HomeMy WebLinkAboutAPA2355Co'.)
r
~
'""-I.
~_.
G.
~
-..<::
C='~
E
-
:\0'-
~Ie.p c
'"I~r.~(')P I 'a (')::r;
~-1 »CD ;z.()\~(')~;z~~~
,~r ~I---~-~rz
~r-I----''.~
~~'~I~'0
l;::i I~l>
()I II -;m,
April 1980
Fairbanks
Talkeetna
Wasilla
Anchorage
A report on
the first series of
community meetings
on the feasibility studies for the
Susitna hydroelectric
project and other
power alternatives
ALASKA
POWER
AUTHORITY
r/~.~..~~.~-..,
9u9rtNA.~HY<><>O"L£CTR'"
PACI-JO'C'T
~
Iiil :...~=-~·_·I
I/~
~
.-"""lt:f>tn~P'1ot~CIC t.)
ivVo)\Jl
Vo)
\Jl
lJ\
:I;
tr:
:&>'--uc~Zc
[%'l;;.:.
;>::cc..,
~
~en
CONTENTS
L ,~\"
I.Introduction
How people were invited 4
How many attended 4
How the meetings were organized 5
Role of the Alaska Power Authority,
the state legislature and the governor in the
Susitna feasibility studies . . . . . . . . . . . . . . . . ...9
Why Acres American,Inc.was selected to
conduct Susitna feasibility studies 10
Who the decision makers are 11
II.Summary of what the public said ;12
III.Evaluation of the meetings 14
IV.The next step . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .17
V.What happens to this report?18
APPENDIX A:Complete list of table top
discussion comments . . . . . . . . . . . . . . . . . . . . . . . . . .•. .19
APPENDIX B:Complete list of questions .39
Credits 61
Compiled by
THE PUBLIC PARTICIPATION OFFICE
OF THE ALASKA POWER AUTHORITY
333 West Fourth Avenue,Suite 31
Anchorage,Alaska 995011(907)276-0001
Eric P.Yould
Executive Director
Alaska Power Authority
Nancy Blunck
Director,Public Participation
Program
Alaska Power Authority
..\~,
-.)r,\
f
"_~".1-..'Zlt'>"cc~"~<::J)~~J
(WI"'\cP 0 ~'~V"en /'
The April community meetings were actually a continua-
tion of public participation in developing the Plan of
Study,as shown in the following chronology:
PUBLIC PARTICIPATION
THROUGH APRIL 1980
,
J
In April 1980,over 250 Alaskan citizens attended
community meetings in Fairbanks,Talkeetna,Wasilla,
and Anchorage to comment on the adequacy of the Plan
of Study for the Susitna hydroelectric study.
What is the Plan of Study?It is a 528-page document
that describes the individual studies that will be conducted
to determine the feasibility of Susitna hydroelectric
development.It describes how the studies will be
conducted,who will do each study,and the time frame for
completion.There are two aspects to a final decision on
Susitna.First,there is the question of technical feasibility.
This is determined by engineering studies.The other aspect
is how desirable any alternative or group of alternatives is,
and this is the part the public is involved in.Together both
parts form the basis for an informed decision on Susitna
hydroelectric development.
The Plan of Study is intended to be a dynamic
document.That means it can be changed when changes are
appropriate and the Plan of Study can be improved.
Changes can be suggested from the public,from the
legislature,from the governor,from state and federal
agencies,from Acres American,Inc.,from utilities,from
anyone.This report describes the comments,the
questions,and the suggested changes that came from the
public at the April community meetings.
July 1979
September 1979
December 1979
February 1980
April 1980
Environmental panel raised key issues
to engineering firms desiring contract
for Susitna feasibility studies.
Public reviews three plans of study,
listens to presentations,questions top
three engineering firms,and prefers
Acres American,Inc.
Agreement signed between state of
Alaska and Acres American,Inc.,to
conduct feasibility study.
Acres American,Inc.publishes Plan
of Study.Alaska Power Authority
distributes for review to groups,
agencies,individuals and public
libraries.
Fairbanks,Talkeetna,Wasilla and
Anchorage citizens comment on
adequacy of Plan of Study at
community meetings.
u---
2
HOW PEOPLE WERE INVITED
1.Personal letters were sent to the presidents and contact
:persons for 46 groups and organizations in the railbelt
communities,including commercial fishing groups,
sportsmen's groups,general public interest groups,
environmental groups,recreation groups,energy-
related groups,business groups,and mining groups.
2.Per~onal phone calls were made to the groups and
organizations.
3.Personal letters were sent to legislators,state and
federal agencies,and utilities.
4.Personal letters were sent to members and
subcontractors of the House Power Alternatives Study
Committee.
5.Large display ads were published in community
newspapers a week before the meetings.
6.Paid radio ads and public service announcements were
aired on local stations.
7.Daily notices of meetings were placed in newspaper
columns like "Today in Anchorage."
8.Press releases were issued informing the public that
Plans of Study were available for review in public
libraries and giving dates of upcoming community
meetings.
9.The Fairbanks Daily News Miner wrote a five-part
series on the Susitna hydroelectric project.The series
ran the week prior to the meetings and helped-to inform
people about the issues and invite them to the meetings.
HOW MANY ATTENDED
Fairbanks
April14 Travelers Inn
Talkeetna
April15 Talkeetna Elementary School
Wasilla
April16 Wasilla High School
Anchorage
April 17 Bartlett High School
Eric Yould and Robert Moho,Alaska Power Authority
70 persons
31 persons
42 persons
109 persons
252 TOTAL
4
r'
HOW THE MEETINGS
WERE ORGANIZED
The meetings were designed to meet three objectives:
-to describe the Plan of Study in understandable
terms
-to give the public a variety of opportunities to
comment on the adequacy of the Plan of Study and
to suggest additional areas of concern that the
Power Authority should be looking at
-to record all comments and questions in a useful
way for decision makers.
This part of the report describes how information was
given to the public and what methods were used to get
information back from the public.
Giving Information to the Public
Describing the Plan of Study was accomplished by three
formal presentations.It lasted about an hour and a half
and included the following;
SLIDE SHOW HIGHLIGHTING PLAN OF STUDY
John Lawrence,Acres American,Inc.(consultants
conducting the studies)
SLIDE SHOW DESCRIBING HOW ALTERNA-
TIVES WOULD BE REVIEWED AND EVALUATED
Robert Mohn,Alaska Power Authority
DESCRIPTION OF PUBLIC PARTICIPATION
PROGRAM AND ACTION SYSTEM
Nancy Blunck,Alaska Power Authority
Getting Information Back From the Public
A variety of methods was used to listen to what the public
said and to record it.The methods are summarized below
with a brief description:
QUESTION AND ANSWER PERIOD.
Questions were written on
cards because of time
1=======constraints and the large
r==:;~rt-~1f.~Lc:!:.f;!:;~numbers at some of the
meetings.165 questions were
1~~1-.::1:.1LJ.~~1'~~~~'received in writing at all four
1--":1~...:Jt.~~~'.J4...J:.1:meetings.Only in Anchorage
I-r/A./t •was there not enough time to
respond to all written questions.A complete list of
questions is in Appendix B of this report.
In all communities,some time was also given to
informal questions from the floor.These questions are
recorded in the verbatim transcript stored at the Alaska
Power Authority offices but are not included in this
report.
Questions were answered by members of Acres
American,Inc.study team and by members of the Alaska
Power Authority.
Nancy Blunck,Alaska Power Authority
5
TABLE TOP DISCUSSIONS.
INFORMAL CONVERSATIONS.
6
•
.-/--"..................
I ~~
1\~,
•Is this an adequate Plan of Study?
•Are there other concerns or questions that the
Alaska Power Authority should address?
The results of the table top discussions were reported
to the Alaska Power Authority and to Acres American,
Inc.in a summary form that night.The complete results
are in this report.There were 182 table top comments
received on the adequacy of the Plan of Study.
These discussions were held in
Fairbanks,Talkeetna,and
Anchorage,and gave each
participant a chance to voice
his or her concerns and
opinions in small groups of 6-8
people .••Each table had a
group member record all
comments in writing,and this provided the raw data for
the tables in Appendix A of this report.Each group was
asked to consider these two questions:
..Wasilla's meeting operated as a group of the whole and
did not include individual table top discussions.
