HomeMy WebLinkAboutAPA4139 September 5, 1989
SUMMARY OF: A Special Report on the Alaska Energy Authority,
Selected Budgetary Practices, Analysis of Personal
Services, and Loan Programs, August 18, 1989.
PURPOSE OF THE REPORT
In accordance with a Legislative Budget and Audit Committee request and
Title 24 of the Alaska Statutes, this special report was prepared to:
(1) report on the budgetary practices of the Alaska Energy Authority
(AEA) for FY 88 and FY 89; (2) analyze the nature and extent that
personal services costs are charged to various AEA capital projects; and
(3) analyze available cash balances as of June 30, 1989 of loan fund
programs administered by AEA.
STATUS OF PROJECTS
As of June 30, 1989 the Alaska Energy Authority (AEA) was administering
over 50 projects and capital appropriations. In order to provide for a
basis for discussing the status and activities associated with various
projects, we have divided them into five general categories: (1)
completed operational projects; (2) projects in the feasibility
assessment phase; (3) rural area projects; (4) hydroelectric projects in
the construction phase; and (5) miscellaneous other projects.
For each category of a project a schedule has been prepared presenting
the total authorizations, expenditures, encumbrances, and the remaining
balance for each project identified as of June 30, 1989.
BUDGET STRUCTURE AND PERSONAL SERVICES
The Alaska Energy Authority's operational budget is made up of four
components: (1) Administration, (2) Capital Improvement Projects (CIPs),
(3) Operations and Maintenance (O&M), and (4) Power Cost Equalization
Program. Most of the administration component of the budget is funded
by non-continuing General Fund appropriations. The CIP component is
primarily funded by continuing General Fund appropriations made for
particular CIP projects and the proceeds from bond sales made to finance
major capital projects. The O&M component is funded from program
receipts earned from the sale of power from three of the four dam pool
projects which are operated by AEA.
Using the Revised Program process, AEA has avoided having to reduce
positions in their administrative component by shifting some of the
costs to capital projects. By doing so, AEA is essentially capitalizing
a certain amount of their administrative costs into the costs of the
projects being developed.
AEA has acknowledged that this transfer of administrative costs to a
major capital project represents a departure from past agency practice.
However, the agency has maintained that this practice ". . .is
consistent with the private sector common practice of capitalizing
administrative costs."
OTHER ADMINISTRATIVE COSTS CHARGED TO PROJECTS
Many of the positions classified and budgeted as CIP positions perform
administrative or support duties for AEA operations. Through the
agency's internal Labor Distribution System, most of the personnel costs
associated with these positions are charged to CIP projects as indirect
labor. This report analyzes the impact of charges of personal services
costs associated with these "administrative" CIP positions compared with
direct personnel costs.
LOAN FUNDS AND BALANCES
As of June 30, 1989 AEA was responsible for administering three
revolving loan funds that provided funding for various projects related
to energy and power development. Our analysis indicates that as of June
30, 1989 the available cash balance for each of these funds was as
follows:
Power Development Revolving Loan Fund $55,711
Rural Electrification Revolving Loan Fund $84,053
Power Project Loan Fund $54,179
UNDERWRITING COSTS
According to an internal report prepared by AEA's Senior Auditor, the
agency incurred $442,474 in underwriting expenses for bonds that were
never issued. Additionally, the agency has incurred more than $120,000
in underwriting costs for bonds that have yet to be issued for the
Bradley Lake Hydroelectric Project.
A SPECIAL REPORT ON THE
DEPARTMENT OF COMMERCE AND ECONOMIC DEVELOPMENT
ALASKA ENERGY AUTHORITY
SELECTED ADMINISTRATIVE PRACTICES
August 18, 1989
Audit Control Number
08-4316-89-S
Alaska Energy Authority Board of Directors
Chairman Robert Martin
Public Member Neil Davis
Public Member Lee Nunn
Commissioner, Department of Commerce and
Economic Development Larry Merculief
Commissioner, Department of Transportation
and Public Facilities Mark S. Hickey
The Adjutant General, Department of
Military and Veterans Affairs John W. Schaeffer
Director of Policy, Office of Management
and Budget, Office of the Governor Mary Halloran
September 5, 1989
Members of the Legislative Budget
and Audit Committee:
In accordance with a Legislative Budget and Audit Committee special
request and the provisions of Title 24 of the Alaska Statutes, the
attached report is submitted for your review.
A SPECIAL REPORT ON THE
DEPARTMENT OF COMMERCE AND ECONOMIC DEVELOPMENT
ALASKA ENERGY AUTHORITY
SELECTED ADMINISTRATIVE PRACTICES
August 18, 1989
Audit Control Number
08-4316-89-S
The audit involves a report on the current status and remaining balances
of various capital projects administered by the Alaska Energy Authority;
selected budgetary and cost accounting practices of the agency; and a
special presentation of the available cash balances in the loan funds
administered by AEA.
