Loading...
HomeMy WebLinkAboutFalse Pass Preliminary Cost Estimates for Hydropower Development Sep 2015polarconsult alaska, Inc. 1503 West 33rd Avenue, Suite 310 Anchorage, Alaska 99503-3638 .� Phone: (907) 258-2420 FAX: (907) 258-2419 M E M O R A N D U M DATE: September 13, 2015 TO: Bob Christensen, Living Systems Design, LLC FROM: Joel Groves, P.E. SUBJECT: Preliminary Project Performance and Development Cost Estimates for Unga Man Creek Hydro near False Pass, AK CC: Unga Man Creek is under consideration for hydropower development to provide electricity to the community of False Pass. Reconnaissance -level cost estimates, development schedules, and performance estimates are provided to assist in economic evaluation of the project. 1. Preliminary Estimates of Project DesijZn Parameters Preliminary estimates of project design parameters are presented in Table 1. It must be emphasized that the preliminary design parameters in Table 1 are reconnaissance - level estimates and they may change significantly as the project is studied and better information becomes available. In particular, the appropriate and feasible design flow could change significantly, which would result in a proportionate change in project installed capacity and significant changes in capacity factor, annual energy generation, and other project performance parameters. Table 1: Preliminary Design Parameters for Unga Man CrPPk Hvrlrn Prniort Design Parameter Preliminary Estimated Value Design Flow 1 12 cubic feet per second (cfs) Gross Head 200 feet (ft.) Net Head 180 ft. Penstock 2 4,600 ft. Installed Capacity 125 kilowatts (kW) Resource Capacity Factor 1 85% Annual Energy 1 936,000 kilowatt-hours (kWh) Utility Load Supplied by Hydros 86% Transmission Line 2 3,000 ft. 7.2/12.4 kilovolts (kV) Access Road z 4,600 ft. ivuLe�: 1. See Section 2 of this letter report for assumptions made to estimate design flow, capacity factor, annual energy generation and portion of utility load supplied by the hydro project. 2. Based on estimated lengths presented in Renewable Energy Resource Assessment for the Communities of Cold Bay, False Pass, and Nelson Lagoon, YourCleanEnergy, LLC. May 18, 2010. 150913-FALSEPASSCOSTMEM0.DOC POLARCONSULT LETTER REPORT PRELIMINARY PROJECT PERFORMANCE AND DEVELOPMENT COST ESTIMATES FOR UNGA MAN CREEK HYDRO 2 Preliminary Estimate of Proiect Performance 2.1. Existing Utility Load Recent False Pass electric utility load data is shown in Figure 1. In the last five years, total load at generation has ranged from approximately 450,000 to 710,000 kilowatt-hours (kWh). Peak load at generation for fiscal year (FY) 2015 was 145 kilowatts (kW).' Figure 1: Monthly kWh at Generation, FY 2011 through FY 2015 ___ - ___. 150 t Monthly kWh Gen -o- Monthly Peak Load (kW) 125 V R 0 100 OU 80,000 m IL 75 70,000 50 0 60,000 m i m 25 50,000 0 40,000 t 30,000 r c 20,000 2 10,000 0 Jan 10 Jan 11 Jan 12 Jan 13 Jan 14 Jan 15 Jan 16 Data provided by City of False Pass. The utility's hourly load data is modeled using the Alaska Village Load Calculator (AVLC).z Figure 2 presents actual monthly load data over the past five years (FY 2011 through FY 2015), average monthly load over this same time period, and the modeled monthly load using the AVLC. Table 2 presents average and modeled monthly load data for the utility. Tnklo 7• Fivc_Vanr AuararsP and Mndeled Monthly Utilitv Load at Generation Month Model Monthly kWh at Generation Actual Five Year Average Monthly kWh at Generation Jan 59,268 52,356 Feb 54,568 51,394 Mar 58,332 57,511 Apr 53,340 56,485 May 49,493 59,551 Jun 44,699 50,204 July 45,036 50,706 Aug 47,937 44,744 Sept 48,548 42,687 Oct 54,954 54,262 Nov 53,352 54,300 Dec 60,446 53,287 Annual Total 629,972 (rounded to 630,000 kWh) 627,487 1 The fiscal year runs from July 1 to June 30, so FY 2015 is July 1, 2014 through June 30, 2015. 2 The Alaska Village Electric Load Calculator, NREL/TP-500-36824, NREL, Golden Colorado, Sept. 2004. September 13, 2015 Page 2 of 8 POLARCONSULT LETTER REPORT PRELIMINARY PROJECT PERFORMANCE AND DEVELOPMENT COST ESTIMATES FOR UNGA MAN CREEK HYDRO Figure 2: Actual and Modeled Utility Load at Generation 90,000 80,000 = _. ..............70,000 _ ...........o...................._I�0 ........ _..... ..... ................. _� I `8 m 60,0 b. ............... . ...................... :....._........... 50,000 — t ?� 40,000 ° O O p-...... _GL-.....-...__._-.._.__...... _.. .—-....._.... �-........... O 30,000 ......... -. -.... ................................ :......... _._..... -......... .......... .... _................ ..... ...°...... ................_g........._........... ....... — .!......0.— .. C ? i f 20,000 --- - O Actual Monthly Load at Generation --- i - -�- Model Monthly Load at Generation 10,000 -4- 5-Year Average Actual monthly Load at Generation 0 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2.2. Hydro Generation Preliminary estimated average annual hydro project generation potential is calculated using the preliminary design parameters listed in Table 1 and estimated average daily discharge at Unga Man Creek based on the hydrology record for Russell Creek near Cold Bay scaled by relative drainage basin areas to Unga Man Creek .3 Water availability for hydropower generation assumes a five cubic feet per second (cfs) in -stream flow reservation to accommodate fish habitat that may exist along the project bypass reach. The need for and amount of in -stream flow reservation would be determined during the permitting process. Estimated daily flow and available project flow is shown in Figure 3. Figure 3: Preliminary Estimate of Average Daily and Available Project Flow in Unga Man Creek 3 Preliminary estimated hydrology for Unga Man Creek is discussed in Preliminary Hydrology Estimate for Hydropower Development at Unga Man and Waterfall Creeks near False Pass, AK. Letter Report, Polarconsult Alaska, Inc. September 11, 2015. September 13, 2015 Page 3 of 8 POLARCONSULT LETTER REPORT PRELIMINARY PROJECT PERFORMANCE AND DEVELOPMENT COST ESTIMATES FOR UNGA MAN CREEK HYDRO 2.3 Hydro Project Performance Daily utility load data described in Section 2.1 is compared against daily hydro generation capability in Section 2.34 to estimate how much of the utility's load the hydro can be expected to carry. A basic generation dispatch model is used to determine which of the utility's generation plants (diesel and/or hydro) would be used to meet system load on a daily basis. The model assumes that the hydro is governed with a 20 kW load bank, and that the diesel and hydro plants have an integrated supervisory control and data acquisition (SCADA) system that supports automated switching and paralleling. The SCADA would make dispatch decisions on a continuous basis based on changing utility load and water availability. Since only daily data is available for analysis, the following dispatch logic is used in the generation dispatch model to approximate actual SCADA dispatch decisions: 1. On days when the available hydro capacity exceeds the utility peak load by more than 20 kW (assumed load bank governor capacity), the hydro is assumed to carry 100% of utility load with the diesel plant turned off for the entire day. 2. On days when the available hydro capacity is more than the peak load by less than 20 kW, the diesel plant is assumed to operate for two hours with the smallest gen-set loaded at 40% of its capacity. For the False Pass diesel plant, this base diesel loading is approximately 50 kW. 3. On days when the available hydro capacity is less than 100% of the daily peak load but greater than daily average load, the diesel plant is assumed to operate for 12 hours with the smallest gen-set running at 40%. 