HomeMy WebLinkAboutSuWa184Alaska Resources Library & Information Services
Susitna-Watana Hydroelectric Project Document
ARLIS Uniform Cover Page
Title:
Alaska Railbelt regional integrated resource plan (RIRP) : draft report
presentation
SuWa 184
Author(s) – Personal:
Author(s) – Corporate:
Black & Veatch
AEA-identified category, if specified:
AEA-identified series, if specified:
Series (ARLIS-assigned report number):
Susitna-Watana Hydroelectric Project document number 184
Existing numbers on document:
Published by:
[Overland Park, Kan. : Black & Veatch, 2009]
Date published:
December 10, 2009
Published for:
Date or date range of report:
Volume and/or Part numbers:
Final or Draft status, as indicated:
Draft
Document type:
Slide presentation. No commentary.
Pagination:
88 p.
Related work(s):
Pages added/changed by ARLIS:
Notes:
All reports in the Susitna-Watana Hydroelectric Project Document series include an ARLIS-
produced cover page and an ARLIS-assigned number for uniformity and citability. All reports
are posted online at http://www.arlis.org/resources/susitna-watana/
Alaska Railbelt
Regional Integrated Resource Plan (RIRP)
December 10, 2009
Draft Report Presentation
December 10, 2009Page -1
Agenda
Introductory Comments and Introductions
Project Overview/Executive Summary
Situational Assessment
Methodology Considerations
Key Assumptions
Susitna Analysis
Summary of Results
Financial Analysis
Risks and Uncertainties
Implementation Action Plan (2010-2012)
Questions and Answers
Concluding Comments
December 10, 2009Page -2
Consultant Team
Black & Veatch –Prime
HDR, Inc. –Susitna Analysis
EPS, Inc. –Transmission Stability Analysis
Seattle-Northwest Securities –Financial Analysis
December 10, 2009Page -3
Advisory Working Group Members
Norman Rokeberg, Retired State of Alaska Representative, Chairman
Chris Rose, Renewable Energy Alaska Project
Brad Janorschke, Homer Electric Association
Carri Lockhart, Marathon Oil Company
Colleen Starring, Enstar Natural Gas Company
Debra Schnebel, Scott Balice Strategies
Jan Wilson, Regulatory Commission of Alaska
Jim Sykes, Alaska Public Interest Group
Lois Lester, AARP
Marilyn Leland, Alaska Power Association
Mark Foster, Mark A. Foster & Associates
Nick Goodman, TDX Power, Inc.
Pat Lavin, National Wildlife Federation -Alaska
Steve Denton, Usibelli Coal Mine, Inc.
Tony Izzo, TMI Consulting
December 10, 2009Page -4
Project Overview / Executive
Summary
December 10, 2009Page -5
Some Definitions
REGA means “Railbelt Electrical Grid Authority”
GRETC means “Greater Railbelt Energy &
Transmission Company”
RIRP means “Railbelt Integrated Resource
Plan”
REGA study determined the business structure for
future Railbelt G&T
GRETC initiative is the joint effort between Railbelt
Utilities and AEA to unify Railbelt G&T
RIRP is the economic plan for future capital
investment in G&T and in fuel portfolios that
GRETC would build, own and operate
Three Discrete Tasks
December 10, 2009Page -6
What is an RIRP?
Current
Situation
•Limited redundancy
•Limited economies
of scale
•Dependence on
fossil fuels
•Limited Cook Inlet
gas deliverability
and storage
•Aging G&T
infrastructure
•Inefficient fuel use
•Difficult financing
•Duplicative G&T
expertise
RIRP Study
•Plan that economically
schedules what, when,
and where to build, based
on available fuel and
energy supplies
•50-year time horizon
•Competes generation,
transmission, fuel supply
and DSM/energy
efficiency options
•Includes CO2 regulation
•Includes renewable
energy projects
•Arrives at a plan to build
future infrastructure for
minimum long-run cost to
ratepayers
•Considers fuel supply
options and risks
December 10, 2009Page -7
Limitations of RIRP
Does not set State energy policy
Directional
Identified/generic/actual projects
Agnostic to owner/developer of projects
December 10, 2009Page -8
GRETC Vision
A statutory company
Privately owned not-for-profit company with public
responsibilities defined in law
Own and operate Railbelt power generators and
transmission lines
Build infrastructure specified in the RIRP
Significant financial muscle to shoulder long-term debt
Make use of State and federal financial underwriting
To benefit all Railbelt ratepayers equally
Regulated by RCA under tailored regulations or non-
jurisdictional with strong bond covenants
December 10, 2009Page -9
Stakeholder Involvement Process
December 10, 2009Page -10
Key Drivers
Resource-specific risks
Gas availability and price
Acceptability of large hydro and other renewables
Potential CO2 costs
Limited transmission network
Required financing
Regional vs. individual utility focus
December 10, 2009Page -11
Evaluation Scenarios
December 10, 2009Page -12
Results –DSM/EE Resources
Energy Requirements (MWh)
0
