Loading...
HomeMy WebLinkAboutAPA2367JUl a 5 - SOUTHCENTRAl RAIlBELT AREA.ALASKA UPPER SUSITNA RIVER BASIN SUPPLEMENTAL FEASIBILITY REPORT APPENDIX -PART II Section G-Marketability Analysis Section H -Transmission System Section I -Environmental Assessment for Transmiss on System Prepared by the Alaska District,Corps of Engineers Department of the ArmY February 1979 SECTION G MARKETABILITY ANALYSIS United States Department of Energy Alaska Power Administration (j).:".';,..•.......-.~~c. , Department Of Energy Alaska Power Administration P.O.Box 50 Juneau.Alaska 99802 Colonel George R.Robertson District Engineer Corps of Engineers P.O.Box 7002 Anchorage,Al~ska 99510 Dear Colonel Robertson: April 2,1979 This is Alaska Power Administration's new power market report for the Upper Susitna Project.It's an update of the previous power market ana1ys~s provided for the Corps'1976 Interim Feasibility report. The power market report includes:a new set of load projections for the Railbelt area through year 2025 and a review of alternative sources of power.Load/resource and total power system cost analyses were prepared for different scenarios under various assumptions to determine effects on power rates. Under the assumptions made for this report,Alaska Power Administration determines that the UpperSusitna Project is feasible from a power marketing standpoint. A draft of this report was circulated to the area utilities and con- cerned State officers for informal review and comment.Comments have been incorporated and the letters of comments are appended. Sincerely, "';" .'.-',/',;C'-:,i.C~'i&'2...----~ Robert J.Cross Administrator "llII\••OtI CON'TENTS Introduction ,.. National Defense ".. Data '.. Al ternatives Considered ••••••••••••••••••••••••••••••••• PAGE NO. 1 3 7 7 8 10 10 12 13 13 15 16 16 16 23 33 33 33 3~ 33 33 36 36 38 38 55 61 63 63 63 63 63 64 64 67 70 70 71 71 71 71 72 73 ... ...... ...... ...... ........ ....".. Lo cat ion._ -1 0 •••• Capaci ty , '. Inves tment Costs -. Coal Fuel Cost and Availability . Cost of Power •••.••••••••••.•••••••••••••••••••• Comparative Cost of Power (FERC)••••.••••••••••• Oil and Natural Gas •••••••••••.•••••.•••••••••••••••• Hydro '--- . Cri teria . Summary . Single Large Capacity Sites •••••••••••••••.••••• Combinations of Small Capacity Sites •••••••••••• Introduction '1'1 .. PART VI -ALTERNATIVE·POWER SOURCES ••••••••••••••••••••••• Utili ty •••••••••.•••••••••••••••••••••••••• National Defense •••••••••••••••••••••••••.• Self-Supplied Industry ••••••••••••••••••••• Estimate of Future Demands •••••••••••••••••.•••• Comparison With Other Forecasts •••••••••••'•.•••• Load Dis tribution •••••••••••••••••••••••••••••..•••••••• Capaci ty Requirements ••••••••••••••••••••••••••••••••••• Population .. Utility _. Analysis PART V -PO~R REQUIREMENTS •••••••••••••••.••••••••••••••• PART II -S~RY .. PART III -POWER MARKET AREAS •••••••••••••••••••••••••••.• Anchorage-Cook Inlet ••••••.••••••••••••••••••••••••••••• Fairbanks-Tanana Valley ••-••••••••••••••••••••••••••••••• Self-Supplied Industry ••••••••••••••••••••••••••••••• Energy &Power Demand Forecasts •••.•••.•••••••••.••••••• Assumptions and Methodology . PART IV -'EXISTING POWER SYSTEMS •••••••••••••••••••••••••• Utility Systems and Service Areas ••.•••••••••••••••••.•• National Defense Power Systems •••••••••••••••••••••••••• Indus trial Power Sys tems •••••••••••••••••••••••••••••••• Existing Generation Capacity •••••••••••••••••••••••••••• P 1anned Generation Capacity ••••••••.•••••••••••••.•••••• PART I -INTRODUCTION ••••••••••..••••••••••••••.•••••••••• TITLE i __---_"__W_~--_ CONTENTS (Continued) 86 89 8?0/ W ~ 90J 91J. 91 97 0/77 9if3 1~ 11<W ~@~m 105 106 106 108 j@§ i@§ !6§ 10§ He H~ 116 Il7 Page No.n is] 7~3 73 3 is 4 74 75 iSS ilj5 71j7 ilfJ 799 71ft 79 86 P .~t;;:P ¥-ce!Q..e~'t.ts~"r-'•It :Ill ••!.,!..• ,__••••••••'"•••~Q 011 ••III •••1l'II'••011 •It ••• A ..,,-"~'-r'.LNi'u.'\IC.LAL ft..NAL'{Sl.S ••.••,••o'.,"••••••••••••••• 11arkE;tl~A+..p.r.ni..ect.T.F..o.:\>re.r •••••••,,,.,,•••,,,,,.,,"••,PAK:r X -l,.J.~AN.L;rNL :Alt8.LY~l.S •D"••0 •11 III . 'C,<:;t"0 '"'''''W'0"';1:~a'r":et'fQor"~QJ~'ec't''Po'w~e'~•••••,.,"",••,...,"...,.".•".,,,.,••t\..L •••••••••••••001t •••••••l;l'e •••••••,..,';~~~'[a<5t.,c,:?"n.,'·e tA .....:;j-l'p;::;1-of ...."".(";o"-t''0,,"'J~-~'",__,.,.._..,.~.,.C"•••.••",,,.,,',.•,.,,.,••,.,,••••"ti S .<l..I,.0 ~c '-,.,••••'0'••••••••0 ••••••••••'"•••••••••••••• ""Jwer lta·(K.~tl.na '."ons:Ltlf,,_;catJ "",,,,".".•"",.,,,.,., A:verap"€,R,..e uet~nUJ;1..ar..J..on ..••'..••..•• •••••••••..•.••..•....••'.••..•'.'Barkeq ·..."i;'(',..:.ct~a '·'Orf!.iiI::"i-'"Trr,n,;."',"r -,'.~·v 1 .,.~•.Power 1:1ar.1te.tlI1g.a onsJ".ae-r<t.tf6tfs'·.;-.~.•..;'...-;•.-';'•.'.'.'.':,'•.'~nCt1f.:t'<'oe-Go".l(..:r:nl.:-'~'.'.~"'''M,a,IRet,As;g€ctsor .ume-t '!'tktrsntl!:i:Sictrt '/{~terngt:i:ves'.'.'''''''o':1..,.!,,;;u"1par~lSG1.l.ot Sus.1.)-1.""'!1':,.1>(1 '"<"r,!';.;l r;=!"1 I:r;;:,:.'\f ':'..'<',;:,~}t.['1·')1.1'1'_.a.n~or::a~e-CooK Tn eCAi'eit •~':.,'••••'.:•••'~'.:.'.;'::.~••••coJ~AJfrJJr?dof'Susifrla'td'Sfea:mp J:a:rt'Ls1Utlf and 'W'±thout .,.• ii 1\._-------------------------- ~.' 2.Previous Studies and Bibliography. 3.LOAD/RESOURCE AND SYSTEM COST ANALYSIS FOR THE RAILBELT REGION OF ALASKA:1978-2010 --Informal Report--by Battelle Pacific Northwest Laboratories,Richland,Washi~gton -January.1979. 4.Comments. a.Federal Energy Regulatory Commission,San Francisco,California. b.Battelle Pacific Northwest Laboratories,Richland,Washington. c.Corps of Engineers,Anchorage,Alaska d.The Alaska State Clearinghouse,Juneau,Alaska e.Municipal Light and Power,Anchorage,Alaska iii TABLES NUMBER PAGE NO. 1. 2. RAILBELT AREA GENERATION CAPACITY SUMMARY -1977 BASIC POWER AND ENERGY FORECASTING DATA ANCHO~~GE-COOK INLET AREA (INCLUDING SEWARD) 14 18 3.BASIC POWER AND ENERGY FORECASTING DATA FAIRBANKS-TANANA VALLEY AREA ••..••.••••••.•.••..••..••19 4.BASIC POlfER AND ENERGY FORECASTING DATA RAILBELT AREA (ANCHORAGE-COOK INLET AND FAIRBANKS-TANANA VALLEY)..•••••.•••••.••••..•.•.•••..•20 5.NET GENERATION (GWH) ANCHORAGE-COOK INLET AREA ......to •••••••••••••.PO .21 6.NET GENERATION (GWH) FAIRBANKS-TANANA VALLEY AREA ••...••...••....•...••.•.• 7.AVERAGE ANNUAL UTILITY GROWTH SUMMARY •.•..••••••..•.•. 8.POPULATION ESTIMATES 1980-2025 •.....••.•....•.•..•..••• 22 26 34 9.NET ANNUAL PER CAPITA GENERATION (K\{H) RAILBELT AREA UTILITIES •••.•.••.•.••......••....•....•39 10.POWER AND ENERGY REQUIRE~lliNTS (ANCHO~~GE-COOK INLET AREA)••..•....•.••••.•.••.....••40 ~\ 11.POWER AND ENERGY REQUIRE~NTS (FAIRBANKS-TANANA VALLEY AREA)43 12.RAILBELT ~EA POWER AND ENERGY REQUIREMENTS ANCHORAGE-COOK INLET AREA AND FAIRBANKS-TANANA VALLEY AREA COMBINED ..•••••.........•.••.....••..••........••46 13.COMPARISON OF UTILITY ENERGY ESTIMATES, 1975 MARKETABILITY REPORT,UPDATE OF 1975, AND 1978 ANALYSIS •..••••••••.••••....••.....•..••.•.••49 14.UTILITY ENERGY FORECASTS (GWH) ANCHORAGE-COOK INLET AREA .•••••••••••...•••..•.•.•.•••52 15.UTILITY PEAK DEMAND FORECASTS (MW) ANCHORAGE-COOK INLET AREA •..••••••••.•••••....•....•..53 16.UTILITY ENERGY AND PEAK DEMAND FORECASTS FAIRBANKS-TANANA VALLEY AREA ••.•..••....•..•..•.•••...54 iv TABLES (Continued) NUMBER'PAGE NO. 17.LOAD DISTRIBUTION CHARACTERISTICS MONTHLY PEAK LOADS AND LOAD FACTORS ...................................59 18.MONTHL Y ENERGY REQUIREMENTS AS PERCENT OF ANNUAL REQUIREMENT .........•••.........•................••...60 19.COMPARISON OF INVESTMENT COSTS FOR COAL-FIRED STEAMPLANTS ....•.•...........•....••..................65 20.GENERATION COSTS FOR CONVENTIONAL COAL-FIRED STE.Al1.PLANTS 69 21.SUMMARY OF THERMAL GENERATING CAPACITY ADDITIONS TO THE YEAR 2010 .....•••....•..............•...•.........78 22.ANNUAL POWER SYSTEM COSTS :..0%INFLATION (COMBINED ANCHORAGE-COOK INLET AND FAIRBANKS-TANANA VALLEY AREAS)...•......•...•.••..•....•...............81 INVESTMENT COST SUMMARY ......••.••••••...•.•.•..•.•...88 REPLACEMENT COSTS •.....•.•.•...•••.•....•....•.•..••..96 .INVESTMENT AND OM&R COST SUMMARY 100 OPERATION AND MAINTENANCE COST SUMMARy................95 99 CONSTRUCTION COST SUMMARy.............................87 ANNUAL OPERATION AND MAINTENANCE COST ESTIMATE .'.'. • . . .92. MARKET FOR UPPER SUS ITNA POWER (ANCHORAGE AND FAIRBANKS AREAS)MEDIUM LOAD GROWTH ESTIMATES COST SUMMARY COMPARISON WITH 1976 INTERIM FEASlB ILITY REPORT ........•..................•.••••.••103 AVERAGE POWER COSTS ANCHORAGE-COOK INLET AREA -0%INFLATION •.••..•..•....'.. . . . . . • . . . •. •. . . . . ••83 AVERAGE POWER COSTS -0%INFLATION FAIR13ANKS-TANANA VALLEY AREA ...•...•..•..•..•......•..84 COMBINED ANCHORAGE-COOK INLET AND FAIRBANKS-TANANA VALLEY'AREA AVERAGE ANNUAL POWER COSTS .••..••...•.••..85 AVERAGE RATE DETERMINATION (WATANA AND DEVIL CANYON)......•..•............•••.•.•104 23. 24. 24a. 25. 26. 27. 28. 29. 30. 31- 32. 33.r-. v NUMBER TABLES (Continued) PAGE NO. 34.HISTORIC DATA (GLENNALLEN-VALDEZ AREA).......•.•..•...111 35.UTILITY NET GENERATION (GWH) (GLENNALLEN-VALDEZ AREA)••••........•..••...••....•..•112 36.UTILITY FORECASTS (VALDEZ-GLENNALLEN AREA)..•••....•••113 37.TRANSMISSION SYSTEM INVESTMENT COST SUMMARY (GLENNALLEN-VALDEZ AREA)•.••.••.•..•.....•••.•.•...•..114 38.TRANSMISSION SYSTEM OPERATION,MAINTENANCE,AND REPLACEMENT COST SUMMARY (GLENNALLEN-VALDEZ AREA)115 vi ~. I FIGURES NUMBER PAGE NO. 1.UPPER SUSITNA RIVER BASIN PROJECT FEATURE SITE LOCATION •..••......•.•....•.•.••••..•.•..viii 2.UPPER SUSITNA RIVER PROJECT AREAS PRESENTLY SERVED BY RAILBELT UTILITIES .•.•••.•••..••••••..•••.••11 3.ENERGY SECTOR RATIOS ANCHORAGE-COOK INLET AREAS AND ANNUAL ENERGY GENERATED OR SOLD ANCHORAGE-COOK INLET AREA 27 4.ANNUAL ENERGY USE PER CAPITA &PER CUSTOMER ANCHORAGE-COOK INLET AREA •.•.•••••.•.•••••••••.••••.••28 5.ANNUAL POPULATION.EMPLOYMENT.AND UTILITY CUSTOMERS ANCHORAGE-COOK INLET AREA •••.•.••.••.••••..••••••••.••29 6.ENERGY SECTOR RATIOS FAIRBANKS-TANANA VALLEY AREA AND ANNUAL ENERGY GENERATED OR SOLD FAIRBANKS-TANANA VAL-LEY 'AREA 30 ENERGY FORECAST ANCHORAGE-COOK INLET AREA ....•.••.••..41 PEAK LOAD FORECAST FAIRBANKS-TANANA VALLEY AREA .••.•••45 TOTAL RAILBELT AREA ENERGY FORECAST •....••.•••.•••••••47 ANNUAL ENERGY USE PER CAPITA AND PER CUSTOMER FAIRBANKS-TANANA VALLEY AREA ••••.•••••••...•.~........31 42 44ENERGYFORECASTFAIRBANKS-TANANA VALLEY AREA ANNUAL POPULATION.EMPLOYMENT.AND UTILITY CUSTOMERS FAIRBANKS-TANANA VALLEY AREA .•••.•.•.••••.•.•..••.••..32 PEAK LOAD FORECAST ANCHORAGE-COOK INLET AREA ~7. 8. 9. 10. II. 12. 13. 14.TOTAL RAILBELT AREA PEAK LOAD FORECAST ••.•••••••••.•..48 15.SYSTEM DAILY GENERATION CURVE ANCHORAGE AREA 1976 •.••.56 16.SYSTEM DAILY GENERATION CURVE ANCHORAGE AREA 1977-78 ••57 17.LOAD DURATION CURVE -1977 ANCHORAGE AREA 58 18.ANNUAL POWER SYSTEM COSTS WITH AND WITHOUT SUSITNA COMBINED ANCHORAGE-COOK INLET AND FAIRBANKS-TANANA VALL EY '.;/82 19.COMPARISON OF SUSITNA AND ALTEfu~ATIVE COAL-FIRED STEk~LANT RATES CONSIDERING 5%ANNUAL INFLATION 107 vii Figure 1 APA 12/78 viii . ."""'\. ,...5 __...·~( PART I.INTRODUCTION The Interim Feasibility Report of the Upper Susitna River Basin Project (1976 report)was completed by the Alaska District Corps of Engineers (Corps)in 1976.Alaska Power Administration (APA)provided the trans- mission system and power market analyses for that report. The Corps submitted the 1976 report to the Office of Management and Budget (OMB)for review.In September 1977,OMB requested the Corps obtain additional data before submitting the report to Congress.The requested data were to:(1)provide additional geologic data for the Watana damsite;(2)*reana1yze the cost estimate contingency factor;(3) reanalyze area development benefits;and (4)reanalyze the projected cOllstruction schedule.There were also questions about power supply and demand,including sensitivity to developing a large block of power in APA's area of responsibility. This report updates the power market analysis and addresses OMB concerns.It uses three years additional data on power usage,effects of the oil embargo t and other faetors.Specifically,it (1)updates the power demand forecasts reflecting data since the 1976 report;(2) updates the transmission and project OM&R costs;(3)presents load/resource analyses to determine timing of major generation and transmission investments and reflect resulting impacts on power system costs;(4)presents·system power cost analyses that show annual system-wide costs of power with and without the Upper Susitna Project; (5)examines the value of an Anchorage to Fairbanks interconnection with and without Susitna;(6)provides a subanalysis of the feasibility of delivering Susitna power to the Valdez-Glennallen area;(7)determines power rates and marketability of Susitna power compared with alternative generation methods;and (8)responds to the OMB questions in APA's areas of responsibility. APA gave the Corps,for their report purposes:updated transmission system costs and project OM&R estimates;load estimates;detailed load/resource and system cost analyses with and without Susitna project; and proposed responses to OMB questions pertinent to APA areas of responsibili ty.• The Corps'current proposal for the Upper Susitn&Project is essentially the same as plan 5 in the 1976 report:a two-phase,two-dam complex including Watana and Devil Canyon dams and powerplants,with the Watana phase and a transmission system interconnecting Anchorage and Fairbanks coming on-line first.Power production facilities include Watana dam, reservoir,and powerplant,and Devil Canyon dam,reservoir,and powerplant.Watana dam would be an earthfill structure with reservoir normal water surface elevation of 2,185 feet;the powerplant would have 795 MW capacity.Devil Canyon dam would be a double-curvature concrete-arch structure with maximum pool elevation of 1,450 feet, providing water for a 778-MW powerp1ant.The transmission system would be constructed in conjunction with the first stage (Watana),and, 1 as planned,would be,totally required for system reliablilty.The system would incude two parallel 230-kv single circuit lines from Watana to Devil Canyon (30 miles),two parallel single circuit 345-kv lines from Devil Canyon to Pt.McKenzie (Anchorage,135 miles),and two parallel single circuit 230-kv lines from Devil Canyon to Ester-Gold Hill (Fairbanks,198 miles). Several significant changes were made by the Corps since the 1976 report: (1)The Devil Canyon dam design and costs are presented for both a gravity structure and a thin-arch concrete structure.The 1976 report was based on a thin-arch concrete structure. (2)The construction period for Wata.na was increased from 6 years to 11;'Devil Canyon from 4 years to 7;and the Anchorage-Fairbanks intertie re-scheduled for 1991--three years before Watana POL. (3)Watana dam (earth fill)was redesigned,based on new geologic data. The APA power market report uses certain assumptions that differ from the Corps plan,namely: (1)Design power generation capacity:The Corps design capacity is based on critical year primary energy and 50 percent annual plant factor (1,392 W,.]).The APA load/resource analyses assume a design capacity based on average annual energy and 50 percent plant factor (1,573 MlV). APA analyses include both primary and secondary energy as well as firm and non-firm power. (2)'Transmission intertie schedule: The Corps plans show a 1991 on-line date for the transmission intertie. The APA system cost analyses examine alternative on-line dates of 1990, 1992,and 1994.The load/resource analysis showed the earliest intertie dates could be 1986, 1989,and 1991.APA financial analyses are consistent with the Corps schedule. (3)For Devil Canyon Design: The APA system cost and financial analyses.assume the thin-arch design for Devil Canyon as presented in the 1976 report,rather than the more costly gravity structure alternative now being used by the Corps for feasibility testing.A separate analysis demonstrates the effect of the gravity dam alternative on cost of power. The term Tl1976 report"is used throughout this report.This term refers to the Corps of Engineers Interim Feasibility Report on the Upper Susitna project,dated December 1975,revised June 1976.It also refers .to APA's·Power Market analysis dated 1975 and included as Appendix G in the revised Interim Feasibility Report. 2 l""........__r .."""""",..> Part II.SUMMARY Current studies have updated and revised the power market analyses of the 1976 Upper Sustina Report (1976 report).New estimates of power requirements through the year 2025 have been prepared. The 1976 report used energy and power estimates based on data through December 1974.The new analyses benefit from three full years of additional data through December 1977.This provides a 'full four years of "post oil-embargo"data--especially significant from the viewpoint of identifying conservation trends.Evidence of conservation shows in the Anchorage-Cook Inlet area growth comparisons before and after the 1973-74 fuel crisis.The 1970-73 average annual growth in net generation dropped from 14.2 percent to 12.7 percent in the 1973-77 period.The decrease was more dramatic for per capita net generation: A drop from 8 percent to 3.8 percent. Because the net generation kwh/capita raio seemed to reflect the closest corr~lations.particularly in recent years,this ratio and population were used to forecast net generation values between,1980 .and 2025. The following Railbelt totals are detailed in Part V.Trended values offer an interesting comparison but are not presented as part of the forecast.The trend is an average annual growth of 12.3 percent resulting from 12.7 percent for the Anchorage area and 10.5 percent for the Fairbanks area. Railbelt Area Energy Forecast (GWH) 3 Area load characteristics data were updated and new estimates of monthly energy distribution were made.The conclusion was that the 50 percent plant factor sizing assumption is still valid. A further review of possible power supply alternatives included oil and natural gas,coal,alternative hydro projects,nuclear,wind, geothermal,and tide.It concluded again that coal-fired steam plants are the most logical alternatives for major ra~lbelt area power supplies in the proposed Susitna project timeframe. New estimates of cost of power from coal-fired steamplants were ~repared using results of several recent studies.They indicate: Investment costs of $1,620-$l,860/kw Unit cost of power of 5.2-6.4¢/kwh (including transmission to load center) A set of load/resource and annual system cost analyses were performed to examine the e,ffects of Susitna and the transmission intertie from an overall power system approach.These analyses were needed to provide respon~es to OMS questions regarding:(1)the value of an interconnected transmission system between Anchorage and Fairbanks;(2) scheduling.ofillflior powerplants;and,(3)sensitivity of developing large blocks'of power.APA's response to the OMB questions are appended.!Th):'e'fi cases were analyzed using three projected load growth estimates: Case 1..~without Susitna Proj ect and without transmission intertie situation ~ssuming all generating capacity to be supplied by coal-fired steamplaTj~:~. Case 2.Same as case I but with transmission intertie. Case 3.A with Susitna Project and with intertie situation assuming additional ge-n,erating capacity supplied by coal-fired steamplants. The load/resource analyses showed the schedule of new plant additions needed for all three cases for 1978-2011. The system cost analyses compared annual power system costs for all three cases,assuming 0 and 5 percent inflation rates.The analyses showed annual system cost savings of $2.23 billion between 1990 and 2011,with the Susitna project.Average power system rates for the year 2000 assuming no inflation will be: 4 Load Forecast High Mid L(;W Case 1 Wi thout Susitna or Intertie 6.6 1/ 6.9 1/ 7.5 J:../ ¢/KWH Case 2 Without Sus tina With Intertie 6.4 6.6 6.7 Case 3 With Susitna and Intertie 5.8 5.7 6.4 ]j Anchorage and Fairbanks are not interconnected for case combined system rate is shown for academic purposes only. l',the For the medium-energy use range,system rates,compared to those without Susitna or interconnections,will be 5.7 1 /percent less with interconnections 18.6 percent less with Susitna.-The analyses showed Susitna will result in cheaper power cost to Anchorage and Fairbanks in all load growth cases.It also shows that the Pf,Pj ect power could be fully used under all projected power demand cases.- In comparison with the 1976 report~investment costs are 89 percent ($1.567 billion)greater.Contributing factors are:interest rate increase from 6 5/8 to 7 1/2 percent total construction period increase from 6 years to 10 years,cost inflation;and redesign of Watana dam and powerplant facilities.New construction cost estimates for.Watana dam (containing effects of both design quanitity changes and unit cost inflation)are $595 million (72.percent)higher.Construction cost estimates for Devil Canyon dam (thin-arch concrete)power plant facili ties,and the transmission system were updated primarily by indexing.This resulted in a 54 percent increase over the 1976 report ($233 million for Devil Canyon and $82 million for the transmission system).The total interest during construction increase is 265 percent ($657 million).In summary.the increases in construction costs are: Watana Devil Canyon Transmission System Interest during Construction Total $595 233 82 657 $1567 million II 11 II million project investment cost increase Financial ~malyses were based on the October 1978 price level,Fiscal Year 1979 Federal interest rate of 7 1/2 percent,intertie in 1991 or 1992,and repayment of all principal and interest within 50 years after the last unit is installed. }j Case 2 Value (6.6%)-1 Case 1 Value (7.0%) -5.7%;Case 3 Value (5.7%)-1 Case 1 Value (7.0%) -18.6% 1/Interconnection benefits leading to lower rates involve load supply flexibility,economics of scale and operations.decreased reserve requirements,and better reliability. 5 A comparison .of the rate for Sustina at 4.7¢/kwh with the coal-fired steamplant alternative at 5.2/kwh to 6.4¢/kwh shows Susitna is less costly. The Glennallen-Valdez area was considered as a market area supplementary to the Railbelt.Ihe Copper Valley Electric Association (CVEA)plans to construct a Glennallen-Valdez transmission line,and the presence of the pipeline terminal in Valdez with its related economy has made this area a more attractive market since the 1976 report.Service to the area would require a l38-kv line from Palmer to Glennallen (136 miles).Area market factors are subject to fluctuation.Potential industrial loads are difficult to project at this time,but service to utility loads can be evaluated for a probable range of demands.Energy costs to serve the incremental market area will range from 2.6¢/kwh to 1.3¢/kwh for a range of loads from 150 to 300 kwh/year in addition to the project energy cost of .4.7¢/kwh.Inclusion of the market area costs with other project costs for a single project-wide rate would not adversely affect the rate. .~., .~. PART III.POWER MARKET AREAS Throughout its history of investigations,the Upper Susitna River Basin Proje~t has been of interest for hydroelectric power generation because of its central location to the Fairbanks and Anchorage areas.These areas have Alaska's largest concentrations of population,economic activity,services,and industry.Under any plan of development,major portions of the proj ect po~er will be used in these two areas.In addition,the basic project transmission system serving Anchorage and Fairbanks could provide electric service to present and future developments between the two cities. The potential maj or market areas "are the Anchorage-Cook Inlet area and the Fairbanks-Tanana Valley area. Anchorage-Cook Inletu~ This area includes the developed areas of the Matanuska Valley,Greater Anchorage Area,and Kenai Peninsula. This general area has been the focal point for most of the State's growth in terms of population,business,services,and industry since World War II.Major building of defense installations,expansion of government services,discovery and development of natural gas and oil in the Cook Inlet area,and emergence of Anchorage as the State's center of government,finance,travel,and tourism are maj or elements in the history of this area.. Because of its central role in business,commerce,and government,the Anchorage area is directly influenced by economic activity elsewhere in the State.Much of the buildup in construction and operation ·of the Alyeska pipeline,much of the growth related to Cook Inlet oil development,and"much of the growth in State and local government services since Statehood has occurred in the immediate Anchorage vicinity. Initially,economists overestimated the impacts of completion of the trans-Alaska oil pipeline.In a recent study prepared by the University of Alaska Institute of Social and Economic Research,the projected 1980 population for Anchorage-Cook Inlet was lower than that of the historical 1977 population.Though this has been corrected,it indicates that the area's economy has been stronger than anticiapted. The Greater Anchorage Are?Borough estimated its July 1,1977 population at 195,800,an increase of nearly 55 percent since the 1970 census.This was more than 48 percent of the total estimated State population in 1977 . 7 -----------,-~_._---- The Matanuska Valley includes several small cities (Palmer,Wasilla, Talkeetna)and the State's largest agricultural'community.Other economic activities include recreation and light manufacturing.Much recent growth in th~Borough has been in residential and recreational homes for workers in'the Anchorage area.Estimated 1977 population T.vas 15,740,'a 61 percent increase since 1974. The Kenai Peninsula Borough includes the cities of Kenai,Soldotna, Homer,Seldovia,and Seward.with important fisheries,oil and gas,and recreation resources.Estimated 1977 population was 23,100,a 39 percent increase since 1974. Present and proposed activities indicate likelihood of rapid growth in this general Cook Inlet area for the future.Much of this activity is related to oil and natural gas,including expansion of the refineries. The State capital city site relocation issue remains unresolved.In the November 1978 general election,voters turned down the $966 million bond issue to relocate the capital.In the same election,voters approved an initiative which would require full disclosure of the costs to move the capital.Therefore,it is impossible at this time to include specific assumptions concerning the capital move. The area will continue to serve as the transportation hub of western Alaska,and tourism will likely continue'to increase rapidly.Major local development seems probable. Fairbanks-Tanana Valley Area Fairbanks is Alaska's second largest city -the trade center for much of Alaska's Interior,the service center for several major military bases, and the site of the main campus of the University of Alaska with its associated research center.The outlying communities of Nenana,Clear, North Pole,and Delta Junction are included in the Fairbanks-Tanana Valley area.Historically,the area is famous for its gold. The completion of the pipeline construction has taken its toll in Fairbanks.The area is experiencing a severely depressed economy. Employ~ent in the construction industry has decreased to half of the previous pipeline level.There has been a slight increase in employment generated by government,distributive industries,and retail trade.In 1977-78,Fairbanks and its outlying areas experienced a 16 percent decline in population. The .decision favoring the ALCAN route for the proposed natural gas pipeline was made in late 1977.The proposed-gas pipeline will follow the route of the trans-Alaska oil pipeline route from Prudhoe Bay to Del ta Junction.Fairbanks has been selected as the operation headquarters by the Northwest Pipeline Company,responsible for construction and operation of the gas pipeline.The Fairbanks-Tanana Valley area will probably be heavily impacted again by the pipeline construction;however,a more stable permanent employment base is likely to become established. 8 The Fairbanks;"'North Star Borough had an estimated 1977 population of 44,262 and an estimated additional 8,OOO:i,n the outlying communities within the power market area.The total population decreased 10 percent since 1974. 9 ------~------- PART IV.EXISTING POWER SYSTEMS Utility Systems and Service Areas The electric utilities in the Railbel t power market area are listed below,and areas now receiving electric service are shown on figure 2. A detailed listing of power generating units is in the appended Battelle report,table 3.4. Anchorage-Cook Inlet Area Alaska Power Administration (APA) Anchorage Municipal Light and Power (fu~&P) Chugach Electric Association (CEA) Matanuska Electric Association (MEA) Homer Electric Association (REA) Homer (Standby) Seldovia,English Bay,Port Graham Seward Electric System (SES) Fairbanks-Tanana Valley Area Fairbanks Municipal Utility System (TI1US) Golden Valley Electric Association (GVEA) 1/Major generation supplied by CEA system. Installed Nameplate 2/ Capacity MW - 30.0 121.1 345.7 !/ 0.3 Jj 1.8 5.5 1/ 69.6 219.2 Y Consists of 4S WAf hydro.All the rest are fuel-fired (80%gas turbine~t, 10 A .'1!1!1~!111Iil~ll!j\I!ll!ljjill!1111!:111i\\j~;lj!i[l\;jj,,;... ~----- o 11 --------_._--------- Figure 2 SCALE; 50 APA 12/78 IOOMil.~ These totals differ from the Battelle appended report because the report ~ includes some planned units not installed in 1977 as well as use of some ratings other than nameplate. APA operates the Eklutna hydro·electric proj ect and markets wholesale power to CEA.A..\fL&P.and MEA. AML&P serves the Anchorage Municipal area.CEA supplies power to the Anchorage suburbs and surrounding rural areas.and provides power at wholesale rates to HEA.SES.and MEA.The HEA service area covers the western portion of the Kenai Peninsula~including Seldovia.across the bay from Homer.MEA serves the town of Palmer and the surrounding rural area in the Matanuska and Susitna Valleys. The utilities serving the Anchorage-Cook Inlet area are now loosely interconnected through facilities of APA and CEA.An emergency tie is available between the AML&P and Anchorage area military installations. FMUS serves the Fairbanks municipal area.while GVEA provides service to the rural areas.The Fairbanks area power suppliers have the most complete power pooling agreement in the State.FMUS.GVEA.the Univer- sity of Alaska.and most of the military bases have an arrangement which includes provisions for sharing reserves and energy interchange. The delivery point for Upper Susitna power to the GVEA and FMUS systems is assumed at a substation of'GVEA near Fairbanks. Other small power generating systems in the Fairbanks-Tanana Valley area were included in determining the power requirements of the region.They include: Fairbanks-Tanana Valley Area Alaska Power and Telephone Company (Tok and Dot Lake vicinity) Northway Power and Light Company (Northway vicinity) Installed Capacity MW 2.28 0.48 National Defense Power Systems The six major national defense installations in the power market area are: Anchorage area-- Elmendorf Air Force Base Fort Richardson 12 Fairbanks area-- Clear Air Force Base Eielson Air Force Base Fort Greely Fort Wainwright Each maj or base has its own steamplant that is used for power and for central space heating.Except for Clear Air Force Base,each is inter- connected with the local utility.Numerous small isolated installations are not included in this study. In the past,national.defense electric generation has been a major portion of the total installed capacity.With the projected stability of military sites and the growth of the utilities,the national defense ins~allation will become a less significant part of the total generating capacity. Industrial Power Systems Three industrial plants on the Kenai Peninsula maintain their own power- plants,but are interconnected with the REA system.The Union 76 Chemical Division plant generates its basic powe~to satisfy its energy needs,receiving only standby capacity from HEA.The Kenai liquified natural gas plant buys energy from REA,but has it,s own standby generation.Tesoro Refinery buys from REA and also satisfies part of its own needs.. Other self-supplied industrial generators include oil platform and pipeline terminal facilities in the Cook Inlet area. Existing Generation Capacity Table 1 provides a summary of existing generating capacity.The table was generally current as of 1978;The Anchorage-Cook Inlet area had a total utility installed capacity of 504.5 Mt~in 1977-78.Natural gas-fired turbines were the predominant energy source with 435.1 MW. Hydroelectric capacity of 45 MW was available from two projects,Eklutna and Cooper Lake.Steam turbines comprised 14.5 MW.Diesel generation, mostly in standby service,accounted for the remaining 9.8 MW. The Fairbanks-Tanana Valley area utilities had a total installed capacity of 288.8 MW in 1977.Gas turbines (oil-fired)provided the largest block of power in the area with an installed capacity of 203.1 MW.-Steam turbine generation prOVided 53.5 MW of power and diesel generators contributed 32.1 MW to the area. 13 Area Table 1 AAILBELT AREA GENERATION CAPACITY Summary -1977 Upper Susitna Project Power Market Analysis Installed Capacity -MW Hydro Diesel Gas Steam Int.Comb.Turbine Turbine Total Anchorage~Cook Inlet utility systi§nt', National Def~tis~.. Industrial System Subtotal Fairbanks-TananaVa11ey utility System National Defense Subtota1 45.0 45.0 9.8 9.2 10.2 29.3 32.1 14.0 46.1 435.1 14.8 449.9 203.1 203.1 14.5 40.5 55.0 53.5 63.0 116.5 504.5 49.7 25.0 579.2 288.8 77.0 365.8 Notes: Source: The majority of the dieSel generation is in standby status. Roundin~Causes differertces between summations of the parts and the totals shown. Utility reports to Alaska Public utility Commission to the Department of Energy,the Alaska Air Command,the oil and gas compahies,and APA files. (Minor differences exis~between this table and the appended Battelle Report.). APA 11/78 ~, 14 Planned Generation Capacity The two major utilities in the Anchorage-Cook Inlet area,AML&P and CEA, plan to add a total of approximately 420 ffi~installed capacity to their existing system between 1979 and 1985.k'1L&P plans to add a 16.5-MW combined cycle system to their existing combustion turbine.In addition,CEA has plans to complete the 230-kv interconnection loop with MEA. In December 1978,GVEA decided to postpone development of their proposed Healy II steam turbine system (104 MW)until more favorable economic conditions prevail. A unit by unit breakdown of planned generating systems is presented in the appended Battelle report,table 3.8 • .. 15 PART V.POWER REQUIREMENTS I Introduction This summarizes the analyses of historic data and estimates of future needs in the ,power market areas.The study examines in detail electric utility statistics 1970 to 1977 with special effort to identify changes in use patterns related to conservation measures since the 1973 oil embargo. Estimates of future utility power needs are derived from estimates of individual energy use and area popu~ation.Population projections were developed by the University of <Alaska,Institute of Social and Economic Research (ISER).The individual use forecast was estimated by assumed conservation-induced changes in kwh/capita growth rates.The end results are forecasts of net generation (kwh)and peak load demand (kw). The three energy use sectors analyzed in this study are: Utility Includes all utilities which serve residential and commercial/industrial customers. National Defense -Includes all military installations. Self-Supplied·Industry -Includes limited number of heavy industries, i.e.,natural gas and oil processing industries on the Kenai Peninsula which generate their own power.The study assumes that these industries will purchase energy if it becomes economically feasible.Some have interchange agreements vith local utilities. Evaluations of monthly energy distribution and installed capacity requirements are included and are premised on characteristics of area power demands. Data This presents the basic parameters used in the analyses leading to the Susitna Power Market forecast assumptions. The historical data·summarizes the Anchorage-Cook Inlet and Fairbanks-Tanana Valley areas which comprise the Railbelt area.Each area is divided into utility,national defense,and self-supplied industrial components (Fairbanks-Tanana Valley area has no known significant self-supplied industries). The utility component is divided into four sectors: Commercial-Industrial,Total Sales,and Net Generation. 16 Residenti~l, ,,----------------------------------------------- Data was collected from government agencies,from commands,by correspondence publications and news media. utility and industry reports to various utilities directly,from Alaska military wi thindus try,and from various statistical Basic data needed for the 1970-1977 analysis are presented on tables 2, 3,and 4 included is utility annual energy and customers for each sector,national defense and industrial annual energy consumption, utili ty and national defense annua.1 peak load,industrial installed capacity,annual population,and average annual employment.In addition,utility net generation,listed on tables 5 and 6,was compiled for the 1960-1977 period. As part of the forecasting foundation,the following historical chronology indicates fluctuations affecting Rai1be1t energy use. 1970.Uncertainty construction,and approval. Above average temperature. concerning the oil Native land claims pipeline design, legislation pending. 1971. temperature. Uncertainty concerning pipeline.Below average 1972.Uncertainty concerning pipeline.Coldest year of period. 1973.Start of fuel crisis and conservation publicity in December. Below average temperature. 1974.Start of pipeline·construction.Near average temperature. 1975. ture. Peak of pipeline construction activity.Near average tempera- 1976.Start of pipeline construction "wind-down.II Electric pm.;er cable across Knik Arm out of service for an extended period (all but one circuit).Above average temperature. 1977.Oil started flowing in pipeline.Warmest year of period. Residential construction boom in Anchorage.Large increase in non-residential authorizations issued. 17 Year 1970 1971 1972 1973 1974 1975 1976 1977 Year 1970 1971 1972 1973 1974 1975 1976 1977 ~> Table 2 '\ .! BASIC POWER AND ENERGY FORECASTING DATA ANCHORAGE-COOK INLET AREA (INCLUDING SEWARD) Upper Susitna Project Power Market.Analysis Utility Energy Sales (G~{H)Net Generation (GWH) Resi.Comm./lndu.Total ]j Utility 'l:./Nat.Def.1/Indu. 310.5 342.3 678.7 744.1 156.2 1.65 369.7 393.9 792.5 886.9 161.2 421.6 454.0 911.6 1,003.8 166.5 45.3 459.5 514.8 1,012.2 1,108.5 160.6 496.1 552.8 1,087.4 1,189.7 155.1 45.3 595.1 631.9 1,270.6 1,413.0 132.8 677.6 738.7 1,462.2 1,615.3 140.3 741.0 813.4 1,600.8 1,790.1 130.6 69.5 Utility Customers Peak Load (MW) Resi.Comm./lndu.Total Utility Nat.Def.Indu.!!! 39,271 5,230 45,042 .165.2 34.6 12.3 42,501 5,581 48,670'184.8 ,-,., 46,724 6,104 53,278 212.8 33.9 12.3 49,307 6,491 56,280 229.9 52,585 6,798 59,893 257.2 32.6 12.3 56,801 7,478 64,797 345.8 61,881 8,220 70,622 349.9 68,320 9,221 78,066 423.9 40.5 24.8 Population Civilian Total Employment Avg.Annual 1970 1971 1972 1973 1974 1975 1976 1977 135,963 145,108 155,084 160,162 165,938 196,320 207,090 222,424 149,428 159,046 167,765 174,280 179,544 209,049 219,337 234,674 47,408 51,092 54,329 57,157 65,919 78,786 83,604 88,869 11 Excludes deliveries to national defense. 21 Total retail sales of energy +non-revenue energy used +losses. 31 Includes receipts from utilities,excludes deliveries to utilities. 41 Self-supplied industrial data is installed capacity rather than peak load. GWH =million KWH MW =thousand KW /~ KW =Kilowatt APA 11/78 18 Table 3 BASIC POWER AND ENERGY FORECASTING DATA FAIRBANKS-TANANA VALLEY AREA Upper Susitna Project Power Market Analysis Utility Customers Year Resi.Comm./Indu.Total Utility Energy Sales (GWH) Year 1970 1971 1972 1973 1974 1975 1976 1977 1970 1971 1972 1973 1974 1975 1976 1977 Resi. 91.7 112.4 122.3 134.4 155.8 193.0 195.9 200.7 10,364 11,014 11 ,584 11,931 12,832 14,025 15,569 16,709 Comm./Indu. 108.3 119.8 127.3 139.5 150.3 196.3 204.2 221.6 1,721 1,779 1,839 1,929 2,069 2,247 2,435 2,580 Total 1./ 210.2 244.3 262.9 282.3 323.0 409.2 420.5 442.7 12,268 12,947 13,611 14,041 15,084 16,447 18,179 19,463 Net Generation (GW'H) Utility ..Y Nat.Def.'if 239.3 203.5 275.5 201.4 306.7 203.3 323.7 200.0 353.8 197.0 450.8 204.4 468.5 217.5 482:9 206.8 Peak Load (MW) Utility Nat.Def. 56.3 44.4 65.3 66.6 41.4 72.7 87.5 40.8 110.0 102.6 118.9 41.0 Population Civilian Total Emp laymen t Avg.Annual 1970 1971 1972 1973 1974 1975 1976 1977 42,310 43,188 45,516 45,396 51,137 60,884 58,051(e) 47,l55(e) 52,141 50,585 52,383 52,2Z.6 57,836 67,011 63,762 52,155 15,681 15,817 16,873 16,794 21,960 34,451 34,325 27,385 1/Excludes deliveries to national defense. 2/Total sales +non-revenue use +losses. 3/Includes receipts from utilities,excludes deliveries to utilities. 4/Self-supplied industrial data is installed capacity rather than peak load. Gffi!=million Kffi! MW =thousand KW 19 APA 9/78 ----------------------------------------p------- Table 4 ~\ BASIC POWER AND ENERGY FORECASTING DATA RAILBELT AREA Upper Susitna Project Power Market Analysis Utility Energy Sales (GWH)Net Generation (GWH) 'Year ResL Comm.!Ingu.Total Utility Nat.DeL Indu.Total 1970 402.2 450.6 888.9 983.4 359.7 1.6 1,344.7 1971 482.1 513.7 1,036.8 1,162.4 362.6 25 (e)1,550.0 1972 543.9 581.3 1,174.5 1,310.5 369.8 45.3 1,725.6 1973 593.9 654.3 1,294.5 1,432.2 360.6 45.3(e)1,838.1 1974 651.9 703.1 1,410.4 1,543.5 352.1 45.3 1,940.9 1975 788.1 828.2 1,679.8 1,863.8 337.2 45.3(e)2,246.3 1976 873.5 942.9 1,882.7 2,083.8 357.8 45.3(e)2,486.9 1977 941.7 _1,035.0 2,043.5 2,273.0 337.4 69.5 2,679.9 Utility Customers Peak Load (MH) Year Resi.Comm.!Indu.Total Utility Nat.DeL Indu.Total 1970 49,635 6,951 57,310 221.5 79.0 12.3 312.8 1971 53,515 7,380 61,617 ,150.1 77(e)12.3 (e)3:~r\ 1972 58,308 7,943 66,889 279.4 75.3 12.3 36 {.O 1973 61,238 8,420 70,321 302.6 74(e)12.3(e).388.9 1974 65,417 8,867 74,977 344.7 73.4 12.3 430.4 1975 70,826 9,725 81,244 455.8 73 (e)12.3(e)541.1 1976 77,450 10,654 88,801 452.5 76(e)12.3(e)540.8 1977 85,029 11,801 97,529 542.8 81.5 24.8 649.1 Total Avg.Annual Population Employment 1970 201,569 63,089 1971 209,631 66,909 1972 220,148 71,202 1973 226,526 73,951 1974 237,380 87,879 1975 276,060 113,237 1976 283,099 117,929 1977 286,829 116,254 APA 11~! 20 ))') Table 5 NET GENERATION (GWH) ANCHORAGE~COOK INLET AREA Upper Susitna Project Power Market Analysis (Includes receipts of electric energy from military;excludes electric energy deliveries to military) Year AML&P CEA APA MEA IlEA KU SES Total Growth %---_.- 1960 0.8 27.5 187.6 0.1 8.2 1.8 5.7 231.6 1961 3.2 44.8 193.8 0.1 3.6 2.0 6.2 253.7 9.5 1962 20.0 101.8 150.3 0.2 0 2.3 3.7 278.2 9.7 1963 55.7 100.5 152.7 0.2 0 2.7 0 311.8 12.1 1964 97.3 94.5 146.1 0.5 1.2 3.8 0 343.4 10.1 1965 101.2 167.4 132.1 0.6 1.4 4.1 0 406.8 18.5 N 1966 108.6 204.6 138.2 0.7 1.4 5.2 0 458.7 12.8...... 1967 100.1 217.1 178.5 0.8 1.5 6.7 0 504.6 10.0 1968 125.3 280.0 155.5 0.8 1.7 10.1 0 573 .4 6.5 1969 148.1 314.6 158.2 0.9 2.2 8.9 0.1 633.0 17.8 1970 186.0 385.5 154.7 1.1 2.4 9.0 0.1 738.8 16.7 1971 24?3 476.6 144.9 1.3 2.7 8.0 0.1 878.9 19.0 1972 270.0 554.2 164.0 1.5 3.3 7.0 0.1 1 t OOO.1 13.8 1973 359.0 657.3 96.3 0.3 3.6 --0.1 1 t 116.5 11.6 1974 389.6 678.4 1.1 --4.2 --0.1 1,197.4 7.2 1975 384.3 888.8 135.1 --.3.4 --3.2 1,414.9 18.2 1976 442.9 1,054.5 118.5 --0.5 --1.5 1,617.3 14.3 1977 420.3 1,179.7 203.6 --0.5 --0.8 1,804.9 11.5 AHL&P CEA APA MEA HEA KU .. SES -Anchorage Municipal Light and Power -Chugach Electric Association -Alaska Power Administration -Matanuska Electric'Association -Horner Electric Association -Kenai Utilities -Seward Electric System APA 11-78 22 Analysis Detailed investigations of relationships among the basic data components are listed in tables 2,3,and 4.Analysis was done separately for each major sector (utility,national defense,and self-supplied industry) within eacn geographic area. Utility The analysis of utility data set out to develop assumptions for fore- casting net generation and peak load.Investigations evaluated the impact of changes in population,employment,customers,weather, tariffs,and other events upon energy use.These evaluations then helped to:(1)determine if energy sectors (residential, commercial-industrial,total sales)other than net generation needed to be forecast;(2)determine which energy ratio (kwh/capita,kwh/employee, kwh/customer)to use in the forecasting procedure;(3)develop procedure for forecasting utility annual net generation from energy use assumptions and demographic parameters (population,employees,or customers);(4)determine load factor with which to calculate peak load forecast from the net generation forecast. Constants,small amplitude cycles,or trends in relationships among the energy use and customer sectors were investigated for use as forecasting aids.If,for instance,the residential energy use/net generation ratio remained almost constant from 1970 through 1977,only net generation need be subj ected to the forecasting procedure.The same type of analysis was app lied to energy use ratios:a look for an average or trend to De used as a factor in forecasting net generation. After developing the net generation forecast,the peak load forecast was calculated using energy and an assumed load factor.Analysis of historic load factors determined an average or trend from which the assumed load factor was derived.Forecasted net generation and the assumed future load factor were then used in the formula:Peak load =8,760 hr/yr.x load factor x net generation .. The evaluations showed a mix of similarity and contrast between the two Railbelt areas.In both areas,the major energy use determinants were the trans-Alaska oil pipeline construction and the fuel crisis of 1973-74.Other correlations with weather,tariffs,etc.,seemed insignificant.For instance,energy growth increased in some years despite above average temperatures which reduced energy need. Anchorage-Cook Inlet Area Analysis Results procedures resulted in the following Anchorage-Cook Inlet area. 23 The foregoing observations evaluation for the ----"_liflt'_i'i'lP_W_=_·_"'=.~I1_·,....._., (a)Observations indicate no significant shift in energy use patterns or in share of total load among the various utility sectors (residential,etc.).The ratios among the sectors (residential/total sales;total sales/net generation,etc.)remained essentially constant through the study period.This was true for both energy and customers. Therefore,only one sector--net generation--represents all sectors in the forecast. (b)Energy rate of growth per customer and per capita had a significant reduction after the 1973-74 fuel crisis.The 1973-77 per capita average growth rate was about half that for 1970-73.It appears that conservation can be considered an influence after 1973. (c)Events impinging upon energy use are listed in the previous section.Between 1973 and 1977,several events bear repeating for emphasis:fuel crisis in 1974;start of pipeline construction in 1974; peak pipeline activity in 1975;decreas~of pipeline'activity in 1976 and 1977;cables across Knik Arm,which carry a large share of Anchorage energy,went out of service in 1976;warmer than average weather in 1974,1976,and especially 1977.Yearly growth rates'reflected rather large fluctuations as different historical events influenced each parameter.(This is a recurring phenomenon in Alaskan history). (d)Parameters were not influenced alike as figures 3 through 8 attest. For instance.customer growth reacted'to events in a steadier pattern than did population and employment.Reasons for this are more people~, per customer and time needed for connecting more customers to a utility system at the initial onslaught of large demographic growth. (e)Comparing the energy fluctuations with others,such as population and employment,gave a measure of correlation between parameters.(The energy use and customer growth fluctuations correlated only in part; their patterns did not coincide every year).However,energy and popu- la tion growth rate changes were coincidental for every year but 1977. That is,when the energy growth rate increased,so did the population growth rate;when the population growth rate decreased,so did the energy growth rate. (f)Energy use and weather comparisons were inconclusive.Warm weather did not bring corresponding reduction in energy use.Cold weather increases in energy use were buried in other events (pipeline construction,etc.). (g)Because the net generation kwhhapita ratio seemed to reflect the closest correlations,particularly in recent years,this ratio and population were used to forecast net generation values between 1980 and 2025. (h)Values basic to the forecasting assumptions are the kwh/capita ratio averaging 3.8 percent average annual growth between 1973 and 1977 and net generation averaging 12.7 percent. (i)Aver age annual growth results'are summarized on tab Ie 7.Figures .3,4,and 5 are graphs of pertinent elements of the analysis. 