HomeMy WebLinkAboutAPA3414SUSITNA
HYDROELECTRIC PROJECT
FEDERAL ENERGY REGULATORY COMMISSION
PROJECT No. 7114
AQUATIC MONITORING MANUAL
[M]~[ffi~~c:J~~~®~@
SUSITNA JOINT VENTURE
DRAFT REPO.RT
APRIL 1986
D.OCUMENT No. 3414
Alaska Power Authority __ _,.
----~----------------
SUSITNA HYDRQELECTRI(! PROJECT
AQUATIC MONITORING MANUAL
Report by
Harza-Ebasco Susitna Joint Venture
Prepared for
Alaska Power Authority
Draft Report
April 1986
Document No. 3414
Susitna File No. 4.3.1
l;
b tc ~~ ~.
l:
I
t
\
I I'
l
L r
I
l
f
I
l
I
NOTICE
ANY QUESTIONS OR COMMENTS CONCERNING
THIS REPORT SHOULD BE DIRECTED TO
THE ALASKA POWER AUTHORITY
SUSITNA PROJECT OPPICB
TABLE OF CONTENT
Section/Title
l.U INTRODUCTION
2. 0 PROCEDURES
2.1 WATER QUALITY
2.1.1 Dissolved Gas Supersaturation
2.1.2
2.1 .. 3
2~L4
2 .. 1.5
2 .1.6
Temperature
Ice
Tu~bidity/Sediment
Mercury
Miscelle.neous Water Quality Parameters
2.2 WATER QUANTITY
2.3 BIOLOGICAL
2.3.1 Salmon*
2.3.1.1 Adult Escapement
i. Enumeration
ii. Access
iii. Spawning Success
2.3.1.2 Egg Incubation
i. Physical Parameters
i i. Survival
2.3.1.3 Juvenile Rearing
i. Enumeration
ii. Growth
2.3.1.4 Outmigration
i. Enumeration
ii. Timing
iiie Size/Age
2.3.2 Resident Fish *
2.3.2.1 Spawning
i. Enumeration
ii. Success
2.3.2.2 Rearing
i. Enumeration
ii. Growth
2.3.2.3 Migration
2.4 STRUCTURAL
2.4.1 Fluvial Geomorphology
2.4.2 Slough Modification
3.0 QUALITY CONTROL
4.0 KEPORTING
.5.0 CORTINGENCIES
6 .. 0 REFERENCES
431007
860303
.
~
.PREFACE
This manual was prepared by the Alaska Power Authority for use during the
development and operation of . the Susitna Hydroelectric Project. Severc:.l
sources provided material for inclusion in this manual. Major portions were
derived directly from procedure manuals developed by the Alaska Department
of Fish and Game for previous studies on the Susitna Project.
The Power Authority is the project proponent for the Susitna Hydroelectric
Project. The Director of the Power Authority, working in concert with the
Board of Directors, is ultimately responsible for the overall monitoring
program. However, the key contact concerning the implementation and
progress of the monitoring plan will be the Director of Environment and
Licensing~ This individual, or a designee, will manage the program and will
be responsible in assuring that it is carried out as planned. At present,
the Alaska Department of Fish and Game's SuHydro Aquatic Study Team carries
out many aspects of the program, particularly the fisheries-related studies.
It is anticipated that they will continue in that role. Other aspects of
the program not performed by the SuHydro Study Team will be carried out
directly by the Power Authority or its designee. It is anticipated that the
resource agencies will continue to be actively involved in the m.onitor·ing
activities through continued interagency consultation with the Power
Authority, on-site visits, and the annual review process.
Mention of specific product names does not constitute an endorsement by the
Power Authority. Certain instruments have been used in previous and on-
going monitoring work; therefore, it is recommended that either the current
models or their equivalent be used for future studies.
431007
860303
ii
I
r
I
1.0 Introduction
Monitoring is an essential part of the Susitna Hydroelectric Project. The
purpose of this long-term aquatic monitoring plan is to determine if objec-
tives for maintaining fish and aquatic habitat are met~ It will focus on
areas downstream of the project in order to;
o Determine baseline (natural) and with-project conditions
o Evaluate the effectiveness of mitigation measures
o Provide input to refine operation procedures and mitigation
measures
o The Susitna Hydroelectric Project will impact aquatic resources
The basic approach to aquatic monitoring is to compare selected pre-project
conditions with with-project conuitions to determine if unpredicted signifi-
cant impacts have occurred, and to determine the effectiveness of mitigation
measures. The data requirements will depend upon the parameter or situation
to be monitored. Monitoring will begin with the 1985 field season and
continue through project completion (Table 1). It is believed that as the
project matures, significant impacts will be mitigated fully and the need
for monitoring 'tqill decrease. Should monitoring reveal that conditicns
other than those anticipated exist, the resource agencies will be consulted
and agreement will be reached on specific modifications to correct them.
This mc\nual only presents procedures for monitoring. The overall rationale
for development of the monitoring plan and selection of parameters are pre-
sented in other documents (Harza-Ebasco 1985, APA 1986).
431007
860303
1
Study Element
A. Water Quality
1. Dissolved Gas
Supersaturation
2. Temperature
3. Ice
4. Turbidity/Sediment
5. Heavy
Metals
6. Miscellaneous Water Quality
Parameters
B. Water Quantity
C. Fish Resources
D. Structural
1. Fluvial Geomorphology
2. Slough Modification
431007/TBL
TABLE 1
SUSJITNA HYDROELECTRIC PROJECT
SCHEDULE FOEl LONG-TEIDf AQUATIC MONITORING PLAN
Prior Stage I
Data 1985 1986 1988 1989 1990 Watana
Avail. W S S F W S S F W S S F W S S F W S S F Complete
yes
yes
yes
yes
no
yes 1 --------
Stag~::: II
Devil Canyon
Complete
Stage III
Watana
Complete
Complete
Project
+ 5 years
------------------>
yes ------------------------------~-------------------------------------------------->
yes
yes
no (If incorporated as part of mit1gation)
(Perfo,ed on a~ as-nee1ed basir
W S S F -Winter, Spring, Summer, Fall
------->
-------> ------->
2.0 PROCEDURES
2.1 Water Quality
2.1.1 Total Dissolved Gas Saturation
2.l.lel Program Description
i. Objectives:
The ma1n objectives of the total dissolved gas monitoring will be
t ():
o Document the relationship between river discharge and
natural, total dissolved gas concentrations
o Monil~r total dissolved gas concentrations resulting from
fixed cone valve, spill'w·ay, and powerhouse discharges
o Assure that concentrations meet any regulatory require-
ments
ii. Rationale
431007
860303
Dissolved gas supet'saturation from dams primarily occurs v1hen water
is released over a spillway and plunges into a pool. This entrains
air and carries it to depth where the hydrostatic head forces it
into solution. If the hydrostatic head at depth is sufficient, the
air will stay in solution. At shallower depths, however, supersat-
urated gas comes out of solution as the gases equilibrate with the
atmosphere, thus caus1~g bubbles to form. If the gas comes out of
solution within a fish, it may cause mortality, or sublethal
stress.
3
To avoid potential impacts from supersaturation, operational proce-
dures for the project have been designed to minimize the need for
spillway discharges. One way this will be accomplished is to store
and release all floods with recurrence of 50 years or less. Anoth-
er means will be to provide fixed cone valves for both dams.
Releases from these valves would be dispersed as a spray and there-
fore would not plunge to depth nor be expected to cause dissolved
gas saturation in excess of 110% downsLream.
To assure that these operational procedures and structural features
work as designed, total dissolved gas concentrations resulting from
discharges through spillways, fixed cone valves, and the power-
houses of each dam will be monitored.
