenile fish and salmon
S-3
embryos for incubation, passage for outmigration and passage to and from
feeding areas.
8.2.2 Access to Project Site
Several means of access to the project site, other than those proposed by
the preferred plans of both the COE and this report, have been studied and
reviewed. In its FEIS, the COE identified an alternative access that
requires extension of the East End road. This road runs northeast out of
Homer through the hills above Kachemak Bay. To develop this road for
project access would require extending the East End road northeastward past
Caribou Lake, across Fox River Valley, and along the foothills of the Kenai
Mountains to join the project road. Although parts of this road could be
made to parallel or be contained within the right-of-way ~f the presently
proposed transmission line, the road alignment would cross the fresh water
wetlands and impact moose habitat, eagle nesting areas, river otter habitat
and approach important staging and nesting areas of migrating waterfowl and
shorebirds. About 20 miles of new construction would be needed, along with
adequate clearing for road construction and right-of-way. In addition, to
the impacts within the Fox and Sheep River wetlands, further consideration
of the East End road would require additional technical and environmental
studies to fully assess impacts along its entire length and to formulate
appropriate mitigation recommendations. It is concluded that both
environmental and economic concerns resulting from the development of this
alternate access way preclude its further consideration.
8.2. 3 Martin River Borrow Site
The Martin River area is considered the most economically and
. ~Il.Yil:'Qil_m_entally _ a.c:c.:_e.pt,abJ~ ar-~~ fQr P9X'rQW_ of gravel and ot_her s_imilar
materials needed for project construction. The preferred plan described by
this report reduces the quantities of material that would be b.orrowed from
the Martin River gravelled delta area in comparison to previously suggested
plans. Borrow material from this site have been identified for the
following project construction needs:
8-4
PROJECT ROADS
Airstrip to Powerhouse
Embankment
Gravel Surfacing
Powerhouse to Lower Camp
Embankment
Gravel Surfacing
Rip rap (from excavation of lower-to-upper
camp road)
Lower-to-Upper Camp
Embankment
Gravel Surfacing
Upper Camp to Dam
Embankment
Gravel Surfacing
Martin River Access
Embankment
Gravel Surfacing
BARGE BASIN-DOCK-CONSTRUCTION
Embankment
Slope Protection (from excavation of lower-
to-upper camp road)
LOWER CAMP SITE AREA
Embankment
AIRSTRIP
Embankment (less material from tunnel excavation)
POWERHOUSE & SUBSTATION CONCRETE
Gravel and Sand
POWER CONDUIT & WATERWAYS CONCRETE
Gravel and Sand
---------------------
DAM AREA & SPILLWAY CONCRETE
Gravel and Sand
TOTAL ESTIMATED NEEDS FOR BORROW
8-5
Borrow Quantity
(cubic yards)
1,500
1,000
215,000
12,900
0
0
8,500
0
6,900
25,000
0
55,000
0
150 '000
156,000
6,000
.. 41,000
25,000
703,800
The above total quantity represents a reduction of about 333,000 cubic
yards of material, when compared to the quantities for similar construction
items of the preferred plan previously studied by the COE.
I
The areas that would need to be excavated to provide the total quantity of
embankment material, gravel, and sand material would greatly depend on the
depth of excavation that can be developed within acceptable environmental
limits. For example, a 10 foot deep excavation would require about 55
acres assuming a 20 percent allowance for waste and bulking. The concepts
for developing the borrow area will be prepared during the FERC License
Application effort of the project and will consider both environmental
aspects as well as availability and location of material sources.
An acceptable development plan for this site, which is currently being
evaluated, will review the possibility of excavating for borrow with a work
area of irregular forms and shapes, and with depths of excavation varying
from 6 to 15 feet. Small causeways, from where excava.ting and trucking
equipment can operate, would be incorporated in the plan. Contouring
during development and after construction would also be considered to
ensure the area would minimize fish and wildlife habitat impacts. The plan
would be submitted to resource agencies for input and comment prior to its
incorporation in construction documents for the project.
8.2.4 Waterfowl Nesting
Under the present concepts of project development, it is planned to spoil
material excavated from the barge basin and its access channel in an area
that will be enclosed by the powerhouse to camp access road embankment and
the shoreland. The area identified for spoil is about 40 acres and is
located east of Sheep Point. About 464,000 cubic yards of material would
have to be dredged and spoiled. Disposal of these materials would be
accomplished by pumping the dredged material into large compartmentalized
areas. Present data on the slurry material indicates that about 18 hours
of retention will be needed within thes~ diked areas to allow for
settlement -of clayey silt soils. Although definitiv~ plans for the
disposal-dike area have not been determined, it is proposed that upon
8-6
completion of disposal, the ground surface of the spoil area be graded to
raise portions of the fill surface to above mean higher high water
elevation, to provide surface drainage and ponds. The plans for developing
waterfowl habitat would be prepared during the FERC License Application
effort in consul tat ion with agency personnel, before incorporating into
construction contracts.
8.2.5 Moose Migration
Previous environmental evaluations have identified that moose use the upper
flatlands of Bradley Lake as a migratory corridor to reach wintering
habitat near Nuka Bay on the east coast of the Kenai Peninsula. In order
to obtain a better understanding of moose migratory and dispersal patterns,
the Power Authority has authorized a fall-winter 1983 study to observe
moose movements across the upper reaches of Bradley Lake. This study would
record the moose pattern and characteristics of moose migration froq~_, the
•,;..,,
Kachemak Bay area, across the upper end of Bradley Lake and over to the
Nuka River Valley crossing area. The results from this study will be used
as input for formulating mitigative measures regarding moose.
8 . 3 IMPACT ADJUSTMENTS
8. 3.1 Elimination of Alternative Structures
The preferred plan presented in this report incorporates several
modifications that either eliminate or minimize environmental impacts
resulting from project development.
Environmental impacts to the project have been reduced with the elimination
of:
o The 2,800 feet long exposed penstock from the powerhouse to the tunnel
portal.
o A 2-mile access road from the powerhouse to the power tunnel portal.
8-7
o The access road that would have been required for the development of
the surge shaft and the surge shaft construction itself.
o The exposed steel penstock and bridge, and its associated access road,
needed for the power tunnel Bradley River crossing, about one half a
mile downstream of the dam.
The above modifications have eliminated wildlife, terrestrial and visual
impacts that would have resulted had these structures been included in the
preferred plan; It is estimated that about 26 acres of timber resources,
consisting of mature conifer and mixed conifer-deciduous forest will be
saved by the ·elimination of the penstock and access road clearing.
Similarly, the visual aesthetics of the mountain slope will remain intact.
The elimination of the exposed steel penstock and bridge and its associated
construction work will reduce the impact to the mountain goat wintering
area and movement corridor.
8. 3. 2 Additional Project Features
One of the requirements of the present feasibility study was to review
previous transmission line routes and to identify alternative routes that
may be considered technically acceptable and which have a reduced
environmental impact and may be more acceptable to the people of the
region. In selecting alternative routes, a review was made of the FEIS to
ascertain the concerns and impacts associated with transmission alignments
previously proposed by the COE. The impacts identified were:
o Encroachment on privately owned lands
o Encroachment on nesting and staging areas for migratory birds
Two field trips, a brief review of land ownership and preliminary soil
probes along considered routes resulted in the corridor alignment presented
by this report. The proposed corridor has not been presented to any
agencies, or the public. Although portions of thecorridor are in the same
alignment as the transmission routes studied by the COE, it will be
8-8
necessary to better assess the environmental effects of this new
alignment. The first section of the proposed corridor, from the powerhouse
to the Fox River and Sheep Creek deltas, is approximately 6 miles long and
transverses the heavily forested area along the slopes of the Kenai
Mountains. The second section, across the Fox River delta at the head of
Kachemak Bay, is approximately 3 miles long and is over open terrain.
Toward the northwest, the third section traverses a flat plain for about 10
miles from the delta to the tie with the Homer Electric Association
transmission line. Although a 1600 feet wide corridor is offered for
flexibility of line alignment, the two circuit parallel lines will actually
require a right-of-way width of 225 feet plus an additional 50 feet on
either side for selective cutting of trees to prevent high tree fall from
interfering with the line. Only the tallest danger trees will be
selectively cut in this additional width beyond the clear cut
right-of-way. An assessment of these impacts will be made during the FERC
license preparation period.
An additional feature presented by this report, not previously identified;
is the construction of a 210 bed campsite near the upper dam area of the
project. Development of this campsite will require the preparation of
about 3 acres of land that is found adjacent to an oblong lake,
approximately 1.1 miles west of the proposed dam, near the recommended
access road alignment. If developed, the camp will draw water from the
lake for domestic use and fire protection. Specific utility requirements
for this site have not been defined and additional baseline data are needed
to ascertain and resolve such requirements, as well as, environmental
impacts to the lake and the transportation corridor between the upper camp
and the lower area facilities.
8-9
PROPOSED HABITAT MAINTENANCE FLOWS
FOR PROJECT PLANNING PURPOSES
Activity Recommendedl
Month (life stage) Streamflow
October Rearing 50
November Incubation 40
December Incubation 40
January Incubation 40
February Incubation 40
March Incubation 40
April Incubation/Outmigration 40/100
May Outmigration 100
June Rearing 100
July Spawning 100
August Spawning 100
September Spawning/Rearing 100/50
(1) Instantaneous m~n~um flows to be provided at the USGS gage station at
RM 5.1 on the lower Bradley River
.___ ________ TABLE 8.2-1
9
LAND AND
LAND RIGHTS
9. LAND AND LAND RIGHTS
The majority of project lands were withdrawn for the purposes of the
development of a hydroelectric project by Public Land Order 3953, dated
March 15, 1966, and amended by Public Land Order 4056, dated July 18,
1966. The withdrawal included approximately 38,066 acres of Federally
owned land. The project reservoir and structures will require
approximately 4, 300 acres. The remaining 33,766 acres will be used for
watershed protection.
The Bradley Lake transmission line corridor extends from the powerhouse to
the new transmission line to be built by Homer Electric Association between
Fritz Creek and Soldotna. The corridor is approximately 20 miles long in
three contiguous sections. The first section extends northeastward from
the powerhouse to the Fox River and Sheep Creek delta and is approximately
6 miles long. The second section, 3 miles long, crosses the delta at the
head of Kachemak Bay in a northwesterly direction. The third section
traverses about 10 miles extending toward the west from the delta to the
Bradley Junction and the tie with the Fritz Creek-Soldotna line. A
preliminary corridor width of 2,000 feet has been identified within which
the final alignment will be established. The right-of-way for the two
parallel, wood pole, 115 kV lines will consist of a 225 to 325 feet wide
corridor and will encompasses approximately 750 acres of land.
The borrow sources for construction materials are located in lands
withdrawn for the project under Land Orders 3953 and 4056.
The project facilities are located within Federal, State, and private
lands. The transmission line corridor crosses mostly Federal and State
lands: the Fox River Flats Critical Habitat Area on the east side but does
not enter the Kenai National Moose Range Expansion, withdrawn by Public
Land Order 5653, dated November 16, 1978. It does cross six identified
parcels of private land, however title and ownership for these private land
were not investigated in this study.
9--1
An estimate of land acquisition cost is included in the Project Cost
Estimate for private lands along the transmission line. Further
investigation is required within the transmission line corridor to
establish the required 325 feet wide right-of-way limits. This will be
accomplished during preparation of the FERC License Application for the
project.
9-2
10
PROJECT SCHEDULE
AND
CONSTRUCTION
CONTRACTS
10. PROJECT SCHEDULE AND CONSTRUCTION CONTRACTS
10 . 1 GENERAL
The proposed project schedule is shown on Plate 23. The schedule has been
developed to delineate the major construction and procurement contracts
described below.
The project schedule extends over a five year period with the initiation of
construction activities dependent upon the award of a FERC license for the
project. Receipt of a FERC license is anticipated in May 1985 with.
commercial .operation of the units scheduled during the Fall of 1988 and
final project completion before the end of 1988. The critical path
involves those activities related to FERC license Application processing;
design, fabrication, and delivery of the tunnel boring machine; power
tunnel excavation; inclined shaft excavation; concrete tunnel lining and
steel liner embedment, penstock installation, arid start· iip of tlie turoirie
generators.
Should award of the FERC license be delayed, seasonal scheduling problems
will ensue, and the entire project schedule and commercial operation dates
will be delayed.
10.2 ENGINEERING AND DESIGN
Engineering and design activities will commence upon submittal of the FERC
license application in February 1984. The initial thrusts of these
activities will be directed toward seeping and implementing various field
surveys, and conducting detailed engineering studies and analyses. The
results of these studies will then be utilized in developing design
criteria for final design of the various civil features and developing
performance standards and specifications for purchasing the major
mechanical and electrical equipment.
Procurement of the turbine/generator equipment will be required at an early
stage to provide data and information to support continuing work efforts on
10-1
the powerhouse auxiliary equipme:Q.t, and allow commencement of engineering
and design of the powerhouse civil works and powerhouse crane.
Concurrently, engineering and design of the other major civil structures
and facilities will occur during 1984 and extend into 1985. Other
activities scheduled within this period will include FERC licensing support
activities and preparation and submittal of the various Federal and State
licenses and permits required prior to construction.
Environmental monitoring and agency consultation will continue as required
throughout the entire schedule.
10. 3 CONSTRUCTION SCHEDULE
With the exception of transmission line construction, the primary criteria
utilized in developing the overall schedule was to schedule the various
construction activities during the milder seasons.
Upon award of the General Civil Contract, the Contractor will mobilize, and
design and fabrication of the Tunnel Boring Machine (TBM) will commence.
This will be followed by construction of the lower access, staging and camp
facilities, powerhouse excavation, and power tunnel portal excavation, all
of which must be completed to accept delivery of and commence power tunnel
excavation with the TBM.
Access from the barge basin and staging facilities to the reservoir area
will be established in two phases. The initial phase will consist of
developing a pioneer road along the final alignment utilizing work crews to
develop initial headings at strategic points along the route. The initial
headings will be extended until the route is completely opened, allowing
access to begin construction of the diversion tunnel. The second phase,
concurrent with diversion tunnel construction, will consist of roadway
widening and other improvements and will be completed prior to the harsher
winter months.
10-2
Construction of the cofferdams at the lake outlet will commence in March
1986, followed by construction of the main dam and excavation of the intake
tunnel. Should work on the main dam be d~layed during 1986, due to the
early onset of inclement weather, it can be completed during 1987 since the
dam is not on the critical path.
Excavation of the power tunnel using the TBM will continue through 1986
followed by excavation and lining of the inclined and intake gate shafts.
Once excavation of the inclined shaft has been completed, installation of
the concrete and steel lining for the power tunnel will commence from the
inclined shaft and continue toward the tunnel portal.
The powerhouse construction contract award has been scheduled for October
1986 with construction extending over an 18 month period. Powerhouse
excavation will be performed to accommodate simultaneous work activities on
the powerhouse and power tunnel during this period.
Construction of the transmission facilities and switchyard are not critical
to project completion since construction electrical power will be furnished
by contractor supplied diesel generators. As such, these activities have
been tentatively scheduled for the 1986-87 winter period.
10. 4 CONTRACTS
It is unlikely that sufficient information will be available to permit the
construction facilities, main dam, power conduit and powerhouse to be
included within a single contract. Therefore, three major construction
contracts are proposed, as well as one major equipment order and various
miscellaneous supply orders. The facilities, material, and equipment
encompassing each of the contracts and procurement orders are descr_ibed
below.
10.4 .1 General Civil Contract
The General Civil Contract will include the construction of the barge
basin, access roads, construction camps, warehouse, and staging area,
10-3
powerhouse excavation, powerhouse laydown and staging area-, airstrip,
borrow pits, tunnel portal, power conduit, steel liner, construction
diversion facilities, cofferdams, main dam, spillway, Middle For Diversion,
and the permanent camp and warehouse facilities.
10.4.2 Powerhouse Contract
The Powerhouse Contract will include the construction of the powerhouse,
installation of the generation equipment and auxiliary electrical and
mechanical equipment and the penstock between the tunnel portal and
powerhouse, powerhouse substation, and tailrace.
10.4.3 Transmission Line Contract
The Transmission Line contract will include the construction of two
_parallel 115 kV three phase lines to connect the Bradley Lake powerhouse
substation with the new line to be built between Fritz Creek and Soldotna.
The new Fritz Creek-Soldotna line will be in place and provision for the
construction of a tap is included at Bradley Junction.
10. 5 SUPPLY ORDERS
The major equipment order will include the design, manufacture,
fabrication, and delivery of the generation equipment including two Pelton
turbines, generators, governors, spherical valves, air depression system,
and accessory mechanical and electrical equipment.
Miscellaneous supply orders will include:
o Electrical and Controls
1. Generator Breakers
2. Main Power Transformers
3. Control and Relay Boards
4. Supervisory Control and Data Acquisition Equipment
10-4
5. Station Batteries and Battery Chargers
6. 480V Load Centers
7. Hotor Control Centers
8. Isolated Phase Bus and Enclosures, PT' s and Surge Equipment
9. Plant Telephone and Paging System
10. Event Recorder
11. Diesel and Propane Driven Generators
12. Reservoir Water Level Recorders
o Hechanical and Building Service
1. Powerhouse Bridge Crane
2. Station and Unit Unwatering Pumps
3. Service Water Pumps
4. Transformer Oil Treatment System
5. Lube Oil Treatment System
6. Oil Separators
7. Dirty Water PUmps
8. Air compressors System and Driers
9. Service Water Strainers and Filters
10. Special Hazards Fire Protection Systems
11. C0 2 Detection System
12. Fire Pumps, Motors, and Accessories
13. HVAC Equipment
o Hydro-Civil and Power
1. Intake Gates, Guides and Operators
2. Intake Trash Racks and Bulkheads
3. Draft Tube Gate and Lifting Beam
4. Miscellaneous Large Gates and Valves
5. Construction Diversion Stop Logs
o Switchyard
1. Carrier Equipment
10-5
2. High Voltage Breakers
3. Disconnect Switches
o Construction Support
1. Penstocks, Tunnel Liners, and Miscellaneous Large Pipe
2. Structural Steel and Crane Rails
10-6
11. PROJECT COST ESTIMATES
11. 1 PROJECT COST ESTH1ATE SUMMARY
In response to the requirements of the Alaska Power Authority and the needs
of the feasibility study, a cost estimate has been prepared for the
preferred 90 MW Bradley Lake project. The cost estimate is:
0
0
Bid Price Cost
Overnight Cost
$308,400,000
$283,019,000
A summary of the main stem accounts by FERC classification and other costs
included are shown by Table 11.1-1. The summary is followed by the
expenditure forecast of the overnight estimate, and the detailed estimate
consisting of eleven pages.
The Cost Estimate includes the following:
o Direct material, labor, and construction equipment.
o Engineering and design.
o Construction management.
o Construction distributables.
o Contingency.
o All-risk insurance.
o Land and land rights.
o Based on the Project Construction Schedule in Section 10 of this Report.
o Bid price estimat·e assumes July 1983 construction start date, the
Overnight Estimate assumes a present day of July 1983.
o Owner's cost; including general and administrative, legal, engineering,
financing cost, etc.
o Escalation during the construction period only.
This estimate excludes the following:
o Escalation other than that during the construction period.
o Interest during construction.
11-1
The Overnight Estimate is the Bid Price Estimate modified by the amount of
$25,381,000, which reflects a credit for the escalation during the
construction period. It is our understanding that the Alaska Power
Authority will use the Bid Price Estimate, and adjust this accordingly, to
develop the Nominal Cost Est·imate for project financing studies and plans.
The estimates are based on conceptual level studies and drawings and a
preliminary construction schedule. Representative data and budget costs
received from major equipment manufacturers on items such as turbines,
generators, bridge cranes and transformers . were used in the cost
estimates. Estimates of major quantities are developed from the conceptual
level drawings and smaller items are prorated from costs for similar past
projects. Material unit prices are from several sources such as existing
purchase orders, contracts on current work, publications, budget prices
from suppliers and other bona fide data. Labor manhour rates were
developed from State of Alaska Department of Labor publications with
appropriate adjustments as required.
included where applicable.
Contractor's equipment costs are
The economics of the Bradley Lake Hydroelectric Project is dominated by the
cost of the power tunnel. Field and office investigations by SWEC
engineers and the Consultants on the Technical Review Board conclude that a
substantial portion of the power tunnel can be excavated using a tunnel
boring machine (TBM) including crossing through the fault zones. The
project cost estimate is therefore based on the contractor using a tunnel
boring machine to excavate approximately 16,850 feet of the tunnel. The
rates of progress for the TBM excavating the tunnel as used in the cost
estimate were developed from on-site field examinations of the various rock
types along the tunnel alignment, laboratory testing of rock samples of the
rock to be excavated; and correlation with the progress rates being
experienced on the Power Authority's Terror Lake Project.
allowances are included in the estimate for full concrete
In addition,
lining of the
entire length of tunnel. The cost estimate for the tunnel was reviewed by
an expert in tunnel construction and construction costing.
11-2
The, cost of engineering and design is based on SWEC' s Bradley Lake Proposal
and includes the cost of this Feasibility study.
The costs for the Construction Manager were made available to SWEC by the
Power Authority as were Owner's cost. Owner's cost includes previous
expenditures for studies on Bradley lake subsequent to its assumption by
the Power Authority.
A contingency of 25 percent is applied to arrive at the Bid Price
Estimate. Escalation is included at the rate of 6. 3 percent annually for
the three year construction period only, assuming a start of construction
date of July, 1983.
11.2 COST ESTIMATES FOR ECONOMIC ANALYSIS
In determining a selected installation for development of the Bradley La~~
Project, it was necessary to cost and evaluate 60 MW, 90 MW and 135 MW
installations using both Francis and Pelton type hydraulic turbine units in
the powerhouse, as well as a range of different dam heights for the upper
reservoir. Cost estimates prepared for each of these installations were
then used in the economic evaluation computer model which assessed the
merits of Bradley Lake in a mix of alternative generating and transmission
line scenarios. A summary of the Present Day Estimates (Overnight)
selected for the seeping economic evaluation studies are given in Table
11.2-1. It should be noted that these estimates reflect costs for interest
during construction less escalation (interest at discount rate). The
inclusion of this cost item complies with the .Alaska Power Authority
Economic Evaluation Guidelines FY83. Having selected a preferred plan, a
similar cost estimate was prepared and used in the final economic
evaluatiofl study reflecting the attributes of the preferred plan in the
generation planning scenarios.
Plant Operating and Maintenance (O&M) costs were developed for the economic .
evaluation studies, as were O&M costs for the transmission line connecting
the project to the proposed Homer Electric Association line. Further,
construction costs were prepared for a 230 kV transmission line that would
11-3
connect the Kenai Peninsula to the Anchorage area, as were O&M costs for
this line. These cost data are shown on Tables 11.2-2 through 11.2-5.
11-4
FEASIBILITY STUDY COST ESTIMATE
90 MW PREFERRED PLAN
FERC
ACCOUNT DESCRIPTION
330
331
332
333
334
335
336
350
352
353
357
Production Plant
Land & Land Rights
Power Plant Structures
Reservoirs, Dams & Waterways
Turbines & Generators
Accessory Electrical Equipment
Mise Power Plant Equipment
Roads, Barge Facility & Airstrip
TOTAL PRODUCTION PLANT
Transmission Plant
Land & Land Rights
Switcbyard Structures
Switchyard Equipment
Transmission Line
TOTAL TRANSMISSION PLANT
Construction Distributables
Construction Camp ·
Mobilization/Demobilization
Other Construction Items
Construction Management
TOTAL CONSTRUCTION DISTRIBUTABLES
TOTAL CONSTRUCTION COST
Engineering & Design
TOTAL CONSTRUCTION & ENGINEERING
Owner's Cost.
TOTAL CONSTRUCTION & INDIRECTS
Contingency
BID PRICE ESTIMATE
Escalation
OVERNIGHT ESTIMATE*
*Present day as of July, 1983.
($ in OOO's)
2,783
9,~43
87,715
16,829
4,501
4,411
13,474
139,156
11
1,940
1,279
7 1 599
10,829
24,263
10,476
13,133
14 1 243
62,155
212,100
28 1 500
240,600
6 1 100
246,700
61 1 700
308,400
(25 1 381)
283,019
'-----------TABLE 11.1-1
EXPENDITURE FORECAST OF OVERNIGHT ESTIMATE
(PRESENT DAY 7 /83)
BRADLEY LAKE PROJECT
ALASKA POWER AUTHORITY
Calendar Year
1983
1984
1985
1986
1987
1988
Total Overnight Estimate
Dollars in
Thousands
2,200
8,200
65,990
78,160
83,080
45,389
283,019
PG 2 OF 13
'-----------TABLE 11.1-1
ORDER OF MAGNITUDE ESTIMATE
90 MW PLANT
FEASIBILITY STUDY COST ESTIMATE
CLIENT-ALASKA POWER AUTHORITY STONE & WEBSTER ENGINEERING CORPORATION
PROJECT-BRADLEY LAKE HYDROELECTRIC PROJECT ORDER OF MAGNITUDE ESTIMATE
~AIN SUB CORP CC
STEM ACCT ACCT ST M L DESCRIPTION
330 1000 1000 0 •:l 0 LAND ~ LAND RIGHTS
90 Mil PLANT
FEASIBILITY STUDY COST ESTIMATE
GUAN UN
330 3000 0 0 0 0 ENVIRONMENTAL MITIGATION
I LS
I LS
1 LS 330 5000 0 0 0 0 EXHIBIT R -RECREATION
330 TOTAL LAND ~ LAND RIGHTS
POWER PLANT STRUCTURES & IMPROVEMENTS
1000 7101) POWER HOUSE
1100 7100 2 A A EXCAVATION-UPPER BENCH
1110 7100 2 A A EXCAVATION-FIRST STAGE
1120 7100 5 A A BACKFILL-SELECT TEMP.
1130 7100 1 A E REMOVAL OF TEMP. FILL
1200 7100 2 A A EXCAVATION-SECOND STAGE
1201 7100 5 A A BACKFILL-COI!"ON
1202 7100 7 A A ROCK BOLTS
. 1320 7100 10 A E SURFACE CLEANING
1511 7100 11 A E CONCRETE
1522 7100 15 A E FORMS-STRAIGHT
1523 7100 16 A E FORMS-CURVED
1524 7100 19 A E REINFORCING
1520 7100 14 A E SURFACE FINISH
1530 7101) 22 A E EMBEDMENTS
1610 7100 20 A E STRUCTURAL STEEL
1630 7100 99 A E ARCHITECTURAL ALLOWANCE
1650 7100 31 A E FIRE PROTECTION-WATER
1660 7100 31 A E PLUMBING ~ DRAINAGE
1670 7100 31 A E HEATING ~ VENTILATION
1680 7100 41 A E LIGHTING
TOTAL POWER HOUSE
1000 CY
53000 CY
1380 CY
1380 CY
13800 CY
1180 CY
120 EA
6900 SF
4600 CY
39200 SF
4650 SF
278 TN
16000 SF
22000 LB
270 TN
1 LS
1 LS
1 LS
1 LS
1 LS
DATE OF ESTIMATE 10/24/83
BID PRICE DATE-JULY 1983
UNIT
COST
0.00
2,226,000.00
556,500.00
14.54
14.54
6.57
5.41
24.23
6.78
364.14
1.02
213.29
38.59
54.24
3,175.30
1.02
5.93
3,710.92
722,635.00
75, B41. 50
665,215.00
78,870.50
175,449.00
JOI !4500
?6 1 OF!!
PG 3 OF 13
TOTAL
COST
0
2,226,000
556,5•JO
2,782,500
14,537
770,466
9,070
7,470
334,353
a,ooo
43,697
7,017
981,123
1,512,708
252,216
882,733
16,272
130,515
1,001,948
722,635
75,842
665,215
78,871
175,449
7,690,138
..__ _________ TABLE 11.1-1
ORDER OF MAGNITUDE ESTIMATE
90 MW PLANT
FEASIBILITY STUDY COST ESTIMATE
CLIENT-ALASKA POWER AUTHORITY STONE & WEBSTER ENGINEERING CORPORATION DATE OF ESTIMATE 10/24/83
BID PRICE DATE-JULY 1983
PROJECT-BRADLEY LAKE HYDROELECTRIC PROJECT
MAIN SUB CORP CC
STEM ACCT ACCT ST M L DESCRIPTION
ORDER OF MAGNITUDE ESTIMATE
90 ~~~ PLANT
FEASIBILITY STUDY COST ESTIMATE
QUAN UN
-------------------------------------------------
~.,.,
.,j.j,.
1700 ilOO STATION YARD
1710 7100 98 A A CLEARING @ POWER HOUSE 2 AC
1711 7!00 99 A E SRADE,DRAIN & LANDSCAPING 5 AC
1722 7100 99 A E FENCING ~ GATES 1 LS
1730 7100 41 A E LIGHTING I LS
1740 7100 31 A E WATER SUPPLY 1 LS
TOTAL STATION YARD
2000 HISC BLDG ~ STRUCTURES
2400 9220 26 A A WAREHOUSE & SHOP 1 LS
2500 8220 26 A A me 1 LS
TOTAL HISC BLD6 ~ SiR
3000 8220 OPERATORS VILLAGE
.3100 8220 STRUCTURES
3110 8220 26 A A PERMANENT CAMP 1 LS
3120 8220 26 A A SINGLE FAMILY RES. 1 LS
3200 8220 SERVICES
3210 8220 31 A A WATER LS
3220 8220 31 A A SEWER LS
3230 8220 41 A A L!SHTING LS
3300 8220 99 A A SR!JUNDS LS
TOTAL OPERATORS VILLAGE
331 TOTAL POWER PLANT STRUCTURES ~ iMPROVEMENTS
UNIT
COST
6,090.00
5,075.00
16,747.50
50,496.25
39,458.12
618,600.00
38,662.50
541,275.00
409,822.50
COST INCLUDED WITH
TRMPORARY CAI'IP
JOt !4500
PG 2 OF!!
PG 4 OF 13
TOTAL
COST
12,180
25,375
16,748
50,496
39,458
144,257
618,600
38,663
657,263
541,275
409,823
951,!)98
9,442,755
'--------------TABLE 11.1-1
·ORDER OF MAGNITUDE ESTIMATE
90 MW PLANT
FEASIBILITY STUDY COST ESTIMATE
CLIENT-ALASKA POWER AUTHORITY STONE & WEBSTER ENGINEERING CORPORATION DATE OF ESTIMATE 10/24/83
BID PRICE DATE -JULY 1983
PROJECT-BRADLEY LAKE HYDROELECTRIC PROJECT ORDER OF MAGNITUDE ESTIMATE
90 ~II PLANT
FEASIBILITY STUDY COST ESTIMATE
MAIN SUB CORP CC
STEM ACCT ACCT ST M L DESCRIPTION QUAN UN
332 RESERVOIRS, DAMS & WATERWAYS
3000 3000 RESERVOIR
3110 3000 98 A A CLEARING 2480 AC
3200 4100 ROCI<FILL DAI'I-1180 POOL ELEVATION
32!0 4100 COFFERDAM & PUMPING
3211 4100 6 A A U/S COFFERDAM 1 LS
3212 4100 97 A A PUMPING & MAINT. 24 KO
3213 4100 1 A A RE!1!JVAL 1 LS
3220 4100 6 A A DIS COFFERDAM II/ MAIN DAM 1 LS
3300 4100 EXCAVATION
3311 4100 I A A UNCLASSIFIED 63500 CY
3312 4100 2 A A SOLID ROCK-TOE SLAB 3200 CY
3313 4100 10 A A FOUNDATION PREPARATION 1900 SY
3J14 4100 8 A A DR ILL & 6ROUT 1 LS
3400 4100 CONCRETE-FACE ~ TOE SLAB
3411 4100 19 A A REBAR 563 TN
3412 4100 15 A A FORMS 131100 SF
3413 4100 11 A A CONCRETE 8940 CY
3414 4100 99 A A DEFLECTOR 64300 LB
3500 4100 EMBANKI1ENT
3511 4100 A A QUARRY & PLACE
3512 4100 6 A A ROCKFILL 278700 CY
3513 4100 6 A A SELECT FILL 83000 CY
3514 "4100 6 A A RIP-RAP-HEAVY 2400 CY
TOTAL ROCKFILL DAM EXCL RESERVOIR
UNIT
COST
461.27
293,056.40
24,277.50
135,954.00
o.oo
14.57
50.71
5.50
86,239.08
2,114.84
28.59
203.66
2.29
10.47
12.56
104.66
JOt 14500
PG 3 OF!!
