HomeMy WebLinkAboutAPA2366SOUTHCENTRAL RAILBELT AREA,ALASKA
LIPPER SUSITNA RIVER BASINSUPPLEMENTALFEASIBILITYREPORT
11;::
1-~~S
.5b
!11:3>
JUl 2 5 1980 VlO,23bto
ALASKA RESOURCES LIBRARY
u.s.Department of t"1"',ne fllenor
HYDROELECTRIC POWER AND RELATED PURPOSES
;,~,-,\~"-.i·:,,\C:;Uk cr~·\·
Prepared by the LJi:\;j?,,~~~FORMATjONSE~'/JCh.\
Alaska District,Corps of Engineers.JL'Y....C StREET,SUITE 100DepartmentoftheArmyA!',ir'!·lORi\GE.Au.su 90S03
Februa ry 1979
SOUTHCENTRAL RAILBELT AREA,ALASKA
LIPPER SUSITNA RIVER BASINSUPPLEMENTALFEASIBILITYREPORT
11;::
1-~~S
.5b
!11:3>
JUl 2 5 1980 VlO,23bto
ALASKA RESOURCES LIBRARY
u.s.Department of t"1"',ne fllenor
HYDROELECTRIC POWER AND RELATED PURPOSES
;,~,-,\~"-.i·:,,\C:;Uk cr~·\·
Prepared by the LJi:\;j?,,~~~FORMATjONSE~'/JCh.\
Alaska District,Corps of Engineers.JL'Y....C StREET,SUITE 100DepartmentoftheArmyA!',ir'!·lORi\GE.Au.su 90S03
Februa ry 1979
Resources Development Act of 1976 enacted by the 94th Congress on
22 October 1976,states:
The Secretary of the Army,acting through the
Chief of Engineers,is authorized to undertake the
Phase I design memorandum stage of advanced engineer-
ing and design of the project for hydroelectric power
on the Susitna River,Alaska,in accordance with the
recommendations of the Board of Engineers for Rivers
and Harbors in its report dated June 24,1976,at an
estimated cost $25,000,000.This shall take effect
upon submittal to the Secretary of the Army by the
Chief of Engineers and notification to Congress of
the approval of the Chief of Engineers.
Notification to Congress of the Chief of Engineers'approval has
been forestalled because of Office of Management and Budget (OMB)
reservations regarding economic justification.In a letter to the
Secretary of the Army dated 9 September 1977,Eliot R.Cutler,OMB
Associate Director for Natural Resources,Energy and Science stated,
1I •••we strongly believe further information is needed to verify the
benefit-cost status before the project proceeds to Phase I planning.1I
During 1978,additional geological explorations,engineering and
environmental resource studies,and economic analyses were undertaken
to address the concerns expressed by OMB.This Supplemental Feas"ibility
Report presents the results of those additional investigations.
The report consists of three documents:a main report that responds
specifically to the comments and suggestions offered by OMB and a two
part supporting appendix that is comprised of Sections A through I.
These correspond directly to the sections of Appendix 1 of the 1976
Interim Feasibility Report.This Supplemental Feasibility Report is
i;
..
..'
Resources Development Act of 1976 enacted by the 94th Congress on
22 October 1976,states:
The Secretary of the Army,acting through the
Chief of Engineers,is authorized to undertake the
Phase I design memorandum stage of advanced engineer-
ing and design of the project for hydroelectric power
on the Susitna River,Alaska,in accordance with the
recommendations of the Board of Engineers for Rivers
and Harbors in its report dated June 24,1976,at an
estimated cost $25,000,000.This shall take effect
upon submittal to the Secretary of the Army by the
Chief of Engineers and notification to Congress of
the approval of the Chief of Engineers.
Notification to Congress of the Chief of Engineers'approval has
been forestalled because of Office of Management and Budget (OMB)
reservations regarding economic justification.In a letter to the
Secretary of the Army dated 9 September 1977,Eliot R.Cutler,OMB
Associate Director for Natural Resources,Energy and Science stated,
1I •••we strongly believe further information is needed to verify the
benefit-cost status before the project proceeds to Phase I planning.1I
During 1978,additional geological explorations,engineering and
environmental resource studies,and economic analyses were undertaken
to address the concerns expressed by OMB.This Supplemental Feas"ibility
Report presents the results of those additional investigations.
The report consists of three documents:a main report that responds
specifically to the comments and suggestions offered by OMB and a two
part supporting appendix that is comprised of Sections A through I.
These correspond directly to the sections of Appendix 1 of the 1976
Interim Feasibility Report.This Supplemental Feasibility Report is
i;
..
..'
not designed as a comprehensive document.Rather,only changes to the
original report and new information pertinent to OMB's comments are
presented here.
iii
not designed as a comprehensive document.Rather,only changes to the
original report and new information pertinent to OMB's comments are
presented here.
iii
MAIN REPORT
TABLE OF CONTENTS
Item
SUMMARY
Scope of Investigations
Study Results
WATANA SITE GEOLOGY AND TEST BORINGS
Scope of Geological Investigations
Findings and Design Changes
CONTINGENCY ESTIMATES
AREA REDEVELOPMENT BENEFITS
CONSTRUCTION SCHEDULE
General
Diversion Plans
Main Dams
Effect of Delay
SLlPPL Y ESTIMATES
Introduction
Natural Gas Availability
Oil Price Change Impacts
Anchorage-Fairbanks Intertie
Powerplant Scheduling and Risk Reduction
DEMAND ESTIMATES
Forecast Methodology
Population and Economic Activity Forecast
Forecast Results
Util ity Sector
National Defense Sector
Self-supplied Industries Sector
SENSITIVITY ANALYSIS
Introducti on
Snettisham Review
Implications for Susitna
Current Evaluation
iV
1
1
3
9
9
11
15
18
20
20
20
21
21
24
24
26
28
30
32
34
34
35
36
37
38
39
42
42
42
45
46
MAIN REPORT
TABLE OF CONTENTS
Item
SUMMARY
Scope of Investigations
Study Results
WATANA SITE GEOLOGY AND TEST BORINGS
Scope of Geological Investigations
Findings and Design Changes
CONTINGENCY ESTIMATES
AREA REDEVELOPMENT BENEFITS
CONSTRUCTION SCHEDULE
General
Diversion Plans
Main Dams
Effect of Delay
SLlPPL Y ESTIMATES
Introduction
Natural Gas Availability
Oil Price Change Impacts
Anchorage-Fairbanks Intertie
Powerplant Scheduling and Risk Reduction
DEMAND ESTIMATES
Forecast Methodology
Population and Economic Activity Forecast
Forecast Results
Util ity Sector
National Defense Sector
Self-supplied Industries Sector
SENSITIVITY ANALYSIS
Introducti on
Snettisham Review
Implications for Susitna
Current Evaluation
iV
1
1
3
9
9
11
15
18
20
20
20
21
21
24
24
26
28
30
32
34
34
35
36
37
38
39
42
42
42
45
46
LIST OF PLATES
Number Item
1 Upper Susitna River Basin Selected 2-Dam Plan
2 Watana Damsite Exploration Plan
3 Watana Dam Detail Plan
4 Watana Dam Sections
5 Devil Canyon Dam,Concrete Gravity Dam,Detail Plan
6 Devil Canyon Dam,Concrete Gravity Dam,Elevation
and Sections
APPENDIX
PART I
Section A
Section B -
Section C -
Section D-
Section E -
Section F -
Hydrology
Project Description and Cost Estimates
Power Studies and Economics
Foundations and Materials
Environmental Assessment
Recreational Assessment (no changes)
PART II
Section G
Section H
Section I
-Marketability Analysis
-Transmission System (no changes)
Environmental Assessment for Transmission
System (no changes)
v
LIST OF PLATES
Number Item
1 Upper Susitna River Basin Selected 2-Dam Plan
2 Watana Damsite Exploration Plan
3 Watana Dam Detail Plan
4 Watana Dam Sections
5 Devil Canyon Dam,Concrete Gravity Dam,Detail Plan
6 Devil Canyon Dam,Concrete Gravity Dam,Elevation
and Sections
APPENDIX
PART I
Section A
Section B -
Section C -
Section D-
Section E -
Section F -
Hydrology
Project Description and Cost Estimates
Power Studies and Economics
Foundations and Materials
Environmental Assessment
Recreational Assessment (no changes)
PART II
Section G
Section H
Section I
-Marketability Analysis
-Transmission System (no changes)
Environmental Assessment for Transmission
System (no changes)
v
SUMMARY
SCOPE OF INVESTIGATIONS
The purpose of this supplemental feasibility study was to reevaluate
the economic justification of the proposed upper Susitna River basin
hydropower development (see Plate 1).Both benefits and costs were
reanalyzed in the process of responding to the concerns expressed by
the Office of Management and Budget.Certain additional studies not
specifically suggested by OMS,but required to insure comparability
in the data,were also undertaken.Study efforts were directed at those
aspects of feasibility to which the benefit and cost estimates are most
sensitive.
Project costs are highly dependent upon site foundation conditions,
and a significant amount of new geological information was gathered
during the supplemental studies in 1978.Geological reconnaissance
and mapping were conducted at the Watana damsite to identify and trace
the surface expressions of discontinuities and shear zones,and also
in the reservoir area to identify potential slide hazards.Core borings
were made at the damsite to verify the depth of overburden materials
and quality of bedrock.Potential borrow sources were explored to
determine the extent and quality of available construction materials.
Refraction seismograph studies were performed to supplement the data
gained from the borings and test pits.Refer to Plate 2 for explora-
tion locations as the Watana site.
SUMMARY
SCOPE OF INVESTIGATIONS
The purpose of this supplemental feasibility study was to reevaluate
the economic justification of the proposed upper Susitna River basin
hydropower development (see Plate 1).Both benefits and costs were
reanalyzed in the process of responding to the concerns expressed by
the Office of Management and Budget.Certain additional studies not
specifically suggested by OMS,but required to insure comparability
in the data,were also undertaken.Study efforts were directed at those
aspects of feasibility to which the benefit and cost estimates are most
sensitive.
Project costs are highly dependent upon site foundation conditions,
and a significant amount of new geological information was gathered
during the supplemental studies in 1978.Geological reconnaissance
and mapping were conducted at the Watana damsite to identify and trace
the surface expressions of discontinuities and shear zones,and also
in the reservoir area to identify potential slide hazards.Core borings
were made at the damsite to verify the depth of overburden materials
and quality of bedrock.Potential borrow sources were explored to
determine the extent and quality of available construction materials.
Refraction seismograph studies were performed to supplement the data
gained from the borings and test pits.Refer to Plate 2 for explora-
tion locations as the Watana site.
Supplemental explorations at the Devil Canyon site where drilling
had previously been conducted were limited to three seismic refraction
lines,each approximately 1,100 feet long.
While foundation conditions playa key role in estimating project
costs,those costs are also very dependent upon the contingency factors
used.A feature-by-feature analysis was made to determine the appro-
priate contingency factor on the basis of cost histories of similar
projects,experience in Alaskan construction,and analysis of the un-
certainties associated with the design and material requirements of
the various features.
A third element of the supplemental studies that impacted cost was
the construction schedule.Mobilization,river diversion,and material
placement requirements were closely examined along with the interdepen-
dencies among construction activities to determine the length of time
required for construction.
The newly acquired geological information led to design modifications
which.of course,also affected the cost estimates.
In addition to the factors influencing project costs,there are a
number of determinants of project benefits that were also analyzed.
First,the project's power capability was reexamined using an additional
3 years of historical streamflow data and an updated seasonal load curve.
Load growth forecasts were revised using 3 additional years of histori-
cal data,more sophisticated population and economic activity forecast-
ing tools,and more conservative economic development assumptions.A
2
Supplemental explorations at the Devil Canyon site where drilling
had previously been conducted were limited to three seismic refraction
lines,each approximately 1,100 feet long.
While foundation conditions playa key role in estimating project
costs,those costs are also very dependent upon the contingency factors
used.A feature-by-feature analysis was made to determine the appro-
priate contingency factor on the basis of cost histories of similar
projects,experience in Alaskan construction,and analysis of the un-
certainties associated with the design and material requirements of
the various features.
A third element of the supplemental studies that impacted cost was
the construction schedule.Mobilization,river diversion,and material
placement requirements were closely examined along with the interdepen-
dencies among construction activities to determine the length of time
required for construction.
The newly acquired geological information led to design modifications
which.of course,also affected the cost estimates.
In addition to the factors influencing project costs,there are a
number of determinants of project benefits that were also analyzed.
First,the project's power capability was reexamined using an additional
3 years of historical streamflow data and an updated seasonal load curve.
Load growth forecasts were revised using 3 additional years of histori-
cal data,more sophisticated population and economic activity forecast-
ing tools,and more conservative economic development assumptions.A
2
range of forecasts were made,reflecting the uncertainties involved
in power demand projections.
A load-resource analysis was developed and used to explore the
sequence and timing of powerplant additions for the railbelt area and
to determine how quickly Susitna power would be absorbed into the load.
Power benefit estimates were evaluated using 1978 cost estimates
of thermal generation,the cost of which establishes the value of the
hydropower project1s output.The other categories of benefits,including
load center interconnection,recreation,flood control,and employment,
were also updated.
Finally,a comprehensive sensitivity analysis was conducted to
ascertain those conditions under which the Susitna project would
become uneconomic.This was augmented by a marketability analysis
that estimates the cost of Susitna power relative to thermal generation
under various load growth,timing and price level assumptions.
Other aspects of feasibility which were the subject of supple-
mental analyses included seismicity and environmental impact studies.
STUDY RESULTS
At the Watana damsite,the technical feasibility of constructing a
dam in the general vicinity was reconfirmed.The rock at the damsite
was found to be as good or better than previously assumed.Gravel
borrow appears to be less abundant than anticipated,but large deposits
of impervious material were located during the explorations.To take
advantage of these findings,the dam design was altered by changing
3
range of forecasts were made,reflecting the uncertainties involved
in power demand projections.
A load-resource analysis was developed and used to explore the
sequence and timing of powerplant additions for the railbelt area and
to determine how quickly Susitna power would be absorbed into the load.
Power benefit estimates were evaluated using 1978 cost estimates
of thermal generation,the cost of which establishes the value of the
hydropower project1s output.The other categories of benefits,including
load center interconnection,recreation,flood control,and employment,
were also updated.
Finally,a comprehensive sensitivity analysis was conducted to
ascertain those conditions under which the Susitna project would
become uneconomic.This was augmented by a marketability analysis
that estimates the cost of Susitna power relative to thermal generation
under various load growth,timing and price level assumptions.
Other aspects of feasibility which were the subject of supple-
mental analyses included seismicity and environmental impact studies.
STUDY RESULTS
At the Watana damsite,the technical feasibility of constructing a
dam in the general vicinity was reconfirmed.The rock at the damsite
was found to be as good or better than previously assumed.Gravel
borrow appears to be less abundant than anticipated,but large deposits
of impervious material were located during the explorations.To take
advantage of these findings,the dam design was altered by changing
3
the gravel shells to rock shells and by widening the semipervious core
(see Plates 3 and 4).Other modifications of the original Watana
design included relocation of the spillway to take better advantage
of rock lines,relocation of the diversion tunnel portals to place them
in better rock,terraced rather than continuous rock cuts and other
minor changes.
At Devil Canyon a gravity dam design was evaluated as an alterna-
tive to the original concrete thin arch concept (see P1ates 5 and 6).
The gravity structure,which is more costly but less sensitive to foun-
dation problems,offers greater assurance that a dam can be built at
the Devil Canyon site at a cost equal to or less than the estimated
cost presented in the report.The less costly thin arch dam with
separate spillway will be considered further if additional explorations
during Phase I studies establish acceptable foundation conditions.By
including in the economic analysis the higher cost of the gravity dam,
the project1s economic justification is presented on a more conservative
basis.
