HomeMy WebLinkAboutAPA4036-
TK
1425
.S8
ES8
no.4036
TASK 7
ENVIRONMENTAL STUDIES
DRAFT WILDLIFE MITIGATION OPTION PAPER
APRIL 1982
-
't
-
-
.....
./
-n)
l4d-.5
~S~
E5'6
ro _4a3fJ
ALASKA POWER AUTHORITY
SUSITNA HYDROELECTRIC PROJECT
Task 7
ENVIRONMENTAL STUDIES
DRAFT WILDLIFE MITIGATION OPTION PAPER
April 1982
Prepared by:
Terrestrial Environmental Specialists,Incorporated
R.D.1 Box 38'8
Phoenix,New York I 13135
for
Acres American,Incorporated
Liberty Bank BUilding
Main at Court
Buffalo,New York 14202
ARLIS
Alaska Resources
Library &Information Servtces
JUlchorage,~aska
,-
-
-
,-
......
,-
F-
!
DRAFT WILDLIFE MITIGATION OPTION PAPER
INTRODUCTION
This paper,together with the Susitna Hydroelectric Fish and
Wildlife Mitigation Policy,represents the product of the wildlife
mitigation planning that has taken place during the two-and-one-half
year feasibility study and license application effort.Presented are
approaches to mitigate impacts predicted to occur if the Susitna
hydroelectric project is constructed.This paper does not,however,
reflect decisions made prior to this study--the location of such
project facilities as the access road,forexample--that have a
mitigDtive effect.Such decisions indicate that the planning process,
from its early stages,included a certain level of mitigation.This
paper addresses impacts that could not be avoided during that phase of
the project.
The purpose of the program described herein is to insure that the
negative impacts on wildlife resources that 'Ni11 occur as a result of
the Susitna project will be mitigated to the greatest extent possible.
The program was developed according to the approach described in the
Susitna Hydroelectric Fish and Wildlife Mitigation Policy.It must be
understood that achieving an appropriate level of mitigation for a
project such as Susitna is complicated and requires considering a broad
range of problems.Some of these problems have obvious and simple
solutions;others,however,cannot be adequately solved with presently
avai lable scientific knowledge.
A major problem with many impact issues related to this project
i nvo 1ved predi cting the magnitude of the impact on the wil dl ife
resource.This difficulty was especially true for impacts dealing with
the behavior of animals and less so for those involved in quantifying
habitat loss..In many cases,the 1ack of preci se estimates of the
number of animals that could be impacted also complicated planning of
the appropriate level of mitigation.Thus,for the purpose of
miti gation pl anning,in cases where preci se popu 1ati on estimates were
1
-
-
-
-
r
,I
r
1
I,
lacking and where the impact is dependent upon behavioral responses of
the animals,a worst-case impact level was assumed.It was felt that
this conservative approach would establish the degree of mitigation
planning necessary to insure that the resulting benefit to the wildlife
resource at least equaled the negative impacts brought about by the
project.
Assessing the impacts and associated mitigation options
demonstrated that no single approach was suitable to address all impact
issues effectively.The analysis of mitigation options identified two
distinct types of impact problems pertaining to the issue of
mitigation.The first type of impact (Type 1)affords practical
options for mitigation.The second type of impact (Type 2)is one in
which no conventional options exist,impacts are difficult to predict
and quantify,and current scientific knowledge regarding the issue is
so limited that research efforts would be required that are beyond the
.app 1i cant IS reasonab 1e respons ibil i ty.Type 2 impacts are obvi ous1y
the most demanding in a mitigation program.
The present program was formulated with these two types of impact
in mind.Where pr,actica1 mitigation options existed,they were
reviewed,and the most appropriate and promising are discussed here.
If additional study needs were identified,they were also included in
the program.To deal with Type 2 impacts and with those Type 1 impacts
where practical solutions did not totally mitigate the impact,some
unconventional actions were incorporated into the program.Several
such innovative options were considered,and,again,the most promising
are presented.
This report presents the mitigation program on the basis of the
two types of impacts described above.Also attached,is documentation
of the analysis of mitigation options,in particular,those pertaining
to Type 1 impacts.Detai 1s of the basel ine information and impact
'.predictions for each resource issue are referenced to the appropriate
sections of the feasibility report.
2
"'...
r
!
I
-
The mitigation program outlined in this report should,if
implemented,serve to benefit the overall wildlife resource of Alaska
to a degree which will at least offset the negative consequences of the
Susitna project.The options available for mitigating these losses
have been limited to a great extent by the fact that the key species
involved are wilderness species;thus,conventional management
techniques are often inappropriate.Moreover,compared to information
on the wildlife resource in many other portions of the country,less is
known about the basic life history,predator/prey dynamics,and habitat
requisites of Alaskan wildlife.
The Alaska Power Authority has committed to additional studies to
quantify impacts further and to refine mitigation plannin.g and
techniques.Thus,the mitigative actions delineated in this paper will
be further developed and adjusted on the basis of additional studies.
TYPE 1 IMPACTS
The following impacts are those for which some conventional
mitigation options,ranging from avoidance through compensation,have
been identified.The options described should be useful in
lessening the negative impacts identified.Also identified with each
impact issue are additional study needs.These are study efforts that
should be conducted prior to implementing the mitigation option.In
most cases,the indicated study needs have been proposed for Phase II
of the Susitna studies.Not included in this category are monitoring-
type study efforts that are part of the mitigation program.
Watana and Devil Canyon Impoundments -Cliff-nesting Raptors
Impact -As a result of inundation,a total of 42.5 km of good nesting
cliffs will be lost.This reduction in the number of available
nesting sites will increase the importance of the remalnlng
25.8 km of good nesting cliffs in the vicinity of the proposed
impoundments.
3
3.2(c)(iv)
3.6(a)(iii)and 3.6(b)(iii)
....
(a)
Reference Sections -Baseline:
Impact:
Mitigative Action-
1.Recreation facilities could be so located to avoid
bringing people close to cliff-nesting sites.Such place-
ment would be most appropriate at nesting sites that would
~not be disturbed by other project components.
-
,....
2.Activities associated with clearing woody material from
the impoundments could be scheduled to avoid at critical
times for the raptors t those areas where suitable nesting
habitat is expected to remain following flooding.
3.If the raptor population is reduced because of a lack of
suitable nesting sites t consideration could be given to
erecting artificial nest platforms on some of the
remaining cliffs.
Anticipated Results -Although it would be impossible to avoid this
impact t the magni tude of the impact wou ld be mi nimi zed by adopt ing
these measures.The unavoidable loss of nesting sites is
considered as a T~pe 2 impact issue.
Additional Study Needs -None
a.The reference sections refer to the appropriate portions of the
Susitna Hydroelectric Feasibility Report.
4
3.2(c)(iv)
3.6(a)(iii)and 3.6(b)(iii)
Northern Segment of the Transmission Line -Peregrine Falcon
Impact -That segment of the proposed transmission line from Healy to
Fairbanks will pass close to an inactive peregrine falcon
nesting site along the Tanana River.If the nest is active
during the construction period,it is possible that
construction-related activities may disturb the birds.
Reference Sections -Baseline:3.4(b)
Impact:3.8(b)
Mitigative Action -The potential for disturbing nesting peregrines
could be reduced by first determining if the nest is active,
and if so,scheduling construction in the area so as to avoid
any disturbing activities during the nesting period.
Anticipated Results -This potential impact could be avoided entirely
by taking the proposed mitigative action.
Additional Study Needs -None
Watana and Devil Canyon Impoundments'-Bald Eagle
Impact The two impoundments will result in the loss of two of the six
known active bald eagle nests and the one known inactive nest
in the area.
Reference Sections -Baseline:
Impact:
Mitigative Action -
1.During the clearing of woody material from the impoundments,
clumps of tall spruce trees (where they are available)could
be left uncut along the shoreline at one-to two-kilometer
5
-\
-
..-
~
I
-
intervals.The selected trees would be located in the cleared
zone near the the normal high pool level but far enough away
to avoid their being washed away during unusually high water
periods.If adequate perching sites are unavailable,
artificial perching sites could also be provided.
2.Following inundation,monitoring of eagle nesting would help
to determine if the birds are successfully locating and using
alternative nesting sites.If the eagle population appears
to suffer by failing to use the remaining nesting
opportunities,artificial nest platforms could be erected in
suitable locations.
Anticipated Results -Although it will be impossible to avoid this
impact,the mitigative actions should at least minimize the
magnitude of the impact and possibly compensate for the loss.
Additional Study Needs -None
Watana .and Devi 1 Canyon Impoundments -l"1oose
Impact -The inundation resulting from the two impoundments will reduce
the carrying capacity of the upper basin.Downstream from Devi 1
Canyon to Cook Inlet,plant succession trends may also be altered
as a result of flow regulation.Consequently,the amount of
winter browse may be reduced over time,thereby affecting moose
that rely on this area during severe winters.
Reference Sections -Baseline:3.2(a)(i)and 3.2(a)(ii)
Impact:3.6(a)(i),3.6(b)(i),and 3.6{d)(i)
Mitigative Action -Moose habitat management programs could be
conducted along the lower Susitna River,downstream from
Talkeetna,in order to counterbalance the possible loss of winter
browse resulting from alterations in flow and also to compensate,
6
-
:~
.....
-~,
at least partially,for habitat loss in the upper basin.
Management efforts might be directed toward two general areas.
First,in order to provide improved browse conditions for moose
that range west of the Susitna,vegetation on selected river
islands could be burned,or where mature balsam poplar is present,
commercial logging could be conducted.Second,habitat management
efforts could be conducted in selected areas east of the Parks
Highway/Alaska Railroad corridor.This approach would benefit
those moose that range east of the river into the foothills of the
Talkeetna Mountains.Management efforts east of the two major
transportation corridors are desirable to reduce the need for
moose to cross these corridors;such crossings result in
substantial mortality.These selected east-side management areas
could be improved for moose by either prescribed burning,
commercial logging,or mechanical crushing,depending on the
suitability and acceptability of these techniques.
Since moose in the upper basin function as a key species in the
wildlife community of that area,habitat management efforts could
also be considered for the areas adjacent to the impoundments.
Prescribed burning is probably the only management technique that
might improve this area1s carrying capacity.Since information
concerning the effects of fire at higher elevations is lacking,
however,the suitability of this procedure is unclear.As part of
the mitigation program,then,the applicant could investigate the
feasibility of prescribed burning here and,if the technique is
demonstrated to be suitable,at least a 1imited burning program
could be developed to compensate for the reduced carrying capacity
caused by the project.
The prime focus for mitigating the loss of moose habitat should
still be the downstream area because this area is more conducive
to successful management.While the magnitude of the downstream
management program would be contingent upon the possibility of
improving moose habitat in the upper basin,its actual scope will
complement the upper basin plan and,in fact,allow for complete
7
-
.,...
r
I
I
r-
i
I
r
i'
I
I
r
I'I
il
mitigation.In other words,if it is shown that prescribed
burning will not produce the desired results,then the management
effort downstream would be increased;on the other hand,if it
appears that through prescribed burning,moose populations in the
upper basin can be increased,then the downstream program would be
reduced.If,for some reason,management efforts in the lower
basin also prove unacceptable,then a search could ensue for
alternative management opportunities.
Anticipated Results -The moose.management program would result in an
increased carrying capacity in the downstream area as compensation
both for the reduction that will occur in the upper basin and for
those reductions that may occur along the lower river.If burning
is successful,compensation would also occur in the upper basin.
Additional Study Needs -Further quantification of the habitat loss in
the upper basin is needed in order to determine the magnitude of
the management effort that wi 11 be required.For examp 1e,browse
surveys should be performed.Preliminary studies are also
necessary to identify potential areas for moose habitat management
in the lower basin.The proposed management approach is
biologically feasible.There are,however,questions concerning
land ownership,plant ecology,the acceptability of prescribed
burning to the public,and numerous other issues that win have to
be addressed in the selection of lands for management.
As indicated above,additional study is needed to determine the'
feasibility of prescribed burning in the upper basin.Research
efforts should include insuring that the currently planned BLM
burn in the Alphabet Hills,for example,provides the answers to
critical questions concerning prescribed burning and its
usefulness as a habitat management technique.The entire issue of
habitat management as a form of compensation within the upper
basin depends upon the outcome of that study effort.
8
-
Watana Impoundment -Dall Sheep
Impact -The impoundment created by the Watana dam will seasonally
flood a portion of the Jay Creek mineral lick and,thus,may
negatively impact the sheep population that currently uses it.
Reference Sections -Baseline:3.2(a)(viii)
Impact:3.6(aHi)
Mitigative Action -The schedule for clearing woody material from the
Watana impoundment could be arranged so that no clearing
activities would take place within 2 kilometers of the Jay Creek
lick during the months of May and June when sheep use the area.
