Loading...
HomeMy WebLinkAboutLoud Creek Hydro Conceptual Design and Feasibility Report - July 2011 - REF Grant 2195472LOUDCREEKHYDROPOWERDEVELOPMENT CONCEPTUAL DESIGN AND FEASIBILITY REPORT Prepared For: City of Akutan Prepared By: EES CONSUL TING, INC. MCMILLEN, LLC DRYDEN & LARUE/EPS July 29, 2011 TAB L E OF CONTENTS Executive Summary ........................................................................................................ 1 Task Description ............................................................................................................. 3 Technical Feasibility ........................................................................................................ 4 Previous Studies .......................................................................................................... 4 Land Ownership ........................................................................................................... 4 Site Visit ....................................................................................................................... 4 Watershed Description ................................................................................................ 8 Anadromous Fish Presence ........................................................................................ 8 Geology ....................................................................................................................... 9 Project Arrangement .................................................................................................. 1 O Base Case ............................................................................................................. 1 O Alternat ive 1 ........................................................................................................... 1 O Power Transmission Options ................................................................................. 1 O Hydrology and Hydraulics ............................................................................................. 11 Hydrology .................................................................................................................. 11 Background ............................................................................................................ 11 Peak Stream Flow .................................................................................................. 12 Hydraulics .................................................................................................................. 16 Flood Routing ......................................................................................................... 16 Spillway and Flood Outlet Section and Design ...................................................... 17 Free board .............................................................................................................. 17 Dam Embankment ................................................................................................. 17 Conceptual Design ........................................................................................................ 18 Diversion Dams ......................................................................................................... 18 Base Case ............................................................................................................. 18 Alternative 1 ........................................................................................................... 19 Dock .......................................................................................................................... 19 Access Roads ............................................................................................................ 20 Powerhouse ............................................................................................................... 20 Substation .................................................................................................................. 20 Power Transmission and Interconnection .................................................................. 20 Energy Production ......................................................................................................... 23 Base Case ................................................................................................................. 23 Alternative 1 ............................................................................................................... 25 Permitting ...................................................................................................................... 26 Federal Energy Regulatory Commission ................................................................... 26 United States Army Corps of Engineers .................................................................... 27 Alaska Department of Natural Resources .................................................................. 28 Dam Safety Program .............................................................................................. 28 Water Rights .......................................................................................................... 28 Alaska State Historic Preservation Office .................................................................. 28 Alaska Coastal Zone Management Review (Coastal Project Questionnaire) ............ 29 Alaska Department of Environmental Conservation .................................................. 29 Alaska Department of Fish and Game ....................................................................... 29 Loud Creek Hydropower Developm ent C on c eptual Design and Feasibility Report Pag e ii Local Government ..................................................................................................... 29 Cost Estimates .............................................................................................................. 30 Base Case ............................................................................................................. 30 Alternative 1 ........................................................................................................... 30 Transmission and Substation Costs ....................................................................... 31 Basis of Transmission Cost Estimates ................................................................... 32 Diesel Generator Set .............................................................................................. 32 Evaluation .............................................................................................................. 32 Summary of Construction and Development Costs ................................................... 33 Cost of Power ................................................................................................................ 35 Project Schedule ........................................................................................................... 38 Conclusions and Final Recommendations .................................................................... 39 Conclusions ........................................................................................................... 39 Recommendations ................................................................................................. 39 References .................................................................................................................... 42 LIST OF FIGURES Figure 1. Loud Creek Drainage Basin ............................................................................. 5 Figure 2 . East Fork Loud Creek Proposed Dam Site ...................................................... 6 Figure 3 . West Fork Loud Creek Diversion Site .............................................................. 6 Figure 4. Powerhouse Site .............................................................................................. 7 Figure 5 . Typical Shoreline around Akutan Harbor ......................................................... 8 Figure 6. USGS Geology Map of Akutan Island , Alaska ................................................. 9 Figure 7. Loud Creek Stream Gage .............................................................................. 12 Figure 8 . Russell Creek USGS Gage 15297610 ........................................................... 13 Figure 9 . Russell Creek near Cold Bay, Alaska ............................................................ 13 Figure 10. Russell Creek near Cold Bay, Alaska .......................................................... 14 Figure 11 . Loud Creek Calculated Flows ...................................................................... 24 LIST OF TABLES Table 1 Russell Creek Near Cold Bay, Alaska Peak Streamflow Statistics ................... 14 Table 2 Loud Creek Drainage Basin Area ..................................................................... 15 Table 3 East Fork Loud Creek Peak Stream Flow Statistics ......................................... 16 Table 4 Base Case Energy Production ......................................................................... 25 Table 5 Power Transmission and Substation Costs ...................................................... 31 Table 6 Project Costs .................................................................................................... 34 Table 7 Cost of Power ................................................................................................... 36 Table 8 Summary of Potential Generation Source Costs at Akutan, Alaska ................. 36 Table 9 Anticipated Power Consumption ...................................................................... 37 Table 10 Proposed Tasking Cost Estimates ................................................................ .41 Loud Creek Hydropower Development Conceptual Design and Feasibility Report Page iii Append ix A -Drawings Appendix B -Cost Estimates Appendix C -Schedule APPENDICES Appendix D -Harbor Power Consumption Estimates Appendix E -Project Monthly Energy Generation Table Appendix F -Cost of Energy Calculations LIST OF DRAWINGS Drawing 1 -Location Map , Vicinity Map, and Drawing Index Drawing 2 -Standard Abbreviations and Symbols Drawing 3 -General Site Plan Drawing 4 -Design Criteria Drawing 5 -Site Plan -Base Case Drawing 6 -Site Plan -Alternative 1 Drawing 7 -Typical Dam Plan and Sections Drawing 8 -Dam Penstock Section Drawing 9 -Roadway Details Drawing 10 -Pipeline Plan, Profile, and Details -Base Case Drawing 11 -Pipeline Plan, Profile , and Details -Alternative 1 Drawing 12 -Powerhouse Foundation Plan and Sections Drawing 13 -Powerhouse Generator Plan and Sections Drawing 14 -Transmission Lines Route Options Loud Creek Hydropower Development Conceptual Design and Feasibility Report Page iv Executive Summary A feasibility and analysis was completed for the Loud Creek Hydropower project to determine the technical feasibility of producing power at Loud Creek and delivery of the power to the City of Akutan (City). The 1990 HOR/Ott report indicated the Loud Creek project was technically constructable using a cross bay transmission cable. The report also concluded that the "economic viability of the project will like ly improve over time , as the City 's demand for energy increases." The current study was initiated because the City's power demand has increased since the 1990 study. The power demand is expected to further increase with the development of the new Akutan Harbor (Harbor) and other expansion activities . Early in the current study efforts , the City determined that the cross bay transmission cable presents an extremely high risk of failure requiring additional study efforts for a transmission line routing. A total of 6 transmission routing options were evaluated . Conceptual power generation arrangements