HomeMy WebLinkAboutAPA1399I
I
II I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Attachment A.-4
Amendment No. 3
ALASKA POWER AUTHORITY
SUSITNA HYDROELECTRIC PROJECT
PLAN OF STUDY -REVISION 3
MAY 19, l9t32
by
AGKES AMEtUCAN INCORPOKJ.\TED
Liberty Bank Building, Main at Court
Buffalo~ New York 14202
I
I
I
I
I
I
I
I
I
I
I
I
I
••
I
I
I
I
I
TABLE OF CONTENTS
R~l -INTRODUCTION • ····~········.;t·············· .. ··················,·······
R .2 -REVIS IONS TO DETAILED ACTIVITY DESCR l?TIONS BY TASK ... H ••••••••
R.,2.1. -Task 2 -Surveys and Site Facilities .................. o
R.2. 2. -Task 3 -Hydrology ................................... C>. ,(1
R. 2. 3 .. -Task 5 -Geotechnical Exploration .................•. "'
R'"2o4. -Task 6 -Design Development ... ~ .•.. ·~ ............ ·····~
R.·2. 5. -Task 7 -Environmental Studies •••••••••••••••••••••• ~.
R.2.6. -Task 9 -Construction Cost Estimates & Schedules ....•.
R.2 .. 7. -Task 12-Public Participation ··········••o•••Oe·······
R.2.8. -Task 13-Administration ...•••..................•......
Page
1
2
3
5
19
24
25
52
54
55
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I-
I
I
R -1 -IN ·:f(uuUCTION
Since the issue of the February 1980 POS, two amendments to the POS have been
completed. These (ID'Iendments have been in response to suggestions from state and
federal agencies, interested citizens, and public and private organizations. In
response to continuing dialogue among study, participants {i.e., APA, state and
federal agencies, and Acres) it has been determined that the projec.t would bene--
fit by extending the date for FERC 1 icense apolication from June -30, 19b2 to
September 30, l98t.~, and continuing with certain of the ongoing work. This will
substantially improve the quality of the license application and, although post-
poned by 90 days~ should not delay granting of the license by Ft:RC .. The license
application would be improved as follows:
-Additional time will be available for APA and the agencies to review and com-
ment on the project Feasibility Report and supporting documents. Acres will
then have sufficient time to address the comments in the FERC license applica-
tion. ·
-The data obtained by ADF&G during the 1981/1982 winter season will be used in
the development of mitigation proposals and will be included in Exhibit E -
Environmental Report.
-Time will be available for obtaining additional field data and developing more
detailed fish and wildlife impact mitigation proposals than presently ;:xists ..
-Adaitional information will be developed and included in the license applica-
tion regarding various-project financing arrang~~ents.
Additional work items which are planned through the end of September 1Y82 are:
-Additional planning o.nd permitting activities and associated fie1d wort< to
develop a comprehensive geotechnical program to meet the 1ong-term needs of
the project.
-Field reconnaissance and further study of the access route location and elimi-
nation of the 11 pioneer road 11 concept.
-Continued operation of the field camps· and logistics support.
-Continued monitoring of hydrologic, climatic and geotechnical instrumenta-
+-• .. 1on.
-Continued Project Management and Administration for the extended time pe'riod.
c
-Preparing/updating cost estimates and schedules in connect ion 'ifith the above.
-Continued environmental studies and analyses concerning socioeconomics~ land
use~ recreation, fish ecology and wildlife.
.
-Investigation of various design changes necessary to meet changing environ-
mental criteria.
1
-•
I
I
I
I
I
I
I
I
I
I
I
I
I~
I
I
I
I
I
(l
R .2 -REVISIONS TO DETAILED. ACTIVITY DESCRIPTIONS liV TASK
Revisions to detailed activity descriptions by Task are presented in the
following pages.
2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
~ubtask 2.02. -Provisio.n of field Camp~ and Associated Logist,ics Suppor,l
(a) Objective
Provide ongoing field camp ana logistics support for the continuing field
studies.
(b) Apprqach .
During the time period from April 1 to June 30, 1982~ the camp operation
will be maintained at a minimum level and fue1 consumption will be mini-
,,. mized through the use of the smaller 60kw generator. During this time
period the actual calculated fuel needs for camp and helicopter operations
will be supplied to the camp by helicopter.
During the period July 1 to September 30, 1982, camp staff will be in-
creased to h~ndle the increased field staff to support continuing environ-
mental and geotechnical activities.. He1 icopter contracts for up to four
aircraft will be awarded~ and fixed wing service from Anchorage and
Fairbanks will be ·initiated.
Fuel resupply will be made early in July to supply the needs for the summer
operation.
' ' In addition to the above needs, a contract will be negotiated with High
Lake Lodge to prov"lde accommodations for personnel involved in
environmental and access studies ..
(c) Schedule
See above ..
3
I
I
I
I
I
I
••
I
I
I
I'
·~
I
-I
/
Subtask 2.10 -Access Roads
(a) Q.bjective
(b)
To evaluate alternatives to the "pioneer road" concept.
Approach
During the time period f~om April 1 to June 30~ 1982, t~e preliminary engi-
neering studies for the recommended access road route will be completed.
Due to. the concern over the pioneer road concept, recommended alternatives
to this concept will be reviewed and a corridor studied which could help
alleviate schedule constraints. The level of study and pre1iminary design
on this alternative route will be brought up to the same level as the
studies on the recommended route. Appropriate amendments to the access
road report wi 11 be prepared.
(c) Schedule
April 1, 1982 to June 30 7 1982.
4
I
I.
I
I
I
I
I
I
I·
I
I
I
I
I
I
I
I
I
••
Subtask 3.03 ... Field Data CoJ lection and Processing .
(a) Objectiv<!
To continue field data acquisition and perform studies to address newly
identified needs to support the instream flow program.
{bl Approach
Studies will be undertaken in eight main areas.
(i) Continuing Field Data Acquisition and New Field Work
(ii)
( i i;)
(iv)
Field data acquisition will continue at the same level of effort as
Phase I in the Upper Susitna Basin, wit;l additional field wnrk in
the river below Dsvil Canyon to support new studies. All six cli-
mate stations wi 11 cant inue to operate, as will the Watana stream-
gaging site. Water quality sampling will continue to be conducted
at Vee Canyon and Gold Creek, with possible expansion to other
sites. Snow surveys will be continued through the 1982 winter and
spring. New field work is concentrated on obtaining data in sel-
ected side-channels above Talkeetna and in the main river below
Talkeetna. Additional staff gages, bed material sampling, cross-
sections in sloughs and channel sections will be obtained to support
additional studies for fisheries and navigation .. Selection of data
acquisition sites will be made following discussions with Acres,.
ADF&G, and Envir~nmental subcontractor.
Water Source Studies of Sloughs and Side~Channels
Studies will be conducted at representative sloughs and side-
channels to determine the relative contributions to flow of ground
water and of intergravel flow from the mainstem Sus1tna, especially
during the winter period. Determination of permeability of soils in
the islands and berms wi 11 be made and used in an analysis of
contributions during post-pr.oject w1nter flows a~_d stages.
Incremental Flow Study -Fisheries Enhancement
Hydraulic analysis of side channels and sloughs, us·Jng existing
mode 1 s, will determine the effects of varying flow rates on the
hydraulic characteristics at salmon spawning h(}!1?tat reaches. It is
anticipated that this will be an interdisciplinary effort with fish-
eries. biologists. The budget estimate is for conducting the
hyd.raulic studies.
Ice and Hydraulic Studies, Lower Susitna River ... ®
The Susitna River below its confluence with the Chulitna wi11 have a
reduced capacity to t~··ansport sediment due to the reduced summer
5
I
I
I
I
I
I
I
I
I
I
••
I
·~
:•
;I
I
I
I
I
I
f1ows from the Susitnct River.. Consequently, additional study is re-
quired to further refine the impact on the channel configuration and
to refine aggradat iort estimates.. Bedload data wi 11 be gathered by
the U.S. Geological Survey at the Chulitna River, Talkeetna River,
Susitna River above the confluence, and Susi'tna River at Sunshine.
Bed material.particle-size distribution data, crossesections, and
stage data will be collected and used to analyze morphological
changes in reach between the Chulitna confluence and Montana Creek.
Ice observations and water temperature data will also be collected
in this reach. Both studies will attempt to identify how far
downstream the effects will be noticed.
Note: U .. S. Geological Survey and Alaska Power Authority have discussed a
joint funding agreement for bedload data collection for the 1982
season. The agreement is for $200,000 ($100,000 from APA, $100,000
from USGS). (Refer to the letter from Phil Emery, USGS, to APA,
dated 22 September 198).
(v) Lower Susitna Crass-Sections
Reduced summer flows may have impacts on navigation on the ri.ver be-
low Talkeetna. Cross-sections will be surveyed at critical points
between Talkeetna and Cook Inlet, and crest and staff gages in-
stalled to establish a stage-discharge relationship.
(vi) Hydraulic Studies -Talkeetna to Devil Canyon
Additional studies of the water surface elevations between Devil
Canyon and T.all<eetna may be required in support of fisheries
studies. Further refinement of the accuracy of the model is pos-
sible with additional cross-sections and crest stage data at criti-
cal sites.
(vii) Cross-Sections, Middle Susitna
{viii)
.,
Additional cross-sections may be required to support the hydraulic
studies between Talkeetna and Devil Canyon. The budget is fer up to
20 additional cross-sections.
Glacier Studies
Phase 1 studies indicate that possioly 10 to 15 percent of the flow
recorded at Gold Creek may have been provided by the shrinking of
Susitna Basin glaciers. Consequently~ studies to define the volume,
the mass oalance, and the flow dynamics assume increasing import-
ance.