During breaks,during table top discussions,and after the
meeting,members of the public individually talked with
Acres American,Inc.and Alaska Power Authority staff.
1
Top and below:Talkeetna citizens giving table top discussion reports.
7
i
ANCHORAGE -Paul Johnson,President of Anchorage
Chapter of the Sierra Club:.
•concern that it is very important to not get locked
into Susitna but take a fair and good look at
alternatives and that the public be involved in this
determining the feasibility of Susitna hydroelectric
development
•further concern that environmental and social
standards be established prior to a decision
ANCHORAGE -Floyd Heimbuch,Executive Director
of Cook Inlet Aquaculture Association:
•request that any mitigation plan or system have
payment in salmon,not in cash payments,and not
in a plan to fund research activities
•concern that the technology of stock separation is
not yet developed and request that the technology
be developed as a part of the Plan of Study
•concern that procedures for developing a
quantitative description of rearing and spawning
habitat are not well developed and therefore not
highly accurate
•statement that not necessarily opposed to Susitna
project and will help to provide answers to complex
questions of fish impact
The following two persons gave oral comments:
FAIRBANKS -Ron Punton:
•support the immediate go ahead with the intertie
between the Healy site and the Talkeetna site·
•the Public Participation office interprets this to
mean the intertie between Fairbanks and
Anchorage
There was a formal opportunity at each meeting for people
to give written or oral comments to the groups as a whole.
Three persons presented written comments they had
prepared ahead of time.The complete texts are included in
the verbatim transcripts at the Alaska Power Authority
offices.Additionally the testimonies have been entered
into the ACTION SYSTEM and are being responded to in
writing by Acres American,Inc.and the Alaska Power
Authority.
A summary of the testimonies is included here:
TALKEETNA -'Roberta Sheldon:
•Acres American,Inc.Plan of Study appears
superior to previous Corps plans of study
•concern for objectivity of Alaska Power Authority
•concern for objectivity of public participation
program
•concern for potential impacts of industrial growth
associated with Susitna
•request that Talkeetna and other communities be
included in recreation survey to be conducted by
Acres American,Inc.
•request that H area residents impacted by dam"be
included in list of groups addressed in the public
participation program
•request that transmission corridor assessment
include impact on open-to-entry property owners
•request that Plan of Study include sociocultural
analysis of Talkeetna area
WASILLA -Michael Bronson:
•concern that environmental and social criteria be
used in combination with cost information in
PUBLIC COMMENT PERIOD.
ACTION SYSTEM.MEETING SUMMARY
8
{~"",--·~l
-~-'-::--~-I----~.~~I
I
1-=1Io,~,_-~___._-JI__~
l ---------
Written com-
ments sub-
mitted during
public commenl
period none
*The same basic format wasfollowed at ail the meetings but was
adapted to the size ofthe audience and to the community.Wasilla's
meeting operated as a group ofthe whole and did not include
indiyidual table top discussions.
23 26
79
27
1 person
14 groups
Anchorage
78 comments
•
*
37
37
none
Wasilla
2 groups
Talkeetna
23 26
I person none
II groups
Fairbanks
79 comments 25 comments
Number of
table top
discussion
groups
Number of
written com-
ments from
table top
discussions
Number of
written ques-
tions receive(!
Number of
written
questions
responded to
Verbal com·
ments given
during public
comment
period
The Action System was
introduced to the public
during the week of the
community meetings.
Essentially this is a method for
insuring that all questions or
concerns raised by the public
get a written response from
the AlaSka Power Authority and from Acres American,
Inc.At the meetings,time did not allow adequate or full
answers to all questions.An easy-to-use form was
distributed at the meeting and people were encouraged to
use it to get additional infonnation.As of the writing of
this report,over a hundred individual questions and
concerns have been received by the Alaska Power
Authority.Responses to these are being individually
prepared and sent to the author of each request.The
content of the Action System comments will be regularly
summarized in future reports by the Public Participation
office.
Talkeetna community meeting
...-
r
ROLE OF THE ALASKA
POWER AUTHORITY,THE
STATE LEGISLATURE AND
THE GOVERNOR
During the 1970's the federal government studied the
feasibility of Susitna hydroelectric development through
the U.S.Anny Corps of Engineers.
In 1978 Alaska's congressional delegation advised the
state of Alaska to consider its own sponsorship of the
Susitna project because of the political climate in
Washington D.C.It did not appear that any major
hydroelectric project in Alaska would be funded with
federal dollars.
The Alaska Power Authority is a state corporation
and is the vehicle set up by the state to conduct feasibility
studies and to finance and construct electrical power
projects.Policy is set by a five-member Board of Directors
appointed by the governor.The Authority has a staff of
eleven,including an Executive Director,a Director of
Finance,a Director of Engineering,and a Director of
Public Participation.
Through the Alaska Power Authority Board,pre-
liminary reports will be sent to the governor and the
legislature.The first is due March 30,1981,and the second
is due April 30,1982.Both reports will recommend
whether to continue studies on Susitna and the other viable
alternati ves.
Additionally,the Power Authority will:
-manage the public participation process.
-monitor the work of Acres American,Inc.on
all Susitna feasibility studies except the alterna-
tives study (this will be conducted by an
independent contractor and be managed by the
Office ofthe Governor).
-submit a license application to the Federal
Energy Regulatory Commission if Susitna
hydroelectric development is selected as the
most feasible and desirable alternative.
-recommend a financing plan and sell bonds if
bonds are a part 0 f the fmancing plan.
What is the role of the legislature and the governor?
The legislature funds all studies and oversees the study
process.The governor manages the alternatives study,and
acts to accept,reject,or modify the recommendations
from the Power Authority Board in selecting the most
feasible and desirable way to meet future electrical needs.
One of the roles of the Alaska Power Authority is to manage the public
panicipalion program.as seen at the Fairbanks community meeting.
I
9
,
WHY ACRES AMERICAN,INC.
WAS SELECTED TO CONDUCT
THE SUSITNA FEASIBILITY
STUDIES
At its November 1979 meeting,the Alaska Power
Author,ity Board selected Acres American,Inc.to conduct
Susitna feasibility studies.Comments from the public were
included in this selection as were comments received from
the House Power Alternatives Study Committee.Both the
public comments and the House Power Alternatives Study
Committee supported the choice of Acres American,Inc.
Here is a summary of the reasons:
1.Acres American,Inc.possessed th e greatest experience
with sub-Arctic construction and planned to retain the
most experienced firm in Alaska for geotechnical work.
2.Acres American,Inc.planned to spend a greater
portion of its budget in-state than other firms.
3.The Acres American,Inc.proposal contained the most
objective and detailed studies of power market demand
and power alternatives.
4.The Acres American,Inc.proposal provided for the
most extensive and direct public participation process.
Chuck Debelius and John Lawrence,Acres American.Inc.
10
WHO THE DECISION
MAKERS ARE ..•
The Alaska Power Authority Board will make two
preliminary reports to the governor and the legislature.
The reports will be based on Acres American,Inc.'s work,
on the work of the alternatives study,and on public input.
The first report is due March 30,1981,and will
recommend whether studies should continue on the
Susitna hydroelectric project.If the recommendation is
that study should continue,the report shall explain the
following in detail:economic evaluations and preliminary
environmental impact assessments for the Susitna
Current members of the Alaska Power Authority Board are:(left to right)
Charles Conway,Chairman (Sitka):Arnold Espe,Vice Chairman (Anchorage);
Commissioner Charles Webber,Department of Commerce and Economic
Development,member (Juneau);Roben Weeden,member (Fairbanks);and
Tom Kelly,member (Anchorage).
hydroelectric development and aU viable alternatives;a
description of the federal and state permits needed before
construction can begin;and the expected construction start
date.
The second report is due April 30,1982 and shall
again recommend if work should continue on the Susitna
project and other viable alternatives.If the recommenda-
tion is to continue Susitna studies,the report will give more
detail on design,on phases of construction,expected
completion dates of each phase of construction,expected
costs of each phase,and the costs to the state and to the
consumers of the project under different methods of
project financing (including revenue bonds,general
obligation bonds and general fund appropriations).
Governor Hammond
II
,
II.SUMMARY OF
I
WHAT THE
PUBLIC SAID
8 MAJOR CONCERNS
The following areas received the most comments during
the table top discussions:
15 comments saying Plan of Study adequate.