Following inundation,monitoring efforts should be undertaken to
document the reaction of sheep to the change and the extent to
which they continue to use the lick.If the lick is abandoned
following the impoundment filling or if the use of it is
substantially reduced,an artificial lick could be established
using mineral blocks specifically designed to match or to improve
upon the chemical composition of the current lick.The artificial
lick could be placed within the natural range of this sheep herd
and situated where sheep would be less vulnerable to wolf
predation than they currently are when they use the Jay Creek
1i ck.
Anticipated Results -Avoiding the Jay Creek lick during clearing of
the impoundment should allow the sheep to continue using the lick
prior to flooding.If reservoir filling results in abandonment
of the lick,the creation of an artificial lick will compensate
for the loss attributable to the project.
Additional Study Needs -It will be necessary to determine the chemical
composition of the Jay Creek lick in order to prepare comparable
mineral blocks should the need arise.Continued monitoring of
sheep should be done to gain an understanding of the degree of
their use of this and other licks and,thus,of the severity of
any negative impact thay may occur.
9
,....
I
f"""
I
!
-
Watana Impoundment -Caribou
I.Impact - A possibility exists that the ice conditions and/or any
floating debris associated with the Watana impoundment will act
as a barrier to migrating caribou.
Reference Sections -Baseline:3.2(a)(iii)
Impact:3.6(a)(i)
Mitigative Action -Any negative impacts resulting either from ice
conditions or floating debris could be minimized through the
following actions:
1.Prior to flooding,all woody material could be totally cleared
from the impoundment.
2.If floating debris develops so as to represent an impediment
to caribou or any other big game species,a removal program
could be immediately undertaken.
3.If,while enroute to its calving area,the Nelchina herd
encounters hazardous ice conditions in the reservoir,it may
completely resist crossing the impoundment.If this situation
occurs,the herd will either develop a new calving area or
transfer major calving activities to an area used only
marginally or occasionally as a calving area.In that event,
the applicant could petition the appropriate state or federal
agencies to take whatever action is necessary to insure that
the herd will remain undisturbed while it establishes its new
calving site.
4.In order to determine when the above-mentioned measures are
needed,the Nelchina herd should be monitored during filling
of the reservoir and after construction is completed.This
monitoring should be conducted during the late winter period,
through calving,and as far enough into the post-calving
10
"...
r-,
I
period as is necessary to determine if any aspect of the
impoundment is interfering with the herd's movement.
Monitoring would have to continue until the results
demonstrate that the impoundment does not represent a barrier
or until the herd has successfully readjusted to any changes
brought about by the project.
Anticipated Results -Since it is difficult to predict either the
likelihood of this impact1s occurring or the magnitude of any
negative consequences that could result,it can only be
anticipated that taking the stated actions will lessen the
probabi 1ity of a negati ve impact as well as reduce.the magni tude
of any impact that does occur.Since the possibility exists that
a negative impact could occur regardless of any preventative
measure,this issue is also considered as a Type 2 impact.
Additional Study Needs -Although no specific studies are needed to
implement the above action,continued monitoring of the Nelchina
herd would be valuable so that if the animals undertake a major
river crossing prior to inundation,the area used for crossing
could be accurately defined.In this way,once the important
areas are clearly 'identified,they can be monitored following
flooding.The upp~r Susitna-Nenana subherd should also be so
monitored because thi s herd occupi es an area that may represent an
alternative calving area for the main herd.
II.Impact -The activities associated with clearing woody material
from the Watana impoundment will disturb caribou migration to
the calving area south of the river and/or post-calving
movements to the area north of the river.
Reference Sections -Baseline:3.2(a)(iii)
Impact:3.6(a)(i)
Mitigative Action -Clearing schedules could be flexible enough so that
no clearing activity will take place in the areas used by
migrating caribou during the time of their movements.To
11
,....
determine if the clearing activities might conflict with the
herd's movements and thus need to be modified,the Nelchina herd
could be monitored during late winter and early spring,and again
following calving.
In addition,if woody material is burned following clearing,uncut
travel lanes could be left for caribou to use.Three or four
lanes each at least 0.8 km-wide and continuous from one side of
the impoundment zone to the other would probably be sufficient.
These lanes should be located between Deadman and Jay creeks and
the woody material within them removed immediately prior to
inundation.These lanes could be located at points that are
expected to be safe crossings after the impoundment has been
filled,so that the herd could continue to use the same crossing
locations.
Anticipated Results -An appropriate clearing schedule would minimize
any disturbance of the Nelchina herd's migration during clearing
of the impoundments.
Additional Study Needs -Although no specific studies are needed in
order to implement the action described above,continued
monitoring of the Nelchina herd should be conducted so that any
impact could be predicted and the appropriate mitigative steps
taken.
Construction Camps/Vi 11 ages and All Access Roads -Red Fox,Bears,
Wolverine,Pine Marten,Ground Squirrel,Gulls,and Raven
Impact -These species will be negatively affected by any illegal
feeding by personnel associated with the construction and
operation of the project.Improper disposal of garbage would also
result in a negative impact to these species.
Reference Sections -Baseline:3.2(b)(i),3.2(b)(ii),3.2(a)(vi),
3.2(a)(vii),3.2 (c)(iii),3.2(c)(iv),
and 3.2(d)(i)
Impact:3.6(a),3.6(b),and 3.6(e)
12
"...
......
Mitigative Action -The following options could be taken:
1.Secure garbage containers could be available in all work
areas,and all refuse could be promptly collected and either
incinerated or disposed of in the 1andfill.
2.All landfills could be covered with soil on a daily basis •
3.All camp facilities (especially landfills)could be securely
fenced,with the bottom edge of the fence buried at least
0.5 m (18 in.)below the ground surface.
4.Work crews could be hired and charged with promptly picking up
all discarded refuse from work areas and along all roads
associated with the project.
5.A mandatory education program could also be developed for all
project personnel and designed to educate workers to the
problems,both biological and legal,associated with feeding
wi 1d anima 1s.
6.State laws prohibiting the feeding of wi 1d animals should be
strictly enforced,and repeated violators could be dismissed
from their employment and permanently prohibited from future
work on any aspect of the project.
Anticipated Results -The above steps will minimize and,itis hoped,
avoid the negative consequences of this impact.
Additional Study Needs -None
Construction Camps and Villages -Red Fox and Wolf
Impact -The housing of domestic dogs at the camps and villages creates
the potential for introducing rabies into the native canid
population.Improper dog control could also produce a population
of feral dogs.
13
Reference Sections -Baseline:
Impact:
3.2(b)(i)and 3.2(a)(iv)
3.6(a)(i),3.6(a)(ii),3.6(b)(i),
3.6(b)(ii)
and
.-
-
Mitigative Action -During the construction period,dogs could be pro-
hibitedat the camps and villages,thereby avoiding this potential
impact.During operation,dogs could be allowed in the permanent
town and the impact could still be avoided,or at least minimized,
by requiring registration of all dogs.To prevent the intro-
duction of rabies,certification of immunization should be
required.The potential problem of dogs'becoming feral could be
reduced by requiring dogs to be under the control of the owner at
all times~Any dog found outside of the camp area and not under
direct control of the owner could be destroyed by camp security
personnel if reasonable attempts to capture the animal fail.
Anticipated Results -If properly enforced by camp authorities,these
actions will greatly minimize the likelihood of introducing rabies
into the native canid population as well as reduce the possibility
of establishing a feral dog population.
Additional Study Needs -None
Access Roads?Construction Camps and Recreation Facilities -All
Upstream Furbearer and Big Game Species
Impact -These project components wi 11 result'in increased human
acti vity and resu lting di sturbance and harassment of wil dl ife .
Reference Sections -Baseline:3.2(a)and 3.2(b)
Impact:3.6(a),3.5(b),and 3.6(e)
Mitigative Action -The specific steps that could be taken to mitigate
this impact differ during the construction and the
post-construction periods and are thus discussed separately.
14
~
I
I
....
-
....
During the construction period,all project personnel could have
no greater access to the upper basin than that available to the
general public except,of course,access to the actual
construction sites.All project personnel could be required to
travel directly from the start of the access road to the camp or
work area without stopping,except for emergencies.Personnel
could be prohibited from leaving the access roads or work sites
for any reason,including to hunt or trap.Construction managers
could attempt to schedule the movement of construction vehicles to
leave uninterrupted "windows"of traffic during which animals will
be able to cross the access roads without encountering vehicles.
Such uwindows"would be particularly important during the time
period extending from two hours before sunset to two hours after
sunrise.
During the post-construction period,when the road (at least to
Devil Canyon)will be open to the general public,it will be the
responsibil i,ty of the Alaska Department of Fish and Game to
monitor the status of the area1s big game populations to a degree
sufficient to determine if a detrimental harvest level is taking
place.Should such a harvest level be detected,ADF&G could
implement the necessary regulations to correct the situation.To
minimize undue disturbance of wildlife and to prevent damage to
vegetation,ATV use could be barred from originating at project
facilities on the north side of the river.In other words,no
ATVs would be permitted to pass the Devil Canyon dam site.If it
is decided to permit publ icaccess as far as the Watana dam,
access from the road or dam sites could be allowed only by foot or
on horseback.When a specified destination exists (the Watana
dam),there will be a t~ndency for the present network of ATV
trails from the Denali Highway to be extended.Therefore,a
prohibition of ATV travel to the Watana dam site from the Dena 1i
Highway may also be appropriate.
Anticipated Results -The measures described above will help minimize
the impact of disturbance on the wildlife resource.Since this
impact can not be totally avoided,it is also considered as a Type
2 impact.
15
'"''''
.....
"
Additional Study Needs -None
All Access Roads -Moose
Impact -Moose may be k"illed as a result of collisions with vehicles
using both the main access road and the access roads to borrow
areas.
Reference Sections -Baseline:3.2(a)(ii)
Impact:3.6(c)(i)and 3.6(e)(i)
Mitigative Action -The following steps could be taken to minimize this
impact:
1.Areas of high collision potential could be identified and
warning signs erected to alert motorists of the possibility of
encountering moose.
2.Speed limits could be established to limit travel to speeds
which will lessen the potential for collisions with animals
while still permitting the timely movement of vehicles.
3.During winters,when snow is quite deep,numerous pull-off
areas could be plowed clear to permit moose to move off the
road.Appropriate areas could be identified based on the
location of winter moose concentrations and associated snow
depths.
4.In conjunction with other worker orientation/education
programs,an attempt could be made to impress upon workers the
value of wildlife and the need to avoid killing animals
through collisions with vehicles.
Anticipated Results -The above actions will minimize this impact •
Additional St~dy Needs-None
16
Borrow Areas,Access Roads to Borrow Areas,and Temporary Camp and
Construction Areas -All Furbearer Species,Many Avian and Small Mammal
Species,and All Big Game Species Except Dall Sheep
Impact -These project components represent a temporary loss or
alteration of habitat for the indicated wildlife resources.
Reference Sections -Baseline:3.2
Impact:3.6(a),3.6(b),and 3.6(c)
Mitigative Action -This impact could be mitigated through a combined
program of restoration and compensation.Since the use of these
project components wlll be temporary,efforts could be undertaken
to restore the above-mentioned areas following their use.All
topsoil removed from these areas cou 1d be stockpil ed and saved.
In addition,all topsoil removed from areas that will be
permanent ly di sturbed cou 1d be saved and added to these
stockpiles.When an area is no longer in use,the topsoil could
be redistributed and the area regraded,if necessary,to avoid
erosion.Restored ar~as could then be seeded lightly with grasses
and fertilized to stimulate the initial growth of native
vegetation.During the first year of restoration,a fertilizer
mix high in phosphorus (such as N,P,K,10-20-10,or 8~32-16)
could be applied in amounts sufficient to supply 85-110 kg of
nitrogen per hectare.During the second growing season,these I~~
areas would be fertilized at half the initial treatment rate.
During the third growing season,they would be fertilized at
one-third the initial rate.The placement of willow cuttings in
the ground during seeding of grasses could also be performed to
increase the habitat value of the area for species such as moose.
Since a restoration effort would probably not totally restore the
disturbed areas to the same level of usefulness to wildlife that
currently exists,some compensation measures would be needed in
regard to this impact.Compensation efforts directed at loss of
moose habitat caused by the impoundment and other project
facilities could be increased to cover the reduced carrying
17
-
-
-
capacity brought about by these project components.Efforts would
be concentrated along the lower Susitna River and are described in
the section of this report headed Watana and Devil Canyon
Impoundments -Moose.
Anticipated Results -It is impossible to determine how much the
proposed restoration effort will successfully mitigate the habitat
losses resulting from these temporary use areas.The proposed
effort should,however,restore the areas involved to some degree
of usefulness.Furthermore,by increasing the moose compensation
effort downstream,the loss attributable to these temporary areas
should be mitigated.
~dditional Study Needs -At present,no specific studies are required
to determine the feasibility of this approach,other than those
mentioned in regard to the moose habitat effort.Some additional
site specific work will have to be done prior to restoration in
order to insure that the most appropriate combination of seeding
and fertilizer is used,including the application rate and
timing.
Air Traffic -All Big Game Species,Raptors,and Trumpeter Swans
Impact -These species will be negatively impacted as a result of
disturbance from air traffic,especially low-flying,large
hel icopters.
