Loading...
HomeMy WebLinkAboutAPA1344I I I I I I I I I I I I I I I I I I I • AL~SK~ POWEP AUTHORITY SUSITNA HYDROELECTRIC PROJECT TASK 8 -TRANSMISSION SUBTASK-8~02-PROGRESS REPORT ELECiR I C SYSTEf~ STUDIES ·!> MARCH 1981 ACRES AMERICAN INCORPORATED 1000 Liberty Bank Building Main at Court Buffalo., New York 14202 I I I •• I I I I I I I I I I I I I I I ALASKA POWER AUTHORITY SUSITNA HYDROELECTRIC PROJECT TASK 8 -TRANS.tvtiSSION SUBTASK 8.02 -PROGRESS REPORT ELECTRIC SYSTEM STUDIES TABLE OF CONTENTS f_age LIST OF TABLES • • • • • • • • • • • • • • • • • • • .. • • • • • • • • • • • • • • • • • • • • • • • . • • • • • • • • • • • • • i i ; ,., .. • • • • • • c • • • • • • • • • • • • • • • ~ • • • 0 • • • • • • • • • • • • • • • • ~ • • • • • • • • • • • • LIST OF FIGURES 1 -INTRODUCTION •••••••••••••••• ·• ••••••••••• & •• ~ •••••• 0 ••••••••••••••.••.• 1 .. 1 -Background ................................................... . 1. 2 ·-Repo.rt Contertts ........................... ~ ......•............ 1-1 1-1 1-1 2-S.UMMARY .................................................. ,. .... ;~ ....•. 2-1 2 .. 1 -Scope of Work .................................................. ·2-1 2 .. 2 -Reports Reviewed ..•.............. 8. • • • • • • • • • • • • • • • • • • • • • • • • • • 2-1 2.3-Planning Criteria ........................ ·, ..................... 2-1 3 -APPROACH ......... ,. .....••...•........ ·.. . . . . . . .. . . . . . . . . .. . . . . . . • . .. . . . . 3-1 4 -DESCRIPTION OF STUDIES AND PRELI~UNARY RESULTS ...................... 4-l 4.1 -System Data Assembly ...................•.•................... 4-1 4:2 -System Load Distribution •...•.•....•..•.......••............. 4-1 4.3 -Description of Studies ................................ o ••••••• 4-1 4.4 -Preliminary Results of Studies ............................... 4-3 5 -GENERf.\L COMMENTS •••• · • • • • • • • • • • • • • • . • • • • • • • • • • • • • . • • • • • • • • • • .. • • • • • • • 5-1 APPENDIX A -PROPOSED PLANNING CRITERIA B -TRANSMISSION LINE -ECONOMIC CONDUCTOR SIZE ATTACHMENT -LETTER TO APA, DATED MARCH 24, ~:981 SUBJECT: TRANSMISSION LINE CHARACTERISTICS i I I I I I I I I I I I I I I I I I I I LIST OF TABLES · Number 4.1 4.2 4 .. 3 Title Page Staging of the Susitna Development •..•....•...•.•••.......... 4-5 Maximum Power to be Transmitted to Anchorage and Fairbanks For Each Stage of Susitna Development ........... 4-5 Line Losses· Under Maximum Power Transmission ................. 4-6 ii I I I I I I, I I I I I I I I I I I I I LIST OF FIGURES Number Title 4.1 345 kV System···············"·············--·············· ... ···· 4-7 i ;·; I I I I I I I I I I I I ·I I I I I I I 1 -INTRODUCTION 1.1 .... Background The Plan of Study {POS) for the Susitna-Hydroelectric Project, which is current- ly being undertaken for the Alaska Power Authority by Acres American Inc. includes studies of the required transmission system under Task 8. Subtask 8.02 of Task 8 is entitled Electric System Studies. The objective of this subtask, as defined in the February 1980 POS is as follows: uro ensure that the electrical aspects of the project design are integra- ted with the existing Railbe,lt area power systems and to design an elec- trical power system which is reliable and economic ... The Transmission System for the Susitna Project, as currently envisaged, will ultimately involve 1 ines from the 1Jatana and Devil Canyon sites to both Fairbanks and Anchorage. The system will also be compatible \'lith ·the proposed intertie between Healy and Fairbanks which is presently under study for the A1 aska Power Authority by Commonwealth Associates. · \~ork on Subtask 8.02 commenced in June 1980 .and is scheduled to be complete by March 5, 1982. The purpose of this progress report is to present the resu1ts of work c_ompleted under Subtask 8.02 through February 15, 1981-. 1.2 Report Contents A summary of the report is presented in Section 2 and the approach adopted in the studies in Section 3. A description of studies undertaken and a discussion of pre11min~~.Y results follows, in Section 4. Gene·ral comments on the results to date are presented in Section 5. Appendices A and B and an attachment are also included ~s support documents which have been issued to advise APA of early study findings. · 1-1 I I 2 -SUMMARY •. 