Turbulence in Devil C&nyon naturally causes super saturation down-
stream of the canyon, with higher discharges resulting in higher
dissolved gas concentrations (Figure 1). These concentrations can
exceed the State of Alaska maximum allowable standard of 110% total
dissolved gas saturation when flows in the river are greater than
about 15,000 to 20,000 cfsa Naturally occurring supersaturation
levels decrease by approximately 50% in the first 20 miles down-
stream of Devil Canyon. Fish collected in the area of highest gas
concentrations bave net exh1bited any of the signs associated with
bubble disease (ADF&G 1983). The data collected thus far 1s
sufficient to provide a general understanding of the relationships
concerning dissolved gas concentrations in the Devil Canyon reach.
Additional pre-project data will be needed, however, to .fill some
information gaps.
iii. Program Design
431007
860303
This task will focus on comparing total dissolved gas concentra-
tions resulting from various combinations of project discharge from
fixed-cone valves, spillways, and powerhouses for· both dams. These
4
431007
860303
INSERT FIGURE 1
DISSOLVED GASES RELATIONSHIP
5
!
l
I
I
l
l
l
I
!
I
l
both c.qms. These concentrations will be compared to baseline
pre-project conditinns and to State water quality stand.::.rds in
order to ascertain whether or not a significant impact exists.
Field data will be obtained from continuous recording total
dissolved gas meters located at fixed sampling locations. Inten-
sive sampling will be performed during early phases of each project
stage. Once it is demonstrated that mitigation measures (fixed
cone valves, flood flow retention, etc*) have achieved their goals
over a range of project conditions, the monitoring of dissolved gas
conce~trations will be reduced or phased out.
2.1.1.2 Data Collection
i. Methods
431007
860303
Continuous recording dissolved
baseline data has been collected
both built by Common Sensing (
gt:\s meters will be used. The
;.Jith two models of recorders -
) .
It is recommended that either these models or their equivalent be
used for future data collection. If modt:ls are changed, tests must
be made to determine the comparability of data collected. between
the new models and those previously used. The methods for opera-
tion and calibration of these meters are attached in Appendix A.
Interfaced with these meters are datapod recorders (Appendix B).
Also coupled with the meters are continuous recording temperature
probes (see Figure 2). Although internal gel cell batteries are
provided with the model , the meters tnust be connected to a 12
volt car battery (cr its equivalent) for long term reliability.
Probes will be attached to the meters us~ng 30 ft. cable (available
from the manufacturer). This wi 11 allow sufficient length for
placement of the mete.r and battery above the high water mark.
6
431007
860303
INSERT FIGURE 2
CONTINUOUS RECORDING TEMPERATURE PROBE
7
431007
860303
high water mark. Each meter and attached battery must be appropr1-
ately guarded from weather~ theft, and vandalism.
Prior to field operation, the meters must be calibrated and checked
to ensure that they are functioning properly. This must be done
according to :i.nstructiQns d~~c:ribecl in Appendix A. Information
that must be maintained in the permanent data files includes:
o Data on calibration or servicing
o Person or group that performs servicing
o Repairs or calibrating that has been performed
o Any notes on the general condition of the units
During the field season, the meters should be checked once each
month and calibrated to assure that they are functioning properly.
This should be done in cc"lformance with instructions in Appendix A.
Particular attention must be paid to the general condition of the
probe and semi-permeable membrane, battery output, and readings for
temperature and dissolved gas recordings. If a meter is not func-
tioning properly, and the problem cannot be corrected, then the
meter must be removed from the field and repaireda
When a meter is placed at a particular location, the following must
be recorded either in a permanent log book or on data forms:
o Date/time of placement and person( s) and group respons-
ible
o Location of unit (to nearest 0.1 river mile)-include a
map with notes on general current flow, depth of probe,
and location of meter
8
o Notes on initial performan<-e and any addi tiona 1 calibra-
tion required
During the sampling season, meters must be checked at least once
each month. Data is recorded on an erasable mini~ture electronic
memory chip or data storage module (DSM). Total dissolved gas is
me:~sured every 5 minutes and the average, minimum, and maximum are
recorded ever 6 hours on the DSM. A DSM has a storage capacity of
2, 047 readings and thus, replacement is necessary every 84 days.
Prior to installation each probe must be calibrated and assigned a
correction value. The following must recorded:
o Date and time of servicing and the person( s) or group
re span sib le
o Notes on any recalibration or servicing needed,
including:
1~ Condition of probe with particular attention to
semipermeable membrane -replace if damaged or not
working correctly. Replace according to instruc-
tions in Appendix A.
2. Check temperature against glass thermometer (accur-
ate to-* 0.1 °C). Adjust if necessary.
3. Check total gas pressure aga~nst a mercury barometer
to determine if recalibration is necessary. If the
total gas meter is recalibrated, this must be noted
in a log book or on a data form.
4. The data storage module (DSM) should be removed, its
serial number ~ecord~d, and a ne-.;<7 DSM chip (with
se~ial number recorded) replaced in the datapod.
431007 9
860303
AJ1007
860303
At the end of each sampling season, the meters must be cleaned,
serviced, and checked. They are then to be checked through the
Power Authority 1 s equipment control and placed in dry storage for
use during the next season.
Field installation procedures for the total dissolved gas meters
are as follows (refer to Figure 3):
1. Install a fence post on the stream bank out of the range
of flood flows and attach a waterproof storage box to
the post.
2. Install the meter and a data pod recorder l.n the water-
proof storage box~
3. To obtain water temperatures at the streambed, attach
the probe to either a weight or a spike so that the
probe can monitor the total dissolved gas (and tempera-
ture) of the lower portion of the water column. Then
run the probe cable along the streambed/steambank to the
recorder, concealing the cable so it cannot be damaged
by debris, vandalism, or wildlife.
4. Attach the probe cable(s) to the recorder.
5. Check the operation of the data pod and probes. To
ensure the datapod and probes are operating normally, a
short data display sequence must be activated. This is
done by pressing the grey exterior button. The follow-
ing information is then displayed: errors made in
storage, number of storage points used, minutes until
the next recording, and current total dissolved gas and
temperature readings. Surface water temperature will be
10
431007
860303
INSERT FIGURE 3
DISSOLVED GAS DATAPOD FIELD INSTALLATION
11
measured at the surface water probe with a calibrated
thermometer with an accuracy of +0.1 °C and compared to
the datapod temperature.
6. Close the waterproof storage box, making sure it 1s
properly sealed and secured~
Units must be monitored twice monthly after installation for low
battery charge or disturbance. Probes and cables must be checked
for physical damage, siltation, or dewatering. The short data
display sequence is activated and recorded, and the total dissolved
gas (and water temperature at the streambed) is calibrated accord-
ing to precedures in Appendix A. Data concerning calibration and
servicing ar~ recorded. Data storage modules are changed if
necessary. They are replaced when nearly full or sooner, if the
data are required prior to scheduled replacement.
ii. Locations
431007
86030.3
During the pre-project baseline monitoring, sampling locations will
be in the mainstem river at Curry Station (RM 120), Gold Creek (RM
136.9), just upstream of Portage Creek ( 148.9). and at the Watana
Dam site (RM 184 .4). With-project monitoring will begin with
initial testing of the fixed cone valves and the spillway for
Watana. Sampling locations during this initial period will be the
same as for natural conditions (Table 2). An additional station
will be located immediately upstream of either the cone valve
inta!tes or the spilhmy.. This station will serve as a control for
comparison to measurements downstream. Similar positioning of
stations will occur at the Devil Canyon damsite when it becomes
operational. One station, will be upstream of either the spillway
or cone valve intake. The other downstr-eam stations will include
those for pre-project sampling.
