HomeMy WebLinkAboutAmbler, Shungnak, and Noatak Photovoltaic Location and Feasibility Study Summary - Aug 2010 - REF Grant 2195412Ambler, Shungnak, and Noatak
Photovoltaic Location and Feasibility Study Summary
Prepared for
Alaska Village Electric Cooperative, Inc.
4831 Eagle St.
Anchorage, AK 99503
Prepared by
Solstice Alaska Consulting, Inc
11760 Woodbourne Drive
Anchorage, Alaska 99516
And
Solar Wind Consultants
915 30{h Avenue
Suite 229
Fairbanks, AK 99701
August 2010
Purpose of Report
In 2009, the Alaska Village Electric Cooperative (AVEC) applied for separate Alaska Energy Authority
(AEA) Renewable Energy Grants to construct photovoltaic (PV) solar systems in Ambler, Shungnak, and
Noatak. AEA awarded AVEC the funding to study and design one project in Ambler, Shungnak, or
Noatak. After discussions, it was determined that solar siting and feasibility studies would be conducted
in the three villages.
The purpose of this report is to provide a summary of the solar siting studies in Ambler, Shungnak, and
Noatak. The information is presented to AVEC and AEA to assist in determining how to move forward
with these solar projects.
Background
Existing Power Issues
Currently, diesel -fuel power generation is the only source of electricity in these communities. In
general, the cost of fuel is affected by two variables: the price of oil and the cost of delivery. The high
cost of fuel transportation is the primary factor behind high fuel delivery costs in Ambler, Shungnak, and
Noatak. In 2009, Ambler, Shungnak, and Noatak had the third, second, and first highest cost of
delivered fuel of all AVEC communities. Much of the fuel for Ambler and Shungnak must be flown in
because the Kobuk River is often too low to accommodate fuel barges. The Noatak River changed
course in the mid-1990s and since then all deliveries of fuel to Noatak have been by air. Air deliveries
are also complicated by a periodic shortage of aircraft that are equipped to deliver fuel.. As a result fuel
delivery costs are high. In 2009 in Ambler, 12 out of the 15 fuel deliveries were made by air. In
Shungnak in 2009, 25 of the 28 fuel deliveries were made by air. In Noatak in 2009, all 28 of the fuel
deliveries were by air.
The average AVEC delivered fuel costs in 2009 to Ambler, Shungnak, and Noatak were $3.79/gallon,
$4.35/gallon, and $6.41/gallon respectively. In 2008, average delivered fuel costs were significantly
higher in Ambler and Shungnak; $6.13/gallon in Ambler and $5.55/gallon in Shungnak.
Although the cost of energy is high, Ambler, Shungnak, and Noatak residents use more energy than most
AVEC villages. Ambler's average residential consumption of energy is above the average consumption of
all AVEC villages most years, according to AVEC records. Shungnak and Noatak's average residential
energy consumption has been above the average consumption of all AVEC villages since 1992. It is
unknown why these communities consume more power than other communities, but it is suspected
that their high latitude position, and darker, colder winters contribute to this electric usage.
Potential Renewable Energy Solutions
AVEC decided to explore solar energy as a possible energy source after considering other options. Wind
power is not a feasible solution, since the wind resource in this area is very low. Biomass (wood) has
been suggested as an alternative heating source for all the villages; however, its use for energy
production is unproven. Currently, AVEC and NANA Regional Native Corporation are exploring
hydroelectric options near Ambler and Shungnak; however, it will be years before it is determined
whether hydropower is a feasible alternative energy source.
Ambler, Shungnak, and Nootak
PV Location and Feasibility Study Summary
Page 2
Study Methods
AVEC hired Remote Power, Inc. to study the solar energy potential and possible locations for PV panels
in Ambler, Shungnak, and Noatak. Remote Power, using the Solar Pathfinder" (SP) site analysis tool,
first generated sunpath diagrams from digital photos taken at each site. The sunpath diagrams were
then used to determine solar positions and shading effects of landscape features on potential solar
energy systems at each location. These images were then analyzed using Solar Pathfinder Assistant;"
Version 4.0 (SPA) software to determine the most appropriate location for PV panels. Production
estimates and fuel savings were then estimated through analysis of these images and an estimation of
the effect the surrounding landscape would have on a potential PV array.
