HomeMy WebLinkAboutHoonah Energy Projects Concept Design Report - May 2009 - REF Grants 7040036, 7030019Hoonah Energy Projects May 29, 2009
Concept Design Report Alaska Energy and Engineering
i
EXECUTIVE SUMMARY
This report has been prepared by Alaska Energy and Engineering, Inc. (AE&E)
for the Alaska Energy Authority / Rural Energy Group (AEA/REG). The purpose
of this study is to provide a concept design and construction cost estimate for the
following potential local energy projects for the community of Hoonah:
Diesel Power Plant Replacement.
Three Potential Hydroelectric Generation Projects.
Diesel Generation Heat Recovery System.
Excess Hydroelectric Energy Recovery
Participants in the project include the City of Hoonah and the Inside Passage
Electric Cooperative (IPEC).
On Thursday October 19 and 20, 2006, David Lockard of the Alaska Energy
Authority / Rural Energy Group (AEA/REG) and John Dickerson of Alaska
Energy and Engineering (AE&E) traveled to Hoonah. The purpose of this site
visit was to meet with local officials as well as representatives of local and
regional organizations to identify and discuss potential energy infrastructure
projects within the community as well as to gather reconnaissance level
information for preparation of a Conceptual Design Report (CDR) for any
identified energy infrastructure projects.
The IPEC (originally THREA) power plant was constructed in 1977 and was
partially renovated after a fire in 1990. Existing generator No. 1 is an antiquated
Caterpillar model 398. Generators No. 2 and 3 are Caterpillar model 3512's with
approximately 75,000 total hours each. The interior walls are covered with
painted plywood up to a height of 8' with vinyl-encased fiberglass batt insulation
exposed above the plywood and across the ceiling. The exterior metal siding is
in fair condition but the exterior paint is in very poor condition and is peeling
badly. The area around the plant is poorly drained and the plant is prone to
flooding, especially during spring breakup.
A new power plant is proposed to be constructed on a raised gravel pad next to
the existing power plant. The new power plant will include two new generators,
one existing low-hour generator, one existing high-hour generator in good
condition (3,100kW total), state of the art automatic start/stop/paralleling
switchgear, remote radiators with variable speed control, a fire suppression
system, critical grade exhaust silencers and all required engine coolant piping
and ventilation equipment.
Three potential hydroelectric generation facilities are identified, one on Gartina
Creek, one on Water Supply Creek as well as one that is located on both Gartina
Creek and Water Supply Creeks (Combined G&WS Hydro). The proposed site
locations are all in close proximity to each other and are all located within four
miles of the community of Hoonah on or near existing gravel logging roads.
Each proposed hydroelectric facility includes: diversion structure(s); penstock(s);
hydroelectric power house(s); programmable automatic start/stop/paralleling
switchgear; approximately four miles of 12.5kV three-phase overhead
transmission line with fiber optic communication cable; and access roads to the
power house(s) and diversion structure(s).
The proposed generation heat recovery project would deliver recovered
generation heat to the swimming pool/gymnasium, school classroom building,
fire hall, senior center, senior apartments, and clinic, offsetting as much as
57,000 gallons of space heating diesel fuel annually. The project would include
a total of approximately 6,500 feet of buried 4” diameter arctic pipe as well as
heat exchangers, pumps and associated equipment located in the power plant
and the six identified community buildings.
Hoonah Energy Projects May 29, 2009
Concept Design Report Alaska Energy and Engineering
ii
The proposed excess hydroelectric energy recovery system would capture
otherwise wasted hydroelectric potential by using an electric boiler to add heat to
the diesel heat recovery system during times when excess hydroelectric potential
is available.
The proposed power plant and heat recovery system project schedule calls for
design and permitting to be completed by November 2009 and for construction to
occur between April and November 2010, with the new power plant fully
functional by December 2010.
The proposed hydroelectric facility and transmission line project schedule calls
for design and permitting to be completed by July 2011 and for construction to
occur between March and November 2012, with the hydroelectric facility fully
functional by December 2012.
Separate cost estimates have been prepared for the Power Plant Replacement
and Diesel Generation Heat Recovery System as well as each of the three
potential Hydroelectric Generation projects and the Excess Hydroelectric Energy
Recovery System. The estimated total project cost including all design,
supervision, inspection, permitting, with a 15% to 25% contingency for each
component is:
$2,791,000 Power Plant Replacement (3,100kW @ $900/kW)
$905,000 Generation Heat Recovery System
$4,710,000 Gartina Creek Hydroelectric Project (600kW)
$4,078,000 Water Supply Creek Hydroelectric Project (600kW)
$8,645,000 Combined G&WS Hydroelectric Project (1,300kW)
$100,000 Excess Hydroelectric Energy Recovery System
The following table summarizes the avoided fuel costs and simple payback
periods for the potential hydroelectric projects with and without energy recovery:
AVOIDED FUEL COST & SIMPLE PAY BACK OF POTENTIAL PROJECTS
Project Project
Cost
Annual
Avoided
Fuel,
Gallons
Annual
Value of
Avoided
Fuel,
$/Year (1)
Simple
Pay
Back
Period
Fuel
Cost
Avoided
Over 30
Years
Excess Hydro ER $.10M 12,500 $62,000 1.6 yrs $1.88M
Diesel HR $.91M 57,000 $285,000 3.2 yrs $8.55M
Gartina Hydro $4.71M 130,000 $650,000 7.3 yrs $19.5M
Gartina Hydro w/
Diesel HR $5.61M 176,000 $881,000 6.4 yrs $26.4M
Water Supply
Hydro $4.08M 134,000 $670,000 6.1 yrs $20.1M
Water Supply
Hydro w/ Diesel HR $4.98M 180,000 $900,000 5.5 yrs $27.0M
Combined Hydro $8.65M 215,000 $1,075,000 8.0 yrs $32.2M
Combined Hydro w/
Diesel HR &
Excess Hydro ER
$9.65M 257,000 $1,285,000 7.5 yrs $38.5M
1) Assume a future fuel cost of $5.00/Gallon
Hoonah Energy Projects May 29, 2009
Concept Design Report Alaska Energy and Engineering
iii
INDEX
Executive Summary......................................................................................Page i
Index .........................................................................................................Page iii
Acronyms and Abbreviations .......................................................................Page v
1.0 Introduction .......................................................................................... Page 1
1.1 Program Overview......................................................................... Page 1
1.2 Community Description ................................................................. Page 2
1.3 Site Investigation ........................................................................... Page 3
1.4 Code Analysis & Deficiencies........................................................ Page 3
2.0 Existing Facilities.................................................................................. Page 4
2.1 Power Plant................................................................................... Page 4
2.2 Power Distribution ......................................................................... Page 5
3.0 Community Power Demand ................................................................. Page 5
3.1 Estimated Future Load Growth...................................................... Page 5
3.2 Alternative Energy/Efficiency Improvements ................................. Page 5
4.0 Proposed Energy Infrastructure Project Descriptions........................... Page 6
4.1 Diesel Power Plant Replacement .................................................. Page 6
4.1.1 Generator Selection ................................................................ Page 7
4.1.2 Switchgear & SCADA.............................................................. Page 8
4.1.3 Power Plant Fuel System........................................................ Page 9
4.2 Three Potential Hydroelectric Projects .......................................... Page 9
4.2.1 Gartina Creek.........................................................................Page 10
4.2.2 Water Supply Creek...............................................................Page 11
4.2.3 Combined Gartina and Water Supply.....................................Page 11
4.2.4 Hydroelectric Power Utilization...............................................Page 12
4.2.5 Permitting...............................................................................Page 12
4.3 Heat Recovery System.................................................................Page 14
5.0 Site Selection & Control ......................................................................Page 15
5.1 Power Plant Site...........................................................................Page 15
5.2 Hydroelectric Project Area............................................................Page 15
5.3 Hydroelectric Intertie Route ..........................................................Page 15
5.4 Heat Recovery Pipeline Route......................................................Page 16
5.5 Site Control ...................................................................................Page 16
6.0 Permitting and Spill Response ............................................................Page 16
6.1 Environmental Assessment..........................................................Page 16
6.2 Fire Code......................................................................................Page 17
6.3 Spill Response..............................................................................Page 17
Hoonah Energy Projects May 29, 2009
Concept Design Report Alaska Energy and Engineering
iv
6.4 Air Quality Permit..........................................................................Page 17
6.5 Hydroelectric Project Permitting ...................................................Page 17
7.0 Construction Plan................................................................................Page 18
7.1 Local Job Skills.............................................................................Page 19
7.2 Local Equipment...........................................................................Page 19
7.3 Material Sources...........................................................................Page 19
8.0 Schedule .............................................................................................Page 19
8.1 Power Plant Replacement & Heat Recovery System Schedule ..Page 20
8.2 Hydroelectric Project Schedule.....................................................Page 20
9.0 Cost Estimate......................................................................................Page 20
Concept Design Drawings.....................................................................Appendix A
Construction Cost Estimates.................................................................Appendix B
Site Control Documents ...................................................................... Appendix C
Electrical Load Data............................................................................. Appendix D
2007 Hydroelectric Analysis and Revised Cost Estimate
by HDR Inc............................................................................................Appendix E
2002 Reconnaissance of Three Potential Hydro Sites
Near Hoonah by HydroWest Group LLC...............................................Appendix F
Supplement to June 2002 Hydroelectric Study By AP&T.....................Appendix G
Hoonah Energy Recovery Worksheet and Graphs.............................. Appendix H
Community Correspondence .................................................................Appendix I
Hoonah Energy Projects May 29, 2009
Concept Design Report Alaska Energy and Engineering
v
ACRONYMS AND ABBREVIATIONS
ADCCED AK Department of Commerce, Community and Econ. Development
ADEC Alaska Department of Environmental Conservation
AEA/REG Alaska Energy Authority/Rural Energy Group
AIDEA Alaska Industrial Development and Export Authority
CDR Conceptual Design Report
COE U. S. Army Corps of Engineers
DC Denali Commission
DOT (Alaska) Department of Transportation and Public Facilities
EPA U.S. Environmental Protection Agency
F Degrees Fahrenheit
FERC Federal Energy Regulatory Commission
GPM Gallons Per Minute
HUD Housing and Urban Development
IBC International Building Code
ICDBG Indian Community Development Block Grant
IFC International Fire Code
NEC National Electric Code
NFPA National Fire Protection Association
NFS Non-frost susceptible
RPSU Rural Power System Upgrade
SHPO State Historic Preservation office
SPCC Spill Prevention Control and Countermeasures
USCG United States Coast Guard
USCOE United States Army Corps of Engineers
USS United States Survey
Hoonah Energy Projects June 1, 2009
Concept Design Report Alaska Energy and Engineering
1
1.0 INTRODUCTION
This report has been prepared by Alaska Energy and Engineering, Inc. (AE&E)
for the Alaska Energy Authority / Rural Energy Group (AEA/REG). The purpose
of this study is to provide a concept design and construction cost estimate for the
following potential local energy projects for the community of Hoonah:
Diesel power plant replacement.
Four potential hydroelectric generation projects.
Generation heat recovery system.
Participants in the project include the City of Hoonah and the Inside Passage
Electric Cooperative (IPEC).
1.1 Program Overview
The Alaska Energy Authority (AEA), Rural Energy Group is pursuing grant funds
to upgrade rural bulk fuel tank farms and electric power systems. All project
components are dependent on available funding. Following is a brief outline of
the program:
Most of the funds are federal and provided through the Denali Commission
(DC). Other federal funding may be available from HUD (ICDBG) and the
Environmental Protection Agency (EPA). Additional funds may be available
from the State of Alaska, USDA, and loan financing.
In order to receive grant funds, each community must demonstrate that the
proposed facility will be sustainable by accepting a business plan. The
business plan shall describe who will own the facility, and how it will be
operated, maintained and replaced.
New energy projects are funded, designed, and constructed in three phases:
Phase 1, Conceptual Design; Phase 2, Design Completion; and Phase 3,
Construction.
During Phase 1, Conceptual Design, staff from AEA will visit a community,
discuss the program, and work with residents and the local government to
select sites for the new facilities.
At the completion of Phase 1 Conceptual Design, the community will be
requested to review and approve the location, capacity, and basic
configuration of the facilities as well as a draft business plan.
During Phase 2, Design Completion, the design for the new energy projects
will be completed. An environmental assessment will be prepared and site
control documented. A business plan will be prepared for signing.
Each community will be requested to provide “in kind” contributions as
available.
Project may include local hire and construction trade training programs,
subject to Denali Commission funding.
If the Denali Commission approves the business plan it will be circulated for
signature and construction procurement will start.
Hoonah Energy Projects June 1, 2009
Concept Design Report Alaska Energy and Engineering
2
Ineligible Projects: Funding is not available through AEA for buildings,
propane facilities, fuel tank trucks or trailers, fuel to fill the tank farm,
operation & maintenance costs, or residential tank upgrades. Loans for fuel
tank trucks and trailers may be available through USDA.
Training Available: AEA has several training programs available for
communities.
1.2 Community Description
Hoonah is located on the northeast coast of Chichagof Island, 40 air miles west
of Juneau. It lies at approximately 58.11° North Latitude and -135.44° West
Longitude. (Sec. 28, T043S, R061E, Copper River Meridian.) The area
encompasses 6.6 sq. miles of land and 2.1 sq. miles of water. Hoonah's
maritime climate is characterized by cool summers and mild winters. Summer
temperatures average 52 to 63; winter temperatures average from 26 to 39.
Temperature extremes have been recorded from -25 to 87. Annual precipitation
averages 100 inches, with 71 inches of snowfall. The population was estimated
at 861 residents in 2005. Local governments include a first class city and an IRA
council. Hoonah is located in the Sitka Recording District, the Hoonah City
School District, and the Sealaska Regional Native Corporation but is not within
an organized borough.
LOCATION MAP
Hoonah Energy Projects June 1, 2009
Concept Design Report Alaska Energy and Engineering
3
1.3 Site Investigation
On Thursday October 19 and 20, 2006, David Lockard of the Alaska Energy
Authority / Rural Energy Group (AEA/REG) and John Dickerson of Alaska
Energy and Engineering (AE&E) traveled to Hoonah. The purpose of this site
visit was to meet with local officials as well as representatives of local and
regional organizations to identify and discuss potential energy infrastructure
projects within the community as well as to gather reconnaissance level
information for preparation of a Conceptual Design Report (CDR) for any
identified energy infrastructure projects.
In addition to the field investigations, available information was obtained and
analyzed from the following sources:
Gartina Creek Project Reconnaissance Report, Harza Engineering, 1979
Concept Review Report, Gartina Creek Hydroelectric Project, HDR, 1998
Reconnaissance of Three Potential Hydroelectric Sites Near Hoonah Alaska,
Hydro West Group, LLC, 2002
Gartina Creek Hydrology & Power spreadsheet, AP&T, 2002
Comprehensive Renewable Energy Feasibility Study for Sealaska
Corporation, Springtyme Company, LLC, 2005
Hoonah Power Cost Equalization (PCE) fuel use data, FY2005-2007
Hoonah Power Plant SCADA system data, IPEC, 2005-2007
AEA Rural Utility Circuit Rider Field Trip Report
Other relevant data.
Additional information and input was obtained from the following individuals:
Windy Skaflestad, Mayor, City of Hoonah 945-3633
David Richards, Administrator, City of Hoonah 945-3663
Jan Supler, Vice President Retail Operations, Wards Cove (206) 323-3200
Steve Brown, General Manager, Hoonah Trading 945-3211
Tim McLeod, General Manager, AEL&P 463-6317
Corry Hildenbrand, Energy Resource Developer, AEL&P 463-6317
Jody Mitchell, General Manager, IPEC 789-3196
Keith Berggren, Generation Manager, IPEC 789-3196
Peter Bibb, Distribution Manager, IPEC 789-3196
Bob Butera, P.E., HDR 644-2000
Larry Coupe, P.E., AP&T (360) 385-1733
1.4 Code Analysis & Deficiencies
The following is a summary of existing power plant code analysis and
deficiencies observed during the site investigations.
Poor site drainage at existing power plant building causing seasonal flooding.
Antiquated / inefficient diesel genset #1 – expensive to maintain and operate.
Extremely high hours on gensets #2 & #3 – due for replacement soon.
Manual paralleling switchgear only.
Hoonah Energy Projects June 1, 2009
Concept Design Report Alaska Energy and Engineering
4
Exposed interior vinyl-encased fiberglass batt insulation absorbs oil vapors, is
difficult to clean and is a potential fire hazard.
No operational fire suppression system
Power plant building previously incurred severe fire damage
The concept design for all energy projects have been prepared to meet current
code and regulatory requirements, which include:
The 2006 Edition of the International Building Code (IBC).
The 2006 Edition of the International Fire Code (IFC) and currently adopted
Alaska State Fire Marshal Fire and Safety Regulations.
The 2006 Edition of the National Electrical Code (NEC).
The 2006 Edition of the National Electrical Safety Code (NESC).
40 CFR, Part 112.1-12, U.S. Environmental Protection Agency Spill
Prevention Requirements
2.0 EXISTING FACILITIES
The existing power plant and electrical distribution system were visually
examined to determine suitability for re-use. The following paragraphs
summarize findings for the community.
2.1 Power Plant
The IPEC (originally THREA) power plant was constructed in 1977 and was
partially renovated after a fire in 1990. It is located on the eastern edge of town
at the intersection of Gartina Highway and White Alice Site Road. The building is
a 40'Wx100'L metal-sided, pre-engineered steel frame structure that houses
three generators, an office and a warehouse. The interior walls are covered with
painted plywood up to a height of 8' with vinyl-encased fiberglass batt insulation
exposed above and across the ceiling. The exterior metal siding is in fair
condition but the exterior paint is in very poor condition and is peeling badly. The
concrete foundation, steel frame members and horizontal steel girts appear to be
in fair condition. According to the operator, the finish grade around the plant
does not drain well and the plant is prone to flooding, especially during spring
breakup. Previous attempts at grading the site to improve drainage have been
thwarted by the shallow bedrock associated with the rock quarry bottom on which
the plant was built.
There are three Caterpillar generators currently installed in the power plant. Unit
#1 is a model 398 with a capacity of 600kW at 1,200RPM. The 398 is an
antiquated pre-combustion design with poor fuel economy and increasingly
difficult availability of parts. This unit is used for emergency backup only and is
slated for replacement. Unit #2 is a model 3512 with a prime capacity of
1,100kW at 1,200RPM. Unit #3 is a model 3512 with a prime capacity of 855kW
at 1,200RPM. Units #2 and #3 each have approximately 75,000 total engine
hours.
Hoonah Energy Projects June 1, 2009
Concept Design Report Alaska Energy and Engineering
5
Engine cooling is with three remote radiators located outside at the front of the
power plant. Each generator is on a stand-alone cooling system with one
radiator. There is currently no generation heat recovery equipment installed.
Station service is provided by a metered 480V three phase load center as well as
an un-metered 120/208V three phase load center. The 5kV manual paralleling
switchgear was installed new in 1990 after a fire in the power plant damaged the
existing switchgear and one of the generators. The switchgear includes a
section for each of the three generators and a feeder/station service section.
2.2 Power Distribution
Power generation is currently at 4160V 3-phase and distribution is at
7200/12.47kV 3-phase. There are two separate community feeders with a
750kVA bank of pole-mounted transformers feeding the community grid to the
east of the power plant and a 750kVA pad-mount step-up transformer feeding the
community grid to the west of the power plant. The transformers and main
community feeder pole are located within the fenced area adjacent to the power
plant. These transformers appear to be original equipment with visible surface
rust and are probably due for replacement. Overall, the community overhead
distribution system is in good condition and no other distribution deficiencies
were identified.