(c) Schedule
(i) 1 April to 30 June
{l) Mass balance data are to be collected by the Geophysical
Institute in late April or early May, the period of maximum
6
,,
I
I
I
I
I
I
I
I
I
I
I
I
I
I
~.
I
I
I
I
snowpack. The budget is to obtain data, with only pre1 iminary
analysis. A continuing data acquisition program following the
1981 season 1s important in gathering annual mass balance
data.
(2) Glacier velocity data acquisition is to be expanded to the
MacLaren and East Fork Gi aciers, with control points to be
located on each. Data will continue to be collected at West
Fork and ·susitna Glaciers ..
(ii) 1 JulY. to 30 September:
(1) A second mass balance measurement is to be conducted in August
in order to obtain the net balance.. The scope of work is
similar to that during 1 April to 30 June.
(2} PhotograrMletric Mapping West Fork and East Fork Glaciers. The
relative elevation change in the above glaciers (and the total
ice Joss) between 1950 and 1982 can be determined through
photogrammetric techniques, as determined in a feasibility
study conducted on East Fork Glacier in 1981.. Accuracy is
limited by that of the control. Using available data, accuracy
can be pinned down no closer than .:!:_60 feet.
Surveyed horizontal and vertical control, together with panel-
ling ar1d new photography will enable accuracies to within +10
feet. Studies should inc1ude both West Fork and East Fork-
Glaciers in order to bracket the major glaciers.
7
I,
I
I.
I
I
I
I
I
I
I
•••
I
I
I
I
I
I-
I
••
Subtask 3.07 -S~diment Yield and ~iver Morphologl
(a) Objective
To further evaluate glacial flour setting behavior.
(b) Agpro ach
The Reservoir Sedimentation Report completed January 1982 under Subtask
3~07 included -results from a· 1 iterature search to gather information on the
trap efficiency of natural glacial lakes and associated sedime:!tation pro-
cesses. Results of this search show that published literature offers
1 itt1e insight into glacial f1rur-setting behavior.
(i) Phase I Studies
Under Phase I of the current reservoir sedimentation study, investi-
gations have begun to retrieve any unpublished data or reports from
those references included in the Reservoir Sedimentation Report and
to search out any additional information from sources worldwide.
Table I 1 tsts the individuals interviewed to date concerning the
problem of reservoir sedimentation processes and water quality.
Each described his relevant work experiences, recommenaed additional
publications, and/or suggested other individuals to be contacted ..
Several, as indicated, have agreed to forward unpub 1 ished informa-
tion for use in the study.
Table 2 lists those individuals worldwide who have been contacted by
letter requesting any information in published or unpublished form~
concerning bl.t not limited to: temperature stratification, turbid-
ity levels, particle-size distribution, sediment concentration, or
controls on productivity in lake or reservoir systems. Information
from these sources will be reviewed, and if judged applicable to
Susitna, additional analyses of the data will be carried out.
(ii) Phase 2 Studies: watana Reservoir Clari.ty Analysis
There is available a considerable amount of data and studies on the
proposed Watana Reservoir that should be further analyzed with re-
spect: to the water clarity problem .. The work outlined below in
Table 3 and Figure I will utilize this information and analyze the
physical processes associated with settlement of fine particles
(less than 20 microns). Emphasis is placed on interpreting and
quantitatively analyzing the driving mechanisms that retain the fine
sediment in suspenslon. These consist primarily of wind-driven cur-
rents, thermal currents., and reservoir operation. The end result
would be an annual turbidity vs. time graph.
8
I
I
I
I
I
I
I
I
lc
I
I
I
I
I
I
I
I
I ...
I
(iii)
The analyses will be carried out for each month and summarized on a
figure similar to that which is attached. TI1ts will portray key
parameters and their variability. After each month has been.
analyzed, it will be an easy task to summarize it on an annual
graph. Since this is in part a qualitative assessment., all results
will be discussed thoroughly and founded by expected maximtm and
minimum values.
Phase 3 Studies: Comparison With Other Northern
Reservoirs and Lakes
The results of analyses conducted in Phase 2 need to be compared
with ather northern systems.. Due to 1 imitations of the existing
data base and analytical techniques, it would be difficult to
instill confidence in the Phase 2 results without making comparisons
with similar systems. For example, from the engineering standpoint~
the longer the detention time, ttle greater tha settlement of
particles, and hence, c1earer the water. However, Jeff Koe;nings
(AOF&G) has found that through his observations on Kenai Peninsula
Lakes, the shorter the detention time, the clearer systems become
during winter. His preliminary explanation for this is that the
short detention period allows the clear winter water input to dis-
place the cloudy water. During summer, glacial waters would again
fill the lakes with cloudy water.
If the efforts explained in Phase I produce other case histories or
studies similar to Susitna, then a thorough-as-possible comparison
will be made. Basic principles will be reviewed to insure their
applicability to Susitna. Res,Jltant values of key parameters on
Susitna will be compared with those on other projects and an assess-
ment of represent i veness made. Key parameters. wi 11 be bounded so
that an appreciation of expected maximum and minimum values for each
can be defined.
Results of the natural lake suspended sediment concentration and
turbidity survey currently being conducted by R&l-1 Consultants will
be compared with Phase 2 results. Since there is no lake system
that has physical characteri sties that can be directly related to
the Watana Reservoir, it will be important to screen the key par<l~
meters prior to making the comparison.
It is proposed that bulk samples be retrieved from some of the lakes
bei.ng studied. These samples then would be ·run through a settling-
column analysis~ as was conducted on Susitna River water last summer
If the lake water cleared in a similar manner as the Susitna water,
then it would indicr:::.e that water currents ~re present in deep
northern lakes of sufficient magnitude to retain the glacial flour
in suspension. This would indicate as well that a similar process
would be expected in the Susitna Reservoir. It is recommended that
samples be retrieved from the lakes before the ice leaves.
9
I
·I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
{c) Accomplishments and Deliverables
Report
Field Data Index {update)
Climate Uata ( f\'1eteoro 1 og ica l)
10/~1 -6/82
-7/82 -9/82
Ice Observations, 1981-1982
Fie 1 d Data Co 11 ect ion
Water QuaT ity Interpretative Report
Side Channel Analysis
Interim Report (Including available ground
water, water surface elevation, and cross-
section data}
Final Report
Glacial Lake Thermal & Sediment Regime Analysis
Interim Report
Final Report
Glacier Mass Balance Data Report -l9H2
10
Date
July l9tl~
July 19~2
September 1982
August 1982
Oct{)ber 1982
September 19~2
July 198t!
November 19~~
June 1982
Novemoer 1982
September 1982
--------
TV ONE.
WIND. ROSE.
•
DR lVI
INFLOW.
OUTFLO'R.·
FLow· THRU VELOCITY:
DETENTION• TIME~
ICE COVER. PRESENT
MEAN AMBIENT TEMP:
MEAN RESERVOIR TEMP~
• THERMAL TREND
INFLOW. TEMP:
FLOW PATTERN
MIXING POTENTIAL.
ISM ..
I
\
THERMAL CURRENT VELOCITY~:
WIND DRIVEN CURRENT VELOCITY.
EXAMPLE MONTH.
~ KOSINA'
WIND. ROSE.
,,
----
FIGURE l .
WATANA.
WIND ROSE . .
---
WATER CHARACTERISTICS.
SEDIMENT= CONCENTRATION: IN
SEDIMENT CONCENTRATIO·N: MID,~ . ' .
SEDIMENT CONCENTRATION OUT
REEN1'RAINMENT POTENTIAL
STRATIFICATION. POTENTIAL
RELATIVE TURBIDITY. IN
RELATIVE TURBIDITY MID
RELATIVE TURBIDITY OUT
• I
I
I
I
I
• I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
*
*
*
TABLE 1
Individuals interviewed concerning reservoir sedimentation
processes and water qua 1 ity .
• Jeff Koenings ... ADF&G -FRED Division .. Soldotna
• Jack Colonell -Woodward-Clyde Consultants ... Anchorage
.. Paul Chao -TAMS Eng. -N.Y.
• Bill Wilson· AEIDC .. Anchorage
• 'Earl Hadfield -CH2M-HILL -Corvall.is, Oregon
• Joe Scott -CH2M-HILL -Seattle
• Bill Fullerton -Simons, Li & Assoc. ~ Ft. Collins, CO
• Victor Galay-Northwest Hydraulics, L~d. -Canada
• Mike Okum -Northwest Hydraulics, Ltd. -Canada
• Arve Tvede -Norwegian Water Resources & Electricity Board
• Iver Hagen -Norwegian Water Resources & Electricity Board
• Larry Peterson -L.A. Peterson & Associates -Fairbanks
• Dr. Donald Gray -University of Michigan, Dept. of Civil Engineering
• Dr. Richard Woods -University of Michigan, Dept. of Civil Engineering
.. Or. Bob Carlson -Institute of Water Resources -Fairbanks
• Jacque 1 ine LaPerriere -A 1 ask a Cooper at iva Fisheries Research
Unit -Fairbanks
o Dr. Tom Osterkamp -Geophysical Institute -Fairbanks
• Jim Aldrich-State Pipeline Coordinator's Office-Fairbanks
• Or. Charles Slaughter -Institute of Northern Forestry -Fairbanks
• Dr. C.T. Dyrness -Institute of Northern Forestry-Fairbanks
.. Dr. Sathy Naidu -Institute of Marine Sciences -Fairbanks
* Will provide additional information for use in this study.