The audit was conducted in accordance with generally accepted
governmental performance auditing standards. A further statement of our
audit approach is included in the Report Objectives, Scope, and
Methodology section of this report.
Randy S. Welker, CPA
Legislative Auditor
Division of Legislative Audit
TABLE OF CONTENTS
Page
Report Objectives, Scope, and Methodology . . . . . . 1
Organization and Function . . . . . . . . . . . . . . 3
Status of Projects. . . . . . . . . . . . . . . . . . 5
Budget Structure and Personal Services. . . . . . . . 13
Loan Funds and Balances . . . . . . . . . . . . . . . 21
Underwriting Expenditures . . . . . . . . . . . . . . 25
Agency Response:
Alaska Energy Authority . . . . . . . . . . . . . . 27
-1-
REPORT OBJECTIVES, SCOPE, AND METHODOLOGY
In accordance with a Legislative Budget and Audit Committee request and
Title 24 of the Alaska Statutes, this special report was prepared to:
(1) report on the budgetary practices of the Alaska Energy Authority
(AEA) for FY 88 and FY 89; (2) analyze the nature and extent that
personal services costs are charged to various AEA capital projects;
and (3) analyze available cash balances as of June 30, 1989 of loan fund
programs administered by AEA.
Objectives
The specific objectives of this report were to respond to specific
interests expressed by the Legislative Budget and Committee's audit
request. The following selected management practices or areas of
interest and concern were reviewed:
1. The unexpended and unobligated balance of the capital projects
administered by the Alaska Energy Authority.
2. The use of capital project funds to support the agency's
administrative costs.
3. The existing and projected balances of the energy loan funds
administered by the Alaska Energy Authority.
4. An accounting of bond counsel and underwriting expenditures for
projects for which bonds have not been or yet to have been issued.
Scope
The scope of our review involved both FY 88 and FY 89, although
depending on what aspect of objectives were being addressed and the
availability of information, different fiscal years' activities were
emphasized.
Budgetary practices for both FY 88 and FY 89 are included in this
report. Although how personal services costs associated with AEA
administration were charged to capital projects was analyzed for both
fiscal years, the report primarily focuses on FY 88 activity. Loan fund
balances and analysis are as of the end of FY 89. The accounting of
various underwriting and bond counsel costs are from inception to the
last day of fieldwork.
Methodology
In the course of preparing this report we relied on the following
sources of information:
1. Internal budget and financial planning documents prepared and used
by AEA.
2. Accounting information as recorded on the State's accounting
system (AKSAS).
3. Internal accounting information generated by AEA's Labor
Distribution System.
4. Schedules prepared by AEA accounting staff, which were reconciled
to AKSAS.
-2-
5. Informational documents that AEA makes available to the general
public, including annual audited financial statements, capital
projects status report summary, and the agency's annual report.
From this assortment of information we developed the analysis and
presentation necessary to respond to the objectives of our report and
address the concerns expressed by the Legislative Budget and Audit
Committee in their special audit request.
-3-
ORGANIZATION AND FUNCTION
The Alaska Energy Authority (formerly named the Alaska Power Authority),
was established in 1976 "to promote, develop, and advance the general
prosperity and economic development of the people of Alaska by providing
a means of constructing, acquiring, financing, and operating (1) power
projects and (2) facilities that recover and use waste energy."
To accomplish these goals, Alaska Energy Authority (AEA) conducts
reconnaissance and feasibility studies; designs, constructs, and
operates power projects; issues bonds; administers loan and grant
programs; and enters into contracts for the sale of power and waste
heat. The extent of AEA's involvement in any power project depends upon
local needs and preferences, project financial requirements, and state
budget considerations.
AS 44.83.020 establishes AEA as a public corporation of the State within
the Department of Commerce and Economic Development but with separate
and independent legal existence. Consequently, AEA is governed by a
seven-member Board of Directors, including the Commissioners of the
Departments of Commerce and Economic Development, Military and Veterans
Affairs, and Transportation and Public Facilities; the Director of the
Office of Management and Budget; and three members at large appointed by
the Governor.
With a staff of more than 70, AEA administers the various capital funds
for identified power development projects throughout the State. The
agency administers three loan funds to assist in the energy production
and development, and will assume administration of the Bulk Fuel
Revolving Loan Fund during FY 90. AEA also administers the State's
Power Cost Equalization program, aimed primarily at subsidizing the cost
of power in rural areas of the State.