3.0 COMMUNITY POWER DEMAND
Power consumption data was obtained from the Power Cost Equalization (PCE)
program and from the IPEC SCADA system for fiscal years 2005 through 2007.
Graphs are included in Appendix D. During these years total annual generation
ranged between 5.1 and 5.5 million kWhrs with an average annual load of
between 607kW and 628kW. Annual fuel consumption averaged 366,000
gallons. According to the SCADA data daily peak demand in FY 2007 ranged
from a low of 832kW to a high of 920kW. Daily minimum (nighttime) loads in FY
2007 ranged between 340kW and 460kW. Monthly and peak data were not
available for FY 2008 from either source. According to available PCE data, total
annual generation for FY 2008 was 5.0 million kWhrs.
3.1 Estimated Future Load Growth
It is important to evaluate the impact of planned infrastructure improvement
projects on an existing power generation system. New construction and other
community improvements can adversely impact the adequacy of existing
facilities.
Steady growth in Hoonah's summer peak loads and annual generation are likely
over time due to expected increases in tourism, a planned new subdivision
development and possible increases in the local wood processing industry. It is
possible that annual generation requirements could grow to over 6,000,000kWH
and peak demand loads could reach 1,000kW within five years.
3.2 Alternative Energy / Efficiency Improvements
Careful sizing and selection of new generators with advanced technology in
conjunction with the installation of new fully automatic paralleling switchgear and
Hoonah Energy Projects June 1, 2009
Concept Design Report Alaska Energy and Engineering
6
a continuous off-line engine preheat system will maximize the fuel efficiency of
the new diesel power plant.
An analysis of four potential hydroelectric projects is included in Section 4.2.
Analysis of a potential energy recovery/district heating project is included in
Section 4.3.
Used motor oil from a variety of sources including the power plant is currently
used for space heating at the City shop building.
The Alaska Energy Authority/Alaska Industrial Development and Export Authority
published a draft Rural Alaska Energy Plan dated December 31, 2002 as a
follow-up report to the previously released Screening Report of Alaska Rural
Energy Plan dated April 2001. The Screening Report evaluated a dozen
alternative energy technologies other than diesel engine heat recovery. Only
wind energy was identified as alternative energy technology warranting further
evaluation in the draft Rural Alaska Energy Plan. According to the Wind Energy
Resource Atlas of the United States the community of Hoonah is located within a
class 3 wind regime and is not a viable candidate for a wind energy program
using currently available technologies.
There are no other known practical energy sources, such as solid fuel or natural
gas, currently available at Hoonah. At this time, it appears that supplemental
hydroelectric generation, generation heat recovery and possibly additional end-
use conservation are the only viable fuel-saving technologies available for
Hoonah.
4.0 PROPOSED ENERGY INFRASTRUCTURE PROJECT DESCRIPTIONS
The following proposed facility descriptions are separated into three sections:
Section 4.1, "Diesel Power Plant Replacement" describes the proposed
construction of a new IPEC diesel power plant including a new building new
and refurbished generation equipment, switchgear, and controls.
Section 4.2, "Potential Hydroelectric Projects", describes three potential local
hydroelectric projects located near Hoonah. It also describes a potential
excess hydroelectric energy recovery system.
Section 4.3, "Diesel Generation Heat Recovery System", describes a potential
generation heat recovery project serving the school complex and other
community buildings.
4.1 Diesel Power Plant Replacement
Historically, the IPEC power plant has been the sole source of power generation
for Hoonah and it will likely continue to be the prime power source even if
hydroelectric or other alternative energy projects are developed.
Due to the age, condition and drainage issues of the existing building as well as
the total hours on the existing generators and equipment, the power plant should
be replaced. Keeping the existing plant on-line during construction of the new
plant will provide power to the community and will eliminate the project cost of
providing temporary power during construction. The new power plant building
Hoonah Energy Projects June 1, 2009
Concept Design Report Alaska Energy and Engineering
7
will be a pre-engineered metal building with concrete slab-on-grade foundation
co-located on the same lot and approximately 50 feet southwest of the existing
power plant. The operator’s room, switchgear room, and bathroom will be
located in the north end of the building. Radiators will be located on the west
side of the building beneath a covered area. An area site plan, power plant floor
plan and typical section are provided in Appendix A.
The following proposed items will modernize the power plant and the reliability,
fire prevention/protection, noise control, and operations of the electric utility:
Provide new electronically controlled diesel-generating units.
Provide new automatic paralleling switchgear and SCADA system with load
sharing/control capabilities for possible integration of hydroelectric generation.
Provide critical grade silencers on all generators.
Provide sound-insulated air intake and exhaust fan ducting.
Provide new radiators with variable speed motor controls.
Provide heat recovery / engine cooling system.
Provide redundant generator cooling systems to enhance plant reliability.
Provide fire suppression system.
Provide sound insulated control room.
A new code compliant 12,000-gallon double wall day tank with overfill protection
was installed in 2007 and will be used at the new plant.
4.1.1 Generator Selection
IPEC was recently notified that the have been awarded an RUS grant of
approximately $735,000 for purchase of a new generator for the Hoonah power
plant. It is our recommendation to apply these funds to the installation of a new
Caterpillar 3512C generator. If funding is available for spring 2010 construction it
would be most cost effective to install this unit directly into the new IPEC Hoonah
power plant. These grant funds could be considered a like-kind contribution by
IPEC to the RPSU project.
Proper sizing and selection of the diesel generators is critical to meet the electric
loads while minimizing fuel consumption. To meet the anticipated future electric
demands and to optimize the use of future hydroelectric power (if constructed),
the new diesel power plant will be equipped with four diesel generators.
Based on the projected loads the following generating units have been selected:
Unit No. 1: 550 kW, Caterpillar C18 Marine (new)
Unit No. 2: 550 kW, Caterpillar C18 Marine (new)
Unit No. 3: 1000 kW, Caterpillar 3512C (new RUS funded unit)
Unit No. 4: 1000 kW, Caterpillar 3512 (best unit from old power plant)
Benefits of this new generator combination include:
Provides adequate capacity to meet current and future peak loads.
Hoonah Energy Projects June 1, 2009
Concept Design Report Alaska Energy and Engineering
8
Units #1 or #2 will operate efficiently for nighttime loads as well as operating
efficiently in parallel with potential future hydroelectric.
Units #1 and #2 in parallel will meet present and near future peak loads.
Units #1 and #2 produce recoverable heat due to wet manifolds.
Units #2 or #3 are both capable of independently meeting the present and
near term peak load.
Any combination of generators can be operated in parallel to meet high future
peak loads.
Commonality of parts between units.
4.1.2 Switchgear & SCADA
The switchgear will be metal-clad switchgear with draw-out vacuum circuit
breakers consisting of six separate 36” wide sections. There will be one section
for each of the four generating units. The upper compartment will house the
generator controls and relays and the lower compartment will house the vacuum
breaker. There will be one separate section for the two feeders with the feeder
breakers “stacked”. There will also be one separate master section with the
master controls and metering.
The new switchgear will provide automatic paralleling and load control of the four
generating units. The load control system will monitor the electrical demand on
the generators and provide automatic selection of the most efficient generating
unit or combination of generating units to meet the demand. The switchgear will
automatically start the most suitable engine, bring it up to speed, automatically
synchronize the unit, and close the engine circuit breaker. When a unit is taken
off line, either for maintenance or due to a reduction in electric load, the
switchgear will automatically remove the unit from the bus and allow the engine
to cool down before shutdown. Generator controls and relaying will provide
complete protection and monitoring of each engine and generator.
The new switchgear controls and distribution connection will be designed for
incorporation and communication with any future alternative energy sources.
IPEC has recently standardized on a common utility supervisory control and data
acquisition (SCADA) system for all of its facilities. The new switchgear will
include the IPEC standard SCADA system for generation and distribution
monitoring. A desktop PC will be provided in the new plant operator’s office to
allow operator access and control of the different systems.
Hoonah Energy Projects June 1, 2009
Concept Design Report Alaska Energy and Engineering
9
4.1.3 Power Plant Fuel System
Based on historic fuel use and estimated future electric loads, it is proposed that
the power plant fuel storage system provide a nominal 7-day fuel supply based
on the following:
HOONAH POWER FUEL CONSUMPTION
Current Average Daily Use for Peak Month in Gallons (1) 1,200
Current Peak 7 Day Use in Gallons (1) 8,400
Approximate Net Usable Capacity of 12,000 Gallon Day Tank (2) 10,000
(1) From Hoonah Power FY07 PCE data – peak month August.
(2) 90% Maximum Fill, 12" Minimum Fuel Level.
The existing 12,000-gallon double wall day tank, piping and appurtenances,
installed new in summer 2007, will be reused for the new power plant. The day
tank is a shop built double wall, horizontal, welded steel tank built and labeled in
accordance with UL 142 and equipped with steel saddles and skids. The tank is
equipped to comply with EPA requirements for redundant overfill protection for
alternative secondary containment systems, and is equipped with a fill limiter,
clock gauge, gauge hatch, pressure vacuum whistle vent, and emergency
venting. The tank is top filled and equipped with a ground-level quick connect
and spill catch basin. The tank will be truck filled from the Wards Cove tank farm
typically once per week.
All piping will be schedule 80 steel. Each isolated section of piping will be
provided with pressure relieving devices to account for thermal expansion of
product caused by temperature fluctuations. Provisions for movement of the
piping caused by thermal expansion and contraction will be included. All valves
will be steel body industrial grade valves intended for use with fuels.
The new power plant, tanks, and piping will be enclosed within a chain link fence
with barbed wire top. Two each three foot wide man gates will be provided for
ingress and egress.
4.2 Potential Hydroelectric Projects
In June, 2002, Larry Coupe, P.E. of HydroWest Group, LLC, a subsidiary of
AP&T, published a report titled "Reconnaissance of Three Potential Hydroelectric
Sites Near Hoonah, Alaska". This report was commissioned by the City of
Hoonah and is included in Appendix F of this report. It was preceded by a
previous study titled "Gartina Creek Project - A Reconnaissance Report"
performed in 1979 by Harza Engineering for the Alaska Power Authority. A
review and update of the 1979 report titled "Concept Review Report, Gartina
Creek Hydroelectric Project" was performed in 1998 by HDR for the City of
Hoonah. The three hydroelectric prospects included in the 2002 HydroWest
report are identified as Gartina Creek, Water Supply Creek and Elephant Falls.
Water Supply Creek and Elephant Falls are both tributaries of Gartina Creek. All
flow data for these three drainages is transposed from the stream gage records
of the Kadashan River drainage near Tenakee which is very similar in geology,
precipitation, orientation and elevation to the three Hoonah sites.
Hoonah Energy Projects June 1, 2009
Concept Design Report Alaska Energy and Engineering
10
All available data regarding these potential hydroelectric projects, including the
mentioned reports, was forwarded to hydroelectric generation specialist Bob
Butera, P.E. at HDR, Inc. Mr. Butera was tasked with analyzing the information
along with available stream data and providing a cursory opinion on the
feasibility, constructability and reliability for each of the proposed projects. He
was also tasked with providing an updated and inflation adjusted cursory
budgetary cost estimate for the hydroelectric projects. The HDR, Inc. analyses
and revised 2009 cost estimates are included in Appendix E of this report.
After analyzing the reconnaissance studies and the HDR report, another potential
hydroelectric project was identified. The new project is a combination of Gartina
and Water Supply projects described in the 2002 HydroWest report with
additional modifications. Larry Coupe of AP&T performed an analysis and cost
estimate of this potential project in May, 2009. His report titled “Supplement to
the June 2002 Hydroelectric Study” is included in Appendix G of this report.
The following sections contain a cursory description of the three potential
hydroelectric projects identified as the most feasible and cost effective to
construct.
The Elephant Falls site mentioned in the HydroWest report is not being
considered for development at this time primarily due to the fact that it is located
in the Tongass National Forest. This would require a land swap with the federal
government and necessitate FERC licensing, both of which would add delay and
cost to the project.
4.2.1 Gartina Creek
The Gartina Creek project as described in the 2002 HydroWest report consists of
the following components:
A fifteen feet high concrete and rockfill diversion dam.
A concrete intake structure and sluiceway
A 54-inch diameter steel pipeline approximately 200 feet long from the intake
structure to the powerhouse.
A 20'x20'x25' high two level reinforced concrete powerhouse
A single turbine with 600kW three-phase generator.
Programmable automatic paralleling switchgear with remote control and
unattended operation capability.
A pad-mount disconnect switch and step-up transformer bank adjacent to the
powerhouse.
Approximately four miles of 12.5kV three-phase overhead transmission line to
an interconnection near the Hoonah airport.
An approximately 0.3 mile long access road to the intake structure and
powerhouse from an existing Forest Service road.
The Gartina Creek site is estimated to have an average annual flow of around
66 CFS, a maximum divertible flow of 140 CFS and a net head of 61 feet.
Using a flow-duration method, the maximum potential annual generation of
Hoonah Energy Projects June 1, 2009
Concept Design Report Alaska Energy and Engineering
11
this site was estimated in the HydroWest report to be 1,880,000kWH. The
estimated construction cost for the Gartina Creek site is $5.63 million based
on 2012 construction.
See “Hoonah Hydroelectric Study Review”, Appendix E and “2002
Reconnaissance of Three Potential Hydro Sites Near Hoonah”, Appendix F for a
more detailed analysis of this potential hydroelectric project.
4.2.2 Water Supply Creek
The Water Supply Creek project as described in the 2002 HydroWest report
consists of the following components:
An eight feet high concrete and rockfill diversion dam.
A concrete intake and sluiceway
A 5,500 feet long combination 24" diameter HDPE and 20" diameter steel
pipeline from the intake structure to the powerhouse.
A 20'x40'x15' high single story pre-engineered metal building powerhouse.
A single turbine with 600kW three-phase generator.
Programmable automatic paralleling switchgear with remote control and
unattended operation capability.
A pad-mount disconnect switch and step-up transformer bank adjacent to the
powerhouse.
Approximately four miles of 12.5kV three-phase overhead transmission line to
an interconnection near the Hoonah airport.
An approximately 0.25 mile long access road to the intake structure and
powerhouse from an existing Forest Service road.
The Water Supply Creek site is estimated to have an average annual flow of
around 9 CFS, a maximum divertible flow of 20 CFS and a net head of 400
feet. Using a flow-duration method, the maximum potential annual generation
of this site was estimated in the HydroWest report to be 1,820,000kWH. The
estimated construction cost for the Water Supply Creek site is $4.83 million
based on 2012 construction.
See “Hoonah Hydroelectric Study Review”, Appendix E and “2002
Reconnaissance of Three Potential Hydro Site Near Hoonah”, Appendix F for a
more detailed analysis of this potential hydroelectric project.
4.2.3 Combined Gartina Creek and Water Supply Creek
The Combined Gartina Creek and Water Supply Creek (Combined G&WS)
project as described in the Supplement to the June 2002 Hydroelectric Study
consists of the following components:
The diversion dam and intake structure for Water Supply Creek as previously
described.
The pipeline/penstock for Water Supply creek as previously described except
extended 3,200 feet to the Gartina Creek powerhouse.
Hoonah Energy Projects June 1, 2009
Concept Design Report Alaska Energy and Engineering
12
The diversion dam and intake structure for Gartina Creek as previously
described.
The penstock for Gartina Creek as previously described except downsized to
48” diameter.
The powerhouse for Gartina Creek as previously described except enlarged
to house the turbine and control system for Water Supply Creek.
An Ossberger-type impulse turbine for Gartina Creek as previously described
except down-sized to 500kW.
A twin-jet Pelton unit for Water Supply Creek as previously described except
increased to a capacity of approximately 800kW.
The rock weir and diffuser tailrace as previously described for Gartina Creek.
The substation and transmission line as previously described for Gartina
Creek except upgraded for the increased generating capacity.
Access roads as previously described for Gartina Creek and Water Supply
Creek except for the elimination of the Water Supply powerhouse access
road.
A 13kW energy recovery turbine at the City water tap on the Water Supply
penstock.
The Gartina component is estimated to have an average annual flow of
around 55 CFS, a maximum divertible flow of 120 CFS, a net head of 61 feet
and annual potential generation of 1,758,000kWhrs. The Water Supply
component is estimated to have an average annual flow of around 9 CFS, a
maximum divertible flow of 20 CFS, a net head of 581 feet (to be verified) and
annual potential generation of 2,476,000kWhrs. The maximum potential
annual generation of the combined G&WS project was estimated to be
4,344,000kWH, including 110,000kWhrs from the city water connection
energy recovery turbine. The estimated construction cost for the combined
G&WS project is $8.95 million based on 2012 construction.
See “Supplement to June 2002 Study”, Appendix G and “2002 Reconnaissance
of Three Potential Hydro Site Near Hoonah”, Appendix F for a more detailed
analysis of this potential hydroelectric project.
4.2.4 Hydroelectric Power Utilization
The design output for proposed hydroelectric installations must be compared to
actual community demand curves in order to determine the percent of potential
hydroelectric power that can be utilized. Community load profile data from the
IPEC power plant SCADA system was provided to AP&T in order to make this
determination for the various proposed projects. The design hydroelectric output
was compared against actual demand curves at 1% incremental values (10,000
comparisons per month). See “Supplement to the June 2002 Hydroelectric
Study”, Appendix G for a more complete description of the methodology used.
The comparison of design output to community load profile verified the
assumptions in the 2002 report that virtually all of the potential generation from
Hoonah Energy Projects June 1, 2009
Concept Design Report Alaska Energy and Engineering
13
either Gartina Creek (1,880,000kWhrs) or Water Supply Creek (1,820,000kWhrs)
would be utilized if only one of these projects were constructed.
The combined Gartina & Water Supply design output was also incrementally
compared to the community demand curves. The result of that comparison
shows an annual utilization of 3,009,000kWhrs or 71.7% of the 4,334,000kWhr
total potential generation. This leaves an un-used annual excess hydroelectric
capacity of approximately 1,331,000kWhrs.
A portion of the excess hydroelectric generation potential can be utilized to offset
heating fuel use by installing an electric boiler in the power house and feeding the
electrically heated water into the proposed diesel heat recovery system (see
Section 4.3 below). The boiler would be controlled by the switchgear PLC and
would come on only when excess hydroelectric generation was available. An
analysis of excess hydroelectric energy recovery in conjunction with the
combined Gartina & Water Supply project was conducted as part of the Hoonah
Energy Recovery Worksheet, Appendix H. This analysis assumes that the
swimming pool/gymnasium, high school, elementary school, fire hall, senior
center, senior apartments, and clinic are connected to the proposed diesel
generation heat recovery system. This electric boiler installation also enables
enhanced control of the hydroelectric system during transfers of load from
hydroelectric to diesel generation.
The following table summarizes hydroelectric utilization and excess hydroelectric
energy recovery for the proposed projects:
HYDROELECTRIC UTILIZATION & EXCESS HYDRO ENERGY RECOVERY
Potential
Annual
Hydroelectric
Generation,
kWH
Hydroelectric
Generation
Utilized
Annually,
kWH
Heating Fuel
Offset By
Excess Hydro
Energy
Recovery,
Gallons/Yr
Percent of
Annual Diesel
Generation
Offset Annually
(1)
Gartina Creek 1,820,000 1,820,000 0 34.5%
Water Supply
Creek 1,880,000 1,880,000 0 35.7%
Combined
G&WS 4,344,000 3,009,000 0 57.1%
Combined
G&WS With
Excess
Hydroelectric
Energy
Recovery
4,344,000 3,514,000 12,000 ---
(1) Assuming Average Annual Community Generation of 5,270,000kWhrs
Hoonah Energy Projects June 1, 2009
Concept Design Report Alaska Energy and Engineering
14
4.2.5 Permitting
The HydroWest report addresses permitting issues for each of these sites. The
Gartina Creek and Water Supply Creek projects would fall under the State of
Alaska small hydroelectric project exemption from Federal Energy Regulatory
Commission (FERC) jurisdiction.