2.1 -Scope of Work I I ••• I I I I I I I I I I I I ·~ The scope of work includes the following: planning criteria -system data. assembly -power delivery points -line loading ·preliminary system configurations -preliminary cost for alternatives -preliminary screening of systems -recommend transmission configuration, voltage, and conductor size. 2.2 -Reports Reviewed The following reports were reviewed as to content relating to the scope of work. .. -U.S. Corps of Engineers/Alaska Power Administration -Susitna Hydroelectric Project Interim Feasibility Report .. Sect ion H -Transmission System, December 1975. -International Engineering Co, Inc/Robert H. Retherford Associates Economic -Feasibility Study Report, December 1979. -Institute of Social and Economic Research -Electric Power Consumption for the Railbelt: A Projection of Requirements, May 1980. ,. -Woodward -Clyde Consultants: Forecasting Peak Electrical Demand For Alaska's Railbelt! draft September, 1980 and final report December, 1980 - Subtask 1.02o -Subtask 1.01 -Closeout Report, Review of ISER Work December, 1980. -Corrmonwealth Associates Inc -Anchorage -Fairbanks Transmission Intertie draft November, 1980. -Commonwealth Associates Inc -Anchorage -Fairh ... nks Interconnection Fe as ib il ity Study, January, 1981. -Subtask 6.36, Generation Planning-Preliminary Information. 2.3 -flanrling Criteria System planning criter·ia (Appendix A) \'/ere submitted to APA in ·August, 1980. The system study assumes a fully developed Susitna potential so that final system parameters can be determined. The criteria are based on the desirability to maintain· rated power flow to Anchorage and Fairbanks during the outage of any single 1 ine or transformer element. The essential features of the criteria. are as follows~ 2-1 . . ~ . . . · : . . . t. ~ " ... . • !'. • • • -total power output of Susitna to be delivered to two stations at Anchorage and one at Fairbanks -"breaker-and-a-half11 switch~ng station arrangements -dynamic overvoltages during line ener·gizing not to exceed specified limits -system ~oltages to be within established limits during normal operation -power delivered to the loads to be maintained and system voltages to be kept within establi~hed limits for system operation under emergency conditions -transient stability during a 3-phase line fault cleared by breaker action with no reclosing -where performance limits are exceeded, the most cost effective corrective measures are to be taken. 2-2 I I I I I I I ·I I I I I I ., I •• ·I· I I I I I I -I I I I I I I I I 3 -APPROACH The following steps were adopted and pursued to achieve the preliminary subtask objectives. -develop system planning criteria (paragraph 2~3) -ass.emb1e existing system data (obtained by RWRA) -study present load distributicn to Anchorage and Fairbanks -establish bulk power delivery points -obtain development capabilities (from Task 6) ·-determine 1 inE! loadings at each development stage -examine various system configurations -compare various systems on a performance and cost basis -make prelimin~ry voltage recom~endation I I • I I I I I I I I I I I I I I I I I 4 -DESCRIPTION OF STUDIES AND PRELIMINARY RESULTS 4.1 -System Data Assembly The services of R. W. Retherford· Associates were obtained August, 1980 to gathet .. system data from the utilitieso The final data assembly was completed late October, 1980. 4.2 -System Load Di stri buti on Based on the ISER load forecasts (low~ medi urn and high load growth), the di strihutron .of the total Rai lbelt load between Anchorage and Fairbanks ar'eas remains essentially constant throughout the range of load growth p·r-edictions. Anchorage is predicted to have approximately 80 percent of the total load with Fairbanks having the r-emaining 20 percent. To allow for some variations in the forecasted load split, the transmission system will be designed to deliver 85 percent of total Susitna power to Anchorage and 25 percent to Fairbanks. · The foregoing was studied after receipt of system data and the delivery points, two at Anchorage and one at Fairbanks were estab 1 i shed in November, 1980. 