HomeMy WebLinkAboutCity of Nenana Biomass District Heat System 65% Design Report_Wood Fired Boiler Plant - Jun 2021 - REF Grant 701402865% Design Report
Wood Fired Boiler Plant
City of Nenana
Nenana, Alaska
June 4, 2021
Presented by
Cushing Terrell
For
City of Nenana
Cushing
Terrell.
Cushing Terrell Project: NENANA BIOMASS
City of Nenana
Wood Fired Boiler Plant
65% Design Report
INTRODUCTION
June 3, 2021
This report summarizes the basis of design for a new wood fired boiler plant for the
City of Nenana, Alaska. The new wood fired boiler plant will be constructed as a
stand alone building and will house a boiler room, a chip storage area, and an area
to store City owned equipment. The east end of the building will also house a
future washeteria. Pre -insulated piping will be installed from the boiler plant to
Nenana School, the Water Treatment Plant (WTP), and the Nenana Fire
Department building to distribute heat from the boiler plant to these buildings.
The report will provide information on the existing heating systems, fuel use, wood
boiler sizing, boiler plant system design, and the building integration design. A site
visit to review existing conditions was completed by Nathan Ratz with Cushing
Terrell on April 22-23, 2021.
EXISTING BUILDING INFORMATION
Nenana School was constructed in 1955 and expanded in 1966 and 1986. The
gymnasium was constructed in 1972 and was connected to the main school
building during the 1986 addition essentially creating a single contiguous building
that is approximately 70,000 square feet. There are two boiler rooms in the facility:
one in the original school building and one in the gym. In a major mechanical
system retrofit approximately 15 years ago, new heating water mains were
installed throughout the facility, and the boilers were re -piped to provide heat to
this main loop. That work allows any boiler to provide heat to the entire facility.
The main boiler room has two cast iron, sectional boilers, fuel oil fired, each rated
at 2,500,000 Btu/hr output. The gym boiler room has two cast iron, sectional
boilers, fuel oil fired, each rated at 950,000 Btu/hr output. Two main system
pumps operating in lead/back up configuration circulate the heating hot water
through the buildings. Several smaller pumps serve various equipment and parts
of the building by pulling water from the main loop. The building has a digital
control system with a front end that allows monitoring of various HVAC equipment.
The Water Treatment Plant (WTP) was constructed in the mid 1970's and a
complete renovation of the plant including the heating system is currently
underway. The building is approximately 3,000 square feet. The renovation will
provide two new fuel oil fired, cast iron, sectional boilers, each rated at 396,000
Btu/hr output. The boilers provide heat to the building, but also provide heat to the
water system to keep it above freezing in the winter and to facilitate treatment
processes. The new design incorporate taps in the heating hot water piping to
allow the new wood fired plant to heat the new system. A new control system will
be installed to control the water treatment plant process and this system will also
control the HVAC equipment.
Cushing
Terrell.
Page 1
City of Nenana
Wood Fired Boiler Plant
65% Design Report
June 3, 2021
The Fire Department is a metal building with two modular buildings attached to it
that was constructed in the 1980's and is approximately 6,000 square feet. The
facility is heated with two fuel oil fired boilers, each rated at 272,000 Btu/hr output.
A basic controller provided with the boilers stages the boilers on and off and
starts/stops the zone pumps.
The new boiler plant will be 6,500 square feet and will be located on a lot between
the school and water treatment plant. The foundation for the building has been
poured. A metal building superstructure has been purchased and will be installed
with super insulated panels for the roof and the exterior walls. The estimated
envelope heating load for this building is 120,000 Btu/hr. The primary source of
heat will be from the wood boiler located inside the building, however, a small fuel
oil boiler will be installed to provide back up heat in case of operational problems
with the wood boiler. The back up boiler will only be sized for the boiler plant
building heating loads and is not intended to provide heat to the other buildings or
to the future washateria loads. The City has purchased a wood fired boiler from
Biomass Energy Techniques, Inc. out of Versailles, Missouri. The boiler is a model
BET 24-S and is rated for 1,400,000 Btu/hr output.
See the appendix for the boiler size summaries for each building.