The construction period for the entire project is now estimated
at 14 years,with power-on-1ine for the initial phase occurring in
1994.The schedule allows 10 years for Watana construction and 8 years
for Devil Canyon,with 4 years of concurrent construction.The trans-
mission intertie could be available in 1991 to interconnect the Anchorage
and Fairbanks load centers.This schedule is based on a construction
start in October 1984.
4
the gravel shells to rock shells and by widening the semipervious core
(see Plates 3 and 4).Other modifications of the original Watana
design included relocation of the spillway to take better advantage
of rock lines,relocation of the diversion tunnel portals to place them
in better rock,terraced rather than continuous rock cuts and other
minor changes.
At Devil Canyon a gravity dam design was evaluated as an alterna-
tive to the original concrete thin arch concept (see P1ates 5 and 6).
The gravity structure,which is more costly but less sensitive to foun-
dation problems,offers greater assurance that a dam can be built at
the Devil Canyon site at a cost equal to or less than the estimated
cost presented in the report.The less costly thin arch dam with
separate spillway will be considered further if additional explorations
during Phase I studies establish acceptable foundation conditions.By
including in the economic analysis the higher cost of the gravity dam,
the project1s economic justification is presented on a more conservative
basis.
The construction period for the entire project is now estimated
at 14 years,with power-on-1ine for the initial phase occurring in
1994.The schedule allows 10 years for Watana construction and 8 years
for Devil Canyon,with 4 years of concurrent construction.The trans-
mission intertie could be available in 1991 to interconnect the Anchorage
and Fairbanks load centers.This schedule is based on a construction
start in October 1984.
4
The Susitna project is estimated to cost $2.59 billion at October
1978 prices.This includes $1.77 billion for Watana and the transmis-
sion facilities and $0.82 billion for the Devil Canyon phase.The 1978
combined project cost estimate amounts to a 70 percent increase over
the cost estimate presented in the 1976 Interim Feasibility Report,
which was based on January 1975 prices.Approximately 56 percent of
this increase is due to price level changes over the 3-3/4 years between
estimates.Another 15 percent is the result of using the cost of the
alternate concrete gravity design at Devil Canyon.The remainder of
the increase resulted from design changes and more detailed information
on local construction materials.
When interest during construction is added,along with operation,
maintenance and replacement costs,the average annual equivalent cost
becomes $228 million,based on a discount rate of 6-7/8 percent.
The project's combined power output is estimated at 6.9 billion
kilowatt hours average annual energy and 1,392 megawatts dependable
capacity.Rai1be1t area power requirements are forecasted to grow
to 12.7 billion kilowatt hours annual energy and 2,850 megawatts peak
power by the year 2000 according to the medium range projection.
Susitna power would need to be augmented by additional capacity from
other powerp1ants,presumably coal-fired,within 9 years after initial
power-on-1ine.
The estimated average annual benefits of the Susitna project amount
to $324 million.This represents an increase of 119 percent over those
5
The Susitna project is estimated to cost $2.59 billion at October
1978 prices.This includes $1.77 billion for Watana and the transmis-
sion facilities and $0.82 billion for the Devil Canyon phase.The 1978
combined project cost estimate amounts to a 70 percent increase over
the cost estimate presented in the 1976 Interim Feasibility Report,
which was based on January 1975 prices.Approximately 56 percent of
this increase is due to price level changes over the 3-3/4 years between
estimates.Another 15 percent is the result of using the cost of the
alternate concrete gravity design at Devil Canyon.The remainder of
the increase resulted from design changes and more detailed information
on local construction materials.
When interest during construction is added,along with operation,
maintenance and replacement costs,the average annual equivalent cost
becomes $228 million,based on a discount rate of 6-7/8 percent.
The project's combined power output is estimated at 6.9 billion
kilowatt hours average annual energy and 1,392 megawatts dependable
capacity.Rai1be1t area power requirements are forecasted to grow
to 12.7 billion kilowatt hours annual energy and 2,850 megawatts peak
power by the year 2000 according to the medium range projection.
Susitna power would need to be augmented by additional capacity from
other powerp1ants,presumably coal-fired,within 9 years after initial
power-on-1ine.
The estimated average annual benefits of the Susitna project amount
to $324 million.This represents an increase of 119 percent over those
5
presented in the 1976 report.which were based on a January 1975 price
1eve 1.
By far the largest category of benefits is that which results from
the sale of power.The value of the power is derived from the cost of
producing it by means of the least cost nonhydro alternative which,
in this case,is coal-fired generation.The cost of the thermal alter-
native was provided by the Federal Energy Regulatory Commission (FERC)
and is based on 1978 price levels.The FERC composite Anchorage-
Fairbanks capacity value of $186.58 per kilowatt-year represents a
107 percent increase over the comparable estimate provided by FERC
(then the Federal Power Commission)in 1975.The 1978 composite energy
value of 12.76 mills per kilowatt-hour amounts to a 144 percent increase
over the comparable estimate of 1975.These higher estimates more
than double the power benefit to an average annual equivalent of $289
million.
Besides those from the sale of power,there are power-related
benefits derived from interconnection of the Anchorage and Fairbanks
load centers.An interconnected system allows the sharing of capacity
reserves so that fewer reserves are required in the system.Thus.
interconnection offers benefits equal to the cost savings from not
constructing additional capacity that would otherwise have been neces-
sary.This benefit amounts to an average annual equivalent of $11
million.
Recreation benefits estimated at $300,000 annually are no change
from the 1976 report.The benefits associated with flood control are
6
presented in the 1976 report.which were based on a January 1975 price
1eve 1.
By far the largest category of benefits is that which results from
the sale of power.The value of the power is derived from the cost of
producing it by means of the least cost nonhydro alternative which,
in this case,is coal-fired generation.The cost of the thermal alter-
native was provided by the Federal Energy Regulatory Commission (FERC)
and is based on 1978 price levels.The FERC composite Anchorage-
Fairbanks capacity value of $186.58 per kilowatt-year represents a
107 percent increase over the comparable estimate provided by FERC
(then the Federal Power Commission)in 1975.The 1978 composite energy
value of 12.76 mills per kilowatt-hour amounts to a 144 percent increase
over the comparable estimate of 1975.These higher estimates more
than double the power benefit to an average annual equivalent of $289
million.
Besides those from the sale of power,there are power-related
benefits derived from interconnection of the Anchorage and Fairbanks
load centers.An interconnected system allows the sharing of capacity
reserves so that fewer reserves are required in the system.Thus.
interconnection offers benefits equal to the cost savings from not
constructing additional capacity that would otherwise have been neces-
sary.This benefit amounts to an average annual equivalent of $11
million.
Recreation benefits estimated at $300,000 annually are no change
from the 1976 report.The benefits associated with flood control are
6
estimated at $65,000 annually,an increase of 30 percent over the 1975
figure due solely to price changes associated with repair to damaged
facilities.
The final benefit category,that attributable to the use of other-
wise unemployed labor in project construction,is estimated at an
average annual equivalent of $24 million.The 155 percent increase
in this benefit over the original 1975 estimate is due to the higher
cost of construction and more detailed analysis of labor requirements.
Under the base case set iof~~ssumpt,~_ons,the P,-~~j/~s~~_hS~~.~t,nr pr-0ject
offers annual net benefits of $95 million and a benefit-cost ratio of
1.42.The hydropower project's net benefits exceed those of the thermal
alternative by $76 million annually.With an assumption of stable
prices and medium load growth,the year 2000 average power system rates
with the Susitna project are estimated at 5.5¢/kWh in Anchorage and
6.7¢/kWh in Fairbanks.This represents a 17 percent and 25 percent
savings over the anticipated 6.6¢/kWh and 8.9¢/kWh rates without
Susitna power.
In summary,the supplemental feasibility studies undertaken during
1978 have confirmed the adequacy of the Watana site for construction
of the proposed facilities.The project design has been refined in
light of the newly acquired geologic and foundation information.The
need for additional power in the railbelt area has been verified,and
additional environmental resource information has been added to the
data base.The review of project costs and benefits has indicated that
7
estimated at $65,000 annually,an increase of 30 percent over the 1975
figure due solely to price changes associated with repair to damaged
facilities.
The final benefit category,that attributable to the use of other-
wise unemployed labor in project construction,is estimated at an
average annual equivalent of $24 million.The 155 percent increase
in this benefit over the original 1975 estimate is due to the higher
cost of construction and more detailed analysis of labor requirements.
Under the base case set iof~~ssumpt,~_ons,the P,-~~j/~s~~_hS~~.~t,nr pr-0ject
offers annual net benefits of $95 million and a benefit-cost ratio of
1.42.The hydropower project's net benefits exceed those of the thermal
alternative by $76 million annually.With an assumption of stable
prices and medium load growth,the year 2000 average power system rates
with the Susitna project are estimated at 5.5¢/kWh in Anchorage and
6.7¢/kWh in Fairbanks.This represents a 17 percent and 25 percent
savings over the anticipated 6.6¢/kWh and 8.9¢/kWh rates without
Susitna power.
In summary,the supplemental feasibility studies undertaken during
1978 have confirmed the adequacy of the Watana site for construction
of the proposed facilities.The project design has been refined in
light of the newly acquired geologic and foundation information.The
need for additional power in the railbelt area has been verified,and
additional environmental resource information has been added to the
data base.The review of project costs and benefits has indicated that
7
the Susitna project is economically justified under a broad range of
possible futures.Finally,Susitna power has been shown to be marketable
and less costly than any viable alternative.
The direction taken in the conduct of these supplemental feasi-
bility studies was largely dictated by the concerns regarding project
justification expressed by the Office of Management and Budget.The
remainder of the main report responds to the specific questions raised
by OMB.The Alaska Power Administration of the Department of Energy
and Batte1le Pacific Northwest Laboratories both contributed signifi-
cantly to the analysis and to the formulation of the responses.
Supplementary data and analysis in support of the responses are contained
in the appendix.
8
the Susitna project is economically justified under a broad range of
possible futures.Finally,Susitna power has been shown to be marketable
and less costly than any viable alternative.
The direction taken in the conduct of these supplemental feasi-
bility studies was largely dictated by the concerns regarding project
justification expressed by the Office of Management and Budget.The
remainder of the main report responds to the specific questions raised
by OMB.The Alaska Power Administration of the Department of Energy
and Batte1le Pacific Northwest Laboratories both contributed signifi-
cantly to the analysis and to the formulation of the responses.
Supplementary data and analysis in support of the responses are contained
in the appendix.
8
WATANA SITE GEOLOGY AND TEST BORINGS
OMS COMMENT
The cost estimates for Watana have been derived
without benefit of any test borings at the Watana site.
This is a departure from standard Corps practice,which
calls for exploratory drilling at all sites before
projects are proposed for authorization.Test borings
would provide more reliable data on which to base cost
estimates and on which to assess any potential seismic
problems.The Watana site is located near the Susitna
Fault and also within 50 miles of the Denali Fault -an
area where major earthquakes have occurred in the past.
SCOPE OF GEOLOGICAL INVESTIGATIONS
Field Reconnaissance
Geologic reconnaissance and mapping of the reservoir area and
damsite were conducted concurrently with subsurface investigations
throughout the spring and early summer of 1978.Within the damsite
area the primary purpose was to locate,identify,and trace the surface
expressions of discontinuities and shear zones to aid in directing
the drilling program and to provide a preliminary geologic map of the
site.Within the reservoir area,the primary thrust of the reconnais-
sance was to identify by reason of shape,structure,or overburden
mantle the slopes that could develop slumps or slides as a result of
permafrost degradation or seismic action.
Borings and Test Pits
During 1978,explorations were conducted in the dam foundation
and relict channel area.Core borings in the valley walls and floor
9
WATANA SITE GEOLOGY AND TEST BORINGS
OMS COMMENT
The cost estimates for Watana have been derived
without benefit of any test borings at the Watana site.
This is a departure from standard Corps practice,which
calls for exploratory drilling at all sites before
projects are proposed for authorization.Test borings
would provide more reliable data on which to base cost
estimates and on which to assess any potential seismic
problems.The Watana site is located near the Susitna
Fault and also within 50 miles of the Denali Fault -an
area where major earthquakes have occurred in the past.
SCOPE OF GEOLOGICAL INVESTIGATIONS
Field Reconnaissance
Geologic reconnaissance and mapping of the reservoir area and
damsite were conducted concurrently with subsurface investigations
throughout the spring and early summer of 1978.Within the damsite
area the primary purpose was to locate,identify,and trace the surface
expressions of discontinuities and shear zones to aid in directing
the drilling program and to provide a preliminary geologic map of the
site.Within the reservoir area,the primary thrust of the reconnais-
sance was to identify by reason of shape,structure,or overburden
mantle the slopes that could develop slumps or slides as a result of
permafrost degradation or seismic action.
Borings and Test Pits
During 1978,explorations were conducted in the dam foundation
and relict channel area.Core borings in the valley walls and floor
9
were used to explore the quality and structure of the foundation rock
and to obtain representative samples for testing.Borings in the relict
channel area were used to define depth of overburden,the extent of
permafrost,and the location of the water table as well as to examine
the nature and condition of the materials by drilling.
Also during 1978,numerous test pits were dug in potential borrow
areas utilizing tractor-mounted backhoes.Bulk sack samples were
retrieved from each test pit for later testing.Shallow auger holes
were also used to determine the extent of deposits and to verify the
existence of quantities necessary for embankment construction.
Seismic Refraction Surveys
A seismic refraction exploration program consisting of 22,500 lineal
feet of seismic refraction lines was completed by Dames and Moore,
Consultants,in 1975.In the fall of 1978,an additional seismic
refraction survey was completed by Shannon and Wilson,Consultants,
which included 47,665 feet of seismic refraction 1ineso The survey
confirmed the Dames and Moore findings of a buried relict channel and,
in general,supported conclusions relating to rock quality in the
abutments as interpreted from the recent core borings and geologic
reconnaissance.The Shannon and Wilson study also confirmed the
existence of large quantities of borrow materials on Tsusena Creek.
The specific locations of the exploratory borings,test pits,and
seismic refraction lines are shown on Plate 2.
10
were used to explore the quality and structure of the foundation rock
and to obtain representative samples for testing.Borings in the relict
channel area were used to define depth of overburden,the extent of
permafrost,and the location of the water table as well as to examine
the nature and condition of the materials by drilling.
Also during 1978,numerous test pits were dug in potential borrow
areas utilizing tractor-mounted backhoes.Bulk sack samples were
retrieved from each test pit for later testing.Shallow auger holes
were also used to determine the extent of deposits and to verify the
existence of quantities necessary for embankment construction.
Seismic Refraction Surveys
A seismic refraction exploration program consisting of 22,500 lineal
feet of seismic refraction lines was completed by Dames and Moore,
Consultants,in 1975.In the fall of 1978,an additional seismic
refraction survey was completed by Shannon and Wilson,Consultants,
which included 47,665 feet of seismic refraction 1ineso The survey
confirmed the Dames and Moore findings of a buried relict channel and,
in general,supported conclusions relating to rock quality in the
abutments as interpreted from the recent core borings and geologic
reconnaissance.The Shannon and Wilson study also confirmed the
existence of large quantities of borrow materials on Tsusena Creek.
The specific locations of the exploratory borings,test pits,and
seismic refraction lines are shown on Plate 2.
10
FINDINGS AND DESIGN CHANGES
As a result of the additional field exploration and geologic studies
in 1978,a more knowledgeable assessment of the proposed project can be
made.Fo 11 owi ng is a summary of the items wh i ch refl ect changes to the
1976 Interim Feasibility Report or reinforce its basic concepts.
Nothing was found during this phase of the study to cast doubt on
the feasibility of a dam at the Watana site.All exploration and geologic
studies reinforce the previous conclusion that a large earth and rock-
fill or concrete gravity dam could be built in this Vicinity.
