Loading...
HomeMy WebLinkAboutAPA2975INTERIM FEASIBIUTY REPORT SOUTHl L RAILBELT AREA ALASKA UPPER SUSITNA RIVER BASIN .i1:J TK 1425 .S8 A23 no.2975 ROELECTRIC POWER RELATED PURPOSES •~·.CORPS Of E~ ~*I:)III:- C *Z~I *I 5?,05I 1-I .; '".....Z eft....-~.... ·...".Al·177 , 12 DECEMBER 1915 APPENDIX II PERTINENT CORRESPONDENCE AND REPORTS OF OTHER AGENCIES Table of Contents Tl< 1~'2..S .~td A23 n .29tS Letter from:Date Page------_.__.- Alaska Power Administration 20 November 1975 1 Alaska Power Administration 10 December 1975 5 Alaska Railroad 10 June 1975 10 Bureau of Indian Affairs 3 November 1975 11 Bureau of Land Management 13 March 1975 12 Bureau of Land Management 15 July 1975 13 Department of Transportation 11 November 1975 14 Federal Power Commission 12 August 1975 16 Federal Power Commission 20 August 1975 21 Federal Power Commission 4 December 1975 22 U.S.Weather Bureau Undated Draft 27 <0 Alaska Energy Office 6 October 1975 43<0 N Division of Parks 4 April 1975 44r--Division of Parks 4 June 1975 46-=t0 State Policy Development and Planning 9 June 1975 47 0 State Policy Development and Planning 12 September 1975 520 0 Stan Justice 29 May 1975 53I.!') I.!')Matanuska Electric Association 10 June 1975 55 "John L.Cerutti,P.E.13 June 1975 57M M Barbara Winkley 7 October 1975 58 Mountaineering Club of Alaska 7 October 1975 59 Fairbanks North Star Borough 13 October 1975 60 T.R.Slaton.P.E.15 October 1975 62c.H.Swanson,Jr.,M.D.21 October 1975 63 Anchorage Chamber of Commerce 22 October 1975 64 Knik Kanoers and Kayakers 17 November 1975 65 Report of U.S.Fish and Wildlife Service,10 October 1975 Ala,a HI"urrf', Library {I;InFor nl ('}Il'enices An -110 age Ala I a AplJend i x II i IN lIEPLY REFUl TO: 700 AIRMAIL United States Department of the Interior ALASKA POWER ADMINISTRATION P.o.BOX 50 JUNEAU.ALASKA 9Gl6JOX 99802 November 20,1975 Colonel Charles Debelius Corps of Engineers Alaska District Box 7002 Anchorage,AK 99510 De ar Colonel Deb elius: This covers several items discussed in telephone conversations of November 11 and 12,1975,with Eric You1d and Gary Flightner of your office.Subjects discussed included: 1.Consideration of adding an additional skeleton bay at both Watana and Devil Canyon powerplants for future peaking capacity. 2.A request for AP A views on any benefits that might be associated with interconnecting Railbelt area power loads. 3.Revisions in the designs and estimates for Devil Canyon and Watana which resulted from internal Corps review,specifically a require- ment for capability to evacuate Watana Reservoir in a short period of time which would require a large increase in outlet capacity and costs . We do not have the details on items 1 and 3,but it is apparant that these changes could have significant impact on power marketability. Therefore,we would like to offer comments on the changes as well as furnishing the requested views in interconnection benefits. Append;x II 1 .,"1:.~,.~.,('"•••".-,~4 ~. 2 1.Additional Peaking Capacity The plan included in your draft report is premised on a 50 percent annual plant factor with provisions of a skeleton bay in each powerplant for future additional peaking capacity.The 50 percent figure is as recommended by APA;we understand the additional skeleton bays are judgement additions by the Corps.The costs and benefi ts associated with the provisions for \ added peaking capacity are not identified in the Corps draft reports. Our draft power market appendix (September 1975)includes some of the reasoning behind our recommendations for a 50 percent plant factor. This is premised on rather simplistic assumptions relative to the role of a major hydro plant in the Railbelt area.Our data and studies have not, at least thus far,given any indication that markets would exist for addition- al peaking capacity at this project until well beyond the year 2000. We do not object to including the single skeleton bay for peaking addi tions at the twopowerplants.However,we do not have any support for assign- ing b enefi ts to this future added cap aci ty . It is our suggestion that the incremented costs for the skeleton bays including waterways be identified and excluded from your basic benefit-cost comparison. This would amount to:0)demonstrating feasibility based on the 50 percent plant factor,and (2)demonstrating costs for providing the future option separately. We do not concur in the concept of adding a second skeleton bay at each of the two plants,since we believe that any potential markets for such additional capacity are too remote to be considered in a feasibility determination.' 2.Interconnection B enefi ts A number of previous studies by APA and others provide good indication that a Railbelt intertie would be justified eventually without development of the Upper Susitna Project.Possible situations that would bring about the justification include: 1.Bulk power supply to the Interior from a future large thermal station (coal or nuclear). 2.Any new sizable power demands at points between Anchorage and Fairbanks.An example is the concept of electric drive for pipeline pumping stations.or a possible new community in Susitna drainage. Appendix II 2 "-;--------------------------.'..--lQi:~: 3 The existing studies indicate advantages associated with load diversity and shared reserves would be relatively minor.For example,as between the Anchorage and Fairbanks areas there is not a great diversity on a seasonal or hourly basis,and any advantages in reserve sharing would be limited by reserve requirements imposed because of transmission reliability . A further limit on intertie advantages is disparity in size of market. Anchorage area loads are several times larger than Fairbanks area loads. Areas of potential intertie benefits include added flexibility in day to liay scheduling of generation,increased flexibility in selecting new power sources,and added flexibility in power sale and interchange arrangements. We believe it would be consistent with your procedures for benefit evaluation to examine intertie benefits on the basis of alternative costs for achieving the intertie benefi ts.The APA evaluation of alternati ve power costs (power market study)and the FPC benefit determination assmne separate coal fired plants for the Anchorage and Fairbanks areas.Location assumptions of Beluga and Healy for the plants are consistent with the evaluation,with aggregate plant capacity equivalent to the Susitna plan. Following this lfalternati"\Telf,it would be logical to asSume that the next major power addition for the Railbelt would be a large thermal plant in the Beluga area with an intertie between ~eluga and Healy. For your benefit evaluations,you might assume a completion date of around 1995 and a construction cost of around $60 million as the alternative cost of achieving the intertie benefits.This is premised on rough estimates of costs of a 230 kv intertiebet\.veen Beluga and Healy including necessary substation costs. 3.Requirement for Rapid Evacuation of Watana Rese.rvoir We understand that the requirement under consideration is essential evacuation of active capacity over afour month period assuming record high inflows for the period.We also understand that this is now a standard design criteria for Corps reservoirs subject to exception on an individual basis. Appendix II 3 --------"'-------------- 4 It occurs to us that such a requirement would be essentially infeasible for most large reservoir projects,but may very well be desirable for many structures in and near populous areas. From the viewpoint of project operation,including structural safety, we do not see a requirement for the suggested rapid evacuation of Watana Reservoir.The long winter period and very large hydraulic capacity of the powerphmt would appear thoroughly adequate as provision for reservoir draw down . 4.Fuel Conservation Aspects The existing evaluation procedures do :r:ot provide specific recognition of fuel conservation aspects of water power development except as purchase cost of fuel is included in the evaluation of alternative costs or benefits. From the viewpoint of the nation's energy economy,the development of the hydro project provides a new source of power which is recognized under NED objectives.It results in a net increase in national fuel supplies because less energy would be taken from thermal plants over the life of the hydro project.The actual fuel savings would include substantial amounts of oil and natural gas immediately on completion of the project and longer term savings of coal. We believe it is quite well established that current and near future fuel prices are generally below the probable long-term value of these fuels to the nation,and to this extent the project benefits are understated. In its benefit evaluation,FPC used coal prices of 60¢and 50¢per million. Btu for the Fairbanks and Anchorage areas,respectively.In the APA alternative power cost evaluation,the assumption is made of a price range of $1.00 to $1.50 as 1985 coal cost in 1974 dollars (no inflation). If the higher values are appropriate,and assuming no further increase in real value of the fuels after 1985,project benefits will likely be on the order of 5 to 10 mills per kilowatthour higher than indicated by the FPC estimates. We recognize that FPC procedures require use of current cost levels in their benefit determinations.However,I am sure that all involved recognize that the procedures were developed during a period when fuel prices and real cost of energy in the economy were on a long-:term down trend relative to other prices. Sincerely yours, Appendix II 4 ev{(fL~ Rob ert J.Cross . Acting Arlministr3tor I~~t:PLY REtLR 11"0: 700 United States Dcpartmen~of the Interior ALASKA POWER ADMlt'lJSTRATJON P.O.BOX 50 i JUNEAU.ALASKA 99802 December 10 #1975 Oolonel Charles A.Debelius Dilstrict Engineer O:)rps of Engineers BI:)x 7002 Aln.chorage.AK 99510 Dear Colonel Debelius: The enclosed reports cover the Alaska Power Administration1s studies· on power markets #operation and maintenance requirements,trans- mi.ssion systems,and transmission sye tem environmental assessment for the proposed Upper Susitna hydroelectric development.We understand the AP A reports are to be included as portions of Technical Appendix I for the Corps of Engineers report on the proposed project with the following designation: Appendix I,Part G.Report on Power Markets (including estimates of proj ect operation.maintenance,and replacement requirements). Appendix I.Part H.Report on Project Transmission Systems. Appendix I,Part I.Transmission System Environmental Assessment. Authority The AP A studies were prepared in support of the Corps of Engineers evaluation of hydroelectric development of the Upper Susitna River Bal;in in Alaska under a January 1972 study resolution by the U.S. Senate Public Works Committee.Authorization for the AP A work includes Sec:tion 5 of the Flood Control Act of 1944 concerning Interior Department resiponsibilities for transmission and marketing of,power from Corps of AppendiX II 5 Save Energy and You Serve A merical 2 Engineers projects,and the Act of Au gus t 9,1955,concerning Interior Department investigations of Alaska water and power development potential.The