Remote Power considered other issues associated with maintaining PV panels in cold, high latitude
environments. Remote Power studied fixing the solar array tilt to keep snow from accumulating on the
panels and inhibiting power production versus mounting panels on adjustable racks to maintain an
optimum angle for year-round power production, especially in the late spring to early fall. Remote
Power also investigated locations and options for PV panels considering the potential for vandalism of
the solar arrays in the villages.
Features in Common to All PV Options / General Considerations
The PV arrays at that would be installed in the three villages would consist of 175-watt monocrystalline
cell modules manufactured by Sharp Solar. The inverter that would be used with the PV arrays is
manufactured by Fronius and would produce 277 vac 3-phase power. Unless otherwise noted, the tilt
angle of each array, adjusted twice annually, would be 52 degrees from May through September and 90
degrees the remainder of the year. As much as possible, all trees or other obstructions to sunlight
would be removed to ensure optimum system performance.
The ideal foundations for PV arrays in Ambler, Shungnak, and Noatak have not been determined.
Typically, foundations for unheated structures on ice rich and permanently frozen soils are constructed
to ensure that the active layer is contained in a thaw -stable material such as gravel or that the load is
supported by the frozen soil under the active layer. Foundations used to support the PV arrays in this
study are expected to be installed on large quantities of non -frost susceptible soil such as gravel. Since
gravel may not locally available in some communities, the shipping costs for this material could add
substantially to overall project cost. The amount of gravel would be dependent upon the area of the
foundation and the depth of the active layer of the soil that would have to be removed.
If a large Triodetic foundation, a stiff foundation designed to resist twisting and buckling caused by
heaving ground, were considered for this site, further research should be conducted to determine the
capabilities and limitations of the Triodetic foundation. Additionally, ballast material added to the
foundation or some sort of anchoring mechanism would be necessary to keep the solar array from
blowing over or shifting in the event of high winds in the area.
An alternative installation option would be to drive piles into the permafrost at a depth substantial
enough to resist jacking (and creep settlement) and install the array on the piles. Pile depths depend on
the conditions of the sail. A geotechnical report should be conducted for all foundation options to
determine active layer depth and soil composition.
Ambler, Shungnak, and Noatak
PV Location and Feasibility Study Summary
Page 3
Connection to the existing AVEC power system was investigated for this study. There was concern that
under certain conditions a large PV array could back feed power into the existing diesel generators,
providing more power than the system might require, and causing a power reversal fault. As a safety
precaution, a "reverse power relay" would be installed to prevent this from occurring. Reverse power
relays are standard equipment on grid tie generators. On a multi generator system, the relays enable
the generator that is being over -powered to disconnect from the grid. Another option to handle excess
power would be to shunt the power into a storage battery or use it in a recovered heat system.
Amb-ler Solar Project Options
Four solar project options were investigated in Ambler, as described below. Table 1 summarizes the
findings.
Ambler Option #1 (Schwatka Street Option)
Ambler Solar Site Option #1 is located across Schwatka Street, just southwest of the existing AVEC
power plant facility (Figure 1). This lot slopes to the northwest and is currently covered with a mixture
of densely growing black spruce and willows.' A PV array at this site would consist of 180 PV modules
rack mounted in a single long row running east to west. The relatively narrow east -west dimension of
the property would limit the array size to 30.5kW instead of the preferred 50.4 kW size.
Figure 1. Ambler PV Option #1 location.
' Because of dense vegetation growth, it was difficult to obtain a useful SP image of the site; however, SP images
were taken from less obstructed areas adjacent to the site, and digital photographs were taken of the surrounding
area to determine the project configuration and potential production.