24 Fairban~s-Tanana Valley Area Analysis Results Some of the Anchorage-Cook Inlet area evaluation results apply also to the Fairbanks-Tanana Valley area,others do not.The following observations parallel tl:ose of Anchorage-Cook Inlet. (a)No significant shift in energy use patterns or in share of total load among the various utility sectors (residential,etc.).Again,only one sector--net generation--need be forecast. (b)Energy growth was similar to that of Anchorage (somewhat smaller in the pre-1973 period);but customer,population,and employee growth were different in the two areas.Consequently,the energy use per customer, per capita,and per employee ratios indicate different growth patterns in Fairbanks.The large swings of employment and population in Fairbanks during pipeline construction compared to almost constant preconstructionvalues cloud comparisons of the two periods. (c)Although the effects of pipeline construction are evident,the population/employee ratio (2.29 average through the study period)was constant enough to indicate that either population or employment can be used as a forecasting parameter. (d)The effects of weather on energy use could not be detected.In some years,degree day variations were not in phase with energy use variations. (e)Energy use/capita exhibited wider variations than the other two ratios,but,nevertheless,had the nearest to constant average ,annual growth rates.Because of this and the other observations,net generation kwh/capita and population were used to forecast net genera- tion. (f)As in the Anchorage-Cook Inlet area,values basic to the forecasting assumptions are the net generation/capita growth,averaging 10.6.percent per year,and net generation growth,averaging 10.5 percent per year between 1973 and 1977. (g)Growth rate results are summarized on table 7.Figures 6,7,and 8 are graphs of some pertinent elements of the analysis. ALASKA RESOUR£ES UBR~RY .,~•,I ' 25 'Table 7 ~ AVERAGE ANNUAL UTILITY GROWTH SUMM..A.RY ANCHORAGE-COOK INLET AREA Upper Susitna Project Power Market Analysis Avg.Growth Avg.Growth 1970.1973 1977 1970-1973 1973-1977 Energy GWH Rj=sidential Sales 310 460 741 14.0% 12.6% Commercial/Industrial 342 515 813 14.7 12.1 Total Sales 679 1,012 1.601 14.2 12.1 Net Generation 744 1,108 1,790 14.2 12.7 Energy Use,kwh/Customer Residential 7,907 9.319 10,846 5.6 3.8 Commercial/Industrial 65,449 79,310 88,212 5.6 2.6 Total Sales 15,068 17,985 20,506 6.0 3.3 Energy Use,kwh/Capita Residential 2,284 2,869 3,332 8.0 3.8 Commercial/Industrial 2,518 3,214 3,657 8.6 3.3 Total Sales 4,992 6,320 7.197 8.3 3.3 Net Generation 5,473 6,921 8,048 8.0 3.8 /-"", Fairbanks-Tanana Valley Area Avg.Growth Avg.Growth 1970 1973 1977 1970-1973 1973-1977 Energy GWH Residential Sales 92 134 201 13.4%10.7% Commercial/Industrial 108 140 222 9.1 12.2 Total Sales 210 282 443 10.2 11.9 Net Generation 239 324 483 10.8 10.5 Energy Use,kwh/Customer Residential 8.852 11,262 12,010 8.3 1.7 Commercial/Industrial 62,931 72,303 85,899 4.8 4.4 Total Sales 17,134 20,104 22,746 5.4 3.1 Energy Use,kwh/Capita Residential 1,759 2,572 3,848 13.5 10.6 Commercial/Industrial 2,077 2,670 4,249 8.7 12.3 Total Sales 4,031 5,403 8,488 10.3 12.0 ~Net Generation 4,589 6,196 9,259 10.5 10.6 APA 11/78 26 ~------------------------------ Figure 3 t"l',lEEGY SECI'OP.PAT1C::; .....,.e::-- =50.3% 46.1%Avg.a Hc·~43 42 .F---------..."'...,-="-~-::.-::-:-::-~-:::--""-~~--_:_-----__ Res1dent1al Sales 41 l 40 ::-:::;------+1------+1------+1------+[.£N~·e:.:t~G~e::.n:.:e:.:r~a~tf.i:::o:.n:---....:A~"+.,g:!..:.:.....:::....::4~'1:':':.,:7:.:%:"-l 19(70 1971 1972 1973'1974 1975 1976 1977 YEl\PS At'K:!!QI<I\GE-CCOK INTEr ARE.1\. 51 Upper Susitna Project Power Market Analysis 50 .['-'"-~~'-----'-------------'-"~~ial~'~~i~~~------- "9 T Total Sales 'Avg. ~4.~I tiP q,;.~46 ---~.~--~=~=.=:.:::::.:=:.:.:--~-~..:::-=------------ 45 Residential Sales 44 Total Sales N~CHO:Rl\GE-CCOK INLJTI'.l\.iWJ\ 1977197613731972 Upper Susitna Project Power Market Analysis 1971 -1's {CillO ---- .1 S'"c ",.-:::::.._----1 1 (',-\st.,-1-"_~----r ci ,\l-n··(_,.,.". _~::::::::::==~::::::::::::::::::::::::::::::::::::::::::::::::::~(::':':.T\"':..:G:_:'===::::,_::t.i31 S<l}c 5 ...,..t ••=====_ResideD .l=::==::--::::=-~"'i-.-'--==---------11-----,.....-------111-----+1-.----~f------ 197'J 1975 18(\0 1700 I 1000 1SQO ~1400 1300s:: 0 1200'M...;1100.-l T..-l F-100011 ~900 I;J ~SOO.....700 T;>.(,00 tl~ lr.500~ f1 ~OO 1:===300 1970 'fT::i\HS APA 12/78 27 Figu:r:e 4 11,000 ANClIORl-.GE-CCOK n,-ru:r AHE.l\. Upper Susitna Project Power Market Analysis 10,000 9,000 8,000 7,000 6,DOO • 5,000 • 4,000 3,000 J.977197619'15197319721971 L------cl------t------1-·------Ilf-------If----'----4'--J 1974 2,000 19'10 APA 12/78 28 .,I"""": 250.000 225,000 200,000 175,000 W -J 0..o ~150,000 l.1.o C/) 0:: W m!25,OOO :E .J Z 100,000 - 75,000 ANNU~~\L POPULATION t Er~iPLOY~..H;:NTt AND UTiLITY CUSTOf.1ERS ANCHORJ..'\GE-COO~<INLET AREA Upper Susitna Project Power Market Analysis Figure,5 'r-, 25.0°01---- 1970 1l-_-L-'L__--lI __---"1~.1 1971 1972 1973 1974 1975 19-(6 1977 YEARS APA 1/79 29 Figure 6 Avg.==41.3%" Avg.=46.4% Residenti.al Sales (,Net Generation Residential Sales Total Sales ---=:.--:;;;;.. Commercial-Industrial Sales " Total Sales Avg.=48.9% 38 ENERGY SECTOR RATIOS FAIRBANKS-TANANA VALLEY AREA Upper Susitna Project Power Market Analysis52 50 48-~460 z-440....42« 0::: 'denti.a1 Sales (GWH) ReS.J,. Upper Susitna Project Power Market Analysis .a1 sa~es (G"..m)·a~_Industr.J,.ccmmeI:c.J,. :3 6 l.....__--'''--__--II--....._---L-.....__.-.L .-.L .-.L --l 1970 1971 1972 1973 1974 1975 1976 1977 YEARS ANNUAL ENERGY GENERATED OR SOLD FAIRBANKS-TANANA VALLEY AREA500 :I:400 3= ~ zo--1300-1 ~ ".. :r: ~200 z >-(.!) a:100 IJJ Z lJJ - - O/9L.7~O-----:-l19-=7~1---19J-7-2--'-----'/9L.-7-3---,..1.9-74---,S.L7-S---/..J9-7S-----l1977 "YEARS .30 APA 1i79 Figure 7 ~~NNUAL ENERGY USE PER CAPITA AND PER CUSTOMER FAIRBANKS-TANANA VALLEY AREA upper susitna Project Power Market Analysis (Ttl.) .ta ITt-i.)caP(1.\.., 1 sales per Resident:La.... t .al <:ales Per capita Conunex-ciaJ.-InduS r~- 3000 2000 .4000 J3pOO 10,000 J ',000 12,000 -'P .....", 7000 >-" C) a:::·6000 w -. Z IJJ 5000 -.::I:9000 ~ :t:: (r-.8000 1000 ~---,I__I__I_-.-lI:"'-----I[_---,I,,---_l 1971 1972 197.3 1974 1975 1976 1977 YE~RS I. 31 APA 1/79 , .j Figure 8 70,000 ANNUAL POPULATION,EMPLOYMENT, AND UTILITY CUSTOMERS -EA.JR8AJ~U(S_~IAr{~N~_'l~L L~Y AREA Upper Susi~~a Project Power Market Analysis Ave:t:age ~l Employment ., .~ .(incl ...Total Po~ula-Uon 201 0c0 UJ ...Ja.o w 401000a.. LLo (J) 0:: IJJ.en 30,000 ::E ::J Z 10,000 Residential Customers . ..Commercial-Industrial CUstomers 1970 1971 1972 1973 1974 .-YEARS 1975 1976 32 A'PA 1/79 .~. National Defense Evaluation of historical national defense data resulted in net 'generation and peak load averages.The analysis encompassed the U.S. Army and Air Force installations in the Anchorage and Fairbanks areas. No definite trends surfaced--on1y a small,cyclic.decrease in the Anchorage area net generation and an increase in peak load.In the Fairbanks area,net generation increased slightly and peak load decreased.Total national defense is about 15 percent of utility for both net generation and peak load. Self-Supplied Industry Railbelt industry and the upper Kenai Peninsula complex showed no significant change in capacity and energy generation until 1977 when the chemical plant expanded.Therefore,the analysis consisted of a plant factor .dete,rmination only.Other factors needed in forecasting are discussed as assumptions in the next section. Energy and Power Demand.Forecasts This section presents future energy and power requirement estimates developed from the previous analyses.Work for the new estimates consisted of:(1)using the analyses to obtain forecasting assumptions; (2)using the assumptions in forecasting utility net generation/capita; (3)combining net generation/capita with Institute of Social and Economic Research (ISER)population projections to obtain the utility net gener:ation forecast,and forecasting national defense and industry generation from pertinent assumptions;and (4)combining the net generation forecast with load factors resulting from the historical dat.a analysis to'obtain peak load (power requirement)forecasts. Assumptions and Methodology Population --The ISER econometric model of the Southcentral Region Water Study (Level B)furnished high and low range population forecasts.The model disaggregated the Anchorage':'Cook Inlet area.from a sta.tewide population forecast.No recent,applicable forecast of Fairbanks-Tanana Valley population was available;therefore,APA assumed statewide growth rates from the ISER model applied to the Fairbanks-Tanana Valley areas. (See table 8). Utility -Assumptions,based on the preceding analyses,lead to the net generation and peak load forecast.Net generation is the product of forecasted energy use per capita and projected population.Peak load demand is derived from net generation and the assumed utility load factor.Multiplying these growth rates by forecasted 1980 values of kwh/capita resulted in the energy use estimates • 33 Table 8 POPULATION ESTIMATES 1980-2025 RAILBELT AREA Upper Susitna Project Power Market Analysis II S .d II Fairbanks-Tanana Valley 1./Anchorage-Cook Inlet -tatew~e - Year High Low High Low High Low 1980 270,200 239,200 513,766 500.225 62,020 60,390 1985 320,000 260,900 640,718 563,303 77 ,350 68,010 1990 407.100 299,200 790,042 618,397 95.370 74,660 1995 499,200 353,000 947,312 680,286 114,360 82.130 2000 651.300 424.400 1,157,730 743,034 139,760 89,700 2025 904,000 491,100 1,484,784 820,369 179,240 99.040 Notes:*No mid-range estimates are shown because,when the forecasts were done,ISERll had made only the high and low projections. A comparison of the mid-range forecast already performed (see text for method)with one using the mid-range population,when received,indicated no reason to re-do the forecasts. *Values shown include national defense population II From Iser,Southcentral AlaskaTs Economy and Population:A base Study 1965-2025.September 1978 with December 1978 revisions. II Calculated from statewide growth rates. 34 .~. Since the ratios of residential.commercial':"'industrial.and total sales energy to net generation remain constant.net generation is assumed to be an appropriate forecasting parameter.The evaluations indicated that the other sectors do not need individual forecasting. The basic energy use (net generation kwh/capita)assumption for the entire Railtlelt are~is a 3.5 percent average annual.mid-range.1980-85 growth rate.It is based on the Anchorage-Cook Inlet area value of 3.8 percent annual growth ffom .1973-77 and an assumed·continuation of the post-1973 conservatiorr--trend.As mentioned in the Anchorage-Cook Inlet area evaluations.a conservation trend was apparent when comparing energy use growth rates for 1973-77 and 1970-73 (see table 7).Tied to this is the assumption of gradually increasing effectiveness of future conservation programs coupled with perhaps upper limits of.electric energy use.These are reflected in an average annual growth by the year 2000 or 2 percent for high range,1 percent for mid~range,and 0 percent for low range.These assumptions result in decreased growth rates for each five-year increment,as shown below: Time Period High Mid Low 1980-1985 4.5%3.5%2.5% 1985-1990 3.5% 3.0%2.0% 1990-1995 3.0%2.5%1.5% 1995-2000 2.5%2.0%1.0% 2000-2025 2.0%1.0%0% Multiplying these growth rates by forecasted 1980 values of kwh/capita resulted in the energy use estimates. The 1980 mid-range value of kwh/capita was derived from the 1973-1977 average annual growth of net generation.The 1980 net generation was estimated.The Anchorage-Cook Inlet mid-range assumption of 12 percent annual load growth rate for 1977-80 net generation came from a historical 12.7 percent.The respective Fairbanks-Tanana Valley values were 10.5 percent assumed,10.6 percent historical.Mid-range 1980 kwh/capita was calculated using the estimated net generation and projected population.The 1980 high and low range average annual kwh/capi ta growth rates for Fairbanks-Tanana Valley were assumed 120 percent and 80 percent of the calculated mid-range value respectively. Comparable values for Anchorage-Cook Inlet were 130 percent and 80 percent.The differences between the two areas reflect population estimates and an attempt to derive a reasonable 1977-80 transition period coupled with the population estimates. Peak load (l~)forecasts were calculated using a 50 percent load factor. Anchorage-Cook Inlet area load factor averaged 51.9 percent between 1970 and 1977 and 51.0 percent between 1973 and 1977.Fairbanks area averaged 48.9 percent and 48.4 percent in the same periods. 1/Conservation here includes results of the fuel cr1S1S and perhaps of nationwide publicity on the need for saving energy.Other factors may be involved,but no other events are as coincidental with reduced energy use as is the fuel crisis. 3S " National Defense -Historical data from Army and Air Force installations in the Anchorage and Fairbanks areas indicate reasonable energy assumptions to be: 1.0 percent annual growth for mid-range forecast,1 percent for high range,and -1 percent for low range. 2.A 50 percent load factor was assumed for use with energy (net generation)to obtain peak load. Self-Supplied Industries -The following assumptions were developed from existing data and conditions.consultations with many knowledgeable people in government and industry,and from reports on future developments. 1.Industries will purchase power and energy if economically feasible. 2.Forecast based on listing in the March 1978 Battelle report. 3.High range includes existing chemical plant,LNG plant,and refinery as well as new LNG plant,refinery.coal gasification plant, mining and mineral processing plants,timber industry.city and aluminum smelter or some other large energy intensive industry. 4.Mid-range includes all of the above except the aluminum smelter. 5.Low range includes all listed under high range except the aluminum smelter and the new capital. 6.In some instances,high,mid,and low range may be differentiated by amount of installed capacity as well as the type of installations assumed. 7.No self-supplied industries are assumed for the Fairbanks-Tanana Valley area.Any industrial growth has been assumed either (1)included in utility forecasts or (2)not likely to be interconnected with the ~rea power systems. 8.Net generation forecast calculated from forecasted capacity and a plant factor of 60 percent. The ISER model assumed the following Cook Inlet area industrial scenario.It is compared to industries assumed for the self-supplied industrial forecasts of this report. 36 ISER Cook Inlet Industrial Scenarios Assumptions Self-Supplied Industries Forecast HIGH RANGE Oil treatment and shipping facilities Small LNG Beluga Coal (40 emp loyees in shipping) New capital (2,750 employees 1982-84) Refinery-petroche~ica1 complex l! Pacific LNG Bottom fish industry Oil lease development No new pulp mills or sawmills Existing refinery (2,.4 MW) Existing LNG plant (.4 to .6 MW) Coal gasification (0 to 250 MW)2/ New city (0 to 30 MW)- New refinery (0 to 15.5 MW) New LNG plant (0 to 17 MW) Mining and mineral plants (5 to 50 MW) Timber (2 to 12 MW) Existing chemical plant (22 to 26 MW) Aluminum smelter or other energy intensive industry (0 to 280 MW) MiD RANGE 1/ LOW RANGE Pacific LNG New LNG plant (0 to 17 MW) Existing refinery (2.4 MW) Existing LNG plant (.4 MW) Existing chemical plant (22 MW) Coal gasification (0 to lOMW) New refinery (0 to 15.5 MW) Mining and mineral plants (0 to 25 MW) Timber (2 to 12 MW) A recent decision by ALPETCO changes this to the Valdez area. The changes involved were not enou~h to warrant forecast revisions. Part of coal gasification could be equivalent to "Beluga Coal,"but .it i.s much more than "40 emp loyees in shiPping." At the time this forecast and analysis was performed,no ISER mid-range projections of populations and employment had been developed. 37 Estimate of Future Demands Using the high and low population proj ections and high,mid,and low kwh/capita assumptions,six different net generation utility forecasts were obtained.From these,the high population/high energy use and the low population/low energy use were used for the high and low range final forecasts.The mid-range final forecast came from averaging the high population/low energy use and the low population/high energy use forecasts.In lieu of a miq-range net generation based on a mid-range population projection,these last two forecasts were enough alike to justify the average as mid-range net generation. Near the completion of this analysis,ISER provided APA with a mid-range population proj ection.Comparing the previous results with forecasts using these mid-range proj ections,APA concluded that the two were consistent and that no changes were neeessary. National defense and self-supplied industrial forecasts were calculated from the assumptions and summarized with the utilities on table 10 for the Anchorage-Cook Inlet area and tab Ie 11 for the Fairbanks-Tanana Valley area.Railbelt totals,both peak load demand and net generation, are summarized on table 12.Appropriate graphs follow each table on figures 9 and 10 for Anchorage-Cook Inlet,11 and 12 for Fairbanks-Tanana Valley,and 13 and 14 for the Railbe1t totals. ~ I Trend lines based on 1973-1977 average annual energy growth are superimposed on the energy graphs,figures 9,11,and 13."-""" 1973-1977 Average Annual Growth Anchorage-Cook Inlet Fairbanks-Tanana Valley Railbelt 10.9% 7.1% 9.9% Historical and forecast energy use comparisons are summarized in table 9. Comparison with Other Forecasts This section compares the present forecast (1978)with two previous forecasts,and forecasts available from various utilities. The previous forecasts included the 1976 report and its 1977 update. The 1977 update used 1975 criteria and assumptions.See table 13 for a comparison tabulation.In general,the present forecasts produced values less than the previous ones. 38 Table 9 NET ANNUAL PER CAPITA GENERATION (KWH) RAILBELT AREA UTILITIES Upper Susitna Project Power Market Analysis Historical High Mid Low Historical High Mid Low 1970 1977 1990 2000 .2025 Anchorage-Cook Inlet Area 4980 7630 16,300 21,400 35,100 14,000 17,500 22,400 12,000 13,600 13,600 Fairbanks-Tanana Valley Area 5655 10,240 18,400 24,000 39,000 16,300 20,300 26,000 14,100 15,800 15,900 APA 11/78 Energy use per capita nearly doubled in both areas in the historical seven years.Growing use of electric space heating,electric cooking in place of gas and oil,and many other possibilities can justify the assumptions shown.Again,conservation has been factored in through decreasing growth rates. 39 J.<iUl.e l.V POWER AND ENERGY REQUIREMENTS ANCHORAGE-COOK INLET AREA Upper Susitna Project Power Market Analysis PEAK POWER 1970 1973 1977 1980 1985 1990 1995 2000 2025 MW MW MW MW MW MW MW MW MW UTILITY High 620 1,000 1,515 2,150 3,180 7,240 Mid 165 230 424 570 810 1,115 1,500 2,045 3,370 Low 525 650 820 1,040 1,320 1,520 NATIONAL DEFENSE High 31 32 34 36 38 48 Mid 35 33 41 30 30 30 30 .30 30 Low 29 28 26 24 24 18 J:-INDUSTRIAL 0 IUgh 32 344 399 541 683 1,615 Mid 12 12 25 32 64 119 199 278 660 Low 27 59 70 87 104 250 TOTAL High 683 1,376 .1,948 2,727 3,901 8,903 Mid 212 275 490 632 904 1,264 1,729 2,353 4,060 Low 581 737 916 1,151 1,4~8 1,788 ANNUAL ENERGY GWH GWH GWH .GWH GWH GWH GWH GWH GWH----UTILITY High 2,720 4,390 6,630 9,430 13,920 31,700 Mid 744 1,108 1,790 2,500 3,530 4,880 6,570 8,960 14,750 Low 2,300 2,840 3,590 4,560 5,770 6,670 NATIONAL DEFENSE High 135 142 lfl9 157 165 211 Mid 156 161 131 131 131 131 131 131 131 Low 127 121 115 105 lOLl 81 INDUSTRIAL High 170 1,810 2,100 2,840 3,590 8,490 Mid 2 45 70 170 340 630 1,050 1,460 3,470 Low 141 312 370 460 550 1,310 TOTAL High 3,025 6,342 8,879 12,427 17,675 40,401 Mid 902 1,314 1,990 2,801 4,001 5,641 7,751 10,551 18,351 Low 2,568 3,273 4,075 5,125 6,424 8,061 eJ ;;,.'JA 2/79 ;( ) hj 1-'- lQ C I-i (D \.D LOW Upper susitna Project Power Market Analysis ANCHORAGE-COOK INLET AREA ENERGY FORECAST 2000 1- 30,000 40,000 100,000 r'-r -., 90,000 7 I 80,000 70,000 60,000 50,000 2"0,000 (J) cr ::> 0:r: l-10,000l- <t 9000 3:8000 <t 7000 <:)-6000 C> 5000 4000 3000?; ~ ..... t'-J "-...] OJ .r:--...... 1000 II'1 1 I I !I I I I I I I 1970 1915 19711980 19851990 1995 2000 2005 2010 2015""2020 2025 YEAR upper Susitna Project Power Market Analysis ANCHORAGE-COOK INLET AREA PEAK LOAD FORECAST 3000 4000 10 1 000'I 9000 8000 7000 6000 5000 2000 LOW I /'./'-(J) }- ./:"-}-N <r 3';1000«900 Cl 800 W 700~I I //~"'"'- 600 500 400 ?ti 300V I hj I /-'-~lQ ~ I-'I 11 IV CD ........200 I--.l I-' 00 0 100 I "I !I I I I.I I I J 1970 19751977 1980 1985 1990 19?~...·...l.·"2000 2005 2010 2015 2020 2025 .~AR ~c > )') Table 11 POWER AND ENERGY REQUIREMENTS FAIRBANKS-TANANA VALLEY AREA Upper Susitna Project Power Market Analysis PEAK POWER 1970 1973 1977 1980 1985 1990 1995 2000 2025 MW MW MW MW MW MW MW MW MW---------UTILITY High 158 244 358 495 685 1,443 Mid 56 73 119 150 211 281 358 452 689 Low 142 180 219 258 297 329 NATIONAL DEFENSE High 49 51 54 56 59 76 Mid 44 41 41 47 47 47 47 47 47 .p-Low 46 44 42 40 38 29w TOTAL High 207 295 412 551 744 1,519 Mid 101 114 160 , 197 258 328 405 499 736 Low 188 224 261 298 335 358 I ANNUAL ENERGY GWH CWH GWH GWH GWH GWH GWH Glill GWH----------_.- UTILITY High 690 1,070 1,570 2,170 3,000 6,320 Mid 239 324 483 655 925 1,230 1,570 1,980 3,020 Low 620 790 960 1,130 1,300 1,440 NATIONAL DEFENSE High 213 224 235 247 260 333 Mid 203 200 207 >207 207 207 207 207 207 Low 203 193 184 175 166 129 TOTAL " High 903 l,29!f 1,805 2,417 3,260 6,653 Mid 443 524 690 862 1,132 1,437 1,777 2,187 3,227 Low 823 983 1,144 1,305 1,466 1,569 APA 11/78 FAIRBAN~(S-TANANA VALLEY AREA / OPper Susitna ~~c~tRp~wy'!r~c~~~~i~T ~~~~ ",.9'd \G'r\0'1 ~\ 24000 3000 10,000r'-.------""'7'"-------.. 9000 7 I 8000 7000 6000 5000 J 100 I I I I !I I I I !,!I 1970 1975 1977 1980.1985 1990 1995 2000 2005 2010 2015 2020 2025.) ). l 2020 20252015200520)01990.1995 2000 YEAR 1985 FAIRBANKS-TANANA VALLEY AREA PEAK LOAD FORECAST Upper Susitna Project Power Market Analysis 100C:I!1 I !I !!!I I I 1970 1975 1977 1980 4000 3000 10,000 i I 9000 8000 7000 6000 5000 2000 en .t:'-I- V1 to-« ~.~1000 «900 (!)800W ::a 700 600 500 400 ~300 LOW ~ I f-' I N I hJ ""--J 200 I ..... co I l.Qs:: Ii CD f-' N ./:'- 0'1 Table 12 POWER AND ENERGY REQUIREMENTS (RAILBELT AREA) Upper Susitna Project Power Market Analysis PEAK POWER 1970 1973 1977 1980 1985 1990 1995 2000 2025 MW MW MW MW MW MW MW MW MW------ -- -- -TOTAL High 890 1,671 2,360 3,278 4,645 10,422 Mid 313 389 650 829 1,162 1,592 2,134 2,852 4,796 Low 769 961 1,177 l,l,[,9 1,783 2,146 Average Annual Growth for period % %%%%%%% High 11.0 13.4 TI .6.8 7.2 3.3 Mid 7.S 13.7 8.4 7.0 6.5 6.0 6.0 2.1 Low 5.8 4.6 4.1 4.2 4.2 0.7 ANNUAL ENERGY TOTAL High Mid Low Average Annual Growth for period High Mid Low Note:The increase addition in 1985 of (280 MW). ) GWH GWH GOO GWH .GWH GWH.GWH GWH GWH 3,928 7,636 10,684 14,844 20,935 47,054 1,345 1,838 2,681 3,663 S,133 7,078 9,528 12,738 21,578 3,391 4,256 5,219 6,430 7,890 9,630 %%%%%%%% 13.6 14.2 6.9 6.8 TI 3.3 11.0 9.9 11.0 7.0 6.6 6.1 6.0 2.1 8.1 4.6 4.2 4.3 4.2 0.8 in 1980-1985 high range growth rates reflects the the energy intensive self-supplied industry load APA 11/78 ) Upper Susitna Project Power Market Analysis TOTAL RAILBEL T AREA ENERGY FORECAST 30,000 40,000 100,000 I )1 90,000 80,000 70,000 60,000 50,000 20,000.- ma:: ::> 0.r:--:r"--J I-10,000 C ///LOWI-9000<X:8000~. <t 7000 C!) 6000- C!) 5000 4000 ~3000 ~)'.hj ~. ;rJ LQr::H Iil'V CD"'-2000 .--.j •i-'OJ W 1000 I J I I I I I I I I I I I 1970 1975 1977 1980 1985 1990 1995 2000 2005 2010 2015 2020 202.5...YEAR TOTAL RAILBELT AREA PEAK LOAD FORECAST Upper Susitna Project Power Market Analysis• 3000 4000 10 1000 i ::::;:;;;0'"I 9000 8000 7000, 6000 5000 Table 13 """,COMPARISON OF UTILT1 ENERGY ESTIMATES )1976 MARKETABILITY REPORT-,Uf .....E OF 1976,AND 1978 ANALYSIS Upper Susitna Project Power Market Analysis Anchorage-Cook Inlet Fairbanks-Tanana Valley Total Railbe1 t Forecast\1976 Update 1978 1976 Update 1978 1976 Update 1978 Year Ran~Report of 1976 Forecast Report of 1976 Forecast Report of 1976 Forecast 1974 Historic 1,305 1/1,189.7 1/330 353.8 1,635 1,543.5 1975 High 1,489 377 1,866 Mid 1,467 371 1,838 Low 1,450 367 1,816 Historic 1,413.0 450.8 1,863.8 +:--1976 High 1,699 430 2,129 \0 Mid 1,649 417 2,066 Low 1,611 407 2,018 Historic 1,615.3 468.5 2,083.8 1977 High 1,939 490 2,429 Mid -1,853 469 2,322 Low 1,790 453 2,242 Historic 1,790.1 1,790.1 482.9 482.9 2,273.0 2,273.0 1980 High 2,850 2,660 2,720 700 720 690 3,550 3,380 3,410 Mid 2,580 2,540 2,500 660 690 655 3,240 3,230 3,155 Low 2,410 2,460 2,300 610 660 620 3,020 3,120 2,920 1990 High 6,880 6,300 6,630 1,660 1,700 1,570 8,540 8,000 8,200 Mid 5,210 5,000 4,880 1,270 1,360 1,230 6,480 6,360 6,110 Low 4,420 4,410 3,590 1,050 1,180 960 5,470 5,590 4,550 2000 High 15,020 13,600 13,920 3,500 3,670 3,000 18,520 ·17-,270 16,920 Mid .9,4io 8,950 8,960 2,230 2,440 1,980 11 ,650 11,390 10,940 Low 6,570 6,530 5,770 1,530 1,750 1,300 8,100 "8,280 7,070 !.7-Fi14 historiclfata revised between 1975 and 1978.APA 11/78 GWH =million kwh Further comparisons confirm that the 1976 report forecast was valid. Historic values through 1977 fell between the high and low ranges of the forecast. The 1976 report was based on load data through 1974 and the following assumptions for uti1it¥load growth: Average Annual Growth Rates 1974-1980 1980-1990 1990-2000 High Range 14.1%9.0%8.0% Mid-Range 12.4 7.0 6.0 Low Range 11.1 6.0 4.0 The following percentages compare this report and the above assumptions. Average Annual Growth Rates From 1978 Utility Energy Forecast High Range Mid-Range Low Range 1977-1980 14.5% 11.5 8.7 1980-1990 9.0% 6.8 4.5 1990-2000 7.5% 6.0 4.5 The 1976 report based the utility energy forecast on assumed average annual growth rates.The 1978 report based the fOrecast on assumed growth in population and per capita energy use.Both reports considered energy conservation,but it was given more specific and higher importance in the 1978 forecast. Forecasts available from various utilities are tabulated on tables 14, 15,and·16.Some were done by the utilities,some by consultants,and some by REA.All data was tabulated and,where necessary,extrapolated as part of the State Alaska Power Authority Railbel t Intertie Study. Comparisons are summarized in 5-year increments. Utility Forecasts 1978 Susitna Forecasts Energy (GWH)High Mid Low 1980 3,344 3,410 3,155 2,920 1985 6,277 5,460 4,455 3,630 1990 10,965 8,200 6,110 4,550 1995 17,748 11,600 8,140 5,690 2000 26,550 16,920 10,940 7,070 Peak (MW) 1980 725 778 720 667 1985 1,377 1,244 1,021 830 1990 2,.986 1,873 1,396 1,039 1995 3,835 2,645 1,858 1,298 ~2000 5,641 3,865 2,497 1,617 50 The utility forecasts run higher than those of this report.No definite reason for the differences can be made other than the utilities assumed higher growth rates.The basis of the utility assumptions was not considered in this study. 51 ----------------------------rF'--------------------------- Table 14 ~, UTILITY ENERGY FORECASTS (GWH) ANCHORAGE-COOK INLET AREA Upper Susitna Project Power Harket Analysis Year AML&P 1/CEA 2:../MEA '}j HEA !:./Total 1979 634 1,109 280 310 2,333 1980 699 1,283 333 374 2,689 1981 771 1,468 395 452 3,086 1982 847 1,679 468 546 3,541 1983 930 1,921 559 620 4,030 1984 1,018 2,197 668 705 4,588 1985 1,111 2,509 799 800 5,219 1986 1,210 2,810 954 909 5,883 1987 1,313 3,147 1,140 1,033 6,634 1988 1,422 3,525 1,322 1,155 7,424 1989 1,534 3,948 1,534 1,290 8,306 1990 1,650 4,422 1,779 1,442 9,293 1991 1,770 4,864 2,064 1,611 10,309 1992 1,891 5,350 2,394 1,801 11,437 ,.-,." 1993 2,014 5,885 2.706 1,978 12,584 1994 2,138 6,474·3,057 2,173 13,843 1995 2,245 7,121 3,455 2,388 15,209 1996 2,357 7,691 3,904 2,623 16,575 1997 2,475 8,306 4,412 2,882 18,075 1998 2,599 8,971 4,853 3,111 19,533 1999 2,729 9,638 5,338 3,359 21.113 2000 2,865 10,463 5,872 3,626 22,826 Source:Obtained from utilities in 1978 for Alaska Power Authority Rai1be1t Intertie Study. 1/Anchorage Municipal Light &Power Department 2/Chugach Electric Association 3/Matanuska Electric Association 4/Homer Electric Association APA 1/79 52 Table 15 UTILITY PEAK DEMAND FORECASTS (Mttl) ANCHORAGE-COOK INLET AREA Upper Susitna Project Power Market Analysis Year AML&P 1/CEA Y MEA 2J REA I:..!Total 1979 124 239 67 64 495 1980 138 271 81 78 567 1981 152 310 97 94 653 1982 167 355 116 113 752 1983 184 406 142 129 860 1984 202 465 171 146 983 1985 221 530_207 166 1,124 1986 241 594 251 188 1,274 1987 263 655 303 214 1,445 1988 285 745 343 239 1,612 1989 309 835 389 267 1,800 1990 333 935 442 29)1 2,008 1991 358 1,028 501 334 2,222 1992 384 1,131 569 373 2,458 ·1993 411 1,244 630 410 '2,695 1994 437 1,369 698 451 2,954 1995 461 1,505 773 495 3,234 1996 486 1,626 857 544 3,512 1997 512 1,756 950 598 3,816 1998 539 1,901 1,026 645 4,111 1999 568 2,048 1,108 696 4,421 2000 599 2,212 1,197 752 4,759 Source:Obtained from utilities in 1978 for Alaska Power Authority Railbe1t Intertie Study. 1/Anch.orage Municipal Light &Power Department 2/Chugach Electric Association 3/Mat8muska Electric Association 4/Homer Electric Association APAl/79 53 ·,".........-,--,------,-----"4'4--------------------- Table 16 ~I UTILITY ENERGY AND PEAK DEMAND FORECASTS FAIRBANKS-TANANA VALLEY AREA Upper Susitna Project Power Market Analysis Net Energy (GWH)Peak Demand (MW) Year GVEA 1./FMU :!:../Total GVEA FMU Total 1979 450 144 594 111 33 144 1980 502 153 655 123 35 158 1981 560 162 722 136 37 173 1982 625 172 796 151 39 190 1983 693 182 875 167 42 209 1984 769 193 962 .186 44 230 1985 853 205 1,058 206 47 253 1986 947 217 1,164 228 50 278 1987 1,050 230 1,280 252 53 305 1988 1,155 244 1,399 278 56 334 1989 1.271 259 1,529 305 59 364 1990 1.398 274 1,672 335 63 398 ~.1991 1,537 288 1.825 368 '66 434 1992 1,691 302 1.993 405 69 474 1993 1,843 317 2.160 440 72 512 1994 2.009 333 2,342 480 76 556 1995 2,190 350 2,540 521 80 601 1996 2,387 367 2,754 569 84 653 1997 2,602 386 2,987 619 88 707 1998 2,810 405 3,215 668 92 760 1999 3,035 425 3.460 722 97 819 "2000 3.278 446 3.724 780 102 882 Source:Obtained from utilities in 1978 for Alaska Power Authority Railbe1t Intertie Study. 1/Golden Valley Electric Association II Fairbanks Municipal Utilities APA1/79 54 Load Distribution Reservoir operation studies used in sizing reservoirs need an average monthly distribution of annual energy to help relate hydroelectric output to the elec;tric load.This section reports updated averages of monthly energy use divided by annual energy use wi thin the Anchorage-Cook Inlet area. This section also reports a study of hourly load distribution in the weeks of winter peak load (same as annual peak)and summer minimum peak load.By studying these load curves from several years,hydroelectric plant factor is evaluated.(See capacity section). The utility systems have had combined annual load factors slightly over 50 percent in the past few years (54 percent in 1977 as shown on figure 17)-.Data presented in table 17 shows that mid-summer peaks have been running about 60 percent of mid-winter peaks and that monthly load .factors generally exceeded 70 percent.For 1977,the December load factor was 76 percent.Figures 15 and 16 illustrate that winter and summer loads are quite similar.The load duration curves of figure 17 present these daily load curves concisely.The 1976 report contains daily load curves of previous years.Winter and summer curves are plotted together showing similarities of slope and shape. The update of average monthly energy'is presented.as percent of the r-,annual value in table 18.Average percentages used in the 1976 report compare closely with 1970-77 averages.Slight changes are reflected in the "recommended distribution"column.Winter load is about two-thirds of total. 55 SYSTEM DAILY GENERATION CURVEANCHORAGEAREAUpperSusitna project Power Market Analysis ,...'"'=#___.,.__~~_,."""""_"."""-_,.,,,,,,..,..,~_,.,;~-'-'~t,. 4~ ;I .i I i iI i I lJ1 0'1 ,..'''"I,III'I'!I4.n111 I . I I II I '~ _:rn;H-t+t+t11 1 III 'lInWr--··--·..·~I '1'1 I --.n~l":I!m.h.e.,6 ..11.t91S I 'I .". 1rtliIIIIIIUIIIIWIIIIIL I I:II:I ·1 I I I 1,111 h-ru- I ill,r!!1 I I l ",I ,I 1 I :!I 'I,ll I i I "'I '!:11 II i l i J -,!I I;I,I I I 6...l11 \,1-111111111111111 1 1'11 I I I I 1"l..lr'11 I ':I ~ rr;:-----.:~ ---+-J-t-t.-.w',rH-++-HJ+FlW1twttljh+ttllimttttlmtHm4-H-H~~FW-Wmn[[[OIITJ~II:I:-'i:,fl I ;I~......,.-.i"'" -,',P·hi:I ! I I I,I:i I :;:~; 120 /10 100i;j ~ f-' N '---.l OJ SUNDAY :':ONDAY TUESDAY WEDNESDAY SATURDAY DAYS OF THE WEEK )J .) , SYSTEM DAILY GL)ERATION CURVE·:',.) 'ANCHORAGE AREA Upper susitna Project Power Market Analysis II ill i 11./i'lIIITTl rm I: ;tjlllll':lIfllllllllll!'I,1 , I I lilllillilTill'\-1 J Ii II ."',!mfI'II:I!II !rnmII i !I !II i III i1:i II j 1III I I I I I I!i 11111'II !Ii I '~-!f~..lf.;LL~-f-l-l.l-l..J...:.LL1.:!,.u.~-:!:-L.l:l.::L1..!:J..L!-W-~~~6~~.;~i ~i J iT·1 I 1\1-r-rTl'T~1!'1 \I I:11111111\IIIIII\llllllllllllllllltll!rTr:lmmTn:llTlrmrrml .11; SUNDAY TUESCAY •mNESOAY THURSDAY FilIl>AY SATURDAY ~.EXCESS 0'IH?:I OvER '918 .'"DAYS OF THE WEEK ..-.~-.--_._----"-----._-- Figure 17 ANCHORAGE AREA LOAD DURATION CURVE 1977 Upper Susitna Project Power Market Analysis100r,---...,...---,..-----,---,.-----r--.,-----,--...,..---,---; June 1977 December 1977 Summer Peak Load30 540/0 load Factor 70 ..I--Winter Peak Load -.----.-~-------------------650(0 Winter Base Load 80 90 60 ~« L.tJ 50a... ~0 40 Summer Base Load 20 10 o 10 20 30 40 50 60 70 80 90 100 %TIME APA 12/78 58 'Table Ii LOAD DISTRIBUTION'CHARACTER1STICS MONTHLY P~AK LOADS'AND LOAD FACTORS'. Upper Susitna Prqj ect Power Market AnaIya.i~,;! ) I I }' I 1971-1972 .1972-1973 1973-1974 1974-1975 1975-1976 1975-1977. .J ...-...;:J::.u -.u ::c .u .., JI.ffi l)~.~0 ~~0 ~~,I)JI.:;:U X .,.0, r.!&to to ttl ~ttl ~t:I :;a d 2 lOa t;l (}&14 (l)~.(l)t:..:... ~"l,O p.,""p.,"A "0 'I:0 't1 0 ~0 'd 0 ';;l 0 ';:l ~ri .s ~ri ttl ~ri,rl ri ro ~ri ",.....-I (5~ttl :::III .s ~III 0 ...ro oS ~~0 ~r:~.A g >.;;0;j ~g );I-l ...~;::I >.A ;::I ><h "'"~>-,.:: :3 e'0\~C'C t;'\G':.:c ~\.l .~l:H .~t:\.l .~C J.<,:>!.<J.<-r.:l .::(}S 1:.1 C <QJ I::.::(l),I::ttl <(J tJ (J -5 ('J c ~t:o·!J c::0 (l)c ~1:.1 C 5 <J C 5:::p.,.P ~dP ~:,,;Il<n w ::<:tl<.'1'14 tl<.,~:.::t..c'.'~::: I )eto!:lc::IS5.8 73 94.1 68 209.2 74 10B.8 70 224.3 B2 122.7 73 252.9 71 134.3 71 342.2 81 153.0 60 359.a S8 182.2 63. ~o'Je:;-';'er 222.8 aa 113.0 70 -236.3 83 124.4 73 269.6 98 .144.6 74 266.2 .75 156.0 a1 367.6 87 ,196.2 74 360.7 as 193.8'75 'ec~::-.ber 236.2 93 121.1 70 260.7 92 .143.3 74 266.9 97 147.0 74 314.9 89 -170.7 i3 420.5 100 226.3 72 ~oa.3 100 223.4 74. ra:r~~::y 254.5 100 135.3 72 233.0 100 153.6 72'274.5 100 159.3 78 354.1 100 180.8 69 394.1 94 213.3 73 376.4 92 209.9 75 lal:':-t:.z.=y 22~.5 88 115.3 76 -259.6 92 127.5 73 264.5 .96 139.4 79 316.7 89 166.9 78,383.3 'n 203.5 i6 356.8 81 181.7 76 .. :arch 222.8 87 119.2 70 225.1 80 125.5 75 '2'-:9.4 '91 ·135.5 73 26B.6 .76 156.6 7S'342.,1'81 187.6 7'-:,369.0 90 :WS.&76 ,p:il 176.7 69 96.6 76 196.4 69 105.4'75 201.6 73 112.4 77 249.0 70 129.2 72 2,85.3 6B 159.0 77 334.4 82 177;0 73 :ay 157.9 62 87.8 75 176.7 62 9a.5 75 180.4 66 104.17S 222.0 63 120.9 73 253.6 60 145.0 77 2St,.S 70 161.3 76 ·~:'I.e ''152.1 66 78.5 72 165.2 58 87.6 74 176.2 64 95.4 75 209.0 59 113.Q 75 236.1 56 128.9 76 265.0 65 H8.1 79 'a1y 146.8 '52 76.6 70 162.8 59 .89.S 74,178.9 65 97.5 73 207.0 58 110.9 72 248.0 59 134.4 73 257.!.63 141.3 74 ,\::.gust.134.5 54 86.9 75 175.9 64 96.2 73 195.7 71.101.9 70.211.5 61 UB.3 73 250.6 60 139.9 73 271.8 67 151.7 75 ~pt.Cl:':ocr I 179.6 . 64 92.9 72 194.5 71 100.8 72 210.3 77 106.1 70 247.4 70 131.9 74 278.0 66 151.2 76 318.9 79 166.7 73 . in,St:::,~e~·?~a:'{ =:57.7f.1 57.5t.1 64.2~58.59"56.~'G 63.O~. ~:,.~,·':'ntc=?O~:~ l/Rcprescnts s~m of loads fo~the Anchorage (kV~&?,C~A) --and Fai~ba~~s (FMv,GVEA)utilities Table 18 c~ MONTHLY ENERGY REQUIREMENTS AS PERCENT OF ~rruAL REQUIREMENT Upper Susitna Project Power Market Analysis 1970-1972 1970-1977 Utility Utility Recommended MONTH Loads 1/Loads 2/Distribution 3/ Oct.7.9 8.1 8.2 Nov.8.9 9.2 9.0 Dec.10.2 10.2 9.7 Jan.11.3 10.8 10.2 Feb.9.2 9.3 9.1 Mar.9.8 9.4 9.1 .April 8.0 7.8 7.9 May 7.2 7.3 7.6 June 6.5 6.6 7.0 July 6.4 6.7 7.1 Aug.7.1 7.1 7.4 Sept.7.5 7.5 7.7 Total 100.0 100.0 100.0 SEASONAL Oct.-April 65.3 64.8 63.2 May-Sept.34.7 35.2 36.8 ~ l/Combined loads of CEA~AML&P,GVEA~FMUS,for Oct.1970-Sept.1972. Basis for (1975 Susitna Power market analysis)1976 report. 1/Combined net generation of CEA,fu~&P,APA,GVEA,FMUS,for Oct. 1970-Sept.1977.Updated Basis. 1/Assumes total requirements consisting'of 25 percent industrial loads and 75 percent utility loads.Update of previous recommendations. 60 Capacity Requirements With reference to the load factor evaluations in the previous section,a trend towards somewhat higher annual load factors in the future is anticipated.In addition to benefitting from any load diversity in the interconnected system,peak load management (including such practices as peak load pricing)offers considerable opportunity for improving load factors,which in turn reduces overall capacity requirements for the system in any given year.For planning purposes,it is assumed that the annual system load factor will be in the range of 55 to 60 percent by the latter part of the century. Sys tem capacity requirements plus The 1Gwer summer and'repairs. requirements are determined by winter peak load allowances for reserves and unanticipated load growth. peaks provide latitude for scheduled unit maintenance System daily peak load shapes indicate that a very small portion of the capacity is needed for very low load factor operation.Some of the gas turbine capacity now used for base load is expected to be used mainly for peak shaving purposes,eventually.It will be operating during peak load hours for the few days each year when loads approach annual peak, and will be in standby reserve for the balance of the year.Figure 17. the annual peak week duration curve,shows that the highest 10 percent load occurs for 30 percent of the week (about two days). Reliability standards would be upgraded as the power systems deveJ-op. Likely in~lusions are specific provisions for maintaining spinning reserve capacity to cover possible generator outages and substantial improvements in system transmission reliability. Results -Examination of the winter load duration curve (figure 9) indicates that the base load portion is about 65 percent of total load and the peak load is about 35 percent of total load.Load factor for the peak portion is about 54 percent.Winter weekly load factors are approximately 80 percent.This is illustrated in the winter and summer load duration curves by proportioning the areas under the curves to the total possible area if peak load occurred 100 percent of the time. An annual plant factor of 50 percent is recommended for the proposed Upper Susi~a Project.This is largely a judgment factor and is based on the folloWing considerations: 1.The recommended plant factor provides for serving a proportional share of both peaking and energy requirements throughout the year while maintaining adequate flexibility to meet changing conditions in any given year. 2.Any significant reduction in this capacity could materially reduce flexib Hity. 61 ------~--_.---------------.,,-------- 3.A significant market for low load factor peaking capacity seems unlikely within the foreseeable future.Load management and additional industrial loads will probably increase the overall system load factor in the future.It is expected that several existing and planned gas turbine units could eventually be used for peak shav,;ing. 4.It is recognized that the mode of operation for the hydro will change through time.In the initial years of operation,it is likely that the full peaking capacity will be used infrequently.For example, the mid-range Railbelt estimated system peak load for the year 2000 is 2,852 MW.Assuming load shapes similar to the current Anchorage area loads,the winter peak week would require about 1,850 MW of continuous power to cover the base loads and about 1,000 MW of peaking power.Load factors of the peak portion would be about 50 percent. A design capacity based on 50 percent plant factor applied to average annual energy (primary plus secondary)appears appropriate.Machine overload capability contributes to spinning reserves for emergencies or other short term contingencies. The Corps based nameplate capacity on 50 percent plant factor applied to critical year firm energy.This smaller capacity,when applied to average annual energy,results in a 56 percent plant factor.APA feels the smdller design capacity may unduly reduce flexibility. 62 .~. 1 PART VI.ALTERNATIVE POWER SOURCES Introduction This section examines alternative power supply options in the Railbelt in lieu of the Upper Susitna Project and presents detailed cost estimates of power from new coal-fired steam plants. Alternatives premised on unproven technology were eliminated. Alternatives Considered Potential 8,lternative sources of electric power generation are identi- fied by energy type.They are coal,oil and natural gas,hydro, nuclear,wind,geothermal,and tide. Some alternatives will be restricted in time or capacity because of Federal energy policy controlling use of energy resource.Others will be restricted by practical available energy supply.Still others are impractical because of lack of large-scale technology. Coal Evaluation of coal utilization is based on mine-mouth coal-fired steam generation.Potential advanced technology,such as gasification,is not considered because,development would not be available within this study period. Recent studies provide general information about possible locations, s~z~ng,and cost of new steamplants,but Alaska specific data are limited and extrapolations have been made for local conditions. Information sources of specific interest for this analysis are:studies by Battelle Pacific Northwest Laboratories (March 1978);the Electric Power Research Institute (EPRI)(January 1977);and the Washington Public Power Supply System (WPPSS)(June 1977);the Federal Energy Regulatory Commission (FERC)determination of power values for the Bradley Lake Project (October 1977)and the Upper Susitna Project (October 1978);and evaluations of costs for the proposed Golden Valley Electric Association (GVEA)plant additions at Healy.These are all listed in the bibliography. Location It is assumed that new coal-fired steamplants would be located near the Beluga fields for service to the Anchorage-Cook Inlet area and at Healy for service to the Fairbanks-Tanana Valley area.The plants would use known but undeveloped coal resources at Beluga and the existing coal mining operation near Healy. 63 It is recognized that other locations are possible.For example,it may be possible to locate a coal-fired plant on the Kenai Peninsula and use coal from either local reserves or Beluga.A Kenai location might offer co-generation possibilities because steam could:be reused in manufacturing by the petrochemical industry.The potential for mining coal on the Kenai Peninsula is substantially less attractive thaI].for Beluga because of thin coal seams and other geologic factors. Capaci ty -These analyses are for two-unit 200-W;""and SOO-MW plants. This size range is considered appropriate for new coal-fired plants that might come on-line between 1985 and 2000. Investment Cost -Table 19 summarizes unit investment costs for new coal-fired plants presented in several recent studies.The data assembled by each entity is quite complex with respect to original estimated price levels,inflation to updated price levels,or projected future on-line dates,size,pollution control equipment,location,type of plant.and other items.Price levels were not adjusted to a uniform date because of the complexity of data involved. All 1977 and 1978 estimates are substantially higher than APA estimates for the 1976 Alaska Power Survey and the 1976 report. The most in-depth analysis was the WPPSS study which investigated the construction.of 1,OOO-MW steamplants at 10 plant sites in Washington, Montana,and Wyoming.Several grades and sources were assumed.Costs were estimated for with and without sulphur dioxide scrubbers (scrubbers).Twenty-two options of plant sites,coal supply,and trans- portation were investigated. APA's estimate of coal-fired steamplant investment costs is derived from the WPPSS study,Procedures for adjusting costs to current Alaska conditions are similar to the analysis used in the appended Battelle report. The basic cost in the WPPSS study for a 1,000 MW single unit plant in operation during mid-1976 was: ,-... Without Scrubbers With Scrubbers $554/kw $684/kw The WPPSS procedure increased these costs for the quality of the coal used and other specific powerp 1ant site conditions.The coal quality problems have not been considered in this estimate,and the construction site variable is assumed to be included in the Alaska factor. 64 -)') Table 19 COMPARISON OF INVESTMENT COSTS FOR COAL-FIRED STEAMPLANTS Upper Susitna Project Pow~rMa~ketAn'ciiysi'~ 0'1 \JI Source of Estimate ALASKA LOCATIONS APA )) APA Susitna River Studies Golden Valley Electric Association'!:../ 3Battelle-/ Price Level 'Oct.1978 Oct.1978 Oct.1978 Oct.1978 Jan.1975 Jan.1975 1974 1977 1977 1978 Jan.1977 Jan.1977 Jan.1977 Jan.1977 Jan.1977 Jan.1977 Location Healy or Beluga Healy or Beluga Healy or Beluga Healy or Beluga Healy or Beluga Healy or Beluga Healy Healy Healy Healy Beluga Beluga Healy or Nenana Healy or Nenana Anchorage Anchorage Size,MW 200 200 500 500 200 500 132 150 150 100 200 200 200 200 200 200 No.of Units 2 2 2 2 2 2 2 2 2 1 1 1 1 1 1 1 Scrubbers No Yes No Yes Ye-s Yes No No Yes Yes No Yes No Yes No Yes Investment Cost,$/kw 1,500 1,860 1,300 1,610 726 630 950 1,400 1,700 1,800 1.220 to 1,571 1,400 to 1,766 1,470 to 1,920 1,710 to 2.158 1,120 to 1,440 1,280 to 1.690 Oct.1978 Jan.1977 Oct.1978 Federal Energy Regulatory Commission Y Anchorage or Kenai Areas Anchorage or Kenai ------'-------~.-Areas Healy 450 450 230 2 2 -2 Yes Yes Yes 900 1,220 to 1;240 1,475 to 1,510 Tah1e 19 (cont.) COMPARISON OF INVESTMENT COSTS FOR COAL-FIRED STEAMPLANTS Vpper Susitna Project ,Power Mi.HlcetAna!ysis Source of Estimate Price Level Location Size.MW No.of Units Scrubbers Investment Cost.$/kw The 1978 estimates assume operation include 5 percent annual inflation.) !I APA's estimate is based 1argly on the WPPSS study with adjustments for Alaska conditions and size of plant. Future inflation not shown.". 2/GVEA 1974 estimate assumed units hecoming operational in 1983 and 1986. -in 1984 at $2.500/kw assuming 7%inflation. 3/Battelle's estimates are based on adjusting both WPPSS and EPRI study data.The higher figures are from the -EPRI study.Their studies with future operation dates include inflation. 4/Scrubbers are assumed included in the cost. S/This is the basic study adjusted by APA and Battelle above.The 1987 costs ~.).cThe July 1976 price level includes costs for init )operation in 1978. 7i J"The price level is 1975 costs adjusted to show cm:h:."s for a 1984 operation date. Adjusting the cost for the time between mid-1976 and October 1978 us~ng the Handy-Whitman Steamp1ant Cost Index increased the cost 18.4 percent. Without Scrubbers With Scrubbers $656/kw $810/kw Powerplants smaller than the 1,000 ffi{that will fit near-future Alaska power needs have a smaller total cost,but a larger cost per installed kilowatt.An adjustment needs to be applied to the costs to compensate for the loss of economy of the large scale plants.The factor recom- mended is the ratio of the plant size to the 0.85 exponent.A 500-MW plant thus costs 55.5 percent of a 1,000 MW plant,and a 200-MW plant costs 25.5 percent.Scaling the plants to 200 MW and 500 MW gives: .Plant Size Without Scrubbers With Scrubbers $Million 167,000 207,000 200 MW $/kw 835 1,035 $Million 364,000 450,000 500 MW $/kw 728 899 An Alaska factor of 1.8 was used to adjust Pacific Northwest costs to Alaska wages and conditions: Plant Size Without Scrubbers With Scrubbers $Million 300,000 372 ,000 200 MW 1,500 1,860 $Million 655,000 810,000 500 MW 1,310 1,620 Fuel Cost and Availability -There is a wide range of opinions about the probable future cost of coal.For many years,coal prices were set at a small margin above production costs so that coal could compete with low-cost oil and natural gas.This situation has changed drastically because of price increases for oil and gas and incentives for power generation and has resulted in industrial conversion to coal.Coal production costs are also increasing rapidly due to normal inflationary and regulation factors.FERC reported the national average price of coal at 96,.2¢/million Btu in July 1977,up from 80.8¢in July 1975.and 39.8¢in August 1973. Alaskan coal prices have shown sizable increases recently.The cost of coal at Healy in September 1978 was 80 cents per million Btu,up from 62 cents in 1975.The Fairbanks Municipal Utility System (f:t.1US)pays an. additional $6/ton shipping cost for Healy coal resulting in a price of $1.15 per million Btu at the powerplant in Fairbanks. 67 --"""1,--------------------- In October 1978,owners of the Beluga coal field stated that large ~. reserves in the Beluga coal field may compete in the world energy market at a price of $1.10 to $1.40/million Btu stockpiled on the shore of Cook Inlet.The conclusions were based on company studies that included geologic investigations,drilling,bulk sampling programs,'mining preparation,environmental evaluation,and navigation and shipping studies. FERC estimated $1.DO/million Btu for determination of power values in the Bradley Lake Project (October 1977).Other recent studies suggest this is a reasonable current (1978)cost for Beluga coal delivered to a steamplant at Beluga,with no allowance for price increase in future years. Earlier MA studies for the 1976 FPC Power Survey and the 1976 Susitna report .assumed $1.00 to $1.50/million Btu for coal at 1985 price levels in 1974 dollars.This included consideration of future economies of scale of larger mining operations. APA analyses for this report are still based on a coal cost of $1.00 to $1.50/million Btu for a mine-mouth plant at either Beluga or Healy for mid-1980 conditions.This is comparable with $1.28 in 1985,estimated by GVEA for Healy coal by increasing the current 80 cents by 7 percent annually.Because of the wide diversity of studies and opinions, analyses based on a range of costs are .presented. In this study,we are assuming fuel values will increase about 2 percent~. per year--more rapidly than overall price indexes.This is consistent with other analyses. 68 Table 20 GENERATION COSTS FOR CONVENTIONAL COAL-FIRED STEAMPLANTS Upper-Susitna Project Power Market Analysis 1985 COSTS (1978 PRICES)l/Plant Size,MW 200 500 Number of Units Investment Cost,Railbelt,$/kw Capital Cost,mills/kwh 2 1,860 38.5 2 1,620 33.5 Operation and Maintenance,mills/kwh Subtotal Assumed Fuel Costs,mills/kwh Transmission Cost to Load Center Total Energy Cost,mills/kwh 1994 ENERGY COST Capital Cost,mills/kwh Operation and Maintenance,mills/kwh Transmission Cost,mills/k~m Subtotal Fuel,Inflated 2%1985 to 1994 Total 6.5 5.6 45.0 39.1 1.00/mmBtu 1.50/mmBtu 10.0 15.0 10.0 15.0 4.0 4.0 3.0 3.0 59.0 64.0 52.1 57.1 Fuel escalated 2%/year 1985 to 1994 38.5 33.5 6.5 5.6 4.0 3.0 49.0 42.1 12.0 17.9 12.0 17.9 61.0 66.9 54.1 60.0 Fuel Escalated 7%/Year from 1985 to 1994; Capital Cost and O&M Escalated 5%/Year from 1978 to 1994 Capital Cost Operation and Maintenance Transmission Subtotal Fuel Total 80.0 69.7 13.5 11.6 8.3 6.2 101.8 87.5 18.4 27.6 18.4 27.6 120.2 129.4 105.9 115.1 l/APAestimate based on studies by Washington Public Power Supply System Studies 1977. 