29 comments saying alternatives study not adequate
and why.
25 suggestions for energy sources that should be
considered in alternatives study.
17 suggestions for serious consideration of decentralized
alternatives.
17 comments describing what the socioeconomic studies
should address.
11 comments suggesting a level of effort on studies on
fish,wildlife and plants.
8 comments describing concerns about transmission
studies.
8 suggestions for getting information to the public.
THE 8 MOST ASKED
QUESTIONS
Written questions were asked most often in the following
areas (listed in rank order):
27 questions expressing concern for completeness of
alternatives study
13 questions on adequacy of energy forecasts
11 questions on objectivity of those conducting the
alternatives study
10 questions on the decision making process andthe
timing of decisions
10 questions on construction costs and schedules
8 questions on marketing and financing of Susitna
7 questions on access roads to damsites
7 questions on local hire in feasibility studies
3
12
TABLE TOP DISCUSSION
SUMMARY
j,
QUESTION AND ANSWER
SUMMARY
This chart summarizes the total number of table top This chart shows how many questions were asked about
comments received on the adequacy of the Plan of Study.each TASK in the Plan of Study.
#of %of #of %of
comments total questions total
Plan of Study 29 16%asked questions
Task 1:Power Studies 84 46%Plan of Study 5 3%
Task 2:Surveys and Site Facilities none -0-Task 1:Power Studies 79 48%
Task 3:Hydrology 7 4%Task 2:Surveys and Site Facilities 9 6%
Task 4:Seismic 4 2%Task 3:Hydrology 2 1%
Task 5:Geotechnical none -0-Task 4:Seismic 7 4%
Task 6:Design Development 2 'h%Task 5:Geotechnical 2 1%
Task 7:Environmental 30 17%Task 6:Design Development 7 40/0
Task 8:Transmission 8 4%Task 7:Environmental 9 6%
Task 9:Construction Costs and Task 8:Transmission 5 3%
Schedules
I
none -0-Task 9:Construction Costs and
Task 10:Licensing none -0-Schedules 13 8%
Task 11:Marketing and Financing 4 2%Task 10:Licensing 1 les~than 1%
Task 12:Public Participation 14 8%Task 11:Marketing and Financing 8 5%----
TOTALS 182 100%Task 12:Public Participation 6 4%
Miscellaneous 12 7%----
TOTALS 165 100%
13
~--~t -~,~,--''''''''~$Zf'Wfff£Jfw~,",+,,,,,"",,,r,'C6,"-,,'~~·;tK'-Swm,,.,;''''',=i'''''''~#11:j;m~7'"'';;7,·:;;:;.---;q;;:;;;_:::~:,.-;:,::;;~;;.';;';:;;;;;;;;~
,
III.EVALUATION
OF THE MEETINGS
The following is a summary of the evaluations filled out by
those attending all four community meetings.
HOW UNDERSTANDABLE WAS
EACH OF THE THREE
PRESENTATIONS?(statistical averages)
1.Is the handout on the overall decision-making process
clear enough to understand without a verbal
description?
85070 yes
15070 no
2.Are the proposed methods for responding to public
comments and questions adequate?
70070 yes
10070 tentative yes/perhaps/somewhat
11070 no
9070 other
100070 TOTAL
14
C..Public Participation Program (description by Nancy
Blunck,Alaska Power Authority)
A.Plan of Study (first slide show by Acres American,
Inc.)
B.Selection Process and List of Alternatives (second
slide show by Robert Mohn,Alaska Power Authority)
terribly
oonfu~q I 2 3 4 5 6
terribly
confusing I 2 3 4 5 6
terribly
confusing I 2 3 4 5 6 7
very
8 9 10 understandable
very
8 9 10 understandable
very
9 10 understandable
3.Anything else we could be doing to get information
to the public?
Mentioned the most ....USE OF TELEVISION
(mentioned 19 times).
Second USE OF NEWSPAPERS
(mentioned 10 times).
Third EXPAND MAILING LIST
AND MAIL IN ADVANCE
(mentioned 7 times).
NOTE:"use of television"was most often mentioned in
Anchorage and Fairbanks,but was also mentioned
in Talkeetna and Wasilla.
4.Other comments:
There were 33 comments on the meeting format.About
75070 (24 comments)said that the table top discussions
were very effective.Other issues appeared only once or
twice.
~
Members of the public evaluate the content and design of the Talkeetna meeting.
15
J
16
The purpose of the public participation program is the incorporation of citizen
ideas into the feasibility study ...that's what happens in the NEXT STEP.
Wasilla community meeting
~--------------...-t-------
IV.THE NEXT STEP
The 1980 Legislature appropriated an additional
$1,365,000 to make changes in the Plan of Study.The
revised plan was prepared by the Alaska Power Authority
and Acres American,Inc.It reflected the suggestions for
change from the public at the community meetings,from
consultants to the House Power Alternatives Study
Committee,and from state and federal agency review of
the Plan of Study..
The major suggested alterations in the alternatives
study are summarized below:
-change the time frame for decision making and
stretch it over an additional year
-increase the work allotted to identification and
description of power alternatives,including
conservation and load management
-present a number of alternative power plans for
public review during the second year
-augment the demand forecast data base
-increase the level of effort allotted to financial
and marketing aspects of the alternatives,and to
risk analyses
-utilize a multidisciplinary review panel
-increase the environmental studies of alternatives
-conduct a more complete sensitivity analysis.
Additionally,the Office of the Governor is now
overseeing the alternatives study.An independent firm will
be hired to conduct the alternatives study,and this effort
will be entirely separate from the Acres American,Inc.
work on Susitna feasibility.
.1
17
,
~WHAT HAPPENS
TO THtS REPORT?
-';.,
Several things:
1.Acres American,Inc.,their subcontractors,the Alaska
Power Authority,and the Alaska Power Authority
Board will have copies of this report so they are aware
of the concerns expressed and so they can assure that
the studies are responsive to the concerns.
2.The Federal Energy Regulatory Commission will have
this report to assist them in their determination of the
adequacy of the public participation program:how was
the public encouraged to participate and how were their
comments incorporated into the study process?
3.This report is the first of several documents that will be
the major part of the Public Participation Director's
report to the governor and to the Alaska Power
Authority Board prior to decision making on Susitna.
(Also included in the report will be the reportsjrom
juture meetings,workshops and ACTION list
comments.)
4.This report will help form the agenda for future
workshops.The Public Participation office has kept
track of those questions that were asked most
frequently and those questions that were not adequately
answered at the first set of meetings.
5.The Public Participation office will use this report to
help plan the agenda for the next series of community
meetings in 1981.
6.Communities will have the opportunity to see what
concerns other communities had.The table top discus-
sion comments and the questions are identified by
community for comparison purposes.
7.This report will go to the Office of the Governor with
the hope that it will be used in the conduct of the new
alternatives study.
8.Others to receive this report:
-public libraries within the railbelt region
-commercial fishing groups -sportsmen's groups
-general public interest -environmental groups
groups -energy groups
-recreation groups -mining groups
-business groups -individuals upon
-media request
18
L
APPENDIX A:COMPLETE LIST OF
TABLE TOP DISCUSSION COMMENTS
Following is a complete list of table top discussion comments received.They are organized by TASK in the same
manner as the original Plan of Study document.
,
19
COMMENTS ON PLAN OF STUDY 20
Plan of Study considered adequate.
Plan of Study adequate only if studies completed properly.
Plan of Study more than adequate.
Enough studies have been done already-build Susitna now.
Studies are an improvement over previous studies.
People conducting studies appear to be open and objective.
TOTAL
1
Plan of Study-
adequate
Plan of Study-
difficult to under-
stand and evaluate
Studies difficult to evaluate without knowing how studies will
be done.
Plan of Study should indicate more clearly what its priorities are.
Plan of Study difficult to understand:break into smaller parts.
TOTAL
Plan of Study-
comments on scope
of work
Plan of Study should include previous studies done by Corps
of Engineers.
Studies too broad,costly and are difficult to complete in
time allowed.
TOTAL
Plan of Study-
assumptions
questioned
-3
Plan of Study appears to assume that railbelt people would favor
converting to electric heat.
Plan of Study appears to assume that we should be meeting future
energy demands.
Plan of Study appears to assume that hydro is best and
only solution.