12
TABLE 2
SUSITNA HYDROELECTRIC PROJECT
TOTAL DISSOLVED GAS SAMPLING LOCATIONS AND FREQUENCY OF SAMPLING FOR
SUSITNA HYDROELECTRIC PROJECT AQUATIC MONITORING PROGRAM
l. Devil
Watana Canyon Watana
Project Operation Operation Operation
Phase 'Pre-project (Stage I) (Stage II) (Stage III)
-
Curry Station
(Mainstem Susitna) X X X X
Gold Creek
(Mainstem Susitna) X X X X
Above Portage
Creek
(Mainstem Susitna) X X X X
Watana Damsite
(Mainstem Susitna) X X X X
Downstream Down3tream Downstream
of Project of Project of Project
Spillway, Powerhouse,
or Cone Valve Intake-
Devil Canyon Dg~ X
Spillway, Powerhouse,
or Cone Valve Intake-
Devil Canyon Dam X
Spillway, Powerhouse,
Cone Valve Intake-
Watana III X
Long-term
Permanent
X
X -Meter will be at this location until testing of various combinations of spillway, cone
valve, and powerhouse discharges are complete.
431007 /TBL
. ~ \
1:
l
I
!
[
I
I
l
r·
l
I
1
l
l
)
l
i
i
. . .
11.1..
431007
860303
Once the various combinations of spillway, cone valve, and power-
house discharge are tested, and if no significant problems due to
dissolved gas supersaturation are found, the sampling locations
will be reduced to the one permanent station just upstream of
Portage Creek.
The test conditions that should be monitored are max1mum power-
house, spillway, and cone valve discharge. Each one of these
should be tested separately (e.g., monitor for total dissolved gas)
in areas downstream of the respective dams during the largest
operational powerhouse discharge. Repeat the test during a max1mum
cone valve release~
For any of the above test conditions, an intermediate discharge
should also be tested (e.g., one·-half the operational cone valve
discharge). The spillway will be tested during initial project
startup. Although the actual discharge over either the Watana or
Devil Canyon spillways is not known at present, monitoring gear
must be in place before maximum flows are reached •
Schedule
Extensive amounts of data have already been collected concerning
total dissolved gas concentrations in the Susitna River (ADF&G ,
APA 1986). These serve as sufficient information for baseline
purposes. One additional data collection during the open-water
season will be required prior to commencement of project construc-
tion. This will be necessary to assure that earlier data collec-
tions represent baseline conditions (i.e. no physical changes have
occurred in the Susitna River which may have altered baseline
conditions).
During project construction and operation, sampling will be initi-
ated at the beginning of each new project phase and will continue
13
f
f I
I
until combinations of discharge from spillways~ cone valves, and
powerhouses are sufficiently examined to assure that no significant
problems exist.
One meter will be maintained upstream of Portage Creek for .:tn
indeterminant amount of time. Once the relationships between total
dissolved gas resulting :Erom the various project discharge struc-
tures are defined, operation of this meter will be discontinued.
2.1.1.3 Data Handling
i. Field Data
Field records will be in the form of:
a. Records on meter and data pod performance (e.g • .! calibra-
tion dates, repairs, etc.)
b. Data storage modules (DSM's) from the datapods and records
about placement and retrieval of the data storage modules
ii. Date Transfer
431007
860303
A copy of the records for (a) above will be kept at the field
office (location undetermined at this time). A duplicate copy will
be kept at the SuHydro office in Anchorage. At the end of each
calendar year, a copy of the records for the entire year will be
sent to the Power Authority.
The DSM's will be sent directly to SuHydro in Anchorage for t~ans
lation. The data is retrieved from the DSM via an Omnidata model
217 Datapo.i/Cassette Reader (in Anchorage) and printed as 6-hour
maximum, minimum and mean dissolved gas levels.
14
f
!
I
The following gen1eral procedures are followed when transmitting
field data to Anchorage.
1. After the data has been reduced and checked as stated
above, the data ~s transmitted to the QC auditor in
Anchorage.
2. The QC auditor checks for obvious errors and proper
format and corrects problems (after consultation with
field crews). The QC auditor transfers a photocopy of
the data to the project computer for processing. The
original copies of the data are categorized and filed by
site and activity (i.e., form number) in chronological
order.
3. The data is processed into the project computer.
4. A printout of the processed data is returned to the QC
auditor for checking and editing. It is then transfer-
red to the project leaders, and field personnel for
additional checking and editing.
5. The checked and edited printout is returned to the QC
auditor for transmittal back to the computer.
iii. Data Analysis
431007
860303
As part of their annual report to the Power Authority, Sultydro will
provide an analysis of the data. This analysis will include:
o A time series graph (for the entire year) for each station
that shows discharge (mainstem at Gold Creek -USGS gaging
station no.), and total dissolved gas saturation
15
431007
860303
o A hard copy, tabular computer output which has the total
dissolved gas saturation (percent saturation), tempera-
ture, discharge (mainstem at Gold Creek) and date shown by
six hour increments for each sampling date
o A comparison to long-term natural baseline conditions and
water quality standards
o A discussion of difficulties or problems encountered
during sampling which may affect results
o A detailed description of any calculations or adjustments
used in arriving at the final data (e.g., any adjustments
made to percentage saturation as a result of temperature
or barometric pressure)
16
r
l
r
I
J
2.1.2 Water Temperature
2.1.2.1 Program Description
i. Objective
The main objective of the watter temperature monitoring task will be
to document pre-project and! with-project water temperatures down-
stream of the project. This documentation will be used to deter-
m1ne if with-project water temr· . atures agree with 2re-project
projections and to refine, if nE:.: c 1sary, multi-level intake and
cone valve operation.
ii. Rationale
431007
860303
Water temperature 1s a key parameter that directly affects every
aspect of the life history of aquatic organisms in the Susitna
River. It also affects aquatic habitat, primarily through the
effects of ice processes. These effects can be either positive or
negative; therefore, documentation of pre-project and with-project
water temperature regimes is a necessary component of aquatic
monitoring.
The Power Authority has included multi-level intakes in the designs
for both the Watana (Project Phases 1. and III) and Devil Canyon
developments in order to mitigate for potential temperature impacts
on ice formation and aquatic organisms.. These intakes wi 11 be
operated to provide as near natural temperatures as possible.
There is some flexibility in selecting temperatures of the water
discharged from these structures. Within the range of selection,
some optimization of the temperature regime for downstream areas
may be possible. To perform this optimization, water temperatures
must be recorded and used in the overall analysis of with-project
impacts.
17
iii. Program Design
Pre-project and with-project temperature data will be collected at
fixed stations on the Susitna River. This will be done on a
continuous basis except when conditions during the ice-covered
period are at or near 0 °C.
thisG
Spot checks will be made to confirm
With-project water temperatures will be compared to pre-project
data and model predictions (APA 1986). They will also be used as a
key factor in the analysis of project impacts on aquatic
organisms.
2.l.2a2 Data Collection
1o Methods
431007
860303
Water temperature data will be collected in conjunction with
sampling for total dissolved gases. The meters used for tot a 1
dissolved gases (see Appendix ) incorporate a teiuperature
recording system that can store data in the attached datapods ~
All data collecti0n and processing, calibration, and field
procedures will be the same as those for total dissolved gases
monitoring (see Section 2 .1.1), except at Sunshine Station were
only a datapod recorder will be used.
Two-channel Datapod recorders (or their equivalents) using TPlOV
temperature probes (see Appendix B) will be used to monitor and
record surface water temperatures at Sunshine Station. Instrument
accuracy, as stated by the manufacturer (Omnidata International),
is i_O.l °C. Data is recorded on an erasable tnt:mory chip or data
storage module (DSM). Temperatures are measured every 5 minutes
and the average, minimum, and maximum are recorded every 6 hours on
the DSM.. A DSM has a storage capacity of 2, 04 7 readings and thus,
18
replacement is necessary every 84 days. Prior to installation each
probe must be calibrated and assigned a correction value.
ii. Locations
Sampling sites will be the same as those for total dissolved gases
with the addition of a site at the Sun shin£ Station (RM 80). The
same scheme for placement of the meters will be used for both
pre-project and with-project monitoring.
iii. SchedulE:
431007
860303
Pre-project studies will occur dt1ring the open water season (May
through October). With-project studies will be conducted through-
out the year at stations where meters can be maintained. During
the open water season, this will be at all stations. During the
ice-covered season, only those stations upstream of the ice front
will be maintained.
