HomeMy WebLinkAboutElim Wind-Diesel Analysis Report - Oct 2016 - REF Grant 7040053Elim, Alaska
Wind-Diesel Analysis
Google Earth image of Elim
October 12, 2016
Douglas Vaught, P.E.
V3 Energy, LLC
Anchorage, Alaska
www.v3energy.com
Elim, Alaska Wind-Diesel Analysis Page | i
This report was prepared by V3 Energy, LLC under contract to Alaska Village Electric Cooperative to
assess the technical and economic feasibility of installing wind turbines in Elim, Alaska. This analysis is
part of a renewable energy project funded by the Alaska Energy Authority through the Renewable
Energy Fund.
Contents
Introduction..................................................................................................................................................1
Executive Summary.......................................................................................................................................1
Village of Elim................................................................................................................................................1
Wind Resource..............................................................................................................................................2
Measured Wind Speeds............................................................................................................................3
Wind Roses................................................................................................................................................4
WAsP Wind Flow Model ...............................................................................................................................4
Orographic Modeling................................................................................................................................4
Wind Turbine Project Site Options ...............................................................................................................5
Recommended Turbine Site......................................................................................................................6
Elim Power System........................................................................................................................................6
Diesel Generators .....................................................................................................................................6
Electric Load..............................................................................................................................................6
Thermal Load ............................................................................................................................................7
Wind-Diesel Hybrid System Design and Equipment.....................................................................................7
Proposed Wind Turbine............................................................................................................................8
HOMER Modeling .........................................................................................................................................9
Modeling Assumptions .............................................................................................................................9
Model Results .........................................................................................................................................10
Met Tower Site, two NPS100C-24 turbines, 37 m hub height............................................................10
Airport Hill Site, two NPS100C-24 turbines, 37 m hub height............................................................11
Economic Analysis.......................................................................................................................................12
Project Capital Cost.................................................................................................................................12
Fuel Cost..................................................................................................................................................12
Economic Valuation ................................................................................................................................12
Recommendations......................................................................................................................................13
Elim, Alaska Wind-Diesel Analysis Page | ii
Appendix – Elim Wind Resource Assessment Report.................................................................................14
Summary.................................................................................................................................................15
Met tower data synopsis ....................................................................................................................15
Site information..................................................................................................................................15
Tower sensor information ..................................................................................................................15
Data Quality Control ...............................................................................................................................17
Wind Speed.............................................................................................................................................18
Time Series..............................................................................................................................................19
Probability Distribution Function................................................................................................................20
Wind Direction............................................................................................................................................22
Wind Shear and Roughness........................................................................................................................24
Extreme Winds............................................................................................................................................25
Turbulence..................................................................................................................................................26
Temperature, Density, and Relative Humidity ...........................................................................................28
Wind Speed Scatterplot..........................................................................................................................29
Solar Resource ........................................................................................................................................30
Elim, Alaska Wind-Diesel Analysis Page | 1
Introduction
Alaska Village Electric Cooperative (AVEC) is the electric utility for the Native village of Elim, Alaska.
AVEC was awarded a grant from the Alaska Energy Authority (AEA) to complete resource assessment
and feasibility work for installation of wind turbines in the community of Elim.
Executive Summary
Depending on the project site – the met tower location or possibly the hill west of the airport – Elim has
a low to moderate wind resource for wind power development, but the new Northern Power Systems
NPS100C-24 wind turbine is expressly designed for lower wind class environments and modeling results
predict the potential for surprisingly good energy production. Site options for wind turbines are limited
in Elim and given the poor wind resource at the met tower site, the hill west of the airport is the only
truly viable option, but development of the hill site likely would require another met tower study, FAA
permitting, and consideration of project capital costs.
Village of Elim
Elim is located on the northwest shore of Norton Bay on the Seward Peninsula, 96 miles east of Nome. It
lies 460 miles northwest of Anchorage. Elim falls within the transitional climate zone, characterized by
tundra interspersed with boreal forests, and weather patterns of long, cold winters and shorter, warm
summers. Norton Sound is ice-free generally between mid-June and mid-November. Summers are cool
and rainy; winters are cold and dry.
This settlement was
formerly the Malemiut
Inupiat Eskimo village of
Nuviakchak. The Native
culture was well-developed
and well-adapted to the
environment. Each tribe
possessed a well-defined
subsistence harvest
territory. The area became a federal reindeer reserve in 1911. In 1914, Rev. L.E. Ost founded a Covenant
mission and school, called Elim Mission Roadhouse. The city was incorporated in 1970. When the Alaska
Native Claims Settlement Act (ANCSA) was passed in 1971, Elim decided not to participate and instead
opted for title to the 298,000 acres of land in the former Elim Reserve. The Iditarod Sled Dog Race
passes through Elim each year.
Elim, Alaska Wind-Diesel Analysis Page | 2
Topographic map of Elim and vicinity
Google Earth image of Elim (view north)
Wind Resource
A 34 meter NRG Systems, Inc. tubular-type meteorological (met) tower was installed in Elim in an open
area of city land immediately northeast of the community and just east of the road to Moses Point. The
met tower was operational for nineteen months, from late January 2014 to mid-September 2015.