were developed for the Loud Creek hydropower development. The Base Case alternative consisted of a single diversion dam located on the East Fork of the Loud Creek . Alternative 1 included a second diversion dam on the West Fork of Loud Creek increasing the overall design flow and annual power production . The Loud Creek power could be delivered at or below the current cost of power using diesel generation . The Loud Creek power cost would be significantly higher than Trident Seafoods' (Trident) existing self generation cost. It is likely that Trident would generate their own power rather than buy more expensive power from the Loud Creek project. Without the sale of power to Trident and/or the new Harbor, power delivered from Loud Creek to the City would exceed demand for the foreseeable future , particularly if the Town Creek hydropower system becomes fully operational. The combination of Alternative 1, power generation, and Option 4a, transmission, was the recommended alternative. The power generation facilities consist of new diversion dams on the East and West Forks of Loud Creek, a new 18 inch diameter penstock delivering up to 15 cubic feet per second ( cfs) to a new powerhouse near the mouth of Loud Creek, a dock, and a primitive access road from the dock to the diversion dam . The powerhouse is a single 350 kilowatt (kW) Pelton Wheel turbine capable of generating up to 1,548, 100 kilowatt hours (kWh) annually. The power will be delivered from the Loud Creek powerhouse to the new Harbor facilities via a buried submarine cable located in the intertidal zone. The estimated total project cost is $7,727,400 with a cost of power of $0.43/KWh . The recommended alternative is considered a "standalone" arrangement delivering power to only the new Harbor. Loud Creek Hydropower Development Conceptual Design and Feasibility Report Page 1 Based on the results of the feasibility study, it is recommended that the conceptual business and operations plan requi red under AEA Phase II milestones should be completed along with a business case analysis that addresses the cost of diesel, power purchase agreements , projected revenues , and the non-monetary benefits of the project. A project schedule was developed , which indicates that operation could be achieved within approximately 3 years from initiation of the final engineering design effort. The permitting process would be the critical path schedule item . A key issue for the project is obtaining permits to allow construction to start in the summer of 2013 . It is believed that the Federal Energy Regulatory Commission (FERC) would issue an order declaring that it does not have jurisdiction. This would mean that the permits required for construction would be from the State and other federal entities . Note that water rights for the project need to be procured immediately to preserve the schedule. Loud Cree k Hydropower Development Conceptual Design and Feasibility Report Page 2 Task Description EES Consulting, Inc (EES) and McMillen , LLC (McMillen) were retained by the City to conduct a preliminary feasibility assessment on the Loud Creek Hydropower Development to determine the preferred hydroelectric system configuration and transmission routing. This assessment included the recommended sizing of a hydroelectric system, including projected annual energy generation and fuel displacement for the project. Other elements of the assessment discussed in this report include : a . Technical feasibility of the project. b . Conceptual design of the project, to include location of system components , penstock and transmission alignments , and sizing/type of piping , turbines , generators, and all necessary components related to system construction . c . Conceptual design summary including recommended construction methods , construction access, and design practices. d. Power systems integration including turbines , generators , switchgears, controls, and transmission lines . e. Issues related to permitting and permit processing . f . All other information , conclusions and recommendations relative to the design , construction , operation and maintenance of the selected system configuration. Loud Creek Hydropower Development Conceptual Design and Feasibility Report Page 3 Technical Feasibility Previous Studies In June 1990, HOR/OTT Engineering and Dryden & LaRue (HOR/OTT) published a hydroelectric feasibility study report for both the Loud Creek and North Creek projects. The Loud Creek Project was examined in detail and was deemed technically constructible. However, it was not deemed financially economic for the City to construct alone at that time. The report concluded that the economic viability of the project would likely improve over time as the City's demand for energy increases. It was also noted in the report that the project may become economically feasible if Trident (located in Akutan) purchased excess power or became a co-developer of the project. The 1990 report proposed a configuration that would include two diversions on Loud Creek. The main diversion would be at elevation (El.) 560 feet (ft) above mean sea level (amsl) on the East Fork of Loud Creek (East Fork) and a secondary diversion would be located on the West Fork of Loud Creek (West Fork) at El. 175 ft amsl. Figure 1 depicts the locations of the East and West Fork drainage basins. With this configuration, there would be two penstocks that each feed into a separate turbine- generator set. The main turbine-generator set would have a rating of 330 kilowatts (kW) and the secondary would have a rating of 60 kW. Both of the turbine-generator sets would be housed in a small powerhouse to be constructed above maximum tidewater on the rock bluff. A 4,500-foot long underwater transmission cable was planned from the powerhouse to the City along with a buried intertie cable that would lead to the Trident Seafood facility. The 1990 report estimated the cost for the Loud Creek Hydropower Development at $1.7 million dollars. Land Ownership The Loud Creek drainage is owned by the City as acquired under 14(c)3 of the Alaska Native Claims Settlement Act. The Akutan Native Corporation owns the land from Loud Creek to the Trident facility and Harbor. The tidelands from Loud Creek to the Trident facility are owned by the State of Alaska . From the Trident facility to Akutan, the land is owned by Trident and the City. Site Visit The Loud Creek drainage basin is located directly across the bay from the City (Figure 1 ). EES and McMillen conducted a site visit to the Loud Creek drainage basin on October 25, 2009. At the time of the site visit, there was snowpack in the upper altitudes of the basin. Loud Creek Hydropower Development Conceptual Design and Feasibility Report Page 4 The team was able to identify the HOR/OTT proposed site of the dam on the East Fork at approximately El. 500 ft amsl (Figure 2). The 1990 West Fork diversion dam site was examined but was deemed not a preferred location for a diversion dam . A more suitable diversion dam lo cation was observed during the site visit at approximately El. 500 ft amsl. A photograph of this location is presented in Figure 3 . The penstock routes from both diversion dams down to the powerhouse site appear to be relatively straightforward to construct. The powerhouse site would be located near the mouth of the creek, well above high tide on a rock bluff as illustrated in Figure 4. Ak arbor East Fork Loud Ck Figure 1. Loud Creek Drainage Basin Loud Creek Hydropower Developm ent Conce ptual De sign and Feasi bility Report Page 5 Figure 2 . East Fork Loud Creek Proposed Dam Site Figure 3. West Fork Loud Creek Diversion Site Loud Creek Hydropower Development Conceptual Design and Feasibility Report Page 6 Figure 4. Powerhouse Site The team toured the bay investigating an underwater cable route along the shoreline . The shoreline underwater cable route was investigated because concern had been expressed about an underwater cable running straight across the bay to the City and the potential for boats anchoring within the bay snagging the cable. Figure 5 presents a typical photograph of the shoreline. Loud Creek Hydropower Development Con ceptual Design and Feasibility Report Page 7 Figure 5. Typical Shoreline around Akutan Harbor Watershed Description The Loud Creek watershed (drainage basin) totals approximately 1.0 square mile (sq mi) and is comprised of an East and West Fork . The East Fork drainage basin above El. 500 ft asml (above proposed diversion dam) is approximately 0 .59 sq mi, while the West Fork basin above El. 500 ft (above proposed diversion dam) is approximately 0.19 sq mi in size. The drainage basin below the El. 500 ft asml diversion dams is 0 .22 sq mi. The Loud Creek basin varies from El. 0 ft amsl at the outlet to approximately El. 1,800 ft amsl at the top of the East Fork drainage basin. The drainage basin slopes range from approximately 10% (near stream) to approximately 70% (mountain slopes). The watershed land cover is characterized by native tundra vegetation and exposed rock outcroppings, with no forested, developed, or glaciated areas in the watershed . Anadromous Fish Presence Based on observations made during the October 2009 site visit, anadromous fish were not observed in Loud Creek . Furthermore , the Alaska Department of Fish and Game has not identified Loud Creek as an anadromous stream. However, not all the streams in the Akutan region have been mapped , and subsequently, the absence of information in the fish catalog does not necessarily indicate that anadromous species are not present. It is likely that the regulatory agencies will require fish studies to confirm the lack of anadromous fish within the Loud Creek drainage. Loud Creek Hydropower Development Conceptual Design and Feasibility Report Page8 Geology The United States Department of Agriculture (USDA) has not completed a Soil Survey for the Loud Creek drainage basin . The geologic soils located within the Loud Creek project boundaries as mapped by the Un ited States Geological Survey (USGS) are shown in the highlighted area of Figure 6. Geologic soils include colluviums (Qcu), tephra (Qtu), and volcanic rock (QTv). Colluvium is a loose deposit of rock debris accumulated through the action of rainwash or gravity and is located toward the base of the Loud Creek drainage slope. Tephra soils include volcanic deposits of shattered rock fragments, ranging in size from fine dust and ash to particles greater than 32 mm in diameter. Volcanic rock is extrusive igneous rock solidified near or on the soil surface. These soils are similar to those found at the Town Creek dam site which has experienced seepage through the foundation and abutment interface . Careful consideration of these soils and possible transverse faults through the site will have to be considered as part of a geotechnical investigation required for the dam site as part of the final design effort. • Volcan ic Rocks, Undifferenti ated D Collu vi um , Und ifferen tiated D T e phra Figure 6. USGS Geology Map of Akutan Island, Alaska Loud Creek Hydropower Development Conceptual Design and Feasibility Report Page 9 Project Arrangement The 1990 HOR/OTT report recommended a project arrangement that included two diversions and two turbine-generator sets . In this arrangement, the West Fork would consist of a small diversion (at El. 175 ft amsl) and separate penstock leading to the powerhouse with a small unit rated at 60 kW . The main diversion would be located on the East Fork (at El. 560 ft amsl) with a penstock leading down to the powerhouse fitted with a 300 kW impulse turbine set. This arrangement requires more switchgear and complex controls for reliable operation . Additionally, this arrangement would be more expensive to construct, operate, and maintain than a project with a single turbine- generator set. In our opinion, this