Extensive amounts of water temperature data on the Susitna River
are already available; therefore, only one additional year of data
will be needed prior to the initiation of project construction.
Extensive data collection efforts will continue at all stations
throughout construction and at least 5 years into operation.
Thereafter, the monitoring program for temperature will be reduced
in scope with only one permanent station tentatively located just
upstream of Portage Creek. If temperature measurements at this
station are not found to be representative of the river (in other
words, the flows from the powerhouse, cone valves, and spillway are
not well mixed by the time they reach this station), then another
permanent station may be needed downstream.
19
2.1.2.3 Data Handling
i. Field Data
Immediately after installation of the recorder and pr1or to removal
of a full DSM, a streambed water temperature is obtained with a
calibrated mercury thermometer. In addition, streambed water
temperature is obtained from a "short data dump" which the recorder
is programmed to yield. The "short data dump" is a listing of data
which also includes errors accumulated, numbers of data points
stored, and minu.tes to next recording. The two streambed water
temperatures are compared, taking into consideration probe calibra-
tion factors, to ensure accuracy of the instrument.
11. Data Transfer
Data on temperature will be transfered simultaneously with total
dissolved gas measurements (See Section 2.1.1.3ii).
All data/information requests or transmittals must go through the
Power Authority. In addition, all data/information requests or
transmittals tQ persons/agencies outside the Alaska Power Authority
must go through the Power Authority's Aquatic Studies Coordinator.
A complete copy of all data transmitted and a copy of the transmit-
tal letter/memo will be kept in the QC files. In addition, a log
is maintained which provides a record of all transmittals.
iii. Data Analysis.
431007
860303
As p~rt of their annual report to the Power Authority, SuHydro will
pr0vide an analysis of the temperature data. This analysis 1-1ill
include:
20
= f..._m
431007
860303
o A time series graph (for the open-water season and ice
free areas in the winter) for each station that shows
water temperature (in degrees centigrade) and discharge
(as measured in the mainstem at Gold Creek)
0 A hard copy, tabular computer output which has water
temperature, discharge at Gold Creek, and date. This
should be shown by six hour increments for each sampling
date
o A comparison to long term natural baseline conditions
o A discussion of difficulties or problems encountered
during sampling which may affect results
o A detailed description of any calculations or adjust-
ments used in arriving at the final data
21
2.1.3 Ice
2.1.3.1 Program Description
1. Objective
The main objectives of ice monitoring will be to document 1ce
conditions to determine if they follow pre-project predictions and
to adjust dam operational procedures, if needed, to optimize ice
fc1rmation and breakup for the benefit of human and non-human
re&ources e
ii. Rat~onale
431007
860303
The Watana (Stages I and III) and Devil Canyon Reservoirs wil:.
cause water temperatures and ice processes in downstream areas to
differ from natural conditions. In winter, due to reservoir
releases of water ranging from 0 to 4°C, a large portion of the
river downstream of the dam will remain free of ice. In the Middle
River, ice cover formation will be rlelayed from r..atural conditions
(ice fron.~· -progression up the Middle River will be delayed 2 to 6
weeks). .Br~akup will be earlier and less severe because the 1ce 3
at least in the Middle River, iJ expected to melt in place. When
Stage III is completed, the ice front is estimr-.ted to be located 15
to 30 miles downstream trom Devil Canyon. In the ice-free area,
temperatures may remain above natural (0°C) by up to 3°C throughout
the winter. The variation from natural will be greatest near the
dam, and will decrease with distance downstream. Uncle--: the ice
cover, temperatures will be 0° C, the same as for natural conditions
(AEIDC, 1984).
Higher-than-natural winter discharges will result in elevated water
levels downstream of the ice front. Upstream of the with-project
ice front, water levels will be lower than natural because
ice-cover staging will be eliminated.
22
Ch~·:1ges from natural conditions ~o1ill result in more frequent
overtoppings of slough berms wherever an ice cover forms. This
overtopping will introduce cold (0°C) water and ice into the
sloughs. ~lans to prevent this cvertopping include increasing the
height of the berms at the upper ends of sloughs (WCC 1984a). The
Power Authority has included multi-level intakes in the designs for
both the Watana (both stages) and Devil Canyon developments to
provide as near natural temperatures as possible.
The ice processes in the Susitna River can cause extensive changes
in habitat and potentially can affect human resources (e .• g., ice
can impact structures suGh as bridges, railroad beds, etc.).
Although the with-project ice processes are expected to have less
potential for causing change, it is necessary that ice formation
and breakup be carefully monitored, especially during the early
years of project operation, to assure that pre-project predictions
are realized. This monitoring will also be needed to determine if
any changes in dam operation could provide more optimum ice proces-
ses (e.g., release warmer winter discharges to further delay i.ce
formation).
iii. Program Design
431007
860303
Pre-project overflights and field studies of the Susitna River have
been completed. The observations made during the overflights have
concentrated on . 1ce J.ce front progression up the formatioa and
river, ice thickness at selected locations, overtopping of sloughs
due to staging, location and effects of ice jams, forms of ice
development (anchor ice, frazi.l ice, etc.) and breakup processes
(R&M Consultants, in press). In addition to these overflights,
extensive modelling of with-project ice conditions has been made
(APA 1986). Monitoring of with-project ice conditions will be
continued throughout the operation of the project. This monitoring
wlll be intensive during initial project operation and will then
generally decrease as project operation becomes routine.
23
In addition to ice observations, weather stations were maintained
at Denali, Watana damsite, Devil Canyon damsite, Sherman and
Talkeetna. The purpose of these stations was to provide weather
data for correlation to ice formation. All stations except the
Talkeetna weather station were maintained by R&M Consultants
( 1984). The Talkeetna weather station (located at the Talkeetna
airport) was maintained by the
Atmospheric Administration (NOAA).
Talkeetna) will be maintain~d to
studies, as needed.
National Oceanographic and
·rwo stations (Devil Canyon and
support the ice monitorir1g
2.1.3.2 Data Collection
i. Methods
Pre-project overflights were made by hel::.copter from Cook Inlet to
the upper Susitna River (AEIDC, in press). They were generally
conducted on a weekly basis from September through January to
describe the freeze-up process. Breakup was periodically observed
from April 12 to Nay 15. Once the process began, observations were
made on a daily basis until breakup was complete.
With-project overflights will be the same as pre-project.
ii. Locations
431007
860303
Overflight observations will be made from Cook Inlet to the Watana
damsite (for Stage I only and then Devil Canyon thereafter). They
will concentrate on the mainstem Susitna River.
Weather stations lilill be maintained at Talkeetna and Devil Canyon
to continue supplemental information collection that may be needed
for correlation to ice observations. It is expected that these
stations will be maintained primarily for other reasons (it .
1S
24
assumed thac NOAA will maintain the station at Talkeetna as part of
its normal weather observations and the Power Authority will main-
tain the Devil Canyon station as part of normal project data
collections).
2.1.3.3 Data Handling
1.. Field Data
43l007
860303
Field data will be separated into two different types:
o Observations made during overflights and data from the
weather stations
A trip report will be required for each overfligl:-1\t. This report
will be a narrative description that will include, but not be
limited to:
o Date of overflight
o Observer
o General weather conditions
o Time of trip (begin/end)
o Location of ice bridges
o Locations and effects of ice jams
o Channel morphology changes
o Aquatic habitat modifications (e.g., oyertopping of
sloughs)
0
0
Ice in side channels and sloughs
Flooding of islands
25
o Measurements at selected locations to determine staging
due to the ice cover (this will be done at existing
staff gauges at:
1.