69 Cost of Power -The estimated total cost of electric power that would be generated by a coal-fired steamplant alternative to the Susitna project is presented in table 20.Development of the estimated cost applied to a plant in either the Beluga or Healy area is based on the investment and fuel costs discussed earlier in this section,and includes other criteria developed in this report.In summary,the parameters are: L Investment cost includes all construction,overhead,and interest during construction,and is based on updating and adjusting WPPSS Pacific Northwest costs for Alaska conditions.Annual capital costs are based on a 35-year life and 7 percent interest rate. ~ 2.Operation and maintenance costs are based on a detailed WPPSS personnel and materials estimate adjusted for plant capacity in the same manner as investment costs,increased by 50 percent for Alaska condi tions,as developed in the 1976 Alaska Power Survey,and indexed from January 1977 to'October ).978 using the U.S.Department of Labor index. 3.Fuel costs of both $1.00 and $1.50/kw are presented with a heat rate of 10,000 Btu/kwh. 4.Transmission costs are for lines connecting Beluga with Anchorage, and Healy with Fairbanks. The resulting average unit cost of electric power from coal-fired .~ steamplants to supply the Railbelt market area ranges from 5.21 to 6.40¢/kwh,varying with fuel cost and plant capacity. Table 20 also presents an analysis of the cost of energy with fuel costs escalated at 2 percent anually from 1985 through 1994 (Susitna project, Watana phase on-line)and fuel cost escalated at 7 percent annually from 1985 through 1994. Comparative Cost of Power (FERC)-FERC evaluated alternative costs for coal-fired steam plants at Beluga for the Anchorage area and Healy for the Fairbanks area as part of their power benefit studies for the Upper Susitna Project.• The FERC estimates of 4.93 to 5.64¢/kwh are in the same range as those estimated by APA for the Anchorage area.However,the FERC estimates of 4.02 to 4.30¢/kwh for the Fairbanks area are low compared to MA estimates.FERC estimated construction costs (July 1978)at $1,475/kw compared to $1,8l0/kw estimated by MA.In addition,GVEA recently estimated a cost of $1,800/kw for a comparable Healy steamplant. FERC data are based on: 1 •An Anchorage area plant assumed to be a two-unit 450-MW plant with fuel cost of $l.lO/million Btu and a heat rate of 10,000 Btu/kwh.The Fairbanks plant is assumed to be two units,totaling 230 MW,with a fuel cost of $O.SO/million Btu and a heat rate of 10,500 Btu/kwh.For ~. non-Federal cases,the Anchorage area plant investment cost was estimated at $l,240/kw and the Fairbanks investment cost at $1,47S/kw. 70 2.Financing is based on a composite Anchorage-Kenai interest rate of 7.9 percent with 75 percent financing by REA at 8.5 percent and 25 percent by the municipality of Anchorage at 6.25 percent.The interest :rate for Fairbanks is 5.75 percent assuming State of Alaska Power Authority financing.In comparison.a Federal rate of 6.875 percent is used for both areas.the same rate used in the Corps of Engineers benefit analysis. Oil and Natural Gas The Upper Susitna Project involves a large new power supply beginning in 1994,with an expected life in excess of 100 years. APA does"not believe that oil and natural gas are realistic alternatives for equivalent power supplies,particularly in .new of the timeframe (start in 1994)and very long life (through 2094). Hydro Criteria -Evaluation of possible hydroelectric generation alternatives to the Susitna project is based on comparing:(1)the potential generation capability,and (2)unit cost of power.Possible sites are identified by:(1)single sites with sufficient capacity to supply the projected power demands;(2)combinations of smaller sites within selected geographic areas and river basins;and (3)a combination of the best sites from all areas accessible to the Railbelt. The hydro evaluation considered power requirements ran.ging from 600 MW to 2,290 MW,which are,respectively,the low-range and high-range projected increases in Railbelt demands from 1990 to 2000.Associated annual firm energy requirements would range from 2,670 gwh to 10,260 gwh.By comparison,the Susitna project is scheduled to provide about 1.573 MW capacity and 6,100 gwh annual firm energy. Possible hydro generation alternatives were selected from the APA inventory of hydroelectric resources.The inventory estimates unit cost of power at the generator bus bar based on 1965-1966 cost at 3 1/4 percent intl~rest rate.Susitna inventory cost data indexed to 1975 price levels give unit costs within 10 percent of that determined for the 1976 report. Single Large Capacity Sites Seven single sites have sufficient capaci ty potential to be an alternative to supplying minimum Susitna market area requirements.These are within a maximum of 1.4 times the unit cost for Susitna power.However,land use designations (National Parks and Honuments and Wild and Scenic Rivers)and/or known maj or environmental impacts preclude.consideration of developing any of the sites at the present time. 71 The sites are: Site Holy Cross Ruby Rampart Porcupine Woodchopper Yukon-Taiya Wood Canyon Stream Yukon R. Yukon R. Yukon·R. Porcupine R. Yukon R. Yukon R. Copper R. (~, Firm Capacity Percent Energy MW of Susitna G';<1H/yr Cost 12,300 2,800 140 6,400 1,460 62 34,200 5,040 32 2,320 530 79 14,200 3,200 71 21,000 3,200 52 21,900 3,600 51 None of the above sites can be considered available resources in the 1990's timeframe.This is due to:(1)Holy Cross,Ruby,Rampart,and Woodchopper are main-s tem Yukon River sites with known maj or environ- mental problems,(2)Porcupine,Woodchopper,and Yukon-Taiya have major international c.onsiderations,and (3)Wood Canyon has a known major fishery problem. Si tes wi thin the Nenana River basin have also been identified in past work.Their economic feasibility depends upon being developed as a unit.However,several of the sites are located partially within Mount McKinley National Park and are precluded from development. In conclusion,no single,large hydro generation sites are available as alternatives to the Upper Susitna Project. Combination of Small Capacity Sites -Combinations of single sites with less capacity than the Susitna project consist of 78 sites within the Matanuska,Tanana,Yentna-Skwentna,Talkeetna,and Chulitna River basins,the northwest drainage of Cook Inlet,the Kenai Peninsula,and scattered small sites and small basins within the Railbelt area.None of these areas contain sites with total capacity potential to supply minimum Susitna requirements.(Site combinations with the most capacity--the Yentna-Skewntna River basin and Kenai Peninsula--total 609 ffi~and 646 ~w respectively,but with costs for individual sites ranging from 1.4 to 20 times Susitna costs.) If consideration is given to combining the best small sites from each of the geographic areas,12 sites totalling 1,276 MW are within the range of twice the cost of Susitna.Only one (Chakachamna)is near Susitna cost (103 percent),and has 366 MW potential. Chakachamna is partly within the new Lake Clark National Monument.Other new or proposed Federal land withdrawals would preclude sites with about half of the total potential of the combined sites.Other sites have various environmental impact potentials.Some streams that would be affected have major anadromous fish resources.Also,because the sites are widely distributed,the needed transmission systems would be fairly extensive and costly..~ 72 p~Summary -Based on examination of individual sites and combinations of sites.there are no hydro generation opportunities available to provide enough power to be an alternative to the Susitna Project.Small individual sites may be available.but would satisfy only a small portion of the market area demand.Other sites,with apparently acceptable quantity and economic capability.have been or will be precluded by land status designation. Nuclear Nuclear gen,=ration may be technically viable in Alaska.but probable cost and siting problems eliminate.it as a potential alternative to Susitna.Available information indicates that in other states.nuclear is economically competitive with coal,depending on specific conditions. Difficult conditions.possible seismic and environmental siting problems.and readily available coal indicate that nuclear generation will probably not be economically attractive in Alaska in the foreseeable future. Wind The State has shown serious interest in wind generation technology by developing pilot projects in the bush communities of Ugashik,Nelson Lagoon,and Kotzebue.Wind seems to provide near-term power for small communities presently dependent on high-cost diesel generation. The cost and applicable scale of technology does not make wind power a viable alternative for large near-future power demands. Geothermal Investigations to date have found no high quality geothermal resources suitable for power development in areas accessible to the Railbelt area. Geothermal potential is considered high in the Wrangell Mountains and portions of the Alaska Range,and may be applicable to the Railbelt in the future.At this time,insufficient data are available to define the resource.even for appraisal of the large Susitna project market. Tide There is a large physical potential for tidal power development in the Cook Inlet area where the State estimates that a total of 8,560 MW could be harnessed.A potential of 785 MW is estimated for Knik Arm alone, and approximately twice that amount for Turnagain Arm. Several different concepts have been developed for the Cook Inlet tidal potential because of the interest in alternative energy sources •There is merit to preparing a good reconnaissance of this alternative,as pointed out in the 1976 report.However.the scope of work involved to develop the tidal resource,the large cos t of development,and the important environmental considerations eliminate tidal power as a reasonable alternative to the Susitna project. 71 Conclusion The range of power options for the Alaska Railbelt is narrowing rapidly. 1.Oil and natural gas are very suspect in terms of long-range national supply and availability for use in power production. 2.Coal is proving to be far more expensive as a power source than previously anticipated. 3.Many hydroelectric alternatives have moved to the "unavailable" classes because of land area designations.The remaining are less desirable in terms of cost and ability to meet projected requirements. 4.Nuclear is expected to be as expensive as coal. 5.Geothermal,tide,and wind are unrealistic planning alternatives at this time. 74 PART VII.LOAD/RESOURCE AND SYSTEM POWER COST ANALYSES Introduction A series of load/resource and system cost demonstrate impacts of the Susitna project in system costs. analyses were made to terms of overall power ~.. The load/resource analysis determined probable timing of new maj or investments in generation and transmission facilities.It also shows annual energy from each type of plant.The load/resource analyses were prepared for these basic power supply strategies: Case 1.All additional generating capacity assumed to be coal- fired steam turbines without a transmission interconnection between the Anchorage-Cook Inlet area and the Fairbanks-Tanana Valley area load centers. Case 2.All additional generating capacity assumed to be coal- fired steam turbines,including a transmission interconnection. Case 3.Addli tional capacity to include the Upper Susitna proj ect (including transmission intertie)plus additional coal as needed,and for the three load limits (high,medium,and low). I The system cost analyses,keyed to the load/resource,determined cost by year to amortize investments and pay all annual costs·(fuel,O&M expenses,etc).Inflation rates of a and 5 percent ~ere considered. APA developed a number of the costs,etc.APA contracted prepare the report. key inputs,e.g.,demands,unit sizes and with Battelle to make the studies and This section summarizes key assumptions and results.More detailed information is available in the appended Battelle report. Basic Data and Assumptions Basic data and assumptions used in the load/resource and system power cost analyses are: 1.Interest rate for repayment of facilities =7 1/2 percent. 2.Inflation rates of 0 and 5 percent,with construction costs increasing at inflation rate,and fuel costs increasing at 2 percent above inflation rate. 3.System reserve capacity of 25 percent for non-interconnected load centers and 20 percent for interconnected systems. 4.Transmission losses of 1.5 percent for energy and 5 percent for capacity. 75 .," 5.Retirement schedules for proposed generating facilities (economic facility lifetime):l/ Years Coal-Fired Steam Oil-Fired Steam Gas-Fired Combustion Turbine Oil-Fired Combustion Turbine Hydroelectric Diesel 35 35 20 20 50 20 6.Plant factors for new and most of the.existing facilities are: Percent Hydro Steam Combustion turbine Diesel 50 75 50 10 The factor for combustion turbines was reduced to 10 percent in the· study when adequate steam turbine capacity was available. l/See tables 3.4 and 3.5 of appended Battelle report for estimated retirement dates of existing facilities. 7.Hydro plants designed for 115 percent of nameplate capacity for limited reserve requirements. 8.Watana power on-line (POL)in 1994 and Devil Canyon POL in 1998. 9.Existing and planned generating facilities for Anchorage and Fairbanks are shown in the appended Battelle report. 10.New coal-fired steamplants for Fairbanks assumed to be 100-}rn units (first six),then 200-MW units.Anchorage units assumed to be 200 MW (first five),then 400-Mlv units. 11.New coal-fired steamplants to be located at Beluga for Anchorage area and at Healy (or other sites within 100 miles)for Fairbanks. 12.Fuel costs--see appended Battelle report. 13.Power demands will be met by resource allocation using Susitna hydro generation first,coal-fired second,and natural gas and oil last. 14.Heat rate for new coal-fired steamplants =10,500 Btu/kwh. 76 15.Total investment cost in October 1978 dollars. Plant ($million)($/kw) 100-~1W Coal Steam Turbine 245.4 2,454 200-MW Coal Steam Turbine 372.0 1,860 400-~1W Coal Steam Turbine 646.8 1,617 Watana Dam (795 MW)and 2,020.7 2,554 Transmission Line 470.5 Devil Canyon Dam (77 8 MW)834.0 1,072 Total Susitna Project (1,573 MW)3,335.2 2,120 16.Operation,maintenance,and replacement costs. Plant 100-MW Coal Steam Turbine 200-.MW Coal Steam Turbine 400-MW Coal Steam Turbine Watana Dam (795 MW) Devil CanyonDam (778 MW) New Transmission Facilities Study Methodology ($million/yr.) 3.76 5.7 9.8 0.74 0.73 ($/RW/yr .) 37.6 28.5 24.5 0.941/ 0.941/ 2.0)) ~.. As stated in the introduction,three cases were analyzed to determine timing of generation and transmission (G&T1 investments and their impact on total power system costs. The first step in estimating the cost of power from alternative generation and transmission system configurations was to perform a series of load/res?urce analyses.These analyses determined the schedule of major investments based on assumptions of load grovrths, capaci ty and energy production of the potential generating facilities, and constraints as to when the facilities could come on-line.The load/resource analyses also determined the annual power production from each type of generating plant in the system. The system cost analyses then determined the annual cost for amortizing and operating the facilities.Summing the annual cost for generation and transmission of each of the generating facilities gave a total cost, by year,for the entire system being analyzed.Dividing the total annual cost by the power produced gave an average annual cost of power for the entire system. 1/This breakdown of OM&R costs by proj ect feature for convenience of the load/resource analysis resulted in slightly higher cost.Signifi- cance to Susitna rate is,at most,~ess than 1 percent. 77 p=o •I Rounded Thermal generating capacity additions to the year 2010 from the previous tables are summarized as follows: Table 21 SUMMARY OF THEfu~GENERATING CAPACITY ADDITIONS TO THE YEAR 2010 Upper Susitna Project Power Market Analysis Case 1:Without Interconnection &Without Susitna Assumed Load Megawatts Growth Anchorage Fairbanks Total Low 2,600 471 3,071 Mid 4,600 871 5,471 High 8,200 1,471 9,671 Case 2:Interconnection Without Susitna Assumed Load Megawatts Growth Anchorage Fairbanks Total Low 2,200 471 2,671 Mid 4,200 671 4,871 ~, High 8,200 1,271 9,471 Case 3:Interconnection With Susitna Assumed Load Megawatts Growth Anchorage Fair'banks Total Low 1,000 171 1,171 Mid 3,000 371 3,371 High 6,600 1,071 7,671 Note:Bradley Lake and Susitnahydroe1ectric projects are not included • .~. 78 Results Load/Resouree Analyses The schedule of new plant additions for Anchorage and Fairbanks for 1978-2011 are shown in the appended Battelle report.A summary of the thermal generating capacity additions is in table 21.Further discussion of the computer model results and graphs are also shown in the appended Battelle report. Under the criteria used,completion of construction for interconnection is scheduled in 1986,1989,and 1994 for high,mid and low load growth cases,respectively,without Upper Susitna.With Upper Susi tna,the corresponding dates are 1986,1989,and 1991. System Power Costs Annual system costs and unit power costs are presented in detail,both tabular and graphically,in the appended Battelle report.The following tabulations summarize these findings.Table 22 shows annual'power system costs for cases 1,2,and 3,high,mid and low range,with 0 percent inflation.The first few years after Watana comes on-line,the total annual power system costs increase slightly.However,comparing the total annual power system costs for the 1990-2011 period to case 1, construction of the Susitna project·results in a savings of $2.20 .~billion,or 12 percent. .Figure 18 shows the relative savings in Susitna,and case 1,without Susitna, assumptions. annual cost for case 3,with for the three load growth Tables 23, 24,and 24a summarize Anchorage and Fairbanks separately plus the combined system average annual power costs in ¢/kwh for 1978-2011- The tables verify the feasibility of the intertie in power cost savings for Anchora.ge and Fairbanks.By the year 2000,system wide power rates would be: 79 4 Average Power System Rates for Anchorage and Fairbanks -0%Inflation (¢/kwh) Case 1 Without Susitna or Intertie Case 2 With Intertie Case 3 With Susitna and Intertie Combined Combined Combined Anch.Fbks.System Anch.Fbks.System Anch.Fbks.System High 6.2 8.8 6.6 1/6.1 8.0 6.4 5.8 6.2 5.8 Mid 6.6 8.9 6.9 II 6.2 8.4 6.6 5.5 6.7 5.7 Low 7.1 9.2 7.5 Y 6.2 8.8 6.7 6.1 7.8 6.4 .• Comparison of Power Costs by Year 2000 Percent Change in Cost of Power Below Case 1 -0%Inflation Case 2 Case 3 Combined Combined Anch.Fbks.System Anch.Fbks.System High -1.6 -10.0 -3.1 -6.7 -41.9 -13.8 Mid -6.5 -6.0 -4.5 -20.0 -32.8 -21.1 Low -14.5 -4.5 -11.9 -16.4 -17.9 -17.2 For the Anchorage-Cook Inlet area,inclusion of the Susitna Project into the system (case 3)generally raises the cost of power above cases 1 and 2 during the first two to four years after Watana comes on-line,but lowers power costs during the 1996-2011 period.This reduction in the cost of power is significant in most cases. For the Fairbanks-Tanana Valley load center construction of the inter- connection (case 2)again generally reduces the cost of power compared to without an interconnection (case 1).The inclusion of the Susitna project (case 3)generally raises the cost of power above case 2 for about two years after Watana comes on-line,but,as with the Anchorage-Cook Inlet area,results in lower power costs during the 1996-2011 period. 1 I .Anchorage and Fairbanks are not interconnected for case 1,the combined system rate is shown for~ademic comparison purposes only. 80 Figure 18 . 'COMBINED .e~NCHORAGE-COO£-(ff\!LET AND FAfR8ANi<S-TANAr~A VALLEY ANNUAL POWER SYSTEr,,4 COSTS \fIlTH AND \VITHOUT SUSITNA Upper Susitna Project Power Market Analysis Case I High 2010 .-_-'Case I Low 982000 ,-~~--+-------lCase 3 Low cc:c-3 1990 94 YEAR !----I-------+--....."e+----!----;p--------fl Case 3 Medium t----+--------+-----~e::-I-----___:;fCase·I Medium ~; 1----+-------+-------II-----~'____i1 Case 3 High 2400· 2200 2000 z 18000 ,-J -J ~1600 ~,.1400en....en 0 12'00U a:::w 10003: 0a.. -J 800 <:t: ::> Z Z 600 <t. 400 200 '0 78 1980 Case I:without :Susitna Case 3:with Susitna 82 .A PA 1/79 ·Table 23 ANCHORAGE-COOK INLET AREA AVERAGE POWER COSTS -CENTS PER KILOWATT HOUR -0%INFLATION Upper Susitna Project Power Market Analysis Case 1 Case 2 Case 3 Year High Medium Low'High l'1edium Low High Medium Lm., 78-79,1.3 1.3 1.4 1.3 1.3 1.4 1.3 1.4 79-80 1 ..4 1.5·1.7 1.4 1.5 '1.7 1.4 1.7 :80-81 1.3 1.6 ,1.8 1.3 1.6 1.8 1.3 1.8 81-82 1.2 1.6 1.9 1.2 1.6 1.9 1.2 1.9 82-83 3.2 2.9·2.2 3.2 2.9 2.2 3.2 2.2 83-84 3 ..6 2.8 2.1 3.6 2.8 2.1 3.6 2.1 84-85 4.0 2.8 2.2 4.0 2.8 2.2 4.0 2.2 85-86 4.6 4.3'2.4 4.6 4.3 2.4 4.6 2.4 86-87 5 ..0 4.2 2.3 4.8 *4.2 2.3 4.8 *2.3 87-88 4.8 .4.7 3h 5.3 '4.7 3.7 5.3 3.7 88-89 5.4 4.4 3.5 5.1 4.4 3.5 5.1 4.4 3.5 89-90 5 ..1 4.8 4.2 5.7 4.5 *4.2 5.7 4.5 *4.2 90...,91,4.8 4.5 4.1 5.4 4.8 4.1 5.4 4.8 4.1 "91-92 5.2 5.0 4.1 5.7 5.3 4.1 5.7 5.3 4.6 *, 92-93 5 ..5 5.6 4.7 5.4 5.9 4.7 5.4 5.9'4.4 93-94 5 ..3 5.3 4.6 5.7 5.6 '4.6 5.7 5.61 5.0 94-95 5.5 5.1 5.3 5.5 5.4 4.9 *6.4#6.9\;#7.3 # 95-96 5 ..8 5.6 5.7 5.6 5.8 5.4 6.0 6.5 6.8 96-97 5.9 6.2 6.5 5.8 6.4 5.8 6.2 6.1 6.5 97-98 6.0 6.5 ,6.3 5.9 6.1 6.6 6.2+5.8 +'6.3+ 98-99 6.1 6.3 6.1 6.0 6.5 6.4 6.1 5.8 6.1 99-2000 6 ..2 6.6 7.1 6.1 6.2 6.2 5.8 5.5 6.1 00-01 6 ..3 6.4 6.9 6.2 6.6 7.2 5.5 5.3 5.9 01-02 6 ..1 6.3 6.9 6.3 6.4'7.2 5.6 5.2 5.6, 02-03 6 ..2 6.6 6.8 6.4 6.3 7.1 5.7 '5.7 5.7 03-04 6.3 6.5 6.8 6.2 6.7 7.1 5.6 5.6 5.6 04-05 6 ..1 6.4 6.7 6.1 6.6 7.0 5.8 5.5 5.6 05-06 6.3 6.9 7.6 6.2 6.5 7.0 5.9 5.4 5.5 06-07 6.4 '6.8 7.5 6.3 6.4 7.0 5.8 5.8 5.5 07-08 6.3 6.8 7.5 6.5 6.9 7.0 5.9 5.8 5.5 08-09 6.4 6.7 7.5 6.3 6.8 6.9 6.0 5.7 5.4 09-10 6 ..5 6.6 7.5 6.4 6.7 6.9 5.9 5.6 5.4 10-11 6.3 6.9 7.5 6.5 6.7 6.9 6.0 5.9 5.4 *Interconnection Installed #Watana on-line +Deveil Canyon on-line 83 APA 11/78 ""=::1 Table 24 AVEAAGE PCWER COSTS -0%INFLATIO::i (¢/KWH) FAIRBAJ.'JKS-TANJl.NA VAI..L1::."'Y AREA Upper Susitna Project Power Market Analysis Case 1 case 2 case 3 Year High Medium Low High Medium IDw'High r-~edium !.oN 78-79 4.1 4.3 4.4 4.1 4.3 4.4 L3 4.3 4.4 79-80 4.1 4.3 4.5 4.1 4.3 4.5 L4 4.3 4.5 80-81 4.1 4.3 4.7 4.1 4.3 4.7 L3 4.3 4.7 81-82 4.0 4.3 4.7 4.0 4.3 4.7 L2 4.3 4.7 82-83 3.8 4.2 4.7 3.8 4.2 4.7 3.2 4.2 4.7 83-84 3.4 3.8 4.3 3.4 3.8 4.3 3.6 3.8 4.3 84-85 5.2 3.4 3.9 5.2 3.4 3.9 4.0 3.4 3.9 85-86 4.7 5.4 3.6 4.7 5.4 3.6 4.6 5.4 3.6 86-87 5.9 5.1 3.3 5.5 *,5.1 3.3 '4.8 *5.1 '3.3 87-88 5.6 4.8 3.0 5.1 4.8 3.0 5.3 4.8 3.0 88-89 5.5 4.8 3.1 5.0 4.8 3.1 5.,1 4.8 3.1 88-90 6.5 6.3 5.6 4.7 5.8 *5.6 5.7 5.8 *5.6 90-91 6.5 6.4 5.8 4.6 5.9 5.8 5.4 5.9 5.8 ~. 91-92 6.2 6.2 5.9 4.4 5.7 5.9 5.7 5.7 7.2 92-93 6.8 7.3 5.6 6.3 5.4 5.6 5.4 5.4 6.9 93-94 6.6 7.1 5.5 7.3 5.2 5.5 5.7 5.2 6.8 94-95 7.4 6.9 ,7.1 7.0 6.5 6.7 *6.4 #6.8 =If 8.8 # 95-96 7.2 6.9 7.3 7.8 7.7 6.9 6.0 6.7 8.9 96-97 7.6 7.8 7.1 8.2 7.4 8.3 6.2 6.4 8.6 97-98 8.1 8.3 7.9 8.7 7.8 9.1 6.2 6.9 7.8 98-99 8.'9 9.1 9.4 8.3 8~7 8.9 6.1 +6.9 +7.6 + 99-2000 8.8 8.9 9.2 8.0 8.4 8.8 5.8 6.7 7.8 00-01 8.3 8.7 9.3 7.7 8.3 8.8 5.5 6.6 7.8 01-02 8.0 8.6 9.3 ,7.5 8~2 8.8 5.6 6.5 7.7 02-03 7.7 8.4 9.1 7.2 9.0 8.7 5.7 7.3 7.6 03-04 8.5 9.8 9.1 8.0 8.9 8.7 5.6 7.2 7.6 04-05 8.2 9.7 9.1 8.7 8.8 8.7 5.8 7.1 7.5 05-06 8.0 9.5 9.0 8.4 8.6 8.6 5.9 7.0 7.4 06.,.07 7.8 9.4 9.0 8.2 8.6 10.1 5.8 6.9 7.4 07-08 8.5 9.-3_9.1 8.1 8.5 10.1 -S.9 6.8 7.4 08-09 8.4 9.2 9.0 7.9 8.4 10.1 6.0 6.8 7.4 09-10 8.2 9.1 9.1 7.7 8.3 10.2 5.9 6.7 7.4 10-11 8.0 9.1 9.1 7.6 8.2 10.2 6.0 6.6 7.4 *Interconnection Instal1e::l #Watana on-line +Devil Canyon on-line ~\ 84 ...... Table 24a COMB~EDANCHORAGE-COOK INLET AND FAIRBANKS-TANANA VALLEY AREA AVERAGE ANNUAL POWER COST 1./(¢/KWH) Upper Susitna Project Power Market Analysis Case 2 Case 3 YEAR HIGH MEDIUM LOW HIGH MEDIUM LOW 1978-79 1979-80 1980-81 1981-82 1982-83 1983-84 1984-85 1985-86 1986-87 4.90 *4.90 *1987-88 5.31 5.31 1988-89 5.07 5.07 1989-90 5.56 4.79 *5.56 4.79 *1990-91 5.24 5.06 5.24 5.06 1991'-92 5.52 5.39 5.52 5.39 5.14 1992-93 5.58 5.83 5.58 5.83 4.89 1993-94 5.94 5.57 5.94 If 5.57 if 5.35 if ~.1994-95 5.71 5.63 5.28 *6.67 6.91 7.59 1995-96 5.92 6.19 5.69 6.25 6.52 7.25 1996-97 6.18 6.61 6.29 6.35 6.17 6.93 1997-98 6.34 6.44 7.08 6.30 6.01 6.56 1998-99 6.36 6.88 6.91 6.14 +5.96 +6.39 + 1999-2000 6.37 6.61 6.68 5.84 5.68 6.42 2000-2001 6.47 6.87 7.54 5.70 5.50 6.23 2001,-2002 6.53 6.75 7.51 5.89 5.40 6.16 2002-2003 6.55 6.75 7.39 5.93 5.99 6.02 2003-2004 6.51 7.06 7.37 5.90 5.90 5.98 2004-2005 6.47 6.96 7.33 6.05 5.80 5.93 2005-2006 6.52 6.85 7.30 6.11 '5.71 5.88 2006-2007 6.58 6.76 7.55 5.97 6.02 5.85 2007-2008 6.71 7.18 7.53 6.04 5.94 5.82 2008-2009 6.57 7.09 7.51 6.11 5.86 5.79 2009-2010 6.62 7.01 7.50 6.10 5.78 5.76 2010-2011 6.67 6.92 7.48 6.23 6.07 5.74 1:./Case I not interconnected,therefore combined system rate does not apply. *Interconnection Installed If Watana on-line +Devil Canyon on-line /"- 85 Part VIII.INVESTMENT COSTS Construction costs for power producing facilities were prepared by the Corps of Engineers (Corps);those for the transmission facilites by Alaska Power Administration (APA).APA prepared estimates of interest during construction based on 7 1/2 percent. Corps estimates Canyon--thin-arch, (USBR).and the conservative. include alternative design concepts as orginally proposed by Bureau of concrete gravity design,which is more for Devil Reclamation costly and Transmission estimates are based on same plan presented in 1976 report, with costs updated by indexing. Current costs for transmission facilities are based on indexing construction costs presented in the 1976 report (January 1975 prices)to current levels (October 1978 prices)by applying a factor of 1.38 to clearing and rights-af-way,1.33 to all other transmission line components (access roads,structures,etc.).and 1.28 to substations and switchyards,resulting in an overall factor of about 1:32.The clearing and rights-of-way factor is based on experience of the Alaska Department of Transportation and on recent experience of the USBR and Bonneville Power Administration (BPA).The 1975 prices are based on component prices from BPA with an increase of 90'percent for labor and 10 percent for material transportation from the Pacific Northwest to Alaska. Examination indicated that these factors are also valid for this analysis,but should be reevaluated if more detailed cost estimates are made in future years. Transmission system costs are summarized in table 25. Investment costs are calculated by adding interest during construction at the 'annual rate of 7 1/2 percent to construction costs presented previously. The project schedule includes (1)first-stage construction of Watana dam and powerplant and the total project transmission system.and (2) second-stage Devil Canyon dam and powerplant.The transmission system will be completed about three years before completion of Watana to develop interconnection benefits by deferring of required steamplant capacity (discussed in Part XIII,Load Resource Analysis). Table 26 summarizes the investment costs required. 86 Table 25 CONSTRUCTION COST SUMMARY Upper Susitna Project Power Market Analysis Item Transmission Lines Clearing Right-of-Way Access Roads Line Structures Subtotal -T.L. Switchyards and Substations Fairbanks Substation Talkeetna Substation Anchorage Substation Healy Switchyard Watana Switchyard Devil Canyon SWitchyard Subtotal -S.S. Total Rounded 87 Construction Cost ($1,000 -10/78) System No.5 $3,350 5,000 19,110 242,190 $269,650 $11,710 10,100 15,890 4,770 6,360 19,660 . $68,490 $338,140 $338,000 APA 10/78 , i Table 26 INVES'IMENT COST SUMMARY ($!MILLION)· Upp~r Susitna Project Power Market Analysis Stage Power Production Facilities COnstruction Interest during Construction Investment Power Transmission Facilities COnstruction Interest during Construction Investment Watana (1st) 1,427.0 603.7 2,030.7 338.0 132.5 470.5 Devil canyon (2nd) 665.0 168.6 833.6 Total 2,092.0 .772.3 2,864.3 338.0 132.5 470.5 ,.7' Total Investment -Susitna 88 2,501.2 833.6 3,334.8 PART IX.OPERATION,MAINTENANCE,AND REPLACEMENT PLAN AND COSTS Operation and Maintenance This updates information furnished in the 1976 report.Operation, maintenance,and r-eplacement costs were indexed for this report. Plan Description This plan assumes Federal operation of the facilities. The plan assumes the headquarters and main operations center for the Susitna project will be near Talkeetna or at some other equally accessible point.Equipment at the center will remotely control the operation of t~e generation and transmission system and operation of Devil Canyon and Watana dams and reservoirs.Electrician/operators and mechanic/operators will be located at the powerplants to provide routine maintenance and manual operation when required. Specialized personnel,such as electronic technicians and meter and relay repairmen,will service both powerplants and the substations and switchyards from the project headquarters.Project administration, including supervision of power production,water scheduling,and transmission facilities,will also be from the project headquarters. Major turbine and generator inspection and maintenance will be done by electricians,mechanics,engineers,and other experienced personnel from APA.Manufacturers'representatives and other specialized expertise will be consulted. Alaska Power Administration's (APA)headquarters office in Juneau will handle power marketing,accounting,personnel management,and general administrative services. Transmission line maintenance will be performed by two line crews,with assistance from the existing Eklutna Project line crew.Transmission line maintenance warehouses and parts storage yards will be at Devil Canyon or Watana,approximately mid-way between Devil Canyon and Fairbanks,and at the project headquarters.Line crew personnel will be stationed along the lines at designated maintenance stations and at the major substations to provide routine line patrol and maintenance tasks. Crews from throughout the project will be assembled for major work. Visitor facilities with provisions for self-guided powerplant tours will need assistance from operation personnel. Project-related recreation facilities will require cooperation between Federal,State,and local interests,and are assumed to be maintained by a State or local entity. 89 Project operation,maintenance,and administration could be combined with the existing Eklutna Project.Eklutna could be supervisory controlled from the Susitna project operations center with electrician/operators and mechanic/operators stationed at Eklutna.It is estimated that approximately $lOO,OOO/year could be saved by joint operation •. Marketing and Administration Marketing and administration include three main functions: 1.Administration Personnel management Property management Budgeting Marketing policy Rate and repayment studies 2.Accounting Customer billing Collecting Accounts payable Financial records Payroll 3.Marke~ing Rate schedules Power sales contracts Operating agreements System reliability and coordination Part of this work would be carried out by the project,with overall administration and support services provided by the APA headquarters staff.' Annual Costs The estimated annual costs for operation,maintenance,marketing,and administration are based on itemized estimates of personnel,equipment, supplies,and services needed to do the work,with a provision for contingencies. The -estimate assumes Federal classified personnel providing management and administrative functions and wage grade personnel performing technical operation and maintenance activities.Classified salaries are based on a mid~grade rate.Hage grade rates are based on those in effect in the Anchorage area and include basic hourly rates,benefits, and overtime. 90 * 1-"", " Costs of supp).ies,equipment,and personnel requirements are based on Bureau of Reclamation (USBR)guidelines and the experience of the Eklutna and Snettisham Projects.The Eklutna Project is fully staffed, including a line crew,which has been in operation since 1955.The Snettisham Project is isolated;it is separated from the Juneau load. center by 45 miles of rugged terrain and water.A maintenance crew resides and performs routine maintenance at the powerp lant;proj ect operations are remotely controlled from Juneau.The Susitna project would have some characteristics of both projects. Itemized costs for operation,maintenance,marketing,and administration are presented in table 27. Costs by major category and number of personnel are summarized in table 28. Rep lacements The annual replacement cost prOV1S1on establishes a sinking fund to finance replacement of major items which have an expected service life of less than the 50-year project repayment period.The objective is to cover costs and ensure financing for a timely replacement of major cost items to keep the project operating efficiently throughout its life. The replacement cost is based on factors developed from USBR experience. The factors apply to the total powerp lant,substation,swi tchyard, transmission tower,fixtures,and conductors.Replaceables include generator windings,communication equipment,a small percent of the transmission towers,and items in the substation and switchyards.Items covered by routine annual maintenance costs include vehicles,small buildings,camp utilities,and materials and supplies.Major features, such as dams and powerplant structures,are considered to have service lives longer than the 50-year repayment period.Their costs are not covered by the replacement funds.Right-of-way and clearing costs are not included.The 7~percent interest rate used for project repayment was used to establish the replacement sinking fund. Table 29 presents calculations of the annual replacement fund.• The following tabulation summarizes the operation,maintenance,and. replacement costs: .Watana Devil Canyon Total Annual Operation and Maintenance $1,000 $2,360 530 $2,890 Annual Rep lacement $1,000 $260 170 $430 Total OM&R $1,000 $2,620 700 $3,320 Price base -October 1978. 91 ------------.....,..-----------~--------------------- Table 27 ANNUAL OPERATION &}L~INTEN~~CE COST ESTIMATE Upper Susitna Project Power Market Analysis October 1978 Prices Dam and Powerplant.Total Transmission System /~, ,'--. Tab Ie 27 (cant.) ANNUAL OPERATION &MAINTENANCE COST ESTIMATE Miscellaneous Telephone Official travel Vacation travel Supplies,Services &Maintenance--Powerplant Supplies &Services--Vehicles &Equipment Employee training Line spray Government camp maintenance Subtotal -Miscellaneous Equipment Operation,Maintenance,and Replacement Annual Cost $10,000 19,000 19,000 125,000 50,000 6,000 25,000 19,000 $273,000 Initial Service No.Cost Life Tractor with Dozer 1 $150,000 10 $15,000 Loader 1 75,000 10 7,500 Maintainer 1 75,000 10 7,500 Pickup 10 80,000 7 11 ,400 Sedan 1 5,000 7 700 Tractor &Lowboy 1 75,000 10 7,500 Dumptruck 1 25,000 10 2,500 Flatbed 2 20,000 7 2,900 Fir,etruck 1 25,000 10 2,500 Sno trac 2 16,000 7 2,300 Backhoe 1 35,000 10 3,500 Crane,50 ton 1 200,000 20 10,000 Hydraulic Crane,20 ton 1 100,000 20 5,000 Line truck 4 200,000 10 20,000 Subtotal -Equipment $98,300 APA Headquarters Marketing and Administration 165,000 Subtotal 1,966,000 Contingencies (20%+)394,000 TOTAL WATANA &TRAN~~ISSION $2,360,000 93 'Table 27 (cont.) ANNUAL OPERATION &MAINTENANCE COST ESTIMATE Devil Canyon Dam and Powerplant Personnel Watana and Devil Canyon,supervisory controlled from a remote' operation-dispatch center. Increase base staff for Assistant operators Electricians Mechanics Maintenance Subtotal Devil Canyon. 2@15.00/hr. 2@lT.00/hr • 1@17.00/hr. 1@15.00/hr. Overtime Government Contributions Foreman Pay Subtotal Subtotal -Personnel Miscellaneous Vacation travel Employee training Supplies,Services &Materials Supplies and Services Subtotal -Miscellaneous Equipment Pick up Snow tractor Initial Cost 2 @ 16,000 1 @ 10,000 Service/ Life 7 7 $2,300 1,100 Subtotal -Equipment APA Headquarters Marketing and Administration Subtotal Devil Canyon Additions $ $ 3,400 35,000 444,000 Contingencies (20%+) TOTAL DEVIL CANYON O&M ADDITION TOTAL WATANA·AND TRANSMISSION TOTAL SUSITNA PROJECT 94 M 86,000 $530,000 2,360,000 $2,890,000 .~. ) Table 28 OPERATION AND MAINTENANCE COST SUMMARY Upper Susitna Project Power Market Analysis Watana &Trans- mission System Number Dollars Personnel: Devil Canyon Number Dollars Total Devil Canyon, Watana &Transmission Number Dollars ~ VI Salaries/Wages,Allowances Classified Personnel 7 Wage Board Personnel 31 Miscellaneous: Telephone,Travel,Supplies, Services,Training,Line Spray,Camp Maintenance Equipment: Annual cost Replacement Marketing and Administration APA Headquarters Subtotal Contingencies (20%+) TOTAL - $1,429,700 273,000 98,300 165,000 $1,966,000 394,000 $2,360,000 $274,700 o 7 130,900 3,400 35,000 $444,000 86,000 $530,000 $1,704,400 7 38 403,900 101,700 200,000 $2,410,000 480,000 $2,890,000 Table 29 REP~CEMENT COSTS Upper Susitna Project Power Market Analysis Watana and Transmission System Devil Canyon .Total Annual Annual Annual Annual Rep lace-Rep lace-Rep lace-Replace- ment Construction ment Construction ment Construction ment Feature Factor Cost Cost Cost Cost Cost Cost----". Powerp1ant 0.0010 $197,370,000 $197,370 $120,860,000 $120,860 $318,230,000 $318,230 Transmission towers, fixtures,Ii.conductors 0.0001 251,32 Lf,000 25,130 ----251,324,000 25,130 \0 0\Substations and switchyards 0.0033 11,000,000 36,300 14,760,000 _48,710 25,760,000 85,1HO Total $258,000 $169,570 $428,370 Rounded .$260,000 $170,000 $430,000 Replacement factors are based on 7 1/2 percent interest rate. Construction cost based on the portion of the feature subject to replacement. )-) PART X.FINANCIAL ANALYSIS This part estimates the market for project power and evaluates power rates needed to repay the investment in power facilities.Power market size is in more detail in tHis study than in the 1976 report.Likewise, costs are slightly more detailed. The Upper Susitna Project is primarily for hydroelectric power generation and transmission.,Minor portions of'project costs (less than 1 percent)would be allocated to other purposes,such as recreation and flood control.Project financial viability is the essential element in demonstrating feasibility of the power development.The repayment rate is influenced principally by size of the market,amount of investment, and applicable interest rates.Operation,maintenance,and replacement costs are a minor part of total annual costs;they influence these rates insignificantly.If rates needed to repay the hydro project are attractive in comparison to other available alternatives,the project is economically justifiable. 'The 1976 report compared the costs of five dam and reservoir plans for developing the Susitna River hydroelectric potential and found all costs were within a 15 percent range.Therefore,the scoping analysis was not repeated for this study. In addition to analyzing the basic Susitna project plan,variations were also analyzed for sensitivity.These included interconnection with additional service areas,different timing for interconnection between Anchorage and Fairbanks,use of the more expensive Devil Canyon gravity dam instead of the arch dam,low load growth,and the-effect of inflation.In addition,the load/resource and system cost analyses examine impact of the Susitna Project on overall system costs. Market for Project Power Upper Susitna will operate as part of a hydro/thermal power system. The 1976 report assumed the market for Susitna firm energy as 75 percent of the mid-range utility requirements.Average rates for firm energy were estimated on that'basis. For this analysis,the market for firm energy was assumed to be approximated by load growth after Susitna power becomes available,plus market made available through retirement of older plants. The balance of the Susitna energy is assumed marketable as secondary energy for fuel replacement,as long as all energy fits under the load curve.A value is assigned for marketable secondary energy based on estimated future coal costs.The actual value is probably significantly higher. 97 The value of fuel replacement energy is the same as that used in the load resource analysis,which is $1.00 to·$1.50/million Btu by 1985. This is based on the concept that large,efficient coal mines will be developed in the Beluga area by then.T.he price is escalated at 2 percent per year above the zero inflation rate from 1985 to 1994, resulting in a cost of $1.20 and $1.80/million Btu's. Table 30 summarizes the estimated market for Susitna energy using these criteria. Cost of Project Table 31 summarizes the construction cost,interest during construction, operation,maintenance,and replacement costs for Devil Canyon and Watana phases.Construction costs were furnished by the Corps for an October 1978 price level.Interest during construction was calculated from Corps construction cash flow estimates with interest accumulated until the project becomes operational.OM&R costs were updated from APA earlier estimates. Costs have increased from the 1976 report for several reasons.Table 32 presents a summary comparison of the cost factors.Interest rates have increased from 6 5/8 to 7 1/2 percent.Design and cost changes were made by the Corps as a result of foundation drilling.Costs'were updated for the Devil Canyon dam and the transmission line by indexing procedures.The major change in operation,maintenanae,and replacement costs was due to inflation in personnel wages and provisions for con- tingencies such as unlisted items and state of the art.Watana's construction period was extended from 6 years to 10 years,increasing its construction period from 10 years to 14 years.The revised project investment cost is 89 percent higher than in the 1976 report. 98 >-------------------------------------------- TABLE 30 MARKET FOR UPPER SUSITNA POWER ANCHORAGE AND FAIRBANKS AREAS Upper Susitna River Project Power Market Analysis MEDIUM ESTIMATE Year 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 Firm Energy Sales GWH 633 1,385 2,231 2,873 3,531 4,244 4,686 5,055 5,630 5,983 6,352 6,767 6,787 Fuel Replacement Sales GWH 2,401 2,043 1,197 555 2,872 2,543 2,101 1,732 1,115 804 235 20 o COMPARISON WITH TOTAL AREA POWER REQUIREMENTS Year 1995 2000 2005 Estimated Anchorage and Fairbanks Energy Annual Energy Million KWH 10,323 13,288 15,083 Estimated Market for New Hydroelectric Power Annual Energy Million KWH 1,385 (13)1/ 4,686 - (35)1/ 6,767 - (45)];..1 !/Percent of total area requirements Data Source:APA Load/Resources Analysis Medium Load Gro~h Estimates, Energy Losses are included. 99 ._-..,- Table 31 INVES TMENT AND OM&R COST SUMMARY Upper Susitna Project Power Market Analysis Unit Completion Date Watana 1994 Costs -$1,000 Devil Canyon 1998 Total System Power Production Facilities Construction Costs Interest During Construction Investment Cost Transmission Facilities ~/ Construction Costs Interest During Construction Investment Cost Total System Investment Cost 1,427,000 603,700 2,030,700 338,000 132,500 470,500 665,000 1/ 168,600 833,600 2,864,300 470,500 3,334,800 Annual Operation and Maintenance Annual Replacement Annual OM&R 2,890 430 3,320 Price level is October 1978.Interest rate for repayment purposes in FY 1979 is 7-1/2%. 11 Costs are for arch dam plan at Devil Canyon. 2/Transmission system assumed online in 1991. 100 Average Rate DetJrmination Table 33 summarizes the estimated average firm energy rate for firm energy needed to repay project facilities investment for mid-range load growth conditions.The method used is similar to that used in the 1976 report.Present Federal criteria for power producing facilities require repayment of project costs,with interest,within 50 years after the unit becomes revenue producing.The applicable interest rate for Fiscal Year 1979 is 7 1/2 percent •.Revenues were credited to the project from sale of secondary energy at a fuel replacement rate of l.2c/k,m during early years of project operation.The average required rate for repayment over 50 years after the last unit is installed is 4.7¢/kw. Total repayment period will be 54 years with Devil Canyon coming on-line four years after Watana. Alternatives to the basic project plan were analyzed to determine effects on average power rates: 1.Devil Canyon gravity dam in lieu of the thin-arch dam: Investment cost increased $204.9 million. Average rate for firm energy increased to a total of 4.9C/kw. 2.Transmission investment deferred until Watana phase comes on-line /_(1994): Watana phase investment reduced $76 million. Average rate reduced O.lC/kw to a total of 4.6C/kw. 3.Mid load growth case,5 percent inflation: Investment cost increased $3.598 billion. Revenue needs increased $243 million annually. Firm energy is the same for all mid growth cases. Average rate for firm energy increased 4.7¢/kwh to 9.7C/kwh. 4.Low load growth case: Revenue needs same as for mid range growth case. Firm energy sales decreased;fuel replacement sales increased. Average firm energy rate increased L 7¢/kw. All Corps plans are based on completing Watana first,followed by Devil Canyon four years later.This is appropriate for mid range and high range growth conditions,but if low range conditions remain,it may mean the Devil Canyon unit could be deferred a few years. 101 Power Marketing Considerations The average rate is useful for comparing the proposal with the alternatives.Actual marketing contracts will likely include separate provisions for demand and energy charges,wheeling'charges,reserve agreements,and other factors. There are some built-in inequities for any method of pricing.What amounts to a postage stamp rate is used by most utilities and large Federal systems.That is,power rates are the same for all delivery points on the system.Actual costs vary with the distance,size,and characteristics of load--it is more costly to serve a small load several miles from the power source than to serve a large load nearby.Policies vary from system to system as to "hookup"costs born by the customers. 102 Table 32 COST SUMMARY COMPARISON WITH 1976 INTERIM FEASIBILITY REPORT Upper Susitna Project Power Market Analysis Difference Item (Costs $Million) Interest Rate for Repayment Construction Period Watana Devil Canyon Transmission System Total Construction Cost Watana Devil Canyon Transmission System Total Interest During Construction W'atana Devil Canyon Transmission System Total 1976 Interim Feasibility Report 6-5/8% 6 yrs. 5 3 10 yrs. 832.0 432.0 256.0 1,520.0 165.4 57.2 25.4 248.0 1978 Marketability Analysis Update 7-1/2% 10 yrs. 8 3 14 yrs. 1,427.0 665.0 338.0 2,430.0 603.7 168.6 132.5 904.8 Amount +7/8% +4 yrs. +3 o +4 yrs +595.0 +233.0 +82.0 +910.0 +438.3 +111.4 +107.1 656.8 Percent +13 +67 +60 o +40 +7.2 +54 +32 +60 +265 +195 +422 +265 Investment Cost W'atana Devil Canyon Transmission System Total Annual Cost for Repayment of Investment Annual Equivalent OM&R Total Annual Equiv.Cost (Less Secondary Energy Sales II -(Fuel Replacement Sales)- Total Net Annual Equiv.Cost Annual Equiv.Energy GWHlI Total Annual Equiv.Energy Cost -¢/KWH .,--,.11 Median load growth 997.4 489.2 281.4 1,768.0 113.34 2.27 115.61 5.77 109.84 5,218 2.11 2,030.7 833.6 470.5 3,334.8 239.20 3.14 242.34 11.34 231.00 4,923 4.69 +1,033.3 +344.4 +189.1 +1,566.8 +125.86 +0.87 +126.73 +5.57 121.16 -295 2.58 +104 +70 +67 +89 +111 +38 +110 +97 +110 -6 +123 Note:Total energy during period of analysis is the same in both reports. Difference is due to variation in load build-up. 103 ------------;----------------rl-----~----------------- Project Costs $1,000 Table 33 AVERAGE RATE DETERMINATION (WATANA AND DEVIL CANYON) Upper Susitna Project Power Market Analysis 199L.PW Costs $1,000 Project Energy Sales Million KWH Investment OM&R 2,501,200 2,437 2,267 2,109 1,962 (1998-2047) 624,200 32,256 Revenue Producing. Year Investment'OM&R 1994 2,501,200 2,620 1995 2,620 1996 2,620 1997 2,620 1998 833,600 3,320 I-'1999 3,320 0 2000 3,320.t:- 2001 3,320 2002 3,320 2003 3,320 2004 3,320 2005 3,320 2006-2047 Totals 3,334,800 Annual Equivalents ... 3,125,400 .239,200 41,031 3,1L.l Firm Fuel Replacement 1994 PW Fuel Replace- Energy Energy Sales Finn Energy IDent Sales (1994-2005) 633 2,401 •589 2,233 1,385 2,043 1,198 1,768 2,231 1,197 1,796 964 2,873 555 2,151 416 3,531 2,872 2,459 2,000 4,244 2.543 2.750 1,648 4,686 2,101 2,824 1,266 5,055 1,732 2,834 971 5,63,0 1,115 2,937 582 5,983 804 2,903 390 6,352 235 2,867 106 6,767 20 2,841 8 6,787 000 36,171 64,320 12,352 4,923 845 (3)Equivalent Annual Firm Energy Sales (4)Average Rate For Repayment ($231,000,000/ 4,923,000,000 l~) Average Rate Computation: (1)Annual Costs: (2)Revenue From Fuel Replacement Energy at 12 mills per kilowatt hour ).) Capital OM&R Total $239,200,000 3,140,000 $242,3L~0,000 -11,340!000 $231,000,000 4,923,000,000 KWH 46.9 mills/KWH ) Actual rates for the Su~itna system could reflect several items of costs and revenues not identified in the project studies.For example,during its life,proj ect facilities would likely be used to wheel power from other sources.Wheeling revenues will lower overall project power rates somewhat.Conversely I wheeling costs for proj ect power delivered over non-Federal transmission lines will be added to project rate schedules. This is now done under APA marketing contracts for the Snettisham Project;there are similar situations in other Federal power systems. Market Aspects of Other Transmission Alternatives It is reasonable to expect modifications of the project transmission system as requirements (or needs)change.The main 345-kv and 230-kv lines could be upgraded substantially by adding compensation and transformer capacity.Substations eQuId be added as future loads increase to a case-by-case determination of economics.Similarly, extensions of the project transmission lines to serve other areas would be considered on the basis of needs,economics,and available alternatives. Anchorage-Cook Inlet Area The costs in the proposed plan are premised on delivery points to substations near Talkeetna and Anchorage.Rough estimates indicate similar costs for a plan with delivery points at Talkeetna,Anchorage, and the existing APA Palmer substation.