PG 5 OF 13
TOTAL
COST
1,143,956
293,056
582,660
135,954
f)
924,973
162,282
10,456
86,239
1,!90,655
3,748,608
1,820,732
147,432
2,916,958
1,042,443
251,191
13,3!3,638
'------------TABLE 11.1-1
ORDER OF MAGNITUDE ESTIMATE
90 MW PLANT
FEASIBILITY STUDY COST ESTIMATE
CLIENT-ALASKA POWER AUTHORITY STONE & WEBSTER ENGINEERING CORPORATION
PROJECT-BRADLEY LAKE HYDROELECTRIC PROJECT
MIN SUB CORP CC
STEM ACCT ACCT ST K L DESCRIPTION
ORDER OF MAGNITUDE ESTIMATE
90 Mil PLANT
FEASIBILITY STUDY COST ESTIMATE
QUAN UN
-------------------------------------------------
332
2900 4200 SPILLWAY
2911 4200 I A A EXCAVATION-COHI!ON 8500 CY
2912 4200 2 A A EXCAVATION-ROCK 7300 CY
2913 4200 5 A A BACKFILL 300 CY
2915 4200 7 A A ROCK BOlTS 1800 LF
2930 4200 12 A A CONCRETE 10075 CY
2931 4200 15 A A FORMS-STRAIGHT 23000 SF
2932 4200 16 A A FORH5-CURVED 4700 SF
2933 4200 19 A A REBAR 167 TN
2950 4200 9 A A DRAINS 1 LS
2960 4200 8 A A GROUTING 80 CF
2961 4200 10 A A FOUNDATION CLEANING 3500 SY
2962 4200 18 A ll WATERSTOPS 1 LS
2970 4200 14 A A ENERGY DISSIPATOR 1 LS
TOTAL SPILLWAY
5000 4700 WATERWAYS
DIVERSION TUNNEL
5100 470(1 2 A A EXCAVATION-PORTAL 1550 CY
5120 4700 4 A A EXCAVATION-TUNNEL 0170 CY
5125 4700 2 A A EXCAVATION-DIS CHANNEL 600 CY
5130 4700 7 A A ROCK SUPPORTS 1 LS
5151 4700 13 A A CONCRETE 941 CY
5152 4700 19 A A REBAR 16 TN
5153 4700 17 A A FORMS-TUNNEL 15100 SF
5154 4700 15 A A FORI'IS-5TRAI6HT 2330 SF
5160 4700 24 A A STEEL STOP LOGS 76000 LB
5161 4700 12 A A CONCRETE 420 CY
5162 4700 19 A A REBAR 21 TN
5163 4700 15 A A FORtiS 1895 SF
5170 4700 8 A A GROUT RING (PLUSJ 1 LS
5180 4700 32 A A GATES ~ VALVES 1 LS
5181 4700 22 A A me STEEL 1 LS
TOTAL DIVERSION It CONTROL STRUCTURE
DATE OF ESTIMATE 10/24/83
BID PRICE DATE -JULY !983
UNIT
COST
10.17
16.44
10.17
14.80
190.97
25.43
111.59
2,327.80
13,899.00
28.25
5.711
2,825.00
56,500.00
30.24
386.63
30.24
482,095.60
307.80
3, ;)86.84
14.92
27.43
3.62
244.17
3,856.58
23.59
148,229.90
310,419.20
256,569.04
JOI 14500
PG 4 OF!!
PG 6 OF 13
TOTAL
COST
86,445
120,023
3,t)Sl
26,645
1, 924,023
584,775
289,450
388,743
13,899
2,260
20,171
2,825
56,500
3,518,809
411,868
2,385,476
18, !42
482,096
289,643
54,189
225,348
63,923
274,759
102,552
80,988
44,712
148,230
310,419
256,569
4,783,?15
------------TABLE 11.1-1
CLIENT-ALASKA POWER AUTHORITY
ORDER OF MAGNITUDE ESTIMATE
90 MW PLANT
FEASIBILITY STUDY COST ESTIMATE
STONE ~ WEBSTER ENGINEERING CORPORATION DATE OF ESTIMATE 10/24/83
BID PRICE DATE -JULY 1983
PROJECT-BRADLEY LAKE HYDROELECTRIC PROJECT ORDER OF ~AGNITUDE ESTIMATE
90 "W PLANT
FEASIBILITY STUDY COST ESTIMATE
MAIN SUB CORP CC UNIT
STEM ACCT ACCT ST II L DESCRIPTION QUAN UN COST
-------------------------------------------------
__ .,
.:,.;;;..:.
5200 4500 ~IDDLE FORK DIVERSION
5210 4500 99 A A SKY CRANE $8000/HR 1 LS 994,400.00
5211 4500 2 A A EXCAVATION 100 CY 35.60
5213 4500 10 A A SURFACE CLEANING 9000 SF 1.36
5215 4500 6 A A ROCKFILL-DAII 4500 CY 35.60
5216 4500 28 A A SHEET PILE 42 TN 1,586.52
5217 4500 11 A A CONCRETE 190 CY 324.87
5218 4500 19 A A REBAR 20 TN 3,599.05
5219 4500 15 A A FORIIS 3100 SF 42.94
5220 450(1 8 A A 6ROUT CURTAIN 1 LS 9,605.00
5225 4500 99 A A WOODEN ACCESS BRIDGE 1 LS 30,510.00
5231 4500 2 A A EXCAVAT!UN-PIPE TRENCH 6600 CY 35.60
5232 4500 5 A A BACKFILL 9250 CY 15.26
5235 4500 .33 A A STEEL PIPE o'DIA 3/S"WALL 2020 LF 562.18
5236 451'.10 24 A A SLUICE SATES 2 EA 44,917.50
5237 ~500 99 A A HISC STEEL 1000 LB 3.11
TOTAL MIDDLE FORK DIVERSION
5300 -4410 ?OWER TUNNEL
5310 44!0 HORIZONTAL @ INTAKE
5311 4410 4 A A EXCAVAT!DN-ROCK-CONV 5400 CY 328.80
5312 4410 7 A A ROCK BOLTS 25EA 450.46
5313 4410 7 A A STEEL SETS 7000 LB 2.85
5317 4410 13 A A CONCRETE 2285 CY 320.01
5318 4410 17 A A FORIIS-TUNNEL 33000 SF 7.55
5319 4410 19 A A REBAR 31 TN 4,656.82
JOI 14500
PG 5 OF11
PG 7 OF 13
TOTAL
COST
994,400
3,560
12l204
160,178
66,634
61,726
7!,981
!33,!14
9,605
30,510
234,927
125,854
1,135,594
89,835
3,108
3133228
1~775,520
11,261
19,947
731,230
249,061)
144,361
TABLE 11. 1-1
ORDER OF MAGNITUDE ESTIMATE
90 MW PLANT
FEASIBILITY STUDY COST ESTIMATE
CLIENT-ALASKA POwER AUTHORITY STONE ~ WEBSTER EN6INEERIN6 CORPORATION
PROJECT-BRADLEY LAKE HYDROELECTRIC PROJECT ORDER OF MAGNITUDE ESTIMATE
MAIN SUB CORP CC
90 Mil PLANT
FEASIBILITY STUDY COST ESTIMATE
STEM ACCT ACCT ST K L DESCRIPTION QUAN UN
332
5330 4410
5331 4410 4 A A
5332 4410 7 A A
5336 4410 13 A A
5337 4410 17 A A
5337 4410 16 A A
5338 4410 19 A A
5340 441!)
5341 4410 3 A A
5342 4410 7 A A
5343 4410 7 A A
5346 4410 13 A A
5347 4410 17 A A
5348 4410 19 A A
5350 4410 27 A A
6100 4430
6110 4430
6111 4430 2 A A
6112 4430 b A A
6113 4430 2 A A
6!14 4430 7 A A
6115 4430 7 A A
6116 4430 7 A A
6120 4430 11 A A
6121 4430 19 A A
6122 4430 15 A A
6123 4430 16 A A
INCLINED SECTION
EXCAVATION-RAISE BORE 4000 CY
ROCK BOLTS 50 EA
CONCRETE 1550 CY
FORI'!S-TUNNEL 28650 SF
FORI1S-ELBOIIS 2800 SF
REBAR 22 TN
HORIZONTAL FROH INCLINE TO OUTLET PORTAL
EXCAVATION-TBH 85300 CY
ROCK BOLTS 450 EA
STEEL SETS 127000 LB
CONCRETE 24030 CY
FORMS 504600 SF
REBAR 255 'TN
STEEL LINING 1380 TN
TOTAL POIIER TUNNEL
INTAKE @ RESERVOIR
CHANNEL EXCAVATION
EXCAVATE ~ SPOIL 22300 CY
EXCAVATE (INCL W/DAI!l 52100 CY
EXCAVATE PORTAL 490 CY
ROCK BOLTS-I' 10' 120 EA
ROCK BOLTS-I I 1 5' 75 EA
STEEL SETS 3700 LB
CONCRETE 130 CY
REBAR 16 TN
FORI'!S-STRAIGHT 1170 SF
FORI'IS-CURVED 1190 SF
TOTAL INTAKE STRUCTURE
DATE OF ESTIMATE 10/24/83
BID PRICE DATE -JULY 1983
UNiT
COST
890.40
457.44
315.27
8.04
63.85
4,587.80
280.63
431.58
2. 76
350.98
6.32
4,656.82
7,203.16
15.70
1), 00
50.71
347.71
519.54
2.40
284.46
4,083.32
30.40
43.01
TOTAL
COST
JOI !4500
?S 6 OFll
PG 8 OF 13
3,561,600
22,872
488,669
230,345
178,766
!00,932
23,937,9!0
194,210
351,003
8,434,097
3,189,057
1,187,489
9,940,361
54,748,689
350,!j98
0
24,849
41,725
38,965
8,883
36,979
65,333
35,563
51,185
653,580
TABLE 11. 1-1
ORDER OF MAGNITUDE ESTIMATE
90 MW PLANT
FEASIBILITY STUDY COST ESTIMATE
CLIENT-ALASKA POWER AUTHORITY STONE & WEBSTER ENGINEERIN6 CORPORATION
PROJECT-BRADLEY LAKE HYDROELECTRIC PROJECT ORDER OF nAGNITUDE ESTIMATE
MAIN SUB CORP CC
90 1'111 PLANT
FEASIBILITY STUDY COST ESTIMATE
STEM ACCT ACCT ST M L DESCRIPTION QUAN UN
6300 4430 GATE SHAFT
6310 4430 1 A A EXCAVATE-OVERBURDEN 1350 CY
6311 4430 2 A A EXCAVATE-ROCK ABOVE GRD 2500 CY
6312 4430 4 A A EXCAVATE-SHAFT 2350 CY
6313 4430 7 A A ROCK BOLTS 3/4" B' 75 EA
6314 4430 7 A A ROCK BOLTS 3/4" 6' 7SO EA
6331 4430 13 A A CONCRETE 800 CY
6332 4430 19 A A REBAR 41 TN
6333 4430 15 A A FORI'IS-STRAIGHT 2220 SF
6334 4430 16 A A FORI'IS-CURVED 11650 SF
6341 4430 22 A A I!ISC STEEL 1 LS
TOTAL GATE SHAFT
6600 4430 INTAKE APPURTENANCES
6610 4430 24 A A GATES INCL GUIDES & HOIST 1 LS
6611 4430 24 A A TRASH RACKS I LS
TOTAL INTAKE APPURTENANCES
TOTAL INTAKE STRUCTURE, GATE SHAFT & APPURTENANCES
DATE OF ESTIMATE 10/24/83
BID PRICE DATE -JULY 1983
UNIT
COST
10.17
!5.93
904.00
63.28
49.72
242.05
3,570.80
44.58
63.28
331,655.00
433,680.70
234,704.88
iOTAL
COST
JOI 14500
,PG i OF11
PG 9 OF 13
13,730
39,833
2, 124,400
4, 746
37,290
1'13, 637
146,403
98,964
737,212
331,655
3,727,869
433,681
234,7>)5
668,386
5,049,835
'-----------TABLE 11.1-1
ORDER OF MAGNITUDE ESTIMATE
90 MW PLANT
FEASIBILITY STUDY COST ESTIMATE
CLIENT-ALASKA POWER AUTHORITY STONE ~ WEBSTER ENGINEERING CORPORATION
PROJECT-BRADLEY LAKE HYDROELECTRIC PROJECT
MAIN SUB CORP CC
STEM ACCT ACCT ST M L DESCRIPTION
ORDER OF MAGNITUDE ESTIMATE
90 1111 PLANT
FEASIBILITY STUDY COST ESTIMATE
QUAN UN
-------------------------------------------------
31'? "~
9000 4420 PENSTOCK
8010 4420 2 A A EXCAVATION-ROCK 1380 CY
8011 4420 5 A E BACKFILL 880 CY
8015 4420 7 A A STEEL SETS 0 LB
8016 4420 7 A A ROCK BOLTS 0 EA
9200 4420 27 A E STEa PENSTOCK 80 TN
8205 4420 27 A E ROLL OUT SECTION 10 TN
8210 4420 27 A E m 30 TN
8220 4420 33 A E VALVES INCL W/ T/6 0 EA
8300 4420 11 A E CONCRETE-STRUCTURAL 720 CY
8310 4420 11 A E CONCRETE-LEAN 470 CY
9320 4420 14 A E CONCRETE FINISH W/ CONC 0 SF
8330 4420 15 A E FORMS-STRAIGHT 4600 SF
8350 4420 19 A E REBAR 115 TN
TOTAL PENSTOCK
9001) 7500 TAILRACE
9120 7500 2 A A EXCAVATION-ROCK 3590 CY
9300 7500 24 A E DRAFT TUBE GATES I LS
TOTAL TAILRACE
332 TOTAL RESERVOIRS, DANS & WATERWAYS
DATE OF ESTIMATE 10/24/83
BID PRICE DATE -JULY !983
UNIT
COST
22.24
10.65
8,695.05
9, toB.25
9,641. 45
246.66
179.99
31.35
3,324.23
19.68
46,538.75
TOTAL
COST
JOi !4500
PG 8 0Fl1
PG 10 OF 13
30,692
9,369
695,604
91,683
289,244
177' 592
84,597
144,208
382,286
1,905,274
70,664
46,539
117,203
371 7!4, 546
'-----------TABLE 11.1-1
CLIENT-ALASKA POWER AUTHORITY
ORDER OF MAGNITUDE ESTIMATE
90 MW PLANT
FEASIBILITY STUDY COST ESTIMATE
STONE & WEBSTER ENGINEERING CORPORATION DATE OF ESTIMATE 10/24/83
BID PRICE DATE -JULY 1983
PROJECT-BRADLEY LAKE HYDROELECTRIC PROJECT ORDER OF MAGNITUDE ESTIMATE
90 1111 PLANT
FEASIBILITY STUDY COST ESTIMATE
MAI!l SUB CORP CC UNIT
STEM ACCT ACCT ST ~ L DESCRIPTION GUAN UN COST
-------------------------------------------------
333 WATER WHEELS, TURBINES ~ GENERATORS
1000 7200 51 A E TURBINES-PELTON TYPE 300 2EA 4,317,950.00
RPM INCL SPHERICAL VALVES,
GOVERNORS ~ MODEL TESTS
2000 7200 51 A E SENERATOR-45MN-56.3111VA 2 EA 4,096, 729.00
EXCITATION, REGULATION,
GROUNDING XFI'IR, COOLING
~ SHOP TESTS
333 TOTAL TURBINes· & GENERATORS
334 ACCESSORY ELECTRICAL EQUIPMENT
1000 7300 CONDUCTORS, CONDUITS ~ CABLE TRAY
1220 7300 41 A E GENERATOR LEADS 260 LF 1,747.88
1230 7300 41 A E POWER CABLE 1 LS 666,029.00
1240 7300 41 A E CONTROL CABLE 1 LS 683,774.00
1250 7300 41 A E GROUNDING INCL CATH. PROT 1 LS 282,737.00
1320 7300 41 A E CONDUIT. 1 LS 306,988.50
1340 7300 41 A E CABLE TRAY · 1 LS 357,561.75
2000 7300 SWITCHGEAR & CONTROL E9UIPI1ENT
2310 7300 41. A E GENERATOR BREAKERS,KETAL 1 LS 408,726.50
CLAD SIIITCHGEAR,POTENTIAL
XFMR,GEN. SURGE PROTECT., ETC.
2500 7300 41 A E ~AIN CONTROL & RELAY PNLS I LS 431,292.23
2610 7300 41 A E AUX SENERATORS-250KW I LS 103,175.35
DIESEL & 5KII PROPANE
2620 7300 41 A E STATION BATTERY-125V 1 LS 28,451.15
2630 7300 41 A E COMKUNICATION BATTERY I LS 21,944.65
2700 7300 41 A E SUPRV. CONTROL & DATA AQ. 1 LS 87,394.13
3000 7300 CUBICLES & APPURTENANCES
3200 7300 41 A E STATION SERVICE LOAD CTR 1 LS 174,788.25
3300 7300 41 A E MOTOR CONTROL CENTERS 6 EA 82,277.65
334 TOTAL ACCESSORY ELECTRICAL E9UIPMENT
JOt 14500
P6 9 OF11
PG110F13
TOTAL
COST
8,635,900
8,193,458
16,829,358
454,449
666,029
683,774
282,737
306,989
357,562
408,727
431,292
103,175
28,451
21,945
97,394
174,788
493666
4,500,978
TABLE 11.1-1
ORDER OF MAGNITUDE ESTIMATE
90 MW PLANT
FEASIBILITY STUDY COST ESTIMATE
CLIENT-ALASKA PONER AUTHORITY STONE & WEBSTER ENGINEERING CORPORATION
PROJECT-BRADLEY LAKE HYDROELECTRIC PROJECT ORDER OF MAGNITUDE ESTIMATE
90 MW PLANT
FEASIBILITY STUDY COST ESTIMATE
MAIN SUB CORP CC
STEM ACCT ACCT ST M L DESCRIPTION QUAN UN
336
336
MISCELLANEOUS PONER PLANT EQUIPKENT
1000 7400 AUXILIARY EGUIPHENT
1100 7400 35 A E UNWATERINS & LON LVL DRN
1300 7400 35 A E HISC SYSTEMS
1400 7400 35 A E COMPRESSED AIR SYSTEM
1500 7400 35 A E FIRE PROTECTION!INCL C02J
1600 7400 35 A E POWER HOUSE CRANE 150TN
2000 7400 35 •J 0 PERMANENT OPERATING EGUIP
3000 7400 35 A E COMMUNICATION SYS-LOCAL
3100 7400 35 A E KICRONAVE,SUPRV~TELEHETRY
9000 0 99 0 0 SPARE PARTS
1 LS
1 LS
1 LS
1 LS
1 E.oi
1 LS
1 LS
1 LS
1 LS
TOTAL HISC POWER PLANT EQUIPMENT
ROADS, BARSE FACILITY & AIR STRIP
1000 8100 ROADS-PERMANENT
1001 8100 96 A A AIR STRIP TO PH
1002 8100 96 A A PH TO DAM
1004 8100 96 A A CAMP TO MARTIN RIVER
3000 8200 96 A A DREDGED CHANNEL
3100 8200 96 A A BARBE FACILITY
4000 8102 96 A A AIR STRIP
1 LS
1 LS
1 LS
1 LS
1 LS
1 LS
TOTAL ROADS, BARSE FACILITY & AIR STRIP
TOTAL PRODUCTION PLANT
TRANSMISSION PLANT
350 1000 7800 0 0 0 LAND & LAND RISHTS-XMSSN 1 LS
DATE OF ESTIMATE 10/24 83
BID PRICE DATE -JULY 1 83
UNIT
COST
71,867.25
106,174.25
150,832.50
202,647.90
874,828.50
1,301,300.00
b2, 107.50
458,708.25
1,183,000.00
175,087.50
7,026,337.50
471,975.00
3, 560,043.00
1,144,410.00
1,096,000.00
11,130.00
JOt 14500
PS 10DF1!
PG 12 OF 13
TOTAL
COST
71,867
106,174
150,833
202,648
874,829
!, 301,300
62,108
458, 7•j8
1,183,000
4,411,466
175,088
7,026,338
471,975
3,560,043
1, 144,410
1,096,000
13,473,853
139,155,455
11, !30
'-------------TABLE 11.1-1
ORDER OF MAGNITUDE ESTIMATE
90 MW PLANT
FEASIBILITY STUDY COST ESTIMATE
CLIENT-ALASKA POWER AUTHORITY STONE & WEBSTER ENGINEERING CORPORATION DATE OF ESTIMATE 10i24 83
BID PRICE DATE -JULY 1 83
PROJECT-BRADLEY LAKE HYDROELECTRIC PROJECT ORDER OF MAGNITUDE ESTIMATE
KAIN SUB CORP CC
90 Mil PLANT
FEASIBILITY STUDY COST ESTIMATE
STEM ACCT ACCT ST K L DESCRIPTION QUAN UN
------- ----------------------------
352 SUBSTATION & SIIITCHING STATION STRUCTURES
1230 7600 99 A E FENCING 1 LS
2110 7600 5 AE SUBSTATION FILL 16500 CY
2115 71:00 2 AE RIP-RAP 700 CY
2116 ?bOO 5 A E CRUSHED ROCK 185 CY
2410 7600 99 A E IIISC. WORK 1 LS
3110 7600 11 A E CONCRETE 515 CY
3112 7600 19 A E REBAR 52TN
3113 7600 15 A E FORI'I5-STRAIGHT 10700 SF
3114 7600 22 A E EMBEDS 1800 LB
3115 7600 99 A E i1ISC. WORK 1 LS
4130 7600 99 A E DUCTLINES ~ MANHOLES 200 LF
4210 7600 20 A E STRUCTURAL STEEL-KISC 1 LS
5220 7600 41 A E POWER SUPPLY-CAMP & SERY. 1 LS
352 TOTAL SUBSTATION & SWITCHING STATION STRUCTURES
353 SUBSTATION & SWIT4HIN6 STATION EQUIPMENT
1210 7600 44 A E INSULATORS & BUSHINGS 1 LS
1220 7600 44 A E ALUMINUM TUBULAR BUSWORK 1300 Lf
!250 7600 44 A E GROUNDING SYSTEM LS
2110 7600 44 A E POWER XFMR-115KV-13.BKV 2 EA
2200 7600 44 A E POWER CIRCUIT BREAKERS 1 LS
2220 7600 44 A E DISCONNECT SWITCHES 1 LS
3210 7600 21 A E STRUCTURAL STEEL TOWERS 1 LS
TOTAL SUBSTATION ~ SWITCHING STATION EQUIPMENT
357 1000 7800 49 B T TRANSMISSION LINE 1 LS
TOTAL TRANSMISSION PLANT
UNIT
COST
27,120.00
8.50
106.22
22.06
101,022.00
269.53
3,175.30
29.95
5.93
28,984.50
124.30
73,450.00
830,781.65
13,503.50
62.49
INCLUDED IN ACCT I 334
319,196.75
323,914.50
101,671.75
120,062.50
7,599,182.20
TOTAL
COST
JOi !4500
P6 !10F11
PG 13 OF 13
27,120
140,210
74,354
4,081
101,022
138,807
165,116
320,412
10,679
28,985
24,860
73,450
830,782
1,939,876
13,504
81,236
638,394
323,915
101,672
120,063
1,278,781
7,599,!82
10,828,969
------------TABLE 11.1-1
COST ESTIMATES OF STUDY ALTERNATIVES
JOI 14500
8/19/83
PD 7/83
1190 POOL
1351'1N 901'1N 6011W
FERC ------ --------------------------------
ACCT DESCRIPTION PELTON FRANCIS PELTON FRANCIS PELTON FRANCIS
--------------------------------------------------------------------------------
(000) !000) !00.01 !000) !000) !000)
PRODUCTION PLANT
330 LAND & LAND RISHTS 0 0 0 0 0 0
331 POWER PLANT STRUCTURES 7,128 8,097 5,934 6,125 5,424 5,303
332 RESERVOIRS, DAMS & WATERWAYS 81,812 93,287 75,530 84,025 70,422 78,762
333 TURBINES & GENERATORS 16,656 14,814 13,921 11,920 11,337 8,932
334 ACCESSORY ELECTRICAL EQUIPMENT 3,837 3,837 3,055 3,055 2,817 2,817
335 MISC POWER PLANT EQUIPMENT 2,691 2, 721 2,661 2,551 2,551 2,441
336 ROADS, BARSE FAC. & AIRSTRIP 14,166 14,834 14,166 14,834 14,166 14,834
TOTAL PRODUCTION PLANT 126,290 137,590 115,267 122,510 106,717 113,089
TRANSMISSION PLANT
350 LAND & LAND RIGHTS 10 10 10 10 10 10
352 SWITCHYARD STRUCTURES 1,717 1,717 1, 717 1,717 1, 717 11717
353 SWITCHYARD EQUIPMENT 2,472 2,472 2,311 2,311 2,190 2,190
357 TRANSMISSION LINE 6,725 6,725' 6,725 6,725 6, 725 6,725
TOTAL TRANSMISSION PLANT 10,924 10,924 10,763 10,763 10,642 10,642
CONSTRUCTION DISTRIBUTABLES
CONSTRUCTION & PERMANENT CAMP 29,000 30,100 28,500 29,300 28,000 28,900
MOBILIZATION/DEMOBILIZATION 10,000 10,000 10,000 10,000 10,000 10,000
OTHER CONSTRUCTION ITEMS 11,800 11,800 11,800 11' 800 11,800 11, BOO
CONSTRUCTION 11ANA6EI'IENT 13,200 13,200 13,200 13,200 13,200 13,200
TOTAL CONSTR. DISTRIBUTABLES 64,000 65,100 63,500 64,300 63,000 63,900
TOTAL CONSTRUCTION COST 201,214 213,614 189,530 197,573 180,359 187,631
ALLOWANCE FOR INDETERMINATES 50,286 53,386 47,370 49,377 45,091 46,919
TOTAL CONSTR. COST & AFI 251,500 267,000 236,900 246,950 225,450 234,550
ENGINEERING ~ DESISN 28,500 28,500 28,500 28,500 28,500 28,500
TOTAL CONSTRUCTION ~ ENSR 280,000 295,500 265,400 275,450 253,950 263,050
OWNER'S COST 6,300 6,400 6,250 6,300 6,150 6,200
TOTAL PRESENT DAY ESTIMATE 286,300 301,900 271,650 281,750 260,100 269,250
ESCALATION NOT INCLUDED
IDC !-l ESCALATION 17,200 18,100 16,300 16,900 15,600 16,150
TOTAL PRESENT DAY ESTIMATE
INCLUDING (!DC-ESCALATION! 303,500 320,000 287,950 298,650 275,700 285,400
TABLE 11.2-1
HYDROELECTRIC PLANT O&M COSTS
BRADLEY LAKE HYDROELECTRIC PROJECT
ITEM
A. Plant Operators at $68,000 to provide daily
coverage and daily maintenance.
B. Plant production supervisor; assigned 100% of
th~ time at $78,400/year.
C. APA operations staff time at 100 hours/year.
D. Consulting services contracts for operation
.and maintenance.
E. Department of Energy fees.
F. Operating Utility administrative overhead costs.
G. APA Administrative overhead costs.
H. Minor operation contracts.
I. Annual replacement costs.
J. Miscellaneous services and supplies.
K. Travel (2 trips per week to Homer)
L. Property and machinery insurance
M. Casualty, Workman's Compensation, auto, marine
and airplane insurance.
Subtotal
20% Emergency Contingency
TOTAL
USE
ANNUAL
ESTIMATED
COST -1983
DOLLARS
$204,000
78,400
21,500
40,000
18,800
18,800
25,000
40,000
114,700
16,900
52,000
100,000
50,000
$780,100
156,000
$936,100
$940,000
'------------TABLE 11.2-2
TRANSMISSION LINE O&M COSTS
BRADLEY LAKE POWERHOUSE TO PROPOSED
HOMER ELECTRIC LINE
ITEM
A. Substation periodic inspection and testing.
B. Transmission line inspection and maintenance
including SCADA communication line rental charge.
C. Maintenance of SCADA System.
D. Annual relay and meter inspection, testing, and
calibration.
E. Right-of-way clearing, inspection and maintenance.
F. Transmission line loss insurance.
G. Operating Utility administrative overhead costs.
H. APA operations staff time at 200 hours.
I. APA administrative overhead costs.
J. APA accounting costs.
K. Annual replacement costs.
L. Miscellaneous supplies and services.
Subtotal
20% Emergency Contingency
TOTAL
USE
ANNUAL
ESTIMATED
COST -1983
DOLLARS
$ 34,200
133,300
8,100
19,000
10,200
10,000
13,000
9,100
8,700
2,200
7,700
4,400
$259,900
52,000
$311,900
$312,000
NOTE: Totals rounded up to the nearest $10,000; line items rounded up
to the nearest $100.
~----------TABLE 11.2-3
230 KV ANCHORAGE/SOLDOTNA
TRANSMISSION LINE
LAND & LAND RIGHTS
Allowance
OVERHEAD PORTION
Labor & Material
Clearing @ 15%
Engineering & Construction Management @ 12%
Owners Costs @ 8%
Contingency @ 15%
Subtotal
SUBMARINE CABLE
Labor & Material
Engineering & Construction Management @ 15%
Owners Costs @ 8%
Contingency @ 25%
Subtotal
SUBSTATIONS & SWITCHYARDS
Allowance
TOTAL COST
$ 1,280,000
$16,000,000
2,400,000
1,900,000
1,300,000
$21,600,000
3,240,000
$24,840,000
$28,500,000
4,275,000
2,280,000
35,055,000
8,764,000
$44,000,000
$ 5,000,000
$75,120,000
...__ ________ TABLE 11.2-4
ITEM
TRANSMISSION LINE O&M COSTS
ANCHORAGE/SOLDOTNA
230 KV TRANSMISSION LINE
A. Substation periodic inspection and testing.
B. Transmission line inspection and maintenance
including SCADA communication line rental charge.
C. Maintenance of SCADA System.
D. Annual relay and meter inspection, testing, and
calibration.
E. Right-of-way clearing, inspection and maintenance.
F. Transmission line loss insurance.
G. Operating Utility administrative overhead costs.
H. APA operations staff time at 200 hours.
I. APA administrative overhead costs.
J. APA accounting costs.
K. Annual replacement costs.
L. Miscellaneous supplies and services.
M. Sinking fund for submarine crossing conductor
replacement and inspection.
Subtotal
20% Emergency Contingency
TOTAL
USE
ANNUAL
ESTIMATED
COST -1983
DOLLARS
$ 34,200
179,300
8,100
19,000
10,200
10,000
13,.000
9,100
8,700
2,200
7,700
4,400
479,300
$785,200
157,000
$942,200
$943,000
NOTE: Totals rounded up to the nearest $10,000; line items rounded up
to the nearest $100.
'----------TABLE 11.2-5
12
POWER STUDIES
AND
ECONOMIC
EVALUATIONS
12. POWER STUDIES AND ECONOMIC EVALUATION
12. 1 INTRODUCTION
The objectives of the power study and economic evaluation of the Bradley
Lake Project are to identify the economic advantages or disadvantages of
the Project for the Railbelt and to select the plant capacity. The
analyses were performed using data from several sources, including the FY83
Power Authority economic guidelines, previous Bradley Lake studies
performed by other organizations, and the Harza-Ebasco Susitna FERC
application dated July 1983.
The primary tool used in this evaluation was a computer program developed
by SWEC and the Massachusetts Institute of Technology for the Electric
Power Research Institute. This program, Electric Generation Expansion
Analysis System (EGEAS), provides the capability to automatically develop
electric generation expansion plans based on the characteristics and costs
of alternative generation sources, existing unit characteristics and
retirement dates, and load data. A mathematical optimization method
(dynamic programming) is used to consider all feasible plans for installing
new generation capacity to meet the load requirements. The total present
worth cost for each plan is determined, with the lowest cost plan being the
economically preferred plan. A detailed description of EGEAS is provided
in Reference 1.
Several variations in the Railbelt generation expansion plans were
evaluated during the Bradley Lake power study. Using EGEAS, separate
analyses were performed for generation expansion plans using thermal power
plants (gas-fired combined cycle, gas-fired combustion turbine, and coal-
fired steam turbine), Susitna combined with thermal plants, and the Bradley
Lake Project (with and without Susitna) for the three proposed project
capacities of 60 MW, 90 MW, and 135 MW. Also, sensitivity studies were
performed to determine the effect of variations in the Railbelt load growth
rate on the economic performance of the Bradley Lake Project.
12-1
In addition, EGEAS has a unique capability to perform a two-area analysis
which models reserve sharing and economy interchange between two connected
utility systems. This capability was used in .the Bradley Lake study to
evaluate the effect of transmission limitations on the present worth costs
of the optimized expansion plans associated with the Kenai Peninsula. The
current transmission tie between the Kenai Peninsula and Anchorage is a 115
kV transmission line. The addition of a 230 kV line with its substations
and switching stations, between Anchorage and Soldotna, would cost about
$75 million (Table 11.2-4). Therefore, an assessment of the differences in
transmission costs associated with generation expansion plans including and
not including the Bradley Lake Project is essential to the power study.
This was accomplished using the EGEAS two-area analysis capability.
The primary data source for the study was the recent Harza-Ebasco Susitna
FERC application dated July 1983 (Reference 2). Information derived from
this document included items such as fuel prices and escalation rates, new
generation alternatives, Susitna characteristics, and existing generation
units in the Railbelt. The Railbelt electric load forecast used in the
Bradley Lake study was also derived from this source. The load forecast,
titled "Sherman H. Clark Associates NSD Case," has an average annual com-
pounded load growth rate of about 2.8 percent for the period 1983 through
2007.
12. 2 METHODOLOGY
The Bradley Lake and Susitna projects have been the subject of previous
reports and projections for the power requirements of the Railbelt area of
Alaska. Since the Bradley Lake Project is small compared to the total
Railbelt load, the relative economics of Bradley Lake can become lost in
the much larger present worth costs of the entire Railbelt. The objective
of this power study was to clearly and precisely define the economic
advantages or disadvantages of the Bradley Lake Project.
