Loading...
HomeMy WebLinkAboutAPA1279I I I I I I I I I I I • I I I I I I I Q ALASKA POWER AUTHORITY SUSITNA HYDROELECTRIC PROJECT TASK 6 -DESIGN DEVELOPMENT SUBTASK 6.02 -CLOSEOUT REPORT INVESTIGATE TUNNEL ALTERNATIVE FINAL DRAFT MARCH 1981 ACRES AMERICAN INCORPORATED 1000 Liberty Bank Building Main at Court Buffalo, New York 14202 Telephone! (716) 853-7525 --------------·--- I ' I I I I I I I I I I I I I I I I I I ALASKA POWER A~THORITY SUSITNA HYDROELECTRIC PROJECT TASK 6 -DESIGN DEVELOPMENT SUBTASK 6.02 -CLOSEOUT REPORT INVESTIGATE TUNNEL ALTERNATIVE TABLE OF CONTENTS LIST OF TJlBLES • • ~ e • • , ~ • • • • e • • • • • • • • • • • n • • • • • • • • • • • • • • • • • • • • • • • o • • LIST OF FIGURES ···~·~·····················~Q···········••&•••···· L I ST OF PLATES •••••• o •••• o ......... e ••••••••••.•••••••••••••••••••• 1 -INTRODUCTION 1.1-Overview •••••••o••••··································· 1.2 -Devil Car~on Dam and Tunnel Schemes •••••••••••••••••••• 1.3-Report Contents ·········~······················~······· 2 -SUMMARY 2.1-Scope of Work ····················~····················· 2.2 -Conceptual Tunnel Schemes •••••••••••••••••••••••••••••• 2.3-Tunnel Design and Construction Considerations •••••••••• 2.4-Screening of Conceptual Tunnel Schemes ••••••••••••••••• 2.5 Preferred Tunnel Scheme ············~··················· 2. 6 --Comparison with De vi 1 Canyon Dam Scheme •• \H ......... o ••• 2.7-Conclusions and Recommendations ......................... . 3 -SCOPE OF WORK 3.1 -Study Objectives • • • 0 • • • • • • • ~ • • • • Q • • • 0 • • • • • • • • • ~ • • • • • • • • 3.2-Approach .,. •••••••••••• 0 ••• , ............................. . 4 -CONCEPTUAL TUNNEL SCHEMES 4.1 -Economics of Tunnel Schemes within the Susitna Basin •••••••••••••••••••••••••••••••••••••••••••••••••• 4.2-Conceptual Devil Canyon Tunnel Schemes .................. .. 4.3 -Scheme 1 ••••••••·~·····••••••••••••••••••••••o••••••••• 4.4-Scheme 2 ············································~·· 4.5 -SchemR 3 ............................................... . 4. 6 -Sc h ente 4 •••••••••••••••••••••••••••••••••• o ••••••••• ., •• 4.7 -Historical Precedence .................................... . 5 -7UNNEL DESIGN AND CONSTRUCTION CONSIDERATIONS 5.1-Geologic Setting ••••••••••••••••••••••••••••••••••••••• 5.2-Geotechnical Design Aspects ••o••·················~····· 5.3 -Seismic Considerations ••••••••••••••••••••••••••••••••• 5.4-Design Considerations .................................. . 5. 5 -Construction ~let hods .................................... . i iii iv v 1-1 1-1 1-2 2-1 3-1 3-l 4-l 4-1 4-2 4-3 4-3 4-3 4-3 5-1 5-2 5-3 5-4 5-5 I I I I I I I I I I I I I I I I I I I ----~--~-----------------.,.~---. ------------.------ ALASKA POWER AUTHORITY SUSITNA HYDROELECTRIC PROJECT TASK 6-DESIGN·OEVELOPMENT SUBTASK 6.02 -CLOSEOUT .. REPORT INVESTIGATE TUNNEL ALTERNATIVE TABLE OF CONTENTS (Cont'd) 6 -SCREENING OF CONCEPTUAL TUNNEL SCHEMES 6.1-Introduction ·································~·····~··· 6.2 -Tunnel Scheme Costs ...................................... "'. 6. 3 -Power and. Energy ..................................... .,. ••• 6.4-Environmental Considerations .......................... ~. 6.5-Geotechnical Considerations ..................... "' ••••••••• 6.6-Preferred Tunnel Scheme···········~············~······· 7 -PREFERRED TUNNEL SCHEME 7.2-Design and Operational Assumptions ••••••••••••••••••••• 7.3-Project Description ••••tt•••········· .. ······/!1 ........... . 7.4 -Cost Estimate and Construction Schedule ••• IIOOOO(!Oeoooo• 7. 5 ~-Power and Energy .......................... -•••••••••••••• ". 7.6 -Environmental Impact Assessment ..................... ~·~·· 8 -COMPARISON WIT'i DEVIL CANYON DAM SCHEME 8~1 -Economic Cow.parison ..................................... . 8.2 -Environmental Comparison ···············~·~;············· 8.3 -Comparison of Construction Schedules ···············••o• 8. 4 -Summary ••••••••••• " ••••.•• a •••••••• .., .... = * ................. . 9 -CONCLUSIONS AND RECOMMENDATIONS 9.1 -Conclusions •••••••••••••••• ., ........................... . 9.2 -Recolll!nendations •••••••••••••••••••••••••••••••••••••••• BIBLIOGRAPHY PLATES APPENDIX A -ROCK UNIT DESCRIPTIONS (40) ii Page 6-l 6-1 6-1 6-2 6-3 6-4 7-1 7-1 . 7-2 7-2 7-3 7-3 8-1 8-2 8-2 8-2 9-1 9-1 I II LIST OF TABLES I Number 4.1 I 4.2 I 4.3 5.1 I 5.2 I 5 .. 3 5.4 I 6.1 I 6.2 I 6.3 7.1 I 7.2 7.3 I 7.4 I 7 .. 5 I 8.1 8.2 I I I I I Title Page Assumptions ftJr Tunnel Site Comparison Index . . . . . . . . . . . . . 4-5 Information on the Devil Canyon Dam and Tunnel Schemes . . . 4-6 Historical Tunneling Precedence . . . . . . . . . ~ . . . ~ . ~ ~ ~ . . . . . . . . 4-7 Geo 1 ogic StrtA~:·ture uf Reg ion Between the Devil Can~_,on and Watana Dam S·ites • • . . • • • . • • • • • • • . • • • • • • • • • • • • • • • • . . • • . 5-8 Effects of Se !"5mic Loading on Tunnels (11) . . . . . . . . . . . . . . . 5-9 Tunnel Cover Experience •••••••.•.••...••.•••....••......• 5-10 Regional Geology fr'iap Units ............................... 5-11 Assumed Tunnel Support . • . • . • • .. . . . . • .. . • . . • • • . . . • • • • • • • • • . • 6-5 Devil Canyoit Tunnel Schemes -Costs, Power Output and Average Annual Energy • • • . • .• • • . . • • • • • • • • • • • • . • . • • . • • . • • • . . 6-6 Litho logy of Tunne 1 Routes • • • • • • .. . . • . • • • • • • • • • . • • . . . • .. • . • 6-7 Drilling Results at Watana and Devil Canyon Dam Sites ••.• 7'""6 Optimization of T4nnel Diameter • . • • • . • • • • • • • . • • • • • . • • • • • • 7-7 Cost Estimate for Devil Canyon Tunnel Scheme (Two 30- Font Diameter Tunnels) •...••...•.•...• , ••..••.•••••.•••.• i-8 Cost Estimate for Dev i 1 Canyon Tunne 1 Scheme (One 40- Foot Diameter Tunne 1) • • . . • • • • . . • . • • . . • • . . • • . • . • • . • . • • • • • • 7-9 Power and Energy Produce ion from Tunnel Scheme .•.••••••• e 7-10 Summary of Economic Eva 1 uat ions (Mi 11 ion Do 11 ars) • • . . • • • . 8-4 Summary of Economic Sensitivity Evaluations (Mill ion Do 11 ar s ) . .• • . • . . . . . . . . . . . . e • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • a .. 5 i i; . I I I I I I I I I I I I I I I I I I I LIST OF FIGURES Number L.l 4.1 4.2 5.1 5.2 5.3 5.4 5.5 5 .. 6 6.1 7.1 8.1 Title Tunnel Alternative Vicinity Map .........•............... Economic Potential of Tunnel Schemes ................... . Schematic Represent at ion of Conceptua 1 Tunne 1 Schemes ... . Plate Tec~onic Map (Reproduced from Reference 43) ...... . Regional Geology with Tunnel Routes (Reproduced from Reference 43) ..... 0 ....................................... . Boundary Fault and Significant Feature Map for the Site Region (Reproduced from Reference 43) ·······••u•··· Devil Canyon Area Significant Feature Mao (reproduced from Reference 43) . . . . . . . . . . . . . . . . . . . .. . ............... . Devil Canyon Site Significant Feature Map (reproduced from Reference 43) .......... ~ ..............•............. Watana Site Significant Feature Map (Reproduced from Reference 43) . ., ................... ., ............ o •••••••••• Typical Daily Power Produ«:tion for March ....... • ........ . Construction Schedule Preferred Scheme 3 . . . . . . . . . . . . . . . . Construction Schedule Comparison .•. 0 •••••••••••••••••••• iv I • • ~ ..... ~" . ·~ . . I • • ;o, Page 1-3 4-8 4-9 5-12 5-14 5-15 5-16 5-17 6-8 7-11 8-6 I I I I I I I ,. ' I I I I I I I •• I I I LIST OF PLATES .. Number 1 T ·t·l _ 1 e 2 3 Conceptua 1 Tunne 1 Schemes -Plan & Sections Preferred Tunnel Scheme 3 -Plan Views Preferred Tunnel Scheme 3 -Sections v I I I I I I I I I I I I I I I 'I I I I 1 -INTRODUCTION L.l -Overview Subtask 6~02 of Task 6 Design Development studies for the Susitna Hydr·oelectric Project is entitled "Investigate Tunnel A1ternative 11 -. The scope of this subtask as ·originally defined in the Acres American Inc. POS dated February 1980, was expanded in the revisions to the POS issued in September 1980o The objective of the Subtask 6. 02 study is to undertake a preliminary assessment of the feasibil- ity of using a major tunnel to develop hydroelectric power on the Susitna-River between the proposed Watana and Devil Canyon dam sites (see Figure 1.1). The scope of work i nvo 1 ves essentially a desk study uti 1 i zing av a i 1 ab 1 e data. The limited specific geologic or geotechnical information available along the tunnel,,route will a11ow no more than a conceptual assessment of the feasibility of excavation of tunne-ls in the geologic structures adjacent to the Susitna River in the region considered. Thus the assessment of the structural desi~n requirements and the determination of feasible size and cost of such tunnels has necessarily been based on Acres engineering judgement and experience at this time. It is considered unlikely that goetechnical conditions would be so poor that tunnels could not be excavated by some means in the region under considera- tion. Nevertheless it is important to note that the worse the conditions, the higher the cost will be. Estimates based substantially on judgement and experience, however good, will be subject to the uncertainties.of the basic assumptions used. To establish the technical and economic feasibility of a tunnel alternative,. a substantial amount of field geotechnical investigation, design, and construction cost estimating and schedu 1 ing work waul d be required. Notwithstanding the foregoing constraints, the study has been .tiirected towards assessing whether or not there are sufficient grounds to consider the tunnel option in more detail as a potentially economic, technical feasible and environmentally sound alternative to the Devil Canyc··~ development. This report presents the results and conclu- sions of this study. 1.2 -Devil Canyon Dam and Tunnel Schemes The Watana-Devil Canyon \:!am scheme is compriseJ of two major dams, Watana and Devil Canyon (Figure 1.1) .. As currently envisaged, Watana is a 840-foot high gravel and rockfill structure with a crest elevation at 2225 feet and an 800 M\~ undernround powerhouse. The full pool surface area of Watana reservoir is 43,0QO acres and full pool storage volume is 10 million acre-feet. The large storage volume allows regulation of river flows on bL·th a seasonal and yearly basis. The Devil Canyon dam is a 625-foot high concrete arch structure with a crest elevation of 1464 feet and a 400 MW underground powerhouse. The Devil Canyon dam has a full pool storage volume of 1 mi 11 ion acre-feet and the reservoir surface area is 7600 acres. o A 1 arge power tunnel could be utilized to develop the head below Watana instead of the Devfl Canyon dam. C.anceptually, this Devil Canyon tunnel scheme could be used to develop either the total head of both dams or just that portion develop- ed by the Devil Canyon dam. This could be achieved by locating the !11take works either in the Watana reservoir or at some point downstream from the Watana dam ... Based on init~a1 co~ceptui!l desi_gn corysiderations, a typical tunnel scheme would comprise the foll:aw1ng ma,Jor componen1:s: 1-1 I I I I I I I ., I I I I I I I I I I. ·- Power tunnel intake works. - A re-regt! 1 at ion dam if the i nta.~e works are 1 ocated downstream f~om Watana, with a small hydroelectric development to utilize the available head and flow. - -One or two power tunnels <'f up to forty feet in diameter and up to thirty miles in 1 ength. -An underground powerhouse 1 .ith a capacity of_up to 1200 MW located in the· vicinity of the Devil Canyon dam site., la3 -Report Contents Section 2 of this report is a summary of the work undertaken and conclusions and recommendations. Section 3 is an outline of the scope of work. The four basic conceptual tunnel schemes considered are described in Section 4 and the screen- ing process used to select the preferred scheme is outlined in Section 6. An overview of the site geolos.,v and geotechnical design considerations are dealt with in Section 5. The preferred tunnel scheme is described and analyzed in more detail in Section 7 and compared to the Watana-Devil Canyon dam scheme in Section 8. Conclusions and Recommendations are presented in Section 9. 1-2 --------.... ----------' '12 FOG CR. LEGEND i A . ' I .t. DAM SITES 0 5 !!5 ,_., SCALE IN MilES i TUNNEL ALTERNATIVE VICINITY MAP FIGURE tl I I 2 -SUMMARY ( To be written after approval of draft. I I I I I I I I I I I I I I I I . 2-1 I I I I I I I I I I I I I I I I I I I, 3 -SCOPE OF WORK l.l -Study Objective The objectiv~s of this study are to investigate the feasibility of replacing the currently proposed Devil Canyon dam project with a tunnel-supplied power plant fed from the Watana dam site. 3.2 -Approach To satisfy the study objectives, the work was organized and carried out in the following manner: -Four basic conceptual tunnel schemes were developed to investigate alterna- tives for utilizing the available head between the Watana and Devil Canyon dam sites~ -The available Information on tunnels of similar size previously constructed elsewhere in the world was reviewed and summarized. - A general evaluation of the topography, geology~ and seismicity of the area was undertaken on the basis of the available information. -Preliminary assessments v1ere made of geotechnical and structural design assumptions and criteria for use in evaluation and comparison of alternatives. -A preliminary assessment of costs, energy yields, and environmental impact associated .with the conceptual tunnel schemes was undertaken. -Based on the information developed abov:2, a single scheme was selected as a tentative optimtm for further study. This, more! detailed study, included: • 0 Develo(l11ent of preliminary engineering layouts. More detailed assessment of capital costs and development of construction schedules. Monthly ·simu1 at ion of power and energy yields utilizing a computer model. Pre 1 iminary environmental impact assessment. -The selected tunnel scheme was compared with the Devfl Canyon dam alternative on the basis of technical, economic, environmenta.l and construction schedule considerations. -The study was completed with the development of conc1us1ons on the viability of the tunnel scheme and recorrmendations for further consideration of the scheme as an alternative for inclusion in Susitna Basin development planning studies. 