Elim
Elim, Alaska Wind-Diesel Analysis Page | 3
The wind resource measured at the Elim met tower site is marginal with a mean annual wind speed of
5.12 m/s and a wind power density of 191 W/m
2 at 34 meters above ground level. This confirms the
AWS Truepower wind resource map which predicts wind power Class 2 winds at this location. The wind
resource is summarized below, and described in detail in the Appendix of this report. Higher winds are
predicted on the high terrain surrounding Elim, including the hills immediately west and north of the
airport.
Elim met tower data synopsis
Data dates 1/30/2014 to 9/14/2015 (19 months)
Wind speed mean, 34 m, annual 5.12 m/s (11.5 mph)
Wind power density mean, 34 m 191 W/m
2
Max. 10-min wind speed 17.5 m/s (39.1 mph)
Maximum 2-sec. wind gust 25.5 m/s (57.0 mph)
Weibull distribution parameters k = 1.71, c = 5.54 m/s
Wind shear power law exponent 0.247 (low)
Surface roughness 0.74 meters (urban)
IEC 61400-1, 3rd ed. classification Class IIIA
Turbulence intensity, mean (at 34 m) 0.145 (at 15 m/s)
Calm wind frequency (at 34 m) 41% (< 4 m/s) (19 mo. measurement period)
Measured Wind Speeds
During the measurement period, winds at the test site measured 5.12 m/s (annualized), which can be
considered fair for wind power development, provided a wind turbine optimized for lower wind speeds
is selected.
Elim met tower wind speed graph
Elim, Alaska Wind-Diesel Analysis Page | 4
Wind Roses
Wind frequency rose data indicates that winds at the Elim met tower site are primarily bi-directional,
with east-northeasterly and west-southwesterly winds predominating. The mean value rose (see
Appendix A) indicates that ENE winds are of equal intensity as WSW winds, but with more frequent ENE
winds, the dominant energy winds are from that direction.
Calm frequency, the percent of time that winds at the 34-meter level are less than 4 m/s, a typical cut-in
speed of larger wind turbines, was 41 percent during the 19-month test period.
Wind Frequency Rose Wind Energy Rose
WAsP Wind Flow Model
WAsP (Wind Atlas Analysis and Application Program) is a PC-based software designed to estimate wind
resource and power production for individual wind turbines and/or wind turbine farms. WAsP was used
to predict wind turbine performance at selected locations in Elim.
Orographic Modeling
WAsP modeling begins with import of a digital elevation map (DEM) of the subject site and surrounding
area and conversion of coordinates to Universal Transverse Mercator (UTM). UTM is a geographic
coordinate system that uses a two-dimensional Cartesian coordinate system to identify locations on the
surface of Earth. UTM coordinates reference the meridian of its particular zone (60 longitudinal zones
are further subdivided by 20 latitude bands) for the easting coordinate and distance from the equator
for the northing coordinate. Units are meters. Elevations of the DEMs are converted to meters (if
necessary) for import into WAsP software.
A met tower reference point is added to the digital elevation map, wind turbine locations identified, and
a wind turbine(s) selected to perform the calculations. WAsP considers the orographic (terrain) effects
on the wind, plus surface roughness variability and obstacles if added, and calculates wind flow increase
or decrease at each node of the DEM grid. The mathematical model, although robust, has a number of
Elim, Alaska Wind-Diesel Analysis Page | 5
limitations, including an assumption that the wind regime at the turbine site is the same as at the met
tower reference site, prevailing weather conditions are stable over time, and the surrounding terrain at
both sites is sufficiently gentle and smooth to ensure laminar, attached wind flow. The version of WAsP
software used for this analysis is not capable of modeling turbulent wind flow resulting from sharp
terrain features such as mountain ridges, canyons, shear bluffs, etc.
Given the hilly terrain of Elim and surrounding area, orographic modeling with the met tower station as
the reference point indicates higher winds may be found on the hill west of the airport, the prominent
treeless knob immediately north of Elim (along the road to Moses Point), and other higher terrain
further from the community. This confirms the AWS Truepower mesoscale wind model which predicts
wind power class 2 winds at the met tower site and up to wind power class 4 winds on the hill west of
the airport. WAsP predicts a wide range of wind speeds on the hill west of the airport, but for
evaluation 6.0 m/s is chosen as representative of a location on the northeast slope of the hill, between
the forest margin and the high point.
WAsP wind modeling of Elim
Wind Turbine Project Site Options
The Elim met tower location is a site option for wind turbines, but the recently completed met tower
study indicated that the wind resource in this location is poor suited for wind power and hence not an
ideal choice. A second option is on the hill complex west of the airport, subject to successful approval of
an FAA obstruction evaluation. Earlier discussions with FAA indicated that they objected to wind
turbines at the high point of the hill but that lower elevations to the north side could possibly be
Met tower site
Hill west of airport
Elim, Alaska Wind-Diesel Analysis Page | 6
permitted. With that, a site on the northeast shoulder of the hill complex somewhat near the airport
tarmac is another wind turbine site option in Elim.