CURRENT HEATING ENERGY USE
The school is using on average 34,000 gallons of fuel oil annually; the WTP is
using on average 17,400 gallons of fuel oil annually, and the fire department is
using approximately 4,200 gallons of fuel oil annually. See the appendix for a
summary of fuel use.
The heating Energy Use Index (EUI) for the school is 67.3 kBtu/SF, for the WTP is
803.3 kBtu/SF, and for the fire department is 97.0 kBtu/SF. The WTP is an outlier
and out of range for the typical building heating energy use seen for commercial
buildings. This is due to the significant amount of energy used to heat the
municipal water for treatment and for freeze protection, so the majority of energy
used at the WTP is for process loads.
BIOMASS BOILER SIZE
Wood fired boilers do not modulate well, so it is best to size them so they can
operate at full load as much as possible, which allows them to operate at
maximum efficiency as much as possible. The peak heating load of a building also
does not occur very often, usually less than 10 hours in a typical year. For this
Cushing
Terrell®
Page 2
City of Nenana
Wood Fired Boiler Plant
65% Design Report
June 3, 2021
reason, Cushing Terrell does not recommend sizing a wood boiler for the peak
heating load, but to size it large enough to meet approximately 80-85% of the
typical annual heating energy use of the building. The existing heating systems
would be used for the other 15-20% of the time during peak heating conditions,
during times when the biomass boiler is down for servicing, and during swing
months when only a few hours of heating each day are required. In general,
previous energy models of various school buildings have shown that a boiler sized
at approximately 50% of the peak load will typically accommodate approximately
85% of the heating run hours.
A basic temperature bin data heating energy analysis was performed to help
determine how much energy the new wood boiler will be able to offset for each
building.
School:
For the school envelope loss, all heating hours from September through May were
used. For the school ventilation air, 7,500 CFM was estimated based on review of
the existing school mechanical drawings and based on information from the
school. The units operated five days a week from September to May from for the
hours from 6:00 a.m. to 4:00 p.m, and the heating hours from these time frames
were used.
Using these assumptions, the bin model estimated 36,300 gallons of fuel oil use
for the school compared to the reported average of 34,000 gallons. The estimated
peak heating load is 3,000,000 Btu/hr at -60 F. This correlates with recent
experience at the school. For a late winter cold spell three months ago, the low
temperature reached -40 F, and the school was able to heat with a single primary
boiler rated at 2,500,000 Btu/hr and the air handlers operating with minimum
outside air being provided. Using this analysis, if 600,000 Btu/hr of heat energy
can be provided to the school, it is estimated to offset approximately 80% of the
total heating energy.
Fire Department:
For the fire department envelope loss, all heating hours for the entire year were
used. There is no mechanical ventilation at the fire department to account for.
Using these assumptions, the bin model estimated 4,400 gallons of fuel oil use for
the building compared to the reported average of 4,200 gallons. The estimated
peak heating load is 175,000 Btu/hr at -60 F. Using this analysis, if 60,000 Btu/hr
of heat energy can be provided to the building, it is estimated to offset
approximately 80% of the total heating energy.
Water Treatment Plant:
The majority of the fuel oil use is for process loads, and those loads vary by use
within the city and by outdoor air temperature, so it is very difficult to model the
process load profile and estimate the associated energy use. The envelope
Cushing
Terrell.
Page 3
City of Nenana
Wood Fired Boiler Plant
65% Design Report
June 3, 2021
heating energy was estimated to determine approximately what portion is for
building heating. For the envelope loss, all heating hours for the entire year were
used. Using these assumptions, the bin model estimated 5,000 gallons of fuel oil
use. The estimated peak heating load is 200,000 Btu/hr at -60 F. Using this
analysis, if 70,000 Btu/hr of heat energy can be provided to the building, it is
estimated to offset approximately 80% of the total heating energy.
The peak connected load for the building heating equipment and the heat
exchangers for the process heating is 575,000 Btu/hr (320,000 Btu/hr for the
process heating and 225,000 Btu/hr for the heating equipment). Since there is a
consistent load from the water treatment plant, the design will account for 500,000
Btu/hr of energy to be transferred at the WTP to maximize the potential fuel oil
offset.
