Loading...
HomeMy WebLinkAboutAPA3426I I - \ BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION APPLICATION FOR LICENSE FOR MAJOR PROJECT SUSITNA HYDROELECTRIC PROJECT DRAFT LICENSE APPLICATION VOLUME 2 EXHIBIT B PROJECT OPERATION AND RESOURCE UTILIZATION ARLIS Alaska Resources Library &Infonnatlon ServICes Anchorage,Alaska November 1985 l"t< t42.5 ..S 5S ;:.47{ fLo."3'12.( i I \ n .\\ "'\~) ,'1 ' '} ,"'1 ,·,rl,· } ~J ] j ''\ 1 ,j J ;1 'J I I .I .J NOTICE 1 ) 1 -J ) A NOTATIONAL SYSTEM HAS BEEN USED TO DENOTE DIFFERENCES BETWEEN THIS AMENDED LICENSE APPLICATION AND THE LICENSE APPLICATION AS ACCEPTED FOR FILING BY FERC ON JULY 29,1983 This system consists of placing one of the following notations beside each text heading: (0)No change was made in this section,it remains the same as was presented in the July 29,1983 License Application (*).Only minor changes,largely of an editorial nature,have been made (**)Major changes have been made in this section (***)This is an entirely new section which did not appear in the July 29,1983 License Application J 1 1 1 ,I ; } 1 1·1 "J 'J ,'1 ,/ ] J, \ j 'I r 1 J 1- I ' : VOLUME COMPARISON VOLUME NUMBER COMPARISON LICENSE APPLICATION AMENDMENT VS.JULy 29,1983 EXHIBIT A CHAPTER Entire DESCRIPTION Project Description LICENSE APPLICATION JULy 29,1983 AMENDMENT APPLICATION VOLUME NO.VOLUME NO. 1 1 B C D Entire App.Bl App.B2 App.B3 Entire Entire App.Dl Project Operation and Resource Utilization MAP Model Documentation Report RED Model Documentation Report RED Model Update Proposed Construction Schedule Project Costs and Financing Fuels Pricing 2 3 4 4 5 5 5 2 &2A 2B 2C 1 1 1 E 1 2 Tables Figures Figures 3 General Description of Locale 6 Water Use and Quality 6 7 8 Fish,Wildlife and Botanical 9 Resources (Sect.1 and 2) Fish,Wildlife and Botanical 10 Resources (Sect.3) 5A 5A 5A 5B 5B 6A 6B 6A 6B Fish,Wildlife and Botanical Resources (Sect.4,5,6,&7) 11 6A 6B Socioeconomic Impacts Geological and Soil Resources 4 5 6 Historic &Archaeological Resources 12 12 12 7 7 7 Project Design Plates 15 Supporting Design Report 16 Project Limits and Land Ownership 17 Plates r--- !len ,1.0co.......q,..q :0iOo 11.0 1.0 I I'.('1) ('I) F F G 7 8 9 10 11 Entire Entire Entire Recreational Resources Aesthetic Resources Land Use Alternative Locations,Designs and Energy Sources Agency Consultation 13 13 13 14 14 8 8 8 9 lOA lOB 3 4 J ] 1 1 1 ] l ( ..l , 1 I 1 I , 1 j j ] 1 ,j SUMMARY TABLE OF CONTENTS SUSITNA HYDROELECTRIC PROJECT LICENSE APPLICATION SUMMARY TABLE OF CONTENTS EXHIBIT A PROJECT DESCRIPTION Title 1 -PROJECT STRUCTURES -WATANA STAGE I (**)••...·.. Page No. A-1-2 • ••o.• 1.1 -General Arrangement (**)•• 1.2 -Dam Embankment (**)••••• 1.3 -Diversion (**)••••••••• 1.4 -Emergency Release Facilities (**) 1.5 -Outlet Facilities (**)•••• 1.6 -Spillway (**)••••••••• 1.7 -This section deleted ••••• 1.8 -Power Intake (**)•••••• 1.9 -Power Tunnels and Penstocks (**)••• 1.10 -Powerhouse (**)• • • • • 1.11 -Tailrace (**)•••••••••••••• 1.12 -Main Access Plan (**) 1.13 -Site Facilities (**). 1.14 Relict Channel (***)•.•••••• A-1-2 A-1-4 A-1-6 A-1-9 A-1-10 A-l-13 A-I-15 A-1-15 A-1-18 A-1-19 A-1-22 A-1-23 A-1-25 A-1-29 2 -RESERVOIR DATA -WATANA STAGE I (**)••·..·.·..A-2-1 3 -TURBINES AND GENERATORS -WATANA STAGE I (**) 3.1 -Unit Capacity (**)• 3.2 -Turbines (***)•••• 3.3 -Generators (**) 3.4 -Governor System (0) . . . .. o • • • • • • • ·.' • 0 • • • .... A-3-I A-3-1 A-3-1 A-3-1 A-3-3 4 -APPURTENANT MECHANICAL AND ELECTRICAL EQUIPMENT - WATANA STAGE I (**>'• • • • • • • • • • • • • • • •..A-4-1 4.1 -Miscellaneous Mechanical Equipment (**).". 4.2 -Accessory Electrical Equipment (**)•••• 4.3 -SF6 Gas-Insulated 345 kV Substation (GIS)(***) A-4-1 A-4-5 A-4-12 5 -TRANSMISSION FACILITIES FOR WATANA STAGE I (0)• •• ••A-5-1 5.1 -Transmission Requirements (0) 5.2 -Description of Facilities (0) 5.3 -Construction Staging (0)••• .. . A-5-1 A-5-1 A-5-11 851014 i SUMMARY TABLE OF CONTENTS (cont'd) 8.1 -Unit Capacity (**).· · · · ·•·A-8-1 8.2 -Turbines (**)·· · ·A-8-1 8.3 Generators (0). . . . . .···. .· · .·.A-8-1 8.4 -Governor System (0). .•· ··•· ··A-8-2 1 I 1 1 I 1 I l I 1 l ·1 1 l A-9-1 A-6-1 A-6-1 A-6-2 A-6-4 A-6-6 A-6-8 A-6-10 A-6-12 A-7-1 A-6-12 A-6-13 .1\-'6-14 A-6-17 A-6-17 A-6-18 Page No. • • ·.. •._0 • o • • • • · . ... . . . •0 ••.•..•. • ••••• • • • • EXHIBIT A PROJECT DESCRIPTION 6.1 -General Arrangement (**) 6.2 -Arch Dam (**)••••. 6.3 -Saddle Dam (**)•••• 6.4 -Diversion (**)• 6.5 -Outlet Facilities (**)••..•••••• 6.6 -Spillway (**)•••• 6.7 -Emergency Spillway ••• (This section deleted) 6.8 -Power Facilities (*)• . . • • • • • ••• 6.9 -Penstocks (**)• • • • ••••• 6.10 -'Powerhouse arid R.elated structures (**}••••. 6.11 -Tailrace Tunnel (*)• ••••••••• 6.12 -Access Plan (**)•••.••••••• 6.13 -Site Facilities (*)•••••• 9 -APPURTENANT EQUIPMENT -DEVIL CANYON STAGE II (0). Title 7 -DEVIL CANYON RESERVOIR STAGE II (*) 6 -PROJECT STRUCTURES -DEVIL CANYON STAGE II (**) ··__·_·_-_·······__··---·9·.-1-··_·-Mi-s·~el·laneaus-Me~ha·n-i~al-Equi-pment--Ea1-..-.-.-.--.-.-A-9-1--- 9.2 -Accessory Electrical Equipment (0)••• • •A-9-3 9.3 -Switchyard Structures and Equipment (0).• •A-9-6 11 -PROJECT STRUCTURES -WATANA STAGE III <***)0 • • • A...,ll-1 11-1 A-1l-3 A-1l-5 A-U-6 A-1O-1•• •• • • ii c:.lL1 -GeneraI·ArrangemeriF{***}: 11.2 -Dam Embankment (***)• • • • •••• 11.3 -Diversion (***)••••••••.••••• 11.4 -Emergency Release Facilities (***)•••• 10 -TRANSMISSION LINES -DEVIL CANYON STAGE II (**) 851014 SUMMARY TABLE OF CONTENTS (cont'd) EXHIBIT A PROJECT DESCRIPTION Title Page No. 11.5 -Outlet Facilities (***)·····A-1l-6 11.6 -Spillway (***).····A-1l-7 II.7 - Power Intake (***)· ··· · · .···.· · · · A-U-8 11.8 ~Power Tunnel and Penstocks (***)·A-ll-ll II.9 - Powerhouse (***)··········A-ll-ll 11.10 -Trailrace (***)· · ··A-11-13 11.11 -Access Plan (***)· · ·· · · · ·A-ll-13 11.12 -Site Facilities (***)··.A-ll-13 11.13 -Relict Channel.(***)····A-ll-13 12 -RESERVOIR DATA -WATANA STAGE III (***)••••·•••A-12-1 · . . 13 -TURBINES AND GENERATORS -WATANA STAGE III (***) 13.1 -Unit Capacity (***)•••• • 13.2 -Turbines (***)••• 13.3 -Generators (***) 13.4 -Governor System (***)••• 14 -APPURTENANT MECHANICAL AND ELECTRICAL EQUIPMENT - WATANA STAGE III (***)•••••••••••••• ·. • • A-13-1 A-13-1 A-13-1 A-13-1 A-13-1 A-14-1 14.1 -Miscellaneous Mechanical Equipment (***)•A-14-1 14.2 -Accessory Electrical Equipment (***)• . • • • •A-14-1 15 -TRANSMISSION FACILITIES -WATANA STAGE III (***) 15.1 Transmission Requirements (***)• 15.2 Switching and Substations (***)• 00.A-15-1 A-15-1 A-15-1 16 -LANDS OF THE UNITED STATES (**)• •G •e _ • • • •0 A-16-1 17 -REFERENCES 851014 • • • • • • • • • • • • • • • • • 0 0 • • • iii A-17-1 SUMMARY TABLE OF CONTENTS (cont I d) I ) I ] I l t 1 ,I. B-l-l B-2-l B-2-1 B-2-1 B-2-22 B-2-48 B-1-12 B-1-17 B-l-l B-1-4 B-1-5 Page No. • • • • • ...~.o 0 COl 0o..e EXHIBIT B PROJECT OPERATION AND RESOURCE UTILIZATION 1.1 -Previous Studies (***)• • • • • • • 1.2 -Plan Formulation and Selection Methodology (***). 1.3 -Damsite Selection (***). 1.4 -Formulation of Susitna Basin Development Plans (***)• • • • • • • • • •... 1.5 -Evaluation of Basin Development Plans (***) ,-'2.1 S1.1si tna 'Hydt6electticDevel6pmenE ''(*'**)-- 2.2 -Watana Project Formulation (***).• • • • • • 2.3 -Selection of Watana General Arrangement (***)•• 2.4 -Devil Canyon Project Formulation (***)•••••• 2.5 -Selection of Devil Canyon General Arrang eme l1 t (***)..• • • • • • • • • • •B-2-60 Selection of Access Road Corridor (*~)B-2-67 "Selec'tionof 'rransmi-ssiori.-FaciTitfes-(***)-.-:-"':-:-:=B:'2:'S3 -Selection of Project Operation (***)B-2-131 2 -ALTERNATIVE FACILITY DESIGN,PROCESSES AND OPERATIONS (**'*).....0 ..• ••••• • Title 1 -DAMSITE SELECTION (***)..0 e • 2.6 - -----2-.7 2.8 ..,--------------4-----POWER-AND-ENERGY--PRODUC!f.ION-{-***}-..-.-.-.-.--.--.-.--.-.-.--B-4-1---- 4.1 -Plant and System Operation Requirements (***) 4.2 -Power and Energy Production (***)• • • 5.1 -Introduction (***). 5.2 -Description of the RailbeltE:lectricSystems C***) 5.3 -Forecasting Methodology (***)•••••• 5.4 -Forecast of Electric Power Demand (***) •0 • • ••• • • • • •e 0 0 • •0 •.0. j 1 I I !I r J B-3-1 B-5-1 B-3-1 B-3-6 B-3-20 B-7-1 B-6-1 B-4-1 B-4-10 B-5-1 B-5-1 B-5-17 B-5-47 .... . .. .. • •• • o 0 0 0 ••• • •••• •••• 3.1 -Hydrology (***)• • • • • • • •..• • • 3.2 -Reservoir Operation Modeling (***)•••• 3.3 -Operational Flow Regime Selection (***) FUTURE SUSITNA BASIN DEVELOPMENT (***) 3 -DESCRIPTION OF PROJECT OPERATION (***) 6 5 -STATEMENT OF POWER NEEDS AND UTILIZATION (***) 7 -REFERENCES 851014 ') ) SUMMARY TABLE OF CONTENTS (cont'd) EXHIBIT B -APPENDIX BI MAN-IN-THE-ARCTIC PROGRAM (MAP) TECHNICAL DOCUMENTATION REPORT STAGE MODEL (VERSION A8S.I) REGIONALIZATION MODEL (VERSION A84.CD) SCENARIO GENERATOR Title Stage Model 1.Introduction ..··· · ·· · · ··· · ·· ·2.Economic Module Description · ···3.Fiscal Module Description · · · ·· · ·4.Demographic Module Description ·· ·· · ·· · · ·5.Input variables · · · ·· · · · ·..·· ·6.Variable and Parameter Name Conventions · · · ·7.Parameter Values,Defini tions and Sources · · · ·· ·8.Model validation and Properties ·· · · ·· · · ···9.Input Data Sources ·· · · .....· · ····10.Programs for Model Use ·· ·· · ··· · · ···11.Model Adjustments for Simulation ···· ···· · I )12.Key.to Regressions ··· · ·I J 13.Input Data Archives · · ··· ·· · · · · Regionalization Model Page No. 1-1 2-1 3-1 4-1 5-1 6-1 7-1 8-1 9-1 10-1 11-1 12-1 13-1 1.Model Description · ·····1 2.Flow Diagram · · ·· · 5 3.Model Inputs . .··· ·· · 7 4.Variable and Parameter Names ··· · · · 9 5.Parameter Values ·· ··· · ·· ··· · · · 13 6.Model Validation ··· · ·· · · · ·· · 31 7.Programs for Model ····· · ·· · ·· · · ·38 8.Model Listing ··· · 39 9.Model Parameters ·· ···· · ·· · · ···57 10.Exogenous,Policy,and Startup Values 61 Scenario Generator Introduction • • • • • • • • • • • • • • 1.Organization of the Library Archives •••• 2.Using the Scenario Generator ••••••• 3.Creating,Manipulating,Examining,and pri nting Library Files •••••• • • • • 4.Model Output ••••••••••• 1 1 8 14 22 851014 v SUMMARY TABLE OF CONTENTS (cont'd) EXHIBIT B -APPENDIX B2 RAILBELT ELECTRICITY DEMAND (RED)MODEL TECHNICAL DOCUMENTATION REPORT (i983 VERSION) 7 -PRICE ELASTICITY.--.....-.••• 5 -THE RESIDENTIAL CONSUMPTION MODULE • 7-.1 ! -1 1 Page No.-I 1.1 I 2.1 3.1 I 4.1 il1 5.1 601 ( .-...~-.--.:-0 .0. o 00.•00. e 0 0 0 • 0 • • • • •e • • • •eo.0 0 • . . . 1 -INTRODUCTION • 3 -UNCERTAINTY MODULE • Title 2 -OVERVIEW • • 6 -THE BUSINESS CONSUMPTION MODULE 4 -THE HOUSING MODULE • • 8 -THE PROGRAM-INDUCED CONSERVATION MODULE • • 0 • • • • • • • • • 0 10.1 12.1 13.1 11.1 8.1 9.1. . . • • 0 0 0 • • . . . . o 0 . . .. .. .. ... vi 10 -LARGE INDUSTRIAL DEMAND 11 -THE PEAK DEMAND MODULE 12 -MODEL VALIDATION 13 -MISCELLANEOUS TABLES 9 -THE MISCELLANEOUS MODULE 851014 SUMMARY TABLE OF CONTENTS (cont'd) EXHIBIT B -APPENDIX B3 RAILBELT ELECTRICITY DEMAND (RED)MODEL CHANGES MADE JULY 1983 TO AUGUST 1985 2 -RED MODEL PRICE ADJUSTMENT REVISIONS 3 -RESIDENTIAL CONSUMPTION MODULE 6 -EFFECT OF THE MODEL CHANGES ON THE FORECASTS Title 1 -INTRODUCTION 4 -BUSINESS SECTOR 5 -PEAK DEMAND 851014 ..... . .. vii Page No. 1.1 2.1 3.1 4.1 5.1 6.1 SUMMARY TABLE OF CONTENTS (cont'd) 1.1 -Access (*)... .. .·1.Z Site Facilities (**)·· · · ··· ··1.3 -Diversion (**)·· · · ···1.4 -Dam Embankment (**)'.·· · ·· ·· ··1.5 -Spillway and'Intakes (**)··· ·1.6 -Powerhouse and Other Underground Works (**)·1.7 -Relict Channel (**).···· · ··· ·· · ·1.8 -Transmission Lines/Switchyards (*)·· ·1.9 -General (**). . . ,;·· ·· · ·· ·· 2 ...DEVIL CANYON STAGE II SCHEDULE (**)•••• •• • ..• • EXHIBIT C PROPOSED CONSTRUCTION SCHEDULE .] ] J j .J ~J j j C-2 ....1 C-I-Z C-I-Z C-I-2 C-I-2 C-I-3 C-I-3 C-I-3 C-I-3 C-I-3 C-l-1 C-2-1 C-Z-1 C-Z-1 C-2-1 C-2-Z <::";'-1'=-2" C-Z-Z C-Z-Z Page No. •e e ·.. •e f)•e • · . .., ·......... ·. Z.1 -Access (**)••••••••••••• 2.Z -Site Facilities (**)••• Z.3 -Diversion (*)• Z.4 -Arch Dam (**)• 2.5 -Spillway and Intake (*) "Z-;;6 .;;';p'owernouse -and OElierUnae-rgroundWorKs~~(or· Z.7 -Transmission Lines/Switchyards (*)•••• Z.8 -General (*)• • • • • • • • • • • 1 -WATANA STAGE I SCHEDULE (**) Title 3.1 -Access (***)•••••••••••••C-3-1 3.Z -Site Facilities (***)• • • • • • • •••C-3-1 -..--------·---,---3.-3 ---Dam--Embankment··(-***}•-,;....-.-..•.-.-.---;-..'C--3-1 .....-~~._~.-~..-..~----....-3..4-""---Spil.l.wa:y-and-Intakes..-(.***.).~.·~.-.·-.-·.~-.~·.~·.·~.-·····.-..-.·-·~·G-3-2--..-..---..-.-.-... 3.5 -Powerhouse and Other Underground Works (**)C-3-2 3.6 -Relict Channel (***)•••••••••C-3-Z 3.7 -Transmission Lines/Switchyards (***)••••C-3-Z 3.8 -General (***)• • • ••.•• • •• •C-3-Z viii • • • • • 0 0 • • • 3 -WATANA STAGE III SCHEDULE (***)• 4 -EXISTING TRANSMISSION SYSTEM (***) 851014 • • •••• •·..••C-3-1 C-4-1 I i J I I I I .I I SUMMARY TABLE OF CONTENTS (cont'd) EmIBIT D PROJECT COSTS AND FINANCING Title Page No. 1 -ESTIMATES OF COST (**)• • • • • • 0 eo.• •G • • •D-1-1 1.1 -Construction Costs (**)•••••••.••• 1.2 -Mitigation Costs (**)• 1.3 -Engineering and Administration Costs (*)•••• 1.4 -Operation,Maintenance and Replacement Costs (**) 1.5 -Allowance for Funds Used During Construction (AFDC)(**)••••••••• 1.6 -Escalation (**)• •.'• • • • • • • • • • • 1.7 -Cash Flow and Manpower Loading Requirements (**). 1.8 -Contingency (*)•.••••••••••••• 1~9 -Previously Constructed Project Facilities (*) D-1-1 D-1-6 D-1-7 D-1-10 D-1-11 D-1-12 D-1-12 D-1-13 D-1-13 2 -EVALUATION OF ALTERNATIVE EXPANSION PLANS (***)•...D-2-1 2.1 -General (***)••••••••••• 2.2 -Hydroelectric Alternatives (***)•••• 2.3 -Thermal Alternatives (***) 2.4 -Natural Gas-Fired Options (***)• 2.5 -Coal-Fired Options (***)•••••• 2.6 -The Existing Railbelt Systems (***)•••••.• 2.7 -Generation Expansion Before 1996 (***) 2.8 -Formulation of Expansion Plans Beginning in 1996 (***)••••••••••••• 2.9 Selection of Expansion Plans (***)••••• 2.10 -Economic Development (***)•••••• 2.11 -Sensitivity Analysis (***)•••••••• 2.12 -Conclusions (***)••••••• D-2-1 D-2-1 D-2-10 D-2-10 D-2-19 D-2-24 D-2-27 D-2-28 D-2-33 D-2-39 D-2-44 D-2-46 3 -CONSEQUENCES OF LICENSE DENIAL (***)......D-3-1 3.1 -Statement and Evaluation of the Consequences of License Denial (***). 3.2 -Future Use of the Damsites if the License is Denied (***)• • • • • • 4 -FINANCING (***)• • • • • • • • • • • • • • • 4.1 -General Approach and Procedures (***)• 4.2 -Financing Plan (***)•••••••• 4.3 -Annual Costs (***)•••••••••• •••• • D-3-1 D-3-1 D-4-1 D-4-1 D-4-1 D-4-3 851014 ix SUMMARY TABLE··OF CONTENTS (cont f d) EXHIBIT D PROJECT COSTS AND FINANCING Title 4.4 -Market Value of Power (***)• • 4.5 -Rate Stabilization (***) 4.6 -Sensitivity of Analyses (***) •0 0 _ • • • • 0 Page No. D-4-4 D-4-4 D-4-4 ! 1 J l I 5 -REFERENCES (***) 851014 e-• • • • •0 • • • • • • • •D • • • x D-5-1 , 1 .~ :1 1 I j 1 j I I 1 ] l SUMMARY TABLE OF CONTENTS (cont'd) EXHIBIT D -APPENDIX D1 FUELS PRICING o • • • • • ••0 ~eo.•0 e _0 Title 1 -INTRODUCTION (***) 2 -WORLD OIL PRICE (***)• • •• • 0 • 0 • •eo..... Page No. Dl-l-l Dl-2-1 . . 2.1 -The Sherman H.Clark Associates Forecast (***) 2.2 -The Composite Oil Price Forecast (***) 2.3 -The Wharton Forecast (***)•••• Dl-2-1 Dl-2-2 Dl-2-5 3 -NATURAL GAS (***)•0 •••....o G • •G.• • • • • •Dl-3-1 3.1 -Cook Inlet Gas Prices (***)•Dl-3-1 3.2 -Regulatory Constraints on the Availability of Natural Gas (***)• • • • • • • • • • • • •Dl-3-10 3.3 -Physical Constraints on the Availability of Cook Inlet Natural Gas Supply (***)••• ••Dl-3-12 3.4 -North Slope Natural Gas (***)•Dl-3-20 . . 4 -COAL (***) 4.1 4.2 4.3 4.4 ..... ........ ........ -Resources and Reserves (***) -Demand and Supply (***)• • • ••••• -Present and Potential Alaska Coal Prices (***) -Alaska Coal Prices Summarized (***)• .'Dl-4-l Dl-4-1 Dl-4-3 Dl-4-4 Dl-4-10 • • •• •• ••••• ••••••5 -DISTILLATE OIL (***) 5.1 -Availability (***)•••• 5.2 -Distillate Price (***) . ... . Dl-5-1 Dl-5-1 Dl-5-1 6 -REFERENCES 851014 .... .................. xi Dl-6-1 SUMMARY TABLE OF CONTENTS (cont'd) -----~.._---~~.._~.._._--~~---_...--~-_._._.~---.~-~.._-~--~-~--~----~-~~----_.------_.~---_._---~---_.~--_.---.•.__.~.. •• 0 • • •e 0 eo.0 e •e c •e e eo. EXHIBIT E -CHAPTER 1 GENERAL DESCRIPTION OF THE LOCALE j ] 'J 1 j l ..j l .\ I I J j I I 1 l Page No. E-I-I-I E-I-3-1 E-I-2-1 E-I-I-I E..;,I-I..;,2 .... o 0 e 0 • •e <0 0•• o 0 0 Gee 0 • "e 0 e ••0 • • D •0 •e •.,.0. 1.1 -General Setting (**) 1.2 -Susitna Basin (*) 3 -GLOSSARY • • 1 -GENERAL DESCRIPTION (*)•• Title 2 -REFERENCES 1 -) xii .. SUMMARY TABLE OF CONTENTS (conttd)· EXHIBIT E -CHAPTER 2 WATER USE AND QUALITY Title Page No. I -INTRODUCTION (**)• • • •o • • • • ••• • • o ..• •e E-2-1-1 1 I 2 -BASELINE DESCRIPTION (**)•..•co • • • • •·•·E-2-2-1 2.1 -Susitna River Morphology (**)· ··E-2-2-3 2.2 -Susitna River Water Quantity (**)E-2-2-12 2.3 -Susitna River Water Quality (**)•· · .•··E-2-2-19 2.4 -Baseline Ground Water Conditions (**)··..E-2-2-46 2.5 -Existing Lakes,Reservoirs,and Streams (**)E-2-2-49 2.6 -Existing Instream Flow Uses (0)E-2-2-50 2.7 -Access Plan (**),E-2-2-63...·2.8 -Transmission Corridor (**)..·E-2-2-64 3 -OPERATIONAL FLOW REGIME SELECTION (***)•• ••co ·...E-2-3-1 3.1 -Project Reservoir Characteristics (***) 3.2 -Reservoir Operation Modeling (***).. 3.3 -Development of Alternative Environmental Flow Cases (***)••••••••••••• 3.4 -Detailed Discussion of Flow Cases (***).• 3.5 -Comparison of Alternative Flow Regimes (***). 3.6 -Other Constraints on Project Operation (***) 3.7 -Power and Energy Production (***)••••• ~4 -PROJECT IMPACT ON WATER QUALITY AND QUANTITY (**)co ..co E-2-3-1 E-2-3-2 E-2-3-6 E-2-3-17 E-2-3-37 E-2-3-43 E-2-3-53 E-2-4-1 4.1 -Watana Development (**)•••••• 4.2 -Devil Canyon Development (**)••• 4.3 -Watana Stage III Development (***). 4.4 -Access Plan (**)•••••• 5 -AGENCY CONCERNS AND RECOMMENDATIONS (**) ·. . ·...... E-2-4-7 E-2-4-110 E-2-4-160 E-2-4-211 E-2-5-1 6 -MITIGATION,ENHANCEMENT,AND PROTECTIVE MEASURES (**)• 6.1 -Introduction (*)••••••••••••..•• 6.2 -Mitigation -Watana Stage I -Construction (**) 6°.3 -Mitigation -Watana Stage I -Impoundment (**). E-2-6-1 E-2-6-1 E-2-6-1 E-2-6-5 851014 xiii Title SUMMARY TABLE OF CONTENTS (cont'd) EXHIBIT E -CHAPTER 2 WATER USE AND QUALITY 6.4 -Watana Stage I Operation (**)• • • • • • • • 6.5 -Mitigation -Devil Canyon Stage II - Construction (**)• • • • • • • • 6.6 -Mitigation -Devil Canyon Stage II - Impoundment (**)•••••••• • • • • • 6.7 -Mitigation -Devil Canyon/Watana Operation (**)• 6.8 -Mitigation -Watana Stage III - Construction (***)•••••••••• 6.9 -Mitigation -WataUa Stage III- Impoundment/Construction (***)••• 6 ..10 -Mitigation -Stage III Operation (***)••••• 6.11 -Access Road and Transmission Lines (***)•••• I j 1 1 J 1 1 i '--1 'I Page No. E-2-6-7 E-2-6-13 E-2-6-15 E-2-7-1 E-2-6-13 E-2-6-13 E-2-8-1 E-2-6-16 E-2-6-16 E-2-6-18 ....tI • • • •e • •tI •tI.,....••• •eo.• • •~•0 eo.•0 • • •e • • • • 7 -REFERENCES " • 8 -GLOSSARY 851014 I I j I 1 ,I 1 j SUMMARY TABLE OF CONTENTS (cant'd) EXHIBIT E -CHAPTER 3 FISH,WILDLIFE,AND BOTANICAL RESOURCES Title Page No. 1 -INTRODUCTION (0)E-3-1-1 1.1 -Baseline Descriptions (0) 1.2 -Impact Assessments (*)•• 1.3 -Mitigation Plans (*)•• E-3-1-1 E-3-1-1 E-3-1-3 2 -FISH RESOURCES OF THE SUSITNA RIVER DRAINAGE (**)o'J 0 0 · . I]2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 -Overview of the Resources (**>•••• -Species Biology and Habitat Utilization in the Susitna River Drainage (*)••••.• -Anticipated Impacts To Aquatic Habitat (**) -Mitigation Issues and Mitigating Measures (**) -Aquatic Studies Program (*)• •••• • -Monitoring Studies (**)•••••••"'••• -Cost of Mi tigation (***)•••••••• -Agency'Consultation on Fisheries Mitigation Measures (**)• • • • • • • • • • • • • E-3-2-1 E-3-2-1 E-3-2-14 E-3-2-104 E-3-2-244 E-3-2-279 E-3-2-280 E-3-2-303 E-3-2-304 3 -BOTANICAL RESOURCES (**)·........'......E-3-3-1 3.1 -Introduction (*)····3.2 -Baseline Description (**)··.···3.3 -Impacts (**)..· · · .·3.4 -Mitigation Plan (**)····· 4 -WILDLIFE (**)..•.• • • •••••.•.•••• • • E-3-3-1 E-3-3-6 E-3-3-34 E-3-3-63 E-3-4:-1 4.1 -Introduction (*)•••• 4.2 -Baseline Description (**)• • 4.3 -Impacts (*).•••••.•• 4.4 Mitigation Plan (**) ·. . · . . . . . E-3-4-1 E-3-4-3 E-3-4-110 E-3-4-248 5 -AIR QUALITY/METEOROLOGY (***)•............E-3-5-1 ·. . 5.1 -Introduction (***)••••••••••••• 5.2 -Existing Conditions (***)•••••• 5.3 -Expected Air Pollutant Emissions (***). 5.4 -Predicted Air Quality Impacts (***)•• E-3-5-1 E-3-5-1 E-3-5-2 E-3-5-3 851014 xv SUMMARY TABLE OF CONTENTS (cant'd) J ] ,1 I .j I ] .j .'.J J ] ] I 1 } ] ,I J j E-3-7-1 E-3-6-1 E-3-5-3 Page No. .........••.......... METHODS USED TO DETERMINE MOOSE BROWSE UTILIZATION AND CARRYING CAPACITY WITHIN THE MIDDLE SUSITNA BASIN STATUS,HABITAT USE AND RELATIVE ABUNDANCE OF BIRD SPECIES IN THE MIDDLE SUSITNABASIN EXISTING AIR QUALITY AND METEOROLOGICAL CONDITIONS EXJ?I..ANATI()NA.l@ JUS'I'I:Fr.CA.1JQN:.O:F.,A.~'I'.I::F1CIA.I..:N~$T MITIGATION (THIS SECTION HAS BEEN ,DELETED) FISH AND WILDLIFE MITIGATION POLIC~ PERSONAL COMMUNICATIONS (THIS SECTION HAS BEEN DELETED) • •eo.G •0 • • • • • • • ••• ••0 •0 • • 5.5 -Regulatory Agency Consultations (***)•• EXHIBIT E -CHAPTER 3 FISH,WILDLIFE,AND BOTANICAL RESOURCES E1.3 7 -GLOSSARY E6.3 Title E8.3 E3.3 E4.3 E9.3 Ell.3 E5.3 APPENDICES 6 -REFERENCE E2.3 ENVIRONMENTAL GUIDELINES MEMORANDUM (THIS APPENDIX HAS BEEN DELETED) PLANT SPECIES IDENTIFIED IN SUMMERS OF 1980 AND 1981 IN THE UPPER AND MIDDLE SUSITNA RIVER BASIN,THE DOWNSTREAM FLOODPLAIN,AND THE INTERTIE PRELIMINARY LIST OF PLANT SPECIES IN THE INTERTIE AREA (THIS SECTION HAS BEEN DELETED AND ITS -.,.--.-----'.---.-.--r-NFORMA:TION~I'NCORPORA:TED--r-NTO=kPPENDIX~E3-.c3~~~)~ STATUS AND RELATIVE ABUNDANCE OF BIRD SPECIES OBSERVED ON THE LOWER SUSITNA BASIN DURING GROUND SURVEYS CONDUCTED JUNE 10 THE JUNE 20,1982 __-_._--_---_.- -.-.'-.-._------_--.._...._._._-_...-. ..E2•.3__.S.CI.ENT_IE.I.C_NAME.S_QF_MAMMAL_S.PECIES....EOUND_IN.....THE PROJECT AREA SUMMARY TABLE OF CONTENTS (cont I d) EXHIBIT E -CHAPTER 4 HISTORIC AND ARCHEOLOGICAL RESOURCES Title 1 -INTRODUCTION AND SUMMARY (**)0 co 0 0 ••co •co ..... .. Page No. E-4-1-1 1.1 -Program Objectives (**) 1.2 Program Specifics (**) • • • • • " • 0 E.,.4-1-4 E-4-1-4 2 -BASELINE DESCRIPTION (**)co • o • o .. ..........co co ••E-4-2-1 (I I j 2.1 The Study Area (**)•••••••• 2.2 -Methods -Archeology and History (**)• 2.3 -Methods -Geoarcheology (**)••• 2.4 -Known Archeological and Historic Sites in the Project Area (**)••• 2.5 -Geoarcheology (**)•••••••• ID 0 •" . .. E-4-2-1 E-4-2-2 E-4-2-10 E-4-2-12' E-4-2-13 3 -EVALUATION OF AND IMPACT ON HISTORICAL AND ARCHEOLOGICAL SITES (**)..co ......e 9 •e 0 0 • •E-4-3-1 3.1 -Evaluation of Selected Sites Found: Prehistory and History of the Middle Susitna Region (**)• • • • • • • • • • • • • • • 3.2 -Impact on Historic and Archeological Sites (**)• 4 -MITIGATION OF IMPACT ON HISTORIC AND ARCHEOLOGICAL SITES(**)• •co ...... .. .. ..co e 0 .0 . . . .E-4-3-1 E-4-3-4 E-4-4-1 4.1 -Mitigation Policy and Approach (**)••••••• .4.2 -Mitigation Plan (**)••••••••• E-4-4-1 E-4-4-2 5 -AGENCY CONSULTATION (**)• •••e •e e 0 e 0 0 0 •0 E-4-5-1 6 -REFERENCES •0 • • •eo.• • • • • • • • • • • • • •E-4-6-1 IJ 7 -GLOSSARY 851014 • •0 ••••• • • • • • • • ••• • • • • • xvii E-4-7-1 SUMMARY TABLE OF CONTENTS (cont ed) 2.1 -Identification of Socioeconomic Impact Areas (**)• • • • • • •••• • • • • • •E-5-2-1 2.2 -Description of Employment,Population,Personal Income and Other Trends in the Impact Areas (**)E-5-2-1 ~I J ,I ] , ] j -'J J l ] ] j J ,] ~.1 J E-5-3-49 E-5-3-35 E-5-3-39 E-5-3-65 E-5-4-2 E-5-3-1 E-5-2-1 E-5-3-59 E-5-4-1 E-5-4-1 E-5-4-2 E-5-1-1 Page No. .,.,., . .. fill •e 5 .. .., o • • • ... .,.,.,• •• • o •• • • ••0 ••$•e D ., ., ····xviii 3.1 -Impact of In-migration of People on Governmental Faci Ii ties and·Services (**)•••••••••• 3.2 -On-site Worker Requirements and Payroll, by Year and Month'(**)• • • • • • • • • 3.3 -Residency and Movement of Project Construction Personnel (**)••••••••••••••••• 3.4 -Adequacy of Available Housing in Impact Areas (***)•••••••••••• Di-spl-ac'ement-and'"-!nfluenc'es-'on~Re-srde'trcce'$~ana-~-" Businesses (**)'••••••••••••••••• 3.6 -Fiscal Impact Analysis:.Evaluation of Incremental Local Government Expenditures and Revenues (**)• • " • • • • • • 3.7 -Local and Regional Impacts on Resource User Groups (**)• • • • BASELINE DESCRIPTION (**)• 4.1 -Introduction (**)••••••• 4.2 -Background and Approach (**) 4.3 -Attitudes Toward Changes (This section deleted) 4.4 -Mitigation Objectives and Measures (**)•• 1014 EXHIBIT E -CHAPTER 5 SOCIOECONOMIC IMPACTS 3 -EVALUATION OF THE IMPACT OF THEPRO.JECT (**) 2 1 -INTRODUCTION (**)• •0 .,., Title SUMMARY TABLE OF CONTENTS (eont'd) EXHIBIT E -CHAPTER 5 SOCIOECONOMIC IMPACTS Title 5 -MITIGATION MEASURES RECOMMENDED BY AGENCIES(**).... Page No. E-S-S-l 6 -REFERENCES ••••••• • •-.• • • • •0 • • • • • 0 E-6-6-1 . . . II IJ S.l -Alaska Department of Natural Resources (DNR)(**) S.2 -Alaska Department of Fish and Game (ADF&G)(*) S.3 -U.S.Fish and Wildlife Service (FWS)(*) S.4 -Summary of Agencies'Suggestions for Further Studies that Relate to Mitigation (**) E-S-S-l E-S-S-l E-S-S-2 E-S-S-2 8S1014 xix SUMMARYTABI..E OF CONTENTS (cont'd) 3.1 -Reservoir-Induced Seismicity (RIS)(*)• •E-6-3-1 3.2 -Seepage (*)• • • • • • • • • • • • • • • • •E-6-3-4 3.3 -Reservoir Slope Failures (**)• • • • •E-6-3-4 3.4 -Permafrost Thaw (*)• • • • • • • • • • • •E-6-3-11 3.5 -Seismically-Induced Failure (*)• • • • • • •••E-6-3-11...-_._-~-~_.__._-----3-:-6-------Reservoir-FreeDo-ard---rcir-·Wind;--·Wav"es--_._~-**).-~.--~---.-=-_._~._~._---E--6=3=11 3.7 -Development of Borrow Sites and Quarries (**)• •E-6-3-12 .J .1 'J ".'1-:".. } "] j J j .1 j 1 1 J Page No. E-6-1-1 E-6-3-1 E-6-2-1 E-6-2-2 E-6-2-3 E-6-2-4 E-6-2-11 E-6-2-17 E-6-2-23 E-6-4-1 E-6-5-1 E-6-2-1 •• · .. ·.. ·... .... o • •0 • . . .". . . . . · . . ·"" ·.." ... . •• • • •••••• .. . .... •• •• • ••• ...(*) o .0.• • 0 • ••••• • • • ••• (**) xx . . . . . ..• . . . ..0.. .eo.0 . ••• ••• • • 0 • • • • • 0 • • • • • •0 • -Regional Geology (*)•••••••• -Quarternary Geology (*) -Mineral Resources (0)• • • • • • • • -Seismic Geology (*)• • -Watana Damsite (**)•• -Devil Canyon Damsite (0)•••• -Reservoir Geology (*)• • • • • • • • • EXHIBIT E -CHAPTER 6 GEOLOGICAL AND SOIL RESOURCES 2.1 2.2 2.3 2.4 2.5 2.6 2.7 1 -INTRODUCTION Title 2 -BASELINE DESCRIPTION 3-IMPA.CTS (*)•.. 5 -REFERENCES 4 -MITIGATION (**)• 6 ....GLOSSARY 851014 4.1 -Impacts and Hazards (0)• • • • • • •••E-6-4-1 4.2 -Reservoir-Induced Seismicity (0)• • •E-6-4-1 4.3 -Seepage (**).• • • • • • • • • • • •E-6-4-2 .........................,,4';-4 ReservoirSlope'FaUure's"(**),;,;....;...;···;·················..E.;..;6·~;;;;2·"···..· ....·~····..,4·.5·-Perma·f·rost~-Thaw··€-**~·~""• • • • •.'·;·;-·'E..6·4'-..3 ,~. 4.6 -Seismically-Induced Failure (*)• • • • • • •••E-6-4-3 4.7 -Geologic Hazards (*)• • • •E-6-4-4 4.8 -Borrow and Quarry Sites (*)• • • • • • • • •E-6-4-4 SUMMARY TABLE OF CONTENTS (cont'd) EXHIBIT E -CHAPTER 7 RECREATIONAL RESOURCES Title Page No. 1 -INTRODUCTION (**)• •• • • o • •'0 e ••••••eo • •E-7-1-1 11 1.1 -Purpose (**) 1.2 -Relationships to Other Reports (*) 1.3 -Study Approach and Methodology (**)• 1.4 -Project Description (**)••••~ 2 -DESCRIPTION OF EXISTING AND FUTURE RECREATION WITHOUT THE SUSITNA PROJECT (**)••0 •0 •••• 2.1 -Statewide and Regional Setting (**)• 2.2 -Susitna River Basin (**)••.••• o • E-7-1-1 E-7-1-1 E-7-1-1 E-7-1-3 E-7-2-1 E-7-2-1 E-7-2-8 3.1 -Direct Impacts of Project Features (**) 3.2 -Project Recreational Demand Assessment ••• (Moved to Appendix E4.7)[I 3 -PROJECT IMPACTS ON EXISTING RECREATION (**)• 4 -FACTORS INFLUENCING THE RECREATION PLAN (**) e • • • • ..... E-7-3-1 E-7-3-1 E-7-3-12 E-7-4-1 4.1 Chara'cteristics of the Project Design and Operation (***)• • . • • • • • • • • • • . • • • 4.2 -Characteristics of the Study Area,(***)• 4.3 -Recreation Use Patterns and Demand (***)•.•• 4.4 -Agency,Landowner and Applicant Plans and Policies (***)••••••••••••••• 4.5 -Public Interest (***)"•••••••••• 4.6 -Mitigation of Recreation Use Impacts (***) E':'7-4-1 E-7-4-2 E-7-4-2 E-7-4-3 E-7-4-12 E-7-4-13 5 -RECREATION PLAN (**)• • • • • • • • •0 • • • • • • •E-7-5-1 6 -PLAN IMPLEMENTATION (**) . . . II--' IJ j 5.1 5.2 5.3 5.4 851014 -Recreation Plan Management Concept (***) -Recreation Plan Guidelines (***)• • • • • • -Recreational Opportunity Evaluation • •••• (Moved to Appendix E3.7.3) -The Recreation Plan (**) ............... xxi E-7-5-1 E-7-5-2 E-7-5-4 E-7-5-4 E-7-6-1 SUMMARY TABLE OF CONTENTS (cont'd) !. 1 ( j !I 1 l ( 1 j. j .1 l r 1 J j \ 1 j E-7-10-1 E-7-8-1 E-7-8-1 E-7-8-1 E-7-8-2 E-7-8-1 E-7-7-1 E-7-7-1 E-7-7-2 E-7-7-1 Page No. E-7-6-1 E-7-6-1 E-7-6-2 E-7-6-3 .. . .. ..••.•• 0 • • • • • ••••e e e 0 e 0 0 .'• • 0 • • • •~• • • • •eo.• • • • xxii RECREATION SITE INVENTORY AND OPPORTUNITY EVALUATION EXAMPLES OF TYPICAL RECREATION FACILITY DESIGN STANDARDS.FOR THE SUSITNA PROJECT PHOTOGRAPHS OF SITES'WITHINTHE·PROJECT RECREATION STUDY AREA PROJECT RECREATIONAL DEMAND ASSESSMENT DATA ON REGIONAL RECREATION FACILITIES o 0 EXHIBIT E -CHAPTER 7 RECREATIONAL RESOURCES 7.1 -Construction (**)••••••• 7.2 -Operations and Maintenance (**) 7.3 -Monitoring (***)••••••• 8.1 -Agencies and Persons Consulted (**)• 8.2 -Agency Comments (**)••••.•• 8.3 -Native Corporation Comments (***) 8.4 -Consul tation Meetings (***) 6.1 -Phasing (**)••••••••••••••.•• 6.2 -Detailed Recreation Design (***)••••• 6.3 -Operation and Maintenance (***)•• 6~4 -Monitoring (**)••••••••• E5.7 APPENDICES 851014 10 -GLOSSARY E1.7 E6.7.·· E4.7 8 -AGENCY COORDINATION (**) Title 7 -COSTS FOR CONSTRUCTION AND OPERATION OF THE PROPOSED RECREATION FACILITIES (**)••••••••••0 • •• SUMMARY TABLE OF CONTENTS (cont'd) EXHIBIT E ~CHAPTER 8 AESTHETIC RESOURCES Title 1 -INTRODUCTION (**)••...••.... .•Cl 0 • • ...·. Page No. E-8-1-1 · .. 1.1 -Purpose (*)...•. 1.2 -Relationship to Other Analyses (*) 1.3 -Environmental Setting (**)•••·. . E-8-1-1 E-8-1-1 E-8-1-1 G eo.e 0 0 0 •••••.•••• 2 -PROCEDURE (*)• • •• 3 -STUDY OBJECTIVES (*) • •..0 • •• • • • • • • • •• • E-8-2-1 E-8-3-1 • • • 0 :.Cl • • • • • • • • • •4 -PROJECT FACILITIES (*) 4.1 -Watana Project Area (*)• • • • • • • • • • 4.2 -Devil Canyon Project Area (*)r~>.• • • • • • • • • 4.3 -Watana Stage III Project Area (***)•••••• 4.4 -Denali Highway to Watana Dam Access Road (*) 4.5 -Watana Dam to Devil Canyon Dam Access Road (*) 4.6 -Transmission Lines (*) 4.7 -Intertie •••.•.•••.•••••.•••. (This section deleted) 4.8 -'Recreation Facilities and Features (*)•• E-8-4-1 E-8-4-1 E-8-4-1 E-8-4-1 E-8-4-1 E-8-4-2 E-8-4-2 E-8-4-2 E-8-4-2. 5 -EXISTING LANDSCAPE (**)•••••• • • • ••·.....E-8-5-1 5.1 -Landscape Character Types (*)•• 5.2 -Notable Natural Features (**)••·. . . . .· . E-8-5-1 E-8-5-1 . . . . . . . . ... . ... . . ...4.6 -VIEWS (**) 6.1 -Viewers (***) 6.2 -Visibility (***) . . .· . . .... . E-8-6-1 E-8-6-1 7 -AESTHETIC EVALUATION RATINGS (**)·..•••••••••E-8-7-1 I J ) 7.1 -Aesthetic Value Rating (*) 7.2 -Absorption Capability (*)• 7.3 -Composite Ratings (**)•• · .·......· . . ... E-8-7-1 E-8-7-1 E-8-7-2 851014 xxiii SUMMARY TABLE OF CONTENTS (cont'd) EXHIBIT E -CHAPTER 8 AESTHETIC RESOURCES Title Page No. l ;( ( ) . I 11 -AGENCY COORDINATION (**)•• • • •••• • •••·• • E-S-ll-1 11.1 -Agencies and Persons Consulted (**)··.E-S-ll-l 11.2 -Agency Comments (**)•• •··• • E-8-11-1 12 -REFERENCES •.0 ••0 • • • •••• . 0 0 •0 •0 • • • E-S-12-1 9.1 -Mitigation Feasibility (**)••••••••• 9.2 -Mitigation Plan (***)••••••••• 9.3 -Mitigation Costs (**)•••• 9.4 -Mitigation Monitoring (***)••••• S.l -Mitigation Planning of Incompatible Aesthetic Impacts (Now addressed in Section 9) 8.2 -Watana Stage I (***)• • • • • •••• S.3 -Devil Canyon Stage II (***)•• S.4 -Watana Stage III (***). • • • • • • • • • • 8.5 -Access Routes (***)• • •.~••••• 8.6 -Transmission Facilities (***)•••••••••• ,.\' J I I :I I 'j ·'1 ) \ 1 1 ( 'j 1 E-8-10-1 E-8-8-1 E-S-9-1 E"'S-9-1 E-8-9-2 E-S-9-11 E-S-9-12 E-8-8-1 E-8-8-2 E-S-8-3 E-S"'S-4 E-S-8-5 E-S-8-6 • • •0 • e •0 • • •• • • •e e e •0 e • • •e e 0 G •e 0 0 •0 xxiv • • • 0 • • • • • • • • • • • • • • • 0 ••E-S-13-1 _..--"._---~~.-.~-_..__.._~_.~.__.._._----------_.._---~-_.._-_._---_._~._.__._---------_...---"----_.._-------------------_.._--------------_.._"-"--_.. SITE PHOTOS WITH SIMULATIONS OF PROJECT FACILITIES EXCEPTIONAL NATURAL FEATURES EXAMPLES OF EXISTING AESTHETIC IMPACTS ·PHOTOS OF PROPOSED PROJECT FACILITIES·SITES -GLOSSARY • E1.8 E2.8 APPENDICES 8-AESTHETIC IMPACTS (**) E4.8 E3.8. 9 -MITIGATION (**)e e 0 0 • • 0 10 -AESTHETIC IMPACT EVALUATION OF THE INTERTIE --"-~<-This.Section.DelectecL)-.~..~...".-....~._~ .851014 SUMMARY TABLE OF CONTENTS (cont'd) EXHIBIT E -CHAPTER 8 AESTHETIC RESOURCES Title APPENDICES (cont'd) Page No. J E5.8 E6.8 E7.8 E8.8 E9.8 85~014 EXAMPLES OF RESERVOIR EDGE CONDITIONS SIMILAR TO THOSE ANTICIPATED AT WATANA AND DEVIL CANYON DAMS PROJECT FEATURES IMPACTS AND CHARTS GENERAL AESTHETIC MITIGATION MEASURES APPLICABLE TO THE PROPOSED PRO~ECT LANDSCAPE CHARACTER TYPES OF THE PROJECT ARE~ AESTHETIC VALUE AND ABSORPTION CAPABILITY RATINGS xxv SUMMARY TABLE OF CONTENTS (cont'd) EXHIBIT E-CHAPTER 9 LAND USE AREA (***)eo.• •C)• • •0 .'-.0 e _0 J. .1 \ 1 [ .I 1 I \ 1 Page No. E-9-2-l E-9-1-1 E-9-4--1 E-9--3-1 E-9-2-l E-9-2-1 E-9-5-1 E-9-6-1 .... .... .. . ..".. • •Cl 0 ..eo .. ...... ... • •C'•G Q.e .". •DO.• •0 0 ""e • 0 • 0 • • 0 •0 • • •e 0 •••• • " " " . .. •.f)•" .... o GO. c a 0 • 2.1 -Historical Land Use (***) 2.2 -Present Land Use (***) 1 -INTRODUCTION (***)"""""e "..e .. Title 3 -LAND MANAGEMENT PLANNING IN THE PROJECT 4 -IMPACTS ON LARD USE WITH AND WITHOUT THE PROJECT (***).."..eo ".."..".."..• 2 -HISTORICAL AND PRESENT LAND USE (***) 5 -MITIGATION (***)" 6 -REFERENCES 851014 ,',.xxvi \ ,'l I 1 1 ,) 1 1 SUMMARY TABLE OF CONTENTS (cont'd) EXHIBIT E -CHAPTER 10 ALTERNATIVE LOCATIONS J DESIGNS J AND ENERGY SOURCES Title Page No. 1 -ALTERNATIVE HYDROELECTRIC SITES (*)•0 • • • •G e o •E-10-1-1 1.1 -Non-Susitna Hydroelectric Alternatives (*) 1.2 -Assessment of Selected Alternative Hydroelectric Sites (***)• • • • • 1.3 -Middle Susitna Basin Hydroelectric Alternatives (0)•••••••••••• 1.4 -Overall Comparison of Non-Susitna Hydroelectric Alternatives to the Proposed Susitna Project (***) E-10-l-1 E-10-1-2 E-10-1-17 E-10-1-32 2 -ALTERNATIVE FACILITY DESIGNS (*)G •5 •• • • •0 • •E-10-2-1 2.1 -Watana Facility Design Alternatives (*)••••• 2.2 -Devil Canyon Facility Design Alternatives (0) 2.3 -Ae;cess Alternatives (0)••••••••••••• 2.4 -Transmission Alternatives (0) 2.5 -Borrow Site Alternatives (**)•••••.•••• E-10-2-1 E-10-2-3 E-10-2-4 E-10-2-24 E-10-2-53 3 -OPERATIONAL FLOW REGIME SELECTION (***)• •......E-1O-3-1 3.1 -Project Reservoir Characteristics (***)••••• 3.2 -Reservoir Operation Modeling (***) 3.3 -Development of Alternative Environmental .Flow Cases (***)•••••••••••••••• 3.4 -Detailed Discussion of Flow Cases (***)• • • • • 3.5 -Comparison of Alternative Flow Regimes (***) 3.6 -Other Constraints on Project Operation (***) 3.7 -Power and Energy Production (***)•••••• E-10-3-1 E-10-3-2 E-10-3-6 E-IO-3-17 E-10-3-38 E-1O-3-43 E-IO-3-53 4 -ALTERNATIVE ELECTRICAL ENERGY SOURCES (***)••••• • E-10-4-1 u 4.1 -Coal-Fired Generation Alternatives (***) 4.2 -Thermal Alternatives Other Than Coal (***) 4.3 -Tidal Power Alternatives (***)•••• 4.4 Nuclear Steam Electric Generation (***) 4.5 -Biomass Power Alternatives (***) 4.6 -Geothermal Power Alternatives (***)•• E-lO-4-1 E-lO-4-27 E-lO-4-39 E-lO-4-41 E-lO-4-42 E-lO-4-42 851014 xxvii SUMMARY TABLE OF CONTENTS (cont I d) EXHIBIT E -CHAPTER 10 ALTERNATIVE LOCATIONS:t DESIGNS:t AND ENERGY SOURCES l oj \ Title 4.7 -Wind Conversion Alternatives (***)•••• 4.8 -Solar Energy Alternatives (***)• • • • • • 4.9 -Conservation Alternatives (***)••••••• • •e _e e 0 0 • 0 •••0 •G e $0 0 0 • 1 I ) ii1 I ,\ 1 1 l I .I oj J 1 J 1 E-lO-4-43 E-lO-4-44 E-lO-4-44 E-IO-7-l Page No. E-lO-6-l E-lO-5-le• xxviii ••0 • •e 0 e 0 0 ••c •e 0 0 • •eo.07 -GLOSSARY 5 -ENVIRONMENTAL CONSEQUENCES OF LICENSE DENIAL (***) 6 -REFERENCES SUMMARY TABLE OF CONTENTS (cont'd) EXHIBIT E -CHAPTER 11 AGENCY CONSULTATION Title Page No. 1 -ACTIVITIES PRIOR TO FILING THE INITIAL APPLICATION (1980-February 1983)(***) 2 -ADDITIONAL FORMAL AGENCY AND PUBLIC CONSULTATION (***)• • • • • • • • • • ••e G •e 0 0 • ••••• • • •0 E-ll-l-l E-1l-2-1 I II., I IU 2.1 -Technical Workshops (***)••••••••• 2.2 -Ongoing Consultation (***)• • • • • • 2.3 -Further Comments and Consultation (***)••••• E-1l-2-1 E-1l-2-1 E-1l-2-2 851014 xxix SUMMARY TABLE OF CONTENTS (cont I d) EXHIBIT F SUPPORTING DESIGN REPORT (PRELIMINARY) Title Page No. 1 -PROJECT DATA (***).... .. ....Cl o 0 0 e o Cl 0 0 .... ......F-1-1 • • • • • •e _ •e • •Cl •C F-2-1 F-2-1 F-2-1 F-2-1 F-2-1 F-2-1 F-2-2 . . ·. . ·. . ·.. ..'••0 • · . . . .· .. · . . ...2.1 -Topographical Data (0) 2.2 -Hydrological Data (**)•• 2.3 -Meteorological Data (*)•••••••• 2.4 -Reservoir Data (0)•• 2.S -Tailwater Elevations (0)••••••• 2.6 -Design Floods (**)••••••••• 2 -PROJECT DESIGN DATA (**) 3.1 -Governing Codes and 3.2 -Design Loads (**)• 3.3 -Stability (*)••• 3.4 -Material Properties ...Standards (0) (0)• F-3-1 F-3-1 F-3-1 F-3-6 F-3-9 .. .. . . · . . •• • • · . .· . . . . Cl e • • •.... ·.. ·......3 -CIVIL DESIGN DATA (*) 4 -GEOTECHNICAL DESIGN DATA (**).... .. .. ...... ..•••••F-4-1 4.1 -Watana (**)• ••• 4.2 Devil Canyon (**)· . ...• •G •· . . F-4-1 F-4-10 S -HYDRAULIC DESIGN DATA (**)••0 • • •.'•.•• • • • • F-S-1 S.l -River Flows (**)• • • • • • • • • • •F-S-l S.2 -Design Flows (**)• • • • • • •F-S-1 ..............._~.•.I=Re~~~yQi.?;I,._~.y~1§1 ..{~1._'.......•....••L'_.....F~S~L .. S.4 -Reservoir Operating ..Rule (**).!..!.--"--'!._F~S-2_. ··----·S.5-Reservoir Data (**f-=-=--:--:'-=--=-.:.• • • • • • • •F-S-2 S.6 -Wind Effect (**)•••••••••••• • •F-S-3 5.7 -Criteria (***)• •F-5-3 6 -EQUIPMENT DESIGN CODES AND STANDARDS (**).... .. ....Cl ..F-6-1 6.1 -Design CQdesand Standards (*) 6.2 -General Criteria (*)••••• • • 0 e 0 0, ~0 0 COD G D 0 F~6~1 F-6...2 851014 I ) I SJ.N3J.NOO :10 318'0'J. ii EXHIBIT B PROJECT OPERATIONA.ND·RESOURCE UTILIZATION 1.5.1 -Evaluation Methodology (*)•...B-I-I7 (a)Initial Economic Analyses (*)B-I-20 (i)Plan EI -Watana/Devil Canyon (*)• • • • • • •B-1-20 ,··_·_-_·(-u-)'-Pl-anE2~-HigIiDeviT Canyon/Vee ••••••B-I-20 (iii)Plan E3 -Watana-Tunnel (*).B-I-21 (iv)Plan E4 -Watana/High Devil Canyon/Portage Creek (*)B-I-21 (b)Load Forecast Sensitivity Analyses (*)• • • • • • •B-I-21 1.5.2 -Evaluation Criteria (*)• • •B-I-22 _(a)Economic{~)-..-............'·B-1-22 (Q}...'Environmen t..9_L._(~t__._..._.._.__•__•__.._-,.-B",,1=22 (c)Social (*).•.•~• . • . • .B-I-22 (d)Energy Contribution (*)• • • •B-I-23 1.5.3 -Results of Evaluation Process (*).B-I-23 (a)Devil Canyon Dam Versus Tunnel (*).B-I-23 (i)Economic Comparison (*)B-I-24 (ii)Environmental Comparison (*).B-I-24 -'Ciii)SocIaLCompar1sotl(~,)-.".....B-I-24 (:iv).FJIl~l:'gY:C::()lIIpa:t':il;()'l.C*);:-;:&--1"'"'25 (v)Overall Comparison (*)B-I-25 (b)Watana/Devil Canyon Versus High Devil Canyori'/Vee (*)• • • • • •B-I-25 1.5 ...Evaluation of Basin Development Plans (*)•• I J I I 1 j ~ij 1 J I ) I i J j I 1 .1 j B-I-I7 B-I-14 B-I-I5 B-I-I5 B-I-15 B-I-I5 B-I-I5 B-I-I5 B-I-I6 B-I-I6 B-I-I6 B-I-I6 B-I-I6 B-I-I6 Page No. ...... ••• 2.1 (*). 2.2 (*)• 2.3 (*)• 1.1 (*)• 1.2 (*)• 1.3 (*) ~ABLE.OF CONTENTS (cont'd) Selected Basin Development Plans (*) (a)Plan 1 ("!'C')• • 0)Subplan (ii)Subplan (iii)Subplan (b)Plan 2 (*)•• (i)Subplan (if)Subplan (iii)Subplan (c)Plan 3 (*)•• (i)Subplan 3.1 (*)• (ii)Subplan 3.2 (*)• (d)Plan 4 (*)• . 1.4.3 - Title 851104 EXHIBIT B PROJECT OPERATION AND.RESOURCE UTILIZATION 1.6 -Preferred Susitna Basin.Development Plan (**)•• TABLE OF CONTENTS (cont'd) Title (i) (ii) (iii) (iv) (v) Economic Comparison (*)• • • Environmental Comparison (*). Energy Comparison (*). . Social Comparison (*). Overall Comparison (*) Page No. B-1-25 B-1-25 B-1-26 B-1-26 B-1-26 B-1-27 2 -ALTERNATIVE FACILITY DESIGN,PROCESSES AND OPERATIONS (*)........... 2.1 -Susitna Hydroelectric Development (0) 2.2 -Watana Project Formulation (*) 2.2.1 -Selection of Reservoir Level (0) (a)Methodology (0)•••••••••• .(b)Ecomonic Optimization (*) (c)Relict Channel (**)•••••.•. (d)Conclusions (0)••'••••• 2.2.2 -Selection of Installed Capacity (*). (a)Installed Capacity (*). . (b)Unit Capacity (*)•••• 2.2.3 -Selection of Spillway Design Flood (*) 2.2.4 -Main Dam Alternatives (*).. (a)Comparison of Exbankment and Concrete Type Dams (0)• • • • (b)Concrete Face Rockfill Type Dam (*). (c)Selection of Dam Type (*) 2.2.5 -Diversion Scheme Alternatives (*). (a)Design Flood for Diversion (*)• (b)Cofferdams (*). . . . . . . . . . . (c)Diversion Tunnels (*)•••• (d)Emergency Release Facilities (*) (e)Optimization of Diversion Scheme (*) (f)Selected Diversion Scheme (*) 2.2.6 -Spillway Facilities Alternatives (*) (a)Energy Dissipation (*)• (b)Environmental Mitigation (*)• 2.2.7 -Power Facilities Alternatives (*)• (a)Comparison of Surface and Underground Powerhouse (*). B-2-1 B-2-1 B-2-1 B-2-2 B-2-2 B-2-3 B-2-4 B-2-4 B-2-5 B-2-5 B-2-6 B-2-7 B-2-9 B-2-9 B-2-9 B-2-11 B-2-13 B-2-13 B-2-14 B-2-14 B-2-14 B-2-15 B-2-16 B-2-17 B-2-17 B-2-18 B-2-18 B-2-19 851104 iii EXHIBITB PROJECT OPERATION,AND RESOURCE UTILIZATION TABLEOF,CONTENTS (cont'd) Title (b)Comparison of Alternative Locations (*)••••••• (c)Underground Openings (*)• • • • • • (d)Seleciion of Turbiries (*)••••• (e)Transformers (*)• • • • • • • • • • (f)Power Intake and Water Passages (*). (g)Environmental Constraints (*)••• 2.3 -Selection of Watana General Arrangement (0) (ii) (iii) "(iv) (v) (vi) 2.3.2 2.3.3 2.3.4 2.3.1 -Selection of Methodology (*) (a)Preliminary Review (*)••••••• (b)Intermediate Review (*)' (c)Final Review (*)• • • • -Design Data and Criteria (*) -Evaluation Criteria (*)• • -Preliminary Review (*) (a)Basis of Comparison of Alternatives (*)••• (~b)"..Desc-r-iptionofAlternatives +*-)~~.• (i)Double Stilling Basin Scheme (*). Alternative 1 (*)•••• Al ternatives 2 through 2D (*) Alternative 3 (*)•••• Alternative 4 (*)••••• Selection of Schemes for ¥~,~~h~_!_,__..~~_~gY ...J,_~.l._,.__!.__:_!_,._!!--..!.....• 2.3.5 -Intermediate Review (*)•••••••••_..__.~-------.-------...".-.-.-.-.-~._~-~-~[aJ Descr-iption of Alterna--EIves . Schemes (*)•••••• • • • (i)Scheme WP1 (*)•••••••• (ii)Scheme WP2 (*)• • • • (iii)Scheme WP3 (*) (iv)Scheme WP4 (*)•••••• -(b)--Coll1paI"is()n'ot SclleUi.es ,(*"-) (c)Selec t:i.on~of Scheme s'-for Further Sfudy "'(*)-~~:-'-:--':-':-:'- 2.3.6 -Final Review (*)••••• (a)Scheme WP3(*)•••• (i).Main Dam (*)••••••• 851104 iv I i I Title EXHIBIT B PROJECT OPERATION AND.RESOURCE,UTILIZATION TABLE_OF CONTENTS (cont'd) Page No. (ii)Diversion (*)· ·(iii)Outle t Fac il ities (*)·(iv)Spillways (*)· ·(v)Power Facilities (*) (vi)Access (*)···(b)Scheme WP4A (*).·· · · · · · ···(i)Main Dam (*)·· ···.. (ii)Diversion (*)·· · · ·(iii)Outlet Facilities (*) (iv)Spillways (*)· ·(v)Power Facilities (*) (c)Evaluation of Final Alternative Schemes (*).· ··· · · · · ·2.3.7 -Amendment to License Application (***) (a)Staged Construction (***)· · ···(b)Diversion Tunnels and Cofferd-ams (***)··· · ·(c)Excavation and Foundation Treatment for Dam (***)· ·· · · ·(d)Dam and Cofferdam Configuration and Composition (***) (e)Spillway (***)· · · · · ··· ·(f)Relocation and Reorientation of Caverns (***)· · · · · · · · ·(g)Power Conduits and Intake (***) (h)Power Intake and Spillway Approach Channels (***) (i)Turbine-Generator Unit Speed (***)·(j)Gas Insulated Switchgear and Bus (***). .· ··· · · 2.4 -Devil Canyon Project Formulation (0) 2.4.1 -Selection of Reservoir Level (*)...• 2.4.2 -Selection of Installed Capacity (*) 2.4.3 -Selection of Spillway Capacity (*) 2.4.4 -Main Dam Alternatives (*).• (a)Comparison of Embankment and Concrete Type Dams (*). (i)Rockfill Dam (*)...•. B-2-37 B-2-37 B-2-38 B-2-39 B-2-40 B-2-40 B-:2-40 B-2-40 B-2-41 B-2-41 B-2-41 B-2-42 B-2-42 B-2-43 B-2-43 B-2-44 B-2-44 B-2-45 B-2-46 B-2-46 B-2-47 B-2 47 B-2-47 B-2-48 B-2-48 B-2-48 B-2-49 B-2-50 B-2-50 B-2-51 851104 v vi EXHIBIT B PROJECT OPERATION AND RESOURCE UTILIZATION 2.5 -Selection of Devil Canyon General Arrangement (*)••••• j j j J ) j j j 1 J ] 1 1 j 1 1 1 ! B-2-60 B-2-57 B-2-52 B-2-53 B-2-53 B-2-54 B-2-54 B-2-55 B-2-55 B-2-55 B-2-56 B-2-57 B-2-57 B-2-58 B-2-58 B-2-58 B-2-59 B-2-59 B-2-60 B-2-60 B-2-60 Page No. ...B,.,..2",,60 .L ..]3~2.:':.6.L ---..". B-2-62 B-2-63 B-2-63 B-2-64 B-2-65 B-2-65B__2__65 B-2...15.5 B-2-66 B-2-66 B-2-66 (c) (d) (e) U) TABLE OF CONTENTS (cont'd) (ii)Thick Arch Dam (*)••~• (iii)Thin Arch Dam (*)• •••• (b)Comparison of Arch Dam Types (*) -Diversion Scheme Alternatives (*)• (a)General Arrangements (*). (b)Design Flood for Diversion (*)• .(c)Cofferdams (*)•••••• (d)Diversion Tunnels (*) (e)Optimization of Diversion Scheme (*) -Spillway Alternatives (*)•••• -Power Facilities Alternatives (*) (a)Comparsion of Surface and Underground Powerhouses (*) (b)Comparison of Alternative Locations (*) Selection of Units (*) Transformers (*)••.• Power Intake and Water Passage (*)• Environmental Constraints (*) 2.4.6 2.4.7 2.4.5 -Selection Methodology (*) -Design Data Criteria (*) -Preliminary Review (*) (a)Description of Alternative ..]£h(~meLt~L .'..L'.'..•...•.•.• (i)Scheme DC1 (*)•.-"....!......!..• ·····-~TiTr·Scheme 'DC2 (*) (iii)Scheme DC3 (*).•.. (iv)Scheme DC4 (*) (b)Comparison of Alternatives (*). (c)Selection of Final Scheme 2.5.4 -Final Review (*)•••• (a)"Main DBili(*)•'.• • •e.'••• (h)SpIilway~andOut1etFacilities(-A-)0···Ccy-··I:rrversioiiT*y··:·::··:···:······:·:·.. .0 (d)Power Facilities (*).0 0 •••••• 2.5.5 -Amendment to License Application (***) 2.5.1 2.5.2 2.5.3 Title 851104 I EXHIBIT B PROJECT OPERATION AND RESOURCE UTILIZATION TABLE OF"'CONTENTS (con t 'd) Title 2.6 -Selection of Access Road Corridor (*) Page No. B-2-67 2.6.1 -Previous Studies (*)····B-2-67 2.6.2 -Selection Process Constraints (*)B-2-68 2.6.3 -Corridor Identification and Selection (*)B-2-68 2.6.4 -Development of Plans (*)· · · ··B-2-69 2.6.5 -Evaluation of Plan (*)B-2-70 1 (a)Plan 13 'North'(*)B-2-71 i I (b)Plan 16 'South'(*)B-2-71 (c)Plan 18 'Denali-North'(*)·····B-2-72 2.6.6 -Comparison of the Selected Alternative Plans (*)..··· ·······B-2-72 (a)Costs (*)····B-2-73 (b)Schedule (*)· · ·······B-2-73 (c)Environmental Issues (*)·B-2-74 (i)Wildlife and Habitat (*)B-2-74 (ii)Fisheries (*)····B-2-76 (d)Cultural Resources (**)B-2-79 (e)Socioeconomics (0)·· · · · · B-2-79 (i)Cantwell (0).B-2-7-9 (ii)Hurricane (0)····B-2-80 (iii)Trapper Creek and Talkeetna (0)B-2-80 (Lv)Gold Creek (0).· · B-2-80 (f)Preferences of Native Organizations (*)B-2-80 (g)Relationship to Current Land Stewardships,Uses and Plans (**)B-2-80 2.6.7 -Summary (0).··········B-2-81 2.6.8 -Final Selection of Plan (0)···B-2-81 (a)Elimination of 'South Plan'(0)B-2-81 (b)Schedule Constraints (*)·B-2-82 (c)Cost Impacts (0)·····B-2-83 (d)Summary (*)· · · · · · B-2-83 (e)Plan Recommendation (0)B-2-83 (f)Environmental Concerns -Recommended Plan (*)··········· · B-2-83 J 2.7 -Selection of Transmission Facilities (0)•····B-2-83 2.7.1 -Electric System Studies (0)· · ···B-2-84 851104 vii Page No. TABLE OF CONTENTS (contld) EXHIBIT B PROJECT OPERATION AND RESOURCE.UTILIZATION I J :I ,I J I :J J :I 'j ] ,.~ 'J .1 J ] B-2-11 1 B-2-105 B-2-106 B-2-108 B-2-111 B-2-112 B-2-112 B-2-112 B-2-114 B-2-85 B-2-85 B-2-86 B-2-87 B-2-87 B-2-87 (a) (b) (c) Existing System Data (*)• ••• Power Transfer Requirements (**) Transmission Alternatives (*) (i)Susitna to Anchorage (**). (ii)Sus itna to Fairbanks (0) (iii)Total System Alternatives (*)• (d)Configuration at Generation and Load Ce,:lter s (0)• • • • • • • ••.•B-2~88 (i)Susitna Configuration (**)B-2-89 (ii)Switching at Willow (*)B-2-89 (iii)Switching at Healy (0)••••B-2-89 (iv)Anchorage Configuration (**)B-2-89 (v)Fairbanks Configuration (0)B-2-90 2.7.2 -Corridor selection (0)•••• •••B-2-90 (a)Methodology (0)••••••B-2-90 (b)Selection Criteria (0)• • •B-2-9l (c)Identification of Corridors (0)B-2-9l (d)Description of Corridors (0)• •••B-2-9l (i)Southern Study Area (0)B-2-92 (ii)Central Study Area (0)B-2-94 (itt)-Norfnern -StuoyAr-ea (oJ • •••.:6=2=100 2.7.3 -Corridor Screening (0)•••••B-2-102 (a)Reliability{o)•••••••B-2-102 (b)Technical Screening Criteria (0)••B-2-103 (i)Primar.y Aspects (0)• •B-2-103 (ii)Secondary Aspects (0)•B-2-104 (c)Economic Screening Criteria (0)B-2-105 (i)Primary Aspects (0)• • • •••B-2-105 _______(.ii_)...Secondary_As·pects--(oJ-.-.--.-.--.·-B-2-105 ._.tg,L..Envir.o.nme.ntal_S.cr-eening,--__..-_.-...--- Criteria (0)• • • • • • • (1)Primary Aspects (0)•• (ii)Secondary Aspects (0)• (e)Screening Methodology (0) (i)Technical and Economic Screening Methodology (0)• (ii)EnvironmentaL.Screening M~f:l:1,Q<iolQgy (Q)••••• • • 2.7.4 -Selected Corridor (0)•••• (a)Southern Study Area (0) (b)Central Study Area (0)• Title 851104 viii II EXHIBIT B PROJECT OPERATION AND-RESOURCE UTILIZATION TABLE OF CONTENTS (cont'd) Title (i)The Choice Between CD and CF (0)••••• (ii)The Choice Between ABC AND AJC (0)• ••• (c)Northern Study Area (0)•••• 2.7.5 -Route Selection (0)•• (a)Methodology (0)'•••• (b)Selection Criteria (0)• ••• (c)Environmental Analysis (0)••••• (d)Technical and Economic Analysis (0). (i)Selection of Alternative Routes (0)•••••••• (ii)Evaluation of a Primary Route (0)• • • • • • • (e)Route Soil Conditions (0) (i)Despription (0)•••• (ii)Terrain Unit Ana,lysis (0)• (f)Results and Conclusions (0)••.•• 2.7.6 -Towers,Foundations and Conductors (0) (a)Transmission Line Towers (0) (i)Selection of Tower Type (0)•• (ii)Climatic Studies and Loadings (0) (iii)Tower Family (0)•••• (b)Tower Foundation (0)• • • • • • • • (i)Geotechnical Conditions (0) (ii)Types of Foundations (0) (c)Voltage Level and Conductor Size (0) Page No. B-2-116 B-2-117 B-2-119 B-2-120 B-2-120 B-2-120 B-2-121 B-2-122 B-2-122 B-2-122 B-2-123 B-2-123 B-2-124 B-2-125 B-2-126 B-2-126 B-2-126 B-2-127 B-2-128 B-2-128 B-2-128 B-2-129 B-2-131 3 -DESCRIPTION OF PROJECT OPERATION (***) 3.1 -Hydrology (**) • 0 e _B-3-1 B-3-1 II 3.1.1 -Historical Streamflow Records (**) 3.1.2 -Effects of Glaciers (***) 3.1.3 -Floods (**)•••••• 3.1.4 -Flow Variability (***)••••••••• 3.1.5 -Flow Adjustments (**)• 3.2 -Reservoir Operation Modeling (***) 3.2.1 -Reservoir Operation Models (***) B-3-1 B-3-2 B-3-3 B-3-4 B-3-5 B-3-6 B-3-6 851104 ix Title x B-3-16 B-3-21 B-3-8 B-3-9 B-3-I0 B-3-I0 B-3-I0 B-3-11 B-3-12 B-3-13 B-3-14 B-3-15 B-4-1 B-3-7 B-3-8 B-3-20 B-3-17 B-3-17 B-3-18 B-3-20 B-3-21 B-4-1 B-4-1 B-4-2 B-4-4 B-4-5 B-4.,..5 B-4-6 B-4-6 B-4-7 Page No. . . (***)3.3.1 -Reservoir Storage Characteristics 3.3.2 -Reservoir Operation (***)• 3.3.3 -Development of Alternative Flow Regimes (***) EXHIBIT B PROJECT OPERATION AND RESOURCE UTILIZATION TABLE OF CONTENTS (cont'd) 3.2.2 -Basic Concept and Algorithm of Reservoir Operation (***)•••••• (a)Watana Stage I (***)•••••• (b)Watana Stage I or Stage III with Devil Canyon Stage II (***)••.• 3.2.3 -Standard Weeks (***)•••••••• 3.2.4 -Demand Forecast (***)• • • • • • • • 3.2.5 -Existing Hydroelectric Plants (***) 3.2.6 -Release Constraints (***) 3.2.7 -Reservoir Operation (***)•• ••• • (a)Rule Curve Operat ion (***)• • (b)Rule Curve Development (***)• • (c)Operating Guide (***)•••• (d)OperatirigGuIdeDevelopment (***) 3.2.8 -Special Considerations for Double Reservoir Operation (***). 3.2.9 -Reservoir Operation Computer Programs (***)••••••••••••• (a)Monthly RESOP Program (***)•••• (b)Week1y RESOP Program (***)• • 4.1.1 -System Reliability Criteria (**) (a)Installed Generating Capacity (**)• (b)Transmission System Capability (**). (c)Summary (*~)'._!.'.'.•!'••••• 4.1.2 ....Economic Dispatch of Units (*)••••• (a)Order-:of':""MeritSchedu.le ·(0)•••• (b)Optimum Load Dispatching (0)• • (c)Operating Limits of Units (*).. (d)Optimum Maintenance Program (0). 3.3 -Operational Flow Regime Selection (***)• 4.1 -Plant and System Operation Requirements (**) 851104 Title EXHI.BIT B PROJECT OPERATION AND RESOURCE UTILIZATION TABLE OF .CONTENTS (con.t'd) Page No. 4.1.3 -Unit (a) (b) 4.1.4 operation Reliability Criteria·(0)• Power System Ana1ys.es (0)••••• System Response and Load-Frequency Control (*)•••••.• (c)Protective Relaying System and Devices (0)••.•••• -Dispatch Control Centers (*). B-4-7 B-4-7 B-4-8 B-4-8 B-4-8 4.2 -Power and Energy Production (***)B-4-9 ! ] 4.2.1 -Operating Capabilities of Susitna Units (**) (a)Watana (**)••.• (b)Devil Canyon (**)•••• 4.2.2 -Tai1water Rating Curve (0) 4.2.3 -Average Energy Generation (***). 4.2.4 -Firm Energy Generation (***) 4.2.5 -Dependable Capacity (***)•. 4.2.6 -Base Load and Load-Following Operation (***)••••••. 5 -STATEMENT OF POWER NEEDS AND UTILIZATION.(**)•.. . . B-4-l0 B-4-l0 B-4-11 B-4-11 B-4-1l B-4-ll. B-4-l2 B-4-l2 B-5-l 5.1 -Introduction (**)• •0 •• • • • •B-5-l \ 5.2 -Description of the Rai1be1t Electric Sys tems (**)••••••••••••B-5-l 851104 5.2.1 -The (a) (b) Interconnected Rai1be1t Market (**)• The Electric Utilities and Other Suppliers (**)•••••...••• (i)Anchorage-Cook Inlet Area (**)••••.•• (ii)Fairbanks -Tanana Va11y Area (**)••••••••• (iii)Other Suppliers (*)••• The Existing Electric Energy Supply And Power Plant Capacity (**) xi B-5-l B-5-2 B-5-2 B-5-4 B-5-6 B-5-6 xii TABLE OF CONTENTS (cont'd) 1 ] ] 1 l j ] ,j "'j ] ] ) j j ) ) I 1 J B-5-11 B-5-11 B-5-23 B-5-23 B-5-21 B-5-11 B-5-7 B-5-7 B-5-10 B-5-12 B-5-13 B-5-13 B-5-15 B-5-10 B-5-10 B-5-18 B-5-21 B-5-21 B-5-7 B-5-8 B-5-9 B-5-9 Page No. Model Overview (**)• • • • • • Alaska Petroleum Revenue Sensitivity (APR)Model (**)• • • • • • • • (i)Input Data (***)•••• (ii)APR Mode 1 Output (***) Man';"ll1-the-Arctic'prograDl (}fAp) Economic Model (*)..•.• (T)-Scenario Generator Submodel (*) (ii)Statewide Economic Submodel (*)...•..••• (c) (a) (b) EXHIBIT B PROJECT OPERATION·AND RESOURCE UTILIZATION 5.2.2 -Railbelt Electric Utilities (**)•••• (a)Utility Load Characteristics (**) (i)Monthly Peak and Energy Demand (**)••••••.•• (ii)Daily Load Profiles (**) (iii)Railbelt Load Diversity (**). (b)Electricity Rates (**)••.•••• (i)Anchorage Municipal Light and Power (AMLP)(**)• • •.'.• (ii)Chugach Electric Association, Inc.,(CEA)(**)•.•••• (iii)Fairbanks Municipal Utilities System (mus)(**) (iv)Goldel1ValleyElectric Association,Inc. (GVEA)(**)• • • • • • • (c)Conservation and Rate Structure Programs (*)•••••••••• (i)The Anchorage Municipal Light and Power (AMLP}Program (**) Eii)-.The··Go-lden~Val-leyc-Electric-·- Association,Inc.(GVEA) Program (*)••••••••• (iii)Other Utility Programs (0) (iv)Other Conservation Programs (*)..... 5.2.3 -Historical Data for the Market Area (**) --,f:-3.I--='-Fore cas t ing Mode 1s(**)-~-•._-:--~-•-..-:--~--_.~_.-.-_...·:6=5=16····... B-5-16 Title 851104 Title 851104 EXHIBIT B PROJECT OPERATION .AND·RESO.ORe!UTILIZATION TABLE OF.CONTENTS (cont'd) (iii)Regionalization Submodel (*) (iv)Input Variables and Parameters (*) (v)MAP Model Output (*) (d)Railbelt Electricity Demand Model (*)....••..••... (i)Uncertainty Module (*) (ii)Housing Module (*) (iii)Residential Consumption Module (*)..... (iv)Business Consumption Module (*) (v)Program-Induced Conservation Module (*). (vi)Miscellaneous Consumption Module (*)..•.... (vii)Peak Demand Module (*) .(viii)Input Data (*)•.... (x)RED Model Output (*).... (e)Optimized Generation Planning (OGP) Model (*)•.•.••.•..... (i)Reliability Evaluation (*) (ii)Production Simulation (*).. (iii)Purchases and Sales (*). (iv)Conventional Hydro Scheduling (*) (v)Thermal Unit Maintenance (*). . . . . . • (vi)Thermal Unit Commitment (*). (vii)Thermal Unit Dispatch (*) (viii)Investment Costing (*). (ix)OGP Optimization Procedure (*). (x)Input Data (*) (xi)Output Data (*). 5.3.2 -Model Validation (*) (a)APR Model Validation (***)• • • • • (b)MAP Model Validation (0)• (i)Stochastic Parameter Tests (*)•.•••. xiii Page No. B-5-25 B-5-25 B-5-28 B-5-28 B-5-30 B-5-31 B-5-31 B-5-32 B-5-33 B~5-33 B-5-34 B-5-34 B-5-34 B-5-35 B-5-36 B-5-37 B-5-38 B-5-38 B-5-38 B-5-39 B-5-39 B-5-40 B-5-40 B-5-41 B-5-42 B-5-43 B-5-43 B-5-43 B-5-43 Title 5.4 -Forecast of Electric Power Demand (**). 6 -FUTURE SUSITNA BASIN DEVELOPMENT.(*) ) ] .} ,j- Page No. B-5-44 1 B-5-45 IB-5-46 B-5-46 .\ B-5-46 "(\.)\ B-5-47 B-5-48 !B-5-49 B-5-49 :8-5-50 31 B-5-51 / B-5-53 B-5-53 I jB-5-54 B-5-54 B-5-54 ,'j B-5-54 \ B-5-54 .j B-5-56 B-5-57 )-B-5-57 --_.__._--"-.-.-_...•".- B~5~58 ... B-5-59 1B-5-59 B-5-60 B-6-1 J .I B-7-1 \ J , J 1 ] o •~0 •• •e • xiv EXHIBIT B PROJECT OPERATION.AND RESOURCE.UTILIZATION TABLE OF.CONTENTS (cont'd) (ii)Simulation of Historical Economic Conditions (*)• (c)RED Model Validation (**) 5.4.1 -Variables and Assumptions (**) (a)APR Model (**) (b)MAP Model (*) (c)RED Model (*).• • • • (d)OGP Model (0)•• 5.4.2 -Load Forecasts (**)• (a)StatePettoletilll Revenues (**) (b)Fiscal and Economic Conditions (**)••••• (i)Population (***) (ii)Employment (***) (iii)Households (***)•• (c)Electric Power Demand (**) ~~~fi:)-~Househcol-ds-Servedand Va-eafit .... Households (***)• • • • (ii)Residential Electricity Use Per Household (***)• (iii)Business Use Per E~ployee (***)••••• 5.4.3 -Forecast Comparison (***)•• 5.4.4 -Sensitivity Analysis (**)••• .......__....JaL_MAP_ModeLSensitivity---Tests-(-**J (b)RED_Mode ISens i tivi ty-T_e_s_t_s_t~~>- ---------(c)-OGP Model Sensitivity Tests (**) 5.4 ~5 -Comparison with Previous Forecasts (**)• 5.4.6 -Impact of Oil Prices on Forecasts (**) 7 ..;;,REFERENCES 851104 Number B.1.3.1 B.1.3.2 --I B.1.3.3 B.1.4.1 B.l.4.2 B.l.4.3 B.l.4.4 B.1.4.S B.1.4.6 B.l.S.1 B.l.S.2 B.l.S .3 B.l.S.4 B.l.S.S B~l.S.6 B.l.S.7 851104 EXHIBIT B PROJECT OPERATION AND RESOURCE UTILIZATION LIST OF TABLES Title POTENTIAL HYDROELECTRIC DEVELOPMENT COST COMPARISONS DAM CREST AND FULL SUPPLY LEVELS CAPITAL COST ESTIMATE SUMMARIES :SUSITNA BASIN DAM SCHEMES COST IN $MILLION 1980 RESULTS OF SCREENING MODEL INFORMA TION ON THE DEVIL CANYON DAM AND TUNNEL SCHEMES DEVIL CANYON TUNNEL SCHEMES,COSTS,POWER OUTPUT AND AVERAGE ANNUAL ENERGY CAPITAL COST ESTIMATE SUMMARIES TUNNEL SCHEMES COSTS IN $MILL ION 1 980 SUSITNA DEVELOPMENT PLANS SUSITNA ENVIRONMENTAL DEVELOPMENT PLANS RESULTS OF ECONOMIC ANALYSES OF SUSITNA PLANS - MEDI UM LOAD FORECAST RESULTS OF ECONOMIC ANALYSES OF SUSITNA PLANS -LOW AND HIGH LOAD FORECAST ANNUAL FIXED CARRYING CHARGES SUMMARY OF THERMAL GENERATING RESOURCE PLANT PARAMETERS ECONOMIC BACKUP DATA FOR EVALUATION OF PLANS ECONOMIC EVALUATION OF DEVIL CANYON DAM AND TUNNEL SCHEMES AND WATANA/DEVIL CANYON AND HIGH DEVIL CANYON/VEE PLANS xv Number B.lo5.S B.lo5.9 B.l.5.l0 B.lo5.11 B.l.5.l2 B.l.5.13 B.lo5.l4 B.2.2.l B.2.2.2 B.2.2.3 B.2.2.5 B.2.2.6 B.2.3.l B.2.3.2 851104 EXHIBIT B PRO.JECT OPERATION AND RESOURCE UTILIZATION LIST OF TABLES (cont'd) Title ENVIRONMENTAL EVALUATION OF DEVIL CANYON DAM AND TUNNEL SCHEME SOCIAL EVALUATION OF SUSITNA BASIN DEVELOPMENT SCHEMES/PLANS ENERGY CONTRIBUTION EVALUATIGN OF THE DEVIL CANYON DAM AND TUNNEL SCHEMES OVERALL EVALUATION OF TUNNEL SCHEME AND DEVIL CANYON DAM SCHEME ENVIRONMENTAL EVAL UATIONOF'WATANA/DE\TIL cANYON AND HIGH DEVIL CANYON/VEE DEVELOPMENT PLANS ENERGY CONTRIBUTION EVALUATION OF THE WATANA/DEVIL CANYON AND HIGH DEVIL CANYON/VEE PLANS OVERALL EVALUATION OF THE HIGH DEVIL CANYON/VEE'AND ...........-.,..WATANKlDE VII;'CA:NYONDAM-PLANS-"--'_---_.-- CCMBINED WATANA AND DEVIL CANYON OPERATION PRESENT WORTH OF PRODUCTION COSTS DESIGN PARAMETERS FOR DEPENDABLE CAPACITY AND ENERGY PRODUCTION ..WATANA -MAX.IMJ]~t ..CAPACI'IY.REQ_UIRED.,__01'.TION_L_.........----... THERMAL AS BASE WATANA -MAXIMUM CAPACIlY REQUIRED,OPTION 2 - THERMAL AS PEAK SUMMARY COMPARISON OF POWERHOUSES AT WATANA DESIG~.,DA'rAA~!?_I:>r;~:I;G~_CRI1Ii:R1A,FOR FINAL REVIEW OF LAYOUTS EVALUATION CRITERIA xvi t,1 .~...~ f i ") j ') ,I r ) ) J .i I Number B.2.3.3 B.2.4.1 B.2.S.1 B.2.S.2 B.2.7.1 B.2.7.2 B.2.7.3 B.2.7.4 B.2.7.S B.2.7.6 B.2.7.7 B.2.7.8 B.2.7.9 B.2.7.10 B.2.7.11 B.2.7.12 8S1104 EXHIBIT B PROJECT OPERATION AND RESOURCE UTILIZATION LIST OF TABLES (cont'd) Title SUMMARY OF COMPARATIVE COST ESTIMATES DEVIL CANYON -.MAXIMUM CAPACITY REQUIRED DESIGN DATA AND DESIGN CRITERIA FOR REVIEW OF ALTERNATIVE LAYOUTS SUMMARY OF COMPARATIVE COST ESTIMATES POWER TRANSFER REQUIREMENTS (MW) SUMMARY OF LIFE CYCLE COSTS (1993 $MILLION) TECHNICAL,ECONOMIC,AND ENVIRONMENTAL CRITERIA USED IN CORRIDOR SECTION ENVIRONMENTAL INVENTORY -SOUTHERN STUDY AREA (WILLOW TO ANCHORAGE/POINT MACKENZIE) ENVIRONMENTAL INVENTORY -CENTRAL STUDY AREA (DAMSITES TO INTERTIE) ENVIRONMENTAL INVENTORY -NORTHERN STUDY AREA (HEALY TO FAIRBANKS) SOIL ASSOCIATIONS WITHIN THE PROPOSED TRANSMISSION CORRIDORS -GENERAL DESCRIPTION,.OFFROAD TRAFFICABILITY LIMITATIONS (ORTL)AND COMMON CROP SUITABILITY (CCS) DEFINITIONS FOR OFFROAD TRAFFICABILITY LIMITATIONS AND COMMON CROP SUITABIL.ITY OF SOIL ASSOCIATIONS ECONOMICAL AND TECHNICAL SCREENING SOUTHERN STUDY AREA (WILLOW TO ANCHORAGE/POINT MACKENZIE) ECONOMICAL AND TECHNICAL SCREENING CENTRAL STUDY AREA (DAM SI TES TO INTERTIE) ECONOMICAL AND TECHNICAL SCREENING NORTHERN STUDY AREA (HEALY TO FAIRBANKS) SUMMARY OF SCREENING RESULTS xvii EXHIBIT B PROJECT OPERATION AND RESOURCE UTILIZATION LIST OF TABLES (cont'd) 'Number Title=.;;.;;;..;~--------- B.2.7.13 ENVIRONMENTAL CONSTRAINTS -SOUTHERN STUDY AREA (WILLOW TO ANCHORAGEJPO INT MACKENZIE) :5.2.7.14 ENVIRONMENTAL CONSTRAINTS CENTRAL STUDY AREA (DAM SITES TO INTERTIE) B.2.7.15 ENVIRONMENTAL CONSTRAINTS NORTHERN STUDY AREA (HEALY TO FAIRBANKS) B.2.7.16 TECHNICAL,ECONOMIC AND ENVIRONMENTAL CRITERIA USED IN CORRIDOR SCREENING B.3 ..1.1 PERTINENT DATA FOR GAGING STATIONS B.3 .1.2 USGS STREAMFLOW SUMMARY B.3.1.3 WATANA NATURAL MONTHLY FLOWS (CFS) :13.3.1.4 DEVIL CANYON NATURAL MONTHLY FLOWS (CFS) B.3.1.5 GOLD CREEK NATURAL MONTHLY FLOW (CFS) B.3 .1.6 WEEKLY STREAM FLOW AT WATANA (CFS) :5.3.1.7 WEEKLY STREAM FLOW AT DEVIL CANYON (CFS) B.3.1.8 WEEKLY STREAM FLOW AT GOLD CREEK (CFS) B.3.1.9 SUMMARY OF ESTIMATED STREAMFLOW B.3.1.10 INSTANTANEOUS PEAK FLOWS OF RECORD B.3.1.11 ESTIMATED EVAPORATION LOSSES, B.3•.l.12 WATER APPROPRIATIONS WITHIN ONE MILE _.."-OFTFJJr§JI~Trn~J,U'iT_~g~'_~____ :I3~3~2~rRESERvotR OPERATfoNLEVEi.CONSTRAINTS B.3.2.2 STANDARD WATER WEEKS FOR.ANY WATER YEAR N 851104·xviii j ] ) 1- r I ) ,I 1 ) J I 1 j I I I 1 J Number B.3.2.3 B.3.2.4 B.3.2.5 B.3.3.1 B.3.3.2 B.4.1.1 B.4.2.1 B.4.2.2 B.5.2.1 B.5.2.2 B.5.2.3 B.5.2.4 B.5.2.5 B.5.2.6 B.5.2.7 B.5.2.8 II B.5.2.9L_J 851104 EXHIBIT B PROJECT OPERATION AND "RESOURCE UTILIZATION LIST OF TABLES (cont'd) Title SHCA LOAD FORECAST DISTRIBUTION OF RAILBELT MONTHLY ENERGY REQUIREMENT EXISTING AND PLANNED RAILBELT HYDROELECTRIC ENERGY GENERATION WEEKLY MI'NIMUM MEAN FLOWS AT -GOLD CREEr.< FOR FLOW CASE E-VI ECONOMIC ANALYSIS OF ENVIRONMENTAL FLOW CASES TRANSMISSION SYSTEM PERFORMANCE UNDER DOUBLE CONTINGENCY GENERATING UNIT OPERATING CHARACTERISTICS ENERGY PRODUCTION AND DEPENDABLE CAPACITY INSTALLED CAPACITY OF THE ANCHORAGE-COOK-INLET AREA INSTALLED CAPACITY OF THE FAIRBANKS-TANANA VALLEY AREA EXISTING GENERATING PLANTS IN THE RAILBELT REGION MONTHLY DISTRIBUTION OF PEAK POWER DEMAND PROJECTED MONTHLY DISTRIBUTION OF PEAK AND ENERGY DEMAND PERCENTAGE OF ANNUAL DEMAND TYPICAL 24-HOUR LOAD DURATION RELATIONS LOAD DIVERSITY IN THE RAILBELT RESIDENTIAL AND COMMERICAL ELECTRIC RATES - ANCHORAGE-COOK INLET AREA,MARCH 1983 RESIDENTIAL AND COMMERCIAL ELECTRIC RATES - FAIRBANKS-TANANA VALLEY AREA,MARCH 1983 xix Number B.5.2.10 B.5.2.U B.5.2.12 B.5.2.13 B.5.2.14 B.5.3.1 B.5.3.2 B.5.3.3 B.5.4.1 B.5~4.2 B.5.4.3 B.5.4.5 B.5.4.6 B.5.4.7 B.5.4.8 B.5.4.9 EXHIBIT B PROJECT OPEBATION AND RE SO l:JRCE·UTILIZATION LIST.OF TABLES (cont'd) Title ANCHORAGE MUNICIPAL LIGHT AND POWER,CUMULATIVE ENERGY CONSERVATION PROJECTIONS HISTORICAL ECONOMIC AND ELECTRIC POWER DATA MONTHLY LOAD DATA FROM ELECTRIC UTILITIES OF THE ANCHORAGE-COOK INLET AREA 1976-1983 MONTHLY LOAD DATA FOR THE FAIRBANKS-TANANA VALLEY AREA 1976-1983 NET GENERATION BY RAILBELT UTILITIES 1976-1984 COMPARI SON OF RECENT FYf98S'PETROLEUM PRODUCTION FORECASTS FROM PETREV MAP MODEL VALIDATION SIMULATION OF HISTORICAL ECONOMIC CONDITIONS COMPARISON OF ACTUAL AND PREDICTED ELECTRICITY CONS UMPTIONFORT980';;;T98T FORECASTS OF WORLD OIL PRICE APR MODEL MAJOR VARIABLES AND ASSUMPTIONS APR MODEL VARIABLES AND ASSUMPTIONS MAP MODEL ..··················SUMMARY-OF···MAp····MODEL···PROJECTIONASSUMPTIONS ._JSHGA.AND_.GOMEOS.I.TE._CASESJ____....._._. VARIABLES AND ASSUMPTIONS RED MODEL FUEL PRICE FORECASTS USED BY RED -SHCA CASE FUEL PRICE FORECASTS USED BY RED -COMPOSITE CASE .....JIQUSIW.G J)EMAND .CQEFF'ICIENTS. EXAMPLE OF MARKET SATURATIONS OF APPLIANCES IN SINGLE-FAMILY HOMES FOR ANCHORAGE-COOK INLET AREA xx j l I ]. .J . J J i I ~ 1 )1 .J j j I I ] 1 ( J Number B.5.4.10 B.5.4.1l B.5.4.12 B.5.4.13 B.5.4.14 B.5.4.15 B.5.4.16 B.5.4.17 B.5.4.18 B.5.4.19 B.5.4.20 B.5.4.21 B.5.4.22 B.5.4.23 B.5.4.24 B.5.4.25 B.5.4.26 851104 EXHIBIT B PROJECT OPERATION AND ..RESOURCE UTILIZATION LIST OF TABLES (cont'd) Title PARAMETER VALUES IN RED MODEL PRICE ADJUSTMENT MECHANISM PERCENT OF APPLIANCES USING ELECTRICITY AND AVERAGE ANNUAL ELECTRICITY CONSUMPTION, RAILBELT LOAD CENTERS,1980 GROWTH RATES IN ELECTRIC APPLIANCE C1\PACITY AND INITIAL ANNUAL AVERAGE CONSUMPTION FOR NEW APPLIANCES PERCENT OF APPLIANCES REMAINING IN SERVICE YEARS AFTER PURCHASE RED BUSINESS SECTOR ELECTRICITY CONSUMPTION PARAMETERS VARIABLES AND ASSUMPTIONS -OGP MODEL ECONOMIC PARAMETERS SHCA CASE FORECAST·SUMMARY OF INPUT AND OUTPUT DATA COMPOSITE CASE FORECAST SUMMARY OF INPUT AND OUTPUT DATA SHCA CASE STATE PETROLEUM REVENUES COMPOSITE CASE STATE PETROLEUM REVENUES SHCA CASE STATE GOVERNMENT FISCAL CONDITIONS COMPOSITE CASE STATE GOVERNMENT FISCAL CONDITIONS SHCA CASE POPULATION COMPOSITE CASE POPULATION SHCA CASE EMPLOYMENT COMPOSITE CASE EMPLOYMENT SHCA CASE HOUSEHOLDS xxi EXHIBIT B PROJECT OPERATION AND RESOURCE UTILIZATION Number B.S.A.27 B.S.4.28 B.5.4.29 B.S.4.30 B.5.4.31 B.5.4.32 B.5.4.33 B.5.4.34 B.S.4.35 B.5.4.36 B.5.4.37 B.5.4.38 LIST OF TABLES (cont'd) Title COMPOSITE CASE HOUSEHOLDS SHCA CASE FORECAST NUMBER OF HOUSEHOLDS SERVED COMPOSITE CASE FORECAST NUMBER OF HOUSEHOLDS SERVED SHCA CASE FORECAST NUMBER OF VACANT HOUSEHOLDS COMPOSITE CASE.FORECAST NUMBER OF VACANT HOUSEHOLDS SHCA CASE FORECAST RESIDENTIAL ELECTRICITY USE PER HOUSEHOLD COMPOSITE CASE FORECAST RESIDENTIAL ELECTRICITY USE PER HOUSEHOLD SHCA CASE FORECAST BUSINESS ELECTRICITY USE PER EMPLOYEE COMPOSITE CASE FORECAST BUSINESS ELECTRICITY USE PER SHCA CASE FORECAST SUMMARY OF PRICE EFFECTS COMPOSITE CASE FORECAST SUMMARY OF PRICE EFFECTS SHCA CASE FORECAST BREAKDOWN OF ELECTRICITY REQUIREMENTS ANCHORAGE-COOK INLET AREA I I ....~~.__B.5_.A •.39_.~_._._~SH.CA..-CASEJORECAST~-BREAKDOWN-OF_~ELECTRICTTY. REQUIREMENTS FAIRBANKS-TANANA VALLEY AREA B.5.4.40 B.5.4.41 B.5.4.42 851104 COMPOSITE CASE FORECAST BREAKDOWN OF ELECTRICITY REQUIREMENTS ANCHORAGE-COOK INLET AREA COMPOSITE CASE FORECAST BREAKDOWN OF ELECTRICITY ~-'--""-"-_•..."_."-".."."_""..".,,,,..','"'',,",,..,.".,""",,,".." REQUIREMENTS FAI RBANKS.,.TANANA VALLEY AREA SHCA CASE END USE FORECAST PROJECTED PEAK AND ENERGY DEMAND ···xxii 1 Number B.5.4.43 B.5.4.44 B.5.4.45 B.5.4.46 B.5.4.47 B.5.4.48 B.5.4.49 B.5.4.50 851104 EXHIBIT B PROJECT OPERATION AND RESOURCE UTILIZATION LIST OF TABLES (cont'd) Title COMPOSITE CASE FORECAST PROJECTED PEAK AND ENERGY DEMAND WHARTON CASE FORECAST SUMMARY OF INPUT AND OUTPUT DATA RESULTS OF RED MODEL SENSITIVITY TESTS ON APPLIANCE SATURATION RESULTS OF RED MODEL SENSITIVITY TEST ON BUSINESS SECTOR CONSUMPTION INTENSITY RESULTS OF RED MODEL SENSITIVITY TEST ON OWN PRICE ELASTICITIES RESULTS OF RED MODEL SENSITIVITY TEST ON CROSS PRICE ELASTICITIES TOTAL ELECTRICITY REQUIREMENT WITHOUT LARGE INDUSTRIAL RESULTS OF RED MODEL SENSITIVITY TEST ON ANNUAL LOAD FACTOR TOTAL ELECTRICITY REQUIREMENT?WITHOUT LARGE INDUSTRIAL LIST OF PREVIOUS RAILBELT PEAK AND ENERGY DEMAND FORECASTS (MEDIUM SCENARIO) xxiii Number B.I.I.I B.1.1.2 B.l.2.1 B.l.3.1 B.1.3.2 B.l.3.3 B~1.3.4 B.l.3.5 B.1.3 ..6 B.l.3.7 B.1.3.9 B.1.4.1 B.1.4.2 B. B.I.5.1 B.1.5.2 B.1.5.3 B.2.2.1 851104 EXHIBIT B PROJECT OPERATION AND RE SO DRCE UTILIZATION LIST OF FIGURES Title LOCATION MAP DAMSlTES·PROPOSED BY OTHERS SUSITNA BASIN PLAN FORMULATION AND SELECTION PROCESS PROFILE THROUGH ALTERNATIVE SITES MUTUALLY EXCLUSIVE DEVELOPMENT ALTERNATIVES DEVIL CANYON HYDRO DEVELOPMENT FILL DAM WATANA HYDRO DEVELOPMENT FILL DAM WATANA STAGED FILL DAM HIGH DEVIL CANYON.HYDRO DEVELOPMENT SUSITNA III HYDRO DEVELOPMENT DENALI AND MACLAREN HYDRO DEVELOPMENTS SCHEMATIC REPRESENTATION OF CONCEPTUAL TUNNEL SCHEMES PREFERRED TUNNEL SCHEME 3 PLAN VIEW PREFERRED TUNNEL SCHEME 3 SECTIONS GENERATION SCENARIO WITH SUSITNA PLAN El.3,MEDIUM LOAD FORECAST GENERATION SCENARIO WITH SUSITNA PLAN E2.3,MEDIUM LOAD.FORECAST GENERAtION SCENARIo wt'tHSUSITNA PLAN E3.1,MEDlbM LOAD FORECAST WATANA RESERVOIR DAM CREST EVEVATION/PRESENT WORTH OF PRODUCTION COSTS xxiv 1 l I ( ,I :.f I j i j Number B.2.2.2 B.2.2.3 B.2.2.4 B.2.2.5 B.2.2.6 B.2.2.7 B.2.3.1 B.2.3.2 B.2.3.3 I B.2.3.4l\ B.2.3.5 B.2.3.6 B.2.3.7 B.2.3.8 B.2.3.9 B.2.3.10 B.2.3.11 B.2.3.12 B.2.4.1 B.2.4.2 851104 EXHIBIT B PROJECT OPERATION AND ..RESOURCE UTILIZATION LIST OF.FIGURES (cont'd) Title WATANA -ARCH DAM ALTERNATIVE WATANA ALTERNATIVE DAM AXES WATANA DIVERSION HEADWATER ELEVATION/TUNNEL DIAMETER WATANA DIVERSION UPSTREAM COFFERDAM COSTS WATANA DIVERSION TUNNEL COST/TUNNEL DIAMETER WATANA DIVERSION TOTAL COST/TUNNEL DIAMETER WATANA PRELIMINARY SCHEMES WATANA SCHEME WPI PLAN WATANA SCHEME WP3 SECTIONS WATANA SCHEME WP2 AND WP3 WATANA SCHEME WP2 SECTIONS WATANA SCHEME WP4 PLAN WATANA SCHEME WP4 SECTIONS WATANA SCHEME WP3A WATANA SCHEME WP4A WATANA DAM STAGE I DE VIL CANYON DAM STAGE II WATANA DAM STAGE III DEVIL CANYON DIVERSION HEADWATER ELEVATION/TUNNEL DIAMETER DEVIL CANYON DIVERSION TOTAL COST/TUNNEL DIAMETER xxv B.2.7.l B.2.6.l B.2.7.7 1 j 1 t- 1 1 L) 01 OJ ! °l ( I I 'I 1 I j j ACCESS PLAN 18 (PROPOSED) ALTERNATIVE ACCESS CORRIDORS RECOMMENDED TRANSMISSION CORRIDOR -SOUTHERN STUDY AREA ACCESS PLAN 13 (NORTH) ACCESS PLAN 16 (SOUTH) xxvi LIST OF FIGURES (cont'd) RECOMMENDED TRANSMISSION CORRIDOR -CENTRAL STUDY AREA ALTERNATIVE TRANSMISSION LINE CORRIDORS -CENTRAL STUDY AREA RECOMMENDED TRANSMISSION CORRIDOR -SOUTHERN STUDY AREA Title SCHEDULE FOR ACCESS AND DIVERSION ALTERNATIVE TRANSMISSION LINE CORRIDORS -NORTHERN STUDY-AREAo.-..--.-.----------0-·0··_••·0 ••_00-0 ~..._.....-- RECOMMENDED TRANSMISSION CORRIDOR -CENTRAL "STUDY- AREA ALTERNATIVE TRANSMISSION LINE CORRIDORS -SOUTHERN STUDY AREA DEVIL CANYON SCHEME DC4 DEVIL CANYON SCHEME DCl DEVIL CANYON SELECTED SCHEME DEVIL CANYON SCHEME DC3 DEVIL CANYON SCHEME DC2 EXHIBIT B PROJECT OPERATION AND.RESOURCE UTILIZATION 6 B.2.6.S B.2.7.2 B.2.6.4 B.2.6.3 B.2.7.4 B.2.7.3 B.2.S.4 B.2.6.2 B.2.S.3 B.2.S.2 B.2.S.l B.2.7.S B.2.S.S B. Number 851104 Number B.2.7.8 B.2.7.9 B.2.7.10 B.2.7.11 B.3 .1.1 B.3.1.2 B.3.1.3 B.3.1.4 B.3.1.5 B.3.1.6 B.3.1.7 B.3.1.8 B.3.1.9 B.3.1.10 851104 EXHIBIT B PROJECT OPERATION AND RESOURCE.UTILIZATION .LIST OF FIGURES (cont'd) Title RECOMMENDED TRANSMISSION CORRIDOR -NORTHERN STUDY AREA RECOMMENDED TRANSMISSION CORRIDOR -NORTHERN STUDY AREA RECOMMENDED TRANSMISSION CORRIDOR -NORTHERN STUDY AREA RECOMMENDED TRANSMISSION CORRIDOR -NORTHERN STUDY AREA STREAMFLOW GAGING AND WATER QUALITY MONITORING STATIONS AVERAGE ANNUAL FLOW DISTRIBUTION WITHIN THE SUSITNA RIVER BASIN DAILY DISCHARGE HYDROGRAPHS 1964 NATURAL FLOWS;CANTWELL WATANA,AND GOLD CREEK DAILY DISCHARGE HYDRO GRAPHS 1967 NATURAL FLOWS;CANTWELL,WATANA,AND GOLD CREEK DAILY DISCHARGE HYDRO GRAPHS 1970 NATURAL FLOWS;CANTWELL,WATANA,AND GOLD CREEK ANNUAL FLOOD FREQUENCY CURVE,MACLAREN RIVER NEAR PAXTON ANNUAL FLOOD FREQUENCY CURVE,SUSITNA RIVER NEAR DENALI ANNUAL FLOOD FREQUENCY CURVE,SUSITNA RIVER NEAR CANTWELL ANNUAL FLOOD FREQUENCY CURVE,SUSITNA RIVER AT GOLD CREEK MONTHLY AND ANNUAL FLOW DURATION CURVES,SUSITNA RIVER xxvii EXHIBIT B PROJECT OPERATION.AND RESOURCE UTILIZATION ...._..·-B:-5-;t~1--··----MrLBELTAJmA-(jF-·AtAS!<A-SlmVrtNC-'£LlfCTRTCA:ttOAlJ CENTERS Number B.3.2.1 B.3.2.2 B.3.2.3 B.3.2.4 B.4.1.1 B.4.1.2 B.4.1.3 B.4.1.4 B.4.1.5 B.4.2.1 B.4.2.2 B.4.2.3 B.4.2.4 B.5.2.2 B.5.2.3 B.5.2.4 B.5.2.5 851104 ·,LIST.OF FIGURES (cont I d) Title RESE~R.vOIR AREA AND VOLUME VERSUS ELEVATION,WATANA AND DEVIL CANYON MONTHLY RULE CURVE ELEVATIONS LEVELlZED THERMAL ENERGY GENERATION WATANA OPERATING GUIDE CURVES TYPICAL LOAD VARIATION IN ALASKA RAIL BELT SYSTEM MONTHLY LOAD VARIATION FOR RAILBELT AREA ANCHORAGE-FAIRBANKS TRANSMISSION RELIABILITY EVALUATION,1999 INTERCONNECTED SYSTEM ANCHORAGE-FAIRBANKS TRANSMISSION RELIABILITY EVALUATION,2005 INTERCONNECTED SYSTEM ANCHORAGE-FAIRBANKS TRANSMISSION RELIABILITY EVALUATION-,·2025 INTERCONNECTED SYSTEM WATANA UNIT OUTPUT DEVIL CANYON UNIT OUTPUT WATANA AND DEVIL CANYON TAILWATER RATING CURVES SUSITNA DEPENDABLE CAPACITY LOCATION MAP SHOWING TRANSMISSION SYSTEMS MONTHLY LOAD VARIATION FOR RAILBELT AREA WEEKLY LOAD CURVES -APRIL,.AUGUST,AND DECEMBER 1983 HISTORICAL POPULATION GROWTH :It,viii j ! j 'I 1 1 j j l ! I I i ( ,i ,t ,I ) J j Number B.5.2.6 B.5.3.1 B.5.302 Bo 5.303 B.5.3.4 B.5.3.5 B.5.306 B.5.307 B.5.3.8 B.5.3.9 B.5.3.10 .B.5.3.11 B.5.3.12 B.5.3.13 B.5.3.14 B.5.4.1 B.5.4.2 B.5.4.3 B.5.4.4 B.5.4.5 851104 EXHIBIT B PROJECT OPERATION AND RESOURCE.UTILIZATION LIST OF FIGURES (cont'd) Title HISTORICAL GROWTH IN UTILITY NET GENERATION RELATIONSHIP OF PLANNING MODELS AND INPlIT DATA, APR SENSITIVITY MQDEL STRUCTURE MAP MODEL S¥STEM ECONOMIC MODULE,FISCAL MODULE AND DEMOGRAPHIC MODULE MAP REGIONALlZATION SUB-MODEL STRUCTURE RED INFORMATION FLOWS RED UNCERTAINTY MOD ULE RED HOUSING MODULE RED RESIDENTIAL CONSUMPTION MODULE RED BUSINESS CONSUMPTION MODULE RED MISCELLANEOUS CONSUMPTION MODULE RED PEAK DEMAND MODULE OPTIMIZED GENERATION EXPANSION PLANNING (OGP) PROGRAM INFORMATION FLOWS OPTlMAlZED GENGRATION PLANNING EXAMPLE OF CONVENTIONAL HYDRO OPERATIONS ALTERNATIVE OIL PRICE PROJECTIONS ALTERNATIVE RAILBELT POPULATION FORECASTS ALTERNATIVE RAILBELT HOUSEHOLDS FORECASTS ALTERNATIVE ELECTRIC ENERGY DEMAND FORECASTS ALTERNATIVE ELECTRIC PEAK DEMAND FORECASTS xx~x - i -1 ~l j .j j j ] j 1 ! 1 j i ] 851104 EXHIBIT B PROJECT OPERATION AND RESOURCE UTILIZATION 1 -DAMSITE SELECTION (0) This section summarizes the previous site selection studies and the studies done during the Alaska Power Authority Susitna Hydroelectric Project Feasibility Study (Acres 1982c,Vol.1). 1.1 -Previous Studies (*) Prior to the undertaking of the Susitna Hydroelectric·Project Feasi- bility Study by the Applicant,the hydroelectric development potential of the Alaskan Railbelt had been studied by several entities. 1.1.1 -Early Studies of Hydroelectric Potential (*) Shortly after World War II ended,the United States Bureau of Reclamation (USBR)conducted an initial investigation of hydroelectric potential in Alaska and issued a report of the results in 1948.Responding to a recommendation made in 1949 by the nineteenth Alaska territorial legislature that Alaska be included in the Bureau of Reclamation program,the Secretary of the Interior provided funds to update the 1948 work.The resulting report,issued in 1952,recognized the vast hydroelectric potential within the territory and placed particular emphasis on the strategic location of the Susitna River between Anchorage and Fairbanks as well as its proximity to the connecting Railbelt (Figure B.1.1.1). A series of studies was commissioned over the years to identify damsites and conduct geotechnical investigations.By 1961,the Department of the Interior proposed authorization of a two-dam power system on the Susitna River involving the Devil Canyon and the Denali sites (Figure B.1.1.2).The definitive 1961 report was subsequently updated by the Alaska Power Administration (an agency of the USBR)in 1974,at which time the desirability of proceeding with hydroelectric development was reaffirmed. The Corps of Engineers (COE)was also active in hydropower investigations in Alaska during the 1950s and 1960s,but focused its attention ·on a more ambitious development at Rampart on the Yukon River.This project was capable of generating five times as much annual electric energy as the prior Susitna proposal. The sheer size and the technological challenges associated with Rampart captured the imagination of supporters and effectively diverted attention from the Susitna basin for more than a decade. The Rampart report was finally shelved in the early 1970s because of strong environmental concerns and the uncertainty of marketing B-1-1 prospec~s for so much energy,particularly in light of .abundant natural gas which had been discovered and developed in Cook Inlet. The energy cr1S~S precipitated by the OPEC oil boycott in 1973 provided some further impetus for seeking development of renewable resources.Federal funding was made·available both to complete the Alaska Power Adnlinistration's update report on Susitna in 1974 and to launch a prefeasibility investigation by the COED The State of Alaska itself commissioned a reassessment of the Susitna project by the Henry J.Kaiser Company in 1974. Salient features of the various reports to date are outlined in the following sections. 1.1.2 -u.S.Bureau of Reclamation -1953 Study (*) The USBR 1952 report to the Congress on Alaska's overall hydroelectric potential was followed shortly by the first major study of the Susitna basin in 1953.Ten damsites were identified above the railroad crossing at Gold Creek.These sites are identified ortFigtireB~1.1.2;artdare listed below: o Gold Creek o Olson o Devil Canyon o Devil Creek o Watana o Maclaren o Denali o Butte Creek o Tyone (on the Tyone River). Fifteen more sites were considered below Gold Creek.However, more attention has been focused over the years on the upper ..................-Susitnabasin,where the.topography.is.bett er.suited .·to.dam __cons truc tion andwhere.les simRac t on anadromous:f::i.§her:i.~.~i.1L_ expected.Field reconnaissance eliminated half the original upper basin list,and further USBR consideration centered on Olson,Devil Ganyon,Watana,Vee,and Denali.All of the USBR studies since 1953 have regarded these sites as the most appropriate for further investiga tion. In 1961 a more detaIled feas{bIl{tystudyresult:ed rna recommended five-stage development plan to match the load growth curve as it was then projected.Devil Canyon was to be the firs t development--a 635-foot high arch dam with an installed 'j j .1 1.1 II 851104 B-1-2 851104 capacity of about 220 MW.The reservoir formed by the Devil Canyon Dam alone would not store enough wa'ter to permit higher capacities to be economically installed,since long periods of relatively low flow occur in the winter months.The second stage would have increased storage capacity by adding an earthfill dam at Denali in the upper reaches of the basin.Subsequent stages involved a4ding generating capacity to the Devil Canyon Dam. Geotechnical investigations at Devil Canyon were more thorough than at Denali.At Denali,test pits were dug,but no drilling occurred. 1.1.4 -Alaska Power Administration -1974 Study (*) Little change from the basic USBR 1961,five-stage concept appeared in the 1974 report by the Alaska Power Administration. This later effort offered a more sophisticated design,provided new cost and schedule estimates,and addressed marketing, economics,and environmental considerations. 1.1.5 -Kaiser Proposal for Development (*) The Kaiser study,commissioned by the Office of the Governor in 1974,proposed that the initial Susitna development consist of a single dam known as High Devil Canyon (for location,see Figure B.l.l.2).No field investigations were made to confirm the technical feasibility of the High Devil Canyon location because the funding level was insufficient for such efforts. Visual observations suggested the site was probably favorable. The USBR had always been uneasy about foundation conditions at Denali,but had to rely upon the Denali reservoir to provide storage during long periods of low flow.Kaiser chose to avoid the perceived uncertainty at Denali by proposing to build a rockfill dam at High Devil Canyon which,at a height of 810 feet, would create a large enough reservoir to overcome the storage problem.Although the selected sites were different,the CaE reached a similar conclusion when it later chose the high dam at Watana as the first to be constructed. Subsequent developments suggested by Kaiser included a downstream dam at the Olson site and an upstream dam at a site known as Susitna III (Figure B.l.l.2).The information developed for these additional dams was confined to estimated energy potential. As in the CaE study,future development of Denali remained a possibility if foundation conditions were found to be adequate and if the value of additional firm energy provided economic justification at some later date. 1.1.6 -U.S.Army Corps of Engineers -1975 and 1979 Studies (*) The most comprehensive study of the upper Susitna basin prior to the current study was completed in 1975 by the CaE.A total of B-1-3 23 alternative developments were analyzed,including those proposed by the USBR,as well as consideration of coal as the primary energy source for Railbelt electrical needs.The COE agreed that an arch dam at Devil Canyon was appropriate,but found that a high dam at the Watana si te would form a large enough reservoir for seasonal storage and would permit continued generation during low flow periods. The COE recommended an earthfill dam at Watana with a height of 810 feet.In the longer term,development of the Denali site remained a possibility which,if constructed,would increase the amount of firm energy available in dry years. An ad hoc task force was created by Governor Jay Hammond upon completion ,of the 1975 COE study.This task force re'Commended endorsement of the COE request for Congressional authorization, but pointed out that extensive further studies,particularly those dealing with environmental and socioeconomic questions, were necessary before any construction decision could be made. At the federal level,concern was expressed at the Office of .Management and Budget regarding the adequacy of geotechriica 1 data at the Watana site as well as the validity of the economics.The apparent ambitiousness of the schedule'and the feasibility of a thin arch dam at Devil Canyon were also questioned.Further investigations were funded and the COE~roduced an updated report in 1979.Devil Canyon and Watana were reaffirmed as appropriate sites,but alterttative dam types were investigated.A concrete ~~-gravnyaamwasanalyzeQasanan:erna..tiv'e-~for~Elfe-t1t~in arch dam at Devil Canyon and the Watana Dam was changed from earthfill to rockfilL Subsequent cost and schedule estimates still indicated economic justification for the project. 1.2 -Plan Formulation and Selection Methodology (*) The proposed plan which is the subject of this License Application was selected after ··a revi.ewand,-rea sses sment of all previous ly-considered .. s_Ltes_(Ac.r_es..L9.82_c_,....V_o_L U..__~_.. This section of the report outlines the engineering and planning stud- ies carried out as a basis for formulation 6f Susitna basin development plans and selection of the 'preferred plan. In the description of the planning process,certain plan components and processesarefrequeniiy di.scussed..'it Is appropriate that ....three par- ti.Ctlla.r .terllls be clearly defined: o Damsite -An individual potential damsite in the Susitna basin, re ferred to in the generic proces s as "candida te ." j - j ,j 'J 851104 B-1-4 ,,.] o Basin Development Plan - A plan for developing energy within the upper Susitna basin involving one or more dams,each of'.specified height,and corresponding power plants of specified capacity. Each plan is identified by a plan number and subnumber indicating the staging sequence to be followed in developin'g the full potential of the plan over a period 6f time. o Generation Scenario - A specified sequence of implementation of power generation sources capable of providing sufficient power and energy to satisfy an electric load growth forecast for the 1980-2010 period in the Railbelt area.This sequence may include different types of generation sources such as hydroelectric and coal-,gas-or oil-fired thermal.These generation scenarios were developed for the comparative evaluations of Susitna basin generation versus alternative .,methods of generation. In applying the generic plan formulation and selection methodology, ~ive basic steps are required:gefining the objectives,selecting can- didates,screening,formulation of development plans,and,finally,a detailed evaluation of the plans (Figure B.1.2.1).The objective is to determine the optimum Susitna basin development plan.The various steps required are outlined in subsections of this section. Throughout the planniag process,engineering layout studies were made to refine the cost estimates for power generation facilities or water storage development at several damsites within the basin.These data were fed into the screening and plan formulation and evaluation stud- ies. The second objective,the detailed evaluation of the various plans,is satisfied by comparing generation scenarios that include the selected Susitna basin development plan with alternative generation scenarios, including all-thermal and a mix of thermal plus alternative hydropower developments. 1.3 -Damsite Selection (*) In previous Susitna basin studies,twelve damsites were identified in the upper portion of the basin,i.e.,upstream from Gold Creek. These sites are listed in Table B.1.3.1 with relevant data concerning facilities,cost,capacity,and energy. The longitudinal profile of the Susitna River and typical reservoir levels associated with these sites are shown in Figure B.1.3.1.Figure B.1.3.2 illustrates which sites are mutually exclusive,i.e.,those which cannot be developed jointly,since the downstream site would inundate the upstream site. It can be readily seen that there are several mutually exclusive schemes for power development of the basin.The development of the 851104 B-1-5 Watana site precludes development of High Devil Canyon,Devils Creek, Susitna III and Ve.e but fits well with Devil Canyon.Convers·e1y,the High Devil Canyon site would preclude Watana and Devil Canyon but fits well with Olson and Vee or Susitna III.These downstream sites do not preclude development of the upstream storage sites,Denali or Butte Creek and Maclaren. .All relevant da ta concerning dam type,capital cost,power,and energy output were assembled and are summarized in Table B.1.3.1.For the Devil Canyon,High Devil Canyon,Watana,Susitna III,Vee,Maclaren, and Denali sites,conceptual engineering layouts were produced and capital costs were ~stimated based on calculated quantities and unit rates.Decai1ed analyses were also undertaken to assess the power capability and energy yields.At the Gold Creek,Devil Creek,Olson, Butte Creek,and Tyone si tes,no de tailed engineering or energy studies were undertaken;data from previous studies were used wit~capital cost estimates updated in 1980 levels.Approximate estimates of the potential average energy yield at the Butte Creek and Tyone sites were under~a~en to assess the relative importance of these sites as energy produce rs. The data presented Iti TabieB.f::f~I sh6wthatDevlt CanyOn,fl.ighDevil Canyon,and W~tana are the most economic large energy producers in the basin.Sites such as Vee and Susitna III.have only medium energy production,and are slightly more costly that the previously mentioned damsites.Other sites such as Olson and Gold Creek are competitive provided they have addi tiona1 upstream regulation.Sites such as Denali and Maclaren produce substantially higher cost energy than the -'-othersi tes but-cao·lilso··l)-e used·to-increase-regulliEiO·o·o-f·-flow-for·-- downstream use. 1.3.1 -Site Screening (*) The objective of this screening process was to eliminate sites which would obviously not be included in the initial stages of the Susitna basin development plan and which,therefore,did not --···-·deserve······further-studyat-thisst-age.··Three··basic-screening-.....__.... .--~c-r-i-te·r-ia-we·r.e-used:---en-vir.onmental,.--alter.na.tLve si tes,-andener.gy. contribution. The screening process involved eliminating all sites falling in ~he unacceptable environmental impact and alternative site categories •.Those failing to meet the energy contribution c:r:itgria Wg:re._~JSlgel.im.itl~.l:.egy.tlles stheyha,<Lt;Qmep()tetltia 1 for upstream regulation.The result:s of this process were as f(>llows: o The "unacceptable site"environmental category eliminated the Gold Creek,Olson,andTyones:i.tes. I ] I J I.J -1 851104 B-1-6 J o The alternative sites category eliminated the Devil Creek and Butte Creek sites. o No additional sites were eliminated for failing to meet the energy contribution criteria.The remaining sites upstream from Vee,i.e.,Maclaren and Denali,were retained to insure that further study be directed toward determining the need and viability of providing flow regulation in the headwaters of the Susitna. 1.3.2 -Engineering Layouts (*) In order to obtain a uniform and reliable data base for studying the seven sites remaining,it was necessary to develop engineering layouts and reevaluate the costs.In addit~on, staged developments at several of the larger dams were studied. The basic objective of these layout studies was to establish a uniform and consistent development cost for each site.These layouts are consequently conceptual in nature and do not necessarily represent optimum project arrangements at the sites. Also,because of the lack of geotechnical information at several of the sites,judgmental decisions had to be made on the appropriate foundation and abutment treatment.The relative accuracy of cost estimates made in these studies is on the order' of pI us or minus 30 percent. (a)Design Assumptions (*) In order to maximize standardization of the layouts,a set of basic.design assumptions was developed.These assumptions covered geotechnical,hydrologic,hydraulic, civil,mechanical,and electrical considerations and were used as guidelines to determine the type and size of the various components within the overall project layouts.As stated previously,other than at Watana,Devil Canyon,and Denali,little information regarding site conditions was available.Broad assumptions were made on the basis of the limited data,and those assumptions and the interpretation of data have been conservative. It was assumed that the relative cost differences between rockfill and concrete dams at the site would either be marginal or greatly in favor of the rockfill.The more detailed studies carried out subsequently for the Watana and Devil Canyon sites support this assumption.Therefore,a rockfill dam has been assumed at all developments in order to eliminate cost discrepancies that might result from a consideration of dam-fill unit costs compared to concrete unit costs at alternative sites. 851104 B-1-7 (b)General Arrangements (*) Brief descriptions of the general arrangements developed for the various sites are given below.Descriptions of Watana and Devil Canyon in this section are of the preliminary lay- outs and should not be confused with the proposed layouts in Exhibit A and Exhibit F.Figures B.l.3.3 to B.l.3.9 illustrate the layout details.Table B.l.3.3 summarizes the crest levels and dam heights considered. In laying out the developments,conservative arrangements have been adopted,and whenever possible there has been a general standardization of the component structures. (0 Devil Canyon (Figure B.l.3.-3)(*) The development at Devil Canyon,located at the upper end of the canyon at its narrowest point,consists of a rockfill dam,single spillway,power facilities incorporating an underground powerhouse,and a tunnel diversion.- The rockfill dam would rise above the valley on the south abutment and terminate in an adjoining saddle dam of similar construction.The dam would be 675 feet above the lowest foundation level with a crest elevation of 1,470 and a volum~of 20 million cubic The spillway would be located on the north bank and would consist of a gated overflow structure and a concrete-lined chute linking the overflow structure with intermediate and terminal stilling basins. Sufficient spillway capacity would be provided to pass the Probable Maximum Flood safely. -------------------.----The--power---fa-c-i-l-i-t-ies--wo u1-d-be-loca-ted-on-the north-. .----._.~_--_..~_-_._--_.._-_._--___._------.__.._~_--_~_-----.._-----_.---~a-b.u.tmen.t-o--The~tIia:s.s.i1T~intake-:.s_truc~t_ure_+w.o.ul_d __b.e .__~ founded within the rock at the end of a deep approach channel and would consist of four integrated units, each serving individual tunnel penstocks.The powerhouse would house four l50~vertically mounted Francis type turbines driving overhead l65-MVA synchronous gene~ators. As an alternative to-the full power CievE!lqpml:!llt:ill the first phase of construction,a staged powerhouse alternative was also investigated.The dam would be completed to its full height but with an initial plant installed capacity in the300-MW range.The ] - 1 -::1 J 851104 B-1-8 J 1.1 ) 851104 complete powerhouse would be constructed t~gether with penstocks and a tailrace tunnel for the initial two 150-MW units,together with concrete foundations for future units. (ii)Watana (Figures B.l.3.4 and B.l.3.5)(*) For initial comparative study purposes,the dam at Watana is assumed to be a rockfill structure located on a similar alignment to that proposed in the previous COE studies.It would be similar in construction to the dam at Devil Canyon with an impervious core founded on sound bedrock and an outer shell composed of blasted rock excavated from a single quarry located on the south abutment.The dam would rise 880 feet from the lowest point~on the foundation and have an overall volume of approximately 63 million cubic yards for a crest elevation of 2,225. The spillway would be located on the north bank and would be similar in concept to that at Devil Canyon with intermediate and terminal stilling basins. The power facilities located within the south abutment with similar intake,underground powerhouse, and water passage concepts to those at Devil Canyon would incorporate four 200-MW turbine/generator units giving a total output of 800 MW. As an alternative to the initial full development at Watana,staging alternatives were investigated. These included staging of both dam and powerhouse construction.Staging of the powerhouse would be similar to that at Devil Canyon,with a Stage I installation of 400 MW and a further 400 MW in Stage II. In order to study the alternative dam staging concept,it was assumed that the dam would be constructed for a maximum operating water surface elevation some 200 feet lower than that in the final stage (Figure B.l.3.5). The powerhouse would be completely excavated to its fina I size during the first stage.Three oversized 135-MW units would be installed together with base concrete for an additional unit.A low-level control structure and twin concrete-lined tunnels leading into a downstream stilling basin would form the first stage spillway. B-I-9 For the second stage,the dam would be completed to its full height,the impervious core would 'be ' appropriately raised,and additional rockfill would, be placed on the downstream face.It was assumed that,before construction commenced,the top 40 feet of the first stage dam would be removed to ensure the complete integrity of the impervious core for the raised dam.A second spillway control structure would be constructed at a higher level and would incorporate a downstream chute leading to the Stage I spillway structure.The original spillway tunnels would be closed with concrete plugs.A new intake structure would be ~onstructed utilizing existing gates and hoists,and new penstocks would be driven to connect with the existing ones.The existing intake would be sealed off.One additional 200-MW unit would be installed and the required additional penstock and tailrace tunnel constructed.The existing 135~units would be upgraded to 200 MW. (iii)HighDevilCal1 yon (Figure B'.1.3.6)(*) The development would be located between Devil Canyon and Watana.The 855-foot high rockfill dam would be similar in design to Devil Canyon,containing an estimated 48 million cubic yards of rockfill with a crest elevation of 1,775.The south bank spillway and the north bank powerhouse facilities woul,d also 'oesiliiTlaj:-in concept-to DeviT Cany'on;wiEn 'an - installed capacity of 800 MW. Two stages of 400 MW were envisaged,each of which would be undertaken in the same manner as at Devil Canyon,with the dam initially constructed to its full height. ····(.iv}·Sus-itna-I-I-I-(Fig-ure .B.l.3.7)--(-*) ._--_.._---------_.._--------------_._-----------~.._____--------___---.._. !'I J 1 1 'j 851104 (v) The development would involve a rockfill dam with an impervious core approximately 670 feet high,a crest elevation of 2,360,and a volume of approximately 55 million cubic yards.A concrete-lined spillway chute and a single stilling basin would be located underground,with the two diversion tunnels on the south bank. Vee (Figure B.1.3.8)(*) A 610-foot high rockfill dam founded on bedrock with a crest elevation of 2,350 and total volume of 10 million cubic yards was considered. B-1-10 I j I Since Vee is 10cate4 farther upstream than the other major sites,the flood flows are correspondingly lower,thus allowing for a reduction in size of the spillway facilities.A spillway utilizing a gated overflow structure,chute,and flip bucket was adopted. The power facilities would consist of a 400-MW underground power house located in the south bank with.a tailrace outlet well downstream of the main dam.A secondary rockfill dam would also be required in this vicinity to seal off a low point.Two diversion tunnels would be provided on the north bank. (vi)Maclaren (Figure B.l.3.9)(*) The development would consist of a l85-foot high earthfill dam founded on pervious riverbed materials.The crest elevation of the dam would be 2,405.This reservoir would essentially be used for regulating purposes.Diversion would occur through three conduits located in a open cut on the south bank,and floods would be discharged via a side chute spillway and stilling basin on the north bank. (vii)Denali (Figure B.l.3.9)(*) Denali is similar in concept to Maclaren.The dam would be 230 feet high,of earthfill construction, and with a crest elevation of 2,555.As for Maclaren,no generating capacity would be included. A combined diversion and spillway facility would be provided by twin concrete conduits founded in open cut excavation in the north bank and discharging into i a common stilling basin. ~ J 1.3.3 -Capital Costs (*) 851104 J For purposes of initial comparisons of alternatives,construction quantities were determined for items comprising the major works and structures at the site.Where detail or data were not sufficient for certain work,quantity estimates were made on the basis of previous development of similar sites and general knowledge of site conditions reported in the literature.In order to determine total capital costs for various structures, unit costs have been developed for the items measured.These have been estimated on the basis of review of rates used in previous studies,and of rates used on similar works in Alaska and elsewhere.Where applicable,adjustment factors based on B-l-ll geography,climate,manpower and accessibility were used. Technical publications have'also been reviewed for basic rates and escalation factors. The total capital costs developed are shown in Tables B.l.3.l and B.l.3.2.It should be noted that the capital costs for Maclaren and Denali shown in TableB.1.3.1·have been adjusted to incorporate the costs of generation plants with capacities of 55 MW and 60 MW,respectively.Additional data on the projects are summarized in Table B.l.3.3. 1.4 -Formullitioti.of Susitna Basin Development Plans (*) The results of the site screening process described above indicate that the Susitna basin development plan should incorpora-te a combination of several major dams and powerhouses located at one or more of the following sites: o Devil Canyon a High 'nevi1 Canyon' o Watana. o Susitnli III o Vee. Supplementary upstream flow regulation could be provided by structures at Maclaren and Denali. A computer-assisted screening process identified the plans of Devil Canyon/Watana or High Devil Canyon/Vee as most --economic.In addition to these two basicde~elopmentplans,a tunnel scheme which provides potentilil environmental advantages by replacing the Devil Canyon Dam with a long power tunnel and a development plan involving Wa tana Dam were also introduced. The criteria used-at'this"stage of-the 'process'for selectron-o·f-pre.......--.--- -,-~--.-----..---ferred--Sus-i-tna---bas-in--deve-l-opment--plans-were-ma-in-l-y-econom-ic-(-F-igure--,---------- B.l.2.l).Environmental considerations were incorporated into the further assessment of the plans finally selected. The results of thes.creeningprocessareshown in TableB.1.4.2 Because of the simplifying asstnIlptions that were made in the screening model,'the _three best solutions from an economic point of view are included'in--the --tlible; The most important conclusion!:!that can be drawn are as follows: o For energy requirements of up to 1,750 GWh,the High Devil Canyon,Devil Canyon or the Watana sites individually provided .•c-.' 'I: -..1' J ,."~, j 1 I J ,.I I 1 851104 B-1-12 the most economic energy.The difference between the costs shown on Table B.l.4.2 is around 10 percent,which is similar to the accuracy that can be expected from the screening model. o For energy requirements of between 1,750 and 3,500 GWh,the High Devil Canyon site is the most economic. o For energy requirements of between 3,500 arid 5,250 GWh,the combinations of either Watana and Devil Canyon or High Devil Canyon and Vee are most economic. o The total energy production capability of the Watana/Devil Canyon development is considerably larger than that of the High Devil Canyon/Vee alternative and is the only plan capable of meeting energy demands in the 6,000 GWh range. 1.4.1 -Tunnel Alternatives (*) A scheme involving a long power tunnel could conceivably be used to replace the Devil Canyon Dam in the Watana/Devil Canyon development plan.It could develop similar head for power generation and might provide some environmental advantages by avoiding inundation of Devil Canyon.Obviously,because of the low winter flows in the river,a tunnel alternative could be considered only as a second stage to the Watana development. Conceptually,the tunnel alternatives wou~d comprise the following major components in some combination,in addition to the Watana Dam,reservoir and associated powerhouse: o Power tunnel intake works; o One or two power tunnels up to 40 feet in diameter and up to 30 miles in length; o A surface or underground powerhouse with a capacity of up to 1,200 MW; o A re-regulation dam if the intake works are located downstream from Watana;and o Arrangements for compensation flow in the bypassed river reach. Four basic alternative schemes were developed and studied. Figure B.l.4.l is a schematic illustration of these schemes.All schemes assumed an initial Watana development with full reservoir supply level at elevation 2,200,and the associated powerhouse with an installed capacity of 800 MW.Table B.l.4.3 lists all the pertinent technical information.Table B.l.4.4 lists the 851104 B-l-13 851104 power and energy yields for the four schemes.Table B.1.4.5 itemizes the capital cost estimate. Based on the foregoing economic information,Scheme 3 (Figures B.1.4.2 and B.1.4.3)produces the lowest cost energy by a factor of nearly 2. A review of the environmental impacts associated with the four tunnel schemes indicates that Scheme 3 would have the least impact,primarily because it offers the best opportunities for regulating daily flows downstream from the project.Based on this assessment and because of its almost 2 to 1 economic advantage,Scheme 3 was selected as the only scheme worth further study.(See Development Selection Report for detailed analysis.) The capital cost estimate for Scheme 3 appears in Table B.1.4.5. The estimates also incorporate single and double tunn~l options. For purposes of these studies,the double tunnel option has been selected because of its superior reliability.It sh.ould also be recognized that the cost estimates associated with.the tunnels are probably subject to more varia tion than those associated with the dam schemes,due to geotechnical uncertainties.·In an attempt to compensate for these uncertainties,economIc sensitivity analyses using both higher and lower tunnel costs have been conducted. 1.4.2 -Additional Basin DevelOpment Plan (*) As noted,the Watana and High Devil Canyon damsites.appear to be l.ndIvTdualTY -superIor-Tn economlcterms-to--arr others:-An additional plan was therefore developed to assess the potential for developing these two sites together.For this scheme,the Wa tana Dam would be developed to its full potential.The High Devil Canyon Dam would be constructed to a crest elevation of 1,470 to fully utilize the head downstream from Watana. 1.4.3 -Selected Basin DevelOpment Plans (*) ------The-ess en·t-ia-1-ob-:iee-t-i-ve-o-f-t-h-is-s-t-ep-in-t-he-de-velopment-se-lec-t-ion--- process was defined as the identification of those plans which appear to warrant further,more detailed evaluation.The results of the final screening process indicate that the Watana/Devil Canyon and the High Devil Canyon/Vee plans are clearly superior to all other dam combinations.In addition,it was decided to study'l'um!eLSchf:T!l.eJ fUJ::ther ..;3.s<1n.;3.:J.t:eI:"n<1tive.t:Qt:he liigh Devil --------CanyonDam and-a plan combiningWatana and·High Devil-Canyon. Associated with each of these plans are several options for staged development.For this more detailed analysis of these basic plans,a range of different approaches to staging the developments was considered.In order to keep the total options B-1-14 r ) { J , j to a reasonable number and also to maintain reasonably large staging steps consistent with the total development size,staging of only the two larger developments (i.e.,Watana and High Devil Canyon)was considered.The basic stag~ng concepts adopted for these developments involved staging both dam and powerhouse construction or,alternatively,just staging powerhouse construction.Powerhouse stages were considered in 400-MW increments. Four basic plans and associated subplans are.briefly described below.Plan 1 involves the Watana/Devil Canyon sites,Plan 2 the High Devil Canyon/Vee sites,Plan 3 the Watana-tunnel concept, and Plan 4 the Watana/High Devil Canyon sites.Under each plan several alternative subplans were identified,each involving a different staging concept.Summaries of theseq'pl'ans are given in Table.B.l.4.6. (a)Plan 1 (*) (i)Subplan 1.1 (*) The first stage involves constructing Watana Dam to its full height and installing 800 MW.Stage 2 involves constructing Devil Canyon Dam and installing 600 MW. (ii)Subplan 1.2 (*) For this subplan,construction of the Watana Dam staged from a crest elevation of 2,060 to 2,225. powerhouse is also staged from 400 MW to 800 MW. for Subplan 1.1,the final stage involves Devil Canyon with an installed capacity of 600 MW. (iii)Subplan 1.3 (*) is The As 851104 This subplan is similar to subplan 1.2 except that only the powerhouse and not the dam at Watana is staged. (b)Plan 2 (*) (i)Subplan 2.1 (*) This subplan involves constructing the High Devil Canyon Dam first with an installed capacity of 800 MW.The second stage involves constructing the Vee Dam with an installed capacity of 400 MW. B-I-15 (ii)Subplan 2.2 (*) For this subplan,the construction of High Devil Canyon is staged from a crest elevation of 1,630 to 1,775.The installed capacity is also staged from 400 to 800 MW.As for subplan 2.1,Vee follows with 400 MW of installed capacity. (iii)Subplan 2.3 (*) This subplan is similar to subplan 2.2 except that only the powerhouse and not the dam at High Devil Canyon is staged. (c)Plan 3 (*) (i)Subplan 3.1 (*) This subplan involves initial construction of Watana and installation of 800-MW capacity.The next stage involves the construction of the downstream reregulation dam to a crest elevation of 1,500 and a IS-mile long tunnel.A total of 300 MW would be installed at the end of the tunnel and a further 30 MW at the re-regulation dam.An additional 50 MW of capacity would be installed at the Watana powerhouse to facilitate peaking operations. This subplan is essentially .the same as subplan 3.1 except that construction of the initial 800-MW powerhouse at Watana is staged. (d)Plan 4 (*) ··_---c-··-This-·sing1:eplan-was--developed--to·jointly-eva-luatethe- de-ve-1-opme·nt--o-f-the-two..:.mo st~eGonom-ic-dams-i-tes-,--Wa-ta-na-and--..---_... High Devil Canyon.Stage 1 involves constructing Watana to its full height with an installed capacity of 400 MW.Stage 2 involves increasing the capacity at Watana to 800 MW. Stage 3 involves constructing High Devil Canyon to a crest elevation of 1,470 so that the reservoir extends to just downstream of Watana.In orcier to develop the full head betweenWatanaandPortage·'Creek,'an-additional smaller dam is:"a.dded:"dowtls ttea.m:"0 LHigh .DevilLCartyoo.Thi sdanLwoul d be located just upstream from Portage Creek so as not to interfere with the anadromous fisheries,and would have a crest elevation of 1,030 and an installed capacity of 150 .J. 1 I j 851104 B-I-I6 851104 MW.For purposes of these studies,this site is referred to as the Portage Creek site. 1.5 -Evaluation of Basin Development Plans (*) The overall objective of this step in the evaluation process was to select the preferred basin development plan.A preliminary evaluation of plans was initially undertaken to determine broad comparisons of the available alternatives.This was followed by appropriate adjustments to the plans and a more detailed evaluation and comparison. In the process of initially evaluating the final four schemes,it became apparent that there would be environmental problems associated with allowing daily peaking operations from the most downstream reser- voir in each of the plans described above.In order to avoid these potential problems while still maintaining operational flexibility to peak on a daily basis,re-regulation facilities were incorporated in the four basic plans.These facilities incorporate both structural measures such as re-regulation dams and modified operational pro- cedures.Details of these modified plans,referred to as El to E4,are listed in Table B.l.5.l. The plans listed in Table B.I.5.1 were subjected to a more detailed analysis as described in the following section. 1.5.1 -Evaluation Methodology (*) The apprnach to evaluating the various basin development plans described above is twofold: o For determining the optimum staging concept associated with each basic plan (i.e.,the optimum subplan),only economic criteria are used and the least-cost staging concept is adopted. o For assessing which plan is the most appropriate,a more detailed evaluation process incorporating economic, environmental,social and energy contribution aspects is taken into account. Economic evaluation of any Susitna basin development plan requires that the impact of the plan on the cost of energy to the Railbelt area consumer be assessed on a systemwide basis.Since the consumer is supplied by a large number of different generating sources,it is necessary to determine the total Railbelt system cost in each case to compare the various.Susitna basin development options. B-1-17 851104 The primary tool used for system costs was the mathematical model developed by the Electricity Utility Systems Engineering Department of General Electric Company.The model is commonly known as OGP5 or Optimized Generation Planning Model,Version 5. The following information is paraphrased from GE literature on the program (General Electric 1979). The OGP5 program was developed over ten years to combine the three main elements of generation expansion planning (system reliability,operating and investment costs)and automate generation addition decision analysis.OGP5 will automatically develop optimum generation expansion patterns in terms of economics,reliability and operation.Many utilities use OGP5 to study load management,unit size,capital and fuel costs,energy storage ,forced outage rates,and forecast uncertainty.· The OGP5 program req uires an extensive system of specific da ta to perform its planning function.In developing an optimal plan, the program considers the existing and committed units (planned and under construe tion)available to the system and the characteristics of these units including age,heat rate,size and Clutage rates a.s the ba.se generation plan.The program then considers the given load forecast and operation criteria to determine the need for additional system capacity based on given reliabil.ity criteria.This determines "how much"capacity to add and "when"it should be installed.If a.need exists during any monthly iteration,the program will consider additions from a list of alternatives and select the available unit best fitting thesy s~tejjCiiEH:fds·~·····Un1 tSE!lEtcthm-is~-m1:l(:le-·by-coIl1puting~pr oduction~ costs for the system for each alternative included and comparing the results. The unit resulting in the lowest system production cost is selected and added to the system.Finally,an investment cost analysis of the capital costs is completed to answer the question of "what kind"of generation to add to the system. _~......~~__.!h.e_mo_d_e_l is then further used to compare alternative pJans for. meeting variable electrical demands,based on system reliability and production costs for the study period. A minor limitation inherent in the use of the OGP5 model is that the number ·of years of simulation is limited to 20.To overcome this,the study period of 1980 to 2040 has been broken into three separate·segtnents for study purposes.These.segments.are COlIlIllOn to all system generation plans.