1,000,000
2,000,000
3,000,000
4,000,000
5,000,000
6,000,000
7,000,000
8,000,000
20112014201720202023202620292032203520382041204420472050205320562059YearEnergy Requirements (MWh)Without DSM/EE
With DSM/EE
December 10, 2009Page -13
Results –Scenario 1A
Energy By Resource Type
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
20112014201720202023202620292032203520382041204420472050205320562059ENERGY(GWh)Ocean Tidal
Wind
Municipal Solid Waste
Geothermal
Hydro
Purchase Power
Fuel Oil
Nuclear
Coal
Natural Gas
December 10, 2009Page -14
Results –Scenario 1B
Energy By Resource Type
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
20112014201720202023202620292032203520382041204420472050205320562059ENERGY(GWh)Ocean Tidal
Wind
Municipal Solid Waste
Geothermal
Hydro
Purchase Power
Fuel Oil
Nuclear
Coal
Natural Gas
December 10, 2009Page -15
Results –Scenario 2A
Energy By Resource Type
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
20112014201720202023202620292032203520382041204420472050205320562059Energy (GWh)Ocean Tidal
Wind
Municipal Solid Waste
Geothermal
Hydro
Purchase Power
Fuel Oil
Nuclear
Coal
Natural Gas
December 10, 2009Page -16
Results –Scenario 2B
Energy By Resource Type
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
20112014201720202023202620292032203520382041204420472050205320562059ENERGY(GWh)Ocean Tidal
Wind
Municipal Solid Waste
Geothermal
Hydro
Purchase Power
Fuel Oil
Nuclear
Coal
Natural Gas
December 10, 2009Page -17
Sensitivity Cases
Scenario 1A Without DSM/EE Measures
Scenario 1A With Committed Units Included
Scenario 1A Without CO2 Costs
Scenario 1A With Higher Gas Prices
Scenario 1A With Fire Island
Scenario 1A Without Chakachamna
Scenario 1A With Chakachamna Capital Costs Increased by 75%
Scenario 1A With Susitna (Lower Low Watana Non-Expandable Option) Forced
Scenario 1A With Susitna (Low Watana Non-Expandable Option) Forced
Scenario 1A With Susitna (Low Watana Expandable Option) Forced
Scenario 1A With Susitna (Watana Expansion Option) Forced
Scenario 1A With Susitna (Watana Option) Forced
Scenario 1A With Susitna (High Devil Canyon Option) Forced
Scenario 1A With Modular Nuclear
Scenario 1A With Tidal
December 10, 2009Page -18
Results –Economics
Case
Cumulative
Present Value
Cost ($000,000)
Average Cost
(¢ per kWh)
Renewable
Energy in 2025
(%)
Total Capital
Investment
($000,000)
Scenarios
Plan 1A $12,925 4.60 49.17% $10,035
Plan 1B $12,916 4.59 54.78% $10,014
Plan 2A $20,978 4.29 53.57% $18,226
Plan 2B $21,507 4.40 55.55% $22,175
Sensitivities
1A Without DSM/EE Measures $13,262 4.40 51.10% $9,791
1A With Committed Units Included $13,863 4.93 32.03% $9,592
1A Without CO2 Costs $10,402 3.70 14.36% $8,685
1A With Higher Gas Prices $14,945 5.31 61.94% $9,798
1A With Fire Island $12,965 4.61 54.78% $10,502
1A Without Chakachamna $13,273 4.72 22.80% $9,179
1A With Chakachamna Capital Costs Increased
by 75%
$13,273 4.72 22.80% $9,179
1A With Susitna (Lower Low Watana Non-
Expandable Option) Forced
$15,209 5.41 54.70% $13,166
1A With Susitna (Low Watana Non-Expandable
Option) Forced
$14,898 5.30 60.18% $14,742
1A With Susitna (Low Watana Expandable
Option) Forced
$15,437 5.49 60.18% $15,274
1A With Susitna (Low Watana Expansion
Option) Forced
$15,943 5.67 61.58% $15,902
1A With Susitna (Watana Option) Forced $16,281 5.79 61.82% $16,049
1A With Susitna (High Devil Canyon Option)
Forced
$16,238 5.77 61.82% $16,016
1A With Modular Nuclear $12,591 4.48 49.05% $9,864
1A With Tidal $12,198 4.34 59.10% $10,052
December 10, 2009Page -19
Results –Emissions
Case CO2 (million tons) NOx (million tons) SO2 (million tons)
Scenarios
Plan 1A 176,205 222 36
Plan 1B 169,440 216 33
Plan 2A 287,321 281 240
Plan 2B 250,460 245 75
Sensitivities
1A Without DSM/EE Measures 181,208 242 242
1A With Committed Units Included 219,645 351 273
1A Without CO2 Costs 222,614 295 383
1A With Higher Gas Prices 166,406 248 268
1A With Fire Island 166,934 223 39
1A Without Chakachamna 219,110 223 35
1A With Chakachamna Capital Costs
Increased by 75%
219,110 223 35
1A With Susitna (Lower Low Watana Non -
Expandable Option) Forced
158,703 210 35
1A With Susitna (Low Watana Non -
Expandable Option) Forced
127,589 207 38
1A With Susitna (Low Watana Expandable
Option) Forced
127,589 207 38
1A With Susitna (Low Watana Expansion
Option) Forced
140,912 208 38
1A With Susitna (Watana Option) Forced 138,140 209 39
1A With Susitna (High Devil Canyon
Option) Forced
134,780 208 39
1A With Modular Nuclear 162,858 224 37
1A With Tidal 153,908 213 33
December 10, 2009Page -20
Conclusions –Preferred Resource Plan
DSM/EE Programs (2011)
Anchorage and GVEA MSW (2012)
Fire Island Wind (2012)
Southcentral Power Plant (2013)
Glacier Fork Hydro (2015)
Nikiski Wind (2017)