Recommended Turbine Site
Although the Elim met tower site is modeled in this report, it is not recommended for wind power
development due to insufficient wind resource and excessive turbulence. The hill west of the airport
clearly has a better wind resource but turbulence is unknown at present, although likely less than the
met tower site. The hill west of the airport is only recommended given the presumption of a better
wind resource than at the met tower site, but land ownership, FAA permitting, and cost constraints are
unknown at present.
Elim Power System
The Elim power system at present consists of three diesel generators without heat recovery and a three-
phase power distribution network to serve the community.
Diesel Generators
The Elim power plant is equipped with three diesel generator models as described below. The power
plant is not equipped with a recovered heat system because of its distance from other community
facilities. Note also that the power plant is equipped with manual switchgear which would require
upgrade to operate seamlessly with wind turbines.
Elim power plantdiesel generators
Generator Electrical Rating Diesel Engine Generator
1 363kW Detroit Diesel S60K4 1800 rpm MAR 5M4027
2 236kW Detroit Diesel S60K4 1200 rpm Newage
3 506 kW MTU 8V2000 MAR 5M4030
Electric Load
Elim electric load was obtained from AVEC via its automated logging which requires energy delivered
every 15 minutes. The file used for this analysis contained data from December 21, 2012 to March 5,
2016. Energy was converted to power, the 15-minute time periods were average to obtain a
representative year logs, and the resulting file uploaded to HOMER software for analysis. AVEC data
indicates an average load in Elim of 139 kW with a typical (15 minute) peak load of 220 KW which can
occur in the coldest winter months of November through March. Total annual electric energy demand is
1,220 MWh.
Elim, Alaska Wind-Diesel Analysis Page | 7
Elim electric load
Thermal Load
Jacket water heat from the Elim powerplant diesel engines is ejected to the atmosphere via the system
radiators and hence is not used to offset thermal load demand in the larger structures of the
community, such as the school. With that, to use excess energy from wind turbines, a remote node
boiler must be installed in the school, water plant, or other location with significant thermal demand.
Wind-Diesel Hybrid System Design and Equipment
Wind-diesel power systems are categorized based on their average penetration levels, or the overall
proportion of wind-generated electricity compared to the total amount of electrical energy generated.
Commonly used categories of wind-diesel penetration levels are very low, low, medium, and high
penetration. The wind penetration level is roughly equivalent to the amount of diesel fuel displaced by
wind power. Note however that the higher the level of wind penetration, the more complex and
expensive a control system and demand-management strategy is required.
Categories ofwind-dieselpenetrationlevels
Penetration
Category
Wind Penetration Level
Operating Characteristics and System Requirements
Instantaneous Average
Very Low <60% <8%x Diesel generator(s) runs full time
x Wind power reduces net load on diesel
x All wind energy serves primary load
x No supervisory control system
Low 60 to 120% 8 to 20%x Diesel generator(s) runs full time
x At high wind power levels, secondary loads are
dispatched to insure sufficient diesel loading, or wind
generation is curtailed
x Relatively simple control system
Medium 120 to 300% 20 to 50%x Diesel generator(s) runs full time
Elim, Alaska Wind-Diesel Analysis Page | 8
Penetration
Category
Wind Penetration Level
Operating Characteristics and System Requirements
Instantaneous Average
x At medium to high wind power levels, secondary
loads are dispatched to insure sufficient diesel
loading
x At high wind power levels, complex secondary load
control system is needed to ensure heat loads do not
become saturated
x Sophisticated control system
High
(Diesels-off
Capable)
300+% 50 to 150%x At high wind power levels, diesel generator(s) may be
shut down for diesels-off capability
x Auxiliary components required to regulate voltage
and frequency
x Sophisticated control system
Medium penetration is a reasonable compromise between fuel use offset and relatively minimal system
complexity and is AVEC’s preferred system configuration. Installation of wind turbines in Elim would
likely be configured at the medium penetration level.
Proposed Wind Turbine
The Northern Power Systems NPS 100C-24 wind turbine is proposed for Elim on the highest tower that
can be permitted. This turbine is rated at 95 kW and is equipped with a permanent magnet,
synchronous generator for direct drive (no gearbox) operation. The turbine has a 24.4-meter diameter
rotor and is available with three tubular tower heights: 22, 29, and 37 meters. The NPS 100C-24 is
specifically optimized for lower wind speed sites and is marketed as a IEC 61400-1, 3
rd edition, Class III-C
turbine.
The NPS 100C-24 is stall-regulated and for Elim would be equipped with an arctic package enabling
operation at temperatures as low as -40° C. The NPS 100 is the most widely represented village-scale
wind turbine in Alaska with a significant number of installations in the Yukon-Kuskokwim Delta and on
St. Lawrence Island. The NPS 100 wind turbine is manufactured in Barre, Vermont, USA. More
information can be found at http://www.northernpower.com/. The power output and coefficient of
thrust (Ct) curves of the NPS 100C-24 are shown below.