4.3 -Description of Studies (a) Power Transfer -After studying various reports 1 i sted above and obtaining preliminary information on the staging of Susitna from Subtask 6.36, Generation Planning, the electric system studies were able td proceed in December, 1980o Table 4.1 shows the staging schedule for the Susitna Development. The maximum power to be transmitted to Anchorage and Fairbanks for each stage of development, based on the 85 percent and 25 percent limits is given in Table 4.2. The load power factor is assumed to be 0.95 and the power factor capability of the Susi tna generators is assumed to be 0.90. Following determination of the system power transfer requirements for each stage of Susi tna deve 1 opment, alternative system configurations were developed taking into account the following: -initial Susitna development at the Watana site -a major switching station at Devil Canyon or near Gold Creek -possible intermediate switching at Willow and Healy. Preliminary line lengths for the system configurations under study were obtained from Subtask 8.03, Transmission Line Rout~: Selection .. Having established the peak power to be delivered and the distances over which it is to be transmitted, transmission voltages and number of circuits required were determined. To maintain a consistency with standard ANSI voltages used in other parts of the U.S.A., the following voltages were considered for Susitna tran$mission. 4-1 (b) (c) -Watana to Devil Canyon or Gold Creek and on to Anchorage -Devil Canyon or Gold Creek to Fairbanks .. 500 kV or 345 kV 345 kV or 230 kV (,) Conductor Sizes -Based on the selected transmission and power transfer requ1rements at the var·ious stages of Susitna development, economic cnnductor sizes can be selected. The methodology used to obtain the economic conductor size and the results obtained are outlined in Appendix B, 11 Transmission Line-Economic Conductor Size11 • Also included in Appendix B are the capit~~lized costs of transmission line losses. The cost of these losses are taken into account in comparing the overall costs of alternative transmission schemes. When determi ni ng1 appropriate conductor size, th\ · se 1 ected conductor i s checked for radio interference (RI) and corona "equirements. If RI and corona performance are within acceptable limits~ then the selected conductor based on economic analysis may be used4 On the other hand, where necessary to satisfy RI and corona performance requirements, a larger conductor size may be selected. Total line lassos for the proposed conductor size for each of the different line voltages be·ing considered are given in Table 4.3. These losses are for the alternat·!ves where a major switching station is located at Devi 1 Canyon. The losses given are the total losses for transmis;;ion from Devil Canyon to Anchorage and from De vi 1 Ca;tyon to Fairbanks. The line ·from Devi 1 Canyon to Anchorage is 155 miles long.. The losses were calculated for the maximum expected power transfer to Anchorage and to Fairbanks for each of the stages of Susitna development as given in Table 4.,2~ Line Energizing and Outage Coaditions -Following selection of the conductor sizes using economic, RI and corona criteria, computer simulations of line energizing were carried out. These simulations w ·."e performed to determine shunt reactor requi.rements necessary to ensure that dynamic overvoltages during line energizing. remained below the values established in the system planning criteria .. (See attached Appendix A). Once the line reactor requirements were established, computer load flow simulations of single contingency outage conditions were commenced. The purpose of these simulations is-to determine the following: -need for intermediate switching stations -transformer tap settings -need for, and magnitude of series compensation -var generation requirements at the load centers These simulations are being carried out for the various transmission system configurations and stages of development of Susitna being considered and are current 1 y in progress. 4-2 I I I I I I I I •• I. I I I I I I I I I I I I I I I I I I I I I ~ I I I I I I I (d) Pre 1 iminary Cap ita 1 Cost Estimates -These estimates wi 11 be engineering type estimates with an appropriate cent ingency to cover any unforeseen construction problems. In working up the transmission 1 ine costs, Acres referred to RWRA experience in Alaska_. The line costs are based on an X-type tower. The cost figures developed are consistent with CAI January, 1981 transmission 1 ine costs. Appendix B shows the methodology of obtaining the line costs as a function of voltage and conductor size. The capitalized cost of 1 ine losses are _also treated in this appendix. Substation equipment costs were developed, based on unit costs in the U.S. Department of Energy, Federal Energy Regulatory Commision publication, 11Hydroelectric Power Evaluation 11 , August 1979 edition. The costs obtained from this publication were escalated to reflect 1981 levels and the higher cost of 1 abor in Alaska. 