Ambler, Shungnak, and Nootak
PV Location and Feasibility Study Summary
Page 4
Power Estimate/Fuel Savings
The annual power production of Ambler Option #1, estimated based on the installation of a 31.5 kW
array, would be 24,982 kWh (with shading), and the estimated fuel savings would be approximately
1,850 gallons annually.z At the 2008 average cost of delivered fuel to Ambler ($6.13/gallon), the annual
savings associated with this option would be about $11,332. At the 2009 average cost of delivered fuel
to Ambler ($3.79/gallon), the annual savings associated with this option would be approximately $7,012.
Installation Cost
Ambler Option #1 would cost between $346,500 and $378,000 (assuming $11-12%watt). This cost does
not include connection to the existing power lines or fencing around the array.
Payback Period
Based on a cost of between $346,500 and $378,000 and 2009 average fuel costs, it is expected that it
would take between 49 and 54 years to pay for Ambler PV Option 41. At a higher fuel cost, for example
using 2008 average Ambler delivered fuel costs, it would take between 31 and 33 years to pay for the
Ambler PV Option #1.3
Option Analysis
Ambler Option #1 was dismissed from further consideration. Although this option is near the existing
AVEC power plant and has relatively low transmission costs and overall installation costs, the practical
array size is limited and the potential for shading is high. The production from this option would only
displace about 1,850 gallons of diesel annually and would not result in considerable cost savings.
Ambler Option #2 (Old Sewage Lagoon Option)
Ambler Solar Site Option #2 is located at the old sewage lagoon approximately 0.25 miles northwest of
the AVEC power plant. The lagoon, which is scheduled to be closed and filled, would be available for
development after the summer of 2010. A PV array at this site would consist of a 50.4 kW south -facing
array of 180 modules rack mounted in a single long row running east to west.
z Based on 13.5 kWh/gallon
3 Simple payback calculation: Payback Perlod=Initial Cost/Annual Cost Savings
Ambler, Shungnok, and Noatok
PV Location and Feasibility Study Summary
Page 5
Figure 2. Ambler PV Option #2 location
Power Estimate/Fuel Savings
The annual power production of Ambler Option #2, estimated on the installation of a 50.4 kW array,
would be approximately 44,623 kWh (with shading), and the estimated fuel savings would be
approximately 3,305 gallons annually.° At the 2008 average delivered fuel price, the annual savings
associated with this option would be approximately $20,245. At the 2009 average delivered fuel price,
the annual savings associated with this option would be approximately $12,526,
Installation Cost
Ambler Option #2 would cost between $503,600 and $554,000 (assuming $9-10/watt). This cost
includes $50,000 for connecting into the existing power lines, but it does not include the cost of fencing
the array. It is likely that some cost saving would be realized because after the lagoon site is filled and
abandoned, it will be better prepared for installation of the array than other sites where site work would
be required.
Payback Period
Based on a cost of between $503,600 and $554,000 and 2009 average Ambler delivered fuel costs, it is
expected that it would take between 40 and 44 years to pay for Ambler PV Option ##2. However, at 2008
fuel costs, it would take between 25 and 27 years to pay for the Ambler PV Option #2 .5
Option Analysis
Although this option had the best solar access and energy production capability in Ambler, Option #2
was dismissed from further consideration primarily because of installation cost and the potential for
vandalism at the site.
4 Based on 13.5 kWh/gallon
5 Simple payback calculation Payback Period=Initial Cost/Annual Cost Savings
Ambler, Shungnak, and Nootak
PV Location and Feasibility Study Summary
Page 6
Ambler Option #3 (AVEC Facility Option)
Ambler Solar Site Option #3 is located within the AVEC power plant facility. This option includes placing
a south -facing 10.5 kW array consisting of 60 modules northwest of the fuel storage tanks. The location
of the tanks and generator buildings on this property would cause considerable shading of the array.
Power Estimate/Fuel Savings
The annual power production of Ambler Option #3, estimated on the installation of a 10.5 kW array and
considerable shading at the site, would be approximately 7,583 kWh, and the estimated fuel savings
would be approximately 562 gallons annually.6
Installation Cost
Ambler Option #3 would cost between $115,500 and $126,000 (assuming $11-12/watt). Since this
option is located within the existing and fenced AV1 C facility, there are no costs associated with fencing
or connection into the existing power system. Using the 2008 average cost of delivered fuel to Ambler,
the annual saving associated with this option would be about $3,442. Using the 2009 average cost of
delivered fuel to Ambler, the annual savings associated with this option would be approximately $2,130.