~asically the proposed plan includes costs to provide for delivery points on the existing CEA and APA systems north of Knik Arm,but does not include costs of delivering power across or around the Arm. With or without the Susitna project,additional transmission capability is needed on the approaches to Anchorage.CEA plans for a Knik Arm system considers 230-kv transmission an important step in developing this capability,but more capacity will be needed by the mid-1980's. Essentially the same problems will exist with alternative power sources, such as the Beluga coals.. Following project authorization,detailed studies will be needed to consider alternatives for providing power a~ross Knik Arm.Costs would be worked into rate structures through wheeling charges on non-Federal lines or annual costs on project lines,if needed. The transmission plan to deliver project power in Anchorage will need to be worked out in the detailed post authorization studies.It will involve added costs,either wheeling charges for project power over non-Federal lines,or constructing project transmission lines around or under Knik Arm.These costs could be about the same for alternative power sources such as the Beluga coals. It is essential that scheduling of project facilities be closely tied to the marketing function. 105 Comparison of Susitna to Steamplants With and Without Inflation Without inflation,the 4.7¢/kwh rate for the Susitna project is significantly ,lower than the estimated cost of power from coal-fired steamplants at 5.2 to 6.4¢/kwh at October 1978 costs.Considering inflation,the capital costs of botH the steamplant and hydro powerplant increase until construction is complete.For the completed projects, inflation affects only the hydro project operation and maintenance cost, a small part of the energy cost.For the steamplant,inflation continues to increase the fuel cost as well as the much larger operation and maintenance cost. The difference of the effect of inflation is shown on figure 19. Capital and O&M costs are assumed to inflate at 5 percent per year for both.Fuel costs are assumed to inflate 2 percent per year higher than a base price of $1.00 or $1.50 per million Btu in 1985.The conclusions are that Susitna is considerably less susceptible to inflation than steamplants. 106 COMPARISON OF SUSITNA .'Figure 19 AND ALTERNATIVE COAL-FIRED STEAMPLANT RATES CONSIDERING 5%ANNUAL INFLATION 17 16 15 14 13 12 II :r: ~ ~IO .......en..- 29w ,~,'u w 8..- .q: a: 7 6 5 4 3 2 o tpper Susitna Pro ect Power M rket Anal f!s s / /y / 'j / / I // STEAMPLANT /VALTERNATIVE\ ~V/ V'V // V V.... /'L Sl.JSITNA . " 1978 i980 1985 1990 1994 1995 2000 YEAR OF PRICE BASE *(Fue I cost infla1ed 2%higher) 107 APA 1/79 ~--------~--_._---------- PART XI.GLE~~ALLEN AND VALDEZ Introduction The primary justification for the Upper Susitna proj ect is to supply power and energy to the State's two largest power market areas, Anchorage-Cook Inlet and Fairbanks~Tanana Valley. The Glennallen-Valdez area is recognized as a possible additional market area.The two communities are the principal load centers for the Copper Valley Electric Association (CVEA).At present,both are supplied from oil-fired generators. CVEA is now moving into initial construction phases of its Solomon Gulch hydroelectric plant near Valdez,and is in final design stages for a l38~kv transmission line extending 104 miles to interconnect Valdez and Glennallen.CVEA could be interconnected ,nth the major ui tlities in the Anchorage-Cook Inlet area by adding a transmission line between Palmer and Glennallen.The transmission distance is 136 miles;minimum transmission voltage would likely be 139 KY.Depending on future demand,a higher voltage such as 230 kv may be justified. VeD7 preliminary studies summarized in the following section indicate a good chance that the Palmer-Glennallen intertie is feasible. Power Market Area Introduction Similar to Fairbanks,both Glennallen and Valdez have been heavily impacted by trans-Alaska oil pipeline construction and operation.The pipeline term~.]'11 storage and shipping facilities are at Valdez.The pipeline was completed and went into operation in 1977.The Glennallen-Valdez area 1977 population was approximately 9,905,39 percent higher than in 1974.However,the 1976 population (13,000) decreased 31 percent in 1977. Valdez is the proposed site of a maj or refinery and petruchemical complex to process the State's royalty share of Prudhoe Bay oil.Plans are not yet finalized,but construction could begin as early as 1980. This would have major impacts in terms of both construction employment and a long term increase in employment and population for Valdez.The operations phase of the refinery involves 1,000 new jobs according to recent reports.Glennallen I s population and economy are expected to continue to grow. Existing Power System The Copper Valley Electric Association (CVEA)serves both Glennallen and Valdez.CVEA's radial distribution lines extend from Glennallen,30 miles north on the Copper River.55 miles south on the Copper River to ,~ Lower Tonsina,and 70 miles west on the Glenn Highway.Figure 2 outlines the area. '''0 CVEA plans to .construct 104 miles of 138-kv lOng transmission line between Valdez and Glennallen.This is related to the Solomon Gulch 12-MW hydro development now beginning construction.At present,the utili ty loads are served totally by diesel generation of 17.7 MW:10.1· MW at Valdez and 7.6 MW at Glennallen.Two small utilities serving limited areas on the highways north of Glennallen are included in historical data.Their installed diesel capacity totals 1/3 MW. The Alyeska oil terminal faGili ty at Valdez has 37.5 MW in oil-fired steam-turbine capacity.This is a total energy facility that satisfies the terminal's electrical and steam requirements. Power Requirements This section summarizes historic energy use and related data, information from a 1976 load forecast prepared for CVEA,and some general observations on likely magnitude of future power requirements. Historic Data Energy use and peak demand data were obtained from three power generating sources in the Valdez-Glennallen area:CVEA,the utility serving over 95 percent of the area;Chistochina Trading Post;and Paxson Lodge,Incorporated.The utility data yielded information on energy use,peak demand,and customer sector breakdowns. Population and employment data were derived from statistics provided by the State of Alaska Department of Labor.This information illustrates demographic characteristics of the study area. The 1970-77 Valdez-Glennallen area is summarized on table 34.Net generation by utility from 1960-77 is on table 35. Analysis The energy use,population,and employment data reflect events tied to construction and operation of the Alyeska oil pipeline.The 'large jumps "in population and employment during the construction years cannOt be directly tied to utility power requirements since most of the workers were housed in construction camps that supplied their own power. The 1977 use data show total utility requirements at more than four times the 1970 level.Total number of customers tripled during the period. Per customer residential use increased from 3,846 to 6,423 kwh per year over the 7-year period. This historic data prOVides no clear insight to probable future levels of power use--any trends that would be useful in forecasting are hidden by the construction impacts. 109 "'P~~I""I"_ Forecast Table 36 summarizes future power demand estimates from CVEA's 1976 power requirements study ..The study included estimates of demands through 1991;APA made a rough extension to the year 2000,assuming a 6 percent rate of increase. The average energy capability of the Solomon Gulch project is estimated at 55 million kwh/year.'The·forecasts indicate that the Solomon Gulch power would be fully utilized as soon as it comes on-line.By the time Upper Susitna power would be available,CVEA total demands would exceed 'Solomon Gulch capability by around 100 million kwh/year. The CVEA study predated the plans for the oil refinery at Valdez,pence there is substantial likelihood that the actual requirements will exceed the'forecast amounts. Transmission Plan And Cost Incremental service to the Glennallen-Valdez market areas would require constructing transmission facilities from Palmer to Glennallen to connect to the CVEA system serving the market area.Susitna project generation and transmission to the Anchorage-Cook Inlet a"rea would be sufficient to accomodate the incremental service. The Palmer-Glennallen transmission system would have 136 miles of single circuit 138-kv line,with a substation at Palmer and a switchyard'at Glennallen.The Palmer substation would have a 230/138-kv transformer. a 230-kv breaker.and a 138-kv circuit-breaker.The Glennallen switch- yard would include two 138-kv circuit breakers.and would connect with the planned CVEA 138-kv line extending to Valdez.Peak'capacity of the 138-kv Palmer-Glennallen line would likely be from 50 to 80 ~v.This is an assumption for study purposes (stability.sizing J and power flow studies were not made). System costs are based on comparable elements of other project transmission systems,indexed from the 1976 report (January 1975 prices) to October 1978 prices (about 32 percent increase).The basic prices are based on Bureau of Reclamation (USBR)and Bonneville Power Administration (BPA)with adjustments for Alaska conditions (refer to Part VIII).Advance planning would analyze evaluations of structural, operation control.environment,and other elements affecting route location,design,and operation of the system serving this area. Investment costs are calculated by adding 7~percent interest annually during construction.The Palmer-Glennallen line would be ccnstructed during the same period as other facilities,and would be ready for service when project power is available in 1994.Table 37 summarizes construction and investment costs. Table 34 HISTORIC DATA GLENNALLEN-VALDEZ AREA Upper Susitna Project Power Market Analysis Net Generation Peak Load (MW) Utility Energy Sales (G~'iH) Res CI Total 1970 2.1 7.4 9.9 1971 2.6 7.8 10.8 1972 2.8 7.6 10.8 1973 2.9 8.3 11.6 1974 3.7 10.4 14.5 .1975 7.7 16.0 24.4 1976 10.3 22.4 33.5 1977 10.9 31.0 42.9 utility CustoU'ers Res CI Total 1970 546 221 793 ,"'-"".1971 681 226 939 1972 655 237 926 1973 684 247 965 1974 911 317 1,268 1975 1,172 361 1,576 1976 1,677 404 2,128 1977 1,697 427 2,183 Utility 11.9 12.8 13.0 13.8 16.8 28.2 40.7 48.7 utility 2.4 2.5 2.6 2.7 4.0 7.3 8.6 9.3 Industry 39.4 Industry 37 (38.6 installed capacity) 1970 1971 1972 1973 1974 1975 1976 1977 Population (Total) 3,098 2,932 3,464 3,568 3,833 9,639 13,000 9,905 Res residential CI commercial-industrial III Employment (Avg.Annual) 831 1,085 904 985 1,526 4,626 7,818 3,918 APA 12/78 ·~ Table 35 UTILITY NET GENERATION (GWH) GLENNALLEN-VALDEZ AREA Upper Susitn~Project Power Market Analysis. Year CVEA CTP PLI Total Growth % 1960 3.2 0.1 3.3 1961 3.4 0.1 3.5 6.1 1962 4.0 0.1 4.1 17.1 1963 4.5 0.1 4.6 12.2 1964 4.2 0.1 4.3 -6.5 1965 6.5 0.2 ..6.7 55.8 1966 8.0 0.2 8.2 22.4 .1967 8.2 0.3 8.5 3.7 1968 8.6 0.4 9.0 5.9 1969 9.7 0.4 0.5 10.6 17.8 1970 10.7 0.4 0.7 11.8 11.3 d!#< 1971 11.7 0.4 0.7 12.8 8.5 1972 1l.8 0.4 0.7 12.9 0.8 1973 12.6 0.4 0.7 13.7 6.2 1974 16.6 0.4 0.7 17.7 29.2 1975 26.9 0.4 0.7 .28.0 58.2 1976 39.3 0.4 .0.7 40.4 44.3 1977 47.4 0.4 0.7 48.5 20.1 CVEA -Copper Valley Electric Association CTP -Chistochina Trading Post PLI -Paxson Lodge,Inc. APA 12/78 112 Table 36 VALDEZ-GLENNALLEN AREA UTILITY FORECASTS Upper Susitna Project Power Market Analysis Energy (gwh)Peak Demand (HW) CVEA 1/CVEA Y Year Glennallen Valdez Total Glennallen Valdez 1976 12.5 24.5 37.0 40.7 Y 3.1 6.0 1977 21.0 27.0 48.0 48.7 Y 4.2 5.9 1978 22.1 27.2 49.3 4.4 5.8 1979 24.0 27.6 51.6 4.6 5.8 1980 45.9 27.9 73.8 7.3 5.8 1981 48.5 30.5 79.0 7.7 6.3 1982 50.0 33.0 83.0 8.1 6.8 1983 52.2 35.5 87.7 8.5 7.4 1984 55.0 38.2 93.2 9.0 8.0 1985 57.6 41.4 99.0 9.5 8.6 1986 60.0 45.0 105.0 10.1 9.3 1987 63.1 48.5 111.6 10.6 10.1 1988 66.0 52.5 1'18.5 1l.1 10.9 1989 69.1 56.8 125.9 11.7 11.8 '1990 72.3 61.4 133.7 12.4 12.8 1991 75.0 66.4 141.4 13.0 13.8 1995 180 2000 240 2025 1,025 y Copper ,Valley Electric Association Forecast from 1976 REA Power Requiremertts Study. y Historical values 113 ____..,..-----------""-w---''''''F------·---------------- Table 37 INVESTMENT COST SUb~RY GLENNALLEN-VALDEZ AREA TRANSMISSION SYSTEM Upper Susitna Transmission Line (Palmer-Glennallen} Clearing Right-of-Way Access Roads Line Structures Subtotal Project Power Market Analysis (Costs-$l,OOO 10/78) Construction Interest Investment During Construction $1,540 310 5,490 25,760 $33,100 Switchyards &Substations Palmer Substation Glennallen Switchyard Subtotal Total $3,880 920 $4,800 $37,900 $2,900 $40,800 ~'I Operation and Maintenance Costs Addition of tb~l36-mile Palmer-Glennallen transmission line would involve comparatively minor increases in overall system operation, maintenance,and replacement costs. For purpose of this analysis we are assuming the incremental O&M costs would be roughly equivalent to 1/3 of the annual cost of one transmission line maintenance crew.Adding an allowance for replacements,the annual OM&R cost is estimated at $131,000 per year.This is indicated on Table 38. 114 Table 38 OPERATION,MAINTENANCE,AND REPLACEMENT COST SUMMARY GLENNALLEN-VALDEZ AREA TRANSMISSION SYSTEM Upper Susitna Projec~Power Market Analysis Annual Cost -$1,000 Full Crew 1/3 CrewOperationandMaintenance Personnel Salary &allowances for 6 Wage Grades 240 80 /'- Miscellaneous Telephone,travel,supplies,services training,line spray,camp maintenance Equipment (Replacement) Marketing and Administration Subtotal contingencies 20%+ Subto,tal -O&M Rounded Replacement Transmission towers,fixtures,conductors 0.0001 x $25,766,000 Substations &Switchyards 0.0033 x $4,800,000 Subtotal -Replacement Rounded Total OM&R 115 10 3.3 8 2.7 22 7.3 280 93.3 60 20 340 113.3 113 2.6 15.8 18.4 18 131 Assessment of Feasibility A minimum intertie between Palmer and Glennallen would involve incremental investment costs on the order of $40.8 million.Incremental annual costs are estimated as: Amortiza t ion OM&R Total Annual Cost $3,140,000 131,000 $3,271 ,000 ..~...-. Based on the utility forecast for CVEA,it is possible that a market in excess of 100 mil1ion kwh/year could be supplied over the Palmer-Glennallen line.This would equate to transmission costs of 3.3¢/kwh. The ·100 million kwh/year would be equivalent to 22.8 MW at 50 percent annual load factor.This is substantially less than half the estimated capacity for a 138-kv Palmer-Glennallen line. Full utilization of the intertie could involve transmission of 200 to 300 million kwh/year,in which case,average transmission cost would drop from one-half to one-third the cost indicated above. Regardless of the source of power--coal ,oil,hydro--generation costs for CVEA will likely be higher than for the larger utility systems .~ serving the Anchorage-Cook Inlet area.In this context,transmission costs on the order of 1.1 to 3.3¢/kwh between Palmer and Glennallen may be justifiable. APA concludes that the Palmer-Glennallen intertie has a good chance for feasibility,and that a more detailed examination is warranted . APPENDIX 1.Letter dated January 3,1979 to Col.G.R.Robertson,Alaska District Corps of Engineers,.transmitting responses to OMB questions falling in APA's area of responsibility. 2.Previous Studies and Bibliography. 3.LOAD/RESOURCE AND SYSTEM COST ANALYSIS FOR THE RAILBELT REGION OF ALASKA:1978-2010 --Informal Report -by Battelle Pacific Northwest Laboratories,Ric"hland,Washington -January,1979. 4.Comments. a.Federal Energy Regulatory Commission,San Francisco,California, March 6,1979. b.Battelle Pacific Northwest Laboratories,Richland,Washington, February 27,1979. c.Corps of Engineers,Anchorage-,Alaska,March 19,1979. d.The Alaska State Clearinghouse,Juneau,Alaska,March 23,1979. e.Municipal Light and Power Company,Anchorage,Alaska,March 1,1979. 117 ',"",,r< Deoartment Of Energy•Alaska Power Administration P.O.Box 50 Juneau,Alaska 99802 Colonel George R.Robertson Alam(a District Engineer Corps of Engineers P.O.Box 7002 Anchorage,AK 99510 Dear Colonel Robertson: January 3,1979 Attached are our responses to the Susitna project o~m questions we agreed to provide (re:our letters dated January 20,24,1978). Copies of these responses were sent via Go1dstreak direct to Captain Mohn December 28,1978. Sincerely, Donald L.Shira Chief,Planning Division 1 OMB question 5.1,and .2. OI'-lB asked that the analysis of the "without"project condition be expanded to clearly analyze: 1.Why,with natural gas projected to be in such short supply,the Anchorage utilities have only contracted for 55 percent of proved reserves or 25 percent of estimated ultimate reserves,and, 2..The sensitivity of the analysis.to the collapse of OPEC and the cost of shipping oil to the East Coast. Both questions must be considered in terms of national en~rgy policy_ The Nation needs to reduce dependency on oil i~ports on both a short- term and a long-term basis,and to accomplish a major shift a\,;ay from· oil and natural gas to alternative energy sources.The reasons for this include national economic considerations,as well as very real.limits on national and world supplies of oil and natural gas. In terms of national energy policy,oil and natural gas are not available alternatives for lo?g-term production of electric power.There are . remaining questions as to how quickly exist~ng uses will be phased out and on how complete the prohibitions will be on new oil.and natural gas- fired powerplants. There is general .agreement.that implementation of national policy must include stropg efforts in conservation,substantial in~rease in use of coal,and major efforts to develop renewable energy sources.Each of these components is sensitive to energy price and snpply variables.A reduction in world oil prices or·a period of oversupply serves as a marketplace disincentive for conservation efforts and \olork·on alterna- tiveenergy sources. The lowest cost alternatives and those with fully proven technology are the least sensitive;those that depend on further R&D are most easily sidetracked. Tht:!Susi.tna Proj ec·t involves l<l.rge blocks of pOtver and ne,v e.ne.rgy from a rene,....able source,fully proven technol.ogy,long revenue-produci.ng period (in excess of 100 years),and essential freedom from long-term price increases.Its unit costs appear attrac~ive in comparison to coal-·fired pm.·;erplants.It is a t,vo-stage project "lith opportunity to defer the second st.age if demands are lO\v2r than present estimates or if price relationships cha.nge. The above factors suggest that t:he Upper Susitna Project is much less sensitive to short-:-term oil price and supply variations than most other u.s.energy options. -""-------------...,._._--------~----,.."..------------------------ 2 If it i!;as'-:;lIl:lecl that 1\lClsktm oil and natUl~al gas ",ill be isolated fro:n U_S_and world demalld Cluel pric.:ing,l\)aska \<Joulc1 pr(lb~lbly continue to use its oil ':-Inc1 getS for most of its pover.Tbi!;its!;1.lmption did,in fact, prevail h(~t\<lecn the initinl oi.l and gas c1i.~;covc:r.ies in the Cook Inlet area and the 1973 oil cmb".rgo.In J.960 ,the l~nchorilge-Cook Inlet n:ce,l pO\4er supplies came almost:·entirely from coal and hydro.'l'he 10'.'1 cost, abundant:gas brought a halt to hydro dcvelop,uent:and destroyed the arei!.t s coal industry.'l'he one re..-uaining l\laskan coal mine barely made it tIlro.ugh the 1960's because of compc"tition from relatively cheap oiL The Cook Inlet gas has been subjected to increasing competition in ·the last fe':l years,including proposals for LNG facilities,aC1ditional petrochemical plants,~nd consideration of pipeline alternatives to tie in \oTith the Alcan pipeline project.The competition resulted in :increas- ing prices and increasing difficulty in obtaining long-term co~~itments o~gas for power.The ~ompetitions and the price increases are expected to continue.. The real question on gas availability as it pertair;s to Upper Susitna' is:"lhat is the out·look foi long-term gas supplies for po\ver after 1990?That out-look is not good in terms of competing uses and national policy .. .3 3 Response to Of.m question 5.3. "The Necessity for an Anchorage-Fairbanks intertie at:a cost of $200-300 million" The estimated construction cost (1978 dollars)for the transmission lines from the Susitna project to the Fairbanks area is $152 million, and $186 million for the lines from the project to the Anchorage area (total $338 million). Th .1 .d"1/h d t .h t f "b'l"ere are:severa prev~ous stu 1es-t at emons rate 1n eren easl 1 1 ty of an Anchorage-Fairbanks intertie with or without construction of the Upper Susitna Project.The main reason that the intertie is not now in place is that short term benefits to the Anchorage area are quite small, i.e"most of the short term benefits for the intertie \-10uld occur through reduced energy and power costs in the Fairbanks area. APA studies in the 1975-feasibi1ity report evaluated Susitna Project power to Fairbanks on a cost-of-service basis (see Appendix I,p.6-89). This was a specific demonstration of feasibility of including Fairbanks as part of the Upper Susitna Power Market area. 1/Amongr the previous studies are:. Alaska Power Survey,Federal Power Commission,1969. Central .Alaska Power Pool,working paper,Alaska Power Administration, October 1969. Alaska Railbelt Transmission System,working paper,Alaska Power Admin- istration,December 1967~· Electric Generation and Transmission Intertie System for Interior and Southcentral Alaska,CH2M Hill,1972. Central Alaska Power Study,The Ralph M.Parsons Company,undated, Alaska Power Feasibility Study,The Ralph M.Parsons Company,1962. 4 Further verification of feasibility of the intertie is provided in the new load-resource analyses and system cost analyses prepared for the current studies.These general cases were analyzed: j !, i Case 1. Case 2. Case 3. All future generating capacity assumed to be coal-fired steam turbines without intertie. All future generating capacity assumed to be coal-fired steam turbines with intertie. Future generating capacity to include Upper Susitna Project plus coal~fired_steam plants as needed.Includes intertie. Results of power cost analyses for Anchorage and Fairbanks for the year 2000,with and without intertie are as fQl1ows: Power Costs for Anchorage and Fairbanks (0%Inflation) (¢/KWH) Case 1 Case 2 Case 3 Without Intertie with Intertie With Susitna and Intertie Anchorage Fairbanks Anchorage Fairbanks Anchorage Fairbanks High 6.2 8.8 6.1 8.0 5.8 6.2 Med 6.6 8.9 6.2 .8.4 5.5 6.7 LmV'7.1 9.2 6.2 8.8 6.1 7.8 The following table presents a comparison of the costs of power in the "year 200~for Case 2,and 3 as compared to Case 1.As shown the costs of power are reduced below the cost of power for Case I in all cases. The reduction in the cost of power is typicallY greater in the I~'Fairbanks-Tanana Valley area than in the Anchorage-Cook Inlet area because the Anchorage-Cook Inlet area will have a higher percent of its generation supplied by steam plants which are more costly than Susitna. Comparison of Power Costs for Year 2000 Percent Change in Cost of Power Below Case 1 -0%Inflation', Anchorage Fairbanks High Medium Low High Medium Low Case 2 -1.6 -6.5 -14.5 -10.0 .-6.0 -4.5 Case 3 -6.9 -20.0 -16.4 -41.9 -32.8 -17.9 Table 1 compares annual system costs for all three cases for Anchorage and Fairbanks during the 1990-2011 period. Table 1 shows the following percent savings in system costs (1990-2011) for Ca.ses 2 and 3 compared to Case 1: Case 2 Case 3 Anchorage -0.4 -10.7 Fairbanks -7.9 -28.1 Total -1.4 -14.1 .) Table 1.Annual Power System Costs for Power Supply Under Cases I,II,and III -Mid-Range Load Projections -0%Inflation ($Million) Period Case I Case II Case III Anchorage Fairbanks Anchorage Fairbanks _Anchorage Fairbanks 1980-90 272.0 90.6 254.5 84.2 254.5 84.2 90-91 274.2 96.8 293.8 89.0 293.8 89.0 -91-92 324.2 98.2 343.8 90.2 343.8 90.2 92-93 387.5 119.5 409.9 88.2 409.9 88.2 93-94 391.7 120.9 414.1 89.2 414.1 89.2 94-95 398.9 122.2 421.3 114.9 537.5 120.5 95-96 463.7 127.6 486.1 143.7 537.9 124.8 96-97 549.0 152.4 571.5 143.2 543.0 124.0 97-98 615.9 167.8 578.7 158.5 549.3 139.2 98-99 627.7 -192.0 650.2 182.6 576.3 145.1 1999-2000 694.4 193.8 657.2 184.5 577.2 145.7 Sub total 4,999.4 1,481.8 5,081.1 1,368.2 5,037.3 1,240.1 00-01 691.8 194.9 714.3 185.5 573.4 146.5 01-02 698.6 196.2 721.1 186.8 578.5 147.4 02-03 760.3 195.0 723.1 208.2 658.6 168.6 03-04 767.9 230.8 789.8 209.6 665.1 169.6 04-05 776.0 232.2 798.5 211.0 670.8 170.6 05-06 864.0 232.1 807.1 210.9 677.6 170.2 06-07 872.8 233.5 815.9 212.3 744.4 171.2 07-08 881.9 235.1 904.4 213.8 751.6 172.3 08-09 891.1 236.5 913.6 215.2 759.0 173.4 09-10 901.6 238.1 923.1 216.9 .766.7 174;6 10-11 969.9 239.6 932.7 218.4 834.3 175.7 '1.'0 tal 14,075.1 3,945.8 14,124.7 3,656.9 12,717.3 3,080.2 /' ).J (j\ 7 ReSpOnSE!to Qr·m question 5.4. "Scheduling of po~.,eEpla.nts and t.he reduced risk of building small incrcment.s." The LoacVResource analysis for without project condition addresses,the .'. scheduling of steamplants and size of units needed.This is demonstrated in Chapt:er VII of the marketability report.Annual power system costs shown in Table 1 under question 5.3 show savings from Susitna over the without Susitna case.The steamplants are smaller units than Susitna, but thei.r higher cost contributes to higher overall system costs.An analysis of hydro alteinative~indicate that there are not economical sites available in sufficient quantity to be comparSlble to Susitna. This is supported by APA's draft report on "Analysis of Potential Alternat:ive Hydroelectric sites to Serve Railbel t Area.II .., 8 Response to OMS question 6.1,.2,and .3. Demand Estimates The analysis of load growth should be more specific with respec~ to: 1.Increasing use by consumers;and, 2.Increasing number of consumers. 3.Industrial groTtl"th,i.e.,Ttlhere-does Alaska's comparative ~ advan~age lie ou~side the area of raw materials and governmen~ functions? The new estimates of future P9wer demand are responsive to the first two parts of this question.APA completed a very careful analysis of recent power use trends by class of customer,with particular emphasis on identifying recent trends that could be attributed ~o conservation efforts.The future demands are based on future population estimates developed by the University of Alaska's Institute of Social and Economic Research and incorporate assumptions of substantially improved efficiency in use of electric power through conservation. The third part of the question requires consideration of the overall Alaskan economy,present and future,and the role of Upper Susitna power. Alaska is not a heavily industrialized State nor is it expected to be. $ The oil and gas industry is presently the dominating sector of the State's GNP,and ~.;ill continue to be so for at least the balance of .the 20th century.This is the principle source of revenues for the State and thus the driving force behind State programs for education,local government assistance,....lelfare,and so on.Other important industries are the fisheries,forest products,and recreation-tourism. The low-and mid-range population estimates incorporate very modest assumptions of industrial expansion based on pioneering of Alaskan natural resources for the most part.The specific industrial assumptions reflect proven sources of natural resources and projects that are well along in the planning stages. w 9 Extraction and processing of natural reso?rces will undoubtedly continue to be major aspects of the Alaskan economy.Other important aspects include.~usiness activities of Native Corporations and increasing amounts of land made available to State and private mmership.Actions pending on the new National Parks,Refuges,and wild and Scenic Rivers will encourage further development of the recreation and tourism industries. As inmost parts of the country,Alaska employment is not dominated by.~. the industrial sectors.l-lost jobs are in service.industries,the coinmer- cial establishments,transportation,utilities,and government.The new population estimate by ISER indicates that the distribution of employment will not change sUbstantially.The anticipated gro\~h in the economy, employment,and in power demands is primarily in the non-industrial sectors. It should be nbted that the Railbelt area demands for electric energy in 1977 were 2.7 billion kilm.,ratt-hours,which is approaching the firm energy capability of the Watana Project.The load resource analyses demonstrate full utilization of Watana energy essentially as soon as it becomes available,even under the lower power demand case.This basically leads us to a finding that the Upper Susitna justification is not dependent on major industrial expansion in Alaska. 10 .~. Response to Qr.m Question 7. Under the topic Sensitivity Analysis,OMB provided the following comments: "POl-ler demand should be subjected to a sensi tivi ty a.nalysis to better assess the uncertainties in development of such a la.rge block of power. The typical utility invests on the basis of an 8-10 year time horizon . .The Susitna plan has an 11-16 year horizon in face of risks that loads may not develop and the option of l-lheeling p0l-ler to other markets is not available.It should be noted that.the pO"ler demand for Snettisham t.,as unduly optimistic l-lhen it w'as built.This resulted in delays in installing generators.A similar error in a project the size of Susitna ,'!ould be much more costly and wouLd have a major adverse effect on the project's economics." . The new power demand estimates,load resources analyses,and financial .~. analysis presented in this report,all provide a better basis for examining these questions.In addition,there is need to review some of the Snettisham Project history to bring out similarities and differences with the Upper Susitna case. Snettisham Review The Snettisham Hydroelectric Project is located near Juneau,Alaska,and is now the main source of power for the greater Juneau area.The project was authorized in 1962 on the basis of feasibility investigations by the Bureau of Reclamation,constructed by the Corps of Engineers,and opera- ted by the Alaska Power Administration. The-project ,vas conceived as a .two-stage development and construction of the first,or Long Lake,stage was completed in late 1973 with first commercial power to Juneau in December 1973.The second,or Crater Lake,stage would be added when power demands dictate. ,,- ,~,' 11 Juneau was,and is,an isolated power market area.Difficult terrain and long distances have thus far prevented electrical interconnection with other Southeast Alaska communities and neighboring areas of Canada; hmvever"such interconnections may prove feasible ...Ii thin the next 15 to 20 years.The project planning and justification waS premised on per- vice only to the greater Juneau area. The Snettishamauthorization was based on power demand estimates by the Alaska District,Bureau of Reclamation (no~'1 Alaska PO\'1er Administration)./- l!The estimates were based on actual power use through 1960 and projec- tions to the year 1987.The outlook'at that time \-laS that the first stage construction would be completed in 1966,and that total project capability would not be needed until 1987. A comparison of power demand estimates at the time of authorization with actual demands is shovm on Table 1.The 1977 energy load waS 112,197 megawatt-hours or 81 percent of the amount estimated in 1961 based on historical records through 1960. l!Re,~raisal of the Crater-Long Lakes Division,Snettisham Project, Alaska,USER,November 1961. ----------''''1---------------------' Table 1 Power ana Energy Requirements-Juneau Area 12 ..~ Forecasted Demands at Actual Demands Time of Authorizatipn 11 Fiscal Year Peak I>l~v MWH Peak MW (Oct.1 -Sept.30) 1958 23,945 4,788, 1959 26,297 5,321 1960 28,499 5,465 1970 58,266 12,420 73,400 ·15,230 ,~ 1971 63,786 13,780 80,700 16,750 1972 70,225 14,910 88,800 18,430 1973 75,753 15,470 97,500 20,240 1974 83,059 l6,220 106,900 22,190 1975 94,609 17,840 116,900 24,260 1976 106,296 19,800 127,600 26,480 1977 .·1:12,197 20,440 139,100 28,870 Project,A.).~~$'il,.USBR,November 1961. 1/.From Reapp;r;J~~~'~the Crater-D:mg Lakes Division,Snettisham )'::~~:,,:i.....~:;r·:'-:;, "F .~~. 13 The inherent flexibility of a staged project proved to be very benefi- cial in the case of Snettisham.APA made periodic updates of the power demand estimatesoduring construction of the Long Lake stage.For several years,these forecasts indicated a'need to proceed with the Crater Lake stage construction immediately on completion of th~Long Lake stage.The Corps of Engineers construction schedules and budget requests,based on the APA power demand estimates,anticipated start of construction on Crater Lake in FY 1977.Major factors in these fore- casts were plans for a major new pulp mill in the Juneau area and for iron ore mining and reduction facility in the vicinity of Port Snettisham. Ned ther of these developments \iere anticipated at the time of authoriza- tion.Both of these resource developments fell through,and this resulted in a substantial reduction in the APA power demand estimate and a decision in late 1975 to defer.the Crater Lake cons·truction start. The pulp mill was particularly influential in the change in demand estimates.The mill was planned for operation in the early 1970's with a large population and commercial impact on Juneau~Initial access faciliti,es \...ere constructed and site preparation \'1as well underway when the project became entangled in protracted la\'1 suits involving logging practices in SOutheast Alaska.Several court decisions were made in favor of the development,but a last minute remand put the project back to base one and led to cancellation in early 1975. This type of uncertainty faces all utility planners.The staged project like Snettisham'affords a great deal of capability to adjust to changes in'demand. Nany other factors influenced Juneau area power demands and utilization of project power.Of particular concern at the moment is impact of Alaska's capital move initiative.This would certainly change use of project power,with the most likely outcome that the cornmunity would move more quickly into an all-electric TOClde (space heating and electric vehicles appear particularly attractive in this area)and industrial use of power would increase through economic diversification. -------------------------------------,--------------------- 14 The key points of the ~nettisham revieH are: 1.The project was planned and authorized with intent to handle grov~h in area power requirements for'a 20-year period. 2.The load forecasts used·as a basis for authorization were reasonably accurate. 3.The actual use of project power may turn out to be substantially different than originally anticipated. 4.The flexibility of staged projects was actually used. 5.The outlook for financial viability appears excellent at this time in history •. Implications for Susitna First,the norm for utility investments cannot remain as the basis of an 8 to lO.year time horizon.This is evidenced by experiences since about 1970 on time required to plan,obtain necessary permits or authorizations, find financing,and then build new powerplants and major transmission facilities.The 8 to 10 years is much too short for nuclear,coal,and hydro plants and for major transmission lines. It appears appropriate to require a 20-year planning horizon with careful checks at each step in the process and business-like decisions to shift construction schedules if conditions (demands)change.We believe the snettisham experience is very positive in this light. The Susitna Project is similar in that project investment is keyed to two major stages.The commitment of construction funds for Natana would be needed in 1986 or 1987 to have power on line by 1993 or 1994.If .~ conditions in 1986 indicate need to defer the project,it should be deferred.Similarly,start of actual construction on Devil Canyon can .(.1, 15 and should be based on conditions that actua:py prevail at the time the decision is made. The level of uncertainty for Upper Susitna is greater than was the case for Snetltisham on counts of higher interest costs and larger total investment.Sensitivity to change in demands is much less for Susitna because of its large and diversified power market area.There are many more \'1ays that Susitna Project pm'1er could be effectively utilized in the even"t that traditional utility power markets are smaller than anticipa"ted at the present. Upper Susitna'does not have as many uncertainities in terms of environ- mental ~uestions as would equivalent power supplies from coal or nuclear plants.Uncertainties on air quality are particularly relevant for any larger Alaskan coal-fired powerplants. -,---_---------:--------------...,1--------------------------- 16 .~) Current Evaluation Power demands were estimated for High,Medium,and Low cases to year 2025 assuming logical variations in population and energy use per capita. The projections reflect energy use per capita based on detailed studies of 1970-1977 data from both the Anchorage and Fairbanks areas.The projections considered variations in per capita use ranging from increased use of electricity in the horne to anticipated effects of con~ervation on decreasing the growth rates.A detailed discussion of the development of the power demands is included in Chapter 5 of this report. The load/resource and cost analysis provided system cost for comparison of cases both with and without the Susitna Pn?ject.The analysis also compared the power demands to the resources required to determine sizes and timing of new plants (the load/resource analysis is summarized in Chapter VII}.Table 2 summarizes the resources needed during the 1990's for the range of projections..~. The Table indicates that even under the ITDst conservative load growth condition (low),1,500 Miv are needed to meet the combined Anchorage- Fairbanks demands,which is roughly the capability of Susitna. Tables 3 and 4 show the pOyler costs for Anchorage and Fairbanks during the 1990's with an interconnection and with and without the Susitna ·Project.It is readily apparent the rates are less for the case with Susitna. For example,in the medium case for the year 2000,Anchorage costs are 5.5¢/kwh or 13 percent less than without Susitna.In the Fairbanks costs,the difference is much larger,6.7¢/kwh or 25 percent less than without Susitna. In Table 5,annual system interest costs are composed with and without Susitna with intertie from 1990 to 2011.Examination of the system cost on an annual basis reveals the case with Susitna is cheaper than the without Susitna case for each year except the first few years after Watana comes on line. 'l'able 2.Schedule of Plant Additions -l~i 17 Cases with "Interconnection without Upper Susitna Anchorage Fairbanks Period .'High Median !.ow High Median Low· 89-90 400 *200 *100 90-91 200 91-92 400 200 ~ 92-93 400 200 200 93-94 400 100 94-95 *100 * 1""""'"95-96 400 400 200 .100 100 96-97 400 400 200 100 100 97-98 400 400 200 100 100 98-99 400 400 100 99-00 400 TOTAL 90-2000 3200 2000 1200 700 "400 300 *Interconnection Installed in 1987 for high case,1990 for median case, &1995 for low case. Repla,cement of military powerplants,many of which also supply heat for buildin<;rs are additional but not shown here. ---"''"t""--------------------,,--- TABLE 3.Power Costs for Anchorage and Fairbanks Areas With Interconnection and Without Upper Susitna -0%Inflation (cents/kwh) 18 ~. ,:au Anchorage Fairbanks Period High Median Low High Median Low 89-90 5.7 4.5 4.2 4.7 5.8 5.6 90-91 5.4 '4.8 4.1 4.6 5.9 5.8 91-92 5.7 5.3 4.1 4.4 5.7 5.8 92-93 5.4 5.9 4.7 6.3 5.4 5.6 93-94 5.7 5.6 4.6 7.3 5.2 5.5 94-95 5.5 5.4 4.9 7.0 6.5 6.7 95-96 5.6 5.8 5.4 7.8 7.7 6.9 96-97 5.8 6.4 5.8 8.2 7.4 8.3 97-98 5.9 6.1 6.6 8.7 7.8 9.1 ~, 98-99 6.0 6.5 6.4 8.3 8.7 8.9 99-00 6.1 6.2 6.2 ,8.0 8.4 8.8 TABLE 4.Pb,.;er Costs for Anchorage and Fairbanks Areas With Interconnection and With Upper Susitna Coming on IJine in 1994 -0%Inflation (cents/kwh) Anchorage Fairbanks Period Hig~Median Low High Median La,.; 89-90 5.7 4.5 4.2 4.7 5.8 5.6 90-91 .5.4 4.8 4.1 4.6 5.9 5.8 91-92 5~7 5.3 4.6 4.4 5.7 7.2 92-93 5~4 5.9 4.4 6.3 5.4 6.9 93-94 5.7 5.6 5.0 7.3 5.2 6.8 94-95 6.4 6.9 7.3 7.9 6.8 8.8 95-96 6,,0 6.5 6.8 7.7 6.7 8.9 96-97 6.2 6.1 6.5 7.2 6.4 8.6 97-98 6.2 5.8 6.3 6.6 6.9 7.8 98-99 6.1 5.8 6.1 6.5 6.9'7~6 99-00 5.8 5.5 6.1 6.2 6.7 7.8 19 20 ~. TABLE 5.Po\"er System Annual Costs for Anchorage and Fairbanks With Upper Susitna Coming On Line in 1994 -0%Inflation (million $) Anchorage Fairbanks Period High Median Low High Median Low 89-90 508.5 254.5 173.4 85.2 84~2 63.4 90-91 514.1 293.8 175.0 89.0 89.0 68.5 91'-92 591.8 343.8 206.0 90.2 90.2 87.4 92-93 597.3 409.9 205.0 137.8 88.2 85.5 93-94 666.0 414.1 244.5 166.8 89.2 86.4 .ao 94-95 798.5 537.5 372.3 192.2 120.5 115.6 95-96 806.1 537.9 368.4 198:0 ·124.8 119.2 96-97 898.6 543.0 368.5 198.5 124.0 117.5 97-98 793.1 549.3 369.9 192.5 139.2 109.2 ,..-". 98-99 1,009.1 576.3 376.1 .201.3 145.1 109.7 99-00 1,018.9 577.2 3910 7 203.5 145.7 114.9 00-01 1,025.1 573.4 381.4 228.6 146.5 114.5 01-02 1,101.3 578.5 380.3 254.0 147.4 114.5 02-03 1,172.1 658.6 375.3 254.3 168.6 111.9 03-04 1,190.4 665.1 376.6 291.6 169.6 112.0 04-05 1,287.7 670.8 376.8 296.0 170.6 112.1 05-06 1,366.8 677.6 378.0 296.1 170.2 110.7· 06-07 1,386.8 744.4 379.4 299.2 171.2 110.8 07-08 1,467.2 751.6 380.8 302.4 .172.3 110.9 08-09 1,548.1 759.0 382.2 305.7 173.4·111.1 09-10 1,569.9 766.7 383.7 343.5 174.6 111.2 10-11 1,671.6 834.3 385.2 347.0 175.7 111.4 Total 22,989.0 12,717.3 7,430.5 4,973.4 3,080.2 2,308.4 '21 (con1;inued) TABLE 5.Power System Annual Costs for Anchorage and Fairbanks Without Upper Susitna Coming,On Line in 1994 -0%Inflation (million $) Anchorage Fairbanks Period High Median Low High Median Low-- 89-90 508.5 254.5 173.4 85.2 84.2 63.4 90-91 514.1 293.8 175.0 89.0 89.0 68.5 91-92 591.8 343.8 185.7 90.2 90.2 71.1 92-93 597.3 409.9 223.3 137.8 88.2 69.2 93-94 666.0 414.1 227.2 166.8 89.2 70.1 94-95 678.0 421.3 252.4 169.<1 114.9 87.2 95-96 750.0 486.1 290.9 201.3 143.7 91.8 96-97 843.4 571.5 327.9.224.8 143.2 113.1 97-98 918.8 578.7 389.8 253.4 158.5 127.6 98-99 998.3 650.2 396.7 256.3 182.6 128.4 99-00 1,074.0 657.2 397.9 259.7 184.5 '129.3 00-01 1,160.8 714.3 470.6 262.3 185.5 129.6 01-02 1,238.6 721.1 472.5 265.3 186.8 130.2 02-03 1,310.9 723.1 469.8 265.8 208.2 128.3 03-04 1,331.0 789.8 472.8 303.5 209.6 128.8 . 04-05 1,350.7 798.5 474.8 341.2 211.0 129.3 05-06 1,431.7 807~1 477.8 343.1 210.9 128.4 06-07 1,513.3 815.9 480.9 346.5 212.3 151.7 07-08 1,615.1 904.4 484.0 350.1 213.8 152.2 08-09 1,638.1 913.6 487.1 353.7 215.3 152.8 09-10 1,721.4 923.1 490.3 357.5 216.9 153.3 10-'-11 1,801.7 932.7 493.6 361.4 218.4 153.9 Total 24,253.5 14,124.7 8,314.4 5,484.3 3,656.9 2,558.2 22 ,~. It should be noted that in the 10\0'energy use estima.te the total system cost for Anchorage during this period amounts to $883.9 million less with Susitna than ~vithout.the project.,The difference is even larger in the medium and high cases.The combined Anchorage-Fairbanks cash savings for the Same period based on the medium power use estimate is almost'$2 Billion~ Previous Studies There \.,as a fairly substantial backlog of power system and project studies relevant to the 1976 evaluation of the Upper Susitna River Project.The previous studies most relevant include: 1.Advisory Committee studies completed in 1974 for the Federal Power Commission's (FPC)1976 Al~ska Power Survey.The studies include evaluation of existing power systems and future needs through the year 2000,and the main generation and transmission alternatives available to meet the needs.The power requirement studies and alternative generation system studies for the 1976 power survey were used extensively. 2.,A·series of utility system studies for Railbelt area utilities include assessments of loads,power costs,and generation and trans- mission alternatives. 3.Previous work by the Alaska Power Administration,the Bureau of Reclamation,·the utility systems,and industry on studies of various plans for Railbel t transmission interconnections and the Upper Susi tn'a hydroelectric potential. It should be noted that many of the studies listed in the bibliography represent a.period in history when there \vas very little concern about energy conservation,growth,and needs for conserving oil and natural gas resourc~s.Similarly,many of these studies reflected anticipation of long term,very low cost energy supplies.In this regard,the studies for the 1976 power survey are considered particularly significant in that they provide a first assessment of Alaska pmver system needs .reflecting the current concerns for energy and fuels conservation and the environment,and the rapidly increasing costs of energy in the economy. The latter concern for conservation,etc.has been carried even further in this report.As yet unpublished studies by the Alaska Power Admini- stration have made a definite reflection of conservation assumptions. The resulting load forecasts were used in load/resource analyses done and reported by Battelle Pacific Northwest Laboratories in 1978 and 1979.(Ba:Helle also published a report in 1978 entitled Alaska Electric Power,and Analysis ~Future Requirements and Supply Alternatives for the Railbelt Region.)Pop'ulation and employment used in the recentfurecasts lvere proj ected and reported by the Institute of Social and Economic Research in September 1978.The result of their econometric:model is entitled South Central Alaska's Economy and Population,1965-2025:A Base Study and Projection.A partial bibliography of related studies including those of the 1976 Susitna report,is appended. 25 PARTIAL BIBLIOGP~PHY OF RELATED STUDIES The 1976 Alaska Power Survey,Federal Power Commission Vol.I and Vol.II. Alaska Regional Energy Resources Plant Project -Phase I,Alaska Division of Energy and Power Development,Department of Commerce an.d Economic Development,October 1977. Volume I -Alaska's Energy Resources,Findings and Analysis Volume II -Alaska's Energy Resources,Inventory of Oil,Gas, Coal,Hydroelectric,and Uranium Resources Jobs and Power For Alaskans:A Program for Power and Economic Develop- ment,July 1978.Department of Commerce and Economic Development. Appendix:Power and Economic Development Program,July 1978. Alaska Electric Power Statistics 1960-1976,Alaska Power Administration, July 1977. The Proposed Glennallen-Valdez Transmission Line.An Analysis of Available Alternatives.Robert W.Retherford Associates,May 1978. Power Requirements Study,Matanuska Electric Association,Inc.Rural Electrification Administration,May 1978. 26 Southcentral Railbelt Area,Alaska,Upper Susitna River Basin Interim Feasibility Report.Hydroelectric Power and Related Purposes,Corps of Engineers,December 1975. Appendix I,Part I:(A)Hydrology,(B)Proj'ect Description and Cost Estimates,(C)Power Studies and Economics, (D)Foundation and Materials,(E)Environmental Assessment, (F)Recreational Assessment· Appendix I,Part II:(G)Marketability Analysis,(H)Trans- mission System,(I)Environmental Assessment for Transmission Systems Appendix II:Pertinent Correspondence and Reports of Other Agencies. A Hydrologic Reconnaissance of the Susitna River Below Devils Canyon. Environaid,October 1974. Solomon Gulch Hydroelectric Project.Definite Project Report. Robert W.Retherford Associates,March 1975. Electric Power in Alaska,1976-1995.Institute of Social and Economic Research,University of Alaska,August 1976. Southcentral Alaska's Economy and Population,1965-2025:A Base study and Projection. Economic Research,University of Alaska,September 1978 (Draft Report). 27 Interior Alaska Energy Analysis Team Report.Fairbanks Industrial Development Corporation for Division of Ener~and Power Development, June 1977. Natural Gas Demand and Supply to the Year 2000 in the Cook Inlet Basin of Southcentral Alaska.SRI International for Pacific Alaska LNG Company,November 1977. Load/Resource and System Cost Analysis for the Railbelt Region of Alaska;1978-2010.Battelle Pacific Northwest Laboratories, January 1979. Participation in Healy It Electric Generation,Fairbanks Mun~cipal Utilities System.Harstad Associates,Inc.June 1978. Economic Feasibility of a possible Anchorage-Fairbanks Transmission Intertie.Robert W.Retherford Apsociates for Alaska Power Authority (not yet completed). 1976 Po'wer Systems Study,Chugach Electric Association,Inc.Tippett and Gele.March 1976. Comparative Study of Coal and Nuclear Generation Options in the Pacific Northwest,Washington Public Power Supply System,June 1977. Coal-Fired Powerplant Capital Cost Estimates,Electric Power Research Institute,January 1977. 28 Analysis of the Economics of Coal Versus Nuclear for a Powerplant Near Boise,Idaho,Idaho Nuclear Energy Commission,March 1976. Alaska Electric Power,AD Analysis of Future Requirements and Supply Alternatives for the Railbelt Region,Battelle Pacific Northwest Laboratories,March 1978. Geology and Coal Resources of the Horner District Kenai Coal Field,Alaska, Geological Survey Bulletin lOSS-F,19S9. Development of the Beluga CoalField,a status report,A.M.Laird, Placer Arnex Inc.,San Francisco,California,October 1978. TTidal Power From Cook·Inlet,Alaska,Swales,M.C.and Wilson,E.M., published in Tidal Power,Proceedings of the International Conference on the Utilization of Tidal Power,May 1970. Advisory Committee Reports for Federal Power Commission Alask~ Power Survey: Report of the Executive Advisory Committee;December 1974 Economic Analysis and Load Projections,May 1974 Resources and Electric Power Generation,May 1974 Coordinated Systems Development and Interconnection,December 1974 Environmental Considerations and Consumer Affairs,May 1974 29 Alaska Power Survey ,Federal Pmver Commission,1969. Devil Canyon status Report,Alaska Power Administration,May 1974. Devil Canyon Project -Alaska,Report of the Commissioner of Reclamation, March 1961,and supporting reports.Reprint,March 1974. Reassessment Report on Upper Susitna River Hydroelectric Development for the State of Alaska,Henry J.Kaiser Company,Sept.1974. Project Independence,Federal Energy Administration,1974.A main report,summary,seven task force reports,and the draft environmental impact statement. Engineering and Economic Studies for the City of Anchorage,Alaska Municipal Light and Power Department,R.W.Beck and Associates and Ralph R.Stefano and Associates,August 1970. Power Supply,Golden Valley Electric Association,Inc.,Fairbanks, -Alaska,Stanley Consultants,1970. Copper Valley Electric Association,Inc.-15 Year PO\ver Cost Study, Hydro/Diesel,Robert W.Retherford Associates,October 1974 . .