The HydroWest report also addresses environmental issues for each of these
sites. The primary environmental concern is the possible impact on anadromous
and resident fish populations due to reduced in-stream flows between the intake
structure and the power house. Because Water Supply Creek is located above
Gartina Falls, no anadromous fish will be present and only resident fish
populations are of concern. The bypassed reach of stream for the Gartina Creek
project does include salmon pools at the base of the falls. This could result in
increased bypass flow requirements or significant increases in construction
costs.
4.3 Diesel Generation Heat Recovery
An analysis of available diesel heat recovery was conducted for the various
proposed projects as part of the Hoonah Energy Recovery Worksheet, Appendix
H. The proposed diesel heat recovery project consists of the following
components:
Heat recovery supply and return buried arctic pipe (approximately 6,500 feet
total of 4” diameter piping) located along Douglas Drive between the IPEC
power plant and the school complex.
Heating connections to the swimming pool/gymnasium, school classroom
building, fire hall, senior center, senior apartments, and clinic. These six
public facilities use approximately 60,000 gallons of diesel annually for space
and water heating
Six port heat exchanger, pumps and associated equipment in power plant.
Recovered heat BTU meter in the power plant.
Individual heat exchangers and associated equipment in each of the six
identified facilities’ boiler rooms.
Alarms for loss of flow, loss of pressure, and no load/backfeed condition with
annunciation in the power plant switchgear.
An overall area site plan showing the proposed heat recovery pipeline routing is
provided in Appendix A. Appendix H, Graph 1 shows the estimated annual and
monthly heating fuel saved by including diesel heat recovery in the various
proposed projects.
The following table lists the estimated diesel heat recovery heating fuel offsets
when coupled with the various proposed power generation projects:
Hoonah Energy Projects June 1, 2009
Concept Design Report Alaska Energy and Engineering
15
DIESEL HEAT RECOVERY
Heating Fuel
Saved,
Gallons/Yr
Diesel Heat Recovery With No Hydro Installation 57,000
Diesel Heat Recovery with Gartina Creek Hydro
Installation 46,000
Diesel Heat Recovery with Water Supply Creek
Hydro Installation 46,000
Diesel Heat Recovery with Combined G&WS
Hydro Installation 30,000
5.0 SITE SELECTION & CONTROL
Work for this project will be performed in four general areas: (1) The “Power
Plant Site”; (2) The "Hydroelectric Project Area"; (3) The “Hydroelectric Intertie
Route”; and (4) The “Heat Recovery Pipeline Route”. There are no known flood
hazards at any of these locations.
5.1 Power Plant Site
The proposed new power plant site is within a potion of Lot 2, U.S. Survey No.
4539, near the existing power plant as shown in Appendix A, Sheet M3. The new
power plant will be located approximately where the old abandoned IPEC tank
farm currently sits. The abandoned tank farm will be demolished by others prior
to the start of this project. The site will be leveled prior to construction of the
power plant building. It is unknown if an environmental site assessment of the
site will be required. See Appendix A, Sheet M3
5.2 Hydroelectric Project Area
All three identified potential hydroelectric projects, including drainages, access
roads, diversion dams and pipelines are located within an area encompassed by
Sections 11, 12, 13 & 14 of Township 44 South, Range 61 East, Copper River
Meridian. The proposed power house locations are all between three and four
miles from the center of Hoonah. See Appendix A, Sheet M1 and Appendix F,
Figures 1 & 3.
5.3 Hydroelectric Intertie Route
The proposed overhead transmission intertie will be routed cross country along
existing logging roads within Sections 34 and 35, Township 43 South, Range 61
East and Sections 2 and 11, Township 44 South, Range 61 East from the end of
the existing overhead distribution system near the airport to the powerhouse
sites. See Appendix A, Sheet M1 and Appendix F, Figures 1 & 3.
Hoonah Energy Projects June 1, 2009
Concept Design Report Alaska Energy and Engineering
16
5.4 Heat Recovery Pipeline Route
The proposed generation heat recovery pipeline mains are routed within the
Douglas Drive and Hemlock Drive road right-of-ways. Branch pipelines to the
senior housing complex and the clinic are within Lots 3 and 4 of Hillside
Subdivision. The branch pipeline to the fire hall is within Lot 3 of U.S. Survey
4539. Branch pipelines to the school building and gymnasium/pool complex are
within the school reserve parcel and Lot 9 of US Survey 736. See Appendix A,
Sheet M2
5.5 Site Control
A sight control opinion letter was written on February 18, 2008. A copy of the
letter is included in Appendix C.
The proposed new power plant site is vested in the City of Hoonah with a long
tern lease to IPEC and a sublease of a portion of the site to the State of Alaska,
Department of Military Affairs.
According to the HydroWest report, the proposed hydroelectric project(s) area is
vested in the Seaalaska Corporation.
Ownership of the hydroelectric intertie route is currently unknown but it is
expected that the City of Hoonah, the State of Alaska Department of
Transportation and the Seaalaska Corporation are among the vested owners.
The City of Hoonah has jurisdiction over the Douglas Drive and Hemlock Drive
dedicated rights of way for the entire route of the buried heat recovery pipeline.
The fire hall and clinic sites are vested in the City of Hoonah. The senior housing
complex appears to be vested in the Tlingit-Haida Regional Housing Authority but
further research will be required. The school/pool/gymnasium complex appears
to be vested in the Presbytery of Alaska but further research will be required.
6.0 PERMITTING AND SPILL RESPONSE
The proposed projects are subject to regulations of both State and Federal
agencies including the Alaska Coastal Management Program, the Alaska
Department of Environmental Conservation (ADEC), the Division of Fire
Prevention, and the U.S. Environmental Protection Agency.
6.1 Environmental Assessment
An Environmental Assessment (EA) will be completed prior to construction of the
proposed projects. An EA is required for all projects that are federally funded or
require a federal permit (such as a Corps of Engineers Wetlands Permit). The
EA determines whether there is a significant impact to the environment caused
by the project. As part of the EA, a Coastal Zone Management Project
Questionnaire will be completed and submitted to the Alaska Coastal
Management Program. The Coastal Zone Management Project Questionnaire
helps to identify state or federal permits that may be required.
Hoonah Energy Projects June 1, 2009
Concept Design Report Alaska Energy and Engineering
17
6.2 Fire Code
A Plan Review permit from the State Fire Marshal is required for the proposed
diesel and hydroelectric power plant projects. Final stamped design drawings will
be submitted to the Fire Marshal for review prior to construction. Plans will be
reviewed for conformance with the International Fire Code and related codes
including the International Building Code and the National Electrical Code. The
review process can take anywhere between 3 weeks to 6 months.
6.3 Spill Response
Because the power plant day tank has oil storage tanks in excess of 1,320
gallons it is subject to U.S. Environmental Protection Agency regulations. The
Spill Prevention Control and Countermeasures (SPCC) plan will be reviewed and
updated as required as part of this project.
6.4 Air Quality Permit
The existing plant operates under a Title V permit. A Title V permit is required for
facilities with potential to emit >250tpy of hazardous air contaminants (NOx) and
for Prevention of Significant Deterioration (PSD) facilities.
The existing Hoonah power plant consumes more than 330,000-gallons but less
than 825,000-gallons of diesel fuel annually, and therefore, does not emit
>250tpy of NOx. As such, the Hoonah plant does not need to operate under a
Title V permit. DEC has a General Permit that is intended for facilities that emit
between 100 and 250tpy annually.
The new power plant should be permitted as a GPA facility rather than a Title V
facility. A GPA permit is less costly than a Title V permit and the operational
requirements are less intrusive.
The following actions are recommended:
Continue to operate the existing power plant under the existing Title V
permit.
Apply for a Title I construction permit for the new power plant.
Apply for a GPA Operating Permit for the new plant.
Once the new plant is online and operational, and the old plant
decommissioned, IPEC will notify DEC of the "shut down" and the existing
Title V permit will be rescinded.
6.5 Hydroelectric Project Permitting
In addition to the EA requirements listed above, the hydroelectric portion of this
project will require the following separate permits/review process if built:
Alaska Department of Natural Resources
o Water Rights Permit
o Fish Habitat Permit
o Coastal Zone Management Consistency Review
Hoonah Energy Projects June 1, 2009
Concept Design Report Alaska Energy and Engineering
18
Federal Energy Regulatory Commission (FERC) license or waiver
Site control permits and/or easements for access to the site(s) and for
electric transmission line right of way.
7.0 CONSTRUCTION PLAN
The AEA/REG has a history of administering similar projects on a "modified"
force-account basis. Force-account construction involves the owner or grantee
acting as the employer and utilizing primarily local labor. This method tends to
achieve a higher percentage of local hire and is strongly supported by many
communities and funding agencies. The highly technical nature of power
generation and distribution projects requires a limited number of workers with
specific experience and expertise to be brought in for the project when not
available locally. All work must be supervised and managed by a superintendent
with extensive experience in the construction of rural power generation and
distribution systems. All specialty work, such as pipe welding and electrical
installation must be performed by skilled craftsmen with appropriate certifications.
An experienced construction manager will be required to recruit the necessary
skilled labor, coordinate the construction team, and oversee procurement and
project logistics. The design engineer will provide quality control through
communication with the construction manager and periodic on-site inspections.
The nature of the projects identified will allow most of the projects to be
constructed independently from the other. The power plant, generation heat
recovery system and hydroelectric projects are separate and will not necessarily
need to be constructed using the same construction management teams.
Because it will replace the existing power plant, the new power plant can be fully
completed, tested and energized with minimal impact to the existing power
system.
There are at least two options for shipping project construction materials and
equipment into Angoon:
Hoonah is on the Alaska Marine Highway (AMH) ferry system. Roll-on, roll-
off containers not exceeding 40 feet in length and 13 feet 6 inches in height
can be delivered by the ferry and off-loaded at the ferry dock. However, this
option would require the project to procure the rolling stock and to pay full fair
for the return leg of any empty trailers.
Alaska Marine Lines provides seasonal containerized freight service direct
from Seattle to Hoonah. Freight is off-loaded with a large fork lift at the
marine industrial center in the vicinity of the ferry dock. The cost estimate
and the project schedule have been developed on this basis. Containers are
available in 20, 24 and 40 foot lengths. Transporting the freight from the
marine industrial center to the construction site is the responsibility of the
project. IPEC has a tilt-bed winch trailer that would be available to the
project.
Hoonah Energy Projects June 1, 2009
Concept Design Report Alaska Energy and Engineering
19
7.1 Local Job Skills
The City was not able to provide information regarding the availability of specialty
skilled labor in Hoonah. Due to the relatively large population of this community
it is likely that there are a number of local residents with specialty skills and
general labor experience in various types of construction. It should be assumed
that at a minimum a project superintendent, a pipe welder/mechanical foreman, a
journeyman electrician, and a journeyman lineman will need to be brought into
Hoonah for this project.
7.2 Local Equipment
The City was not able to provide an inventory of locally available heavy
equipment. Calls to local contractors confirmed that there is a considerable
amount of heavy equipment in the community, including several 200 class
excavators, small and medium sized dozers, a 25-ton track crane and 10 yard
dump trucks. It is likely that a skid steer loader is the only piece of equipment
that will need to be imported into Hoonah.
Prior to the start of construction, an experienced fleet service mechanic will need
to go through the equipment with a local mechanic to ensure the equipment is in
proper operating condition.
7.3 Material Sources
Gravel will be required for pad development and finish grading at the proposed
diesel and hydroelectric power plant sites, for access roads to the hydroelectric
sites, for bedding material for heat recovery arctic pipe and for concrete
aggregate. There are stockpiles of blast material available in Hoonah. A small
screen is available locally that is capable of producing relatively small quantities
of structural fill as well as 1” minus gravel for arctic pipe bedding and finish
grading. No concrete aggregate is available in large quantities locally and will
need to be purchased in one yard super sacks and delivered to Hoonah by barge
from Seattle or Juneau.
8.0 SCHEDULE
The proposed project schedule is separated into two sections: Section 8.1,
"Power Plant Replacement and Diesel Heat Recovery System Schedule"; and
Section 8.2, "Hydroelectric Project Schedule". The schedules have been set to
take advantage of the best seasonal weather for most work. All schedules are
contingent on timely approval of the plan by all project participants and funding
agencies.
Hoonah Energy Projects June 1, 2009
Concept Design Report Alaska Energy and Engineering
20
8.1 Power Plant Replacement and Diesel Heat Recovery System Schedule
The following schedule has been developed on the basis of performing the majority
of the work on the power plant replacement and generation heat recovery project
during Spring/Summer 2010. This schedule is contingent on approval of the plan by
the project participants as well as on funding availability.
June-Nov 2009: Design, permitting, and site control.
Nov 2009 -Feb 2010: Order building, generators, switchgear, radiators, etc...
April 2010: Mobilization.
May-Dec 2010: Project construction.
Jan 2011: Project completion, power plant commissioning & operator training.
Feb 2011: O&M manuals and project close out.
8.2 Hydroelectric Project Schedule
The following schedule has been developed on the basis of performing the majority
of the work for the hydroelectric project during early spring through summer 2012.
This schedule assumes only one of the three potential hydroelectric projects is
funded and is contingent on timely approval of the plan by the project participants as
well as on funding availability.
June 2009-July 2011: Stream gauging, design, permitting, and site control.
Aug 2011: Order turbine, switchgear, building materials, etc.
Feb 2012: Project mobilization, startup.
Mar-Nov 2012: Project construction.
Dec 2012: Project completion, commissioning & operator training.
Jan 2013: O&M manuals and project close out.
9.0 COST ESTIMATE
The construction cost estimates have been developed based on a "modified"
force-account approach utilizing a combination of local labor, certified craftsmen,
and specialty sub-contractors under the direction of an experienced construction
manager. Labor rates are based on Title 36 equivalent wages for certified
specialty labor and prevailing local force-account wage rates for general labor
and equipment operation.