TOTAL
airbanks 11keetna nchorage
TASKl
mllm~
IIfJ!;1D POWER STUDIES
•determine the need for power generation facilities in the railbelt
•consider and evaluate all viable alternatives for satisfying the need
AD EQUA CY:113 comments on adequacy of power studies:
alternatives study-
not adequate
Alternatives studies not adequate.
Criteria for evaluating alternatives appears vague and too
mechanical.Specific concerns raised for evaluating
alternatives were:
....Will cost outweigh socioeconomic values?
....Will value of Alaska's wilderness be given any weight?
....Will "emotional public sentiment"outweigh economic
considerations?
Not enough money for alternatives studies.
Acres American,Inc.experience and objectivity questioned.
Not enough time to do adequate alternatives studies.
Only "legitimate"alternatives should be considered.
TOTAL
('\"
,
lMairbanks .alkeetna IInchorage continued 21
I
power studies,continued.
alternatives study-
suggestions
centralization versus
decentralization
Alternatives study should include CONSERVATION,both
voluntary and government enforced.
Alternatives study should include SMALL HYDROELECTRIC
development.
Alternatives study should include TIDAL.
Alternatives study should include SOLAR.
Alternatives study should include BURNING WOOD TO
GENERATE ELECTRICITY.
Alternatives study should include GEOTHERMAL near
Devils Canyon.
Alternatives study should include North Slope NATURAL GAS
via pipeline.
Alternatives study should include BELUGA COAL.
Alternatives study should include NUCLEAR.
Alternatives study should incorporate new technologies as
they develop.
Alternatives study should take into consideration some kind of
overall energy plan.
TOTAL
Alternatives study should consider decentralized alternatives to
Susitna hydro;8 of 15 comments suggested studying various
combinations of decentralized alternatives.
Alternatives study should evaluate vulnerability of centralized
power source.
TOTAL
continued
•
22
power studies,continued.
energy forecasts-
suggestions
power costs
Load forecasts should identify seasonal variations as well as
daily variations.
Power studies should anticipate the effects of public reaction to
increasing cost of energy and public desire to reduce
energy consumption.
Demand forecast should include possible electrification of Alaska
Railroad.
Load forecasts should provide for auxiliary back-up power in
addition to main power supply.
TOTAL
Studies should show how much of Susitna costs will be paid
by consumer.
Studies should compare consumer costs of Susitna relative to
other alternatives.
Studies should consider ways to lower power costs.
Studies should show how the most economic power production
is determined.
TOTAL
I
energy
independence
decision making
Studies should evaluate possibility of selecting a power plan that
would achieve energy independence.
TOTAL
Plan of Study should allow flexibility of decision making.
TOTAL
airbanks alkeetna nchorage continued 23
,
power studies,continued.
QUESTIONS:
VALUES:
pro Susitna
against Susitna
four questions on power studies in table top reports:
-What kinds of power (other than hydro)will be available in the future?(Talkeetna)
-Looking beyond current technologies,what alternatives sources can be expected in the
near future?
-If natural gas generators are to be prohibited in the future and!or fossil fuels become
prohibitively costly,what would be the alternatives or how much power would be
available without the use of hydropower-in the next 20 years?(Talkeetna)
-When will the Golden Valley Electric Association be bringing on capacity from the oil
pipeline stations (the waste heat power project)?(Fairbanks)
27 values expressed on power studies during table top discussions:
-I am in favor of it.(Fairbanks)
-Agree that it is a good project.(Fairbanks)
-Get going with project.(Anchorage)
-Build the dam first,then develop alternatives.(Fairbanks)
-Susitna is good,long term energy supplier.(Fairbanks)
-Project is environmentally desirable and inflation proof.(Fairbanks)
-Build dam now before costs are too high.(Fairbanks)
-Susitna is large in cost,but not in capacity.It is less affected by inflation.(Fairbanks)
-Feel that we lost out by not getting Rampart Dam-cost of energy will be too high if
dam isn't built.(Fairbanks)
-Opposed to dam. (Fairbanks)
-Is Susitna a dinosaur egg that we'll be sorry we hatched?(Anchorage)
-For the $3 billion cost of Susitna project,with existing technology,distribution of that
amount on a per capita ($10,000 per person)basis should be considered to reduce
consumption and eliminate need for more generation capacity.(Anchorage)
continued
24
power studies.continued.
pro hydro
alternatives study
power costs
opposed to centralized
power sources
-In the presence of a shortage of energy,we shouldn't question hydro.(Anchorage)
-Hydro should be used by those who have access to the renewable resource;the fossils
should be saved for those who don't have hydro potential.(Anchorage)
-Alaska does have hydro potential;it's clean and we should use it.(Fairbanks)
-Stationary energy requirements should be supplied by large hydro in preference to using
coal.(Fairbanks)
-Hydro is the only form of energy other than nuclear that we could look to for the long
term.(Fairbanks)
-"The water is all running down hill
-Better get at it-
The gas we can sell;water we can't.
Never seen a hydroproject blow up-just get wet."(25-year Alaskan;Anchorage)
-No need to study nuclear.(Anchorage)
-Conservation should be a priority in any projection of needs,as Alaska has a uniquely
large potential for saving in that area.(Anchorage)
-Conservation is less costly than building new project.(Fairbanks)
-Should not consider heating homes with electricity-not efficient.(Anchorage)
-Reason for developing new energy sources should be lower cost of energy,not
attracting new industry.(Talkeetna)
-Fairbanks pays a lot for electricity.(Fairbanks)
-Opposed to centralization of energy sources.(Fairbanks)
-Opposed to government controlled centralization of energy sources.(Fairbanks)
!
25
TASK 2
A
-A~A.
SURVEYS AND SITE
FACILITIES
26
,
•provide safe,cost effective and environmentally acceptable logistical support for the feasibility studies
•conduct topographic surveys of the project area
•resolve real estate issues
ADEQUACY:no table top comments received on adequacy of this section of Plan of Study.
QUESTIONS:
VALUES:
three questions included in table top reports:
-Will native lands around dams be purchased at unreasonable prices?(Fairbanks,twice)
-Who owns the land at dam sites?(Fairbanks)
-Will any federal land withdrawals delay dam?(Fairbanks)
no values expressed about the work to be done in this section of the Plan of Study.
TASK 3 HYDROLOGY
•collect data and perform analysis for the hydrologic,hydraulic,ice and climatic factors in project
planning and design
AD EQUA CY:seven comments on adequacy of hydrology studies:
Studies should examine effects of large reservoirs on climate.
Studies should examine silting problems both behind dam and in
river.
Studies should determine effects of ice break-up on Susitna.
TOTAL
QUESTIONS:
VALUES:
no questions on hydrology included in table top reports.
no values expressed about the work to be done in the hydrology section of the
Plan of Study.
airbanks alkeetna ITlchorage 27
TASK 4 SEISMIC STUDIES
28
•assess seismic potential of Susitna basin
•determine seismic design criteria
•evaluate seismic stability of project structures
•'assess the potential for reservoir-induced seismicity and landslides
ADEQUACY:four comments on adequacy of seismic studies:
Studies should include extensive seismic analysis which would
continue after June 1982.
Studies should evaluate reliability of current knowledge about
the effects of large reservoirs on highly seismic areas.
TOTAL
QUESTIONS:
VALUES:
no questions on seismic studies included in table top reports.
no values expressed about the work to be done in the seismic section of the
Plan of Studies.
airbanks alkeetna nchorage
TASKS ~~
~,.
t)
.'
GEOTECHNICAL
EXPLORATION
•determine the surface and subsurface geology and geotechnical conditions of the project sites
ADEQ UA CY:no table top comments received on adequacy of this section of Plan of Study.
QUESTIONS:
VALUES:
no questions on geotechnical exploration included in table top reports.
no values expressed about the work to be done in the geotechnical section of the
Plan of Studies.
,~,.
,
29
TASK 6 DESIGN
DEVELOPMENT
30
•prepare the optimal plan for Susitna hydroelectric development (includes whether tunnel or dam,
,number of dams,types,where,size and timing of development if staged)
•prepare preliminary engineering and design information for the selected development plan
ADEQUACY:two comments on adequacy of design development studies:
Studies should identify appropriate minimum levels of stream
flow during filling of reservoir.