· The first segment has been assumed to be from 1980 to 1990.The model of this time period included all committed generation units and is assumed to be common to all generation scenarios. B-1-18 I ] .J ) 1 1 J 1 851104 ,I The end point of this model becomes the beginning of each 1990-2010 model. The model of the first two time periods considered (1980 to 1990, and 1990 to 2010)provides the total production costs on a year-to-year basis.These total costs include,for the period of modeling,all costs of fuel and operation and maintenance of all generating units included as part of the system.In addition, the completed production costs include the annualized investment costs of any production plans added during the period of study. A number of factors which contribute to the ultimate cost of power to the consumer are not included in this model.These are common to all scenarios and include: o All investment costs to plants in service prior to 1981; o Costs of transmission systems in service both at tha transmission.and distribution level;and o Administrative costs of utilities for providing electric service to the public. Thus,it should be recognized that the production costs modeled represent only a portion of ultimate consumer costs and in effect are only a portion,albeit major,of total costs. The third period,2010 to 2040,was modeled by assuming that production costs .of 2010 would recur for the additional 30 years to 2040.This assumption is believed to be reasonable given the limitations on forecasting energy and load requirements for this period.The additional period to 2040 is required to at least take into account the benefit derived or value of the addition of a hydroelectric po~er plant which has a useful life of 50 years or more. The selection of the preferred generation plan is based on numerous factors.One of these is the cost of the generation plan.To provide a consistent means of assessing the production cost of a given generation scenario,each production cost total has been converted to a 1980 present worth basis.The present worth cost of any generation scenario is made up of three cost amounts.The first is present worth cost (PWC)of the first ten years of study (1981 to 1990),the second is the PWC of the scenario assumed during 1990 to 2010,and the third is the PWC of the scenario in 2010 assumed to recur for the period 2010 to 2040.In this way the long-term (60 years)PWC of each generation scenario in 1980 dollars can be compared. A summary of the input data to the model and a discussion of the results follow. B-1-19 (a)Initial Economic Analyses (*) Table B.I.5.2 lists the results of the first series of economic analyses undertaken for the basic Susitna basin development plans listed in Table B.l.5.l.The information provided includes the specified on-line dates for the various stages of the plans,the OGP5 run index number,the total installed capacity at year 2010 by category,and the total system present worth tost in 1980 for the period 1980 to 2040.Matching of the Susitna development to the load growth for PlansEl,E2,and E3 is shown in Figures B.l.5.1, B.l.5.2 and B.l.5.3,respectively.After 2010,steady state conditions are assumed and the then-existing generation mix and annual costs for 2010 are applied to the years 2011 to 2040.This extended period of~time is necessary to ensure that the hydroelectric o~tions being studied,many of which only come on line around 2000,are simulated as operating for periods approaching their economic lives and that their full impact on the cost of the generation system is taken into account. J I "j- 1 (i)Plan El -Watana/Devil Canyon (*) Staging the dam at Watana (Plan El.2)is not as economic as constructing it to its full height (Plan El.1 and El.3).The present worth advantage of not staging the dam amounts to $180 million in 1980 dollars. The results indicate that,with the level of analysis performed,there is no discernible benefit in staging construction of the Watana powerhouse (Plan E1.l and EL3).However,Plan El.4 results indicate that, should the powerhouse size at Watana be restricted to 400 MW,the overall system present worth costs would increase. Additional runsJ:)erformed for variations ofplan~El ..3_ indicate that system present worth would increase by $1,110 million if the Devil Canyon Dam were not constructed.A five-year delay in construction of the Watana Dam would increase system present worth by $220 million. ,l 1 1 851104 -_ucnLPlan E2--~High D-evir-CanY9ii/V€!eI-kr--- The res Ul.!iS for plan E2 .3:cndTcate t ha t the sy stem present worth is $520 million more than Plan El.3. Present worth increases also occur if the Vee Dam B-1-20 ~I I. I stage is not constructed.A reduction in present worth of approximately $160 million is possible if the Chakachamna hydroelectric project is constructed instead of the Vee Dam. The results of Plan E2.1 indicate that total system present worth would increase by $250 million if the total capacity at High Devil Canyon were limited to ~O~. (iii)Plan E3 -Watana-Tunnel (*) The results for Plan E3.1 illustrate that the tunnel scheme versus the Devil Canyon Dam scheme (E1.3) adds approximately $680 million to the total system present worth cost.The availability of reliable geotechnical data would undoubtediy have improved the accuracy of the cost estimates for the tunnel alternative.For this reason,a sensitivity analysis was made as a check to determine the effect of halving the tunnel costs.This analysis indicates that the tunnel scheme is still more costly than constructing the Devil Canyon Dam. (iv)Plan E4 -Watana/High Devil Canyon/Portage Creek (*) The results indicate that system present worth associated with Plan E4.l,excluding the Portage Creek site development,is $200 million more than the equivalent El.3 plan.If the Portage Creek development is included,the present worth difference would be even greater. (b)Load.Forecast Sensitivity Analyses (*) The plans with the lowest present worth cost were subjected to further sensitivity analysis.The objective of the analysis was to determine the impact on the development decision of a variance in forecast.The load forecasts used for this analysis were made by ISER and are presented in Section 5.4.5 of this Exhibit.These results are summarized in Table B.l.5.3. At the low load forecast,full capacity development of Watana/Devil Canyon Scheme 1.3 is not warranted.Under Scheme 1.4,the most economic development includes a 400-~ development at each site,as compared to Watana only. Similarly,it is more economic to develop High Devil Canyon and Vee,as compared to High Devil Canyon only,but at a total capacity of only 800 ~. 851104 B-1-21 \ At this level of projected demand,the Watana/Devil Canyon plan is more economic than the High Devil Canyon/Vee plan or any singular development ($210 million,present worth ba- sis).As individual developments,however,the High Devil Canyon only plan is slightly superior economically to the Watana project ($90 million,present worth basis). At the high load forecast,the larger capacities are clearly needed.In addition,both the High Devil Canyon/Vee and Watana/Devil Canyon plans are improved economically by the addition of the Chackachamna project.This illustrates the superiority of the Chackachamna project to the addition of alternative coal and gas projects using the study price pro- jections.Similar to the low load forecast,the Wa tana/ Devil Canyon project is superior to the High Devil Canyon/ Vee alternative but the margin of difference on "a-present worth basis is much greater ($1.0 billion,present worth basis)• 1.5.2 -Evaluation Criteria (*) The following criteria were used to evaluate the short-listed basin development plans.These criteria generally contain the requirements of the generic process with the exception that an additional criterion,energy contribution,is added ,in order to ensure that full consideration is given to the total basin energy potential developed by the ~arious plans. (a)Economic (*) Plans were compared using lotig;;.;tetm present worth cos ts, calculated using the OGP5 generation planning model.The parameters used in calculating the total present worth cost of the total RaUbel t generating system for the period 1980 to 2040 are listed in Tables B.1.5.4 and B.l.5.5.Load forecasts used in the analysis are presented in Section (b)Environmental (*) A qualitative assessment of the environmental impact on the ecological,cultural,and aesthetic resources is undertaken for each plan.Emphasis is placed on identifying major concerns so that these can be combined with the other ·€!V~ill'iJat:io·ll.··ifttribut'esin:an overall assessment of the plan. (c)Social (*) This attribute includes determination of the potential nonrenewable resource displacement,the impact on the ;1 !'jI. I,. J - I 1 1 ;..j 1J ~I "1 1"( ,I 851104 B-1-22 ,I state and local economy,and the risks and consequences of major structural failures due to seismic events.Impacts on the economy refer to the effects of an investment plan on economic variables. (d)Energy Contribution (*) The parameter used is the total amount of energy produced from the specific development plan.An assessment of the energy development foregone is also undertaken.The energy loss that is inherent to the plan and cannot easily be recovereu by subsequent staged developments is of greatest concern. 1.5.3 -Results of Evaluation Process~*) The various attributes outlined above have been determined ·for each plan and are summarized in Tables B.1.5.6 through B.1.5.14.Some of the attributes are quantitative while others are qualitative.Overall evaluation is based on a comparison of similar types of attributes for each plan.In cases where the attributes associated with one plan all indicate equality or superiority with respect to another.plan,the decision as to the best plan is clear cut.-·In other cases where some attributes indicate superiority and others inferiority,differences are highlighted and trade-off .decisions are made to determine the preferred development plan.In cases where these trade-offs have had to be made,they were relatively straightforward,and the decision-making process can therefore be regarded as effective and consistent.In addition,these trade-offs are clearly identified so that independent assessment can be made. The overall evaluation process is conducted in 'a series of steps. At each step,only two plans are compared.The superior plan is then taken to the next step for evaluation against a third plan. J 851104 (a)Devil Canyon Dam Versus Tunnel (*) The first step in the process involves the comparison of the Watana/Devil Canyon Dam plan (E1.3)and the Watana-tunnel plan (E3.1).Since Watana is common to both plans,the evaluation is based on a comparison of the Devil Canyon Dam and the Scheme 3 tunnel alternative. In order to assist in the evaluation in terms of economic criteria,additional information obtained by analyzing the results of the OGP5 computer runs is shown in Table B.1.5.6. This information illustrates the breakdown of the total system present worth cost in terms of capital investment, fuel,and operation and maintenance costs. B-1-23 I) 851104 (i)Economic Comparison (*) From an economic point of view,the Watana/Devil Canyon Dam scheme is superior.As summarized in Tables B.l.s.6 and B.l.s.7,on a present worth basis the tunnel scheme is $680 million more expensive than the dam scheme.For a low demand growth rate,this cost difference would be reduced slightly to $650 million.Even if the tunnel scheme costs are halved, the total cost difference would still amount to $380 million.As highiighted in Table B.lo5.7, consideration of the sensitivity of the basic economic evaluation to potential changes in capital cost estimates,the period of economic analysis,the. discount rate,fuel costs,fuel cost escalation,and economic plant life do not change the basic econ~ic superiority of the dam scheme over the tunnel scheme. (ii)Environmental Comparison (*) The eIlvironlIlental comparison of the two schemes is summarized in Table B.1.5.8.Overall,the tunnel scheme is judged to be superior because: o It offers the potential for enhancing anadromous fish populations downstream of the re-regulation dam due to the more uniform flow -distribution that will be-achi-eved-in this reach; o It would inundate 13 miles less of resident fisheries habitat in the river and major tributaries; o It has a lower potential for inundating .a rch eologicaL.sites.due__to_the_smaUer . ..reservoir involved;_and_______~_ o It would preserve much of the characteristics of the Devil Canyon gorge which is considered to be an aesthetic and recreational resource. (iii)Social Comparison (*) --Table B..l.s.9summarizes the eval-uation of the two ~_."~_.•..._-_...••._.-."..--.---_.....~--. schemes in terms of the social cri teria.In terms of impact on state and local economics and risks because of seismic exposure,the two schemes are rated equal. However,due to its higher energy yield,the dam B-1-24 " .~-. 1.-:, \ ) I L scheme has more potential for displacing nonrenewable energy resources and therefore has a slight overall advantage in terms of the social evaluation criteria. (iv)Energy Comparison (*) Table B.I.S.IO summarizes the evaluation in terms of the energy contribution criteria.The results show that the dam scheme has a greater potential for energy produc tion and develops a larger portion of the basin's potential.The dam scheme is therefore judged to be-superior from the energy contribution standpoint. (v)Overall Comparison (*) The overall evaluation of the two schemes is· summarized in Table B.I.S.II.The estimated cost saving of $680 million in favor of the dam scheme plus the additional energy produced are considered to outweigh the reduction in the overall environmental impact of the tunnel scheme.The dam scheme is therefore judged to be superior overall. (b)Watana/Devil Canyon Versus High Devil Canyon/Vee (*) The second step in the development selection process -in- volves an evaluation of the Watana/Devil Canyon (EI.3)and the High Devil Canyon/Vee (E2.3)·development plans. I (0 Economic Comparison (*) In terms of the economic criteria (see Table B.I.S.6 and B.I.S.7)the Watana/Devil Canyon plan is less costly by $520 million.Consideration of the sensitivity of this decision to potential changes in the various parameters considered (i.e.,load forecast,discounted rates,etc.)does not change the basic superiority of the Watana/Devil Canyon plan. Under the low load-growth forecast,the Watana/Devil Canyon plan is favored by only $210 million,while under the high load-growth forecast the advantage is $1,040 million. 851104 (ii)Environmental Comparison (*) The evaluation in terms of the environmental criteria is summarized in Table B.I.S.12.In assessing these B-I-2S plans,a reach-by-reach comparison was made.for the section of the Susitna River between Portage Creek and the Tyone River.The Watana/Devil Canyon scheme would create more potential.environmental impacts in the Watana Creek area.However,it is judged that the potential environmental impacts which would occ ur above the Vee Canyon Dam with a High Devil Canyon/Vee development are more severe in overall comparison. Of the seven environmental factors considered in Table B.l.S.12,except for the increased loss of river valley,bird and black bear habitat,the Watana/Devil Canyon development plan is judged to be more environmentally acceptable than the High Canyon/Vee plan. The other six areas in which Watana/Devil Canyon was judged to be superior are fisheries,moose,caribou, furbearers,cultural resources,aesthetics,and land use. (iii)Energy Comparison (*) The evaluation of the two plans in terms of energy contribution criteria is summarized in Table B.l.S.13.+he Watana/Devil Canyon scheme is assessed to be superior because of its higher energy potential and the fact that it develops a higher -proporfion o-f--Ehe DasTnrs-energy-pofentia.T~-- The Watana/Devil Canyon plan annually develops 1,160 GWh and 1,6S0 GWh more average and firm energy, respectively,than the High Devil Canyon/Vee plans. (iv)Social Comparison (*) ,.j J J -j l ..........o .__.•__Tab le-B.1.5.-9-8 umma·rcizes··t-he-evaluat-ion-in te·rms-of--·· ....._..___._........J:_b.!!_s_o_cia.l_cri.ter.ia_•._As-in_the-ca·s e--o.f--the--dam--···-·---·__·-·_···-· versus tunnel comparison,the Watana/Devil Canyon plan is judged to have a slight advantage over the High Devil Canyon/Vee plan.This is because of its greater potential for displacing nonrenewable resources.In other socia 1 impac t areas there are 1 minimal differences between plans.. (v)OveraU COIllparison ( The overall evaluation of the two schemes is summarized in Table B.1.S.14.The $S20 million I( 8S1104 B-1-26 estimated cost saving coupled with the lower environmental impacts and a marginal social"advantage make the Watana/Devil Canyon plan superior to High Devil Canyon/Vee. 1.6 -Preferred Susitna Basin Development Plan (**) One-on-one comparisons of the Watana/Devil Canyon plan with the Watana- tunnel plan and the High Devil Canyon/Vee plan are judged to favor the Watana/Devil Canyon plan in each case.The Watana/Devil Canyon plan was therefore selected as the preferred Susitna basin development plan. In May 1985,the Applicant concluded that a number of benefits would be derived from a modification of the Watana/Devil Canyon two-dam plan providing for completion of construction in three stages. Accordingly,the·Applicant has prepared al ternative facility designs and operation studies of a construction plan that permits construction in three stages:first,construction and operation of a facility at the Watana site with a dam elevation of 2,025 feet (Stage I);second, proposed Devil Canyon dam elevation of 1,463 feet (Stage II);and third,further elevation of the dam at the Watana facility to the 2,205 foot level proposed in the July 1983 License Application (Stage III). Although the three-stage construction plan will not alter the character of the fully completed project,staging construction in th~ee steps will accomplish certain desirable changes over the course of project development. The development of Watana to its full height results in concentration of expenditures in the early years of the Susitna Project.Completion of Watana Stage I at a 2,025 foot crest elevation would reduce the initial materials requirements and construction time.The result would be both a reduction in initial state financial commitments and improved opportunity for private financing.Moreover,stretching out the pace of development of project energy and capacity would permit a better matching of load growth and capacity available,thereby ensuring greater flexibility in responding to future ra tes of system growth. 851104 B-1-27 !J :l J ,I il- l J 1 ,,} "1 ,'~! f .i -(~-)-j l 1 ,I j 2 -ALTERNATIVE FACILITY DESIGN,PROCESSES AND OPERATIONS (*) 2.1 -Susitna Hydroelectric Development (0) As originally conceived,the Watana project initially comprised an earthfill dam with a crest elevation of 2,225 and 400 MW of generating capacity scheduled to commence operation in 1993.An additional 400 MW would be brought on line in 1996.At Devil Canyon,an additional 400 MW would be installed to commence operation in the year 2000.Detailed studies of each project have led to refinement and optimization of designs in terms of a number of key factors,including updated load forecasts and economics.Geotechnical and environmental constraints identified as a result of continuing field work have also greatly influenced the currently recommended design concepts. Plan formulation and alternative facility designs considered for the Watana and Devil Canyon developments are discussed in this section. Background information on the site charact-eristics as well as addition- al detail on the plan formulation process are included in the Support- ing Design Report of Exhibit F and the referenced reports. 2.2 -Watana Project Formulation (*) This section describes the evolution of the general arrangement of the Watana-Stages I &III projects which,together with the Devil Canyon project Stage II,comprises the development plan proposed.The process by which reservoir operating levels and the installed generating capacity of the power facilities were established is presented, together with the means of handling floods expected during construction and subsequent project operation. The main components of the Watana development are as follows: o Dam embankment o Diversion facilities o Spillway facilities o Outlet facilities o Emergency release facilities o Power facilities. A number of alternatives are available for each of these components and they can be combined in a number of ways.The following paragraphs describe the various components and methodology for the preliminary, intermediate,and final screening and review of alternative general arrangement of the components,together with a brief description of the selected scheme.This section presents the alternative arrangements studied for the Watana project. 851104 B-2-1 2.2.1 -Selection of Reservoir Level (0) The selected elevation of the Watana Dam crest is based on considerations of the value of the hydroelectric energy produced from the associated reservoir,geotechnical constraints on reservoir levels,and freeboard requirements.Firm energy, average annual energy,construction costs,and operation and maintenance costs were determined for the Watana development with dam crest elevations of 2,240,2,190,and 2,140.The relative value of energy produced in terms of the present worth of the long-term production costs (LTPWC)for each of these three dam elevations was determined by means of the OGP5 generation planning model described in Section 1 of this Exhibit.The physical constraints imposed on dam height and reservoir elevation by geotechnical considerations were reviewed and incorporated into the crest elevation selection process. Finally,freeboard.requirements .for the Probable Maximum Flood (PMF)and settlement of the dam after construction or as a result of seismic activity were taken into account. 1,j ~] '\ (a)Methodology (0) Firm and average annual energy produced by the Susitna development is based on 32 years of hydrological records. The energy produced was determined by using a multi-reser- voir simulation of the operation of the Watana and Devil Canyon reservoirs.A variety of reservoir drawdowns was examined,an~drawdowns producing the maximum firm energy consi~tent w~th~!lgin~~.!~l:J:g~fea.~ibilitLandcost of the intake structure were selected.Minimum floW-requirements were established at both project sites based on downstream fisheries considerations. To meet system demand,the required maximum generating capability at Watana in the period between 1994 and 2010 ranges from 665 MW to 908 MW.For the reservoir level determinations,energy estimates were made on the basis of asslimed·-averageannual··capacity .requi-rementsof-680·····MW··at ...................__..----Wat·ana-in---l-99 4,-increasing·t-o-l-,-020-·MW--at-Wa·t-ana---i-n--20 07-,---· with an additional 600 MW at Devil Canyon coming on line in the year 2002.The long term present worth costs of the generation system required to meet the Railbelt energy demand were then determined for each of the three crest elevations of the Watana Dam using the OGP5 model. The construction cost estimates·usedin the OGP5·mo<:leling proces sfor··l:heWal:anaand .Devil Canyon proJect sViere based on preliminary conceptual layouts and construction schedules.Further refinement of these layouts has taken place during the optimization process.These refinements I 851104 B-2-2 j have had no significant impact on the reservoir level selection. (b)Economic Optimization (*) Economic optimization of the Watana reservoir level was based on an evaluation of three dam crest elevations of 2,240, 2,190,and 2,140.These crest elevations applied to the central portion of the embankment with appropriate allowances for freeboard and seismic settlement,and correspond to maximum operating levels of the reservoir of 2,215, 2,165,and 2,115 feet,respectively.Average annual energy calculated for each case using the reservoir simulation model are given in Table B.2.2.l,together with corresponding project construction costs. In the determination of LTPWC,the Susitna capital costs were adjusted to include an allowance for interest during construction and then used as input to the OGP5 model. Simulated annual energy yields were distributed on a monthly basis by the reservoir operation model to match as closely as possible ~~e projected monthly energy demand of the Railbelt and 'then input to t]:1e QGP5 model.The LTPWC of meeting the Railbelt energy demand using the Susitna development as the primary source of energy was then determined for each of the three reservoir levels. The results of t~ese evaluations are shown in Table B.2.2.2, and a plot showing the variation of theLTPWC with dam crest elevation is shown in Figure B.2.2.1.This figure indicates that,on the basis of the assumptions used,the minimum LTPWC occurs at a Watana crest elevation ranging from approximately 2,160 to 2,200 (reservoir levels 2,140 to 2,180 feet).A higher dam crest will still result in a development which has an overall net economic benefit relative to thermal energy sources.However,it is also clear that,as the height of the Watana Dam is increased, the unit cost of additional energy produced at Watana is somewhat greater than for the displaced thermal energy source.Hence,the LTPWC of the overall system would increase.Conversely,as the height of the dam is lowered, and thus Watana produces less energy,the unit cost of the energy produced by a thermal generation source to replace the lost Susitna energy is higher than that of Susitna. In this case also,the LTPWC increases. 851104 B-2-3 I (c) (d) Relict Channel (**) On the north side of the reservoir created by the Watana Dam,an infilled relict channel,reaching a depth of 400 feet,exists between the reservoir and Tsusena Creek.A potential problem caused by the relict channel involves subsurface seepage resulting in potential downstream piping and/or loss of wa ter from the reservoir.Details of the geology and potential impacts of the relict channel are addressed in Exhibits A and F.In response to these potential seepage problems,$57,100,000 have been provided in the cost estimate for the construction of a downstream toe drain during Stage I and a slurry trench cutoff across the buried channel thalweg during Stage III.The Stage I pool (el.2,000)is 185 feet low.er than Stage III (el. 2,18S);therefore minimal remedial measures have been programmed,including observation device monitoring,during this period. Conclusions (0) tt is important to establish clearly the overall objective used as a basis for setting the Watana reservoir level.An objective which would minimize the LTPW energy cost would lead to selection of a slightly lower reservoir level than an objective which would maximize the amount of energy which could be obtained from the available resource,while doing so with a technically sound project. , 1 ,r j Ij The three values of LTPWC developed by the OGPS computer runs defined a relationship betweenLTPWCand Watana Dam height which is relatively insensitive to dam height.This is highlighted by the curve ·of LTPWCversus dam height in Figure B.2.2.1.This figure shows that there is only a slight variation in the LTPWC for the range of dam heights included in the analysis.Thus,from an economic ........_.......standpoint.,...the-opt-imum--c.rest--eleva·t·ion-could-becons-idered ___..__..__as_v:a.r~dng._oJl.e.r __a....Iange_.o.:L.eleYations--fr.om-2-,.140-.to.-2-,-220-. with little effect on project economics. The normal maximum operating level of the reservoir was therefore set at elevation 2,185,allowing the objective of maximizing the economic use of the Susitna resource still to be satisfied. I .! Ij 8S1104 B-2-4 .J 2.2.2 -Selection of Installed Capacity (*) The generating capacity to be installed at both Watana and Devil Canyon was determined on the basis of generation planning studies together with appropriate consideration of the following (Acres 1982c,Vol.1): o Available firm and average energy from Watana and Devil Canyon; o The forecast energy demand and peak load demand of the system; o Available firm and average energy from other existing and committed plant; o Capital cost and annual operating costs for Watana and Devil Canyon; o Capital cost and annual operating costs for alternative sources of energy and capacity; o Environmental constraints on reservoir operation;and o Turbine and generator operating characteristics. Table B.2.2.3 lists·the design parameters used in establishing the dependable capacity at Watana. (a)Installed Capacity (*) A computer simulation of reservoir operation over 32 years of hydrological record was used to predict firm (dependable) and average energy available from Watana and Devil Canyon reservoirs on a monthly basis.Seven alternative reservoir operating rules were assumed,varying from a maximum power generation scenario which would result in significant impact on downstream fisheries through to a scenario that provides guaranteed minimum summer releases which minimize the impact on downstream fisheries.For the preliminary design, predicted energies from a moderate flow case,referred to as Case C,have been used to assess the required plant capacity. The computer simulation gives an estimate of the monthly energy available from each reservoir,but the sizing of the plant capacity must take into account the variation of demand load throughout each month on an hourly basis.Load forecast studies have been undertaken to predict the hourly variation of load through each month of the year and also 851104 B-2-5 the growth in peak load (MW)and annual energy demand (GWh) through the end of the planning horizon (2010). The economic analysis for the proposed development assumes that the average energy from each reservoir is availab Ie every year.The hydrological record,however,is such that this average energy is available only from a series of wetter and drier years.In order to utilize.the average energy,capacity must be available to generate the energy available in the wet years up to the maximum requirement dictated by the system energyciemand,less any energy available from other committed hydroplants. Watana has been designed to operate as a peaking station,if required.Tables B.2.2.4 and B.2.2.S show the estimated maximum capacity required in the peak demand month (December)at Watana to fully utilize the energy available from the flows of record.If no thermal energy is needed (i.e.,in wetter years),the maximum requirement is contrplled only.b.¥_the shape of the.demand curve •If thermal energy is required (in average to dry years),the maximum capacity required at Watana will depend on whether the thermal energy is provided by high merit order plant at base load (Option 1,Table B.2.2.4),or by low merit order peaking plant (Option 2,Table B.2.2.S). On the basis of this evaluation,the ultimate power generation capability at WataGa was selected as 1,020 MW for cl~sJgIJ,P1.l_l:'PQl:l~~..~o CiUQ~aIIlCil:'g ~J,l JQl:'hYcll:'Q_~pJl1J,li!lgl:'~s~:.rv ~ and standby for forced outage.This installation also provides a margin in the event that the load growth exceeds the medium load forecast. (b)Unit Capacity (*) Selection of the unit size for a given total capacity is a compromise between the initial least-cost solution, ---------·····-·-g-en-erallyinvotV'inga-schemewi"t1:1asmaller-ntimberr ·0 f-1 arge -.-----..--..-.-.c-a-pa-c-i-ty--uni-ts-,-and-the----{-mproved-p-l-an-t--e-fficiency--and---·---- security of operation provided by·a larger number of smaller capacity units.Other factors include the size of each unit as a proportion of the total system.load and the minimum anticipated load on the station.Any requirement for a minimum downstream flow would also affect the selection. Growth of the actual -load.demand is-also a significant factor,since the installationofcunits maybe phased to ......c __mat.ch .t.he-acfua-l-l oad-growEh .---The-numb er-of--tiriiEsaiid lih ei r individual ratings were determined by the need to deliver the required peak capacity i.n the.peak demand month of 'j ] 851104 B-2-6 J December at the minimum December reservoir level with the turbine wicket gates fully open. An examination was made of the economic impact on power plant production costs of various combinations of a number of units and rated capacity which would provide the selected total capacity of 1,020 MW.For any given installed capacity,plant efficiency increases as the number of units increases.The assumed capitalized value used in this evaluation was $1.00 per average annual kWh over project life,based on the economic analysis completed for the thermal generation system.Variations in the number of units and capacity will affect the cost of the power intakes,penstocks,powerhouse,and tailrace.The differences in the~e capital costs were estimated and included in the evaluation.The results of this analysis are presented below. Capitalized Rated Value of Number Capacity Additional Additional of of .Unit Energy Capital Cost Net Benefi t Units (MW)($Millions)($Millions)($Millions) 4 250 6 170 40 31 9 8 125 56 58 -8 It is apparent from this analysis that a six-unit scheme with a net benefit of approximately $9 million is the most economic alternative.This scheme also offers a higher degree of flexibility and security of operation compared to the four-unit alternative,as well as advantages .if unit installation is phased to match actual load growth.The net economic benefit of the six-unit scheme is $17 million greater than that of the eight-unit scheme,while at the same time no significant operational or scheduling advantages are associated with the eight-unit scheme. A scheme incorporating six units,each with a rated capacity of 170 MW,for a total of 1,020 MW,has been adopted for all Watana alternatives. 2.2.3 -Selection of the Spillway Design Flood (*) Normal design practice for projects of this magnitude,together with applicable design regulations,requires that the project be capable of passing the Probable Maximum Flood (PMF)routed through the reservoir without endangering the dam. .:: 851104 B-2-7 In addition to this requirement,the project should have sufficient spillway capacity to safely pass a major flood of lesser magnitude than the PMF without damaging the main dam or ancillary structures.The frequency of occurrence of this flood, known as the spillway design flood or Standard Project Flood (SPF),is generally selected on the basis of an evaluation of the risks to the project if the spillway design flood is exceeded, compared to the costs of the structures required to safely discharge the flood.For this study,a spillway design flood with a return frequency of 1:10,000 years was selected for Watana.A list of spillway design flood frequencies and magnitudes for several major projects is presented below. Additional capacity required to pass the PMF be provided by "an emergen'cy 'spillwayconsis'fing"of"'afuse'p[ug'aiid rOCK channel on the right bank. j 'j J .1 ] ] 1 .1 1 Inflow Peak 326,000 cfs 1$6,000 cfs B-2-8 1:10,000 years Frequency Probable Maximum Spillway Design Flood 851104 I I Spillway Spillw9-Y Design Flood I Basin ..I Capacity I Peak I EMF"IAfter Routing Project Frequency l!nfleM'(cfs)I (cfs)1 (cfs)* I I I Mica,Canada :EMf 1 250,000 1 250,000'1 150,000 I 1 I Churchill'Falls,I 1 I Canada 1:10,000 1 600,000 11,000,000 I 230,000 I I I New Bullards,USA EMF I 226,000 I 226,000 I 170,000 I I I Oroville,USA 1:10,000 I 440,500 I 711,400 I 440,500 I I I - - --~-~------_._---_.....•.__.--Gui:i,Venezuela' (final stage)PMF I 1,000,000 11,000,000 1,000,000 I I I Itaip.1,Brazil EMF 1 2,195,000 12,195,000 I 2,105,000 I 1 I Sayano,USSR 1:10,000 I 480,000 1 N/A 1 680,000 *All spillways except Sayano have capacity to pass PMF with 2.2.4 Main Dam Alternatives (*) This section describes the alternative types of dams considered at the Watana site and the basis for the selected alternative. (a)Comparison of Embankment and Concrete Type Dams (0) The selection between an embankment type or a concrete type dam is usually based on the configuration of the valley,the condition of the foundation rock,depth of the overburden,and the relative availability of construction materials.Previous studies by the CaE envisaged an embankment dam at Watana.Initial studies completed as part of this current evaluation included comparison of an earthfi11 dam with a concrete arch dam at the Watana site. An arrangement for·a concrete arch.dam alternative at Watana is presented in Figure B.2.2.2.The results of this analysis indicated that the cost of the embankment dam was somewhat lower than.the arch dam,even though the concrete cost rates used were significantly lower than those used for the Devil Canyon Dam.This preliminary evaluation did not indicate any overall cost savings in the project in spite of some savings in the earthworks and concrete structures for the concrete dam layout.A review of the overall construction schedule indicated a minimal savings in time for the concrete dam project. Based on the above and the likelihood that the cost of the arch dam would increase relative to that of the embankment dam,the arch dam alternative was eliminated from further considera tion. j 851104 (b)Concrete Face·Rockfi11 Type Dam (*) The selection of a concrete facerockfill dam.at Watana would appear to offer economic and schedule advantages when compared ~o a conventional impervious-core rockfi11 dam. For example,one of the primary areas of concern with the earth-core rockfill dam is the control of wa ter content for the core material and the available construction period during each summer.The core material will have to be protected against frost penetration at the end of each season and the area cleared and prepared to receive new material after each winter.On the other hand,rockfi11 materials can be worked almost year-round and the quarrying and placing/compacting operations are not affected by rain a~d only marginally by winter weather. The.eoncrete face rockfi11 dam would also require less ------foundation preparation,since the critical foundation contact area is much less than that for the impervious- B-2-9 core/rock foundation contact.The side slopes for faced rockfill could probably be on the order of 1.5H:1V·or steeper as compared to the 2.5 and 2.0H:1V for the earth:"core rockfill.This would allow greater flexibility for layout of the other facilities,in particular the upstream and downstream portals of the diversion tunnels and the tailrace tunnel portals.The diversion tunnels could be shorter,giving further savings in cost and schedule. However,the ultimate heightdf theWatafla Dam as currently proposed is 885 feet,some 70 percent higher 'than the highest concrete face rockfill dam buil tto date (the 525-foot high Areia Dam in Brazil completed in 1980).A review of concrete face rockfill dams indicates that increases in height have been typically in the range of 20 percent;for example,Paradela -370 feet completed in 1955; Alto Anchicaya -460 feet completed in 1974;Ar,eia -525 feet completed in 1980.Although recent compacted rockfill dams have generally performed well and a rockfill dam is inherently stable even with severe leakage through the face, a one-step increase in height of 70 percent over existing structures is well beyond precedent. In addition to the height of the dam,other factors which are beyond precedent include the seismic and climatic conditions at Susitna.It has been stated that concrete face rockfill dams are well able to resist earthquake forces and it is admitted that they are very stable structures in th~ml!~lv.§~•__lloweYE:!!",__moyemE:!l1J:oJ~:t"Q.c::~_'l~ad:i.-l1g~9 .fl:lUllre of the face slab near the base of the dam could resul t in excessive leakage through the dam.To correct such an occurrence would require lowering the water level in the reservoir which would take many years and involve severe economic penalties from loss of generating ci:lpacity. No concrete face rockfill daIll has yet been built in an arctic environment.The drawdown at Watana is in excess of ...------------------lOO'·-fe-~fta1:ia-tne-upJ.:j'e-i:'---sEn::t-i:'()n-of-the-fa-ce--sl-a;b .wi:'ll--be -.-subjec-ted--to--severefreeze-!-thaw-cy c-J:es.- Although the faced rockfill dam appears to offer schedule advantages,the overall gain in impoundment schedule would not be so significant.With the earth-core rockfill dam, impoundment can be allowed as the dam is constructed.This is not the case for a concrete face rockfill since the concrete face slab is normally not constructed until all 'rockfill has beenpraced'ai:id'Corisfr~ucfioi:isettlement has taken place.The slab is then poured in continuous strips from the foundation to the crest.Most recent high faced rock-fill dams also incorporate an impervious earth fill cover over the lower section to minimize the risk of ,] ,'j -- .j 'J 'j 851104 B-2-10 )excessive leakage through zones which,because of their depth below normal water level,are difficult to repair. Such a zone at Watana might cover the lower 200 to 300 feet of the slab and require considerable volumes of impervious fill,none of which could be placed until all other construction work had been completed.This work would be on the critical path with respect to impoundment and,at the same time,be subject to interference by wet weather. The two types of dam were not cos ted in detail because cost was not considered to be a controlling factor.It is of interest to note,however,that similar alternatives were estimated for the LG 2 project in northern Quebec and the concrete face alternative was estimated to be about 5 percent cheaper.-However,the managers,on the recommenda- tion of their consultants~decided against the use of a concrete face rockfill dam for the required height of 500 feet in that environment. In summary,a concrete face rockfill dam at Wal:ana is not considered appropriate as a firm recommendation for the feasibility stage of development of the Susitna project because of: o the 70 percent increase ~n height over precedent;and o the possible impacts of high seismicity and climatic conditions. (c)Selection of Dam Type (*) Selection of the configuration of the embankment dam cross section was undertaken within the context of the following basic considerations: o The availability of suitable construction materials within economic haul distance,particularly core material; o The requirement that the dam be capable of withstanding the effects of a significant earthquake shock as well as the static loads imposed by the reservoir and by its own weight; o The relatively limited construction season available for placement of compacted fill materials. The dam would consist of a compacted core protected by fine and coarse filter zones on both the upstream and downstream slopes of the core.The upstream and downstream outer supporting fill zones would contain relatively free draining 851104 B-2-11 851104 compa.cted gravel or rockfill,providing stability to the overall embankment structure.The location and inclination of the core are fundamental to the design of the embankment. Two basic alternatives exist in this regard: o A vertical core located centrally within the dam;and o An inclined core with both faces sloping upstream. A central vertical core was chosen for the embankment based on a review of precedent design and the nature of the available impervious mate.rial. The exploration program undertaken during 1980-81 indicated that adequate quantities of materials suitable for dam construction were located within rea:sonable haul distances from the site.The 'well-graded silty sand material is considered the most promising source of impervious fill. Compaction tests indicate a natural moisture content slightly on the wet side of optimum moisture content,so thai control of moisture contintwill be critical in "achfeving a dense""core with 'high "shear strength. Potential sources for the upstream and downstream shells include either river gravel·from borrow areas along the Susitna River or compacted rockfill from quarries or excavations for spillways. During the"intermediate review process·,··the upstream slope of the dam was flattened from 2.5H:IV used during the initial review to ~.75H:IV.This slope was based on a conservative estimate of the effective shear strength paramet'ers of the available construction materials,as well as a conservative allowance in the design for the effects of earthquake loadings on the dam • ....D~l:"iggt:J:J,~.fim3.J.l:"~.Yi?w:,§lt:.~g?,.t:1:1E:!.?~l:E:!l:"i.()l:"t:!P§ltl:"E:!gI:D."§lJQPg of the dam was steepened from 2.75H:IV to 2.4H:IV, reflecting-the··resul ts of thepre"timfnarystaticand-dy-namic design analyses being undertaken at the same time as the general arrangement studies.As part of the final review, the volume of the dam with an upstream slope of 2.4H:IV was computed for four alternative dam axes.The locations of these alternative axes are shown on Figure B.2.2.3.The dam ..voltuneassoclated with each of the~four alternative axes islistedbelow:·:····" I ] I 1 ,1 ,'] Alternative Axis Number 1 2 3 4 Total Volume (million yd 3 ) 69.2 71.7 69.3 71.9 A section with a 2.4H:1V upstream slope and a 2H:lV downstream slope located on alternative axis number 3 was used for the final review of alternative schemes. 2.2.5 Diversion Scheme Alternatives (*) The topography of the site generally dictates that diversion of the river during construction be accomplished using diver.sion tunnels with upstream and downstream cofferdams protecting the main construction area. The configuration of the river in the vicinity of the site favors location of·the diversion tunnels on the north bank,since the tunnel length for a tunnel on the south bank would be approximately 2,000 feet greater.In addition,rock conditions on the north bank are more favorable for tunneling and excavation of intake and outlet portals. (a)Design Flood for Diversion (*) The recurrence interval of the design flood for diversion is generally established based on the characteristics of the flow regime of the river,the length of the construction period for which diversion is required and the probable consequences of overtopping of the cofferdams.Design crit- eria and experience from other projects similar in scope and nature have been used in selecting the diversion design flood. At Watana,damage to the partially completed dam could be significant or,more importantly,would probably result in at least a one-year delay in the completion schedule.A preliminary evaluation of the construction schedule indicates that the diversion scheme would be required for four or five years until the dam is of sufficient height to permit initial filling of the reservoir.A design flood with a return frequency of 1:50 years was selected based on experience and practice with other major hydroelectric projects.This approximates a 90 percent probability that the cofferdam will not be overtopped during the five-year construction period.The diversion design flood together with average flow characteristics of the river significant to diversion are presented below: 851104 B-2-13 o Average annual flow o Maximum average monthly flow o Minimum average monthly flow o Design flood inflow (1:50 years) 7,990 cfs 42,800 cfs-(June) 570 cfs (March) 87,000 cfs I] 1 (b) (c) Cofferdams (*) For the purposes of establishing the overall general arrangement of the project and for subsequent diversion optimization studies,the upstream cofferdam section adopted comprises an embankment structure approximately 100 feet high placed in the dry. Diversion Tunnels (*) Concrete...lined tunnels and unlined rock tunnels were compared.Preliminary hydraulic studies indicated that the design flood routed through the diversion scheme would result in a design discharge of approximately 80,500 cfs. For conctete-linedtunnels,design velocities on the order of 50 ft/sec have been used in several projects.For unlined tunnels,maximum design velocities ranging from 10 ft/sec in good quality rock to 4 ft/sec in less competent material are typical.Thus,the volume of material to be excavated using an unlined tunnel would be at least 5 times that for a lined tunnel.The reliability of an unlined tunnel is more dependent on rock conditions than is a lined tunnel,particularly given the extended period during which -t-he-d-ivers-i-on--scheme--i-s-requir ed--to--operate.~""Based-on -these considerations,given a considerably higher cost,together with the somewhat questionable feasibility of four unlined tunnels with diameters approaching 50 feet in this type of rock,the unlined tunnels have been eliminated. The following alternative lined tunnel schemes were examined as part of this analysis. o Pressure tunnel with a free outlet o Pressure tunnel with a submerged outlet o Free flow tunnel ] ,] :-) ) (d)Emergency Release Facilities (*) The emergency release facilities influenced the number, -type ,andarrangement-ofthediver-sion--tunnels selected for the final scheme. At an early stage of the study,it was established that some form of low-level release facility was required to meet instream flow requirements during filling of the reservoir, and to permit lowering of the reservoir in the event of an 851104 B-2-14 I' I extreme emergency.The most economical alternative available would involve converting one of the diversion tunnels to permanent use as a low-level outlet facility. Since it would be necessary to maintain the diversion scheme in service during construction of the emergency facilities outlet works,two or more diversion tunnels would be required.The use of two diversion tunnels also provides an additional measure of security to the diversion scheme in case of the loss of service of one tunnel. The low-level release facilities will be operated for approximately three years during filling of the reservoir. Discharge at high heads usually requires some form of energy dissipation prior to returning the flow to the river.Given the space restrictions imposed by the size of the diversion tunnel,it was decided to utilize a double expansion system constructed within the upper tunnel. (e)Optimization of Diversion Scheme (*) Given the considerations described above relative to design flows,cofferdam configuration,and alternative types of tunnels,an economic study was undertaken to determine the optimum combination of upstream cofferdam height and tunnel diameter. Capital costs were developed for three heights of upstream cofferdam embankment with a 30-foot wide crest and exterior slopes of 2H:1V.A freeboard allowance of 5 feet for settlement and wave runup and 10 feet for the effects of downstream ice jamming on tailwater elevations was adopted. Capital costs for the 4,700-foot long tunnel alternatives included allowances for excavation,concrete liner,rock bolts,and steel supports.Costs were also developed for the upstream and downstream portals,including excavation and support.The cost of intake gate structures and associated gates was determined not to vary significantly with tunnel diameter and was excluded from the analysis. Curves of headwater elevation versus tunnel diameter for the various tunnel alternatives with submerged and free outlets are presented in Figure B.2.2.4.The relationship between capital cost and crest elevation for the upstream cofferdam is shown in Figure B.2.2.5.The capital cost for various tunnel diameters with free and submerged outlets is given in Figure B.2.2.6.The results of the optimization study are presented in Figure B.2.2.7 and indicate the following optimum solutions for each alternative. 851104 B-2-l5 I.. The cost studies indicate that a rel'atively small cost differential (~to 5 percent)separates the various alternatives for tunnel diameter from 30 to 35 feet. '!Wo free flow tunnels 32.5 Two pressure tunnels 30 69,000,000 66,000,000 68,000,000 1,595 1,555 1,580 Cofferdam Crest Elevation (ft)Total Cost ($) 35 Diameter Type of Tunnel (feet) '!Wo free flow turmels (f)Selected Diversion Scheme (*) An important consideration at this point is ease of cofferdam closure.For the pressure tunnel scheme,the invert of the tunnel entrance is below riverbed elevation, and once the tunnel is complete diversion can be accomplished with a closure dam section approximately 10 feel::high •The free flow tlinnel scheme-,howeVer,requires a tunnel invert approximately 30 feet above the riverbed level,and diversion would~involve an end-dumped closure section 50 feet high.The velocities of flows which would overtop the cQfferdam before the water levels were raised to reach the tunnel invert level would be prohibitively higher, resulting in complete erosion of·the c~fferdam,and hence ~···t1fe-d ua1~free ··f1ow~tun~ne l~;"scheme~cwa~s·d:ropp~e~d·'from consideration. Based on the preceding considerations,a combination of one pressure tunnel and one free flow tunnel (or pressure tunnel with free outlet)was adopted.This will permit initial diversion to be made using both tunnels,thereby simplifying the critical closure operation and avoiding potentially ............serious..delay.sinthe.schedule •.ThreeaLternati:v.es.-were .. ..........~_:r:.e.'::.eyal1la.t.e~.a.Lf.Q.LLows:__..__._~_._~..___.........._. Tunnel Diameter (feet) Upstream Crest Elevation (feet) Cofferdam Approximate Height (feet) 30 35 36 ··1595 1555- 1550 150·· ·flO 100 'J More detailed layout studies indicated that the higher cofferdam associated with the 30-foot diameter tunnel 851104 B-2-16 alternative would require locating the inlet portal further upstream into "The Fins"shear zone.Since good rock conditions for portal construction are essential and the 36-foot diameter tunnel alternative would permit a portal location downstream of "The Fins",this latter alternative was adopted.As noted in (e),the overall cost difference was not significant in the range of tunnel diameters considered,and the scheme incorporating two 36-foot diameter tunnels with an upstream cofferdam crest elevation of 1,550 was incorporated as part of the selected general arrangement. 2.2.6 Spillway Facilities Alternatives (*) As discussed in subsection 2.2.3 above,.the project has been designed to safely pass floods with the following return frequencies: ..: Flood Spillway Design Probable Maximum Frequency 1:10,000 years Inflow Peak (cfs) 156,000 326,000 Total Spillway Discharge (cfs) 120,000 150,000 Discharge of the spillway design flood will require a gated service spillway on either the left or right bank.Three basic alternative spillway types were examined: o Chute spillway with flip bucket o Chute spillway with stilling basin o Cascade spillway. Consideration was also given to combinations of these alternatives with or without supplemental facilities such as valved tunnels and an emergency spillway fuse plug for handling the PMF discharge. Clearly,the selected alternative utilizing one serv~ce spillway will greatly influence and be influenced by the project general arrangement. (a)Energy Dissipation (*) The two chute alternatives considered achieve effective energy dissipation either by means of a flip bucket which would direct the spillway discharge in the form of a free-fall jet into a plunge pool well downstream from the dam or a stilling basin at the end of the chute which would dissipate energy in a hydraulic jump.The cascade type spillway would limit the free-fall height of the discharge 851104 B-2-17 by utilizing a series of 20-to50-fpot steps down to river level,with energy dissipation at each step. All spillway alternatives were assumed to incorporate a concrete ogee type control section controlled by fixed- roller vertical lift gates.Chute spillway sections were assumed to be concret~-lined,with ample provision for air entrainment in the chute to prevent cavitation erosion,and with pressure relief drains and rock anchors in the foundation. (b)Environmental Mitigation (*) During development of the general arrangements for both the Watana and Devil Canyon Dams,a restriction was imposed on the amount of excess dissolved nitrogen permitted in the spillway discharges.Supersaturation oceurs when aerated, flows are subjected to pressures greater than 30 to 40 feet of head which forces excess nitrogen into solution.This occurs when wa;er is subj~cted to the high pressures that occur in'deepplunge pools or at large hydraulic jumps.The excess nitrogen would not be dissipated within the dowtlstreaIlfDevil Caiiyou'reSfervoif'and a DU:iTdiip of ni tfogeri concentration could occur throughout the body of water.It would eventually be discharged downstream from Devil Canyon with harmful effects on the fish population.On the basis of an evaluation of the related impacts and discussions with interested federal arid state agencies,spillway facilities were designed to limit discharges of water from either Wa:tana()r-Devil·~Ca:ny()ri-··thae-m·a:yc·b·e-cofuE:!~S\i:I;feysa:·tilratedwith ,. nitrogen to a recurrence period of not less than 1:50 years. 2.2.7 -Power FaciUtie§.Alte:rnatives (*) Selection of the optimum power plant development involved consideration of the following: o Geotechnical considerations o Number,type,size and setting of generating units o.Arrangement of intake and water passages o Environmental constraints..'_"''._"_",','_4"_'__,_,_,_'_______'_'__'__'_'_'.w··,~••"••._••._.,,__·_,_ ,.J ,1 \ ). I I 851104 B-2-18 .J 'j (a)Comparison of Surface and Underground Powerhouse (*) Studies were carried out to compare the construction costs of a surface powerhouse and of an underground powerhouse at Watana.These studies were undertaken on the basis of preliminary conce~tual layouts assuming four or six units and a total installed capacity of 840 MW.The comparative cost estimates for powerhouse civil works and electrical and mechanical equipment (excluding common items)indicated an advantage in favor of the underground powerhouse of $16,300,000.A summary comparison of the cost estimates for the two types of powerhouses is in Table B.2.2.6.The additional cost for the surface powerhouse arrangement is primarily associated with the longer penstocks and the steel linings required. The underground powerhouse arrangement is also better suited to the severe winter conditions in Alaska,is less affected by river flood flows in summer,.and is aesthetically less obtrusive.This arrangement has ..the1i.",efore been adopted for further development. (b)Comparison of Alternative Locations (*) Preliminary studies were undertaken during the development of conceptual project layouts at Watana to investigate both right and left bank locations for power facilities.The configuration of the site is ,such that south bank locations required longer penstock and/or tailrace tunnels and were therefore more expensive. The location on the south bank was further rejected because of indications that the underground facilities would be located in relatively poor quality rock.The underground powerhouse was therefore located on the north bank such that the major openings lay between the two major shear features ("The Fins"and the "Fingerbuster"). (c)Underground Openings (*) Because no construction adits or extensive drilling in the powerhouse and tunnel locations have been completed,it has been assumed that full concrete-lining of the penstocks and tailrace tunnels would be req.uired.This assumption is conservative and is for preliminary design only;in practice,a large proportion of the tailrace tunnels would probably be unlined,depending on the actual rock quality encountered. 851104 B-2-l9 The minimum center-to-center spacing of rock tunnels and caverns has been assumed for layout studies to be 2.5 times the width or diameter of the larger excavation. (d)Selection of Turbines (*) The selection of turbine type is governed by the available head and flow.For the design head and specific speed, Francis type turbines have been selected.Francis turbines have a reasonably flat load-efficiency curve over a range from about 50 percent to 115 percent of rated output with peak efficiency of about 92 percent. The number and rating of individual units is discussed in detail in subsection 2.2.2 above.The final selected arrangement comprises six units producing 170 MW each,rated at minimum reservoir level (from reservoir simulation studies)in the peak demand month (December)at full gate. The unit output at best efficiency and a rated head of 680 feet is 181 MW. (e)Transformers (*) The selection of transformer type,size,location and stepup rating is summarized below: o Single-phase transformers are required because of transport limitations on Alaskan roads and railways; o Direct transformation from 15 kV to 345 kV is preferred for overall system transient stability; o An underground transformer gallery has been selected for minimum total cost of transformers,cables,bus, and transformer losses;and o A grouped arrangement of three sets of three f:fingre;;;;pliase''fransfOrmers fOr'····e'acli·setOftwOiiiiifs h'a's'-b'e-en--s-e-tec't-e-d'-(-ato't-a-t-of-nine---t'ran-EffcH:mer's-)-tcf"" reduce the physical size of the transformer gallery and to provide a transformer spacing comparable with the unit spacing. ,I 'j ,l 851104 B-2-20 i,j (f)Power Intake and Water Passages (*) The power intake and approach channel are significant items in the cost of the overall power facilities arrangement.The size of the intake is controlled by the number and minimum spacing betw~en the penstocks,which in turn is dictated by geotechnical considerations. The preferred penstock arrangement comprises six individual penstocks,one for each turbine.With this arrangement,no inlet valve is required in the powerhouse since turbine dewatering can be performed by closing the cantrolgate at the intake and qraining the penstocks and scroll case through a valved bypass to the tailrace.An alternative arrangement with three penstocks was considered in detail to assess any possible advantages.This scheme would require a bifurcation and two inlet valves on each penstock and extra space in the powerhouse to accommodate the inlet valves. Estimates of relative cost differences are summarized below: Item Cost Difference ($x 106) 6 Penstocks 3 Penstocks Total Intake Penstocks Bifurcations Valves Powerhouse Capitalized Value of Extra Head Loss Base Case o o o o o o -20.0 -3.0 +3.0 +4.0 +8.0 +6.0 -2.0 851104 Despite a marginal saving of $2 million (or less than 2 percent in a total estimated cost of $120 million)in favor of three penstocks,the arrangement of six individual penstocks has been retained.This arrangement provides improved flexibility and security of operation. The preliminary design of the power facilities involves two tailrace tunnels leading from a common surge chamber.An alternative arrangement with a single tailrace tunnel was adopted to achieve significant cost saving. Optimization studies on all water passages were carried out to determine the minimum total cost of initial construction plus the capitalized value of anticipated energy losses caused by conduit friction,bends and changes of section. For the penstock optimization,the construction costs of the B-2-2l intake and approach channel were included as a function of the penstock diameter and spacing.Similarly,in the optimization studies for the tailrace tunnel the costs of the surge chamber were included as a function of tailrace tunnel diameter. (g)Environmental Constraints (*) Apart from the potential nitrogen supersaturation problem discussed,the major environmental constraints on the design of the power facilities are: o Control of downstream river temperatures,and o Control of downstream flows. The intake design has been modified to enable power plant flows to be drawn from the reservoir at_four different levels throughout the anticipated range of reservoir drawdown for energy production in order to control the downstream river temperatures within acceptable limits. Minimum flows at Gold Creek during the critical summer months have been studied to mitigate the project impacts on salmon spawning downstream of Devil Canyon.These minimum flows represent a constraint on the reservoir operation and influence the computation of average and firm energy produced by the Susitna development. of Watana General Arrangement (0) Preliminary alternative arrangements of the Watana project were devel- oped and subjected to a series of review and screening processes. The layouts selected from each screening process were developed in greater detail prior to the next review and,where necessary, additional layouts were prepared combining the features of two or more of the alternatives.Assumptions and criteria were evaluated at each ····stage··and·additionaldata-incorporated--as·neces·sary~--····The selection·· ......··_·_pI'-OC ess--·f.ol-1owed-~he--gene·t'-a-l-se-l-ec·t-ion-me·l;;hodo-l-ogy-~est·ab-H-shed-forthe-. Susitna project and is outlined below. 2.3.1 -Selection Methodology (*) The determination of the project general arrangement at Watana was undertaken in three distinct review stages:preliminary, ·intermediate ,and finaL 1 851104 B-2-22 ] (a)Preliminary Review (completed early in 1981)(*) This comprised four steps: Step 1:Assemble available data,determine design criteria, and establish evaluation criteria. Step 2:Develop preliminary layouts and design criteria based on the above data including all plausible alternatives for the constituent facilities and structures. Step 3:Review all layouts on the basis of technical feasibility,readily apparent cost differences, safety,and environmental impact. Step 4:Select those layouts that can be identified as most favorable,based on the evaluation criteria established in Step 1,and taking into account the preliminary nature of the work at this stage. (b)Intermediate Review (completed by mid-198l)(*) This involved a series of five steps: Step 1:Review all data,incorporating additional data from other work tasks. Review and expand design criteria to a greater level of detail. Review evaluation criteria and modify,if necessary. Step 2:Revise selected layouts on basis of the revised criteria and additional data.Prepare plans and principal sections of layouts. Step 3:Prepare quantity estimates for major structures based on drawings prepared under Step 2. Develop a preliminary construction schedule to evaluate whether or not the selected layout will allow completion of the project within the required time frame. 851104 B-2-23 Prepare a preliminary contractor's type estimate to determine the overall cost of each scheme. Step 4:Review all layouts on the basis of technical feasibility,cost impact of possible unknown conditions and uncertainty of assumptions,safety, and environmental impact. Step 5:Select the two most favorable layouts based on the evaluation criteria determined under Step 1. (c)Final Review (completed early in 1982)(*) Step 1:Assemble and review any additional data from other work tasks. Revise design criteria in accordance with additional available data. Finalize overall~valuation criteria. Step 2: Step 3: Revise or further develop the two.layouts on the basis of input from-Step -Tand--determine overall dimensions of structures,water passages,gates, and other key item~. Prepare quantity take-offs for all major structures • .RevIew-----c.o.st c·omp·oiient-s wiE1il n a·iireIIiDf-iiiir"y contractor's type estimate using the most recent data and criteria,and develop a construction schedule. Determine overall direct cost of schemes. j Step 4:Review all layouts on the basis of practicability, ...............---......-.technical feasibility,···cost-,·-impact-ofpossible -.-----'-unknot'1:n-condi-t-i-ons-,-sa-fet~T-and-en:v-i.ronmenta!··· impact. Step 5:Select the final layout on the basis of the evaluation criteria developed under Step 1. 2.3.2 -DesigIl pata,and Criteria(*) AS diScusSed above,the review process includeda.ssembling relevant design data,establishing preliminary design criteria, 851104 B-2-24 ] and expanding and refining these data during the intermediate and final reviews of the project arrangement.The design data and design criteria which evolved through the final review are presented in Table B.2.3.l. 2.3.3 -Evaluation Criteria (*) The various layouts were evaluated at each stage of the review process on the basis of the criteria summarized in Table B.2.3.2.These criteria illustrate the progressively more detailed evaluation process leading to the final selected arrangement. 2.3.4 -Preliminary Review (*) The development selection studies (Acres 1982c,Vol.1;Acres 1981)involved comparisons of hydroelectric schemes at a number of sites on the Susitna River.As part of thase comparisons a preliminary conceptual design was developed for Watana incorporating a double stilling basin type spillway. Eight further layouts were subsequently prepared and examined for the Watana project during this preliminary review process in review process in addition to the scheme shown on Figure B.l.3.4 These eight layouts are shown in schematic form on Figure B.2.3.1.Alternative 1 of these layouts was the scheme recommended for further study. This section describes the preliminary rev~ew undertaken of alternative Watana layouts. (a)Basis of Comparison of Alternatives (*) Although it was recognized that prov~s~on would have to be made for downstream releases of water during filling of the reservoir and for emergency reservoir drawdown,these features were not incorporated in these preliminary layouts. These facilities would either be interconnected with the diversion tunnels or be provided for separately.Since the system selected would be similar for all layouts with minimal cost differences and little impact on other structures,it was decided to exclude these facilities from overall assessment at this early stage. Ongoing geotechnical explorations had identified the two major shear zones crossing the Susitna River and running roughly parallel in the northwest direction.These zones enclose a stretch of watercourse approximately 4,500 feet in length.Preliminary evaluation of the existing geological data indicated highly fractured and altered materials within .: 851104 B-2-25 851104 (b) the actual shear zones which would pose serious problems for conventional tunneling methbds and would be unsuitable for fbunding of massive concrete structures.The originally proposed dam axis was located between these shear zones; since no apparent major advantage appeared to be gained from large changes in the dam location,layouts generally were kept with~n the confines of these bounding zones. An earth and rockfill dam was used as the basis for all layouts.The downstream slope of the dam was assumed as 2H:lV in all alternatives,and upstream slopes varying between 2.5H:lV and 2.25H:lV were examined in order to determine the influence of variance in the dam slope on the congestion of the layout.In all preliminary arrangements except the one shown on Figure B.l.3.4,cofferdams were incorporated within the body of-the main dam. Floods greater than the routed l:lO,OOO-year spillway design flood and up to the probable maximum flood were assumed to be passed by surcharging the spillways,except in cases where an unlined cascade or stilling basin type spillway served as the sole discharge facility.In such instances , under large surcharges,these spillways would not act as efficient energy dissipators but would be drowned out, acting as steep open channels with the possibility of their total destruction.In order to avoid such an occ urrence, the design flood for these latter spillways was considered as the routed probable 'maximum flood. On the basis of information existing at the time of the preliminary review,it appeared th~t an underground powerhouse could be loca ted on either side of the river.A surface powerhouse on the north bank appeared feasible but was precludec!from the south bank by the close proximity of the downstream toe of the dam and the adjacent broad shear zone.Locating the powerhouse further downstream would ___~~.qE.~_;'~__t tJ!1.~~JJ.!1:g_.~£;'2.~1!...th ~_.~h_~~t::_,~g.!1:~,.._~.h!i:J1l\f2.u.1c:l .....l:l~_, expensive and would require excavating a talus slope. Furthermore,it was found that a south bank surface powerhouse would either interfere with a south bank spillway or would be directly impacted by discharges from a north bank spillway. Description of Alternatives (*) (I)DoublELStiUing Basin Scheme (*) The scheme as shown on Figur~B.l.3.4 has a dam axis location similar to that originally proposed by the B-2-26 l .' J ,J 851104 COE,and a north bank double stilling basin spillway. The spillway follows the shortest line to the river, avoiding interference with the dam and discharging downstream almost parallel to the flow into the center of the river.A substantial amount of excavation is required for the chute and stilling basins,although most of this material could probably be used in the dam.A large volume of concrete is also required for this type of spillway,resulting in a spillway system that would be very costly.The maximum head dissipated within each stilling basin is approximately 450 feet.Within world experience, cavitation and erosion of the chute and basins should not be a problem if the structures are properly designed.Extensive erosion downstream would·not be expected. The diversion follows the shortest route,cutting the bend of the river on the north bank,and has inlet portals as far upstream as possible without having to tunnel through "The Fins."It is possible that the underground powerhouse is in the area of "The Fingerbuster,"but the powerhouse could be located upstream almo.s.t as far as the system of drain holes and galleries just downstream of the main dam grout curtain. (ii)Alternative 1 (*) This alternative (Figure B.2.3.l)is recommended for further study and is similar to the layout described above except that the north side of the dam has been rotated clockwise,the axis relocated upstream,and the spillway changed to a chute and flip bucket.The revised dam alignment resulted in a slight reduction in total dam volume compared to the above alternative.A localized downstream curve was introduced in the dam close to the north abutment in order to reduce the length of the spillway.The alignment of the spillway is almost parallel to the downstream section of the river and it discharges into a pre-excavated plunge pool in the river approximately 800 feet downstream from the flip bucket.This type of spillway should be considerably less costly than one incorporating a stilling basin, provided that excessive pre-excavation of bedrock within the plunge pool area is not required.Careful design of the bucket will be required,however,to prevent excessive erosion downstream,causing undermining of the valley sides and/or buildup of B-2-27 material downstream which could cause elevation of the tailwater levels. (iii)Alternatives 2 through 2D (*) Alternative 2 consists of a south bank cascade spillway with the main dam axis curving downstream at the abutments.The cascade spillway would require an extremely large volume of rock excavation,but it is probable that most of this material,with careful scheduling,could be used in the dam.The excavation would cross "The'Fingerbuster"and extensive dental concrete would be required in,that area.In the upstream portion of the spillway,velocities would be relatively high because of the narrow configuration of the channel,and erosion could take place in this area in proximity to the dam.The discharge from the spillway enters the river perpendicular to the general flow,but velocities would be relatively low and should not cause substantial erosion problems. The powerhouse is in the most suitable location for a surface alternative where the bedrock is close to the surface and the overall rock slope is approximately 2H:1 V. Alternative 2A is similar to Alternative 2 exc~p~ that the upper end of the channel is divided and separate control structures ar.e provided.This diJ[i~i9n w9U IdaLLowthetute _ofone.s,tr,ucture _or upstream channel while maintenance or remedial work is being performed on the other. Alternative 2B is similar to Alternative 2 except that the cascade spillway is replaced by a double stilling basin type structure.This spillway is somewhat longer than the similar type of structure on the north bank in the alternative described above. '---------------libwever;-tne'sTop'eo fthe groiind Ts--ressEnaii'Ehe -.._------'-----------'---rath'er-st'e'e'p-n'o'rth-'b'ank'--cmd-nray-b'e'-tfa--shfr---'to-' construct,a factor which may partly mitigate the cost of the longer structure.The discharge is at a sharp angle to the river and more concentrated than the cascade,which could cause erosion of the opposite bank. j 851104 Alternative 2C is adeI'iva.ti'ltebf 2B with a similar -c-arrangeme n t,exce pt:'t:hat;~the~~clouble sti I Iing basin spillway is reduced in size and augmented by an additional emergency spillway in the form of an inclined,unlined rock channel.Under this B-2-28 851104 arrangement the concrete spillway acts as the main spillway,passing the l:lO,OOO-year design flood with greater flows passed down the unlined channel which is closed at its upstream end by an erodible fuse plug.The problems of erosion of the opposite bank still remain,although these could be overcome by excavation and/or slope protection.Erosion of the chute would be extreme for significant flows, although it is highly unlikely that this emergency spillway would ever be used. Alternative 2D replaces the cascade of Alternative 2 with a lined chute and flip bucket.The comments relative to the flip bucket are the same as for Alternative 1 except that the south bank location in this instance requires a longer chute,partly offset by lower construction costs because of the flatter slope.The flip bucket discharges into the river at an angle which may cause erosion of the opposite bank.The underground powerhouse is located oQ:o;.,the north bank,an arrangement which proy-ides an overall reduction of the length of the water passages. (iv)Alternative 3 (*) This arrangement has a -dam axis location slightly upstream from Alternative 2,but retains~the downstream curve at the abutments.The main spillway is an unlined rock cascade on the south bank which passes the design flood.Discharges beyond the l:lO,OOO-year flood would be discharged through the auxiliary concrete-lined chute and flip bucket spillway on the north bank.A gated control structure is provided for this auxiliary spillway which gives it the flexibility to be used as a backup if maintenance should be required on the main spillway.Erosion of the cascade may be a problem, as mentioned previously,but erosion downstream should be a less important consideration because of the low unit discharge and the infrequent operation of the spillway.The diversion tunnels are situated in the north abutment,as with previous arrangements, and are of similar cost for all these alternatives. (v)Alternative 4 (*) This alternative involves rotating the axis of the main dam so that the south abutment is relocated approximately 1,000 feet downstream from its Alternative 2 location.The relocation results in a B-2-29 851104 reduction in the overall dam quantities but would require siting the impervious core of the dam directly over "The Fingerbuster"shear zone at maximum dam height.The south bank spillway, consisting of chute and flip bucket,is reduced in length comp~red to other south bank locations,as are the power facility water passages.The diversion tunnels are situated on the south bank;there is no advantage to a north bank location,since the tunnels are of similar length owing to the overall downstream relocation of the dam.Spillways and power facilities would also be lengthened by a north bank location with this dam configuration. (vi)Selection of Schemes for Further Study (*) A basic consideration during design development was that the main dam core should not cross the major shear zones because of the obvious problems with treatment of the foundation.Accordingly,there is very little scope for realigning the main dam apart from a slight-rotation toplace-,-it more at right angles to the river. Location of the spillway on the north bank results in a shorter distance to the river and allows discharges almost parallel to the general direction of river flow.The double stilling basin arrangement·would be _~extremel:y:".expe nshTe,~par.tic.ul arly_._iL.Lt.must.b.e. designed to pass the probable maximum flood.An alternative such as 2C would reduce the magnitude of design flood to be passed by the spillway but would only be acceptable if an emergency spillway with a high degree of operational predictability could be constructed.A flip bucket spillway on the north bank,discharging directly down the river,would appear to be an economic arrangement,although some sc6ur··1iiignCOcc·urifi.-·tne-pTunge.pooiarea·~-Acascade-· spi-l-lway-on-the-south-b-anrc-ou·td--be-an-a-c-cep·tabl.e·····---.· solution provided that most of the excavated material could be used in the dam,and adequate rock conditions exist. The length of diversion tunnels can be decreased if they are located on the north bank.In addition,the tunnels would be accessible bya preliminary access -·-"road-from·-the--north,-which-is-the·most likely ·route. This location would also avoid the area of "The Fingerbuster"and the steep cliffs which would be B-2-30 encountered on the south side close to the downstream dam toe. The underground configuration assumed for the powerhouse in these preliminary studies allows for location on either side of the river with a minimum of interference with the surface structures. Four of the preceding layouts,or variations of them, were selected for further study: o A variation of the double stilling basin scheme,but with a single stilling basin main spillway on the north bank,a rock channel and fuse plug emergency spillway,a south bank underground powerhouse and a north bank diversion scheme; o Alternative 1 with a north bank flip bucket spillway,an underground powerhouse on the south bank,and north bank diversion; o A variation of Alternative 2 with a reduced capacity main spillway and a north bank rock channel with a fuse plug serving as an emergency spillway;and o Alternative 4 with a south bank rock cascade spillway,a north bank underground powerhouse, and a north bank diversion. 2.3.5 -Intermediate Review (*) For the intermediate review process,the four schemes selected as a result of the preliminary review were examined in more detail and modified.A description of each of the schemes is given below and shown on Figures B.2.3.2 through B.2.3.7.The general locations of the upstream and downstream shear zones shown on these plates are approximate and have been refined on the basis of subsequent field investigations for the proposed project. (a)Description of Alternative Schemes (*) The four schemes are shown on Figures B.2.3.2 through B.2.3.7. (i)Scheme WPI (Figure B.2.3.2)(*) This scheme is a refinement of Alternative 1.The upstream slope of the dam is flattened from 2.5:1 851104 B-2-31 to 2.75:1.This conservative approach was adopted to provide an assessment of the possible impacts on project layout of conceivable measures which may prove necessary in dealing with severe earthquake design conditions.Uncertainty with regard to the nature of river alluvium also led to the location of the cofferdams outside the limits of the main dam embankment.As a result of these conditions,the intake portals of the diversion tunnels on the north bank are also moved upstream from "The Fins".A chute spillway with a flip bucket is located on the north bank.The underground powerhouse is located on the south bank. (ii)Scheme WP2 (Figur~s B.2.3.4 and B.2.3.5).(*) This scheme is derived from the double stilling basin layout.The main dam and diversion facilities are similar to Scheme WP1 except that the downstream cofferdam .i~relocated further downstream from the ..spillway outlet and the diversion tunnels are correspondingly extended.The main spillway is located on the north bank,but the two stilling basins of the preliminary scheme (Acres 1981)are combined into a single stilling basin at the river level.An emergency spillway is also located on the north bank and consists of a channel excavated in rock,discharging downstream from the area of the relict channel.The channel is closed at its ---~-upstream-end~Dya-c()mpactedearthfIlr:tusepItiiand is capable of discharging the flow differential between the probable maximum flood and the surcharged capacity of the main spillway.The underground powerhouse is located on the south bank. (iii)Scheme WP3 (Figures B.2.3 •.3 and B.2.3.4)(*) Thiss chemei-s-simi-lart oScheme-WPl-inaH-res peets·.. ._..excapt_that.au__emer_gency__spiUway_is_added-----..-.. consisting of north bank rock channel and fuse plug. (iv)Scheme WP4 (Figures B.2.3.6 and B.2.3.7)(*) The dam location and geometry for Scheme WP4 are similar to that for the other schemes.The diversion is on the north bank and discharges dQwos.t.ream fromthe.pow.erhouse.tailrace outlet.A rock cascade spillway is located on the south bank and is served by two separate control structures with ·l ·1 851104 B-2-32 1 downstream stilling basins.The underground powerhouse is located on the north bank. (b)Comparison of Schemes (*) The main dam is in the same location and has the same configuration for each of the four layouts considered. The cofferdams have been located outside the limits of the main dam in order to allow more extensive excavation of the alluvial material and to ensure a sound rock foundation beneath the complete area of the dam.The overall design of the dam is conservative,and it was recognized during the evaluation that savings in both fill and excavation costs can probably be made after more detailed study. The diversion tunnels are located on the north bank.The upstream flattening of the dam slope necessitates the location of the diversion inlets upstream from "The Fins" shear zone which would require extensive excavation and support where the tunnels pass through this extremely poor rock zone and could cause delays in the construction schedule. A low-lying area exists on the north bank in the area of the relict channel and requires approximately a 50~foot high saddle dam for closure,given the reservoir operating level assumed for the comparison study.However,the finally selected reservoir operating level will require only a nominal freeboard structure at this location. A summary of capital C0st estimates for the four alternative schemes is given in Table B.2.3.3. The results of this intermediate analysis indicate that the chute spillway with flip bucket (Scheme WPl)is the least costly spillway alternative. The scheme has the additional advantage of relatively simple operating characteristics.The control structure has provision for surcharging to pass the design flood.The probable maximum flood can be passed by additional surcharging up to the crest level of the dam.In Scheme WP3 a similar spillway is provided,except that the control structure is reduced in size and discharges above the routed design flood are passed through the rock channel emergency spillway.The arrangement in Scheme WPl does not provide a backup facility to the main spillway,so that if repairs caused by excessive plunge pool erosion or damage to the structure itself require removal of the spillway from service for any length of time,no alternative discharge \ 851104 B-2-33 facility would be available.The additional spillway of Scheme WP3 would permit emergency discharge if it were required under extreme circumstances. The stilling basin spillway (Scheme WPZ)would reduce the potential for extensive erosion downstream,but high velocities in the lower part of the chute could cause cavitation even with the provision for aeration of the discharge.This type of spillway would be very costly,as can be seen from Table B.Z.3.3. The feasibility of the rock cascade spillway is entirely dependent on the quality of the rock,which dictates the amount of treatment required for the rock surface and also the proportion of the excavated material which can be used in the dam.For determining the capital cost of Scheme WP4, conservative assumptions were made regarding surface treatment and the portion of material that would have to be wasted. The diversion tunnels are locate~on the north bank for all alternatives examined in the intermediate review.For Scheme WPZ,the downstream portals must be located downstream from the stilling basin,.,resulting in an increase of approximately 800 feet in the length of the tunnels.The south bank location of the powerhouse requires its placement close to a suspected shear zone,with the tailrace tunnels passing through this shear zone to reach the river.A LOJlger_acces_s__tunneLisalsorequired,_together with an - additional I,000 feet in the length of the tailrace •The south-side location is remote from the main access road, which wi 11 probably be on the north side 6f the river,as will the transmission corridor. (c)Selection of Schemes for Further Study (*) Examination of the technical and economic aspects of Schemes ,,-----------------WPr-tlirougli--WP~--indi-caEes--tner-e-Ts-rit t ie--scopefor'" -----~adJus-tmen-t-'o-f-th-e-d-am aX:ls,owing r:o-ffie confinement -imposed by the upstream and downstream shear zones.In addition, passage of the diversion tunnels through the upstream shear zone could result in significant delays in construction and additional cost. From a comparison of costs in Table B.2.3.3,it can be seen thatth€f 'f 1-~p_bti_c:~_et__~)TpE'i ~pDJ~l3,ii_~._t;li€i~c>sJec onomi caI , 'but because-of the 'potentialfor'erosionund-er extensive operation it is undesirable to use it as the only discharge facility.A mid...;level release will be required for emergency drawdown of the reservoir,and use of this release - 1 ,] 851104 B-Z-34 ,I I.' 851104 as the first-stage service spillway with the flip bucket as a backup facility would combine flexibility and safety of operation with reasonable cost.The emergency rock channel spillway would be retained for discharge of PMF flows. The stilling basin spillway is very costly and the operating head of 800 feet is beyond precedent experience.Erosion downstream should not be a problem but cavitation on the chute could occur.Scheme WPZ was therefore eliminated from further consideration. The cascade spillway was also not favored,for technical and economic reasons.However,this arrangement does have an advantage in that it provides a means of preventing nitrogen supersaturation in the downstream discharges from the project which could be harmful to the fish population.A cascade configuration would reduce the dissolved nitrogen content;hence,this alternative was retained for further evaluation.The capacity of the cascade was reduced and the emergency rock channel spillway was included to pass the extreme.floods. The results of the intermediate review indicated that the following components should be incorporated into any scheme carried forward for final review: o Two diversion tunnels located on the north bank of the river; o An underground powerhouse also located on the north bank; o An emergency spillway,comprising a rock channel excavated on the north bank and discharging well downstream from the north abutment.The channel is sealed by an erodible fuse plug of impervious material designed to fail if oyertopped by the reservoir;and o A compacted earthfill and rockfill dam situated between the two major shear zones which traverse the project site. As discussed above,two specific alternative methods exist with respect to routing of the spillway design flood and minimizing the adverse effects of nitrogen supersaturation on the downstream fish population.These alternatives are: o A chute spillway with flip bucket on the north bank to pass the spillway design flood,with a mid-level B-2-35 851104 release system designed to operate for floods with a frequency of up to about 1:50 years;or o A cascade spillway on the south bank. Accordingly,two schemes were developed for further evaluation as Part of the final review process.These schemes are described separately in the paragraphs below. 2.3.6 -Final Review (*) The.t'tYoschemes considered in the final review process were essentially deri va tions of Schemes WP3 and WP4. (a)Scheme WP3A (Figure B.2.3.8)C*) This scheme is a modified version of Scheme WP3 described above.Because of scheduling and cost considerations,it is extremely important to maintain the diversion tunnels downstream from "The Fins."It is also important to keep the dam axis as far upstream as possible to avoid congestion of the dbwl1strealll structures.For these reasons,the inlet portals to the diversion.tunnels were located in the sound bedrock forming the downstream boundary of "The Fins."The upstream cofferdam and main dam are maintained in the ups tream locations as .shown on Figure B.2 .3.8.As ment ione d previously,additional criteria have necessitated modifications in the spillway configuration,and low-level ·an-d~emergency··drawdown~outl-e-tshave-bee·n·lnU'bducecl-.-Tne- main modifications to the scheme are as follows. (i)Main Dam (*) Continuing preliminary design studies and review of world practice suggest that an upstream slope of 2.4H:1V would be acceptable for the rock shell • ......Adoptionofthisslope.resultsno_Lonl~in a_ reduction in dam fill volume butalso.~re<luc..tio.!!..in ~ the base width of the dam which permits the main project components to be located between the major shear zones. The downstream slope of the dam is retained as 2H:1V. The cofferdams remain outside the .limits of the dam .•in.order foalloW complete ex:ca;V'a.t:iooof the·riverbed alluvium. B-2-36 .( ] 851104 (ii)Diversion (*) In the intermediate review arrangements,diversion tunnels passed through the broad structure of "The Fins,"an intensely sheared area of breccia,gouge, and infills.Tunneling of this material would be difficult,and might even require excavation in open cut from the surface.High cost would be involved, but more important would be the time taken for construction in this area and the possibility of unexpected delays.For this reason,the inlet portals have been relocated downstream from this zone with the tunnels located closer to the river and crossing the main system of jointing at approximately 45°.This arrangement allows for shorter tunnels with a more favorable orientation of the inlet and outlet portals with respect to the river flow directions. A separate low-level inlet and concreta7lined tunnel is provided,leading from tqft reservoir at approximate Elevation 1,550 to downstream of the diversion plug where it merges with the diversion tunnel closest to the river.This low-level tunnel is designed to pass flows up to 12,000 cfs during reservoir filling.I~would also pass up to 30,000 cfs under 500-foot head to allow,emergency draining of the reservoir. Initial closure is made by lowering the gates to the tunnel located closest to the river and constructing a concrete closure plug in the tunnel at the location of the grout curtain underlying the core of the main dam.On completion of the plug,the low-level release is opened and controlled discharges are passed downstream.The closure gates within the second diversion tunnel portal are then closed and a concrete closure plug constructed 'in line with the grout curtain.After closure of the gates,filling of the reservoir would commence. (iii)Outlet Facilities (*) As a provision for drawing down the reservoir in case of.emergency,a mid-level release is provided.The The intake to these facilities is located at depth adjacent to the power facilities intake structures. Flows would then be passed downstream through a concrete-lined tunnel,discharging beneath the downstream end of the main spillway flip bucket.In B-2-37 -' order to overcome potential nitrogen supersaturation problems,Scheme WP3A also incorporates a system of fixed-cone valves at the downstream end of the outlet facilities.The valves were sized to discharge in conjunction with the powerhouse operating at 7,000 cfs capacity (flows up to the equivalent routed 50-year flood).Eight feet of reservoir storage is utilized to reduce valve capacity.Six cone valves are required,located on branches from a steel manifold and protected by individual upstream closure gates.The valves are partly incorporated into the mass concrete block forming the flip bucket of the main spillway.The rock downstream is protected from erosion by a concrete facing slab anchored back to the sound bedrock. (iv)Spillways (*) As discussed above,the designed operation of the main spillway facilities was arranged to limit discharges of potentially nitrogen-supersaturated water from Watana to flows having an equivalent return period greater than 1:50 years. The main chute spillway and flip bucket discharge into an excavated plunge pool in the downstream river bed.Releases are controlled by a three-gated ogee structure located adjacent to the outlet facilities and power intake structure just upstream from the damce;iterl ine:-""Thadesign-di sella rge -I s a-pprox Ena t;ely ---" 120,000 cfs;corresponding to the routed 1:10,OOO-year flood (150,000 ·cfs)reduced by the 31,000 cfs flows attributable to outlet and power facilities -discharges.-Maximum reservoir level is 2,194 feet.The plunge pool is formed by excavating the alluvial river deposits to bedrock.Since the excavated plunge pool approaches the limits of the -cd-cu-rated-maximum-scour-ho-le-,--iti-s-no tant icipa t ed ------------------------------tha-t,--g-i-ven-t-he-i-n-f-r-eq-uen-t--d-i-scha-r-ges-,--s-i-g-n-i-f-i-can-t- downstream erosion will occur. An emergency spillway is provided by means of a channel excavated in rock on the north bank, discharging well downstream from the north abutment ill the directi.on of_TSltlsenaCreek.The channel is sealed 'by an erodible fuse plug of impervious mater-ial-de signed.tofai l"'ix-o"\t-ertopped by the reservoir,although some preliminary excavation may be necessary.The crest level of the plug will be set at Elevation 2,230,well below that of the main ,j ·J 'I ] J 1 ) 851104 B-2-38 851104 dam.The channel will be capable of passing,in conjunction with the main spillway and outlet facilities,the probable maximum flood of 326,000 cfs. (v)Power Facilities (*) The power intake is set slightly upstream from the dam axis deep within sound bedrock at the downstream end of the approach channel.The intake consists of six units with provision in each unit for drawing flows from a variety of depths covering the complete drawdown range of the reservoir.This facility also provides for drawing water from the different temperature strata within the upper part of the reservoir and thus regulating the temperature of the do~stream discharges close to the natural temperatures of the river or temperatures advantageous to fishery enhancement.For this preliminary conceptual arrangement,flow withdrawals from different levels are achieved by a series of upstream vertical shutters moving in a single set of guides and operated to form openings at the required level.Downstream from these shutters each unit has a pair of wheel-mounted closure gates which will isolate the individual penstocks.. The six penstocks are 18-foot diameter, concrete-lined tunnels inclined at 55°immediately downstream from the intake to a nearly horizontal portion leading to the powerhouse.This horizontal portion is steel-lined for 150 feet upstream from the turbine units to extend the seepage path to the powerhouse and reduce the flow within the fractured rock area caused by blasting in the adjacent powerhouse cavern. The six 170-MW turbine/generator units are housed within the major powerhouse cavern and are serviced by an overhead crane which runs the length of the powerhouse and into the service area adjacent to the units.Switchgear,maintenance room and offices are located within the main cavern,with the transformers situated downstream in a separate gallery excavated above the tailrace tunnels.Six inclined tunnels carry the connecting bus ducts from the main power hall to the transformer gallery.A vertical elevator and vent shaft run from the power cavern to the main office building and control room located at the surface.Vertical cable shafts,one for each pair of B-2-39 transformers,connect the transformer gallery to the switchyard directly overhead.Downstream from the transformer gallery the underlying draft tube tunnels merge into two surge chambers (one chamber for three draft tubes)which also house the draft tube gates for isolating the units from the tailrace.The gates are operated by an overhead traveling gantry located in the upper part of each of the surge chambers. Emerging from the ends of the .chambers,two concrete-lined,low-pressure tailrace tunnels carry the discharges to the river.Because of space restrictions at the river,one of these tunnels has been merged with the downstream end of the diversion tunnel.The other tunnel emerges in a separate portal with provision for the installation of bulkhead gates. The orientation of water passages and underground caverns is such as to avoid,as far as possible, alignment of the main excavations with the major joint sets. (vi)Access (*) Access is assumed to be from the north side of the river.Permanent access to structures close to the river is by a road along the north downstream river bank and then via a tunnel passing through the concreteformingthe--f-Hpbucket-.kt unnel-fromthis point to the power cavern provides for vehicular access.As~co:g.daryaccess road across the crest of the dam passes down the south bank of the valley and across the lower part ()f the d8Jll. (b)Scheme WP4A (Figure B.2.3.9)(*) ..'IbJJL .sch_gm_e._.i.s __sim_ila;J;'__in_l!to_s_t_r_esp~_cJ:_s to Sch emSlWP3A .......previously discussed,excee..L for.the spillw~l_ arrangement s. (i)Main Dam (*) The main dam axis is similar to that of Scheme WP3A, except for a slight downstream rotation at the southabutlliertt at the sp~llWc:lycorttrol structures. J -J J -----·····Ti n fiivet'-sTon.-T*T . The diversion and low-level releases are the same for the two schemes. 851104 B-2-40 ..1 J 851104 (iii)Outlet Facilities (*) The outlet facilities used for emergency drawdown are separate from the main spillway for this scheme. The outlet facilities consist of a low-level gated inlet structure discharging up to 30,000 cfs into the river through a concrete-lined,free-flow tunnel with a ski jump flip bucket.This facility may also be operated as an auxiliary outlet to augment the main south bank spillway. (iv)Spillways (*) The main south bank spillway is capable of passing a design flow equivalent to the 1:10,000-year flood through a series of 5Q-foot drops into shallow pre- excavated plunge pools.The emergency spillway is designed to operate during floods of greater magnitude up to and including the PMF. Main spillway discharges are controlled by a broad multi-gated control structure discharging into a shallow stilling basin.The feasibility of this arrangement is governed by the quality of the rock in the area,requiring both durability to withstand' erosion caused by spillway flows and a high percentage of sound rockfill material that can be used from the excavation directly in the main dam. On the basis of the site information developed concurrently with the general arrangement studies,it became apparent that the major shear zone known to exist in the s,outh bank area extended further downstream than initial studies had indicated.The cascade spillway channel was therefore lengthened to avoid the shear area at the lower end of the cascade. The arrangement shown on Figure B.2.3.9 for Scheme WP4A does not reflect this relocation,which would increase the overall cost of the scheme. The emergency spillway consisting of rock channel and fuse plug is similar to that of the north bank spillway scheme. (v)Power Facilities (*) The power facilities are similar to those in Scheme WP3A. B-2-41 (c)Evaluation of Final Alternative Schemes (*) An evaluation of the dissimilar features.for each arrangement (the main spillways and the discharge arrangements at the downstream end of the outlets)indicates a saving in capital cost of $197,000,000,excluding contingencies and indirect cost,in favor of Scheme WP3A. If this difference is adjusted .for the savings associated with using an appropriate proportio.n of excavated material from the cascade spillway as rockfill in the main dam,this represents a net overall cost difference of approximately $110,000,000 including contingencies,engineering,and administration costs. As discussed above,although limited info'rmation exists regarding the'quality of the rock 'in the downstream area on the south bank,it is known that a major shear zone runs through and is adjacent to the area presently alloca ted to the spillway in Scheme WP4.This.,Jo?ould require relocating the south bank cascade spillway several hundred feet farther downstream'into an area.'Y7here the roc.k quality is unknown and the topography less suited to the.gentle overall slope of the cascade.The ,cost of the.excavation would substantially increase compared to previous assumptions, irrespective of the rock quality.III addition,the resistance of the rock to erosion and the suitability for use as excavated mate.rial in the main dam would become less certain.The economic feasibility .of this scheme is largely -",-,"'pt'E:roicateoon tllisla s'tfactof;'ffilfc'eEnea15iTity 'fo useYne' material.as a source of rockfill for the main dam represents a major cost saving. In conjunction,with the,maiIlchute spillway,the problem'of the occurrence of ni trogen.supersa tura tion can be overcome by the use of a regularly operated dispersion-type valve outlet facility in conj unction with the main chute spillway. "h'h "1 l''h,.."..S:Lnce_.t:Ls_,SC emepresents..,a,,-more-econom:Lca.sout.lonW:Lt " ,,_.__,__._--._.f~.!'l..e_r_p.o_t,e,nt,i,aLp,r,o,b,Lem,s.:...co,ncerning_th.e ...geotechnicaLas,pects of its design,the north bank chute arrangement (Scheme WP3A)has been adopted as the final selected scheme. Subsequent to adoption of the final scheme and prior to submission of the July 1983 License Application,refinements to the design were made as presented in Exhibit F. Since the filing of the License Application,additional studies and geotechnical investigations have been conducted.These j I 'I 851104 B-2-42 1 I I. have been directed toward reviewing and refining project design concepts and estimating costs of alternative features and layouts.With more information available after the completion of two drilling programs conducted during the Winter of 1982-83 and the Summer of 1984,estimated project costs have been reduced. Studies of alternatives have also shown where cost reductions can be made.Revisions of the project design concepts are therefore shown in this amendment to the License Application and are described below. (a)Staged Construction (***) In this amended License Application,the Susitna Project will be constructed in three stages.The initial construction of the Watana development will be for normal maximum operating reservoir at el.2,000,and is designated Stage I.Construction of the Devil Canyon ~evelopment for normal maximum operating reservoir at el.1,455 is designated Stage II and is scheduled after the Watana initial construction.The raising of Watana dam for the el. 2,185 reservoir,its ultimate height,is designated Stage III.The layouts of the three stages are presented in Figures B.2.3.10,B.2.3.11,and B.2.3.12. Constructing the Watana development in stages will reduce. the initial financial commitment of the state and the burden on electric rate payers "by providing more flexibility in meeting load growth. (b)Diversion Tunnels and Cofferdams (***) The diversion tunnel concept shown in Exhibit F of the initial application consists of two 38-foot diameter tunnels.Tunnell was set high in order to pass ice without pressurizing.Tunnel 2 was set below the river bed to divert flow from the upstream cofferdam area,easing its closure~Tunnel 1 would later be converted to an emergency release facility,as previously described in the application. Studies were conducted to verify the necessity of passing ice through a tunnel with free surface flow.It was concluded that a pressurized tunnel can pass ice,therefore, lowering Tunnel 1 is feasible to increase its hydraulic capacity.The two 36-foot diameter diversion tunn~ls,as proposed in this amendment,will pass the 1:50-year flood. This same criterion was in the initial License Application. 851104 B-2-43 In the amended project,Tunnel 2 is raised by 25 feet to avoid the potential for clogging by bed load deposition in a continuously submerged tunnel. These revisions will result in improved performance of the diversion tunnels and reduce cost. Cofferdam crest elevations have been increased,to provide a greater level of protection to the dam foundation excavation area during construction from a possible ice jam causing higher river level.The combination of greater cofferdam heights and reduced tunnel diameters still results in a decrease in construction cost. (c)Excavation and Foundation Treatment for Dam (***) The main dam foundation treatment,as shoWn in this License Application Amendment,would reduce rock excavation beneath the core and shells and limit excavation of the river valley alluvium to the central 80%of the dam foundation.The areas of the dam in proximity to the upstream and downstream toes of the embankment are now planned to be founded on the riverbed alluvium. Tp.e 1983 Winter Geologic Exploration showed that the bedrock is of a better quality than originaHy anticipated. Therefore,only limited excavation of bedrock beneath··the embankment is foreseen.Fresh hard diorite in most inELt~Il<:~~exis t.~.from the becl~ock_sU1;:face.!...._RemovaIQ~ foundation treatment (dental excavation of concrete backfill)will be perfO'rmed in local areas beneath the shells where erodible or otherwise'unsatisfactory foundation bedrock is encountered.The quantity of rock to be removed under the embankmertt will be reduced from that estimated in the License Application by about 3.75 million cubic yards. The License Application cost estimates assumed a trench beneath the iIJ?pervious core and filters averaging 40 feet ·············-aee-p;--a-rt-d·-arc·av·€H..age-·-exc'a.'raEea "-aepth--under-tli-e-'sneTls"···0£······10· .----------feet.--The--amended--de-srgn--provid-e-s-a-c-o-re--cren-ch-tO--re-et----··- deep in the river section,and 20 feet deep on the abutments.Excavation under the shells on the abutments averages one foot.A reduction in the grout curtain drilling and grouting was also made,in view of the better quality foundation bedrock. Cd)Dam and Cofferdam Configuration and Composition (***). The License Application design for the dam cross section has been essentially retained in this amendment,as it is ! I .' ] ] .J ) 851104 B~2-44 1, considered to be satisfactory and will produce a stable structure.To increase safety against seismic shaking,the steepening of the exterior slopes near the embankment crest has been eliminated.This results in the same exterior slope from crest to toe both upstream and downstream.The embankment internal zoning design has also been modified to incorporate materials from the required excavations along with by-product materials from the processing operations. The amended layout includes the use of rock and processed granular materials in the shells outside the impervious core.This section increases the utilization of available materials and will reduce required borrow as well as reduce spoil requirements. The cofferdam sections have been revised to a more conservative design,and a positive slurry trench cutoff to bedrock is provided. (e)Spillway (***) This License Application Amendment eliminates the emergency spillway and increases the discharge capacity of the chute spillway and flip bucket to pass the routed PMF.This revision will reduce cost of ._the development and reduce terrestrial and aesthetic impacts by reducing ground surface disturbance •. The capacity of the spillway will be increased by providing larger gates and increasing the width of the chute and flip bucket.Th~three gates will be increased from 36 feet wide by 49 feet high to 44 feet wide by 64 feet high. The width of the chute,which varied from 140 to 80 feet, will be increased to vary from 164 to 120 feet.The flip bucket will be increased from 80 feet to 120 feet wide. In Stage I the crest of the spillway control structure will be at el.1,950,and in Stage III the crest will be at el.2,135.The ultimate crest will be 13 feet lower than previously shown to accomodate the larger gates for the increased discharge capacity. This amendment also includes a rev~s~on of the type of spillway gate from fixed wheel gate to radial gate and revises the type of hoist from electric motor driven drum to hydraulic cylinder operator.The revised type of gate will cost less and will have improved operating characteristics. 851104 B-2-45 (f)Relocation and Reorientation of Caverns (***) A review of the site geology indicated a major set of fractures which trended N 50 0 W and a second minor set perpendicular to these.The caverns for the powerhouse, transformer gallery,and surge chamber,as shown in the License Application,trend in a direction approximately N 20 o W,straddling between the major joint system and a sub joint system. Excavation of the longitudinal walls would be improved if the major joint planes were to intersect the walls as near to the perpendicular as possible.Consequently,the caverns have been rotated accordingly,resulting in less overbreak of rock in the cavern faces,fewer construction problems and improved safety during construction.This change will also be beneficial to the changes in the power conduits and access tunnel geometry described below. (g)Power Conduits and Intake (***) The-LicenseApplication indicates a single structure power intake with six intake passages located approximately 1,000 feet upstream from the dam axis.The power conduits consist of six individual penstock tunnels and shafts with a developed length of about 1,500 feet each connecting the intake structure to the powerhouse,and two tailrace tunnels approximately 2,000 feet long connecting the powerhouse to ---.------.~-~the~iv.e.r.~_....The~do_ws~t_r.eam_3.0~0.fee.t_o.LQne_o_f.~t.he.tail.