project plan was formulated in accordance with the Alaska provisions of the Army-Interior Agreement of March 14,1962. Plan of Development The proposed plan of development includes the Watana dam and power- plant with installed capacity of 792,000 kilowatts,followed by the Devil Canyon dam and powerplant with installed capacity of 776.000 kilowatts,for a total capacity of 1,568,000 kilowatts.The Corps of Engineers studies indicate the plan would have annual firm energy potential of 6.149 billion kilowatt hours based on evaluation of critical period water supply.Average annual energy production would be 6.85 billion kilowatt hours.The plan includes transmission lines to the Anchorage-Cook Inlet area,and Fairbanks-Tanana Valley area, and necessary switchyard and substations.The transmission facilities are described below: Transmission System Studies and Transmission Environmental Assessment The main elements of these studies were evaluation of alternative corridors for locating proj ect transmission facilities,considering environmental.engineering,reliability and cost aspects,and prepara- tion of designs and cost estimates for transmission systems needed for alternative project development plans.The corridor studies concern general locations of facilities with actual route locations to be determined in the more detailed studies following proj ect authorization. It was concluded that the most desirable corridor locations would follow existing surface transportation sys terns,rather than pioneering new corridors for the transmissi~n facilities. The transmission plan and cost estimate for the proposed hydro development plan includes the following features:1)two single-circuit Z3Q-kv lines from \'iatana to Devil Canyon (30 miles);2)two single- circuit 230-kv lines from Devil Canyon to Fairbanks (198 miles),with an intermediate switching station at Healy;3)two single-circuit 345-kv lines to points on the North Shore of Knik Arm (136 miles),with an intermediate substation in the vicinity of Talkeetna;4)switchyards at the two powerplants;and 5)substations at Fairbanks.and in the Point Mackenzie area.Estimated construction costs for the transmission Appendix II 6 system are $256 million based on January 1975 price levels.It is esti·· mated that three years would be required for construction following completion of the detailed route studies,final designs,and acquisition of necessary rights-of-way. The most serious conflicts in the final route selection will likely be encountered in the Nenana Canyon route through the Alaska Range.The Fish and Wildlife Service has recommended that a route west of the Parks Highway be selected through the Nenana Canyon to minimize possible conflicts with raptor habitat.Any route through the Canyon area would· ilwolve lines visible from portions of 1.fount McKinley National Park and the FWS proposal would place portions of the route within park boundaries. A'PA considers use of the corridor through the Nen.ana Canyon will result ill substantially less environmental damage than would the pioneering of nlew corridors through the Alaska Range. Additional conflicts are anticipated in final route selection along the approaches to Anchorage because of the Knik Arm,.and topography,and land use and ov-rnership patterns on possible routes around Knik Arm. Cost estimates presented in this report assume delivery of project power to points on the CEA transmission system north of Knik Arm.It is rf~cognized that the detailed studies following authorization would need to consider several alternative plans to transmit power across or around Knik Arm to Anchorage. Based on informal consultations with the State Archeologist,the corridors Ulnder consideration involve known and potential archeological sites. Archeological surveys would be needed as part of the final route studies. Inadvertent discovery of an unsuspected site at a later stage would entail either relocation of a line segment or salvage of the site under applicable laws and regulations. The initial plan does not include transmission facilities to serve the Copper Valley area.Such facilities may be justifiable as a future stage of the system. Operation,Maintenance,and Replacement APA's evaluation of annual costs,operation,maintenance,and replace- ment are summarized on Exhibit 2 of the report on power markets.The elstimates cover the full range of operations and marketing activities. Annual "OM&R II costs for the proposed plan are estimated at $2,400,000 based on 1975 price and wage levels. Appendix II 7 4 Power Market The P;P A power market report includes our estimates of future area power requirements,the portion of the requirements that might be served from the Susitna Project.a review of available alternatives to hydro develop- ment,and evaluation of repayment requirements. As indicated below.we estimate that an average rate for firm energy delivered at wholesale in the Fairbanks and Anchorage areas at 21.1 mills per kilowatt hour would be needed under present Federal repay- ment criteria: Devil Canyon Watana Total System WS.Elevation Completion date Installed Capacity,MW Annual Firm Energy, billion kwh Annual Secondary Energy, billion kwh Construction Costs.$1,000 Interest During Cons truc1i.on $1,000 Total Investment,$1,000 Total Annual Costs,$1000 1,450 1990 776 3.05 432,000 2,200 1986 792 3.10 1,088.000 1,568 6.15 0.7 1,520,000 248,000 1,768,000 115,612 Assumed rate for secondary energy,mills/kwh Required average rate for firm energy,mills/k-wh 10 21.1 These computations are premis.ed on January 1975 price levels and future cost increase would be reflected in higher cost for project power. Our review of alternative power sources indicates that the Susitna power would be substantially more expensive than present power from natural gas in the Cook Inlet area.but less expensive than alternative power supplies from new coal-fired plants.It is APAls view that alternative costs for power from coal-fired steamplants is an appropriate measure of relative merit of the Upper Susitna proposal. AppendiX II 8 5 Conclusions This letter reflects the findings of the Alaska Power Administration and does not represent a position by the In.terior Department on the Susitna Project. AP A considers the general corridor locations,the transmission plan and estimates.and the operation.maintenance and replacement evaluations appropriate for purposes of determining feasibility of the Upper Susitna Pr~ject.From the viewpoint of power markets.the proposed development plaJ'l including the Watana and Devil Canyon units appears feasible and relCltively more attractive than the other alternative hydro development plaJ'ls considered in the Corps studies. We are not in agreement with the Corps'appraisal of the potential Denali unit..and we believe that future studies may demonstrate that Denali is a d«~sirable future addition to the proposed plan. It is APArs view that the proposed plan of development,including Watana and Devil Canyon units,is feasible frem the viewpoint of power market- ing and repayment requirements. Sincerely yours, Acting Administrator Enclosures Appendix II 9 -----~-----,---~~----,--~~--;-------_......._---- DEPARTMENT OF TRANSPORTATION FEDERAL RAILROAD ADMINISTRATION THE ALASKA RAILROAD P.O.Box 7-2111 Anchorago.Alaska 99510 June 10,1975 Mr.Charles Welling Economic Section,Corps of Engineers Box 7002 Anchorage,AK 99510 Dear Mr.Welling: You have requested information from us concerning possible benefits that could be derived by the Railroad as a result of the construction of a dam on the Susitna River. One direct benefit would be a reduction in periodic damage to roadbed and track during break up.Large ice jams would be eliminated,which on previous occasions have caused flooding and washing out of grade with a subsequent interruption in train service to Fairbanks.Average damage of such a washout has run about $50,000. A controlled flow of the Susitna would also reduce bank protection work.It is estimated that a yearly expenditure of $50,000 is cur- rently required to provide the necessary rip rap and revetment work. Sincerely, 'J.t-qVf~t!4~ T.C.Fuglestad Chief Engineer Appendix II 10 UNITED STATES DEPARTMENT OF THE INTERIOR BUREAU OF INDIAN AFFAIRS .klneau Area Office P.O.Box 3·8000 Juneau,Alaska 99802 IN REPLV REFER TO: November 3)1975 Memorandum To:O"istrict Engineer)Department of the Army Anchorage From:Alrea Di rector Subject:Review of draft environmental impact statement for Hydroelectric Development)Upper Susitna River Basin)Southcentra1 Rai1be1t Area tAl as ka (ER 75/942) General Comnents: The document is presented in a good format so the document is readable and easy to follow through.There appear to be provisions made to avoid any future land conflicts under the Alaska Native Claims Settlement Act. Specific Comments: We have no further comments. Appendix II 11 United States Department of the Interior BUREAU OF LAND MANAGEMENT State Office 555 Cordova Street Anchorage.Alaska 99501 IN ~EPLV ~EFER TO 2650.11 (931) MAR 13 1975 Mr.Lee Thompson U.S.Army Corps of Engineers Real Estate Divi~ion P.O.Box 7002 Anchorage,Alaska 99510 Dear Mr.Thompson: Since your telephone inquiry of February 19,1975,we have done some research on the relationship between power site reserves and Alaska Native Claims Settlement Act withdrawals and have come to the following conclusion.A 25-township withdrawal under section 11(a)(1)of the act (PL 92-203,85 Stat.688)predominates over all other withdrawals except National Park System and National Defense withdrawals.A deficiency withdrawal under section ll(a)(3)of the act does not. The reason for this difference is found in the differing authprities under which the two types of withdrawals are made.The 25-township withdrawals are by direct act of Congress "the following public lands are withdrawn ••.II The deficiency withdrawals,however,are public land orders signed by the Secretary of the Interior under a restricted authority from Congress,"The Secretary shall withdraw three times the deficiency from the nearest unreserved,vacant and unappropriated public lands."J/(Emphasis added).The land within the power site reserve is segregated from a deficiency withdrawal under ANCSA because it is "reserved public land"and Congress did not give the Secretary the authority to make deficiency withdrawals from reserved lands. Whatthis all means is that Native villages and regions may select power site land if it lies within their section ll(a)(l),25-township withdrawal, but they may not se1ec~power site land from within a section 11(a)(3) deficiency withdrawal. Sincerely yours, Append;x II 1211PL92-203,§ll(a)(l)II PL 92-203,I ll(a)(3)(A) United States Department of the Interior BUREAU OF LAND MANAGEMENT Anchorage District Office 4700 East 72nd Avenue Anchorage,Alaska 99507 IN REPLY AEFEfit TO: 1780 (110) JUL 1 5 1975 Mr.Henry Nakamura Department of the Army Alaska District Corps of Engineers P.O.Box 7002 Elmendorf AFB,Alaska 99510 Dear Mr.Nakamura: Impacts of the proposed Devils Canyon,Watana Creek and Denali hydroelectric power project on BLM lands,resources and programs is difficult to access.The information necessary to do a thorough analysis of these projects,simply isn't available.The reports of the impacts onthe various resources drafted by our staff,briefly summarizes the basic data that is available,recognizing that more detailed information is necessary. Management of the recreation activities which would be generated by development of the proposed projects will also be an important con- sideration.If the lands adjoining the future reservoirs go into· private ownership,the on-the-ground recreation management responsi- bilities may better be handled by an agency other than the BLM;the State may be a good choice.However,in order to insure public access, it is strongly recommended that the BLM,through whatever means pos- sible,retain ownership of public access points to the lake.The actual management,operation and/or ultimate ownership could rest with another public agency after a more detailed cost effectiveness analysis were undertaken.Naturally,if the adjacent lands remain in Federal ad- ministration,we would be interested in developing and managing a recreation program.With the present land status situation,it is impossible to determine whether or not the adjoining lands will remain in public ownership. A more thorough analysis will be made during the impact statement review process. M Sincerely,. \...f 01.