TOTAL
QUESTIONS:
VALUES:
three questions included in table top reports:
-How much voltage will be produced by the dam?(Talkeetna)
-What impacts would there be on railbelt communities if there was a major breakdown
of Susitna hydro while it was on the line at -60 degrees?(Talkeetna)
-What is the life span of the dam project?(Fairbanks)
no values expressed about the work to be done in the design development studies.
Flairbanks alkeetna 'nchorage
TASK 7 ENVIRONMENTAL
STUDIES
•collect baseline data
•compare alternative plans from an environmental standpoint
•assess the socioeconomic,archaeological,historical,land use,recreational,water resource,fish,
wildlife,and plant ecology impacts of Susitna development
ADEQUACY:thirty comments on adequacy of environmental studies.
socioeconomic
irbanks alkeetna nchorage
Socioeconomic studies should address goals of railbelt.
Studies should consider socioeconomic effects of Susitna hydro
on railbelt communities.
Specific concerns mentioned were:
-Will the rate of inflation increase like it did during
pipeline days?
-What will the effects of new industrial development be?
TOTAL
continued 31
environmental studies,continued.
impact on fish,
wildlife,plants
environmental
trade-offs
u
Studies should consider impact of fish populations in Susitna
River and its tributaries.
Studies should be more thorough and include inventory of plant
and animal resources.
Studies should continue for at least one normal animal cycle (a
hare cycle is plus or minus ten years).
Studies should consider impact on moose and caribou,
particularly in Susitna flat estuary and Beluga calving
grounds.
TOTAL
Studies should establish guidelines for acceptable environmental
tradeoffs.
TOTAL
32
Susitna as navigable
river
;1',Studies should evaluate Susitna as a navigable river.
TOTAL
QUESTIONS:
VALUES:
wilderness
industrialization
preserve river as
natural system
no environmental questions asked during table top discussions.
three values expressed related to environmental studies:
Alaska has plenty of wilderness areas.(Fairbanks)
Opposed to industrialization-keep things the way they are.(Fairbanks)
Susitna is a beautiful,unique river.(Fairbanks)
F'ltirbanks Tallceetna Alnchorage
TASK 8 TRANSMISSION
•select the transmission route
•produce conceptual designs for transmission facilities
AD EQ UA CY:eight comments on adequacy of transmission studies:
Studies should examine negative aspects of intertie.
Studies should identify health hazards of living near transmission
lines.
Studies should examine best routes for transmission lines.
(NOTE:"best route"not defined at meetings.)
Design of transmission lines should accommodate transmission
of electricity from variety of sources.
TOTAL
QUESTIONS:
VALUES:
three questions included in table top reports:
-Can you live near transmission lines and not receive power?(Talkeetna)
-Why does there need to be new transmission lines if there's already a connecting
power line from North Pole to Homer?(Talkeetna)
-Will Cantwell be bypassed?(Fairbanks)
two values expressed during table top discussions:
-Build intertie now.(Fairbanks,three times)
-Recommend putting transmission lines along highway and not along railroad-too
many people live along railroad.(Talkeetna)
airbanks alkeetna nchorage
33
TASK 9 CONSTRUCTION COST
ESTIMATES AND
SCHEDULES
34
•develop cost estimates for the Susitna project
•prepare detailed engineering and construction schedules
•conduct risk analysis of all possible things that could affect cost overruns
ADEQUA CY:no table top comments received on adequacy of this section of Plan of Study.
QUESTIONS:
VALUES:
one question included in table top reports:
-Is there a minimum acceptable benefit/cost ratio that will permit construction of the
project?Will cost overruns be somehow included in contingency factor?(Anchorage)
no values expressed about the work to be done in this section of the Plan of Study.
TASK 10 LICENSING
•prepare and assemble all documentation for the license application to the Federal Energy Regulatory
Commission (FERC)
ADEQ UA CY:no table top comments received on adequacy of this section of Plan of Study,
QUESTIONS:
VALUES:
one question included in table top reports:
-If the state of Alaska funded a significant (major)portion of this project,would federal
environmental guidelines need to be followed and met?(Anchorage)
one value expressed during table top discussions:
-Our consensus is that federal intervention is necessary to speed up the time frame of the
project-to save real dollars and eliminate possible brownout.(Anchorage)
'\',
.)'~
,
35
TASK 11 t-.,MARKETING AND
FINANCING
36
•assess methods of financing the Susitna project
•,prepare draft support documentation for bond offering,including risk analysis
ADEQUACY:four comments on adequacy of marketing and financing studies:
o 0
o
Studies should determine costs of Susitna hydroelectric
development.
Studies should determine whether or not Susitna project is
economically feasible in a traditional sense (without big
state inputs).
Studies should evaluate whether state can afford to finance both
gas pipeline and Susitna hydro.
Financial studies should be delayed until conclusion of all
other studies.
TOTAL
QUESTIONS:
VALUES:
no questions on marketing and financing included in table top reports.
no values expressed about the work to be done in the marketing and financing
section of the Plan of Study.
airbanks alkeetna 'chorage
TASK 12 PUBLIC
PARTICIPATION
•keep the public fully informed of plans,progress and findings
•provide a means whereby the public can influence the course of the work
ADEQUACY:fourteen comments on adequacy of public participation program:
information to the
public
input/rom the
public
Need to educate public better.Suggestions included T.V.,radio,
attending community council meetings,using shopping
center displays,and finding ways to reach persons who are
unable to attend meetings (such as those in Pioneer Home).
Preliminary reports should be available to public prior to
community meetings and decision times.
Final reports should be concise and easy to read.
TOTAL
Public needs more input-more time to speak at meetings.
Public needs to know how their comments influence decisions;
2 or 3 comments expressed doubt that public comment has
any affect on decisions.
TOTAL
irbanks alkeetna nchorage continued 37
,
public participation,continued
QUESTIONS:
VALUES:
one question on the publIc participation program included in table top reports:
...,....Will the issue be brought up to a public vote?Possibility of making it so?(Fairbanks)
five values expressed about the public participation program:
-Governor appoints Alaska Power Authority Board,yet input of Acres and public goes
to Board.(Talkeetna)
-Four comments were included on the April 1980 community meetings:
-Slide shows should have more numbers,fewer cartoons.(Fairbanks)
-Slide show was clear,informative.(Fairbanks)
-Rather than break for table top discussions,would have preferred you continue
with written questions.(Anchorage)
-The handout on alternatives did not emphasize alternatives enough.
(Anchorage)
38
APPENDIX B:COMPLETE LIST OF
QUESTIONS
Following is a complete list of written questions submitted at the meetings.They are organized by TASK in the same
manner as the original Plan of Study document.
I
39
__"""",,,,,-··,=..~,~,,.~'••·'.·=~aoc;.-·..c ..••:;:;_"...""..~....;:,;:"."7",,,,-,";Z=:;;:;:u"'".c:'.!="L
1
~_-
~.".~.
t1Yl:IRCH.-r.Y<"C
""O~"l:T
~
LllIJ._..~
1
use of past data
,GENERAL QUESTIONS ON THE
PLAN OF STUDY
1.What's become of past data?Is it available?Will it be used?(Wasilla)
2.What additional information could possibly be needed after all the work that's been
done?(Wasilla)
40
cost of feasibility
studies
exchange of
information
1.What is the total amount of the contract with Acres American,Inc.?(Anchorage)
1.Are there any avenues for exchange of information between Acres American,Inc.and
engineering firms which have completed large earth or concrete dams in other
Arctic locations-such as in Scandinavia or Siberia?(Talkeetna)
UNANSWERED QUESTION (in Anchorage this was not answered because of time and the very large number of written questions
submitted)
title of plan of study 1.Doesn't the title of the project,"Hydroelectric Feasibility Study,"give the false assumption on the part
of the general public that the study is not on all or many different power alternatives?Why was it
named this?
TASKl
mr:lm~
IIgQD POWER STUDIES
•determine the need for power generation facilities in the railbelt
•consider and evaluate all viable altematives for satisfying the need
general on
alternatives
budget for
alternatives
who is studying
alternatives?