Anchorage Simple Cycle Turbine (2018)
GVEA Combined Cycle (2020)
Parallel pursuit of Chakachamna/Susitna/Glacier Fork
Multiple transmission projects
December 10, 2009Page -21
Conclusions –Other
Regional resource plan –historical cross-road
Increased reliance on DSM/EE and renewables
Robust transmission network
Need for frequency regulation
Spreading of risks
Foundation for economic development
Cost of renewables future if large hydro is not
development
Larger loads = lower unit costs
December 10, 2009Page -22
Conclusions –Regional or Individual Utility
Future
0
500,000
1,000,000
1,500,000
2,000,000
2,500,000
3,000,000
20112014201720202023202620292032203520382041204420472050205320562059YearAnnual Cost of Power ($000,000)Scenario 1A With Committed
Units
Scenario 1A Base Case
December 10, 2009Page -23
RIRP Plan 1A Capital Expenditures and Debt Capacity of the Railbelt Utilities
Conclusions –Financing the Future
Capital Expenditures
High Debt Capacity
Low Debt Capacity
December 10, 2009Page -24
Conclusions –GRETC as the Enabler
Current
Situation
•Limited redundancy
•Limited economies
of scale
•Dependence on
fossil fuels
•Limited Cook Inlet
gas deliverability
and storage
•Aging G&T
infrastructure
•Inefficient fuel use
•Difficult financing
•Duplicative G&T
expertise
RIRP Study
•Plan that economically
schedules what, when,
and where to build, based
on available fuel and
energy supplies
•50-year time horizon
•Competes generation,
transmission, fuel supply
and DSM/energy
efficiency options
•Includes CO2 regulation
•Includes renewable
energy projects
•Arrives at a plan to build
future infrastructure for
minimum long-run cost to
ratepayers
•Considers fuel supply
options and risks
RIRP
Results
•Increased
DSM/energy
efficiency
•Increased
renewables
•Reduce
dependence
on natural gas
•Increased
transmission
GRETC -Enabler
REGA Study
Proposed
GRETC
Formation
Future Situation
•Robust transmission
•Diversified fuel supply
•System-wide power rates
•Spread risk
•State financial assistance
•Regional planning
•Wise resource use
•Respond to large load
growth
•Technical resources
•New technologies
10-Year Transition Period
Financing Options
•Pre-funding of capital
requirements
•Commercial bond market
•State financial assistance
(Bradley Lake model)
•Construction-work-in-progress
December 10, 2009Page -25
Conclusions –Resource-Specific Risks
Relative Magnitude of Risk/Issue
Resource Resource Potential Risks Project Development and Operational Risks Fuel Supply Risks Environmental Risks Transmission Constraint Risks Financing Risks Regulatory/ Legislative Risks DSM/EE Moderate Limited N/A N/A N/A Limited -
Moderate
Moderate
Generation Resources
Natural Gas Limited Limited Significant Moderate Limited Moderate Moderate
Coal Limited Moderate-
Significant
Limited Moderate -
Significant
Limited -
Significant
Moderate –
Significant
Moderate
Modular Nuclear Limited Significant Moderate Significant Limited Significant Significant
Large Hydro Limited Significant N/A Significant Significant Significant Significant
Small Hydro Moderate Moderate N/A Moderate Moderate Limited -
Moderate
Limited
Wind Moderate Moderate N/A Limited Moderate Limited -
Moderate
Limited
Geothermal Moderate Moderate N/A Moderate Moderate –
Significant
Limited –
Moderate
Limited
Solid Waste Limited Moderate-
Significant
N/A Significant Moderate Limited –
Moderate
Limited-
Moderate
Tidal Limited Significant N/A Significant Moderate -
Significant
Moderate –
Significant
Moderate -
Significant
Transmission Limited Significant N/A Moderate N/A Significant Moderate -
Significant
December 10, 2009Page -26
Conclusions –Transmission Projects
December 10, 2009Page -27
Recommendations
Form GRETC
Establish State energy policies
Large hydro
DSM/EE
RPS and pursuit of other renewables
System benefit charge
Select preferred resource plan
Public outreach program
December 10, 2009Page -28
Recommendations (continued)
Address level/form of State assistance
Address short-term and long-term gas supply
issues
Develop regional portfolio of DSM/EE programs
and provide start-up funding
Begin detailed engineering/permitting activities
associated with selected generation and
transmission projects
Pursue Chakachamna, Susitna and Glacier Fork
to determine if any of these projects can be built
December 10, 2009Page -29
Recommendations (continued)
Form regional entity (if GRETC is not formed) to
develop DSM/EE programs and renewable projects
Pursue Federal funding for DSM/EE programs and
renewable projects
Streamline siting/permitting process for transmission
projects
Develop regional frequency regulation strategy
Develop competitive power procurement process
and standard power purchase agreement
December 10, 2009Page -30
What it Means?