type of arrangement is not cost effective as it significantly increases the cost of the project for a very small incremental gain in power production . EES and McMillen identified two potential alternatives for the construction of a hydropower facility on Loud Creek. These alternat ives are based on the 1990 HOR/OTT report and the 2009 site visit and are briefly described below . A more detailed description of each hydropower alternative along with potential power transmission options are presented in the Conceptual Design section of this report. Base Case EES and McMillen first developed a simple project arrangement (herein referred to as the Base Case) with a single diversion dam on the East Fork and a pen stock with an inner diameter (ID) of 16 inches (in) extending approximately one mile to a small powerhouse located just above the outlet of Loud Creek. Alternative 1 Alternative 1 consists of the Base Case scenario and a dam on the West Fork. A diversion dam would also be constructed on the West Fork at approximately El. 500 ft amsl. The cost to construct a diversion structure and penstock (16 in) to intersect with the East Fork penstock will be considered in addition to the dam and penstock from the East Fork . The combined penstock inside diameter would shift to 18 in after the intersection . This alternative would allow for more water to be captured from the basin and still allow for a single turbine-generator set at the powerhouse . Power Transmission Options The hydropower arrangement alternatives, Base Case and Alternative 1, were coupled with a range of power transmission options . These options were developed to determine the optimum routing and cost associated with delivering the power generated at the Loud Creek plant to the potential users . The identified options include both submarine and land based routes to the City and new Harbor facilities. Loud Creek Hydropower Development Conceptual Design and Feasibility Report Page 10 Hydrology and Hyd raulics Hydrology Background In 1986, the Alaska Power Authority contracted with the Water Resources Section of the Alaska Division of Geological and Geophysical Surveys (DGGS) to collect and summarize stream flow for both North Creek and Loud Creek. Data was only collected from June 1986 to October 1988. The 1990 HOR/Ott report reviewed the DGGS data and noted the follow ing: • Loud Creek had a gage installed at the mouth and developed a record from June 3, 1986 through August 14 , 1987 . • A gage was added to record stream flows in the East Fork for the periods of September 11, 1986 to November 27, 1986; February 24, 1987 to August 14, 1987 ; and September 10, 1987 to July 30, 1988. • The East Fork data was deemed unreliable because it did not achieve a run-off ratio (cubic feet per second [cfs] per square mile) similar to either Loud Creek (at the mouth) or North Creek . • Peak flows occur from June through August and in December and January. Low flows occur from February through Apri l. It was not known what proportion of the winter flow may originate from the upper versus the lower portion of the bas in . As a part of the current effort, additional stream flow data is being obtained for Loud Creek at the mouth to help verify the character istics of the drainage basin . A gaging station was installed on February 18, 2010 and is being maintained on Loud Creek to determine hydrologic flows (see Figure 7). Typically, data collected over a long period of time (10 years) is required to properly characterize stream flows from a given drainage basin . Due to time constraints, one year of stream flow data collection will be sufficient for the hydrology analysis of this project. Data collected from this stream gage will be used during subsequent design phases of the project. This data will be collected in June 2011 , compiled , and submitted under a separate cover. Data collection will continue for a complete year to determine daily and monthly flows . No other gaged streams of a comparab le size in the Aleutian Islands have been located . The data from Loud Creek will be used to develop a correlation with ot her gaged streams to better understand the stream flow characteristics . Lo ud Creek Hydropower Develop me nt Conceptual Design and Feasibility Report Pag e 11 Figure 7. Loud Creek Stream Gage Peak Stream Flow For purposes of designing a small dam, long-term average daily stream flows are needed to determine the peak flow characteristics of the basin . In addition, basin characteristics such as soil type, basin slope, and representative channel shape are needed for the development of an inflow hydrograph. Since this data has not been collected for Loud Creek, the design analysis will focus on determining the peak stream flow statistics based on regional regression equations. The results will be compared to a local reference site for suitability . The USGS maintains gage sites at a number of streams in Alaska and the data is available on their web site. The Russell Creek gage (30 .9 square mile drainage area) near Cold Bay, Alaska is in a very similar climate as Loud Creek and is the closest available stream gage station to Loud Creek providing reliable data. Cold Bay is about 150 miles east of Akutan in the Aleutians East Borough. Figure 8 illustrates the long- term record for flows in Russell Creek near Cold Bay, Alaska . This gage record exists in two continuous parts ; from October 1981 to October 1986 and from October 1995 to October 2009 . Loud Creek Hydropower Development Conceptual Design and Feasibility Report Page 12 llUSGS USGS 15297610 RUSSELL C NR COLD BAY AK 5000 .---------------------------. "g 4000 8 3000 " " 2000 (,. " 0.. ~ 1000 .!! CJ ·~ J:I ~ CJ 40 ---------------------------------------~ 1982 1985 1988 1991 1994 1997 2000 2003 2006 2009 ~ Daily ftean discharge ---Period of approved data • Flow at station affected by ice ---Pe r iod of provisional data Figure 8. Russell Creek USGS Gage 15297610 Figure 9. Russell Creek near Cold Bay, Alaska (looking downstream from gage station) Loud Creek Hydropower Development Conceptual Design and Feasibility Report Page 13 Figure 10. Russell Creek near Cold Bay, Alaska (looking upstream from gage station) The peak stream flow record for the Russell Creek gage was analyzed using the USGS PKFQWin software program (http ://water.usgs .gov/software/PeakFQ/). The software determines peak stream flow statistics based on Bulletin 178 guidelines . Table 1 summarizes the peak stream flow results . Table 1 Russell Creek Near Cold Bay, Alaska Peak Streamflow Statistics AnnualExceedance Recurrence Bulletin 178 95-Percent Unit Probability Interval Estimate Confidence Limits Discharge (Years) (cfs) Lower Upper (cfs/sq mi) 50% 2 2,601 2,217 3,033 84 20% 5 3,723 3,183 4,585 120 10% 10 4,600 3,849 5 ,944 149 4% 25 5,876 4,741 8 ,261 190 2% 50 6,956 5,452 10 ,350 225 1% 100 8,156 6,210 12,8 10 264 0.5% 200 9,493 7,023 15,730 307 0.2% 500 11,500 8,196 20,410 372 The unit discharge for the 50% and 1 % exceedance probabil iti es are 84 cfs and 264 cfs per square mile , respectively. Peak stream flow statistics for the ungaged Loud Creek basin are calculated below using the regression equations developed by the USGS. Regression equations were Loud Creek Hydropower Development Conceptual Design and Feasibility Report Page 14 developed for s even separate regions statewide. The Loud Creek drainage basin is in Region 1 , where the peak stream flow statistics are calculated based on the equations listed below. 2-YR: 5-YR: 10-YR: 25-YR: 50-YR: 100-YR: 200-YR: 500-YR: where : a2 = o.004119 Ao .8361 (ST +1ro.359o p o.9 11 0 (J+32 )1.635 O s = o.009024 A o.8322 (ST +1 r o.3670 p 0.8128 (J+32 )1.64o 0 10 = 0 .01 450 A o.83 o6 (ST+1ro.3691 p o.7655 (J+32 )1 .622 0 25 = 0.02522 A o.8292 (ST+1ro.3697 p o.116s (J+32 )1 .588 0 50 = 0 .037 1 1 Ao .8286 (ST +1 r o.36 93 p o.6847 (J+32 )1 .559 O mo= 0 .0 5 354 A o.8281 (ST +1 ro.368 3 p o.6556 (J+32 )1 .s21 0 200 = 0.07 5 58 A o.8276 (ST +1 yo.3669 p o.62 84 (J+32 )1.4 95 O so o = 0 .1209 A o.8212 (ST +1 r 6.3646 p o.5948 (J+32 )1.449 A = Drainage Area (sq mi) ST = Storage Area (%) P =Mean Annual Precipitation (inches) J =Mean Minimum January Temperature (deg F) Using the USGS Unimak (A-6) quadrangle geo-referenced map, the drainage areas of the Loud Cree k basin were calculated and are shown in Table 2. These areas are comparable to the estimates in the 1990 HOR/OTT report. The Unimak quadrangle contour interval is 100 ft. The accuracy of the watershed delineation is based upon the accuracy of the available data . Table 2 Loud Creek Drainage Basin Area Basin Area (sq mi) East Fork Above 500 ' 0 .59 West Fork Above 500' 0 .19 Loud Creek below 500 ' 0.22 Entire Basin 1.00 Mean annual precipitation was found to be 50 in from GIS data. For temperature determinations, Dutch Harbor (http ://www.wrcc.dri.edu/cgi-bin/cliMAIN .pl?ak2587 ) and Cape Sarichef (http://www.wrcc .dri.edu/cgi-bin/cliMAIN .pl?ak1325) climate data was used. The mean minimum January temperature was determined to be 28 degrees Fahrenheit. Since there are no ponds or lakes in the drainage basin , the storage area was determined to be 0%. Loud Creek Hydropower D evelopment Conceptual Design and Feasibility Report Page 15 Table 3 summarizes the peak stream flow statistics calculated for the East Fork basin . AnnualExceedance Recurrence Interval Regression Equation Unit Discharge Probabilit Years Estimate cfs cf sis mi 50 % 2 77 128 20 % 5 117 195 10% 10 145 242 4 % 25 181 302 2% 50 209 349 1% 100 237 395 0.5% 200 267 445 0.2 % 500 306 510 The Loud Creek basin produces a higher unit discharge than the Russell Creek basin . Unit discharge values are within error tolerances for flows less than the 4% (25-YR) exceedance probability. The predicted unit discharges for the 50% and 1 % exceedance probabilities calculated using the regional equations are 128 cfs and 395 cfs per square m ile, respectively, and are considerably larger than the unit discharges calculated from the Russell Creek gage data . S ince the unit discharge is greater in the East Fork basin, using the computed value will provide a more conservative approach when designing components of the dam. Therefore, the regression equation estimates shall be used when utilizing hydraulic and/or hydrologic inputs. Hydraulics Based on the limited dam heights and small reservoirs and the fact that there is no downstream life or property in peril by these dams, the Loud Creek diversion dams would not be expected to be regu lated by the State of Alaska Dam Safety Program (AS 4617 .900(3)). For purposes of this study , the 2004 Federal Emergency Management Agency (FEMA) Federal Guidelines for Dam Safety were used to evaluate the proposed Loud Creek dams . As outlined by FEMA, low hazard dams whose failure results in limited or no loss of benefits or loss of life during the project life can be hydraulically designed with an average return probability of 1% (100-YR). Since the Loud Creek site meets these requirements, the dam and associated structure will be designed using the probable maximum discharge of approximately 240 cfs for the 1 % exceedance event. Flood Routing The Loud Creek Dam will not operate for flood storage or a reduction of the inflow hydrograph and, therefore , will be considered a run-of-river dam for routing . Since the reservoi r offers minimal storage capacity, it is assumed that the hydrograph will not be attenuated while traveling through the reservoir. Loud Creek Hydropower Development Con ceptual Design and Feasibility Report Page 16 Spillway and Flood Outlet Section and Design The divers ion dams are designed with three hydraulic structures : (1) penstock intake , (2) outlet structure, and (3) spillway. The penstock intake is normally located on the dam abutment and consists of a headwall fitted with a trashrack and isolation gate or valve . The penstock exits the intake structure low in the water column to provide sufficient operating head on the penstock pipe . The isolation gate is either fully open or closed since the hydraulic control is maintained at the powerhouse . . For small earthfill dams, the outlet structure normally consists of a drop inlet riser structure .. As the inflow to the reservoir increases beyond the turbine design flow, excess flow will spill over the riser and be conveyed to the dam tailrace via an outlet pipe. A 50% recurrence probability flow (2-yr) is a typical design flow event selected for an outlet structure, though larger flow events can be selected . A spillway normally consists of a rock armored or concrete lined open channel designed with a simple overflow inlet. The FEMA guidelines for low hazard dams requires a minimum spillway design recurrence probability flow of 50% (100-yr). The flow split between the outlet structure and spillway as well as the design recurrence intervals will be evaluated and finalized as part of the final design work effort. For purposes of this study, the 50% (2-yr) and 1 % (100-yr) recurrence intervals were assumed for the outlet structure and spillways, respectively. These conceptual design parameters were used to determine approximate structure sizes for developing preliminary cost estimates. Freeboard For the conceptual design study, it was assumed that the 1 % return frequency flow passes through the outlet structure and spillway while maintaining 2 ft of freeboa rd over the dam crest elevation . Dam Embankment A geotechnical study will be required to determine the suitability of the native soil material for design purposes . The conceptual design of the dam embankment assumed 3H:1V slopes on the upstream and downstream faces (Appendix A-Drawings 7 and 8). These values were used to determine quantities for cost estimating purposes. A detailed geotechnical study will be required to determine the subsurface conditions, embankment design parameters, and seepage control mechanisms. Particular attention will be required to the interface between the embankment dam and foundation where specific design details will be required to control seepage . Loud Creek Hydropower Development Conceptual Design and Feasibility Report Page 17 Conceptual Design Two basic alternatives were developed for a hydropower facil ity on Loud Creek: • Base Case consisting of a single diversion dam located on the East Fork , a penstock from the dam to the powerhouse, and a new powerhouse located just upstream from the Loud Creek outlet. • Alternative 1 which includes the facilities described for the Base Case plus a diversion dam on the West Fork of Loud Creek . A second penstock will convey water from the West Fork to a connection point with the East Fork penstock . The Base Case was developed to represent the simplest approach to generating power with a single diversion dam, penstock, and powerhouse . Alternat ive 1 de livers more wate r to the powe rhouse increasing the overall power generation capacity. Conceptual layouts for these alternatives are presented in Drawings 1 through 14. These drawings were used to develop conceptual level quantity takeoffs to support preparation of cost estimates. For both of these alternatives , a range of transmission options were considered to convey the power generated from the powerhouse to the power demand at the City of Akutan and the Harbor. In general , the transmission options would be identical for each power generation alternative . A brief discussion of the Base Case and Alternative 1 generation alternatives as well as the options for transmission is presented in the following paragraphs . Diversion Dams Base Case For the Base Case , a small diversion dam at around El. 500 ft amsl would be constructed on the East Fork (Drawing 5). The dam would be approximately 1 O ft tall in height and constructed of locally processed soi ls , a penstock intake , outlet structure, spillway, and a form of seepage cutoff wall. The seepage control system would require careful cons ideration to minimize seepage through the dam abutments and foundation . A deta iled geotechnical site investigation would be required to support the dam des ign work effort.(Drawing 7). The penstock intake structure would include a trashrack , which can be hand cleaned and provis ions for slu icing accumulated sediment from the impoundment (Drawings 8 through 10). The intake structure will feed into a penstock pipe with a buried shutoff valve, a sluice valve downstream of the dam and a shutoff va lve near the powerhouse. The penstock is designed to convey 9 cfs from the East Fork of Loud Creek to the powerhouse . A 16 in d iameter penstock provides a maximum Loud Creek Hydropower Development C o nceptual Design and Feasibility Report Page 18 flow velocity of 6.5 fps. The outlet structure was assumed to consist of a drop inlet riser and the spillway rock riprap protected open channel. As discussed previously, these dam hydraulic structures are consistent with a typical small dam design approach. The diversion dam will create a reservoir with up to 10 acre-feet of storage . The storage in this reservoir will allow the turbine generator to provide power for approximately 15 to 20 hours depending on the inflow rate and, as such, is not a significant amount of storage. This generation period was determined assuming an average flow rate of 9 cfs to the powerhouse. The time required to fill will depend on the inflow to the reservoir. Gage data is being collected to provide a better indication of the total flow expected from the Loud Creek basin. An estimate of the flow from the east drainage basin will be developed to determine the minimum inflow to the East Fork reservoir. Alternative 1 For Alternative 1, a second diversion dam would be constructed on the West Fork also at El. 500 ft amsl (Drawing 6) in addition to those facilities identified as part of the Base Case alternative. The West Fork impoundment would be very small , but would serve to divert stream flows into a pipeline that would intersect with the main penstock below the East Fork diversion dam and prior to entering the powerhouse. The des ign of the West Fork dam would be similar to the East Fork . Up to 6 cfs would be diverted from the West Fork of Loud Creek and conveyed via a 16 in diameter penstock to the East Fork penstock . Downstream from the intersection point, the combined penstock would be increased to 18 in diameter to carry the combined 15 cfs flow from the East and West Fork diversions. Dock A dock and landing area will be required for offloading of materials during construction (Drawings 5 and 6). The same design approach was assumed for both the Base Case and Alternative 1. The facility would be located near the outlet of Loud Creek and provide efficient access to the powerhouse . The dock would consist of three polyethylene docks (6.5 ft x 10 ft), an aluminum gangway (4 ft x 35 ft), and two 12-inch steel piles. This dock structure may change during the design process depending on the type of wave action exerted along the shoreline from the bay . · The landing area would be located adjacent to the dock to allow access for equipment on and off of barges or boats . This landing area will consist of a gravel ramp/pad (approximately 40 ft x 50 ft x 1 ft in size) and it will extend below the high tide line on the shore. The estimated volume for this landing area is 100 cubic yards . The proposed access road will tie into the loading dock. Loud Creek Hydropower Development Conceptual Design and Feasibility Report Page 19 Access Roads A road will be required to provide access to the dam(s) to support construction as well as subsequent operation and maintenance activities (Drawings 5, 6 and 11) for both the Base Case and Alternative 1. The road will be constructed from the dock area to the powerhouse, then continue from the powerhouse up to the dam(s). Due to the steep elevations in two portions of the road alignment, two climbing turns will be required. These roads will be designed so that equipment may travel safely up the hill and erosion is minimized during precipitation and snowmelt events. The road will be constructed from a minimum of 6 in of % in minus road mix placed over the exposed subgrade. The final design of the road cross-section will be determined incorporating the recommendations of a geotechnical site investigation which will be required as part of the final design work effort. Powerhouse A powerhouse will be built near the outlet of Loud Creek above the high tide line (Drawings 5 and 6) for both the Base Case and Alternative 1. The powerhouse will be approximately 30 ft by 30 ft in size and will house the turbine generator, electrical components, maintenance vehicles, and equipment. The building and footing w i ll be designed to meet the applicable building code requirements . Drawings 14 and 15 illustrate the powerhouse floor plan and equipment arrangement. A horizontal two jet Pelton turbine with a directly connected synchronous generator arrangement is indicated. A backup diesel generator will be stationed at the Harbor to provide power in the event of a powerhouse shutdown. The diesel generator will also be used for the new hovercraft maintenance and storage area at the Harbor. This generator will be sized with adequate capacity to support not only the hovercraft facility , but the entire harbor area with provision for future expansion . The ability to transport and store fuel to the Harbor site makes it an ideal location for the diesel generator. The close proximity to the load center is also an advantage to this location. Substation A small pad-mounted transformer will be installed to step up the generator voltage (480V or 600V 3-phase) to transmission voltage. The location and construction method of this transformer will be determined during subsequent design phases of this project. However, it is anticipated that the transformer and associated pad will be located adjacent to the powerhouse along the access road. Power Transmission and Interconnection It is envisioned that the transmission line will consist of underwater cable(s) starting from a terminal on shore near the powerhouse and extend around the southwest side of Loud Creek Hydropower Development Conceptual Design and Feasibility Report Page 20 the bay to the new Harbor facilities. These facilities are proposed at the west end of the bay in the intertidal area (Drawing 3). The power is likely to be transmitted to the City/Trident along a new road (direct buried) from the new Harbor facilities. The location and construction method of the transmission line will be determined during subsequent design phases of this project. To transmit the power generated at the Loud Creek Hydro Plant to the City, several electrical system components will be required. A step-up substation at Loud Creek Hydro Plant, a transmission line to the City, and a delivery point at the City's existing diesel power plant are required. The step-up substation at Loud Creek will transform the voltage of the generated power to match the City's existing distribution voltage, 12.4 7 kV grounded wye. This will facilitate the connection of the transmission line to the City's distribution system without another transformation. Due to extreme weather on the Aleutian Chain, the 12.47 kV power transmission line from Loud Creek to the City will be underground. Several routing options were considered for the transmission line as described below (see Drawing 14 ): • Option 1: Routing would begin at the Loud Creek Hydro Plant and run directly across Akutan Harbor to the City power plant. A submarine power cable would be utilized for the entire run . • Option 2 : Routing would begin at Loud Creek Hydro Plant, then enter Akutan Harbor running underwater following the perimeter of the harbor