HomeMy WebLinkAboutGartina Falls Hydroelectric Project Conceptual Design Report - Feb 2011 - REF Grant 7060922GARTINA FALLS &
WATER SUPPLY CREEK
HYDROELECTRIC PROJECTS
CONCEPTUAL DESIGN REPORT
Prepared for:
Inside Passage Electric Cooperative
12480 Mendenhall Loop Road
Juneau, Alaska
Prepared by:
HDR Alaska
2525 C Street, Suite 305
Anchorage, AK
February 2011
Gartina Falls & Water Supply Creek Hydroelectric Projects
Conceptual Design Report
Hoonah Hydroelectric Projects Page i February 2011
Contents
EXECUTIVE SUMMARY ............................................................................................................................ ES-1
1 INTRODUCTION ................................................................................................................................ 1
2 BACKGROUND INFORMATION .......................................................................................................... 2
3 HYDROLOGY .................................................................................................................................... 2
3.1 Regional Hydrology .................................................................................................................. 2
3.2 Basin Characteristics ................................................................................................................. 3
3.3 Comparable Gages .................................................................................................................... 4
3.4 Kadashan River ......................................................................................................................... 5
3.5 Flood Frequency Analysis ......................................................................................................... 5
3.6 Hydrology Summary ................................................................................................................. 7
3.6.1 Gartina Creek at Gartina Falls ....................................................................................... 7
3.6.2 Water Supply Creek ....................................................................................................... 8
4 PROJECT ARRANGEMENTS ............................................................................................................... 9
4.1 Gartina Falls .............................................................................................................................. 9
4.2 Water Supply Creek ................................................................................................................ 11
5 ENERGY GENERATION ................................................................................................................... 13
5.1 Assumptions ............................................................................................................................ 13
5.2 Results ..................................................................................................................................... 14
5.3 Sensitivity ................................................................................................................................ 14
6 COST ESTIMATES ........................................................................................................................... 14
6.1 Contingency ............................................................................................................................ 14
6.2 Indirect Construction Costs ..................................................................................................... 15
6.3 Interest During Construction ................................................................................................... 15
6.4 Cost Estimate Results .............................................................................................................. 15
7 PROJECT ECONOMICS ..................................................................................................................... 15
7.1 Financing Costs ....................................................................................................................... 15
7.2 Operations & Maintenance ...................................................................................................... 15
7.3 Energy Cost Results ................................................................................................................ 16
7.3.1 Grant Funds ................................................................................................................. 16
7.3.2 Avoided Cost ............................................................................................................... 16
7.3.3 Environmental Issues ................................................................................................... 17
8 OPERATIONAL DISCUSSION............................................................................................................ 17
8.1 Utilization ................................................................................................................................ 17
8.2 Downtime ................................................................................................................................ 18
Appendix
Appendix A
Appendix B
Gartina Falls Water Supply Creek Hydroelectric Projects
Conceptual Design Report
Hoonah Hydroelectric Projects Page ii February 2011
Figures
Figure 1. Vicinity Map .................................................................................................................................. 1
Figure 2. Long-term average daily flows on Kadashan River above Hook Creek (USGS gage#
15106920) ................................................................................................................................... 3
Figure 3. Daily average flows gaged on Gartina Creek near Hoonah in 2010. ............................................ 3
Figure 4. Daily average unit runoff for water years 1976-1977 for streams on Chichagof Island. .............. 4
Figure 5. Flood frequency curve for Gartina Creek based on the methods of Curran et al, 2003. ............... 6
Figure 6. Flood frequency analysis of Kadashan River using the 37-year gaging record and
Bulletin 17B methods.................................................................................................................. 6
Figure 7. Probability of exceedance of daily discharges at Gartina Falls ..................................................... 7
Figure 8. Gartina Falls Average Monthly Flow ............................................................................................ 8
Figure 9. Measured flows at Water Supply Creek and Gartina Creek compared to flows calculated
using the drainage basin ratio. ..................................................................................................... 9
Figure 10 – Gartina Falls Conceptual Arrangement ................................................................................... 11
Figure 11 – Water Supply Creek Alternative Powerhouse Locations ........................................................ 13
Figure 12 – Energy Utilization.................................................................................................................... 17
Tables
Table 1. Record length of other stream gages on Chichagof Island. ............................................................ 4
Table 2. Drainage basin characteristics of Kadashan above Hook Creek and Gartina Creek. ..................... 5
Table 3. Drainage basin characteristics of Water Supply Creek and Gartina Creek..................................... 8
Table 4 - Gartina Falls Project Parameters ................................................................................................. 10
Table 5 - Water Supply Creek Project Parameters ...................................................................................... 12
Table 6 - Energy Summary ......................................................................................................................... 14
Table 7 - Water Supply Creek Sensitivity Analysis .................................................................................... 14
Table 8 - Cost Estimate Summary .............................................................................................................. 15
Table 9 - Energy Cost Summary ................................................................................................................. 16
Table 10 - Energy Cost Summary with State of Alaska Support ................................................................ 16
Gartina Falls & Water Supply Creek Hydroelectric Projects
Conceptual Design Report
Hoonah Hydroelectric Projects Page ES-1 February 2011
Executive Summary
HDR Alaska was contracted by the Inside Passage Electric Cooperative to develop conceptual
designs and analyze two small proposed hydroelectric projects for the community of Hoonah,
Alaska. The two projects being considered are the Gartina Falls project and the Water Supply
Creek project. Both projects are located on or near Gartina Creek approximately 3.5 miles
southeast of Hoonah. This work is being funded by grants from the U.S. Dept. of Energy and
Alaska Energy Authority.
This study prepared a conceptual design for each project along with a corresponding cost and
energy estimate. For the Water Supply Creek project, two powerhouse locations were evaluated.
The analysis concluded that each project is technically feasible. Cost estimates included the full
cost of project development and incorporated a 25% level of contingency. The first year annual
cost of energy includes financing costs, operations & maintenance, insurance and a repair and
replacement allowance. The results of the analysis are summarized below.
Table E1 - Project Summary
Gartina Falls
Water Supply Creek
Alternative
A B
Capacity, kW 445 400 500
Avg. Annual Energy, MWh 1770 1480 1650
Total Project Cost $5.8M $6.5M $7.6M
1st Year Cost of Energy $0.28 $0.37 $0.38
The current avoided cost of diesel generation in Hoonah is approximately $0.24/kWh (fuel only).
Both projects are located at or upstream of the anadromous fish barrier so environmental
concerns related to salmon should be minimal. The Gartina Falls project effectively has no
bypass reach so an environmental flow release would likely not be required. The Water Supply
Creek project will likely be required to have an environmental flow release. Any agency
requirements in excess of what was assumed in this study will reduce the amount of available
energy and adversely affect the economics of each project.
Gartina Falls & Water Supply Creek Hydroelectric Projects
Conceptual Design Report
Hoonah Hydroelectric Projects Page 1 February 2011
1 Introduction
HDR was retained by Inside Passage Electric Cooperative (IPEC) to develop conceptual level
designs for two potential small hydroelectric projects near Hoonah, AK. The Gartina Falls
project is located on Gartina Creek. The Water Supply Creek project is located on Water Supply
Creek, a tributary of Gartina Creek. Both projects are located approximately 3.5 miles southeast
of Hoonah as shown in Figure 1.
Figure 1. Vicinity Map
Gartina Falls Water Supply Creek Hydroelectric Projects
Conceptual Design Report
Hoonah Hydroelectric Projects Page 2 February 2011
The work has been performed at a conceptual level with the intent of making an estimate of the
energy potential of the basin and the cost to develop the projects. The work scope included a
field visit to the sites by team members; a review of available project documentation and related
information; development of conceptual project layouts; a review of existing hydraulic and
hydrologic parameters; an estimation of energy production and new facility costs; and
preparation of this summary report. This work did not include an in-depth geotechnical
investigation.
2 Background Information
Both projects have been investigated at a reconnaissance level several times in the past with the
most recent work being associated with the Concept Design Report and Construction Cost
Estimate for Energy Projects in the Community of Hoonah prepared for the Alaska Energy
Authority by Alaska Energy and Engineering, Inc. (AE&E) dated May 29, 2009. The AE&E
report provides a concise summary of the previous investigative efforts and therefore they are not
repeated here.
3 Hydrology
3.1 Regional Hydrology
Gartina Creek is located on NE Chichagof Island, a large (> 2000 square-mile) island in the
Alexander Archipelago. The stream is near the town of Hoonah, and 40 miles west of the Juneau.