12
I
I
I
I
I
I
I
I
I
I
••
I
I
I
I
I
I
I
I
TABLE 2
Individuals Contacted by Letter Requesting Additional Data
Dr. Paul Chao
TAMS Engineering
New York~ New York
Or; Carl J. Bowser
University of Wisconsin
, ·Madison, Wisconsin
Dr. Robert A. Ragotzkie
University of Wisconsin
Madison, Wisconsin
Dr. Gabrie 1 T. -Csanady
Woods Hole, Massachusetts
Dr.· Abraham Lerman
Northwestern University
Evanstor~ Illinois
Dr. Daw·yl Simons
Simons, Li & Associates
Fort Call ins, Co lorado
Dr. Hans P. Eugster
The Johns Hopkins Uni~ersity
Baltimore, Maryland
Or. Lawrence A. Hardie
The Jahns Hopkins University
Baltimore, Maryland
C'r. Tyler B. Coplen
U.S. Geological Survey
Reston, Virginia
Dr. ~.J. Pearson, Jr.
U.S~ Geological Survey
Reston, Virginia
Mr. Herb Schneider
University of California-Davis
Davis, California
Mr. Wa1ten•·· Wunderlich
Engineering Laboratory
Tennessee Valley Authority
f't~rris., Tennessee
13
I
I
I
I
I
INDIA
Or. Devendra La 1
Physical Research Laboratory
Navrangpura, Ahmedabad~ India
Dr. S. Krishnaswami
Physical Research Laboratory
Navrangpura, Ahmedabad, India
NORWAY
I Mr. Gunnar Ostrem
Norwegian Water Resources & Electricity Board
I
I.
I
••
I
I
I
I
I
I
I
I
I
Oslo, Norway
SWEDEN
Mr. Ake Sundberg
Uppsala University
Uppsala. Sweden
SWITZERLAND
Dr • Werner Stumm
Swiss Federal Institute of Technology
Ouebendorf, Switzerland
Dr. Dieter M. Imboden
Swiss Federal Institute of Technology
Duebendorf, Switzerland
Dr. Kenneth J. Hsu
Geological Institute
Zurich, Switzerland
Or. Kerry Ke 1ts
Geological Institute
Zurich, Switzerland
CANADA
Dr. Peter G. Sly
Canada Centre for In 1 and Waters
Burlington, Ontario, Canada
Dr·. Mary A. Barnes
University of Britjsh Columbia
Vancouver, B.C., Canada
Dr. Willi am C. Barnes
University of British Columbia
V~ncouver, B.C., Canada
14
I
I'
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
TABLE 3
WORK OUTLINE
-1. Climate Data
• Obtain summaries of ongoing data gathering activities (R&M).
.. Extract and tabulate pertinent data.
2. Reservoir Data
• Extract from Hydrology Report •
• More detailed modelling results (Acres) ..
3. Sediment Data
• Obtain USGS and R&M data.
• Summarize monthly •
• Tabulate.
4. Ver-ify Sediment Cottcentrations vs. Turbidity Relationship
.. Investigate other projects.
. Meet with experts in field.
5. gonduct Sediment Settling Velocity Analysis
• Assume quiescent conditions •
• Simulate water temperature. viscosity, etc. for each month •
• Calculate settling velocity for the following sized particles:
-20, 10, 5, 2, 1 and 0.5 hli~rons.
-Consider various shaped particles.
6. Wind-Driven Currents and Transport
• Based on wind data, compute frequency of significant wind-driven current
for each month.
• Assume a simple one-dimensional reservoir configuration •
• Compute current velocity at incremental depths •
• Qualitatively assess potential of establishing wind-driven coastal current
magnitude and direction.
8 Summarize for each month frequency, duration, current velocities, and
expected current ~irection.
7. Thermal Currents and Stratification
o Obtain reservoir temperature modeling report and data.
• Obtain available data on,..deep northern lakes •
• Incorporate results of reservoir thermal modelling studies (Acres).
o Qualitatively assess thermal-generated currents and density stratification
pctenti al for each month •
• Determine potential for separate flow patterns; i . .a., underflow,
interflow, or overflow.
15
I
I.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
TABLE 3 -Contid
8. Reservoir Operation
• Obtain reserv~ir operation scheme and data for each month.
• Assume one-dimensional flow •
• Calculate 1 ive and dead stor~ge for e;ach month •
• Calculate flow velocity for 1 ive star' age zone •
. Calculate flow velocity for total stClrage zone.
" Qua1 ftatively assess reintrainment ptltential along 1 ive storage shore
zone.
9. Suspended Sediment Concentration and T'urbidity Analysis
• Assume that if the driving mechanisms produce currents equal to or greater
than particle size, no settling wi1'1 occur •
.. Assume that if driving mechanisms p·roduce currents ·1ess than the fall
velocity, a linear relationship exists and the fall velocity is retarded
proportionally •
• Compare various particle settling velocities with current velocities,. and
determine the proportion of sedime1nt that is expected to stay in suspen-
sion during each month at mid-reservoir anq outlet ..
• Determine turbidity levels based on sediment concentrations from relation-
ship curve for each month •
• Plot annual turbidity vs. time ba$ed on these results.
10. Qualitative Assessment
• The above analysis obviously is simple and assumes a modified ideal sit-
uation. The results would probably portray maximum clarity that could be
expected in the Watana Reservoir.
• Address each assumption made and! qualitatively assess it with respect to
the real situation.
• Develop other scenarios that would bound the above res:ults and reasonably
represent confidence limits. Plot on turbidity vs. time graph.
16
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
TABLE 4
SUSITNA SEDIMENTATION AND WATER CLARITY STUDY
WATANA RESERVOIR
VARIABLES TO BE.CONSIDERED IN ANALYSES
Morphological
• Depth
• Length
• Width
. Surface area
• Volume
• Shoreline characteristics
• Lake surface and land drainage relationship
Physical
• Ba•;·in characteristics
• Latitude
. Altitude
• Drainage area
• Percent glacier coverage
Reservoir
• Orientation
• Distance from source
• Streamflow -post project inflow/outflow
• Deter;tion time
. Wind-generated currents
• Thermal currents
. Operational induced currents
Climate
• Wind
• Air temperature
• Solar radiation
. Cloud cover
. Mean annual precipitation
• Water temperature
• Ice cover development
• Albedo
Sediment
• Incoming sediment concentration
• Turbidity/1 ight attenuation
• Particle size distribution
17
I
I
••
I
I
I
I'
I
I
I
I
I
I
I
I
I
I
I
I
TABLE 4 (Cont'd)
• Specific weight
.. Mineralogy
.. Electrical properties
Chemical
• pH
• Conductivity
• Alkalinity
• Phosphorous
• Nitrogen
Reservoir Operation
• Potential bank erosion
• Permafrost processes
• Effects of changing water levels
• Outlet elevations
• Orawdown
Processes Active in the Reservoir
• Trap efficiency
• Flow patterns
-Underflow
-Inflow
-Overflow
-Currents
• Wind
• Density
• Thermal
• Sedimentation processes
-Coagulation
-Floccul aton
-Aggradation
-Reentr'ainment
-Stratification
. Thermal processes
-Stratification
,.
18
I
I
I
I
I
I
I
I
I
I
I
I
-I
I
I
I
I
I
I
"
Subtask 5 .. 09 -sc·oeing FY83 Program (Geotechnical)
(a) Obj£!CtiY!
,
This work will be done from April l, 1982 through June 30, 1982, and will
consist of preparing a detailed scope and cost for performing the geotech-
nical work during fiscal year 1983.
(b) ApJ?roach/Discussion
Work from April 1 through June 30 will consist of preparing a detailed
scope and cost for performing the geotechnical work during FY83.
The scope of work to be undertaken will be prioritized based on geotech-
nical and engineer'ing design requirements.. The scope will clearly define
the objective and purpose for performing the work. Based on the results of
the 1980-81 geotechnical work performed at the Watana site, the principal
areas to be investigated during FY83 are:
• Borrow Areas D, E, and I; and
• Relict channel.
The scope of work to be prepared wi 11 . inc 1 ude aetai 1 s of:
• Type of· equipment to be used;
• Number, location, and depth of boreholes and test trenches;
• Seismic work;
• In-hole testing; and
.. Laboratory testing.
Also included in the scope will be a detailed schedule and cost for per-
forming the work and preparation of necessary permit application to local
and state agencies. Alternative contingency plans for accomplishing this
work will also be addressed.
(c) Schedule
April 1, 1982 through June 30, 1982.
19
I
I
·~
I
I
I
I
I
I'
• II
I
I
I
I
I
I
I
I
I
Subtask 5.10 -Specification Preparation and Contract
Administration (Geotechnical)
(a) Objective.
To prepare the necessary specifications and contracts to do the work
defined under Subtask 5o09 ..
(b) Approach/Discussion
Based on the scope of work prepared under Subtask 5.09, the necessary spec-
ifications and contY'acts will be prepared to perfonn the work within the
project schedule. The Anchorage and Buffalo offices will identify equip-
ment suppliers and testing facilities that are capable of performing the·
FY83 work. Discussions will be held with various vendors and contractors
to ascertain their capabilities of performing the work.
In order to meet the project schedule_for commencing field investigations
by July 1982, drilling and testing contracts must be in place so that
mobilization can begin on July 1. Where necessary, Acres will:
.. Prepare specifications and bid documents;
• Issue for bids and review quotations; and
.. Award and prepare contracts ..
(c) Schedule
It is anticipated that all contracts for performing the summer work from
July 1 through September 30 will be tn place by June 1982~
20
I
I
••
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Subtask 5.11 -Field Investigations, Testing~ and Reports {Geotechnical)
(a) Objective
To perform additional field investigations, laboratory testing, data reduc~
tion, and prepare the fiscal year 1983 geotechnical program ..
{b) !illProach/Oiscussion
Based on a detailed review of the geologic and geotechnical conditions at
the Watana. site, three principal areas warrant further investigation during
the July through September period. These are:
• Borrow Areas 0, E, and I; and
• Relict channelo
Details of the proposed FY~3 investigation program wi11 be presented to APA
during May 1982. The work to be undertaken during July through September
will consist of geologic mapping, drilling, laboratory testing, and data
processing.