A two-phased approach was used, with one phase based on life cycle cost
comparisons of Bradley Lake with other alternative generation sources and
one based on optimum expansion plans developed for the Railbelt using EGEAS.
12-2
Although the Bradley Lake Project will impact the entire Railbelt Area, its
greatest impact will be in the Kenai Peninsula. Most of the investment and
annual expenses incurred outside the Kenai Peninsula will be common to
generation plans with and without Bradley Lake. However, the small
proportion that is not common is significant in the determination of
Bradley Lake size and overall economics. In order to capture the essential
variations in total cost to the Railbelt due to alternative Bradley Lake
options, a two-area analysis was made in which the total present worth of
annual expenses and investment were segregated into a Kenai area and a
Railbelt-without-Kenai area. For the purposes of determining the benefits
of the Bradley Lake Project, incremental differences in the costs
associated with the Railbeltwithout-Kenai were combined with the total
Kenai costs. This approach prevents the cost of alternatives with respect
to Bradley Lake being lost in a one-area Railbelt analysis. It should be
emphasized that the objective was to reduce total Railbelt costs to a
minimum and not to limit the study to the Kenai Peninsula.
The two-area analysis was also required to assess transmission requirements
between the Kenai Peninsula and the Anchorage systems. The transmission
requirements were a significant factor in the evaluation of the Bradley
Lake Project. The computer program EGEAS was selected specifically for its
unique ability to perform a two-area analysis and optimize the whole
Railbelt area while maintaining the identity of the Kenai Peninsula, and to
include the effects of transmission limitations on the overall
optimization. These concepts will be expanded in the following sections.
12.2 .1 Electric Generation Expansion Analysis System
Electric Generation Expansion Analysis System (EGEAS) is a computer program
that was developed jointly by SWEC and the Massachusetts Institute of
Technology for the Electric Power Research Institute and represents
state-of-the-art methodology. Representatives of 15 electric utilities
were intimately involved in the development and testing of the program. It
incorporates a number of optimization methods and generation dispatch
algorithms within one modular set of programs using one common data base.
A short description is given here of those particular features that were
used for this project.
12-3
In EGEAS, each plan is evaluated in terms of present worth of all expenses
incurred over the study period including fuel cost, operation and
maintenance cost, and investment. Investment in a particular unit can be
considered to be a one-time expense at the time of unit installation, or an
annual cost of interest and depreciation may be used to represent the cost
of capital for each year of the economic life of the unit.
Expansion plans may be developed for 20 years during which system load will
grow as specified. An end-effects period can also be used to extend the
economic analysis for any number of years. During the end-effects period,
the load is assumed to stop growing in the 20th year. New generation
installed during the first 20 years will be retired at the end of its
economic life and replaced in-kind during the extension period. Fuel costs
can be escalated in the end-effects period at a rate different than that
used in the expansion period. The program develops the preferred plan
based on minimum present worth of costs over both the expansion period and
the end-effects period.
Generation expansion plans are developed automatically and optimized by
EGEAS based on characteristics and costs of alternative generation sources,
existing unit characteristics and retirement dates, and load data. A
mathematical optimization method (dynamic programming) is used to consider
all feasible plans for installing generating capacity to meet the new
generation requirement. Several thousand plans may be analyzed and the
one-hundred least cost plans are retained for printout. The plans are
printed in order of least cost. The ability to retain and list suboptimum
plans allows the user to consider other plans that may be better for the
short term (20 years) as compared to the long term (50 years), particularly
if the long term advantages of the 11 optimum 11 plan are relatively small
compared to the short term advantages of another plan.
Two areas, 11 A11 and 11 B, 11 can be modeled by EGEAS. In this formulation, area
11 A11 is optimized for a fixed expansion plan in 11 B. 11 Stated another way, a
small system connected to a large system by limited transmission capacity
may be optimized without involving the whole pool in the optimization
process, but including the reserve sharing and economy interchange provided
by the large system up to the limit of the transmission system.
12-4
As a practical matter, EGEAS provides a very economical and yet accurate
method for performing the Bradley Lake studies. Even though probabilistic
production cost simulation using conventional methods (Booth-Baleriaux
convolution) is relatively efficient compared to hour-by-hour simulation, a
new method (the Method of Moments) devised for EGEAS is an
order-of-magnitude faster than Booth-Baleriaux and produces identical
results. Furthermore, because of its water storage characteristics, the
Bradley Lake Project lends itself to an annual load duration curve analysis
rather than monthly or a more frequent sub-yearly analysis. The slight loss
in accuracy in representing unit maintenance by using an annual load
duration curve is more than offset by the ability of the program to perform
many studies at relatively low cost with a true system optimization in the
process. Maintenance is modeled by derating units by an amount equal to
the expected time on maintenance.
Two separate economic analyses were performed for the power study as
follows:
A. Life Cycle Cost
Bradley Lake was compared unit-to-unit with each feasible power supply
alternative in terms of levelized energy costs for a range of capacity
factors.
B. Railbelt Generation Expansion Optimization
Railbelt power supply scenarios were developed and optimized by EGEAS from
the feasible energy supply alternatives (Bradley Lake, Susitna, combined
cycle, combustion turbines, and coal-fired steam plants) and economic
evaluations were performed on a net present worth cost basis.
12.2. 2 Life Cycle Cost
In general, there is
supply the system load.
a need for several different types of capacity to
Base load, intermediate, and peaking capacity is
one broad generalization. For fossil fueled plants, base load capacity is
characterized by high investment and low energy cost and is expected to run
12-5
at high capacity factors. Intermediate load capacity has lower investment
and higher production cost than base load and may be expected to follow
morning and evening loads on the system. Peaking capacity usually has
lower investment and higher fuel costs than the other two types and tends
to be used only during system peak load periods and, as a result, is
characterized by low capacity factors. Host systems need all three types
and each will be selected as an economic choice over a particular range of
capacity factors.
A life cycle bus -bar cost analysis is one in which the cost of energy in
mills/kWh, levelized over the life of the unit, is computed for various
assumed capacity factors. The two major components of this analysis are
investment and operating expense. Typical life cycle cost
curves are shown in Figure 12.2-1.
Each pair of life cycle cost curves cross at a particular capacity factor
which may be designated as the break-even capacity factor. The lower
investment/higher fuel cost alternatives will be the economic choice at
capacity factors lower than break-even and the other unit will be more
economical at all other capacity factors. For instance, it can be seen
from Figure 12.2-1 that peaking capacity is more economical than other
sources for capacity factors less than about 10 percent, intermediate
capacity has an economic range of 10 percent to 40 percent, and base load
units are economical at capacity factors higher than 40 percent.
The life cycle analysis was useful for several purposes. First, it was
used to determine which fossil-fueled alternative would be the most
economical source within the Bradley Lake capacity factor range and the
difference in bus-bar cost between this alternative and Bradley Lake.
Also, the life cycle analysis was used to screen fossil-fueled alternatives
to be included in the EGEAS optimization (an alternative that is not
economical at any capacity factor in the life cycle analysis will not be
selected for installation by EGEAS).
12-6
12.2.3 Generation Expansion Optimization with EGEAS
A meaningful study of the Bradley Lake Project must take into account the
relative isolation of the Kenai Peninsula from the remainder of the
Railbelt Area, from the standpoint of both supplying the Kenai load and
distributing Bradley Lake generation.
Currently, the transmission tie between Kenai and Anchorage is limited to
approximately 40 MW and consists of one 115 kV transmission line. Single
contingency planning requires that the system continue to operate with the
loss of this circuit. This is currently accomplished by installing enough
generation in the peninsula to supply the load, with the tie used only as
back-up. When Bradley Lake comes on line in 1988, and depending on the
capacity installed, this transmission capacity may have to be increased to
allow full utilization of the Bradley Lake generation to the Railbelt. In
the alternatives that do not include Bradley Lake, the tie capacity may
also have to be increased to allow the load in the Peninsula to be supplied
from other Railbelt sources or to allow economy interchange. Therefore,
the inst~llation of new transmission circuits coincident with the
installation of the Bradley Lake Project may represent early installation
of circuits that will be needed at a later date in any case. An accurate
assessment of the differences in transmission costs associated with plans
including and not including Bradley Lake was essential to this analysis.
Separate analyses were performed using the optimization program, EGEAS, as
follows:
I. Without Bradley Lake
a. without Susitna
b. with Susitna
II. Bradley Lake at 60MW
a. without Susitna
b. with Susitna
III. Bradley Lake at 90MW
a. without Susitna
b. with Susitna
12-7
IV. Bradley Lake at 135MW
a. without Susitna
b. with Susitna
The following sequence was used for each of these analyses:
Stage 1, (Figure 12.2-2)
A single-area optimization of the total Railbelt was made. In this
analysis, the "existing" capacity included the thermal generation in
service in 1983 plus Bradley Lake installed in 1988 and the two stages of
Susitna installed in 1993 and 2002 in those cases that include the
respective hydroelectric projects. The existing thermal units and new
thermal units were retired at the appropriate year in the study. The
Railbelt generating reserve was maintained at a minimum of 30 percent of
the peak load requirement.
Stage 2, (Figure 12.2-2)
The new generation installed in the Stage 1 optimization was assigned to
either area "A" or area "B" as appropriate and the present worth of annual
costs segregated into these two subdivisions (the total will equal the
Stage 1 optimum cost). At this stage, unlimited tie capacity between the
Kenai Peninsula (Area "A") and the Railbelt-without-Kenai (Area "B") was
assumed and EGEAS was rerun. The one important additional piece of
information that was developed at Stage 2 that was not available from the
single area analysis of Stage 1 was the flow of energy over the ties
between "A" and "B." From this information, it was possible to estimate
the transmission ties required to provide "unlimited" tie capacity (the
ties are unlimited in the sense that they do not impede economy interchange
or reserve sharing).
A new total present worth cost was developed at Stage 2 that included the
cost of the new transmission lines (if any) between the two areas.
12-8
Stage 3 (Figure 12.2-2)
If appreciable tie capacity is required in Stage 2, it may be possible to
develop a more optimum plan by reducing the amount of transmission capacity
between areas "A" and "B". The offsetting penalty for reducing
transmission capacity and cost will come in two forms: more capacity in
Kenai and higher fuel cost due to limitation in economy interchange. As
demonstrated in Figure 12.2-2, some capacity installed in area "A" may have
to be transferred to the Kenai Peninsula if the transmission capacity is
reduced. This will usually require substituting capacity available for
installation on the peninsula for a different type of capacity available
only in area "B" (i.e., coal-fired capacity) or in some cases the same type
of capacity may be transferred but at a higher fuel cost or smaller unit
size.
Economy interchange takes place mainly during off-peak periods when lower
cost energy in one area is substituted for high cost energy in another
area. A reduction in tie capacity will limit the amount of economy energy
transfer and thus cause higher fuel cost. An EGEAS two-area analysis at
Stage 3 correctly models these two effects of limited ties on the overall
cost to both areas.
12.2. 4 Bradley Lake and Susitna Energy Dispatch
EGEAS uses a probabilistic generation dispatch method based on an annual
load duration curve. Hydroelectric plants such as Bradley Lake and Susitna
are modeled as "limited energy sources" and are used by the model to
provide as much peak shaving as possible within the operational constraints
imposed by each project. The effective storage available for daily load
cycling at Bradley Lake is large enough to allow maximum peak shaving
within the energy constraint.
Since all three proposed Bradley Lake unit sizes produce essentially the
same total energy, the evaluation of un'it size pivots on two factors:
12-9
1. transmission requirements for each size to allow economy interchange
and reserve sharing between the Kenai Peninsula and the rest of the
Rail be 1 t, and
2. advantages of higher capacity replacement value and the displacement of
higher cost fuel by the larger generation as compared to the
incremental investment of the larger units.
Figure 12.2-3 demonstrates the manner in which the three different sized
Bradley Lake units were modeled by EGEAS. The larger units operate at a
lower capacity factor than the smaller alternatives and are loaded "higher"
on the load duration curve. The hydroelectric units are "loaded" by EGEAS
by finding the proper location on the load duration curve that will use all
the energy available while running at maximum output as much as possible.
12.3 ECONOMIC PARAMETERS AND DATA
Numerous types of data are required in order to model a Railbelt power
supply plan with EGEAS and perform the economic analysis. These data
include items such as the Railbelt load growth projection, fuel prices and
escalation rates, costs and operating characteristics of existing and
future generation units, transmission requirements, and economic parameters.
Several sources of data were used in the Bradley Lake evaluations. As a
part of the Susitna Hydroelectric Project evaluation, Harza-Ebasco compiled
a significant part of the data required. In addition, the Chugach Electric
Association has operating and cost data available for the existing
generation units in their system. These data sources were
supplemented, as needed, by the data contained in reports from previous
Railbelt power supply studies.
The parameters used in the economic evaluations are summarized in Table
12.3-1. The majority of these parameters are consistent with the FY83
Power Authority economic guidelines (Reference 3). However, certain
parameters, such as fuel escalation rates and the period of time over which
fuel escalation occurs, were consistent with the values assumed by
Harza-Ebasco in their projection of the Railbelt load growth.
12-10
12.3. 1 Reference Case Railbelt Load Projection
Detailed electric load growth projection studies have been recently
completed in support of the Susitna FERC application. The results of these
studies are reported in Exhibit "B" of the Susitna FERC application dated
July 1983 (Reference 2). In accordance with agreements reached with the
Power Authority, the Bradley Lake power study was based on a load growth
projection resulting from these studies titled "Sherman H. Clark Associates
No-Supply-Disruption Case." This projection, referred to as the ''Reference
Case" by Harza-Ebasco, was in the middle range of the forecasts evaluated
and was used as the base case in the Susitna power study. A brief overview
of the analysis performed by Harza-Ebasco will be provided here.
One of the primary factors in the Susitna analysis which affected the load
projection was the assumed world oil price. Several oil price projections
were considered by Harza-Ebasco, including the Sherman H. Clark
projections. The oil price affected the need for Railbelt electric power
in four ways:
1. petroleum revenues available to the State of Alaska are a direct
function of the market price of petroleum;
2. the price of electricity to the consumer is impacted since most
Railbelt power is generated from fossil fuels;
3. the ability to economically substitute different fuels for power
generation is dependent on the price of oil;
4. the level of oil exploration and development in Alaska will vary with
the world oil price.
Harza-Ebasco used four interrelated computer models to project the future
Railbelt load growth for each oil price projection. The four models
included the following:
12-11
1. PETREV --Operated by the Alaska Department of Revenue. This model
uses a probability distribution of possible values that affect Alaska
petroleum revenues to predict a range of royalties and production taxes.
2. ~fAP Developed by the Institute of Social and Economic Research
(ISER), University of Alaska. The MAP (Man-in-the-Arctic Program) is
an economic model that simulates the behavior of the Alaska economy and
population growth for each of twenty regions of the state.
3. RED --Developed by ISER and modified by Battelle Pacific Northwest
Laboratories. The RED (Railbelt Electricity Demand) model is a
simulation model which forecasts annual electricity consumption for
each end-use sector in the Anchorage-Cook Inlet and Fairbanks-Tanana
Valley load centers.
4. OGP Developed by General Electric Company. OGP (Optimized
Generation Planning) is a model used to produce generation expansion
plans based on system reliability, operating, and investment costs.
With these models, Railbel t load growth projections for several oil price
scenarios were produced for the Susitna FERC application. A complete
description of the procedure is provided in Exhibit "B" of the Susitna FERC
application dated July 1983 (Reference 2).
A summary of the input and output data for the Reference Case is presented
in Table 12.3-2. During the 28 years included in this scenario, the net
Railbelt electric energy demand is projected to increase 109 percent from
2, 803 GWH to 5, 858 GWH, while the peak demand increases 110 percent from
579 MW to 1,217 MW. This load projection is shown in Table 12.3-3 for each
year in the period 1983-2010. The Kenai Peninsula load is included in the
Anchorage-Cook Inlet category. Table 12.3-4 shows the annual change in the
Railbelt load.
In order to perform a two-area analysis with EGEAS and identify the impact
of Bradley Lake on the Kenai Peninsula, a separate load projection for the
Kenai Peninsula was required. For this purpose, the Anchorage-Cook Inlet
load from the Reference Case in Table 12.3-3 was separated into Anchorage
12-12
area and Kenai Peninsula components. The historical load in each region
was the basis used to separate the projection. The historical
Anchorage-Cook Inlet utility peak demand and energy requirements are shown
in Tables 12.3-5 and 12.3-6, respectively. In both cases, the portion of
the total Anchorage-Cook Inlet load occurring in the Kenai Peninsula varied
from 14 to 16 percent during recent years. Based on this information, it
was assumed that the Kenai Peninsula would represent 15 percent of the
Anchorage-Cook Inlet load during the 1983 through 2007 time frame of the
Bradley Lake power study. The resulting load projections for the Anchorage
area and
Kenai Peninsula are shown in Table 12.3-7. This projection represents a
conservative estimate of the load portion occurring in the Kenai Peninsula
since other recent projections (such as Reference 4) indicate that the
Kenai Peninsula may grow at a somewhat faster rate than the rest of the
Railbelt. Assuming a slightly higher load growth for the Kenai Peninsula
would have little effect on the study, but would tend to favor the Bradley
Lake Project.
12.3.2 Reference Case Fuel Price Projections
As part of the Susitna FERC application, Harza-Ebasco also performed
studies to determine the future availability and price of fossil fuels in
the Railbelt. Projections for natural gas, coal, and distillate oil were
made so that Railbelt generation expansion plans involving alternatives to
Susitna (thermal plants) could be developed and evaluated on a life cycle
cost basis. The fuel price projections developed for the Reference Case
were used in the Bradley Lake power study to evaluate hydroelectric
alternatives. A complete description of the fuels pricing studies is
included in Exhibit "D" Appendix D-1, of the July 1983 Susitna FERC
application (Reference 2).
The fuel prices used in the Bradley Lake studies are shown in Table
12.3-8. The following major assumptions relate to these price projections:
1. The escalation in the price of natural gas will vary in the same manner
as that of oil.
12-13
2. Although proven Cook Inlet natural gas reserves will be exhausted
around the year 2000, it was assumed that sufficient additional
reserves will be discovered to meet all future demand during the study
period. No supply restrictions were imposed in any portion of the
Bradley Lake power study.
3. The Beluga coal field, presently undeveloped, will be opened for
development and coal will be exported to Japan.
12.3.3 Existing Railbelt Generation System
The Railbelt electric power market contains two primary load centers
(Anchorage-Cook Inlet and Fairbanks-Tanana Valley) and is served by several
utilities and other suppliers. The 1982 Railbel t generating capacity is
shown in Table 12.3-9. For the Bradley Lake power study, the market was
considered to be interconnected with the addition of the transmission tie
between Anchorage and Fairbanks (currently under construction by the Alaska
Power Authority). The existing ll5 kV transmission tie between Anchorage
and the Kenai Peninsula was subject to the capacity limitations discussed
previously.
For the generation expansion plans developed by EGEAS, the cost of new
transmission lines was included as required. The natural gas-fired
combustion turbines and combined cycle plants had no additional
transmission cost since their siting flexibility allowed them to be located
near the load centers. The coal plants, however, required transmission
from the plant site to the nearest load center, and this cost was included
accordingly. The Bradley Lake plants included the cost of transmission
from the plant to the existing transmission line in all cases plus the cost
of a new 230 kV line between Anchorage and Soldotna when required.
The existing Railbelt generating plants were included in the generation
expansion plans developed by EGEAS. These existing plants were dispatched
by EGEAS along with new generation plants to arrive at an optimum
generation expansion plan for the total Bradley Lake power study period.
12-14
All plants, both existing and new, were retired in accordance with the
equipment lifetimes shown in Table 12.3-1. A complete listing of the
existing generating plants in the Railbelt is shown in Table 12.3-10.
In addition to Bradley Lake benefits for capacity and energy, an allowance
was also made for the ability of the Project to provide spinning reserve.
As a conservative estimate of the capability, spinning reserve benefit was
applied for the Kenai Peninsula load only. This was accomplished with EGEAS
by forcing the CEA Bernice #3 and /ft4 gas-fired combustion turbine units
(see Table 12. 3-10) to operate continuously at no less than 20 percent
capacity in those scenarios without Bradley Lake. The heat rate of these
units at this reduced capacity was approximately 28,000 BTU/kWh, with the
heat rates decreasing as the output approached full load to the values
shown in Table 12.3-10. In the EGEAS simulations, these two units were
dispatched in an optimum manner except that they never dropped below 20
percent of their full output. Thus, the scenarios without Bradley Lake had
the portion of the capacity of these plants in excess of their current
operating level available as spinning reserve. In the cases where the
Bradley Lake Project was included, the two Bernice units were dispatched by
EGEAS without a requirement to continuously operate at any level, and
Bradley Lake provided spinning reserve for the Kenai Peninsula.
12.3.4 Future Railbelt Electric Generation Alternatives
The development of Railbelt generation expansion plans with EGEAS required
performance and cost specifications for the feasible Railbelt electric
generation alternatives. A screening of alternatives was not performed for
the Bradley Lake power study since the performance and cost of possible
choices were evaluated in previous Rail belt studies. The technical and
economic feasibility of numerous options was evaluated by Battelle Pacific
Northwest Laboratories in 1982 (Reference 5). Battelle evaluated a wide
variety of electric generation options, taking into account the unique
characteristics of the Railbelt. The candidate resources included coal,
natural gas, petroleum, peat, municipal refuse, wood waste, geothermal,
hydroelectric, tidal power, wind, solar, and uranium. The most readily
adaptable thermal alternatives for the Railbelt included coal, natural gas,
12-15
and oil resources. Thus, the thermal generation alternatives in the
Bradley Lake power study included coal-fired steam, gas-fired combustion
turbines, and gas -fired combined cycle plants. These thermal options are
described in detail in Exhibit "D" of the Susitna FERC application of July
1983 (Reference 2). A summary of the thermal generation plant parameters
used in EGEAS is shown in Table 12.3-11.
The hydroelectric plant parameters and costs used in the Bradley Lake power
study are summarized in Tables 12.3-12 through 12.3-14. Tab 1 e 12 . 3 -12
shows the Bradley Lake Project parameters developed by S\<lEC and the Susitna
Project parameters obtained from the Susitna FERC application of July
1983. The capital and fixed operating and maintenance costs for the
Bradley Lake options and Susitna are shown in Tables 12.3-13 and 12.3-14,
respectively.
12.3.5 Sensitivity Studies
The Railbelt load and price projections are dependent on numerous factors
which involve various degrees of uncertainty (such as future world oil
prices). Sensitivity studies were performed with EGEAS to determine the
effect of load and fuel price variations on the economic performance of the
Bradley Lake Project. In addition to the Reference Case (Sherman H. Clark
NSD) Railbelt load growth and fuel price projections, two other cases were
examined in the Bradley Lake power study. These are:
1. A Railbelt no-growth case where the 1983 load (2,803 GWH at a peak of
579 MW, net) was assumed to remain constant for the duration of the
power study. The fossil fuel price projections were the same as in the
Reference Case.
2. A Railbelt load growth and fossil fuel price projection titled "DOR 50%
Case." This projection, developed in July 1983, was supplied to SWEC
by the Power Authority. The case was studied with EGEAS for the base
case (new thermal plants only) and the 90 MW Bradley Lake option.
The load growth and fossil fuel projections for the DOR 50% case are shown
in Tables 12.3-15 and 12.3-16. For the period 1983 to 2010, the Railbelt
load shown in Table 12.3-15 grows at an average compound rate of about 2.3
12-16
percent per year. The fossil fuel price projections in Table 12.3-16
indicate that coal prices remain constant, the turbine oil price decreases
by about 25 percent between 1983 and 2000 and then remains constant, and
the natural gas price decreases by about 11 percent between 1983 and 2000
and then also remains constant. For comparison, the levelized fuel costs
for natural gas and coal are shown in Table 12.3-17 for the Reference Case
and DOR 50% Case projections.
12. 4 RESULTS
The evaluations indicate that the Bradley Lake Project is economically
beneficial for the Railbelt at any of the three proposed plant capacities,
both with and without the presence of Susitna. Significant life-cycle
savings result by using Bradley Lake in place of thermal generation
alternatives (gas-fired combined cycle, gas-fired combustion turbines, and
coal-fired steam plants). The capacity for Bradley Lake is dependent on
and sensitive to the projected load growth rate for the Railbelt. The
differences in present worth cost between the three proposed capacities for
alternative load growth projections are relatively small. Of the three
capacities evaluated, the 90 MW Bradley Lake Project is the economically
preferable choice at the reference load growth rate of an average 2. 8
percent per year as adopted in this study. It is also economically
beneficial under the DOR 50% Case. For an assumed load growth rate of zero
percent per year, the 60 MW plant is the preferred choice. However, since
the 90 MW Bradley Lake Project is the least sensitive to load growth
variations, it appears to be the most favorable plant capacity. The
Bradley Lake Project options are very close in terms of annual average
energy, with only a 3 to 5 percent difference between successively larger
installations.
EGEAS was used to develop optimized Railbelt generation expansion plans for
the various scenarios discussed in the previous sections. For each
generation expansion plan, EGEAS created an extensive printout of results
which was unrealistically long to attempt to reproduce in this report.
Thus, the power study results are summarized in the following sections with
12-17
certain pages extracted from the EGEAS output data primarily for the base
case (new thermal plants only) and the recommended Bradley Lake capacity of
90 MW.
12.4. 1 Reference Case
This section presents the results of the Bradley Lake power study for the
Reference Case load and fuel price projections (Sherman H. Clark NSD).
Tables 12.4-1 through 12.4-14 summarize the results of the study. Present
worth costs, in 1983 dollars, are shown for all cases in terms of total
Railbelt cost and the portion of the cost attributable to the Kenai
Peninsula alone. The present worth savings due to the Bradley Lake Project
(base case cost minus Bradley Lake cost) are also shown along with the
fraction of the base case cost which these savings represent.
Table 12.4-1 shows the present worth costs for the plans consisting of
alternatives to Bradley Lake. The thermal plant base case with the lowest
present worth cost includes the Anchorage-Soldotna 230 kV transmission line
and has a value of $5,832 million. This base case is compared to the
"Bradley Lake without Susitna" plans. The "Bradley Lake with Susitna"
plans are compared to a base case including Susitna and thermal plants
which has a total present worth cost of $5,724 million.
The "Bradley Lake without Susitna" cases are shown in Tables 12.4-2 and
12.4-3 for the total Railbelt and the Kenai Peninsula, respectively. For
all three Bradley Lake capacities, significant savings are realized when
compared to the base case. For the total Railbelt plans, the savings range
from 5.1 to 6.3 percent of the base case. However, when the present worth
costs are separated for the Kenai Peninsula using the EGEAS two-area
evaluation, the Bradley Lake savings range from 23.1 to 33.7 percent of the
Kenai Peninsula base case cost. the 90 MW Bradley Lake Project shows the
largest present worth savings for the total Railbelt and the Kenai
Peninsula and is the optimum choice. The incremental cost for increasing
the plant capacity to 135 MW (including the additional plant capital cost
plus the Anchorage-Soldotna 230 kV transmission line) is not justified
since the total savings are less than for the 90 MW plant.
12-18
Additional information for the 11 Bradley Lake without Susitna'' cases is
presented in Tables 12.4-4 to 12.4-11. The new generation capacity
projected by EGEAS for installation in the Railbelt is shown in Tables
12.4-4 to 12.4-7 for the base case, 60 MW Bradley Lake, 90 MW Bradley Lake,
and 135 MW Bradley Lake, respectively. These Tables show that the optimum
expansion plans, with and without the presence of Bradley Lake, include the
addition of natural gas-fired combined cycle units in the years prior to
2000, with coal-fired steam plants added in the successive years through
2007. Natural gas -fired combustion turbines were also added in the year
2000 timeframe.
Tables 12.4-8 and 12.4-9 illustrate the energy generation and cost by fuel
class for the ''Bradley Lake without Susitna11 case. The energy generated
and total fuel cost for each year in the 1988 through 2007 period are shown
for natural gas, coal, oil (existing plants only --no new oil-fired plants
were added), and existing hydroelectric.
Tables 12.4-10 and 12.4-11 show the Reference Case expansion plan summary
for base case and 90 MW Bradley Lake cases. These summary pages, copied
from the EGEAS output, show the annual Railbel t load, capacity installed
and retired, reserve percent, capital cost of the new units, production
cost (fuel cost plus variable O&M), fixed O&M cost for the new units, total
and cumulative annual cost, and total and cumulative present worth cost.
Lastly, life cycle levelized cost curves were produced for the Reference
Case as discussed in earlier sections and are presented in Figure 12.4-1.
These curves illustrate the relative levelized energy costs of the Railbelt
generation alternatives taking into account capital costs, variable O&M
costs, fixed O&M costs, and fuel costs. Other benefits which accrue to the
Bradley Lake Project, such as spinning reserve, are not reflected on these
curves as in the EGEAS evaluations. On the bas is of levelized bus -bar
energy cost, Figure 12.4-1 shows that the three Bradley Lake capacities are
the least cost alternatives compared to the thermal plants at the same
capacity factor. The levelized energy cost for the 90 MW Bradley Lake
Plant is about 34 percent lower than for the natural gas -fired combined
cycle plant.
12-19
Tables 12.4-12 and 12.4-13 present the results for the "Bradley Lake with
Susitna" plans. As expected, the present worth savings for the three
Bradley Lake capacities are less due to the presence of the large Susitna
plants. However, savings still result for all three plants and range from
1. 2 to 3. 1 percent for the total Railbel t base case and from 7. 4 to 22.4
percent for the Kenai Peninsula base case. In these plans, the present
worth savings are essentially equal for the 60 and 90 MW Bradley Lake
capacities. The 135 MW plant results in less savings, indicating that the
economically preferable Bradley Lake plant capacity for the cases including
Susitna should be either 60 MW or 90 MW.
The "Bradley Lake with Susitna" plans did not require the addition of any
new thermal generation plants after the Bradley Lake on-line date of 1988.
In the succeeding years, the existing generation plants with Bradley Lake
Project and Susitna (Watana in 1993 and Devil Canyon in 2002) were
sufficient to meet the Railbelt Reference Case load with adequate
reserves. The expansion plan summary from EGEAS for the 90 MW "Bradley
Lake Project with Susitna" case is shown in Table 12.4-14.
12.4. 2 Sensitivity Studies
It is recognized that uncertainty exists in the projections for future
Railbelt electric loads, primarily because of the volatile nature of world
oil prices. If the Railbelt load growth were to exceed the Reference Case
projection, then Bradley Lake would continue to be an economically
beneficial option for the Railbel t. However, in order to determine the
impact on Bradley Lake if the Railbelt growth is less than the Reference
Case, two other scenarios were examined with EGEAS.
A load growth rate of zero percent per year was assumed to determine the
economic performance of Bradley Lake under a Railbel t no-growth scenario.
The 1983 Railbelt load was assumed constant for the duration of the power
study. The fossil fuel prices were the same as in the Reference Case. The
results of the sensitivity study are shown in Table 12.4-15. The present
worth costs indicate that Bradley Lake remains competitive with a thermal
plant base case for all three Bradley Lake capacities. For the zero load
growth rate, the 60 HW Bradley Lake Project provides the largest net
12-20
benefit since the 230 kV Anchorage-Soldotna transmission line was required
for the 90 and 135 MW cases to allow economy interchange and reserve
sharing between the Kenai Peninsula and Anchorage. The cost for this line
was greater than any additional savings due to either the 90 or 135 MW
capacities.
Tables 12.4-16 and 12.4-17 show the generation installation schedule
developed by EGEAS for the base case and 90 MW Bradley Project under zero
percent load growth. The generation by fuel class for the 1988 through
2007 study period is shown for these two cases in Tables 12.4-18 and
12.4-19. Lastly, the summaries of annual and present worth costs are shown
in Tables 12.4-20 and 12.4-21 for the expansion plan with new thermal
plants only and the plan including the 90 MW Bradley Lake Project.
The second sensitivity study, performed at the request of the Alaska Power
Authority, used the July 1983 "DOR 50% Case" load growth and fuel price
projections which were described previous~y. Only two expansion plans were
generated with EGEAS for this study: A base case (new thermal plants only)
and a case with the 90MW Bradley Lake Project plus thermal plants. The
results are as follows:
Present Worth Cost ---Millions 1983 Dollars
Thermal Plants*
90 MW Bradley Lake
+ Thermal Plants
3461
3305
>':Includes 230kV Anchorage-Soldotna transmission line.
The installation of the 90 MW Bradley Lake Project results in a present
worth savings of about $156 million. This savings is comprised of
approximately $56 million for spinning reserve and energy cost savings plus
$100 million for not installing the 230 kV Anchorage-Soldotna transmission
line. For the DOR 50% case, this line is not required if the 90 MW Bradley
Lake Project is installed on the Kenai Peninsula. A comparison of life
cycle levelized bus-bar costs for Bradley Lake and thermal generation
12-21
alternates is shown in Figure 12.4-2 for the "DOR 50% Case." The 90 MW
Bradley Lake Project has a slight energy cost advantage when compared to
the 200 MW natural gas-fired combined cycle plant at the same capacity
factor.