4.4 -Preliminary Results of Studies ·The studies performed to date (February 15, 1981) have given preliminary results as.follows: (a) (b) (c) (d) (e) (f) 345 kV is a viable voltage for transmission from Susitna to Anchorage and to Fairbanks and appears to be the economic choice. Two circuits are expected to be adequate to each 1 oad center~ however., the circuits to Anchorage will require series compensation to handle the heavier loading to the south. System configuration is shown in Figure 4.1. Conductor sites (preliminary) are 2 x 1272 MCM to Anchorage and 2 x 795 MCM to Fairbanks. Costs and performance calculations to date are inconclusive as to the preferred location of the Susitna terminal station -either Gold Creek or Devil Canyon. Final decision may be based on other factors. Intermediate switching at Wi 11 ow is a cost-effective ~tJay of improving the contingency performance of transmission· to Anchorage. It also has the advantage of facilitating the supply of future load at this point (e.g. future capital) .. Studies are based on two delivery points in the Anchorage area to handle the u 1 t imate 1 oad i n!:~O'f 1020 to 1190 MW. [This is based on assumed requirements for subtransmission rights of way in the load area and has no impact on the question of primary transmission voltage and configuration]. (g) Transmission to Fairbanks does not need an intermediate switching station at Healy to satisfy contingency requirements. This could be added if required for load or generation at this point. 4-3 The cost estimates obtained from these studies were used to calculate transmission system costs for the "1981 Upper Limit Capital Cost Estimate and Associated Economic Analysesu dated March. 1981. 4-4 ~. I 'I I I I I .I 'I I I I I I I •• I I I I 1: I I I I I I I I 'I I I I I I I I I . . ~ . . . . . . . . . .. ,. . . . . . . . ·:: . . .. . . TABLE 4.1 -STAGING OF THE SUSITNA DEVELOPMENT Year - Watans Increments Susitna C~acity -MW Devil anyon Total Increments Total Susltna Total 199J 1996 2000 400 400 2000 (optiona.) - 400 800 400 200 400 600 400 800 1,200 1,400 TABLE 4.2 -MAXIMUM POWER TO 8~ TRANSMITTED TO ANCHORAGE AND FAIRBANKS FOR EACH STAG£ OF SUSITNA DEVELOPMENT Total Susitna Maximum Power Transmission C!Eaeit:t (MW) To AnChorage (MW) To fairbankS (MW) 400 340 100 800 680 200 1,200 1,020 300 1,400 1 '190 350 Note: For system planning purposes a mriximllll of 85 percent .of. Susitna generation is assumed to be transmitted to Anchorage and a maximum of 25 percent to Fairbanks. 4-5 0 TABLE 4.3: LINE LOSSES UNDER MAXIMUM POWER TRANSMISSION Susitna Capacity (MW) 400 800 1,200 Susitna Capacity (HW) 400 800 1,200 1,400 Devil Canyon to Anchorage (155 miles) Pnwer · 5otrkV 345 kV . 3 circuits Transaitted (MW) 2 Circuits (MW) 2 Circuits (MW) (MW) 340 680 1,020 1,190 1.5 .6.2 13.8 18.8 3 .. 2 12.8 28.8 39.2 2.9 11.2 .25.5 35.3 Power . · 345 kv · DO kV Tranmwitted (MW) 2 Circuits (MW) Z Circuits (MW) 100 200 300 350 4-6 0.5 2.0 4.6 6.3 I I ·~·· ·- ' I •• I I I I I I ·~ I I I I I -· -. ~; ------ . -- ANCUOUAG& It ifAIRBANKS WILLOW ... I ' ~ I E 65 ~I SO MI 189 MI 138 K 345 KV 15 MI 138 K.V ·-:( 65 MI 90 MI 189 i-ii 345 Kv· 345 KV ANCHORAGE I LEGEND 345 KV DEVIL CANYON -LOAD e--GE~lERATION &-VAR GENERAl'ION ~E-.SERIES C~iPENSATlON 27 Mt ..-rvY"\._ SUUNT UEACTOR 27 MI ~ GENERATOR TRANSFORMER(S) ~ STEPDOWN TRANSFOnMER(S) 345 KV WATANA WITH TERTIARY WINDING 345 KV SYSTEM FIGURE 4.1 filii I I I I I I I I I I I I I I t:~ ... I I I ·s-GENERAL COMMENTS Transmission planning studies are still in progress examining the impact of conti ng~n<;Y~.o~;t,~aes and transi e1 .