-4-
Alaska Energy Authority
Completed Projects
Schedule of Authorizations, Expenditures, Encumbrances, and
Remaining Project Balances
As of June 30, 1989
(UNAUDITED)
Total Expenditures Remaining
Authorizations thru 6-30-89 Encumbrances Balance
Terror Lake $202,639,156 $198,468,746 $ 2,250 $ 4,168,160
Tyee Lake 131,113,397 127,461,236 1,000 3,651,161
Anchorage-Fairbanks Intertie 128,463,119 125,326,360 35,816 3,100,943
Swan Lake 95,755,046 94,795,049 2,250 957,747
Solomon Gulch 48,351,728 48,222,513 51,000 78,215
Craig-Klawock Intertie 750,000 749,735 -0- 265
Total Completed Projects $607,072,446 $595,023,639 $92,316 $11,956,491
-6-
STATUS OF PROJECTS
As of June 30, 1989 the Alaska Energy Authority (AEA) was administering
over 50 projects and capital appropriations. At the end of each
calendar year the agency prepares a report summarizing the status and
funding of the various projects. In addition, the report provides a
description of the project, what was accomplished during the past year,
and what activities are planned for the project in the upcoming year.
In order to provide a basis for discussing the status and activities
associated with various projects, AEA's projects were divided them into
five general categories: (1) completed operational projects; (2)
projects in the feasibility assessment phase; (3) rural area projects;
(4) hydroelectric projects in the construction phase; and (5)
miscellaneous other projects.
Completed Projects
The schedule on the opposite page summarizes the six projects classified
as completed and operating projects. Only those projects owned and
operated by AEA are included in this category. Other projects completed
on behalf of local communities/utilities are classified elsewhere (such
as the Chester Lake project which is classified under the Rural Projects
category).
The hydroelectric projects that make up the Four Dam Pool are included
in this category. Although these projects are on-line and operational,
AEA is still incurring some incidental construction-related
expenditures, which are being charged to the projects. These most
recent year charges represent a minor part of the projects' overall
costs.
According to AEA's January 1989 project status report, remaining items
to be addressed for these projects include those associated with Federal
Energy Regulatory Commission (FERC) compliance and licensing standards,
safety features, completion of construction items, and cost of
litigation. These final construction costs are anticipated to be
substantially completed by January of 1991.
The Anchorage-Fairbanks Intertie is a 170-mile, 345 KV transmission line
which connects the existing power generating systems of southcentral
Alaska with the Fairbanks area. The system has been operational since
1985. AEA recently received a claims settlement of more than $3 million
from the project's design engineer.
-7-
Alaska Energy Authority
Feasibility Projects
Schedule of Authorizations, Expenditures, Encumbrances, and
Remaining Project Balances
As of June 30, 1989
(UNAUDITED)
Total Expenditures Remaining
Project Authorizations thru 6-30-89 Encumbrances Balance
Susitna Feasibility $135,182,776 $135,182,776 $ -0- $ -0-
Black Bear Lake 3,247,053 3,233,571 -0- 13,482
Cordova Hydroelectric 2,196,304 2,183,300 -0- 13,004
Railbelt Energy Alternatives 2,091,500 1,986,669 33,903 70,928
Grant Lake 1,696,608 1,696,608 -0- -0-
Southeast Intertie 799,000 678,848 40,198 79,954
Larsen Bay 280,000 231,783 -0- 48,217
Stream Gauging Projects 63,700 36,357 18,100 9,243
Kotzebue - Nome Coal Study 150,000 28,694 121,306 -0-
Manokotak - Dillingham Intertie 35,000 25,466 9,428 106
Total Feasibility Projects $145,741,941 $145,284,072 $222,935 $234,934
The Craig-Klawock transmission line is a recently completed project
that services the two communities in southern Southeast Alaska. The
Craig-Klawock Intertie consists of 5.5 miles of transmission line that
is leased, operated, and maintained by Alaska Power and Telephone. The
line has been operational since January 1988 and has provided for the
transfer of lower cost power from Craig to the Klawock service area.
Feasibility Projects
Included in this group of projects are appropriations made for
feasibility assessments of relatively larger scale projects which, for
the most part, were anticipated to serve urban areas. The most
significant project in this group is the extensive feasibility study
done of the Susitna Hydroelectric project.
In FY 89 AEA charged almost $6,000 to Susitna wind-down activities.
Local entities serving Prince of Wales Island and Seward are pursuing
FERC licensing for the Black Bear Lake and Grant Lake projects,
respectively. In FY 89 AEA charged less than $6,000 to the Black Bear
project and had made no charges to Grant Lake. According to AEA, the
remaining balance of the Black Bear Lake appropriation is needed to
cover costs incurred by the agency in providing technical assistance to
local utility which is seeking an FERC license for the project.
Projects with relatively larger remaining balances - the Railbelt
Energy Alternatives Study, Southeast Intertie feasibility, and Larsen
Bay feasibility projects continue to be the most active projects in
this category.