•~/.- .t1t#.~Jt4 ~;fv~l'r Donovan Yingst Acting District Manager•Appendix II 13 .tlNITED ~JATES GOVERNMENT, MemorandulJl DEPARTMENT OF TRANSPORTATION OFFICE OF THE SECRETARY SUB.iECT, FROM , TO DATE: Hydroelectric Pm"er Develo[Jment,Upper In reply Susitna River Basin,Southcentral Railbelt Area,reler to, Alaska Secretarial Representative,Region 10 District Engineer Corps of Engineers Anchorage,Alaska November 11,1975 Attached is the only comment received from DOT agencies on the subject EIS. ~P .Regional Representative of the Department of Transportation,Region 10 Attachment Appendix II 14 DEPARTMENT OF TRANSPORTATION UNITED STATES COAST GUARD MAIL-INO ADDRESS, COMMANDER (do lJ 17TH COAST GUARD ISTRICT FPC SEATTL.E "'7' 1 October 1975 From:Commander.Seventeenth Coast Guard District •To:Secretarial Representative.Region 10,Seattle,~IA. Attn:CAPT R.T.BROWER Subj:Review of EIS for Hydroelectric Power Development,Upper Susitna River Basin.Southcentral Railbelt Area.Alaska; comment concerning 1.Subject EIS has been reviewed and the only significant Coast Guardl impact would be the i'ncrease in recreational boating activity on the newly created lakes behind the dams.No other areas of Coast Guard interest were revealed.k __ &GRANTHAM By di rl:!cti on Appendix II 15 ~\~1li CC' ----~------rl-·-------·- FEDERAL POWER COMMISSION REGIONAL OFFICE 555 SATTERY STREET,ROOM 4 t 5 SAN FRANCISCO.CAL./F.9411 t August 12,1975 Colonel Charles A.Debelius,District Engineer Alaska District,Corps of Engineers P.O.Box 7002 Anchorage,AK 99510 SUbject:Power Values for Devil Canyon - Watana Project (Your NPAEN-DB-HY) Dear Colonel Debelius: In response to your letter o£17 April 1975 requesting subject power values,we are furnishing the values shown following.The power values are based on a January 1,1975 price level and public non-federal and federal financing,the latter at 5-7/8%interest rate.Public-nonfederally financed values were estimated using the same methodology employed in c9mputed federal values except that fixed charges were calculated using composite REA-municipal finan- cing derived on the basis of the weighted-average of REA and municipal electric utility net energy for loads in 1974.This composite financing was computed at 6.25%interest rate for the Anchorage-Kenai market area and 5.95~interest rate for the Fairbanks market area. HYdroelectric power values in both the Fairbanks and Anchorag~ Kenai markets delivered at the respective 138-kV receiving station bus were estimated for average annual capacity factors of 45%and 51.8~.These capacity factors correspond to the peaking capability and average annual energy output for Devil Canyon without upstream storage and Devil Canyon with Watana.Peaking capability is esti- mated to be 15 per:cent higher than the installed nameplate capacity. As shown in our letter of l~rch 7,1975 regarding power values ·for the Devil Canyon-Denali project,it was asswned that the output of the proposed subject project would be delivered to the two market aress,in 1985 and thereafter,in the ratio ot:25'f;to the Fairbanks load area and 7510 to the Anchorage-Kenai load area.This approximate division ot:load requirements is based on projected future power requirements,using a mid-range growth rate,as shown in Table 12, Total Power ReqUirements by Regions,1972-2000,of the May 1974 Report of the Alaska Power Survey Technical Advisory Committee on Economic Analysis and Load Projections.This estimate was used in sizing alternative steam-electric capacity. Appendix II 16 -2- As previously mentioned in our letter of May 9,1975,we relriewed all of the factors which affected the subject study. Da''-a which you,the Alaska Power Administration,utilities,and ellectric equipment ma.nufacturers furnished were thoroughly analyzed to determine ma.terial and construction costs in the Southcentral arlee of Alaskb. Fuel costs used &re based upon the best 1nf'orltk:J.tion available pertaining to contrlict prices as 0"£the pricing level date.Among the sources of inf'ormation are:the 19'(4 Alaska Power ~urvey Heport,s of the Executive Aavisory Committee and the Technical Advisory Com- mittee on Resources and Electric Power Generation;Southcentral electric util1tyreports,datG,and personal contacts;various State agencies;and several natural gas and coal producing companies. The at-market power values eire shown below.The total value is the sum of the value of project's dependable capacity and its us,able energy. VALUE OF PCMEll ~e of Financ!ng Public-nonfedera1 11 Federal (Price level of 1/1/75) Market Area 45~Annwal Capacity Factor Dependable Usable Dependable Us~hle-­ Capacity Ener,y Capaci tY__~J1el'c-~~_ $!kw-yr.mills kWh $/kw-yr.rd.1l0\:\lh Fairbanks Anchorage-Kenai Coal-fired Alternative Combined Cycle Alternative 21.8'i'Annual Capacity Factor Fairbanks Anchorage-Kenai Coal.-fired Alternative Combined Cycle Alternative 11 Co~)osite REA and MUnicipal 96.95 86.15 46.89 7.84 5.36 6.37 87.54 74.14 41.14 88.88 75.12 42.00 5 .1~2 6.1;'3 .(.34 5.36 6.37 Appendix II 17 -3- !'airbanks Power Values The at-market power values for the Fairbanks area are based on estimated costs of power from an alternative steam-electric source described as follows:A coal-fired generating plant vith 150 MW total capacity consisting oftvo 75 MW units;heat rate,12,000 Btu/kWh; capital cost,$640 per kilowatt;service life,35 years;and coal cost of 6o¢per million Btu. For the Fairbanks area neither a combined cycle nor combustion turbine alternative plant was considered due to:1)uncertain future availability of natural gas and/or oil in sufficient quantities to use as an operating fuel,and 2)the relatively abundant source of coal in the Healy area.The power values include a 10%hydro-steam adjustment made to at-market estimated capacity costs to credit the hydroelectric plant with its greater operating reliability and fleXibility. Anchorage-Kenai Power Values The at-market power values for the Anchorage-Kenai area are based on studies of the estimated costs of power from two alternative sources as described folloving: (l)Coal-fired generating plant with 450 1~total capacity consisting of three 150 ~M units;heat rate,9800 BtU/kWh; capital cost,$595 per kilowatt;service life,35 years;and coal cost of 50¢per million Btu. (2)Combined cycle generating plant with 450 1'<M total capacity consisting of four 112.5 MW (100 MW nameplate)units (one combustion turbine and one steam turbine per unit);heat rate, 8500 Btu/k\f.b;capital cost,$235 per kilowatt;service life, 30 years;and natural gas (operating)cost of 70¢per million Btu and distillate oil (standby)cost of $1.75 per million Btu. The estimates include 5'{,and 10'"hydro-steam adjustments made to at-market estimated costs for the combined cycle and coal-fired alternatives respectively.These adjustments credit the hydroelectric plant with its greater operating reliability and flexibility. Although for the Anchorage-Kenai area the combined cycle alter- native plant is the more economically feasible of the two considered, it is desirable to provide values for both alternatives.The Alaska Power Survey indicates that natural gas could supply sufficient energy to meet total State power requirements through the year 2000 and beyond. Some utilities,gas producing companies,and state agencies question the amount of natural gas reserves but acknowledge that reserve potential exists.It is the policy of this Commission to discourage use of AppendiX II 18 -4- natural gas ~s an operating fuel for power generation in the contiguous United States.Due to changes in requirements,other Federal ~nd/or State agencies may impose restrictions on the fUture usage of n~tural gas or oil for electric power generating purposes in Ala.l:lka.Due to the uncertcdnty of the future availability of natural gas after 19($5 for new generating capacity,the unf'oreseen possibility of its restrictive use if available,and its sensitivity to worldwide economic pressures,coal may be the most likely alternative fuel for therml-electric plants to be constructed after 1985.The extensive coal deposits near Cook Inlet are attractive future alternative sources of energy for this region anp,could lel:id to options to convert from oil and natural gas to coal as the major power source during the 1980's. In fHlmmary,it is not readily apparent whether future generating plants viD~use natural gas or coal as a primary fuel.Assuming either fuel is f~uf'ficiently available,its use would then be dictated by not only economics but future environmental constraints.Therefore,we are prmriding power values for two alternate fuels -natural gas and coal. DepEmdable Capacity Dependable capacity of the project has been estimated ~sing sUb~lect project critical period energy output as supplied in the atulchments to your letter of 17 Apr:Ll 1975 and assuming power first bec()mes available in 1985.On a calendar year basis,December was detE~rmined to be the criticEll month -the month when maXimum other capacity is required.Our load-resource studies show that the Devil Ca~ron project without upstream storiage can be absorbed by the combined Anchorage-Kenai and Ftdrbanks loads in 199::>.Devil ~nyon vi th Watana, avajLlable in 1990,wouJ.d be usable in meeting combined ares loads in 1993.Our estimate of the dependable capacity or the Devil Canyon- Watsna project is shown on the attached table. Very truly yours, ~._~~J~ K.Frank Thomas Regional Engineer At~:!chment cc:North Pacific Div. Corps or Engineers Appendix II 19 ------.-~--~---r__--'.