NPS 100C-24 power and thrust curves
Elim, Alaska Wind-Diesel Analysis Page | 9
Northern Power Systems 100 (B model) wind turbines, Shaktoolik, Alaska
HOMER Modeling
HOMER energy modeling software was used to analyze the Elim power system. HOMER is a static
energy balance and financial model designed to optimize hybrid power system designs that contain a
mix of conventional and renewable energy sources, such as diesel generators, wind turbines, solar
panels, batteries, etc. HOMER software is widely used in the State of Alaska to aid development of
village wind-diesel power projects.
Modeling Assumptions
HOMER modeling assumptions are detailed in the table below. Many assumptions, such as project life,
discount rate, operations and maintenance (O&M) costs, etc. are AEA default values. The base or
comparison scenario is the existing Elim power plant with its present configuration of three diesel
generators.
New NPS 100C-24 wind turbines constructed at the Elim site are assumed to operate in parallel with the
diesel generators. Excess energy, if sufficient, will serve thermal loads via a remote node secondary load
controller and electric boiler to serve thermal loads in the school, community water plant or other
location. Installation cost of the wind turbines assumes road construction to either the met tower site
or a site west of the airport.
HOMER and AEA modeling assumptions
Economic Assumptions
Project life 20 years (2018 to 2037)
Discount rate 3% (reference: AEA EvaluationModelREFR9Final spreadsheet)
Operating Reserves
Load in current time step 10%
Wind power output 50% (in event of loss of one wind turbine if two are operational)
Diesel Generators
Elim, Alaska Wind-Diesel Analysis Page | 10
O&M cost $0.203/kWh (reference: AEA EvaluationModelREFR9Final
spreadsheet)
Minimum load 15%
Schedule Optimized; always diesels-on
Wind Turbines
Net AEP 85% (net all losses: icing, wake, O&M, electrical, soiling, etc.)
O&M cost 1% of capex/year (reference: AEA EvaluationModelREFR9Final
spreadsheet)
Wind speed 5.12 m/s at 34 m, measured at met tower;
6.0 m/s estimated by WAsP modeling on hill west of airport
Wind shear 0.187 power law exponent
Energy Loads
Electric 3.34 MWh/day average Elim electric load
Thermal Modeled as remote node and infinite
Model Results
HOMER energy modeling software was used to calculate wind turbine energy production and excess
energy available (not demanded by the electrical load). Note that inclusion of wind turbines as a wind-
diesel power system, even at lower penetration levels, can result in energy generation greater than
electrical load demand. This is due to spinning reserve and minimum loading requirements of the diesel
generators. Note that wind turbine energy production in these analyses is calculated at 85 percent of
gross. HOMER software does not model system dynamic response. Possible system instability would be
addressed during design.
Met Tower Site, two NPS100C-24 turbines, 37 m hub height
This configuration is two Northern Power NPS100C-24 wind turbines on 37-meter towers at the existing
met tower site. In this scenario, wind turbine penetration (percent electrical power production by wind)
would be 26.1 percent. Excess energy is modeled as 35.8 MWh/year, or 2.9% of energy generated.
Energy table, met tower site, two NPS 100C-24 turbines, 85% net AEP
Elim, Alaska Wind-Diesel Analysis Page | 11
Chart, met tower site, electric load and two NPS 100 turbines, 85% net AEP
Airport Hill Site, two NPS100C-24 turbines, 37 m hub height
This configuration is two Northern Power NPS100C-24 wind turbines on 37-meter towers at a presently-
undefined location on the hill west of the airport between the tree line and the hill summit. In this
scenario, wind turbine penetration (percent electrical power production by wind) would be 34.2
percent. Excess energy is modeled as 68.8 MWh/year, or 5.6% of energy generated.
Energy table, airport hill site, two NPS 100C-24 turbines, 85% net AEP
Elim, Alaska Wind-Diesel Analysis Page | 12
Chart, airport hill site, electric load and two NPS 100 turbines, 85% net AEP
Economic Analysis
AEA’s 2015 EvaluationModelREFR9Final (1)Excel spreadsheet was used to evaluate the potential
economic benefit of a wind power project in Elim.
Project Capital Cost
Capital and installation costs of wind turbines to serve Elim is estimated from AEA’s 2015
EvaluationModelREFR9Final (1)Excel spreadsheet default assumption of $10,897/kW installed wind
power capacity. With this assumption, capital cost for economic benefit calculation is $2.18M for a two
turbine project.
Fuel Cost
A fuel price of $3.96/gallon was chosen for the initial HOMER analysis by reference to the AEA’s 2015
EvaluationModelREFR9Final (1)Excel spreadsheet. This price reflects the average estimated fuel price in
Elim between the 2018 (the assumed project start year) fuel price of $3.35/gallon and the 2036 (20-year
project end year) fuel price of $4.79/gallon using diesel fuel price projection in the spreadsheet. This
price projection includes an average CO2-equivalent allowance cost of $0.67/gallon.