With FY 89 expenditures of more than $1 million, the Railbelt Energy
alternatives study was the most active feasibility project administered
by AEA during the past fiscal year. According to the January 1989
project's summary report, it was anticipated that the overall
alternative study would be completed in final form by mid-1989. The
alternatives study will present information regarding feasibility and
costs of meeting the energy demand of Railbelt consumers. It reviews
alternatives involving extended interties between Anchorage and Kenai,
upgrading of the Anchorage-Fairbanks intertie, or construction of a new
line between Anchorage and Fairbanks via Glenallen. In addition, the
final report addresses power supply plans without the proposed
interties and analyzes the merits of more consumer conservation, coal,
and natural gas pipeline alternatives.
The focus of the Southeast Intertie feasibility analysis has been
affected by the recent upswing in mining activity in that region of the
-8-
State. Projections of energy demand are being reevaluated in light of
the actual and anticipated increases for energy demand. The Larsen Bay
hydroelectric project feasibility study has been completed, and the
city of Larsen Bay is undertaking construction of the project utilizing
a $493,694 loan from the Power Project Revolving Loan Fund.
Rural Area Projects
Projects in this category are generally smaller scale, aimed at
providing affordable power to a limited number of potential customers
in the rural parts of the State. The appropriations in this category
are for specific projects in identified communities or are for programs
that provide assistance to various rural communities in developing
power generation and distribution facilities.
The non-community specific projects in this category are all aimed at
improving access to, and efficiency of, power supplies in rural Alaska.
The projects include the rural electrification, community feasibility,
construction assistance, technical assistance, waste heat, regional
feasibilities, rural energy reconnaissance, and the metering
installation survey. In AEA's annual capital projects status report
the various communities served by these projects are listed.
Appropriations received for specifically identified projects cover all
aspects of power generation and development. Specific projects range
from the more than $4 million Chester Lake project, which has been
operational since May 1988, to a much smaller $15,535 appropriation for
a reconnaissance study for a Port Alsworth electrical system.
Based on the amount of FY 89 expenditures compared to the total
inception to date expenditures listed in the schedule above, AEA
focused a great deal of attention on the completion of rural projects
during the past year. In particular, the following seven projects
either had significant progress or were completed during the past
fiscal year:
1. Chignik Lake ($198,008 in FY 89 expenditures) - This project was
a result of design and preconstruction engineering funding
provided by rural community feasibility funds in FY 81. State
appropriations were combined with $26,000 in federal funds to
construct a power generation and transmission facility.
2. Quinhagak Electrification ($125,599) - This project is
essentially complete and represents construction of a new
distribution system. In addition to AEA funds, the community
utilized a $400,000 municipal grant from the Department of
Administration.
3. Ouzinkie Hydroelectric Project ($108,745) - This project involved
the design and construction of a 117 kilowatt hydroelectric
project. Actual total costs of the completion of the project were
approximately $610,000. This project funding represented a grant
to cover part of the community's costs associated with this
project.
4. Brevig Mission Upgrade ($107,158) - This project replaced a low
voltage distribution system with a more efficient high voltage
system capable of accommodating 20 new homes built in the
community. The project should be complete and closed by January
1990.
-9-
5. Napaskiak Power Plant Upgrade ($100,000) - This project involved
relocating the community's power plant and fuel storage tanks in
addition to upgrading the electrical distribution system.
6. Tatitlek Electrification ($99,468) - This project is completed
and involved replacement of an unsafe, unreliable, and outgrown
overhead distribution system with a high voltage underground
system.
7. Unalaska Generator Upgrade ($50,000) - This project involved
upgrading the community's generation capacity in response to
increased demand brought on by seafood processors connecting to
the city's electrical system.
In addition to the significant recent expenditure activity for these
projects, all expenditures reported in the schedule for the White
Mountain Power System Upgrade, Eagle region villages, and Chalkyitsik
Electrification projects were made during FY 89. This suggests that
these projects are just beginning to get off of the ground and probably
will involve significant activity in FY 90.
Major Projects in Construction
Bradley Lake is the largest project currently being managed by AEA. The
90 megawatt project is located near Homer and will contribute to the
generating capacity of Alaska's railbelt area. Recently, AEA has
revised downward its estimate of completion costs to $328,000,000 net of
financing costs. As of mid-August 1989 it was estimated that the
project was halfway completed.
Miscellaneous Projects
The largest appropriation in this category is for enhancing AEA's
information processing system. The project has allowed AEA to automate
the agency's contract administration systems, project cost management
systems, and accounting systems. Currently AEA in consultation with the
Department of Administration's Division of Finance is seeking a cost
effective automated accounting system that can be integrated into the
State's accounting system structure.
The State Energy Policy Task Force was a group of 22 individuals (13
from the public, 4 from the Executive Branch, and 5 legislators) which
reviewed the State's energy policy and programs. The task focused on
issues such as energy program organization, the Power Cost Equalization
Program, energy conservation programs, and power project financing.