10% / 8%
50%
$10 billion
$0.5 –$1.5 billion
7.3%
December 10, 2009Page -31
Situational Assessment
December 10, 2009Page -32
History of Independent but Cooperative Decisions
Infrastructure Investments
Alaska Intertie
Bradley Lake Hydro Project
Gas Supply
ML&P’s investment
Attractive historical prices
Innovative Solutions
GVEA’s BESS
Joint Operations and Contractual Arrangements
Intertie Operating and Reliability Committees
Full requirements contracts
Economy sales
December 10, 2009Page -33
Summary of Issues
Cost
Issues
RAILBELT
Future
Adopt New Direction
Maintain Status Quo
Businesses and Consumers
Power Costs
Future
Resource
Options
Uniqueness
of the Railbelt
Region
Natural Gas
Issues
Infrastructure
Issues
Load
Uncertainties
Political
Issues
Cost
Issues
RAILBELT
Future
Adopt New Direction
Maintain Status Quo
Impact on Railbelt
Reliability
Sustainability
Risks
Future
Resource
Options
Uniqueness
of the Railbelt
Region
Natural Gas
Issues
Infrastructure
Issues
Load
Uncertainties
Political
Issues
Management Risk
December 10, 2009Page -34
Methodology Considerations
December 10, 2009Page -35
Methodology Considerations
Time horizon –50 years
Models used –Strategist®and PROMOD®
Hydroelectric methodology
Transmission analysis
Financial analysis
December 10, 2009Page -36
Key Assumptions
December 10, 2009Page -37
General Assumptions
RIRP conducted assuming GRETC in place
Study period: 2011-2060
Objective Function:
2011 Cumulative Present Value Costs
December 10, 2009Page -38
Costs Included
Railbelt system fuel costs
Railbelt system non-fuel O&M costs
Railbelt system CO2 emission allowance costs
Capital costs for new Railbelt generation
Capital costs for new Railbelt transmission
Costs Not Included
Existing generation capital costs
Existing transmission capital costs
Distribution costs
December 10, 2009Page -39
Evaluation Scenarios
December 10, 2009Page -40
Significant Load Growth Opportunities
Large new loads (mines, etc.)
Conversion from gas to electric space and water
heating
Electric vehicles
December 10, 2009Page -41
Resources Considered
Demand-Side Management/Energy
Efficiency (DSM/EE) Measure
Categories Conventional Generation Resources Renewable Resources
Residential Simple Cycle Combustion Turbines Hydroelectric Projects
Appliances LM6000 (48 MW) Susitna
Water Heating LMS100 (96 MW) Chakachamna
Lighting Combined Cycle Glacier Fork
Shell 1x1 6FA (154 MW) Generic Hydro – Kenai
Cooling/Heating 2X1 6FA (310 MW) Generic Hydro - MEA
Commercial Coal Units Wind
Water Heating Healy Clean Coal BQ Energy/Nikiski
Office Loads Generic – 130 MW Fire Island
Motors Generic Wind – Kenai
Lighting Generic Wind - GVEA
Refrigeration Geothermal
Cooling/Heating Mt. Spurr
Municipal Solid Waste
Generic – Anchorage
Generic - GVEA
Other Resources Included in Sensitivity Cases
Modular Nuclear
Tidal
December 10, 2009Page -42
Planning Reserve Margin
30 Percent for GRETC
No capacity credit is given for wind
Operating Reserves
Operating reserves –150% times largest unit on the system
times area’s share
Area’s share = area’s largest unit / sum of all utility
participants’ largest units
Spinning reserves –100% times largest unit on the system times
area’s share
BESS included as 27 MW of spinning reserve in GVEA’s area
SILOs not included
December 10, 2009Page -43
Assumed Transmission System Transfer
Capability
Alaska Intertie
Current –75 MW south and north
2024 –130 MW south and north
Southern Intertie
Current –60 MW south, 75 MW north
2016 –110 MW south, 120 MW north
December 10, 2009Page -44
Natural Gas Prices
4
6
8
10
12
14
2010 2015 2020 2025 2030
YearGas Price ($US / MMBtu). Forecast of Railbelt Gas (purchase price for electric utility)
Forecast of LNG Delivered in Japan
Projection of ConocoPhillips-ENSTAR Contract (2008, terms through 2013)
Projection of Marathon-ENSTAR Contract (2008, terms through 2017)
Armstrong (North Fork)-ENSTAR contract (2009, floor & ceiling)
December 10, 2009Page -45
CO2 Allowance Costs
Year $/ton
2012 18.41
2020 39.70
2030 103.78
2040 213.91
2050 440.89
2060 564.38
December 10, 2009Page -46
Committed Units
Plant Name Area
Capital
Cost
($000)
Maximum Winter
Capacity (MW)
Commercia
l Online
Date
Southcentral Power Project Anchorage 281,100 187 2013
ML&P 2500 Simple Cycle Anchorage 43,200 33 2012
MLP LM6000 Combined Cycle Anchorage 95,200 73 2014
Healy Clean Coal Project GVEA 95,000 50 2011/2014
HEA Aeroderivative HEA (1) 34 2014
HEA Frame HEA (1) 42 2014
Nikiski Upgrade HEA (1) 77 (34 incremental) 2012
Eklutna Generation Station MEA 269,900 180 2015
Seward Diesel #N1 City of Seward 7,200 2.9 2010
Seward Diesel #N2 City of Seward 1,100 2.5 2011
(1)HEA has requested that their cost estimates remain confidential while they are obtaining their bids.