-rg.c_e. tunnels utilized the downstream portion of one of the diversion tunnels. To reduce the power conduit length in the amended design, the intake structure was shifted to a location between the spillway and the river channel and nearer to the dam axis, resulting in relocation and shortening of the power conduits.The number of penstock tunnels was reduced from .......-···-·sIi--to -fl:iree-power-fi.iniiels~·-·eacnofwhTcliwilTbi furc·ate·t6 .- ~,----,--'_.,-_._---------,---------.---~--sma IIer pe nsf 0 ck~tUI111el-s-.--G{f(:frd--v~-lvl:fS~wi-ll---b~e-·-pr-ovid-ed·--fo·r·--·-- each turbine.-The net head on the generating units will be greater,and the shorter,more efficient power conduits will provide better unit operation.Vertical shafts are also shown instead of sloping Shafts because excavation and concreting of vertical shafts requires less time,personnel, -and equipment,.and given the-geologic conditions,should res~l 1:in less overbreak. J 1 - .\ 'j 1 "I 851104 B-2-46 )(h)Power Intake and Spillway Approach Channels (***) The hydraulic conditions of the approach channels to the power intake and spillway as shown in the License Application can be improved with the relocation of the powerhouse and the power conduits.In the License Application,the power intake is located such that it appears to impede flow to the spillway.The amended location of the power intake will eliminate this effect. The approach channels as shown will require larger quantities of rock excavation;however,this material can be used for fill in the dam and for concrete aggregate. (i)Turbine-Generator Unit Speed (***) The synchronous speed of the turbine-generator units has been increased from 225 rpm,as shown in the License Application,to 257.1 rpm.Basically,the higher speed unit required a deeper.setting of the turbine distributor below tailwater.The depth shown in the License Application is, however,greater than necessary for the 225-rpm turbine and is sufficient for the 257.l-rpm turbine •..This increase in speed will reduce the physical size and cost of the turbine-generator set and also may possibly result in some reduction in the powerhouse size at the time the final design is made. (j)Gas Insulated Switchgear and Bus (***) Revisions of the high voltage conductors from the main power transformers to the ground surface and elimination of the ground level switchyard and bus are shown in Exhibit A. These revisions include use of a single 9-foot diameter vertical SF6 bus shaft instead of two vertical 7-foot 6-inch diameter cable shafts from the transformer gallery to the surface.All switching equipment will be underground,thus simplifying maintenance.This will·provide an improved environment for operation and maintenance by elimination of the potential for icing of equipment in a ground level switchyard.Substitution of SF6 buses for oil-filled cables will improve safety,removing fire hazards from the cable shaft area.Elimination of the switchyard will also reduce environmental impact and improve aesthetics by the construction of fewer and smaller surface structures. 851104 B-2-47 851104 \. 2.4 -Devil Canyon Project Formulation (0) This section describes the development of the general arrangement of the Devil Canyon project.The method of handling floods during con- struction and subsequent project operation is also outlined in this section. The reservoir level fluctuations and inflow for Devil Canyon will es- sentially be controlled by operation of the upstream Watana project. This aspect is also briefly discussed in this section. 2.4.1 -Selection of Reservoir Level (*) The selected normal maximum operating level at Devil Canyon Dam is el.1,455.Studies by the USBR and COE on the Devil Canyon project were-essentially based on a similar reservoir level, which corresponds to the average tailwater level at the Watana site.'Although the narrow configuration of the Devil Canyon site and the relatively low costs involved in increasing the dam height suggest that it might be economic to do so,it is clear that the upper economic limit of reservoir level at Devil Canyon .is the Watana tailrace level. Although significantly lower reservoir levels at Devil Canyon would lead to lower dam costs,the location of adequate spillway facilities in the narrow gorge would become extremely difficult and lead to offset ting increases in cos t."In the extreme case,a spillway discharging over the dam would raise concerns regarding safety from scouring at the toe of the dam,which have already -led-to-reTectTon-'orsli"cn"scliemes ; 2.4.2-Selectionof·lnstalledCapacity (*) The methodology .used f·or the preliminary selection of installed capacity at Devil Canyon is similar to the Watana methodology described in Section 2.2.2. -..--The--decision ·toopera-te--De vil"-Canyon.primari1,,y,,~.as..a base.",.l 0 ad . .._..''~_-plant_w.aL.gml.e.r-ne-d_b-y-the-fo.lLo.w:ing-ma.in_c_o.n.sJd_er.a.t.io.n.s..:.___..._ o Daily peaking is more effectively performed at Watana than at Devil Canyon;and o Excessive fluctuations in discharge from the Devil Canyon Dam may h~ve an undesirable impact on mitigation measures incorporated in the final design to protect.the downstream fisheries!. Given this mode of operation,the required installed capacity at Devil Canyon has been determined as the maximum capacity needed B-2-48 I J ] I j ,] .'J '.,I' .(".. ,\ " 851104 '\ I to utilize the available energy from the hydrological flows of record,as modified by the reservoir operation rule curves.In years where the energy from Watana and Devil Canyon exceeds the system demand,the usable energy has been reduced at both stations in proportion to the average net head available, assuming that flows used to generate energy at Watana will also be used to generate energy at Devil Canyon. Table B.2.4.l shows an assessment of maximum plant capacity required at Devil Canyon in the peak demand month (December). The Devil Canyon capacity is the same whether thermal energy is used for base load or for peaking,since Devil Canyon is designed for peaking only. The selected total installed capacity at Devil Canyon has been established as 600 MW for design purposes.This will provide some margin for standby during forced outage and possible accelerated growth in,.demand. The major factors governing the selection of the unit size at Devil Canyon are the rate of growth of system demand,the minimum station output,and the requirement of standby capacity under forced outage conditions. The power facilities at Devil Canyon have been developed using four units at 150 MWeach.This arrangement will provide for efficient station operation during low load periods as well as during peak December loads.During final design,consideration of phasing of installed capacity to match the system demand may desirable.However,the uncertainty of load,forecasts and the additional contractual costs of mobilization for equipment installation are such that for this study it has been assumed that all units will be commissioned by 2002 •. The Devil Canyon Reservoir will usually be full in December; hence,any forced outage could result in spilling and ~loss of available energy.The units have been rated to deliver 150 MW at maximum December drawdown occurring during an extremely dry year; this means that,in an average year,with higher reservoir levels,the full station output can be maintained even with one unit on forced outage. 2.4.3 -Selection of Spillway Capacity (*) A flood frequency of 1:10,000 years was selected for the spillway design on the same basis as described for Watana.An emergency spillway with an erodible fuse plug will also be provided to safely discharge the probable maximum flood.The development plan envisages completion of the Watana project prior to construction at Devil Canyon.Accordingly,the inflow flood B-2-49 peaks at Devil Canyon will be less than pre"'project flood peaks because of routing through the Watana reservoir.Spillway design floods are: Flood 1:10,000 years Probable Maximum Inflow Peak (cfs) 165,000 345,000 I ,'I Ij The avoidance of nitrogen supersaturation in the downstream flow for Watana also will apply to Devil Canyon.Thus,the discharge of water possibly supersaturated with nitrogen from Devil Canyon will be limited to a recurrence period of not less than 1:50 years by the use of fixed-cone valves similar to Watana. 2.4.4 -Main Dam Alternatives (*) The location of the Devil Canyon damsite was examined during previous studies by the USBR and COED These studies focused on the narrow entrance to the cany~n and led to the recommendation of a concrete arch dam.Notwithstanding this initial appraisal, a comparative analysis was undertaken as part of this feasibility study to evaluate the relative merits of the following types of structures at the same location: o Thick concrete arch o Thin concrete arch~ o Fill embankment. (a)Comparison of Embankment and Concrete Type Dams (*) The geometry was developed fbrboth the thin concrete arch and the thick concrete arch dams,and the dams were analyzed and their behavior compared under static, hydrostatic,and seismic loading conditions.The project layouts for these arch dams were compared to a layout for a rockfill dam with its associated structures • .·-----Considera·t'ion-of-the·centra-l-·core-rockfi-H-dam-l-ayout·· indicated relatively small cost differences from an arch dam cost estimate,based on a cross section significantly thicker than the finally selected design.Furthermore,no information was available to indicate that impervious core material in the necessary quantities could be found within a reasonabledistance.of thedamsite •...The ..rockfill dam was accordingly dropped from further consideration.It is further noted:that ,since .this~·al tercnat-ive dam s tudYT seismic analysis of the rockfill dam at Watana has resulted in an upstream slope of 2.4H:IV,thus indicating the \J ,I I ) .J I 851104 B-2-50 851104 requirement to flatten the 2.5H:IV slope adopted for the rockfill dam alternative at Devil Canyon. Neither of the concrete arch dam layouts was intended as the final site arrangement,but were sufficiently representative of the most suitable arrangement associated with each dam type to provide an adequate basis for comparison.Each type of dam was located just downstream of the point where the river enters Devil Canyon and close to the canyon's narrowest point,which is the optimum location for all types of dams.A brief description of each dam type and configuration is given below. (i)Rockfill Dam (*) For this arrangement the dam axis would be some 625 feet downstream of the crown section of the concrete dams.The assumed embankment slopes would be 2.25H:1V on the upstream face and 2H:1V on the downstream face.The main dam would be continuous with the south bank saddle dam,and therefore no thrust blocks would be required.The crest length would be 2,200 feet at el.1,470;the crest width would be 50 feet. The dam would be constructed with a central impervious core,inclined upstream,supported on the downstream side by a semi-pervious zone.These two zones would be protected upstream and downstream by filter and transition materials.The shell sections would be constructed of rockfill obtained from' blasted bedrock.For preliminary design all dam sections would be assumed to be founded on rock; external cofferdams would be founded on the river alluvium,and would not be incorporated into the main dam.The approximate volume of material in the main dam would be 20 million cubic yards. A single spillway would be provided on the north abutment to control all flood flows.It would consist of a gate control structure and a double stilling basin excavated into rock;the chute sections and stilling basins would be concrete-lined, with mass concrete gravity retaining walls.The design capacity would be sufficient to pass the l:lO,OOO-year flood without damage;excess capacity would be provided to pass the PMF without damage to the main dam by surcharging the reservoir and spillway. B-2-5l 851104 The powerhouse would be located underground in the north abutment.The multi-level power intake would be constructed in a rock cut in the north abutment on the dam centerline,with four independent penstocks to the 150-MW Francis turbines.Twin concrete-lined tailrace tunnels would connect the powerhouse to the river via an intermediate draft tube manifold. (ii)Thick Arch Dam (*) The main concrete dam would be a single-center arch structure,acting partly as a gravity dam,with a verti~al cylindrical upstream face and a sloping downstream face inclined at IV:0.4H.The maximum height of the dam would be 635 feet,with a uniform crest width of 30 feet,a crest length of approxi- mately 1,400 feet,and a maximum foundation width of 225 feet.The crest elevation would be 1,460.The center portion of the dam would be founded on a massive mass concrete pad constructed inthe;t:excavat- ed riverbed.This central section.would incorporate the main spillway with sidewalls anchored into solid bedrock and gated orifice spillways discharging down the steeply inclined downstream face.of the dam into a single large stilling basin set below river level and.spanni ng the valley. The main dam would terminate in thrust blocks high on ...theabutments.•..~.~Thesou-th abutment~.thrustblock_would. incorporate an emergency gated control spillway structure which would discharge into a rock channel running well'downstream and terminating at a level high above the river valley. Beyond the control structure and thrust block,a low-lying saddle on the south abutment would be closed by means of a rockfill dike founded on '·6earock~··""The·powerholis'e'wouldhouserour-T5<F·MW --------u:nns~and'wouIdDelocateatmderground--Wnnin·tne-~' north abutment.The intake would be constructed integrally with the dam and connected to the powerhouse by vertical steel-lined penstocks. The main spillway would be designed to pass the 1:10,000-year ,routed flood.The probable maximum W()ul<i)"eQ..a,ss!id'byc::()1l!1.'!.irie.ddis.c;1:'large s through the main spillway;()utletfacility;and emergency spillway. B-2-52 ,1 ,j "I (iii)Thin Arch Dam (*) The main dam would be a two-center,double-curved arch structure of similar height to the thick arch dam,but with a 20-foot uniform crest and a maximum base width of 90 feet.The crest elevation would be 1,460.The center section would be founded on a concrete pad,and the extreme upper portion of the dam would terminate in concrete thrust blocks located on the abutments. The main spillway would be located on the north abutment and would consist of a conventional gated control structure discharging down a concrete-lined chute terminating in a flip bucket.The bucket would discharge into an unlined plunge pool excavated in the riverbed alluvium and located sufficiently downstream to prevent undermining of the dam and associated structures. The main spillway would be supplemented by orifice type spillways located in the center portion of the dam,which would discharge into a concrete-lined plunge pool immediately downstream from the dam.An emergency spillway consisting of a fuse plug discharging into an unlined rock channel terminating well downstream would be located beyond the saddle dam on the south abutment. The concrete dam would terminate in a massive thrust block on each abutment which,on the south abutment, would adjoin a rockfill saddle dam. The main and auxiliary spillways would be designed to discharge the 1:10,000-year flood.The probable maximum flood would be discharged through the emergency south abutment spillway,main spillway and auxiliary spillway. (b)Comparison of Arch Dam Types (*) Sand and gravel for concrete aggregates are believed to be available in sufficient quantities within economical distances from the damsite.The gravel and sands are formed from the granitic and metamorphic rocks of the area;at this time it is anticipated that they will be suitable for the production of aggregates after screening and washing. The bedrock geology of the site is discussed in the 1980-81 Geotechnical Report (Acres 1982a).At this time it appears 851104 B-2-53 that there are no geological or geotechnical concerns that would preclude either of.the dam types from consid·eration. Under hydrostatic and temperature loadings,stresses within the thick arch dam would be generally lower than for the thin arch alternative.However,finite element analysis has shown that the additional mass of the dam under seismic loading would produce stresses o.fa greater magnitude in the thick arch dam than in the thin'arch dam.If the surface stresses approach the maximum allowable at a particular section,the remaining understressed area of concrete will be greater for the thick arch,and the factor of safety for the dam would be correspondingly higher.The thin arch is, however,a more efficient design and better utilizes the inherent properties of the concrete.It is designed around acceptable predetermined factors of safety and requires a much smaller volume of concrete for the actual dam structure. The thick arch arrangement did not appear to have a distinct technical advantage compared toa thin arch dam and would be more expensive.because of the'larger volume of concrete needed.Studies therefore continued on refining the feasibility of the thin arch alternative. 2.4.5 -Diversion Scheme Alte:rnatives (*) In this section the selection of general arrangement and the .-..---·ba·s-is·"·for-cs-izing"·of....the~di-vers·ion"schemeare···pres ented.. (a)General Arrangements (*) The steep",:"walled valley at the si teessentially dictated that diversion of the river during construction be accomplished using one or two diversion tunnels,with upstream.and downstream cofferdams protecting the main g()..ll.§t::r1,1(,:j:j&1l,.g.J:'~.g!. .-______I "-___.._. The selection process .for establishing the final general arrangement included examination of tunnel locations on both banks of .the river.Rock conditions for tunneling did not favor one bank over the other.Access and ease of construction strongly favored .the south bank or abutment, the obvio.us,approach being via the alluvial fan.The total ·leilgth6f.tunnel'require'dfor tli¢<,s0tJth bank is .approximately300feetgreater.;c.however,-.a.ccess to the north bank cOuld nOi::be achievedwfEhou'i::···gr'eat:'·difficUlfY. .,) ,I I 1 I "I 'J j 851104 B-2-54 (b)Design Flood for Diversion (*) The recurrence interval of the design flood for diversion was established in the same manner as for Watana Dam. According~y,at Devil Canyon a risk of exceedance of 10 percent per annum has been adopted,equivalent to a design flood with a 1:10-year return period for each year of critical construction exposure.The critical construction time is estimated at 2.5 years.The main dam could be subjected to overtopping during construction without causing serious damage,and the existence of the Watana facility upstream would offer considerable assistance in flow regulation in case of an emergency.These considerations led to the selection of the design flood with a return frequency of 1:25 years. The equivalent inflow,together with average flow characteristics of the river significant to diversion,are presented below: o Average annual flow: 9,080 ds o Design flood inflow (1:25 years routed through Watana reservoir): 37,800 cfs (c)Cofferdams (*) As at Watana,the considerable depth of riverbed alluvium at both cofferdam sites indicates that embankment-type cofferdam structures would be the only technically and economically feasible alternative at Devil Canyon.For the purposes of establishing the overall general arrangement of the project and for subsequent diversion optimization studies,the upstream cofferdam section adopted will comprise an initial closure section approximately 20 feet high constructed in the wet,with a zoned embankment constructed in the dry.The downstream cofferdam will comprise a closure dam structure approximately 30 feet high placed in the wet.Control of underseepage through the alluvium material may be required and could be achieved by means of a grouted zone.The coarse nature of the alluvium at Devil Canyon led to the selection of a grouted zone rather than a slurry wall. (d)Diversion Tunnels (*) Although studies for the Watana project indicated that concrete-lined tunnels are the most economically and 851104 B-2-55 technically feasible solution,this aspect was reexamined at Devil Canyon.Preliminary hydraulic studies indicated that the design flood routed through the diversion scheme would result in a design discharge of approximately 37,800 cfs. For concrete-lined tunnels,design velocities of approximately 50 ft/sec would permit the use of one concrete-lined tunnel with an equivalent diameter of 30 feet.Alternatively,for unlined tunnels a maximum design velocity of 10 ft/sec in good quality rock would require four unlined tunnels,each with an equivalent diameter of 35 feet,to pass the design flow.As was the case for the Watana diversion scheme,considerations of reliability and cost were considered sufficient to eliminate consideration of unlined tunnels for the diversion scheme. For the purposes of optimization studies,only a pressure tunnel was considered,since previous studies indicated th.at cofferdam closure problems associated with free flow tunnels would more than offset their other advantages. (e)Optimization of Diversion Scheme (*) Given the considerations described above relative to design flows,cofferdam configuration,and alternative types of tunnels,an economic study was undertaken to determine the optimum combination of upstream cofferdam elevation (height) and tunnel diameter. ____c~Gapital costs!,?er~L.develop~<!tQ.~~..'J;:angg,Q.Lp'J;:§L~sUI'~.t:tJ.J:l.n.§l diameters and corresponding upstream cofferdam embankment crest elevations with a 30-foot wide crest and exterior slopes of2H:lV.A freeboard allowance of 5 feet was included for.settlement and wave runup. Capital costs for the tunnel alternatives included allowances for excavation,concrete liner,rock bolts,and steel supports.Costs'were also developed for the upstream ..····_-..··-·-and·downs·tre-am-por·tats·-;-tncl'uding-excavation-and··slippor·t-;-··. ..._.._--.-The..·co·st--of--an····intake--gate······s·t·ructure-and--associa·ted-·ga·te's···· was determined not to vary significantly with tunnel diameter and was excluded from the analysis. The centerline tunnel length in all cases was estimated to be 2,000 feet. Rating curves for the single pressure tunnel alternatives are presented inFigur·e:8~2.4~:"1"::===The=~i'e.fati()i:ishipbetween capital costs for the upstream cofferdam and various tunnel diameters is given in Figure B.2.4.2. ··,1c."! i 1 !f :1 85.1104 B-2-56 ·l The results of the optimization study indicated that a single 30-foot diameter pressure tunnel results in'the overall least cost (Figure B.2.4.2).An upstream cofferdam cofferdam 60 feet high,with a crest elevation of 945,was carried forward as part of the selected general arrangement. 2.4.6 -Spillway Alternatives (*) The project spillways have been designed to safely pass floods with the following return frequencies: Inflow Peak Flood Spillway Design Probable Maxhnum Discharge Frequency 1:10,000 years Inflow (cfs) 165,000 345,000, 851104 A number of alternatives were considered singly and in combina tion for Devil Canyon spillway facilities.These inc1 uded gated orifices in the main dam discharging into a plunge pool, chute or tunnel spillways with either a flip bucket or stilling basin for energy dissipation,and open channel spillways.As described for Watana,the selection of the type of spillway was influenced by tQe general arrangement of the major structures. The main spillway facilities would discharge the spillway design flood through a gated spillway control structure with energy dissipation by a flip bucket which directs the spillway discharge in a free-fall jet into a plunge pool in the river.As noted above,restrictions with respect to limiting nitrogen supersaturation in selecting acceptable spillway discharge structures have been applied.The various spillway arrangements developed in accordance with these considerations are discussed in Section 2.5. 2.4.7 -Power Facilities Alternatives (*) The selection of the opthnum arrangements for the power facilities involved consideration of the same factors as described for Watana. (a)Comparison of Surface and Underground Powerhouses (*) A surface powerhouse at Devil Canyon would be located either at the downstream toe of the dam or along the side of the canyon wall.As determined for Watana,'costs favored an underground arrangement.In addition to cost,the under- ground powerhouse layout has been selected based on the following: B-2-57 o Insufficiertt space is available in the steep-sided canyon for a surface powerhouse at the base of the dam; o The provision of an extensive intake at the crest of the arch dam would be detrimental to stress conditions in the arch dam,particularly under earthquake loading,and would require significant changes in the arch dam geometry;and o The outlet facilities located in the arch dam are designed to discharge directly into the river valley; these would cause significant winter icing and spray problems to any surface structure below the dam. (b)Comparison of Alternative Locations (*) The underground powerhouse and related facilities have been located on the north bank for the following reasons: o Generally superior rock quality at depth; o The south bank area behind the main dam thrust block is unsuitable for the construction of the power intake;and . o The river turns north downstream from the dam,and hence the north bank power development is more suitableforextending~the tailrace~tunneltodevelop extra head. (c)Selection of Units (*) The turbine type seiected for the Devil Canyon development is governed by the design head and specific speed and by economic considerations.Francis turbines have been adopted for reasons similar to those discussed for Watana in The selection of the number and rating of individual units is discussed in detail in subsection 2.4.2.The four units will be rated to deliver 150 MW each at full gate opening and minimum reservoir level in December (the peak demand month)• (d)Transformers (*) Transformer selection is similar to Watana subsection 2.2.7(e). I I I 851104 B-2-58 ,J (e)Power Intake and Water Passages (*) For flexibility of operation,individual penstocks are provided to each of the four units'.Detailed cost studies showed that there 1s no significant cost advantage ~n using two larger diameter penstocks with bifurcation at the powerhouse compared to four separate penstocks. A single tailrace tunnel with a length of 6,800 feet to develop 30 feet of additional head downstream from the dam has been incorporated in the design.Detailed design may indicate that two smaller tailrace tunnels for improved reliability may be superior to one large tunnel since the extra cost involved is relatively small.The surge chamber design would be essentially the same with one or two tunnels. The overall dimensions of the intake structure are governed by the selected diameter and number of the penstocks and the minimum penstock spacing.Detailed studies comparing construction cost to the value of energy lost or gained were carried out to determine the optimum diameter of the penstocks and the tailrace tunnel. (f)Environmental Constraints (*) In addition to potential nitrogen-supersaturation problems caused by spillway operation,the major impacts of the Devil Canyon power facilities development are: o Changes in the temperature regime of the river;and o Fluctuations in downstream river flows and levels. Temperature modeling has indicated that a multiple-level intake design at Devil Canyon would aid in controlling downstream water temperatures. Consequently,the intake design at Devil Canyon incorporates two levels of draw-off. The Devil Canyon station will normally be operated as a base-load plant throughout the year to satisfy the requirement of no significant daily variation in power flow. 851104 B-2-59 2.5 -Selection of Devil Canyon General Arrangement (*) The approach to selection of a general arrangement for Devil Canyon was a similar but simplified version of that used for Watana. 2.5.1 -Selection Methodology (*) Preliminary alternative arrangements of the Devil Canyon project were developed and selected using two rather than three review stages.Topographic conditions at this site limited the development of reasonably feasible layouts,and four schemes were initially developed and evaluated.During the final review,the selected layout was refined based on technical,operational and environmental considera tions identified during the prel iminary review. 2.5.2 -Design Data and Criteria (*) The design data and design criteria on which the alternative layouts were based are presented in TableB.2.5.i.Subsequent to selection of the preferred Devil Canyon scheme,the information was refined and updated as part-of the ongoing study program. 2.5.3 -Preliminary Review (*) Consideration of the options available for types and locations of various structures led to the development of four primary layouts for examination at Devil Canyon in the preliminary review -..phase-;~-Previous stud±eshad-l-edtoth·e se·lection-··of-a .thin-.. concrete arch structure for the main dam and indicated that the most acceptable technical and economic location was at the upstream entrance to the canyon.The dam axis has been fixed in this location for all alternatives. (a)Description of Alternative Schemes (*) The s.ch emes.e'Va luated_.during_theprel im inaryreJdew.are ._..._.__~__~..._described below.In.each of the alternatives evaluated,_ the dam is founded on the sound bedrock underlying the riverbed.The structure is 635 feet high,has a crest width of 20 feet,and.a maximum base width of 90 feet.Mass concrete thrust blocks are founded high on the abutments, the south block extending approximately 100 feet above the existing bedrock surface and supporting the upper arches of the dam.The thrust block on the north abutillerif makes the cross-river profile of the dam more sYmmetrical andc:on-td.btites .toa more unIfomsEressdIst:rIbtidon. :[ ] 851104 B-2-60 J 851104 (i)Scheme DC1 (Figure B.2.5.1)(*) .In this scheme,diversion facilities comprise upstream and downstream earthfill and rockfill cofferdams and two 24-foot diameter tunnels beneath the south abutment. A rockfill saddle dam occupies the lower-lying area beyond the south abutment running from the thrust block to the higher ground beyond.The impervious fill cut-off for the saddle dam is founded on bedrock approximately 80 feet beneath the existing ground surface.The maximum height of this dam above the foundation is approximately 200 feet. The routed 1:10,000~year design flood of 165,000 cfs is passed by two spillways.The main spillway is located on the north abutment.It has a design discharge of 120,000 cfs,and flows are controlled by a three-gated.ogee control structure.This discharges down a concrete-lined chute and over a flip bucket ,which ejects the water in a diverging jet into a pre-excavated plunge pool in the riverbed. The flip bucket is set at el.925,approximately 35 feet above the river level.An auxiliary spillway discharging a total of 35,000 cfs is located in the center of the dam,100 feet below the dam crest,and is controlled by three wheel-mounted gates.The orifices are designed to direct the flow into a concrete-lined plunge pool just downstream from the dam. An emergency spillway is located in the sound rock south of the saddle dam.This is designed to pass, in conjunction with the main spillway and auxiliary spillway,a probable maximum flood of 345,000 cfs,if such an event should ever occur.The spillway is an unlined rock channel which discharges into a valley downstream from the dam leading into the Susitna River. The upstream end of the channel is closed by an earthfill fuse plug.The plug is designed to be eroded if ov~rtopped by the reservoir.Since the crest is lower than either the main or saddle dams, the plug would be washed out prior to overtopping of either of these structures. The underground power facilities are located on the north bank of the river,within the bedrock forming B-2-61 851104 the dam abutment.The rock within this abutment is of better quality with fewer shear zones and a lesser degree of jointing than the rock on the south side of the canyon,and hence more suitable for underground excavation. The power intake is located just upstream from the bend in the valley before it turns sharply to the right into Devil Canyon.The intake structure is set deep into the rock at the downstream end of the approach channel.Separate penstocks for each unit lead to the powerhouse. The powerhouse contains four 150-MW turbine/generator .units.The turbines are Francis type units coupled to overhead synchronous generators.The units are serviced by an overhead crane running the 'length of the powerhouse and into the end service bay. Offices,the control room,switchgear room, maintenance room,etc.,are located beyond the service bay.The transformers are housed in a separate upstream gallery located above ..the lower horizontal section of the penstocks.Two vertical cable shafts connect the gallery to the surface.The draft tube gates are housed above the draft tubes in separate annexes off·the main powerhall.The draft tubes converge in two bifurcations at the tailrace tunnels which discharge under free flow conditions to ,.tlHLrill..eX.Ac..ce..s..s ..t.o_the.po..werhollse.isb..y ..means.of ... an unlined tunnel leading from an access portal on the north side of the canyon.. The switchyard is located on the south bank of the tivet"justdoWnstream from the saddle dam,and the power cables from the transformers are carried to it across the top of the dam. ---___.._._.._-_-_.. The layout is generally similar to Scheme DCI except that the chute spillway is located on the south side of the canyon.The concrete-lined chute terminates in a flip bucket high on the south side of the canyon,dropping the discharge into the river below.Thedesign.f1ow is 120,000 cis,and discharge are controlled by ath·tee..;;gatedogee....crested control structures{niIlarto that ·forScherne DCl;which abuts the south side thrust block. B-2-62 .( ../ 851104 The saddle dam axis is straight,following the shortest route between the control structure at one end and the rising ground beyond the low-lying area at the other. (iii)Scheme DC3 (See Figure B.2.5.3)(*) The layout is similar to Scheme DCl except that the north-side main spillway takes the form of a single tunnel rather than an open chute.A two-gated ogee- control structure is located at the head of the tunnel and discharges into an inclined shaft 45 feet in diameter at its upper end.The structure will discharge up to a maximum of 120,000 cfs. The concrete-lined tunnel narrows to 35 feet in diameter and discharges into a flip bucket which directs the flows in a jet into the river below,as in Scheme DCl. An auxiliary spillway is located in the center of the dam and an emergency spillway is excavated on the south abutment. The layout of dams and power facilities are the same as for Scheme DCl. (iv)Scheme DC4 (See Figure B.2.5.4)(*). The dam,power facilities,and saddle dam for this scheme are the same as those for Scheme DCl.The major difference.is the substitution of a stilling basin type spillway on the north bank for the chute and flip bucket.A three-gated ogee control structure is located at the end of the dam thrust block and controls the discharges up to a maximum of 120,000 cfs. The concrete-lined chute is built into the face of the canyon and discharges into a 500-foot long by l15-foot wide by 100-foot high concrete stilling basin formed below river level and deep within the north side of the canyon.Central orifices in the dam and the south bank rock channel and fuse plug form the auxiliary and emergency spillways, respectively,as in the other alternative schemes. The downstream cofferdam is located beyond the stilling basin and the diversion tunnel outlets are B-2-63 located farther downstream to enable construction of the stilling basin. (b)Comparison of Alternatives (*) The arch dam,saddle dam,power facilities,and diversion vary only in a minor degree among the four alternatives. Thus,the comparison of the schemes rests solely on a comparison of the spillway facilities • .As can be seen from a comparison of the costs in Table B.2.5.2,the flip bucket spillways are substantially less costly to construct than the stilling basin type of Scheme DC4.The south-side spillway of Scheme DC2 runs at a sharp angle to the river and ejects the discharge jet from high on the canyon face toward the opposite ~ide of the canyon. Over a longer period of operation,scour of the heavily jointed rock could.cause undermining of the canyon sides and their subsequent instability.The possibility also exists of deposition of material in the downstream riverbed with a corresponding elevation of the tailrace.Construction of a spillway on the steep south side of the river could be more difficult than on the north side because of the presence of deep fissures and large unstable blocks of rock which are present on the south side close to the top of the canyon. The two north-side flip bucket spillway schemes,based on either an open chute or a tunnel,take advantage of a ..downs.tream..bend..intheriv.erto..di schar.ge .parallelto .the course of the river.This will reduce the effects of erosion but could still present a problem if the estimated m.iiximum possible scour hole should occur. t'hetunnel type spillway could prove difficult to construct because of the large diameter inclined shaft and tunnel paralleling the bedding planes.The high velocities encountered in the tunnel spillway could cause problems with.·the-possT6ITIty of 'spIralIiig-flows an;r~sever ec·avi.t:atlon··... The stilling basin type spillway of Scheme DC4 reduces downstream erosion problems within the canyon.However, cavitation could be a problem under the high flow velocities experienced at the base of the chute.This would be somewhat alleviated by aeration of the flows..There is, however~little precedent forstilTirigbasin operation at heads of over 500 feet;even where floods of much less than the design capacity have been diSCharged,severe damage has occurred. I 1 851104 B-2-64 .\ Ij (c)Selection of Final Scheme (*) The chute and flip bucket spillway of Scheme DC2 could generate downstream erosion problems which could require considerable maintenance costs and cause reduced efficiency in operation of the project at a future date.Hydraulic design problems exist with Scheme DC3 which may also have severe cavitation problems.Also,there is no cost advantage in Scheme DC3 over the open chute Scheme DC1.In Scheme DC4,the operating characteristics of a high head stilling basin are little known,and there are few examples of successful operation.Scheme DC4 also costs considerably more than any other scheme (Table B.2.5.2). All spillways operating at the required heads and discharges will eventually cause some erosion.For all shemes,the use of solid-cone valve outlet facilities in the lower portion of the dam to handle floods up to 1:50 -year frequency is considered a more reasonable approach to reduce erosion and eliminate nitrogen supersaturation problems than the gated high-level orifice outlets in the dam.Since the cost of the flip bucket type spillway in the scheme is considerably less than that of the stilling basin in Scheme DC4,and since the latter offers no relative operational advantage, Scheme DCl has been selected for further study as the selected scheme. 2.5.4 -Final Review (*) The layout selected in the previous section was further developed in accordance with updated engineering studies and criteria. The major change compared to Scheme DCl is.the elimination of the high-level gated orifices and introduction of low-level fixed-cone valves,but other modifications that were introduced are described below. The revised layout is shown on Figure B.2.5.5.A description of the structures is as follows. (a)Main Dam (*) The maximum operating level of the reservoir was raised to el.1,455 in accordance with updated information relative to the Watana tailwater level.This requires r~ising the dam crest to el.1,463 with the concrete parapet wall crest at el.1,466.The saddle dam was raised to el.1,472. (b)Spillways and Outlet Facilities (*) To eliminate the potential for nitrogen supersaturation problems,the outlet facilities were designed to restrict 851104 B-2-65 \' supersaturated flow to an average recurrence interval of greater than 50 years.This led to the replacement of the high-level gated orifice.spil:J.way by outlet facilities incorporating seven fixed-cone valves,three with a diameter of 90 inches and four wi.th a diameter of 102 inches,capable of passing a design flow of 38,500 cfs. The chute spillway and flip bucket are located on the north bank,as in Scheme DCl;however,the chute length was decreased and the elevation of the.flip bucket raised compared to Scheme DCl. More recent site surveys indicated that the ground surface in the vicinity of the saddle dam was lower than originally estimated.The_emergency spillway channel was relocated slightly""to the south to accommodate the larger dam. (c)Diversion (*) The prevtous twin diversiqn tunnels were replaced by a single tunnel scheme.This was determined to provide all necessary security and will cost approximately one-half as much as the.two tunnel alternative. "J (d)Power Facilities (*) The drawdown range of the reservoir was reduced,allowing a reduction in height of the power intake.In order to .1ocate.the--intake-wi-th-in--so-l-id--rock,·-it:·has-·been .move d into'" the side of.the valley,requiring a slight rotation of the water passages,powerhouse,and caverns comprising the power fad lides. Subsequent to the adoption oftflis schetne and-prior to submission of the July 1983 License Application,refinements to the design were made as presented in Exhibit F. _,._--_._..•-~----,_._,.._.----_-_.-,.__._--_.•._,-.._-__.-..__..---.__._--._.,..-. •....Am.endlllent to License Application (***) The amended layout of Devil Canyon (Stage II)is presented in Figure B.2.3.ll.This eliminates the emergency spillway and increases the discharge capacity of the chute spillway and flip .bucket to pass the rout~d PMF.This revis.ion will reduce cost of the development and reduce terrestrial and .aesthetic impacts by ...reducing ground surface disturbance. The capacity of the spillway will be increased by providing larger gates and increasing the width of the chute and flip 851104 B-2-66 851104 I bucket.Each of the three gates will be increased from 30 feet wide by 56 feet high to 48 feet wide by 58 feet high. The chute width,which varied from 122 feet to 80 feet,will be increased to vary from 176 feet to 150 feet.The flip bucket width will be increased from 80 feet to 150 feet wide.The crest of the spillway control structure will be lowered from el.1,404 to el.1,398. The type of gate and operator will be revised from fixed wheel gate with electric motor driven drum hoist to tainter gate with hydraulic cylinder hoist.The gate type revision will cost less and provide improved operating cha~acteristics. The flood hydrology for the higher frequency floods has been reevaluated based on additional years of records.The peak inflows for the 1:25 and 1:50 year floods routed through Watana (Stage I)reservoir and the intervening flow are,respectively 43,300 and 46,900cfs. The impact of this change will be principally on the construction diversion,requiring the tunnel diameter to be increased from 30 feet to 35.5 feet while maintaining the upstream cofferdam crest at elevation 945.This solution is conservative and during the design phase optimization studies will be made to determine the optimum cofferdam height versus tunnel diameter. The outlet facilities of three 90-inch and four 102-inch fixed cone valves operating at an 80 percent opening are capable of passing the 1:50 year flood without surcharging the reservoir above Elevation 1,456. 2.6 -Selection of Access Road Corridor (*) 2.6.1 -Previous Studies (*) The potential for hydroelectric power generation within the Susitna basin has been the subject of considerable investigation over the years,as described in Section 1.1 of this exhibit.These studies produced much information on alternative development plans but little on the question of access. The first report to incorporate an access plan was that of the Corps of Engineers in 1975.The proposed plan consisted of a 24- foot wide road with a design speed of 30 miles per hour that connected with the Parks Highway near Chulitna Station, paralleled the Alaska Railroad south and east to a crossing of the Susitna River,then proceeded up the south side of the river to Devil Canyon.The road continued on the south side of the Susitna River to Watana,passing by the north end of Stephan Lake B-2-67 and the west end of the Fog Lakes.In addition,a railhead facility was to be constructed at Gold Creek.This plan is S1m1- lar to one of the selected alternative plans,Plan 16 (South), discussed later in this section. Other studies concerning the Susitna Hydroelectric Project men- tioned access only in passing and did not involve the development of an access plan. This section of the License Application outlines the studies carried out asa basis for formulation and selection of the preferred hydroelectric plans.These studies were conducted over the period 1979 through 1982 and are based on cost data and load forecasts from that period of study.These data were analyzed consistently in each study iteration and the resulting development plans are the most attractive alte'rnat ives. 2.6.2 -Selection Process Constraints (*) Throughout the development,evaluation;,and selection of the access plans,the foremost o~jective has been to provide a transportation system that would supportconstruc.tion activities and-allow for-the orderiy deveiopInemi:and'maint-Emance of site facilities. Meeting this fundamental objective involved the consideration not only of economics'and technical re-ase of development,but also many other diverse factors.Of prime importance was the potential for impacts to the environment,namely impacts to the ~~tocar-fiSli and~game populations.--~lilaaaition,--sIncetl:ie Native villages and the Cook Inlet Region will acquire surface and subsurface rights adjacent to the project,their interests were recognized and taken into account as were those of the local communities and general public. With so many different factors influencing the choice of an access plan,it is evident that no one plan will satisfy all interests.,The aim d uringthe ..selec,t:ion-pI'ocesshas-been ··to consider a_l_Lfa..c_t_o_r_s,_in,_their_prop_er~per,s_pec_tiv_eand_,pr.oduce-a plan that represents the most favorable solution to meeting both project-'related goals and minimizing impacts to the environment and surrounding communities. 2.6.3 -Corridor Identification and Selection (*) 'three generai corridor'swere iden'tified leading fr~m the existing ____.!=!,~!l,~PQ:C:~?l:iQ:9..n~l:wo:r:t<:tothe<ialI1si te.s..This network cons i st s of the Parks Highway and the Alaska Railroad to the west of the damsites and the Denali Highway to the north.The three general corridors are identified in Figure B.2.6.L ,j 1 "1 'I 851104 B-2-68 Corridor 1 -From the Parks Highway to the Watana damsite via the north side of the Susitna River. Corridor 2 -From the Parks Highway to the Watana damsite via the south side of the Susitna River. Corridor 3 -From the Denali Highway to the Watana damsite. The access road studies identified a total of eighteen alternative plans within the three corridors.The alternatives were developed by laying out routes on topographic maps in accordance with accepted road and rail design criteria.Subsequent field investigations resulted in minor modifications to reduce environmental impacts and improve alignment. 2.6.4 -Development of Plans (*) At the beginning of the study a plan formulation and initial selection process was developed.The criteria that most significantly au:£ected the initial selection process were identified as: o Minimizing impacts on the environment; o Minimizing total project costs; o Providing transportation flexibility to minimize construction risks;and o Providing ease of operation and maintenance. During evaluation of the access plans,input from the public agencies and Native organizations was sought and their response resulted in an expansion of the original list of eight alternative plans to eleven.These studies culminated in the production of the Access Route Selection Report (Acres 1982b) which recommended Plan 5 as the route which most closely satisfied the selection criteria.Plan 5 starts from the Parks Highway near Hurricane and traverses southeast along the Indian River to Gold Creek.From Gold Creek the road continues east on the south side of the Susitna River to the Devil Canyon damsite, crosses a low-level bridge and continues east on the north side of the Susitna River to the Watana damsite.For the project to remain on schedule it would have been necessary to construct a pioneer road along this route to facilitate bridge construction prior to the FERC license being issued. In March of 1982 the Alaska Power Authority (APA)presented the results of the Susitna Hydroelectric Feasibility Report (Acres 1982c),of which access Plan 5 was a part,to the public, agencies and organizations.During April,comment was obtained from these groups relative to the feasibility study.As a result of these comments,the pioneer road concept was eliminated,the 851104 B-2-69 evaluation criteria were refined,and six additional access alternatives were developed. During the evaluation process the Applicant formulated an additional plan,thus increasing the total number of plans under evaluation to eighteen.This subsequently became the plan recommended by Applicant's staff to the Applicant's Board of Directors,and was formally adopted as the Proposed Access Plan in September 1982. 2.6.5 -Evaluation of Plans (*) The refined criteria used to evaluate the eighteen alternative access plans were: o No pre-license construction o Minimize environmental impacts o Minimize construction duration o Provide access·between sites during project operation phase o Provide access flexibility to ensure project is brought on line within budget and schedule o Minimize total cost of access o Minimize initial investment required to provide access to the Watana damsite o Minimize.risks to project schedule t. o Accommodate current land uses and plans o Accommodate agency preferences o Ac:(:~g'J.!l!ll()dat;~·"Rr~:l:e~~I!~_~~.QJl'1at:ive organizations o Accommodate preferences of loc~l communities o Accommodate public concerns All eighteen plans were evaluated using these refined criteria to determine the most responsive access plan in··each of the"three basic corridors. To meet the overall project schedule requirements for the Watana ··_··_'-··-·deve-Iopment;···it··-is·-neces·sary--··t·(f·-secure i"iriHaracc·e~fs-to th-e--- .----.------·--Wa"t-a·na~damsi-te-wi-th·in-one-con·st·ruc-tron-s·e-a·son-or-the-FERC--I-ic-ens-e-- being issued.The con~traint of no pre-license construction resulted in the elimination of any plan in which initial access could not be completed within one year.This constraint eliminated six plans (plans 2,5,8,9,10,12)from further consideration. On completion of boththeWatan~andDevilC~nyonDamsCitis ·plariried-tOopera.t-e·and~II1ailit:a.inbothsite:s:fr()mone·central location,Watana.To facilitate these operation and maintenance activites,access plans with a road connection between the sites were considered superior to those plans without a road I 1 .\ 851104 B-2-70 1 1 connection.Plans 3 and 4 do not have access between the sites and were discarded. The ability to make full use of both rail and road systems from southcentral ports of entry to the railhead facility provides the project management with far greater flexibility to meet contingencies;and control costs and schedule.Limited access plans utilizing an all-rail or rail-link system with no road connection to an existing highway have less flexibility and would impose a restraint on project operation that could result in delays and significant increases in cost.Four plans with limited access (plans 8,9,10 and 15)were eliminated because of this constraint. Residents of the Indian River and Gold Creek communities are generally not in favor of a road access near their communities. Plan 1 was discarded because plans 13 and 14 achieve"the same objectives without impacting the Indian River and Gold Creek areas. Plan 7 was eliminated because it includes a circuit route connecting to both.the George Parks and Denali Highways.This circuit route was considered unacceptable by the resource agencies since it aggravated the control of public access. The seven remaining plans found to meet the selection criteria were plans 6,11, 13, 14, 16,17 and 18.Of these plans,plans 13,16 and 18 in the North,South,and Denali corridors, respectively,were selected as being the most responsive plan in each corridor.The three plans are described below and the route locations shown in Figures B.2.6.2 through B.2.6.4. (a)Plan 13 'North'(see Figure B.2.6.2)(*) This plan utilizes a roadway from a railhead facility adjacent to the George Parks Highway at Hurricane to the Watana damsite following the north side of the Susitna River.A spur road,seven miles in length,would be constructed at a later date to service the Devil Canyon development.This route is mountainous and includes terrain at high elevations.In addition,extensive sidehill cutting in the region of Portage Creek will be necessary;however, construction of the road would not be as difficult as under plan 16. (b)Plan 16 'South'(see Figure B.2.6.3)(*) This route generally parallels the Susitna River,traveling west to east from a railhead at Gold Creek to the Devil 851104 B-2-71 Canyondamsite,and continues following a southerly loop to the Watana damsite.Twelve miles downstream of the Watana damsite a temporary low-level crossing of the Susit~a River will be used until completion of a permanent bridge.A connecting road from the George Parks Highway to Devil Canyon with a major high-level bridge across the Susitna River is necessary to provide full road access to either site.The topography from Devil Canyon to Watana is mountainous and the route involves the most difficult construction of the three plans,requiring a number of sidehill cuts and the construction of two major bridges.To provide initial access to the Watana damsite this route presents the most difficult construction problems of the three routes and has the highest potential for schedule delays and related cost increases. (c)Plan 18 'Denali-North '.(see-Figure B.2.6.4)(*) This route originates at a railhead in Cantwell,utilizing the existing Denali Highway to a point 21 miles east of the junction of the George Parks and Denali Highways.A new road will be constructed from this point due south to the Watana da1l'lsite.The majority of the new roa.d win traverse relatively flat terrain which will allow construction using side borrow techniques,resulting in a minimum of disturbance to areas away from the alignment..This is the most easily constructed"route for initial"access to the Watana site.Access to the.Devil Canyon development will consist primarily of a railroad extension from the existing AlasKaRaiTroadatGoTdCree1f--to-ci-raiTlieadfaci-n ty ---- adjacent to the Devil Canyon camp area.To provide access to the Wat~na damsite and the existing highway system,a connecting road will be constructed from the Devil Canyon railhead following a northerly loop to the Watana damsite. Access to the north side of the Susitna River will be attained via_a high-level suspension bridge constructed approximately one mile downstream of the Devil Canyon Dam. ----In-genera-l-,---the--al-ignment-c:t;'oss.e s---ter:t;'ain--with-gent 1e -to ____...._.__~~~mo_d_er_a_t_e_sLo_p_es __w:hic1Lwill_.aliow.....r.oadbed_cons.truction without deep cuts. 2.6.6 -Comparison of the Selected Alternative Plans (*) To determine which access plan best accommodates both project- related goals and the concerns of the resource agencies,Native organizations,andaffectedocommunities,thethreeselected C1lt~I'Ilative ••pl.9.nsW~I'~s1Jb j ec:teel.f:o ~lll1J:lf:i-cl:i,$c:ip:litl~lrY­ evaluation and comparison.The key issues addressed in this evaluation and comparison were: ,] !j j -----~85-a-04-----------B-2-72 (a)Costs (*) For the development of access to the Watana site,the Denali-North Plan has the least cost and the lowest probability of increased costs resulting from unforeseen conditions.The North Plan is ranked second.The North Plan has the lowest overall cost while the Denali-North has the highest.However,a large portion of the cost of the Denali-North Plan would be incurred more than a decade in the future.When converting costs to equivalent present value,the overall costs of the Denali-North and the South Plans are approximately equal.The costs of the three alternative plans can be summarized as follows: Estimated Total Cost ($x 10 6 ) Plan Watan~Devil Canyon Total Discounted Total North (13)241 South (16)312 Denali-North (18)224 127 104 213 368 416 437 287 335 326 The costs are in terms of 1982 dollars and include all costs associated with design,construction,maintenance and- logistics. (b)Schedule (*) The schedule for providing initial access to the Watana site was given prime cons~deration since the cost ramifications of a schedule delay are highly significant.The elimination of pre-license construction of a pioneer access road has resulted in the compression of on-site construction activities during the initial construction seasons.With the present overall project scheduling,should diversion not be completed prior to spring runoff in the fourth construction season,dam foundation preparation work will be delayed one year and hence cause a delay to the overall project of one year.It has been estimated that the resultant increase in cost would likely be in the range of 100-200 million dollars.The access route that assures the quickest completion and hence the earliest delivery of equipment and material to the site has a distinct advantage. The forecasted construction period,including mobilization, for the three plans is: 851104 o Denali-North o North o South B-2-73 6 months 9 months 12 months It is evident that,with the Denali-North Plan,site activities can be supported at an earlier date than by either of the other routes.Consequently the Denali-North Plan offers the highest probability of meeting schedule and hence the least risk of project delay and increase in cost. The schedule for access in relation to diversion is shown for the three plans in Figure B.2.6.5. (c)Environmental Issues (*) Outlined below are the key environmental impacts which have been identified for the three routes.The specific mitigation measures necessary to avoid,minimize or compensate for these impacts are discussed in Exhibit E. (i)Wildlife and Habitat (*) The three selected alternative ~ccess routes are made up of five distinct wildlife and habitat segments: o Hurricane to Devil Canyon (Segment 1):This segment is composed almost entirely of productive mixed forest,riparian,and wetlands habitats important to moose, furbearers,and birds.It includes three areas where slopes of over 30·percent will require side hill cuts,all above wetland zones vulnerable to erosion-related tDpacts. ,Ir . ~.~_.-~-~-- o Gold Creek to Devil Canyon (Segment 2):This segment is composed of mixed forest and wetland habitats,but includes less wetland habitat and fewer wetland habitat types than the Hurricane to Devil Canyon segment.Although this segment contains habitat suitable for moose,black bears,furbearers and birds,it has the least potential for adverse impacts to wildlife of the·~five ·"seglrien"tsconsIdered:~.-.~ o Devil Canyon to Watana (North Side)(Segment 3): The following comments apply to both the Denali-North and North routes.This segment traverses a varied mixture of forest ,shrub, and tundra habitat types,generally of meditnn....to-~lowproductivity~as ·wildlife habitat. However,it crosses the Devil and Tsusena Creek drainages,which are 1mporfarit moose arid brown bear habitat. j ] .J 1 851104 B-2-74 1 !, i I o Devil Canyon to Watana (South Side)(Segment 4): This segment is highly varied with respect to habitat types,containing complex mixtures of forest,shrub,tundra,wetlands,and riparian vegetation.The western portion is mostly tundra and shrub,with forest and wetlands occurring along the eastern portion in the vicinity of Prairie Creek,Stephan Lake,and Tsusena Creek.Prairie Creek supports a very high seasonal concentration of brown bears and the lower Tsusena Creek area supports concentrations of moose and black bears.The Stephan Lake area also supports relatively high densities of moose and bears.In addition to habitat·loss or alteration and increased hunting,significant human-bear conflicts would probably result from access development in this segment. o Denali Highway to Watana (Segment 5):This segment is primarily composed of shrub and tundra vegetation types,with little productive forest habitat present.Although habitat diversity is relatively low along this segment, the southern portion along Deadman Creek contains important brown bear habitat and browse for moose.This segment crosses a peripheral portion of the range of the Nelchina caribou herd which is occupied by a subherd that uses the area year-round including during calving.Althou~it is not possible to predict with any certainty how the physical presence of the road itself or traffic will affect caribou movements,population size,or productivity,it is likely that a variety of site-specific mitigation measures will be necessary to protect the herd. The three access plans are made up of the following combinations of wildlife habitat segments: North South Denali-North Segmen ts 1 and 3 Segments 1,2,and 4 Segments 2,3,and 5 851104 The North route has the least potential for creating adverse impacts to wildlife and habitat,for it traverses or approaches the fewest areas of productive habitat and zones of B-2-75 species concentration or movement.The wildlife impacts of the South Plan can be expected to be greater than those of the North Plan due to the proximity of the route to Prairie Creek,Stephan Lake and the Fog Lakes, which currently support high densities of moose and black and brown bears.In particular, Prairie Creek seasonally supports what may be the highest concentration of brown bears in the Susitna basin.Although the Denali-North Plan has the potential for disturbances of caribou, brown bear and black bear concentrations and movement zones,it is considered that the potential for adverse impacts with the South Plan is greater. (ii)Fi.sheries (*) All three alternative routes would have direct and indirect impacts on the fisheries.Direct impacts include the effects on water quality and aquatic habJtat wl1~I:'eas jncreased angling pressure is an indirect impact.A qualitative comparison of the fishery impacts related to the alternative plans was undertaken.The parameters used to assess impacts along each route included:the numbe.r,of streams crossed,the number and length of lateral transits (i.e.,where the roadway parallels the streams and runoff from the roadway can run directly into the-stream);~thenumberorwa'terstiecfsaffected;and the presence of resident and anadromous fish. The three access plan alternatives incorporate combinations of seven distinct fishery segments: o Hurricane to Devil Canyon (Segment 1):Seven stream crossings will be required along this "route,including·rndianRiverwhich-is an··· .-~-..~.-~.~~-----~_-.--~----~-impor-t·an.r.--sa-lmon-s.pa~·m-i-ng--r-i~v:e·r-.-···~Bot-h-·t-he·- Chulitna River watershed and the Susitna River watershed are affected by this route.The increased access to Indian River will be an important indirect impact to the segment. Approximately 1.8 miles of cuts into banks greaf:En:tl1.ag3Q.degrees occur along this route requiring erosion control measures to preserve .thewater..quality--al1d aquatic habitat. o Gold Creek to Devil Canyon (Segment 2):This segment would cross six streams and is expected 851104 B-2~76 J to have minimal direct and indirect impacts. Anadromous fish spawning is limited to the lower reaches of Jack Long Creek,the tributary to Slough 21 at road corridor mile 43.3, Waterfall Creek,and Gold Creek (ADF&G 1984a). Approximately 2.5 miles of cuts into banks greater than 30 degrees occur in this section. In the Denali North Plan this segment would be railroad,whereas in the South Plan it would be road. o Devil Canyon toWatana (North Side,North Plan)(Segment 3):This segment crosses twenty streams and laterally transits four rivers for a total distance of approximately 12 miles. Seven miles of this lateral transit parallels Portage Creek,which is an important salmon spawning area. o Devil Canyon to Watana (North .Sider,- Denali-North Plan)(Segment 4):The difference between this segment and segment 3 described above is that it avoids Portage Creek by traversing through a pass.4.miles to the east. The number of streams crossed is consequently reduced to twelve,and the number of lateral transits is reduced to two'with a total distance of 4 miles. o Devil Canyon to Watana (South Side)(Segment 5): The portion between the Susitna .River crossing and Devil Canyon requires nine steam crossings, but it is unlikely that these contain significant fish populations.The portion of this segment from Watana to the Susitna River is not expected to have any major direct impacts;however,increased angling pressure in the vicinity of Stephan Lake may result due to the proximity of the access road.The segment crosses both the Susitna and the Talkeetna watershed.Seven miles of cuts into banks of greater than 30 degrees occur in this segment. o Denali Highway to Watana (Segment 6):The segment from the Denali Highway to the Watana damsite has twenty-two stream crossings and passes from the Nenana into the Susitna watershed.Much of the route crosses or is in proximity to seasonal grayling habitat and runs parallel to Deadman Creek for nearly 10 miles. If recruitment and growth rates are low along this segment,it is unlikely that resident populations could sustain heavy fishing pressure.Hence,this segment has a high potential for impacting the local grayling population. o Denali Highway (Segment 7):The Denali Highway from Cantwell to the Watana access turnoff will require upgrading.The upgrading will involve only minor realignment and negligible alteration to present stream crossings.The segment crosses eleven streams and laterally transits two rivers for a total distance of 5 miles.There is no anadromous fish spawning in this segment and little direct or indirect impact is ,expected. The three alternative access routes comprise the following fisheries segments: J -) -J~·~l o North o South o Denali-North Segments I and 3 Segments 1,2,and 5 Segments 2,4,6 and 7 The Denali-North Plan is likely to have both direct and indirect impacts on grayling fisheries given the number of stream crossings,lateral transits,and ......water:sheds affected ...Anadromousg.!!herj.,es.._~mpac t~.. will be minimal and will only be of concern along the railroad spur between Gold Creek and Devil Canyon. The South Plan is likely to create significant direct and indirect impacts at Indian River,which is an important salmon spawning river.Anadromous fisheries impacts may also occur in the Gold Creek to Devil Canyon segment,as for the Denali-North Plan. -------Io"-additi-orr,-indirect-impacts-may'occur in .the .._--._-_..._~.."--·_--·-S-t;-eph-an-r.ake--a·rea-.-·_.._·-_.... ] 851104 The North Plan,like the South Plan,may impact salmon spawning activity in Indian River.Direct impacts may occur along Portage Creek due to temporary water quality changes through increased erosion;indirect impacts,such as increased angling pressure,could also occur. With any of the selected plans,direct and indirect effects can be minimized through proper engineering design and prudent management.Criteria for the B-2-78 .1 {J development of borrow areas and the design of bridges and culverts for the proposed access plan t0gether with mitigation recommendations are discussed in Exhibit E. (d)Cultural Resources (**) A preliminary evaluation of the relative cultural resources sensitivity of the three access plans was made.This consisted of a review of relevant literature and information on previously recorded sites in the general area,and a flyover of the three routes by archeologists.Random ground checks were made during the course of the latter.The Denali-North plan,because of its greater overall length and its location parallel to Deadman Creek,is believed to have the greatest potential for impacting archeological sites. the South Plan,although it traverses less archeologically sensitive terrain than the North Plan,by virtue of its greater length,is believed to have a greater potential for impacting acheological resources than the latter plan.The ranking from the least to the highest with regard to cultural resources impacts is therefore South,North,and Denali-North. Impacts on archeological sites can to be adequately mitigated by avoidance or data recovery;consequently,this issue is not critical to the selection process.It should be noted,however,the less forested nature of the terrain along the Denali-North and portions of the North Plan would allow for more efficient identification of cultural· resources in these areas than along the more forested Sout~ Route during pre-construction surveys. (e)Socioeconomics (0) Socioeconomic impacts on the Mat-Su Borough as a whole would be similar in magnitude for all three plans.However, each of the three plans affects future socioeconomic conditions in differing degrees in certain areas and communities.The important differences affecting specific communities are outlined below. (i)Cantwell (0) The Denali-North Plan would create substantial increases in population,local employment,business activity,housing and traffic.These impacts result because a railhead facility would be located at Cantwell,and because Cantwell would be the nearest community to the Watana damsite.Both the North and 851104 B-2-79 South Plans would impact Cantwell to a far lesser extent •. (ii)Hurricane (0) The North Plan would substantially affect the Hurricane area since currently there is little population,employment,business activity or housing. Socioeconomic impacts for Hurricane would be less under the South Plan and considerably less under the Denali-North Plan. (iii)Trapper Creek and Talkeetn~(0) Trapper C~eek would experience slightly greater changes in economic indicators with the North Plan than under the South or Denali-North Plans.The South Plan would impact the Talkeetna area slightly more than the other two plans. (iv)Gold Creek (*) With the South Plan,a railhead facility would be developed at Gold Creek,creating significant socioeconomic impacts in this area.The Denali-North Plan includes construction of a railhead facility at the Devil Canyon site,which would create impacts at Gold Creek,but not to the same extent as with the ····_--Sou~hP·lan·.·--·M·inimal--impacts.would-resul ~in-Gold· Creek under the North Plan. (f)Preferences of Native Organizations (*) The Cook Inlet Region Inc.(CIRI)and mosto£il:s associated village corporations all prefer the South Plan since it provides full road access to their lands south of .........__.th~..§..t1~tl:!l.C1J~.iY~!:.!.....M:r.nf4.,..J:!lC ....l!!l(L!;h~_<;:;1!!lJ:.w~11YiJJ~g~ Corporation support the Denali-North Plan.None of the Native organizations supports the North Plan •._....-....... (g)Relationship to Current Land Stewardships,Uses and Plans (**) J .J"~l 1 J 851104 As described in Exhibit E,Chapter 9,much of the land required for project devE!lopment ha.sbeen or may be conveyed to Na.tive organizations.·.The remaining lands are generally undersl:al:e'and federal Conl:roLTJieSoul:h'Plan traverses more Native-selected lands than either of the other two routes,and Native organizations have expressed an B-2-80 ,1 'j I J 851104 IJ interest in potentially developing their lands for mining, recreation,forestry or residential use. The other land management plans that have a large bearing on access development are the Bureau of Land Management's (BLM) recent decision to open the Denali Planning Block to mineral exploration,and the Susitna Area Plan.In general,none of the plans would be in major conflict with any present federal,borough or Native management plans. 2.6.7 -Summary (0) In reaching the decision as to which of the three alternative access plans would be recommended,it was necessary to evaluate the highly complex interplay that exists between the many issues involved.Analysis of the key issues indicates that no one plan satisfied all the selection criteria nor accommodated all the concerns of the resource agencies,Native organizations and the public.Therefore,it was necessary to make a rational assessment of trade-offs between the sometimes conflicting environmental concerns of impacts on fisheries,wildlife, socioeconomics,land use and recreational opportunities on the one hand,with project cost,schedule,construction risk and management needs on the other.With all these factors in mind, it should be emphasized that the primary purpose of access is to provide and maintain an uninterrupted flow of materials and personnel to the damsite throughout the life of the project. Should this funda~ental objective not be achieved,significant schedule and budget overruns will occur. 2.6.8 -Final Selection of Plan (0) (a)Elimination of 'South Plan'(0) The South route,Plan 16,was eliminated primarily because of the construction difficulties associated with building a major low-level crossing 12 miles downstream of the Watana damsite.This crossing would consist of a floating or fixed temporary bridge which would need to be removed prior to spring breakup during the first ~hree years of the project (the time estimated for completion of the permanent bridge). This would result in a serious interruption in the flow of materials to the site.Another drawback is that floating bridges require continual maintenance and are generally subject to more weight and dimensional limitations than permanent structures. A further limitation of this route is that for the first three years of the project all construction work must be supported solely from the railhead facility at Gold Creek. B-2-81 This problem arises because it will take an estimated three years to complete construction of the connecting road across the Susitna River at Devil Canyon to Hurricane on the George Parks Highway.Limited access such as this does not provide the flexibility needed by the project management to meet contingencies and control costs and schedule. Delays in the supply of materials to the damsite,caused by either an interruption of service of the railway system or the Susitna River not being passable during spring breakup, could result in significant cost impacts.These factors, together with the"realization that the South Plan offers no specific advantages over the other two plans in any of the areas of environmental "or social concern,led to the South Plan being eliminated from further consideration. (b)Schedule Constraints (*) The choice of an access plan thus narrowed down to the North and Denali-North plans.Of the many"issues addressed during the evaluation process,the issue of "schedule"and "schedule risk"was determined to be the most important in the final selection of the recommended plan. Schedule plays an extremely important role in the evaluation process because of the special set of conditions that exist in a sub-arctic environment.Building roads in these regions involves the consideration of many factors not found in_other~_en"Vironment:s.~--Specificacl.ly~,~the--ch-iecf~conce~n -·is- one of weather,and the consequent short duratio~of the construction season.The roads for both the North and Denali-North Plans will,for the most part,be constructed at elevations in excess of 3,000 feet.At these elevations the likely time available for uninterrupted construe tion in a typical year is 5 months,and at most 6 months. The forecasted construction period including mobilization is--....__.-~,_._-..----_._-----,----,-_._-----_._--.,---.-------~.·-6---monEh-s-~~--for-·---:·-Eli-e~-De'n'a-i-'i=··Nor-th p'I-aii~an'd-'-'-'~r-'month-s---'fo--r------t-il"e-~"---- ----------"""NOI'"Elf-;;--Atfi r s cgTancea-------'---dTHerence inscneQ1.iTeof3·monEns does not seem great;however,when considering that only 6 months of the year are available for construction,the addi- tional 3 months become highly significant. If diversion is not achieved prior to spring runoff in the - -·-fourth year -ofconstruction,-dam-foundation--preparation work will be delayed one year,and hgnce ca~sg a gelay to the overall project of one year ~" J "J j 851104 B-2-82 ] (c)Cost Impacts (0) The increase in costs resulting from a one-year delay have been estimated to be in the range of 100-200 million dollars.This increase includes the financial cost of investment by the date of scheduled river diversion,the financial costs of rescheduling work for a one-year delay, and replacement power costs. (d)Summary (*) The Denali-North Plan has the highest probability of meeting schedule and least risk of increase in project cost for two reasons.First,it has the shortest construction schedule (six month~).Second,a passable route could be constructed even under winter conditions due to the relatively flat terrain along its length.In contrast the North route is mountainous and involves extensive sidehill cutting,especially in the Portage Creek Area.Winter construction along sections such as this would present major problems and increase the probability of schedule delay. 1 I.! (e) (f) Plan Recommendation (0) It is recommended that the Denali-North route be selected so as to ensure completion of initial access to the Watana damsite as soon as possible after receipt of a project license,for it is considered that the risk of significant cost overruns is too high with any other route. Environmental Concerns -Recommended Plan (*) The main disadvantage of the Denali-North route is that it has a higher potential for adverse environmental impacts than the North route alternative.These impacts have been identified and,following close consultation with environ- mental subconsultants,many of the impacted areas have been avoided both by careful alignment of the road and the development of design criteria which do not detract from the semi-wilderness character of the area.Some environmental impacts and conflicts are unavoidable,however,and where these impacts occur,specific mitigation measures have been developed to reduce them to a minimum.These measures are outlined in detail within the relevant sections of Exhibit E. 2.7 -Selection of Transmission Facilities (0) The objective of this section is to describe the studies performed to select a power delivery system from the Susitna River basin 851104 B-2-83 generating plants to the major load centers in Anchorage and Fairbanks. This system will comprise transmission lines,substations,a dispatch center,and means of communications. The major topics of the transmission studies include: o Electric system studies, o Transmission corridor selection, o Transmission route selection, o Transmission towers,hardware and conductors, o Substations,and o Dispatch center and communications. 2.7.1 Electric System Studies (0) Transmission planning criteria were deve10ped~to ensure the design of a reliable and economic electrical power system,with components rated to allow a smooth transition through early project stages to the ultimate developed potential. Strict application of optimmn,long-term criteria woulcI-.orequire the installation of equipment with ratings larger than necessary, at excessive cost.In the interest of economy and long-term system performance,these criteria were temporarily relaxed during the early development stages of the project.Although allowing for satisfactory operation during early system development,final system parameters must be based on the ultimate Susitna potential. The criteria are intended to ensure maintenance of rated power flow to AnchClrage .ailc!Fairbanks during the outage .of any single line or transformer element.The essential features of the criteria are: o Total power output of Susitna to be delivered to one or two stations at Anchorage and one at Fairbanks; o Overvoltages during line energizing not to exceed specified limits; o System vol tages to be within .established limits during normal operation; o Power delivered to the loads to be maintaLned and system vol t:ages tabe kept:withines tablished limits for system operation under emergency conditions; ·1 f 1 .) ',1 I J. 851104 B-2-84 o Transient stability during a 3-phase line fault cleared by breaker action with no reclosing;and o Where performance limits are exceeded,the most cost-effective corrective measures are to be taken. (a)Existing System Data (*) Data compiled in a report by Acres (1982c)have been used J for preliminary transmission system analysis.Other system ,I.data were obtained in the form of single line diagrams from the various utilities. (b)Power Transfer Requirements (**) The Susitna transmission system mtistbe designed to ensure the reliable transmission of power and energy generated by the Susitna Hydroelectric Project to the load centers in the Rai1belt area.The power transfer requirements of this transmission system are determined b~the following factors: o System demand at the various load centers; o Generating capabilities~at the Susitna project;and o Other generation available in the Rai1belt area system • The electric load demand in the Railbel~area is located in two main centers:Anchorage and Fairbanks.The largest load center is Anchorage,with most of its load concentrated in the Anchorage urban area.The second largest load center is'Fairbanks.Two small load centers (Willow and Healy)are located along the Susitna transmission route.The Glennallen-Valdez load center is not planned to be inter- connected with the Railbelt nor to be served by the Susitna project.It is therefore excluded from disscusion in this License Application. A survey of past and present load demand levels as well as forecasts of future trends indicates these approximate load levels at the two load centers: 851104 Load Area Anchorage -Cook Inlet Fairbanks Tanana Valley B-2-85 Percent of Total Railbelt Load 83 17 Accordingly,it has been assumed for study purposes that about 83 percent of the generation at Susitna will'be trans- mitted to the Anchorage area and 17 percent to Fairbanks. The potential of the Susitna Hydroelectric Project is expected to be developed in three stages as the system load grows over the next three decades.The transmission system must be designed to serve the ultimate Susitna development, but staged to provide reliable transmission at every intermediate stage.Present plans call for three stages of Susitna capacity additions:360 MW installed at Watana in 1999,600 MW at Devil Canyon in 2005,and an additional 660 MW at Watana in 2012.The 660 MW addition at Watana Stage III reflects two additional units at 170 MW each (340 MW), plus an incremental increase in the four existing units of 320 MW due to the increased~ead from the raised dam. Development o~other generation resources could alter the geographic load and generation sharing in the Railbelt, depending on the location of this development.However, current studies indicate that no other very large projects are likely to be developed until the full potential of the Susitna project is utilized.The proposed transmission configuration and design should,therefore,be able to satisfy the bulk transmission requirements for at least the next three decades.The next major generation development after Susitna will then require a transmission system deter- mined by its own magnitude and location. The resulting power transfer requirements for the Susitna transmission system are indicat~d in Table B.2.7.1. (c)Transmission Alternatives (*) J .) Because of the geographic location of the various centers, transmission from Susitna to Anchorage and Fairbanks will result in a radial!)ystem configuration.This allows,-sIgnTfIcant-free-dom io-the--c.hoTce -of-transmIssion _.vortages~ _._--~._._-_._..._--_.__._------._._-~----_.-conduc tors,and other parameters for the two Htle--secEions, with only limited dependence between them.Transmission alternatives were developed for each of the two system areas,including voltage levels,number of circuits required,and other parameters,to satisfy the necessary transmission requirements of each area.This work is described by Acres (l982c)in their electrical system studies closeout report. 851104 To maintain a consistency with standard ANSI voltages used in other parts of the United States,the following voltages were considered for Susitna transmission: B-2-86 I' .} I J , I I ! o Watana and Devil Canyon to Gold Creek and on to Anchorage:500 kV or 345 kV o Devil Canyon to Fairbanks:345 kV or 230 kV (i)Susitna to Anchorage (**) I,I (ii ) Transmission at either of two different voltage levels (345 kV or 500 kV)could reasonably provide the necessary power transfer capability over the distance of approximately 132 miles between Gold Creek and Anchorage.'This transfer capability is higher than the projected load in year 2020.At 345 kV,either three circuits uncompensated or two cir- cuits with series compensation are requir'ed to provide the necessary reliability for the single contingency outage criterion.At lower voltages,an excessive number of parallel circuits are required, while above 500 kV,two circuits are still needed to provide service in the event of a line outage. Susitna to Fairbanks (0) Applying the same reasoning used in choosing the transmission alternatives to Anchorage,two cir- cuits of either 230 kV or 345 kV were chosen for the section from Devil Canyon to Fairbanks.The 23D kV alternative requires series compensation to satisfy the planning criteria in case of a line outage. 851104 (iii)Total System Alternatives (*) The transmission system alternatives mentioned above were combined into five realistic total system alternatives.Three of the five alternatives have different voltages for the two sections.The principal parameters of the five transmission system alternatives analyzed in detail are as follows: B-2-87 Susitnato Anchorage Susitna to Fairbanks Number of Number of Alternative Circuits Voltage Circuits Voltage .~(kV)(kV) 1 2 345 2 345 J233452345 3 2 345 2 230 4 3 345 2 230 -}5 2 500 2 230 Electric system analyses,including simulations of line energizing,load flows of normal and emergency operating conditions,and transient stability per- formance,were carried out to determine the technical feasibility of the various alternatives.An economic comparison of transmission system life cycle costs was carried out to evaluate the relative economic merits of each alternative.All five transmission alternatives were found to have acceptable performance characteristics.The'most significant difference was that single-voltage systems (345 kV, Alternatives 1 and 2)and systems without series compensation (Alternative 2)offered reduced complexity of design and operation and therefore were likely to be marginally more reliable.The present worth life cycle costs of Alternatives 1 through 4 were all within 1 percent of each other.Only the -------._-----~--cost-~o-£-the~50 O/-2-30k-V-c scheme"(-A-Hoercna-tive-5 )was 14 percent above the others.A summary of the life cycle cost analyses for the various alternatives is shown in Table B.2.7.2. A technical and economic comparison was also carried out to determine possible advantages and disadvantages of HVDC transmission,as compared to an ..._._...._5i.·c:·.J~y~~~IIl;J()J;J:EIi!I!~J.IlJ~~_t!!g§l!~_~t_ll,,!_..];>C>.w~_r:.~()_____ Anchorage and Fairbanks.HVDC transmission was found 'tObetechnically andoperationally -more complex -a-s- well as having higher life cycle costs. (d)Configuration at Generation and Load Centers (0) Interconnections between generation and load cent'ers and the transmission system were developed after reviewing the existing system configurations at both Anchorage and roariks as well as the possioiliHes arid currerit develop- ment plans in the Susitna,Anchorage,Fairbanks,Willow,and Healy areas. .J .) 851104 B-2-88 (i)Susitna Configuration (**) Preliminary development plans indicated that the first project to be constructed (Stage 1)would be Watana with an initial installed capacity of 360 MW. The next project considered in this study (Stage II), would be Devil Canyon,with an installed capacity of 600 MW.The last project (Stage 3)will be the raising of the Watana Dam and addition of two more generating units to increase the total generating capacity at Watana to 1,020 MW. (ii ) (iii) Switching at Willow (*) Transmission from Susitna to Anchorage is facilitated by the introduction of ~n intermediate ~witching station.This has the effect of reducing line energizing overvoltages and reducing the impact of line outages on system stability.Willow is a suitable location for this intermediate switching station;in addition,it would make it possible to supply local load when this is justified by development in the area.This local load is expected to be less than 16 percent of the total Railbelt area system load,but the availability of an EHV line tap would definitely facilitate future power supply. Switching at Healy (0) A switching station at Healy was considered early in the analysis but was found to be unnecessary to satisfy the planning criteria.The predicted load at Healy is small enough to be supplied by local generation and the existing 138-kV transmission from Fairbanks. 851104 (iv)Anchorage Configuration (**) Analysis of system configuration,distribution of loads,and development in the Anchorage area led to the conclusion that a transformer station near Palmer would be of little benefit.Most of the major loads are concentrated in and around the urban Anchorage area,at the mouth of Knik Arm.To reduce the length of subtransmission feeders,the transformer stations should be located as close to Anchorage as possible. The routing of transmission into Anchorage was chosen from the following three possible alternatives: B-2-89 -Submarine Cable Crossing From Point MacKenzie to Point Woronzof This would require transmission through a very heavily developed area.It would also expose the cables to damage by ships'anchors,which has been the e~perience with existing cables,resulting in questionable transmission reliability. -Overland Route North of Knik Arm via Palmer This may be most economical in terms of capital cost,in spite of the long distance involved. However,overhead transmission through this developed area may have,.-signi ficant environmental consequences.A~longer overland route around the developed area may be technically unacceptable because of the mountainous terrain. -Submarine Cable Crossing of Knik Arm,In the Area of Lake Lorraine and Six Mile Creek This option,approximately parallel to the new 230 kV cable -under construction for Chugach Electric Association (CEA),includes some 3 to 4 miles of submarine cable and involves a high capital cost. Since the area is upstream from the shipping lanes to the port of Anchorage,it will result in a t"elia·blet:r;ansmission link,and--one.that does.not have to cross environmentally sensitive conservation areas. (v)Fairbanks Configuration (0) Susitna power for the Fairbanks area is recommended to be delivered to a single EHV/138 kV transformer Sl~<!it~.Ql:l._lo..5=at~j_at Ester.No alternatives were given de ta i led cons idera'-tToti-~---------···---... ..........._-_._--_._-_.._----._~.__...-.... 2.7.2 Corridor Selection (0) (a)Methodology (0) Development of the proposed Susitna Project will require a transmission system to..deliver electric power to the Rail bel t.area.The building of .t:h~Atlchorage to Fairbanks trit:erEie sysfemwill result ,iii a defined cdrridor and route for the Susitna transmission lines between Willow and Healy. Therefore,three areas require study for corridor selection: the northern area to connect Healy with Fairbanks,the ,'J 'J 1J I 851104 B-2-90 ) central area to connect the Watana and,Devil Canyon damsites with the Intertie,and the southern area to connect Willow wi th Anchorage. Using the selection criteria discussed below,corridors three to five miles wide were selected in each of the three study areas.These corridors were then evaluated to determine which ones meet the more specific screening criteria.This screening process resulted in one corridor in each area being designated as the recommended corridor for the transmission line. (b)Selection Criteria (0) Since the corridors studied range in width from three to five miles,the base criteria had to be applied in broad terms.The study also indicated that the criteria listed for technical purposes could reappear in the economic or environmental classification.The technical criteria were defined as requirements for the normal and safe performance of the transmission system and its reliability. The selection criteria were in three categories:technical, economic and environmental.The criteria are listed in Table B.2.7.3. (c)Identification of Corridors (0) As discussed previously,the Susitna transmission line corridors studied are located in three geographical areas, namely: o The southern study area between Willow and Anchorage; o The central study area between Watana,Devil Canyon, and the Intertie,and o The northern study area between Healy and Fairbanks. (d)Description of Corridors (0) Figures B.2.7.1 through B.2.7.3 portray the corridors evaluated in the southern,central,and northern study areas,respectively.For purposes of simplification,only the centerline of the three-to-five-mile wide corridors are shown in the figures. In each of the three figures,each corridor under consideration has been identified by the use of letter symbols.The various segment intersections and the various 851104 B-2-91 segments,where appropriate,have been designated.Thus, segments in each of the three study areas can be separately referenced.Furthe~ore,the segments are joined together to form corridors.For example,in the northern study area Corridor ABC is composed of Segments AB and BC. The alternative corridors selected for each study area are described in detail in the following paragraphs.In addition,Tables B.2.7~4,B.2.7.5 and B.2.7.6 contain detailed environmental data for each corridor segment. (i)Southern Study Area (0) -Corridor One -Willow to Anchorage via Palmer (0) Corridor ABC',consisting of Segments AB and BC', begins at the intersection with the Intertie in the vicinity of Willow.From here,the corridor travels in a southeasterly direction,crossing wetlands,Willow Creek,and Willow Creek Roa:d before turning slightly to the so.utheast following the drainage of Deception Creek.The topography in the vicinity of this segment of the corridor is relatively flat to gently rolling with standing water and tall-growing vegetation in the vicinity of the creek drainages. At a point northw.est of Bench Lake,the corridor turns in an eas!=~dyg:ixection,.cx.o.s.s.ingthe '_·_-·southern f(;othills of the Talkeetna Mountains.The topography here is gently to moderately rolling with shrub-to trees ized vege tationocc urring throughout.As the corridor approaches the crossing of the Little Susitna River,it turns and heads southeast again,crossing the Little Susitna River and Wasilla Fishhook Road. Pas s ing'nea:rWolf·LakE'f"ana·Gooain~rLake·;tfie'".. .......~~__~._.._._-corti-dor-then"cTo's'ses-a-s'e'c-oucbrry-road-;--'some -. agricultural lands,State Route 3,and the Glenn Highway,before intersecting existing transmission lines south of Palmer.In the vicinity of the Little Susitna River,the topography is gently rolling.As the corridor travels toward Palmer, the land flattens,more lakes are present,and some agricultural development .is Occutri'!1g.After crossing the Glenn Highway,-the'corridor passes through a residential area before crossing the broad floodplain of the Matanuska River. ·1J 'J 851104 B-2-92 j ,} 851104 Just west of Bodenburg Butte,the corridor turns due south through more agricultural land before crossing the Knik River and eventually connecting with the Eklutna Power Station.All of the land south of Palmer is very flat with some agricultural development.Just south of Palmer,the proposed corridor intersects existing transmission facilities and parallels or replaces them from a point just south of Palmer,across the river and into the vicinity of the Eklutna Power House.From here into Anchorage,the corridor as proposed would parallel existing facilities,crossing near or through the communities of Eklutna,Peters Creek, Birchwood,and Eagle River by using one of the two existing transmission linec·rights-of-way in this area.The land here is flat to gently rolling with a great deal of residential development.This corridor segment is the most easterly of the three considered in the southern study area and avoids an underwater crossing of Knik Arm. Corridor Two -Willow to Point MacKenzie via Red Shirt Lake (0) Corridor ADFC,consisting of Segments ADF and FC, commences again at the point of intersection with the Intertie in the vicinity of Willow but immediately turns to the southwest,first crossing the railroad,then the Parks Highway,then Willow Creek just west of Willow.The land in the vicinity of this part of the segment is very flat, with wetlands dominating the terrain. Southwest of Florence Lake,the proposed corridor turns,crosses Rolly Creek,and heads nearly due south,passing through extensive wetlands west and south of Red Shirt Lake.The corridor in this area parallels existing tractor trails crossing very fl~t lands with significant amounts of tall-growing vegetation in the better drained locations. Northwest of Yohn Lake,the corridor segment turns to the southeast,passing Yohn Lake and My Lake before crossing the Little Susitna River.Just south of My Lake,the corridor turns in a generally southerly direction,passing Middle Lake,and east of Horseshoe Lake before finally intersecting the existing Beluga 230-kV transmission line at a spot just north of MacKenzie Point.From here,the corridor parallels MacKenzie Point's existing B-2-93 851104 transmission facilities .before crossing u~der Knik Ann to emerge on the easterly shore of Knik Arm in the vicini ty of Anchorage.'The land in the vicinity of this segment is extremely flat and very wet,supporting dense stands of tallgrowing vegetation on any of the higher or better drained areas. Corridor Three -Willow to Point MacKenzie via Lynx Lake (0) Corridor AEFC is very similar to and is a derivation of Corridor ADFC;it consists of Segments AEF and FC.This corridor also extends to the southwest.·of Willow.West of the Parks Highway,however,just north of Willow Lake,this" corridor turns and travels southwest of Willow and east of Long Lake,passing between Honeybee Lake and Crystal Lake.The corridor then turns southeastward to pass through wetlands east of Lynx Lake and Butterfly Lake before crossing the Little Susitna R.Iver.The land is well developed iri this area.It is very flat and,while it is wet,also supports dense stands of tall-growing vegetation on the better drained sites.Corridor Three rej~ins Corridor Two at a point south of My Lake. (ii)Central!tudyArea (0) The central study area encompasses a broad area in the vicinity of thedamsites.From Watana,the study area extends to the north as far as the Denali Highway and to the south as far as Stephan Lake. From this point westward,the study area encompasses the foothills of the Alaska Range and,to the south, the foothills of the Talkeetna Mountains.Included -------···-in-·this--study--area--a·re--lands--undet"-cons-iderat-ion-by.... t-he-Int-e·J:'.t-ie-P.r-o~ect-in:v:es.t.i.ga.to.r.s_.---'!he_aLter_na_ti:v:.e .. corridors would connect both Devil Canyon and Watana Dams with the Intertie at one of four locations, which are identified in Figure B.2.7.2.. As for the southern study area,individual corridor $egments a".t'e listed in the text.This is to aid the reader both in determining corridor locations in the figure-sand itl 'exatniningtheenvironmenta I invento-ry data listed for each segment in Tables B.2.7.4, B.2.7.5 and B.2.7.6. B-2-94 1. 1 1 .1 I Ij 851104 Corridor One -Watana to Intertie via South Shore, Susitna River (0) Corridor ABCD consists of three segments:AB,BC, and CD.This corridor originates at the Watana damsite and follows the southern boundary 6f the river at an elevation of approximately 2,000 feet from Watana to Devil Canyon.From Devil Canyon, the corridor continues along the southern shore of the Susitna River at an elevation of about 1,400 feet to the point at which it connects with the Intertie,assuming the Intertie follows the railroad corridor.The land surface in this area is relatively flat,though incised at a number of locations by tributaries to the Susitna River.The relatively flat hills are covered by discontinuous stands of dense,tall-growing vegetation. -Corridor Two -Watana to Intertie via Stephan Lake (0) ABECD,.the second potential corridor,is essentially a derivation of Corridor One and is formed by replacing Segments BC with BEe. Originating at Point B,Corridor Segment BEC leaves the river and generally parallels one of the proposed Watana Dam access road corridors.This corridor extends southwest from the river,passing near Stephan Lake to a point northwest of·Daneka Lake.Here the route turns back to the northwest and intersects Corridor One at the Devil Canyon damsite.The terrain in this area,again,is gently rolling hills with relatively flat benches. Vegetation cover ranges from sparse at the higher elevations to dense along the river bottom and along gentler slopes of the Susitna River and its tributaries. Corridor Three -Watana to Intertie v~a North Shore,Susitna River (0) Corridor Three (AJCF),located on the north side of the river,consists of Segments AJ and CF. Starting at the Watana damsite,the corridor crosses Tsusena Creek and heads westerly,following a small drainage tributary to the Susitna River. Once crossing Devil Creek,the corridor passes north and west of High Lake. B-2-95 The corridor stays below an elevation of 3,700 feet as it crosses north of the High Lake"area,east of Devil Creek,on its approach to Devil Canyon.From Devil Canyon,the corridor again extends to the west,crossing Portage Creek and intersecting the Intertie in the vicinity of Indian River.In the drainages,to elevations of about 2,000 feet,tree heights range to 60 feet.Between Devil Creek and Tsusena Creek,however,at the higher elevations, very little vegeta tion grows taller than 3 feet. Once west of Devil Creek,discontinuous areas of tall-growing vegetation exist. Corridor Four -Watana to Intertie via Devil Creek Pass/East Fork Chulitna River"(0) Another means of connecting the two dam schemes with the Intertie is to follow Corridor One from Watana to Devil Canyon and then exit the Devil Canyon project to the north (ABCJHI).This involves connec'ting Corridor Segments AB,BC,CJ, HJ,·andHI.··With this ·alternative,the corridor extends northeast at Devil Canyon past High Lake to Devil Creek drainage.From there,it moves northward to a point north of the south boundary of the Fairbanks Meridian.The corridor then follows the Portage Creek "drainage beyond its point of origin to a site within the Tsu~ena Creek drainage. ·Likewis e·,".it~fol·lows~the~T~usena.·Creek-d~ai na·ge··to a point near Jack River,at which point it parallels this drainage into Caribou Pass.From Caribou Pass,the corridor turns to the west, following the Middle Fork·Chulitna River until meeting the Intertie in the vicini ty of Summit Lake. While along much of this corridor the route follows".-.'.----..--."----.'---.-'---,.-.----·rl-ver'·'·-vaI"reys-;'the---·plan -a:I·s'o'--··'re-q ui res"'---cr o-fi sin g-hi-gIl ·----~-~--mountain passes inruggea-·terrailr;··Tl:1i-s···fs··_··_······ especially true in the crossing between Portage Creek and Tsusena Creek drainages,where elevations of over 4,600 feet are involved.Tall-growing vegetation is restricted to the lower elevations along the river drainages with little other than low-growing forbsand~shrubs present at higher elevci"!:iotls. j j 851104 B-2-96 1 851104 -Corridor Five -Watana to Intertie via .Stephan Lake and the East Fork Chulitna River (0) A variation of Corridor Four,Corridor Five (ABECJHI)replaces Segment BC with Corridor Segment BEC (of Corridor Two).This results in a corridor that extends from the Watana damsite southwesterly to the vicinity of Stephan Lake,and from Stephan Lake into the Devil Canyon damsite. From Devil Canyon to the Intertie,the corridor follows the Devil Creek,Portage Creek,and Middle Fork Chulitna drainages previously mentioned.As before,the corridor crosses rolling terrain throughout the length of the paralleled drainages, with some confined,higher elevation passes encountered between Portage Creek and Tsusena Creek. Corridor Six -Devil Canyon to the Intertie via Tsusena Creek/Chulitna River (0) Another option (CBARI)for connecting the dam projects to the Intertie involves connecting Devil Canyon and Watana along the south shore of the Susitna River via Corridor Segment CBA,then exitingWatana to the north on Segments AR and HI along Tsusena Creek to follow this drainage to Caribou Pass.The corridor then contains the previously-described route along the Jack River and Middle Fork Chulitna until connecting with the Intertie near Summit Lake.The terrain in this corridor proposal would be of moderate elevation with some confined,higher elevation passes between the drainages of Tsusena Creek and the Jack River. Corridor Seven -Devil Canyon to Intertie via Stephan Lake and Chulitna River (0) This alternative uses Corridor Six but replaces Segment BC with Segment BEC from Corridor Two. This route would thu$be designated CEBAHI. Terrain features are as described in Corridors Two and six. -Corridor Eight -Devil Canyon to Intertie via Deadman/Brushkana Creeks and Denali Highway (0) Yet another option to the previously-described corridors is the interconnection of Devil Canyon B-2-97 851104 with Watana via Corridor One (Segment CBA),with a segment then extending from Watana northeasterly along the Deadman Creek drainage (Segment AG).The segment proceeds north of Deadman Lake and Deadman Mountain,then turns to the west and intersects the Brushkana Creek drainage.It then follows Brushkana Creek north to a point east of the Kana Bench Mark.This segment of the corridor would parallel one of the proposed access roads.From there,the corridor turns west,generally parallel to the Denali Highway,to the point of interconnection with the Intertie in the vicinity of Cantwell.The ar~a encompasses rolling hills with modest elevation changes and some forest cover,especially at the lower elevations. Corridor Nine -Devil Canyon to Intertie via Stephan Lake and Denali Highway (0) Corridor Nine (CEBAG)is exactly the same as Corridor Eight with the exception of Corridor Segment .BEe,uti 1 ized·to replace Segment BC.Each combination of segments has been previously described. Corridor Ten -Devil Canyon to Intertie via North Shore,Susitna River,.and Denali Highway (0) ,. --····L;Ol:'-l"-],Cl(rt:'-Ten·connect.s~De·vilCanyon-Wa·tana·wi th the Intertie in the vicinity of Cantwell by means of Corridor SegmentsCJAG.Segment CJA is part of Corridor Three and,as such,has been previously described..Segment AG has also been described above as part of Corridor Eight.As noted earlier, the Corridor Ten terrain consists of mountainous stretches with accompanying gently-rolling to 1ll()<i_~l:"_a.J;.e ~y-=-roll i !!gjli U~~.!!c:1ga.1:.pJa.J!!~coy_~re d ~n ._...E.~~c:es.!i:~ll..~a 1.!=gl"()w:i:.I!~!.e:.~r:..~~~~on~..._....... -Corridor Eleven -Devil Canyon to the Intertie via.Tsusena Creek/ChuU tna River (0) Another northern route connecting Devil Canyon with Watana is that created by connecting Corridor SegmentCJA (part of Corridor Three)with Segment ......AHLof Corridor Six •.. B-2-98 J 1 .] I .( I. \ 851104 -Corridor Twelve -Devil Canyon-Watana to the Intertie via Devil Creek/Chulitna River (0) Another route under consideration is Corridor JA-CJHI.From north to south,this involves a corridor extending from the Intertie near Summit Lake,heading easterly along the Middle Fork Chulitna drainage into Caribou Pass.From here,it parallels the Jack River and connects with the Portage Creek-Devil Creek route,Segment HJ.At point J,located in the Devil Creek drainage east of High Lake,the corridor splits,with one segment extending westerly to Devil Canyon and the other extending east to the Watana damsite along previously-described Corridor Segments JC and JA, respectively.Terrain features of this route have been previously described. -Corridor Thirteen -Watana to Devil Canyon via South Shore,Devil Canyon to Intertie via North Shore,Susitna River (0) Corridor Segments AB,BC,and CF are combined to form this corridor.Descriptions of the terrain crossed by these segments appear in discussions of Corridor One (ABCD)and Corridor Three (AJCF). -Corridor Fourteen -Watana to Devil Canyon via North Shore,Devil Canyon to Intertie via South Shore,Susitna River (0) This corridor would connect the damsites in the directionally opposite order of the previous corridor,and include Corridor Segment AJCD. Again,as parts of Corridors One and Three,the terrain features of this corridor have been previously described. Corridor Fifteen -Watana to Devil Canyon via Stephan Lake,Devil Canyon to Intertie via North Shore,Susitna River (0) Corridor Two (ABEC)and Corridor Three (CF)form to create this study-area corridor.Terrain features have been presented under the discussions of each of these two corridors. B-2-99 (iii)Northern Study Area (0) In the northern study area,four transmission line corridor options exist for connecting Healy and Fairbanks (Figure B.2.7.3). Corridor One -Healy to Fairbanks via Parks Highway (0) Corridor One (ABC),consisting of Segments AB and BC,starts in the vicinity of the Healy Power Plant.From here,the corridor heads northwest, crossing the existing Golden Valley'Electric Association Transmission Line,the railroad,and the Parks Highway before turning to the north and paralleling this road to a point due west of Browne.Here,as a result of terrain features,the corridor turns northeast,crossing the Parks Highway once again as well as the~existing transmission line,the Nenana River,and the railroad,and continues northeasterly to a point northeast of the Cleat Missile Early Warning S ta tion (MEWS). Continuing;northward,the corridor eventually crosses the Tanana River east of Nenana,then heads northeast,first crossing Little Goldstream Creek, then the Parks Highway just north of the Bonanza ----------------.--------,---~-----.---.----Creek Exper-imetrta~t-Fo-re-s~t_;---Be-·fo-·re----r·ea·ch~in-g---the---- drainage of Ohio Creek,this corridor turns back to the northeast,crossing the old Parks Highway and heading into the Ester substation west of Fairbanks. Terrain along this entire corridor segment is relatively flat,with the exception of the .foothill s-nor-th_oLthe_...Tana naRiv.er •Much _of the ..-.-~.-~.-_.._~..._._....._._.__.__..r.o.u.t.e.,.e.s.p_e_c ially~that __Rortion between.the Nenana and the Tanana River crossings,is very broad and flat,has-standing water during the summer months and,in some places,is overgrown by dense stands of tall-growing vegetation.This corridor segment crosses the foothills northeast of Nenana,also a heavily-wooded area. ·.t\Il()pti()Il~ot1:leabove (and not shown in the figures),that of closely parallel and sharing rights-of-way with the existing Healy-Fairbanks transmission line,has been considered.While it is usually attractive to parallel existing I ~] } 'I 1 ) ,I '! 851104 B-2-100 corridors wherever possible,this option necessitates a great number of road crossings and an extended length of the corridor paralleling the Parks Highway.,A potentially significant amount of highway-abutting land would be usurped for containment of the right-of-way.These features, in combination,eliminated this corridor from further evaluation. Corridor Two -Healy to Fairbanks Wood River (0) via Crossing The second corridor (ABDC)is a variation of Corridor One and consists of Segments AB and BDC. At point B,east ·of the Clear MEWS,instead of turning north,the corridor continues to the northeast,crossing Fish Creek,the Totatlanika River,Tatlanika Creek,the Wood River,and Crooked Creek befQ~e turning to the north.At a point equidistant from Crooked and ,Willow Creeks,the corridor turns north,crosses the Tanana River east of Hadley Slough,and extends to the Ester substation.North of the Tanana River,this corridor segment also crosses Rose Creek and the Parks Highway. Where it diverges from the original corridor,this corridor traverses extensive areas of flat ground, with standing water very prevalent throughout the summer months.Heavily-wooded areas occur in the broad floodplain of the Tanana River,in the vicinity of the river crossing,and in the foothills around Rose Creek. Corridor Three -Healy to Fairbanks via Creek and Japan Hills (0) Healy 851104 Corridor Three (AEDC),consisting of Segments AE and EDC,exits the Healy Power Plant in an easterly direction.Instead of proceeding northwest,this corridor,following its interconnection with the Intertie Project,heads east up Healy Creek, passing the Usibelli Coal Mine.Near the headwaters of Healy Creek,the corridor cuts to the east,crossing a high pass of approximately 4,700 feet elevation and descending into the Cody Creek drainage.From Healy to the Cody Creek drainage, the terrain is relatively gentle but bounded by very rugged mountain peaks.The elevation gain from the Healy Power Plant to the pass between the B-2-101 Healy Creek-Cody Creek drainages is apprqximately 3,300 feet.From here,the segment turns to the northeast,following the lowlands accompanying the Wood River.The corridor next parallels the Wood River from the Anderson Mountain area,past Mystic Mountain,and out into the broad floodplain of the Tanana River east of Japan Hills.Near the confluence of Fish Creek and the Wood River,the corridor turns north and intersects the north-south portion of Corridor Two (Segment DC),after first passing through Wood River But tes.Much of the area north of Japan Hills is flat and very wet with stands of dense,tall-growing vegetation. -Corridor Four -Healy to Fairbanks via Wood River and Fort Wainwright (0) Corridor Four (AEF)is a derivation of Corridor Three and is composed of Segments AE and EF.Point E is located just north of Japan Hills along the Wood River.From here,the corridor deviates from corridor Three by running north across the Blair Lake Air Force Range,Fort Wainwright,and several tributaries of the Tanana River,before reaching the crossing of Salchaket Slough.Corridor Four passes Clear Creek Butte on the east.A new substation would be located on the Fairbanks side of the Tanana River just north of Goose Island. ~~~__c __·•,~c_~~-~,cFr()m-Pcyint;-E-to~Po'int'F,.the...terrain'ofthe'".. corridor is flat and very wet,and again,dense stands of tall-growingvegeta tion exist both in the better drained portions of the flat lands and in the vicinity of the river crossing. 