Climate is maritime, with major storm activity in late fall (October and November), snow
accumulation at higher elevations in the winter, and cool, rainy summers. Stream runoff on the
island tends to be flashy, with very little basin storage other than high elevation snowpack.
The longest gaged stream on Chichagof Island is USGS gage # 15106920 located on the
Kadashan River above Hook Creek. The daily average flows at this gage from 1968-2007 are
shown in Figure 2. This runoff pattern is typical of moderate-sized streams on Chichagof Island.
Gartina Falls Water Supply Creek Hydroelectric Projects
Conceptual Design Report
Hoonah Hydroelectric Projects Page 3 February 2011
Figure 2. Long-term average daily flows on Kadashan River above Hook Creek (USGS gage# 15106920)
3.2 Basin Characteristics
Gartina Creek at Gartina Falls drains 10.2 miles of forested, mountainous terrain. HDR installed
a streamgage on Gartina Creek immediately upstream of Gartina Falls on 6/15/2010, and records
are currently available through 11/08/2010. During this short period of time, flows ranged from 4
cfs to 166 cfs. The highest flows occurred in the late fall, near the end of the gaging period, and
the lowest flows occurred in late summer (Figure 3).
Figure 3. Daily average flows gaged on Gartina Creek near Hoonah in 2010.
0
20
40
60
80
100
120
140
160
1 Jan 31 Jan 2 Mar 1 Apr 1 May 31 May 30 Jun 30 Jul 29 Aug 28 Sep 28 Oct 27 Nov 27 Dec
Kadashan Mean Daily Flows Kadashan Minimum Daily Flows Kadashan Annual Average
Snowmelt Fall
Rainstorms
Winter Low Flow Summer Low Flow
0
20
40
60
80
100
120
140
160
180
Jun 10 Jul 10 Aug 10 Sep 10 Oct 10Discharge (cfs)
Gartina Creek at Gartina Falls
Gartina Falls Water Supply Creek Hydroelectric Projects
Conceptual Design Report
Hoonah Hydroelectric Projects Page 4 February 2011
3.3 Comparable Gages
There are several creeks on Chichagof Island with gage records longer than 5 years, including
Tonalite Creek, Pavlof River, Kadashan River (lower and upper), Hook Creek (lower and upper),
and Indian River (lower) (Table 1). The longest gaged stream is Kadashan River above Hook
Creek, which the USGS gaged for a total of 37 years between 1968 and 2007. None of these
gages were in operation during the summer of 2010. All of the streams mentioned above have
similar unit runoff and respond to the same events. The main differences are in snowmelt runoff,
as would be expected with different drainage basin elevations (Figure 4).
Table 1. Record length of other stream gages on Chichagof Island.
Name Gage#Start End Drainage Area
Indian R Near Tenakee 15107920 10/1/1975 9/30/1982 12.9
Pavlof R Near Tenakee 15108000 6/1/1957 9/30/1981 24.3
Kadashan R Near Tenakeee 15107000 9/1/1964 9/30/1979 37.7
Tonalite Creek Near Tenakee 15106980 6/1/1968 9/30/1988 14.5
Hook Creek near Tenakee 15106960 12/1/1966 9/30/1980 8
Hook Creek above TR near Tenakee 15106940 8/1/1967 9/30/1980 4.48
Kadashan R Above Hook Creek 15106920 1/1/1968 9/30/2007 10.2
Figure 4. Daily average unit runoff for water years 1976-1977 for streams on Chichagof Island.
The closest currently active gage to Gartina Creek is Montana Creek near Juneau, 40 miles to the
Northeast on the mainland. Although Montana Creek appears to respond to the same events as
Gartina Creek and the Kadashan River, it has higher summer runoff than both systems. This is
probably due to greater snowpack as the Montana Creek basin has twice the topographic relief of
the other two basins. The statistical correlation between Montana Creek and Gartina Creek is too
0
10
20
30
40
50
60
70
80
90
100
Oct 75 Dec 75 Mar 76 Jun 76 Sep 76 Dec 76 Mar 77 Jun 77 Sep 77Unit Runoff (cfs/square mile)
Pavlof Unit Runoff
Upper Hook Unit
Runoff
Tonalite Unit Runoff
Lower Hook Unit
Runoff
Kadashan Unit Runoff
Indian Runoff
Gartina Falls Water Supply Creek Hydroelectric Projects
Conceptual Design Report
Hoonah Hydroelectric Projects Page 5 February 2011
low to make it a reliable proxy for streamflow. The Chichagof stations listed above are all much
more similar to one another than they are to Montana Creek.
3.4 Kadashan River
Kadashan River above Hook Creek is nearly identical to Gartina Creek at Gartina Falls in
drainage area and similar in relief and aspect (Gartina Creek flows NE while Kadashan flows
NW). The former gage site on Kadashan is about 30 miles south of the gage site on Gartina
Creek. Precipitation is also similar: according to data from Jones and Fahl, 1994, the Gartina
watershed receives approximately 100 inches of precipitation per year, while Kadashan receives
approximately 110 inches. There are no mapped lakes, ponds, or glaciers in either drainage
basin. Both basins are forested, although portions of the Gartina Creek basin have been clearcut.
Gartina Creek also drains elevations that are a few hundred feet higher than Kadashan River.
Based on these similarities, Kadashan River above Hook Creek is recommended as a proxy to
Gartina Creek at Gartina Falls until more data on Gartina Creek can be collected.
Table 2. Drainage basin characteristics of Kadashan above Hook Creek and Gartina Creek.
Characteristic Unit Gartina Creek
at Gartina Falls
Kadashan above
Hook
Drainage Area mile2 10.3 10.2
Main Channel Length mile 4.8 4.0
Main Channel Slope % 2.5% 1.2%
Mean Basin Elevation ft above mean sea level 1240 1040
Basin Relief ft 2900 2360
Basin Aspect NE NW
Area of Lakes and Ponds % 0 0
Mean Annual Precip inches 100 110
Mean Min Jan Temp °F 24 24
Area of Glaciers % 0 0
Average Annual Runoff cfs/mile2 -- 6.4
3.5 Flood Frequency Analysis
Two methods are used to estimate flood magnitude and frequency for Gartina Creek at Gartina
Falls. The first is based on regression equations in Curran et al., 2003. This 100-year flood
estimate is 3900 cfs, and the 2-year flood estimate is 1390 (Figure 5). This is very similar to the
mean annual recorded peak on Kadashan River of 1325 cfs.
Gartina Falls Water Supply Creek Hydroelectric Projects
Conceptual Design Report
Hoonah Hydroelectric Projects Page 6 February 2011
Figure 5. Flood frequency curve for Gartina Creek based on the methods of Curran et al, 2003.
The second method is a Bulletin 17B analysis of flows at Kadashan River above Hook Creek.
The Bulletin 17B analysis using 37 years of record returns a 100-year flood of 2500 cfs and a 2-
year flood of 1100 cfs (Figure 6). The Bulletin 17B analysis has a smaller standard error than the
regression analysis and is therefore likely to be more accurate.
Figure 6. Flood frequency analysis of Kadashan River using the 37-year gaging record and Bulletin 17B
methods.
0
2000
4000
6000
8000
10000
0 100 200 300 400 500Flood Discharge (cfs)
Return Interval (years)
Regression based Flood Frequency Analysis
Flood Discharge 5% Confidence 95% Confidence
0
500
1000
1500
2000
2500
3000
3500
4000
4500
0 100 200 300 400 500Flood Discharge (cfs)
Return Interval (years)
Bulletin 17B Analysis of Kadashan River
Flood Discharge 5% Confidence 95% Confidence
Gartina Falls Water Supply Creek Hydroelectric Projects
Conceptual Design Report
Hoonah Hydroelectric Projects Page 7 February 2011
3.6 Hydrology Summary
3.6.1 Gartina Creek at Gartina Falls
Ideally, a historical record of stream flow of 30 years or more is desirable to analyze a stream of
interest. However, long-term stream flow records are not usually available for small or remote
streams and synthesized data is often created. For this study, the daily flows recorded on the
Kadashan River above Hook Creek were considered representative of the flows to be expected at
the Gartina Creek at Gartina Falls project site.
A flow duration curve and a graph of average monthly flows for the project site was produced
using this data and is shown in Figures 7 and 8.