---,-------- DEVIL CAHYON-WA~ANA PROJECT,ALASKA Capacity Dependable on Combined Anchorage-Kenai and Fairbanks Axea Loads Mfl ~985 86 87 88 89 1990 91 92 93 to end of service life 117 21.3 328 449 575 765 932 lilO 1233 11 11 Equals 1l5~(600 +472)Mol Appendix II 20 ,( FEDERAL POWER COMMISSION REGIONAL O,FFICE 555 BATTERY STREET,ROOM 415 SAN FRANCISCO.CALIF.94 t l' August 20,1975 Lt.Colonel Joseph W.Hurst Acting District Engineer ~skaD1strict,Corps of Engineers P.O.Box 7002 Anchorage,AK 99510 Su"!Jject:Power Values for De vi.1 ~nyon-Watana Project (Your NPAEN-DB-HY) Dear Colon~l Hurst: In response to the request in sour letter of August 11,1915, pover IItllues for the Devil Canyon-Hatana Project based on Federal Interest Rate or 6-1/8%are furnished below.The pri~e level of January 1,1975 and all other considerations described in our J.etter of August 12,1975 remaj~n unchanged. At-Market Value of Hydroelectric Power Federal Financh Market Area 45!Annual Capacity F;;actor Fairbanks bIlchortlge-Kenai Coal-fired Alternative Combined.Cycle nlternaGive 51.8~Annual Capacit;r Factor Fairbanks Anchorage-Ktnai Coal-fired Alternative Combined CYcle Alternative Price .Level of Dependable Capacity ~/lf.W-yr. 90.84 16.11 42.79 Appendix II 21 Yours very truly, "':hv~:r~~~ M.Frank Thomas Regional Engineer FEDERAL POWER COMMISSION REGIONAL.OFFICE 555 BATTERY STREET,ROOM 415 SAN FRANCISCO,CALIF.94111 December 4,1975 Colonel Charles A.Debelius District Engineer Alaska District,Corps ofE;ngincers P.O.Box 7002 Anchorage,Alaska 99510 Dear Colonel Debelius: We have reviewed your Draft ~nvironmental Impact statement on the HYdroelectric Development Upper Susitna River Basin,Southcentral Railbelt Area,Alaska,dated September 1975. These comments of the San Francisco.Regional Office of the Federal Power Commission's Bureau of Power are made in accordance with the National Environmental Policy Act of 1969,and the August 1,1973,Guidelines of the Council on Environmental Quality. Our comments are primarily directed toward the need for power that would be produced by the Upper Susitna Development,the alternative power sources,and the fuel situations relative to non-hydroelectric power alternatives. The recommended plan is to construct dams and power plants at the Watana and Devil Canyon sites and electric transmission facilities to the Railbelt load centers.The proposed plan for the Watana site would include the construction of an BIO-foot high earthfill dam and power plant which would contain three Francis turbines with a nameplate capacity of 250 Mif each.'Ihe firm annual generation would be 3.1 billion kWh.Development of the Devil Canyon site would include a 635-foot high thin-arch dam and power plant with four Francis turbines,each rated at 180 MW.The firm annual generation would be 3.0 billion kWh with regulated streamflow from Watana storage.The electrical power generated would be transmitted to the Fairbanks -Tanana Valley and the Anchorage -Kenai peninsula areas.The recommended development is shown to be economically feasible. Appendix II 22 - 2 - ,....-'(l)'Ihe Need for Power We agree with and endorse the subject report's assertion in Section 2.04 that substa.ntial amotmts of new generating capacity will be needed to meet future power requirements of the Southcentral Railbelt area.Recent studies of the Southcentral and Yukon region (which includes the Southcentral Rail- belt as its main component),as defined in the 1974 Alaska Power Survey Report of the Executive Advisory Committee,indicate that rapid rates of increase in power requirements will continue at least for the balance of the 1970's, reflecting economic activity associated with.North Slope oil development and expansion of commercial and public services.Estimates beyond 1980 reflect a range of assumptions as to the extent of future resources use and industrial and population growth.All indications are that accelerated growth will continue through the year 2000,with economic activity generated by North Slope oil and natural gas development being a major factor -but only one of several important factors.It is generally considered that the Southcentral-Yukon regional population will continue to grow at a faster rate than the national and state averages,that future additional energy systems and other potential mineral developments will have a major effect, and that there will be notable expansion in transportation systems.Signi- ficant economic advances for all of Alaska and especially for the Alaska Native people should be anticipated as a result of the Alaska Native Claims Settlement Act.Other influencing factors could be cited,but the general outlook is for further rapid expansion of energy-and power requirements in the Southcentral-Yukon area. A ranf;e of estimates for future power requirements of the Southcentral and Yukon regions is presented in the 1974 Report of the Alaska Power Survey Technical Advisory Committee on Economic Analysis and Load Projections.The range of estimates attempts to balance a myriad of controlling factors including costs,conservation technologies,available energy sources,types of Alaskan development,et cetera.The higher growth range anticipa.tes significant new energy and mineral developments from among those that appear more promising.The lower growth range generally assumes an unqualified slackening of tIle pace of development follo~nng completion of the Alyeska pipeline and,in our opinion,is not considered realistic.'Ihe mid-range growth ratE!appears to be a reasonable estimate which we adopt as most repre- sentative based on recent manifestations and our assessment of future condi- tions.It should be noted that there are several responsible advisory committee members who feel that recent acceleration of mineral raw material shortages .of all kinds indicates a possibility that even the high range estimates could be e~:ceeded.Table 1,which is a condensed extract of information contained in the a.forementioned advisory corrnnittee report,summarizes load estimates f~r the Southcentral and Yukon Regions.Indicated load increments by decade ~~e as follows: Appendix II 23 - 3 - Increments of Southcentral-Yukon Power Requirements 1972-1980 Peak Annual Demand Energy H'iv GWh 1980-1990 Peak Annual Demand Energy Jv1W ffifu 1990-2000 Peak Annual Demand Energy MW Gltlh 1972-2000 Peak .Annual Demand Energy MW GWh l~460 28 110 Righer Estimate M:l.d-Range 888 638 4 623 3 093 930 4 570 2 800 13 070 1 950 10 240 8 148 45 803 3 518 17 903 According to the SUbject report,a total of 6100 GWh of firm annual energy would be produced by the combined Devil ca.nyon-Watana system which would have a nameplate capacity of 11~70 Mll.Although the report does not indicate proposed commercial operation dates,based on information in our files the project would be staged and the initial Devil canyon installation (3000 GWh and 720 IvlW)could become operable in 1985 and the ultimate installa- tion in 1990.Under this timetable it is apparent that there is a need for power in the Southcentral-Yukon Region by 1985 and 1990 in the order of mag- nitude of at least as much as the proposed subject development.Therefore, operation of the proposed project would help meet the po~~r needs of the Southcentral Railbelt area by 1985 and beyond. (2)Alternative Power Sources and ~uel Situation Our recent estimate of power values for the Devil Canyon-Watana project indicates that the most economical alternative to the project's output would be power from a combined cycle generating plant using natural gas as an operat- ing fuel.We ac1mowledge the SUbject report's premise that there are many questions concerning future availability and costs of natural gas and oil for power production.It is the policy of this Commission to discourage use of natural gas as an operating fuel for power generation in the contiguous United states.Due to changes in requirements,other Federal and/or stat.e agencies may impose restrictions on the future usage of natural gas and oil for electric power production throughout Alaska.Recognizing the undertainty of the future availability of natural gas and oil after 1985 for new generat- ing capacity,the possibility of its restrictive use if available,and its sensitivity to worldwide pressures,coal may be the most likely alternative fuel for thermal-electric plants to be constructed in the mid-1980'S and beyond. Essentially,we agree with the discussion of alternative sources of power in paragraphs 6.02.1 -6.02.10 of the subject report. AppendiX II 24 - 4 - (3)other Alternatives to the Proposed Action The Corps I DElS discusses several.potential alternative hydroelectric developments within the Southcentral Railbelt Area.All of these alternativE either have a greater adverse environmental impact than the proposed plan, or are not considered feasible at the present time. Very truly yours, j:(~,?/t/~f!f/JZYd-eI::(;/(Deputy) M.~'RANK THOMAS (Acting)Regional Engineer Attachment (1'able 1) Appendix II 25 .,,,,,,,,,lb' <,. TAGLE 1 Total PO\.;cr RcClu;rcmcnts Southcentra1 and Yukon RGg;ons l! )::> "'0 "'0 I'D ::::::; No.. O'l ~. X Actua 1 Requi rements,Estimated,Future Requ;rements____ 1-1 1-1 Region '.19.12 Pea~"AnnuaT D2m~nd'Energy r,jl,'!"G'~/h'-- 1980 Peak Annual Demand Energy ~·~'l G\-!h 1990 Peak Annual Demand Energy, !\i\~GI'lh 2000 Peak Annual Demand Energy ~I\~G\'fh Higher Rate of Growth __ 31 7 1 4·65 990 5 020 330 1..610 1 390 7 000 7 190 40 810 47 8108·580 5 020 30 760 760 _ 3 980 5 780 34 7406630..1 320 542 2 007432 115Yukon(Interior) Tota 1 SCl1thcentra1 Likelx Mid-Range Growth Rate Southcentra1 790 3 790 ·1 530 7 400 3 040 1:;3r)nv.......J .4." Yukon (I nteri or)280 1 310 470 2 270 910 t.''1'''''.0 ',J Tota 1 1 070 5 100 2 000 9 670 3 950 1"0'''';;'"I J 11 As defined in the 1974 Alaska PO\I/er Survey TO:. FROM: SUBJ: DRAFT--- Mr.Vernon K.Hagen Office of Chief of Engineers Corps o~Engineers Forrestal Bldg.,Rm.5-F-039 Washington,D.C.20314 John T.Riedel Chief,Hydrometeorological Branch Tentat:i.ve Estimates of Probable Maximum Precipitation (PMP)and Snowmelt Criter:i.a for Four Susitna River Drainages Introd\JLction The Office of Chief of Engineers,Corps 0'£Engineers requested PMP and snowmelt criteria for the subject drainages in a memorandum to the Hydrometeorological Branch,dated December 12,1974.The Alaska District requested the study be completed by February 1,1975i however,a more realistic date for completing a study in which ~e have'confidence is June 1,1975.Because of the Deed to soon begin hydrologic studies based on meteorological criteria,the Branch has concentrated on the probl~n and has determined the general level of criteria.A range of PMP values are given in this memorandum within ·,..hich we believe values from a more comprehensive study will fall.The sequences of snowmelt winds, temper.!tures,and dew points should be checked ~ith additional studies. In addItion,if we knew in detail hoW'sno.....~elt will be computed,we could give em.phasis to the more important elements. PMP estimates for four drainages A range of estimates of P}W for 6,24,and 72 hours for four drainages outlined on the map accompanying the December 12,1974 memorandum a-re listed in table 1.These are nuobered from 1 to 4 (smallest to largest). Appendix II 27 r-~------------- -2- The estimates are for the months of August a=C September -the season of greatest rainfall potential.For the sn~~lt season.multiply the estimates by 70 percent. The estimates take into account numerous cocsi~erations including several methods of modifying PMP estimates made preYi~~ly for other Alaska drainages.and PMP estimates from the Weste=.n :~ited States for areas with similar terrain. Appendix II 28 -)- Temperatures and Dew Po~~ts for Snowmelt. A.During PMP Storm 1.Dew point for PMP centered on June 1.5 ...56°F (assume maximum I-day PMP i,n middle of 3-day storm). 