HomeMy WebLinkAboutGrant Lake-Creek Hydroelectric Project Alternative Energy Grant Proposal - Feb 2008 - REF Grant 2195333Homer Electric Association, Inc.
Corporate Office PertiaaNtilat Service Center
T i take 5tri�ct 280 .Air kWl la,':14
llwllcr. ,llssk a 9Q06-76811 Kunui, Ahskc;a 1)901 1- 1'80
FAX [91171 ? 55- ;13 E:AX (907) 28;-"i1??
PROJECT SPECIFIC INFORMATION
In support of the
ALTERNATIVE ENERGY GRANT PROPOSAL
PRECONSTRUCTION GRANT APPLICATION
For
GRANT LAKE/CREEK PROJECT
Prepared by:
Homer Electric Association, Inc.
February 11, 2008
2008-02-11 AEA Alt Energy Grant App - Grant Lance A Touchstone Energy" Cooperative 0.
ALTERNATIVE ENERGY GRANT PROPOSAL
PRECONSTRUCTION APPLICATION
Homer Electric Association, Inc. — GRANT LAKE/CREEK PROJECT
PROJECT DESCRIPTION
HEA desires to construct a low -impact hydro facility utilizing the water resources provided by
Grant Lake/Creek, located approximately 1.0 mi east of the Seward Highway near the town of
Moose Pass in Kenai Peninsula Borough, Alaska. A map of the proposed project area is
provided below.
The proposed project would have a siphon (or gravity feed) intake in Grant Lake, near the point
at which it flows into Grant Creek. As part of an initial assessment, information gathering would
be undertaken to assess the feasibility of constructing a small dam or dike to raise the surface
elevation of Grant Lake to increase storage for generation.
Lessons learned from the design and implementation of the proposed siphon design could be
employed on future small, low -impact hydro projects, including others being considered by HEA
Grant Lake, which is located at an elevation of approximately 800 ft MSL, flows into Grant
Creek. The Grant Lake watershed is about (including Grant Creek) 14 mi2, and the lake has an
approximate surface area of 1,888 ac. Grant Creek, which discharges into Upper Trail Lake,
has an estimated average annual flow of 193 cubic feet per second (cfs). The proposed project
would generate power with approximately 171 ft of head and have an anticipated generation
capacity of about 5.0 MW.
February 11, 2008 Page 2 of 7
ALTERNATIVE ENERGY GRANT PROPOSAL
PRECONSTRUCTION APPLICATION
Homer Electric Association, Inc. — GRANT LAKE/CREEK PROJECT
The powerhouse tailrace would be designed to carry the project flow to Grant Creek or Upper or
Lower Trail Lake. The dimensions of the tailrace would be developed based on terrain and
other pertinent information to be obtained during the study phase.
The project would include 1 — 2 mi of new overhead transmission line employing one of two
potential transmission options: 1) power generated at the powerhouse at low voltage would be
transmitted to a remote transformer, where it would be converted to 115 kV and connected to
the existing transmission grid or 2) power generated at the project would be transmitted directly
to the grid from a step-up transformer near the powerhouse.
The legal description and ownership of lands (ADNR 2006) within the proposed project
boundary are provided in the table below. All land is referenced to the Seward Meridian. Un-
shaded rows pertain to the Grant Lake outlet and Grant Creek. Shaded rows include Grant
Lake in its entirety and potential transmission areas.
Township
Range
Section
Ownership
.......... SNP
5.
_JSDA Forest.Service
IE
= 29::
USDA Forest Seiyice.
30
=:State "" atented land _
MateZatenfed
_:USDA forest Sery�ce
36 , _
.04
.3SbAF6restService
4N
IE
5
USDA Forest Service
4N
1E
6
State patented land
4N
I
7
State patented land
9N.
1WPilvate,._
4N
1W
12
Private
The project in its final form would likely consist of a dam, pipelinelpenstock, powerhouse,
access road, and transmission lines. All improvements could potentially affect a combination of
federal, state, and private lands. No portion of the potential project area has been designated
as a Wilderness Area, recommended for designation as a Wilderness Area, or designated as
Wilderness Study Area. No portion of the project area has been included in the Wild and Scenic
River System.
Power from the project would be available to customers of Homer Electric Association and other
areas served by the existing transmission grid. Power from the proposed project would be
important to the citizens of the Kenai Peninsula and would be environmentally beneficial and
cost effective as an alternative source of energy to offset fossil fuel generation. The power from
the proposed project would reduce consumption of non-renewable carbon -based energy
sources, thereby helping to improve air quality in Kenai Peninsula Borough.