3-1 ' 4 -CONCEPTUAL TUNNEL SCHEMES 4 .. 1 -Economics of Tunnel Schemes Within the Susitna Basin In order to put the Devil Canyon tunnel scheme into perspective. a brief study was undertaken to assess the relative economics of tunnel schemes located in v.:;.t"'ious portions of the basin. An essential part of a tunnel scherrte is an upstream reservoir for seasonal and yearly flow regulation. Initially, the Watana and Vee dam sites (see Figure 1.1) were selected as potential upstr~am reservoir sites at which tunnel intakes would be located. An appropriate index for initial comparison of alternatives was derived on the basis of the estimated energy yield in kWh per cubic yard of tunnel excavation for each alternative. The basic assumptions used in this analysis are shown in Table 4.1. The energy yield was evaluated using the average annual discharge less 500 cfs compensating . flow, and the net head allowing for friction losses. Preliminary studies indicated that minimum cost of energy occurred at flow velocities ranging from about 5 to about 7. 5 feet per second. For preliminary study purposes a uniform velocity of 6 feet per second was adopted. Estimates of kWh/yd3 for the alternatives considered are illustrated in Figure 4.1, from which it is evident that the first 12 miles of a tunnel starting at Watana has lower economic potential than the lower portion from Devil Creek downstream to Portage Creek. The curves also indicated that the economic potential of a tunnel scheme down- stream from the Vee dam site is much lower than that between Devil and Portage Creeks. The third curve on Figure 4.1 indicates the economic poten~ial of a tunnel starting from .a re-r~:gulation dam loca·::.d downstream from Watana and just upstream from Devil Creek. As outlined in the following section, this re-regulation dam was ultimately chosen as the site for the intake in one of the tunnel schemes. 4.2-Conceptual Devil Canyon Tunnel Schemes All tunnel schemes considered assume that Watana (maximum water surface eleva- tion 2200 feet} with an 'installed capacity of 800MW is the project's first stage of development and that ;a minimllll of lOO'J cfs compensation flow is required in the Susitna R1ver downstream frotl: Watana at all times., Four iJasic tunn.el schemes were selected for study. These involve utilizing either the full head represented by hath the Watana and Devil Canyon dams or just the head represented by the Devil Canyon dam and two basic operating modes, i.e. peaking and base load power generation. The installed capacities for the schemes are all based on a total Susitna Basin development plant factor of between 50 and 55 percent. These schemes are depicted in Figure 4. 2 and are as follows: 4-1 I -I I .I I I I 'I I I :I I I •• .I I I ;I I I I I I I I I I I I I I I I I I ·I I I (a) Scheme 1 This scheme involves the development of head between the Devil Car,yon dam site and Watana and incorporates peaking operation of the tunnel power- house. (b) Scheme· 2 As for Scheme 1 except that the full head, including that avai·lable at the Watana dam, is utilized. (c) Scheme 3 This scheme involves the development of head between the Devil Canyon dam · site and Watana and incorporates base load operation. (d) Scheme 4 As for Scheme 3 except that full head, including that available at Watana dam, is utilized. Schemes 1 and 3 require a secondary dam downstream of Watana to re~regulate Watana releases and to control the water level at the tunnel intakes. For Scheme 1 this re-regulation dam requires relatively little storage as the two pow_erhouses operate essentially in series, i.e. they both peak simultaneously. This can be proviJeci by a small re-regulation dam ·located some 2 miles downstream from Watana. Re-regu 1 at ion storage requirements for Scheme 3 are much grea cer. To a 11 ow peaking operations from the Watana reserve ir and base 1 c·ad o~·erat ion of the tunnels requires a substantially larger volume. A brief economic study revealed that this could best be provided by a re-regulation dam located some 15.8 miles downstream from Watana. This site appears to be suitable for dam construction and is located immediately upstream from the reach from Devil Canyon to Portage Creek with higher economic tunnel potential, as discussed in Section 4.1. The savings in tunnel cost at this site more than compensate for the increased height of the re-regulation dam located this far downstream from Watana. ~more detailed discussion of the tunnel schemes is presented in the following sections. Table 4. 2 summarizes pertinent information on each of the schemes which are i 11 ustrated on P 1 ate 1." 4.3 -Scheme 1 (Devil Canyon Head, Peaking Operation) Scheme 1 consists of the Watano. dam with an 800 MW powerhouse and a re-regul a- t ion dam approximately 75 feet in height located two miles downstream. The tunnel intake works are located just upstream from the· re-regulation dam and a 550 MW powerhouse is located in the vicinity of Devil Canyon. Tunnel length is about 27 miles. A minimum compensation flow of 1000 cfs is provided between Watana and Devil Canyon. The re-regulation dam•s storage capacity is that "" 4-2 required fo~ the powerhr.uses to operate in serieso For preliminary study purposes it has been assumed that sufficient storage to absorb approximately one hour of peak power discharge from \tJatana will be necessary. This requires 1,600 acre-feet of storage. Peaking operations will create daily water ·level fluctua- tions downstream from the Devil Canyon powerhouse, v-1hich will probably require regulation. 4.4 -Scheme 2 (Full Head, Peaking Operation) Scheme 2 consists of the Watana dam and power tunne1 intake works located upstream of the damo Two tunnels, 29 miles long will discharge at a 1150 MW powerhouse at De vi 1 Canyon. Upon completion of the tvr.nel stage of the over a 11 prGject, the Watana powerhouse capacity will be reduced from 800 MW to 70 MW, just sufficient to release the required minimum compensation flow. Base load and peak power demands will be generated at the Devil Canyon powerhouse. Water level fluctuations downstream of Devil Canyon are s·imilar to those of Scheme 1 • 4.5 -icheme 3_1Devil Canyon Head, Base Load Operation)~ Scheme 3 consists of the Watana dam with an 800 1M powerhouse and a re-regula- tion dam approximately 245 feet in height locat€:d 15.8 miles downstream fr·om Watana. The tunnel intake works are upstream of th~ re-regulation dam with a 300 MW powerhouse in the vicinity of Devil Canyon. fhe re-regulation dam has a storage capacity of approximately 350,000 acre-feet. A maximum v1ater level fluctuation of four feet is sufficient to store the daily peak discharge from Watana and release a constant discharge into the power tunnels. Watanats 800 MW pO\t~erhouse wi 11 be operated as a peaking hydro ·faci 1 ity discharging into the re-regu1ation res"rvoir. Devil Canyon•s 300 MW powerhouse: will be operated as a base load faciliiy, and thus, no significant daily water level fluctuation will occur downstream~ A re 1 at i ve 1y sma 11 powerhouse with a capacity of 30 M~l wi 11 f?e constructed at the re-regulation dam. A minimum flow of 1000 cfs will be passed through the re-regulation dam powerhouse to supply the required downstream compensation flow. 4.6 -Scheme 4 (Full Head, Base Load Operation), The general layout of Scheme 4 is similar to Scheme 2 with the following opera- tional changes. The Watana powerhouse will remain at 800 MW and meet peaking requirements. During off peak ·periods a constant base load of 35 MW will be genel'·ated at Watana while satisfying compensation flow requirements bet\-Jeen Watana and Devil Canyon. Th2 Devi 1 Canyon 365 t4W powerhouse and tunne 1 wi 11 be operated as a base load facility. The full head potential for the entire flow is not developed in Scheme 4, and thus annual energy production is less than the other schemes. Daily water level fluctuations downstream of Devil Canyon are similar to Schemes 1 and 2, and large water level fluctuations between Watana and Devil Canyon wi'Il occur. 4.7 -Historical Pre·cedence In crder to obtain a perspective of the tunnel scheme in terms of world wide historical experience, a brief review of other tunnel schemes was undt:rtaken. The results of this r·eview are sumJ11arized in this section. 4-.3 I I I .I I :1 •• 'I I I '.I I ~. •• ;I I I I •• I . I I I I II I I I I I I I I I ~ • •• •• ~ •. I Table 4.3 compares on a greai;ely abbreviated basis, the Susitna tunnel alternative with several other projects. It is clearly evident that the propos~d tunnel concept at Susitna is unique. However, it is important to note that tunnels of similar size, length, purpose, and located in similar geology have been successfully completed. The Susitna tunnel alternative is definitely within the state of the art. Larger and longer tunnels have been driven in more complex geologi: settings. , . 4-4 I I •• I I I I I I I I I I I I I I ' TABLE 4.1: ASSUMPTIONS FOR TUNNEL SITE CO~PARISON INDEX - - (1) The tunnel powerhouse operates as a base load facility. (2) Straight line tunnel alignments between the dam site and the tunnel tail rane. (3) Tunnel jischarge is the average annual discharge less 500 cfs compensation flaw. ( 4) Tunnel size is based on an average flow velgpi.tcy of six feet per second and one power tunnel.. • (5) Average net head equals the gross head less head losses due to friction. (6) Gross head is the difference between the dam tailwater level and the tunnel tailwater level. (7) Averr.ge head loss is based on a flow velocity of six feet per second and a mam1ing n of 0.026. 4-5 II t I J I I 1: •. - I ._.. I I I •• I ' I I I I I I TABLE 4.2: INFORMATION ON THE DEVIL CANYON DAM AND TUNNEL SCHEMES Devil Canyon Tunnel Schemf! Dam 1 4 -- Reservoir Area (Acres) 7,500 320 0 3,900 0 River Hiles Flooded 31.6 2.0 0 15.8 0 Tunnel Length (Miles) 0 27 29 13.5 29 Tunsel Volume (Yd ) · 11,976,000 12,863,000 3,732,000 5,131,000 Compensating Flow Helease from 5001 Watana (cfs) 0 1,000 1,000 1,000 Oownstream 2 ~eservoir Volume (Acre-feet} 1,100,000 9,500 350,000 OoMtst ream Oa~ Height. (feet) 625 . 75 245 Typical Daily Range of Discharge 6,000 From Devil Canyon 4,000 4,000 8,300 3,900 Powerhouse to to to to to (cfs) 13,000 ':4,000 14,000 8,900 4,200 Approximate Maxirum Daily Fluctuations in Downstream Reservoir (feet) 2 15 4 i 1,000 cfs compensating flow release from the re-regulat.ion :dam. Downstrean from Watana. 3 Estimated, above existing rock elevation. 4-6 TABLE 4.3: HISTORICAL TUNNELING PRECEDENCE Project Length Excavati~n Maximum Static Name Location ~ (miles)' Shape Diameter Rock Method Depth Head b!ning TARP Chicago Sewer Approx. Circular 18 7t-35 ft Dolomite TBM Approx. Partially C0..'1crete 140 .300 ft lined Kemano British Power 10.1 Modified 25 ft Igneous and D&B 2200 ft 2585 ft Approx. 1}3 u:;qined, Columbia Horseshoe metamorphics 1/) concrete li~ed and 1/3 lined with rock bolts and shot- crete Snettisham Alaska Power 1.9 t-kldified 13.5 ft Quartz-dorite, D&B 1200 ft Approx. 87 percent oolined, Horseshoe Gneiss, Biotite~ 900 ft supported ldth rock Schist bolts, 1 J pe:r~ent supported ~ith rock bolts and ~crete Bersimis 1 Quebec Power 7.6 Modified 31.0 ft Gneisic and D&B BOO ft 875 ft Concrete lined, Horseshoe Granitic entire length Bersimis 2 Quebec Po we~: 0.5 Cirt!ular 36 ft Gneisic and D&B N 367 ft Concrete lured .f::oo Granitic .I .....; Chute-des-~..,-dbec Power 5.6 Modified 34.3 ft Gneisic and DAJ.!, N 640 ft Concre.te lined Passes Horseshoe Granitic Chute-deE::t-Quebec Tail 1.7 Modified 46 ft Gneisk and D&B 250ft N Unlined Passes Horse!'lhoe Granitic Paijanne Sweden Water 72 Horseshoe 26.4 ft Granite. Gneiss D&B N N Unlined Supply Oa."le Sou~h Power l..6 Circular 24 ft Clay-Shale iBM N 210 ft, Concrete litred Dakota (2 tunnels) 2.8 Circular 24 ft Clay-Shale TBM 272ft Eklutna Alaska Power 4.5 Circular . 9 ft Argillite, N N 74ft Concrete lined Graywacke Bath Co. Virginia Power Approx. Horseshoe 32 ft Shale, Sandstone D&B N N Concrete lined 4 Susitna Alaska Power 13.~ or Modifierl 25 ft-40 ft Argillite, Gray-O&B Approx. 600 ft Suggest same as (Tent a-29 Horseshoe wacke., Granite, 2000 ft to 1300 Kemano for study tive) Granodiorite ft purposes 1 ABBREVIATIONS: TBM -Tunnel Boring Hachine D&B -Drill and Blast N .:. Not Known 0 I ' ' ~ I ' I I I I I 11 it J ,, I ~- II I I I I I • 1 X lJJ 0 z -1 <( .. 0.6 ..... 0.5 0.4. 1-z LJJ 6 ~0.3. a. vo3 0 ~ 0 z 8 I.1J 0.2 0.1 :tt! w w a: (,) z i 0 4 11.1 0~01 '----""'' ---L.' --....&..' __ ...., .. •' __ ....... , __ ....... , r-_0_., __ __., o s 10 H5 20 25 30 as 40 TUNNEL LENGTH (MILES} LEGEND TUNNEL. INTAKE WORKS IS.\·: RE'-REGULA.HON DAM S!TE LOCAT ) JUST UPSTREAM FROM DEVIL CREEK -· -WATANA DAM SlTE ---VEE DAM SITE ECONOMIC POTENTIAL OF TUNNEL SCHEMES 4-8 ii I t I I I I I I I I I I I I I I I t I I 2200 FT. WATANA 800 MW --+--2 MILES :--J475 FT. ,....__..._._ RE-REGULATION DAM 3S Ft. DIAMETER 800 MW-70MW 2 TUNNELS 38 FT. DIAMETER 550 MW 1150 MW -----RE-REGUI..ATI~~ DAM 30 MW 30 FT. DIAMETER 800 MW 365 MW 24FT. DIAMETER SCHEMATIC< REPRESENTATION OF . CONCEPTUAL TUNNEL SCI-!' 'ES 4-9 TUNNEL SCHEME # 2. 