2.7.3 Corridor Screening (0) _The.obje.c tives...of.the.scr.eening ...pro.ces.s..w.ere __t.o...:t:o.C.u~LQn_J:_h.e.p.~e=._ ......__~..__viously::-selected corridors and select those best meeting ._ technical,economic,and environmental criteria. (a)Reliability (0) Reliability is an uncompromising factor in screening alternative transmission line.corridors.Many of the ."'''crfi:::eriaiiti lizeCl forecoriorilic,en vir6tlI1ierital,arid te chri i cal reasonsal·sorelate to the-selection of a corridor within tiThich~iInec~n'be oPera.te dwI thmIollIltJm power interruption.Six basic factors were considered in relation to reliability: .( .\ ,J .l .! 851104 B-2-102 o Elevation: o Aircraft: o Stability: 0 Existing Power Lines: -I 0 Topography: I 0 Access: Lines located at elevations below 4,000 feet will be less exposed to severe wind and ice conditions,which can interrupt service. Avoidance of areas near aircraft landing and takeoff operations will minimize risks from collisions. Avoidance of areas susceptible to land, ice,and snow slides will reduce chance of power failures. Avoidance of crossing existing transmission lines will reduce the possibility of lines touching during failures and will facilitate repairs. Lines located in areas with gentle relief will be easier to construct and repair. Lines located in reasonable proximity to transportation corridors will be more quickly accessible and therefore more quickly repaired if any failures occur. (b)Technical Screening Criteria (0) Four primary and two secondary technical factors were con- sidered in the screening of alternative corridors. (i)Primary Aspects (0) -Topography (0) -Climate and Elevation (0) Low temperatures,snow depth,icing,and severe winds are very important parameters in transmission design,operation,and reliability. Climatic factors become more severe in the mountains,where extreme winds are expected for exposed areas and passes.The Alaska Power Administration believes that elevations above 4,000 feet in the Alaska Range and Talkeetna Mountains are completely unsuitable for locating major transmission facilities.Significant advantages of reliability and cost are expected if the lines are routed below 3,000 feet in elevation.This 851104 B-2-103 851104 elevation figure was used in the screening process. -Soils (0) Although transmission lines are less affected by soils and foundation limitations than railroads and pipelines,it is more reliable to build a transmission line on soil that does not appear to be underlain by seismically-induced ground failures.It is also desirable to avoid swampy areas where maintenance and inspection may create problems.These factors were utilized in the screening process.Because of the vast areas of wetlands in the study area,particularly in the southern portion,it was not possible.to locate a corridor that would avoid all wetland areas. -Length of Corridors (0) (ii)Secondary Aspects (0) -Vegetation and Clearing (0) Heavily-'forestedareas must be cleared prior to construction of the transmission line.Clearing the vegetation will cause some disruption of the soil.If the cleared right-of-way is not properly .~-~staonizea--tnrough~iestora t ic)n--ana re vegetaEroii~.- increased erosion will result.If the vegetation is cleared up to river banks on stream crossings, additional sedimentation may result.During the corridor screening,those corridors crossing large expanses of heavily timbered areas were el imina ted. Highway and river crossings were avoided where possible. B-2-104 .1 I j '.I, (c)Economic Screening Criteria (0) Three primary and one secondary aspect of the economic criteria were considered. (i)Primary Aspects (0) -Length (0) -Right-of-Way (0) Whenever possible,existing rights-of-ways were shared or paralleled to avoid problems associated with pioneering a corridor in previously inaccessible areas. -Access Roads (0) (ii)Secondary Aspects (0) In addition to the major considerations concerning economic screening of corridors,some other aspects were also considered.These include topography (since it is more economical to build a line on a flat corridor than on a-rugged or a mountainous one) and limiting the number of stream,river,highway, road,and railroad crossings in order to minimize costs. (d)Environmental Screening Criteria (0) Because of the potential adverse environmental impacts from transm~ssion line construction and operation, environmental criteria were carefully scrutinized in the screening process.Past experience has shown the primary environmental considerations to be: o Aesthetic and Visual (including impacts on recrea tion); o Land Use (including ownership and presence of existing righ ts-of-way)• Also of significance in the evaluation process are: o Length, o Topo gra phy , o Soils, 851104 B-2-105 851104 o Cultural Resources, o Vegeta tion, o Fishery Resources,and o Wildlife Resources. A description and rationale for use of these criteria are presented below. (i)Primary Aspects (0) -Aesthetic and Visual (o} The presence of large transmission line structures in undeveloped areas has the potential 10r adverse aesthetic impacts.Furthermore,the presence of ,these lines can conflict with recreational use, particularly those nonconsumptive recreational act;iv:i.ti~s such as hiltitlg ~md b:i.rd watching where .great emphasis is placed on scenic values.The number of road crossings encountered by transmission line corridors is also a factor that needs to be inventoried because of the potential for visual impacts.The number of roads crossed, the manner in which they are crossed,the nature of ..('!:J(;~~t i1'lg_y('!g('!t:a ti.Q1'l.1!~_J::h('!_~r 0 s §:i,1'lg__~j.J;:~_(:i,.~~,. potential visual screening),and the number and type of motorists using the highway all influence the desirability of one corridor versus another. Therefore,when screening the previously-selected corridors,consideration was focused on the presence of recreational areas,hiking trails, heavily utilized lakes,vistas,and highways where views of transmission line facilities would be -Land Use (0) The three primary components of land use considera- tions are:1)land status/ownership,2)existing rights-of-way,and 3)existing and proposed development. I..andStatus/Ownershipc(e)- The ownership of land to be crossed by a transmission line is important because certain B-2-106 '1 .1 ,1 J II I IU 851104 types of ownership present more restrictions than others.For example,some recreation areas such as state and federal parks and areas such as game refuges and military lands,among others,present possible constraints to corridor routing. Private landowners generally do not want transmission lines on their lands.This information,when known in advance,permits corridor routing to avoid such restrictive areas and to occur in areas where land use conflicts can be minimized • •Existing Rights-of-Way (0) Paralleling existing rights-of-way tends to result in less enviropmental impac~than that which is associated with a new right-of-way because the creation of a new right-of-way may provide a means of access to areas normally accessible only on foot.This can be a critical factor if it opens sensitive,ecological areas to all-terrain vehicles. Impact on soils,vegetation,stream crossings, and other inventory categories can also be lessened through the paralleling of existing access roads and cleared rights-of-way.Some impact'is still felt,however,even though a right-of-way may exist in the area.For example, cultural resources may not have been identified in the original routing effort. Wetlands'present under existing transmission lines may likewise be negatively influenced if ground access to the vicinity of the tower locations is required. There are common occasions where paralleling an existing facility is not desirable.This is particularly true in the case of highways that offer the potential for visual impacts and in situations where paralleling a poorly sited transmission facility would only compound an existing problem • •Existing and Proposed Developments (0) This inventory identifies such items as agricultural use,planned urban developments, B-2-107 851104 existing residential and cabin developments,the location of airports and lakes used for float planes,and similar types of information.Such information is essential for locating transmission line.corridors appropriately,as it presents conflicts with these land use act i vi ties. (ii)Secondary Aspects (0) -Length (0) The length ofa t.ransmission line is an enviromnental facto.r and,as such,was considered in the screening process.A longer line will require more construction activity than a shorter line,will disturb more land area,and will have a greater inherent probability of encountering environmental cons traint s Oil.., -Topography.(0) The natural features of the terrain are significant from the standpoint that they offer both positive and negative aspects to transmission line routing. Steep slopes,for example,present both difficult construction and soil stabilization problems with _p_~tent~~lly_:I,ong::term L neg~~i.~~~!lJti~o11I!t~I.l~~J. consequences.Also,ridge crossings have the potential for visuai impacts.At the same time, slopes and elevation changes present opportunities for routing transmission lines so as to screen them from both travel routes and existing communities. Hence,when planning corridors the identification of changes in relief is an important factor. ====..~_..__._.._.___---_._-.__~..-__. Soils are important from several standpoints. First of all,scarification of the land often occurs during the construction of transmission lines.Asa result,vegetation regeneration is affected,as arE:!the related features of soil stability arid erosion.potential.In addition,the development and installation of access roads,where .....·-necessary,are~~very-~dependent .upon soil types·. Tower designs and locations are dictated by the types of soils encountered in any particular corridor segment.Consequently,the review of existing soils information.is very significant. B-2-108 .J .1 851104 This inventory was conducted by means of.a Soil Associations Table,Table B.2.7.7.Table B.2.7.8 presents the related definitions as they apply to the terms used in Table B.2.7.7. -Cultural Resources (0) The avoidance of known or potential sites of cultural resources is an important component in the routing of transmission lines.A level-one cultural resources survey has been conducted along a large portion of the transmission corridors.In those areas where no information has been collected to date an appropriate program for identifying and mitigating impacts will be undertaken.This program is discussed in more detail in Chapter 4 of Exhibit E. -Vegetation (0) The consideration of the presence and location of various plant communities is essential in transmission line siting.The inventory of plant communities,such as those of a tall-growing nature or wetlands,is significant from the standpoint of construction,clearing,and access road development requirements.In addition,identification of locations of endangered and threatened plant species is also critical.While several Alaskan plant species are currently under review by the U.S.Fish and Wildlife Service,no plant species are presently listed under the Endangered Species Act of 1973 as occurring ·in Alaska.No corridor currently under consideration has been identified as traversing any location known to support these identified plant species. -Fishery Resources (0) The presence or absence of resident or anadromous fish in a stream is a significant factor in evaluating suitable transmission line corridors. The corridor's effects on a stream's resources must be viewed from the standpoint of possible disturbance to fish species,potential loss of habitat,and possible destruction of spawning beds. In addition,certain species of fish are more sensitive than others to disturbance. B-2-109 851104 Closely related to this consideration is.the number of stream crossings.The nature of the soils and vegetation in the vicinity of the streams and the manner in which the streams are to be crossed are also important environmental considerations when routing transmission lines.Potential stream degradation,impact on fish habitat through disturbance,and long-term negative consequences resulting from siltation of spawning beds are all concerns·that need evaluation in corridor routing. Therefore,the number of stream crossings and the presence.of fish species and habitat value were considered when data were available. -Wildlife Resources (0) The three major groups of wildlife which must be considered in transmission corridor screening are big game,birds,and furbearers.Of all the wildlife species to be considered in the course of routing studies for transmission lines,big game species (together with endangered species)are most significant.Many of the big game species, including grizzly bear,caribou,and sheep,are particularly sensitive to human intrusion into relatively undisturbed areas.Calving groungs, denning areas,and other important or unique habitat areas as identified by the Alaska Depa r"tnientof-F:LsnanGGame were·tdent-ifiedanG·· incorporated into the screening process. Many species of birds such as raptors and swans are sensitive to human dJstJJI."bance.Identifyingthe presence and location of nesting raptors and swans permits avoidance of traditional nesting areas. Moreover,if this ca.tegory is investigated,the .presence.ofendangered.species{viz,peregrine . .....fa Ij~.onsJ_._c_a.IL-b.e--!ie_t_e_rm i ne_d.•_..~_._. Important habitat for furbearers exists along many potential transmission line corridors in the Railbelt area,and its loss or disruption would have a direct effec·tonthese animal populations. Investigating habitat preferences ,noting existing hablta t,a.nd ..,identIfYing .po pula t ion s through .......•;,iY;,iil;,i1:>1~=~1l.j:()'I:TIl;,il;iQ11.C3.l:'.EL.impQI'l;ant ..st~ps in addressing the selection of environmentally acceptable alternatives. B-2-110 J .1 ! 1. (e)Screening Methodology (0) (i)Technical and Economic Screening Methodology (0) The parameters required for the technical and economic analyses were extracted from the environ- mental inventory tables (Tables B.2.7.4 through B.2.7.6).These tables,and Tables B.2.7.9 through B.2.7.lS are derived from studies carried out prior to the issuance of the Feasibility Report in March 1982;at that time the routing of the proposed access route was undecided.Subsequent to the publication of the Feasibilty Report the decision was made to select the Denali-North Plan as the proposed access route.Since the location of the aceess route is of major importance in relation to the transmission line_ within the central study area,the tables have been modified to reflect this decision and the ratings assigned to each corridor adj~sted accordingly.The reasons for changing these ratings are discussed in more detail in subsection 2.7.4. The tables,together with the topographic maps, aerial photos,and existing published materials,were used to compare the alternative corridors from a technical and econoIlIic~"point of view.The parameters used in the analysis were:length of corridors, approximate number of highway/road crossings-, approximate number of river/creek crossings,land ownership,topography,soils,and existing rights-of-way.The main factors contributing to the economic and technical analyses are combined and listed in Tables B.2.7.9,B.2.7.l0,and a.2.7.ll.It should be noted that most of the parameters are in miles of line length,except the tower construction. In this analysis,it was decided to assign 4.S towers for each mile of 34S-kV line. In order to screen the most qualified corridor,it was decided to rate the corridors as follows: Corridor rated A -recommended, Corridor rated C -acceptable but not preferred,and Corridor rated F -unacceptable. From a technical point of view,reliability is the main objective.An environmentally and economically sound transmission line was rejected if the line was not reliable.Thus,any line that received an F 8S1104 B-2-11 I technical rating was assigned an overall rating of F and eliminated from further consideration •. The ratings appear in each of the economic and technical screening tables (Tables B.2.7.9,B.2.7.10, and B.2.7.11)and are summarized in Table B.2.7.12. (ii)Environmental Screening Methodology (0) In order to compare the ~lternative corridors (Figures B.2.7.1,B.2.7.2,and B.2.7.3)from an environmental standpoint,the environmental criteria discussed above were combined into environmental constraint tables (Tables B.2.7.13, B.2.7.14 and B.2.7.15)•These tables combine information for eac~corridor segment into the proper corridors under study.This permits the assignment of an environmental rating,which identifies the relative rating of each corridor within each of the three study areas.The assignment of environmental ratings is a subjective,qualitative technique intended as an aid to corridor screening.Those corridors that are recommended are identified with an "A,"while those corridors that are acceptable but not preferred are identified with a "C."Finally, those corridors that are considered unacceptable are identified with an "F." The selected corridor consists·of the following segments: o Southern Study Area:Corridor ADFC (Figures B.2.7.4 and B.2.7.5), o Central Study Area:Corridor AJCD(Figures B.2.7.6 and B.2.7.7) .0 -·Nor the rn-"Study--Area:-"Corridor-AB€--'(-F-igures-B.2.7.8 Specifics of these corridors and reasons for rejection of others are discussed below.More detail on the screening process and the specific technical ratings of each alternative are in Chapter 10 of Exhibit E. (a)Southern Study Area (0) In the southern study area,Corridor Segment AEF and,hence, Corridor Three (AEFC)were determined unacceptable.This results primarily from the routing of the segment through the relatively well-developed and heavily-utilized Nancy .\ I .l 851104 B-2-112 1 851104 Lake state recreation area.Adjustments to this ~oute to make it more acceptable were attempted but no alterations proved successful.Consequently,it was recommended that this corridor be dropped from further consideration. Corridor One (ABC'),identified as.acceptable but not preferred,was thus given the C rating.Its great length, its traversing of residential and other developed lands,and the numerous creek crossings and extensive forest clearing involved relegate this corridor to this environmental rating.Economically and technically,this corridor has more difficulties than the other two considered.This is a longer line and crosses areas which may require easements in the area north of Anchorage. Corridor Two (ADFC)was identified as the candidate which would satisfy most of the screening criteria.This corridor is shown in Figures B.2.7.4 and B.2.7.5 and stretches from an area north of Willow Creek to Point MacKenzie in the south.The corridor is located east of the lower Susitna River and crosses the Little Susitna River.The corridor also crosses an existing 138-kV line owned and operated by Chugach Electric Association (CEA),which starts at Point MacKenzie and extends to Teeland Substation. Up to this point in the corridor selection study,Point;. MacKenzie has been considered a terminal point for Susitna power.It was assumed tha.t an underwater cable crossing would be provided at this location.Upon further study and data gathering it has become known that the existing crossing at Point MacKenzie has experienced power interruptions caused by ships'anchors snagging the submarine cables.CEA,which owns the submarine cables, required additional transmission capacity to Anchorage. After thoroughly studying the matter,it has opted for a combined submarine/overhead cable transmission across Knik Arm and on to Anchorage.This was the most desirable option to CEA from both the environmental and technical point of view. The CEA crossing will be located approximately 8 miles northeast of Point MacKenzie on the west shore of the Knik Arm and across 'from Elmendorf Air Force Base in the vicini ty of Six Mile Creek.This crossing is located northeast of Anchorage Harbor,away from heavy ship traffic,thereby reducing the risk of anchor damage to the cable. It is intended to terminate Corridor ADFC at this new crossing point and extend the transmission corridor to Elmendorf Air Force Base and beyond to Anchorage. B-2-113 Although the crossing is approximately 8 miles no~theast of Point MacKenzie,it does not influence the resul ts of this corridor selection and screening process.The best corridor has been selected and screened.During routing studies minor deviations outside the corridor will have to occur in order to terminate at the revised crossing point.However, preliminary investigations indicate it will be possible to select a technically,economically,and environmentally acceptable route,particularly since an existing transmission line can likely be paralleled frqm the selected corridor to the revised crossing point.Furthermore,CEA has received the necessary permits and is constructing an underwater crossing at Knik Arm,indicating acceptable levels of environmental impact. (b)Central Study Area (0) In the central study area,several corridor segments and -their associated corridors were determined to be unacceptable.The first of these ,Corridor Segment BEC, appears laS.part of Corridors Two (ABECD),Five (ABECJHI), Seven (CEJAHi),-Nine (C.EBAG),and Fifteen (ABECF).The primary reason for rejecting this segment is that the developed recreation area around Stephan Lake would be needlessly harmed because viable options exist to avoid intruding into this area.An acceptable modification could not be found and,consequently,it is recommended that these _________!i~e c()l:l:'idc~_rs _~~~ropp=-~fr.~mfurt~er_,=-~~l~ideration. Corridor Segment AG was also determined not to warrant further consideration,-because of its approximate 65-mile length,two-thirds of which would pos sibly require a pioneer access road.Also,extensive-areas of-clearing would be required,opening the corridor to view in some scenic locations.Finally,the impacts on fish and wildlife habitats are potentially severe.These preliminary findings,-coupledwi-th-the--fact--that-more-viable-options__to _ --Segment-AG--ex-i-st-,~-sugges-t--tha-t-_consideIa_t.ion __o_f_t.hLs____ corridor segment and therefore Corridors Eight (CBAG)and Ten (CJAG)should be terminated. Corridors Eleven (CJAHI)and Twelve (JA-CJHI)were identified as not acceptable.This rating arose from the _fact that ,aslilhown in Environmental Constraint Table B.2.7.14,numerous constraints affect this routing. Irifo:rIliation-frolllrecentlycompleted..:-fielci-:i,nye s t:i,gations suggest that these constraints cannot be overcome and the routes should be rejected.Furthermore,the technical and economical ratings preclude these corridors from further consideration. 1 J ! .j 1 851104 B-2-114 ] Corridor Segment HJ has been moved so that it no longer parallels the Devil Creek drainage;the new location HC is selected to avoid both High Lake and the Devil Creek drainage.It then follows the Portage Creek drainage to the point of intersection with Corridor Segment JH,near the creek's headwaters.Subsequent investigations have con- firmed that this corridor segment is not viable and, consequently,Corridors Four and Five are eliminated from further consideration. Corridor Six (CBAHI)intrudes on valuable wildlife habitat and would cross numerous creeks,none of which are currently crossed by existing access roads.In addition,a high mountain pass and its associated shallow soils,steep slopes,and surficial bedrock constrain this routing. Finally,its crossing of areas over 4,000 feet in elevation makes it technically unacceptable,so this corridor is dropped from further consideration. The four remaining corridors (Corridors One,Three,Thirteen and Fourteen)were each identified as being acceptable in terms of the technical,economic and environmental criteria described in subsection 2.7.3. The Denali-North Plan was selected as the proposed access route for the Susitna development (subsection 2.6.8).The location of existing and proposed access is of prime importance both from an economic and environmental standpoint.Therefore,subsequent to the access decision, each of the four corridors was subjected to a more detailed evaluation and comparison.In order to more directly compare the four corridors a preliminary route was selected in each of the segments.The final route selection process leading to the perferred route in the corridor,which was subsequently recommended,is discussed in more detail in subsection 2.7.5.The four corridors comprise the following segments: o Corridor One o Corridor Three o Corridor Thirteen o Corridor Fourteen ABCD, AJCF, ABCF,and AJCD. 851104 Segments ABC and AJC link Watana with Devil Canyon and, similarly,segments CD and CF link Devil Canyon with the Intertie. B-2-1l5 851104 (i)The Choice Between CD and CF (0) On closer examination of the possible routes between Devil Canyon and the Intertie,segment CD was found to be superior to segment CF for the following , reasons. Economic (0) A four-wheel drive trail is already in existence on the south side of the Susitna River between Gold Creek and the proposed location of the railhead facility at Devil Canyon.Therefore,the need for new roads along segment CD,both for construction and oper~tion and maintenance,is significantly less than for segment CF,which requires the construction of a pioneer road.In addition,the proposed Gold Creek to Devil Canyon railroad extension will also run parallel to segment CD.The lengths of Segments CD and CF are 8.8 miles and 8.7 miles,respectively--not a sigtitfi~'antdifferen~e~'Among the secondary economic considerations is that of topography. Segment CF crosses more rugged terrain at a higher elevation than segment CD and would therefore prove mO.re difficul,t and costly to construct and maintain.Hence,segment CD was considered to have a higher overall economic rating. Technical (0) Although both segments are routed below 3,000 feet elevation,segment CF crosses more rugged, exposed terrain with a maximum elevation of 2,600 feet.Segment CD,on the other hand,traverses generally flatter terrain and has a maximum ..elevation,ofl,.8,QO.,fJ:!et!_ThJL.Qj,~a,c:lya,I'!!=,a,g~.§l_2.t, se~ent,CF._ar~_somewhat offset,however,by the Susitna River crossing 'thatwITT'be needed a't-'--' river mile 150 for segment CD.Overall,the technical difficulties associated with the two segments may be regarded as being similar. ,Environmental (0) One of the main concerns of.the variousenv[cot111lenEaIgroups and agencies is to keep a.ny form of access away from sensitive ecological areas previously inaccessible other than by foot. Creating a pioneer road to construct and maintain B-2-116 .J ] J 851104 a transmission line along segment CF would open that area to all-terrain vehicles and public use, and thereby increase the potential for adverse impacts to the environment.The potential for environmental impacts along segment CD would be present regardless of where the transmission line was built since there is an existing four-wheel drive trail together with the proposed railroad extension in that area.It is clearly desirable to restrict environmental impacts to a single common corridor;for that reason,segment CD is .preferable to segment CF. Because of potential environmental impacts and economic ratings,segment CF was dropped in favor of segment CD.Consequently,corridors Three (AJCF)and Thirteen (ABCF)were eliminated from further cons idera tion. (ii)The Choice Between ABC and AJC (0) The two corridors remaining are therefore corridors One (ABCD)and Fourteen (AJCD).This reduces to a comparison of segment ABC on the south side of the Susitna River and segment AJC on the north side.The two segments were then screened in accordance with the.criteria set out in subsection 2.7.3.The key points of this evaluation are outlined below: Economic (0) For the Watana development,two 345 kV transmission lines will be constructed from Watana through to the Intertie.When comparing the relative lengths of transmission line,it was found that segment ABC was 33.6 miles in total length compared to 36.4 miles for the northern route using segment AJC.Although at first glance a difference in length of 2.8 miles (equivalent to 12 towers at a spacing of 1,200 feet)seems significant,other factors were taken into account.Segment ABC contains mostly woodland, black spruce in segment AB.Segment BC contains open and woodland spruce forests,low shrub,and open and closed mixed forest in about equal amounts.segment AJC,on the other hand,contains significantly less vegetation and is composed predominantly of low shrub and tundra in segment AJ and tall shrub,low shrub and open mixed forest in segment JC.Consequently,the amount of B-2-1l7 851104 clearing associated with segment AJC is ~onsider­ ably less than with segment ABC,resulting in savings not only during construction but also during periodic recutting.Additional costs would also be incurred with segment ABC due to the increased spans needed to cross the Susitna River (at river mile 165.3)and two other major creek crossings.In summary,the cost differential between the two segments would probably be marginaL Technical (0) Segment AJC traverses generally moderately-sloping terrain ranging in height from 2,000 feet to 3,500 feet with 9 mile'S of the segment being at an elevation in excess of 3,000 feet.Segment ABC traverses more rugged terrain,crossing several deep ravines and ranges in elevation from 1,800 .feet to 2,800 feet.In general there are advantages of reliability and cost associated with transmission lines routed under 3,000 feet.The 9 miles of segment AJC at elevations in excess of 3,000 fe.et will be subject to more severe wind and ice loadings than _segment ABC,and the towers will have to be designed accordingly •Hqwever,these additional costs will be offset by the construction and maintenance problems with the more rugged topography and major river -and cree~k crossings of segment ABC.The technical difficulties associated with the two segments are therefore considered simila r. Environmental (0) From the previous analysis,it is evident that th er ear ~~l!Q__si g!l:..-iJ i <:i!..I!~_I;tiJ~f_ex.enc_e~~_betwee n_~th e~. ~~--~--two--s-egments in terms of technicaldi fficul ty and economics.The deciding factor therefore reduces to the environmental impacts.The access road routing between Watana and Devil Canyon was selected because it has the least potential for creating adverse impacts to wildlife,wildlife habitat and fisheries.Similarly,Segment AJC, withinwhichtheacce$sroad is loca.fed,is .en-v:ir0tnnel1tall;yl es s seIlS itive~ha.n .SegmE!tl t A.BC, for it traver'ses or approaches fewer areas of productive habitat and zones of species concentration or movement.The most important consideration,however,is that for ground access B-2-118 ] 'j .1 .1 J during operation and maintenance,it will be necessary to have some form of trail along the transmission line route.This trail would permit human entry into an area which is relatively inaccessible at present,causing both direct and indirect impacts.By placing the transmission line and access road within the same general corridor as in Segment AJC,impacts will be confined to that one corridor.If access and transmission are placed in separate corridors,as in Segment ABC,environmental impacts would be far greater. Segment AJC is thus considered superior to Segment ABC.Consequently,Corridor One (ABCD)was eliminated and Corridor Fourteen (AJCD)selected as the proposed route. (c)Northern Study Area (0) Corridors Three (AEDC)and Four (AEF)were determined unac- ceptable because of many constraints,and thus rated F. They include:the lack of an existing access road;prob- lems in dealing with tower erection in shallow bedrock zones;the need for extensive wetland crossings and forest clearing;the 75 riv.er or creek crossings involved;and the fact that prime habitat for waterfowl,peregrine falcons, caribou,bighorn sheep,'golden eagle,and brown bear would be crossed.In addition,Corridor Four crosses areas of significant land use constraints and elevations of over 4,000 feet. Corridor Two (ABDC)was identified as acceptable but not preferred,and thus rated C.Certain constraints indenti- fied for this corridor suggest that an alternative is pref- erable.Compared with Corridor One,Corridor Two crosses additional wetlands and requires the development of more access roads and the clearing of additional forest lands. Corridor One (ABC),shown in Figures B.2.7.8 to B.2.7.11, was the only recommended corridor in the northern study area.While many constraints were identified under the various categories,it appears possible to select a route within this corridor to minimize constraint influences. This corridor is attractive economically,because it is close to access roads and the Parks Highway.The visual impact can be lessened by strategic placement of the line. This line also best meets technical and economical req uirements • 851104 B-2-U9 2.7.5 Route Selection (0) (a)Methodology (0) After identification of the preferred transmission line corridors,the next step in the route selection process involved the analysis of the data as gathered and presented on the base map.Overlays were compiled so that various constraints affecting construction or maintenance of a transmission facility could be viewed on a single map.The map was used to select possible routes within each of the three selected corridors.By placing all major constraints (e.g.,areas of high visual exposure,private lands,endan- gered species,etc.)on one map,a route of least impact was selected.Existing facilities,such as transmission lines and tractor trails within the study area,w~re also considered during the selection of a minimum 'impact route. Whenever possible,the routes were selected near existing or proposed access roads,sharing werever possible existing righ t s-of-way. The data ..base used in this aria lysis wa.s obtain.ed from the following sources: o An up-to-date land status study, o Existing-aerial photos, o New aerial photos conducted for selected sections of the previously-recommended transmission line , o Environmental studies including aesthetic considerations, o Climatological studies, o Geotechnical exploration, o Additional field studies,and o Public opinions • ......."'...····(b}-Sele ction··Cr iter-ia{.o.)--.-..---__.__._.... The purpose of this section is to identify three selected routes:one from Healy to Fairbanks,the second from the Watana and Devil Canyon damsites to the Intertie,and the third from Willow to Anchorage. The previously-chosen corridors were subject to a process of refinement and evaiut iotl based on the.s;:tme techriical, ~economic,;:tn<:i·gn'V'iroOIngntalcrit~r;8:.usgdin corridor sel- ection.In addition,special eUlphasis was placed on the following points: ,] 1 851104 B-2-120 o Satisfying the regulatory and permit requir~ments; o Selection of routing that provides for minimum visibility from highways and homes;and o Avoidance of developed agricultural lands and dwellings. (c)Environmental Analysis (0) The corridors selected were analyzed to arrive at the route which is most compatible with the environment and also meets engineering and economic objectives.The environ- mental analysis was conducted by the process described below: o Literature Review (0) Data from various literature sources,agency communi- cations,and site visits were reviewed to inventory existing environmental variables.From such an inventory,it was possible to identify environmental constraints in the recommended corridor locations. Data sources were cataloged and filed for later retrieval. o Avoidance Routing by Constraint Analysis (0) To establish the most appropriate location for a transmission line route,it was "necessary to identify those environmental constraints that could be impediments to the development of such a route.Many specific constraints were identified during the preliminary screening;others were determined during the 1981 field investigations. By utilizing information on topography,existing and pro~osed land use,aesthetics,ecological features, and cultural resources as they exist within the corridors,and by careful placement of the route with these considerations in mind,impact on these various constraints was minimized. o Base Maps and Overlays (0) Constraint analysis information was placed on base maps.Constraints were identified and presented on overlays to the base maps.This mapping process involved using both existing information and that acquired through Susitna project studies.This information was first categorized as to its potential for constraining the development of a transmission 851104 B-2-121 line route within the preferred corridor and then placed on maps of the corridors.Environmental constraints were identified and recorded directly onto the base maps.Overlays to the base maps were prepared indicating the type and extent of the encountered constraints. Three overlays were prepared for each map:one for visual constraints,one forman-made,and one for biological constraints (Acres,TES 1982). (d)Technical and Economic Analysis (0) Route location objectives are to obtain an optimum combina- tion of reliability and cost with the fewest environmental problems.In many cases,these objectives are mutually compatible. Throughout the evaluation,much emphasis was placed on locating the route relatively clos.e to existing surface transportation facilities whenever possible. The factors that contributed heavily in the technical and economic analysis were:topography,climate and elevation, soils,length,and access roads.Other factors of less importance were vegetation and river and highway crossings. These factors are detailed in Tables B.2.7.3 and B.2.7.16. The next step in the .routeselection process involved analysis of the data presented on the base maps.The da ta we'['e used to select pOSll3ible routes within each corridor.By placing all major constraints on one map,routes of smallest impacts were selected. Existing facilities,such as transmission lines and tractor.trails-within..the.studyarea.,were .a1so ..taken ..in to .cons i de.:c.a t i.o..1l.:.c.d tlr i ng.J;:lLe~s eJ,..e~t:io.n.Qfa l.e.a.s.t... impact route. j .J ,j ,l " (ii )Evaluation of a Primary Route (0) 851104 The evaluation and selection of alternative routes to arrive at'a primaryroute.involved a closer examfna.tion of.each.ofothe"possible routes using ··J:Il~pp$Ilgpr()c=e~Sle§l:andcl~t:~p.z;.ev:i.(luslYclesC=l:i1:>ed! Preliminary routes were compared to determine the route of least impact within the primary corridors of each study area.For.example,such variables as number of stream and road crossings required were B-2-122 .1 I 1 i I noted.Then,following the field studie~and through a comparison of routing data,including the route's total length and its use of existing facilities,one route was designated the primary route.Land use, land ownership,and visual impacts were key factors in the selection process. (e)Route Soil Conditions (0) (i)Description (0) Baseline geological and geotechnical information was compiled through photo interpretation and terrain unit mapping.The general objective was to document the conditions that would significantly affect the design and construction of the tranmission line towers.More specifically,these conditions include the origins of various land forms,noting the occurrence and distribution of significant geologic features such as permafrost,potentially unstable slopes,potentially erodible soils,possible active fault traces,potential construction materials, active floodplains,organic materials,etc. Work on the air photo interpretation consisted of several activities culminating in a set of terrain unit maps showing surface materials,geologic features,and conditions in the project area. The first activity consisted of a review of the literature concerning the geology of the Intertie corridors and transfer of the information gained to high~level photographs at a scale of 1:63,000. Interpretation of the high-level photos created a regional terrain framework which assisted in interpretation of the low-level 1:30,000 project photos.Major terrain divisions identified on the high-level photos were then used as an aerial guide for delineation of more detailed terrain units on the low-level photos.The primary effort o·f the work was the interpretation of over 140 photos covering about 300 square miles of varied terrain.The land area covered in the mapping exercise is shown on map sheets and displayed in detail on photo mosaics (R&M Consultants 1981a). As part of the terrain analysis,the various bedrock units and dominant lithologies were identified using published U.S.Geological Survey reports.The extent of these units was shown on the photographs,and, 851104 B-2-123 using exposure patterns,shade,texture,and other features of the rock unit as they appeared on the photographs,unit boundaries were drawn. Physical characteristics and typical engineering properties of each terrain unit were considered and a chart for each corridor was developed.These charts identify the terrain units as they have been mapped and characterize their properties in numerous categories.This allows an assessment of each unit's influence on various project features. (ii)Terrain Unit Analysis (0) (1 ,\ The terrain unit is a special purpose term comprising the land·forms expected to occur from the ground '} surface to a depth of about 25 feet.'..;~ The terrain unit maps for the proposed Anchorage-to- Fairbanks transmission line show the aerial extent of 'J the specific terrain units which were identified during-the air photo investigation and were corrobo- rated in part by a limited on-site surface investiga-,'.1 tion.The units document the general geology and geotechnical ,characteristics of the area. The north and south corridors are separated by J several hundred miles and,not surprisingly, eucoun-tet'··diffe-t'ent-,·geomot'ph-iG--pt'ov-iuGes and-c-l-imatic condi tions.Hence,while there are many landforms ,,\, (or individual terrain units)that are common to both ) corridors,there are also some landforms mapped in just one corridor.The landforms or individual '..( terrain units mapped in both corridors were briefly ) described.' Several of the landforms have not been inde- 851104 pendently but rather as compound or complex terra --,-uni~-Gompound---terrain units resuftwhen one ----- landform overlies a second recognized unit at a shallow depth (less than 25 feet),such as a thin deposit of glacial till overlying bedrock or a mantle of lacustrine sediments overlying till.Complex terrain units have been mapped where the surficial exposure pattern of two landforms are so intricately related that they must be mapped as a terrain unit complex,Stich as some areas of bedrock and colltivit:lrii. The compound and complex terrain units were described as a composite of individual landforms comprising them.The stratigraphy,topographic position,and B-2-124 l J .) i J-:; aerial extent of all units,as they appear in each corridor,were summarized on the terrain·unit properties and engineering interpretations chart (R&M Consultants 1981a). (f)Results and Conclusions (0) A study of existing information and aerial overflights,to- gether with additional aerial coverage,was used to locate the recommended route in each of the southern,central,and northern study areas. Terrain unit maps describing the general material expected in the area were prepared specifically for transmission line ..studies and were used to loca te the route away from unfavor- able soil conditions wherever possible.Similarly,environ- mental constraint analysis information was placed on base maps and overlays (Acres,TES 1982)and the route modified accordingly. Subsequent to the submission of the Feasibility Study (Acres 1982c),additional environmental and land status studies made it possible to further refine the alignments to the extent that most environmentally sensitive areas and areas where land acquisition may present a problem have been avoided.In the Fairbanks-to-Healy and the Willow-to- Anchorage line sections,these refinements have resulted in an improved alignment which is generally in close proximity to the earlier proposal. Also subsequent to the Feasibility Study,the proposals for access to the power development were reassessed.As mentioned earlier,this resulted in a decision to provide access to Watana for the Denali Highway and build a connecting road between the dams on the north side of the Susitna River.The earlier line routing proposals were accordingly reviewed to establish the optimum alignment. The desire to limit environmental impacts to a single corridor led to the routing of the transmission line more or less parallel to the access road.Hence,between the dams, the line shares the same general corridor as the access road to the north of the Susitna River.From Devil Canyon to the intersection with the Intertie (at a switching station approximately four miles northeast of Gold Creek),the line is located south of the Susitna River paralleling the proposed railroad extension,and an existing four-wheel drive trail. The original corridors,which were three to five miles in width,were narrowed to a half mile and,after final adjust- 851104 B-2-125 ment,to a finalized route with a defined right~of-way.The selected transmission line route for the three study areas is presented in Exhibit G.Preliminary studies have indicated that,for a hinged-guyed X-configuration tower having horizontal phase spacing of 33 feet,the following right-of-way widths should be sufficient: I J o 1 tower o 2 towers o 3 towers o 4 towers 190 feet, 300 feet, 400 feet,and 510 feet. These right-of-way widths will be subject to minor local variation where the need for special tower structures dic- tates or where difficult terrain is encountered 'and will be addressed fully in the final design phase of the project. 2.7.6 Towers,Foundations and Conductors (0) The Anchorage and Fairbanks Intertie will consist of existing lines and a new section between Willow and Healy.The new s-ecEi6tiwilr be b'liilEE6345kVsbitida.rdsblit will be temporarily operated at 138 kV and will be fully compatible with Susitna requirements. (a)Transmission Line Towers (0) (i)Selection of Tower Type (0) Because of the unique soil conditions in Alaska which are characterized by extensive regions of muskeg and permafrost,conventional self-supporting or rigid towers will not provide a satisfactory solution for the proposed transmission line. Permafrost and seasonal changes in the soil are known -tocaus e-largeearth-moveme nt s-at--someloca t io ns,- ..~r_eq_uidng_t.o.w_e.r.s._w_ith_a_.high_degr.ee_.o_f .._fl.exibili.ty__ and capability to sustain appreciable loss of structural integrity. A guyed tower is well suited to these conditions; these include the guyed-V, guyed-Y,guyed delta,and guyed portal type structures.The type of structure ·selected for·the construction o{the Intertie is the hing~ci-"g'Uy~dl;t:~~lX:'::t:ow~:r,c9,r~JiI1~lll~I1t0 f theguyeci structure concept.This type of tower is therefore a prime candidate for use on the Watana transmission system.Guyed pole-type structures will be used on larger angle and dead end structures;a similar I J j 851104 B-2-l26 ) J 851104 arrangement will be used in especially heavy loading zones. The design features of the X-tower include hinged connections between the legs and the foundation and four longitudinal guys attached in pairs to two guy anchors,providing a high degree of flexibility with excellent structural strength.The wide leg spacing results in relatively low foundation forces which are carried on pile type footings in soil and steel grillage or rock anchor footings where rock is close to the surface. In narrow right-of-way situations,cantilever steel pole structures are anticipated,with foundations consisting of cast-in-lace concrete augered piles. In the final design process,experience gained in the construction and operation of the Intertie will be used in the final selection of the structure type to be used for the Watana transmission. All tower structures will be of "weathering"type steel which matures to a dark brown color over a period of a few years and is considered to have a more aesthetically pleasing appearance than either galva~ized steel or aluminum. (ii)Climatic Studies and Loadings (0) Climatic studies for transmission lines were performed to determine probable maximum wind and ice loads based on historical data.A more detailed study incorporating additional climatic data was carried out for the Intertie final design.These studies have resulted in the selection of preliminary loading for the line design (Acres 1982c,Vol.4)• Preliminary loadings selected for line design should be confirmed by a detailed study,similar to that performed for the Intertie,that will examine conditions for the Healy-to-Fairbanks, Willow-to-Anchorage and Gold Creek-to-Watana sections of the route,together with an update of the Healy-to-Willow study incorporating any data from field measurement stations collected in the interim period. B-2-127 851104 (b) Based on data currently available,it appears that the line can be divided up into zones as far as climatic loading is concerned as follows: o Normal Loading Zone, o Heavy Ice Loading Zone,and o Heavy Wind Loading Zone. The heavy ice and heavy wind zones will have an addi- tional critical loading case included to reflect the special nature of the zone. (iii)Tower Family (0) A family of tower designs will be developed as follows: o Suspension towers will be provided for both standard span plus angle (up to 3°)application .and for long span or light angle (0°to 8°) application. o Tension towers will be provided for light angle and dead end (0°to 8°),for large angle and dead end (8°to 50°),and for minimum angle and dead end (50°to 90°). The maximum wind span and weight span ratios to be .-···uti-Uzed ~i:J:tDe-~ret infinal--di'fsignto-refl ectthe .. rugged nature of the terrain along the line route. Some triaL spotting.of towers in representa ti ve terrains will be used to guide this selection. Minimum weight ~pl:i..!ltowind span ratio limits will be set during tower spotting and a "low temperature template"used to check that unexpected uplift will not develop at low weight .span towers for very low The span to be used in design will be the subject of an economic optimization study.A span of not less than 1,200 feet is expected with spans in the field varying to greater and lesser values in specific cases depending upon span ratio and loading zone. Geotechnical Conditions (0) The generalized terrain analysis (R&M Consultants 1981a) was conducted to collect geologic and geotechnical data B-2-l28 ) l '~1 I J J 1 for the transmission line corridors,a relatively large area.The engineering characteristics of the terrain units have been generalized and described qualitatively. When evaluating the suitability of a terrain unit for a specific use,the actual properties of that unit must be verified by on-site subsurface investigation,sampling, and laboratory testing. The three main types of foundation materials along the transmission line are: o Good material,which is defined as overburden which permits augered excavation and allows installation of concrete without special form work; o Wetland and permafrost material which requires special design details;and o Rock material de fined as material-in which drilled-in anchors and concrete footings can be used. Based on aerial,topographic,and terrain unit maps,the following was not;:ed: o For the southern study area:Wetland and permafrost materials constitute the major part of this area.Some rock and good foundation materials are present in this area in a very small proportion. o For the central study area:Rock foundation and good materials were observed in most of this study area. For the northern study area:The major part of this area is wetland and permafrost materials.Some parts have rock materials. (.1.'1.')f 'Types 0 Foundat1.ons (0 ) 851104 The types of tangent tower envisaged for these lines will require foundations to support the leg or mast capable of carrying a predominantly vertical load with some lateral shear,and a guy anchor foundation. B-2-129 The cantilever pole structure foundation.is required to resist the high overturning moment inherent in the cantilever arrangement • The greater part of the combined maxnnum reactions on a transmission tower footing is usually from short duration loads such as broken wire,wind,and ice. With the exception of heavy-angled,dead end or terminal structures,only a part of the total reaction is ofa permanent nature.As a consequence,the permissible soil pressure,as used in the design of Quilding foundations,may be considerably increased for footings for transmission struc tures • The permissible values of soil pressure used in the footing design will depend on the structure and sup- porting soil.The basic criterion is that displacement of the footing not be restricted because of the flexibility of the selected X-frame tower and its hinged connection to the footing.The shape and configU1:ation of the selected.tower are important factors in foundation considerations. Loads on the tower consist of vertical and horizontal loads and are transmitted down to the foundation and then distributed ~o the soil.In a tower placed at an angle or used as dead end in the line,the--_.------.--···------------liofTion far -roads.·~i"re--res·ponsiorefor--·-a·Ta rge-·portion of the loads on the foundation.In addition to the horizontal shear,a moment is also present at the top of the foundation,creating vertical download and upl iftforces on the footing. To enable the selection of a safe and economical tower foundation design for each tower site,it is .····-·--neces·saI'-y~-to·sele ct-·a·footing-which take saccount·o f· .the_ac.l:.ual-soil__.condi..tio.ns_a.~-the-si.te..__This_is...done_.. by matching the soil conditions td a series of ranges of soil types and groundwater conditions which have been predetermined during the design phase to cover the full range of soils expected to be encountered along the line length.Preconstruction drilling, soil saIllpling,and laboratory testing at representative locations along the line enable the design ofa familyoLfo·otings tobeprepa red for each tower type from which a selection of the appropriate footing for the specific site can be made during construction. I I 851104 B-2-130 The foundation types for structure legs and masts will be grouted anchor where rock is very shallow or at surface and steel grillage with granular backfull where soil is competent and not unduly frost-sensitive.In areas where soils are weak and where permafrost or particularly frost-heave prone material is encountered,driven steel piles will be used. Guy anchors will use grouted anchors in rock. Grouted earth or helical plate screw-in anchors with driven piles will be used in permafrost or very weak soils. Proof load testing of piles and drilled-in anchors will be required both for design and to check on the as-built capacity of these foundation elements during construction. (c)Voltage Level and Conductor Size (0) Economic studies were carried out on transmission utilizing 500 kV,345 kV,and 230 kV a.c.At each voltage level an optimum conductor capacity was developed.Schemes involving use of 500 kV or 345 kV on the route to Anchorage and 345 kV or 230 kV to Fairbanks were investigated.The study recommended the adoption of two 345-kV units to Fairbanks and three 345-kV units to Anchorage.Comparative studies were carried out on the possible use of HVDC.However, these studies indicated no economic advantage of such a scheme. The 345-kV system studies indicated that a conductor capacity of 1,950 MCM per phase was economical with due account for the value of losses.A phase bundle consisting of twin 754-MCM Rail (45/7)ACSR was proposed as meeting the required capacity and also having acceptable corona and radio interference performance.Detailed design studies as part of the final design will compare the economics of this conductor configuration with the use of alternatives such as twin 954-MCM Cardinal (54/7)ACSR and single 215.6-MCM Bluebird (84/19)ACSR which could give comparable electrical performance with better structural performance.Cardinal, because of a 15 percent superior strength-to-weight ratio, can be sagged tighter than Rail,thereby resulting in savings in tower height and/or increased spans.Bluebird, because of a smaller circumference and projected area compared with a twin conductor bundle,attracts some 15 851104 B-2-131 851104 percent less load from ice or wind.Together with its greater strength,this leads to less sag under heavy loadings and lighter loads for the structures to carry. Conductor swing angles will also be reduced,thus reducing tower head size requirements and edge of right-of-way clearing. B-2-132 ,\ I 3 -DESCRIPTION OF PROJECT OPERATION (***) 3.1 -Hydrology (**) Operation of the Susitna project is dependent upon the hydrology of the basin.A complete discussion of the Susitna basin hydrology appears in Section 2.2 of Exhibit E,Chapter 2.A summary follows. 3.1.1 -Historical Streamflow Records (**) Continuous historical streamflow records of various length (7 to 34 years through water year 1983)exist for gaging stations on the Susitna River and its tributaries.USGS gages are located at Denali,Cantwell (Vee Canyon),Gold Creek,and Susitna Station on the Susitna River;near Paxson on the Maclaren River;near Talkeetna on the Chulitna river;at Talkeetna on the Talkeetna River;and at Skwentna on the Skwentna River. In 1980 a USGS gaging station was installed near Susitna Station on the Yentna River,and in 1981 a USGS gaging station was installed at Sunshine on the Susitna River.Statistics on river mile,drainage area,and years of record are shown in Table B.3.1.1.A summary of the recorded maximum,mean,and minimum monthly flows for water year 1951 s through 1981 are shown in Table B.3.1.2.Because of the short duration of the streamflow records at Sunshine and on the Yentna,summaries for these two stations have not been included.The station locations are illustrated on Figure B.3.1.1. Monthly and weekly streamflow sequences for the Susitna River at the Watana and Devil Canyon damsites and at Gold Creek were estimated from the existing USGS data.The procedures are outlined in a report by the Applicant (HE 1985).Tables B.3.1.3 through B.3.1.5 provide estimated monthly streamflow at Watana, Devil Canyon,and Gold Creek,respectively.Tables B.3.1.6 through B.3.1.8 provide weekly streamflow for the same locations. The streamflow sequences were used in weekly and monthly reservoir operation simulations.The 1969 low flow year was not modified for these sequences as it had been for the July 1983 License Application (APA 1983).Table B.3.1.9 compares the estimated monthly mean,maximum,and minimum flows at several sites in the basin.. Comparison of mean annual flows in Table B.3.1.9 indicates that 40 percent of the streamflow at Gold Creek originates above the Denali and Maclaren gages.It is in this catchment that the glaciers which contribute to the flow at Gold Creek are located. Figure B.3.1.2 shows the average annual flow distribution within the Susitna River Basin.The Susitna River above Gold Creek 851104 B-3-1 contributes approximately 20 percent of the.mean annua~flow measured at Susitna Station near Cook Inlet.The Chulitna and Talkeetna Rivers contribute about 20 and 10 percent of the mean annual flow at Susitna Station,respectively.The Yentna provides 40 percent of the flow,with the remaining 10 percent from miscellaneous tributaries. The variation between summer mean monthly flows and winter mean monthly flows is greater than a 10 to 1 ratio at all stations. This large seasonal difference is due.to the characteristics of a glacial river system.Glacial melt,snow melt;and rainfall provide th.emajority of .the annual river flow during the s~mer. At Gold Creek,for example,almost 90 percent of the annual streamflow volume occurs during the months of May through September. A comparison of the maximum and minimum monthly flows for May through September indicates a high flow variability at all stations from year to year. 3.1.2 -Effect of Glaciers (***) The glaciated portions of the Susitna River Basin above Gold Creek play a significant role in the hydrology of the area. Located on thedsouthern slopes of the Alaska Range ;the glaciated regions receive the greatest ameunt of snow and rainfall in the basin.During the'summer months ,these regions contribute significant amounts of snow and glacial mel t..The glaciers, .CoverIng-aDDu!:290'square miresTor··.aboutfi·ve-perceii!:··o~f·Elie tbtal drainage area above Gold Creek Station),act as reservoirs that-may produce a significant portion 0.£the water in the basin above Gold Creek during drought periods.In the record drought year of 1969 ,thepropor.tionof flow at Gold Creek contributed from upstream of the Denali and Maclaren gages was 53 percent. On average,·the same area contributes only 40 percent. ··_·E-v·en-·though--the·re--is-e-vidence··that--the-gla-c-ier-s--ha·ve---been-wasting -- ...._.._~---.~-since-L949-,--there-is ..lit-tle-da.ta-a:llailab-le-to-determine~wha.t-the impact of wasting has been on the recorded flow at Gold Creek or . what will occur in the future (R&M;1981 c and 1982a).Large glaciers,such as those in the Susitna Basin,take decades to attain equilibrium after a change in climate. For years of very low precipitation,runoff from the glaciers willbe.more·important ,and-theremaybesubstantialnet waste of ..-'gla c iers~L'--How.ever;:if .long~term:.mean.pr.e_cipitationrema ins approximately the same,it is likely that net waste of glaciers in one year will be replenished by excess snow in another. j .\ 851104 B-3-2 1 The Applicant has analyzed the mass balance of the glaciers over the 1981-1983 period (Harrison 1985)and refined the estimate of glacier wasting from 1949 to the present (Clarke 1985).These analyses are dicussed in Exhibit E,Chapter 2,Section 2.2. It is difficult to predict future trends.If the glaciers were to stop wasting due to,perhaps,a climate change,there could be hydrological changes throughout the basin.On the other hand, the wasting of the glaciers could easily continue over the life of the project.There is no way to judge whether wasting will continue into the future.Hence,no mechanism presently exists for analyzing what will occur during the life of the project.As a result,the recorded streamflow was not adjusted to account for glacier wasting. 3.1.3 -Floods (**) The most common causes of floods in the Susitna River Basin are snow melt or a~~ombination of snow melt and rainfall over a large area.This type of flood occurs between May and July,with the majority occurring in June.Floods attributable to heavy rains have occurred in August and September.These floods are augmented by snow melt from higher elevations and glacial runoff. Examples"of flood hydrographs can be seen in the daily discharges for 1964,1967,and 1970 for Cantwell,Watana,and Gold Creek (Figures B.3.l.3 through B.3.l.s).The years 1964,1967,and 1970 represent wet,average,and dry hydrological years on an annual flow basis;respectively.The daily flow at Watana has been approximated using a linear drainage area-flow relationship between Cantwell and Gold Creek.Figure B.3.l.3 shows the largest snow melt flood on record at Gold Creek.The 1967 spring flood hydrograph shown in Figure B.3.l.4 has a daily peak equal to the mean annual daily flood peak.In addition,the flood peak of 80,209 cfs is the fifth largest flood peak at Gold Creek on record.Figure B.3.l.s illustrates a low flow spring flood hydro gra ph. The maximum recorded instantaneous flood peaks for Maclaren, Denali,Cantwell,and Gold Creek,recorded by the USGS,are presented in Table B.3.l.l0.Annual peak flood frequency curves for these stations are illustrated in Figures B.3.l.6 through B.3.l-9. Based on the station record,estimates of the 100-year,1000-year and 10,000-year floods at Gold Creek have been made.Since the station records are only available for 34 years,estimates of the 95 percent one-sided upper confidence limit have been provided. 851104 B-3-3 Flood Return Period 100-Year 1,000-Year 10,000-Year Mean Estimate (cfs) 108,000 147,000 190,000 95 Percent One-Sided Upper Confidence Limit (cfs) 138,000 200,000 270,000 851104 The mean annual flood at Go:l.d Creek is estimated as the flood having a return period of 2.33 years (Chow 1964)or approximately 50,000 cfs.The mean annual floods at Watana and Devil Canyon would be approximately 45,000 cfs and 48,000 cfs,respectively. Probable maximum flood (EMF)studies were conducted for both the Watana and Devil Canyon damsites for use in the design of project spillways and related facilities (Acres 1982c).The EMF floods were determined by using the SSARR watershed model developed by the Portland District,U.S.Army Corps of Engineers (1975)and are based on Susitna Basin climatic data and hydrology.The probable maximum precipitation was derived from a maximization study of historical storms.The studies indicate that-'the PMF peak at theWatana-damsi-te is 326,000 cfs. 3.1.4 -Flow Variability (***) The variability of flow in a river system is important to all instream flow uses.To illustrate the :variability of flow in the Susitna River,monthly and annual flow duration curve~showing ------~the--pl:opoI'_t-ion~oc£··~t~ime~tha-l;_the--di_sch-arge-:equa-lg--or--.-exceeds-·-a given value were developed for three mainstem Susitna River gaging stations (Denali,Cantwell,and Go1d.Cr.E!ek).These curves,based on mean daily flows,are illustrated in Figure B.3.1.1O. The shape of the monthly and annual flow duration curves is similar for each of the stations and is indicative of flow from ._l:lS'~tl:l~!!.gII:l~~o!IJ~!Y~.!:_!!(!i~111~J~~f)-"__litr~~m flQ'N_j~}~_--lg_Wj,!L.~l1,~.· winter months,with little variation in flow and no unusual peaks.Groundwater contributionsa-re the primary ·source of the small but relatively constant winter flows.Flow begins to increase slightly in April as breakup approaches.Peak flows in May are an order of magnitude greater than in April.Flow in May also shows the greatest variation for any month,as low flows may continue into May before the high snow melt/breakup flows occur. June has the highest peaks ..and the highestmedian ..f1ow for the middlearid·uppei basiristati6ns.tbti!1llont::hs·6fJu:l.Y·and August have relatively flat flow duration curves.This situation is indicative of rivers with strong base flow characteristics,as is the case for Susitna,with its contributions from snow and B-3-4 1 851104 glacial melt during the summer.More variability of flow is evident in September and October as cooler weather becomes more prevalent accompanied by a decrease in glacial melt and,hence, discharge. The daily hydrographs for 1964,1967,and 1970,shown in Figures B.3.1.3 through B.3.1.5,illustrate the daily variability of the Susitna River at Gold Creek,Watana,and Cantwell.The years 1964,1967,and 1970 represent wet,average,and dry hydrological years on an annual flow basis,respectively. 3.1.5 -Flow Adjustments (**) Evaporation from the Watana and Devil Canyon reservoirs has been evaluated to determine its significance.Evaporation is influenced by air and water temperatures,wind,atmospheric pressure,and dissolved solids within the water.However,the evaluation of these factors'effects on evaporation is difficult because of their interdependence on each ,ather.Consequently, more simplified methods were preferred and have been utilized to estimate evaporation losses.For Watana,only Stage III was evaluated,since this would be the more critical case. The monthly evaporation estimates for the reservoirs are presented in Table B.3.1.11.The estimates indicate that evaporation losses will be less than or equal to additions due to precipitation on the reservoir surface.Therefore,a conservative approach was taken,with evaporation losses and precipitation gains neglected in the energy calculations. Leakage is not expected to result in significant flow losses. Seepage through the relict channel is estimated as less than one-half of one percent of the average flow and therefore has been neglected in the energy calculations to date. Minimum flow releases ~re required throughout the year to maintain downstream river stages.The most significant factor in determining the minimum flow value is the maintenance of downstream fisheries.After completion of Devil Canyon,flow releases from Watana will be regulated by system operation requirements.Because the tailwater of the Devil Canyon reservoir will extend upstream to the Watana tailrace,there will be no release requirements for streamflow maintenance of Watana for the Watana/Devil Canyon combined operating configuration. See Section 3.3 of this Exhibit for further discussion of the flow release requirements. Existing water rights in the Susitna basin were investigated to determine impacts on downstream flow requirements.Based on inventory information provided by the Alaska Department of B-3-5 Natural Resources,it was determined that existing water users will not be affected by the project.A listing of all water appropriations located within one mile of the Susitna River is provided in Table B.3.1.12. 3.2 Reservoir Operation Modeling (***) 3.2.1 -Reservoir Operation Models (***) Two computer models used to simulate the operation of the Susitna Project reservoirs are:the monthly reservoir operation program (Monthly RESOP);and the weekly reservoir operation program (Weekly RESOP).The monthly RESOP was originally developed for the Susitna feasibility study and subsequently updated.The weekly RESOP was developed using selected subroutines from the monthly RESOP.The objective of-the reservoir ope~ation study ~s to determine the operation which maximizes the Susitna Project benefits under the specified constraints and to provide estimated reservoir outflows and water levels for environmental impact ana.lyses. The time increment used for the simulation affects both the computational effort required and the accuracy of the results obtained.A weekly time step is used for flow regime studies because the results more precisely show the fluctuation of water surface elevation and reflect the critical conditions.Weekly simulations also yield more gradual changes in outflow discharges from week to week than monthly simulations.Both simulations ~yiera~-coinparaDre--es timatesorSusTEna-power-and-en~ergy production.The monthly program is used to determine the project capability for -the economic analyses while -the weekly simula tion is used to provide input to the environmental analyses. Either program simulates Susitna operation over 34 years of historical streamflow records (January 1950-December 1983).Key inputs to the models are the reservoir and powerplant --------------cha-racter-ist-ics,---power-demand--distri-but-ion-,~--and~-env-i-ronmen-t-a-l-- ---~--constraints-.--The~RESO-P-mode_ls--'-simu_la-te-the-reser-vo-i-r-storage-,-- power generation,turbine discharge,outlet works release,and spill,as a function of time. The resulting water levels,and releases from turbines,outlet works,and the spillway,are used for evaluation of environmental itnpacts OLflowstability,fij;hery _habi~at,flood fr:equency, temperature,stage fluctuation,and ice conditions in the river downstream.The _average energy _production_,__firmenergy production,and capacity of the project for various operation schemes are used by the electric generation expansion program in the economic evaluation of alternative expansion plans. -i .j 'J II 851104 B-3-6 851104 3.2.2 -Basic Concept and Algorithm of Reservoir Operation (***) Reservoir operation simulation is basically an accounting procedure which monitors the reservoir inflow,outflow,and storage over time.The storage at the end of each time step is equal to the initial storage plus inflow minus outflow within the time step.The time step is either a month or a week,depending on the program used.A key constraint on the simulation is the minimum instream flow requirement at Gold Creek which must be satisfied each time step.The minimum project release is the minimum flow requirement at Gold Creek minus the intervening area flow between the downstream project site and Gold Creek.A rule curve or operation guide governs the release for power,with the total powerhouse release restricted by the discharge required to meet the system power demand. The basic Susitna development scheme is as follows: 1.Watana Stage I is the initial project.At a normal maximum reservoir level of el.2,000 feet above mean sea level (ft,msl),and with 150 ft of drawdown,2.37 million acre-feet of active storage is provided.This is roughly 40 percent of the mean annual flow at the damsite,and affords some seasonal regulation.All Stage I units will be operational _in 1999. 2.Devil Canyon is Stage II.It will be constructed in a narrow canyon with a normal maximum reservoir level of el.1,455 ft,msl and only 50 ft.of drawdown.Hence, it mainly develops head,relying upon.Watana to regulate flows for power production.All Stage II units will be operational in 2005. 3.Stage III involves raising the Watana dam 180 feet to its ultimate height,with a normal maximum reservoir elevation of el.2,185 ft,msl and 120 feet of drawdown. The active storage will be 3".7 million acre-feet,about 64 percent of the mean annual flow.Commercial operation of the two new Stage III units will be in 2012. The reservoir operation methodology attemps to keep the Devil Canyon Reservoir close to its normal maximum operating level while using Watana's storage to provide the necessary seasonal regulation.Therefore,the modeling effort in both single and double reservoir operation simulation is focused on the Watana operation.The operation level constraints are summarized in Table B.3.2.l.Curves of area and volume versus elevation for both the Watana and Devil Canyon Reservoirs are shown on Figure B.3.2.I. B-3-7 (a)Watana Stage I (***) An initial operation is done for each time step to begin the simulation.This algorithm is explained in detail in Section B-3.2.7 of this Exhibit.After the initial operation,the energy generated is compared to the system energy demand in each time step.If the energy produced is greater than that which the system can use,the energy production is reduced.This is done by decreasing the discharge through the powerhouse. A minimum instream flow requirement isp~escr~bed at Gold Creek to ensure that the project will release flows for environmental purposes.The historical intervening flow between Watana and Gold Creek is assumed to be available to supplement the project releases to meet the minimum flow requirement.If the flow requirement is not met,more water is released through the powerhouse in order to meet the requirement.The instream flow requirement may cause more energy to be generated than the required amount.The powerhouse discharge must again be decreased.However, ....instead of reducing the total project outflow,discharge is diverted from the powerhouse to the out'let works.This cone valve release is called an environmental release since it is made only to meet the environmental requirement and is not used for power generation. The outlet works capacity atWatana I is 24,000 cfs,while .__._--~~t;.he--powerhouse-ca-pac-i-ty-is-about--14-;0 OO-·cis.··-Int;.he··event that a flood could not be passed through the powerhouse and outlet works,because ofe_ne..rgy ciemand and hydraulic capacity limitations,the reservoir is allowed to surcharge above the normal maximum water surface elevation.This surcharging is done to avoid the use of the spillway for floods less than the 50-year event !A maximtnn surcharge level ·of el.2,014 is permitted before the spillway 11 l IJ .1 ··--Tb-Y--watanasta:-ge--Ior-stage--rrrwt th DevilcanyOti-·_· Stage II (***) For simulation of double reservoir operation,the initial operation for each time step is the.s.ame as .that for the single reservoir.Devil Canyon operates as run-of-river as long as the :reservoir is f tl1l.The DeyilCatlyotl reservoir is-to be-refilled.if.the reservoir.is~n()i::full,and the fotal irif10w is greaterthariEhe release required 1:0 meel: the downstream flow requirement.After the initial operation,the total energy generated at Watana and Devil 851104 B-3-8 Canyon is compared to the system energy demand.If the energy produced is greater than that which the system can use,the energy produc tion is reduced.This is done by decreasing the discharge through the Watana powerhouse. The intervening flow between Devil Canyon and Gold Creek is - assumed to be available to supplement the project releases to meet the minimum flow requirements.If the flow requirement is not met,more water is released through the Devil Canyon powerhouse in order to meet the requirement and the Devil Canyon reservoir will draw down.If the increased release through the Devil Canyon powerplant will cause the total energy generation to be greater than the system demand,the release from the Watana powerplant is reduced. Continuous drawdown at Devil Canyon can occur in the summer of dry ,years when the system energy demand is.low and the downs tream flow req uirement is high.If the wa ter leve 1 at Devil Canyon reaches the minimum eleva tion,of 1,405 ft, Watana must then release water to satisfy the minimum flow requirement.If the release from Watana for the minimum flow requirement will generate more energy than the required amount,part of the release is diverted to the outlet works. The powerhouse hydraulic capacity 'is about l4,QOO cfs for both Watana Stage I and Devil Canyon,and about 22,000 cfs for Watana Stage III.The outlet works capacity at Devil Canyon is 42,000 cfs while the capacity at Watana is 24,000 ds in Stage land 30,000 ds in Stage III.In the event that a flood could not be passed through the powerhouse.and cone valves,because of energy demand and hydraulic capacity limitations,Watana is allowed to surcharge above its normal maximum.The maximum surcharge.level is el.2,014 ft for the Watana Stage I dam and el.2,193 for the Stage III dam. Since the capacity of the outlet works at Devil Canyon is large,and flood flows are attenuated at Watana before reaching Devil Canyon,a surcharge of only one'foot above the normal maximum of el.1,455 is allowed,and the spillway operates if the water surface exceeds el.1,456 ft. 3.2.3~Standard Weeks (***) A system of standard weeks,in which the dates of weeks in a year are the same every year,is used in the weekly simulation.In accordance with the water year,standard weeks start on October 1 and end on September 30 with seven days a week in normal weeks but with eight days for the last week in September.The last week in February also has eight days in a leap year.A standard week begins on Sunday and ends on Saturday. 851104 B-3-9 The weekly simulation is done on a calendar year basis"from January to December.In applying the standard weeks in the weekly simulation,the first week of a year starts on December 31 of the previous year and ends on January 6 of the current year. The standard week numbers and corresponding dates are listed in Table B.3.2.2. 3.2.4 -Demand Forecast (***) The reservoir operation models use the system'energy requirement at plant to define the expected demand.Since SHCA and composite electric demand forecasts are similar (Exhibit B,Chapter 5, Tables B.5.4.6 and B.5.4.17),reservoir operation studies were conducted using the SHCA forecast.The annual peak and net energy generation projections of the railbelt system based on the SHCA forecast are listed in Table B.3.2.3.The monthly energy requirements are obtained by applying the monthly distribution of annual requirement as shown in Table 'B.3.2.4. 3.2.5 -Existing Hydroelectric Plants (***) 'Tlieexist:irig Railbelt hydrcfplarits are 'lUodeled as a.cOll1bined plant in the simulation.These plants include Eklutna,Cooper Lake, and Bradley Lake.Eklutna and Cooper Lake are currently operating.Bradley Lake is assumed to go on-line in 1990.The monthly average energy generation of'the existing hydroplants is given in Table B.3.2.5. ~~Tb:e-'differE!n-C-Ef-Detweeff-tl'fe"tot:alsystern····e nergyrequ'iremenc·····atid the energy production of existing hydroplants is the residual requir.ement to be provided by either Susitna orthennal plants. In order to determine the energy requirement on a weekly basis, the monthly energy requirement and the ener,gy production of existing hydroplants are converted to a weekly energy.The weekly energies were estimated from the monthly energies so that the sum of the weekly energy within a month equals the monthly 3.2.6 -Release Constraints (***) An instream flow regime is a series of minimum and maximum discharges for maintaining fish habitat.The degree of fish protection provided varies with the flow regime.The maximum limits at Gold Creek are,in general,about 15,000 cfs in winter and 35 ,OO(jcfs in summer.With Susitna ..operati.ng,.the discharge will I1()te:xc:eeCi:thisma:ximUIil limit.·Th~:t;"~f():t:'~,:I1()lllaximumlinti.t on outflow discharge is set in the simulation. The following definitions are used in describing the flow constraints: .I 851104 B-3-10 Minimum instream flow requirement -The m~n~mum instream flow requirement is a minimum discharge level which must be maintained at the Gold Creek gaging station.The minimum release from the downstream damsite is the minimum instream flow requirement at Gold Creek minus the intervening flow between the damsite and Gold Creek. Minimum turbine discharge -In the monthly simulation,the m~n~mum turbine release is the discharge necessary to meet the firm energy specified in the input.In the weekly simulation,the minimum percentage of the expected turbine flows defined in the input will set the minimum turbine release. Maximum tMrbine flow -The maximum turbine discharge is the turbine hydraulic capacity or the discharge required to meet the system energy requirement,whichever is less. Maximum outlet works release -The outlet works will operate in two cases;(1)the maximum turbine flow is less than the release required to meet the minimum instream flow requirement,and (2)the reservoir level is higher than the normal maximum level.For case 1,the outlet works release only the amount required to satisfy the downstream requirement. For case 2,the outlet works discharge up to their maximum capacity to minimize surcharge above the normal maximum reservoir elevation. For Watana,the maximum outlet works discharge is limited to 24,000 cfs in both Stage I and Stage III,even though the Stage III capacity is 30,000 cfs.This is to ensure that inflows to Devil Canyon do not exceed the outiet works capacity there for floods with return periods of 50 years or less. Maximum daily fluctuation -Because of limitations on the accuracy of streamflow measurement,actual releases from the downstream project may vary up to plus or minus 10 percent of the weekly average flow for the week. 3.2.7 -Reservoir Operation (***) To simulate the operation of the Watana development,two approaches are used;a conventional rule curve,and an operating guide.The monthly operation program (Monthly RESOP)uses rule curve operation while the weekly operation program (Weekly RESOP) uses the operating guide.The rule curve operation approach can be thought of as "predictive"because it attempts to achieve a 851104 B-3-11 target end-of-period elevation based on the expected reservoir inflow during the period (i.e.,a monthly period).The historical record is used as a predictor of the inflow for the monthly period being simulated.The operating guide approach can be viewed as "nonpredictive"because its purpose is to achieve a specific discharge rate through the powerhouse based only upon the reservoir elevation at the beginning of the period.The operating guide is a family of rule curves,with each curve related to a powerhouse discharge rate. The rule curve approach is easy to apply for simulation of the operation,but is operationally difficult to achieve because reservoir inflows are difficult to accurately forecast.The operating guide approach is more difficult to model,but it is more straightforward operationally. The two approaches yield similar results in terms of overall power and energy production.The operating guide approach is used for input to analyses of reservoir temperature,river temperature,and downstream fisheries habitat,because the operating guides more closely simulate the expected project releases •The rule'curve approach is used for input to economic analyses because it is easier to apply and yields comparable power and energy production. The distinction between the rule curve and operating guide approaches applies only to Watana reservoir operation.In both cases,Devil Canyon operation is governed by a rule curve.The 'D-evilCanyono'p'eratingrule'is"~·t()=·ke=ep-t'h·e-:--re·s-ervoirasfull a's' possible throughout the simulation.Hence,the Devil Canyon rule curve is set equal to the normal maximum reservoir elevation (el.1455 ft,msl)each period (Figure B.3.2.2). (a)Rule Curve Operation (***) The monthly simulation is governed by two primary ......._constraints •..TheconstrainLonminimuIlLenergy..,production,is... a "target"value of firmenergy~.be generated.The ._.__. constraint on maximtnIl energy production is the rule curve or the system energy requirement,whichever results in less energy production.. The target value of annual firm energy is first input to the model.The corresponding monthly finn energy targets are "]:nencompuEed "oased on a specified 'distribution.The model ....!,H!jll~~J.a l ••!y ••1II.altE!..the:rE!qtl~'I'E!d ..pOWE!:rhg uSE!.·rE!!e.a se to meet the monthly firm energy target.The end-of-month reservo elevation is then computed based on the starting elevation, the powerhouse release,and inflow during the month.This end-of-month water surface elevation (WSEL)is then compared 1 .j j l 851104 B-3-12 to the rule-curve elevation (RCEL)for the month.If the WSEL is below the specified RCEL,no additional release is made.If the WSEL is above the specified RCEL,the water stored between these two elevations is released to generate secondary energy.The secondary energy generated may be limited by the system energy requirement. The simulation continues for each month of the simulation period until the annual firm energy is maximized.The annual firm energy is maximized when the reservoir elevation reaches the normal minimum reservoir elevation once during the simulation (in the critical period)without any shortfalls in firm energy production or in meeting the minimum instream flow requirement. (b)Rule Curve Development (***) The rule curve is developed by trial and error.Figure B.3.2.2 depicts example ru1~curves for Watana Stage I and Stage III.Two distinct periods,the draw down season and the filling season,are defined by the shape of the rule curve.The drawdown season extends from the beginning of October through the end of April.During these months,the average natural inflow to the reservoir is less than the reservoir outflow,and the reservoir level.decreases.The filling season extends from the beginning of May through the end of September.During these months,the average natural inflow to the reservoir exceeds the reservoir outflow,and the reservoir level increases.Hence,the general approach to developing the rule curve is as follows:at the end of the filling season,the reservoir should be full,and at the end of the drawdown season,the reservoir should be at the minimum rule curve elevation. The higher the minimum rule curve elevation,the greater the .firm energy production,because more water would be available during a drought,resulting in higher energy output.Alternatively,the lower the minimum rule curve elevation,the greater the average energy production, because there is more storage available for regulation on an average annual basis.Different minimum rule curve elevations will yield different values of firm energy and total energy production.The acceptable minimum rule curve elevation is selected based on an operationwhich provides a reasonable trade-off between firm and average energy production. The maximum rule curve elevation is set equal to the normal maximum reservoir elevation at the end of the filling season. 851104 B-3-13 Once the minimum and maximum rule curve elevations have been established,the rest of the rule curve elevations are determined by trial and error.The objectives of this procedure are to establish the monthly ReELs that distribute the hydroelectric energy such that the costs of thermal energy generation during the drawdown and filling seasons are minimized.In this approach,equal quantities of thermal energy are generated during each month within each season.The thermal energy generation required in each season is thus "levelized"as depicted in Figure B.3.2.3. (c)Operating Guide (***) The operating guide comprises three main elements,as described below. Expected Powerhouse Discharge -This is a set of weekly powerhouse discharges (cfs)which will produce the desired distribution of energy production over a year. Increasing Curves -This is a set of curves defining powerhouse discharge rates as a function of Watana reservoir elevation and time of yea~.The curves,which are expressed in terms .of a percentage of the expected discharge for each week,are used to decide .whether or not the present rate of discharge should be increased (FigureB.3 .2.4). -------..c--~---Dec-I'eas-in-g--Gu't'ves~---Thcis~is-a~-seconds et--o-f-c·ur-ves,.similaI' to those descri~ed above,which are used to decide whether or not the present rate of discharge should be decreased (Figure B.3.2.4). The expected powerhouse discharges represent the average annual flow volume,distributed through the year to minimize the costs of generating the thermal energy component of the ...~y~_~~!!!:.....e_I!~~gy._._~_~ql!.i:..~~~l!t .!......_!:I!-~l!.i.l;3 __~p._p.!:.Q~<;h.,_~q~!__. quantities of thermal energy are produced during each week ·o£-thedrawdown season·ati-d also-each week of-thefITIiiig season. The operating guide can be viewed as a "family"of rule curves.The guide is applied by comparing the current discharge rate to that prescribed by the guide based on the time of year and the water surface elevation.If the water surface elevation at the begiritlingJ)ftJ:ie~week is higher than the increasing curv-eofthe next higher rate ,the discharge should be increased to the next higher rate in this week.If the water surface elevation is lower than the I ,] 851104 B-3-14 decreasing curve of the next lower rate,the rate.should be decreased to the next lower rate in this week. (d)Operating Guide Development (***) The operating guide attempts to do the following: o Keep the powerhouse discharge close to the expected (100 percent)discharge; o Maximize total energy production; o Keep discharge rates nearly constant for at least several weeks at a time;and o Minimize cone valve releases (i.e.,meet environmental flow constrants with powerhouse release).. The expected discharges are determined by first performing a monthly rule curve simulation.The weekly expected . discharges are estimated from the monthly discharges through the powerhouse.The resulting weekly expected discharges will levelize the thermal energy requirement in the draw down and filling seasons.Under average flow conditions,it would be optimal to always release at 100 percent of the weekly expected discharge.However,due to natural variations in reservoir inflow,the release rates must increase and decrease accordingly to optimize the power and ener~y production. The development of the operating guide curves is an iterative process.The lowest decreasing curve (63%)is selected by examining the most critical drought period. Sixty-three percent was judged to be the highest percent discharge that would enable the project to satisfy the instream flow and minimum energy requirements through the most critical drought.The highest increasing curve (140%) is selected by examining the most extreme flood period.The rate should be high enough to minimize spills when streamflow is above average.The intermediate curves are adjusted in order to maintain adequate storage during the drought,minimize spills,and to keep the discharge rate fairly constant. The"increasing"curve rates which have been used are 80, 100 120 and 140 percent of expected discharge;the "decreasing"curve rates are 120,100,80,and 63 percent. If the reservoir is operating at 100 percent,only the 120 percent "increasing"and the 80 percent "decreasing"curves are checked.This restricts the rate of change of discharge 851104 B-3-l5 in any iteration to the difference in the rates assigned to the curves.If the water surface elevation is between these curves,such as Point A in Figure B.3.2.4,the discharge rate will stay at 100%.If the water surface elevation is above 120 percent increasing curve (Point B,)the discharge will increase to 120 percent.If the water surface elevation is below the 80 percent decreasing curve (Point C),the discharge will decrease to 80 percent. 3.2.8 -Special Considerations for Double Reservoir Operation (***) The previous discussion has focused on the operation of the Watana Reservoir. When both Watana and the Devil Canyon are operating,special considerations come into play..These are: o Ensuring that Watana generates enough energy each period to permit peaking operation;and o Ertstirirtgthat Devil Canyort cone valve releases are such that low-temperature releases are minimized. The downstream flow requirement is high from May to October but the energy demand is low in this period.Releases to meet the downstream requirement through the powerplants at Watana and Devil Canyon could conceivably generate more energy than the systemrequires~The·reservoi rcould o·p-er·crte··i:n·such away··that .... Devil Canyon draws down to meet the,downstream requirement and generates most of the system requirement.Only.a small part of the requirement which is not satisfied by Devil Canyon would then be satisfied by theWatana powerplant.In.prillciple,Watana is operated for peak generation and Devil Canyon for base-load generation.If Watana energy generation is too small,it cannot satisfy the daily fluctuation of power demand.In order to ......permit_peaking_at..Wa.tana,.·a.minimum.Watana.ener.gy .generation..is __J!ssi~ed in the inQut.For any_given time period,Watana is_ required to generate at least 30 percent of the total Susitna output. On the other hand,if Watana were to generate too much energy in summer,then it could potentially meet the entire system demand without generating at Devil Canyon.Consequently,Watana would generate all of the.system energy r.equirernent ,with Devil Canyon :;(it~:;~ying thlado'W'l1~treatn f1 ow·rl?qt.1iretnl?l1t)YJ:'.laJeas ingw(iter through its outlet works.Because the outlet works intakes are at a lower elevation than the powerhouse intakes,a release through them during the summer period would be at a lower j ] i1 'j 'j ,J I J ] 851104 B-3-l6 ,1 temperature.As a result,the temperature in the downstream channel would be lowered. In order to avoid low streamflow temperature in the downstream channel,a minimum Devil Canyon generation is also assigned. When the total project release would generate more energy than the system requirement,the program will attempt to meet the minnnum target firm energy by generating at Devil Canyon.If Devil Canyon does not satisfy total energy requirement,the rest will be met by Watana. 3.2.9 -Reservoir Operation Computer Programs (***) (a)Monthly RESOP Program (***) The monthly reservoir operation program uses ~he rule curve' approach to simulate the operation of the Susitna reservoirs on a monthly basis.The snnulation is done on a water year basis.Water year n begins on October 1 of year n-1,and extends through September 30 of year n.A summary of the program input requirements and output data follows. Input Data.The input data are organized as follows: o Titles,number of reservoirs,and snnulation period; o Historical streamflow at damsites; o Reservoir area-volume curves and tai1water rating curves; o Turbine characteristics curves; o Reservoir minnnum,and maxnnum,and rule curve elevations; o Historical streamflow at Gold Creek and minnnum instream flow requirement;and o Annual energy demand,distribution of monthly demand, energy production of existinghydroplants,and minimum energy to be generated by each project. Output.The output data is organ~zed into three parts: o Echo of the input data; o Annual snnulation results;and o Summary results. 851104 B-3-17 /. The input data echoed includes the streamflow record, reservoir characteristics,tailwater rating,turbine characteristics,reservoir control elevations,and rule curve elevations for each reservoir,streamflow record at the downstream station (Gold Creek),minimum instream flow requirement at the downstream station,monthly energy demand,energy production of existing hydroelectric powerplants,distribution of monthly demands in a year,and monthly firm energy. The second part of the output is the annual simulation results.For each year,simulation results for each reservoir and a summary of energy production and powerplant capability are printed.Reservoir inflow,turbine discharge,spills,end-of-month storage,end-of-month elevation,tailwater elevation,net head,plant efficiency and capability,and total energy are printed.Totals and averages are also print·ed. The third part of the'output is the summary results.Tables of reservoir inflow,turbine discharge,spill,net head, water surface elevation,energy production,intervening flow,and.flows at the downstream station with and without the project are provided.Each table gives the monthly data in chronological order'over the total simulation period.A summary ta~le of plant capability and energy production is also provided.Average and minimum capability,and minimum energy production for each plant,are listed. (b)Weekly RESOP Program (***) The weekly reservoir operation program uses the operating guide approach to simulate the operation of the Susitna reservoirs on a weekly basis.The simulation is done on a calendar year basis (January 1 through December 31).A summary of the program input requir~ments and output data Input Data.The input data are organized as follows: o Titles,number of reservoirs,simulation period,and output options; 0-Historical streamflow at damsitc:!.§;.... o Weeklyor1ll0litlilyexpected C100%)~discharge alid increasing and decreasing curves of the operating guide; !] ,~] j I 1 J 851104 B-3-18 :) 851104 o Reservoir area-volume curves and tailwater rating curves; o Turbine characteristic curves; o Maximum and minimum reservoir elevations; o Historical streamflow at Gold Creek and minimum instream flow requirement;and o Annual energy demand,distribution of weekly demand, energy production of existing hydroplants,and minimum energy to be generated by each project. Output.The output data is organized into thr~e part~: o Standard output,similar t~that provided by the monthly program; o Flow duration and frequency output;and o Output for Reservoir temperature studies. Standard Output The standard output is much the same as that described for the monthly program.The major difference is that the results are reported on a weekly,rather than monthly, basis. Output for Duration and Frequency,Curves This output is designed for input to the environmental studies.Tables of flow duration and frequency are provided for:with-project flow at Gold Creek,reservoir inflow, turbine discharge,excess release and water surface elevation for each reservoir,and intervening flows between reservoirs and between the downstream reservoir and Gold Creek.For each parameter there are two tables;one provides simula tion resul ts in chronological order by week, and the other is in the form of duration relations, expressing the percent of time a given flow is equaled or exceeded.Water surface elevation',expressed as the probability of occurrence within assigned ranges,is also provided. B-3-19 Output for Reservoir Temperature Studies This output provides weekly turbine discharge,outlet works discharge,spill,and wa ter surface elevation,in chronological order for a specified period of years. 3.3 -Operational Flow Regime Selection (***) 3.3.1 -Reservoir Storage Characteristics (***) Storage characteristics of the Watana reservoir will vary, depending on whether Stage lor Stage III is operating.Devil Can.yon.storage characteristics are unchanged throughout its operation period.Area and voltnne versus.elevation curves for both the Watana and Devil Canyon reservoirs are shown on Figure B.3.2.1. Watana -Stage I The Watana Stage I reservoir will have a normalr:operating level at el.2,000 ft,msl.At this elevation,the reservoir will be approximately 39 miles long,with a maximtnn width on the order of three miles.The total voltnne and surface area at the normal operating level will be 4.25 million acre-feet and 19,900 acres, respectively.The minimtnn operating leveL is at el.1,850 ft, msl,resulting in a 150~ft maximum drawdown.The active storage is 2.37 million acre-feet. The Devil Canyon reservoir will have a normal operating level at e1.1,455 ft,msl.At this levei,the reservoir will be approximately 26 miles long,with a maximum width of approximateIy one-half rolfe.-The total·voltnne and surface area at the normal operating level will bel.l million acre-feet and 7,800 acres,respectively.The minimtnn operating level is at e1.l,405ft,msl,resulting in a 50 ft.maximtnn drawdown.The--,-._.._-_.....__...,~-----.-,.,-'..'.,·····--------·------_····---"act"ive-----··s·'tor·a-g~-is----·-'35-(j~.(io"(j··-··'-afr~e-=·fe-et-·-:···,·'0 -------.--.~-----------....--.----.--"~--.-.--.-...,.'.--.,.._.-.-,'."0'_"-- Watana -Stage III The Watana Stage III reservoir will have a normal'operating level at el.2,185 ft,msl.At this eleva tion,the reservoir will be approximately 48 miles long,with a maximum width on the order of five miles ..Thetotalvoltnneand surface area at the normal operating level will be 9.5 millionacre....feet:gJ.'l.4 38,000 acres, respectively.TheminimUID operating levetts atel ~2 ,065 ft, msl,resulting in a l20-ft maximtnn drawdown.The active storage is 3.7 million acre-feet. j 851104 B-3-20 \J 851104 I 3.3.2 -Reservoir Operation (***) The Applicant's goal is to operate the project to maX1m1ze power and energy benefits within environmental and operational constraints.Details of the reservoir operation are provided in Section 3.2 of this Exhibit. 3.3.3 -Development and Comparison of Alternative Flow Regimes (***) Alternative flow regimes were compared,based on their performance in meeting economic and environmental objectives. The economic objective is to minimize the cost of producing energy to meet projected Railbelt system energy demands.The environmental objective is to provide sufficient -habitat to ~intain naturally producing populations,so called no-net-loss of habitat.The environmental objective ma~be achieved by providing the river flow.s necessary ,to meet l ~he objective 'or by ,-a combination of flows and other compensation such as rearing facilities.Environmentar flow requirements affect Susitna energy product,ion and Il}ay require the construction and operation of other generating facilities to meet Railbelt system energy demand.Therefore,the costs resulting from the implementation of environmental ",flow requirements are included in the economic evaluation of the costs to meet Railbelt energy demand.The economic and environmental objectives are combined in a single evaluation criteria which is the total cost of providing the Railbelt energy demand,including the costs of the Susitna Hydroelectric P~oject,other generation facilities and the costs of mitigation measures. A complete description of each of the alternative flow reg1mes and of the selection process undertaken to develop the preferred flow regime is set out in Exhibit E,Chapter 2,Section 3.Based upon this combined economic and environmental selection process set out in that section,flow regime Cases E-VI and E-IV are judged to be the superior flow cases.Case E-VI is selected as the preferred case because of superior energy benefits.Table B.3.3.1 shows the weekly minimum flow requirements at Gold Creek for Case E-VI.Table B.3.3.2 shows the relative ranking of the al terna tive flow regimes based upon bo th economic and environmental costs. B-3-21 J :] --J } J 'J o ..J ] oj 0 1 ] J 1 .1 .J ] J o ] J 4-POWER AND ENERGY PRODUCTION (***) 4.1 -Plant and System Operation Requirements (**) The main function of system planning and operation control is the allocation of generating plant on a short-term operational basis so that the total syste~demand is met by the available generation at minimum cost consistent with the security of supply.The objectives are generally the same for long-term planning or short-term operation load dispatching,but with important differences in the latter case. In the short-term case,the actual state of the system dictates system reliability requirements,overriding economic considerations in load dispatching.An important factor arising from economic and reliability considerations in the system planning and operation is the provision of stationary reserve and spinning reserve capacity.Figure B.4.l.l shows the daily variation in demand for the Railbelt system during typical December (winter)and August (summer)weekdays.The variation in monthly peak demands as.estimated for the year 1983 is shown on Figure B.4.1.2. 4.1.1 -System Reliability Criteria (**L Reliability criteria for electric power system operation can be divided into those criteria which apply tocgeneration capacity requirements and those which apply to transmission adequacy assessment. The following basic reliability standards and criteria have been adopted for planning the Susitna project. (a)Installed Generating Capacity (**) Sufficient generating capacity is installed in the system to ensure that the probability of occurrence of load exceeding the available generating capacity shall not be greater than one day in ten years (Loss-of-Ioad probability (LOLP)of 0.1).The evaluation of generation reserve by probability techniques has been used for many years by utilities and the traditionally adopted value of LOLP has been about one day in ten years (Sebasta 1978,IEEE 1982).Many utilities and reliability councils in the lower-48 states continue to employ such a criteria (IEEE 1977). ·Economic evaluation of expansion plans across a range of LOLP levels from one day in ten years (0.1)to three days in ten years (0.33)were analyzed.These results indicated that the expansion plans and associated system costs of the With-and Without-Susitna plans are not significantly affected within the LOLP range studied.In addition,at least one major utility has expressed the aim of achieving 851104 B-4-l an LOLP of one day in ten years (Stahr,1983). for the present level of study,an LOLP of one years has been adopted. There·fore, day -in ten The above generation reliability criteria was used as an input to the generation planning model described in Section 5.3 of this Exhibit.This generation planning model was used to evaluate generation expansion with and without the Susitna project as presented in Exhibit D. (b)Transmission System Capability (**) Thehigh...,voltage transmission system should be operable at all load levels to meet the following unscheduled single or double contingencies without instability,cascading or interruption of load: o The single contingency situation is the loss of any single generating unit,transmission line, transformer,or bus (in addition to normal scheduled or maintenance outages)without exceeding the applicable emergency rating of any facility;and o.The double contingency situation is the subsequent outage of any remaining equipment,except for line if outage of the line will resul t in the loss of the load center served,'without exceeding the short time emergency rating of any facility. In the sIngle contingencysItuatIoJ:l.,the power system must be capable of readjustment so that all equipment would be loaded within normal ratings and,in the double contingency situation,within emergency ratings for the probable duration of the outage. Duri~g any contingency: ---.---------------o--Suf-ficient-'·reactive--power--(-MVAR-}--capac±tywith --------------._---------adeq.ua-te-con-tr.o.ls-i-s-inst-a-l-l-ed-t-o--ma-in-t-a-in-ae-cept-ab-l-e-- transmission voltage profiles. o The stability of the power system is maintained without loss of load or generation during and after a three-phase fault,cleared in normal time,at the most critical location. -.Havingthetransmission':':-line s:"'itl.patallel,-:instead 0 fon e line only,improves greatly the reliability of the trans- mission system.Besides removing the necessity of hot line maintenance,the frequency of failure of the transmission system will be lowered by a factor of about 15. 851104 B-4-2 The transmission system performance was examined by performing load flow and transient stability studies.Load flow studies examined the system under normal operating conditions with all-elements in service,then removal of one line segment which verified adequate system performance under single contingency.Double contingency operation was verified by further removal of a second element (not including a second line).The loss of two parallel line circuits would result in loss of the load center served and was not considered in double contingency studies. The following criteria were used for the load flow studies: 1.For energization while the system is in normal status: a.Voltage at the sending end should not be reduced below .90 per unit. b.Initial voltage at the receiving end should not exceed 1.10 per unit. c.Following the switching of transformers and VAR control devices onto the system,the voltage at the receiving end should not exceed 1.05 per unit. 2.In case of normal status or single contingency and peak load: a.The voltages at all buses tapped for loading shall stay between 0.95 and 1.05 per unit. b.The voltage/load angle between the Susitna generators and any point of the system should not exceed 45 degrees. 3.In case of double contingency and peak load: a.The voltages at all buses tapped for loading shall stay between 0.90 and 1.10. b.The voltage/load angle between the Susitna generators and any point of the system should not exceed 55 degrees.The transmission system configuration was tested for energization (no load),and for peak load flow conditions.The load flows were prepared for normal transmission system conditions as well as selected contingency conditions.In addition to the load flow studies,dynamic stability studies were also prepared (Acres 1982f). 851104 B-4-3 cc) Figures B.4.1.3,B.4.1.4,and B.4.1.5 are one-line diagrams showing system performance for the approximate peak loadings in years 1999,2005,and 2025 under a critical double contingency condition.This condition assumes that one of the Gold Creek-Willow lines is out of service and that there is an additional loss of one of the Willow-Knik Arm lines. The critical parameters of the above cases are shown in Table B.4.l.1.As can be seen from the table,the system performs within the criteria established above. The loss of two circuits on the same right-of-way has a low level of probability if the spacing between the two circuits are set far apart to-minimize this potential problem.Part of the generation reserve capacity will be in the form of spinning reserve.As determined·in the generation planning studies,this spinning reserve will be from the next most economical increment of capacity over those units required to meet load considering the system as a whole.In addition to spinning,reserve,standby reserve can be maintained by the utilities in individual load centers using less economical units.The cost of this spinning and standby reserve has been included in the economic analyses presented in Exhibit D,Chapter.2. Operational reliability criteria thus fall into four main categories: o LOLP of 0.1,or one day in ten years,is maintained for the recommended plan of operation; ,J "'J /' o The single and double contingency requirements are maintained for any of_~~~,~'?E_~J)J:_()~~E!_E!