2.Flor PMP placement prior to June 15 s-~tract 0.8°1"for each 3-day period prior to June 15 (e.g.the ~dew point for June 12 will be 55.2°p).This ~0.8°F per 3-days may be applied to obtain the maximum I-day dew point during the PMP back to as early as May 15. 3.For first day of PMP storm,subtract 1°F from criteria of ~for 3rd day of PMP storm subtract 2°F. 4.Add 2°F to each of the three daily cev points to get daily temperatures for the 3-day PMP period. B.TempE!ratures and Dew Points Prior to 3 4 .:;)ay PMP Storm (High dew point case) Day I)rior to PMP---- 2ci 4:th Adjustment to teroperature and dew point on day of max.bcJa p~ ~ Temperature (°F) -2 -1 o +1 Dew point (el) -2 -4 -4 -5 Appendix II 29 -4- c.Temperatures.Dew Points Prior to 3-day PMP (High temperatu=e case) Adjustment of temperature and dew point on day of maximu:a PMP Day prior to PMP 1st 2d. 3rd 4th Temperature (oF) +1 +2 +4 +7 -12 - 9 - 7 - 6 Elevation Adjustment c-:"e. For the 3 days of PMP and for the high dew point~\apply a -3°F per 1000 ft to the temperatures and dew points.The basic criteria are considered applicable to 1000 mb or zero elevation. For the high temperature criteria apply a -4 D F per 1000 ft increase 1n elevation. Half-day Values If half-day values are desired for te~eratures and dew points.the following rules should be followed: 1.For the hi~h-temperature sequence,apply an 18°F spread for temperatures and a 6°F spread for dew point.Por example,for a mean daily dew point of 50°F.the half-day values woulc be 41°F and 53°F. 2.For the high dew point case.apply a 12 D :spread for temperature and a 4°F spread for dew point. Appendix II 30 -~ 3.In no case,however,should a 12-=:d~.point be used that exceeds the I-day value for that date.For examp'~,the value not to be exceeded for June 15 is 56°F,for June 3 (four 3~?eriods before June 15)is Appendix II 31 -6- Uind Criteria for Snowmelt Since two sets of criteria (one emphasizing high temperature and the other high dew point sequences)are given for snowmelt prior to PMP. two sets of wind criteria are also necessary since the pre-PliP synoptic situation favoring high temperatures differs from the criteria favoring high dew points.The recommended winds.tables 2 and 3.are given by elevation bands.In the high dew-point case,table 2.(where synoptic exist conditionsAfavoring maritime influences prior !£PMP),the same wind for 4-days prior to PMP is appropriate. All of the winds presented in tables 2 and 3 have been adjusted for applicability over a snow surface.Although a seasonal variation in the high dew point wind criteria is realistic for the present tentative criteria.they are considered applicable to May and June. Snowmelt Winds During the PMP Wind criteria for the 3-day PMP are the same for both the high temperature and high dew point sequences.They are shown in table 4. Appendix II 32 "'''''.....-------......-_............-------------_....-.........._...-------_.....;,..,,;;..;.;,;..;.;,---- -7- Snow Pack Available for Melt Some work was done in determining the m,ean and maximum October-April precipitation of record for the available precipitation stations. These stations and other data are tabulated in table 5.The drainages and available stations are shown in figure 1. Table 5 also shows the years of record available for October-April prec:f.pitation,as well as a column labeled "synthetic October-April precipitation.rr This gives the sum of the greatest October,greatest Novenmer,etc.,to the greatest April preci?1tation total from the available record.These synthetic October-~rU precipitation values and the means are plotted on figure 1. Apprc)ximately 9 years of snow course data ce available for 14 locations in and surrounding the Susitna drainage.From these records,the greatest watel~equivalents were plotted on a map.'!"::ese varied from a low of 6 inc::hes at Oshet~a Lake (elevation 29.50 ft)to an extreme of 94.5 inches at Gulkana Glacier,station C (elevation 6360 ft).A smooth plot of all maxilna against elevati.on gave a method of deter.rlning depths at other elevations.Figure 2 shows resulting smooth water equivalents based on smoothed elevation contours and this relation. Some additional guidance could be obtained ==oa mean annual precipitation maps.One such map available to us is in ~\OAA Technical Memorandum NWS AR-IO,"Mean Monthly and Annual Precip1tath--n,Alaska.rr The mean annual of this report covering the Susitna drainage is shown in figure 3. Appendix II 33 -----"'--_._------,------- -8- Also on this figure is shown the mean runo=f for three portions of the Susitna River drainage based on the years of re~ord shown.No adjustment has been made for evapotranspirarion or any other losses.This indicates that the actual mean annual prec~?itat~~n is probably greater than that given by NWS AR-IO. Conclusion.Time hasn't allowed checks,e7a1uation,and comparison of ~ the several types of data summarized here.It appears the "synthetic October-April precipitation"generally is ?-~ss tr--an the maximum depths over the drainages based on snow course neasur~cs.There depths,or figure 2,would be considered the least that couli be available for melt \ in the spring. Further Studies The variation of precipitation with terrai~feat~~es in Alaska is important but yet mostly unknown and unstudied.Mor~effor:should be placed on attempts to develop mean annual or mean seasonal ?recipitation maps,at least for the region of the Susitna River.S~e 10 years of data at about a dozen or so snow courses could be used ~this attempt,as well as stream runoff values. Some work has been done toward estimating ~~depth-area-duration values in the August 1967 storm;an important in~t to the present estimates.Attempts should be made to car=y out a complete Part I and Part II for this storm,although data are S?arse ~d emphasizing the use of streamflow as a data source. Appendix II 34 -9- The objective of these two studies with regard to the Susitna drainages is to attempt a better evaluation of to~aphic effects,and to make a better evaluation of snow pack avai~la for melt. Stud)'of additional storms could give ~~e important conclusions and guid~~ce on how moisture is brough~u?~e Cook Inlet to the Talkeetna Mountains and how these mountains effect the moisture. Sno~!elt criteria in this quick study is licited to 7 days.Considerably more work needs to be done to extend tl1is to a longer period.Then we would need to emphasize compatability 0=a large snow cover and high templ!ratures.More known periods of b.:l.~snowmelt runoff need to be stud:led to determine the synoptic val~es of the meteoroloKical parameters. Appendix II 35 --------~-""-------~-----~--"_.-T -10- Table 1 General level of PMP est~tes for 4 Susitna River drainages Drainage Number 1 2 3 4 Area (S9 mi) 1260 4140 5180 5810 12-hr PMP (in.) 9-12 7.5-10.5 7';'9 7-9 For 24-hr PMP,multiply 72-hr value by 0.60. For 6-hrPMP,multiply 72-hr value by 0.30. PMP for intermediate durations may be obt~ed from a plotted smooth curve through the origin and the 3 values ~cified. Table 2 Snowmelt \-.rinds precedingl'MP for Susi::la Basins for high dew point sequenee Elevation (ft) sfc 1000 2000 3000 4000 5000 6000 7000 8000 9000 10,000 Dai1y ~~d speed. (::roh) 8 9 U 18 25 34 36 31 39 40 42 *For each of the 4 days preceding the 3-eay ~. Appendix II 36 @$£ -11- /~;, Table 3 Snowmelt winds preceding ~)for Susitna Basins for high temperature sequence Daily Yind speed (mph) Elevation (ft)~prior to 3-day PMP 1st 2nd 3rd ~ sfc 10 13 4 4 1000 10 13 4 4 2000 11 14 5 5 3000 12 16 5 5 4000 13 16 6 6 5000 13 17 6 6 6000 14 18 6 6 7000 15 20 6 6 8000 16 20 7 7 9000 16 20 7 7 10,000 17 21 7 1 Table 4 Winds during 3-day PMP 'Wind speed (mph) Day of Day of 2nd Day of 3rd E1ev2Lt ion (ft)maximum p~highest PMP highest PMP sfc 12 9 8 1000 14 10 9 2000 19 14 12 3000 29 21 18 4000 ·42 31 27 5000 56 42 36 6000 58 44 38 7000 62 46 40 8000 64 48 41 9000 68 51 44 f"""""10,000 70 52 45 Appendix II 37 Table 5 Stations with Precipitation Records in and surrounding the :t:> Susitna Drainage u l:l Mean Number(0 ~Yrs of record for Maximum of months for Synthetic ..Meanwe..co -'.complete Oct.-Apr.obs.Oct-Yr of synthetic Oct.-Oct.-Apr.Oct.-Apr.x ......Station Elevation precipitation Apr.prec •Maximum hR,r.season precipe Precipe......(ft.)(in.)(in.)(in.) Susitna Meadows 750 4 17.18 70-71 4 23.18 13.77 Gu1kana 1572 18 6.77 56-57 18 12.68 4.19 Paxson 2697 2 8.42 43-44 6 14.25 7.64 Trims Camp 2408 3 23.26 59-60 5 35.82 15.3 Summit 2401 19 14.09 51 ...52 20 26.59 7.93 Tolkoctnn 3/15 35 21.17 29-30 37 40.59 12.26 Sheep Mountain 2316 13 11.91 59-60 12 18.42 4.78 .... N. ) / )) Figure l.--Drainage outlines and October-April precipitation in inches. (Upper values -synthetic October-April precipi~ation; Lower •mean October-April precipitation.)------------- 1"I,j?. fRZ$~'1 7°.' rr·-.1~Afl,e 11.,7)0,1 -,I, (JII!.-t If,,",lit 4-•.z...,.;..~",.ff-.l, ]).8 -(it",.s C. /.1",J (4:-(, '-r'c," "1...1 r) I ,/ (I ~( "--" I \- .("'->',.__..(.i / \....t i ,.! --;/ t {t.'*.} /..,.",'Pi cr I~(?+,., ............. 1)~".\,1-\ (J /,.1,'JV',I) f" )::0 U U CD ~ (.oJ 0- 1.0 ...... X I- -."Ol~I...}f\~ 1'tII\fll ,,;..' Appendix II 40 ~ ~ ........ J ,.,)'-t ~ 0 i+ r1 "t \j" \~ ~ () .......... " t:t ~ . i('- .. CIl .. ~ CLI.c: ~u;; '" t.':~ ':) ... ~ ). - r' lI-l lI-l 0 § 501 ~ CLI 501 I.J CO "'Cl J::: I III \ J::: 0 '"! ... III... '"~ '"U CLI,... ~ .-I III :J J::: fa \ ~ oS \ ..... • II I . M CLI 501 ='~ ~ 4Ol. '"'»00\~,,) -'".... '" '-...J.:. ~~,+ Appendix II 41 ~.........--------~--"',--'--- TEN NOST SEVERE STOR."1S IN UPPER SUSITNA BASIN SINCE 1961 Year 1962 1963 1964 1965 1967 1971 Date of Storm June 13-15 July 16-18 *June 10 i<June 20-27 *June 26-28 *July 12-15 July 18-22 Aug 9-16 June 29-30 July 12-17 Aug 1-10 Date of Flows Over 35,000 cfs at Gage June 11 to June 24 July 7 to 18 June 1 to 22 June 1 to 22 . June 28 to June 29 July 13 to July 14 July 20 to 22 Aug 13 to 19 June 23 to July 1 July 15 to 16 Aug 8 to 15 NOTES:(1)Heather Stations The Gr:lcious House Summit fAA HcKinely P.ark Trims Camp (3)*=Used SurnriJit FAA only Appendix II 42 (2)U.S.G.S.Gage Susitna River at Gold Creek (, I I i;\\ I I !(~ 'I I /J'\\I I I \I i 1 ,\1 I ,,.