-,-------------.....,.--------------.,,------------------------ 30 Environmental Analysis for Proposed Additions to Chugach Electric Association,Inc.,Generating station at Beluga,Alaska,Chugach Electric Association,October 1973. Central Alaska Power Pool,working paper,Alaska Power Administration, October 1969. Alaska Railbelt Transmission System,working paper,Alaska Power Administration,December 1967. Electric Generation and Transmission Intertie System for Interior and So~thcentral Alaska,CH2M Hill,1972. Central Alaska Power Study,The Ralph M.Parsons Company,undated. Alaska Power Feasibility Study,The Ralph M.Parsons Company,1962. "...} PNL-2896 INFORMAL REPORT LOAD/RESOURCE AND SYSTEJl1 COST ANALYSIS FOR THE RAILBEt.T REGION OF ALASKA: 1978-201 0 for ALASKA POWER ADMINISTRATION u.s.DEPARTMENT OF ENERGY by J.J.Jacobsen W.H.Swift J.A.Haech January 1979 Pacific Northwest Laboratory Richland,Washington 99352 "----nv---""----,----'j"--------------r""'i----------------- CONTENTS LIST OF FIGURES LIST OF TABLES . 1.0 INTRODUCTION 2.0 SUMMARY AND CONCLUSIONS 3.0 LOAD/RESOURCE ANALYSES 3.1 ANALYSIS METHODOLOGY 3.2 ASSUMPTIONS 3.2.1 Forecasted Power and Energy Requirements 3.2.2 Existing and Planned Generating Capacity 3.2.3 Reserve Margin 3.2.4 Transmission Losses 3.2.5 Construction Schedule Constraints 3.2.6 Plant Availability Constraints 3.2.7 Economic Generating Unit ,Size 3.3 SYSTEM CONFIGURATIONS =DEFINITION OF CASES ANALYZED 3.3.1 Case 1:Without Interconnection and Without Upper Susitna Project 3.3.2 Case 2:With Interconnection,Without Upper Susitna Project . 3.3.3 Case 3:Interconnected System With Upper Sus itna Project 3.4 RESULTS OF LOAD/RESOURCE ANALYSES 4.0 SYSTEM POWER COST ANALYSES 4.1 FACTORS DETERMINING THE COST OF POWER 4.1.1 Capital Costs 4.1.2 Heat Rate 4.1.3 Operation,Maintenance,and Replacement Costs 4.1.4 Financing Discount Rate 4.1.5 Payback Period 4.1.6 Annual Plant Utilization Factor 4.1.7 Unit Fuel Costs 4.1.8 General Inflation Rate. 4.1.9 Construction Escalation Rate iii v 'Ii 1 4 7 8 8 8 15 15 21 21 22 25 25 25 26 30 31 66 66 '66 68 68 69 69 69 69 73 73 __~"""""',.,.......~----~'*~_~_m __---_ 4.1.10 Fuel Escalation Rate ..73 4.2 METHOD OF COMPUTING THE ANNUAL COST OF POWER FROM INDIVIDUAL GENERATING FACILITIES 73 4.3 METHOD OF COMPUTING AVERAGE SYSTEM POWER COST 75 4.4 RESULTS OF SYSTEM CASH FLOW AND POWER COST CALCULATIONS 76 iv 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 3.11 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 4.9 4.10 FIGURES Railbelt Region Peak Loads Anchorage-Cook Inlet ~rea Annual Energy Fairbanks Area Annual Energy Plant Utilization Factor versus Plant Age Railbelt Region Showing the Watana and Devil Canyon Damsites,a Possible Route for the Interconnection,and the Beluga Area Load/Resource Analysis for Anchorage-Cook Inlet Area Without Interconnection and Without Susitna Project (Case 1). .Load/Resource Analysis for Anchorage-Cook Inlet Area With Interconnection but Without Upper Susitna Project (Case 2) Load/Resource Analysis for Anchorage-Cook Inlet Area With Interconnection and With Upper Susitna Project Coming On Line in 1994 (Case 3) Load/Resource Analysis for Fairbanks-Tanana Valley Area Without Interconnection and Without Upper Susitna Project (Case 1) Load/Resource Analysis for Fairbanks-Tanana Valley Area With Interconnecti on but Without Upper Sus itna Project.(Case 2) Load/ResourceP..na lys i sfar Fairbanks-Tanana Valley Area ~.Jith Interconnecti on and With Upper Sus i tna Project Comi og On Li ne in 1994 (Case 3) Components of the Total Annual Cost of Power Estimates of Future Coal Prices -.2%and 7%Escalation Estimates of Future Natural Gas Prices -2%and 7%Escalation Estimates of Future Fuel Oil and Diesel Prices -2%and 7% Esca.l ation Power Costs for Anchorage Low Load Growth Scenario Power Costs for Anchorage Medi urn Load Growth Scena ri 0 Power Costs for Anchorage High Load Growth Scenario Power Gnsts for Fairbanks Low load Growth Scenario Power Costs for Fairbanks Medium Load Growth Scena~io Power Costs for Fairbanks High Load Growth Scenario v 12 13 14 23 28 60 61 62 63 64 65 67 70 71 72 116 117 118 119 120 121 TABLES 3.6 3.5 3.7 3.4 58 54 56 19 20 27 32 6 9 10 19 16 11 18 3.8 3.9 3.10 3.11 Comparisbn of Power Costs for Year 2005 Anchorage-Cook Inlet Area Power and Energy Requirements Fairbanks-Tanana Valley Are?Power and Energy Requirements Total Power Requirements;Anchorage-Cook Inlet Area and Fairbanks-Tanana Valley Area Combined. Existing (Fall-1978)Generating Capacities for Anchorage-Cook Inlet Area Existing (Fall-1978)Generating Capacities for Fairbanks-Tanana .Valley Area Anchorage-Cook Inlet Area Existing Capacity and Maximum Annual Plant Utilization (October 197&) Fairbanks-Tanana Valley Area Existing Capacity and Maximum Annual Plant Utilization (October 1978) Planned Additions for Railbelt Region (1979-1995) ,Transmission System Alternatives. Load/Resource Balance for Case 3:Medium Load Growth Scenario . Schedule of Plant Additions (Megawatts)Base Cases Without Interconnections 3.12 Schedule of Plant Additions (Megawatts)Cases With Interconnection Without Upper Susitna . 3.13 Schedule of Plant Additions -(Megawatts)Cases With Interconnection With Upper Susitna Coming On Line in 1994 2.1 3.1 3.2 3.3 4.1 Anchorage-Cock Inlet Area,Low Load Growth Scenario,Case 1, O~~Infl ation 78 4.2 4.3 4.4 Anchorage-Cook 5%,rnf1 ation Anchorage-Cook 0%Infl ati on . Anchorage-Cook 5%Inflation Inlet Area,Low Load Growth Scenario,Case 1, Inlet Area~Low Load Growth Scenario,Case 2 Inlet Area,Low Load Growth Scenario,Case 2,..' 79 80 81 4.5 4.6 4.7 Anchorage~Cook Inlet Area,Low Load Growth Scenario,Case 3, 0%Inflation. Anchorage-Cook Inlet Area,Low Load Growth Scenario,Case 3, 5%Inflation. Anchorage-Cook Inlet Area,Medium Load Growth Scenario,Case 1, 0%lnfl ati on 82 83 84 v; TABLES (contd) 4.8 Anchorage-Cook Inlet Area,Medium Load Growth Scenario,Case 1, 5%Inflation.85 4.9 Anchorage-Cook Inlet Area,Medium Load Growth Scenario,Case 2, 0%Inflation .86 4.10 Anchorage-Cook Inlet Area,Medium Load Growth Scenario,Case 2, 5%Infl ation .87 4.11 Anchorage-Cook Inlet Area,Medium Load Growth Scenario,Case 3, 0%Inflation 88 4.12 Anchorage-Cook Inlet Area,Medium Load Growth Scenario,Case 3, ,5%Infl ation 89 4.13 Anchorage-Cook Inlet Area,High Load Growth Scenario,Case 1, 0%Infl ation .90 4.14 Anchorage-Cook Inlet Area,High Load Growth Scenario,Case 1, 5%Inflation .91 4.15 Anchorage-Cook Inlet Area,High Load Growth Scenario,Case 2, 0%Infl ation .92 4.16 Anchorage-Cook Inlet Area,High Load Growth Scenario,Case 2, 5%Inflation .93 4.17 Anchorage-Cook Inlet Area,High Load Growth Scenario,Case 3, 0%Inflation 94 4.18 Anchorage-Cook Inlet Area,High Load Growth Scenario,Case 3, 5%Inflation 95 4.19 Fairbanks~Tanana Valley Area,Low Growth Scenario,Case 1, 0%Inflation 96 4.20 Fairbanks-Tanana Valley Area,Low Growth Scenario,Case 1, 5%Inflation.97 4.21 Fairbanks-Tanana Valley Area,Low Growth Scenario,Case 2, 0%Inflation.98 4.22 Fairbanks~Tanana Valley Area,Low Growth Scenario,Case 2, 5%Inflation.99 4.23 Fairbanks-Tanana Valley Area,Low Growth Scenario,Case 3, 0%rnfl ation .100 4.24 Fairbanks-Tanana Valley Area,Low Growth Scenario,Case 3, 5%Inf1 ation .101 4.25 Fairbanks-Tanana Valley Area,Medium Growth Scenario,Case 1, 0%Infl ation .102 4.26 Fairbanks-Tanana Valley Area,Medium Growth Scenario,Case 1, 5%Inflation.103 vii ......__....__------,---------L_..-----"F'I------------------- .~ 'I TABLES (contd) 4.27 Fairbanks-Tanana Valley Area,Medium Growth Scenario,Case 2,. 0%Inflation.104 4.28 Fairbanks-Tanana Valley Area,Medium Growth Scenario,Case 2, 5%Infl a tion ·105 4.29 Fairbanks-Tanana Valley Area,Medium Growth Scenario,Case 3, 0%Infl ation ·106 4.30 Fairbanks-Tanana Va 11 ey Area,Medium Growth Scenario,Case 3, 5%Infl atian ·107 4.31 Fairbanks-Tanana Valley Area,High Growth Scenario,Case 1, ·0%Inflation ·108 4.32 Fairbanks-Tanana Valley Area,High Growth Scenario,Case 1, 5%Infl ation '.109 .. 4.33 Fairbanks-Tanana Valley Area,High Growth Scenario,Case 2, 0%Inflation 110 4.34 Fairbanks-Tanana Valley Area,High Growth Scenario,Case 2, 5%Inflation 111 4.35 Fairbanks-Tanana Va 11 ey Area,High Growth Scenario,Case 3,~ 0%Inflation ·112 4.36 Fairbanks-Tanana Va 11 ey Area,High Growth Scenario,Case 3, 5:~Inflation ·113 viii LOAD/RESOURCE AND SYSTEM COST ANALYSIS FOR THE RAILBELT REGION OF ALASKA -1978-2010 Prepared fqr the Alaska Power Administration by Battell e Pacific Northwest Laboratories January 1979 1.0 INTRODUCTION The Alaska RaiTbelt region presents some unique attributes for considera- tion in future power system planning.The region currently consumes 83%of the State1s electric power and even the lower estimates of electrical load growth (5%~erannum)for the region are above the national average. The State,and particularly this reg10n,is a difficult one in which to forecast load growths.This difficulty results from the nature of the economic activity base being influenced by external forces such as oil and gas develop- ments and transportation systems with their cyclical tendency.Also,since the economic base is still not large,the injection of a competitively scaled industry such as major ~etroleum refinery or electrochemical industry can sig- nificantly perturb a forecast.• A major shift in the Alaskan Railbelt future power generating mode appears inevitable.The Cook Inlet Region's capacity is presently dominated by combus- tion turbines fired by currently low-cast natural gas;the Fairbanks-North Star Borough by a mix of coal-fired steam turbine generation and oil-fir'ed combus- tion turbines.The oil and gas based mode of generation,however,are highly exposed to inflationary pressures,external market forces,and Federal regula- to ry i nterven ti on. The Railbelt region,however,does have a number of options open in the future.These include: •Continued use of oil and gas in existing plants. •Increased coal based thermal generation both in the interior based on the Healy Coal Field and in the Cook Inlet Region based on several coal fields~including the very large reserves in the Beluga Region. •Development of the signiftcant hydroelectric potential.including Upper Susitna River and Bradley Lake. • A transmission intertie between the Cook Inlet and Fairbanks load centers is of obvious interest as a means of increasing rel1ability or alternately reducing additional generating capacity needed for reliability.Marketing of power from Upper Susitna projects will be dependent upon such an· intertie. Electric power generation by whatever means is a very capital intensive activity.Different forms of generation,however,have different levels of exposure to inflation and escalation and,cost comparisons on a straight S/kW .~ of installed capacity can be misleading.Thus a higher cost per kilowatt hydro-., electric project has this exposure largely limited to the time period during planning and construction.On the other hand,a fossil fueled plant faces rising fuel costs as well as operating and maintenance costs in the future. Regardless of these factors,all generation options are faced with long lead, times from decision to proceed to commercial operating date. The purpose of this report is to examine the probable timing of major generation and transmission investments and their impact on system power costs under a range of assumptions about power demands and inflation and escalation rates for the following general Railbelt power supply strategies: Case 1.All additional generating capacity assumed to be coal fired steam turbines without a transmission interconnection between the .8.nchorage- Cook Inlet area and the Fairbanks-Tanana Valley area load centers. Case 2.All additional generating capacity assumed to be coal fired steam turbines,including a transmission interconnection. Case 3.Additional capacity to include the Upper Susitna Project (including transmission intertie)plus additional coal as needed. The first step involved in estimating the cost of power from alternative generation and transmission system configurations is to perform a series of load/resource analyses.These analyses determine the schedule of major invest- ments based on assumptions about the load growth,the capac;ty and power produc- tion of the prospective generating facilities,and constraints as to when the facilities can come on line. The load/resource analyses provide information on the annual power produc- tion of the various types of generating plants.Once the annual plant utiliza- tionsare known,they can be used in conjunction ~ith estimates of annual system costs to calculate the annual cost of producing power from the facili- ties.Summing the annual cost for generation and transmission of each of the generating facilities gives a total cost for the entire system being analyzed. Dividing the total annual cost by the power produced gives an average annual cost of power for the entire system.By comparing the average annual power costs over the period of interest (1978-2010)the alternative configurations can be ranked based on the cost of power.All other things being equal,the system configuration producing power at the lowest cost should be selected as the most desirable system. The report was prepared on contract to the Alaska Power Administration (APA) as input to APA's power market analysis for the Upper Susitna Project.The APA furnished,and is responsible for,a11 data on power requirements,cost assump- tions,and certain key criteria for the study.The balance of the criteria were ~eveloped jointly by the APA and Battelle. Chapter 2 contains a bri ef summary of the results of the study.The loadl resource analyses are described in Chapter 3.Chapter 4 presents the methodol- ogy and results of the cash flow and power cost calculations.Appendix A con- tains the data used in the load/resource analyses.Appendix B contains a list- ing of the computer model (AEPMOD)used to perform the load/resource matching. The output of AEPMOD for the cases analyzed in this report are presented in Appendix C.Appendix 0 contains a listing of the model used to compute the cost of power and Appendix E contains some selected results of ECOST 4 model runs. 3 2.0 SUMMARY AND CONCLUSIONS Load/Resource Matchinq •Forecasted peak loads for the Anchorage/Cook Inlet and the Fairbanks/ Tanana Valley load centers have been matched with schedules of plant addi- tions for low,median,and 'high forecasted load growths.These were replicated for cases considering 1)continued separation of the load cen- ters.2)interconnection without development of Upper Susitna hydroelec- tric power,3)interconnection including development of the proposed Upper Susitna hydroelectric projects beginning in 1994. •Thermal generating capacity additions to the year 2010 were estimated as follows: Case 1:Without Interconnection and Upper Susitna Assumed Load Megawatts Growth Anchorage Fairbanks Total Low Median High 2600 4600 8200 471 871 1471 3071 5471 9671 Case 2:Interconnection wi thout Upper Sus itna Assumed Load Megawatts Growth Anchorage Fairbanks Total Case 3:Interconnection with Upper Susitna Assumed Load Megawatts Growth Anchorage Fairbanks Total Low Median High Low Median High 2200 4200 8200 1000 3000 6600 4 471 671 1271 171 371 1071 2671 4871 9471 1171 3371 7671 •Provision of the interconnection without Upper Susitna reduces thermal plant addition requirements by 200 to 600 MW over the period. •Interconnection with Upper Susitna reduces thermal plant addition require- ments by 1500 to 1800 MW depending on the assumed load growth. •Under the criteria used.the interconnection is called for in 1986. 1989. and 1994 for high.median;and low load growth cases.respectively.with- out Upper Susitna projects.With Upper Susitna.the corresponding dates are'1986,1989.and 1991. System Power Cost •F6r the Anchorage-Cook Inlet load center construction of the inter- connection reduces the cost of power compared to the case without an i nterconnecti on ~ •For the Anchorage~Cook Inlet area inclusion of the Upper Susitna project into the system generally raises the cost of power above the other cases during the first 2 to 4 years after the Watana Dam comes on line with results in lower power costs during the 1996-2010 time period. Q For the Fairbanks-Tanana Valley area construction of the interconnection again generally reduces the cost of power. •For the Fairbanks-Tanana Valley load center inclusion of the Upper Susitna project generally raises the cost of power above the case with the.inter- connection for about 2 years after the Watana Dam comes on line but,as with the Anchorage-Cook Inlet area,results in lower power costs during the 1996-2010 time period~ •Table 2.1 presents a comparison of the costs of power in the year 2005 for the cases evaluated in the report using the case without either the interconnection or the Upper Susitna projects (Case 1)as the base.The costs of power computed in Case 1 are compared to cases with the inter- connection (Case 2).and with Upper Susitna coming on line in 1994 (Case 3). As shown,the costs of power are reduced below the cost of power for Case 1 in but one case.This reduction varies from 4.3%to 39.3%depend- ing upon the situation. 5 ______________-,.-,-.------""'F'"-----.-r"'""....------.------------- TABLE 2.1.Comparison of Power Costs for Year 2005 Percent Change in Cost of Power Below Case 1 5%Inflation Anchorage Fairbanks High Median Low High Median Low Case 2 -4.3 -1 C.1 -12.2 +8.9 -9.6 -4.2 Case 3 -10.5 -30.3 -39.3 -8.9 -30.8 -26.3 6 3.0 LOAD/RESOURCE YScS The load/resource analysis is intended to match forecasted electric power.. requirements with appropriate generating capability additions.The analysis schedules new plant additions,keeps track of older plant retirements,and com- putes the loading of installed·capacity on a year-by-year basis over the period 1978 to 2010. The analysis schedules the additions to assure that both peak loads and energy requirements (including reserves)are met on a year-by-year basis with the least amount of installed capacity and with generating plants loaded in any preselected order,typically in ctcier of lowest to highest marginal power costs. A number of factors must be taken into account: 1.Forecasted loads in terms of peak power requirements in megawatts (MW)and annual energy requirements in millions of killowatt hours (MMkWh). 2.The stock of existing generating capacity by type,size,year of retirement, /'-..,and maximum allowable plant factor. 3.Desired reliability reserve margin to Pi J ide ~ outages,unforeseen delays in plant availabili t..J' of those anticipated. ''ince against forced ~r lOed qrowths in excess 4.Transmission and distribution losses. 5.Construction schedule constraints;i.e.,lead times necessary between unit selection and first power on line date. 6.Plant availability constraints based on type~Jnd age.(Thermal plants generally have lower availability at the start and end of their economic 1 He.) 7.Assumptions about the economic size of future generating plants in relation to the loads. 8.System configuration;i.e.,interconnections,alternative siting strategies. 7 -,.0_,....1AA....~_--------r- 3.1 ANALYSIS METHODOLOGY The load/resource matching is done on an annual basis.The Alaskan.elec- tric utility systems experience their annual peak load requirements during the winter months and resources must be available to meet these peak loads.During recent years the annua~load factor for Railbelt electrical demand has typi-, cally been about 46-50%.It is expected to remain in the range of 50-52% during the time horizon of this study.The existing and planned future gener- ating capacity in the Railbelt region is capable of operating at a capacity factor either equal to or greater than 50%.Because of this,the decision to add n~w capacity will usually be based on the need for capacity (kW)rather than energy (kWh).Thus in this analysis capacity additions are scheduled based on peak loads rather than upon average annual energy. The general approach to load/resource analysis is to summarize existing and planned gross resources for each year,adjust them downward for a reliabil- ity margin and for system transmission losses to arrive at net resources.If these net resources exceed the critical period load for the year being analyzed, plant additions are not called up and the analysis proceeds to the next year and is repeated~At some point,the net resources will not meet the forecasted peak loads and additional capacity must be added.Also,for each year,the energy generated by each class of plants (e.g.,hydl~O,steam turgine,combus- tion turbine,anD diesel is computed so that plant utilization factors are available for review and system energy costs can be developed.The stepwise calculations are continued to the end of the period being studies (2010). 3.2 ASSUMPTIONS 3.2.1 Forecasted Power and Energy Requirements The analyses are based on forecasts prepareo by the Alaska Pmver Adminis- tration for both the Anchorage-Cook Inlet and the Fairbanks-Tanana Valley areas. Probable high and low bounds were provided along with median forecasts.These are presented in Tables 3.1 through 3.3 and are shown graphically in Figures 3.1 through 3.3.In addi ti on to util ity loads,Anchorage-Cook In1 et forecasts include both national defense and industrial loads and the Fairbanks-Tanana Valley forecasts include national defense loads. 8 l!MW =Megawatts GWh =Gigawatt-hours (Equivalent to MMkWh =Millions of kilowatt-hours) Source:Alaska Power Administration,October 1978 9 10 TABLE 3.3.Total Power Requirements;<,rage-Cook Inlet Area and Fairbanks-Tanana Valley M·ca ::Jliibi ned PEAK pmJER 1977,/1980 1985 1990 1995 2000 2025 MW -MW MW MW MW MW ~~\~ TOTAL High 890 1,671 2,360 3,278 4,645 10,422 Median 650 829 1,162 1,592 2,134 2,852 4,796 Low 769 961 1,177 1,449 1,783 2,146 ANNUAL ENERGY , Gi'i:-'GWh GWh GWh GWh GWh GWh--- TOTAL High 3,928 7,636 10,684 14,844 20,935 47,054 Median 2,681 3,663 5,133 7,078 9,528 12,738 21,578 Low 3,391 4,256 5,219 6,430 7,890 9,630 l!~~W =Megawa tts GWh =Gigawatt-hours (Equivalent to MMkWh =Mil1i~ns of kilowatt-hours) Source:Alaska Power-Admi ni stra ti on,GeL._~ 11 FAIRBANKS-TANANA VALLEY AREA ANCHORAGE -COOK INLET AREA 200 L 3000 2000 6000 5000 . 4000 tn LOWI-- I--« $:« 0 1000u...! ~900 0 800<: 0 -l 700~«600wc.. 500 400 300 LOW 100-l..--__.....l-I.-:.:....-_.....l-__---J'--__.........__----'....L-__--'-' 1980 1985 1990 1995 2000 2005 2010 FIGURE 3.1.Railbelt Region Peak Loads 12 ~. z:10,000 o 9000 --I --I 8000 ~~7000 >-. r,,:)6000c::: l..t-I 3 5000 .....I <C ~4000 z <C 3000 2000 Anchorage-Cook Inlet Area Annual Energy 13 2005 20la 3000 .~... ~...1000 o 900 800 700 600 500 300 200 6000 5000 4000 ::2:-> (,:) c:: UJz UJ -J<: =:l 400zz <: 100 1..-__....L-__-.J-__---l..l.-__.....l-__~_____a..I 1980 1985 1990 1995 2000 200S 2010· ·.FIGURf 3.3.Fairbanks Area Annual Energy 14 The Alaska Power Administration data h'-o ::that approximately 80%of the Railbelt region loads are expected to be in :he Anchorage-Cook Inlet area. These loads have been interpreted as recognizing distribution losses. 3.2.2 Existing and Planned Generating Capacity The exi sting stock of gen~rating capacity for the Anchorage-Cook Inl et area and the Fairbanks-Tanana Valley area is presented in Tables 3.4 and 3.5,. .respectively. The.total existing capacities and maximum plant utilization .the various generating types for the Anchorage-Cook Inlet area and the Fairbanks-Tanana Valley area are ,:I~own in.Tables 3.6 and 3.7,respectively..--" The Toad/resource matchi ng analyses use these totals for the fi rst year of the analyses (1978-1979). Generating capacity additions can be specified to be added in'one of two ways_It can either be added i~a specified year or can be added when it is required to maintain adequate generating capacity.In the former case the generati ng units are added whether they are requi red or not.The pl anned addi- tions shown in Table 3.8 are brought on line ;"i the V"'O>I'"S specified.National defense generating units are assumed to be replaced_~:;am turbine generating units the same year as they are retired.(See Sectior 3.2.7 ~or 3 discussion of the units aded as required to maintain adequate generating capacity.) 3.2.3 Reserve Margin Utility systems invariably carry a reserve rnli~gin of generating and trans- mission capacity as insurance against loss of l"",-,c,unexpected .peak require- ments as a result of severe weather,load growths more rapid than anticipated, adverse:hydroelectric.conditions,and delays in the commercial operation of new generation_.The.most appropriate.reserve margin will vary from system to system depending on the nature of the loads and types of resources and special factors.Typically,a reserve capacity at peak of 20%is used nationally. However,this can vary to as low as T2%as is the present case for the Pacific Northwest with its predominance of reliable hydropower and interruptable loads. 15 TABLE 3.4.Existing (Fall 1978)Generating Capacities for Anchorage-Cook Inlet Area 1988 1993 1996 1995 1996 1996 1996 1983 1992 1998 NA 1982 1982 1984 1988 1992 1995 1995 Retirement Year 33,000 54,600 9,300 65,000 67,810 68,OOOCe) 32,200 8,370 17,860 18,000 16,500 S.c:C.To} S.C.C.T. R.C.C.T.* S.G.C.T. R.C.C.T. S.C-C.T. S.C.C.T. C.C. S.C.C.T. S.C.C.T. S.C.C.T. Hydro Berni ce Lake Bernice Lake Bernice Lake Cooper Lake ;Beluga Beluga Beluga Beluga Beluga Beluga Beluga Beluga ;~, Deisel Unit 1 Unit 2 Unit 3 Unit~4,. Unit 5. Unit 6 Type of Capacity Unit Reference/Name Location Generation (kW) ANCHORAGE MUNICIPAL LIGHT AND POWER (AML&P) Anchorage Diesel 2,200 Anchorage S.C.C.T.*15,130 Anchorage S.C.C.T.15,130 Anchorage S.C.C.T.18,650 Anchorage S.C.C.T.31,700 'Anchorage S.C~C.T.36,000 Anchorage C.C.16',500' Subtotal 137,500 (a) ;,'...::..:.:.:::.=:...:.:::;;.;.-==.:;~:..=..-:...=:...=..=.;...:..:.....:..:~(...,;;.C==-EA.;.L.) Tal keetna Di es e1 HOMER ELECTRIC ASSOCIATION (HEA) .Eng1 ish Bay Diesel S.T.* Subtotal MATANUSKA ELECTRIC ASSOCIATION 1993 1993 1985 1991 1987 1993 1993 1995 100 200 300(c) 7,000(d) 30,510 18,140 10,OOOCt) 449,.790 (MEA) Di esel S.C.C.T.~ S.C.C.T.I S.C.C.T. Diesel S.C.C.T. Port Graham. Homer' Homer Talkeetna. English Bay Homer'&Kenai e Combined Homer Combined Port Graham Combined 16 TABLE 3.4 (contd) Type of Unit Reference/Name Location Generation HOMER ELECTRIC ASSOCIATION (HEA) Capacity __(t~ (contd) Retirement ,Year Seldovia Combined Seldovia Diesel Subtotal SEWARD ELECTRIC SYSTEM (SES) Subtotal ALASKA POWER ADMINISTRATION Seward Combined Seward Diesel 1 ,500 9)100 3)000(b) 2,500 5,500 (APA) 1980 1985 1996 Ekl utna Ft.Ri chardson/ Emendorf Kenai Ek1 utna Hydro Subtotal NATIONAL DEFENSE S.T. Diesel Diesel Subtotal INDUSTRIAL ,S.C;C.T. TOTAL 30,000 30,000 40,500 7)300 2,000' 49)800 12,300(g) 685,290 NA 1991 1985' 1991 1988 J • 3. 4.r *S.C.C.T.-Simple Cycle Combustion Turbine R.C.C.T.-Regenerative Cycle Combustion Turbine S.T.-Steam Turbine C.C.-Combined Cycle 1a)Capacities for individual units are from sources 1 and 2.These sum to 118,810 kW.Total shown is from source 2. (b)Standby (c)Leased to CEA (d)Leased to HEA by Golden Valley Electric Assoc~"ion for 1977-1979. (e)Included in this study,but late 1978 plans are ~o defer 8etuga 8 until 1980 and double the capacity. (f)Nameplate capacity derated to 10,000 KW from 14,500 KW. (g)Recent data shows industrial load to be 25,000 KW rather than 12,300 KW. SOURCES: Electric Power in Alaska,1976-1995,ISER,University of Alaska, .pp.J.5.2-7.4,August 1976. 2.Alaska Electric Power Statistics 1960-1976,Alaska Power Administra- tion,pp.15-17,July 1977.' 1976 Power System Study,Chugach Electric Association,Inc.,Tippett and Gee,Dallas,TX,p.7,March 1976. Alaska Power Administration,August 1978. 17 TABLE 3.5.Existing (Fall '1978)Generating Capacities for Fairbanks-Tanana Val1ey Area Unit Reference Name Location Type Generation Capac;ty (kW) Year of Retirement FAIRBANKS MUNICIPAL UTILITIES SYSTEM (FMUS) Chena 2 Fairbanks S .T.2,000 1988 Chena 3 Fairbanks s.r.1,500 1988 Chena 1 Fairbanks S.T.5,000·1988 Chena 4 Fairbanks S.C.C.T.5,350 1983 Oi esel 1 Fairbanks Di esel 2,664 1988 Di~sel 2 Fairbanks Diesel 2,665 1988 Diesel 3 Fairbanks Diesel 2,665 1988· Chena 5 Fairbanks S.T.20,000 2005· .Chena 6 Fairbanks S.C.C.T.23,500 1996 Subtotal 65,345 GOLDEN VALLEY ELECTRIC ASSOCIATION (GVEA) Fairbanks Diesel 24,000 1984 Healy #1 Healy S.l.25,000 2002 Fai rbanks S.C.C.T.40,000 1992 Delta Di esel 500 1988 North Pale #1 North Pole S.C.C.T.70,000 1997 North Pale #2 North Pole S.C.C.T.70,000 1997 Subtotal 229,500 NATIONAL DEFENSE CombiJled CTear A.F.B.and Ft~Greely Ft:.vlai nwrig'ht and Eils.on,A.-F'~B."-' Diesel 14,000 1988 S.T.24,500 1995 S.L 32,000 (a)1990 Suhtotal 70,500 fa)5 MW pTantat Eilson A.F.B.installed in 1970 and old 1.5 MW plant -at Ft.Wai nwright were i nadvertant1y omitted. SOURCE; 1.Interior Alaska Energy Analysis Team,Final Report,June 1977. 2.Alaska Power Administration,August 1978. 18 TABLE 3.6.Anchorage-Cook Inlet Area Existing Capacity and Maximum Annual Plant Utilization (October 1978) Hydro Steam Electric.•Combustion Turbine Diesel Capacity (MW) 46.5 50.5 575.01 19.13 Plant Util ization (%) 50.0 75.0 50.0 15.0 TABLC 3.7.Fairbanks-Tfrnana Valley Area Existing Capacity and Maximum Annual Plant Utilization (October 1978) Hydro Steam Electric Combustion Turbine Di ese 1 Capacity (t~i~) o 110 208.9 46 19 Plant ,Utilization. (%) 50.0 75.0 50.0 10.0 . TABLE 3.8.Planned Additions for Railbelt Region (1979-1995) Unit Reference!Year of Name Installation Location Type of Generation Capacity (kW) Unit 7 Unit 6 ANCHORAGE MUNICIPAL LIGHT AND POWER (AML&P) 1979 Anchorage S.C.C.T. 1979 .Anchorage C.C. 65,OOO~~~ 16,500 GOLDEN VALLEY·ELECTRIC ASSOCIATION (GVEA) As Required "Healy S.T. Beluga #9 X-I Bern ice Lake #4 X-2 Berni ce .Lake #5 Healy #2 CHUGACH ELECTRIC ASSOCIATION 1979 Beluga 1980 1981 Bernice Lake 1982 . 1984 Bernice Lake (CEA) C.C. S.ex.!. S.C.C.L S.C.C.T. S.C.C.T. 32,200(C) 100,000 18,000 100,000 18,.000 / 100,000 Bradley Lake ALASKA POWER ADMINISTRATION (APA) 1985 Bradley Lake Hydro NATIONAL DEFENSE 1985 Ft.Ri cha rdson and Emendorf A.F.G.S.T. 1988 Fairbanks Combined S.T. 1990 Ft.Greely and Clear A.F.B.S.T. 1991 Ft.Ri cha rdson and Ernendorf A.F.B.S.T., 1995 Ft.Greely and Clean A.F.B .S.T. 70,000 T,300 14,000 32,000 42,500 24,500 . (a)Unit #7 is a simple cycle combustion turbine unit which also supplies exhaust heat to Unit-#6. (b)This increase.reflects the increase in capacity 'resulting from the addition of Unit:#T.. (e)Beluga.#9 is.a steam unit addition to Beluga #7 {converts these to a 100 MW combined cycle unit}. SOURCES: 1.1976 Power System Study,Chugach Electric Association,Inc.,Tippett and Gee,Dallas,TX,pp.7 and 25,March 1976. 2.Electric Power in Alaska,1976-1995,ISER,University of Alaska, pp.J.5.2-7.4,August 1976. 3.Alaska Power Administration,August 1978. ~o Since a reserve margin effectively increases the amount of generating r--ca'.Hyin place at any given time~it does contribute costs to the system. Therefore~an excessive reserve margin is to be avoided while at the ~ame time recognizing that an inadequate reserve margin could,on outage,result in a wi de va ri ety of sad a1 cos ts. For the purposes of this study,the Alaska Power Administration has suggested that the analysis be based 6n reserve margins of 25%and 20%for non- interconnected load centers and the interconnected systems~respectively.In the future,a more refined analysis of the desired reserve margin appears' warranted. 3.2.4 Transmission Losses Transmission losses must be added to forecasts of peak and energy loads to establish net capacity and energy at the plant substations.The Alaska Power Administration expects losses as follows: % Capacity Energy 5 1.5 The results of the load/resource analysis are thus in net deliverable capacity and energy and do nc~include energy and capacity required for internal plant operations. The above losses are reasonably applicable for the independent operation. of the load centers~for interconnected systems including the Upper Susitna project and for configurations with future generation capacity additions being distributed proportionally near the load centers.In the case of interconnec- tion without Upper Susitna and with a tendency to centralize Rai1be1t thermal generation,the transmission losses may be considerably higher as discussed later in Section 3.2.8. 3.2.5 Construct~on Schedule Constraints Due to the lead times necessary for the permit processes and construction, generating unit and site selection must take place a number of years in advance 21 -------------,-~~-------r"'--,-- of the forecasted date when the units commercial operation will be required. For coal-fired thermal plants,the Pacific Northwest Utilities Conference Committee estimates a 62 month (5.2 years)period from final site selection to commercial operation for plants in the 500 MW and higher range based on recent U.S.experience. Although individual thermal plant capacities appropriate to Alaska's loads are somewhat smaller and may require less field erection work,the construction season is shorter and the 5 to 6 year scheduling period appears reasonable. For the potential Upper Susitna hydroelectric projects,the scale of effort is more demanding and increased site evaluation is necessary.Current understanding is that the Watana Dam and power plant could be brought to commer- cial operation by 1994,followed by Devil Canyon no sooner than 1998. A transmission interconnecti.on between Anchorage-Cook Inlet and Fairbanks- Tanana"Valley could be brought into service prior to completion of Watana, possibly as early as 1986. The load/resource analysis technology recognizes the above schedule con-~ straints by not allowing callup of new generation or transmission'capacity that could not be made available. 3.2.6 Plant Availability Constraints Generating and transmission plant availability can be expressed in terms of maximum and minimum plant utilization factors (PUF).These factors are primarily dependent upon plant type and plant age.For purposes of this analy- sis we have assumed the following economic facility lifetimes after which the facility is retired from service.(l) Years Coal-Fired Thermal Generation 35 Oil-Fired Steam Generation 35 Gas-Fired Combustion Turbine 20 Oil-Fired Combustion Turbine 20 Hydroelectric Generation 50 (1)See Tables 3.4 and 3.5 for dates of expected retirements for existing systems. 22 Due to the nature of the system,some plants could be retired from service P17~to the expiration of their economic life.In actual practice,however, it is expected that utilities may elect to retain the units on standby.In order to assure their avai1ability in emergencies,the utilities vlil1 periodi- cally operate the \.unitsto make sure they are in working condi tion. Experience has shown that large thermal plants experience a learning curve during the first few ye'ars of operation as IIbugs il are worked out.Once past this period they reach a maxiTliumthat aliows for scheduled maintenance and replacement conducted during the off-peak season.Toward the end of the economic life,increased frequency and duration of outages for maintenance usually occur and the maximum plant util ization facto-r decl i.f:1es.For purposes of this analysis,we have assumed constraints on the maximum PUF for new coal- fired steam electric plants as shown in Figure 3.4. 80 70 60a::o I-u ~50 z:o..... ~40N..... -I..... I- :::l 30 L- Z: ~ -I 0.20 10 o 105a 15 20 25 30 35 PLANT AGE (YEARS) FIGURE 3.4.Plant Utilization Factor versus Plant Age 23 -----.-.'----~i _,~------nv_m _ Other types of generating capacity are allowed to rUll at their maximum· PUF frornthe start ..For ne\v capacity and most types of existing capacity,the following maximum PUFs are assumed: Maximum Plant Utilization (%) Hydro 50.0 Steam Electric 75.0 Combustion Turbine 50.0 Diesel 10.0 Hydroelectric generation systems,as a result of their storage ability and conservative ratings,can make additional power available for ·peaking and it is assumed they can be scheduled at 115%of design capacity for this service. As pointed out earlier in Section 3.1,the p~ak demand during the winter usually determines the amount of generating capacity required rather than the annual ~nergy.Because of this,some generating units are utilized at less than their maximum annual plant utilization factors.The decision as to·which units should not be loaded is usually based on the margin cost of operating the facilities.In this analysis it is assumed that diesel capacity has the highest margin operating cost followed by combustion turbines,steam turbines and hydroelectric capacity in that order.It is assumed that diesel PUFs can be reduced to O~O while the PUFs for combustion turbine and steam electric capacity is not allowed to go below 10%. Transmission plant availability is generally not as schedule constrained as are generating p~ants with their long lead times.For purposes of these analyses,the interconnection between the Anchorage-Cook Inlet area and the Fairbanks-Tanana Valley area will be provided 3 years before the completion of the Watana dam or when the Healy 1 (existing 25 MW)and Healy 2 (planned 100 MW net)plants become fully loaded.whichever occurs first.(2)This assump~ion in effect places oil-fired plants serving the area on standby after that date. (2)It wilT probably be desirable to provide at least a portion of the inter- connection prior to Watana date on-line as a source of power for construction. 24 ~1 ~.• 1.2.7 Economic Generating Unit Size The selection of optimum generating size c~n be a complex process involv- ing uncertain assumptions regarding probability of future load growth paths, desirability of sizing individual units in comp'1rable sizes and types for each of maintenance,assuring that system reliabili+y is not penalized by addition of too large a single unit,smoothing of construction schedules for possible multiunit plants,and maintaining as small as possible departure from the desired rel iability margin.A fun optimization does not appear warranted thi's stage and is beyond the scope of this analysis. Thus for the purposes of thi s <:"':udy,the fi rs t six coa I-fi red steam electric.plants in the Fairbanks ;Inana Valley area are assumed to be 100:MW units.Any additional units are assumed to be 200 MW units.In the Anchorage-, Cook Inlet area the first five coal-fired steam electric plants are assumed to be.200 MW units,while any additional plants are assumed to be 400 MW units. These size ranges,though probably not exact optimums,appear reasonable block sizes for introduction and typically become fully loaded at about 10%of plant ;r-:-1 He. 3.3 SYSTtM CONFIGURATIONS:DEFINITION OF CASES ANALYZED 3.3.1 Cas e -!Without Interconnection and Without Upper Susitna Project The base case consists of power supply to the Anchorage-Cook Inlet and Fairbanks-Tanana Valley on a noninterconnected basis.In this instance,no power is available from the Upper Susitna project. Future capacity additions.for the Anchorage-Cook Inl et load center are assumed to be.near-mine,..mouth coal-fired units located on the ..../est side of Cook Inlet-with a,nominal 50-mile transmission distance using two 345 kV circuits with a capacit.:r of 1600 MW.Capital cost of this transmission system is $228 million in October 1978 prices~ Further capacity additions for the Fai rbanks-Tanana Vall ey load center are assumed to be coal-fired units with a nominal lOO-mile transmission distance. The'Healy site is used as a proxy recognizing,however,that the Prevention of Significant Deterioration (PSD)provisions of the Clean Air Act may preclude 25 Advantages a)Lower capital and operating costs for generation. b}Econom;es of scale can be achi eved; c)Siting problems in the interior may be avoided. Disadvantages a)Higher transmission losses (and costs)are incurred for the fractipn of power fl owi ng to the Fa i rbanks-Tanana Va 11 ey load center.These costs may cancel out savings from the advantages. b}The latter area becomes strongly dependent upon reliability of the transmission system--possibly to the point of requiring a second cir cui t or maintenance of additional standby combustion turbine capacity. c}Any actverse.environmental effects are borne by a single area notneces sariTy bene.fiti ng in proporti on. Z.Coal Plants Sited in Proportion to Relative Load Growth {Distributed Siti!!g}. 3.3.2 Case 2:With Interconnection,Without Upper Susitna Project In the case of an interconnected system without;the Upper Susitna project· ._.'c,·i<"J C:E;X~~~0~~1 and all new capacity coal fired,the load/r~source analysis is not as straight:- forwar~.in that it is not readily apparent what strategy for siting plants shoul d be foll owed.Two primary options are apparent: 1..All coal plants sited ata single location{T)(Concentrated Siting)., the siting of additional plants beyond the planned Healy 2 100 MW unit.A 230 kV single circuit will transmit up to 400 MW and a 230 kV double c.ircuit, 800 MW.Capital costs are $44 million and $70 million,respectively. Table 3.9 provides a summary of the transmission system alternatives.A map of the Railbelt region showing the Watana and Devil Canyon dam sites~a possible route for the interconnection,and the Beluga area is presented in Figure 3.5. (1)For the purposes of this analysis~mine~mouth location at Beluga is used-as ~~, a proxy. 26 ')) TAIlLE 3.9.Transrni ssion Sy~tem AlterrHlti V~$(l) Approx . Capad ty .Capa~i ty Investment Location Ci rcul t t'lW loss,%Cost --.J!1r1 $/kW--,., Isolated Load Centers He~ly -Fairpank$ 100 mil es 230 kV Single·400 6 44 110 230 kV Double 800 6 70 88 Beluga -AnchQrage 100 mil es 345 kV Single 400 114 285 800 114 142 N Two 345 kV Single 800 228 285 "-.j 1600 228 142 Interconnected WithoutSusitna Anchorage -He~lY 200 miles 230 kV Single 200 6 .88 293 300 8 88 225 345 kV Single 400 3 228 570 560 5 228 407 Interconnection With Susitna 1573(2)5·471 .(299 ) (1)Source:Alaska power Administrat on (2)Actual peak power availabilHy co ld be about 15%higher Qr 18Q8 MW, ALASKA POWe:R ADMINISTRATION o SCALE: / iOOIWiles FIGURE 3.5.Railbelt Region ShO\'ling the Watana and Devil Canyon Damsites,a Possible Route for the Interconnection, and the Beluga Area 28 Advantages Siting problems rel ated tne latter a.rea. a) b)Generation costs in the Fairbanks-Tanana·Valley a)The interconnection becomes lightly loaded,thus reducing transmission losses to some degree although charging losses would continue. b)Transmi S5 i on i nterconnecti on rel i abil ity dependence is reduced as the intertie assumes more o.f a capacity reserve characteristic. c)Environmental burdens are distributed,possibly with more equity. In this report.coal plants are assumed to be sited in proportion to the relative,load growths of the two load centers.As with Case 1,additional coal-fired generating units are sited at Beluga to serve the Anchorage-Cook Inlet area and at HealyjNenana to serve the Fairbanks-Tanana Valley areas. The transmission interconnection is used for capacity reserve allowing the reserve fi1'i.rgin for both load centers to be reduced from 25%to 20%(see Section 3.2.3 Under this scenario there is no net energy transfer during any single year.If one load center is low on capacity the other load center provides the additional capacity required assuming it has a surplus.If no surplus exists the original load center must add capacity. The interconnection is assumed to be brought on line in the same year as the Healy 2 coaT plant becomes .fully loaded and new generating capacity would be:required in the Fairbanks-Tanana Vaney area.Addition of the interconnec- tion allows the.Fairbanks-Tanana,Vaney area to ge.t capacity reserve from the: Anchorage-Cook InTet Area.This allows the Fairbanks area to postpone the construction of additional capacity by 2 to 6 years depending upon the scenario. In the high 10acLgrowth case the interconnection would be completed in 1986,in the medium load growth case it would come on line in 1989,and in the r<"...;I;,oW load growth case it would come on line in 1994-.In all cases 45%of the cost of the interconnection is assigned to the Fairbanks-Tanana Valley load center. --------------~----- 3.3.3 Case 3:Interconnected'System With Upper Susitna Project In addition to the interconnection described in the previous section, Case 3 includes two hydroelectric generating facilities.The Watana dam is schedul ed to come on 1 ine in 1994.The date';s assumed to be the same for all three load growth scenarios.The Devil Canyon dam is assumed to come on line. as soon as required following 1994 but nat before 1998.It is assumed it would take at least 4 years to complete the Devil Canyon dam following comple- tion of the Watana dam.It turns aut that the Devil Canyon dam is required in 1998 in the medium of high load growth scenarios but not until 1999 in the low load growth scenario, Because of reservoir fiTling requirements it is assumed that both dam~. will take 2 y~ars to reach full capacity and power output.The capacities,«.:i/i:\:;j:?~ power production and plant utilization factors for the two dams 'are show below . .Watana Capacity Energy Util i za ti on Year (MW)(MMkWh)(%) 703 3080 50.0 2+795 3480 50.0 Devil Canyon 1 689 3020 50.0 2~778 3410 50.0 For the medium and high load growth the transmission interconnection~is assumed to come on line in 1989 and 1986 respectiveTy~the same years as for case:.2_In the low load growth scenario the interconnection comes on Tine in 1991 rather-than 1994.This earlier cempl etion date wiTl anow the Watana dam construction site to besuppTied with power from either the Anchorage-Cook Inlet area or the Fairbanks-Tanana Valley area. The power output of the two dams is divided between the two load centers in proportion to the;r relative energy consumption in 1994.This resul ts in the percentage divisions shown below. 30 !,Load Growth ,Scenario Anchorage- Cook Inl et Fairbanks- Tanana Valley Low Medium High 80%' 81% 84% 20% 19% 16% 3.4 RESULTS OF LOAD/RESOURCE ANALYSES An additional generating capacity beyond utility plans assumed to be coal-fired steam turbines including a transmission interconnection. An additional generating capacity beyond utility plans assumed to be coal-fired steam turbines without a transmission interconnection between the Anchorage-Cook fnlet area and the Fairbanks-Tanana Valley . .area load centers. Case 1 Case 2 Using the methodology outlined in Section 3.1 and the assumptions explained tnSection 3.2,a series of load/resource analyses were As poi.nted out earlier,three basic cases were evaluated: Case 3 All additional generating capacity beyond util ity plans assumed to be coal-fired steam turbines but including the Upper'Susitna project (in:1uding a transmission intertie)coming on line in 1994. For each ",f these three cases.Three load growth scenarios (low,medium and high)are evaluated resulting in a total of nine load/resource.analyses. The assumptions discussed in this chapter are incorporated in a computer model called AEPMOD.The output of AEPMOD for Case 3 assuming the medium load growth scenario is presented in Table 3.10.The results of an nine cases,are. presented in Appendix c~The AEPMOD computer code is presented in Appendix B and the data base necessary to make the runs is presented in Appendix A. The capacity additions called up in the various cases are presented in Tables 3.11,3.12 and.3.13 . .The results of the runs are summarized in Figures 3.6 through 3.11. """-I 31 '- PEAK --PEAK LOAO/G£N£~ATIM~CAPACITY ~tYUIR~~ENTS(MEGA~ATTS) Io'f'llF --MAX1l'~UM PLA>j1 liT LLIZATlON FACTOR "'!"til'-ACTuAL PLA;~l \JTLLLZATlOIII fACTOtj ENERGY --GEN~~~TION/.N~U.L EWEKGY KEQUI~tMENTS{MILLI0N~OF KILu~ATT-HUU~~) 32 'TABLE 3.10 • ...tA:~.I"~.I"'S FAl~8ANA5 C~Se:2 --~EaIUM LOAO GROWTH Wre.~11t n.R:1'1"0. NOfES:UtC.o.191~~I U.5.-I~'.' (contd) C R 1 rIC A l.~ERII)D 1 1"'>l-1'I7"i 1 1 '17'1-1 '..Iv 1 1~~~-1"81 1 "F.A~MPUF M'uF E~.ERG(1 "€U ,",puF APuF ENERGY 1 f';:AK '""uF A"uF Ei\;Etlb( 1------·._-.---.1------------.-1------_.------ ---------------/1 I i-:E\:iiLlrJ.it~~N rs I 11:1'1.80/;.I 1'l7.!Ie2.I 20'l.'He. ---------------1 ....I I "'1:~nu ..CF.5 /I.I f:11;,r 1'.(0 I I I "Yul<ll 1 o..50 .50 O.I O..511 .50 U.1 O..50 .50 0_. :;rl:.A',,/ELEC I 110.,1'5 •co 033.I 110..7~.72 b'l~.I 1\0 •.7':>.1 ~7c!3. Cu·Mo.rl'~o [i..E.I 209.•50 .10 l!l~.I .:!09 •..~O •10 \llS_I 20'1 •.50 .11 207 • UllO~El.I Qa_.10 .00 il.I Qo..10 .uo U.I II;'..111 .110 <I.• //I TIl r AI-I 305.II 1"•.I 305.<175.I 31>5.'l3u. 1 I I AlJUITI'1.'.S I I I ';(UII'j I I I .'Hi·M/Ft.£C I I I c.(J.;~..TtlRoINE I I I :;n.SEL I I I I I I HET l"ii~'f:'.TS I I I t'l'fi,iRi,J I I I ::'IL":~/r:LEr::I I I co ...,TIl"'';H.F f I I llIE::.EL I I I f I I ---------------/I I 10 ..05:;fiE 5fJ,jWC E 5 I 30':\•.all>.I 305.,il7'S .'I 30'.:l.930 •. I I I CA;.o "ts."Al<.GIrU o.'l>lJ I O.Ii'.:l2 I Q.1QII r'"I I I ';E:iE"lJ€.RE').I QQ.I 1I'l.I 52. I I I L[j:'S~.::'I ".12.I 10.I j •.I 10.1 ~. I I I "Ei kJ;:SDUl'lCE5 I .HlI.80tl./301<•BoO!.I 302.91b. I I I i ;I.·.~FE"EO I u.I O.I O. I I I I I , SUwPL.uS I 12b.ll.I 10'1_O.I 93.O. PEAl<Pf:"",LO"U/GEN~tlAr!I;G CAPAC t TT ~E~UlwEMENT5(MEGA~ArTS) ,~II'tIF MAllMUM i'L.ANr UTlLHATIUN FACTUR AI-UF ACTUAl."'LANT lJ IILl ZA HUN FAcrojoj ENERGY --GEN~~ATION/.NNUAI.EI~EFtGY kEuuIHEHENT5(MILLIDNS OF l(IL.0 1'1 A TT -HOURS) 33 TABLE 3.10.(contd) Af<f":Ar.C"O"A ..e: ANr."nf<Af.1'c ..:n:<I --"EIJ!I)'"LOA{J GIlII"T"~ I'.rEII r I~TE ..II :1'1'10.I "OTES:D~C.b,1'176 ,0 U.~.-l'j'l'l. C >l I T I C A L.?..>l I 1.1 lj---------------_._--------------------------------------------'--.._------------------_._---- /ICJ ..l-l'18~/l'Itl~-lCJa3 I 1.'1<13-1 CJllol /PEA~,"'PuF APuF E....€>lG·Y /PEA ..."'''tJF A..uF EfoC:>lGY I PEAK ,"PUF A"UF ENF.>lGJ/--------'------/--------._----1---------------------------1 /I "EIJU.J.lE ~.i.T3 /741 •3~81./7'15.3'>cl./lISO..311l1 • ---------------1 // itE~Ou~CES /.// Exr:>Tl(;',/// ';Y;.I>10 /'53..~O •50 20il •/5~..50 .50 cOli.I 53..50 .50 20"• STii"IIEI.EC I Sl..7'3 •75 ~32 •/51..•75 .75 H2.I 251..TS .4<'123. CUH~.rll""lN€/7~'1..:'/l •jCJ a71 "•/1l07..50 •.sc aasu./1l'l1..50 .J5 cD';I.~ UI!:.SEL I lr..15 .00 (I./17..1'>.00 0./l'5..15 .00 O. /// TorA\.I '110.3251./Q28.2/85./1210.31117. /// 100111'"),,5 I I / "YIJI",/// SH.',~/fL~C I /200..7'>.<21l 350.I C'lhd.rU>I';I PI!;:/1tl..50 .50 19./tOo..50 .5.0 438./ ,vll:SEI.I //..../// "E T I III:"E III TS /// rl'rtJIoit)/// ~TI:A"'/i:.l.EC /// co ....~.rUjo("INt://15..00 .00 O./6..00 .DO O. ulESEL //2..00 .00 O./•///\---------------/// (.~lJs!>;;EsnUHCEs,(928.3~311./1210."35H./1<202.31111. /// CAP "1::5.:-IARG l:i/1j.25~/0.523 /0.41'1 /// ...