Reference Sections -Baseline:3.2(a),3.2(c)(iii),and 3.2(c)(iv)
Impact:3.6(a)
Mitigative Action -The following restrictions could be enforced to
reduce the impact of air traffic on wildlife:
1.All air traffic could fly directly to and from the camps or
work sites with no unnecessary diversions.
18
-
2.Flight distances and weather permitting,all project-related
air traffic could maintain an altitude of at least 150 m (500
ft.)above ground throughout the upper basin at all times.
.....
....
3.A minimum altitude of 300 m (1000 ft.)above ground could be
maintained in the following areas:
-caribou calving area (May and June)and any post-calving
aggregations (June and July)
-wolf dens (April through July)
-bald eagle nests (15 March -31 August),including a
horizontal restriction zone of a 0.4-km (0.25 mi)radius
-gyrfalcon nests (15 February -15 August),including a
horizontal restriction zone of O.4-km (0.25 mi)radius
-golden eagle nests (l April -31 August),including a
horizontal restriction zone of O.8-km (O.50 mil radius
-the Jay Creek sheep lick (May and June)
-trumpeter swan nests near the Oshetna River and other
adjacent areas in the upper reaches of the Watana
impoundment (May through July).
Anticipated Results -The implementation of these restrictions should
minimize the disturbance and allow,in the case of some species,
for anima'ls to become acclimated to the presence of aircraft and
their disturbing influence.
Additional Study Needs -Prior to the continuation of air-supported
activities,additional surveys should be conducted to determine
sensitive locales where restrictions are required.After
19
"~~--~------------------~--~-------
-
r
inundation,some of these sensitive areas will likely change,and,
therefore,at least three to five years of monitoring should
follow flooding to lpcate sensitive sites.Following this study
/
period,and for as long as air support is needed,the locations of
such sites could be updated annually on the basis of both
incidental information and surveys scheduled at three-year
intervals.
TYPE 2 IMPACTS
The following list of impacts are considered Type 2 impacts;in other
words,they are impacts for which no conventional form of mitigation
was identified.They could not be avoided by modification of the
project without affecting power output;they could not be effectively
minimized or reduced;and no habitat manipulation options were
available to use in a compensatory effort.Some of the impacts listed
below were also identified as Type 1 impacts.They are included here
because it is likely that the options proposed in the discussion of
Type 1 impacts will not totally mitigate the impact.Inmost of the
Type 1 impacts also discussed below as Type 2,the proposed options
served to minimize the magnitude of the impact but will not compensate
for the remaining level of impact.The impact issues are first
identified,including a brief "description of the impact and reference
citations concerning the appropriate sections of the feasibility
report that can be consulted for more information.Following the 1 ist
of impact issues,two approaches to mitigation are presented and
discussed.
Watana and Devil Canyon Impoundments -Mink and River Otter
Impact -Creation of both impoundments and associated facilities will
result in the loss of riverine and terrestrial habitat and an
associated decrease in the available food base.
Reference Sections -Baseline:3.2(b)(iv)and 3.2(b)(v)
Impact:3.6(a)(ii),3.6(b)(ii),and 3.6(c)(ii)
20
-
,.,..
Watana and Devil Canyon Impoundments -Pine Marten
Impact -Creation of both impoundments and,to a lesser degree,
associated facilities will result in the loss of pine marten
habitat.
Reference Sections -Baseline:3.2(b)(ii)
Impact:3.6(a)(ii)and 3.6(b)(ii)
Watana and Dev i1 Canyon Impoundments - Forest-dwe 11 ing and Riveri ne
Bird and Small Mammal Species
Impact -The two impoundments will inundate a large percentage of the
forested habitats in the vicinity of the project,with a resulting
negat ive impact on those bird and sma 11 mammal spec ies that
utilize these habitat types.
Reference Sections -Baseline:·3.2(c)and 3.2(d)
Imp ac t :3.6 (a){iii)an d 3.6 (b)(iii)
Watana and Devil Canyon Impoundments -Bald Eagle
Impact -The two impoundments may result in reduction of bald eagle
feeding habitat.
Reference Sections -Baseline:3.2(c)(iv)
Impact:3.6(a)(iii)and 3.6(b)(iii)
Watana and Dev i1 Canyon Impoundments -Black Bear and Brown Bear
Impat -Both black and brown bears will be negatively impacted by the
loss of habitat caused by the two impoundments.Black bears will
probably be more severely affected than brown bears from this
habitat loss.Both species may also suffer if the operation of
the Dev;1 Canyon dam reduces the number of spawning salmon between
Devil Canyon and Talkeetna.
21
Reference Sections -Baseline:
Impact:
.,...
3.2(a)(vi)and 3.2(a)(vii)
3.6(a)(i),3.6(b)(i),3.6(c)(i),
3.6(d)(ii)and 3.6(e)(i)
Operation of the Devil Canyon Dam -Downstream Beavers
Impact -Changes in the flow regime caused by the Devil Canyon dam will
affect beavers living downstream from the dam.Although increased
winter flows may be of benefit to beavers,reduced summer flows
may limit available sloughs for use by these aquatic furbearers.
The daily fluctuations in flow may also cause unstable ice
conditions and make it very difficult for beavers to maintain
winter food caches.
Reference Sections -Baseline:
Impact:
3.2(bHiii)
3.6(d)(iii)
Watana and Devil Canyon Impoundments -Wolf and Wolverine
Impact -The two impoundments and their associated facilities will
result in a loss of habitat for both wolves and wolverines.These
two species,particularly wolf,will also be impacted by a
reduction in the number of moose present in the area.As a
result,the long-term carrying capacity for wolves and wolverines
will be lowered by the project.
Reference Sections -Baseline:3.2(a)(iv)and 3.2(a)(v)
Impact:3.6(a)(;),and 3.6(b)(i),and 3.6(c)(i)
Watana and Devil Canyon Impoundments -Cliff-nesting Raptors
Impact -As a result of inundation,a large percentage of the good
cliff-nesting sites will be lost.If raptors do not use
alternative nesting sites successfully,then the population of
cliff-nesting raptors in the area will be reduced.
Reference Sections -Baseline:3.2(c)(iv)
Impact:3.6(a)(iii)and 3.6(b)(iii)
22
3.2
3.6(a),3.6(b),and 3.6(c)
-,
Watana Impoundment -Caribou
Impact -The possibil ity exi sts that ice conditi ons associ ated with the
Watana impoundment wi 11 act as a barrier to migrating caribou.If
.other mitigation measures fail to avoid this impact,the Ne1china
herd could suffer some level of negative impact.
Reference Sections -Baseline:3.2(a)(iii)
Imp ac t:3.6 (a )(i )
Permanent Access Roads and Camp Facilities -All Furbearer Species,
Many Avian and Small Mammal Species,and All Big Game Species Except
Da 11 Sheep
Impact -These project components will represent a permanent loss of
habitat for the indicated wildlife resources.
Reference Sections -Baseline:
Impact:
Access Roads,Construction Camps and Recreation Facilities -All
Upstream Furbearer and Big Game Species
Impact -These project components will result in increased human
activity,resulting in disturbance and harassment of wildlife.
Although this impact can be minimized to some degree,it cannot be
totally avoided.
Reference Sections -Baseline:3.2(a)and 3.2(b)
Impact:3.6(a),3.6(b)and 3.6(e)
Mitigative Action -Without question,the most difficult aspect of
dealing with Type 2 impacts is determining the level of mitigation
needed to offset the anticipated impacts.The fact that Type 2
impacts are not only difficult to predict but,more importantly,
difficult to quantify means that any proposed mitigative action
23
-
-
must be flexible enough so that,as the actual impact is
monitored,the mitigation program can be adjusted in such a manner
as to reflect an appropriate level of effort.Because of the
problems associated with determining the appropriate level of
mitigation to propose in regard to Type 2 impacts,it will
therefore,be necessary for the final decision to be based
primarily upon a negotiated agreement among all concerned
parties.
In order to deal effectively with the difficult task of mitigating
Type 2 impacts,the applicant could take two actions.The first
concerns the concept of replacement lands.This idea,proposed by
the Alaska Department of Fish and Game,was reviewed and found to
have sufficient merit to warrant its inclusion in the Susitna
wildlife mitigation program.
In brief,the goal of using replacement lands as a form of
mitigation is to protect the wildlife resource in some other area
from the types of future development that would be detrimental to
the resource.In the short term,a land set aside does not
compensate for losses resulting from the Susitna project because
no new wildlife resources or habitat would be created.When
replacement lands are secured,however,the long-term protection
of the resource can be considered a benefit that would help to
offset the negative consequences of the Susitna project.Without
such action,there would be a continual decline in the resource.
Since,from a management standpoint,little can presently be done
other than to protect lands occupied by the wilderness-type
species involved,this approach does represent a viable solution
to at least a part of the mitigation problem.An associated
advantage is that the resource.would be safeguarded and would thus
be available for management at some future time,when new
techniques may be available.
There are,admittedly ,several questi ons associ ated wi th us i ng
replacement lands as a form of mitigation.The first is
24
---=,--_.-----~-----------------------
-
determining which lands to designate as replacement lands.
Because many Type 2 impacts are not habitat related and since all
land is not of equal value as wildlife habitat,it would not
suffice simply to designate an equal amount of acreage as
replacement for the habitat that will be impacted.Both the
overall quality of the habitat must be considered as well as its
critical value to certain species.For some species,such as
moose and caribou,such a determination will not be difficult,
since they tend to use certain areas,like calving grounds or
riparian wintering areas.The identification of such critical
areas for other species,however,will be more difficult.
Therefore,the selection of replacement lands must consider two
major elements:critical areas for important species that can be
identified and the total habitat value of the area in question.
Depending upon the outcome of this selection analysis,the amount
of land set aside as replacement might be greater than the area
impacted by the Susitna project,or if several crit i ca 1 areas are
located,or land of greater habitat value is found,the total land
selected may be less than that impacted by the project.
The types of activities allowed on such land should"be emphasized.
Any use that would not be detrimental to the wildlife resource
could be permitted.Certain types of mineral extraction,hunting,
trapping,and most recreation activities could be permitted if
they do not interfer~with seasonally important wildlife
activities,such as caribou calving.In other words,the land
would be open to the public for a wide variety of uses as long as
such uses do not result in a reduction in the wildlife resource.
The second action that the applicant could take to mitigate Type 2
impacts is the establishment of a wildlife research station in the
upper Susitna basin.The purpose of a research station is to
compensate for the negative impacts of the project by advancing
understanding of the ecological relationships of the wildlife
resource and thus improving the chances of successfully managing
that resource in the future.As stated in the introduction//
25
-----~--......--------._---,----------_........---------
or-
I
a major problem encountered during the Susitna impact and
mitigation studies has been the lack of a solid research base
concerning many species.Compared to wildlife species in other
parts of the country,very little is presently known about the
basic life history,predator/prey dynamics,and habitat
requisites of many species inhabiting Alaska.The goal is,
therefore,to further our knowledge of wildlife ecology and to
collect data in such a manner as will benefit wildlife throughout
Alaska,in particular interior Alaska.In addition,since most of
the past research in Alaska has focused on a few areas,such as
Point Barrow,Prudhoe Bay,Fairbanks,along the Trans Alaska
Pipeline,and the Kenai Peninsula,information concerning wildlife
in other parts of Alaska is especially lacking.The upper Susitna
basin and,in general,that area south of the Alaska Range has
only recently begun to attract concentrated research efforts.
The concept of a permanent research stat i on has addit i ona 1 meri t,
since its work could be combined with the monitoring efforts
called for in the mitigation policy statement.This approach
would permit the determination of the effectiveness of mitigation
efforts as well as the documentation of-impacts that actually
occur as a result of the project and would,thus,be useful in
predicting and mitigating the impacts of future development
projects.
Contributing to the attractiveness of a wildlife research station
is the valuable opportunity that will exist.First of all,
permanent support facilities will be available at the two dam
sites.This arrangement would greatly reduce the overall cost of
research activities,since the logistic expenses associated with
operating in remote wilderness areas is often the major cost item
in research projects.Second,a sound and comprehensive data base
will already exist,since a minimum of four to five years of
baseline data will be cqllected prior to the initiation of
construction.Thus,research projects could be directed at
specific questions without first obtaining the rudimentary
26
____~~~aa:;.iili¥J~-_
..,.
.-
-
understanding of the area that is usually needed.By capitalizing
upon this opportunity,researchers could offer overall benefits to
Alaskan wildlife that would offset the negative consequences of
the Susitna project.
Obviously,details concerning the organization and operation of
the research station would depend upon negotiations between the
Power Authority,FERC,and the appropriate state agencies.For
basic consideration,however,the following is proposed.If
approved,the station could be supported by the Power Authority
for a minimum of 20 years.This time period was selected both
because of the long life spans of many big game species and also
because of the need to conduct long-term research if acceptable
levels of data val,idity are to result.Following the 20-year
minimum time period,the Power Authority would review the need for
additional research efforts with FERC and,based on that review,
either terminate the facility or renew the commitment for
support of the facility.