()t:1_t._~ge~in thepTanF-oEErariSDils-s[on sys tem; 851104 o System stability and voltage regulation are assured from the electrical system studies.The spinning reserve capacity with six units at Watana and four units at Devil Canyon will meet load frequency control criteria;and o The loss of all Susitna transmission lines on a single right""of'""wayhasa-lCiw'lefvEH -of-'prooability.Ill.the event of the loss of all lines serving a load center, standby reserve in the affected load center can be brought on line to meet critical loads. B-4-4 ] 1 I 4.1.2 -Economic Dispatch of Units (*) A Susitna Area Control Center will be located at Watana to control both the Watana and the Devil Qanyon power plants.The control center will be linked through the supervisory system to a Central Dispatch Control Center near Anchorage. Operation will be semi-automatic with generation instruction inputs from the Central Dispatch Center,but with direct control of the Susitna system at the Susitna Area Control Center for testing/commissioning or during emergencies.The control system will be designed to perform the following functions at both the Watana and Devil Canyon power plants: o Start/stop and loading of units by operator; o Load-frequency control of units; o Reservoir/water flow control; o Continuous monitoring and data logging; o Alarm annunciation;and o Man-machine communication through visual display units (VDU),and console. In addition,the computer system will be capable of retrieval of technical data,design criteria,equipment characteristics and operating limitations,schematic diagrams,and operating/maintenance records of the units. The Susitna Area Control Center will be capable of completely independent control of the Central Dispatch Center in case of system emergencies.Similarly,it will be possible to operate the Susitna units in an emergency situation from the Central Dispatch Center,although this would be an unlikely operation considering the size,complexity,and impact of the Susitna generating plants on the system. The Central Dispatch Control Engineer decides which generating units should be operated at any given time.Decisions are made on the basis of known information,including an "order-of-merit" schedule,short-term demand forecasts,limits of operation of units,and unit maintenance schedules. (a)Order-of-Merit Schedule (0) In order to decide which generating unit should run to meet the system demand in the most economic manner,the Control 851104 B-4-5 Engineer is provided with information of the running cost of each unit in the form of an "order-of-merit"schedule.The schedule gives the capacity and fuel costs for thermal units and reservoir regulation limits for hydro plants. (b)Optimum Load Dispatching (0) One of the most important functions of the Control Center is the accurate forecasting of the load demands in the various areas of the system. Based on the anticipated demand,basic power transfers between areas,and art allowance for reserve,the planned generating capacity to be used is determined by taking into consideration the reservoir regulation plans of the hydro plants.The type and size of the units should also be taken into consideration for effective load dispatching. In a hydro-dominated power system (such as the Railbelt system would be if Susitna is develo.ped),the hydro uni t will take up a much grea~er part of base load operation than in a thermal-dominated power system.The planned hydro units at Watana typicany are wen-suited to load following and frequency regulation of~the system and providing spinning reserve.Greater flexibility of operation was a significant:'factor in the selection of six units pf 170 MW capacity at Watana,rather than fewer,larger-size units. Opera.ting Limits of J]p.its!'C~)" There are strict constraints on the minimum load and the loading rates of machines;to dispatch load to these machines requires a systemwide dispatch program taking these constraints irtto consideration.Iii genera.l ,hyd ro units have excellent start-up and load following characteristics; thermal units have good part-loading chara.cteristics. 'J ] "I } [/ 851104 (1)Hydro Units (*) o Reservoir regulation constraints resulting in not-to-exceed maximum and minimum reservoir levels, daily or seasonally. o Part loading of units is undesirable in the zone of rough turbine operation {typically from"above no-load-speed to 50 percent load)due to vibrations arising from hydraulic surges. B-4-6 I.. (2)Steam Units (*) o Loading rates are slow (10 percent per minute). The units may not be able to meet a sudden steep rate of rise of load demand. o The units have a minimum econom~c shutdown period of about twenty-four hours. The total cost of using conventional units includes banking, raising pressure,and part-load operations prior to maximum economic operation. (3)Gas Turbines (*) o Eight to ten minutes are required for normal start up from cold. o Emergency start-up times are on the order of five to seven minutes. (d)Optimum Maintenance Program (0) An important part of operational planning which can have a significant effect on operating costs is maintenance programming.The program specifies the times of year and the sequence in which plants are released for maintenance. 4.1.3 -Unit Operation Reliability Criteria (0) During the operational load dispatching conditions of the power system,the reliability criteria often override economic considerations in scheduling of various units in the system.Also important in considering operational reliability are system response,load-frequency control,and spinning reserve capabilities. (a)Power System Analyses (0) Load-frequency response studies determine the dynamic stability of the system due to the sudden forced outage of the largest unit (or generation block)in the system.If the generation and load are not balanced,and,if the pick-up rate of new generation is not adequate,loss of load will eventually result from under-voltage and under- frequency relay operation,or load-shedding.The aim of a well-designed high security system is to avoid load-shedding by maintaining frequency and voltage within the specified statutory limits. 851104 B-4-7 (b)System Response and Load-Frequency Control (*) To meet the frequency requirements,it is necessary that the effective capacity of generating plant supplying the system at any given instant be in excess of the load demand.The capacity of the largest thermal unit in the system has been taken as a design criterion for spinning reserve to maintain system frequency within acceptable limits in the event of the instantaneous loss of,the largest unit. In the system expansion studies,thermal units are run part-loaded to provide sources of spinningxeserve. Ideally,it would be advantageous to provide spinning reserve with the hydroelectric generation as well,in order to spread spinning reserves evenly throughout the system. The quickest response in system generation could come from the hydro units.The large hydro units at Watana and Devil Canyon can respond in the turbining mode within 30 seconds. (c)Protective Relaying Systems and Devices (0) The primary protective relaying systems provided for the generators and tr~nsmission system of the Susitna project are designed to disconnect the faul ty equipment.from ..the system in the fastest possible time.Independent protective systems are installed to the extent-necessary to provide a fast-clearing backup for the-primary protective syste~so as to limit equipment damage,limit the shock to the system, .allg.l3.pe.edres.toration..of.·..•.seryice._.The relay.ing.-sys.temsare ".- designed so as not to restrict the normal or necessary network transfer capabilities of the power system. 4.1.4 -Dispatch Control Centers (*) The operation of the Watana and Devil Canyon powerplants in relation to the Central Dispatch Center can be consi~ered to be the second tier of a three-tier control structure as follows: _...._.~_..__._.._...._---...--_._~~~·~--o·-Ce-ntra-t-Di-spatcn--COrft-ro t-Cerft e r-(-345~RV-netwo ff)--iiea r'"._..._..._....._... Anchorage:manages the main system energy transfers, advises system configuration ,and checks overall security. o Area Control Center (Generation connected to 345-kV sy.stem;-for-example,·Watana and Devil Canyon):.deals with the loadin~of~enerators connected directlY to the 345-kV -network,switchingandsafetY·precaut{ons 'of local ') ,1 () J 1 1 I 851104 B-4-8 .,J J I I I systems,and checks security of interconnections to main system. o District or Load Centers (138-kV and lower voltage networks):manages generation and.distribution at lower voltage levels. For the Anchorage and Fairbanks areas,the district center functions are incorporated into their respective area control centers. Each generating unit at Watana and Devil Canyon is started, loaded and operated,and shut down from the Area Control Center at Watanaaccording to the loading demands from the Central Dispatch Control Center.Due consideration is given to: o Watana Reservoir regulation criteria; o Devil Canyon Reservoir regulation criteria; o Turbine loading and de-loading rates; o Part-loading and maximum loading characteristics of turbines and generators; o Hydraulic -transient characteristics of waterways and turbines; o Load-frequency control of demands of the system;and o Voltage regulation requirements of the system. The Watana Area Control Center is equipped with ~computer-aided control system to efficiently carry out these functions.The computer-aided control system allows a minimum of highly trained and skilled operators to perform the control and supervision of Watana and Devil Canyon plants from a single control room.The data information and retrieval system will permit performance and alarm monitoring of each unit individually,as well as the plant/reservoir and project operation as a whole. 4.2 -Power and Energy Production (***) The Watana-Stage I development will operate as a base load project until the Devil Canyon Stage II development enters operation.Under Stage II operation,the Devil Canyon development will operate on base load and the Watana-Stage I development will operate on peak load and as reserve.The power and energy output of both facilities are increased when Watana-Stage III comes on-line. 851104 B-4-9 The operation simulation of the reservoirs and the power facilities at the two developments is carried out on a monthly basis to assess the dependable capacity and energy potential of the schemes.An optimum reservoir operation pattern was established by an iterative process to minimize net system operating costs while maximizing firm and average annual energy production,as discussed in Section 3.2 of this Exhibit. 4.2.1 -Operating Capability of Susitna Units (**) The operating capability of the Susitna units are summarized in Table B.4.2.1 and are based on the three stages of project development as follows:First,construction and operation of a facility with four turbine/generators at the Watana site with a dam crest elevation of 2,025 feet (Stage 1);second,completion and -operation of the Devil Canyon facility with four turbine/generators at the originally-proposed dam crest elevation of 1,463 feet (Stage II);and third,construction of the dam crest at the Watana facility to the 2,205-foot level (Stage III) including the addi tion of two turbine/generato.rs,for a total of six units,as proposed in the License Application (APA 1983). (a)Watana (**) The Watana powerhouse will have prov~s~ons for six generating units.Four units will be installed during Stage I construction and the remaining two units will be installed during Stage III construction.Both sets of units will have a capability of 170 MW when operating at res~:ry<?i.J:'_E:!~~y~l:!on_~,J1Q f_~~~•ThX~_:r_f?_~~.!'_voi,Le I eyg t ion corresponds to the average of the minimum December and January elevations expected in Stage III,and define's the unit capacity in relation to the occurrence of the peak system demand.During Stage I,the average of the minimum December-January reservoir--levels is at elevation 1,915 feet.The power output 'of each unit during this peak load period with this reservoir elevation is approximately 90 MW. -...------.-----.-----_·-·-·-·Th-e--f.ou];'---Wa-t_ana-S-t_age·-I~t_ur-bi_nes·-h-ave-been-se-l-ec:t;-ed--to-- operate within the expected reservoir elevation range of the initial Watana dam and the raised Watana dam (Stage III). These units will operate under net heads ranging from a minimum of 384 feet in Stage I to a maximum of 719 feet in Stage III operation;no modification is necessa.ry to the units__f;o peI'l1l,it Stage III operation. TheusUalmaxinitirii rangeofi5perafiori~of a Francis t.urbine is from approximately 65 percent of its design head (the head at which optimum efficiency is obtained)to approximately 125 percent of its design head.Using these 1 1 J ,J ,j 851104 B-4-10 j criteria,the design head for the Stage I turbines is established at 590 feet in order to permit these units to operate with suitable efficiencies with the reservoir raised in Stage III.The two turbines which are installed in Stage III will have their design head at 680 feet to have their peak efficiency within the narrower range of heads which will prevail in Stage III. The generating unit output versus net head relationship for the Watana Stage I and III units is shown on Figure B.4.2.1. (b)Devil Canyon (**) The Devil Canyon powerhouse will have four generating units each with a capability of 150 MW at the minimum reservoir level (el.1,405)and a corresponding net head .of 545 feet on the station.The generating unit output versus net head relationship for the Devil Canyon unit is shown in Figure B.4.2.2. 4.2.2 -Tailwater Rating Curves (0) The tailwater rating curves for the Watana and Devil Canyon developments are shown on Figure B.4.2.3. 4.2.3 -Average Energy Generation (***) Based on the hydrology,reservoir operation,and flow regime E-VI described above in Section 3,average energy generation from the Susitna project has been determined. Table B.4.2.2 provides the estimated average annual energy production from the Watana Stage I development,from Watana Stage I operating with Devil Canyon Stage II,and from Watana Stage III operating with Devil Canyon Stage II.When Watana is raised (Stage III),the additional storage available for flow regulation at Watana increases the energy production of both Watana and Devil Canyon.Also,two additional units are installed in the Watana powerhouse to take advantage of the added head and flow regulation. 4.2.4 -Firm Energy Generation (***) The firm or reliable energy generation from the Susitna project is taken as the energy generated with a 90 percent probability of exceedance,based upon 34 years of water records.Therefore the energy generation of the Susitna Project will be greater than or equal to the firm energy 90 percent of the time.Table B.4.2.2 851104 B-4-11 shows the estimated firm annual energy production from the three Susitna stages. 4.2.5 -Dependable Capacity (***) The dependable capacity of a hydroelectric project is defined as the capacity which,for a specified time interval and period,can be relied upon to carry system load,provide assured reserve and meet firm power obligations,taking into account unit operating variables,hydrologic conditions,and seasonal or other charact- eristics of the load to be supplied. Section 4.2.1 of this Exhibit describes the-operating characteristics of the units to be installed at Watana and Devil Canyon based on the hydrologic conditions discussed in Section 3.1,the reservoir operation studies presented in-Section 3.2, and flow regime E-VI as discussed in Section 3.3.Based on those operation studies,the dependable capacity of the Susitna project has been determined. The Watana development will operate as a base load project until the Devil Canyon development begins operation,at which time the Devil Canyon development wIll operate ·oU·base and the Watana development will operate on peak and reserve.The dependable capacity of the three Susitna stages was estimated by inputting to OGP the capability.(MW)of each stage,based on reservoir operation studies,and tabulating the capacity dispatched at the time of peak load from the OGP output. --_···--~Fi gu re-B~~4:2~-4 ·s6.ows~Eh-eaeperidable--capacrty~of-Watana and De vi 1 Canyon in relation to the peak load forecast for the E-VI flow regime.As can be seen from Figure B.4.2.4,in Stages II and III the dependable capacity of the development increases as the peak load increases.Table B.4.2.2 shows the dependable capacity for the three stages as limited by load,and with no limitation of load. -----4.2.-6---Base-Load--and---Load-Fol-lowing Ope r a-tio n(-***}~.---- The Watana plant initially would operate on base to maintain nearly uniform discharge from the power plant.The Watana project could also be utilized for spinning reserve,which could require that it follow load to some extent.When Devil Canyon comes on line,Watana would change to a peaking operation,while Devil Canyon operates on base. Tht?ul t:ill1ateobject iveofanyllydro-electric:~pr.6jeC.t..opera t ion is to have the flexibility to follow loads,regulate frequency and voltage,provide spinning reserve,and react to system needs under all normal and emergency conditions.The project should be dispatched to minimize thermal operation and fuel costs.Conse- ) J ,·1,I • f 851104 B-4-12 quently,it would be desirable for the Susitna Project to follow load as closely as practical as it fluctuates on an hourly and seasonal basis. To assess the economic impact of base load versus load following operation,the power and energy data for the load following case were input to the OGP model and an economic evaluation was made. The With-Susitna plan,assuming base-load operation of the downstream project,has a 1985 present worth of system costs of $4,823 million.For the same plan,assuming load-following operation,the 1985 present worth of system costs are $4,693 million.The difference of $129 million can be considered foregone project benefits or mitigation costs. 851104 B-4-l3 1 , J ,I 1 ,I '[ 1 ,) 'J 1i I ,I ) ] I' i :] j 851104 5 -STATEMENT OF POWER NEEDS AND UTILIZATION (**) 5.1 -Introduction (**) Electric power demand forecasts have been developed for the Railbelt market that will be served by the Susitna Project. The following sections present the existing electric power demand and supply situation and the basic approach used to develop the electric power forecasts for the Railbelt market that will be served by the Sus i tna Proj ect. Section 5.2 describes the electric power system in the Railbelt, including utility load characteristics,conservation programs and electricity rates.Section 5.3 presents the forecasting_methodology. The section describes the four computer-based models that were utilized in preparing the economic and electric energy forecasts and the genera tion expansion plan for meeting the loads..Section 5.4 presents the key variables involved in producing the forecasts,the results of the forecasts,and the impact of world oil prices!··:on the forecasts. 5.2 -Description of the Railbelt Electric Systems (**) This section describes the present Railbelt electric systems.This includes a general description of the interconnected Railbelt market and the electric utilities serving the market,the characteristics of the loads,electricity rates,conservation programs,and historical data covering Railbelt electricity demands and regional economic factors. 5.2.1 -The Interconnected Railbelt Market (**) The Railbelt region,shown in Figure B.5.2.1,contains two important electrical load centers:the Anchorage-Cook Inlet area and the Fairbanks-Tanana Valley area.These two load centers comprise the interconnected Railbelt market.The Glennallen-Valdez load center is not planned to be interconnected with the Railbelt nor to be served by the Susitna Project.It is therefore excluded from discussions in this document. The existing transmission system of the Anchorage-Cook Inlet area extends from Anchorage north to Willow and consists of a network of 115-kV,138-kV,and 230-kV lines with interconnection to Palmer.The Fairbanks-Tanana system extends from Fairbanks south to Cantwell over a 138-kV line.The Anchorage-Fairbanks Intertie,connecting Willow and Healy,was completed by the Alaska Power Authority in October 1985 and is currently operating at 138 kV.The existing transmission system in the Railbelt region is illustrated in Figure B.5.2.2. B-5-1 (a)The Electric Utilities and Other Suppliers '(**) (i)Anchorage-Cook Inlet Area (**) The Anchorage-Cook Inlet area has two municipal utilities,three Rural Electrification Administration (REA)cooperative associations, a Federal power agency,and two military installations,as follows: o Municipality of Anchorage~unicipal Light &Power Department (AMLP) o Seward Electric System (SES) o Chugach Electric Association,Inc.(CEA) o Homer Electric Association,Inc.(HEA) o Matanuska Electric Association,Inc.(MEA) o Alaska Power Adminis tration (APAd) o Elmendorf AFB -Military o Fort Richardson -Military All of these organizations,with the exception of MEA,haveelec-trica-l generat-ing-£ae-ilit-iesc.~-MEA-buys- its power from CEA and the APAd.HEA and SES purchase power from CEA and maintain generating facilities primarily for standby operation. AMLP and CEA are the two principal utilities servicing the AJlchorag~-C()ok Inlet area.AMLP serves most areas within the City of Anchorage except for some sections served-by CEA.In addition~AMLP _____~~E":~~__~!t~~_~~_h 0 ~~_g~_~_Il:~~t'I!a ti:g~o!lJ_~!t'P~:r_t,__I!Il,SL__ provides electrical energy to Elmendorf AFB and Fort --l'Hchardson on a'non-fIrm basis.AMLP also provides bulk power to CEA.The customers and associated sales of AMLP in 1984 are listed below.Residential sales represented slightly over one fourth of total commercial sales.Its most important load is the downtown business and commercial district. -I 1 f I I ] .j 851104 B-5-2 1 851104 AMLP 1984 Customer Class Number Energy Sales (MWh) Residential 18,007 138,808 Commercial 3,921 523,088 Street Ligh ting 8,135 Sales to Public Authorities 1 15,907 Total 21,928 685,938 CEA serves certain urban and most suburban sections of Anchorage.In addition,CEA serves customers at Kenai Lake,Moose Pass,Whittier,Beluga and Hope. CEA also provides bulk power to AMLP.CEA's residential load is greater than its commercial and industrial loads. Furthermore,CEA'save rage commer c ia 1 c us tomer is consistently smaller than that of AMLP.Its 1984 sales are presented below: CEA 1984 Customer Class Number Energy Sales (MWh) Residential 55,036 532,133 Commercial &Industrial (50 kVA or less)5,874 410,812 Commercial &Industrial (over 50 kVA)3 10,583 Public St.&Hwy.Lighting 5,444 Sales for Resale 3 834,228 Total 60,916 1,793,200 HEA,MEA and SES provide electricity service to approximately 43,000 customers by purchases from CEA. In 1984,HEA,MEA,and SES purchased about 349 GWh, 396 GWh,and 26 GWh of electrical energy, respectively.REA serves the City of Homer and other customers on the Kenai peninsula.MEA has a service area encompassing Eagle River,the Matanuska Valley and surrounding areas.SES serves the City of Seward.These areas are depicted on Figure B.5.2.1. B-5-3 851104 The Alaska Power Administration provides wholesale power (firm and secondary)to MEA,CEA,and AMLP. These utilities are interconnected with the Alaska Power Administration on 115-kV lines owned by the Administration.Fort Richardson and Elmendorf AFB supply their own needs.Their electrical requirements in 1984 were approximately 59 and 72 GWh,respective1y~Both bases have non-firm power agreements with AMLP.Fort Richardson has a contract with AMLP to purchase about 30 GWh on an interruptable basis. (ii)Fairbanks -Tanana Valley Area (**) The Fairbanks-Tanana Valley area is currently served by a municipal utility and an REA cooperative.,In addition,a university and three military installations have their own electric systems,as follows: o Fairbanks Municipal Utili ties System (FMUS) o Golden Valley Electric Association,Inc. (GVEA) o University of Alaska,Fairbanks o Eielson AFB -Military o Fort Greeley -Military o Fort Wainwright -~ilitary Fairbanks Municipal Utilities System and Golden Valley Electric Association,Inc.own and operate generation,transmission,and distribution faci1i- ......ties.TheUniversity..andmilita rybas esmaintain... h ',··d d''b'f '1',.te~r_o.wn.genera.t~o.n._an.._~s.t.r~..ut~o.n..a.c.~..~t~e.S..L ..._•... Fort Wainwright is interconnected with GVEA and FMUS and is providing both uti li ties with economy energy. EMUS serves an area bounded by the city limits of Fairbanks,except for several residential subdivisions recently annexed by the city.The Chena R.i.verflowsthrougll the northern part of the service ·areawith ·ForJWaitlwrig1:lJ:·Military.:R.fasfarva tion providing a border on the east.The downtown business district lies in the northeast corner of the FMUS service area along the south bank of the Chena River.There is an industrial area which is B-5-4 I I 851104 contained in part within the City of Fairbanks.The north bank of the Chena River provides the ·southern boundary of this industrial area.In addition to serving its own customers,FMUS provides economy energy to GVEA.The 1984 sales of FMUS are as follows: FMUS 1984 Customer Class Number Energy Sales (MWh) Residential 4,802 29,132 Commercial 1,201 80,834 Sales to Public Authorities 113 16,944 Street Lighting 2,500 GVEA 1 12,935 Total 6,117 142,345 The commercial customers are significant in number and,more importantly,in terms of total energy sales.The residential ~nd government sectors had about the same level of energy sales in 1984. GVEA serves the Fairbanks North Star Borough including por·tions of the City of Fairbanks not served by 'FMUS,the City of North Pole,the communities of Fox and Ester,and the two military bases -Eielson Air Force Base and Fort Wainwright. Other communities within its service area include Nenana,Healy,Cantwell,Clear,Anderson,and Rex. In 1984,GVEA sales were as follows: B-5-5 GVEA 1984 Customer Class Number Energy Sales (MWh) Residential 20,275 172,958 Commercial &Industrial (50 kVA or less)2,239 50,505 Commercial &Industrial (over 50 kVA)264 136,678 Public St.&Hwy.Lighting Sales to Public Authorities 1 3,140 Sales for aesale 1 17,132 Total 22,780 380,413 The University of Alaska at Fairbanks,Fort Wainwright,and Eielson AFB generate their own electrical requir-eme~s.At the present time,Fort WainwrighLsupplies all of Fort Greeley's electricity needs with GVEA wheeling the power on their transmission lines.Fort Wainwright provides economy energy to EMUS and GVEA from coal-fired units.In 1984,Fort Wainwright had net generation of about 75 GWh and Eielson AFB generated about 49 GWh of electricity. Several major industrial companies in the RaUbel t provide their own electric power supply.During 1983,the latest year for which data are available, such generation accounted for nearly 361 GWh in the Anchorage-Cook Inlet area.The major industrial self suppliers are located in HEA's service area.The main industrial firms with operations in Kenai include Union Oil of Ca-lifornia;PhH-lipsPetrol-eum - --Gompany-,-Ghe-vr-on--U-.S-.A.,----Inc-,,-,--and--1'esoro-A-l-a-skan----- Petroleum Corp. In 1983,industrial sources of electrical generation in the Fairbanks-Tanana Valley area did not produce any electrici ty. (b)The Existing Electric Energy Supply And Power Plant Cal'acity(**) The Anchorage-Cook Inlet area is almost entirely dependent on natural gas to generate electricity.About 92 percent of J J J 1 851104 B-5-6 j I the total capacity is provided by gas-fired units.The rema~n~ng are hydroelectric units (5 percent)and oil-fired diesel units (3 percent).Table B.5.2.1 presents the total generating capacity of the Anchorage-Cook Inlet utilities, the two military installations,and the industrial sector~ For the Fairbanks-Tanana Valley area,the total generating capacity of the utilities,the three military installations, and industrial self suppliers,by type of unit is presented in Table B.5.2.2.A large portion of the total installed capacity consists of oil-fired combustion turbines (58 percent)and coal-fired steam turbines (32 percent).The remaining capacity is provided by diesel units.The transmission intertie between Anchorage and Fairbanks allows Fairbanks utilities to purchase economy energy,fueled by natural gas,from Anchorage.It also allows both load centers to take advantage of reserve capacity available in both load centers to provide greater reliability. Tab1eB.5.2.3 provides a complete list of generating plants of the Rai1be1t area.The plant data and characteristics shown were developed by the Applicant from information provided by the Rai1be1t utilities. 5.2.2 -Rai1be1t Electric Utilities (**) (a)Utility Load Characteristics (**) This section presents monthly peak and energy demand,hourly load data for a typical week in April,August,and December,and an analysis of load diversity between the two load centers. (i)Monthly Peak and Energy Demand (**) Table B.5.2.4 presents monthly distributions of peak and energy demand for the two load centers and for the total Rai1be1t area.The average monthly values for the period 1976-1982 are based on Alaska Power Adminis tration da.ta.The monthly values for 1982 and 1983 and their averages are based on hourly load data supplied by AMLP,CEA,mus and GVEA. Figure B.5.2.3 shows the 1983 monthly load variation for each load center. 851104 Both regions have winter peaks, December,January or February. lowest during the months of May B-S-7 occ urring in The peak demand through August, is and (ii ) the ratio of summer to winter peaks varies between 0.58 and 0.65.Although monthly peak demand varies from year to year,mainly due to weather conditions, Table B.S.2.4 shows that the pattern has remained relatively constant during the period 1976-1983. As denoted by the data in Table B.5.2.4,the monthly distribution of energy (net generation)demand has remained about the same for the period 1976-1983 with both regions having a similar distribution.The winter months,November through February,had an average monthly demand of about 9.8 percent of the total annual energy.The summer months,June through August,had an average monthly demand of about 6.8 percent of the total annual energy. The hourly load data for 1982 and 1983 have been used in the generation expansion studies described in Chapter 2 of Exhibit D.For these studies,monthly ratios and hourly ratios have been developed f~the historical load records.The technique used is referred.to c'3.s the.Ml:t:1l.Q9.0f,Illg.iI:"~~tAveraging. This method develops rank orders to compute load magnitudes and time orders to compute load sequences. Table B.S.2.5 summarizes the distribution of monthly peak demand to annual peak demand and mo'nthly energy requirement as a percentage of the annual energy requirement resulting from the Method of IndirectA.veraging ana lysl~---,----------.-.- Daily Load Profiles (**) ,.1 '1 .1 ..I FigureB.5.2.4 presents graphs of the hourly load data for typical weeks in April,August,and December 1983.The data from individual utilities were combined to produce representative load curves -...-----.--...'··-foreachl'oad-centerand·the·total RaUbe'lt'area~-' ..-The~-fol-low-i-ng-pa-ragra·ph's--de·s·cri·be··-the-·weekly-load' profiles. In April,th~re is usually a morning peak between 8 and 10 a.m.,and an evening peak between 6 and 8 p.m. The evening peak is usually greater than the morning peak.The night load is about 65-70 percent of the daily load.The average daily load factor is about 85-percent •...... r ! 851104 B-5-8 In August,the load begins to rise from about 7 a.m., continuing to increase until 11-12 a.m.,wnen it reaches a peak,it then decreases slowly to about midnight before dropping off sharply.The night load is about 55-60 percent of the daily peak load.The average daily load factor is about 82 percent. In December,there is usually a morning peak between 8 and 10 a.m.,and an evening peak between 6 and 7 p.m.The evening peak is usually about 10 percent greater than the morning peak.The night load is about 60 percent of the daily peak load.The average daily load factor is about 85 percent. Table B.5.2.6 presents twenty~,four hour load-duration relations for typical weekday and weekend days for the months of April,August,and December.These data were developed from the utility hourly load data as discussed above.Similar load duration data were computed for the remaining months.These data have been used in the generation expansion studies described in Chapter 2 of Exhibit D. (iii)Railbelt Load Diversity (**) A system load diversity analysis w&s done by comparing the peak days in 1982 and 1983.The peak coincident and non-coincident loads were collected from the hourly load data provided by AMLP,CEA, FMUS,and GVEA and the load diversity was calculated based on the data.Table B.5.2.7 shows the hourly load demand for the Jariuary 6,1982 and January 10, 1983 peak days.The diversity measure in the total Railbelt was about 0.99.The basic conclusion of the analysis is that the total coincident peak load for the Railbelt would be within two percent of the total non-coincident peak demand.For the expansion planning analysis,the Railbelt peak demand is considered to be the sum of the projected peak demand of the two load centers. (b)Electricity Rates (**) Tables B.5.2.8 and B.5.2.9 present the current residential and commercial electric rates for the utilities of the Anchorage-Cook Inlet area and Fairbanks-Tanana Valley area, respectively. Electric rates are considerably less in the Anchorage-Cook Inlet area than in the Fairbanks-Tanana Valley area.The 851104 B-5-9 851104 average residential cost per kWh is approximately 6 cents/kWh in the Anchorage-Cook Inlet area,and 8.4 cents/kWh and 12.4 cents/kWh for FMUS and GVEA respectively in the Fairbanks-Tanana Valley area.The lower rates in Anchorage-Cook Inlet can be explained by the relatively low cost natural gas supply and low capital cost facilities used for electric generation.The relatively high rates in Fairbanks-Tanana are a result of considerable oil-fired generation,and high capital cost of coal-fired facilities.A discussion of these rates is presented in the following paragraphs. (i)Anchorage Municipal Light and Power (AMLP)(**) The AMLP tariff for residential service and small general service customers comprises a fixed monthly _ customer charge and a flat energy charge per kWh. The large general .service customer schedule has a monthly demand charge in addition to a fixed customer charge and a flat energy charge per kWh.In addition,AMLP has an experimental program for time.,..of.,..day rates for customers dependent upon electric space heating. (ii)Chugach Electric Association,Inc.,(CEA)(**) CEA has tariffs for residential customers that reflect a declining block rate structure.Small "commercial .cus-tomer-schedules--pr-ovide-£ot'a·-f-ixe d monthly customer charge and a flat energy charge per kWh.CEA's schedule for large commercial customers contains a demand charge as well as a fixed monthly customer charge and a flat energy charge per kWh. CEA has a wholesale electric power and energy contract with HEA,MEA,and SES.MEA,HEA,and SES have.tariffschedl1 les whiclldiffer .in specific --de tails"DuE ~ii:-e-"simi1arrn struct"ure"to those"of the -la-rger--Rattoert----eIectric utiTities ,-as shown In-Table B.5.2.8.In addition,CEA has a rate schedule for intertie with AMLP which contains a flat energy charge and certain commitment and start/stop charges. (iii)Fairbanks Municipal Utilities System (FMUS)(**) In the Fairbanks-Tanan.a Valley area,EMUS has residential,all electric;aifdgeneralservice rate schedules which reflect declining rates as energy consumption increases in blocks.For general service customers with demand blocks of 30.kW or greater, B-5-10 there is (in addition to an energy charge)a monthly minimum charge per meter based on a fixed dollar amount times the highest demand reading of the preceding 11 months or times the estimated maximum demand of the first year,whichever is greater. (iv)Golden Valley Electric Association,Inc. (GVEA)(**) GVEA has a residential schedule with an energy charge for the first 500 kWh and a lower charge for each kWh over 500 kWh of consumption.There is a separate schedule for general service customers depending on their kW demand.'For GVEA's general service customers with electrical demand not exceeding SO kW, there,is only a decreasing energy charge associated with three increasing blocks of consumption.General service customers with loads exceeding SO kW have a schedule which provides for a fixed demand charge per kW pI us declining energy charges in correspolldenc;e with four increasing consumption blocks. (c)Conservation and Rate Structure Programs (*) This section presents conservation and rate structure programs initiated by the electric utilities and government agencies.The effects of these existing programs are reflected in current electricity consumption which serves as the basis of the load forecast,described in Section 5.4 of this Exhibit. The utilities have various programs aimed at'supplying information to the public concerning the dollar savings associated with electricity conservation.In general,the utilities rely on market forces;however,they promote consumer recognition of those forces.Examples of conservation and rate structure programs introduced by AMLP and GVEA are described. (i)The Anchorage Municipal Light and Power (AMLP) Program (**) The AMLP program addresses electricity conservation in both residential and institutional settings.It is a formal conservation program mandated by the Powerplant and Industrial Fuel Use Act of 1978 (FUA). The AMLP program is designed to achieve a 10 percent reduction in electricity consumption.To achieve this level of conservation,AMLP provides information on available state and city programs to its consumers.Additionally,it has programs to: 851104 B-5-11 o Distribute hot water flow restrictors; o Insulate 1000 electric hot water heaters; o Heat ·the city water supply,increasing the temperature by 15°F (decreasing the thermal needs of hot water heaters); o Convert two of its boiler feedwater pumps from electricity to steam; o Convert city street lights from mercury vapor lamps to high pressure sodium lamps;and o Convert the transmission system from 34.5 kV to US kV. AMLP also supplies educational materials to its customers along with "Forget-me-not"stickers for light switches.The utility has a full time energy engineer devoted to energy conservation program development. The projected impacts of specific energy conservation programs are detailed in Table B.5.2.10 for the period 1981-1987.The greatest impact will occur as a result of street light conversion,transmission line conversion,and power plant boiler feed pump ~co~nversio_n •....~.By ..L98:7~,_thes_e~programs~are_expected~to provide 35,000 MWh of electricity conservation,or 72%of the total programmatic energy conservation. In the case of conversion to new sodium lights,the record shows that AMLP installed 96 kW by the end of 1980,an additional 8 kW in 1981,16.6 kW in 1982, and 14.3 kW of additional sodium lights in 1983.In addition to these conservation programs,AMLP has also projected conservation due to ce-induced e (ii)The Golden valley Electric Association,Inc.(GVEA) Program (*) .J I GVEA has an energy conservation program based plan established pursuant to REA regulations. -utili-ty--employsan-Energy-Use-Advisor who: on a The 851104 0--Performsadvisory'{non-quantitative)audits; o Counsels customers on an individual basis on means to conserve electricity; B-5-12 ;·1 851104 o Provides group presentations and panel discussions;and o Provides printed material,including press releases and publications. GVEA also eliminated its special incentive rate for all-electric homes,and placed a moratorium on electric home hook-ups in 1977.It has given out flow restrictors.It has prepared displays and presentations for the Fairbanks Home Show and the Tanana Valley State Fair. The efforts of GVEA,combined with price increases and other socioe.conomic phenomena,produced a conservation effect·in residential use per household. Although much of the decline in average consumption can be attributed to conversions from electric heat to some other fuels,part of the reduction is the direct result of conservation.A moderate upturn in electricity consumption per household in 1982 indicates that the practical limit of conservation may have been reached in the GVEA system. Currently,GVEA's load management program is directed toward commercial consumers.A significantly lower rate schedule is available to commercial customers whose demand is maintained at less than 50 kW. Larger power customers are advised on ways to manage their electrical load to minimize demand.In addition,seasonal rates are available to those large consumers who significantly reduce their demand during the winter peak'season.A program is underway to identify customers who operate large interruptible loads during periods of system peak demand.Various methods of residential load management are under study,but none appears cost effective at this time other than voluntary consumer response to education programs. (iii)Other Utility Programs (0) Other utilities have programs similar to the ones described above.For example,FMUS has two main programs aimed at electric conservation and reducing the consumer's electric bill.FMUS placed an advertisement in a local newspaper about energy conservation and offered to provide a free booklet on the topic.Also,FMUS plans to advertise the availability of an "Energy Teller"device to allow B-5-13 851104 the customer to determine the direct cost of using a given appliance.These instruments are exp~cted to be available for free loan for a period of up to two weeks. (iv)Other Conservation Programs (0) There are several efforts,both public and private, under way throughout Alaska.The two main programs that affect the Railbelt area are described in the following paragraphs. The State Program.The Alaska Department of Community and Regional Affairs administers the United States Department of Energy's low-income weatherization program.The program is currently directed at rural areas and is gradually being phased out.It has involved the following activities; o Training of energy auditors; o Performance of residential energy audits,which are physical inspections including measurements of heat loss; o Provid~ng grants of up to $300 per household, or loans,for energy conservation improvements based upon the audit;and o Providing home retrofitting (e.g.insulation, weatherization)for low income households. The City of Anchorage Program.The City of Anchorage Program is operated by the Energy Coordinator for the City of Anchorage.This program also involves audits,weatherization,and educational efforts. Based on walk-through audits performed on city -_.-'-··"Dfj-i-ldi"i·fg·S'---~~fna··--tfchoo'I-s--;"------de"-e'a'-ir-iid-----aua-r"t:'·s..,-"'fi'a-ve'---oe"Eiii"'---_.--~--_.,_._~._,-.. The city's weatherization program is available to low income families and provides grants of up to $1,600 for materials and incidental·repairs. ---The educational-program-has involved working with realtors,bankers,contra.ctors,and businessmen.It -alsohas--involved-informalconta ct s wi thcommer cial building maintenance personnel.Finally,it has involved contacts with the general public. B-5-14 ..~ .J ] '] ./ j ) ,J 851104 5.2.3 -Historical Data for the Market Area (**) Historical economic and electric power data for Alaska and the Railbelt are summarized in Table B.S.2.1l.The table shows the rapid growth that has occurred in the state's and the Railbelt's population,economy,and use of electric power.From 1960 to 1984,the state population has grown from 226,000 to 523,000,an average annual growth rate of 3.6 percent.The Railbelt population has grown at a faster rate of 4.1 percent,increasing from 140,000 in 1960 to about 371,000 in 1984.The growth has been especially rapid during the last five years. Between 1960 and 1984,employment in the state grew from 94,000 to 1'64,000,an increase of 180 percent,or an average of '4.4 percent per year.Much of the population and economic growth that occurred during this period is attributable to several factors.During the 1960'S,oil and gas resource development in Cook Inlet provided the beginning of a bax base and a stimulus to infrastructure development.The 1964 earthquake in Anchorage and the 1967 flood in Fairbanks resulted in significant construction activity.The 1970's were dominated by the anticipation and construction of the trans-Alaska pipeline.In 1979,a decline in the economy resulted from the reduction in construction employment,but it was significantly offset by expansion of state and local government,made possible by the tremendous increase in state petroleum revenues from Alaska's North Slope.The quadrupling of the world oil price at the beginning of the decade has provided the impetus for the current cycle of Alaska's economic growth. State petroleum revenues have grown from only $4.2 million in 1960 to $2.9 billion in 1984 while state general fund expenditures have risen from less than $100 million per year to $3.3 billion.Figure B.S.2.S illustrates the historical growth in Rai1belt population,showing the annual growth rate for each five-year period from 1960 to 1980 and from 1980 to 1984. Consumption of electric energy in the Railbe1t has risen significantly faster than the rate of economic growth.Between 1965 and 1984 total utility energy generation increased from 487 GWh to 3208 GWh,a six-fold increase,or an average of 10.4 percent per year.Figure B.5.2.6 illustrates the historical growth in Rai1belt net generation,showing the annual growth rate for each five-year period from 1965 to 1980 and from 1980 to 1984. Tables B.5.2.12 and B.5.2.13 present monthly electric power use and peak demand during the period 1976 to 1983 for the Anchorage and Fairbanks load centers.These tables show that, while there has been a steady rise in the use of electric energy B-S-15 and in peak demand,there has been variation in monthly energy use and peak demand from one year to the next,due mostly to different weather conditions in the Railbelt.Table B.5.2.14 presents the annual net generation of each Railbelt utility between 1976 and 1984. 5.3 -Forecasting Methodology (*) Th1S section presents the methodological framework used for the forecasts of economic conditions and electricity demand in the Railbelt.First,the models used for forecasting purposes are identified and explained.Next,model validation is discussed for the petroleum revenue model (APR),economic model (MAP),and electricity demand model (RED)and the optimized generation planning model (OGP). 5.3.1 -Forecasting Models (**) (a)Model .Overview (**) Four computer-based and functionally int~rrel~ted models were used to forecast Railbelt economic growth and the associateci·d~Ill~~ci f9I:'.~lecl:ric power,and for evaluating alternative generation plans for meeting electric power demand.The models and their relationship are 'graphically displayed in Figure B.5.3.1. The starting-point for the demand forecast is a series of da ta inputs concerning 'the projected world oil price and the pro je cted.Alas kagasa~cl()npric:~s .and.:pr od uc t io~l~Jlels_._ Aii:hIs stage 'of the'process,the world oil price forecast is important because it affects the wellhead price of oil in Alaska,and also affects the assumed price of na tural gas. The first economic model in the series,the Alaska Petroleum Revenue Sensitivity Model (APR),was designed by the Alaska Department of Revenue (ADOR)to translate petroleum price and production forecasts into forecasts of state petroleum 851104 The model is a simplified version of ADOR's PETREV model, which the agency uses to make its quarterly petroleum revenue forecasts.The price and production forecasts input to the APR model are combined with assumptions about royalty rates,severance tax rates,and certain adj ustment factors to produce forecasts of state petroleum revenue.,· The,state pe trol eum-revenue-forecast 'output by the APR model becomes input to the second economic model in the series. !he Man-in-the-Arctic Program (MAP)was developed by the University of Alaska's Institute of Social and Economic B-5-16 I j 851104 Research (ISER)for the purpose of forecasting economic growth in Alaska.The MAP model was designed to take assumptions concerning basic industrial development,state petroleum revenue forecasts,fiscal policies,and several national and state economic and demographic parameters,and from these assumptions forecast growth in the state economy. Railbelt economic growth in terms of population,households, and employment is then isolated from the state totals. The Railbelt economic growth forecast output by the MAP model becomes input to the Railbelt Electricity Demand (RED) model,a partial end use model developed by ISER and later modified by Battelle Paci~ic Northwest Laboratories.The RED model also incorporates many other assumptions, incl uding: o residential and business end use data,including saturation rates for various electrical end uses o an industrial/military load forecast o estimates of heating oil,natural gas,propane,and electricity prices to be paid by residential and business consumers in the Anchorage and Fairbanks load centers o long term and short term price elasticities,which define consumers'responses to changes in the price of electricity and competing fuels Given these assumptions and the MAP model's economic growth forecast,the RED model produces a forecast of energy demand and peak load through 2010. The output of the RED model is the product of one iteration of the demand forecasting process.The energy and peak load forecasts become input to the Optimized Generation Planning (OGP)model,which is part of the economic and financial analysis component of the Susitna project evaluation process.Given a load forecast,and the cost of building thermal generation alternatives,the OGP model chooses the optimal generation expansion path and calculates the cost of electricity associated with that path.If the resulting production cost of electricity is out of line with the retail prices assumed in the RED model,the RED model is rerun with new electricity prices,and OGP is rerun with the new load forecast until the prices converge. The following sections describe each of the four principal models,including their respective submodels and modules, B-5-17 key input variables and parameters,and primary output variables.Additional information on the APR model assumptions which,except for oil and gas prices,are the same as the ADOR's PETREV model assumptions,is available in the quarterly issues of Petroleum Production Revenue Forecast (Alaska Department of Revenue 1985).Additional information on the MAP modei may be found in the MAP model system documentation (ISER 1985).The system documentation presents a detailed description of the model,including a complete listing of its equations and input variables and parameters.Two other documents present similarly detailed documentation of the RED model.The RED model·Technical Documentation Report (Battelle 1983)was part of the Susitna license applica.tion as accepted by FERC in July 1983.The model documentation included in that report is still current,except for those changes noted in a more recent report prepared by Battelle (Scott,King and Moe 1985).The OGP model is a proprietary program of General Electric Company.The version used in the current study is presented in .the Descriptive Handbook,Optimized Generation Planning Program,by General Electric (GE 1983). (b)Alaska Petroleum Revenue Sensitivity (APR)Model (**) Petroleum revenues currently constitute a large proportion of total state revenues.State revenues and expenditures .also have considerable potential variability and are important determinants of future state economic conditions. T.b_e_.Al_a~.k:a.D_ep-ar_tme_nt ..of Reveuue.th_er_e_fore _pr.od_uces. quarterly projections of the most important sources of petroleum revenues,production taxes and royal ties.Those projections·are generated by a.specialiiedriiodel,PETREV. The APR model used for this load forecast is a special submodel of PETREV.The PETREV model will be described first,followed by a description of the APR model. PETREV is structured to take into account the uncertainties-_.--------------------of --fufurEf·-oir-prfc-e::I--and--(fElier-faEfors-ass·ocTafedw nIl ----f-orl:c-a-s-ttn-g-I'etr()~I-eUfif-r-eV'enue-s-.--U-s-tn-'g-PETREV-;--th-e-----A:DOR----------------- issues updated petroleum revenue projections on a quarterly basis covering a 17 year period.The ADOR uses current data available on petroleum production,a range of world oil prices,tax rates,regulatory events,natural gas prices, and iriflat ion ra tes • PETREV is an -economic a.ccount ingriiodeltha.t ··uti 1 izes a probability--distributionof·possiblevalues--for each of the factors that affect state petroleum revenues to produce a range of possible state royalties and production taxes.The principal factors influencing the level of petroleum I j 1 851104 B-5-18 ,] I. I I revenues are petroleum production rates,mainly on the North Slope,the market price of petroleum,and tax and 'royalty rates applicable to the wellhead value of petroleum. Natural gas prices and production levels are also taken into account,as are Cook Inlet petroleum prices and production levels.This model description focuses on North Slope petroleum,which accounts for over 90 percent of state petroleum revenue. For input into the PETREV model,wellhead value of oil is estimated by a netback approach.The costs of gathering and transporting crude oil and a quality differential value are subtracted from the market value at its destination on the West Coast or Gulf Coast of the United States.For petroleum produced on the North Slope,the source of most of the oil produced in Alaska subject to state royalties and production taxes,future wellhead value is estimated as follows.The projected world price of Ecuador Oriente petrol eum11 is adjusted by subtracting (1)the projected cost of pumping oil through the ]~ans Alaska Pipeline System from Prudhoe Bay to Valdez,including the pipeline tariff, (2)the projected cost of shipping the oil to refineries on the West Coast and the Gulf Coast of the United States,and (3)a projected quality differential factor representing the difference in quality between North Slope petroleum and Ecuador'Oriente grade.The result is the estimated value of petroleum at Pump Station 4/:1 at Prudhoe Bay,Alaska.For other North Slope fields,the price is lowered by the respective pipeline charges between each field and Pump Station if/:1. Future royalties collected by the state are estimated by multiplying total projected production in barrels from state lands by the estimated per barrel price at the pump, subtracting field costs,and multiplying the result by .125. This amounts to a 1/8 royalty payment on oil produced after all gathering and transportation costs are met.The State of Alaska may receive the royalty either in kind or in dollars.Future severance,or production,taxes are estimated by multiplying forecasted production,net of the 12.5 percent taken by the state as royalties,by the estimated pump station price and the tax rate adjusted by an economic limit factor (ELF).The nominal tax rate varies 11 Ecuador Oriente is a common measure of petroleum grade and price. Other standards include Saudi light and Saudi medium grade petroleum. 851104 B-5-19 851104 between 12.25 and 15 percent of net production value, depending upon the age of production wells.The e·conomic limit factor (ELF)adjustment takes into account declining well productivity and increased production costs.On the North Slope most production will be subject to a 15 percent nominal severance tax rate,but the effe~tive tax rate after adj ustment varies from 0.0 to 15.0 percent.A decline in the ELF in effect lowers the tax rate to which Alaskan petroleum is subject. Due to the many uncertainties involved in forecasting revenues,the PETREV model projects a range,or frequency distribution,of state petroleum revenues by year,so that for each year a forecasted petroleum revenue figure may be selected based on a given cumulative frequency of occurrence.The model accomplishes this by iteratively selecting a set of input variable values from among the alternative values and computing a petroleum revenue figure for each time period.Each projection is computed using a set of accounting equations l!hat estimate royalties and production taxes from each state oil and gas lease for each time period.By selecting the average.value of all input data,the model can also produce an average petroleum revenue forecast. For the Susitna Project evaluation it is necessary to examine the implications of more than one world oil price projection.This need is accommodated by ADOR through the Al~§l_ka ..l'e tJ'oleumRg'l~J,'lU~·.S~n1dtiytty_JA1>R)_Mo.deL_...W.ithtwo exceptions,this sensitivity accounting model,which is in effect a submodel of the PETREV model,utilizes the accounting equations and average values from PETREV.The two exceptions are world oil price and Cook Inlet gas price. By executing tn.esensitivity model with the alternative oil and gas price projections,alternative petroleum revenue projections are developed for use in projecting state economic activity in the MAP model.The APR model structure -i·ssnowil·in-Figure-B~S~3~Z~.__. The process of projecting state petroleum revenues and the functions of the PETREV model are presented in more detail in the quarterly "Petroleum Production Revenue Forecast" (ADOR 1985).The petroleum revenue projections used in preparing the electric power market and economic forecasts are based on the March 1985 average expected values of all factors other than oil prices a.nd Cook Inlet gas prices. Those·input assumptions are summarized in Section 5.4.1. B-5-20 J J :I ] .1 851104 (i)Input Data (***) As noted above,the APR model uses the mean values for the input data used in the PETREV model.The input includes both oil and gas revenue variables. Oil revenue variables include: o World oil price; o Oil price adjustment factors for each field expected to operate at any time during the forecast period (Prudhoe Bay,Kuparuk River, Milne Point,Endicott,Lisburne,West Sak Sands,Seal Island,unspecified onshore North Slope production,and Cook,rnlet); o Petroleum production for each field;and o Number of wells and economic limit factor for " each field,nominal severance tax rate and royalty rate gathering and cleaning charges by field. Gas revenue variables include o North Slope and Cook Inlet gas price; o North Slope and Cook Inlet gas production; o Economic limit factor by field;and o Severance tax and royalty rates. (ii)APR Model Output (***) The output data from the APR model includes oil and gas severance tax and royalties for each oil field and each gas producing area.The revenue estimates by field are summed to produce the input used in the MAP model,including: o State severance tax revenue by year,1985-2010; and o State royalty revenue by year,1985-2010. (c)Man-in-the-Arctic Program (MAP)Economic Model (*) The MAP model is a computer-based economic modeling system that simulates the behavior of the economy and population B-5-21 of the State of Alaska and each of 20 regions of the state. The regions correspond closely to Bureau of the Census divisions.The Railbelt consists of six of those regions: Anchorage,Fairbanks,Kenai-Cook Inlet,Matanuska-Susitna, Seward,and S.E.Fairbanks.The model was originally developed in the 1970s by the Institute of Social and Economic Research of the University of Alaska,under a grant from the National Science Foundation.The model has been continually improved and updated since it was originally developed.In addition to its use on the Susitna Project, it has been used in numerous economic analyses such as evaluations of the economic effects of alternative state fiscal policies and assessments of the economic effec ts of development of outer continental·petroleum shel f leases. The MAP model functions as three separate but linked submodels:the scenario generator submodel,the economic submodel,and the regionalization submodel,as illustrated in Figure B.5.3.3.The scenario generator submodel enables the user to quantitatively define scenarios of development in exogenous industrial sectors;i.e.,sectors whose development is basic to.tl:t~.economy rather than supportive. Examples of such'sectors are petroleum production and other mining,the federal government,and tourism.The scenario generator submodel also enables the user to implement assumptions concerning state··revenues from petroleum production.The economic submodel produces statewide projections of numerous economic and demographic factors based on quantitative relationships between elements oJ the ._..~~-~--Alaskan economy such as···em·ploYmentlli-basic i.ndustrIes, employment in non-basic industries,state revenues and spending,wages and salaries,gross product,the consumer price index,and population.The regionalization submodel enables the user to disaggregate the statewide projections of population and employment to each of the 20 separate regions of the state,using data on historical and current economic conditions and assumptions concerning basic ...............industrial development. --_._--.__...._.. Each of the three MAP submodels exists as a computer program,and each program is supported by a set of input variables and parameters.Each of these programs and the supporting input variables and parameters are discussed briefly in the following sections.Detailed information on each submodel,including a complete model listing and the input variables and parameters used ..in executing the model, is provided in.thiS License Amendment:. .J 851104 B-5-22 851104 (i)Scenario Generator Submodel (*) In order to operate the MAP model,the user must make a number of assumptions concerning the future development of basic industries in the State.Such assumptions are needed because the state economy is driven by interrelated systems of endogenous and exogenous demands for goods and services.Endogenous demands are generated by exogenous industries and the resident population which provides employment to all industries. Exogenous demands originate outside Alaska due to the favorable position of the state to export its minerals and other resources to other states or countries.In Alaska,exogenous demands stem·from the state's natural resource base,especially petroleum;non-energy minerals;federal property;and tourist attractions.Exogenous demands lead directly to employment in basic sectors such as mining, indirectly to employment and output in industries such as oil field services that support basic industry,and also to industries such as housing and restaurants that support workers in basic industries and their families. The scenario generator model.permits the user to build,from among a large number of alternative basic industrial cases,economic scenarios that can be used to project economic conditions in the State of Alaska and,for purposes of the Susitna Hydroelectric Project,the Railbelt.Input data for each of the scenarios are in the form of employment projections by sector and region of the state on an annual basis over the forecast period. The scenario generator model is also used to select the level of state petroleum revenue that is assumed available to the state's general fund for expenditure on state government operations and capital inves tment. Key input and output variables and assumptions for the scenario generator are summarized in Section 5.4.1 of this Exhibit. (ii)Statewide Economic Submodel (*) The statewide economic submodel is a simultaneous system of more than 1,000 equations that B-5-23 individually and collectively define the quantitative relationships between economic and demographic factors in Alaska.Some values for input variables come from the scenario generator,whose values can be expected to vary from one execution of the model to the next.Other values come from files of necessary exogenous data,such as files describing state fiscal behavior,whose values generally do not change across runs.Parameters,whose values are generally fixed from one model execution to the next,are provided from another input file.The equations are solved algebraically each time the model is executed to produce a unique set of values for the dependent variables. While the equations in the statewide economic model are solved as a unit each time the model is executed, they are grouped for organizational and conceptual purposes into three modules:economic module,fiscal module,and demographic module,as illustrated in Figure B.5.3.4. The equations in the economic module express relationships be tween economic factors such as employment in basic industrial sectors and output and employment in support sectors.Important products from the economic module include projections of employment and payroll by industry and personal j "J The fiscal m()dult:c01llputesstate government revenues and .the mix of government expenditures.This info:rmation is used as input to the economic module. The fiscal module plays a key role in examining the fiscal and economic effects of different future world petroleum prices and state petroleum revenue levels. ............__.._...The.demographic module expresses~~.£.~lationshiI>~_ between both households and population and economic factors recognized as key determinants of population. Population is determined by such factors as employment,labor force participation rates, fertility and mortality rates,and unemployment and wage rate differentials be.tween Alaska and the rest of th e Urti te d S.~§l tE!$• HouseholdfoiIllation is based lIpon a unique propensi ty to form households in each age,sex,and racial category.Over the last few years this household 'j "J .1 851104 B-5-24 :1 i \ lJ formation rate has generally increased.The increase is expected to continue at reduced rates. (iii)Regiona1ization Submode1 (*) Statewide employment,population,and household projections are disaggregated by the regiona1ization model,the third submode1 of the MAP economic modeling system.Disaggregation is accomplished by combining statewide projections with regional industrial development data and regional parameters based on historical,economic and demographic relationships between each region and the state.This process,illustrated in Figure B.5.3.5,produces projections by region or region group such as the Anchorage and Fairbanks greater metropolitan areas. (iv)Input Variables and Parameters (*) As indicated above,some input variables are factors whose values are provided by the user to the model and whose values can be expected to change from one execution of the model to the next.Parameter values are generally fixed both over time within each simulation and during the course of successive model executions. The scenario generator model produces 16 input variables to define the exogenous economic assumptions for each model execution: o Agriculture Employment o Mining Employment o High Wage Exogenous Construction Employment o Regular Wage Exogenous Construction Employment o High Wage Exogenous Manufacturing Employment o Regular Wage Exogenous Manufacturing Employment o Exogenous Transportation Employment o Fish Harvesting Employment 851104 B-5-25 851104 o Active Duty Military Employment o Civilian Federal Employment o Tourists Entering Alaska o State Production Tax Revenue o State Royalty Income o State Petroleum Lease Bonus Payment Revenue o State Petroleum Property Tax Revenue o State Corporate Petroleum Tax Revenue Of these 16 variables,10 are used to define discrete industrial development scenarios and are therefore region specific.One variable defines the level of tourism fon .the state~The remaining five input variables are elements of state revenue forecasts. Est imat:~~():fpetroleUlD p:rod1J~t:i,on taxes and royal ties are obtained from the APR model.The Alaska Department of Revenue's March 1985 estimates of state petroleum.corporate taxes are used (ADOR 1985). State petroleum property tax estimates are based on ADOR projections adjusted for ISER estimates of OCS-related activities.Future lease bonus payments ...._..~!:.~_~..J:s t !maE~~EL~SER.__...._ 'The regionalization model is executed using a data series for 40 exogenous variables,based on 20 state regions in the scenario generator.For each region, there are basic sector employment and the government sector employment.Total state population, households,and the ratio of support to total employment are provided by the state economic ·····submodel.-· In to the variables discussed above,the MAP model utilizes three types of parameters:variable state fiscal policy parameters;stochastic parameters;and calculated,or non-stochastic, parameters. Variable state fiscal policy parameters are used primarily in the fisca ltllodule torepreserit policy options for the collection of revenues and the timing and composition of state expenditures.The most important function of these parameters is to B-5-26 ] I .---.•.,__.••••.•.__'~"'_"'~_".__.._._~_,..,_.8 ' '~'__'' ''_~".__••._.__•__,•••••••.••..••.••__._.••• .••~_•• 851104 quantitatively define state expenditure and revenue policies.In projecting economic conditions for the Susitna Hydroelectric Project,the following assumptions were made: o State expenditures for operations and capital improvements in 1985 dollars will rise in proportion to state population as long as revenues can support this level of expenditure; this assumption is in accordance with a 1982 amendment to the Alaska State Constitution setting a ceiling 'on state expenditures. o When revenues from existing sources cannot support expenditures at the constant real per capita level,earnings from the permanent fund will be made available for operating and capital expenditures at the expense of the Permanent Fund dividend program;as revenues decline,state spending priorities shift from subsidies and capital improvements toward the operating budget. o When revenues from Permanent=Fund earnings and other sources are not sufficient to maintain expenditures at.the constant real per capita level,a state personal income tax will be reimposed at its previous rate. o When all of these revenue sources plus any accrued general fund balances are unable to support expenditures at the constant real per capita level,both capital and operating expenditures will be curtailed proportionately so that they will not exceed revenues. Stochastic parameters are coefficients computed using regression analysis.They are used primarily in the economic module of the statewide economic model to express the functional relationships between economic factors such as employment,wages and salaries,wage rates,gross product,and other national and regional economic factors such as unemployment and consumer price indices.Stochastic parameters are also used in the population module to express the relationship between population migration into and out of Alaska and wage rate and unemployment level differentials. Calculated or non-stochastic parameters are generally calculated rates or other quotients,and are used B-5-27 primarily in the population~::and household formation modules and the regionalization model.Calculated parameters include factors such as survival rates for the population by race,age group,and sex. Calculated parameters used in the regionalization model include factors such as the ratio of population to residence adjusted employment by region. (v)MAP Model Output (*) Economic forecasts through the year 2010 are generated for alternative oil and gas prices and state petroleum revenue cases and other input variables and parameters described above.Specific MAP Model-output used directly as input to the Railbelt Electricity Demand (RED)Model include the following: o Population by load center,Greater Anchorage and Greater Fairbanks,by year,n!·985 through 2010 o Total employment by load center by year o Total households in the state by age group of head of household -24 and under years of age, 25-29,30-54,and over 55 -by year .._.Q TQtalho.useholds byl0.ad.center by year (d)Railbelt Electricity D~mand Model (*) The Railbelt Electricity Demand Model is an end use - econometric model that projects both electric energy and peak load demand in the Anchorage-Cook Inlet and Fairbanks-Tanana Valley load centers of the Railbelt for the period 1980-2010.The Anchorage-Cook Inlet load center is --aefinedtoincrudetlieAncnorage;Kena i=C()okfiiI e'E ;.- ---·'--M·at·anuska=S·us·i'tnli-;-anaSewara'census regions~.IKe Fairbanks-Tanana Valley load center includes the Fairbanks and SE Fairbanks census regions. The RED model was originally written by the Institute of Social and Economic Research (ISER)of the University of .Alaska·(·ISER 1980.).-It was later modified and expanded by -Battelle Pacific Northwest Laboratories (Battelle 1982, .-Volume VITr).·The-present·version is a ftirthermodification and improvement,and includes a validation of the model performance.The resul ts of these e·fforts are fully documented in Battelle (1983)and Scott,King and Moe (1985).A summary description of the methodology used by the RED model and an explanation of each module are 11 '1 851104 B-5-28 I .'] presented in the following paragraphs.These discussions are followed by a description of the input and output data. The RED model is a simulation model designed to forecast annual electricity consumption for the residential,business (commercial,small industrial,government),large industrial,and miscellaneous end-use sectors of the two load centers of the Railbelt region.The model is made up of seven separate but interrelated modules,each of which has a discrete computing function within the model.They are the Uncertainty,Housing,Residential Consumption, Business Consumption,Program-Induced Conservation, Miscellaneous Consumption,and Peak Demand Modules.Figure B.5.3.6 shows the basic relationship of the seven modules. The model may be.operated probabilistica11y.In this mode, RED randomly selects values for key model parameters from frequency distributions in the model's data files.The model may also be operated on a deterministic basis,whereby only one set of forecasts is produced based on a single set of average input variables.When operated probabilistically,the RED model begins with the Uncertainty Module,which selects a trial set of values for model parameters to be used by other modules.These parameters include price elasticities,appliance saturations,end-use consumption per square foot of business floor space,and regional load factors.Exogenous forecasts of population, employment,and households from the MAP model,plus retail prices for fuel oil,gas,and electricity are used with the model's parameters by the Residential Consumption and Business Consumption Modules to produce forecasts of electricity consumption.These forecasts,along with additional trial parameters,are used in the Program-Induced Conservation Module to simulate the effects of government programs that subsidize or mandate the market penetration of certain technologies that reduce the need for power.This program-induced component of conservation is in addition to those savings that would be achieved through normal consumer reaction to energy prices.The consumption forecasts of residential and business (commercial,small industrial,and government)sectors are then adjusted to reflect these additional savings.The revised forecasts are used to estimate future miscellaneous consumption and total sales of electricity.These forecasts and separate assumptions regarding future major industrial loads are used along with a trial system load factor to estimate peak demand. 851104 After a complete set of projections is prepared, begins preparing another set by returning to the Module to select a new set of trial parameters. B-5-29 the model Uncertainty After 851104 several sets of projections have been prepared,they are formed by RED into a frequency distribution to allow the user to determine the probability of occurrence of any given load forecast.When only a single set of projections is needed,the model is run in deterministic mode whereby a specific default set of parameters is used and only one trial is run.This deterministic formulation was used to produce alternative load forecasts for the Susitna Hydroelectric Project. The RED model produces projections of electricity consumption by load centers and sectors at five-year intervals.A linear interpolation is performed to obtain yearly data. The outputa from the RED model runs are used by the Optimized Generation Planning (OGP)model to plan and dispatch electric generating·capacity for each year.The remainder of this section presents a description of each module in the RED model. ··(-0 Uncerta-intyModule-(*) When used in probabilistic mode,the purpose of the Uncertainty Module is to randomly select values for individual model parameters that are-considered most subject to forecasting uncertainty.These parameters include the market saturations for major appliances c"~~-in~-the~.residentcialc-sectorc;--the~pr"ice~elasHc i tyand cross-price elasticities of demand for electricity in the residential and business sectors;the intensity of electricity use per square foot of floorspace in the business sector;and the electric system load factors for each load center. These parameters are generated by a Monte Carlo routine,which uses information on the distribution-of--eachparameter(such""asTfs·expectecf··val ueana.·_· range)anClthe computer's ranClom numoergeneratoi'-fo- produce sets of parameter values.An overview of information flows within the Uncertainty Module is given in Figure B.5.3.7.Each set of generated parameters represents a "trial".By running each successive trial set of generated parameters through the rest of the modules,the model builds distribu- tions of annual el.aC:tricityconsumptiona.nd peak dem,fcid~The end points bf each distribtition reflect the probable range of annual electric consumption and peak demand,given the level of uncertainty. B-5-30 1 ,J 851104 The Uncertainty Module need not be run every time RED is run.The parameter file contains "default"values of the parameters that may be used to conserve computation time.In the current study,the RED model was used in deterministic mode for all forecasts.Default values for the parameters were set at their most probable level. (ii )Hous ing Module (*) The Housing Module calculates the number of households and the stock of housing by dwelling type in each load center.The Housing Module's structure is shown in Figure B.5.3.8.Using regional forecasts of households and total population,the housing module first derives a forecast of the number of households served by electricity in each load center.Next,using·..,exogenous statewide forecasts of household headship rates and age distribution of Alaska's population,it estimates the distribution of households by age of head and size of household in each load center.Finally,it forecasts the demand for four types of housing stock:single family units,mobile homes,duplexes,and multifamily units. The supply of housing is calculated in two steps. First,the supply of each type of housing from the previous period is adjusted for demolition and compared to the demand.If demand exceeds supply, construction of additional housing begins immediately.If excess supply of a given type of housing exists,the model examine$the vacancy rate in all types of houses.Each type is assumed to have a maximum vacancy rate.If this rate is exceeded, demand is first reallocated from the closest substitute housing type,then from other types.The end result is a forecast of occupied housing stock for each load center for each housing type in each forecast year.This forecast is passed to the Residential Consumption Module. (iii)Residential Consumption Module (*) The·Residentia1 Consumption Module forecasts the annual consumption of electricity in the residential sector.The Residential Consumption Module employs an end-use approach that recognizes nine major end-uses of electricity,and a "small appliances"category that encompasses a large group B-5-3l 851104 of other end uses.In addition to space heating,the major end uses are water heaters,cooking,-clothes dryers,refrigerators,freezers,dishwashers,clothes washers,and saunas and jacuzzis.Figure B.5.3.9 shows the calculations that take place in this module. For a given forecast of occupied housing,the Residential Consumption Module first adjusts the housing stock to net out housing units not served by an electric utility.It then forecasts the residential appliance stock and the portion using electricity,stratified by the "type of dwelling and vintage of the appliance.Appliance efficiency standards and average electric consumption rates are applied to that portion of the stock of each appliance using electricity and the corresponding consumption rate.to derive a preliminary consumption forecast for the residential sector.Finally,the Residential Consumption Module receives exogenous forecasts of resident ial fuel oil,natural gas,and electricity prices,al()ng wit1:J.values of price elasticities and cross-price elasticities of demand from the Uncertainty Module.It adjusts the preliminary cons~ption forecast for both short-and long-run price effects on appliance use and fuel switching.The adjusted forecast is passed to the Program-Induced Conservation Module. The Business Consumption Module forecasts the consumption of electricity by load center for each forecast year.Because the end uses of electricity in the commercial,small industrial,and government sectors are more diverse and less known than in the residential sector,the Busine$s Consumption Module 'forecasts'e-lectrical'useon-anaggregate-basisrather--. ~~~-l;-han-by-end-us·e,,·---:-F-igure-B.-5..3.10--pr'es·ent-s--a---------.-- flowchart of the module. RED uses a proxy (the stock of commercial and industrial floorspace)for the stock of capital equipment to forecast the derived demand for ..electricity •.Usingan.exogenous forecast of regional employment,the module forecasts the regional stock ·of·floorspace.-Next,.ecoI10111efric equatioI1s are used to predict the intensity of electricity use for a given level of floors pace in the absence of any relative price changes.Finally,a price adj ustment B-5-32 J ] 1 j similar to that in the Residential Consumption Module is appl ied to derive a forecast of business' electricity consumption.This total excludes large industrial demand,which is exogenously determined. The Business Consumption Module forecasts are passed to the Program-Induced Conservation Module. (v)Program-Induced Conservation Module (*) Battelle developed this module for the State of Alaska,Office of the Governor (Battelle 1982, Volume VIII)to analyze potential large scale conservation programs that would be subsidized by the State of Alaska.This module permits explicit treatment of government programs which could foster additional market penetration of technologies and programs that reduce the demand for utility-generated electricity.The module structure is designed",to incorporate assumptions on the technical performance, costs,and market penetration of electricity-saving innovations in each end use,load center,and forecast year. The module forecasts the additional electricity savings by end use that would be produced by government programs beyond that which would be induced by market forces aione.It also forecasts the costs associated with these savings,and adjusted consumption in the residential and business sectors. In the current study,this module was not used. Existing conservation programs are being phased out and there are many uncertainties regarding the future of long term government conservation programs.The impact of past program-induced conservation is reflected,however,in the historical electricity consumption values used to initialize the model. 851104 (vi)Miscellaneous Consumption Module (*) The Miscellaneous Consumption Module forecasts total miscellaneous consumption for second (recreation) homes,vacant houses,and street lighting.The module uses the forecast of residential housing stock to predict electricity demand in second homes and vacant housing units.The sum of residential and business consumption is used to forecast street lighting requirements.Figure B.5.3.ll provides a flowchart of this module. B-5-33 851104 (vii)Peak Demand Module (*) The Peak Demand Module forecasts the annual peak demand for electricity.The annual peak load factors were based on an analysis of historical Railbelt load patterns •.A two-stage approach using load factors is used.The unadjusted residential and business consumption,miscellaneous consumption,plus load factors are used to forecast preliminary peak demand.Separate estimates of peak demand for major industrial loads are then added to compute annual peak demand for each load center.Figure B.5.3.12 provides a flowchart of this module. (viii)Input Data (*) There are five input data files to the RED model. One of the five,CONSER,which contains data on program-induced conservation,was not used in this project.The other four are described as follows. The RDDATA file contains output data of the MAP model,including load center population,households, and employment,plus state households by age group. The file also contains the real prices (in 1980 dollars)of fuel oil and natural gas,by load center and end-use sector. The RATE DAT file contains the real prices of elec- .t:.:t:'i.~:i.ty ..by-I_Qild .~ellt_exandend ..usesec tor._These prices are derived from present costs of electricity adjusted to future conditions based on the OGP results. The PARAMETER file contains the numerical values for certain parameters,incl uding housing demand coefficients;saturation rate of electrical appliances;floors pace elasticities;short-t.erm and tong-;;;.-term'own.;;;,;price-,iindcro ss-;;;';price-eTast fcTEres for' ·_·---,-e-l'e-c·tri-crty-,-fue-r-o'i-l--;-atla-n:~ftur-a-l ga sT-and-ann u~n-­ load factors. The EXTRA DAT file contains information on the annua 1 electrical consumption and peak demand of large industrial projects. ex)RED Model Output (*) The RED output report contains various tables generated by the program.The main tables include the following: B-5-34 '.J I .j II o Number of households for each load center, forecast year (1980,1985,and at five-year intervals to 2010),and type of housing (single family,multifamily,duplex,and mobile homes) o Residential appliance saturations for each load center,forecast year,and type of housing o Residential use per household before price elasticity adjustments for each load center, forecast year,and appliance category (small appliance)large appliance,and space heat) o Business use per employee before price elasticity adjustments,for each load center and forecast year o Electric energy requirements,including price adjustments,for each load center,year,and category of consumption.·(residential,business, miscellaneous,incremental conservation savings,large industrial,and total) o Peak electric requirements for each load center and year Output from the RED model is used as input in the OGP computer model for the purposes of analyzing alternative expansion programs. (e)Optimized Generation Planning (OGP)Model (*) The OGP program was developed over 20 years ago by General Electric Company (GE)for two reasons.First,to combine the three main elements of generation expansion planning (system reliability,operating costs,and investment costs), and second,to automate the decision analysis for additions to the generating system.The following description of the model was extracted from GE literature and the Descriptive Handbook (GE 1983). The first task in selecting the generating capacity to install in a future year is the reliability evaluation.The evaluation uses either percent installed reserves or loss-of-Ioad probability (LOLP)to answer the questions of how much capacity to add and when it should be installed.A production costing simulation is also done to determine the operating costs for the generating system with the given unit additions.Finally,an investment cost analysis of the capital costs of the unit additions is performed.The 851104 B-5-35 851104 operating and investment costs help to answer the question of what kind of generation to add to the system.-Figure B.5.3.l3 outlines the procedure used by OGP to determine an optimum generation expansion plan. The next three sections (reliability evaluation,production simulation,and investment costing)review the elements of these computations.The OGP optimization procedure is then described,followed by a discussion of the input and output files. (i)Reliability Evaluation (*) Historically,electric utility system planners measured generation system reliability with a percent reserves index.This planning design criterion compared the total installed generating capacity to the annual peak load demand.However, this approach proved to be a relatively insensitive indicator of system reliabib~ty,particularly when comparing alternative units whose size and forced outage rate-varied.. Since its introduction in 1946,the measure that has gradually gained widest acceptance in the inqustry is "loss-of-load probability"(LOLP).The LOLP method is a probabilistic de-termination of the expected number of days per year on which the demand exceeds .the~-avai-lable-Ga-paGit-Y-·cL~~It:~factorsintothe-­ reliability calculation the forced and planned outage rates of the units on the system as well as their sizes.An LOLP of 1 da.y illl0 years a usual industry standard. Computing LOLP requires an identification of all outage events possible (in a system with n units, this means 2n events)and then a determination of"""Ehepr-obabTi":lty-of each-ouEag-ee-venE:-"However,··sInc-e -LOLP-rs concerned-wrEnsys tem ca pad ty-outages-and--- not so much with particular unit outages,the probability of a given total amount of capacity on outage is calculated. Utilizing a highly efficient recursive computer technique ,capacityoutage--tables are -calculated .directly ...from a.list of__JJll_:iJ:rcktings __cmd forced oi.ifagera te s. The LOLP for a particular hour is calculated based on the demand and installed capacity for the hour.The B-5-36 ,I[; reserves are given by capacity minus demand.On this basis,a deficiency in available capacity CLe.,loss of load)occurs if the capacity on forced outage exceeds the reserves.The probability of this happening is read directly from the cumulative outage table and is the LOLP for a single hour. In addition to calculating the percent installed reserves,OGP can also calculate a daily LOLP (days/year).The daily LOLP is determined by summing the probabilities of not meeting the peak demand for each weekday in the year.The hourly LOLP is calculated by summing the probabilities of not meeting the load for all the hours in the year. (ii)Production Simulation (*) Once a system with sufficient generating capacity has been determined by the reliability evaluation,the fuel and related operating and maintenance (O&M) costs of the system must be calculated.OGP doe.s this by an hourly simulation of a typical weekday and weekend day for each month of system operation. The program commits and dispatches generation so as to minimize costs.However,the -user has the option of biasing or overriding the normal economic operation of the system.This can be accomplished in two ways.The user may specify weighting factors for various environmental parameters such that the program will operate those units to minimize their impact.The user may also limit,on a monthly basis, the number of hours that units may run or the amounts of different fuels that may be consumed. The production simulation in OGP is performed in six steps: o Load modification based on recognition of contructual purchases and sales; o Conventional hydro scheduling and its associated load modification; o Monthly thermal unit maintenance scheduling based on planned outage rates; o Pumped storage hydro or other energy storage scheduling; 851104 B-5-37 o Thermal unit commitrilentfor the rema~n~ng loads based on economics and/or environmental factors,spinning reserve rules,and unit cycling capabilities;and o Unit dispatch based on incremental production costs and environmental emissions.The production simulation is for a single utility system or pool.Unrestrained power transfer capability is assumed between areas or companies internal to the pool represented. (iii)Purchases and Sales (*) The OGP production cost lo·ad model is an hour-by-hour model of a typical weekday and weekend day for each month,arranged in monotonically decrea'sing order. These hourly loads are modified to reflect the firm purchases and sales between the area being studied and entities outside that area.Each contract has associated with it a demand charge ($/kW/yr)and an energy "'charge ($!kWh);, (iv)Conventional Hydro Scheduling (*) -] I. (v)Thermal Unit Maintenance (*) .-------_._------_._-_._--_...-----._----------'---- 851104 The power and energy availabl~from any conventional hydroelectric project used in a simulation is divided into two types:base load and peak load.The basec l'oadenergythatmust beccproducedis account-ed for by subtracting a constant capacity from every hourly ~oad in the month as shown on Figure B.5.3.14.This capacity value is referred to as the plant minimum rating.A£terthis baseload energy is used,any remaining energy available is used for peak shaving.I.n such si tuations,the program uses the remaining capacity and energy of the hydro unit to -.J:'e.c:l.uc_ELthe .p-~JlltlQ~4~g~.~_l,ll;_1:l_g~_p()_~Sl ~'l>l§!-,,_!.t~llY excess energy exists at the end of a month,a user-specifi-ed maximUJiJ.storage amount can be-carifeci' forward into the next month. On a utility system,the planned maintenance of iridi'ifiduaT -iiiiipr is--usually'performed oll a monthly basis.During these periods,the units are unavai.1a bie .fo-retle-rgy procltic Hon.Maintenance scheduling is normally done so as to minimize the effect on both system reliability and system operating costs.A common strategy for scheduling B-5-38 I ) ) Ij maintenance,and the method used in OGP,is the levelized reserves approach.The monthly peak loads are examined throughout the year,and incremental amounts of generating capacity maintenance are scheduled to try to levelize the peak load plus capacity on maintenance throughout the year. Increased maintenance levels which might be required during the first few years of a unit's operation are modeled using an immaturity multiplier.OGP also allows the user to annually input a predetermined maintenance schedule for units for which this information is available. (vi)Thermal Unit Commitment (*) After modifications for contracts,hydro,unit maintenance~Land energy storage,the remaining loads must be served by the thermal units on the system.In OGP,the units can be committed to minimize either the operating costs,as is usually done,or some combination of user specified environmental factors and operating costs.The operating costs are calculated from the fuel and variable O&M costs and input-output curve for each unit.Fixed O&M costs do not affect the order in which units are committed,but are included in the total p~oduction cost. The unit commitment logic determines how many units will be on-line each hour and also attempts to provide an adequate level of operating reliability while minimizing the system operating costs and/or environmental emissions.The operating reliability requirement is met by committing sufficient generation to meet the load plus a user specified spinning reserve margin.Units are committed in order of their full load energy costs or emissions, starting with the least expensive. 851104 (vii)Thermal Unit Dispatch (*) If a unit is committed,the unit's m~nunum loading level requires that its output be at that level or higher.When the final commitment has been established,each unit will be loaded to at least its minimum.Typically the sum of the minimums does not equal the load.Additional load will be served by the units'incremental loading sections.The dispatching function in the OGP production B-5-39 851104 simulation loads the incremental sections of the units committed in a manner which serves the demand at minimum system fuel cost or emissions.This dispatch technique is known as the equal incremental cost approach. (viii)Investment Costing (*) The investment cost analysis in OGP calculates the annual carrying charges for each generating unit added to the system.This is computed based on a $/kW installed cost,a kW nameplate rating,and an annual levelized fixed charge rate. (ix)OGP Optimization Procedure (*) For the year under study,a reliability·eval.uation is performed.This determines the need for additional generating capacity.If the capacity is sufficient,the program calculates the annual production and investment costs,prints these values, andproceeds ...to the next ..year •. If additional capacity is needed,the program will add units from a list of available additions until the reliability index is ~et.For each combination of units added to the system,OGP does a production simulation and investment cost calculation for the y-earunder s ..tudy.The....program~mLest ..he.....iJ;li9~J;J!I.a~i9 n .gained from the cost calculations to logically step through the different combinations of units to add, eliminating from consideration comQinations that 'would produce higher annual costs than previously found.This process continues until the expansion giving the lowest annual costs is found.The selected ~hits are added to the system,and the proceeds to the next year of the study • ........ ·-In-cas~e~s~..'tYh-e-r·e(:fJ:ferift·in·g~c·o·s·t-i:n·f·la·ti:on·-and-lor--time-· variation in unit outage rates are present,the OGP optimization logic utilizes a look-ahead feature. The look-ahead feature develops levelized fuel and O&M costs and applicable outage rates for use in the economic evaluation.As part of the output informa- ·..tion·available:;theuserobtainsdocumentation of the· relative costs of a.ll the alternatives examined. Afterthe"generating unit selection,the reliability and costing calculations are repeated for the chosen alternative so that the expansion report available for the user contains the correct annual values. B-5-40 .1 851104 (x)Input Data (*) There are two major input files to OGP:the Generation file and the Load file.The Generation file model is created for use as a data base representing the in-service and on-order generating units.For each unit,the following characteristics are described: o Types of Generator o Unit sizes and earliest service year allowable 0 Unit costs 0 Fuel types and costs 0 Operation and maintenance costs..., 0 Heat rates 0 Commitment minimum uptime rule 0 Forced outage rates 0 Planned outage rates The Load file is specified by the user to represent peak and shape characteristics which are projected to occur for the years included in the OGP study.The user supplies the following load shape data: o Annual peak and energy demand o Month/annual ratios o The 0 percent,20 percent,40 percent,and 100 percent points on the peak load duration curve, by month o Typical reference weekday and weekend-day hourly ratios by month In addition to these two input f~les,the user uses the Data Preparation (DP)program and the Generation Planning (GP)program to run the OGP model.The DP program produces standard tables which describe the thermal and hydro options.Included are tables for plant capital,O&M,and fuel costs;inflation patterns,planned and forced outage rates;minimum B-5-41 851104 loading points;and environmental data.The GP program includes input data on loss of load probability criteria,hydro firm energy,economic parameters,and output options. (xi)Output Data (*) Output options have been designed and included in OGP to provide the user with flexibility in the level of detail and volume of documentation received. Complete output reports as well as summary outputs are available. The output available from the OGP program includes the following info.rmation: o Listing of the input data o Standard tables,as defined by the user,for various unit characteristics o Listitlg ofth~lltl:i..t types and sizes available for optimization and their characteristics o Listing of the Load file for the study period o Listing of the generating units o~the system and their characteristics o Year-by:-year summary 0 the fIrm contracts input by the user o Production simulation summaries,listing all of the generating units of the system with their energy output,fuel and O&M costs,fuel consumption,and ~nvironmental emissions. These summaries can be obtained on a monthly or annual basis:;'for all"the decision pass esor ....~..-·~"j'ust~·t·he'opt'imum-~sys·tem------~"--·-"-'-'--..~---~~ o Summary of all the expansion alternatives,with their associated costs and reliability measures,evaluated during the optimization oS.ummaries,of thefinaLsys tem expans ion through time and the associated costs B-5-42 ! ] .1 5.3.2 -Model Validation (*) The APR,MAP,and RED models are used to simulate future conditions based on alternative assumptions concerning world and state economic conditions and electricity demand in the Railbelt.Mea~ures that have been taken to ensure that the models simulate economic and electricity utilization conditions and relationships as accurately as possible are summarized below. (a)APR Model Validation (***) As noted earlier,the APR model is a simplified, deterministic version of the Alaska Department of Revenue's probabilistic PETREV model.To test the ability of the APR model to reproduce PETREV's results,both results were compared for the March 1985 mean petroleum revenue case.The APR forecast performed as follows for the 17 year PETREV forecast period: Maximum underestimate Maximum overestimate·" Average difference :0.1.6% 2.0% 0.9% (b) 851104 The PETREV model is used..by ADOR to produce a probabil ity distribution of new revenue forecasts each quarter.Table B.5.3~1 -illustrates how the range and mean for FY1985 total revenues have varied since the September 1983 forecast. Each successive forecast becomes increasingly more reliable as the forecast period draws nearer,reflecting the increasing reliability of the data used in the model.The curr~nt model formulation has not been in use long enough to estimate its long term accuracy. MAP Model Validation (0) Validation of the MAP model has been accomplished using two separate but interrelated techniques.First,a standard set of statistics was computed for each of the stochastic parameters used in the MAP model equations.These statistics provide information on the expected accuracy of each coefficient and the probability that each coefficient expresses the correct relationship between variables •. Second,the MAP Model was tested to determine the accuracy with which it could simulate observed historical conditions. (i)Stochastic Parameter Tests (*) Stochastic parameters are,as indicated previously, coefficients computed using regression analysis,a B-5-43 statistical procedure whereby the quantitative relationship between variables is estimated by one or more computed coefficients. Most of the equations in the economic module of the statewide economic model are computed using regression analysis. In estimating coefficients using regression analysis a number of statistics are computed.These statistics indicate the accuracy of the coefficient and the overall efficiency of the equation in estimating the true value of the dependent variable. Among these statistics are t-values,R2, Durbin-Watson statistic,and the standard error of regression.They are used both in selecting the best independent variables for estimating a given dependent variable and in determining the expected accuracy of the final equation. These statistics have been computed for each Sl:_O~bc1istic eqU.;ition tlseci i.J:ll:heMA:p Model.In each equation efforts have been made to obtain the highest possible values for these statistics .in order to ensure that the model re-flects actual economic relationships as accurately as possible.As a resul~ of this effo-rt all the coefficients used in the MAP Model have a relatively high level of statistical (iO Simulation of Historical Economic Conditions (*) Although the MAP Model has 'been in use since 1975, analyses condueted for the Susitna Hydroelectric Project were the first applications of the model in long range projection of economiccoJ:lditions. Previous applications of the model had been in --analys-es-e>f-ece>nomicef-fe e-ts --ofalt-ernative-s-tate ..'..-."--. -..----.----------------npol-i-ci-es-.--Ii:-i-s-not--pos-si-b-le-,-there-fore,---to--tes-t the model's long-term projection accuracy using old forecasts.However,the model's accuracy was tested by simulating historical economic conditions by executing the model utilizing historical data and input variables.Table B.5.3.2 summarizes the results of simulation of selected.historical conditions.The table shows that the MAP Model reproducesh-i-stol:'-iccil--condit-ions -with remarkable accuracy,in a period when significant growth and structural change occurred.The model's performance is acceptable for periods showing markedly different .j I 851104 B-5-44 growth characteristics,such as during pipeline construction and during both pre-and post-pipeline development. (c)RED Model Validation (**) The accuracy of the RED Model was assessed by utilizing the MAP model's historical simulation of employment,popula- tion,and numbers of households;actual historical heating degree days;and actual historical energy prices to predict electricity consumption by sector and load center.The MAP historical simulation was considered superior to actual employment and population statistics because the actual series contain random and short-term disturbances that have little to do with planning and developing stocks of energy-using capital equipment.In addition,the model was run and adjustments were made using the best e'stimates of 1980 through 1983 economic drivers and fuel prices.Table B.5.3.3 summarizes the results of comparing the SHCA case with actual utility data for 1980 through 1983.The ,.m historical period used in the analysis was brief because of the lack of available data for the end-use forecasting model.Complete historical data on end-use (fuel mode split,appliance saturation,end-use energy consumption, etc.)are only available for 1980.Therefore,the accuracy tests which can be performed on the model are limited. Even though the RED model is a long-term forecas ting model which uses 5-year interval inputs,it produces forecasts that are fairly close to actual values in the short term. When the forecast is adjusted for weather conditions and price changes,the Anchorage-Cook Inlet residential and business sectors and the Fairbanks-Tanana Valley business sector closely match the actual values for consumption in most years.The Fairbanks-Tanana Valley residential sector is 15 to 20 percent high in all years but 1980.The probable cause is that existing electric heating equipment is not being utilized;rather,wood is being used to provide much of the heat in the area's residential sector.In Battelle-Northwest's residential survey (described in Scott,King and Moe 1985),wood was listed as an alternative heat source in 53.5 percent of dwellings ha.ving only one alternative and as the primary fuel in 16.3 percent of all homes. The other difference is that Fairbanks-Tanana Valley forecasted business consumption is growing faster than its actual value as shown in Table B.5.3.3.This is partly due to the fact that,until recently,square footage per employee had been growing slowly to absorb the post-pipeline 851104 B-5-45 building stock.Fairbanks square footage per employee may soon increase again in response to a downtown redevelopment plan involving major hotel and convention facilities. 5.4 -Forecast of Electric Power Demand (**) Two companion load forecasts,plus a third sensitivity case,have been produced following the methodology discussed in Section 5.3.This section discusses the three forecasts.First,there is a discussion of the data input to the APR,MAP,RED,and OGP models for the two companion forecasts.This is followed by a detailed presentation of the two companion forecasts and a briefer discussion of the third sensitivity forecast.Next,there is a discussion of the many sensitivity tests performed to estimate the impact of various input assumptions on model output.Finally,there is a brief discussion of other load forecasts and their relationship to the Susitna project studies. 5.4.1 -Variables and Assumptions (**) Many variables and assumptions are used in the..APR,MAP,RED,and OGP models etescribed.in Section 5.3 •....Inpuj:variables for each of these models are discussed in the following paragraphs. (a)APR Model (**) State petroleum revenues from North Slope oil-production are expected to account annually for between 93 and 99 percent ~...of s ta te .J>etroleum_~royalties an_(Lp-roductionl;c9..xe~<!l,g:j.!1cg the period 1985 to 2012.Remaining royal ties and production taxes will be generated by petroleum production on state lands in Cook Inlet and from production of natural gas on the North Slope and Cook Inlet.The input to the APR model is therefore focused primarily on North Slope oil,and secondari lyon Cook Inlet oil,North Slope gas,and Cook Inlet gas • .-.···-As--sta-te-d-in Si?H:tion-S;3-;-theint>uttoth·e·APR-tnodelts .----~---.._.-..-.~-~-.taken-direc-t-ly-from-the-kla-ska~Depa-rtment-o-f-Revenue-'-s--.------.-.-.. PETREV model except for two variables:world oil price and Cook Inlet gas price.Three forecasts of petroleum revenue have been prepared,each associated with a different world oil price forecast and its companion gas price forecast. The three oil price cases include forecasts made by Sherman H.Clark Associates (SHCA)and Wharton Econometrics,as well as a Composite cas.e representing the average forecast of ----several--ptibl--ic agencies and private forecasting organizations.This discussion focuses on the SHCA and Composi te cases.All three oil price forecasts are shown on Table B.5.4.l and in Figure B.5.4.l.A detailed discussion .] j ._j~.~ I 1 851104 B-5-46 of the forecasts appears in Exhibit D,Appendix D1. Other input to the APR model for the SHCA and composite cases are shown on Table B.5.4.2.Of the factors listed on Table B.5.4.2,North Slope petrolemn production has the largest potential impact on state petrolemn revenues. Projected North Slope petrolemn prod~ction is the smn of projected production from several fields:Prudhoe Bay-Sadlerochit,Kuparuk,Milne Point,Endicott,Lisburne, West Sak Sands,Seal Island,and unspecified onshore fields. Currently only Prudhoe Bay-Sadlerochit and Kuparuk are producing fields.The other fields are projected to begin production between 1986 and 1997.The currently producing fields are projected to remain the main producers, accounting for 72 percent of total North Slope production in 2000 and 79 percent in 2010. While production rates during the next eight to ten years can be fOl:1ecasted with some degree of certainty,production rates after this period will depend on the rate of exploration and development of oil fields.Exploration rates will depend largely on the level of world petrolemn prices and the demand for petrolemn,but development of oil fields will depend on oil discoveries and production costs as well as petrolemn prices and demand. (b)MAP Model (*) Table B.5.4.3 lists ten categories of exogenous or basic employment,one measure of tourism,five categories of II )1·petrolemn revenues,and four national economic parameters that are used as input to the MAP model.These factors are the principal input variables and parameters to the MAP Model. For the current studies,the values of all the variables listed in Table B.5.4.3 other than petrolemn production tax and royalty revenues were left unchanged during each of the MAP model executions.Sensitivity tests indicated that varying the value of several of these factors produced demonstrable effects on economic projections.Based on results of sensitivity tests,the key input factors to the MAP model other than petrolemn revenues are:state mining employment,which includes petrolemn production;state active duty military employment;tourists visiting Alaska; U.S.real wage growth rate;and price level growth rate. Employment relating to construction of the Susitna Hydroelectric Project was not included in the analysis. Construction employment for electric power generating stations that would be required in the absence of the 851104 B-5-47 project is included in the larger category of construction employment. Table B.5.4.4 summarizes the basis for selecting the values for the variables listed in Table B.5.4.3.The values for many of the variables listed have been developed from the MAP model Data Base (Goldsmith et al.1985),a volume of economic and demographic data compiled and maintained by the Institute of Social and Economic Research.These data are derived from information collected by various state and federal governmental agencies,published reports,and other sources.The data are organized,adjusted,and in the case of some variables,projected to the year 2010 to meet the input requirements of the MAP model. (c)RED Model (*) Table'B.5.4.5 lists the main variables that are used in each module of the RED model.In the Uncertainty module, the fuel price forecasts,the housing demand coefficients, the saturation of residential appliances,and the price adj ustmerit~coefficiei::l.tsarethemaiIfvatiables. Tables B.5.4.6 and B.5.4.7 show the projected customer real prices of heating fuel oil,natural gas,and electricity for the SHCA and Composite cases,respectively.The heating fuel oil price forecast was derived from the 1983 actual price,escalated at the same growth rate as the world oil ---~--~-~p-rt-ce~i:ll-~fat:h---ca;-se-FThe--tta~turCa-l-ga~s~pri-:'c'e~~foreca-st·for the- Anchorage-Cook Inlet area was derived from average price (old and new contracts)of natural gas.The new contract prices were estimated as a function of the world oil price. In the Fairbanks-Tanana Valley area,a continuation of the present practice of using propane for heating was assumed. The price escalates with world oil prices.Retail electricity prices were calculated as a function of the .1evelized_production ...cost.sforeach_~ca.se._.