Economic Valuation
HOMER software was used in this wind-diesel analysis to model the wind resource, wind turbine energy
production, effect on the diesel engines when operated with wind turbines, and excess wind energy that
could be used to serve thermal loads. Although HOMER software is designed to evaluate economic
valuation by ranking alternatives, including a base or “do nothing” alternative by net present cost, AEA
economic valuation methodology differs in its assumptions of O&M costs, fuel cost for each year of the
project life, and disposition of excess energy. Excess energy is valued in the ISER spreadsheet with an
assumption that the power plant is not co-generation. In other words, excess energy is valued without
Elim, Alaska Wind-Diesel Analysis Page | 13
consideration of possible thermal production loss due to reduced diesel engine loading as would occur
in a co-generation system configuration.
In an effort to align economic valuation of project alternatives with Alaska Energy Authority methods,
this feasibility analysis uses AEA’s economic evaluation methods. The model is updated every July in
preparation for the next round of Renewable Energy Fund requests for proposals in the form of an
explanation report and an Excel spreadsheet. The latest version of the spreadsheet has a file name of
EvaluationModelREFR9Final (1)and is available on AEA’s website.
Project economic valuation
No.
Turbines
Diesel
Fuel
Saved
(gal/yr)
Heat Oil
Saved
(gal/yr)
Petroleum
Fuel
Saved
(gal/yr)
(in $ millions)
Site Project
Cost
NPV
Benefits
NPV
Costs
B/C
ratio
Met Tower 2 2.18 1.84 2.18 0.84 28,306 854 29,160
Airport Hill 2 2.18 2.6 2.18 1.19 33,350 1,638 34,988
Recommendations
Elim has a low-to-moderate wind resource for wind power development, but the new Northern Power
Systems NPS100C-24 wind turbine is designed for lower wind class environments and modeling
indicates very respectable energy production and turbine capacity factor in Elim, especially on the hill
west of the airport. The very cold temperatures of Elim are a bonus due to the performance boost from
increased aerodynamic lift across the rotor blades, compared to standard conditions.
Wind turbine site options are limited in Elim and although the met tower site would be a convenient
location for wind turbines, the met tower study demonstrated and only marginal wind resource with
high turbulence at that location. A preferred wind turbine site would be the hill west of the airport,
presuming a new met tower study verifies the presumed 6.0 m/s wind resource, successful FAA
obstruction permitting, and project capital costs are reasonable.
Elim, Alaska Wind-Diesel Analysis Page | 14
Appendix – Elim Wind Resource Assessment Report
Elim met tower, view southwest
Elim, Alaska Wind-Diesel Analysis Page | 15
Summary
The wind resource measured at the Elim met tower site is wind power Class 2 (marginal) with a mean
annual wind speed of 5.12 m/s and a wind power density of 191 W/m
2 at 34 meters above ground level.
This validates the AWS Truepower wind resource map which predicts Class 2 to 3 winds at the Elim met
tower site.
Met tower data synopsis
Data dates 1/30/2014 to 9/14/2015 (19 months)
Wind speed mean, 34 m, annual 5.12 m/s (11.5 mph)
Wind power density mean, 34 m 191 W/m
2
Max. 10-min wind speed 17.5 m/s (39.1 mph)
Maximum 2-sec. wind gust 25.5 m/s (57.0 mph)
Weibull distribution parameters k = 1.71, c = 5.54 m/s
Wind shear power law exponent 0.247 (low)
Surface roughness 0.74 meters (urban)
IEC 61400-1, 3rd ed. classification Class IIIA
Turbulence intensity, mean (at 34 m) 0.145 (at 15 m/s)
Calm wind frequency (at 34 m) 41% (< 4 m/s) (19 mo. measurement period)
Site information
Site number 0054
Latitude/longitude N 64° 37.290’, W 162° 14.530’
Time offset -9 hours from UTC (Yukon/Alaska time zone)
Site elevation 43 meters (141 ft.)
Datalogger type NRG SymphoniePLUS3, 10-minute time step
Tower type Tubular, 15 cm (6 in.) diameter, 34 meter (112 ft.) height
Tower sensor information
Channel Sensor type Designation SN Height Boom Multiplier Offset Orientation
1 NRG #40C
anemometer
34 m A 219000 34.3 m 183
cm
0.749 0.36 060° T
2 NRG #40C
anemometer
34 m B 219010 34.2 m 183
cm
0.754 0.35 340° T
3 NRG #40C
anemometer
21 m 219009 21.1 m 183
cm
0.746 0.38 060° T
7 NRG #200P
wind vane
Direction 33.0 m 183
cm
0.351 210 030° T
9 NRG #110S
Temp C
Temp 2.5 m 0.136 -86.38 North
10 NRG RH5X
rel. humidity
RH 2.5 m 0.097 0
11 Li-Cor LI200
pyranometer
solar PY
80401
2.5 m 1.368 0
Elim, Alaska Wind-Diesel Analysis Page | 16
Tower photographs
North face of met tower East face of met tower
South face of met tower West face of met tower
Elim, Alaska Wind-Diesel Analysis Page | 17
Google Earth image, Elim, location of met tower
Data Quality Control
Data was filtered to remove presumed icing events that yield false zero wind speed data and non-variant
wind direction data. Data that meet the following criteria are automatically filtered:
x Anemometer icing – data filtered if temperature < 1°C, speed SD = 0, and speed changes < 0.25
m/s for minimum 2 hours
x Vane icing – data filtered if temperature < 1°C and vane SD = 0 for minimum of 2 hours
x Tower shading of the 34 meter A and B paired anemometers – data filtered when winds ± 15°
from behind tower
Data is also manually filtered for obvious icing that the automatic filter didn’t identify, and invalid or low
quality data for situations such as logger initialization and other situations.