Figure 7. Probability of exceedance of daily discharges at Gartina Falls
0
100
200
300
400
500
600
700
800
900
1000
0 10 20 30 40 50 60 70 80 90 100Discharge (cfs)
Probability of Exceedance (%)
Gartina Falls Flow Duration Curve
Gartina Falls Water Supply Creek Hydroelectric Projects
Conceptual Design Report
Hoonah Hydroelectric Projects Page 8 February 2011
Figure 8. Gartina Falls Average Monthly Flow
3.6.2 Water Supply Creek
Water Supply Creek is a small, steep drainage basin that is tributary to Gartina Creek. The creek
was gaged concurrently with Gartina Creek in the summer and fall of 2010. This gage was
located at the existing water supply intake. Basin characteristics of Water Supply Creek at the
gage and upstream at the proposed hydroelectric intake, along with a comparison to Gartina
Creek are shown in Table 3.
Table 3. Drainage basin characteristics of Water Supply Creek and Gartina Creek.
Characteristic Unit
Water
Supply Creek
at Gage
Water Supply
Creek at
Proposed Hydro
Intake
Gartina
Creek at
Gartina Falls
Kadashan above
Hook
Drainage Area mile2 1.9 1.5 10.3 10.2
Main Channel Length mile 2.0 1.2 4.8 4.0
Main Channel Slope % 7.5% 7.1% 2.5% 1.2%
Mean Basin Elevation ft msl 1570 1800 1240 1040
Basin Relief ft 2720 2390 2900 2360
Basin Aspect NE NE NE NW
Area of Lakes and Ponds % 0 0 0 0
Mean Annual Precip inches 100 100 100 110
Mean Min Jan Temp °F 24 24 24 24
Area of Glaciers % 0 0 0 0
Average Annual Runoff cfs/mile2 -- -- -- 6.4
0
20
40
60
80
100
120
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug SepFlow, cfs
Gartina Falls
Average Monthly Flow
Gartina Falls Water Supply Creek Hydroelectric Projects
Conceptual Design Report
Hoonah Hydroelectric Projects Page 9 February 2011
A direct comparison of Water Supply Creek to Gartina Creek at the gage locations by drainage
basin gives a ratio of 0.19. This ratio yields a very close fit to measured flows during the summer
of 2010 (Figure 9).
Synthesized flows for Water Supply Creek at the intake site were derived by scaling the Gartina
Falls data by the ratios of drainage basins (0.15).
Figure 9. Measured flows at Water Supply Creek and Gartina Creek compared to flows calculated using the
drainage basin ratio.
4 Project Arrangements
4.1 Gartina Falls
The Gartina Falls hydroelectric project will be a low-head small hydroelectric project located on
Gartina Creek at Gartina Falls, approximately 3.5 miles southeast of Hoonah. There does not
appear to be a technically convenient way of creating a meaningful amount of storage. Therefore,
the project will operate in a run-of-river mode.
The following are the proposed project features:
A diversion structure at the head of Gartina Falls that will raise the water surface
approximately 15 feet. The diversion will consist of a center section with an inflatable
gate and concrete abutments. The abutments will have grouted rock fill on the
downstream side to provide stability. The center gate section will be lowered during high
flow events to add flood capacity and to pass accumulated sediment.
0
20
40
60
80
100
120
Gartina Measured Water Supply Measured Drainage Comparison
Gartina Falls Water Supply Creek Hydroelectric Projects
Conceptual Design Report
Hoonah Hydroelectric Projects Page 10 February 2011
A concrete intake structure and sluiceway on the left (west) abutment of the diversion
dam. The flow diverted to the power plant will first enter the sluiceway, and then be
drawn through a trashrack into an intake chamber.
A 54-inch-diameter steel pipeline (penstock), about 220 feet long, will convey water from
the intake structure to the powerhouse. The initial 120 feet of the pipeline will have a
mild slope and be located on a bench cut into the hillside roughly parallel to the stream.
The final 100 feet will drop steeply down the hillside to the powerhouse.
A powerhouse approximately 25 feet by 20 feet and 15 feet high.
A horizontal axis cross-flow (Ossberger) turbine and induction generator with a rated
capacity of 445 kW.
A rock-lined tailrace to return flows to Gartina Creek near the base of Gartina Falls.
A small substation/switchyard located adjacent to the powerhouse.
A 12.5 kV transmission line, approximately 4.5 miles long, to transmit the power from
the substation/switchyard to an interconnection near the Hoonah airport.
An access road, approximately 0.5 miles long, connecting the powerhouse and the intake
structure to the existing timber harvest road 8503.
Pertinent project features are shown in Table 4. A project schematic is shown in Figure 10.
Project layout drawings and detailed project information is presented in Appendix A.
Table 4 - Gartina Falls Project Parameters
Headwater, ft 232
Tailwater, ft 170
Turbine Centerline, ft 177
Net Head at design flow1 ft 58
Design Flow, cfs 110
Capacity, kW 445
Avg. Inflow, cfs 76
Active Storage, AF 0
1Assumes 67% energy recovery from draft tube
Gartina Falls Water Supply Creek Hydroelectric Projects
Conceptual Design Report
Hoonah Hydroelectric Projects Page 11 February 2011
Figure 10 – Gartina Falls Conceptual Arrangement
4.2 Water Supply Creek
The Water Supply hydroelectric project will be a medium head small hydroelectric project
located on Water Supply Creek, approximately 5 miles south of Hoonah. There does not appear
to be a technically convenient way of creating a meaningful amount of storage. Therefore, the
project will operate in a run-of-river mode.
The following are the proposed project features:
A diversion structure located on Water Supply Creek at elevation 768 that will raise the
water surface approximately 8 feet. The diversion structure will consist of a concrete core
wall with grouted riprap embankments.
A concrete intake structure and sluiceway on the right abutment of the diversion
structure. The flow diverted to the power plant will first enter the sluiceway, and then be
drawn through a trashrack into an intake chamber.
A low-level outlet to release environmental flows into the bypass reach of Water Supply
Creek.
A 20-inch-diameter steel pipeline (penstock) will convey water from the intake structure
to the powerhouse. The initial 1800 feet of the pipeline would have a mild slope and be
located on a bench cut into the hillside roughly parallel to the stream. The remaining
penstock to the powerhouse will be buried.
A powerhouse approximately 24 feet by 36 feet and 15 feet high.
A horizontal axis Turgo turbine and induction generator.
A rock-lined tailrace to return flows to Water Supply Creek.
A small substation/switchyard located adjacent to the powerhouse.
Gartina Falls Water Supply Creek Hydroelectric Projects
Conceptual Design Report
Hoonah Hydroelectric Projects Page 12 February 2011
A 12.5 kV transmission line to transmit the power from the substation/switchyard to an
interconnection near the Hoonah airport.
An access road connecting the intake structure to the existing timber harvest road 8503.
Two possible powerhouse locations were evaluated. The first location is immediately
downstream of the existing City of Hoonah water supply intake. The second location is just
upstream of the point where Water Supply Creek flows into Gartina Creek.
Table 5 - Water Supply Creek Project Parameters
Alternative
A B
Headwater, ft 778 778
Tailwater, ft 358 248
Penstock length, ft 5100 6800
Access road, mi 1.0 1.3
Transmission line, mi 4.25 4.5
Turbine Centerline, ft 365 255
Net Head, ft 369 465
Design Flow, cfs 15 15
Capacity, kW 400 500
Avg. Inflow, cfs 11 11
Active Storage, AF 0 0
Gartina Falls Water Supply Creek Hydroelectric Projects
Conceptual Design Report
Hoonah Hydroelectric Projects Page 13 February 2011
Figure 11 – Water Supply Creek Alternative Powerhouse Locations
Project layout drawings and detailed project information is presented in Appendix B.
5 Energy Generation
The energy generation for the projects was estimated using HDR’s proprietary software
“Hydroelectric Evaluation Program” (HEP). HEP has been specifically designed to model run-
of-river operations. HEP uses tabulated daily flows, turbine and generator efficiencies, friction
coefficients and physical parameters to simulate energy production through a period of record.
Turbine and generator efficiencies are determined from tables. Output from HEP consists of
effective capacity rating of the unit(s), simulated production in MWh, percent operating time and
overall plant factor.
5.1 Assumptions
The following are the key assumptions used in modeling energy production:
There would be no environmental flows required at the Gartina Falls project
For the Water Supply Creek project it is assumed that an environmental flow release into
the bypass will be a requirement of the resource agencies. A portion of the environmental
flow release will subsequently be used for water supply. A water supply reservation of 1
cfs was assumed for all cases.
Losses totaling 3% were included for station service, transformer and transmission losses
and scheduled downtime.
Gartina Falls Water Supply Creek Hydroelectric Projects
Conceptual Design Report
Hoonah Hydroelectric Projects Page 14 February 2011
5.2 Results
Using these assumptions and the project configurations described above, the average annual
energy generation for each project alternative is shown below in Table 6.