~,,;\\i \,JAY S.HAMMOND,GDYERNDR:I I I \I i I I .),Ii\!I }\,\,\I j I !J \ Olr.'ICE 01-'TilE t.OVEUNOll / I ALASKA CNCRGY OFfiCC / 6 October,1975 Colonel Charles A.Debelius u.s.Army Corps of Engineers Gentlemen: 338 OCNAli STREET -ANCHORAGE 99501 PHONE:907272·0527 The Alaska State Energy Office,within the Office of the Governor, appreciates the importance of the possible development of the Upper Susitna River hydro-electric potential.We also appreciate the opportunity to express a point or two concerning this matter. Before final approval of the two dams now being considered,the Devil's Canyon and the Watana,is made we feel quite strongly that a net-energy-benefit analysis should be prepared and circulated for study and corrUllent.How much energy will be consumed in the con- struction,operation,and maintenance of these dams,including the entire system and other costs such as rerouting highways?How does that compare with the energy it will produce?Is that ratio worth attaining?These questions need to be addressed and answered. Sincerely w~(.tn~e~ William C.McConkey -:- Director WMc/mgf Append;x II 43 323 E.4TH A\'fNUE AHOfORAGE 99501 DEI-AIITMENT OF NATUIIAL JIESOtJlICES DIVISION OF PARKS April 4,1975 RE:2425 Colonel Charles A.Debelius Corps of Engineers,Alaska District Department of the Army P.O.Box 7002 Anchorage,N(99510 Dear Colonel Debelius: / JAY S.HAMMOND,Covernor Reference is made to your letter of March 18,1975 and our response dated March 19,1975 concerning the cooperative aspects of the planning and development of a recreation program for the proposed Devil's Canyon Hydroelectric Project and related impoundments.This letter will serve as a declaration of intent on our part to provide the necessary local participation at said project,as required under the Federal Hater Project Recreation Act,Public Law 89-72,to the extent set forth hereafter:The State of Alaska would: 1.Administer project land and water areas for recreational purposes. 2.~vith legislative approval,contribute in kind,pay,or repay with interest,1/2 of the separable cost for recreation facilities and specific recreation lands,in accordance with the Federal Hater Project Recreation Act of 1965. 3.Operate and maintain said recreation facilities. At this very preliminary stage of planning,we recognize that the proposed projects have the potential for fulfilling a portion of the significant deficits of recreation facilities within the Southcentral and Interior regions of Alaska.Furthermore,we recognize the very general and tentative nature of the recreation program identified here with respect to congressional authorization for further study and funding,and the capability of future state budgets to support such endeavors. It is our understanding t~t more definitive yecreation a~ea and site planning would follow project authorization by congress,and based on this,formal contract agreement could become possible between our Appendix II 44 1 Colonel Charles A.Debelius April 4,1975 Page 2 respective agencies.Furthermore,it is our understanding that this letter of intent does not bind the State of Alaska to any future formal contract agreement with the Corps of Engineers. Due to the very limited staff of the Division of Parks,we can provide only limited comment and input during this pre-authorization stage of planning.However,if authorized,the project will be of great interest to the state and at that time we would wish to discuss a formal recreation contract agreement. Sincerely, f~\I~ Direc:tor cc:Guy R.Hartin,Commissioner Department of Natural Resources NCJ:krm Appendix II 45 DEI•.;\.IlT~IEN'T 01:X.;\.TIJIl.;\.I~IU':SOIJIU~I~S OWlS/ON Of PARKS June 4,1975 Re:2425 Colonel Charles A.Debelius Corps of Engineers,Alaska District Department of the Army P.O.Box 7002 Anchorage,Alaska 99510 Dear Colonel Debelius: JAr S.HAMMOND,GOVERNOR 121 E.4TH AVENIlE -ANCHORAGE 99501 ../ The Division of Parks has reviewed the April 1975 draft copy of the "Recreation Resource Appendix for Devil's Canyon Interim Feasbility Study",by Don Geil,and we offer the following comments.Generally, the report appears adequate;however,it should be pointed out that Section 5.01 (Basic Assumptions)is not an accurate statement of the intent of the Division of Parks. Although the Division of Parks is interested in operating the recreational aspects of the Devil's Canyon Project,we do not consider the area as "an extension of Denali State Park".We see Devil's Canyon more as an independently operated State Recreation Area.Undoubtedly there will be a close relationship between Denali State Park and Devil's Canyon,but the purposes of a state park are different from those of a Recreation Area.It is our feeling that since Devil's Canyon will be subject to significant man-made disturbance that the classification of Recreation Area is the only definition which can be applied to this project. The projected visitor use and recommended development plan for the pro- ject,although in a very conceptual stage,appear reasonable. We appreciate the opportunity to review this draft document and look forward to continuing communication with the Corps of Engineers on this project. Sincerely, I I ,.l C L1'·-r '. RUSSELL W.CAHILL Dire<;,tor \{~'\.\<'\...>('-;.\\}j\\C -1'\•. , \,~r>."VI \i •(~"/'"""C r -~l...,,\,:\/,v \.,'\.-..e.A/__._..._.... By:Neil:,C.Johannsen Park Planner I NCJ:cb AppendiX II 46 ~VmV[@w ml~~~m /MrUA'M~U_ OFFICE OF TilE GO'9EUXOn I SrArr I'OliCY DEVElDPMCNT AN'O PLANNINC /POUCH AD -JllftlCAU 99811 June 9,1975 fW#tIf •.,,6rP H.W.HolHday Chief,En~lineering Divi sion Department of the Army Alaska District Corps of Engineers P.O.Box 7002 Anchorage,Alaska 99510 Subject:Southcentral Rai Ibelt Hydroelectric Power Study State I.D.No.75041804 Dear Mr.Holliday: The Alaska State Clearinghouse has completed review on the subject project. The following agencies were invited to review and comment: State of Alaska Department of Community &Regional Affairs Department of Economic Development Department of Envi ronmental Conservation Department of Fi sh &Game Department of Highways Department of Law Department of Natural Resources Division of Lands Division of Parks Department of Public Works Alaska Energy Office Office of Comprehensive Health Planning Seven of the above agencies responded. The Department of Community &Regional Affair's stated: In short,the brochure is designed to be a pUblic opinion questionnaire andan"imnouncement that a study is in progress.The information presented is mSlJffieient to warranCcomments on the quality'of the study or on the effects the proposed Upper Susitna River hydroprojiect will have on this Department's operations.We do have some study content recommendations. The!Corps has conducted an II inventory and evaluation of the cnvi ronmental, esthetic and recreational resources of the Susitna Riverll •Howlwer,this lnfolrmation is only avai lable for review at the Anchorage office.A task team AppendiX II 47 ------r-~~---------------- Mr.Holliday -2-June 9,1975 has also been organized to "evaluate environmental,economic,engineering and social aspects of hydropower development of the Upper SusitnaRiver as well as possible alternatives".This team is responsive to questions,but there is little published information for review and comment. We welcome,indeed request,an opportunity to review and comment on a draft and final copy of the study.For this Department to determine the quality of the study and the possible effects of the proposed hydropmjects on our operations, at least the following concerns must be addressed in detai I: I.Effect on Community Growth and Development: Development or nondevelopment of additional electric generation capacity is a policy issue which must be resolved at all levels of government.A decision not to expand generation capacity will tend to slow population growth and community development.Whereas the amount of power developed and construction schedule can be varied to meet existing and anticipated needs or to serve as a catalyst for increased population and industry growth. Information on the impacts of the various power development and construction schedule alternatives should be available to decision-makers.Direct impacts such as population changes and increased traffic associated with project construction as well as secondary impacts such as housing shortages, demand for municipal services and changes in the natural envi ronment due to community growth (or Jack of growth). 2.Alternatives to the Devi I Cany -.')j ects: The U.S.Senate Public Works Committee resolution specifica Ily requested the study on the Devil Canyon and associated projects.Thus,there is an inherent pro-hydroelectric bias which may overshadow other alternatives. This bias can be seen in the brochure.The only detailed information presented is related to the Devil Canyon projects.The quality of the final study will depend on how much consideration is given to alternatives.To adequately comment on the Devil Canyon projects,we need to see more information on the 'alternatives. The Department of Economic Development stated: Hydropower is one of several energy resources available to the Southcentral region.If developed,it can free fossil fuels far export or for their petro- chemical values.The total energy equivalent of capital costs and materials for dam construction should be evaluated.Net energy production should be positive and preferebly high. Sauthcenta-al Alaska has both the energy potential and the developed frame work for surface transportation to market.The threat of over production of energy seems highly unlikely,especially if hydropower and fossi I fuel energy can be interfaced to provide for both industrial and residential needs.The region compares well with many industrial nations. Appendix II 48 Mr.Holliday -3-June 9,1975 ThE!final decision should depend on careful study of the total energy equivalent of the investment in capital and materials.The proposal area appears to be favorable with conside.-ation for game crossing and phased construction.An optimum energy -envi ronmental mix should be feasible. A series of low dams may yield a bettet-balance with lower drawdown re- quirements and more niodest construction costs.The sequence could develop over time to grow with requirements and market --with the plan with the best total b~lance. Cost estimates should be supplied to give the public a better idea of the funding pro1blem and a compat-;son of this··between planning choices.