2.
3 ..
4.
5.
6.
7.
Any additional notes or observations that appear meaningful should
be incorporated into the report. An ex.1mple of additional notes
would include comments on any damage to modified sloughs, particu-
larly the berms that protect them. All locations mentioned in the
report must be referenced to the nearest 0.1 river mile.
ii. Data Transfer
431007
860303
When an overflight is completed, the narrative description will be
formalized. The original of this report will be maintained by the
group performing the 0'\:rerflight. A copy will be sent to the Power
Authority for their files. At the end of the ice-covered season,
an annual summary report will be submitted to the Power Authority
within two months after the final overflight.
The weather data from the Talkeetna station will be obtained from
NOAA through a formal request by the 'Power Authority or its
designee. Data from the Devil Canyon site will be processed on a
monthly basis.
26
iii. Data Analysis
431007
860303
Unless further analysis ice processes is warranted, the . 1ce for
observation data and the weather station data will archived by the
Power Authority for future reference. If, however, some unfore-
seenproblems do arise or there is a need to Change operational
procedures for the dam (e.g., change the release temperature), then
further analyses will be performed as appropriate. It is antici-
pated that both the ice observation data and the weather data will
be used for other purposes; such as terrestrial monitoring studies,
or to address any potential concerns of the Alaska Railroad or
people that inhabit sites near the river downstream of the dams.
It is, therefore, important that these files be well-maintained.
27
2.1.4 Turbidity/Sediment
2.1.4.1 Program Description
i. Objective
Turbidity
selected
monitoring will be performed to
optical characteristics of waters
document changes
downstream of
to
the
project. Sediment monitoring will be performed to document changes
to bott bedload and suspended sediment discharges from the impound-
ment zone. Both programs will provide basic input for evaluating
potential biological changes at all trophic levels 1n waters
downstream of the project.
ii. Rationale
431007
860303
Most sediments that presently depend on the river's tractive force
for downstream transport are expected to be trap~~d upstream of the
dams. Particles passing downstream through the dams will be fewer
and Slilaller, and the averagf:! mineral composition and three-dimen-
sional shapes will be altered. The present suspended sediment and
turbidity regimes should become more seasonally continuous and less
variable. Enhancement of biological productivity is possible if
sufficiently clearer water can be combined with river ten~peratures
and a flow regime which protects critical aquatic habitats during
appropriate seasons.
Biological changes are expected to orcur at all trophic levels in
aquatic habitats dir.ectly affected by project-induced changes in
suspended sediment and turbidity regimes. Because changes in these
parameters can either positively or negatively affect fishery
reso·Jrces, it is important to understand how much change will
occur.
28
iiio Progr~m_Q~sign
Turbidity monitoring will include the determination of nephelo-
metric turbidity units (NTU's) of waters sampled, plus a complete,
detailed description of sample collection and sample analysis
procedures, and all notations (including field notes) made.
Sediment monitoring will include the determination of the
following:
o Total sediment discharge (tons/day)
o Bedload sediment discharge (tons/day)
o Suspended sediment discharge (tons/day)
o Suspended sediment concentration (mg/liter)
o Settleable solids (mg/liter)
o Suspended sediment particle size classification
2ol.4.2 Data Collection
i. Methods
431007
860303
Turbidity samples will consist of replicate subsamples of each
sample collected for suspended particulate analysis (see below).
Each subsample will be taken according to the best available
technology utili~ed by the USGS. Nephelometric analysis of a~ 1
samples will be performed within 24 hours of collection. Samples
will be stored at less than 4°C in dark; .. :ess until they are prepared
for analysis by warming them to a standardized laboratory tempera-
ture (18 to 24 °C). The temperature and subjective .. ·ppearance of
each sample shall. be recorded at the time of analysis.
29
Total sediment, bedload sediment, and suspended sediment discharges
wi 11 be collected using the technology recommended by the USGS
(1969). Samples to be analyzed for suspended and settleable sedi-
ment concentrations, sediment particle size classification, and for
turbidity will be subsampled from composited, verticallyintregrated
water/sediment samples taken with an appropriate device (e.ge USGS
P61 sampler). Such samples will be collected from at least three
substations along a horizontal transect at each sampling station
(see Section ii¥ Location, below). Each substation will represent
at least one-third of the river's discharge (i.e., nearshore,
middle, and farshore). One liter water samples taken vertically at
each substation will be combined to form a "composite" station
sample. Each station sample will be analyzed as follows:
Total Suspended Sediment (mg/1) -Prewash and weigh a 0.45 -
0.50 micron nominal pore size filter until a constant weight
is attained. Attach to vacuum bottle containing water sample
and apply vacuum pressure. Dry filter at 105°C until a con-
stant weight is attained. Repeat for at least two 100-500 ml
replicates and record all replicate weights.
Settleable Solids (mg/1) -Use the most recent methodology,
according to the "Standard Methods for Water and vlastewater"
of the American Public Health Association (1980).
Suspended Sediment Particle Size Classification -Use the
most recent USGS methodology (USGS 1969).
ii. Location
431007
860303
Samples for turbidity and sediment analysis will be collected at
the following stations:
30
I
o Vee Canyon (RM 223~1)
o Gold Creek (RM 136.4)
o Sunshine (RM 83.9)
o Susitna (RM 25.8)
iii. Schedule
Samples for turbidity and sediment analyses will be collected twice
monthly.
2.1.4.3 Data Handling
i. Laboratory Data
All data generated by water sample analyses will be tabulated
according to sampling location and time, and stored both on paper
and electronically. Each month a hard copy of all analyses and
results will be sent to the Power Authority. A summary hard copy
will be sent at the end of the sampli·ng year (See Section 4.0).
ii. Data Anilysis
431007
860303
Tabulated data will be compared to ascertain if with-project
conditions differ significantly from pre-project conditions.
Appropriate statistical procedures involving either parametric
(e.g., t-tests) or non~parametric (e •. g., sign tests) testing will
be used, depending on the hypothesis being tested and the
characteristics of the data produced from the sampling regime.
31
2. le 5 M;ercury
2 .. 1. 5 .1 Program Descriptio11;
L. Ob j ect:i v~
The objective of this program ls to collect baseline and
with-project data on the total tissue concentration of mercury in
middle Susitna River fish and fish predators, to evaluate this
data, and to 'make recommendations related to public health.
ii. Rationale
Literature published during the last two decades indicates that
mercury has a tendency to concentrate in a toxic form in the
tissues of higher trophic level organisms as a result of
impoundment construction. The trophic position of vertebrates,
particularly fish an4 fish predators, is ideal for the
bioaccumulation of mert':ury at levels that may be of concern to
human health.
The Susitna Hydroelectric Project has the potential to induce
bioaccumulation of mercury in animal tissues.. It is anticipated
that this will not be a significant problem. There are no known
methods to mitigate for this phenomena other than awareness of the
danger and avoid•1nce of contaminated food organisms. A program is
needed, therefore, to collect and evaluate the data needed to
determine if mercury bioaccumulation is occurring.
iii. Program Design
431007
860303
The program is designed to determine the mercury concentrations in
the tissues of four species of sport fish found in the proposed
Watana and Devi 1 Canyon impoundment zo1 ,._s, including:
32
-·
o Rainbow trout
o .Burbot
o Lake trout
o Arctic grayling
Tissue levels of mercury will also be determined in river otter, a
fish predator. Samples of muscle tissue will be collected in the
fall, when fat reserves are highest. With-project samples ~dll be
compared to baseline samples collected prior to construed on to
determine the degree of impact, if any, the project has had on
tissue concentration of mercury.