Hoonah Energy Projects June 1, 2009
Concept Design Report Alaska Energy and Engineering
21
Detailed cost estimates are included in Appendix B. Separate estimates have
been prepared for the Power Plant Replacement, Heat Recovery System and
each of the three potential hydroelectric projects. The estimated total project
cost including all design, supervision, inspection, permitting, and a 15%
contingency (power plant and heat recovery projects) or 25% to 33% contingency
(hydroelectric projects) is:
$2,791,000 Power Plant Replacement (3,100kW @ $900/kW)
$905,000 Diesel Generation Heat Recovery System
$4,710,000 Gartina Creek Hydroelectric Project (600kW)
$4,078,000 Water Supply Creek Hydroelectric Project (600kW)
$8,645,000 Combined G & WS Hydroelectric Project (1,300kW)
$100,000 Excess Hydroelectric Energy Recovery System
It is assumed that the operation and maintenance costs of hydroelectric power
generation and energy recovery systems will be comparable to that for diesel
generation. Therefore, the various project costs need to be compared to the
primary benefit, which is the avoided fuel cost. The following table summarizes
the avoided fuel costs and simple payback periods for the potential hydroelectric
projects with and without energy recovery:
AVOIDED FUEL COST & SIMPLE PAY BACK OF POTENTIAL PROJECTS
Project Project
Cost
Annual
Avoided
Fuel,
Gallons
Annual
Value of
Avoided
Fuel,
$/Year (1)
Simple
Pay
Back
Period
Fuel
Cost
Avoided
Over 30
Years
Excess Hydro ER $.10M 12,500 $62,000 1.6 yrs $1.88M
Diesel HR $.91M 57,000 $285,000 3.2 yrs $8.55M
Gartina Hydro $4.71M 130,000 $650,000 7.3 yrs $19.5M
Gartina Hydro w/
Diesel HR $5.61M 176,000 $881,000 6.4 yrs $26.4M
Water Supply
Hydro $4.08M 134,000 $670,000 6.1 yrs $20.1M
Water Supply
Hydro w/ Diesel HR $4.98M 180,000 $900,000 5.5 yrs $27.0M
Combined Hydro $8.65M 215,000 $1,075,000 8.0 yrs $32.2M
Combined Hydro w/
DHR & EHER $9.65M 257,000 $1,285,000 7.5 yrs $38.5M
1) Based on an assumed future fuel cost of $5.00/Gallon
APPENDIX A
CONCEPT DESIGN DRAWINGS
APPENDIX B
CONSTRUCTION COST ESTIMATES
ALASKA ENERGY ANDENGINEERINGHOONAH ENERGY PROJECTSDIESEL POWER PLANT COST ESTIMATE SUMMARY MAY 29, 2009CONCEPT DESIGN REPORTPOWER GENERATION UPGRADES $1,776,800MISCELLANEOUS $15,400OVERHEAD $146,858FREIGHT $95,880CONSTRUCTION SUB-TOTAL $2,034,938DESIGN AND CONSTRUCTION ADMIN. $200,000CONSTRUCTION MANAGEMENT $200,000PROJECT SUB-TOTAL $2,434,938CONTINGENCY $365,241 15 %TOTAL PROJECT COST (ROUNDED) $2,800,000TOTAL INSTALLED KW CAPACITY3,100 kWCOST PER KW OF INSTALLED CAPACITY $903B-1
ALASKA ENERGY ANDENGINEERINGHOONAH ENERGY PROJECTSDIESEL POWER PLANT COST ESTIMATEMAY 29, 2009CONCEPT DESIGN REPORTITEM QUAN UNIT UNIT MATLUNIT LAB LAB LABORCONTRFREIGHT TOTALUNIT TOTAL COST COST HRS HRS RATE COST COST COST COST WT WT(#)POWER GENERATION UPGRADESClear & Prep Site 1 lump $0 $0 250 250 $80 $20,000 $20,000 0Power Plant Foundation 125 cu.yd. $300 $37,500 4 500 $80 $40,000 $77,500 375,00044'x60' Metal Building 1 lump $150,000 $150,000 1000 1000 $80 $80,000 $230,000 43,000 43,000Water & Sewer Service to Bldg 1 lump $20,000 $20,000 200 200 $80 $16,000 $36,000 5,000 5,000Install Existing Cat 3512's 2 ea. $0 $5,000 200 400 $80 $32,000 $37,000 0550 kW Genset (Cat C18 Marine) 2 ea. $250,000 $500,000 120 240 $80 $19,200 $519,200 0125 VDC Battery Rack 1 ea. $15,000 $15,000 20 20 $80 $1,600 $16,600 5,000 5,000Switchgear 1 lump $250,000 $250,000 100 100 $80 $8,000 $258,000 30,000 30,0001000 kVA Step Up XFMR 2 ea. $30,000 $60,000 20 40 $80 $3,200 $63,200 14,000 28,00075 kVA Station Service XFMR 1 ea. $5,000 $5,000 10 10 $80 $800 $5,800 5,000 5,000Generation/Distribution Wiring 1 lump $20,000 $20,000 200 200 $80 $16,000 $36,000 5,000 5,000Fire Suppression 1 lump $100,000 $100,000 200 200 $80 $16,000 $116,000 2,000 2,000Ventilation 1 lump $30,000 $30,000 150 150 $80 $12,000 $42,000 3,000 3,000Radiators/Aftercoolers 6 ea. $20,000 $120,000 40 240 $80 $19,200 $139,200 3,000 18,000Engine Coolant Piping 1 lump $20,000 $20,000 250 250 $80 $20,000 $40,000 6,000 6,000Exhaust Silencers 3 ea. $5,000 $15,000 27 80 $80 $6,400 $21,400 500 1,500Exhaust Thimbles, Pipe, Etc 3 ea. $2,000 $6,000 27 80 $80 $6,400 $12,400 333 1,000Stn Service/Lighting/Wiring 1 lump $30,000 $30,000 240 240 $80 $19,200 $49,200 1,500 1,500Gen Fuel/Lube Oil Pipe & Fittings 1 lump $8,000 $8,000 60 60 $80 $4,800 $12,800 700 700Misc Strut, Hangers, Fasteners 1 lump $16,000 $16,000 80 80 $80 $6,400 $22,400 700 700Paint & Insulate Piping 1 lump $5,000 $5,000 60 60 $80 $4,800 $9,800 700 700Fill Coolant & Lube 1 lump $7,500 $7,500 60 60 $80 $4,800 $12,300 6,000 6,000MISCELLANEOUSSigns & Valve Tags 1 lump $1,000 $1,000 30 30 $80 $2,400 $3,400 100 100Misc Hardware 1 lump $2,000 $2,000 0 0 $80 $0 $2,000 500 500Misc Tools & Safety Gear 1 lump $5,000 $5,000 0 0 $80 $0 $5,000 500 500Welding Rod, Gases, Etc. 1 lump $5,000 $5,000 0 0 $80 $0 $5,000 1000 1000B-2
ALASKA ENERGY ANDENGINEERINGHOONAH ENERGY PROJECTSDIESEL POWER PLANT COST ESTIMATEMAY 29, 2009CONCEPT DESIGN REPORTITEM QUAN UNIT UNIT MATLUNIT LAB LAB LABORCONTRFREIGHT TOTALUNIT TOTAL COST COST HRS HRS RATE COST COST COST COST WT WT(#)OVERHEADAudit Grants 1 lump $6,000 $6,000ROW Legal Work 1 lump $5,000 $5,000 0Construction Insurance 1 lump $1,513 $1,513 0First Year Operation Insurance 1 lump $3,226 $3,226 0CM Prof. Liability Insurance 1 lump $4,450 $4,450 0Rent Heavy Equip 1 lump $20,000 $20,000 0Skid Steer Rent 6 mo. $12,000 $12,000 0Pickup Rent 6 mo. $3,600 $3,600 0Welder/Compr/Misc Tool Rent 1 lump $20,000 $20,000 0Project Diesel Fuel/Gasoline 1 lump $5,000 $5,000 0Load Test 40 hr 1 40 $90 $3,600 $3,600Commission/Train Operators 40 hr 1 40 $90 $3,600 $3,600Superintendent Overhd Off-Site 100 hr 1 100 $90 $9,000 $9,000Superintendent Overhd On-Site 100 hr 1 100 $90 $9,000 $9,000Crew Travel Time 120 hr 1 120 $90 $10,800 $10,800Crew Airfares 12 trips $10,800 $10,800Crew Per Diem 245 mn.dy $10,269 $10,269Housing Rent 6 mo. $9,000 $9,000FREIGHT539,200Barge Freight Seattle-Hoonah539200lb. $0.15 $80,880Misc Small Freight & Gold Streaks 1 lump $15,000 $15,000CONSTRUCTION SUB-TOTAL $1,433,000 4,890$395,200 $110,858$95,880 $2,034,938Engineering (Design & CCA) 1 lump$200,000Construction Management 1 lump$200,000PROJECT SUB-TOTAL $1,433,000$395,200 $510,858$95,880 $2,434,938Contingency15 % $365,241TOTAL PROJECT COST$2,800,178B-3
ALASKA ENERGY ANDENGINEERINGHOONAH ENERGY PROJECTSDIESEL HEAT RECOVERY SYSTEM COST ESTIMATE SUMMARY MAY 29, 2009CONCEPT DESIGN REPORTHEAT RECOVERY SYSTEM $494,200MISCELLANEOUS $101,900OVERHEAD $89,723FREIGHT $21,340CONSTRUCTION SUB-TOTAL $707,163DESIGN AND CONSTRUCTION ADMIN. $40,000CONSTRUCTION MANAGEMENT $40,000PROJECT SUB-TOTAL $787,163CONTINGENCY $118,074 15 %TOTAL PROJECT COST (ROUNDED) $905,000B-4
ALASKA ENERGY ANDENGINEERINGHOONAH ENERGY PROJECTSDIESEL HEAT RECOVERY SYSTEM COST ESTIMATEMAY 29, 2009CONCEPT DESIGN REPORTITEM QUAN UNIT UNIT MATLUNIT LAB LAB LABORCONTRFREIGHT TOTALUNIT TOTAL COST COST HRS HRS RATE COST COST COST COST WT WT(#)HEAT RECOVERY SYSTEMArctic Pipe & Fittings 6,500 ft. $45 $292,500 0.20 1300 $80 $104,000 $396,500 10 65,000PP Expansion Tank 1 lump $3,000 $3,000 10 10 $80 $800 $3,800 600 600PP Heat Exchanger 1 ea. $15,000 $15,000 80 80 $80 $6,400 $21,400 5,000 5,000PP HR Pumps, Piping & Devices 1 lump $15,000 $15,000 40 40 $80 $3,200 $18,200 800 800PP BTU Meter 1 ea. $4,500 $4,500 10 10 $80 $800 $5,300 100 100Secondary HX's, Piping & Devices 5 ea. $5,000 $25,000 60 300 $80 $24,000 $49,000 100 500MISCELLANEOUSContract Repair & Repave Roads 1 lump $0 $0 0 0 $80 $0 $75,000 $75,000 0 0Signs & Valve Tags 1 lump $2,000 $2,000 30 30 $80 $2,400 $4,400 100 100Misc Hardware 1 lump $5,000 $5,000 0 0 $80 $0 $5,000 500 500Misc Tools & Safety Gear 1 lump $7,500 $7,500 0 0 $80 $0 $7,500 500 500Welding Rod, Gases, Etc. 1 lump $10,000 $10,000 0 0 $80 $0 $10,000 2500 2500OVERHEADAudit Grants 1 lump $6,000 $6,000ROW Legal Work 1 lump $5,000 $5,000 0Construction Insurance 1 lump $1,513 $1,513 0CM Prof. Liability Insurance 1 lump $4,450 $4,450 0Heavy Equip Rent 1 lump $20,000 $20,000 0Skid Steer Rent 2 mo. $4,000 $4,000 0Pickup Rent 2 mo. $1,200 $1,200 0Welder/Compr/Misc Tool Rent 1 lump $20,000 $20,000 0Project Diesel Fuel/Gasoline 1 lump $5,000 $5,000 0Commission/Train Operators 20 hr 1 20 $90 $1,800 $1,800Superintendent Overhd Off-Site 40 hr 1 40 $90 $3,600 $3,600Superintendent Overhd On-Site 40 hr 1 40 $90 $3,600 $3,600Crew Travel Time 40 hr 1 40 $90 $3,600 $3,600Crew Airfares 4 trips $3,600 $3,600Crew Per Diem 80 mn.dy $3,360 $3,360Housing Rent 2 mo. $3,000 $3,000B-5
ALASKA ENERGY ANDENGINEERINGHOONAH ENERGY PROJECTSDIESEL HEAT RECOVERY SYSTEM COST ESTIMATEMAY 29, 2009CONCEPT DESIGN REPORTITEM QUAN UNIT UNIT MATLUNIT LAB LAB LABORCONTRFREIGHT TOTALUNIT TOTAL COST COST HRS HRS RATE COST COST COST COST WT WT(#)FREIGHT75,600Barge Freight Seattle-Hoonah 75600 lb. $0.15 $11,340 $11,340Misc Small Freight & Gold Streaks 1 lump $10,000 $10,000 $10,000CONSTRUCTION SUB-TOTAL $379,500 1,910 $154,200 $152,123 $21,340 $707,163Engineering (Design & CCA) 1 lump $40,000 $40,000Construction Management 1 lump $40,000 $40,000PROJECT SUB-TOTAL $379,500 $154,200 $232,123 $21,340 $787,163Contingency15 % $118,074TOTAL PROJECT COST$905,237B-6
ALASKA ENERGY ANDENGINEERINGHOONAH ENERGY PROJECTSGARTINA FALLS HYDROELECTRIC PROJECTCOST ESTIMATE SUMMARYMAY 29, 2009CONCEPT DESIGN REPORT1. ACCESS ROADS $89,0002. DIVERSION STRUCTURE $682,0003. POWER CONDUIT $203,0004. POWERHOUSE $1,116,0005. TRANSMISSION $341,0006. CONSTRUCTION SUB-TOTAL $2,431,0007. CONTINGENCY $608,000 25 %8. CONSTRUCTION + CONTINGENCIES $3,039,0009. DESIGN, SURVEYING, GEOTECHNICAL $455,850 15 %10. LISCENSING/PERMITTING $303,900 10 %11. CONSTRUCTION MANAGEMENT $151,950 5 %12. ESCALATION 2007 to 2012 (5 YR @ 5%/YR) $759,750 25 % See Note 213. CONSTRUCTION FINANCING (2 YR @ 10%/YR) $0 0 % See Note 314. TOTAL PROJECT COST (ROUNDED) $4,710,000Notes:1. See Hydroelectric Analysis and Revised Cost Estimate, Appendix E for additional cost estimate information. 2. Cost Estimate in Appendix E prepared for 2007construction. This estimate assumes 2012 construction.3. Cost Estimate in Appendix E includes 2 years of conventional financing. This estimate assumes grant funding.B-7
ALASKA ENERGY ANDENGINEERINGHOONAH ENERGY PROJECTSWATER SUPPLY CREEK HYDROELECTRIC PROJECTCOST ESTIMATE SUMMARYMAY 29, 2009CONCEPT DESIGN REPORT1. ACCESS ROADS $74,0002. DIVERSION STRUCTURE $158,0003. POWER CONDUIT $614,0004. POWERHOUSE $910,0005. TRANSMISSION $349,0006. CONSTRUCTION SUB-TOTAL $2,105,0007. CONTINGENCY $526,000 25 %8. CONSTRUCTION + CONTINGENCIES $2,631,0009. DESIGN, SURVEYING, GEOTECHNICAL $394,650 15 %10. LISCENSING/PERMITTING $263,100 10 %11. CONSTRUCTION MANAGEMENT $131,550 5 %12. ESCALATION 2007 to 2012 (5 YR @ 5%/YR) $657,750 25 % See Note 213. CONSTRUCTION FINANCING (2 YR @ 10%/YR) $0 0 % See Note 314. TOTAL PROJECT COST (ROUNDED) $4,078,000Notes:1. See Hydroelectric Analysis and Revised Cost Estimate, Appendix E for additional cost estimate information. 2. Cost Estimate in Appendix E prepared for 2007 construction. This estimate assumes 2012 construction.3. Cost Estimate in Appendix E includes 2 years of conventional financing. This estimate assumes grant funding.B-8
ALASKA ENERGY ANDENGINEERINGHOONAH ENERGY PROJECTSCOMBINED GARTINA WATER SUPPLY HYDROELECTRIC PROJECTCOST ESTIMATE SUMMARYMAY 29, 2009CONCEPT DESIGN REPORT1. ACCESS ROADS $172,0002. DIVERSION STRUCTURES $956,0003. POWER CONDUIT $1,636,0004. POWERHOUSE $2,027,0005. TRANSMISSION $409,0006. CONSTRUCTION SUB-TOTAL $5,200,0007. CONTINGENCY $1,300,000 25 %8. CONSTRUCTION + CONTINGENCIES $6,500,0009. DESIGN, SURVEYING, GEOTECHNICAL $195,000 15 %10. LISCENSING/PERMITTING $650,000 10 %11. CONSTRUCTION MANAGEMENT $325,000 5 %12. ESCALATION 2009 to 2012 (3 YR @ 5%/YR) $975,000 15 % See Note 213. CONSTRUCTION FINANCING $0 0 % See Note 314. TOTAL PROJECT COST (ROUNDED) $8,645,000Notes:1. See Supplement to 2002 Hydroelectric Study, Appendix G for additional cost estimate information. 2. Cost Estimate in Appendix G prepared for 2009 construction. This estimate assumes 2012 construction.3. Cost Estimate in Appendix G includes 5% for conventional financing. This estimate assumes grant funding.B-9
ALASKA ENERGY ANDENGINEERINGHOONAH ENERGY PROJECTSEXCESS HYDRO ENERGY RECOVERY SYSTEM COST ESTIMATE SUMMARY MAY 29, 2009CONCEPT DESIGN REPORTELECTRIC BOILERS, EQUIPMENT & INSTALLATION $45,000CONTROLS $15,000OVERHEAD $5,000FREIGHT $2,000CONSTRUCTION SUB-TOTAL $67,000DESIGN AND CONSTRUCTION ADMIN. $10,000CONSTRUCTION MANAGEMENT $10,000PROJECT SUB-TOTAL $87,000CONTINGENCY $13,050 15 %TOTAL PROJECT COST (ROUNDED) $100,000Notes:1. Assumes 2012 construction B-10
APPENDIX C
SITE CONTROL DOCUMENTS
APPENDIX D
ELECTRICAL LOAD DATA
HOONAH PCE DATA
Community
Fisc
Month
Fisc
Year Month
KWH
Gen
Fuel
Used
Avg Load
(kW)
Peak Load
(kW)
Efficiency
(kWH/Gal
Hoonah 1 2005 Jul 431,510 29,613 580 852 14.6
Hoonah 2 2005 Aug 443,879 30,904 597 824 14.4
Hoonah 3 2005 Sep 458,899 31,698 637 864 14.5
Hoonah 4 2005 Oct 418,215 28,976 562 820 14.4
Hoonah 5 2005 Nov 474,663 32,163 659 856 14.8
Hoonah 6 2005 Dec 443,462 30,080 596 900 14.7
Hoonah 7 2005 Jan 509,111 37,191 684 892 13.7
Hoonah 8 2005 Feb 443,292 28,562 660 864 15.5
Hoonah 9 2005 Mar 435,346 27,689 585 780 15.7
Hoonah 10 2005 Apr 430,065 26,805 597 812 16.0
Hoonah 11 2005 May 415,703 29,295 559 760 14.2
Hoonah 12 2005 Jun 414,147 28,712 575 800 14.4
ANNUAL TOTALS / AVERAGES 5318292 361688 607 835 14.7
Hoonah 1 2006 Jul 398,400 27,697 535 824 14.4
Hoonah 2 2006 Aug 462,325 31,378 621 848 14.7
Hoonah 3 2006 Sep 426,332 29,277 592 880 14.6
Hoonah 4 2006 Oct 449,975 28,112 605 776 16.0
Hoonah 5 2006 Nov 418,601 31,694 581 840 13.2
Hoonah 6 2006 Dec 424,994 29,126 571 832 14.6
Hoonah 7 2006 Jan 433,294 29,834 582 820 14.5
Hoonah 8 2006 Feb 444,085 30,063 661 868 14.8
Hoonah 9 2006 Mar 421,673 29,040 567 880 14.5
Hoonah 10 2006 Apr 434,842 30,189 604 740 14.4
Hoonah 11 2006 May 393,336 26,959 529 780 14.6
Hoonah 12 2006 Jun 396,675 32,277 551 800 12.3
ANNUAL TOTALS / AVERAGES 5104532 355646 583 824 14.4
Hoonah 1 2007 Jul 392,585 27,065 528 884 14.5
Hoonah 2 2007 Aug 530,755 36,045 713 900 14.7
Hoonah 3 2007 Sep 476,422 34,966 662 944 13.6
Hoonah 4 2007 Oct 472,728 33,067 635 832 14.3
Hoonah 5 2007 Nov 466,555 31,813 648 920 14.7
Hoonah 6 2007 Dec 483,615 31,399 650 860 15.4
Hoonah 7 2007 Jan 457,170 34,274 614 860 13.3
Hoonah 8 2007 Feb 423,287 28,510 630 876 14.8
Hoonah 9 2007 Mar 474,803 34,546 638 864 13.7
Hoonah 10 2007 Apr 454,991 30,333 632 796 15.0
Hoonah 11 2007 May 422,790 28,609 568 844 14.8
Hoonah 12 2007 Jun 444,061 29,543 617 832 15.0
ANNUAL TOTALS / AVERAGES 5499762 380170 628 868 14.5
D-1
D-2Hoonah Monthly kWH Generated 0100,000200,000300,000400,000500,000600,000Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May JunMonthkWH Generated200520062007
D-3Hoonah Peak kW Load01002003004005006007008009001000Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May JunMonthkW200520062007
D-4Hoonah Average kW Load0100200300400500600700800Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May JunMonthkW200520062007
D-5Hoonah Annual kWH Generated01,000,0002,000,0003,000,0004,000,0005,000,0006,000,0002005 2006 2007YearkWH
APPENDIX E
2007 HYDROELECTRIC ANALYSIS AND
REVISED COST ESTIMATE BY HDR, INC.
HDR Alaska, Inc. 2525 C Street
Suite 305
Anchorage, AK 99503
Phone (907) 644-2000
Fax (907) 644-2022
www.hdrinc.com
Page 1 of 4
Memo
To: Steve Stassel, AE&E
From: Bob Butera, HDR Project: Hoonah Hydroelectric Study
Review, Hoonah RPSU CDR-106
FINAL
CC:
Date: November 8, 2007 Job No: 201662/61482
Introduction
A 2002 hydroelectric study by HydroWest Group, LLC (HydroWest) titled "Reconnaissance of
Three Potential Hydroelectric Sites near Hoonah, Alaska" analyzed the feasibility of a 3 separate
hydroelectric projects for the community of Hoonah.
Alaska Energy and Engineering (AE&E) requested HDR Alaska, Inc. (HDR) to:
1. Review report and assess feasibility of proposed development of the three sites based on the
included hydrology, power calculations, permitting requirements and
conclusions/recommendations.
2. Review construction cost estimates for each of the three identified projects. Provide opinion
of constructability and recommended improvements to proposed construction. Update
construction costs as necessary to reflect hard-dollar bid with bonding and prevailing wage
rates. Cost estimate to be escalated for construction in 2009.
Background
The HydroWest report analyzed the feasibility of a 3 separate hydroelectric projects for the
community of Hoonah. Table 1 summarizes information on these three sites which was presented in
the HydroWest report.
Table 1 – Summary of Proposed Projects
Gartina Falls Water Supply Creek Elephant Falls
Location At 50 foot falls, 3 miles
upstream from tidewater.
Tributary of Gartina
Creek
Tributary of Gartina Creek
Drainage Area 10.1 square miles 1.39 square miles 0.66 square miles
Land Ownership Sealaska Corporation Sealaska Corporation US Forest Service
Diversion Elevation 200 feet 800 feet 1100 feet
Dam Height 15 feet 8 feet 8 feet
Capacity 600 kW 600 kW 600 kW
Net Head 61 feet 400 feet 800 feet
Design Flow 140 cfs 20 cfs 9.3 cfs
Penstock Diameter 54 inches 24/20 inches 18/15 inches
Penstock Length, Type 200 feet 5500 feet, HDPE/steel 3900 feet, HDPE/steel
Turbine Type Ossberger impulse Turgo or Ossberger or
Pelton
Turgo or Ossberger or
Pelton
Transmission Line 4 miles, 12.5 kV, OHE 4 miles, 12.5 kV, OHE 4 miles, 12.5 kV, OHE
Access roads 0.3 miles 0.25 miles 2.2 miles
Average annual generation
(assumes 0 instream flow
requirement)
1,880 MWh 1,820 MWh 1,780 MWh
2002 Estimated Construction
Cost
$3,271,000 (2002 Dollars) $2,786,000 (2002 Dollars) $3,337,000 (2002 Dollars)
HDR Alaska, Inc. 2525 C Street
Suite 305
Anchorage, AK 99503
Phone (907) 644-2000
Fax (907) 644-2022
www.hdrinc.com
Page 2 of 4
Hydrology
The method used by HydroWest to estimate the flows for the three projects was to use drainage area
and elevation correction factors to the existing streamflow record from Kadashan River above Hook
Creek near Tenakee (The HydroWest report incorrectly names this site Kadashan River near
Tenakee which is a different site with a larger drainage area.). Kadashan River above Hook Creek
near Tenakee at the gage site has a drainage area of 10.2 square miles and a period of record of 10
years from 1968 to 1978. The HydroWest report states that it has similar basin characteristics to the
three evaluated watersheds.