€:.Ei<VE·...E.u./~H~./19'1./au • /// I..IJ5St.S I '3.1.4'1./411.51./41.1)0. /// '.fl PlE.SOUl/eE5 I TO.,.leU./972.35e1../'147.,S7bl. /// TRAfoSFE",Eli I -~I Q.I O. /// J // 5 .....,.I..U~1 -3';.O./117 •O./'II.II. ~EAK PEAK 1..0AU/G~NE~ATING CAPACITY iolE~u!We.~e.NTS(MEGA"ATTS] kPIiF MAXIMuM P1....NT UT!LIZAIIOI'l FACillW APlJf ACTUAl."LANf U1ILlZATtiJI'<FACTU", EHER!;"--GU"""A TIUIIlIANNUAl.,.U;EWGY kEIJUIREHl;:N fS (~II,I.IU;'lS OF K lLO.....TT-...OUw$) 34 PEAK Pl:.u LOALl/GEN,,;:U Tl~G-C-APAC-{I f -io/""UIWl:.;~i:IH:;.(...eGA .....-r TSJ- M~VF MAX!~UM P~A~T ~rIL1ZATION FACTO>! A~uF ACTuiL PLANT UTILIZATION FACTOio/ Ek£wGY --GtNt~ATION/ANi'UAL £~tftGl ~EUU!>!lMtNI5(MILL10~S OF KILowATT-~uu~~J 35 -------------------,-------'------~ TABLE 3.10.(contd) .~<:~:""CHOI/AGE I~."c"o".,,<:CA[>l:.:a --"""luM L.IJAU G~UWTH I,'dEIH H.tf..tR:I 'I'll). /iOTES:OfC.b.1'176 "I U.5.-19'l4. C II I T I C A L.P E Ij I 0 [) --------.------------------------~-------------.-----------------------------------------I 19<14-19015 I l'la~-1'l8b I 1'ld&-I 'ill 11PEA,(HPuF APuF EN£~i;y I PEAK H"UF'APuF EN£IIGY I PE4K H'-Ill"AI'uF E"~EIlr,y 1-------_._-_.--1------.------1--------.----- ---------------1 I I "f'lIJ l~t."E,.rs I '10".4001.I Hb.4329.I 10'1<1.IIb57. ---------------1 I I ~E,;("J ..CE S I I I tq::'II'li.I I I Ii v lJ'ct}I 'i$.•~O .50 i!1I11.I 5~•.:;11 .~o 204.I 13li..5U .50 510. ~TEA"tEl,.E C I ~.';I ••/5 .53'11104.I a',H..75 •1>4 I"U5 •t '1';<:1..75 .:;0 22':1'1 • CO;·l"•.TllHI;tr.E I ~I>j.•~o •.)'1 21>15.1 ~Hlt,..51l .28 2111,.I e5';..511 .~&1956 • t11~5EI.t 1'5..15 .1)0 I).I IS..15 •()(I I).I 5..IS .110 I)• I I I 10rAI.I 12Q2.~,*1l2.I 1205.37211.I lli52.'1721. I I I Avli IT!0,,1 I I I HYLJkl!I I !II..~o •50 307 •t STl:.AM/fLl::C I I 201.•75 .20 31>3 •I co",,.:rulIt!WE I 1>1..';0 ,.50 79.I I D H SEl.I I I I I t ~t.T PIE','€;"r S t I I I1YU"O I I t :.J Ii:Aj:,.L/E.LiC I I t CO"'~.ru~"rr'E t 15..00 .1I0 II.I 31..110 .QO 1I.t uIESEL.I t 10..00 .00 O.t //I ---------------/// (olIOS;,"'e;S!lU~l:fSI 12GS.40&1.I 1452'_4394./l'lsa.4127. t /I CAl'"e:s •.~ARG 11<1 0.353 I O.lI811 /G.3as I I / ~ESF."w€.j.(E:~./22b.I 2l14./2b2. //I LOSSeS t ll~.b/J •I ~q.&5.I 52.10. ///~,I.e i "e.SOuI{CES /'Hli.lI00t./11 Sq.4329./lljd.4b51. I I / iR ..hSFEREil I 1>.I G'.,I Il. I // I I 1 SuRFLuS I 30.o.I 183.Q./90.II. PEAK PI:A"L.O.O/GENERA [lNGC"PAC I TV ~El.IlJl11E"'€fj·TS (I<'E'GA'"TT::l1 MPllF MAlllMu~PLAi.,UIILIZAOt.N FACiUII ..PIIF ACTUAL I'I.ANf uTIL.HAnONh"fi;'f~· ENl:RGY --GENEiUTlON/4"HUAL ENERGYllEOUlilE1'ti'.NTS{Mll.LIONS OF ~ILo ....n-I1IlU~_ 36 TABLE 3.10.(contd) I"'E A;F A I"IlAtjl<~ FAIk01Ar."S CASt:.2 --1'lEDIUM 1.0AD GRl".TM INTEr/TIE rEA":!940. NiJH.S:OfC.o.197il "I U.S.-19'l1l. C R I 'T'1 C A L ~E "I U 0----_..._---.------------...---------------------------------------------~------------------- I 1'1<l4-1'1!l~I I 'H'~-I'l<l"J 1"~t>-1'I,,1 I PEAl<MPUF APuF fNEiH,Y I P!;.AK "PUI'AI'I;F ENERGy I 1'£101<1'110'1;1'"APuF c;''''f~~'f 1-------------1------.--.-...--J------------- ---------------1 I J "i::o;UI"'t:."fAfS I 258.1132.I 272.11'13.J 2<1&.12,4. ---------------1 I I "'E~;Jd~CES.I I I L<l~r PH.//I Hr"iolu J u..~O .~o u.I (I..5~.5Q 0.I u..:.u .:'0 0. :>leA'~/EI.EC I llO..75 ./5·72!..I HO..7S •75 123.I 21u •.7S .55 101<1. CO'-d.TufllHNE I 2~4..50 .24 "20.I 2(,4..50 •teo 313.I 20"..50 .1 ~c'H. li1fSe.1.I 46..10 .00 O.I :.!l.• I \I .00 0.I <12..10 .tlO U. I I I IflTAI.I 300.114'1.I 330 •.1030.I 43&.1273. I I I l!JUI r 10,'5 /I I nYu":,I I I :'ltA ./ELEC /I 100..7~•.20 17.,•I CU-·Ui.fUf.l1-i I HE I I I DIESEl.I I I I I I ,,£11kE"'I:...r5 I I I rifl"jt:C'tj 1 I 1 STEAHELEC /I I .:0'.01.ruiolu I:,E I I 1 UH.;;"1.I 2'1..00 .00 0.-.I I /I I ---------------1 I I ~RO~~IoIE:>OU"CE~/.531>•.11<19.I''131>•.1211./'130.l.e1J. /I I ColI'wE:;..URI;lit/(J.300 I o ./Jv l I v.523r'./I I 'lESERVE MErl •.I "5.I bil.I 72. /I I ,-OSSES I l.5.17.I 1'1.1 ~./14.I II. I I / "'€T So:ESillJi<CES /~58.1132.I 35'1.11 'i3./350.1<1511. I I I .OUt·I:>F€"t:1J /0 •.I U.I O. I I I I I 1 SURPl.US I u.0.I Si!.0.I bll.tI. PEAK Mll>uF ~I'UI' E:.fItGY P~AK LOAO/GEN£~.lTl~G C~PACITY ItEQuIHE~INTS{MES.lhATTS) M.~IMUM PLANT UTILIZArIUN FACTO~ ACTUAL ~L.NT uTILIZArlUN FAC1U~ --G~NtRATlaN/AHNUAL ENEHGY HEQUIHI~~NT5(~lLLIONS OF KtLu~ATT-"OUHSl 37 TABLE 3.10. ~~EA:A.C~OkA'E· ANC~*~bl CAS~:~--MEUIUM LUAU G~owTH I~TEHTIE YEAR:l'l~U. WUTES:otC.b.197~~I U.S.-19'l'l. (contd) C k 1 rIC ...L P E fj 100 ----------------------_...--------------------------------------------------------------- I 19i:l7-1'l88 1'.188-1989 1 j'ld'i-I'lq" 1 I'~A~""til'A~U"ENEItGl 1041"1)1'APIlF "NlOlitH J ?\:.h MPUF ...iOUF C.'l~"t,;Y1------"--------_.-------.---1-------------- ---------------1 / "t.'JlH~E"ENrS I I 1.i!1k.'1985.1l9c!.~.H 3./1.i!1I1i.5"41 •. -------------/I ,IlE;;Ou.cCE5 I I E~1::1 II.;'""/. "·YOl<,,,,I~I1.1311.:.~'}.sa SlQ.J 13'1..~() ::iJtA"t/i:l.EC F 45/1 •.&43.•7~.~8 32S".I ,,43 •.75/'C Q',.loi·.1"11 ..os £lIE /"S'='.855.·.Su·.23 1,,28.{791..':lu,.".U:S£!;../-5'.5.,·.15 .00·II.I ~'-.15 I I lOU,-I 53'B.I 1573.,I ~ul>1T 1Uus I 1 rtTr..I1G '1 I :>TI:.A:~/I:L£C,I I ell.....II Il<K ltl£./r I1f':'S!1-.I I I I ;/0.Tll<E;'1Erlt:;I r t't't1J'ciJ I I STc:....,/EUC I 15..,,0'.00'.0.,.I CO"';.Tll""INE I &4_.00 .00 0 •.I uH.St~,J /.J---------------1 I ;r,IlUS.,>lESIJIlItCES/Ibn.5QbO'••1573.,53'13.1 1573. // CAP I<e5.,i'lA;,GINI CJ ...loc-0.320 I 0.245 /I ,<ei:lE"'o'e '''Et.•.I 26 4'._.298 ••1 253. I I .LO:iSfS I S&.7S.,bU •.50 •.I b3.~.,. I I ,jET "IEsouIolCES I 1301.ll'leS.,.121b.53U.1 12~7.5&'11. // TR ...,,:;FERf.:J I 0'_ll •.I 7. /I I I SUi/PLUS /1~1..:I •.2".G•/Q.G. PEAK P~A~LOAO/GENE>lAT!NG CAPACITY liE~oIREME~TS(MeGAwArT51 MPUF --MAXIMuM PLAWT UTILIZATION FACTOR ...PIlF --A'TUAL Pl.ANT UTILllAT10Jli FACTul< (l'j(ltGY --Gc."~R·ArzO"'/ANr.UAL.E"Ehin ~eQuIHEMENTS(M11.1.!ONS OF KILOwArT-ttOUi/SI &$ 38 TABLE 3.10.(contd) AHEA~FAr-<IlAN"S FAtHR"J><"S CASE:2 --MEDIUM LO"O GROOilTW • r,~TE.1oI1 II:TEA~:1'1'10 •. ~uTES:O~C.c.1~/b ~I U.5.-l9'/4. C R I TIC A L.?E Il 100 o. ENEioI(il l'H19-l99il ",PuF VuF I ENEIlGl 1 PEA'"--------1------ I 1.UI>.I I I".'"/ J I / /. 1312 •.•I I I I' I I I I· I I II.I I 0 •.I,. I 1397..I .'4 \'h.. I I 1I •.!1T I I b&.· I 21 •.I lb •. I U7b.I .D7. J I -1."... I I Q ..I .!.. .OQ.:.00 19l:ld-l9l:l'l MPuF APIJi' 0 .. ttl,. 325. o. 1$35 •. 1315 •. I EUER~f I POI<--------1------ I 1315.I 31'1. I I':. I I I lqb~.F 0 •.•/ I U35~I' 19c7-l'1/l/l ",PuF "put" 75 ...· I).: 21u. iOQ .. 22 •. 5Ui<i'l.tlS RefIll!:"1E'n S.· "-''':;J~i). S !~A'~/EI..EC· CUMil.!IJi<rl INE II TESE\.; L.OSSES I I PEAl<1---------------------1~~U~l~!~E~rS I 300.-------·_------1 "e:StJ"ilCE$·I e:U~n.NG-I' ;:ii~~~~/rL"c ~ Cn~.!1·.,.njHbI NE I Oll:.SE:1..r r I '13 ..... I It/flH rONS.I ·.,,,v""Q.·.I .$,Tb'""'/EJ..U;.I c.o;o.,.b--..rU"~rNE.,r Ulr5E\.;I I' I I I J'. I I---------------1("llilSS-..<e::,uUiiCESI '131:1. I /""""'.eJ.;>~t:S·..I4A~GH.I O.'1':lo! I I I' J I NE T ~FSOljIiCES.I I I I I I PEAK --PEAK LOAD/GENEi<ATING CAPACITY i<EQUIIlEMeNTS(MEG"~ArTs) ,",PUF·--MAXIMU,.Pl.Al\IT UTILIZ"TION FACTO" A"UF .-.ACTUAl.PLUIT UT ILIlAflUr.FAI.TO>l E"'E~Gf --GeNt:.kA TiONI ANNUAL EhErlGY REf.ll.lREMENTS (11 11.1.IONS OF I<Il.OIIIA fl-HQuOlSI 39 ~\ TABLE 3.10.(contd) ~",EA:'••C110><~"f ~"ie110RAGE C~~"":2 --!olED tUM LUAU GRU"TH P<TE~TIl:.YE~R:1'1"0. "uT~s:or;;c.b,1'I7~"I U.5.-I'/';'1. c ..I T I C A L.P E R I 0 0-------------------.._-----------_._--------------------------------~------------~--------I 1 '1'10-1'1'll /1"'1I-I'1'1~/19'i2-1'i'U /PE~""'l"uF ."UF E;~EI<GY /PEAK MPuF A?UF ENE>lGY /PEAK /,\puF APUF ENERGY/----------_..-/--------------/------.-----...... ---------------//I nt:·uld~e:M€~.r$/1351.bye3./1115Y.o"d~.I 15'13."'l07. ---------------//I kE~OoJ"CE5 ,// EJI:.iTING I // 1"t11JktJ I 13'1..50 •50 Sill •/134..50 •50 '310.I 13<1 •.:'0 •50 510 • SIEA·.,EL£C I bll~..15 •71 3'1<1b_/8'13 •.1'5 .&5 4'55~./10'15.•15 .5b 51110 • efJ"'....TU><flINF:I 7'11..50 •1'1 1 'SO!!.I 1'11 ••50 .il,10'15.,773 •.50 •10 b3U1 • ull:.Z:lEI./5.•15 •nll o•/5 •.15 .00 O./3..15 •00 Q• I I / TO TAI../157.5_5804./17n.0157./1"1';5.&311l •. //, AI)OlTliJ"S /// H'I'Uj.;'(;/// STc.A"',ELEC I ~O".•75 •.2U 350 •I .2'13 • •75 •.20 4.25./400 ••75 •.20 101 •co.".TU""I',E /I / Ult-SEL /// I // ;jETll'l ..·.Eo;TS I I I JotYUHi]I I I ~Ti."'/FLtC I /'II..oa .00 Il.I (.[J'H••lu"!'II'!,//II:!..00 •00 II.I ':ill •.00 .YQ 0. DIE::>EL /I 2._.00 .CiO fl./ /I I ~---------------/I / GRClS ..><ESOUWCE:;I 1773.&154.I 195'5.&5il2./230b.7011 .. /// CAP',;ES~MAIIl;UU fl.JU7 /0.349 I ~.~94 /// "'::~E,,\I~REa.I 271.I .290./30'1. I I / "(J:lsc:s /b ...'11./73.97./77.1 \/'1. I // ~.E:r "<.50IJ",C£::'I 143'1.&Ob3.I 1593.0'18'5.I l'12U.b907. /// r;IAN:lFEH'E~/~./-<'I.I -d... I I I I /I SUI<PLUS /77.,O.I 114.O.I 211'1.0 .. 'tA~'i.~LOAO/GiNERATINi CA'.CITY kEQUIR£~ENTS(MEGA~ATTS) l.lilllF 'U~I"'lJH PLAiH UTIL.ILHION .~CTUI< Ali'UF ACTUAL p~,~r uTIL.IlATIUN F~CTU~ ENERGY --GENlRATIO~/'~hUAI..E~fRGY REaUIREHENTS(MI~~IONS 01"KI~O~ArT-HOUWSJ TABLE 3.10. A~E":FAp"HAN~S FAIwH4NKS CASt:2 --~EOIUM LOAD GROWTH IhTERTIE IEIW:1990. NUTES:UEC.b.1976 N/U.S.-199Q. (contd) C ..I T rCA L f'E R I cl 0 .50 •50 O• .7'5 •bB lcll3. •511 .IB 313 • •111 .00 \/. 1591. .5v .50 {I. .1':1 .71 1359 • .50 .23 327. .10 .VO (I • I !lee. /19"0-IQQl / /I'EAI'\....PUF ..PuF E;,,,1<6l /I'EAlI/------------J---------------------// I<E\'Ur~E·~ENlS /343.1505./358. ---------------// ,><E ;;()UPCES // eI.I~rl'lI.// >HUI<U /IJ..50 .:i0 ,O.,o. SlEA"i/t:":L,EC /21b.•/5 ./3 11701 •,211>. CO"'o •.TtJR6Ii,E·/20 ....•50 .17 300.,204 • (l1l:SEL•./IJ.•iO .DD D•./D. // TOUL /41"1.1472./419. /, lUll r 111Jr.3 // "YoJ)/O I I ~It ".'IIELEC I 3<!..15 .20 51>•./ t.'j;-'>I.1IJIIH INf:I / I.:ItS€L I I I I 1<t r IIH.MI:.N I 3 I I hV()i><1 I I ::.rE"'~If LEe /32..00 .00 O.I CU.1Fi.TlJi'lIl1 TN£.I / ~lI:SEL I I I ::--------------1 , ",HUSS.·"IESlJUI(CESI Q 1 <~•.15~!f•.I 41q ._ I I .'-'p...l<E:i."'''RlOIN'u.222 I 0.1.10 I I :iESf"ve:..Ea.I 69.I 72. I I kOSSE:;I 1 7 •23.I 18. I I 'J!::T ,.jESOiJIICES I 333.1505.I 330. I I 1.10 41.,:,1<f.III:U I ).,I 29. I I /I S'JIlPLUS·/-Iu •.O./O. 19'11-1992 / ~PUF APuF ENE"GY I PEAlI--------,;.----- I 1573.I 374. I I I I O. I 2U•• I 0204. I O. I I 419. I I I I / I / I I I /4(1. I I I 15'H./H'I. I I 110013 I I 1'5. / 24./19. / 1'513.I 286. / I ~'1. I I O.I u. lqq2-19q3 ""uF A?UF _I,IU .uo 1;'41. \/. v. PEAIl,--PEA ..L.OAU/GEI>;.iRA n-.lO CAPACITY i«Eill)IiiE~,EI'iTS(MEGA ..ATT S ~ M~UF --~~xrMUM t>LANT UIILIZATIUN FAcrUN APUF --ACTuA~,PLANr UTILLZATION 'ACTuN E!.EPiGf --GENl:.K.l.T IONI AtlkUAI.ENERGY HEQUIREMEJli-lS lMILUOIiS iJ,i'"KILOI'lA TT-huUI<lSl 41 _~"'l~~=--,-------.--------------------------------------------- ~I TABLE 3.10.(cantd) A~EA:A~'CMOl<A6E A,;C ...fH~A&E CASt.:a --r~EOIUH LOAD GHuVI!H I ..rE~rh TE .,1:1'l~U. NuTE5:IJc.C.b,1918 "'J U.S.-199<1. C H I T I C "L.P E H·1 0 D----------------------------------------------------------------------------------------- J 1'193-19'14 J 19'14-1995 J 19'1S-19'lb 1 PEA",",PUF APlJl'EI;E"'liT 1 PEAK "PilI'"PilI'ENElilir I P~AK "'>'uF ""UF t.NEl<Gr 1-----------~--1------·--------1-.;------------ ---------------1 I I l'CE.i.i1f1~e.'_1~~f3 I 11>3:,.132'1.J 1129.1151.I 1,,'5<1.831 1. ---------------1 J I ~E ~Ou"1CE5 I 1 J E~I::.TI·;t>I J J ..ru"fJ I 13<1..~Q .~O ~l<I.I 13<1..511 .50 '510.J 7"'lc.•';iQ .50 jOl':>• "reA·.../f"LC.C J IIl<l')..1'5 .~II j,j4j.I 14"5..75 .34 Q~oa.I 14<1~.•75 .3&"''''1'''•C;J'lB.iURS IhE 1 12"..5G .10 'Soo •.I bo'!.•50 .10 5Bb.I £Obit ••50 .10 417 • !I rE·~"L J 3..15 •0"o./:)..15 .00 o•1 3.•1'5 •till o• I J 1 TOTAL I 23Gb.7"j'l.I 2251.531>Z.I a'HI9.·l>10b. I J I AvvLTI11I-l5 1 I J l"'I'ftJk(J J.I 1>51>..~tI .':10 a5i1~.I 6o..50 ,':III .!z~. STt,A;.</ELEC I I I cu><".rU""'INE I I J IIH:.S!:.1.r I'I J I I ~ET1"E'1E.NT3 I J I ",Yu-..u·I 1 J ;;H....·I/E\.£C J J J Cll';;".Tu ><"IN£I 55..uO .00 u..I J lZS •..00 .011 u_ II I~:;l:.1.1 I 1 I I I --------.------J r I .~ "..os~~ES'lURCESI U'H.7439'~I Zq09·.IIH.]•J aIHI.8~~1>.. I I I CAi'fte.s.lol.kGINI 0.37&J 0.682 I 0.548 J.:I 1 kE:>E",VE "El.i •.I 321_I jAb •..I 371_ J J I l.iJS;;;t:s I l\Z.l1p.J Bb.Ill>.I 93.1;:5. 1 1 J 1<e T ;,tl:;:;OuRCES J 11\4~.73;:~.·J a41&.1751_J Z41l1.il311. J 1 I 'l<Ari::'FE~E!J I -107.I o.J tI. J I 1 J I I SUi/PI.US J 9'1.o.J 747 •.G.J 553.Il. PEAK P~AK I.UAO/GENEHATINli CA~ACl'Y HeQU1~EMt.Nli{~E~A"ArrS) HP~F H.XIMUM PLANT UI~1.12ArIUN FACTUR AIo'IIF ACTUA~Pl.A..oI'UT,IL.1ZATtUN FACTtlH ENl:WG't --Go.Nl:.IoI ...TION/...NNUAI.EI'<El<IH ..€I1Ullil:;I'I!:....rs (I4ILI.10I'<S UF K II.OIOA rT-HHUHlIl 42 ., TABLE 3.10. _AREA:F~l"'flalllt:t FAI~~.N~S CAS~:~--Mfulu~LUAU GNO~TH I1HElilli:.H ••lt:1~'lQ. NOTES:OeC.b,1~7&~I U.S.-l~~4. (contd) --------.---------------------------------------------------------------~--~-----~------- I 19'13-19'1<1 ,199"-1~9'5 I 1995-199& I P!:ArI ·'''UF A"'Ur EHEIIGr I PEAK /4P'jF Al'j,F Er.li.RIiT /P:'AK MPUF .?(jF ENt"1liY 1-------------,------...-------/-------------- ---------------,I / Hf.!-HJ 1 (,fe ....j:,,'~I ~,.S!l'l.17~'1 •I 'lOS.1771./".?3.Ib~'1. ---------------~I I "E~uv ..CF.S 1 I 1 EJl::.IlV.1 // "1l;;lfJ /11..5".SO 0.I (J..•'50 .50 tI.I l:il..50 .50 ~7~. :;'';:.:1/I:LEC 1 21b.•15 .73 1371./21b..75 .sa llH:lb./21&•.7'5 .bJ IIJ'53, CO.,;.TU'l!>It.E /104..~o •25 357.,H,"..50 •10 145./1&"•.~o .10 1 '13 •. ul ..Sli.t..1 o..1U t.Q.Q tI./.fJ'..10 ..00 O.1 o..10 .UO u. I 1 / TOlAL "37'1.1735_',.379.122'1_,'530.17H. I // "Oli 1 rlU"'z:,i.1 // H"rvR.U .1 .;,lSI..50 •50 '57'1./19 •.5l1 .50 7'1. ;'T1.A"l/cLeC""'//,2':>..7'5 •211 43 • CIIM".T'J';11 [r'e /1 / 01r.:;':L //I I I / ;1l:.TIRE:.,l:.N IS 1 ,1 ,,1lJRO 1 I I ::.TU""ELEC I /I <1.5..ou .uO u. CO",H.flllol.;Ttllr./-.I I -[H ..~Et.//; I ,/ ---------------,I I iilolUS:>>IF.~IIlJ"CE:;'.H~.1735•.I 530_1804.I ':i"9.1ll1l7. 1 I I ,"'-~.lP "'ES~....R&1·N/-II.02&/0.306 I o.a~1l I -I 1 "l:...t:r<VE I<EY./7~."lit.I ~"". 1 /I 1.0"S£.S I 19.20.I aQ.2T.I cl.2/l. /// ;,E t '1E:;UI/IolCES 1 2R2.1709.1 42':1.1777 •I ~".s.1·1l:>'l. I /I T""""'I:.IIEil J 10'•I o.I o. I I /,I 1 SUo/PLUS I o.O.I all.o.I ao.u. PE.l1<PUrl L.O.U,GENEIUTIN&C.lp:.cnr ~Etwl"EI'\ENTS(!'lE&,t,..ATTS) HPuF ....XIMUM PLA~T UTI~lZ,t,TION FACTUR .lPUF ACTu"LPL.l~T UI1LIZAT10N "CTuw E.....E~GY --Gl:.Nl:.R.lf1UI'l/.lNi\iUAL.ENE~GT k£OUlIiEMENTS{M1LLIOIf5 OF I\I!..U".lIl-l'Iuvo<:» 4-3 TABLE 3.10.(contd) AI,EA:A.'jC ....O..A~E ANCHU~A~E CA~~:2 --MEU!UM LOAD GkO~r" !~rER1I~YEA~:1990. NIJTE:S:UEC.<0,1'l711 'Il1.U.S.-199'1. c ~I lIe A I.PER[OD o• 15u. o. 7b1l8. 9991. 33114. ..\12,:>• a 111 • u• 1 g I "I • •so .50 •SIl .50 •75 .32 •so .10 •15 .00 .00 .UO 1998-1999 M>'uF APUF O. /:iTS. [445. 335 • o. 33411 • S'-"311 • 29'1 • O• I ENE"GY 1 P\:.A~ --------1------I '1'1$1.I 2a2~. I I 1 I I I 1 I 9512.I 205'l. I I I o5~. I 1 I 1 I 1 I I I I I 9S72~'1 ~i!~!I. I I li.lI7<J 1 I "'lb. 1 1 4 1.I 111. I 9'131.I 2131:i. 1 I I I o.1 510. •541 .50 .75 .47 •'50 .•10 •15 .00 19'17-1998 M>,UF APUF I 1 'l':l6-1 'l'i-7 I I I'i:.AK MI'<.JF ....1.1"ar.E I;Ii V 1 POll 1--------------1------ ---------------1 1 ioIEUUlioI("'I:.'H:I 1 1979.U71.I 2103. ---------------1 1 R£::;OuRC£S I 1 EXl;>II,H;1 I rifl"RO I 1:178..::'0 .~O 3344.I a711. :>1i:.Ar./ELEC I 1~4'i.•75 .'"5.:16 ....I l Q 'I5. (0;-,,,.Tuol"[;1£I '5<15.•50 .10 294.I 335. ull:.SE.L I 3..15 .00 O.I U. I I IOrAL.I Z81l •.9111l"•I 265'1. I 1 Ae,,:;I r 1'J"::;I I "rviolO I 1 5fEA~/F.Le:C I I (;()....;.lu ..l:IINE I 1 iJH.St.t.I 1 1 1 IlEfl~O::"ENl S I I I1lUl<O 1 I ~ri:.."/ELEC I 1 COM~.TIJIl:HI<E:I 211]•.uo .00 O.1 01t.~i:.L 1 ~..•uo .00 O.I I I ---------------1 I (;$«,S::;~t,::;UlliolCe::;1 2b5".'1004 •.I 2b'i'l. I'I CAP ,;e:S.,O1AilGHl1 o•3!~3 I O~2b4 1 I ioIt,SEkVE kEQ.1 396.I 1121. I I l,OSS"S I '19.13J •.I 105. 1 1 :.£1 ioIESOuwCES I 21"'"8/:171.I 2133 •. 1 I' 'HAI'SFEREU I -27.I O. I I I I SuHP1..US I l'5d.II.I 30. I'EA~peA~LDAO/GENE~ArING CAPACITY HEuulkEHENTS(MEGAWAITSJ HPUF MAXIMUM ?LA~r UTILIZAl10N 'ACTUR A~W ACTUAl.PLANT urILIZArIO~FACTUH '~~EHG1 --G~N~~ATIO~/AN~UAL ~NE~Gl NEQUIH~ME~lS(HILLIOM~UF ~ll,O~Arl-"OUHSl ,.~, A • ,~,TABLE 3.10.(contd) Ali'EA:FAI~fI"N ...S FAlkUAN":;CAS ..:~-.'.fu lUM L.UAU Gl/llwrM I"lIEIIiIl>TEA!<;1"~O. 1,(jIES:OfC....\9711 "ill U.S.-19'14. C !<I T 1 C A L.I'E ~I II 0-----------------------.---------------.---------------.-----------,----.----------------- I I q~l>.1 ~''17 1 l"q7-1~911 I 1991l-1'l9q I PEAK "'''UF Ar'I,F EI.E!<GT /I'EA~MPlJF APllf Er,fNGT /I'EAI\1-1~\IF ....!.IF EI"....GT1-··-·--------/._--..--------/----_.---------------··---·--1 I 1 ilE"U!REME·'1IS I "4.!.I ~'ll •I <ll>I.21123./"ao.211J':!....-..--.-...../I I RESOIJ;/CES /I I <:llIllIItJG 1 I / rt¥u;,!1 /170..50 .50 &48./170..5ll .SO &48.I 1711..~O .50 oa~.. S H.AI<·/i:.i..EC I 21&../'5 .,,11 IctOO.I 210..7').105 la~o.I 31b..15 .35 9"~. C1/"".luI/clUE /16t.1...'i0 •10 123 •/Illu..50 .10 O./o..'ii).10 II • <LJ!:'lll:.l./o..10 .00 O.I v..10 .00 II./O.•11).0'0 o. /// TOTAi.../549.l'HO.I 52&.U7a.I 'lab.1/>11. I I I ADD 1 T t OtiS.I I I "TuRl)I '"/I \38..51>.511 5025. i:lHA'./t:L"C I I 1110..75 .cO 17';./ CO"II'.Til"'''tNE I // oIESEL I // /// Ht:Tt,,;;:t~I:.rlTS-I I I "T!J~I)/// ST€A;~/ELEC I // t u"".r"~!:l HiE I c4..00 •00 O•/1110..00 •00 O•I :l1ESEL I I I I I I"'--..--.....---/I / 511\153.~ESl)lIilCESI ')C".l'HU •.I 'llla •.20S.5./cell.2137 •,//1 ~~P "ES •.'~ARGl'u 0.16'1 /~.G~3 /O.e'l'1 //I Nf::'E""f wEu./~'"./'12.I 910. //I LoOS3c.S I 22.2'1./23.3Q.I 2'1.32. I I I ,.£T i<f50uRCES /'11~.1'Ill 1 •.I 370.2023./SO".2105. I I I II<'A'~5F£Rf.O I 27./U.I G. I I I /// SuRPl.US /o.U.I ·'11.O.I 211.II. PEAK Pf~K L.aAO/GE~ERATING C~PACI1'NEQUI~f~EkTS(MEGA~ArT5) ~puf MA~lMvM PLANT UTILIZATION FACTOI<' APUF A'JUALo I'i..ANT uT1L~lAT~ON FACTOH ENEHGT ••G..NfRA.rIUN/ANNUAL ENf.HGT xEuUI"EMEfflS(MILLIONS OF KIL.U~Arl·HOUHSl 45 TABLE 3•11]. A"EA:"NC,lIl"Al.E A,<l:HU,O"1'CAS ..:2 --IolEuluM L.UAU GHIJwTH IHTE"TIE YEA":I~~Q. NoTES:OeC.b.1'111;..,iJ.3.-1994. (contd) Cf<ITICAL.~E RIO 0-----------------------------.-------------------------------------------------._--------/19"'1-2\10u /2000-2001 /2uOl-21l02 I PEA~,",PUF U'UF EJ\lEIo/G1 /Pl:.AII MI'U~APUF ENEIoIG1 /PEAII l'lI'UF Ai'U;cNl;1ol1>1 1-------------1-----..---------/------.-.-.--- ---------------1 // "E"'Ul ...E'~E:no.I 2j53.10:)51~/2'121.1 U8bj./2'1'lu.11115. ---------------1 // K(:;Oul<CES //I EU:>II"l./// IHU ..O /I'iH..~O .:)0 San./Ib17..50 •50 blbU •I Ib17 ••50 .50 121120 •:.HAH/EL.EC /1'145.•15 •34 4343 •I 1445 •.1~•J7 'H47 •/1'1"~..75 .411 50(10 •. COMS.fUR;'WE /317..50 .10 200.'I 23&..50 .10 119./136..511 •10 103 • ClI ..SEI./o..15 .00 G.I 0.-.15 .00 O.I o..15 .00 D. /I / TOTAL I 32'15 •.10.38&./32'18.11 02/:1./31'16.11343. //IA\JO!T10.":;//I H'tlIiU /85.•50 .50 323 •/I S T~A""El.fC I // CO.1e!.TUI/b IUE I I I lJ (ESEL I /I //I lit:Tt .."...t:i.TS /I I 111'iJitO //I S P:A",cL.EC /I / cn.....11110/"INf /62 •.•110 .ao o.I 100 •.00 .00 D•.I 10..1111 .00 U.Ull:.SEL /// /I / ---------------///~";"OSS flESO,jHCES/3291:1.10709.../31'18.11112 ...I 3180.11.3"3.· //I CAP WES.1'<...1'11011.1 0 •./102 /0~321 /0.277 I I /icESE><VE REy.I 1171./4184.I 498. I I / I.OSSES /II'.1'311.I 121.11>3./T2'5.1123. //I "ET OlEo.OuRCE5 /211"•1 0::'5 1.I 2593.108l>3./2'558.1111'S..//I TI'IAI'~"ERED /o.I o.I -b./I I I /I S'JRPI.US /351.ii •.I 172.o./101.o. PEA~--PEA~L.OAU/G~NERATLNG CAPACIT'~EyUIKEM£NTS(HEGAftATTS) MPUF --MAXIMuM PLA~T UTILIZATIuN FACTUR ",PUF --ACTUAl.PLA~r UTILIZArION FAcrn~ ENE~GT --G~N~HATION/ANNUAI.E~E~~T icfYUIWEMENTS(MILI.IONS uF KII.O~ATT-~uU~51 ,~, "' 46 TABLE 3.10.(contd) ~~tA:,~1l<6At'KS FI>HIA~lj~S CAS..:2 --.-1EOIU"l.OAD GRuwTH I"'TEUTl~YE~il :19'10. IIOTE.:;:lJE.C.,.,1916 /jl U.S.-1'19Q. C II 1 T 1 C ~l.I't I(1 U 0-----------------------------------------_.._-----------------------.--------------------- I 191j9-200a I 2000-2001 I 2001-2002 I PEAK MP!JI'APUF ENERGY I PEAK Ml'uF ,4Pt.:r EJ\lERlOl I PEAK MPUF A"OF ENEilGl 1--------------1--------------1------------- ---------------1 I I fcEuIlIllU'~lnS I 499.2187 &.I 508.2a29.I 518.2270. ---------------1 I I "I:.SUI.Ii<CES I I I E~l:'Tl'.iO I I I '1 <1.11<,}I 308 •..~o •50 1173 •I 32&..50 .50 lallY.I 32l>..50 .50 124O. :.TEA"/ELEC I jl&..7'5 •.3'3 980.I 316..75 .37 1022.I 31b..7'3 .36 lUb". cu"'&.T\JioId U.£I u..50 •.10 O•I O..50 .10 O.I o..50 .10 u. o IESli.L-I oJ..10 •00 O•I O..10 .00 O.I O..10 .00 O. I I I TOIA~I &24·•.21'33.I &41.·2202.I &'11.,!JOe •. I I I AOO IT lor.s I I I ~'I"t.",;;j!fJ I la..50 .50 i:J7.I I STE",,·l/El.EC I I I CO'<ll.Tu'"'''INE.I I I 01 tSli.L I I I I I I J;lli.T 1I'lE"'ErHS I I I 'HUIIl;1 I I ST ..,l.rIlEl.tC I I I C[."'~.Tu"'''lI.C:.I I I DIE:>E.l.I I I I I I --~------------I I I '"uSS.fcESijuiolCESI bill.2220.I &111.22b2.I &41.2304. I I I Ct.,,·I<f.:l."AIU.n.1 0.21l5 I O.2bC!I O.C!.3l! I I I i<E;i£i<vt:KEli.I 10u~I I (l2~I lOll • I I I ~OSSES I 25.~3.I 25.33 •.I 2b.311. I I I ;,£T "'E:iUlI;lCES I 51b.alt17 •I SIll.222".I SIC!.2270. I I I TRAU.:oFEREO I u.I O.I b. I I I I I I SIJICPLUS I 1 T.O.I b.o.I (I.O. PEA~PtAK ~OAO/GENERATI~~CAPACITY "'~~UIHE~ENTS(MEG.~ATTSI "I'UF MAXH1W1 1'1.ANT Urrl.lLATlON FACTup APlIF ACTu~t..~l.ANT UTILlLHION F~CTlJk tNf....Gy --GtN~R~T1[)I\I/"'N,"U~l.EJ~EI<GY JlEIJUIKErll1'l I S (Mll.l.IOI~::S 01'I<11.011.."TT-l1UUK:l1 47 TABLE 3.10.(contd) A"I:.&:A.\C"O,a",e A~C"O~AbE CASe:2 --MEDIUM ~OAO GROWI~ I~TERrlt YE.R:19iO. ~~II:.S:OEC.ti,1978 ./U.S.-199<1. CR 161 I C A ~10 ER I a 0--------------.-------------------------------------------------------------------------- o. o. 12111. 1~111. .51)•50 blbl)• .75 •J&0133 • .50 .10 u • •15 .liO O• Ic293. 20,)/1-2\)1)5 MpuF APUF .00 •i,l0 U. lel. 1&11. 184,:>• 10. O. / 1 "E..AK1------ / /2119". I I I / 1 I / / 1 5480. I / / I I / / 1 1 / / I 1 / I 3402. / I O.ae", I /539. I I 1.5'). I 1 .Hai. I 1 I I U./ 177. ENERGY .so .511 bl&O. •1~.3&51l01. .so •10 1'3. .15 .01)O. 1197". 2U05-2uO'l MpuF APUF I). Il.17 • lall~. Ill •. O. olbU • /1103. IS. O• I, E,~EKGY ..;/PEAK --------1------I 11487.1 2l.2l.. 1 / J / / I I / 10959.I 3480. I / / 701.I / / / I / I u.1 / / I 11l.59./3"80. / /O.32~ I 1 525. / 17o!.I 131. I 11487./282". I / 1 1 O./I'HI. ./5 .CO •~U-'.50 •r-!.38 ,.su .1 U •15 •(10 cO"2-i!\JQ3 ..i'UF A?UF o. 11>17. 1445. Ud. a.' TOUt.' Al!ull ral,:. ,",ft-wI';' So r"A""~LEC. ClJ,~".TU~ij HIE CIE.::>E.L ;j~.T lW;:'HEN rs "r,).:10 5T<'.:HELfC tl)"1~..lLJHt]10i:, uI~SE.L ,-U:;5..5 /, /PEA"/--------------------/~EQuIREM~NrS /2~~~. ---------------1..£:'0 ').:1CE5 , / EAISTIt,r,/ "'uRU / STU"'/ELEC / CfJ"~.Ttl""IM,/ 1i11:.5U./ / /,51&'). 1 / / /'UIU. / / / / / / /lDU. J 1 -------.-------/bRQ5~~€5nllRCE5J 34~U_ 1 CAP RES.MANGlh/U.3~1 1 /')12. / I 12/>. I NET ~ESUURCES I 2841. I / / / /i!/l5. PEl~--PEAK ~UAu/GEN~RATING CA~ACITY ~£QUl~E~£NTS(HEGAwATTS) "IOU'--MAXIMUM PLANT Ul1~IZATrON FICTO~ .>'tlF .-ACTUAl.PLA,"T UII~lZ"'T1(;N f4<:.II1~ E~e~GY --GE.Ne~Al1U~/ANNUAL ENERGY ~EUUlwE~ENTSlMILLlaNS Of KILU~AT1-MUU~~J 48 TABLE 3.10.(contd) J,iotE,A.:,f Po !l"I'dANI\S FAIR~~~~S'CAS~:2.--MEOIU~~OAO G~O~T~ 'I"rEIHlc.YfAIl:1~90. MuTeS'OEC.1:>.\91ij ~I U.5.-19~~. C 1/I TIC Ai.,__I'E 1/I lJ 0 .------~--------------------------------------------------------------------------------- o. .sa. .50 •50 li!'lO • .15 ..35 1191. •511 .10 o • .10 •00 O• 2431. ~OO"-,NO~ MPUF APUF ENERGY o. 27. 1240. 1146 • O. O• I ENERGY J PEAl<.--------1------ / 2353.1 '.:i4/:>. / I 1 / 1 I I / 23118.I 71&. I I I 1 I I I I I I -'I I 1 1 23118.I Hb. I I 0 •.:51 1 1 I 109. I .lS./ I 2353.I sao. I / / I O.I .50 .50 •7~.34 .~o .10 • 1 It ..00 c003-i!OOQ MPl;F APuF 1 20u2-2003 1 1 PEA<.,PUF ,Ai'UF t:f'~fk\3Y 1 PEA~ 1--------------/------ ---------------/I kE:uUlkE"Elojl::i I '')27.2312.,/537. ---------------/,/ i<E:SOLlHCE::i I /c.X I::;r II,../, "YuHI)I 32.....5f!.50 1.24U./321>. ::;TU'''/~LEC /311>../5 .37 "H.I 3'H.co;.a.TUi/a INE:I q..~O .10 0.,1 0., ul~Se:L /u..10 .uO,O./O. // TOTAL 'I ...'It •c17l.I 711:>• I / AO!J 1 TIO,.S I'/ riYUtolO /I STLAM/€LEC /1011.•75 .20 17'5 •/ Cu'.!'.r'J~b INE./I !111:..~..t..I I I / RE:rlPEME.'1TS I / ,,'1'i.J~O /I ::;ro,"nt.."c /2:>..UO .00 U./ COHlS.rURti INE // ~.::t.Se:L 1 / I I ---------------1 I ....(;:;;;;I<E:WUkCI:.l>1 71".c3qJ •/7IIl. I I .~CA~"I:.~.MAI/GINI o•.3~~I 0;333' /I i/ESE"VE,.l<t:Q./10"./107. /I L.O::;Sc5 /2".15./.,21. I / r.E T "E SI)URCE 5 /50"•2312.I 502. // TII .....::;I'EI/"O /O./O. 1 I // SUI;PLUS /57.O./,,'). PEA~PEA~~OAD/GENEI/ATING CAPACI1Y ~F.~UI~EMENTS(MEGA~ATTS) HPUF MAXIMUM p~A~r UTIL.ILATIUN FACTUII A~UF ACTUAL PLANT VTILIl ...rrUN fACTvK ENE~GY --GENc.R"'110'~IAN;,jUAL ENE~IOY REQul;;El'lENTSlMlLt..IOfliS OF KII.OilATI-"uURS) 49 Pe~~Pf~~~OAu/G€NcHATING CA~ACITY ~EQulk€~ENT~(MEG.~.TTSJ ~PUF ~A~lMU~PLANT ~rlLIZArluN FACTUH APUF aCTUAL ~LA~r uTILIZATIO~FaCTD~ E~E~GY --GtNcHArION/AN~U.L ENckGV ~EYUIHEMtNrSfMILLIONS uF ~!Lu~ATT-~~U~8J 50 ~.. , TABLE 3.10.(contd) ''''EA:FAI~"AN"S f.llollhN.S CAS~:2 --MEl.lIUM L.OAO GRO"'l" Ir,TE"11!:'YEArO 1""0. ~IO IES :Or.c.h.1918 "',U.S.-I""'!. C R I T I C A I."E il I a 0-----------------------------------------------------------------------------------------/~Qu5-cuOh ,cOO,,-cu()1 /2uu7-coOl! /PEAK 1'Il'uF AI'UF EiIE"lGT 1 PEAK ,.PUF APur Eh£IolGl /PEAK IoIPUF AP\JF ENEi/Gl/----------.---/-------------1-----------------------------1 // wH,uIRElo';::r.T S /55<..2437./5&5.2418./515.25211. -~------------I // ''''E~UiJ''(;£S /// HI:>r lW~·/.// "Yuila I 321>..':>0 .5D 12'10.I 3Olb..50 •50 12'Hl.I 32&..50 .so 12'!0 • ~n.A"/ELEc I j"l../5 •So 12.34./.511 •..1">.j9 1<17,:>.1 .511..15 ."1 [jIll. CO"'".TI.o«/l I1.IE /Q...,:>0 .1i>O./O..50 •10 O./0..50 .10 Ii • lIIr.::'U./O..10 .00 Q./0..10 .00 I).I D..HI .ilO 0. /// rOUL /710.2'114_..i b9b •.251S_/&9b_2550. /// .laO IT IO!'<S /// ri'iJf'l.f)/// sreA"'/l:LEC /// CUM'!.TU.<fI tr.E //I i[.o IE5EI../// /I I ~E TI;'E"r.I~r::i·/,/ ;l"'tYL:~J ,// ,:,H A t'£I.EC /211..01).00 O.// 1 CO"...Tu~"11.£I I / OU~"L./// ,/I /---------------/// \oiHjlz:...l::~OuRtE~/·o'Jo.2 'n'l./&'110.2'515./&90.i!ssa. I // t~~"..s ...,.:lGII./11.252 1 O.23Ol /o.all /// ..E5~"\iE liEU./111./113.I 115.,//. ..OliSl~I 20.37./21'1.:51./2~.311. //I 'iE,l'lESOll"CES /'3'57.2437./55S.2<1711./552.Ol5OlO. I // li"....SF EIolElJ /0·•./10./23. I // /I 1 SuR9L.US I 1 •.O./O.O./O.II. PEAK PEA~LOIO/~E~f~ATIH~CA~ACIIT j.{EYUIRE~ENTS1HEbA~ATTS) H~UF ~AX1MU~PLANr UIILIlATIUN 'ACTuR A"IJF 11;TI:1-L.I'LA"r UI1LIZAII0N F.l.CTUI'i E~EwGl --GEN~R1-rl0~jANNuaL ENERGY RECUI~EMENTS(MIL.LIONSOF KILowaTT-MOURSJ 5-1 TABLE 3.10. ~kEA:~"CHOkA"E A,.ChUilAloE CA::it.:2 --i~EOluM LOAu GllO,HH I~TEN1I~TEAk:1~90. ~UT~S:~~C.h.1~7d ~I U.S~-lq~~. (contd) C I'(I TIC A L P E Ii I iJ LJ ---------------------~-------------------------------------------------------------------1 2Du<l-c!110q I 2~Uq-20Iu I 2'H Q-2Ull I PEA,(",PuF Ar'IlF ENE~~Y I PEAX MPI;F A;>uF ENEiiGY I PEAl(MPUF APuF ENEliGT 1--------.-----1--------------1-------------- ---------------1 I I -NEA,J~~..-<!:.I'IS I Zql>d.13350;.1 3030.13..71.I 310'1.13'Il;3. -------_·------1 I I j(E·~{;l.J ...~1.~I "f 1 EO"II'H'I 1 1 i1Tu..-a /1"'11.•50 •50 01&0./I t I 7•.50 .50 &1&0.I 1 b 1/•.5\1 .50 01 ..11. iiTU>i/ELEC /22'1~..75 .38 1<100./2245.-.75 •3CJ Ip".I 22'15 •.75 .37 n3c!. ca"'B.Tllw ..II-!€1 ~.•50 ~lQ O.1 o•.50 .10 O./O..50 .111 u. ~.;'liIc.;ofL I 1*._.IS-.I>il o./(J..1:;.1>0 .O.I u..1 ':>..1.10 U. I I 1 TIITAL 1 3M''?1355~.I 31lb2.1:5<170.I 30b2.IJ'ICJ2. I I I ",,0 I no',s /I I tt1u~{J I .I I / ::.n.A,HU.EC I I /400..75 .2\1 1 \t I •. CO><Il.TUlltllNE I I I l)lt.~tL I I I I I I "I':.T!REJlEflT:I I I I Hl'l,)~i1 I // S lE...-./tLEC I // cr."'i.Tllna U.E 1 /I UIt:SEI.1 /I I I I .~---------------/I / '-~U~.;i Ii/cSH'-l",CESI Jabi!.t3o:.59.I 38b2.1387&./'1e62.1'11'13. I /I '41'><£5."Ali'G Ira 0 •.301 /0.212 I 0.373 J I I ~E~E"vE.;(£0.I 5q·~•I bUl./021. /I I Lrl.'>~E;;;1 14d.e\)il.I 152 •.20'>.1 155.2111. J I I NET flESOIl"CES 1 3120.1335".1 3103.13611./34<1 ...13'1113. 1 // Hi.lH:>FERED /-3.:.4.I -4"./-Sa. I I / //I 5 u..-Pl..uS /1 t,s.O./21.O./3 ..5.0.'' PEA~PE~~LU~UJGENE~.lrI~~C.lPAClTY REoulkE~ENTS(MEGAwATTS) MPUF MAXI~~M ~~A~l UTILIZATIUN FACTUk A"OF ACTuAl.PI.A,H UTlLlZATION FACUJ"- EN~kGY --GaN~RAT!UN/AN"UAI..eNERGY REQUIk(MENTS(MILLIONS uF KILUWArT-~UURS) TABLE 3.10.(contd) A,;fA:FA!"'bANKS F~IH8AN~S CASE:2 --MEOIuM LUAD GRO~TH INTF.Rllc YfAH~Iq'1U. NU1<.S:U£C.~.l~'~#1 u.~.-I~~4. CRITIC'>..PER r (J 0 .50 .50 12'10 • .7'].'1'14'1'5. .~O .1 \1 u. .10 .00 o • C'~('\.'3., 0 •. 2QIO-2ull MPUF ~PUF E"E~G' .50 •50 12'10. .7'5 .43 140c. .'50 •10 o• •1ll .OU O. 2e.4.L!. 2009-2010 I MPuF APuF EI.ERGY /PEA,.;_._-----/------ / ZbO-i.I b03. I / / /32i>. /371. I O. /O. / ;Q'''h•• / / / / / I / / / 1 / / f / 21042./b'Ur. 1 /0.154 I 1 121. 1 39.1 30. / 2~03.1 '5'1';. / /58. / / II./O. .~O .50 1240. .75,.~2 1359. •50 .:0 o • •10 .00 O• 2599. ~Ov~-2UOq / MPuF "PUF ENEwGY /PEAK -----~--1------ / 2501./59'1. / / / /32b. /371. I o. /O. / //091>. / / / / / / I / / I / / I I 2599.I ~9~•. I /0.172 / /11'1'., I 38./30 •. I 25..1./548. / I 46. I I 0 .•I II.u. 32b., 371. O. <I. SUi/PLUS TIl rAL AUOI T!Ot~S "YUR" ~1<''''''/ELEC co,"".TUi'lrlII.E O!",SEL "f'r H<E>oii?:NT S "'ffHiII 5H/.·~/fU.C CQ"'b.Tu"'"WE O!ESEl- 1 1 PEU/---------------------/~!UUJkt~~H1S I 5A~. _._------------/i<Esu\ii<CES 1 EU:;TTrIG 1 t<,jJ~iJ / :iTEA"'/ELEC / COl<8.TURtllNE / lJH.SEL../ / 1 ,,"h. / / / 1 / / / / / / / / / ---------------1G~OS~~ESaURCES/..q~. / CU'"'E3.,",."tHNI (}.l'1Z./ RESErI'Il::REil./117. 1 / / ~ET ",fIOUrlCES I S~U. / / f / 1 P~A~~EA~~OAO/GENERArlNG CA~AC!T'~EQurREMENT5(MEGA~ATTSl ~~UF MAXIMUM ?LA~r urr ..llAfIDN FAC1UN Al'llF ACTUAL.PLANr ulILllAT.l:ON FACTON ENEWGl --G~N~RATI0N/ANNUA~ENENGT REgUIRfMENT~(MrLLION$OF KILUwATT~HOURS) 53 TABLE 3.11.(contd) Scheduled Combustion Turbines Scheduled Combustion Turbines +400 MW S.T. Anchorage 400 MW Coal-Fired Units Could be Replaced with Staged 800 MW Capacity Units Scheduled Combustion Turbine +200 MW S.T. Bradley Lake (70 MW)x 1.15 for Peaking +7 ~~W S.T.National Defense Bradley Lake/(70 MW)x 1.15 for Peaking +200 MW S.T.+7 MW S.T.National Defense Na ti ona 1 Defense 200 MW S.T.+43 MW S.T.National Defense 400 MW S.T.+43 MW S.T.National Defense 55 TABLE 3.12.(contd) *Interconnection Installed (1)Scheduled Combustion Turbine Additions (2)100 MW Scheduled Combustion Turbine +400 MW S.T. (3)100 MW Scheduled Combustion Turbine +200 MW S.T. (4)Bradley Lake (70 MW)x 1.15 for Peaking +7 MW S.T.National Defense (5)Bradley Lake (70 r4W)x 1.15 for Peaking +200 MW S.T.+7 MW S.T.National Defense (6)18 ~1W Scheduled Combustion Turbine +200 MIN S.T. (7)Anchorage.400 r~w Coal-Fired Units Could be Replaced with Staged 800 ~4W Units (8)National Defense (9)200 ~1W S.T.+43 MIN S.T.National Defense (10)100 MW S.T.+25 M~~S.T.National Defense (11)400 MW S.T.+43 MW S.T.National Defense 57 TABLE 3.13.(contd) *Interconnection Installed (1)Scheduled Combustion Turbine Additions (2)Scheduled 100 MW Combustion Turbine +400 MW S.T. (3)Share of WatanaCapacity x 1.15 for Peaking (4)Share of Devil Canyon Capacity x 1.15 for Peaking (5)Scheduled 100 MW Combustion Turbine +200 MW S.T. (6)Bradley Lake (70 MW)x 1.15 for Peaking + 7 MW S.T.National Defense (7)Bradley Lake (70 MW)x.1.15 for Peaking +200 ~~W S.T.+MW S.T.National Defense (8)Scheduled 18MW Combustion Turbine +200 MW S.T. / (9)Anchorage 400 MW Coa l-Fi red-Units Cou1 d be Repl aced wi th Staged 800 MW Units (10)National Defense (11.)Share of Watana Capacity x 1.15 for Peaking +25 ~,\~S.T.National Defense (12)200 MW S.T.+43 MW S.T.National Defense (13)Share of Watana Capacity x 1.15 for Peaking +25 MW S.T.National Defense (14J 400 MW S.T.+43 MW S.T.National Defense 59 __________-r-----~_w ---__"---=---------- 7000 r". 6000 ~' ~ -b3:5000:E-0 ~ ..J ~4000<1.1.1 ~ 0z I "'"'< V1 I 1.1.1 3000u 0:: ;::) 0 V1 1.1.1 0::: I-20001.1.1 J-------Z I ~, I 1000 o 80 85 90 95 YEAR 2000 2005 2010 FIGURE 3.6.Load/Resource Analysis for Anchorage-Cook Inlet Area Without Interconnection and-Without Susitna Project (Case 1).Low~Medium.and High Load Growth Scenarios 60 7CXXJ / / 6COO t I-ls: ~5000c 7«0 ....J ~<W 0..400Jc:z< c.n L.LJ U Q:3000:::l 0en 1.1.1 0:: l- l.U:z 2000 ;.......... I ------ 1000 OL....-__~__......J....__---Ji--__...J..-__--'-__--l ..l-----J 80 85 90 95 YEAR 2000 2005 2010 FIGURE 3.7.Load/Resource Analysis for Anchorage-Cook Inlet Area With Interconnection but Without Upper Susitna Project (Case 2).Low,Medium,and High Load GroIJ/th Scenarios 61 -7000r--~-----------------------, .6000 ;:5000 ~ o ~ --l .~4000.<c.. LLJ C- o Z <C ~3000u0:: ~o V') LLJ0::2000 I- LLJ Z 1000 Ol...-__--L .L-__--l-...I--__-J...-"--__-J...-----: 80 85 90 95 2000 2005 2010 YEAR FIGURE 3.8.Load/Resource Ana1ysis for Anchorage-Cook In1et Area With Interconnection and.With Upper Susitna Project Coming On Line in 1994 (Case 3).Low,Medium,and Hi gh Load.Growth Scenarios 62 ~, 1200 t"....--I I 1050 J r,/ '-J-~ ~ Q 900 ~I....J ~I«~IQ.750c Iz«/," In I~u J....~10:: ::J 6000 IIn ~ 10:: I- 1.1.1z 450 '--._-'_.-..._-- 300 150 o 80 85 90 95 YEAR 2000 2005 2010 FIGURE 3;9.Load/Resource Analysis for Fairbanks-Tanana Valley Area Without Interconnection and Without Upper Susitna Project (Case 1).Low,Medium,and High Load Growth Scenario 63 1200 r-----------------------------,~. ,. 1050 I'- I I 900 I -3: :E-0 <:7500 ....l ~<: UJ C- o 600'z« V') UJ U -----.-c:: ::> 0 450Vl UJc::~, I- u.J:z 300 150 a 80 85 90 95 YEAR 2000 2005 2010 FIGURE 3.10.Load/Resource Analysis for Fairbanks-Tanana Valley Area With Interconnection but Without Upper Susitna Project (Case 2).Low,Medium,and High Load Growth Scenari 64 1200 ,.....--------------------------., 1050 ,I /. I-, J \_' I \I I \1 300 900-3: ~ o C§750 -J ~ isa. ~600< en u.J Uc:: ~ S;450 l.I.I.0:: l- I.1.J Z 150 o 80 85 90 95 YEAR 2000 2005 2010 FIGURE 3.11.Load/Resource Analysis for Fairbanks-Tanana Valley Area With Interconnection and With Upper Susitna Project Coming On Line in 1994 (Case 3).Low,Medium,and High Load Growth Scenarios 65 --I 4.0 SYSTEM POWER COST ANALYSES This chapter describes the methodology used to evaluate the annual cost of power from individual generating facilities (or groups of similar generating facilities),the method of computing the average system-wide power costs,and presents.the results of the system power cost analyses. The first section briefly discusses the factors which determine the cost of power.The second section describes the computational method used to compute the annual cost of power.This method is incorporated into a computer model titled ECOST4.A listing of the computer code is given in .Append i x D. The third section of this chapter contains a discussion of how the system-wide power costs are computed given the power costs for the'indi- vidual facilities.The results are presented in the last part of the chapter. 4.1 FACTORS DETERMINING THE COST OF POWER Three cost'categories are evaluated in this report:1)interest and amortization charges (capital cost);2)fuel ~osts;and 3)operating, maintenance and replacement costs.Of course,there are other cost items included in the cost of power to the consumer,such as taxes,insurance, distribution and billing charges,but these costs are not evaluated in this report since they typically do not vary among the three cases evaluated. .' These components of the cost of power are shown in Figure 4.1.The annual plant capital expenses are fixed by the initial financing and are typically constant over the life of the plant.Operation,maintenance, and replacement fuel costs typically increase overtime as affected by inflation and real price increases.As a result,the total annual cost of power progressively increases over time. 4.1.1 Capital Cos ts The capital costs represent the total cost of constructing a gene- rating facility.ihe capital cost estimates used in this analysis include 66 TOTAL ANNUAL COST \ COST OF ELECTRICITY (MILLS/KWH) TIME (YEARS) FIGL'Ru..J....Components of the Total Annual Cost of Power 67 interest and escalation during construction.It is assumed that the capital costs are repaid in equal annual payments over the payback period of the plant.The capital cost estimates used are in terms of constant October 1978 do 11 ars.. The total investment cost for the coal-fired and hydroelectric generating facilities are shown below. Total Investment Cost 100 MW Coal Steam Turbine 200 MW Coal.Steam Turbine 400 MW Coal Steam Turbine Watana Dam (795 MW) Devil Canyon Dam (778 MW) (mi 11 ion $) 245.4 372.0 646.8 .2501.2 834.0 ($/kW) 2454 1860 1617 3146 1071.9 SOURCE:Alaska Power Administration,August 1978. Transmission facility costs are presented in Table 3.7. 4.1.2 Heat Rate The heat rate is the ratio of the Btu·s going into the plant as fuel to the kWhls of electricity produced by the plant.The heat rate is assumed to remain constant for all plant utilization factors over the lifetime of the plant.The heat rate for new coal-fired stearn electric plants is assumed to be 10,500 BtU/kWh. 4.1.3 Operation,Maintenance,and Replacement Costs The operating,maintenance,and replacement (OM&R)costs include the administrative and general expenses as well as the interim replacement costs.All estimates are expressed in terms of Oct.ober 1978 dollars. They are escalated at a rate equal to the rate of general inflation. The 0~1&R costs for coal-fired steam electric and hydroelectric generating facilities and transmission facilities are shown below. 68 .~. 100 MW Coal Steam Turbine 200 M",!Coa 1 Steam Turbi ne 400 MW Coal Steam Turbine Watana Dam (795 MW) Devil Canyon Dam (778 MW) New transmission facilities OM&R (million $) 3.76 5.7 9.8 0.74 0.73 Costs ($/k~J/yr) 37.6 28.5 24.5 0.94 0.94 2.0 SOURCE:Alaska Power Administration,August 1978. 4.1.4 Financing Discount Rate The financing discount rate represents the cost of capital to utility.A rate of 7.0%is assumed in this report.This is assumed to be an average of all types of financing available. 4.1.5 Payback Period The length of time over which the plant is fi~anced is the payback period.This is assumed to be equal to the plant lifetime except for hydro projects where a 50-year payback period is assumed versus at least a lOO-year plant lifetime (see Section 3.2.6). 4.1.6 Annual Plant Utilization Factor The plant utilization factor (PUF)is the ratio of the actual power production during a year to the theoretical maximum if the plant was to run 8760 hours at lOO~capacity during the year. The annual plant utilization factor is highly variable depending upon many factors (e.g.,forced outage rate,cost of power from alternative sources,and power production requirements).Because of this,it is necessary to explicitly consider the effects of the PUFon the cost or power over the 1ifetime of a pl ant.As pointed out earl ier,the PUFs used in the report are determined by the load/resource analyses (see Section 3.2.6). 4.1 ..7 Unit Fuel Costs Fuel costs for thermal generation pl ants are expected to increase over times following paths shown in Figures 4.2 through 4.4 for natural 69 10 ~----------':"----------r-'7' BELUGA &HEALY • 201090.200080 0.1 '-----J-__.l....-_---J.__--l-__..... FIGURE 4.2.Estimates of Future Coal Prices - 2%and 7%Escalation SOURCE:Alaska Power Administration,August 1978. 70 _________________________w' 10.0 ANCHORAGE -KENA ILO BELUGA 0.1 70 80 -90 00 10 20 FIGURE 4.3.Estimates of Future Natural Gas Prices - 2%and 7%Escalation SOURCE:Alaska Power Administration,August 1978 71 FAIRBANKS ~/j II 7'/0 II II IIII. IIIIII il /1 II ANCHORAGE':KENAI PENINSULA 00 10 20 FIGURE 4.4.Estimates of Future Fuel Oil and Diesel Pri ces -2%and 7%Escalation SOURCE:Alaska Power Administration~August 1978. i2 gas (Cook Inlet areas),coal and distillable o{l.Although natural gas is likely to become available in the Fairbanks region in the early to mid 1980·s,Federal policies are expected to preclude its use for ~ower gen- eration except for probing and the cost is indeterment at the present time. 4.1.8 General Inflation Rate Because of the uncertainty involved in estimating the future rate of inflation,two alternative cases are evaluated.A constant dollar case (0%inflation),and a 5%inflation case. 4.1.9 Construction Escalation Rate In this analysis,construction costs are assumed to escalate at the same rate as the rate of general inflation. 4.1.10 Fuel Escalation Rate The fuel escalation rate is set to equal the general inflation rate plus 2%. 4.2.METHOD OF COMPUTING THE ANNUAL COST OF POWER FROM INDIVIDUAL GENERATING FACILITIES· During any year the electrical power production is computed thus: *EPPF;i=(ICAP *PUF;*HPY)/1000 where :" ICAP =Installed capacity (MW) PUF i =Plat utilization factor in year (fraction) HPY =Hours per year (8760 hours/year) *Parameters with the subscript i are assumed to vary each year over the i ifetime of the pi ant.Parameters without the subscript are assumed to be constant over the lifetime of the plant. 73 The total annual costs (TAG)are composed of two elements:variable costs and fixed costs.In equation form: TAC.=VARC.+FIXC.111 where: VARC i =Variable costs in year i ($/Year) FIXC i =Fixed costs in year;($/Year) The variable costs consist only of the fuel costs. VARe.=FUELC.1 1 where: FUELC;=Fuel costs in year i ($/Year). In turn,fuel costs are computed: FUELC;=HEATR *EPPRO i *UFUELC i where: HEATR =Heat rate (Btu/kWh)~, EPPRO i =Electrical power production in year i (MMk~Jh) UFUELC i =Unit fuel costs in year i ($/MMBtu) The fixed costs consist of two factors.These factors can be writ- ten in the following equation form: FIxe i =INTAM +OMRC i where: INTAM =Interest and amortization (capital recovery)charges (S/Year) OMRC i =Operations,maintenance and replacement costs in ye~r;($/Year). The interest and amortization charges (INTAM)represent the annual debt service payments. 74 INTAM =CRF *TINVC where: CRf =Capital Recovery Factor TINVC :Total Investment Costs ($) The capital recovery factor is used to compute a future series of equal end-of-year payments that will just recover a present sum p over n periods at compound interest (IR).It is computed thus:(l,p.26) ,CRF :JR(l +IR)PBP .(l +IR)PBP_l where: PBP :Payback period (years) The methodology described in this section is incorporated into a computer model called ECOST4. 4.3 METHOD OF COMPUTING AVERAGE SYSTEM POWER COST Once the costs of producing power from the various individual gen- erating facilities in a system are known,a method of comparing the total cost of Hwer from the three alternative system configurations evaluated in this report is needed. To compare the overall cost of power produced'by these alternatives a relatively straightforward method is used.The costs of producing and transmitting power for each of the generation and transmission facilities are added tl1gether for each year during the period 1978-2010.In equation form: TAC. J where: n:l: i=l AG ..lJ TAG,:total annual cost of power production for the system in J year j ($) 75 .'AC ..=annual cost of prOd~cii1g...or ~t:~ansmitting power for faci 1i ty~\lJ i during year j ($) n =number of generation and"transmission facilities in system. Likewise the amount of power produced by each facility during each year is summed to give a system-wide total. TAPP j where : n =2:PP .. i =1 lJ TAPP j =total annual power production for the system in year j (kWhs) PP ..=power 'produced by ead+generating faci1 ity i during year jlJ (KWHs) n =number of generating facilities in system By dividing the total cost by the total generation an average cost of power for the system is obtained for each year. EPCOST j = where: TAC. J TAPP j EPCOST j =average system-wide cost of power for year j ($/kWh) By comparing the costs of power,the system producing the lowest cost of power can be selected. 4.4 RESULTS OF SYSTEM CASH FLOVJ AND POWER COST CALCULATIONS The results of the sented in this section. evaluated: system cash flow and power cost calculations are pre- As pointed out earlier in the report three cases were Case 1.All additional generating capacity assumed to be coal-fired steam turbines without a transmission interconnection between the Anchorage-Cook Inlet area and the Fairbanks-Tanana Valley load centers. 76 Case 2.All additional generating assumed to be coal-fired steam turbines including a transmission irterconnection. Case 3.Additional capacity to include the Upper Susitna project (including transmission interconnection)plus additional coal as needed.Upper Susitna assumed to come on line in 1994. Tables 4.1 through 4.36 present the cash flow and power cost calculated for the 3 cases.The contents of these tables are summarized below: 07177777"'__I TABLE 4.1.Anchorage-Cook Inlet Area,Low Load Growth Scenario,Case 1,0%Infl a ti on----- New Hydroelectric TranslIli 55 t on Total Cost _J~COil L£!r~d CaedC!!y'_Costs _~_IS __10tal Total Total System of Existing Investment OM&R Coa1 Investment OM&R Investment OM&R Investment System Consumption.Average Power Year Capad ty ~osts_.Cos ts CosiL-_~.t>__~sts ~~!L.-~Costs costs.$Mt1t:~IH Costs.¢n~H 78-79 33.1 ---------------0.6 0.4 ---34.1 2376 1.4 79-BO 42.2 ------.--------0.6 0.4 ---43.2 2568 1.7 80-81 48.2 ---------------0.6 0.4 .-.49.2 2706 1.8 81-82 52.8 ---.-----------0.6 n.4 ---63.8 2050 1.9 82-B3 61.1 ------3.1 ------0.6 0.4 ---65.3 .299\2.2 83-84 62.0 _.....---3.3 ------0.6 0.4 ._-66.3 3132 2.1 84-85 66.7 ------3.3 ------0.6 0.4 ---71.1 3273 2.2 85-86 66.7 1.3 0.2 3.6 10.9 0.4 0.6 0.4 12.8 84.1 3433 2.4 8b-;i7 67.2 1.3 0.2 3.7 10.9 0.4 0.6 0.4 12.8 84.8 3594 2.3 87-08 66.4 30.0 5.9 6.7 10.9 0.4 17.1 3.6 58.0 141.0 3754 3.7 83-S~1 59.0 30.0 5.9 9.6 10.9 0.4 17.1 3.6 58.0 136.6 39\5 3.5 89-90 .54.5 58.7 11.6 16.6 10.9 0.4 17 .1 3.6 86.7 173.4 4075 4.2 90-91 50.2 58.7 11.6 22.5 10.9 0.4 17.1 3.6 86.7 175.0 4285 .4.1 91-92 47.1 66.8 13.2 26.6 10.9 0.4 17.1 3.6 94.8 165.7 4495 4.1 "co 92-gJ 42.4 95.5 HI.9 34.5 10.9 .0.4 17.1 3.6 123.5 223.3 4705 4.7 93-94 38.9 95.6 18.9 41.9 10.9 0.4 17.1 3.6 123.5 227.2 4915 4.6 94-95 ,39.4 124.2 24.6 50.7 10.9 0.4 17.1 3.6 152.2 270.9 5125 5.3 %-96 34.5 152.9 30.3 56.9 10.9 0.4 17.1 3.6 180.9 306.6 5385 5.7 96-97 &8.3 202.8 40.1 64.1 10.9 0.4 17.1 3.6 230.8 ~67.3 5645 6.5 97-96 25.4 202.6 40.1 69.1 10.9 0.4 17.1 3.6 230.8 369.4 5904 6.3 98-99 27.4 202.8 40.1 74.1 10.9 0.4 17.1 3.6 230.8 376.4 6164 6.1 99-2000 22.6 252.7 49.9 80.4 10.9 0.4 3.3.5 6.8 297.1 457.2 6424 7.1 00-01 12.2 252.7 49.9 83.B 10.9 0.4 33.5 6.8 297.1 450.2 6'189 6.9 01-02 11.0 252.7 49.9 86.9 10.9 0.4 33.5 6.8 297.1 452.1 6555 6.9 02·03 4.8 252.7 49.9 90.4 10.9 0.4 33.5 6.8 297.\449.4 6620 6.8 ~ 03-04 4.B 252.7 49.9 93.3 10.9 0.4 33.5 6.8 297.1 452.3 6686 6.8 04·05 3,6 252.7 49.9 96.6 10.9 0.4 33.5 6.8 297.1 454.4 6751 6.7 05-06 3.6 302.6 59.7 99.6 10.9 0.4 33.5 6.8 347.0 517.1 6CJl 7 7.6 06-07 3.6 302.6 59.7 102.7 10.9 0.4 33.5 6.8 347.0 520.2 6882 7.5 07-08 3.6 302.6 59.7 105.8 10.9 0.4 33.5 6.8 347.0 523.3 6948 7.5 08-09 3.6 302.6 59.7 108.9 10.9 0.4 33.5 6.8 347.0 526.4 7013 7.5 09-10 3.6 302.6 59.7 112.1 10.9 0.4 33.5 6.8 347.0 529.6 7079 7.5 lO-1l 3.6 302.6 59.7 115.4 10.9 0.4 33.5 6.8 3117.0 532.9 7\44 7.5 ))) ')) TABLE---i:l.Anchorage-Cook Inlet Area.Low Load Growth Scenario.Case 1,5%Inflation New Ilydroelectric Transmission Total.cost _~~.J:oallJ!:£.iLCapac!!L_Costs __._2Ystems Total Total lota 1 Sys tem of Existing Investment OH&R Coal lnves tmentOM&R Investment OM&R Investment System Consumption,Average Power _Year _~~illL Costs Cos~Costs ~Costs._.D!ili _.fo sts__Costs Costs fasts,$I-lMKWH Costs.C/KWH 78-79 29.7 ---"'-----------0.7 0.4 ---30.8 2376 1.3 79-80 39.1 ------------0.7 0.4 -.-40.1 2568 1.6 1 80-81 45.7 ---_..----------0.7 0.4 ---46.8 2706 1.7 81-62 47.9 ---------------0.7 0.5 --.49.1 2650 1.7 62-63 59.5 ------3.1 ------0.7 0.5 ---63.9 2991 2.1 63-84 63.6 ------3.3 ------0.7 0.5 ---68.1 3132 2.2 j ll4-65 68.7 _.----3.3 ------0.7 0.5 ---73.3 3273 2.2 85-86 68.9 2.0 0.4 3.6 14.6 0.6 0.7 0.5 17.5 90.8 3433 2.6 I 66-87 69.8 2.0 0.4 3.9 14.8 0.6 0.7 0.5 17 .5 92,7 3594 ~.6 87-98 67.1 46.6 9.2"7.3 14.0 •0.6 24.1 5.4 65.5 175.2 3754 4.7 86-89 60.6 46.6 9.7 11.1 14.6 0.6 24.1 5.7 65.5 173.2 3915 4.4 89-90 56.4 95.7 19.9 20.1 14.6 0.7 24.1 6.0 134.6 237.8 4075 5.8 90-91 52.5 95.7 20.9 28.6 14.8 0.7 24.1 6.3 134.6 243.6 4285 5.7 91-92 49.6 111.1 24.0 35.2 14.0 0.7 24.1 6.6 150.0 267.2 4495 5.9 "-J '-D 92-93 47.4 168.0 37.4 48.4 14.6 0.6 2U 6.9 206.9 347.8 4705 7.4. 61.3 24.1 362.0 491593-94 46.5 168.0 39.2 14.8 0.1:1 7.3 206.9 7.4 94-95 46.5 230.7 51.6 77.9 14.8 0.9 24.1 7.7 269.6 456.2 5125 6.9 95-96 43.8 296.5 67.3 92.2 14.8 0.9 24.1 8.1 335.4 547.7 5385 10.2 96-97 36.3 416.7 94.3 108.6 14.8 0.9 24.1 8.5 455.6 704.2 564f.12.5 97-98 37.7 416.7 99.0 122.6 14.8 1.0 24.1 8.0 455.6 724.8 5904 12.3 S8-99 37.5 416,7 103.9 138.4 lUI 1.0 24.1 9.3 455.6 ·745.7 6164 12.1 99-2000 31.7 555.8 136.4 ,156.6 14.8 1.1 68.3 18.4 638.9 983.1 6424 15.3 00·01 16.7 555.8 143.3 172.0 14.8 1,1 68.3 19.3 638.9 991.3 6498 15.3 01-02 15.3 555.8 lSO.4 186.5 14.8 1.2 60.3 20.3 636.9 1012.6 6555 15.4 02-03 5.4 555.8 157.9 204.8 H.ll 1.3 6B.3 21.3 638.9 1029.6 6620 15.5 03·04 5.5 555.0 165.0 221.6 14.8 1.3 68.3 22.4 636.9 1055.5 6686 15.8 04-05 3.6 555.8 174.1 240.4 14.8 1.4 68.3 23.5 638.9 1081.9 6751 16.0 05-06 3.7 742.3 219.4 259.11 14.8 1.5 68.3 24.6 825.4 1334.4 6817 19.6 06-07 3..9 742.3 230.4 280.8 14.8 1.5 66.3 25.9 825.4 1367.9 6882 19.9 07-08 4.0 742.3 241.9 303.6 14.8 1.6 68.3 27.2 825.4 1403.7 6948 20.2 08-09 4.1 742.3 254.0 '328.2 14.6 1.7 68.3 211.5 825.4 1441.9 7013 20.6 09-1O 4.2 472.3 266.7 354.6 14.8 1.8 68.3 30.0 825.4 1462.7 7079 20.9 10-11 4.4 742.3 200.1 382.9 14.8 1.9 68.3 31.5 825.4 1526.2 7144 21.4 LABlE U·Anchorage-Cook Inlet Area.Low Load Growth Scenario.Case 2.0%Inflation New Ilydroelectrlc Transmission Total \fast New Coal f1 red Ca~1 ty Costs ~ems Total Total Total System of Existing Investment 'OM&R-COar-ro~ve5tmenr-OH&JC tnvestment--OFi&R Investment System Consumption.Average Power Year _Capacity ~~Costs Costs__foSll_fQ.Ul Costs fQili..Costs Costs,$MNKIJIi Costs,¢/KWlj 76-79 33.1 ...--------------0.6 0.4 ---34.1 2376 1.4 79-80 42.2 ---------------0.6 0.4 ---43.2 2568 1.7 80-81 48.2 ---------------0.6 0.4 ---49.2 2706 1.8 81-82 52.8 --------- ------0.6 0.4 ---53.8 2850 1.9 82-83 61.1 ------3.1 .-----0.6 0.4 ---65.3 2991 2.2 83-B4 62.0 _.----3.3 ------0.6 0.4 -.