Table 6 - Energy Summary
Gartina Falls
Water Supply Creek
Alternative
A B
Environmental Flow, cfs 0 1 2
Avg. Annual Energy, MWh 1770 1480 1650
Capacity, kW 445 400 500
Plant factor .45 .43 .38
Days shutdown due to low water 27 73 107
5.3 Sensitivity
To determine the effect of different environmental flow requirements for Water Supply Creek,
two additional energy simulations were made assuming an additional 1 cfs would be required.
The results are shown in Table 7 below.
Table 7 - Water Supply Creek Sensitivity Analysis
Water Supply Creek
Alternative
A B
Environmental Flow, cfs 2 3
Avg. Annual Energy, MWh 1310 1460
Capacity, kW 400 500
Plant factor .38 .34
Days shutdown due to low water 107 140
6 Cost Estimates
An opinion of probable construction costs was derived for the projects presented above. The
approach used was to develop base work units and unit prices and then apply these units and
prices consistently to the various project features.
6.1 Contingency
A contingency of 25% was added to the the direct construction costs to reflect the uncertainty of
the layout and design that won’t be resolved until later in the development process.
Gartina Falls Water Supply Creek Hydroelectric Projects
Conceptual Design Report
Hoonah Hydroelectric Projects Page 15 February 2011
6.2 Indirect Construction Costs
Indirect construction costs associated with engineering, licensing, permitting, construction
management, and owner’s administration were added to the cost estimate as either percentages or
lump sum amounts.
6.3 Interest During Construction
An assumed financial cost representing the interest accrued at 5% APR during an 18 month
construction period was also included.
6.4 Cost Estimate Results
The results are shown in Table 8 below.
Table 8 - Cost Estimate Summary
Gartina
Creek
Water Supply Creek
Alternative
A B
Direct Construction Costs 3,600,000 $4,200,000 $4,900,000
Contingency 900,000 $1,050,000 $1,125,000
Engineering, Licensing & Permitting 730,000 $620,000 $690,000
Owners Administration 180,000 $210,000 $245,000
Construction Management 180,000 $210,000 $245,000
Interest During Construction 200,000 $230,000 $265,000
Total Project Costs 5,790,000 $6,520,000 $7,570,000
7 Project Economics
A detailed economic evaluation was not included in the scope of this work. However, in order to
get a conceptual view of the economics of the project generic financial assumptions were made.
The results are presented as the first year estimated annual costs per kWh in 2011 dollars. The
assumptions and results are presented below.
7.1 Financing Costs
Annual financing costs were determined assuming 100% debt and a constant principal and
interest payment calculated over 30 years at a 5% APR. All project costs have been assumed to
be capitalized.
7.2 Operations & Maintenance
First year O&M expense was assumed to include labor, direct and indirect expenses and
insurance. It was assumed that the project would be designed for un-manned operations and
would be part of a larger organization thereby the project would experience lower administrative
expenses. On-site O&M labor would be limited to periodic inspections and seasonal
Gartina Falls Water Supply Creek Hydroelectric Projects
Conceptual Design Report
Hoonah Hydroelectric Projects Page 16 February 2011
maintenance. Total labor, expenses and owner’s G&A expenses were estimated at $50,000/yr. A
repair and replacement fund of $5,000 was also included. General liability and business
interruption insurance was estimated at $1.00 per $100.00 of asset. Any royalties associated
with land use are unknown and therefore have not been included.
7.3 Energy Cost Results
The average first year cost of energy for each of the projects is shown below in Table 9.
Table 9 - Energy Cost Summary
Gartina
Creek
Water Supply Creek
Alternative
A B
Average First Year Energy Cost, kWh $0.28 $0.37 $0.38
As with all hydroelectric projects, once the debt is paid off the only costs would be for O&M and
the energy costs will be significantly lower.
7.3.1 Grant Funds
The primary cost of energy values above do not reflect the benefit of any grant funds or low
interest loans often made available to rural energy projects in Alaska. The following table shows
the impact of several scenarios reflecting State of Alaska assistance.
Table 10 - Energy Cost Summary with State of Alaska Support
Average First Year Energy Cost, kWh
Scenario Gartina
Falls
Water Supply Creek
Alternative
A B
Zero interest loan $0.17 $0.23 $0.23
$1M Grant Funds $0.23 $0.32 $0.33
$3M Grant Funds $0.15 $0.22 $0.24
$5M Grant Funds $0.06 $0.11 $0.15
7.3.2 Avoided Cost
The cost of hydroelectric energy will undoubtedly be compared to the equivalent cost of diesel
generation. IPEC’s current diesel plant produces 14.3 kWh per gallon of diesel fuel. At the
current average price of $3.50 per gallon, the raw generation cost of diesel generation is
$0.24/kWh. Hydroelectric power would also defer maintenance costs associated with diesel
generation but these savings are not reflected in the first year cost of energy comparison.
Gartina Falls Water Supply Creek Hydroelectric Projects
Conceptual Design Report
Hoonah Hydroelectric Projects Page 17 February 2011
7.3.3 Environmental Issues
Environmental issues for hydropower projects typically center on fisheries issues. The fisheries
issue likely to have the greatest impact on project economics is the environmental flow that must
be maintained in the bypass reach. For the Gartina Falls project, the bypass reach is negligible so
it is unlikely that environmental flow release will be required.
For Water Supply Creek, there is a significant bypass reach and it has been documented that
resident fish reside in this area. Therefore, it is almost certain that an environmental release will
be required from the intake. A nominal 1 cfs has been assumed however this value is subject to
change following discussions with resource agencies. Increases in the environmental flow to
meet fisheries requirements or domestic water supply needs would have an adverse affect on
project economics for Water Supply Creek.
8 Operational Discussion
The following section discusses issues surrounding the conclusions reached in this study work
and the actual operation of the projects.
8.1 Utilization
For small electrical systems in Alaska, such as the one in Hoonah, the primary benefit from a
hydroelectric project comes from the avoided cost of diesel generation. However, operational
constraints necessary to provide a stable electrical system may limit the amount of energy from a
run-of-river hydroelectric that can be effectively utilized. To provide an initial assessment of
utilization, the energy potential of the projects was compared to the actual generation in 2010 as
shown in Figure 12 below.
Figure 12 – Energy Utilization
0
50
100
150
200
250
300
350
400
450
500
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov DecMWhHoonah Energy Generation
Diesel
Gartina Falls
Water Supply Creek Alt. A
Combined Hydro
Gartina Falls Water Supply Creek Hydroelectric Projects
Conceptual Design Report
Hoonah Hydroelectric Projects Page 18 February 2011
As is shown in Figure 12, either one of the hydro projects could easily fit into the existing
electrical generation profile of the system and be 100% utilized. In the case of both projects
being constructed, there would need to be some curtailment of generation as diesel generation
would always need to remain on the system to provide frequency control. In the case of both
projects being available, curtailment of hydro generation in the order of 10-15% would likely
need to occur.
8.2 Downtime
The energy simulations indicate that either of the projects would experience some level of
downtime due to low water. For run-of-river projects this is to be expected during low water
years and/or periods of low flow on the annual hydrograph. However, in the case of Water
Supply Creek, this problem is exacerbated with increasing environmental flows in the bypass
reach. Prolonged downtimes can lead to increased maintenance and operational difficulties.