Explorations at the damsite indicate that the rock is as good or
better than previously assumed.Foundation rock is considered adequate
to support either an earth and rockfill or concrete gravity structure
at this site.
The 1978 exploration program confirmed the existence of marginal
permafrost in the area.Specific locations of permafrost were identified
and a number of temperature measuring devices were installed.It was
determined that this is a very "warm ll permafrost,ranging in temperature
from 0°C to _1°C.Permafrost was encountered in bedrock in the left
abutment of the dam and its effects on the grouting in this area are
discussed in the appendix.Permafrost was also encountered in the
impervious borrow area;however,it is not considered to be a serious
problem as it is quite warm and can be easily excavated.
The 1976 report envisioned rather large amounts of gravels avail-
able for construction of the shells of the dam and limited amounts of
11
FINDINGS AND DESIGN CHANGES
As a result of the additional field exploration and geologic studies
in 1978,a more knowledgeable assessment of the proposed project can be
made.Fo 11 owi ng is a summary of the items wh i ch refl ect changes to the
1976 Interim Feasibility Report or reinforce its basic concepts.
Nothing was found during this phase of the study to cast doubt on
the feasibility of a dam at the Watana site.All exploration and geologic
studies reinforce the previous conclusion that a large earth and rock-
fill or concrete gravity dam could be built in this Vicinity.
Explorations at the damsite indicate that the rock is as good or
better than previously assumed.Foundation rock is considered adequate
to support either an earth and rockfill or concrete gravity structure
at this site.
The 1978 exploration program confirmed the existence of marginal
permafrost in the area.Specific locations of permafrost were identified
and a number of temperature measuring devices were installed.It was
determined that this is a very "warm ll permafrost,ranging in temperature
from 0°C to _1°C.Permafrost was encountered in bedrock in the left
abutment of the dam and its effects on the grouting in this area are
discussed in the appendix.Permafrost was also encountered in the
impervious borrow area;however,it is not considered to be a serious
problem as it is quite warm and can be easily excavated.
The 1976 report envisioned rather large amounts of gravels avail-
able for construction of the shells of the dam and limited amounts of
11
impervious core material.However,the recent explorations indicate
that the reverse is true.Large quantities of gravel were not located,
but large quantities of impervious core material were discovered near
the damsite.Because of the apparent shortage of large quantities of
gravel and the excess of impervious material,the dam section has been
revised with gravel shells having been changed to rock shells.This
change to rockfill has allowed the use of a steeper slope on the up-
stream face of the dam.A large portion of the rock will come from
required excavation of the spillway and the remainder will come from
excavation of underground facilities and access roads and from a large
borrow source on the left abutment.
The core has been widened somewhat from that shown in the 1976
report and a zone of semipervious material,approximately of the same
width as the core,has been added.This was done because of the large
amounts of this material available and because our estimates show that
it can be placed within the dam at a considerably lower cost than the
rock shell material.The total thickness of these impervious or semi-
pervious zones was determined by considering their effect on the total
stability of the dam and the difficulties of placing materials which
require careful moisture control in the arctic environment.Laboratory
tests performed on these materials indicate that optimum moisture will
be a critical factor in their compaction.
The foundation excavation has been increased in order to remove all
gravels from beneath the embankment and strip the entire dam foundation
to bedrock.
12
impervious core material.However,the recent explorations indicate
that the reverse is true.Large quantities of gravel were not located,
but large quantities of impervious core material were discovered near
the damsite.Because of the apparent shortage of large quantities of
gravel and the excess of impervious material,the dam section has been
revised with gravel shells having been changed to rock shells.This
change to rockfill has allowed the use of a steeper slope on the up-
stream face of the dam.A large portion of the rock will come from
required excavation of the spillway and the remainder will come from
excavation of underground facilities and access roads and from a large
borrow source on the left abutment.
The core has been widened somewhat from that shown in the 1976
report and a zone of semipervious material,approximately of the same
width as the core,has been added.This was done because of the large
amounts of this material available and because our estimates show that
it can be placed within the dam at a considerably lower cost than the
rock shell material.The total thickness of these impervious or semi-
pervious zones was determined by considering their effect on the total
stability of the dam and the difficulties of placing materials which
require careful moisture control in the arctic environment.Laboratory
tests performed on these materials indicate that optimum moisture will
be a critical factor in their compaction.
The foundation excavation has been increased in order to remove all
gravels from beneath the embankment and strip the entire dam foundation
to bedrock.
12
The 1976 report showed a vertical access shaft to the low-level
drain system which passed through the embankment of the dam.This has
been changed to a tunnel through the right abutment thereby eliminating
any structures in the dam embankment.
A grout gallery has been added to the lower portions of the dam
to facilitate grouting and to accommodate the process of thawing the
permafrost rock for grouting.
The spillway shown in the 1976 report has been relocated to the
southwest to insure rock cut for its entire length.The rock and
overburden material from this large excavation will be utilized in
the dam embankment.Also,the diverison tunnel portals have been
shifted to insure their location in sound rock.
The 1976 report discusses a potential problem of seepage along a
relict channel in the right abutment area.The 1978 exploration program
verified the existence of this channel;however,studies indicate
that it is not a problem and no remedial actions are necessary.
Ellis Krinitzsky of the Waterways Experiment Station and Ruben
Kachadoorian and Henry J.Moore of the U.S.Geological Survey were
contracted to perform seismic studies and evaluate the earthquake
risk at these sites.Their work was divided into two phases:
Kachadoorian and Moore performed the final reconnaissance of active
faults and other geologic hazards,and Krinitzsky assessed the poten-
tial for earthquakes associated with such faulting.The resulting
USGS report recognized that this is a highly seismic region;however,
13
The 1976 report showed a vertical access shaft to the low-level
drain system which passed through the embankment of the dam.This has
been changed to a tunnel through the right abutment thereby eliminating
any structures in the dam embankment.
A grout gallery has been added to the lower portions of the dam
to facilitate grouting and to accommodate the process of thawing the
permafrost rock for grouting.
The spillway shown in the 1976 report has been relocated to the
southwest to insure rock cut for its entire length.The rock and
overburden material from this large excavation will be utilized in
the dam embankment.Also,the diverison tunnel portals have been
shifted to insure their location in sound rock.
The 1976 report discusses a potential problem of seepage along a
relict channel in the right abutment area.The 1978 exploration program
verified the existence of this channel;however,studies indicate
that it is not a problem and no remedial actions are necessary.
Ellis Krinitzsky of the Waterways Experiment Station and Ruben
Kachadoorian and Henry J.Moore of the U.S.Geological Survey were
contracted to perform seismic studies and evaluate the earthquake
risk at these sites.Their work was divided into two phases:
Kachadoorian and Moore performed the final reconnaissance of active
faults and other geologic hazards,and Krinitzsky assessed the poten-
tial for earthquakes associated with such faulting.The resulting
USGS report recognized that this is a highly seismic region;however,
13
their reconnaissance of the proposed Devil Canyon and Watana damsites
and reservoirs did not uncover evidence of recent or active faulting
along any of the known or inferred faults.Their studies did not find
any evidence of the Susitna Fault which was previously thought to
exist a short distance west of the Watana damsite;therefore,they
were not able to confirm the existence of such a fault.USGS also
noted the areas where slides might be expected to occur along the valley
walls under the influence of saturation and thawing permafrost.
Krinitzsky's work assessed the possible occurrence of earthquakes at
the damsites and the motions that are likely to be associated with
earthquake activity.His findings indicate that the design of the
proposed dams to withstand such motion is within the state of the art
for seismic design.
14
their reconnaissance of the proposed Devil Canyon and Watana damsites
and reservoirs did not uncover evidence of recent or active faulting
along any of the known or inferred faults.Their studies did not find
any evidence of the Susitna Fault which was previously thought to
exist a short distance west of the Watana damsite;therefore,they
were not able to confirm the existence of such a fault.USGS also
noted the areas where slides might be expected to occur along the valley
walls under the influence of saturation and thawing permafrost.
Krinitzsky's work assessed the possible occurrence of earthquakes at
the damsites and the motions that are likely to be associated with
earthquake activity.His findings indicate that the design of the
proposed dams to withstand such motion is within the state of the art
for seismic design.
14
CONTINGENCY ESTIMATES
OMS COMMENT
A standard 20 percent contingency factor was used
in arriving at cost estimates.A contingency of 30
percent could result in reducing the benefit-cost-
ratio to 1.A larger contingency factor could reduce
the ratio below unity.The recently completed Snetti-
sham project in Alaska cost 36 percent more than
original estimates,after correction for inflation.
A review of the 20 percent contingency factor
should be undertaken,in light of the best existing
information on comparable projects and project loca-
tions.
Contingency factors have been reviewed and adjusted.The review
included incorporation of the new 1978 foundation,material,and
topographic information.Instead of utilizing a single contingency
factor for the project as a whole,each major feature was examined
individually to derive a contingency that reflects the uncertainties
associated with the design and cost of that specific feature.The
total estimated contingencies for the Watana project are approximately
$246 million or 18 percent of the estimated total construction cost.
Individual factors range from 15 percent for the relatively well defined
earth and rockfill main dam to 20 percent for many of the other features.
The contingencies used for the Devil Canyon project were adjusted
in two ways.First,a fundamental change in the design concept was
made.To insure that the cost estimates in this supplemental feasi-
bility study were sufficient to cover the possibility of unexpected
15
CONTINGENCY ESTIMATES
OMS COMMENT
A standard 20 percent contingency factor was used
in arriving at cost estimates.A contingency of 30
percent could result in reducing the benefit-cost-
ratio to 1.A larger contingency factor could reduce
the ratio below unity.The recently completed Snetti-
sham project in Alaska cost 36 percent more than
original estimates,after correction for inflation.
A review of the 20 percent contingency factor
should be undertaken,in light of the best existing
information on comparable projects and project loca-
tions.
Contingency factors have been reviewed and adjusted.The review
included incorporation of the new 1978 foundation,material,and
topographic information.Instead of utilizing a single contingency
factor for the project as a whole,each major feature was examined
individually to derive a contingency that reflects the uncertainties
associated with the design and cost of that specific feature.The
total estimated contingencies for the Watana project are approximately
$246 million or 18 percent of the estimated total construction cost.
Individual factors range from 15 percent for the relatively well defined
earth and rockfill main dam to 20 percent for many of the other features.
The contingencies used for the Devil Canyon project were adjusted
in two ways.First,a fundamental change in the design concept was
made.To insure that the cost estimates in this supplemental feasi-
bility study were sufficient to cover the possibility of unexpected
15
foundation conditions at the Devil Canyon site,a concrete gravity dam
design was analyzed.The concrete gravity structure requires less
ideal foundation conditions than does the concrete thin arch structure
recommended in the 1976 report.While the concrete arch design is still
deemed engineeringly feasible on the basis of the available Devil Canyon
geological explorations,the less sensitive and more costly concrete
gravity structure has been used as the basis of the 1978 cost estimate.
In this way,sufficient cost is included in the estimate to allow con-
struction of either the concrete thin arch if favorable site conditions
are found during preconstruction planning or the concrete gravity
structure if less favorable conditions are found to exist.Thus,
econolnic feasibility has been presented using the most conservative
set of conditions.
In addition to the more conservative gravity design at Devil Canyon,
normal contingency factors were also applied.·The total contingencies
for the Devil Canyon gravity dam estimate are about $121 million or
17 percent of total construction costs.
With the 1978 estimates of Susitna project benefits and costs,a
68 percent contingency factor would be required to have costs exceed
benefits under the base case set of assumptions.
The Snettisham Hydroelectric Project that provides power to the
Juneau area was mentioned by OMS as an example of cost overruns.The
reported 36 percent cost increase over original estimates is not
16
foundation conditions at the Devil Canyon site,a concrete gravity dam
design was analyzed.The concrete gravity structure requires less
ideal foundation conditions than does the concrete thin arch structure
recommended in the 1976 report.While the concrete arch design is still
deemed engineeringly feasible on the basis of the available Devil Canyon
geological explorations,the less sensitive and more costly concrete
gravity structure has been used as the basis of the 1978 cost estimate.
In this way,sufficient cost is included in the estimate to allow con-
struction of either the concrete thin arch if favorable site conditions
are found during preconstruction planning or the concrete gravity
structure if less favorable conditions are found to exist.Thus,
econolnic feasibility has been presented using the most conservative
set of conditions.
In addition to the more conservative gravity design at Devil Canyon,
normal contingency factors were also applied.·The total contingencies
for the Devil Canyon gravity dam estimate are about $121 million or
17 percent of total construction costs.
With the 1978 estimates of Susitna project benefits and costs,a
68 percent contingency factor would be required to have costs exceed
benefits under the base case set of assumptions.
The Snettisham Hydroelectric Project that provides power to the
Juneau area was mentioned by OMS as an example of cost overruns.The
reported 36 percent cost increase over original estimates is not
16
entirely correct since the 36 percent factor included additional con-
struction not contemplated in the original cost estimate.The original
estimate was for a project that included only the Long Lake phase of
development with associated camp facilities and transmission system.
The planned Crater Lake phase of development was added in fiscal year
1973,but construction has been deferred.The actual cost overrun as
of 1978 is 22 percent.More than half of this 22 percent overrun from
original cost estimates was accounted for by the temporary repairs and
subsequent permanent relocation of a failed portion of the transmission
line.Environmental considerations had dictated its original location
in an area of extreme winds and ice conditions not previously encoun-
tered on any transmission line in North America.
17
entirely correct since the 36 percent factor included additional con-
struction not contemplated in the original cost estimate.The original
estimate was for a project that included only the Long Lake phase of
development with associated camp facilities and transmission system.
The planned Crater Lake phase of development was added in fiscal year
1973,but construction has been deferred.The actual cost overrun as
of 1978 is 22 percent.More than half of this 22 percent overrun from
original cost estimates was accounted for by the temporary repairs and
subsequent permanent relocation of a failed portion of the transmission
line.Environmental considerations had dictated its original location
in an area of extreme winds and ice conditions not previously encoun-
tered on any transmission line in North America.
17
AREA REDEVELOPMENT BENEFITS
OMS COMMENT
These benefits are a correction for the use of other-
wise unemployed labor during construction.Though standard
procedures permit this benefit category for power projects,
it would seem that such benefits should not be accepted in
the Susitna report because private development for power
purposes would produce equivalent benefits.
An evaluation of the validity of the use of ARA benefits
in the Susitna report should be made.
Project costs are considered to be an adverse effect on the national
economy because resources required for construction would normally be
diverted from other uses.The value of resources in their alternative
uses is therefore the true economic cost of the project.If some
resources used in the proposed plan would otherwise be unemployed,
these resources would not be diverted from production of other goods
and services and,hence,are not an economic cost to the national
economy.Procedurally,the credit for using unemployed labor is con-
ventionally tabulated as an addition to benefits rather than a deduction
from costs.
The basis for determination of employment benefits as with benefits
associated with all other project purposes,is a comparison of condi-
tions with and without a plan to provide the planning objective.The
with condition is the plan under consideration,namely the provision
of additional power.The without condition is without provision of
18
AREA REDEVELOPMENT BENEFITS
OMS COMMENT
These benefits are a correction for the use of other-
wise unemployed labor during construction.Though standard
procedures permit this benefit category for power projects,
it would seem that such benefits should not be accepted in
the Susitna report because private development for power
purposes would produce equivalent benefits.
An evaluation of the validity of the use of ARA benefits
in the Susitna report should be made.
Project costs are considered to be an adverse effect on the national
economy because resources required for construction would normally be
diverted from other uses.The value of resources in their alternative
uses is therefore the true economic cost of the project.If some
resources used in the proposed plan would otherwise be unemployed,
these resources would not be diverted from production of other goods
and services and,hence,are not an economic cost to the national
economy.Procedurally,the credit for using unemployed labor is con-
ventionally tabulated as an addition to benefits rather than a deduction
from costs.