Boiler Plant
In the future, when the washateria is built out, the majority of the fuel oil use will be
for clothes dryers, domestic hot water for clothes washers, and for heating make
up air for the dryers. Those loads will vary significantly by hours of operation and
actual use by citizens, so it is very difficult to model the process load profile and
estimate the associated energy use. The envelope heating energy was estimated
to determine approximately what portion is for building heating. For the envelope
loss, all heating hours for the entire year were used. Using these assumptions, the
bin model estimated 3,000 gallons of fuel oil use. The estimated peak heating load
is 120,000 Btu/hr at -60 F. Using this analysis, if 42,000 Btu/hr of heat energy can
be provided to the building, it is estimated to offset approximately 80% of the total
heating energy. The peak connected load for the building heating equipment and
the future water heaters, dryers, and make up air units is heat exchangers for the
process heating is estimated to be 1,120,000 Btu/hr.
The wood boiler output is 1,400,000 Btu/hr. On a peak heating day with full use of
the washateria, there would only be approximately 280,000 Btu/hr available for the
district heating system. However, this would be an extremely rare condition. This
would have to occur on a peak heating day of -60 F, and it is very unlikely that the
washateria will be in full use on a cold day such as that and also require all the
dryers, make up air, and domestic water heating at that time.
Another way to look at the boiler capacity is to review the amount of energy
required for 80% offset. In the appendix is a summary showing this for each
building. Looking at just heating the buildings, and ignoring the process loads, to
obtain 80% offset in the district heating loop and 100% offset at the boiler plant,
855,000 Btu/hr would be required. This would leave 545,000 Btu/hr for process
loads at the water treatment plant or the future washateria loads.
Cushing
Terrell®
Page 4
City of Nenana
Wood Fired Boiler Plant
65% Design Report
BOILER PLANT DESIGN
June 3, 2021
The new boiler plant will have areas for the wood boiler and associated fuel
handling equipment, heating system components, a chip storage area, and an
area where city equipment such as a loader and/or a grader can be stored. The
eastern portion of the building will be finished out as a washateria in the future.
See drawings for further information.
Chips will be stored in the middle portion of the building. A loader or skid steer will
deposit chips into the day bin. A horizontal conveyor will move the chips north to a
pit where the chips will drop onto a conveyer that will lift the chips and deposit
them into the metering bin on the boiler. The boiler has a bio char auger that will
move the material to the north and deposit it into a bin that the City will collect and
dump.
The proposed hydronic system will have the boiler on it's own hydronic loop with
it's own pump to circulate to a thermal storage tank, which is calculated to be
approximately 1,000 gallons. See appendix for the sizing calculation. This tank
will serve as a hydraulic separator, and the hot tap on the tank will then feed two
loops. One loop will be for the district heating. Two base mounted pumps with
variable speed drives will circulate heating water from the plant to the three
buildings. Flow will vary to meet the various loads of the buildings. The second
loop will be for the boiler plant and future washateria. This loop will be a primary
cascade loop with pumps for each heating need. The systems requiring hotter
water temperatures will be served first, and the systems with lower temperature
needs (such as the in floor radiant heat) will be served last.
The heating fluid will be treated water — no glycol. The plant will have an
emergency generator to provide power to the main system pumps and the back up
boiler. So the water will be able to be circulated and heated enough to stay above
freezing when there is an emergency situation. Where outside air will be heated,
such as the make up air unit for the dryers, a small glycol loop will serve the coil,
and a heat exchanger used to heat the glycol loop.
The majority of the building will be heated with in slab radiant heat. The exception
being the boiler room, where supports and other equipment will need to be bolted
into the floor, so having tubing will be problematic. The boiler room will have a unit
heater for back up, but the residual heat from the wood boiler will likely heat the
room.
The boiler plant will have a small fuel oil boiler to provide heat when the wood
boiler is down. This boiler will only be sized for the building envelop heating, and
not for any process loads.
Cushing
Terrell.
Page 5
City of Nenana
Wood Fired Boiler Plant
65% Design Report
June 3, 2021
The boiler room and chip storage area will also be ventilated and opportunities to
utilize the waste heat will be investigated.
