HomeMy WebLinkAboutSuWa285Alaska Resources Library & Information Services
Susitna-Watana Hydroelectric Project Document
ARLIS Uniform Cover Page
Title:
SuWa 285
Susitna-Watana studies resume after spending freeze lifted
Author(s) – Personal:
Elwood Brehmer
Author(s) – Corporate:
AEA-identified category, if specified:
AEA-identified series, if specified:
Series (ARLIS-assigned report number): Existing numbers on document:
Susitna-Watana Hydroelectric Project document number 285
Published by: Date published:
[Anchorage, Alaska : Alaskan Publications, 2015] August 16, 2015
Published for: Date or date range of report:
Volume and/or Part numbers:
Final or Draft status, as indicated:
Document type: Pagination:
News article 2 p. (pages 11 and 20)
Related work(s): Pages added/changed by ARLIS:
Notes:
Originally issued in: Alaska journal of commerce (August 16, 2015)
All reports in the Susitna-Watana Hydroelectric Project Document series include an ARLIS-
produced cover page and an ARLIS-assigned number for uniformity and citability. All reports
are posted online at http://www.arlis.org/resources/susitna-watana/
August 16,2015 •Alaska journal ofCommerce • Page 11 :
Susitna-Watana studies resume after spending freeze lifted
By Elwood Brehm er
Alaska journal of Commerce
Work is resuming on the Susit-
na-W atana hydroelectric project
under spending guidelines put in
place by Gov. Bill Walker's ad-
ministration.
The overall cost for the pro-
posed 705-foot dam in the upper
reaches of the Susitna River has
been pegged at $5.6 billion in
2014 dollars by the Alaska En-
ergy Authority, or AEA.
AEA will need $105 million,
maybe more, to get through the
Federal Energy Regulatory Com-
mission licensing process and to
construction, authority Executive
Director Sara Fisher-Goad said
during an Aug. 6 board meet-
ing. However, AEA only has the
ability to spend the $6.6 million
it has in the bank for the project
through 2017.
That money should get the
project to the study plan deter-
mination, at which point FERC
would rule whether or not the
authority has gathered sufficient
relevant data to apply for a proj-
ect license. The FERC license is
the last and largest pre-construc-
tion hurdle.
Fisher-Goad said AEA will
continue to update data with field
studies as necessary to prevent
work from becoming stale or out-
dated. National Marine Fisheries
Service officials have questioned
the validity of some Susitna-Wa-
tana fisheries studies.
"The longer we stretch this
out, we're losing our economy of
scale to be able to have logis-
tics support on several studies
at one time," she said. "We're
doing this in more of an incre-
mental fashion."
AEA has completed 14 of 58
FERC-approved studies so far,
according to Dyok.
To date, the project has re-
ceived $192 million in state ap-
propriations. The Walker admin-
istration lifted an administrative
order July 6 that halted spending
on the dam, one of six large infra-
structure projects that were put
on hold in late December.
After 2017, once AEA has
exhausted its funds for working
towards a study plan determina-
tion, "the project will be revisited
in the context of the fiscal envi-
ronment and other competing
major capital projects," Office of
Management and Budget Direc-
tor Pat Pitney wrote in a memo to
Fisher-Goad.
Mike Wood, president of the
lead Susitna-W a tan a opposi-
tion group the Susitna River
Coalition, in a July 16 release,
called resuming the project a
"slap in the face" to Alaskans
AP PHOTo/FRAil Fuvni/Awu EIERGY AIITHORITY
Researchers walk alo ng the Susitna River in this 2012 Alaska Energy Authority photo. With a spending freeze lifted by Gov. Bill Walker, work is resuming on the
Susitna-Watana hydroe lectric project. However, the authority will need about $100 million in new funding to get through the Federal Energy Regulatory Commis-
sion licens ing process and to construction.
as state leaders discuss ways to
increase state revenue during a
time of multi-billion dollar bud-
get deficits.
"The proposed dam has al-
ready wasted hundreds of mil-
lions of state dollars and needs
to be immediately shut down,"
Wood said. "It diverts necessary
funds for other, more respon-
sible and reasonable alternative
energy developments, as well as
goes against Walker's campaign
promises of fiscal responsibility
and fish-first policies."
AEA has touted the dam,
which would generate about
2,800 gigawatts, as a way to pro-
vide half of the Railhelt's energy
demand with clean energy at
long-term stable prices.
Continuing at a slower pace
to prevent unnecessary spending
could end up costing the state if
the dam is ultimately built, AEA
Project Manager Wayne Dyok
said at the AEA board meeting.