-8-
Alaska Energy Authority
Rural Area Projects
Schedule of Authorizations, Expenditures, Encumbrances, and
Remaining Project Balances
As of June 30, 1989
(UNAUDITED)
Total Expenditures Remaining
Authorizations thru 6-30-89 Encumbrances Balance
Waste Heat Projects (Note 1) $ 6,831,000 $ 5,899,231 $133,714 $ 798,055
Chester Lake (Note 2) 4,031,700 4,012,365 14,190 5,145
Rural Electrification 3,106,000 2,803,412 85,469 217,119
Rural Community Feasibility 2,982,453 2,720,923 8,961 252,569
Bethel Region 1,254,800 1,253,369 -0- 1,431
Rural Energy Construction
Assistance (Note 3) 1,000,000 340,748 -0- 659,252
Rural Technical Assistance 617,973 592,750 22,801 2,422
Regional Feasibility Program 505,000 502,123 -0- 2,877
Rural System Efficiency Improvement 300,000 236,800 61,753 1,447
Ouzinkie Hydroelectric 260,000 260,000 -0- -0-
Nikolai Electrical System 250,000 166,760 83,240 -0-
Rural Energy Reconnaissance 250,000 227,339 1,767 20,894
Chignik Lake 199,000 198,515 -0- 485
Quinhagak Electrical Project 152,000 136,898 -0- 15,102
Hope Electrical Line Extension 150,000 50,693 95,000 4,307
Brevig Mission 144,900 107,158 -0- 37,742
Red Devil Electrification 125,000 107,920 17,080 -0-
Bethel Intertie 102,551 83,591 2,400 16,560
Napaskiak Power Plant Upgrade 100,000 100,000 -0- -0-
Tatilek Electrification 100,000 99,750 250 -0-
Metering Installation Survey 100,000 99,641 430 (71)
White Mountain Power System Upgrade 75,000 39,020 30,837 5,143
Eagle Region Communities 65,000 6,572 20,000 38,428
Chalkyitsik Electrification 51,300 21,881 -0- 29,419
Unalaska Generator Upgrade 50,000 50,000 -0- -0-
Yakutat Waste Heat 36,000 33,824 -0- 2,176
Port Alsworth Electrical Project 15,535 14,818 -0- 717
Total Rural Projects $22,855,212 $20,166,101 $577,892 $2,111,219
Note 1: AEA has completed, owns, and operates approximately $3,500,000 of waste heat
projects located in rural Alaska. Revenues from the sale of energy from these projects
fund a portion of the agency's operations.
Note 2: Chester Lake is owned by the Metlakatla community and is operated by Metlakatla
Power and Light.
Note 3: The rural energy construction assistance project is funded entirely from funds from
local communities that are used to "purchase" technical assistance from AEA.
-15-
Alaska Energy Authority
Bradley Lake Hydroelectric Project
Schedule of Authorizations, Expenditures, Encumbrances, and
Remaining Project Balances
As of June 30, 1989
(UNAUDITED)
Total Expenditures Remaining
Authorizations thru 6-30-89 Encumbrances
Balance
Bradley Lake (Note 1) $442,580,000 $110,574,138 $ -0-
$332,005,862
Note 1: Authorizations for Bradley Lake represent the following:
General Fund Appropriations $175,080,000
Bond Proceeds 267,500,000
Total Authorizations $442,580,000
Alaska Energy Authority
Miscellaneous Projects
Schedule of Authorizations, Expenditures, Encumbrances, and
Remaining Project Balances
As of June 30, 1989
(UNAUDITED)
Total Expenditures Remaining
Authorizations thru 6-30-89 Encumbrances Balance
Management Information
Study $505,000 $504,609 $ -0- $ 391
Energy Policy Task
Force 200,000 200,000 -0- -0-
Snettisham Project
Transfer 74,178 46,047 25,798 2,333
Total $779,178 $750,656 $25,798 $2,724
-16-
BUDGET STRUCTURE AND PERSONAL SERVICES
The Alaska Energy Authority's (AEA) operational budget is made up of
four components: (1) Administration, (2) Capital Improvement Projects
(CIPs), (3) Operations and Maintenance (O&M), and (4) Power Cost
Equalization Program. Most of the administration component of the
budget is funded by non-continuing General Fund appropriations. The CIP
component is primarily funded by continuing General Fund appropriations
made for particular CIP projects and the proceeds from bond sales made
to finance major capital projects. The O&M component is funded from
program receipts earned from the sale and transmission of power from the
six electric facilities owned by AEA in addition to revenues from waste
heat sales.
In response to legislative reductions of funds, but not of positions, in
the FY 88 administration budget component, and in order to fund the
number of authorized positions in the final budget, AEA began shifting
some of that component's costs to the CIP component. The diagram on the
following page illustrates the reallocation of personal services
expenditures between the agency's budgetary components.