The future washateria will require domestic hot water heaters, clothes dryers with
hot water coils, an energy recovery ventilator for the shower rooms, and a make up
air unit for the dryers.
INTEGRATION WITH EXISTING HEATING SYSTEMS
Integration of the wood fired boiler system will be relatively straight forward at each
building. The field visit confirmed the location of the boiler and mechanical rooms
and identified the points of connection for the existing heating systems in each
building. See the drawings for further information on the site pipe routing and the
integration at each building.
School:
Preinsulated PEX piping from the biomass boiler plant would run below ground
from the new boiler plant to near the north entry to the school. The piping would
rise up on the exterior and then enter the building in the maintenance office area
and run through the ceiling of the maintenance offices, a hallway, and a teacher
break room and enter the original boiler room. The portion of exterior piping above
grade will be covered with an insulated enclosure.
Once the heating water piping enters the existing boiler room it would run to a heat
exchanger located next to the air handling unit under the walkway. On the other
side of the heat exchanger, a primary -secondary piping connection would be
installed in the existing heating water return piping and a pump would circulate
water from this connection though this heat exchanger to inject heat just upstream
of the boiler connections. A Btu meter would be installed to measure energy use
of the school system. A temperature sensor would also be installed on the district
heating piping so that if the district loop is not warm enough to provide beneficial
heat to the school, the heat injection pump on the school loop side would not
operate.
Water Treatment Plant:
Preinsulated PEX piping from the biomass boiler plant would run below ground
from the new boiler plant to the northeast corner of the WTP. It would rise up and
enter the building and then run to the boiler room. A heat exchanger would be
installed in the boiler room in a spot identified in the renovation project, and the
district piping would connect to the hot side of the heat exchanger. On the other
side of the heat exchanger, piping would be extended and connect to the primary -
secondary piping taps that are part of the renovation project. A heat injection
pump would circulate water from the building heating loop through the heat
exchanger and inject heat into the return piping just upstream of the boilers.
Cushing
Terrell®
Page 6
City of Nenana
Wood Fired Boiler Plant
65% Design Report
June 3, 2021
Fire Department:
Preinsulated PEX piping would run below ground from the WTP to the east side of
the fire department where the boiler room is located. This is a continuation of the
loop serving the WTP. A heat exchanger would be installed on the storage area
above the boiler room, and the district piping would connect to the hot side of the
heat exchanger. On the other side of the heat exchanger, piping would be
extended and connect to new primary -secondary piping connections to the building
return piping. A heat injection pump would circulate water from the building
heating loop through the heat exchanger and inject heat into the return piping just
upstream of the boilers.
ELECTRICAL SERVICE
The new boiler plant will be provided with a new 480 volt, 3 phase service from
Golden Valley Electric Association.
Attachments:
• Building Fuel Use, Heating Load, and Boiler Load Summary
• Wood Fuel Use Summary
• Temperature Bin Energy Analysis
• 65% Drawings
Cushing
Terrell®
Page 7
Wood Fired Boiler Plant
City of Nenana
Nenana, Alaska
nistoncai rues uu use
Average
Annual
Building
Gallons
School
34,000
Water Treatment Plant
17,400
Fire Deparment
4,200
Total
55,600
Heating Boiler Summary
Output
Building Equipment
Fuel
MBH
School Boiler 1
Fuel Oil
2,503
Boiler 1A
Fuel Oil
2,503
Boiler 2
Fuel Oil
950
Boiler 2A
Fuel Oil
950
Total
6,906
WTP Boiler 1
Fuel Oil
396.0
Boiler 2
Fuel Oil
396.0
Total
792
Fire Dept Boiler 1
Fuel Oil
272.0
Boiler 2
Fuel Oil
272.0
Total
544
Preliminary
Boiler Plant Boiler 1
Wood
1,400
Boiler
Fuel Oil
148.0
Total
1,548
Heating Equipment Summary, WTP and Boiler Plant
Building Equipment
MBH
WTP Building Heating Equipment
254.6
Process Heat Exchangers
320
Total
574.6
(Preliminary)
Boiler Plant Envelope
120
Dom. Water Heaters (2 x 100)
200
Dryers (10 x 35)
350
Make Up Air Unit
450
Total
1,120
I nermal Storage I anK bizin
V min = gmin x t
500 x dT For modulating boilers.