1.Can you outline top three alternatives?(Wasilla)
2.Will anybody evaluate employment opportunities provided by different alternatives,
both immediate and long term?(Fairbanks)
1.How much money is in the budget for alternatives?(Talkeetna)
2.How much money is being spent on Susitna feasibility study?By contrast,how much
is being spent on the alternative feasibility studies?(Anchorage)
3.How much ofthe study plan's budget will be spent on identifying and evaluating
alternatives?What percentage?(Fairbanks)
1.Who exactly is studying alternatives to Susitna?(Talkeetna)
2.Please clarify who is doing the alternatives investigation and when results will be
available?(Anchorage)
continued
i
41
power studies,continued.,._,-
,
decentralized vs.
centralized power
Susitna hydro
how Susitna power
used
other hydro
1.Will Category 'B'on the lavender sheet attempt to quantify and/or compare the risks
(costs and otherwise)of a centralized source of power as opposed to decentralized
sources?Will this take into account the cost of necessary backup (standby)
systems?(Anchorage)
2.Considering the immensity and high cost of this project and the favorability of local
decentralized power sources (wind and solar),what kind of assurance can you
give that these alternatives will receive proper consideration?(Fairbanks)
1.Is there really an alternative better than Susitna?No need to look at alternatives.
(Wasilla)
1.What are the uses envisioned for Susitna electricity?Space heat for residences,
industry,transportation?(Anchorage)
2.What is the purpose of the Susitna project?To provide power for increased
population?residential use?provide power for industrial development and
expansion?to create jobs?other?(Anchorage)
3.Would you anticipate total electrification of the railbelt area,Le.power substations
for smaller communities which are currently without commercial electricity?
(Fairbanks)
1.Will Acres American,Inc.evaluate the 64 potential hydro sites identified by the
federal government in southcentral and interior Alaska?In what detail?
(Fairbanks)
2.What are other possible hydro sites (outside the railbelt)?(Wasilla)
3.What other hydro sites are being studied?(Talkeetna)
42
tidal 1.Is tidal power feasible for Anchorage?(Talkeetna)
2.Is the Cook Inlet tidal power project an alternative which could be considered
competitive in cost with Susitna?(Anchorage)continued
power studies,continued.
other alternatives
costs of Susitna to
consumer
1.I understand there are questions concerning the availability of NATURAL GAS.How
long will natural gas from Beluga and the Kenai Peninsula last?(Anchorage)
2.What has been done with the in-state GAS line idea and study of Bonner and Moor?
(Fairbanks)
3.Why is the SOLAR alternative limited to centralized electrical generating units?
(Anchorage)
4.What is the role of SOLAR residential applications (specifically,active and passive
systems in new and existing housing stock)?(Anchorage)
5.With regard to WOOD,will the residential space heat potential be assessed (Le.wood
used in wood stoves as opposed to being burned in a generator)?(Anchorage)
6.Are studies of alternatives limited to a specific geographic area (Le.railbelt)?
GEOTHERMAL may not be a viable alternative for the railbelt but perhaps in
the Copper River basin it would be.(Anchorage)
7.Will CONSERVATION,our #1 alternative,be tested extensively through application
in existing facilities,or alternatively,will more efficient design be considered?
(Anchorage)
8.Among the conservation measures considered,will direct LOAD CONTROL
techniques and innovative rate structures be considered as a means of conserving
generating capacity?(Anchorage)
1.I understand that Susitna power will be equal to $80/barrel of oil.Comment?
(Fairbanks)
2.Whatever happened to the Rampart dam proposal?Is Susitna more cost effective?
(Wasilla)
3.Will the Susitna project be economically viable?(Fairbanks)
4.If the federal government won't foot the construction bill,will power from Susitna
(including transmission line costs)cost more than using natural gas in gas turbine,
combined cycle power plants?(Fairbanks)'i
continued
j
43
f
power studies,continued.~
costs of alternatives
to consumer
energy forecasts
how decisions made
1.Do you have any estimated costs on the alternatives'?(Wasilla)
1.What are power use trends in Alaska relative to nationwide trends'?(Wasilla)
2.How have past population and power usage projection figures been formulated'?
(Talkeetna)
3.How will future population and power usage figures be formulated'?(Talkeetna)
4.How are future energy projections determined'?Is social opinion considered in making
these projections'?(Talkeetna)
5.How will we insure that our energy need projections will not be exaggerated'?
(Anchorage)
6.Doesn't a large forecast of energy become a self-fulfilling prophecy and be an
invitation to industry to come in'?(Wasilla)
7.Will the Susitna hydroelectric project produce excess energy'?(Wasilla)
8.If the dam is to provide power for increased population-where are the people going to
come from and what will they be doing'?Hasn't population declined'?
(Anchorage)
9.Are energy load forecasts ready'?Figures ready'?(Wasilla)
10.What is the background for the Institute of Social and Economic Research (ISER)'?Is
it private'?Is it funded'?How long in Alaska'?(Talkeetna)
11.Is anyone from ISER here'?Their demand projections seem crucial and subject to
conscious or unconscious bias.(Fairbanks)
12.ISER mentioned six consumer categories-half were industrial categories.Why the
emphasis on industrial use?(Talkeetna)
1.Will the go/no go decision be made by the legislature or by a general voting
opportunity'?(Anchorage)
2.Will social and environmental factors be a part of the criteria for determining
feasibility,or will cost be the only criteria'?(Wasilla)
continued
44
continued
power studies,continued.
timing of decisions
objectivity of
Acres American
objectivity of
Alaska Power
Authority
1.Why conduct detailed Susitna studies before alternative studies are complete?
(Wasilla)
2.Why aren't considerations of environmental impacts involved in the first go/no go
decision?Necessary environmental studies will not be completed in time for this
important decision.(Fairbanks)
3.Will any decisions regarding Susitna (go/no go)be made before 1982?Or will phase I
study results precede any decision at all?(Fairbanks)
4.Why is the decision schedule so long and drawn out?Considering the vast amount of
studies already done,can't this process be expedited?(Fairbanks)
5.Why is the go-ahead decision being made in February 1981 before the seismic studies
are done?(Talkeetna)
1.Acres American,Inc.seems to have a history of dam building proposals.Therefore I
sense a predisposition to seeing Susitna as the only viable alternative.I would like
Acres American,Inc.to tell in detail what past research they have done on
alternatives to large-scale hydro?Has Acres American,Inc.ever done a study and
decided a dam wasn't the best alternative?(Anchorage)
2.Can Acres American,Inc.be an advocate of such alternatives?(Anchorage)
3.We have seen many impressive slides of hydro projects in which Acres American,Inc.
has been involved.What experience has Acres American,Inc.had in less
imposing alternative energy sources such as solar and retrofitting of energy-saving
alternatives?Have they been advocates for any alternatives?(Anchorage)
4.Acres American,Inc.has done feasibility studies on other dams.What percentage
were actually built?(Talkeetna)
5.Isn't it in the financial interest of Acres American,Inc.to give a 'go'signal at the
go/no go decision point?How can Acres American,Inc.be objective at this
point?Who will review them?(Fairbanks)
6.Question to Acres American,Inc.:based on previous experience,what are the odds as
you estimate them now that the study will be positive for hydro construction?
(Fairbanks)
1.Does the Alaska Power Authority have a vested interest in the project?Le.How would
your agency and you as individuals be affected by cancellation of the project?
(Anchorage)
I
45
power stuaies,continued.>
UNANSWERED QUESTIONS (in Anchorage these were not answered because oftime and the very large number of written questions
submitted)
46
,
general on alternatives
whq is studying
alternatives
decentralized
vs.centralized
how Susitna power to
be used
industrial growth
1.What types of power sources is the APA studying besides hydro?
2.Concerning "parameters for evaluatingalternatives":Where will you look at the (1)environmental
quality and (2)socioeconomic opportunity costs of present or probable future uses of resources
affected?
3.Will assessment of alternatives take into account the "state of the art"in 1990 as well as projected "cost"
or "need"?
1.What sort of experts will be employed in evaluating the alternatives,such as conservation,solar,
and wind?
1.How can the value and advantages of a decentralized system be realistically compared to a centralized
system?A specific area of concern is the reliability of a large centralized system.
I.What is the potential power output of the Susitna project as it is now envisioned?
2.Will the dam meet all of Anchorage area energy needs?
3.For how many years will the Susitna Dam project (assuming Watana and Devils Canyon dams are built)
be sufficient for our energy needs?I understand the Corps did a study showing that the dams will
carry our energy load for only a few years.Then new sources will be needed to supplement.
