Loading...
HomeMy WebLinkAboutSE Alaska HVDC Sys Report Update 2-2011Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 1 07/21/11 CITY AND BOROUGH OF SITKA, ALASKA SITKA-KAKE-PETERSBURG INTERTIE STUDY UPDATE February 2011 DR. GEORGE KARADY – Professor and consultant F. MIKE CARSON - Northstar Power Engineering Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 2 07/21/11 SITKA-KAKE-PETERSBURG HVDC INTERTIE STUDY George G. Karady and F. Mike Carson 2011 Executive Summary The objective of this study is to assess the feasibility to interconnect Sitka-Kake-Petersburg when the Takatz Lake Hydro is built. The proposed line would constitute an important section of the Southeast Alaska Intertie Plan. The system capacity would be rated at 50 MW. This will permit energy transfer between Sitka, Kake, and Petersburg. The intertie would also provide back-up power during faults in local generation. A similar study was prepared 10 years ago by the same authors. After reviewing several feasible system configurations, this study concluded that a multi-terminal voltage source converter based High Voltage Direct Current (HVDC) system in a bi-polar configuration was the most economical system for the intertie. The major advantages of the multi-terminal HVDC system are the active, reactive power control, and black start capability. The final conclusion was that HVDC Light system made by Asea-Brown-Boveri (ABB) would be the best solution. In the last 10 years the voltage source based multi-terminal HVDC become a matured product, more than eleven (11) systems are in operation. In addition to ABB, manufacturers like Siemens and Areva also offer a similar system. However, the market has changed in the last 10 years and the cost of IGBT converters and DC cable increased significantly. ABB proposed 50MW, 80 kV converters at an estimated cost of $35M. Another market change is that the manufacturers are not interested in building small HVDC Light or HVDC Plus systems. Indian and Chinese markets as well as the European offshore wind farms demand large, several hundred megawatt ratings for the voltage source based HVDC systems. The manufacturers are working on large IGBT based HVDC systems which can compete with the classical thyristor based HVDC and suitable to form DC networks. ABB suggested building a traditional 138kV, 50MW AC intertie with submarine cable compensated by reactance. System operation analysis proved that the submarine cable capacitive current can be compensated with two reactances. This system is close to 36 million dollars cheaper than lowest cost HVDC system. The intertie will use the 138kV and 69kV transmission lines, which are already in operation in Alaska. The new component is the submarine cable and its compensation with two inductances. The one line diagram of the recommended 138kV and 69 kV systems is shown in figure below. Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 3 07/21/11 Table of Contents Executive Summary .................................................................................................................. 2 List of Figures ........................................................................................................................... 5 List of Tables ............................................................................................................................ 6 1 Nomenclature .................................................................................................................... 7 2 Introduction ....................................................................................................................... 7 3 Objectives ......................................................................................................................... 9 4 Description of the Proposed Line ..................................................................................... 9 5 Present State of Voltage Source Converter Based HVDC Systems ............................... 12 5.1 HVDC with Voltage Source Converter .................................................................. 13 5.2 HVDC Substations .................................................................................................. 17 5.3 HVDC Cables ......................................................................................................... 20 1 Manufacturers Data ......................................................................................................... 26 2 Conceptual design and cost estimate .............................................................................. 29 2.1 Hybrid system ......................................................................................................... 31 2.2 Hybrid system-Alternative 1 ................................................................................... 31 2.3 Hybrid system Alternative 2 ................................................................................... 35 2.3.1 Transmission Line and Cable Cost Estimate ...................................................... 36 2.3.2 Hybrid System Alternative 1 & 2 Cost Estimate ................................................ 36 2.4 Multi-Terminal DC System .................................................................................... 39 2.4.1 Multi-Terminal DC System Alternative 1 .......................................................... 39 2.4.2 Multi-Terminal DC System Alternative 2 .......................................................... 42 2.4.3 Budgetary Cost Estimate for Multi-Terminal HVDC Light Systems ................. 42 2.5 AC transmission System with compensated submarine cable ................................ 43 2.5.1 Analysis of the Three Phase AC Intertie Operation ............................................ 44 2.5.2 Budgetary Cost Estimate Three Phase AC System............................................. 46 2.6 Summary of the Comparison of Different Systems ................................................ 46 3 Conclusions ..................................................................................................................... 47 4 References ....................................................................................................................... 47 5 Biosketches ..................................................................................................................... 48 Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 4 07/21/11 Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 5 07/21/11 List of Figures Figure 1 Proposed Intertie between Sitka-Kake-Petersburg ..................................................... 9 Figure 2 Direct Buried DC Cable in Sweden .......................................................................... 11 Figure 3 HVDC Solid state converter development. (Copy Panel 02-1 Overview of HVDC Transmission, ABB WEB site). ...................................................................................... 12 Figure 4 HVDC system with voltage source converter .......................................................... 14 Figure 5 StakPak module of IGBT’s ...................................................................................... 15 Figure 6 Arrangement of Heat sinks and IGBT modules ....................................................... 15 Figure 7 IGBT valves used for light HVDC ........................................................................... 16 Figure 8 Multi-level converter for the HVDC Plus system. ................................................... 16 Figure 9 HVDC plus valve. .................................................................................................... 17 Figure 10 Conceptual design of a HVDC light substation ..................................................... 18 Figure 11 IGBT valves mounted in metal enclosures ............................................................. 18 Figure 12 Light HVDC station ............................................................................................... 19 Figure 13 Pair of extruded polymer HVDC cables. ................................................................ 19 Figure 14 DC submarine cable ............................................................................................... 20 Figure 15 Giulio Verne Cable Laying Ship ............................................................................ 21 Figure 16 138kV Cross-linked polyethylene Cable ................................................................ 21 Figure 17 Circuit diagram of a PWM converter ..................................................................... 23 Figure 18 PWM voltage waveform ......................................................................................... 23 Figure 19 Generation of PWM voltage waveform ................................................................. 24 Figure 20 Example for a planned multi-terminal DC system ................................................. 25 Figure 21 Sitka’s Electric Energy Requirements and Resource ............................................. 30 Figure 22 Hybrid system conceptual connection diagram ...................................................... 31 Figure 23 69 kV transmission tower used in Sitka area .......................................................... 32 Figure 24 138 kV transmission tower used in Petersburg area ............................................... 33 Figure 25 Multi-Terminal DC Transmission System. ............................................................ 39 Figure 26 The S1 composite insulator .................................................................................... 40 Figure 27 Three phase AC transmission system ..................................................................... 43 Figure 28 Equivalent circuit for the Three phase AC transmission system ............................ 44 Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 6 07/21/11 List of Tables Table 1 Light HVDC Systems ................................................................................................ 13 Table 2 HVDC light submarine cables (Extract from ABB Brochure “HVDC Light Cables”) ......................................................................................................................................... 34 Table 3 HVDC light Converters (Extract from ABB Brochure “HVDC Light Cables”) ....... 35 Table 4 HVDC Light Submarine Cables (Extract from ABB Brochure “HVDC Light Cables”)........................................................................................................................... 35 Table 5 Variation of Consumer Price Index between 1999-2010 ........................................... 37 Table 6 ABB Provided Cost Data ........................................................................................... 38 Table 7Hybrid systems with HVDC light, Alternative 1:69 kV and 138 kV transmission lines and 80 kV DC submarine cable ...................................................................................... 38 Table 8 Hybrid system with HVDC light, alternative 2:138 kV transmission lines and 80 kV DC submarine cable, 80 kV ............................................................................................ 