For the Elim data set, anemometer icing was surprisingly minimal but wind vane icing was quite high
with the sensor out-of-service for long periods of time during the mid-winter months. It is unusual to
observe so much obvious icing behavior in a wind vane but not in the anemometers.
Sensor data recovery table
Data Column
Possible
Records
Valid
Records
Recovery
Rate (%)Icing Invalid
Tower
shading
Speed 34 m A 85,156 84,619 99.4% 537 0 0
Speed 34 m B 85,156 84,596 99.3% 555 5 0
Elim, Alaska Wind-Diesel Analysis Page | 18
Data Column
Possible
Records
Valid
Records
Recovery
Rate (%)Icing Invalid
Tower
shading
Speed 20 m 85,156 84,608 99.4% 548 0 0
Direction 33 m 85,156 72,648 85.3% 12,508 0 0
Temperature 85,156 85,156 100.0% 0 0 0
Relative humidity 53,902 53,902 100.0% 0 0 0
Pyranometer 85,156 85,156 100.0% 0 0 0
In addition, for paired anemometers, data is normally filtered for tower shadow but the typically
distinctive speed ratio dual signature indicating tower shadow was not present, due perhaps to the
turbulent air at the site. For this reason, the 34 meter anemometers were not filtered for tower shadow
even the different measured mean wind speed indicates that some shadow was present.
Tower shading rose, 34 m anemometers
Elim tower shadow rose Typical tower shadow rose
Wind Speed
Anemometer data obtained from the met tower, from the perspectives of both mean wind speed and
mean wind power density, indicate a marginal wind resource at the met tower site. The table below
presents raw and filtered anemometer (icing only) wind speed data.
Anemometer data summary
Variable Speed 34 m A Speed 34 m B Speed 20 m
Measurement height (m) 34.3 34.2 21.1
Raw mean wind speed (m/s) 4.80 4.94 4.25
Filtered mean wind speed (m/s) 4.82 4.97 4.28
MoMM wind speed (m/s) 4.99 5.12 4.41
Max 10-min wind speed (m/s) 17.5 17.4 15.3
Max 2-sec. gust wind speed (m/s) 25.4 25.5 25.3
Weibull k 1.61 1.71 1.57
Weibull c (m/s) 5.34 5.55 4.73
Mean power density (W/m²) 164 172 117
MoMM power density (W/m²) 183 191 130
Elim, Alaska Wind-Diesel Analysis Page | 19
Variable Speed 34 m A Speed 34 m B Speed 20 m
Mean energy content (kWh/m²/yr) 1,434 1,505 1,027
MoMM energy content (kWh/m²/yr) 1,603 1,670 1,141
Energy pattern factor 2.3 2.2 2.3
Frequency of calms (< 4.0 m/s) 44.2 42.5 51.7
MoMM = mean of monthly means (annualized)
Time Series
Time series calculations indicate higher wind speeds during the autumn months compared to the
remainder of the year. Interestingly, summer wind speeds are nearly as high as during mid-winter. The
daily wind profile (annual basis) indicates relatively even wind speeds throughout the day with slightly
higher wind speeds during night hours.
34 m B anemometer data summary
Raw
Mean
Filtered
Mean Max Gust
Std.
Dev.
Weibull
K
Weibull
c
Year Month (m/s)(m/s)(m/s)(m/s)(m/s)(-)(m/s)
2014 Feb 5.93 6.16 14.1 21.5 2.84 2.24 6.90
2014 Mar 5.72 5.72 15.2 23.5 3.01 1.86 6.37
2014 Apr 5.14 5.13 11.7 16.0 2.37 2.25 5.76
2014 May 4.11 4.11 12.4 14.7 2.23 1.91 4.63
2014 Jun 4.01 4.01 9.7 14.7 2.00 2.10 4.53
2014 Jul 5.18 5.18 16.8 21.5 3.00 1.78 5.82
2014 Aug 4.04 4.04 15.7 20.6 2.17 1.92 4.55
2014 Sep 4.73 4.73 17.1 20.6 2.63 1.86 5.32
2014 Oct 5.92 5.92 17.4 23.5 2.85 2.17 6.67
2014 Nov 5.56 5.68 14.7 22.5 3.49 1.57 6.28
2014 Dec 7.07 7.07 16.2 25.5 3.64 1.95 7.91
2015 Jan 4.88 4.88 16.3 24.5 3.72 1.15 5.07
2015 Feb 6.16 6.55 17.2 23.5 3.60 1.77 7.29
2015 Mar 4.23 4.25 11.5 16.7 2.54 1.55 4.66
2015 Apr 4.48 4.48 12.4 17.4 2.37 1.90 5.02
2015 May 3.35 3.35 12.3 16.0 2.03 1.63 3.72
2015 Jun 4.86 4.86 12.2 19.0 2.46 2.02 5.46
2015 Jul 4.01 4.01 13.1 15.3 1.96 2.12 4.51
2015 Aug 4.98 4.98 16.9 20.6 2.80 1.85 5.61
2015 Sep 4.62 4.62 12.1 16.7 2.47 1.85 5.16
All Data 4.94 4.97 17.4 25.5 2.92 1.71 5.55
MoMM 5.09 5.12
Elim, Alaska Wind-Diesel Analysis Page | 20
Monthly time series, mean wind speeds (gap-filled wind data)
Daily wind profile (all data)
Probability Distribution Function
The probability distribution function (PDF), or histogram, of the Elim met tower site wind speed
indicates a shape curve dominated by moderate wind speeds and is somewhat reflective of a “normal”
shape curve, known as the Rayleigh distribution (Weibull k = 2.0), which is defined as the standard wind
distribution for wind power analysis. As seen below in the wind speed distribution of the 34 meter B
anemometer, the most frequently occurring wind speeds are between 3.0 and 6.0 m/s with no 10-
minute average wind events exceeding 20 m/s (note that the cutout speed of most wind turbines is 25
m/s; see following Occurrence by wind speed bin table).