4. FfGURE 4.2 I I I I I I I I I I I I I I I I .t I I 5 -TUNNEL DESIGN AND CONSTRUCTION CONSIDERATIONS 5.1 -Geologic Setting Determining the geology along the tunnel alignment is critical in predicting tunneling conditions, methods! and costs. The information acquired to date includes several regional geology reports, site specific geology for the Devil Canyon and Watana dam sites, and the findings of the Woodward-Clyde Consultants' (l~CC) 1980 Seismicity Study {43). The Susitna project is located in a tectonically active and geologically complex region. Subduction of the Pacific plate under the North American plate (Figure 5.1) has resulted in forces which have folded, faulted, thrusted, sheared, differentially uplifted, metamorphosed and intruded the area. The most common geologic structures encountered include folds, faults, shear zones, joints, flow foliation, stocks, dikes, and plutons~ (a) Litho 1..Q.9x_ As shown on Figure 5.2, three main lithologic units are crossed by the tunnel alignments: -Argillite-Graywacke; Biotite-Granodiorite; and Schist, Migmatite~ and Granite. ~ The Argi1'1ite-Graywacke Unit (Kag) has undergone complex folding with a well developed axial plane cleavage and numerous quartz stringers. The argillite is dark gray to black and in some areas has metamorphosed to a slate OY" fine-grained phy11 it e.. Tests performed by the USBR for samples taken at the Devil Canyon site ·indicate ·~ts unconfined compressivg strength ranges from 12,900 to 16,850 psi, Young's modulus averages 9 X 10 psi~ and Poissons' ratio averages 0.17. The Graywacke is dark to medium-gray, fine to medi urn grained, and is inter'- calated with the argillite in graded beds ranging in thickness up to 16 feet. It comprises between 30 percent and 40 percent of the Ar gi 11 ite- Graywacke Unit. Tests performed by the USBR indicate its unconfinec_ com- pressive strength6ranges between 28,540 and 36,570 psi, Young's mo:\alus averages 9.8 x 10 psi and Paissons' ratio ranges between 0.15 and 0.2.5 .. The Biotite-Granodiorite Unit (Tbgd) is described as light to medium-gray, medium to coar·se grained intrusive rock with a granitic texture. Biotite is the chief mafic mineral~ but hornblende is occasionally present. Although no test data is available, the average static properties for this type of rock are generally be 1 i eved to be an unconfined compress i ve 6 strength between 20,000 and 30,000 psi, Young's modulus about 8 X 10 and a Poissons' ratio of 0~2* The Schist, Migmatite and Granite Unit (Tsmg} can be described as undiffer- entiated terrain of relatively high grade pelitic schist, migmatite and small granitic plutons occurring in approximately equal proportions with gradational contacts. Again, no static properties are known for this unit, but the granite and migmatite properties are probably similar to the granodiorite. The schistose rock properties will vary wit.h the direction they al"e loaded and wi11 probab~y demonstr .::te a wide range of values. It is important to determine t~1e properties of this unit and the percentage of tunnel through it. A poor quality schistose rock may present major problems to tunneling operations • • A complete descl"iption of these units is included as Apper.dix A (40). (b) Structure As mentioned earlier, the geologic structure in this region is complex. The major structural -crends are NE-SW and NW-SE and major faults trend NE-SW. Results of outcrop mapping between Dev i1 Canyon and Watana are shown in Table 5.1 .. (c) Topography The topography is gener·ally rugged along the tunne 1 alignments, and the geologic· structure exerts some topographic control. Elevations vary . between 1300 and 3500 feet. Topographic lows, such as the locations of streams and creeks, are areas of concern. They may represent ~;ones of poorer rock quality and may require that tunnels be structural-ly 1 ined to meet stability and cover requirements. (d) Lineaments As part of the wee study, sever·al 1 ineaments were mapped which cross the tunnel routes. These are shown on Figures 5. 3 to 5. 6. rnese 1 ineaments are considered significant for further investigations due to their charac- teristics and possible problems in tunneling through them. Other lirtea- ments may exist along the tunnel routes which were not identified due to their distances from the dam sites. A more detailed investigation is required if the tunnel alternative studies are continued as a preferred scheme. 5.2 -Geotechnical gesign Aspects I Potential geotechn,·~.~al problems and their impact on the tunnel schemes are reviewed in thi.s section. Geotechnical design and hence the cost and construction schedule for a tunnel is heavily dependent on evaluation of the geology along the potential routes. The major tunneling problems are created by fau·lt and shear zones, joint sets, lith- ologic contacts, water and gas. It is normally not economica1ly feasible to undertake a comprehensive exploration program for the entire route. Therefore, reconnaissance, mapping, and exploratory work must be directed towards locating all potential problem areas and these ·must be. evaluated in detail. Fault and shear zone!: may create severe problems. Special tunneling techniques and h~avy supports may be required and decreased production rates during con- struct ion can be expected in these areas. If the 1 ineaments identified by wee prove to be fault and/or shear zones, l.he tunnel alignments will probably have 5-2 • .r_. • .. . • • . . . ~ ~ \ ' . . ~ . I I I I f I I I I I I I I ' I I I I I I I I ' I I I I I I I I I I I I I I I I I. to be adjusted to avoid or minimize the impact of these features. The shortest route across these zones is preferred. Topographic lows such as Devil Creek, Tsusena Creek and other creeks and str\'~ams may indicate weak zones. Drilling and seismic refraction survey techniques .\\,ill be required to determine the properties of the 1 ineaments and topographic lows. A 1 imited amount of outcrop geologic mapping has been used to align the routes at this time. Tunnel alignments have been oriented to cross the joints to detre:~se support requirements and to help control overbreak. Lithologic contacts may also present several problems. ,·f the contact is sharp and fresh, no structural problem may exist, but production rates may change and tunne 1 ing methods wi 11 have to be adjusted for the new rnck. Prob 1 ems wi 11 also be encountered if the contact is sheared or brecciated. Special designs are required if these contacts contain unconsolidated material and these contacts may also be a source of water which can create serious difficulties. Many joints in the Watana and Devi1 Canyon drill cores are tight and healed. Down- hole permeabil ities vary but average less than IQ-5 em/sec be·low the weathered zone. If this rsmains true along the tunnel alignments, water should nut be a problem. Gas can create both health and safety problems, i.e. asphyxiation and/or explo- s·~on. Gas is not usually a problem in the lithologies present and good ventila~ tion will probably eliminate any potential problems. · 5.3 -Seismic Considerations There are several ways an ea,' thquake may adversely effect a tunnel. Three common sources of damage are displacement, shaking, and ground failure. Displacement is U$Ually associated with serious damage and is considered the most severe nroblem. Small mov·ements along discontinuities are generally not cr.,itical and only minor damage may result. However, displacements of several feet can lead to serious damage. Shaking may cause cracking, rockfalls, or possibly collapse. Dynamic stress concentrations occur which increase static loadings and may result in damage. Ground fa i 1 ure inc 1 udes liquefaction and 1 ands 1 id ing. These types of fa i 1 ures may not damage the tunnel itself, but may seriously damage portal areas, and thus, effect the tunnel use. Dowding and Rozen (11) studied the effects of seismic loading on tunnels. Based on 71 tunnels throughout Japan, Alaska, and California, they developed a corre- lation between peak motion, particle velocity and observed damage~ Table 5.2 summarizes their findings. They concluded that earthquakes expected to cause hea·Jy damage to surface struc- tures cau.···~ only minor damage to tunnels. Peak motions for earthquakes usually occur in 1... ~ 0. 4 to 10 Hz range. These low frequencies are several orders of magnitude. lower than the natural frequencies of tunnels and not likeJy to create diffel'·ential acceleration and damage to tunnels~ Lined and grouted tunnels are less subject to damage than unlined ones. Under simi1a·. sei.smic loadi,ngs an 5-3 unlined tunnel may experience rockfalls while a lined and grouted tun-nel may experience only minor cracking. · Seismic design considerations for tunnels usually include: -Avoiding faults which may experier~~~ large displacements during an earthquake. -Supporting, 1 in ing ~ and grouting areas of poor rock qua 1 ity. -Adequately designing portals for seismic loadings. The preliminary indications from the WCC studies indica:te that the Benioff Zone may produce tne controlling or design earthquake in the vicinity of the Watana and Devil Canyon dam sites. The design earthquake would, thus, be as high as 8.5 magnitude event (Richter Scale) and produce mean peak horizontal accelera- tions in the order of of 0.4 g. Therefore, minor rockfalls and some cracking of concrete may occur but no major tunnel stability problems are anticipated. 5.4-Design Considerations The following preliminary de~ign considerations were adopted for purposes of estimating t:osts of the conceptual tunnel schemes outlined in Section 4. (a) (b) Tunnel Size The power tunnels were sized to maximize the net benefit. This required cross-section~i areas of between 700 and 2000 ft2. The geologic information to date indicates that tunnels in the 700 to 1000 ft2 range could be constructed without major problems;. Although it may be difficult to economically construct very 1 arge tunnels through poor r"'ock, no adjustments to the economically sized tunnels was made during this study as the amount of geologic information available was not sufficient for this adjustment. Tunnel Shape runnel shape is gener-ally a functi~n of hydraulics, stability and ease of construction. In good quality, high strength rock, stability is not a problem and the other factors govern the shape. As rock quality and strength decrease or the rock is overstressed, shapes tend to be more circular. For purposes of this study, a modified horseshoe shape was tentatively selected based on the assumptions that: -The majority of the tunnel is in good to excellent rock requiring little support$ -It is the easiest shape to drill and blast. (c) Tunnel Alignment The objective of aligning the tunnels is to have the shortest tunnel through the best rock. Avoiding zones of poor qua 1 ity and topographic 5-4 'I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I lows, crossing adverse geologic structures (not paralleling them), attaining the minimum cover over the tunnel, and keeping the stresses compressive around the tunnel are major considerations. ,, _(d) Tunnel Grade Tunnel grade or depth is selected so as to locate the tunnel in a competent strata and meet cover requirements. These cover requirements vary greatly and Table 5. 3 summarizes the cover used in several projects. It indicates that values of between 15 percent and 50 percent of the total hydraulic design head have been used. For purposes of these studies, rock cover equal to the static head was used. When the rock cover is less than this, a lining is ..tssumed neces- sary. It has been assumed that slopes within the tunnels will be inclined slightly (approximately'0-.5 percent) to ease construction and haulage. Access ad its are located so as to minimize their 1 engths. Maximum grades are 3 percent for rai.l haulage system and 10 percent for trucks. I) (e) Tunnel Lining and Support Drilling at Watana and Devil Canyon indicate that the rock is tight and impermeable at depth. For purposes of this study it has been assurra:d that one third of the tunnel length will require st~uctural concrete lining with a combination of steel sets and rockbolting, one third shotcrete li-ning .and rockbo 1 ting, and the remaining one third wi 11 require no lining or support, except for the concrete-lined invert. 5.5-Construction Methods ' Initially, three tunneling methods were considered for this study: -Drill and Blast -Tunnel Boring Machine (TBM) ·-Road Header Based on available knowledge, drill and blast appears to be the most viable for Susitna c.md the tunnel estimates are currently based on this method. Each method, however, has advantages and d i sadv ant ages and is discussed briefly below. (a) Drill and Blast. Drill and blast is the oldest form of rock tunneling~ Each cycle involves: -Drilling -Loading -Shooting 5-5 -Ventilating -Supporting • -t4ucki ng. The two most common approaches involve heading and bench or full face excavation. Heading and bench removes a small top heading atoa higher unit cost, then removes the bench at a lower unit cost. The full face excava- tion ~ethod excavates the entire face at once.