via submarine cable to the western side of the existing Trident facilities. Routing would then proceed on land and run north of the existing Trident facilities and then follow the existing foot trail east of the Trident facilities to the existing City diesel power plant. The landward transmission line would utilize conventional underground cable. • Option 3 : Routing would follow the same routing as Option 2. In addition to Option 2, a small segment of the transmission line would exit the harbor for a short section at the west end of Akutan Harbor where the proposed Harbor dock facilities will be located. This small land section of the routing would provide future electric service to the proposed facilities. • Option 4: Routing would begin at Loud Creek Hydro Plant, then enter Akutan Harbor running underwater following the perimeter of the harbor via submarine cable to the west end of Akutan Harbor. The routing would then exit the harbor onto the land at the proposed Harbor dock facility. The routing would then follow the future Harbor dock service road to the City diesel power plant utilizing conventional underground power cable. Loud Creek Hydropower Development Conceptual Design and Feasibility Report Page 21 • Option 5: Routing is to provide a power feed to the existing Trident facilities from the City's distribution system. It follows the existing foot trail from the City to the Trident facilities and would utilize conventional underground cable. • Option 6: Routing would be completely overland in the upland adjacent to the high tide line along Akutan Bay . A primitive road would be constructed along the route for installation and maintenance . The line would travel from Loud Creek to the proposed dock facilities and then onto Akutan on the proposed road . During the course of the feasibility study analys is, the C ity requested that options for delivery of power to the new Harbor facilities as a standalone option be considered. These options are : • Option 4a : Routing would begin at the Loud Creek Hydro Plant , then enter Akutan Harbor running underwater following the perimeter of the harbor via submarine cable to the Harbor facilities located at the west end of Akutan Harbor. • Option 6a: Routing would be completely overland in the upland area along Akutan Bay to the Harbor facilities located on the west end of Akutan Harbor. Loud Creek Hydropower Development Conceptual Design and Feasibility Report Page 22 En ergy Produ ction The estimated annual energy production was estimated for the Base Case and Alternative 1. A brief discussion of the approach , analysis , and projected energy production is presented in the following paragraphs . Base Case For purposes of estimating annual energy production from a hydroelectric project, a long-term reco rd of average daily stream flows is required . Unfortunately, no such record exists for Loud Creek. The work done by the DGGS is not a long enough record to be of use . Data being collected at Loud Creek starting on February 18, 2010 as a part of this effort will not be available and will still be too short of a record to be of use in the conceptual design analysis. The available data will be collected in June 2011, compiled, and submitted under a separate cover. Data collection will continue in order to provide a complete year of flow data to determine daily and monthly flows . For this conceptual analysis, the Russell Creek reco rd from October 1995 to October 2009 was utilized . By using the ratio of the drainage areas of the Russell Creek basin (30.9 square miles) and the Loud Creek basin (above the proposed dam area of .78 square miles), a new record of daily flow was developed to be used for energy production estimates . Figure 11 shows the daily flows for Lou d Creek developed by factoring the Russell Creek data . Loud Creek Hydropower Development C onceptual Design a nd Feasibility Re port Page 23 Loud Creek Calculated Flows J-95 J-96 D-96 D-97 D-98 D-99 D-00 D-01 D-02 D-03 D-04 D-05 D-06 D-07 D-08 D-09 Date Figure 11. Loud Creek Ca lculated Flows In order to develop a detailed power generation model , a computer model of the stream and pipeline system was constructed using EXCEL software. A daily time-step model was developed that projects daily energy generation using daily inflows obtained from the daily average flow data. For each day in the model, inflow at the intake is taken from the hydrology data. For this analysis, we have assumed that there is no minimum flow required below the diversion dam . The stream flow is the flow available that day for power generation. This is then capped at the maximum flow capacity of the turbine, which is a function of the size of the turbine. Any available flow in excess of plant capacity would be spilled into Loud Creek at the intake. For the Base Case, a range of installed capacity was reviewed. An installed capacity of 350 kW (maximum output) appears reasonable given that it yields a plant capacity factor of 37%, which would be considered a typical run-of-the-river plant factor. Turbine operation is then modeled , taking into account the available flow, head losses in the penstock at that flow , and variation in machine efficiency (both turbine and generator) depending on percent load . Pipeline head losses are calculated at each daily flow using a pipeline friction equation and a pipeline friction factor head loss coefficient of 0.014, which is a typical value for steel or HOPE pipe . Daily generation is calculated , and then generation from each day is added up to provide monthly and annual total expected gross generation. Loud Creek Hydropower Development Conceptual Design and Feasibility Report Page 24 However, this total needs to be adjusted for other expected losses. The model allows the user to make deductions to the gross generation for the following: • Main transformer and transmission line losses -set at 1 % and 3%, respectively • P lant outage for planned and unplanned maintenance -set at 3% • Use of energy for station service (heat, lights , lubrication, cooling & HPU pumps, controls) -set at 10 kW The projected generation is then tabulated monthly, annually, and the plant capacity factor is then calculated . Table 4 presents the results of the energy production analysis for the Base Case. Based on this analysis, the project could be expected to produce an average of 1, 132,861 kWh annually . A more detailed projected monthly generation data for the average water year (1996) for the Base Case and Alternative 1 is included in Appendix E. 1996 37 % 1997 974 ,576 32% 1998 1,244 ,561 41% 1999 903,900 29% 2000 1,197,077 39% 2001 1,065,179 35% 2002 1,217,384 40% 2003 1 ,081 ,621 35% 2004 1,414 ,624 46% 2005 1,301,905 42% 2006 1, 125,781 37 % 2007 1,140,416 37 % 2008 931 ,915 30 % Avera e 1, 132,861 37 % Alternative 1 For Alternative 1, an energy analysis was made for an average year (1996) to incorporate both drainage areas above the dams (total drainage area 0.78 square miles). Based on this computation, the installed capacity would increase to 450 kW, the penstock inside diameter would increase to 18 in after the penstock intersection. The average annual energy production would increase to 1,548, 100 kWh (approximately 37% greater than the Base Case). The plant capacity factor for this installation was estimated at 39%. Loud Creek Hydropower Development Conceptual Design and Feasibility Report Page 25 Permitting The regu latory agencies that may exert authority over the construction and operation of the Loud Creek Hydropower Development are discussed in the following paragraphs . The regulatory authority of each agency and the required perm its and approvals for construction are presented. As noted below, the FERC has primary jurisdiction over construction of most hydropower projects (in addition to other entities). However, on some small projects in Alaska , the FERC has agreed that certain projects are non-jurisdictional. In those cases , the State has been the entity that approves the construct ion of a hydroelectric project. For example , the Nushagak Cooperative i n Dill ingham, Alaska was able to obtain a declaration of non -jurisdiction because its proposed projects would not be connected to an inter-state grid ; the project would not be lo cated on federal lands and is located on a non-navigable river. It is believed that Loud Creek could meet these same cond itions . Federal Energy Regulatory Commission Under the Federal Power Act, the FERC has been appointed with the authorization and regulation of the nation 's non -federal hydropower resources . FERC issues three types of authorizations : • License -Issued for 30-to 50-year terms and must be renewed each term . • 5-Megawatt (MW) Exemption -This exemption is issued in perpetuity and must be located at the site of an existing dam or use a natural water feature without the construction of impoundments. The applicant must own all lands and facilities other than federal lands to be eligible . • Conduit Exemption -This exemption is issued in perpetuity and must use the potential of a conduit constructed primarily for non-hydropower purpose. The applicant must own the proposed powerhouse and the lands upon which the powerhouse will be located . A conduit exemption may not use federal lands . The Loud Creek Hydropower Development will not qualify for the 5-MW exemption since a new dam impoundment will be constructed . It also does not qualify for the conduit exemption since it will be located within a natural stream system . If FERC were to confirm that they had jurisdiction over the proposed Loud Creek Project, the C ity would have to apply for a preliminary permit. It may be a candidate for licensing under the small hydro/low impact expedited licensing process. The City would apply for a License for the construction and operation of the project using FERC 's Traditional Licensing Process (TLP) instead of the default Integrated Licens ing Process (ILP). The TLP requires minimal steps as compared to the ILP process . Once a preliminary perm it has been received from FERC , the licensing process would begin the same as with the Loud Creek Hydropower Development Con ceptual Design and Feasibil ity Report Page 26 ILP process; a Notice of Intent (NOi) and pre-application document (PAD) filed with FERC along with a request to use the TLP. Once FERC approves the use of the TLP , the City would proceed under the TLP Process, with some revisions to expedite the process. This would involve combining scoping of issues with pre-filing consultation and working with the agencies to expedite their rev iews and set their terms and conditions early. The following summarizes the FERC application process . 1. First Stage a. Applicant submits to FERC : i. Notice of Intent (NOi), ii. Pre-Application Document (PAD), iii. Request to use TLP, and iv. newspaper notice; b. FERC approves use of TLP ; c . Applicant conducts joint agency/public meeting and site visit; d . Resource agencies and tribes provide written comments ; and e . Agencies , tribes, or applicant request dispute resolution on stud ies with the FERC . 2. Second Stage a . Applicant completes reasonable and necessary studies ; b. Applicant provides draft application and study results (National Environmental Policy Act) to resource agencies and tribes; c . Resource agencies and tribes comment on draft application; and d. Applicant conducts meeting if substantive disagreements exist. 