The basis for determination of employment benefits as with benefits
associated with all other project purposes,is a comparison of condi-
tions with and without a plan to provide the planning objective.The
with condition is the plan under consideration,namely the provision
of additional power.The without condition is without provision of
18
additional power.The relevant without condition for purposes of
benefit evaluation is not an alternative solution to the planning objec-
tive even though in the absence of the recommended project,an alter-
native will be provided.Therefore,the entire applicable employment
benefit is credited to each project considered in the plan formulation
process.If,alternatively,wage payments of otherwise unemployed
labor is credited as a savings in economic costs,it is even more
apparent that such wage payments would be fully deductible from costs
of any and all projects constructed.
19
additional power.The relevant without condition for purposes of
benefit evaluation is not an alternative solution to the planning objec-
tive even though in the absence of the recommended project,an alter-
native will be provided.Therefore,the entire applicable employment
benefit is credited to each project considered in the plan formulation
process.If,alternatively,wage payments of otherwise unemployed
labor is credited as a savings in economic costs,it is even more
apparent that such wage payments would be fully deductible from costs
of any and all projects constructed.
19
CONSTRUCTION SCHEDULE
OMB COMMENT
The ll-year construction schedule for the Watana
project,based on preliminary inspection of comparable
projects,appears to be on the short side.A longer
schedule of 14 years appears more reasonable because
of (1)normal slippages and (2)a 3-year peak con-
struction schedule that calls for more work to be put
in place on a single site than the Corps has ever
accomplished in similar time periods.This should
be reexamined and its effects on the project BIC
ratio calculated.
GENERAL
The construction schedule has been reanalyzed and lengthened from
10 to 14 years.The Watana dam and powerplant will take 10 years to
construct,an increase of 4 years over the previous schedule.The
Devil Canyon project construction will require 8 years rather than the
previously estimated 5 years.There will be 4 years of concurrent
construction to meet power-on-line dates.
DIVERSION PLANS
The time for Watana diversion works construction and stream diver-
sion has been extended to 3 years from the previously estimated 2 years,
because the construction access to the tunnel portals requires extensive
rock cuts and added time.The start of construction of the diversion
works for the Devil Canyon dam has been delayed from the 5th to the
7th year of Watana construction because it is dependent on stream
regulation by the upstream Watana dam.
20
CONSTRUCTION SCHEDULE
OMB COMMENT
The ll-year construction schedule for the Watana
project,based on preliminary inspection of comparable
projects,appears to be on the short side.A longer
schedule of 14 years appears more reasonable because
of (1)normal slippages and (2)a 3-year peak con-
struction schedule that calls for more work to be put
in place on a single site than the Corps has ever
accomplished in similar time periods.This should
be reexamined and its effects on the project BIC
ratio calculated.
GENERAL
The construction schedule has been reanalyzed and lengthened from
10 to 14 years.The Watana dam and powerplant will take 10 years to
construct,an increase of 4 years over the previous schedule.The
Devil Canyon project construction will require 8 years rather than the
previously estimated 5 years.There will be 4 years of concurrent
construction to meet power-on-line dates.
DIVERSION PLANS
The time for Watana diversion works construction and stream diver-
sion has been extended to 3 years from the previously estimated 2 years,
because the construction access to the tunnel portals requires extensive
rock cuts and added time.The start of construction of the diversion
works for the Devil Canyon dam has been delayed from the 5th to the
7th year of Watana construction because it is dependent on stream
regulation by the upstream Watana dam.
20
MAIN DAMS
Foundation preparation at Watana would be delayed to the 4th year
as a result of the extended diversion requirements which would delay
the start of cofferdam construction.Watana embankment construction,
scheduled to begin in the 5th year and continue into the 10th,would
require 6 years instead of the previously estimated 3 years,based on
construction seasons of 5 months with average daily placement rates
of 80,000 cubic yards.Water impoundment would start in the 8th year
with power-on-line in October of the 10th year.The reservoir filling
would continue beyond the power-on-line date and would depend on the
rates of inflow and power generation.
Foundation preparation for Devil Canyon dam would start in the 9th
year,a 2 year delay from the earlier estimate.Concrete placement
and dam completion would begin in the 10th year and require 5 years,
an increase of 2 years over the earlier schedule.Impoundment would
commence in the 13th year and end with a full reservoir in October of
the 14th year.
EFFECT OF DELAY
The presently scheduled power-on-line dates are 1994 for Watana
and 1998 for Devil Canyon.These were previously scheduled for 1986
and 1990 respectively.These dates include the result of the changes
in assumed congressional construction authorization from July 1980
to October 1984 and the revised construction schedule.Transmission
line construction could be completed in 1991,permitting connection
21
MAIN DAMS
Foundation preparation at Watana would be delayed to the 4th year
as a result of the extended diversion requirements which would delay
the start of cofferdam construction.Watana embankment construction,
scheduled to begin in the 5th year and continue into the 10th,would
require 6 years instead of the previously estimated 3 years,based on
construction seasons of 5 months with average daily placement rates
of 80,000 cubic yards.Water impoundment would start in the 8th year
with power-on-line in October of the 10th year.The reservoir filling
would continue beyond the power-on-line date and would depend on the
rates of inflow and power generation.
Foundation preparation for Devil Canyon dam would start in the 9th
year,a 2 year delay from the earlier estimate.Concrete placement
and dam completion would begin in the 10th year and require 5 years,
an increase of 2 years over the earlier schedule.Impoundment would
commence in the 13th year and end with a full reservoir in October of
the 14th year.
EFFECT OF DELAY
The presently scheduled power-on-line dates are 1994 for Watana
and 1998 for Devil Canyon.These were previously scheduled for 1986
and 1990 respectively.These dates include the result of the changes
in assumed congressional construction authorization from July 1980
to October 1984 and the revised construction schedule.Transmission
line construction could be completed in 1991,permitting connection
21
of the Anchorage and Fairbanks load centers in advance of Watana power-
on-line.The economic evaluation is based on this longer 14-year con-
struction schedule and the delayed power-on-line dates.
Even with the longer 14-year construction period,additional con-
struction delays are possible.The impacts,however,would be minimized
by the recommended two-stage construction sequence.If significant
delays were experienced on Watana,the start and schedule of Devil
Canyon construction could be adjusted with minimal cost impact.Delays
in Devil Canyon construction would have no effect on Watana's schedule.
The project1s economic justification has been analyzed to assess
the impact of construction delays that would extend the power-on-line
dates.As an example,a 2-year delay in Watana completion was evaluated.
The primary effect on project cost would be the accumulation of addi-
tional interest during construction.The 2-year delay increases average
annual costs by about $17 million.
The delay of Watana power-on-line would also affect project benefits,
although the change would be small.The impact on benefits is due to
the mix and schedule of thermal plants coming on line prior to Watana
and to the rate of load growth during the years after power-on-line.
For a 2-year delay,equivalent average annual power benefits would be
reduced about $4 million.
The net change in project economics would be an increase in total
annual costs to $245 million and a reduction in annual benefits to $320
million.This decreases the benefit-cost ratio from 1.42 to 1.31.
22
of the Anchorage and Fairbanks load centers in advance of Watana power-
on-line.The economic evaluation is based on this longer 14-year con-
struction schedule and the delayed power-on-line dates.
Even with the longer 14-year construction period,additional con-
struction delays are possible.The impacts,however,would be minimized
by the recommended two-stage construction sequence.If significant
delays were experienced on Watana,the start and schedule of Devil
Canyon construction could be adjusted with minimal cost impact.Delays
in Devil Canyon construction would have no effect on Watana's schedule.
The project1s economic justification has been analyzed to assess
the impact of construction delays that would extend the power-on-line
dates.As an example,a 2-year delay in Watana completion was evaluated.
The primary effect on project cost would be the accumulation of addi-
tional interest during construction.The 2-year delay increases average
annual costs by about $17 million.
The delay of Watana power-on-line would also affect project benefits,
although the change would be small.The impact on benefits is due to
the mix and schedule of thermal plants coming on line prior to Watana
and to the rate of load growth during the years after power-on-line.
For a 2-year delay,equivalent average annual power benefits would be
reduced about $4 million.
The net change in project economics would be an increase in total
annual costs to $245 million and a reduction in annual benefits to $320
million.This decreases the benefit-cost ratio from 1.42 to 1.31.
22
[
Analysis shows that the construction period would have to be prolonged
at least an extra 9 years before the Susitna project would become
uneconomic.
23
[
Analysis shows that the construction period would have to be prolonged
at least an extra 9 years before the Susitna project would become
uneconomic.
23
SUPPLY ESTIMATES
OMB COMMENT
The analysis of the without project condition needs
to be expanded considerably to clearly analyze the
following:
a.Why,with natural gas projected to be in such
short supply,the Anchorage utilities have only con-
tracted for 55 percent of proved reserves or 25 percent
of estimated ultimate reserves.
b.The sensitivity of the analysis to the collapse
of OPEC and the cost of shipping oil to the east coast.
c.The necessity for an Anchorage-Fairbanks inter-
tie at a cost of $200-300 million.
d.Scheduling of powerplants and the reduced risk
of building small increments.
INTRODUCTION
The first two items must be considered in terms of national energy
policy.The United States needs to reduce dependency on oil imports
on both a short-term and a long-term basis and to accomplish a major
shift away from oil and natural gas to alternative energy sources.
The reasons for this include national economic considerations,as well
as very real limits on national and world supplies of oil and natural
gas.
In terms of national energy policy,oil and natural gas are not
available alternatives for long-term production of electric power.
There are remaining questions as to how quickly existing uses will be
phased out and on how complete the prohibitions will be on new oil
and natural gas-fired powerplants.
24
SUPPLY ESTIMATES
OMB COMMENT
The analysis of the without project condition needs
to be expanded considerably to clearly analyze the
following:
a.Why,with natural gas projected to be in such
short supply,the Anchorage utilities have only con-
tracted for 55 percent of proved reserves or 25 percent
of estimated ultimate reserves.
b.The sensitivity of the analysis to the collapse
of OPEC and the cost of shipping oil to the east coast.
c.The necessity for an Anchorage-Fairbanks inter-
tie at a cost of $200-300 million.
d.Scheduling of powerplants and the reduced risk
of building small increments.
INTRODUCTION
The first two items must be considered in terms of national energy
policy.The United States needs to reduce dependency on oil imports
on both a short-term and a long-term basis and to accomplish a major
shift away from oil and natural gas to alternative energy sources.
The reasons for this include national economic considerations,as well
as very real limits on national and world supplies of oil and natural
gas.
In terms of national energy policy,oil and natural gas are not
available alternatives for long-term production of electric power.
There are remaining questions as to how quickly existing uses will be
phased out and on how complete the prohibitions will be on new oil
and natural gas-fired powerplants.
24
There is general agreement that implementation of national policy
must include strong efforts in conservation,substantial increase in
use of coal,and major efforts to develop renewable energy sources.
Each of these components is sensitive to energy price and supply
variables.A reduction in world oil prices or a period of oversupply
serves as a marketplace disincentive for conservation efforts and work
on alternative energy sources.
The lowest cost alternatives and those with fully proven technology
are the 1east sensitive;those that depend on further research and
development are most easily sidetracked.
The Susitna project involves large blocks of power and new energy
from a renewable source,fully proven technology,long revenue-producing
period (in excess of 100 years),and essential freedom from long-term
price increases.Its power costs appear attractive in comparison to
coal-fired powerplants.It is a two-stage project with opportunity to
defer the second stage if demands are lower than present estimates or
if price relationships change.
The above factors suggest that the Susitna project is much less
sensitive to short-term oil price and supply variations than most
other U.S.energy options.
If it is assumed that Alaskan oil and natural gas will be isolated
from U.S.and world demand and pricing,Alaska would probably continue
to use its oil and gas for most of its power.This assumption did,
in fact.prevail between the initial in the
25
There is general agreement that implementation of national policy
must include strong efforts in conservation,substantial increase in
use of coal,and major efforts to develop renewable energy sources.
Each of these components is sensitive to energy price and supply
variables.A reduction in world oil prices or a period of oversupply
serves as a marketplace disincentive for conservation efforts and work
on alternative energy sources.
The lowest cost alternatives and those with fully proven technology
are the 1east sensitive;those that depend on further research and
development are most easily sidetracked.
The Susitna project involves large blocks of power and new energy
from a renewable source,fully proven technology,long revenue-producing
period (in excess of 100 years),and essential freedom from long-term
price increases.Its power costs appear attractive in comparison to
coal-fired powerplants.It is a two-stage project with opportunity to
defer the second stage if demands are lower than present estimates or
if price relationships change.
The above factors suggest that the Susitna project is much less
sensitive to short-term oil price and supply variations than most
other U.S.energy options.
If it is assumed that Alaskan oil and natural gas will be isolated
from U.S.and world demand and pricing,Alaska would probably continue
to use its oil and gas for most of its power.This assumption did,
in fact.prevail between the initial in the
25
Cook Inlet area and the 1973 oil embargo.In 1960,the Anchorage-Cook
Inlet power supplies came almost entirely from coal and hydro.The
low cost,abundant gas brought a halt to hydro development and de-
stroyed the area's coal industry.The one remaining Alaskan coal mine
barely survived the 1960's because of competition from relatively
cheap oil.
Cook Inlet gas has been subjected to increasing competition in
the last few years,including proposals for LNG facilities,additional
petrochemical plants,and consideration of pipeline alternatives to tie
in with the Alcan pipeline project.The competition resulted in
increasing prices and increasing difficulty in obtaining long-term
commitments of gas for power.The competitions and the price increases
are expected to continue.
The real question on gas availability as it pertains to the Susitna
project is:what is the outlook for long-term gas supplies for power
after 1990?The answer is that the outlook is not good in terms of
competing uses and national policy.
NATURAL GAS AVAILABILITY
The primary reason for not considering natural gas-fired generation
as the alternative to Susitna hydropower development is not gas avail-
ability,but national energy policy.The Powerplant and Industrial
Fuel Use Bill of the National Energy Act of 1978 clearly indicates
that the intent of the Administration and Congress is to strongly
discourage the use of natural gas for electrical generation.The law
26
Cook Inlet area and the 1973 oil embargo.In 1960,the Anchorage-Cook
Inlet power supplies came almost entirely from coal and hydro.The
low cost,abundant gas brought a halt to hydro development and de-
stroyed the area's coal industry.The one remaining Alaskan coal mine
barely survived the 1960's because of competition from relatively
cheap oil.
Cook Inlet gas has been subjected to increasing competition in
the last few years,including proposals for LNG facilities,additional
petrochemical plants,and consideration of pipeline alternatives to tie
in with the Alcan pipeline project.The competition resulted in
increasing prices and increasing difficulty in obtaining long-term
commitments of gas for power.The competitions and the price increases
are expected to continue.
The real question on gas availability as it pertains to the Susitna
project is:what is the outlook for long-term gas supplies for power
after 1990?The answer is that the outlook is not good in terms of
competing uses and national policy.
NATURAL GAS AVAILABILITY
The primary reason for not considering natural gas-fired generation
as the alternative to Susitna hydropower development is not gas avail-
ability,but national energy policy.The Powerplant and Industrial
Fuel Use Bill of the National Energy Act of 1978 clearly indicates
that the intent of the Administration and Congress is to strongly
discourage the use of natural gas for electrical generation.The law
26
.-.
contains a prohibition against the use of natural gas as a primary
fuel in any newly constructed utility generation facility.Permanent
exemptions from this prohibition for a new base load powerplant may
be obtained under certain circumstances.The Department of Energy's
draft implementing regulations permit exemptions if utilities can prove
it would be overly costly,environmentally unsound,or impossible because
of insufficient or unavailable supplies of coal or other fuels at the
plant's location.None of these exemptions appear applicable to Alaska.
The Federal Energy Regulatory Commission,in not providing gas-fired
generation costs,agrees with that assessment.