A previous evaluation of the Gartina Falls project (HDR, 1998) used flow data collected at Tonalite
Creek near Tenakee Springs. Tonalite Creek near Tenakee Springs is 20 miles south of Gartina
Creek and is very similar to Gartina Creek in all of its basin characteristics. Tonalite Creek at the
gage site has a drainage area of 14.5 square miles and a period of record of 20 years from 1968 to
1988.
Using data from Kadashan River above Hook Creek near Tenakee, the HydroWest report estimated
the average annual flow at the Gartina Creek site to be 66 cfs. Using data from Tonalite Creek near
Tenakee estimates the average annual flow at the Gartina Creek site to be 69 cfs. The two estimates
are very close. Further design work should use the Tonalite Creek record as it has twice the period
of record of the Kadashan River above Hook Creek site.
It is not necessary to collect streamflow information from Gartina Creek at any of the three proposed
sites. The existing long term record from nearby similar stream basins is sufficient for hydroelectric
planning and design.
Power Calculations
Data was not available to review the power calculations in detail. The method described appears
satisfactory. For the Gartina Falls site, the power output estimated by HydroWest was nearly
identical to the power output estimated by HDR.
Permitting Requirements
Permitting requirements described in the HydroWest report are correct. One permit not mentioned is
a State of Alaska Dam Safety permit that will be required for dams over 10 feet in height. This will
apply to the Gartina Falls project. This permit also requires inspection on a regular basis depending
on the classification of the dam leading to additional long term O&M costs.
General Discussion
The Gartina Creek project is a low head project on a fairly deeply incised stream that has a high peak
flow and high potential for bedload issues. All of these factors will lead to increased construction
and O&M costs. This project also has the potential for disruption of fish and mammal habitat and
the increased scrutiny and permitting issues that this will bring. An additional permit consideration
is that this project will have a dam with a height greater than 10 feet which will cause it to be
regulated under state jurisdiction, leading to increased operations costs.
The Water Supply Creek project is a moderate head project on a stream that is easily accessible and
appears not to have significant environmental issues. During design it should be investigated
whether the intake can be located at a higher elevation for additional power. During design tapping
the hydroelectric penstock for the city water supply should also be considered. This will allow the
powerhouse to be located at a lower elevation for greater head and will eliminate the increased O&M
HDR Alaska, Inc. 2525 C Street
Suite 305
Anchorage, AK 99503
Phone (907) 644-2000
Fax (907) 644-2022
www.hdrinc.com
Page 3 of 4
costs of a second intake. The construction of this project will need to consider provision of
continuous water supply to the City.
The Elephant Falls project is a higher head project with its intake at high elevation. This higher
elevation may cause difficult winter access and may be more problematic due to increased snowfall
at this elevation. This project has a significantly smaller drainage basin, with the potential to have
periods when the flow is insufficient for project operation. It is located on Forest Service land which
will require an FERC permit for construction.
Estimate of Cost
HydroWest provided an estimated cost for each of the proposed projects. These estimates were
updated based on the following assumptions:
The construction estimate and contingency factors provided by HydroWest in 2002 are
reasonable and accurate and were based on contractor bid and prevailing wage rates.
An inflation factor of 1.22 based on Engineering News Record construction cost index. (Year
2002 = 6538, July 2007 = 7959) is applied to the 2002 construction costs.
Design costs of 15%, construction management of 5%, and permitting varying from 5% to 15%
for the three projects depending on expected complexity of permitting.
Estimate includes escalation for construction in 2009 at a rate of 5% per year which is an average
of the past five years of construction cost escalation.
Estimate includes construction financing costs at a rate of 10% per year for 2 years.
Value of displaced diesel fuel is based on fuel price of $3.00 per gallon.
Table 2 – Estimate of Cost
Gartina Falls Water Supply Creek Elephant Falls
2007 Estimated Construction Cost $4,900,000 $4,200,000 $4,700,000
Annual Debt Service (30 yrs @ 6%) $350,000 $300,000 $320,000
Project Annual Energy (MWh/yr) 1750 1820 1780
First Year Energy Cost per kWh $0.23 $0.19 $0.22
Value of Displaced Diesel Fuel $404,000 $420,000 $411,000
Details of this estimate are attached. With a fuel price of $3.00 per gallon and assuming a typical
diesel generator efficiency of 13 kWh/gallon, the fuel cost for diesel generation is $0.23/kWh.
Neglecting diesel generator operational and maintenance costs, all of these projects will produce
power for less than or equal to the cost of diesel generation.
Conclusions and Recommendations
It is not necessary to collect additional streamflow data for the Gartina Falls or Water Supply
Creek projects. The existing 20-year record from Tonalite Creek is sufficient for hydroelectric
planning and design. If the Elephant Falls project were to be constructed, additional streamflow
data should be collected to verify that the flows from this basin were not too small to be usable.
All projects benefit from the existence of logging roads that provide some access to the sites.
Water Supply Creek and Gartina Creek require only short segments of road to access the intake
and powerhouse sites. Elephant Falls requires significant additional access roads.
Estimated project costs were increased 122 % since 2002 due to inflation. Diesel fuel costs have
increased 240% since 2002. A simple economic analysis shows that all of the sites will produce
power at a rate that is less than or equal to the current cost of diesel power.
HDR Alaska, Inc. 2525 C Street
Suite 305
Anchorage, AK 99503
Phone (907) 644-2000
Fax (907) 644-2022
www.hdrinc.com
Page 4 of 4
Hydroelectric projects provide communities with a reliable, alternative energy source that does
not require the use or handling of fossil fuels.
The cost of power generated from a hydroelectric facility will remain relatively constant over
time whereas diesel costs may continue to increase.
The Water Supply Creek site is the preferred site of the three sites. It is preferred for the
following reasons:
o It provides the least cost per kWh of power,
o The intake and powerhouse sites are easily accessible and appear to support
straightforward construction,
o The environmental issues associated with this project appear to be the least of the three
sites,
o The height of the dam will be lower than the threshold for dam safety regulation, and
o Combining this project with the city water supply could reduce overall operations cost for
the city.
Issues regarding the Water Supply Creek site that should be resolved in the next phase of this
project are
o Estimate of annual power using data from Tonalite Creek at Tenakee.
o Explore potential for locating an intake at a higher elevation.
o Consider providing city water supply from the hydroelectric penstock.
o Perform evaluation of fish resources in Water Supply Creek.
o Perform a jurisdictional wetlands analysis for the proposed site.
o Explore the issues of FERC jurisdiction over this project.
Subsequent construction of either of the Gartina Falls or the Elephant Falls sites would benefit
from the transmission line constructed for the Water Supply Creek project. Analysis of power
requirements should be done to ensure that the power generated by these additional projects
would be needed by the City.
HOONAH "GARTINA FALLS" HYDROELECTRIC PROJECT
RECONNAISSANCE LEVEL COST ESTIMATE
2002 2007
Item Description Estimate Factor Estimate
1 Access Roads 73,000$ 122% $89,000
2 Diversion Structure 560,000$ 122% $682,000
3 Power Conduit 167,000$ 122% $203,000
4 Powerhouse
4.1 Structures and Improvements 292,000$ 122% $355,000
4.2 Generating Equipment 250,000$ 122% $304,000
4.3 Control System 375,000$ 122% $457,000
5 Transmission 280,000$ 122% $341,000
TOTAL DIRECT CONSTRUCTION COSTS 1,997,000$2,431,000$
Contingency 25% 499,000$608,000$
TOTAL DIRECT CONSTRUCTION COSTS + CONTINGENCIES 2,496,000$3,039,000$
Design Engineering, Surveying & Geotechnical 15% 455,850$
Licensing/Permitting 10% 303,900$
Construction Management 5% 151,950$
Escalation 2007 to 2009 (2 years at 5% per year)10% 303,900$
Construction Financing (2 years at 10% per year)20% 607,800$
TOTAL OTHER COSTS 1,823,400$
TOTAL CONSTRUCTION COSTS (2007 DOLLARS, ROUNDED)4,900,000$
Plant Max. Output (kW) 600
Project Annual Energy (MWh/yr) 1,750
Cost per installed kW $8,167
Annual Debt Service (30 yr @ 6%, 100% financing of entire project cost) $352,536
Annual O&M Allowance $50,000
First Year Energy Cost per kWh $0.23
Diesel Fuel Cost 3.00$ Gallon
Diesel Efficiency 13.0 kWh/gallon
Value of Displaced Diesel Fuel 403,846$
HOONAH "WATER SUPPLY CREEK" HYDROELECTRIC PROJECT
RECONNAISSANCE LEVEL COST ESTIMATE
2002 2007
Item Description Estimate Factor Estimate
1 Access Roads 61,000$ 122% $74,000
2 Diversion Structure 130,000$ 122% $158,000
3 Power Conduit 504,000$ 122% $614,000
4 Powerhouse
4.1 Structures and Improvements 122,000$ 122% $149,000
4.2 Generating Equipment 250,000$ 122% $304,000
4.3 Control System 375,000$ 122% $457,000
5 Transmission 287,000$ 122% $349,000
TOTAL DIRECT CONSTRUCTION COSTS 1,729,000$2,105,000$
Contingency 25% 432,000$526,000$
TOTAL DIRECT CONSTRUCTION COSTS + CONTINGENCIES 2,161,000$2,631,000$
Design Engineering, Surveying & Geotechnical 15% 394,650$
Licensing/Permitting 10% 263,100$
Construction Management 5% 131,550$
Escalation 2007 to 2009 (2 years at 5% per year)10% 263,100$
Construction Financing (2 years at 10% per year)20% 526,200$
TOTAL OTHER COSTS 1,578,600$
TOTAL CONSTRUCTION COSTS (2007 DOLLARS, ROUNDED)4,200,000$
Plant Max. Output (kW) 600
Project Annual Energy (MWh/yr) 1,820
Cost per installed kW $7,000
Annual Debt Service (30 yr @ 6%, 100% financing of entire project cost) $302,173
Annual O&M Allowance $50,000
First Year Energy Cost per kWh $0.19
Diesel Fuel Cost 3.00$ Gallon
Diesel Efficiency 13.0 kWh/gallon
Value of Displaced Diesel Fuel 420,000$
HOONAH "ELEPHANT FALLS" HYDROELECTRIC PROJECT
RECONNAISSANCE LEVEL COST ESTIMATE
2002 2007
Item Description Estimate Factor Estimate
1 Access Roads 313,000$ 122% $381,000
2 Diversion Structure 132,000$ 122% $161,000
3 Power Conduit 350,000$ 122% $426,000
4 Powerhouse
4.1 Structures and Improvements 102,000$ 122% $124,000
4.2 Generating Equipment 250,000$ 122% $304,000
4.3 Control System 375,000$ 122% $457,000
5 Transmission 287,000$ 122% $349,000
TOTAL DIRECT CONSTRUCTION COSTS 1,809,000$2,202,000$
Contingency 33% 597,000$727,000$
TOTAL DIRECT CONSTRUCTION COSTS + CONTINGENCIES 2,406,000$2,929,000$
Design Engineering, Surveying & Geotechnical 15% 439,350$
Licensing/Permitting 10% 292,900$
Construction Management 5% 146,450$
Escalation 2007 to 2009 (2 years at 5% per year)10% 292,900$
Construction Financing (2 years at 10% per year)20% 585,800$
TOTAL OTHER COSTS 1,757,400$
TOTAL CONSTRUCTION COSTS (2007 DOLLARS, ROUNDED)4,700,000$
Plant Max. Output (kW) 600
Project Annual Energy (MWh/yr) 1,780
Cost per installed kW $7,833
Annual Debt Service (30 yr @ 6%, 100% financing of entire project cost) $338,146
Annual O&M Allowance $50,000
First Year Energy Cost per kWh $0.22
Diesel Fuel Cost 3.00$ Gallon
Diesel Efficiency 13.0 kWh/gallon
Value of Displaced Diesel Fuel 410,769$
APPENDIX F
2002 RECONNAISSANCE OF THREE POTENTIAL HYDROELECTRIC
SITES NEAR HOONAH BY HYDROWEST LLC
APPENDIX H
HOONAH ENERGY RECOVERY WORKSHEET AND GRAPHS
HOONAH ENERGY RECOVERY WORK SHEET ====================================== =========Analysis of Diesel HR (No Hydro Installation)ANNUAL FUEL SAVINGS:AnnualO&M cost:0$/year. [ =============================================]Cost Estimate$ [ Diesel HR, Gallons:56936]Fuel heat value:138000Btu/gall. [ =============================================]Fuel cost0.00$/gallonFuel cost escal.0/yearPower increase0/yearDiscount rate0/yearGEN DATA: Jacket Water OnlySYSTEM LOSS DATA:Heat rate at kw-load above0 2800Btu/kwhConstant losses:Heat rate at kw-load above114 2800Btu/kwh Plant piping:15000Btu/hr. Piping main insulated, branch piping &flexes bareHeat rate at kw-load above152 2800Btu/kwh Buried Arctic piping:195000Btu/hr.(6500' of 4" @ 0.25)*(170F-50F)Heat rate at kw-load above176 2800Btu/kwhGenset Eng. Preheat:20000Btu/hr. Pre-heat 2 offline enginesHeat rate at kw-load above205 2800Btu/kwhTotal constant:230000Btu/hr.Heat rate at kw-load above255 2800Btu/kwhHeat rate at kw-load above375 2800Btu/kwhVariable losses:Heat rate at kw-load above465 2800Btu/kwh Radiators/Exter Pipe100Btu/hr.xFAmot normally closed, 1/2" normally open bypassHeat rate at kw-load above400 2800Btu/kwh Plant Heating:75Btu/hr.xFControl only, gen room heated by running engineHeat rate at kw-load above4502200Btu/kwhOther0Btu/hr.xFHeat rate at kw-load above5002200Btu/kwhGENERATION DATA:WEATHER DATA: NOTES:Kwh/month:HDD/Month: HonnahJanuary498,0001108February438,000944March433,000961April420,000756May410,000531June397,000330July436,000249August428,000242September455,000423October428,000695November416,000933December447,00010365206000 8208BUILDING DATA:Fuel use, Non- BoilergallonsSeasonalSeasonalEfficiency Building in use, 1=yes, 0=noOPER.HDDBuildings35600 2800 75%1 1 1 1 1 0 0 1 1 1 1 1107630Pool14400 7200 75%1 1 1 1 1 1 1 0 1 1 1 1117967H-1
HOONAH ENERGY RECOVERY WORK SHEET ====================================== =========Analysis ofGartinaCreek Hydro & Diesel HRANNUAL FUEL SAVINGS:AnnualO&M cost:0$/year. [ =============================================]Cost Estimate$ [ Diesel HR, Gallons:46316]Fuel heat value:138000Btu/gall. [ Excess Hydro Energy Recovery, Gallons0]Fuel cost0.00$/gallon [ Diesel Generation Fuel Savings,Gallons130000]Fuel cost escal.0/year [ Total Potential Fuel Savings176316]Power increase0/year [ =============================================]Discount rate0/yearGEN DATA: Jacket Water OnlySYSTEM LOSS DATA:Heat rate at kw-load above0 2800Btu/kwhConstant losses:Heat rate at kw-load above114 2800Btu/kwh Plant piping:15000Btu/hr. Piping main insulated, branch piping &flexes bareHeat rate at kw-load above152 2800Btu/kwh Buried Arctic piping:195000Btu/hr.(6500' of 4" @ 0.25)*(170F-50F)Heat rate at kw-load above176 2800Btu/kwhGenset Eng. Preheat:20000Btu/hr. Pre-heat 2 offline enginesHeat rate at kw-load above205 2800Btu/kwhTotal constant:230000Btu/hr.Heat rate at kw-load above255 2800Btu/kwhHeat rate at kw-load above375 2800Btu/kwhVariable losses:Heat rate at kw-load above465 2800Btu/kwh Radiators/Exter Pipe100Btu/hr.xFAmot normally closed, 1/2" normally open bypassHeat rate at kw-load above400 2800Btu/kwh Plant Heating:75Btu/hr.xFControl only, gen room heated by running engineHeat rate at kw-load above4502200Btu/kwhOther0Btu/hr.xFHeat rate at kw-load above5002200Btu/kwhDIESELGENERATION DATA:WEATHER DATA: HYDROELECTRICGENERATION DATAGENERATION FUEL SAVINGSKwh/month:HDD/Month: HoonahKwh/month:(@14kWhr/gallon diesel efficiency)January397,4711108January100,5297181February337,471944February100,5297181March326,188961March106,8127629April224,177756April195,82313987May128,309531May281,69120121June223,168330June173,83212417July366,886249July69,1144937August360,980242August67,0204787September302,112423September152,88810921October171,441695October256,55918326November237,979933November178,02112716December309,8181036December137,18297993386000 8208 1820000kWhr130000gallonsBUILDING DATA:Fuel use, Non- BoilergallonsSeasonalSeasonalEfficiency Building in use, 1=yes, 0=noOPER.HDDBuildings35600 2800 75%1 1 1 1 1 0 0 1 1 1 1 1107630Pool14400 7200 75%1 1 1 1 1 1 1 0 1 1 1 1117967H-2
HOONAH ENERGY RECOVERY WORK SHEET ====================================== =========Analysis of Water SupplyCreek Hydro & Diesel HRANNUAL FUEL SAVINGS:AnnualO&M cost:0$/year. [ =============================================]Cost Estimate$ [ Diesel HR, Gallons:45767]Fuel heat value:138000Btu/gall. [ Excess Hydro Energy Recovery, Gallons0]Fuel cost0.00$/gallon [ Diesel Generation Fuel Savings,Gallons134286]Fuel cost escal.0/year [ Total Potential Fuel Savings180053]Power increase0/year [ =============================================]Discount rate0/yearGEN DATA: Jacket Water OnlySYSTEM LOSS DATA:Heat rate at kw-load above0 2800Btu/kwhConstant losses:Heat rate at kw-load above114 2800Btu/kwh Plant piping:15000Btu/hr. Piping main insulated, branch piping &flexes bareHeat rate at kw-load above152 2800Btu/kwh Buried Arctic piping:195000Btu/hr.(6500' of 4" @ 0.25)*(170F-50F)Heat rate at kw-load above176 2800Btu/kwhGenset Eng. Preheat:20000Btu/hr. Pre-heat 2 offline enginesHeat rate at kw-load above205 2800Btu/kwhTotal constant:230000Btu/hr.Heat rate at kw-load above255 2800Btu/kwhHeat rate at kw-load above375 2800Btu/kwhVariable losses:Heat rate at kw-load above465 2800Btu/kwh Radiators/Exter Pipe100Btu/hr.xFAmot normally closed, 1/2" normally open bypassHeat rate at kw-load above400 2800Btu/kwh Plant Heating:75Btu/hr.xFControl only, gen room heated by running engineHeat rate at kw-load above4502200Btu/kwhOther0Btu/hr.xFHeat rate at kw-load above5002200Btu/kwhDIESELGENERATION DATA:WEATHER DATA: HYDROELECTRICGENERATION DATAGENERATION FUEL SAVINGSKwh/month:HDD/Month: HoonahKwh/month:(@14kWhr/gallon diesel efficiency)January388,1581108January109,8427846February329,848944February108,1527725March322,313961March110,6877906April219,749756April200,25114304May129,480531May280,52020037June226,322330June170,67812191July365,025249July70,9755070August350,266242August77,7345552September286,857423September168,14312010October160,154695October267,84619132November241,942933November174,05812433December305,8871036December141,113100803326000 8208 1880000kWhr134286gallonsBUILDING DATA:Fuel use, Non- BoilergallonsSeasonalSeasonalEfficiency Building in use, 1=yes, 0=noOPER.HDDBuildings35600 2800 75%1 1 1 1 1 0 0 1 1 1 1 1107630Pool14400 7200 75%1 1 1 1 1 1 1 0 1 1 1 1117967H-3