4. On days when the available hydro capacity is less than the daily average load, the diesel plant is assumed to operate all day, with the smallest gen-set running at 40% or as - needed to meet utility demand. Preliminary estimated performance of the Unga Man Creek hydro is summarized in Table 3. Table 3: Preliminary Estimated Performance for Unga Man Creek Hydro Project Parameter Estimated Value 2 Hydro Generation Used to Supply Utility Load 540,000 kWh (58%) Hydro Generation to Load Bank Governor 1 175,000 kWh (18%) Hydro Generation not Used (Available for Interruptible Loads) 221,000 kWh (24%) Total Hydro Energy Generation 936,000 kWh (100%) Utility Load Supplied by Hydro Plant 540,000 kWh (86%) Utility Load Supplied by Diesel Plant 90,000 kWh (14%) Total Utility Load 630,000 kWh (100%) Percentage of Time All Diesels are turned off 73% 1. Load bank governor size assumed at zU Kw. Joao DanK Como De urea for Spilt a Ui weLcl ncaui �. 2. Model results have been rounded to nearest 1,000. 4 Section 2.3 only provides an annualized summary of hydrology statistics. Estimated hydro performance is calculated using the actual daily flow records for Russell Creek, as adjusted to the Unga Man basin, over the 25-year period of record. September 13, 2015 Page 4 of 8 PoLAxcomsocrLcTrsx RcpoxT PRELIMINARY PROJECT PERFORMANCE AND DEVELOPMENT COST ESTIMATES FOR UNGA MAN CREEK HYDRO Estimated hydro performance, based on Russell Creek hydrology and model utility load, is presented in Figure 4. Annual performance for atypical year (2OO7)|sshown inFigure S. Figmne4: Estimated Hydro Project Performance, 1996 to2015 zso mo zam zzo zzn zoo yu � oo � rn � so 50 40 yo Excess Hydro, Energy Available ............. Hydro to Load Bank Governor ao I= Utility Load Met by Diesel ME Utility Load Met by Hydro zo —Total Utility Load o ENNENNEMEM zyya 1997 zoou znyy 2000 aooz zooz uooa zoo^ zoos a000 zoor zoou uooy aozo zozz zozz 2013 2014 2015 zozs Figure 5: Estimated Hydro Project Performance in a Typical Year (2007) POLARCONSULT LETTER REPORT PRELIMINARY PROJECT PERFORMANCE AND DEVELOPMENT COST ESTIMATES FOR UNGA MAN CREEK HYDRO 3 Development Schedule and Cost Developing the hydro project would occur in the following stages: 1. Feasibility study. 2. Design and permitting. 3. Construction. Preliminary estimated schedule and cost for these steps is summarized in Table 4. Narrative of the purpose and effort involved in each step, and basis for the estimated schedule and cost, follow. r.. l.l., n. 1) ia..,c., m, rc+;mn+arl CrharlulP and Rudget for Proiect Development Development Stage Schedule Budget Feasibility Study 1 to 2 years $170,000 to $270,000 Design and Permitting 1 to 3 years $250,000 to $500,000 Construction 1 to 2 years $4,000,000 Start-up 2019 - 2023 $4,430,000 to $4,770,000 3.1 Feasibility Study Feasibility study phase consists of a comprehensive review of technical, regulatory, financial, and environmental issues pertaining to the project to determine if it is feasible. The study would include targeted field work and data collection to fill in critical data gaps including: - Topographic surveys to measure available project head. - Field work to identify probable locations of project features. - Hydrology studies to determine availability of water flow. - Fisheries studies / agency consultations to determine need for and to quantify any restrictions on water diversion to protect fish habitat. - Preliminary wetlands inventory to quantify probable wetland impacts Feasibility study schedule is driven by the need to collect a minimum one year of stream flow data on Unga Man Creek to begin characterizing the hydrology. The feasibility study results are as good as the data fed into the feasibility analysis. The budgetary range for the feasibility study covers a range of data collection intensity and quality. There is some discretion in how much money can justifiably be spent collecting data at this stage of project development. Typically, an increased budget in the feasibility stage offsets costs in the design / permitting phase. 3.2 Design and Permitting The scope, budget, and schedule for the design and permitting phase of project development will depend on the outcome of the feasibility study. Planning estimates are provided. 