While national energy policy is reason enough to discount n,atural
gas-fired generation as a long-term alternative to a major hydropower
project,data on the local supplies of natural gas was presented in the
1976 report as additional evidence.That data has been updated using
1978 information.
There are an estimated 4,428 billion cubic feet (BCF)of recoverable
gas reserves in Cook Inlet,with an additional speculative potential of
from 6 to 29 trillion cubic feet.Approximately 3,698 BCF,or 84 per-
cent of the estimated recoverable reserves are presently committed to
Alaskan and export uses.The proportion of committments would even be
higher but for an unwillingness on the part of natural gas owners to
enter into contracts for the provision of gas during a period of rapidly
escalating gas prices and great uncertainty regarding gas price deregu-
lation.Additional committments are anticipated as the pricing structure
stabilizes.
27
.-.
contains a prohibition against the use of natural gas as a primary
fuel in any newly constructed utility generation facility.Permanent
exemptions from this prohibition for a new base load powerplant may
be obtained under certain circumstances.The Department of Energy's
draft implementing regulations permit exemptions if utilities can prove
it would be overly costly,environmentally unsound,or impossible because
of insufficient or unavailable supplies of coal or other fuels at the
plant's location.None of these exemptions appear applicable to Alaska.
The Federal Energy Regulatory Commission,in not providing gas-fired
generation costs,agrees with that assessment.
While national energy policy is reason enough to discount n,atural
gas-fired generation as a long-term alternative to a major hydropower
project,data on the local supplies of natural gas was presented in the
1976 report as additional evidence.That data has been updated using
1978 information.
There are an estimated 4,428 billion cubic feet (BCF)of recoverable
gas reserves in Cook Inlet,with an additional speculative potential of
from 6 to 29 trillion cubic feet.Approximately 3,698 BCF,or 84 per-
cent of the estimated recoverable reserves are presently committed to
Alaskan and export uses.The proportion of committments would even be
higher but for an unwillingness on the part of natural gas owners to
enter into contracts for the provision of gas during a period of rapidly
escalating gas prices and great uncertainty regarding gas price deregu-
lation.Additional committments are anticipated as the pricing structure
stabilizes.
27
In 1976.34 percent of Alaska's total energy consumption was pro-
vided by Cook Inlet natural gas.Several forecasts of gas demand have
been completed.and estimated proven Cook Inlet gas reserves are inade-
quate to meet the requirements in all forecasted cases.The deficit
through the year 2000 varies from a low of 783 BCF to a high of 3.804
BCF.depending on the forecasted use.The use of Cook Inlet gas for
new gas-fired electrical generation after 1985 would increase the year
2000 deficit by about 532 BCF.
OIL PRICE CHANGE IMPACTS
The economic justification for the Susitna hydropower project is
sensitive to changes in the price of oil only if oil-fired generation is
considered a realistic long-term alternative for electrical generation
in the rail belt area.However.the use of oil in benefit determination
for 100 years of power for a major new hydro project does not seem
appropriate in light of national energy policy in general and the
National Energy Act of 1978 in particular.As in the case of natural
gas.the use of oil in newly constructed generation facilities is pro-
hibited with limited exception.The exemptions contained in the legis-
lation do not appear pertinent in the face of the large supplies of
coal and hydropower potential available to the rail belt area.
Despite the strong arguments against new oil-fired generation in
the mid-1990's and beyond.project justification was examined using an
oil-fired powerp1ant as the basis of benefit calculation.Oil-fired
costs provided by FERC were used in the analysis.and the midrange load
28
In 1976.34 percent of Alaska's total energy consumption was pro-
vided by Cook Inlet natural gas.Several forecasts of gas demand have
been completed.and estimated proven Cook Inlet gas reserves are inade-
quate to meet the requirements in all forecasted cases.The deficit
through the year 2000 varies from a low of 783 BCF to a high of 3.804
BCF.depending on the forecasted use.The use of Cook Inlet gas for
new gas-fired electrical generation after 1985 would increase the year
2000 deficit by about 532 BCF.
OIL PRICE CHANGE IMPACTS
The economic justification for the Susitna hydropower project is
sensitive to changes in the price of oil only if oil-fired generation is
considered a realistic long-term alternative for electrical generation
in the rail belt area.However.the use of oil in benefit determination
for 100 years of power for a major new hydro project does not seem
appropriate in light of national energy policy in general and the
National Energy Act of 1978 in particular.As in the case of natural
gas.the use of oil in newly constructed generation facilities is pro-
hibited with limited exception.The exemptions contained in the legis-
lation do not appear pertinent in the face of the large supplies of
coal and hydropower potential available to the rail belt area.
Despite the strong arguments against new oil-fired generation in
the mid-1990's and beyond.project justification was examined using an
oil-fired powerp1ant as the basis of benefit calculation.Oil-fired
costs provided by FERC were used in the analysis.and the midrange load
28
forecast was assumed.With stable prices t the project1s annual power
benefits fall $78 million from the $289 million calculated on the basis
of the coal-fired alternative.Net benefits become $18 million t giving
a benefit-cost ratio of 1.08.
To calculate the impact of relative changes in the price of oil on
project feasibilitYt three sample cases were analyzed.First t there is
an assumption that fuel costs esclate at 2 percent per year between
1978 and the 30th year beyond power-on-line t after which there is no
additional escalation.The 30-year period corresponds to the service
life of the initial thermal plant.The 2 percent rate is selected as
representative of long-term real price increases arising from depleting
more distant sources t increasing environmental safeguards in extra-
ction.processing and handling.and anticipated producing nation pricing
policy.Two percent annual escalation in the price of oil results in
a 57 percent increase in annual power benefits over that with stable
prices;the benefit-cost ratio becomes 1.60.
The second case looks at the possibility of no price escalation
prior to power-on-line followed by a 30-year period of 2 percent
annual escalation.This case is designed to reflect the possibility
of a near-term softening of the market for oil due to slackening demand
or increased supply in the short-term.With stable prices in the near
term followed by a 30-year period of escalation t annual power benefits
increase 22 percent over the stable price case,giving a benefit-cost
ratio of 1.29.
29
forecast was assumed.With stable prices t the project1s annual power
benefits fall $78 million from the $289 million calculated on the basis
of the coal-fired alternative.Net benefits become $18 million t giving
a benefit-cost ratio of 1.08.
To calculate the impact of relative changes in the price of oil on
project feasibilitYt three sample cases were analyzed.First t there is
an assumption that fuel costs esclate at 2 percent per year between
1978 and the 30th year beyond power-on-line t after which there is no
additional escalation.The 30-year period corresponds to the service
life of the initial thermal plant.The 2 percent rate is selected as
representative of long-term real price increases arising from depleting
more distant sources t increasing environmental safeguards in extra-
ction.processing and handling.and anticipated producing nation pricing
policy.Two percent annual escalation in the price of oil results in
a 57 percent increase in annual power benefits over that with stable
prices;the benefit-cost ratio becomes 1.60.
The second case looks at the possibility of no price escalation
prior to power-on-line followed by a 30-year period of 2 percent
annual escalation.This case is designed to reflect the possibility
of a near-term softening of the market for oil due to slackening demand
or increased supply in the short-term.With stable prices in the near
term followed by a 30-year period of escalation t annual power benefits
increase 22 percent over the stable price case,giving a benefit-cost
ratio of 1.29.
29
The final case explores the impact of real oil price declines prior
to power-on-line.An immediate sharp drop in price is assumed,with
no change in price thereafter.This scenario is included to show the
possible effect on project justification of a breakup of the OPEC
cartel.The immediate decline in oil prices followed by stable prices
results in costs exceeding benefits and a benefit-cost ratio of 0.85.
To summarize,oil-fired generation is not an appropraite long-term
alternative to Susitna hydropower.If,nonetheless,oil-fired costs are
used in benefit calculation,the project remains economically justified
except in the extreme case of an immediate and precipitous drop in the
price of oil.
OMB suggested that the issue of shipping costs be explored.The FERC
fuel cost estimate that was used in the benefit calculation is net of
transportation costs between Alaska and continental u.s.ports.The fuel
costs used are the estimated cost of processed Alaskan oil at the power-
plant.No additional consideration of shipping costs to the East Coast
is deemed necessary.
ANCHORAGE-FAIRBANKS INTERTIE
The estimated construction cost (1978 dollars)for the transmission
lines associated with the Susitna project is $338 million.The portion
from the Susitna project to Fairbanks accounts for $152 million of the
total.
There are several previous studies that demonstrate inherent feasi-
bility of an Anchorage-Fairbanks intertie with or without construction
30
The final case explores the impact of real oil price declines prior
to power-on-line.An immediate sharp drop in price is assumed,with
no change in price thereafter.This scenario is included to show the
possible effect on project justification of a breakup of the OPEC
cartel.The immediate decline in oil prices followed by stable prices
results in costs exceeding benefits and a benefit-cost ratio of 0.85.
To summarize,oil-fired generation is not an appropraite long-term
alternative to Susitna hydropower.If,nonetheless,oil-fired costs are
used in benefit calculation,the project remains economically justified
except in the extreme case of an immediate and precipitous drop in the
price of oil.
OMB suggested that the issue of shipping costs be explored.The FERC
fuel cost estimate that was used in the benefit calculation is net of
transportation costs between Alaska and continental u.s.ports.The fuel
costs used are the estimated cost of processed Alaskan oil at the power-
plant.No additional consideration of shipping costs to the East Coast
is deemed necessary.
ANCHORAGE-FAIRBANKS INTERTIE
The estimated construction cost (1978 dollars)for the transmission
lines associated with the Susitna project is $338 million.The portion
from the Susitna project to Fairbanks accounts for $152 million of the
total.
There are several previous studies that demonstrate inherent feasi-
bility of an Anchorage-Fairbanks intertie with or without construction
30
of the Susitna project.The main reason that the intertie is not now
in place is that short-term benefits to the Anchorage area are quite
small;most of the short-term benefits for the intertie would occur
through reduced energy and power costs in the Fairbanks area.
The Alaska Power Administration.in the 1976 Interim Feasibility
Report.evaluated the provision of Susitna project power to Fairbanks
on a cost-of-service basis (see Appendix I,p.6-89 of the 1976 report).
This was a specific demonstration of feasibility of including Fairbanks
as part of the upper Susitna power market area.
Further verification of feasibility of the intertie is provided in
the new load-resource analyses and system cost analyses prepared for
the current studies.These general cases were analyzed:
Case 1.All future generating capacity assumed to be coal-fired steam
turbines without intertie.
Case 2.All future generating capacity assumed to be coal-fired steam
turbines with intertie.
Case 3.Future generating capacity to include the Susitna project
plus coal-fired steam plants as needed.This includes the
i nterti e.
The following table presents the costs of power in the year 2000
for each of the three cases.As shown,the costs of power are less
with the intertie.The reduction in the cost of power is typically
greater in the Fairbanks-Tanana Valley area than in the Anchorage-Cook
Inlet area because the Anchorage-Cook Inlet area will have a higher
percent of its generation supplied by steamp1ants which are more costly
than Sus itna.
31
of the Susitna project.The main reason that the intertie is not now
in place is that short-term benefits to the Anchorage area are quite
small;most of the short-term benefits for the intertie would occur
through reduced energy and power costs in the Fairbanks area.
The Alaska Power Administration.in the 1976 Interim Feasibility
Report.evaluated the provision of Susitna project power to Fairbanks
on a cost-of-service basis (see Appendix I,p.6-89 of the 1976 report).
This was a specific demonstration of feasibility of including Fairbanks
as part of the upper Susitna power market area.
Further verification of feasibility of the intertie is provided in
the new load-resource analyses and system cost analyses prepared for
the current studies.These general cases were analyzed:
Case 1.All future generating capacity assumed to be coal-fired steam
turbines without intertie.
Case 2.All future generating capacity assumed to be coal-fired steam
turbines with intertie.
Case 3.Future generating capacity to include the Susitna project
plus coal-fired steam plants as needed.This includes the
i nterti e.
The following table presents the costs of power in the year 2000
for each of the three cases.As shown,the costs of power are less
with the intertie.The reduction in the cost of power is typically
greater in the Fairbanks-Tanana Valley area than in the Anchorage-Cook
Inlet area because the Anchorage-Cook Inlet area will have a higher
percent of its generation supplied by steamp1ants which are more costly
than Sus itna.
31
COMPARISON OF POWER COSTS FOR YEAR 2000
(¢/kWh -0%inflation)
Anchorage Fairbanks
High Medium Low High Medium Low
Case 1 6.2 6.6 7.1 8.8 8.9 9.2
Case 2 6.1 6.2 6.2 8.0 8.4 8.8
Case 3 5.8 5.5 6.1 6.2 6.7 7.8
Following are the percent savings in total system costs between
1990 and 2011 for Cases 2 and 3 compared to Case 1,under the midrange
load forecast.
Case 2
Case 3
Anchorage
-0.4
-10.7
Fairbanks
-7.9
-28.1
Total
-1.4
-14.1
POWERPLANT SCHEDULING AND RISK REDUCTION
The risks associated with the overbuilding of powerplants is gen-
erally reduced by building small incremental additions to a system.
In other words,as closely as possible,load growth should be matched
as it occurs.The validity of this generalization increases as the
degree of confidence or certainty in load growth forecasts decreases.
This risk minimization is accompanied by an increase in economic costs,
however,since economies of scale are a significant factor in power-
plant costing.
The evaluation for the Susitna project recognized this risk factor
in that a range of area load growth possibilities and assumptions
required for their realization was developed.Those assumptions con-
sidered most likely were reviewed to form a most probable future
32
COMPARISON OF POWER COSTS FOR YEAR 2000
(¢/kWh -0%inflation)
Anchorage Fairbanks
High Medium Low High Medium Low
Case 1 6.2 6.6 7.1 8.8 8.9 9.2
Case 2 6.1 6.2 6.2 8.0 8.4 8.8
Case 3 5.8 5.5 6.1 6.2 6.7 7.8
Following are the percent savings in total system costs between
1990 and 2011 for Cases 2 and 3 compared to Case 1,under the midrange
load forecast.
Case 2
Case 3
Anchorage
-0.4
-10.7
Fairbanks
-7.9
-28.1
Total
-1.4
-14.1
POWERPLANT SCHEDULING AND RISK REDUCTION
The risks associated with the overbuilding of powerplants is gen-
erally reduced by building small incremental additions to a system.
In other words,as closely as possible,load growth should be matched
as it occurs.The validity of this generalization increases as the
degree of confidence or certainty in load growth forecasts decreases.
This risk minimization is accompanied by an increase in economic costs,
however,since economies of scale are a significant factor in power-
plant costing.
The evaluation for the Susitna project recognized this risk factor
in that a range of area load growth possibilities and assumptions
required for their realization was developed.Those assumptions con-
sidered most likely were reviewed to form a most probable future
32
condition.Therefore,the load forecast used represented a high degree
of confidence by the cross section of disciplines and agencies who
developed it.The evaluation further recognized the principle of load
growth matching when determining the most likely alternative thermal
plant in the absence of Susitna hydropower.Alternative thermal plants
were phased in to match the portion of load demand provided from Susitna.
For the initial years this means that only annual increases due to new
load were evaluated.,
As a further confirmation,an analysis of hydropower alternatives
indicates that economical sites are not available in sufficient quantity
to be comparable to Susitna.Small individual sites might be available,
but they would satisfy only a small portion of the market area demand.
Other sites with apparently acceptable power and economic capability
have been or will be precluded by land status designation.This
finding was supported by Alaska Power Administration's 1978 draft
report on Analysis of Potential Alternative Hydroelectric Sites to
Serve Railbelt Area and by the Corps of Engineers'Review of South-
central Alaska Hydropower Potential completed in January 1979.