2.1.5.2 Data Collection
i. Methods
431007
860303
Organisms for study will be collected by traps, nets, or snares~
which will utilize baits native to the adjacent habitat or no baits
at all. A total of three fish of each species and three otters
will be collected at each sampling location. All o~gan1sms
collected will be sexually mature. They will be killed and sealed
in polyethylene or polypropylene bags as soon as possible after
capture. Contamination or dessication of tissues must be avoided
since both actions can affect sample analysis. Each sample bag
must be labelled and, then frozen until all samples are collected,
at which time they are to be transported to an analytical
laboratory.
The laboratory analysis will consist of EPA techn.ique number 245.1
(see Appendix ) , as ft)llows:
1. Remove a 1 to 5 gr.am sample 0f muscle tissue and digest
in a mixture of sulfuric and rdL:.:ic a~cids.
33
2.-Use the cold vapor modification followed by absorption
spectrophotometery to determine total mercury content.
ii. Locations
Grayling and lake trout will be sampled in any two upper basin
tundra lakes, plus at least one lake in the Watana impoundment
zone.
Grayling, rainbow trout, burbot, and river otters will be sampled
in the mainstem Susitna River within the upper, middle, and lower
. r1.ver zones.
iii. Schedule
All organisms will be collected in late summer or early fall.
Baseline samples will be collected 1 year prior to impoundment;
with-project samples will be collected 5 years after impoundment.
Samples will be analyzed within three months of collection.
2.1.5.3 Data Handling
i. Field Data
This data will consist of the sampling location, the organism
collected, the date, and the collecto~. The data will be recorded
in pencil on waterproof paper and will be affixed to the appropri-
ate sample bag.
ii. Laboratory Data
431007
860303
Data from tissue analyses will be recorded in notebooks and on
computer diskettes. A copy of the results will be sent to the
Power A~~hority within one month ~fte~ the samples are analyzed.
34
iii. Data Analysis
431007
860303
A threshold level of danger is 0.5 to 1.0 ppm= Appropriate statis-
tical tests (Student's t-test) will be used to determine if
with-project ti~sue levels are significantly higher than pre-
project levels. All tissue concentrations will be reviP..wed fo!'
potential public health hazards.
35
2.1.6 Miscellaneous Water Quality Parameters
2.1.6.1 Progra~ Description
~. Objective
The sampling of dissolved oxygen, pH, conductivity, and temperature
is standard in the m~nitoring of aquatic conditions~ ·rhe measure-
ment of these parametrrs will be used to determine if water quality
conditions are within the ranges of tolerance of the Susitna
River's biologic ~esources.
ii. Rationale
Construction and operation of the Susitna Hydroelectric Project
will cause changes in the physical and chemical characteristics of
the Susitna River which, in turn, may have an impact on the river's
biological resources. Knowledge of the ranges of tolerance of
these parameters for the more prevalent biological entities found
in the Susitna River exists. Measurement of these parameters will
yield data useful in the evaluation of the project's effects on
these organisms.
iii. Study Design
431007
860303
Monitoring of these parameters 't\Ti 11 occur coincidentally with the
monitoring of turbidity and sediment' levels (Section 2.1.4). Data
collected under natural conditions will be compared to those
collected under ~ith-project conditions. Comparison of with-
project measureP-lonts to known tolera.r~ce levels of aquatic organisms
found in the Susitna River will be n~de to determine if ~etrimental
environmental conditions have occurred due to project operation.
36
I
2ol.6.2 Data Collection
i. Methods
Field measurements of dissolved oxygen (DO), pH, conductivity, and
temperature are taken with a Hydrolab model 40ld portable multi-
parameter meter (see Appendix ) • The parameters are measured
simultaneously at the sonde unit (underwater pTobe) and the
readings are displayed in an indil!ator unit. The met~rs must be
calibrated prior to entering the field (temperature is factory-
calibrated).. Mel..er calibration, operation, and maintenance
i-t"oc~~ures are list-:-;! in Appendix --
To tske measurements,; place the sonde U!~it in slow-moving, well-
mixed water, such as ehind a boulder, for at least 5 minutes
before taking readings. The instrument should have the DO function
noNH during this equilibration process. Followiilg field use,
perform .~ calibration check to adjust the instrument drift.
ii. Locations
Moni.toring locations for these parameters are the same as those
described for turbidity and sediments (Section 2.1.4).
iii. Schedule
The schedule for monitoring o.f these parameters is the same as that
listed for turbidity and sediments (Section 2.1.4).
2.l.6o3 Data nandl~ng
i. Field Data
Readings taken from
.. Miscellaneous Water
the Hydrolab meter are recorded on
Quality Parameter Form" (Figure Q) •
readings are recorded as they are taken.
431007
860303
the
All
Sampling
Site Sampling
(Name/Rt-1) Date
.
431007/TBL
l?IGURE Q
SUSITNA HYDROELECTRIC PROJECT
FIELD DATA FORM
MISCELLANEOUS WATER QUALITY PARAMETERS
River Water Dissolved
Collected Stage Temperature Oxygen
oy (Gold Creek) c~c) (ppm)
•
Conductivity
PH (umhos/cm)
..
j
ii. Data Transfer
Data collected on the field data form is transfered in tabular form
to a computer floppy disc, according to the program steps listed in
Appendix • Transfer into computer storage occurs within three
(3) days of sampling completion. All field forms are stored in a
three-ringed binder on file with the Director of Environment and
Licensing.
iii. Data Analysis
431007
860303
Data from the monitoring of miscellaneous water quality parameters
is tabulated upon the completion of each year's field season.
Time-series plots are prepared and compared to known tolerance
levels of Susitna River biota to determine if cheshold values have
been reached or exceeded at anytime throughout the sampling
period.
38
I
V.'
.
.
t p .. I"
l
I
l
2.2 Water Quantity
2.2.1 Program Description
i. Objective
The objective of this task is to provide the information needed to
evaluate performance in meeting the Case E-VI flow criteria and the
effectiveness of the criteria in providing for the fishery manage-
ment program.
ii. Rationale
The habitat available for fish 1n the Middle Susitna River .
l.S
related to flows and flow stability. The estimation of habitat
available with-project is based on an assessment of the expected
effects of with-project flows on fishery habitat (APA 1985). Flow
constraints have been developed using this assessment. lt will be
necessary to mouitor with-project flows to determine how the fish
resources are responding to the altered conditions, so that needed
modifications of the flow constraints can be made to improve
conditions.
Additionally, as the flow requirements are expected to be incorpor-
ated in to the Project's License, regulatory agencies will need to
monitor project performance in meeting the constraints.
iii. Program Design
431007
86()303
Th'! program is designed to make all the information necessary for
the evaluation of t-he project's performance in meeting flow
requirements readily available for regulatory agencies review.
Additionally, a method is incorporated for notifying the appropri-
ate agencies when the flow requirements are not met. A third part
39
c"
.. (,~ ~ ··~ " , ..
431007
860303
of the program is the compilation of flow data on an annual basis
for use in other river-reLated studies~
The evaluation of project performance in meeting flow requirements
requires that information on flows in the Susitna River be
available for:
o Gold Creek, where minimum and max1.mum weekly a'r~rage
flows will be evaluated, and
o The most downstream operating project (ise., Watana in
Stage I and Devil Canyon in Stages II and III) where
flow stability criteria will be evaluated.
Additionally, information will be required on inflows to the
project and reservoir water levels to avaluate:
o Whether natu=al streamflows for the year comprise a 1:10
year low-flow condition, and
o Whether fixed cone value and spillway operations were
carried out in accordance with flow constraints on rates
of change of release from these facilities.