Figure 3. Ambler PV Option #3 location
Payback Period
Based on a cost of between $115,500 and $126,000 and 2009 average fuel costs, it is expected that it
would take between 54 and 53 years to pay for Ambler PV Option #3. At 2008 fuel costs, it would take
between 34 and 37 years to pay for the Ambler PV Option #3.'
6 Based on 135 kWh/gallon
7 Simple payback calculation Payback Period=Initial Cost/Annual Cost Savings
Ambler, Shungnak, and Noatak
PV Location and Feasibility Study Summary
Page 7
Option Analysis
Ambler Option #3 was dismissed from further consideration because of the low power output due to
significant shading from the fuel tanks. Although this option had few costs associated with securing the
array and connecting to the existing power system, the annual production from this option would
only displace about 562 gallons of diesel annually and would not result in considerable cost
savings.
Ambler Option ##4 (AVEC Tank Top/Power Plant Roof Option)
Placing a PV array on top of fuel storage tanks and on top of the power plant modules within the AVEC
facility was considered. While some vandalism concerns and shading concerns would be alleviated at
this location, installation on top of the tanks would require adequate ballast or weight to secure the
panels and tanks when the tanks are not full and winds are strong. Adding ballast could require
excavation and the construction of a concrete and steel foundation. The soils in this location are
seasonally frozen, resulting in movement throughout the year, which causes additional complications.
Due to these factors, this option was not investigated in more detail.
Installing PV panels on top of the AVEC generators modules was considered. To avoid the shading
associated with the generator exhaust, the PV panels would only be suited on the southernmost
modules. Large tracking arrays could not be installed because they could not turn without encountering
the exhaust stacks. Because of these issues, an array on top of the power plant was not considered
further.
Table 1. Summary Photovoltaic Options in Ambler
Option
Summary
Annual
Annual
Annual
Installation
Years to
Description
Power
Fuel
Cost
Cost
Payback
Estimate
Savings
Savings"
(kWh)
(gallons)
Ambler Option #1
31.5 kW array
28,032
1,850
$7,012
$346,500-
Simple:
across road from
$378,000
49-54
AVEC power plant
Ambler Option #2
50.4 kW array at the
49,940
3,305
$12,526
$503,600-
Simple:
old sewage lagoon
$554,000
40-44
Ambler Option #3
10.kW array on the
8,942
562
$2,130
$115,500-
Simple:
northwest side of
$126,000
54-59
tanks on AVEC
property
Ambler Option #4
PV array sited atop
Not pursued further due to wind, foundation, and generator
AVEC fuel tanks or
exhaust issues
power plant
" Using 2009 average cost of fuel delivered to Ambler=$3.79/gallon
Ambler, Shungnak, and Noatak
PV Location and Feasibility Study Summary
Page 8
Shungnak Solar Project Options
Two solar project options were investigated in Shungnak as described below. Table 2 summarizes the
findings.
Shungnak Option #1. (North of AVEC Site-52° Tilt)
Shungnak Option #1 would be located on the lot leased by AVEC just northwest of the Shungnak power
plant (Figure 4). The lot consists of permafrost sails with scattered black spruce. This option includes
installing a 50.4 kW array of 288 PV modules. The array would face true south.
Figure 4. Shungnak PV Option #1 and #2 locations.
Power Estimate/Fuel Savings
The annual power production of Shungnak Option #1, estimated on the installation of a 50.4 kW array
and some shading, would be approximately 46,588 kWh, and the estimated fuel savings would be
approximately 3,451 gallons annually." At the average 2008 delivered fuel cost to Shungnak
($5.55/gallon), the annual savings associated with this option would be approximately $19,169. At the
average 2009 delivered fuel cost to Shungnak ($4.35/gallon), the annual savings associated with this
option would be approximately $15,012.
Installation Cost
Shungnak Option #1 would cost between $554,400 and $604,800 (assuming $11-12/watt). These costs
do not include fencing or connection into the existing power system.