(As against Btu equivalents of the power potential.) The Depalrtment of Environmental Conservation stated: We have no comments on the reiterated infol-mation in this study. The Department of Law stated: Thl:!corps should be commended for developing and using this means of incorporating public and outside opinions into its planning at an ear-Iy date. The Department of Public Works stated: We are firmly on record in favor of this project and its impact oli public wOlrks. The Alas~(a Energy Office stated: The Alaska Energy Office fully supports the Southcentral Railbelt Hydroelectric Power Study now being conducted by the Army COI-pS of Engineers.Focusing on the hydropower potential of the Upper Susitna River,this feasibility study also provides an excellent opportunity to investigate other energy resource alternatives in the area. In 1985,the estimated demand for power in the railbelt area,which contains OVE~r 75%of the state's population will be around 7,000 million kilowatt hours per'year.Existing power plants are not capable of meeting this demand; therefore,in order for these future needs to be met,it is imperative that consideration and advance planning take place now.The feasibility study by the Corps provides an excellent oppourtunity to evaluate notonly hydropower bUll other energy resource options available in the region as well. Th,e Alaska Energy Office is fi rmly committed to the premise that the policy of ~=ontinued Alaskan dependence on "non-renewable"fossil fuels must be reE!valuated.This is because the present traditional energy resources (coal,oil,and natural gas).are not unlimited and we must learn to use the~m wisely and in the most efficient wa,;_~;:;ossible if the United States is Ito ever achieve "energy independence". Appendix II 49 Mr.Holliday -4-June 9,1975 Although the statels fossil fuels remain virtually untouched,we Alaskans must also realize that the demand for use of these fuels outside will become more and more intense as these energy resow-ces in the Lower 48 become depleted. Today hydropower is the most attractive n renewable ll resource available in the state.A proven technology and economic practicability make it commercially competitive with the fossil fuels when generating large blocks of electricity. Perhaps the greatest hindrance to hydropower development is the potential negative impact upon the land,fisheries,and wildlife of the area.Un- fortunately,little detailed information on these possible consequences is available.Before construction of any hydroelectric sites on the Upper Susitna River can be endorsed by the Alaska Energy Office,a thorough environmental impact evaluation of the region must be completed. At the present time geothermal,wind,solar,and tidal power are not practical enel"gy a Iternati ves for large sea Ie power plants.Future technological advances and changing economics,however,may help these energy sources play an instrumental role in Alaska1s long range energy picture.Nuclear power may also have a significant impact in the years ahead, but at this time little is known about the statels uranium reserves. We do recommend that a detailed inventory of these alternative sources be taken for the region now.This valuable information would then be on hand when evaluation of the long range power needs of the area takes place. Of course,attention must also be given to possible use of our lInon-renew- able"fossil fuels.Continued use of natural gas from Cook Inlet,tapping off a natural gas pipeline from the North Slope,construction of additional refineries to process Alaskan oil and building production facilities at the Susitna and Nenana Coal Fields are ali possible short term options which must be considered.Further depletion of coal,oil,and gas reserves in the Lower 48,the possible deregulation of natural gas,and the volatile Middle East situation make the future use of these fuels for power generation questionable.There are many other more efficient and required uses for these resources.As always all environmental considerations must be analyzed before new projects can be condorsed by this office. In conclusion,the Southcentral Raitbelt Hydroelectric Power Study is an Important first step toward what,we hope,will become a coordinated and systematic state and federal effort aimed at meeting Alaska's future energy needs. The Office of Comprehensive Health Planning stated: This office has no comment. AppendiX II 50 Mr Holliday -5-June 9,1975 In reviewing the comments received,and from conversations with those agencies not responding to this public brochure,there is not enough information in this document to fo/-m any sort of state position on this project at this time.However,we hope these:comments will be of some assistance to you in the development of the draft envi ronmental impact statement. Sincerely. /~/"",/"'; ~~J~~J;V.';,Zs,;C~",.' State-Federal Coordinator cc:Robert Weeden,DPOP Robert LeResche,F&G Appendix II 51 OFFICE OF TilE GOVEllNOn JAr t HAMMOND,SOVIINOI -.~. STATE POLICY DEVELOPMCNT AND PlANNING /POUCH AD-JUNEAU 99811 PHONE 465-3512 September 12,1975 Colonel Charles A.Debelius District Engineer Corps of Engineers Alaska District P.O.Box 7002 Anchorage,Alaska 99510 Dear Colonel Debelius: In response to you August 28,1975 letter the State of Alaska definitely sees a need to reserve lands for public recreation and fish and wildlife purposes within the proposed Devil Canyon-Watana power project,if concerned agencies and Congress approve the project. More extensive studies should be conducted by the State and Federal agencies on land use in the upper Susitna River area before any decision is made on the boundaries of the proposed power project.We would like to be involved in any future studies on land use in this area. If we can be of further assistance,please advise. Sincerely, ~~/UI.~ aYrfi nd W.Estess Sta e-Federal Coordinator Appendix II 52 NSTITUTE OF WA TEB RESOURCES UNIVERSITY OF ALASKA COLLEGE.ALASKA 99701 29 May 1975 Southcentra1 Railbelt Task Team Corps of Engineers,Alaska District Box 7002 Anchorage,Alaska 99510 Dear Sirs: Thle comments I make here are my own a.nd don't necessarily represent the opinions of the Institute of Water Resources. The Susitna River Hydro-electric project stirs mixed reactions with me.It is easy to recommend the project on it I S merit of saving oil,but will that really happen or will it attract industrial development and leave the domestic market still reliant on oil fired generators?Before I would support this project I would have to be convinced that the power will be used by Alaskan home owners and not for stimulation of industrial development. I feel there are better solutions to our energy problem which should be tried before building hydro projects.Energy conservation measures could be used to decrease demand.This should be tried through a combina- tion of 1)public awareness campaigns,2)raising fuel prices,and 3)giving tax incentives for insulating and other energy saving measures. I""',P Development of alternate energy sources should also be given priority to dam construction on the Susitna River.Solar.wind,tidal and refuse burn- ing eire all viable energy sources which could easily be developed. Another area that I am concerned about is water quality and for the last year I have studied the effect of reservoirs ~n water quality extensively. The following is the conclusion of my masters special topics paper,a copy of which is included. "In a reservoir the processes of stratification,eutrophicatioh, evaporation,sedimentation,ice cover and leaching all cause changes in water quality to occur.Examination of the processes and their inter-relations is essential to a complete understand- ing of what changes will take place in impoundment water quality. The results may be an improvement in water quality although often times the water is degraded. In general,reservoirs are documented to cause increases in the concentrations of color,total dissolved solids,electrical con- ductivity,alkalinity,hardness,iron,manganese,chlorides,nit- rogen,phosphorus,and carbon.The concentrations of suspended matter,dissolved oxygen and bacteria usually decrease as water passes through a reservoir. PLEASE REPLY BY AIRMAIL Appendix II 53 UNIVERSITY OF ALASKA Southcentral Railbelt Task Team May 29,1975 Page 2 The literature shows that removal of organic material prior to reservoir site inundation results in improved water quality characteristics.The various methods of aerating the hypolimnion, withdrawing only selected layers of water and applying chemicals have all met with some degree of success in alleviating reser- voir problems." I recommend,if the project is built,that it include the following operational and design features. 1)The reservoir sites should be cleared of all trees and brush.Areas of deep organic material should either be covered with inorganic material or removed.~c':, 2)The dam should be designed with multiple outlets at different eleva- tions so as to allow for the controlled release of specific water layers. 3)Aeration devices should be installed for use in controlling strati- fication and low dissolved oxygen. 4)A sound water quality management plan should be developed to protect· downstream fisheries and water uses. In closing I emphasize my point that the project should be for replacement of oil and gas use and not for stimulation of industrial development with cheap power. Sincerely, Stan Justice Environmental Engineer Appendix II 54 PLEP.SE REPLY BY AIRMAiL MATANUSKA ELECTRIC ASSOCIATION,INC. P.O.Box nG" PALMER,ALASKA 99645 TELEPHONE (907)745·3231 June 10,1975 District Engineer Alaska District,Corps of Engineers Box 7002 Anchorage,Alaska 99510 The Board of Directors and t,janagement of r~atanuska Electric Association,Inc. wish to go on record as being in full support of the full development of the Upper Susitna River hydroelectric potential to be brought on line on a schedule that will be paced to the needs of the rai1be1t area. l'lEA's service area extends from Eagle River northerly to include the Knik River, Matanuska River,and much of the Susitna River valleys.It is our firm belief that the development of Susitna hydro is the most realistic solution to the areas' growing nE~eds.I~EA's projections indicate that its system requirements could easily exceed 100 megawatts by the time the first Devil Canyon units could come on the line. We are much in favor of the development of this renewable resource which,in a moderate ~"ay,can help to conserve fossil fuels for other than boiler fuel to generate needed electricity. The South Central Railbe1t Area continues to grow at a rapid rate with its demand for electric energy steadily rising.The need cannot be met by such interesting sources of energy such as wind,solar,tidal,or geothermal on any kind of real istic schedule.Gas and oil should be conserved.Coal could be used as it is in abundance in this area;however,we see some serious environ- mental objections to large scale mining and coal burning electric generation plants. We see no reason to consider development of nuclear energy when we have the Susitna potential at our doorstep with its minimal environmental impact.Of the several alternate plans it would be our opinion that the final decision should rest on the combination that \",i11 most efficiently harness the full potential of the river system for the production of hydroelectric energy. We predict that the construction of the project and the availability of an abundance of electric energy will impact the rail belt area and hasten its AppendiX II 55 ~i.4SKA'S FIRST REG-INCORPORATED 1941-ENERGIZED 1942 ~.".. './ J . District Engineer Alaska District,Corps of Engineers Page 2 June 10,1975 ~'. occupation and development in many ways,such as farming,mining,commercial, industrial,and residential activities. It's our fear that without the earliest possible availability of Susitna hydro energy in the railbelt area we will see utilities,of necessity,turning to less efficient,less desirable environmentally,and more costly alternates that will not be to the maximum benefit of the region and its people. ~~/~.f~ I Willard H.hnson,P.E. General Manager cn Appendix II 56 ~~~l ,,'t"st '5th "\'~n~ l\l\chor:\~'C.!