HOONAH ENERGY RECOVERY WORK SHEET ====================================== =========Analysis ofCombined Hydro, Diesel HR and Excess Hydro Energy RecoverANNUAL FUEL SAVINGS:AnnualO&M cost:0$/year. [ =============================================]Cost Estimate$ [ Diesel Heat Recovery, Gallons29606]Fuel heat value:138000Btu/gall. [ Excess Hydro Energy Recovery, Gallons0]Fuel cost0.00$/gallon [ Diesel Generation,Gallons214929]Fuel cost escal.0/year [ Total Potential Fuel Savings244535]Power increase0/year [ =============================================]Discount rate0/yearGEN DATA: Jacket Water OnlySYSTEM LOSS DATA:Heat rate at kw-load above0 2800Btu/kwhConstant losses:Heat rate at kw-load above114 2800Btu/kwh Plant piping:15000Btu/hr. Piping main insulated, branch piping &flexes bareHeat rate at kw-load above152 2800Btu/kwh Buried Arctic piping:195000Btu/hr.(6500' of 4" @ 0.25)*(170F-50F)Heat rate at kw-load above176 2800Btu/kwhGenset Eng. Preheat:20000Btu/hr. Pre-heat 2 offline enginesHeat rate at kw-load above205 2800Btu/kwhTotal constant:230000Btu/hr.Heat rate at kw-load above255 2800Btu/kwhHeat rate at kw-load above375 2800Btu/kwhVariable losses:Heat rate at kw-load above465 2800Btu/kwh Radiators/Exter Pipe100Btu/hr.xFAmot normally closed, 1/2" normally open bypassHeat rate at kw-load above400 2800Btu/kwh Plant Heating:75Btu/hr.xFControl only, gen room heated by running engineHeat rate at kw-load above4502200Btu/kwhOther0Btu/hr.xFHeat rate at kw-load above5002200Btu/kwhDIESELGENERATION DATA:WEATHER DATA: HYDROELECTRICGENERATION DATAGENERATION FUEL SAVINGSKwh/month:HDD/Month: HoonahKwh/month:(@14kWhr/gallon diesel efficiency)January313,0001108January186,00013286February253,000944February185,00013214March238,000961March196,00014000April93,000756April326,00023286May68,000531May404,00028857June115,000330June282,00020143July287,000249July149,00010643August293,000242August135,0009643September201,000423September254,00018143October58,000695October370,00026429November130,000933November286,00020429December211,0001036December236,000168572260000 8208 3009000kWhr214929gallonsBUILDING DATA:Fuel use, Non- BoilergallonsSeasonalSeasonalEfficiency Building in use, 1=yes, 0=noOPER.HDDBuildings35600 2800 75%1 1 1 1 1 0 0 1 1 1 1 1107630Pool14400 7200 75%1 1 1 1 1 1 1 0 1 1 1 1117967H-4
5/30/2009 excess hydro GWS Page 5HOONAH ENERGY RECOVERY WORK SHEET ====================================== =========Analysis of Energy Recovery From Excess Hydro Only(CombinedG&WS Hydro With Electric Boiler in Power PlanANNUAL FUEL SAVINGS:AnnualO&M cost:0$/year. [ =============================================]Cost Estimate$ [ Diesel Heat Recovery, Gallons0]Fuel heat value:138000Btu/gall. [ Excess Hydro Energy Recovery, Gallons12497]Fuel cost0.00$/gallon [ Diesel Generation,Gallons0]Fuel cost escal.0/year [ Total Potential Fuel Savings12497]Power increase0/year [ =============================================]Discount rate0/yearGEN DATA: Jacket Water OnlySYSTEM LOSS DATA:Heat rate at kw-load above0 3412Btu/kwhConstant losses:Heat rate at kw-load above114 3412Btu/kwh Plant piping:15000Btu/hr. Piping main insulated, branch piping &flexes bareHeat rate at kw-load above152 3412Btu/kwh Buried Arctic piping:195000Btu/hr.(6500' of 4" @ 0.25)*(170F-50F)Heat rate at kw-load above176 3412Btu/kwhGenset Eng. Preheat:20000Btu/hr. Pre-heat 2 offline enginesHeat rate at kw-load above205 3412Btu/kwhTotal constant:230000Btu/hr.Heat rate at kw-load above255 3412Btu/kwhHeat rate at kw-load above375 3412Btu/kwhVariable losses:Heat rate at kw-load above465 3412Btu/kwh Radiators/Exter Pipe100Btu/hr.xFAmot normally closed, 1/2" normally open bypassHeat rate at kw-load above400 3412Btu/kwh Plant Heating:75Btu/hr.xFControl only, gen room heated by running engineHeat rate at kw-load above4503412Btu/kwhOther0Btu/hr.xFHeat rate at kw-load above5003412Btu/kwhGENERATION DATA:WEATHER DATA: NOTES:Kwh/month:HDD/Month: HoonahJanuary56,0001108February56,000944March56,000961April127,000756May265,000531June131,000330July20,000249August33,000242September112,000423October240,000695November140,000933December95,00010361331000 8208BUILDING DATA:Fuel use, Non- BoilergallonsSeasonalSeasonalEfficiency Building in use, 1=yes, 0=noOPER.HDDPool, bldgs27564 2148 75%1 1 1 1 1 0 0 0 1 1 1 1973880 0 75%1 1 1 1 1 0 0 0 1 1 1 197388H-5
H-6Graph 1: Hoonah Estimated Energy Recovery Versus Heating Demand020004000600080001000012000 JanuaryFebruary March April May June July AugustSeptember OctoberNovemberDecemberMonthDiesel Saved (Gallons Per Month)60,000 Gal/Yr - Estimated District Heating Demand (Pool, Schools and Other Buildings)56,936 Gal/Yr - Heating Fuel Saved From Diesel HR (Diesel Generation Only - No Hydro)46,316 Gal/Yr - Heating Fuel Saved With Gartina Creek Hydro & Diesel HR 45,767 Gal/Yr - Heating Fuel Saved With Water Supply Creek Hydro & Diesel HR 42,103 Gal/Yr - Heating Fuel Saved With Combined Hydro & Diesel HR/Excess Hydro
H-7Graph 2: Total Estimated Diesel Savings Comparisons of Potential Projects010000200003000040000JanuaryFebruary March AprilMayJuneJuly AugustSeptemberOctoberNovemberDecemberMonthTotal Diesel Saved (Gallons Per Month)257,031 Gal/Yr - Total Fuel Saved With Combined Hydro & Diesel HR/Excess Hydro 180,053 Gal/Yr - Total Fuel Saved With Water Supply Creek Hydro & Diesel HR176,316 Gal/Yr - Total Fuel Saved With Gartina Creek Hydro & Diesel HR 56,936 Gal/Yr - Total Fuel Saved With Diesel HR Installation Only (No Hydro Project)
APPENDIX I
COMMUNITY CORRESPONDENCE
Hoonah Energy Infrastructure Projects
10/20/06 Trip Report & Preliminary Information
November 13, 2006
On Thursday October 19 and 20, 2006, David Lockard of the Alaska Energy Authority /
Rural Energy Group (AEA/REG) and John Dickerson of Alaska Energy and Engineering
(AE&E) traveled to Hoonah. The purposes of this site visit were to: 1) meet with local
officials as well as representatives of local and regional organizations to identify and
discuss potential energy infrastructure projects within the community; 2) to gather
reconnaissance level information for preparation of a Conceptual Design Report (CDR) for
any identified energy infrastructure projects and; 3) to collect field data for the installation of
a new 12,000 gallon double wall fuel tank at the IPEC power plant.
After a short weather delay in Juneau we arrived in Hoonah by plane around 1 PM. After a
tour of the community we met Keith Berggren, Peter Bibb and Thomas Jack of Inside
Passage Electrical Cooperative (IPEC) at the power plant. We spent the afternoon
inspecting the IPEC facility and as-builting the site in order to determine a suitable location
for the proposed new fuel tank. A meeting was held the next morning at 8 AM to discuss
potential energy infrastructure projects in Hoonah. David Lockard discussed the
AEA/REG rural energy programs as well as Denali Commission (DC) funding
requirements. Much of the meeting was spent discussing the proposed AEL&P Hoonah
intertie extension as well as potential local hydro projects, the proposed City/Hoonah
Trading consolidated bulk fuel storage project and the potential use of generation heat
recovery in Hoonah. Meeting attendees included:
Dennis H. Grey, Sr., Mayor, City of Hoonah
Jerry Medina, Administrator, City of Hoonah
Jan Supler, Vice President Retail Operations, Wards Cove/Hoonah Trading
Steve Brown, General Manager, Hoonah Trading
Tim McLeod, General Manager, AEL&P
Corry Hildenbrand, Energy Resource Developer, AEL&P
Vern Rauscher, General Manager, IPEC
Keith Berggren, Generation Manager, IPEC
Peter Bibb, Distribution Manager, IPEC
Dick Somerville, P.E., PND Engineers
Don Reid, Alaska Marine Lines
Following the meeting we reviewed plans for the new Hoonah Marine Industrial Center and
visited the site where phase I of the project is currently under construction. Discussions
were held regarding the preferred location and layout of the proposed consolidated bulk
fuel storage facility, automotive gas station, truck loading/bulk transfer facility, marine
dispensing float, large vessel marine fuel dock and marine header.
The following report is based on reconnaissance level information gathered during and
subsequent to this site visit. It includes preliminary information on:
1) Proposed AEL&P Hoonah intertie extension
2) AC vs HVDC transmission technology for the Hoonah Intertie
3) Three potential local hydroelectric projects near Hoonah
Hoonah Energy Infrastructure Projects
10/20/06 Trip Report & Preliminary Information
Page 2 of 13
4) Potential generation heat recovery project
5) Existing IPEC power plant
6) Estimated future community power demand
7) Proposed IPEC power plant upgrades
8) Replacement generator selection
9) Proposed IPEC distribution upgrades
10)Existing IPEC tank farm
11)New IPEC power plant fuel tank
12)Existing Hoonah Trading bulk fuel storage facility
13)Required community fuel storage capacity
14)Proposed new tank farm, bulk transfer and dispensing facilities
15)Alternative energy
This report along with comments from project participants will outline the issues to be
addressed in the CDR.
1) AEL&P Hoonah Intertie Extension:
The proposed Hoonah intertie extension is part of a long term effort by AEL&P, IPEC, The
Southeast Conference and the City of Hoonah to construct a transmission link between
Juneau and Hoonah. The intertie would allow the community of Hoonah to take advantage
of AEL&P's excess hydroelectric generation capacity and eliminate diesel generation in
the community.
The first leg of the intertie to the Greens Creek mine was completed in July, 2006 at a cost
of approximately $9 million. This leg included a 9.5 mile long submarine cable between
Douglas and Admiralty Islands as well as six miles of overhead transmission line to the
Greens Creek Mine. According to AEL&P current average loads at the mine are running
around 8 megawatts and near term total annual energy requirements are expected to be in
excess of 70GWh, higher than originally anticipated.
If constructed, the Hoonah intertie extension would include a 25 mile long submarine cable
between Admiralty and Chichagof Islands as well as a 3 mile long overhead transmission
line to Hoonah. According to a recently updated estimate by AEL&P the cost of the
Hoonah Intertie would be approximately $29 million for design, permitting and construction.
The long term annual energy requirements of Hoonah are expected to be 6 to 7GWh.
Permitting would likely take one to two years. Engineering completed to date includes a
power flow analysis by Power Engineers, Inc. and a preliminary submarine cable design by
Nexans and BC Hydro. An amount of $1 million was recently awarded to IPEC by DOE for
submarine cable route bathymetric studies and permitting.
According to AEL&P, if the Hoonah intertie were constructed today the rate to IPEC would
be $.10/KWh and would include all O&M as well as a contingency for cable repairs and
replacement. This rate would be "interruptible" in that Juneau area customers would
receive first priority in times of limited hydroelectric generation while Hoonah would have
priority of usage over the Greens Creek mine. It is assumed that if constructed the Hoonah
intertie would provide virtually all the power required by the community of Hoonah and that
Hoonah Energy Infrastructure Projects
10/20/06 Trip Report & Preliminary Information
Page 3 of 13
no upgrade to the existing IPEC power plant or new local hydroelectric projects would be
considered.
An economic analysis of the Hoonah Intertie titled "Hoonah Intertie Extension - Economic
Considerations" was recently prepared for AEA by Emerman Consulting, LLC and will be
included as an appendix in the final Hoonah Energy Infrastructure Upgrade Projects CDR.
Four separate scenarios were analyzed using different fuel prices, project schedules and
Hoonah energy requirement estimates. The benefit to cost ratios of the four scenarios
calculated over the estimated 30 year economic life of the intertie ranged from 0.78 to
0.50.
Additional research on the proposed intertie will be conducted and will be included in the
final Hoonah Energy Infrastructure Projects CDR.
2) AC versus HVDC transmission technology for the Hoonah Intertie:
Appendix E of the "Southeast Alaska Intertie Study Phase I Final Report" prepared by D.
Hittle & Associates for the Southeast Conference in 2003 includes a report on alternate
energy transmission technologies study conducted for the proposed interties. The study
concluded that an HVDC (High Voltage Direct Current) system would be feasible but more
expensive than an AC system for the Hoonah Intertie. The following are some
comparisons of HVDC and AC transmission technology for the proposed Hoonah intertie:
Submarine cable lengths are limited to between 40 and 50 miles in AC transmission
systems due to capacitive currents. HVDC systems make much longer submarine
crossings possible because they do not generate capacitive currents. With a crossing
length of only around 25 miles the Hoonah intertie is well within the limits for submarine
cables in AC systems.
HVDC systems can carry more current on a given size cable than with an AC system.
However, the size of the submarine cable specified for the Hoonah intertie is controlled
by the strength requirement of the cable rather than by the conductive capacity. This
offsets any potential savings of an HVDC system due to conductor size advantages for
the Hoonah intertie.
Low cost extruded polymer cable has recently been developed for use in HVDC
systems. Extruded cables are less expensive than other cable technologies but have
little history in submarine applications. There is also as yet no proven technology for
repairing a damaged submarine extruded cable.
HVDC systems can be constructed with a single cable where ground return is used.
However a single cable HVDC system is not considered an option for the Hoonah
intertie due to environmental, permitting and reliability issues. Therefore a two-cable
HVDC system would be required. Three-phase AC submarine cable is available as a
bundled unit while the HVDC system would require two separate cables. The per unit
cost of the HVDC submarine cable would be less than the bundled three-phase AC
cable but the total submarine cable cost for the Hoonah intertie would be higher for the
HVDC system due to the requirement of two separate cables.
An HVDC intertie would require a total of two voltage source converters (VSC) for
conversion of AC to HVDC and then back to AC. In 2003 the price estimate of each
VSC was $3.2 million.
Hoonah Energy Infrastructure Projects
10/20/06 Trip Report & Preliminary Information
Page 4 of 13
Additional research into the latest HVDC technology available will be conducted and will be
included in the final Hoonah Energy Infrastructure Projects CDR.
3) Three Potential Local Hydroelectric Projects Near Hoonah:
In June, 2002 HydroWest Group, LLC, a subsidiary of AP&T, published a report titled
"Reconnaissance of Three Potential Hydroelectric Sites Near Hoonah, Alaska". This
report was commissioned by the City of Hoonah. It was preceded by a previous study
titled "Gartina Creek Project - A Reconnaissance Report" performed in 1979 by Harza
Engineering for the Alaska Power Authority. A review and update of the 1979 report titled
"Concept Review Report, Gartina Creek Hydroelectric Project" was performed in 1998 by
HDR for the City of Hoonah. The three identified hydroelectric prospects in the Hoonah
area are identified as Gartina Creek, Water Supply Creek and Elephant Falls. Water
Supply Creek and Elephant Falls are both tributaries of Gartina Creek. All flow data for
these three drainages is transposed from the stream gage records of the Kadashan River
drainage near Tenakee which is very similar in geology, precipitation, orientation and
elevation to the three Hoonah sites.
Gartina Creek
The Gartina Creek project as described in the 2002 HydroWest report consists of the
following components:
A fifteenfeet high concrete and rockfill diversion dam.
A concrete intake structure and sluiceway
A 54-inch diameter steel pipeline approximately 200 feet long from the intake structure
to the powerhouse.
A 20'x20'x25' high two level reinforced concrete powerhouse
A single turbine with 600kW three-phase generator.
Programmable automatic paralleling switchgear with remote control and unattended
operation capability.
A pad-mount disconnect switch and step-up transformer bank adjacent to the
powerhouse.
Approximately four miles of 12.5kV three-phase overhead transmission line to an
interconnection near the Hoonah airport.
An approximately 0.3 mile long access road from an existing Forest Service road to the
intake structure and powerhouse.
The Gartina Creek site is estimated to have an average annual flow of around 66 cfs, a
maximum divertible flow of 140 cfs and a net head of 61 feet. Using a flow-duration
method, the maximum potential annual generation of this site was estimated in the
HydroWest report to be 1,880,00kWH. The estimated construction cost for the Gartina
Creek site is $3.75 million based on 2006/2007 construction.
Water Supply Creek
The Water Supply Creek project as described in the 2002 HydroWest report consists of
the following components:
An eight feet high concrete and rockfill diversion dam.
Hoonah Energy Infrastructure Projects
10/20/06 Trip Report & Preliminary Information
Page 5 of 13
A concrete intake and sluiceway
A 5,500 feet long combination 24" diameter HDPE and 20" diameter steel pipeline
from the intake structure to the powerhouse.
A 20'x40'x15' high single story pre-engineered metal building powerhouse.
A single turbine with 600kW three-phase generator.
Programmable automatic paralleling switchgear with remote control and unattended
operation capability.
A pad-mount disconnect switch and step-up transformer bank adjacent to the
powerhouse.
Approximately four miles of 12.5kV three-phase overhead transmission line to an
interconnection near the Hoonah airport.
An approximately .25 mile long access road from an existing Forest Service road to the
intake structure and powerhouse.
The Water Supply Creek site is estimated to have an average annual flow of around 9
cfs, a maximum divertible flow of 20 cfs and a net head of 400 feet. Using a flow-
duration method, the maximum potential annual generation of this site was estimated in
the HydroWest report to be 1,820,00kWH. The estimated construction cost for the
Water Supply Creek site is $3.1 million based on 2006/2007 construction.
Elephant Falls
The Elephant Falls project as described in the 2002 HydroWest report consists of the
following components:
An eight feet high concrete and rockfill diversion dam.
A concrete intake and sluiceway
A 3,900 feet long combination 18" diameter HDPE and 15" diameter steel pipeline
from the intake structure to the powerhouse located on Gartina Creek.