Payback Period
Based on a cost of between $554,400 and $604,800 and Shungnak's 2009 average delivered fuel costs, it
is expected that it would take between 37 and 40 years to pay for Shungnak PV Option #1. At 2008 fuel
costs, it would take between 29 and 32 years to pay for the Shungnak PV Option #1.9
" Based on 13.5 kWh/gallon
9 Simple payback calculation Payback Period=Initial Cost/Annual Cost Savings
Ambler, Shungnak, and Noatak
PV Location and Feasibility Study Summary
Page 9
Option Analysis
Although this option is close to the AVEC power plan and the cost associated with connecting to the
local system would be low, this option was dismissed from further consideration primarily because of
high installation cost. In addition, buildings and other obstructions in the vicinity of this option could
lower power output during the winter months.
Shungnak Option #2 (North of AVEC Site-340 Tilt)
Shungnak Option #2 is identical to Shungnak Option #1 (a 50.4 kW array of 288 PV modules located just
northwest of the AVEC power plant, Figure 4), except that that the tilt of the array is different. Option
#2 tilt angle of the array would be 34 degrees from May through September and 90 degrees the
remainder of the year.10
Power Estimate/Fuel Savings
Changing the summer tilt angle to 34 degrees shows approximately a 2.5% increase in power production
compared to the 90/52 tilt scenario. The annual power production of Shungnak Option #2 would be
approximately 47,731 kWh, and the estimated fuel savings would be approximately 3,536 gallons
annually.1' At the average 2008 delivered fuel cost to Shungnak, the annual savings associated with this
option would be approximately $19,641. At the average 2009 delivered fuel costs to Shungnak, the
annual savings associated with this option would be approximately $15,382.
Installation Cost
It is assumed that the Shungnak Option #2 would cost the same as the Shungnak Option #1; between
$554,400 and $604,800 (assuming $11-12/watt), These costs do not include fencing or connection into
the existing power system.
Payback Period
At 2009 average Shungnak delivered fuel costs, is expected that it would take between 36 and 39 years
to pay for Shungnak PV Option #2; about 1 year less than the Shungnak Option #1. At 2008 fuel costs, it
would take between 28 and 31 years to pay for the Shungnak PV Option #2. 12
Option Analysis
Shungnak Option #2 is a better solar alternative than Option #1. Changing the tilt of the array to 34
degrees May through September would result in about 2.5% more energy production and additional
annual fuel use savings compared to Option #1. This option was dismissed from further consideration,
however, due to the high installation costs compared to the relatively low output.
Another option investigated at this site included mounting the array 16 feet above ground level.
Although the probability of any shading from obstructions would be minimized by this option, the
additional cost and technical issues of raising the array indicate that this option should not be
considered further.
10 The modeling feature that allowed angle and azimuth optimization was not available during the Ambler and
Noatak site visits.
11 Based on 13.5 kWh/gallon
12 Simple payback calculation Payback Period=Initial Cost/Annual Cost Savings
Ambler, Shungnak, and Noatak
PV Location and Feasibility Study Summary
Page 10
Shungnak Option #3 (AVEC Tank Top/Power Plant Roof Option)
Shungnak Option #3 includes installing PV panels either on top of the AVEC fuel tanks or power plant
modules. Although this option alleviates security and vandalism issues, it would not be a feasible
solution for lowering or maintaining energy costs in Shungnak. Additional costs and technical issues
associated with wind and exhaust shading indicate that this option should not be considered further.
Table 2. Summary Photovoltaic Options in Shungnak
Option
Summary
Annual
Annual
Annual
Installation
Years to
Description
Power
Fuel
Cost
Cost
Payback
Estimate
Savings
Savings
(kWh)
(gallons)
A
Shungnak Option #1
50.4 kW array just
46,588
3,451
$15,012
$554,400-
Simple:
northeast of the
$604,800
37-40
AVEC facility with
a 90/52 tilt
Shungnak Option #2
50.4 kW array just
47,731
3,536
$15,382
$554,400-
Simple;
northeast of the
$604,800
36-39
AVEC facility with
a 90/34tiIt
Shungnak Option #3
PV array sited atop
Not pursued further due to wind, foundation, and generator
AVEC fuel tanks or
exhaust issues
power plant
A Using 2009 average cost of fuel delivered to Shungnak=$4.35/gallon
Noatak Solar Project Options
Two solar project options were investigated in Noatak as described below. Table 3 summarizes the
findings.