3. Third Stage a. Applicant files final application with FERC and sends copies to agencies and tribes. United States Army Corps of Engineers The United States Army Corps of Engineers (USACE) will require an individual permit for the construction of a new hydroelectric facility on a jurisdictional water body under the authorization of Section 404 of the Clean Water Act. The City will be required to submit a completed copy of the "Application for Department of the Army Permit" to the USAGE along with associated engineering drawings showing the design of the project in relation to jurisdictional water bodies . A delineation of the high tide line, o rdinary high water (streams) and/or wetlands may be required to complete the USAGE appl ication and identify the location of jurisdictional water bodies within the boundary of the project. Also , if the project will impact a federally listed threatened or endangered species or their critical habitat, consultation with the United States Fish and Wildlife Service (USFWS) and/or the National Oceanic and Atmospheric Administration (NOAA) Fisheries ' National Marine Fisheries Service (NMFS) will be required to address these impacts . The preparation of a Biological Assessment may be required to supplement the USAGE individual permit depend ing on agency comments and review. Loud Creek Hydropower Development Conceptual Design a nd Feasibility Report Page 2 7 Alaska Department of Natural Resources Dam Safety Program The Alaska Dam Safety Program does not have jurisdiction over dams that are federally owned or operated or hydroelectric dams regulated by FERG. If FERG confirms they have j urisdiction over this hydroelectric project, then the Alaska Department of Natural Resources does not have regulatory authority on this project fo r dam safety . If during final design, the dam si z e increases to fall within the Alaska Dam Safety Program jurisdictional authority, coordination with the state dam safety office should be initiated . Jurisdictional dams are considered if the dam reservoir exceeds 50 ac re-ft i n volume and 10 ft in height or any dam 20 ft in height or greater. Water Rights The diversion of water from Loud Creek for use in the hydroelectric project will require appropriate water rights . The Loud Creek drainage is owned by the City as acquired under 14(c)3 of the Alaska Native Claims Settlement Act. The tidelands from Loud Creek to the Trident facility are owned by the State of Alaska . Based on a sea rch , the water rights have not been acquired fo r the project. An "Application for Water Right" will require comp letion and submittal to the Alaska Department of Natural Resources . Alaska State Historic Preservation Office The Alaska Office of History and Archaeology carries out the responsib ilities of the State Historic Preservation Office . Section 106 of the National Historic Preservat ion Act requires review of any project funded, licensed, permitted, or assisted by the federal government for impacts on significant historic properties. If a project l icense is required by FERG , the project will require a Section 106 review before a federal permit can be approved . A review will be conducted by the Alaska Office of History and Archaeology to determine if cultu ral resources surveys have been previously done in the area. If cultural resources are present or the potential to discove r unknown sites is high, a survey may be recommended in the Loud Creek area. This survey will be incorporated into the environmental assessment or environmental impact statement portion of the FERG license application. An archeological survey was carried out for the City in August 2010 . A report, "An Archaeological Survey of the Hot Springs Valley and Akutan Harbor Energy and Rural Developments Projects" by Buck Benson and Herbert Maschner (Idaho State University) documented the results of the survey work performed . The survey included the portion of Loud Creek basin , which could be affected by the development of a hydroelectric project. Three previously recorded sites were identified (including the remains of a 20th century whaling station . All three identified sites can be avoided during construction and operation of the project. Loud Creek Hydropower Development Conceptual Design and Feasibility Report Page 28 Alaska Coastal Zone Management Review (Coastal Project Questionnaire) The State of Alaska uses a coordinated system for agency review and processing of all resource-related permits required for proposed projects in or affecting coastal areas of Alaska . This system , called "project consistency review," is based on the Alaska Coastal Management Program (ACMP) and is designed to improve management of Alaska's coastal land and water uses. Project proposals are rev iewed to determine the project's consistency with the standards of the ACMP and enforceable policies of approved district coastal management programs . Participants in the State's review process include: the applicant; State resource agencies: Alaska Departments of Environmental Conservation (DEC), Fish and Game (DFG), and Natural Resources (DNR); the affected local coastal district; and other interested members of the public. The Coastal Project Questionnaire (CPQ) will determine State and federal permitting requirements as well as which State agency will coordinate the consistency review. Alaska Department of Environmental Conservation The Alaska Department of Environmental Conservation has implemented the Alaska Pollutant Discharge Elimination System, which meets the standards of the Environmental Protection Agency (EPA) National Pollutant Discharge Elimination System (NPDES). If the construction of the project will disturb more than one acre of land, a Construction General Permit will be required along with the development of a Storm Water Pollution Prevention Plan (SWPPP). Alaska Department of Fish and Game The Alaska Department of Fish and Game regulates fish and wildlife species within their jurisdiction. Based on observations made during the October 2009 site visit, anadromous fish were not observed in Loud Creek. Furthermore, the Alaska Department of Fish and Game has not identified Loud Creek as an anadromous fish stream . However, not all the streams in the Akutan region have been mapped, and subsequently, the absence of information in the fish catalog does not necessarily indicate that anadromous species are not present. A fish study may be required to document the presence or lack of fish in Loud Creek to comply with the Alaska DFG permitting requirements . It has not been confirmed if Loud Creek supports fish presence or habitat. However, if the project intends to disturb fish species or their habitat, a Fish Habitat (Title 16) Permit will be required. Local Government The local regulatory agency for the project is the City; however, there are no local regulations pertaining to the construction of new dams or hydroelectric projects within their jurisdictional limits. Loud Creek Hydropower Development Conceptual Design and Feasibility Report Page 29 Cost Estima tes Cost estimates were prepared based on the conceptual design details and drawings presented within this report for the Base Case and Alternative 1. Transmiss ion and substation costs were estimated for each of the transmission Options 1 through 6 , as well as the new Harbor only transmission, Options 4a and 6a. These estimates are considered planning level conceptual cost estimates. More detailed cost estimate breakdowns are included in Appendix B . Base Case Canyon Industries was contacted for a budgetary turbine-generator water-to-wire equipment price. This package would include a turbine with direct driven synchronous generator, exciter, turbine inlet valve , switchgear, controls and station service equipment. The December 2009 estimated price was $500 ,000 which is Freight on Board (FOB) Bellingham , WA and does not include shipping, offloading, installation, or startup assistance. It is expected that a pre-engineered powerhouse metal building 30-ft by 30-ft would be adequate to house the turbine-generator, auxiliary equipment, and switchgear as well as provide adequate room for an ATV and snowmobile . This building size would be adequate for either the Base Case or Alternative 1. A reinforced concrete foundation will be required for the turbine-generator equipment, building structure (footings) and tail race pit. The estimated cost for this component is approximately $180,000 . The penstock will be a 16-inch ID running in an excavated 5-foot trench for approximately one mile . The maximum static pressure is calculated to be 220 psi . The pipe would be transported by barge to the site. Installation would require trenching, production and placement of backfill , and restoration of the surface to prevent eros ion . The Base Case dam construction includes the primary embankment on the East Fork, the outlet works, and associated erosion control. For the purpose of preparing cost estimates , the dam was assumed to consist of compacted earthfill with a seepage cutoff wall , a vertical riser, and a rock riprap open channel spillway . Alternative 1 The water-to-wire equipment price for Alternative 1 is expected t o increase to $645 ,000 based on the Canyon Industries estimate . This cost does not include shipping , offloading , installation , or startup assistance. It is assumed that the same building for the Base Case will be acceptable for Alternative 1. Loud Cree k Hydropower Development Con ceptual Design and Feasibility Report Page 30 A reinforced concrete foundation will be required for the turbine-generator equipment , building structure (footings) and tailrace pit. For Alternative 1, the lower part of the penstock would increase from a 16 to an 18-inch inside diameter (from the point of the intersection of the two separate penstocks from each dam to the powerhouse). The upper part of the penstock would split and supply water from the two dams . The length of the penstock from the West Fork Dam to the intersection of the main penstock from the East Fork Dam is approximately 950 ft and would be sized for 7 cfs, resulting in a calculated inside diameter of 16 in. Both the East Fork and West Fork dams will consist of compacted earthfill with a seepage cutoff wall, a vertical riser, and a rock riprap protected open channel spillway. Transmission and Substation Costs Transmission and substation costs were provided by EPS . A number of transmission alternatives were considered as part of this study . The costs are presented in Table 5. Additional cost breakdowns for the transmission and substation cost estimates are presented In Appendix B. Table 5 Power Transmission and Substation Costs Onshore Submarine Total Item Description Cable Cable Estimated Length Length (miles) (miles) Cost Loud Creek Step -Up Substation, 500 kVA w/ Recloser at Loud Creek and at Akutan Power House N/A N/A $352,600 Option 1 -Loud Creek to Akutan -Directly Crossing Harbor -All Submarine cable N/A 0.90 $1 ,364 ,400 Option 2 -Loud Creek to Akutan -Following shoreline to Trident and onshore to Akutan 0.70 3.20 $5,022,000 Option 3 -Similar to Option 2 with onshore portion at proposed dock facilities 0.90 3.10 $4 ,994 ,800 Option 4 -Loud Creek to Akutan -Submarine from Loud Creek to proposed dock facilities then onshore URD followinQ proposed road to Akutan Power House 2.80 1.70 $4,226,100 Option 4a -Loud Creek to Harbor -Submarine from Loud Creek to new Harbor -1.70 $2 ,750 ,200 Option 5 -Akutan Power House to Existing Trident Facilities 0 .50 0.00 $268 ,200 Option 6 -Loud Creek to Akutan -Overland URD from Loud Creek to proposed dock facilities then onshore URD foll owinQ proposed road to Akutan Power House 4 .80 -$4 ,086 ,700 Option 6a -Loud Creek to Harbor -Overland URD from Loud Creek to proposed dock facilities 2 .00 0 .00 $1 ,915,000 Notes : 1) Options 4a and 6a were developed to illustrate a power supply to the new Harbor facilities should this supply option be exercised . Option 4a provides a submarine routing while Option 6a is an overland route . Loud Creek Hydropower Development Conceptual Design and Feasibility Report Page 31 Basis of Transmission Cost Estimates Loud Creek Hydro Plant Substation • Install 500 1-0/A 480/12.5 kV step-up transformer at Loud Creek