-.66.3 3132 2.1 84-85 66.7 ------3.3 ------0.6 0.4 ---71.1 3273 2.2 85-86 66.7 1.3 0.2 3.6 10.9 0.4 0.6 0.4 12.8 84.1 3433 2.4 86-87 67.2 \.3 0.2 3.7 10.9 0.4 0.6 .0.4 12.8 84.8 3594 2.3 81-B8 66.4 30.0 5.9 6.7 10.9 0.4 17.1 3.6 58.0 141.0 3754 3.7 8£1-89 59.0 30.0 5.9 9,6 10.9 0.4 17.1 3.6 58.0 136.6 3915 3.5 89-90 54.5 58.7 11.6 16.6 10.9 0.4 17.1 3.6 86.7 173.4 4075 4.2 90-91 50.2 58.7 11.6 22.5 10.9 0.4 17.1 3.6 86.7 175.0 4285 4.1 91-92 41.1 66.8 13.2 26.6.10.9 0.4 17.1 3.6 94.8 185.7 4495 4.1 OJ 0 92-93 42.4 95.5 18.9 34.5 10.9 0.4 17 .1 3.6 123.5 223.3 4705 4.7 93-94 38.9 95.5 IB.9 41.9 10.9 0.4 17:1 3.6 123.5 227.2 4915 4.6 94-95 39.4 95.5 18.9 46.3 10.9 0.4 35.9 5.6 142.3 252.4 5125 4.9 95-96 34.5 124.2 24.6 55.3 10.9 0.4 35.9 5.6 171.0 290.9 5305 5.4 96-97 28.3 152.9 30.3 64.1 10.9 0.4 35.9 5.6 199.7 :127 .9 5645 5.8 97-98 25.4 202.8 40.1 69.2 10.9 0.4 35.9 5.6 249.6 389.8 5904 6.6 98-99 27.4 202.8 40.1 74.1 10.9 0.4 35.9 5.6 249.6 396.7 6164 6.4 9'1-2000 22.6 202.5 40.1 flO.4 10.9 0.4 35.9 5.6 249.6 397.9 6424 6.2 00-01 12.2 252.7 49.9 83.8 10.9 0.4 52.4 8.8 316.0 470.6 6489 7.2 01·02 11.0 252.7 49.9 86.9 10.9 0.4 52.4 8.8 316.0 412.5 6555 7.2 02-03 4.8 525.1 49.9 90.4 10.9 0.4 52.4 8.8 Ji6 ..0 469.8 6620 7.1 OJ-04 4.8 252.7 49.9 93.4 10.9 0.4 52.4 8.8 316.0 412.8 •6686 7.1 04-05 3.6 252.7 49.9 96.6 10.9 0.4 52.4 8.8 316.0 474.8 6751 7.0 05-06 3.6 525.7 49.9 99.6 10.9 0.4 52.4 8.8 J16.0 477 .9 6017 7.0 06-07 3.6 252.7 49.9 99.6 10.9 0.4 52.4 8.8 316.0 480.9 6882 7.0 01-08 3.6 252.7 49.9 105.7 10.9 0.4 52.4 8.8 316.0 484.0 6948 7.0 08-09 3.6 252.7 49 ..9 108.9 10.9 0.4 52.4 8.8 316.0 487.1 7013 6.9 09-10 3.6 252.7 49.9 112.1 10.9 0.4 52.4 8.8 316.0 490.3 7079 6.9 10-11 3.6 252.7 49.9 115.4 10.9 0.4 52.4 8:8 316.0 493.6 7144 6.9 )))., '))) TABLE_4.4.Anchorage-Cook Inlet Area,Low Load Growth Scenario,Case 2,5%Inflation New IlYdroe1ectrtc Transm!5S ton Total Cost New Coal ft'ml capac~'!y'Costs ~s Total Total Total System of Existing Tii'ilestmenr--OJ;oa~lovestment-OM11C Trlvestment -liJf&R Investment System Consumption.Average Power -!lli-Capact ty Costs £2sts Cos~_Cost_s~f.~_C!lS~Costs COsts Cos 15 •$-'1':!~Costs,¢/K"'~ 78-79 29.7 ---------------0.7 0.4 ---30.8 2376 1.3 79·80 39.1 ------------0.7 0.4 ---40.1 2566 1.6 80·81 45.7 ------------_..0.1 0.4 ---46.8 2706 1.7 81-82 47.9 ---------------0.7 0.5 ---49.1 2850 1.7 82-83 59.5 ------3.1 ------0.7 0.5 ---63.9 2991 2.1 83-84 63.6 ------3.3 ------0.7 0.5 ---68.1 3132 2.2 84-65 68.7 ------3.3 -----.0.7 0.5 ---73.3 3273 2.2 65-86 68.9 2.0 0.4 3.6 14.8 0.6 0.7 0.5 17.5 90.8 3433 2.6 86-87 69.8 2.0 0.4 )(14.8 0.6 0.7 0.5 17 .5 92.7 3~94 2.f> 81-88 6'7'.1 46.6 9.2 7.J 14.8 0.6 24.1 5.4 85.5 175.2 3754 4:7 88-69 60.6 46.6 9.7 11.1 14.6 0.6 ,24.1 5.7 85.5 '173.2 3915 4.4 89-90 56.4 95.7 19.9 20.1 14.8 0.7 24.1 6.0 134.6 237.8 4075 5.8 90·91 52.5 95.7 20.9 23.6 14.6 0.7 24.1 6.3 134.6 243.6 4285 5.7 91-92 49.8 111.1 24.8 35.2 14.6 0.7 24.1 6.6 150.0 267.2 4495 5.9 CO 92-')3 47.4 Hi8.0 37.4 43.4 14.8 0.8 24.1 6.9 206.9 347.8 4705 7.4...... 93-94 46.5 166.0 39.2 61.3 14.8 0.8 24.1 7.3 206.9 362.0 4915 7.4 94-95 48.5 168.0 39.3 71.2 14.8 0.9 63.6 9.7 246.4 416.0 5125 8.1 95-96 43.8 233.C1 54.4 89.5 14.8 0.9 63.6 10.3 312.2 511.1 5385 9.5 96-97 36.3 302.9 70.8 108.6 14.8 0.9 63.6 10.8 381.3 603.7 5645 10.8 97-98 37.7 429.1 99.1 122.6 14.8 1.0 63.6 11.3 507.5 779.2 5904.13.2 93-99 37.5 429.1 104.1 138.4 14.8 1.0 63.6 11.9 507.5 800.4 6164,13.0 99-2000 31.1 429.1 109.3 156.6 14.8 1.1 63.6 12.5 501.5 818.7 '6424 12.7 00-01 16.7 575.2 143.4 172.0 14.8 1.1 110.0 22.1 700.0 1055.3 6489 16.3 01-02 15.3 575.2 150.6 106.4 14.8 1.2 110.0 23.2 700.0 1076.7 6555 16.4 02-03 5.4 575.2 158.1 204.9 14.8 1.3 110.0 24.4 700.0 1094.1 6620 16.5 03-04 5.5 575.2 166.1 221.6 ,14.{j 1.3 110.0 25.6 700.0 1120.1 6666 16.7 04·05 3.6 575.2 174.4 240.4 1Ul 1.4 110.0 26.9 700.0 1146.7 6751 17.0 OS-Of!3.7 575.2 183.1 259.8 14.8 1.5 110.0 28.2 700.0 1176.3 6817 17 .2 06·07 3.9 575.2 192.2 280.8 14.8 1.5 110.0 29.6 700.0 1208.0 6882 17.5 07-08 4.0 575.2 201.8 303.6 14.0 1.6 110.0 31.1 700.0 1242.1 6948 17.9 08-09 4.1 575.2 211.9 320.2 14.8 1.7 110.0 32.7 700.0 1278.6 7013 18.2 09-10 4.2 575.2 222.5 354.6 14.0 1.8 110.0 34.3 700.0 1317 .4 7079 10.6 10-11 4.4 575.2 233.7 302.9 14.8 1.9 110.0 36.0 700.0 1358.9 7144 19.0 TABLE 4.5.Anchorage-Cook Inlet Area,Low Load Growth Scenario,Case 3,0%Inflation New lIydroelectrlc Transmission Total Cost ~'1....r;Q!!l!..!!ed QQ!!f.!!Y__Costs _~stems Total Total Total System of Existing Investl/lent OM&R Coa 1 Inves tment-~OM&1f-Investment OM&R Investment System Consumption.Average Power ..J!!!.L..Capac!ty Costs Costs ~~CostL._£Qrti ~!.L..~Costs Costs,$_~.!:!!L_Costs~ 78-79 33.1 ---------------0.6 0.4 ---34.1 2316 1.4 79-80 42.2 ---------------0.6 0.4 ---43.2 2568 1.7 80-81 48.2 --------.------0.6 .0.4 ---49.2 2706 1.8 81-132 52.8 ----.----------0.6 0.4 ---53.6 .2850 1.9 82-83 61.1 -.----3.1 ---.--0.6 0.4 ---65.3 2991 2.2 83-84 62.0 ------J.3 ------0.6 0.4 ---66.3 3132 2.1 84·65 66.7 -----.3.3 ---,--0.6 0.4 ---71.1 3273 2.2 85-86 66.7 1.3 0.2 3.6 10.9 0.4 0.6 0.4 12.8 84.1 3433 2.4 86-87 67.2 1.3 0.2 3.7 10.9 0.4 0.6 0.4 12.8 84.8 3594 2.3 87-88 66.4 30.0 5.9 6.7 10.9 0.4 17 .1 3.6 58.0 141.0 3754 3.7 89-89 59.0 30.0 5.9 9.6 10.9 0.4 17 .1 3.6 58.0 136.6 3915 3.5 89-90 54.5 58.7 11.6 16.6 10.9 0.4 17.1 3.6 86.7 173.4 4075 4.2 90-91 50.2 58.7 11.6 22.5 10.9 0.4 17 .1 3.6 86.7 175.0 4285 4.1 CO 91-92 47.1 66.8 13.2 26.6 10.9 0.4 35.9 5.6 113.6 206.0 4495 4.6 N 92-93 42.4 66.8 13.2 30.3 10.9 0.4 35.9 5.6 113.6 205.0 4705 4.4 93-94 38.9 95.5 HI.9 38.9 10.9 0.4 35.9 5.6 142.3 244.5 4915 5.0 94-95 39.4 95.5 13.9 20.6 155.9 1.0 35.9 5.6 287.3 372.3 5125 7.3 95-96 34.5 95.5 111.9 21.6 155.9 1.0 35.9 •5.6 287.3 368.4 5385 6.8 96-97 28.3 95.5 18.9 27.9 155.9 1.0 35.9 5.6 207.3 368.5 5645 6.5 97-98 25.4 .95.5 111.9 32.2 155.9 1.0 35.9 5.6 287.3 369.9 5904 6.3 98-~9 27.4 95.5 18.9 26.4 155.9 1.0 35.9 5.6 287.3 376.1 6164 6.1 99-2000 22.6 95.5 18.9 7.9 204.2 1.6 35.9 5.6 335.6 391.7 6424 6.1 llO-Ol 12.2 95.5 18.9 B.O 204.2 1.6 35.9 5.6 335.6 3B1.4 6489 5.9 01-02 11.0 95.5 18.9 IJ.1 204.2 1.6 35.9 5.6 335.6 380.3 6555 5.6 02-03 4.8 95.5 111.9 9.3 204.2 1.6 35.9 5.6 335.6 375.3 6620 5.7 03·04 4.8 95.5 18.9 10.6 204.2 1.6 35.9 5.6 335.6 376.6 6686 5.6 0~-05 3.6 95.5 10.9 12.0 204.2 1.6 35.9 5.6 335.6 376.6 6751 5.6 05-06 3.6 95.5 18.9 13.2 204.2 1.6 35.9 5.6 335.6 378.0 6817 5.5 G6·07 3.6 95.5 IM.9 14.6 204.2 1.6 35.9 5.6 335.6 379.4 6692 5.5 07-06 3.6 95.5 18.9 16.0 204.2 1.6 35.9 5.6 335.6 380.8 6948 5.5 08·09 3.6 95.5 18.9 17 .4 204.2 1.6 35.9 5.6 335.6 382.2 7013 5.4 09-10 3.6 95.5 18.9 18.9 204.2 1.6 35.9 5.6 335.6 383.7 7079 5.4 10-11 3.6 95.5 18.9 20.4 204.2 1.6 35.9 5.6 335.6 385.2 7144 5.4 » -) TABLE 4.6.Anchorage-Cook Inlet Area;Low Load Growth Scenario.Case 3;5%Inflation New Hydroelectric·Transmfssion Total Cost New Coal FlredCapacftir--Costs S.1s tems Total Total Total System of Existing TilvestmeiitoM&R COa Tnves tmentoM&R Investment OM&R·Inves tillent System Consumption.Average Power ~Capacity Costs Costs Costs Costs Costs Costs _Costs Costs Costs,$MMKWH Costs.II/KWH-.- 78-79 29.7 ---------------0.7 0.4 ---30.8 2376 1.3 79-80 39.1 ---------0_---0.7 0.4 ---40.1 2568 1.6 80-81 45.7 ---------------0.7 0.4 ---46.8 2706 1.7 81-82 47.9 ----~!I'---------0.7 0.5 -_.-49.1 2850 1.7 82-83 59.5 ----..3.1 ------0.7 0.5 ---63.9 2991 2.1 83-84 63.6 ------3.3 ------0.7 0.5 ---6B.l 3132 2.2 84-85 68.7 .......----3.3 ------0.7 0.5 ---73.3 3273 2.2. 85-86 6B.9 2.0 0.4 3.6 14.B 0.6 0.7 0.5 17 .5 90.8 3433 2.6 86-87 69.3 2.0 iJ.4 3.9 14.8 0.6 0.7 0.5 17 .5 92.7 3594 2.6 B7-8e 67.1 46.6 9.2 7.3 14 ..8 0.6 24.1 5.4 85.5 175.2 3754 4.7 88-89 60.6 46.6 9.7 11.1 14.a 0.6 24.1 5.7 85.5 173.2 3915 4.4 89-90 56.4 95.7 19.9 20.1 14.8 0.7 24.1 6.0 134.6 237.8 407S 5.B 90-91 52.5 95.7 20.9 28.6 14.8 0.7 24.1 6.3 134.6 243.6 4285 5.7 91-92 49.8 111.1 24.8 35.3 14.8 0.7 58.2 8.4 184.1 303.1 4495 6.7 COw 92-93 47.4 111.1 26.1 42.5 14.8 0.8 58.2 8.8 184.1 309.7 4705 6.6 93-94 46.5 170.a 29.2 56.9 14.8 0.8 58.2 9.3 243.8 396.5 4915 8.1 94-95 48.5 170.8 41.1 31.7 319.9 2.1 58.2 9.7 548:9 682.0 5125 13.J 9S-96 43.8 110.8 43.2 35.0 319.9 2.2 50.2 10.2 548.9 633.3 5385 12.7 96-97 3&.3 170.8 45.4 47.4 319.9 2.3 56.2 10.7 54B.9 691.0 5645 12.2 97-96 37.7 170.8 47.6 56.9 319.9 2.4 5n.2 11.3 54B.9 704.8 5904 11.9 98-99 37.5 170.8 ~O.O 68.1 319.9 2.5 68.2 11.8 548.9 718.8 6164 11.7 99-2000 31.7 170.8 52.5 15.4 449.7 4.2 58.2 12.4 67B.7 794.9 6424 12.4 00-01 16.7 170.8 55.0 16.3 449.7 4.5 58.2 13.5 678.7 784.8 5489 12.1 01-02 IS.3 170.8 57.9 17.4 449.7 4.7 5fU 13.7 678.7 787.7 6555 12.0 02-03 5.4 170.6 60.8 21.2 449.7 4.9 S8.2 14.4 678.7 765.4 6620 11.9 03-04 5.5 170.8 63.8 25.1 449.7 5.2 511.2 15.1 6711.7 793.4 6666 11.9 04-05 3.6 170.8 67.0 29.9 449.7 5.4 58.2 15.9 670.7 BOO.5 6751 11.9 05-06 3.7 17Q.a 70.4 34.3 449.7 5.7 56.2 16.7 670.7 809.5 6816 11.9 06·07 3.9 170.6 73.9 40.0 449.7 6.0 58.2 17.5 678.7 B20.0 6882 11.9 07-08 4.0 170.8 77 .6 45.9 449.7 6.3 5f!.2 16.4 678.7 830.9 6948 11.9 08-09 4.1 170.8 81.5 52.4 449.7 6.6 5i1.2 19.3 678.7 842.6 7013 12.0 09-10 4.2 170.8 8li.5 59.7·449.7 6.9 58.2 20.2 676.7 1155.2 7079 12.1 10-11 4.4 170.8 89.8 67.~449.7 7.3 58.2 21.3 676.7 669.0 7144 12.2 TABLE 4.7.Anchorage-Cook Inlet Area.Medium Load Growth Scenario,Case 1.0%Inflation New IIydroelectrfc Transm1 ss 10n Total Cost _New Coa.t.f.!red cupac1_~_Costs Systems Total Total Total System of Ex1stfng 1nvestment OM&R Coa Investment OM&R lilves tment OM&R Investment System Consumption.Average Power -.!lli.-CapacHy Costs CosU Costs Cosls f~Cosh Costs Costs Costs,$MMKWH Costs.¢/KWH 7B-79 33.1 ---------------.6 .4 ---34.1 2531 1.3 79-BO 42.2 ---------------.6 .4 _.-.43.2 2801 1.5 80-Bl 48.2 ---------'_..----.6 .4 ---49.2 3041 1.6 81-82 52.8 ---------.-----.6 .4 ---53.8 3281 1.6 82-83 61.1 28.1 5.7 6.5 ------.6 .4 29.3 103.0 3521 2.9 83-84 62.0 28.1 5.1 9.2 ------.6 .4 29.3 106.6 3761 2.8 04-85 66.7 28.7 5.7 11.8 ------.6 .4 29.3 114.0 4001 2.8 85-06 66.7 58.7 11'.6 10.5 10.9 .4 17.1 3.6 06.7 107.6 4329 4.3 86-87 67.2 58.7 11.6 24.19 10.9 ..4 17.1 3.6 fJ6.7 193.7 4657 4.2 87-0B"66.4 87.4 17 .3 29.9 10.9 0.4 17 .1 3.6 .115.4 233.0 4985 4.7 88-89 59.0 87.4 17.3 36.2 10.9 0.4 17 .1 3.6 115.4 231.9 5313 4.4 89-90 54.5 116.1 23.0 46.4 10.9 0.4 17.1 3.6 144.1 272.0 5641 4.B 90-91 50.2 116.1 23.0 52.9 10.9 0.4 17.1 3.6 144.1 274.2 6063 4.5 91-92 47.1 152.9 30.3 61.9 10.9 0.4 17.1 3.6 100.9 324.2 6485 5.0 CO 92-93 42.4 202.8 40.1 70.2 10.9 0.4 17.1 3.6 230.8 387.5 6907 5.6-Po 93-94 38.9 202.8 40.1 77 .9 10.9 0.4 17.1 3.6 230.8 391.7 7329 5.3 94-95 39.4 202.8 40.1 114.6 10.9 0.4 17.1 3.6 230.8 39fJ.9 1751 5.1 95-96 34.5 252.7 49.9 g.,6 10.9 0.4 17.1 3.6 2fJO.7 463.7 8311 5.6 96-97 28.3 302.6 59.7 106.8 10.9 0.4 33.5 6.8 341.0 549.0 llll71 6.2 97-9B 25.4 352.5 69.5 116.9 10.')0.4 33.5 6.fJ 396.9 615.9 9431 6.5 98-99 27.4 J53.5 69.5 126.7 10.9 0.4 33.5 6.8 396.9 627.7 9991 6.3 99-2000 22.6 402.4 79.3 130.5 10.9 0.4 33.5 6.6 446.8 694.4 10551 6.6 00-01 12.2 402.4 79.3 146.3 .10.9 0.4 33.5 6.8 446.ll 691.8 10863 6.4 01-02 11.0 402.4 79.3 IS·!.3 10.9 0.4 33.5 6.8 446.8 698.6 11175 6.3 02·03 4.8 452.3 B9.1 162.5 10.9 0.4 33.5 6.8 496.7 760.3 114117 6.6 03-04 4.8 452.3 89.1 170.7 10.9 0.4 33.5 6.8 496.7 767.9 11799 6.5 04-05 3.6 452.3 89.1 179.4 10.9 0.4 33.5 6.8 496.7 716.0 12111 6.4 05-06 3.6 502.2 9£\.9 108.0 10.9 0.4 50.0 10.0 563.1 864.0 12423 6.9 06-07 3.6 502.2 90.9 196.0 10.9 0.4 50.0 .10.0 563.1 072.8 12735 6.8 07-08 3.6 502.2 9ll.9 205.9 10.9 0.4 50.0 10.0 563.1 fJ81.9 13047 6.8 08-09 3.6 502.2 9ll.9 215.1 10.9 0.4 50.0 10.0 563.1 B91.1 13359 6.7 09·]0 3.6 502.2 98.9 224.6 10.9 0.4 50.0 10.0 563.1 901.6 13671 6.6 10-11 3.6 552.1 106.7 234.2 10.9 0.-1 50.0 10.0 613.0 969.9 139B3 6.9 ))J ) TJ\BLE 4.8.Anchorage-Cook Inlet Area,Medium Load Growth Scenario.Case 1,5%Inflation ----~" Total Cost New Hydroelectric Transml ss Ion New Coa 1 !'Ired Capacl ty Costs Systems 0 Total Total Total System of Existing Jnvestment oiiiR-Coa'--Investment OHIR "Investment ""MAR Investment Systetn Consumption,Average Power ~"~~Costs ~~ll.Costs ~~illL-.Costs ~tL-£!im Costs Costs l $I'J~KWH Costs l UI(WH 78-79 29:7 ---------------0.7 0.4 ---30.8 2531 1.2 79-80 39.1 ---------...~"---0.7 0.4 ---40.2 2801 1.4 80-81 45.7 ---------------0.7 0.4 ---46.8 3041 1.5 81-82 47.9 ---------------0.7 0.5 ---49.1 3281 1.5 62-63 59.5 34.9 6.9 6.5 ------0.7 0.5 35.6 109.1 3521 3.1 83-84 63.6 34.9 7.2 9.2 -----0.7 0.5 35.6 116.1 3761 3.1 84-85 68.7 34.9 7.6 11.8 ._----0.7 0.5 35.6 124.3 4001 3.1 85-86 68.9 77.3 16.4 18.1 14.6 0.6 23.0 4.9 115.1 .224.0 4329 5.2 86-87 69.8 77.3 17.2 25.3 14.0 0.6 23.0 5.1 115.1 233.2 4657 5.0 87-88 67.1 121.9 26.8 32.7 14.8 0.6 23.0 5.4 159.7 292.3 4985.5.9 60.6 121.9 211.2 14.8 23.0 5.7 159.7 296.5 . 68-89 41.6 0.6 5313 5.6 89-'90 56.4 171.0 39.3 56.3 14.8 0.7 23.0 6.0 208.8 367.5 5641 6.5 90-91 52.5 171.0 41.3 67.3 14.8 0.7 23.0 6.3 20B.8 376.9 6063 6.2 91-92 49.8 240.6 56.9 82.2 14.0 0.7 23.0 6.6 278.4 474.6 6485 7.3 OJ 47.4 339.5 90.60192-93 79.2 •14.8 0.8 23.0 6.9 377 .3 608.6 6907 8.8 93·94 46.5 339.5 83.2 1'13.9 14.8 0.3 23.0 7.2 377 .3 628.9 7329 8.6 94~95 48.5 339.5 87.3 130.1 14.8 0.9 23.0 7.6 377 .3 659.3 7751 8.5 95-96 43.8 454.0 114.2 153.3 14.8 0.9 23.0 8.0 491.8 B12.0 6311 9.7 96-97 36.3 574.2 143.5 160.8 14.8 0.9 63.0 16.0 652.0 1029.5 6871 11.6 97-98 37.7 700.4 175.5 207.2 14.8 1.0 63.0 16.6 778.2 1216.2 9431 12.9 98-99 37.5 700.4 184.2 236.7 14.8 1.0 63.0 17.4 778.2 1255.0 9991 12.6 99-2GOO 31.8 839.5 220.8 269.7 14.8 1.1 63.0 18.3 917.3 1459.0 10551 113 .8 00-01 16.7 839.5 231.8 300.2 14.11 1.1 63.0 19.2 917.3 1486.3 10863 '13.7 01-02 15.3 839.5 243.4 331.2 14.8 1.2 63.0 20.2 917.3 1528.6 11175 13.? 02-03 5.4 1000.6 207.2 368.3 14.8 1.3 63.0 21.2 1078.4 1761.B 11487 15.3 5.5 1000.6 .301.5 405.2 14.8 1.3 63.0 22.2 1078.4 1814.1 11799 15.403-04 04-05 3.6 1000.6 316.6 446.6 14.8 1.4 63.0 23.3 1070.4 1069.9 12111 15.4 05-06 3.7 1107.1 369.0 490.4 14.8 1.5 116.7 34.9 1319.6 2218.1 12423 17 .8 06-07 3.9 1187.1 387.5 53(\.4 14.0 1.5 116.7 36.6 1318.6 2286.5 12735 17 .9 07-08 4.0 1187.1 406.8 590.9 14.0 1.6 116.7 3a.5 1318.6 2360.4 13047 18.1 08 ..09 4.1 1181.1 427.2 648.1 14.8 1.7 116.7 40.4 1318.6 2440.1 13359 18.3 09-10 .4.2 1181.1 448.5 71 0.1 14.8 1.8 116.7 42.4 1318.6 2525.6 13671 18.5 10-11 4.4 1425.1 517.7 777.3 14.8 1.9 116.7 44.6 1556.6 2902.5 13983 20.7 TABLE 4.9.Anchorage-Cook Inlet Area.Medium Load Growth Scenario,Case 2,0%Inflation ----~ Total C~st :.;New f1ydroe1ectrlc TransmissIon New Coal fired Capa~1tl---Costs Systems Total Total Total System of Existin9 Investment Or~&R Coal Investment OM&R Investment OM&R Investment System ConsumptIon.Average Power ~Capacity Costs fQill Costs Costs fllil Costs_Costs ~-Costs I $MMKWIt Costs I ¢/KWtJ 78-79 33.1 ------.0._0-._-0.6 0.4 ---34.1 2531 1.3 H-BO 42.2 ---------------0.6 0.4 ---43.2 2801 1.5 60-81 48.2 .-.------------0.6 0.4 ---49.2 3041 1.6 81-B2 52.3 ---------._----0.6 0.4 ---53.8 3281 1.6 82-133 61.1 28.7 5,7 6.5 ------0.6 0.4 29.3 103.0 3521.2.9 83-84 62.0 28.7 5.7 9.2 ------0.6 0.4 29.3 106.6 3761 2.8 lJ4-85 66.7 28.7 5.7 11.8 ---._.0.6 0.4 29.3 114.0 4001 2.8 85-86 66.7 50.7 11.6 18.5 10.9 0.4 17 .\3.6 1J6.7 187.6 4329 4.3 86-87 67.2 58.7 11.6 24.19 10.9 0.4 17 .1 3.6 86.7 193.7 4657 4.2 87-88 66.4 87.4 17.3 29.9 10.9 0.4 17 .1 3.6 115.4 233.0 4985 4.7 IlS-89 59.0 87.4 17.3 36.2 10.9 0.4 17 .1 3.6 115.4 231.9 5313 4.4 89-90 54.5 87.4 17.3 42.5 10.9 0.4 35.9 5.6 134.2 254.5 5641 4.5 90-91 50.2 116.1 24.6 50.1 10.9 0.4 35.9 5.6 162.9 293.8 6063 4.8 91-92 47.1 152.9 31.9 59.1 10.9 0.4 35.9 5.6 199.7 343.8 .6485 5.3 co 0)92-93 42.4 202.8 41.7 70.2 10.9 0.4 35 ..9 5.6 249.6 409.9 6907 5.9 93-94 38.9 202.8 4].7 77.9 10.9 0.4 35.9 5.6 249.6 414.1 7329 5.6 94-95 39.4 202.6 41.7 84.6 10.9 0.4 35.9 5.6 249.6 421.3 7751 5.4 95-96 34.5 252.7 51.5 94.6 10.9 0.4 35.9 5.6 299.5 486.1 6311 5.0 96-97 28.3 302.6 61.3 106.8 10.9 0.4 52.4 8.8 365.9 571.5 8U7l 6.4 97-98 25.4 302.6 61.3 116.9 10.9 0.4 52.4 8.8 365.9 578.7 9431 6.1 98-99 27.4 352.5 71.1 126.7 10.9 0.4 52.4 6.8 415.0 650.2 9991 6.5 99~2000 22.6 352.5 71.1 138.5 10.9 0.4 52.4 8.8 415.8 657.2 10551 6.2 00-01 12.2 402.4 80.9 146.3 10.9 0.4 52.4 8.8 465.7 714.3 10863 6.6 01-02 11.0 402.4 00.9 154.3 10.9 0.4 52.4 0.0 465.7 721.1 11175 6.4 02-03 4.8 402.4 00.9 162.5 10.9 0.4 52.4 ·8.8 465.7 723.1 11487 6.3 . 03-0~3.6 452.3 90.1 110.7 10.9 0.4 52.4 0.8 515.6 789.8 11799 6.7 04-05 3.6 452.3 90.7 179.4 10.9 0.4 52.4 8.8 515.6 798.5 12111 .6.6 05-06 3.6 452.3 90.7 lB8.0 10.9 0;4 52.4 8.6 515.6 Il07.I 12423 6.5 06-07 3.6 452.3 90.1 196.8 10.9 0.4 52.4 6.6 515.6 815.9 12735 6.4 07-08 3.6 502.2 100.5 205.9 10.9 0.4 66.9 12.0 582.0 904.4 13047 6.9 08-09 3.6 502.2 100.5 Z15.1 10.9 0.4 68.9 12.0 582.0 913.6 13359 6.8 09-10 3.6 502.2 100.5 224.6 10.9 0.4 68.9 12.0 Sill.0 923.1'13671 6.7 10-11 3.6 &02.2 100.5 234.2 10.9 0.4 68.9 12.0 51l2.a 932.7 13903 6.7 c.)) i;. )) TABLE 4.10.Anchorage-Cook Inlet Area,Medium Load Growth Scenario,Case 2,5%Inflation-------- New Ilydroe 1ectrl c Transmission Total Cost New Coal fired caeac~ty Costs ~stems Total Total Total System of Existing InvesTmeiituFlm-oar lnVes tmentUJ1&r Tilves tmeii-t-OOll Investment System ConsumptIon,Average Power .1lli-Capac1 t.y Cos ts Cost~CostL_Costs -,~Costs Costs Costs Costs,$~--Costs,¢/KIIII_ 78-79 29.7 ---------------0.7 0:4 ---30.8 2531 1.2 79-80 39.1 ------------0.7 0.4 ---40.2 2801 1.4 80-81 45.7 -------_.-------0.7 0.4 ---46.8 3041 1.5 81-82 47.9 ---------""",-,".---..0.7 0.5 ---49.1.3281 1.5 B~-83 59.5 34.9 6.9 6.5 ------0.1 0.5 35.6 109.1 3521 3.1 83-84 63.6 34.9 7.2 9.2 -----0.7 0.5 35.6 116.1 3761 3.1 84-85 68.7 34.9 7.6 11.8 ------0.7 0.5 35.6 124.3 4001 3.1 85-86 68.9 77.3 16.4 18.1 14.3 0.6 23.0 4.9 115.1 224.0 4329 5.2 B6-ill 69.8 77.3 l7.2 25.3 14.8 0.6 23.0 5.1 115.1 233.2 4657 5.0 87-6!!67.1 H1.9 26.8 32.7 14.8 0.6 23.0 5.4 159.7 292.3 4985'5.9 8tl-89 60.6 121.9 28.2 41.6 14.8 0.6 23.0 5.7 159.7 296.5 5313 5.6 89-90 56.4 121.9 29.6 51.5 14.8 0.7 ,53.9 9.3 190.6 333.1 5641 6.0 90-9)52.5 173.5 41.3 63.7 14.8 0.7 53.9 9.7 242.2 410.1 6063 6.8 (Xl 91-92 49.8 243.1 56.9 70.3 14.8 0.7 53.9 10.2 311.8 507.8 6485 7.8 --.J 92-93 47.4 342.0 79.2 98.5 '14.8 0.8 53.9 10.7 410.7 647,4 6907 9.4 93-94 46.5 342.0 83.2 113.8 14.8 0.8 53.9 11.3 410 .-7 666.4 1329 9.1 94-95 48.5 342.0 87.3 130.1 14.0 0.9 53.9 11.8 410.7 689.3 7151 8.9 95-96 43.8 465.5 .114.2 153.3 14.8 0.9 53.9 12.4 534.2 858.8 8311 10.3 96-97 36.5 576.7 143.5 180.8 14.8 0.9 93.9 20.9 685.4 1067.8 8871 12.0 97-98 37.7 576.7 150.6 207.1 14.8 1.0 93.9 21.9 685.4 1103.8 9431 11.7 98-99 37.5 709.2 184.2 236.6 14.8 1.0 93.9 23.0 817 .9 1300.3 9991 13.0 99·2000 31.7 709.2 193.4 269.7 14.0 1.1 93.9 24.2 017.9 1338.1 10551 12.7 00-01 16.7 055.3 23\.7 300.2 14.8 1.1 93,9 25.4 964.0 1539.1 10063 14.2 01-02 15.3 855.3 243.3 331.2 lUI 1.2 93.9 26.7 964.0 1581.7 11175 14.1 ' 02-03 5.4 955.3 225.5 3u8.3 14.8 1.3 93.9 28.0 964.0 1592.5 11407 13.9 03-04 5.5 1024.4 301.5 405.2 14.8 1.3 93.9 29.4 1133.1 1876.0 11799 15.9 04-05 3.6 1024.4 316.6 446.6 14.8 1.4 93.9 30.9 1133.1 1932.2 12111 15.9 05-06 3.7 102~.4 332.4 490.4 14.8 1.5 93.9 32.4 1133.1 1993.5 12423 16.0 06-07 3.9 1024.4 3·19.0 538.4 14.0 1.5 93.9 34.0 1133.1 2059.9 12735 16.2 07-08 4.0 1230.0 406.8 590.9 14.8 1.6 •140.9 46.1 1393.7 2443.7 13047 18.7 08-09 4.1 1230.0 427.1 646.1 14.0 1.7 148.9 49.0 1393.7 2523.7 13359 18.9 09-10 4.2 1230.0 44&.4 710.1 14.8 1.8 148.9 51.5 1393.7 2609.7 13671 19.1 10-11 4.4 1230.0 470.8 777.3 14.8 1.9 143.9 54.1 1393.7 2702.2 13963 19.3 TABLE 4.11.Anchorage-Cook Inlet Area,Medium Load Growth Scenario,Case 3,0%Inflation------- NIl\j Itydroelectr1c lransmission Total Cost _~llew C~red Capacuy_Costs _----.il'.stems Total Total Total Sys tern of Existing Investment OM&R Coal Investment OM&R Investment OM&R Investment System Consumptioll,Average Power ~Capacity _~1._Cos.!i Cost_s__Costs _Costs Costs Costs Costs Costs.~---"Y1kIlH__Cost~•.c/K\lH 78-79 33.1 ---------1.0 ------------34.1 2531 79-80 42.2 ---------1.0 ------------Lf3.2 2801 80-81 78.2 --- ------1.0 ------------49.2 3041 81-B2 52.8 ---------l.0 ------------53.8 3281 82-83 61.1 28.7 5.7 6.5 l.0 ---------29.3 103,0 3521 83-84 62.0 28.7 5.7 9.2 1.0 ---------29.3 106.6 3761 84-85 66.6 2(1.7 5.7 11.8 20.7 ---------29,3 114.0 4001 85-86 66.7 58.7 11.6 18.4 20.7 ---------86.7 187.6 4329 dfi-87 67.1 58.7 11.6 24.1 20.7 --- --- ---86.7 193.7 4657 87-88 66.3 87.4 17.3 30.1 20.7 ------.-.115,4 233.0 4985 U8-89 59.0 87.4 17 .3 36.2 10.9 0.4 17.1 3.6 115.4 231.9 5313 4.4 89-90 54.5 81.4 17 .3 "42.5 10.9 0.4 35.9 5.6 134.2 254.5 5641 4.5 90-91 50.2 116.1 24.6 50.1 10.9 0.4 35.9 5.6 162.9 293.8 6063 4.8 co 91-92 47.1 152.9 31.9 59.1 10.9 0.4 35.9 5.6 199.7 343.8 6485 5.3 CO 92-93 42.4 202.8 41.7 70.2 10.9 0.4 35.9 5.6 249.6 409.9 6907 5.9 93-94 38.9 202.8 41.7 77.9 10.9 0.4 35.9 5.6 21 9•6 414.1 7329 5.6 !l4-95 39.4 202.0 41.7 53.3 157.7 1.1 35.9 5.6 396.4 537.5 7751 6.9 95-96 3~.5 202.8 41.7 58.6 157.7 1.1 35.9 5.6 396.4 537.9 8311 6.5 96-97 28.3 202.8 41.7 69.9 157.7 1.1 35.9 5.6 396.4 543.0 8871 6.1 97-98 25.4 202.8 41.7 79.1 157.7 1.1 35.9 5.6 39ti.4 549.3 9431 5.0 98-99 27 .4 202.8 41.7 54.5 206.6 1.8 35.9 5.6 445.3 576.3 9991 5.8 99-2000 22.6 202.0 41.7 60.2 206.6 1.8 35.9 5.6 445.3 577 .2 10,551 5.5 00-01 12.2 202.8 41.7 66.8 206.6 1.8 35.9 5.6 445.3 573.4 10.863 5.3 01-02 11.0 202.8 41.7 73.1 206.6 1.8 35.9 5.6 445.3 578.5·11 ,175 5.2 02-03 4.8·252.7 51.5 80.0 206.6 1.8 52.4 8.8 511.7 650.6 11 ,487 5.7 03-04 4.0 252.7 51.5 86.5 206.6 1.8 52.4 8.8 511.7 665.1 11 ,.799 5.6 04-05 3.6 252.7 51.5 93.4 206.6 1.8 52.4 8.8 511.7 670:0 12,lll 5.5 05-06 3.6 252.1 51.5 100.2 206.6 l.8 52.4 8.8 511.7 677.6 12,423 5.4 06-07 3.6 302.6 61.3 107.3 206.6 l.8 52.4 8.8 561.6 744.4 12,735 .5.8 07-08 3.6 302.6 61.3 114.5 206.6 1.8 52.4 B.£!561.6 751.6 13,047 5.B Otl-09 3.6 302.6 61.3 121.9 206.6 1.8 52.4 8.8 561.6 759.0 13,359 5.7 09-10 3.6 302.6 61.3 129.6 206.6 1.8 52.4 B.8 56l.6 766.7 13,671 5.6 10-11 3.6 352.5 71.1 137.5 206.6 1.8 52.4 0.8 611.5 .834.3 13,983 5.9. 'J )) ..~ ; I )) " ') TABLE 4.12.Anchorage-Cook Inlet Area t Medium Load Grow~h Scenario,Case 3,5%Inflation New Ilydroe 1ectri c Transmission Tota 1 Cost New Coal Fired Capacity Costs Systems Total Total Total System of Existing InVestment 6M&R Coal Investment OM&R Investment OM&R Investment System Consumption,Average Power ~Capacity Costs Costs ~!_S _Costs ~OSh Costs fQlli.Costs Costs',$MHKWIl Cos ts,¢/KWH 78-79 29.7 ---------------0.7 0.4 ---30.8 2531 1.2 79-80 39.1 --.---------0.7 0.4 ---40.2 2801 1.4 80-81 45.7 ---------'-~----0.7 0.4 ---46.8 3041 1.5 81·82 47.9 ---------------0.7 0.5 .1..49.1 3281 l.S 62-83 59.5 34.9 6.9 6.5 ------0.7 0.5 35.6 109.1 3521 3.1 63-84 63.6 34.9 7.2 9.2 -----0.7 0.5 35.6 116.1 3761 3.1 84-85 68.7 34.9 7.6 11.8 ------0.7 0.5 35.6 124.3 4001 3.1 8~-c36 6<3.9 77.3 16.4 18.1 14.3 0.6 23.0 4.9 115.1 224.0 4329 5.2 86-67 69.8 77 .3 17 .2 25.3 14.8 0.6 23.0 5.1 115.1 233.2 4657 5.0 81-1.18 67.1 121.9 26.8 32.7 14.8 0.6 23.0 5.4 159.7 .292.3 49B5 5.9 88-B9 60.6 121.9 28.2 41.6 14.8 0.6 23.0 5.7 159.7 296.5 5313 5.6 69-90 56.4 121.9 29.6 51.5 14.8 0.7 53.9 9.3 190.6 330.1 5641 6.0 90-91 52.5 173.5 41.3 63.7 14.8 0.7 53.9 9.7 242.2 410.1 6063 .6.8 91-92 49.8 243.1 56.9 78.3 14.8 0.7 53.9 10.2 311.6 507.8 6485 7.6 (Xl 47.4 342.0 79.2 9B.5 14.8 0.8 53.9 10.7 410.7 647.4 9.4~92-93 6907 93-94 46.5 342.0 83.2 113.B 14.8 0.8 53:9 11.3 410.7 666.4 7329 9.1 9~·95 48.5 342.0 1.17.4 82.1 323.7 2.4 53.9 11.13 119.6 951.8 7751 12.3 95-96 43.8 342.0 91.7 94.9 323.7 2.5 53.9 12.4 719.6 964.9 8311 11.6 96-97 36.3 342.0 96.3 118.3 323.7 2.7 53.9 13.0 719.6 986.2 8871 11.1 97-9B 37.7 342.0 101.1 140.2 323.7 2.0 53.9 13.7 719.6 1015.1 9431 10.8 98-99 37.5 342.0 106.2 1Ol.13 448.8 4.4 53.9 14.3 844.7 1109.0 9991 11.1 99-2000 31.7 342.0 111.5 .117.2 440.8 4.6 53.9 15.1 644.7 1124.8 10,551 10.7 00-01 16.7 342.0 117.1 137.1 448.8 4.9 53.9 15.8 844.7 1136.3 10,863 10.5 01-02 15.3 342.0 122.9 156.8 448.8 5.1 53.9 16.6 844.7 1161.4 11,175 10.4 02-03 5.4 503.1 160.7 181.4 44B.8 5.4 104.9 26.9 1056.8 1436.6 11,487 12.5 03·04 5.5 503.1 160.'1 205.3 448.8 5.6 104.9 28.2 1056.8 1470.1 11 ,799 12.4 04·05 3.6 503.1 1'17.1 232.5 448.8 5.9 104.9 29.6 1056.8 1505.5 12,111 12.4 05-06 3.7 503.1 105.9 261.4 4413.8 6.2 104.9 31.1 1056.8 1545.1 12,423 12.4 06-07 3.9 690.9 233.7 293.5 4Q8.8 6.5 104.9 32.7 1252.6 1822.9 12,735 14.3 07·08 4.0 698.9 245.4 328.7 448.8 6.8 104.9 34.3 1252.6 1071.8 13,047 14.3 08-09 4.1 69£\.9 257.6 ~367.5 448.8 7.2 104.9 36.0 1252.6 1925.0 13 ,359 14..4.. 09-10 4.2 698.9 270.5 409.9 44£\.8 7.5 104.9 37.8 1252.6 1982.2 13 ,671 14.5 10-11 4.4 936.9 330.7 456.3 448.8 7.9 104.9 39.7 1490.6 2329.6 13,983 16.7 TABLE 4.13.Anchorage-Cook Inlet Area,High Load Growth Scenario,Case 1,0%Inflation .Transml ss i on lotal Cost New Hydroelectric New Coal Fired capac~Costs ~stems Total Total Total System of Existing TRVestment OM&~oa rnvestme~nvestmen~M~--Investment System Consumption,Average Power -lm-Capacity ~t_s_Costs Costs J~~Costs fosts Cost_s__Costs,S MMKIJIl Costs ,¢/KIJH_..-- 78-79 33.1 ---------------0.6 0.4 ......-34.1 2680 1.3 19-80 42.2 ---------------0.6 0.4 ---43.2 3025 1.4 80-81 48.2 --- ------------0.6 0.4 ---49.2 3688 1.3 81-82 52.6 ---------------0.6 0.4 ---53.6 4352 1.2 82-63 61.1 57.4 11.4 9.8 ------17 .1 3.6 74.5 160.5 5015 3.2 83-84 62.0 66.1 17.1 18.6 ------17 .1 3.6 103.2 204.5 5679 3.6 84-85 66.7 114.8 22.8 29.9 ------17 .1 3.6 131.9 254.9 6342 4.0 85-86 66.7 144.8 28.7 44.8 10.9 0.4 17.1 3.6 142.8 317.0 6849 4.6 86-87 67.2 164.7 38.5 66.2 10.9 0.4 17.1 3.6 192.7 368.6 7357 5.0 87-88 66.4 164.7 38.5 73.4 10.9 0.4 17.1 3.6 192.7 375.0 78M 4.8 8S·09 59.0 214.6 48.3 81.2 10.9 0.4 33.6 6.8 259.1 454.8 8372 5.4 89-90 54.5 214.6 48.3 88.6 10.9 0.4.33.6 6.8 259.1 457.7 8879 5.1 90-91 50.2 214.6 40.3 98.5 10.9 0.4 33.6 6.8 259.1 463.3 9589 4.8 1.0 91-92 47.1 272.6 59.7 109.9 10.9 0.4 33.6 6.8 317.1 541.0 10,29a 5.2 0 92-93 42.4 322.5 69.5 120.1 10.9 0.4 33.6 6.8 367.0 606.2 11,008 5.5 93-94 38.9 322.5 69.5 132.6 10.9 0.4 33.6 6.8 367.Q 615.2 11,717 5.3 94-95 39.4 372.4 79.3 143.9 10.9 0.4 33.6 6.8 416.9 686.7 12,427 5.5 95-96 34.5 422.3 89.1 161.3 10.9 0.4 50.1 10.0 483.3 778.6 13,477 5.8 96-97 28.3 472.2 98.9 181.5 10.9 0.4 50.1 10.0 533.2 852.3 14,526 5.9 97-98 25.4 522.1 lOll.7 200.I 10.9 0.4 50.1 10.0 583.1 927.7 15,576 6.0 98-99 27.4 572.0 118.5 217.9 10.9 0.4 50.1 10.0 633.0 1008.2 16,625 6.1 99-2000 22.6 621.9 128.3 238.7 10.9 0.4 66.6 13.2 699.4 1102.6 17 ,675 6.2 00-01 12.2 671.8 138.1 256.6 10.9 0.4 66.6 13.2 749.3 1169.8 18,584 6.3 01-02 11.0 671.8 138.1 275.8 10.9 0.4 66.6 13.2 749.3 1187.8 19.493 6.1 02-03 4.8 721.7 147.9 294.6 10.9 0.4 66.6 13.2 799.2 1260.1 20,402 6.2 03-04 4.8 771.6 157.7 314.7 10.9 0.4 66.6 13.2 849.1 1339.9 21,311 6.3 04-05 3.6 771.6 157.7 335.6 10.9 0.4 66.6 13.2 849.1 1359.6 22,220 6.1 05-06 3.6 821.6 167.5 356.9 19.9 0.4 83.1 16.4 915.5 1460.3 23,129 6.3 06·07 3.6 871.4 177.3 378.8 10.9 0.4 83.1 16.4 965.4 1541.9 24,038 6.4 07·08 3.6 871.4 177 .3 401.2 10.9 0.4 83.1 16.4 965.4 1564.3 24,947 6.3 08-09 3.6 921.3 187.1 42'1.2 10.9 0.4 83.1 16.4 1015.3 1647.0 25,1156 6.4 09-10 3.6 971.2 196.9 447.a 10.9 0.4 83.1 16.4 1065.2 1730.3 26,765 6.5 10-11 3.6 971.2 196.9 472.0 10.9 0.4 83.1 16.4 1065.2 1754.5 27,674 6.3 ))) ".I ))) TAI3LE 4.14 .Anchorage-Cook Inlet Area.High Load Growth Scenario.Case 1.5%Inflation-------- New Hydroelectric Transmission Total Cost New Coal Fired CaRac~Costs Systems Total Total Total System of Existing Investment OM&R oar--'lnves tmcnt OMlR Investment OOR Investment System Consumption,Average Power Year _Capacity Costs Costs !1J!~_Costs Costs Costs ~Costs Costs,$MMKWH Costs,t/K!lH 78-79 29.7 ---------------0.7 0.4 ---30.8 2680 .1.1 79-80 39.1 ---------...---0.7 0.4 ---40.2 3025 1.3 80-81 45.7 ------------...--0.7 0.4 ---46.8 3688 1.3 81-82 47.9 --------- ------0.7 0.5 ---49.1 4352 1.1 82-83 59.5 69.8 13.8 9.9 ------21.0 4.4 90.8 \78.4 5015 3.6 83-84 63.6 106.4 21.8 18.6 ...---21.0 4.6 127.4 2;)6.0 5679 4.2 84-85 68.7 144.9 30.5 29.9 ------21.0 4.9 165.9 299.9 6342 4.7 85-86 68.9 187.3 38.9 44.8 14.8 0.6 21.0 5.1 223.1 381.4 6849 5.6 86-87 69.8 261.1 49.2 69.4 14.8 0.6 21.0 5.4 296.9 491.3 ,356 6.7 87-88 67.I 261.1 51.7 80.5 14.8 0.6 21.0 5.6 296.9 502.4 7864 6.4 3<1-89 60.6 342.5 70.2 93.4 14.0 0..6 48.1 11 ,2 405.4 641.4 8372 7.7 8~-90 56.4 342.5 73.7 107.4 14.8 0.7 46.1 11.7 405.4 655.3 8870 1'.4 90-91 52.5 342,5 77.4 125.4 14.0 0.7 48.1 12.3 405.4 673.7 9569 7.0 lO 91-92 49.8 452.1 102.6 145.9 14.8 0.7 46.1 12.9 515.0 826.9 10,298.8.0 --'92-9)47.4 551.0 127.2 168.5 14.8 0.8 48.1 13.6 613.9 971.4 11.000 8.8 93-94 46.5 551.0 133.5 193.8 14.8 0.0 48.1 14.3 613.9 1002.8 11,717 8.6 94-95 48.5 660.0 161.6 221.3 14.8 0.9 48.1 15.0 722.9 1)70.2 12,427 9.4 95-96 43.8 774,5 192.2 261.2 14.8 0.9 07.1 22.7 876.4 1397.2 13,471 10.4 96·97 36.3 894.7 225.4 307.4 14.8 0.9 87.1 23.9 996.6 1590,5 14,526 10.9 97-98 37.7 1020.9 261.5 354.5 14.8 1.0 87.1 25,1 1122.8 1002.6 15,576 11.6 98-99 37.5 1153.4 300.5 407.1 14.8 1.0 87.1 26.3 1255.3 2027.7 16,675 12.2 9~-2000 31.7 12&2.6 342.8 464.8 14.8 1.1 131.3 36.2 1438.7 2315.3 17,675 13.1 00·01 16.7 H3il.7 380.7 526.5 14.8 1.1 131.3 37.9 1584.8 2555.7 18,5B4 13.8 01-02 15.3 1436.7 4011.1 592.6 14.8 1.2 131.3 39.9 1564.8 2641.9 19.493 13.6 02-03 5.4 1599.6 460.1 667.5 14.8 1.3 131.3 41.9 1745.9 2922.1 20,402 14.3 03-04 5.5 1769.0 516,3 746.8 14.8 1.3 131.3 43.9 1915.1 3220.9 21,311 15.1 04-05 3.6 1769.0 542.2 835.5 14.8 1.4 131.3 46.1 1915.1 3343.9 22.220 15.0 05-06 3.7 1955.5 605.9 930.8 14.8 1.5 184.3 58.4 2154.6 3754.9 23,129 16.2 06·07 3.9 2151.3 674.6 1035.9 14.8 1.5 Hl4.3 61.3 2350.4 4127.6 24.038 17 .2 07·08 4.0 2151.3 708.3 1151.5 14.8 1.6 184.3 64 .4 2350.4 4280.2 24,947 17 .2 .08-09 4.1 2367.2 7B6.1 1270.1 14.8 1.7 184.3 67.6 2566.3 4703.9 25,856 18.2 09-10 4.2 2593.9 869.9 1416.3 14.8 1.8 134.3 70.9 2793.0 5156.1 26,765 19.3 10-11 4.4 2593.9 913.4 1566.6 14.8 1.9 184.3 74.5 2793.0 5353.8 27,674 19.3 TABLE 4.15.Anchorage-Cook Inlet Area.High Load Growth Scenario,Case 2,0%Inflation New Hydroelectric Transmission Total Cost,New Coal fired Capa!Oiy__"Costs Systems Total Total Total System of £Kisting Investment OM&R Coal Investment OM&"R Investment OMloR Investment 'System Consumption.Average Power ~Capacity Costs Costs Costs Costs ~!!sts Costs Costs Costs Costs.S MMKWH Cos!!.L.YKWH 7B-79 33.1 .-------------.0.6 0.4 ---34.1 26BO 1.3 79-80 42.2 -------.-------0.6 0.4 ._-43.2 3025 1.4 BO-Bl 48.2 ---------_.----0.6 0.4 ---49.2 3688 1.3 1ll-82 52.8 ---------------0.6 0.4 .--53.8 4352 1.2. 82-83 61.1 57.4 11.4 9.8 ------17.1 3.6 74.5 160.5 5015 3.2 83-84 62.0 66.\17 .\18.6 ---_.-\7.1 3.6 103.2 204.5 .5679 3.6 84-85 66.7 114.8 22.8 29.9 ----_.17.1 3.6 131.9 254.9 6342 4.0 85-86 66.7 144.8 28.7 44.8 10.9 0.4 17.I 3.6 142.8 317.0 6849 4.6 86-87 67.2 144.8 28.'58.7 10.9 0.4 35.9 5.6 191.6 352.2 7357 4.8 61-88 66.4 194.7 33.5 73.4 10.9 0.4 35.9 5.6 '241.5 420.8 7664 5.3 88·89 59.0 194.7 38.5 .til.2 10.9 0.4 35.9 5.6 241.5 .426.2 il372 5.I 89-9il 54.5 244.6 48.~68.6 10.9 0.4 52.4 8.8 307.9 506.5 6679 5.7 90-91 50.2 244.6 48.3 98.5 10.9 0.4 52.4 8.B 307.9 514.1 9589 5.4 ~91-92 41.I 302.6 59.7 109.9 10.9 0.4 52.4 8.8 365.9 591.8 10,296 5.7 N 92-93 42.4 302.6 59.7 120.I 10.9 0.4 52.4 8.8 365.9 5~1.3 11,008 5.4 93·9~31),9 352.5 69.5 132.6 10.9 0.4 52.4 8.8 415.8 666.0 11.717 5.7 94-95 39.4 352.5 69.7 143.9 10.9 0.4 52.4 B.8 415.8 678.0 12.427 !j.5 95-96 34.5 402.4 79.3 161.3 10.9 0.4 52.4 8.8 465.7 750.0 13.477 5.6 96-97 28.3 452.3 89.1 I III .5 10.9 0.4 60.9 12.0 532.1 843.4 14.526 5.8 97-98 25.4 502.2 90.9 200.1 10.9 0.4 68.9 12.0 582.0 918.8 15.576 5.9 98-99 27.4 5!i2.1 108.7 217.9 10.9 0.4 68.9 12.0 631.9 998.3 16,625 6.0 99·2000 22.6 602.0 118.5 238.7 10.9 0.4 68.9 12.0 6111.8 107'4.0 17,675 6.1 00-01 12.2 651.9 128.3 256.5 10.9 0.4 85.4 15.2 740.2 1160.8 18.564 6.2 01-02 11.0 701.0 138.1 215.0 10.9 0.4 85.4 15.2 798.1 123ll.6 19,493 6.3 02·03 4.8 751.7 147.9 294.6 10.9 0.4 85.4 15.2 648.0 1310.9 20,402 6.4 03-04 4.8 751.7 147.9 314.7 10.9 0.4 85.4 15.2 848.0 1331.0 21,311 6.2 04-05 3.6 151.7 147.9 335.6 10.9 0.4 85.4 15.2 848.0 1350.7 .22,220 6.1 05·06 3.6 801.6 157.7 356.9 lO.9 0.4 85.4 15.2 897.9 1431.7 23,129 6.2 06-01 >.6 851.5 161.5.378.8 10.9 0.4 85.4 15.2 947.11 1513.3 24.038 6.3 07-08 3.6 901.4 177 .3 401.2 10.9 0.4 101.9 18.4 1014.2 1615.1 24.947 6.5 08-09 3.6 901.4 171.3 424.2 10.9 0.4 101.9 16.4 1014.2 1638.1 25.856 6.3 09·10 3.6 951.3 W7.1 447.11 10.9 0.4 101.9 18.4 1064.1 1721.4 26.765 6.4 10-11 3.6 1001.2 1fl6.9 472.0 10.9 0.4 101.9 16.4 11l4.0 1801.7 27,674 6.5 ) ~,,?) '\), TABLE 4.16.Anchorage-Cook Inlet Area,High Load Growth Scenario,Case 2,5%Inflation New l/ydroe1cctrfc ...,frlll)sJ!1isslon Totill Cost New Coal Fired CaJ!.<!.£.ity Cos ts .~tems Totll1 Total Total System of Existing tnvestiilen-r-oM&R~Coal lnves tmenC-CM1T 1nves'tme·ii'tliMXR-Investment System Cons umptf on,Average Power ~Capad ty Costs ~Costs~Costs Costs Costs Costs Costs ~osts,S MMKWH Costs,¢/KWH 76-79 29.7 ---------~"~----0.7 0.4 .--30.8 2660 1.1 ]g-80 39.1 -------------_.0.7 0.4 ---40.2 3025 1.3 80-81 45.7 ---------------0.1 0.4 ---46.6 3688 1.3 111-82 47.9 ---------------0.7 0.5 ---49.1 4352 1.1 62-83 S9.5 69~'8'13.8 9.9 -------".21.0",·4.4 90.8 1.78.4 5015 3.6 83-84 63.6 10604 21.8 18.6 ------21.0'4.6 127.4 236.0 S679 4.2 84-85 68.7 144.9 30.S 29.9 ---......-21.0 4.9 165.9 299.9 6342 4.7 65-66 68.9 187.3 38.9 44.8 14.8 0.6 21.0 S.l 223.1 301.4 6849 5.6 86-87 69.0 167.3 40.8 61.5 14.8 0.6 47.7 8.1 249.8 430.6 4357 5.8 87-88 67.1 264.6 58.0 BO.5 14.8 0.6 47.1 8.6 327.3'542.1 786'4 6.9 68-89 60.6 264.8 60.9 93.4 14.8 0.6 47.7 9.0 327 .3 551.8 8372 6.6 89-90 56.4 350.2 80.8 107.4 14.8 0.7 74.8 14.7 439.6 699.8 8879 7.9 90-91 52,5 350.2 64.8 125.4 14.6 0.7 74.8 15.4 439.8 718.6 9589 7.5 lD 91-92 49.8 459.8 110.5 145.9 14.6 0,1 14.8 16.2 549.4 872.5 •10.298 8.5 Lv 92-93 47.4 459.6 115.9 166.5 14.11 0.8 74.8 17 .0 549.2 899.0 11.008 8.2 93-94 46.5 563.6 142.2 193.9 14.6 0.8 74.8 17 .9 653.2 1054.5 11,717 9.0 94-\15 48.5 563.6 149.3 221.3 14.8 0.9 74.8 18.8 563.2 1092.0 12.421 8.8 95-96 43.8 67il.l 179.2 261.2 14.8 0.9 74.8 19.7 767.1 1272..5 .13.477 9.4 96-97 36.3 798.3 211.8 307.4 14.8 0.9 113.8 27.7 926.9 1511.0 14 ,526 10.4 97-98 37.1 924.5 241.2 354.5 H.8 1.0 113.8 29.1 1053.1'1722.6 15,576 11.1 96-99 37.5 1057.0 285.5 407.1 14.6 1.0 113.8 .30.5 1185.6 1947.2 16,625 11.7 99-2000 31.7 1196.2 327.1 464.8 14.6 1.1 113.8 32.0 1324.8 2181.5 17.675 12.3 00-01 16.7 1342.3 372.2 526.5 lUI 1.1 160.2 42.6 1517.3 2476.4 18.564 13.3 01·02 15.3 1495.7 420.9 591.£I 14.6 1.2 160.2 44.7 1670.7 2744.6 19.493 14 .1 02-03 5.4 1656.£1 473.t."667.5 14.8 1.3 160.2 46.9 1831.8 3026.4 20.402 14 .8 03-04 5.5 1656.8 497.2 746.8 14.B 1.3 160.2 49.3 lB31.B 3131.9 21,311 14.7 04-05 3.6 1656.8 522.1 835.5 14.£1 1.4 160.2 51.8 1831.8 3246.2 22.220 14.6 05-06 3.7 1843.3 .584.8 930.8 14.0 1.5 160.2 54.4 2018.3 3593.5 23,129 15.5 06-07 3.9 2039.1 652.4 1035.9 14.8 1.5 160.2 57.1 2214.i 3964.9 24,038 16.5 07-08 4.0 2244.7 725:3 1151.5 14.6 1.6 215.2 70.9 2474.7 44211.0 24,947 17.7 08-09 4.1 2244.7 761.6 1278.1 14.8 1.7 215.2 74.5 2474.7 4594.7 25,856 17 .8 09-10 4.2 2471.4 844.2 1416.3 14.0 1.8 215.2 78.2 2701.4 5046.1 26.765 18.8 10-11 4.4 2709.4 933.1 1566.6 14.8 1.9 215.2 £12.1 2939.4 5521.5 27,674 19.9 TABLE 4.17.Anchorage-Cook Inlet Area,High Load Growth Scenario,Case 3,0%Inflation Total Cost New Hydroelectric Transm1sliton _New Coal Fired Capacity Costs Systems Total Total Total System of Existing Investment OM&R Coal loves tment-(jf4&R-Investment OM&~Investment System Cons (jmp ti on •Average Power ~Capacity Costs ~Costs Costs Cost~~~-Costs ..f2ill..--Costs.$MMKWII Costs,¢m/ll 78-79 33.1 ---------------0.6 0.4 ---34.1 2680 1.3 79-80 42.2 ---_.----.------0.6 0.4 ---43.2 3025 1.4 80-Bl 48.2 ---,....----------0.6 0.4 ---49.2 3688 1.3 81-82 52.8 ---------------0.6 0.4 ---53.8 4352 1.2 82-83 61.1 57.4 11.4 9.8 ------17.1 3.6 74.5 160.5 5015 3.2 83-34 62.0 86.1 17.1 18.6 ------17.1 3.6 103.2 204.5 5679 3.6 64-85 66.7 114.8 22.8 29.9 ------17.1 3.6 \31.9 254.9 6342 4.0 85-86 66.7 144.8 28.7 44.8 10.9 0.4 17.1 3.6 142.8 317.0 6849 4.6 86-87 67.2 144.8 28.7 58.7 10.9 0.4 35.9 5.6 191.6 352.2 7357 4.8 87-88 66.4 194.7 33.5 73.4 10.9 0.4 35.9 5.6 241.5 420.8 78M 5.3 88-69 59.0 194.7 38.5 81.2 10.9 0.4 35.9 5.6 241.5 426.2 8372 5.1 89-90 54.5 244.6 48.3 86.6 10.9 0.4 52.4 8.B 307.9 508.5 8879 5.7 90-91 50.2 244.6 48.3 90.5 10.9 0.4 52.4 8.0 307.9 514.1 9589 5.4 w !H-92 47.\302.6 59.7 109.9 10.9 0.4 52.4 8.B 365.9 591.B 10.298 5.7 .po.92-93 42.4 302.6 59.7 120.1 10.9 0.4 52.4 8.8 365.9 597.3 11,008 SA 93-94 38.9 352.5 69.5 132.6 10.9 0.4 52.4 8.B 415.8 666.0 11.717 5.7 94-95 39.4 352.5 69.5 111.7 163.1 1.1 52.4 8.B 568.0 798.5 12.427 6.4 95-96 34.5 352.5 69.5 124.2 163.1 1.1 52.4 0.8 568.0 806.1 13.477 6.0 96-97 28.3 402.4 79.3 143.5 163.1 1.1 68.9 12.0 634.4 898.6 14.526 6.2 97-98 25.4 452.3 89.1 161.2 163.1 1.1 68.9 12.0 684.3 973.1 15,576 6.2 98-99 27.4 452.3 89.1 143.9 213.8 1.7 68.9 12.0 684.3 1009.1 16.625 6.1 99-2000 22.6 452.3 89.1 158.5 213.8 1.7 68.9 12.0 684.3 1018.9 17,675 5.8 00-01 12.2 452.3 89.1 175.1 213.8 1.7 68.9 12.0 684.3 '1025.1 18.5ll4 5.5 01-02 11.0 502.5 98.9 192.5 213.8 1.7 68.9 12.0 785.2 1101.3 19.493 5.6 02-03 4.8 552.1 108.7 210.1 213.8 1.7 68.9 12.0 834.8 1172.1 20,402 5.7 03-04 4.8 552.1 •109.7 228.4 213,8 1.7 68.9 12.0 834.8 1190.4 21.311 5.6 M-05 3.6 602.,(1 118.5 247.;;·213.8 1.7 85.4 15.2 901.2 1287.1 22.220 5.8 05-06 3.6 651.9 128.3 266.9 213.8 1.7 85.4 15.2 951.1 1366.8 23.129 5.9 06-07 3.6 651.9 128.3 286.9 213.8 1.7 85.4 15.2 951.1 1386.8 24.038 5.8 07-08 3.6 70\.8 13B.l 307.6 213.8 1.7 85.4 15.2 1001.0 1467.2 24.947 5.9 OB-09 3.6 11.1.7 147.9 328.8 213.8 1.7 85.4 15.2 1050.9 1548.1 25.856 6.0 09-10 3.6 751.7 147.9 350.6 213.8 1.7 B5.4 15.2 1050.9 1569.9 26.765 5.9 10-11 3.6 DOl.r.157.7 372.9 213.8 1.7 101.9 18.4 1117.3 1671.6 27.674 6.0 ,) it , Inlet Area,)i9h .)TABLE 4.18.I\nchoruge-Cook Load Growth Scenario,Case 3,5%Inflation New l~droolectric Transmission Total Cost r--.l!.~~~i-().!!U~r~!..(-~l.cj!:j',_.Costs rr_.s.Y.~t.~rns -0'.---Total Total Total System of Existing nv~s tillent ~1"R Coal liivcStiilcrll-o:Hrr-nvestment ,·11.R Investnlent S.ys tern Consurnption,Average Power Year _.~1~c i l y_.~~J:.L__to~0~.t~_Costs ,(:os ts _S9~ls_Costs Costs SJ2.-~.J fll~K\JIl Co s ~_Wb'!!.------_._---~--- 78 -79 29.7 ----,........-------0.7 0.4 ---30.8 2680 1.1 79-80 39.1 ---------------0.7 0.4 ---40.2 3025 1.3 80-81 45.7 -_.~---.."'..---.--0.7 0.4 -_...46.8 36118 1.3 81-82 47.9 ...-".-----------0.7 0.5 ---49.1 4352 1.1 82-83 59.5 69.8 13.8 9.9 ------21.0 4.4 90.8 175.4 5015 3.6 83-84 63.6 106.4 21.B 18.6 ..-----21.0 4.6 127 .4 236.0 5679 4.2 84-85 68.7 144.9 30.5 29.9 ------21.0 4.9 165.9 299.9 6342 4.7. 85-86 68.9 187.3 38.9 44.8 14.8 0.6 21.0 5.1 223.1 381.4 6849 5.6 86-87 69.8 HJ7.3 40.8 61.5 14.8 0.6 47.7 8.1 249.8 430.6 4357 5.B 81-88 67.1 264.0 58.0 80.5 14.8 0.6 47.7 8.6 327.3 542.1 7864 6.9 813-89 60.5 264.8 60,9 93.4 14.8 0.6 47.7 9.0 327 .3 551.8 8372 6.6 89-90 56.4 3S0.2 8D.B 107.4 14.8 0.7 74.8 14.7 439.8 699.8 8e79 7.9 90-9)52.5 350.2 84.8 125.4 14.8 0.7 74.B 15.4 439.13 718.6 9589 7.5 ~o 91-92 49.13 459.8 110.5 145.9 14.8 0;7 7Ui 16.2 549.4 e72.5 10,298 8.5 c..n 92-93 47.4 4~i9 .8 115.9 168.5 14.8 0.8 74.8 17.0 549.2 899.0 11 ,008 0.2 93 ·9·1 46.5 563.6 142.2 193.9 14.8 0.8 74.8 17.9 653.2 1054.5 11 ,717 9.0 94-95 48.5 563.6 149.3 171.3 335.2 2.2 74.8 18.8 973.6 1364.2 12.427 10.9 95-96 43.8 563.6 156.!1 2DI.2 335.2 2.3 74.8 19.7 973.6 1397.4 13.477 10.4 96-97 35.3 683.8 lOB.2 243.1 335.2 2.4 llUI 27.7 1133.8 1595.2 14,525 10.9 97-98 37.7 810.0 222.4 2nS.6 33S.2 2.5 114.8 29.1 1260.0 1837.3 1'j ,576 11.8 98-99 37.5 010.0 7.33.5 2611.9 464.9 4.2 114.8 30.5 1389.7 1954.3 16,625 11.8 99·7000 31.7.nl0.0 245.2 308.5 464.9 4.4 114.8 32.0 13U9.7 2011.5 17,675 .~11 .4 00-01 16.7 810.0 257.5 359.3 464.9 4.6 114.8 33.6 1389.7 2061.4 18.584 11.1 01-02 15.3 963.4 300.5 413.1 464.9 4.8 114.8 35.3 1543.1 2312.1 19,493 11.9, 02-03 5.4 1124.5 347.1 476.1 464.9 5.1 114.8 37.1 1704.2 2575.0 20,402 12.6 03-04 5.5 1174.5 364.4 5'11 .9 464.9 5.3 114.8 38.9 1704.7.2660.2 21,311 12.5 04·05 3.6 1302.I 417.5 616.1 464.9 5.6 168.5 51.9 1935.5 3030.2 22 ,220 13.6 .05·06 3.7 1488.6 474.9 696.2 454.9 5.9 168.5 54.5 ·2122.0 3357.2 23,129 14.5 06-07 3.9 1488.6 49l1.7 784;9 4.64.9 6.2 168.5 57.2 2122.0 3472.9 24,038 14.4 07-08 4.0 1694.2 563.9 882.8 464.9 6.5 168.5 60.1 2327.6 3844.9 24,947 15.4 08-09 4.1 191 D.I 634.5 990.5 464.9 6.B 168.5 63.1 2543.5 4238.4 25.856 16.4 09-10 4.2 1910.1 665.3 110B.7 464.9 7.1 168.5 66.2 2543.5 4396.0 26,765 16.4 10-J1 4.4 2148.1 746.3 1237.8 46Q.9 7.5 222.0 81.5 2835.0 4912.5 27,674 17.7 .. TABLE 4.19.Fa i rbanks -Ta nana Valley Area,Low Growth Scenario,Case 1,0%Inflation New Hydroelectric Transmission Total Cost New Coal Ff rid Capacf ty Costs ~tellls Total Total Total System of Exlstfng Investmf:~O;'l R --Coa1-lnves'fijienrOM&T 1nves tmeriT-OM&R Investment System Consumptfon,Average Power ~Capacfty Costs Costs Costs ~li.._fQ.ili..~~Costs Costs Costs,$MMKWH Costs,t/KIIH 78-79 33.8 ----.----0.3 0.2 ---34.3 778 4.4 79-80 36.6 ---_.----0.3 0.2 ---37.1 823 4.5 80·B}39.4 ._-------0.3 0.2 ---39.9 855 4.7 61-82 41.6 ----_.---0.3 0.2 ---42.1 887 4.7 82-83 35.6 ._----6.9 0.3 0.2 ---43.1 919 4.7 83-84 33.1 ------7.2 0.3 0.2 ---40.8 951 4.3 84-85 30.3 ------7.3 0.3 0.2 ---38.2 9113 3.9 .85-86 28.2 ------7.5 0.3 0.2 ---36.6 1015 3.6 86-87 26.1 ------7.7 0.3 0.2 ---34.3 1047 3.3 87-88 24.0 ------7.8 0.3 0.2 ---32.4 1079 3.0 88-89 22.9 2.6 0.5 7.7 0.3 0.2 2.9 34.2 1111 3.1 89·90 23.1 21.5 4.3 10.0 3.5 1.0 25.0 63.4 lH4 5.6 90-91 20.9 27.6 5.5 10.0 3.5 1.0 31.4 68.5 1176 5.8 1.0 91-92 21.1 27.6 5.5 12.4 3.5 1.0 31.7 71.1 1208 5.9 Ol 92-93 18.2 27.6 5.5 13.3 3.5 1.0 31.1 69.2 1240 5.6 93-94 18.4 27.6 5.5 14.\3.5 1.0 31.1 70.1 1272 5.5 94-95 18.5 46.5 9.3 14.7 3.5 1.0 50.0 93.5 1305 7.1 95-96 16.9 51.2 10.2 15.4 3.5 1.0 54.7 98.2 1337 7.3 96-97 14.3 51.2 10.2 16.4 3.5 1.0 54.7 97.1 1369 7.1 97-98 3.8 70.1 14.0 lB.9 3.5 1.0 73.6 111.2 1401 7.9, 9.8-99 3.8 69.0 17.8 19.6 3.5 1.0 92.5 134.7 \433 9.4 99-2000 3.8 89.0 17.8 20.6 3.5 1.0 92.5 135.7 1466 9.2 00-01 3.8 89.0 17.8 20.9 3.~1.0 92.5 136.0 1470 9.3 01-02 3.8 89.0 17.8 21.5 3.5 1.0 92.5 136.6 1474 9.3 02-03 1.5 89.0 17.8 21.9 3.5 1.0 92.5 134.7 1478 9.1 03-04 1.5 89.0 17.8 22.4 3.5 1.0 92.5 135.2 1482 9.1 04-05 1.5 89.0 17.8 22.9 3.5 1.0 92.5 135.7 1437 9.1 05-06 ---89.0 17.8 23.5 3.5 1.0 92.5 134.8 1491 9.0 06-07 ---89.0 \7.8 24.\3.5 1.0 92.5 135.4 1495 9.0 07-08 ~~-89.0 17.8 24.6 3.5 1.0 92.5 135.9 1499 9.1 08-09 ---89.0 17.8 24.7 3.5 1.0 92.5 136.0 1503 9.0 09-10 ---89.0 17.8 25.7 3.5 1.0 92.5 137.0 1507 9.1 10-Jl ---89.0 \7.8 26.2 3.5 1.0 92.5 137.5 1511 9.1 )).) ) TABLE 4.21.Fairbanks-Tanana Valley Area.Low Growth Scenario,Case 2,0%Inflation New Hydroelectric Transmh s 1on Total Cost New Coal Fir-cd (apacllY Costs Systems Total Total'Total System of ExistIng lnves tme;;t--oM&R .-Coa-l-.Inves tmertr-OM&1C Investment OM&R,Investment System Consumptfon.Average Power ~Capacity ..-1!!.ill-f£sts Costs _~tL-_Costs Costs 0ili.Costs Costs J $_MHKl-Ifi_._Costs.C!KWH 70-79 33.0 ---------0.3 0.2 ---34.3 778 4.4 79-80 36.6 .--------0;3 0.2 ---37.1 823 4.5 80-81 39,4 ---------0.3 0.2 ---39.9 855 4.7 81-82 41.6 ---_......---0.3 0.2 ---42.1 887 4.7 82-83 35.6 ------.6.9 0.3 0.2 ---43.1 919 4.7 83-84 33.1 ------7.2 0.3 0.2 ---40.0 951 4.3 84-85 30.3 ------7.3 0.3 0.2 ---38.2 983 3.9 85-86 28.2 ------7.5 0.3 0.2 ---36.6 1015 3.6 86-87 26.1 ------7.7 0.3 0.2 ---34.3 1047 3.3 87-08 24.0 ------7.0 0.3 0.2 ---32.4 .1079 3.0 88-09 22.9 2.6 0.5 7.7 0.3 0.2 2.9 34.2 1111 3.1 89-90 23.1 21.5 4.3 10.0 3.5 1.0 25.0 63.4 1144 5.6 90-91 20.9 27.6 5.5 10.0 3.5 1.0 31.4 68.5 1176 5.8 \.0 91-92 2].1 27.6 5.5 12.4 3.5 1.0 31.7 71.1 1208 5.9 CO . 92-93 18.2 27.6 5.5 13.3 3.5 1.0 31.1 69.2 1240 5.6 93-94 .18.4 27.6 5.5 14.1 3~5 1.0 31.1 70.1 1272 5.5 94-95 HI.5 27.6 5.5 14.7 16.6 2.0 46.4 87.2 1305 6.7 95-96 16.9 32.3 6.4 15.4 18.8 2.0 51.1 91.8 1337 6.9 96-97 14.3 51.2 10.2 16.4 18.8 2.0 70.0 113.1 1369 8.3 97-98 3.7 70.1 14.0 18.9 10.8 2.0 88.9 127.6 1401 9.1 98-99 3.7 70.1 14.0 19.6 10.8 2.0 8tl.9 128.4 1433 8.9 99-2000 3.7 70.1 14 .0 20.6 18.0 2.0 80.9 129.3 1466 8.8 00-01 3.8 70.1 14.0 20.9 10.8 2.0 88.9 129.6 1470 8.8 01-02 3.8 70.1 14.0 21.5 10.0 2.0 08.9 130.2 1474 8.8 02-03 1.5 70.1 14.0 21.8 18.8 2.0 88.9 128.3 1478 0.7 0)-04 1.5 70.1 14.0 22.4 HI.8 2.0 88.9 128.0 1482 6.7 04-05 1.5 70.1 14.0 22.9 18,8 2.0 68.9 129.3 1487 8.7 05-06 ---70.1 H.O 23.5 '18.8 2.0 88.9 128.4 1491 8.6 06-07 ---89.0 17.8 24.0 18.0 2.0 107.8 151.7 1495 10.1 07-00 ---89.0 lI.B 24.5 18.8 2.0 107.8 152.2 1499 10.1 08-09 ---89.0 17.0 25.1 10.8 2.0 107.8 152.8 1503 10.1 09-10 ---89.0 17.8 25.7 18.8 2.0 107.8 153.3 1507 10.2 10-11 ---89.0 17.8 26.2 18.8 2.0 107.8 153.9 1511 10.2. ))) ,_....;.~..,. -",,--. ') TABLE 4.22.Fairbanks-Tanana Valley Area,Low Growth Scenario,ease 2,5%Inflation New Hydroelectdc Tran~mjssjon lata 1 Cos t New Coal Fired Capacity Costs ~stems .Total Total Total System of Existing liivestment-OM&R Coa1-rnvestment ilMllC wves tlnent -----oHlR Investment System Consumption,Average Power ~L _Capadty Costs Costs Costs Costs -fQ.ili.Costs Costs Costs Costs I $MMKWH Costs ,UKWH 76-79 30.57 ---------0.2 0.2 ---30.9 776 4.0 79-80 33.9 ---------0.2 0.2 ---34.2 823 4.2 80-81 37.4 ---------0.2 0.2 ---37.8 .855 4.4 81-82 40.7 ---------0.2 0.2 ---41.0 887 4.6 82-83 36.6 ------6.9 0.2 0.2 ---43.9 919 4.8 83-84 35.6 ------7.2 0.2 0.2 ---43.2 951 4.5 84-85 33.5 --- --- 7.3 0.2 0.2 ---41.3 983 4.2 8~-86 32.3 ------7.5 0.2 0.2 ---40.3 1015 4.0 86-87 30.4 ------6.1 0.2 0.3 ---38.9 1047 3.7 87-68 28.1 ------8.6 0.2 0.3 ---37.8 1079 3.5 88-89 27.9 4.2 0.7 8.9 0.2 0.3 4.4 42.4 1111 3.B 89-90 29.3 36.6 7.0 12.1 4.5 1.7 41.1 91.3 1144 7.9 90-91 28.4 48.0 7.4 12.7 4.5 I.B 52.5 102.B 1176 B.7 to 91-92 30.1 48.0 7.4 16.5 4.5 1.9 52.5 108.2 1208 8.9 '-0 .8.692-93 26.7 48.0 7.4 lB.7 4.5 2.0 52.5 107.0 1240 93-94 28.1 48.0 7.8 20.6 4.5 2.1 52.5 ]10.8 1272 8.7 94-95 29.5 48.0 11.9 22.6 36.8 4.0 84.8 153.0 1305 11.7 95-96 2B.8 58.1\14.6 24.9 36.8 4.2 95.6 168.1 1337 12.6 96-91 27.1 105.4 24.4 27.9 36.8 4.4 142.2 226.6 1369 16.5 97-9B 6.1 153.3 35.2 33.5 36.8 4.6 190.1 269.6 1401 19.2 98-99 6.4 153.3 36.9 36.7 36.8 4.8 190.1 275.0 1433 19.2 99-2000 6.6 153.3 38.7 40.1 36.8 5.1 190.1 280.6 1466 19.1 00-01 7.0 153.3 40.7 43.0 36.8 5.3 190.1 266.2 1470 19.4 01-02 7.3 153.3 42.7 46.1 36.6 5.6 190.1 291.9 1474 19.8 02-03 2.7 153.3 44.9 49.6 36.8 5.9 1'.J0.l 293.2 1478 19.8 03·04 2.8 153.3 47.1 53.2 36.8 6.2 190.1 299.4 1482 20.2 04-05 2.9 153.3 49.5 57.1 36.6 6.5 190.1 306.2 1487 20.6 05·06 .--153.3 51.9 61.3 36.8 6.8 190.1 310.1 1491 20.8 06-07 ---227.6 69.2 65.7 36.8 7.2 264.4 406.6 1495 27.2 07-0B ---227.6 72.6 70.5 36.8 7.5 264.4 415.1 1499 27.7 66-09 ---221.6 76.3 75.7 36.3 7.9 264.4 424.4 1503 28.2 09-10 ---227.6 80.1 81.2 36.8 B.3 264.4 434.1 1507 28.8 10-11 ---227.6 84.1 87.1 36.3 8.7 264.4 443.3 15H 29.4 TABLE 4.23.Fairbanks-Tanana Valley Area.Low Growth Scenario,Case 3,0%Inflation----- Hew Hydroa 1ec tri c Transmission Total Cost New Coal Fired Capacl!y Casts _~I])L __Total Total Total System of Existing II\~estniellt -011&[Coal-Inves tment OM&R III~es tlllen t OM&R Investment System COllsumlltfon.Average Power ~Capad ty Costs ~Cos~Costs "_Costs .Costs_f2ili Costs Costs.$MMKWU Costs,¢/KliH 78-79 33.8 .......------------0.3 0.2 ---34.3 776 4.4 79-60 36.6 ---------------0.3 0.2 ---37.1 823 4.5 80-81 39.4 ._-------------0.3 0.2 ---39.9 855 4.7 81-82 41.6 ---------------0.3 0.2 ---42.1 887 4.7 82-83 35.6 ------6.9 ---.-.0.3 0.2 ---43.1 919 4.7 83-84 33.1 ------7.2 --- --- 0.3 0.2 ---40.8 951 4.3 84-85 30.3 ...---7.3 ------0.3 0.2 ._-38.2 983 3.9 85-86 26.2 -.----1.5 ------0.3 0.2 ---36.6 1015 3.6 85-87 26.1 ------7.1 --..--0.3 0.2 ---34.3 1047 3.3 87-88 24.0 _..---7.8 ------0.3 0.2 ..-32.4 1019 3.0 88-89 22.9 2.6 0.5 1.7 ------0.3 0.2 2.9 34.2 1111 3.1 89-90 23.1 21.5 4.3 10.0 ------3.5 1.0 25.0 63.4 1144 5.6 90-91 20.9 27.6 5.5 10.0 ---.--3.5 1.0 31.4 68.5 1176 5.8 ......91-92 21.1 21.6 5.5 12.4 ------18.8 2.0 46.4 61.4 1208 7.2 0 0 92-93 18.2 21.6 5.5 13.3 ------18.8 2.0 46.4 85.5 1240 f.9 93-94 18.4 27.6 5.5 14.I ------18.8 2.0 46.4 1l6.4 1272 6.6 94-95 18.5 21.6 5.5 6.9 36.2 0.1 18.8 2.0 C2.6 115.6 1305 8.8 95-96 16.9 32.3 6.4 6.5 36.2 0.1 18.8 2.0 B2.6 119.2 1337 B.9 96-97 14.3 32.3 6.4 1.3 36.2 0.1 18.8 2.0 82.6 117.5 1369 8.6 97-98 3.8 32.3 6.4 9.6 36.2 0.1 18.8 2.0 82.6 10!U 1401 7.11 98-99 3.8 32.3 6.4 10.1 36.2 0.1 16.8 2.0 82.6 109.1 1433 7.6 99-2000 3.6 32.3 6.4 3.1 411.3 0.2 10.11 2.0 99.4 114.9 1466 1.8 00-01 3.8 32.3 6.4 2.7 41L3 0.2 H\.8 2.0 99.4 114.5 1470 1.8 01-02 3.B 32.3 6.4 2.1 48.3 0.2 16.6 2.0 99.4 114.5 1474 1.7 02-03"1.5 32.3 6.4 2.4 46.3 0.2 18·a 2.0 99.4 111.9 1478 7.6 03-04 1.5 32.3 6.4 2.5 48.3 0.2 IB.8 2.0 99.4 112.0 1482 7.6 04-05 1.5 32.3 6.4 2.6 4B.3 0.2 10.8 2.0 99.4 112.1 14B7 7.5 05-06 ---32.3 6.4 2.7 48.3 0.2 18.8 2.0 99.4 110.7 1491 7.4 06-07 .-.32.3 6.4 2.8 48.3 0.2 18.8 2.0 99.4 110.8 1495 7.4 07-08 ---32.3 6.4 2.9 48.3 0.2 IB.B 2.0 99.4 110.9 1499 7.4 08-09 --.32.3 6.4 3.1 48.3 0.2 18.8 2.0 99.4 111.1 1503 1.4 09-10 ---32.3 6.4 3.2 48.3 0.2 18.8 2.8 99.4 111.2 1507 7.4 IO-IJ ---32.3 6.4 3.4 411.3 0.2 lIJ.B 2.0 99.4 111.4 1511 1.4 ))) ) TABLE 4.24.Fairbanks-Tanana Valley Area.Low Growth Scenario.Case 3.5%Inflation New f1ydroelectr1c Transm1ss 10n Total Cost New Coal Fired Capacity Costs Systems Tobl Totlll Total System of Ex1stlng Investment OM&R Coal Inves-tment OM&R 1.J1ves tment OM&R Investment System Consumpt10n.Averagl;!Power ~Capacity .Costs__Costs CostL-Costs Costs .Cost_s_Costs Costs Costs.S MMKWfI Costs.t/KWH 78-79 30.5 ---------------0.2 0.2 -'--30.9 778 4.0 79·80 33.9 -.-------._----0.2 0.2 ---34.2 823 4.2 80-Bl 37.4 ---------------0.2 0.2 ---31.a-855 4.4 81-82 '40.7 ---------------0.2 0.2 ---4].0 887 4.6 82-83 36.6 -.----6.9 ------0.2 0.2 ---43.9 919 4.8 83-84 35.6 ------7.2 ------0.2 0.2 ---43.2 951 4.5 84-85 33.5 -,.....---7.3 -.----0.2 0.2 .--41.3 983 4.2 85-86 32.3 ------7.5 ------0.2 0.2 ---40.3 1015 4.0 86-87 30.4 ------B.l ------0.2 0.3 ---3B.9 1047 3.1 87-88 28.7 c-.....---8.6 ------0.2 0.3 ---37.8 1019 3.5 88-89 27.9 4.2 0.7 8.9 ------0.2 0.3 4.4 42.4 111l 3.8 B~·90 29.3 36.6 7.0 12.1 ------4.5 1.7 41.1 91.3 1144 7.9 90-91 28.4 4B.0 1.4 12.7 ------4.5 I.B 52.5 102.8 1176 8.7 --'91-92 30.1 48.0 10.3 16.4 .-----32.4 3.5 80.4 140.1 1208 11.6a --'92-93 26.7 48.0 10.8 lB.7 ------32.4 3.6 60.4 140.3 1240 11.3 93·94 26.1 48.0 11.4 20.6 ------32.4 3.8 80.4 144.3 1272 11.3 94·95 29.5 46.0 11.9 10.1 76.2 0.3 32.4 4.0 156.6 213.1 1305 16.3 95-96 2B.B 58.8 14.6 10.5 16.2 0.3 32.4 4.2 167.4 225.8 1331 .16.9 96-97 21.1 58.8 15.3 12.4 76.2 0.3 32.4 4.4 167.4 221.5 1369 16.6 97-98 6.1 58.8 16.1 16.9 76.2 0.4 32.4 4.6 167.4 211.5 1401 15.1 98-99 6.4 58.B 16.9 10.9 16.2 0.4 32.4 4.8 167.4 214.8 1433 15.0 99-2000 6.6 58.8 17.7 5.9 IOB.6 0.8 32.4 5.1 199.8 .l36.0 1466 16.1 00·01 7.0 511.8 Ill.6 5.4 108.6 0.8 32.4 5.3 199.8 236.9 1470 •16.1 01·02 7.3 58.8 19.6 5.8 1Oil.6 0.9 32.4 5.6 199.8 239.0 1474 16.2 . 02-03 2.7 58.8 20.5 5.5 10B.6 0.9 32.4 5.9 199.8 235.3 1478 15.9 03-04 2.8 5B.B 21.6 5.9 108.6 1.0 32.4 6.2 199.8 237.3 1462 16.0 04-05 2.9 58.8 22.6 6.5 108.6 1.0 32.4 6.5 199.8 239.3 1487 16.1 05-06 -_.58.8 23.1 7.1 108.6 1.1 32.4 6.6 199.6 238.5 1491 16.0 06·07 -.