A 20'x40'x15' high single story pre-engineered metal building powerhouse.
A single turbine with 600kW three-phase generator.
Programmable automatic paralleling switchgear with remote control and unattended
operation capability.
A pad-mount disconnect switch and step-up transformer bank adjacent to the
powerhouse.
Approximately four miles of 12.5kV three-phase overhead transmission line to an
interconnection near the Hoonah airport.
An approximately 4,000 feet long access road from an existing Forest Service road to
the intake structure and an approximately 7,500 feet long access road from an existing
Forest Service road to the powerhouse.
The Elephant Falls site is estimated to have an average annual flow of around 4 cfs, a
maximum divertible flow of 9.3 cfs and a net head of 800 feet. Using a flow-duration
method, the maximum potential annual generation of this site was estimated in the
HydroWest report to be 1,780,00kWH. The estimated construction cost for the
Elephant Falls site is $3.76 million based on 2006/2007 construction.
Hoonah Energy Infrastructure Projects
10/20/06 Trip Report & Preliminary Information
Page 6 of 13
The potential annual generation capacity calculated for each of these sites is only available
if the local load is always in excess of the available hydroelectric generation. During
seasonally high stream flow periods, the nighttime community loads will fall below the
anticipated 600kW hydroelectric generation capacity. This will result in the usable annual
generation capacity being less than the potential annual generation capacity quoted for
each site. If two of these sites are developed even less of the potential annual generation
would be usable, especially during high flow periods. The annual usable generation from a
single and two-site hydroelectric project was estimated using available transposed stream
flow data, five percent flow duration charts and IPEC community average load data. The
results indicate that if only one of these hydroelectric sites were developed it would provide
approximately 30% of Hoonah's near term projected annual generation demand. If two of
these sites were developed they would provide approximately 50% of Hoonah's annual
generation demand.
The HydroWest report addresses permitting issues for each of these sites. The Gartina
Creek and Water Supply Creek projects would fall under the State of Alaska small
hydroelectric project exemption from Federal Energy Regulatory Commission (FERC)
jurisdiction. Because the Elephant Falls site is within the Tongass National Forest, it would
fall under FERC jurisdiction unless a land exchange with the City of Hoonah or Sealaska
Corporation could be arranged.
The HydroWest report also addresses environmental issues for each of these sites. The
primary environmental concern is the possible impact on anadromous and resident fish
populations due to reduced in-stream flows between the intake structure and the power
house. Because Water Supply Creek and Elephant Falls are located above Gartina Falls,
no anadromous fish will be present and only resident fish populations are of concern. The
bypassed reach of stream for the Gartina Creek project does include salmon pools at the
base of the falls. This could result in increased bypass flow requirements or significant
increases in construction costs.
4) Potential Generation Heat Recovery Project:
The IPEC Hoonah power plant has burned an average of 360,000 gallons of diesel
annually over the past two years. An efficient generation heat recovery system will recover
the heating energy equivalent of approximately 20% of the fuel burned by the generators.
Using this rule of thumb, the IPEC generators have the potential to provide the heating
equivalent of over 70,000 gallons of diesel fuel in recovered generation heat annually.
The swimming pool, school buildings, fire hall, senior center, senior apartments, and clinic
are all located in the same general vicinity. These six public facilities use approximately
60,000 gallons of diesel annually for space heating.
Ideally the power plant should be located as close as possible to the recovered heat end
use facilities to minimize conductive heat looses in the buried pipe. However the existing
power plant is located approximately one half mile from the school site where the bulk of
the recovered heat would be used and no suitable sites for power plant relocation have
been identified. Assuming four inch diameter arctic pipe and a total buried length of one
mile for supply and return piping, the conductive heat losses would be the equivalent of
approximately 20,000 gallons of diesel annually, reducing the net available recovered
generation heat to the equivalent of around 50,000 gallons of diesel.
Hoonah Energy Infrastructure Projects
10/20/06 Trip Report & Preliminary Information
November 13, 2006
On Thursday October 19 and 20, 2006, David Lockard of the Alaska Energy Authority /
Rural Energy Group (AEA/REG) and John Dickerson of Alaska Energy and Engineering
(AE&E) traveled to Hoonah. The purposes of this site visit were to: 1) meet with local
officials as well as representatives of local and regional organizations to identify and
discuss potential energy infrastructure projects within the community; 2) to gather
reconnaissance level information for preparation of a Conceptual Design Report (CDR) for
any identified energy infrastructure projects and; 3) to collect field data for the installation of
a new 12,000 gallon double wall fuel tank at the IPEC power plant.
After a short weather delay in Juneau we arrived in Hoonah by plane around 1 PM. After a
tour of the community we met Keith Berggren, Peter Bibb and Thomas Jack of Inside
Passage Electrical Cooperative (IPEC) at the power plant. We spent the afternoon
inspecting the IPEC facility and as-builting the site in order to determine a suitable location
for the proposed new fuel tank. A meeting was held the next morning at 8 AM to discuss
potential energy infrastructure projects in Hoonah. David Lockard discussed the
AEA/REG rural energy programs as well as Denali Commission (DC) funding
requirements. Much of the meeting was spent discussing the proposed AEL&P Hoonah
intertie extension as well as potential local hydro projects, the proposed City/Hoonah
Trading consolidated bulk fuel storage project and the potential use of generation heat
recovery in Hoonah. Meeting attendees included:
Dennis H. Grey, Sr., Mayor, City of Hoonah
Jerry Medina, Administrator, City of Hoonah
Jan Supler, Vice President Retail Operations, Wards Cove/Hoonah Trading
Steve Brown, General Manager, Hoonah Trading
Tim McLeod, General Manager, AEL&P
Corry Hildenbrand, Energy Resource Developer, AEL&P
Vern Rauscher, General Manager, IPEC
Keith Berggren, Generation Manager, IPEC
Peter Bibb, Distribution Manager, IPEC
Dick Somerville, P.E., PND Engineers
Don Reid, Alaska Marine Lines
Following the meeting we reviewed plans for the new Hoonah Marine Industrial Center and
visited the site where phase I of the project is currently under construction. Discussions
were held regarding the preferred location and layout of the proposed consolidated bulk
fuel storage facility, automotive gas station, truck loading/bulk transfer facility, marine
dispensing float, large vessel marine fuel dock and marine header.
The following report is based on reconnaissance level information gathered during and
subsequent to this site visit. It includes preliminary information on:
1) Proposed AEL&P Hoonah intertie extension
2) AC vs HVDC transmission technology for the Hoonah Intertie
3) Three potential local hydroelectric projects near Hoonah
Hoonah Energy Infrastructure Projects
10/20/06 Trip Report & Preliminary Information
Page 2 of 13
4) Potential generation heat recovery project
5) Existing IPEC power plant
6) Estimated future community power demand
7) Proposed IPEC power plant upgrades
8) Replacement generator selection
9) Proposed IPEC distribution upgrades
10)Existing IPEC tank farm
11)New IPEC power plant fuel tank
12)Existing Hoonah Trading bulk fuel storage facility
13)Required community fuel storage capacity
14)Proposed new tank farm, bulk transfer and dispensing facilities
15)Alternative energy
This report along with comments from project participants will outline the issues to be
addressed in the CDR.
1) AEL&P Hoonah Intertie Extension:
The proposed Hoonah intertie extension is part of a long term effort by AEL&P, IPEC, The
Southeast Conference and the City of Hoonah to construct a transmission link between
Juneau and Hoonah. The intertie would allow the community of Hoonah to take advantage
of AEL&P's excess hydroelectric generation capacity and eliminate diesel generation in
the community.
The first leg of the intertie to the Greens Creek mine was completed in July, 2006 at a cost
of approximately $9 million. This leg included a 9.5 mile long submarine cable between
Douglas and Admiralty Islands as well as six miles of overhead transmission line to the
Greens Creek Mine. According to AEL&P current average loads at the mine are running
around 8 megawatts and near term total annual energy requirements are expected to be in
excess of 70GWh, higher than originally anticipated.
If constructed, the Hoonah intertie extension would include a 25 mile long submarine cable
between Admiralty and Chichagof Islands as well as a 3 mile long overhead transmission
line to Hoonah. According to a recently updated estimate by AEL&P the cost of the
Hoonah Intertie would be approximately $29 million for design, permitting and construction.
The long term annual energy requirements of Hoonah are expected to be 6 to 7GWh.
Permitting would likely take one to two years. Engineering completed to date includes a
power flow analysis by Power Engineers, Inc. and a preliminary submarine cable design by
Nexans and BC Hydro. An amount of $1 million was recently awarded to IPEC by DOE for
submarine cable route bathymetric studies and permitting.
According to AEL&P, if the Hoonah intertie were constructed today the rate to IPEC would
be $.10/KWh and would include all O&M as well as a contingency for cable repairs and
replacement. This rate would be "interruptible" in that Juneau area customers would
receive first priority in times of limited hydroelectric generation while Hoonah would have
priority of usage over the Greens Creek mine. It is assumed that if constructed the Hoonah
intertie would provide virtually all the power required by the community of Hoonah and that
Hoonah Energy Infrastructure Projects
10/20/06 Trip Report & Preliminary Information
Page 3 of 13
no upgrade to the existing IPEC power plant or new local hydroelectric projects would be
considered.
An economic analysis of the Hoonah Intertie titled "Hoonah Intertie Extension - Economic
Considerations" was recently prepared for AEA by Emerman Consulting, LLC and will be
included as an appendix in the final Hoonah Energy Infrastructure Upgrade Projects CDR.
Four separate scenarios were analyzed using different fuel prices, project schedules and
Hoonah energy requirement estimates. The benefit to cost ratios of the four scenarios
calculated over the estimated 30 year economic life of the intertie ranged from 0.78 to
0.50.
Additional research on the proposed intertie will be conducted and will be included in the
final Hoonah Energy Infrastructure Projects CDR.
2) AC versus HVDC transmission technology for the Hoonah Intertie:
Appendix E of the "Southeast Alaska Intertie Study Phase I Final Report" prepared by D.
Hittle & Associates for the Southeast Conference in 2003 includes a report on alternate
energy transmission technologies study conducted for the proposed interties. The study
concluded that an HVDC (High Voltage Direct Current) system would be feasible but more
expensive than an AC system for the Hoonah Intertie. The following are some
comparisons of HVDC and AC transmission technology for the proposed Hoonah intertie:
Submarine cable lengths are limited to between 40 and 50 miles in AC transmission
systems due to capacitive currents. HVDC systems make much longer submarine
crossings possible because they do not generate capacitive currents. With a crossing
length of only around 25 miles the Hoonah intertie is well within the limits for submarine
cables in AC systems.
HVDC systems can carry more current on a given size cable than with an AC system.
However, the size of the submarine cable specified for the Hoonah intertie is controlled
by the strength requirement of the cable rather than by the conductive capacity. This
offsets any potential savings of an HVDC system due to conductor size advantages for
the Hoonah intertie.
Low cost extruded polymer cable has recently been developed for use in HVDC
systems. Extruded cables are less expensive than other cable technologies but have
little history in submarine applications. There is also as yet no proven technology for
repairing a damaged submarine extruded cable.
HVDC systems can be constructed with a single cable where ground return is used.
However a single cable HVDC system is not considered an option for the Hoonah
intertie due to environmental, permitting and reliability issues. Therefore a two-cable
HVDC system would be required. Three-phase AC submarine cable is available as a
bundled unit while the HVDC system would require two separate cables. The per unit
cost of the HVDC submarine cable would be less than the bundled three-phase AC
cable but the total submarine cable cost for the Hoonah intertie would be higher for the
HVDC system due to the requirement of two separate cables.
An HVDC intertie would require a total of two voltage source converters (VSC) for
conversion of AC to HVDC and then back to AC. In 2003 the price estimate of each
VSC was $3.2 million.
Hoonah Energy Infrastructure Projects
10/20/06 Trip Report & Preliminary Information
Page 4 of 13
Additional research into the latest HVDC technology available will be conducted and will be
included in the final Hoonah Energy Infrastructure Projects CDR.
3) Three Potential Local Hydroelectric Projects Near Hoonah:
In June, 2002 HydroWest Group, LLC, a subsidiary of AP&T, published a report titled
"Reconnaissance of Three Potential Hydroelectric Sites Near Hoonah, Alaska". This
report was commissioned by the City of Hoonah. It was preceded by a previous study
titled "Gartina Creek Project - A Reconnaissance Report" performed in 1979 by Harza
Engineering for the Alaska Power Authority. A review and update of the 1979 report titled
"Concept Review Report, Gartina Creek Hydroelectric Project" was performed in 1998 by
HDR for the City of Hoonah. The three identified hydroelectric prospects in the Hoonah
area are identified as Gartina Creek, Water Supply Creek and Elephant Falls. Water
Supply Creek and Elephant Falls are both tributaries of Gartina Creek. All flow data for
these three drainages is transposed from the stream gage records of the Kadashan River
drainage near Tenakee which is very similar in geology, precipitation, orientation and
elevation to the three Hoonah sites.
Gartina Creek
The Gartina Creek project as described in the 2002 HydroWest report consists of the
following components:
A fifteenfeet high concrete and rockfill diversion dam.
A concrete intake structure and sluiceway
A 54-inch diameter steel pipeline approximately 200 feet long from the intake structure
to the powerhouse.
A 20'x20'x25' high two level reinforced concrete powerhouse
A single turbine with 600kW three-phase generator.
Programmable automatic paralleling switchgear with remote control and unattended
operation capability.
A pad-mount disconnect switch and step-up transformer bank adjacent to the
powerhouse.
Approximately four miles of 12.5kV three-phase overhead transmission line to an
interconnection near the Hoonah airport.
An approximately 0.3 mile long access road from an existing Forest Service road to the
intake structure and powerhouse.
The Gartina Creek site is estimated to have an average annual flow of around 66 cfs, a
maximum divertible flow of 140 cfs and a net head of 61 feet. Using a flow-duration
method, the maximum potential annual generation of this site was estimated in the
HydroWest report to be 1,880,00kWH. The estimated construction cost for the Gartina
Creek site is $3.75 million based on 2006/2007 construction.
Water Supply Creek
The Water Supply Creek project as described in the 2002 HydroWest report consists of
the following components:
An eight feet high concrete and rockfill diversion dam.
Hoonah Energy Infrastructure Projects
10/20/06 Trip Report & Preliminary Information
Page 5 of 13
A concrete intake and sluiceway
A 5,500 feet long combination 24" diameter HDPE and 20" diameter steel pipeline
from the intake structure to the powerhouse.
A 20'x40'x15' high single story pre-engineered metal building powerhouse.
A single turbine with 600kW three-phase generator.
Programmable automatic paralleling switchgear with remote control and unattended
operation capability.
A pad-mount disconnect switch and step-up transformer bank adjacent to the
powerhouse.
Approximately four miles of 12.5kV three-phase overhead transmission line to an
interconnection near the Hoonah airport.
An approximately .25 mile long access road from an existing Forest Service road to the
intake structure and powerhouse.
The Water Supply Creek site is estimated to have an average annual flow of around 9
cfs, a maximum divertible flow of 20 cfs and a net head of 400 feet. Using a flow-
duration method, the maximum potential annual generation of this site was estimated in
the HydroWest report to be 1,820,00kWH. The estimated construction cost for the
Water Supply Creek site is $3.1 million based on 2006/2007 construction.
Elephant Falls
The Elephant Falls project as described in the 2002 HydroWest report consists of the
following components:
An eight feet high concrete and rockfill diversion dam.
A concrete intake and sluiceway
A 3,900 feet long combination 18" diameter HDPE and 15" diameter steel pipeline
from the intake structure to the powerhouse located on Gartina Creek.
A 20'x40'x15' high single story pre-engineered metal building powerhouse.
A single turbine with 600kW three-phase generator.
Programmable automatic paralleling switchgear with remote control and unattended
operation capability.
A pad-mount disconnect switch and step-up transformer bank adjacent to the
powerhouse.
Approximately four miles of 12.5kV three-phase overhead transmission line to an
interconnection near the Hoonah airport.
An approximately 4,000 feet long access road from an existing Forest Service road to
the intake structure and an approximately 7,500 feet long access road from an existing
Forest Service road to the powerhouse.
The Elephant Falls site is estimated to have an average annual flow of around 4 cfs, a
maximum divertible flow of 9.3 cfs and a net head of 800 feet. Using a flow-duration
method, the maximum potential annual generation of this site was estimated in the
HydroWest report to be 1,780,00kWH. The estimated construction cost for the
Elephant Falls site is $3.76 million based on 2006/2007 construction.
Hoonah Energy Infrastructure Projects
10/20/06 Trip Report & Preliminary Information
Page 6 of 13
The potential annual generation capacity calculated for each of these sites is only available
if the local load is always in excess of the available hydroelectric generation. During
seasonally high stream flow periods, the nighttime community loads will fall below the
anticipated 600kW hydroelectric generation capacity. This will result in the usable annual
generation capacity being less than the potential annual generation capacity quoted for
each site. If two of these sites are developed even less of the potential annual generation
would be usable, especially during high flow periods. The annual usable generation from a
single and two-site hydroelectric project was estimated using available transposed stream
flow data, five percent flow duration charts and IPEC community average load data. The
results indicate that if only one of these hydroelectric sites were developed it would provide
approximately 30% of Hoonah's near term projected annual generation demand. If two of
these sites were developed they would provide approximately 50% of Hoonah's annual
generation demand.
The HydroWest report addresses permitting issues for each of these sites. The Gartina
Creek and Water Supply Creek projects would fall under the State of Alaska small
hydroelectric project exemption from Federal Energy Regulatory Commission (FERC)
jurisdiction. Because the Elephant Falls site is within the Tongass National Forest, it would
fall under FERC jurisdiction unless a land exchange with the City of Hoonah or Sealaska
Corporation could be arranged.
The HydroWest report also addresses environmental issues for each of these sites. The
primary environmental concern is the possible impact on anadromous and resident fish
populations due to reduced in-stream flows between the intake structure and the power
house. Because Water Supply Creek and Elephant Falls are located above Gartina Falls,
no anadromous fish will be present and only resident fish populations are of concern. The
bypassed reach of stream for the Gartina Creek project does include salmon pools at the
base of the falls. This could result in increased bypass flow requirements or significant
increases in construction costs.
4) Potential Generation Heat Recovery Project:
The IPEC Hoonah power plant has burned an average of 360,000 gallons of diesel
annually over the past two years. An efficient generation heat recovery system will recover
the heating energy equivalent of approximately 20% of the fuel burned by the generators.
Using this rule of thumb, the IPEC generators have the potential to provide the heating
equivalent of over 70,000 gallons of diesel fuel in recovered generation heat annually.
The swimming pool, school buildings, fire hall, senior center, senior apartments, and clinic
are all located in the same general vicinity. These six public facilities use approximately
60,000 gallons of diesel annually for space heating.
Ideally the power plant should be located as close as possible to the recovered heat end
use facilities to minimize conductive heat looses in the buried pipe. However the existing
power plant is located approximately one half mile from the school site where the bulk of
the recovered heat would be used and no suitable sites for power plant relocation have
been identified. Assuming four inch diameter arctic pipe and a total buried length of one
mile for supply and return piping, the conductive heat losses would be the equivalent of
approximately 20,000 gallons of diesel annually, reducing the net available recovered
generation heat to the equivalent of around 50,000 gallons of diesel.
Hoonah Energy Infrastructure Projects
10/20/06 Trip Report & Preliminary Information
Page 7 of 13
The final CDR will include a proposed heat recovery pipeline routing plan and cost
estimate for supplying recovered heat to the previously mentioned public facilities.