December 10, 2009Page -47
Transmission -GRETC Concept
Transmission system to be upgraded over time to
remove transmission constraints that currently
prevent the coordinated operation of all the utilities
as a single entity. This is projected to happen within
ten 10 years.
December 10, 2009Page -48
Starting Assumptions for Transmission Analysis
Study to include all the utilities' assets 69 kV and
above. These assets, over a transition period, flow
into GRETC and form the basis for a phased
upgrade of the system into a robust, reliable
transmission system that can accommodate the
economic operation of the interconnected system.
Assumes that all utilities participate in GRETC with
planning being conducted on a GRETC basis. The
common goal will be the tight integration of the
system operated by GRETC.
December 10, 2009Page -49
Railbelt Transmission Projects
Projects classified in following categories:
Transmission projects to connect new generation
projects to the grid (Generation Interconnections)
Transmission projects to upgrade the grid required by
new generation projects (Generation Upgrades)
Replacement projects that need to be done because of
age and condition (Replacement)
Upgrade projects to the grid to implement the GRETC
concept, based on existing generation (GRETC)
December 10, 2009Page -50
Load Profile –2011 Peak
GVEA
Area Load
238 MW
MEA
Area Load
146 MW
Anchorage
Area Load
412 MW
Kenai
Area Load
HEA/SES
97 MW
December 10, 2009Page -51
Recommended Transmission Projects
No. Transmission Projects Type Cost ($000) Priority
1 Soldotna – University New Build (230kV) $161,250 1
2 Soldotna – Quartz Creek Upgrade (230kV) $84,000 1
3 Quartz Creek – University Upgrade (230kV) $112,500 1
4 Lake Lorraine – Douglas New Build (230kV) $46,200 2
5 Douglas – Healy Upgrade (230kV) $12,000 2
6 Douglas – Healy New Build (230kV) $252,000 3
7 Beluga – Pt. Mackenzie New Build (230kV) $67,700 3
8 Douglas - Teeland Upgrade (230kV) $37,500 3
9 Healy – Gold Hill Upgrade (230kV) $145,500 4
10 Hea ly – Wilson Upgrade (230kV) $145,500 4
11 Soldotna – Bradley Lake Upgrade (115kV) $61,800 4
12 Daves Creek – Seward New Build (115 kV) $28,000 4
13 Eklutna – Lucas New Build (230kV) $13,300 5
14 Lucas – Teeland Upgrade (230kV) $26,100 5
15 Lucas – Teeland New Build (230kV) $26,100 5
16 Pt. Mackenzie – Plant 2 Replacement (230kV) $32,200 6
December 10, 2009Page -52
Susitna Analysis
December 10, 2009Page -53
Susitna Hydroelectric Project
December 10, 2009Page -54
Project Location
December 10, 2009Page -5555
Watana DamDevil Canyon Dam
Watana ReservoirDevil Canyon Reservoir
N
Potential Project Sites
High Devil Canyon Dam
December 10, 2009Page -56
Evolution of Susitna Project Studies
1983 Submittal of FERC license application
1985 Revised FERC license
Phased project development
1986 Project shelved
Reason was drop in price of fossil-fuel generated
power
March 2008 Interim Susitna Report
Re-evaluation of cost, energy, schedule and
economics of 5 of the 1980s project alternatives
Fall 2009 RIRP support
Development of alternative projects tailored to system
loads and costs
Nov. 2009 Final Susitna Report
Evaluation of cost, energy, and schedule of 9 project
alternatives
56
December 10, 2009Page -57
Fall 2009 RIRP Work
Identify lower cost alternatives
Estimate energy and cost
Determine firm capacity
57
Firm Capacity
“the amount of power the project can
generate on a continuous basis from
Nov. 1 through April 30 with 98%
reliability”
December 10, 2009Page -58
RIRP Project Configurations Studied
All Single Dam Configurations
Lower Low Watana
620’ high dam, 380 MW
Low Watana (1985 Phase 1 development)
685’ high dam, 600 MW
Low Watana (non-expandable)
Watana
880’ high rockfill dam, 1,200 MW
RCC Watana
880’ high roller compacted concrete (RCC) dam, 1,200 MW
High Devils Canyon
855’ high RCC dam, 775 MW
58
December 10, 2009Page -59
Project Comparison
December 10, 2009Page -60
Study Results
60
Alternative Dam Type
Ultimate
Capacity
(MW)
Firm
Capacity,
98% (MW)
Construction
Cost ($ Billion)
Energy
GWh/yr)
Schedule
(years from
start of
Licensing)
Lower Low Watana Rockfill 380 170 $4.1 2,100 13-14
Low Watana Non-