~t · stability on system configuration. Other detai Ts ___ wfi1ch are not yet fi na h zed and which may influence the transmission configuration are the sizes and staging of generation at Watana and Devi 1 Canyon sites. Current work on transient stabi 1ity has shown that survival of a three-phase fault on the EHV system will be difficult (and costly) to achieve~ The arbitrary choice.of a three-phase design fault in the planning criteria may have been undu1y severe,. since multiphase faults are rare in EHV systems • . Further study is needed but we may propose changing to EHV design fault in -the planning criteria from "three-phaseu to "sing1e~line-to-ground 11 • Structural and mechanical detai 1 s of the trqnsmi ssi on system have not been studied as yet. These will be addressed after completion of the electrical system· studies. I I .I a·. I I I -I I •• (I 1\ I t~ I I I I I APPENDIX A P"ROPOSED PLANNING CRITERIA I I I I . I I I I ~ I I I I I I I I I I SUSI~'NA TRANSMISSION PLANNING PROPOSED PLAi~NING CRITERIA July 22, 1980 P5700.08 I'n general, we propose to plan transmission facilities so ~"lat single contingency outages will not result in restrictions in power transfer although voltages may be temporarily out- side of normal limits. The proposed guidelines concerning stability, system performance limits and thermal overloads are detailed below. {a) Stability The system \\Till be checked at each stage of development for transient stability. In the case of multiphase faults, delayed reclosing is assumed, \vhereas high speed rcclosing would be attempted following single-. ph;,:;~" faults that ~vere cleared by single pole switching. -. The de:>i9n fault for transienc stability check would !;C' ~ 1-phnsc fault cleared in ~ cycles by the local h:•'}~: .... r nnd 8 cycles bythe r~~mote breaker, vlith no .,.. -..... 1 r:·~ l. n·""" ... t "\.~ .... . " : • (Note: l\t later· sta .. ;es of de~;ign it may be useful to check dynamic stability for unsuccessful rcclosurc of a SLG fault cleared eventually by 3-phasc trip and lock-out following initial single-pole trip. For the present, a 3-phase design fault is considered to be equivalent in terms of severity.) (b) Station Configuration~ The determination of system transmission requitemerits \vill be based (initially at least} on assumed. success- ful breaker operations. When the oaf feet of a stuck breaker is examined, the clearing of back-up breakers will be based on 11 breaker-and-a-half11 ::.;witching arrangements. {c) System Energizing Line energizing initially and as part of routine switching operations will generate some dynamic over- voltages. System design should be arranged to keep these.overvoltages within the following limits -line open-end voltages at the c-remate end should not exceed 1.15 pu on line energizing -following line energizing, switching of transformers and VAR control devices at the receiving end should bring the voltage down to 1.10 pu or lqwer . -the step-change in voltage at the energizing end of the line should not exceed 5 percent. (d) Load Flow System load flows will be checked at each .stage of development to ensure that the system configuration and component ratings ,are adequate for normal and emergency operating conditions. The load levels to be checked will include peak load, minimum load (assumed 50 percent of peak) and also any intermediate load level tht3.t is judged to be critical due to off-peak sh:.! t do\.;n of loo.d-ccnter generation. 2 Nor:nal system flows must be v: i t:.hin all normal thermal li:-:-its for transformers and l~acs, nnd should give bus '.tolt.vr(!S on the _EHV system tvit..hin +5 percent, -10 percent, ~nd t1t subtran!.;mi~sion buses within +5 percent, -5 percent~ " ~ Em~rgcncy system flo·.-.rs with the loss of one system ele:ncnt must be within emerge:1cy thermal limits for lines and transformers (20 percent 0/L). Bus vo;t.tages on the EHV system should be v1ithin +5 percent, -10 percent, and at. subtransmission buses \..rithin +5 percent,. -10 percent. (e) Corrective Measures Where limiting performance criteria are exceeded, system design modifications will be applied that are considered to be most cost-effective. Where conditions of low voltage are encountered 1 for exampler power factor improvement would be tried. 1ihere voltage variations exceed the range of normal corrective transformer tap change, supplementary VAR generation and control would be applied" Where circuit and transformer thermal limits are about to be exceeded, additional elements·would be scheduled. I I I I I I I I I I 'I I I I I I I I -· ~ ·-------~--;-:'.-' ' . '1.