V min = minimum required volume (gallons)
qmin minimum heat ouput of boiler (Btu/hr)
t = minimum time of on cycle at minimum firing rate (minutes)
dT = water temperature rise in tank based on absorbing all heat from combustion (deg F;
500 = constant based on water
V min qmin t T begin T final
(gal) (Btu/hr) (min) (deg F) (deg F)
1050 350000 45 150 180 25% Firing Rate
Cushing Terrell June 4, 2021
Wood Fired Boiler Plant
City of Nenana
Nenana, Alaska
neaang Loaa summary
Heating
Heating
Building
Heating
Load
Estimated
Load
Area
Output
Index
Peak Load
Index
Building
Sq. Ft.
Btu/hr
Btu/hr/SF
Btu/hr
Btu/hr/SF
School
70,000
6,906,000
98.7
3,000,000
42.9
WTP
3,000
792,000
264.0
200,000
66.7
Fire Dept
6,000
272,000
41.8
272,000
41.8
Boiler Plant
6,500
148,000
22.8
120,000
18.5
(Estimate only, envelope
loss only.)
rsurnmea vvooa csouer sae ana rracuon or i orai rnergy
Heat Energy
for 80%
Fuel Offset
Building
Btu/hr
School
600,000
WTP
75,000
Fire Dept
60,000
Boiler Plant
120,000 Full Building Heating Load for Boiler Plant
Total
855,000
Wood Boiler Ouput
1,400,000
545,000 Btu/hr available for process and peak loads.
Based on Temperature Bin Energy Estimation
Annuai energy
use ana rocenuai vvooa ruei use aummary
Avg.
Current
Current
Gross
Gross
Building
Annual
Fuel
Est.
Energy
Energy
Heating
Area
Heating
Fuel
Cost
Annual
Convers.
Use
EUI
Building
Sq. Ft.
Energy
units
$/Unit
Cost
Btu/unit
Therms
kBtu/SF
School
70,000
34,000
Gal
$3.00
$102,000
138,500
47,090
67.3
WTP
3,000
17,400
Gal
$3.00
$52,200
138,500
24,099
803.3
Fire Dept
6,000
4,200
Gal
$3.00
$12,600
138,500
5,817
97.0
Totals
79,000
55,600
Gal
$166,800
Chips/Ground Fuel
80.0%
Fuel Oil
Building
Wood
Gross
Equiv.
Equiv.
Boiler
Energy
Boiler
Energy
Energy
Wood
Wood
Est.
Use
Est.
Use
Convers.
Fuel
Fuel
Building
Eff.
Therms
Eff.
Therms
Btu/Ib
tons
tons
School
0.82
38,614
0.75
51,485
5,712
450.7
360.5
WTP
0.82
19,761
0.75
26,348
5,712
230.6
184.5
Fire Dept
0.82
4,770
0.75
6,360
5,712
55.7
44.5
Unit Fuel Costs
Net
Gross
System
System
Delivered
Gross
FuelType Units Btu/unit
Effecienc
Btu/unit
$/unit
$/MMBtu
$/MMBtu
Fuel Oil gal 138,500
0.82
113,570
$2.90
$25.53
$20.94
$3.00
$26.42
$21.66
$3.25
$28.62
$23.47
$3.50
$30.82
$25.27
$4.00
$35.22
$28.88
Chips tons 1.142E+07
0.75
8,568,000
$60.00
$7.00
$5.25
Cushing Terrell June 4, 2021
� E a
� o m
E E
E o
3
v Q 3
- m
Y
=
o a
;ao
— 3 —
�
m E
n ¢ �
s 6
mom=
UH
3
Y
a
- o
a
=
O
3
o a
;ao
— 3 —
�
A
mom=
UH
))/
�
-_
U F=
o �
3
Y
a
- O
a
=
O
3
o a
;ao
— 3 —
�
A
mom=
UH