expandable Rockfill 600 245 $4.5 2,600 14-15
Low Watana Expandable Rockfill 600 245 $4.9 2,600 14-15
Watana Rockfill 1,200 380 $6.4 3,600 15-16
Watana RCC Roller Compacted Concrete 1,200 380 $6.6 3,600 14-15
Devil Canyon Concrete Arch 680 75 $3.6 2,700 14-15
High Devil Canyon Roller Compacted Concrete 800 345 $5.4 3,900 13-14
Watana/Devil Canyon Rockfill/Concrete Arch 1,880 710 $9.6 7,200 15 -20
Staged Watana/Devil
Canyon Rockfill/Concrete Arch 1,880 710 $10.0 7,200 15 -24
Alternative Dam Type
Ultimate
Capacity
(MW)
Firm
Capacity,
98% (MW)
Construction
Cost ($ Billion)
Energy
GWh/yr)
Schedule
(years from
start of
Licensing)
Lower Low Watana Rockfill 380 170 $4.1 2,100 13-14
Low Watana Non-
expandable Rockfill 600 245 $4.5 2,600 14-15
Low Watana Expandable Rockfill 600 245 $4.9 2,600 14-15
Watana Rockfill 1,200 380 $6.4 3,600 15-16
Watana RCC Roller Compacted Concrete 1,200 380 $6.6 3,600 14-15
Devil Canyon Concrete Arch 680 75 $3.6 2,700 14-15
High Devil Canyon Roller Compacted Concrete 800 345 $5.4 3,900 13-14
Watana/Devil Canyon Rockfill/Concrete Arch 1,880 710 $9.6 7,200 15 -20
Staged Watana/Devil
Canyon Rockfill/Concrete Arch 1,880 710 $10.0 7,200 15 -24
December 10, 2009Page -61
Conclusions
Of all the renewable resources in the Railbelt region,
the Susitna projects are the most advanced and best
understood
Project is considered to be technically feasible
Environmental and seismic risk is considered
manageable
61
December 10, 2009Page -62
December 10, 2009Page -63
Summary of Results
December 10, 2009Page -64
Limitations of RIRP
Does not set State energy policy
Directional
Identified/generic/actual projects
Agnostic to owner/developer of projects
December 10, 2009Page -65
Results –DSM/EE Resources
Energy Requirements (MWh)
0
1,000,000
2,000,000
3,000,000
4,000,000
5,000,000
6,000,000
7,000,000
8,000,000
20112014201720202023202620292032203520382041204420472050205320562059YearEnergy Requirements (MWh)Without DSM/EE
With DSM/EE
December 10, 2009Page -66
Results –Scenario 1A
Energy By Resource Type
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
20112014201720202023202620292032203520382041204420472050205320562059ENERGY(GWh)Ocean Tidal
Wind
Municipal Solid Waste
Geothermal
Hydro
Purchase Power
Fuel Oil
Nuclear
Coal
Natural Gas
December 10, 2009Page -67
Results –Scenario 1B
Energy By Resource Type
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
20112014201720202023202620292032203520382041204420472050205320562059ENERGY(GWh)Ocean Tidal
Wind
Municipal Solid Waste
Geothermal
Hydro
Purchase Power
Fuel Oil
Nuclear
Coal
Natural Gas
December 10, 2009Page -68
Results –Scenario 2A
Energy By Resource Type
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
20112014201720202023202620292032203520382041204420472050205320562059Energy (GWh)Ocean Tidal
Wind
Municipal Solid Waste
Geothermal
Hydro
Purchase Power
Fuel Oil
Nuclear
Coal
Natural Gas
December 10, 2009Page -69
Results –Scenario 2B
Energy By Resource Type
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
20112014201720202023202620292032203520382041204420472050205320562059ENERGY(GWh)Ocean Tidal
Wind
Municipal Solid Waste
Geothermal
Hydro
Purchase Power
Fuel Oil
Nuclear
Coal
Natural Gas
December 10, 2009Page -70
Sensitivity Cases
Scenario 1A Without DSM/EE Measures
Scenario 1A With Committed Units Included
Scenario 1A Without CO2 Costs
Scenario 1A With Higher Gas Prices
Scenario 1A With Fire Island
Scenario 1A Without Chakachamna
Scenario 1A With Chakachamna Capital Costs Increased by 75%
Scenario 1A With Susitna (Lower Low Watana Non-Expandable Option) Forced
Scenario 1A With Susitna (Low Watana Non-Expandable Option) Forced
Scenario 1A With Susitna (Low Watana Expandable Option) Forced
Scenario 1A With Susitna (Watana Expansion Option) Forced
Scenario 1A With Susitna (Watana Option) Forced
Scenario 1A With Susitna (High Devil Canyon Option) Forced
Scenario 1A With Modular Nuclear
Scenario 1A With Tidal
December 10, 2009Page -71
Results –Economics
Case
Cumulative
Present Value
Cost ($000,000)
Average Cost
(¢ per kWh)
Renewable
Energy in 2025
(%)
Total Capital
Investment
($000,000)
Scenarios
Plan 1A $12,925 4.60 49.17% $10,035