(i) Borrow Area D InvestigC!tion
-Objective
To confirm the quantity and material properties of borrow mate-
rials in Area D ..
-Approach
Acres proposes to use two auger type dr.i 11 rigs capable of dri 11-
ing to depths of 100 to 150 feet in Area D. Disturbed and undis-
turbed samples will be taken as required for laboratory testing,.
Selected holes will be instrumented upon completion to monitor
ground water and permafrost conditions.
(if) Relict Channel Investigation
-Objective
To confirm the stratigraphy and material properties within the
relict channel and to determine the extent of these units at
depth. To perform preliminary tests to determine the hydrologic
regime in the relict cnannel.
.
-Approach
Acres proposes to use the auger drill rigs used in the Borrow Area
D·to perform drilling in the relict channel. The limited capacity
of these rigs preclude the drilling to the bottom of the thalweg;
however, it is expected that sufficient shallow surface data will
21
••
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
be obtained to develop a detailed investigative program for the
winter FY83 dr i 11 i ng progr ~m ..
(iif) G!plogic Mapping
Acres will perform a lim·ited geologic mapping program in the relict
channel, Borrow Area 0 and the damsite" The mapping is required to
obtain recorded data for the scoping of the FY83 win~er and spring
drilling programs. In addition, the geologic features identified
during the 1980-81 program wi 11 be mapped for continu·ity. Detailed
survey control will be provided to accurately locate these features
relative to the damsite. In addition, survey contro1s will be
established along the river for that which is used 1y the Becker
dri 11 ing program.
(iv) Laboratory T.es!ing
Concurrent with the field inve~tigation, a detailed soils testing
program will be implemented for the borrow area and relict channel ..
To expedite the testing program, Acr-es proposes to establish a soils
1 aboratory at the Watana camp to perform routine soil t·asts. The
more sophisticated tests, incluJiing cyclic triaxia.l and resonant
column tests, will be performed by qualified laboratories.
(v) Data Reduction
To expedite the data reduction, Acres proposes that the information
coming from the program be reduced and analyzed in the field. To
accomplish this, Acres proposes to place a contingent of engineers
and geologists who have worked extensively on the project in the
field during this period. They will work in the collection and
reduction of the data. It is anticipated that at the termination of
the exploration program .in September, all the fiela data will be in
a draft form suitable for firtal reduction and report preparation.
Long-term laboratory testing will likely not be completed within the
September time frame.
(vi) Preparation of FY83 Winter Program
As a result of the lengthy lead time required to mobilize special
equipment needed for the winter program, it will be necessary to
implement the planning and contractual arrangements for" this equip.-
ment during July and August 1983. As part of this task, Acres pro-
poses to prepare the detailed scope of work (which will be based an
preliminary results obtained from activities in the relict channel}
and to prepare the necessary specifications and contracts for per-
forming the winter program.
22
I
I
a·
I
I
I
I
I
I
I
I
I
I.
I
I
I
I
I
I
(c) Accomplishments and Deliverables
Report
.
Geotechnical Field Uata (Draft)
Engineering and Geotechnical Heconnaissance
Report of Primary Routes
FIELD EXPLORATION PROGRAM
Instrumentation Monitoring
Laboratory Tests on Aggregate Samples
23
Uate
~eptemoer 30, 1982
September 1~ 1982
June 20, 1982
July 20, 1982
August 20, 1982
September 20, 1982
September 15, 1982
-I
I
I
I
I
I
I
I.
I
I
I
I
I
I
.I
I·
I
I
I
TASK 6 -DESIGN DEVELOPMENT
(a} Objective
Update various design aspects of project and address those design changes
necessary to meet changing environmental criteria.
{b) Approach/Discussion
A~though not precisely defined at this time, there will be certain proposed
design changes or ·investigation of various possible alternatives to the de-
sign which will be required to meet changing environmental criteria.
Examples of these are possible changes in access route location, el imina-
tion of the pioneer road concept, intake structure changes if additional
gathering of temperature data so indicates, etc. Appropriate budget has
been designated for this work.
(c) Schedule
April 1, 1982 through September 30, 1982.
24
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I -.
Subtask 7~05 -Socioeconomi~ Analysis
The proposed socioeconomic studies are divided into two separate work packages.
The numbers one and two are used consistently to refer to work packages eight
and nine.
(a) · Obje~t i ves
The objectives of the two different proposed work packages are as follows;
1. Determine economic effects of Susitna Hydroelectric Project on conmer-
cial, recreational, and subsistence fish and game user groups.
2. Determine the significance of the economic effects of the Project for
each user group.
{b) Justification
Heasons for implementing the two socioeconomic work packages are as
follows:
1. Economic value is a common denominator. These values will provioe a
better understanding of what could be gained or lost by user groups and
will facilitate the development of mitigation measures.
2. Frequently, dollar values by themselves are not meaningful. Dollar
values need to be ~ut into contexts that are meaningful to both t~ose
persons being impacted and those who make decisions.
(c) Approach/Discussion
•
1. vlork Package 8: Economic Effects of Project on Commercial, Recrea-
tional, and Subsistence User Groups.
To complete this work package, a determination will be made .of the
economic effects on user gl·oups that could result from project-induced
changes in the harvestable stocks of fish (e.g., salmon, Dolly Varden,
Arctic grayling, etc.) and game (e.g., moose, caribou, brown bear!>
etc.). For fish, the focus is on salmon that utilize the Susitna River
and its tributaries and drainages; and f9r game, the focus is ori Game
Management Unit 13.
2. Hark Package 9: Significance of Economic Effects of Project on Commer-
cial, Recreational, and Subsistence User broups.
Minimum resource conditions/ standaras vii 11 be determined for each user
group. Past and present utilization rates and patterns will play a key
role in these determinations. The minimum resource conditions for each
user group will be compared to the expected resource condition {i.e.,
project-induced resource conditions). Differences in the conditions
will be calculated on a ·per-user basis. Where losses are identified,
opportunities for users to make up part or all of losses will be iden-
tified. These opportunities will involve harvest of fish and game in
other geographic areas and/or habitat replenishment.
26
I
I
I;
I
I
I
I
I
I
I
I ,_.,
I
I
I
I
I
I
I
I
(d) Accomplishments and Deliverables
-4th Quarter FY82
\-lark Package 8 will be concentrated during this quar-ter. The ;ccomp1 ish-
ments duri.ng the quarter are as follows:
1. Describe user groups and user group ut i1 i zati on of selected fish and
game species (salmon, artie grayling, Dolly Varden, moose, caribou,
bear, and selected furbearers).
2. Determine and describe user group characteristics.
J. Determine quantity and value of harvest by location and user group.
4. Assess project-induced changes in harvestable stock and value of har-
vestable stock by location and user group.
5.. Determine potential changes in unit fish and game values and implica-
tion of these changes to user groups.
It should be noted that in this analysis it will be assumed that, where
the cost of harvest exceeds the cost of delivery of a fish or animal to a
person's residence, the user will be considered a recreational user. At
the end of the quarter a draft report will be available.
The basic information needed to accomplish Work Package 9 will be assem-
bled during this quarter. Accomplishments include:
1. Establish minimum resource conditions on. a per-user basis.
2. Describe future fish and game utilization rates 0-n a per-user basis ..
3. Compare future utilization rates to the minimum resource conditions
on a per-user basis.
4. Compare fu1:ure resources va 1 ue per user to current resource value per
user.
5. Identify ways to mitigate losses or ennance benefits.
6. Briefly assess impact of increasing demand for fish and game on cur-
rent users.
-1st Quarter FY83
Botn Work Package reports will be fina1ized by early September. Under
Work Package 8 a draft report will be released for comments to various
project member's. A final report will be prepared two weeks following
receipt of all comments. Under Work Package 9, a draft report will be
available at the end of July. The report will oe finalized four weeks
from receipt of comments on the Work Pack.age 8 report.
27
I
I
I
I
I
I,
I
I
I
I
I
I
I
I
I
I
I
Suotask 7.06 -Cultural ResourcesJr1vestigation
(a) Objective
To identify the archaeological and historical resources of the project
study area and to propose mitigation measures to 'lessen the impact of
ground-disturbing preconstruction and construction activities.
(b) Approach
(c)
The Cultural Resources Investigation is designed to fulfill the cultural
resource obligation for both the licensing and construction phases of this
project~ through pre-license application {Phase I) and post-license appli-
cation (Phase II) efforts~
Cultural resources experts at the University of Alaska lvtuseum wi 11 execute
an intensive five-step research effort specifically to satisfy both state
and federal legislation pertinent to cultural resources. The five steps
are:
(1)
(2)
(3)
(4)
(5)
Preparation for field studies;
Reconnaissance-level archaeological survey of P~'"Oject areas;
Intensive testing of archaeological and historic sites discovered
during Step (2);
Final report preparation; and
Registration of all collections in accoraance with state and federal
requirements pertinent to the preservation of antiquities.
The University·Museum will execute a multi-step research effort specif-
ically designed to satisfy both state and federal legislation pertinent to
cultural resources.
The steps are as follows:
Step 1 -t<ee.ruitment of personnel and fie.ld work staging. Clearance "Work
in preparation for geotechnical testing.. Limited· scope in late
June for initial crew.
Step 2 -Reconnaissance-level archaeological survey of priority areas, in-
cluding access corridors and potential sites identified in pre-
vious work. This will be an intensive effort within the rela-
tively short field season.
s·tep 3 -Intensive testing of archaeological and historical sites discov-
ered during earlier work. Steps 2 and 3 activities may conttnue
s imu 1 taneous ly.
Step 4 -Dr~+"t report pre par at ion to provide location and pre 1 iminary des-
criptitm of cultural sites recorded. All steps will provide rec-
ommendations for mitigation of adverse effects.
Schedule
June 15, 1982 through September 30, 1982.