The Power Authority would provide basic support for the station,
including office and laboratory facilities,'housing for permanent
and transient investigators,funding for a permanent director and
support staff (secretarial/clerical),and use of air-support
facilities.The initial development of the station would also be
funded by the Power Authority and wou ld include research items
such as laboratory and communications equipment,computer
terminals,and office supplies.
In ~ddition to establishing the station,the Power Authority would
provide an annual base amount of research funds to be divided
evenly between the Alaska Department of Fish and Game and the
University of Alaska.These monies would be used by the two
organizations to conduct research directed at documenting the
impacts of the project as well as analyzing the ecology of the
species involved.The director of the station would have
authority to approve and coordi nate a 11 research efforts conducted
27
----_._,,--------.--
-
-
"""
-
through this facility.In addition to the base level funds
provided by the Power Authority~the two participating
organizations would be allowed to utilize funding from other
sources,with the Power Authority providing the above-mentioned
facil ity and logi st ic support.The costs invo lved in estab 1i shing
the station,the annual base funding support,and the cost of
supporting research funded from other sources would,of course,
require more detailed analyses before appropriate figures could be
included in this program.
Anticipated Results -Although Type 2 impacts are difficult to predict
quantitatively,it is anticipated that by obtaining replacement
lands and by taking advantage of the opportunities offered by a
long-term research station,sufficient benefits to the wildlife
resource would result as to compensate for the negative impacts
that will occur as a result of the Susitna project.The
mitigation monitoring program,along with associated ecology
studies conducted through the research station,will enable a
quantification of the magnitude of the Type 2 impacts that
actually occur.The flexibility associated with the level of
effort expended in securing replacement lands and research efforts
will,thus,permit a reevaluation of the situation at a later date
and allow for possible adjustments in mitigative effort to more
accurately compensate for losses incurred by the wildlife
resource.
Additional Study Needs -The key element in selecting replacement lands
would be identifying critical areas for consideration,in
combination with determining both the habitat value of lands lost
because of the project and the habitat value of candidate lands
for replacement designation.In order to assess habitat value,
the habitat analysis conducted during the early portion of
Phase I could be refined.This approach is explained in a Phase I
subtask report and may serve as a useful means of assessing
habitat value.Along with the refinement of the habitat value
analysis,initial steps could be taken to establish criteria for
identifying and selecting candidate lands that represent critical
areas for wildlife.
28
----,---------------------------~------------
,-
....
Many details would also have to be addressed in regard to the
wildlife research station.Steps could be taken to develop
preliminary cost estimates associated with establishing the
station and with providing annual support.Since the station
would also function as part of the mitigation monitoring program~
it would be necessary to estimate the level of monitoring effort
and the associated funding that would be required by the
monitoring program.To estimate how much support would be needed
to cover research activities funded from outside sources~beyond
the annual fundi ng commitment of the Power Authority ~the two
associated organizations would have to provide preliminary
estimates of the level of funding they would be able to obtain
from other sources.
29
Mitigation Options Consideration Worksheet (Draft)Page 1 of 5
Wildlife Resource
Cliff-nesting
raptors
Impact
Flooding of
nesting'
habitat
Options Considered Recommended*
-Lower pool elevation
-Avoid conf1 ict with I X
recreation facilities
-Schedule clearing to I X
avoid nest sites during
nesting period
-Consider artificial J X
nest platforms
-Rep 1acement 1ands &I X
research station
Rejected
X
Rejection Reason
Project Conflict
Bald eagle (upstream)1 Habitat loss I -Leave clumps of trees
along impoundment
-Monitor nesting after
fi 11 ing
-If necessary,provide
artificial nest plat-
forms
-Stock fish
,- -Replacement i ands &
research station
Peregrine falcon
Moose
Disturbance
due to trans-
mission line
construction
Habitat loss
in upper basin
&possible re-I
duction of
browse along
lower river
-Determine if nest site
is active
-Schedule construction
to avoid nest during
nesting period
-Lower pool elevation
-Habitat management
lower river
upper basin
X-
X
X
X
X
X
X(pend-
ing further
study)I X
x
x
Impoundment conditions may not
be suitable.Cost may not be
justified.
Probable conflict
*Recorrrnended for further consideration.
l l.I ~Itt l l l L .l
Mitigation Options Consideration Worksheet (Draft)Page 2 of 5
Wildlife Resource
Dall Sheep
Caribou
Caribou
Impact
Loss of
mineral lick
Barrier cre-
ated by
floating
debris
Barri er cre-
ated by ice
condit ions
Options Considered Recommended
-Lower pool elevation
-Schedule clearing to I X
avoid lick during May
and June
-Determine mineral I X
composition of lick
-Monitor sheep followin~X
floodi ng
-If necessary,create I X
ar t if i cia 1 1ick
-Clear only drawdown
zone
-Clear entire impound-I .X
ment
-Debris removal program,1 X
if necessary
-Monitor movements I X
-Erect fences to direct
herd to safe crossing
-Protect new calving I X
area if established
-Replacement lands &I X
research station
Rejected Rejection Reason
X I Project confl ict
X I Probably would not prevent
woody material from floating to
surface
X I May not be effective &may
conflict with other species
Caribou Disturbance
during
clearing
-No action
-Do not clear impound-
ment
-Monitor movements
-Stop clearing if herd
approaches
-Leave uncut travel
lanes until filling
X
X
X
x
x
Important to allow uninterrupted
movement prior to fill'ing
Floating debris represents a
more severe potential problem
I
I t __~t I L __.,I ._....~(i I ..I i.l {
""1\':,."-'"
Mitigation Options Consideration Worksheet (Draft)Page 30f 5
Wildlife Resource
Red fox,bears,
marten,ground
squirrel,gulls,
&raven
Red fox &wolf
Impact
III ega 1 feed-
ing by projectl
personnel
Domest ic dogs
rabies and
feral popula-
tion
Options Considered
-Proper disposal of
refuse
-Fence facilities
-Education program
-Enforce state laws
-Total prohibition of
dogs
-Prohibition of dogs
during construction
-Registration &rabies
certification during
operational phase
Recommended
x
X
X
X
X
X
Rejected
x
Reject i on Reason
May be difficult to enforce
and legality questionable
Temporary 10ss1 -Do nothing
of habitat
Upstream furbearers
&big game species
Most species except
Dal1 sheep
Disturbance
from human
activity
Construction Phase
-Restrict worker access
-Unrestricted worker
access
Operation Phase
-Unrestricted public
access
-Control of ATV use by
pub lie
-Monitoring of game
populations
-Replacement lands &
research station
-Restoration of tempor-
ary use areas
X
X I Wou 1d permit ex tens i ve di s-
turbanc~&localized heavy
hunting &trapping
X I Would pennit extensive disturb-
ance &localized heavy hunting
&trapping,as well as vegeta-
tion damage
X
X
X
I lit wou 1d take a very 100g timeX
for natural processes to create
usable habitat
X
l L__(L~c~l [I L _
Mitigation Options Consideration Worksheet (Draft)Page 4 of 5
Wildlife Resource
Oig game,raptors,
&trumpeter ~wans
Mink &river otter
Pine marten
Forest-dwelling &
riverine bird &small
mamma 1 spec i es .
Black bear &
brown bear
Downstream beavers
Impact
Disturbance.
from air
traffic
Habitat loss
Habitat loss
Habitat loss
Habftat loss
&loss of
spawning
salmon
Possible food
cache prob1ems 'due to f1uctu
ating winter
flows
Options Considered
-No restrictions
-Specific altitude,
location,&time
restrictions
-Stock impoundments
with fish
-Replacement lands &
research station
-Habitat management
-Replacement lands &
research station
-Habitat management
-Replacement lands &
research station
-Habitat management
-Mitigation of salmon
loss
-Replacement lands &
research station
-Reduced fluctuations
-Replacement lands &
research station-
Recommended
x
x
x
x
x
X
X
Rejected
X
x
x
X
X
x
Rejection Reason
Would fail to mitigate this
impact
Conditions may not be suitable
&cost may not be justified
Not feasible
Not feas ible
Probably not feasible
Project.conflict
Wolf &wolverine
(upstream)
Habitat loss 8
reduced foodIbase(moose)
-Habitat management
-Moose management X (pend
1ng further
study)
X Not feasible
1-~I t I t fie l [I
Mitigation Options Consideration Worksheet (Draft)Page 5 of 5
Wildlife Resource Impact
Mos t spec i es except IPermanent
Dall sheep habitat loss
Options Considered
Habitat management
-Replacement lands &
research station
Recommended
x
Rejected Rejection Reason
x I Not feasible
Big game
Big game
All wildlife species
Moose
Avoidance of
impoundment
during
clearing
Avoidance of
borrow areas ~
associated
roads
Unauthorized
fires
Collisions
with vehicles
-Delay clearing until
just prior to filling
-Schedule movement of
equipment so as to
allow undisturbed use
by animals during a
part of each day
Fire suppression
program
-Identify areas of
high collision
potential
-Restrict vehicle
speed
-Plow pull-off areas
when deep snow
prevails
-Education program
x
x
x
x
x
x
x
Impact will be short term &
specific problem areas are
covered under separate impact
issues
Of questionable value &project
confl ict
Unnecessary since it will be
part of camp operation anyway;
fire is not unnatural;some
fires may not represent a
negative impact
[l L l [l L t I I [I [([I 1
-
J~
.....
DRAFT ANALYS ISOFWI LDLlFE
MITIGATION OPTIONS .
DRAFT COpy
-
~
I
I
-
-
LJ
i
f .
i
r
PRIORITY RATING
OF
IMPACT ISSUES
,
-
1-
PREFACE
This document is a preliminary draft working paper of poss'ible wildlife
mitigation options being considered in connection with the Susitna
Hydroelectric Project.It should not be considered as any type of commit-
ment by the Alaska Power Authority (APA).
This document was prepared in November and discussions are continuing with
the design team to modify design and operation of the Susitna project so as
to mitigate adverse impacts.
Sections in this document entitled "Recommended Course of Action"include
options under consideration.As it will not be possible to implement all
of the actions,APA is requesting members of the Fish and Wild"1ife Mitigation
Review Group comment on which options are considered to be the most cost
effective,most practical to implement,and most important considering the
resource and the degree of impact likely to occur.
Following receipt of these comments,continued studies and final design and
operation decisions,mitigation options will be reviewed and deleted or added
as appropriate.It is expected the process of arriving at final mitigation
decisions will be a continuous one involving APA,its consultants,and the
regulatory agencies.
-
-
-,
-
""'f~----.•-
SUSITNA HYDROELECTRIC PROJECT
DRAFT ANALYSIS OF WILDLIFE
MITIGATION OPTIONS
COMPILED BY:Edward T.Reed
rN COOPERATION WITH:A.W.F.Banfield,Ph.D
Steve Buskirk
William Collins,Ph.D
Philip Gipson,Ph.D
Winston Hobgood
Brina Kessel,Ph.D
Steve MacDona ld
Jay McKendrick,Ph.D
Joseph McMullen
Karl Schneider
Richard Taber,Ph.D
December 9,1981
-
-
......
PRIORITY RATING CRITERIA
·CRITERION A -IMPORTANCE OF RESOURCE
2pts.-.low importance
4 pts.-moderate importance
6 pts.-high importance
CRITERION B ..LIKELJHOOO OF NEGATIVE IMPACT OCCURRING
1 pt.-low likelihood
2pts.-moderate likelihood
3 pts.-high likelihood
CRITERION C -SEVERITY OF IMPACT TO RESOURCE
1 pt.-low severity
2 pts.-moderate severity
3 pts.-high severity
POSSIBLE SCORE TOTALS AND ASSOCIATED PRIORITY RATINGS
Priority 1 (high)=10 to 12 pts.
Priority 2 (moderate)=7 tog pts.
Priority 3 (low).=4 to 6 pts.
PRIORITY RATING OF IMPACT ISSUES
CRITERIA
..IM..;;.,P.-.AC;;;,..;T.--;ISo.;;.,SlJE #A-B-C-TOTAL
PRIORITY
RATING
1 4 2 3 9 2
2 4 3 2 9 2
3 4 2 2 8 2
4 4 1 2 7 2
5 2 3 1 6 3
6 6 3 2 11 1
7·4 3 3 10 1
8 6 3 1 10 1
. 9 6 2 2 10 1
10 6 2 1 9 2
11 6 1 2 9 2
"'""
12 4 2 2 8 2
13 6 2 3 11 1-14 6 2 1 9 2
15 6 2 2 10 1
,.-16 6 3 2 11 1
17 6 3 2 11 1
18 6 2 1 9 2
19 6 2 1 9 2
20 6 3 3 12 1
21 4 1 2 7 2
22 6 1 2 9 2
23 6 2 2 10 1
-
..,.
i~
,,-----
IMPACT ISSUE:1...,.....PRIORITY RATING:2
"""
....