Since the information will be used by the Alaska Power Authority in
operation of the project, it will generally be available to
interested parties within a short period of its becoming available
to the Power Authority. The Power Authority expects that the
Project License will require it to notify appropriate regulatory
agencies when it becomes apparent that a flow constraint has not
been or will not be met. The following specific information will
be available from the Power Authority:
40
431007
860303
o Discharges at Gold Creek (in cubic feet per second cf s)
o Project discharges (cfs)
o Reservoir water levels (in feet of elevation)
o Reservoir inflows (cfs)
The Power Authority will notify the £\ppropriate agencies when the
following conditions occur:
1. The average weekly flow for the prev1ous week was below
the minimum flow requirement.
2. The scheduled average weekly flow for the upcom1ng week
will be below the 9,000 cfs minimum by reason of low
inflow for the year or low reservoir water level, or for
any other reason.
3. The flow stability criteria are not ma{utained.
4. . reservo1r water level reaches the normal . max1mum The
level and outlet works operation begins.
J. Outlet works operation ends.
6. The reservoir water
environmental surcharge
must begin.
7. Spillway operation endso
level
level
reaches the
and spillway
. max1mum
operation
8. Susitna River flows at Gold Creek exceed the maximum
constraint wh~!ther as a result of dam safety
41
431007
860303
9.
requirements in passing flows or when flow from the area
intervening between the project and Gold Creek is large.
This notification wi 11 be made as soon as the hourly
discharge exceeds the maximum constraint, or earlier if
it becomes apparent this will happen even if the weekly
average flow remains below the constraint.
. ar1.ses, requiring the project to release An emergency
either significantly more or less flow than plrnned.
Suc1 an emergency may be:
o loss of energy generation from some other
portion of the generating system requiring
additional generation from Susitna.
o loss of energy generation from Susitna for any
reason.
Additionally, the Power /·1thority will make available, at a c.entral
location where flows arc recorded, the expected average weekly
discharge for the next week and will estimate whether outlet works
or spillway discharges are expected.
42
2.2.2 Data Collection
2.2.2.1 River Flow Data -Gaged Sites. River flows on the Susitna River
at the Gold Creek gaging station, Sunshine gaging station, upstream of the
reservoir(s) and on the Oshetna River will be determined by standard ru.:;thods
of the U.S. Geological Survey. Water levels at tbe sites will be monitored,
recorded at the site and telemetered to the project operations ( uter and
the USGS at hourly intervals., At the project operations center, the water
levels will be converted to estimated discharges using the latest available
gage rating curves from the USGS. The USGS in cooperation with the Alaska
Power Authority will maintain the gages in good order. Periodic measure-
ments of flow at the sites will be made to check the gage rating curve. as
deemed appropriate by the USGS and using standarrl methods of the USGS. Gage
ratings will be adjusted as deemed appropriate by the USGS.
2.2.2.2 Flow Data -Ungaged Sites. The Power Authority anticipates th~t it
will develop a system for forecasting streamflow into the prclject as a
result of snowmelt and precipitation. This system will be developed after a
License is granted. This system will be used to estimate flows from ungaged
as well as gaged areas. These estimates will be , relatively long periods
except ilur:i,ng floods when project ()peration requires more frequent data.
The system will include a large number of meteorological and hydr.ological
data gathering stations and a mathematica 1 model of basin hydrology. The
output of this ptodel w:11 provide the estimates of discharge from ungageo
portions of the watershed.
2 • 2 • 3 • 3 F 1 ow data -· Pro j e c t Fa c i 1 it i P. s • Powerhouse flow data will be
determined by summing discharges from operating turbines:.
Outlet works and spillway discharges will be determined from rating curves
established for these features. These rating curves will probably be
established by physical hydraulic model studies and will give discharge as a
function of water surface level in the reservoir and gate opening.
431007
860303
43
All powerhouse, outlet works, and spillway flow data will be collected
hourly and whenever conditions change significantly such as a change in gate
opening or when a turbine begins or ends operation.
2.2.2.4 Reservoir Water Level Data. This data will be determined from
gages placed in the reservoir. Data will be transmit ted to the central
operations center, by wire or by radio.
431007
860303
44
2.l.3 Data Transfer
2.2.3.1 River Flow Data -Gaged Siteso River water levels at gaging sites
will be telemetered to the central project operating center ar.d the water
levels and estimated discharges wi 11 be displayed, recorded and stored
electronically. A summary table will be prepared on a monthly basis.
2.2.3.2 River Flow Data -Ungaged Sites. This will be estimated data and
will be generated by a mathematical model most likely located at the project
operations center. This data will also be .iisplayed, recorded and stored
electronically. Data will be summarized and sent to the Power Authority on
a monthly basis.
2.2.3.3 Project Facilities. This data will be transmittei to the project's
central operations center by wire or by radio and will be displayed,
recorded, and stored electronically. A summary table will be prepared on a
monthly basis.
2.2.3.4 Reservoir Water Levels. This data wi 11 be transmitted to the
central operations center by wire or radio and will be displayed, recorded,
and stored electronically. A summary table will be prepared on a monthly
basis.
431007
860303
45
2.2.4 Data Analysis
Flow data will be reviewed weekly to determine if project operation remained
within the Case E-Vl flow constraints.
At the end of each water year (September 30) all flow data from that year
will be compiled. Data will be based on the final rating curves for the
appropriate gaging stations as adopted by the USGS. This data may vary
slightly from that posted during the year.
include:
Data of significant interest
0 Daily . . m1n1mum, and mean flows for the Susitna River at
Gold Creek, for the site upstream of the project on the Susitna
River, for the Oshetna River site, Sunshine Station and as
estimated for the ungaged portion of the basin
o Daily minimum, max1mum, and mean powerhouse, outlet works, and
spillway releases
Daily minimum, maximum, and mean reservoir water levels
o Hourly outlet works and spillway discharges for all periods when
these featurAs operate
o A summary of all periods when environmental flow requirements were
not maintained and the reasons for these occurrences
431007
860303
46
2.4 Structural
2.4.1 Fluvial Geomorphology
2.4.1.1 Program Description
i. Objective
This program is designed to monitor changes in the gene~al morpho-
logy of the Susitna River (downstream of Devil Canyon) that result
from operation of the Susitna Hydroelectric Project and to assess
the hnpacts of these changes in geomorphic regime on aquatic
resources.
ii. Rationale
The Susitna River is a dynamic system undergoing a natural process
of geomorphic evolution due to physical processes such as ~ce
breakup and flooding. River channels often aggrade or degrade to
adjust to changes in local climate, runoff, sediment supply, or
slope. Changes in these physical pro~esses may be wrought by
with-project flow regulations, with a subseq\:ent alteration in
aquatic macrohabitat. It is expected that the rate of change will
be signficantly reduced ~ith-project; therefore, it is important to
document chauges in the river's geomorphologic pat tern and to
periodically compare the effects of these changes on productivity
of tne aquatic system.
iii. Program Design
431007
860303
The primary means for documenting macrohabitat change~ will be
through detailed aerial photography of the river from Devil Canyon
to Cook Inlet. From these photographs, the macrohabitat types
47
(e.g., mainstem, side-channel, side slough, tributary mouth, etc.)
will be examined qLalitatively and compared to pre-project photos.
Key items of interest will be changes (or lack thereof) due to ice
processes and stabilized __ ows. If other monitoring studies demon-
strate that further analyses are required, these photos will be
available for more detailed quantitative analysis. The photos will
also be used in conjunction "'ith monitoring of terrestrial
resources.
2.4.1.2 Data Collection
~. Methods/Locations
431007
860303
The primary method for obtaining photos wi 11 be through aerial
photography of the entire main stem river from Cook Inlet to Devi 1
Canyon.. Black and white and color aerial photographs will be
obtained at an approxima:::e scale of 1 inch = 1, 000 feet, for the
Middle River (Talkeetna to Devil Canyon) and 1 inch = 2,000 feet
for the Lower River (Cook Inlet to Devil Canyon) with a 60 percent
overlap between adjacent photos. Baseline photogr·aphs of the
Middle River for river discharge (as measured at the USGS Gold
Creek gaging station) ranging from 5,100 through 23,000 have
already been taken (Table 4).