Noatak PV Option #1 (Riverbank Option)
Noatak Option #1 would be located on a gravel all -terrain vehicle trail between the existing AVEC power
plant and the Noatak River (Figure 5). This option includes installing a 50.4 kW array of 288 modules.
Because of site constraints (the tank farm is located to the west and the river is located to the east), the
array would face east toward the river.
Pourer Estimate/Fuel Savings
The annual power production of Noatak Option #1, estimated on the installation of a 50.4 kW array and
some shading, would be approximately 33,144 kWh, and the estimated fuel savings would be
approximately 2,455 gallons annually.13 At the 2008 average fuel delivery costs to Noatak
($6.22/gallon), the annual savings associated with this option would be about $15,282. At 2009 average
fuel delivery costs to Noatak ($6.41/gallon), the annual savings associated with this option would be
about $15,737.
13 Based on 13.5 kWh/gallon
Ambler, Shungnak, and Noatak
PV Location and Feasibility Study Summary
Page 11
Figure 5. Noatak Option #1 location
Installation Cost
Noatak Option #1 would cost between $554,400 and $604,800 (assuming $11-12/watt). These costs do
not include fencing or connection into the existing power system.
Payback Period
Based on a cost of between $554,400 and $604,800 and Noatak's 2009 average delivered fuel costs, it is
expected that it would take between 35-38 years to pay for Noatak PV Option #1. At 2008 fuel costs, it
would take between 36 and 40 years to pay for the Noatak PV Option #1. 14
Option Analysis
Noatak Option #1 was dismissed from further consideration because the riverfront site has significant
shading from the western sun, which significantly impacts the production of the system, fuel savings,
and system payback. In addition, although this location is near the existing AVEC facility, AVEC is
planning to move the power plant and tank farm away from the Noatak River, which is prone to erosion
in this area.
Another 50.4 kW PV array option considered at this site included installing 16 separate pole mounted
sub -arrays in a row along the riverfront. Each subarray would face south (instead of east) and would be
separated by 20 feet. Because this configuration would result in most of the sub -arrays being
significantly shaded by another subarray part of the day, this option would produce less power than an
east -facing array. This option was omitted from further consideration because shading significantly
limited power production.
14 Simple payback calculation Simple payback calculation
Ambler, Shungnak, and Noatak
PV Location and Feasibility Study Summary
Page 12
Noatak PV Option #2 (Near School Option)
Noatak Option #2 would be located on property west of the village and adjacent to the newly
constructed school. The lot consists of permafrost soils with occasional scrub spruce trees among the
tussocks (Figure 6). The array would be installed at a new AVEC power plant and bulk fuel facility, which
is being planned by AVEC and would be constructed once funding is acquired. Although the array was
originally proposed on the north side of the future AVEC compound, Option #2 would place the array on
the south side of the compound (Figure 7). This option includes installing a 50.4 kW array of 288
modules.
Power Estimate/Fuel Savings
The annual power production of Noatak Option #2, estimated on the installation of a 50.4 kW array and
some shading, would be approximately 46,588 kWh and the estimated fuel savings would be
approximately 3,573 gallons annually. At 2008 average fuel delivery costs to Noatak, the annual savings
would be approximately $22,241. At 2009 average fuel delivery costs to Noatak, the annual savings
would be about $22,903.
Installation Cost
Noatak Option #2 would cost between $554,400 and $604,800 (assuming $11-12/watt). These costs do
not include fencing or connection into the existing power system.