.,~
r
PROJECT COMPONENT(S):Wat ana and Dev i 1 Canyon Impoundments
WILDLIFE RESOURCE:Mink and river otter
DESCRIPTION OF IMPACT:Loss of riverine and terrestrial habitat and an
associated decrease in the available food base
MITIGATION OPTIONS:Due to the nature of this impact,compensation is
the only form of mitigation that is feasible.In ...kind
compensation would require taking appropriate steps to insure that
the aquatic habitat created by the impoundments suppl ies an .
adequate food base for these two furbearer species.If that
approaich is not possible,some form of out-of-kind compensation
will be required.
DISCUSSION:There will be a negative impact on mink .and river otter as
a result of the elim"ination of a consider-able amount of both
terrestrial and riverine habitat.Conversely,the creation of two
large impoundments will result in a net increase in the amount of
aquatic habitat available.The important question is how suitable
will the impoundments be in providing available feeding
opportlJnities for mink and river otter.The impoundments may,
without any action on the part of the applicant,provide an
adequate food base to compensate for the predicted loss.Until
further details are available it is difficult to quantify this
potent'ial.There are thus three scenarios associated with this
situation:1)the impoundments will be suitable for a healthy
fisheries resource and that resource wi 11 develop natura l1y,2)
the re~iervoirs will be suitable for the establishment of a
fisheries resource but it will require the introduction of fish to
stimulate the growth of that resource,and 3)the impoundments
will not be capable,from alimnological standpoint,of supporting.
an adequate fisheries resource.
---------.._~,_.-----'----~~--------------
"""
"...
RECOMMENDED COURSE OF ACTION:..'.
1.Determine the suitabi 1ity of the impoundments to support fish
2.If the impoundments prove suitable,a stocking program to
stimulate and maintain a fisheries resource should be
developed ..
3.If the development of a fi sheries resource,either natura l1y
or"as a result of artificial means,is not feasible,compen-
sa.te for this loss in some out-at-kind fashion.
IMPACT rss!:Ji:2 PRIORITY RATING:2
-
'""'
.-
PROJECT COMPONENT(S):Watanaand Devil Canyon Impoundments
WILDLIFE RESOURCE:Pine marten
DESCRIPTION OF IMPACT:Habitat loss as a result of flooding
MITIGATION OPTIONS:It wi1l be impossible to avoid this impact
entirlely,and unless a project with a lower pool elevation is
selected,no minimization opportunities exist.Therefore the only
feasible .form of mitigation is through compensation in an
out-of-kind manner •.
DISCUSSION::Due to the nature of pine marten habitat,it will be
impossible to manage or create compensatory habitat in the project
area.In addition,this species wi 11 be impacted in the project
area to a severe extent because the bulk of suitable marten
habit,lt lies within the projected impoundment zones.
RECOMMENDED COURSE OF ACTION:Compensate for the loss of marten
.habitat and the resultant impact on marten by improving the
habitat for some other species either within the project area or
outside of the project area.Since the marten is an important
resource to trappers,any out-of-kind compensatory action should
be directed at other furbearer species if at all possible.
,,..,;.-----------~-~,------~----------~---......._-------~-~-
..;;.,;IM.....P.....AC.....T--...IS.....S~,:3 PRIORITY RATING:2
-
....
PROJECT COMPONENT(S}:Watana and Devi1 Canyon Impoundments
WILDl.,IFE RESOURCE:Cliff-nesting raptors
DESCRIPTION OF IMPACT:Reduction in the number of suitable cliff-
nesting sites and an associated increase;n importance of
remaining sites
~ITIGATIONOPTIONS:Although it will be impossible to avoid this
impact,it ,W"r 11 be pass ib 1e to minimi ze the magni tude of the
impact by taking acti on to a now raptors to ut il ize the remai ning
sites.If the raptors do not find the remaining nest sites
acceptable,or if efforts recommended to protect these sites fail,
it is unlikely that the impact can be compensated for in any
in-kind manner,thus necessitating an out-af-kind act of
compensation.The following options exist and would serve to
minimi:ze the impact by protecting remaining sites.
1.Pl.-anning by peop 1e such as recreation specialists cou ld
attempt to avoid schemes that would bring people in proximity
to cliff-nesting sites,at least during the sensitive tim~
period (gyrfalcon:2/15 -8/15 and golden eagle:.4/1 -
8/:n)or unti 1 June 1 when monitoring efforts have determined
that a nesting site is inactive.
2.Activities associated with the clearing of woody material from
the:impoundments could be scheduled so as to avoid those areas
where suitable nesting habitat should remain following
flooding.
3.During the construction and operation phases of the project,
helicopter traffic could be restricted,unless absolutely
necessary,from those areas that are suitable nesting sites.
Thi:srestriction would pertain only to the sensitive time
period.See Impact Issue #23 for details on air traffic
restrictions •
I...t!
.....
-
.DISCUSSION,:It is necessary that raptorscurrently nesting along the
river not be unduly harassed during the construction phase.This
will increase the likelihood of these birds utilizing alternative
sites as pres.ently used sites are inundated.It will be possible
to identify potential alternative sites prior to the start of
construction.If these sites can be protected,tile impact
associated with the loss of presently used sites may be
minimized.
RECOMMENDED COURSE OF ACTION:It is recommended that the three options
previously identified be implemented. Option 1 should be
in;th.ted now so that recreation p1 anners can take this matter
into (:onsideration as early on in their efforts as possible.
Option 2 mayor may not be necessary depending on the proximity of
areas to be cleared to nesting sites.Due to topographic factors,
the amount of clearing that would be necessitated near nesting
sites wi 11 probab 1y be minimaL If a total abandonment of nest iog
sites occurs,the possibility of erecting artificial nest
platforms could also be investigated •
PRIORITY RATING:2
.....
.....
....
,PROJECT CCIMPONENT(S}:Watana and Devil Canyon Impoundments
~ILDLIFE RESOURCE:Bald eagle
DESCRIPTION OF IMPACT:Loss of nesting and feeding habitat
MITIGATION OPTIONS:A variety of steps can be taken to minimize,and
if necessary,compel)sate for the loss of nesting sites and feeding
habitat •
1.During the clearing of the impoundments,clumps of tall
spruce trees (if a~ailab1e)could be left uncut along the
impoundment at 1/2 to l-mi1e interva-ls.These trees should be
l()cated in the cleared zone as far from the normal high pool
lE~ve 1 as possi ble to avoid their be ing washed away dur ing
unusually hi ghwater.periods.If other conditi ons permit the
existence of a high eagle population,artificial perching
sites could be provided.
2.Following inundation,eagle nesting could be monitored to
determine if eagles are successfully locating and using
alternative sites.If it is determined that the eagle
population has suffered due to a failure to use the remaining
nesting opportunities,artifica1 nesting platforms could be
erected in suitable locations.
3.If limnological conditions are suitable,and the impoundments
have not naturally developed a suitable fisheries resource,
efforts could be undertaken to stock suitable fish species to
generate a good food base for bald eagles.
DISCUSSION:Although some eagle nests and suitable nesting sites will
be lost as a result of the project,the creation of two large
impoundments may,if suitable conditions exist,result in a
greater'abundance of bald eagles using this area in the future
than ar'e currently found here.If the proper steps are taken,
this pCltentialincrease in eagle abundance could function as a
form of out-of-kind compensation to offset losses suffered by
other species.~
RECOMMENDED COURSE OF ACTION:The three options identified above
should be implemented.Of these options,the monitoring of eagle
populations and the establishment ofa fisheries resource are the
most important and are critical to the successful mitigation of
this impact.
-,
I
-
.....
On the other hand.,in the upper basin it app·ears that the only
practical option is prescribed burning,and some Question exists
as to the ability of this technique to produce the desired results
under the environmental conditions present.An argument against
an upstream management effort is that in doing so the habitat
WOll 1d be so altered as to·enab le the ex i stence of a moose
population at an artifically high level,and unless long-term
management efforts are continued,there would ultimately be a
reducti em in carrying capacity.Of course management efforts in
the downstream area may also result in a high moose population
that would require long-term management efforts to provide for the
continued existence of a higher moose density.By not direct1ng
management efforts in the upstream area,moose popul ation would be
allowed to be lowered and reach a new level that natural
conditions would be able to support without continued management
efforts.On the other hand,the status of moose in the upper
basin is important to a variety of other species,including wolves
and bears,which prey on moose;caribou,which would probably
incur higher wolf predation if the moose population decreased;and
also numerous scavengers,such as the wolverine and red fox that
frequently utilize wolf-killed moose for food.Therefore,
allowing the project to reduce the carrying capacity of the upper
basin for moose would have indirect impacts on other species.The
impact on sportsmen,although not a biological consideration,
should also be factored into the choice.Fail ing to support
upstream moose would not be taken favorably by those hunters that
use the;~rea,but 1ikewi se the improvement of moose habitat in the
downstream area would be viewed positively by sportsmen in that
area.Aliso to be considered is the fact that improved access into
the upper'basin will probably result in greater hunting pressure
and an a~;sociated demand for game.An associated aspect of the
moose habit at management issue is the impact that management
efforts ~till have on other species.Some species will also
benefit from this type of moose mitigation,while other species
will be negatively influenced.As noted in the list of mitigation
options,both the upstream and downstream areas may not be
acceptab 1e and management efforts coul d be consi dered for other
appropriate portions of the state.Possible areas of
consideration could be portions of the upper Susitna _basin far
removed from the project area,the Tanana Fl ats near fai rbanks,
the Kenai Peninsula,etc.
RECOMMENDED COURSE OF ACTION:It;s recommended that pl ans be
developed to improve moose habitat in both the upper basin
adjacent to the impoundments,and also in the lower basin (see
Impact Issue #13)•Research efforts shoul.d first be undertaken to
gain an understanding of how burning will affect vegetation in the
upper basin and,if the results are favorable,a program of
prescribed burning should be undertaken.Since the effectiveness
of burning is currently questionable,a program of moose habitat
improvement along the lower river should also be developed.The
u1t imate dec isi on as to the di stri but i on of effort between these
two areas will have to await the determi nation as to the
usefulness of burning in the upper basin.The following specific
recommendations can be made in regard to the two management areas:
Upstream -Investigate the suitabil ity of burning for moose
hab it at managemen t •
-Conduct detailed browse util ization,productivity,and
availabil ity studies in order to determine the extent
to which compensation is needed and the level of effort
requi red to ach i eve th at 1eve 1 of camp ens at ion.
-Gather more complete information on moose distribution
in the upper basin and also conduct snow depth studies
in areas identified as potential management areas in
order to insure that browse resulting from management
efforts will be available to moose in winter.
....
.-
-Any burning program should take into consideration
impacts on other wi 1dl i fe spec ies and be conducted in
such a fashion as to minimize any negat iveimp acts,for
example,all burns should be of a linear configuration
and oriented parallel to caribou migration routes since
recent 1y burned areas have proven to funct"i on as a
barrier_to migrating caribou.
Downstream -Mature timber on selected islands should be logged
-Selected islands that do not contain mature cottonwood
trees should be burned.
-Suitable areas east of the river should be identified
and a program of moose habitat management developed
that utilizes burning,logging,crushing,or a
combination of all three depending on the situation •
!::.)
PRIORITY RATING:1
I~
PROJECT COMPONENT(S):Watana and Devil Canyon Impoundments
WILDLIFE RESOURCE:Upper basin moose population
-
-
l~
DESCRIPTION OIF IMPACT:Habitat loss
MITIGATION OPTIONS:The only form of mitigation that can be considered
in regard to this impact issue is compensation.It should be
feasible through habitat management to compensate for the loss
that wi 11 be incurred.In cons idering habitat management,it must
first be determined where compensation efforts should be
implemented.The efforts could be directed ·in any of the
following areas:1)the upper basin adjacent to theriew
impoundlTlEmts,2)selected portions of the lower basin,3)a
combination of upstream and downstream areas,or 4)some area
totally T'emovedfrom the influence of the project ..
Upstream habitat .management -the only practical approach to
improving moose habitat in the upstream area may be through
prescribed burning.
Downstream habitat management -in the downstream area it would be
possible to improve moose habitat either directly on river islands..
and/or associated riparian areas,or in more upland situations
east of the river.On thei s1ands with more mature stands of
timber,logging operations should provide the needed habitat
a lterati ons,with the possi bi Tity of prescribed burning in thosel
areas that do not contain mature cottonwood trees.In up]and
areas,either burning,crushing,logging,or a combination of all
three are poss ib1e management opt ions.
DISCUSSION:In deciding where (upstream vs.downstream)to institute
management efforts'to compensate for loss of moose habitat,the
first question is whether or not the ,mitigation effort should be
implemented in the immedi ate vi cinity of the impact (upstream)or
if more d'i stant areas are acceptab1 e (downstream).The major
argument 'in favor ofa downstream effort is that along the lower
river theT'e are proven techniques available that will,with a high
degree of certai nty,be effective in achi evi"9 the desired goal.