Gartina Falls & Water Supply Creek Hydroelectric Projects
Conceptual Design Report
Hoonah Hydroelectric Projects Page A-1 February 2011
Appendix A
GARTINA.OUT E (s16.66H ---------------------------------------------------------------------------------------------------------------------------- Gartina Falls POWER GENERATION ----------------------------------------------------------------------------------------------------------------------------DATA FILE USED: 15106920.QCHMODEL DESCRIPTION-----------------PIPE # LENGTH DIAMETER MANNING'S n MINOR LOSSES 1 220 54 .011 2 HEADWATER ELEV: 232 TAILWATER ELEV: 172 GROSS HEAD: 60 NET HEAD @ FULL LOAD: 58.0NAMEPLATE CAPACITY (kW): 445.0 @ 1 POWER FACTORSTATION SERVICE LOSS: .5 TRANSFORMER LOSS: .5 TRANSMISSION LOSS: 1 SCHEDULED DOWN TIME: 1 TURBINE SELECTED: 1 - CROSS-FLOWGENERATOR SELECTED: INDUCTION W/ GEARBOX MINIMUM INSTREAM FLOWS OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP ---------------------------------------------------------------------------------------------------------------------------- 0 0 0 0 0 0 0 0 0 0 0 0 SIMULATED PRODUCTION IN MEGAWATT-HOURS YEAR OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP TOTAL ---------------------------------------------------------------------------------------------------------------------------- 1969 219.2 176.7 36.6 0.0 0.0 40.2 248.0 312.3 180.9 136.6 124.3 118.1 1593.0 1970 117.1 200.3 188.5 43.9 169.1 181.1 150.1 252.7 198.7 151.8 118.3 180.9 1952.6 1971 246.3 136.1 149.0 100.5 58.7 56.8 118.2 304.8 295.6 125.6 111.8 183.9 1887.5 1972 214.6 151.5 37.7 45.9 22.3 64.4 80.0 306.9 305.8 169.0 161.9 131.6 1691.6 1973 219.5 145.6 56.4 46.4 60.6 58.7 232.0 314.7 275.8 102.6 138.3 158.1 1808.7 1974 248.7 41.4 83.0 3.2 108.2 9.5 164.1 318.0 225.1 100.3 54.1 132.6 1488.1 1975 308.9 265.2 183.7 82.4 19.1 8.3 89.3 297.7 279.2 162.7 71.6 150.7 1918.7 1976 198.1 89.9 139.5 116.9 80.7 145.4 152.2 300.2 279.8 174.8 70.2 170.3 1918.0 1977 237.9 238.9 218.5 177.3 229.2 117.3 211.1 182.7 179.0 63.9 8.5 108.2 1972.4 1978 217.3 99.8 6.2 27.9 52.1 81.3 194.8 259.5 125.5 60.5 20.5 80.6 1225.9 1981 244.6 218.4 79.4 242.6 96.1 129.6 91.4 123.7 67.4 74.9 96.5 202.2 1666.9 1982 203.7 234.4 146.7 103.0 16.3 44.9 124.7 297.9 179.6 62.3 44.9 120.0 1578.4 1983 253.9 131.8 89.5 180.8 109.7 99.5 192.8 231.3 71.5 31.3 164.9 168.4 1725.4 1984 241.9 96.1 15.1 177.8 211.4 234.4 122.8 153.2 137.2 101.6 105.5 104.5 1701.5 1985 171.1 119.8 129.2 275.6 182.0 101.3 155.0 295.9 273.8 157.8 83.6 106.7 2051.8 1986 211.1 66.1 164.5 183.1 100.7 225.0 165.0 265.9 233.9 69.3 95.8 39.9 1820.4 1987 251.8 136.5 242.8 198.1 154.6 80.4 208.4 264.0 221.0 69.9 11.5 180.4 2019.4 1988 297.4 276.7 218.0 92.0 151.9 187.9 171.1 262.7 175.1 77.9 91.9 158.9 2161.6Page 1
GARTINA.OUT 1989 279.3 229.9 108.8 87.5 44.3 21.9 203.7 271.0 98.1 2.4 16.3 115.0 1478.3 1990 221.5 190.7 260.9 111.3 98.7 174.3 237.6 214.7 85.2 63.5 87.1 169.2 1914.7 1991 233.0 116.2 133.2 111.9 149.5 74.4 228.0 299.5 186.8 73.1 126.8 245.8 1978.2 1992 258.0 274.5 219.1 253.3 150.8 171.1 158.2 210.5 166.6 55.8 89.3 203.9 2211.2 1993 178.8 210.1 149.7 87.2 149.9 179.4 261.8 234.9 67.7 6.1 10.8 96.1 1632.7 1994 173.8 241.1 222.9 122.7 42.9 253.2 286.6 241.0 123.0 57.1 38.0 203.2 2005.5 1995 320.0 191.6 98.4 76.8 147.9 81.9 260.8 251.2 103.6 48.8 78.6 90.0 1749.6 1996 222.2 145.9 105.4 37.1 34.5 115.5 176.6 168.9 115.6 45.5 98.8 187.3 1453.3 1997 202.3 126.5 97.8 22.2 184.8 86.3 204.0 226.4 74.8 86.7 82.0 129.8 1523.5 1998 199.8 171.6 260.1 97.3 146.6 87.6 135.8 142.9 51.4 63.2 117.1 148.3 1621.7 1999 205.7 170.1 176.7 149.3 37.7 90.7 217.1 302.3 271.2 118.1 123.1 203.5 2065.4 2000 288.1 214.1 196.0 97.1 69.6 174.4 188.7 226.1 179.1 107.4 104.0 196.6 2041.2 2001 222.4 194.7 132.7 198.0 98.0 115.5 105.0 210.6 155.3 85.3 49.1 212.8 1779.5 2002 244.4 179.2 116.5 106.3 109.5 42.3 62.7 238.5 146.4 62.1 165.5 159.8 1633.1 2003 221.8 144.2 158.6 162.7 90.4 85.2 128.4 112.8 79.4 26.0 29.8 215.0 1454.5 2004 158.3 144.4 171.1 131.4 181.7 157.6 229.0 233.3 65.0 8.5 1.1 147.9 1629.3 2005 187.8 232.4 231.8 58.9 115.9 180.2 176.6 130.2 41.0 93.8 90.8 195.1 1734.4 2006 210.2 198.3 208.2 108.2 79.0 53.7 82.1 198.6 96.3 38.7 65.4 204.2 1543.0 2007 233.4 49.4 145.0 143.9 67.6 62.6 213.2 302.8 269.2 158.0 30.3 184.7 1860.1AVERAGE 226.1 168.9 145.3 115.1 103.3 110.1 173.7 242.2 164.3 83.6 80.5 156.9 1770.0AVERAGE PLANT FACTOR: 0.45AVG. # DAYS/YEAR SHUTDOWN DUE TO LOW WATER: 27 THIS SIMULATION USED THE FOLLOWING EQUIPMENT EFFICIENCIES % LOAD TURBINE GENERATOR COMBINED ---------------------------------------- 0 0.0 0.0 0.0 10 82.0 89.7 73.5 20 86.3 92.0 79.4 30 86.8 93.4 81.1 40 87.0 94.0 81.8 50 87.0 94.3 82.0 60 87.0 94.5 82.2 70 83.9 94.7 79.4 80 87.0 94.7 82.4 90 87.0 94.7 82.4 100 87.0 94.7 82.4Page 2
Item Quantity Unit Unit Cost Amount
330 LAND AND LAND RIGHTS
.1 Land Rights - Generation Plant 0 LS 50,000$ -$
.2 Special use permits 0 LS 50,000$ -$
.3 Surveying 1 LS 20,000$ 20,000$
331 STRUCTURES AND IMPROVEMENTS
.1 POWERHOUSE
.1 Excavation 350 CY 75$ 26,250$
.2 Concrete (incl. reinforcement) 90 CY 1,500$ 135,000$
.3 Metal Building SF 125$ -$
.4 Misc. Metals 1 LS 5,000$ 5,000$
.5 HVAC, Plumbing & Electrical 1 LS 50,000$ 50,000$
.6 Grounding Grid 1 LS 10,000$ 10,000$
.7 Fire Protection 1 LS 10,000$ 10,000$
332 RESERVOIRS, DAMS AND WATERWAYS
.1 SITE WORK
.1 Clearing/Drainage/Erosion Control 1 LS 50,000$ 50,000$
.2 DAM AND SPILLWAY
.1 Excavation 180 CY 50$ 9,000$
.2 Care of Water/Diversion 1 LS 50,000$ 50,000$
.3 Concrete (structural) 50 CY 1,500$ 75,000$
.4 Concrete (mass) 30 CY 500$ 15,000$
.5 Riprap 180 CY 100$ 18,000$
.6 Obermeyer Gate
.a Equipment Package, Controls, and Misc Hardware 1 LS 210,000$ 210,000$
.b Installation 1 LS 15,000$ 15,000$
.c Foundation Concrete (structural) 60 CY 1,500$ 90,000$
.3 INTAKE
.1 Excavation 150 CY 50$ 7,500$
.2 Care of Water/Diversion 1 LS 10,000$ 10,000$
.3 Trash racks 1 LS 2,500$ 2,500$
.4 Shutoff Valve w/operator 1 LS 75,000$ 75,000$
.5 Concrete (structural) 180 CY 1,500$ 270,000$
.6 Concrete (mass) 0 CY 500$ -$
.7 Misc. Metals 1 LS 10,000$ 10,000$
.8 Misc. electrical & mechanical 1 LS 60,000$ 60,000$