Using the Revised Program (RP) process, AEA transferred the funding of
two administrative positions (Accountant and Analyst Programmer) to the
CIP portion of their budget. In addition, AEA began transferring select
percentages of personal services costs associated with management and
administrative positions in their administration component to projects
in the CIP component of their budget. The inset
to the right provides a break-down of the positions and the portion of
their personal services reallocated to CIP projects.
At the time that these transfers were approved, it was estimated that
they represented almost $97,000 in personal services costs. Another 40%
of the personal services costs for the director of Program Development
and Facilities was transferred to the O&M component. This combination
of transferring all or a percentage of personal services costs allowed
AEA to meet the Legislature's $179,900 personal services reduction in
their FY 88 Administration budget component.
Response to FY 89 Budget Reductions
The FY 89 budget act reduced AEA's FY 89 administrative budget's
personal services component to $600,000 from the agency's requested
amount of $847,100. AEA received a supplemental appropriation of
$120,000 for this component, thus resulting in a net reduction of
$127,100. Although the agency stated in the FY 88 RP request that they
did not anticipate continuing the shift of administration component
costs to the CIP component, the $127,100 personal services budget
required continuation of the practice. AEA reevaluated some of the
percentages and the administrative positions that were charged to
Bradley Lake and the Railbelt Alternatives Study for FY 89. In addition
to charging 40% of the director of Program Development and Facilities'
personal services to the O&M component, the agency processed a new FY 89
RP which transferred a portion of administration component personal
service costs to the agency's capital project component. See the inset
at left for a breakdown of personal services' percentages transferred.
FY 90
For FY 90, AEA's final proposed budget for personal services in the
administrative component was for $866,100. The amount represented the
prior year's budget level of $720,000 with the $127,000 cut restored and
an increase of $19,000 for increased costs associated with health care
benefits. AEA received a final administration component personal
-17-
services budget of $787,900, a reduction of $78,200. AEA anticipates
continuing allocation of administration component personal services
costs to the CIP and O&M components for the upcoming fiscal year.
Essentially, AEA has avoided having to reduce positions in their
administration component by shifting some of the costs to capital
projects. By doing so, AEA is essentially capitalizing a certain amount
of their administrative costs into the costs of the projects being
developed.
AEA notes in the narrative of the first FY 88 budget RP request that
charging a portion of personal services costs of administration to major
capital project represents a departure from past AEA practice. The
narrative goes on to note, however, that this practice ". . .is
consistent with the private sector common practice of capitalizing
administrative costs."
Capital Project Positions
In the inset below is a schedule of positions that were included in the
FY 88 AEA Budget as CIP Positions. Although some of these positions
have been eliminated and others have been reclassified for FY 89 and FY
90, the general nature of CIP positions has essentially remained the
same.
Individuals in these positions complete time sheets each two weeks
recording what projects they worked on during the period. Personal
services costs associated with these positions are charged to various
CIP projects based upon these time sheets. Projects are charged direct
personal services expenditures when the time sheets reflect that
individuals specifically worked on an identified project.
The projects also receive an allocation of indirect personal service
charges which are generated from individuals recording their time to the
performance of administrative overhead functions.
Projects receive an allocation of indirect personal service expenditures
based on the amount of direct personal service costs which have been
charged to the project. At the direction of AEA management, not all
projects receive indirect personal services charges. Most of the rural,
smaller scale projects are not charged with any indirect personal
services costs. AEA management decisions regarding which projects
receive allocations of indirect costs are based on the project's
budgetary constraints. Very often AEA receives appropriations for the
bare cost of procuring equipment for a small community; in those cases
AEA generally charges any associated agency personal services costs to
one of the more "generic" rural/regional program support projects. The
schedule on the following page presents a comparison of FY 88 direct and
indirect personal services as recorded for twelve major projects on the
State's accounting system.
CIP Positions with Administrative Functions
Many of the positions classified and budgeted as CIP positions perform
administrative or support duties for AEA operations. Although they are
involved with and support AEA projects, positions such as Public
Information Officer, Graphics Specialist, various Accountant/Auditor
positions, Personnel Officer, Records/Library Supervisor, and
Information Systems Supervisor indicate duties that provide general
administrative services to all of AEA operations.
Through the agency's internal Labor Distribution System, most of the
personnel costs associated with these positions are charged to CIP
projects, as indirect labor. To analyze the impact of these
-18-
"administrative" CIP positions, we reviewed the FY 88 indirect cost
charges for selected positions that appear to us to perform
administrative duties. Positions in bold print on the CIP position
schedule on page 16 were selected for further analysis.
These positions' indirect costs made up approximately half of the FY 88
indirect labor charges made to the Bradley Lake project. These
positions' costs made up over 40% of the costs charged to the Southeast
Intertie study project. The pie charts on page 19 illustrate the
breakdown between direct labor charges, indirect CIP labor charges, and
indirect administrative CIP labor charges for twelve selected projects.