/
-------_.,..""""-,---,--------'---~-------"'-------------------
PROJECT COMPONENT.(S):Watana and Devil Canyon Impoundments-
..IMPACT ISSUE:7 PRIORITY RATING:1
-
-
.-
WILDLIFE RESOURCE:Black bear-.................;..;......;;,.---
DESCRIPTION OF IMPACT:Habitat loss,including the elimination of most
denning and foraging areas in the vicinity of the project
MITIGATION OPTIONS:The only option in regard to this impact issue is
compensation by improving black bear habitat in some other area,
or compensating in an out-of-kind fashion through some other
species.
DISCUSSION:The black bear population in the project area will be
severely impacted since the impoundments wi 11 result in the
eliminat"ion of most of the suitable black bear habitat in the
area.The presence of a large and healthy brown bear population
and the restriction of forested habitats to the river area
preclude the existence ofa black bear population in adjacent
areas.Since there is no possibility of managing the adjacent
areas for'black bears,the only choice is to either compensate
through mitigation efforts directed at other species,or to
attempt to improve black bear habitat in areas outside of the
upper basin.Although the black bear is an abundant species in
Alaska,a.s evidenced by the liberal game regulations pertaining to .
this species,future demands for this species as a game animal
will probably increase and efforts to compensate for the predicted
loss,and thus insure the avail abil ity of bl ack bears in the
future,should be considered~
RECOMMENDED COURSE OF ACTION:The loss of black 'bears should be
compensatled for by improving the status or abundance of other
species,11100se being the most likely species.If mOose habitat
management efforts are implemented along the lower river,it is
suggested that a thorough review of the habitat requirements of
black beal-s be conducted and any reasonable efforts be taken in
conjunction with moose management to improve the same areas for
I
/
--------,_._---~~
-
b1ack bears,keep i 09 in mind,however,that a 11 owi n9 or
encouraging greater black bear abundance cou ld reduce moose calf
survival and thus be counterproductive in regard to the goals of
the moose management program.
IMPACT ISSUE:8 PRIORITY RATING:1
-
--
-
PROJECTCClMPONENT(S):Watana and Devil Canyon Impoundments
WILDLIFE RESOURCE:Brown bear
DESCRIPTION OF IMPACT:Loss of spring foraging habitat as a result of
inundation
MITIGATION OPTIONS:Out-of-kind compensation is the only form of
mitigation that can be considered in regard to this impact issue.
DISCUSSION:rhe distribution of the brown bear,unl ike the black bear,
is not as restricted to the impoundment area -in the upper basin,
and thus the inundation of that area will result in the
elimination of only a portion of the total area used by this
speciE~s.At the present time it is impossible to predict how much
the loss of this area,which is frequented during spring,will
mean to the brown bear population.It will be impossible,as in
thecclse of the b1ad bear,to manage other areas of the project
-area for the loss that wi 11 occur here.This loss wi 11 be,
however,only one of several different forms of project-related
impacts that will be directed towards brown bears,,and although it
may not be in itself of a critical nature,it may,in conjunction
with other impacts represent a severe influence on the future of
this species in the project area.
RECOMMENDED COURSE OF ACTION:Since little can be done to directly
compensate for this impact,it is recommended that,1)compensa-
tion efforts directed towards other species be increased in order
to cOI11])ensate for this impact on brown bears,and 2)recommenda-
tions made in regard to other impacts on this species be
imp1emt:!nted in order to reduce the combined impact on brown
bears.
,/
IMPACT ISSUE:9
<.~PRIORITY RATING:1
....
-
PROJECT COMPONENT(S):Watana and Dev i1 Canyon Impoundments
WILDLIFE RESOURCE:Wolf
DESCRIPTION OF IMPACT:Habitat loss and reduction in food base
{moo5te}
MITIGATION OPTIONS:The only form of mitigation feasible to minimize
this impact is to take steps to maintain the present abundance of
moose in the upper basin.If this is not possible,the impact on
thi s species wi 11 have to be compensated for in some other
manner.
DISCUSSION:The extent to which the reduction in moose will impact
this species is difficult to predict although it will certainly
have some negative impact.Although wolves feed on moose,they
also kii1numerous caribou;however,the distribution of caribou
varie~sboth from year to year,and also among seasons.Thus
caribou do not represent as consistently available a sourceef
foodi!s do moose.Whether or not the upper basin can successfully
be managed for moose is questionable (see discussion on impact
issue #6).The ext~nt to which the moose population can be
maintained through management efforts is thus currently unknown
and location of moose management efforts and their success will be
one factor that wi 11 greatly infl uence the future status of wo Ives
in the upper basin.
RECOMMENDED COURSE OF ACTION:It is recommended that the suggestions
concerning the management of upper bas in moose as made in Impact
Issue #6 be implemented.The project will impact wolves in other
ways,and a 1though each impact may not appear severe by i tse 1f ,
collectively they do represent a major impact on this species;
therefore,whenever possible other recommendations made in regard
to other impact issues concerning this;species should be
implemented.
lMPACT ISSUE:10.................-.-..........-
PROJECT C~MPONENT{S):Watana Impoundment
WILDLIFE RESOURCE:Dal1 sheep
PRIORITY RATING:2
-
,.,.,.
DESCRIPTION OF IMPACT~Possible loss of the Jay Creek mineral lick
MITIGATION OPTIONS:Compensation of this 'loss is the only form of
mitigation that may be possible.It could be possible to replace
the inundated mineral lick with an artificial lick at a different
location,but still within the range of the sheep that currently
use the Jay Creek lick.
DISCUSSION:At the present time it appears that at least a portion of
the Jay Creek 1ick wi 11 be inundated during a part of the year.
It is po.ssible,however,that the lick will not be under water
during May and June,when mos~use of the lick occurs.It remains
speculathe as to whether or not the lick will still be usable,or
acceptable to sheep under project conditions.It is also unknown
as to thow dependent the sheep populatio"is in regard to this
lick.However,considering the frequency of use,and the
willln9ness of sheep to ex.pose themselves to predation in order to
reach the lick,it must be of some significance to them.
RECOMMENDED COURSE OF ACTION:The following steps to mitigate this
impact are recommended:
1.Effclrts currently underway to determine the chemica 1
comp'os it i on of the 1ick and the number of sheep us lng the 1ick
should continue.
2.Following inundation,monitoring efforts should be undertaken
to actually document the reaction of sheep to the change and
the extent to which they continue to use the lick.
3~If the lick ;s abandoned following flooding,or use
SUbstantially reduced,an artificia1 lick should be established
using salt blocks specifically designed to match or improve
upon the chemical composition of the current lick and placed
within the natural range of these sheep,preferably in a less
vulnl!!rable location.
IMPACT ISSUE:11..............
PROJECT COMPONENT(S):Watana Impoundment
WILOLIFE RESOURCE:Caribou
PRIORITY RATING:2
r
I
I~
DESCRIPTION OF IMPACT:The possibility exists that during April and
May the drawdown zone of the Watana Impoundment and the
associated ice conditions may function as a barrier to the
migratory movement of the Nelchina caribou herd to the calving
area.
MITIGATION OPTIONS:If it is demonstrated that caribou attempt to
utilize hazardous crossing -points,this impact may be minimized by
erecting fences in such a manner as to direct migrating caribou to
safer crossing points.If the Nelchina herd finds the
impoundments a total barrier,and if attempts to direct them to
safe crossing pointsfa;l,the only other mitigation option is to
insurl:that the area they select for calving be totally protected
durin9 the calving period.
DISCUSSION::-The severity of this impact wi 11 depend on three factors:
1)whE!ther or not the Ne lch i na herd has to cross the impoundment
in a north to south direction en route to the calvi~garea,2)
whether or not they are able to locate safe crossing points,and
3)if they are forced to calve in a new area whether or not that
area will prove suitable for successful calving.Although the
Nelchina herd has in the past frequently wintered north of the
SusitnaRiver and thus crossed the river as they move to the
calving area on the south side of the river,during the past few
years they have wintered east-,.pf the calving area,particularly on
the Lake Louise Flats,and thus have moved in a westerly direction
to reach the calving area.It is impossible to predict whether or
not this current movement pattern win persist after the
impoundment is created,a lthough cons;dering the tendency of
caribou herds to suddenly shift migratory patterns,it is likely
that sometime following inundation they will again winter north of
....
-
".,.
.-
-
P T
the rher and be faced with the necessity of crossing the
impoundment.The ice conditio~s that will be present during a
crossing will probably vary greatly from area to area and year to
year ilnd it is presently predicted that caribouw;11 attempt to
locatE!safe crossing points and thus avoid hazardpus crossing
conditions.If they fail at this effort to select'safe crossing
pointsi,it will be possible to erect fences to alter their
direction of movement in such a manner as to guide them to safer
points.If all of this fails and the herd is totally blocked by
the Wa.tana Impoundment and is thus forced to calve elsewhere,it
will be critical to monitor the situation and through whatever
action is necessary,insure the total protection of the herd as it
is faced with the difficult task of adjusting to a new calving
si tuat ion.
RECOMMENDED COURSE OF ACTION:Due to the unknowns associ atedwith
mitigati'ng this potential impact,the first and most critical need
is to monitor the movements -of the herd from late winter through
the calving period.This monitoring effort should continue until
it is demonstrated that the herd has either successfu lly
negotiated the impoundment·in a spring migration movement or has
established a new calving area.In other words,the monitoring
effort should continue for at least several years following the
first .attempt of the herd to cross the impoundment,and of course
it is 'impossible to predict at this point how long it will be
until the Nelchina herd actually attempts a crossing.During the
first'several springs following the initiation of operation,a
reconn.ilisance survey should be conducted to ascertain the
conditjion of drawdown ice conditions and map the location of both
hazardc)us and safe crossing points.This information will be
needed if an attempt is made to alter the direction of migratory
movement by fencing •.Depending on this review of crossing
conditions,a plan for establishing temporary fences should be
prepared,and if it appears that traditional crossing points wi 11
be difficult for caribou to negotiate,the necessary fencing
materia.l should be secured and placed in the field so that if
monitor'ing efforts indicate the likelilhood of an attempted
crossing,they can be erected quickly during the migration
....
-
.....
-i
.....
period.The purpose of the fencing is to create a visual,and not
necessarily a physical barrier.Thus relatively cheap material
such as snow fencing or even burlap sheets can be used.In order
to avoid undue interference with other species,the fences should
be used only when necessary,and only during the period when the
herd is migrating towards thE river and when hazardous ice
conditions prevail.The last reconmendation is that any new
cal ving area that may be establ ;shed due to the Watana Impoundment
blocking migration be totally protected during the calving period,
including a total closure of all human activity as well as air
traffic restrictions specifying a minimum flight altitude of at
least 1,1000 feet above ground during the calving period and over
the post-calving aggregation •
IMPACT ISSUE:12 PRIORITY RATING:2
-
.p
.....
-
PROJECT COMPONENT(S):Operati on of Devi 1 Canyon Dam
WILDLIFE RESOURCE:Beavers inhabiting the Susitna River downstream
from the Devi 1 Canyon Dam
DESCRIPTION OF IMPACT:Due to flow regulation by the Devil Canyon dam
there will probably be a change in the number of sloughs available
for use by these aquatic furbearers.The daily fluctuations in
flow lIDay also result in unstable ice conditions and make it very
diffilcult for beavers to maintain winter food caches.
MITIGATION OPTIONS:The predicted impact on aquatic furbearers in this
area can be minimized by reducing the degree of daily flow
fluctuations during the winter months and operating in a fashion
as to provide flow regimes as close to natural conditions as
possible.
DISCUSSION::The exact extent of this impact is difficult to predict at
this time and wi 11 differ between the area north and the area
south of Talkeetna..Although there may be less summer habitat
availclble,it is possible that higher winter flows may actually
increalse the amount of suitable overwintering habitat for beavers;
however,if unstable ice conditions exist due to daily
fluctuations there could be a net decrease in beaver abundance
because they will not be able to maintain food caches which are
normally frozen in place by ice.It is anticipated that ice
problems would be most prevalent north of Talkeetna which has
comparatively fewer beavers than the area south of Talkeetna.In
addition to serving as an .important fur resource,beavers
inhabiting the floodplain of the lower Susitna River also aid in
thecr1eation of moose browse by cutting trees and opening areas
for thle generation of early success iona 1 shrub speci es •Thus any
negative impact on beavers in this area could indirectly reduce
the winter carrying capacity for moose.At this point in time it
is impl)ssible to state what proportion of the moose browse is the
result of beaver activity in comparison to other factors
influencing·the generation of browse.
-
--i
-
-
"""
RECOMMENDED COURSE OF ACtION:to the greatest extent possible,daily
fluctuations in winter flow from the Devil Canyon dam should be as
sma 11 as pr ac t i ca 1.A1sa ,in order to de term i ne the degree to
which negative impacts on beavers will reduce winter moose br-owse,
furthier study of downstream beavers,especially be"low Ta1keetna,
should be undertaken.This is necessary in order to totally
assess-impacts of the project on downstream moose populations and
thus the level of compensatory moose management required (see
Impact Issue 'IS 6 and 13).