.9 Intake Building 1 LS 5,000$ 5,000$
.4 SLUICEWAY
.1 Excavation 40 CY 50$ 2,000$
.2 Concrete (structural) 70 CY 1,500$ 105,000$
.3 Gate w/operator 1 LS 25,000$ 25,000$
.4 Misc. Metals 1 LS 5,000$ 5,000$
.5 WATER CONDUCTORS AND ACCESSORIES
.1 PENSTOCK
.a Clearing 0.3 ACRE 25,000$ 6,313$
.b Excavation 500 CY 75$ 37,500$
.c Fill 300 CY 100$ 30,000$
.d penstock material 220 LF 687$ 151,231$
.e Concrete (thrust blocks and supports) 50 CY 1,500$ 75,000$
.f Exposed Penstock installation 1 LS 25,000$ 25,000$
.g Buried Penstock installation 1 LS 10,000$ 10,000$
.h Mid Span Support 1 LS 15,000$ 15,000$
.2 TAILRACE
.a Excavation 1 LS 5,000$ 5,000$
.b Support and lining 1 LS 2,500$ 2,500$
333 WATERWHEELS, TURBINES AND GENERATORS
.1 Supply 445 kW 1,200$ 534,000$
.2 Install 1 LS 60,000$ 60,000$
334 ACCESSORY ELECTRICAL EQUIPMENT
.1 Switchgear 1 LS 75,000$ 75,000$
.2 Station Service 1 LS 30,000$ 30,000$
.4 PLC Controls, Panel, and Generator Wiring 1 LS -$ -$
.5 Conduit/wires/cables 1 LS 25,000$ 25,000$
335 MISC. POWER PLANT EQUIPMENT
.1 Cooling Water System 1 LS 25,000$ 25,000$
.2 Powerhouse crane rail 1 LS 5,000$ 5,000$
336 ROADS, RAILROADS AND BRIDGES
.1 Upgrade Existing Road 0.0 MI 50,000$ -$
.2 New Road to Intake and Powerhouse 0.5 MI 250,000$ 125,000$
.3 Clearing/Drainage/Erosion Control 1 LS 10,000$ 10,000$
IPEC Hoonah Hydropower
OPINION OF PROBABLE COST
Gartina Falls
350 LAND AND LAND RIGHTS
.1 Land rights - transmission line 0 LS -$
352
STRUCTURES AND IMPROVEMENTS
(TRANSMISSION FACILITY)
.1 Substation foundations 1 LS 10,000$ 10,000$
.2 Oil spill containment 1 LS 10,000$ 10,000$
.3 Grounding grid 1 LS 15,000$ 15,000$
353 STATION EQUIPMENT
.1 Generator Step-up Transformer- 600 kVA 1 LS 30,000$ 30,000$
.2 Disconnects 3 LS 10,000$ 30,000$
.3 Surge Arrestors 3 LS 2,000$ 6,000$
356 OVERHEAD CONDUCTORS & DEVICES
.1 Overhead Transmission Line 4.25 MI 180,000$ 765,000$
.2 ROW Clearing 4.25 MI 10,000$ 42,500$
397 Communication and Control Equipment
.1 Telemetry and Communications Equipment 1.0 LS 75,000$ 75,000$
Total Direct Construction Costs 3,600,000$
Contingency 25% 900,000$
Design Engineering 10% 360,000$
Licensing & permitting 370,000$
Owner's General Administration & overhead 5% 180,000$
Construction Management 5% 180,000$
Subtotal 5,590,000$
Interest During Construction 5% 18 months 202,000$
Total 5,792,000$
HTS -INC
HYDROPOWER TURBINE SYSTEMS, INC.
PO Box 736
Hayes, VA, USA 23072
TEL: 804-360-7992
FAX: 866-552-9946
January 29, 2011 Email:hts-inc@hts-inc.com
E S T I M A T E
RE: P-2534-1 GARTINA FALLS HYDRO ELECTRIC PROJECT in ALASKA
OSSBERGER TURBINE/GENERATOR SET
Price Estimate : EUR 320,000
Option for AISI 316 alloy EUR 90,000
HYDROPOWER TURBINE SYSTEMS, INC.
Gartina Falls & Water Supply Creek Hydroelectric Projects
Conceptual Design Report
Hoonah Hydroelectric Projects Page B-1 February 2011
Appendix B
Item Quantity Unit Unit Cost Amount
330 LAND AND LAND RIGHTS
.1 Land Rights - Generation Plant LS 50,000$ -$
.2 Special use permits LS 50,000$ -$
.3 Surveying 1 LS 40,000$ 40,000$
331 STRUCTURES AND IMPROVEMENTS
.1 POWERHOUSE
.1 Excavation 200 CY 75$ 15,000$
.2 Concrete (incl. reinforcement) 50 CY 1,500$ 75,000$
.3 Metal Building 864 SF 125$ 108,000$
.4 Misc. Metals 1 LS 5,000$ 5,000$
.5 HVAC, Plumbing & Electrical 1 LS 50,000$ 50,000$
.6 Grounding Grid 1 LS 10,000$ 10,000$
.7 Fire Protection 1 LS 10,000$ 10,000$
332 RESERVOIRS, DAMS AND WATERWAYS
.1 SITE WORK
.1 Clearing/Drainage/Erosion Control 1 LS 50,000$ 50,000$
.2 DAM AND SPILLWAY
.1 Excavation 180 CY 50$ 9,000$
.2 Care of Water/Diversion 1 LS 25,000$ 25,000$
.3 Concrete (structural) 45 CY 1,500$ 66,750$
.4 Concrete (mass) 10 CY 500$ 5,000$
.5 Riprap 170 CY 100$ 17,000$
.3 INTAKE
.1 Excavation 60 CY 50$ 3,000$
.2 Care of Water/Diversion 1 LS 10,000$ 10,000$
.3 Trash racks 1 LS 2,500$ 2,500$
.4 Shutoff Gate w/operator 1 LS 15,000$ 15,000$
.5 Concrete (structural) 30 CY 1,500$ 45,000$
.6 Concrete (mass) 0 CY 500$ -$
.7 Misc. Metals 1 LS 10,000$ 10,000$
.8 Misc. electrical & mechanical 1 LS 50,000$ 50,000$
.4 SLUICEWAY
.1 Excavation 180 CY 50$ 9,000$
.2 Concrete (structural) 60 LS 1,500$ 90,000$
.3 Gate w/operator 1 LS 25,000$ 25,000$
.4 Misc. Metals 1 LS 5,000$ 5,000$
.5 WATER CONDUCTORS AND ACCESSORIES
.1 PENSTOCK
.a Clearing 5.9 ACRE 25,000$ 146,350$
.b 0.125 in penstock material 1800 LF 80$ 144,000$
.c 0.1875 in penstock material 2800 LF 110$ 308,000$
.d 0.25 in penstock material 500 LF 140$ 70,000$
.e Concrete (thrust blocks and supports) 50 CY 1,500$ 75,000$
.f Exposed Penstock installation 2300 LF 100$ 230,000$
.g Buried Penstock installation 2800 LF 125$ 350,000$
.h Slope stabilization/benching 1800 LF 150$ 270,000$
.2 TAILRACE
.a Excavation 1 LS 25,000$ 25,000$
.b Support and lining 1 LS 25,000$ 25,000$
333 WATERWHEELS, TURBINES AND GENERATORS
.1 Supply 400 kW 850$ 340,000$
.2 Install 1 LS 150,000$ 150,000$
334 ACCESSORY ELECTRICAL EQUIPMENT
.1 Switchgear 1 LS 75,000$ 75,000$
.2 Station Service 1 LS 30,000$ 30,000$
.4 PLC Controls, Panel, and Generator Wiring 1 LS -$ -$
.5 Conduit/wires/cables 1 LS 25,000$ 25,000$
335 MISC. POWER PLANT EQUIPMENT
.1 Cooling Water System 1 LS 25,000$ 25,000$
.2 Powerhouse crane rail 1 LS 25,000$ 25,000$
336 ROADS, RAILROADS AND BRIDGES
.1 Upgrade Existing Road 0.9 MI 50,000$ 45,000$
.2 New Road to Intake and Powerhouse 0.1 MI 250,000$ 25,000$
.3 Clearing/Drainage/Erosion Control 1 LS 50,000$ 50,000$
350 LAND AND LAND RIGHTS
.1 Land rights - transmission line LS -$
IPEC Hoonah Hydropower
OPINION OF PROBABLE COST
Water Supply Creek - Option 1
352
STRUCTURES AND IMPROVEMENTS
(TRANSMISSION FACILITY)
.1 Substation foundations 1 LS 10,000$ 10,000$
.2 Oil spill containment 1 LS 10,000$ 10,000$
.3 Grounding grid 1 LS 15,000$ 15,000$
353 STATION EQUIPMENT
.1 Generator Step-up Transformer- 500 kVA 1 LS 30,000$ 30,000$
.2 Disconnects 3 LS 10,000$ 30,000$
.3 Surge Arrestors 3 LS 2,000$ 6,000$
356 OVERHEAD CONDUCTORS & DEVICES
.1 Overhead Transmission Line 4.25 MI 180,000$ 765,000$
.2 ROW Clearing 4.25 MI 10,000$ 42,500$
397 Communication and Control Equipment
.1 Telemetry and Communications Equipment 1.0 LS 75,000$ 75,000$