Functions associated with project wrap-up and closing are more
administrative in nature than engineering or technical. For example,
the major work effort involved with closing the Susitna Feasibility
project was the organization, microfilming, and storage of project
records. Accordingly, the relatively higher amount of charges for
administrative CIP positions to projects in the wind-down stages such as
Susitna (68.2%), Tyee Lake (57.3%), and Terror Lake (55.2%) can be
attributed to the nature of the workload involved.
-15-
Alaska Energy Authority
Schedule of Personal Services Charges
For Major Capital Projects
For the Year Ending June 30, 1988
CIP Admin Pct. of Pct. of
Direct Indirect Indirect Admin CIP Admin CIP
Personal Personal Personal Indirect to Indirect to
Name of Project Services Services Services Tot. Indirect Total Pers. Svcs.
Bradley Lake $ 509,702 $253,217 $116,298 45.93% 15.2%
Railbelt Energy Alternative 97,095 89,073 33,027 37.1 17.7
Waste Heat Products 70,746 48,950 21,030 43.0 17.6
Terror Lake Hydro 102,729 48,192 26,611 55.2 17.6
Susitna Feasibility 108,748 30,747 20,967 68.2 15.0
Rural Electric Projects 36,958 25,912 9,514 36.7 15.1
Anchorage/Fairbanks Intertie 98,049 24,668 10,801 43.8 8.8
Tyee Lake 25,518 16,159 9,238 57.2 22.2
Southeast Intertie 19,743 22,968 7,684 33.5 18.0
Solomon Gulch 19,348 11,788 8,659 73.5 27.8
Chester Lake 16,170 10,711 1,516 14.2 5.6
Swan Lake 13,432 9,618 4,646 48.3 20.2
Total $1,118,238 $592,003 $269,991 45.6% 15.8%
Analysis of Power Development Revolving Loan Fund:
Appropriations to the Fund, Inception to Date $210,000,000.00
Less: Appropriations Lapsed Back to the
General Fund (59,846,062.70)
Net Appropriations to the Fund, Inception to Date $150,153,937.30
Cash Provided by Income to Fund 40,141,669.78
Total Cash Available for Loans,
Inception To Date $190,295,607.08
Less:
Loans Outstanding as of June 30, 1989 (185,239,896.17)
Cash Reserved for Self-Insurance Fund (5,000,000.00)
Available Cash Balance as of June 30, 1989 $ 55,710.91
Analysis of Rural Electrification Revolving Loan Fund:
Appropriations to the Fund, Inception to Date $6,720,100.00
Less: Appropriations Lapsed Back to the
General Fund (1,614,900.00)
Net Appropriations to the Fund, Inception to Date $5,105,200.00
Less:
Loans Outstanding as of June 30, 1989 (4,488,377.65)
Loan Administration Expenses, FY 88 & FY 89 (14,979.27)
Cash Balance as of June 30, 1989 $ 601,843.08
Less: Loans Obligated but not Disbursed 517,790.40
Available Cash Balance as of June 30, 1989 $ 84,052.68
-16-
LOAN FUNDS AND BALANCES
As of June 30, 1989 AEA was responsible for administering two revolving
loan funds that provided funding for various projects related to energy
and power development: (1) the Rural Electrification Revolving Loan
Fund, and (2) the Power Project Loan Fund. In addition, AEA assumed
responsibility as of July 1, 1989 for the administration of two other
energy-related loan funds: (1) the Power Development Revolving Loan
Fund, and (2) the Bulk Fuel Revolving Loan Fund. In accordance with the
special request and the objectives of our review, we have analyzed the
four funds in order to determine the available cash balance of each
fund.
Power Development Revolving Loan Fund
Under the loan fund's terms as set out in AS 44.33.600 the Power
Development Revolving Loan Fund is made up of legislative
appropriations, repayments of principal, and both the income from the
investment of the fund's cash balance and from projects financed by
loans from the fund.
Loans for the construction of the Four-Dam Pool projects make up the
bulk of the outstanding loans. Since its inception in 1984, the fund
has received $210 million in appropriations, over $40 million in income
from power sales agreements, interest, and investment of available cash
balances. Beginning in 1985, almost $60 million has been lapsed back to
the General fund. The schedule on the opposite page provides a summary
of cash sources, uses, and available balance from inception through June
30, 1989. The totals presented are unaudited and were compiled from
AEA's accounting records.
Rural Electrification Revolving Loan Fund
Under the loan fund's terms as set out in AS 44.83.361 the Rural
Electrification Revolving Loan Fund (RERLF) is made up of legislative
appropriations and repayments of principal. Any interest earned on
RERLF loans is put into the State's General Fund.
Loans are made only to electric utilities certified by the Alaska Public
Utilities Commission. Loans may be made only for the extension of new
electric service into an area of the State that an electric utility may
serve under a certificate of public convenience. As of June 30, 1989
RERLF had made thirteen loans totaling more than $5.2 million (although
as of that date only $4.75 million in proceeds had been disbursed).