33
condition.Therefore,the load forecast used represented a high degree
of confidence by the cross section of disciplines and agencies who
developed it.The evaluation further recognized the principle of load
growth matching when determining the most likely alternative thermal
plant in the absence of Susitna hydropower.Alternative thermal plants
were phased in to match the portion of load demand provided from Susitna.
For the initial years this means that only annual increases due to new
load were evaluated.,
As a further confirmation,an analysis of hydropower alternatives
indicates that economical sites are not available in sufficient quantity
to be comparable to Susitna.Small individual sites might be available,
but they would satisfy only a small portion of the market area demand.
Other sites with apparently acceptable power and economic capability
have been or will be precluded by land status designation.This
finding was supported by Alaska Power Administration's 1978 draft
report on Analysis of Potential Alternative Hydroelectric Sites to
Serve Railbelt Area and by the Corps of Engineers'Review of South-
central Alaska Hydropower Potential completed in January 1979.
33
DEMAND ESTIMATES
OMB COMMENT
The analysis of load growth should be more specific
with respect to:
a.Increasing use by consumers;and,
b.Increasing number of consumers.
c.Industrial growth,i.e.,where does Alaska's
comparative advantage lie outside the area of raw
materials and government functions?
FORECAST METHODOLOGY
In order to explore the causative factors of load growth in greater
detail,the method of forecasting has been changed in certain respects
from that which was used in the 1976 Interim F,easibility Report.The
Alaska Power Administration (APA)has used a simplified end-use model
to forecast future power requirements,augmented by trend analysis
and an econometric model.Total power demand has been categorized
into three primary end uses:the residential/commercial/industrial
loads supplied by electric utilities,the national defense installation
sector,and the self-supplied industrial component.
Those factors in each category that best explain historical trends
in energy use were identified.In the utility sector,those explanatory
variables are population and per capita use.Population was forecasted
with the help of a committee of experts using a regional econometric
34
-------------",!IO
DEMAND ESTIMATES
OMB COMMENT
The analysis of load growth should be more specific
with respect to:
a.Increasing use by consumers;and,
b.Increasing number of consumers.
c.Industrial growth,i.e.,where does Alaska's
comparative advantage lie outside the area of raw
materials and government functions?
FORECAST METHODOLOGY
In order to explore the causative factors of load growth in greater
detail,the method of forecasting has been changed in certain respects
from that which was used in the 1976 Interim F,easibility Report.The
Alaska Power Administration (APA)has used a simplified end-use model
to forecast future power requirements,augmented by trend analysis
and an econometric model.Total power demand has been categorized
into three primary end uses:the residential/commercial/industrial
loads supplied by electric utilities,the national defense installation
sector,and the self-supplied industrial component.
Those factors in each category that best explain historical trends
in energy use were identified.In the utility sector,those explanatory
variables are population and per capita use.Population was forecasted
with the help of a committee of experts using a regional econometric
34
-------------",!IO
model,while per capita use estimates are an extrapolation of past
trends adjusted to account for anticipated departures from those trends.
National defense needs are assumed to depend on the level of military
activity and the number of military personnel in the study area.Future
self-supplied industrial power requirements are based on explicit assump-
tions regarding future economic development and the energy needs associa-
ted with such development.
POPULATION AND ECONOMIC ACTIVITY FORECAST
The most important sector in terms of magnitude of electrical
energy use is the utility sector,and population is the key factor in
this sector's future power requirements.Population forecasts in turn,
are highly dependent upon assumptions of future economic activity.
Economic activity assumptions are also important because they have a
direct impact on energy requirements in the self-supplied industrial
sector.
The population and economic activity assumptions used in this fore-
cast are based on a draft report of the Economics Task Force,South-
central Alaska Water Resources Study,dated September 18,1978.The
report is entitled,"Southcentral Alaska's Economy and Population,
1965-2025:A Base Study and Projection."
The report was a joint effort of economists,planners,and agency
experts who were members of the Economics Task Force of the Southcentral
Alaska Water Resources Study (Level B).It;s being conducted by the
Alaska Water Study Committee,a joint committee of Federal and State
agencies,the Alaska Federation of Natives,the Alaska Municipal League,
35
model,while per capita use estimates are an extrapolation of past
trends adjusted to account for anticipated departures from those trends.
National defense needs are assumed to depend on the level of military
activity and the number of military personnel in the study area.Future
self-supplied industrial power requirements are based on explicit assump-
tions regarding future economic development and the energy needs associa-
ted with such development.
POPULATION AND ECONOMIC ACTIVITY FORECAST
The most important sector in terms of magnitude of electrical
energy use is the utility sector,and population is the key factor in
this sector's future power requirements.Population forecasts in turn,
are highly dependent upon assumptions of future economic activity.
Economic activity assumptions are also important because they have a
direct impact on energy requirements in the self-supplied industrial
sector.
The population and economic activity assumptions used in this fore-
cast are based on a draft report of the Economics Task Force,South-
central Alaska Water Resources Study,dated September 18,1978.The
report is entitled,"Southcentral Alaska's Economy and Population,
1965-2025:A Base Study and Projection."
The report was a joint effort of economists,planners,and agency
experts who were members of the Economics Task Force of the Southcentral
Alaska Water Resources Study (Level B).It;s being conducted by the
Alaska Water Study Committee,a joint committee of Federal and State
agencies,the Alaska Federation of Natives,the Alaska Municipal League,
35
the Municipality of Anchorage,the Southcentral region borough govern-
ments,and regional Native corporations.
The projections reported relied on two long-run econometric models
devised by economists from the University of Alaska Institute of Social
and Economic Research (ISER)and from the MIT-Harvard Joint Center for
Urban Studies with funding by the National Science Foundation's Man
in the Arctic Program (MAP).The two specific models used here were
modifications of the Alaska State and regional models developed under
that program.The models produced estimates of gross output,employ-
ment,income,and population for the years 1975-2000.Population and
employment were disaggregated and extrapolated to the year 2025 by
ISER researchers under Economics Task Force direction,and using Task
Force concensus methodology.The data required to run the model were
provided by various members of the Economics Task Force.Assumptions
were reviewed by the Task Force,and the model outputs and tentative
projections were reviewed for internal consistency and plausibility
by ISER researchers and by the Task Force.
The use of the econometric model requires a set of assumptions
related to the level and timing of development.The assumptions pri-
marily consist of time series on employment and output in certain of
the export-base industries and in government.
FORECAST RESULTS
The Level B population forecast for the Anchorage-Cook Inlet sub-
region was adopted by APA for estimating power requirements without
36
the Municipality of Anchorage,the Southcentral region borough govern-
ments,and regional Native corporations.
The projections reported relied on two long-run econometric models
devised by economists from the University of Alaska Institute of Social
and Economic Research (ISER)and from the MIT-Harvard Joint Center for
Urban Studies with funding by the National Science Foundation's Man
in the Arctic Program (MAP).The two specific models used here were
modifications of the Alaska State and regional models developed under
that program.The models produced estimates of gross output,employ-
ment,income,and population for the years 1975-2000.Population and
employment were disaggregated and extrapolated to the year 2025 by
ISER researchers under Economics Task Force direction,and using Task
Force concensus methodology.The data required to run the model were
provided by various members of the Economics Task Force.Assumptions
were reviewed by the Task Force,and the model outputs and tentative
projections were reviewed for internal consistency and plausibility
by ISER researchers and by the Task Force.
The use of the econometric model requires a set of assumptions
related to the level and timing of development.The assumptions pri-
marily consist of time series on employment and output in certain of
the export-base industries and in government.
FORECAST RESULTS
The Level B population forecast for the Anchorage-Cook Inlet sub-
region was adopted by APA for estimating power requirements without
36
any modification.APA applied projected statewide growth rates to the
Fairbanks-Tanana Valley area to develop population forecasts for that
region.Actual population growth will likely fall within the limits
established by the high and low forecasts.
UTILITY SECTOR
The midrange net generation forecast from 1977 to 1980 was based
on the average annual growth rate between 1973 and 1977.This rate was
adjusted upward and downward by 20 percent to establish the 1980 high
and low forecasts respectively.Beyond 1980,the high and low case net
generation is estimated by multiplying forecasted population by pro-
jected per capita use.Between 1973 and 1977,per capita use of elec-
tricity grew at an annual rate of 3.8 percent in Anchorage and 9.4
percent in Fairbanks.The lower Anchorage growth rate was adopted as
the basis of the per capita use trend.Increasing electrification is
assumed to be partly offset by increasing effectiveness of conservation
programs,resulting in a gradually slower rate of growth in per capita
use.
As a check on the validity of the per capita use projections,a
comparison was made with two regions of the Pacific Northwest.The
regions were selected for comparison on the basis of their similarity
in population and commercial/industrial characteristics to the rail-
belt area.The Pacific Northwest regions'present per capita use rates
of electrical power are significantly higher than those of the rail-
belt area.In fact,the current rates in the Pacific Northwest are
37
any modification.APA applied projected statewide growth rates to the
Fairbanks-Tanana Valley area to develop population forecasts for that
region.Actual population growth will likely fall within the limits
established by the high and low forecasts.
UTILITY SECTOR
The midrange net generation forecast from 1977 to 1980 was based
on the average annual growth rate between 1973 and 1977.This rate was
adjusted upward and downward by 20 percent to establish the 1980 high
and low forecasts respectively.Beyond 1980,the high and low case net
generation is estimated by multiplying forecasted population by pro-
jected per capita use.Between 1973 and 1977,per capita use of elec-
tricity grew at an annual rate of 3.8 percent in Anchorage and 9.4
percent in Fairbanks.The lower Anchorage growth rate was adopted as
the basis of the per capita use trend.Increasing electrification ;s
assumed to be partly offset by increasing effectiveness of conservation
programs,resulting in a gradually slower rate of growth in per capita
use.
As a check on the validity of the per capita use projections,a
comparison was made with two regions of the Pacific Northwest.The
regions were selected for comparison on the basis of their similarity
in population and commercial/industrial characteristics to the rail-
belt area.The Pacific Northwest regions'present per capita use rates
of electrical power are significantly higher than those of the rail-
belt area.In fact,the current rates in the Pacific Northwest are
37
comparable to those that are projected for the rail belt area in 1990.
Without doubt!Alaska exhibits a considerable potential for increased
electrification.
With the high and low population forecasts and with high!mid!and
low per capita use assumptions!six different net generation forecasts
were calculated.From these!the high population-high energy use and
the low population-low energy use combinations were used for the high
and low range net generation forecasts.The midrange utility sector
forecast came from averaging the high population-low energy use and the
low population-high energy use forecasts.
Peak load forecasts were calculated from projected net generation
using a 50 percent load factor.For the low range forecast,utility
sector peak load requirements are expected to increase from 667 mega-
watts (MW)in 1980 to 1,617 MW in the year 2000.Fifty-one percent
of that increase is due simply to population growth,while the remainder
of the increase is a result of increased per capita use.The compara-
ble increase in forecasted peak load requirements between 1980 and 2000
for the high range forecast is 3,087 MW.In this case!population
growth accounts for 43 percent of the increase!with the remainder
accounted for by changes in per capita use.
NATIONAL DEFENSE SECTOR
The forecast for this relatively minor sector is based on historical
data from Army and Air Force installations in the railbelt area.Zero
growth is assumed for the midrange forecast.For the high range,growth
at percent p~r year is assumed,while the low range forecast is based
on a decline of 1 percent annually.
38
________________________________________,II"
comparable to those that are projected for the rail belt area in 1990.
Without doubt!Alaska exhibits a considerable potential for increased
electrification.
With the high and low population forecasts and with high!mid!and
low per capita use assumptions!six different net generation forecasts
were calculated.From these!the high population-high energy use and
the low population-low energy use combinations were used for the high
and low range net generation forecasts.The midrange utility sector
forecast came from averaging the high population-low energy use and the
low population-high energy use forecasts.
Peak load forecasts were calculated from projected net generation
using a 50 percent load factor.For the low range forecast,utility
sector peak load requirements are expected to increase from 667 mega-
watts (MW)in 1980 to 1,617 MW in the year 2000.Fifty-one percent
of that increase is due simply to population growth,while the remainder
of the increase is a result of increased per capita use.The compara-
ble increase in forecasted peak load requirements between 1980 and 2000
for the high range forecast is 3,087 MW.In this case!population
growth accounts for 43 percent of the increase!with the remainder
accounted for by changes in per capita use.
NATIONAL DEFENSE SECTOR
The forecast for this relatively minor sector is based on historical
data from Army and Air Force installations in the railbelt area.Zero
growth is assumed for the midrange forecast.For the high range,growth
at percent p~r year is assumed,while the low range forecast is based
on a decline of 1 percent annually.
38
----------------------------------------,""
SELF-SUPPLIED INDUSTRIES SECTOR
This category of load is comprised of those existing industries
that generate their own power,along with all similar type facilities
expected to be constructed in the future.It is likely that such
industries would purchase power and energy if available at reasonable
cost.The specific assumptions for this sector are based on Battelle's
March 1978 report entitled Alaskan Electric Power,An Analysis of
Future Requirements and Supply Alternatives for the Railbelt Region.
The high range development forecast includes enlargement of existing
facilities as well as new industry.The new developments include an
LNG plant,refinery,coal gasification plant,mining and mineral
processing plants,timber industry,capital city,and some large energy
intensive industry.This set of assumptions coincides with the Level
B Study Task Force high case development assumptions with two excep-
tions.Coal gasification and an energy intensive industry were included
by APA because informed judgement indicates their definite potential.
Their impact on population and economic activity is relatively minor
but their effect on peak load requirements could be substantial.There-
fore,they have both been included in the development assumptions for
the high range forecast.
The midrange forecast is the same as the high range except that
the large energy intensive industry (aluminium smelter)is excluded.
The low range further excludes the new capital city.There is also
some reduction of peak load requirements of the mid and low range
cases.
39
SELF-SUPPLIED INDUSTRIES SECTOR
This category of load is comprised of those existing industries
that generate their own power,along with all similar type facilities
expected to be constructed in the future.It is likely that such
industries would purchase power and energy if available at reasonable
cost.The specific assumptions for this sector are based on Battelle's
March 1978 report entitled Alaskan Electric Power,An Analysis of
Future Requirements and Supply Alternatives for the Railbelt Region.
The high range development forecast includes enlargement of existing
facilities as well as new industry.The new developments include an
LNG plant,refinery,coal gasification plant,mining and mineral
processing plants,timber industry,capital city,and some large energy
intensive industry.This set of assumptions coincides with the Level
B Study Task Force high case development assumptions with two excep-
tions.Coal gasification and an energy intensive industry were included
by APA because informed judgement indicates their definite potential.
Their impact on population and economic activity is relatively minor
but their effect on peak load requirements could be substantial.There-
fore,they have both been included in the development assumptions for
the high range forecast.
The midrange forecast is the same as the high range except that
the large energy intensive industry (aluminium smelter)is excluded.
The low range further excludes the new capital city.There is also
some reduction of peak load requirements of the mid and low range
cases.
39
Alaska is not a heavily industrialized state nor is it expected to
be.The oil and gas industry is presently the dominating sector of the
State's GNP and will continue to be so for at least the balance of
the 20th century.This is the principle source of revenues for the
State and thus the driving force behind state programs for education,
local government assistance,welfare,and so on.Other important
industries are fisheries,forest products,and recreation-tourism.
The low and mid-range population estimates incorporate very modest
assumptions of industrial expansion based on pioneering of Alaskan
natural resources for the most part;the specific industrial assumptions
reflect proven sources of natural resources and projects that are well
along in the planning stages.
Extraction and processing of natural resources will undoubtedly
continue to be major aspects of the Alaska economy.Other important
aspects include business activities of Native Corporations and increas-
ing amount of land made available to State and private ownership.
Actions pending on the new National Parks,Refuges,and Wild and Scenic
Rivers will encourage further development of the recreation and tourism
industries.
As in most parts of the country,Alaska employment is not dominated
by the industrial sectors.Most jobs are in service industries,
commercial establishments,transportation,utilities,and government.