February 11, 2009 Page 3 of 7
ALTERNATIVE ENERGY GRANT PROPOSAL
PRECONSTRUCTION APPLICATION
Homer Electric Association, Inc. — GRANT LAKE/CREEK PROJECT
PROPOSED STUDY PROGRAM
The study program, which HEA hopes will culminate in the filing of a License Application with
FERC, would be conducted according to the Commission's licensing regulations.
Potential Study Program Elements
Engineering -and feasibility
• Hydrology
• Bathymetry
• Stream gauging
• Dam stability and soils tests and analysis (if needed)
• Preliminary design, i.e., unit type and size
• Tunnel/pipeline alignment
• Evaluation of transmission line route
• Financial analysis
Environmental Studies
• Fish species composition
• Fish habitat assessment
• Rare, Threatened and Endangered (RTE) species inventory
• Vegetation
• Wildlife
• Recreation
• Cultural
• Aesthetics
• Project effects analysis
Stakeholder Consultation
HEA will consult with potential stakeholder entities (i.e., agencies, NGOs, Native Corporations,
and communities) early in the study phase to ensure that all significant concerns are addressed
and planned for in the studies in anticipation of the licensing process for the Grant Lake / Grant
Creek project.
MANAGEMENT & TECHNICAL CAPACITY
Homer Electric Association is a well established railbelt electric cooperative that has been
serving its members since 1945. The cooperative operates and maintains both fossil fuel and
hydroelectric generation facilities, including the 120MW Bradley Lake Hydroelectric Plant. Its
management and staff are well prepared to oversee the development of this small hydro facility
February It, 2008 Page 4 of 7
ALTERNATIVE ENERGY GRANT PROPOSAL
PRECONSTRUCTION APPLICATION
Homer Electric Association, Inc. — GRANT LAKE/CREEK PROJECT
from its conception through construction and operation. Where needed, HEA will contract with
qualified firms and consultants to conduct the engineering, studies and detailed design
associated with the project.
PRECONSTRUCTION COST ESTIMATES & FINANCING
It is generally recognized that initial capital costs for alternative energy projects are significantly
higher than comparable fossil fuel generation assets, though the long-term benefits of
alternative energy projects can be substantial. Denali Commission and AEA funding can help to
offset some of these initial project screening and capital costs and contribute to the economic
and social viability of an eventual project. HEA is strategically planning to expand its generation
portfolio to include renewable energy sources. This application is one result of implementing this
planning effort. The purpose of this long-term vision is to provide more consistently priced,
environmentally responsible energy to balance the traditional generation resources currently
available.
One of the stated elements of the proposed study program is to develop a financial analysis or
model for the project. This will be one of the first tasks undertaken by HEA along with further
engineering feasibility study. The table below details the preconstruction costs that lead to a
FERC license application.
PRE CONSTRUCTION STUDY PROGRAM ELEMENTS
Budget
Feasibility Evaluation (Financial & Engineering Models)
$ 100,000.00
Initiate Stakeholder Consultation
$
30,000.00
Prepare and file Pre -Application Document (PAD)
$
20,000.00
FERC Scoping
$
20,000.00
Proposed Study Plan (PSP)
$
20,000.00
Revised Study Plan (RSP)
$
20,000.00
Initiate Field Studies
$ 200,000.00
Complete Field Studies
$
25,000.00
Additional/Supplementary Data Collection
$
25,000.00
Draft License Application.
$
20,000.00
File License Application
$
20,000.00
Total Proposed Study Program
$ 500,000.00
The estimated cost of conducting studies, investigations, tests, surveys, mapping and
developing plans and specifications for the proposed Grant take 1 Grant Creek Project is
$500,000. AEA funding requested here will support the feasibility evaluation listed above.
Preconstruction funds will initially be drawn from a combination of grant funding and internal
financing. Other options may be explored depending on the results of the preconstruction
assessments.
February 11, 2008 Page 5 of 7
ALTERNATIVE ENERGY GRANT PROPOSAL
PRECONSTRUCTION APPLICATION
Homer Electric Association, Inc. -- GRANT LAKE/CREEK PROJECT
PRELIMINARY COSTS & BENEFIT -COST ESTIMATE
A preliminary benefit -cost estimate is provided in the spreadsheet on the next page.
Assumptions pertaining to power production, construction, financing and avoided costs are
noted at the top of the analysis. The costs and savings are brought to present worth in 2008 for
comparison. The benefit -cost ratio for this project is estimated at 1.95.
This paragraph will briefly describe the costs considered in the analysis. Once the project is past
the preconstruction phase and has entered a FERC licensing process, an additional one million
dollars is allocated for licensing, further studies and detailed design. Preliminary construction
capital costs for this S.OMW project are estimated at $3,500/kW, or approximately $17,500,000.