Tables 12.4-22 to 12.4-27 contain further information from the EGEAS
evaluations for the "DOR 50% Case." The plant installation schedules for
the base case and 90 MW Bradley Lake case are shown in Tables 12.4-22 and
12.4-23. The corresponding annual values for energy generation and cost by
fuel class for 1988 through 2007 are summarized in Tables 12.4-24 and
12.4-25. As for the Reference Case, the major Railbel t fuel source is
natural gas, with combined cycle plants being the primary generation method
with a smaller installed capacity of gas turbines. However, since the "DOR
50% Case" projects the price of coal as a constant value and the price of
natural gas decreasing in real terms, the optimum expansion plans developed
by EGEAS do not include the addition of any coal plants during the period
of the power study. The summaries of annual costs for the two "DOR 50%
Case" expansion plans are included in Tables 12.4-26 and 12.4-27.
12.4.3 Evaluation of Selected 90 MW Bradley Lake Project
The power study results described in the previous sections were based on
the Bradley Lake Project designs developed during the SWEC feasibility
studies. After the selection by SWEC of the 90 MW Bradley Lake Project as
the recommended option, additional refinements of the 90 MW plant were
undertaken. As a result, small changes were made in the capital cost and
annual average energy output from the 90 MW plant. The cost used for the
economic analysis of the selected 90MW plant is the $283,019,000 overnight
cost plus an additional $16,981,000 for interest during construction at the
discount rate, for a total of $300,000,000. The original feasibility stage
values and refined values for the selected plant are shown in Table
12.4-28. These changes to the 90 MW Bradley Lake Project resulted from the
following:
12-22
1. A detailed review of the feasibility stage cost estimate,
2. Detailed evaluations of reservoir inflow conditions, and
3. Reevaluation of minimum diversion flows for aquatic habitat.
EGEAS was run for the selected 90 MW Bradley Lake Project plus thermal
plants (at the Reference Case load and fossil fuel price projections) to
test the effect of the changes in capital cost and energy on the generation
expansion plan. The present worth costs are shown in Table 12.4-29 along
with the values from the base case for comparison. The present worth cost
for the feasibility stage 90 MW Bradley Lake Plant was $5,464 million, or
only $9 million higher than the selected plant present worth value. The
lower present worth cost for the selected plant indicates that the increase
in capital cost is more than offset by benefits from the additional average
annual energy generated. Table 12.4-30 is a summary of the annual costs
and present worth cost from EGEAS for the selected 90 MW Bradley Lake
Project. As before, significant life-cycle savings result by using the
refined 90 MW Bradley Lake Project in place of thermal generation
alternatives for the Railbelt. The generation expansion plan developed by
EGEAS for the selected plant is identical to the feasibility stage plan in
Table 12.4-6. Figure 12.4-3 shows the levelized bus-bar cost for the
selected 90 MW plant and the thermal alternatives.
Although the 60 MW and 135 MW Bradley Lake Projects were not reevaluated
after the feasibility stage, similar results would be obtained for these
plant capacities. The cost and annual average energy values would change
in the same proportion as for the selected 90 MW Plant. The three Bradley
Lake plant capacities would have the same relative economic performance as
discussed in the previous sections. Thus, the conclusions reached in the
power study remain unchanged, and the 90 MW Bradley Lake Project is the
recommended capacity.
12-23
POWER STUDIES AND ECONOMIC EVALUATION
REFERENCES
1. Electric Power Research Institute, "Electric Generation Expansion
Analysis System," Report No. EPRI EL-2561, Six Volumes.
2. Alaska Power Authority, Susitna Hydroelectric Project FERC
Application, prepared by Harza-Ebasco Susitna Joint Venture, July 1983.
3. Alaska Power Authority, "FY83 Guidelines for Power Studies and
Economic Analyses," July 1982.
4. Burns & McDonnell, "Report on the Power Requirements Study for Chugach
Electric Association, Inc.," Report No. 82-182-4-001, 1983.
5. Battelle Pacific Northwest Laboratories, "Railbelt Electric Power
Alternatives Study: Evaluation of Railbel t Electric Energy Plans,"
for the Office of the Governor, State of Alaska, Division of PoJicy
Development and Planning and the Governor's Policy Review Committee,
February 1982.
12-24
ECONOMIC EVALUATION PARAMETERS
PARAMETER
Inflation Rate
Real Discount Rate
Equipment Economic Lifetimes (years)
Gas Turbines
Combined Cycle Turbines
Steam Turbines
Hydroelectric Projects
Transmission Systems
Base Year
Planning Period (20 years)
Wood Poles
Steel Towers
Submarine Gables
Economic Analysis Period (50 years)
VALUE
O%
3.5%
20
30
30
50
30
40
30
1983
1988-2007
1988-2037
'-------------TABLE 12.3-1
SHERMAN H. CLARK NSD CASE FORECAST
SUMMARY OF INPUT AND OUTPUT DATA
ITEM DESCRIPTION 1983 1985 1990 1995
World Oil Price (1983$/bbl) 28.95 26.30 27.90 32.34
Energy Price Used by RED (1980$)
Heating Fuel Oil -Anchorage ($/MMBTU) 7.75 6.45 6.84 7.93
Natural Gas -Anchora~e ($/MMBTU) 1.73 1.95 2.88 4.05
State Petroleum Revenues<l (Nom.$xlo6J
Production Taxes 1,474 1,561 2,032 1,868
Royalty Fees
(Nom. $xl06)
1,457 1,555 2,480 2,651
State Gen. Fund Expenditures 3,288 3, 700 5,577 7 '729
State Population 457,836 490,146 554,634 608,810
State Employment 24 3, 067 258' 396 293,689 313,954
Railbelt Population 319,767 341,613 389,026 423,460
Rai1belt Employment 159,147 169,197 190,883 204,668
Railbelt Total Number of Households 111' 549 120,140 138, 640 152,463
Railbelt Electricity Consumption (GWh)
Anchorage 2' 322 2,561 3,045 3, 371
Fairbanks 481 535 691 800 --
Total 2,803 3,096 3, 736 4,171
Railbelt Peak Demand (MW) 579 639 777 868
2000 2005 2010
37-50 43.47_ 50.39
9.19 10.65 . 12.35
4.29 4.96 5.38
1,910 2,150 2,421
3,078 3,799 4,689
9,714 13,035 • 17,975
644,111 686,663. 744,418
325,186 345' 701 376,169
451,561 486,851 533,218
214,542 231,584' 255,974
163,913 177' 849 195,652
3,662 4,107 4 '735
880 ~ 1,123
4,542 5,093· 5,858
945 1,059 1,217
lpetroleum revenues also include corporate income taxes, oil and gas property taxes, lease bonuses, and federal
shared royalties.
Source: Reference 2, Exhibit B, Table B.l03.
~----------------------------~--~------------~----TABLE12.3-2~
Year
1983
1984
1985
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
PROJECTED PEAK AND ENERGY DEMAND (NET)
SHERMAN H. CLARK NSD CASE
Anchorage-Fairbanks-
Cook Inlet Area Tanana Valley Area Total Rail belt
Energy Peak Energy Peak Energy Peak
GWh MW GWh MW GWh MW
2,322 469 481 110 2,803 579
2,442 493 508 116 2,950 609
2,561 517 535 122 3,096 639
2,658 538 566 129 3,224 667
2,755 558 597 136 3,352 695
2,852 579 629 144 3,481 722
2,949 599 660 151 3,609 750
3,045 619 691 158 3,737 777
3,111 633 713 163 3,824 796
3,176 646 735 168 3,911 814
3,240 659 757 173 3,997 832
3,306 672 778 178 4,084 850
3,371 686 800 183 4,171 868
3,429 697 816 186 4,245 884
3,487 709 832 190 4' 319 899
3,545 721 848 194 4,394 914
3,604 732 864 197 4,468 930
3,662 744 880 201 4,542 945
3, 751 762 902 206 4,652 968
3,840 780 923 211 4,762 991
3,929 798 944 215 4,872 1,013
4,018 816 965 220 4,983 1,036
4,107 834 986 225 5,09 3 1,059
4,232 859 1,013 231 5,246 1,091
4, 358 885 1,041 238 5,399 1,122
4,484 910 1,068 244 5,552 1,154
4,609 936 1,096 250 5,705 1,186
4, 735 961 1,123 256 5,858 1,217
Source: Reference 2, Exhibit B, Table 8.117 •
._____ _________ TABLE 12.3-3
Year
1983
1984
1985
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
RAILBELT PEAK DEMAND
AND ENERGY PROJECTION (NET)
SHERMAN H. CLARK NSD CASE
Peak Demand
MW Change, %*
579 5.18
609 4.9 3
639 4.38
667 4.20
695 3.88
722 3.88
750 3.60
777 2.45
796 2.26
814 2.21
832 2.16
850 2.12
868 1.84
884 l. 70
899 1.67
914 1.75
930 1.61
945 2.4 3
968 2.38
991 2.22
1,013 2.27
1,036 2.22
1,059 3.02
1,091 2.84
1,122 2.85
1,154 2.77
1,186 2.61
1,217
Average annual compound growth rate: 2.8%
Average load factor: 55%
*Percent change from current to following year •
Energy
GWH
2,803
2,950
3,096
3,224
3,352
3,481
3,609
3, 737
3,824
3,911
3,997
4,084
4,171
4,245
4' 319
4,394
4,468
4,542
4,652
4,762
4,872
4,983
5,093
5,246
5,399
5,552
5,705
5,858
..___ ________ TABLE 12.3-4
HISTORICAL ANCHORAGE AND COOK INLET PEAK DEMAND
Peak Demandz MW Load Fraction
Chugachl AMLP4
Occurring in
Year HEA+KCL2 Seward3 Kenai Peninsula5
1974 185.6 24.7 5.8 76.8 0.12
1976 217.6 34.8 4.1 91.2 0.13
1978 290.1 50.6 7.0 94.5 0.15
1980 337.4 58.5 5.0 121.0 0.14
1982 372.3 66.9 5.3 ll8.5 0.15
1. Includes Chugach Electric Association, Homer Electric Association (HEA)
and Kenai City Light (KCL), Matanuska and Seward.
Source: Reference 4.
2. Reference 4.
3. Reference 4.
4. Data obtained from Anchorage Municipal Light and Power (AMLP), July 29,
1983.
5. HEA + KCL + Seward
Chugach + AMLP
.._____ _________ TABLE 12.3-5
HISTORICAL ANCHORAGE AND COOK INLET ENERGY REQUIREMENTS
Ener~~ Reguirement 1 GWH Load Fraction
Chugach 1 HEA+KCL2 Seward3 AMLP4
Occurring in
Year Kenai Peninsula5
1974 708.4 124.8 16.0 391.7 0.13
1976 1,091.0 174.9 19.2 444.9 0.13
1978 1,351.0 240.0 23.2 443.1 0.15
1980 1,491.8 284.6 26.0 486.6 0.16
1982 1,765.2 346.5 29.5 579.5 0.16
1. Includes Chugach Electric Association, Homer Electric Association (HEA)
and Kenai City Light (KCL), Matanuska and Seward. Source: Reference 4.
2. Reference 4.
3. Reference 4.
4. Reference 2, Exhibit B, Table B.86 except 1974 value which was obtained
from Anchorage Municipal Light and Power (AMLP) data.
5. HEA + KCL + Seward
Chugach + AMLP
.____ ________ TABLE 12.3-6
Year
1983
1984
1985
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2001
2008
2009
2010
LOAD PROJECTION (NET)
SHERMAN H. CLARK NSD CASE
SEPARATION OF ANCHORAGE -COOK INLET LOAD
INTO ANCHORAGE AND KENAI PENINSULA
Anchorase Kenai Peninsula
Energy-GWH Demand-MW Energy-GWH Demand-MW
1,974 399 348 70
2,076 .419 366 74
2,177 439 384 78
2,259 457 399 81
2, 342 474 413 84
2,424 492 428 87
2,507 509 442 90
2,588 526 457 93
2,644 538 467 95
2,100 549 476 97
2,754 560 486 99
2,810 571 496 101
2,865 583 506 103
2,915 592 514 105
2,964 603 523 106
3,013 613 532 108
3,063 622 541 llO
3,113 632 549 112
3,188 648 563 ll4
3,264 663 576 117
3,340 678 589 120
3,415 694 603 122
3,491 709 616 125
3,597 730 635 129
3,704 752 654 133
3,8ll 774 673 137
3,918 796 691 . 140
4,025 817 710 144
..____ _________ TABLE 12.3-7
Sheet 1 of 2
FUEL PRICE PROJECTIONS
SHERMAN H. CLARK NSD SCENARIO
1983 $/MMBTU
Natural Diesel Turbine Beluga Nenana
Year Gas* Oil Oil Coal Coal
1983 2.17 6.87 6.23 1.86 1.72
1984 2.57 6.55 5.94 1.89 1.74
1985 2.46 6.25 5.66 1.92 1.77
1986 2.81 6.25 5.66 1.95 1.83
1987 2.81 6.25 5.66 1.98 1.83
1988 2.89 6.25 5.66 2.01 1.92
1989 2.96 6.4 3 5.83 2.05 1.97
1990 3.04 6.63 6.01 2.08 2.02
1991 3-13 6.83 6.19 2.11 2.07
1992 3.21 7.03 6-38 2.15 2.11 .
1993 3-30 7.24 6.57 2.18 2.17
1994 3-39 7.46 6.76 2.21 2.22
1995 3.48 7.68 6.97 2.25 2.27
1996 3-57 7-91 7.18 2.29 2. 32
1997 3.67 8.15 7.39 2.32 2.38
1998 3-77 8-39 7.61 2-36 2.43
1999 3.88 8.64 7.84 2.40 2.48
2000 3-99 8.91 8.08 2.44 2.55
2001 4.10 9.18 8.32 2.48 2.60
2002 4.21 9.45 8.57 2.51 2.66
2003 4.33 g. 74 8.83 2.55 2.73
2004 4.45 10.03 9.09 2.60 2.79
2005 4.57 10.32 9.36 2.64 2.85
2006 4.70 10.63 9.64 2.68 2.9 3
2007 4.83 10.95 9.9 3 2.72 2.99
2008 4.97 11.28 10.23 2.77 3.06
2009 5.11 11.62 10.54 2.81 3.14
2010 5.25 11.97 10.85 2.86 3.21
2011 5.38 12.26 11.31 2.90 3.28
2012 5.50 12.57 11.40 2.95 3-35
2013 5.63 12.88 11.69 2.99 3.4 3
2014 5.77 13.21 11.98 3.04 3-51
2015 5.90 13.54 12.28 3.09 3.58
2016 6.04 13.88 12.59 3.14 3.66
2017 6.19 14.22 12.90 3.19 3. 75
2018 6-34 14.58 13.23 3.24 3-83
2019 6.49 14.94 13.56 3.29 3-91
2020 6.64 15.32 13.89 3-35 4.00
'-----------TABLE 12.3-8
Year-
2021
2022
2023
2024
2025
2026
2027
2028
2029 '
2030
2031
2032
2033
2034
2035
2036
2037
Sheet 2 of 2
FUEL PRICE PROJECTIONS
SHERMAN H. CLARK NSD SCENARIO
1983 $/MMBTU
Natural Diesel Turbine Beluga Nenana
Gas* Oil Oil Coal Coal
6.74 15.55 14.10 3.40 4.09
6.83 15.78 14.31 3.45 4.18
6.93 16.02 14.5 3 3-51 4.28
7 .o 3 16.26 14.75 3-57 4-37
7.13 16.50 14.97 3.62 4.47
7.23 16.75 15.19 3.68 4.57
7.34 17.00 15.42 3. 74 4.67
7.44 17.25 15.65 3.80 4.77
7.55 17.51 15.89 3.86 4.88
7.66 17.78 16.13 3.92 4.99
7. 7 3 17.95 16.29 3.98 5.10
7.81 18.13 16.45 4.05 5.21
7.88 18.31 16.61 4.11 5-33
7.96 18.50 16.78 4.18 5.45
8.03 18.68 16.95 4.25 5.57
8.11 18.87 17.12 4. 31 5.70
8.19 19.06 17.29 4.38 5.82
* Includes 30¢/MMBTU for pipeline transportation cost.
Source: Reference 2, Exhibit D, Appendix D-1, Table
D-1.9 (natural gas), Table D-2.14 (Beluga coal
and Nenana coal), and Table D-3.2 (diesel oil
and turbine oil) •
.___ ________ TABLE 12.3-8
TOTAL GENERATING CAPACITY
WITHIN THE RAILBELT SYSTEM --1982
Abbrevia-Installed
tions Railbelt Utility Capacity (l)
AMLP Anchorage Municipal Light and Power Department 311.6
CEA Chugach Electric Association 463.5
GVEA Golden Valley Electric Association 221.6
FMUS Fairbanks Municipal Utilities System 68.5
MEA Matanuska Electric Association 0.9
HEA Homer Electric Association 2.6
SES Seward Electric System 5.5
APAd Alaska Power Administration 30.0
U of A University of Alaska 18.6
Total 1,122.8(2)
(1) Installed capacity as of 1982 at 0°F.
(2) Excludes National Defense installed capacity of 101.3 MW.
Source: Reference 2, Exhibit D, Table D.l3.
"------------TABLE 12.3-9
(SHEET 1 of 5)
EXISTING GENERATING PLANTS IN THE RAILBELT
Plant/Unit
EklutnaCa)
Station nCb)
Unit fFl
Unit 112
Unit 113
Unit /14
Diesel l(c)
Diesel 2Cc)
Station n(d)
Unit /15
Unit 116
Unit 117
Unit /18
Beluga
Unit fFl
Unit 112
Unit 113
Unit /J4(e)
Unit /15
Unit #6
Unit 117
Unit /J8(f)
Prime
Mover
H
SCCT
SCCT
SCCT
SCCT
D
D
SCCT
CCST
SCCT
SCCT
SCCT
SCCT
RCCT
SCCT
RCCT
CCCT
CCCT
CCST
Fuel
~ Date
Nameplate
Capacity
(MW)
ALASKA POWER ADMINISTRATION
1955 30.00
Generating
Capacity
@ 0°F (MW)
ANCHORAGE MUNICIPAL LIGHT AND POWER
NG/0 1962 14.00 16.3
NG/0 1964 14.00 16.3
NG/0 1968 18.00 18.0
NG/0 1972 28.50 32.0
0 1962 1.10 1.1
0 1962 1.10 1.1
0 1974 32.30 40.0
1979 33.00 33.0
0 1980 73.60 90.0
NG/0 1982 73.60 90.0
CHUGACH ELECTRIC ASSOCIATION
NG 1968 15.25 16.1
NG 1968 15.25 16.1
NG 1973 53.30 53.0
NG 1976 10.00 10.7
NG 1975 58.50 58.0
NG 1976 72.90 68.0
NG 1977 72.90 68.0
NG 1982 55.00 42.0
Heat Rate
(BTU/kWh)
14,000
14,000
14,000
12,500
10,500
10,500
12,500
11,000
12,500
15,000
15,000
10,000
15,000
10,000
15,000
15,000
'-------------TABLE 12.3-10
(SHEET 2 of 5)
EXISTING GENERATING PLANTS IN THE RAILBELT
Nameplate Generating
Prime Fuel Capacity Capacity Heat Rate
Plant/Unit Mover ~ Date (MW) @ 0°F (MW) (BTU/kWh)
CHUGACH ELECTRIC ASSOCIATION (continued)
CooEer Lake (g)
Units tn, 2 H 1961 15.0 16.0
International
Unit tn SCCT NG 1964 14.0 14.0 15,000
Unit li2 SCCT NG 1965 14.0 14.0 15,000
Unit 113 SCCT NG 1970 18.5 18.0 15,000
Bernice Lake
Unit tn SCCT NG 1963 7.5 8.6 23,400
Unit 112 SCCT NG 1972 16.5 18.9 2 3,400
Unit 113 SCCT NG 1978 23.0 26.4 23,400
Unit 114 SCCT NG 1982 23.0 26.4 12,000
Knik Arm(h)
Unit In ST NG 1952 0.5 0.5
Unit 112 ST NG 1952 3.0 3.0
Unit 113 ST NG 1957 3.0 3.0
Unit 114 ST NG 1957 3.0 3.0
Unit t/5 ST NG 1957 5.0 5.0
HOMER ELECTRIC ASSOCIATION
Kenai
Unit Ill D 0 1979 0.9 o.9 15,000
Point Graham
Unit n D 0 1971 0.2 0.2 15,000
Seldovia
Unit Ill D 0 1952 0.3 0.3 15,000
Unit n D 0 1964 0.6 0.6 15,000
Unit 113 D 0 1970 0.6 0.6 15,000
.____ _________ TABLE 12.3-10
(SHEET 3 of 5)
EXISTING GENERATING PLANTS IN THE RAILBELT
Nameplate Generating
Prime Fuel Capacity Capacity Heat Rate
Plant/Unit Mover ~ Date (MW) @ 0°F (MW) (BTU/kWh)
MATANUSKA ELECTRIC ASSOCIATION
Talkeetna
Unit til D 0 1967 0.9 0.9 15,000
SEWARD ELECTRIC SYSTEM
SES ( j)
Unit Ill D 0 1965 1.5 1.5 15,000
Unit li2 D 0 1965 1.5 1.5 15,000
Unit ti3 D 0 1965 2.5 2.5 15,000
MILITARY INSTALLATIONS --ANCHORAGE AREA
Elmendorf AFB
Total Diesel D 0 1952 2.1 10,500
Total ST ST NG 1952 31.5 12,000
Fort Richardson
Total Diesel(c) D 0 1952 7.2 10,500
Total ST(i) ST NG 1952 18.0 20,000
GOLDEN VALLEY ELECTRIC ASSOCIATION
Healy
Coal ST Coal 1967 64.7 65.0 13,200
Diesel(c) D 0 1967 64.7 65.0 10,500
North Pole
Unit Ill SCCT 0 1976 64.7 65.0 14,000
Unit t/2 SCCT 0 1977 64.7 65.0 14,000
Zendher
GTl SCCT 0 1971 18.4 18.4 15,000
GT2 SCCT 0 1972 17.4 17.4 15,000
GT3 SCCT 0 1975 2.8 3.5 15,000
GT4 SCCT 0 1975 2.8 3.5 15,000
Combined Diesel D 0 1960-70 21.0 21.0 10,500
.____ ________ TABLE 12.3-10
(SHEET 4 of 5)
EXISTING GENERATING PLANTS IN THE RAILBELT
Nameplate Generating
Prime Fuel Capacity Capacity Heat Rate
Plant/Unit Mover ~ Date (MW) @ 0°F (MW) (BTU/kWh)
UNIVERSITY OF ALASKA --FAIRBANKS
Sl ST Coal 1.50 1.50 12,000
S2 ST Coal 1980 1.50 1.50 12,000
S3 ST Coal 10.00 10.00 12,000
Dl D 0 2.80 2.80 10,500
D2 D 0 2.80 2.80 20,500
FAIRBANKS MUNICIPAL UTILITIES SYSTEM
Chena
Unit ill ST Coal 1954 5.00 5.00 18,000
Unit 1/2 ST Coal 1952 2.50 2.50 22,000
Unit fF3 ST Coal 1952 1.50 1.50 22,000
Unit #4 SCCT 0 1963 5.30 7.00 15,000
Unit #5 ST Coal 1970 21.00 21.00 13,320
Unit 116 SCCT 0 1976 23.10 28.80 15,000
Diesel fFl D 0 1967 2.80 2.80 12,150
Diesel #2 D 0 1968 2.80 2.80 12,150
Diesel fF3 D 0 1968 2.80 2.80 12,150
MILITARY INSTALLATIONS --FAIRBANKS
Eielson AFB
Sl, S2 ST 0 1953 2.50
S3, S4 ST 0 1953 6.25
Fort Greelel
•
Dl D2 ~3(i) D 0 3.00 10,500
D4: D5 t i D 0 2.50 10,500
Fort Wainwri~ht ( j)
Sl, S2, S3, S4 ST Coal 1953 20.00 20,000
S5(i) ST Coal 1953 2.00
'--------------TABLE 12.3-10
(SHEET 5 of 5)
EXISTING GENERATING PLANTS IN THE RAILBELT
Legend:
Notes: ---
H
D
SCCT
RCCT
ST
CCCT
NG
0
Hydro.
Diesel.
Simple cycle combustion turbine.
Regenerative cycle combustion turbine.
Steam turbine.
Combined cycle combustion turbine.
Natural gas.
Distillate fuel oil.
(a) Average annual energy production for Eklutna is approximate-
ly 148 GWh.
(b) All AMLP SCCT's are equipped to burn natural gas or oil. In
normal operation they are supplied with natural gas. All
units have reserve oil storage for operation in the event
gas is not available.
(c) These are black-start units only. They are not included in
total capacity.
(d) Units #5, 6, and 1 are designed to operate as a combined
cycle plant. When operated in this mode, they have a
generating capacity at 0°F of approximately 139 MW with a
heat rate of 8,500 BTU/kWh.
(e) Jet engine, not included in total capacity.
(f) Beluga Units #6, 1, and 8 operate as a combined cycle plant.
When operated in this mode, they have a generating capacity
of about 178 MW with a heat rate of 8,500 BTU/kWh.
(g) Average annual energy production for Cooper Lake is approxi-
mately 42 GWh.
(h) Knik Arm units are old and have higher heat rates; they are
not included in total.
(i) Standby units.
(j) Cogeneration used for steam heating.
Source: Reference 2, Exhibit B, Table B.73 •
.....__---------TABLE 12.3-10
THERMAL GENERATION PLANT PARAMETERS
1983 DOLLARS***
Capital Fixed Variable Forced
Cost* O&M O&M Outages Heat Rate
$/K\v $/KW-YR $/MWH % BTU/KWH
Years
Combined C;z:cle
200 MW 1,185 7.76 1.81 8.0 8,000
Gas Turbine
70 MW 683 2.89 5.18 8.0 12,200
Coal**
200 MW 2,632 18.01 0.64 5.7 10,000
* Includes IDC at the rate of 3.5 percent per year.
** Includes transmission cost.
*** 1982 dollars were escalated to 1983 dollars by 7 percent.
Source: Reference 2, Exhibit D, Table D.l8.
Construe-Life-
tion Period time
Years Years --
2 30
l 20
6 30
'"-------------------------TABLE 12.3-11
NEW HYDROELECTRIC GENERATION ALTERNATIVES
PLANT PARAMETERS
Projected
Hy droel ec tri c Capacity Average Annual Installation
Plant MW Energy, GWH Year
Bradley Lake 60 330.5 1988
Bradley Lake 90 345.4 1988
Bradley Lake 135 356.6 1988
Wa tana* 1,020 3,499.0 1993
Devil Canyon* 600 3,435.0 2002
*Source: Reference 2, Exhibit B, page B-3-11.
------------TABLE 12.3-12
BRADLEY LAKE HYDROELECTRIC PROJECT
PLANT COSTS
Millions 1983 Dollars
Bradley Lake
Capacity, MW Capital Cost*
Annual
Fixed O&M**
*
**
***
60
90
135***
Includes IDC.
275.70
287.95
303.50
1.252
1.252
1.252
Includes cost of annual capital renewals (i.e.,
sinking fund for periodic major equipment replacement).
Excludes cost of 230 kV Anchorage/Soldotna
transmission line.
NOTE: For description of Capital Costs and Annual Fixed O&M
Cost, see Section 11 of this report.
L..----------TABLE 12.3-13
Watana
SUSITNA HYDROELECTRIC PROJECT
PLANT COSTS
Millions 1982 Dollars*
~-~-Annual Annual
Capital Cost** Fixed O&M Capital Renewals
4081 10.4 10.79
Devil Canyon 1734 4.8 4.66
* 1982 dollars were escalated to 1983 dollars by 7% for
the economic analysis.
** Includes AFUDC.
Source: Reference 2, Exhibit D, Table D.l, Table D.5 and
Table D.l2.
~---------TABLE 12.3-14
Year
1983
1984
1985
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
RAILBELT PEAK DEMAND
AND ENERGY PROJECTION (NET)
DOR 50% SCENARIO (JULY 1983)
Peak Demand
MW Change, %*
580 5-34
611 4.91
641 3.12
661 3.18
682 2.93
702 2.99
723 2.77
743 1.35
753 1. 33
763 1.18
772 1.30
782 1.28
792 1.64
805 1.61
818 1.59
831 1.56
844 1.54
857 2.10
875 2.06
893 1.90
910 1.98
928 1.94
946 2.64
971 2.57
996 2.41
1,020 2.45
1,045 2.39
1,070
Average annual compound growth rate: 2.3%
Average load factor: 55%
*Percent change from current to following year.
Source: Alaska Power Authority
Energy
GWH
2,808
2,956
3,104
3,198
3,292
3,385
3,479
3,573
3,620
3,667
3,714
3, 761
3,808
3,871
3,9 35
3,998
4,062
4,125
4,211
4,297
4,384
4,470
4,556
4,676
4,796
4,916
5,036
5,156
L------------TABLE 12.3-15
Year
1983
1984
1985
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000**
FUEL PRICE PROJECTIONS
DOR 50% SCENARIO (JULY 1983)
1983 $/MMBTU
Natural Turbine
Gas* Oil
2.77 6.23
2.60 5.80
2.4 3 5. 37
2.47 5-30
2.51 5.23
2.54 5.16
2.58 5.09
2.62 5.02
2.60 4.98
2.58 4.95
2.57 4.91
2.55 4.88
2.53 4.84
2.52 4.81
2.50 4.77
2.49 4.74
2.47 4.70
2.46 4.67
Coal
1.80
1.80
1.80
1.80
1.80
1.80
1.80
1.80
1.80
1.80
1.80
1.80
1.80
1.80
1.80
1.80
1.80
1.80
* Includes 30¢/MMBTU for pipeline transportation cost.
** All fuel prices remain constant after the year 2000.
Source: Alaska Power Authority
~--------TABLE 12.3-16
LEVELIZED FUEL COSTS (1988-2037)
$/MMBTU
Natural
Gas Coal
Sherman Clark NSD Case 4.77 2. 7 3
DOR 50% Case (July 1983) 2.50 1.80
'-----------TABLE 12.3-17
ALTERNATIVES TO BRADLEY LAKE
PRESENT WORTH COST OF OPTIMUM EXPANSION PLANS
ALTERNATIVE
0 Thermal without hydroelectric
(combined cycle, gas turbines, coal)
-with Anchorage/Soldotna 230 KV Tie
-without Anchorage/Soldotna 230 KV Tie
0 Susitna and Thermal
-with Anchorage/Soldotna 230 KV Tie
PRESENT WORTH COST
MILLIONS OF 1983 DOLLARS
5,832
5,860
5,724
'-----------TABLE 12.4-1
BRADLEY LAKE WITHOUT SUSITNA
PRESENT WORTH COSTS AND SAVINGS
FOR DIFFERENT BRADLEY LAKE CAPACITIES
TOTAL RAILBELT EXPANSION PLANS
BRADLEY LAKE ANCHORAGE/SOLDOTNA
PRESENT WORTH, MILLIONS 1983 $
TOTAL COST SAVINGS DUE TO
BRADLEY LAKE
SAVINGS
COMPARED TO
RAILBELT
BASE CASE, % CAPACITY, MW 230 KV TIE
60 NO 5,517 315 5.4
90 NO 5,464 368 6.3
135 YES 5,535 297 5.1
Railbelt Base Case Present Worth Cost = $5,832 (Millions 1983 $)
--------------TABLE 12.4-2
BRADLEY LAKE WITHOUT SUSITNA
PRESENT WORTH COSTS AND SAVINGS
FOR DIFFERENT BRADLEY LAKE CAPACITIES
KENAI PENINSULA EXPANSION PLANS
BRADLEY LAKE ANCHORAGE/SOLDOTNA
PRESENT WORTH, MILLIONS 1983 $
TOTAL COST SAVINGS DUE TO
BRADLEY LAKE CAPACITY, MW 230 KV TIE
60 NO 605 299
90 NO 599 305
135 YES 695 209
Kenai Peninsula Base Case Present Worth Cost = $904 (Millions 1983 $)
SAVINGS
COMPARED TO
KENAI PENIN.