28
I
.. I
I
I
I
I
I
I
I
·I
I
I
I
I
I
I
I .,
I
Subtask 7 .. 07 -Land Use Analysis -Winter Navigation Survey
(a) Objective
To determine the magnitude and significance of dogsled and snowmobile use
of the Susitna River in areas that could be affected by the Susitna Hydro-
electric Project. To qualitatively assess the impacts of the project upon
this means of transportation and associated human activities.
(b) Justification
The Susitna River, in its frozen winter condition, is currently used as an
avenue of tran~portation by means of dogsleds and sno'hroobiles. The degree
of significance of this use, however, is presently unknown.. Ice studies
have predicted that during project operation the Susitna River below the
Oev i 1 Canyon dam wi 11 have open -water in the winter at 1 east as far down-
stream as Talkeetna. Agencies and private individuals have expressed and
doct.mented their concern about the impact of the project on winter use of
the river. A study based on interviews and existing information will be
the first step in answering these concerns.
(c) Approach/Discussion
Interviews with agency personnel and private individuals (including repre-
sentatives of dogsledding organizations) will yield information on the pur-
poses of winter trave~--for example, trapping, recreation, travel between
Trapper Creek and Talkeetna. Such information on the purpose of travel
will be usea to make qualitative assessments of the potential ramifications
of the preclusion of winter river travel due to changes in ice conditions ..
Publ ishea and unpublished reports that might contain information on winter
river use will also be sought. Available results of Susitna ice studies
will be reviewed, and a qualitative assessment of the impacts on w'inter
river travel due to changes in ice conditions will be made.
(d) Quarterly Accomplishments and Deliverables
4th Quarter fY82
None~
-1st Quarter FY83
Interviews and data review will be performed in July and August 1982. A
draft report of findings will be prepared by the end of September 1982.
No results from this study will be incorporated into the license applica-
tion. (As in the Feasibility Report, this impact issue will be addressed
in general terms in the License Application.) ·
29
I
I
I
I
I
I
I
I
I
I
I
I
I
i
I
I
I ,,
I
Subtask 7.07-La~d Use Analysis-Mitigation of Aesthetic Impacts
.. c .. . . . .
(a) Objective
To develop a draft plari for mitigation of impact.s of the Susitna Hydroelec-
tric Project on the aesthetic resources of the Upper Susitna River Basin.
(b) Justific'ation
FERC requires a license application to contain, in a report on aesthetic
res·ources, "a description of mitigative-measures proposed by the applicant,
including architectural design,-landscaping, and other reasonable treatment
to be given project works to preserve and enhance aesthetic and related re-
sources during construction and operation of proposed project facilities."
The recently enacted FERC regulations place this requirement in the envi-
ronmental report (Exhibit E) rather than in a separate exhibit (Exhibit V
under the superseded regulations}. The· FERC 1 icense application, by June
1982, will address the mitigation of aesthetic impacts.o Because of the
general and conditional nature of many of the statements to be mades how-
ever, this report will not represent a "mitigation plan!' Although tne en-
vironmental team has provided input to the design engineers on many issues
of visual impact, sites for some project facilities were selected too late
in the feasib~lity study process to permit a thorough dialogue between the
des·ign engineers and the environmental tearn prior to_ the preparation of the
license application. Therefore, without additional work~ the FERC require-
ments for the Report on Aesthetic Resources cannot be completely addressed.
Furthermore~ many aspects of project facilities will undergo refinement
during continuing design studies, thereby presenting an opportunity to mit-
igate some potential impacts on aesthetic resources ..
{c) Approach/Discussion
The essence of this effort will be coordination bet\':cen Acres and the
environmental team. The preparat·ion of the draft mitigatjon plan requires
substantial cooper at ion and written input from project architects and engi-
neers.
Project facilities that will be discussed with aesign engi.neers inclooe the
architectural design and landscaping of the permanent village at Watana and
the appearance and design of other facility components. The plans for res-
toration of borrow areas, to reduce the degree of permanent visual 'ifli41act,
also need further refinement. Further planning and design of recreation
facilities {see Subtask. 7.08) will require coordination to assure that
these facilities themselves are compatible with the landscape and also that
unattractive aspects of project facilities do not detract from the setting
of the recreation facilities.
This aesthetic mitigation effort does not include the proposed transmission
facilities or access road, although further mitigation of the potential
aesthetic impacts associated with these facilities will eventually be
30
.I
I
-:1-
I
-1
I
I
I
I
I
I
-.
I'
I
1-
I
I
I
If'
required. Visual impacts will be the primary consideration, but limited
attention will also be given to noise, where appropriate, and to odor,
where applicable. Emphasis will oe placed on the avoidance or minimization
of permanent impacts to aesthetic resources, rather than on temporary -
intrusions during the construction period, when public access will be
restricted ..
(d) Quarterly Accomplishments and Oeliverables
-4th Quarter FY82
None.
-lst Quarter FY83
The product of this work package ~/ill be a draft plan in early September
for the m"itigat ion of aesthetic impacts.
Review of the assembled report by Acres and approval by APA will then be
required, but revision of the report prior to September 30 is n.ot antici-
pated. Such revision, as well as continued coordination ana mitigation-
planning, will likely be needed as part of subsequent efforts.
31
.-I-
I_
I·
I
I
I
I
I
·I
I
I'
I
I
I
I
I
I
S~btask 7.0~ ~ Recr:ea.tion P1anniJ1.9
(a) Objective
To obtain quantitative estimates of existing use of the project vicinity in
the Upper Susitna River Basin and to refine the recreation plan for the
Susitna Hydroelectric Project.
(b) Justi.fication
i::lec.ause of the subtle and dispersed nature of existing recreationa1 use in
the vicinity of the proposed hydroelectric project, quantitative estimates
of such use are very difficult to obtain.. With recognition that existing
use is low in comparison with more accessible areas, the Phase I Plan of
Study did not propose to attempt quantification. Nevertheless, ·state
agency personnel have expressed their desire to know how much existing use
would be affected by the proposed project. Also, FERC license application
requirements include "estimates of existing and future recreational use at
the project,9 in daytime and overnight visitation (recreation daysr, with a
.description of the methodology used in developing these data.u To fully
.:nmply with this regulation, some attempt at quantification of existing use
seems necessary.
Although a conceptual recreation plan has been developed, including specif-
ic proposea sites for recreation facilities, many details of these facil-
ities remain to be worked out. As plans are refined, the cost and schedule
of recreation development should be refined accordingly.
(c) Approach/Discussion
A concerted effort will be made to obtain quantitative estimates of exist-
ing recreational use of the Upper Susitna River Basin. A field survey of
recreationists in the project area is not considered to be practical"" and
will not be. attempted. Potential sources of existing data, however, will
be probed. These potential sources include guiding records and other st~
tistics maintained by tne Alaska Department of Public Safety, Division of
Fish and Wildlife Protection~ Air taxi operators, riverboat services. and
the managers of the three lodges in the project vicinity (Stephan Lake,
H'igh Lake, and Tsusena) wi 11 be contacted for information on the lavels of
present recreation.
Refinement of the recreation plan itself will consist of planning and pre-
liminary site drawings for specific recreation facilities •.. To avoid un-
necessary expPnditures, this effort will be 1 imited at this time to those
facilities which form the nucleus of the recreation plan. Such site plan-
ning will present agencies with a more detailed proposal· and, thus, may
facilitate the approval process. This effort will include, in particular,
continuing and strengthening dialogue on a technical level wit~ AUNt<,
Division of Parks, and USDI, National Park Service. Coordination with the
Aldska Division· of Parks is especially important in the plan refinement
stages to ensure consistency in objectives and standards. Refinement of
-I
I
I
-I
I
••
I
I
I
I
~I
I
I
I
I
I
I
-I
I
·the schedule and costs as-stleiated with the proposed recreation faci 1 ities ~ill also be accomplished as additional details are developed.
{d) Quar~rly Accomp 1 ishments and Del iverab les
-/fth Quarter FY82
None.
-1st Quarter FY83
The results of this subtask will be presented in a supplementary report
on recreation resources, which is scheduled to be completed in draft form
in early September. Additional site planning and design of recreation
facilities will be required in subsequent Phase II studies.~
.,
33
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Subtask 7 .. 10 ... Fish Ecology Baseline Studies and Analysis
(a) o.bJective
To perform the necessary analyses and prepare various technical reports in
support of Exhibit E of FERC license application. Specific objectives to
be accomp l i shed are: ·
-Provide a review of the feasibility report and identify data analysis
deficiencies~ related data ~aps for all subjects~ the proposed ·course of
action to be taken by the group to rectify deficiencies within its area
of responsibility.
-Recommended studies to be implemented in 19~2 to fill any data gaps.
These studies would be funded within the 1982 budgets of other organiza-
tions or from the allocation of discretionary resources alloted to the
analysis group. Detailed study .plans will be provided for any new
studies recomnended by the analysis groupe
-Prepare technical reports within a variety of the subject areas in sup-
port of the FERC license application. May 31, 1982, will be the cut-off
date for any additional data that might be included in support documents
for a September 30, 1982 1 icense appl icatione These documents will in-
clude an analysis of historic, literature, and project data. They will
provide a comprehensive discussion of project effects on the in stream use
or resource of interest, and identify any 1982 summer studies that might
provide pertinent data or information which could be amended to the
application. Mitigation options will be described in as much deta.il as
is presently possible, in a sequence consistent with the USFWS definition
of mitigation. The limitations and the benefits for each mitigation
option will be detailed.
-Provide periodic technical seminars/workshops for the resource agencies
through the Susitna Hydro Steering Committee.
"'
-Interim administrative reporting will be minimal; finished technical sup-
port docl.JT1ents wi 11 be suomitted as required.
-Prepare technical amendments and responses to support the FERC license
application which includes 1982 summer study results.