-' I I I I I I I I I I, I I I I I I (f) Power Delivery Points · For study purposes, it will be assumed that when Susitna generation is ·fully developed (i .. e .. , to approximately 1,500 MW), the total output will be delivered to 'terminal stations as follows -Fairbanks -one station at Gold Hill . Anchorage t"t--.70 stations -one c.-'c Palmer -one 11 elsewhere 11 -(the two stations at Anchorage would be interconnected at EHV.) The provision of intermediate switching stations along the routc.·may prove to be economic and essential for stability and operating flexibility. Utilization of thr·::~· ~·..;i r-ching stations for the supply of local load ·..;ill b .. ! ~xamined, but security of supply to Anchorage ~nd Fairbank~ will be given priority consideration. MWS:rf 0 /"' )j /' l...t- M. W. L ..,= • ( 1 ft..' I ./ r-v··r-v Cl. ~-A- Stoc.ldart 3 I I I I I I -- I I I I I I I ~.r •• I ·~· I I I I () APPENDIX B TR..l\NSMISSION LINE ECONOMIC CONDUCTOR SIZE I ~ ... ~,~ I ~-- • I I I ~ I I a I. I I I I I I ~· I TRANSMISSION LINE - ECONOMIC CONDUCTOR SIZE 1 -INTRODUCTION February 13, 1981 In EHV tra.nsmis=-ion, line conductors and conductor bundles must be sized to minimize corona, RI and audible noise effects. An additional factor that needs to be quantified is the economic incentive to increase the conductor section still further to achieve savings in the future cost of line loss. This appendix deals with the economic aspects of conductor sizing, and since both line costs and line losses ar~ pro- portional to line length, the analysis is carried out on the basis of costs per circuit -mile. 2 -LINE CAPITAL COST Transmission costs are generally a function of the trans- mission voltage and conductor size, modified by local considerations such as me~eorological factors, access, transport costs and local labor costs. At a particular voltage, the variation in line cost as a function of conductor area is normally of the form On the basis of line·cost estimates for Alaska, values of "Kl", nK2u and "a" have been determined. These are approximate, but they describe the relationship between line cost and conductor size sufficiently well to be used 2 as a guide in dete·rrnining the economic size of line conductor .. The equations are shown belew 230 kV = $/mi...te ~ 125,000+2 ( 1\l C M ) 1 • 4 5 345 1<. v = $/mi_i_e ~ 175,000+2 {MCM)1.45 500 k.V = $im-i...te.. ~ 300,000+2 ( M C 1\l ) 7 • 4 5 . 3 -CAPITALIZED COST OF LOSS Line loss varies directly as the square of the line loading and inversely as the conductor cross. sectional area. Since the line loading varies in a daily pattern and also through- out the life of the facility, these variations must be taksn into account. Daily variations in load are described by the Load Factor (LF) which in the railbelt area is expected to be about 62 .. 5 percent.. The average annual energy capability at Susitna is also of the same order, and the load factor of line losses (LLF) is estimated to be LLF = (LFJ 2 +LF 2 = {0.625) 2 +0.625 2 = 0.508 LLF ~ 0.50 .. I ,.,,,. I .,._ I I I I I I I I I I I I ... __,:_ I J I v ' I I I I I I - ' I I ~_., ' I I. I ...... I I ,,• I .... I I ,,. - I I 3 Transmission line loading over the life of the facility can orily be estin:tated at this time. According to generation planning studies, each time a block of 400 MW of generation is cotn.T'!lissioned (in years 1993, 1997 and 2000), this capapility is fully absorbed by the system. Generation additions after year 2000 cannot be forecast with any. certainty. The contribution to loss energy from any additional peaking capacity would be negligible, hence, the following load pattern kS assumed. Period 1993 -1996. 1996 -2000 2000 -20 43 Susitna Caoacity (HW) 400 800 l 200 ~ine Loadings - To Anchorage 320 640 960 {MW} To Fairbanks 80 160 240 Expressing line loading and line resistance in per unit on · Surge Impedance Loading (SIL} and surge impedance {Ze) base leads to the following expressions Li.n:e -'l.e.~.s .i...~!> .tan c. e. I n £..{. n e. i o a. d.i. n g 100 ohm.~~ peJt m.i.ic. -· XlTIT 100 1 pe-t LUt.i...t pe.t = .\fC,'.l X. Ze = S pe4 unlt on SIL ba~c -S 2 X TOO X J pe~ anlt MC~\I TC: k. v 2 = z-e '~'-'Htl 1 m L l.c 2 100 1 kv 2 = S x ITC"i\f x. z c. x. Tr ( Af W I m ,{. e. e. } S 2 100 lzV 2 = X ~ X - 1 .2 X 8. 76 X LLF c. { GW • It I m f.. t \.?..} 4 And i6 the eo6~ o6 loJ~ ene.~gy = e ~/kW·h = c. $ M.<.t.e..i. o n I Gltf • It 2 1 0 0 . lc V 2 = S x x ---rr x. 8~76 x. LLF x. e ~ -9 {. Ze { $ AU. t tl o n I m .