BASE CASE I %
33.1
33.7
23.1
'------------TABLE 12.4-3
Year
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
Total
NEW GENERATION CAPACITY ADDED
BASE CASE (THERMAL PLANTS ONLY)
SHERMAN H. CLARK NSD CASE
Combined Cycle Coal Gas Turbine
200 MW 200 MW 70 MW
IF Capacity tF Capacity IF Capacity
Units MW Units MW Units MW
1.0 200
1.0 200
1.0 200
1.0 200
1.0 70
1.0 200
1.0 200
1.0 200
4.0 800 3.0 6oo 1.0 70
'------------TABLE 12.4-4
Year
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
Total
NEW GENERATION CAPACITY ADDED
60 MW BRADLEY LAKE PROJECT
SHERMAN H. CLARK NSD CASE
Hydroelectric Combined Cycle Coal
200 MW 200 MW
II Capacity II Capacity # Capacity
Gas Turbine
70 MW
II Capacity
Units MW Units MW Units MW Units MW
1.0 60 1.0 200
1.0 200
1.0 200
1.0 70
1.0 70
1.0 70
1.0 200
1.0 200
1.0 200
1.0 60 3.0 600 3.0 600 3.0 210
.____ ________ TABLE 12.4-5
Year
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
Total
NEW GENERATION CAPACITY ADDED
90 MW BRADLEY LAKE PROJECT
SHERMAN H. CLARK NSD CASE
Hydroelectric Combined Cycle Coal
200 MW 200 MW
II Capacity II Capacity II Capacity
Gas Turbine
70 MW
II Capacity
Units MW Units MW Units MW Units MW
1.0 90
1.0 200
1.0 200
1.0 200
l.O 70
l.O 70
l.O 200
l.O 200
1.0 200
1.0 90 3.0 600 3.0 600 2.0 140
.____ ________ TABLE 12.4-6
Year
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
Total
NEW GENERATION CAPACITY ADDED
135 MW BRADLEY LAKE PROJECT
SHERMAN H. CLARK NSD CASE
Hy droel ec tric Combined Cycle Coal
200 MW 200 MW
II Capacity II Capacity # Capacity
Gas Turbine
70 MW
// Capacity
Units MW Units MW Units MW Units MW
1.0 135
1.0 200
1.0 200
1.0 70
1.0 200
1.0 70
1.0 200
1.0 200
1.0 200
1.0 135 3.0 600 3.0 600 2.0 140
----------TABLE 12.4-7
Natural Gas
Energy Fuel Cost
Year GWH $106
1988 2,903 78
1989 3,032 84
1990 3,153 91
1991 3,237 97
1992 3, 303 102
1993 3,375 107
'1 AI"'\ II 3,652 1AI""\
.l.:;l:;l'i .I.V:;I
1995 3, 726 115
1996 3, 794 120
1997 4,288 135
1998 4, 342 140
1999 4,416 147
2000 4,616 154
2001 4, 731 163
2002 4,836 171
2003 4,947 180
2004 3,890 146
2005 3,005 117
2006 1,992 82
2007 2,131 90
*Gross Generation
GENERATION BY FUEL CLASS
BASE CASE (NEW THERMAL PLANTS ONLY)
SHERMAN H. CLARK NSD CASE
Existing
Coal Oil H~droelectric
Energy Fuel Cost Energy Fuel Cost Energy Fuel Cost
GWH $106 GWH $10~-GWH $106
633 16 28 1 190 0
638 16 39 2 190 0
642 17 54 3 190 0
645 17 66 4 190 0
647 18 90 5 190 0
649 18 108 7 190 0
543 1C. 33 ,., 1{'\{'\ {'\
.I.U t::. .L"7V v
550 16 46 3 190 0
556 17 50 3 190 0
172 5 19 1 190 0
177 5 34 2 190 0
179 6 39 3 190 0
89 3 14 1 190 0
89 3 17 1 190 0
89 3 27 2 190 0
89 3 29 2 190 0
1,292 34 0 0 190 0
2,447 65 0 0 42 0
3,623 98 0 0 42 0
3,643 100 0 0 42 0
Total Railbelt
Energy* Fuel Cost
GWH $106
3,753 96
3,899 103
4,039 111
4,137 118
4,230 125
4, 322 132
" 111 Q 127 --r J "'1~V
4,511 134
4' 5.90 140
4,669 141
4, 7.43 148
4, 8'24 155
4,909 158
5 ,0,27 167
5,1J42 176
5, 2155 185
5, 372 180
5,493 182
5,657 180
5,816 189
'---------,------------,--------~-------------TABLE 12.4-8
GENERATION BY FUEL CLASS
90 MW BRADLEY LAKE PROJECT
SHERMAN H. CLARK NSD CASE
Natural Gas Coal Oil Hldroelectric*
Energy Fuel Cost Energy Fuel Cost Energy Fuel Cost
Year GWH $106 GWH $106 GWH
1988 2,498 73 675 17 44
1989 2, 710 70 642 17 11
1990 2,842 76 646 17 16
1991 2,934 82 648 18 21
1992 3,015 87 650 18 30
1993 3,099 {)') 652 , 0 38 :7"-.J..V
1994 3,170 97 650 19 61
1995 3,251 102 652 19 73
1996 3,479 104 562 17 18
1997 3,948 119 178 5 10
1998 4,017 124 180 6 16
1999 4,100 1~0 180 6 16
2000 4,258 139 89 3 24
2001 4,390 148 89 3 14
2002 4,511 157 89 3 13
2003 3,429 121 1,292 34 8
2004 3,547 129 1,292 34 0
2005 2,657 99 2,451 65 0
2006 1,635 63 3,638 98 0
2007 1, 773 71 3,656 100 0
* 90 MW Bradley Lake Project plus existing hydroelectric plants.
** Gross generation.
$106
2
1
1
1
2
" t:.
4
5
1
1
1
1
2
1
1
1
0
0
0
0
Energy Fuel Cost
GWH $106
535 0
535 0
535 0
535 0
535 0 .......... ::> .:;::> 0
535 0
535 0
535 0
535 0
535 0
535 n
535 0
535 0
535 0
535 0
535 0
387 0
387 0
387 0
Total Railbelt
Energy** Fuel Cost
GWH $106
3, 753 92
3,899 87
4,040 94
4,138 100
4,232 106
lo ,........,_ 113 "',j~:;>
4,418 120
4,511 126
4,594 122
4,672 125
4,748 130
4,831 137
4,906 144
5,029 152
5,148 160
5,264 155
5,375 163
5,496 164
5,660 161
5,817 171
L----------------"--------------TABLE 12.4-9
EXPANSION PLAN SUMMARY
BASE CASE (THERMAL PLANTS)
REFERENCE CASE LOAD
ELECTRIC POHER RESEARCH INSTITUTE BRADLEY LAKE
EGEAS REPORT VER 00 LEV 00 EXPAUSION PLAII SUI·ft!ARY
*********MMMifMMMffMMiflflflfMMM*MMMMtiMMM*IfM*If*MMM************************************************M*IfMiflfMiflflf*MiflflflflflflfiltlflflflftflfM
PLAN
PEAH ENERGY •••••• CAPACITY, IIH ••••••• RESERVE ••.••••••• tlEH UNITS ••••••••••
YEAR LOAD, IIH GIIH IIISTALLED RETIRED TOTAL PERCEUT CAPACITY ,IIH CAPITAL CDSTS,H$ ---------------------------
BEliCH 780. 3757. 1079. 38.29
19e8 779. 375Q. 200. 6. 1~79. 6'1.01 zoo. 237.
1989 810. 3899. 0. 0. 1279. 57.95 0. 0.
1990 839. QO'IO. 0. 1. 1278. 52.39 o. 0.
1991 859. <1139. 0. 19. 1259. '16.58 0. 0.
1992 879. '1232. o. 31. 1228. 39.16 0. 0.
1993 898. QJ4:6. 0. 8. 1221. 35.91 o. o.
199Q 918. Q'l19. zoo. 28. 1393. 51.78 zoo. 237.
1995 937. '1513. 0. 20. 1373. '16.5'1 0. 0.
1996 95'1. Q596. 0. 88. 1285. 3Q.69 0. 0.
1997 970. '167'1. 200. 129. 1356. 39.71 200. 237.
1998 987. Q752. D. '19. 1307. 32.50 D. 0.
1999 100'1. '1835. D. 1. 1306. 30.13 D. D.
2000 1020. '1913. zoo. '15. H61. '13.26 200. 237.
2001 10'15. 5032. D. 0. 1'161. 39.86 D. 0.
2002 1070. 5152. 0. '15. 1Q16. 32.QO D. 0.
2003 1093. 5266. 70. 53. 1Q33. 31.05 70. '18.
2DOQ 1118. 5386. zoo. 139. 1'19'1. 33.61 zoo. 526.
2005 11'13. 5505. 200. 89. 1606. '10.'16 200. 526.
2006 1178. 5672. 200. 188. 1618. 37.36 200. 526.
2007 1211. 5833. 0. 0. 1618. 33.57 0. 0 •
• • ALL UNITS •• • • • • • • • UEH UNITS DilLY ••••••• • •• ••••••••••••••••••••• COST SUiftiARY ••••••••••••••••••••••••
YEAR PROD. COST FIXED 0 & H FIXED CHARGES ANNUAL CUll. AtlNUAL PRESENT l«lRTH CUll. PRES. HORTH ------------------------------·-------------------------------------------
1988 10Q. 2. 13. 118. 118. 100. 100.
1989 112. 2. 13. 126. ~45 .. 103. 202.
1990 120. 2. 11. 135. 379. 106. 308.
1991 128. 2. 13. 1QZ. 521. 108. Q16.
1992 135. 2. 13. 1Q9. 671. 110. 526.
1993 n1. z. 13. 157. 828. 112. 631.
199Q 136. 3. 26. 165. 993. 113. 750.
1995 1'13. 3. 26. 172. 1165. 11Q. 86'1.
1996 150. 3. 26. 178. 1H3. 11'1. 978.
1997 150. 5. 39. 193. 1536. 119. 1097.
1998 157. 5. 39. zoo. 1737. 119. 1217.
1999 16Q. 5. 39. 208. 19'1'1. 120. 1337.
2000 167. 6. 52. 225. Zl69. 125. 1'162.
2001 176. 6. 52. 23'1. 2'103. 126. 1588.
2002 185. 6. 52. 2'13. 26Q6. 126. 11n.
2003 195. 6. 55. 257. 2903. 129. 18Q3.
200'1 189. 10. 8'1. 282. 3105. 137. 1980.
zoos 189. 1'1. 112. 315. 3500. 1'18. Zl28.
2006 186. 17. 1'11. 3'1'1. 38'1Q. 156. 228Q.
2007 196. 17. 1Ql. JSQ. '1198. 155. 2'139.
EXT. 3293. 5732.
tlOTES -AtltiUAL COSTS ARE Itl HILLIDtiS OF CURRENT DOLLARS.
-PRESEtlT NORTH COSTS ARE IN IIILLiotiS OF DOLLARS DISCOUNTED TO THE BEGINNitiG OF 1983.
TABLE 12.4-10
EXPANSION PLAN SUMMARY
90 MW BRADLEY LAKE PROJECT
REFERENCE CASE LOAD
ELECTRIC POHER RESEARCH IHSTlTUTE BRADLEY LAHE
EGEAS REPORT VER 00 LEV 00 EXPANSiotl PLAN SutttiARY
.................... ._. ......................................................................... ************************
PLAN
PEAH En&5Y •••••• CAPACITY, HH ••••••• RESERVE •••••••••• NEH UNITS ••••••••••
YEAR LOAD, HH 6HH INSTALLED RETIRED TOTAL PERCENT CAPACITY ,1-IH CAPITAL CDSTSotl$ ---------------------------
BENCH 780. 3757. 1079. 38.Z9
1988 719. 3754. , .. 6. 1169. 49.96 90. Z88.
1989 810. 3899. 200. 0. 1369. 69.06 zoo. Z31.
1990 839. '10'10. 0. 1. 1368. 63.12 o. 0.
1991 859. '1139. 0. 19. 13'19. 57.05 o. 0.
1992 879. '1232. 0. 31. 1318. 50.01 o. 0.
1993 898. 43Z6. 0. 8. 1311. 45.93 o. 0.
1994 918. 4419. 0. Z8. 1Z83. 39.79 o. 0.
1995 937. 4513. 0. zo. 1Z63. 34.80 0. 0.
1996 954. 115"· zoo. 88. 1375. '14.1Z zoo. Z37.
1997 970. 46711. zoo. 1Z9. 14'16. 48.99 zoo. Z37.
1998 987. 475Z. 0. '19. 1397. 41.62 0. o.
1999 1004. 4835. o. 1. 1396. 39.10 0. 0.
2000 10ZO. 4913. 0. 45. 1351. 32.47 0. o.
2001 1045. 5032. 70. 0. 14Z1. 36.03 70. 48. zooz 1070. 515Z. 70. 45. 1446. 35.Zl 70. 48.
Z003 1093. 5Z66. 200. 53. 1593. 45.69 zoo. 5Z6.
C:OO'I 1116. 5386. o. 139. HS4. 30.03 0. o.
Z005 1143. 5505. 200. 89. 1566. 36.96 zoo. 526.
2006 1176. 567Z. zoo. 188. 1578. 33.97 zoo. SZ6.
Z007 1Z11. 5833. o. 0. 1578. 30.27 o. o.
• • ALL UNITS •• ••••••• NEH UNITS OtL Y ••••••• • ••••••••••••••••••••••• COST SUHHARY ••••••••••••••••••••••••
YEAR PROD. COST FIXED 0 t H FIXED CHARGES AHNUAL tUN. AHtllJAL PRESENT tlORTH CUtl. PRES. HORTH --------------------------------------------------------------------------
1988 102. 1. 14. 117. 117. 99. 99.
1989 94. 3. 27. 124. 2'1Z. 101. 200.
1990 10Z. 3. Z1. 13Z. 37'1. 104. 304.
1991 108. 3. Z7. 138. 512. 105. 409.
1992 115. 3. Z7. 145. 657. 106. 515.
1993 12Z. 3. Z7. 15Z. 809. 108. 623.
199'1 1:!9. 3. Z7. 159. 968. 109. 73Z.
1995 136. 3. 27. 166. 1134. 110. 8'12.
1996 130. '1. '10. 17'1. 1309. 111. 953.
1997 133. 6. 53. 192. 1500. 118. 1072.
1998 139. 6. 53. 198. 1696. 118. 1189.
1999 1'15. 6. 53. ZO'I. 190Z. 116. 1307.
2000 153. 6. 53. Z12. Zl1'1. 118. 1425.
2001 161. 6. 56. ZZ'I. 2337. 1ZO. 1546.
200Z 170. 6. 60. Z36. 257'1. 123. 1669.
Z003 163. 10. 88. Z61. Z835. Ill. 1800.
2004 172. 10. 88. 270. 3105. Ill. 1931.
zoos 172. 14. 117. 302. 3407. 14Z. 2073.
2006 167. 17. 1'16. 330. 3738. 150. 2223.
Z007 178. 11. 146. 340. '1078. 149. z:sn.
EXT. 3089. 1'141.
NOTES -ANNUAL COSTS ARE IN HILLIOIIS Of CURRENT DOLLARS.
-PRESEIIT HORTH COSTS ARE IN lllLLIOHS OF DOLLARS DISCOUNTED TO THE BEGINNING Of 1983.
TABLE 12.4-11
BRADLEY LAKE WITH SUSITNA
PRESENT WORTH COSTS AND SAVINGS
FOR DIFFERENT BRADLEY LAKE CAPACITIES
TOTAL RAILBELT EXPANSION PLANS
BRADLEY LAKE ANCHORAGE/SOLDOTNA
PRESENT WORTH, MILLIONS 1983 $
TOTAL COST SAVINGS. DUE TO
BRADLEY LAKE CAPACITY, MW 230 KV TIE
60 NO 5,548 176
90 NO 5,549 175
135 YES 5,658 66
Rai1be1t Base Case Present Worth Cost = $5,724 (Millions 1983 $)
SAVINGS
COMPARED TO
RAILBELT
BASE CASE I %
1.2
'-------------TABLE 12.4-12
BRADLEY LAKE WITH SUSITNA
PRESENT WORTH COSTS AND SAVINGS
FOR DIFFERENT BRADLEY LAKE CAPACITIES
KENAI PENINSULA EXPANSION PLANS
BRADLEY LAKE ANCHORAGE/SOLDOTNA
PRESENT WORTH, MILLIONS 1983 $
TOTAL COST SAVINGS DUE TO
BRADLEY LAKE CAPACITY, MW 230 KV TIE
60 NO 531 143
90 NO 523 151
135 YES 624 50
Kenai Peninsula Base Case Present Worth Cost = $674 (Millions 1983 $)
SAVINGS
COMPARED TO
KENAI PEN IN.
BASE CASE I %
21.2
22.4
7.4
~-----------TABLE 12.4-13
EXPANSION PLAN SUMMARY
90 MW BRADLEY LAKE PROJECT WITH SUSITNA
REFERENCE CASE LOAD
ELECTRIC POHER RESEARCH INSTITUTE BRADLEY LAI<E
EGEAS REPORT VER 00 LEV 00 EXPANSION PLAN SUIUfARY
*******************~***************************************************************************************************
PLAtl
PEAH ENERGY • • • • • • CAPACITY, tiH ••••••• RESERVE •••••••••. NEH UNITS •••••••••.
YEAR LOAD, IIH GHH IllSTALLED RETIRED TOTAL PERCENT CAPACITY, tiH CAPITAL COSTS,If$ --------------------------
BEliCH 780. 3757. 1079. 38.29
1908 779. 37Sq. 90. 6. 1169. 49.96 90. 288.
1989 810. 3899. 0. o. 1169. 4'1.36 0. o.
1990 839. 40'10. o. 1. 1168. 39.27 0. o.
1991 859. 4139. o. 19. 1149. 33.78 0. 0.
1992 879. '1232. o. 31. 1118. 27.25 0. 0.
1993 898. '1326. 102D. a. 2131. 137.Z3 1020. 4367.
199'1 91S. 4419. D. ~e. 2103. 129.16 0. 0.
1995 937. 4513. D. 20. 2083. 122.32 o. D.
1996 95'1. 4596. 0. 88. 1995. 1D9 .10 0. o.
1997 970. 4674. 0. 129. 1866. 92.27 0. 0.
1998 987. q752. 0. 49. 1817. aq.19 D. 0.
1999 10D~. 4835. o. 1. 1816. 80.9'1 0. 0.
2000 10ZO. 4913. o. 45. 1771. 73.65 D. 0.
2001 1oq5, 5032. 0. o. 1771. 69.53 0. 0.
2002 1070. 5152. 600. '15. 2326. 117.'17 600. 1855.
2D03 1093. 5266. o. 53. 2273. 107.87 0. 0.
2ooq 1118. 5386. o. 139. 2134. 90.84 0. 0.
2005 1143. 5505. o. 89. 2046. 78.95 0. o.
2006 1178. 5672. o. 188. 1858. 57.74 o. o.
2007 1211. 5833. o. o. 1858. 53.39 0. 0.
.. ALL UNITS •• .•••••• NEH UNITS ONLY ••••••• . •.•••••••••••••••••.••• COST SUIU·fARY ••••.••.••••••••••••••••
YEAR PROD. COST FIXED 0 I. H FIXED CHARGES ANNUAL CUH. ANNUAL PRESENT NORTH cuu. PRES. HORTH ---------------------...... ___________ .., __________ -----------------------------
1988 102. 1. 1'1. 117. 117. 99. 99.
1989 111. 1. 1'1. 126. 244. 103. 202.
1990 120. 1. 1'1. 136. 379. 107. 308.
1991 128. 1. 14. 1'14. 523. 109. 417.
1992 136. 1. 14. 152. 675. 112. 529.
1993 8. 24. 233. 265. 940. 188. 717.
199'1 11. 211. 233. 268. 1208. 184. 900.
1995 1'1. 24. 233. 271. 1479. 179. 1080.
1996 17. 24. 233. 27'1. 1753. 175. 1255.
1997 21. Zl.J. 233. 277. 2031. 171. 1'126.
1998 24. 24. 233. 280. 2311. 167. 159'1.
1999 27. 2'1. 233. 284. 2595. 164. 1757.
2000 31. 24. 233. 288. 2883. 160. 1918.
2001 36. 2'1. 233. 293. 3175. 158. 2075.
2002 0. 34. 325. 360. 3535. 187. 2262.
2D03 0. 34. 325. 360. 3895. 181. 2443.
2004 0. 34. 325. 360. 4254. 175. Z618.
2005 0. 34. 325. 360. 4614. 169. 2786.
Z006 0. 34. 325. 360. 4973. 163. 2949.
2007 0. 34. 325. 360. 5333. 157. 3107.
EXT. 2439. 5545.
NOTES -ANtlUAL COSTS ARE IN IIILLIONS OF CURREtfT DOLLARS.
-PRESENT NORTH COSTS ARE IN IIILLIOtlS OF DOLLARS DISCOUNTED TO THE BEGINNifiG OF 1983.
TABLE 12.4-14
RAILBELT GENERATION EXPANSION PLANS
SENSITIVITY ANALYSIS TO RAILBELT NO-GROWTH CASE
0% Load Growth per year
Without Susitna
Thermal Plants only
60 MW Bradley Lake
90 MW Bradley Lake>'<
135 MW Bradley Lake*
MILLIONS OF 1983 DOLLARS
PRESENT WORTH COST PRESENT \WRTH SAVINGS
3,194
2,966
2,990
3,010
228
204
184
* Includes Anchorage/Soldotna 230 KV Transmission Line
~--------TABLE 12.4-15
Year
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
Total
NEW GENERATION CAPACITY ADDED
BASE CASE (THERMAL PLANTS ONLY)
0% LOAD GROWTH SENSITIVITY CASE*
Combined Cycle Coal Gas Turbine
200 MW 200 MW 70 MW
11 Capacity tl Capacity 11 Capacity
Units MW Units MW Units MW
1.0 200
1.0 200
2.0 140
1.0 200
2.0 400 1.0 200 2.0 140
*Assumed 0% load growth was used in combination with fuel prices from the
Sherman Clark NSD Case •
.____ ________ TABLE 12.4-16
Year
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
Total
NEW GENERATION CAPACITY ADDED
90 MW BRADLEY LAKE PROJECT
0% LOAD GROWTH SENSITIVITY CASE*
Hydroelectric Combined Cycle Coal Gas Turbine
200 MW 200 MW 70 MW
IF Capacity II Capacity II Capacity fj Capacity
Units MW Units MW Units MW Units MW
1.0 90
1.0 200
2.0 140
1.0 70
1.0 200
1.0 90 1.0 200 1.0 200 3.0 210
*Assumed 0% load growth was used in combination with fuel prices from the
Sherman Clark NSD Case •
.____---------TABLE 12.4-17
Natural Gas
Energy Fuel Cost
Year GWH $106
1988 2,124 63
1989 2,124 64
1990 2,124 66
1991 2,124 68
1992 2,119 70
1993 2,119 72
1994 2,106 73
1995 2,097 74
1996 2,097 76
1997 2,584 87
1998 2,570 88
1999 2,570 91
2000 2,682 98
2001 2,682 100
2002 2,661 102
2003 2, 711 101
2004 2,714 105
2005 2,869 114
2006 1,687 72
2007 1,687 74
GENERATION BY FUEL CASE
BASE CASE (NEW THERMAL PLANTS ONLY)
0% LOAD GROWTH SENSITIVITY CASE*
Coal Oil H:t:droelectric*
Energy Fuel Cost Energy Fuel Cost Energy Fuel Cost
GWH $106 GWH $106 GWH $106
675 17 21 1 190 0
675 17 21 1 190 0
675 18 21 1 190 0
675 18 21 1 190 0
675 19 26 1 190 0
675 19 26 2 190 0
675 20 -39 2 190 0
675 20 47 3 190 0
675 20 46 3 190 0
219 7 16 1 190 0
219 7 28 2 190 0
219 7 28 2 190 0
89 3 42 3 190 0
89 3 42 3 190 0
89 3 57 4 190 0
89 3 16 1 190 0
89 3 0 0 190 0
89 3 0 0 42 0
1,265 35 0 0 42 0
1,265 3? 0 0 42 0
*Assumed 0) load growth was used in combination with fuel prices from the Sherman Clark NSD Case.
**Gross generation.
Total Rail belt
Energy** Fuel Cost
GwH $106
3,010 81
3,010 83
3, o;w 85
3,010 88
3' 0!1..0 90
3,010 92
3,0~0 95
3,010 97
3,099 100
3,008 94
3,006 97
3,0p6 100
3,0b3 103
3,003 106
2,997 109
3,0p7 106
2,9~3 108
3,000 117
2,994 107
2,994 110
L-..--------------~--------..l---TABLE 12.4-18
Natural Gas
Energy Fuel Cost
Year GWH $106
1988 1 '796 48
1989 1,796 49
1990 1,796 51
1991 1,796 52
1992 1,795 54
1993 1, 795 55
1994 1,792 56
1995 1,790 58
1996 1,790 59
1997 2,218 79
1998 2,246 71
1999 2,246 73
2000 2, 376 79
2001 2,376 82
2002 2,371 84
2003 2,357 86
2004 2,382 89
2005 2,528 100
2006 1, 343 57
2007 1,185 50
GENERATION BY FUEL CLASS
90 MW BRADLEY LAKE PROJECT
0% LOAD GROWTH SENSITIVITY CASE*
Coal Oil H:t:droelectric**
Energy Fuel Cost Energy Fuel Cost Energy Fuel Cost
GWH $10 6 GWH $10 6 GWH $10 6
675 17 4 0 535 0
675 17 4 0 535 0
675 18 4 0 535 0
675 18 4 0 535 0
675 19 5 0 535 0
675 19 5 0 535 0
675 20 7 0 535 0
675 20 9 1 535 0
675 20 9 1 535 0
233 7 22 1 535 0
221 7 7 0 535 0
221 7 7 1 535 0
89 3 9 1 535 0
89 3 9 1 535 0
89 3 13 1 535 0
89 3 24 2 535 0
89 3 0 0 535 0
89 3 0 0 387 0
1,269 35 0 0 387 0
1,433 40 0 0 387 0
*Assumed O% load growth was used in combination with fuel prices from the Sherman Clark NSD Case.
**90 MW Bradley Lake Project plus existing hydroelectric plants.
***Gross generation •
Total Rail belt
Energy***Fuel Cost
GWH $106
3,010 65
3,010 67
3,010 69
3,010 71
3,010 72
3,010 75
3,010 77
3,010 78
3,010 80
3,010 87
3,010 78
3,010 81
3,009 83
3,009 85
3,008 87
3,P06 91
3,006 92
3,004 103
3,000 91
3,005 90
....__ ____ __,_ _______ _..;;, ________ --+---TABLE 12.4-19
EXPANSION PLAN SUMMARY
BASE CASE (THERMAL PLANTS)
NO GROWTH CASE
ELECTRIC POHER RESEARCII INSTITUTE BRAOLEY LAKE
EGEAS REPORT VER 00 LEV 00 EXPAHSIOH PLAH SUID·IARY
******************************************************************************************************************* ... ***
PLAH 1
PEAH EHERGY • • • • • • CAPACITY, HH •••••• , RESERVE •••••••••• HEH UltiTS ••••••••••
YEAR LOAD, HH GHH INSTALLED RETIRED TOTAL PERCENT CAPACITY oHH CAPITAL COSTS,IIt -----------__ .. _____________
BEliCH 625. 3010. 1079. 72.59
1988 625. 3010. o. 6. 1079. 72.59 o. o.
1989 625. 3010. o. o. 1079. 72.59 o. 0.
1990 625. 3010. o. 1. 1078. 72.50 o. 0.
1991 625. 3010. o. 19. 1059. 69.52 o. 0.
1992 625. 3010. o. 31. 1028. 64.50 o. 0.
1993 625. 3010. o. 8. 1021. 63.30 o. 0.
1994 625. 3010. o. 28. 993. 58.82 o. o.
1995 625. 3010. o. 20. 973. 55.68 0. o.
1996 625. 3010. 0. 88. 885. •11.63 0. 0.
1997 625. 3010. 200. 129. 956. 52.93 200. 237.
1998 625. 3010. o. 49. 907. 45.17 0. 0.
1999 625. 3010. o. 1. 906. 45.02 o. 0.
2000 625. 3010. o. 45. 861. 37.81 o. o.
2001 625. 3010. o. o. 861. 37.81 o. o.
2002 625. 3010. o. 45. 816. 30.61 o. o.
200] 625. 3010. 200. 53. 963. 54.08 200. 237.
2004 625. 3010. o. 139. 824. 31.86 0. 0.
2005 625. 3010. 140. 89. 876. 40.10 140. 96.
2006 625. 3010. 200. 188. 888. 42.02 zoo. 526.
2007 625. 3010. o. o. 888. '12.02 o. o.
• • All UltiTS •• ....... HEH UltiTS OHLY ....... .. ...................... COST Sl.tiHARY ........................
YEAR PROD. COST FIXED 0 & H FIXED CHARGES AKHI.IAL CUI1. AtHJAl PRESENT HORTH CUH. PRES. HORTH --------------------------------------------------------------------------
1988 89. 0. 0. 89. 89. 75. 75.
1989 91. 0. 0. 91. 179. 74. 148.
1990 93. o. o. 93. 272. 73. 221.
1991 95. o. o. 95. 367. 72. 294.
1992 98. o. o. 98. 465. 72. 365.
1993 100. o. 0. 100. 565. 71. 436.
1994 103. o. o. 103. 668. 70. 506.
1995 105. o. o. 105. 773. 70. 576.
1996 108. o. o. 108, 880. 69. 645.
1997 101. 2. 13. 115. 995. 71. 716.
1998 103. 2. 13. 118. 1113. 70. 786.
1999 106. 2. 13. 121. 1234. 70. 856.
2000 110. 2. 13. 125. 1359. 69. 925.
2001 113. 2. 13. 128. 1486. 69. 994.
2002 116. 2. 13. 131. 1617. 68. 1062.
2003 111. 3. 26. 140. 1757. 70. 1132.
2004 11'1. 3. 26. 143. 1900. 69. 1202.
2005 124. 4. 32. 160. 2060. 75. 1271.
2006 113. 7. 61. 181. 2240. 82. 1359.
2007 115. 7. 61. 183. 2'12'1. eo. 1439.
EXT. 1755. 3l9'L
tlOTES -AHHUAL COSTS ARE IIi HILLIOHS OF CURREHT DOLLARS.
-PRESEHT HORTH COSTS ARE IIi IIILLIOHS OF DOLLARS DISCOUttTED TO THE BEGIHHIHG OF 1983.
TABLE 12.4-20
EXPANSION PLAN SUMMARY
90 MW BRADLEY LAKE PROJECT
NO GROWTH CASE
ELECTRIC POHER RESEARCH INSTITUTE BRADLEY LAI<E
EGEAS REPORT VER 00 LEV 00 EXPAHSIDH PLAit SUitWIT
PLAit
PEAK EHER&Y •••••• CAPACITY, HH ••••••• RESERVE •••••••••• NEH '-'tiTS ••••••••••
UAR LOAD, HH &HH INSTALLED RETIRED TOTAL PERCENT CAPACITYoHH CAPITAL COSTS,Ht -------------------------------------------
BENCH 625. 3010. 1079. 72.59
1988 625. 3010. 90. '· 1169. 86.99 90. 2811.
1989 625. 3010. o. o. 1169. 86.99 o. o.
1990 625. 3010. o. 1. 1168. 86.90 o. o.
1991 625. 3010. O; 19. 11'19. 8].92 0. o.
1992 625. 3010. 0 .• 31. 1118. 78.90 o. o.
1993 625. 3010. o. II. 1111. 77.70 o. o.
199'1 625. 3010. o. 28. 1083. 73.22 o. o.
1995 625. 3010. o. 20. 1063. 70.08 o. o.
1996 625. 3010. o. 88. 975. 56.03 o. o.
1997 625. 3010. o. 129. M6. 35.33 o. o.
1998 625. 3010. zoo. 49. 997. 59.57 200. Zl7.
1999 625. 3010. o. 1. 996. 59.42 o. o.
2000 625. 3010. o. 45. 951. 52.21 o. o.
2001 625. 3010. o. o. 951. 52.21 o. o.
2002 625. 3010. o. 45. 906. 45.01 0. o.
2003 625. 3010. o. Sl. 85l. 36.'18 o. o.
200'1 625. 3010. 1'10. 139. 85'1. 36.66 140. 96.
2005 625. 3010. 70. 89. 836. 33.70 70. 48.
2006 625. 3010. 200. 188. 8'18. 35.62 200. 526.
2007 625. 3010. o. o. 848. 35.62 o . o.
.. ALL '-'tiTS •• .. • • ••• HEN '-'tiTS DilLY ....... .. ...................... COST SUitWIT ........................
YEAR PROD. COST fiXED 0 & H FIXED CHARGES AlftJAL Cl.ll. AlftJAL PRESENT HORTH Cl.ll. PRES. NORTH -------------------------------------------------------------------------
1988 71. 1. 1'1. 87. 87. 73. 13.
1989 73. 1. 1'1. 89. 176. 72. 145.
1990 75. 1. 14. 90. 266. 71. 216.
1991 71. 1. 14. 92. 358. 70. 287.
1992 78. 1. 1'1. 9'1. 45l. 69. 356.
1993 80. 1. 1'1. 96. 549. 68. 42'1.
1994 82. 1. 1'1. 98. 6'17. 67. 491.
1995 8'1. 1. 1'1. 100. 747. "· 557.
1996 86. 1. 1'1. 102. M9. 65. 623.
1997 95. 1. 14. 111. 960. 68. 691.
1998 83. 3. 27. 113. 1013. 68. 759.
1999 85. 3. 27. 115. 1189, 67. 825.
2000 88. 3. 27. 118. 1307. "· 891.
2001 90. 3. 27. 120. 1lf27. 65. 956.
2002 92. 3. 27. 123. 15lf9. 6lf. 1019.
2003 96. 3. 27. 126. 1675. 63. 1083.
2004 98. 3. 34. 135. 1810. 65. 1148.
2005 109. 3. 37. 150. 1960. 70. 1218.
2006 96. 7. "· 169. 21Z9. 71. 1295.
2007 94. 7. "· 167. 2296. 73. 1368.
EXT. 1516. 28811.