~.Theproduction_~ ___~costs were estimated by-earlier OGP resultslQL~he_l!am~ cases.All fuel prices shown in Tables B.5.4.6 and B.5.4.7 are expressed in 1980 dollars,the base year used in the RED model. Table B.5.4.8 presents the housing demand coefficients which were used in the housing demand equations for single family, -'-~"-'-murHfami1Y,-arid mobile~J:iom~S.TableB.5~4~9 gives ari ~:lC.anlPl~••1:)ftna:t:'kel:•.sa tt1l:'~l:~Ql!~()~=appl~.9.l!c~l;:il!..•s ing!efam i~y homes for the Anchorage-Cook Inlet area,and Table B.5.4.10 presents the parameter values of the price adjustment mechanism. '1 '~'.''"1 ,j 851104 B-5-48 ,J 851104 (d) For the Housing module,the two main variables are the regional household forecast,and the state households by age group.These variables are directly obtained from the MAP output file. The main variables in the Residential module include households by dwelling type and various appliance characteristics.Tables B.5.4.ll,B.5.4.l2,and B.5.4.l3 provide detailed information on the percent of appliances using electricity,the annual consumption and growth rate of residential appliances,as well as the survival rate of the existing and new appliances. The main variables of the Business Consumption module are regional employment,which is an output of the MAP model, and the floors pace consumption parameters listed on Table B.5.4.l4.Vacant housing,second homes and street lighting, and their expected annual consumptian are the variables of the Miscellaneous module.The ann~l load factor for the two load centers are the main variables of the Peak Demand module. Of the many variables included in the RED model,several can be identified as key variables.Because the RED model is an end-use model,the appliance saturation rate based on the existing stock of appliances is important.Also,the energy usage per appliance has a major effect on electricity demand.Further,the growth rate of consumption per appliance type has a significant impact on residential electricity consumption in future years.In the business sector,the projections of the demand for floorspace and the consumption per unit of floorspace are key variables.Own- and cross-price elasticities of demand have a significant impact on electricity consumption by influencing consumption behavior in both the short and long term.The own-price elasticity values that are assumed in the model determine the extent and time path of electricity price impacts on residential and commercial consumption.The cross-price elasticities show the impact on electricity consumption due to changes in the price of substitute energy resources for electricity.The own-and cross-price elasticities of demand are used to adjust electricity consumption for price-induced conservation of electrical energy.The last key factor is the regional peak load factor,which is applied to the energy demand forecast to forecast peak loads. OGP Model (0) Table B.5.4.15 presents the main variables of the OGP model. The variables are:fuel costs and escalation rates, B-5-49 thermal and hydro plant construction costs,and the discount rate.A detailed presentation of these variables -is given in Exhibit D and Exhibit D,Appendix D1. 5.4.2 -Load Forecasts (**) A total of three load forecasts were made.Two are discussed here,while the third --a low bound sensitivity case --is presented in Section 5.4.3.The two cases presented here are associated with the two petroleum price forecasts discussed earlier,Le.,the SHCA and composite cases. As described in Section 5.4.1,the petroleum prices served as the basis for the state petroleum revenue forecasts,which in turn comprised one of the inputs to the MAP model.The MAP model produced economic projections which were then used by the RED model to forecast electric energy demands. Tables B.5.4.16 and B.5.4.17 summarize the data for the SHCA and Composite cases,showing the oil price scenarios and a corresponding set of input and output prices of other forms of energy,revenues,population,and employment.Table B.5.4.16 shows that in the SHCA case,Railbelt population will grow approximately 33 percent between 1985 and 2010,reaching 506,384 by the year 2010.During this same period the Railbelt's electric energy demand is forecasted to rise from 3,323 to 4,929 gigawatt-hours,a 48 percent increase.Peak demand is projected to rise from 632 to 938 megawatts,a 48 percent increase during the--25-;1-ear_period~-and....-an~-a:v:erage-annual--grow~th~rateoLl.6 percent.Similarly,Table B.5.4.17 indicates that under Composite case assumptions,Railbelt population would be expected to grow by 32 percent by the year 2010.During the same period, the Railbelt's electric energy demand would rise to 4888 gigawatt~hours,a 47 percent increase.Peak demand is projected to rise to 930 megawatts. The following sections summarize the SHCA and Composite case...----.-,.,-"".,---------"'--fo'r'ec-~i's-ts--'-o·r'--s-Ea'-te-·-·pe-tr'oI-e"um-""·--reveiiue-s·-~···--"·f-is-c-a-l·-'·-'and--e-c·c)"ti()TQlc· con at-t-ions,anaelectric energy aemand-.-Decailed--illput-ana- output values for both cases appear in Tables B.5.4.18 through B.5.4.43. (a)State Petroleum Revenues (**) --c_.Table B.5.4-.18 presents SHCAcase-projections of state petroleum revenues from each of the prima-ry revenue sources through the year 2010~The first two columns ()f this table contain projected royalties and severance,or production,taxes,respectively.These projections are in nominal dollars,reflecting an annual change in the J J -] 851104 B-5-50 consumer price index of 5.5 percent.The projections of royalties and severance taxes through the year 2010 were produced by the Department of Revenue's APR petroleum revenue forecasting model.The same revenue information for the Composite case appears on Table B.5.4.19. Tables B.5.4.18 and B.5.4.19 also present projections of state petroleum revenues derived from corporate income taxes,property taxes,lease bonuses,and federal shared royalties.Forecasts of future revenues from these sources were used,along with the projections of royalties and severance taxes,as input to the MAP economic model. In nominal terms,as indicated on Tables B.5.4.18 and B.5.4.19,petroleum revenue is expected to rise-and fall in cycles over the forecast period.In real terms,however, petroleum revenue is expected to fall continuously after 1987.In the SHCA case,real petroleum revenue is forecast to decline by 71 percent between 1987 and 2010,while contributions to the general fund (net of permanent fund contributions)fall by 73 percent during the same period. In the Composite case,total petroleum revenue and contributions to the general fund are forecast to fall by 74 percent and 76 _.percent,respectively. (b)Fiscal and Economic Conditions (**) State petroleum revenues constitute a major,but declining, portion of the.total funds available to the State of Alaska for expenditure on operations and capital investment, which in turn affects the general level of economic activity in the state.The impact on economic activity,however,is not directly proportional to the decline in petroleum revenue.Basic sector economic activity is expected to continue to expand as it has in the past.This growth will include--in varying degrees--all of Alaska's resources but would continue to be dominated by petroleum and mining. Federal civilian and tourism employment will grow;although mi Ii tary employment will continue its secular decl ine. Manufacturing employment will be minimal. This continuing,but gradual,expansion of basic activities will be the growth trend underlying several indentifiable phases in the economy in future decades.Four periods can be characterized as pause,renewed growth,structural realignment,and the post-Prudhoe economy. The economy is expected to enter a flat period in the immediate future as the economy adjusts to lower petroleum prices as well as the excess capacity produced during the 851104 B-5-51 rapid growth years of the early 1980s.The primary forces driving the economy-construction,state and local government,petroleum employment--will stop growing or contract,causing the economy to pause.This pause in new job creation will result in net out~igration which will slow,but not eliminate growth in population and households. Toward the end of the decade,economic growth is expected to resume as oil prices begin to rise and petroleum and mining activity increase.Activity in the state and local government sectors will be augmented by new revenue measures,including reimposition of the income tax and transfer of Alaska Permanent Fund earnings to the General Fund for annual appropriations.These measures maintain the existing employment level in government but are not sufficient for expansion of government employment. Toward the end of the century,the decline in petroleum revenues resultin;g;;;.from the depletion of the Prudhoe Bay field will become more pronounced,leading to a marked contraction in state-and local-government-activity,which will continue through 2010.This is initially a period of slow growth,marked by a structural realignment of the economy as the public sector contracts absolutely as well as in p~rcentage terms. As this realignment continues,the economy eventually will ---~-enter what--mightbe-character-ized-as-the~post"""l'.rudhoe.-Bay era.State and local governments are less dominant forces in the economy,and growth will be more closely related to private sector basic activities. During this period,growth in population and the number of households will be primarily the result of natural increase. The annual addition of new jobs to the economy will be the growth in the labor supply resulting in net out-migration in...._..._.---..·--maiiy-ye-~irs-:-B-e-causethe-averag-e--househoTd-sIzewIII---- ...·_-·---conEinue its-downwara.treiia-;-tfie growtnin tnenumoero-f-~­ households will exceed that of population.The labor force participation rate will remain high so that the proportion of the population at work will stay relatively constant. Table B.5.4.20 presents projections of several important components·of the state's fiscal structure for the SHCA case,while TableB.5.4.21 presents the same information for theCoiiipositecase.These c6iiiponentsincl'ude unrestricted general fund expenditures,the balance in the general fund, permanent fund dividends,state personal income tax revenues,level of outlays for subsidies,and the percentage 851104 B-5-52 of Permanent Fund earnings that are added to the general fund.Table B.5.4.20 shows that,based on the fis·cal rules summarized in Section 5.3 above,dividends from the Permanent Fund continue to be disbursed through the year 1990 in the SHCA case,at which time the program is halted. A state personal income tax is reinstituted in the year 1992 in order to augment revenues.State subsidy programs are terminated after the year 1990,and reinvestment of Permanent Fund dividends ends after 1992.Table B.S.4.21 indicates that in the Composite case,maintenance of general fund expenditures requires the same actions,in the same years,as in the SHCA case. However,while these fiscal measures are assumed to be implemented,petroleum revenues are projected to continue to provide a large share of state expenditures,accounting in the year 2010 for approximately 42 percent of total unrestricted general fund expenditures (those expenditures not funded by revenues dedicated to specific functions)in the SHCA case.Petroleum revenues constitute ap~roximately 39 percent of unrestricted general fund expenditures in 2010 in the Composite case. l\ 851104 (i) (ii) Population (***) Table B.5.4.22 pr~sents SHCA case population projections for the state,Rai lbelt"Anchorage-Cook Inlet area,and Fairbanks-Tanana Valley area.The state population is forecast to increase by 30 percent.Railbelt population is projected to grow by approximately 33 percent between 1985,from 381,264 to 506,384.In the Railbelt,the Anchorage area is projected to grow by 34 percent,compared to the projected growth in Fairbanks of 27 percent.Table B.5.4.23 indicates that in the Composite case,growth rates would be 32,34,and 26 percent in the Railbelt,Anchorage,and Fairbanks,respectively. Employment (***) The growth of employment in the SHCA case is shown on Table B.5.4.24.While statewide non-agriculture wage and salary employment is projected to grow by 33 percent during the next 25 years,total state employment is forecast to increase by only 29 percent.Again the Railbelt is projected to experience a higher employment increase,rising by 34 percent,with the Anchorage area growing by 35 percent compared to 29 percent growth in the Fairbanks area. B-5-53 Table B.5.4.25.Total state employment is forecast to grow by 29 percent,while Railbelt growth is 33 percent over the same 25 year period.The Anchorage and Fairbanks areas are forecast to grow by 34 and 29 percent,respectively.- (iii)Households (***) Table B.5.4.26 presents household projections for the SHCA case according to state total,the Railbelt, the Anchorage area,Fairbanks area,and statewide by age of head of household.Households are projected to increase faster than population.Statewide households are projected to increase by 37 percent by the year ·.2010,compared to a 39 percent increase in the Railbelt,a 40 percent rise in the Anchorage area,and a 34 percent increase in the Fairbanks area.Household growth in the Composite case is slightly lower than in the SHCA case,showing 36 percent growth in the state,38 perQent in the Railbelt,40 percent in the Anchorage area,and 33 percent in the Fairbanks area.The figures are shown on Table B.5.4.27. (c)Electric Power Demand (**) (i)Households Served and Vacant £ouseholds (***) The-regional households -proJections-obtained from the MAP model are used in the RED housing module to derive the number of households served by electric utilities and the number of vacant households. Tables B.5.4.28 and B.5.4.29 present the number of households served in the SHCA and Composite cases, respectively.Tables B.5.4.30 and B.5.4.31 present the number of vacant households by case.The residential module then computes the annualco-nsumptTonper--typeoI ---househoI d·-bas-edon-the ·market·_· ...···saturationof-appriances andt'fi"eannua-l--consumpTion- per appliance. (ii)Residential Electricity Use Per Household (***) Table B.5.4.32 summarizes the average consumption per ..--·householdbefore and-after-conservation adjustment anCl.-fuel substitution int:heSHCA case.In the Anclior~rge-area;-the average-consumption per household is expected to decrease from about 11,700 kWh in 1985 to 10,100 kWh in 2000,mainly due to the real increase of electricity price which will continue to I 1 I j ·1 851104 B-5-54 j 851104 cause so~e conversion from electric space heating to substitute fuels.After 2000,the consumption is expected to slowly increase to about 10,300 kWh in 2010,at an average annual growth rate of less than one percent.In the Fairbanks area,the average household consumption is expected to increase from 12,400 kWh in 1985 to 14,500 kWh in 2010,at an average annual growth rate of about one percent. This increase is due to the stabilization of electricity prices,while the prices of substitute fuels are increasing.The projected consumption per household in year 2000 is similar to the 1975 average consumption. Table B.5.4.33 summarizes the average consumption per household in the Composite case.The use per household is essentially the same as for the SHCA case. (iii)Business Use Per Employee (***) The employment forecasts obtained from MAP are used in the RED Business Consumption module to derive the electric demand in the business (commercial-government-small industrial)sector. Table B.5.4.34 summarizes the business use ~per employee projections for the SHCA case.The consumption projections were obtained from a forecast of predicted floorspace per employee,and an econometrically derived electricity consumption per square foot,which is then adjusted for price effects.The floorspace per employee is expected to increase at the Anchorage historical rate until 2010, bringing square footage per employee close to the 1979 U.s.national average.As a result,in the Anchorage area,the average consumption per employee is expected to increase from about 8,700 kWh in 1980 to about 10,000 kWh in 2010,at an average annual rate of less than one percent.In the Fairbanks area,the consumption per employee is expected to increase from about 8,100 kWh in 1980 to 12,000 kWh in 2010,corresponding to an average annual growth rate of 1.3 percent. As indicated in Table B.5.4.35,business electricity use per employee in the Composite case is expected to be similar. Table B.5.4.36 provides a year by year projection of price-induced conservation and fuel switching for the B-5-55 851104 two load centers in the SHCA case,while Table B.5.4.37 provides the same information for ·the Composite case.Tables B.5.4.38 and B.5.4.39 give a year by year breakdown of energy consumption projections for the residential,business (commercial-government-small industrial), miscellaneous,and large industrial sectors for the two load centers for the SHCA case.Tables B.5.4.40 and B.5.4.41 present the composite case.The industrial sector includes projections of large industrial and military loads.Industrial loads were derived from estimates of industrial growth in the Kenai Peninsula.Military loads were derived from discussions with representatives at each military installation. Finally,Tables B.5.4.42 and B.5.4.43 sunmarize the annual peak and energy demand projections for each load center and for the total system for the SHCA and Composite cases,respectively.In the SHCA case,the averge annual growth rate of electricity demand is expected to slowly decrease from about ·1.5 percent during the period 1985-1990 to 0.6 percent during the period 1995-2000.After 2000,the demand is expected to increase at an average annual rate of 1.5 percent.until 2005,and 2.7 percent for the period 2005-2010.In the ComposIte case,the rates of change are essentially the same. 5.4.3 -Forecast Comparison (***) In addition to the SHCA and Composite cases,the Wharton case was carried through the MAP and RED models.The results are presented on Table B.5.4.44.Projections of population, households,energy demand,and peak demand are displayed in Figures B.5.4.2 through B.5.4.5 for all three cases. As Shawn 'iii ..Figiire"':B ~.5~4:'2~-the"Rairoertpopu ration-is expected ---~to-ill"c-rea-s"e-from-381-;300-in-t98S-to-Lf99-';-200-in····tn.e-Wnartonca s e and 506,400 in the SHCA case,for the year 2010.The corresponding number of households,shown in Figure B.5.4.3, would increase from·134,300 in 1985 to 184,000 or 187,000. Railbelt employment is expected to increase from 181,900 in 1985 to 240,300 under the Wharton case,and 243,200 in the SHCA case. As shown onFigureB.5.4.4,the 2010 energy consumption would be between 4,900 and 5 ;100 GWh in aU-'cases ."The corresponding average annual growth rate over the period 1985-2010 would be appJ;oximately 1.7 percent.The peak demand shown in Figure B-5-56 1 ,) ! } "1 \) B.5.4.5,is expected to increase from 630 MW in 1985 to approximately 950 MW in 2010 in all three cases. 5.4.4 -Sensitivity Analysis (**) Sensitivity analyses for a number of variables were conducted using the MAP,RED,and OGP models in order to determine the extent to which forecasts are affected by varying the values of selected input variables and parameters. (a)MAP Model Sensitivity Tests (**) The Susitna License Application as accepted by FERC in July 1983 (APA 1983)contained a summary of several MAP model sensitivity tests •.At that time,input variables subjected to sensitivity testing included ten industrial development factors,tourism in Alaska,and four national economic variables,as well as a number of other parameters not reported in the License Application.The results indicated that of the variables tested,projections of households are most sensitive to mining employment,which includes petroleum production;military employment;tourism;growth in real wages;and growth in the consumer price index. An additional set of tests was made during the autumn of 1984.The results of these tests are shown on Table B.5.4.45.The first three tests (TEST 0,1,2)investigated the effect of adding new and revised data such as updated population and wage and salary figures to the data base. Three tests (TESTS 3,3S,4)were undertaken to assess the sensitivity o~model simulations to the econometric methods used to estimate the stochastic equation coefficients,and one test (TEST 5)redefined the form of the relationship between support industry gross product and income.Three tests (TEST 6,6R,6T)compared the effects of various petroleum corporate income tax levels,while one test (TEST 7)holds royalty,severance tax,and petroleum corporate income taxes constant.One test (TEST 8)assumes very high levels of petroleum revenues and petroleum employment.One test (TEST 9)determines the gross effect of Susitna construction on the state economy (without netting out the displaced economic activity associated with meeting Railbelt power demands by some other means). Additionally,three tests (CTST lOA,lOB,laD)gauged simulation sensitivity to varying certain state government policies,such as increasing the return on the Permanent Fund balance from 3 to 4 percent,combining no reintroduction of the income tax with perpetuation of the 851104 B-5-57 permanent fund dividend,and permanent elimination of the income tax alone. One test (CTST 11)examined the combined effects on households of a decline in the labor force participation rate and a related change in average household size. Finally,four tests (TEST 9.82, 9.81,9.80,9.79)were made to determine how sensitive the support sector equations are to the extension of data series to termination points in 1982, 1981,1980,and 1979. The results indicate that the forecast of households is most sensitive to 1)high exogenous estimates of petroleum-related employment,and 2)a declining labor force participation rate accompanied by a declining average household size.The latter effect is large because changes in labor force participation are usually correlated with changes in household ~ize,creating more households in a given population. (b)RED Model Sensitivity Tests (**) Sensitivity analyses were conducted for key variables,using the data files from the Uncertainty Module.These variables include (1)appliance saturations,(2)business consumption and the trend in.square feet of business floorspace per employee,(3)own price eiasticity,(4)cross price elasticity,(5)the lagged adjustment factor,and (6) 10a~L factors.J'he ..senslt:ivity analyses were~.!:lx:r_l~d.Qut f.Qr the SHCA Case.The results are shown on Tables B.5.4.45 through B.5.4.49.Although these sensitivity tests were based on earlie~RED Model runs using prices that are slightly different,the results are similar to the current cases. Table B.5.4.45 summarizes the results obtained when appliance saturations were allowed to vary.Table B.5.4.9 ............._......fffeSrerits-'a"typica le-xanfpIe·'ofmafket'-sfaturat-ioff ·rangeswnich ......--..·-·~----cwere-us·e·d-as--input-·-into-the-Uncertai:ntrModu-l-e-;'."'The-'- saturations were allowed to vary over their entire range (in some instances,+10 percent)•.As shown on Table B.5.4.45,the results on the overall energy demand are within 1 percent of the test case values •. .The sensitivity analysis.o.ftheBusinessSector was done by allowing the consumption rate parameter to vary within a range 'approximately-corresponding--to 'a95'percent confidence interval.This resulted ina range of values within +20 percent of tl:lemean value for the Anchorage-Cook Inlet area. As shown on Table B.5.4.46,the effects on the overall .1 "'j .(I, j 851104 B-5-58 energy demand are within 20 percent of the test case values. Because of the lack of detailed historical data for the Fairbanks area,the range of the consumption parameter value was set by assumption and the results of the Monte Carlo test reflect this assumption. Tables B.5.4.47 and B.5.4.48 present the results of the own-price and cross-price elasticities variations.The values of the parameters were allowed to vary within an assumed range of minus 16 percent to plus 40 percent for own price elasticity,plus or minus 100 percent for oil price elasticity,and plus or minus 40 percent for gas price elasticity.This roughly corresponds to a 95 percent confidence interval.The effects on the overall energy demand are within plus 5 percent to minus 2Q percent of the test case values. Finally,a sensitivity analysis was done for the peak demand,using the range of the annual load factors of the two load centers for the period 1970-1982.The results are presented in Table B.5.4.49.For the year 2010,the peak residential plus commercial demand would vary between 925 and 1187 MW,with a test case value of 1030 MW.No range has been specified for industrial demand;however,the total 2010 ftemand levels that would be forecast with 75 percent and 25 percent confidence are 1032 MW and 1212 MW, respectively,compared to the reference value of 1085. I) (c)OGP Model Sensitivity Tests (**) Sensitivity tests were also conducted for the OGP Model. The key variables other than petroleum price which were tested are base fuel price,discount rate,Watana construction cost,real coal price escalation and natural gas availability.The sensitivity analyses are described ~n Exhibit D. 5.4.5 -Comparison with Previous Forecasts (**) Previous power demand forecasts have been used in earlier stages of the Susitna Hydroelectric Project studies.In 1980,the Institute for Social and Economic Research (ISER)prepared economic and accompanying end-use electric energy demand projections for the Railbelt.These forecasts were used in several portions of the feasibility study,including the development selection study.The forecast is shown on Table B.5.4.50. In 1981 and 1982,Battelle Pacific Northwest Laboratories produced a series of load forecasts for the Railbelt.These forecasts were developed as,a part of the Railbelt Alternatives 851104 B-5-59 Study completed by Bat telle under contract to the State of Alaska.Battelle's forecasts were based on updated economic projections prepared by ISER and some revised end-use models developed by Battelle which took into account price sensitivity and several other factors not included in the 1980 projections. The December 1981 Battelle forecast used in the optimization studies for the Watana and Devil Canyon developments is shown on Table B.5.4.50. Another series of load forecasts was made to support the Susitna License Application as accepted by FERC in 1983 (APA 1983).The reference case forecast is shown on Table B.5.4.50.The reference case and other forecasts were made following the same procedures described in Section 5.3.They reflect an ongoing process of model refinement,pI us the ..updating of underlying ecqnomic assumptions. In addition to the forecasts made for the purpose of.planning the Susitna Hydroelectric Project,the Railbelt utilities annually produce fo.reca-sts for their own respective markets.The sum of the current Railbelt utility forecasts is shown on Table B.S-.4.50. Table B.5.4.50 provides a summary comparison of these previous power market forecasts.While these forecasts are not precisely consistent in the definitions of the market area or in the assumptions relating to the current reference c·ase,the comparison does provide an insight into the change in·perception .·o·f-...futut'eg-rowthra-t es.dur-ing.-the-"timec.."that--the~vaI'ious--sets of forecasts were developed. 5.4.6 -Impact of·Oil Prices on Forecasts (**) The world price of oil is a significant factor in the Alaskan economy.As a consequence,world oil prices influence the demand for electric energy and other forms of energy.Although oil prices are important,there are many other economic,social,'anci""polItTcaT'factors'whIchaffecE·"·fuEur-eAT"iskari'economicErends·. -and-energy req uirement"5':~-----...--'.--------.-.----.--------..---..----..--..--..-------- Among the factors which mitigate the impact of declining oil prices on the level of economic activity in Alaska are the following: o'.Other basic industries-,--unre-latedctopetroleum,exist independent of the oil industry in'Alaska and will continue to d6 56. o The presence of the petroleum industry in Alaska has already transformed the Alaska economy,creating an 851104 B-5-60 ,I ) ./ J l.1 infrastructure and a degree of economic maturity that would not be undone if the oil industry declines in importance. o The current level of petroleum producing activity in the state is relatively insensitive to oil price changes within a wide range,because continued operation of existing fields requires only sufficient revenue to cover low field operating costs.(Lower petroleum prices do,however,have a more dramatic impact on exploration and development of new fields). o Diversion of a portion of past petroleum revenue into the State's Permanent Fund,plus reinvestment of Permanent Fund interest,has provided the state with a cushion against falling petroleum revenues in the future.Interest on the Permanent Fund could be channeled into the General Fund (as is assumed in the MAP model)to help maintain the level of operating and capital expenditures. The impact of world oil prices on future.eco,nomic conditions and electric energy and peak demands can therefore best be understood by reviewing the load forecasting procedure.First,a number of world oil price scenarios were used in the APR Model to generate various petroleum revenue projections.Because royalties and severance taxes are sens.itive to changes in world oil prices, different petroleum 'revenue projections were obtained.Next,the projected petroleum revenues along with specified economic development assumptions and other variables were employed in the MAP Model to project economic factors such as households,state government expenditures,and employment.These economic factors were influenced by the various oil price growth rate assumptions, but were also influenced by other economic factors which tend to mitigate the impact of petroleum revenues alone.Finally, electric demand forecasts were produced using the RED Model.The RED Model employed the output of the MAP Model as well as other assumptions and input data.The fuel price data used in the RED Model for electricity,natural gas,and heating oil are affected by the growth rates assumed for world oil prices.An electric demand forecast was made for each world oil price scenario.This procedure resulted in the production of electric demand forecasts which incorporated all direct and indirect effects of a given timepath of world oil prices on electric demand in the Railbelt in a comprehensive and consistent manner.The ·range of electric demand forecasts reflects the overall impact of world oil prices as well as other key variables included in the separate models. 851104 B-5-61 i II. 6 -FUTURE SUSITNA BASIN DEVELOPMENT (*) Development of the proposed Susitna Hydroelectric Project would preclude further major hydroelectric development in the Susitna basin,with the exception of major storage projects in the Susitna basin headwaters.Although these types of plans have been considered in the past,they are neither active nor anticipated to be so in the foreseeable future. 851104 B-6-1 1 .) 1 \ f ) ] I ,I I I I 1 ·1 I ) 1 1 J 1 -_.__-------.----_.__.__._---.,-.___.._--_..------__..-_..----_.._._--------___--,-.._---_---_.._---.---------.-----_._-----_-.-.-_.___--_._-..- J 7 -REFERENCES Acres American Inc.1981.Susitna Hydroelectric Project,Development Selection Report.Prepared for the Alaska Power Authority. •1982a.Susitna Hydroelectric Project,Feasibility Report (7---Volumes).Prepared for the Alaska Power Authority. •1982b.Susitna Hydroelectric Project,1982 Supplement to the---1980-81 Geotechnical Report.Prepared for the Alaska Power Authority. •1982c.Susitna Hydroelectric Project,Subtask 8.02.Closeout---Report.Electrical System Studies.March 1982. Acres American Inc.and Terrestrial Environmental Specialists Inc. 1982.Transmission Line Selected Rout~.Prepared for the Alaska Power Authori ty. Alaska Department of Fish and Game.1978a.Alaska's Fisheries Atlas (Volumes I and II).Anchorage,Alaska. •1978b.Habitat Essential for Fish and Wildlife on State Lands.---Anchorage,Alaska. Alaska Department of Revenue.1985.Petroleum Productio~Revenue Forecast.Petroleum Revenue Division. Alaska Economics Inc.1983.Alaska's Economic Potential:Background. March,1983. Alaska Power Administration.1984.Alaska Electric Power Statistics (1960-1983).Ninth Edition.U.S.Department of Energy.Sept. Alaska Power Authority.1983.Susitna Hydroelectric Project FERC License Application,Project No.7114-000. •1985.Susitna Utility Meeting -Results of Sensitivity Analy~is.---June 19,1985. Battelle Pacific Northwest Laboratories.1981.End Use Survey. Unpublished report. •1982.Railbelt Electric Power Alternatives Study (17 Volumes).---Prepared for the Office of the Governor,State of Alaska. December,1982. •1983.RED Model (1983 Version)Documentation Report.--- Brown,A.C.1985.The Policeless State of OPEC.Fortune.112(2):52. 851104 B-7-1 Burns and McDonald.1983.Report on Power Requirements Study for Chugach Electrical Association. CIRl/Holmes and Narver.1980.Susitna Hydroelectric Project,Subtask 2.04.Land status maps.Prepared for Acres American Inc. Chow,V.T.1964.Handbook of Applied Hydrology.McGraw-Hill. Clarke,T.S.1985.Glacier Runoff Balance and Dynamics in the Upper Susitna River Basin,Alaska.A thesis presented to the University of Alaska,Fairbanks in partial fulfillment of the requirements for the degree of Master of Science. Commonwealth Associates Inc.1980.Anchorage-Fairbanks Transmission Intertie-Transmission System Data.Prepared for the Alaska Power Authority. Data Resources Inc.1983.U.S.Long-Term Review. Energy Probe.1980.An Evaluation of the ISER Electricity Demand Forecast. ExxonCorp.-T984.MiddleEast Oil arid Gas.Public:Affairs Department. New York,New York.40 pp. French ,M.1985.Long Term Outlook for Petroleum Prices.Wharton Econometric Forecasting Associates,Philadelphia,PA. Friese,N.V.1975.Pre-Authorization Assessment of Anadromous Fish -.-----POI:lUlaEIons-of-tne-Upper-S-iis-itha·RiverWat:er-snealtfthe-Vicinrty of the Proposed Devil Canyon Hydroelectric Project.Alaska Department of Fish and Game ,Divisionof Commercial Fisheries. General Electric Co.1983.OGP6 User's Manual.March~1983. Goldsmith,S.and L.Husky.1980.Electric Power Consumption for the Railbelt - A Projection of Requirements.Prepared for State of ··Alaska,Ho us ePower-Al-terna.tives Study--Committ ee__andAlas ka Power .... -.-..-------.Author-it¥-.J_une_,__L9SO-.__._.....__ Goldsmith,S.,T.Hull and S.Colt.1985.Monitoring the Performance of the Alaska Economy:The 1985 ISER MAP Economic Database.Institute of Social and Economic Research,University of Alaska.April, 1985. Harrison,W.D.1985.Susitna HydroelectricProject,Glacier Mass Balance and RunoffStuqy ..JJJ:liyer'si.t:y Qf.A,laI31ta,Fairbanks, Geophysical Institute.Prepared for Harza-Ebasco Sus tna·Joint Venture. i .j 1 ·1 .J 851104 B-7-2 lJ Harza-Ebasco Susitna Joint Venture.1984.Evaluation of Alternative Flow Requirements.Final Report.Prepared for Alaska Power Authority,Anchorage,Alaska.55 pp. Institute of Electrical and Electronics Engineers.1977.symposium on Reliability Criteria for System Dynamic Performance.IEEE Power Engineering Society 1977 Winter Meeting.pp.15,34,36. •1982.Power System Reliability Evaluation.IEEE Tutorial Course. pp.54,56. Institute of Social and Economic Research.1980.Electric Power Consumption for the Rail be 1 t:A Projection of Requirements, Technical Appendices.Prepared jointly for State of Alaska House Power Alternatives Study Committee and Alaska Power Authority. •1981.Alaska Economic Projections for Estimating Requirements for the Rai1be1t.Prepared for Battelle Pacific Northwest Laboratories.October,1981. •1983.MAP'~ode1 Technical Documentation Report.June,1983. •1985.MAP Modeling System Documentation.Compiled by O.S. Goldsmith,University of Alaska. Manne,A.S.and L.Schrattenho1zer.1985.International Energy Workshop:A Progress Report. Morrow,J.E.1980.the Freshwater Fishes of Alaska.Alaska Northwest PubliShing Co.,Anchorage,Alaska. R &M Consultants Inc.1981a.Terrain Analysis of the North and South Intertie Power Transmission corridors.Prepared for Acres American Inc. •1981b.Susitna Hydroelectric Project,Regional Flood Studies. Prepared for Acres American Inc. •1981c.Susitna Hydroelectric Project,Glacier Studies.Prepared ----for Acres American Inc. •1982a.Susitna Hydroelectric Project,1982 Susitna Basin Glacier ----Studies.Prepared for Acres American Inc. •1982b.Susitna Hydroelectric Project,Tributary Stability ----Analysis.Prepared for Acres American Inc. 851104 B-7-3 Scott,M.,M.J.King and R.J.Moe.1985.Review and challges to the Railbelt Electricity Demand Model.Pacific Northwest Laboratories. Sebasta,D.1978.Lowering Reliability Offers Little Benefit. Electrical World.190(7):pp.70-71. Sherman H.Clark Associates.1983a.Evaluation of World Energy Developments and Their Economic Significance,Volume II.Prepared for Harza-Ebasco. ___•1983b.Long-Term Outlook for Crude Oil and Fuel Oil Prices. Prepared for Harza~Ebasco. Sherman H.Clark and Associates.1985.Oil Price Outlook.Prepared for Harza-Ebasco Susitna Joint Venture,Anchorage,Alaska. Stahr,T.R.1983.Personal communication.General Manager,Municipal Light and power.Letter to D.Glascock,Harza-Ebasco Susitna Joint Venture,June 22,1983. Trihey,E.W.1981.Susitna Hydroelectric Project,Instream Flow Assessment :Issuefdent:rUcat:ion and Bas-eHne 1jat:aArialysis,1981 Study Plan.Prepared for Acres American Inc. u.S.Department of Agriculture,Soil Conservation Service.1979. Exploratory Soil Survey of Alaska.Washington,D.C. u.S.Army Corps of Engineers.1975.Program Description and User Manual --fo-rStreamf16wSYntnesis and-I1eservoir Regura:tion CS-SA1nn:U~S-. Army Corps of Engineers,North Pacific Division.Portland, Oregon. Woodward-Clyde Consultants.1980.Forecasting Peak Electrical Demand for Alaska's Railbelt.Prepared for Acres American Inc.December, 1980. --.-1982.--Final Report·on-Seismic·--Studies-forSusitnaHydroelectric-------_______Pro.J_ect..Prepared_fOIAc:ies -American.Inc -Eebr_uar.y_,_1.982-.-~-. -1 ] J 851104 B-7-4 TABLES l J J 1 j 1 j 1 TABLE B.1.3.1:POTENTIAL HYDROELECfRIC DEVELOPMENT Capital Average Economicl/ Dam Cost Installed Annual Cost of Source Proposed Hel.gh t Ups tream $million Capacity Energy Energy of Site Type Ft.Regulation (1980)(MW)GWh $/1000 kWh (1980)Data Gold Creeld Fill 190 Yes 900 260 1,140 37 USBR 1953 0180n11 (Susitna Up Concrete 160 Yes 600 200 915 31 USBR 1953 KAISER 1974 COE 1975 Devil canyo~Concrete 675 No 830 250 1,420 27 This Study Yes 1,000 600 2,980 17 " High Devil t.nyon "(Susitna I)Fill 855 No 1,500 800 3,540 21 " Devil Creek I Fill Approx No 850 Wa tana I Fill 880 No 1,860 800 3,250 28 " Sus itna III Fill 670 No 1,390 350 1,580 41 " Vee I Fill 610 No 1,060 400 1,370 37 " Maclaren Fill 185 No 530~/55 180 124 " Denali Fill 230 No 480.1:1 60 245 81 " Butte Cree I Fill Approx No -40 1303 -USBR 1953 150 Tyonell Fill Approx No -6 22 3 -USBR 1953 60 1/Include AFDC,Insurance,Amortization,and Operation and Maintenance Costs.2/No deta led engineering or energy studies undertaken as part of this study.3/These a e approximate estimates and serve only to represent the potential of these two damsites in perspective.~/Include estimated costs of power generation facility. TABLE B.1.3.2:mST COMPARISONS A C RES 1980 Capital DAM Site Gold Creek Olson (Susitna II) Type Fill Concrete Installed Capacity -MW i Capital Cost $mi llion Cost EstimateV Ins talled Capacity -MW 2601/ 1901/ (1980 $) OTHERS Capi tal Cos t $million 890 550 Source and Da te of Data USRB 1968 mE 1975 Devil Canyon Fill :Concrete Arch :Concrete Gravity High Devil Canyon Fill (Susitna I) 600 800 1,000 1,500 776 776 700 630 910 1,480 mE 1975 mE 1978 COE 1975 Devil Creek Watana SusitnaIII Vee Maclaren Denali Fill Fill Fill Fill Fill Fill 800 350 400 55 60 1,860 1,390 1,060 530 480 792 445 None 1,630 770 500 COE 1978 KAISER 1974 COE 1975 COE 1975 1/Dependable Capaciity 1/Excluding Anchorage/Fairbanksit~ansmissioninter~ie,but including local access and transmission. ~~<------.- TABLE B.1.3.3:DAM CREST AND FULL SUPPLY LEVELS Staged Full Dam Average Dam -- Dam Supply Crest Tailwater Heigh tl/ Site Construction Level -Ft.Level -Ft.Level -ft.ft. Gold Creek No 870 880 680 290 Olson No 1,020 1,030 810 310 Portage Creek No 1,020 1,030 870 250 -Devil Canyon - intermediate heigh t No 1,250 1,270 890 465 Devil Ca nyon - full height No 1,450 1,470 890 675 High Devil Canyon No 1,610 1,630 1,030 710 No 1,750 1,775 1,030 855 Watana Yes 2,000 2,060 1,465 680 Stage 2 2,200 2,225 1,465 880 Susitna III No 2,340 2,360 1,810 670 Vee No 2,330 2,350 1,925 610 Maclaren No 2,3'95 2,405 2,300 185 Denali No 2,540 2,555 2,405 230 1/To foundation level TABLE 'IB.i .4.1:CAPITAL COST ESTIMATE SUMMl\RIESSUSITNA BASIN DAM SCHEMES (CO$T IN $MIllION 19BO) Devil Ca~yori High Devil Canyo~Watana Susitna III Vee Maclaren Denali I : 1470 ft ~rest 1775 ft Crest 2225 ft Crest 2360 ft Crest 2350 ft Crest 2405 ft Crest 2250 ft Crest Item 600 MW 800 MW BOO MW 330MW 400 MW No power No power 1)lands,Damages &Reservoirs 26 ,11 46 13 22 25 38 2)Diversion Works 50 4B 71 88 37 lIB 112 3)Main Dam 166 432 536 39B 183 106 100 4)Auxiliary Dam 0 0 0 0 40 0 0 5)Power System 195 232 244 140 175 0 0 6)Spillway Syst.em 130 141 165 121 74 0 0 7)Roads and Bridges 45 6B 96 70 80 57 14 8)Transmission line 10 10 26 40 49 0 0 9)Camp facilities and Support 97 140 160 130 100 53 50 10)Miscellaneousl!8 8 8 8 8 5 5 11)Mobilization and Preparation 30 47 57 45 35 15 14 Subtotal 757 1137 1409 1053 803 379 333 Contingency (20%)152 227 282 211 161 76 67 Engineering and Owner's Administration (12%)91 136 169 126 96 45 40 TOTAL 1000 ,1500 1860 1390 1060 500 440 ! 1-1 ;, Includes recreational facilities,buil~ings and grounds and pe:rmanent operating equipment. ~-------' '-~---'--~~'-~-"-------~-----_..-'-'..--~----------- TABLE B.1.4.2:RESULTS OF SCREENING MDEL To al Demand Optimal Solution First Suboptimal Solution second Suboptimal Soultion M9x.lust.Total M9x.lust.Total M9x.Inst.Total Cap Energy Site Water Cap.Cost Site Water Cap.Cost Site Water Cap.Cost Run }M GWh Names Level }M $million Names Level }M $million Names Level }M $million 1 400 1750 HiW:t 1580 400 885 Devil 1450 400 970 Watana 1950 400 980 Devil Canyon Canyon 2 800 3500 HiW:t 1750 800 1500 Watana 1900 450 1130 Watana 2200 800 1860 .Devil Canyon I I I Devil Canyon 1250 350 710 I I 'IOIAL 800 1840 3 120C 5250 Watana 2110 700 1690 HiW:t .1750 800 1500 HiW:t 1750 820 1.500 Devil Devil Canyon .Canyon Devil 1350 500 800 Vee.2350 400 1060 Susitna 2Dl 380 1260 Canyon III 'IOIAL 1200 2490 'IOIAL 1200 2560 'IOIAL 1200 2760 4 14(X 6150 Watana 2150 740 1770 NO SOLUTION NO SOLUTION Devil 1450 660 1000 Canyon 'IOIAL 1400 2770 i ! J TABLE B.1.4.3:INFORMATION ON THE DEVIL CANYON DAM AND TUNNE,4 SQHEMES J 1 1 1I·Devil Canyon •Tunnel Scheme Item j Dam j 1 j 2 I 3 ~4 I 1 1 j I 1IIII•Reservoir Area I I ••I (Acres)I 7,500 I 320 I 0 1 3,900 j 0 1 ,•••)River Miles 1 I I I I Flooded I 31.6 I 2.0 1 0 I 15.8 I 0 I I I I I JTunnelLengthIj•1 i (Miles)I 0 I 27 I 29 I 13.5 j 29 •I ••I ITunnelVolumeIIIjj (1000 Yd 3 )1 0 1 11,976 j 12,863 1 3,732 1 5,131 j 1 j I j Compensating Flow 1 j j I j -1Release(cfs)I 0 I 1,000 j 1,000 j 1,000 j 1,000 1 I I I 1 I I I I i 1ReservoirVolumeI1iIj (1000 Acre-feet)I 1,100 I 9.5 I J 350 I 1 j 1 I I jDamHeightII I I j (feet)I 625 i 75 ,I 245 "I ,I.I I I I lTypicalDailyIjI J I I Range of Discharge I 6,000 j 4,000 j 4,000 8,300 3,900 !from Devil Canyon I to I to I to to to Powerhouse (cfs)I 13,000 j 14,000 j 14,000 8,900 4,200 I j I IApproximatejII maximiirii'aaify j Reservoir (feet) 1 I ] 1 ..j 1 TABLE B.1.4.4:DEVIL CANYON TUNNEL SCHEMES COSTS,POWER OUTPUT AND AVERAGE ANNUAL ENERGY Installed Devil Canyon Increasel!in Tunne 1 Scheme Cost21 of Capacity (MW)Increasel!in Average Annual Average Total Project Additional Watana Devil Canyon Installed Capacity Energy Annual Energy Costs Energyl Stage Tunnel (MW)(GWh)(GWh)$Million (mills/kWh) STAGE 1: Watana D m 800 .§.IlillL2: Tunnel: -Scheme 1 BOO 550 550 2,050 2,050 19BO 42.6 -Scheme 2 70 1,150 420 4,750 1,900 2320 52.9 -Scheme J2/B50 330 3BO 2,240 2,lBO 1220 24.9 -Scheme 4 BOO 365 365 2,490 890 1490 73.6 1-1 Inc~ease over single Watana,BOO MW development 3250 GWh/yr 2-1 Includes power and energy produced at re-regulation dam 3-1 Energy cost is based on an economic analysis (i.e.using 3 percent interest rate) CAPITAL COST .ESTIMATE SUMMARIES TUNNEL SCHEMES COSTS IN $MILLION 1980 Item TABLE B.1.4•5: Two 30 ft dia tunnels One 40 ft dia tunnel J j } Land and damages,reservoir clearing Diversion works Re-regulation dam Power system (a)Main tunnels (b)Intake,powerhouse,tailrace and switchyard Secondary power station Spillway system Roads and bridges Transmission lines Camp facilities and support Miscellaneous Mobilization and preparation TOTAL CONSTRUCTION COST Contingencies (20%) Engineering,and Owner's Administration TOTAL PROJECT COST 14 35 102 68'0 557 123 21 42 42 15 131 8 47 1,137 227 136 1,500 .... 1 1 I J l i 1 I .1 ] 1 (i TABLE B.l.4.6:SUSIrNA DEVELOPMENT PLANS (Page 1 of 3) Cumulative Stage/Incremental Data System Data Annual Maximum Energy Capital Cost Earliest Reservoir Seasonal Production Plant $Millions On-line Full Supply Draw-Firm Avg.Factor Plan)Stage Construction (1980 values)Datel/Level -ft.down-ft GWh GWh % 1.1 I 1 Watana 2225 ft 800MW 1860 1993 2200 150 2670 3250 46 2 Devil Canyon 1470 ft 600 MW 1000 1996 1450 100 5500 6230 51 TOTAL SYSTEM 1400 MW 2860 1.2 I 1 Watana 2060 ft 400 MW 1570 1992 2000 100 1710 2110 60 2 Watanaraise to 2225 ft 360 1995 2200 150 2670 2990 85 3 Watana add 400 MW capacity 130.£/1995 2200 150 2670 3250 46 4 Devil Canyon 1470 ft 600 MW 1000 1996 1450 100 5500 6230 51 TOTAL SYSTEM 1400 MW 3060 1.3 I 1 Watana 2225 ft 400 MW 1740 1993 2200 150 2670 2990 85 2 Watana add 400 MW capacity 150 1993 2200 150 2670 3250 46 3 Devil Canyon 1470 ft 600 MW 1000 1996 1450 100 5500 6230 51 TOTAL SYSTEM 1400 MW 2890 TABLE B.l.4.6 (Page 2 of 3) ptage/lncremental Data Cumulative System Data Plan Stage Construction Capital Cost $Millions (1980 values) Earliest Reservoir On-line Full Supply Datel/Level -ft. Maximum Seasonal Draw'- down-ft. Annual Energy Production Firm Avg. GWh GWh Plant Factor % MW 2.1 2.2 2.3 3.1 1 2 1 2 3 1 2 3 1 2 Highi Devil Canyon 1775 ft 800 MW Vee 2350 ft 400 MW TOTAL SYSTEM 1200 MW High'~~Yil Canyon 163(>,ft 400 MW. HighJDevil Canyon addi400 MW capacity raise dam to 1775 f Vee 2350 ft 400 MW TOTAL:SYSTEM 1200 MWI High i Devil Canyon 1775:ft 400 MW High i D~vil Canyon addi400 i MW capacity Vee 2350 ft 400 MW TOTAL SYSTEM 1200 MW ! i I Watana2225 ft 800 ~ Watana add 50 MW . tunnel 330 MW TOTAL SYSTEM 1180 i 1500 1060 2560 1140 500 1060 2700 1390 140 1060 2590 1860 1500 3360 1994~l! 1997 1993J/ 1996 1997 19941/ 1994 1997 1993 1995 1750 2330 1610 1750 2330 1750 1750 2330 2200 1475 ~-~". 150 150 100 150 150 150 150 150 150 4 .~ 2460 3400 3870 4910 1770 2020 2460 3400 3870 4910 2400 2760 2460 3400 3870 4910 2670 3250 4890 5430 49 47 58 49 47 79 49 47 46 53 ~ TABLE BI.1.4.6 (Page 3 of 3) Plan Stage Construction 3.2 1 Watana 2225 ft 400 MW 2 Watana add 400 MW capacity 3 Tunnel 330 MW add 50 MW to Watana Cumulative Stage/Incremental Data System Data Annual Maximum Energy Capital Cost Earliest Reservoir Seasonal Production Plant $Millions On-line Full Supply Draw-Firm Avg.Factor (1980 values)Datel/Level -ft.down-ft.GWh GWh % 1740 1993 2200 150 2670 2990 85 150 1994 2200 150 2670 3250 46 1500 1995"1475 4 4890 5430 53 3390 4.1 I 1 Watana 2225 ft 400 MW 1740 19951/2200 150 2670 2990 85 2 Watana add 400 MW capacity 150 1996 2200 150 2670 3250 46 3 High Devil Canyon 1470 ft 400 MW 860 1998 1450 100 4520 5280 50 4 Portage Creek 1030 ft·150 MW 650 2000 1020 50 5110 6000 51 TOTAL SYSTEM 1350 MW 3400 1 /A lowing for a 3 year overlap construction period between major dams. 2_/P an 1.2 Stage 3 is less expensive than Plan 1.3 Stage 2 due to lower mobilization costs. 3_/A~sumes FERC license can be filed by June 1984,ie.2 years later than for the Watana/Devil Canyon Plan 1. TABLE B.l.5.~:SUSITNA ENVIRONMENTAL DEVELOPMENT PLANS (Page 1 of 3) Cumulative System Data Plan Stage Construction Capital Cost $Millions (I980 va 1 ue s) Stage/Incremental Data Earliest Reservoir On-line Full Supply Date!/Level -'ft. Maximum Seasonal Draw- down-ft Annual Energy Production Firm Avg. GWh GWh plant Factor % El.I El.2 E1.3 1 2 1 2 3 4 1 2 3 Wata na,2225 ft 800~ ,I and Re-Regu1atioq Dam Devil Canyon 1470 ft 49 0M W I 'IOTAL SYSTEM 1200MW i Watana 2060 ft 400MW Watana.rai se to 2225 ft Watana add 400MW ~ap~City and Re-Regulation Daml Devil Canyon 1470 it ' 400MW Ii 'IO'I1AL,SYSTEM 1200MW! Watiana2225 ft 400~ Watanaadd 400MWc~p~city and I R~-Regu1ation Dami Dev~l Canyon 1470 f~ 4pp MW 'IOTAL SYSTEM 1200MW 1960 1993 2200 150 2670 3250 46 900 1996 1450 100 5520 6070 58 2860 1570 1992 2000 100 1710 2110 60 360 1995 2200 150 2670 2990 85 2301/995 2200 150 2670 3250 46 900 1996 1450 100 5520 6070 58 3060 1740 1993 2200 150 2670 2990 85 250 1993 2200 150 2670 3250 46 900 1996 1450 100 5520 6070 58 2890 ~--''---''---'l!f/·.. '------''~ TABLE B.Il.5.1 (Page 2 of 3) ---~.- Cumulative Stage/Incremental Data System Data Annual Maximmn Energy Capital Cost Earliest Reservoir Seasonal Production Plant $Millions On-line Full Supply Draw-Finn Avg.Factor Plan tage Cons truction (1980 values)Datel/Level -ft.down-ft.GWh <Mh % E1.4 1 Watana 2225 ft 400MW 1740 1993 2200 150 2670 2990 85 2 Devil Canyon 1470 ft 400MW 900 1996 1450 100 5190 5670 81 TOTAL SYSTEM 800MW 2640 E2.1 11 Hi gh Devil Ca nyon 1775 ft 800MW and Re-Regulation Dam 1600 19941/1750 150 2460 3400 49 2 Vee 2350ft 400MW 1060 1997 2330 150 3870 4910 47 TOTAL SYSTEM 1200MW 2660 E2.~11 High Devil Canyon 1993.111630f t 400MW 1140 1610 100 1770 2020 58 2 High Devil Canyon raise dam to 1775 ft add 400MW and Re-Regulation Dam 600 1996 1750 150 2460 3400 49 3 Vee 2350 ft 400 MW 1060 1997 2330 150 3870 4910 47 TOTAL SYSTEM 1200MW 2800 E2.3 I 1 High Devil Canyon 1775 ft 400MW 1390 19941/1750 150 2400 2760 79 2 High Devil Canyon add 400MW capacity and Re-Regulation Dam 240 1995 1750 150 2460 3400 49 3 Vee 2350 ft 400MW 1060 1997 2330 150 3870 4910 47 TOTAL SYSTEM 1200 2690 TABLE B.l.5.1 (Page 3 of 3) Stage/Incremental Data Cumulative System Data I Plan Stage Co~struction Capital Cost $Mill ions (1980 values) Earl iest Re servoir On-1 iqe Fun Supply Datell Level -ft. Maximtnn Seasonal Draw- down-ft. Annual Energy Production Firm Avg. GWh GWh Plant Factor % E2.4 1 2 3 E3.2 1 2 3 E4.l 1 2 3 4 Hi~h 'Devil Canyon 1755 ft 400MW High Devil Canyon : add400MW capacit~ and Portage Creek i Dam 150 ft ' VeJ,2350 ft 400MW: TOTAL SYSTEM i Watana i 2225 ft 400MW Watanai add 400 .MW ca pac i ty anq Re-Regulation Dam. Wat±ana'add 50MW Tumtei Scheme 330MW TOTAL SYSTEM 1180~ Watana 2225 ft 400MW Watana add 400MW capacity! and Re-Regulation I Dam i High Devil Canyon 1470 f t 400MW Portage Creek 1030 ft 150MW . 'IDTAL SYSTEM 1350 Mw 1390 790 1060 nziIT 1740 250 1500 1Zi"9rr 1740 250 860 650 '15UU 19941/ 1995 1997 1993 1994 1995 19951/ 1996 1998 2000 1750 1750' 2330 2200 2200 1475 2200 2200 1450 1020 150 150 150 150 150 4 150 150 100 50 2400 2760 3170 4080 4430 5540 2670 2990 2670 3250 4890 5430 2670 2990 2670 3250 4520 5280 5110 6000 79 49 47 85 46 53- 85 46 50 51 1 / 2=/ 3_/ Allowing for ,a 3 year overlap Fons truction.periiod between major dams. Plan 1.2 Stage 3 is less exp~nsive than plan 1.3 Stage 2 due to lower mobilization costs. Assumes FERC license can be Ifiled by June 1984,!ie.2 years later than for the Watana/Devil Canyon Plan 1. '---<~~'---'.--:....,.~ TABLE B.1.5.2:RESULTS Of ECONOMIC ANALYSES Of SUSITNA PLANS -MEDIUM LOAD fORECAST Susitna Development Plan Inc.Installed Capacity (MW)by Total System Total System On-line Dates .Category in 2010 Installed Present Remarks Pertaining to Plan Sta es OGP5 Run Thermal Hydro Capacity In Worth Cost the Susitna Basin No.1 2 3 4 Id.No.Coal Gas Oil Other Susitna 20l0-MW $Millionl/Development Plan ELI 2000 ----LXE7 300 426 0 144 1200 2070 5850 E1.2 1995 1997 2002 L5Y9 200 501 0 144 1200 2045 6030 El.3 1996 2000 --L8J9 300 426 0 144 1200 2070 5850 1996 ----L7W7 500 651 0 144 800 2095 6960 Stage 3,Devil Canyon Dam not constructed 19J8 2001 2005 --LAD7 400 276·30 144 1200 2050 6070 Delayed implementation schedule E1.4 19J3 2000 ---LCK5 200 726 50 144 800 1920 5890 Total development limited to 800 MW Modified 1 E2.1 19 4 2000 -- -- LB25 400 651 60 144 .800 2055 6620 High Devil Canyon limited to 400 MW E2.yl!t 1996 2000 -L601 300 651 20 ~44 1200 2315 6370 19 3 1996 ----LE07 500 651 30 144 800 2125 6720 Stage 3,Vee Dam,not constructedModified E2.3 19 3 1996 2000 LEB3 300 726 220 144 1300 2690 6210 Vee Dam replaced by Chakachamna Dam 3.1 19~3 .1996 2000 --L607 200 651 30 144 1180 2205 6530 Special 19933.1 1996 2000 --L615 200 651 30 144 1180 2205 6230 Capital cost of tunnel reduced by 50 percent E4.1 1996 1998 --LTZ5 200 576 30 144 1200 2150 6050 Stage 4 not constructed 1-1 Adju ted to incorporate cost of re-regulation dam C", TABLE B.1.5.3:RE~ULfS Of ECONOMIC ANALYSES Of SUSITNA PLANS -LOW AND HIGH LOAD fORECAST I ':, Susitna Development Plan Inc.Installed Capaci~y (MW)by Total System Total System On-line Dates Category ini2010 Installed Present Remarks Pertaining to Plan Stages OGP5 Runi Thermal Hydro Capacity In Worth Cost the Susitna Basin No.1 2 3 4 Id.No.:Coal Gas Oil Other Susitna 20l0-MW $Million Development Plan VERY LOW fORECASTl n.4 1997 2005 ----L7B7 0 651 50 144 800 1645 3650 LOW LOAD fORECAST n.3 1993 1996 2000 -------- -- --------Low energy demand does not warrant plan capacities n.4 1993 2002 ----LC07 0 351 40 144 800 1335 4350 1993 ------LBK7 200 501 80 144 400 1325 4940 Stage 2,Devil Canyon Dam, not constructed E2.1 1993 2002 ----LG09 100 426 30 144 800 1500 4560 High Devil Canyon limited to 400 MW 1993 ------LBUl 400 501 0 144 400 1445 4850 Stage 2,Vee Dam,not constructed. E2.3 1993 1996 2000 ------------------Low energy demand does not warrant plan capacities Special 3.1 1993 1996 2000 --L613 0 576 20 144 780 1520 4730 Capital cost of tunnel reduced by 50 percent 3~2 1993 2002 ----L609 0 576 20 144 780 1520 5000 Stage 2,400 MW addition to.Watana,not constructed HIGH LOAD fORECAST E1.3 1993 1996 2000 --LA73 1000 951 0 144 1200 3295 10680 Modified E1.3 1993 1996 2000 2005 LBV7 800 651 60 144 1700 3355 10050 Chakachamna hydroelectric generating station (480 MW) brought on line as a fourth stage E2.3 -1993 1996 2000 --LBV3 1300 951 90 144 1200 3685 11720 Modified E2.3 1993 1996 2000,2003 LBY!1000 876 10 144 1700 3730 11040 Chakachamna hydroelectric generating station (480 MW) i brought on line as a fourth i stage I Note:Incorporating load ~anagement and conservation I --'--''-'--' TABLE B.l.5.4:ANNUAL FIXED CARRYING CHARGES Economic Parameters Economic Cost of Life Money Amortization Insurance Project Type -Years %%% Thermal -Gas Turbine (Oi 1 Fired)20 3.00 3.72 0.25 Dies~l,Gas Turbine (Gas Fired)and Large Steam Turbine 30 3.00 2.10 0.25 -Small Steam Turbine 35 3.00 1.65 0.25 Hydropower 50 3.00 0.89 0.10 FUEL COSTS AND ESCALATION RATES IJ Natural Gas .Coal Distillate I ) I Base Period (January 1980) Prices ($/million Btu) Market Prices Shadow (Opportunity)Values $1.05 2.00 $1.15 1.15 $4.00 4.00 Real Escalation Rates (Percentage) Change Compounded (Annually) 1980 -~985 1986 -1990 1991 -1995 Composite (average)1980-1995 1996 -2005 2006 -2010 1.79% 6.20 3.99 3.98 3.98 o 9.56% 2.39 -2.87 2.93 2.93 o 3.38% 3.09 4.27 3.58· 3.58 o TABLE B.l.5.5:SUMMARY OF THERMAL GENERATING RESOURCE PLANT PARAMETERS PLANT TYPE COAL-FIRED STEAM COMBINED GAS Parameter CYCLE TURBINE DIESEL 500 MW 250 MW 100 MW 250 MW 75 MW 10 MW Heat Rate (Btu/kWh)10,500 10,500 10,500 8,500 12,000 11,500 O&M Costs Fixed O&M ($/yr/kW)0.50 1.05 ·1.30 2.75 2.75 0.50 Variable O&M ($/MWh)1.40 1.80 2.20 0.30 0.30 5.00 Outages P.lanned Outages (%)11 11 11 14 11 1 Forced Outages (%)5 5 5 6 3.8 5 Construction Period (yrs)6 6 5 3 2 1 Start-up Time (yrs)6 6 6 4 4 1 Total Capital Cost ($million) Railbelt:175 26 7.7 B~~1!gll:..'__'_J,J30 630 .~.2JL Unit Capital Cost ($/kW)l/ RaBbel t:728 250 778 Beluga:2,473 2;744 3,102 1/Including AFDC at 0 percent escalation and 3 percent interest. I 1 .j J J ) ,1 J ) / j -j ,) j ] j ,] j .] ] ] ) TABLE B.l.5.6:ECONOMIC BACKUP DATA FOR EVALUATION OF PLANS Total Present Worth Cost for 1981 -2040 Period $Million (%Total) Parameter Generation Plan With High Devil Canyon -Vee Generation Plan Generation Plan With Watana -With Watana - Devil Canyon Dam Tunnel All Thermal Generation Plans Capital Investment Fue Operation and Maintenance TOT~: 2800 (44) 3220 (50) 350 (6) 6370 (100) 2740 (47) 2780 (47) 330 (6) 5850 (100) 3170 (49) 3020 (46) 340 (5) 6530 (l00) 2520 (31) 5240 (64) 370 (5) 8130 (l00) TABLE B.1.5.7: ! I I II I . ECONOMIC EVALUATION Of DEVIL CANYON DAM ANID TUNNEL SCHEMES AND WATANA/DEVIL CANYON AND HIGH DEVIL CANYON/VEE PLANSii' Present Worth of Net Benefit ($million)of Total Generation System Costs for the: Devil Canyon Dam over Watana/Devil Canyon Dams over I the Tunnel Scheme the High Devil Canyon/Vee Dams Remarks ECONOMIC EVALUATION: -Base Case SENSITIVITY ANALYSES: -Load Growth -Capital Cost Estimate -Period of Economic Analysis -Discount Rate Low High Period shorten~d to (1980 -2010)i 5 '"IAII 8%(interpolat~d) 9%! 680 650 N.A. Higher uncertain~y assoc- iated with tunnel scheme.,.I 230 520 210 1040 Higher uncertainty associated with H.D.C./Vee plan. 160 Economic ranking:Devil Canyon Dam scheme is superior to tunnel scheme.Watans/Devil Canyon Dam plan is superior to the High Devil Canyon Dam/Vee Dam plan. The net benefit of the Watana/Devil Canyon plan remains positive for the range of load forecasts considered.No change in ranking. Higher cost uncertainties associ- ated with higher cost schemes/plans.Cost uncertainty therefore does not affect economic ranking. Shorter period of evaluation decreases economic differences. Ranking remains unchanged. -fuel Cost -fuel Cost Escalation -Economic Thermal Plant life 80%basic fuel Icost i, 0%fuel escala~ioh 0%coal escalatton 50%extension 0%extension As both the capi~al and fuel costs associated with the tunnel scheme and H.D.C.I/Vee Plan are higher than for Watans/Devil Canyon plan any qhanges to these parameters cannot reduce the Devil Canyon or ~atana/Devil Canyon net benefit to below zero. Ranking remains unchanged. ~~.-..J '--~---' TABLE 8.1.5.8:ENVIRONMENTAL EVALUATION Of DEVIL CANYON DAM AND TUNNEL SCHEME (Paga 1 of 2) Environmenta Attribute Ecological: -Downetreamlfisheries and Wildlife Concerna Effects resulting from changea in water quantity and quality. Appraiaal (Differencea in impact of two achemee) No aignificant differ- ence betwesn achemes regsrding effecta down- stream of Devil Can~on. Identification of difference Appraisal Judgment Not a factor in evaluation of scheme. Scheme judgsd to have ths leaat potential impsct Tunnel DC Reaident fisperies: Wildlife: Loss of resident fisheries habitet. Loas of wildlife hebitat. Difference in reach between Devil Canyon dam and tunnel re- regulation dam. Minimal differences betwssn schsmea. Minimal differsncee between schemes. With the tunnel schema controlled flowa between regulation dam and down- stream powerhouse offers potential for anadromoua fisheries enhancement in thia 11 mile reach of the river. Devil Canyon Dam would inundate 27 miles of ths Susitns River and approx. 2 milss of Dsvil Cresk. The tunnel acheme would inundate 16 milea of the Susitna River. The most eensitive wild- life habitst in this reach is upstream of ths tunnel re-rsgulstion dsm where there is no significant difference between the echeme.The Devil Canyon Dam schems in addition inundatss ths river vslley between the two damsites resulting in s mode rete increase in impacts to wildlife •. If fieheriea enhancement opportunity can be realized the tunnel echeme offere e positive mitigetion measuree not aveilable with the Devil Canyon Dam schsme.This opportunity is'considered moderate and,favore the tunnel scheme.However,there are no current plens for such enhance- ment and feasibility is uncertain. Potential value is therefore not significant relative to additional coat of tunnel. Loaa of,habitat with dam schema ia leas than 5~of total for Susitna mainatem.This resch of river ia thsrefore not considered to bs highly significsnt for rssident fisheries and thus the difference betwsen the schemes is minor and favors the tunnel scheme. Moderate wildlife populatione of moose,black besr,weasel,fox, wo]verine,'othsr small msmmals and songbirds and aoms riparian cliff hsbitat for ravsns and raptora,in 11 miles of river, would be loat with the dam schems. Thus,the difference in loss of wildlife habitat ia considerad moderate and favora the tunnel scheme. x x x ·TABLE 0.1.5.0:(Page 2 0(2) Environmental Attribute Concerna Appraisal (Differences in impact of two achemea) Identi fication of diffe.renca Appraiaal Judgment Schema udged to have the leaat potential impact Tunnel DC Cultural: Land Uae: Inundation of archeological sites. IInundstion of Devil Canyon. ~otential differences between schemes. ! . S'igni ficant di fference O'etwelln schemea. Due to the larger area inundated the probability of inundatingarche~logi­ cal eites ia increased. The Devil Canyon ie'con- sidered a unique resource, ,80 percent of which would be inundated by the Devil Canyon Dam scheme.This would reault in a loea of both ao aeathatic value plua the optential for white water recreation. Significant archeological aites,if identified,can proba- bly be excavated.Additional coats could range from several hundred a to hundreds of thouaands of dollara,but are atill consider- ably less than the additions1 cost of the tunnel scheme.This concern is not considered a factor in scheme evalustion • The aesthetic and to some extent the recreational losses associ- ated with the development of the Devil Canyon Dam iethe main aspect favoring the ,tunnel scheme. However,current recreational uses of Devil Canyon are low due to limited sccess.future possibilities include major recrational develop- ment with conatruction of restsu-. ranta,msrinaa,etc.Under such conditions,neither scheme would be more favorable. x OVERALL EVALUATION: '---~ The tunnel ,scheme haa overalll a ! -..---' i,'Ilowerimpactontheenvironment. .-.....,--../~----'~.~ TABLE B.I.5.9:SOCIAL EVALUATION OF SUSITNA BASIN DEVELOPMENT SCHEMES/PLANS Remarks Devil Canyon Dam scheme potential higher than tunnel scheme.Watana/ Devil Canyon plan higher than High Devil Canyon/ Vee plan. socia~Tunnel Devil Canyon High Devil Canyon/Watana/Devil Aspec Parameter Scheme Dam Scheme Vee Plan Canyon Plan poteor Million tons 80 110 170 210 non-r newable Beluga coal resou ce over 50 years displ cement Impac statejeconomy Impac on local economy All projects would have similar impacts on the state and local economy. All projects would have similar impacts on the state and local economy. seismtc expos re Risk of major structural failure All projects designed to similar levels of safety.Essentially no difference between plans/schemes. Potential impact of failure on human life. Any dam failures would effect the same downstream population. -- Overa~l Evalu~tion 1.Devil Canyon Dam superior to tunnel. 2.Watana/Devil Canyon superior to High Devil Canyon/Vee plan. TABLE B.I.5.10:ENERGY CONTRIBUTION EVALUATION OF THE DEVIL CANYON DAM AND TUNNEL SCHEMES Parameter Total Energy Production Capability Annual Average Energy GWh Firm Annual Energy GWh %Basin Potential Developed.1/ Energy Potential Not Developed GWh Dam 2850 2590 43 60 Tunnel 2240 2050 32 380 Remarks Devil Canyon dam annually develops 610 GWh and 540 GWh more average and firm energy respectively than the tunnel scheme. Devil Canyon scheme develops more of the basin potentia 1. As currently envisaged, the Devil Canyon Dam does not develop 15 ft gross head between the Watana site and the Devil Canyon reservoir.The tunnel scheme incorporates addi- tional friction losses in Euiinels-~-Arso-thecompeii:";; sation flow released from re-regulation dam is not used in conjunction with head between re-regulation dam and Devil Canyon. [ ) ) ) I lLBased-on-annual average .energy.--Ful-l--potent-ialbasedonUSBR-four-- \) 'I ,I J ~l "I(j TABLE B.I.5.11:OVERALL EVALUATION OF TUNNEL SCHEME AND DEVIL CANYON DAM SCHEME ATTRIBUTE SUPERIOR PLAN Economic Devil Canyon Dam Energy Contribution Devil Canyon Dam Environmental Tunnel Social Devil Canyon Dam (Marginal) Overall Evaluation Devil Canyon Dam scheme is superior Tradeoffs made: Economic advantage of dam scheme is judged to outweigh the reduced environmental impac.t associated with the tunnel scheme. TABLE B.1.5.12:ENVIRONMENTAL EVALUATIbN bf WATANA/DEVIL CANYON AND HIGH DEVIL CANYON/VEE DEVELOPMENT PLANSt•,(Page 1 (If 2) Environmental 'Attribute PlaQ Comparison _~pp~ai~~!_~udgment Plan jUdged to have the least potential impactHocrv·~···W70C Ecological: 1)fisher ies No significant differenceiin effects on downstream anadromous fisheries.ii' Hoc/v would inundate a~prbximatelY 95 miles ofithe Susitna River and 28 m~le~of tributary stream~,in- cluding the Tyone River.i i W/DC would inundate apRro*imately 84 miles of ~he Susitna River and 24 miles of tributary streams, including Watana CreekJ Due to the avoidance of the Tyone River,lesser inundation of resident fisheries habitat and no significant difference in the effects on anadromous fisheries, the W/DC plan is judged to have less impact. x xriverDuetothelowerpotentialfor direct impact on moose populations within the Susitna,the W/DC plan is judged superior. I HDC/v would inundate li3 miles of critical winter bottom habitat.i ' IW/DC would inundate 108 miles of this river bottom hsbitat.'. Hoc/v would inundate a IIS~ge area upstream of vee ut~lized by three sub-p,opulations of moose that range in the northeast secti~n of the basin. 2)Wildlife a)Moose b)Caribou c)furbearers d)Birds &Bears W/DC would inundate the Watana Creek area utilized by moose.The condition 6,f ~his sub-population o~moose and the quality of the ra~itat they are using ~ppears to be decreasing •!'' The increased length o~river flooded,especia]ly up- stream from the Vee damsite,would result in the HoD/Vplan creating a g~eater potential divisi~n of the'Nelchina herd I s range.j In addition,an inc,tease in ,r~nge would be direcrly:inundated by the Ve~res- ervo~r.I ' The area flooded by thel Ve:e reservoir is consid:ered important to some key f~rb~arers,particularly ~ed fox. This area is judged to be more important than the Watana Creek area that Wou[d be inundated by the W/DC plan.!' i ! forest habitat,important ,for birds and black bears, exist along the valley ~lopes.The loss of this habi- tat'would be greater wi~h ~he W/DC plan. ! Due to the potential for a greater impact on the Nelchina caribou herd,the HDC/v scheme is considered inferior. Due to the lesser potential for impact on furbearers the W/DC is judged to be superior. The HDc/V plan is judged superior. x x x Cultural:There is a high potenti~l for discovery of arch~ologi­ cali sites in the easterly region of the upper Susitna basin.The HDc/v plan ~asl a greater potential pf affecting these sites.Ifor other reaches of the river the difference between plans is considered minimal • The W/DC plan is judged to have a lower potential effect on archeological sites. x ._.__i' ~~.--~ TABLE B.l.~.12 (Page 2 of 2) EnvironmentJal Attribute Plan Comparison Appraisal Judoment Plan~uaged to have the least potential impact HDC/V -WTDC Aestheticl Land Use With either scheme,the aesthetic quality of both Devil Canyon and Vee Canyon would be impaired.The HDC/v plan would also inundate Tsusena Falls. Due to construction at Vee damsite and the size of the Vee reservoir,the HDC/v plan would inherently create access to more wilderness area than would the W/DC plan. Both plans impact the valley aesthetics.The difference is considered minimal. As it is easier to extend access than to limit it,inherent access requirements were considered detrimental and the W/DC plan is judged superior".The ecological sensitivity of the area opened by the HDC/V plan reinforces this judqment. x OVERALL EVALUATION:The W/DC plan is judged to be superior to the HDe/V plan. (The lower impact on birds and bears associated with HDC/v plan is considered to be outweighed by all the other impacts which favor the WiDe plan.) Notes:WIWatana Dam DC =Devil Canyon Dam HD =High Devil Canyon Dam V Vee Dam TABLE B.l.5.l3:ENERGY CONTRIBUTION EVALUATION OF THE WATANA/DEVIL CANYON AND HIGH DEVIL CANYON/VEE PLANS I Parameter Total Energy Production Capability Annual Average Energy GWh Firm Annual Energy GWh %Basin Potential Developedl..l Energy Potentia~Not Developed GWh '1:.7 Watana/ Devil Canyon 6070 5520 91 60 High'Devil Canyon/Vee 4910 3870 81 650 Remarks Watana/Devil Canyon plan annually devel- ops 1160 GWh and 1650 GWh more average and firm energy,re- pectively,than the High Devil Canyon/Vee Plan. Watana/Devil Canyon plan develops lIlOte of the basin potential As currently con- ceived,the Watana/- Devil Canyon plan does-not--devel"op t 5 ft of gross head between the Watana site and the Devil Canyon reservoir. The High Devil Canyon/Vee Plan does not develop 175 it gro.ss __hea.d_b.etwee.n_ site and } I Notes: 1/Based on annual average energy..F1illp6~~nt:~aT basecl0nUSBR'fpur . dam schemes. '1:./Includes losses due to unutilized head. J I J TABLE B.I.5.14: ATTRIBUTE Economic Energy Contribution Environmental Social Overall Evaluation OVERALL EVALUATION OF THE HIGH DEVIL CANYON/VEE AND WATANA/DEVIL CANYON· DAM PLANS SUPERIOR PLAN Watana/Devil Canyon Watana/Devil Canyon Watana/Devil Canyon Watana/Devil Canyon (Marginal) Plan with Watana/Devil Canyon is superior Tradeoffs made:None -I TABLE B.2.2.1:COMBINED WA'l'ANA AND DEYfCCANYON OPERATION Watana Dam Crest Elevation (ft MSL) j ----------------------------------A-v-e-r-a-g-e-A-n-n-u-a-l--J Wat anal/Devil Canyonl/Total Energy (GWh) Cost Cost Cost Watanak /Watana/Devil ($x 10 6 )($x 10 6 )($x 10 6 )Alone Canyon 2240 (2215 reservoir elevation) 2190 (2165 reservoir elevation) 4,076 3,785 1,711 1,711 5,787 5,496 3,542 3,322 6,809 6,586 .) I 2140 (2115 reservoir elevation)3,516 1,711 5,227 3,071 6,264 II Estimated costs in January 1982 dollars,based on preliminary conceptual designs,including relicfcnaiinel drainage blanket and 20 percent contingencies. kl Prior to year 2002 ,1 I i J ) TABLE B.2.2 .2: Watana Dam Crest Elevation (ft MSL) 2240 (reservoir elevation 2215) 2190 (reservoir elevation 2165) 2140 (reservoir elevat ion 2115) PRESENT WORTH OF PRODUCTION COSTS Pre sent Wo rth of Production Costs1/ ($x 10 6 ) 7,123 7,052 7,084 1/.LTPW in January 1982 dollars TABLE B.2.2.3:DESIGN PARAMETERS FOR DEPENDABLE CAPACITY AND ENERGY PRODUCTION Watana Minimum stream flow!/(monthly average,cfs)570 (March 1950) Mean streamflow!/7,990 Devil Canyon 664 (March 1964) 9,080 Maximum streamflow!/42',840 (June 1964)47,816 (June 1964)1 J Evaporation Approximately cancels precipitation and is neglected. Leakage Negligible Negligible Critical streamflow for dependable capacity curve (Watana and Devil Canyon combined) Area capacity curve Hydraulic Capacity Flow (cfs)1/2 full 'best Efficiency 1/2 fu-l-l- best Generator output (kW)1/2 full best Tailwater rating curves 5,450 GWh annual potential recurrence frequency 1 in 32 years Figure B.3.2.1 Figure B.3.2.1 1,775 1,895 3,550 3,790 2,900 3,100 87 87 94 94 91,000 82,000 183,000 164,000 156,000 139,000 Figure B.4.2.3 Figure B.4.2.3 ) J I,I ,1 TABLE B.2.2.4:WATANA -MAXIMUM CAPACITY REQUIRED (MW) OPTION 1 -THERMAL AS BASE . CAPACITY (MW) Hydrological Year 1995 2000 2010*** 1 743 762 838* 2 550 569 680 3 760 779 836* 4 749 I 768 836* 5 744 763 868* 6 763 782 832* 7 737 756 838* 8 771 790 836** 9 799**818**825* 10 563 582 683* 11 769 788 832* 12 784*803 829*. 13 773 792 832* 14 771 790 838* 15 745 , 764 844* 16 550 569 840* 17 745 764 836* 18 554 573 684* 19 771 790 832* 20 550 569 685* 21 550 569 678 22 550 569 672 23 784*803 834* 24 747 766 838* 25 550 569 684 26 ·550 569 678 27 728 747 839* 28 550 569 675 29 785*804 833* 30 550 569 678 31 787*806 837* 32 754 773 839* *Restricted by peak demand **Maximum value ***Including Devil Canyon TABLE B.2.2.5:WATANA -MAXIMUM CAPACITY REQUIRED (MW) OPTION 2 -THERMAL AS PEAK CAPACITY (MW) Hydrological Year 1995 2000 2010* 1 575 575 838 2 382 382 389 3 592 592 839 4 581 581 836 5 576 576 868 6 595 595 832 7 569 569 838 8 603 603 836 9 631 631 825 10 395 365 391 11 601 601 832 12 616 616 829 13 605 605 832 14 603 603 838 15 577 577 844 16 382 382 840 17 577 I 577 836 18 386 386 j 392 19 603 603 832 20 382 382 393 21 382 382 386 22 382 382 380 23.616 626 834 -."""5.79 ~38 25 382 382 392 26 382 382 386 27 560 560 839 .28 382 382 383 29 617 617 833 30 382 382 387 31 619 619 837 32 586 586 839 """"- J l 1 ( i j .1 J i ,\ TABLE B.2.2.6:SUMMARY COMPARISON OF POWERHOUSES AT WATANA S U R F ACE U N D ERG R 0 U N D ($000)($000)($000) Item 4 x 210 MW 4 x 210 MW 6 x 140 MW Civil Works: Intakes 54,000 54,000 70,400 Penstocks 72,000 22,700 28,600 Powerhouse/Draft Tube 29,600 26,300 28,100 Surge Chamber NA 4,300 4,800 Transformer Gallery NA 2,700 3,400 Tailrace Tunnel NA 11,000 11,000 Tailrace Portal NA 1,600 1,600 Main Access Tunnels NA 8,100 8,100 Secondary Acc.ess Tunnels NA 300 300 Main Access Shaft NA 4,200 4,200 Access Tunnel Portal NA 100 100 Cable Shaft NA 1,500 1,500 Bus Tunnel/Shafts NA 1,000 1,200 Fire Protection Head Tank NA 400 400 Mechanical -For Above Items 54,600 55,500 57,200 Electrical -For Above Items 37,400 37,600 41,200 Switchyard -All Work 14,900 14,900 14,900 TOTAL 262,500 246,200 277 ,000 TABLE B.2.3.1:DESIGN DATA AND:DESIGN CRITERIA FOR FINAL REVIEW OF LAYOUTS .River Flows Average flow (over 30 years of record): Probable maximum flood (routed): Maximum inflow with return period of 1:10,000 years: Maximum 1:10,000-year routed discharge: Maximum flood with return period of 1:500 years: Maximum flood with return period of 1:50 years: Reservoir normal maximum operating level: Reservoir minimum operating level: Dam Type: Crest elevation at point of maximum super elevation: Height: Cutoff and foundation treatment: Upstream slope: Downstream slope: Crest width: Diversion Cofferdam type: __~~Cut9 ft=and founda t ion :~~~~_~__~~~~~_ Upstream cofferdam crest elevation: Downstream cofferdam crest elevation: Maximum pool level during construction: Tunnels: Final closure: Releases during impounding: (Page 1 of 2) 7,860 cfs 326,000 cfs 156,000 cfs 115,000 cfs 116,000 cfs ,87,000 cfs 2215 ft 2030 ft Rockfill 2240 ft 890 ftabove foundation Core foundedon'rock; grout curtain and down- stream drains .2.4H:IV 2H:lV 50 ft Rockfill ..Slurry_tre!1~J!.~~().Q~drC?~c~ 1585'ft 1475 ft 1580 ft Concrete-lined, Mass concrete plugs 6,000 cfs maximum via bypass to outlet structure J ..l Design floods: Main spillway -Capacity: -Control structure: Emergency spillway -Capacity: -Type: Passes PMF,preserving integrity of dam with no loss of life Passes routed 1:l0,000-year flood with no damage to structures Routed1:10,000-year flood wi th 5 ft surcharge "/Gated agee crests ! PMF minus 1:10,000 year flood Fuse plug -I TABLE B.2.3.1 (Page 2 of 2) Power Intake ] Type: Number of intakes: Draw-off requireme~ts: Drawdown: Penstocks Type: Number of penstocks: Powerhouse Type: Transformer area: Control room and administration: Access -Vehicle: -Personnel: Power Plant Type of turbines: Number and rating: Rated net head: Design flow: Normal maximum gross head: Type of generator: Rated output: Power factor: Frequency: Transformers: Tailrace Water passages: Surge: Average tailwater elevation (full generation): Reinforced concrete 6 Multi-level corresponding to temperature strata 185 feet Concrete-lined tunnels with downstream steel liners 6 Underground Separate gallery Surface Rock tunnel Elevator from surface Francis 6 x 170 MW 690 ft 3,500 cfs per unit 745 ft Vertical synchronous 190 MVA 0.9 60 HZ 13.8-345 kV,3-phase 2 concrete-lined tunnels Separate surge chambers 1458 ft Note:Certain design data and criteria have been revised since date of layout review.For current project parameters refer to Exhibit F,Preliminary Design Report. PRELIMINARY REVIEW Technical feasibility Compatibility of layout with known geological and topographical site features Ease of construction Physical dimensions of component structures in certain locations TABLE B.2.3.2:EVALUATION CRITIERA INTERMEDIATE REVIEW Technical feasibility Compatibility of layout with known geological and topographical site features Ease of construction FINAL REVIEW Technical feasibility Compatibility of layout with known geological and topographical site features Ease of construction ,~ Obvious cost differences of comparable structures Environmental accept- ability Overall cost Environmental accept- ability Overall cost Environmental impact 'J ,I j TABLE B.2.3.3:SUMMARY OF COMPARATIVE COST ESTIMATES INTERMEDIATE REVIEW OF ALTERNATIVE ARRANGEMENTS (January '1982 $x 10 6 ) WP1 WP2 WP3 WP4-- Diversion 101.4 112.6 101.4 103.1 Service Spillway 128.2 208.3 122.4 267.2 Emergency Spillway -46.9 46.9 Tailrace Tunnel 13 .1 13.1 13 .1 8.0 Credit for Use of Rock in Dam (ll.])(31.2)(18.8)(72.4) Total Non-Common Items 231.0 349.7 265.0 305.9 Common Items 1643.0 1643.0 1643.0 1643.0 Subtotal 1874.0 1992.7 1908.0 1948.9 Camp &Support Costs (16%)299.8 318.8 305.3 311.8-- Subtotal 2173.8 2311.5 2213 .3 2260.7 Contingency (20%)434.8 462.3 442.7 452.1 Subtotal 2608.6 2773.8 2656.0 2712.8 Engineering and Administration (12.5%)326.1 .346.7 332.0 339.1 TOTAL 2934.7 3120.5 2988.0 3051.9 ____..~~__~_..__._.--=-=-==--==~--l ........=====~=---------- **Maximum Value TABLE B.2.4.1:DEVIL CANYON -MAXIMUM CAPACITY REQUIRED (MW) <:1 Hydrological Year 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 25 26 27 28 29 30 31 Capacity (MW) 2010 (Option 1 and 2) 544** 353 546 546 514 548 544 546 557 351 548 551 548 544 538 542 546 350 550 349 355 361 544 349 355 543 359 549 355 545 1 "J j J I J l ( -J I I 1 I i 1 .1 ) j J TABLE B.2.5.1:DESIGN DAT~AND DESIGN CRITERIA FOR REVIEW OF ALTERNATIVE LAYOUTS River Flows (Page.1 of 2) Average flow (over 30 years of record): Probable maximum flood: Max.flood with return period of 1:10,000 years: Maximum flood wi th return period of 1:500 years: Maximum flood with return period of 1:50 years: Reservoir Normal maximtml operating level: Reservoir minimum operating level: Area of reservoir at maximum operating level: Reservoir live storage: Reservoir full storage: Dam Type: Crest elevation: Crest length: Maximum height above foundati<Jn: Crest width: Diversion Cofferdam types: Upstream cofferdam crest elevation: Downstream cofferdam crest elevation: Maximum pool level during construction: Tunnels: Outlet structures: Final closure: Releases during impounding: 8,960 cfs 346,000 cfs 165,000 cfs (after routing through Watana) 42,000 cfs (after routing through Watana) 1455 feet 1430 feet 21,000 acres 180,000 acre-feet 1,100,000 acre-feet Concrete arch 1455 feet 635 feet 20 feet Rockfill 960 feet 900 feet 955 feet Concrete-lined Low-level structure with slide closure gate Mass concrete plugs ~n line with dam grout curtain 2,000 cfs min.via fixed-cone val ves TABLE B.2.5.1 (Page 2 of 2) Spillway Design floods: Service spillway -capacity: -control structure: energy dissipation: Secondary spillway -capaci ty: -control structure: -energy dissipation: Emergency spillway -capacity: 1:10 ,OOO-year -type: Power -Intake Type: Transformer area: Access: Type of.turbines: Number and rating: Rated ne t head: _M~~LimJ.Im g:J;Q~!iLb_ead:._ ____Iype of generator:__.._._ Rated output: Power factor: Passes PMF,preserving integrity of dam with no loss of life Passes routed l:10 ,OOO-year flood wi th no damage to structures 45,000 cfs Fixed-cone valves Five 108-inchdiameter fixed-cone valves 90,000 cfs Gated,ogee crests Still ing basin prof mi nus routed flood Fuse plug Underground Separate gallery Rock Tunnel Francis 4 x 140 MW 550 feet 565f.ee.tapprox._ _____Vertica1~ynchronous 155 MVA 0.9 ..~ Note:Certain design data and criteria have been revised since date of layout review.For current projectparB.III.eters refer to Exhibit F,Preliminary Desi~l1Report.] TABLE B.2.5.2:SUMMARY OF COMPARATIVE COST ESTIMATES PRELIMINARY REVIEW OF ALTERNATIVE ARRANGEMENTS (January 1982 $X 10 6 ) Item DC1 DC2 DC3 DC4 Land Acquisition 22.1 22.1 22.1 22.1 Reservoir 10.5 10.5 10.5 10.5 Main Dam 468.7 468.7 468.7 468.7 Emergency Spillway 25.2 25.2 25.2 25.2 Power Facilities 211.7 211.7 211.7 211.7 Switchyard 7.1 7.1 7.1 7.1 Miscellaneous Structures 9.5 9.5 9.5 9.5 Access Roads &Site Facilities 28.4 28.4 28.4 28.4 Common Items -Subtotal 783.2 783.2 783.2 783.2 Diversion 32.1 32.1 32.1 34.9 Service Spillway 46.8 53.3 50.1 85.2 Saddle Dam 19.9 18.6 18.6 19.9 Non-Common/Items Subtotal 98.8 104.0 100.8 140.0 Total 882.0 887.2 884.0 923.2 Camp &Support Costs (16%)141.1 141.9 141.4 147.7 Subtotal 1023.1 1029.1 1025.4 1070.9 Contingency (20%)204.6 205.8 205.1 214.2 Subtotal 1227.7 1234.9 1230.5 1285.1 Engineering &Administration (12.5%)153.5 154.3 153.8 160.6 Total 1381.2 1389.2 1384.3 1445.7 TABLE B.2.7.1:POWER TRANSFER REQUIREMENTS (MW) 1 J \ J l i j l l ) 1 ! I I j j \ 52 198 276 327 601 1245 TRANSFER EXPECTED Sus tina to Susitna to Anchorage Fairbanks 170 320 405 578 1088 1377 360 960 1620 600 600 360 360 1020 DEPENDABLE CAPABILITY TRANSFER CAPABILITY Devil Total Susitna to Susitna to Watana Canyon Susitna Anchorage Fairbanks 1999 2005 2012 Year TABLE B.2.7.2:SUMMARY OF LIFE CYCLE COSTS (1985 $Mi1lion)ll TRANSMISSION ALTERNATIVE 1 2 3 4 5 Transmi sion Lines Capital $220.12 $231.37 $188.18 $205.28 $223.72 Land Ac uisition 26.70 29.64 25.76 28.70 26.59 Capi tal zed Annual Charges 181-.56 191.25 153.17 166.57 180.95 Capital zed Line and Losses 75.66 77.70 91.97 93.85 61.05 Total T ansmission Line Cost $504.04 $529.96 $459.08 $494.40 $492.31 Swi tchi g Stations caPital!$168.62 $155.35 $190.43 $177 .16 $224.79 Capital zed Annual Charges 181.06 167.53 204.19 190.66 242.85 Total S itching Station Cost $349.69 322.88 394.19 367.82 467.64 TOT~$853.72 $852.84 $853.70.$862.22 $959.95 II Thit estimate is based on an Acres (1982).Subsequently,switching equipment for Devil Canyon was shifted to reate Gold Creek switchyard.However,selection of alternative 2 did not change. il J Type 1.Technical -Primary -Secondary 2.Econanical -Primary -Secondary 3.Envirornental -Primary -Secondary Criteria General Location Elevation Relief Access River Crossings Elevation Access River Crossings Timbered Areas ~tlands reveloprent .Erlsting-Tranmsslori Right-of-Way Land Status Topogra];hy Vegetation Selection o>nnect with Intertie near Gold Creek,WillCM, and Healy.Connect Healy to Fairbanks.0>0- nect WillCM to Anchorage. Avoid IDOWltainous areas. Select gentle relief. IDcate in praximi~to existing transP2rtation corridors to facill.tate maintenance arid repairs. Minimize wide crossings. Avoid IIlJUntainous areas. IDca~e in proximity to existiJ?g tranSportation corrldors to reduce constroctlon costs. Minimize wide crossings. Minimize such areas to reduce clearing costs. Minimize crossings which require special designs. Avoid existing or proposed developed areas. ParalleI: Avoid private lands,wildlife refuges,parks. Select gentle relief. Avoid heavily timbered areas. ,I I ~l I j i TABlE B.2.7.4:fNI/!IlIPl!·£'·lT.,\L INVENTORY -SOUTHERN STUDY AREA (WIllOW TO ANCHORAGE/POINT MACKENZIE:) (Page I of 2) length (miles) AB 38 Be 35 Corridor Segment ADf 26 AEf 27 fC 12 Number of Road Crossings Number of River Creek Croasing Topogrsphy Soilsl! lsnd ownerShiP/it Stetus Existing/Proposed Developments Existing Rights~of­ Way Scenic Quality/ Recrestion Cultural Resourc~sll 2 hwy (Rt.3,Glenn),6 light duty roads,1 unimproved road, 2 trails,1 railroad 1 river,17 creeks Willow (100'),croases Willow Ck.,follows Deception Ck.(1000')along ridge of Talkeetns Hte.,s.e. into Palmer (200') Willow to near Palmer-S04, Palmer-EO! A to e.of Willow Ck.Rd. crosaing-mostly P,with aome BAP and some SP,•••to due n. of Wasilla-mainly SPTA,•••to B-mostly P,with aome BAP and SP Ag.usea n.&w.of Palmer, ag/res.use near l.Susitna, proposed capital aite,mixed res.area at Willow Ck., Willow air atrip,cabin near A follows no known right-of-way for appreciable distance Gooding l.-bird-watching, rec.traila a.of Willow- hunting,hiking,x-c skiing, dog sledding,snowmobiling, snowshoeing,rec.trsil by Decep.Ck.-anowmobiling, dog eledding,fishing DATA VOID 4 hwy (Glenn,4x),3+light duty roads,7 unimproved roads, 1 trail,several railroads 4 rivers,II creeks Palmer (200'),crosses Knik River to base st Chugsch Hta. (500'),along Knik Arm (200'- 300'),to Anchorsge (200') Palmer-EO!,Knik Arm-En,S. of Eklutna to n.of Anchorage- 505,Anchorege -504 B to Knik R.-P,...to Birchwood-mainly VS with eome SPTA,P and BAP,Birchwood eres-P,s.w.of Birchwood to nesr C'-U.S.Army Military tid!.,C'-DATA VOID Urban uses in Anch.,pssses through/near eeverel communitiesl Eegle R, Birchwood,Eklutna,Chugisk, Peters Ck. Parallela trans.line Knik R. to Anch.,parallels Glenn Hwy. from Knik R.to Birchwood, parallels RR-Esgle to C' Pssses near 2 camping grounda, parellela Iditarod racing trail (x-c ekiing,aledding, snowmobiling),birdwatching at Eklutna flata and Hatunusks River DATA VOID 1 hwy (Rt.3),3 tractor traile 1 river,6 creeks Willow (100'),e.along SuaitnsRiver plaina (flat, wet area,with drier,raised leveea,200'-400'),to f at 150' Willow-504,S.of Willow to f-SOI Near A-P,route fairly even mix of BAP and SPTA,some P near fieh Ck,area aurrounding l Suaitna R -Susitna flate Gsme Reguse,near f-SPTA Red Shirt lake-mixed residential use;near residential &recr.areas s.w. of Willow,Suaitna flats State Gsme Refuge Generally parallela a tractor treil X-c eki &snowmobile traile; recreation area s.w.of Willow DATA VOID 1 hwy (Parka),1 tractor trail 1 river,6 creeks Willow (100'),s.slong flat wet area (200'-400'),to f at about 150' Near l.Susitns River -505, Remainder-S04 A,s.to Rainbow l.-mostly P, small parcels BAP;State selected fed.parcel w.of Willow l.,e.to l.Susitna R. -Nsncy lake State Rec.Area, to f -mix of SPTA and BAP Mixed res.areas;lakes used to land float plsnes No known Mixed rec.sreas,Nancy lake State Rec.area,traila and multiple uses;msy cross Gooss Bay st.Gsme Re fuge DATA VOID 2 trsctor trails 2 creeks f et 150'along flste to C nesr ses level Nesr f -504,Nesr C -501 f to I mi.s.-SPTA,...s.to Horseehoe l.-Pt.MacKenzie Agr.Ssle;•••s.to C-mainly SPT A,some BAP Scsttered residentisl/cabins on Horsehoe lake,proposed ago uses in area Generally follows a trsctor trail Hsy cross Susitna flats State Wildlife Refuge DATA VOID TABlE B.2.7.4 (Paga 2 of 2) AB dorridor Sagment !AOfBC AEf FC VegetationAl fish Reaourcea21 Birda.61 furbearera.61 Bi!il Game.61 Upland,mixad deciduoue- conifer forests (birch-spruce) -open and closed mostly.Tsll shrub (s~der);,somawoodland black spruce;bogs along Deceptlo'l Ck. Willow Ck.,-chinook ealmon, graylingJ burbot I longnoee eucker,~ound wh tefish, Dollsr V~rdan,ialimy aculpin; lake trout!&rainbow trout in lakea;l~Susitna R.-king salmon;qecep.'Ck.-king, pink salnion DATA VOlq DATA VOID Except near Palmer-black bear aummer rsnge.mooee winter/ summer ranga,migrating corridora and calving araa; near A alao brown bear summar ranga and faeding area ,! ~aci~uoua forest (balsam ~opl~r)along rivar,probsbly ~irc~/apruce foreets on uplands in most of aras.DATA VOID I S'ockJya,chinook,pink,ahum,c~hoisalmon in Isrge rivera; grayling burbot,longnose s~cker,round whitefish,Dolly V~r~n,slimy eculpin,lake and rainbow trout in lakes &: stream;ealmonof,perticular sIgnificsnce in the Hstanuska ard ~nik Rivers Waterfowl and shore bird n~eting areae around Knik Arm ard ~agle River Flata I , DATA VOID I IiTA\VOID • Higher grounds:Spruce-birch- poplar forests.Wet sedge grase boga and black spruce forest a prevalent in lower half Willow Ck.-chinook aalmon, lake and rainbow trout possible in some lakes;also, in etreams are grayling,bur bot,long nose sucker,round w~itefish,Dolly Vardsn, slimy.sculpin;Red Skirt l.- lake trout,sockeye sslmon Waterfowl snd shore bird nesting in Willow Creek/ Delta Islanda VOID Brown and black bear'feeding moose winter/summer range and calving area Upper half;mostly upland birch,spruce &:aapen.lower halfl wet sedge-grasa bogs snd black apruce;eome birch, spruce;aspen on higher ground lekes msy contain rainbow snd lake trout;possibly grsyling in the region Ssme aa ADf Same as AUF Ssme aa ADf Spruce foresta,spruce-birch foreata,sedge-grsss bogs snd black spruce boga lake may contain rainbow snd Iske trout;posaibly grayling in the region Waterfowl snd shore bird migration route,feeding and neating area Furbearer snd small mammal summer/winter rsngs Black bear summer rsnge and fseding area;moose winter/ summer range,feeding snd calving area :l !.) Tall shrub=slder;low ShrUb=dw•....ar.f'.birch'and/or WillO['~pen spruce=black (wet)covrr,mixed forest=spruce-birch. ,I little data svailable.Sour~e of information in this tablel Alaeka Department of Fieh and Geme 1978a. !I little dste available.Source of information in this tsble:Alaeka Department of Fish and Game 1978b. 1..1 2..../ 3J 4J 5..../ 6..1 Source I Source I Coaatal i I •.•.I,Unites Statea Department ,of Agriculture,Soi~Conservation Service 1979.See Table B.43 for explanation of soil units. I ,! CIRI/Holmes and Na~v~r.~980.P=Private,SPTf+s,ate Patented or Tentatively Approved,SP=State P~tented,BAP=Borough Approved area probably haa many eites,available liter~ture not yet reviewed.! or Patented. !_~-~-_!~.'----------- TABLE B.2.7.5:ENVIRONMENTAL INVENTORY -CENTRAL STUDY AREA (DAMSITES TO INTERTIE)(Page 1 of 6) Approx. Approx.IJ Al?Prox.IJCorridorLen~th Road Rlver/Creek a Land b Segment (Mi es)Crossings Crossings Topography Soils Ownership/st at us AB 7 0 5 creeks Moderate sloping s.rim of S015 VSSusitnaR.V811ey;crosses deep ravine at Fog Ck.at about 2000'contour II:18 0 8 creeks 2000'contour along s.rim B,westwiird-S015;VSofSusitnaRiver;crosses near C -SOlO3st.eep gorges CD 15 1+1 river Moderately sloping terraini OSlO C to 1 1/2 mi.e.4 creeks crosses 5usit.na R.near Go d of Susitna R.-Creek (800')VSi Susitra R.t.o 1 12 mi.e.- SPTA;...to D-P BEC 23 0 8 creeks Crosses moderate slopes 8,westward -OS15;VS except wherearoundStephaniLake;w.,then ret ween B &C corridor skirts n.to avoid dee~ravine at IU3;near C -SOlO Cheechako Ck. Cheechako Ck.,hen follows s.ravine,..which isrimofSusitnaatabout2000'classi ied 5S Suspended AJ 18 0 11 creeks A (about.2000')t.o 3500';A,westward -OS15;SS ex ceRt at JcrossesdeepravineatDevilremainder,exce~t and at.westward Ck.(2000');goes by several J -OS16;near J - across Tsusena ponds SOlO Ck.,which are VS JC 8 0 1 creek J (2000'),s.w.throu~OSlO SS excegt.at JgentlyslopingHighL e and C w ich are area,to C at Devl1 VSCanyon(2000') CF 15 0 2 creeks Devil Cannon «2000'f west SOlO C to 1 1/2 mi.e.across 60 'deep Por age of Miami L.Creek gorge;w.across mainly VS with rentle terrain to F small parcel of 1200')S5;...to F-P AG 65 0 1 river A (2000'~6 n.along Deadman Near A and along A-VS;n.of A35creeksCk.to 3 0';crosses Denali Hwy.-to s.w.of Big L. Brushkana drainage (at OS15;throu!tl -SS,•••to s. 3200')'dr~s to Nenana uts.-5016 •of Deadman L.- River (240 ,)and fairly SPTA ...to flat.t.errain to G (2200 )Denali Hwy -Fed. D-l Land;data void for 8 mi.' around G -Smail Fed.Parcel a.Source:United States Department of Agriculture,Soil Conservation Service 1979.See Table B.42forexplanationofsoilunits. b.Source:CIRI/Holmes and Narver.1980.P=Private,SPTA=State Patented or Tentatively Approved, SS=St.ate Selection,VS=Village Selection. TABLE B.2.7.,5 (flage 2 of 6) Approx.Approx./1 Corridor Length Road Segment (Mila:!)Crossings Appro,./IRI~er Creek Crossings Topography a Soils Land b Ownership/Status Ali 22 0 HI HJ 21 0 23 0 91 creeks 151 creeks 0,creeks I A (2000')1,along Tsusena Ck. past Tsusena Buft e;through, fit.pass lat 3600'';I H (3400')1 through mts.;along Jack R.drainage and Caribou Pass;to II at 2400' H (3400')1 through mts.along Portage Ck.draInage,through pass at 3600'into Devil Creek dra~nage;;to J at 2000' I ' i Near A -5015Lmt.base -SOlb; mts.-RMl Mts.-RMl; along hwy -S015 Near J -5016 mid elevations- S017;mts.- RMI A -V5;•••to n. of Tsusena Butte 55;dat a void l:eyond here If -VS;data void to east J-VS;Devil Ck drainage -SS; data void beyond here a. b. !lSource:,United States Department for explanation of aoil unit~.I Source:CIRI/Holmes and Nar~eri. I of Agricult ure,Sop Conservation Service,1979.See Table B.42 p 1980.P=Private,iSPTA=State Patented or Tentatively Approved, I i '---''--~~----;'---' TABLE B.2.7.5 (Page 3 of 6) Corridor Segment AB II: ro E£C AJ JC CF a Fish Resources F llJ Lakes -Dolly Varden,sculpin; Stephan Lake contains laKe and rainbow trout~sockeye &coho salmon,whit~rish,longnose sucker,gray~ng;Durbof Several small tributaries crossed, perhaps used by grayling Same as II: Several small tributaries crossed, perhaps used by grayling,burbot Dolly Verden;grayling in Tsusena Creel< Burbot;no data for High Lake Portage Creek has king,chinook, chum and pink salmon,grayling, ~rb~ Birds Potential raptor nesting habitat in Fog Creek area Potential raptor nesting habitat along Devil Canyon Potential raftornestinghabiat along Devil Canyon Potential raftornestinghabiat along Devil Canyon and along drainages upstream; Stephan Lake area important to waterfowl and migrating swans Data void Potential raptor hab. by Devil Can~on;golden eagle nest along Devil Ck.s.of confluence of ck.from High Lake Potential raptor habitat along lower Portage Ck.and from Portage Ck.mouth through Devil Canyon Fur bearers Excellent fox and marten habitat; Fog Lakes support numerous beavers and muskrat;otters common Excellent fox and nart en ha bit at Area around Devil Canyon has excellent fox and marten habitat Excellent fox and marten habitat, particu larly around Stephan Lake Red fox denning sites,numerous beaver,muskrat and mink,esp.ecially around High Lake Same as AJ Area bet ween P ar ks Hwy~nd Devil Canyon supports numerous !:eaver,muskrat,and mili< Big Game Supports large pop. of moose;wolves,wolverine and bear, (especially brown) common;caribou regularly use area Area around Stephan Lake &Prairie Ck. supports large pcp. of moose;wolves, wolverines,and some bear (especially brown)common; caribou regular users Moose,caribou,and bear nabitat Same as AB Mout h of Tsusena Ck. important moose habitat;heavily used by black and brown bear Important moose and !:ear habitat;data void Probably imp~rtant moose w~nter~ng area area and black bear habitat t at leastonewolrpack a.Little data available.Sources of information in this table:Alaska Department of Fish and Game 1978a,Friese 1975,and Morrow 1980. TABLE B.2.7.5 (Page 4 of 6) Corridor Segment AG AH HI HJ a Fish Resources ,' Dollr-Vardeni lakes -I lake trout, grayling,whlte-fish;tributaries foNenana River and Brushkana Creekn.of Deadman Mt.,:and Jack R.near Denali H~considered fish habitat I I I Dolly Varden;grayling ! Lake trout,Cari bou Phssi area; Jack River s.of Caribou:Pass considered important fish habitat;data void !ipb~tage Creek -king,Ich~nook, chum,and pink salmon~grayling, bur bot 'i Birds Waterfowl numerous at Deadman Lake;impor- tant baHl eagle habitat by Denali Hwy and Nenana R~just w.of Monahan Flat;unchecked bald eagle nest along Deadman Ck.,s.e.of Tsusena ~utte Known acti ve bald eagle nest s.e.of Tsusena ~utte Data voi(J I I I Data voi~ Fur bearers P~ulation relati vely low, although beaver, mink,fox present; Deadman Mt.to Denali Hwy - moderate pop.redfox Population along Tsusena Ck.prooably relatively low;with beaver 1 ffilnk,and fox probab y present Data void Numerous beaver, muskrat.~and mink around Ni!tl Lake Big Game Probably important area for caribou, expecially in the north Data void Data void Data void '------'-''-"--- a.Little data available.Sour6eslof information Game 197Ba,Friese 1975,andl Moii-row 1980. I in this table: I Alaska Department of Fish and '10., ~-'-~'-'--' TABLE B.2.7.5 (Page 5 of 6) Corridor Segment AB II: ID BEC Existing/Proposed Development s Cabins on FW Lakes; planes use lakes Cabins and lodge on Stephan Lake Follows proposed Susitna railroad extension;scattered cabins in Canyon/Gold Creek area Cabins and lodge on Stephan lake Exist ing Right s -of -Way No known No known Old Corps trail, Gold Ck.to Devil Canyon No known Scenic Quality/Recreation Fog Lakes -high aest hetic qual1t y; fishing in Fog Lakes Stefhan Lake -hiQh aes hetic quality Scenic area; possible fishing st efhan Lake -hiQh aes hetic qualH y; major recreation area for fishing/ boat i ng/planes Cult ural Resources Arch.sHes identi fied near Wat ana Dam site and w.shore of Stephan Lake; potential for more sites around F9Q Lakes and Stephan Lake Arch.sites near Stephan Lake Hist.sit es near Gold Ck.;data void See AB a Vegetation Most ly wood land black spruce (wet); some low shrub Open and woodland spruce forests,low shrub,open ana closea ffi1xed forest in about equal amounts Mostly closed mixed forests Woodland sp'ruce and bogs arouna Stephan Lakei low shrub, mat ~cushion and sedge-grass tundra at upper end of Cheechako Ck.drain- age;tall shrub (alder)and mixed forest along Cheechako Cl<.and towards Devil Canyon a.Tall shrub:alder;low shrub:dwarf birch}and/or willow;open spruce:black (wet)or white spruce,25%-60%cover; woodland spruce:white or black spruce,0%-25%cover,mixed forest :spruce-birch. TABLE B.2.7.5 (Page 6 of 6) Corridor Existing/Proposed Segment Developments Exist ing Rights-of -Way ScenicQ~lity/Recreation Cult ural Resources a Vegetation Mostly low shrub, mat &:cushion, sedge-grass tundra some ta II shrub (alder) Tall shrub (alder) shrub and open low mixed forest Mostly low shrub in southern end; northern end -data void Open &:closed mixed forest,tall shrub, low shrub Mat &:cushion sedge-grass tundra, tall shrub and open mixed forest in southern end Low shrub,tall shrub,woodland spruce Data void Arch.sites at Portage Ck.and Susitna R.con- fluence and near 11atana Dam site No Known arch. sites Arch.sites at Portage Ck.; hist.si t es near Canyon Arch.sites along Deadman Ck. Arch.site n.of Tsusena But t e along T susena Ck.; data void Data void Data void Boating in Susitna; hunt ing,fishing, hiking High Lake and other laKeS -high aesthe- tic quality·fishing/hun~ing in H~ght lake area S~me as AJ Scenic drainage; S?eep hunting in n. I .Remote flat areas - high visibility;.. Deadman L.and Me.• Alaska Range -hig~ aesthetic quality; fishing,qoat p~anes;major rae. aJ,'eas oy Bfushkana afrl Nenana R., Dresher L. Tsusena Butte - aesthetic quality; major sheep hunting area IM~j or sheep hunting stea;,bird watching at Summit L. I No Known No known No known No known No known Parallels'Denali Hwy beyond Brushkana Ck. drainage to G iNo known Cabins near Tsusena Butte Cabins near Summit Follows pr op osed Sasitna access road along Devil Creek approx,.3 mi.1 cabins along uevil Creek drainage follows proposed Susit ns access road from Watana to just s ~,of Deadman Mt.; occasional cabins; landing strip along, Denali Hwy;airporf near G AH HJ AG Cf AJ follows proposed Susitna access road from Tsusena Creek to Hi{fl Lake; lodge at High Lake JC Generally follows proposed Susitna access rd.;lodge at 'High Lake Mining claims,cabins i':l'Portage Creek area HI a.Tall shru,b,:a1"der;,low shrub:dwatf birch l and/or willdw;open spruce:black (wet)or white spruce ,25%-60%cover; woodland,spruce:white or bla~k ~pruce,0%-25%cover~mixed forest:spruce-birch. j.- ~-------~ TABLE 8.2.7.6:ENVIRONMENTAL INVENTORY -NORTHERN STUDY AREA (HEA~Y TO FAIRBANKS)i (Page 1 of 2) Length (millis) Number of Roed Croesings Number of River/ Creek Croesings Topography SoilsY Land Ownerahip/lI Status Existing/Propoaed Developmenta Existing Rights-of Way Scenic Quality/ Recreation Cultural Resourcea AB 40 2 hwy (Park).3 traila (1 winter>.2 unim- proved rds ••I rail- rosd 3 rivers.15 creeks Follows Nensna River north at 1000'to Browne-crossea River; n.w.to Clear MEWS at 500' IRIO A to e.of Dry Ck.- small Fed.Parcel;••• to s.of Clear MEWS and at B-mostly SPTA. small parcels of p. small Fed.Nat.Allot. along Nenana R.;Clear MEWS area-parcel CIRI Selection.and U.S. Army Wdl.land Scat tared residential and other usee along Parke Hwy;cabin near Browne;air atrip at Healy Generally parallele Parke Hwy.RR and trans.line-Healy to Browne Parka Hwy-acenic area; rafting.kayaking on Nenana R. Dry Ck.arch.eite near Healy;good possibility for other sites;DATA VOID f£ 50 Parks Highway, 1 winter trail 1 river.25 creeks Clear MEWS (500') north across plain (400'),n.e.across Tanana River Valley to Ester (600') Near B-IRIO;flats a. of Tanana River-IQ2; Tanana River-IQ3; Tanana R.to Ester- IRI4 B to 1-1/2 mi n.- SPTA;•••to s.to Tansna R.-SS;•••to Tanana R.-P;•••to crossing l.Goldstream· Ck.-mostly SPTA;•••to Bonanza Ck.Crossing - SS;•••to nesr C-SP; remainder-DATA VOID Scattered residential and other uses along Parks Hwy;cabin at Tanana R.crossing Followa w/in aeveral mi.Parke Hwy.RR,and trans.line;more closely follows Parka Hwy.and trans.Une and aled rd.n.of of Tanana R. Parks Hwy-eceni~area; hunting,fishing Good poasibility for arch.aites;DATA VOID Corridor Segment roc 46 1 winter trail 2 rivera.29 creeka Clear MEWS (500'), n.e.across plain to a point about 24 mi. due a.of Eeter;n. acrosa plain to Tanana R.(400')and n.to Ester Near B-IRIO.Remainder -IQ2 B area -SPTA;Fish Ck. to Tanana R.-data void remainder-SPTA,8I\P with P at C and just n. of Tanana R. Ft.Wainwright Hil. Reservation No known Wide open flat-high visibility;enow- mobiling in flata e. of Fairbanks Good possibility fDr arch.sitea;DATA VOID AE 65 I hwy.(Parks), 1 trail I river 50 creeka l Up Healy Ck.to pass st 4500';down WDDd R. drainsge tD Japan Hilla (1100');ateep mta.; valleya Near A-IRIO;rot.baae- IQ25;mt.area-RHl; near E-IRI A tD Nenana R.-small Fed.Parcel;•••to e. Df GDld Run-SPTA ••• remainder-DATA VOID Air at rips-Healy and Cripple/Healy Cka. cDnfluence;cabins- CDdy Ck/WoDd R., SnDW Ht.Gulch Parallels small rd.- near Healy tD CDal Ck.;amall RR-Healy to Suntrana;trail at pass between Healy and Cody Cks. Scenic quality data vDid;Healy Ck.-rafting area Dry Ck.arch.site near Healy;few arch.sites in mDuntains;maybe near Japan Hills;DATA VOID EOC 50 7 trails 2 rivers,22 creeks Japan Hilla (1100') n.w.Dn plain alDng WDod R.;thrDugh Wood R.Buttes area, n.acrDSS Tanana R.; n.to Ester Near E-IRI;between E and Dpen flats- IRIO;open flata IQ2;Tanana R.-IQ3; Eater-IRl4 Same aa BOC nDrth Df the Tanana River Ft.Wainwright Hil. Res.;WDDd R.Butte VABH ND knDwn Wide Dpen flats-high viaibility;anow- mobiling in flata a. of Fairbanks High pDssibility fDr arch.sites;DATA VOID EF 40 Several roads in Fairbanka depending upDn exact route;3 trails 2 rivera,10 creeks, Salchaket SIDugh Japan Hilla (1100')n. acroas plain to Tanana R.(500');n.tD Fairbanks Near E-IRl;a.section of flats-IRIO;flats-IQ2; Fairbanks-IQ3 DATA VOIO Ft.Wainwright Hil. Rea.;cabin-WDod R. crDssing a.Df Clear Butte Parallels Bonnifield Trail -Clear Ck.Butte to Fairbanks;trsns.line juet s.Df Fairbanks Wide open flats-high visibility Arch.sites have been identified fDr the Ft. Wainwright and Blair Lakes areas '~l TABLE B.2.7.6 (Page 2 of 2) Vegetation!! fish Resourcee21 Bird~ furbearers.61 Big Game.61 AB Southern end-da~a void NortherneOd-low shrub,eedge-grase tundra Grayling.burbot i••long- nose.sucker.Do~ly Varden.round.white- fish.slimyrsculpin Importsnt ~)d~n eagle habitat na'!r A Prime habitat-15 mi. from Nenana to B from Nenans R.to B- prime moose and impor- tant black bear habitat;fr,om A ~orth­ wsrd about 10 mi~-prime moose habit~t . oc S.of Tsrana River-wet old river floodplain, low shrup a~d sedge- gress bogs;ITanans R. crossingrwi~low and alder ahrubltypea, white sPfuc~,balaam poplar forests slong river;nL o~Tanana R. -open a~cloaed de- ciduous ~bl~ch and aspen)forsats on alopes,~/woodlsnd spruce spd bogs,low shrub,and ~st sedge- grsss onlVa~ley bottoms Grayling~~rbot.long- nose suc~er~Dolly Varden.round white- fish.slimy iaculpin. sslOlon (~oho king. chum).s~se~Ish;lske chub possibleI! I . Prime pe~egr~ne.hsbitst st Tsna~R.I;prime waterfowl habitat slang Tanana RJ s.1 of corridor I I I !Prime haDitat-from Clear ME~S ac.ross the Tanana I ! Clear MEWS to across Tanana RJ-prtme mooss and imporl'tan~blsck bear hsbJ!,tat;n~of Bonanza Ck.Exp. foreat-p~ime!blsck bear habirat! Corridor Segment IDC Probably wet,low shrub,andlisedga-grass. alder shrub,lowland spruce;n.lof Tansna- uplsnd deciduous forests ! Ssme as OC Near Totatlanika Ck. to Tanena ft.-prime waterfowl habitat; near Wood n.-important rapt or hab~tat;be­ tween O&C ~y Tanana R. -prime per~grine habitat ! Prime habitiat from B to across ~anana Rive I B to across,Tanana R. -prime moo~e.important black bea~hsbitat; Wood R.to Uust s.of the Tanana R.-prime black bear·habitat i AE DATA VOID Same aa AB Important golden eagle habitat at A &along Healy !Ck.s.of Usibelli Pk,prime peregrine habitat on Keevy Pk. Prime habitat from E to the s.about 15 mi. Usibelli to Japan Hills-prime moose & caribOu habitat, between A.&Mystic Mt .-prime sheep habitat;E to the s.- import••black bear habitat mc Probably similar to IDC Same as AB.lske chub possible from Wood R.Buttes to n.of Tansns R.-prime waterfowl hsbitat; between D&C along the Tanans R.-prime peregrina habitat Prime hllbitat from E to just n.of Tsnana River E to just n.of Tansna R.-prime moose.impor- tant black besr hsbitat;Wood R.to just s.of Tsnana R.~ prime,black besr Ef Probably similar 'to EDC; wet Same as Be with the excep- tion of coho sslmon.which is not recordsd N.of Blsir Lake Air force Renge to the Tanana R.- prime wsterfowl habitat; s.of fairbanks along Tanana R.-prime bald eagle habitat Prime habitst from E to Tsnana River E to tanana R.-prime mooae and important black bear habitat;Clear MEWS to Tanans R.-prime black bear habitat J!Assumes corridor is located on r.side of Healy Ck.fori most .of its length.n.sidelof Cody Ck ••and n.~.aida of Wood R. 11 So~rcsl United Ststes Dept.ofl~griculture.Soil conss~vs~ion Service 1979 ..See T~ble B.42 for explanation of soil units. I !.11 Source I CIRI/Holmes and Narver.1900.P=Private.5PT~=S~ete Patented or Tentatively Approved;sp=state Patented;SS=State Selection.BAP=Borough Approved or Patented. !I Tall shrub=alder;low shrub=dwarf birch,end/or wtllOW;!open spruce=blsck (wet)or ~ite spruce,25~60~cover;woodland spruce=white or black spruce,10~-25~ccover;mixed foreat=spruce-birch.'..I Source I VanBallenberghe personal communication.Primelhabitat=minimum amount of land neceesary to provide sustained yield for that species;based upon knowledge of that species'nesds from experience of AOf&G personnel.Importsnt habitat=land which the AOf&G considera not aa critical to a species aa is Prime habitat but is valuable. 21 Little data available. ~ ,' Sources.of information in thia tab~el Alsska Dept.of fishlan~Game 1970a and Morrow 1900. •...ib!!.:..-.'---'.k-.,~--'._-,;;.;....: TABLE B.2.7.7:SOIL ASSOCIATIONS WITHIN THE PROPOSED TRANSMISSION CORRIDORS -GENERAL DESCRIPTION,OFFROAD TRAFFICABILITY LIMITATIONS (ORTL),AND COMMON CROP SUITABILITY (CCS)a EFI -Typic Gyofluvents -Typic Cryaquepts,loamy,nearly level (Page 1 of 3) -Dominant soils of this association consist of well-drained,stratified, waterlaid sediment of variable thickness over a substratum of gravel, sand,and cobblestones.Water table is high in other soils,including the scattered muskegs.ORTL:Slight -Severe (wet;subject to flood- ing);CCS:Good -Poor (low soil temperature throughout growing season). E01 -Typic Cryorthents,loamy,nearly level to rolling -This association occupies broad terraces and moraines;most of the bed- rock is under thick deposits of very gravelly and sandy glacial drift, capped with loess blown from barren areas of nearby floodplains.Well- drained,these soils are the most highly developed agricultural lands in Alaska.ORTL:Slight;CCS:Good -Poor. IQ2 -Histic Pergelic Cryaquepts -loamy,nearly level to rolling The dominant soils in this association are poorly drained,developed in silty material of variable thickness over very gravelly glacial drift. Most soils have a shallow permafrost table,but in some of the very gravelly,well-drained soils,permafrost is deep or absent.ORTL: Severe -Wet;CCS:Poor IQ3 -Histic Pergelic Cryaquepts -Typic Cryofluvents,loamy,nearly level -Soils of this association located in low areas and meander scars of floodplains are poorly drained silt loam or sandy loam;these are usually saturated above a shallow permafrost table.Soils on the natural levees along existing and former channels are well-drained,stratified silt loam and fine sand;permafrost may occur.ORTL:Severe (wet);CCS:Unsuit- able (low temperature during growing season;wet)-Good (but subject to flooding). IQ25 -Pergelic Cryaquepts -Pergelic Cryochrepts,very gravelly,hilly to steep -Soils of this association occupying broad ridgetops,hillsides,and valley bottoms at high elevation are poorly drained,consisting of a few inches of organic matter,a thin layer of silt loam,under which is very gravelly silt loam;permafrost table is at a depth greater than 2 feet. In locations of hills and ridges above tree line these soils are well- drained.ORTL:Severe (wet,steep slopes);CCS:Unsuitable (wet;low soil temperature;short,frost-free period). a.Source:U.S.Department of Agriculture,Soil Conservation Service 1979. See Table B~43 for definitions for Offroad Trafficability Limitations and Common Crop Suitability. ! TABLE B.2.7.7 (Page 2 of 3) IRI -Typic eryochrepts,loamy,nearly level to rolling r ) , 1 -On terraces and outwash plains,these soils are well-urained,having a thin mat of course organic matter over gray silt loam.In slight depres- sions and former drainage ways,these are moderately well-drained soils, having a thin organic mat over silt loam,with a sand or gravelly sub- stratum.ORTL:Slight-Moderate;ees:Good.r TRIO -Typic eryochrepts,very gravelly,nearly level to rolling -Aeric erya- quepts,loamy,nearly level to rolling -Generally well-to moderately well-drained soils of terraces,outwash plains,and low moraines.Typically,these soils have a silt loam upper ·1 lay~r over gravelly soils.Pockets of poorly drained soils with a shal- low permafrost table occupy irregular depressions.ORTL:Moderate- Severe (we.t);ees:Good -Poor (wet;low soil temperature throughout growing season;short,frost-free period). IR14 -Alfie eryochrepts,loamy,hilly to steep -Histic Pergelic eryaquepts, loamy,nearly level to rolling On mid-slopes,these soils are well drained,of micaceous loess ranging to-many feet thick over shattered bedrock of mica schist.Bottomland I areas are poorly drained with a relatively thick surface of peatmoss.In .] ~Qi I!;,perntafrost r~l1g~s fJ:()m 5..30 inches in depth.ORTL: Moderate -Severe (steep slope;wet);CeS:Poor (steep slopes;highly susceptible to erosion). IU3 Perge1ic eryumbrepts,very gravelly,hilly to steep -rough mountainous land On high alpine slopes and ridges close to mountain peaks,these soils have a thin surface mat of organic material beneath which is an 8 to 12- ---..~~."_.__._..._--_.__."---'-'-~i-nc1:f;;;;t1fi-clt-;--'~da-rk'--b-r'own~--'h-o'ri~z'on--f·onne·d--'···-i-n·-very·---g'·rave-1-1y---or·_·,s -tony loam . .---..--------·--·--~~·---·---·--Th±s--a·s·s·o·c-i·a~t·i_o-n---a-l-s·o-i-nc-l-ude·s-·-a-r:e-a·s·---o·f--ba-:re-~r.oc·k-an<i-s.t-o.nJ7---I.u.b.b_Le o_n _ mountain peaks.ORTL:Severe (short,frost-free period)-Very Severe (steep slope);ees:Unsuitable (short,frost-free period;shallow bedrock)• RMI -Rough Mountainous Land SOl -Typic eryorthods,loamy,nearly level to rolling -Sphagnic Borofibrists, nearly level .1 -Low hills,terraces,and outwash plains have well-drained soils formed in silty loess or ash,over gravelly glacial till.Depressions have poorly drained,fibrous organic soils.ORTL:Slight -Very Severe;ees:Good (on well-drained soils)-Unsuitable (wet organic soiO. TABLE B.2.7.7 (Page 3 of 3) S04 -Typic Cryorthods~very gravelly,nearly level to rolling -Sphagnic Borofibrists,nearly level -Soils of nearly level to undulating outwash plains are well-drained to excessively well-drained,formed in a mantel of silty loess over very gravelly glacial till.Soils of the association located in depressions are very poorly drained,organic soils.ORTL:Slight -Very Severe; ees:Good -Unsuitable (wet,organic). S05 -Typic eryorthods,very gravelly,hilly to steep -Sphagnic Borofibrists, nearly level -On the hills and plains,these soils,formed in a thin metal of silty loess over very gravelly and stony glacial drift,are well drained and strongly acid.In muskegs,most of these soils consist of fibrous peat. ORTL:Severe (steep slope);ecs:Unsuit~ble (steep slopes;stones and boulders;short,frost-free season). SOLO -Humic Cryorthods,very gravelly,hilly to steep -Generally,these are well-drained soils of foothills and deep mountain valleys,formed.in very gravelly drift with a thin mantel of silty loess or mixture of loess and volcanic ash.These soils are characteristically free of permafrost except in the highest elevation.ORTL:Severe (steep slope);ees:Poor -Unsuitable (low soil temperature throughout growing season;steep slopes). S015 -Pergelic eryorthods -Histic Pergelic eryaquepts,very gravelly,nearly level to rolling -On low moraine hills,these soils are well drained,formed in 10 to 20 inches of loamy material over very gravelly glacial drifts.On foot slopes and valleys,these soils tend to be poorly drained,with shallow permafrost table.ORTL:Slight -Severe (wet);ecs:Unsuitable (short, frost-free period;wet;stones and boulders). S016 -Pergelic Cryorthods very gravelly,hilly to steep -Histic Pergelic Cryaquepts,loamy,nearly level -On hilly moraines these soils are well-drained;beneath a thin surface of partially decomposed organic matter,the soils have spodic horizons developed in shallow silt loam over very gravelly or sandy loam.In valleys and long foot slopes,these are poorly drained soils,with a thick,peaty layer over a frost-churned loam or silt loam.Here,depth of permafrost is usually less than 20 inches below surface mat.ORTL: Severe (steep slope;wet);ees:Unsuitable (short,frost-free period)- Poor (wet;low soil temperature). TABLE B.2.7.8:DEFINITIONS FOR OFFROAD TRAFFICABILITY LIMITATIONS AND COMMON CROP SUITABILITY OF SOIL ASSOCIATIONSa OFF ROAD TRAFFICABILITY LIMITATIONS (ORTL) (Page 1 of 3) ,J .