· In large tunnels~ heading and bench may be more economical than full face excavation. Both methods would be suitable for the proposed Susitna tunnel scheme. There are several advantages to drilling and blasting: -It is flexible and will acconmodate most rock types, tunnel shapes, grades~ and can be adapted to rapidly changing geologic conditions. -The initial cost is generally lower. -Lead aYJd mobilization times are usually shorter. -There are many experienced contractors. Some of the d isadv ant ages inc 1 ude: -Running costs are higher. -Ground disturbance is high and overbreak may be considerable. -More extensive support and/or lining may be required. -Production, on the average, is lower than for mechanical excavators~ Considering the complex geology and the present lack of geologic informa- tion along the tunnel routes, this method was selected. It is sufficiently flexible to deal with any problems 1:hat may ari'e and yields a relatively conservative ~onstruction cost estimate. (b) Tunnel Boring Maching (TMB} Machine tunneling has advanced greatly in the 1 ast 20 years. TBMs are being designed to handle a variety of geologic conditions and by the time the Devil Canynn tunnels are required machine tunneling m~y be an attrac- tive option. Presently, this system seems too inflexible for the geologic conditions anticipated. The TBMs have several advantages: -Low rock disturbance., -Lower support requirements. -Lower running cost. Q 5-6 I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I - A 1 in ing may not be required. -Higher ~Jroduction rates if the rock quality is good anrl, ·"geology is uniform. Some major disadvantages are: -They are inflexible, that is, grades and operating radii. are 1 imited and only a circular shape is possible for large tunnels. -High initial cost. These machines are unecono.;7ical for tunnels less than several miles in length. -Longer lecd time, probably one year. -Longer setup time, probably six weeks. -Prob 1 ems tunne 1 ing through poor qua 1 ity rock. TBf4s \'lork very we 1 i ... nder the conditions they were designed for, but do not ada\pt well to geologic . changes. (c) Road Headers A road header is an offshoot from the mining industry and involves a mechanico.1 tunneling system. It ha.:s the advantages of being mere flexible than a TBM, but presently cannot cut hard rocks efficiently. If these machines had the capability of cutting hard rocks at reascnable prcdlJCtion rates, they would merit serious consideration. {d) ~ucking Mucking is the term used to describe removal of the excav11ted materia.l from the tunnel. Sel~cting a mucking system depends on tunnel grace, length, .and equipment the contractor has available. Within the tunnel, two haulage systems are conmonly used, ra'll and truck .. Rail systems are favored for long tunnels since they can usually haul large quantities economically. Their maximlJTl grade is 3 percent, but they may be winched on steeper grades. Trucks ara favored in tunne 1 s less than about 4000 feet. Their maximum grade is 10 percent. Considering the volume of material and haul distance to the access way, a rail system has been assumed for the Sus itna tunne 1 schemes~ 5-7 I I I I I I I I I I I I I I I I I I I A~ B. TABLE 5.1: GEOLOGIC STRUCTURE OF REGION BETWEEN THE DEVIL CANYON AND WATANA DAM SITES GENERAL AREA Orientation Feature Major Joint Set Major Joint Set Major Joint Set Average 335° 82° sw ' Range 320°-355°, 63°-9'0° sw 300°-355c, 62°-90° NE 40°-60°, 65°-90° SE 325° 77° NE 48°: 79° SE ARGILLITE-GRAYWACKE AND UNIT IN THE -IMMEDIATE VI!:INITY OF' THE DEVIL CANYON DAM SITE (Based on Geologic Mapping) Feature Bedding . , ............. ., ...... . Major Joint Set ••••••••• Major Joint Set •..•• ,. •••• Minor Joint Set ••••••••• Orient at ion 53°-70°, 50°-80° SE 320°-350°, 82° NE (avera~e) 70°-105°, 15°S <~1erage) 70n-105°, 65° NW (average) 5-8 Spacing 6 in to 2 ft 6 ir: to 3 ft 6 in to 1.5 ft •' I I I I I I I I I I I I I I I I I I I TABLE 5.2: EFFECTS OF SEISMIC LOADING ON TUNNELS (11) Horizontal Accelerat~on(g) {ft/sec ) < 0.19 0.19 -0.25 0.25 -0.52 Velocitr (In/sec) < 8 8.16 16-32 5-·9" Damage None Few instances of minor cracking, some rock falls in 1..11lined tunnels One part~al collapse in a masonry lined tunnel associated with a landslide I I I I I I I I I I I I I I I I I I. I TABLE 5.3: TUNNEL COVF.R EXPERIENCE Ratio of Rock Cover to Project Hydraulic Head.* Abjors 0.4 Bersimis 2 0 .. 5 Gonda 0.2 Handek I 0.16 Handek II 0.18 Innertkirchen 0.14 Kern ana 0.4 Montpezat Ce26 South Holston 0.5 Bersimis 1 0.5 Calancasa 0.33 Chute des Passes 0 .. 5 Spray 0.24 *Hydraulic head includes both static and dynamic head. 5-10 I I I I I I I I I I I I I I I I 0 ·rot 0 N 0 c: 4l u f.) """ 0 N 0 (I) (I) :::: 0 """ 0 N 0 (J.) r-1 a:1 0.. TABLE 5.4: REGIONAL GEOLOGY MAP UNITS Qs Tsu Tv Tbgd/Thr·J Tsmy/Tkgr- Kag Jtr/Jgd/Jgcin Jam TRv TRvs Psv/Pls Undifferentiated Surficial Deposits Undifferentiated Sedimentary Racks Undifferentiated Volcanic Racks Biatita & Biotite-Hornblende Granodiorite Granites and Schists Argillite and Graywacke Quarts Diorites & Granodiorites Amphibolites Basaltic Metavolcanic Racks Me~ abasalt and Slate Basaltic: to P.ndesitic Metavolcanogenic Racks with Ird;erbedded Limestone Modified after Csejtey and others, 197Bo 5-11 . . -· ~ 0 0 0 ~ )> :D 0 n r -< 0 m n 0 z en c l- ~ z -i en -&; Ol ~ .l> c ~ 60° n Ol 3 CT (I .... ... 0 U) ~ 01 I __, N ... ! • r --· ·------ 150° 180° \ . r~~~ \ \ ,,, NORTH EURASIAN ',, \ \ PLATE \ \ NOTES 1. Base map from Tarr (1974). 2. After Packer and others (1975), Beikman (1978}, Cormier (1975), Reed and Lamphere (1974), P .Jker, and others { 1978). PACIFIC --- -·--- -:-. ' 150° 120° AMERICAN PLATE Yakutat Block PLATE LEGEND ••··········•·····•·• (;' :::::::::::::::::::::Wrangell Bfock ..... " ...... ~ Relative Pacific Plate Motion ----Plate Boundary, dashed where inferred 6 A 6. Shelf Edge Structure with Oblique Slip ---Intraplate Transform or Strike·Siip Fault I 150° Queen Chaclfotte Islands Fauat Q I --·-1200 . PlATE TECTONIC MAP 600 -~ AGURE 5.1 I I I I I I I I I I I I I I I I I I .J EXPLANATION OF MAP SYMBOLS -'wro•h•te CtlfttaC:t of ~rl1eta1 .deposits -------~~~ ~ J) _.-----····· Fault l.slll9 du.Md wben appro:d•tely located; snort duhed an tnft.n<l; dotted ..here a~ncaleiS. U tndlc.tes upthflllljft side are dtrcttOfl of disphee!llt'!'lt b tno.r.. .An-ows indicate rellthe lat.er11 .:~nl!l!'nt. e • w ,_,.---.....----•• ,. ••••••• Thnnt f1ult LOillJ dished llhere appro:d•tely locat.td. short dashed •::'1! 1!!1ferftd. dotted .tlt!re Cl.l!ICEiled. Teeth. 1nclftate upthnMI stele. ~ ----v---.••••••• y· .•• Apprc•1•te axis of intense shear zone of variable width. possibl)l -.rttng a thrust fault Dotted white eonce~l!d; teeth indicate poss1bl@ upthro-r. st~ of postulAted thrvst. ! ----..., .. --~ Antt.clhtll. showtng c:rest line ; S171C1tre, showing trough 1iM i.oflg lbshf!d llfl>frv. llppro:~~t~Mtaly located• an"OW 1nd1e&te$ plunge. Lcutton of Slllfllt dited by ·thl: U.S. ~log1C:.1 S!J!"l'e1 us1ng ~ patllss1~a-~rvon or the lud-alphl a!thO<S. snowSng IIIP n\JIIber, field fillllber, alld tM tlllt1.111~ •fNrll age. et -biotite. Jb -hombll'l'l~. J~IJ!Ibo."~tte. kt -aetJnoHte. 2r • zircor., wr -whole tuc.k. • .... .. . -... . 5-13 Loati011 of s.uple !!.ted by iumer and Slltth (1974) &~SfnlJ the potanilft-t argon aethod. fhowin; .ap nu.btr. field nUNb!r. ind the c&ltu1ated •iMnal age. 11 -1!\.,ttte~ lib -t~Urnblftlde. x+. Foss1l loaltt.Y in units 'llv. Pl'-and DSls. Str1b and dt~ of bedS -,-1AC11fle4 •» -'"'l-u ~ -+-YerUc.al -1-Ap~d•u• esttated froa dfstllnt oburvauons 2.0 Stnu 18\d dtp of fr1c:wre cluva;e r--r-' Incl tned eo .....-f-J Vfftlal StrH.e and dip of slaty or u111 plane cleuage ,---, Inc:Hned 50 1---1 Yertial StrUt and dip of shur plane~. •~TPhie foH&UDft or-seMst~stt.y --v-• !nel ine.i 30 ..-.-Vertical StrUt .and dtp of igMOus flow foliation ......--Inclined 30' -+-~erttal learfag and plun~. or HneatfOi'l Strht ud dip of jr.tnts -z::r-Jncl1ned "0 -e-Yerttal 'tlfE<1£NCI: cse:JTEY,I.ET AL AfCOHHAISSAJifC£ ~Eot.oelC WAP• a CEOCIUt<*OU>C'r, TALitlt:TNA JIIOON'!AiJI. OUAOftA)t&L,t:, HOftTHED PART Ofr ANCH~ QUADRANGLE, &ND .SountM:IT CORNEJt Of tiE:ALY OUAPftAIUilJ:, Al!ISAA. U.S.S.S. OP'£N ,IU ftEP<Wf 71· 551A.t.,_, REGiONAL GEOLOG,r WITH TUNNEL ROUTES 0 P! SCALE N01'E! '3 6 12 -~s~~~~~~~L· IN. MlLES ROCK UNITS ARE LISTEO lfl! FIGURE 4.l b FIGURE 5.2 -.· _,.-. ... 40 ~·' .. ... . ... . ,.., .. _~·~.s .. ;-.. _.~ .. :. .... , ..... .•' ... ~. . .. ·. .. ~<- ~" ..... ........... : \ :! ... 5-14 .... o 0 ·----.... l I :. " i ~-.. '\ .. ~ \ t ,. ~-.. 1 ..... . ,. ..... . · . ' "' . . . .. , .. ,... ~ ..,._, ..;:. :--:-....__ ... ··;;:." T ~ , . ... '..... . "' ... LEGEND BOUNDARY FAULTS Faults with recent displac~ment SIGNIFICANT FEATURES -----Indeterminate A feature ~~-~~-·-Indeterminate B feature \ -N- 0 BOUNDARY FAULT AND SIGNIFICANT FEATURE MAP FOR THE SITE REG!ON 0 10 20 30 40 50 Mite:: ~===1~~~~==:f\~~i~~~~~~EI====~l 0 , 0 20 30 40 50 Kilometers I i FIGURE &3 .. -r---- ...,.,. --.a ~indeterminate • A feature -m • • ....._.~Indeterminate • 8 feature _ .._ -.,.. Indeterminate - B L feature -~--.. --!'""\- rl "-. ... I £1 I ,_ I r. I I t. I ;I I [I I 1 I { I (I I ···' t .. . •. .• ~ -.- WOOOWA~D-Cl..YDE CONSULTANTS 14658A Dm!emt*r 1980 . 5-16 . . -. ,/ ··:Jo'•~ 'If .. ., • II .. .. .... ., ... ._. LEGEND --Indeterminate • A feature -......-Indeterminate-B feature -a-lndeterminalte-BL feature DEViL CANYON SITE SIGNIFICANT FEATURE MAP FIGURE 5:5 -. _ _, t ~\ ; .. ·, ' -. ... . - ] ·----~1..--""." { l WPOOWARD-CLYOE CONSULTANTS 14658A Def:ernber 191~ .· ... -~-. ----·- ·;' ... 1 ' . __. r $; /,.· ~. ,;·~ ·. FOG .... . ' '".• .._ .......... ..__.., --- · .. .. _ .. -· ::: ,- I ' I _ ...... . ' :: .. -· .. \' . I .... ~ ( ..... . -. - I I --------' I ( -!·· .-----...---.------,. ---.· / /-·--· .- -. LEGEND a •--·•----·-·----... o.-o-- .. --. Indeterminate lndeterminete Indeterminate A feature E feature BL feature WATANA SITE SIGNIFICANT FEATURE MAP . ' ·FlGURE 5.6 ., I I I I I I I I I I I I I I I I I I 6 -SCREENING OF CONCEPTUAL TUNNEL SCHEMES 6.1 -Introduction The screening analysis w~s performed to compare the four conceptual tunnel schemes and determine the best tunnel scheme for furt~1er study s Costs, power and energy, geology, and environmental aspects are uSied as screening criteria. 6.2 -Tunnel Scheme Costs All costs are based on 1S80 dollars. Unit prices were applied to estimated quantities for the various components in each tunnel scheme. The total project cost for each tunne 1 scheme inc 1 udes the tot a 1 construct ion cost p 1 us a 20 .. percent contingency and a 12 percent allowance for engineering and administra- tion. Wherever possible unit prices were developed and/or compared with cost informa- .tion on recent projects in Alaska. Unit prices developed from projects outside of Alaska were adjusted to Al~ska using the Handy Whitman price indices. In general~ costs are based on the same unit pr;ces as those used for the Susitna Basin dam alternatives outlined in the Subtask 6. 05 report on 11 0evelopment Selection". Tunnel costs are based on the conservative assumption that excavation will be done by conventional drill and blast operationse Knowing very little about the rock mass quality along the route, support requirements are difficult to predict. Therefore, the lining and suppor-t assumptions were based largely on experience at the Kemano Project which is similar in concept, and the results of drilling at Devil Canyon and Watana, as outlined on Table 6 .. 1. As mentioned previously, due to the lack of geologic information and the fact that the tunnel is a major cost item~ total project co~t estimates must be regarded as tentative at this time. In any event, totdl project costs are relevant 'for a valid economic comparison between conceptual tunnel schemes. Tunnel scheme to·~al project costs are given in Table 6. 2 for each of the four tunnel schemes. 6.3-Power and Energy Energy values for the tunnel schemes were determined from an annual f1ow duration curve developed frnm the simulated monthly outflow from the Watana reservoir (35). This curve was adjusted to all ow for a 1000 cfs minimum discharge in the river. Allowance was made for tunnel friction and entrance losses. Installed capacities were calculated to yield an overall p1 ant factor of between 50 and 55 percent for the total Watana dam-tunnel system. For the tunnel generating portions of t~1e total development p1 ant factors of about 50 perce·t~t were used for peaking tunnels and about 80 percent for base load tunne~s .. The resultant installed capacities and average annual energy yields are shown in Table 6.2. Figure 6.1 illustrates in the form of simplified power durat~on curves the operating modes of the various powerhouses in the tunnel schemes. 6o-1 I) Of primary importance in the assessment of the tunnel schemes' potential is the increCise in energy production over the single Watan~ development. As shown on Table 6.2, Scheme 3 yields the largest increase in energy production with 2180 Gwh of added average annual energy. Schemes 1 and 2 would provide for an increase in average annual energy of 2050 Gwh and 1900 G~ths respectively. Scheme 4 would have the smallest increase of only 890 Gwh. 6.4 -Environmental Considerations A preliminary assessment of the environmental asp~cts associated with the four tunnel schemes has been made {33). This preliminary ass.essment was done for comparison and screening of the tunnel schemes only, and impacts common to all schemes were not addressed. The results of this assessment are as follows: {a) Scheme 1 The environmental impacts associated with this tunnel scheme are likely to be greater than those of at 1 east one of the other tunne 1 ~chemes eva 1 tJated (i .. e. Scheme 3). The main criterion for this assessment is the adverse effects, particularly on fisheries and recreation of the variable down- stream flows ( 4000-14000 cfs daily) created by the De vi 1 Canyon pov1erhou~e peaking operation. Other negative impacts would result from construction of both there-regulation dam and a relatively long tunnel. Tunnel impacts are similar to those of Schemes 2 and 4 and include disturbance Qf Susitna tributaries as a result of tunnel access and the potential prob~ems associated with disposal of a relatively large volume of tunnel muck. {b) Scheme 2 As for Schem~ 1~ this scheme involves adverse environmental impacts associated with variable downstream flows caused by peaking operation at the Devil Canyon powerhouse (4000-14CJOO cfs). Without there-regulation dam, however, less land would be inundated and the impacts associated with construction of this relatively small dam would be avoided. As for Scheme 1, the long tunnel proposed will also have negative conseouences, including disturbance of tributaries for tunnel access and the potential problems connected with tunnel muck disposal. (c) Scheme 3 The overall environmental impact of this scheme is conside~ed less than that related to each of the tv1o pre vi a us-schemes, and a 1 so 1 ess than that related to the fourth scheme. The relatively r ·stant discharge (about 8300-8900 cfs) from the Devil Canyon powt:;•house is desirable for maintain- ing downstream fish habitat and recreationai potential. A general reduc- tion in river flows through Devil Canyon in this a 1 ternati ve may a 