NOTES -AtKIAL COSTS ARE IN HILLIDHS OF CURRENT DOLLARS.
-PRESENT liORTH COSTS ARE IN NIUiotiS OF DOLLARS DISCDU'fTED TO THE BEGitiiiNG OF 1983.
TABLE 12.4-21
Year
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
Total
NEW GENERATION CAPACITY ADDED
BASE CASE (THERMAL PLANTS ONLY)
DOR 50% CASE (JULY 1983)
Combined Cycle Coal Gas Turbine
200 MW 200 MW 70 MW
II Capacity fJ Capacity II Capacity
Units MW Units MW Units MW
1.0 200
1.0 200
1.0 200
1.0 70
1.0 70
1.0 200
2.0 140
1.0 200
5.0 1,000 -0--0-4.0 280
~-----------TABLE 12.4-22
Year
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
Total
NEW GENERATION CAPACITY ADDED
90 MW BRADLEY LAKE PROJECT
DOR 50% CASE (JULY 1983)
Hydroelectric Combined Cycle Coal
200 MW 200 MW
II Capacity II Capacity II Capacity
Gas Turbine
70 MW
II Capacity
Units MW Units MW Units MW Units MW
1.0 90
1.0 200
1.0 200
l.O 70
1.0 70
1.0 70
l.O 70
1.0 200
l.O 70
l.O 200 1.0 70
1.0 90 4.0 800 -0--0-6.0 420
'------------TABLE 12.4-23
Natural Gas
Energy Fuel Cost
Year GWH $106
1988 3,012 71
1989 3,099 75
1990 3,185 78
1991 3,177 77
1992 3,261 80
1993 3,235 78
1994 3,255 78
1995 3,308 78
1996 3, 701 81
1997 4,045 86
1998 4,102 87
1999 4,170 88
2000 4,256 89
2001 4' 347 91
2002 4,447 93
2003 4,534 96
2004 4,685 97
2005 4,924 102
2006 5,071 105
2007 5,197 198
* Gross generation.
GENERATION BY FUEL CLASS
BASE CASE (NEW THERMAL PLANTS ONLY)
DOR 50% CASE (JULY 1983)
Existing
Coal Oil Hydroelectric
Energy Fuel Cost Energy Fuel Cost Energy Fuel Cost
GWH $106 GWH $106 GWH $106
492 12 26 1 190 0
507 12 34 2 190 0
518 12 43 2 190 0
523 12 98 4 190 0
528 12 62 3 190 0
532 12 131 6 190 0
535 13 161 7 190 0
534 13 161 7 190 0
329 8 43 2 190 0
77 2 19 1 190 0
80 2 26 1 190 0
81 2 25 1 190 0
51 1 34 1 190 0
54 1 36 1 190 0
55 1 30 1 190 0
56 1 31 1 190 0
32 1 0 0 190 0
38 1 0 0 42 0
19 1 0 0 42 0
21 1 0 0 42 0
Total Railbelt
Energy* Fuel Cost
GWH $10 6
3,719 84
3,830 88
3,936 93
3,989 94
4,041 95
4,089 96
4,141 97
4,193 98
4,263 91
4, 331 89
4, 398 90
4,~67 90
4,531 92
4,626 94
4,722 96
4 ,8ll 98
4,906 97
5,Q04 103
5,132 106
5,261 108
L....---------------..,;..-_----------TABLE 12.4-24
GENERATION BY FUEL CLASS
90 MW BRADLEY LAKE PROJECT
DOR 50% CASE (JULY 1983)
Natural Gas Coal Oil H~droelectric*
Energy Fuel Cost Energy Fuel Cost Energy Fuel Cost
Year GWH $106 GWH $106 GWH
1988 2,498 64 645 15 40
1989 2,592 68 648 15 54
1990 2,862 66 526 12 12
1991 2,889 66 531 12 34
1992 2,952 67 536 13 19
1993 2,~65 67 540 13 50
1994 3,004 67 539 13 64
1995 3,044 68 544 13 12
1996 3,097 69 549 13 79
1997 3,634 76 131 3 30
1998 3,670 76 150 3 41
1999 3, 747 78 161 4 25
2000 3,911 81 76 2 15
2001 4,002 84 76 2 18
2002 4,100 86 77 2 15
2003 4,188 89 78 2 16
2004 4, 317 88 60 1 0
2005 4,556 94 61 1 0
2006 4 '723 97 28 1 0
2007 4,850 100 32 1 0
*90 MW Bradley Lake Project plus existing hydroelectric plants.
**Gross generation •
$106
2
2
1
2
1
2
3
3
3
1
2
1
1
1
1
1
0
0
0
0
Energy Fuel Cost
GWH $106
535 0
535 0
535 0
535 0
535 0
535 0
535 0
535 0
535 0
535 0
535 0
535 0
535 0
535 0
535 0
535 0
535 0
387 0
387 0
387 0
Total Rail belt
Energy** Fuel Cost
GWH $106
3,7;l9 81
3,830 86
3,936 78
3,989 80
4,042 81
4,090 82
4' 143 83
4,195 84
4,252 85
4' 331 80
4, 396 82
4 '4.68 82
4,5137 84
4 ,6r32 86
4,7~8 88
4,817 92
4,912 89
5,005 95
5,139 97
5,2M 101
.____~ ____________ ..;.._ _______ __.__ __ TABLE 12.4-25
EXPANSION PLAN SUMMARY
BASE CASE (THERMAL PLANTS)
DOR 50% CASE
ELECTRIC PotiER RESEARCH INSTITUTE BRADLEY LAHE
EGEAS REPORT VER 00 LEV 00 EXPANSION PLAN SUIIIARY
***********************•************************************************************************•*********************'
PLAN
PEAK EtiERGY •••••• CAPACITY, HH ••••••• RESERVE •••••••••. NEH UNITS ..........
YEAR LOAD, 1-!H GliH INSTALLED RETIRED TOTAL PERCENT CAPACITY ,.IH CAPITAL COSTS ,.1$ ------------------------------------
BEliCH 772. 3718. 1079. 39.73
1968 772. 3719. 200. 6. 1279. 65.60 200. 237.
1969 795. 3830. 0. o. 1279. 60.79 o. o.
1990 817. 3936. o. 1. 1278. 56.38 o. 0.
1991 828. 3989. o. 19. 1259. 52.06 0. o.
1992 e39. ~0'12. o. 31. 12~8. '16.32 o. o.
1993 e'l9. '1090. o. 8. 1221. '13. 73 o. 0.
19911 860. '11~3. o. 28. 1193. 38.63 0. o.
1995 e71. 4196. o. 20. 1173. 311.63 0. 0.
1996 866. 4265. 200. ea. 1285. 45.13 200. 237.
1997 900. 433'1. zoo. 129. 1356. 50.67 200. Z37.
1998 914. ~'103. o. ~9. 1307. ~3.01 o. o.
1999 928. '1'171. o. 1. 1306. '10. 72 0. 0.
2000 9~3. '15'10. 0. 'IS. 1261. 33.80 0. 0.
2001 962. '1636. o. 0. 1261. 31.05 0. 0.
2002 9e2. '1731. 70. 'IS. 1286. 30.95 70. ~e.
2003 1001. '1821. 70. 53. 1303. 30.17 70. 'le.
ZOO 'I 1021. ~916. 200. 139. 13611. 33.63 zoo. 237.
zoos 10'11. 5012. 1'10. 89. 1'116. 36.0'1 1'10. 96.
Z006 1068. 514'1. ~00. 188. 1'128. 33.66 200. 237.
Z007 1096. 5276. o. 0. 1428. 30.31 0. o .
.. ALL utiiTS .. .. .. .. • NEH UHITS OILY ....... • , ...................... COST SUHUARY •••• , ...................
YEAR PROD. COST FIXED 0 & H FIXED CHARGES ANNUAL CUH. ANNUAL PRESENT HORTH CUU. PRES. HORTH --------------------------------------------------------------------------
196B 92. 2. 13. 106. 106. 90. 90.
19e9 97. 2. 13. 111. 21e. 91. teo.
1990 102. 2. 13. 116. 33'1. 91. 271.
1991 103. 2. 13. 117. ~51. e9. 360.
1992 10'1. 2. 13. 119. 570. e7. qqe.
1993 106. 2. 13. 120. 690. es. 533.
1994 107. 2. 13. 1~2. e11. e3. 616.
1995 10e. 2. 13. 122. 934. el. 697.
1996 '99. 3. 26. 128. 1062. e2. 779.
1997 97. 5. 39. 1'10. 1202. e7. 865.
199e 9e. 5. 39. 142. 13'1'1. 85. 950.
1999 99. 5. 39. 1'12. 1~86. e2. 1032.
2000 101. 5. 39. 14'1. 1630. eo. 1112.
2001 103. 5. 39. H6. 1776. 79. 1191.
2002 lOS. 5. '12. 152. 1929. 79. 1270.
2003 10e. 5. '15. 159. 2De7. 80. 1350.
200'1 107. 7. 58. 172. 2259. 83. 1'133.
2005 113. 7. 65. 185. 2~'1<1. 87. 1520.
2006 116. 9. 78. 203. 26'17. 92. 1612.
2007 119. 9. 7e. 206. Z853. 90. 1702.
EXT. 1658. 3361.
NOTES -ANIIUAL COSTS ARE IN IIILLIONS OF CURRENT DOLLARS.
-PRESENT HORTH COSTS ARE IN tiiLLIOtiS OF DOLLARS DISCOUHTED TO THE BEGIHNIIIG OF 1983.
TABLE 12.4-26
EXPANSION PLAN SUMMARY
90 MW BRADLEY LAKE PROJECT
DOR 50% CASE
ELECTRIC POWER RESEARCH IHSTITUTE BRAOLEY LAHE
EGEAS REPORT VER 00 LEV 00 EXPANSIOH PLAN SUIRIARY
*******************************************•****************************************••························•********
PLAN
PEAK ENERGY • • • • •• CAPACITY, IIH ••••••• RESERVE •••••••••• tiEl~ UNITS ••••••••••
YEAR LOAD, lllf GI~H INSTALLED RETIRED TOTAL PERCENT CAPACITY ,IIH CAPITAL COSTS,IIS ---------------------------
BEliCH 772. 3718. 1079. 39.73
1986 772. 3719. 90. 6. 1169. 51.35 90. 268.
1989 795. 3630. 0. 0. 1169. 46.96 0. 0.
1990 817. 3936. 200. l. 1368. 67.40 200. 237.
1991 828. 3969. 0. 19. 1H9. 62.92 0. o.
1992 839. 4042. 0. 31. 1316. 57.04 0. 0.
1993 849. 4090. 0. e. 1311. 54.33 0. 0.
1994 860. 41<U. 0. 28. 1283. 49.09 0. 0.
1995 871. 4196. 0. 20. 1263. 44.96 o. 0.
1996 886. 4265. o. 86. 1175. 32.71 0. 0.
1S97 900. 4334. 200. 129. 1246. 36.45 200. 237.
1996 914. 4403. o. 49. 1197. 30.98 0. o.
1999 9Z8. 4471. 70. 1. 1266. 36.41 70. 48.
2000 943. 4540. 70. 45. 1~91. 36.98 70. 48.
2001 962. 4636. 0. o. 1291. 34.16 0. o.
2002 962. 4731. 70. 45. 1316. 34.00 70. 46.
~003 1001. 4821. 70. 53. 1333. 33.17 70. 46.
~004 1021. 4916. 200. 139. 1394. 36.57 200. 237.
2005 1041. 5012. 70. 89. 1376. 32.19 70. 46.
2006 1068. 5144. 270. 188. 1458. 36.47 270. 285.
2007 1096. 5276. o. 0. 1458. 33.05 0. 0.
• • ALL UHITS •• ....... NEH UHITS Otll Y ....... • ....................... COST SUIIIlARY ........................
YEAR PROD. COST FIXED 0 & II FIXED CHARGES ANNUAL CUll. ANNUAL PRESEIIT HORTH CUll. PRES. HORTH --------------------------------------------------------------------------
1988 90. l. 14. 106. 106. 89. 89.
1969 96. 1. 14. 111. 217. 91. 160.
1990 86. 3. 27. 116. 333. 91. 271.
1991 87. 3. 27. 117. 450. 89. 360.
1992 88. 3. 27. 118. 569. 87. 447.
1993 90. 3. 27. 120. 668. 65. 531.
1994 91. 3. 27. 121. 809. 63. 614.
1995 92. 3. 27. 122. 932. 81. 695.
1996 94. 3. 27. 124. 1056. 79. 775.
1997 68. 4. 40. 132. 1188. 62. 856.
1996 90. 4. 40. 134. 1322. 80. 937.
1999 91. 5. 44. 139. 1461. eo. 1017.
2000 92. 5. 47. 144. 1605. 80. 1097.
2001 95. s. 47. 147. 1752. 79. 1176.
2002 98. 5. so. 153. 1906. eo. 1256.
2003 102. s. 54. 160. 2066. 81. 1336.
2004 98. 7. 67. 171. 2237. 63. 1419.
20QS 105. 7. 70. 182. 2419. 65. 1505.
2006 107. 9. 86. 202. 2621. 92. 1596.
2007 111. 9. 86. 206. 2827. 90. 1666.
EXT. 1614. 3301.
IIOTES • AIIIIUAL COSTS ARE IN IULLIOIIS OF CURRENT DOLLARS.
-PRESENT HORTH COSTS ARE Ill llllliOIIS Of DOLLARS DISCOUNTED TO THE BcGitlNING OF 1981.
TABLE 12.4-27
CAPITAL COSTS AND AVERAGE ANNUAL ENERGY
90 MW BRADLEY LAKE PROJECT
FEASIBILITY STAGE AND SELECTED VALUES
Feasibility Stage Values
Values for Selected Plant
* Includes IDC
Capital Cost* Average Annual Energy,
Millions 1983 $ GWH
287.95
300.00
345.4
369.2
NOTE: For description of Capital Costs and Annual Fixed O&M Costs, see
Section 11 of this Report.
L------------TABLE 12.4-28
SELECTED 90 MW BRADLEY LAKE PROJECT WITHOUT SUSITNA
PRESENT WORTH COSTS AND SAVINGS
Base Case
90 MW Bradley Lake Project
Present Worth, Millions 1983 $
Total Cost Savings Due to
Bradley Lake
5,832
5,455 377
..______ ________ TABLE 12.4-29
EXPANSION PLAN SUMMARY
SELECTED 90 MW BRADLEY LAKE PROJECT
REFERENCE CASE LOAD
ELECTRIC POHER RESEARCH ItiSTITUTE BRADLEY LAI<E
EGEAS REPORT VER 00 LEV 00 EXPAHSIOH PLAH S~IHARY
***************************************************•***********•**************••••••••*********************************
PLAH
PEAl< EHERGY •••••• CAPACITY, IIH, •••••• RESERVE • ......... HEH UHITS ..........
YEAR LOAD, HH GHH IHSTALLED RETIRED TOTAL PERCEHT CAPACITY oi-IH CAPITAL CDSTS,H$
---------------------------
BEliCH 780. 3757. 1079. 38.Z9
1988 179. 315'1. 90. 6. 1169. '19.96 90. 300.
1989 810. 3899. zoo. o. 1369. 69.06 zoo. Z31.
1990 639. '10'10. o. 1. 1368. 63.12 o. o.
1991 859. '1139. o. 19. 13'19. 57.05 o. o.
1992 879. '1232. o. 31. 1318. 50.01 o. o.
1993 898. '1326. 0. 8. 1311. '15.93 o. 0.
199'1 918. '1'119. o. Z8. 1Z8l. 39.79 o. 0.
1995 937. '1513. o. zo. 1Z63. 3'1.80 0. 0.
1996 9511. '1596. zoo. 88. 1375. '1'1.1Z zoo. 237.
1997 970. 467'1. zoo. 1Z9. 1446. '18.99 zoo. Zl7.
1998 987. 4752. o. '19. 1197. '11.62 o. o.
1999 1004. '1815. 0. 1. 1196. 39.10 o. o.
2000 1020. '1913. 0. '15. 1151. 32.'17 o. 0.
Z001 10'15. 5012. 70. o. 1'121. 36.03 70. '18.
Z002 1070. 515Z. 70. 45. 1'1'16. 35.21 70. '18.
2003 1093. 5266. zoo. 51. 1591. '15.69 200. 526.
200'1 1118. 5386. o. 139. 1454. 30.03 o. 0.
2005 11113. 5505. 200. 89. 1566. 36.96 zoo. 526.
2006 1178. 567Z. zoo. 188. 1578. 33.97 zoo. 526.
2007 1211. 5831. o. o. 1578. 30.27 o. o.
• • ALL UHITS •• • ...... HEH UHITS ONI. Y ••••••• .. ...................... COST SUilllARY ........................
YEAR PROD. COST FIXED 0 l H FIXED CHARGES ANNUAL CIJ1. AHHUAL PRESEHT HORTH CUI1. PRES. HORTH --------------------------------------------------------------------------
1988 101. 1. 15. 117. 117. 99. 99.
1989 93. 3. Z8. 1Z'I. Z'l1. 101. 199.
1990 101. 3. 28. 132. 313. 103. 303.
1991 108. 3. 28. 138. 511. 105. '108.
1992 114. 3. 28. 1'15. 655. 106. 51'1.
1993 121. 3. 28. 152. 807. 107. 621.
199'1 1Z8. 3. Z8. 159. 966. 109. 730.
1995 135. 3. 28. 166. 1132. 110. 8'10.
1996 1Z9. II. 41. 17'1. 1306. 111. 951.
1997 132. 6. 5'1. 191. 1497. 118. 1069.
1998 138. 6. 5'1. 198. 1695. 118. 1187.
1999 1'15. 6. 5'1. ZO'I. 1899. 118. 1305.
2000 152. 6. 5'1. 211. 2110. 118. 1'123.
2001 160. 6. 57. Z2'1. 233'1. 1ZO. 1543.
2002 169. 6. 60. 236. 2570. 123. 1666.
2003 162. 10. 89. 261. Z83l. 131. 1797.
200'1 171. 10. 89. Z70. 3101. 131. 1928.
2005 171. 1'1. 118. 302. 3'103. 1'12. 2070.
2006 166. 17. 1'16. 330. 3733. 149. 2219.
2007 117. 17. 1'16. 3'10. 4072. 149. 2368.
EXT. 3082. 5451.
NOTES -ANNUAL COSTS ARE IH HILLIOHS Of CURREHT DOLLARS.
-PRESENT NORTH COSTS ARE IH IIILLIONS Of DOLLARS DISCOUtiTED TO THE BEGIHHIHG Of 1983.
TABLE 12.4-30
PEAKING
INTERMEDIATE
BASE
0 0.2 0.4 0.6 0.8 1.0
CAPACITY FACTOR
TYPICAL BUS-BAR COSTS
""'----------FIGURE 12.2-1
RAILBELT
STAGE 1
KENAI PENINSULA
N l---1 UNLIMITED
TIEFLOW4
RA_ILBELT W/0 KENAI
N)---1
STAGE 2
KENAI PENINSULA RAILBELT W/0 KENAI ---/ .......
/ ' ' N,__-1
LIMITED TIE FLOW
STAGE 3
LEGEND
@ NEW CAPACITY
® EXISTING CAPACITY
~ LOAD
STAGES IN EGEAS GENERATION EXPANSION ANALYSIS
..____ ______________ FIGURE 12.2-2
100
60 MW PLANT
HOURS
8760
100
c
<(
0
...J
90 MW PLANT
HOURS
8760
100
~ c
<(
0
...J
BRADLEY LAKE DISPATCH BY EGEAS
135 MW PLANT
8760
HOURS
..___ ______________ FIGURE 12.2-3
120
110
100
J:
3:
~ 90 --en
..J
..J
:E 80 ..,.,
en 70 0
0
a:
<( 60 co
ch
::;) 50 co
0 w
N 40
..J w
> 30 w
..J
20
10
0
0 0.1
0
135MW
+230 kV LINE
0 = BRADLEY LAKE
0.2 0.3
0
90MW
GAS TURBINE
0
60MW
0.4 0.5 0.6 0.7
CAPACITY FACTOR
SHERMAN CLARK NSD CASE
0.8 0.9 1.0
..___ ______________ FIGURE 12.4-1
120
110
100
:I:
3: 90
~
Cl)
..J
..J 80
::!: ..... 70 Cl)
0
0
a: 60
<(
m
ch 50 ::> m
c 40 w
N
..J w 30 >
135MW
+230 kV LINE
~------~6=0~M:W~0~·~--~~~~~~~======:1 90 MW COMBINED CYCLE
w
..J
20 0 = BRADLEY LAKE
10
0
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0
CAPACITY FACTOR
DOR 50% CASE (JULY 1983)
....___ ______________ FIGURE 12.4-2
110
100
:I:
~ 90 .........
Cl)
...J
...J 80
:2:
~--· Cl) 70
0
0
a: 60
<(
a'.l
ch ::>
a'.l
fa 40
N
...J w 30 > w
...J
20
10
0= BRADLEY LAKE
0
90MW
CAPACITY FACTOR
SHERMAN CLARK NSD CASE
SELECTED 90 MW PLANT
GAS TURBINE
L-----------------FIGURE 12.4-3
13
FINDINGS
AND
RECOMMENDATIONS
13. FINDINGS AND RECOMMENDATIONS
13. 1 FINDINGS
13.1.1 Introduction
The findings address major portions of the study efforts and the overall
objective of the study for selecting a technically,
economically preferred plan for development of
Hydroelectric Power Project.
environmentally, and
the Bradley Lake
These findings are based on available data and information gathered during
the study, on preliminary engineering and technical investigations, and on
environmental and economic evaluations.
13.1.2 Technical Findings
Foundation conditions in the area of the main dam, powerhouse, access
roads, and barge channel are considered satisfactory for the development of
these structures. Further, it was determined that the use of a tunnel
boring machine for excavating the main portion of the power tunnel is
feasible on the basis of the available data and represents the least cost
alternative. Conventional drill and blast, as well as raised boring
techniques can be applied to other appropriate sections of the power
conduit such as the portals, the inclined shaft and short tunnel lengths.
Exploratory work and available data also indicate that the power tunnel can
be excavated through the Bradley River and Bull Moose fault zones using
these methods. Further, combined use of these techniques will result in a
lower total project cost without extending the construction schedule
developed in previous studies.
The findings show that Pelton units, rather than Francis units, are
preferred for the Bradley Lake Project. The Pelton units offer lower total
project costs, better response to peak load following operations, less
complicated control equipment, easier maintenance, and avoidance of
immersion of the turbine equipment and penstock in tidewater.
13-1
With respect to the main dam, the findings show that a concrete faced
rockfill dam ·is preferred because of lower cost, greater use of natural
material, and ease of construction. A dam built to accommodate a maximum
operating pool for generation of elevation 1180 was selected for the
preferred plan. This pool level provides essentially optimum storage for
generation, avoids suspect areas of possible reservoir rim leakage near the
Battle Creek headwaters, and allows maximum effective use of available
riverbed area and channel topography for the development of the dam.
Inclusion of the Middle Fork Diversion concept to seasonally divert water
to Bradley Lake was found technically and economically feasible. The
estimated additional energy generated by use of Middle Fork flows is 16 GWH
per year. Including these seasonal divers ion flows, the 90 MW preferred
plant could provide about 378 GWH of average annual energy if water is not
released for maintaining aquatic habitat and about 369 GWH when some of the
storage is used
habitat. Average
month historical
to supplement
annual firm
period was
natural flows,
energy generation
computed to be
respectively. These energy values represent
available at the generator leads.
as needed for aquatic
during the critical 44
348 GWH and 334 GWH,
the total plant output
Two 115 kV parallel transmission lines, each capable of handling the full
plant output, are provided for greater reliability when transmitting power
to the Kenai Peninsula transmission line grid. Study findings also show
that the selected 90 MW plant will not require another transmission line
between Soldotna and Anchorage as the existing 115 kV line is capable of
providing reserve sharing and economy interchange between Anchorage and the
Kenai Peninsula.
Two separate camps will better support the construction activities of the
project. A lower camp near tidewater will serve the powerhouse, main
tunnel, and transmission line construction; and an upper camp will support
construction of the main dam, diversion tunnel, Middle Fork and other
structures such as the intake channel, upper tunnel and gate shaft.
Development of the proposed upper camp will require additional baseline
13-2
data to further assess its technical feasibility as well as its impact to
the local environment.
Development of an access channel and barge basin at Sheep Point is
technically feasible and cost effective with less environmental impacts
than other alternatives considered. Similarly, access road routes
identified during the study are the best alignments possible for
development, both from a technical and construction scheduling standpoint.
13. 1. 3 Costs and Economics
For all plant capacities evaluated, developments with Pelton type turbines
result in the lowest estimated capital cost. Although the Pelton turbine
and generator equipment costs more than the related Francis equipment,
powerhouse civil costs are less. In addition, surge facilities are not
required for the Pelton turbine installations.
Similarly, cost comparisons for the different dam types favored the
recommended concrete faced rockfill dam over a concrete gravity dam.
The utilization of a tunnel boring machine for the excavation of the major
portion of the main power tunnel results in substantial savings over
convential methods.
The Overnight Cost Estimate for the preferred 90 MW plant is $283,019,000.
This cost includes direct material, labor,
engineering and design cost; cost for the
owner's cost including previous expenditures
and construction equipment;
management of construction;
realized for project studies
and development; land rights cost; all risk insurance; and a contingency of
25 percent. The Overnight Cost Estimate reflects cost as of July 1983.
Economic evaluations show that the 60, 90 and 135 MW installations studied
for the Bradley Lake Project are economically beneficial for the Railbelt,
both with and without the Susitna Hydroelectric Development.
life-cycle savings result by using Bradley Lake in place
generation alternatives. The optimum Bradley Lake project
13-3
Significant
of thermal
capacity is
dependent on and sensitive to the projected load growth rate for the
Railbelt area and the Kenai Peninsula. The economic evaluation studies
showed that the 90 MW selected plan is the prefered choice at the reference
load growth rate of an average 2. 8 percent per year as adopted in this
study. Also, the findings show that this selected installation is less
sensitive to load growth variations.
The study findings show that the Bradley Lake options are very close in
terms of annual energy developed from the project, with only 3 to 5 percent
differences between the three capacities evaluated. The findings also show
that the 90 MW installation would better respond to the load growth demands
for capacity and energy for the Kenai Peninsula area and would result in
greater relative cost savings (due to less transmission costs) when serving
this area rather than the entire Railbelt region.
In conclusion, the feasibility study findings indicate that the Bradley
Lake Hydroelectric Power project is a technically feasible development,
economically attractive and can be adopted to its environmental setting.
13.2 RECOMMENDATIONS
Based on the above outlined findings and conclusions, it is recommended
that the energy potential of Bradley Lake be developed utilizing a 90 MW,
two unit Pelton turbine powerhouse, a concrete faced rockfill dam, a
machined bored concrete lined power tunnel, the Middle Fork diversion, and
two 115 kV parallel transmission lines. Efforts should now proceed with
the preparation of a Federal Energy Regulatory Commission (FERC) License
Application and continue with the definitive engineering-design phase of
the work.
In conjunction with the License Application it is recommended that
unresolved environmental concerns and issues be addressed, and mitigation
and enhancement plans be conceptually developed in the following areas:
o Bradley River fishery habitat
o Rehabilitation of the Martin River borrow areas
13-4
o Waterfowl nesting in select spoil areas
o Moose dispersion and migration corridors
o Environmental impacts along the preferred transmission line corridor
and upper camp area
To support the engineering-design phase of the work, it is recommended that
field investigative programs be identified at an early stage to develop
additional geologic, survey, and other engineering data.
13-5
14
BIBLIOGRAPHY
14. BIBLIOGRAPHY
1. Reanalysis of the Bradley Lake Hydroelectric Project, Main Report and
Appendix 1A -U.S. Army Corps of Engineers, Alaska District, March
1978.
2. Reanalysis of the Bradley Lake Hydroelectric Project, Appendix 3
Economic and Environmental References, Alaska District Army Corps of
Engineers -March 1978.
3. Bradley Lake Photo Control, COE August-Sept.
calculation sheets plus 2 Rite Rain Field Books.
1979. Data and
4. Survey Bradley Lake Field Survey Information, Corps of Engineers
5.
data with USGS maps and tidal bench marks. 1979
Survey Bradley
calculations and
February 1980.
Lake Hydrographic Survey Outlet,
3 Rite Rain survey log books.
COE with maps,
December 1979
6. Survey Books (4)-Bradley Lake -Lake Stream Outlet, control levels,
River topo, Lake cross sections. COE June 1980. See also Document #16.
7. Survey -Bradley Lake Hydrographic Outlet Topo, includes copies of 4
booklets and 2 depth sounding graphs. June 1980.
8. Design Memorandum No. 2, original & copy of an unnumbered plate drawn
June 1980. Corps of Engineers.
9. Bradley Lake Drill Hole Locations -Preliminary Alignment, Corps of
Engineers. June 1980. Reference field books in Document #11.
10. Bradley Lake Drill Hole Locations, with maps, computer printouts and
calculations. No date.
11. Survey Books (7)-Bradley Lake Dam Alignment, Drill Holes & Powerhouse
Tunnel, COE June-July 1980. See also Document #9.
12. Bradley Lake Dam Area Drill Hole Locations and Horizontal Control,
with maps, computer printouts and survey data. COE. June-August 1980.
13. Bradley Lake Power Tunnel Alignment Drill Hole Locations, with maps
and computer printouts. Power tunnel horizontal and vertical control
calculations, transponder locations, final adjusted coordinates on
upper and lower powerhouse, dam area vertical control, coordinates for
boat basin and airstrip camp area and daily log of field surveys.
June-September 1980.
14. Bradley Lake Project -Hewlett/Packard Notes, COE June-August 1980.
Small ring-bound booklet.
15. Bradley Lake Depth Soundings, COE July 1980. Reference 2 BRA 92-06-06.
16. Bradley Lake -Lake Stream Outlet, COE July 1980. Reference 2 BRA
92-06-03. Also see Document #6 for 4 Field Books.
17. Surv~y -Staging Area, referencing Topo Map 2 BRA 92-06-05, computer
printout, Corps of Engineers. July 1980
18. Survey -Bradley Lake Tidal Datums, USC & GS NOAA, ITech Levels, Horiz
Control Data (General) Corps of Engineers, July-August 1980
19. Bradley Lake -Middle Fork Diversion Horizontal & Vertical Control,
COE August 1980. Reference 2 BRA 92-06-07. See also Document #22-6
Rite Rain Field Books.
20. Survey -Bradley Lake Tailrace, referencing Topo Map 2 BRA 92-06-04
J-97, computer printout, Corps of Engineers, August 1980.
21. Survey -Access Road, referencing Topo Map 2 BRA 92-06-08, Corps of
Engineers August through October 1980.
22. Survey Books (6)-Bradley Lake Project Middle Fork Diversion Alignment
& Topo, COE Sept-Oct 1980. See also Document #19.
23. Survey Books (11)-Bradley Lake Access Road, COE fall 1980.
24. Survey -Bradley Lake Transmission Line Control, utilizing Topo Map 2
BRA 92-06-11, also includes copy of Inertial Survey Report for
Gravulate Transmission Line and North Fork Diversion in Homer, Alaska
Area by International Technology Limited Oct. 1980, Corps of
Engineers. October 1980
25. Survey -Bradley Lake Barge Basin Staging Area, mise. data on Boat
Basin Area & power tunnel drill holes. 1980-1981 Corps of Engineers.
26. Survey -Bradley Lake New Alignment Camps only -Upside down Design,
with maps and computer data. May 26, 1981.
27. Design Memorandum No. 1, June 1981 Hydrology Bradley Lake
Hydroelectric Project -U.S. Corps of Engineers, Alaska District.
28. Design Memorandum No. 1, Hydrology, Bradley Lake Project (DRAFT), U.S.
Army Corps of Engineers -Alaska District.
29. Survey -Main, Airport & Portal Roads Design Version #1, utilizing
Topo Map 2 BRA 92-06-01, Corps of Engineers July -August 1981.
30. Survey -Bradley Lake Airport Road Traverse Adjustment, Corps of
Engineers November 1981.
31. Survey Bradley Lake Revised Calculations for Creek & Tunnel
Alignment, Topo Map 2 BRA 92-06 12/10/81, Corps of Engineers. November
1981
32. Survey Bradley Lake Dam to River Crossing, Computer printout of
curve data. Corps of Engineers 1981.
33. Survey-Main Access Road, Corps of Engineers 1981.
34. Survey Bradley Lake Mise. Information, includes Topo Maps 2 BRA
92-06-01 J97 & H100, 2 BRA 92-06-12 Sheet 8 of 8, and an unnumbered
plate of Design Memorandum #2; and a Tide Schedule for Seldovia,
Alaska. Corps of Engineers. 1981
35. Survey -Bradley Lake Supplement to 1981 Survey, Corps of Engineers.
1981
36. Survey -Bradley Lake Portal Road, Corps of Engineers 1981 & 1982.
37. Survey-Bradley Lake Intake Portals, Corps of Engineers misc. data.
38. Bradley Lake Hydroelectric Project Design Memorandum No. 2, February
1982, General Deslgn Memorandum -Volume 1 of 2, Main Report, U.S.