In addition, photos for the Lower River have been taken for vari.ous
ranges from 13,900 to 75,200 cfs (measured at the USGS Sunshine
gaging station) (Table 5).
Prior to project operation, overflights of the Middle River and
Lower River will be taken at approximately 12,000 cfs and 35,000
cfs, respectively. The reason for these specific flows is that
they are relatively low, allowing definition of many of the
macrohabitat s. These wi 11 be used for comparison to previous
48
Table 4.
SUSITNA HYDROELECTRIC PROJECT
DATES &~D MAINSTEM DISCHARGES AT WHICH AERIAL
PHOTOGRAPHY OF THE MIDDLE SUSITNA RIVER WAS OBTAINED.
Date Discharge (cfs)
6-1-82 23,000
8-24-80 18,000
9-11-83 16,0(0
9-6-83 12,500
9-9-84 H>: 600
10-4-84 7,400
10-14-84 5,100
Source: APA 1985
431007/TBL
TABLE 5.
SUSITNA HYDROELECTRIC PROJECT
DATES AND DISCHARGE AT WHICH AERIAL PHOTOGRAPHY WAS OBTAINED
Discharge
Date at Sunshine
8-27-84 75;200 cfs
8-27-83 59,100 cfs
9-6-83 36,600 cfs
9-16-83 21,100 cfs
10-25-83 13,900 cfs
Source: APA 1985
431007/TBL
photos and to document conditions immediately before impoundment.
Similar sets of phot0s will be taken periodically during project
operation to continue the documentation and comparison process. If
macrohabitat changes are found to be minimal, the oeriod between
overflights will be extended or the overflights discontinued.
iii. Schedule
Existing photos have already been taken (Tables 4 and 5).
Additional pre-project photos will be take~ one year before initial
operation. Approximately every five years afcer impoundment,
additional photos will be taken. After each series, the need for
further overflights will be reviewed.
2.4.1.3 Data Handling
i. Field Data
Field data will be collected by a commercial aerial photography
firm. Their data must include information on date of overflight,
time, altitudes, flight lines, participants, and any notes.
,.
Stream discharges will be monitored prior to flights to assure that
photos are taken at similar flows.
ii. Data Transfer
431007
860303
Photos will be deYeloped in Anchorage by the commercial firm~ The
firm wi 11 retain origina 1 negatives and wi 11 send to the Power
Authority, a copy of the negatives and two sets of prints ~ach for
t:he I . .>wer River and Middle River overflights. The Power Authority
will archive the negatives ~md one set of prints and will store the
other set of prints in an active file.
49
iii. Data Analysis
431007
860303
The photographs will primarily be used for qualitative assessments
of macrohabitat changes. They will be available in the event that
more detailed quantitative analyses are needed. Following the
examination of each set of photos, a technical memorandum will be
written which describes any important features or changes that have
occurred from previous photos. Particular attention will be given
to any obvious changes in macrohabitat (especially if they may
affect mitigation measures such as protective berms for s laughs).
If other monitoring shows that the aquatic system has been
significantly impacted by the dam, further and more detailed
analyses of the macrohabitat may then be warranted.
50
2.4.2 Slough Modifications
2.4.2.1 Program Description
~. Objectiv~
Various features incorporated into slough habitat modification will
be monitored to determine if access for adult salmon is unhindered,
and that suitable spawning conditions exist.
ii. Rati0nale
The Alaska Power Authority has proposed specific structural
modifications for several Middle Susitna River sloughs that are
utilized by adult salmon for spawn~ng. The purpose of these
modifications is to provide fish habitat at existing or higher
levels of production under with~project conditionsB The
modifications must be monitored to ensure that they are meeting
their intended function.
iii. Program Design
431007
860303
Protective berms constructed at the heads of sloughs will be
inspected to identify and implement needed .
repa~rs. Features
designed to facilitate adult access into sloughs will also be
inspected. Modif~cations designed to maintain spawning areas will
be inspected to ensure the area contains suitable spawning
conditions. Water temperature and flow will be monitored to ensure
conditions are favorable for egg survival.
51
2.4.2.2 Data Collection
i. Methods
431007
860303
Berms - A visual inspection of each protective berm is to be
performed annually. The structure's integrity, including signs of
eros1on, scouring, overtopping, or undermining, is of primary
concern.
Access Structures -Structures designed to maintain or enhance
access of adult salmon into sloughs are to be inspected visually
for signs of erosion, undermining, misaltgnment, or feilure~ Water
depths across the upper:-middle, and lower sections of critical
passage reaches are to be measured by stretching a meter tape from
bank to bank above the wat~r surface at each site and reading the
depth every 0.5m with d stadia rod.
Spawnin& Conditions During the first 5 years following
modification, the distribution and abundance of spawning adult
salmon and the number of outmigrating juvenile salmon will be the
most useful measure of habitat conditions in modified sloughs (see
Section 2 .3). Prior to each spawning season a foot-survey and
subjective evaluation of habitat conditions in each modified slough
is to be completed. The evaluation centers on the quality of
spawning gravels (visual estimate of composition), estimated water
velocity and depth measurements, and the presence of upwelling
groundwater. Structures in~talled to maintain depths, to control
velocities, and to retain gravels are to be inspected for signs of
~rosion, undermining, defect, and failure.
Sloughs undergoing modifications are to be monitored for changes in
flow and temperature. Staff gages are to be installed in each
sl•.::mgh and stage-discharge relationships developed following
52
431007
860303
modification. Continuous recording thermographs are to be
installed in each slough for use throughout the spawn~ng and
incubation periods.
Identification of any deficiency in structural modifications of
spawning sloughs may trigger more extensive studies of such
parameters as gravel quantity and quality, water quantity and
quality, habitat availability, and the incubation environmentA
53
4.0 Reporting
Analyses of all field data will be on an annual basis (January -December)
and will be completed by ::anuary 15 of the succeeding year so that the data
may be incorporated into the Power Authority's annual report to the Federal
Energy Regulatory Commission and to the resource agencies. The Power
Authority will provide this final 'report by March J of the year following
data collection.
Data on water quantity is normally collected on the basis of the 11 water
year" (October 1 to September 30). In order to maintain continuity with
other monitoring programs, water quantity data will also be reported on a
calendar year basis. This should not create undue hardship, since such data
will be summarized on a weekly basis for project operation.
431007
860303
54
5.0 Contingencies
Although the results of the long-term monitoring program will be reviewed on
an annual basis, there may be unforeseen instances when either additiona 1
monitoring or a change in on-going monitoring may need to be initiated on
short-term notice. In these cases, the Alaska Power Authority's Director of
Environment and Licensing (DEL) will notify the appropriate agency or
agencies, the situation will be discussed, and action agreed upon will be
taken. If such occurrences are first observed by personnel of the resource
agenc1es, such agencies should notify the DEL and request a meeting to
address the situation.
The long-term monitoring manual has been designed as a three-ring binder so
t.hat when additions or alterations in the long-term monitoring plan occur,
they are to be documented and placed in the manual. Copies of such changes
are to be distributed to all agencies and individuals possessing copies of
the manual. A list of those receiving the manual is to be kept w1th the
master manual copy on file at the office of the DEL.
431007
860303
55
REFERENCES
6 .. 0 REFERENCES
Alaska Power Authority. 1985. Preconsultation Package.
American Public Health Association. 1980. Standard Hethods for Water and
Wastewater.
EPA. 1983.Methods for Chemical Analyses of Watar and Wastes, U.S.
Environmental Pro' action Agency, Cincinnati~ Ohio, 1979. EPA
600/4-79-020 Revised March 1983
USGS. 1969. Techniques of Watar Resources Investigations.
Laboratory Theory for Sediment Analysis.
431282
850303
56
Book 5 , Ch • 1 :