The cost of this construction capital is amortized over a thirty year period. Operations &
Maintenance (O&M) costs are based on HEA experience and are escalated over the life of the
project. All these costs are brought to a 2008 present worth value of $43,562,152.
The project savings are estimated as HEA's avoided cost of purchasing power produced by
natural gas at $8.29/MMBtu in 2007 dollars. The avoided cost of power is escalated by 5% per
year over the project life and then brought to a present worth in 2008 equal to $84,735,652.
February 11, 2008 Page 6 of 7
ALTERNATIVE ENERGY GRANT PROPOSAL
PRECONSTRUCTION APPLICATION
Homer Electric Association, Inc. — GRANT LAKE/CREEK PROJECT
u,c
j
ark
� I
y
n�
I �up�
l.(•F i'f I i iSCir hl.
N 7 U
J
�: 1 r u' r e -� - 1 u- {o r- i r -
.
*I yQ9
[MIN
77 IA �N VI NIf�-9, `��=j�u/K:E�,ifh fH dr.o4l9 Eq yj'.Snd+H �l��l(AN �{.h..+4J.A F-4 NtiH b9�H MI��Fi
i''F I
�1 -MNi11��lu 1!'-f�ti M m a11NL 11" I
i -
I (J
� a
ml
o
M1MOI*W� O t to 'N +ni �Itn N I[r gylr`MM1 M! ql M
N 41J1 WI6 MiM I m€ 4 rtN {� I I {00 �-.M1
? � M1W T�I��O N M1�iN Im
I
�IM 49'b% h'�IH! M b4I M' IH H'4l�IIE�31{YI J64 �
Iv O 3
glCl m,m wltiR M14 �M
4i[I MO
N Nm'l�u.. 4M1
6�6sia,.N0s�, �cn
�qsai1I,NOov],Il4O�vI.'�.aMaE9l3mWnWi1}b�IIo�N69
'' -.
O O
_iL
IIdo J
o �1I
iCq �'IOAOtaF
�'CM��Iy+tlNcL9
i�tlf91o6s�-,
1 loio� foloio a.cvoignncFo
(fljv1;63�nH rns;qraM1s�
' �[a
11 - 1 H1,641M,(91 i6)�b4,h cq,vfsvlcalv.•d4,�9�M �49.N{N/,
lil1
I
}
a
F! S I f I { J
WI
w l�w�
1
1010
i !
Ora
-}_ f _4+r`1�i31NSIyF inlL{9:5iJTMff»'C�v N�V! Wl r•Y'r` `•`: `'+F Ye`iY 4} �Ib 63 H M {h Et
-
N
Ex W "C?IIX• kF. �SW zl
!
.
aU
{
f 3
Q .0-
p
a
L]
O
t
7�T
42
O
�Q-
U
0- ❑
.
O
164 b1 d149,'B9: b969 bY�ln,f� hl Vf i i IN jII iM6 -000 {aWW 4�4�-iOO W' N6Mi '.
IN 11�'YON.Q�1
NI INN NNN NNNM MMM �M
f1h
fh S9.{q-646/.M-E91Htdl1f9 Hx H. �.(91W[H9.f4.[9: bS`df H_Fy.�H:m
ICtli1;1.iM W. L4
io
taFw M w In-r Ic•- w
14
1
�j49`b41Wf6494+HHr4_''.��/Udf:��64.491I64 b1:64'K d}fA-fh,H d} I ' F
1 1
�I�
1 +a .-I j�i�,� N INiNIN N hS NININ M I F ,
F`^1-
IV1 I- Igiq q p-q O'Q1p[O 410'O 610 O O'tl ltl{nJtlin'n tl I 1 1 [ f
1
U F-
64 [9 H -(n'v 6fJglta ViliH K�FRf9 (91(A f9 b4 FhiHi HIS+4 M169 bY:64 +H1f9 63:fB'Nf 89 W.[9�f9'.6414n ryly F69:&ilf9 N! 64.NiIf9 69;6f:&i�tl
• a .
U
-
- -
C]
JIFF
b_o 69:W:.N:SA�69:%f:%9%9W HHi49H—'—E96969--�-('a'aa����-�-63�».%5��.6a6+a
'iJ
0 � O
n Iw {n s4.Injrnlln In -
_
❑
IL
: -
!d"
W
W �m F 'm 'N .N len _ 'NON M'M M M R M M V• eF-M LL'1 N_A,� J 'N I[fIMp 't lii W:1[f
irvl -
❑
a NtN N NfN NFN N.[�eiN N N=N.NN N NN-N!N N N!NFN N EN N'N:NIty N N'Nlry N.N N!N N N N�N
- 1
.�F
February l ] , 2009 Page 7 of 7