IMPACT ISSUE:13
I ...--PRIORITY RATING:1
PROJECT COMPONENT(S):Operation of Devi 1 Canyon Dam
WILDLIFE RESOURCE:Moose inhabiting the area downstream from the Devil
Canyon Dam
DESCRIPTION OF IMPACT:South (downstream)from Devil Canyon there may
be an alteration of plant succession trends due to flow regulation
causing a possible reduction over time in the amount of winter
browsje available to moose that rely on this area during
winte~r,especially when deep snows prevail.
MITIGATION OPTIONS:There are several management techniques that cou 1d
be employed to'improve moose habitat in this area in order to
compensate for possible reductions in the quantity of browse.
1.commercial logging of mature cottonwood -trees on the islands
2.prescribed burning of islands that are not dominated by mature
cottonwood trees
3.l01gging,burning,or crushing of vegetation in upland areas
east of the river
DISCUSSION:Based on the information current1yava i1ab le.,it is
diffil:U 1t to accurate ly predict the extent of the impact that wi 11
occur in regard to this area.Although tr-ends will be
predictable,due to the nature of the river and the number of
fac tor's that i nf 1uence the creation and movements of is lands,it
will ~trobably be impossible to ever detennine the actual quantity
of brclwse that wi 11 be lost as a resu It of the project.If the
regula,tion of the river does cause a reduction in the creation of
new islands,and thus areas suitable for the invasion of browse
spec i es such as wi 11 ow,;tis expected that two ch anges wi 11
occLlr.First,many areas that would be washed away under present
flow conditions will remain secure enough for the development of
moose browse,thus resulting in a possible short-tenn (1S,to 25
years);ncreasein the amount of browse a va il ab 1e to moose.
Howeve'r,as pl ant success i on proceeds and the vegetati on matures
-
-
beyond the point of serving as suitable browse,there will be a
gradUia 1 long-term reduction in the capacity of the ripari an area
to support moose under deep snow conditions,thus causing an
associated reduction in the abundance of moose on both sides of
the river.
RECOMMENDED COURSE OF ACTION:In order to compensate for the possible'
loss of moose browse it is recommended that a habitat management
program be developed to improve thehabi tat in the area south of
Devil Canyon to support wintering moose.As previously discussed
(Impact Issue #6),this area may also function as a means of
compensating for moose habitat losses in the upper basin.The
first step wi 11 be to identify appropri ate areas for management
activ"ities,including consideration of land ownership and
vegetation types,and correlating this information with census and.
movement data being collected by ADF&G.Where appropriate,blocks
of mature trees should be removed by means of commerci al logging
operation~.Prescribed burning should also be considered,but due
to the!extent of human habi tation in thi s area there may be severe
constr'a ints on burning opportuniti es.The use of a vegetat ion
crusher can also be considered in areas where burning and logging
are not feasible.Although moose curl·ently use the riparian area
during severe winters,and although some management efforts should
be directed to those areas,serious consideration should be given
to managing habitat east of the Parks Highway and the Alaska
Raflroad.Many moose that use the river move down from the
foothills of the Talkeetna Mountains,located to the east,and in
doing so incur high mortality in crossing the railroad and
highway.Therefore,if management efforts are directed at areas
east of these two transportation corridors,migratory moose would
no 10nger have to cross this area.On the other hand,many moose
move ttl the river from the west and therefore adequate management
effort$directly on the river1 itself should also be undertaken to
provi dE!browse for these moose.
IMPACT ISSUE:14................................-PRIORITY RATING:2
.....
-
-
PROJECT COMPONENT{S):Clearing of woody mater;a1 from Dev;1 Canyon and
Watarua Impoundments
WILDLIFE RESOURCE:All upstream big game species
DESCRIPTION OF IMPACT:Big game species wi 11 avoid the area being
cleared during the period of clearing.
MITIGATION OPTIONS:In order to minimize the magni~udeof this impact
on animals exi'st ing adjacent to the proposed impoundment zones,
the woody material could be cleared from the floodplain of the
river,progressing up the sides of the impoundment as the
impoundment is filled.Th is wou 1d also leave more habitat intact
for a larger time period since clearing would not have to start
until dam construction is almost complete,and thus reducing the
temporal magnitude of the habitat loss that will result from the
impoundment.
DISCUSSION:There is little justification to expend a large-mitigative
effort in this area since this impact will be relatively short in
durati on and wi 11 basically impact an'ima1s that wi 11 be far more
severely impacted by inundation and the associ-ated pennanent loss
of habitat.In addition,there will be differences in the
severity of the disturbance depending on the associated big game
species •
RECOMMENDED COURSE OF ACTION:Other than the above-mentioned
option of clearing ahead of fill ing,the only other recommendation
concerns the Jay Creek mineral lick.Since sheep may be able to
use th'is lick following inundation (see Impact Issue 110),it is
recommE~nded that no clearing be conducted within one mile of the
lick during the months of May and June.If clearing operations
continue year round,WOOdy material near the lick should be
removed during some other time of the year,preferably during the
winter.This will enable the uninterrupted use of the lick by
sheep and possibly allow for continued use following filling.
2
--------,_..---------"""""""'""...""",..."",====""""""'~-----------
IMPACT ISSUE:15-PRIORITY RATING:1
".,.
PROJECT COMPONENT(S):Clearing of wo~dy material from the Watana
Impoundment
WILDLIFE RESOURCE:Caribou
DESCRIPTION OF IMPACT:There may be'disturbance of caribou migrating
to the calving area south of the river and/or post-calving
movement to the area north of the ri"er~
MITIGATION OPTIONS:Two options exist to avoid or minimize the
magnitude of this impact,1)schedule clearing activities to avoid
crossing areas during the migratory period,and 2)leave uncut
travel lanes to provide sheltered routes across the impoundment
zone during the construction period.
DISCUSSION:Due to the unpredi ctable nature of caribou movement
pattelrns,it is possible that during the clearing peri od there
wi 11 not be a major movement of the Nelchina herd through the
irnpoundment·zone en route to'or from the calving area.Such
movements have occurred in the past and therefore the possibi 1ity
does exist that the herd will attempt to cross the river during
the period of clearing.In order to avoid undue disturbance of
this critical activity,all possible efforts should be taken to
minimize disturbance of migrating caribou.In order to accomplish
thi s,1ate winter and early spring meni toring of the herd wi 11 be
requir'ed to predict if action is necessary.Clearing schedules
should!be flexible enough to accommodate a shift in the location
of clearing efforts if necessary.It can be argued that little
attention should be devoted to this short-term impact since a
reservoir will ultimately cover the area in question.Even though
the disturbance of migration caused by clearing activities is,
admittedly,a short-term impact,it is also one of many forms of
impact that the Nelchina herd will be subject to as a result of
the project.Each impact may not by itself represent the
-
-
potential for severely impacting the herd,but collectively there
could be a major disruption of the activities of this herd with
associated negative consequences.Therefore,it is important that
each caribou-related impact issue be mitigated to the fullest
extent possible in order to avoid the collective results of all
forms of impact.The major issue in this caseis·disrupting the
movement of the herd to their calving area.If the herd is
permitted to cross the river during the clearing operation and
succe~ssfully crosses the river.during the fi 11 i og operation,
chances of successful crossings after filli~g will be increased.
RECOMMENDED COURSE OF ACTION:Travel lanes should be left uncut until
absolutely necessary.These lanes should be located between
Deadman and Jay creeks and should each be 1/2-mi le wide.Three or
four such lanes should be adequate and continue from the north
through the south slopes of the impoundment zone.During the
clearing period the Nelchina herd should be monitored by'ADF&G,
especially in late winter and early spring in order to determine
the possibility of the herd attempting to cross the river from
north to south.If monitoring efforts indicate that a crossing
will occur,'clearing operations should be halted;n the crossing
area for the four to six week period that crossing normally takes
place.This will likely occur from early April to mid-May.The
monitoring effort should continue during the early post-calving
period and work halted if it appears that the post-calving
aggre9ation of cows and ca lves wi 11 cross the river moving north.
IMPACT IS5~:16 PRIORITY RATING:1
-
-
PROJECT CClMPONENT(S}:Construction camps and all access roads
WILDLIFE RESOURCE:Red fox,wolf,black bear and brown bear
DESCRIPTION OF IMPACT:Illegal feeding of animals and improper
disposal of garbage
MITIGATION OPTIONS:The following options exist to avoid and/or
minimize impacts associated with the feeding of wild animals by
humans and the acquired dependency of wild animals on available
refuse.
1.All camp facilities (especially landfills,if used)could be
slecure ly fenced with the bottom edge of the fences buri ed
1:8"below ground.
2.S~ecure·garbage containers could be available in all work areas
al'ld all refuse collected and incinerated.
3,.W()rk crews could be hired and charged with picking up all
discarded refuse from all work areas and along all·access
r()ads.
4.State laws prohibiting the feeding of wild animals could be
strictly enforced by security personnel and repeated violators
diismissed from their position of employment and permanently
p'·ohibited from future work on any aspect of the project.
5.A mandatory education program for all project personnel could
be!prepared an d imp 1ernen ted.
DISCUSSION:This is one impact that can,through proper planning and a
concer'ted effort,be minimized,if not totally avoided.The.
key element in the successful execution of these options lies
with personnel respons ib 1e for the actions of a 11 workers
associated with the construction effort.It is therefore critical
that all supervisory personnel be impressed with the need to
prevent illegal feeding and are committed to maintaining a
preventative program to that end.Al"I construction contracts and
union agreements entered into for this project should clearly
·,.
identify the agreed-upon ru,les and regulations that pertain to
this issue and also identify the consequences to workers who fail
to camp ly.
RECOMMENDED COURSE OF ACTION It is recommended that all five (5)
options identified as mitigation options be implemented during the
const,·uction and operationa 1 phases of the project •
....
.....
'--------,-~-----_._---------------------
)).IMPACT IS~:17 PRIORITY RATING:1
-
....'
PROJECT COMPOHENT(S):Main access road,borrow areas,access roads
to borrow areas,and construction camps
WILDLIFE RESOURCE:All furbearer species,many avi an and small mamma 1
speci es,and all bi 9 game speci es except Da 11 sheep
DESCRIPTION OF IMPACT:Habitat loss as a result of these project
components
MITIGATION OPTIONS:The magnitude of this impact can be avoided to
some degree by arranging camp facilities in as_co,mpact a fashion
as poss i b1eand keeping them as close to work areas as feasible.
Permanent facilities (main access roa:d and permanent camp
facil'i ties)wi 11 represent a permanent loss of habitat and
compensatory actions through habitat management will be required.
Tempor'ary faci 1;ties (borrow areas,roads to borrow areas,and
tempor'ary camp fac"i1ities)could be restored to a condition that
would provide usable wildlife habitat.
DISCUSSION:There are basically three levels of consideration involved
with this issue.First,the magni tude of the habitat loss
associated with these project components can be minimized to some
degree through careful planning.Secondly,temporary use areas,
such as borrow areas and portions of camp facilities,can be
restored "in a manner that wi 11 allow for future use by wi ldl ife.
And thirdly,unavoidable losses that will result from the
permanent portion of the project can be mitigated through
compensatory action.
RECOMMENDED COURSE OF ACTION:The following steps are recommended to
mitigate the anticipated habitat losses associated with the
abovemlmtioned project components.
1.C~np facilities should be arranged in as compact a fashion as
pO!lsible and located as close to work areas as possible,in
order to'avoid undue habitat disturbance.
,1iW/lIiiIl
....
-
2.Temporary use areas (borrow areas,roads to borrow areas,and
temporary portions of the camp)shou ld be restored fo 110wing
use.All top soil removed from these areas should be
stockpiled and saved.In addition,any top soil removed from
areas that will be permanently disturbed should also be saved
and added to the stockpil es.Fo Hawing use of each area,the
tlOP soil should be reapplied and regraded if necessary to
avoid erosion.The areas should then be lightly seeded with
grasses,and fertilized in order to stimulate the initial
growth of native vegetation.It is recommended that during
the first year the reclamation areas be fertilized with a mix
h'igh in phosphorus (10-20-10 or 8-32-16)and applied at a rate.
sufficient to supply 75-100 pounds of nitrogen per acre.
During the second growing season these areas should be
re~fertil;zed ata rate 1/2 that of the initia~treatment,and
during the third growing season at a rate 1/3 that of the
initial treatment.
3.Tel compensate for permanent losses to big game and furbearer
species it is recommended that habitat management efforts
directed toward moose be increased to compensate for these
lclsses.In the case of avi an species,it is recommended that
advantage be taken of the newly created aquatic habitat --
represented by the impoundments and that efforts be expended
to utilize these impoundments to improve habitat for certain
waterfowl in order to compensate for the loss of terrestrial
habitat and associated terrestrial species.Efforts should be
expended to insure that an adequate fisheries food base exists
in the impoundments.This may entail the stocking of
appropriate fish species.Obviously,it must first be
established as to whether or not the,impoundments will be
limnologically suitable to support a good fisheries resource.