39 Table 9 Technical Specification of MacLaen Composite Insulators. (Copy from MacLaen Catalouge) ....................................................................................................................... 40 Table 10 IEC 515 Recommended Creapage Distances for Polluted Insulators. (Copy from IEC 515) .......................................................................................................................... 41 Table 11 Cost Estimate for the Multi-Terminal HVDC Light System Alternative 1 ............. 42 Table 12 Cost Estimate for the Multi-Terminal HVDC Light System Alternative 2 ............. 43 Table 13 Data for Operation Analysis .................................................................................... 44 Table 14 Cost Estimate for the AC Transmission System ...................................................... 46 Table 15 Cost Comparison of Different Systems ................................................................... 46 Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 7 07/21/11 SITKA-KAKE-PETERSBURG HVDC INTERTIE STUDY 1 Nomenclature • HVDC High Voltage DC energy transportation system • HVDC Light Asea_Brown Bovery (ABB) developed DC energy transportation system using voltage source converters • HVDC Plus Siemens developed DC energy transportation system using voltage source converters • IGBT Insulated Gate Bipolar Junction Transistor, suitable for high frequency switching. • Thyristor High power switching device, which can turn on a circuit, but it turns off when the current reverses. • Monopolar DC A DC system which has only one current carrying conductor and the current returns through the earth • Bipolar DC A DC system, which has two current carrying conductors and a neutral conductor. No ground current • Hybrid system An energy transportation system that has AC lines and DC submarine cable • Multi-terminal DC A DC system, which contains more than one converter connected in parallel to the system. • Converter Electronic circuit that can work as a rectifier or as an inverter 2 Introduction Southeast Alaska Transmission Intertie includes the interconnection of the Sitka and Petersburg electric power systems, via Kake. The area requires interconnections between islands close to each other as well as rough mountainous terrain with several meter yearly snow fall. The load on the interconnection varies between 2MW-50MW. Several studies investigated the design, budgetary cost and specifications of the Southeast Alaska Transmission Intertie. The major studies investigating the transmission and generation aspect of the Intertie are: 1. Transmission Intertie, Kake-Petersburg, A Reconnaissance Report, Alaska Power Authority, Robert W. Retherford Associates, January 1981 2. Tyee-Kake Intertie Project, Detailed Feasibility Analysis, Volumes 1 and 2, Alaska Power Authority, EBASCO, March 1984 3. Feasibility Study, Kake-Petersburg Intertie, State of Alaska-Department of Community and Regional Affairs, Division of Energy, R.W. Beck, June 1996 4. Takatz Creek Project-Alaska, U.S. Department of the Interior, Alaska Power Administration, 1960. Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 8 07/21/11 5. Analysis of Electric System Requirements, City and Borough of Sitka, R. W. Beck, April 1974 6. Electric Resource Evaluation and Strategic Plan, City and Borough of Sitka, R.W. Beck, November 1991 7. Southeast Alaska Intertie DC Transmission System- Reconnaissance Design and Cost Estimate, Teshmont Consultants, November 1982. 8. Southeast Alaska Transmission Intertie Study, Alaska Power Authority, Harza Engineering, October 1987 9. Southeast Alaska Electrical Intertie System Plan, Southeast Conference, Acres International, January 1998. 10. Sitka-Kake-Petersburg HVDC Intertie Study, Northstar Power Engineering, George G Karady, and F. Mike Carson. January 1999 11. Southeast Alaska Intertie Study, Southeast Conference, D. Hittle and Associates, December 2003 12. Kake-Petersburg Intertie Study, Southeast Conference, D. Hittle and Associates, July 2005 13. Kake-Petersburg Intertie Study Update, Southeast Conference, D. Hittle and Associates, May 2009 14. Takatz Overhead Transmission Line Alternative Feasibility Review Report Summary, Commonwealth Associates, February 10, 2011. These studies recommended different solutions and provided budgetary cost estimates. Harza Study [#8] and our [#10] ten years old study proposed the building of a high voltage DC transmission system. The main reason is that the capacitive current limits the length of an AC underwater cable in the 30-40miles. Simultaneously the DC cable technology improved in the last 20 years and the economic building of long HVDC cables with solid dielectric material (cross linked polyethylene) became feasible. In our previous study [#10] we showed that building of a traditional HVDC system using thyristor based current commutated converters are not economical for the short (less than 50 miles) distances and for low power (50MW or less). According to the literature, the traditional HVDC system is economical above around 300miles length and 500MW power transfer. In the last 10 years, the technology for the voltage source converter based multi-terminal HVDC system further developed. Originally, this system was designed for low power and short distance energy transport. Small HVDC transmission systems have been built (ABB and Siemens) and are operating successfully. Technology matured and more manufacturers offer voltage source converter based multi-terminal HVDC systems. However, the cost of the converters remained high, which upset the advantages of the HVDC system. The above described development suggests an investigation of all feasible alternatives both AC and voltage source converter based HVDC systems for the Sitka-Kake-Petersburg Intertie. Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 9 07/21/11 3 Objectives The objective of this study is to investigate the most feasible interconnection for the planned Sitka-Kake-Petersburg Intertie. The study will investigate: 1) The technical advantages of the proposed system including: i) Emergency power in case of power plant outage ii) Voltage support in case of overload iii) Load flow control iv) Blocking the development of cascading outages v) Transient stability improvement vi) Inter-area (small signal) oscillation damping 2) Description of the project and identification of major components 3) Economic evaluation and budgetary cost estimate 4 Description of the Proposed Line A comprehensive description of the proposed intertie was provided in our last report [#10]. In this report the intertie description was updated and slightly modified to conform to the City’s latest plans. Presently, Sitka is supplied by the Blue Lake (7.0MW) and Green Lake (18.54MW) hydro plants and some diesel generation. 69 kV transmission lines connect the power plants to the city of Sitka. Approximately 22 miles northeast of Sitka is Takatz Lake, where a 28MW hydro power plant can be built. This plant would produce excess energy that could be sold to Kake and Petersburg. However, this requires an intertie between Sitka, Kake, and Petersburg. Figure 1 Proposed Intertie between Sitka-Kake-Petersburg Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 10 07/21/11 The intertie would start from the Blue Lake 69 kV switchyard and connect the proposed Takatz Lake Hydro to the Sitka system using an AC overhead line with segments of underground/submarine cable. In the other direction, a submarine cable would connect the Takatz Lake powerhouse to Kake. From Kake, an overhead line with two short submarine cable crossings would connect to the existing 138kV Petersburg-Tyee Lake transmission line. The investigation of the present loads and the rather moderate expected load growth by the City of Sitka suggested a tie line capacity of 50 MW. Figure 1 shows the proposed intertie route. It can be seen that the intertie is divided into three main sections. 1. Blue Lake switchyard to Takatz Lake powerhouse (21.2 miles transmission line). The terrain between the two sites is extremely rugged, with two mountain passes. One pass is between Takatz Lake and Baranof Lake (elevation 2100 ft) and the other is between Baranof and Medvejie Valleys (elevation 2500 ft). The new transmission line would start at an overhead tap on the existing Green Lake 69 kV transmission line near Bear Cove about 5.0 miles southeast of Blue Lake Switchyard. The transmission line would follow the Medvejie Valley easterly past Medevjie Lake. At the head of the valley, a tunnel would be bored into nearby Baranof Valley to avoid the steep rugged mountain pass. Underground transmission cable in conduit would be used in the 2.0 mile long tunnel. The new transmission line would continue east along the Baranof Valley to Baranof Lake. Heavy duty H-frame structures would be used for this 6.2 mile segment. Then the new transmission line would continue along the north side of Baranof Lake to a point west of the community of Baranof where the line would turn north and follow along the east side of Sadie Lake. At the upper end of Sadie Lake, the line would cross the steep ridge and continue down to the south side of Takatz Bay where it would bifurcate. Heavy duty H-frame structures would be used for this 5.3 mile segment. Then the line would either continue west to the powerhouse or would continue east to a submarine cable landfall on Chatham Strait. Heavy duty H-frames would be used because of the terrain. 2. Takatz Lake Power House to Kake (41.1 miles submarine cable). Harza proposed a 100 kV submarine cable from Warm Springs Bay to Point White at a total distance of 35 miles (56.3 km). This submarine cable route was modified to connect to the selected submarine cable landfall on the south side of Takatz Bay. The new submarine cable would cross Chatham Strait and Frederick Sound near the tip of Admiralty Island. The maximum water depth is about 350 fathoms that requires double armored cable. Harza’s proposed landfall at Point White also was modified. The new landfall would be at the Kake Substation site southeast of Kake (Point K in the 2009 Kake-Petersburg Intertie Study Update Report) to avoid a transmission line through the center of town and by the airport. 