Elim, Alaska Wind-Diesel Analysis Page | 21
PDF of 34 m B anemometer (all data)
Comparative Weibull k shape curve table
Weibull values table, 34m B anemometer
Weibull Weibull Proportion Power R
k c Mean Above Density Squared
Algorithm (-)(m/s)(m/s)7.985 m/s (W/m2)(-)
Maximum likelihood 1.71 5.55 4.95 0.436 169 0.960
Least squares 1.66 5.61 5.01 0.441 182 0.961
WAsP 1.86 5.69 5.05 0.459 163 0.953
Actual data (84,596 time steps) 4.97 0.459 163
Occurrence by wind speed bin (34 m B anemometer)
Bin Endpoints
(m/s)Occurrences
Cumu-
lative
Bin Endpoints
(m/s)Occurrences
Cumu-
lative
Lower Upper No.Percent Percent Lower Upper No.Percent Percent
0 1 5274 6.23% 6.2% 9 10 2862 3.38% 93.5%
1 2 7737 9.15% 15.4% 10 11 2129 2.52% 96.0%
2 3 10488 12.40% 27.8% 11 12 1612 1.91% 97.9%
3 4 11354 13.42% 41.2% 12 13 984 1.16% 99.0%
Elim, Alaska Wind-Diesel Analysis Page | 22
Bin Endpoints
(m/s)Occurrences
Cumu-
lative
Bin Endpoints
(m/s)Occurrences
Cumu-
lative
Lower Upper No.Percent Percent Lower Upper No.Percent Percent
4 5 10928 12.92% 54.1% 13 14 502 0.59% 99.6%
5 6 9907 11.71% 65.8% 14 15 213 0.25% 99.9%
6 7 9199 10.87% 76.7% 15 16 70 0.08% 100.0%
7 8 6868 8.12% 84.8% 16 17 21 0.02% 100.0%
8 9 4444 5.25% 90.1% 17 18 4 0.00% 100.0%
Cumulative distribution function
Wind Direction
Wind frequency rose data indicates that wind at the Elim met tower site is primarily bi-directional, with
northeasterly and southwesterly winds predominating. The mean value rose indicates that both
northeasterly and southwesterly winds are of relatively high intensity winds, but with more frequent
northeasterly winds, the dominant energy winds are from that direction.
Calm frequency, the percent of time that winds at the 34-meter level are less than 4 m/s, a typical cut-in
speed of larger wind turbines, was a high 41 percent during the 19-month test period.
Note that the wind rose measured at the met tower site correlates fairly well with that observed by the
automated weather station at the nearby Elim Airport, although airport winds are more northerly. This
is a curious anomaly, but AWS Truepower wind data validates the met tower site wind rose of prevailing
northeasterly winds.
Elim, Alaska Wind-Diesel Analysis Page | 23
Wind frequency rose Mean value rose
Wind energy rose
Elim, Alaska Wind-Diesel Analysis Page | 24
Elim Airport wind frequency rose
Wind Shear and Roughness
Wind shear at the Elim met tower site was calculated with the 34 m A and 20 m anemometers, both of
which were oriented east-northeast. The calculated power law exponent of 0.247 indicates high wind
shear at the site. The calculated surface roughness at the site is 0.74 m (the height above ground where
wind speed would be zero) for a roughness class of 3.66 (description: large city with tall buildings).
Clearly the dense trees to the north of the site dramatically affected the wind shear profile.
Vertical wind shear profile
Elim, Alaska Wind-Diesel Analysis Page | 25
Wind shear by direction sector graph
Extreme Winds
One method to estimate Vref, or the maximum 50 year (10-minute average) wind speed, is a Gumbel
distribution analysis modified for monthly maximum winds instead of annual maximum winds. Nineteen
months of data however are minimal at best and hence results should be viewed with caution.
Nevertheless, with data available the predicted Vref in a 50 year return period (in other words,
predicted to occur once every 50 years) by this method is 24.3 m/s. This easily classifies Elim as Class III
by International Electrotechnical Commission 61400-1, 3rd edition (IEC3) criteria.