Powerhouse • Utilize 3-phase recloser at Loud Creek and at Akutan powerhouse for cable termination and line protection. • Provide oil containment for transformer • Assume 25 ft by 25 ft area for transformer, recloser, and ground grid • Control and interface of hydro to diesel plant not in estimate 12.5 KV Sub-Transmission line • 12.47 1-01 line construction • De livery to the existing City diesel power plant via new recloser placed to intercept an existing main feeder at City power plant. • #2 Cu 15 kV Power Cable, -1800 KVA ultimate power line capacity • Sectionalizing enclosures included at 900 ft intervals on land cable installations General • 20% contingency included on all project costs . • No Right-of-Way or Permits are included in estimate • Construction Equipment is assumed to be shipped to Akutan . The rental or use of this construction equipment has been included in the cost estimates. D iesel Generator Set The new Harbor facility would require a power supply in case the hydroelectric project has an outage or its output is insufficient to fully power the Harbor facility (assuming the new Harbor is not interconnected to the City generating plant). The cost for this diesel generator set is not included in the hydroelectric project cost estimate . A diesel gene rator set of 300 kW installed capacity would cost on the order of $500,000 including fuel tanks. Evaluation The 6 basic transmission options represent feasible routings for delivering power generated at the Loud Creek Hydro Plant to the City . Option 1, Loud Creek to Akutan using a submarine cable, is the shortest distance from the proposed powerhouse to the City, as well as the lowest cost. The submarine routing presents significant risk due to the potential for ships anchors damaging the submarine cable , as well as interrupting power service from Loud Creek . For this reason, Option 1 was eliminated from furthe r consideration . Options 2 and 3 have the highest cost and consist of a comb ination of submarine routings and land based route from the Trident facilities to the City. Though feasible these options have a higher cost and more challenging routing than proposed with Options 4 and 6. Loud Creek Hydropower Development Conceptual Design and Feasibility Report Page 32 The primary difference between Options 4 and 6 is that the first leg of the transmission line from the Loud Creek powerhouse to the new Harbor facilities is submarine with Option 4 and overland with Option 6. The second leg of the transmission line would follow the proposed road from the new Harbor to the Akutan powerhouse. Considering the challenging access and protected nature of the shoreline along the south shore of the Akutan Bay, Option 4 was selected as the recommended transmission option . Option 4a was developed at the City's request to identify the cost associated with delivering power to the new Harbor facilities only. Option 4 and 4a were carried forward to determine the cost of power for the Base Case and Alternative 1 power generation arrangements. Summary of Construction and Development Costs Table 6 presents the estimated project costs for the power generation Base Case and Alternative 1 arrangements. Each power generation alternative was coupled with the recommended transmissions Option 4 as outlined in the previous section. The Harbor only transmission, Option 4a, was provided for consideration as requested by the City. The cost estimate included engineering and permitting costs set at 8% of the construction costs . It is assumed that construction management of the project will be performed by the City with some engineering assistance during start-up. Construction cost estimates (dams, penstock, and the transmission system etc.) include a 30% contingency. See Appendix B for more detailed information on the cost estimates. Loud Creek Hydropower Development Conceptual Design and Feasibility Report Page 33 Table 6 Project Costs Task Base Case Alternative 1 Option 4 '} Option 4a"i Option 4' Option 4a" Turbine -Generator Equipment $1,040,000 $1 ,040,000 $1,300,000 $1,300,000 Dam Construction $320,000 $320,000 $640 ,000 $640,000 Penstock(s) $700,000 $700,000 $950,000 $950 ,000 Powerhouse Foundations $180,000 $180,000 $180 ,000 $180,000 Powerhouse Building $162,000 $162,000 $162,000 $162,000 Misc. Powerhouse Equipment $30,000 $30,000 $20,000 $20,000 Roads I Do ck $310 ,000 $310,000 $380,000 $380,000 Substation $353,000 $353,000 $353,000 $353,000 Transmission $4,226,000 $2,750,000 $4,226,000 $2,750,000 Trident or Harbor Interconnection $270,000 $270,000 $270,000 $270,000 Freiqht ($50,000/ba rqe) $50,000 $50,000 $100,000 $100,000 Construction Management I Startup $50,000 $50,000 $50,000 $50,000 Subtotal $7,691,000 $6,215,000 $8,631,000 $7 ,155,000 Engineerinq and Permittinq (8%) $615,280 $497,200 $690,480 $572,000 Total $8,306,280 $6,712,200 $9,321,480 $7,724,400 Notes: 1) Transmission Option 4 consists of submarine cable (intertidal burial) around the perimeter of Akutan Bay to the new Harbor facilities, then exit to follow the future Harbor dock service road to the City diesel power plant utilizing conventional underground power cable. 2) Transmission Option 4a consists of submarine cable (intertidal burial) around the perimeter of Akutan Bay to the new Harbor facilities . This is a Harbor only transmission line . Loud Creek Hydropower Development Conceptual Design and Feasibility Report Page 34 Cost of Power Overall, the cost of power could vary depending on the operations and maintenance (O&M) cost and the project cost. Presently energy generated at the Town Creek plant (100% diesel generation), as reported in the Power Cost Equalization (PCE) forms, is produced for approximately 0.66 $/kWh . Cost of energy to residents, due to PCE, is presently 0.32 $/kWh. It should be noted that PCE is an issue to be considered, as PCE for hydroelectric generation would not be available. At other projects, the State has agreed to phase PCE out over time to minimize the impact. O&M costs include pe rsonnel, management, insurance, debt service (if applicable), contracted maintenance, replacement of spares , etc. The cost of O&M could range widely depending on financing and the other costs listed above . For the purposes of this report , it has been assumed that O&M costs will be approximately $100,000 per year including labor, equipment , equipment, parts, and overhead. The cost of power was estimated for the Base Case and Alternative 1 power generation arrangements. The recommended transmission Option 4, as well as the Harbor only transmission Option 4a, were coupled with the power generation alternatives to provide a total system cost comparison . Table 7 presents a summary of the cost of power for these power generation and transmission combinations, see Appendix F for calculations. As shown on Table 7, Alternative 1 is the preferred alternative delivering power at the lowest cost considering both transmission Options 4 and 4a. Cost of power, assuming no subsidies or grants, is still less than energy produced by diesel at the Town Creek plant. Of course, the cost of production by diesel generation is expected to climb in the long term, whereas cost of power produced by a hydroelectric facility will not significantly increase over time. Once the debt from the hydropower facility is retired, the cost of power would dramatically decrease. Loud Creek Hydropower Development Conceptual Design and Feasibility Report Page 35 Table 7 Cost of Power Base Case Alternative 1 Description Ootion 4 '1 Option 4a"1 Option 4 '1 Option 4a"1 Capital Cost $8,306,280 $6,712,200 $9,321,480 $7,727,400 Financing 100% 100% 100% 100% Debt $8,306,280 $6,712,200 $9,321,480 $7,727,400 Term (years) 30 30 30 30 Interest Rate 6% 6 % 6% 6% Annual P&I ($603,442) ($487,641) ($677, 195) ($561 ,387) Annual O&M ($100,000) ($100,000) ($100 ,000) ($100 ,000) Annual Energy Production (kWh) 1, 132,861 1, 132,86 1 1,548,100 1,548,100 Annual Cost of Power $/kWh) -0.62 -0.52 -0.50 -0.43 Notes: 1) Transm 1ss1on Opti on 4 consists of submarine cable (intertidal burial) around the perimeter of Akutan Bay to the new Harbor facil ities, then exit to follow the futu re Harbor dock service road to the City diesel power plant utilizing conventional underground powe r cable. 2) Transmission Option 4a consists of submarine cable (intert ida l burial) around the perimeter of Akutan Bay to the new Harbor facilities. This is a Harbor only transmission option. The cost of power generated by the Loud Creek Hydropower system was compared to the cost of other power generated on Akutan . As illustrated in Table 8 Trident's generation facilities would be expected to generate power at a significantly lower cost than the Loud Creek hydropower facility. This would suggest that Trident would be more likely to generate their own power rather than buy more expensive power from the Loud Creek project. Generation Source Diesel Generators Akutan Geothermal Pro"ect High Efficiency Diesel Generators (at a rate of 14.5 kWh/ al Tridents Self Generation Loud Creek Base Case -Transmission 0 tion 4 Loud Creek Base Case -Transmission 0 tion 4a Loud Creek Alternative 1 -Transmission 0 tion 4 Loud Creek Alternative 1 -Transmission 0 tion 4a Low Unit Power Cost $/kWh 0 .20 0.65 NA 0 .50 0.21 0.62 0.52 0.50 0.43 High Unit Power Cost $/kWh NA 1.01 NA 0.77 0.34 NA NA NA NA A significant issue associated with the development of the Loud Creek Hydropower Development has been that it can generate more energy than Akutan has historically used. As noted above, the project could generate between 1, 132,861 and 1,548, 100 kWh annually depending on the configuration . The City is presently selling less than 500,000 kWh annually . The new Harbor area is anticipated to consume the power levels as shown in Table 9. Loud Creek Hydropower Development Conceptual Design and Feasibility Report Page 36 Table 9 Anticipated Power Consumption . . . Power Consumer kWh/ ear Harbor 1, 150,000 Harbor Residences 60,000 Hovercraft Fac ilit 11 ,000 Resorts 150,000 Commercial Buildin s 150,000 Restaurants 250,000 WWTF 132,000 Total 1,903,000 Reference: Information Insights . 