3. Kake to Petersburg (50.0 miles transmission line and 1.8 miles submarine cable). From the cable landfall at the Kake Substation site, an overhead transmission line would continue southeast across Kupreanof Island to Duncan Canal and Wrangell Narrows where two submarine cable crossings would be located. Single pole structures would be used for this line. The line would connect to the existing 69/138 kV Petersburg-Tyee Lake overhead transmission line near Papke's Landing. The proposed route has been Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 11 07/21/11 identified as the Center-South Alternative and is described in detail in the 2009 Kake- Petersburg Intertie Update Report by Hittle and Associates. The latest Acres International Corporation study estimated the cost of this intertie to be about US $65-$66 million, where the first two sections (Kake-Sitka) is estimated at US $45,489,000 in 1996 dollars and the Kake-Petersburg section at US $19,734,600 in 1996 dollars. The 2009 cost estimate for the Center-South Alternative in the Hittle Kake- Petersburg Intertie Update Report is $37,922,200 (Table 4-3) DC cables can be direct buried or placed in conduit. Figure 2 shows an example of direct buried crosslink polyethylene DC cable. This example suggests the investigation of using DC cables instead of 69 kV overhead lines if an access road is available. Deep snow would not jeopardize the operation of underground cable. An economical DC cable solution would require the building of a primitive access road to the Takatz Lake powerhouse. However, we understand that an access road would not be in the project plan unless the Alaska Department of Transportation participates in the project. Figure 2 Direct Buried DC Cable in Sweden Our previous study suggested voltage source converter based DC system for the intertie because the 41 mile long DC submarine cable, between the Takatz Lake Powerhouse and Kake, would not cause a large capacitive current. The capacitive charging current limits the length of an AC submarine cable. However, the capacitive current of the 138 kV submarine cables can be compensated by inductances. Because of the high cost of DC converters, ABB suggested the compensated 138 kV submarine cable as an alternative. Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 12 07/21/11 The advantage of the DC link is that it eliminates the possible stability problems that could surface in this relatively low voltage system with long lines. From a commercial point of view, another advantage is that the DC permits accurate regulation of the power transfer from Takatz Lake powerhouse to Kake and Petersburg. Sitka would be able to control the distribution of the Takatz Lake hydro produced power. Figure 3 HVDC Solid state converter development. (Copy Panel 02-1 Overview of HVDC Transmission, ABB WEB site). 5 Present State of Voltage Source Converter Based HVDC Systems Our previous study and the literature show that the traditional thyristor based HVDC system is economical for transmission systems over 300 miles and 500 MW. Consequently, the traditional DC or even with a hybrid system is not economical or feasible for the Southeast Alaska intertie. This study will consider only the voltage source converter based HVDC and AC systems. The voltage source converter based HVDC system was discovered 10 years ago by ABB, which marketed the system under the name of HVDC Light. In the mean time, Siemens developed a similar system under the name of HVDC Plus. Also, AREVA-ALSTON recently started building similar systems. Several new systems are in successful operation. Some of them have close to 10 years of successful operation record. Table 1 shows the list of existing and future HVDC projects using voltage source converters. In addition to the DC links, the voltage source IGBT converter is used for static VAR compensation. Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 13 07/21/11 Table 1 Light HVDC Systems Name Location Km kV MW Year Type Terranora interconnector (Direktlink) ABB Australia - Mullumbimby ABB 59 80 180 2000 IGBT Eagle Pass, Texas B2B, ABB USA - Eagle Pass, TX 15.9 36 2000 IGBT Tjæreborg, ABB Denmark - Tjæreborg/Enge 4.3 9 7 2000 IGBT Cross Sound Cable, ABB USA - New Haven, CT 40 150 330 2002 IGBT Murraylink, ABB Australia - Red Cliffs 177 ±150 220 2002 IGBT HVDC Troll, ABB Norway - Kollsnes 70 60 80 2004 IGBT Estlink, ABB Estonia - Harku 105 150 350 2006 IGBT NordE.ON 1, ABB Germany - Diele 203 150 400 2009 IGBT HVDC Valhall, ABB Norway - Lista 292 150 78 2009 IGBT Trans Bay Cable, Siemens USA - East Bay - Oakland, CA 88 200 400 2010 IGBT Caprivi Link, ABB Namibia - Gerus 970 500 300 2010 IGBT SydVästlänken, ABB Sweden–Hallsberg Norway–Oslo 400 1200 2013/ 2015 IGBT The voltage source based HVDC system is designed for less power than the classical thyristor based HVDC system. One of the major advantages is multi-terminal DC or DC network building. Typical applications are: • Small isolated remote load supply • Power supply to an island or off shore oil and gas platforms • Interconnection of asynchronous grids • In-feed to cities by land cables • Interconnection of small scale (low-head hydro) generation • Connect off shore wind power generation to power grids 5.1 HVDC with Voltage Source Converter The voltage source converter based HVDC system is a fast developing technology, which uses insulated gate bipolar transistor (IGBT) switches and pulse width modulation (PWM). The capacity of a voltage source converter based HVDC system is limited to 1200MW and +/- 320kV in 2010. The semiconductor manufacturers are increasing the capacity of the IGBT switches and as a result the capacity of the HVDC system is increasing. Presently, Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 14 07/21/11 ABB and Siemens are selling IGBT’s rated 6500V, 600A for HVDC systems. The IGBT has voltage controlled capacitive gate and it is shunted by a parallel connected diode in reverse direction. The first voltage source converter based HVDC was introduced by ABB in 1997. Presently more than 10 systems are in successful operation and several new systems are under construction. The technical parameters of the voltage converter based HVDC system indicate that this technology produces a nearly ideal transmission component that has the potential to change the conventional methods of electric power transmission and distribution. The market survey shows that ABB is offering the HVDC Light system, Siemens offers the HVDC Plus system and ALSTON-AREVA is preparing a demonstration site with voltage source converters. The basic module of the voltage source converter is the three phase bridge built with Integrated Gate Bipolar Transistors, shunted by diodes in the reverse direction. Figure 4 shows basic circuit diagram of a transmission system with voltage source converters. D1 IGBT1 IGBT2 D2 CDC IGBT5IGBT3 IGBT4IGBT6 LAC Vdc VAC C B A CDC D1 IGBT1 IGBT2 D2 CDC IGBT5IGBT3 IGBT4IGBT6 LAC VDC VAC C B A CDC Figure 4 HVDC system with voltage source converter The systems supplying the converters do not need high short circuit capacity or at the receiving end do not need to have generation. The voltage source converter can supply an island without generation. It has black start capacity. Typically a standard transformer and a series converter reactor (inductance) connect the converter to the network. Because of the PWM system only small AC filter is needed. At the DC side, two capacitors connected in series serves as a filter. The midpoint of the capacitors is grounded. The converter is not grounded if it is a floating system. Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 15 07/21/11 The converters can operate automatically without communication between the stations. The system can regulate both the amplitude and phase angle of the AC voltage. This means the independent regulation of the active and reactive power. The direction of power transfer depends on the voltage. The current flows from the converter operating at a higher voltage than the other. The reversal of the power flow requires the reversal of current direction and not the reversal on the voltage. The system is suitable for multi-terminal operation. Each valve consists of several hundred IGBTs connected in series. The valve is divided into series connected modules called StakPak by ABB. Figure 5 shows the StakPak module. Several of these modules are connected in series to form the valve. Figure 5 StakPak module of IGBT’s (Copy from ABB Website [1]) The IGBTs are cooled by de-ionized water. The even voltage distribution is assured by a parallel connected voltage divider. Figure 6 shows the general arrangement of heat sinks, IGBT modules and gate drives. Figure 6 Arrangement of Heat sinks and IGBT modules (Copy from ABB Website [1]) The voltage across each IGBT is rectified and provides power for the gate drive of the IGBT. Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 16 07/21/11 An optical link from the ground controls the gate drives. Figure 7 shows a section of an IGBT valve used for HVDC light systems. Figure 7 IGBT valves used for light HVDC (Copy from ABB Website [1]) Siemens introduced the HVDC Plus system and built the Trans Bay Cable projects in California. One major contribution of Siemens is the development of a new type of multi-level converter. Figure 8 shows the basic circuit, which contains two IGBT’s and a capacitor. Several of these units are connected in series to form the valve as shown in Figure 9. Figure 8 Multi-level converter for the HVDC Plus system. Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 17 07/21/11 Figure 9 HVDC plus valve. Copy from Siemens Website The VSC technology allows straightforward AC side connections. The HVDC Plus system is supplied by standard transformers equipped with cooling fans. The HVDC Plus system is protected by one circuit breaker per converter station, which is connected between the power transformer and the AC network. The station can be safely isolated from both the AC network and DC circuit with disconnect switches. The insulated AC and DC bus can be automatically grounded with grounding switches for safety reasons. Standard surge arresters protect the system against lightning and switching type over-voltages. On the AC side, the voltage and current is measured by standard voltage and current transformers. The DC voltage is measured by resistive voltage dividers and the DC current is measured with shunt resistances. Due to its modular construction, the HVDC Plus converter is flexible in its configuration, which permits the use of standard components. 5.2 HVDC Substations The HVDC substations with voltage source converters are built indoors except the transformers. The station is built with modular equipment, in which the components are installed in enclosures in the factory. Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 18 07/21/11 Figure 10 Conceptual design of a HVDC light substation (Copy from ABB Website [1]) Figure 10 shows the general arrangement of a voltage source converter based substation. In this figure, three AC cables feed the substation through filters and three large series connected phase reactors (inductance). The IGBT valves are installed in the factory in metal clad enclosures. The rather large cooling system is adjacent to the valves. The DC side with the filter capacitors is at the back of the substation. Figure 11 IGBT valves mounted in metal enclosures (Copy from ABB Website [1]) Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 19 07/21/11 Figure 11 shows two light green boxes containing the IGBT valve assemblies. These boxes are assembled in the factory and transported to the site. The factory assembly is particularly advantageous for Alaska where the construction is difficult in the winter time. Figure 12 shows the photograph of another ABB HVDC Light substation, where the valves are placed in a building. This substation is supplied by four transformers (one spare) and through filters placed between the transformers and the valve hall. Figure 12 Light HVDC station (Copy from ABB Website [1]) In the foreground of the buildings is the cooling equipment. The fans are visible in the picture. Figure 13 Pair of extruded polymer HVDC cables. (Copy from ABB Website [1]) Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 20 07/21/11 5.3 HVDC Cables The voltage source based HVDC system can supply transmission lines or cables. The advancement of cable technology promotes the use of land cables, which can be competitive with the overhead lines in difficult terrains where a road is present. The HVDC Light systems use extruded polymer cables for land cable. Usually, HVDC light is an ungrounded bipolar system with a positive and a negative cable. As an overhead line, it also needs two conductors (positive and a negative). Figure 13 shows typical polymer cable pair designed for the HVDC Light application. The cable has aluminum conductors surrounded by a black semi-conducting layer, which reduces the electrical field on the conductor surface. The white extruded polymer is the main insulation of the cable. The polymer insulation is surrounded by black semi-conducting layer and a grounded woven copper shield conductor. The next white layer prevents water penetration. The outer jacket of the cable is PVC. Figure 14 shows the construction of a typical submarine cable. The coaxial single conductor cable is XLPE insulated. The construction of this cable is more rugged than the cables used on land. This cable has two layers of shield conductors, lead sheet and steel wire armor. Figure 14 DC submarine cable Submarine cable installation requires a cable laying ship. Pirelli operates the Giulio Verne Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 21 07/21/11 cable ship, which is capable of laying cables in all weather conditions. Figure 15 shows this ship that is equipped with a 7000-ton rotating turntable. Figure 15 Giulio Verne Cable Laying Ship Copy from Siemens Website ABB suggested the use of a compensated 138kV submarine cable connection between Takatz Lake and Kake. The proposed cable is shown in Figure 16. Figure 16 138kV Cross-linked polyethylene Cable Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 22 07/21/11 According to Prysmian(Pirelli) and Caldwell Marine, the installation of the proposed 138 kV AC three conductor submarine cable is feasible but there are three extraordinary design considerations that significantly increase the material and labor costs. The minimum recommended conductor size for 138 kV AC cables is 750 kCM per the Association of Edison Illuminating Companies (AEIC) standards and 600 kCM per the Insulated Cable Engineers Association (ICEA) standards due to the electric fields. Therefore, the 185 square mm or about 350 kCM copper conductor recommended by ABB would not meet these standards. Since double armor is recommended for the depths up to 2100 ft. (350 fathoms) in Chatham Strait, a three conductor 750 kCM copper 138 kV AC double armored submarine cable would be significantly more expensive than the ABB estimate. This 138 kV AC submarine cable also will have considerable more weight due to the larger conductors and extra armor. When installed at 2100 depth, Caldwell Marine estimated the maximum cable tension would be approximately 64,000 lbs. This high tension exceeds the strength of the cable and equipment capacity. Prysmian(Pirelli) recommended a special double flat strap cable armor that is shown in Figure 16. This special armor reduces the cable weight from 65 lbs/ft to about 57 lbs/ft. The cable weight and approximately 8” cable diameter results in a logistics problem and Prysmian(Pirelli) indicated that the installation would have to be performed in two separate campaigns. Only half of the cable could be laid at one time and the cable ship or barge would have to return to port to load the remaining submarine cable. As a result, the mobilization and demobilization cost would approximately double along with the cost of an underwater cable splice. The closest port with the facilities to handle the submarine cable is Seattle or in Prysmian’s case, the Guilio Verne would have to return to Naples, Italy for the second load. The proposed 80 kV DC submarine cables do not have similar extraordinary design considerations that increase the material and labor costs. The required copper conductor size for the two 80 kV DC submarine cables due to ampacity is 600 kCM so the minimum conductor size is not an issue. The weight of 600 kCM copper conductor is about 80 percent of 750 kCM copper conductor so the 80 kV DC single conductor submarine cable weight and tension will be less than the 138 kV AC three conductor submarine cable and probably not an issue. However, two passes of the cable ship or barge are required to lay the two 80 kV DC single conductor submarine cables. According to Caldwell Marine, the estimated installation cost to lay the two 80 kV DC submarine cables will be about $8M more than the 138 kV AC three conductor submarine cable. 5.4 PWM technology The modern manufacturing industry requires AC motor drives that are accurately regulated. These drives should operate close to unity power factor and not generate significant current harmonics in the AC supply. These requirements led to the development of the PWM (pulse width modulation) technique. Figure 17 shows the concept of PWM and Figure 18 presents the generated voltage waveform. Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 23 07/21/11 D1 IGBT1 IGBT2 D2 CDC IGBT5IGBT3 IGBT4IGBT6 LAC VDC VAC C B A Figure 17 Circuit diagram of a PWM converter The converter in Figure 17 can operate as a rectifier or as an inverter. It is built with six semiconductor switches, which are shunted by diodes. The semiconductor switch can be a transistor, IGBT or a MOSFET. The six switches form a six-pulse bridge. A capacitor shunts the DC side and three inductors are connected in series with each phase on the AC side. The switches are turned on in sequence, e.g. 1-2, 3-4, 5-6, etc. The turn on of switch 1 connects the positive DC terminals to phase A and the turn on of switch 2 connects the negative DC terminals to phase B. The switches are turned on for a short period of time, which generates a pulse train at the ac terminals. Figure 18 PWM voltage waveform Figure 18 shows the generated pulse train. It can be seen that the width of the pulses is modulated and hence the name PWM. The filtering of the output voltage produces a sinusoidal waveform. Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 24 07/21/11 Figure 19 Generation of PWM voltage waveform The generation of the PWM waveform is illustrated on Figure 19. As shown in Figure 19(a), a high frequency triangular wave is compared with a 60 Hz reference sine wave to generate the control pulses shown in Figure 19(b). The intersection of the triangular ‘carrier’ and the sinusoidal ‘reference’ determines the pulse width as demonstrated in Figure 19(b). If the sinusoidal reference voltage is higher than the triangular carrier wave, the upper semiconductor switch (1, 3 or 5) connects the phase terminal to the positive DC terminal; if it is lower the bottom switch (2, 4 or 6) connects the phase terminal to the negative DC terminal. The frequency spectrum of the generated pulse train contains the base 60 Hz component and other high frequency components. The latter are multiples of the triangular carrier frequency. The AC inductance blocks the current harmonics at the AC side, which are further reduced by a high-pass filter. The DC capacitor reduces the harmonics at the DC side. The DC capacitor also controls the turn-off over voltages, by providing a low impedance path. The output voltage can be controlled by the pulse pattern and by the DC voltage. This converter can supply a passive AC system. It can be used to start an AC system after a fault. If the AC system has a voltage source, controlling the converter voltage phase angle can independently regulate the real and reactive power transfer. The active power depends mostly on the converter voltage phase angle and the reactive power is dependent on the Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 25 07/21/11 voltage magnitude. The converter can act as a motor or generator without mass and can provide either capacitive or inductive reactive power. The converter controls the AC current and consequently does not contribute to the AC short circuit current. The PWM converter is an ideal device for energy transmission. It was proposed and developed more than a decade ago for low power applications. The lack of high power high frequency switches initially prevented application to HVDC systems. For start up, the AC breaker is closed at one side. The diodes in the converter produce a DC voltage and energize the DC line. This charges the power supplies of the gate drive units, which permits a start of the converter operation. The first converter that starts will control the DC voltage. The second converter that starts controls the power transfer. The reactive power is controlled independently at each station. The active power flowing in the DC network has to be equal to the active power transmitted from the first network to the second network plus the losses. In this system, one converter station maintains the DC voltage constant. The other station controls the active power flow within the limits of the system. This is achieved by controlling the phase angle between the network voltage and the sinusoidal reference control voltage. If an AC fault occurs at the side that receives the power, the power-controlling converter is blocked. This interrupts the outgoing power, but not the incoming power. This results in a fast rise of DC voltage. The dc voltage-controlling converter will reduce or even reverse the incoming power to maintain the DC voltage level. If the fault occurs on the AC side of the converter that controls the DC voltage, the converter is blocked and a sudden drop in the DC voltage occurs. In this case, the remaining converter will control the DC voltage and simultaneously control its reactive power flow. The operation mode of this converter will be similar to the operation of a dynamic voltage restorer. In case of a ground fault in the AC system, the converter control will reduce the DC voltage to limit the current flow to the pre-fault value. The voltage source converter will not increase the short circuit current in the AC system. Voltage source converters can be applied to HVDC system to permit multi-terminal operation. Several converters can be connected in parallel to a DC transmission line. Sitka Takatz Hydro Kake Petersburg DC Submarine Cable 41.1 mi 69kV AC 69kV AC 138 kV AC DC line 21.1 mi DC line 44.3mi 20MW 69kV Figure 20 Example for a planned multi-terminal DC system Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 26 07/21/11 As an example if the Sitka-Kake-Petersburg Intertie is built with voltage source converters, four converters could be connected in parallel by DC transmission lines and submarine cables. Figure 20 shows the possible arrangement. The problem with this arrangement is that the power requirement of the various sites is