Following the establishment of a food base,it is recommended
that nest boxes be erected in adjacent forest areas to provide
nesting opportunities for cavity-nesting waterfowl such as
goldeneyes and buffleheads.
,.~
IMPACT ISSl[:18 PRIORITY RATIKG:2
PROJECT Cm1PONEKT(S):Borrow areas and access roads to borrow areas
WI LDLIFE RESOURCE:All upstream bi g gamespeci es except Da 11 sheep
DESCRIPTION OF IMPACT:.Avoidance reaction during construction period
and resulting in loss of habitat use
MITIGATION OPTIONS:The only feasible option to minimize the magnitude
of this impact is to schedule activity and equipment movement in
such a.fashion as to allow animals to uti 1ize the area adjacent to
the borrow areas for a portion of the day.
DISCUSSION:The concept of limiting human activity in these areas to
certain portions of the day may prove effective for only some
species.It is likely that moose WQu'ld benefit from such an
arrangement while more wilderness species such as the wolf and
wolverine would not,respond positively to such an approach.
RECOMMENDED COURSE OF ACTION':Since the duration of this impact will
be for only the construction period,and since it is likely that
any scheduling program would be only partially effective,it is
recommended that no action be taken to mitigate this impact.
Instead,mitigative action should be applied towards the
restoration of these areas and thus the securing of long-term
availability of the habitat that will be disturbed as a result of
borrow areas and the as soci ated access roads.
3/
~IM..;.;..P.;...;,;AC;;.,;.T......I;.;;.S~=19 PRIORITY RATING:2
.....
-
....
PROJECT COMPONENT(S):Main access road and all access roads to borrow
areas
WILDLIFE RESOURCE:Moose and caribou
DESCRIPTION OF IMPACT:Mortality caused by collisions with vehicles
MITIGATION OPTIONS:Although it is unlikely that this type of impact
can be totally avoided,there are steps that can be taken to
minimize the magnitude of this impact.Construction workers,and
espel:ially truck drivers,could be exposed to an educational
prog,'"am descr-ibing the value of wildlife in the area and the need
to m'inimize impact through careful and thoughtful driving.Speed
limits could be posted and enforced that would reduce the
frequency of collisions.During winter months when moose and
caribou may frequent the road as a result of superior traveling
'condlitions,numerous pull-off ar.eas could be plowed clear to give
animals an escape opportunity in order to avoid vehicles.
DISCUSSIm~:The severity of this impact wi 11 depend on severa 1
factcfrs,the vo lume and speed of project-associated traffic,the
atti tude of the drivers,and the depth and duration of winter
snow •
RECOMMENDED COURSE OF ACTION:In conjunction with the educational
program recol11mended to reduce the illegal feeding of animals (see
Impact Issue 116)an attempt should be made to impress on workers,
especially those workers that will be driving trucks and other
large equipment,as to the value of wildlife and the need to avoid
killing animals through collisions with vehicles.It is also
recommended that speed limits be established on the access road
and strict ly enforced.The suggested rate of speed wi 11 have
..
to dE~pend on the design speed of the road,the types of vehicles
usinHthe road,etc.It is recommended that the speed limit be
kept as low as possible while'sti 11 allowing for the timely
movement of equipment and personnel.Due to the increased
frequency of collisions after dark,it,would be advantageous to
have two speed limits,one for daylight hours and'a lower limit
for night.The placement of warning signs at known crossing
points should be considered to alert motorists to the increased.
likeliho'od of encountering moose on the road.It is also
recommended that during winter plowing operations numerous
pull--off areas be provided along the road in order to provide
opportunities for moose to get out of the way of vehicles.The
number of such pull-off areas and the spacing between them wi 11
probably vary dep"ending.on the associated.vegetation cover type
and the distribution of moose.Therefore,it is suggested that
prior to road construction,and following a decision as to the
exact route~areas be·identified where pu l1-off points will be
needed as well as which areas will not require such action.
;"'"
•'1',1 •
IMPACT IS~~:20 PRIORITY RATING:1
,....
-
PROJECT COMPONENTCS):Access road and construction camps
WILDLIFE ~tESOURCE :All upstream furbearer and bi 9 game speci es,except
Dal1 sheep
DESCRIPTION OF IMPACT:Increased human activity associated with
improved·access and the resulting disturbance and harassment of
wildlife,and increased hunting and trapping pressure
MITIGATION OPTIONS:During both the construction and post-construction
peri ad there are three opt ions in regard to human access and
activity in the project areas.First of an,n"o effort could be
taken to restrict or control human access or activity;and
secondly,efforts could be taken to totally restrict additional
activity.There is of course a compromise option in which human
access would be permitted during certain times of the year and/or
in certa in are as •
DISCUSSION:The improved access associated with the Susitna Project,
and the potential impact on both furbearer and big game species,
may r1i!present the most severe single avenue of impact resulting
from this project,possibly exceeding in magnitude impacts
assod ated with habitat loss due to inundation and other habitat
disturbing aspects of the project.It is therefore very important
that the negative aspects of this source of impact be minimized to
the gJ~eatestextent poss ib lee Due to the differences in contra 1
options·available,and also differences in the magnitude of the
impact potential,this issue will be considered separately for the
constr'uction period and the post-construction period.
Construction Period ..during this period there will be a great
number'of peop 1e in the area throughout the year and·the potent i a1
for disturbing wildlife is very high.However,during this period
the opportunity for controlling human activity is greatest since
---------_...~---------------
~....
I
-
1'"'"
i
,.
the Inajority of personnel in the area wi 11 be under the direct
control of the camp manager and will be in the area solely for
work purposes.It is antici pated that no publ ic access will be
a 1101N'ed during the construction per;ad.Therefore,although the
potential for negative impact is greatest during the construction
period,the opportunity'to minimize that impact is also available
and s hou ld be used.
Post·-constructionPeriod -It is anticipated that following
construction the access road wi 11 be open to the general publ;c
for ~ihatever use they wish to make of it.The magni tude and
naturoe of human activity during this period should differ from the
const.ruction period and thus different considerations apply to
mitigation options.
RECOMMENDED COURSE OF ACTION:The recommended mitigation actions for
this impact differ from the construction to the post-construction
period and are thus described separately.
Constructjon Period -The general policy suggested for the
construction period is that project personnel have no greater
access to the upper basin than that available to the general
public.It;s therefore recommended that all project personnel be
require<.l to travel directly from the start of the access road
to the camp or work area without stopping except for emergencies.
Personnel should not .be permitted to leave the access road for any
reason including to hunt or trap.If a route from Watana to the
Denali Highway and/or a northern route between Watana and Devil
Canyoln is selected,it is recommended that from mid-April to
mid-Sleptember all traffic on these routes be restricted to a time
period extending from two hours after sunrise to two hours before
sunset in order to provide opportunities for big game species,
especially caribou and brawn bears,to cross the highway without
being disturbed by,traffic.
Post-Construction Period -Following the construction period,when
the r()ad is opened to the general public,it is recommended that
ADF&G monitor the status of big game populations in the area and
-
-
,....
""'"I
,
....
•~J
take whatever regulatory steps can be practically imp 1emented to
prevE!Ot a game harvest in excess of that which would allow for a
sustained yield.In order to minimize undue ~isturbance of
caribou during the calving and post-calving period it is
recommended that ATV activity from the access road be prohibited
from May 1 to August 15 of each year.This will also help reduce
long lasting destruction of vegetation by ATV activity.
"""
•61 l J
IMPACT ISSUE:21-
PROJECT COMPONENT(S):Construction camps
WILDLIFE RESOURCE:Red fox and wolf
PRIORITY RATING:2
F""
i
l
r
r
I
DESCRIPTION OF IMPACT:Possible introduction of rabies by domestic
dogs and the establishment of a feral dog population
MITIGATION.OPTIONS:There are two options available to avoid or
minimize the possibility-of,this impact taking place:1)total
prohibition of all dogs in the camp facilities,or 2)regulations
concE!rning the housing and control of domestic dogs.
DISCUSSION:It is our understanding that at the present time rabies
and feral dogs are not a problem in the upper Susitna basin.The
housing of domestic dogs at the camp facilities represents the
potenti al for both of these situations to change with potenti ally
severe impacts to native carnivores,especially faxes and wolves
which are highly susceptible to rabies.The establishment of a
feral dog population would also be a negative impact although the
severity of that impact is'less than the scenario of a rabies
epidanic.'
RECOMMENDE])COURSE OF ACTION:It is recommended that camp residents be
pennitted to house domestic dogs at the camp under the following
cond i 1:;ons •
1.All dogs must be regi s tered wi th the camp man ager and c erti -
fication of rabies immunization be provided and updated at
appropriate intervals.
2.Dogs must be under control at all times.
3.Any dogs found outside of the fenced camp area,and not .under
direct control of the owner,shall be destroyed by camp
security personnel if attempts to capture the dogs prove
futile.
-----------~--------.....".;------~-------------
..-
IMPACT IS~~:22 PRIORITY RATING:2
-
-
.....
PROJECTCQMPONENT(S):Construction camps and access roads
WILDLIFE RESOURCE:All upper basin wildlife species
DESCRIPTION OF IMPACT:Possible habitat destruction or alteration
resullting from unauthorized fires
MITIGATION OPTIONS:In order to avoid this impact,preventative
measures could be taken to minimi ze the potential for uncontrolled
fires occurring.Adequate fire fighting equipment could be made
available to extinguish any fires that occur.
DISCUSSIO~~:Although the avoidance of this impact is fairly simple and
obvious,since the consequenc.es of fire can be extensive,it is
impor'tant that the proper precautions be recommended and strictly
adher'ed to.
RECOMMENDED COURSE OF ACTION:As part.of the education/orientation
program recommended for workers (Impact Issues 16 and 19),a
portion should deal with fire prevention and fire fighting plans
as well as addressing the need for fire prevention and the
potential harm to wildlife that could result.A program of fire
prevention and fire fighting plans should be prepared by the.camp
manager and strictly enforced.Adequate fire fighting equi pment
and knowledgeable operators should a'lso be available in the event
that a fire occurs.In order to identify the potential for fires
occurring,and-thus the level of preventative measures needed
during periods of high fire potentiaT,camp personnel should
periodically contact the BLM for an evaluation of fire potential.
This 'wi 11 be especi ally important during periods of hot,dry
weath,er.
-""""'1__---------f-------------...--
IMPACT ISSUE:23
PROJECT C:OMPONENT(S):Air traffic
PRIORITY RATING:1
.....
WILDLIFE RESOURCE:All bi g game speci es,raptors,and trumpeter swans
DESCRIPTION Of IMPACT:Di sturbance of norma,1 acti viti es as a result of
air 'traffic,especially low-flying,large helicopters
MITIGATION OPTIONS:Although there is no way to totally avoid
disturbing wildlife as a result of air traffic associated with the
Susitna Project,there are several options available to minimize'
this impact.In general,it will require restrictions in both
altitude and location of flying activity to keep the disturbance
factor taa minimum.Seasonal restrictions wi 11 also prove
helpful in some cases.Since wildlife species vary in their
sensitivity to aircraft disturbance,restrictions could be
developed to avoid the most sensitive species Csuch as brown bears
and Il'Iolves)and be more liberal concerning certain areas or times
of the year that are important to less sensitive species (such as
moosje)•
DISCUSSIOI!:It is antici pated that over time sam'e speci es wi 11
accommodate to air traffic and the negative aspects of disturbance
will be reduced.Other species,trumpeter swans,brown bears;and
wolv4:5,for example may be negatively impacted before any such
adjustment level is achieved,if it is ever achieved.Therefore,
it is very importan~that air traffic restrictions be designed to
minimi ze impact on such sensitive speci es,while at the same time
not being over restrictive in regard to less sensitive species ..
RECOMMENDED COURSE OF ACTION:In order to minimize disturbance due to
air traffic the following restrictions are recommended.
1.All air traffic should fly directly to and from the camp or
\lIlork sites with no unnecessary diversions •
I \, I
-
2.Flight distances and weather permitting,all air traffic
should maintain at least 500 feet altitude above ground
throughout the upper basin during all seasons.
3.A.minimum altitude of 1,000 feet above ground should be
maintained in the following areas un 1ess landing or taki ng
off.
-caribou calving area (May and June)andover any
post-calving aggregations (June and July)
-wolf dens (April through July)
-bald eagle nests (3/15 -8/31)including a horizontal
restriction zone of a 0.25 mi 1eradius
-gyrfa leon nests (2/15 -8/15)including a horizonta 1
restriction zone of a 0.25 mile radius
-golden eagle nests (4/1 -8/31)including a horizontal
restriction zone of a 0.50 mile radius
-the Jay Creek sheep lick (May and June)
-nesting trumpeter swans near the Oshetna River and other
adjacent areas in the upper reaches of the Watana
Impoundment (May through July)
Obviously some of these areas will have to be identified on a
yearly basis in order to keep the location of such critical areas
accurately updated and available for review by personnel
responsible for controlling air traffic.