Payback PeriodBased on a cost of between $554,400 and $604,900 and Noatak's 2009 average delivered
fuel costs, it is expected that it would take between 24 to 26 years to pay for Noatak PV Option #2. At
2008 fuel costs, it would take between 25 and 27 years to pay for the Noatak PV Option #2. is
Option Analysis
Out of all the options studied in this report, Noatak Option #2 has the highest power estimate and fuel
savings. Using both 2009 and 2009 average delivered fuel costs to Noatak, this option has the best
annual savings and payback. However, this option is not feasible until the new AVEC facility is installed
in Noatak. It is recommended that this option be considered in the future, once funding has been
obtained for the new power plant and tank farm.
15 Simple payback calculation Simple payback calculation
Ambler, Shungnak, and Noatak
PV Location and Feasibility Study Summary
Page 13
Figure 6. Noatak Option #2 location
Suggested Solar Farm and
Site Dispensing
r ►
Facility
r �
_ S l o ::
tw FA*
Figure 7. Noatak PV Option #2 layout
Ambler, Shungnak, and Noatak
PV Location and Feasibility Study Summary
Page 14
Noatak PV Option #3 (Existing AVEC Tank Top/Power Plant Roof Option)
A PV array was considered on top of fuel storage tanks and on top of the power plant modules within
the currently existing AVEC facility. Mounting arrays on the fuel storage tanks was determined to be
impractical because the tanks are close to eroding into the Noatak River and will likely be moved in the
near future. Generator exhaust stacks would keep PV tracking systems mounted on the power plant
from working correctly. In addition, exhaust could shade the panels and limit power production. This
option was not investigated in more detail because it is likely that the power plant and tank farm will be
moved in the future, and it would be difficult and expensive to move solar arrays after they have been
installed.
Noatak PV Option #4 (New AVEC Tank Top/Power Plant Roof Option)
Noatak Option #4 consists of incorporating a PV array into the planned new power plant modules. This
option would be designed in detail once funding is acquired for the new facility near the school. The
overall design and placement of the power plant would consider the solar opportunities at this site. A
south facing array on the side of the modules, instead of the top, could be incorporated into the design.
Although no detailed analysis of this option was completed, it is likely that a 17 kWh (a 95 panel array)
could be installed. It is recommended that this option be considered in the future, once funding has
been obtained for the new power plant and tank farm.
Table 2, Summary Photovoltaic Options in Noatak
Option
Summary
Annual
Annual
Annual
Installation
Years to
Description
Power
Fuel
Cost
Cost
Payback
Estimate
Savings
Savings a
(kWh)
(gallons)
Noatak Option 91
50.4 kW east-
33,144
2,455
$15,737
$554,400-
35-38
facing array along
$604,800
the Noatak
riverbank
Noatak Option 42
50.4 kW array at
46,588
3,573
$22,903
$554,400-
24-26
the planned AVEC
$604,800
facility near the
new school
Noatak Option 43
PV array sited atop
Not pursued further due to wind, foundation, and generator
existing AVEC fuel
exhaust issues
tanks or power
plant
Noatak Option #4
PV array sited atop
Recommend option be considered in the future, once funding
new AVEC fuel
has been obtained forthe a power plant and tank farm
tanks or power
plant
A Using 2009 average cost of fuel delivered to Noatak=$6.41/gallon
Conclusions
The cost of delivered fuel in Ambler, Shungnak, and Noatak is higher than in any other AVEC community.
The high costs are associated with having to fly fuel in because the rivers are too low to accommodate
Ambler, Shungnak, and Noatak
PV Location and Feasibility Study Summary
Page 15
barges. Renewable energy options in these communities are limited; however, solar energy may be a
good alternative. Most PV options considered in this study have high installation costs and do not
produce enough power to justify further planning or design. However, based on the expected solar
output, gallons of fuel saved, and the high cost of delivered fuel in Noatak, it is recommended that PV
options associated with the new power plant be studied in more detail. These options should be
investigated once funding for the new power plant and tank farm is obtained.
Although PV has a relatively high first cost on a per kilowatt basis, PV has the lowest maintenance and
repair costs of any power generation scheme. In addition, PV inverters have 10 to 20 year warranties,
and most crystalline PV modules come with a standard 25-year warranty. Considering that there are no
other renewable energy sources in Noatak, PV appears to be the best -suited alternative energy source
for this community.