-58.8 24.9 7.8 106.6 1.1 32.4 7.2 199.8 240.8 1495 16.1 07-0B ---58.8 26.2 8.5 106.6 1.2 32.4 7.5 199.8 243.2 1499 16.2 08-09 ---58.8 27.5 9.3 10B.6 1.2 32.4 7.9 199.6 245.7 1503 16.3 09-10 ---58.8 28.9 10.2 lOB.6 1.3 32.4 B.3 199.8 248.5 1507 16.5 10·11 ---56.6 30.3 11.1 108.6 1.4 32.4 B.7 199.8 251.3 1511 16.6 )) Il\]lE 4.26.Fairbanks-Tanana Valley Area.Medium Growth Scenario.Case 1*5%Inflation New Hydroelectric Transm15s Ian Total Cost New Coal Fired Capdclty Costs S.Y~tt'JlS Total Total Total System of Existing TiiVestment OM&R (oa"-TriVes tment -OM&R"""nves tmen OM&R Investment System Consumption.Average POlo/er ~~a£ll.L...Costs fasts Costs ~!.L.-Costs Costs CoSh Costs Costs I $MMKWH Costs,t!I<WtI 78-79 30.5 -.-------0.2 0.2 .--30.9 604 3.8 79-80 33.9 ---------0.2 0.2 ---34.2 862 4.0 80-81 37.4 ---------0.2 0.2 ---37.8 916 4.1 81-82 40.7 ---------0.2 0.2 ---41.0 970 4.2 82-83 36.6 ------6.9 0.2 0.2 ---43.9 1024 4.3 83-84 35.6 ------7.2 0.2 0.2 ---43.2 1078 4.0 84-85 33.5 ------7.3 0.2 0.2 ---41.3 \132 3.6 85-136 32.3 26.6 5.3 9.4 4.4 1.2 31.0 79.2 1193 6.6 86··67 30.4 26.6 5.5 11.4 4.4 1.3 31.0 79.6 1254 6.3 87-88 28.7 26.6 5.8 13.6 4.4 1.4 31.0 80.5 1315 .6.1 83-89 27.9 30.8 7.0 15.4 4.4 1.5 35.2 87.0 1376 6.3 89-90 29.3 63.2 13.6 17.6 4.4 1.5 67.6 129.7 1437 9.0 90-91 28.4 74.6 16.4 19.3 4.4 1.6 79.0 145.3 1505 9.6 -~91-92 30.1 74.6 16.4 22.3 4.4 1.7 79.0 149.5 1573 9.5 0 92-93 26.1 112.1 23.8 25.5 4.4 1.8 116.5 194.4 1641 11.8W 93-94 28.1 112.1 25.0 28.5 4.4 1.9 116.5 200.1 1709 11.7 94-95 29.5 112.1 26.2 31.fl 4.4 2.0 116.5 206.1 1777 11.6 95-96 28.8 122.9 29.7 35.13 4.4 2.2 121.3 223.8 1859 12.0 96-97 21.1 169.5 40.1 40.7 8.5 2.3 178.0 288.8 1941 14.9 97-98 6.1 217.4 51.7 48.5 8.5 2.4 225.9 334.6 2023 16.!) 98-99 6.4 267.7 64.1 54.0 8.5 2.6 276.2 403.4 2105 19.2 99-2000 6.6 267.7 67.3 59.9 8.5 2.7 276.2 412.7 2187 18.9 00-01 7.0 267.7 70.7 65.3 8.5 2.8 276.2 422.0 2229 111.9 01-02 7.3 267.7 74.3 71.1 8.5 3.0 276.2 431.9 2270 19.0 02-03 2.7 267.7 77.9 17.6 0.5 3.2 276.2 437.6 2312 18.9 03-04 2.8 365.0 77.9 77.6 8.5 3.4 373.5 561.5 2353 23.9 04-05 2.9 365.0 102.1 92:1 8.5 3.6 373.5 574\2 2395 24.0 05-06 --365.0 107,2 100.3 8.5 3.7 373.5 584.7 2437 24.0 06-07 ---365.0 112.6 109.1.a.5 3.8 373.5 599.0 2478 24.2 07-08 ---365.0 1l!l.2 llB.7 8.5 4.2 373.5 614.4 2520 24.4 08-09 ---365.0 124.1 129.1 8.5 4.2 373.5 630.9 2561 2·1.6 09-10 ---365.0 130.3 140.4 8.5 4.4 373.5 648.6 2603 24.9 10-11 ---365.0 136.8 152.5 8.5 4.5 373.5 667.3 2645 25.2 TABLE 4.27.Fairbanks-Tanana Valley Area,Medium Growth Scenario~Case 2~0%Inflation New I/ydroe 1ectrl c Transmission Total Cost New Coal Fired Ca~ac~!y Costs Systems Total Total Tota 1 System of Existing Investment nM&R ·Coar--1nves tmentOM&rr TiiVestment OM&R Investment System Consumption.Average Power .J.lli-CapacHy Costs Costs Costs Costs Costs Costs ~Costs CO$ts.S M~IK~JH Costs.¢/KWH 78-19 33.8 ---------0.3 0.2 ---34.2 804 4.3 19-80 36.6 ---------0.3 0.2 ---37.0 862 4.3 80-81 39.4 ---------0.3·0.2 ---39.8 916 4.3 81·82 41.6 ------._-0.3 0.2 ---42.1 970 4.3 82-83 35.6 ------6.9 0.3 0.2 ---43.0 1024 4.2 83-64 33.1 ------7.2 0.3 0.2 ---40.8 1078 3.8 84-85 30.3 ------7.3 0.3 0.2 ---36.1 1132 3.4 85-86 2e.2 18.9 3.8 9.4 3.5 1.0 22.4 64.9 1193 5.4 86-81 26.1 18.9 3.6 10.9 3.5 1.0 22.4 64.2 1254 5.1 87-88 24.0 18.9 3.8 12.4 3.5 1.0 22.4 63.7 1315 4.8 8il-89 22.9 21.5 4.3 13.3 3.5 1.0 25.0 66.6 1376 4.8 89-90 23.1 21.5 4.3 14.5 18.8 2.0 40.3 64.2 1437 5.8 90-91 20.9 27.6 6.5 19.1 18.8 2.0 46.4 89.0 1505 5.9 91-92 21.1 21.6 5.5 15.2 18.8 2.0 46.4 90.2 1573 5.7 C)92-93 18.2 27.6 5.5 16.0 18.8 2.0 26.4 80.2 1641 5.4,f;:. 93-94 13.4 27.6 5.5 16.9 10.0 2.0 46.4 09.2 1709 5.2 94-95 18.5 46.5 9.2 19.8 18.8 2.0 65.3 .114.9 1777 6.5 95-96 16.9 70.1 13.8 22.1 1ll.B.2.0 06.9 143.7 1859 7.7 96-91 14.3 70.1 13.8 24.0 18.8 2.0 08.9 143.2 1941 7.4 97-9/1 3.76 69.0 17 .5 27.3 111.8 2.0 101.8 158.5 2023 7.-8 98-99 3.1 10].9 21.2 23.9 13.3 2.0 126.7 182.6 2105 8.7 99-2000 3.7 107.9 21.2 30.7 18.n 2.0 126.7 184.5 21B7 6.4 GO·Ol 3.B 107.9 21.2 31.8 18.8·2.0 126.7 185.5 2229 8.3 01-02 3.8 107.9 21.2 33.1 18.8 2.0 126.7 186·.8 2270 8.2 02-03 1.5 126.8 24.9 34.2 18.8 2.0 145.6 208.2 2312 9.0 03-04 1.5 126.8 24.9 35.6 18.8 2.0 145.6 209.6 2353 8.9 04-05 1.5 126.8 24.9 37.0 18.8 2.0 145.6 211.0 2395 8.6 05-06 ---126.8 24.9 3B.44 18.3 2.0 145.6 210.9.2437 8.6 06-07 ---126.8 24.9 39.6 18.8 -2.0 145.6 212.3 2478 8.6 07-08 ...126.8 24.9 41.3 11l.8 2.0 145.6 213.8 2520 8.5 08-09 ---126.8 24.9 42.8 lB.8 2.0 145.6 215.3 2561 8.4 09-10 ._-126.0 24.9 44.3 18.3 2.0 145.6 216.9 2603 8.3 10-11 ---126.8 24.9 45.9 18.8 2.0 145.6 218.4 2645 8.2 )c,) I.. '\ J TABLE 4.28.Fairbanks-Tanana Valley Area.Medium Growth Scenario.Case 2.5%Inflation------- New Hydroelectr1c Transm1ss1on Tohl Cost New Coal F1red capac~!y Costs Systems Total ,Total Total System of Exist1ng lnvostment---TIM&--R--',oal---,Investment of.l&R-·1nves tmen t OM&R Investment System Consumpt1on.Average Power ~!r-Capacity Costs Costs Costs CostL_fosts Costs Costs Costs Costs,S ~_'H__~-Li/K"'H 78-79 30.5 ---------0.2 0.2 ---30.9 804 3.8 79-80 33.9 ---------0.2 0.2 ---34.2 862 4.0 80-81 37.4 -.-------0.2 0.2 ---37.8 916 4.1 81-82 40.7 ---------0.2 0.2 ---41.0 970 4.2 82-83 36.6 ------6.9 0.2 0.2 ---43.9 1024 4.3 83-84 35.6 ------7.2 0.2 0.2 ---43.2 1078 4.0 84-85 33.5 ---7.3 0.2 0.2 ---41.3 1132 3.6 85-86 32.3 26.6 5.3 9.4 4.4 1.2 31.0 79.2 1193 6.6 86-117 30.4 26.6 5.5 11.4 4.4 1.3 31.0 79.6 1254 6.3 87-88 28.7 26.6 5.6 13.6 4.4 1.4 31.0 80.5 1315 6.1 68-89 27.9 30.8 7.0 15.4 4.4 1.5 35.2 87.0 ,1376 6.,3 89-90 29.3 30.9 7.3 17.6 29.7 3.2 60.6 118.1 1437 8.2 90-91 26.4 42.3 9.8 16.0 29.7 3.4 72.0 131.8 1505 6.7 .....91-92 30.1 42.3 10.3 20.2 29.7 3.5 72.0 136.1 1573 8.6 0 . U1 92-93 26.7 42.3 10.8 22.4 29.7 3.7 72.0 135.7 1641 8.3 93-94 28.1 42.3 11.4 24.7 29.7 3.9 72.0 140.1 1709 8.2 94-95 29.5 83.7 20.2 30.5 29.7 4.1 113.4 197.8 1777 11.1 95-96 28.8 137.9 31.'}35.8 2').7 4.3 167.6 268.5 1859 14.4 96-97 27.7 137.9 33.5 40.7 29.7 4.5 167.6 274.0 1941 14.1 97-98 6.1 165.8 44.7 48.5 29.7 4.7 215.5 319.5 2023 15.8 98-99 6.4 236.1 56.6 54.0 '29.7 5.0 265.8 388.1 2105 18.4 99-2000 6.6 236.1 59.6 59.9 29.7 5.2 265.8 397.1 2187 18.2 00-01 7.0 236.1 62.6 65.3 29.7 5.5 265.8 406.2 2229 18.2 01-02 7.3 236.1 65.7 71.1 29.7 5.7 265.8 415.6 2270 10.3 02-03 2.7 291.2 81.1 77 .5 29.7 6.0 326.9 494.3 2312 21.4 03-04 2.8 297.2 05.2 84.4 29.7 6.3 326.9 505.7 235.3 21.5 04-05 2.9 297.2 89.5 92.1 29.7 6.7 326.9 518.2 2395 21.6 05-06 ---~97.2 93.9 100.2 29.7 7.0 326.9 528.1 2437 21.7-06·07 ---297.2 90.6 109.1 29.7 7.3 326.9 541.9 2470 21.9 07-08 ---297.2 103.6 118.7 29.7 7.7 326.9 556.9 2520 22.1 03-09 -_.297.2 108.7 129.1 29.7 8.1 326.9 572.8 2561 22.4 09-10 ---297.2 114.2 140.3 29.7 8.5 326.9 590.0 2603 22.7 10-11 ---297.2 119.9 1~2.5 29.7 0.9 326.9 606.2 2645 23.0 TABLE 4.29.Fairbanks-Tanana Valley Area.Medium Growth Scenario.Case 3.0%Inflation New Hydroclectdc Transm15sion Total Cost New Coal fired capacity Costs Systems Total Total Tota 1 Sys tem of Existing Investment OM&R Coal Investnlent OM&R Investment OM&R Investment System Consumption,Average Power ..1ru:-.Capacity Costs fQill Costs ~2_H1_fQ.ill..~lliL....Costs Costs Costs.$HHKl-IlI Cost5,t/KWIi 7B-79 33.B·---------------0.3 0.2 ---34.2 B04 4.3. 79-80 36.6 ----...---- --- ---0.3 0.2 37.0 862 4.3 80-81 39.4 0.3 .0.2 39.8 •916 4.3------------------ 81-82 41.6 ---------------0.3 0.2 ---42.1 970 4.3 82-83 35.6 ------6.9 ------0.3 0.2 ---43.0 1024 4.2 83·84 33.1 ------7;2 ------0.3 0.2 ---40.11 1078 3.8 114-65 30.3 ----.-7.3 ------0.3 0.2 ---3B.l 1132 3.4 65-86 28.2 18.9 3.8 9.4 ------3.5 1.0 22.4 64.9 1193 5.4 06-87 26.1 18.9 3.8 10.9 ------3.5 1.0 22.4 64.2 lZ54 5.1 87-88 24.0 18.9 3.8 12.4 ------3.5 1:0 22.4 63.7 1315 4.8 88-89 22.9 21.5 4.3 13.3 ------3.5 1.0 25.0 66.6 1376 4.8 89-90 23.1 <'1.5 4.3 14.5 ------18.8 2.0 40.3 84.2 1437 5.8 90-91 20.9 27.6 5.5 19.1 ------18.11 2.0 46.4 89.0 1505 5.9 91-92 21.1 27.6 5.5"15.2 ------18.8 2.0 46.4 90.2 1573 5.7 0 92·93 18.2 27.6 5.5 16.0 18.8 2.0 26.4 88.2 1641 5.40'\------ 93-94 13.4 27.6 5.5 16.9 ------18.0 2.0 46.4 89.2 1709 5.2 :H-95 18.5 27.6 .5.5 13.6 34.4 0.1 ·18.8 2.0 80.8 .120.5 1777 6.8 9S-'J6 16.9 32.3 6.4 13.9 34.4 0.1 18.0 2.0 85.5 124.8 .1859 6.7 96-97 14.3 32.3 6.4 15.6 34.4 Q.l 18.8 2.0 85.4 124.0 1941 6.4 97-38 3.7 51.2 10.2 10.7 34.4 0.1 1ll.O 2.0 104.4 139.2 20ll 6.9 98-99 3.7 51.2 10.2 13.0 45.9 0.2 18.8 2.0 115.9 145.1 2105 6.9 99-2000 3.7 51.2 10.2 13.6 45.9 0.2 10.8 2.0 115.9 145.7 21117 6.7 00-01 3.8 51.2 10.2 14.4 45.9 0.2 18.8 2.0 115.9 146.5 2229 6.6 01-02 3.8 51.2 10.2 15.3 45.9 0.2 18.8 2.0 115.9 147.4 2270 6.5 02-03 1.5 70.1 14.0 16.1 45.9 0.2 18.8 2.0 134.8 168.6 2312 7.3 03·04 1.5 70.1 14.0 17 .1 45.9 0.2 18.8 2.0 134.8 169.6 2353 7.2 04-05 1.5 70.1 14.0 10.1 45.9 0.2 18.0 2.0 134.8 170.6 2395 7.1 05-06 ---70.1 14.0 19.2 45.9 0.2 18.8 2.0 134.8 110.2 2437 7.0 06-07 --.70.1 14.0 20.2 45.9 0.2 18.8 2.0 134.8 171.2 2478 6.9 07-08 ---70.1 14.0 21.3 45.9 0.2 18.8 2.0 134.6 172.3 2520 6.6 08-09 ---70.1 14.0 22.4 45.9 0.2 10.8 2.0 134.8 173.4 2561 6.8 09-10 --.70.1 14.0 23.6 45.9 0.2 18.6 2.0 134.6 174.6 2603 6.7 lO-n ---70.1 14.0 24.7 45.9 0.2 16.6 2.0 134.6 175.7 2645 6.6 ))) I ) I TABLE 4.30.Fairbanks-Tanana Valley Area,Medium Growth Scenario.Case 3,5%Inflation New Hydroelectric Tr\lnSRlisSion Total Cost New COdl Fired Capacit~Costs --.Jlltems Total Total Total ~ystem of Existing Investment OM&R COdl Investment OM&R Investment OM&R Investment System Consumption.Average Power ~Capacity Costs Costs Costs __C(lsts_fQ.ili.-..f.2!!_s_Costs Costs Costs.S tJ.MKWH Costs.aKWH 78-79 30.5 ---------------0.2 0.2 ---30.9 804 3.6 79-80 33.9 ----.----._----0.2 0.2 ---34.2 662 4.0 60-81 37.4 ---------------0.2 0.2 ---37.8 916 4.1 61-82 40.7 -------.-------0.2 0.2 ---41.0 970 4.2 82-63 36.6 --.._-6.9 ----.-0.2 .0.2 -..43.9 1024 4.3 63-64 35.6 ------7.2 -_.---0.2 0.2 ---43.2 1078 4.0 84-85 33.5 ---.--7.3 ------0.2 0.2 ---41.3 1132 3.6 65-66 32.3 26.6 5.3 9.4 ------4.4 1.2 31.0 79.2 1193 6.6 66-87 30.4 26.6 5.5 11.4 ------4.4 1.3 31.0 79.6 1254 6.3 87-88 28.7 26.6 6.8 13.6 ------4.4 1.4 31.0 60.5 1315 6.1 88-69 27.9 30.8 7.0 15.4 ------4.4 1.5 35.2 67.0 1376 6.3 89-90 29.3 30.9 7.3 17.6 ------29.7 3.2 60.6 .116.1 1437 8.2 90-91 28.4 42.3 9.8 18.0 ------29.7 3.4 72.0 131.8 1505 6.7 --'91-92 30.1 42.3 10.3 20.2 ---29.7 3.5 72.0 136.1 1573 8.6 0 . ""-I 'J2-9J 26.7 42.3 10.8 22.4 ------29.7 3.7 72.0 135.7 1641 8.3 93-94 28.1 42.3 11.4 24.7 -.----29.7 3.9 72.0 140.1 1709 B.2 94-95 29.5 42.2 11.9 20.9 72.5 0.2 29.7 4.1 144.4 211.2 1777 11.8 95-96 28.8 53.0 14.7 22.6 72.5 0.3 29.7 4.3 155.2 .225.9 1859 12.1 96-97 27.7 53.0 15.4 26.5 72.5 0.3 29.7 4.5 155.2 229.6 1941 11.8 97-98 6.15 100.9 25.7 33.2 72.5 0.3 29.7 4.7 203.1 273.1 2023 13.5 98-99 6.4 100.9 26.9 24.4 101.8 0.7 29.7 4.9 232.4 295.7 2105 14.0 99-2000 6.6 100.9 28.3 26.4 101.8 0.7 29.7 5.2 232.4 299.6 2187 13.7 00-01 7.0 100.9 29.7 29.5 101.0 0.8 29.7 5.5 232.4 305.1 2229 13.7 01-02 7.3 100.9 31.2 32.0 101.0 0.8 29.7 5.7 232.4 310.2 2270 13.7 02-03 2.7 162~0 44.9 36.6 101.8 0.9 29.7 6.1 293.5 3B4.7 2312 16.6 03·04 2.B 162.0 47.1 40.6 101.6 0.9 29.7 6.4 293.5 391.3 2353 16.6 04-05 2.9 162.0 49.5 45.1 101.8 1.0 29.7 6.7 293.5 398.7 2395 16.6 05-06 ---162.0 51.9 50.0 101.8 1.0 29.7 7.0 293.5 403.4 2437 16.6 06-07 ---162.0 54.6 55.3 101.8 1.1 29.7 7.3 293.5 411.8 2478 16.6 07-08 ---162.0 57.3 61.2 10).8 1.1 29.7 7.7 293.5 420.8 2520 16.7 08-09 -.-162.0 60.2 67.5 101.8 1.2 29.7 8.7 293.5 430.5 2561 16.8 09-10 -.-162.0 63.2 74.5 101.8 1.2 29.7 8.5 293.5 440.9 2603 16.9 10-11 ---162.0 66.4 1I2.1 101.8 1.3 29.7 8.9 293.5 452.2 2645 17 .1 TABLE 4.31.Fairbanks-Tanana Valley Area.High Growth Scenario.Case 1,0%Inflation New lIydroelectric Trdn~mls~ion Total Cost f!!!~LfJ!ed Callilc~Costs Systems Total Total Tota 1 System of Existing TriVestment OM&R Coa Investme~&R Invl'!s tPil'nt OM&R Investment System Consumption,Average Power ~Capacity CMU Costs Costs Cost~fosts Costs Cos!!.Costs Costs.$Ml4KWH Cos ts t't/KWH 78-79 38.8 -------.-0.3 0.2 ---34.2 032 4.1 79-80 '36.6 ---------0.3 0.2 --.37.0 903 4.1 80-81 39.4 ---------0.3 0.2 ---39.8 931 4.1 81-82 41.1 ---------0.3 0.2 ---42.1 1059 4.0 82-83 35.7 ---_...-6.9 0.3 0.2 ---43.0 1137 3.8 83-84 33.2 ------7.2 0.3 0.2 ---40.8 1215 3.4 94·85 30.4 13.9 3.8 9.1 3.5 1.0 22.4 66.7 1294 5.2 85-86 2lJ.3 18.0 3.8 10.6 3.5 1.0 22.4 66.2 1396 4.7 86-87 26.1 37.8 7.6 12.1 3.5 1.0 41.3 88.2 1498 5.9 87-88 24.1 37-11 7.6 15.6 3.5 1.0 41.3 89.7 1600 5.6 88-89 22.9 40.4 8.1 17.2 3.5 1.0 43.9 93.1 1702 5.5 89-90 23.1 59.3 11.9 lB.7 3.5 1.0 62.8 117.6 1805 6.5 90-91 20.9 65.4 13.1 20.5 3.5 1.0 68.9 124.4 1927 6.5 --I 91-92 21.1 65.4 13.1 22.5 3.5 1.0 60.9 126.7 2049 6.20 CO 92-93 18.3 84.3 16.9 24.6 3.5 1.0 87.8 148.7 2172 6.8 93-94 18.4 84.3 16.9 26.8 3.5 1.0 07.8 150.9 2294 6.6 94-95 18.5 103.2 20.7 28.8 5.3 1.8 108.5 178.3 2417 7.4 95-96 16.9 107.9 21.6 31.5 5.3 1.8 113.2 85.0 2585 7.2 96-97 14.4 126.8 25.4 34.8 5.3 1.8 132.1 200.5 2i54 7.6 97-98 3.8 155;5 31.1 39.5 5.3 1.8 160.8 237.0 2922 0".1 98-99 3.8 184.2 36.0 42.4 5.3 1.8 189.5 274.4 3091 •8.9 99-2000 3.8 \8·1.2 36.8 45.0 5.3 1.8 189.5 286.7 3260 8.8 00-01 3.8 184.2 36.8 48.5 5.3 1,8 189.5 200.4 3396 8.3 01-02 3.8 184.2 36.8 51.5 5.3 1.8 189.5 283.4 3531 "8.0 02-03 1.5 184.2 36.0 51.3 5.3 1.8 189.5 2!l3.9 3667 7.7 03-04 1.5 212.9 42.5 .57.6 5.3 1.0 218.2 321.6 3003 8.5 01-05 1.5 212.9 42.5 60.9 5.3 1.8 218.2 324.9 3939 8.2 05-06 .-212.9 42.5 6<1.3 5.3 1.8 218.2 326.8 4074 8.0 06-07 ---212.9 42.5 67.7 5.3 1.8 218.2 330.2 4210 7.8 07-0B ---241.6 48.2 71.3 7.1 2.6 240.7 370.8 4346 8.5 00-09 ---241.6 48.2 74.9 7.1 2.6 248.7 374.4 4481 8.4 09-10 ---241.6 48.2 78.7 7.1 2.6 248.7 .378.2 4617 8.2 10-11 ---241.6 40.2 82.6 7.1 2.6 248.7 382.1 4753 8.0 J 0 )) -;" ) TABLE 4.32.Fairbanks-Tanana Valley Area.High Growth Scenario.Case 1,5%Inflation------ New Hydroelectrlc Transmiss ton Total Cost New Coal Fired Call!£~Costs ~tems Total Total Total System of Existing TiiVestment OMllf-oal lilves tment-OOll nvestmenr---oM~Investment System Consumption.Average Power .1£!L..-Capacity Costs Costs Cos~Costs ~Costs ~Costs Costs.S MMKl>iH Cos ts.j/KIIH 70-79 30.6 ---------0.2 0.2 ---30.9 832 3.7 79-80 33.9 ---_......---0.2 0.2 ---34.2 903 3.8 80-81 37.5 ---------0.2.0.2 ---37.8 081 3.9 81-82 40.1 ---------0.2 0.2 ---41.0 1059 3.9 82-83 36.7 ------6.9 0.2 0.2 _.-43.9 1131 3.9 83-84 35.6 ------7.2 0.2 0.2 ---43.2 1215 3.6 84-85 33.6 25.4 5.0 9.1 4.4 1.2 29.8 78.a 1294 6.1 85-86 32.4 25.4 5.2 10.6 4.4 1.3 29.8 19.4 1396 5.7 85-87 30.4 43.3 11.0 12.7 4.4 1'.3 57.1 113.2 1498 7.6 87-88 28.7 53.3 II .5 17.1 4.4 1.4 57.7 lI6.5 1600 1.3 88'-89 21.9 57.5 13.0 19.8 4.4 1.5 61.9 124.1 1702 1.3 89-90 29.4 69.9 20.1 22.7 4.4 1.6 94.3 16B.l 1805 9.3 90-91 28.5 10).3 23.2 26.1 4.4 1.1 105.1 185.3 1927 9.6 91-92 :iO.l 101.3 24.3 29.9 4.4 1.1 105.7 191.1 2049 9.4 0 92-93 26.8 138.8 32.9 34.6 4.4 1.8 143.2 239.3 2172 11.0to 93-94 28.1 138.8 34.6 39.2 4.4 1.9 143.2 247.0 2294 10.8 94-95 29.6 180.2 44.5 44.3 8.4 3.6 188.6 310.7 2417 12.8 95-96 28.8 191.0 48.9 51.0 8.4 3.1l 199.4 331.9 2585.12.8 96-91 25.1 237.6 57.9 58.9 8.4 4.0 246.0 392.5 2754 14.2 97-98 6.2 310.2 75.2 70.0 8.4 4.3 318.6 474.3 2922 16.2 98·99 6.4 386.4 94.0 19.3 8.4 4.6 394.8 ,579.2 3091 lB.7 99-2000 6.7 386.4 98.7 1l9.3 8.4 4.8 394.8 594.3 3260 18.2 00-01 7.0 386.4 103.7 99.5 8.4 5.1 394.8 610.1 3396 11.9 01-02 1.3 386.4 108.8 lIO.7 .8.4 5.3 394.8 626.9 3531 17 .1 02-03 2.1 386.4 114.3 123.1 B.4 5.6 394.8 640.5 .3667 11.5 03-04 2.8 483.1 139.3 136.6 8.4 5.8 492.1 776.6 3803 20.4 04-05 2.9 433.7 146.3 151.5 8.4 6.0 492.1 798.8 3939 20.3 05-06 -.-433.1 153.6 161.6 8.4 6.3 492.1 819.6 4074 20.1 06-07 483.1 161.2 185.3 8.4 6.7 492.1 845.3 4210 20.1 07-08 ---602.0 192.8 204.7 16.5 10.2 618.5 1026.2 4346 23.6 08-09 !""--602.0 202.5 225.9 16.5 10.5 610.5 1057.4 4431 23.6 09-10 ---602.0 212.6 248.9 16.5 10.9 618.5 1090.9 4617 23.6 10-11 ---602.0 223.2 274.0 16.5 11.4 618.5 1121.1 4153 23.1 TA BL l3·33.Fairbanks-Tanana Valley Area,High Growth Scenario.Case 2,0%Inflation New Ilydroelectrlc Transml ss Ion Total COst ·New Coal Fired Capacity Costs Systems Total Total Tlltal System of Existin9 Investment OM&R Coal inves tlnent OM&R Investment OM&R Investment System Consumption,Average Power ~Capacity Costs Costs Costs Costs Costs Costs ~sts Costs Cos.!h-1 MHK',lfI Costs,tlKIiH 78-79 33.8 ---------0.3 0.2 ---34.2 832 4.1 79-80 36.6 ---_.----0.3 0.2 ---.37.0 903 4.1 60-81 39.4 --.------0.3 0.2 ---39.8 981 4.1 01-62 41.7 ---------n.3 0.2 ---42..1 1059 4.0 B2-83 35.7 ------6.9 0.3 0.2 _.......43.0 1137 3.8 83-64 33.2 ------7.2 0.3 0.2 ---40.8 1215 3.4 84-85 30.4 13.9 3.8 9.1 3.5 1.0 22.4 66.7 1294 5.2 85-86 28.3 16.0 3.8 10.6 3.5 1.0 22.4 6U 1396 4.7 86-87 26.1 lB.9 3.8 12.1 18.8 2.0 37.7 01.6 1490 5.5 87-88 24.0 18.9 3.8 13.7 .18.8 2.0 37.7 81.3 1600'5.1 88-69 22.9 21.5 4.3 15.0 18.8 2.0 40.3 84.6 1702 5.0 b9-90 23.1 21.5 4.3 15.4 18.8 2.0 40.3 85.2 1805 4.7 90-91 20.9 27.6 5.5 14.1 18.8 2.0 46.4 89.0 1927 4.6 -I 91-92.21.1 27.6 5.5 15.2 18.8 2.0 46.4 90.2 2049 4.4 -I 92··93 18.2 65.4 13.1 20.2 .18.a 2.0 84.2 137.8 2172 6.3'=' 93-94 18.4 84.3 16.9 26.3 18.8 2.0 .103.1 166.8 2294 7.3 94-95 18.5 34.3 16.9 28.8 18.8 2.0 103.1 .169.4 2417 7.0 95-96 16.9 107.9 21.6 31.5 20.6 2.8 128.5 201.3 2585 7.8 96-97 14.3 126.8 25.4 34.8 20.6 2.8 147.4 224.8 2754 8.2 97-98 3.7 155.5 31.1 39.5 20.6 2.8 176.1 253.4 2922 8.7 98-99 3.7 155.5 31.1 42.4 20.6 2.8 176.1 256.3 3091 8.3 99-2000 3.7 155.5 31.1 45.8 20.6 2.8 176.1 259.7 3260 8.0 00-01 3.8 155.5 31.1 41J.4 -20.6 2.8 176.1 262,3 3396 7.7 01-02 3.8 155.5 31.1 51.5 20.6 2.£1 176.1 265.3 3531 7.5 02-03 1.5 155.5 31.1 54.3 20.6 2.8 176.1 265.8 3667 7.2 03-04 1.5 164.2 36.0 57.5 20.6 2.3 204.8 303.5 3303 8.0 04-05 1.5 212.9 42.5 60.8 20.6 2.0 233.5 341.2 3939 8.7 05-06 ---212.9 42.5 '64.2 20.6 2.8 233.5 343.1 4074 8.4 06-07 ---212.9 42.5 67.7 20.6 2.8 233.5 346.5 4210 ,8.2 07·08 -.-212.9 42.5 71.3 20.6 2.8 233.5 350.1 4346 8.1 08-09 ---212.9 42..5 74.9 20.6 2.8 233.5 353.7 4481 7.9 09-10 ---212.9 42.5 78.7 20.6 2.8 233.5 357.5 4617 7.7 10-11 --.212.9 42..5 1l2.5 20.6 2.8 233.5 361.4 4753 7.6 ),.J ').)-) TABLE 4.34.Fairbanks-Tanana Valley Area,High Growth Scenario,Case 2,5%Inflation New Hydroelectric TranslRiss ion Total Cost Ne\'l Coal Fired CaJl.!f..i!t Costs Systems Total Total Totol System of Exf~tin9 I"vest~OM~{oal Investment o"MlR Investment OM&R Investmer,t System Consumption,Average Power ..lli!:-Capacity _-J;~Costs Cos~Costs_~Costs Costs Costs ,'.Costs,$MMKWH Costs.UK\~H 7:1!~79 30.6 ---0,2 0.2 ---30.9 832,3.1 ej,1~6!')"13:9"",,'-_.,-a:z:0.2 ---34.2 903 3.8 ·:fti,';'i!",rt,','~ll:'''S,~':',''1}80"61.,,0.2 0.2 ---37.8 1 981 3.9 8:176'2\11(,'it~Wr 0.2 Q.2 ---41.0 1059 3.9'~"'{;-~1~~;':')"< ~t0:'~'36.7 '6.9 0.2 0.2 ---43.9 1137 3.9 "35.6 ------7.2 0.2 0.2 ---43.2 1215 3.6 84-85 33.6 25.4 5.0 9.1 4.4 1.2 29.8 78.8 1294 6.1 8S-86 32.4 25.4 5.2 10.6 4.4 1.3 29.6 79.4 1396 5.7 86-87 30.4 25.4 5.5 12.7 26.3 2.8 51.7 103.3 149B--6.9 87-88 28.7 25.4 5.8 14.9 26.3 2.9 51.7 104.1 1600 6.5 88-89 27.9 29.6 7.0 17.2 26.3 3.1 55.9 111.2 1702 6.5 89-90 29.3 29.6 7.3 18.7 26.3 3.2 55.9 114.6 1005 6.3 90-91 28.4 41.0 9.B 18.0 26.3 3.4 67.3 127.I 1927 6.6 --'91-92 30.1 41.0 10.3 20.2 26.3 3.6 67.3 131.5 2049 6A -' --'92-93 26.7 116.0 25.6 20.3 26.-3 3.7 142.3 226.8 2172 10.4 93-94 28.1 155.4 34.7 3B.4 26.3 3.9 1Ill.7 206.9 2294 17..5 94-95 29.5 155.4 36.4 44.3 26.3 4.1 161.7 2"96.2 2417 12.3 95-96 28.8 209.6 48.9 51.0 30.4 6.0 240.0 374.8 2565 14.5 96-97 27.7 256.2 60.3 58.9 30.4 6.3 266.6 439.8 2754 16.0 97-96 6.1 328.6 77.7 70.7 30.4 6.6 359.2 519.7 2922 17.8 98-99 6.4 328.0 01.6 79.3 30.4 6.9 359.2 533.5 3091 17 .3 99-2000 6.6 328.8 85.7 89.2 30.4 7.3 359.2 548.1 3260 16.8 00-01 7.0 328.8 89.9 99.5 30.4 7.7 359.2 563.3 3396 16.6 01-02 7.3 328.8 94.5 110.6 30.4 6.1 359.2 579.7 3531 16.4 02-03 2.7 328.8 99.2 123.1 30.4 8.5 359.2 592.7 3667 16.2 03-04 2.6 426.1 123.4 136.6 30.4 8.9 456.5 '728.2 3803 19.2 04-05 2.9 528.3 149.9 151.5 30.4 9.3 558.7 em.3 3939 22.1 05-06 ---520.3 157.4 167.6 30.4 9.6 550.7 893.5 4074 21.9 06-07 -_.520.3 165.3 185.3 30.4 10.3 558.7 919.6 4210 21.8 07-01l ._-528.3 173.5 204.7 30.4 10.8 558.7 947.7 4346 21.6 "08-09 ---5211.3 182.2 225.11 30.4 11.4 558.7 970.1 4481 21.8 09-10 ---528.3 191.3 248.9 30.4 11.9 558.7 1010.8 4617 21.9 10-11 ---528.3 200.9 274.0 30.4 12.5 550.7 1046.1 4753 22.0 TABLE 4.35.Fairbanks-Tanana Valley Area,High Growth Scena ri 0,Case 3,0%Infl ation New Iiyd.'oelectrtc TranslR Iss j on Tota 1 Cos t _~~.£i!~~Il~.£i!i'..__Costs 2tstems Total Total Total System of hhtln9 Inves tment OHIIR·Coa 1 Inves tllleii-t-of·i&R-Inves tijJent OH&R -Investment System Consumptlon.Average Power -1ill.-...Capacity Costs ~P6fs Costs _Costs _Q>sts Costs -Costs Costs Costs,$MMKWH £25tS.tlK1i1l 78-79 38,8 ---------------0.3 0.2 ---34.2 832 4.1 79-ll0 36.6 _.----------.--0.3 0.2 ---37.0 903 4.1 80-81 39.4 ------------.--0.3 0.2 ---39.8 931 4.1 81-82 41.7 --.------.--_.-0.3 0.2 ---42.1 1059 4.0 82-83 35.7 ------6.9 ------0.3 0.2 ---43.0 1137 .3.8 83-84 33.2 ------7.2 ------0.3 0.2 ---40.8 1215 3.4. 84-(15 30.4 13.9 3.8 9.1 -----..3.5 1.0 22.4 66.7 1294 5.2 85-85 28.3 18.0 3.8 10.6 ---.--3.5 1.0 22.4 66.2 1396 4.7 86-87 26.1 18.9 3.8 12.1 ---._.lB.B 2.0 37.7 81.8 1498 5.5 87-88 24.0 18.9 3.8 13.7 ------16.8 2.0 37.7 8t.3 1600'5.1 88-89 22.9 21.5 4.3 15.0 ------10.8 2.0 40.3 84.6 1702 5.0 89-90 23.1 21.5 4.3 15.4 ---'---18.8 2.0 40.3 85.2 1805 4.7 90-91 20.9 27.6 5.5 14.1 .--._-lB.8 2.0 46.4 89.0 1927 4.6 91-92 21.1 27.6 5.5 15 ..2 ------1£1.8 2.0 4[;.4 90.2 2049 4.4 92-93 18.2 65.4 13.1 20.2 --- --- 10.6 2.0 84.2 137.8 2172 6.3 N 93-94 16.4 84.3 16.9 26.3 ---__a 18.8 2.0 103.1 166.8 2294 7.3 94-95 18.5 84.3 16.9 22.6 29.0 0.1 18.8 2.0 132.1 192.2 2417 7.9 95-96 16.9 89.0 17.B 24.4 29.0 0.1 18.8 2.0 136.8 198.0 2505 7.7 96-97 14.4 119.0 17.8 27.4 29.0 0.1 18.8 2.0 136.8 190.5 2754 7.2 97-98 3.8 fi9.0 17.8 32.0 29.0 0.1 HI.a 2.0 136.8 192.5 2922 6.6 98~99 3.8 89.0 11.8 20.4 38.7 0.2 20.6 2.8 148.3 201.3 3091 6.5 99-2000 3.8 89.0 17.0 30.6 28.7 0.2 20.6 2.8 148.3 203.5 3260 6.2 00-01 3.8 107.9 21.6 33.0 38.7 0.2 20.6 2.8 167.2 220.6 .3396 6.7 01-02 3.6 126.8 25.4 35.7 38.7 0.2 20.6 2.8 lil6.1 254.0 3531 7.2 02-03 1.5 126.8 25.4 38.3 30.7 0.2 20.6 2.11 106.1 254.3 3667 6.9 03·04 1.5 155.5 31.1 41.2 38.7 0.2 2U.6 2.6 214.8 291.6 3003 7.7 04-05 1.5 155.5 31.1 45.6 38.7 0.2 20.6 2.8 214.8 296.0 3939 7.5 05-06 ---155.5 31.1 47.2 38.1 0.2 20.6 2.8 214.0 296.1 4074 7.:1 06-07 .-.155.5 31.1 50.3 38.7 0.2 20.6 2.8 214.6 299.2 4210 7.1 07-08 ---155.5 31.1 53.5 30.7 0.2 20.6 2.8 214.8 302.4 4346 7.0 06-09 ---155.5 31.1 56.8 38.7 0.2 20.6 2.8 214.0 305.7 4481 6.8 09·10 ---184.2 36.0 60.2 38.7 0.2 20.6 2.8 243.5 343.5 4617 7.4 10-11 --.104.2 36.8 63.7 3B.7 0.2 20.6 2.B .243.5 347.0 4753 7.3 )) Ii', ) TABLE 4.36.Fairbanks-Tanana Valley Area.High Growth Scenario.Case 3.5%Inflation, New Hydroelectric Transmission Total Cost New Coal Fi red Capa£itr Costs __-2Y.stems To til 1 -JoUl Total System of Existing Investment 0l4&R Coa 1 Investment OM&r Investment OM&R Investment System -Consumption.Average Power ~Capacity Costs !&s ts,C05ts_Costs f~!Costs Costs Costs Cos ts I $MMKllfI''CoHs,¢/Klltl 78-79 30.6 --------- ------0.2 0.2 ---30.9 832 3.7 79-80 33.9 --------------0.2 0.2 ---34.2 903 3.8 80-81 37.5 ---------------0.2 0.2 ---37.8 981 3.9 81-82 40.7 --'!"------------0.2 0.2 ---41.0 1059 3.9 82-83 36.7 ------..6.9 ------0.2 0.2 ---43.9 1137 3.9 63-84 35.6 ------7.2 ------0.2 0.2 ---43.2 1215 3.6 84-85 33.6 25.4 5.0 9.1 ------4.4 1.2 29.8 78.6 1294 6.1 85-86 32.4 25.4 5.2 10.6 ------•4.4 1.3 29.8 79.4 1396 5.7 86-87 30.4 25.4 5.5 12.7 ------26.3 2.8 51.7 103.3 149B 6.9 87-88 28.7 25.4 5.8 14.9 ------26.3 2.9 51.7 104.1 1600 6.5 88-89 27.9 29.6 7.0 17.2 ------26.3 3.1 55.9 m.2 1702 6.5 89·90 29.3 29.6 7.3 10.7 ....,..----26.3 3.2 55.9 114.6 1605 6.3 90-91 28.4 41.0 9.B 10.0 _._.---26.3 3.4 67.3 127.1 1927 6.6 --'91-92 30.1 41.0 10.3 20.2 ------26.3 3.6 67.3 131.5 2049 6.4 --'92-93 26.7 116.0 25.6 20.3 26.3 3.7 142.3 226.8 2n2 10.4w------ 93-94 28.1 155.4 34.7 38.4 ------26.3 3.9 161.7 266.9 2294 12.5 94-95 29.6 155.4 36.4 34.0 61.0 0.3 26.3 4.1 242.7 347.9 2417 14 .4 95-96 28.8 166.2 40.3 39.5 61.0 0.3 26.3 4.3 253.5 366.7 25B5 14.2 96-97 27.7 166.2 42.3 46.4 61.0 0.3 26.3 4.5 253.5 374.7 2754 13.6 97-98 6.2 166.2 44.5 56.7 61.0 0.3 26.3 4.7 253.5 365.9 2922 12.5 9B-99 6.4 166.2 46.7 53.1 85.7 0.7 30.5 6.8 202.4 396.1 3091 12.8 99-2000 6.7 166.2 49.I 59.6 85.7 0.7 30.5 7.1 282.4 405.6 3260 12.4 00-01 7.0 224.4 62.4 67.8 85.7 0.8 30.5 7.5 340.6 486.1 3396 14 .3 01-02 7.3 2B2.6 77.0 76.7 05.7 0.8 30.5 7.8 398.8 568.4 3531 16.1 02-03 U 282.6 00.9 86.7 85.7 0.6 30.5 8.2 398.8 578.1 3667 15.8 03-04 2.8 380.0 104.2 97.7 85.7 0.9 30.5 8.6 496.2 710.4 3803 18.7 04-05 2.9 380.0 109.5 113.6 85.7 0.9 30.5 9.1 496.2 732.2 3939 18.6 05-06 ---380.0 114.9 123.0 05.7 1.0 30.5 9.5 496.2 744.6 4074 18.3 06-07 ---3nO.0 120.7 137.6 1J5.7 1.0 '30.5 10.0 496.2 765.5 4210 18.2 07-08 ---300.0 126.7 153.7 05.7 1.1 30.5 10.5 496.2 788.2 4346 18.1 03-09 ---380.0 133.0 171.3 85.7 1.1 30.5 11.0 496.2 812.6 4481 1B.1 ...... 09-10 ---510.4 165.5 190.5 05.7 l.2 30.5 11.6 626.6 995.4 4617 21.6 10-11 ---5HU 173.7 211.5 85.7 1.3 30.5 12.2 ~626.4 1025.3 4753 21.6 All entries in the tables are in millions of dollars unless noted.The first column is the total cost of the existing capacity.This includes investment, OM&R,and fuel costs except coal costs after 1982-1983 as noted below.This column includes the cost ~f the combustion turbine units planned through 1984 in the Anchorage area.The cost of existing capacity is assumed to be the same for all load growth scenarios and system configurations.This assumption is warrented in this case for two reasons.First,an examination of the load resource analyses for the alternative load growth scenarios and cases reveals relatively little variation in the plant utilization factors among the various scenarios and cases.Second,the.cost of operating the existing capacity is a relatively small part of the overall system costs in the 1990-2010 time period which i~of primary interest in this report. The next three columns present the costs for the new coal-fired capacity. The investment cost is the total of all the individual plant investments.The OM&R costs are the sum of all the OM&R costs of the individual plants.Entries in these two columns begin the same year as the first coal-fired plant comes on line.The coal costs include the coal costs of the new coal-fired capacity. In addition,the coal costs of the existing capacity are included in this column after 1982-1983.(It is subtracted out of the existing capacity after 1982-1983.) The next two columns present the costs for any new hydroelectric capacity that is added.These are the Bradley Lake project,the Watana dam and the Devil Canyon dam.As painted out earlier the Watana.and Devil Canyon costs are divided between the Anchorage-Cook Inlet area and the Fairbanks-Tanana area in proportion to their relative energy consumption in 1994. The transmission system costs are shown in the next two columns.These columns contain the investment and OM&Rcosts for all the transmission lines required.The total investment cost column represents the sum of the new coal- fired capacity investment costs,the hydroelectric capacity investment costs, and the transmission system investment costs. The total system cost is the sum of all the costs (not including the new investment cost column).The total system consumption figures are the same as 114 .~. _------------------0'dL. ,,-u_m •_ :....'....'.:•...~_,...~-..'..···!'I f 'I }~ --CASE 1 ---CASE 2 .••.........•CASE 3 1985 1990 1995 2000 2005 2010 FIGURE 4.5.Power Costs for Anchorage Low Load Growth Scenario 116 £2 CASE ':{ v\;.'(~c'~ .f :;."" '<...••---~------.----_.--------------- CASE 1 ---CASE 2 ............CASE 3 / ...... ....... ...... ~~.........".. .......'.'........./......~..;....... /./ ..;I .I' 30 28 26 24 22 ..c:20 s ~-18Vl--c: Q) oS 16V') l- V) 0 14u cc w..J 12s 0 0- lD 8 6 4 2 1985 1990 1995 2000 2005 2010 FIGURE 4.7.Power Costs for Anchorage High Load Growth Scenario 118 ;~; Power Costs for Fairbanks Low Load Growth Scenario 2010 --CASE1 ---CASE 2 ...••.......CASE 3 200520001995 / / ./ (/ 1 I 1 I 1 I .........J.f·,-.. ::I '......... !I. f J:/t······:1... 1990 30 28 26 24 22 .c 20 .S ~18VI... Ccu ~1:6V') t- V') 0 14u 0:::: w.J 12s 0 Cl- IO 8 6 4 2 1985 FIGURE 4.8. 119 "'------.........----.........-,-~----------~~----------- ,," -.."....-- --CASE 1 ---CASE2 .•••.•.•..-CASE 3 ,....:- . ..................: 30 28 26 24 22 ..r:::.20 $ .¥-18VI-C ~ ~16V') l- V') 0 14u 0::: U-l:s:120 J0- ro J I 8 ./-"'-' 6 4 2 1985 1990 1995 2000 2005 2010 FIGURE 4.9.Power Costs for Fairbanks t~ediurn Load Gro\'~th Scenario 120 CASE 1 ---CASE 2 ............CA SE3 ...----:::::.. . I::..·•••·•·••.••....."'••;. li......P---../:'......: .~.......~.....: / I '/ :-'7/.'... .....I i-t 30 28 26 24 22 20.c: S ~-18In-c: QJu 16--(/') I- U"l 0 14u e:::: w.J 12:s: 0 ~""'a... 10 8 6 4 2 1985 1990 1995 2000 2005 2010 FIGURE 4.10.Power Costs for Fairbanks High Load Growth Scenario 121 --_..--...._......---,----,-----~--~._-------------- where: PW =n:L APC.*----:- i =n 1 (l +r)i PW =Present worth of the cost of power APe i =Average power cost in year} r =Discount rate n =Total number of years. Using this formula the total investment cost and the average power cost over a period of years can be more easily compared~A 7%discount rate is used in these analyses. The results for each of the load growth scenarios for both of the load centers are briefly discussed below. Anchorage-Cook Inlet -Low Load Growth The present worth of the total investment and the present worth of average power costs are shown below. Reference P.W.Total P.W.Average Case Table No.Investment ($)Power Costs (<tikWh) 1 2 2329 78 2 4 2251 76 3 6 2504 70 Case 3 results 1n the lowest cost of power followed by Case 2 and Case 1. Case 2 gives the lowest overall investment costs while Case 3 results in the hi ghest-investment costs. 122 ,I""""Anchorage-Cook Inlet -Medium load Growth Reference P.\~.Total P.W.Average Case Table No.Investment ($)Power Costs (i/kWh) 1 8 3920 83 2 10 3930 83 3 12 3920 77 The present worth of the total investment is almost identical for all three cases.The present worth of the cost of power is the same for Cases and 2,.while the present worth power cost for Case 3 is lowest. Anchorage-Cook Inlet -High load Growth Case 1 2 3 Reference Table No. 14 16 18 P.W.Total Investment ($) 7053 6837 7084 P.W.Average Power Costs (t/kWh) 86 85 83 Again Case 3 results in the lowest present worth for the CDst of power. For this scenario Case 2 results in the lowest present worth .investment with Cases 1 and 3 slightly higher. Fairbanks-Tanana Valley -Low Load Growth Reference P.W.Tota 1 P.W.Average Case Table No.Investment ($)Power Costs (¢!kWh) 1 20 666 110 2 22 699 113 3 24 742 104 Case 3 gives the lowest cost of power while Case 1 gives the lowest investment cost.Case 3 results in the highest present worth investment cost. 123 Fairbanks-Tanana Valley -Medium Load Growth Case 1 2 3 Reference Table No. 26 28 30 P.w.Total Investment ($) 1128 1042 S70 P.~~.Average Power Costs (¢/kWh) 117 111 99 Again Case 3 results in the lowest present worth cost of power.In this scenario however,Case 3 also gives the lowest present worth total investment costs. Fairbanks-Tanana Valley -High Load Growth Case 1 2 3 Reference Table No. 32 34 36 P.w.Total Investment ($) 1642 1587 1527 P.W.Average Power Costs (¢/kWh) 115 110 103 !,..",; Again Case 3 results in the lowest present worth cost of power and the lowest present worth total investment. 124 i~REFERENCES -CHAPTER 4 1.Taylor,G.A.,Managerial and Engineering Economy,O.van Nostrand- Company,Inc.,Princeton,I~J,1964. 125 - i~. f;.;,:.CrFl~~J ENERGY REGULATORY COMMISSION Ii ,;-'0,:41 1,p,laSr,Q REGIONAL OFFICE\j .~_.•1·.-......- 555 BATTERY STREET,ROOM 415-"'"33","n IM.O -::1 in L:'SAN FRANCISCO,CA 941 t 1:.~~"']~hn u March 6,1979 Mr.Robert J.Cross Administrator Department of Energy Alaska Power Administration p.O.Box 50 Juneau,Alaska 99802 Dear Mr.Cross: This will respond to your letter of February 2,1979,requesting our informal review and comments on your Upper Susitna Project Power Market Draf~Report. Although we were unable to make an in-depth review of the draft report due to time and staffing limitations,we do wish to make the following comments: Page g',second paragraph,third sentence.FERC estimated costs are as of Jul)1,1978,not October 1978 as stated. Page 95,seccnd paragraph,last sentence.The San Francisco Regional Office of FERC did include cost adjustments for Alaska conditions in its power value study as it routinely does for all studies in Alaska. Page 95,last paragraph,last sentence.The investment cost estimates of the Fairbanks plant are $1475/kW (@ 5.7570 financing)and $1510/kW (@ 6.875%financing).Cost estimates of the Anchorage-Kenai area plant are $1240/kW (@ 7.94%financing)and $1220/kW (@ 6.875%financing). Page 96,Oil and Natural Gas.Our thoughts on this subject were stated in our October 31,1978,letter to the District Engineer,Alaska District, Corps of Engineers.In that letter we stated that oil~fired combined cycle and regenerative combustion turbine plants were significantly less costly than alternative coal-fired plants for the Upper Susitna River Basin.We are not able to state,however,which alternative is the more probable source.The determining factors would be the Alaska fuel situation and the interpretation of the Fuel Use Act. ..' ~~~.-:.:..__...,_..~.:_.,~,,:.,._,..,;.~._~,~~,_+,,.'._~__~_.•,.'..,·_~.L _•.•~,..,__,_._.~,_•• Mr.Robert J.Cross - 2 - March 6,1979 While the Fuel Use Act prohibits the use of oil or natural gas as primary fuel for electrical generation,the Department of Energy, Economic Regulatory Administration (ERA),is promulgating regulations which will provide for various exemptions.The regulations are ex- pected to be issued in May.We suggest that you contact ERA on this matter. Page 105,item 5.The retirement schedule for combustion turbine is .stated .to be 20 years.Most studies in the Continental United States use 30 years. Pages 159 and 160,Assessment of Feasibility.A cost estimate bf Copper Valley Electric Association1s purchase of Upper Susitna power would be useful to this discussion. Appendix,page 21,3.2.4,Transmission Losses.The 1.5%for energy loss appears to be lowo We appreciate the opportunity to review and comment on your draft report. Sincerely, ~.-e~ Eugene Neblett Regional Engineer February 27,1979 Mr.Robert Cross Department of Energy Alaska Power Administration P.O.Box 50 Juneau,AK 99802 Dear Mr.Cross: R f:-{"\r.-1\./r:-0t~'l,"-v ,_j"tt 1- I I ,..-,-..,~r f \,:..'!'':'C1U,;"asxa lCI~"",,\,..."!J ~Danelle,~j r:..L1 30 r~.-». i I :~i=-"',"C'C':-',,-_.,Pacific Northwest Laboratories;:Xi\S;{~\F;:O,v='n~tgtrP,O.Box 999 ,"Richland,Washington 99352 Telephone (509)942-4745 Telex 32,6345 Thank you for the opportunity to comment on your Draft Power Market Analysis. Both Ward Swift and I read it over and came up with only a few minor comments. The primary focus of our review was the consistency between the body of the report and our background analysis presented in Appendix 3. 1.Page 4,2nd paragraph -The alternative on-line dates of 1990, 1992, and 1994 seem to refer to the interconnection on-line dates for high, medium,and low load growth cases respectively.I believe those dates should be 1986,1989,and 1991.This would be consistent with the dates given in the last line on page 109. 2.Page 8,"ble at bottom -It appears that the costs of power 1isted for Case should be the same numbers listed for the Case 1 of the combi ned sys "tS,1 in the table at the top of page 111.(i.e.,the cos ts . of power should be 6.6,6.9,and 7.5t/KWh rather than 7.0,7.0 and 6.6¢jKWh for the high,medium,and low load growths respectively). 3.P-age 17,Installed name plate capacities -As pointed out on page 19 the totals differ from those used by us in Appendix 3.Most of the differences are relatively minor.The only major difference seems to be the capacity listed for the Chugach Electric Association.As you indicate these differences are due to recent changes in plans to install new capacity.The difference would have a minor impact on the 1978 through 1985 results and practically no impact on the results after 1985. Mr.Robert Cross February 27,1979 Page 2 4.Pages 52, 59,80,and Appendix 3 page 8 -Annual Load Factors -On page 42 and Appendix 3,pa~e 8,both reports are generally in agree- ment that the annual load factor is presently between 46-52%.In Appendix 3 we go on to say that it appears the annual load factor will remain in the 50-52%range du5ring the time horizon of the re- port.On page 80 it is stated that for planning purposes it is assumed that the-annual system load factor will be in the range of 55-60%by the latter part of the century. If the load factor is defined as: ALF where: =GEN CAP *8.760 ALF =Annual load factor (fraction) GEN =Generation (MW) CAP =Capacity (GWH) and use data for the year 2000,low load growth as presented on page 59 we compute an annual load factor of 51%. i.e. i~. A 6424 =LF .=1448 *8.760 .51 This is lower than the 55-60%mentioned on page 80. 5.Page 95,Healy II plant costs -It would be good to poiot out tha~the GVEA estimate is probably in terms of 1985$.. 6.Page 101-102,Conclusions - I think your summary of the alternatives available to Alaska is good. Mr.Robert Cross February 27,1979 Page 3 7.Cover Sheet,Appendix 3 -Enclosed are different cover pages for our report presented in Appendix 3 and the Appendices to our report. Please replace the cover pages you presently have. Thank you for the opportunity to comment on the report. Sincerely, .~c71 (;heoj,JGJ J.Jay Jacobsen Energy Assessment Unit Energy Systems Department JJJ:tw Enclosures ''''''-I''''""'R"Zf"'"1lfII;lI1!"r ------........,..,.,-._ ~I REPLY TO ATTENTION OF: NPAEN-PL-R DEP~R~Mg~~9FTHEARMYALA~~A~'$I'f~I,cf::~RPs OF ENGINEERS u,.,,"'"L,'f?CF'Ei'&.o:S002 ,1.~.\;N'~OR~GE.AL!,?;KA 99510 ..~...,•,.l~\i.-;{"j.,j I --../~ >-:·::-;~l---l:""-~ "'<,,,.$--.-.li.-.;,.-;:J 12 ~AR '919 Mr.Robert J.Cross ,Admi ni strator Alaska Power Administration P.O.Box 50 Juneau,Alaska 99802 Dear Mr.Cross: I am writing to advise you of actions taken in response to your comments on the draft Susitna Supplemental Feasibility Report and also to comment on your draft Power Market Analysis. Your letter of 26 January 1979 transmitting your comments on our draft report lrrived during the final report printing.Any delay at that point Vi 'ld have caused us to miss our deadline which I was unwilling to perml~except under extreme circumstances.On the verbal assurance from your staff that there was nothing of such gravity that the integ- rity of the report would be jeopardized.the decision was made to pro- ceed with the printing as scheduled. I regret that your written comments did not arrive sooner,because the report would have benefited from their incorporation.I am especially sensitive to your contention that insufficient credit was given where APA materials were used.In the future,my staff will be more careful in this regard. Our review of your excellent draft Power Market Analysis has resulted in only one comment.On page 4 you note that the more costly gravity structure for Devil Canyon is "currently proposed ll by the Corps.This is inaccurate in that the gravity structure was presented to insure that estimated costs were sufficient to cover a range of possible foundation conditions at the Devil Canyon site.With appropriate word changes to correct this matter,we find nothing else requiring alteration. Since the Main Report and Appendix Part 1 are already in Washington,please transmit 20 copies of the final Appendix Part 2 to HQDA (DAEN-CWP-W). NPAEN-PL-R Mr.Robert J.Cross 19 MAR 197~ Washington D.C.20314;2 copies to Division Engineer,North Pacific Corps of Engineers,210 Custom House,Portland,Oregon 97209,ATTN; NPDPL;and the remaining 138 copies to the Alaska District,ATTN: NPAEN-US. If you have any questions,Mr.Chuck Bickley at (907)752-5135 can pro- vide assistance. ~ce;;s.~_.._ LI~LE T.S~ LtColOne1,Corps of Engineers Acting District Engineer 2 .~. ...=-.11'IIi!3 DEPARTMENT OF THE ARMY ALASKA DISTRICT,CORFS OF ENGINEERS P,O.BOX 7002 ANCHORAGE,ALASK/'!l95'l, REPLY TO ATT£"lTJON OF: NPAEN-Pl-R i 9 MAR 1979 Mr.Robert J.Cross Administrator' Alaska Power Administration P.O.Box 50 Juneau~Alaska 99802 Dear Mr.t>"oss: 1 am writing to advise you of actions taken in response to you'r comments on the draft Susitna Supplemental Feasibility Report and also to comment on your draft Power Market Analysis. Your letter of 26 January 1979 transmitting your comments on our draft repc~t lrrived during the final report printingo Any delay at that point would have caused us to miss our dead1ine which I was unwilling to per it except under extreme circumstances.On the verbal assurance from 'JI 'staff that there \'ias ooth;ng of such gravity that the integ- rity of ~.le report would be jeopardized.the decision was trade to pro- ceed with~k;r.''''inting as scheduled~ I regret that your written comments did not arrive sonnert because the report would have benefited frOl')1 their incorporation.I am especially sensitive to your contention that insufficient credit was given where APA materials ware used.In the future~my staff will be more careful 1n this regard.~... OUr review of your excellent draft Power Market Analysis has resulted in only one C01ill'Ilent.On page 4-you note that the more costly gravity structure for Devil canyon is IUcurrently proposed"by the Corps.This is inaccurate in that the gravity structure was presented to insure that estimated costs were sufficient to cover a ra.nge of possible foundation conditions at the Devil Canyon site.Hi,ttCappropriate word changes to correct this matter,we find nothing ~lse r~quiring alteration. \'<"<";~:~~C Since the Main Report and Appendix ?a~t 1 a~already in Washington~~~~& transmit 20 copies of the final Appendi~",p,~'H~t 2 to HQDA (DAEN-04P-¥,~\ o ~ ~:z~~ ;',&....:f. 7;>76_191'0 NI'AEN-Pl-R Hr.Robert J'.Cross I9 M'.~1W~ Uashington DwC.20314;2 copies to Div1s1on £ng1neer*rlorth Pacific Corps of Engineers)210 Custom House,Portland.Oregon 97209.iHTN;~~PDPL;and the remaining 138 copies to the !\iaska District,Allil: NPA8{-US.. If you have any questions,Mr.Chuck Bickley at (907)752-5135 can pro- vide assistance. Sincerely yours, :./LTC.Vemelle T.Sroith VERNELLE T.SMITH Lt Colonel.Corps of Engineers Acting District Enginegr 2 .""":&-------------------------------------------,C' ~""?'e...,~4l~tit1r1:1 ~C 1,..."", iVL Su (ivan A1avo r March 1,1979 Robert J.Cross,Administrator Department of Energy Alaska Power Administration P.o.Box 50 Juneau,Alaska 99802 Dear Mr.Cross: 'l'h is letter responds to your letter of February 2,1979,which requested informal comments on the draft Power Market Analyses of the Upper Susitna River Project. Mr.Stahr is out of town and I am writing without knowledge of his personal opinion and comments.The Municipal Light and Power's staff comments appear in the two attached memorandums.Mr.Stahr may forward more comments upon his return. Thank you for the opportunity to review the draft.If you have any questioLs or want more comments please do not hesitate to con- t.act us. Very truly 'lrs , ~~r:J~- Max Foster Revenue Requirements Supervisor MF:bw Enclosure PROVIDE FOR TOMORROW SAVE ENERGY TODA Y. .-. j ,...,.:.~,...":-,';F'"n~~~~~:",IDJm:lRw~~~ March 23,197) Mr.Jim Cheatham U.S.Department of Energy Alaska Power Administration P.O.Box 50 Juneau,AI<99801 JAY 5.HAMMOND GOVERNOR _--...--"'T""'----'POUCH AD-JUNEAU 99811 COOE.INn l'l);'lt t PHONE 465-3577 Subject:Power Market Analysis -Draft on the Upper Susitna River Project State I.D.No.79020902 Dear Mr.Cheatham: ,~The Alaska State Clearinghouse has completed review on the subject project. The State Clearinghouse has no comment on this project. This letter wL satisfy the review requirements of the office of Management and L~dget's Circular A-95. J1'1/cz ~~:~ ..S·tate,-Federal -------------------------)'----~------------------------- "1 ..; Municipality of Ari.cl\orage MEM0.RANDUM L."I"E:February 15,1979 TO:Thomas R.Stahr,General Manager FROM:H.C.Purcell,Assistant Chief Engineer SUBJECT:DOE APA UPPER SUSITNA RIVER PROJECT POWER MARKET ANALYSES I have reviewed the January 1979 draft of this report and find nothing controver- sial in it.There is an error,and there are a few points I will comment on, none of which,hmvever,affect the conclusions reached. /' I~/,l.r r~,.~ On page 33,Table 5 shows AML&P generation in 1965 as 156.2 GWH.This results in area growth 1964-1965 of 34.4%and 1965-1966 growth of -0.6%.AML&P generation in 1965 was actually 101.5 GWH.This changes the area total in 1965 to 407.0 GWH, 1964-1965 growth to 18.5%and 1965-1966 growth to 12.7%. nn pages 37 and 38,the report states ".,.correlations with weather ...seem- ed indeterminable or of little significance,"and "Energy use and weather com- parisons were incc ..clusive."This does not agree with my work or with plain common sense.Growth between 1973 and 1977 is used to forecast energy requi rements.In three of these four years,1974,1976 and 1977,the weather was warmer than normal. Ignoring the influence of weather depresses the growth rate.However,this does ~not affect the report materially,since it winds up using three different growth {rates (low,medium and high)in its market analyses.. It is interbti ig that the situation hasn't changed in twenty years.Page 98 lists six major hydr(projects with much better economics than the Upper Susitna.But they all remail tied up by "major environmental and land use problems." On pages 100-102 the report brushes off exotic energy sources as "not realistic plilnning alternatives ..,"I applaud this,but suspect that much more work will have to be done to convince the vocal proponents of "natural energy." On page 104 the report specifies "System reserve capacity of 25 percent for non-in- terconnected load centers and 20 percent for interconnected systems." I checked these numbers against the PROBS runs I made in connection with DOE regulations on trans iti ana 1 facil ities.For the Anchorage area at present,PROBS showed a loss of load probability of 0.2 days per year with a peak load of 466.3 MW.On the same basis,25%reserve capacity would correspond to.a peak load of 468.8 MW.25% reserve capacity would result in LOLP only slightly over 0.2 days per year.With -the larger interconnected system ten or twelve years in the future,20%reserve capacity will probably provide reasonable LOLP. Page 34 of the Battelle Informal Report schedules a 200 MW steam plant to be on line in 1982,three years hence.Yet Battelle page 22 says "the 5 to 6 year sche- du'ling period [from final site selection to commercial operation]appears reason- ab'le."Either eEA is about to break ground for its coal-fired steam plant or . Battellels dates are inconsistent.Again,however,it doesn1t really matter.The r-~elative economics of Susitna vs.coal-fired steam would not be affected. '. .I., Municipality 01 Anchorage MEMORANDUM DATE: TO: FROM: March 1,1979 Thomas R.Stahr,General Manager,ML&P Max Foster,Revenue Requirements Supervisor,HL&P SUBJECT:DOE-APA Upper Susitna River Project Power Market Analyses This memo comments on the Alaska Power Administration's Upper Susitna River Project Power Market Analysis draft dated January 19790 My impression is that the demand projections for the Anchorage area are conservative.I also think that the installed cost of coal plants is conservative.The Susitna project costs are probably the mosJ:reliable cost estimates appearing in the report. I am not happy with the methodology developing the cost of coal..I think coal could actually cost much more than $1.00 to $1.50 per million BTU.The inflation rates used in the analysis (0%and 5~) seem low in light of recent trends. Significantly,despite the conservative assumptions contained within ~qe report,the Susitna project represented the least cost option in, "er.y case~ My page by page review of the report elicited the following comments': ,J Page 37 -'he lack of correlation to weather and price disburbs me~It may indicate improper equation specification caused by omitting important variable or failing to insert dummy variables in the regression equations to correct for cyclical abnormalities.Additionally.,it seems to me demand projections ...~QY rate cl~ss 'would_be more statistical,ly pigniiicant.C0f"?-/c(-((,~""t,...f WC!-I{-fi-...o.r I.J'S'T?C"\.:'1 O"l a.;v'/o'l"f'!-1 f y )C'1c/!CQ!h-q.J/.J bk~rl<)"'t"o,,,,p(~(:1.117, Pase 77 -The shape of the Anchorage Area load duration curve suggests that a heavy proportion of generation for the area could be large base load increments.This is very favorable for hydroelectric development. Page 94 - I don't like the treatment of 0 &M costs.How does this relate to prosent actual Anchorage labor costs and trends? I think the prices should be measured directly,not arbitrarily increased. Page 150 -The pipline terminal's 37.5 ~M generation plant is not interconnected wi th CVEA.It is not a cogenera t ione;_- fa c i litY•-r;,-r-c«e >1 er9 )"-FO C //1 '1':.0,/;/'c:1..-f1~c r---f J.c O--t-l,) I,'. Memo to Thomas R.Stahr,General Manager Harch 1,1979 Page 2 Appendix 3,Pages 66 to 75-Where is the present worth or annualized cost of power computed?This is a major change from the earlier ECOST2 model.I think the present worth analysis is an impo~tant part of any power cost analysis. In general,the analysis seemS complete.The conclusions echo those of previous studies.From an economic prospective,the Susitna Project is unquestionably justified.Its time to stop revising ,!easibili ty analyses and get on with l'iCens l.ng and ,::onstruction../J't'/1 e HF:bw :',_.-----------~ SECTION H TRJl.NSMISSION SYSTEM None of the OMS comments were directed at the engineering aspects of the transmission system. There are therefore no changes made to this section.Costs of tra~smission have been up- da ted and appea r inSect;on B,Proj ect Descript ion and .Cost Estimates.The economic justification for the transmission intertie is discussed in Section G.Marketability Analysis. SECTION 1 ENVIRONMENTAL ASSESSMENT FOR -TRANSMISSION SYSTEMS This section has not been supplemented becausE; no changes were made to the transmission plan~ " SECTION H TRANSMISSION SYSTEM None of the OMB comments were directed at the engineering aspects of the transmission system. There are therefore no changes made to this section.Costs of transmiss;nn have been up- dated and appear in Section B Project Description and Cost Estimates.The economic justification for the transmission intertie is discussed in Section t Marketability Analysis. SECTION I ENVIRONMENTAL ASSESSMENT FOR TRANSMISSION SYSTEMS This section has not been supplemented because no changes were made to the transmission plan.