HomeMy WebLinkAboutAPA2011\ ' ; ; I • I DOCUMENT CONTROL 'I;'• JH!jlllJJ!~ /EJJ~~~:~ SUBJECT ---------------------------------- SUS/TNA JOINT VENTURE COMPUTED ----------------CHECKED _, ___ _ PERSONNEL COMMUNICATION REPORT PERSON CONTACTED: Charles D. Craddock Engineering Operations Manager Harza-Ebasco Susitna Joint Venture 711 H Street Anchorage, AK. Contacted By: Charles Elliott FILE NO.--------__ DATE------- PAGE -OF _ PAGES SUBJECT: Projected traffic volumes on the project access roads. Conversation in regard to Wildlife Issue Paper W-10. Craddock reported the peak construction season would be about mid-April to mid-October. During the first 2 years of the project (not peak construGtion year) traffic flows will probably be 10% of peak construction year flows. After ·Lhe first 2 years, underground work will start and traffic flows should be about 40% of peak construction year traffic.