5) Status of Existing Hoonah IPEC Power Plant:
The IPEC (originally THREA) power plant was constructed in the 1977. It is located on the
eastern edge of town at the intersection of Gartina Highway and White Alice Site Road.
The building is a 40'Wx100'L metal-sided, pre-engineered steel frame structure that
houses three generators, an office and a warehouse. The interior walls are covered with
painted plywood up to a height of 8' with vinyl-encased fiberglass batt insulation exposed
above and across the ceiling. The exterior metal siding is in good condition but the
exterior paint is in very poor condition and is peeling badly. The concrete foundation, steel
frame members and horizontal steel girts appear to be in good condition. According to the
operator, the finish grade around the plant does not drain well and the plant is prone to
minor flooding, especially during spring breakup.
There are three Caterpillar generators installed in the power plant. Unit #1 is a model 398
with a capacity of 600kW at 1,200RPM. The 398 is an antiquated pre-combustion design
with poor fuel economy and increasingly difficult availability of spare parts. This unit is
used for emergency backup only and is slated for replacement. Unit #2 is a model 3512
with a prime capacity of 1,100kW at 1,200RPM. Unit #3 is a model 3512 with a prime
capacity of 855kW at 1,200RPM. Units #2 and #3 each have approximately 66,000 total
engine hours. With the current schedule of a top-end overhaul every 11,000 hours and a
major overhaul every 22,000 hours, IPEC expects to get at least an additional 54,000
hours each from existing units #2 and #3, barring any unforeseen circumstances.
Engine cooling is with three remote radiators located outside at the front of the power plant.
Each generator is on a stand-alone cooling system with one radiator. There is currently no
generation heat recovery equipment installed.
Power generation is at 4160V 3-phase. There are two separate community feeders with
one pole-mounted and one pad-mount step-up transformer bank within the fenced area
adjacent to the power plant. Station service is provided by a metered 480V three phase
load center as well as an un-metered 120/208V three phase load center. The 5kV manual
paralleling switchgear was installed new in 1990. It includes a section for each of the three
generators and a feeder/station service section.
6) Estimated Future Community Power Demand
According to IPEC data, the current annual peak generation load in Hoonah is around
900kW, the average demand is around 596kW and the annual generation requirement has
averaged 5.2GWh over the past two years. IPEC load data indicates that current seasonal
load variations in Hoonah are minor, with summer and winter loads being very even.
Steady growth in summer peak loads and annual generation are likely over time due to
expected increases in tourism, with annual generation requirements likely to grow to over
6GWh within five years. It appears that both generators #2 and #3 are adequately sized to
handle the estimated near term growth in community demand. Additional research will be
conducted into potential community peak load and generation requirement growth and will
be included in the final CDR.
Hoonah Energy Infrastructure Projects
10/20/06 Trip Report & Preliminary Information
Page 7 of 13
The final CDR will include a proposed heat recovery pipeline routing plan and cost
estimate for supplying recovered heat to the previously mentioned public facilities.
5) Status of Existing Hoonah IPEC Power Plant:
The IPEC (originally THREA) power plant was constructed in the 1977. It is located on the
eastern edge of town at the intersection of Gartina Highway and White Alice Site Road.
The building is a 40'Wx100'L metal-sided, pre-engineered steel frame structure that
houses three generators, an office and a warehouse. The interior walls are covered with
painted plywood up to a height of 8' with vinyl-encased fiberglass batt insulation exposed
above and across the ceiling. The exterior metal siding is in good condition but the
exterior paint is in very poor condition and is peeling badly. The concrete foundation, steel
frame members and horizontal steel girts appear to be in good condition. According to the
operator, the finish grade around the plant does not drain well and the plant is prone to
minor flooding, especially during spring breakup.
There are three Caterpillar generators installed in the power plant. Unit #1 is a model 398
with a capacity of 600kW at 1,200RPM. The 398 is an antiquated pre-combustion design
with poor fuel economy and increasingly difficult availability of spare parts. This unit is
used for emergency backup only and is slated for replacement. Unit #2 is a model 3512
with a prime capacity of 1,100kW at 1,200RPM. Unit #3 is a model 3512 with a prime
capacity of 855kW at 1,200RPM. Units #2 and #3 each have approximately 66,000 total
engine hours. With the current schedule of a top-end overhaul every 11,000 hours and a
major overhaul every 22,000 hours, IPEC expects to get at least an additional 54,000
hours each from existing units #2 and #3, barring any unforeseen circumstances.
Engine cooling is with three remote radiators located outside at the front of the power plant.
Each generator is on a stand-alone cooling system with one radiator. There is currently no
generation heat recovery equipment installed.
Power generation is at 4160V 3-phase. There are two separate community feeders with
one pole-mounted and one pad-mount step-up transformer bank within the fenced area
adjacent to the power plant. Station service is provided by a metered 480V three phase
load center as well as an un-metered 120/208V three phase load center. The 5kV manual
paralleling switchgear was installed new in 1990. It includes a section for each of the three
generators and a feeder/station service section.
6) Estimated Future Community Power Demand
According to IPEC data, the current annual peak generation load in Hoonah is around
900kW, the average demand is around 596kW and the annual generation requirement has
averaged 5.2GWh over the past two years. IPEC load data indicates that current seasonal
load variations in Hoonah are minor, with summer and winter loads being very even.
Steady growth in summer peak loads and annual generation are likely over time due to
expected increases in tourism, with annual generation requirements likely to grow to over
6GWh within five years. It appears that both generators #2 and #3 are adequately sized to
handle the estimated near term growth in community demand. Additional research will be
conducted into potential community peak load and generation requirement growth and will
be included in the final CDR.
Hoonah Energy Infrastructure Projects
10/20/06 Trip Report & Preliminary Information
Page 8 of 13
7) Proposed IPEC Power Plant Upgrades
As mentioned previously, if the proposed AEL&P Hoonah intertie extension is constructed
then it is assumed that no upgrades will be performed at the IPEC plant other than the new
fuel tank (see item 11). If the community remains reliant exclusively on diesel generation or
if a combination of local hydroelectric and diesel generation is the long term solution then
the following upgrades to the existing IPEC power plant are proposed. These upgrades
are intended to modernize the power plant and to improve the overall fuel efficiency,
reliability, fire prevention/protection, noise control and operations at the facility:
Re-grade area around plant to improve area drainage
Replace existing generator #1 with new generator
Replace existing switchgear and relays with new automatic paralleling switchgear
Replace all exterior sheet metal
Replace existing ventilation louvers and ridge vent with sound-insulated air intake and
exhaust fan ducting
Replace existing engine coolant piping with common cooling manifold including a heat
exchanger to allow for utilization of recovered generation heat
Replace existing radiators with new radiators and variable speed motor controls
Replace existing non-operative fire suppression system with new fire suppression
system
Renovate and enlarge control room to contain new switchgear
Install a used oil blender (the feasibility of this will need to be investigated more
thoroughly in the Concept Design Report)
8) Replacement Generator Selection
If a major renovation of the power plant is deemed necessary it is proposed that the
existing antiquated Caterpillar Model 398 generator be replaced with a new, more fuel
efficient unit. Assuming that the two existing 3512's are capable of handling the
expected near term peak loads, the new generator should be prime rated to efficiently
handle night time loads and to provide efficient peak-adding with hydroelectric power if
constructed. A thorough investigation of all Caterpillar model gensets prime rated
between 500kW and 600kW and available in current EPA tier ratings will be conducted
prior to the Concept Design Report.
9) Proposed IPEC Distribution Upgrades
A 12.47/7.2kV overhead distribution system provides electric power to the community of
Hoonah. The distribution system is in generally good condition but there is one issue that
will need to be addressed in the near future. Phase I of the new Hoonah Marine Industrial
Center is currently under construction along Gartina Highway, between the City dock and
the ferry terminal. The existing overhead transmission line currently runs across an area
that will be used for marine vessel and connex storage in the future. The City would like all
distribution in this area to be buried to avoid any potential safety concerns with operating
the new facility around the existing overhead power lines.
10) Existing IPEC Tank Farm:
Hoonah Energy Infrastructure Projects
10/20/06 Trip Report & Preliminary Information
Page 9 of 13
The existing power plant tank farm was built in 1977. It consists of three old BIA style
vertical tanks and two ex-military domed-end horizontal tanks in a lined earthen dike as well
as a gravity-fed exterior day tank located adjacent to the power plant. The two horizontal
tanks have since been taken out of service. The current tank farm configuration has a
gross shell capacity of approximately 26,000 gallons, including a 3,000 gallon double wall
day tank. All fuel is delivered to this facility by tank truck. Deficiencies at the facility
include:
aging, rusted tanks
non-liquid tight dike membrane liner
non-code compliant piping, valves and appurtenances
lack of piping pressure relief
lack of cathodic protection on buried pipe
lack of tank emergency venting
lack of overfill prevention on 3,000 gallon day tank
3,000 gallon day tank too close to the power plant building
lack of surface flow containment at truck transfer area
11) New IPEC Power Plant Fuel Tank:
Because there is a reliable bulk fuel facility operator and fuel delivery service in Hoonah,
IPEC no longer deems it necessary to store such large quantities of fuel at the power plant.
At IPEC's request, AEA has approved funding for installation of a single new double wall
tank at the power plant to replace the entire existing fuel storage facility. The proposed
new tank location was inspected and some preliminary measurements were made during
this site visit. The tank installation project will include the following items:
excavation of hillside at west end of building to enlarge pad for placing new tank
install new 10' diameter x 20' long 12,000 gallon gross shell capacity horizontal skid-
mounted double wall tank with overfill protection
install new security fencing
re-grade yard area to provide surface flow containment around truck transfer area
install new HDPE coated welded steel fuel oil supply and return piping in below grade
concrete utilidor between the new tank and power plant to allow for vehicle access to
step-up transformers behind power plant - provide removable cover for visual
inspection of pipelines
See attached Sheets M1 and M2 for conceptual plans.
The IPEC tank project design will be expedited for summer '07 construction. The tank
fabrication drawings will be completed in time for January '07 procurement and an early
spring '07 tank delivery schedule. An as-built survey of the IPEC facility with surface
contours is required for final site plan development. J. W. Bean Surveying will be in
Hoonah around the first of the year to do work for the City and can perform the required
survey work at that time. Final design will then be completed by February '07, with
permitting and procurement to be completed in time for summer '07 construction.
12) Existing Hoonah Trading Bulk Fuel Storage Facility:
Hoonah Energy Infrastructure Projects
10/20/06 Trip Report & Preliminary Information
Page 10 of 13
The Hoonah Trading bulk fuel storage facility provides storage for virtually all the diesel fuel
and gasoline received by the community. The facility consists of six in-service vertical steel
bulk storage/dispensing tanks, a three product marine header, a three product marine
fueling station, a three product vehicle gas station, a diesel truck loading rack, and three 4"
diameter barge fill/distribution pipelines. The tank farm is located on the hillside above the
Hoonah Trading store. Tank farm access is by a covered wooden stairway from 1st Street.
The fuel is used for local power generation, vehicle dispensing, marine dispensing and
heating fuel delivery. All dispensing and bulk transfers are by gravity.
The total gross shell capacity of the six bulk storage/dispensing tanks is approximately
154,000 gallons of #2 diesel, 19,000 gallons of #1 diesel and 38,000 gallons of unleaded
gasoline. The facility appears to be old but is well maintained. The tank farm is built on a
two-tiered site with four tanks on the lower level and two tanks on the upper level. It is
completely surrounded by chain link fence. Concrete walls on the sides and across the
front of both tiers provide some surface flow containment but there is no dike membrane
liner and the containment is not liquid tight. The tanks are equipped with normal vents and
manways. There are 4" flanged bottom connections with flanged steel ball valves and 1"
threaded steel PRV jumpers for pipeline pressure relief. The manifold piping appears to
be in good condition and is well supported but there are no flexes between tank
connections. The tanks are all supported on concrete bases.
There are three each 4" diameter welded steel barge fill/distribution pipelines that run from
the marine header to the tank farm, supported under the dock, then buried under the road
and finally above grade up the hill to the tank farm.
A three product marine header is located on the end of the fuel dock. Each barge
connection has a 4" quick disconnect hose coupling, a 4" flanged steel check valve, and a
4" flanged steel plug valve. There is a steel drip pan that serves all three marine header fill
connections which does not appear to have adequate capacity to meet the 84 gallon
containment requirement. The marine dispensers are also located under a rain shelter on
the face of the fuel dock and are gravity fed with 2" welded steel branch pipelines off of the
main 3" barge fill/distribution pipelines.
There is a truck rack located near the Hoonah Trading store that allows for bulk loading #1
or #2 diesel into a tank truck for fuel deliveries throughout the community. There is also a
two product gasoline and #2 diesel vehicle dispenser located on the dock near the store.
The following is a summary of existing facility deficiencies observed:
Improper Secondary Containment (Diking)–Tanks are not within a proper liquid tight
secondary containment system of adequate capacity as required by the Fire Code and
EPA regulations.
No Emergency Vents - None of the tanks have emergency vents, in violation of the Fire
Code.
Improper Piping and Valves - Existing piping systems consist of steel piping with a
combination of welded and threaded joints. The threaded joints are particularly prone
to leaking.
Gravity Dispensing - Code requires that all fuel dispensing be by pump.
Above-Ground Dispensing Tank Capacity - State Fire Marshall requirements stipulate
that the maximum size of an above ground dispensing tank is 12,000 gallons.
Hoonah Energy Infrastructure Projects
10/20/06 Trip Report & Preliminary Information
Page 11 of 13
Dispensing From Above-Ground Tanks Without Protective Systems - State Fire
Marshall requirements stipulate protective devices and piping systems to prevent a
gravity discharge of fuel in the event of a failure of the dispenser or piping. No
protective devices are installed.
Cathodic Protection of Buried Pipelines - Code requires all buried piping to have
cathodic protected.
Improper Site Location - The existing bulk/dispensing tanks do not appear to meet Fire
Code minimum separation distance requirements from adjacent public ways and
property lines for unprotected tanks.
This facility does not meet current code or regulation requirements and would not to be
cost effective to renovate. Therefore it should be taken out of service and replaced with a
new tank farm located at the new Hoonah Marine Industrial Center.
13) Required Community Fuel Storage Capacity:
Hoonah is located on a year round ice free port with a deep water dock capable of
receiving ocean-going barges. Fuel deliveries by barge are available from at least two
different vendors and are scheduled to be in the area at least twice per month. According
to fuel delivery records, the community has recently averaged approximately sixteen barge
deliveries per year, spaced from two weeks to one month apart. Based on this delivery
schedule and to ensure no future disruptions in fuel supply, the facility should be sized to
hold an approximate one peak month supply of each product with an adequate reserve
margin. The following table compares the current annual and one peak month use for each
product to the proposed net useable tank capacity for the new facility:
CONSUMPTION VERSUS CAPACITY
Product Average
Annual
Use in
Gallons
(1)
Estimt'd
Peak 1
Month
Use in
Gallons
Proposed
Net
Capacity
in Gallons
(2)
% of
Est.
Peak 1
Month
Use
% of
Est.
Annual
Use
Proposed
Gross
Capacity in
Gallons
Gasoline 250,000 30,000 36,000 120% 14% 40,000
#1 Diesel 210,000 30,000 36,000 120% 17% 40,000
#2 Diesel 1,000,000 125,000 153,000 122% 15% 170,000
Avgas (3) 0 n/a 9,000 n/a n/a 10,000
Total 1,460,000 234,000 260,000
(1) Calendar years 2004 and 2005.
(2)Net capacity (90% of gross shell capacity)
(2)No existing avgas storage but planning to begin avgas sales at airport
14) Proposed New Tank Farm, Bulk Transfer and Dispensing Facilities:
The proposed new tank farm will include a total of six each welded steel vertical bulk
storage tanks, including four at 40,000 gallons for #2 diesel storage, one at 30,000 gallons
for #1 diesel storage and one at 30,000 gallons for gasoline storage. There will also be
two horizontal skid-mounted welded steel dispensing tanks, with each tank divided into two
Hoonah Energy Infrastructure Projects
10/20/06 Trip Report & Preliminary Information
Page 12 of 13
equal 10,000 gallon partitions. The partitions will provide for dispensing of the #2 diesel,
#1 diesel and gasoline as well as storage and transfer of avgas. Secondary containment
will be provided by a lined concrete dike. A drive-through truck loading facility will provide
for top loading of #2 diesel, #1 diesel and avgas. It will be constructed adjacent to the tank
farm and situated so that secondary containment is provided by the tank farm dike. A
service station style dual product gasoline and #2 diesel dispenser in the center of a two
vehicle slab will be installed near the tank farm.
New 4” diameter pipelines will be installed for #2 diesel, #1 diesel and gasoline. A 2"
diameter pipeline will be installed for avgas deliveries. The #2 diesel, #1 diesel and
gasoline pipelines will be equipped with branch tees and isolation valves to allow them to
serve as fill pipelines for barge deliveries as well as distribution pipelines for dispensing
and bulk transfer operations. The pipelines will be suspended below the fuel dock and
buried from the fuel dock to the new tank farm. A drip pan will be provided on the dock at
the termination of the fill pipelines (marine header). A combination of centrifugal and
submersible pumps will be used for bulk transfer and dispensing functions.
A large vessel marine fuel transfer facility with hose stands and meters will be located near
the marine header on the main fuel dock. A separate fuel float will be used for retail fuel
sales to smaller vessels and will include marine dispensing of #2 diesel, #1 diesel and
gasoline.
See attached Sheets M3 and M4 for conceptual plans.
A more detailed tank farm conceptual design will be included in the Hoonah Energy
Infrastructures Project CDR to be completed by spring '07. If comments are received and
a consensus is reached on a facility plan in a timely manner then final design can be
completed in time for a spring '08 tank farm construction schedule.
15) Alternative Energy:
The proposed AEL&P intertie as well as potential local hydroelectric and generation heat
recovery projects have already been addressed in this report. The Alaska Energy
Authority/Alaska Industrial Development and Export Authority published a draft Rural
Alaska Energy Plan dated December 31, 2002 as a follow-up report to the previously
released Screening Report of Alaska Rural Energy Plan dated April 2001. The Screening
Report evaluated a dozen alternative energy technologies other than generation heat
recovery. Only wind energy was identified as alternative energy technology warranting
further evaluation in the draft Rural Alaska Energy Plan. According to the Wind Energy
Resource Atlas of the United States the community of Hoonah is located within a class 3
wind regime and is not a viable candidate for a wind energy program using currently
available technologies.
Hoonah Energy Infrastructure Projects
10/20/06 Trip Report & Preliminary Information
Page 13 of 13
Please review the issues presented and call David Lockard at 269-4541 to discuss or fax
your comments to 269-3044. In order to keep the CDR on schedule we need to receive all
community comments no later than January 31, 2007. I look forward to working with you on
this project.
HOONAH BULK FUEL PROJECT
LOCALLY AVAILABLE EQUIPMENT LIST
OWNER MAKE MODEL YEAR
CAPACITY
(YDS, TONS)
ATTACHMENTS -
(BACK-HOE, FORKS,
AUGER, ETC..)
CONDITION,
COMMENTS
DUMP TRUCKS
DOZERS
LOADERS
TRACK HOES (EXCAVATORS)
SKID-STEERS
CRANES
HOONAH BULK FUEL UPGRADE PROJECT
LOCAL LABOR POOL
Name LaborerTruck DriverHeavy Equip OperatorHeavy Equip MechanicWelders HelperCertified Welder (1)Apprentice ElectricianJourneyman Electrician (2)1) With Current API Welding Certificate
2) With Current Certificate of Fitness 5/18/2007