different. As an example, Kake requires power less than a MW, the Sitka and Petersburg sites requires 50 MW and the Takatz Lake Hydro can be operate with 25-30MW converter. ABB suggested +/- 80kV or +/- 100kV system voltage. The cost of the small MW converters is very high. 1 Manufacturers Data The literature survey shows that three manufactures offer voltage source based HVDC systems in the USA. The manufacturers are: ABB, Siemens, AREVA. All of the three manufacturers have been contacted. We presented the map of the Sitka-Kake-Petersburg Intertie together with the load data and requested a proposal for the system configuration (AC or DC system), voltage level and budgetary cost estimate. Surprisingly, the manufacturers showed very little interest to supply a HVDC system rated 50 MW. We learned that ABB and Siemens are building large HVDC systems for India and China and has no time to work on small systems. The E mail received from ABB states that the use of HVDC Light system is feasible but more economical to use AC transmission for the 50MW Sitka - Kake – Petersburg intertie. The recommendation is copied below: “ABB recommends the following solution: (1) Extend the 138 kV system from Petersburg to Kake by constructing a 138 kV AC line. [50 MW transfer exceeds four times surge impedance loading for a 69 kV line which would be at about its practical line loadability limit for the 44 MW distance.] (2) Install a 138 kV, three-core, submarine cable between Kake and cable landing site near Takatz Lake Hydro. Reactive power compensation may be required at Kake. Cable estimate and technical data is provided below. (3) Build either a 69 kV or 138 kV AC line from the Takatz Lake cable landing site to Sitka to complete the new interconnection between Sitka and Petersburg. (4) There is no reason to install an HVDC system for this application. If one were to do so, however, the logical choice would be to install a 50 MW, +/- 80 kV two-terminal HVDC Light system in symmetrical monopole configuration with two 80 kV single core HVDC Light cables between Takatz Lake Hydro and Kake, and completing the interconnection with AC overhead transmission as described above. Each 50 MW converter station would cost about $35 MUS at today’s exchange rate. The system would most likely be too weak to support conventional HVDC under all operating conditions. The HVDC cable crossing would cost roughly about 70% that for the AC cable crossing. Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 27 07/21/11 (5) The only reason to consider multi-terminal HVDC for this application is if overhead lines are not permitted and cable must be used the entire way. Even then there would be some issues. It would not be possible/practical to serve Kake, a load of only 2-5 MW, from a +/- 80 kV converter. The current would be too small. (6) Even if overhead lines were prohibited, it is probably feasible to build the entire interconnection with AC cable, provided static and dynamic reactive power compensation were installed at each terminal, i.e. Sitka, Takatz Lake Hydro, Kake and Petersburg. The exact values of the reactive power compensation equipment would need to be determined by system study. (7) Although land cable itself would be less expensive than submarine cable, installation cost would be much higher. Depending on the terrain, land cable installation cost could easily run about equal to that of the cable itself. In this application, installed cost of the cable would probably be about twice that of the overhead line as a general approximation. A detailed estimate for the line would have to be compared with a detailed estimate for the cable by contractor with knowledge and experience in this area. (8) Another possible application for an HVDC alternative would be to run the 50 MW +/- 80 kV HVDC submarine cable circuit all the way through the water between Takatz Lake Hydro and Petersburg thereby avoiding a new line between Petersburg and Kake. This may be a competitive alternative. In this case Kake would have to served by local diesel generation or a small AC cable from Takatz Lake Hydro. Budget estimate for the AC cable connection only: This budget estimate includes manufacturing and delivery of 70km 3x185mm2 138kV AC Cable with an integrated 48 SM optical fiber cable, six terminations and one off-shore splice. (no installation) Item Description Quantity Unit price Total price 1 138kV Submarine Cable 70 km 425 USD/m 29 750 000 USD 2 38kV Outdoor Terminations 6 ea. 7 250 USD 43 500 USD 3 138kV Submarine cable Splice 1 ea. 40 000 USD 40 000 USD 4 Mob/demob and Transportation 1 L.S. 4 000 000 USD 4 000 000 USD Total price: $33,833,500 US (Import duties and taxes for Alaska excluded) Based on: Cu = 8140 USD/ton Pb = 2320 USD/ton Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 28 07/21/11 6.64 SEK/USD exchange rate The voltage drop will be around 2.6% for the total length of the circuit. Cable design enclosed (DRAFT) It is hereby understood that neither the indicative technical and pricing data, its associated commercial terms nor any past or future action, course of conduct or failure to act by either party regarding the project will give rise to or serve as a basis for any obligation or other liability on the part of the parties or any of their affiliates. Neither party shall be obliged to enter into any further agreement with the other party. Any commitment, agreement or binding obligation with respect to the project would only arise and would be subject to, among other things, the negotiation, the due execution and delivery by the parties of the definitive agreement regarding the project. ("Definitive Agreement"). The recommended HVDC Light voltage, as indicated below is +/- 80 kV, with symmetrical monopole configuration. The cost of the +/-80 kV HVDC Light submarine cable circuit, also as indicated below, would be about 70% that of the AC cable submarine cable circuit. Note you can prorate for distance to determine the cost of going all the way to Petersburg through the water. We have made no estimation for installation of the cable. Based on this the cost of the DC submarine cable circuit (2 cables) would be 0.7 x $33.8 M = $23.7 M for the 70 km distance + installation say + 20%. We have made no estimation for the +/- 80 kV HVDC Light land cable, but in general it would cost, with joints and terminations, significantly less than the submarine cables due to use of Al conductor instead of Cu, no lead jacket, no armoring, etc. The installation cost would be dependent on local conditions and would require input from contractor but you could assume that installation costs with civil works would cost as much as the cable itself. Therefore for budgetary estimating purposes, you could assume 70% the cost of the DC submarine cable and double it to account for land installation. 0.7 x $23.7 = $16.6 M, or $237 k/ ckt-km for cable and joints + say $200 k /ckt-km for trenching and installation = $437 k/ckt-km but you would be better off to get estimates from local contractors for that portion. Hope this is adequate for you needs. Our cable folks are extremely busy with RFP's for real committed projects and cannot really give any more detail especially in the absence of real router data and local construction costs. “ The discussion with Siemens resulted similar results, but Siemens did not provide any written estimate in spite of the repeated request. The discussion with AREVA T&D resulted the following E mail: Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 29 07/21/11 “ ….For the cable connection Nexans would propose 75 kV monopole configuration with return conductor. 65 km of TKRA-L 75kV 1x300mm² 65 km of TSRA 24kV1x300mm² Total ball park price ex-works Halden, Norway: 20 MUSD Total weight of 2x65 km of cable as above: 1300 tonnes Transport and installation can be estimated once we have more knowledge of project, sites, depth etc. Unfortunately, this leads to an asymmetrical monopole arrangement, which means the converter transformers would be specials. I am working with Nexans to determine a more optimized solution, based on a mid-point ground design. As for the converters, they are IGBT-based multilevel bridges, building on our previous experience with the multilevel GTO-based STATCOMs presently in service. The ABB systems I believe are all 2 or 3 level configurations, although I think they are developing a multilevel system now. The converters for the asymmetrical solution above would probably be in the region of 30 MUSD, so I am trying to optimize this a little more with the cable design. I want to put the voltage down and the current up, whereas they want to put the voltage up and the current down. FYI, here is some recent presentation material which illustrates our VSC system. It's basically an IGBT-based multilevel converter with a maximum rating of 1250 A DC. We can add sufficient modules in series to achieve the required DC rating. The maximum XLPE cable rating is presently around +/-320 kV, so we can achieve up to about 800 MW at the moment. If you want more details please let me know. “ The two presented E-mails shows that the manufacturers are not very motivated to supply small systems. 2 Conceptual design and cost estimate Figure 21 shows that both load and generation will increase significantly between 2010-2030 in the Sitka area. Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 30 07/21/11 Figure 21 Sitka’s Electric Energy Requirements and Resource In spite of the expected rapid load growth, the building of Takatz Lake Hydro increases the system capacity and produces surplus energy, which can be sold in the Petersburg area. This justifies the 50 MW rating of the proposed intertie. In Sitka, the existing system is rated at 69kV, while in the Petersburg area 138 kV is used. The distance between Petersburg and Sitka is about 115 miles. A 138 kV transmission line is marginally suitable to transport 50 MW from Petersburg to Sitka. Simultaneously, the 69 kV line cannot transport 50 MW for such a long distance. An additional problem is the 41 mile submarine cable between Takatz Lake Hydro and Kake. The large charging current limits the capacity of the submarine cables. Compensation of the charging current is needed for AC transmission or a DC link must be used. The viable solutions are: • Hybrid System Alternative 1: 69kV AC transmission line between Sitka and the Takatz Lake Hydro, +/- 80kV DC submarine cable between Takatz Lake Hydro and Kake, and 138 kV AC transmission line between Kake and Petersburg. • Hybrid System Alternative 2: +/- 80 kV DC land cable between Sitka and the Takatz Lake Hydro, +/- 80 kV DC submarine cable between Takatz Lake Hydro and Kake and 138 kV AC transmission line between Kake and Petersburg. • Multi-Terminal DC Alternative 1: +/-80 kV DC submarine cable between Takatz Lake Hydro and Kake and +/- 80 kV DC transmission line in the rest of the intertie. • Multi-Terminal DC Alternative 2: +/- 80kV DC submarine cable between Takatz Lake Hydro and Kake and +/- 80kV DC transmission cable in the rest of the intertie. • AC System with Compensated Submarine Cable. 