[ e. e. ) Typical values of LLF and C for Susitna are LLF = 0.50 (a~ deve~oped ea~lle~) . . c. = ~ 0·. 0 3 5/ltW • h (an ave..tag e. 6ig u.~e. de.ft...L v e.d in the 0 GP-5 pl.annlng -~.tu.dle .. ~ ba,s e.d on. Z(Uto J..n6ta.tLon and 3 pelteen-t ne..t eo.~t o& money) A () t , f) _ 75.33 s 2 ~tv 2 ($ .11 -o"· 1 ·p} naua..(.. c. a .6 ~ o 0 .{..o .. ) ... s -. 1 •• .{ {.. E.t on m.<... t.e . MCAI Z c. ... In tables 1 and 2 the capitalized cost of loss per mile is derived for transmission to Anchorage and Fairbanks 1 respectively,as a function of conductor size and for the line voltages that are being considered. In Table 3 the 1?-ne capital cost and capitalized cost of loss are shown for ea!~h voltage and transmission route. Also shown are the optimum conductor sizes based on loss evaluation. The relationship between total cost and conductor size is sho\.vn graphically in Figure 1 for trans- mission to Fairbanks and Anchora<:e. Line loadings at 50 0 I~ V to Anchorage and at 345 kV to Fairbanks are low and lead to conductor sizes below the acceptable limit from an RI and Corona point of vie~T. Pr9posed conductor sizes for the various line sections, taking into account Corona arid RI effects, are shown at the bottom of Table 3. I I ·-· I I I ' I I "-~· ' I I. :J "" I I ,;:,,.., I '•' I t ""~•"' ' I . , ... - TABLE 1 TRANSMISSION LINE TO ANCHORAGE DEVELOPMENT OF CAPITALIZED COST OF LOSS Loading Perl Annual3 Fac or4 Circuit 1 1 1 Capitalized Total on SIL Cost of Duration of Offset from X Cost of· Period Load Base2 Loss Load Period P.W. Datum T (l+i)m Loss {MW) Un·l) (S-pul. ($M/MCM) (n-Y:ears) (m-years) ($M)acM) "' 1993 -1996 320 160 0.386 3 .. 305 3 0 2. 8286 9;.3-•9 1996 -2000 640 320 ~ 0.771 13.186 4 3 3.4017 44 .. 855 • ltl .2000 -2043 960 480 <ql rt'l 1.157 29.695 43 7 19.4995 579;.,037 Total at:. 345 k.V = $M 633~241/HCM 1993 -1996 320 160 0.178 1~5737 3 0 2.8286 4 .... 451 1996 -2000 640 320 ~ 0.356 6.2949 4 3 3.4017 21 .. 41.3 0 2000 0 0.533 14.1105 43 7 19,4995 275 .. 1.47 -2043 960 480 ltl Total at 500 kV = $M 30l.Oll/MCM " 1 T . . 't d 2 wo c1rcu1 s are assume • SIL base values are: 415 MW (345 kV) and 900 MW (500 kV). 3Annua1 cost of loss = 15.33 s2 kv2Jzc2, based on losses valued at $0.035/kW•h and a 50 percent loss load factor. 4present worth discounting is at annual rate of 3 percent. TABLE 2 TRANSMISSION LINE TO FAIRBANKS DEVELOPMENT OF CAPITALIZED COST OF LOSS .. Loading Perl Factor4 circuit Annuall 1[1 _ 1 xL cap:it:alized Total on SIL cost of Duration of Offset from cost o:f Period Load • Base2 Loss Load Period p .• w. Datum I (l+i)n (l+i)m LOSS (MW) (Mrl) (S-pul T$M/MCM) In-years) (m-years) (.$M,IRCM.) 1.993 -1996 80 40 0 .. 292 0.4665 3 0 2.8286 1 .. 31.95 1996-2000 160 80 0.584 ~I 1.,8660 4 3 3.4017 Ei .. l416 2000 -2043 240 120 o. 87.6 ~ 4.1984 A~ 1 19.4995 Sl .. S-10 --- ... Total at 230 kV • $M 0$ ... S331/MCM 1993 -1996 80 40 0 .• 10 ~I 0.2061 3 0 2.8266 0: .. 5~30 1996 -2000 160 80 0.20 o. 8243 4 3 3.4017 -t .. a:2uo 2000 -2043 240 120 0.30 1. 85·41 43 1 19.4995 3.6· .. l.t'60 Total at 34S ltV ., $M 4Ch.~lil 7/MCM 1 TWo circuits a£e assumed. 2siL base values are: 137 MW {230 kV) and 400 MW (345 kV). lAnnual cost of loss = 15.33 s2 kVlJzc2, based on losses valued at $0.035/kW•b and a 50 percent loss load factor. 4present worth discounting is at annual rate of 3 percent. (J _____ ! ___ _ ,. TABLE 3 SU!-1MARY OF ECONOMIC FACTORS AND PROPOSEO CONDUCTOR SIZES Voltage Transmission to Anchorage soo kv 345 kV Capital cost of line ($M/mile) Capitali;edl cost of loss ($M/~'ile) Optinnun conductor s i~ (i<!Cl.f) Proposed conductors 0.30 + ~ (MCM)1 •45 10 301.011 MCM 1 ( '301 .• 9llxl06 \ 2 .. 45 2.9 . 1 = 1:,870 MCM2 3x795 MCM 0.175 + b-(MCM)l.-4S 10 633.241 f.!CM 1 ( 633.24lxlo6 )2 •45 2.9 = 2,533 MCM 2xl,272 MCM Transmission to Fairbanks 34S kV 230 kv 0.175 + 2 (MCM)1 •45 to6 40.975 MCM 89 .. 534 MC.t-t l. 1 {40. 97Sxlo6 Y2 • 45 \2.9 1 (89.534x!o6)' .'1:~45 · ~ ·g : ..... . = 829 MCM 2 2x795 MCM = 1,140 MCM lxl,272 MCM 1 capitalized cost of loss expressions are derived in tables 1 and 2. 2The economic conductor areas for 500 kV to Anchorage and 345 kV to Fairbanks ,are smaller than the minimum needed fol:' RI and Corona performance. Hence, RI considerations vill dictate conductor si~~e .. 0.4 . "'-. "-TOTAL COST INCLUDING ---,.,., CAPITALIZED LOSS ---~ ........ '54~'1.....--230 KV --._..-- 0.3 -(/) z 0 -_.J ..... .__ ~ .,. ... -----------·~-........... ~ ...J -:E - UJ 0.2 ....J -:a ___ ..... ~---- --.,.,. ......... -----~ --.,.,-'3451<.~--...... -----~ a:: L&J 0. L LINE CAPITAL COST z~ov.:v~ ---- ... fJ) 0 (.) - 0. I 0 500 1000 CONDUCTO·R AREA { MCM) {TOTAL) TRANSMISSION TO FAIRBANKS 1500 FIGURE lA I I t 1 .. . ' t il ;;.,.r,. I· I I I .. ,..,. I I t ' t ·t 1 '~. ' I I I I t ' I I I ' I I I I I _l_·~·- 1 I I I -(J) z 0 :::i 0~7~----------~----------~----------~--------~ TOTAL COST INCUJOtG CAPITALIZED LOSS ::! 0.5 t-------+-------+------+---------1 :s -UJ ...J -~ cr 1.&.1 a.. ...... 0.4 .(I) 0 (.) ~.,._LINE CAPITOL COST· 345 KV , --~ 0.2 .... _____ ......_ _____________________ ..__ ,. -·-· -· -~---·-- 1500-2000 2500 3000 3500 ' TOTAl CONDUCTOR AREA (MCM) TRANSMISSION TO ANCHORAGE FlGURElB ~~~~ I I I . I t a I I t I I I I , I I I I I I ATTACtr!YlENT I I I I I I I I I I I I I I I I I ' I Narch 24, 1981 P5700.11 T.783 r~r. Eric P. Yould Executive Director Alaska Po~tJer Authority 333 West 4th Avenue ·Suite 31 Anchorage$ Alaska 99501 Attention: Mr. David Wozniak Dear Dave: Susitna Hydroelectric Project Transmission Line Char3cteristics ;__; ___ -.w .... .. --· t~e are attaching one copy of interoffice memo from t1. H. S~oddart/ I. R. Shepanik to E. N. ~hudeed. This memo or1tlines t~a: tr.Jnst:lission line characteristics required 1:hich \vil1 carry the pro_:,-.cted 1400 ITI\'1 Susitna capacity to Anchor<.1ge ond Fai rban~:s ~ This information was previously given to A.-Poppens of C;1! ,-.i f.·~;r·uary 20, 1981 .. As noted in the memo, the typE:·~ of com:fuc tor used in thf: •, ~ .;-·: but the conductor capacity is tonsidered as a mini~um. I: t·~ proceeds with 345 kv construction, any conductor choirn ,: :! coordinated with the Susitna ~ quirements. ENS/ljr -Attachment cc: A. D. Poppens ACRES AMERICAN INCORPORATED Con:.c!tt~g Eng r:-oers The Lib~rty aar.~ e• .... :cmg, :.~1\>n nt c"-wt Buffalo ::~::·.•.· Yor:-: 1.!.202 -[John ~. lawl"ence r;r· Project Manager \1 rf! typi ca 1 .. .. ,_ . 1r.~.-er~..1e ... ~ ~losely TO: FROM: SUBJECT.: OFFICI: MEMORANDUf\.'1 E. N. Shadeed Date: March s, 1981 File: P5700.07.08 M. w. Stoddart I. R. Shepanik cc: SUSITNA TRANSMISSION LINES We -are currently carrying out electric system studies to determine transmis~ion requirements for the Susitna . development. The \vork performed to date indicates that the recommended characteristics for the lines from Susitna to !1.nchorage· and Susitna to Fairbanks will be as follO\-lS • Voltage Number -c;rcuits 0!: Number of conductors pt'r bundle . Conductor size Conductor type Susitna to Anchor a<i~- 345 kV 2 z· 1272 J.~c ... ~ ,, ,_ Pl1~.:l r-:"1•1 t ... • .. -...>c.. l. Susitna to Fairbanks 345 kV 2 ... ... 7'15 r·1CH '" '... d • t \ tar The conductor size for the line fro::t Sus i tna t.~J :.;1chorage \Jlas chosen for econor:1i t" reasons. For th-:; Sur: i t: .. 1 to Fairbanks line the conr!uctor size wns r;c lect.c ! ~ o !': c1 tisfy radio in terferencc and corona require~··:; t r;, ~ .. ,· .. ·h in this case override econon~ic considerations. The tower-line dimensions on which calculations of radio {! • interference and corona performance were based are gl.ven belo'tv. Similar dimensions were used for both the lines from Susitna to Anchorage and those from Susitna. to Fairbanks. tower height -95 ft -conductor height above grou:q.d -85 ft at tower -30 ft midspan horizontal phase spacing -27 ft -bundle spacing -18 in. Our studies related to conductor selection focussed on conductor cross sectional area and conductor diameter. These indicated approximately 2x1272 HCM for circuits to Anchorage and 2x795 HCM for the circuits to ~airbanks. \men the total line design is being optimized there will I I I I I I ., I I I •• I I I I I I -· I I I I; I i I . •• I 1: I E. N. Shadeed March 5, 1981 be some trade-offs ,bettveen tower cost and conductor cost, and these will lead to the selection of conductor tvoes -.. with stranding and strength characteristics that are part of an optimized design. The conductor types used in our calculations, Pheasant and Mallard, are considered typical but not necessarily the final choice. Any s;gnificant departures from the above that are being considered for a 345-kV intertie should be chec}~ed for compatability with future Susitna requirements.