1.I have heard conflicting justification for the second dam (Watana).Can you clarify what the purpose is
for Watana:either additional storage or for anticipated industrial growth,or something else?
2.Will the dam cause heavy industry?
continued
power studies,continued.
other alternatives
cost of Susitna to
consumer
energy forecasts
how decisions made
timing of decisions
objectivity of Acres
1.Will you clarify passive solar and wood burning for heat?
2.Explain''additional aspects"under wind power on pink page 2 Power Alternatives?
3.To what degree is the possible reduced demand in electricity resulting from alternatively promoting
conservation measures being studied?
4.What consideration is given to economic uses of waste heat from thermal generation plants (industrial,
residential,agricultural,etc.)in the study?
1.How many barrels of oil to produce an equivalent amount of electricity?of coal?
1.Bucky Fuller made a speech in Anchorage in December 1979 and discussed his prediction regarding
Alaska's future.Will these comments be used in your energy forecasting efforts?
1.It appears that alternate energy advocates are continually voicing objection to this and other hydro
projects without credible alternatives.How does the Alaska Power Authority intend to make ajina/
decision determination in order to prevent this project's being its life's work?
1.How much time will there be between completion of the "project overview"and the go/no go decision?
1.Question to Acres American,Inc.-Given the strong political support for the Susitna project,how
seriously do you believe other viable alternatives will be considered?
2.Robert Mohn stated that Acres American,Inc.and Woodward Clyde would study the power alternatives
(i.e.coal~fired generation).Doesn't it seem a conflict since Acres American,Inc.was hired to study
a dam proposal and their experience is designing dams?
i
experience of Acres 1.Aside from hydroelectric projects in the north and elsewhere,what other energy developments has
Acres American,Inc.been in charge ofor involved with?
2.How many coal-fired plants has Acres American,Inc.designed?
if\:
47
TASK 2
A.
-A~A.
T
SURVEYS AND SITE
FACILITIES
48
f
•provide safe,cost effective and environmentally acceptable logistical support for the feasibility studies
•~onduct topographic surveys of the project area
•resolve real estate issues
land ownership
road access
airport access
1.Who owns the land at the dam sites and upriver in the reservoir areas?(Wasilla)
1.What are the probable access routes?primary roads?secondary roads?(Talkeetna)
2.How will route selections for road access be made?(Wasilla)
1.Where would the runway be located and what size would it be?(Wasilla)
UNANSWERED QUESTIONS (in Anchorage these were not answered because oftime and the very large number of written questions
submitted)
road access 1.At what stage of the planning process will a road be built to the construction site?
2.When is actual construction of road access?
3.What about roads and access?
4.If the dam(s)were constructed,how would the workers,officials.and general public gain access to the
site(s)or to any developed recreational facilities or areas?
5.Once the right-of-way for the road has been established,will it be open for public use?
TASK 3 HYDROLOGY
•collect data and perform analysis for the hydrologic,hydraulic,ice and climatic factors in project
planning and design
No questions were asked in Fairbanks,Talkeetna and Wasilla.
UNANSWERED QUESTIONS (in Anchorage these were not answered because oftime and the very large number of written questions
submitted)
I
rl
climate
ice
1.Are there studies on the effects of large reservoirs on climate throughout the Susitna River area?
1.What types of studies are being planned to estimate the impact and problems of potentUiI additional ice
formation and icing problems in the lower reaches of the Susitna River (from Talkeetna to the
mouth)and in Cook Inlet?
",',.
,
49
TASK 4,
C(,,
'.\.
SEISMIC STUDIES
50
•assess seismic potential of Susitna basin
•determine seismic design criteria
•evaluate seismic stability of project structures
•,assess the potential for reservoir-induced seismicity and landslides
,
general
faults
dam failure
1.What will two years of seismic monitoring tell us?(Talkeetna)
2.What is the maximum size quake that would preclude building a dam?(Wasilla)
1.Where does the Susitna fault lie?(Fairbanks)
2.How close is the Susitna fault to the dam sites?(Fairbanks)
3.How would major seismic activity on the Susitna fault affect the dams?(Fairbanks)
1.What would be the consequences if the dam broke?(Wasilla)
UNANSWERED QUESTION (in Anchorage this was not answered because oftime and the very large number of written questions
submitted)
reservoir induced
earthquake
1.How does a large dam induce earthquakes?
TASKS f'.t;~
GEOTECHNICAL
EXPLORATION
--.~_-~~---~-~~~~~-=~.~~_."~~-,~,,~---
•determine the surface and subsurface geology and geotechnical conditions of the project site
I
II,
~~
!,
I,
soils assessment
mineral resource
assessment
1.What soils assessment will be conducted?(Wasilla)
1.Will the Plan of Study undertake detailed mineral resource assessments?Concern
that significant deposits not become inaccessible.(Wasilla)
'\
;...:-,
,f
51
TASK 6
,.".
=l~DESIGN
DEVELOPMENT
52
,
•prepare the optimal plan for Susitna hydroelectric development (includes whether tunnel or dam,
number of dams,types,where,size,and timing of development if staged)
•prepare preliminary engineering and design information for the selected development plan
size of reservoir
employment
potential
tunnel alternative
1.How large would the lake be?(Wasilla)
2.How many miles long would the reservoirs be?(Wasilla)
3.How wide would the reservoir be?(Wasilla)
1.How many people would the dam employ?(Wasilla)
2.What is the maintenance level of employment on the Susitna project?(Wasilla)
1.Explain the tunnel alternative:the cost,time,head,environment.(Fairbanks)
(Head:vertical drop from top of tunnel to bottom of tunnel.)
UNANSWERED QUESTION (in Anchorage this was not answered because oftime and the very large number of written questions
submitted)
how design for ice 1.How do you get power from the dam when the river is frozen?
TASK 7 ENVIRONMENTAL
STUDIES
~_~~~,"<~.c~~__~~··,·_
•collect baseline data
•compare alternative plans from an environmental standpoint
•assess the socioeconomic,archaeological,historical,land use,recreational,water resource,fish,
wildlife,and plant ecology impacts of Susitna development
Talkeetna local hire 1.Will there be more inclusion of local labor in the study?Many skilled,able and willing
are unemployed here.(Talkeetna)
2.I would like to know what efforts are being made toward local hire of workers for this
study?Local hire is good public relations.(Talkeetna)
3.To what extent is Alaskan hire involved in present feasibility work and if it is a go
decision,what process will be used to hire skilled and unskilled laborers?
(Talkeetna)
4.Could a Talkeetna-based job service roster be established on a preferred basis to fill
Acres American,Inc.positions?(Talkeetna)
{
recreational benefits
of lake
1.What possible benefits would the lake have?(Wasilla)
~\',
"y ~
continued S3
environmental studies,cdntimied.
UNANSWERED QUESTIONS (in Anchorage these were not answered because oftime and the very large number of written questions
.submitted)
54
,
environmental
rK objectivity
,~
Alaskan hire
1.The Department of Fish and Game is a state agency and so is the Alaska Power Authority.Both agencies
are subject to the same bureaucratic pressures.Acres American,Inc.has been successful in getting
dams built!Their job is to satisfy licensing requirements.Where does the objectivity for studying
and reporting environmental impact come from?
I.How many Alaskans will be employed?
2.How big a non-Alaskan staff will be working on the plan of study?10070,30%,or 50%?How much of
this report will be done outside the state of Alaska?10%,30%or 50%?
3.How much money will not go directly to Alaskans?
TASK 8 TRANSMISSION
•select the transmission route
•produce conceptual designs for transmission facilities
health impacts
route selection
intertie
1.In the report it stated that "transmission corridors will also be studied for
environmental compatibility."Does this mean that the same type of transmission
lines and towers that are now operating elsewhere will be studied as to the impact
they have on the health of the people who live near them?(Talkeetna)
1.At this time what are alternative transmission corridors?(Talkeetna)
2.Do the transmission corridors encroach upon open-to-entry land in this area?