(b) Approach/Discussion
The interdisciplinary group would identify project effects (positive and
negative) on the i nstre am uses and resources of ·the Sus itna River with the
exception of reparian vegetation and wildlife haoitat. In oaddition, the
analysis group will oversee the conduct of the necessary studies and pre-
pare a report on the 1 imnology and fishery potential of the impoundments. .
34
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
The analysis group will consist of five.or six profassionals familiar with
the Susitna project~· with demonstra.t.ed experience in conducting field in~
vestigations, and prepare technical reports related to their respective
subject areas •
The group will be responsible for technical coordination of the studies,
including contents of the report, their review, editing, and final report
production.
The following are specific r ... eports that will be prepared by this group in
support of the license application. Each of these reports will be the
assigned res~~nsibility of one of the member~ of the analysis group. ~
(i) Streamflows
This study will involve the review of the feasibility report and
evaluation of the data base supporting comments on downstream flow
impacts. All existing AUF&u and R&M data will be reviewed and rec-
ommendations will be made for expanding or modifying the field work
proposed for the su.r!!mer of 1982. This plan will emphasize use of
the summer 1982 field data for making a preliminary assessment of
the effect of incremental changes in discharge on the utility of the
slough habitats. An interim assessment will be prepared for submi s-
sion to ±he FERC in September. Impact minimization between these
extremes will also be discussed to the extent existing information
will allow.
( i i) . Downstream Temperature Studies
This study will involve review of the stream temperature model and
temperature data available from Acres, R&Yt, and ADF&G. In addition
to the review of co11111ents contained in the feasibility report, which
. pertain· to project effects on stream temperatures, recommendations
wi 11 be made to improve the predictive capability of the stream
temperature models. An analysis will be provided, based on existing
data as of May 31, 1982, which will incl u·de quantitative estimates
of the effects of altered temperatures on egg incubation and emer-
gence. Preliminary statements will be made regarding the antici-
pated effects of altered temperatures. on the fisheries.. The 1982
winter thermal data wi 11 be included in the license application ..
(iii) Water Quality Studies
This study will include review of the feasibility report and will
make recommendations for implementing additional study during the
1982 field season. All of the existing data sources will be com ...
piled and analyzed to define baseline water quality conditions for
the system. Further~ this information will be used to predict the
water quality of the post-project reservoirs, 1 imnological para-
meters of these reservoirs, and productivity of the reservoirs under
post-project conditions. -Information of the water quality of the
reservoirs will also be used to determine water quality of the
35
I:
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
down-stream releases and the probable effects such water qua1 ity con-
ditions would have on the downstream fisheries resources.
(iv) Fisheries Studies
It is the specific intent of this element of the analysis group pro-
gl·am to emphasize and d.escribe the various mitigation options avail-
able to alleviate the impacts identified in the streamflow, stream
temperature, and water quality study reports.. .
This study ~ill involve a review of the feasibility report and will
determine additional analysis and data that are needed to support
the FERC license application. Additional field studies that neea to
be completed during the 1982 summer field season will be desi·gned
and implemented. A report wi 11 be prepared that provides a summary
description of the impacts on the fisheries below Devil Canyon and
discusses specific n.ethods for mitigating these impacts. A report
will.also be prepared on the anticipated.limnological char·acteris-
tics of the Watana Reservoir and its fishery potential ..
(v) Navigation Studies
This study will involve review of the section on navigation con-
tained in the feasibility report and other support documents and
assure that any needed data are obtained during. the summer of 1~82.
The September 30 support document would prov.ide a comprehensive
assessment of river navigation based on all infol~mation available by
t4ay 31. Preliminary conclusions regarding effects of incremental
discharge changes on -navigation wi 11 be pr·ovided for the Susitna
River· .from Alexander slough to Devi 1 Canyon.
(vi) Estuarine Studies
This study will involve review of the section on estuarine impacts
in the feasibility report~ A review of the available literature on
the Cook Inlet estuary will be completed, and interviews will be
conducted with biologists and physical scientists familar with
estuarine problems. Information on ice format ion and prob 1 ems asso-
ciated with icing in Cook Inlet will be a major area of discussion.
Any field studies that will be required will be designed and imple-
mented or scheduled for implementation prior to the. September 30,
1982 application oate. A report will be produced presenting all
existing information and literature pertinent to anticipated
estuarine impacts attributable to the project.
(vii) Geomorphological and Bedload Studies
This study will entail review of the existing documents and state-
ments contained in the feasibility report and make recommendations
for upgrading the data base and analyses supporting these state-
ments. Particular attention will be given to utilizing the bedload
36
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
data collected by the USGS in an analysis which addresse~ the sta-
bility of the conf1u~nce area. A report will be prepared providing
an impact assessment of the project .and mitigation plans witn regard
to th~se subject areas.
(viii) Downstream J ce. Stud,x:
This study will be limited to a review of the feasibility report and
supporting documents describing the ice process models and providing
a summary of statements and concerns regarding the present 1 evel of
confidence in the statements contained in the feasibility report
pertaining to downstream ice cover.
{c) Schedule
April 1, 1982 through September 30, 1982.
c
37
I
I
I
I
I
I
I -~
I
I
I
I
I·
I
I
I
• •
,.,
Su_btask 7 .J.l -Coordination of Wi.ldl ife Studies
(a}
(b)
(c)
(d)
Objectives
The purpose of this task would be to continue the coordination effort among
environmental contractors, subcontractors; and AOF&G. An associated goal
would be to respond to questions by review agencies.
Justification "
This effort is necessary because additional wildlife and habitat data will
be collected during Phase II, and there will be comments and questions from
review agencies that wi 11 have to be addressed. In -addition, coordination .. of the ongoing habitat studies with the big game ~tudies will-be required ..
Approach/Discussion
The wi~dlife work being performed by AOF&G and subcontractors along with
habitat data collected by the University of Alaska will be reviewed in
order to assure that the two types of data provide the appropriate informa-
tion in the proper fashion. This would be accomplished through several
means, one of \'olhich .would be by obtaining the opinions of a few select
species authorities. In addition, a 2-to-3-day workshop would be held in
oraer to. formulate an. approach to integrate the big game data with the
habitat data. Attending this workshop would be representatives fro.'lll the
ADF&G study team, consultants, plant ecology subcontractors, and personnel
outside the study program who have extensive experience with the habitat
relationships of the appropriate big game species.
Schedule
This effort would continue throughout the 4th quarter of FYB2 and tne first
quarter of FY83. Accomplishments will include the resolution of wi 1!rll1 if e-
nabitat interdigitation problems~ the initiation of Phase II studies~ and
the coordination of data collection efforts among the study participants.
38
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Subtask 7.11 -Riparian Zone of Lower Susitna River -tiird ana Beaver Surveys
(a) Obj'ective
The purpose of this study is to determine the species composition of birds
inhabiting the riparian zone along the lower river and to obtain sufficient
information on the ecology of beavers to enable a greater understanaing of
how the changes in hydrology caused by the Susitna Project will affect
them.
(b) Justification
During Phase I, data were gathered which served to document the gene~al
distribution of beaver abundance from Devil Canyon to the Delta Islands.
Further studies concerning specific characteristics of dens~ lodges, and
food caches are needed in order to determine the degree of change that
beaver populations may incur as a result of changes in flow regimes, ice
conditions, and successional trends of riparian vegetation. Since changes
in riparian vegetation are possible, it will also be necessary to ascertain
the avian species that inhabit the ay·ea and could be affected by changes
brought about by the project. With t.t')e exception of one census plot near
Sherman and a cursory survey of migruting waterfowl and n~sting bald
eagles, little bird study effort was expended downstream from uevil Canyon.
The studies proposed herein are designed to fill this data deficiency.
In addition, since portions of the lower Dasin, including the riparian
zone, are under consideration for moose habitat management efforts, it will
be necessary to predict what impacts any habitat changes that result from
moose management will have on other faunal gr.oups. If efforts such as
logging, -crushing, or burning are conducted, they will likely have more of
an impact on non-target species than will changes brought about by altering
the flow regime of the river. Therefore, an understanding of non-target
species such as the beaver, as w~ll as the avian populations involved, will
be needed, if a well-planned moose management program is to be approved.
(c) Approach/Discussion
Several aerial surveys would be conducted during spring to further document
the extent of waterfowl use of the river and also to accurately determine
the number of active bald eagle nests between Cook Inlet and Devil Canyon.
During the breeding season, bird surveys woulcl be conducted in major veg-
etation types in the riparian zone and immediately adjacent to the riparian
zone to document the species composition and general habitat use by breed-
ing birds. For this effort, selected areas from Sherman south to Cook
Inlet would be used and would be chosen following a review of vegetation
studies conducted during Phase I.
The study of beavers along the lower Susitna River would be divided into
the three river segments used previously, i.e., Uevil Canyon to Talkeetna,
Talkeetna to Montana Creek, and Montana Creek to the Delta Islands. To
gain a more complete understanding of the abundance of beavers, the first
step wi11 be to conduct an aerial survey, using helicopters, of all
39
I
I
I
I·
I
I
I
I
I
I
I
I
I
I
I
I
I
I
0
three reaches of the river. This will be done prior to breakup and again
during the open water period of the year. This effort will then be fol-
lowed by ground surveys, expedited through the use of a riverboat, to de-
termine the relationship between bank dens, lodges, and dams to vegetation
characteristics of the river. Notes concerning the location and phenology
of food cache construction and utilization will also be gathered. All
beaver data will be collected in such a 111anner as to enable the use of
corresponding hydrology information jn order to predict what changes the
project may have on the ecology of beavers in this area.
(d) Quarterly Accomplishments and Oeliverables
-4th Quarter FY82
1. The survey of waterfowl would be conducted at two-week intervals frorn
breakup to mid-June. Data tables summarizing the results of the
waterfowl survey would be prepared by July 1.