\lM\&~)9S01 Junp B,1915 Col.Charles A Debelius, Alaska District Engineer U.S.Army,Corps of Engineers P.O.Box 7002 Anchorage,Alaska 99510 Sir:. Your presentation,yesterday,of the nevils Canyon hydro-electric.complex, to the Anchorage Chapter of the Alaska Society of Professional Engineers, was most interesting. I have one complaint.You stated that the Benefit/Cost ratio ,,,as slightly better than lU1ity,and that it had been developed with alternative thenn.al systems fired by fossil fuels.Further,as I asked you,the basis for com- paring the cost of electricity generated from using natural gas did not in- clude the obvious escalation in the cost of this fuel.In addition,I liould venture to say that natural gas ,~ill become so costly as a fuel by the end of the century its use for such purposes will becOJ'!1e prohibitively cost- ly.In fact,at our present rate of consumption,I ,.,rou1d expect the mown gas fields in Alaska to be depleted ",i thin t\'10 or three decades. Thus,comparison of costs based upon present prices of a fuel which will incre:ase in price concor.tl!1i.tantly with a rising demand for electricity ,and, in all likelihood lvill not even be available at the halfway point in the ltfift:y year"life of the project,is patently absurd. AI thoug.lt AI aska has vas t depos its of coal,the cos ts for this fue I also must be·expected to rise during the rest of the century.I had not asked if cost escalation had been taken into acc01IDt.I assume that,as for gas, it hadn't been.Since the supply of coal is so large,there is no reason to question its <;lvailability well heyond the end of the century,and,according- ly,the cost should not increase as sharply as for gas.TIle plethora notwith- standing,the crucial necessity for environmental conservation will have to pay for restoration of mined lands,removal of sulfur and other atmospheric cont::mrl.nants,disposal of ashes,and dispersal of waste heat -all subject to inflationary pressures -if the B/C ratio.is to be logical. l'later is a renewable resource;fossil fuels are not. Very truly yours, ~~G:& Appendix II 57 ,----------"-------------_.~----,..-- 410 Skarland Hall University of Alaska Fairbanks,Alaslm 997:)1 Oct 7,1975 Alas1ca :listric t :orns of ~n'inecr3 P.O'~::'oz 7082 Anchora:::-e,Alas~~a 9951(', D'3ar Sir: I attpnded your l::3.:'ir~~:s r..cLl tv::::,,:,in Fsirb:m'-:::s in October,~;iith :~reat intcr'?st CI.::'.c1 concorn for the :uturo clC:V(;101~,:'(;nt of tho::proposed. sa::Js on t1F'~~i -,3usitna '-(i'ier. I '-r8S .3 O!i;o'::JEl t :=;'1 r'7:'i8 c d ':-'hen Co lone1 '::0 bC"1ius '~;cntionc d that the re mi:ht still hp a ~os3ibility o~additional da~construction such a.s the ~~av~:n.3.rt.';?:en tnc Corls tries to resurrect such sl:018tons of this ma~nituj~~f ~iolo:ic~l bblnder,it ~~~cs ene ~onder about sO'V of ~;~l:r-:-83:::12.':..'Ce;hincl !,resC'nt stuc'.ic's. ,~l thol.t.:::;h I ':'CI')~_':-::tl:'::first tc aC.":~it that the ~-vil'S Can~'on arGa "''-''ttl r :1:':1"to''"'.....~~..,-:--:',tl,,·hc--'-1""catl'o'1 .r'op '"-~2"e -i+-e l'n "'h~.-,J"ate I'I '"...-,.')'':.....::Y'f1-...:...-'.:.........-J~~'.~-',',:=J '-'V t 1._-.:...,.J,".l_l.Q v -::Lt _~='J l,.., fee-I that It is :.·::c-sssary to evalua:'?all of Alao'::a's rcoourc8s, anr''::i3C lan'~'112 --::;lannin:,'::i tl1 the best 8:1d '::iscs-;;us~of rosources in8t~a~of ct0~~~~~in=in a ~i2C~deal style. I f 0 s1 that t~c ~~~s:ion should be rais(d as to the ~£cossity of a (,a'~'~.f'",.....,,.....h r .....;,.....--__....,,"",....-:-'Y'l;..............O~·~::-,-Ja ~L 1-1 l·~'~l~,-,1--r-~~'11 t::';.........-:.:1.-_n ('-p./l';:;.S {:~n"'v'1 '.j.........v,....:1..'._.~-"_~'-'_~"".~.,""'7 v 1.,._•."-...._.l..It ---_--.--~v ''"!an~y I:;rlf:"r;"'~l :r(..:'~·;.:'C>~S be'ill,=:':,'as~c:;.in :\.laG~:a.?lal'i:1:~of :iatu~C1.1 "'as haG oC·C':<1..~?:'~ic:J_cu.t :cr 1Jvcr a ;'-lo::a.~~..~in,cco~-_Il'll·::;t.1\8.9- st~J(~,8r1.\,~Gll <:a.-.~-'·J_::~-:tr~c ,Un.iv·c!'si-i::l of ~'llaG1~.a c..t GcJ_l~;~~c;J I ','Iit:asss rntire floo~s ~l~:~~crssarily burni~~:clcc~ri~i~~y 2L hours a day,alld cC'nml::~)tic:l is at 3.:::a:-i~~lUr1. ~hr fact that ~b~CO~?S o~=n~inc~rs is ~lan~lin~'·this ]rcjrct at ::118 ti'"1C I :}!'iQr te:.~:n()·:ilc;.1~8 c-f ~hr:'rOlltc tIle -'6.3 ~i2Jclin(~::r5_11 :3.;~",-i_'1.[~"_'~Qtr-:2 <:Ul atLi_tudr;of ":::r:vslop!:'l2Ylt for ::l-~,vclo]::'':ntfS 88':0" t(;!)Cr11aI~0 q'J.C ~.~C a -;;cll ~:nc-\'j:l .~las~.~:3,rL inv"2rs·~'1::'. If infact the ~iorth Slope ~o.s T'i:;eline does ::0 throu~'h 1\.las):a,it ~Quld a]prar to ~c to bo cztrc~cly short siChtod o.t thia ti~p to Co ahc'ad ';r=-th r:O?1struction ~lans,as ':;011 as cYlcoura",in~'".orc ';:astc of Alasl~a's rCDo'::ab1c and non rcnc\':ablc resources. Yours sincerely,,~~.,/d:J..tf Barbara '.!int:ley cc:Governor Ha':l:::ond Appendix II 58 Col.Charles A Debelius DepartmEmt of the Army Alaska District Corps of Engineers P.O.Box 7002 Anchorage,Alaska 99510 Dear Colonel Debelius: BOX 2037 ANCHORAGE,ALASKA October 7,1975 The Mountaineering Club of Alaska is a recreational organization located in Anchorage,Alaska and has approximately two hundred fifty mamberships representing a slightly larger number of individuals. Two primary interests of the club are mountaineering and wilderness backpacking and exploration. We oppose the proposed construction of the Upper Susitna Hydroelectric Project because of its intrusion into an area 6f wilderness close to Anchorage.We are concerned not only with the inundation of a scenic: white-water river but also with the establishment of a permanent access road and other recreational projects which would enC'.ourag~motorized . . h \recreatlon 1n t e area. The Mountaineering Club supports creation of the Talkeetna Mountain State Park to the south of the area in question and is concerned that the dams project and related recreational development in the adjoining region would detract from the wilderness aspect of the northern portions of the Talkeetna Mountain State Park. We are particularly concerned with the potential for heavy off road vehicle (ORV)use in the immediate area of the access road and perhaps spilling into even further reaches of this wilderness.In this regard we are reminded of the ORV problem along the Denali Highway during hunting season.I' Thank you for this opportunity to express our concerns. Yours truly, ~/[~~fi4 Fritz R1eger G7 . President .--.._.--------- Append;x II 59 FAIRBANK~l'AJI OROUGH Bo 6Jr iib s,A ~9707 October 13,1975 Col.Charles A.Debelius Col.Corps of Engineers District Engineer Box 7002 Anchorage,Alaska 99510 Dear Col.Debe1ius: As stated at the public hearing held on October 8th,the Fairbanks North Star Borough is supporting development of the hydro-electric potential of the Upper Susitna River as a means of meeting future needs for energy in Interior Alaska. Only through utilization of a natural renewable resource can we best use our non-renewable resource. Interior Alaska is well along is its development as a service area for petroleum and gas fields to the north.The need for electric power is critical now and will become more critical as industrial and tommercia1 development takes place. Long range planning is necessary,but time is slipping by and the energy needs will soon be upon us.It is important that funds be made available for the pre-construction planning for hydro-electric power.We will add whatever support we can; Very truly yours, I2LJtI!~~~~.CARLSON Borough Mayor JAC:1sa cc:U.S.Senator Ted Stevens U.S.Senator Mike Gravel U.S.Representative Don Young Appendix II 60 economical power be provided for Interior Alaska: By:John A.Carlson Introduced:10/9/75 Adopted:10/9/75 RESOLUTION NO.75-40 A RESOLUTION URGING THAT THE CORPS OF ENGINEERS CONTINUE THE UPPER SUSITNA RIVER BASIN PRE-. CONSTRUCTION PLANNING. WHEREAS,the Corps of Engineers has been doing preliminary studies of the Susitna River Hydro-Electric power potential,and WHEREAS.reports indicate this as a feasible source of energy to generate electricity.and WHEREAS,use of hydro power would conserve natural non-renewable resources such as petroleum,natural gas and coal.and WHEREAS.energy demands are increasing as Interior Alaska develops. and WHEREAS.it is important that a source of dependable,reliable, \ \ NOW.THEREFORE.BE IT RESOLVED by the asseTIbly of the Fairbanks North Star Borough that the Corps of Engineers continue the Upper Susitna River Basin (Southcentral railbelt area),Alaska pre-construction planning. PASSED AND APPROVED THIS ".IIiIIl11IrI1r, .•.•...).1 i:I ~"'"~....,\..lnr'Jt'~"";"1 "~ (''.'...."".)'\.,.'.,"" ,..'•'j.'\)., ",.)I I I '0'.)• .I (J \ " •I I .J .i ~TJESl;:.):-?::',.../ '.,:'.•.:)'J .....>••/:I,\l.•.••.~./ j J"~'"",,"/;"',',~•••~~ '."I ( \"•"'\~'~\\\\'.~~ rl .....,...1 .r I I _..."'i •1 9th DAY OF o_c_t_o_b_e_r 1975. Appendix II 61 lo)5/7~ &,'~~~])~ Appendix II 62 STILLWATER CILINIC BOX 8 COLUMBUS,MONTANA October 21,1975 Alaska District Corp of Engineers Anchorage,Alaska 99500 Re:Upper Susitna Basin Hydro-Electric Power Development. Dea.r Sirs: It comes to my attention that a power development including a dam or several dams in the upper Susitna and Devil's Canyon is still being proposed.It is my feeling that very little thought has been given to the environmental impact that such a project would have,and the permanent loss of some tremendous river floating and boating in the future years.Thi.s particular stretch ()f river is as magnificent,as far as rivers go,as McKinley is when one considers its relationship to other mountains. I feel that any measure to change or deface this river should be as carefully considered as would a proposal to change or dei"ace Mount Mc Kinle:~I'. I wish you would enter this statement in the hearing record as evidence that there is strong opposition to the Devil's Canyon fum that will permanently destroy the marvels of this canyon. Sincerely yours (!!il-f;V7W.P-A,-A 4~ C.H.Swanson Jr ••M.D.~j CHS/ch Appendix II 63 Greater Anchorage CHAMBER of COMMERCE October 22,1975 Crossroads of the Air W' Colonel Charles A.Debelius District Engineer Corps of Engineers P.O.Box 7002 Anchorage,Alaska 99510 Dear Colonel Debelius: On behalf of the Board of Directors and membership of the Anchorage Chamber of Commerce,I wish to express our total support for the development of hydro- electric power in the Upper Susitna River area. The Chamber would like to offer its services in helping to promote the con- struction of the Devil's Canyon and Watana dams as soon as possible.Please callan us for any further help we may provide. Sincerely yours, d~~IJ;;G(~u Loren H.Lounsbury President sww Appendix II 64 r;REATER ANCHORAGE CHAMBER OF COMMERCE -612 F STREET,ANCHORAGE,ALASKA 99501 -(907)27:'." Knik Kanoers &Kayakers J Inc. 3014 Columbia Anchorage,Alaska 99504 17 November,1975 Col.Charles A.Debelius,District Engineer Alaska District,Corps of Engineers Department of the Army P.O.Box 7002 Anchorage,Alaska 99510 Dear CoL Debclius: The Knik Jillnoers &Kayakers wish to go on record as opposing the construction of any dams on the Susitna River.Such development would destroy a major wilderness whitewater river, termed lithe biggest in North America"by its first paddler, Dr.Halter Dlackadar. In the 'fifties·and 'sixties the Corpa dammed a number of the nation's finest whitewater rivers in the name of "progress." Yet each new dam served only to spur on further profligate use of energy.In other words,these beautiful rivers were sacrificed to no useful purpose.Nowadays such economic boondog~les would never win approval,yet the Corps ~s attempt- ing to start the same destructive,wasteful process here with one of the country's most spectacular),wildest,loveliest rivers.The Susitna must be left to I'un free for future generations. Sincerely yours, )•~.,11 \, Ed Swanson President Appendix II 65 Alaska R~§g\.\rC~~brary &Inforr~(~,1\;~i'D;,s~;r¥W&% Anchorage)Alaska