(Talkeetna)
3.How will transmission route selection be done?(Wasilla)
1.Would an intertie between Anchorage and Fairbanks be of value at this time,before
completion of studies?(Fairbanks)
i
55
TASK ,9 CONSTRUCTION COST
ESTIMATES AND
SCHEDULES
56
,
•develop cost estimates for the Susitna project
•prepare detailed engineering and construction schedules
•conduct risk analysis of aU possible things that could affect cost overruns
costs
timing
transportation for
construction
1.If two dams are constructed,what will be the cost of concrete,rebar,and temporary
damming or channeling of the river?(Fairbanks)
2.SB 295:are these costs an accurate estimate?(Wasilla)
3.In the figure $4.3 billion:have cost overruns been considered?(Wasilla)
4.Have you looked at the pipeline history of cost overruns?(Wasilla)
1.If all goes to plan,when would the first phase of the dam be operational?(Wasilla)
2.When would construction begin?(Anchorage)
1.What kind of transportation would be used for construction activities?(Wasilla)
continued
construction cost estimates and schedules,continued.
UNANSWERED QUESTIONS (in Anchorage these were not answered because oftime and the very large number of written questions
submitted)
costs
timing
fast tracking the Susitna
project
1.How many barrels of oil will it take to build the Susitna dam?
2.What is the present estimated total cost of this project?
3.Aside from the direct cost of studies,what are the costs of escalation during the study period,Le.what
would be the cost of an extra year of studies?
1.Based on long drawn out issuance of a FERC license,when will the first kilowatt of electricity leave the
dam site?
2.Present generating facilities have fairly definite replacement dates.How well does the proposed Susitna
construction schedule fit those replacement schedules?
1.What are the procedures for placing the Susitna hydroelectric development on the federal "fast track"
(the Energy Mobilization Board)assuming one is established?
TASK 10 LICENSING
I
•prepare and assemble all documentation for the license application to the Federal Energy Regulatory
Commission (FERC)
Why FERC review 1.Why does PERC have to review a license application to construct Susitna?(Fairbanks)
57
TASK;II r~t MARKETING AND
FINANCING
58
•assess methods of financing the Susitna project
•'prepare draft support documentation for bond offering t including risk analysis
,
public or private
funds
1.Would public or private entity finance,construct,and operate the Susitna dam?
(Wasilla)
2.What state involvement would there be in the Susitna project?(Wasilla)
UNANSWERED QUESTIONS (in Anchorage these were not answered because oftime and the very large number of written questions
submitted)
financing
ownership of project
1.What are the financing options for the dam (7.50/0 or what?)
2.How will the Susitna project be financed?Bond issue?State sales tax?
3.What would the pro rata share for the federal government be?
4.What would the pro rata share for the state government be?
1.As the project is now proposed,will other utilities have the opportunity for participation as joint owners
or will the project be 100%state funded?
2.Is the Alaska Power Authority willing to allow other utilities to purchase a portion of the total project?
TASK 12 PUBLIC
PARTICIPATION
~---~~..~~--~~~~~~~~.
•keep the public fully informed of plans,progress and findings
•provide a means whereby the public can influence the course of the work
weight given to
public input
future workshops
citizens'advisory
board
1.What weight will be placed on public input in the evaluation process?(Talkeetna)
1.The first workshop was scheduled for May 1980 in the Plan of Study.When is it now
scheduled?Will it be advertised?(Wasilla)
1.Is there an ongoing citizens'review and advisory board or citizens'review of each
independent study?(Anchorage)
UNANSWERED QUESTIONS (in Anchorage these were not ansW'ered because a/time and the very large number a/written questions
submitted)
meeting location
Kenai area public
hearing
1.Why was this meeting held here rather than at a more central location that was more accessible to public
transportation?
1.Why has the Kenai area been eliminated from having its own public hearing?Environmental impacts of
this project on salmon resources may affect the available harvest allocated to this area.
59
Misc.
?•
MISCELLANEOUS QUESTIONS
60
~""
.~.
.t'~
L':;.-
r J
..
''-(,
',,,"
Acres relationship to
Corps of Engineers
how Acres selected
who would build
dam?
who is the Alaska
Power Authority?
who appoints
advisory board?
other
1.What is the relationship between your proposed study and the Environmental Impact
Statement,Upper Susitna River Basin,Southcentral Railbelt Area,Army Corps
of Engineers?(Talkeetna)
2.What is the relationship of Acres American,Inc.to the Corps of Engineers or vice
versa?(Talkeetna)
1.How was Acres American,Inc.selected as the prime consultant for the study?
(Anchorage)
1.Who would build the actual dam if Acres American,Inc.okays feasibility?Would
Acres American,Inc.build it?(Talkeetna)
1.With a change in administration (i.e.governor and legislature)what effect would there
be on the Power Authority?(Fairbanks)
2.By what authority is the Power Authority established?(Wasilla)
3.What is the purpose of the Alaska Power Authority?Why does it exist?(Anchorage)
1.Who will make the appointments to the $1 million Advisory Board?(Anchorage)
1.HB 967-what is MEA's Project?(Wasilla)
2.One slide John Lawrence showed states that manpower of Acres American,Inc.would
peak at 45.This figure seems low.Is it correct?(Anchorage)
UNANSWERED QUESTIONS (in Anchorage these were not answered because oftime and the very large number of written questions
submitted)
1.If additional areas are requested for study by the Alaska Power Authority,Acres American,Inc.will be
paid more money.Is there any chance that payroll could be reduced if the Power Authority weeded
out some of the unnecessary study items?
2.Over the next 10 years,how much money will be spent per year?
Credits
"--"-'--"="'''~-~~-~~~~_._~----_.......--,._....-.---,....._-_._.--.
The following individuals assisted in conducting the community meetings and in the preparation of this report.
Meeting Moderators
Eric Yould,Executive Director,Alaska Power Authority
Robert Mohn,Director of Engineering,Alaska Power Authority
Nancy Blunck,Director of Public Participation,Alaska Power
Authority
Staff Assistance
Al Arnold -Photography
Madeline Holdorf -Verbatim Transcripts and Typing
Alaska Power Authority Board of Directors
Mr.Charles Conway,Chairman Mr.Arnold Espe,Vice Chairman
P.O.Box 520 Alaska Pacific Bank
Sitka,Alaska 99835 Post Office Box 420
Phone:465-2500 Anchorage,Alaska 99510
Phone:276-3110
Acres American staff
John Lawrence,Project Manager
Charles Debelius,Deputy Project Manager
John Hayden,Technical Study Director
James Gill,Manager of Alaska Office
James Landman and Alex Vircol,Power Studies Engineers
t""
&..,
~.g~~
rgf e:
feS'E=
•A)QJ ....
f C':g (IJg...
:fB
~
Fairbanks Meeting Facilitators
Fairbanks League of Women Voters:
Rosemarie Davis Ann Swift
Ruthann Swanson Arlayne Klein
Sue Jones
Talkeetna Meeting Facilitators
Harriet Shaftel and Sharon Zandman
Wasilla Meeting Facilitator
Harriet Shaftel
Anchorage Meeting Facilitators
Anchorage League of Women Voters:
Virginia Breeze Harriet Shaftel
Sharon Richards BarbaraNewell
Molly Crenshaw Mary Bookman
Consultants
Jean Buchanan -Program Development and Evaluation
Sarah Winterburn -Report Design and Graphics
Elizabeth Baldwin -Writing and Editing Assistance
Commissioner Charles Webber,
Department of Commerce &
Economic Development
PouchD
Juneau,Alaska 99811
Phone:465-2500
Mr.Thomas E.Kelly
225 Cordova Street
Anchorage, Alaska 99501
Phone:274-9671
Mr.Robert B.Weeden
203 Bunnel Blvd.
University of Alaska
Fairbanks,Alaska 99701
Phone:479-7095
..#
61
The Public Participation Program ofthe Alaska Power A uthority is funded by the State ofAlaska.
"
PUBLIC PARTICIPATION PROGRAM
;-;ALASKA POWER,AUTHORiTY
333 WEST 4th -SUITE 31 ,.
ANCHORAGE,ALASKA 99501
,'.~
p
f
-<
- I
B9L9C300009~€C3€
1111 IfII 11111 111111111111111 11111 1IIIIiJIIIIIIIIIIIII111IIIIIIIIII~1111111111111
A~V~8n lVll8VH E>i.:lOV
Commissioner Ronald Skoog
AK Dept of Fish and Game
Subport Building
Juneau,Alaska 99801
BULK RATE
u.s.POSTAGE PAID
PERMIT NO.272
ANCH.AK.99502