11 ow anadromous fish access to a previou:>1,y i!1accessible 15 mile stretch of the Susitna River, and an opportunity for enhancement of the fishet~ies resource. -With a compensation flow sufficient to allow minimum discharge of 1000 cfs through Dev.il Canyon, the riverine character of the reach should be main- tained. ' ""··"I I 1 I I I I I I I I • I I I I 'I I I I I I I I I I I I I I I I ·I 1- I I I I I I I As with all of the tunnel schemes~ the wildlife habitat in the stretch of river bypassed by the tunnel might improve temporarily because of an increase in riparian zone vegetation. With Scheme 3, however, this stretch of river is shorter than with the other tunnel schemes so a 'smaller area would benefit. The wildlife habitat downstream of Devil Canyon powerhouse may well benefit from the flow from tne hydroelectric project regardless of the scheme chosen. With the constant flows allowed in Scheme 3, the improvements to that habitat niay be somewhat greater than with the Vdri able flows resulting from peaking in the other tunnel schemes. One environmental disadvantage of this scheme compai'"ed to the others is the larger area to be inundated by the re-regulation reservoir. This area includes known archeological sites in addition to wildlife habitat. Never- theless~ this disadvantage is offset by the more posit·ive environmental factors associated with constant discharge from the De vi 1 Canyon power- house. (d) Scheme 4 Scheme 4 involves peaking operation at Watana with baseload operation in the tLmne1. Since the net daily l'luctuations in flow below Devii Canyon would be considerable (4000-13000 cfs), Scheme 4 is judged to be less desirable than Scheme 3 7rom an environmental standpoint. Although Scheme 4 would avoid the impa~ts associated with the lower dam and its impoundment (as planned under Scheme 3); the. adverse impacts that would result from fluctuating downstream flows are considered to be an overriding factor. Another, although less significant, disadvantage of Scheme 4 compared to Scheme 3 is the longer tunnel length planned for the former, and perhaps the proposed lccation of the tunnel on the north side of the river. 6.5 -Geotechni~al Consider1tio~s From a geotechnical perspective, the northern and the alternative direct align- ments for Schemes 1, 2 and 4 are similar (see Plate I). Therefore~ they will be discussed together while Scheme 3 will be discussed separately. Table 6.3 shows .estimates of tunnel length proportions within the various lithologic units. The resu1ts of drilling at Devil Canyo:"J and Watana shov1 that rock quality improves with depth. Therefore, the rock at tunnel grade for all three align- ments should be good since the minimum rock cover is several hundreds of feet. The geology along the northern and diret;t routes seems more complex. These routes cross at least four lithologic contacts, three different rock units~ two major lineaments, and several minor ones. One lineament is the Susitna Feature. Although· it is not currently considered likely, if this feature were found to be a fault zone, it could create a very difficult tunneling environment. The topo- graphic 1 ow at De vi') Creek may a 1 so be a problem zone. Tu nne 1 i ng through the schistose portions of the schist, migmatite and granite w:it may also be diffi- cult. Scheme 3 has several advantages. It is about half as long, crosses only 0'2 known lithologic contact, is 90 percent in the Biotite-Granodiorite unit, and crosses one known major lineame.~nt and several mir1or ones. Being 90 percent in an·e unit , machine t unne 1 i ng may be poss i bl e. 6-3 Various lineaments cross the alignments. None have been classified as active· faults and most were in the doubtful category as being.faults (43). None of these features appear to present extreme tunneling problems, but all will require exploration to determine their characteristics. If they are faults, strengthened linings will have to be designed and tunneling techniques may have to be modified. All tunnel alignments were laid out so that they crossed the known joint sets. The northern alignment (for Schemes 1, 2 and 4) was suggested because as it increases available cover. The tunnel length crossing topographic lows at Tsusena and Devil Creeks is minimized, but is about two miles longer than the direct route. The direct route has been proposed because it is the shortest. However, the tunnel lengths crossing the topographic lows at Devil and Tsusena Creeks are 1 anger and the cost of 1 i ni ng these. areas may make this a 1 i gnment less attractive. Also, if these 1ows are zones of poor r·ock quality, tunneling through them may be more costly than minimizing these lengths by avoiding them. Scheme 3 'tas aligned to maintain the minimum cover over the entire route. The tunnel was diverted around topographic lows. Future alignment adjustments may decrease the tunnel length, but not significantly. Presently, the Scheme 3 alignment appears to be preferable from a geotechnical viewpoint. However, explorations are required on all three alignments to firm up this judgement. 6.6 -Preferred Tunnel Scheme It is evident from the above discussion that of the four conceptual tu~~el schemes, Scheme 3 is preferred. The economic aspect~, environmental aspects, and geol·ogical conditions of Scheme 3 are considered superior to the other tunnel schemes at this time. Scheme 3 produces additional energy at by far the lowest cost as· is shown in Table 6.2. Scheme 3 was, therefore, selected for further, more detailed study. 6-4 I II I' I .I I I I I I. I I I I I I I :I I I I I I I I I I I I I I I I I Rock Qti21lity (RQO) > 90 50-90 25-50 < 25 J~BLE 6.1: ASSUMED TUNNEL SUPPORT Percent of Tunnel 34 33 25 a 6-5 Support and Lining None to occas.ional rockbolts Rockbolts, shotcrete, welded wire fabric Rockbolts, shotcrete, welded wire fabric, concrete Steel sets, sho~crete, concrete () 0'\ I 0'\ --.. ---- ---------- TABLE 6.2: DEVIL CANYON TUNNEL SCHEMES COSTS, POWER OUTPUT AND AVERAGE ANNUAL ENERGY Installed Increase1 in Ca~acit~ (MW) Watana Oevil Canyon Installed Capacity (MW) STAGE 1: Watana Dam BOO STAGE 2: Tunnel: -Scheme 1 BOO 550 550 -Scheme 22 70 1,150 420 -Scheme 3 850 330 380 -Scheme 4 BOO. 365 365 1 Increase over single Watana, BOO MW development, 3250 Gwh/yr 2 Includes power and energy produced at re-regulation dam Devil Canyon Average AnnuaJ Enerfi) (Gwh 2,050 4,750 2,240 2,490 3 Energy cost is based on an economic analysis (i.e. using 3 percent intereat rate) as discussed in Section 7-6. Inc1•ease 1 in Tunnel Scheme Average Total Project Annual Energy Costs (Gwh) ($ X 103) . 2,050 1,979,000 1,900 2,317,000 2,180 1,221,000 B90 1,494,000 3 Cost of' AdditiontJ. Ener]Y' · (mills kWn) 42.6. 52.9 24.9 73.6 - I I I I· .I ·;· I -I ,• I I. I I I I I I I I Tli\BLE 6.3: LITHOLOGY Or TUNNEL ROUTES Percent Tunnel Route in Each Lithologic Unit** Scheme(s) Alignment Lithologl: Ksg Tbgd Tsrng Qs* 1,2,4 Northern 31 11 10 48 1,2,4 Direct 13 29 31 27 3 10 90 0 0 NOTES: * The rock units below the Quaternary soils along the alignments are mast likely Tsmg and Tbgd. ** These percentages are based on surficial rock unit distributions. The actual length of tunnel in each unit is unknown. . 6-7 ::.:::- I. 1 I I I I I I I I I I I I I •• ••• I I ,. "'' ! '·~ .. ·.,_ ' e -1200,.. ·~ 1000 ~ -800-a:: lJJ 600 ,.. ~ ~. 400- WATANA. POWER HOUSE 200..-.-J () ....... ____ __.. -.1200 I" ~. iOOO t- ~SOOt- ~ 600· a.. 400- 200 t- 0 ======= 1200,. -~· 10001- ~ 8001- . IJJ 6001-~ 400~ 2001"' o· t: ==~--====- ....... 1200~ ~ '::E' 1000 -0: 800 I'" lJJ ~ 6001- Q. 4001- 200 t- oo 24 HOU~ DEVIL CANYON POWER· HOUSE I I [ I 0 HOURS I I 24 TOTAL SUSJTNA BASIN DEVELOPMENT --· n [ I ~ 0 24 HOUR~ TYPICAL DAI·L Y POWER PRODUCTION FOR MARCH FIGURE 6.1 6-8 TUNNEL SCHEME # I. 2. 3 . 4. fil I I ~--· I I I I I~ I I. i I I I • ._;..;,.. I I I I ·- \) . ' '' 7 -PREFERRED TUNNEL SCHEME 7.1 .... Introduction As outlined in Section 6, tunnel Scheme 3 was selected for more detailed study. The aim of the more detailed study is to further refine the engineering con- c~pts~ to improve the accuracy of the cnst estimate,. and to evaluate the po\~er and energy potential in more detail. This information is used for comparison of the tunnel scheme with the Devil Canyon da.11 $Cherne in Section 8. 7.2 -Design and Operational Assumptions --~~----~------------·-~· --- (a) pesign Assumption~ The design assumptions used in the mc,r~ detailed study are essentially as previously outlined in Section 5.4 and the construction techni-que as in Section 5. 5. The proposed alignment crosses the known ,joint sets to minimize support arld overbreak problems. Adequate cover is maintained along the entire route and the minimiJm tunnel depth or 250 feet is believed to be conservative_ The 1 ining requir~ments for the tunnel are as outlined in Section 5. 4. Table 7.1 summc.tr'izes the rock quality observed in the drill holes at the Watana and Devil Canyon dam sites. If these rock qua'f ities remain true along the Scheme 3 alignment, up to 50 percent to 80 percent o·r the t•Annel could be unlined and 1 ightly supportedtt 20 percent to 40 percent may ~equire rock bolts and shot::rete., and 10 percent to 20 percer;t may require rock bolts, shotcrete and a cast in place concr·ete 1 ining. In view of these t"esults~ t.he 1 inin~l and support requirements suggested in Table 6.1 are conservative and wet··e retained. As before~ the tunnel siz(: was selected on -the basis. of an economic analysis. The optimal tunnel size was determined such that th€~ sun of the amortized tunnel cost and the value of energy lost due to friction is mini- mized. The value of energy was bast!d on a thermal coal-fir·ed plant in the year 2000 .. Table 7.2 summarizes the results of the analysf!S and also indicates that tunnel sizes would not be significantly d·ifferent fer lower energy values or if the cost of energy produced by the tunnel had been minimized • The optimum sing·1e tunnel diameter was found to be 40 feet~ which is rel a- tively large. In view of the sparsity of geotechnical data, two smallet', ~.·sarallel tunnels of similatr total capacity were conservatively selected for study purposes. Such a ccmcept also has security advantages, the optimum sizes of these tunnels be·fng 30 foot diameter. For this study ;'t has bee.n assumed that the powerhouse is located crt the downstream end of the tunnel. This does not necessarily imply that ~ powerhouseo located at thra ups,trea~n end would not bf: studied, with the tunnels being used for tailrace discharges.. Further study would be~ required to determine the optimum location. 7-1 (b) Operational Aspects Minimum discharge of not less than 500 cfs from Watana and 1000 cfs from there-regulation dam were specified. No daily maximum limit on the dis- charge from Watana was specified because of the downstream r-e-regulation dam. Constant dai 1y discharges from the re-regulation dam and the Devil Canyon powerhouse were specified. The Devil Canyon powerhouse is assumed to be oper·ated as a base 1 oad power faci 1 ity (. No daily discharge fluctuations are all owed at the Oevi 1 Canyon powerhouse and daily peaking power .jernands are supplied by the Watana powerhouse. Daily peak discharges-from Watana are regulated at the re-regulation dam with a maximum fluctuation in the re-regulation reservoir of less than four feet •. A relatively s1oall powerhouse at the re-regulation dam operates as a base load power facility and supplies the required down- stream compensation flow. 7.3 -Project Description Scheme 3 is composed of a re-regulation dam, power tunr.el, and powerhouse at Devil Canyon. Plates 2 and 3 illustrate. the detailso The re-regulatiori dam is located approximately 15.8 miles downstream from the Watana dam sit~. Site selection was based on regional geologic mapping and air- photo and topographic interpretations. The 245 foot high dam ts assumed to be a rock fill dam with an impervious core. A spillway is located on the north abut- ment, and a relatively sma'll powerhou~e with a capacity of 30 MW on the south side of the river. The maximum normal operating reservoir level is 1475 feet .• Power tunnel intakes are located on the south side of the river approximately 2000 feet upstream from there-regulation dam. The optimal power tunnel dia- meter is 30 'feet for each of the tWC? power tunnels. The underground Devi 1 Canyon powerhouse has an ·installed capacity of 300 MW, with an assumed four generating units. Overland access to the powerhouse access adit area runs parallel to Cheechako Creek. A surge tank for each power tunnel is 1 ocated, just upstream of the powerhouse. · Sma 11 cellular cofferdams are required a I eng the south bank _of the Susitna to a 11 ow construction of the ta i 1- race. As part o.f this tunnel scheme~ the. installed capacity at the Watana dam is increased by il sma 11 amount to reduce the avera ll system pi ant factor once the base load tunnel generating plant comes on line. A provision for an additional 50 MW has been made in this study. 7.4 -Cost Estimate and Construction Schedule (a) .Cost Estimate The cost .estimating methodology described in Section 6.2 was employed to develop cost estimates for the pr~ferred schemea However, as more detailed engineering layout dra\'lings were available, it l'las possible to undertake a more detai 1 ed cost es.timate than for the study describe<~ in Section 6. 7-2 I' I I I I ·I I I I I I I I I I I I I :li I I I I I I I I I I ·I I I I I I I I I I Tota 1 construction costs were re-estimated for both the twu 30 foot diameter and the one 40 foot diameter schemes. These (;osts amounted to $1.50 billion and $1.34 bill·ion~ respectively. It should be H(?;ied that they are somewhat higher than the estimates associated with the conceptual tunnel schemes due to. the higher level of detai: involved. Summa~'Y cost estimates far the two schemes are shown in Tables 7. 