At $5.6 billion to build today,
inflation on project financing
could add up to $150 million to
the cost each year construction is
delayed, he said.
If everything goes according
to the current plan, AEA will
be able to submit its license ap-
plication with FERC in 2019,
and hopefully begin construc-
tion soon after a typical two-
year review, according to Dyok.
However, if AEA gets the $100
million-plus it needs to submit
its application before 2017, that
timeline could be accelerated
by two years and potentially
save the state $300 million.
The cost of financing the proj-
ect could also have a direct im-
pact on long-term electric rates.
"What you get out of a con-
structed hydro project is this in-
flation-proof aspect, but you don't
get that until it's constructed and
generating," Fisher-Goad said.
Dyok said the dam would save
Railbelt consumers an average
of $224 million per year on en-
ergy costs over the first 50 years
in production, a total savings of
$11.2 billion over that time.
Initial electric rates from Sus-
itna-W atana -with first power
in 2029 -would be in the 13
cents per kilowatt-hour range,
AEA estimates.
That price would continue to
drop to an average of 6.6 cents
per kilowatt-hour as about $8 bil-
lion in principal plus interest is
paid off over 50 years.
By contrast, natural gas-gen-
erated electricity from the large
Alaska LNG Project would be
about 11 cents per kilowatt-
hour in 2029 and increase to
a more stable rate of about 15
cents per kilowatt-hour over
several deQades, according to
Alaska Center for Energy and
Power projections.
On the energy savings alone,
Dyok said the cost-benefit ratio
for the project is 2.39-to-l. When
the avoided cost of building new
gas-fired generating capacity,
generation facility retirement,
and greenhouse gas reductions
are included, the ratio improves
to more than 3-to-1, he said.
Roughly half of the project
qualifies for a U.S. Department
of Agriculture Rural Utilities
Service loan, which is conser-
vatively projected with 4 per-
cent interest, Dyok said.
The rest of the project fi-
nancing is planned as nearly $4
billion paid in state bonds at 5
percent interest over 30 years a
portion of which would be refi-
nanced at a lower rate, accord-
ing to AEA officials.
See Susitna-Watana, Page 20
• · Page 20 • August 16, 2015 • A laska jou rnal of Com merce
Susitna-Watana:
Econ omic, study impacts
As an added bonus, Susitna-W atana
would generate billions for Alaska's econ-
omy dut·ing construction along with clean,
affordable power once its turbines are
turning, AEA claims.
The dam would have an economic im-
pact of $3.4 billion and generate about
1,300 jobs each year during construction,
according to a Northern Economics study
commissioned by the authority.
Preconslruction study work has gener-
ated jobs, but also information that is be-
ing used by other state agencies.
"This project has advanced the state
of science for a number of agencies, par-
ticularly the Alaska Department of Fish
and Game through some of the salmon
Continued from Page 11
work," Dyok said .
ADFG Mat-Su area spcort fish biolo-
gist Richard Y anusz said in an interview
that AEA's funding for fis,heries studies
has provided significant benefit to the
department. He said ther'e is relatively
little data on chinook salnnon in the Sus -
itna drainage, despite the popularity of
the species. AEA's studies in 2013-14
provided drainage-wide albundance esti -
mates through radio teletmetry tracking
and mark-recapture efforts.
According to Yanusz, s,ome of that in-
formation had not been gathered since
the first time Susitna-Watana was pro-
posed in the 1980s.
"It's been a long time between those
abundance estimates, so having such a
basic piece of information is very helpfu l
to management," he said. "It is al mos t
new information, very rare information,
so just having those reference points will
be helpfuL"
Similar studies were done for coho
salmon, the other primary sport fish in the
drainage, on the main stem of the Susitna,
without including the major tributari es
such as the Y entna.
Dyok said the Department of atural
Resources has also found flow data helpful
for other potential projects in the region.
Managing flow below the dam has been
an issue of contention for those opposed to
Susitna-Watana, because of the potential
impacts to juvenile salmon, particularly in
winter.
AEA is developing models to beller
project flow regimes throughou t the year,
but how much water is let through the dam
is ultimately regulated by FERC, accord-
ing to Dyok.
Average winter flow at the dam site would
increase about four times and roughly be cut
in half dming the summer to retain water
during times oflower electric demand based
on early projections, he said.
Flow at the dam site currently compris-
es about 16 percent of the average annual
water in the Susitna.
"Fisheries, recreation, and power, you need
to balance all of those factors," Dyok said.
Elwood Brehmer can be reached al
elwood. brehmer@alaskajournal.com.