2. Bald eagle surveys would be conducted during late June, or possibly the
first half of July.
3. Breeding bird surveys would begin in late rv1ay and continue through the
quarter.
4. Aerial surveys for beaver would be conducted just before breakup, and
surveys from the river would occur during the latter half of the quarter.
-1st Quarter FY83
1. Results of the bald eagle survey would be avail able on August ltc 1982 ..
2. Breeding bird surveys would be completed by mid-July, with a prelim-
inary species list of breeding birds presented by Sep,tember 1, and data
analysis completed by September 30.
3. A summary of the spring beaver studies will be prepared by September
30, 1982.
40
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Subtask 7.11 -Breeding Bird and Small Marrmal Census -l!Q~r Basin
(a) Objective
The goal of this study would be to obtain a second year's data on breeding
bird densities and a third year's data on small mammal abundance in the
Upper Basin.
(b) Justification
The need for this effort is two-fold. First, due to annual differences in
abundance, especially small mammal species which are subject to cyclic and
fluctuating changes in abundance, additional data .are needed to provide
statistical validity to the information used in the initial impact predic-
t ions. The second, and probably more important need, is to gather suffi-
cient data concerning the habitat relationship of these two faunal groups
·for use .:n planning mitigation programs for other· species. This is very
important in regard to habitat management for moose. At the present time,
prescribed burning is being considered as a means of improving moose habi-
tat. Any such program wi 11 result in major changes in habitat with result-
ing impacts on species other than moose. In order to predict and, if pos-
sible, minimize negative impacts on non-target faunal groups, such as birds
and small mammals, it will first be n·ecessary to properly understand the
habitat requirements of all associated faunal groups. Failing to take the
impacts of moose management on other species into proper consideration
could be justifiably criticized. In addition to these two reasons for con-
ducting additional bird and small mammal censuses, there is the fact that
~everal resource agencies have recently been focusing their attention on
the habitat relationships of these faunal groups, and their review of the
Susitna will probably be more favorab1e if this aspect is addressed in a
scientifically valid manner.
(c) Approach/Uiscussion
Since study plots for birds and small mammals have already been established
and co~olete habitat data collected, this effort will simply entail an
addition1.l census of oreeding birds and small mammal abundance.. Breeding
bird cens'"ts techniques and small mammal trapping would be conducted during
the spring of 19ti2, and mammal trapping would be conducted dur·ing early
fall, 1982.
(d) Accomplishments and Ueliverables
-4th Quarter FY82
1. During April and the first half of May, continued detailed analysis
of Phase I data would be conducted.
2. Breeding bird census would start in 1 ate r~ay and continue tnrough the
quarter.
41
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I •
••
I
-1st Quarter FY83
1. Breeding bird censuses would be completed in early July with a
summarization of results available by September 30, 1982. Detailed
data analysis will fGllow.
2. Fall trapping of small mammals would take place in early September
with a brief tabulation of data prepared by the end of the quarter.
•
42
I
I
I
I
I
I
I
I
I
I
l ..
I
I
I
I
I
Subtask 7qll -Pine Marten Densities -Upper Basin
(a) Objective
The goal of this study is to determine the density of pine.marten in tne
vicinity of the proposed impoundments.
(b) Justification
Although a considerable volume of data was collected during Phase I on the
abundance and distribution of this !<ey furbearer species, the effort was
not designed to determine the densijty of this species. The determination
of furbearer density was originally scheduled for Phase II. Although suf-
ficient data exist to predict the general nature and extent of impact that
will result, determining the actual numbers of pine marten inhabiting the
impoundment zone would require additional survey effort.
(c} Approach/Discussio~
Several techniq-ues would be used to determine the density of pine marten
within the proposed ~Jatana and Devil Canyon impoundments. Aerial snow
transects would be flown in the spring and fdll to further document the
distribution and comparative abundance of pine marten. During summer~ a
1 imited amount of radio telemetry data would be gathered to improve the
estimate of home range size that was developed during Phase I and to aeter-
mine the utilization of the dominant habitat types in the impoundments.
Also, an intensive mark-recapture effort would be undertaken in the domi-
nant habitat type in' the Watana impoundment area as well as in the Devil
Canyon impoundment area. The results of the density estimate produced from
the mark-recapture effort, in conjunction with the aerial snow transect
data and radio telemetry data, would permit the generation of an estimate
of how many pine marten will be displaced by the two impoundments.
(d) Accomplishments and Oeliverables
-4th Quar.ter FYb2
The radio telemetry effort would begin during June.
-1st Quarter FY83
1. Radio telemetry studies would continue.
<
2. The mark-recapture effort would be conducted during July and
August.
3. Since neither a spring nor a fall aerial snow transect survey will
have been compl(:ted by the end of the quarter, a report presenting
tentative ;:onclusions, along with data summaries, will be available
by Sep_:tember 30, 1982. A pre 1 imi nary estimate of pine marten pop-
ulations will be available for inclusion in the license applica-
tion.
43
I
I
I
••
I
I
I
I
I
I
I
I
I
I
I
I
I
Subtask 7.11 -Refinement of Wildlife Mitigation Plan
(a) Objective
The purpose of this task would be to continue the mitigation planning con ...
ducted during Phase I. The goals would be to add quantification to the
mitigation effort and to interact with the resour~ce agencies in the devel-
opment of a final plan.
(b) Justification
Due to a lack of both data and time, it was impossible to develop a final
plan for mitigation during Phase 1. Although analysis of many options was
conducted and the process of developing a plan accomplished, a considerable
amount of work still remains to be done.
(c) Approach/Discussion
A wide variety of activities will be conducted under this effort~ Of fore-
most importance will be further analysis of wildlife baseline data, as well
as vegetative data, in order to quantify more precisely the degree of in-
pacts and, therefore, the extent of mitigation effort required. An effort
that will parallel this analysis would be the development of preliminary
cost efforts for mitigation. Obviously, final estimates could not be pre-
pared until the resolution of the final mitigation plan.
In some cases, moose habitat management being a good example, preliminary
steps would be initiated to identify candidate areas for management ef-
forts. Areas in both the Upper Bas in as we 11 as the Lower Basin would be
consiaered under this task.
An additional effort that would fall under this work package would be con-
tinued interaction and coordination with review agencies. This would pro-
·bably entail the clarification or modification of some mitigation issues.
(d) Accomplishments and Deliverables
This would be an ongoing effort covering the entire perioa of April through·
September.. No specific report is presently envisioned for preparation dur-
ing the identified time period. However, the Draft Wilalife Mitigation
Plan in the June Exhibit E will be updated and refined as a result of this
task ..
44
• • • • ,.. & • . . .
... . . -
~ ~· ' ' . _,
I
I
I
--I'
I
I
•••
I
I
-a
I
I
I
I
I
I
I
I
Subtask 7.12 -Browse Quality and Production Assessment in the BLM
Prescribed Burn Are:
(a) Objective
To collect~baseline data necessary to measure the change in the quantity of
moose browse resulting when scrub forest, mlJsl<eg, and other relatively un-
productive shrublands are burned; and to establish permanent plots to moni-
tor vegetation.
(b) Justificat1on
Manipulation of habitat through burning to promote an increase in moose
browse is one of the few promising measures for mitigating loss or degrad~
tion of wildlife habitat •
The extent to which Drowse production increases following a fire is un-
known. Responses are positive for most habitat types; however, some re-
sponses to wildfire have been negative on the Kanai National Moose Range.
The duration of benefits is also undocumented.
The assessment of prescribed burning can be delayed by land ownership pro-
blems. Currently the BLM plans to burn an area in the Alphabet Hills
region of the Upper Susitna l:Sasin. They would be responsible for the costs
and manpower involved with setting and controllihg the fire. A unique and
economical opportunity therefore exists for preburn nabitat and big game
studies to be conducted in this area. This proposed effort is directed at
the vegetation studies, with the big game studies being hand led separately
by ADF&G.
(c) Approach/Discussion
Investigations will include vegetation mapping, plant·production~ inventor-
ies, community structure, and species composition surveys, with emphasis on
important browse palnts such as willow. These data will demand establish-
ing permanently marked plots within the burn and beyond its borders. Data
will be collected on current y~ar•s proauction available for winter use.
Fire severity and intensity will a1sn be measured at each plot. Cont:s that
melt .at different temperatures will be pl.ar.ed in the ffe.ld prior to the
burn.
(d) Quarterly Accomplishments and Deliverables
-4th Quarter FY82
The burn area wi 11 be mapped during May. A draft vegetation map will be
available by the end of the quarter. Preburn plots will be located dur-
ing this quarter •.
45
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I '
'
-1st Quarter FYH3
The primary emphasis during this quarter wi 11 be the fina1 ization of the
vegetation maps and summer sampling of the preburn plots~ Vegetation
sampling including browse production and forage will be performed in July
and August. By the end of the quarter, a final draft of the vegetation
map will be presented; a species list of vegetation by community within
the burn area will be compiled; and raw data for browse production and
forage will be available.
46
I
I
I
I
I
I
I
I
~·
I
I
.I
I ~--
I
I <'.
I
-·<
. . ·.·. ·-~· .: -"' .. : .. .-._· .. :·:·.<>:.-:..{~ .. ·: ...... _ .. ·:: ···~· .:·· .. · ... · .. ·.~ ··. · ..... :· ..... · .. · .. : ... · .. , ... _ .· .. · .. : --.~:-· ... .-·~ .:·_
Subtask 7.12 -Browse Inventory
(a} Objective
To measure the annual production, a rough estimate of summer use, and qual-
ity of moose browse in various habitat types in the Susitna Basin and use
these data to calculate carrying capacities of the moose ranges affected by
the Susitna Hydroe.lectric Project.