3 and T. 4. (b) Construction Schedule As shown in Figure 7 .1, five years \t~ill be needed to complete c.:mstruction of the Scheme 3 facilities. For the purposes of .this study, the schedule is based an assumption that .access will be available frL\1 a previously con- structed road from the Parks Highway to the Watana site. Underground work is assumed to be pass ib 1 e throughout the entire year, and rock p'l acement only throughout the six months of sumner. The exact timing and sequencing of the various "noncritical .. activities will be dependent upon resource and season a 1 1 irni tat ions and other f.actors • Initial \oJOrk will be to construct several access r·oads of up to six· miles in length to connect the Watana-Parks Highway to the re·-~egul at ion dam, Devil Canyon and intermediate access sites. Zt is expected that the construct ion of the Devil Canyon powerhouse can start shortly thereafter with the power on 1 in e. date-approximately 52 months after work commences. Access to the main power tunnels will be through ·inclined access tunnels at two intermediate points .. Additional tunneling will occur at both the power intake porta1 and at t~,;~ main powerhouse. This will enable the tunnels to be driven from as many as six faces~ resulting in an estimated maximum tunnel length of approximately five miles. The complete re-rcgul ation dam will take approximately three and one half years to construct with an estimated p 1 acement rate of approximately 640,000 cubic yards/month during the two year placement period. As shown in Figure 7 .1, the power on 1 ine date is approximately the same .,.,,. ' !loth the re-regul at ion cam and the Oev il Canyon powerhouses. 7.5 -Power and Energy Power and energy have been evaluated by a demand driven computet)'> simulation model. The model is based on monthly average derrrlnds and 30 years of histori";·a1 monthly inflows. Scheme 3 inc 'rporated with the Watana dam has been simu1 ated to accurately represent operation .of the entire development. Pow(~rhous~es were sized to achieve an over a 11 capacity factor>; of 53 percent which i!i with in the des ired plant factor range of the Watana-Devil Canyon dam scheme. Power and energy production from a Susitna basin developnent composed of \~atana and Tunne 1 Scheme 3 is summarized in Table 7. 5. 7. 6 .. Environment a 1 Impact Assessme . .; ~~ A more detailed assessment of the environmental aspects associatf:d with Scheme 3 has been made (33). A comparative environmental analysis on the location of the Devil Canyon powerhouse was also performed to determine the preferred powerhouse location. . 7-3 f : - ~- (a) Locatlon of Devil Canyon Powerhouse Alternative locations for the Devil Canyon powerhouse have been proposed. Two altern at i\~e locations have been determined by the ease of access to the tailrace and powerhouse access are.a. The two sites are an upstream loca- tion about 0.3 mi1es above the Devil c,myon dam site and a downstreiln loca- tion about 1.5 m11es below Portage Creek. The major environmental consid- eration is that a powerhouse upstream of Devil Canyon would preserve much of the aesthetic value of the canyon. In addition, the shorter tunnel would confine construction activities to a smaller area and may result in slight 1y less ground disturbance, particularly if there are fewer access points as well as a smaller muck disposal problem.. It is for these reasons that this powerhouse location is preferred. A downstrecm powerhouse location, on the other hand, might create a mitiga- tion opportunity by opening up a longer stretch of river that perhaps could be managed to create salmon s.pawning habitat due to the lower flows through the rapids. However, there· is currently no data to confirm this and at this stage the downstream powerhouse location is .considered less flexible. (b) Environmental Impacts The major adverse environmental impacts associated with the t~.mnel scheme are the inundation of 3900 acres by the re-regulation .'eservoir, disruption during construction, disposal of tlmnel muck~ and bypassing the major p'i)r- tion of river flows through the tunnel. The area to be inundated by the r~-regulation reservoir. includes known archeological sites in addition to wildlife habitat. The major beneficial environment~1 impaet -is the ability to regulate ·peak discharges from the Watana Dam. The re-regul at ion dam would store the daily peak discharges from Watana and relea::;ce a constant downstream flow. The re-regul at ion dam would el itninate the effects of watana peaking opera- tions on the Susitna River. This would allow Watana to produce the maximum amount of peak energy possible with no adverse impacts downstream .. The compens 1tion flow in the bypassed section of the Susi·ena River is totally controllable and could be varied seasonally. The control abi1 ity of the -tGmpensation flow could be an asset to the fisheries and w·ildlife in · th~ stretch of the river bypassed by the tunnel . . , . /(~) Di,~·~posal of Tunnel Muck -·~ ( ________ _.,;,_ I'f;. · r~< ··important to note that cost estimates for tunnel schemes are current- ly' =.$A~d QP minimal requirements for transportation and disposal of excav a- ted materials by whatevet means are finally selected. If a costly disposal method is selected, trrtal proje£t costs could increase as much as 1 percent. The total volume of excq.vated material ft"orn the two 30 foot diameter tunnels ~aunts to 3 • .7 mill ic.n cubic yards. Allowing for a bulking factor of 1.5 this would amount to approximately 5 .. 6 million cubic yards of muck. 7-4 . ' /';""""" ' I I I :. I •• I I I ·:·,~ ·-~ I •• I I I .,., - I I I I 't:_) '.-.. ~.~----~ ...... '"""-~-"~"' .... ~--.~ '' I I I -' ' I I I I I I I •• I I I. I I. I I I There are a numbt:!r of options which may to be considered for environmen-- tally acceptable disposal of the rock removed in excavating the tunnel. All of these will probab1y involve a small additional transportation and/or d1sposa1 cost, and include: stockpiling the material for use in access road repairS' construction of the re-regul at ion dam (total volume = 7. 7 Olillion cubic yards), or stabiliza:*:ion of the reservoir shoreline; ciisposal in Watana reservoir· dike construction; disposal in a borrow pit created in -dam constructions; sculpture, cover,_ and seed the pile; and disposal in a ravine cr other convenient location. Ii. is unli-kely that the most environ- mentally acceptable option will also be the most economical.. Because many unkno~n factors now exist, a firm recommendation cannot be made without further evaluation. It is quite likely, however, that a combination of diSposal methods will be the best solution. Stockpiling at least SO«~ of the material for access road repairs is believed to be environmentally acceptable provided a suitable location is selected for the stockpile. The material could poss·ibly be utilized for construction of any of the .. access road spurs or temporary roads that are. not already completed at the time the tunnel is excavated. Another acceptable solut·ion might be to stockpile the material :or· us.e in construction of there-regulation dam. This rock could also be a potential source of material for stabilization of reservoir shorelines if required. As with the previous option, an environmentally acceptable stockpile loca- tion would be required. Material disposal in Watana Reservoir might also be environmentally acceptable.. A small Jmount of tunnel muck could possibly also be used for stream habitat development. With any of these options, the pass ible toxicity of minerals exposed to the water should be first determined by assay, if there is ar1y reason to suspect the occurrence of such materials and minerals. ~-,,'0 env·ironmental problems might b~ solved by disposing of the material in a borrow pit created in dam construct ion. To sculpture·, cover, and seed the material is worthy of further considera- tion~ and would require proper planning. For example, borrow areas used ir. darn construction could, perhaps, be restored to original contour by this method. The source of soil for cover is a major consideration as earth should only be taken from an area slated for future disturbance or inunda- tion" The most economic a 1 so 1 ut ion might be to fi 11 a ravine with the materia 1 or to dispose of it in another convenient location. Unless the chosen dispos- al site will eventually be inundated, however, such an arrangement is environmentally unacceptable, especially since _better· options are obviously available .. 7-5 . .,.,, . I I I I I I I I I . I I I I I [ TABLE 7." 1: ... Drill Hole l3H-4 SH-2 frrt,.1 BH-Z BH-6 BH-8 DRILLING RESULTS AT WATANA AND DEVIL CANYON DAM SITES Percent of Cot"e Q!=.e~h . ( ft) ROD>~D SO<RCO<BrJ Rac<:srr (~86 76 16 8 ·. 623 89 8 3 738.4 87 9 4 391 46 28 26 732.4 78 19 3 736.7 70 21 9 7-6 ~ l -J ---~--------------- Diameter {ft) Two Tunnels 20 25 30 3.5 One Tunnel 30 35 40 45 50 Notes: . (1) tnstalled Capacity Davi! Re~~egulation Wat.ana Canyon Dam (MW) (MW) {MW) 850 850 850 800 875 880 800 900 900 115 220 300 400 i90 J10 JOG 375 380 1fl0 50 30 50 30 30 30 30 TABLF 7.2 -OPTUUZATION Of TUNNEL DIAt£TER ------------------------------------ Maximum Head loss (ft) 97.5 !18.0 45.6 30.5 86.0 94.0 33.4 19.9 9~8 Maximum Velocit~1 ) (fps) 5.6 6.8 5.9 5.6 8.1 9.9 6.5 6.3 5.0 Tunnel Alt2rnatl~a Annual Net B~nefif 2 > ($ ~ 106 ) 1.0 29.9 34.7* 29.4 31.9 44.7* 44.7* 42.9 35.8 Tunnel Alternative Annual Net BenefifJ) ($ X 106 ) (17 .3) ( 1.5)-11 ( 1. 7) ( 9.0) 3.1 9.3* 7.1 3.4 ( 3.9) Velocity in unlined tunnel section. (2) 0 Cost of Energy Produced (mills.Jbh) 45 .. 2 30.6~ JO .. &'* 34 .. Q 28 .. ~ 2$ .. ~-il'< 26 •. S 2B •. S 31.7 Based on an ener~y value of 47 mills/kwh, (i.e. the thermal system cost in the year 2000). This value used in this stucly. (3) Based on an energy value of 30 mills/kwh, (the average Watana-Devil Canyon Dam hydrosystem cost L"l che year 2000. * Optimum tunnel diameter. ,1'····· } I I I I I I I I I I I I I I I I TABLE 7.3: COST ESTIMATE FOR DEVIL CANYON TUNNEL SCHEME (TWO 30-FOOT D1At£TER TUNNELS) 1980 ~RICE LEVELS Item Cost ($1 1 000) Land and .Damages • ·• • o •••••••• , ••• ,., • .• • • • • • • • • • • $ Reservoir Clearing •••••••••••••••••••••••••• Re-Regulation Dam ..•••.••••••••..••...•..•..• 10,200 3,300 101,900 41 '700 34,800 26,000 Spillway ...... , •.•..• __. .............. " ........•.•.• Diversion Works ••••••••••••••••••••••••••.••• Intake Worke -Main .......................... . Power Tunnels· .•• .., •• Q ••••••••.••• u ••••••••.••••• Powerhouse -Main •••••••••••.• .., ................ . "Tailrace:__., Main ............... o••••••••o•••••• Switchy~rd ................................. o • ~ • Transmission lines. .. ........................... . Reacts and .6r idges • , .. __ ......... , ................... . Recreational Facilities ...................... . Bv.llding e.!1d Grounds • • • • l •• , ............... .. Permanent Ope~ at ing Equi .. 11ertt •••• Q •••••••••• Secondary Powe~~ Station ..... ,, •••• ~ ••••• ~ ••••• Ca~Jl) facilities and Suppnrt •••••••• ~ ........ . Mobil.izat.ion ••.••. o .......•• '!" ........ , ...... ~ ••• ~. TOTAL CONSTRUCTION COST • u .................. . Engineering, Construction, Management and Owner 1 s .f:osts ••••• ., ••••• e 11 •• ., ••• o."" ........ _., •• Continge ,cies .•••••••••••••• , .•• ,, .............. . TOTAL PROJECT COST •••••••••••••••••••••••••• 7-8 556,600 80,300 13,000 3,500 15,000 42t000 1t000 4:.000 3,000 21 t4.QQ 957,700 '130,700 _--..;,:..;...7 '000 $1,136,300 136,400 227,300 $1 ,500_.000 ,_ I I I I I I I I I I I I I I I I I I I TABLE 7.4: COST ESTIMATE FOR DEVIL CANYON TUNNEL SCHEME (ONE 40-FOOT DIAMETER TUNNEL) 1980 PRICE LEVELS !te.~ Land and Damages •••.••••••••••••••••••• _.. •••••• Reservoir Clear~.ng ••• ? ................... .,. •••• Re--r,egulation Daa-n •••••••••••••••••••••• a •••.•• Spillway ·~···~····,··········~··············· Diversiofi Works ·····················•••••o••• Intake W~rks-Main •••••••••••••••••••••••••• Power Tunnel • ~ •• ~ ••••••••• t'! ................... . Powerhouse-Main •••••••••••••••••••••••••••• Tailrace -f.iain ............ " •••••••• ·~ ••••••••••.• .SwitChyard ••••••••••'•••••••••····~o••••••••• Transmission lines ••••••••••••••••••••••••••• Roads and Br idg.es ............................. . Recreational Facilities ••••••••••••••••• ~ •••• a·uilding and Grounds •••••••••••• ~ •••••••••• -#. • Permanent Operating Equipm~~nt ••••••••••• " • ~ •• Secondary_ Power Station •••••••••••••••••••• ". Subtotal •··············~····················· C~ Facilities and Support .................. . Mobilization -o ................................... . $ $ Cost ($1zDOO) 10,2iJO 3,300 101 '900. 41,700 34,800 26,000 453,100 80,300 13,000 3,500 15,000 42,200 1,000 4,000 3.000 21~400 854,400 117,000 42.%700 TOTAL CONSTRUCTION COST •••••••••••H••·····•·"$1,014,100 Engineer;.,ng, Construction? Management an:.. Owner•s· Cost ······~···*······················ 121,700 Conting~ncies .•••• : ••••••••••• ~ .••••••.•••.•••• _202,800 TiJTAl.. PROJECT COST ................. u ..... ,, ... $1 ,3.38 1 600 7-9 I I I ·I I I I I I I I I I I I I I I I TABLE 7.5: POWER AND ENERGY PRODUCTION FROM TUNNEL SCHEME Description Installed Capacity: Watana Darn .•••••••.•••• G' o .••••••• Devil Canyon········~~········ Re-regulation Dam .............. . TOTAL .... ., .......... -~ ...... -····· Average Annual Energr: Watana Dam •••o••••••••~•••••• Devil Canyon ~················ Re-regulation Dam ••. , •••••••• ., TOTAL ···················••w•• Annual Firm Energr: Watana Dam ..................... . Devil Canyon ••••••••••••••••• Re-regulation Dam •••••••••••• TOTAL •••·•••·••••~•••••••co-•••• 1-40 ft Diameter: Tunnels 850 MW 300 MW 30 MW 1 '180 M'/1 3,194 Gwh .2,064 Gwh '195 Gwh 5,453 G\ltl 2,810 Gwh 1,927 G\'kl 127 Gwh 4,864 G\'oh 7-10 2-30 Ft Diameter Tunnels 850 MW 300 MW 30 MW 1,180 M.W 3,192 Gwh 2,053 G\tkl 188 Gwh 5,433 G~ 2,833 Gwh 1, 925 G\'ll 127 Gwh 4,885 Gwh I I I I~ I I I I I I I I I I I I I I I . <: > '"'"EAR 1 I l ACCESS DIVERSION TUNNELS COFFERDAMS 'RE-REGULATION DAM PONER TUNNELS iNTAKE STRUCTURE . MAIN PO\YER PLANT~ . POWER/SURGE CHAMBER • > POWERHOUSE DRAFT TUBE TAILRACE . TRANSFORMER GALLERY - TUBINE I GENERATOR !MPOUNOMENT - TEST AND COMMISSION SECONDA~ POWER PLANT CRITICAL ACTIVITIES IIIIIIIIDIIIIU MAIN POWER PLANT .,411!11' ~...