The new population estimate by ISER indicates that the distribution of
employment will not change appreciably.The anticipated growth in the
economy,emp 1oyment,and in power demands is pr-j ma ri ly in the non-
industrial sectors.
40
Alaska is not a heavily industrialized state nor is it expected to
be.The oil and gas industry is presently the dominating sector of the
State's GNP and will continue to be so for at least the balance of
the 20th century.This is the principle source of revenues for the
State and thus the driving force behind state programs for education,
local government assistance,welfare,and so on.Other important
industries are fisheries,forest products,and recreation-tourism.
The low and mid-range population estimates incorporate very modest
assumptions of industrial expansion based on pioneering of Alaskan
natural resources for the most part;the specific industrial assumptions
reflect proven sources of natural resources and projects that are well
along in the planning stages.
Extraction and processing of natural resources will undoubtedly
continue to be major aspects of the Alaska economy.Other important
aspects include business activities of Native Corporations and increas-
ing amount of land made available to State and private ownership.
Actions pending on the new National Parks,Refuges,and Wild and Scenic
Rivers will encourage further development of the recreation and tourism
industries.
As in most parts of the country,Alaska employment is not dominated
by the industrial sectors.Most jobs are in service industries,
commercial establishments,transportation,utilities,and government.
The new population estimate by ISER indicates that the distribution of
employment will not change appreciably.The anticipated growth in the
economy,emp 1oyment,and in power demands is pr-j ma ri ly in the non-
industrial sectors.
40
It should be noted that the rail belt area demands for electric
energy in 1977 were 2.7 billion kilowatt-hours,which is approaching
the firm energy capability of the Watana project.The load resource
analyses demonstrate full utilization of Watana energy essentially as
soon as it becomes available,even under the lower power demand case.
This basically leads to a finding that the upper Susitna justification
is not dependent on major industrial expansion in Alaska.
41
It should be noted that the rail belt area demands for electric
energy in 1977 were 2.7 billion kilowatt-hours,which is approaching
the firm energy capability of the Watana project.The load resource
analyses demonstrate full utilization of Watana energy essentially as
soon as it becomes available,even under the lower power demand case.
This basically leads to a finding that the upper Susitna justification
is not dependent on major industrial expansion in Alaska.
41
SENSITIVITY ANALYSIS
OMB COMMENT
Power demand should be subjected to a sensitivity
analysis to better assess the uncertainties in develop-
ment of such a large block of power.The typical utility
invests on the basis of an 8-10 year time horizon.The
Susitna plan has an 11-16 year horizon in face of risks
that loads may not develop and the option of wheeling
power to other markets is not available.It should be
noted that the power demand for Snettisham was unduly
optimistic when it was built.This resulted in delays
in installing generators.A similar error in a project
the size of Susitna would be much more costly and would
have a major adverse effect on the project's economics.
INTRODUCTION
The new power demand estimates and load/resource,economic,and
financial analyses presented in this report all provide a better basis
for examining these questions.In addition,there is need to review
some of the Snettisham project history to bring out similarities and
differences with the upper Susitna case.
SNETTISHAM REVIEW
The Snettisham Hydroelectric Project is located near Juneau,
Alaska and is now the main source of power for the greater Juneau area.
The project was authorized in 1962 on the basis of feasibility inves-
tigations by the Bureau of Reclamation,constructed by the Corps of
Engineers,and operated by the Alaska Power Administration.
The project was conceived as a two-stage development and construction
of the first,or Long Lake,stage was completed in late 1973 with first
42
•
SENSITIVITY ANALYSIS
OMB COMMENT
Power demand should be subjected to a sensitivity
analysis to better assess the uncertainties in develop-
ment of such a large block of power.The typical utility
invests on the basis of an 8-10 year time horizon.The
Susitna plan has an 11-16 year horizon in face of risks
that loads may not develop and the option of wheeling
power to other markets is not available.It should be
noted that the power demand for Snettisham was unduly
optimistic when it was built.This resulted in delays
in installing generators.A similar error in a project
the size of Susitna would be much more costly and would
have a major adverse effect on the project's economics.
INTRODUCTION
The new power demand estimates and load/resource,economic,and
financial analyses presented in this report all provide a better basis
for examining these questions.In addition,there is need to review
some of the Snettisham project history to bring out similarities and
differences with the upper Susitna case.
SNETTISHAM REVIEW
The Snettisham Hydroelectric Project is located near Juneau,
Alaska and is now the main source of power for the greater Juneau area.
The project was authorized in 1962 on the basis of feasibility inves-
tigations by the Bureau of Reclamation,constructed by the Corps of
Engineers,and operated by the Alaska Power Administration.
The project was conceived as a two-stage development and construction
of the first,or Long Lake,stage was completed in late 1973 with first
42
•
commercial power to Juneau in December 1973.The second,or Crater
Lake,stage was to be added when power demands dictated.
Juneau remains an isolated power market area.Difficult terrain
and long distance have thus far prevented electrical interconnection
with other southeast Alaska communities and neighboring areas of Canada;
however,such interconnections may prove feasible within the next 15
to 20 years.The project planning and justification was premised on
service only to the greater Juneau area.
The Snettisham authorization was based on power demand estimates
done in 1961 by the Alaska District,Bureau of Reclamation (now Alaska
Power Administration).The estimates were based on actual power use
through 1960 and projections to the year 1987.The outlook at that
time was that the first stage construction would be completed in 1966
and that total project capability would not be needed until 1987.The
actual 1977 energy load was 112,197 megawatt-hours or 81 percent of
the 1977 estimate forecasted in 1961 on the basis of historical records
through 1960.
The inherent flexibility of a staged project proved to be very bene-
ficial in the case of Snettisham.APA made periodic updates of the
power demand estimates during construction of the Long Lake stage.
For several years,these forecasts indicated a need to proceed with
the Crater Lake stage construction immediately on completion of the
Long Lake stage.The Corps of Engineers construction schedules and
budget requests,based on the APA power demand estimates,anticipated
43
commercial power to Juneau in December 1973.The second,or Crater
Lake,stage was to be added when power demands dictated.
Juneau remains an isolated power market area.Difficult terrain
and long distance have thus far prevented electrical interconnection
with other southeast Alaska communities and neighboring areas of Canada;
however,such interconnections may prove feasible within the next 15
to 20 years.The project planning and justification was premised on
service only to the greater Juneau area.
The Snettisham authorization was based on power demand estimates
done in 1961 by the Alaska District,Bureau of Reclamation (now Alaska
Power Administration).The estimates were based on actual power use
through 1960 and projections to the year 1987.The outlook at that
time was that the first stage construction would be completed in 1966
and that total project capability would not be needed until 1987.The
actual 1977 energy load was 112,197 megawatt-hours or 81 percent of
the 1977 estimate forecasted in 1961 on the basis of historical records
through 1960.
The inherent flexibility of a staged project proved to be very bene-
ficial in the case of Snettisham.APA made periodic updates of the
power demand estimates during construction of the Long Lake stage.
For several years,these forecasts indicated a need to proceed with
the Crater Lake stage construction immediately on completion of the
Long Lake stage.The Corps of Engineers construction schedules and
budget requests,based on the APA power demand estimates,anticipated
43
start of construction on Crater Lake in FY 77.Major factors in these
forecasts were plans for a new pulp mill in the Juneau area and for
an iron ore mining and reduction facility in the vicinity of Port
Snettisham.Neither of these developments were anticipated at the
time of authorization.Both of these resource developments failed to
materialize,and this resulted in a substantial reduction in the APA
power demand estimate and a decision in late 1975 to defer the Crater
Lake construction start.
Many other factors influenced Juneau area power demands and utiliza-
tion of project power.Of particular concern at the moment is impact
of Alaska's capital move initiative.This would certainly change use
of project power,with the most likely outcome that the community would
move more quickly into an all-electric mode (space heating and electric
vehicles appear particularly attractive in this area),and industrial
use of power would increase through economic diversification.
The key points of the Snettisham review are:
1.The project was planned and authorized with intent to handle
growth in area power requirements for a 20-year period.
2.The load forecasts used as a basis for authorization were reason-
ably accurate.
3.The actual use of project power may turn out to be substantially
different than originally anticipated.
4.The flexibility of staged projects was used to great advantage.
5.The outlook for financial viability appears excellent at this
time.
44
...
________________--------.JIl>
start of construction on Crater Lake in FY 77.Major factors in these
forecasts were plans for a new pulp mill in the Juneau area and for
an iron ore mining and reduction facility in the vicinity of Port
Snettisham.Neither of these developments were anticipated at the
time of authorization.Both of these resource developments failed to
materialize,and this resulted in a substantial reduction in the APA
power demand estimate and a decision in late 1975 to defer the Crater
Lake construction start.
Many other factors influenced Juneau area power demands and utiliza-
tion of project power.Of particular concern at the moment is impact
of Alaska's capital move initiative.This would certainly change use
of project power,with the most likely outcome that the community would
move more quickly into an all-electric mode (space heating and electric
vehicles appear particularly attractive in this area),and industrial
use of power would increase through economic diversification.
The key points of the Snettisham review are:
1.The project was planned and authorized with intent to handle
growth in area power requirements for a 20-year period.
2.The load forecasts used as a basis for authorization were reason-
ably accurate.
3.The actual use of project power may turn out to be substantially
different than originally anticipated.
4.The flexibility of staged projects was used to great advantage.
5.The outlook for financial viability appears excellent at this
time.
44
...
________________--------.JIl>
IMPLICATIONS FOR SUSITNA
First,the typical planning horizon for utility investments is in
excess of 8 to 10 years.This is evidenced by experiences dating from
about 1970 on the time required to plan,obtain necessary permits or
authorizations,find financing,and then bui1d new powerplants and
major transmission facilities.The 8 to 10 years is specifically much
too short for nuclear,coal,or hydro plants or for major transmission
lines.
A 20-year planning horizon is more appropriate with careful checks
at each step in the process and business-like decisions to shift con-
struction schedules if conditions (demands)change.The Snettisham
experience is very positive in this light.
The Susitna project is similar in that project investment is keyed
to three major stages of development:transmission interconnection,
Watana,and then Devil Canyon.The commitment of construction funds
for Watana would be needed in 1984 to have power-on-line by 1994.If
conditions in 1984 indicate the need to defer the project,it shou1d
be deferred.Similarly,start of actual construction on Devil Canyon
can and should be based on conditions that actua11y prevail at the time
the decision is made.
The degree of uncertainty for upper Susitna is greater in one respect
than was the case for Snettisham because of higher interest costs and
larger total investment.At the same time,sensitivity to change in
demands ;s much less for Sus;tna because of its large and diversified
45
IMPLICATIONS FOR SUSITNA
First,the typical planning horizon for utility investments is in
excess of 8 to 10 years.This is evidenced by experiences dating from
about 1970 on the time required to plan,obtain necessary permits or
authorizations,find financing,and then bui1d new powerplants and
major transmission facilities.The 8 to 10 years is specifically much
too short for nuclear,coal,or hydro plants or for major transmission
lines.
A 20-year planning horizon is more appropriate with careful checks
at each step in the process and business-like decisions to shift con-
struction schedules if conditions (demands)change.The Snettisham
experience is very positive in this light.
The Susitna project is similar in that project investment is keyed
to three major stages of development:transmission interconnection,
Watana,and then Devil Canyon.The commitment of construction funds
for Watana would be needed in 1984 to have power-on-line by 1994.If
conditions in 1984 indicate the need to defer the project,it shou1d
be deferred.Similarly,start of actual construction on Devil Canyon
can and should be based on conditions that actua11y prevail at the time
the decision is made.
The degree of uncertainty for upper Susitna is greater in one respect
than was the case for Snettisham because of higher interest costs and
larger total investment.At the same time,sensitivity to change in
demands ;s much less for Sus;tna because of its large and diversified
45
power market area.There are many more ways that Susitna project
power could be effectively utilized in the event that traditional
utility power markets are smaller than anticipated at the present.
The whole field of oil and gas fuel displacement could be explored
with emphasis on electric heat for office buildings,electric vehicles,
and electrification of oil and gas pipeline pump and compressor stations.
Further,the Susitna project does not have as many uncertainities
in terms of environmental questions as would equivalent power supplies
from coal or nuclear plants.Uncertainties regarding air quality are
particularly relevant for any large Alaskan coal-fired powerplants.
CURRENT EVALUATION
Power demands were estimated for high,medium,and low cases to year
2025 assuming logical variations in population and energy use per capita.
The projections reflect per capita energy use based on detailed studies
of 1970-1977 data from both the Anchorage and Fairbanks areas.The
projections considered variations in per capita use ranging from increased
use of electricity in the home to anticipated effects of conservation.
The project's economic justification was tested to determine,
among other things,its degree of sensitivity to variations in load
growth.The circumstance potentially most damaging to the economic
viability of the project entails a sudden decrease in the rate of load
growth immediately after the project is completed.The analysis
indicated that the annual rate of load growth would have to fall to
0.8 percent before project costs exceed benefits.This rate should be
46
power market area.There are many more ways that Susitna project
power could be effectively utilized in the event that traditional
utility power markets are smaller than anticipated at the present.
The whole field of oil and gas fuel displacement could be explored
with emphasis on electric heat for office buildings,electric vehicles,
and electrification of oil and gas pipeline pump and compressor stations.
Further,the Susitna project does not have as many uncertainities
in terms of environmental questions as would equivalent power supplies
from coal or nuclear plants.Uncertainties regarding air quality are
particularly relevant for any large Alaskan coal-fired powerplants.
CURRENT EVALUATION
Power demands were estimated for high,medium,and low cases to year
2025 assuming logical variations in population and energy use per capita.
The projections reflect per capita energy use based on detailed studies
of 1970-1977 data from both the Anchorage and Fairbanks areas.The
projections considered variations in per capita use ranging from increased
use of electricity in the home to anticipated effects of conservation.
The project's economic justification was tested to determine,
among other things,its degree of sensitivity to variations in load
growth.The circumstance potentially most damaging to the economic
viability of the project entails a sudden decrease in the rate of load
growth immediately after the project is completed.The analysis
indicated that the annual rate of load growth would have to fall to
0.8 percent before project costs exceed benefits.This rate should be
46
compared to the annual growth rates of 12.7 percent in Anchorage and
10.5 percent in Fairbanks between 1973 and 1977 and to the low range
forecast for the post-1994 period of 4.2 percent.
The load/resource and cost analysis provided system costs for com-
parison of cases both with and without the Susitna project.The analysis
also compared the power demands to the resources required to determine
sizes and timing of new plants.Even under the most conservative load
growth condition,1,500 MW is needed to meet the continued Anchorage-
Fairbanks demands during the 1990·s;this is roughly the capability
of the Susitna project.
Cost of system power estimates indicate that,in the medium case
for the year 2000,Anchorage costs are 5.5¢/kWh or 17 percent less
than without Susitna.For Fairbanks the difference is much larger,
6.7¢/kWh or 25 percent less than without Susitna.
Examination of the system cost on an annual basis reveals the case
II with li Susitna is cheaper than the II without li Susitna case for each year
except the first few years after Watana comes on line.
It should be noted that in the low energy use case the total system
cost for the rai1be1t area during the period from 1990 to 2011 amounts
to $1.1 million less with Susitna than without the project.The
difference is even larger in·the medium and high cases.The combined
Anchorage-Fairbanks cash savings for the same period based on the
medium power use estimate is over $2 billion.~
47
compared to the annual growth rates of 12.7 percent in Anchorage and
10.5 percent in Fairbanks between 1973 and 1977 and to the low range
forecast for the post-1994 period of 4.2 percent.
The load/resource and cost analysis provided system costs for com-
parison of cases both with and without the Susitna project.The analysis
also compared the power demands to the resources required to determine
sizes and timing of new plants.Even under the most conservative load
growth condition,1,500 MW is needed to meet the continued Anchorage-
Fairbanks demands during the 1990·s;this is roughly the capability
of the Susitna project.