3.2.1 Scope Design and permitting typically are conducted in tandem as regulatory agencies need design information to evaluate the project's permit terms and conditions, and the design process requires well-defined permit terms and conditions to complete the project design. Permitting scope includes working with regulatory agencies to obtain all major permits needed to construct and operate the project. Typically, these include the following major permits: September 13, 2015 Page 6 of 8 POLARCONSULT LETTER REPORT PRELIMINARY PROJECT PERFORMANCE AND DEVELOPMENT COST ESTIMATES FOR UNGA MAN CREEK HYDRO - FERC Declaration of Intention to confirm jurisdictional status - Land easements or leases - Wetlands delineation and permitting (U.S. Army Corps of Engineers) - Cultural resources survey (ADNR SHPO) - Water Use Permit / Water Rights (ADNR DMLW) - Fish Habitat Permit (ADFG) Design scope includes developing engineering plans and specifications suitable for constructing the project. Design (and/or permitting) may include the following additional or continuing data collection efforts: - Detailed topographic survey for project design - Geotechnical investigations for diversion structure, powerhouse, access roads, power line extension. - Continuing stream gauging to further define resource availability and support water rights application and fish habitat permit - Fisheries surveys to support fish habitat permit 3.2.2 Budget and Schedule The budget and schedule ranges covers probable complexity of the resource issues. If resource agencies require extensive field studies to address resource questions or support permitting decisions, these studies will increase the cost and time required to complete project permitting and design. 3.3 Construction At this time, there is limited available technical information to form a detailed cost estimate for the project. Instead, recent cost data for generally similar hydro projects is used to provide a realistic planning budget for project construction. 3.3.1 Construction Budget Construction of remote Alaska hydro projects in the size class proposed for False Pass at Unga Man Creek has been costing in the range of $20,000 to $30,000 per kW. Proximity of False Pass to local marine transport / shipping routes, proximity of the project site to existing community roads and the existing electric distribution system, and apparent easy terrain for construction of the access road and penstock installation are all factors that suggest a relatively lower project cost. Preliminary review of the creek suggests the diversion structure will be founded on alluvium with no bedrock present and that the creek experiences significant flood events that the diversion and tailrace must be designed to withstand. Initial field data indicates presence of anadromous fish in the bypass reach and potentially at the diversion site, which would require provisions for fish passage and maintenance of fish flows at the diversion structure. These factors suggest a relatively higher project cost. Based on preliminary information, it is recommended that False Pass budget $25,000 per kW with a 30% contingency at this stage of project development. For a 125 kW project at Unga Man Creek, the preliminary budget estimate for construction is $4,000,000. September 13, 2015 Page 7 of 8 POLARCONSULT LETTER REPORT PRELIMINARY PROJECT PERFORMANCE AND DEVELOPMENT COST ESTIMATES FOR UNGA MAN CREEK HYDRO 3.3.2 Construction Schedule Available data suggests the project could be built by a qualified and experienced contractor in a single construction season. As is typical of remote Alaska projects, this will require careful planning and management to procure necessary construction materials and equipment for a single mobilization. Depending on the availability of suitably qualified local labor, it may be preferable for the City to build the project under force account. Force account helps keep lalior wages in the community, and also enhances the community's familiarly with the hydro and the skills necessary to maintain it for the long term. Depending on the size of the local labor force, force account construction may take an additional season. - September 13, 2015 Page 8 of 8