-FAt SECONDARY POWER PLANT 2 3 4 5 6 _t ' I . I l J l I> 1 ! I J J I I -· ' 111!1111 . lr. ~...-r...-.: - ~.....,.;>_.,..~ . ... l -~t ·. ..J t . .;. ~ I .... , , . .. J I ' ~!1111111111111111111.11111111 lllllllllllllllllllllllllllllfl 11111111 1 . I -l ~- " J -I -:-n--1 J • 'lllmi~;IGIIIIII!III IIIIIIIIUJIIIIIIIIf,lllllllllllll ••••••• 11118111! -•. 1 UNIT I ON-LINE .... . e {UNIT 2 ON-LINE "~ ,::...,.,-...-r...,...,.~..., .. ~~.,......,~...,~.IJI" . .,..,...,~AI!JI'..-r,., ... , " . " EARLIE~T StART OF ACTIViTY . I EARLIEST FINISH. OF ACTIVIl'l' -LATEST FINISH ,-f TOJAL .. ,.(OF ACTIVITY ·II(!-FLDAT - CoNSTRUCTION ·SCHEUULE PREFERRED TUNNEL Su,iEME 3 -" --:?~--~; -- ¥----------------~-=------------------....... _.......,.. ______ ,_...._::.,;,· _____ _.........,.,.._. __________ ,_. ___ .....,;__:.__"_""'''~-··' . _ ___,_ _ __;..._.....;........ ~'--"- 7 l I f I • ~ - ' l --- . . " FJGURE 7.1 fiil .. I I I I I I I I I I I I •• I I I I I I 8 -COMPARISON WITH.OEVIL CANYON DAM SCHEME This section outlines a brief comparison of the preferred tunnel sch~me with the Devil Canyon dam scheme. The schemes are compared from economic, environmental, and scheduling points of view. 8.1 -Economic Comparison Table 8.1 summarizes the results of the comparative economics of the two versions of the tunnel scheme involving either one or two tunnels and the Devil Canyon dam scheme. The economic parameter·s used are as follows: Interest rate = 3%. -Esca1 at ion rate = 0% .. -Economic 1 ife = 50 years .• -Annua 1 cost factor = (3. 00. interest +0.89 -sinking fund +0.10-insurance} = 3.99 -Operation and maintenance = $11/kW/year. -Allowance for funds during construction was based on an assumed S-shaped distribution of cash flow throughout the construction period. The average annual energy yields in Table 3.1 represent the net increases over the first stage Watana dam in each case. It wi 11 be noted that the on~ and two tunnel schemes can de 1 iver energy at a cost of $27 or $31 per 1000 kWh, respec- tively. The equivalent cost associated with tile Devil C::.myon dam is $14 per 1000 kWh. The tunnel scheme represents a 93 or 117 percent increase in cost. It should also be noted that the tunnel schemes; :tually yield between TIC and 790 Gwh less energy than the Devil Canyon dam scheme. This represents about 26 percent. A further factor that shou'Id be taken into consideration in the economic compar- ison of tne t.~.mnel and dam schemes is the lower reliability associated with the capital cost estimate of the tunnel scheme. Because of the uncertainty associated with the geologic conditions as well as the probable availability of more· sophisticated tunnel construction methods in the next decade; it is conceivable that the tunnel costs estimates could vary wide1y. For purposes of this study, sensitivities have been check(,. by assuming that tunnel costs could be doubled or halved. Allowing for this ;;otential range in tunnel construction costs and still incorporating a 20 pe~cent general contingency the economic analyses shown in Table 8.1 were rspeated and the results are summarized on Table 8. 2. Tabie 8.2 c'fearly indicates that even allowing for the unr~rtainty associated with the costs of the tunnel scheme, the Devil Canyon da~ scheme is st·lll economi_cally superior. 8-l 8.2 -Environmental Comparison At present, many gaps exist in the available environmental data. Additional information, combined wit(l environmental field investigations would permit a much more detailed comparison of these two development alternatives. Neverthe- less, from what is presently understood about Scheme 3, it is believed that it is environmentally superior to the Watana-Devil Canyon dam scheme. By virtue of size. alone, construction of the smaller re-regulation dam (245ft) would have less environmental impact than the Devil Canyon dam. The river miles flooded and the reservoir area created by the Scheme 3 re-regul at ion dam would be about half those of the Devil Canyon dam, thereby reducing negat"ive consequences such as loss of wildlife habitat and possible archeological. sites. In addition, the adverse effects upon the aesthetic value of Devil Canyon would be substantially lessened with Scheme 3, particularly with the powerhouse location upstream of the Devil Canyon dam site. Furthermore, Scheme 3 may possibly present a rare mitigation opportunity by creating new salmon spawning habitat that could be actively managed. With the increase in riparian zone vegetation allowed by Scheme 3 the wildlife habitat in the stretch of river bypassed by the tunnel might be temporarily i.mproved. It is believed that the impacts associated with tunnel access and disposal of tunnel muck would be offset by the plan's advan- tages. 8.3-Comparison of Construction Schedules As shown in Figure 8.1, the construct ion duration of the tunnel scheme is approximately one yer;.r shorter than the darn scheme. Construction startup to power on 1 ine for the darn scheme is approximately 66 months while the tunnel scheme is 52 months. The dam scheme's critical path is controlled by dcun con- struction and the tunnel scheme is controlled by poNerhouse construction. There is about a 6 month float period in the construction associated with the tunnel and this could accormtodate some of the potential construction delays which are mar~ likely with the tunnel than the dam Jcheme given the limited geologic in format ion. The construction schedule for the tunnel a1te:·nativ"e is based on the assumption that an access road from the Parks Highway to W<r ana ·is avail able. Shouid this not be the case, access by a new route from Watana., presumably via the Denali Highway, will be required. The same is clearly true for construction of the De vi 1 Canyon. However, additional costs wi 11 arise due to a considerably longer haul distance -For equipment and materials from Anchorage and/or Fairbanks. 8., 4 -S uf11llary The compar-ison of the tunnel schemes with the Devil Canyon dam sche1rne indicate that the dam would yield appro,<imately 36 percent more en<!rgy at a 49 to 54 percent lower energy cost. From an environmental viewpoint, the tunnel scheme :1as advantages, however, these do not appear to outweig.._t the economic benefits of the dam schemes,. From a construction schedule po·in' < F view there is 1 ittle difference between the schemes. It should be borne in mind that the reduced environmental impact outlined in Section 8. 2 would have to be traded off against the higher cost and lower energy production of the tur·~el scheme. This can be quantified in two ways as outlined bel ow. 8-2 I I I •• I I I I I I I I I I I I I I ,'I ..•. '. ' ' I 'I .... ' I I •• i •• I I I I I I I I I I {a) Environmental-Capital Cost Tredeoff The total increase in capital cost between the Devil Canyon Dam Scheme and the more expensive tunnel scherne amounts to $500 to $700 mill ion o These figures are derived by assuming a base fixed cost of 30 percent and prorating the remaining 70 percent of the Devil Canyon dan costs downwards by the ratio of the average annual energy yield of the tunnel schemes to that of the dam s~heme. (This hypothetically results in a Devil Canyon Dam capable of producing energy equal to the tunne"~ scheme for a capital cost of $0.80 b i 11 ion. ) The environment a 1 benefits to be gained in terms of about 16 miles of Susitna River and Devil Canyon which would not be inundated, would not appear to be justified by this additional cost. (b) Environmental-Energy Tradeoff The tunnel schemes yield approximately 770 Gwh less energy on an annual basis than does the dam scheme. In the long term this implied that an additional gener"\ting facility would have to be provided to generate this energy when required and this would create an additional source of environmenta 1 impact and cost ·.vh i ch has not been factored into the comparison at this time.· 8-3 ' l. I I ~ I I I I 1-, ' I I TABLE 8.1: SUMMARY OF ECONOMIC EVALUATIONS (Million Dollars) Total Investment Cost: Total Project Cost Construction Period (years) Allowance for Funds During Construction ( i = 3%, e = ~)* \ Annual Cost: Amortized Cost ( i = J%, 50-year economic life) Operation and Maintenance Cost (® $8/kW) <} Cost Per kWh: Increase in Average Annual Energy (Gwh)** Cost of Additional Energy ($/1000 kWh) Relative Cost of Power (Devil Canyon Dam = 100%) * ~ = ~ntereSt rate, e = escalation rate Scheme J 2-30 Foot Tunnels $ 1,500 5 121 $ 1,62' $ $ 63 4 67 2,183 30.6 217 Scheme J i-40 foot Turnel $ $ $ $ 1.339 5 108 1,447 56 4 60 2,203 27.3 193 ** Increase over single Watana damJ 800 MW devel~ped with an average annual production of 3250 Gwh 8-4 Devil Canyon Dam $ $ $ $ 903 6 81 ~ 984 38 4 42 2,997 14.1 100 I I I I I I ...... t· ·-~ ' I I ' I ~- 1 I I I I I I TABLE 8.2: SUMMARY Of ECONOMIC SENSITIVITY EVALUATIONS (Million ._. ,llars) Tutal Investment Cost Including AFDC -maximum* -minimum** Cost per kWh ($ per 1000 kWh) -maximum -minimum Relative Cost of Power (Devil Canyon Dam = 100%) -maximum -minimun *Based on doubled tunnel costs. *"Gased on halving tunnel costs. Scheme 3 2-30 foot Tunnels 328 149 Scheme 3 1-40 Foot Tunr.el -··".:-.!!If $ 2,213 $ 1,063 39.6 19.3 281 137 I· ~-;:.t I I I I t I I ' I I •• I ' I •• I I I ' YEAR PREFERRED TUNNEL SCHEME ACCESS COFFERDAMS AND DIVERSI~~N kt:-REGULATION DAM - POWER TUNNELS MAIN POWER PLANT IMRXJNDMENT TEST AND COMMISSION SECONDARY POWER PLANT DEVIL CANYON DAM ACCESS COFFERDAMS AND DIVERSION SPILLWAYS DAMS POWERPLANT IMPOUNDMENT TEST AND COMMISS!ON 8 6 - I I l J I 3 ,_ ~ . ' .. I ,- I F *' -I •• ' •' . ~~·--·- !; -,...- . 2 3 4 5 6 7 I I ..... ~-~-1 _1 1 I I ·t I 1_ I -1 1 I ' 1 _1 52 MONTHS-I I - ' " • - - . --··-, 1 UNIT I ON-LINE -.. -' UNI"f ON-LINE 1 -< ' I 66 MONTHS -I . ! . ·~ ~~ . • " >;..- ~ ., ,, ~-..... ~. . . . ; -I . UNIT i QN-UNEJ tl'!);olil~~·....-..: ·=--'""~ . CONSTRUCTION SCHEDULE COMPARISON [Ail FH;URE B .. t w..·~·.i :( " t 1: I I I ' ' I I I ' I ~~ ' ' t I I I I 9 -CON~LUSIONS AND R2COMMENDA.TIONS 9.1 -Conclusions The conclusions of this study are: -A base load tunnel scheme incorporating are-regulation dam downstream f1·om the Watana dam site and developing the head that could be developed by th~ Devil Canyon dam is the most economic typE:' of-tunnel scheme . .. There is no evide~ce that the tunnel scheme is not technically feasible. How- ever, a substantial amount of additio!"lal field data. would be required to firmly establish feasibility. -The estimated capital cost (excl!Jding AFDC) for the selected tunnel schemes varies from $1.50 to $1.34 billion depending on whether one. or two tunnels are required. The rar.ge of capital costs associated with a tunnel scheme could be as high as $2.37 billion or as low as $0.98 billion, i~e. from $1.06 to $2.37 bill ion or from $0.98 ·to $2.05 bill ion for the two and one tunnel schemes, respectively. -The tptal .average energy yield from the tunnel scheme is approximately 2200 Gwh over and above! that obtained from the Watana dam. - A comparison of the tunnel scheme with the Devil Canyon dam scheme indicates that it yie'lds less (26 percent) and more costly (93 percent to 117 percent) energy.. The potenti~1 environmental impact associated with the tunnel scheme is less than that of the dam scheme, but it is believed that this reduced impact is not sufficient to outweigh the economic advant:1ges enjoyed by the dam scheme. 9.2-Recommendations ~ The reconmendations resulting from this study are: -In o;jer to confinn the economic comparisons with the dam scheme the prefel-red tunnel scheme should be incorporated in the Susitna Basin development selec- tion studies. These studies incorporate a. systemwide generation planning model which will allow a more realistic assessment of the economics of the tunnel scheme to be made. -11:\dditional field or office studies of the tunnel scheme should not be under- taken at this stage. / 9-1 , I I I I I I I I t I I •• I I ' I I I I I BIRLIOGRAPHY 1. ASCE, Rock Engineering for Foundations and Sl_opes, Volumes 1 and 2, AugL'~t, 1976. 2. ASCE, Symposium on Underground Rock Chambers, Phoenix, Arizona, January .. 197lo 3. Bleifuss) De J., "Theory for the Design of UnGerground Pressure Co,tduits 11, Powe.r division, ASCE, V. 81, July, 1955. 4. Brown, Hydroe1ectric Engineering Practi~e, Vol. 1, Blackie and Son, Limited~ 1958: 5, Colebrook 9 11 The Flow of Water in Unlined, Lined, and Partly Lined Rock Tunne 1 S 11 , 1958. 6. Cooke, J.B., Libby, J.W., and Madill, J.T., "Ker.tano Tunnel Operation and Maintenance", The Engineering Journal, August, 1962. 78 Cording, E.J., Mathews, A.A., and Peck, R.B., "Design Criteria for Permanent Structural Linings ror Station Excavations in Rock) Washington Metropolitan Area Transit Authorityt', Prepared for DeLeuw, Cather and Co., July, 1976 .. '•. 8. Cummins, A.Bo, apd Given, LA., SME Mining Engineering Handbook, The · American Institute of Mining, I'I~Ctallurgical andPetroleum Engineers, Inc., · Volumes 1 and 2, 1973 . 9. Davis and .Sorensen, Handbook of Applied Hydraulics, McGraw-Hill, 1969 • . - 10. Deere, D.U .. , et al, 11 Design of Tunnel Liners and Support Systems 11 , Univer- sity of Illinois, 1969. 11. Dowding, C.H., and Rozen, A., "Damage to Rock Tunnels from Earthquake Shakingn, Journal of the Geotechnical Engineering Division, ASCE, February, 1978. 12. Eckenfelder, G.V., "Spray Hydroelectric Power Development", The Engineering Journal, April, 1952. 13. Hamel, L. and Nixon, D., 11 Excavation of World's Largest Underground Powerhouse 11 , Journal of the Con~truction Division, ASCE, September, 1978. 14. Hampton, D. and McCusker, T.G., 11 Economic Potential of Tunnel Standardiza- tionn, Journal of the Construction D,ivision, ASCE, September, 1980. 