Plan 1B $12,916 4.59 54.78% $10,014
Plan 2A $20,978 4.29 53.57% $18,226
Plan 2B $21,507 4.40 55.55% $22,175
Sensitivities
1A Without DSM/EE Measures $13,262 4.40 51.10% $9,791
1A With Committed Units Included $13,863 4.93 32.03% $9,592
1A Without CO2 Costs $10,402 3.70 14.36% $8,685
1A With Higher Gas Prices $14,945 5.31 61.94% $9,798
1A With Fire Island $12,965 4.61 54.78% $10,502
1A Without Chakachamna $13,273 4.72 22.80% $9,179
1A With Chakachamna Capital Costs Increased
by 75%
$13,273 4.72 22.80% $9,179
1A With Susitna (Lower Low Watana Non-
Expandable Option) Forced
$15,209 5.41 54.70% $13,166
1A With Susitna (Low Watana Non-Expandable
Option) Forced
$14,898 5.30 60.18% $14,742
1A With Susitna (Low Watana Expandable
Option) Forced
$15,437 5.49 60.18% $15,274
1A With Susitna (Low Watana Expansion
Option) Forced
$15,943 5.67 61.58% $15,902
1A With Susitna (Watana Option) Forced $16,281 5.79 61.82% $16,049
1A With Susitna (High Devil Canyon Option)
Forced
$16,238 5.77 61.82% $16,016
1A With Modular Nuclear $12,591 4.48 49.05% $9,864
1A With Tidal $12,198 4.34 59.10% $10,052
December 10, 2009Page -72
Results –Emissions
Case CO2 (million tons) NOx (million tons) SO2 (million tons)
Scenarios
Plan 1A 176,205 222 36
Plan 1B 169,440 216 33
Plan 2A 287,321 281 240
Plan 2B 250,460 245 75
Sensitivities
1A Without DSM/EE Measures 181,208 242 242
1A With Committed Units Included 219,645 351 273
1A Without CO2 Costs 222,614 295 383
1A With Higher Gas Prices 166,406 248 268
1A With Fire Island 166,934 223 39
1A Without Chakachamna 219,110 223 35
1A With Chakachamna Capital Costs
Increased by 75%
219,110 223 35
1A With Susitna (Lower Low Watana Non -
Expandable Option) Forced
158,703 210 35
1A With Susitna (Low Watana Non -
Expandable Option) Forced
127,589 207 38
1A With Susitna (Low Watana Expandable
Option) Forced
127,589 207 38
1A With Susitna (Low Watana Expansion
Option) Forced
140,912 208 38
1A With Susitna (Watana Option) Forced 138,140 209 39
1A With Susitna (High Devil Canyon
Option) Forced
134,780 208 39
1A With Modular Nuclear 162,858 224 37
1A With Tidal 153,908 213 33
December 10, 2009Page -73
Financial Analysis
December 10, 2009Page -74
RIRP Plan 1A Capital Expenditures and Debt Capacity of the Railbelt Utilities
Debt Capacity vs. Capital Requirements
Capital Expenditures
High Debt Capacity
Low Debt Capacity
December 10, 2009Page -75
Greater Railbelt Energy & Transmission Company
Funding Concept for Large/Long Useful Life Assets
1-40 Years Formation/Maturation 41+ years Stability
Power Sales Agreements Buy/Sell Services
Repayment of Low-Interest Funding
GRETC
GRETC
Debt Capital
Markets
Grant and Low Interest
Construction/Long-Term
Funding
*30-40
year
Funds P&I
Power Sales Agreements
Buy/Sell Services
Credit
December 10, 2009Page -76
Strategies to Lower Capital Cost of RIRP to
Ratepayers
Ratepayer benefits charge
“Pay-go” vs. borrowing for capital
Construction Work in Progress
State financial assistance
Repayment flexibility
Credit support/risk mitigation
Potential interest cost benefit
December 10, 2009Page -77
Comparison of Capital Rates for Base Case Scenario and Alternative* Scenario
Fixed Rate Charge for Capital
-
0.02
0.04
0.06
0.08
0.10
0.12
0.14 20112016202120262031203620412046205120562061206620712076$/per kWhBase Case Alternative Case
*Alternative scenario includes $0.01 Consumer Benefit Charge through 2027
December 10, 2009Page -78
Capital Funding Sources
•Rate Payer Benefits Charge
•Debt Capital Markets
•Asset Transfers
•State Funds
Setting Stage for Funding GRETC
Steps Toward Funding
Define GRETC Organizational Structure Develop Phased Transition Plan
Identify State’s Role in Funding Initiate Dialogue with RCA
GRETC
Utility Managed Corporation
December 10, 2009Page -79
Risks and Uncertainties
December 10, 2009Page -80
General Risks
Organizational
Fuel supply
Inadequacy of transmission network
Market development
Financing and rate impacts
Legislative and regulatory
December 10, 2009Page -81
Resource-Specific Risks -Summary
Relative Magnitude of Risk/Issue