Army Corps of Engineers, Alaska District. (2 copies)
39. Bradley Lake Hydroelectric Project Design Memorandum No. 2, February
1982, General Design Memorandum -Volume 2 of 2, Appendices, U.S. Army
Corps of Engineers, Alaska District. (2 copies)
40. Environmental Impact Statement
Engineers. March 1982.
Appendices, U.S. Army Corps of
41. Bradley Lake Project Calculation Notebook for Barge Basin, Wind
Speed and Wave Height, Seattle District, Army Corps of Engineers -May
1982.
42. Survey -Bradley Lake Design Comps for Structures/Tunnel Alignment,
includes Topo Map J97 C-1, Corps of Engineers. October 6, 1982
43. Design Memorandum No. 3, Access & Construction Facilities Bradley Lake
Project, Alaska-Department of the Army, Alaska District, Corps of
Engineers (3 copies).
44. Final Environmental Impact Statement, August 1982, Bradley Lake
Hydroelectric. Project, Alaska, U.S. Army Corps of Engineers, Alaska
District. (2 copies)
45. "Economic Evaluation Procedure"-Federal Register (Vol. 44, No. 242),
FERC/Corps of Engineers.
46. Survey -Bradley Lake Field Book Index, 51 booklets as indexed by the
Corps of Engineers. Access Road (1-25), Access Road Camp Area,
Airport Road, Tidal Observations, Battle Crk. X-Sections & Powerhouse,
Drill hole ties, Main Access Road and Portal Road.
47. Bradley Lake Hydroelectric Project Plan of Finance, prepared by the
Alaska Power Authority, April 1982.
48. State of Alaska Memorandum Bradley Lake Hydroelectric Project
November 24, 1982 -written to Dr. Ronald D. Lehr, Director, from Eric
P. Yould, Executive Director.
49. Fox River Flats Critical Habitat Area, Range 9 & 10 West, Map, Alaska
Power Authority.
50. Marine Geophysical Survey -Western Bradley Lake, Alaska, Woodward-
Clyde Consultants, November 1980 (2 copies).
51. Marine Geophysical Survey Western Bradley Lake, Alaska, submitted to
COE by Woodward Clyde. Includes 3 maps showing Isopach Lake
Sediments, lake bottom and elevation base of lake sediment. November
1980.
52. Forecasting Peak Elec.trical Demands for Alaska's Railbelt, Final
Report issued by Woodward-Clyde Consultants for Acres American to
Alaska Power Authority. December 1980.
53. Circulation and Dispersion of Bradley Lake River Water in Opper
Kachemak Bay, prepared for Department of the Army, Alaska District,
Corps of Engineers-December 31, 1980, Woodward-Clyde Consultants.
54. Design Earthquake Study -Report on the Bradley Lake Hydroelectric
Project, prepared for Department of the Army, Alaska District, Corps
of Engineers, Woodward-Clyde Consultants.
55. Geologic Reconnaissance Bradley Lake Access Road, Submitted to
Department of the Army, Alaska District, Corps of Engineers, by
Woodward-Clyde Consultants (2 copies).
56. Reconnaissance Geology, Bradley Lake Hydroelectric Project,
Woodward-Clyde Consultants. (2 copies)
57. Bradley Lake Phase I Feasibility Study on Instream Flow Studies, final
report submitted to Stone & Webster Engineering Corp. by
Woodward-Clyde Consultants. October 1983.
58. Bradley Lake Phase I Feasibility Study on Construction Facilities,
final report submitted to Stone & Webster Engineering Corp. by R&M
Consultants. September 1983.
59. Bradley Lake Phase I Feasibility Study of Transmission Line System,
final report submitted to Stone & Webster Engineering Corp. by Dryden
& LaRue Consulting Engineers. September 1983.
60. Bradley Lake Phase I Feasibility Geotechnical Studies, final report
submitted to Stone & Webster Engineering Corp. by Shannon & Wilson,
Inc. September 1983.
61. Geologic Mapping Program, Bradley Lake Project, Dowl Engineers,
January 1983.
62. Summary Report on Analysis of Construction Procedures and Schedules
Bradley Lake Hydroelectric Project, R. W. Beck and Associates, Inc. ,
September 1982 (preliminary draft). (3 copies)
63. Kenai Peninsula Power Supply and Transmission Study, R. W. Beck and
Associates, Inc. -December 1982.
64. Supplement, Kenai Peninsula Power Supply and Transmission Study, R.W.
Beck and Associates, Inc. -December 1982.
65. Preliminary Results of the Railbelt Economic Analysis -letter from
R.W. Beck and Associates dated February 21, 1983, written to Mr. Eric
Marchegiani, P.E., Project Manager Alaska Power Authority.
66. Bradley Lake Project -Water Quality Report, prepared by Ott Water
Engineers, Inc.
67. Generation Planning Studies, Susitna Hydroelectric Project. Close-out
report, April 1982 by Acres American.
68. Feasibility Study of the Soldotna-Fritz Creek
Energy Report R-2518, Homer Electric Assn,
Commonwealth. June 1983
Transmission Line,
Inc., by Gilbert/
69. Power Requirements Study for Homer Electric Assn. , Inc. , by Burns &
McDonnell. 1983
70. Power Requirements Study for Chugach Electric Association, Inc., Burns
& McDonnell. 1983.
71. City of Fairbanks Municipal Utilities System Financial Statements,
from Harza-Ebasco. 1979, 1980 & 1981. Also an hourly generation log
for one week in each month of 1982.
72. Susitna FERC Application, Appendices Band D, Harza-Ebasco Report.
July 1983.
73. Bradley Lake Hydroelectric Project, Homer, Alaska Findings and
Recommendations, April 28, 1982 -Alaska State Legislature.
74. State of Alaska -Office of the Governor (letter), October 22, 1982
Bradley Lake Renewable Energy Hydroelectric Project Fe as, State I. D.
No. AK820831-09, written to U.S. Department of the Army, Alaska
District, Corps of Engineers from Bill Lucia, Deputy Director.
7 5. Bradley Lake Power Market Report, Backup tables and Kenai Peninsula
power forecasts. Department of Energy, Juneau, Alaska.
76. State of Alaska Memorandum -Bradley Lake Project, August 25, 1982,
Written to Robert Mohn, Director of Engineering, Alaska Power
Authority, from George Matz, Program Analyst, Division of Budget and
Management, Office of the Governor Memorandum mentions Draft
Environmental Impact Statement and General Design Memorandum as well
as the Kenai Peninsula Power Supply and Transmission Study and APA
Plan of Finance.
77. State of Alaska Memorandum Bradley Lake Hydroelectric Project
December 7, 1982 -written to Eric Yould, Executive Director APA from
George Matz, Program Analyst, Division of Budget and Management.
78. National Wildlife Refuge, Map
Peninsula.
Alaska Boundary Series, Kenai
79. Electric Utility Directory Data, Alaska. 1982-83
80. Review of Earthquake Activity and Current Status of Seismic Monitoring
in the Region of the Bradley Lake Hydroelectric Project Southern Kenai
Peninsula, USGS Alaska: November 30, 1981.
81. REA Financed Generating Plants, U.S. Department of Agriculture, Rural
Electrification Admin., January 1983.
82. Chugach Electric Association Annual Report, 1979 & 1981 Pamphlet Issue.
83. Chugach Electric Association Amendment to Prior Agreements for the
Sale of Electric Power and Energy and Lease of Facilities, between CEA
and Horner Electric Association and Matanuska Electric Association.
April 1982.
84. Chugach Electric Association Hourly Logs of Loads, one week in each
month of 1982.
85. Chugach Electric Association Plant Operating Reports, REA Form 12, for
each generating plant, for each month of 1982.
86. Chugach Electric Association Gas Purchase Agreement with Standard Oil
of California, January 1983 ..
87. Chugach Electric Association -ML&P Intertie Energy Rate Schedule,
copy of interim interconnection agreement March 1983.
88. Chugach Electric Association Filing for Approval to Revise Fuel &
Purchased Power Cost Adjustment Factor, and Non-Firm Power Purchase
Rate for Cogenerators and Small Power Producers, April 1983.
89. Chugach Electric Association Tariff Book, May 1983.
90. Chugach Electric Association Filings for Rate Increases, May 1983.
Also, generation and sales by month for 1982. See schedules 6 & 7 at
end of document.
91. Anchorage Municipal Light & Power Data, including hourly generation
(one week/each month 1982), 1982 monthly net generation and peak
loads, energy conservation plan, statements on system reliability and
margin, fuel contracts, system load projections, loss factors and
financial statements for the years ended 1980, 1981 and 1982.
92. Golden Valley Electric Association Data (Fairbanks), including
analysis of energy losses, energy conservation program, energy tariffs
and rates, financial statements for 1980, 81 and 82, operating reserve
requirements, system load estimates, coal purchase agreements, oil
purchase agreements, power sales agreements and large commercial
customer and power usage data.
93. Land Withdrawal, Federal Register Data, Volume 31 page 4793, Published
March 1966.
PLATES
STERLING
HIGHWAY
·."'--. ·y~ ., -.....__ ., ·-~ ......
KEN A I\'
PENINSULA
/
'. ( .?··-
-~·.,
./.
K
CARIBOU
LAKE
9
, A .. "-A ,~ ..
--.. ...
........_
.;<. -...
GULF OF ALASKA
20 40 60 80 100MILES
0 ARCTIC OCEAN
~I
~J
-4.:~
BERING SEA
'
\
' CANADA
100 0 100 200 300 400 500MILES
BRADLEY LAKE HYDROELECTRrC PROJECT
ALASKA POWER AUTHORITY .
LOCATION MAP
& STONE & WEBSTER ENGINEF.RING CORPORATION
ANCHORAGE, ALASKA
PLATE 1
+ +
c
r·-·-·~·-·--~ ~
i
i
i
i
i
i +
KACB8JIAX.
BAY
0
[
r t-I-
c..::;
f
l.:;;
[
L
L
t
KACHEMAK BAY
MUD
FLAT
BARGE
ACCESS
CHANNEL
0
~
~
MIDDLE FORK
DIVERSION DAM
BRADLEY LAKE
/
0
'>z1
w w
(/)
--B UPPER CAMP('\ . QUARRY ~ -~ TO DAM :r;-L) ·.""""-AREA BRADLEY LAKE
,f:>OO~ACCESS ~DAD~ WASr?"'··. NORMAL MAX. WS.EL.1180'
UPPER · AREA ~
CAMP ···=-~ c?0\2,
.. ·
~~\'~ PBRA;~'LAKE HYDROELECTRIC PROJECT r··-~···Y c L ALASKA POWER AUTHORITY
GENERAL PLAN
A STONE & WEBSTER ENGINEERING CORPORATION
ANCHORAGE, ALASKA
1000'
NOTE:
ELEVATIONS SHOWN ARE ON
PIDJECT DATUM.
MEAN SEA LEVEL DATUM= PROJECT
DATUM PLUS 4.02 FT.
0 1000' 2000' 300d 40od
SCALE IN FEET PLATE 3
I
w z
~
I
~ .. ..
+ ..
"'
2 ,100,000
0
01 ~I
;;;
KACHEMAK
TIMBER PILE CHAN 8 A y
{500FT SPACING! NEL MARKERS
0
0
0
~
---~---//
_.-~---~
(
t
(''~
/.rr-0"
_r-
NOTE:
ELEVATIONS
0
8
~ ~0 ~
0 ~ ... ::r 2000
GRAPHic scALE IN FEETnJ
ALI>SKA POr:~RELECTRIC PROJECT AUTHORITY
ACCESS FACILITIES ~ROJECT DAT~~OWN ARE ON
EAN SEA LEV. DATUM PLUS 4~62D~~~M= PROJECT STONE & WE RAM BSTER ENGINEE soo• "c'!."~LTANTS. ONC. ANCHORAGE, AL'1~~ACORPORATION
r ~tva Street Anch . ora8e, Alaaka 88502 PLATE 4
SOUTH B5o WEST
SMALL BOAT LAUNCH RAMP
------\/
\
\
\
\
\
250'X76' \
---------
DESIGN BARG.!----\
( IO'DRAFTJ \
\
\
\
\
\
\
\
\
\
\
\
\
GRAPHIC SCALE 5o--J •• ""
DOCK {SEE DETAIL)®
FEET
DOCK ACCESS ROAD
BARGE Off· LOADING EARTH RAMP
NOTES
"BLPD"= BRADLEY LAKE PROJECT DATUM
"FG"=FINISHED GRADE
1'0G11 =0RIGINAL GROUND
ELEVATIONS SHOWN ARE ON
PROJECT DATUM. .
MEAN SEA LEVEL DATUM= PROJECT
DATUM PLUS 4.02 FT.
BRADLEY LAKE HYDROELECTRIC PROJECT
ALASKA POWER AUTHORITY
ACCESS CHANNEl & BARGE BASIN
STONE & WEBSTER ENGINEERING CORPORATION
ANCHORAGE, ALASKA
R&M CONSULTANTS, INC. PLATE 5 5024 Cordova Street Anchorage, Alaaka 1111502
n HIGH TIDE I 8~ BLPO)
~zz..2.MLLW
APPROX. ORIGINAL GROUND----..........
17' HULL SARGE, EMPTY
@ HIGH TIDE
12' HULL BARGE
@LOW TIDE
DREDGE LINE
'I 11\J\'1 II . 1'·1 I 1,1:11
!/1:1· 'II ·i I I• •I I
·: 1/11: il I,
I I' I 11
" II '1/ I I, II
L II U II
J U I U li
u
2 or::::
">7-----~ ~ --------,.,..
. \__APPROXIMATE ORIGINAL GROUND
4.4 SMALL BOATS RAMP SECTION
A GRAPHIC SCALE
\__ 60TTOhl DfttOOfO DUll~
EL -a.!. MLLW l-14 BLPOI
4.4 OFF-L9ADING RAMP SECTION
B GRAPHIC SCALE
0
FT.
10
FT.
10
RAMP SURFACE CONCRETE LOGS
193'-9"'
'I • ;,'3·1V2
I --·------~~------·-16 BENTS@ 12'-&"'0.C. ·--.L \ ··-·~··J\
-r--
!
?
•' I' II ~ II
I' ,I
II r I' d
r
'I IJ
IJ
'I ~
/I
II
II
~ II
II
FENDER PILES
UNTREATED, CLASS "a"
VERTICAL, 35FT@IO'O.C.
I ~~ I I
~ c 'o 'J
"' ~ :,
A ~ ~ ~ ,,
~ •' r 1 ,I
•' r ,, ~ ,,
II
..
I .(~~' I I I I I I II I ,, II ., '• '• II " '• I' ,,
II II II 'I 'J II ,, II ,, II II \i ,, ,,
'I
,,
~ IJ II II Ji II J\ I' lo II
): ~ ;11 ~ A ~ ~ ~ ~ ~ ,, IJ ,, II II I' " ,, II
li ,, II II ,, II IJ d I\ ,, " II It ,, ,, I, ,I 'I II I• I' II
~ ~ lr ~ r i ~ ~ r ~ t 'J ,,
1· II ,I ,, Jo ol II ol II ,I ,, ,, ,, II II ,J ,, ,, II "
LPILES INDICATED ON BENT •• TYPICAL SPACING.
BATTER PILES ARRANGEMENT AS INDICATED
STEEL CLEATS, FIVE TOTAL \
w :~P~I~S:.~:~ IIIII
10 0
FT.
20
I
-4"X 12" ROUGH DECKING, CCA TREATED
---4" X 12'" STRINGERS@ 1'-0" D.C., CREOSOTE TREATED
~'"--"Ln--"'--"1---IO"XI8" JOISTS@ 2'-0"'0.C., CREOSOTE TREATED
I if' X 18" PILE CAP @.12'-6" O.C., CREOSOTE TREATED
·-----~CLASS "B .. CREOSOTE TREATED TIMBER PILES X S6'
12 VERTICAL PILES/BENT
2 BATTER PILES/ BENT ( 4H: 12V BATTER I
4.4 TYPICAL SEC~ION -PILE BENT
NOTE:
ELEVATIONS SHOWN ARE ON
PROJECT DATUM.
D GRAPHIC SCALE
10
FT.
BRADLEY LAKE HYDROELECfRIC PROJECf
ALASKA POWER AUTHORITY
DOCK STRUCTURE DETAILS
MEAN SEA LEVEL DATUM=PROJECT
DATUM PLUS 4.02 FT. STONE & WEBSTER ENGINEERING CORPORATION
ANCHORAGE,ALASKA
RAM CONSULT ANTS, INC.
5024 Cordov•: Street Anchorage, Alaeka 1111502 PLATE 6
BRADLEY LAKE
MAXIMUM OPERATING W.S. EL.1180'
MINIMUM OPERATING W.S.EL.1080'
NOTE:
ELEVATIONS SHOWN ARE ON
PROJECT DATUM.
MEAN SEA LEVEL DATUM=PROJECT
DATUM PLUS 4.02 FT.
:;o· so· '"''
GRAPHIC SCALE 1"s 50'-0"
BRADLEY LAKE HYDROELECTRIC PROJECT
ALASKA POWER AUTHORITY
GENERAL ARRANGEMENT
DAM, SPILLWAY & FLOW STRUCTURES
& STONE & WEBSTER ENGINEERING CORPORATION
ANCHORAGE, ALASKA
PLAfE 7
[EXTREME LOW
W. S. EL 1D60'
CONCRETE
FACE SLAB
tr-GROUT CURTAIN
I
I
TOE SLAB ''!\'
TOE SLAB "A'= 4'
TOE SLAB "B'= 6'
TOE SLAB "C'=B'
1P.V.C. GROUT
SLEEVE (TYP.)
'*9 HOOKED BARS-DRILL & GROUT
3 EACH FOR TOE SLABS "8' &'C'
2 ~~o;~ctOE SLAB ''I<'
® eJ-o· o.c.
ZONE 3A
BETTER QUARRY MATERIAL
COMPACTED ® 16'' LIFTS
ZONE 38
POORER QUARRY MATERIAL
COMAOCTED ® 18' LIFTS
ZONE 2-SELECT COMA!ICTED ROCK ® 3' LIFTS
10 @ 50'= 500'
LJ
MAXIMUM DAM SECTION
SCALE IN FEET
. /-CONCRETE
..t' FACE SLABS
TOE SLAB
TOE SLAB 'c" 1.J
...............
............... -..........
'-----------------_..........--
VIEW LOOKING DOWNSTREAM
0 40' 80'
~--I SCALE IN FEET
MASTIC FILLER
(TYP. ALL JTS.)
9' NEOP. RUBBER
WATER STOP (TYP.)
9'-6'
1 -1
.I
"'5®12'
PREMOLDED
JOINT FILLER
(TYP.)
NOTE:
ELEVATIONS SHOWN ARE ON
PROJECT DATUM.
./
0 2' ... ~P""'§ii_ii"'-~~~1
MEAN SEA LEVEL DATUM= PROJECT
DATUM PWS 4.02 FT.
SCALE IN fEET
OVERSIZED
ROCK
MAX. W.S. DURING
DIVERSION EL.~10~9~6-~6~'JL__,.,"""""""""~~,t(!J.~~~~;h
DUMPED IMPERVIOUS---"?"~/
DUMPED
1.5 "'1
UPSTREAM COFFERDAM
0 ,.. e··
SCALE IN FEET
#5@12"
*'6x6'-0'®6'
...
I
MASTIC FILLER
(TYP. ALL JTS.)
FACE OF SLAB
I. DOWNSTREAM COFFERDAM __J
MAIN RE-BAR
#8 41110" E.W
3-3
9" NEOP. RUBBER
WATER SlOP (TYP.)
PREMOLDED JOINT
Fl LLER <TYP.)
(DUMPED IMPERVIOUS AND FILTER MATERIAL
REPLACED WITH RIP-RAP AFTER CONSTRUCTION)
PREMOLDED JOINT
FILLER (TYP.)
"6x 6'-r::J' ® 6'
*'5®12' \
·o -.o
I
I--GROUT j CURTAIN
'--"'6 til 6'
"5®12'
2'-6'
2-2
0 2' 4' ,...,__ I
SCAU IN FEET
MAIN RE-BAR
""8®10"E.W.
0 -.q.·
9' NEOP. RUBBER
WATER SlOP (TYP.)
4-4
0 2' 4' ,...._,._ I
SCALE IN FEET
0 2' ...
PRI --I SCA1.£1NffET
*'9 HOOKED BARS-DRILL & GROUT
BRADLEY LAKE HYDROELECTRIC PROJECT
ALASKA POWER AUTHORITY
CONCRETE FACED ROCKFILL DAM
SECTIONS & DETAILS
STONE & WEBSTER ENGINEERING CORPORATION
ANCHORAGE, ALASKA
PLATE 8
T.O.DAM
EL.1194' """\
PMF H.W.EL.1190.6'
CREST EL.1180'
EL.VARIES
T.O.DAM
El.1194'"""\
PMF H.W.EL.1190.6'
tT-o'
CREST
0 ' L ______ _J
EU190'
CREST
EL 1180'
165-o'
PMF H.W.EL.1190.6'
l 25-o' 'I
GROUT ~CURTAIN
IIJ ~ ~==============~~~~~~===+==============~ I
VIEW LOOKING DOWNSTREAM
0 10' ...
e
SCALE IN FEET
55-o'
1so·-o·
1-1
0 ,.. ...
&,-· I
SCALE IN FEET
' ' ' ' \
I
I
APPROX.SOUND ~
,,.~~,-~~~~----LL_E_L_1_13 __ 0' ~
2j /
/ _____ ___/
20'-0'
30'-o'
/
/
/
60'-d'
4r:J-o"
I
~
I
I
NOTE:
rEU124'
ELEVATIONS SHOWN ARE ON
PROJECT DATUM.
MEAN SEA LEVEL DATUM= PROJECT
DATUM PLUS 4-02 .FT.
i
BRADLEY LAKE HYDROELECTRIC PROJECT
ALASKA POWER AUTHORITY
SPILLWAY
ELEVATION & SECTIONS
STONE & WEBSTER ENGINEERING CORPORATION
ANCHORAGE. ALASKA
PLATE 9
1120'-
1110'-
1100'-
1090'-
r
1
1' ¢ ROCK SOL TS
® 5' OC. STAG.
15' LONG
CELLTIGHT (TYP.)
0
P'i
365' ROCK BOLT ROOF
470'
215' 30' 185'
GROUT RING
.
TUNNEL PLUG LJ & CONTROL GATES
DIVERSION TUNNEL SECTION
0 30' 60' l"""''~liii-·-~~iiiiii-~'
SCALE IN FEET
..• ;:./f!l:·.
FWW SPRING
--1----f-_.1 LINE
._ ..... : ..... ,.4 .·.·.,.. ..
INV. ,
EL.1076
215'-o''
INTAKE PORTAL
0 10' ,..
e I
SCALE IN FEET
15'-o" .I
1 -1
10' ,..
SCALE IN FEET
30'-o'
3L6"WIDE
WALKWAY
185'-o"
)
TUNNEL PLUG & CONTROL GATES
10' ,..
I
sc:ALEtNFEET
GROUT I
RING~ 1--l--<[ HYDRAUUC CYLINDERS,
1f'f-o'
2-2
0 10' ,..
e I
SCALE IN FEET
OPERATOR, & GATES
3'-6"WIDE
WALKWAY
WATER TIGHT
GATE;: SWT
COVER
TUNNEL
14~o· 14'-o"
5-5
0 10'
PI
STEEL ACCESS
STAIR
,..
I
SPRING
LINE
[SPRING
E
OUTLET PORTAL
0 ,.
0
N
10'
TUNNEL
3-3
oo·
SCAL£ IN FEET
,..
I
NOTE:
ELEVATIONS SHOWN ARE ON
PROJECT DATUM.
MEAN SEA LEVEL DATUM= PROJECT
DATUM PLUS 4.02 FT. '
ROCK BOLTS STEEL SETS
CONCRETE LINED HORSESHOE
n s· to' ,....,... -
0
I"'M•
SCALE IN FEET
4-4
10'
SCALE IN FEET
,..
I
6" STEEL SETS
®PORTALS
® 41 o.c.
BRADLEY LAKE HYDROELECTRIC PROJECT
ALASKA POWER AUTHORITY
CONSTRUCTION DIVERSION
SECTIONS & DETAILS
STONE & WEBSTER ENGINEERING CORPORATION
ANCHORAGE ALASKA
PLATE 10
EL.1212'"""\ __,L___
SPIRAL STAIR
HYDRAULIC
CYLINDER
GATE
~GATE SHAFT
I
I
VENT PIPES
rEL 1203'
[EQUIPMENT PLATFORM
EL1190'
[MAINTENANCE PLATFORM
EL 1170'
lJ .. ~----If-----'2""2'-''!6'----o+f'~12" NOMINAL
CONCRETE
LINING
VENT PIPES
OPERATOR ---H--~H----1
HIGH PRESSURE
BOLTING
MANHOLE
POWER
~t::J,,._,N,EL=-t-Jo'----
1 - 1
0 10' !II)••
EL.1135'"\
tSHAFT
ACCESS STAIRWELL
'.
PLAN-EL.1203'
0 10' 20'
!Ill I
SCALE IN FEET
EL.1030'
TRANSVERSE SECTION
0 30' 60' ,.....__-
SCALE IN FEET
ROCK BOLTS
(TYP.)
SHAFT
INTAKE CHANNEL
~ROCK PLUG COFFERDAM
/ \ (TO BE REMOVED)
eEL 1065'
,--EL 103d
,-EL 1018'
LONGITUDINAL SECTION
0 30' 60' ----==a
SHAFT GATE SHAFT
ACCESS
STAIRS
TOEL 1172'
~HYDRAULIC
PO\NER PACK
HIGH POINT
EL 1203'
REMOVABLE
STEEL
COVERS
PLAN-EL.1053'
0 10' 20'
N• I
SCAlE IN FEET
PLAN -EL.1190'
0 10' e
SCALE IN FEET
STEEL BOLTING
COVERS &
CYLINDER
SUPPORT
.
pi!•
PLAN -EL.1170'
0 10' 20'
N• I
SCALE IN FEET
SHAFT
t--+---+-~ q;_ HYDRAULIC
CYLINDER
GATE
OPERATOR
2-2
, ..
VENT PIPES
NOTE:
ELEVATIONS SHOWN ARE ON
PROJECT DATUM.
MEAN SEA LEVEL DATUM=PROJECT
DATUM PLUS 4.02 FT.
PLOT PLAN-GATE SHAFT
0 50" 100' IY.---I
SCALE IN FEET
BRADLEY LAKE HYDROELECTRIC PROJECT
ALASKA POWER AUTHORITY
INTAKE CHANNEL & GATE SHAFT
SECTIONS & DETAILS
h\ STONE & WEBSTER ENGINEERING CORPOR'ITION
~ ANCHORAGE, ALASKA
PLATE 11
8 + "' \"Q
0
0 +
@
7i
0 0 7.1 0 0 + + 0 0 (::: ~
INTAKE DETAIL
0 10'
!Ill
SCALE IN FEET
1 -1 ,..
N
2-2
,..
SCALE IN FEET
0
0 + 0
\!l
0 z w
CD
...J-
\ I ;:!:
\ \ z
I I 2 I I 0::
I I 0
\ I I 811 '""' ' I "' I I
a.l~ 0 :'!
TORQUE SHAFT \
BOREHOLE~
FOR RAISE ,~,
L=950'
HORIZONTAL TUNNEL
0
0 +
0 ~
UPPER BEND DETAIL
0 , .. ,..
P'l I
SCALE IN FEET
~TUNNEL
3-3
to' 20'
I
.01667 SLOPE-
0 0
0 0
+ +
0 g ~
~TUNNEL
~6'
SCALE IN FEET
I
I
I
I I I 11' 1<1 CONCRETE I I 7i LINED TUNNEL laj\ I I
I I
7.1 ~ 0 0
a .I~ 0
0 0 0 + + +
0 0 0 0 \2 0> OJ " <0
TUNNEL PROFILE
500' o' 5oo' 1000' 1500' ~~~~~.iii
SCALE: 1'= 5001
TUNNEL
12'' NOMINAL
CONCRETE
LINING (TYP.)
7-7
o· a·
P""""1-I
SCALE IN FEET
f-'-END OF 2400'
i----=L:,-=1:.,4::_.4-':i5;:.:0::.,'c-=--+1' STEEL LINER
MAIN TUNNEL
--I--..... ~ REINFORCED
LOWER BEND DETAIL
SCAlE IN FEET
AREA
W4x13
STEEL
SET
TUNNEL
NOTE:
ELEVATIONS SHOWN ARE ON
PROJECT DATUM.
10-10
MEAN SEA LEVEL DATUM= PROJECT
DATUM PLUS 4.02 FT.
0 ••
,...... -
8 +
0
"'
0
0 +
0
'<t
TRh: iSlE; ;T PRESSURE Lll iE t
___ :::-.:_1--_-:-:c PRESSURE LINE J
/!J?~-···----
8 +
0
M
----~
_t-END OF 2400' 6 11 STEEL LINER
0
0 +
@
--25001
--2ood
"' w z
--15001 :J
...J
lli
f-
Ul
--10oo' z
8
CD
--500'
4 TUNNEL & STEF.L LINER
i TUNNEL & STEEL LINER ~~ 6'-8'
'
6-6
0 ••
,...... -
9-9 ,.
I
SCAlE IN FEET
W5x19
STEEL
SET
I \<--GROUT I ' ' HOLES
I
5-5
0 4' 8'
P'"""'J-25
SCAlE WfEIET
8-8
SCAlE IN FEET
HOOP&
LONGITUDINAL
STEEL
REINFORCING
BRADLEY LAKE HYDROELECTRIC PROJECT
ALASKA POWER AUTHORITY
POWER CONDUIT
PROFILE & DETAILS
STONE & WEBSTER ENGINEERING CORPORATION
ANCHORAGE, ALASKA
PLATE 12
PLOT PLAN-POWERHOUSE SITE
1' i1l ROCK BOLTS
® 5' 0. C. STAG.
15' LONG
CELL TIGHT
(TYP.)
TUNNEL
PORTAL
0 ... .... ,...._. __
I
SCAlE IN FEET
CONCRETE
THRUST
Eil.OCK
11' i1l STL PENSTOCK
ELEVATION-POWERHOUSE, PENSTOCK & PORTAL
0;. il'lil--·~o·~~~,.· ,...
SCALEINFEH
CO.RAIL,
EL.70.5
PLAN POWERHOUSE
PENSTOCK & PORTAL
0 10' 20' f.!Nill•ll"iiiiiiiiii~~~~
SCALE IN FEET
ACCESS HATCH
TO TURBINE
CHAMBER
rEL.23'
HIGH TIDE
EL.11.4'
EQUIPMENT D'\TA
1 GENERATOR
2 GENERAlOR BREAKER
3 GENERATOR POTENTIAL
TRANSFORMER
4 NEUTRAL TRANSFORMER
5 CONTROL ROOM
6 DIESEL GENERAlOR
NOTE:
ELEVATIONS :SHOWN ARE ON
PROJECT DATUM.
MEAN SEA LEVEL DATUM=PROJECT
DATUM PWS 4.02 FT.
BRADLEY LAKE HYDROELECTRIC PROJECT
ALASKA POWER AUTHORITY
90 MW PELTON POWERHOUSE
PLANS & SECTIONS-SHT. 1
STONE & WEBSTER ENGINEERING CORPORATION
ANCHORAGE, ALASKA
PLATE 13
40'·0"
UNITS
UNITS
UNIT 2
4:>-o' 55'-o•
~,pi§jl
~ @_] .. :9
1'-
230 N
230
0 17 ,_~~-=~~------------~2~4CJ+4-----+-
p1?r,
{UNIT 2
I
L-----
r------------,
L----------.J
/
PLAN-FLOOR EL.23'
;_ ~iil'lil•!!iiiiiii1~··""""""""""~j"
UNIT 1
I I 01
I 1281 / I o:
L._ ____ ..J._-.J
r--,---,
~ : 29o: 1 I I
I I o•
L _ --1---...J
:_o-_:
EJ EJ~
0:
@)@)@@) ~
=o
-.¢
N
9
'M
"'
··~·.:··if->·?
I. 11'-6"---+__,_11c..c,_6'_' --+----"'-2"'-0'_-o,_" _ __,+----'-11c..c,_6'_' --t-----'-'11'--~ 6,_"---+--"16,__c_,6'--" --1
PLAN-RUNNER EL.15' , .. ,..
I
SCALE IN FEU
HIGH TJDE
EL.11.4 """\
EL.-61
"")
EL.-12'""\
1 __ 4d-cf_ ______ _
BACK-FILL
EL. 21'""\
LONGITUDINAL SECTION
SCALE IN FEET
EERUNNER
TYPICAL SUMP SECTION
0 , ..
e
EQUIPMENT DATA
7 STATIC EXCITATION
8 GOVERNOR ACCUMULATORS
9 GOVERNOR OIL
10 GREASING UNITS
11 OIL SEF1'.RA TOR
12 OIL TANKS
13 MOTOR CONTROL CEN11ERS
14 SPHERICAL VALVE CONTROL
15 SPHERICAL VALVE ACCUMULATORS
16 UNIT SERVICE WATER PUMPS
17 FIRE PUMPS
18 AIR COMPRESSORS
19 AI_R DRYER
20 AIR TANKS
21 WATER PURIFICATION EQUIPMENT
22 WATER TREATMENT
23 DOMESTIC PUMPS
24 JOCKEY PUMP
25 STATOR SUPPORT COLUMN
26 HOT WATER HEATER
27 480V lDAD CENTER
& 480V SWITCHGEAR
28 2-100 GPM DIRTY WATER PUMPS
29 2-500 GPM UNWATERING PUMPS
30 BATTERY ROOM
-BACK-FILL
EL.-6'
NOTE:
[T.O.RAIL
EL 70.5'
([RUNtJER
ELEVATIONS SHOWN ARE ON
PROJECT DATUM.
