HomeMy WebLinkAboutAEA Board HVDC Analysis 3.29.13Economics of HVDC Projects in Alaska
Alaska Energy Authority
Board of Directors
March 29, 2013
HVDC for the Railbelt
Examines North Slope
power generation delivered
to the Railbelt with HVDC
Analysis based on existing
proposal
Recommendation made for
future consideration of this
project
HVDC Opportunities in Alaska
Explores other
opportunities to use HVDC
to supply power in Alaska
Economics modeled based
on costs provided by
proponents of proposed
project
ǯ
developing these
opportunities
2
Economic Analysis of HVDC in Alaska:
Two Approaches
HVDC for
the Railbelt
High level analysis on the economics of a
stand-‐alone project providing the Railbelt with
North Slope power using HVDC
This analysis is intended to provide a clear
answer on the economic viability of the project
Avoids disputing any assumptions
Avoids complex modeling
Analysis based information from existing
project proposal
Proposed by:
Meera Kohler, AVEC
Dr. Robert A Jacobsen
February 2013 (AK House Energy Committee)
3
Economic Analysis for Railbelt HVDC
Three step simple test
Very conservative approach
ǯ
assumptions in existing proposal
Step 1: Isolate annual HVDC
transmission costs
Step 2: Calculate annual gas used
by new power plant
Step 3: Calculate the break even
Railbelt natural gas price
This analysis provides a simple test to
determine if the Railbelt HVDC proposal
warrants further investigation
The test can be thought of as a
Dzdz
The test: Can a new power plant on the
North Slope using HVDC transmission
beat a new power plant on the Railbelt?
ǡ ǯ
Railbelt generation scenario
Utilizing existing Railbelt generation
capacity will only make the HVDC
proposal less economic
4
Step 1: Isolate Annual HVDC Costs
Capital costs include
HVDC power lines
Converter Stations
Annual capital costs calculated
as debt service on capital
O&M calculated from proposal
O&M cost per MWh multiplied
by total MWh to get annual cost
Total annual savings would need
to exceed total annual HVDC
costs to achieve a benefit
5
HVDC Power Lines $1,860
Converter Stations $575
Total Capital Costs $2,435
Term (years)30
Interest Rate 7%
Annual Payment $196
O&M costs per MWh $9.81
Reported Annual GWh 6,203
Annual O&M Costs $61
Total Annual HVDC Cost $257
HVDC Annual Costs ($millions)
Step 2: Annual Gas Used by New Plant
Adjusted the current total
Railbelt electric consumption
Used current power demand
Netted out current hydro and
coal supply
Heat rate for new power plant
ǯ
assumptions
Measured in Btu per KWh
Gas use will be lower with better
heat rate
6
Railbelt Demand (GWh)4,294
Heat Rate 5,687
Annual Gas Use (Bcf)24.4
Annual Gas Demand
Step 3: Calculate Break Even Gas Price
To break even, annual gas
savings must be greater than
annual cost of HVDC
The gas price delta is how much
less expensive North Slope gas
must be to break even
Adding the assumed North
Slope gas price to the gas price
delta gives us the break even
Railbelt gas price
7
Annual HVDC Cost ($mill)$257
Annual Gas Use (Bcf)24.4
Gas Price Delta ($/Mcf)$10.53
North Slope Price ($/Mcf)$3.00
Railbelt Gas Price ($/Mcf)$13.53
Break Even Gas Price
What the Break Even Gas Price Means
We calculated a break even Railbelt natural gas price of $13.53.
Under this thought experiment, Railbelt gas would need to cost
more than $13.53 to make the Railbelt HVDC proposal economic.
That means, if our only two choices were building a massive new
power plant on the North Slope or the Railbelt, we would build one
on the Railbelt (assuming gas will cost less than $13.53).
In reality, producing power with existing Railbelt power plants is
much cheaper than replacing them all with one new plant.
Therefore, if the Railbelt HVDC proposal is more costly than
building a new plant on the Railbelt it must also be more costly
than producing power with existing Railbelt power plants.