Resource Resource Potential Risks Project Development and Operational Risks Fuel Supply Risks Environmental Risks Transmission Constraint Risks Financing Risks Regulatory/ Legislative Risks DSM/EE Moderate Limited N/A N/A N/A Limited -
Moderate
Moderate
Generation Resources
Natural Gas Limited Limited Significant Moderate Limited Moderate Moderate
Coal Limited Moderate-
Significant
Limited Moderate -
Significant
Limited -
Significant
Moderate –
Significant
Moderate
Modular Nuclear Limited Significant Moderate Significant Limited Significant Significant
Large Hydro Limited Significant N/A Significant Significant Significant Significant
Small Hydro Moderate Moderate N/A Moderate Moderate Limited -
Moderate
Limited
Wind Moderate Moderate N/A Limited Moderate Limited -
Moderate
Limited
Geothermal Moderate Moderate N/A Moderate Moderate –
Significant
Limited –
Moderate
Limited
Solid Waste Limited Moderate-
Significant
N/A Significant Moderate Limited –
Moderate
Limited-
Moderate
Tidal Limited Significant N/A Significant Moderate -
Significant
Moderate –
Significant
Moderate -
Significant
Transmission Limited Significant N/A Moderate N/A Significant Moderate -
Significant
December 10, 2009Page -82
Resource-Specific Risks –Wind (Sample)
Resource: Generation – Wind
Risk/Issue Category
Description
Primary Actions to Address Risk/Issue
Resource Potential Total economic resource potential is
unknown
Resource potential may be constrained
by Railbelt regional system regulation
requirements
Complete regional economic
potential assessment, including the
identification of the most attractive
sites
Develop regional regulation
strategy for non-dispatchable
resources
Project Development Ineffectiveness and inefficiencies
associated with six individual utilities
developing wind projects
Lack of standard power purchase
agreements for projects developed by
IPPs
Establish a regional entity
(e.g., GRETC) or rely on IPPs to
identify and develop wind projects
Develop regional standard power
purchase agreements
Develop regional competitive
power procurement process to
encourage IPP development of
projects
Fuel Supply Not applicable Not applicable
Environmental Site specific environmental issues Comprehensive evaluation of site
specific environmental impacts at
attractive sites
Transmission Constraints Location of new facilities can add to
transmission constraints
Integration of non-dispatchable
resources into Railbelt transmission
grid poses challenges
Expand Railbelt transmission
network
Require that all proposed plant
locations also include transmission
infrastructure analyses and costs as
part of any approval process
Develop regional strategy for the
integration of non-dispatchable
resources
Financing Cost per kW can be significant Aggressively pursue available
Federal funding for renewable
projects
Regulatory/Legislative Regional commitment to renewable
resources is uncertain
Establish State RPS targets
Develop State policies regarding
RECs and Green Pricing
December 10, 2009Page -83
Implementation Action Plan
(2010-2012)
December 10, 2009Page -84
Implementation Action Plan
Form GRETC
Establish State energy policies
Large hydro
DSM/EE
RPS and pursuit of other renewables
System benefit charge
Select preferred resource plan
Public outreach program
December 10, 2009Page -85
Implementation Action Plan (continued)
Address level/form of State assistance
Address short-term and long-term gas supply
issues
Develop regional portfolio of DSM/EE programs
and provide start-up funding
Begin detailed engineering/permitting activities
associated with selected generation and
transmission projects
Pursue Chakachamna, Susitna and Glacier Fork
to determine if any of these projects can be built
December 10, 2009Page -86
Implementation Action Plan (continued)
Form regional entity (if GRETC is not formed) to
develop DSM/EE programs and renewable projects
Pursue Federal funding for DSM/EE programs and
renewable projects
Streamline siting/permitting process for transmission
projects
Develop regional frequency regulation strategy
Develop competitive power procurement process
and standard power purchase agreement
December 10, 2009Page -87
Questions and Answers
December 10, 2009Page -88
Concluding Comments