•..'J -I., Offroad Trafficability refers to cross-country movement of conventional wheeled and tracked vehicles,including construction equipment.Soil limitations for Offroad Trafficability (based on features of undisturbed soils)were rated Slight,Moderate,Severe,and Very Severe on the following bases: -Slight Soil limitations,if any,do not restrict the movement of cross-country vehicles. -Moderate Soil limitations need to be recognized but can generally be overcome with careful route planning.Some ,special equipment may be required. -Severe Soil limitations are difficult to overcome,and special equipment and careful route planning are required.These soils should be avoided if possible. -Very Severe Soil limitations are generally too difficult to overcome.Generally, these soils are unsuitable for conventional offroad vehicles. COMMON CROpb SUITABILITY (CCS) Soils were rated as Unsuitable,Good,Fair,and Poor for the production of common crops ·ou-the-following-bases:------- -Unsuitable Soil or climate limitations are generally too severe to be overcome. None of the common crops can be grown successfully in most years,or there is danger of excessive damage to soils by erosion if cultivation is attempted. a.Source:U.S.Department of Agriculture,Soil Conservation Service 1979. b.The principal crops grown in Alaska--barley,oats,grasses for hay and silage,and potatoes--were considered in preparing ratings.Although only these crops were used,it is assumed that the ratings are also valid for vegetables and other crops suited to Alaskan soils. I,'J, ] '( ,j 'j TABLE B.2.7.8 -Good (Page 2 of 3) i ! I I Soil or climate limitations,if any,are easily overcome,and all of the common Alaskan crops can be grown under ordinary management practices. On soils of this group -- (a)Loamy texture extends to a depth of at least 18 inches (45 cm). (b)Crop growth is not impeded by excessive soil moisture during the grow~ng seasons. (c)Damage by flooding occurs no more frequently than 1 year in 10. {d)Slopes are dominantly less than 7 percent. (e)Periods of soil moisture deficiency are rare,or.irrigation is economically feasible. (f)Damage to crops as a result of early frost can be expected no more frequently than 2 years in 10. (g)The hazard of wind erosion is estimated to be slight. -Fair Soils or climate Common crops can may be required. limitations need to be recognized but can be be grown,but careful management and special On soils of this group overcome. practices (a)Loamy texture extends to a depth of at least 10 inches (25 cm). (b)Periods of excessive soil moisture,which can impede crop growth during the growing season,do not exceed a total of 2 weeks. (c)Damage by flooding occurs no more frequently than 2 years in 10. (d)Slopes are dominantly less than 12 percent. (e)Periods of soil moisture deficiency are infrequent. (f)Damage to crops as a result of early frost can be expected no more frequently than 3 years in 10. (g)There is no more than a moderate hazard of wind erosion. TABLE B.2.7.8 -Poor (Page 3 of 3)I, I Soils or climate limitations are difficult to overcome and are severe enough to ) make the use questionable.The choice of crops treatment or management practices are required. overcoming the limitations may not be feasible. is narrow,and special In some places, On soils of this group (a)Loamy texture extends to a depth of at least 5 inches (12 cm). (b)Periods of excessive soil moisture duringc>the growing season do not exceed a total of 3 weeks. (c)Damage by flooding occurs no more frequently than 3 years in 10. (d)Slopes are dominantly less than 20 percent. (e)Periods of soil moisture deficiency are frequent enough to severely damage crops. (f)Climatic conditions permit at least one of the common crops,usually grasses,to be grown successfully in most years. } ,) i. TABLE B.2.7.9:ECONOMICAL AND TECHNICAL SCREENING SOUTHERN STUDY AREA (WILLOW TO ANCHORAGE/POINT MACKENZIE) -Length (miles) -Max.Elev.(ft) -Clearing (miles)= Medium &Light None -Access (miles)= New Roads 4-Wheel -Tower Construction* -Rating: Economical Technical A =recommended corridor C =acceptable but not preferred F =unacceptable (1) ABC' 73 1400 61 12 20 53 329 C C (2) ADFC 38 400 20 18 o 38 180 A A (3) AEFC 39 400 15 24 12 27 176 C A *Approximate number of towers required for this corridor, assuming single-circuit line. rABlE B.2.7.10:ECONOMICAL AND TECHNICAL SCREENING CENTRAL!STUDY AREA (DAM SITES TO INTERTIE) I (1 )(2)!(3)(4)(5),(6)(7)(8) (9)(10)(11)(12)(13)(14)*(15) ABCD ABECD AJCf ABCJHI ABECJH[CBAHI CEBAHI CBAG CEBAG CJAG CJAHI JACJHI ABCf AJCD ABECf !, -Length 40 45 41 77 82 68 75 90 95 91 69 70 41 41 45 I -Max.Elevation,ft.2500 3600 3500 4300 430P 4300 3500 3300 3600 3500 3800 3900 2500 3500 3600 -Clearing Medium &Light 38 30 26 18 30 20 27 45 37 40 55 17 39 26 35 None 2 1~15 59 50 48 46 45 60 51 14 53 2 15 10 -Access New Roads 28 31 12 58 49 44 53 44 49 13 27 44 41 5 45 4-Wheel 12 12 29 8 8 3 3 46 46 78 23 26 0 36 0 -Tower Construction*180 20~185 347 369 306 338 405 428 410 311 315 185 185 203 -Rating: Economical C Ci C f fl C f f f f C f C A C Technical A Ci C f f!F C C C C C C C A C I A =recommended C =acceptable but not preferred F =unacceptable *Approximate number of towers requ.ire,d for this'corridor, assuming single-circuit line.! __i_~---- TABLE B.2.7.11 ECONOMICAL AND TECHNICAL SCREENING NORTHERN STUDY AREA (HEALY TO FAIRBANKS) (1)(2)(3).(4) ABC ABDC AEDC AEF -Length 90 86 115 105 -Max.Elevation 1600 1600 4500 4500 -Clearing Medium &Light 48 50 40 50 None 42 36 75 55 Access New Roads 0 0 54 42 4-Wheel 90 43 42 16 -Tower Construction*405 387 518 473 -Rating: Economical A A C C Technical A C F F A =recommended C =acceptable but not preferred F =unacceptable *Approximate number of towers required for this corridor, assuming single-circuit line. TABLE B.2.7.l2:SUMMARY OF SCREENING RESULTS RAT I N G S Corridor Env.Econ.Tech.Summary -Southern Study Area (1)ABC'C C C C (2)ADFC A A A A (3)AEFC F C A F -Cental Study Area (1)ABCD C C A c (2)ABECD F C C F (3)AJCF C C C C (4)ABCJHI F F F F (5)ABECJHI F F F F (6)CBAHI F C F F (7)CEBAHI F F C F (8)CBAG F F C F (9)CEBAG F F C F (10)CJAG F F C F (11)CJAHI F C C F (12)JACJHI F F C F (13)ABCF C C C C (14)AJCD A A A A (-15-)ABECF F C C -Northern Study Area (1)ABC A A A A (2)ABDC C A C C (3)AEDC F C F F (4)AEF F C F F A =recommended C =acceptable but not preferred F =unacceptable I I ~I ,l ,1 '( 1 ) I ) I I I ! ! ) I 1 I ) j TABLE B.217.13:ENVIRONMENTAL CONSTRAINTS -SOUTHERN STUDY AREA (WILLOW TO ANCHORAGE/POINT MACKENZIE) 1 (ABC') Corridor Segment 2 (ADFC)3 (AEFC) Length (miles) Topograph /Soils Land Use Aesthetic Cultural ~esourcesl/ Vegetatio Fish ResoUrces Wildlife 73 Some soils with severe limita- tions to off road travel;some good agricultural soils No existing ROW in AB;resi- dential uses near Palmer; proposed capital site;much U.S.Military Wdl.,Private, and Village Selection Land Iditarod Trail;trail paral- leling Deception Ck.:Gooding L.birdwatching area;5 crossings of Glenn Hwy,1 crossing of Parks Hwy Archeologicsites -DATA VOID Wetlands along Deception Ck. and at Matanuska River crossing;extensive clearing in upland,forested areas needed 5 river and 28 creek cross- ings;valuable spawning sites, especially salmon:Knik area, Matanuska area,DATA VOID Passes through or near water- fowl and shorebird nesting and feeding areas,and areas used by brown bear 38 Most of route potentially wet, with severe limitations to off road travel;'some good agricultural soils Trail is only existing ROW; residential and recreational areas;susitna Flats Game Refuge;agricultural land sale susitna Flats Game Refuge; Iditarod Trail;1 crossing of Parks Hwy Archeologic sites -DATA VOID Extensive wetlands;clearing needed in forested areas 1 river and 8 creek crossings; valuable spawning sites, especially salmon:L.susitna R.,DATA VOID Passes through or near water- fowl and shorebird nesting, feeding,and migration areas, and areas used by fur bearers and brown bear 39 Same as Corridor 2 No known existing ROW;recrea- tional use areas,including Nancy Lakes;lakes used by float planes;agricultural land sale Lake area south of Willow; lditarod Trail;1 crossing of Parks Hwy Archeologic sites -DATA VOID Extensive wetlands;clearing needed in forested areas 1 river'and 8 creek crossings; valuable spawning sites, especially salmon:L.susitna R.,DATA VOID Same as Corridor 2 Environmental Ratingl!C A F 1-1 Coastjal area probably has many sites;available literature not yet reviewed. 2-1 A =Jecommended;C =acceptable but not recommended;F =unacceptable I~ABlE 8.2.7.14:ENVIRONHENTALICONSTRAINTS CENTRAL STUDY AREA (DAM SITES TO INTERTIE)(Page 1 of J) 1 (ABeD)!2 (AI£CO) Corridor Segment J (AJCF)4 (AIlCJHI)5 .(AI£CJHI) Environmental Retingl!C Length (miles) Topography/Soila Land Use Aaathetica Cultural Raaourcea Vegetation Fieh Reaources Wildlife Reaourcea 40 Cr08!JaaaBveral daep ravinea;1 about 1000'change in ~leva-I tion;!aome wet aoUa ! Little exieting ROW except Corpa Rd.;mostly Village Sel~ction:and Private Lands Fog lakesI Stephan Lake , Archeolog~c aitea near watanal dam .aHe,Stsphan lake and fog lakaa;DATA VOID from Gold Ck~ to Devil Canyon;hiatoric I aitesnea~the communities of Gold Creek and Canyon ! Wetlanda fneastern third of i corrIdor;'extensive forest-i clearing needed I 1 river and 17 creek cross- inga;valusble spswning areas, especially;grayling:DATA VOI~ i unide.ntified rapt or nest Ii located on trib.to Susitns; passeathrough,habitat for:II raptors;furbaarera,wolves, wolverine,:brown bear,cariboti I 45 Crosaea aeveral deep raviJea; about 2000'chenge in ele~a­ tion;some.steep slopes;~ome wet eoils little exieting ROW exceptl Corpa Rd.and at 0;rec.and reaid.areaa;float plane: areaa;moatly Village Selec- tion and Private lsnda I 1 '.·1,fog lakes,Stephan lake;pro- :poaed railroad extenaion,high Icountry (Prairie &Chulitna :Ck.drainages)and viewshed of !Alaaka Range ISame ss Corridor 1 !Wstlsnda in eastern half of ~orridor;extenaive foraat~ :clearing needed ~river and 17 creek cross~ ~ngs;vslusble spawning areaa, ,eapecially grayling:DATA ~OIO 1 Paaaaa through habitat forI ~aptora,waterfowl.migrsting ,owans,furbearere,:cariboui wolves,wolverina,brown ' J f 41 Crosaes several,deep ravinea; sbout 2000'change in eleva- tion;some ateep alopea;aome aome wet aolls No existing ROW except at f; rec.areae;float plane areae; mostly Village Selection and Private Land;reaid.&rec. devalopment in area of Otter l.and old aled road Viawahed:of Alaaka Range & 'High lake;propoaed acceae road Archeologic aites by.Hatana dam site,&near Port'liga Ck.l Susitna R.confluenca,poasi- ble aites elongSuaitna R.; hiatoric aitea near communi- tiea of Gold Ck.and Canyon foreat-clearing.needed in weatern half 14 creek croeaing,valuable spawning areas,especially grayling and salmon I Indian River,Portage Creek,DATA VOID Golden eagle nest along Devil Ck.near High l.,active raven neat on Devil Ck.;passea through habitat ,forI raptora, furbearera,wolvee,brownbaar C n Crosses several deep ravinea; >2000'change in elevation; routing above 4000';eteep alopea;aome wet soils; shallow bedrock in mta. No existing ROW,rec.areaa ieolated cabine;lakee ueed by float planes;much Village Selaction land foglakee;Stephan·lake;pro- poeed acceee road;viewahed of Alsska Range Archeologic eitee near WataOB dam aite,Stephan L.and fog lakea;poeeible aitea along paae between drainagee,DATA VOID betwean H and "I Small wetland Brese in JA area;exteneive foreet- clearing needed;DATA VOID 1 river and 42 creek croee- inge;valuable epawning areae, eepecially grayling Golden eagle neet along Devil Ck.near High L.;caribou movement area;psaaee through habitat for I reptora,watar- fowl,furbearere,wolves, wolverine,brown bear f 82 Croasea several deep ravinea; chan gee in elevation >2000'; routing above 4000';steep slopes;eome wet eoilei ehallow bedrock in mts. Same aa corridor 4 fog lakee;Stephan Lske;High Lake;propoeed accees rosd; viewshed of Alaska Ranga Same as Corridor 4 WBtlands in JA and Stephan Lake areas;exteneive foreat-clearing neaded 42 creek crosainga;valuable spawning areaa,especially grayling and salmon:DATA VOID Same as Corridor 4 with impor- tant waterfowl and migrating ewan habitat at Stephan laka f }j ,IA=recommended,C =acceptabl~but not recommended,f =unacceptablej·i ---" ,~---- TABlE 8.2.7.114 (Page 2 of 3) Cor ridor Segment 6 (CIlAHI)7 (CEIlAHI)8 (CBAG)~(l::E81!1!)10 (CJAG) length (mile Topography/Sbila land Uae Aeathatica cultural Raauurcea Vegatation Fiah Reaourcea Wildlife ReaGurcea Environmanta!Rating 68 Croases aeveral dsep ravinsa; changea in elevation of about 1600';routing above 4000'; steep alopea;BomB wet aoils; shallow bedrock in mta. No known exiating ROW;rec. areas and iaolated cabina; float plana area;Suaitna area and near I are Village Selec- tion lands Fog lakes and Staphan lake; Tsusena Butte;viewshed of Alaska Range Archeologic aitas naar Watana dam aite,Fog lakes &Stephan lake;DATA VOID between H and I Extenaive wetlands from 8 to near Tausena 8utte;extensive forest-clearing needed 32 creek crosainga;valuable apawning areas,espacially grayling:DATA VOID 8ald eagle nest a.e.of Teuaena Butte;erea of caribou movament;paasea thrOUgh habitat forI raptora,water- fowl,furbearera,wolvea, wolvarine,brown bear F 73 Croases saveral deep ravinea; change in elevation of about 1600';routing abova 3000'; steep alopaa;aoma wet soila; shallow bedrock In mta. Same aa Corridor 6 For Fog lakes and Stephan lake;high country (Prairie- Chunlina Cka.);Tauaana Butte; viewahed of Ala aka Range Sama aa Corridor 6 Extensive wetlands in Stephsn l.,Fog lskea Tsusena Butte sress;extensivs foreat- clesring needed 45 creek crossings;vsluable spswning areas,eapecially grayling:DATA VOID Same aa Corridor 6,with important waterfowl and migrating awan habitat at Stephan lake F 90 Crosaes aeveral deep ravinea; change in elevation of about 1600';routing above 3000'; ateep alopes;some wat Boils; ahallow bedrock in mta. No exiating ROW;rec.areas and isolated cabina;float plane areas;air atrip and airport;much Village Selec- tion and Federal land Fog lakea;Stephan lake; •access road;scenic area of Deadman Ck.;viewahed of Alaaka Range Archeologic aites by near Watana dam aite,Fog lakea, Stephan Lake end along Deadman Ck. Wetlanda between 8 and moun- tains;extenaive forest- clearing needed 1 riv,er and 43 creek croas- inga;valuable spawning areaa, espacially grayling:DATA VOID Important bald eagle habitat by Denali Hwy.&Deadman L.; unchecked bald eagle neat near Tsusena Butte;passes through habitat forI raptors,fur- bearera,wolvea,wolverine, brown baar F h" 95 Crosses several deep ravines; changaa in alevation of about 1600';routing above 3000'; steep alopes;aome wet aoila; shallow bedrock in mta. Same aa Corridor 8 Fog lakes;Stephan lake;pro- posed acceas road;high country (Prairie and Chunilna Cks.);Deadmsn Ck.;viewshed of Alaska Range Same as Corridor 8 Wetlands in Stephan L./Fog "Lakes areaa;extenaive foreat-clearing needed 1 river and 48 creek cross- ings;valuable spawning areas, especially grayling:DATA VOID Sama aa Corridor 8,with important waterfowl and migrating swan habitat at Stepahn Lake F 91 Same as Corridor 8 No exiating ROW;rec.areas and isolated cabina;float plane areas;air strip and airport; mostly Village Selection and Fadaral land High Lakes area;proposed accesa rosd;Deadman Ck.drainage;view- shed at Alaska Range Archeologic sites naar Watana dam aite and along Deadman Ck. Small wetlands in JA area; extans~ve forest-clearing needed 1 river and 47 creek cross- ings;vslusble spswning sreas, especislly grayling:DATA VOID Golden esgel neat sIong Devil Ck.near High lake;unchecked bald esgel nest near Tsusena Butte;area of caribou movement; passes through habitst for: raptors,waterfowl,furbearers, brown besr F TABlE 8.2.7.14 (Page J of J) ::¢orridor Segment 11 {!:JAHI)12 (JA-CJf!I)IJ (ABCF)~(A.lCQL __12 (AgCr) length (miles)69 jo 41 41 145 Topography/Soila land Use Aesthetice Culturel Resources Crossee 'eeveral deep ravines; changes 1n elevation of about 1000';r~uting:above JOOO'; steep elopea;aome wet aoila; shallow bedrock in mta. No exiating ROW;rec.areas & iaolated cabins;float plane areas;mostly ,Village Selec- tion and Private land High lake~araa;propoaed acceaa road;viewahed of Alaaka Rrnga ; i Archeologic aitea near Watana dam site!' Same BB Corridor 11!' :INoexiating ROW;rec.areaa ~d !iaolated cabina;float plane area;mostly Villaga Salection and Private land i High lakea area;propoaed Bcce~a road,Tsuaena Butte; yie~ahedofAlaskaRange ~rch~0109ic site,near Wahoo ~m ~ite;possible eite~ ~ass:between drainages !' Crossea several deep ravinea; about 1000'change in eleva- tion;some wet soile No known exieting ROW;except at f;rec.areea;float plane areas;reaid.and rec.use near OHer l.and old aled rd.;iaolated cabins;moatly Village Selection land;aoma Pri vate land fog lakea,Stephan l. Archeologic aitea n~ar Watana dam eite,Portage Ck./Suaitna R.confluence;Stephan l.'and fog lakea;historicieitee near communitiea of Canyon and Gold Ck. Croaaes deep ravine at Devil Ck.;about 2000'change in elevation;routing above 3000';some steep alopea; some wet soila little exieting ROW except Old Corpa Rd.and at 0;rec. areaa;iaolated cabins;much Village Selection land;some Private land Viewehed of Alaska Range and High lake;propoaed acceea road Archeologic eitea by Watana dam aite,poesible aitee along Sueitoo R.;historic sltsa near communitiea of Canyon and Gold Ck. Croases several deep ravines; sbout 2000'change in elevation; some wet soils No known existing ROW except at F;rec.areas;float plane areas;resid.and rec.use near Otter l.&old sled rd.; isolatsd cabins;mostly Village Selection land with some Private land fog lakes;Stephan lake;high country (Prairie andChulina Cka. drainages);viawahed of Alaska Range Same as Corridor 13 f f Wetlande in eaetern half of corridor;extensive forest- clearing needed 15 creek croseings;valuable spawning areas,expecially grayling and salmon:Indian River,Portage Ck.,DATA VOID Important waterfowl and migrating swan hsbitat at Stephan l.;pasaes through habitat for:raptors,water- fowl,furbesrers,wolves, wolverine"brown bear,caribou Golden eagel neet in Devil Ck./High lake area;active raven nest on Devil Ck.; pasaea through habitet for: reptors,furbearers,wolves, brown bear,caribou A 1 river and 16 creek cross- ings;veluable spawning areas, eapacially grsyling:DATA VOID forest-clearing needed in weet ern half Wetlands in eastern third of corridor;extensive forest- clearing needed 15 creek croasings;:valusble spswning aress,especially grayling and salmon:Indian River,Portage Ck.,DAT~VOID Unidentified ~aptor :nsst on tributary to ~uaitnB;paases through habitst for:raptors, furbearers,wolves,wolverine, brown bear,csribou C Small wetland areaa in JA areal fairly extensive foreat- ~leaffng needed 40 c~eek croasings;vsluable qpaw~ing sreas,especislly gray~ng and salmon:DATA VOID I ' I ! dOldl,n eagle nest along De.vil Ok.tJoar,High Lake;pasaea ~hrough habitat for:rapt ora, ~urbearera,wolves,brown bear! Ifl :!,': Small wetland areas 1n JA area;aome foreat-clearing needed I 36 creek croaainga;valuable spawning araaa',eapecially grayling and ealmon:DATA VOID Golden eagle neat along Devil Ck.near:High lake;beld eagle neat a.e.of Tausena Butte; passeathroughihabitat for:' raptora,!furbearera,brown bear ' Vegetetion Wi'ldlife Resources Environmental Rating fish Resourcee TABlE B.2.7.15:ENVIRONMENTAL CONSTRAINTS NORTHERN STUDY AREA (HEALY TO fAIRBANKS) length (mHes) 1 (AOC) 90 2 (AIn:) 86 Corridor Segment J (AEOC) 115 4 (AEf) 105 TopographyJsoils land Use Aesthetics Cultural Resources Vegetation fish Resoutces Wildlife Resourcesl! Some wet soils with severe limita- tions to off-road traffic Air strip;residential aresa and isolated cabina;some U.S.Military Withdrawal and Native land J crossinga of Parks Hwy;Nsnana R.-scenic area Archeologic sites probable since there is a known eite nearby;DATA WID Extensive wetlande;forest-clearing needed msinly north of the Tanana River 4 river and 40 creek crossings; valuable spawning sites:Tanana River,DATA VOID Paases through or near prime hsbitat for:peregrinea,waterfowl,fur- bearera,moose;passes through or near important habitat for:pere- grinee,golden eagles Severe limitations to off-road traffic in wet soils of the flats No exiating ROW n.of Browne; scattered reeidential and isolated cabins;airstrip;fort Wainwright Military Reservation J crossinge of Parks Hwy;high visibility in open flats Dry Creek archeologic eite near Healy;possible sites elong river crosaings;DATA VOID Probsbly extensive wet lends between Wood and Tanana Rivers;extensive foreat-clearing needed n.of Tanana River 5 river and 44 creek croesings; valuable spawning sites:Wood River, DATA VOID Passes through or near prime hsbitat for:peregrinee,waterfowl,fur- bearers;paeses through or near important habitat for:golden eagles,other raptors Chsnge in elevation of ebout 2500'; steep elopes;shallow bedrock in mts.;ssvere limitations to off- rosd traffic in the flats No existing ROW beyond Healy/Cody Ck.confluence;isolated cabins; airstripa;fort Wsinwright Military Reservation 1 crosaing of Parks Hwy.;high visibility in open flata Dry Creek archeologic aite near Hesly;possible sites near Japsn Hills and in the mta.;DATA VOID Probably extensive wstlands between Wood and Tansna Rivers;extensive foreat-clearing neelkld n.of Tanana River;data lacking for southern part J river and 72 cresk croasings; valuable spawning sitea:Wood River, DATA VOID Passes through or near prime habitat for:peregrines,waterfowl,fur- burers,caribou,aheep;passss thrOUgh or near important-habitat for:golden eagles,brown besr Same aa Corridor J Airatrips;isolated cabins; fort Wsinwright Military Reservation High visibility in open flats Archeologic sites near Dry Creek and fort Wainwright;possible sites nesr Tanans River;DATA VOID Probsbly extensive wetlands between Wood and Tansns Rivers J river snd 60 creek crossings; valusble spawning sites:Wood River,DATA VOID Passes through or near prime hsbitat for:peregrines,bald eagles,waterfowl,furbeerers, caribou,sheep;passea thrOUgh or near important habitat for: golden eagles,brown bear Environmental Ratingl!A C f f l-/sourCl:VsnBallenberghe persons1 communication.Prime habitat =minimum amount of land necesaary to prOVide a sustained yield for a species;based upon knowledge of tha species'needs from eeperience of ADf&G personnel.Important habitat =land which ADf&G considers not as critical to a species as ia Prime habitat, but ia valuable. 2-1 A =r commended,B =acceptable but not preferred,C =unaccepta~le TABLE B.2.7 .16:TEffiNI CAL,EOONOMIC AND ENVIRONMENTAL CRITERIA USED IN OORRIOOR SCREENING Technical Primary J ) I j Topography Climate and Soils Length Elevat ion Secondary Economic Primary Secondary Envi ronme nta 1 Primary Vegetation and Clearing Highway and River Crossings Length PresenC!3 of Right:-of-Way Presence of Access Roads Topo~raphy Stream Crossings liighW~y~C'i'['l,4RailrQC'icl CroE.si.rrg§_ Aesthetic and Visual Land Use Presence of Existing Right-of-Way Existing and Proposed Development Length Topography Soils Cultural Reservoir Vegetation Fishery Resources Wildli fe Resources } 1 ../ 1 Table B.3.1.1:PERTINENT DATA FOR GAGING STATIONS USGS Gage Susitna Drainage p,eriods of Record Station Name Number River Mile Area (mi 2 )Streamflow (Continuous)17 Water QualityV Agency Susitna River nr.DenalI 15291000 290.8 950 5/57-9/66,11/68-Present 1957-66,1968-69,1974-Present USGS (6/30/82) Cantwell 15291500 223.1 4,140 5/61-9/72,5/80-Present 1962-72,1980-Present (7/27/82)USGS Cantwell -223.1 4,140 -1980-81 R&M Consult. Susitna River nr.Watana Damsite -182.i1/5,180 8/80-Present 10/80-12/81 R&M Consult. Susitna Rliver at Gold Creek 15292000 136.6 6,160 6/49-Present 1949-58,1962,1967-68,1974-Present USGS (9/16/82) Susitna Rliver at Gold Creek -136.6 6,160 -1980-Present (10/14/82)R&M Susitna Rliver at Sunshine 15292780 83.9 11,100 5/81-present 1971,1975, 1977,1981-Present (10/13/82) Susitna Rliver at Susitna Station 15294350 25.8 19,400 10/74-Present 1955,1970,1975-Present (10/5/82)USGS Maclaren IRiver nr.Paxson 15291200 259.aM 280 6/58-Present 1958-61,1967-68,1975 USGS Chulitna IRiver nr.Talkeetna 15292400 98.o!V'2,570 2/58-9/72,5/80-Present 1958-59,1967-72,1980-Present USGS (6/3/82) Ta1keetnal River nr.Talkeetna 15291500 97.o!V'2,006 6!.64-Present 1954,1966-Present (10/14/82)USGS Skwentna IRiver nr.Skwentna 15294300 28.021 2,250 1O/59-Present 1959,1961,1967-68,1974-75,USGS 1980-81 Yentna Riwer nr.Susitna Station 15294345 28.o!V'6,180 10/80-Present 1981-Present (8/11/82)USGS t recent data available. a continuous water quality monitor was installed at river mile 183.0. mile at tributary's confluence with Susitna R~ver. mile at Yentna-Susitna confluence. 1~All ~treamf1ow gage stations are currently active,however,flow data included in this document is through September 1981. 2-1 "Pre6ent"in periods of record indicates station is active as of January 1983.A date after "Present"indicates the 3-1 4-1 5-1 Source:IUSGS and R&M ----~--~-,-~--_.._----~_.._--" -~---------,~_._--..--'"----.~~-------~._._~.------- TABLE B.3.1.3:WATANA NATURAL MONTHLY FLOWS (CFS) YEAR OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP ANNUAL 1951 3299 1107 906 808 673 620 1302 11650 18518 19787 16478 17206 7734 1952 4593 2170 1501 1275 841 735 804 4217 25773 22111 17356 11571 7777 1953 6286 2757 1281 819 612 671 1382 15037 21470 17355 16682 11514 8035 1954 4219 1600 1184 lO88 803 638 943 11697 19477 16984 20421 9166 7401 1955 3859 2051 1550 1388 1051 886 941 6718 24881 23788 23537 13448 8719 1956 4102 1588 1039 817 755 694 718 12953 27172 25831 19153 13194 9051 1957 4208 2277 1707 1373 1189 935 945 10176 25275 19949 17318 14841 8381 1958 6035 2936 2259 1481 1042 974 1265 9958 22098 19753 18843 5979 7770 1959 3668 1730 1115 1081 949 694 886 10141 18330 20493 23940 12467 8011 1960 5166 2214 1672 1400 1139 961 1070 13044 13233 19506 19323 16086 7954 1961 6049 2328 1973 1780 1305 1331 1965 13638 22784 19840 19480 10146 8603!1962 4638 2263 1760 1609 1257 1177 1457 11334 36017 23444 19887 12746 9833,1963 5560 2509 1709 1309 1185 884 777 15299 20663 28767 21011 10800 9278 I 1964 5187 1789 1195 852 782 575 609 3579 42842 20083 14048 7524 8263 1965 4759 2368 1070 863 773 807 1232 10966 21213 23236 17394 16226 8451 1966 5221 1565 1204 1060 985 985 1338 7094 25940 16154 17391 9214 7374, 1967 3270 1202 1122 1102 1031 890 850 12556 24712 21987 26105 13673 9096 I 1968 4019 1934 1704 1618 1560 1560 1577 12827 25704 22083 14148 7164 8032 1969 3135 1355 754 619 608 686 1262 9314 13962 14844 7772 4260 4912 1970 2403 1021 709 636 602 624 986 9536 14399 18410 16264 7224 6115 1971 3768 2496 1687 1097 777 717 814 2857 27613 21126 27447 12189 8589 1972 4979 2587 1957 1671 1491 1366 1305 15973 27429 19820 17510 10956 8963 1973 4301 1978 1247 1032 1000 874 914 7287 23859 16351 18017 8100 7112 1974 3057 1355 932 786 690 627 872 12889 14781 15972 13524 9786 6314 1975 3089 1474 1277 1216 1110 1041 1211 11672 26689 23430 15127 13075 8403 1976 5679 1601 876 758 743 691 1060 8939 19994 17015 18394 5712 6835 1977 2974 1927 1688 1349 1203 1111 1203 8569 31353 19707 16807 10613 8233 1978 5794 2645 1980 1578 1268 1257 1408 11232 17277 18385 13412 7133 6992 1979 3774 1945 1313 1137 1055 1101 1318 12369 22906 24912 16671 9097 8184 1980 6150 3525 2032 1470 1233 1177 1404 10140 23400 26740 18000 11000 8908 1981 6632 3044 1790 1858 1592 1262 1641 .14416 16739 27601 30542 11669 9985 1982 5700 2650 1863 1700 1234 898 1196 10879 21444 20445 13206 13890 7968 1983 5154 2132 1893 1797 1610 1427 1565 11672 20401 18761 20862 11192 8253 MAX 6632 3525 2259 1858 1610 1560 1965 15973 42842 28767 30542 17206 9985 MIN 2403 1021 709 619 602 575 609 2857 13233 14843 7772 4260 4912 MEAN 4567 2064 1453 1225 1035 936 1158 10625 22980 20747 18366 10875 8046 B.3.1.4:DEVIL,CANYON NATURAL MONTHLY FLOWS (CFS) YEAR OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP ANNUAL 1950 5,758 2~405 1,343 951 736 670 802 10,491 18,469 21,383 18,821 7,951 7,482 1951 3,652 1,231 1,031 906 768 697 1,505 13,219 19,979 2,157 18,530 19,799 8,574 1952 5,222 2,539 1,758 1 484 943 828 ,879 7,990 30,014 24,862 19,647 13,441 8,884 1953 7,518 3,233 1,550 1 000 746 767 1,532 17,758 25,231 19,184 19,207 13,928 9,305 1954 5,109 1,~21 1,387 1 224 930 729 1,131 15.;'286 23,188 19,154 24,072 11,579 8,809 1955 4,830 2,507 1,868 1 649 1,275 1,024 1,1O~8,390 28,082 26,213 24,960 13,989 9,658 1956 4,648 1,189 1,207 922 ,893 852 867 15,979 31,137 29,212 22,610 16,496 10,551 1957 5,235 2,774 1,987 1 583 1,389 1,105 1,190 12,474 28,415 22,110 19,389 18,029 9,633 1958 7,435 3,590 2,905 1 792 1,212 1,086 1,437 11,849 24,414 2,163 21,220 8,689 8,808 1959 4,403 2,000 1,371 1317 1,179 878 1,120 13,901 21,538 23,390 28,594 15,330 9,585 1960 6,061 2,623 2,012 1 686 1,340 1,113 :1.,218 14,803 14,710 21,739 22,066 18,930 9,025 1961 7,171 2,760 2,437 2 212 1,594 1,639 2,405 15,031 27,069 22,881 21,164 12,219 9,965 1962 5,459 2,~44 1,979 1 796 1,413 1,320 1,613 12,141 49,680 24,991 22,242 14,767 10,912 1963 6,308 2,696 1,896 1 496 1,387 958 811 17,698 24,094 32,388 22,721 11,777 10,353 1964 5,998 2,085 1,387 978 900 664 697 4,047 47,816 21,926 15,586 8,840 9,244 1965 5,744 2.;645 1,161 925 829 867 1,314 12,267 24,110 26,196 19,789 18,234 9,507 1966 6,497 1,908 1,478 1 279 1,187 1,187 1,619 8,734 30,446 18,536 20,245 10,844 8,663 1967 3,844 1,458 1,365 1 358 1~268 1,089 1,054 14,436 27,796 25,081 30,293 15,728 10,398 1968 4,585 2,204 1,930 1 851 1,779 1,779 1,791 14,982 29,462 24,871 16,091 8,226 9,129 1969 3,577 1,532 836 687 682 770 1,421 10,430 14,951 15,651 8,484 4,796 5,318 1970 2,867 1,146 810 757 709 772 1,047 10,722 17,119 21,142 18,653 8,444 7,012 1971 4,745 3,082 2,075 1 319 944 867 986 3,428 31,,031 22,942 30,316 13,636 9,614 1972 5,537 2~912 2,313 2 036 1,836 1,660 1,566 19,777 31,930 21,717 18,654 11,884 10,152 1973 4,639 2,155 1,387 1 140 1,129 955 987 7,896 26,393 17,572 19,478 8,726 7,705 1974 3,491 1,463 997 843 746 690 949 15,005 16,767 17,790 15,257 11,370 7,114 1975 3,507 1,619 1,487 1 490 1,342 1,272 1,457 14,037 30,303 26,188 17,032 15,155 9,567 1976 7,003 1,853 1,008 897 876 825 1,261 11,305 22,814 18,253 19,298 6,463 7,655 1977 3,552 2,392 2,148 1 657 1,470 1,361 1,510 11,212 35,607 21,741 18,371 11,916 9,411 1978 6,936 3,211 2,371 1 868 1,525 1,481 1,597 11,693 18,417 20,079 15,327 8,080 7,715 1979 4,502 2,324 1,579 1 304 1,204 1,165 1,403 13,334 24,052 27,463 19,107 10,172 8,965 1980 6,900 3,955 2,279 1 649 1,383 1,321 1,575 11,377 26,,255 30,002 20,196 12,342 9,936 1981 7,335 3,382 1,841 1 958 1,839 1,470 1,898 15,789 18,387 31,680 35,256 13,033 11,156 1982 6,384 3,270 2,207 2 086 1,559 1,094 1,574 12,490 ~4,439 22,877 14,536 16,427 9,079 1983 6,272 2,454 2,192 2 098 1,858 1,596 1,781 13,777 22,789 20,295 23,203 12,731 9,254 MAX 7,518 3,955 2,905 2 212 1,858 1,779 2,405 19,777 47,816 32,388 35,256 19,799 11,156 MIN 2,867 1,146 810 687 682 664 697 3,428 14,710 15,651 8,484 4,796 5,318 MEAN 5,374 ·2,402 1,693 1 415 1,202 1,074 1,324 12,404 25,821 23,025 20,600 12,420 9,063 ~--~'---: B.3.1.5:GOLD CREEK NATURAL MONTHLY FLOWS (CFS) OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP ANNUAL 950 6335 2583 1439 1027 788 726 870 11510 19600 22600 19880 8301 8032 951 3848 1300 1100 960 820 740 1617 14090 20790 22570 19670 21240 9106 952 5571 2744 1900 1600 1000 880 920 5419 32370 26390 20920 14480 9552 953 8202 3497 1700 1100 820 820 1615 19270 27320 20200 20610 15270 10090 954 5604 2100 1500 1300 1000 780 1235 17280 25250 20360 26100 12920 9682 955 5370 2760 2045 1794 1400 1100 1200 9319 29860 27560 25750 14290 10256 956 4951 1900 1300 980 970 940 950 17660 33340 31090 24530 18330 11473 957 5806 3050 2142 1700 1500 1200 1200 13750 30160 23310 20540 19800 10384 958 8212 3954 3264 1965 1307 1148 1533 12900 25700 22880 22540 7550 9476 959 4811 2150 1513 1448 1307 980 1250 15990 23320 25000 31180 16920 10560 960 6558 2850 2200 1845 1452 1197 1300 15780 15530 22980 23590 20510 9712 961 7794 3000 2694 2452 1754 1810 2650 17360 29450 24570 22100 13370 10809 962 5916 2700 2100 1900 1500 1400 1700 12590 43270 25850 23550 15890 11565 963 6723 2800 2000 1600 1500 1000 830 19030 26000 34400 23670 12320 11073 964 6449 2250 1494 1048 966 713 745 4307 50580 22950 16440 9571 9800 965 6291 2799 1211 960 860 900 1360 12990 25720 27840 21120 19350 10169 966 7205 2098 1631 1400 1300 1300 1775 9645 32950 19860 21830 11750 9432 967 4163 1600 1500 1500 1400 1200 1167 15480 29510 26800 32620 16870 11219 968 4900 2353 2055 1981 1900 1900 1910 16180 31550 26420 17170 8816 9811 969 3822 1630 882 724 723 816 1510 11050 15500 16100 8879 5093 5596 970 3124 1215 866 824 768 776 1080 11380 18630 22660 19980 9121 7591 971 5288 3407 2290 1442 1036 950 1082 3745 32930 23950 31910 14440 10251 972 5847 3093 2510 2239 2028 1823 1710 21890 34430 22770 19290 12400 10886 973 4826 2253 1465 1200 1200 1000 1027 8235 27800 18250 20290 9074 8086 974 3733 1523 1034 874 777 724 992 16180 17870 18800 16220 12250 7631 975 3739 1700 1603 1516 1471 1400 1593 15350 32310 27720 18090 16310 10275 976 7739 1993 1081 974 950 900 1373 12620 24380 18940 19800 6881 8189 977 3874 2650 2403 1829 1618 1500 1680 12680 37970 22870 19240 12640 10109 978 7571 3525 2589 2029 1668 1605 1702 11950 19050 21020 16390 8607 8195 979 4907 2535 1681 1397 1286 1200 1450 13870 24g90 28880 20460 10770 9489 980 7311 4192 2416 1748 1466 1400 1670 12060 29080 32660 20960 13280 10748 981 7725 3569 1915 2013 1975 1585 2040 16440 19300 33940 37870 13790 11961 982 7463 3613 2397 2300 1739 1203 1783 13380 26100 24120 15270 17780 9800 983 6892 2633 2358 2265 1996 1690 1900 14950 24510 21150 24500 13590 9926 8212 4192 3264 2452 2028 1900 2650 21890 50580 34400 37870 21240 11961 IN 3124 1215 866 724 723 713 745 3745 15500 16100 8879 5093 5596 EAN 5840 2589 1832 1527 1301 1156 1424 13425 27554 24337 21852 13340 9733 II I TABLE B.3•1.6:WEEKL~STREAMFiLOW AT WATANA (CES)l/(Page 1 of 5) I II j ~EAR I I 656 628 1950 802 774 7~9 869 876 791 559,512 576 558 523 550 557 6q3 717 1,711 6,115 10,442'10,845 13,591 14,369 13,924 21,992 16;255 15,817 17,953 19,6~1 21,345 21,448 19,853 18,160 14,972 11,275 8,096 9,178 6,205 6,282 4,54 1 4,029 3,518 2,007 .1,248 1,176 1,103 1,042 994 903 903 903 903 1951 828 812 812 812 ,757 667 667i 667 641 618 618 6,189 618I5427001,OJ 1 1,861 4,923 14,338 15,945 7,915 13,828 26,695 19,247 12,238 17,232 18,4Q4 21,682 20,7 °19,074 17,891 14,413 15,312 14,985 21,048 24,531 15,237 15,738 15,226 I 2,690 1,928 1,489 1,4897,559 5,055 3,6~4 2,855 2,793 1,908 1,761 1,489 1,489 1952 1,349 1,299 1,2~9 1,299 1,069 819 819 819 784 730 730 730 730 796 796 7~6 696 ,909 1,132 1,549 3,357 16,784 19,892 28,174 30,555 27,039 23,526 16,714 21,31F 23,150 30,727 19,888 15,618 11,855 13,935 15,561 10,522 9,086 12,430 8,559 7,982 5,5~6 4,049 2,938 3,377 2,164 2,542 1,913 1,250 1,250 1,250 1,250 1953 880 820 820 820 722 598 498 598 606 678 678 678 678I 4~6 486 7~5 1,308 1,007 13,666 12,435,21,448 6,652 2].,821 21,482 17,488 20,466 17,377 15,695 17,0~0 17,745 20,931 17,859 14,312 14,731 17,519 14,058 12,806 10,679 9,299 6,126 50,809 3,748 2,971 1,821 1,738 1,608 1,497 1,361 1,174 1,174 1,174 1,174 1954 1,120 1,099 1,0~9 1,099 1,099 984 794 794 794 716 630 630 630 506 506 8~0 930 4,308 8,521 13,802 15,823 14,807 19,799 19,022 18,245 22,178 19,307 15,396 14,9~1 14,981 24,614 20,049 20,049 20,049 18,930 11,256 9,676 9,025 6,621 4,746 4,461 3,3~9 3,359 2,716 2,159 2,032 1,796 1,756 1,657 1,624 1,431 1,431 1955 1,546 1,561 1,338 1,249 1,179 1,052 1,052 949 979 879 879 879 879 I82882884 8 828 2,519 3,321 3,882 11 ,626 12,771 17 ,007 27,727 30,081 28,168 29,660 24,776 19,124 22,869 20,805 19,270 19,771 24~039 34,146 17,921 13,691 11,128 10,015 I6,059 4,461 3,6~3 3,129 2,062 1,721 1,581 1,393 1,306 1,027 1,027 1,027 1,027 1956 848 310 810 810 809 750 750 750 739 689 689 689 689 641 641 641 641 1,798 8,483 12,106 24,085 15,966 27,294 35,522 26,081 22,994I24,335 26,536 26,7~9 26,153 24,666 ,446 29,285 16,173 ·13,792 11,446 16,046 15,637 11,446 5,279 5,279 3,5~3 3,300 2,789 2,342 2,247 2,123 '2,035 1,908 1,852 1,509 1,509 1957 1,399 1,378 1,3~8 1,378 1,310 1,193 1,193 1,193 1,079 920 920 920 920 837 837 8~7 837 2,452 4,269 4,269 15,611 23,050 31,747 28,053 24,892'17,043 19,864 18,252 20,4~3 22,198 17,659 17,664 17,568 16,III 17,894 14,143 15,435 15,008 16,474 7,628 6,544 5,3V 5,503 3,997 3,287 2,815 2,314 2,837 2,991 2,551 1,902 1,544 '------..~ I",,-------,: B.3.1.6 (Page 2 of 5) 19518 1.939 1.514 1,408 1.332 1,101 1,152 1.038 959 959 1,024 1,000 939 939 950 1.063 1,153 1,398 3.001 5,917 8,267 15,742 16,842 24,642 24,642 21,247 19.363 18,442 18,442 18.442 18.082 32,829 23,946 17,783 14,415 9.969 6,695 6,695 5.128 5.862 4.604 5,050 3,865 2,689 2.392 2,068 1.760 1,352 1,215 797 879 1,375 1.375 19519 1.150 1.190 1.056 1,035 1,051 1,027 984 879 797 683 683 683 683 666 666 952 999 1,891 2.951 12,694 17,856 14,298 20,496 15,311 18.247 20,418 21.688 20,819 22,556 17,816 18,373 14.392 18,474 34.121 33,290 20,953 10.824 8.131 8,765 8.534 5.896 3,243 4.051 2,692 2,292 2.194 2,064 1.962 1,656 1.656 1,656 1,656 1.541 1.523 1,360 1,295 1.227 1,175 1.152 1,096 1,062 1,041 996 882 882 694 694 910 945 4.703 6.668 12.886 20,055 29.716 11,838 12,275 12,710 13.971 19,936 14,780 17,003 23,312 26.486 20.467 18,086 17,477 16,811 14,281 22,570 15,996 13,691 9,778 7,102 5,050 3.678 2,753 2.516 2.319 2.958 2.118 2,126 2.985 1.833 1.833 1.776 1,773 1,825 1.846 1.601 1.317 1,297 1,246 1,181 1.097 1,222 1.535 1.535 1,617 1.617 1,783 1,811 5,580 10,306 17,835 16,989 15.795 14.578 23.810 29.749 24.996 18,341 19,253 19.937 29.655 22,581 23.083 19,710 18,708 13.842 9,309 10.560 10,059 11.578 8.304 3,663 3.663 3.663 2.910 2.187 2.187 2,187 2.967 1,742 1.742 1,742 1,742 1,645 1.626 1,626 1.626 1.462 1.237 1.237 1.237 1.207 1~174 1,174 1,174 1.174 1.336 1.335 1.335 1.335 3.165 3,896 10.571 15,580 25.042 25,502 49,464 42,296 29.941 24.659 24.067 20.979 24,659 22,051 19,487 19.487 19.487 19,844 18,961 11.972 9.699 11.158 7.677 5.856 5.094 4,603 3,273 2,427 2.427 2,427 2.243 1,684 1,684 1.684 1.684 1,346 1.303 1,303 1,303 1,284 1.203 1.203 1,203 1.015 870 870 870 870 680 680 680 2.138 2,871 16,185 26,173 29,395 20,039 20,039 20,039 20,039 20,039 25,591 30.081 31,343 26.765 24,772 22.882 19,853 20,996 17,689 13,134 11,736 8.384 9.514 7.204 6,067 4,963 3,760 2,277 2,937 1,803 1,489 1.454 1,358 1,.311 1,038 1,038 913 888 830 807 815 818 802 760 696 612 588 524 524 588 588 637 646 524 521 699 1.548 17 ,791 66,753 45.845 38,257 27.669 22.261 22.938 21.646 14,854 16.893 15,984 12.889 13,741 11.603 8.901 7.255 7.294 7,139 5.814 6,596 4.258 3,387 2,593 2.408 2,383 2.656 1.708 1.175 1.047 952 952 880 866 866 866 821 764 764 764 785 809 809 809 809 1.050 1.050 1.324 1,370 1.702 4.582 7,973 14,365 28,598 18,020 19.249 18.396 27.076 25,264 25,478 23,730 20,581 18,313 16,343 25,247 16.925 9.394 14,093 17,314 15.844 20,946 10,948 6.087 2.852 2,359 2,043 1.676 1.481 1.412 1.361 1,265 1.223 1.174 1.129 1.075 1.062 1,062 1,062 1.026 980 980 980 983 985 985 985 985 1,091 1.091 1,432 1.490 2.210 2,873 5,322 10.202 16,017 37,660 26,954 22,768 19,214 15,178 14.458 15,132 17,122 22,511 18,320 15.064 18.252 14,605 10,023 9,733 9,623 8.022 5,525 3.605 2,802 1,896 1,290 1.192 1,192 1,192 1,173 1,119 1,119 1,119 1,119 ~; ~--' TABLE B.3.1.6 (Page 3 of 5) YEAR I I 1967 1,105 1,106 1,106 1,106 1,077 Ii.037 1,037 1,037 965 882 882 882 882 771 771 790 910 1,409 41,044 14,066 19,680 23,533 22,187 29,069 24,227 23,703 17,634 16,574 24,423 28,466 21,665 2°1,177 44,290 24,653 16,555 23,511 13,875 10,087 8,761 5,636 4,692 3,669 2,797 2,340 11,987 1,881 1,812 1,780 1,740 1,740 1,669 1,657 1968 1,633 1,634 1,634 1,611 1,552 11,561 1,561 1,561 1,561 1,560 1,560 1,560 1,560 1,544 14,885 1,556 1,552 1,787 21,353 10,464 27,061 21,911 21,507 29,938 20,356 22,099 24,724 22,504 21,723 2(},991 18,327 161,541 13,759 12,436 11 ,024 9,099 9,115 5,821 5,903 4,162 3,593 2,768 2,457 2,109 11,631 1,241 1,084 901 809 767 724 687 1969 658 640 ,598 1,598 598 i 587 599 630 630 655 673 709 732 779 919 1,196 1,696 2,867 5!,116 9,727 17,064 10,290 11,525 14,689 15,092 14,614 13,051 16,518 16,974 1~,188 11,668 12~201 6,318 5,126 4,792 5,256 4,595 3,939 3,781 3,018 2,841 2,489 1,680 1,~32 .11,202 950 842 784 735 699 694 694 1970 656 656 628 617 618 1628 589 589 589 605 616 645 645 769 846 969 1,176 1,634 31,900 13,817 12,474 15,221 12,989 12,531 11,864 19,977 22,089 16,855 18,059 17,267 21,606 18~880 14,586 16,486 11,350 9,396 7,477 7,616 4,850 4,991 4,166 3,393 2,885 2,923 2~796 2,543 2,249 2,013 1,886 1,761 1,614 1,446 1971 1,328 1,188 1,080 9,50 880 1821 746 746 730 716 716 716 716 717 744 808 I 904 1,098 1\,415 2,987 3,683 6,558 19,251 39,740 24,136 33,340 21,395 21,771 25,092 16,325 20,943 38~945 34,819 21,362 16,880 19,170 12,233 9,251 9,174 6,619 5,931 4,501 3,711 3,005 21,717 2,574 2,430 2,311 2,015 2,015 1,860 1,860 1972 1,790 1,642 1,642 1,642 1,643 1~528 1,465 1,464 1,403 1,416 1,351 1,351 1,329 1,241 1,241 1,189 ~,241 2,386 13',753 13,553 18,894 31,966 20,142 35,772 31,327 21,178 22,096 22,084 19,683 16,050 18,343 19~674 18,045 18,653 12,473 11,598 15,857 11,686 6,032 4,296 3,976 5,515 ~,090 2,727 2~210 1,887 1,738 1,519 1,356 1,210 1,186 1,186 1973 1,051 1,026 1,026 +,026 1,035 1~008 .1,008 1,008 ,929 868 868 ,868 868 879 879 879 929 1,227 2~355 8,066 11,190 13,811 17,385 28,985 31,344 20,593 18,980 18,143 13,728 14,810 15,752 18\,754 14,942 19,441 20,593 11,210 7,823 6,605 6,133 4,607 3,710 2,558 1,938 1,693 1~459 1,344 1,230 1,129 1,028 926 881 854 1974 816 ,811 778 . I 765 745 1707 694 662 663 648 636 605 605 594 620 747 l,189 2,059 5~341 9,964 22,246 25,280 16,013 13,675 12,785 13,651 14,383 17 865 16,395 1~,766 14,730 15~504 13,265 10,498 14,244 13,395 7,511 6,590 11,410 4,537 4 590 2,402 1,602 1,468 1 1,478 1,478 1,478 1,461 1,264 1,264 1,264 1,264 1975 1,270 1 203 1,203 1,203 1,200 1~123 1,123 1,081 1,051 1,040 1,040 1,040 1,040 1,036 1 047 1,142 ~,354 2,133 5~138 11,291 17,252 23,081 30,459 22,880 28,749 25,700 23,413 25 455 24,131 22,076 20,265 16~199 15,474 13,658 11,.762 9,359 15,849 14,847 14,301 7,559 6 664 6,139 3,621 2,720 1~937 1,475 1,173 1,011 925 80 855 809 i of 5) 778 778 750 739 741 746 746 746 726 687 687 687 687 644 675 839 1,402 3,440 9,778 9,397 9,828 11,375 23,100 24,887 17,525 16,928 16,991 16,954 15,164 15,476 20,226 26,317 19,534 15,004 10,554 6,302 5,160 5,190 6,320 3,729 3,045 2,903 2,576 2,139 1,963 1,839 1,736 2,097 1,902 1,722 1,583 1,462 1,442 1,400 1,326 1,294 1,257 1,219 1,197 1,197 1,156 1,106 1,106 1,106 1,106 1,149 1,149 1,211 1,272 1,314 2,267 8,205 12,588 19,531 29,414 38,954 .31,928 28,489 18,502 20,572 21,740 18,089 19,531 18,939 17,328 17,519 11,066 8,643 12,235 11,736 11,288 8,782 6,882 6,046 4,510 3,355 2,862 2,578 2,392 2,223 2,108 2,015 1,955 1,808 1,741 1,641 1,557 1,496 1,403 1,285 1,247 1,247 1,212 1,258 1,258 1,258 1,275 1,251 1,251 1,251 1,322 3,355 11,862 16,195 10,959 11,660 13,979 19,417 16,614 20,703 19,608 18,215 18,416 18,064 16,600 15,674 14,572 12,160 8,756 9,287 8,372 6,293 5,367 4,195 4,701 3,796 2,849 2,736 2,368 1,774 1,558 1,502 1,483 1,349 1,214 1,170 1,185 1,138 1,138 1,138 1,059 1,067 1,067 1,067 ,989 1,113 1,113 1,113 1,113 1,064 1,113 1,228 1,545 2,451 4,633 10,811 17,246 28,470 25,470 21,379 19,302 23,880 22,832 22,584 27,495 28,100 21,732 20,356 15,431 13,993 12,415 7,911 7,704 11,339 10,260 6,672 8,469 5,948 4,395 4,084 3,698 4,120 2,949 2,811 2,297 2,069 1,890 1,711 1,607 1,535 1,451 1~379 1,345 1,285 i,224 1,176 1,175 1,177 1,177 1,177 1,177 1,122 1,122 1,179 1,604 3,462 8,212 11,764 10,518 16,714 25,823 20,349 26,351 22,988 26,281 26,663 38,137 25,275 28,150 19,051 18,006 16,331 11,948 8,723 9,329 15,679 11,706 8,532 7,605 6,326 5,214 3,950 3,534 2,637 2,685 2,707 2,175 1,678 1,578 1,516 1,448 1,584 1,961 2,118 2,142 1,911 1,594 1,265 1,190 1,194 1,274 1,297 1,314 1,238 1,291 1,373 1,779 4,737 17,566 17,640 11,625 19,077 15,465 14,949 16,085 18,788 14,090 33,261 32,516 29,007 31,168 30,077 38,871 30,803 20,047 15',158 12,220 10,197 9,485 5,901 5,560 5,713 6,627 3,364 2,845 2,782 2,339 2,057 1,971 1,860 1,794 1,794 1,697 1,695 1,695 1,695 1,729 1,662 1,212 ,881 ,767 ,826 ,826 ,874 1,123 ,956 ,956 1,057 1,403 2,641 6,274 11,618 15,603 17 ,916 21,638 18,090 23,883 23,173 16,689 20,637 2,979 23,533 20,306 13,970 12,157 10,610 11,835 10,670 13,360 21,010 13,236 7,782 6,119 4,982 2,921 2,384 2,252 2,137 1,997 1,944 1,850 1,850 1,850 1,965 2,201 1,906 1,590 15,588 1,553 15,335 1,540 1,685 1,583 1,534 1,437 1,389 1,280 1,185 1,208 1,411 ,197 3,484 8,419 14,537 12,909 18,671 23,758 17,019 29,754 ,20,568 22,463 19,352 16,152 17,431 17,935 22,829 21,149 18,683 22,728 15,528 9,607 8,465 11,118 9,429 7,833 6,641 4,560 4,967 2,833 2,462 2,258 2,113 2,947 1,961 1,887 1,826 TABLE B.3.1.6 (Page 5 of 5) MAX MIN MEAN 2,201 1,517 .29,660 10,948 656 486 13,051 3,018 1,274 906 20,412 6,392 1,906 1 617 33 261 8 469 640 486 14.458 2,841 1,235 925 20 804 5 356 1,971 1,783 32,516 6,641 598 603 13,728 2,402 1,204 1,043 20,963 4,235 i2,118 1,907 2i9,007 ;6,627 598 641 1;4,188 i1,602 i1 ,190 i1,232 2:0,393 13,403 2,142 10,007 32,829 4,984 598 524 11,668 12,248 1,137 2,792 21,250 2~650 1,911 Q,566 38,945 3,698 587 521 1 ,201 ,176 1,060 6,260 1~,718 2,264 1,650 17,834 44,209 4,120 559 699 6,318 950 1,019 19,667 18,857 2,027 1,685 27,061 34,121 2,949 512 1,548 5,126 842 987 14,705 17,190 1,868 1,583 31,966 34,145 2,811 576 6,558 4,792 787 ,944 18,439 15,445 1,748 1,560 66,753 24,531 2,911 558 11,525 5,256 735 ,920 22,802 12,573 1,556 1,560 49,464 22,570 2,551 ,523 12,275 5,495 699 ,918 24,502 11,279 1,482 1,560 42,296 21,010 1,955 ,524 11,864 3,939 694 923 23,194 10,324 1,405 1,560 33,340 20,946 1,965 524 13,651 3,781 687 930 21,895 9,788 1,370 1/Flows are presented in stdnd~rd weekly periods of seven days,beginning with week number one (Dec.31 - Jan.6)and continuing ac~oss at thirteen weeks per line.The 39th week is an eight day period (standard water week 52 [Sept.23 -ISept.30])and the flow for this period is the total eight day flow divided by seven as used in the rese~voir operation p~ogram.This flow in week 39 is the average flow multiplied by 1.143.I -L-'-----' (Page 1 of 5)WEEKLY STREAMFLOW AT DEVIL CANYON (CFS)l/ 937 903 910 1,015 1,017 905 639 586 662 658 618 666 741 645 653 707 841 2,073 7,412 12,653 13,142 16,482 16,076 15,579 24,604 18,186 18,806 20,005 21,876 23,788 23,852 22,094 20,211 16,662 12,546 8,782 9,955 6,732 6,814 5,002 4,460 3,893 2,221 1,390 1,308 1,227 1,159 1,105 1,029 1,029 1,029 1,029 928 911 911 911 849 763 763 763 732 693 ,693 ,693 693 632 812 1,247 2,166 5,578 16,270 18,094 8,982 15,694 28,723 20,708 13,168 18,542 20,078 23,579 22,556 29,742 20,059 16,216 17,229 16,860 23,677 28,254 17,550 18,128 17,537 8,578 5,735 4,169 3,240 3,275 3,051 2,256 2,2?1 2,060 1,744 1,744 1,744 1,744 1,547 1,512 1,512 1,512 1,242 913 913 913 876 823 ,823 ,823 823 865 865 865 865 1,070 1,348 1,844 3,994 19,808 23,151 32,788 35,561 31,470 26,455 18,796 24,021 26,032 34,530 22,572 17,722 13,454 15,784 18,093 12,236 10,567 14,453 10,249 9,557 6,653 4,848 4,640 3,958 2,537 3,109 2,241 1,518 1,518 1,518 1,518 1,076 1,001 1,001 1,001 882 728 728 728 737 770 ,770 ,770 770 515 515 833 1,384 11,682 16,151 14,696 25,346 19,715 32,683 25,237 20,543 24,040 19,114 17,262 18,775 19,518 24,005 20,574 16,487 16,972 20,191 17,049 15,531 12,951 11,276 7,420 6,152 4,514 3,597 2,199 2,085 1,928 1,796 1,633 1,374 1,374 1,374 1,374 19154 1,260 1,236 1,236 1,236 1,105 923 923 923 834 718 1,718 ,718 718 585 585 1,006 1,067 5,588 11,134 18,035 20,674 19,401 23,4;45 22,525 21,603 26,262 21,613 17 ,237 16,771 16,771 29,010 23,623 23,623 23,623 22,350 14,288 12,282 11,456 8,406 5,953 5,593 4,211 4,211 3,316 2,637 2,487 2,197 2,140 1,995 1,956 1,723 1,723 1QI55 1,838 1,855 1,589 1,483 1,401 1,280 1,280 1,280 1,153 1,010 1,010 1,010 1,010 962 962 962 962 3,137 4,150 4,849 14,520 15,954 19,123 31,175 33,822 31,673 32,794 27,394 21,145 25,282 22,103 20,433 20,965 25,488 36,191 18,609 14,219 11,555 10,400 6,868 5,055 4,117 3,547 2,325 1,938 1,781 1,570 1,470 1,197 1,197 1,197 1,197 958 913 913 913 914 892 892 892 879 849 ,849 ,849 849 770 770 770 770 2,220 10,455 14,922 29,687 19,760 31,174 40,573 29,790 26,263 27,406 29,885 30,181 29,454 29,030 26,510 23,956 19,099 16,306 14,339 20,101 19,588 14,339 6,577 6,577 4,462 4,110 3,399 3,855 2,740 2,587 2,471 2,213 2,147 1,751 1,751 1,614 1,588 1,588 1,588 1,590 1,396 1,396 1,396 1,263 1,088 1,088 1,088 1,088 974 974 974 974 2,998 5,240 8,557 19,170 28,186 35,489 31,349 27,825 .19,052 21,995 20,209 22,658 24,581 19,970 19,771 19,663 18,031 19,953 17,237 18,813 18,292 20,076 9,403 8,067 5,479 6,784 4,885 4,021 3,443 3,831 3,221 3,868 3,300 2,460 1,998 TABLE B.3.1.7 (Page 2 of 5) YEAR 1958 2,228 1,,953 1,703 :1,611 1,331 ~,333 1,201 1,190 '1,111 1,138 1,110 1,042 1,042 1,071 1~198 1,299 11,575 3,551 1,050 9,849 18,752 20,003 2,116 27,116 23,381 21,304 20,248 20,248 20,248 19,851 36,827 26,,997 20,0,48 16,251 11,239 7,737 7,737 6,008 6,865 5,540 4,873 4,662 3,236 2,770 2,388 2,035 1,563 1,405 985 1,086 1,699 1,699 1959 1,403 1~351 12,288 1,262 1,275 I 1,226 1,096 997 865 865 865 865~,278 831 ,831 1,187 11,246 2,471 41,043 17,266 24,455 19,652 23,860 17,822 21,239 23,769 24,645 23,659 25,632 2P,,245 21,943 111,188 22,064 40,7i§6 39,763 24,835 13,349 10,026 10,810 10,007 6,913 3,803 ~,751 3,192 2,716 2,599 2,444 2,322 1,995 1,995 1,995 1,995 1960 1,857 1,835 1,637 '1,559 1,474 11,378 1,351 1,286 1,247 1,205 1,152 1,019 1,019 790 ,.'790 1,035 il,077 5,345 71,566 14,617 22,750 23,52{f.13,128 13,610 14,093 15,491 22,156 16,426 18,898 25,911 30,054 23,,404 20,681 19,984 19,226 16,823 26,586 18,844 16,128 11,591 8,418 5,986 ~,360 3,269 2;,981 2,749 2,439 2,508 2,534 2,583 2,271 2,271 1961 2,211 2~203 2,268 ~,294 1,988 11,604 1,578 1,516 1,556 1,352 1,505 1,891 1,891 1,996 1,996 2,201 ~,235 6,581 121,101 20,940 19,947 18,628 17,325 28,298 35,357 29,708 21,299 22,357 23,150 2~,984 24,592 I 21,399 30,310 15,053 1,162 12,778 12,169 14,00725;,061 9,801 4,324 4,324 {.,324 3,274 2!,458 2,458 2,458 2,321 1,960 1,960 1,960 1,960 1962 1,837 1,815 1,815 '1,815 1,634 1\,392 1,392 1,392 1,359 1,316 1,316 1,316 1,316 1,486 1~486 1,486 1,486 3,391 41,173 11,325 16,690 26,822 28,876 56,010 47,891 33,902 26,163 25,543 22,258 2~,163 24,614 211,799 21,799 21,799 22,290 22,008 13,899 11,257 12,951 8,737 6~653 5,797 5,238 3,522 21,607 2,607 2,607 2,410 1,872 1,872 1,872 1,872 1963 1,540 I 1,490 1,490 1,490 1,465 11,414 1,414 1,414 1,188 933 933 933 933 693 !693 693 ,693 2,460 3:,320 18,714 30,261 34,055 23,383 23,383 23,383 23,383 28,908 37,368 35,407 30,234 26,472 24:,729 21,455 22,691 19,122 14,318 12,804 10,239 10,381 8,327 7 ~011 5,636 {f,347 2,658 21,374 2,100 1,736 1,690 1,576 1,523 1,205 1,205 1964 1,047 1~020 954 926 934 :'942 922 866 802 707 679 606 606 674 674 730 i 740 590 1604 809 1,790 20,029 74,483 51,153 42,687 30,872, 24,270 25,009 23,601 Ip,194 18~729 17 1,736 14,300 15,247 12,880 10,489 8,548 8,595 8,413 7,044 7,883 5,159 {f,104 2,914 2:,687 2,659 2,963 1,906 1,271 1,133 1,030 1,030 1965 943 928 928 928 880 820 820 820 841 870 870 870 870 1,115 1,115 1,406 1,454 1,899 51,130 8,925 16,084 31,961 20,514 21,916 29,042 30,826 28,458 28;698 26,730 23,181 20,872 181,586 28,711 19,247 10,693 15,833 19,452 17,801 '23,533,'1,804 1,442 1,38813,634 7,579 3,550 2,937 2,500 21,042 1,721 1,656 1,554 1,503 1966 1,298 1,281 1,281 1,281 1,238 11,180 1,180 1,180 1,184 1,187 1,187 1,187 1,187 1,317 1,317 1,731 1,800 2,714 31,540 6,557 12,569 19,703 4,411 15,369 26,668 22,505 17,390 16,564 17 ,337 19,615 16,089 211,345 17,552 21,266 17 ,016 11,802 11,462 11,331 9,448 6,487 4,350 3,288 ~,227 1,568 11,446 1,446 1,446 1,422 1,361 1,361 1,361 1,361 ",---'"---~_.---'~-~.'--~'-------..- TA LE B.3.1.7 (Page 3 of 5) YE R 19 7 1362 1363 1363 1363 1325 1275 1275 1275 1188 1078 1078 1078 1078 963 963 989 1138 1624 4649 16169 22624 207061 24918 32648 27290 26620 20076 19995 27805 32408 25176 23505 51282 28599 19229 27035 15955 11597 10072 6430 5353 4187 3191 2670 2265 2145 2064 2026 1969 1969 1888 1875 19~8 1868 1869 1869 1842 1776 1779 1779 1779 1779 1779 1779 1779 1779 1750 1684 1764 1883 2087 2748 12217 31597 25614 24621 34274 34753 25300 27823 25325 24447 23623 20824 18816 15653 14145 12539 10453 10471 6687 5851 4751 4102 3160 2805 2386 1844 1404 1229 1017 896 849 801 761 191&9 731 711 663 663 663 660 673 607 707 735 755 796 822 878 1036 1348 1912 3208 5726 10892 19104 11446 12312 15692 17191 15610 13725 17372 17848 14921 12703 13327 6903 5598 5234 5924 5179 4441 4262 3613 3401 2979 2011 ·1615 1349 1065 943 883 840 799 793 793 1910 780 781 748 735 735 739 693 693 693 698 711 745 745 811 893 1021 1240 1833 4383 15525 14018 17146 15505 14957 14162 23845 23076 19362 20745 19835 24759 21655 16732 18910 13021 10994 8748 8910 5677 6293 5253 4279 3638 3621 3449 3138 2776 2486 2321 2166 1986 1779 19f1 1597 1429 1298 1140 1059 999 908 908 889 865 865 865 865 870 903 980 1096 1312 1700 2506 4424 7861 21610 44612 27094 37428 ~3189 23596 27197 17694 23161 43006 38447 23577 18657 21459 13693 10354 10269 7354 6590 5002 4124 3386 3056 2896 27-35 2602 2389 2389 2205 2205 19V2 2182 2001 2001 2001 2000 1885 1807 1807 1730 1718 1639 1639 1613 1483 1483 1422 1483 2946 17070 16823 234$2 39387 23332 41437 36288 24532 24274 24261 21623 17632 19568 20953 19219 19865 13290 12589 17212 12685 6546 4631 4286 5945 4490 2970 2408 2056 1894 1654 1511 1349 1321 1321 1162 1134 1134 1134 1142 1142 1142 1142 1059 945 945 945 945 949 959 959 1003 1329 2552 8737 12035 14974 19248 32089 34700 22798 20385 19488 14744 15905 17030 20275 16155 21018 22260 12074 8425 7115 6604 5275 4249 2930 2220 1835 1574 1450 1328 1218 1099 989 941 913 876 870 835 822 798 765 751 717 718 714 700 666 666 639 665 802 1279 2387 6225 11611 25921 29383 18190 15463 14457 15436 16001 19887 18241 17539 16605 17493 14966 11844 16072 15586 8738 8830 13278 5158 5126 2732 1822 1618 1622 1622 1622 1607 1479 1479 1479 1479 1473 1394 1394 1394 1393 1365 1365 1313 1274 1272 1272 1272 1272 1248 1260 1375 1630 2559 6184 13592 20770 27708 34462 25886 32526 29079 TABLE B.3.1.7 (Page 4 of 5) YEAR- 26,155!28,436 26,9571 24,660 22,789 1~,242 17,426 15,380 13,252 10,858 18,386 17,223 16,589 9,346:8,243 7,593 1 \4,478 3,159 2,241 1,707 1,356 1,167 1,063 1,023 983 930 1976 920 921 888 875 875 880 880 880 856 822 822 822 822I7567929831.1,643 4,311 12,374 11,892 12,436 14,396 26,245 28,274 19,909 19,234 18,276'18,235 17,3851 17,831 21,250 2~,600 20,486 15,736 11,079 7,164 5,867 5,902 7,183 4,442 3,626 3,458 1 \3,068 2,652 2,438 2,285 2,156 2,600 2,429 2,200 2,020 1,867 1977 1,772i 1,720 1,6291 '1,590 1,543 [,487 1,461 1,461 1,415 1,355 1,355 1,355 1,355 1,438 1,438 1,516 1 .1,692 1,712 2,974 10,765 16,516 25,448 33,191 43,962 36,028 32,148 20,430 22,716 24,005!19,973 21,372 2p,695 18,935 19,143 12,iOl '9,714 13,751 13,190 12,685 8,112 8,229 7,232!i 5,395 4,079 l3,474 3,131 2,904 2,692 2,523 2,412 2,340 2,163 1978 2,060 1,942 1,8431 il,770 1,663 1,548 1,503 1,503 1,460 1,478 1,478 1,478 1,498 1,441 1,441 1,441',1,522 3,504 12,344 16,853 11,404 12,150 14,917 20,720 17,729 22,092 21,324:19,810 20,028 1 19,646 18,935 lil,917 16,659 13,901 10,010 10,516 9,480 7,126 6,077 5,005 5,607 4,5281 i 3,398 3,267 e,830 2,121 i,862 1,792 1,748 1,591 1,433 1,381 1979 1,359 1,306 1,3061 '1,306 1,212 [,218 1,218 1,218 1,126 1,169 1,169 1,169 1,169 1,131 1,184 1,305!1,640 2,638 4,998 11,662 18,604 30,663 26,683 22,397 20,220 25,018 25,082'24,811 30,2051 ~0,868 24,867 2~,326 18,838 16,043 14,232 8,834 8,606 12,663 11,459 7,486 9,501 6,6731 4,930 4,588 ~,148 4,621 3,309 3,151 2,576 2,321 2,119 1,918 1980 1,801 1,722 1,628!\1,547 1,507 1,440 1,372 1,119 1,320 1,321 1,321 1,321 1,321 1,260 1,260 1,3241 :1,800 3,875 9,212 13,196 11,801 18,768 28,973 22,831 29,565 25,792 29,501 29,933 31,585 1 28,372 31,440 2~,402 20,230 18,346 13,413 9,786 10,465 17,592 13,134 9,434 8,409 6,9941 !5,465 4,389 13,929 2,932 2,985 2,99~2,216 1,710 1,608 1,546 1981 1,525 1,775 2,066 1 :2,232 2,262 2,240 1,868 1,484 1,391 1,391 1,484 1,510 1,529 1,449 1,510 1,608!i2,083 5,196 19,239 19,321 12,733 20,884 18,091 16,425 17 ,674 20,644 16,157 38,138 37,2831 ~3,258 36,067 3~,704 44,852 35,541 23,832 16,893 13,620 11,366 10,573 6,569 6,190 6,361 1 :7,376 4,141 B,513 3,436 2,889 2,534 2,328 2,193 2,115 2,115 1982 2,084 2,083 2,083!!2,083 2,106 2,III 1,542 1,119 982 1,001 1,001 1,060 1,363 1,286 1,286 1,420!'1,886 3,035 il,207 13,345 17,920 20,543 24,650 20,690 27,290 26,402 18,710 23,136 23,5211 26,386 22,303 15,386 13,388 11,684 13,035 12,548 15,713 24,712 15,566 9,491 7,464 6,077!13,562 2,760 e,590 2,458 2,297 2,235 2,142 2,142 2,142 2,274 1983 2,569 2,225 1,974 1 1 1 ,854 1,813 1,769 1,902 1,942 1,821 1,710 1,602 1,548 1,427 1,341 1,366 1,5961 '2,158 4,096 9,947 17,176 15,253 21,996 26,445 18,942 23,102 22,894 24,232 20,875 17 ,4231 18,801 19~944 '2p,388 23,520 20,778 25,284 17,691 19,046 9,644 12,669 10,643 8,842 7,49 51 :5,148 4,558 3,173 2,758 2,532 2,362 2,262 2,167 2,087 2,019 ., I I '---,"--~ ---'-_.-~.__.-'-_._~_.."~- 2,569 2,225 2,268 2,294 2,262 2,240 1,902 1,942 1,821 1,779 1,779 1,891 1,891 1,996 1,996 2,201 2,235 11,682 19,239 20,940 31,597 39,387 74,483 56,010 47,891 37,428 32,794 38,138 37,283 33,258 36,826 43,006 51,282 40,756 39,763 28,254 26,586 24,712 23,533 13,634 9,557 7,593 7,376 4,885 4,148 4,621 3,309 3,221 3,868 3,300 2,460 2,274 MIN ,731 ,711 ,663 ,663 ,663 ,66O ,639 ,586 ,662 ,658 ,617 ,606 ,606 ,515 ,515 ,693 ,693 ,59O ,604 ,809 1,790 7,861 12,312 13,610 13,168 15,436 13,725 16,426 14,744 14,921 12,703 13,327 6,903 5,598 5,234 5,924 5,179 4,441 4,262 3,613 3,401 2,732 1,822 1,390 1,308 1,065 ,943 ,883 ,840 ,799 ,793 ,761 MEAN 1,489 1,442 1,404 1,388 1,324 1,248 1,199 1,160 1,190 1,066 1,064 1,070 1,079 1,047 1,069 1,205 1,422 3,265 7,330 12,498 17,336 21,612 25,764 27,707 26,246 24,768 22,653 23,106 23,303 22,673 23,875 22,124 21,222 19,348 -17,375 14,496 13,016 11,929 11,304 7,506 6,284 4,957 3,983 3,082 2,631 2,355 2,169 2,030 1,822 1,736 1,644 1,602 1J~Flows are presented in standard weekly periods of seven days,beginning with week number one (Dec.31 - Jan.6)and continuing across at thirteen weeks per line.The 39th week is an eight day period (standard water week 52 [Sept.23 -Sept.30])and the flow for this period is the total eight day flow divided by seven as used in the reservoir operation program.This flow in week 39 is the average flow multiplied by 1.143. TABLE B.3.1.~:WEEKLY STREAMFLGW AT OOLD CREEK (CFS)ll (Page 1 of 5) YEAR-- 1950 1,014 979 986 i1,1100 1,100 971 689 629 710 711 666 720 801 774 783 849 11,1009 2,314 8,007 13,671 14,200 17,914 17,100 16,571 26,171 19,343 19,957 21,229 23,214 ~5 ,1243 25,100 23,129 21,157 17,443 13,171 9,263 10,500 7,100 7,186 5,257 4,686 4,091 1 2 ,j334 1,471 1,~86 1,300 1,229 1,171 1,100 1,100 1,100 1,100 1951 980 960 960 1960 900 820 820 820 786 740 740 740 740 774 997 1,529 'i 2,)65 7 6,157 17,~29 19,271 9,567 16,671 29,543 21,300 13,543 19,071 20,729 24,343 23,286 +1,1414 21,429 17 ,614 18,714 18,314 25,600 30,057 18,671 19,286 18,657 9,229 6,171·4,486 !3,1486 3,500 3,~04 2,369 2,343 2,186 1,900 1,900 1,900 1,900 1952 1,643 1,600 1,600 i1,[600 1,343 1,QOO 1,000 1,000 ,949 880 880 880 880 920 920 920 '920 1,191 1,514 2,071 4,486 21,929 24,814 35,143 38,114 33,729 27,629 19,629 25,086 27,i186 37,243 25,Q71 19,686 14,943 17,329 18,886 12,771 11 ,029'15,086 11,143 10,390 7,233 i5 1271 5,000 4,257 2,729 3,343 2,429 1,700 1,700 1,700 1,700 11 :1100 , 1953 1,186 '1,100 1,100 980 820 820 820 ,820 820 820 820 820 930 930 1,504 12 ,1 500 14,129 ~i:~~j 15,300 26,386 20.,743 35,114 27,114 22,071 25,829 20,229 18,271 19,871 ~O ,1657 25,643 17,514 18,029 21,500 18,786 17,114 14,271 12,426 8,119 6,733 4,940 13,937 3,401 2,271 2,100 1,957 1,786 1,500 1,500 1,500 1,500 1954 1,329 1,300 1,300 iI,pOO 1,171 1,pOO 1,000 1,000 ,906 780 780 780 780 870 870 1,496 i1,600 6,743 12,~86 19,900 22,814 21,571 25,457 24,457 23,456 28,514 24,486 19,529 19,000 JJ9 ,000 .31,143 24,QOO 24,000 24,000 23,000 1,586 14,000 13,057 9,581 6,500 :6 ,109 4,500 14,:500 3,686 I 2,829 2,500 2,414 2,200 2,157 1,900 1,9003,0,00 1955 1,986 :2,000 1,714 i,1,!600 1,514 1,lJIOO 1,400 1,400 1,271 1,100 1,100 1,100 1,100 1,200 1,200 1,200 !1,200 3,557 4,5~00 5,247 15,743 17,429 20,329 33,143 35,957 33,671 34,186 28,557 22,043 ~6,357 22,614 20,9100 21,443 26,071 37,243 19,671 15,029 12,214 10,993 7,236 5,327 4,339 !3,(737 2,486 I 1,929 1,700 1,586 1,300 1,300 1,300 1,3002,lPO 1956 1,026 980 980 .,980 976 9,70 970 970 957 940 940 940 940 950 950 950 950 2,514 11 ,400 16,271 32,371 21,686 33,457 43,543 31,971 28,186 ~1,229 I29,057 31,686 32,000 31,429 28,7i71 26,000 20,729 17,714 16,000 22,429 21,857 16,000 7,200 7,200 4,886 14 ,POO 3,757 3,2pO 3,071 2,900 2,757 2,400 2,329 1,900 1,900 1957 1,729 1,700 1,700 11 ,flOO 1,614 1,5QO 1,500 1,500 1,371 1,200 1,200 1,200 1,200 1,200 1,200 1,200 !1,200 3,414 5,7~7 9,400 21,057 30,914 37,443 33,086 29,357 20',100 23,214 21,329 23,914 ~5,943 20,957 20,9~3 20,829 19,100 21,143 19,814 29,643 20,071 20,029 10,333 8,864 7,230 17 ,~54 5,429 4,5~1 3,870 3,181 3,586 4,314 3,680 2,744 2,229 i.I '---------'__"I .-:...-.-...-'----~ L , TABL B.3.1.8 (Page 2 of 5) YEAR 1958 2,429 2,129 1,857 1,757 1,457 1,443 1,300 1,200 1,200 1,200 1,171 1,100 1,100 1,200 1,343 1,457 1,766 3,990 7,883 11 ,014 20,971 22,056 28,000 28,000 24,143 22,000 22,000 22,000 22,000 21,571 38,686 27,529 20,443 16,571 11,557 8,500 8,500 6,600 7,543 3,991 5,271 5,043 3,500 2,986 2,600 2,214 1,700 1,529 1,100 1,214 1,900 1,900 19591 1,557 1,500 1,429 1,400 1,400 1,400 1,343 1,200 1,106 980 980 980 980 1,000 1,000 1,429 1,500 2,857 4,543 19,400 27,486 22,329 26,029 19,443 23,171 25,929 26,400 25,343 27,457 21,686 23,886 18,629 23,914 44,171 43,171 28,700 14,829 11 ,137 12,007 10,714 7,400 4,071 5,086 3,486 3,000 2,871 2,700 2,557 2,200 2,200 2,200 2,200 19601 2,029 2,000 1,786 1,700 1,614 1,500 1,471 1,400 1,357 1,300 1,243 1,100 1,100 1,100 1,100 1,443 1,500 5,857 7,600 14,686 22,857 24,286 14,357 14,886 15,415 16,943 22,929 17 ,000 19,557 26,814 32,043 25,429 22,471 21,714 20 i 857 18,314 28,943 20,514 17 ,557 12,529 9,100 6,471 4,714 3,586 3,300 3,043 2,700 2,757 2,900 2,843 2,500 2,500 1961 1 2,414 2,400 2,471 2,500 2,200 1,800 1,771 1,700 1,614 1,500 1,571 2,100 2,100 2,500 2,500 2,657 2,800 7,229 12,714 22,000 20,957 19,814 18,971 30,986 38,714 32,529 23,000 24,143 25,000 25,900 25,643 26,000 22,200 21,071 15,657 12,429 14,100 13,429 15,457 10,429 4,600 4,600 4,600 3,514 2,700 2,700 2,700 2,529 2,100 2,100 2,100 2,100 1962 1 1,929 1,900 1,900 1,900 1,729 1,500 1,500 1,500 1,456 1,400 1,400 1,400 1,400 1,700 1,700 1,700 1,700 3,700 4,500 12,214 1,800 28,471'30,286 58,743 50,229 35,557 27,186 26,543 23,129 27,186 26,057 23,000 23,000 23,000 23,429 23,571 14,886 12,057 13 ,871 9,150 6,976 6,071 5,486 3,700 2,800 2,800 2,800 2,571 2,000 2,000 2,000 2,000 19631 1,657 1,600 1,600 1,600 1,557 1,500 1,500 1,500 1,286 1,000 1,000 1,000 1,000 830 ,830 ,830 ,830 2,666 3,400 19,171 31,000 35,686 26,000 26,000 26,000 26,000 31,143 40,257 38,143 32,571 27,800 25,143 21,814 23,071 19,543 15,143 13,543 10,829 10,979 8,897 7,491 6,129 5,643 2,886 2,600 2,300 2,900 1,843 1,700 1,643 1,300 1,300 19641 1,129 1,100 1,029 1,000 1,000 1,000 ,980 ,930 ,861 ,770 ,739 ,660 ,660 710 ,710 ,770 ,780 ,866 1,043 1,400 3,099 28,990 75,029 51,529 43,000 31,100 25,371 26,143 24,671 19,629 19,757 18,729 15,100 16,100 13,600 11,354 9,253 9,304 9,106 7,677 8,591 5,623 4,473 3,080 2,836 3,807 3,129 2,033 1,370 1,221 1,110 1,110 19651 981 ,960 ,960 ,960 ,917 ,860 ,860 ,860 ,877 ,900 ,900 ,900 ,900 1,180 1,180 1,489 1,540 2,011 5,386 9,371 16,886 33,643 21,971 23,471 22,429 33,014 30,357 30,614 28,514 24,729 22,229 19,671 30,386 20,371 11,343 15,849 20,700 18,943 25,043 15,086 8,387 3,929 3,250 2,764 2,264 2,000 1,907 1,829 1,714 1,557 1,590 1,530 19661 1,419 1,400 1,400 1,400 1,357 1,300 1,300 1,300 1,300 1,300 1,300 1,300 1,300 1,500 1,500 1,971 2,050 3,014 3,886 7,200 13 ,800 21,657 47,686 34,129 28,829 24,329 18,643 17 ,757 18,586 21,029 28,014 22,914 18,843 22,829 18,300 12,886 12,614 12,371 10,314 6,990 4,687 3,544 2,400 1,729 1,600 1,600 1,600 1,571 1,500 1,500 1,500 1,500 TABLE B.3.1.8 Page 3 of 5) YEAR :, 1967 1,500 1,500 1,500 ~,~OO 1,457 1,4(1)0 1,400 1 400 1,314 1,200 1,200 1,200 1,200 1,100 1:,100 1,129 ~,300 1,743 4,9 t 9 17,143 23 986 28,829 26,571 34,814 29,014 28,386 21,557 21'471 29,857 3~,~00 27,100 25,043 54,871 30 600 20,614 29,071 17,157 12,471 10 ,831 ", 6,851 5,70:3 4,460 ~,400 2,857 2,4i9 2,300 2,214 2,171 2,100 2,100 2,014 2,000 1968 2,000 2,000 2,000 l,971 1,900 1,9(1)0 1,900 1,900 1,900 1,900 1,900 1,900 1,900 1,871 1',800 1,886 ?,Q14 2,243 2,943 13 ,086 33.843 27,543 26,457 36,829 37,343 27,186 29,429 26,786 25,857 24-,~86 22,214 20,143 16,757 15,143 13,429 11 ,271 11 ,291 7,210 6,309 5,061 4,370 3,366 2,987 2,543 l,gzl 1,500 1,314 1,086 950 900 850 807 1969 771 750 700 I ~OO 700 700 714 :750 750 779 800 843 871 957 1:,129 1,471 ~,O86 3,400 6,013 11 ,434 20,1057 12,069 12,800 16,314 17,871 16,229 13,929 17,629 18,114 1~,1143 13,386 14,286 7,399 6,001 5,593 5,303 5,511 4,72,6 4,536 3,940 3,709 3,249 :2 1193 1,714 1,429 1,129 1,000 936 900 857 850 850 850 ":8001970850814,aOO 800 750 :750 750 750 764 800 800 850 1936 1,071 i,300 1,943 4,6]4 15,343 14,1757 18,129 16,971 19,671 15,500 26,100 25,029 21,000 22,500 2',~14 26,429 22,8~1 17,671 19 ;971 13,786 11,897 9,466 9,643 6,143 7,017 5,857 '4,771 4,0;57 4,000 3,8QO 3,457 3,057 2,743 2,571 2,400 2,200 1,971 1971 1,743 1 ~557 1,414 ~,243 1,157 1,100 1,000 1,r000 979 950 950 950 950 964 hOOO 1,086 1,2!l4 1,457 1,9QO 2,800 4,943 8,714 22,857 47,186 28,6571 39,586 24,900 I , 24,471 28,700 1~,q71 24,357 44,743 40,000 24,:529 19,471 22,857 14,586 11,029 10,939 7,744 6,939 5,267 4,3.43 3,600 3,2~7 3,086 2,914 2,771 2,600 2,600 2,400 2,400 1972 2,400 2,200 2,200 2,~oo 2,200 2,0~6 2,000 2,:000 1,914 1,886 1,800 1,800 1,771 1,700 1,too 1,629 ~,700 3,386 19,571 19,286 26,886 44',243 24,471 43,457 38,057 25,729 35,371 25,357 22,600 1~,429 20,243 21,7~9 19,929 20,1600 13,786 13,186 18,029 13,286 8,657 4,786 4,429 6,143 4 5157 3,114 2,5~3 2,171 2,000 1,743 1,600 1,429 1,400 1,400,, 1973 1,229 1,200 1,200 J!2'00 1,200 1,ZQO 1,200 1,200 1,114 1,000 1,000 1,000 1,000,, 1,000 HOOO 1,000 ]Oi57 1,400 2;6~6 9,200 12,'671 15,714 20,214 33,700 36,443 23,943I', 21,057 20,129 15,229 q ,41 29 17,545 21,029 15,757 21,1800 23,171 12,814 8,942 7,551 7,010 .5,636 4,539 3,130 2,3:71 1,914 1,643 1,514 1,:386 1,271 1,143 1,029 979 950 1974 907 900 864 I 8150 829 8do 786 750 750 750 736 700 700 700 729 879 JJ 400 2,571 6,5~6 12,286 27,'429 31,357 19,557 16,700 15,614 16,671i'! 16,943 21,057 19,314 18,5[71 17,714 18,6~6 15,986 12,1651 17,130 16,614 9,314 9,413 14,154 5,503 5,469 2,914 ~,943 1,700 1,70;0 1,700 1,700 1,686 1,600 1,600 1,600 1,600 1975 1,586 1,500 1,500 11,5PO 1,500 1,500 1,500 1,443 1,400 1,400 1,400 1,400 1,400 1,400 1 414 1,543 ~,8~9 2,843 6,8~7 15,071 23,029 30,500 36,400 27,343 34,357 30,714 27,500 29 900 28,343 25,,9!29 24,200 19,486 18,614 15,429 14,157 11 ,743 19,886 18,629 17,943 10,286 9 071 8,357 ~,9'29 3,429 2,457 1,871 1,486 1,271 1,143 1,100 1,057 1,000 ~ ,.;. '------' TABLE B.3.1.8 (Page 4 of 5) YEAR 1976 1,000 1,000 964 950 950 950 950 950 929 900 900 900 900 900 943 1,171 1,957 4,957 13 ,943 13,400 14,014 16,129 27,700 29,843 21,014 20,300 19,329 19,286 18,386 18,857 21,714 27,714 20,571 15,800 11,183 7,729 6,330 6,367 7,750 4,831 3,943 3,760 3,337 2,943 2,714 2,543 2,400 2,886 2,715 2,457 2,257 2,086 1977 I 1,957 1,900 1,800 1,757 1,700 1,629 1,600 1,600 1,557 1,500 1,500 1,500 1,500 1,600 1,600 1,686 1,771 1,971 3,457 12,514 19,200 29,200 24,956 46,300 37,943 33,857 21,714 24,143 25,514 21,229 22,286 21,329 19,514 19,729 12,514 10,363 14,671 14,071 13,534 8,829 8,957 7,871 5,871 4,486 3,829 2,450 3,200 2,964 2,757 2,636 2,557 2,364 1978 I 2,236 2,107 2,000 1,921 1,807 1,700 1,650 1,650 1,600 1,600 1,600 1,600 1,621 1,650 1,650 1,650 1,743 3,643 12,557 17,143 11,600 12,371 15,386 21,371 18,286 22,786 22,314 20,729 20,957 20,557 20,214 19,114 17 ,771 14,829 10,686 11,214 10,109 7,599 6,481 5,416 6,069 4,901 3,679 3,577 3,126 2,343 2,057 1,971 1,900 1,729 1,557 1,500 1979 I 1,457 1,400 1,400 1,400 1,300 1,300 1,300 1,300 1,200 1,200 1,200 1,200 1,200 1,200 1,257 1,386 1,743 2,743 5,143 12,000 19,143 31,671 27,486 23,071 20,829 25,771 26,371 26,086 31,757 32,457 26,514 24,800 20,029 17 ,057 15,171 9,447 9,203 13,543 12,254 7,890 10 ,014 7,034 5,197 4,871 4,424 4,929 3,529 3,357 2,743 2,471 2,257 2,043 1980 I 1,914 1,829 1,729 1,643 1,600 1,529 1,457 1,400 1,400 1,400 1,400 1,400 1,400 1,400 1,400 1,471 2,000 4,143 9,714 13,914 12,443 19,843 32,143 25,329 32,800 28,614 31,343 31,800 33,557 30,143 33,014 23,200 21,929 19,886 14,457 10,570 11,304 19,000 14,186 9,849 8,779 7,303 6,019 4,657 4,211 3,143 3,200 3,200 2,314 1,786 1,679 1,614 1981 I 1,571 1,829 2,129 2,300 2,329 2,414 2,014 1,600 1,500 1,500 1,600 1,629 1,650 1,700 1,771 1,886 2,443 5,623 20,400 20,486 13 ,500 21,943 18,629 15,914 18,200 21,257 17 ,829 42,086 41,143 36,700 38,600 31,657 46,729 37,029 24;971 17 ,986 14,500 12,100 11,256 7,641 7,200 7,399 8,581 4,512 3,943 3,857 3,243 2,828 2,529 2,385 2,300 2,300 1982 I 2,300 2,300 2,300 2,300 2,314 2,357 1,721 1,250 1,100 1,100 1,100 1,164 1,497 1,500 1,500 1,657 2,200 3,386 8,100 15,000 20,143 22,714 26,143 21,857 28,857 28,000 19,500 24,114 24,514 27,500 23,657 16,629 14,471 12,629 14,014 13,486 16,886 26,557 28,000 10,429 8,201 6,677 3,914 2,971 2,786 2,643 2,471 2,400 2,301 2,300 2,300 2,443 1983 I 2,771 2,400 2,129 2,000 1,957 1,900 2,043 2,086 1,957 1,814 1,700 1,643.1,514 1,500 1,529 1,786 2,414 4,586 11 ,086 19,143 17,000 24,143 27,343 19,586 23,886 23,671 25,371 21 ,857 18,243 19,686 21,014 26,586 24,629 21 ,757 26,529 18,957 11,729 10,334 13,574 11,283 9,373 7,945 5,457 4,843 3,386 2,943 2,700 2,414 2,386 2,286 2,200 2,129 TABLE B.3.1.8 (p age 5 0 f 5) YEAR MAX MIN MEAN 2,271 2,500 34,186 15,086 771 700 13,929 3,940 1,607 1,216 23,987 8,102 2 400 2 500 42 08'6 10 390 750 710 17 000 3 709 1 554 1 240 24 4911 6 782 2,471 2,757 41,143 8,357 700 770 15,229 2,914 1,412 1,408 24,708 5,348 2,500 I !t,~Oo 36,~OOI , ~,~81 ~OO 1180 1~,~43 1,9.43!j 1,lJj94 L~67 24,Q31 4,~03 2,329 14,129 38,686 5,429 700 866 13,386 1,471 1,427 3,654 25,294 3,332 I I 2,4l4 20,400 44,743 I . 4,529 ! 700 1,043 I 14,286 I 1,3~6 1,3~4 7,9]]4 23,320 2,861 I 2,043 22;000 54,871 4,929 686 1,400 7,399 1,129 1;300 13,466 22,387 2,562 2 086 33 843 44 171 3 529 629 3,1099 6,001 1,000 1 258 18 715 20 411 2 358 1,957 44,243 43,171 3,586 710 8,714 5,593 ,936 1,204 23,556 18,377 2,204 1,900 65,029 30,057 4,314 711 12,800 6,303 ,900 1,151 27,284 15,621 1,978 1,900 58,743 28,943 3,680 666 14,886 5,511 ,857 1,149 29,369 14,039 1,886 2,100 50,229 26,557 2,744 660 13 ,543 4,726 ,850 1,157 27,860 112,871 1,785 2,100 39,586 25,043 2,500 660 16,229 4,536 ,807 1,167 26,313 12,129 1,739 1.143. 1/ I Flows are presented in stand4rq weekly periods of seven days,beginning with week number one (Dec.31 - Jan.6)and coni:'inuing acros~a.t thirteen weeks Iper line.the 39 th week is an eight day period (standard water week 52;(Sept.23 -Sept.'30)and the flow for th is period is the total eight day flow divided by seven as used in the reservoir ioperation progra~.Th is flow in week 39 is the average flow mu1 tip1 ied by, I TABLE B.3.1.9:SUMMARY OF ESTIMATED STREAMFLOW (cfs)i I Devil Gold ~t,ation Denali Cantwell Watana Canyon CreekJ.!SunshineY Susitna Maclaren Chulitna Ta1keet na Skwentna -I ,t Max 2,165 5,472 6,632 7,518 8,212 20,837 58,640 734 8,062 4,891 7,254 Min 528 1,638 2,403 2,867 3,124 8,176 13,476 249 2,380 1,451 1,929 Mean 1,165 3,149 4,567 5,363 5,825 13,799 32,777 418 4,850 2,683 4,329 iv Max 878 2,487 3,525 3,955 4,192 8,795 31,590 370 3,213 1,721 4,195 Min 192 780 1,021 1,146 1,215 4,020 8,251 95 1,480 765 678 Mean 500 1,460 2,064 2,402 2,578 6,185 15,063 182 2,155 1,223 1,867 LJc Max 575 1,658 2,259 2,905 3,264 6,547 14,690 246 2,100 1,203 2,871 Min 146 543 709 810 866 2,675 5,753 49 1,000 556 624 I Mean 315 951 1,453 1,703 1,828 4,426 9,267 117 1,564 871 1,295 .,.In Max 651 1,694 1,858 2,212 2,452 5,216 10,120 162 1,681 940 2,829 Min 85 437 619 687 724 2,228 6,365 44 974 459 600 I Mean 248 850 1,125 1,429 1,524 3,674 8,112 99 1,330 693 1,068 Feb Max 422 1,200 1,610 1,858 2,028 4,664 9,413 140 1,414 777 1,821 Min 64 426 602 682 723 2,095 5,614 42 820 392 490 Mean 206 706 1,035 1,216 1,309 3,115 .-7,383 81 1,115 548 911 Mar Max 290 1,273 1,560 1,779 1,900 3,920 8,906 121 1,354 743 1,352 Min 42 408 575 644 713 1,972 5,271 36 770 285 522 Mean 192 659 936 1,085 1,173 2,786 6,412 74 1,017 485 826 Apr Max 415 1,702 1,965 2,405 2,650 5,228 13,029 145 1,883 1,075 2,138 Min 43 465 609 697 745 2,233 4,613 50 700 385 607 Mean 231 835 1,158 1,340 1,441 3,585 7,684 86 1,264 605 1,088 May Max 4,259 13,751 15,973 19,777 21,890 43,121 88,470 2,131 21,902 8,840 22,370 I )Min 629 1,915 2,857 3,428 3,745 10,799 28,713 208 2,355 2,140 1,635 ,J Mean 2,306 7,473.10,625 12,462 13,483 27,674 56,770 832 8,862 4,294 8,555 June Max 12,210 34,630 42,842 47,814 50,580 116,152 165,900 4,297 40,330 19,040 40,356 Min 4,647 9,909 13,233 14,710 15,500 40,702 73,838 1,751 15,297 5,207 10,650 Mean 7,532 17,567 22,980 26,043 27,795 63,268 112,256 2,888 22,173 11,085 18,462 July Max 12,110 22,790 28,767 32,388 34,400 85,600 181,400 4,649 35,570 17,079 28,620 Min 6,~56 12,220 14,843 15,651 16,100 45,226 92,511 2,441 20,781 7,080 11 ,670 Mean 9,688 16,873 20,747 23,075 24,390 64,143 126,590 3,241 26,875 10,748 16,997 A\Jg Max 12,010 22,760 30,542 35,256 37,870 84,940 159,600 4,122 33,670 16,770 20,590 [ Min 3,919 6,597 7,772 8,484 8,879 25,092 80,891 974 11 ,300 3,787 7,471 Mean 8,431 14,614 18,366 20,654 21,911 56,148 109,084 2,644 22,896 9,596 13,335 ,C"ep Max 6,955 12,910 17,206 19,799 21,240 54,110 107,700 2,439 22,260 10,610 13,371 ! \Min 1,194 3,376 4,260 4,796 5,093 14,320 37,592 470 6,704 2,070 3,783 !I' Mean 3,334 7,969 10,878 12,555 13,493 32,867 67,721 1,167 12,391 5,779 8,371 "nn Max 3,651 7,962 9,985 11,254 11,961 28,262 63,159 1,276 11,419 5,400 10,024 I I Min 2,127 4,159 4,912 5,352 5,596 14,431 38,030 693 6,110 2,249 4,939 'I ..J Mean 2,885 6,184 8,046 9,159 9,781 23,607 46,891 998 8,931 4,073 6,622 'i.l Data for Gold Creek based on 34 years of recorded data (1950-1983).Missi ng Dat a for all other locat ions !have been filled,in as described in Harza-Ebasco's report (HE 1984b). 2-1 SUllshine discharge for "IN 1980 ancl-9et Apr WY19Bl w~m~m Gold Creek,Talkeetna,and Chulitna discharges for the same period. TABLE B.3.1.10:INSTANTANEOUS PEAK FLOWS OF RECORD . Maclaren Denali Cantwell Go1d··Creek Flows Flows Flows Flows Date (cfs)Date (cfs)Date (cfs)Date (cfs) 8/11/71 9,260 8/10/71 38,200 8/10/71 55,0002 6/7/64 90,700 9/13/60 8,920 8/14-15/67 28,200 6/8/64 51,200 8/10/71 87,400 8/14/67 7,460 7/28/80 24,300 6/15/62 3 46,800 6/17/72 82,600 7/18/63 7,300 8/4/76 22,100 6/17/72 44,700 6/15/62 80,600 6/16/72 7,070 8/9/81 23,200 8/14/67 38,800 8/15/67 80,200 8/10/81 6,650 7/12/7~21,700 7/18/63 32,0004 7/12/81 64,900 6/14/62 6,540 7/27/68 19,000 8/14/81 30,900 6/6/66 63,600 8/5/61 6,540 8/25/59 62,300 Notes:1 Maximum daily flow from preliminary USGS data. 2 Estimated maximum daily·flow based on d~~~ar~~_r~cords at Denali and GoldC-iFeek-:-------------_.--------_.- 3 Approximate date. 4 Maximum.daily flow. Source:USGS -\ I j I ] .1 i t () , ----~-------~----- --_.---------~--"-".._-''-.._..,---,,,-,--_..---,--_.- TABLE B.3 .1.11 :ESTIMATED EVAPORATION LOSSES -WATANA AND DEVIL CANYON RESERVOIRS WATANA STAGE III D E V I L CAN YON Average Monthly Air Temper ture (DC) Pan Reservoir Pan .Reservoir Evaporation Evaporation Evaporation Evaporation Watana11 Devil Canyon2.1 Talkeetna.11Moth(inches)(inches)(inches) (inches) Jan 0.0 0.0 0.0 0.0 -2.5 -4.5 -13.0 Feb 0.0 0.0 0.0 0.0 -7.3 -5.0 -9.3 Mar 0.0 0.0 0.0 0.0 -1.8 -4.3 -6.7 Apr 0.0 0.0 0.0 0.0 -1.8 -2.5 0.7 May 3.6 2.5 3.9 2.7 8.7 6.1 7.0 Jun 3.4 2.4 3.8 2.7 10.0 9.2 12.6 Jul 3.3 2.3 3.7 2.6 13.7 11.9 14.4 Aug 2.5 1.8 2.-7 1.9 12.5 N/A 12.7 Sept 1.5 1.0 1.7 1.2 N/A 4.8 7.8 Oct 0.0 0.0 0.0 0.0 0.2 -1.8 0.2 Nov 0.0 0.0 0.0 0.0 -5.1 -7.2 -7.8 Dec 0.0 0.0 0.0 0.0 -17 .9 -21.1 -12.7------ Annu 1 14.3 10.0 15.8 ll.l II ased on data -April 1980-June 1981 2..1 ased on data -July 1980-June 1981 .11 ased on data -January 1941-December 1980 'J J TABLE B.3.1.12 :WATER APPROPRIATIONS WITHIN ONE MILE OF THE ·SUSITNA RIVER ADL SOURCE .-\LOCATIONl/NUMBER TYPE (DEPTH)AMOUNT DAYS OF USE CERTIFICATE '\ T19N R5W 45156 Single-family dwelling well (?)650 gpd 365 general crops same source 0.5 ac-ft/yr 91 } T25N R5W 43981 Single-family dwelling well (90 ft)500 gpd 365 T26N R5W 78895 Single-family dwelling well (20 ft)500 gpd 365 ,) 200540 Grade school well (27 ft)910 gpd 334 209233 Fire station well (34 ft)500 gpd 365 IT27NR5W200180Single-family dwelling unnamed stream 200 gpd 365 Lawn &garden irrigation same source 100 gpd 153 200515 Single-family dwelling unnamed lake .~5.00 gpd 365 : 1206633Single-family dwelling unnamed lake 75 gpd 365 I 206930 Single-family dwelling unnamed ..lake 250 gpd 365 206931 Single-family dwelling unnamed lake 250 gpd 365 PERMIT 206929 General crops unnamed creek 1 ac-ft/yr T30N R3W 206735 Single-family dwelling unnamed stream 250 gpd PENDING 209866 Single-family dw:elling Sherman Creek 75 gpd Lawn &garden •..irrigation same source 50 gpd l/All locations are referenced to·the Seward Meridian. 153 365 365 183 I J 1 L I j I .J J j TABLE B.3•2.1:RESERVOIR OPERATION LEVEL CONSTRAINTS Normal Normal Minimum Maximum Maximum Water Water Flood Surface Surface Surcharge Reservoir Elevation Elevation Elevation Watana Stage I 1,850 2,000 2,014 Devil Canyon Stage II 1,405 1,455 1,456 Watana Stage III 2,065 2,185 2,193 J J TABLE B.3.2.2:STANDARD WATER WEEKS FOR ANY WATER YEAR N FROM TO FROM TO 1 WEEK WEEK NUMBER day month year day month year NUMBER day month year day month year I 1 1 Oct n-l 7 Oct n-l 27 1 Apr n 7 Apr n 2 8 Oct n-l 14 Oct n-l 28 8 Apr n 14 Apr n 'j315Octn-l 21 Oct n-l 29 15 Apr n 21 Apr n 4 22 Oct n-l 28 Oct n-l 30 22 Apr n 28 Apr n 5 29 Oct n-l 4 Nov n-l 31 29 Apr n 5 May n )6 5 Nov n-l 11 Nov n-l 32 6 May n 12 May n 7 12 Nov n-l 18 Nov n-l 33 13 May n 19 May n 8 19 Nov n-l 25 Nov n-l 34 20 May n 26 May n ') 9 26 Nov n-l 2 Dec n-l 35 27 May n 2 Jun n ;~) 10 3 Dec n-l 9 Dec n-l 36 3 Jun n 9 Jun n 11 10 Dec n-l 16 Dec n-l 37 10 Jun n 16 Jun n 12 17 Dec n-l 23 Dec n-l 38 17 Jun n 23 Jun n ;,13 24 Dec n-l 30 Dec n-l 39 24 Jun n 30 Jun n 14 31 Dec n-l 6 Jan n 40 1 Jul n 7 Jul n 15 7 Jan n 13 Jan n 41 8 Jul n 14 Jul n ,I1614Jann20Jann4215Juln21Juln 17 21 Jan n 27 Jan n 43 22 Jul n 28 Jul n ) 18 28 Jan n 3 Feb n 44 29 Jul n 4 Aug n 19 4 Feb n 10 Feb n 45 5 Aug n 11 Aug'n '( 20 11 Feb n 17 Feb n 46 12 Aug n 18 Aug n ...U,..,18 Feb Il 24 F.~Q 19.Aug..n 25 Aug n 22 25 Feb n 3 Mar n 48 26 Aug n 1 Sep n 1234Marn10Marn492Sepn 8 Sep n 24 11 Mar n 17 Mar n 5.0 9 Sep n 15 Sep n 25 18 Mar'n 24 Mar n 51 16 Sep n 22 Sep n 12625Marn31Marn5223Sepn30Sepn ) r I ) ,J I .j 'J I \, TABLE B.3.2.3:SHCA LOAD FORECAST Net Generation at Plant 1/ I i Year 1985 1986 1987 1988 1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 Peak (MW) 702 713 724 735 746 757 769 782 795 808 821 826 831 836 840 845 858 871 885 898 912 937 962 988 1,015 1,042 1,064 1,087 1,110 1,133 1,157 1,182 1,207 1,232 1,258 1,285 1,312 1,340 1,369 1,398 1 427 Energy Requirement (GWh) 3,691 3,747 3,803 3,861 3,919 3,978 4,043 4,110 4,178 4,247 4,317 4,341 4,366 4,392 4,417 4,442 4,510 4,579 4,650 4,7Zl 4,793 4,923 5,056 5,193 5,333 5,478 5,594 5,712 5,833 5,957 6,083 6,212 6,343 6,478 6,615 6,755 6,898 7,044 7,193 ·7,345 7 501 1/Losses of 10 percent for transmission and distribution included.Net generation =Sa1es/(1-.10) TABLE B.3.2.4:DISTRIBUTION OF RAILBELT MONTHLY ENERGY REQUIREMENT SHCA FORECAST Energy Energy Percent Load Year Load Year Month of Annualll 2004 2025 (GWh)(GWh) Jan .107 505 803 Feb .089 420 667 Mar .089 420 667 Apr .079 373 593 May .072 340 540 Jun .066 312 495 Jul .068 321 510 Aug .070 330 525 Sep .073 345 548 Oct .089 420 667 Nov .095 449 713 Dec .103 486 773 Total s 100.0 4721 7501 1 ")" j J "~I I .J ,\ i,'~,'jI'~ \. !tj I, ':..} II Source:Based on Method of Indirect Averaging analysis of Railbelthourly load data for 19~82and L983 •. TABLE B.3.2.5:EXISTING AND PLANNED RAILBELT HYDROELECTRIC GENERATION Average Energy (GWh) Existing P1antsll Proposed Plant Cooper Sub-Brad1ey~./ Month Ek1utna Lake Total Lake Total Jan 14 4 18 41 59 Feb 12 3 15 39 54 Mar 12 3 15 31 46 Apr 10 3 13 26 39 May 12 3 15 20 35 Jun 12 3 15 13 28 Ju1 13 4 17 17 34 Aug 14 4 18 27 45 Sep 13 3 16 39 55 Oct 14 4 18 34 52 Nov 14 4 18 39 57 Dec 14 4 18 41 59 Total 154 42 196 367 563 Firm Energy (GWh) P1antsl1 Proposed Existing Plant Cooper Sub-Brad1ey11 Month Ek1utna Lake Total Lake Total Jan 13 4 17 41 58 Feb 12 3 15 39 54 Mar 9 3 12 31 43 I Apr 10 3 13 26 39 j May 11 3 14 20 34 Jun 8 2 10 13 23 J Ju1 9 3 12 13 25 Aug 8 2 10 13 23 Sep 9 -3 12 14 26 Oct 9 3 12 29 41 1 Nov 8 2 10 39 .49 Dec 12 3 15 41 56 Total 118 34 152 319 471 II Source:Acres 1982) !I 11 Scheduled on-line in 1990 TABL E B.3•3•1:WEEKLY MINIMUM MEAN FLOWS AT GOLD CREEK FOR FLOW CASE E-VI Minimum Minimum Water Gold Creek Water Gold Creek Week Flow Week Flow (cf s)(cfs) 14 5,000 40 6,000 15 5,000 41 6,000 16 5,000 42 6,000 17 5,000 43 6,400(2) 18 5,000 44 11 ,100(3) 19 5,000 45 12,000 20 5,000 46 12,000 21 5,000 47 12,000 22 5,000 48 12,000 23 5,000 49 12,000 24 5,000 50 11,900(4) 25 5,000 51 7,400(5) 26 5,000 52 6,000(6) 27 5,000 1 5,000 28 5,000 2 5,000 29 5,000 3 5,000 30 5,000 4 5,000 31 5,700(1)5 5,000 32 6,000 6 5,000 .6~OOO·7 5~-00O 34 6,000 8 5,000 35 6,000 9 5,000 36 6,000 .10 5,000 37 6,000,11 5,000 38 6,000 12 -5,000 39 6,000 13 5,000 (1)2 days at 5,000 cfs then 5 days at 6,000 cfs (2)5 days at 6,000,1 day at 7,000,1 day at 3,000 cfs (3)1 day each at 9,000,10,000 and 11,000 and 4 days at 12,000 cfs (4)6 days at 12,000 cfs,1 day at 11,000 cfs (5)1 day each at 10,000,9,000,8,000 and 7,000 cfs and days at 6~000 cfs (6)8da.ysat 6,000 cfs 1 ] J I i~1 ,! ~l I 1 I r J 3 1 I, f ] .'\ ..j,. TABLE B.3.3.2:EmOOMIC ANALYSIS OF ENVIRONMENTAL FLOW CASES SHeA FORECAST Cumulative Cumulative Present Cumulative Present Worth Of Present Worth orth of System Cos t sl!Differential Mitigation Costsl1 of Ne t Sy s tern Co s t s (1996-2054)(1996-2054)(1996-2054) Case I (million 1985 $)(million 1985 $)(million 1985 $) P-l I 4,811 25 4,836 A I 4,813 25 4,838 E-VI I 4,823 0 4,823 E-IV I 4,830 ·0 4,830 C I 5,120 11 5,131 E-V I 5,490 -4 5,486 E-I I 6,570 -7 6,563 Total Railbel t Ins taIled Capacity in Year 2025 (MW) 2,105 2,105 2,192 2,192 2,279 2,543 2,855 I_I cds ts incl ude production costs and cos ts for mi tigat ion measures for E-VI flow requirements. 2_1 Cdsts represent differential costs to mitigate beyond E-VI flow requirements. II Based on an estimated 14%overload capability over rated,assuming a 75% daily load factor. 11 Based on thermal capability of conductor bundle. Parameter Highest Line Loading as %of Rating Highest P.U.Voltage Lowest P.U.Voltage On 345 kV On 115 or 138 kV Max.Differential Phase Angle TABLE B.4.1.1:TRANSMISSION SYSTEM PERFORMANCE UNDER DOUBLE CONTINGENCY Acceptable System Configuration Performance Criteria 1999 2005 2025 11411 27'1:/58'1:/48'1:/ 1.10 1.05 1.05 1.05 0.90 1.006 0.988 0.998 0.90 0.986 0.963 0.964 55°16.5°30.5°30.2° J ~'l 1 1 TABLE B.4.2.1:GENERATING UNIT OPERATING CHARACTERISTICS Devil Watana Canyon Watana Stage I Stage II Stage III eservoir Elevation-ft Normal Maximum 2000 1455 2185 Average Operating 1955 1452 2145 December-January Operating 1915 1405 2110 Minimum Operating 1850 1405 2065 nit Characteristics Number of Units 4 4 4/21/ Net Head-ft Design 590 590 590/680 Maximum Operating 537 600 719/719 Average Operating 490 597 680/680 December-January Operating 450 545 645/645 Minimum Operating 384 545 600/600 enerator Unit Output-MW Maximum Operating Head 125 175 200/200 Average Operating llO 170 185/185 December-January Operating Head 90 150 170/170 Minimum Operating Head 65 150 150/150 ependable Plant Capability-MW (December-January Operating Head)360 600 1020 ominal Plant Capability-MW (Average Operating Head)440 680 1110 /Stage I Units/Stage III Units TABLE I B!4.2.2:ENERGY PRODUCTION AND DEPENDABLE CAPACITY Average Energy (GWh) Finn Energy (Glh) Dependable Capacity (MW) Watana I and Watana III and Watana Stage!I Devil Canyon II Devil Canyon II Not Limited 1999 2004 2005 2011 2012 2025 by Load 2,390 4,200 4,750 5,130 6,690 6,900 1,990 4,200 4,500 5,130 5,720 5,720 300 790 805 1,500 1,520 1,620 \--:--::~:....:..---:...:'------,,---' TABLE B.5.2.1:INSTALLED CAPACITY OF ANCHORAGE-roOK INLET AREA (DECEMBER 1984) Natural Gas Combustion Steam Hydro Diesel Turbine Turbine Total Util itiesl/ Alas ka Power Administration 30.0 0 0 0 30.0 Anchorage Municipal Ligh t and Power 0 0 329.9 0 329.9 Chugach Electric A$sociaton 17.4 0 490.4 0 507.8 Homer Electric Association 0 2.1 0 0 2.1 Matanuska Electric Association 0 0 0 0 0 Seward Electric Association 0 5.5 0 0 5.5 Total 47.4 7.6 820.3 0 875.3 Military Installations.f.! Elmendor f AFB 0 2.1 0 31..5 33.6 Fort Richardson 0 7.2 0 18.0 25.2 Subtotal 0 9.3 0 49.5 58.8 Industrial Installations].! Industry 0 9.6 16.0 0 25.6 TOTAL 47.4 26.5 836.3 49.5 959.7 1/Data based on Applicant's evaluation of information provided by the Rai1belt Utilities. 2:./Source:Departments of Anny and Air Force,January 1985. 1/Source:Battelle (1982)and Alaska Power Administration (1983);updated by Harza-Ebasco Susitna Joint Venture,1983.Figures are for 1981,latest year that data was available. TABLE B.S.2.2:INSTALLED CAPACITY OF THE FAIRBANKS.,.TANANA VALLEY AREA (DECEMBER 1984) Diesel Hydro Utilitiesl/ Faribanks Municipal Utility System 8.4 0 Golden Valley Electric Association 17.3 0 University of Ala.ska 0 0 Sub tot al 25 '.7 0 Military Installations1/ Oil Combustion Turbine 32.2 157.8 o 190.0 Coal Steam Turbine 28.6 25.0 13.0 66.6 Total 69.2 200.1 13.0 202.3 I ( I Eiel son AFB Fort Greeley Fort Wainwright o 5.5 o o o o o o o 15.0 o 22.0 15.0 5.5 22.0 Industry 2.8 0 0 0 2.8 TOTAL 34.0 0 190.0 103.6 327.6 ( I Data based on Applicant's evaluation_oi_infQrrnatio-.npx9JlLded_·~~~. ~~~----_._.~the -Ra il bef t-ir til ftT~-;'----- 1/Source:Departments of Army and Air Force,January 1985. 1/Source:Battelle (1982)and Alaska Power Administration (1983);updated by Harza-Ebasco Susitna Joint V¢J:lture,198J .Figure~a1;'e fo.l:.198.L,.lates t ..year_ that data was available. ) I TABLE B.5.2.3:EXISTING GENERATING PLANTS (Page 1 of 4) IN THE RAIL BELT REGION (DECEMBER 1984) Heat Rate Instal-Retire-Generating @ Gen. Prime Fuel lation ment Capacity Capacity Plant/Unit Mover Type Date Date @ 30°F (MW)(Btu/kWh) Alaska Power Administration Ek1ut nal/H 1955 2051 30.0 Anchorage Municipal Light-and Power Station 1f:11/(b) Unit 1f:1 SCCT NG/O 1962 1990 16.2 15,329 Uni t 1/:2 SCCT NG/O 1964 1990 16.2 15,329 Unit 1/:3 SCCT NG/O 1968 1991 19.9 14,089 Unit 1/:4 SCCT NG/O 1972 1992 33.8 13,901 S ta tion 1/:2 Unit 1/:561/CCCT NG/O 1979 1999 47.5 10,·570 Uni t 1f:7 61/CCCT NG/O 1979 1999 109.3 9,365 Uni t 1f:8 SCCT NG/O 1984 2009 87.0 12,000 Chugach Electric Association Beluga Unit 1f:!SCCT NG 1968 1994 16.1 16,100 )Unit 1/:2 SCCT NG 1968 1994 16.1 16,100 Unit 1/:3 SCCT NG 1972 1999 49.5 12,800 Unit 1/:4 SCCT NG 1976 1996 10.0 17,500 Unit 1f:5 SCCT NG 1975 1999 67.3 12,400 Unit 1f:68!±/CCCT NG 1976 2007 100.6 9,600 Unit 1f:78!±/CCCT NG 1976 2007 100.6 9,600 Cooper Lake2./ Unit 1f:!,2 H 1960 2051 17.4 International Uni t 1f:!SCCT NG 1965 1996 14.3 18,000 Unit 1f:2 SCCT NG 1968 1996 14.3 18,000 Uni t 1/:3 SCCT NG 1970 1996 19.9 14,500 Bernice Lake Uni t 1f:!SCCT NG 1963 1988 8.9 17,300 Unit 1f:2 SCCT NG 1971 1997 18.4 14,500 Unit 1/:3 SCCT NG 1978 2004 27.2 13,700 Unit 1f4 seCT NG 1981 2004 27.2 13,700 Seldovia Unit 1/:1 D 0 1952 1990 0.3 14,998· Unit 1/:2 D 0 1964 1994 0.6 12,006 Unit 1/:3 D 0 1970 2000 0.6 12,006 Unit 1/:4 D 0 1982 2012 0.6 12,006 Seward Electric System SES unit i/:1 D 0 1965 1990 1.5 15,000 Unit 1/:2 D 0 1965 1990 1.5 15,000 Unit 1/:3 D 0 1965 1995 2.5 15,000 Military Installations -Anchorage Area iJ 9,500 9,500 11,210 10,500 20,000 10;500 12,000 Heat Rate @ Gen. Capacity (Btu/kWh) 2.6 7.2 18.0 31.5 60.9 60.9 Generating Capacity @ 30°F (MW) 1997 2006 2007 Retire- ment Date 1967 1976 1977 1952 1952 Instal- lation Date Golden Valley Electric Association Homer Electric Association ~(}-~--T95Z NG 1952 Fuel Type o NG SCCT 0 seCT 0 D~ ST D 0 Prime Mover (Page 2 of 4) North Pole Uni t 1/:1 Unit 1/:2 Fort Richardson Total Diesel D Total Steam ST Elmendorf AFB Tota~I Diesel Total ST Healy Diesel Plant/Unit .TABLE B.5.2.3 TABLE B.S.2.3 (Page 4 of 4) Legend H D SCCT ST CCCT NG o Notes Hydro Diesel Simple cycle combustion turbine Steam turbine Combined cycle combustion turbine Natural gas Distillate.fuel oil I 11 Average annual energy production for Eklutna is lS4 GWh. 11 All AMLP SCCTs are equipped to burn natural gas or oil.!n normal operation they are supplied with natural gas.All units have reserve oil storage for operation in the event gas is not available. 11 uni ts :I/:S,6,and 7 are designed to operate as a combined-cycle plant. When simulat.e.d.Jn.t:Jti;;_m()cl~,t'hfayare mod 131edas two separate units with the characteristics shown.Thus,UnitsffiS and 7 are retired from "gas turbine operation"and added to "combined-cycle operation". !I Beluga Units #6,7,and 8 operate as a combined-cycle plant.When simulated in this mode,they are modeled as two separate units with the characteristics shown.Thus,Units :I/:6 and 7 are retired from "gas ~__t.ur_b_iJJ.g Qper.!!~i.o!!:".a.ll<3.added to "combined-cycle operation".-.,.....---_._..•_..,...__..._~-_..__...--_.._--_._._-_.._-~_.._-_.._..._.__.__..-_._~~_.._-_._-_......•'._--_...................................•._---- 11 Average annual energy production for Cooper Lake is 42 GWh. .i , TABL E B.5•2 .4:MONTHLY DI STRIBUTION (Page 1 of·2) OF PEAK POWER DEMAND Anchorage -Cook Inlet Area Average Average 1976-1982 1982 1983 1982-1983 (%)(%)(%)(%) January 88.5 100.0 100.0 100.0 February 87.4 92.5 88.0 90.2 March 78.4 82.1 80.5 81.3 April 69.4 76.5 72 .8 74.6 May 60.9 63.5 65.3 64.4 June 58.5 60.5 62.5 61.5 July 58.5 61.4 62.1 61.8 August 59.2 62.9 64.4 63.6 September 66.8 72.9 72 .6 72.8 October 80.1 90.6 81.0 85.8 November 88.0 95.8 84.7 90.2 December 99.2 93.7 93.6 93.6 Fairbanks -Tanana Valley Area Average Average 1976-1982 1982 1983 1982-1983 (%)(%)(%)(%) January 92.7 100.0 100.0 100.0 February 91.8 97.2 86.6 91.9 March 79.1 84.5 79.7 85.6 April 68.0 76.3 67.9 72 .1 )j May 60.2 69.4 67.1 68.2 June 56.9 68.4 62.9 65~6 July 57.1 64.6 63.4 64.0 August 58.6 66.0 67.6 66.8 September 64.1 69.5 71.3 70.4 October 75.4 84.6 79.8 82.2 November 84.2 99.4 82.6 91.0 December 95.0 -94.9 97.2 96.0 Total Rai 1 bel t Area Average Average 1976-1982 1982 1983 1982-1983 (%)(%)(%)(%) January 89.8 100.0 100.0 100.0 February 87.7 92.8 87.6 90.2 March 78.9 83.0 80.6 81.8 April 69.2 77.3 72 .2 74.8 May 60.9 65.1 65.1 65.1 June 58.3 61.2 62.1 61.6 July 57.9 62.4 62.1 62.2 August 59.8 63.0 64.4 63.7 September 66.4 72.7 72.0 72.4 October 79.5 89.8 81.0 85.4 November 87.7 96.3 84.3 90.3 December 98.9 94.6 93.5 94.0 TABLE B.5.2.4 (Page 2 of 2) Source:Data for 1976~1982 are taken from Alaska Electric Power Statistics 1960-1983,Alaska Power Administration (1984).Data for 1982 and 1983 are based on Applicant's evaluation of hourly load data provided by the Railbelt Utilities. (%)(%)(%) Anchorage -Cook Inlet Area Average 1982 1983 1982-1983 1 1 I J 1 l ! \ i I .1 1 J ( J ( 1 10.8 9.0 9.0 7.6 7.2 6.6 6.8 7.0 7.4 8.6 9.2 10.4 10.6 8.8 8.9 7.8 7.2 6.6 6.8 7.0 7.4 8.8 9.4 10.3 10.6 8.9 8.9 7.8 7.2 6.6 6.8 7.0 7.4 8.8 9.4 10.3 Average 1982-1983 10.7 8.8 9.0 7.5 7.2 6.7 6.8 7.2 7 ~7 8.5 9.1 10.6 10.4 8.7 8.9 7.8 7.3 6.7 6.9 7.2 7.6 8.7 9.3 10.4 (%)(%) Tanana Valley Area Average 1983 1982-1983 11.0 9.2 8.9 7.8 7.3 6.6 6.8 6.9 7.2 8.8 9.4 10.2 10.7 9.0 8.9 7.9 7.1 6.5 6.8 6.9 7.2 9.0 9.6 10.2 t%)nuuu ..u.....(%-)·u 10.7 10.5 9.0 8.8 8.9 8.9 7.9 7.8 7.2 7.2 6.5 6.7 6.8 6.9 6.9 7.2 7.2 7.6 9.0 8.7 9.6 9.2 10.2 10.4 1982 1983 Total Railbelt Area (%)(%) 10.8 9.7 9.2 7.7 6.9 6.3 6.6 7.1 8.5 9.4 11.3 10.2 9.1 9.0 7.8 7.1 6.5 6.7 6.8 7.2 8.7 9.7 11.2 t%} (%) 10.0 8.9 8.9 7.8 7.2 6.6 6.7 6.9 7.2 8.7 9.8 11.2 Fairbanks - Average 1976-1982 1982 Average 1976-1982 Average 1976-1982 January February March April May June January February March April May June July August September October November December January February March April May June July August September October November December August .September October November December TABLE B.5.2.5:PROJECTED MONTHLY DISTRIBUTION OF PEAK AND ENERGY DEMAND PERCENTAGE OF ANNUAL DEMANDll Total Railbelt Area Peak Energy (%)(%) January February March April May June July August September October November December 100.0 88.5 81.8 74.7 65.1 61.6 62.2 63.6 72 .3 85.4 91.1 94.9 10.7 8.9 8.9 7.9 7.2 6.6 6.8 7.0 7.3 8.9 9.5 10.3 II Source:Based on Applicant's Method of Indirect Averaging analysis of Railbelt hourly load data for·J:982 and 1983 provided by the Railbelt Utilities. TABLE B.S.2 .6:TYPICAL 24-HOUR LOAD DURATION RELATIONS TYP I CAL WEEKD AY TYPICAL WEEKEND DAY RANK APRIL AUGUST DECEMBER APRIL AUGUST DE CEMBER 1 1.000 1.000 1.000 .945 .967 .943 2 .922 .957 .928 .916 .934 .925 3 .899 .947 .898 .899 .931 .914 4 .896 .938 .890 '.877 .908 .912 5 .896 .933 .883 .864 .899 .899 6 .880 .916 .870 .858 .884 .889 7 .869 .912 .860 .857 .858 .884 8 .866 .910 .852 .856 .851 .857 9 .839 .902 .850 .853 .835 .856 10 .829 .871 .843 .841 .832 .846 11 .818 .867 .838 .833 .824 .835 12 .809 .841 .813 .822 .822 .831 13 '.805 .823 .805 .807 .805 .826 14 .796 .810 .793 .803 .798 .802 15 .794 .767 .772 .801 .785 .783 16 .792 .744 .757 .747 .737 .730 17 .717 .723 .704 •735 .715 .721 18 .694 .709 .674-.697 .649 .714 19 .649 .613 .655 .657 --;-626 .674 20 .632 .609 .611 .638 .626 .663 2L -.627-.584 ..-.610 ---.630.-.585-.---.661 22 .613 .579 .610 .621 .584 .627 23 .606·.577 .566 .612 .582 '.602 24 .601 .575 .548 .586 .565 .571 Source:Based on Applicant's Method of Indirect Averaging analysis of Rai 1be1 t hourly load dat.!l.~or 1 ?~2 and 1983pl:'()'V'ided1:ly.tl:1~Ra~!.~_~l~.__fiEiIitTes:--- 1 I I ( I ! \ 1 '\ 1 I I J l I I 1 J ) (- TABLE B.S.2.7:LOAD DIVERSITY IN THE RAILBELT Railbelt Loads (MW)-January 6,1982 Non- Coincident UTILITY 2PM 3PM 4PM 5PM 6PM 7PM 8PM Peak CEA 301.4 309.6 327.8 337.7 352.2 346.2 341.1 352.2 AMLP 109.0 107.0 117.0 114.5 116.0 112.0 107.0 117.0 GVEA 59.8 61.3 61.3 67.6 63.7 65.8 65.7 67.6 FMUS 26.0 26.2 26.1 25.6 24.0 23.5 22.5 26.2 TOTAL 496.2 506.1 532.2 545.4 555.9 547.5 536.3 563.0 Div.ersity =Coincident Peak =555.9 =.987 Non-coincident Peak 563.0 Rail belt Loads (MW)-January 10,1983 Non- Coinciclent UTILITY 2PM 3PM 4PM 5PM 6PM 7PM 8PM Peak CEA 335.2 331.7 354.8 370.0 372.3 370.1 360.5 372.3 \I AMLP 117.0 117.0 121.0 119.0 115.0 114.0 112.0 121.0 LJ GVEA 65.3 67.9 72.2 71.8 70.7 70.2 70.1 72.2 FMUS 27.7 28.0 28.2 26.9 26.0 25.0 24.5 26.9 TOTAL 545.2 544.6 576.2 587.7 584.0 579.3 567.1 592.4 Diversity =Coincident Peak =587.7 =.992 Non-coincident Peak 592.4 Source:Applicants evaluation of 1982 and 1983 hourly load data provided by Railbelt Utilities. TA8LE 8.5.2.8:RESIDENTIAL AND,COMMERCIAL ELECTRIC RATES.l/ ANCHORAGE-COOK INLET AREA JUNE 1985 utility Energy Used Residential Rates (monthly ) (Page 1 of 2) Electric Rate Rate With Cost of Power Fixed Rate Adjustment .1 Anchorage Municipal Light &Power Chugach Electric Association,Inc. Commercial Rates (monthly ) Customer Charge $4.50 All kWh 5.15 cents/kWh 5.99 cents/kWh Customer Charge $5.49 First 1500 kWh 6.00 cents/kWh 6.44 cents/kWh Over 1500 kWh 4.50 cents/kWh 4.94 cents/kWh Anchorage Municipal Light &Power Small General Service 25 kW or less Large General Service Over 25 kW Customer Charge All kWh Customer Charge Demand Charge All kWh $8.24 6.24 cents/kWh $65.00 $7.22/kW 2.90 cents/kWh 7.08 cents/kWh 8.06 /kW 3.74 cents/kWh .\ Exper.Time of Day Chugach Electric Association,Inc. Small General Service 10 kW or Less Customer Charge $18.00 7AM to 7PM 5.86 cents/kWh 6.70 cents/kWh c~7P-M~to.JPM.~~.C .•C To Amt.used 7PM to 7PM 2.41 cents/kWh 3.25 cents/kWh Excess of Amt. 7PM to 7PM 1.64 cents/kWh 2.48 cents/kWh Customer Charge $10.07 All kWh 5.69 cents/kWh 6.13 cents/kWh j ..···-·..--··-Over·-lO-kW-·..·-·..----..Customer-Charge....$-·30-;-51-cents..·....··_;;-"..·····..··-·.._-·· Demand Charge $7.93/kW All 3.32 cents/kWh 3.76 cents/kWh Sale for Resale Customer Charge All kWh Demand Charge MEA HEA SES $132.86 1.06 cents/kWh $14.73 /kW $14.23 /kW $12.10 /kW -1.41 cents/kWh l/Source:Alaska Public Utility Commission,Rates for Regulated Utilities as of June 14,1985. TABLE B.5.2.8 (Page 2 of 2) Electric Rate utility Residential Rates (monthly ) Energy Used Rate With Cost of Power Fixed Rate Adjustment Homer Electric Assn., Inc. Matanuska Electric Assn.,Inc. Seward Electric21 Systan Commercial Rates (monthly ) Homer Electric Assn.,Inc. Customer Charge First 1000 kWh Over 1000 kWh Facility Charge First 1300 kWh Over 1300 kWh Customer Charge All kWh $14.74 6.44 cents/kWh 5.21 cents/kWh $10.00 7.51 cents/kWh 5.81 cents/kWh $20.08/22.28 8.08 cents/kWh 7.57 cents/kWh 6.34 cents/kWh 8.52 cents/kWh Non-Demand Metered Demand Metered Interruptible Matanuska Electric Assn.,Inc. Seward Electric Systan Small General Service 50 kW or Less Large General Service Over 50 kW Customer Charge $29.48 All kWh 6.44 cents/kWh 7.57 cents/kWh Customer Charge $176.90 Danand Charge $4.30 /kW(over 25 kW) All kWh 5.02 cents/kWh 6.15 cents/kWh Customer Charge $176.90 Danand Charge 3.07 /kW(over 25 kW)$ All kWh 5.02 cents/kWh 6.15 cents/kWh Facility Charge $25.00 Demand Charge $3.61 /kW All kWh 4.48 cents/kWh Customer Charge $36.25/45.49 All kWh 9.80 cents/kWh 10.24 cents/kWh Customer Charge $36.25 cents/45.49 Demand Charge $28.31 /kW All kWh 2.59 cents/kWh 3.03 cents/kWh 1/Source:Alaska Public Utility Commission,Rates for Regulated Utilities as of June 14,1985. 11 Source:City of Seward Resolution 85-55,May 15,1985. TABLE B.5.2.9:RESIDENTIAL AND COMMERCIAL ELECTRIC RATES1/ FAIRBANKS-TANANA VALLEY AREA JUNE 1985 Utility Residential Rates Fairbanks Municipal Utilities System Energy Used Customer Charge 0-100 kWh 100-500 kWh Over 500 kWh Electric Rate Rate With Cost of Power Fixed Rate Adjustment $8.00 6.00 cents/kWh 8.00 cents/kWh 7.00 cents/kWh ,J Golden Valley Electric Assn.Cus tomer Cha rge First 500 kWh Over 500 kWh $10 .00 11.25 cents/kWh 9.50 cents/kWh $10.00 J 12.11 cents/kWh ~\ 10.36 cents/kWh Alaska Public Utility Commission,Rates for Regulated Utilities as of June 14,1985. Commercial Rates Golden Valley Electric Assn. cents/kWh cents/kWh cents/kWh cents/kWh \ 1 '\ j 15.86 cents/kWh '! 11.96 cents/kWh 10.36 cents/kWh I I l j 12.22 10.76 10.20 8.44 cents/kWh cents/kWh cents/kWh $15.00 $13.00/kW 10.00 cents/kWh 9.00 cents/kwh 6.00 cents/kwh $20.00 15.00 11.10 9.50 .····-··$4-0~-OO $--6--;-25-t-kW .-------.-..-... 11.36 cents/kWh 9.90 cents/kWh 9.34 cents/kWh 7.58 cents/kWh Customer Charge 0-4500 kWh 4500-5000 kWh Over 5000 kWh Customer Charge Demand Charge (Over 30kW) First 500 kWh 500-1500 kWh Over 15,000 kWh -CUeft:omer "Cnarge- .·Deman-d--Char·ge--· 0-4500 kWh 4500-10000 kWh 10000-15000 kWh Over-15000 kWh Source: General Service 50 kW or Less Fairbanks Municipal Utilities System 1/ ·-··GeneraTServi ce- .-------···-Over-5-0--kW----·-- \ ·l j TA BLE B•5•2•1°:ANCHORAGE MUNICI PAL LIGHT AND POWER CUMULATI VE ENERGY CONSERVATION PROJECTIONS Energy Conservation in MWh/yr Program 1981 1982 1983 1984 1985 1986 1987 Weatherization 586 762 938 1,114 1,290 1,466 1,641 State Programs 879 1,759 2,199 2,683 3,078 3,518 3,737 Water Flow 200 464 464 464 464 464 464 Restrictions Water Heat 3,922 3,922 3,922 3,922 3,922 3,922 3,922 Injection Hot Water NA NA 249 249 249 249 249 Heater Wrap Street Light °555 1,859 3,307 4,788 6,306 7,861 Conversion Transmission ° ° 4,119 8,732 9,256 9,811 10,399 Conversion Boiler Pump 7,148 7,148 7,148 7,148 7,148 7,148 7,148 Conversion TOTAL 12,735 14,609 20,896 27,619 30,195 32,614 35,421 Increase NA 14.7 43.0 32.2 9.3 9.8 8.6 From Previous Year % Source:AMLP,1983 !, i i l i T~B:ciE B.S.2.11 :HISTQRICAL ECONOMIC AND ELECTRIC POWER DATA YEAR ITEM Unit!1960 1965 1970 1975 1980 1982 1984 i I State oil and Gas ($million) Revenues to Genera 1 Fund 4.2 16.4 938.6 88.3 2,261.0 3,580.2 2,866.1 State General Fund Expenditures n.a~157.7 249.6 661.4 1,375.7 3,848.0 3,346.0i State Population 226,000 265,000 305,000 390,000 402,000 437,000 523,000 S tate Employment 94,OqO 110,000 133,000 198,000 211 ,000 232,000 264,000 Railbelt Employment I n.a.74,000 89,000 130,000 132,000 154,000 n.a., Railbelt Population!140,000 n.a.200,000 n.a.276,000 307,000 371 ,000 Railbelt Households 37,OqO n.a.54,000 n.a.94,000 107,000 n.a. Railbelt Electric Energy Generation GNh Anchorage 1/n.a 367 700 1,353 2,105 2,446 2,667 Fairbanks 1../n.a 120 222 452 443 491 541 Total n.a 487 922 1,805 2,548 2,937 3,208 '---'---'---~-----!J LJ!L.. \-.-_. TABLE B.D.2.11 (Page 2 of 2) YEAR ITEM Unit 1960 1965 1970 1975 1980 1982 1984 It Peak 1/ nd MW It Generation city MW n.a. n.a. 107 n.a. 210 n.a. 420 n.a. 577 1,143 598 1,272 609 1,287 1/AML&r'CEA,Alaska Power AdministrationU~~~M 1/Alas a Electric Power Statistics 1960-1983,USDOE APAD.1984 values taken from utility annual reports. Sources MAP Model Data Base;Federal Energy Regulatory Commission,Power System Statement;Alaska Power Administration,Unpublished Printouts,1983. 11 Applicant's evaluation of 1983 Railbe1t utility hourly load data. 11 Includes total net generation byCEA,AMLPand APAD and sales to other utilities.(This equals total Rai1be1t area except MEA purchase from APAD - 5 MW by contract).Source:Alaska Power Administration,unpublished printouts, 1983. 489 19831/ 472 472 489 440 430 392 394 365 356 ...304 319 291 306 291 304 299--315- -34-g-·~35-5-. 429 396 445 414 451 458 1982 202 265 266 188 220 222 187 216 225 170 192 200 154 177 184 148 159 171 156 167 176 157 169 182 164 175 193 197 ·221 221 218 234 236 234 250 265 445 352 377 325 307 272 273 280 276· :310· 350 401 445 1981 2,175 2,445 2,541 444 221 182 186 157 146 137 141 144 152 177 202 259 399 337 322 267 248 234 224 ··241 259 311 350 444 2,104 19801979 209 210 185 162 146 132 136 138 142 168 179 238 395 2,045 358 395 340 268 233 231 217 .-220 245 287 316 391 1978 197 168 173 150 141 130 132 132 139 169 191 209 383 341 329 297 270 240 229 227 -237·- --25-3· 312 353 383 NET ENERGY (GWh) 1,931 375 288 270 283 262 225 209 203 216···· 253- 293 344 375 163 144 165 143 131 118 118 123 128 159 194 217 1977 1,803 1976 TABLE BO.5.2.12:MONTHLY LOAD DATA FROM ELECfRIC UTILITIES OF '!HE ANCHORAGE-mOK INLET AREA 1976-198311 311 293 284 254 220 199 186 194 .198·· 21-g- 278 276 311 January 161 Februa ry 151 March 147 April 127 May 117 June 103 July 108 August III September 121 October 145 November 154 December 172 ANNUAL ANNUAL 1,617 January February March April May June July aug-ust ---S·eptember October November December TABLE B.5•2•13 :MONTHLY LOAD DATA FOR THE FAIRBANKS-T-!\NANA VALLEY AREA 1976-198311 1976 1977 1978 1979 1980 1981 1982 198311 NET ENERGY (GWh) January 56 48 52 49 50 42 54 55 February 53 41 45 51 38 41 45 46 March 44 47 45 42 38 38 43 47 April 34 38 36 35 33 35 39 39 May 30 32 32 30 31 32 35 27 June 27 29 30 28 28 30 32 34 July 28 29 30 30 30 30 34 35 August 29 31 31 29 30 30 34 37 September 31 31 33 32 32 34 36 40 October 40 41 40 36 36 39 43 44 November 43 54 44 37 41 42 46 47 December 53 61 48 48 56 49 50 55 ANNUAL 468 482 466 447 443 442 491 516 PEAK DEMAND (MW) January.101 88 96 89 95 80 94 100 February 100 87 95 101 75 88 92 87 II March 82 86 82 81 70 68 82 80 April 65 73 71 66 60 65 73 68 May 55 60 58 56 56 65 67 67 June 50 56 58 54 54 60 63 63 July 54 54 55 56 56 59 61 64 August 53 56 55 57 59 61 71 68 September 60 65 63 60 61 66 70 72 October 82 79 72 67 71 72 82 80 November 84 102 86 72 76 78 89 83 December 97 118 84 88 95 93 89 98 ANNUAL 101 118 96 101 95 93 94 100 11 Data for FMUS and GVEA including purchases.Source:Alaska Power Administration,unpublished printout,1983. 11 Applicant's evaluation of 1983 Railbelt utility hourly load da ta. [ TA~LE B.5.2.14: I NET G.ENERATION BY RAILBELT UfILITIES 1976-11984 (GWh )! Utility 197611 Anchorage Municipal 444.9 L igh t &Power Chugach Electric Assn.1,054.5 Alaska Power Administration 118.0 Anchorage Cook Inlet Subtotal 1,617.4 Fairbanks Municipal 123.3 Utility System Golden Valley Electric 344.7 As socia tion Fairbanks Area Sub-total 468.0 Rai1be1t Total 2l085.4 1977fJ/I 420.3, 1,179.7! 203 .~ 1,803.~ 128.~ 353.5 481.~ 2,285.3 [ 197811 443.1 1,308.6 180.1 1,931.8 124.7 341.5 466.2 2,398.0 11 97911 '473.1 1 1,:401.0 171 .1 2,[045.2 '124.7 2.9 447.6 2,:492.8 [ 198011 486.6 1,434.1 184.3 2,105.0 125.6 317.7 443.3 2,548.3 198111 485.3 1,467.2 223.2 2,175.7 126.1 316.9 443.0 2,618.7 198211 579.5 1,718.4 147.9 2,445.8 140.7 350.3 491.1 2,936.9 1983-6.1 1984 598.7 654.0 1,775.3 1873.7 149.5 139.2 2,523.5 2666.9 139.1 140.2 364.4 401.4 503.5 541.4 3,027.0 3208.3 Note:Subtotals and total shown m~y ;differ from co1uII\n totals due t.o rounding. 11 II Source:Alaska Power Alaska Electric Power ! Admin stration,Unpublis~ed Printouts,1983. ! Stati ti'cs 1960-1983,A11Ska Power Administration,Sept.1984. .. ~-~---- TABLE B.5.3.1:COMPARISON OF RECENT FY 1985 PETROLEUM PRODUCTION REVENUE FORECASTS FROM PETREV (IN MILLIONS OF DOLLARS) TABLE B.5.3.2:MAP MODEL VALIDATION SIMULATION OF HISTORICAL ECONOMIC CoNDITIONS Observed Estimated Percent Factor Year Value Value Difference Difference Non-Agricultural 1965 70,529 68,377 -2,152 -3.0 Wage and Salary 1970 92,465 90,949 -1,516 -1.6 Employment 1975 161,315 155,908 -5,407 -3.4 1980 170,807 165,323 -5,484 -3.2 1982 199,545 195,990 -3,555 -1.8 Wages and Salaries 1965 721 729 .8 1.1 In Alaska 1970 1,203 1,121 -82 -6.8 (million nominal $)1975 3,413 3,253 -160 -4.7 1980 4,280 4,390 110 2.6 1_982 5,938 5,963 25 0.4 Personc:ilIncome 1965 .827 814 --13 -1.6 In Alaska 1970 1,388 1,276 -112 -8.1 (million nominal $)1975 3,455 3,212 -243 -7.0 1980 5,152 .5,393 241 4.7 1982 7,384 7,437 53 0.7 SotiYce~ISER ·(1985)~. 'j I I I,I TABLE B.5.3.3:COMPARISON OF ACTUAL (Page 1 of 2) AND PREDICTED ELECTRICITY CONSUMPTION OF 1980-1983 (GWh) RED SHCA Red Utility.J.! Case Outputl/Adjustedl/Reported Anchorage -Cook Inlet Area 1980 1 I,I Residential 980 939 936 Business 903 903 915 Others 109 109 109 Total 1,992 1,951 1,960 1981 Residential 1,034 1,030 916 Business 994 1,006 913 Others 117 117 139 Total 2,145 2,153 1,968 1982 Residential 1,088 1,096 1,033 Business 1,084 1,101 1,009 Others 126 126 160 Total 2,298 2,323 2,202 1983 Residential 1,142 1,069 1,059 Business 1,175 1,128 1,158 Others 135 135 97 Total 2,452 2,332 2,314 Fairbanks -Tanana Valley Area 1980 Residential 175 168 168 Business 234 234 239 Others 7 7 5 Total 417 408 412 1981 Residential 193 186 159 !I Others 7 7 4 Total 455 453 421 1/Two adjustments were made.First,residential space heat and ··au·tomooiTeana·EruCR·engine oTo-ckl:ieaterconsumptioii·was··scaTea~·bytfle actual number of heating degree-days compared to the normal heating degree days represented in the model.Second,the total use in both load centers was scaled for price effects using actual retail prices for electricity and estimated gas and oil prices for 1980-1983.Price effects were individually calculated for each year because the RED model contains data only for five year increments (i.e.1980,1985) and not for each intervening year.The scaling mechanism for price ............effectsisfuU.y..documentedin··Scott.,Kingand.Moe···1985.· Data from Alaska Power Administration,Alaska Electric Power Statistics,u.S.Department of Energy,Juneau,Alaska. o Sixth Edition,1960-1980,August 1981. o Seventh Edition,1960-1981,August 1982. o Eighth Edition,1960-1982,August 1983. o Ninth Edition,1960-1983,September 1984. Industrial consumption was estimatecr as Homer Electric Association Largec:ommEarcial c,g,tegory,reported.in:Burns ,g,ncil1c:I>onnell,1983, p.D.19.-I TABL E B.S.4.1:FORECASTS OF WORLD OIL PRICE APR M:>DEL (1985 $/bbl) Year Wharton Composite SHCA 1985 27.10 27.10 28.10 1990 24.80 26.50 27.70 1995 27.60 31.80 32.80 2000 31.30 38.10 41.00 2005 35.10 44.00 50.20 2010 40.70 51.00 61.50 Source:Exhibit D,Appendix D1 MAJOR VARIABLES AND ASSUMPTIONS APR MODEL 1985 1.69 2010 0.15 1985 9.10 2010 4.27 1985 0.86 2010 0.65 1985 12.5 2010 12.6 1985 15.0 2010 15.0 1985 0.03 2010 0.18 1985 1.42 2010 TABLE B.5 .4.2: Name North Slope Oil Variables1/ Production (mmbbl/day) Trans.&Quality Dif- ferential (1985 $/bbl) Prudhoe Bay Economic Limi t Factor Average State Royalty Rate (%) Average Nominal Sever- ance Tax Rate (%) North Slope Gas Variables1/ Production (bcf/day) Price (1985 $/mcf) Year Value Same Value in All Cases 1/Alaska Department of Revenue,APR Data Disk,1985,except as noted 1/See Exhibit D 0.05 0.00 0.54 0.58 Values Vary :B~tY1~~I1Cc':lI3~§ site SHCA "---"-"-------"-------""------"-""------ Cook Inlet Oil Variables1/ Production (mmbbl/day) Cook Inlet Gas Variables1/ Production (bcf/day) Cook Inlet Gas Variablesl/ Price (1985 $/mcf) 1985 2010 1985 2010 2010 4.97 6.43 .j r J '\) ! ) ] i· TABLE B.5.4.3:VARIABLES AND ASSUMPTIONS MAP MODEL Symbol Name Year Value Same Value in All Cases EMAGRI EMP9 EMCNX1 EMCNX2 EMT9X EMMXl EMMX2 EMFISH EMQ:1 EMGC TOURIST GGRWEVS UUS GRDIRPU GRUSCPI RPBS RPPS RTCSPX RPTS RPRY State Agricultural Employment (Employees) State Mining Employment (Employees) State High Wage Exog.Const. Emp •.(Employees) State Regular Wage Exog. Const.Emp.(Employees) State Exog.Transportation Emp.(Employees) State High Wage Manuf.Emp. (Employees) State Regular Wage Manuf. Emp.(Employees) State Fish Harvesting Emp. (Employees) State Active Duty Military Emp.(Employees) State Civilian Federal Emp. (Employees) Tourists Visiting Alaska (Visitor.s ) U.S.Real Wage Growth/Year U.S.Unemployment Rate U.S.Real Per Capita Income Growth/Year Price Level Growth/Year State Bonus Payment &Federal Shared Royalties Revenue (Million Nominal $) State Petroleum Property Tax Revenue (Million Nominal $) State Petroleum Corporate Tax (Million Nominal $) State Petroleum Production Tax Revenue (Million Nominal $) State Petroleum Royalty Revenue (Million Nominal $) 1985 2010 1985 2010 1985 2010 1985 2010 1985 2010 1985 2010 1985 2010 1985 2010 1985 2010 1985 2010 1985 2010 1985 2010 1985 2010 1985 2010 1985 2010 1985 2010 400 1,223 10,391 16,243 2,891 .336 218 o 1,116 2,335 o o 11,129 12,104 7,608 8;233 21,818 19,570. 17,907 20,285 810,000 1,560,000 .01 .06 .015 .055 50.6 82.0 107.4 451.9 190.0 44.9 Values Vary Composi te 1372.0 969.6 1372.0 1784.7 Between Cases SHCA 1372.0 1191.3 1372.0 2207.3 TABLE B.5.4.4:SUMMARY OF MAP MODEL PROJECTION ASSUMPTIONS (SHCA AND COMPOSITE CASES) (Page 1 of 5)',j 1 ASSUMPTIONS COMMON TO BOTH CASES NATIONAL VARIABLES ASSUMPTIONS U.S.Inflation Rate Real Average Weekly Earnings Real Per Capita Income Unemployment Rate INDUSTRY ASSUMPTIONS Trans-Alaska Pipeline North Slope Petroleum P.roduction_ DESCRIPTIONll Consumer prices rise at 5.5 percent annually after 1985 [GRUSCPI]. Growth in real average weekly earnings averages 1 percent annually [GRRWEUS]. Growth in real per capita income averages 1.5 percent annually after 1984 [GRDIRPU]• Long-run rate of 6 percent [UUS]. Operating employment remains constant at 990 through 2010 (~AP.F84). Petroleum employment increases through the e~J;'lyJiiQJL.~Q.jLpe aK..Qf.~!-~_.tl!Qtl ElCl!1cf ..and subsequently tapers off gradually. Construction employment is eliminated by the late 1990s.This case presumes no significant change in current oil price trends (NSO.84B)• ,\ .} 1 Upper Cook Inlet Petroleum Employment in exploration and development of oil and gas in the Upper Cook Inlet area declines·grt,fdual-ly--be·ginning-in-198-3--by······ _..··---·approxi-mate·ly-2.5-percen·t-pe·r-yea·r-(-UPG..F84-)-.-.. OCS Development Exploration and development activity grows through the mid-1990s and direct employment continues through the following decade at a slightly reduced level of approximately 7,000 (OCS.CM3 (-3))• ) (. TABLE B.5.4.4 (Page 2 of 5) ASSUMPTIONS COMMON TO BOTH CASES Oil Industry Headquarters Beluga Chuitna Coal Production Healy Coal Mining U.S.Borax Greens Creek Mine Red Dog Mine Other Mining Activity Agriculture Logging and Sawmills Pulp Mills Commercial Fishing - Nonbottomfish DESCRIPTION1/ Oil company headquarters employment in Anchorage rises by 1,150 between 1983 and 1986 to remain at around 4,600 through 2010 ~OHQ.F84). Development of 4.4 million ton/year mine for export beginning in 1990 provides total employment of 524 (BCL.04T(-4)). Export of approximately 1 million tons of coal annually will add 25 new workers to current base of 100 by 1986 (HCL.84X). The U.S.Borax mine near Ketchikan is brought into production with operating employment of 790 beginning in 1989 and eventually increasing to 1,020 (BXM.F84). Production from the Greens Creek Mine on Admiralty Island results in employment of 150 people from 1988 through 2003 (GCM.F84). The Red Dog Mine in the Western Brooks Range reaches full production with operating employment of 428 by 1993 (RED.F84). Mining employment not included in special projects increases from current level at 1 percent annually (OMN.F84). Moderate state support results in expansion of employment in agriculture by 4 percent per year (AGR.F83). Employment expands to over 3,200 by 1990 before beginning to decline gradually to about 2,800 after 2000 (FLL.F84). Employment declines at a rate of 1 percent per year after 1991 (FPU.F84). Employment levels in traditional fisheries harvest remain constant at 7,500 through 2010 (TCF.F84). TABLE B.5.4.4 (Page 3 of 5) ASSUMPTIONS COMMON TO BOTH CASES Commercial Fish Processing - Nonbottomfish Commercial Fishing -Bottomfish Federal Military Employment Light Army Division Deployment Federal Civilian Employment Tourism DESCRIPTION1I Employment in processing traditional fisheries harvests remains at the level of the average figure for the period 1978-1982, or around 7,300 (TFP.F84). The total U.S.bottomfish catch expands at a constant rate to allowable catch in 2000, with Alaska resident harvesting employment rising to 733.Onshore processing capacity expands in the Aleutians and Kodiak census divisions to provide total resident employment of 971 by 2000 (BCF.F83). Emplo~ment declines at 1 percent per year, consistent with the long-term trend since 1960 (GFM.F84). A portion of a new Army division is deployed to Fairbanks and Anchorage beginning in 1986, augmenting active-duty personnel by 2,600 (GFM.JPR)• Rises at 0.5 percent annual rate consistent with the long-term trend since 1960 (GFC.F84)• Number of visitors to Alaska increases by 30,000 per year to over 1.3 million by 2010 (TRS .XXX)• 1 1 ..