(b) Justification
Browse production and use of different habitat types are key ingredients
for assessing losses (impacts) and assessing the extent of mitigation
(principally compensation) required for the proposed facilities. The im-
plementatinn and design of a mitigation plan for wildlife will be greatly
enhanced by the browse information. This study is directed at moose, which
is the key big game species.
(c) Approach/Discussion
Available browse production, an estimate of summer use, and quality will be
determined by vegetation/habitat type in the upper basin and selected down-
stream areas. Plots will oe establist1ed in various vegetation/habitat
typesl) both within and outside airect impact areas. Browse will be mea-
sured once during the growing season. Summer production and an estimate of
summer use will then be calculated.
As vegetation develops during the spring season, plots will be established
for spring forage production and spring phenology studies in selected areas
in the Upper Basin. The forage production will involve small enclosure
plots placed in areas determined by ADF&G to sustain heavy spring use by
moose. ThE; phenological studies will be directed at vegetation development
on south-facing slopes.
During the field effort, samples will be collected for the quality analy-
sis. Chemical analysis of these samples will be made at the Agricultural
Experiment Station laboratories in Palmer. Analysis will be made for vari-
ous components including protein content, minerals, digestibility, and
tanin content. Input will be requested from ADF&G for other important com-
ponents.
The production and use data will be available to be used in conjunction
with the annual requirements of a moose to predict the carrying capacity of
each habit at type. By knowing the amount of each habit at type to be 1 ost
and the amount remaining, an estimate can then be made of the project 1 s
effect on carrying capacity. Several other factors, however, influence the
ability of a given area to support a population. Further adjustments will
have to be made to the estimated figures. Input wi 11 be required fr.om
ADF&G project personnel and also from personnel involved in the research on
the Kenai Mease range.
47
I
I,
I
I
I ,,
I
I
I
I
I·
'I
1:
I
I
l
I
I
~
In addition to the browse work~ soil samples and pellet counts will be made
at each plot.. Supporting information will be obtained from these datao
(d) Quarterly Accomplishments and Deliverables
-4th Quarter FY82
During th·ts quarter raw data for spring phenology and forage production
will be collected~
-1st Quarter FY83
The phenology and spring forage data will be summarized during this
quartere As part of the chemical analysis, data will be available on the
Jay Creek salt lick. Uata on browse and forage production in the upper
Basin and selected downstream areas will be collected and will !Je in raw
data form by the end of the quarter.
48
I
I
I
I
I
I
I
I
I
I
I
I
I
••
I
I
1
I
I
Subtask 7~12-Identifying Sites Having Potential for Wildlife Miti_9ation
(a) Objective
To identify habitat types and associated sites which, through va_rious
techniques, could be altered to increase productivity of wildlife forage
and bro,_>Jse, and to locate specific areas for mitigation purposes.
(b) Justification
Increasing browse production and quality to compensate for moose habitat·
losses associated with the project is one of the primary mitigation op-
tions. Predictabi1 ity of how and where such treatments should be appl h:d
has not been developed at this time.
Providing information on ·where suitaoie mitigation practices might be best
applied will be needed in both the Upper and Lower Basin areas. The iden-
tification of areas that cou·ld be set aside is another avenue of mitiga-
tion.
(c) Approach/Discussion
Land use and land ownership will be investigated as a major consideration
in this task. Field investigation will also be a source of informat~on.
Prior experience with plant community mapping and data from the proposed
browse and burning studies will al?o prove useful. Currently existing
vegetation cover maps ana aerial photographs will be utilized to develop
potential locations for mitigation •. The identification of lands for miti-
gation purposes is primarily directed at moose mitigation, although some
potential caribou mitigation lands may also be identified. Field surveys
and further information will be utilized to refine this assessment.
(d) Quarterly Accomplishments and Deliverables
Information will be provided as needed with the final schedule oeing coord-
inated with the wildlife personnel. It is anticipated that an interim re-
port will be prepared by the end of September. The resuits of this task
will also be utilized in updating of the Draft Wildlife Mitigation Plan for
tne license applicqtion. The effort \>Jill probably be concentrated in the
first quarter FY83.
49
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
••
Subtask 7.15-Revision of the License Application and
Preparation of Backup Reports
(a) Objective
To revise various portions of the license application and to compile and
organize the available reports of certain environmental disciplines into
backup reports.
(b) Justification
Since the 1 icense application' will be prepared by June 30, 19H2, but not
s·ubmitted to FERC until September 30, 1982, various revisions to the appli-
cation may be required. Additional information, agency comments, change in
facility design or location, etc., will influence the contents of the
application.
Certain of the environmental studies proposed for implementation during
1982 will be compiled as backup reports.
(c} ~proach/OiS<:.!;~SSion
For the revision of the license application, Acres will provide the envi-
ronmental contractor with any changes in the proposed action. ·This will
generally include any modifications to loc-ation and design of project com-
ponents, scheduling of project events, and construction and operation spec-
ifications~ Revised sections of the application will then be prepared and
submitted to Acres. Refinement of the mitigation plan will be handled as a
separate work package.
Reports received from subcontractors will be refined into reports designed
to be used as backup t"eports. Technical revirw, typing, f!diting:J drafting,
and other services will be required to produce these reports.
(d) Accomplishments and Deliverables
Revisions to the 1 icense application as a result of cnanges in the proposed
action will be performed during July and August, with revised sections s·ub-
mitted to Acres by August 15, 1982.
The preparation of backup reports will begin following the receipt of re-
ports from subcontractors. Most of the effort will probably be performed
during the July to September period.
50
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Subtask 7.16 -Response to Interrogatories
(a) Objective
The objective of this proposed effort is to prepare responses to questions
and comments raised by agencies and other concerned groups on pertinent en-
vironmental report sec·tions.
(b) Justifications
Following release of the Feasibility Keport and the Phase I Final Keports
various questions and comments will be received. The comments will warrant
a response as part of the agency contact program.
(c) Approach/Discussion
Response to many of the comments received by APA and Acres will require in-
put from the environmental contractor~ who will provide input for questions
or comments that are received pertaining to the environmental reports .. All
input wi 11 be coordinated throu.gh Acres or APA. Any new information gener·-
ated during this process and received in time will be incorporated into the
application revision under Subtask 7.15.
The level of effort needed for providing input into responses is difficult
to estimate. For costing purposes, an estimate was made of the technical
input required. If more extensive ~ork is required, additional funds may
be requested.
(d) Accomplishments and Oeliverables
Technical input and letters will be provided as needed. It is anticipated
that most of the comments will be received in July and August. As are-
sult~ the effort will probably be concentrated in July, August, and
September.
51
'"· .·::·_., ... ,: .....
:J.. .
. ,,_~ ~
I
I_
;. .
. ~~
I
I
I
I
I
I
·I
I
I
'
. . . ·. . .. '-
• _. • # •
{a} Objective
(~ l ~ .__..r
Update cost est1mates. in connection with the proposed elimination of the
·pioneer road and alternate access routes for inclus-ion in FERC 1 icense
application~. "
/ .
(b) t2proach/D i scus s ion
Investigate. t·he elimination of t)~e pioneer road and alternative access
routes and ,their impact on construction costs res.ulting from changes in ·
schedule. Investigation to include a review of access alternatives covered
tn Task 2, plus other possible alternativesa The emphasis of inves·tigation
will be to determine access that will have minimun impact on schedule and
costs already developed f-or the project. The investigation will include a
site. vis it and discussions with subconsul tants.
( c} Schedule
May 15 through June 30~ 1982.
(d) Report
A suppl ementa 1 report ·Wi 11 be prepar-ed to summarize the results of the
study and reconmendations for access.
i'
I
·,
52
(
' ... -..... ~
\ \
J ·'
.
\~ { ' '
' i ~ t
{
'
.,. .....
~ ( ).
i,
I
I
I
I
-I
I
••
I
I
I
I
I
I
I
I
I
I
Subtask 9.04 -Develop Engineering/Construction Schedule
(a) Objective
(b)
(c)
(d)
Update construction schedules in connection with the proposed elimination
of the pioneer road and alternate access routes for inclusion in FERC
license application.
Approach/Discussio~
Si;-ilar to Subtask· 9.03 concerning cost estimates, an investigation of
the elimination of the pioneer road and alternative routes and their impact
on construction methodology and on-line power da~es will be made.
Schedule
May 15 through June 30, 1982.
Report
I
A supplemental report will be prepared to summarize the results of the
stuqy and recommendations for access.
I
I
I
I
I
I
I
·I
I
I
I
I
I
I
•
I
.I
Subtask 12.07 -Document Distrfhutian
(a) Objective
To prepare and distribute-additional copies of the Feasibility Report and
supporting reference documents to APA, state agencies and various other
interested parties in accordance with J\PA directives.
(b) Approach/Discussion
" The additional quantity requirements and distribution of the various proj-
ect documents were well over the original budgeted amount and involved the
collating, binding, packing and shipping of over 5,500 separate documents
and resulted in more than 12,000 pounds of material being shipped. Consid-
erable overtime had to be expended, as we 11, to meet the very strict time
constraints imposea.
(c) Schedule
March 15~ 1982, through June 30~ 1982.
54
I
I
I
I
·I
I
I
I
I
I
I
I
I
I
I
I
I
.I
J
Subtask 13.05 -Develop Cost Control System
(a) Objective
Continue with the necessary management tools and control systems for moni-
toring, reporting and control of project costs for the period July 1~ 1982,
through September 30, 1982.
(b) Approach
The cost control system will continue to use the expertise of both Acres
and Moolin personnel.
Both man-hours and dollars expended will be reported far the extenaed
pel~iod and the tot a 1 to da.te. Completion costs wi 11 be forecasted and
projected overruns/underruns will be tabulated. Reports will be submitted
to APA monthly.
(c) Schedule
July 1, 1982, through September 30, 1982.
55