15. Holda, J., 1'Tunnel-driving Techniques Until the Year 2000 11 , May, 1980. 16. Huber, W.G., 11 Kemano Penstocks 11 , The Engineering Journal, Nov. 1954. BIBLIOGRAPHY (Cont'd) 17. Jaeger, C., "Present Trends in the Design of Pressure Tunnels and Shafts for Underground Hydroelectric Power Stations", Proceedings of Inst. of Civil Engineers, March, 1955. 18. Lawton, F.L., and Kendrick, J.S., 11 Nechako-Kemano-Kitimat Hydroelectric Power Development and Aluminum-Reduction Pl ant 11 , "'"he Engineering Journal, September~ 1952. 19. Maevis, A.C., and Hustl"Ulid, W.A., editors, Proc~edings-1979 Rapid Excavation and Tunneling Conference, Volumes 1 and 2, June, 1979. 20. McFeat-Smith, I., and Tarkoy, P.J., "Site Investigations for Machine Tunneling Contracts 11 , Tunnels and Tunnelling, Vo1. 12, No. 2, March, 1980 9 P 'JI." g. vO. .. 21. Moavenzadeh, Fo, and Markow, M.J., 11 Simulation t•bde1 for Tunnel Construction Costs", Journal for the Construction Division~ ASCE, March, 1976. ,, 22. "~oye, D. G., 11 Rock Mechanics in the Investigation and Construction of T.l. Underground Power Station, Snowy Mts., Australia", Engineering Geology Case Histories, Number 3, Geological Society of Jlmerica, Inc., 1964. 23. : .Jnsey, T. E., 11 Unique Features of the Snettisham Hydroelectric Project••. 24. Obert, L., and Duvall, W. I., Rock Mechanics and the Design of Structures. in Rock, John Wiley and Sons, 19 -- 25. Parker, A.'u., Planning and E.ltimating Underground Construction, McGraw- Hill, 1970. 26. Patterson, F.W., Clinch, R.L. and McCaig, I.W., 11 Design at Large Pressure Conduits in Rock 11 , Journa.l of the Power Division, ASCE Proc., Vol. 83. 27. Proctor, R.V., and White, T.L., Rock Tunneling with Steel Supports, Commercial Shearing and Stamping Co., 1946. - 28. Richardson, H.W. and Mayo, RoS., Practical Tunnel Drivi.ng, McGraw-Hill, 1941. 29. Rosenstrom, S., 11 Kafue Gorge Hydroelectric Power Project", Water Pmver~ June-July, 1972. 30. Rousseau, F .. , i•Bersimis-Lac Casse Hydroelectric Power Development", The Engineering Journa 1, April, 1956.. - 31. Sta.gg, K. G. and Sienkiewicz, 0. C., Rock Mechanics in Engineering Practice, John Wiley and Sons, 1968. i I I I I I I I I i I 1':! -= I ,, I I I I I I " I I I I I I I f I I • I ' I I I I I I BIBLIOGRAPHY (Cont•d) I 32. Tarkoy, P. J., ;'Predicting Raise and Tunnel Boring Machine P~rf ,rmance: State ;f the Arts 11 , 197S RETC Proceedings, vol. 1. 33. Terrestrial Environmental Specialists, Inc., 11 Pr~l iminary Environmental Assessment of Tunnel Alternativesu, December, 1980. 34. U.S. Department of the Army, Corps of Engineers (Alaska District), Final Environmental Impact Statement, Hydroelectric Power Development, Upper Susitna River Basin, Southcentral Railbelt Area, Alaska, Anchorage., Alaska. 35. U.S. Department of the Army, Corps of Engineers (Alaska District), Hydroelectric Power and Related Purposes: Southcentral Railbelt Area, Alasl<a Opper Susitna R1ver Basin -Interim Feasibility Report, Anchorage, A 1 ask a, 1975. 36~ U.S. Department of the Army, Corps of Engineers (Alaska District), Hydroelectric Power and Related Purposes: Southcentral Railbelt Area, Alaska Upper Susitna River Basin-Supplementary Feasibility Report •.. , 1979. 37. U.3. Department of the Army, Corps of Engineers, Tunnels and Shafts in Rock, EM 1110-2-2901, 1978. 38. U.S. Department of the Army, Corps of Engineers (Al a~ka District), 11 Snett ish am Hydroelectric Project" . 39. U.S. Department of the Interior, Bureau of Reclamation (Alaska District), Vee Canyon Project, Susitna River, Alaska: Engine~ering Geology of Vee Canyon Dam Site, Sacramento, Ca 1 iforn ia, 1962. 40. U.S. Department of the Interior Geological Survey, Reconnaissance Geologic Map and Geochronology, Talkeetna Mountains Quadrangle, Northern Part of Anchorage Quadrangle, and Southwest-:Gorner of Healy Quadrang1e!P A 1 ask a, 1978~ . 41. Vasilescu, t4. S., Benziger, C.P., and Kwiatkowski, R.vJ., 11 Design of Rock Caverns for_ Hydraulic Projects••, Underground Rock Chambers, ASCE, 1971. 42. Wheby, F .•• and Cikanek, E.M., 11 A Computer Program for Estimating Costs of Tunneling", Report prepared for Federal Railroad Administration by Harza Engineering Company, Chicago, Illinois, October, 1973. 43.. Woodward-Clyde Consultants, :•Interim Report on Seismic Studies for Susitna Hydr~electric Project ... , January, 1981 .. I I I I I I I I I I I I -1 - I I I I- I I .. PLATES <%&&$ - ' I I I I I I I I I I I I I I I I I G F E _,. D c B i- ~ lc z 2 Q ~ ~ ti 2500 Ul "- :z 2 l2CCO 0 ~ ~ 1500 hi 10 0 to SUQf. T~lf. ......_~, ~L,lL..A.iiON, Cl4t>1· sc~ r 7 -·---.:~\-----~ ~TEJ<NATIVE DI<Sc;.:r A..I..JG. NMENT \\ ·/(): ----L . (5GHE.M&.~I,2.4) PO~SE-------.~ : INTAKE/ Y, \----SCHEME ' . . ----; 1-lEl.\'l!:~ '2.(4) /.~ \ £:. NQ!:l .. · TI-IERN ALIGNMENT ----J,. . .J -~-.,...._,..____ ~EMES I."Zf4) -----~ -----. --sc~ "29;4 '--_..---------. -------·-. --------SUICG£. TANl(. TUNNEL PLAN ~---------~-~------... _.......,... __ ~ MILES ,_ -·· POWER TUNNE.t.. ri...OW 'SURGR TANIC. - ' . 5C~EME I --~-~· . -r-------------· --------------------._,.,~ --------~---------------.------------------.--,--------------- 1~). ACCE.$S AOJ-? (RA.n.) e ________________ , __________________ -=:-=.=======:;.~= I& DlSTANCE. IN MIL.E.f> NORT~ERI'-! ALIGNMENT (scl-tE.ME.S I, 2 44) SUR.G~ TA.NIC. OISTANC£ tN Mll..£5 25 0\RECT ALIGNMENT (SCl-!E.ME.S 1,'2. 44) ~OTEs: l) ,J~L. .AL!Gio!M~ ~ 11ic;I;I1JI.~E ~ lS S~OWN ON OAAW\.~ ~ 5'lOO"CGt•tr- 2.)AU.. PLANS ~D ~5 ~ CONCEPTLIAI. ~ ~· Qp.L'y. CONCEPTUAL TUNNEL SCHEMES PlAN a SECTIONS I . ' I G ,, I F I I I E I 0 I I c I I I B I I < ... ~ -~ I i I i 1!100---- SUS ITNA 18100 -~·-. · .. Ft..ow - l t 5CJ-4E.ME. ~ PLli..N SCA.LE 0 2 MILE. GE.NERA.L AJ2RA~E.ME.NT &E• f2E.GULtqlO~ DAM scAJ._£ 0 • .. ------. .... ~-.,_ ................ ____ . .._.._ ... ; .. ~--t .... • • ' • • • , r • , -" • • .-• '"": ~~ .r--.w ,6 -- --· NOT.E.: ALt. PLANS AND t.A.YOUTS FOQ. CONd:.PTU.t.l... .STUDY~ Ot-ll-'1, t DAtt • GE.N~RAL. ARRANGE.ME.NT DEVIL. CA~yoN · B;?tiE:.RJ40USE. SCAl-E 0 .. 00 :eoo F£.ET I I .. I • G so~E-T~K o&V1l-~o~ t:~awER.~ouea F E 0 c • PLATE 2 L. [i] ... It. ·.-:-:-~~A ~~lASKA POWEll AUTHOiliTY IUIIITIIA 11YOIIOHII:::'f •. 'lt PIIOJirC'r PREEERRED TUNNEL SCHEME 3 PLAN VIEWS - I I I I I I E I ~ 0 I I I c I I B I I I I I .. I B ~ --.._ :: "%. 0 t:: < > .. ~ "' .... --.. "" "eo MOO ·~ ~ "DO % 0 ~ .. 1500 ~ ... l~llO RE-REGULATION DAM TYPICAL SECTlON .UX.NOit .. At WUATIMI LIV!L 1Lt475\.-- ~ ......... -::-tii I " ~--il'"'' POWER TUNNEL INTAKE SECTION NOJtMll. MAX. ll.K7S' UNLINED SC:Al..E.: A 'f l A A ........... ~~--""" CONC. liNED w-'STEELSET SPILLWAY PROFlLE ~C<'.l-E.:A. SE.CtiON ~-A TYPiCAL TUNr-El SECTIONS c~to seAl.£) I t a ... !d ~ 2~t---~~--~----rt~~-+----~-+--~----~----~--~~--~~~~----~--~~~~4e~--~----+----~----~----~--~~· 1500 ... .. .. .. %IJOO z z 0 ~. ~~--~~--~--~~~-J~----~~~--+-----r-----~---4-----r ~ \ll _, Ill ------ . ----· ~ ---------------- l!o OISTANCZ 1"1 Ml~~ TUNN.E.L A.LlGNMENT ---------------. ----...:.____ ------ DEVIL CANYON POWER FACILf~"IES PROFILE' I" OIA.. ROCICMLT l IIETAI\.6 ('Tl'P.) AOCK BOLTS ROCK BOllS j SHOTCRETE . TYPICAL TUNNEL SECTIONS (NOT 1'0 SC: .... 1..;E) .-7 i I e DETAIL .A / G .. QOUT .. ·· A;$ RE.QUIIil£0 (NR.) ·~~F • r · OE.TA.! L'"e) $ MUi SCALE.~ A NOTE.: AU.. STIO!Ul:TU~ ANC Su~T DEiAI!.-'5 ·ARE CONCE.PTUA.L ~ FO~ STUDY PURPOSES OHI..'i'~ *"" t ... --J ' 3 t t -~ . '"" ~·o,,.,. T .. n .. 2.t..cE TUNNEl. PLATE 3 c • [i]. ·.1---A_lJ_.U_KA_·_ro_. w __ •. · __ .ER_._A_U_T_HOI_JTY_._··~ A lUll Til A MYDllCI;l.U:;T•tc: P.OitC:1i' PREFERRED TUNNEL .. SCHEME 3 SEC'flONS - l -- I I I I I I I I APPENDIX A I ROCK UNIT DESCRte.J.lflNS ( 40) I ·I I I I I I I I I ; ~ I I I I I I I I I I I II I I I I I I I • ROCK UNIT DESCRIPTIONS Tbgd Tsmg BIOTI1"E GRANODIORITE (Paleocene, in part may be Eocene) --Biotite granodiorite and adamellite in approximately equal proportiuns. Biotite is the chief mafic mineral, hornblende is occasionally jJtesent. Color is 1 ight to medit.m gray, grain size is from medium to coarse, texture is granitic to seriate. Very faint flow struc- tures have developed only locally. These rocks occur in shallow, forcibly emplaced epizonal plutons in the northwestern Talkeetna r.tluntains. Aplitic and pegmatitic dikes are common in all the p 1 utons. Just north of the map area, these p 1 uton ic rocks grade into felsic volcanic rocks. Potassium-argon age determinations (see Table 1) indicate that the biotite granodiorite and adamel- lite of the present unit are essentially of the s~s age as the biotite-hornblende granodiorite (unit Thgd). Thus, the rucks of these two units, in view of their spatial proximity, probably are the products of differentiation of the same parent magma, either in situ or at soma deeper levels in the E:\rth's crust. The biotite granodior·ite intrusives are also consid~red to be the plutonic equivalents of some of the felsic volcanic rocks in the 1 ower porticn of the unit Tv. ~SCHIST, MIGMATITE, AND GRANITE (Paleocene intrusive and metamor- phic ages) ---Undifferentiated terrane of andalusite and {or) sillima.nite-bearing pelitic schist, lit-par-lit type migmatite, and small graniti~ bodies with moderately to well-developed flow foliation. These rocks occur in approximately equal proportions, and the contacts between them are generally gradational, as is the contact between the schist and its unmetamorphosed pe 1 it ic rock equivalents {unit Kag) outside the present map unit. The· pelitic schist is medium to dark gray, medium grained!! has well-developed but wavy foliation, and contains lit-par-lit type granitic injections in greatly varying amounts. Rock forming mateials of the schist include· biotite (pleochroism Nz = dark reddish brown, Nx =pale brown), quartz, plagioclase, minor K-feldspar, muscovite, garnet, and sillimanite which locally coexists with andalusite. The 1 it-par-1 it type granitic injections within the schist are medium gray, medium grained, and consist of feldspar, quartz, and biotite. · The rocks of the small, granitic bodies range in composition from biotite adamellite to biotite-hornblende granodiorite. They are medium gray and medium grained, generally have granitic textures, and, in addition to the flow foliation, locally display flow band- ing of felsic and mafic minerals. These granitic bodies appe.ar to be the source of the lit-par-lit intrusions. Tsmg (Cont'd) Kag The proximity ofthe schist to the small granitic bodies, the occurrence of the lit-par-lit injections, and the presence of andalusite in the schist indicate that the schist is the result of contact metamorph·i sm. Perhaps this metamorphism took p 1 ac~ ·i r~ the roof zone of a large pluton, the cupolas of which may be the small granit~c bodies. . . ARGILLI;"~ A~~n· LITHIC GRAYWACKE (Lower Cr:-.etaceous) --These rocks occur in a monotonous, intensely deformed f1yschlike turbidity sequence_, probably sever a 1 thousand .meters thick, in the northwest part of the mapped area, north of the Talkeetna thrust fault. The whole sequence has been compressed into tight and isoclinal folds . and probably has been complexly faulted as well. The rocks are highly indurated, and many,are sheared and pervasively cleaved as a result of low-grade dynamometamorphism, the intensity of which is only locally as high as the lowermost portion of the greenschist metamorphic facies of Turner (1968). Most of the cleavage is probably axial plane cleavage. Neither the base nor the top of the sequence is exposed and, because of the intense deformation, even its minimal thickness is only an estimate. The argillite is dark gray or black. Commonly it contains small grains of detrital mica as much as 1 mm in diameter. Because of the dynamometamorphi sm, in large areas the argillite is actually a s 1 ate or fine-grained phyllite. Th .:, s sections show that some the argillites are derived from very fine grained siltstone and that they contain considerab1e carbonaceous material. The. typical 1 ithic graywacke is dark .to medium gray, fine to I') I. I I I I 'I I I I medi urn grained, and occurs i nterca 1 ated with the argi 11 i te in 1· graded beds ranging in thickness from laminae to about 1.5 m. The individual graywacke beds are not uniformly distributed throughout the whole sequence, of \'lhich they comrpise about 30 to 40 percent by volume, but tend to be clustered in zones 1 to 5 m thicko Thin I sections of graywacke samples show them to be composed uf angular · of subrounded detrita·t grains of lithic fragments, quartz, moderately "fresh plagioclase, and some, generally altered, mica in 1· a very fine grained matrix; euhedra 1 opaque grains, probab 1y authigenic pyrite, are present in most thin sections. The lithic fragments consist in various proportions of little altered, I fine-grained to aphanitic volcanic rocks of mafic to intermediate . composition; fine-grained, weakly foliated low-grade metamorphic rocks; chert; and some fine-grained unmetamorphosed sedimentary 1 rocks possibly of intraformational origin. No carbonate grains · were seen. The matrix. constitutes about 20 to 30 percent of the rock by volume, generally contains some secondary sericite and chlorite~ and, in the more metamorphosed rocks :t biotite and I possibly some amphibole. . · A-2 I I lc I I I I I I I I I I I I I I I I Kag (Cant 'd) Ana lyses of pa 1 eocurrent features, ·Such as sma 11-sca 1 e cross- ,.stratification, found in several exposures near the western edge of the mapped area, suggest that depositional currents came from the east or northeast (A.T. Ovenshine, oral commun., 1974j. Because fossils are extremely sparse, the exact age of the argillite: and lithic graywacke sequence is imperfectly known. A poor specimen of Inoceramus sp. of Cretaceous age was found just west of the map area between the Chulitna and Susitna Rivers~ and a block of Buchia-bearing limestone of Valanginian age was found in float near Caribou Pass in the Healy quadrangle north of the mapped area (D.L. Jones, oral commun., 1978). A-3 -l I