Total Direct Construction Costs 4,200,000$
Contingency 25% 1,050,000$
Design Engineering 10% 420,000$
Licensing & permitting 200,000$
Owner's General Administration & overhead 5% 210,000$
Construction Management 5% 210,000$
Subtotal 6,290,000$
Interest During Construction 5% 18 months 228,000$
Total 6,518,000$
Item Quantity Unit Unit Cost Amount
330 LAND AND LAND RIGHTS
.1 Land Rights - Generation Plant 0 LS 50,000$ -$
.2 Special use permits 0 LS 50,000$ -$
.3 Surveying 1 LS 40,000$ 40,000$
331 STRUCTURES AND IMPROVEMENTS
.1 POWERHOUSE
.1 Excavation 200 CY 75$ 15,000$
.2 Concrete (incl. reinforcement) 50 CY 1,500$ 75,000$
.3 Metal Building 864 SF 125$ 108,000$
.4 Misc. Metals 1 LS 5,000$ 5,000$
.5 HVAC, Plumbing & Electrical 1 LS 50,000$ 50,000$
.6 Grounding Grid 1 LS 10,000$ 10,000$
.7 Fire Protection 1 LS 10,000$ 10,000$
332 RESERVOIRS, DAMS AND WATERWAYS
.1 SITE WORK
.1 Clearing/Drainage/Erosion Control 1 LS 50,000$ 50,000$
.2 DAM AND SPILLWAY
.1 Excavation 180 CY 50$ 9,000$
.2 Care of Water/Diversion 1 LS 25,000$ 25,000$
.3 Concrete (structural) 45 CY 1,500$ 66,750$
.4 Concrete (mass) 10 CY 500$ 5,000$
.5 Riprap 170 CY 100$ 17,000$
.3 INTAKE
.1 Excavation 60 CY 50$ 3,000$
.2 Care of Water/Diversion 1 LS 10,000$ 10,000$
.3 Trash racks 1 LS 2,500$ 2,500$
.4 Shutoff Gate w/operator 1 LS 15,000$ 15,000$
.5 Concrete (structural) 30 CY 1,500$ 45,000$
.6 Concrete (mass) 0 CY 500$ -$
.7 Misc. Metals 1 LS 10,000$ 10,000$
.8 Misc. electrical & mechanical 1 LS 50,000$ 50,000$
.4 SLUICEWAY
.1 Excavation 180 CY 50$ 9,000$
.2 Concrete (structural) 60 LS 1,500$ 90,000$
.3 Gate w/operator 1 LS 25,000$ 25,000$
.4 Misc. Metals 1 LS 5,000$ 5,000$
.5 WATER CONDUCTORS AND ACCESSORIES
.1 PENSTOCK
.a Clearing 5.9 ACRE 25,000$ 146,350$
.b 0.125 in penstock material 1800 LF 80$ 144,000$
.c 0.1875 in penstock material 2800 LF 110$ 308,000$
.d 0.25 in penstock material 2200 LF 140$ 308,000$
.e Concrete (thrust blocks and supports) 50 CY 1,500$ 75,000$
.f Exposed Penstock installation 2300 LF 100$ 230,000$
.g Buried Penstock installation 4500 LF 125$ 562,500$
.h Slope stabilization/benching 1800 LF 150$ 270,000$
.2 TAILRACE
.a Excavation 1 LS 25,000$ 25,000$
.b Support and lining 1 LS 25,000$ 25,000$
333 WATERWHEELS, TURBINES AND GENERATORS
.1 Supply 500 kW 850$ 425,000$
.2 Install 1 LS 150,000$ 150,000$
334 ACCESSORY ELECTRICAL EQUIPMENT
.1 Switchgear 1 LS 75,000$ 75,000$
.2 Station Service 1 LS 30,000$ 30,000$
.4 PLC Controls, Panel, and Generator Wiring 1 LS -$ -$
.5 Conduit/wires/cables 1 LS 25,000$ 25,000$
335 MISC. POWER PLANT EQUIPMENT
.1 Cooling Water System 1 LS 25,000$ 25,000$
.2 Powerhouse crane rail 1 LS 25,000$ 25,000$
336 ROADS, RAILROADS AND BRIDGES
.1 Upgrade Existing Road 0.9 MI 50,000$ 45,000$
.2 New Road to Intake and Powerhouse 0.4 MI 250,000$ 100,000$
.3 Clearing/Drainage/Erosion Control 1 LS 75,000$ 75,000$
350 LAND AND LAND RIGHTS
.1 Land rights - transmission line LS -$
IPEC Hoonah Hydropower
OPINION OF PROBABLE COST
Water Supply Creek - Option 2
352
STRUCTURES AND IMPROVEMENTS
(TRANSMISSION FACILITY)
.1 Substation foundations 1 LS 10,000$ 10,000$
.2 Oil spill containment 1 LS 10,000$ 10,000$
.3 Grounding grid 1 LS 15,000$ 15,000$
353 STATION EQUIPMENT
.1 Generator Step-up Transformer- 500 kVA 1 LS 30,000$ 30,000$
.2 Disconnects 3 LS 10,000$ 30,000$
.3 Surge Arrestors 3 LS 2,000$ 6,000$
356 OVERHEAD CONDUCTORS & DEVICES
.1 Overhead Transmission Line 4.50 MI 180,000$ 810,000$
.2 ROW Clearing 4.50 MI 10,000$ 45,000$
397 Communication and Control Equipment
.1 Telemetry and Communications Equipment 1.0 LS 75,000$ 75,000$
Total Direct Construction Costs 4,900,000$
Contingency 25% 1,225,000$
Design Engineering 10% 490,000$
Licensing & permitting 200,000$
Owner's General Administration & overhead 5% 245,000$
Construction Management 5% 245,000$
Subtotal 7,305,000$
Interest During Construction, 5%/18 months 5% 18 months 265,000$
Total 7,570,000$
HOONAH HYDRO PROJECT
GILKES’ BUDGET OFFER FOR HYDRO TURBINE,
GENERATOR & ASSOCIATED EQUIPMENT
REFERENCE: BMS/Hoonah Rev 0
08 January 2011
Page 2 of 5
BUDGET PROPOSAL
Quotation Ref : BMS/Hoonah
Sales Engineer : Bruce Sellars
: b.sellars@gilkes.com
: 250-483-3883
Date : 08 January 2011
Enquiry from : Leanne Greisen
: HDR
Site location : Hoonah AK
Country : United States
PROPOSAL DISCUSSION
Gilkes has put together a preliminary turbine selection and some budget prices for the potential hydro project
at Hoonah AK. The selection is based on a net head of 400 feet and a flow range of 5 to 20 cfs.
There are three possible turbine options:
- 850P316 twin jet horizontal Pelton
- 20 inch single jet horizontal Turgo
- 15 inch twin jet horizontal Turgo
Efficiency curves for the three turbines are attached. I have also included some representative drawings.
The 850P316 is very close to an 825P316 that Gilkes recently installed at Carnoch Scotland. The 15 inch
Turgo is almost identical to the Coniston project located near Kendal, and the 20 inch is similar to the Garvan
project. The Gilkes Turgo is a very simple and reliable turbine with a long history of superior service.
The recommended turbine is the 15 inch twin jet Turgo for the following reasons:
- The Turgo turbines will be lower cost than the Pelton
- Turgo turbines have good erosion resistance and offer superior performance in applications with
poor quality water. Gilkes has several Turgo units operating in Alaska.
- The twin jet Turgo has better performance at lower flows than the larger diameter single jet unit
In the attached budget prices, we have included the inlet valve, turbine, generator, imbedded parts, turbine
control panel, HPU, shipping and installation supervision. I have included the special tools for installing and
maintaining the equipment.
The price does not include any civil work, or the electrical equipment for the station service, HVAC, SCADA,
or the transformers and switchgear to interconnect with the utility. The scope of supply for this equipment
varies significantly. Gilkes works with a number of electrical engineering firms and can provide a quote for
this equipment when we get more information on the project requirements.