Cost of system power estimates indicate that,in the medium case
for the year 2000,Anchorage costs are 5.5¢/kWh or 17 percent less
than without Susitna.For Fairbanks the difference is much larger,
6.7¢/kWh or 25 percent less than without Susitna.
Examination of the system cost on an annual basis reveals the case
II with li Susitna is cheaper than the II without li Susitna case for each year
except the first few years after Watana comes on line.
It should be noted that in the low energy use case the total system
cost for the rai1be1t area during the period from 1990 to 2011 amounts
to $1.1 million less with Susitna than without the project.The
difference is even larger in·the medium and high cases.The combined
Anchorage-Fairbanks cash savings for the same period based on the
medium power use estimate is over $2 billion.~
47
LOCATIONMAPPLATEALASKADISTRICT,CORPSOFENGINEERSANC>lORAGE.AlAS!<AFEBRUARY1979UPPERSUSITNARIVERBASINSELECTED2DAMPLANGENERALPLANSOUTHCENTRALRAILBELTAREA.ALASKASUPPLEMENTALFEASIBILITYSTUDYLQ~eLouiseRoadToGI,,,Hi'hWOY~~.~--~--'"w>'"O(V'lCAOiYONDo,,,,,,c..,.1..'0....'..obo'<.""",!~.ElftOhOM,of..10mo""........,.UPPERSUSITNARIVERPROFILESCALEoi""""""""'5F=~~'O~"'~15~="i2~oMilesWQfanaAccessRoad{Proposed)RIVERMILES120-290_GOLDJ.CREEK•(.~~,~~\_/"1,,'""\V~_/'-J]l]]JJ.~~c'-<-,(f]~.O\'(j><::-,,,:0'~.,0,,0J~CC",,'<-q::...,.,,""(-,,00J',wr!J1032-79LOCATIONMAPPLATEALASKADISTRICT,CORPSOFENGINEERSANC>lORAGE.AlAS!<AFEBRUARY1979UPPERSUSITNARIVERBASINSELECTED2DAMPLANGENERALPLANSOUTHCENTRALRAILBELTAREA.ALASKASUPPLEMENTALFEASIBILITYSTUDYLQ~eLouiseRoadToGI,,,Hi'hWOY~~.~--~--'"w>'"O(V'lCAOiYONDo,,,,,,c..,.1..'0....'..obo'<.""",!~.ElftOhOM,of..10mo""........,.UPPERSUSITNARIVERPROFILESCALEoi""""""""'5F=~~'O~"'~15~="i2~oMilesWQfanaAccessRoad{Proposed)RIVERMILES120-290_GOLDJ.CREEK•(.~~,~~\_/"1,,'""\V~_/'-J]l]]JJ.~~c'-<-,(f]~.O\'(j><::-,,,:0'~.,0,,0J~CC",,'<-q::...,.,,""(-,,00J',wr!J1032-79
ALASKADISTRICT.CORPSOFENGINEERSUlClfOll:.GE•.-.IoSKASOUTHCENTRALRAILBELTAREA.ALASKASUPPLEMENTALFEASIBILITYSTUDYUPPERSUSITNARIVERBASINWATANADAMSITEEXPLORATIONPLANlllj.]]JJ]]~Jj"""<00<1INV.NO.DACW85·PLATE2U.S.ARMYALASKADISTRICT.CORPSOFENGINEERSUlClfOll:.GE•.-.IoSKASOUTHCENTRALRAILBELTAREA.ALASKASUPPLEMENTALFEASIBILITYSTUDYUPPERSUSITNARIVERBASINWATANADAMSITEEXPLORATIONPLANlllj.]]JJ]]~Jj"""<00<1INV.NO.DACW85·PLATE2U.S.ARMY
\---'I/c,,f',,,\~_.2.\00·.-eOO-=',~o17001800'900"2000\..,)~~~PLATE3= • =!I!sC.LE'"~E(TFEBRUARY1919ALASKADISTRICT.COflPSOfENGINEERSUPPERSUSITNARIVERBASINWATANADAMDETAILPLANSQUTHCENTRALRAILBELTAREA,ALASKASUPPLEMENTALFEASIBILITYSTUDYo~(!~~,~\0~'"'~SAOO~SPILLWAYL,,~<U000=•GC\lC?=00~~\500~.OOO~2\OON:5223000BASEDONAERIALPHOTOGRAPHYDATUMISMEANSEALEVEL(MSUNOTES:I.TOPOGRAPHICCONTOURSAREDATED10JUNE1978.VERTICAL]]]J1r1"J11,Jl\---'I/c,,f',,,\~_.2.\00·.-eOO-=',~o17001800'900"2000\..,)~~~PLATE3=•=!I!sC.LE'"~E(TFEBRUARY1919ALASKADISTRICT.COflPSOfENGINEERSUPPERSUSITNARIVERBASINWATANADAMDETAILPLANSQUTHCENTRALRAILBELTAREA,ALASKASUPPLEMENTALFEASIBILITYSTUDYo~(!~~,~\0~'"'~SAOO~SPILLWAYL,,~<U000=•GC\lC?=00~~\500~.OOO~2\OON:5223000BASEDONAERIALPHOTOGRAPHYDATUMISMEANSEALEVEL(MSUNOTES:I.TOPOGRAPHICCONTOURSAREDATED10JUNE1978.VERTICAL]]]J1r1"J11,Jl
1-IBOO~~w-1700ul-1600-1500-1400-1900...J00:Ii-20ao-2100-2200,1800IMPERVIOUSFILL,1600,\400EL.l5502117COFFERDAM(SEEDETAILA),1200ROCKFllLROCKLINE12'COARSEFILTER,,8001000TO$DAM,600COFFERDAM-DETAILA2.25TYP_EACHSIDE~~I,JJ----"M!!!IN"''''M>eUM''-!P,,O''W!!E''R'--':P'''OO'''Lo..<E,<,Lo!-1,,9,,40,,--24'COARSEFILTER""~---EL.2050MAXIMUMPOOLEL.2185,,200400WIDTH)(,MPERV,OUSCORE~FINEFILTER--'._PERVIOUSFlL!jIIoDiSTANCEINFEETTYPICALSECTION,200EL.,40024'COARSEFILTER,600,'00,\000,1200,1400SANDYGRAVELCOFFERDAM(SEEDETAILA)_~2:::::::::::=:!~~~E~L=_15~00~~;:;1.5::::::II12'COARSEFILTER]]1,IJ]111k~~.E~~--EL.1875_----POWERINTAKESTRUCTURE,360034003200UPPERSUSITNARIVERBASINWATANADAMSECTIONSSOUTHCENTRALRAILBELTAREA,ALASI(ASUPPLEMENTALFEASIBILITYSTUDY,2800~DIVERSIONTUNNEL#:I,30'DIA.(NOTTOSCALE),2600It.DIVERSIONTUNNEL1t2,30'DIA.(NOTTOSCALE1,2400,22002000,1800..EXISTINGGROUNDDAMCRESTEl.21951600DISTANCEINFEET14001200RETAININGWALL1000b!'j;:..--STAIRWELLELEVATORSHAFT,800ROCKEXCAVATIONBENEATHCORE600STRIPPEDTOSURFACEOFROCK400GLACIALTILL2400-2300-2100-2000-1900-1800-~00~~1700-ww~~z1600-Q~~w~1500-w1400-,,02001j~JJrJJJWATANADAMANDINTAKESTRUCTURELOOKINGDOWNSTREAM100'O'100'~oo'•!!I';""~"'CSC~lE'1"·100'·o·At..ASI(ADISTRICT,CORPSOFENGINEERSFEBRUARY1979PLATE41-IBOO~~w-1700ul-1600-1500-1400-1900...J00:Ii-20ao-2100-2200,1800IMPERVIOUSFILL,1600,\400EL.l5502117COFFERDAM(SEEDETAILA),1200ROCKFllLROCKLINE12'COARSEFILTER,,8001000TO$DAM,600COFFERDAM-DETAILA2.25TYP_EACHSIDE~~I,JJ----"M!!!IN"''''M>eUM''-!P,,O''W!!E''R'--':P'''OO'''Lo..<E,<,Lo!-1,,9,,40,,--24'COARSEFILTER""~---EL.2050MAXIMUMPOOLEL.2185,,200400WIDTH)(,MPERV,OUSCORE~FINEFILTER--'._PERVIOUSFlL!jIIoDiSTANCEINFEETTYPICALSECTION,200EL.,40024'COARSEFILTER,600,'00,\000,1200,1400SANDYGRAVELCOFFERDAM(SEEDETAILA)_~2:::::::::::=:!~~~E~L=_15~00~~;:;1.5::::::II12'COARSEFILTER]]1,IJ]111k~~.E~~--EL.1875_----POWERINTAKESTRUCTURE,360034003200UPPERSUSITNARIVERBASINWATANADAMSECTIONSSOUTHCENTRALRAILBELTAREA,ALASI(ASUPPLEMENTALFEASIBILITYSTUDY,2800~DIVERSIONTUNNEL#:I,30'DIA.(NOTTOSCALE),2600It.DIVERSIONTUNNEL1t2,30'DIA.(NOTTOSCALE1,2400,22002000,1800..EXISTINGGROUNDDAMCRESTEl.21951600DISTANCEINFEET14001200RETAININGWALL1000b!'j;:..--STAIRWELLELEVATORSHAFT,800ROCKEXCAVATIONBENEATHCORE600STRIPPEDTOSURFACEOFROCK400GLACIALTILL2400-2300-2100-2000-1900-1800-~00~~1700-ww~~z1600-Q~~w~1500-w1400-,,02001j~JJrJJJWATANADAMANDINTAKESTRUCTURELOOKINGDOWNSTREAM100'O'100'~oo'•!!I';""~"'CSC~lE'1"·100'·o·At..ASI(ADISTRICT,CORPSOFENGINEERSFEBRUARY1979PLATE4
lll11l'r1JJJJJJ1J'-.I"III,~'",,,SOUTHCENTRALRAILBELTAREA,ALASKASUPPLEMENTALFEASIBILITYSTUDYUPPERSUSITNARIVERBASINDEVILCANYONDAMCONCRETEGRAVITYDAMDETAILPLANALASKADISTFHCT,CORPSOFENGINEERSAHC>«)RAGE>ALASI<AFEBRUARY1979PLATE5lll11l'r1JJJJJJ1J'-.I"III,~'",,,SOUTHCENTRALRAILBELTAREA,ALASKASUPPLEMENTALFEASIBILITYSTUDYUPPERSUSITNARIVERBASINDEVILCANYONDAMCONCRETEGRAVITYDAMDETAILPLANALASKADISTFHCT,CORPSOFENGINEERSAHC>«)RAGE>ALASI<AFEBRUARY1979PLATE5
~A>lJSOFDAM126'r"IEL1455~;;:.:;-.~.~~~'...El.1410~.;:~.:'0.75f~TYPICALNON-OVERFLOWSECTION'0'dWI'100':wi!!_..cSCJln,.,,0'-o·PENSTOCK(Ii.TURBINEH.e.6.7fL.925....MAx,J.W.fL.924~~;;:::=::::::::::lG-~~~ST~O=PLOGSLOT,fL.850TRANSFORMRCHAMBER~P.PWEAfPLANTSECTIONTHRUPENSTOCKANDPOWERPLANTSCALE:Iw.IOQ'EL1410~i",-ITOPOFDAMEL.1455,',PENSTOCK--+-+-GATE~~__::~~E~24"alA~/-~fMlf;c~,~,..~~.~'-"MAX,POOLfL.1450AXISOFDAM1455CRESTEL1412.5fL.1075SPILLWAYSECTION200'1..•1JllUPPERSUSITNARIVERBASINDEVILCANYONDAMCONCRETEGRAVITYDAMELEVATIONANDSECTIONSsaUTHCENTRAlRAILBELTAREA.ALASI(ASUPPLEMENTALfEASIBILITYSTUDYFILL...........FILTER-rORIGIN~ROUNO---~.!.,'I,50"'_IIULI_r·40'-0'CANYONAUXILIARYEARTHFILLDAMDEVILELSELECTGRAVELDRAIN-_--;0'<:__.1FINEFllTER--"-'3r.:~~":'~---'T77}"',EL8431455/PLUGSECTIONL200METALTRASHRACKINTAKESTRUCTURETOPOFDAMIi.fL.1075LOWLEVELSLUICESFOREMERGENCYDRAWOOWNI,,,/,~"__-jJH.f-c__J+Ic",,-_'llINTAKEfL.U50//,'aooIdooELEVATORTOWER\UPSTREAMELEVATIONDEVELOPEDALONGitOFDAMSCALE:I".100',,EL833.5/MAXPOOLElL1/v~,,,--\/.,/"-/\/~~---_/\----..,//..-/"\--\..\EL1085jd'<-,----r,,"-"26'OIA.DIVERSION__.~TUNNELL.J//fTOPOfWALL//El.875EfL.975ASSUMEDEXCAVATIONLINEMONOLITHJOINTSORIGINALGROUNDSURFACE)1.>I"JJJJJDIVERSONTUNNELPROFILESCALE:I.10041....$1(...DISTRICT,\Xll'IPSOfENGINEERS.He_AGE.Al4Sl<.FEBRUARY1979PLATE6~A>lJSOFDAM126'r"IEL1455~;;:.:;-.~.~~~'...El.1410~.;:~.:'0.75f~TYPICALNON-OVERFLOWSECTION'0'dWI'100':wi!!_..cSCJln,.,,0'-o·PENSTOCK(Ii.TURBINEH.e.6.7fL.925....MAx,J.W.fL.924~~;;:::=::::::::::lG-~~~ST~O=PLOGSLOT,fL.850TRANSFORMRCHAMBER~P.PWEAfPLANTSECTIONTHRUPENSTOCKANDPOWERPLANTSCALE:Iw.IOQ'EL1410~i",-ITOPOFDAMEL.1455,',PENSTOCK--+-+-GATE~~__::~~E~24"alA~/-~fMlf;c~,~,..~~.~'-"MAX,POOLfL.1450AXISOFDAM1455CRESTEL1412.5fL.1075SPILLWAYSECTION200'1..•1JllUPPERSUSITNARIVERBASINDEVILCANYONDAMCONCRETEGRAVITYDAMELEVATIONANDSECTIONSsaUTHCENTRAlRAILBELTAREA.ALASI(ASUPPLEMENTALfEASIBILITYSTUDYFILL...........FILTER-rORIGIN~ROUNO---~.!.,'I,50"'_IIULI_r·40'-0'CANYONAUXILIARYEARTHFILLDAMDEVILELSELECTGRAVELDRAIN-_--;0'<:__.1FINEFllTER--"-'3r.:~~":'~---'T77}"',EL8431455/PLUGSECTIONL200METALTRASHRACKINTAKESTRUCTURETOPOFDAMIi.fL.1075LOWLEVELSLUICESFOREMERGENCYDRAWOOWNI,,,/,~"__-jJH.f-c__J+Ic",,-_'llINTAKEfL.U50//,'aooIdooELEVATORTOWER\UPSTREAMELEVATIONDEVELOPEDALONGitOFDAMSCALE:I".100',,EL833.5/MAXPOOLElL1/v~,,,--\/.,/"-/\/~~---_/\----..,//..-/"\--\..\EL1085jd'<-,----r,,"-"26'OIA.DIVERSION__.~TUNNELL.J//fTOPOfWALL//El.875EfL.975ASSUMEDEXCAVATIONLINEMONOLITHJOINTSORIGINALGROUNDSURFACE)1.>I"JJJJJDIVERSONTUNNELPROFILESCALE:I.10041....$1(...DISTRICT,\Xll'IPSOfENGINEERS.He_AGE.Al4Sl<.FEBRUARY1979PLATE6