69kV AC transmission line between Sitka and the Takatz Lake Hydro, 138 kV compensated submarine cable between Takatz Lake Hydro and Kake and 138 kV AC transmission line between Kake and Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 31 07/21/11 Petersburg. 2.1 Hybrid system The Alternative 1 hybrid system uses conventional AC transmission lines and HVDC submarine cable for crossing Chatham Strait and Frederick Sound between Kake and Takatz Lake. For Alternative 2 hybrid system, the 69 kV line is replaced by +/- 80 kV DC land cable. 2.2 Hybrid system-Alternative 1 The use of conventional tyristor based HVDC is uneconomical for this low load and short distance. The voltage source converter based HVDC Light or HVDC Plus has been used for this type of submarine crossing in the past. In this hybrid system, the HVDC supplies only the submarine cable. A bipolar, ungrounded voltage source converter based HVDC system with +/- 80kV voltage is proposed for the submarine cable. The concept of the hybrid system is shown in Figure 22. At Kake, the HVDC system will be connected to the 138kV transmission line through a transformers and circuit breakers; at Takatz Lake, the HVDC will supply the local 69 kV lines through a transformer and circuit breaker. The rest of the system is a conventional 69kV or 138kV AC system, with wood pole transmission lines. Figure 22 Hybrid system conceptual connection diagram Sitka builds heavy duty 69 kV lines with horizontally arranged ACSR, 336.4 kCM “Linnet” conductors. The conductor amperage is 537A, the distance between the phases is 10ft 6in, the line resistance per phase is 0.2901 ohm/mile, the reactance is 0.764 ohm/mile, and the capacitance is 14.68 nF/mile. Figure 23 shows the typical wood pole H-frame structure. Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 32 07/21/11 Figure 23 69 kV transmission tower used in Sitka area The distance between Blue Lake switchyard and Takatz Lake Hydro is about 22.6 miles. The 50MW load current is 523A at 69 kV. The capacity of the 336 ACSR with ampacity 537 A is marginal for 50 MW transfer. The voltage drop is 19.04% for the transportation of 50 MW at power factor 0.8 lagging. This is an unacceptable high value. Further analysis shows that a 69 kV line can transport less than 26 MW power to a distance of 22.6 mile at power factor 0.8 lagging when the voltage drop is limited to less than less 10%. Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 33 07/21/11 Figure 24 138 kV transmission tower used in Petersburg area The line capacity can be increased by series connected capacitors. As an example, 3.5µF capacitors connected in series with this line permit the 50 MW load at less than 10% voltage drop and a 7 µF capacitor reduces the voltage drop to 4.82% at 50 MW load. This calculation shows that practically all 28 MW power generated by the future Takatz Lake Hydro can be transported by one 69 kV line to Sitka. However, if the intertie is built, most of the Takatz lake Hydro produced power would be sold to Petersburg. The load at Sitka is less than 25 MW; consequently, the transportation of 50 MW to Sitka is not needed even in Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 34 07/21/11 emergency conditions. If the 50 MW transfer is necessary, 3-4 µF series capacitors must be inserted in the 69 kV line at Takatz Lake or at Sitka. An alternative but more expensive solution is the double circuit line or large conductors. The Kake-Petersburg 50.0 mile section must be 138kV. Figure 24 shows the typical 138kV lines used in the Petersburg area. The 138kV line typical heights are 40ft. The line uses ACSR 336kCM conductor with horizontal span of 350ft. A 24 strand ADSS communication cable would be placed 13 ft under the conductor. The right of way clearance is about 60-50ft wide. The ampacity of the ACSR 336kCM conductor is 537A and the load current at 50MW, power factor 0.8 lagging is 261.5A. The average GMR distance is 12.51ft, the line resistance per phase is 0.2901ohm/miles, reactance is 0.758ohm/mile, and capacitance is 14.82nF/miles. The 50 MW load produces 9.469% voltage drop at power factor 0.8 lagging. This is a marginally acceptable value. Fortunately the HVDC can adjust the voltage and compensate for the marginal voltage drop on the 138kV line. Takatz Lake Hydro and Kake section of the intertie is +/- 80 kV bipolar HVDC system with 41 mile long submarine cable. The 50 MW transmission at 80 kV requires a current of 625A. Table 6 shows submarine cables offered by ABB for a HVDC Light system. Table 2 HVDC light submarine cables (Extract from ABB Brochure “HVDC Light Cables”) According Table 2, the 625A load current requires 300mm2 copper submarine cables if the voltage between the cables is 80 kV, and the cable is spaced “Close Laying”. This implies that the line to ground voltage is only 40 kV. Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 35 07/21/11 Table 3 list the converters that ABB offers for the submarine cables. The smallest converter is the M1 unit which is rated to 102 MW. This is proof that ABB does not offer a 50 MW HVDC light system. The cables will be supplied by two (2) 50MW, 80kV voltage source converters with rated current of 625A. Considering the data in Table 3, the 50MW can be supplied by the half of the M1 converter that is rated to 109 MW. This implies that the voltage between the cables is 80 kV and the voltage to ground is +/-40kV. Table 3 HVDC light Converters (Extract from ABB Brochure “HVDC Light Cables”) 2.3 Hybrid system Alternative 2 The alternative 2 hybrid system includes the addition of a DC land cable section to the intertie, replacing the 69kV transmission line between Takatz Lake and Blue Lake switchyard. Table 4 HVDC Light Submarine Cables (Extract from ABB Brochure “HVDC Light Cables”) Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 36 07/21/11 The terrain between these two stations is very rough, high elevation, with several meters snow in the winter. The maintenance and repair of this line is complicated and the building of this line would be very expensive. We recommend that the City of Sitka build a primitive access road between Takatz Lake and the Medevejie access point, which would permit the direct buried land cable installation or would significantly reduce the cost of overhead line construction. Table 4 shows the land cables offered by ABB. According to Table 4, the 625 A load current requires a land cable with 400mm2 cross section with “Spaced laying”. This cable rating is 90MW, and ampacity is 705A in case of “Spaced laying “. The required cable length is 22.6miles. In this case the system needs an additional 80kV converter at Sitka. The total number of converters needed for this alternative are three (3): Sitka, Takatz Lake and Kake. The other components are: 50.0 miles of 138 kV transmission line between Petersburg and Kake; 41.0 miles of 80kV DC submarine cable pair between Kake and Takatz Lake. 2.3.1 Transmission Line and Cable Cost Estimate Single Wood Poles 138 kV AC Wood $600,000/mile w/Access Road 69 kV AC Wood $550,000/mile 80 kV DC Bipolar $400,000/mile Heavy duty 138 kV AC Wood $1,200,000/mile H-Frames w/ 69 kV AC Wood $1,100,000/mile Helicopter 80 kV DC Bipolar $800,000/mile Construction Submarine Cable 138 kV AC, with installation $1,494,032 /mile 80 kV DC land cable, with installation $763,684/mile 80 kV DC, with installation $1,191,120/mile Underground Land 69 kV AC $2,000,000/mile Cable W/Conduit 80 kV DC $1,400,000/mile & No Road 2.3.2 Hybrid System Alternative 1 & 2 Cost Estimate The major cost is the HVDC stations and the submarine cable. Cable selected from ABB brochure “HVDC Light cables” is the 150mm2 submarine cable. ABB E mail recommends:”50 MW, +/- 80 kV two-terminal HVDC Light system in symmetrical monopole configuration with two 80 kV single core HVDC Light cables between Takatz Lake Hydro and Kake, and completing the interconnection with AC overhead transmission as described above. Each 50 MW converter station would cost about $35 MUS at today’s exchange rate.” In spite of our repeated request Siemens did not provide budgetary cost estimate for a 50 MW HVDC Light system. AREVA estimated the 50 MW converter station for $30M. Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 37 07/21/11 We updated the cost estimates presented in our previous study. The mono-polar system has been eliminated together with the parallel connected converters because both ABB and Siemens WEB sites offer only a bipolar system. The cost of the transmission lines was re-estimated using current data obtained from the 2009 Kake Petersburg Intertie Study Update Report. For estimation of the converter cost, the estimates made 10 years ago were updated. The ABB provided original estimate included the cost of interconnecting transformers in the converter price. The expected increase of the converter price can be estimated using the variation of Consumer Price Index. Table 5 shows the variation of the consumer price index between1999–2010. Table 5 Variation of Consumer Price Index between 1999-2010 YEAR JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC ANN 2010 216.687 216.741 217.631 218.009 218.178 217.965 218.011 218.312 218.439 9999 9999 9999 9999 2009 211.143 212.193 212.709 213.24 213.856 215.693 215.351 215.834 215.969 216.177 216.33 215.949 214.537 2008 211.08 211.693 213.528 214.823 216.632 218.815 219.964 219.086 218.783 216.573 212.425 210.228 215.303 2007 202.416 203.499 205.352 206.686 207.949 208.352 208.299 207.917 208.49 208.936 210.177 210.036 207.342 2006 198.3 198.7 199.8 201.5 202.5 202.9 203.5 203.9 202.9 201.8 201.5 201.8 201.6 2005 190.7 191.8 193.3 194.6 194.4 194.5 195.4 196.4 198.8 199.2 197.6 196.8 195.3 2004 185.2 186.2 187.4 188 189.1 189.7 189.4 189.5 189.9 190.9 191 190.3 188.9 2003 181.7 183.1 184.2 183.8 183.5 183.7 183.9 184.6 185.2 185 184.5 184.3 183.96 2002 177.1 177.8 178.8 179.8 179.8 179.9 180.1 180.7 181 181.3 181.3 180.9 179.88 2001 175.1 175.8 176.2 176.9 177.7 178 177.5 177.5 178.3 177.7 177.4 176.7 177.1 2000 168.8 169.8 171.2 171.3 171.5 172.4 172.8 172.8 173.7 174 174.1 174 172.2 1999 164.3 164.5 165 166.2 166.2 166.2 166.7 167.1 167.9 168.2 168.3 168.3 166.6 According this table the Consumer Price Index was 164.3 in January 1999 and it increased to 216.678 by January 2010. The increase during the 10 years period is: 216.678/164.3 = 1.319. The expected increase of the converter cost can be estimated using the increase of Consumer Price index. The 2 x 25 MW, converter station, with the transformer was $22M, the updated figure is: 50MW Converter Cost = 1.319 *$ 22M = $29.013 M. ABBs’ E-mail gives a budgetary price for 138kV AC submarine cable and for the 80kV DC land and submarine cables. Table 6 gives the ABB provided data in US units. ABB estimated the 50 MW converters would cost $35M. The converter price escalated very rapidly in the last 10 years. We used an updated converter price of $29M for the 50MW converters in our price estimation, which is a conservative approach. We also increased the submarine cable cost to be consistent with other manufacturers. Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 38 07/21/11 Table 6 ABB Provided Cost Data Using the updated data converter data and the adjusted line data, the Hybrid system cost was estimated and presented in Table 7 and Table 8. Table 7Hybrid systems with HVDC light, Alternative 1:69 kV and 138 kV transmission lines and 80 kV DC submarine cable Hybrid System with 69 kV Line, Alternative 1 Description Number of miles or number Cost per mile in $Total cost $ 69kV AC Transmission Line- Double Circuit 5.0 750,000$ 3,750,000$ 69kV AC UG Land Cable- Tunnel 2.0 2,300,000$ 4,600,000$ 69kV AC HD Transmission Line- H Frames 16.4 1,100,000$ 18,040,000$ 138kV AC Transmission Line- Single Pole 50.0 600,000$ 30,000,000$ 138kV AC Submarine Cables- Duncan Canal 2 5,600,000$ 11,200,000$ 138kV AC Kake Substation and Petersburg Tap 1 2,600,000$ 2,600,000$ IGBT 80kV Converter, Filter, Transformer 2 29,013,000$ 58,026,000$ 80 kV DC Submarine Cable- Chatham Strait 41.1 1,191,120$ 48,955,032$ Total 177,171,032$ Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 39 07/21/11 Table 8 Hybrid system with HVDC light, alternative 2:138 kV transmission lines and 80 kV DC submarine cable, 80 kV Hybrid System with Land Cable, Alternative 2 Description Number of miles or number Cost per mile in $Total cost $ 80kV DC UG Land Cable- Road Access 5.0 1,000,000$ 5,000,000$ 80kV DC UG Land Cable- No Road 18.4 1,800,000$ 33,120,000$ 138kV AC Transmission Line- Single Pole 50.0 600,000$ 30,000,000$ 138kV AC Submarine Cables- Duncan Canal 2 5,600,000$ 11,200,000$ 138 kV AC Kake Substation and Petersburg Tap 1 2,600,000$ 2,600,000$ IGBT 80kV Converter, Filter, Transformer 3 29,013,000$ 87,039,000$ 80 kV DC Submarine Cable- Chatham Strait 41.1 1,191,120$ 48,955,032$ Total 217,914,032$ The comparison of the data in the Tables shows that Alternative 2 with the land cable is significantly more expensive than Alternative 1 with the 69kV line. 2.4 Multi-Terminal DC System The multi-terminal system contains DC transmission lines and submarine cable, rated to 50MW. The converters are connected in parallel to the line. The selection of converters matching the local maximum load is not practical. According ABB the purchase of four 80kV, 50 MW converters may be feasible but different lower rated units are prohibitively expensive. The smallest unit that ABB offers at 80kV is the M1 converter that is rated to 109MW. 2.4.1 Multi-Terminal DC System Alternative 1 The multi terminal DC eliminates potential transients and steady state transient stability problems. The voltage drop in the DC system is less than a comparable AC system because of the lack of inductive components in the DC line. Figure 25 shows the conceptual connection diagram of the proposed system. Sitka Takatz Hydro Kake Petersburg DC Submarine Cable 41.1 mi 69kV AC 69kV AC 138 kV AC DC line 21.1 mi DC line 44.3mi 28MW 69kV Figure 25 Multi-Terminal DC Transmission System. Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 40 07/21/11 The DC line is rated 80kV and would be built with four (4) converters rated 50 MW each. The maximum load current at 80kV voltage between the terminals is 625A. The existing 69kV AC transmission line design used in Sitka can be converted to 80 kV DC by removing the insulator and conductor in the middle. The voltage between the conductors would be 80kV. The City of Sitka’s 69 kV lines are built with 336.4 kCM 26/7 ACSR "Linnet” conductors. The thermal rating of the Linnet conductor is 537A. The 625A converter current requires a larger conductor for the DC line. The 477 kCM “Flicker” conductor rated 670A is suitable for this DC application. Figure 23 shows the typical tower of the 69 kV H-frame line used in Alaska. This is a wooden tower with MacLean S1 series suspension (composite) insulators; the catalogue number is: S148040VX06. The technical specification of this insulator is listed in Table 6. Figure 26 shows the S1 composite insulator. Figure 26 The S1 composite insulator (Copy from MacLaen Catalouge) Table 9 Technical Specification of MacLaen Composite Insulators. (Copy from MacLaen Catalogue) Catalog Number Line Voltage Section Length (in) Dry Arc (in) Leakage (in) Dry Electrical Flashover (kV) 60 Hz Wet Electrical Flashover (kV) 60 Hz CIFO+ (kV) Neg Electrical Flashover (kV) CIFO Weight Ea (lbs) S148040VX33 69 40.0 29.9 47.7 299 270 519 556 6.5 S148040VX06 69 40.0 29.9 70.9 299 270 519 556 8.3 S148040VX21 69 40.0 29.9 90.3 299 270 519 556 9.8 S148048VX24 115 48.0 37.9 78.9 375 338 648 690 8.6 S148048VX02 115 48.0 37.9 121.5 375 338 648 690 11.9 S148048VX11 115 48.0 37.9 140.9 375 338 648 690 13.9 S148052VX39 115 52.0 42.9 79.1 413 372 712 756 8.4 S148052VX36 115 52.0 42.9 117.8 413 372 712 756 11.4 S148052VX37 115 52.0 42.9 144.9 413 372 712 756 14.0 S148060VX35 138 60.0 49.9 94.8 490 437 837 886 9.3 S148060VX04 138 60.0 49.9 141.2 490 437 837 886 12.9 S148060VX36 138 60.0 49.9 172.2 490 437 837 886 15. Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 41 07/21/11 The peak AC line to ground voltage on a 69 kV line insulator is: The dry and wet flashover voltage of the insulator is larger than 270kV. The leakage distance is 70.9 inches. The voltage stress on the S148040VX06 insulator is: Table 10 gives the IEC 515 recommendation for “specific creapage distance” at different pollution levels. The creapage distance is the reciprocal value of the voltage stress. The creapage distance of the S148040V06 insulator used in the typical 69 kV line is: Table 10 shows that this insulator is suitable to operate under very heavy pollution conditions because its creapage distance is longer 31mm/kV. Table 10 IEC 515 Recommended Creapage Distances for Polluted Insulators. (Copy from IEC 515) The table specifies the “specific creapage distance” for standard porcelain insulators. The pollution performance of composite insulators is better than the standard porcelain insulators. Consequently, the “specific creapage distance“given in Table 10, provides conservative leakage distance for composite insulators. The consensus is that for DC voltage the “specific creapage distance” should be 30% larger than the same AC voltage. The conversion of the AC line to DC requires the longer specific creapage distance. The specific creapage distance for heavy pollution and for DC line is: VLn 1.05 69kV 3⋅41.829 kV=:= Eins VLn Lleakage 41.829kV 70.9in 0.59 kV in CreapageAC 70.9in 41.829kV 43.053 mm kV=:= CreapageDC 1.3 CreapageAC⋅55.969 mm kV=:= Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 42 07/21/11 The DC voltage is 80 kV between the two conductors, which implies that voltage to ground is 40 kV. The required leakage distance for a 40kV DC insulator for heavy pollution is: CreapageDC_40kV 40kV CreapageDC⋅2.239 m=:=CreapageDC_40kV 88.14 in= The leakage distance of the insulator used presently for 69kV AC in Figure 23 has only 79in leakage. Therefore, the DC line must be built with a longer insulator like S148048VX21, which has 90.3in leakage. The specification of the DC transmission line is: Tower: 69 kV wooden towers. Conductor: 470 kCM “Flicker” ACSR conductor, two (2) conductors on each tower Insulators: MacLean Composite S1 insulator S148048VX21, two (2) per tower 2.4.2 Multi-Terminal DC System Alternative 2 The feasibility of building a DC cable system instead of using overhead lines should be investigated. The major advantage is that bad weather, like ice and snow, does not affect the cables. The cable connection seems to be attractive for the Sitka-Takatz Lake Hydro run, if an access road would be built along this route, which permits the “spaced laying” of two 80 kV, land cables with 400mm2 aluminum conductor, rated 90MW in case of spaced laying. Figure 13 shows the ABB land cable. The cables can be directly buried or placed in a shallow marked ditch. The sea cables are the same as described in previously under the Hybrid System. 2.4.3 Budgetary Cost Estimate for Multi-Terminal HVDC Light Systems Table 11 gives the cost estimates for the two multi-terminal Alternative 1 and Table 12 for Alternative 2. Table 11 Cost Estimate for the Multi-Terminal HVDC Light System Alternative 1 Multi-Terminal System- DC Line, Alternative 1 Description Number of miles or number Cost per mile in $Total cost $ 80kV DC UG Land Cable- Road Access 5.0 1,000,000$ 5,000,000$ 80kV DC UG Land Cable- Tunnel 2.0 1,800,000$ 3,600,000$ 80kV DC Transmisson Line- H Frames 16.4 840,000$ 13,776,000$ 80kV DC Transmisson Line- Single Pole 50.0 420,000$ 21,000,000$ 80kV DC Submarine Cable- Duncan Canal 2 4,000,000$ 8,000,000$ 69kV AC Kake Substation and Petersburg Tap 1 2,400,000$ 2,400,000$ IGBT 80kV Converter, Filter, Transformer 4 29,013,000$ 116,052,000$ 80 kV DC Submarine Cable- Chatham Strait 41.1 1,191,120$ 48,955,032$ Total 218,783,032$ Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 43 07/21/11 Table 12 Cost Estimate for the Multi-Terminal HVDC Light System Alternative 2 Multi-Terminal System- DC Cable, Alternative 2 Description Number of miles or number Cost per mile in $Total cost $ 80kV DC UG Land Cable- Road Access 5.0 1,000,000$ 5,000,000$ 80kV DC UG Land Cable- No Road 18.4 1,800,000$ 33,120,000$ 80kV DC Transmission Line- Single Pole 50.0 420,000$ 21,000,000$ 80kV DC Submarine Cable- Duncan Canal 2 4,000,000$ 8,000,000$ 69kV AC Kake Substation and Petersburg Tap 1 2,400,000$ 2,400,000$ IGBT 80kV Converter, Filter, Transformer 4 29,013,000$ 116,052,000$ 80 kV DC Submarine Cable- Chatham Strait 41.1 1,191,120$ 48,955,032$ Total 234,527,032$ 2.5 AC transmission System with compensated submarine cable The AC transmission system will be built with 138 kV line between Petersburg and Kake, 138kV compensated submarine cable between Kake and Takatz Lake Hydro and 69kV line between Takatz Lake Hydro and Sitka. The transmission lines will be the usual single pole (Kake) or H-frames (Sitka) with wooden poles with composite suspension insulators. ABB proposed a new 138 kV submarine cable shown in Figure 16. The cable total charging current is more than 800A at 138kV, which is larger than the load current. The proper operation of the AC system requires the compensation of capacitive charging current by inductances. Figure 27 shows the connection diagram of the AC three phase version of the intertie. Figure 27 Three phase AC transmission system Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 44 07/21/11 2.5.1 Analysis of the Three Phase AC Intertie Operation The selection of the compensating reactors requires the analysis of the system operation at full load 50MW and no load or at light load 1-5 MW. Compensating reactors will be placed both at the Kake and the Takatz Lake terminals. The system one line equivalent circuit is shown in Figure 28. AC AC AC submarine Cable 138kV 41.1 mi69kV LINE 21.1 mi Sitka 22 MW 69 kV AC 138 kV LINE 44.3 mi Petersburg 50MW 138 kV AC AC Takatz Hydro 28MW Compensating reactance Compensating reactance 1234567 Figure 28 Equivalent circuit for the Three phase AC transmission system For the analysis the worst case is assumed, when Sitka and Takaz Lake Hydro supplies 50 MW to Petersburg through the submarine cable and transmission line. Therefore, Takatz Lake Hydro supplies 28MW and Sitka supplies 22MW through a 69kV line. The 50 MW, pf=0.8 load was connected to the Petersburg terminal; the 138 kV line between Petersburg and Kake is represented by a T circuit; the 138kVsubmarine cable is divided into three (3) sections and represented π circuits connected in series. A compensating reactor is connected between the phase conductor and ground at both side of the submarine cable. The 138kV/69kV transformer is represented by an ideal transformer and its leakage reactance connected in series. The Takatz Lake Hydro is represented by an ideal generator, series impedance (R and L) represents the 69 kV line between Takatz Lake and Sitka. The data used for the analysis is listed in Table 13. Table 13 Data for Operation Analysis The operation analysis calculated the voltage and current at each section. The calculation started at the Petersburg terminal. The load current was calculated first, this will be the current in section 1-2. This is followed by the calculation of the voltage at node 2 using the load current. The capacitive current was calculated using the voltage at node 2. The current between nodes 2-3 is the sum of the capacitive current and the current between nodes 1-2. This procedure has been followed to determine the voltage at each node and the current in each section. The sample calculation is shown in Appendix 1. Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 45 07/21/11 The requirement is that the voltage drop must be less than 10% at maximum load at nodes with loads, less than 15% is acceptable for the other nodes and the current must be less than the specified maximum section current, which is around 550A. The calculation was performed at full load and at no load. The compensation has been varied until acceptable results were obtained. The results at full load with 0.5H and 0.55H compensation reactance at the terminals of the submarine cable are: The results shows that the voltage drop on node 1,2, 6 and Sitka is less than 4%. The line current is less the 400A. This is a very acceptable operation condition. The result at no load with 0.4H and 0.35H compensation reactance at the two terminals of the submarine cable are: The result shows that the voltage drop is less than 2%. The line current is less the 400A. This is a very acceptable operation condition. Accordingly, the proper operation requires two adjustable reactance with inductance adjustable 0.3-0.6 H. ABB offers a 3-phase VSR at 138 kV nominal voltages with regulating range of 60-35 MVAR. Very rough price estimation for this VSR is 2-2.3 MUSD per unit in a standard design for ABB Ludvika and delivered to US port. General delivery time is in the range of Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 46 07/21/11 11-13 months after order. Of course, there would be added costs for state and local sales/use taxes, civil works, installation, local transport to sites, associated circuit breakers/switches, protection etc. 2.5.2 Budgetary Cost Estimate Three Phase AC System Table 14 gives the cost estimates for the three phase AC version of the intertie. Table 14 Cost Estimate for the AC Transmission System 138kV AC System Description Number of miles or number Cost per mile in $Total cost $ 69 KV AC Transmission Line- Double Circuit 5.0 750,000$ 3,750,000$ 69/138kV 50 MVA Substation- Bear Cove 1 138kV AC UG Land Cable- Tunnel 2.0 2,400,000$ 4,800,000$ 138kV AC HD Transmission Line- H Frames 16.4 1,200,000$ 19,680,000$ 138/69kV AC Takatz Powerhouse Conversion 1 500,000$ 500,000$ 138kV AC Circuit Breaker at Landfall-SCADA 1 1,500,000$ 1,500,000$ 138kV AC Transmission Line- Single Pole 50.0 600,000$ 30,000,000$ 138kV AC Submarine Cables- Duncan Canal 2 5,600,000$ 11,200,000$ 138kV AC Kake Substation and Petersburg Tap 1 2,600,000$ 2,600,000$ Reactance 138kV, 550A, 2 2,300,000$ 4,600,000$ 138kV AC Submarine Cable- Chatham Strait 41.1 1,494,032$ 61,404,715$ Total 140,034,715$ 2.6 Summary of the Comparison of Different Systems The cost comparison of the different systems is presented in Table 15. It can be seen that the most economical system is the three phase AC system with compensated submarine cable. Table 15 Cost Comparison of Different Systems Cost comparizion 138kV Three phase AC System 140,884,715.20$ Multi-Terminal System- DC Line, Alternative 1 218,783,032.00$ Multi-Terminal System- DC Cable, Alternative 2 234,527,032.00$ Hybrid System with 69 kV Line, Alternative 1 177,171,032.00$ Hybrid System with Land Cable, Alternative 2 217,914,032.00$ Table 15 shows that the ABB proposed three phase system with the compensated submarine cable is the most economical system. This alternative was not considered in the last study because the literature advised that AC cables longer than 30-40 miles are not advisable. Obviously, ABB experience proved the feasibility to extend the range of AC submarine cables using inductive compensation. The presented calculation clearly shows that the usual 138kV, three phase system with reactance compensated submarine cable is a technically feasible and economical solution for the Southeast Alaska intertie. Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 47 07/21/11 The market changed in the last 10 years and the cost of DC land cable and converters increased significantly. ABB proposed 50MW, 80 kV converters with an estimated cost of $35M, which means $700,000/MW or $700/kW. Another market change is that the manufacturers are not interested in building small HVDC Light or HVDC Plus systems. Indian and Chinese markets as well as the European offshore wind farms demand large, several hundred megawatt ratings for the voltage source based HVDC systems. The manufacturers are working on large IGBT based HVDC systems which can compete with the classical thyristor based HVDC and suitable to form DC networks. From a technical point of view, the HVDC Light system is superior to the classical HVDC system. The major advantages are multi-terminal operation, weak-system tolerance, black start capability, and reactive power control. The authors of this report believe that the multi- terminal approach is the technically most beneficial. Unfortunately, this system is the most expensive. The technical advantages do not compensate for the high cost. Another surprise is that the costs of land cable became significantly higher than a simple AC line cost. ABB’s attitude changed. The enclosed E mail recommends the land cable if the building of an overhead line is not permitted. The recommended three phase AC system losses per mile are the same as the losses on the rest of the 138kV Alaska system. The maintenance of the AC system is the same as the present system maintenance. The submarine cable does not need special maintenance and the compensating reactors are similar to a transformer. 3 Conclusions The investigations show that the Sitka-Kake-Petersburg intertie should be built with as a standard three phase 138kV system with 138kV reactance compensated submarine cable. All components, except for the compensating reactances, are standard well proven products. The compensating reactances are similar to a transformer. The voltage source converter based HVDC Light or HVDC Plus system has technically advantages but the technical advantages do not compensate for the high cost. The manufacturers do not recommend the HVDC Light or HVDC Plus system for 50 MW. 4 References [1] www.abb.com/hvdc [2] siemens.com Global Website [3] HVDC & SVC Light- Reference list; http://www05.abb.com/global/scot/scot267.nsf/veritydisplay/5d0bb83bb5e3a0078525 72e500540f9d/$File/HVDC%20and%20SVC%20Light%20web.pdf [4] Niel Kirby: AREVA T&D Power Electronics-HVDC & FACTS, araeva.pdf [5] HVDC Light® Power Cables.pdf, Brochure ABB’s high voltage cable unit in Sweden. www.abb.com/cables Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 48 07/21/11 [6] Leif Englund, Mark Lagerkvist, Rebati Dass:”HVDC superhighways for China, ABB Review, 14, 4/2003 [7] Michael Bahrman: “HVDC Transmission. Panel session, Atlanta Novembr 1, 2006 [8] W.Breuer,D. Povh, D. Retzmann, E. Teltsch,X. Lei: “ Role of HVDC and FACT in future Power System”; CEPSI, 2004, Shanghai. [9] M. Mohaddes, D. P. Brandt, M.M. Rashwan, K. Sadek, “Application of the Grid Power Flow Controller in a Back-to-Back Configuration”, [CIGRE Report B4-307, Session 2004] [10] Chan-Ki Kim, Young-Hun Kwon, Gilsoo Jang:”New HVDC Interaction between AC network and HVDC Shunt Reactor on Jeju Converter Station, IEEE Trans. on Power Delivery, Vol 22, No3. July, 2007 [11] Chandana Karawita, Udaya D. Annakkage: ”Multi-Infeed HVDC Interaction Studies Using Small-Signal Stability assessment”; , IEEE Trans. on Power Delivery, Vol.24, No2, April. 2009 [12] 1ZSE 954901-19_Application Buyers Guide SR_Rev Aug 2 2009, ABB WEB site [13] The Okonite Submarine Cables and Product: http://www.okonite.com/Product_Catalog.html [14] Submarine Cables and Projects: http://www.abbcables.com/sub.html 5 Bios sketches George Karady (SM'70, F'78) received BSEE and Doctor of Engineering degree in electrical engineering from Technical University of Budapest in 1952 and 1960, respectively. Dr. Karady was appointed to Salt River Project Chair Professor at Arizona State University in 1986, where he is responsible for the electrical power education and performs research in Power Electronics, High Voltage Techniques and Electric Power. Previously, he was with EBASCO Services where he served as Chief Consulting Electrical Engineer. He was Electrical Task supervisor for the Tokomak Fusion Test reactor project in Princeton. He worked for the Hydro Quebec Institute of Research as a Program manager. Between 1952- 1969 he worked for the Technical University of Budapest where he progressed from Post Doctoral Student to Deputy Department Head. Dr. Karady is a registered professional engineer in New York, New Jersey and Quebec. He is the author of more than 100 technical papers. Dr. Karady is the chairman of IEEE WG on Non-Ceramic Insulators and WG on Insulation Coordination. He is a member of the CIGRE U.S. Technical Committee. Dr. Karady served in the US National Committee of CIGRE as Vice president and secretary treasurer. In 1996 Dr. Karady received an Honorary Doctor Degree from Technical University of Budapest. Mr. Mike Carson earned a B. S. degree in electrical engineering and is a registered electrical engineer in Alaska, Washington, Oregon and California. He has over 40 years of experience in the planning, designing and engineering of transmission and distribution systems for small utilities such as cooperatives, municipalities, public utility districts and Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 49 07/21/11 government agencies. His system planning experience includes system design, preparation of long range and construction work plans, life cycle analysis of alternatives, evaluation of losses and conversion of systems to higher voltages. Mr. Carson has over 18 years of experience working on engineering projects in Alaska. He is the owner of Northstar Power Engineering and has been a resident of Southeast Alaska since 1992. Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 50 07/21/11 Appendix Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 51 07/21/11 Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 52 07/21/11 Southeast Alaska HVDC System Report 6-Draft 3-10-11.docx 53 07/21/11