-..-.-.-.-.--.~--'."-'-'--~"---"'--'~-'-.----_...,._--_..-.._..._.._--_.•........._--,-.... State Hydroelectric Projects Construction employment Alaska --Authori typro.fects~peaks af over 700in-T99-0 . for construction of several projects in Southcentral and Southeast Alaska (SHP.F83). STATE PETROLEUM REVENUE ASSUMPTIONS Bonuses Property Taxes Nominal average of past values net of major sales (SHC.B85). Aggregation of property taxes from specific petroleum activities based upon March 1985 Alaska Department of Revenue estimates (SHC.B85)and ISER estimates for OCS-related activities (OCS.CM3(-3)). L! TABLE B.5.4.4 (Page 4 of 5) ASSUMPTIONS COMMON TO BOTH CASES Petroleum Corporate Income Tax Rents State Sharing of Federal Petroleum Revenues STATE FISCAL BEHAVIOR ASSUMPTIONS State Appropriations Capital/Operations Split General Obligation Bonds Municipal Capital Grants Permanent Fund/Other Appro- priations in Excess of Spending Limit Permanent Fund Principal State Loan Programs Permanent Fund Dividend Use of Permanent Fund Earnings Personal Income Tax DESCRIPTION1/ No change from current method of calculating tax base.Based upon March 1985 Alaska Department of Revenue estimates (SHC.B85). Approximately constant at real current level [RPEN]• Increasing $1 million annually in nominal dollars with two steps of $10 million each in the mid-199Gs [RSFDNPX]. If funds available,ceiling established by Constitutional Spending Limit;otherwise appropriations equal revenues [APGF]. Two-thirds operations if Spending Limit in effect;three-fourths operations otherwise [EXSPLITX]• Bonding occurs up to point where debt service is 5 percent of state revenues. Funding terminated in FY 1987 [RLTMCAP]. None Continuous accumulation. New capitalization terminated in FY 1991 [EXSUBSX]. Dividend terminated after FY 1990 distribution [EXPFDIST]. Beginning in FY 1991,half of earnings transferred to General Fund;beginning in 1993,all earnings transferred to General Fund [EXPFTOGF]. Personal income tax reinstated in CY 1992. TABLE B.5.4.4 (Page 5 of 5) ASSUMPTIONS SPECIFIC TO EACH CASE COMPOSITE CAs~1 State Petroleum Revenue Assumptions Severance Taxes Royalties SHERMAN CLARK cAsElI State Petroleum Revenue Assumptions DESCRIPTION11 Based on 1985 "APA Average"world oil price projection used to drive Alaska Department Revenue APR petroleum revenue model (AOF.B85). Based on 1985 "APA Average"world oil price projection used to drive Alaska Department Revenue APR petroleum revenue model (AOF.B85). 'j .! ! of ] of 1 Severance Taxes Royalties Based on 1985 Sherman Clark world oil price projection used to drive Alaska Department of.Reve'nueAPR petroleum revenuemocfel ., (SHC.B85). Based on 1985 Sherman Clark world oil price projection used to drive Alaska Department of Revenue APR petroleum revenue model (SHC.B85)• ._......_--_...__...._.,--------------------------------------------- 11 Codes in brackets are model variables.Codes in parentheses indicate ISER names for MAP Model SCEN case files.Industry and state petroleum revenue assumptions are incorporated into the scenario generator. 2.1 Case HE53.3 with scenario S85.SUA3.j :J..I Case HE53.1 with scenario S85.SUA3. Symbol Name TABLE B.5.4.5:VARIABLES AND ASSUMPTIONS RED MODEL SHCA and Composite Case Values .(Page 1 of 3) Source Uncertainty Module Fuel Price Forecast Table B.5.4.6 and B.5.4.7 1983 Actual Data Combined with Escalation Rates b,c,d SAT ESR, CEOSR, CEGSR Housing Demand Coefficients Saturation of Residential Appliances Price Adjustment Coefficients ,Table B.5.4.8 .Battelle (1983) Table B.5.4.9 Battelle Northwest End Use Survey; Battelle (1983) Table B.5.4.l0 Scott,King,and Moe (1985) Housing Module I, I J THH HH Regional Household Forecast State Households by Age Group Table B.5.4.26 and B.5.4.27 Table B.5.4.26 and B.5.4.27 MAP Output MAP Outpu t Residential Module HI AC Households by Type of Dwellings Average Consumption of Appliances Table B.5.4.28 and B-5.4.29 Table B.5.4.1l Housing Module Output Battelle Northwest End Use Survey; Battelle (1983) TABLE B.5.4.5 (Page 2 of 3) Symbol Name FMS Fuel Mode Split (Percentage of Appliances Using Electicity) AS Initial Stock of Appliances I .1 SHCA and Composite Case Values Source Table B.5.4.11 Battelle (1983) Table B.5.4.9 Battelle (1983) and B.5 .4.11 c Growth in Electricity Use of Applicances Table B.5.4.12 Battelle (1983)j Scott,King and Moe (1985 d Vintage Specific Survival Rate Business Consumption Module TEMP Total Regional Employment Table B.5.4.13 Table B.5.4.24 and B.5.4.25 Battelle (1983) MAP Out put "1 j a,b Floors per Employee Table B.5.4.14 Scott ng and Moe 1985 BETA, BBETA Business Consumptions Table B.5.4.14 Scott,King and Moe 1985 Program-Induced Conservation Module Not used .....Misce.llaneo.u.s-Mo.duLe_.....~.... VACHG vh Vacant Housing Consumption per Vacant Housing Table B.5.4.30 B.5.4.31 300 kWh Battelle (1983) Battelle (1983) \I )J TABLE B.5.4.5 (Page 3 of 3) SHCA and Composite Symbol Name Case Values Source S1 Street Lighting Consumption 1.0 percent Battelle (1983) sh Proportion of Households 2.5 percent Battelle (1983) Having a Second Home shkWh Per Unit Second Home 500 kWh Battelle (1983) Consumpt ion Peak Demand Module LF Annual Load Factor Exhibit D Fairbanks 60.0 percent Anchorage 60.0 percent TABL E B.S.4 •6:FUEL PRI CE FORE CASTS USED BY RED -SHCA CASE (1980 DOLLARS) Anchorage -Cook Inlet Area Fal.rbanks -Tanana Valley Area Year Residential Bus iness Re sident ial Bus iness Heating Fuel Oil ($/MMBtu) 1980 7.75 7.20 7.83 7.50 1985 6.45 5.87 6.51 6.18 1990 6.36 5.79 6.42 6.10 1995 7.53 6.85 7.60 7.22 2000 9.41 8.56 9.49 9.02 2005 11.52 10.49 11.63 11.05 2010 14.11 12.84 14.24 13.53 Natural Gas ($/MMBtu) 1980 1.73 1.50 12.74 11.29 1985 2.11 1.74 10.60 9.12 1990 2.44 2.06 10.45 8.98 1995 4.23 2.97 12.37 10.64 2000 5.13 3.86 15.46 13.29 2005 6~10 4.84 18.94 16.29 2010 7.37 6.11 23.19 19.95 Electricity ($/kWh) 1980 .037 .034 .095 .090 1985 .057 .047 .082 .072 1990 .065 .053 .075 .066 --T99S ;076-;0-62 . 2000 .101 .082 .104 .091 2005 .105 .086 .107 .094 2010 .107 .088 .111 .096 1 ,J 1 1 -! 1 ~1 l j t 1 I ! I j I I ./ J TABLE B.5.4.7:FUEL PRICE FORECASTS USED BY RED-COMPOSITE CASE (1980 DOLLARS) Anchorage -Cook Inlet Area Fairbanks -Tanana Valley Area Year Residential Business Residential Business Heating Fuel Oil ($/MMBtu) 1980 7.75 7.20 7.83 7.50 1985 6.45 5.87 6.51 6.18 1990 6.31 5.74 6.37 6.05 1995 7.55 6.88 7.63 7.25 2000 9.07 8.25 9.15 8.69 2005 10 .51 9.56 10.61 10 .08 2010 12.18 11 .09 12.30 11.68 Natural Gas ($/MMBtu) 1980 1.73 1.50 12.74 11.29 1985 2.11 1.74 10 .60 9.12 1990 2.43 2.05 10.37 8.92 1995 4.11 2.85 12.43 10.69 2000 4.80 3.54 14.90 12.81 2005 5.46 4.20 17.27 14.86 2010 6.23 4.97 20.02 17.22 Electricity ($/kWh) I J 1980 .037 .034 .•095 .090 1985 .057 .047 .082 .072 1990 .065 .053 .075 .066 1995 .071 .058 .077 .068 .2000 .091 .074 .094 .082 2005 .105 .086 .107 .094 2010 .105 .086 .107 .095 Source:Battelle (1983). Note:These coefficients were used in the housing demand equations.A detailed explanation of these equations is presented in Battelle (1983). BAl -0.303 CAl 0.225 DAl 0.068 BA2 -0.175 CA2 0.086 DA2 0.039 BA4 0.080 CA4 -0.090 DA4 0.014 B2S 0.182 C2S -0.203 D2S 0.008 B3S 0.317 C3S -0.280 D3S -0.020 B4S 0.380 C4S -3.352 D4s -0.016 1 J ! 1 1 I, 1 1 ] l j I j ] ! I i .l Mobile Homes Variable Value Mu lti Fami ly Variable Value TABLE B.5.4.8:HOUSING DEMAND COEFFICIENTS Single Family Variable Value TABLE B.5 .4 •9:EXAMPLE OF MARKET SATURATIONS OF APPLIANCES IN SINGLE-FAMILY HOMES FOR ANCHORAGE-COOK INLET AREA (PERCENT) Refrigera tors Freezers Dishwashers Clothes Washers Year Default Range Default Range Default Range Default Range 1980 99.0 88.3 78.2 91.7 1985 99.0 98-100 90.0 85-95 85.0 80-90 92.0 90-94 1990 99.0 98-100 90.0 85-95 90.0 85-95 92.5 90-95 1995 99.0 98-100 90.0 85-95 90.0 85-95 93.7 91-96 2000 99.0 98-100 90.0 85-95 90.0 85-95 95.0 92-98 2005 99.0 98-100 90.0 85-95 90.0 85'-95 95.0 92-98 2010 99.0 98-100 90.0 85-95 90.0 85-95 95.0 92-98 TABLE B.5.4.l0:PARAMETER VALUES IN RED MODEL PRICE ADJUSTMENT MECHANISM Source:Scott,King,and Moe (1985). Short-Run Elasticities Own-Price Cross-Price Natural Gas Oil Long-Run Elasticities Own-Price Cross-Price 'Natural Gas Oil La.'gged Adju stment Residential Sector -O~12 0.0225 0.01 -0.40 0.075 0.033 0.700 Business Sector -0.15 0.0082 0.01 -0.50 0.027 0.033 0.700 1 I I 1 j ] ..I 1 .~ ] 1 1 ! j I I ( 1 j TABLE B.5.4.11:PERCENT OF APPLIANCES USING ELECTRICITY AND AVERAGE ANNUAL ELECTRICITY CONSUMPTION,RAILBELT LOAD CENTERS,1980 Anchorage Fairbanks Percentage US1ng Electr1c1ty Annual kWh Percentage US1ng EDectr1c1ty Annual kWh Appliance SF MH DP MF Consumption SF MH DP MF Consumption Space HeJt (Existing Stock) Single Family 16.0 NA NA NA 32,850 9.7 NA NA NA 43,380 Mobile Home NA 0.7 NA NA 24,570 NA .0.0 NA NA 33,210 Duplex NA NA 22.8 NA 21,780 NA NA 11.7 NA 28,710 Multi-amily NA NA NA 44.4 15,390 NA NA NA 14.8 19,080 Space HeJt (New Stock) 32,850SingleFamily10.9 NA NA NA 9.7 NA NA NA 43,380 Mobile Home NA 0.7 NA NA 24,570 NA 0.0 NA NA 33,210 Duplex NA NA 15.0 NA 21,780 NA NA 11.7 NA 28,710 Multi-amily NA NA NA 25.0 15,390 NA NA NA 14.8 19,080 Water ~eaters (Existing)36.5 50.4 44.0 60.9 3,300 33.1 42.8 43.1 26.2 3,300 Water eaters (New)10.0 0.7 15.0 25.0 3,300 33.1 42.8 43.1 26.2 3,300 Dryers 84.3 88.1 81.3 86.6 1,032 96.2 94.6 94.4 100.0 1,032 Ranges 75.8 23.2 85.2 88.2 850 79.0 48.2 95.0 97.1 850 Sauna-Jacuzzis 93.5 100.0 93.7 81.8 2,000 61.8 100.0 60.8 100.0 2,000 Refrigtrators 100.0 100.0 100.0 100.0 1,800 100.0 100.0 100.0 100.0 1,800 Freeze s 100.0 100.0 100.0 100.0 1,342 100.0 100.0 100.0 100.0 1,342 Dishwashers 100.0 100.0 100.0 100.0 250 100.0 100.0 100.0 100.0 250 Additi~nal Wate Heating (Existing)36.5 50.4 44.0 60.9 799 33.1 42.8 43.1 26.2 799 Wate Heating (New)10.0 0.7 15.0 25.0 799 33.1 42.8 43.1 26.2 799 Clothel Washers 100.0 100.0 100.0 100.0 90 100.0 100.0 100.0 100.0 90 Additi nal Wate Heating (Existing)36.5 50.4 44.0 60.9 1,202 33~1 42.8 43.1 26.2 1,202 Wate Heating (New)10.0 0.7 15.0 25.0 1,202 33.1 42.8 43.1 26.2 1,202 Miscellaneous 100.0 100.0 100.0 100.0 2,110 100.0 100.0 100.0 100.0 2,466 Source:IBattelle (1983). Source:Battelle (1983);Scott,King,and Moe (198S). .......~}..·Tncrementd·growth·of·80-·kWhpercustomerrn·-Anchorage·S-yearperi·od·;--····_·· 100 kWh in Fairbanks. TABLE B.S.4.12:GROWTH RATES IN ELECTRIC APPLIANCE CAPACITY AND INITIAL ANNUAL AVERAGE CONSUMPTION FOR NEW APPLIANCES Appliance Space Heat single Family Mobile Home Duplex Multi-Family Water Heaters Clothes Dryers Cooking Ranges Sauna-Jacuzzis Refrigerators .Freezers Dishwashers Additional Water Heating Clothes Washers Additional Water Heating Miscellaneous Appliances Average Annual kWh Consumption for New Appliances (198S) Anchorage Fairbanks 40,000 43,380 30,000 33,210 26,600 28,710 18,800 19,080 3,475 3,47S 1,032 1,032 1,2S0 1,2S0 1,7S0 1,7S0 1,S60 1,S60 1,SSO 1,SSO 230 230 740 740 70 70 1,OSO 1,OSO 2,160 2,S36 Growth Rate in Electrical Capacity Post 1985 (annual) O.OOS O.OOS O.OOS O.OOS 0.000 0.01 0.01 0.01 0.01 0.01 O.OOS 0.0 O.OOS 1/ J .j J 1 J 1 .] ] I j TABLE B.5.4.14:RED BUSINESS SECTOR ELECTRICITY CONSUMPTION PARAMETERS Variable Anchorage -Cook Inlet Fairbanks -Tanana Valley 1 1 Default Value Range Default Value Range Business Square Feet of Floorspace Per Employeell a i 383.023 317.5622 b 5.811 5.8112 Business Consump.tion of ElectricityZ7 BETA 1 -2.2118 -.7980 BBETA i 1.224 1.003-1.416 .1.0 .826-1.081 11 Equation is STOCK it=(ai *b *t)*TEMP it where:··. STOCK it =Square feet of business floorspace,load center i, year t a i =intercept (1972 value)square footage per employee in each load center i,year t b=growth rate parameter TEMP it =Total employment,load center l,year t ZI Equation is PRECON ik =exp [BETA i +BBETA i x In (STOCK ik)] PRECON ik =Nonprice-adjusted business consumption (MWh),load center 1 forecast period K BETA i =patametet equal to regression equation intercept,load center 1 BBETA i =percentage change in business consumption for a 1%change in stock (floorspace elasticity),load center i STOCK ik square feet of business floorspace,load center l,forecast period k. 1 ] J .1 ] ! TABLE B.5.4.15:VARIABLES AND ASSUMPTIONS --OGP MODEL ECONOMIC PARAMETERS 1.All Costs in January 1985 Dollars 2.Base Year for Present Worth Analysis:1985 3.Analysis Periods: System Expansion:1996-2025 Annual Cost Extension:2026-2054 4.Electrical Load Forecast:1985 to 2025 5.Discount Rate:3.5 percent 6.Inflation Rate:0 percent 7 ..Economic Life of projects: (Page 1 of 3) Combustion Turbines: Combined Cycle Turbines: Steam Turbines Hydroelectric Projects Transmission 8.Annual Fixed Carrying Charges 25 years 30 years 35 years 50 years 50 years Cost of Money Amortization Insurance Total 25-year Life 3.50 2.57 0.25 6.32 30-year 35-year 50-year Life Life Life 3.50 3.50 3.50 1.94 1.50 0.70 0.25 0.25 0.10 5.69 5.25 4.36 I I 9.Susitna Project Construction Cost,$mill ion Watana Stage I 2682 Devil Canyon Stage II 1394 Watana Stage III 1319 Total 5395 10.Susitna Annual Operation and Maintenance Cost,$million 1999-2004 2005-2011 2012-2017 2018-2025 11.50 12.75 12.75 11.45 TABLE B.5.4.15 (Page 2 of 3) Coal 200 MWl/Parameters THERMAL GENE RATI NG PLANT Combined Cycle 229 MW PARAMETERS (1985 $) Combustion Turbine 87 MW6./ ......--ll--Gross···out-pu-t·at··30.9--F--is237-.-3MW··and-inc1udes--correctioo··· .-----..---'------..--for--water--in:iection for--NOx.contI'o-1·,net-out-puG-o-f-.-·2-30--MW--· includes correction for station auxiliary loads. ~/Values reflect assembly of three units,gross output at 30°F is 268.8 MW and includes correction for water injec- tion for NOx control,net output of 262 MW (87.3 MW each) includes correction for station auxiliary loads. J,./Includes AFDC at.3.5 percent interest assuming an S""sha.ped expenditure curve. Heat Rate (Btu/kWh) Earliest Availability O&M Costs Fixed O&M ($/kW/yr) Variable O&M ($/MWh) Outages Planned Outages (%) Forced Outages (%) Construction Period (yrs) Startup Time (yrs) Unit Capital Cost ($/kW) Beluga/Railbelt Nenana Unit Capital Cost ($/kW):J/ Beluga/Railbelt Nenana 10,300 1992 61.42 4.30 8 5.7 6 3 2,593 2 702 2,877 2,998 9,200 1988 13.26 0.66 7 8 2 2 650 673 12,000 1988 8 •.76 0.58 3.2 8 1 1 386 393 ] ] .1 j -j j I ] I j l cj ---~-- TABLE :8.5.4.15 (Page 3 of 3) FUEL PRICES (1985) SHCA Forecast Composite Forecast Forecas tl/ Coal Price Coal Price Nenana Beluga Nenana Beluga Year I Delivered Minemouth Oil Ga s 'I/Del ivered Minemouth Oil .Gas 'I/Oil Gasl/ ($/MMBtu)($/MMBtu)($/bbl)($/MMBtu)$/MMBtu $/MMBtu ($/bbl)($/MMBtu)($/bbl)($/MMBtu) 1985 I 1.84 1.32 28.10 2.13 1.84 1.42 2710 1.98 27.10 1.97 1990 I 1.99 1.45 27.70 2.08 1.99 1.5'4 26.50 1.90 24.80 1.66 1995 I 2.14 1.60 32.80 2.80 2.14 1.65 31.80 2.65 27.60 2.05 2000 I 2.31 1.78 41.00 3.95 2.31 1.78 38.10 3.53 31.30 2.57 2010 I 2.69 2.13 61.50 6.83 2.69 2.19 51.00 5.37 40.70 3.89 2020 I 3.13 2.55 85.00 10.15 3.13 2.57 68.90 7.85 54.60 5.83 2030 3.64 3.30 96.00 11.70 3.64 3.08 75.00 8.70 73.40 8.84 2040 4.24 4.10 106.00 13.12 4.24 3.22 75.00 8.70 75.00 8.70 2050 4.94 5.12 117.00 14.67 .4.94 3.74 75.00 8.70 75.00 8.70 1_/Cdmposite forecast coal prices assumed for Wharton forecast. 2_/Includes 0.40 $/MMBtu charge for delivery. TABLE B.5.4.16:SHCA CASE FORECAST SUMMARY OF INPUT AND OUTPUT DATA Item Description 1985 1990 1995 2000 2005 2010 World Oil Price (1985$/bbl)28.10 27.70 32.80 41.00 50.20 61.50 Energy Price Used by RED (1980$) Heating Fuel Oil-Anchorage ($/MMBtu)6.45 6.36 7.53 9.41 11.52 14.11 Natural Gas -Anchorage ($/MMBtu)2.11 2.44 4.23 5.13 6.10 7.37 State Petroleum RevenueslJ (Million Nominal $) Production Taxes 1,372 1,299 1,286 994 903 1191 Royalty Fees 1,372 1,826 2,031 1,983 1,912 2,207 State General Fund Expenditures (Million Nominal $)3,665 3,773 5,692 5,831 6,387 7,762 State Population 536,525 563,923 597,969 632,655 657,639 699,607 State Employment 269,087 281,962 304,522 319,827 325,447 348,304 Railbelt Population 381,264 399,873 422,238 440,956 468,823 506,384 Railbelt Employment 181,885 189,109 201,168 210,611 222,663 243,163 Railbelt Total Number of Households 134,300 142,574 152,499 161,248 172,218 186,823 Railbelt Electricity Consumptionb / (GWh) Anchor.age 2,Zl5..2,284 2,.983 .3,079 ..3,336...3.,848 Fairbanks 608 797 902 919 978 1,081 Total 3,323 3,581 3,885 3,998 4,314 .4,929 Railbelt Peak Demand (MW)632 681 739 761 821 938 1/Petroleum revenues also include corporate income taxes,oil and gas property taxes,lease bonuses,rents,and federal shared royalties. .j 1 ] .] J ] I ] ] ] TABLE B.5.4.17:COMPOSITE CASE FORECAST SUMMARY OF INPUT AND OUTPUT DATA Item Description 1985 1990 1995 2000 2005 2010 World Oil Price (1985$/bbl)27.10 26.50 31.80 38.10 44.20 51.00 Energy Price Used by RED (1980$) Heating Fuel Oil-Anchorage ($/MMBtu)6.45 6.31 7.56 9.07 10.51 12.18 Natural Gas -Anchorage ($/MMBtu)2.11 2.43 4.11 4.80 5.46 6.23 State Petroleum Revenuesl / (Million Nominal $) Production Taxes 1,372 1,224 1,238 913 783 970 Royalty Fees 1,372 1,717 1,953 1;819 1,650 1,785 State General Fund Expenditures (Million Nominal $)3,665 3,610 5,280 5,586 6,009 7,131 State Population 536,525 562,317 595,023 '6Q8,969 653,542 695,215 State Employment 269,087 280,177.302,226 318,010 323,335 346,249 Railbelt Population 381,264 398,969 419,236 438,363 465,911 503,372 Railbelt Employment 181,885 187,967 199,116 209,340 221,172 241,761 Railbelt Total Number of Households 134,300 142,243 151,445 160,294 171,129 185,668 Railbelt Electricity Consumptionl/. (GWh) Anchorage 2,715 2,770 3,003 3,160 3,344 3,815 Fairbanks 608 793 907 943 981 1,073 i I Total 3,323 3,563 3,910 4,103 4,325 4,888 I !Railbelt Peak Demand (MW)632 678 744 781 823 930~J 1/Petroleum revenues also include corporate income taxes,oil and gas property taxes,lease bonuses,rents,and federal shared royalties. 1/At customer level I. TABLE B.5.4.18:SHCA CASE STATE PETROLEUM REVENUES (Million Nominal $) Total Total to Including General Bonuses,Fund (Net Rents,of and Permanent Corporate Federal Fund Severance Income Property Shared Contri- Year Royalties Taxes Taxes Taxes Royalties bution) 1983 1437.900 1493.000 236.000 152.600 3420.600 3035.849 1984 1396.700 1392.400.265.100 131.000 3237.300 2875.100 1985 1372.000 1372 .000 190.000 107.400 3092.000 2736.350 1986 1695.265 1627.469 24.2.100 102.900 3701.734 3269.417 1987 1828.607 1735.756 264.200 107.000 3970.563 3504.661 1988 1848.434 1453.355 274.100 116.523 3728.412 3257.303 1989 1863.817 1411.140 294.200 137.637 3743.794 3268.590 1990 ...1826.438 ....1299.429 304.000 144.649 3612.515 3146.406 1991 1894.220 1316.453 303.700 147.376 3701.749 3169.838 1992 1971.221 1337.337 29L 700 140.725 3781.982 3228.621 1993 2054.794 1379.784 297.800 156.315 3912.693 3283.655 1994 2050.586 1355.180 268.100 165.402 3882.268 3254.192 1995 2030.882 1285.693 251.100 161.875 3783.550 3158.085 1996 2023.862 1247.807 235.200 206.137 3779.006 3152.047 1997 2046.940 1215.856 222.600 230.911 3783.307 3149.124 1998 2046.433 1167.739 200.700 270.521 3753.394 3119.063 1999 2008.302 1070.878 179.300 306.096 3633.576 3010.385 2000 1983.280 993.533 158.400 379.048 3584.261 2968.277 2001 1843.249 842.240 138.000 449.979 3345.468 2770.893 2002 1780.510 792.668 121.800 486.557 3254.535 2698.482 ..------_..--._----,--,.······-··-200T --18T4'~T69"····-814:537 ..--TOT~500 485~099-"'329S~304 ···---27Z8-~853' -~-"---_._---··-----2004-·..--t8-5-4--.-22-1~"-851--;.-4-50'-.."9'4--;900-4-83-;-2,0-"--3358;-8-4-]:----·-2780-;-0,-4-.. 2005 1911.559 902.923 83.800 480.773 3455.055 2858.787 2006 1955.380 951.888 74.000 477 .435 3536.702 2926.688 2007 2031.676 1025.718 65.300 473.079 3674.773 3041.570 2008 2035.953 1062.136 57.600 467.558 3703.246 3068.460 2009 2118.701 1112.038 50.900 460.572 3823.211 3163.300 2010 2207.310 1191.319 44.900 451.948 3977.478 3290.684 Source:MAP Model Output.Files RE53.1 and HER53.1.Variables:RPRY,RPTS, RTCSPX,RPPS,RP9S,and RP9SGF. J ] ,I .J J l ] .') I ,I 'I j ,I .'] TABLE B.5.4.19:.COMPOSITE CASE STATE PETROLEUM REVENUES (Million Nominal $) Total Total to Including General Bonuses,Fund (Net Rents,of and Permanent Corporate Federal Fund Severance Income Property Shared Contri- Year Royalties Taxes Taxes Taxes Royalties bution) 1983 1437.900 1493.000 236 ..000 152.600 3420.600 3034.849 1984 1396.700 1392.400 265.100 131.000 3237.300 2875.100 1985 1372.000 1372.000 190.000 107.400 3092.000 2736.350 1986 1605.383 1544.257 242.100 102.900 3528.640 3118.794 1987 1729.298 1644.928 264.200 107.000 3780.426 3339.351 1988 1746.100 1375.635 274.100 116.523 3548.358 3102.833 1989 1757.513 1333.247 294.200 137.637 3559.597 3110.969 1990 1717.382 1224.391 304.000 .144.649 3428.422 2989.576 1991 1790.046 1246.316 303.700 147.376 3527.438 3024.175 1992 1871.650 1271.800 291.700 140.725 3616.875 3090.896 1993 1960.157 1318.919 279.800 156.315 3756.291 3155.644 1994 1963.875 1299.419 268.100 165.402 3739.796 3137.733 1995 1953.026 1237.628 251.100 161.875 3657.629 3055.521 1996 1927.142 1189.558 235.200 206.137 3624~037 3026.994 II 1997 1930.842 1148.461 222.600 230.911 3599.814 3000.461 1998 1912.060 1092.759 200.700 270.521 3544.041 2950.022 LJ 1999 1858.931 993.055 179.300 306.096 3406.382 2828.002 2000 1818.815 912.904 158.400 379.048 3339.167 2772.522 2001 1669.401 764.645 138.000 449.979 3094.025 2571.604 2002 1593.035 711.232 121.800 486.557 2985.623 2485.812 2003 1603.990 722.449 107.500 485.099 2993.038 2489.641 2004 1620.013 746.507 94.900 483.270 3019.690 2511.186 2005 1650.406 782.548 83.800 480.773 3073.528 2555.605 2006 1667.140 815.027 74.000 477 .435 3111.602 2588.060 2007 1710.077 867.402 65.300 473.079 3194.857 2658.134 2008 1690.615 886.851 57.600 467.558 3182.624 2651.439 2009 1736.014 916.641 50.900 460.572 3245.126 2700.022 2010 1784.688 969.571 44.900 451.948 3333.107 2773.100 Source:MAP Model Output Files HE53.3 and HERS3.3.Variables:RPRY,R?TS, RTCSPX,RPPS,RP9S,and RP9SGF. TABLE B.5.4.20:SHCA CASE STATE GOVERNEMENT FISCAL CONDITIONS (Million Nominal $) Unre-Percent of stricted Permanent General Fund Earn- Fund General Permanent State State ings to Expendi-Fund Fund Personal Subsidy General Year tures Balance Dividends Income Tax Programs Fund 1983 3499.489 2315.700 176.000 0.000 274.700 23.0 1984 3518.373 2041.822 193.917 0.000 250.000 0.0 1985 3664.836 1497.312 190.524 0.000 250.000 0.0 1986 3410.682 1712.316 238.049 0.000 250,.000 0.0 1987 3736.196 1865.815 269.060 0.000 250.000 0.0 1988 3915.580 "'1611.859 291.666 0.000 250.000 0.0 1989 4150.453 1125.223 314.778 'O.000 200.000 0.0 1990 3772.734 873.367 350.895 0.000 100.000 0.0 1991 4012.436 868.398 0.000 0.000 0.000 50.0 1992 4295.910 935.254 0.000 244.207 0.000 50.0 1993 4922.473 1304.047 0.000 494.410 0.000 100.0 1994 5736.023 993.992 0.000 557.415 0.000 100.0 1995 5692.410 739.742 0.000 609.495 0.000 100.0 .__._._.~---.-~.._--~~._-_._-_._- 1996 5663.820 604.469 0.000 651.376 0.000 100.0 1997 5611.551 623.102 0.000 691.34.9 0.000 100.0 1998 5708.297 640.164 0.000 745.909 0.000 100.0 1999 5750.297 646.602 0.000 804.565 0.000 100.0 2000 5831.277 666.785 0.000 865.454 0.000 100.0 2001 5802.555 659.980 0.000 925.312 0.000 100.a 2002 5833.957 668.094 0.000 974 •.152 0.000 100.0 -------200:3-----591-0·.-074-------695~-758--····-----0;-000 ·---1029;-248----0-;,-000 -100-;0--'--'--- ·-··-----2-004--····--6-g4-.-2-70----7-3~.9.Q_6---0.000---1096-.:306---0-;-000-----100-;-0------. 2005 6386.668 778.551 0.000 1174.044 0.000 100.0 2006 6634.203 818.473 0.000 1261.026 0.000 100.0 2007 6927.227 862.113 0.000 1350.871 0.000 100.0 2008 7150.926 899.289 0.000 1446.110 0.000 100.0 2009 7421.859 964.199 0.000 1551.661 0.000 100.0 2010 7762.457 1039.770 0.000 1669.305 0.000 100.0 Source:MAP Model Output Files HE53.1 and HERS3.1. Variables:EXGFBM,BALGF9,EXTRNS,RTIS,EXSUBS,and EXPFTOGF. ,I ,I l' ] I l 1 I ] j 1 I .1 j l 1 ] ) 1 TABLE B.5.4.21:COMPOSITE CASE STATE GOVERNMENT FISCAL CONDITIONS (Million Nominal $) Unre-Percent of stricted Permanent General Fund Earn- Fund General Permanent State State ings to Expendi-Fund Fund Personal Subsidy General Year tures Balance Dividends Income Tax Programs Fund 1983 3499.489 2315.700 176.000 0.000 274.700 23.0 1984 3518.373 2041.822 193.917 0.000 250.000 0.0 1985 3664.836 1497.312 190.524 0.000 250.000 0.0 1986 3497.226 1475.323 237.954 0.000 250.000 0.0 1987 3519.947 1662.631 268,.661 0.000 250.000 0.0 1988 3907.627 1246.773 290.727 0.000 250.000 0.0 1989 4133.516 591.129 313.038 0.000 200.000 0.0 1990 3610.305 303.882 348.073 0.000 '100.000 0.0 1991 3810.986 303.789 0.000 0.000 0.000 50.0 1992 4104.195 370.859 0.000 242.797 0.000 50.0 1993 4943.199 526.613 0.000 493.807 0.000 100.0 1994 5215.172 538.273 0.000 555.853 0.000 100.0 1995 5279.566 529.848 0.000 604.697 0.000 100.0 1996 5344.398 537.188 0.000 645.287 0.000 100.0 tJ 1997 5422.613 553.246 0.000 685.799 0.000 100.0 1998 5498.207 566.367 0.000 741.467 0.000 100.0 1999 5522.371 569.859 0.000 800.179 0.000 100.0 2000 5585.840 586.949 0.000 860.942 0.000 100.0 2001 5547.316 578.715 0.000 920.752 0.000 100.0 2002 5562.297 583.645 0.000 969.491 0.000 100.0 2003 5669.082 605.258 0.000 1024.249 0.000 100.0 2004 5818.734 635.445 0.000 1090.747 0.000 100.0 2005 6009.129 671.547 0.000 1167.367 0.000 100.0 2006 6207.797 706.578 0.000 1252.621 0.000 100.0 2007 6446.035 745.398 0.000 1341.272 0.000 100.0 2008 6627.434 777.578 0.000 1436.832 0.000 100.0 2009 6850.598 830.434 0.000 1543.331 0.000 100.0 2010 7130.594 889.020 0.000 1660.639 0.000 100.0 Source:MAP Model Output Files HE53.3 and HER53.3. Variables:EXGFBM,BALGF9,EXTRNS,RTIS,EXSUBS,and EXPFTOGF. ~ABLE B.5.4.22:SHCA CASE POPULATION (thousands) Greater Greater Year State Railbelt Anchorage Fairbanks 1983 510.484 1984 527.453 374.240 301.002 73.238 1985 536.525 381.264 307.278 73.987 1986 549.371 391.208 311.344 79.864 1987 551.850 390.471 310.969 79.503 1988 553.178 391.972 312.366 79.607 1989 560.657 397.279 317.269'80.011 1990 563.923 399.873 ·320.000 79.874 1991 567.837 402.244 321.868 80.376 1992 569.795 401.942 321.495 80.447 1993 576.465 406.349 '324.935 81.414 1994 589.708 417.667 334.396 '83.272 1995 597.969 422.238 338'.649 83.590 1996 603.645 419.442 336.577 82.865 1997 607.509 423.985 340.597 83.388 1998 616.940 422.667 339.905 82.763 1999 623.645 432.981 348.769 84.213 2000 632.655 440.956 355.751 .206 2001 638.154 450.147 363.651 86.496 2002 641.315 452.291 365.571 86.721 2003 645.454 457.491 370.066 87.425 2004 651.059 462.966 374.809 88.157 2005 657.639 468.823 379.953 88.870 2006 665.142 475.693 385.946 89.747 ---.-.__......_.•.__..,--"'.-..-.-".---.---..._--_.-._.-._.._..-.-.---_._---------.2007-...._.......612.362 _······_·.··0·------482.381 .391.752 ...........90.•630 - -.-_.._~_._--~----~-_.__..__.._---_._•.._._._-~.._._-----...2.0_0_a_._...._6_8_0___2_2_6___...~2..:i~_.__J97 .903 ..91.452 _...._----- 2009 689.099 497.095 404.682 92.414 2010 699.607 506.384 412.734 93.651 Source:MAP Model Output Files HE53.1 and HER53.1. Variables:POP,P.IR,P.AG,and P.FG. j I 1 1 i J j ] I .1 j J I 1 j i 1 TABLE B.5.4.23:COMPOSITE CASE POPULATION (thousands) Greater Greater Year State Railbelt Anchorage Fairbanks 1983 510.484 1984 527.453 374.240 301.002 73.238 1985 536.525 381.264 307.278 73.987 1986 550.839 391.606 311.573 80.033 1987 551.434 389.888 310.504 79.385 1988 552.191 390.945 311.520 79.426 1989 559.888 396.563 316.673 79.891 1990 562.317 398.969 319.317 79.653 1991 565.875 401.077 320.956 80.122 1992 567.640 400.610 320.444 80.166 1993 576d55 405.522 324.154 81.369 1994 587.631 415.703 332.791 82.913 1995 595.023 419.236 336.150 83.086 1996 599.708 416.280 334.018 82.262 1997 603.835 421.303 338.419 82.884 1998 613.332 420.115 337.833 82.282 1999 619.991 430.404 346.681 83.723 2000 628.969 438.363 353.654 84.709 II 2001 634.505 447.581 361.579 86.003 2002 637.662 449.725 363.500 86.226 ,...-.)641.739 454.889 367.968 86.9222003 2004 647.234 460.295 372.658 87.638 2005 653.542 465.911 377.608 88.303 2006 660.673 472.421 383.303 89.118 2007 667.716 478.976 388.991 89.986 2008 675.723 486.141 395.288 90.854 2009 684.784 494.124 402.265 91.859 2010 695.215 503.372 410.295 93.077 Source:MAP Model Output Files HE53.3 and HER53.3. Variables:POP,P.IR,P.AG,and P.FG. TABLE B.5.4.24:SHCA CASE EMPLOYMENT (thousands) State Non-Ag Greater Greater Wage and State Railbelt Anchorage Fairbanks Year Salary Total Total Total Total 1983 213.243 254.642 1984 222.290 264.038 179.069 142.623 36.446 1985 227.237 269.087 181.885 145.242 36.643 1986 230.977 275.622 186.029 146.478 39.551 1987 230.747 275.175 184.430 145.319 39.112 1988 231.062 275.298 185.665 146.309 39.356 1989 237.587 282.046 189.091 149.379 39.712 1990 237.706 281.962 189.109 149.717 39.392 1991 239.485 283.649 190.640 150.843 39.797 1992 239.117 283.060 190.715 150.751 39.964 1993 244.731 288.840 192.612 152.380 40.232 1994 256.670 301.365 198.950 157.805 41.145 1995 259.797 304.522 201.168 159.816 41.352 1996 260.901 305.539 201.285 159.853 41.433 199Z ....2.60 ....~.~__.~4..a4.2 201.Z2A ..16Q.~,3Jl6 ..A1.378 1998 267.445 312.240 203.778 162.172 41.606 1999 269.222 314.032 206.967 164 ..989 41.978 2000 274.802 319.827 210.611 168.225 42.386 2001 275.004 319.843 213.426 170.652 42.773 2002 273.982 318.556 214.858 171.710 43.148 2003 274.888 319.326 216.952 173.465 43.487 2004 277.481 321.894 219.582 175.696 43.886 -200S-...280;;995 .·----325-;'447···-222:-663-··------178;;-343 ------44;320- --~~-~--"-~~~._-_.._-------~~-~._----~-~--~------_.-----_._---..~~_._..__._._._- 2006 285.102 329.634 226.402 181.529 44.873 2007 288.438 333.002 230.098 184.620 45.479 2008 292.451 337.094 233.656 187.694 45.961 2009 297.192 341.965 237.800 191.240 46.561 2010 303.306 348.304 243.163 195.767 47.396 Source:MAP Model Output Files HE53.1 and HER53.1. Variables:EM97,EM99,M.IR,M.AG,and M.FG. ,1 .J I j I 1 j "j ] j ] I 1 ] ) I ) j ] TABLE B.5.4.25:COMPOSITE CASE EMPLOYMENT (thousan~s) State Non-Ag Greater Greater Wage and State Railbelt Anchorage Fairbanks Year Salary Total Total Total Total 1983 213.243 254.642 1984 222.290 264.038 179.069 142.623 36.446 1985 227.237 269.087 181.885 145.242 36.643 1986 232.708 277.462 187.016 147.205 39.812 1987 229.835 274.206 183.619 144.679 38.940 1988 229.786 273.942 184.560 145.424 39.136 1989 236.797 281.206 188.419 148.836 39.583 1990 236.028 280.177 187.967 148.837 39.130 1991 237.719 281.771 189.426 149.896 39.530 1992 237.420 281.254 189.540 149.833 39.707 1993 245.445 289.600 192.846 152.501 40.345 1994 254.997 299.584 197.462 156.611 40.851 1995 257.641 302.226 199.116 158.141 40.975 1996 258.035 302.488 198.978 158.013 40.965 1997 258.304 302.631 200.169 159.111 41.059 IJ 1998 265.601 310.276 202.399 161.068 41.330 1999 267.451 312.145 205.644 163.933 41.712 2000 273.096 318.010 209.340 167.212 42.128 2001 273.398 318.132 212.230 169.700 42.530 2002 272.404 316.875 213.684 170.776 42.908 2003 273.268 317.600 215.750 172.510 43.240 2004 275.770 320.071 218.317 174.692 43.625 2005 279.013 323.335 221.172 177.159 44.013 2006 282.796 327.176 224.621 180.110 44.511 2007 286.091 330.500 228.281 183.167 45.115 2008 290.405 334.912 232.107 186.452 45.655 2009 295.394 340.048 236.489 190.190 46.299 2010 301.379 346.249 241.761 194.650 47.111 Source:MAP Model Output Files HE53.3 and HER53.3. Variables:EM97,EM99,M.IR,M.AG,and M.FG. Source:MAP Model Output Files HE53.1 and HER53.1. Variables:HH,HH.IR,HH.AG,and HH.FG. 174.930 142.268 32.662 177.555 144.530 33.026 -T8"0".-Z89-.-"-"-""T4-6:913"--".-".··:rf:36'6--"---- ....."--.1"8'3-:-;289-"""-"-···"-r-lf9-;-533-"--------33--;75·6~_:_----. 186.823 152.580 34.243 131.373 106.128 25.246 134.300 108.704 25.596 137.863 110.118 27.745 138.002 110.306 27.696 138.830 Ill.035 27.795 141.253 113.204 28.050 142.574 114.496 28.079 143.725 115.402 28.322 143.962 115.544 28.418 146.003 117.144 28.859 150.409 120.808 29.601 152.499 122.694 29.805 152.187 122.509 29.678 154.032 124.123 29.909 154.385 124.544 29.841 158.106 127.737 30.369 161.248 130.468 30.780 164.568 133.316 31.252 165.607 134.220 31.388 167.646 135.968 31.677 169.862 137.871 31.991 172.218 139.921 32.298 SHCA CASE HOUSEHOLDS (thousands) j J ) ) 1 I ) I ] I j .) ] I J ] j I 1 "'j,,~ (Page 1 of 2) Greater Fairbanks Greater AnchorageRailbelt TABLE B.5.4.26: Year State 1983 171.664 1984 178.150 1985 181.869 1986 186.311 1987 '187.702 1988 188.676 1989 191.754 1990 193.379 1991 195.217 1992 196.374 1993 199.139 1994 204.155 1995 207.471 1996 209.895 1997 211.690 1998 215.375 1999 218.129 2000 221.663 2001 223.997 2002 225.523 2003 227.368 2004 229.700 2005 232.357 2006 235.322 2007 238.186 ····1UO-8------":r4T:T64- "-'-'''''-----""2009--------2-lflj;';;"o79"---"" 2010 248.645 TABLE B.5.4.26 (Page 2 of 2) Head Younger Head Head Head Older Year Total Than 25 25-29 30-54 Than 54 1983 171.664 21.132 29.622 96.310 24.600 1984 178.150 21.394 30.205 100.802 25.749 1985 181.869 21.155 30.102 103.790 26.822 1986 186.311 21.134 30.299 106.954 27.923 1987 187.702 20.623 29.714 108.371 28.994 1988 188.676 20.138 29.106 109.340 30.092 1989 191.754 20.099 29.134 111.210 31.311 1990 193.379 19.837 28.828 112.204 32.510 1991 195.217 19.661 28.641 113.167 33.748 1992 196.374 19.406 28.331.113.652 34.985 '':'. 1993 199.139 19.459 28.500 114.876 36.303 1994 204.155 19.879 29.282 117.269 37.725 1995 207.471 19.973 29.599 118.806 39.093 1996 209.895 19.919 29.690 119.851 40.435 1997 211.690 19.781 29.639 '.120.513 41.757 1998 215.375 19.969 30.117 122.137 43.152 1999 218.129 19.992 30.346 123.285 44.506 2000 221.663 20.139 30.792 124.848 45.885 L]2001 223.997 20.086 30.918 125.785 47.206 2002 225.523 19.923 30.850 126.266 48.484 2003 227.368 19.835 30.897 126.878 49.758 2004 229.700 19.833 31.097 127.738 51.032 2005 232.357 19.879 31.394 128.784 ,52.299 2006 235.322 19.964 31.776 130.024 53.557 2007 238.186 20.021 32.128 131.246 54.791 2008 241.264 20.102 32.533 132.616 56.014 2009 244.679 20.221 33.019 134.208.57.231 2010 248.645 20.403 33.638 136.149 58.454 Source:MAP Model Output Files HE53.1 and HER53.1. Variables:HH,HH24 ,HH25.29,HH30.54,and HH55. TABLE B.5.4.27:COMPOSITE CASE HOUSEHOLDS (Page 1 of 2) (thousands) Greater Greater Year State Railbelt Anchorage Fairbanks 1983 171.664 1984 178.150 131.373 106.128 25.246 1985 181.869 134.300 108.704 25.596 1986 186.818 138.028 110.217 27.811 1987 187.561 137.805 110.150 27.655 1988 188.337 138.473 110.742 27.732 1989 191.489 141.002 112.995 28.007 1990 192.825 142.243 114.246 27.997 1991 194.538 143.298 115.070 28.228 1992 195.626 143.476 115.162 28.314 1993 199.021 145.716 116.871 28.845 1994 203.432 149.716 120.244 29.473 1995 206.446 151.445 121.819 29.626 1996 208.526 151.059 121.599 29.460 1997 210.404 153.061 123.337 29.724 1998 214.106 153.453 123.790 29.663 1999 216.838 157.162 126.975 30.187 2000 220.355 160.294 129.699 30.595 20_01 ..2_22_•.6_9_6 1.63.6_12 1.3_2.•.5..5.2_31.Q6Z 2002 224.215 164.654 133.452 31.202 2003 226.033 166.675 135.188 31.487 2004 228.321 168.862 137.068 31.794 2005 230.879 171.129 139.047 32.083 2006 233.710 173.712 141.287 32.425 2007 236.506 176.284 143.502 32.782 2008 239.624 179.076 145.939 33.138 ..·2009·-----..·---243~-096 ....·---T8Z~154--·-----T48-;;613-·--·----·33:S4Z--·--- ..---··---·_·-20·10---------24-7-;:029--.....--1·8-5-;:668--··--·+51.64-8--··------:34-;:02·1-- Source:MAP Model Output F les HE53.3 and HER53.3. Variables:HH,HH IR,HH.AG,and HH.FG. ] 1 1 1 I .I ~ ] l j I ] I I 1 1 ] j ] TABLE B.5.4.27 (Page 2 of 2) Head Younger Head Head Head Older Year Total Than 25 25-29 30-54 Than 54 1983 171.664 21.132 29.622 96.310 24.600 1984 178.150 21.394 30.205 100.802 25.749 1985 181.869 21.155 30.102 103.790 26.822 1986 186.818 21.222 30.431 107.222 27.943 1987 187.561 20.589 29.668 108.315 28.989 1988 188.337 20.075 29.012 109.170 30.080 1989 191.489 20.056 29.066 111.065 31.302 1990 192.825 19.751 28.689 111.896 32.489 1991 194.538 19.563 28.480 112.774 33.721 1992 195.626 19.307 28.164 113.204 34.952 1993 199.021 19.473 28.509 114.748·36.292 1994 203.432 19.787 29.133 116.826 37.686 1995 206.446 19.839 29.380 118.190 39.037 [1996 208.526 19.741 29.395 119.030 40.360 1997 210.404 19.632 29.385 119.709 41.678 1998 214.106 19.833 29.882 121.325 43.065 I 1999 216.838 19.860 30.119 122.450 44.409 2000 220.355 20.010 30.573 123.996 45.775 IJ 2001 222.696 19.964 30.712 124.934 47.086 2002 224.215 19.804 30.650 125.410 48.351 2003 226.033 19.714 30.698 126.010 49.611 2004 228.321 19.709 30.892 126.850 50.870 2005 230.879 19.744 31.170 127.846 52.119 2006 233.710 19.813 31.523 129.015 53.358 2007 236.506 19.867 31.866 130.199 54.575 2008 239.624 19.960 32.290 131.590 55.784 2009 243.096 20.092 32.799 133.217 56.988 2010 247.029 20.272 33.414 135.148 58.195 Source:MAP Model Output Files HE53.3 and HER53.3. Variables:HH,HH24,HH25.29, HH30.54,and HH55. TABLE B.5.4.28:SHCA CASE FORECAST NUMBER OF HOUSEHOLDS SERVED Year Single Family Mul tifamily Mobile Homes Duplexes Total Anchorage-Cook Inlet Area 1980 35,473 20,314 8,230 7,486 71,503 1985 57,487 26,204 13,233 8,567 105,492 1990 61,250 27,558 14,017 8,460 111,284 1995 65,723 36,308 15,119 8,333 119,483 2000 69,849 33,196 16,193 8,019 127,256 2005 74,870 35,738 17,493,8,607 136,708 2010 81,469 39,268 19,227 9,403 149,367 Fairbanks-Tanana Valley Area 1980 7,220 5,287 1,189 1,617 15,313 1985 ....10 ,646 6,348 .2,130 ),881 ~1,004 1990 11,521 7,960 2,209 2,375 26,064 1995 13,619 7,841 3,001 2,339 26,800 2000 14,470 7,703 3,302 2,298 27,773 2005 15,791 7,549 3,695 2,252 29,287 2010 16,962 8,049 4,019 2,202 31,231 ] ! j j ! ! ..J 1 1 j 1 1 I I I 1 1 J TABLE B.5.4.29:COMPOSITE CASE FORECAST NUMBER OF HOUSEHOLDS SERVED Year .Single Family Mul tifamily Mobil e Homes Duplexes Total Anchorage-Cook Inlet Area 1980 35,473 20,314 8,230 7,486 71,503 1985 57,487 26,204 13,233 8,567 105,492 1990 61,123 27,468 13,984 8,460 111,035 1995 65,254 30,012 15,007 8,333 118,606 2000 69,431 32,990 16,095 7,970 126,486 2005 74,397 35,505 17,381 8,552 135,835 2010 80,963 39,022 19,107 9,345 148,437 Fairbanks-Tanana Valley Area 1980 7,220 5,287 1,189 1,617 15,313 1985 10,646 6,348 2,130 1,881 21,004 1990 11,458 7,960 2,193 2,375 23,986 1995 13,700 7,841 2,742 2,339 26,621 2000 14,413 7,703 3,172 2,298 27,587 2005 15,630 7,549 3,640 2,252 29,071 2010 16,841 7,975 3,991 2,202 31,008 TABLE B.5.4.30:SHCA CASE FORECAST NUMBER OF VACANT HOUSEHOLDS Year Single Family Multifamily Mobile Homes Duplexes Total Anchorage-Cook Inlet Area 1980 5,089 7,666 1,991 1,463 16,209 1985 632 1,496 146 292 2,566 1990 674 1,488 154 289 2,605 1995 723 1,637 166 284 2,810 2000 768 1,793 178 448 3,187 2005 824 1,930 192 284 3,230 2010 896 2,121 212 310 3,539 Fairbanks-Tanana Valley Area 1980 3,653 3,320 986 895 8,854 1985 118 2,173 24 606 2,921 1990 127 454 24 81 686 1995 150 448 33 80 710 2000 159 440 36 78 714 2005 174 431 41 77 722 2010 187 435 44 75 740 ] .j .J j ! ! ·1 j 1 j ! I j I j ! ! I I TABLE B.5.4.31:COMPOSITE CASE FORECAST NUMBER OF VACANT HOUSEHOLDS Year Single Family Mul tifami ly Mobile Homes Duplexes Total Anchorage-Cook Inlet Area ) I 1980 5,089 .7,666 1,991 1,463 16,209II19856321,496 146 292 2,566 1990 672 1,483 154 289 2,598 1995 718 1,621 165 284 2,788 2000 764 1,782 177 497 3,219 2005 818 1,917 191 282 3,209 2010 891 2,107 210 .308 3,516 Fairbanks-Tanana Valley Area 1980 3,653 3,320 986 895 8,854 1985 118 2,173 24 606 2,921 1990 126 454 24 81 686 1995 151 448 30 80 708 2000 159 440 35 78 712 2005 172 431 40 77 720 2010 185 431 44 75 735 [I I,J TABLE B.5.4.32:SHCA CASE FORECAST RESIDENTIAL ELECTRICITY USE PER HOUSEHOLD (kWh) Before Conservation Adjustment and Fuel Substitution Small Appliances Large Appliances Space Heat Total Fairbanks-Tanana Valley Area Anchorage-Cook Inlet Area 1 J j :] -! ,J 1 I J j .! j I .1 j ! I I 1 11,689 10,7~4 10,551 10,083 10,021 10,298 After Adjustment Total 12,410 12,385 13,995 13,857 1.1:.,051 14,465 11,519 12,118 12,667 13,143 13,657 H,lQli: 14,466 13,699 12,923 12,912 13,033 13,291 13,593 13,908 3,314 3,372 3,471 3,514 3,626 3,~!1 3,791 5,089 4,636 4,569 4,505 4,443 4,407 4,431 5,740 6,180 6,529 6,863 7,165 7,427 1~608 6,501 6,098 6,073 6,178 6,418 6,676 6,887 2,466 2,566 2,666 2,766 2,866 2,966 3~(r66-' 2,110 2,190 2,270 2,350 2,430 2,510 2,590 1980 1985 1990 1995 2000 2005 2010 Year 1980 .1985 1990 1995 2000 2005 :foTd TABLE B.5.4.33:COMPOSITE CASE FORECAST RESIDENTIAL ELECTRICITY USE PER HOUSEHOLD (kWh) Year Before Conservation Adjustment and Fuel Substitution Small Appliances Large Appliances Space Heat Total After Adjustment Total Anchorage-Cook Inlet Area 1980 1985 1990 1995 2000 2005 2010 2,110 2,190 2,270 2,350 2,430 2,510 2,590 6,501 6,098 6,073 6,176 6,419 6,675 6,886 5,089 4,636 4,569 4,504 4,444 4,407 4,431 13,699 12,923 12,911 13,030 13,293 13,592 13,907 11,689 10,790 10,710 10,390 10,079 10,220 Fairbanks-Tanana Valley Area 1980 1985 1990 1995 2000 2005 2010 2,466 2,566 2,666 2,766 2,866 2,966 3,066 5,740 6,180 6,528 6.,860 7,165 7,426 7,609 3,314 3,372 3,471 3,552 3,640 3,714 3,791 11,519 12,118 12,665 13,178 13,671 14,105 14,466 12,410 13,405 14,207 14,279 14,148 14,439 TABLE B.5.4.34:SHCA CASE FORECAST BUSINESS ELECTRICITY USE PER"EMPLOYEE (kWh) 8,672 8,086 8,672 8,086 10,123 8,73~9,153 9,278 10,988 9,377 9,104 10,561 11,968 10,022 9,288 11,322 12,945 10,667 9,077 11 ,204 13,975 11,313 9,310 11,427 15,157 11,958 9,997 12,003 Year 1980 1985 1990 1995 2000 2005 2010 Before Conservation Adjustment and Fuel Substitution Anchorage-Cook Fairbanks-Tanana Inlet Area Valley Area After Adjustments Anchorage-Cook Fairbanks-Tanana Inlet Area Valley Area ] '] I ] I j I J ~J 1 J j 1 1 l ,.j ] 1 J TABLE B.5.4.35:C()MPOSIr~CASE FORECAST BUSINESS ELECTRICITY USE PER EMPLOYEE (kWh) Year Before Conservation Adjustment and Fuel Substitution Anchorage-Cook Fairbanks-Tanana Inlet Area Valley Area After Adjustments Anchorage-Cook Fairbanks-Tanana Inlet Area Valley Area 1980 1985 1990 1995 2000 2005 2010 8,672 8,086 8,672 8,086 10,123 8,731 9,153 9,278 10,973 9,377 9,089 10,557 11,940 10,022 9,450 11,473 12,927 10,667 8,833 11 ,632 13,954 11 ,313 9,417 11,587 15,138 11,958 9,996 11,989 TABLE B.5.4.36:SHCA CASE FORECAST SUMMARY OF PRICE EFFECTS (GWh) Anchorage-Cook Inlet Area Fairbanks-Tanana Valley Area Residehtial Sector I IBusiness Sector I Residential Sector Business SectorI, Own-Price Cross-Price 9wri-Price Cross-Price Own-Price Cross-Price Own-Price Cross-Price Year Reduction Reduction Reduction Reduction,Reduction Reduction Reduction Reduction I i ·1985 137.6 -7.4 138.4 2.5 9.2 -3.0 22.4 -2.4 1990 257.1 -21.4 :282.0 0.0 23.7 -5.8 51.0 -4.4 1995 376.2 -79.7 i 449.2 -20.8 26.3 -3.5 56.5 -2.7 2000 556.9 -148.6 i 707.0 -56.4 1.6 4.0 20.6 2.2 2005 708.4 -220.2 933.9 -101.9 21.5 -20.0 -3.5 8.8 2010 854.0 -314.8 11176.9 -166.6 0.6 -0.6 -12.0 14.1 '-----L'---.~ TABLE B.5.4.37:COMPOSITE CASE FORECAST SUMMARY OF PRICE EFFECTS (GWh) Year Anchorage-Cook Inlet Area Resiaentia 1 Sector -BusIness Sector Own-Price Cross-Price Own-Price Cross-Price Reduction Reduction Reduction Reduction Fairbanks-Tanana Resicren:tIal Sector Own-Price Cross-Price Reduction Reduction Valley Area Business Sector Own-Price Cross-Price Reduction Reduction 19851 137.6 -7.4 138.4 2.5 9.2 -3.0 22.4 -2.4 19901 256.4 -20.9 279.9 0.5 23.6 -5.9 50.6 -4.4 19951 351.6 -76.5 412.9 -19.1 30.8 -3.4 62.2 -2.7 20001 505.2 -138.0 634.6 -50.0 13.7 3.1 39.1 1.5 20051 671.5 -194.4 889.6 -85.8 -7.6 8.8 5.5 6.6 20101 811.0 -263.5 1,135.6 -135.0 0.4 0.4 -9.3 10.8 TA BLE B.5 .4.38 :SHCA CASE FORECAST BREAKDOWN OF ELECTRICITY REQUIREMENTS ANCHORAGE-COOK INLET AREA (GWh) Residential Business Mi see 11aneou s Indust./Military Total Year Requirements Requirements Requirements Requirements Requirements 1985 1,233 1,329 28 124 2,715 1990 1,201 1,363 28 192 2,784 1995 1,261 1,484 30 208 2,983 2000 1,283 1,527 31 238 3,079 2005 1,370 1,660 33 273 3,336 2010 1,538 1,957 38 315 3,848 :I .J j ] 1 '.1 ] .1 J 'I J J TABLE B.5.4.39:SHCA CASE FORECAST BREAKDOWN OF ELECTRICITY REQUIREMENTS FAIRBANKS-TANANA VALLEY AREA (GWh) Residential Business Miscellaneous Indust./Military Total Year Requirements Requirements Requirements Requirements Requirements I 1985 261 340 7 0 608,J 1990 323 416 8 50 797 1995 375 468 9 50 902 2000 385 475 9 50 919 2005 412 506 10 50 978 2010 452 569 11 50 1,081 j TABLE B.5.4.40:COMPOSITE CASE FORECAST BREAKDOWN OF ELECTRICITY REQUIREMENTS ANCHORAGE-COOK INLET AREA (GWh) Year Residential Requirements Business Requirements Miscellaneous Requirements Indust./Mi1itary Total Requirements Requirements t "I r ) 1985 °1 ,233 1,329 28 124 2,715 1990 1,198 1,353 28 192 2,770 1995 1,270 1,494 30 208 3,003 2000 1,314 1,577 31 238 3,160 2005 1,369 1,668 33 273 3,344 2010 1,517 1,946 38 315 3,815 I ] .] ) 1 ] I .I j ] I ( 1 l TABLE B.5.4.41:COMPOSITE CASE FORECAST BREAKDOWN OF ELECTRICITY REQUIREMENTS FAIRBANKS-TANANA VALLEY AREA (GWh) Residential Business Mi see llaneou s Indust./Military Total Year Requirements Requ irement s Requirements Requirements Requirements 1985 261 340 7 0 608 1990 322 413 8 50 793 1995 378 470 9 50 907 2000 394 490 10 50 943 2005 411 510 10 50 981 2010 448 565 11 50 1,073 TABLE B.5.4.42:SHCA CASE END USE FORECAST PROJECTED PEAK AND ENERGY DEMAND Anchorage-Cook Fairbanks-Tanana Inlet Area Valley Area Total System Area Energy Peak Energy Peak Energy Peak at 60%Load Year (GWh)(MW)(GWh)(MW)(GWh)Factor (MW) 1985 2,715 517 608 116 3,322 632 1990 2,784 530 797 152 3,580 681 1995 2,983 568 902 172 3,885 739 2000 3,079 586 919 175 3,998 761 2005 3,336 635 978 186 4,314 821 2010 3,848 732 1,081 206 4,930 938 1 .1' \) TABLE B.5.4.43:COMPOSITE CASE END USE FORECAST PROJECTED PEAK AND ENERGY DEMAND Anchorage-Cook Fairbanks-Tanana Inlet Area Valley Area Total System Area Energy Peak Energy Peak Energy Peak at 60%Load Year (GWh)(MW)(GWh)(MW)(GWh)Factor (MW) 1985 2,715 517 608 116 3,322 632 1990 2,770 527 793 151 3,563 678 1995 3,003 571 907 173 3,910 744 2000 3,160 601 943 179 4,104 781 2005 3,344 636 981 187 4,325 823 2010 3,815 726 1,073 204 4,889 930 TABLE B.5.4 .44:~ARTON CASE FDRE'CAST SUMMARY OF INPUT AND OUTPUT DATA Item Description World Oil Price (1985$/qbl~ Energy Price Used by RED,(i1980$) Heating Fuel Oil-Anchdrage ($/MMBtu)!i Natural Gas -Anchorage ($/MMBtu)r State Petroleum Revenues~/ (Million Nominal $) Production Taxes Royalty Fees State General Fund Expe~ditures (Mill ion Nominal $)i' State Population State Employment Railbe1t Population Railbelt Employment Rail bel t Total Number ofl Households ! RailbeltElectricity Co~sumption (GWh)! Anchor,age Fairbanks Total I Rail bel t Peak Demand (MWI) I I 1985 27.10 6.45 2.10 1,372 1,372 3,665 536,525 269,087 381,264 181,885 134,300 2,714 608 3,322 632 1990 24.80 5.90 2.35 1,113 1,556 3,806 559,621 278,012 394,631 185,257 140,751 2,721 786 3,507 667 1995 27.60 6.58 3.65 1,033 1,622 4,701 583,589 293,298 410,458 192,530 148,302 2,946 893 3,838 730 2000 31.30 7.45 4.05 720 1,423 4,944 618,952 313,683 431,301 206,302 157,679 3,260 971 4,231 805 2005 35.10 8.35 4.46 601 1,253 5,335 645,298 320,030 460,071 218,848 168,895 3,576 1,047 4,623 880 2010 40.70 9.68 5.08 751 1,364 6,379 688,969 '344,017 499,187 240,312 183,964 3,964 1,117 5,081 967 i/Petroleum revenue s alIso include corporaite income taxes,oil and gas property taxes, lease bonuses,rentsl,~nd federal share:d royal ties. I ,--_..~_._-<: TABLE B.5.4.45:RESULTS OF RED MODEL SENSITIVITY TEST ON APPLIANCE SATURATIONS Total Electricity Requirements Without Large Industrial 1990 2000 2010 (GWh)(GWh)(GWh) Anchorage-Cook Inlet Area Maxim tnnl/ 25%GE Mean 50%GE 75%GE Minimtnn Std Dev Test Case Fairbanks-Tanana Valley Area Maximtnnl/ 25%GE Mean 50%GE 75%GE Minimtnn Std Dev Test Case 2,681 2,673 2,670 2,669 2,667 2,663 4.82 2,673 721 720 719 719 718 717 1.0 719 3,186 3,179 3,173 3,173 3,167 3,164 6.8 3,174 897 896 894 896 894 892 1.4 895 3,918 3,910 3,904 3,905 3,900 3,890 7.4 3,901 1,117 1,116 1,114 1,114 1,113 1,.1 10 2.0 1,113 1/Maximtnn =maximtnn simulation value. 25%GE =25 percent of simulation values were greater than or equal to table value. Mean =mean value of all simulations. 50%GE =50 percent of simulation values were greater than or equal to table val ue. 75%GE =75 percent of simulation values were equal to or greater than table value. Minimtnn =minimtnn simulation value. TABLE B.5.4.46:RESULTS OF RED MODEL SENSITIVITY TEST ON BUSINESS SECTOR CONSUMPTION INTENSITYll Total Electricity Requirements Without Large Industrial 1990 2000 2010 (GWh )(GWh )(GWh ) .\ ] 775 965 1,203 729 907 1,129 712 886 1,102 712 8.87 1,103 696 867 1,078 §"§l 823 ...._1,02!L-"------._._. 32.0 40.0 51.4 719 895 1,113 3,180 3,804 4,717 2,826 3,364 4,147 2,653 3,149 3,870 2,545 3,016 3,697 2,119 2,488 3,019 2,663 3,164 3,890 276.32 342.7 442.2 2,673 ;-,3,174 3,901TestCase Anchorage-Cook Inlet Area Maximuml.l 25%GE Mean 50%GE 75%GE Minimum Std Dev Test Case Fairbanks-Tanana Valley Area Maximumll 25%GE Mean 50%GE 75%GE "Minimum Std Dev II Coefficient of demand per square foot. ......2"./··MaxinftIlll=·tnaximumsitnuL!rtion·va·luEf;·_··········- ...--·-25-%-@E-=--25--per-cen·t-of--simul·a·tion-va-l-ues-were-·grea·ter-than-or-eq·ua-l-·. to table val ue. Mean =mean value of all simulations. 50%GE =50 percent of simulation values were greater than or equal to table value. 75%GE =75 percent of simulation values were equal to or greater than table value. Minimum =minimum simulation value. 1 i 1 J .J J TABLE B.5.4.47:RESULTS OF RED MODEL SENSITIVITY TEST ON OWN PRICE ELASTICITIES Total Electricity Requirements Without Large Industrial 1990 2000 2010 (GWh)(GWh)(GWh) Anchorage-Cook Inlet Area Max im t.m11/2,720 3,283 4,093 25%GE 2,641 3,138 3,843 Mean 2,621 3,077 3,745 50%GE 2,635 3,072 3,726 75%GE 2,591 3,021 3,659 Minimt.m1 2,528 2,903 3,453 Std Dev 50.82 96.2 160.6 Test Case 2,673 3,174 3,901 Fairbanks-Tanana Valley Area Max im t.m11/736 911 1,137 25%GE 729 905 1,128 Mean 724 900 1,117 50%GE 724 902 1,119 75%GE 720 894 1,108 Minimt.m1 713 887 1,091 i Std Dev 6.0 7.1 13.3L Test Case 719 895 1,113 1/Maximt.m1 =maximt.m1 simulation value. 25%GE =25 percent of simulation values were greater than or equal to table value. Mean =mean value of all simulations. 50%GE =50 percent of simulation values were greater than or equal to table val ue. 75%GE =75 percent of simulation values were equal to or greater than table value. Minimt.m1 =minimt.m1 simu1a tion value. TABLE B.5.4.48:RESULTS OF RED MODEL SENSITIVITY TEST ON CROSS PRICE ELASTICITIES TOTAL ELECTRICITY REQUIREMENTS WITHOUT LARGE INDUSTRIAL (Page 1 of 2) 2,690 3,183 3,965 2,676 3,178 3,931 2,672 3,175 3,907 2,672 3,175 3,911 2,666 3,172 3,893 2,656 3,165 3,838 9.5 5.1 36.0 2,673 3,174 3,901 B.Gas Cross-Price Elasticities _..----Z,-699--~--------3~-279----------~--~_;TOT 2,684 3,219 3,981 2,675 3,180 3,911 2,676 3,184 3,914 2,670 3,162 3,870 2,638 3,024 3,649 15.8 64.7 120.6 723 898 1,132 720 896 1,122 718 895 1,115 719 896 1,116 711 895 -l",cU-L~- 714 892 1,095 2.5 1.5 10 .4 719 895 1,113 A.0.1 Cross-Price Elasticities Anchorage-Cook Inlet Area Maximuml/ 25%GE Mean 50%GE 75%GE Minimum Std Dev Test Case Fairbanks-Tanana Valley Area Maximum1 / 25%GE Mean 50%GE 'Z5_%__GE~- Minimum Std Dev Test Case Anchorage-Cook Inlet Area ------------Maximuml:l ------ 25%GE Mean 50%GE 75%GE Minimum Std Dev Test Case 1990 (GWh) 2,673 2000 (GWh) 3,174 2010 (GWh) 3,901 I ) J I ~4 ~l " f 1 \ .I I I I l I } TABLE B.5.4.48 (Page 2 of 2) 1990 2000 2010 (GWh)(GWh)(GWh) Fairbanks-Tanana Valley Area Maximuml/726 896 1,134 25%GE 720 896 1,122 Mean 719 895 1.,114 50%GE 719 895 1,115 75%GE 717 895 1,110 Minimum 713 891 1,086 Std Dev 3.4 1.6 12.7 Test Case 719 895 1,113 TABLE B.5.4.49:RESULTS OF RED MODEL SENSITIVITY TEST ON ANNUAL LOAD FACTOR TOTAL ELECTRICITY REQUIREMENTS WITHOUT LARGE INDUSTRIAL 1990 (MW) 2000 (MW) 2010 (MW) Anchorage-Cook Inlet Area Maximuml l 25%GE Mean 50%GE 75%GE Minimum Std Dev Test Case Fairbanks-Tanana Valley Area Maximumll 25%GE Mean 50%GE 75%GE Minimum Std Dev Test Case 620 733 890 604 695 843 560 646 790 556 648 795 531 604 754 489 573 708 40.4 50.2 49.5 548 650 799 196 241 297 184 223 279 171 207 254 177 210 253 156 195 234 146 174 217 16.1 19.1 24.5 149 186 231 } J J j I 1 II Maximum =maximum simulation value. 25%GE =25 percent of simulation values were greater than or equal to table value. Mean =mean value of all simulations. 50%GE =50 percent of simulation values~t=J:c:gJ:_E!Cl.t§J:'~I:1Ci_t1_()["c:gIJCl.Lto-tabTevaTue:---- -----------.-.------.----~-~.-.----------~------------7-5"%~GE~=--75 per~cent "-o-f----s~imu-rat "foii .val-u es-were---equ a Y---EQ_···or-----grea t ei----------··--"-_. than table value. Minimum =minimum simulation value.I j 1 1 Ii TABLE B.5.4.50:LIST OF PREVIOUS RAIL BELT PEAK AND ENERGY DEMAND FORECASTS (MEDIUM SCENARIO) ISER Battelle Reference Case Utility 1980 Forecastl/1981 Forecas d./Forecastl/1985 Forecast!!./ Peak Energy Peak Energy Peak Energy Peak Energy Demand Demand Demand Demand Demand Demand Demand Demand Year (MW)(GWh)(MW)(GWh)(MW)(GWh)(MW)(GWh) 1985 685 3,610 1990 735 4,030 892 4,456 777 3,737 869 4,584 1995 934 5,170 983 4,922 868 4,171 971 5,135 2000 1,175 6,430 1,084 5,469 945 4,542 1,085 5,7252./ 2005 1,380 7,530 1,270 6,428 1,059 5,093 NA NA 2010 1,635 8,940 1,537 7,791 1,217 5,858 NA NA 1/Acres American 1982,Volume 1,Table 5.6.Includes 30 percent of military loads,and excludes industrial self-supplied electricity. 2J Acres American 1982,Volume 1,Table 5.7.Excludes military and industrial self-supplied electricity. 3J APA 1983,Table B.117.Excludes 30 percent of military loads,and excludes industrial self-supplied electricity. ±/APA 1985,Table 1. i/Energy and peak demand in the year 2000 were computed by extrapolation,based on the annual growth rate in the last year of each utility's forecast period. Note:The ISER,Battelle,and Reference Case forecasts are for end-use demand, and should be increased for transmission and distribution losses.Net generation =sales/(l-l). 1 OJ I J -] 1 ·1 FIGURES 1 j j ] 1 I ALASKA LOCATION MAP LEGEND "PROPOSED .DAM SITES .",: LOCATION MAP 20 ! FIGURE 8.1./.1 I I ! : !: ~AMSITES PR9~OSED BY OTH~RS i' FIGURE 8.1.1.2 I LEGENDI ! TYONEI ttl DAMSITE .' : 8; ~.:15 ~~.,~t, SCALE IN MILES .........._-_._--------._--~--~'--~_..---"._---"---' COMPUTER MODELS TO DETERMINE LEAST COST DAM COMBINATIONS DATA ON DIFFERENT THERMAL GENERATING SOURCES , ---II COMPUTER MODELS I TO EVALUATE -POWER AND ENERGY YIELDS -SYSTEMWIDE ECONOMICS ENGINEERING LAYOUT AND I , COST STUDIES SCREEN PREWOUS STUQIES AND FIEU RECO ADDITIONAL SITES PORTAGE CREEK DIS'HIGH DEVIL CANYON DIS WATANA GOLD CREEK DEVI L CANYON HIGH DEVIL CAN'rON DEVIL CREEK WATANA SUSITNA m VEE MACLAREN DENALI BUTTE CREEK TYONE CRITERIA DEVIL CANYON OBJECTIVE WATANA I DEVIL ECONOMICS HIGH DEVIL ECONOMIC CANYON ENVIRONMENTAL CANYO~HIGH DEVIL ALTERNATIVE WATANA CANYON I VEE SITES SUSITNA]I[HIGH DEVIL ENERGY VEE CANYON /WATANA CONTRIBUTION MACLAREN '------.....DENALI CRITERIA ECONOMIC ENVIRONMENTAL SOCIAL ENERGY CONTRIBUTION WATANA I DEVIL' CANYON PLUS THERMAL SUSITNA BASIN PLAN FORMULATION ·AND SELECTION PROCESS FIGURE 8.1.2.1 l .! -j I ] I ,) (J) IJJ I--(J) IJJ>-~.za:: IJJ !J <[ ::I:_.c>__....._~-_.._~...__._--_._~_..-:J oa:: ::I:.... UJ ..J-l.Lo......._...._.....Q;- ......_..~..~.a.~~_.__.._._.. g N -oo It) oI-+--r--.,...--,!!! oo ~ o 11--+--1 ~ -oo It) Na:: 1&.1>ii z 1&.1 ~ ..J ~ 2: --------0-~II-+--i ~ N o33A..........~-l 0 N ........-~. 1lI "NJ.ISnS ..,..... a:: 1&.1> ii: 1&.1 Z ~ 1-.ooo N ----------- 15>ii: cs: Z I- 1&.1 % (I)o -...~-1--.---.....-.--...----..-~- oo GOLD CREEK GOLD CREEK I{l!\jl\ll\\\'\\i\\\\:\\\\i\\\\\\\\j\\\~\\\i\\\ OLSON DEVIL .CANYON HIGH IJEVIL CANYON DEVIL CREEK WATANA I SUSITNAm/VEE MACLAREN I PENAL!BUTTE CREEK TYONE OLSpN IlIllIltlflil DEVIL CANYON '11'1[111!lt~ll.llill HIGH DEVIL CANYON ~lilllIIlIL'lt'lli.JII DEVIL CREEK 1111\1111"1\111; WATANA il!ill\IIIII!II~«li\tl LEGEND COMIPATIBLE ALTERNATIVES SUSITNA m '1I111111'(f?I~III~t~il V EE ~~j;~{lll~~lfti,~$.l{(lfr~i' MUTI!JALLY EXCLUSIVE ALTERNATIVES •DAM IN COLUMN IS MUTUALLY EXCLUSIVE IF FULLrl11'''''''''"'II SUPPLY LEVEL OF DAM IN ROW EXCEEDS THIS VALUE-FT.·\;··j;~;~l:~:;'I~;~·::\··j:\·VALUE IN BRACKET REFERS TO APPROXIMATE DAM HEIGHT. MACLAREN 111111 DENALI Ili1'llIilltilt1~I(t BUTIE CREEK f~~lfif1~~~;~~~ TYONE MUTUALLY EXCLUSIVE DEVELOPMENT ALTERNATIVES FIGURE B.I.3.2 IIilOO r - FIGURE 8.1.3. !lon 111..1 DA ,••'u.ul'a..nl .. ..IL'coonl'TUAL PWo.Ja:T LA'rOU'f......-It PrHt CO."...,.IO.or....,.....,TIV.IITII NYaL.Of'IIII.'"a."y 1000 IlIOO IlaTlOll...III naT 800 8PILblIfAY PROfIL!......,. POWER MCILITIU PROEILl: ICALI'. ITllTlOlll"""'flIT o o ~. o -tOO lIOO FlIT IC&Ut A ...........;;;;;;pjo100400 FlIT I PiIPd SECTION DlRY DAM OCALf::• "'L1..Y~II1lIUC"'" ..«I.4!f ""ElL uouonao ...·IIt. ",00 r--f----=~~-=::::::------------------- l;j 1400 r--'''-::=;;;;:::::~~::~1100 i.':V":.J~~011 II IlOO f-------~!IIlO;;~-----:~"7--..:::::"'-.._-8j 1100 r----------....::::l;;:,,~__...I.~~t!,...:.::"'-=7"'::::::~~:...!!!!..!!!!-!!!;:!:! ~lOCO ~==================~~~;;~~~~~;~~~:w:~~ IlOO ~-::-NO.,.,.........:Jt::'-i \.~---r_~........loo~I \\::::s ~..........'/a ,aoo ...PU'IJI d _ 1000 I I ApUi;«-.:7.c ..~-J Jf !Pnl'!:~."'l\.................. ..-- -1-.._'=-=-:.=-,.,....--VUlT_.QROlJa)IURMCa .-1--=..::::::;:;::"'-- .............. A ~-7t:oIllA.~cun:........... IIlTAXlJ ~/~IW.~,gwT ~,AVI"AIC ... '\."\.~~,.,L_ IL." l-, CotmJlUCTlOll AllfT __~W~vJl :i rl-l2lI'llIA.co-.-.IJ!IID TUICIIIUI \'", COIIC1lIEJI:I'LIlI J m'iEtJa.L,...T.I SHUT'-_0l.D.-..... 1100 I.n"n :;;>',c .J 7f/j't-1/~~\:~_,:"s ::f .'.nlL~S: i ROO .....:~.• B 1100 I ~ua~F7 ,..\\1.=s:;]1-------- ! 1000 1000 .i- 1I 1100- i: lOCO 100.00 HYDRO DEVELOPMENT FILL DAMANYONDEVIL BECTION,A-a ICALa:::•, II1EIlIIOQI lIURI'-::l.\/£.f jl ,.,00._:>;> LONGITUDINAL SECTION THRU \IOE bAM lCAU::•' GENERAL ARRANGEMENI 1CAU::.. 5 IeOOL-----------7 ..:::Ti<::...-- ;IllOOL---==:::---;-7~-t--- 8 14OOJ.:::::-==-i.~:::::==='fM--";:::oo~.-mGACiI5IIOOL----~:::-~-,-+.S!!!!f!!J&..--­a _L--..L..:..---~"'"'_=----- ===:-:='--:i:-- i eoo L \;:;:.e=:.=:.--==~= "'00 •-~I _.,--I"..:::::::;, t ::f ~§§===-e¥ii .,~w~ II 1100!=t----=··...=·""'=..:.r...=...:......=--~.---¥\;c--~--?-,f-7"Z741ri;.-[==+f~=-~·-="-=- IOO~-"',-,-7~~Ill. --'-0-~-_.'------.:......r.: ~n.'::.VER 1400 15'00..,-.'''00.0.00 1l~21'0lA.COHCREU.LND tl.Ir«NlELi \..GATEIIURGI IHAFT SECTION THRU DAU StALE t 8 _IIAX. V.L.£L..ftOO.... 10.00 UhOO ITATIOHIIrI&IN FUT fQ.WER FACILITIE8 PROfILE: &cALI'. ~I.I'~ II ---I,-----'L -:r- USL1 'HAFTS ..---<,[XtiTING GROUND IUftFaCI :I .~. II ~TRAHUORIliER AND DRA""-- ::/TUeE GATI a.u.u:RY -.........''''-... ''-... COHCIlI!TI I'UIa uoo 2100 :ססoo 1100 Otoo 15.00 INTAK! CONSTRUCTION ADiT· ",. Dlm"l ROCK UVIL ,,-7Al1.l1ATI. lL'4IlO -.- 1100 .000 ..Ill(\() ::l..1800 !! ~1700 i '800 ~'1lO0 1400 ..tlltOO.. ~;'000~~gl~~~.tIOO ~ ---5 1800 L~:w Itoo ~=:OC~-;~--'~.....-~~=~r.ooo SPiLLWA'-""'"~boo~ ....A GENERAL ARRAHGEUENT DCAL.E·A =f~~~~ ltllOll 110O ..lOCO......11'00 !! ","""a;1&00a- .JOe> ~ FIGUREB.l.3fJ 0 too loonEY IIC>L.<C ;= 0 IO<l _ncr IlCAU •i3 0 IlOO .JgOORfiSCALEA; NOTE -;:;'ii DIIAVI.'ILLU'Ta,nn "...fLU.I••..,co..crflTUAt......OJICT LAY'OUf ..,....ltltl PI>lit '0.......'10..or .w..nb.Tlvl alTI D«Y1L.Dp':dI_n 0"" SECTION A-A 'CALI'e WATANA HYDRO DEVELOPMENT FILL DAM!!J'ptt.!!!EOfPr'H1!!~!i!itliijM..!6£~C~T~I~O:!l:'!!!l!!I~:g==LQNGIWp'HAL 1lW.~'.!' :..-0.0 IOt-OO 15+00 1:01'00 IrtATJOttllKl 11::nET ilPILlV/AY PROfIlE ecAU:'. 0000 IllOO 1400 __I /C«ESTELr.Dl1POl~~~':,."':DILINE /-Jl&fL. ~~~---.:..-=::::::-..../£JliCAVATICMl 'OR COla -:-............~..--::..-,".-....,~.,/KOIlllCll_E ~-............:;,---~-~~-??/ =======iF===-,'"_~.('''''IiIllUL__~-;;.-:;::;::::::-.-=====if";'== ",..........Iy\\.#--/"""'7 ........'U./\~\/"/c;,==_== ./''I\."'----"/1 :, ,/II ......._--------===:::.::!.!::== 1100 ..1:000 ==..lOCO..i- ~1700 ~NOO '- FIGURE 8,1.3.5 ---. o lOG _PeT IeALI I D 100 lIDO PUT ICALI A lIort: -;;;q 0 '•••L.LJJlra..TI...-,..'LU.,.,.C:OItCIPTuaL ,.~"'LAYOUT.......ro IIOCt C:O"""••SOM '"AU'lb..TIYI IITa KYlLO"•••TI 0&" ._-- POWER FACfUTIES PROFILE' IeALI:I SECTfOfl THRIt DAM SCALE:I M 'V'-- FILL D ---- DOD- w.LlLlOOO ./'"""IIT 'NT_lIT_III1_'ftrlL.IOIOliO=--.-·'-'__~IXlITIlOl -_ 1.00 I 4-1,'DL&CONCR!1"&-=------ lOOO fIT !~==::.....==:/UHED T\M<!1.I ..v:<11 il ':\/"'.....11 COIICIIatt PUJI EIlOO ,'-\.r="'~..~APY ·lICO !nOD t'1T"=l'lITA!'I II LS.ITIIA.COIlCMTI ~I'OWI_-t-lrllULT_L ~AVIJIAH ___I'...00 UHED -...'I IITAOUlI.,~,IL 14".5 '~-~.....1POUl \ '"'-."1 -COHIlOUCTlOII AD'~__\\.U'''''J IV _.'<:_.__...J...."..-/-/1100 t?f'L!fftC.r-.a&ft I \'~.......-:;.7 £/J \~..._•............'-,_, -------,.....----~tl=l·•.,~rt:'CRm 111..1118 DOOI':.-'ti'r;::··.1100 #"",C ,~.... •.IWl.ILIMO ~~n',I,~~'"C ....IIl ••U.Ii .aoo ~IOOO],us ~(Jj:J fu.-cr _"/ II'=1 Z~~;e>~~~t·=;;:\..~;::::-__._ I 1100 -=-==10'._.w!!._~__"""~......"I -L...--_~1\1..IIl!O :7 'j S'TAGED rJ'P _,0 @ lIDO,.1 ~T "~D&II UITAR &J z:tOO _0 - 0 _..-----------------:--.--:--.I ,--.------ t ~-::."::'::---...!!:!!!!....l r~f~=~ITA ..11 ~_..-_-_-'oJ~1100 ...................j i '_./,.-*"" l!IlIllO I'--......::..~.~;::-:/I:.:!'-~~~~~~~_;;"~"''::--'"2.:~c=-.:-ii"...-.. 2 11'00 ..---~,~~;:/'Iii _1lIl1G*M.1110010,__-----\,:'\.«/'"/1IIOiIT Ul.LllllUJ \'.'"I ///<::-'F;::-~-:'I 1IlOO ."\\........l~-L-/,'~II -X._---+-_l __~~=====db= LONGITUDINAL I SEhfON THRU \.01'DAM ICAUI'II I I01'"eROU:ID IUIIJfiICI 1IOfDIk.awe ,I ....01'IPlWlAY"f!".L.lrUof :DOll \__.•~.o.T.;:--.!.._I rEllI$TIHIlll'IOUHDIUIIl'l\CltOIl 1200 •~.-----'---..;.------,-~..........:../ItDr1 8M 011 IPIu.Y '_-;:\~_----.a..IHD ~':-:::...:...........~ 2100 n.zooo..,~____........'"":,--~..-._:.~ ,IOOD ....1.---.."""'~wiciL l_mlATE I I,',...:-::::'::::-.~~ ,'IT~II ~....·.........V·to 1000 -:.-~\lOO '"\."\r l·lI/l'D'"fDHCll£TI UH(D'l\lIIIIU.lI ""'"~-.....,=.-..-CllOO....flIlIJCT\lfC'l>.~""'''''\I I -l\,."''-'~lx,mHI 1ll0UH0 .......,.0111=,noD "un IU at'IALLa' !J lloo l I I.~-/"rAIlER TlULWATllla:.:oo .T~'II&l'lLLWAY·iarA~on./"""",---__-._.11-1 • .,.1--~-..r-..)..,..-L---'---, "00 ',,...... '1800',I I ,!I ,I'I I I I I " I I I I I ,.I I I -ODD 0 100 1000 I ,aDO lOOD UDD'100D 11100 4000 I T 1 llT.nOHItJl IN 'EET sJLWAJ PROFILE !.C~"WATANA 2000lOIXl "---to, 111111( 1IlOO SECTION THRU DAM lCALI:. IlOO IDOO ITATIOIOlIll 1M FUT POWER FACILITIES PROfILE .IeALE:. nool :;;;;;/....,:PlLRR L}I ~tIYIUWI \~fll I€8 ..........._ r .._a_'.\...........( -=#{I \~..............IIL}I \_...1_.._1100 :;>'••N_....... 10001 ........c .N'~}9"~.t't~~~............---::U IlOO IlOO....l400....n 1100 BIlOO..~: IOO L IICO 1~1 7Z~??'I ~.. CllUTIl.-Il'1Il' ATc.OPDAIIf GENERAL ARRAN9EMENT DCAUt:. WIlIIOCIl _IU' ~MOUND aRPlllCE ~fOflc:Oll£ I I 'kod!'II I IlCO :0 ......~ l!"""~""";::=IKlO~ "l'lOtl hOKelTUDINAl SECTION THRU !I Of DAM ICALI'• w -iCOO ""'"at"n<*I••IN 'UT SPILLWAY PROfILES IW.!:'g 400 eooriET IICAUE A 0 teo 'IQO'EET1Il:oU.&.- !!OTt: -;:;;t'i "'L.l..WT1I.4TQ A "'LUUU'"CQlIC'PTU.lL.""""".C'f L&T'OUrPtII"NJIfD lOa co....~ew .tLn.""TtVI 11'1 DrvlLoPWWTI HLY HIGH DEVIL CANYON HYDRO DEV~LOPMENT FIGURE 8.1.3.6 FIGURE B.1.3.7 lIOn: ~:~,:::;I~W=~CT L.MOU1' ~POI co ......1aotf OP ALTI....n".&1'1 OCYILOf'II!PTa "LY SECllON THRU DAM 1eAL1'• aTATlONHQ Itl '££T SPILLWAY PROFILE ICAlE.D .L __.-.1 .L L'I ,~I , , I I~,!!!~! ! •o .~:;:-~ !lIliES PROfiLEPOWEREAelCue,8 1400[===-----:::::t:::----;nw:~~~===_--------~;;.;;;;;;;-;;;;::;;;;-===----------II~U'ITIIIO _IIlIlfilQl 1;;1100 .~--1'--- ~.IOO " •"TAICI!IOOO !,lOOt=--'-------;;;;;;;;;;~;=:::::-~~-II,..:,bfqr~---J-+--.:::::.::::::~:-r.::--'--J=G1000 COHlI11JC11OH AOIT 1700 CONal!LUQ i-r.1100 1 ~I::=<:.-;/z/fflffij;;>s. 7':7..'"'"'-FUIA ............. NORIW....u .•L. I~~·ts40 .:."..1Pl,..,CClNl'"RQ.Il1"IlUC7\R..../'__...u.-...1 ......'"-HElL.9&I11 . I~...J;....~-.__/f:=~~ ..1100 __:--..L eUOO ~--_./~'r.~~-rJ..AfLy .1100 ~-~::t~::::::::"'__ !lOOO ~..::--_____1l..1Ol0 !1100 '"",;:::.l -~...::L. 1800 SUSITNA m HYDRO'DEVELOPMENT -----_...--.... LO' '-.I ,,:c..--I~--~_..------r GEH£RAL ARRANGEU~HI i ,.aCALE1A·I I I iCeITEL••NO A~4.~DAU - ---- -""-r--- llilOO ~-:-~.SCALf A Q ~eoo2.000 !! ;;11800 ICALI 8 0 ZOO 400 .....,L..--------~_:_-'----....:::::::::::;;;;:~~+_-___:~;:L--~;z:i!iYJlL:::~-----'- ~ 1- IllOO uoo ~ ....-.-._-----'-------==:~.--' --~--- ® 1IlOO1000100 STATIONINQ IN fErr o CONSTRLJCTIO AD, I»--..;;.~/1~18iDIA.TUHN;~LI !I "''''V'"!~~~S!~~~£_~~.N~~" 1400 1100..1100to.... 2100 I INTAK!ill ~1000 ~IQ) '100 L..-.... ..aDD GENERAL ARRANGEMENT .CALf A HORliAL WAX. W.L.EL.Z!50 ~~----~\1/I~,\2400 tloo ~2200 !!1100 ~2000 !c ,acei:; SADOLI DA".. W 1000 1100 [n fiNE 'ILTER '100 GROUT CURTAiN -""'"\---'0!lAIH SECTION THRU pAM BCALI • POWER FACILITIES PROFILE lSe ....L!:8 ILONGITUDINAL SECTION THOU t OF MAIN DAM SCALI. ~fttT ~O,ttTo IlCALt.! o_La A !!m. nUl OA"ILLUITaan:1 • ..'LI.I COIICIPTII4L "0"",,LAYOUT AttN_ID JIt.l.-CO"'''.'I(').011 &.LTIb.TIVI alTI M'VILO;t1II.TI ~y 1100'000oDOD ITATIOHINa IN frET SPILLWAY PRQf.Il..& leAL!8 100 ~~LI~Y::~___/ .i:1:r~:;.;~~~~:~::"~A; /"_/--.'."'../IJPILLWAY CONTROL ITRUCTURI-(,,'x ~·'~3al••4O"H 'IXID WHI£L 8ATEI--,"~g:lrl~N:.~~U~.'p~~t:i~.-~./.."-. ~'----r:VERAG!tAlLWATIR'-ILlat5 ~.....J::;-._---.....-- _.~._--._-- tlOO 1IlOO 1400 210C..E UOO !1100 ~ZOOO I I~~ W .aoo BEDROCK IUltFACI GRAVITY WALLCAElrIL.IISO tACO..noo toto t200.. !!2100..aooo2 E ,too......1000 VEE HYDRO DEVELOPMENT FIGURE 8.1.3.8 .pi> ...---- tJIP ~~~N/=;:~I -.'&32''U(ID WHIlL aATI' )II / L__--J/ 1IOTe: TNii oa..w••'luurntATU A"fLU'IURY tcMICllr'uA""JioaMCT LA1'OUT.........0 1011 COIlU"ll ••,oa O{I Al.l'••••nlvl IIYI OCVCLOfI'IIhf'oa.., J!I.!j!!::J. 8£II!RAL ARRANGEMENT ICAL!'. ~8!LUIOUTH ('_f:.,TRAJHU.eQ _~N8,..0IVI1ltHlN . .t-".ac-~~. SECTION D-D lCA!-!'C 0 100 100 fI£T lIC.tLI·c ! 0 too 400 nIT 1CAI.I·8 ! 0 400 BOO nIT lCo\IJ!'A i ~~.;::1 .c::s=,ii~;::I -!FLlU IlFUYJOU8 ..._P£fMOUa PLTtR DAM CROSS UCTIOHUCTIOHC-C SECTION In\ _MAX. ~ MACLAREN GENERAL ARRANGEMENT ICAU-A COfPIlIl>IoIII ~ / / /1 uoo t400 ~.a_lI.'jlL.eaa ~',1~~4O!I I .............r.cg:f ~........~IDOOI'..........::::;:;;;>:;>7~i~..................""""""'=0 ! EIZOO L--2ChU :......r~.m'~itMii I iI 8£CTIDH 8-8 ICALEIC DEN~LI a MACLAREN HYDRO DEVELOPMENTS FIGURE 8.1.3.9 -------"" ~~ ~.--'--:>---'--~-,.---r .:...... ~ I. TUNNEL SCHEME -#" DEVIL CANYON 550 MW DAM 2 TUNNELS 800.MW -....-2 MILES __--1475 FT. 2200 FT.WATANA 38 FT.DIAMETER 800 MW_70MW 2 TUNNELS 1150 MW 2. 38 FT.DIAMETER 1475 FT. 800 MW -850 MW 15.8 MILES-I --RE -REGULATION DAM 30 MW '----=.-..:..:==~_...;:::o".300 MW 3. 30 FT.DIAMETER 800 MW 2 TUNNELS 365 MW 4. 24 FT.DIAMETER SCHEMATIC REPRESENTATION OF CONCEPTUAL TUNNEL SCHEMES FIGURE 8.1.4.1 ~ ---_...._-....-~ ~-~,~-!~,\------------1 'SCHEME 3 PLAN ICAU:a ,f III.U Q' NOTI: nUl 0 1..II.LJJIT ••T&I A ,.,LI .,.,.coaca:PTu.AL ",CUCC'T &.4YOUT :3r..:~~,:r .~;'~::.n ...y Q 400 BOO PUT lCALI "''''-r::=a GENERAL AR~ANQE"ENT DEVIL CANYON POWERHOUSE 1'/:1!.~"~ 1100 '1 ,,'-'\:"sr:( :~~~''\:::0',~~~~.~lJI?-.... 't1IL_lZtO ,/ • u ••l'•A "'~~" ~ ~~lIOO ..... ---------1lIoo /"''lllo ---"'--14".---"~'~.,~~ MOO IIlGO . GENERAL ARRA~GE"ENT RE'REOULATIOHI DAM IClL~t 100 1:;RET I PREFERR~D TUNNEL SCHEME 3 PLAN VIEW FIGURE 8.1.4.2 -----'",---","---<~-.~'--'~':.-.,-)...,---..-~.'--.J.-.---,,./'.- 1100..--I I MOO,----I I I I I--~'1500'-----+1----~L,/m;r::c_FL- 14OO1------'---f-----7""""----,HF==dI*-iP....---'''''-<,,-- ~~~I iI '>00 ------=::".....------i II '----'-1+1--- i 1IOOr..<::====u.-!-_....========-.Ill::===Jll'==~ 1100 -.----, RE-REGULATIOU DAM TYPICAL S£CTION SCJoI..E •l~llI!J 100 200 fEET 5iiiiiOiiiiiiii o IC'L~.! NOTI-niii CIt......ILLUaTDI:TD .& .....L.....JrT COMClPTlUL .-.o.IlIcT J..AYOVT ~PO_CO..I.IOM tW M.nnllAnVI ,'T.P4VlLOPI:CWl'l oa...y TUMlEl ALIGNMENT DEVIL CANYON POWER FACILITIES PROFLE seALL A 'r ;-.u AfOUIW>ITYO, ~lTllm'IOIflI10UT IlflI.1.ltOl.E ---, IUNlIT 1-"ROCK erx.r ..ITI:!+PLAn: DETAIL A IlOO ,'-7-.----7 !.', , " ,;b ,.II"'"'DlSTANC£ I "I, I I I w:E:--:-~.~-~3-----=------,1$00 10'~CHAMBf.:R ___"--=.~""-, :rnr:--:,\--~ ----~IZOO iI ll"oo I------------,~r'ltr----rliii §!dOlO.T~'----l;'-+...:'==---:i~1000 1\.OIHt:L !b!!.~'__ ---- BPUWAY PROFL£ ICALE • ClST"~'/'••_C<lII:Af;JI:,'::-.~-~\' IU IIJT_ m.'f"~ 1-• '-I£AMtQ NO f• a!!i.UN!D .,mn QlT '~\ ~INTAKE SEC7lOHA ROO:BOLlS ASiR£llUJlfl) ~ \!II.!!D ------,lIOO.---_ HOIlOW.IWt.~lIlllO~_~...::,.~ ti ,ud ,,'~--illllIlW:"t~ ;------::~~_J~-----=----=-~~-~~-..-----!ZOO -,-------1""".---:----!-.»tz,......AL'm',/!~/d'~iIIillll*=~.~ ....------ or;r.... TYPICAL 'M!'F-SECTIONS IN:r," SECTiON A TYPICAL TlHlNEl SECTIONS (N.t.0-) DETAIL ., PREFERRED TUNNEL SCHEME :3 SECTIONS FIGURE 8,1.4.3 3 3: :E 2 ooo >-l- () ~I <()715 '} ",'1 1 J 1 l 01.---1..------------------------------:--...... LEGEND: I.t I )' ~ J j J 2010 DEVI L CANYON (400 MW) WATANA-L(400 MIN) 2000 EXISTING a COMMITTED 1990 D 'HYDROELECTRIC ItWW1d COAL FIRED THERMAL ~GAS FIRED THERMAL .--Oll-FIRED-'l'HERMA\;'(NO"r,SHOWN-ON-ENERGY DIAGRAM} NOTE:RESULTS OBTAINED FROM OGP5 RUN L8J9 ' 1980 10 2 8 ::I: 3:6(!) ooo TIME GENERATION SCENARIO WITH SUSITNA ,PLAN E 1.3 -MEDIUM LOAD FORECAST- FIGURE B.1.5.1 l 1 \ i 3 3: ::1E 2 ooo >-r- u ~I <t U 715 1980 1972 PEAK LOAD 1990 2230 2211 ... 10 LEGEND: VEE(400 MW) HIGH DEVIL CA.~YON-2 (400 MW) HIGH DEVIL CANYON -1(400MW) EXISTING AND COMMITTED NOTE:RESULTS OBTAINED FROM OGP5 RUN LSOI o HYDROELECTRIC fttt~~1 COAL FIRED THERMAL EZl GAS FIRED THERMAL 18 OIL FIRED THERMAL(NOT SHOWN ON ENERGY DIAGRAM) TOTAL DISPATCHED ENERGY~ 2 8 :I: 3:S(,!) oo Q O'--...;.a..------------------.J 1980 1990 2000 2010 GENERATION SCENARIO WITH SUSITNA PLAN E 2.3 -MEDIUM LOAD FORECAST- FIGURE B.1.5.2 3 I J I ) oJ J t '.I J 2010 WATANA-2 (400MW) TUNNEL(380MW)·-~ WATANA.-I(400 Mw) 2000 EXISTING a COMMITTED TIME 1990 o HYDROELECTRIC It~tt~~~1 COAL FIRED THERMAL (:Z]GAS FIRED THERMAL •6iLFiRED THERMAL.(N()T SHOWN ON ENERGY DIAGRAM) NOTE :RESULTS OBTAINED FROM OGP5 RUN L607 . PEAK LOAD LEGEND' GENERATION.SCENARIO WITH SUSITNA PLAN E3.1 -MEDIUM LOAD FORECAST-. FIGURE 8.1.5.3 1980 715 3= :E 2ooo o J.!I~03~;;~~4;.....~tl=:=I.~4Wb=dL .:2:0°::Jk!.;~~]~~"""'1~1~]~~~tm.1~1~~1~1 1980 1990 2000 2010 0 ......--1....:.....------------------------.....1 >-I- (;) ~I <[ (;) 10 8 :r: 3=6(!) oo Q _•..,._..... (!) --0::-----~--TOTAC-DISPATCHED--·~4 ENERGY~ 7300 I 7200 I I 7100 ,~l-o ~~~CD O x ~ en 7000I-en 0 (,) Z 0 i= (,) :;:) 0 0 69000:a- LL. 0 ::I: I- 0: 0 3: I-6800 z IJJen IJJ 0:a- 6700 6600 1------l------l------l------.1f------+------l 226022402220220021802160 6500 '-J.-J.-J.-l-.---L --I 2140 DAM CREST ELEVATION (FT) WATANA R~~F:RVOIR DAM CREST ELEVATiON/PRESENT WORTH OF PRODUCTION COSTS FIGURE 8.2.2.1 ) J i j l o.~. I.. o 2 1 ~ ~. COO',w.] i I \ (0011'¥"~3 CJ) Wx« :E«o w> ~zl~ « 1600 .------,..-----:--,..-----,------'--..,-------, - FIGURE B2.2~ 45.40 LESS THAN 3 ENTRANCE SUBMERGED ···30 35 TUNNEL DIAM€TERJFTo' 25 1450 '--L-__......_.L-_~__..L-....--,_......___' WATANA DIVERSION HEADWATER ELEVATIONITUNNELDIA"METER o -.1550 J------f------;----:1~....-l~;------+------;...: I&.-zo !i>1&1.... 1&1 NOTE FOR 80,000 CFS .................•..-1····..···TY.PICAL·..·· TUNNEL -----------_._~-----_.._.----- SECTION Ii zo I-e:t> I.LI ..J I.LI 1650 1600 1550 1500 !AT1720COST 50XI06 If I lOX IQ 6 20X 10 6 30XI06 CAPITAL·COST S WATANA DIVERSION UPSTREAM COFFERDAM COSTS FIGUREB.2.2.5 80 ""C 70 ~..., ~.~_ibQ O~'/ 60 f7~~"Y4,,~~:~A io-'....50lD ~~~0 ~x..<c"Y .....~~~ t- tl)40 ~0 U .~ .J .~Ct- o. Cu 30 ...I··c ..... 20 I·..···········1· ---"-~..-.._~_._------".-~,.....--------------~-----~.~--_._._._~_._..._---_...---_...•..-_.__.__.__._~.._---_. 10 0 TYPICAL TUNNEL SECTION 15 20 25 30 35 40 45 TUNNEL DIAMETER (FT.) WATANA DIVERSION ... TUNNEL COSTI TUNNEL DIAMETER FIGUREB.2.2.6 100 ------..,.-----,..-----,------.,-------, 90 .... IJ) 0 ><-80 (I) I- (J) 0 (,) ..J ~70I- a. ~ (,) ..J ~ I- 0 I- 60 0 TYPICAt. TUNNEL SECTION 50 15 20 25 30 35 TUNNEL DIAMETER (FT.) 40 WATANA DIVERSION TOTAL COST/TUNNEL DIAMETER FIGURE 6.2.2.7 .I !. j J 1 U) lJJ ~ W :I: U (f) >-0:: <t.z ~-;;;.;I W 0::a.. ~'t/)I \ I J J J ) ..1 ,j ,I ") 3··g 3 g -. ==N ;;J.D.lI ,.NOJ.LWJ13 I ) ~>) .c:oc..-CIIIUCI\IIlI000It1'f.lllD~ILtATII , NOft....L IWl ..3e ._41" irWLILItoo_..--..---.... .......,'--..----.--"; 2ZOO -.-,r "-1--"'"""'T'-i...\=,rI;g_.-.-:-...~~...----...---....--*--:.._..-"-"-'~"''''......1lOClC'IlOO - ••:>-.••~.~I.--\'"-;I~~'1 .,::-----...,. r~~,lIIOlNl........"",,--.-.---.. IllOO ,;~!-~~-I ...........-.rr-1 ..~.---.::.~"/~~-ClIlT'"iJmoD ~._--.:-.-........:"'Z. 1I ~,.......,...... ,~~'~" ·o.'\"."......:"-...,~m>o ",.,~.""".~"~..::::...."I'-...-.......r lTlu....- IlOO ,~.-....;.:::.........,.,"--.J "8 ....T"'L:""""'" ..,.....-',......"---,~1478cooI"-~~.-......r:-I."-;I tllOO HOO i I .IlOO IDOOD0001000 11lUJNIHQ It PUT 1+"1+8 SPILLWAY PROFILE ""r'I m>o lOo'___'--1..~/i---!..:IlOO .IIi /'1\ !i /)lit .... li /l /---.. 1\•.".f 51lOO J ~I W-'--_·····---·fl'.~--EL.I440 !.J'--,-t.........\,'1•MOO ,-'.!:/ "~>I.1··- _:~;/ ..--.. SECTION A-A SECTION i8-8II I I I ! I III(",en I i -;;jj .....1••fuu.,••rll Ai...LI.,....,cac:IP"UAL.Hta.tacT ".'lDVI' "'"....ID ~CQMPa.flO_OP I !ALTa_attYl .'tT.OIVILOf'_,an ...VI ! I ! I .0 100 'go FEUI-..1I .. III i I SCHEME WP2 SECTIONSWATANA FIGURE B.2.aEtI.., '-''---'~.~.~--'-------.-./',-~'---------'~-----'~'_:~. I \..\ " Z <t ...Ja. va.. ~ w ::Ew J:uen 104D40ID10II10.., IT,nON''':_nET l!PlLLWAY PROFILfi I SCALE:A 10o ,.....WL.r~~"ftL='ZfTAILI_:r~O¥IJI_'.~.*--5t.·I r..----1:-._-_._.===.=........_.~--~~~~~~~~~~~~~~~=-=:':t::;:S:5=-T-'=f~:;-===--=---,----.--.._--.~_.--:-':'---1- I ====:~~;::;~=:~3:::~~~~~~~~~~~~~:;~~~ll\r-:llU:....n ...·R'eKl'"" I t4C<I aoo tIIlO,-B-itt.· I!1_ ~IIOO §IOOO.. 1700 IlOO IIOCl 1400 SECTION B·B ICALa:• ~A '_...._""_':"ITI~-..B ~-L ~_ ..llIlO -.IlAll.••L.~IIL.lle r \••------_ I!l fL.1100,1 14'-------_._"" ;1100 ..,..t ,.CN.T.IJ -'--__.!~'t1J II -----rLiiiD '----••~----••----!,-'-__rllL.llea ~,.-IL.I'"-'---..__.............,;'t."-'-:r- ~IlIIO ===-&..~~~.~--......I r IlL.1110 I J \V L j:t__=-::~~~===~IL.~I~IIO~==§:::(t::~~~==-...:.-------__J·'biiiiiii=Jlr:.-Jjb=~~~/C.__1110 GROUT QlRTAlIl"""'-:r--....-RlLlI!I'OIIAIIII ' I I ~A ~B SPILLWAY CONTROL STRUCTURfi ICALEI • NOTE ~£NtA••••IIt.LUlTW.TIS & "'ILlllllU.'COIIClPTU&L ~CT IoAlQIIT ..lltoAaIO '0'CO""".'IO.0'AL.T.....'I...lit.NW'L~.Ta .L. DO '00 nIT 5iiiiiiiiiiii IllO 400 PUT ~ o ICAU:A E !!. ICJ!l.I • SECTION c-c ICALII •SfiCTION A·A SCALE:8 i ..1'1001 :\_W WWI r'---I. 'NUl 1100 1 I ~'\../I i IRISO I ~F--==--'::::::--'=--J 1._i ! ! e§1IIlO.. I WATANA I SCHEME WP4 SECTIONS FIGURE 8.2.3.7 '---.i -------.;,,---.-'--.-''-------'--=---------'--------.J '-~.----.../'-----..-'.~ ------------- .------./----..J 1100-Nor£ --;;'it 0.".1 ••U..1.uIT...Tla • N[L'........COfiICI"UAL.,..eJeCT'LAl'OUT ..INAIO POtI CO ......'IO.t:# &Ln".T.YI IITI DfYlLOP_I_TI OIL'I @ ----toOCl -1200 ~ .-r--- ".rP #'/ .p>r--- tI'~~ ~~rP'r ~o/ ,.P',;/ /"'.~J ,000 ......---.......-------ITOO~ 100 400 'UT 5iiiiiiiiiiiii FIGUREaa.3.8 8 %";i \ J I \ ) 1 I J ] .J "11 (;) C :Dm !II f\) (}l o t j '------ WATANA DAM STAGE I i WATANA INITIAL DAM (STAGE 1:) i WATANA HIGH DAM (STAGE 1II) , /.~:. P" ~ SCALE o 500Ft. I J ---- --- ....,~ 1/(, I I I I \\\\ --\-L------- \\ II I \ I I I \I \. \ I \ \ \ I' \\ II \\ \\ \\,\ \\. -"'-Q~~] o FIGURE 8.2.3.11 --] ] ] .I "Tl G) C ::Dm !D I\) ()J I\) t j -.~ ~----/--.---/-- ---~/. WATANA DAM STAGE III ----------...-------~ -~ _1-_ SCALE o 500Ft. L-------J 1-<350 -----,...----,...-----,.-------,-----, '1) .1 1 1 I.J J J l j 1FIGURE82.4.1 4035 I -PRESSURE TUNNEL (~6tOOO CFS 25 30 TUNNEL DIAMETER (FT) 20 Lj--- TYP.TUNNEL SECTION 1000 ~----1----____1I-\-----+------f----_ DEV IL CANYON·DIVERSION HEADWATER ELEVATIONITUNNt:LDIAMETER 88-<3 .......---.......-__......11.-........-.6 ---' 9~I------+-------ji------+--.:..-...---+-----:~---i !t=~ iii ..I iii iii ~ra: ::;) (I) ffi 950 1------1----____1f----~-+------f---_ !ci ..~. =- -..,: I&.- \ A$ 0 VTYPICAL~TUNNEL SECTION . 20 18 16 14 -(1)0 >C I ~12.... I- (I) 0 '? I 10 I (L I 8 6 4 o 20 25 -30 TUNNEL DIAMETER (FT.) 35 40 DEV IL CANYON 01 E TOTAL COST/TUNNEL DIAMETER FIGURE 8.2.4.2 POIiCltHOUl1 LOCATION "'-"CT TO OI'IllIlUnOIl lTUOlIi 0'OOn8Tll1ll LOCATIOIIL Tltl.oa••'.O iL;".....ATC... ""LIIII,•••Y CClIICCPTUAL PttOoIIC'T \.41'OU'~"AltfC '0_eo.~.tlo.o• ....fC......TI"'.I'll OtvlL.O~"TI 011 ..1' .!l2!L SECTION A-A . I(( ~~ !! ,,, '\11 \\1\~ § \.II " \~--J I~ 1DOOi I 11,....ItY ...I_t :1 \~tf5.:3:J..>-~::--~__m:: 0-,./ !.:J ,~.. o _ 'CALe:I ! -'A SWlTCH'Y'.ARO /n..1I1O I , ,, I I -.........-~ f-- \ GENERAL iARRANGEMENT ) '.\ '\~\ \I,'..\"""'~~"" \C~.N//·n:Q,~r.~~:-~~\TE,i'xy,/,~~,\/ \ \\,I\~\R ))~"J ( 'l 6 J..:--i "-Jd,.! I,q I t I I I I, , I )!/Ni'.cr,I:!<~,:l ':;~(jj I,i ~'\\~~, , I I I"'~, EL.JjIO '-,ALl~VIU"1M 81vtR em -)DR!jOG!D i\ i l \); ,I ~ \ .\.....\__I. \'\\\ g ~ @)~~i '----,.~~··'--t--;,~800 "-v",....."':", ",.• I ,:I '"Itj lo.""".,I~----'."O~.'I lid'''''!,I"\',::'''1':.:.:(I....+\y~UIUili,.<i~~,\t1i'·::~~~.~-h\.LL~:"","""I, 110..,"'n 1""1-"~"'I"'L , I -----7"','~tl:N I~/I, Jcmu:ra .i I : -~--. ~ ((/ ,LI.lIOY\~. \ os . \ DEVIL CANYON SCHEME DCI FIGURE 8.2.5.1 .~'~ ;1:1.-14&7 EMlAOLNCY IPtU.w"y ~ POW,£RttOUIE LOCATION IUBoJECT TO Om..v.T1OH ITUDIEa Off OOW.S11lf..... LOCATIONS. "'M"0'ILJ.U.,... ,..(LUIU COIIClttTUAL ,.O"ICT LA'I'Wf...1.......(t1 PtMt CO.,"'''.'IO_"" &Ln"aTIYI IITI OIwlU)"M'Nn OM.Y I' I ,/ /I l J ! I J /I ;'./ \ \ i \ ~.- '\ \ \ \ o too 100 PlITp==, ( -....,') "'// (\\jr--.'-J \[J \ \ ii/ .WITCHYAltO IELII70 , ,,,, \'.r -, \ \, I I ,,,, l.(\,J\ "\i .c~ "-...~ '\',- ", \~DI~'AII'"1lI~))~~"llIA.c...c.1ft !..,LIN(O lUNNlLI />,I'/# "'"\\\\1"I~'1 _\(I:!II , : I \ \,',(/ I'.... .'<\,'I): I I I • I I '.'/ , " I I,-=--~~/1-....1-"",""--, '-. ~, "-'-tv ...._- .~~~"..UPSt"MAM CQ'fEROAM-_-----'-,'~~x~-,-;>, '\::::1,I \Itlll",',1 I\:1 11 111",,:I .(';j-I.1U.I.L111 UL I\Jt n~~mr:~/"I".' ,'-------) /~l , \ ',-- i \(§ ~) \( \\ \ \""\ --"--@) -800 _0;....-·......' I i ./ \'-, GENERAL ARRANGEMENT DEVIL CANYON SCHEME DC2 FIGURE 8.2.5.2 rt) Uo zo -~z«u .... i i i ,J ... 8.. I / -/IJ--a+----I I I I I I I I I I I I / I I I I I / I I I / Qo.. / I I I I I I I I II I..-_... / I / / /' / I I, ,/ / I I ~ ,i,.. ,i I ... Z ILl ::Ii 101L1ILl <ll Z <Cl: II:ZII: <Cl:,0 I ..j:: 'U ..J '9 u <Cl:lD ILl II:~rn ILl;z =ILl .. <ll ".. Q '= 100 1:00 niT !!Iii 8ECTION D-D FIGURE B.2.5.4 o 8C.Wl .1 NOTE -;:;'ii Ott......IL.LUl"nUTn " "'UIIIII".RY e:e-UI'TlUL ..-o.rIc:T LA'l'aUT .........,.,'0'1 CO.".IIO..0' ALTaRkATI"'1 IITI C[VILO......IilIT.O_LT 8ECTION 1'-' SECTION C-C SCHEME DC4 SECTION B-B IlOO I /7 DEVI L CANYON MOO i 7 1100 i \:7<I "~ 700 I _•.:._i __....:.....•..!_..!.....:1.................J_..........too noo "'AnOIiIIilG ..nIT SECTION A-A lTllllU.....-1 I ~~.---Go '.-- 800 ~ HOG 1100 I :i"}?'n ............_~~~:\/ 11100 r ......-I -=:::: 1001 CC"=tI"---__=_-:-~>......._--==-=::::........~vb,._v .. ""5il...J........a.._,,-......... ~IOOO I ).111...0'ca.I \I'}\\,<7 ~1I00 Ii~"00 I ..-~>">"__•__'''-7~IOOO ...............""'. e t ~1 ."a·:~~~~~.\~ EllOO ~;;;,..., Ii S 'It c-S"ool "7 I~\.,\lOilO,.. \ \100 SECTION E-! COWfI'UTIDM ar"lIPa..1..lUY-·- ~~ --~ GENERAL ~ i / I /I I I / I //'----"\\I /"I"I "..'.,~/I I I \i ~,'~~_~,___. ."I I:II 'I 'f'~r -----I /I\_,,00 _______-------~,---."I ',i.',II:;..'V6',iII;,.-----..............----........__.i:---~__I,•\.'111 1,"""1 :\I 'i //Iloo ,_'--,~"-i -_____'~__I '\l\liJlJllli;;.(I \)'I ......_C~I I i IInt'r.WO -)I I LillO tuIML ~I \./IItIO -------'"",,-____"-J <\1':1111[1,---\ ~~""~~-'\''1',,,,,.,,I''I \I /--, I"','1\1 I .-I \-"""".\\ I :1 I /\:(/\\ I i,400 "'\~,\'I 'I f ~ , "I \I \, \ Moo,."'\'11\)~I\)~\\I\''.'.~t"..':.,IWW'U \I\I I I \I \\.\\ I jIOQo'-,,"'"\,,\1'\\"I \"\~'\I;1I i /L III; l- I; ; ; / / / \'--~I \I\~~! II I "l I ( ~I\ I IWITCHYARD ~;/\/EL.lI70 I I E .....000 I \~'\-',',__._i·\--\y\"i''\\I '"\\'\\,\"i'j'III II '.II II III \ ~I \;\\\""'GO \\\\~t6 \\\'\,,'t i ,~"'l"\~\,"I \J} --~~,111'[~=1 )\<~n __•\:\\\''Ii!\\,'\\\1\1\\\IJ1/f l ~\\,'!,/G,. I~I I \~,/\\\\;,,\...\.\,"~,I ,""__,_I,"\ I ~I ~l 0 100"zoo nET '~NOTEleaLE,=t ~011.&.,.,IUU"••TIJ A ".LIlt•••..,.cOllcl..rUA .."0.l1C'T l."rouTMI"'.att JO'I CUM'ARIIOII OF ,I ."..,.....,• ,_1 ,........__Jl..'..."n ....'',I ',ALTI ....TIW.liTI Da'VILO_Ita:_Ta 0-.,. I I "\' i \I\.p,J ....--~--.-.-----_.--------- ------ -- ---------_._----FIGUREa25,5 '---'------'~''------I ------..; ,...~ '11' til. y .. y •• ACCESS PLAN 13(NORTH) SUSITNA HYDROELECTRIC PROJECT ALTERNATIVE ACCESS PLAN ••• Til. 'II' FIGURE 8.2.6.21 'II. .... 'IU • ••• ,... \\~.~........ ... , i ACCESS P~AN 16 (SOUTH). SUSITNA HYDROELECTRIC PROJECT,I ALTERNATIVIE ACCESS PLAN ... TO" TIlII Til• ,a. ::::~~_TN. ~~-_....••-_. FIGURE 8.2.6. '--.-___:---''-----'~__-.....---....-----....'------.L.."'----'' ''-----..---'----""'--------~ .... .... '1M '... fII' ,.. 'D. fl•• ACCESS PLAN 18 (PROPOSED) SUSITNA HYDROELECTRIC PROJECT ALTERNATIVE ACCESS PLAN !FIGURE 8.2.6. FIGURE 8.2.6.5 (I)·LATEST START DATE OF CONSTRUCTIONA.CTIVITY. _.SCHE-DUI..E .FOR ACCESS~AND DIVERSION ] ] -} ] 1 .1 ~j ] -] J J ] 1 1 J ] 1 ] J I• I I I I e I I. I I I I I I I I I I I RIVER DIVERSION 171986 (I) 1985 ( I) .__..-.- NORTH SOUTH TIME FRAME FOR EXPECTED ISSUE OF FERC LICENCE DIVERSION CONSTRUCTION I INITIAL ACCESS CONSTRUCTION I DE NAL 1-NORTH Imrrnnn]]]JlIIIJlJlIlIJ]~iiil.iiiiit1 ~gcC:iE;ETaHu~:ED (I).I THIS DATE TO I SUPPORT.DIVERSION CONSTRUCTION DImJ[[[[[]][[QJI_-....1 (I)I I ) NOTES: 111111111111111 ACTIVITY START COULD BE DELAy'ED AFliDQIVERSION STJJ-L MET. !1Ij I ] I J Ii IIl...J REFERENCE:BASE MAP FROM USGS,I:2!IO,OOO HEALY.ALASKA TALKEETNA MOUNTAI~S.ALASKA ALTERNATIVE ACCESS CORR I DORS r R.IIE.R.12E. --:--i.T,22 S. i .l _t)IH. -..J T.9N., FIGURE 8.2.6.1 J ] ,] ] 1 ] ,1 I 1 I ] 1 1 ] 1 1 j ] 'j ~'. r) LEGEND -_...........STUDY CORRIDOR ••••••••••••••I NTERTIE (APPROXIMATE) f?!3A' SCALE IN MILES ALTERNATIVE TRANSMISSION LINE CORRIDORS SOUTH ERN STUDY AREA FIGURE 8.2.7.1 :1, ...; .J j -1 ) I I ~j ) .j I j. I I 1 I .J ) 1 .j 1 2.50 LOCATION MAP I ! II I I LEGEND ---STUDY CORRIDOR ••••••..•..•..I NTERTIE (APPROXIMATE) ALTERNATIVE TRANSMISSION LINE CORRIDORS CENTRAL STUDY AREA I SCALE IN MILES d FIGURE 8.2.7.2 \. ( J j ] j ,.J J I ,l ";j i j ) ,I I ,) t ) j j r ALTERNATIVE TRANSMISSION LINE CORRIDORS NORTHERN STUDY AREA 'Ih"MS4mANICS -=-___r_r--"<=--.J'o ""ilO ~~ LOCATION M:'"IN ,.,LES -J I i I I I I LEGEND - - -STUDY CORRIDOR ••••••••••••••I NTERTIE (APPROXIMATE) o 5 10 I I SCALE IN MILES FI GURE 8.2.7.3 ] 1 I j ...,.',". 1 ~~l I I J /") I I 1 t ) J .j 1 o I ,.,/ MT.JtkKINL£Y ".." "...../. ;,.,,/'"DOIAU r /L_.r-"._ ~1"fJ)-1I7::::::b<~:::F:~ _J o ..""1 J SCAlE IN t:1l..£S l.o-:ATION MAP l I I .,':" MATCHLlN'~ 2- RECOMMENDED TRANSMISSION CORRIDOR SOUTHERN STUDY AREA SCALE IN MILES F1GUREB.J ----~._-"------ r J : J : j :] !'! :J .1 ) ,i J ,) .1 ;'j "] ·1 ·! ·1 :j ,] @. .,!...........-,I . .... ",, !'.., ~',~ "'-,1:IIIuI'I I ::';-'.i:I'..I .....1 I I I , ,. ! Il--iL._M_A_T_C_H_L1_N_E_A_ RECOMMENDED TRANSMISSION CORRIDOR SOUTH ERN STUDY AREA o I 2 I =""'.'!SCALE IN MILES o Z1l !lO-SCJllE IN Y1l..E$ LOCATION MAP FIG U RE 82.7.5 -~.- 1 ] J ] ,) l } I . 1 1 '1 I J ] j j I I J I I 1"'0IIl1-----'1 MATCHLI NE B RECOMMENDED TRANSMISSION CORRIDOR CENTRAL STUDY AREA o i SCALE IN MILES 2 ! FIGURE 8.2.7. ----- ..I l.! -!, \ RECOMMENDED TRANSMISSION CORRIDOR CENTRAL STUDY AREA MATCHLINE B o i SCALE IN MILES 2 I ••50 s:;AL.!IHH,L(S LOCATION MAP FIGURE 8.27.7 / ;J \) J :J J ] ,I ) , I ,-j ) ) : J I I ;I ,J :I :] ,I RECOMMENDED TRANSMISSION CORRIDOR NORTHERN STUDY AREA .....~.. I MATcHuNE C LOCATION MAP 012F;! SCALE IN MILES FIGURE 8.2.7.8 --~-~~~...~~- ,1 J ,1 J j j 1 1 J ) ) .) 1 1 j ,] ) ] FIGUREB:2.7.9 :J:AL['"Wi..D lOCATION MAP 2 /'( .0 / "':'i J\'--L •I \ \ \. \ MATCHLINE 0 ~ SCALE IN MILES I $ o I 1'- .< RECOMMENDED TRNORTHER~NSMISSION CORRIDOR STUDY AREA I MATCHUNE C ·.} ] J ] J .j ~j I j ] ) I j ) j l j : j J J ! ) I I r---i MATCHUNE 01'- I i RECOMMENDED-TRANSMISSION CORRIDOR NORTHERN STUDY AREA MATCHUNE E r-j/ ,, / o I ScAu:IN MILES 2 ! o 2!1 SCALE IN MILD LOCATION MAP j. FIGU~E 8,2.7.1 ~~~~~---~-------------~--------------- iJ ,J .! ,] :J :) I !l I] :J :1 ,] ) l j :.j ,j :1 i 1 o l:'l 00r.... $CN..f INltIL,D MATCHLINE E I RECOMMENDED TRANSMISSION CORRIDOR NORTHERN STUDY AREA o 2 I '=- SCALE'IN MILES FIGURE 8.2.7.11 ---------------- ,} ;1 } 1 ,] 1 1 , I I I I 1 I J 1 .) l 1 :] ) ) 1 LOWER (.!l w W 0:::(.!l '"z w :::>0:::(.!l (.!l (.!l I-<l:~ <l:<l:>-<l::r:...J(.!l (.!l I-0:::'-'0-W (f)::E3:w :::i 0- S (.!l w <l:::E Ci <l: ~C!l (f) LL.<l::::>w I- ::E (f)(.!l C I-Z 0 WW<l:!;t<l:l-LL.0:::0:::::E 0w(f)LL.W W ...J 0:::W ~!;t ~Ci 0 ::E I-0:::W w :::i (f)'-'(f)3:3:(f)co '-' X X X X X X X X X X X X Xl X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X v XA NOTES' I.CONTINUOUS WATER QUALITY MONITOR INSTALLED. 2.DATA COLLECTION(JUL-SEP 1981 AND JUN-SEP 1982.) 3.THE LETTER BEFORE EACH STATION NAME IN THE TABLE IS USED ON THE MAP TO MARK THE APPROXIMATE LOCATION OF THE STATIONS. (A)SUSITNA RIVER NEAR DENALI (B)SUSITNA RIVER NEAR CANTWELL (VEE CANYON) (C)SUSITNA RIVER NEAR WATANA DAMSITE (D)SUSITNA RIVER NEAR DEVIL CANYON (E)SUSlnlA RIVER AT GOLD CREEK (F)SUSmiA RIVER NEAR SUNSHINE (G)SUSITNA RIVER AT SUSITNA STATION (H)MACLAREN RIVER NEAR PAXSON (I)CHULITNA RIVER NEAR TALKEETNA (J)TALKEETNA RIVER NEAR TALKEETNA (K)SKWENTNA RIVER NEAR SKWENTNA (L)YENTNA RIVER NEAR SUSITNA STATION --......... ""\. \ \ I H / J / /6' / / I STATION o' ---/._- / ./ ./ /' \ \ \ \ 'Jl \ \ \ )\\ Q.\ \ \o J ",.,.---------~/'"."'"/ / / /",/-,,/.........__// O~~~:i:il0ii;;;;;;iiiiiiiiiiiiiiiii~"?MILESSCALEI::, ~£KLUTNA LAKE /'" / / / / I / / / / SUSITNA RIVER ./ DRAINAGE BASIN\"././ ,./ ,./~,..... ,./ ---,..-~..- /'" ,/ ,/ /' / I / I / / I / / / / I I / STREAMFLOW GAGING AND WATER QUALITY MONITORING STATIONS FIGURE S:3.1.1 ------~.--, ) J j .j ,~ ,) ] :j i 1 ] ,I ,] :I :] SUSITNA RIVER DEVIL WATANA CANYON SITE SITE ~} ,20%.GOLD CREEK ..) TRIBUTARIES 10% SUSITNA GAGING STATION COOK INLET FLOW DISTRI BUTION SUSITNA RIVER BASIN AVERAGE ANNUAL WITHIN THE FIGURE 8.3.1.2 :1 1 II J J l 1:-1 '\ 'I i ''1 I \'j ~_.._--_._~._.__._- 1 I'j ,j I J i ) • 88 r-:-.r-1-Ir--IITI---rI-""'I--n11i;""r---r"1-""'-I-'TT11-r-I-r-I-rr-1r""'Ir---r,--rqr--'"T'"I--r1-"'-I"'--I-r--,-r--I-,,-r---rII--r,--r''''''I'''--'-'-""\''""1-""""'II-r--,-r--I"""I""""""1"'I""",--rI-'"'T"I-r--r-11 -""\""",-OY--I""" --LEGEND:- 80 t--- CANTWELL FLOW WATANA FLOW GOLD CREEK FLOW I-- 72+------------------------------+-1------------------------------------------f - - - - - · .·.'·.' I-~!\641------------------------------j--i4-.J----------------------------------------1f\, I , I,\ 561-----------------------------+-:+--1+--·-------------------------------------~~NI ~I-I ~ -=I '.'w'48 t---------------,...----------------h---;.--It1it--f't--------------------..,-----------------1~e-L';\11\I u .'.V1 CI)1:\'::'I ~/I C>40 I------------------------------f/'-..--"::-:-u/~1_\l_---------------------;.-----------------1....V I ::!.",.:,I c5 __C :'II - - - I, AUGUST I I II JULY I I II JUNE , MAY MONTH , APRIL , MARCH I FEBRUARY I I JANUARY I- o 32 t----'------------..:.------------..:.---t1r--·-\:7;-:-'!...-\\-I\-f\l-lfi-t----,~-------------.,'--------..:.-------____I I \l\\~I~\~ 1 ~:\~,jl!\A 24 t----------------------------++--:---~---=;4\__h.q,+-------------~----------------..-..1 ,1 \\'\-JFr\A:\,~Ql:'\f.:\ :.',,:,\~ •••••:".":"...."'\A161------------------'------------I~--------'---_';_~~~8_,ftt__f~._a_----------------------------1\\y;...."''\VV ~"V·'"...,,..~:\\/'tJ ......V,.. .\~:'.••••.J\'I ~~\p •••••••".'"'.....A if"\. 8 I------------;----------------I-+-----------------~..~:."':-\-_-..".,p.~\.\:I.Ooe~__~,-J-j..J\c-h---------------I ',..'v'"""\ '..'--/"......."..",.'-'"--...........\-'......'.J",- '-::-~-----__--~..~..... I I I I I II I'I '1",',.···I·"':·.-~r .,.I NOTE: TIME SCALE'S IN INCREMENTS OF 10 DAYS.DAILY DISCHARGE HYDROGRAPHS 1964 NATURAL FLOWS CANTWELL,WATANA AND GOLD CREEK FIGURE 8.3.1.3 I ._---~-- J J -1 ] ] 1 J I ] 1 1 1 -j 1 1 ] ] I 1 88 ..-----r-I-..,...I-....,11r----r--I-..,...-,-..,...I·~:-..,...-,--r--I-"1TIII-r--I-r--j-T'lI"li'-Ir---.....,'r-----r'-rr---r'---r'·--r'"T'---r-r-"T'--r'"T'--rI-I'-lt"--rI-II--r,"-T';-11--r,-r-rJr-T.-.,..,-'Ir--T"I-"'"-""1.-.ow,) I .....LEGEND: •••••.•...CANTWELL FLOW 80,.......-- ---WATANA FLOW GOLD CREEK FLOW - - 721------------~--------------------------------j1t--------------------------~ - • - - - - - : " II , I \I.:, r:~I ,::I II , I \ I \I I w C) 0:'« ::I: U 40(I) C >-...I « C 32 64 I- 56 Ci.i I-u. CJ 0g ,48 .!:.() f\( \1\n:..V 'WI:~:\'\\11 i ':\~;\I 'VI:\,:'...':.:~\.1 \,:~.\(\::,:-t.".:".\I:~:~..,,:\ : . \\I :.~/..:..I A 1":":.1 .::" \•••'y •••,1\•••••"'•••\.'I:::::*.'~J :•./~:::~:'.;-.•.~i \:~f ....'./\oJ ...:••••:.".!:....',J;:..\ f "*.... ."'.,..'"I_\ - I,\~!'.::/~:..''.v:\.\~ .....:\.....'.:'.\. I:..../"-I;, 1:", - - I I APRIL MAY JUNI::JULY AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER NOTE: TIME SCALE IS IN INCREMENTS OF 10 DAYS,DAILY DISCHARGE HYDROGRAPHS 1967 NATURAL FLOWS CANTWELL,WATANA AND GOLD CREEK FIGURE -8.3.1.4 : J J ] :I J ) '~1 1 j j ] ] J ] 1 ] ] ] -J • 88 "'--"--1--r-1-"'I""'I11,--.,--,--r-,-""-r-"'--,-.,.--,-"'"Ilil-.,.--I-.,.--'-TrIII-r--I-Ir----,'i""'TI--,I--,I--,.I-rI---rI-..,.I-..,.I-r'-...1-""'1-'-,,.,--.,-,..,-""""'1I-I .....LEGEND: •••••••••••CANTWELL FLOW ----WATANA FLOW80- -----GOLD FLOW I I I 1 I 1 I - - 721---------------------.:.---------------------------------·-------------------t - 64~-------------------------------------------------------'-----------------1 - 561-----'---------------------------------:----------------~-------------------t - - -en LL '0 ooo.:::.481--------------------------------:c-------------_------------"-.--------------------1 w C) '0:« ::t: (,) (I)o 40 1------------.,.,.-..-----------------------------------'-,__------"---,,-'-------------------1 >...l ~ C - - - I~7\'Vl\"\;J\J/I :....:;...\r'!-'..::v\,.vd \~ 1 \,.,Y\1"i ':I ••~\I ::...~~:\\ I \o¥.~/:•••••..••"••••\ :.\ I .."I..\J'IlJ:~.:..'".::\.~.,J......... . .'...'\ii,,:':~.::~"...I\.'.'.\,~""\.:I... .I,.r .,It. MAY JUNE JULY AUGUST SEPTEMBER OCTORF"R ~:......"....."".',,'....:~y.\.,...:.../'.,"~...:~I'.....:,,"ow --_- ................~ I 'I ,,I I I II I I II I I I I I I .···;···t····I·..···....I..·:::-·:;:··l:::I ..·::::y:::·:-::·~:::-:·i:-=:::-=f'..=.:··t~···=·..=:-:j-...·-=-·-zr~.:;:; APRIL .1 10- 24 --- 16 i- 8 f- 1 1 0 JANUARY FEBRUARY MARCH 32 1-------------,--------------------------------:-------------'---------------------f MA ~~A MONTH NOTE:' TIME SCALE IS IN INCREMENTS OF 10 DAYS.DAILY DISCHARGE HYDROGRAPHS 1970 NATURAL FLOWS CANTWELL,WATANA AND GOLD CREEK ..FIGURE 8.3.1.5 I \ !) ,) -'J ] ] ] ~] ) .] :1 1 1 j ] ) 'j :] i ] I ) ------ ~-_...__.~~----::::.~--"~_u .._~_J -"- THREE PAF AMETER LOG NORMAL DISTRIBUTION WITH 95 %CONFIDENCE LI MITS PARAMETE is ESTIMATED BY MAXIMUM LIKELIHOOD 100 90 80 70 ./60 /'.50 // 40 /V iii 30u./'./(J /§20:::V ~W V /Cl "~a:<::I:~~10 ~~•-ello9 ~8 ------~----..--.o 7 ~..~.,----'W ~6 -.-----!Z 5 A A A A ~4 a U) Z 3 2 I 1.005 1.05 j,25 2 5 10 20 50 100 200 500 RECURRENCE INTERVAL (YEARS) LEGE NO: A a BSERVED DATA 0 E,T1MATED DATA•9'>%CONFIDENCE LIMITS ANNUAL FLOOD FREQUENCY CURVE 0 MACLAREN RIVER NEAR PAXSON FIGURE B.3.1.6 SOURCE'RaM 1981 500200 ~ FIGURE B.3.1.7: 10050 -'--' 20 '--~' 1052: RECURRENCE INTIERVAL (YEARS) --; IANNUAL FLOOD FREQUENCY CURVE SUSITNA RIi"ER NEAR DENALI 1.25 LEGEND: A OBSERVED DATA o ESTIMATED DATA •95%CONFIDENCE LIMITS 1.005 1.05 60 10 80 70 .i i THREE PARAMETER LOG NORMAL DISTRIBUTION WITH 95%CONFIDENCE LIMITS PARAMETERS ESTIMATED BY MAXIMUM L1~EL!HOOD 100 90 RaM 1981 iiiu.o 50 8 S ;40 Cl II:«:::t ~a 30 ~owz·~z ~20enz A THREE IP.AR.AMETER LOG NORMAL DISTRIBUTION WITH 95%CONFIDENCE LIMITS PARAM~TERSESTIMATEDBY MAXIMUM LIKELIHOOD 100•90 r---I-------.---+--._--.-I -.-.--..-.----+-----I + 80 70 _60 (I)u.o 8 50o.... -w C)40a: c( J:o -(I) is CI)30_.::Jow Z c( ~-z c( Iii 20z 1---+------+------- -----+-------_._._---_...._.. ...-.-----+-------.--...-.--...--..---t-.---.--...-.. -t--- ; LEGJND 6 BSERVED DATA o STIMATED DATA •.5%CONFIDENCE LIMITS 101.005 1.05 1.25 2 5 RECURRENCE INTERVAL (YEARS) ANNUAL FLOOD FREQUENCY CURVE SUSITNA RIVER NEAR CANTWELL 10 20 50 100 200 500 SOURCE'RaM 1981 FIGURE B.3.1.8 o , ! .:!• i I ~ ~~ ~~L---0--i ::~ I ,.---.~~-I :...--......~-I I I -,~ I ~A"--'"~---!i ------=..J-....-c"____r -----~~~"------A ~.-A- P-~~i ,-------V i 005 1.05 1.25 2 i 5 10 20 50 100 200 50 RECURRENCE INTERVAL (YEARS) 20 10 I 'f.!:,.._i THREE PARAMETER LOG NORMAL DISTRIBUTlqN'WITH 95%CONFIDENCE LIMITS PARAMETERS ESTIMATED BY MAXIMUM LlKEWIHOOD 000 900 800 700 600 500 400 w Cl II:«':I:ollOO(J);ci'90 (J):805170 ~:60«,H,50z'. ~'40 lJ)' ~,30 iii'300 u.o 0'8,200 ::: LEGEND: A OBSERVED DATA o ESTIMATED DATA •95 %CONFIDENCE LIMITS ANNUAL FLOO~FREQUENCY CURVE SUSITNA RI\tER AT GOLD CREEl< FIGURE ~.3.1.9 SOURCE:RaM 1981 '----.-'----'-___i~ ----~~_._~~~--~._----- I J :] ] J 1 ,J 1 -] r l ] '/ .j j 1 ] 'I ,I J I 1 SURFACE AREA (1000 ACRES) 12 10 8 8 ..2 o VOLUME (ACRE FEET 106 ) RESERVOIR VOLUME AND SURFACE AREA I '"./ I>/ V "~DWME"",VSURF.CE AREA /1\ V \/ !1\ I ..\ \ SURFACE AREA (ACRE x 104 ) 6 5 ..3 2 "./V )v~ •VOLUME f'Y V ~IsuRFACE REA /f\ /\ r\ /\ I , I I a 2 ..6 8 10 12 14 VOLUME (ACRE FEET 105 ) RESERVOIR VOLUME AND SURFACE AREA 900 1400 1500 1500 ~ Ww !: z 0 ~1200~w·oJ'wi 1100 1000 o· 1412108642o 600 SOO 400 00 00 ~ 1.00ww !: z 0 2000~ ~>W 900oJ W 800 I 700 I II '600 I 500 400 WATANA DEVIL CANYON RESERVOIR AREA AND VOLUME VERSUS ELEVATION, WATANA AND DEVIL CANYON FIGIjRE B.3.2.1 1 I l} 1 I ( ,I ,I 'I I ! ( i i 1 I 1 1. ,'}. 1459 RESERVOIR IS KEPT FULL AT ALL TIMES IF POSSIBLE 2178 2185 2163 2150 II2143- II 2129 1 2113 2114 •2100-I 2081 I 2065 2074 -WATANA STAGE III J 2000 1 1986 1966111966 -11942 11926 1928 1 1905 1900 I-I 1890 -'--WATANA STAGE I .•... . I I I I I I I I I I I 1390 -+---f---ir--+---+---t--+---t--~---tr-----+---t----. 1800 1850 2200 MAR APR MONTHS DEVIL CANYON RESERVOIR ',.MONTHLY RULE CURVE ELEVATIONS OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP MONTHS WATANA STAGE I AND STAGE III RESERVOIRS ~2150 -Iw>2100w -I a::o 2050>a::w ff3 2000a:: :x:: I- ~1950 ~ u. o 1900ozw 750 ----------------------------~ 450 350 FILLING SEASON SUSITNA GENERATION DRAWDOWN SEASON 250 650 ::2.{§-z 550o ~a:wzw C) >-C) a:wzw >-...J .. :::r:: I-zo 2 OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP MONTHS - WATER YEAR 2000 LEVEllZED THERMAL ENERGY GENERATION FIGURE 8.3.2.3. 2200 ......----------------------------. 2180 -.-:u.. ;;2160 o I-« ~2140 ..Jw W U« ~2120 :;:)en 0:- w ~2100 3: 2060 -I--__._---r----,,....--....---,--_-........--,,....--__-......--_----f, OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP WATERYEAR LEGEND: --....CURVE FOR IN,CREASING RATE OF POWERHOUSE RELEASE _ac.-....CURVE FOR DECREASING RATE OF POWERHOUSE RELEASE WATANA OPERATING GUIDE CURVES FIGURE 8.3.2.4 12:8:4:12: PM PEAK LOAD CURVE AUGUST 1983 (Peak August Day) 8:4: L -TOTAL RAILBELT ./"""""'---..... j;~.,--r\-AN(-... HORAGE AREA1-"---- r-FA IRBANKS AREA _1--------------'------ 110 550 o 12: AM 440 ~ ~ -330oz« .~ wo o 220« '0 ..J 12:8: ---_1 _ 4: --- 12: PM PEAK LOAD CURVE DECEM8ER 1983 (Peak December Day) 8: ,.-' ."". 4: -- 0'I I I I ,I , 12: AM 110 I I I I if I I I I 440 I I f I I I I I ~I 550 iii i Iii • ~ ~-330 I =r---""1""I I "........,......"......."1....."I '-Io~ z« ~wo ~220 I I It I I I I I o ..J TYPICAL LOAD VARIATION IN ALASKA RAILBEL T SYSTEM 'FIGURE 8.4.1.1 MONTHLY LOAD VARIATION FOR RAILBEL T AREA o 0 JAN.FEB.MAR.APR.MAY JUNE JULY AUG.SEP.OCT.NOV.DEC. 1983 FIGURE 804;1-;2 200 300 500 600 400 iOO \~/ \~/V 1\TOTAL RAILBELT AREA /'"V"/---'""~//.-"""" '"r-.-/- ANCHORAGE-COOK INLET AREA 1.0::---~,---~-------Ic-----~-------~-1--------- ~r--.~IRBANKS.TANANA VALLEY ARE~~ 600 400 100 500 3: :E c' Z <300:Ewc ~<wa.. ~ ~200 zo :E 1.028 L8.1°· 26_ 2 :+to ESTER 1.4 52 26-- ~~7 SVC 183- 12.14.~54.4 345 ,KY i 88~ 138 KV"os Lll 0 -190 -380 ,,,":r.n r.n (0 (0 ...:en . N ....co ....,f ~26.1 1'1.5....~1.04:1L9~40't t t t GOLD ~i CREEK 326;8 80.2 r.n .......26.6 -r.-53.1 g .....';_190 WATANA....',...--...;..--.;.------1 ~t 51 .6 "';-2~:6 345 KV 345 KV -t-Jp 282 105 L 0 0 345KV 68.8 .'1.009 L -5.9° ~!1::-1026 Lao .1·15 KV...1:.8 ...-5 ..8 KNIK ARM 41+--+-362\"G 155.3 ---._58.7 58.6 ---.._:158.2 2.30 KV. <f+-'.......80 80 8 ++-UNIVERSITY 744 .120 1.03 L -3.7 0 '--rn."+~...;;".....;5:_:8;.:,;..7----::::5.:::.:8.~6.....;;;:;:.~..=;...:;:..~,...-- .0$-80 80 8 Olf--+-..e+:S VC.3~~ 345 K'l ---;lII>120 -f-Jlo 58 115 K\l WillOW~.__'0.985 L-4.7 ° 322.9 :39.4 """_~~__I~'-,1 t f -t+81 1.006L2.4 ...._~....138 KV "1 ~ 1999 APPROXIMATE PEAK LOAD.DOUBLE CONTINGENCY LEGEND -REAL POWER (MW) -REACTIVE POWER (MVAR) 1.00,t).00 VOLT AGE IN PER UNIT a ANGLE IN DEGREES ~LOCAL LOAD @ GENERATOR ,lsvcl STATICVAR COMPENSATOR t OIM TL TO U/W CABLE AGE-FAIRBANKS TRANSMISSION RELIABILITY EVALU 1999 INTERCONNECTED SYSTEM FIGURE 8.4.1.3 lI I \ i j J 1 j I j ] i 1 lOS Lao -""""""·-659- ........319 ++.-::SVC 172.~ -.210 -t+103 i 138 KV 1.0SL22.70 +-.410 G ........3~A , WATANA 345 KV 9J+.~o., '345 KV t 9.~ESTER 98_~ 345 KV WILLOW:'.0.961L 0.30 '587;8 2.8 1n t.',{--(:.~t 1"112.80.992L7.8°·l!!!!!f__~IIlIlIllli=~138 KV I.345KV -----.----=-....1-.....---1 ----=-.------.---- ;A15B ~tQ.l 1.015.~-l__:9_1;5~1-025L12' '28.+-1.15 KV -~_ ,'NIK A M-......·:~.t_..1:io~"G 412.1--""~184'fI ,183:B-iI'247.5 _-230 KV ."+-++-121_.4,]25.7+i-UNIVE:RSITY;052·;7·144 T.O £..-3.2___189 -183.8__-iI'.r-.....--,--.- -------------------~u--Ell "CL_l21..L -125.7.'!1--_~_4_- 345 KV 345 KV' 204.4 98.8 Hi:98.8 -161 41204.4"-. .1.042-L20.90 t t,*,t ~t 4t'C.345 KV:".',-,-",.."..-..---,-- GOLD ,~tt,t t t45 ~045L2~390 CREEK qOo.~141.4 194.9 45.8'194.9 .+t-80 G ......----1 DEVIL CANYON @ GENERATOR '-lsvclsTATIC VAR'COMPENSATOR +O/N TL TO U/W CABLE 115 KV 2005 APPROXIMATE PEAK LOAD,DOUBLE CONTINGENCY LEGEND -REAL POWER (MW) -REACTIVE POWER (MVAR) 1.00&>.00 VOLT AGE IN PER UNIT I ANGLE IN DEGREES ~LOCAL LOAD ANCHORAGE-FAIRBANKS TRANSMISSION RELIABILITY EVALUATION 2005 INTERCONNECTED SYSTEM FIGURE 8.4.1.4 J ,( ] I i .........SVC '234.4 --+273 '1.05L13.1°·1.015L 19;2 136.5 --i"- 3.5-1+-ESTER :273136.5 --+..-..- 3.5-++.....70.4 345 KV ......132 . 138 KV.l05L30.90 ..-1070 G 530.8 (Xl ~71..7 138;1 18.7122.3 g WATANAttttr{22.3 -..345 KV 1.037L26,1:-+1iIliI-.....-.....-........-~345 KV GOLD.l t ~t t t ~,1.043 L26;5'~ CREEK 622.4 150.Q.·147'229.7 229.7 -4£10 G 622.4 150.6 147 .......285·: DEVIL CANYON 345 KV +--412.' 1.05LOO _851 :yi'lllOW 608 3 0 2 :0.93 L2.3° 608.3 '0~2 "t'.221 ."t--I-~1+t ,. t +1:60.4 -1-0'7 T 138 1(\1" ~f 345 KV 497,8 80.4 1.001L5..6°a.943L-4.60 497.8 80.4 .~.51 f .1-'..1!!'!.57-+-f.......:.2&.1.917L3.1°~SVC492.6.)tl)~·115'KV ·.737.2 810:6 . :::KNIK ARM -'::;:O::==-H-~~"~";".:::1t~G-,....•.....-·1'i-70~140.2;414.8 -"230 KV ",--_4_9,;;,;2.~6,.._.......__•4..;,.;64;..;,;;.;,.1__--:.;46:.:2::.:;.6:...-.:...-1 UNIVERSITY ...........191.2 214.7..-+-188 ..1.03L-2.7° ___-:;:o;:~-1r4_0._2+-...;,,~4;:.;64:.::.1:-_--...,;4~62:;:;.6::-~"~_"~....---. 4-+-191.2 214.7 -++-r,4:~1" 345 KV 345 KV .985L12.4° 2025 APPROXIMATE PEAK LOAD,DOUBLE CONTINGENCY LEGEND -REAL POWER (MW) ~REACTIVE POWER (MVAR) 1.00&00 VOLT AGE IN PER UNIT & ANGLE IN DEGREES -.LOCAL LOAD @ GENERATOR Isvcl STATIC VAR COMPENSATOR +O/N TL TO U/W CABLE RELIABILITY EVALUATION 2025 INTERCONNECTED SYSTEM, FIGURE 8.4.1:5 RESERVOIR EL.2000 GENERATOR OUTPUT WITH TURBINE OPERATING AT BEST EFFICIENCY GATE -"';"'--:--.. STAGE m NOMINAL PLANT CAPABILITYIt6V8Eo~A-JGEOPERATING HEAD 185MW I-------I------+-------..+---+--,ST AGE m'650 _DEPENDABLE PLANT CAPABILITY I DECEMBER-JANUARY HEAD (645) 170MW GENERATOR OUTPUT WITH TURBINE OPERATING AT FULL GATE POWER--'I 500 1-------1-----...-t---j~-STAGE 1-----+-------1 _NOMINAL PLANT CAPABILITY I AVERAGE OPERATING HEAD (490) 110M'll 750 ,..-----..,-------r-----.,....-----,-----....., 200MW ..:.R:.::E;:.;;S::.::E;:.:.R.:.;V:..;0=r-I:.:.R~.-=E-=L~...:;2:..:1:.;:8:.;:5+_-,,__~r-.1 MA XIMU M HEAD (719) 700 I-------I------+-----+--I---~t-+------I I-w ~600 I-------I------+--~~-_fl_-----I------I 1 w Z a:Ia: ~ ~550 1-------1------+--,1----#--+-------1------1 c <Cw :I: I-w Z STAGE I ........._,,4,,5..0..1--1-----I---1-#-_-.-I-,,~1-+-..~~j5~~~~~~~J~~b~~~~~~~BILlTY_-~. .90MW 400 1-------1--1--1----+--'----+------+-------1 MIN 1M U M H E;.:A~D__+&-__..:.R.:.:E:.;;S:;.;E:::.;;R.:.V~0r__1R........E...L...._1...8...5..0"'1 (384)I 65MW 250200100150 UNIT OUTPUT -MW 350 .....----.......----.....1-----.....----......-------1 o 50 WATANA UNIT OUTPUT .....- FIGURE 8.4.2.1 75MW OMW --MAXIMUM HEAD (600) MINAL PLANT CAPABILITY RAGE OPERATING HEAD 0) E PLANT CAPABILITY EAD TOR OUTPUT WITH OPERATING AT ATE 180160140 UNIT OUTPUT -MW 120 ~1 RESERVOIR EL.1455 GENERATOR1 O~TPUT WITH / TURBINE OPERATING AT I /_NOBESTEFFICIENCY-rJ AVE(y ~.L __17 /'.GENERl /TURBINE FULL Gi ..~/RESERVOIR EL.1405/DEPENDABL MINIMUM H (545)- 150MW- 580 620 560 540 520 100 600 I-wwu. I C«w ::J: I-w Z J FIGURE B.4.2.2 - ."\V~o\l-> ~ ,V~«:., /o¢ bOlO' ~V /' ~ ~- V ATANA ST i\GEm A ~:D DEVIL C I\NYON WATAN STAGE n ~ STAGE!NO DEVJL CAt'-YON STAGE III WATANA StAGE 1 . 1800 1600 -3= :E 1400->a: 4: ::;):z 12004:., Ia:w In :E 1000w 0wc :z... >800 I--0 4:a.. 4: 0 600 w -'In 4: C:z 400wa..wc 200 o 1990 1995 2000 2005 YEAR 2010 2015 2020 2025 I l SUSITNA DEPENDABLE CAPACITY FIGURE 8.4.2.4 1 1 ] j ! J J 1 --) ] ! \ J I .] J j j 1 tOO UI\.£I FIGURE 8.5;2.1 FAIRBANKS·TANANA VALLEY r:'""":,i RAILBELT AREA OF ALASKA SHOWING ELECTRICAL LOAD CENTERS FIGURE 8.5.2.,2 11 LOCATION MAP LEGEND \1 PROPOSED DAM SITES PROPOSED I~KV I.INE -EXISTING I.INES .~ 20 0I . SCAI.E IN MII.ES ::lOCATION MAP SHOWING TRANSMISSION SYSTEMS 20,60 ! MONTHLY LOAD VARIATION FOR RADLBEL T AREA 600 _-,..----.,~.......,........'_""I"......._,..-...,...-....,...-.......-...._~=;=======r600 o 0 JAN.FEB.MAR.APR.MA-<i,JUNE JULY_A.'J§~.S~.()~I~_r-"-QV!_DEC. 11':10., 1__~~---:-.:.·::.-:I ·_------------------.--------------l----~"I--·_·I-----.------------,---- lOOp-..............0::-+---1-----1----+--+--1---+---+--+--+---~-J 100 r--..~IRBANKS-TANANAVALLEY AR~..__ol----t-~ ) \ I j 1 I \ 1 j 1 j ! 1 ! 1 1 1 j JFIGURE8.5.2.3 ----'-,.- ANCHORAGE-COOK INLET AREA '", 1\ 500 ~/5001\"1\TOTALRAILBELTAREA vVv 400 ~~/--400 ;0 1"'\~~~V V g ~r-~V ~300 1--~--l--\.--1--~~~~::.J---t---4--t---1300 wo ~ c(w Q,. ~ ~200 1---+-----1,....-----+--4--I---4---I---+---1---l------I 200 o :l: '---' 600 iii iii i i 500"'I I I I I I , ,,·-'----'1 ..-----..J ,-_......I ,,--•.-.,_.,'',......l ',"f ..1'--...." ANCHORAGE AREA I FAIRBANKS AREA TOTAL RAILBELT -_,'-.""'-'J r-_r.-~,--.'" ~400'I P..~'I ,A I &I A I • I , Q Z«~300 I ,(\\1 H ",-'~\\1 I.'"J1-''1 N '-,\I H """",w •-(..~ Q Q«o 200 I I I I ..I I-I ~I I 100 I 1 1 / 1 1 I 1 I o I ,,,,,,, SUN MON TUE WED THU FRI SAT WEEKLY LOAD CURVES -APRIL 1983 FIGURE 8.5.2.4 Page 1 of 3 C")--:t 0 C\JN LC 8, tD:' wa: :::> CJ u.. ] ] -j a:u.. C") !Xl 0)..... I- ::::>en J::::> I-CJ:::> ~ I en Cl w w > ~a: :::> C,.) Q-~ ~ w 0 ::::>...J I->-...J ~ W W Z ~ 0 2 I- ~en ooo ~-- oo ("II oo ('f') oo "¢- ,••I, I I ~\ '\,«I w Ia:, «,, w , ~I \«'\ a:.. '\ 0 I, ::t:IUI Z ,,«, I-,/I, ..J \.w .. OJ '\, ..J I ~, Ia:,. «, ..J I«w Ia:•I-, 0 «.... I-'\en I I oo LO 1=====t====±====:::J;;;;~~~=====r:::,=-=:,~==-=l------, :z ":::>....en I I I oocc (MII'U ONVIAI300'VO:l '} ,] 600 i I iii i i I 500 I I I _I J{I .-A I f'\1\I ...A .I ~4001 I \1 ,."II I ('.\1 .......''oIl ,p..,""',:....'\\1 1~<:-\\1-Cl Z ~300 I v,,1)..11 ~IUI \1 I \1 I P.'l.I I w Cl o C3 200 I I I I I I I I ...J FAIRBANKS AREA 100 I--=-I--=-t-~I--+---I-----+---I----J........-...,,---.--,......_,-....,-.-.---..,-----....,-...,.... ,'"...""......I ",........I .." __.'_...',....,,1 ....".-'..." 0'I I I I I I , SUN MON TUE WED THU FRI SAT WEEKLY LOAD CURVES -DECEMBER·1983 FIGURE 8.5.2.4 Page 3 of 3 / - 7.7%/y'l .3.3%/V 3,/V 3'B7 3.6%~ " I··c I~-·1-···- HISTORICAL POPULATION GROWTH 400 350 300 -.In 2500 0 0...- 2: 0 200I-«-':> C- O C-150I- ...J W a::l -'«ex:100 50 o 1960 1965 1970 1975 1980 1985 FIGURE 8.5;2.5 J ) J ~j J J J ] ] J J J .j J ] J ] ] .J 3500 .J: 5:3000 C)- Z 0 I-«2500a:w Zw C) >2000C) a:wzw (.) a:1500 I- (.) W ..J W ...I 1000« I- 0 l- I- ...I W 500a::l ...I.-..«a: /6,1%17 7.0%1v! V / .14'4%/V/ 13,6%;/ , 1960 1965 1970 YEAR 1975 1980 1985 -HISTORICAL GROWTH IN UTILITY NET .GENERATION FIGURE 8.5.2.6 OPTIMUM EXPANSION PLANS· FIGURE 8.5.3.1 •EXISTING GENERATION SYSTEM •'FUTURE GENERATION SYSTEM •CONSTRUCTION COSTS ·O&MCOSTS •RELIABILITY AND AVAILABILITY CRITERIA ELECTRICITY PRICES •RESIDENTIAU . BUSINESS END USE DATA •PRICE ELASTICITIES •INDUSTRIAL LOAD FORECAST •NATIONAL ECONOMIC PARAMETERS •INIDUSTRIAL ACTIVITY •STRUCTURAL F?ARAMETERS •STATE FISCAL RULE RELATIONSHIP OF PLANNING MODELS AND I~PUT DATA I ! APR STATE 1 MAP POPULATION_REDPETROLEUM-ENERGY.OGP PETROLEUM ECONOMIC HOUSEHOLDS_ELEctRIC GENERATION REVENUE REVENUE GROWTH.-LOAD PEAK PLAN FORECAST -.FORECAST EMPLOYMENT.FORECAST LOAD I •.ROYALTY RATE •SEVERANCE TAX RATE!. IRESIDENTIAL&qOfl(lMERCIAL HEATING OIL &GAS PRICES ALASKA GAS AND OIL PRICE FORECAST WORLD OIL PRICE FORECAST ALASKA OIL AND GAS PRODUCTION FORECAST ---.J '------''-----"..----.J ..:...---~.__" r 'I I I,, 1 I INPUT VARIABLES: •PRODUCTION VARIABLES •PRICE VARIABLES " REVENUE FORECAST MODULE •North Slope Oil Revenue •North Slope Gas Revenue •Cook Inlet Oil Revenue •Cook Inlet Gas Revenue PETROLEUM REVENUE FORECAST •Severance Taxes •Royalties INPUT PARAMETERS: o INFLATION RATE •TAX AND ROYALTY RATES 8 ECONOMIC LIMIT FACTOR ALASKA PETROLEUM REVENUE SENSITIVITY (APR)MODEL STRUCTURE FIGURE B.5.3.2 'J J ] j 1 } -', ] ,] ] ] ] ] ] ] ] ] .] 1 I I I FIGURE B.5.3.3 NONSTOCHASTIC PARAMETERS INPUT VARIABLES: •INDUSTRIAL CASE FILES •PETROLEUM REVENUE FORECASTS INPUT VARIABLES: •U.S.INFLATION RATE G U.S.UNEMPLOYMENT RATE •otHERS PARAMETERS: •STATE FISCAL POLICY PARAMETERS •STOCHASTIC PARAMETERS ccc...NGNSTGGHASrlG ... PARAMETERS MAP MODEL SYSTEM STATE ECONOMIC PROJECTION REGIONAL ECONOMIC PROJECTION REGIONALIZATION MODEL STATEWIDE ECONOMIC MODEL •ECONOMIC MODULE •FISCAL MODULE •DEMOGRAPHIC MODULE 1lIIIlIIIIIIi...----t I CONSTRUCTION I FISCAL MODULE.r,-sr-;;;-I-L PETROLEUM,..-.----.,....-----I~.GOVT.I"ACTIVITY1__ _ __......r---r--...I LOCAL _ GOVT. Ir BASIC SECTORS FORESTRY FISHERIES FEDERAL GOVT. AGRICULTURE MANUF.FOR EXPORT MINING TOURISM ~, INDUSTRIAL'PRODUCTION SUPPORT SECTORS TRADE FINANCE SERVICES TRANSPORTATION COMMUNICATIONS MANUFACTURING PUBLIC UTILITIES EMPLOYMENT DEMOGRAPHIC MODULE ----....1 I FIGURE 8.5.3.4 MAP ECONOMIC SUB-MODEL STRUCTURE ------------------~ ,Ir WAGES.AND.. SALARIES J, .PERSONAL...INCOME ... DISPOSABLE PERSONAL INCOME •REAL Il1o. DISPOSABLE. PERSONAL -INCOME PERSONAL ~At--~ TAXES ' CONSUMER PRICES NON-WAGE INCOME WAGE RATES 1-----DJooI - LABOR FORCE ALASKA HOUSEHOLDS - ALASKA POPULATION I NATURAL ) I INCREASE r-------------.1----, .'F--'-I 1 NET L.I MIGRATION J I I( ~f LIIII I TOTAL EMPLOYMENT IN OTHER REGIONS POPULATION * TOTAL EMPLOYMENT * BY PLACE OF WORK ~,...-------, EMPLOYMENT BY PLACE OF RESIDENCE BASIC AND GOVT.SUPPORT EMPLOYMENT EMPLOYMENT SCENARIO GENERATOR AND STATE MODEL P0PlJlAr10N-.. BY 1980 CENSUS AREAS *CONSISTENCY ADJUSTMENT APPLIED TO CONFORM WITH STATE MODEL SIMULATION RESULT. HOUSEHOLDS * MAP REGIONALIZATION SUB-MODEL STRUCTURE FIGURE 8.5.3.5 ) '] I ,) ] ] \j ECONOMIC FORECAST ~HOUSING --STOCK I III,,, ..-RESIDENTIAL - UNCERTAINTY MODULE ".....BUSINESS - I]"--- Ir -PROGRAM INDUCED--...CONSERVATION-, LARGE MISCELLANEOUS INDUSTRIAL ,It --ANNUAL SALES -- I I t' I\J -PEAK DEMAND -- RED INFORMATION FLOWS .. FIGURE 8.5.3.6 SELECT PARAMETERS TO BE GENERATED RANDOMLY SELECT NUMBER OF VALUES TO BE GENERATED ..COMPUTER. GENERATES N· RANDOM NUMBERS TRANSFORM RANDOM NUMBERS TO PARAMETER VALUES OUTPUT PARAMETER VALUES RED UNCERTAINTY MODULE NO FIGURE 8.5.3.7 J ] J 1 !] ] J .j J\j 1 '] f ] 1 J 1 1 1 ] NEW CONSTRUCTION OF TYPE TY FILL VACANCIES TY WITH COMPLEMENTARY DEMAND •AGE DISTRIBUTION OF HOUSEHOLD HEADS •SIZE DISTRIBUTION OF HOUSEHOLDS IS DEMAND TY )STOCK TY ? CALCULATE DEMAND FOR HOUSING UNITS BY TYPE TY STRATIFY HOUSEHOLDS BY AGE OF HEAD SIZE OF HOUSEHOLD FORECASTS OF OCCUPIED &UNOCCUPIED HOUSING BY TYPE DIIlIlI ·1!llIlIII1I REINITIALIZE HOUSING STOCKS INITIAL HOUSING STOCK TY RED HOUSING MODULE FIGURE 8.5.3.8 RED RESIDENTIAL CONSUMPTION MODULE J J 1 1 1 J ,I ) 1 I ) J I j 1 ) 1 ,1 , J ] APPLIANCE SATURATIONS BY HOUSING TYPE (UNCERTAINTY MODULE) -PRICE-ADJ~PARAMETERS - RESIDENTIAL SECTOR (UNCERTAINTY MODULE) --PRICE-AND- CROSS·PRICE ADJUSTMENTS ..RESIDENTIAL CONSUMPTION PRIOR TO PROGRAM·INDUCED CONSERVATION SUM PRELIMINARY CONSUMPTION FOR ALL APPLIANCES FIGURE 8.5.3.9 CALCULATE INITIAL SHARE OF EACH APPLIANCE USING ELECTRICITY SUM PRELIMINARY CONSUMPTION FOR APPLIANCE USE BY APPLIANCE FORECAST OF OCCUPIED HOUSING STOCK BY TYPE (HOUSING MODULE) CALCULATE AVERAGE ELECTRICAL USE IN LARGE APPLIANCES BY APPLIANCE CALCULATE STOCK OF LARGE APPLIANCES BY END USE DWELLING TYPE EMPLOYMENT FORECAST CALCULATE BUSINESS GOVERNMENT LIGHT INDUSTRIAL FLOOR SPACE CALCULATE PRELIMINARY BUSINESS ELECTRICAL CONSUMPTION PRELIMINARY BUSINESS USE COEFFICIENTS (UNCERTAINTY MODULE) PRICE ADJ PARAMETERS BUSINESS SECTOR (UNCERTAINTY MODULE) PRICE AND CROSS PRICE ADJUSTMENTS PRICE FORECASTS (EXOGENOUS) BUSINESS CONSUMPTION PRIOR TO PROGRAM-INDUCED CONSERVATION RED BUSINESS CONSUMPTION MODULE FIGURE 8.5.3.10 RED MISCELLANEOUS CONSUMPTION MODULE ElGJ,l8i::.....B.5..3.lL~ IJ 1 ) --I 1 J J J I I J \ I I ] I 1 1 1- CALCULATE VACANT HOUSING CONSUMPTION CALCULATE STREET LIGHTING REQUIREMENTS SUM FOR MISCELLANEOUS -CONS(JMPTION~-. CALCULATE SECOND HOME CONSUMPTION II II LOAD FACTORS (FROM UNCERTAINTY MODULE) ANNUAL ELECTRICITY REQUIREMENTS •RESIDENTIAL •BUSINESS •MISCELLANEOUS CALCULATE PRELIMINARY PEAK DEMAND CALCULATE REVISED PEAK DEMAND CALCULATE PEAK SAVINGS •ANNUAL SAVINGS DUE TO SUBSIDY •PEAK CORRECTION FACTOR (FROM C9NSERVATION MODULE) RED PEAK DEMAND MODULE FIGURE 8.5.3.12 II JFIGURE8.5.3.13 .,11 !;1 FUTURE ECONOMICS &'j OPERATING GUIDELINES 1 j j !1 I -I '] ,] I ] .------_..- ! j .j I,} EXISTING UNITS & ALLOWABLE TECHNOLOGIES OPTIMIZED GENERATION PLANNING (OGP)PROGRAM INFORMATION FLOWS HOURLY BASED PEAKS &ENERGIES OPTIMIZED GENERATION PLANNING (OGP) .J,..EVALUATE RELIABILITY ......., + EVALUATE SELECT UNIT ..... ALL CHOICES SIZES &TYPES STUDY .·WITH"L.OOK~AHEAD"I··.. ~ALL YEARS ~~CALCULATE OPERATING & INVESTMENT COSTS 4~ USING "LOOK-AHEAD" ~....I........._-~.-.... CHOOSE LOWEST COST ADDITIONS & CALCULATE CURRENT YEAR'S COSTS I ........ ,.. ..........J3.ESU.LIAI'YTQeI1MUM ..~._...•I···· EXPANSION PATTERN ·?-==-==··==--=t1-0IJTPtJT--1-_._---_._._._------_._--_.--_..__..~-_.._.._-----------_._-_._---_._._-._------_........._-_. &DOCUMENTATION OF NEAR-OPTIMUM PLANS 20l6 WEEKEND DAY 12a4 PI =MINIMUM RATING (MW) 24 . INITIAL LOAD .a 20128 WEEKDAY MODIFIED LOAD 4a II r I II II rI II HOUR HOUR OPTIMIZED GENERA TION PLANNING EXAMPLE OF CONVENTIONAL HYDRO OPERA TJONS FIGURE 8.5.3.14 o 20 30 40 50 60 10 70 80 20101990199520002005 ! I IALTER~A1iIVE Oil PRICE P~OJECTIONS -$/bbl (1985 $) , i , N01'E:PERCENTAGES IAR~ I 'AVERAGE ANNUAL GRpw;TH RATES FOR S-YEAR PERIODS FOR COUPOSITI!CASI ONL Y / SHCA CASEI ' I v/COMPOSITE CASE I 1 k ,/,}.O% I .~WHARTON CASE i ~/"'~~i i .--::;::;!,-- ~~ -.4%- I,. i 1 50 o 1985 10 30 40 20 60 70 :0 ~ 10m... -I o LLo Woa: 0- C -Ia: ~ FIGURE 8.5.4.1 '-----''-'---""~__,,~L-...L---...;\.----...i >..---i.....:L.i L.--.-...-----..J ~~t:-------i i~--· 700.I ••II I i I •Ii' 600 I I I I U I I I I NOTE:PERCENTAGES ARE AVERAGE ANNUAL GROWTH RATES FOR S-YEAR PERIODS FOR COMPOSITE CASE AND HISTORICAL DATA ONLY -1----3 .6 % v,3.6% WHARTON CASE- COMPOSITE CASE PROJECTIONS SHCA CASE I I 400 I I I :,:I • 0.9%1.0%0.9%1.2% 1.6% 300 t-t----+----t----jf-----+--;e---+----I-------l------1---+----I- /"" 3.3% HISTORICAL ."lV ~3.3% zo-I- <C ..J ::J Q.o Q. I- ..J W OJ 200..J.-<C a: ....., """'o o o 500.. 100 I I I I I I I I I I I I 2005 20102000199519901980197519701985 .YEARS ALTERNATIVE RAILBEL T POPULA TION FORECASTS O'I ••,I I ,•I •, 1960 1965 FIGURE 8.5.4.2 ! AL TERN'~TIVE RAIL BEL THOUSEHOLDS FORECASTS !!I 201020051995200019901985197~1975 .19801965 , 1 !W l"IARTON CASE CO,~POSITE CASE !f'!SHA CASE -..,I, PROJE CTIONS ~~ ~I I ~I·I .-"""'::I I ~~I I I ~~I I I I I I I I I I I I i I •I I I I I I I I 1.2%1.3%1.1%1.3%1.7% / HISTO RICAl / / ! V V ~~! 3.:~I I ! ~i ! ! !Io , 1960 200 180 '"(fJ 0 160 0 0... "'"140 (J) C ..J 120 0 J: W 100 (J) ::J 0 80J: I- ..J 60 Wm ..J 40-<C 0: 20 YEARS NOTE:PERCE'NTAGES ARE AiN AVERAGE ANNUAL GROWTH RATES FOR 5-YEAR PERIOID~FOR COMPOSIT~CASE AND HISTORICAL DATA ONLY.FIGURE B.5.4.3 ~'-------'-----J \...-----I ~--'~'-------''-"-----'-------.J ------.J .-----J ~'-------.J '-----J ._.__I L_~l--..;~ ~ 6000 '"..s::5000 ~ (!) "'" ~4000-I- 0. ~ ;::)3000 CIJ Zoo >-2doo (!) a: wz W 10100 AL TERN A TIVE ELECTRIC ENERGY DEMAND FORECASTS AT POINT OF USE CO~~POSITE CASE SHCA CASE ~W HARTON CASE -;:J PROJEC TIONS ~~ ...?- I I W p-I I I I I I ~I I III.IIIIIII I I I !I I I I I IIIIIIIIIIIIIIHISTORICAl1.4%1.9%1.0%1.1%2.5% 7.8Y / 7 V ';' o 1960 1965 1970 1975 1980 1985 1990 YEARS 1995 2000 2005 2010 NOTE:PERCENTAGES ARE AVERAGE ANNUAL GROWTH RATES FOR 5-YEAR PERIODS FOR COMPOSITE CASE AND HISTORICAL DATA ONLY.FIGURE B.5.4.4 201020052000199519901985198P197519701965 , i W HARTON CA~P l- I PROJE PTIONS ~~I ~~I I !~~l . I !I ~~I I I I I I I I I I IIIII I i I I J I I I I I 1.4%1.9%1.0%1.1 %2.5% i I II HISTO FJICAl i V V 113.0%, 14.4~llYI i V I II ALTERN'ftJTIVE Ef ,':;T,RIC PEAI<DEMAND FORECASTS 1 !: Ii AT POINT OF ,USE I COMPOSITE CASE o • 1960 1000 800 ",~ '.~ '"a 600 z« ~ 'Wa ~ 400 «w Q.. 200 NOTE:PERCENTAGES ARE AVERAGE,ANNUAL,'GROWTH RATES FORS";YEAR PERIO'D~FOR COMPOSITE CASE AND HISTORICAL DATA ONLY. YEARS FIGURE 8.S.4.S ~;~L..-..-.J~<-----J--~'.~'-........--l'-----''---.:~------.;'------'---;