8
HVDC for
the Railbelt
A more extensive analysis of this proposal
may not be necessary
The project does not pass this simple and
very conservative test
The added costs of HVDC outweigh the
benefit of low cost North Slope gas
The break even gas price would actually
be much higher than calculated here
A whole new power plant would not be
needed on the Railbelt
Using more complex and realistic
assumptions make the project even less
economic
9
HVDC
Opportunities
in Alaska
HVDC projects have been proposed to
multiple Alaska markets
The Alaska Railbelt
Large mines in remote locations
Rural Alaska communities
This analysis identifies potential
opportunities to utilize HVDC transmission
Does not recommend particular projects or
project designs
10
Economic Analysis of HVDC Opportunities in Alaska
The economic benefit of HVDC
projects is a function of three
variables
1: Quantity of Electricity (GWhs)
2: Price differential between the
ends of an HVDC line ($/kWh)
3: Total annual cost of HVDC
(HVDC Cost)
Annual economic benefit =
GWhs x $/kWh Ȃ HVDC Cost
This economic analysis uses cost data
supplied by project proponents to
model the economics of different HVDC
projects
The results of the modeling are not
exact, but should be accurate enough to
identify opportunities in Alaska
We model each HVDC project as a stand
alone project, providing power to only
one market
Increased benefits may occur from
combining markets or projects
11
Quantity of Electricity (GWhs)
Railbelt: includes all current
power demand not met by hydro
or coal
Remote Mine: completely
hypothetical very large mine
Rural Alaska: total electricity
demand for Northwest Arctic
Borough
Electricity only, no heat demand
Does not include Red Dog Mine
demand
12
Price Differential ($/kWh)
This analysis uses very rough
estimates of local power costs
Fuel is the largest driver of price
Natural gas for North Slope and
Railbelt, diesel for mines and Rural
Alaska communities
Price differential is calculated as:
Local power cost minus North Slope
power cost
Railbelt: $0.03 per kWh
Remote mine: $0.40 per kWh
Rural Alaska community: $0.47 per
kWh
13
Factor 3: Total Annual Costs of HVDC
Capital cost
Increases with distance of
transmission
Increases with amount of power
system is designed to carry
Annual cost
Debt service on capital costs
Annual O&M
Data supplied by proponents of
existing proposal
Does not use their existing system
plans
14
Capital Cost
$mill
Annual Cost
$mill
Railbelt $2,428 $281
Remote Mine $680 $79
Rural Alaska $680 $79
Calculation of Annual Benefits
Annual economic benefit =
GWhs x $/kWh Ȃ HVDC Cost
The potential savings are the
GWhs multiplied by the price
differential (GWhs x $/kWh)
Annual savings are the potential
savings minus the HVDC costs
A positive annual savings
indicates an economic project
15
GWhs $/kWh
HVDC
Costs
Railbelt 4,294 $0.03 $281
Remote Mine 1,350 $0.40 $79
Rural Alaska 36 $0.47 $79
Potential
Savings
HVDC
Costs
Annual
Savings
Railbelt $132 $281 ($149)
Remote Mine $535 $79 $457
Rural Alaska $17 $79 ($62)
What the Annual Savings Mean
Of the three stand alone HVDC projects analyzed, only the
Remote Mine Scenario provided positive economic benefits
Stand alone HVDC projects to Rural Alaska communities or
the Railbelt from the North Slope are not economic
May be possible to combine a remote mine project to Rural
Alaska communities or the Railbelt
Potential to provide economic benefits to rural communities or
the Railbelt
Dependent on a large remote mine pursuing HVDC power first
16
HVDC
Opportunities
in Alaska
HVDC has the potential to provide significant
economic benefit for remote mines
Potential remote mining projects should
engage AEA to explore an HVDC project
AEA can help design and integrate the HVDC
system
AEA would ensure that the project supplies
power nearby Alaska communities
17
AKEnergyAuthority.org
18