MEAN SEA LEVEL DATUM=PROJECT
DATUM PLUS 4.02 FT.
BRADLEY LAKE HYDROELECTRIC PROJECT
ALASKA POWER AUTHORITY
90 MW PELTON POWERHOUSE
PLANS & SECTIONS-SHT. 2
STONE & WEBSTER ENGINEERING CORPORATION
ANCHORAGE, ALASKA
PLATE 14
TAILRACE
FLOW
-j---+----!-+"-'
leow1"]
UNITS
15KV BUS
I :1 TO POWERHOUSE
rOIL SEI'li.RATOR
-----------
o_
~ (J)
Q: ·q:
~
0
3
Q:
Ol g { "' 0 0 0
\_CHAIN-LINK
FENCE
PLOJ" PLAN-POWERHOUSE SUBSTATION
0 ,..
PI""
SCALE IN FEET
30'WIDE
GATE
(TYP)
WOOD POLE
STRUCTURE
TYPICAL TRANSMISSION UNE STRUCTURE
0 10' 20'
plj I
SCALE IN FEET
TO SOLDOTNA
TO FRITZ CREEK
PLOT PLAN -BRADLEY JUCTION
0 20' 40'
PI •• I
NOTE:
ELEVATIONS SHOWN ARE ON
PROJECT DATUM.
MEAN SEA LEVEL DATUM=PROJECT
DATUM PLUS 4.02 FT.
TO BRADLEY
LAKE PROJECT
BRADLEY LAKE HYDROELECTRIC PROJECT
ALASKA POWER AUTHORITY
POWERHOUSE SUBSTATION AND
BRADLEY JUNCTION
~-STONE & WEBSTER ENGINEERING CORPORATION
~ ANCHORAGE,ALASKA
PLATE 15
VERTICAL SCALE: 1 ·~ 5 •
HORIZONTAL SCALE: 1 •• 100,
E357,000
TYPICAL SECTION
0 ........
SCALE IN FEU
, .
CONDITIONS IN CONDUIT
DISCHARGE =350 CFS
CORRESPONDING DEPTH =4 .13 FT
VELOCITY = 16.9 FT/SEC
STATE-SUPERCRITICAL.
NOTE:
ELEVATIONS SHOWN ARE ON
PROJECT DATUM
MEAN SEA LEVEL DATUM PLUS 4 .of~~M =PROJECT
BRADLEY LAKE ALASKA ~OYWDREORELECTRIC PROJECT AUTHORITY
MIDDLE FORK DIVERSION
PLAN & PROFILE
STONE & WEB :~~~OERNAGGINEEERING CORPORATION
, ALASKA
PLATE 16
SPILLWAY CHANNEL
CONCRETE APRON
DOWNSTREAM OF
lJJW LEVEL OUTLET
PLAN-MIDDLE FORK DIVERSION
0 50' 100' l'lo·.---2!!3 SCALE IN FEET
INTAKE
CENTER LINE
NATURAL FLDW
MAIN DIVERSION
FlDW LINE-
6' CiJ STEEL PIPE
21
1j (; INTAKE & WAL.KWAY BRIDGE
DETAIL A
SHEET PILE
(INTERLOCKS
CAULKED)
0 2' 4' ,..._.-_ I
SCALE IN FEET
MAX.H.W. EL.2210'
72"x 72" SLUICE
WITH CIRCULAR
WALL THIMBLE-----.11
~ ~e M
I -:'1-~-:-:-J· "1 :rg,.""' _
1
''"'"',.. -l
\ / I -1----' lDW LEVEL // \ --1 z -~OUTLET /f I \ --1___ ! 1~--------: s·r;J PIPE ROCK LINE /r// 1 1 '>f-r--\T---.J--r--· --1
1
-.....j f - -__j FILL / J_ I I '\ ~ ! / J CONCRETE --// I --......,_ I I 4 I I ~~sE?r'~" '/--T~' . ,---r---T----T----r---Tl-I ~< '-Z._t_L _ _l _ _l_L/
6 ' ~ P'PE' ' / I ~ ~ I I .J I I I I __./ GROUT CURTAIN WIER KEYED ~ ' ' / -----,, 3 1----" INTO ROCK <" i //I1'2.J : "-, I _L_L_j___L LOCAL KEY
TOP OF SHE=:-:-P:_:;:
EL.2212'-
LOW LEVEL
OUTLET
.J I / .1--@ SHEET PILE
"---1 _L __ L__. CUTOFF WALL
,,
VIEW LOOKING DOWNSTREAM
0 10' ,.
&•· I
4 JJITAKE
fi
2' DEEP KEY CUT
INTO SOLID ROCK
VIEW LOOKING DOWNSTREAM
AT SHEET PILE CUT-OFF WALL
0 10' 2D' e.•• I
SCALE IN FEET
PZ 3!3 CAULKED INTERLOCKS
SHEET PILE CUT OFF WALL
NX DRILL HOLES
15' DEEP ® 10' O.C.
FOR GROUT CURTAIN
NOTE:
ELEVATIONS SHOWN ARE ON
PROJECT DATUM.
MEAN SEA LEVEL DATUM= PROJECT
DATUM PLUS 4.02 FT.
MAX. H.W. EL.2210'
1.5
11/
DAM
1-1
0 10' ,.. e.·-· I
2-2
0 10' 20'
)II"" I
SCALE IN FEET
DAM
· rCOMPACTED J
0 .t ROCK FILL
~& (TYP.)
"Da '&8Dooc
3-3 . ,..
j:o;po.il'l*·il'l-iiiiiiiii~~~l
SCALE IN FEET
MAX. H.W. EL.2210' DAM
EL.2204'
·o -.q
4-4 ,.. ...
I
DETAIL B
0 2' 4'
paw.++-I
SCALE IN FEET
DETAIL A
SELECT BEDDING
MATERIAL BELOW
PIPE SPRING LINE
SELECT BEDDING
MATERIAL BELDW
PIPE SPRING LINE
CONC. APRON
(30'x15')
Wz ;;;;<(
-'--' oa..
zw ww
IIJVJ
4' x 4 CONC BlDCK GROUND
LINE
w z
:J
0 z w
Ill,
1% SLOPE
BRADLEY LAKE HYDROELECTRIC PROJECT
ALASKA POWER AUTHORITY
MIDDLE FORK DIVERSION
ELEVATIONS & DETAILS
STONE & WEBSTER ENGINEERING CORPORATION
ANCHORAGE, ALASKA
PLATE 17
.: u
0
0
Q
,~
tO-~
5-
3 5-
0
2 5-
.: u
!0-
0
0 2
Q
IJJ
(!)
a:
"" :a:
0
<f)
0
I
10-
5-
f.---.-
f-
1-
1-
-
-
f-
--
.....-
MAX. WA~ER SUR!ACE ELE!.( 1186.6 'FT.)
I
/ -------v·----..._ __ -----·-f----f.-__ __ .,..----,._ ___ ---I
I MAX. SPF INFLOW(I4,400CFS)
1\
190
1185
lBO
1 \ MAX. SPILLWAY DISCHARGE(I0,400CFS)
' /\""-
I 1\ // \ ",
"" 1\.
J > v // ~ ", ~ ~ ',
/ ~--;:;.-~ "-......._
~ / ......... r---._ --
I ---..... ./ --
2 4 5 6 7 8 9 10 II 12 13 14 15
DURATION (DAYS)
STANDARD PROJECT FLOOD
m PROBABLE MAX. FLOOD 1NF1.0N (31,300CFSl
I
I
!
i
I I I i I !
!
SPILLWAY DE~IGN DISCH.ARGE(22,,700CFS) I (\ I
I I\
I \
I I 1\ ! I \ I \
I I
J
I \ \ I \
\ I
I I I ~
\
I I I ~ I ! MAX. WATER SURFACE ELEV. (1190.6 FT.) i I !"' ' ! I /I '\ I
I \ \ I I . \ ./ '·-.\
_.v/·' -;~~ !-'-' / I~ '--r---I
r~ // "-I • 1-------,, "~ . ' ..... 3// I
"-........._ r-__ .J'
l
195
190
185
160
2 4 5 6 7 8 9 10 II 12 13 14 15
DURATION (DAYS)
PROBABLE MAXIMUM AND SPILLWAY DESIGN FLOODS
~ w w 125 0
!!:,
z
0 :::!:
~ ::J
~ ~
0
SPILLWAY CRESf EL 1180.0
120
.J 1-w 0 0 115
IJJ .,
0 a: n.
1-
IJJ
0 MINIMlM OPERATING AN
EXISTING LAKE EL.I080.0
110
IJJ
II..
!: 10 50
z
0
5 > IJJ
...J
IJJ
00 v
/ 50
/ v
v
10
9
900
I
8 '"'
250 200 150
1-w w
ll..
z
0
i= ~ w
.J w
PROlLE MALUN JOD
~ -----~
WATER SURFACE EL.1190.6
\'('( 7 -~~ __,/
..........--/
~ ,/ ~
y ~ DATA FROM SURVEY FEB. 1980
/ AND SOrDINGS AUG. 1980
/ v j !
100 50
J 1 +--t--
I i
v i I
i
I
0 50 100 1!50 200 250 350 400 450 500 550
CAPACITY (IN 1000 ACRE FEET)
0 500 1000 1500 2000 2500 3000 3500 4000 4500 5000 5500
AREA (IN ACRES)
AREA a CAPACITY CURVES
~!ACRE-FEET) CAPACITY (ACRE· FEET)
ALTITlDE AREA BELOW LAt<E ABOVE LAKE ALTITUDE AREA BELOW LAKE ABOVE LAKE
(FEETI (ACRES SURFACE SURFACE (FEETI (ACRES) SUR FiliCE SURFACE
860 668 263,318 1,060 1,462 31,223
880 829 248,337 1,080.!/ 1,568 0
900 946 230,570 1,100 2,177 36,339
920 991 211,188 1,125 2,808 98,672
940 1,087 190,396 1,150 3,353 175,707
960 1,217 167,338 1,175 3,749 264,502
980 1,290 142,249 1,200 4,106 362,699
1,000 1,349 115,840 1,225 4,544 470,834
1,020 1,393 88,403 .:._ 1,250 41397 588,868
1,040 1,430 60,158
.!/ MINIMUM OPERATING AND EXISTING LAKE SURFACE
NOTE:
ELEVATIONS SHOWN ~ ON
PROJECT DATUM.
MEAN SEA LEVEL DATUM=PROJECT
DATUM PLUS 4.02 FT.
BRADLEY LAKE HYDROELECTRIC PROJECT
ALASKA POWER AUTHORITY
PROJECT DESIGN FLOODS AND
RESERVOIR AREA-CAPACITY CURVES
STONE & WEBSTER ENGINEERING CORPORATION
ANCHORAGE, ALASKA
PLATE 18
R! u
3
0
_.)
LJ..
80
0 70
:2: ......
I 60 ::;::
g
?5 50
a:: w z 40 w
30
1958 1959 1960 1961 1962 1963 1964 1965 1967 1968 1969 1970 1971
TIME STEP IMONTHSI
ENERGY GENERATION
1958 1959 1960 1961 1962 1963 1964 1965 1966 1967 1968 1969 1970 1971
TIME STEP IMONTHSI
RESERVOIR FLUCTUATION
Ul
1972
i.97Z
ANNUAL ENERGY-GWHRS
AVERAGE
FIRM
SECONDARY
1973 1914
1973 1974
369.2
334.1
35.1
1975
1975
1976 1971
1976 1977
1918 1979 1980
)
1918 1979 1980
198! 1982
i v
1981 1982
2800
2400
2000
10 20 30 40 50 60 70 80 90 100
PERCENT EXCEEDED
MONTHLY
RESERVOIR INFLOW DURATION CURVE
t30oo .. -----.-----.----.-----.-----.----.-----.----.-----.-----.----.-----.-----r----.-----.----.-----.-----.----.-----.---~.----.-----r----.----.
w
~ 2500
);l2000
0
~ 1500
:3 a.
o()1000
::;::
9
"-~
1-w z
------UNREGULATED FLOW
-----REGULATED FLOW
1958 1959 1960
DISTRIBUTION
RESERVOIR INFLOW
1961 1962 1963
1500-
1250-
1000-
UJ
LJ..
IJ ::;:: 750-
0
_.)
LJ..
500-
250-
1964 1965 1966 1967
r--
DISTRIBUTION
SPILLWAY DISCHARGE
r-
r-
r-
-
-
-
1968 1969 1970 1971 1912 1973
@
LJ..
~ ::;::
0
_.)
LJ..
TIME STEP (MONTHS)
FLOW
DISTRIBUTION
POWERPLANT DISCHARGE
1974
0:: ~
z
0 ;::
;l: w
ul
1975 1976 1917 1978 1979
MONTHS
DISTRIBUTION
RESERVOIR ELEVATION
1980 1981 1982
100
75
fi)
"-~ 50 ::;::
~
25
0
i MAXIMUM
AVERAGE
MINIMUM .
DISTRIBUTION
FISH DIVERSION DISCHARGE
NOTE:
ELEVATIONS SHOWN ARE ON
PROJECT DATUM.
MEAN SEA LEVEL DATUM =PROJECT
DATUM PLUS 4.0? FT.
BRADLEY LAKE HYDROELECTRIC PROJECT
ALASKA POWER AUTHORITY
RESERVOIR REGULATION-90 MW PLANT
WITH FISH DIVERSION DISCHARGE
~;.. STONE & WEBSTER ENGINEERING CORPORATION
~ ANCHORAGE,ALASKA
PLATE 19
Ul
lL
lJ :;:
0
...J
lL
28CJO
~ 70
' ~ 60
~
b 50
(l: w z w
p
~
1958 1959 1960 1961 1962 1963 1964 1965 1966 1961 1968 1969 1970 1971
TIME STEP (MONTHS l
ENERGY GENERATION
1972
ANNUAL ENERGY GWHRS
AVERAGE 377.7
FIRM 348.0
SECONDARY 29.7
1973 1974 1975 1976 1977 1978 1979 1980 1981 1982
2400
2000
Ul1600
lL
lJ :;:
~ 1200
:;::
BOO
51180Tn,-.-"-----,-----.---r~-----.-----,--~-.--,;.--->T.---,_~----.-----.----.---.~-----.-----,-----,-----,----.---r..-----.---,-rr---,..--.~.---r
~ ~ 1160
w
(l:
~ 1140
(l: w
~ 1120
(l:
j.I:
z 1100
~
g; 1080
0 z w
Ul
1958 1959 1960 1961 1962 1963 196-4 1965 1966 1967 1968 1969 1970 1971 1972 1973 1974 1975 1976 1977 1978 1979 1980 1981 1982
TIME STEP !MONTHSl
RESERVOIR FLUCTUATION
t3000TO-----,-----,-----,-----,-----,-----,----,-----,-----~----,-----,-----,----,-----,-----,-----,-----,-----,----,-----,-----~----~----,-----,---,
w ~2500
<(
-----UNREGULATED FLOW
-----REGULATED FLOW
I
~2000
0 ,..._
~1500
...J
Q.
o6 1000
:;:
9 lL :;::
,..._
w z
3000-
2500-
2000-
1500-
1000-
500-
1958 1959
-
-
-
1960
r-
r-
1961
-
1-
0 IJ(FIMIAIMIJIJ AlsloiNIDI
MONTHS
DISTRIBUTION
RESERVOIR INFLOW
1962 1963
1500-
1250-
1000-
Ul
lL
lJ :;: 750-
0
...J
lL
500-
250-
1964 1965 1966 1967
-
-
DISTRIBUTION
SPILLWAY DISCHARGE
-
-
-
-
-
-
1968 1969 1970 1971 1972 1973
v;
lL
lJ :;:
0 ...J
lL
TIME STEP I MONTHS l
FLOW
1000
750
500
250
o I
:. ~ ~ . . . .
: ~ ~ : ; :
IAIMIJIJ 1 Ais 1o N 1DI
MONTHS
DISTRIBUTION
POWERPLANT DISCHARGE
1974 1975
1180
1160
~ 1140
z
0
,..._<(-
> 1120
w ...J w
(l:
~ 1100
"' w
(f)
1976
·:::
; ~ ~ ;
1917
::;
1978 1979 1980
~ 1080---!-'-"!'"'·~·.,• '~'""' ·~7-'""' ;7-;'"'c ~7"'7"-~'7-"'7--
IJ FIMIAIMIJIJIAislol Dl
MONTHS
DISTRIBUTION
RESERVOIR ELEVATION
1981 19!!2
QMAXIMUM
~:~::~~
NOTE:
ELEVATIONS SHOWN ARE ON
PROJECT DATUM.
MEAN SEA LEVEL DATUM=PROJECT
DATUM PLUS 4.02 FT.
400
10 20 30 40 50 60 70 80 90 100
PERCENT EXCEEDED
MONTHLY
RESERVOIR INFLOW DURATION CURVE
BRADLEY LAKE HYDROELECTRIC PROJECT
ALASKA POWER AUTHORITY
RESERVOIR REGULATION-90MW PLANT
WITHOUT FISH DIVERSION DISCHARGE
~ STONE & WEBSTER ENGINEERING CORPORATION
~ ANCHORAGE. ALASKA
PLATE 20
1196~----~----r-----r-----r-----.-----~----.-----.-----.-----.-----,------r----.
1194~----+-----~----~-----+----~~----+-----~-----+-----+----~~----+-----~----~
::;
~ 1192~----~-----4------+-----~------~----~-----4~----+-----~----~~----~----~----~
0 ...
~ MAX RES EL 1190.6
~ 1190 ........ 0'1---+-----l ~ ~ g
5 ~ ~ ~ 11881-----+------l------+------+------I-----+V'------li"""C,... ......... ""'---t------+------+----+ ~il---+-----l
z ~
0 ~ X ~ ~ ~ ~ 1186~--~---4---+---~-~~F---~--~---+---~--~~---r~'l--4---~ i J,~// ~
« ~--~----~~~~----~--~----+----+----+---~----r----+·~--~--~ ~1184 v -~
·,Rv/ ~
11800 2 4 6 a 10 12 14 16 18 20 22 24
DISCHARGE (1000 X CFS)
SPILLWAY RATING CURVE
1092~--~-----r----~----~--~-----r----,-----r----,-----.!.-_---_.-l--~
MAX TW 10906
I~0~----~----+-----+----~~----+-----~-----+-----4------~---+-~~~~~~0+-~
I ...,.......V ~-~V ~ ~---4-----+----4-----~---4-----+----~----~~~~4-----~---;-~~ 108e I ~~ e-
V Ill 1088·~--~---+----~--4----+----~~~4----r--~----+----r~~
== v~ 0 ~ ::; ~ ~ ~
0 ~ ::;
b 1084~----+----~-----+-----4~~--t-----1------r-----t---~r-----t------ril----~ // ~ « ~ ~ ~ ~ 1082~--~--~---~~-~--~~--~--~~--+----+--~~---+~1----
; i~ w ! 1080 -MAXDIV~
~ 1078 I ~~ t----+---+---+----+---t----+---+---t----+----1
u. zw « ~"' ~ 1076/ il
; ~~ 2:::; 1074~---+--0 ~~--~-----+-----+-----+----~----4-----+-----~----~---4 I ==
1072~----+-----+-----+-----+-----+-----4-----1-----1-----1-----4-----~-----1
1070~----+----~-----+-----4------t-----1------r-----+----~------~----4------1
I06B0!---~2~--~4~--~6---8~--~I0~--~12~--~14~--~~--~1~8--~20~--2~2~--~24
DISCHARGE (1000 X CFS)
UPPER BRADLEY RIVER TAILWATER RATING CURVE
(POST PROJECT CONDITIONS)
26
1100 ,.------.-----..,.------,-----.------,
1098 1---------+-------t------+-------+-v---+---il
1 o96 ~---~M~A~XI~M~U~M~P~O~O~L~E~L~I~09~6~i.sl~------1
I/? 10941-----+-----+------t/+---:-
~ I "' ~ 1092 !~ * v 0 ~ 10901----~--tl ir--i I ==
10881------+-~ ~ I i 1086 ~~----+-~-~~t---~---4
-
-
1180
1170
1160
« 10841--;+-+---"'-l~i--~ -1150
-1140
DAYS
"" I /'~---+--+------1
IOBOHL----+-~--+-----+-----t-----4
./v
-
-
-
-
1018 .. ~--~~------2~----~3~----4~--~ 5
DISCHARGE 1000 CFS
DIVERSION TUNNEL RATING CURVES
15 _39 HT ~_.!..1 --"2=.___,3~_:.4!___,5~__,6~---'7~__,8~__:;9~___,10,___--"11~~12:.__.!!:13~--'-'14~-"'15~-"16"---1!.!7 _ __,;18~-"1"'9--"2"-0--jii.3T HT
SPRING TIDES
1130
1120
1110
1100
1090
1080
8.80MHHWr---fl-ft--tr-frfrfrH-frH-fl-H-.-Jt------------------------------------.--4r--~---141BMHHW
7.99 MHW 3.87MHW
NEAP TIDES
4.021-ti-H-H-+++ttt-ttH-trH-ttll+-llt-t++t+H1Ht-tt~Hf-n,.-H-it-tt-tt-tr-lt-ti-H--+t-tt-tt-+t+ttrtt-H--Io.oo
::;
~
~
Q
b w a
o.oor-tttttt+-hrHrrttrrtttttttttttttttt+MHrr~~~-t1-t1-t1-t1++++t++++-l-+++++-t1++++++++--l-4o2MsL ~
~
u
-8.00 MLW l--tHHHr-tt--lt-tr-trtt--tr+t-tr+t.JL-tr--tr-*----"--------ll---tt--~+-_JH-~+---lt--4-12.02 MUV
~ -9.61 MLLW I-~HH~-\t--l+-f+--trtt--II-+I-...::...+I---H---II-------------...II...-~IJ--H-~I!--ll---4-13.63 MLLW
;::
i
15.61LT~================jt==~=========================================================1 1--19.63LT
MAY TIDAL RATING CURVES
(SEE NOTE I)
w w
!: ...
X
"' j;j
J:
w
0 ;:::
::;
~
~
Q ...
!d
6
IE
~ w w ... -z
0
~ "" w
~ w
«
~ a: w w
"' a:
NOTES
I. TIDE HEIGHTS BELOW EL 6.0 PROJECT DATUM
WILL NOT AFFECT POWERPLANT OPERATION. IN THOSE INSTANCES WHERE TIDE HEIGHT
EXCEEDS EL 6.0 A TAILWATER DEPRESSION
SYSTEM WILL MAINTAIN WATER LEVELS WITHIN THE DRAFT TUBE BELOW EL 6.0.
BRADLEY LAKE HYDROELECTRIC PROJECT
ALASKA POWER AUTHORITY
RATING CURVES
A STONE & WEBSTER ENGINEERING CORPORATION
ANCHORAGE, ALASKA
PLATE 21
115KV LINES
TO BRADLEY JUNCTION
3 1 • I ccv~~l
115KV __/I
SUBSTATION I "' € "'"
t
r 1200A.
TO
PERMANENT
CAMP
OCB
I
I
I
I
~--------~--------~
1200A
I L.A.
CCVT <>---ill CCVT
I ~u~
I Jl OA/FA/FA 33.8/45/56.3 MVA I
('f rn 115KV GRY.-13.8KV;3111,60HZ * ('f ll
L---~-~-----------------~
1 2 1 2
-<B~>---<BE--«::»-?>--
P.T. P.T.
~ 3000 A. ~ 3000 A.
3 3
-<B E-;r:::n-7;
P.T.
SURGE PROT.
3 3 ~~~ -<B~
P.T.
EXC
~""'"'""· ... , ... 1J.8KV,I,60HZ
o.ll5 P.r.----../
SURGE PROT.
~~~
EXC
TO FRITZ
CREEK
BRADLEY JUNCTION
. T / T • N.O.
N.C.~ (N.C.
~
TO BRADLEY LAKE
LOAD CENTER UNIT SUBSTATION
TO
SOLDOTNA
,----------------,
I I
I
I
I
I
I
I
I
I
I
I
I
I
I
4
P.T.
CL
UW 750 KVA
T
13.8 KV-480V
3 ... 60HZ
t
) 1600A.
~
,
CL
I
I
I
I
I
I
u. ..u 750 KVA I
T 13.8 KV-480V I
3 ... 60HZ
P.T. I
2 ~ I
it: I I
I) )._ I
1600A ~ 4 ~ I
I
I 1aoo 1-
1 800A il') il') 800:ooA il') il') 800A I
I f f f f ! L ________________ ~
P.T.
If
i
250 KVA
480V 3JJ
60HZ.
) 800A
BRADLEY LAKE HYDROELECTRIC PROJECT
ALASKA POWER AUTHORITY
MAIN ONE LINE DIAGRAM
J>\ STONE & WEBSTER ENGINEERING CORPORATION
~ ANCHORAGE, ALASKA
PLATE 22
1984 1985 1986 1987 1988
JAN I FEB I MAR APR I MAY I JUN JUL I AUG I SEP OCT I NOV I DEC JAN I FEB I MAR APR I MAY I JUN JUL I AUG I SEP OCT I NOV I DEC JAN I FEB I MAR APR I MAYj_ JUN JUL I AUG I SEP OCT I NOV I DEC JAN I FEB I MAR APR I MAY I JUN JUL I AUG I SEP OCT I NOV I DEC JAN I FEB I MAR APR I MAY I JUN JUL I AUG I SEP OCT I NOV I DEC
f: FERC LICENSE APPLICATION PROCESSING & SUPPORT ACTIVITY
( -o.)
FERC
AWARD
l I I I I I l
r~r-----------P~R~E~PA=R=E~A~PP~l~IC=A~TI~ON~&~O~B~TA~IN~O~T=H~ER~l~IC~E~NC~E~S~&~P~E=R=MI~TS~--------~~~~~------------------------------------------------------~CO=N=TI=NU~E~O~M~O~NIT~O=R=IN~G--~F~E=RC~&~A~GE=N=CY~CO=O=R~OI=NA=T=IO=N~T=HR=O~UG=H~O~UT~PR=
I (
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
I I
: . ,r------------------------------------------------------------------------------..0 MIDDLE FORK DIVERSION o-----------------------, :
! l ( co~~1~~~WoN c~~'n~WoN 1 !
: l :,------~---------------------------------------------------------------------------------------------------~! : ! l r 1 r ~ !
I I : t._ SPR..LWAY I : I ~ COc"JJf~_fJ!rON ~ §liNTR~~1,1~ACT '-----,~-~ (----------------------------------------o(J Q----------..~ ~ ~ ~
!.. DAM, TUNNELS, DIVERSION, ROADS, & BID EVAL !.!." COFFER ) ' ' ) I !v~~----~~c~o~N~n~·~~~T~w~N~r~M~~~~~~~s~-~rn~c~~~~~·~~~·~&wo~•~~~~~--~~-od0-~_,_0_"_8_0bo---~~~-&oF~~~0~J----~"~~=M=c='=~=~~·="-----~~ ~M~~ ~~&~~;-a ~· -----------------------------------~----~, ~~ ~~~-~O
\ I I I I l
I \ ~"[) CONSTRUCTION SUPPORT FACILITIES Q----.. I : I l I I .. L INTAKE TUNNEL I :
l l ORU & BLAST 1 '-------~--, : l
: 1.._ pJ'JE'rt~~~~~S~X~~~~ T1oN INITIAL TUNNEL SECTION ') : ~
II: "[) Cl<~o(}---------()_i Ill ! :
l._ I I RAISE BORE 1..,. INT~~~ffe:R~HAFT SH~~fC~~~EK~Nlfb~~EL, EXCAVATE&: BREACH J ~
'() TUNNEL BORING MACHINE ITBMl -F' ABRICATE &: DEliVER «) 0 POWER TUNNEL EXCAVATION ITBUJ Q INCUNED SHAFT ~ GATE SHAFT &: PORTAL Q ROCK PLUG (Y / ~~~ ~~~ 1 1 ( .. STAll & TEST ·: ~~~ : \.'()GATE SHAFT EQPT (}) : DEMOBILIZ~
' I l CONCRETE LINE POWER ) I :
"{] TUNNEL TO STEEL UNER 0 STEEL LINER &: CONCRETE (}. .-/ : 1
') I :
I I
I I
I I
I I
I I
I I l I
I
I
I
I
I
I
I
I
I I
l'---------------------------------------------------------------,. (r-------------------o{Y) PENSTOCK l ,(}
1 Rl: ONTRACT
1
1 r----o·OWERHO~S. SWITCHYAROo--------------------------r
POWERHOUSE AWARD : ( l i
CONTRACT POWERHOUSE CONTRACTOR I I STEEL I :'--------------------~-·--·--·-t(r--~---------~---------~--~PO=W~E:RH=O=U~SE~E~N=GI=NE:E=RI:NG~&~O=E=SIG=N~-------~~~~--~-------(yOU~T-F~OR __ BD~·~Lr~B=ID~E=VA:l~~·~A~T~~=IA~l~PR~O~CUR~DE~NT~&~~=·=U~Z=E~~K)~)~c=O~NC~R~ET~E~W~O~R~K~'~~lUP~E-RS~T-RU~C~~i~)E----'~~~5~~~~~~~~i~~~t~T~~l~~~~~~~~~----~l~~n
1 (t(J ( ' ' ~ o (~ ~)(~ r~
l l l : l l I I I
I I 1 I I I l \.!(l UNIT 11NSTALL TURBINE & GENERATOR ~START UP
l l l : : : l (~ ( (~ (""'
UNIT 1
COMMERCIAL OPERATION
I
I
: l l l l : l I I I I
I I : : l I I : \.__., UNIT 2 INSTALL TURBINE ct GENERATOR l,~ STAAT UP )
: l ·
1
, 1
1
I l ~~ (r-u I \.J -1,J
I I I I I 1 I
I : \p~EQPT I ,?IAUT~ORIZATION : I I I 1 I I l cWvREB~~~s?~~~R~l~~~S \ AWARO : ~A~}B~~R,_1~$9E : ! l : l : : 1'\~NGINEERING &: DESIG~OUT FOR BID~ BID EVAL\ MODEL TESTS & MANUFACTURER'S DRAWINGS l, J. I TURBINES, GENERATORS, GOVERNORS, SPH VALVES-FABRICATE&: DELIVER /... : l._ 1.._ I
l"-' '-' .g, ( B;EOPT I I I : l I AWARD I : : l
I ~·~~:r~P=OW~E~R~HO~U~SE~C~R~AN=E~E~NG~~~··~""~G~&~O~E~~~~~~~UT~FO~R~B~IDZ)~~B~IO~E~V~~~O~~F=AC=ru~R~E=R'~S~OR~A~M~N~GS{)~)--------------------~P~O~W£~R~HO~U~S~E~C~RA~~~E_:-~F~AB~R~IC=AT~E~&~OE~l~IV~ER~--~~~--------------1rr11 l
I "-' 'f' I I : I I l I ~I '--------------------------------------------0~--A-UX_Il_IA::: .. Ac:YNC:If'-'fo"C.\'"fu"'N~eo~~o;fS::_&!eOR~Ei:;!~:C~T::<G~::_ICO:::_,lD::o~~'-'~'-IP-NE_H_T __ _,rv_) AUXILARY MECHANICAL &: ELECTRICAL EQUIPMENT -FABRICATE &: DELIVER l, ll.f) ~
I ~ (» ~ LJ !
: AUXILARY MECHANICAL &: ELECTRICAL EQUIPMENT ~ l f'-----------~~--------------~EN"Gc:IN~EE~R:ciN~G,_,DC:E~SIG~N~&~P~RO~C~UR~E~ME~N~T------------~'~ :
I I
I I
I I
I I
UNIT 2 COMMERCIAL
OPERATION
PROJECT
COMPLETE
START FINISH
NQr'---•'--c'-'T'-IV-'IT_r ___ NQE
Q -ENGINEERING
@ -ISSUE PURCHASE ORDER
0 -EOPT DELIVERY TO FIELD
0-CONSTRUCTION OR START UP
I I
I I
I I
I I
I I
BRADLEY LAKE HYDROELECTRIC PROJECT
ALASKA POWER AUTHORITY
I I
I I
I I
I I
I I
I ~ I I CONTRACT I I AWARD I
I I ''--------------------------------------------------------~------~~:r----------~T~RA~N=S=MI=SS=IO=N~l=IN=E~E=NG=IN=Ec:ER=IN=G~&~OE=S=IG=N----~-----{}COU=T~F~~~·=IO~{}~BmO~E~VA~l~~=O~~~f}--~TR~A~NS=M=IS=SI=ON~li=NE~C=O=N=ST~R~UC~T=IO~N--~~jr---------------
1984 1985 1986 1987 1988
PROJECT SCHEDULE
STONE & WEBSTER E"'GINEERING CORPORATION
ANCHORAGE, ALASKA
PLATE 23