Site extreme wind probability table, 34 m B data
Vref Gust IEC 61400-1, 3rd ed.
Period (years) (m/s) (m/s) Class Vref, m/s
3 18.5 25.7 I 50.0
10 21.4 29.7 II 42.5
20 22.1 30.7 III 37.5
30 23.4 32.4 S designer-
specified5024.3 33.7
100 25.5 35.4
average gust factor:1.39
A second technique to calculate extreme wind probability, Method of Independent Storms, yields a
similar calculation of (50 year return period) Vref = 19.4 m/s.
Elim, Alaska Wind-Diesel Analysis Page | 26
Method of Independent Storms
A third method, referred to as EWTS II (European Wind Turbine Standards II) ignores recorded peak
wind speeds and calculates Vref from the Weibull k factor. There are three variations of this method –
exact, Gumbel and Davenport – and for the Elim wind data Vref is calculated between 27.7 and 30.0 m/s.
EWTS II plot
Note that IEC extreme wind probability classification is one criteria – with turbulence the other – that
describes a site with respect to suitability for particular wind turbine models. Note that the IEC3 Class III
extreme wind classification indicates low potential for damaging winds and that turbines installed at this
location can be rated as IEC3 Class III.
Turbulence
The turbulence intensity (TI) at the Elim met tower site is quite high with a mean turbulence intensity of
0.15 and a representative turbulence intensity of 0.18 at 15 m/s wind speed, indicating turbulent air for
Elim, Alaska Wind-Diesel Analysis Page | 27
wind turbine operations. This equates to an International Electrotechnical Commission (IEC) 61400-1,
3rd Edition (2005) turbulence category A to B, which is the top and middle defined categories.
Turbulence table, wind speeds > 4 m/s
Turbulence rose
Turbulence intensity, all direction sectors
Elim, Alaska Wind-Diesel Analysis Page | 28
Turbulence intensity, 22.5° to 67.5° True
Turbulence intensity, 225° to 255° True
Temperature, Density, and Relative Humidity
Elim experiences warm summers and cold winters. Calculated mean air density of 1.285 kg/m
3 exceeds
the 1.219 kg/m
3 standard air density for 43-meter elevation by 5.4 percent. This is advantageous in wind
power operations as wind turbines produce more power at low temperatures (high air density) than at
standard temperature and density.
Temperature and density table
Temp Temp Density
Month Mean Min Max Mean Min Max Mean Min Max
(°C)(°C)(°C)(°F)(°F)(°F)(kg/m3)(kg/m3)(kg/m3)
Jan -11.7 -31.1 2.6 10.9 -24.0 36.7 1.344 1.272 1.451
Feb -9.4 -27.9 4.9 15.1 -18.2 40.8 1.331 1.261 1.431
Mar -11.3 -32.0 5.8 11.7 -25.6 42.4 1.341 1.257 1.456
Elim, Alaska Wind-Diesel Analysis Page | 29
Temp Temp Density
Month Mean Min Max Mean Min Max Mean Min Max
(°C)(°C)(°C)(°F)(°F)(°F)(kg/m3)(kg/m3)(kg/m3)
Apr -2.6 -21.8 13.1 27.3 -7.2 55.6 1.297 1.223 1.397
May 5.5 -5.0 23.2 41.9 23.0 73.8 1.258 1.181 1.308
Jun 10.7 -2.4 28.1 51.3 27.7 82.6 1.234 1.160 1.296
Jul 13.2 1.6 26.5 55.8 34.9 79.7 1.222 1.164 1.276
Aug 12.2 -1.6 25.2 54.0 29.1 77.4 1.227 1.170 1.291
Sep 8.0 -2.3 17.3 46.4 27.9 63.1 1.245 1.204 1.294
Oct -1.5 -11.1 9.3 29.3 12.0 48.7 1.290 1.239 1.339
Nov -4.2 -18.8 6.0 24.4 -1.8 42.8 1.304 1.254 1.380
Dec -9.0 -21.8 4.0 15.8 -7.2 39.2 1.328 1.264 1.396
Annual 0.0 -32.0 28.1 32.0 -25.6 82.6 1.285 1.160 1.456
Elim temperature boxplot graph
Wind Speed Scatterplot
The wind speed versus temperature scatterplot of the Elim met tower data indicates a fairly even
distribution of wind speeds at temperatures between approximately -25° C and 20° C. Color coding of
the scatterplot indicates that northeasterly winds tend to be cold (below freezing) and southwesterly
winds tend to be warm (near or above freezing).
Elim, Alaska Wind-Diesel Analysis Page | 30
Wind speed/temperature (color code indicates wind direction)
Solar Resource
The met tower was equipped with a pyranometer to measure the solar resource. Note in the Dmap
below that local apparent noon occurs at about 2:00 p.m. This is due to the unusual nature of the
Alaska time zone where western Alaska especially is significantly displaced from standard time zone
positioning. Also note the near 24 hours of daylight at summer solstice in June and the very low light
levels at winter solstice in December.
Pyranometer Dmap