The schedule below provides a summary of cash sources, uses, and
available balance from inception through June 30, 1989. The schedule
presented on the opposite page was compiled, unaudited, from AEA's
accounting records.
Power Project Fund
Under the loan fund's terms as set out in AS 44.83.170 the Power Project
Loan Fund (PPLF) is made up of only funds appropriated by the
legislature. Any repayments of principal and the interest earned on
PPLF loans are put into the State's General Fund.
Loans may be made for a wide range of power development activities,
ranging from the financing of reconnaissance and feasibility studies to
the construction or expansion of power generation facilities. Projects
may involve fossil fuel, wind power, tidal power, geothermal, biomass,
hydroelectric, solar or other non-nuclear energy source.
-17-
Currently, AEA has 35 outstanding loan obligations for just over $34.6
million. The loans vary in terms ranging from 1 year to 35 years, and
interest varies from 5% to 9.95%. Borrowers generally are required to
make semi-annual payments due on the first of January and July. The
schedule below provides a summary of cash sources, uses, and available
balance from inception through June 30, 1989. The totals presented
below are unaudited and were compiled from AEA's accounting records.
Appropriations to the Fund, Inception-to-Date $40,400,000.00
Funds Received through Reimbursable
Service Agreements 700,000.00
Less: Appropriations Lapsed Back to the
General Fund (2,377,000.00)
Net Appropriations to the Fund, Inception
to Date $38,723,000.00
Less:
Total Loans Committed, as of June 30, 1989 (34,633,029.91)
Loans Retired, as of June 30, 1989 (4,000,000.00)
Loan Administration Expenses, FY 88 & FY 89 (35,791.52)
Available Cash Balance as of June 30, 1989 $ 54,178.57
Bulk Fuel Revolving Loan Fund
Under the loan fund's terms as set out in AS 45.87.010-.500, the Bulk
Fuel Revolving Loan Fund (BFRLF) is made up of general fund
appropriations and repayments of principal. Any repayments of interest
associated with BFRLF loans are credited to the State's General Fund.
All loans have a one-year term and can be made up for no more than
$50,000. Only communities with a population of less than 2,000 are
eligible to apply. Loans may be made to private individuals if endorsed
by a qualified community. Interest charged on loans varies. The
statute allows the rate to be set up to the maximum of the percentage of
the average weekly yield of municipal bonds for the 12 months preceding
the date of the loan.
The schedule below is an analysis of available cash in BFRLF as of
August 22, 1989.
Appropriations to the Fund, Inception to date $1,974,427
Add:
Reserves not involving cash outlay 53,908
Cash available for Loans and Expenses $2,028,335
Less:
Loans Outstanding 710,570
Loans Committed, Not Disbursed 682,671
Loan Administration Expenses 145,309
Available Cash Balance as of August 22, 1989 $ 489,785
-18-
(Intentionally left blank)
-25-
UNDERWRITING EXPENDITURES
According to an internal memorandum prepared by AEA's senior auditor,
the Authority incurred $442,474 in consulting engineer fees for
financing which were never obtained. According to the memorandum,
in 1983, the Power Authority contracted with R. W. Beck to
provide consulting engineering services. One part of the
scope of Beck's work was to provide services related to the
long-term financing of various Power Authority projects.
[Beck was paid] $442,474 for services in this category
related to the Four Dam Pool projects for which long-term
bond financing was pursued but not placed.
The memorandum goes on to point out that through the use of contingency
conditions in contracts with financial advisors and bond counsel AEA
avoided fees of at least $171,451. Contracts were negotiated with the
firms of First Southwest Company, Wohlforth & Flint, and John Nuveen &
Co. to provide financial advisor, bond counsel, and underwriter services
for the proposed financing of the Four Dam Pool projects.
These contracts were contingent upon the amount of bonds actually issued
and, accordingly, no payment was made for work on projects for which
bonds were not issued. Power authority records indicate that First
Southwest and Wohlforth and Flint had accumulated billings of $171,451
associated with financing never pursued.
Bradley Lake Long-Term Financing
The memorandum further relates to the following discussion of
underwriting costs for long-term financing for the Bradley Lake project
that has yet to be placed:
Variable rate demand bonds were issued in November,
1985 to provide the funds needed during construction
[of the Bradley Lake Project]; these bonds will be
redeemed with the proceeds of long-term bonds to be
issued by completion of the project. As of January
1989, expenditures related to the future issuance of
the long-term bonds total $120,721. . . .
Additionally in November 1988, a competitive contract
was awarded to R. W. Beck to provide services as
Consulting Engineer. The contract provides for a
maximum of $112,000 to be paid to R.W. Beck.
-26-
(Intentionally left blank)