The pricing, terms and technical specifications are subject to the negotiation of a definitive agreement.
Please let me know if you have any questions, or need any other information.
Yours truly,
Bruce Sellars PEng
Hydro Sales Manager
Gilbert Gilkes & Gordon Ltd.
Victoria BC office
250-483-3883
Page 3 of 5
SCOPE OF SUPPLY
1 off Gilkes Turgo or Pelton Turbine
Horizontal arrangement
1 off Hydraulic pressure supply
1 off Induction generator
1 off Turbine shutoff valve
1 off Special tools required for installation and maintenance
1 off Set electrical PLC controls, panel, generator wiring
1 off Lot field services - supervision of installation / commissioning, testing and start up
PRICE
Budget prices for the equipment specified above:
850P316 $US 680,000
20HCTI_SJ $US 465,000
15HCTI_TJ $US 475,000
Price for installation supervision and commissioning is estimated to be about $50,000.
ESTIMATED DELIVERY
8 to 10 months from receipt of order
TERMS AND CONDITIONS
Payment : A payment with order (20% of total contract value) and progress
payments throughout the manufacturing period will be required.
General Terms and Conditions : Gilkes standard form L.91 copy available on request
VALIDITY
Due to the volatility in exchange rates and component prices, these are budget prices only. Firm prices will
be determined upon negotiating and executing a definitive contract.
Page 4 of 5
TECHNICAL DATA
GILKES HORIZONTAL TURBINE
Model : 850P316 20HCTI_SJ 15HCTI_TJ
Type : Pelton Turgo Turgo
No. of jets : 2 1 2
Mean diameter of runner : 850 510 380 mm (nominal)
Rated speed (60Hz) : 514 900 1200 rpm
Turbine design rating (at 20 cfs) : 602 570 574 kW
Turbine efficiency at 20 cfs : 88.9 84.2 84.8 %
Runner material : Stainless steel
Rated net head : 400 feet
Rated flow : 18 cfs
INDUCTION GENERATOR SPECIFICATION
Rated output : 600 kW
Voltage : 480 volts
Frequency : 60 Hz
Expected efficiency : 95% or better @ full load
Insulation - Stator : Class 'F'
Rotor : Class 'F'
Stator temperature rise : Class B' (80 deg. C with 40 deg C ambient)
Exciter insulation : Class 'F'
Mounting details : Foot mounted
Enclosure standard : IP23
Bearing type : rolling element
Ambient temperature range : 0-40 deg C
Altitude : 1000 m.a.s.l. (maximum)
Voltage adjustment : Motorised
Stator temperature sensors : Yes
Bearing temperature indicators : Yes
TYPICAL TURBINE INLET VALVE SPECIFICATION
Type : Butterfly type
Size : 450 mm / 18 inch nominal
Design : Resilient sealing design
Flanges : BS 4504 or US equivalent
Standard : Generally in accordance with BS 5155
Body : Ductile iron
Body seat : Stainless steel or elastomer
Disc : Ductile iron
Disc seal : Nitrile rubber
Shafts : Stainless steel
Bushes : Self lubricating type
Valve operator : Closure by gravity counterweight with oil hydraulic check
Opening by oil hydraulic cylinder
Page 5 of 5
TYPICAL OIL HYDRAULIC PRESSURE SYSTEM SPECIFICATION
Free standing sump tank
Electric motor driven gear pump
Pressure relief valve and gauge
Filler, strainer, breather level gauge and thermometer
Flow/level indicating switches with alarm and trip contacts
Differential unloader valve
Bladder type accumulator system for auto shutdown on loss of AC supply
10 micron filtering system
Electro hydraulic servo valve module
For Main Inlet Valve - electro hydraulic solenoid valve
TYPICAL ELECTRICAL CONTROL SPECIFICATION
Typical Panel Mounted Equipment
Electrical control, monitoring, protection and metering equipment
PLC system for remote control, monitoring communications network by telemetry
Scope of supply does not include station service, transformers or switchgear to interconnect with the utility.
850 P316_SJ
Speed 514 Rpm
07/01/11 Version Number 10
Pelton
Hoonah AKGilbert Gilkes and Gordon Ltd
Kendal, Cumbria, UK. LA9 7BZ
Tel: 01539 720028 Fax: 01539 732110
Approved
0 5 10 15 20 25 30
Flow rate in ft^3/sec
0
200
400
600
800
1000
Power in kW0
20
40
60
80
100
Efficiency in percent0
100
200
300
400
500
Head in feet80
7060
89
85
75
6555
89
80
7060
85
75
6555
Name
New Duty
1 Jet
Head
feet
400.0
400.0
Flow rate
ft^3/sec
18
9
Power
kW
543
270
Efficiency
percent
89.1
88.7
No.of Jets
Hz
2.00
1.00
20. HCTI_SJ
Speed 900 Rpm
07/01/11 Version Number 9
High Capacity Turgo
HoonahGilbert Gilkes and Gordon Ltd
Kendal, Cumbria, UK. LA9 7BZ
Tel: 01539 720028 Fax: 01539 732110
Approved
0 5 10 15 20 25 30 35
Flow rate in ft^3/sec
0
200
400
600
800
1000
Power in kW0
20
40
60
80
100
Efficiency in percent0
100
200
300
400
500
Head in feet84
80
70
6050
84
75
6555
Name
New Duty
Head
feet
400.0
Flow rate
ft^3/sec
18
Power
kW
514
Efficiency
percent
84.4
No.of Jets
Hz
1.00
15. HCTI_TJ
Speed 1200 Rpm
08/01/11 Version Number 9
High Capacity Turgo
HoonahGilbert Gilkes and Gordon Ltd
Kendal, Cumbria, UK. LA9 7BZ
Tel: 01539 720028 Fax: 01539 732110
Approved
0 5 10 15 20 25 30 35
Flow rate in ft^3/sec
0
200
400
600
800
1000
Power in kW0
20
40
60
80
100
Efficiency in percent0
100
200
300
400
500
Head in feet84
80
70
6050
84
75
6555
84
80
70
6050
84
75
6555
Name
New Duty
1 Jet
Head
feet
400.0
400.0
Flow rate
ft^3/sec
18
9
Power
kW
517
258
Efficiency
percent
84.9
84.5
No.of Jets
Hz
2.00
1.00
GILKES 825MM TWIN JET PELTON TURBINES
GILKES 625MM TWIN JET PELTON TURBINES
Coniston 15 inch twin jet Turgo; 292 kW
Northwest Pipe Company Email
12005 N. Burgard, Portland, OR 97203 1 Page
Phone: (503) 407-3389
Fax: (503) 285-2913
To:Leanne Greisen @ HDR Date:14-Jan-11
Phone:425.369.2742 Project:SE Alaska Hydro Project
Email:leanne.greisen@hdrinc.com
Budgetary Quotation
We are pleased to offer prices for steel pipe for the above noted project for materials as listed below.The estimating
prices are provided for reference only and Northwest Pipe shall not be bound by pricing or any other provisions herein.
Final pricing and delivery can be provided once project requirements are finalized.
SPECIFICATIONS:
Pipe:Manufactured per AWWA C200 from steel conforming to ASTM A1018 gr. 42 or better
Length:Standard length to be 40 ft.
Joints:Weld Bell for lap-joint field welding
Coating:Polyurethane coated per AWWA C222 applied 25 mil dft.
Lining:Polyurethane lined per AWWA C222 applied 20 mil dft.
Freight:Prices are FOB our plant with full freight allowed to Seattle, WA dockside.
All unloading shall be done by the buyer.
PRICING VALID FOR 30 DAYS
WELDED STEEL PIPE - Spiral weld DSAW
Qty. O.D. Wall Yield Working Weight Unit Price Extension
Item (lf)(in)(in.)(psi)Pres.(psi)lbs /lf $/lf Total $
1 1,700 20 0.134 42,000 281.4 29 $85.00 $144,500.00
Further Information:
NORTHWEST PIPE COMPANY
Scott Copeland
Product Sales Manager
Mill test reports shall be provided. Delivery can begin approximately 12 to 14 weeks after receipt of
order for straight pipe sections. Engineered pipeline will required approximately 14 to 16 weeks
after receipt of approved drawings. Drawing submittal shall be 3 to 4 weeks after receipt of order
subject to receipt of data to generate final drawings. All delivery schedules are subject to mill and
steel availability at time of order. Terms of sale are net 30 days after date of invoice. If you have
any questions, or need additional information, please contact me at the phone number listed above.