2010. Akutan Geot hermal Dev elopment Project Geothermal Energy Demand & Stakeholder Assessment. January, 2010. The anticipated amount of power consumption identified in Table 9 exceeds the level of power produced in both the Base Case and Alternative 1. However, there are several other energy projects proposed for Akutan that may provide the harbor area with energy. The Loud Creek hydropower project could deliver power to the City at, or below, the City's current cost of power using diesel generation. The Loud Creek project cost of power would be expected to be more cost effective when considering expected diesel cost increases. As shown on Table 8 , the Trident self-generation cost is significantly less than the Loud Creek hydropower project. It is believed that Trident would be more likely to generate its own power rather than buy more expensive power from the Loud Creek project. Without the sale of power to Trident and/or utilization of Loud Creek power at the new Harbor, power delivered to the City from Loud Creek would likely exceed the demand for the foreseeable future, particularly if the Town Creek hydropower system becomes fully operational. Loud Creek Hydropower Development Conceptual Design and Feasibility Report Page 37 Pr oject Schedule A project co nstruction schedule has been developed to illustrate the earliest date the project could be complete and producing energy. There are many factors involved in construction of a hydroelectric project. Of primary concern is obtaining the necessary permits and approvals for the construction work. Based on observations made during the October 2009 site visit, anadromous fish were not observed in Loud Creek . Furthermo re, the Alaska DFG has not identified Loud Creek as an anadromous fish stream. However, not all the streams in the Akutan region have been mapped , and subsequently, the absence of information in the fish catalog does not necessarily indicate that anadromous species are not present. It is likely that the regulatory agencies will require fish studies to support the reported lack of anadromous fish in Loud C reek. For this schedule, it has been assumed that permits for construction could be obtained within 12 months. It has been assumed that a FERG licensing process will not be requi red and the required permits can be readily obtained from other State of Alaska and Federal agencies . The overall permitting effort could range from 12 months to 18 months in duration depending on t he final configuration of the Loud Creek hydropower development. Some project components involve a long lead time to produce , including the turbine- generator equipment and the submarine cable for the project. For these components, the date the equipment is o rdered is on the critical path for project completion. It is possible to order the turbine-generator equipment fairly early as soon as the Owner is comfortable with obtaining permits for the construction of the project. Construction work in the Aleutian Islands , is normally performed during summer and early fa ll. The work execution would have to be sequenced to complete the access road, dam, penstock, and powerhouse building construction during the summer and fall months . Work within the powerhouse could continue through the winter months including final electrical , piping , controls, and finish work . The project schedule is presented in Appendix C. The schedule indicates that the project could be operational within approximately 3 years following notice to proceed. The environmental and permitting schedule would set the critical path on the overall project t imeline . Loud Creek Hydropower Development Conc eptual Design and Feasibil ity Report Page 38 Conclu sions and Final Recommendations Conclusions Based on the technical analys is and findings of this study, the Loud Creek hydropower project is determined to be feasible . Alternative 1 is the recommended altern ative consisting of new diversion dams on the East and West Forks of Loud Creek , a design flow of approximately 15 cfs delivered to a new powerhouse via an 18 inch diameter penstock, new powerhouse w ith a single 350 KW Pelton Wheel turbine , loading dock, and primitive access road to the diversion dams . Option 4 was the recommended transmission routing consisting of a submarine cable buried with an intertida l zone from the Loud Creek powerhouse to the new Harbor facilities . At this point , the transmission line will exit the harbor and continue landward following the future Harbor dock access road to the existing Akutan diesel power generation facil ities . The recommended Alternative 1 coupled with transmission Opt ion 4 has an estimated project cost of $9,321,480 and a cost of power of $.50 per kWh . Alternative 1 is anticipated to generate a total of 1,548 , 100 kWh annually. Considering a transmission Opt ion 4a which delivers power to only the new Harbor facilities combined with A lternative 1 power generation arrangement has an estimated project cost of $7 ,724,400 and a cost of power for $0.43 per kWh. The reduced length and cost of the transmission line results in an approximate project cost savings of $1 ,597,000 and $0 .07 per kWh cost of power reduction . The Loud Creek power could be delivered at or below the current cost of power using diesel generation . The Loud Creek power cost would be significantly higher than Trident's existing self generation cost. It is likely that Trident would generate its own power rather than buy more expensive power from the Loud Creek project. Without the sale of power to Trident and/or utilization of Loud Creek power at the new Harbor, power delivered from Loud Creek directly to the village would exceed demand for the foreseeable future, particularly if the Town Creek hydropower system becomes fully operational. Recommendations As a result of the study analysis, the City requested that the study team evaluate a "standalone" alternative for the new Harbor. The combination of Alternative 1 power generation and Option 4a power transmission from the Loud Creek powerhouse to the new Harbor represents the standalone alternative. The estimated $0.43 per kWh would be s ignificantly lower than a diesel power generation alternative at the Harbor. As a result, the st andalone combination of Alternative 1 power generation coupled with Option 4a power transm ission to the Harbor only is the recommended alternative . Lo ud Cree k Hydropower Development Co nceptual Design an d Feasibility Report Page 39 The following work elements are recommended as the project moves to the next phase : 1) The conceptual business and operations plan requ ired under AEA Phase II milestones should be completed along with a business case analysis that addresses the cost of diesel, power purchase agreements , projected revenues , and the non-monetary benefits of the project. The following work elements are sequential and would be dependent on completing the business plan . 2) More comprehensive evaluation to define the permits that will be required as well as any required environmental studies in support of those permits . It is recommended that a declaration from FERC of non-jurisdiction be obtained as soon as possible because the FERC licensing process takes a very long time (typically years). It is also recommended that initial agency contact be made as soon as possible to better define permit requirements , time line and any s tudy requirements . 3) Additional engineering work will be required to define requirements to coordinate the operation of Loud Creek hydropower development with the Town Creek project if the projects are interconnected . Specifically this will include analyzing the power requirements of the City and the power production potential of the Loud Creek and Town Creek projects . 4) Water rights need to be obtained for the project 5) A geotechnical investigation needs to be performed along the proposed road , pipeline , and dam to determine the quantity of fill material and final costs for the buried pipeline , dam foundation and construction methods , and overall geotechnical design recommendat ions 6) A topographic survey of the project area needs to be completed for the subsequent design phases of the project. 7) An analysis of the proposed energy projects on Akutan should be performed to identify the amount of energy that could be potentially produced. As part of this analysis, potential users should be contacted to help determine future energy requ irements for the Harbor, Trident, and the City . 8) Coordination with Trident should be performed regarding their desire to purchase excess energy generated from , the project (if interconnection is desired). The following tabulates the recommended tasking identified above with a cost estimate for the next project phase. Loud Creek Hydropower De velopment Con c eptual Design and Feasibility Report Page 40 Table 10 Proposed Tasking Cost Estimates Task Cost Estimate Permitting Assistance $100,000 Town Creek/Loud Creek Enqineerinq Coordination (if needed) $10 ,000 Water and Land R ights To Be Determ ined Geotechnical lnvestiqation $30,000 Topoqraphi c Survey In-Progress Akutan Enemv Pro ject Analysis $30,000 Coordination with Trident $5 ,000 Note that significant engineering work will be requ.ired to advance the design of the project to the point that all permits can be obta ined and construction contracts can be awarded . The permitting assistance cost identified above is part of the estimated engineering/permitting costs included in the cost estimate shown in Table 1 O. Loud Creek Hydropower Development Conceptual Design and Feasibility Report Page 41 References Carrick, Stan and Ireland, Roy, Summary of Streamflow Data for the Akutan Area, Unimak A-6 Quadrangle, Alaska, October 1989 . Dam Safety and Construction Unit, Water Resources Section, Division of Mining , Land, and Water; Alaska Department of Natural Resources , June 2005, "Guidelines for Corporation with the Alaska Dam Safety Program ", July 2005 . FEMA, Federal Guidelines for Dam Safety, Selecting and Accommodat ing Inflow Des ign Floods for Dams , April 2004. Glisten Associates , Akutan Airport Marine Access Study, prepared for HOR Alaska Inc, July 2005. HOR/OTT Engineering , Inc, Akutan Hydroelectric Feasibility Study , Final Report, prepared for Alaska Energy Authority, June 1990. Information Insights, Akutan Geothermal Development Project, Geothermal Energy Demand & Stakeholder Assessment, prepared for City of Akutan , January 2010 . USAGE, "Hydrogeology of Proposed Harbor Site at Head of Akutan Bay", Akutan Island, Alaska, August 2001 . USBR, Design of Small Dams , Revised Ed it ion 1977. USGS, Geology of Akutan Island, A laska, 1998 . U.S . Department of Commerce, Technical Paper No. 47, Probable Maximum Precipitation and Rainfall-Frequency Data for Alaska . Loud Creek Hydropower Development Conc eptual Design and Feasibility Report Page 42 APPENDIX A DRAWINGS LOUD CREEK HYDROPOWER DEVELOPMENT 0 I 0 tJ UNALASKA\ .• 4 " ~~~\_ ' AKUTAN LOCATION MAP NTS ,e-.. 6/1 /11 MM CONCEPTUAL DESIGN DRAWINGS Al\ 3/30/10 DA CONCEPTUAL DESIGN DRAWINGS /A\ 2/26/ 10 DA CONCEPTUAL DESIGN DRAWINGS REV DATE BY DESCRIPTION CITY OF AKUTAN, ALASKA CONCEPTUAL DESIGN DRAWINGS ~ANCHORAGE WARNING 0 1/2 1 IF TI-115 BAA DOES NOT MEASURE 1 ~ THEN ORAW1NG IS NOT TO SCAil.£.. VIC INITY MAP NTS MCMILLEN, LLC 14-01 SHORELINE DR. SUITE 100 BOISE. ID 83702 omcE: 208.J.42.4214 FAX; 208.342.4216 owe ND. 3 5 6 7 6 9 10 11 12 13 DRAWING INDEX DESCRIPTION LOCATION MAP, VICIN ITY MAP. AND DRAWING IN DEX STANDARD ABBREVIATIONS AND SYMBOLS GENERAL SITE PLAN DESIGN CRITERIA SITE PLAN -BASE CASE SITE PLAN -ALTERNATIVE 1 TYPICAL DAI.I PLAN ANO SECTIONS DAM PENSTDCK SECTION ROAf'JWAY DETAILS PIPELINE PLAN. PROFILE, ANO DETAILS -BASE CASE PIPELINE PLAN. PROFILE. ANO DETAILS -ALTERNATIVE 1 POWERHOUSE FOUNDATION PLAN AND SECTIONS POWERHOUSE GENERATOR PLAN ANO SECTION TRANSMISSION LINE ROUTING OPTIONS 1-----------C-ITY __ o_F_A_K_u_T_A_N_, _A_LA_s_K_A _________ -i DESIGNED D. AXNESS LOUD CREEK HYDROPOWER DEVELOPMENT 1--------------------------------t DRAWN R. WOOD LOCATION MAP, VICINITY MAP, AND DRAWING INDEX CHECKED M. McMILLEN ISSU ED DATE 6/1 /11 DRAWING 1 SCALE; AS NOTED & 1/0 AMP ABBREV AC ACI AODL AlSC Al.JG ALM ALT ALUM ANG APPROX ARCH AS ASD ASS'f AllfO AUX AVG B/W BKR BL BLDG BM BOF BOP BOT BRG BRGP BS BTU c CA CAIR CAV Cr::H CF CFS CHO CHEM CIP CJ CL cw CLR CMP CMU CNTL co COL CONC CONN CONST CONT CONTD COORD CP CPVC CSK CTR CTRL cu CULV OJ r::H CY D OBL DEG DEG F DEMO DIA DIAG DIM DIV DL DUP DWG(S) E EA Ef EGL EJ EL EMBD ENGR EOP EOUIP EOUl\I ES J6. 6/1/11 ..!}, 3/30/10 IA 2/2s/10 REV DATE AND OPEN-CLOSE AMPERE ABBREVIATION ASPHALT CONCRETr AMERICAN CONCRETE INTERNATIONAL AODITTONAL AMERICAN INSTITUTE OF STEEL CONSTRUCTION ALIGNMENT ALARM ALTERNATE ALUMINUM ANGLE APPROXIMATE ARCHITECTURE AIR SUPPLY ALLOWABLE STRESS DESIGN ASSEMBLY AUTOMATIC AUXILIARY AVERAGE BACK OF WALL BREAKER BASELINE BUILDING BENCHWIRK, BEAM BOTTOM OF FOOTING BOTTOM/BEGINNING OF PIPE BOTTOM BfARING BfARING PLATE BOTH SIDES BRITISH THERMAL UNfT CONOUfT COMPRESSED AIR COMPRESSED AIR SYSTEM CONTINUOUS ACTING AIR VALVE COUNTER CLOCKWISE CUBIC Fro' (FOOT) CUBIC Fro' PER SECOND CHORD CHEMICAL CAST IN PLACE CONSTRUCTION JOINT CENTERLINE, CLASS, CLOSE COllTROL JOINT CLEAR CORRUGATED METAL PIPE CONCRETr MASONRY UNIT CONTROL CLEAN OUT, CONCRETr OPENING COLUMN CONCRETr CONNECTION CONSTRUCTION CONTINUOUS CONTINUED COORDINATE COllTROL POINT CHLORINATED POLYVINYL CHLORIDE COUNTERSINK CENTER CONTROL CUBIC CULVERT VALVE. CONTROL CLOCKWISE CUBIC YARD ORAN DOUBLE DEGREE DEGREE FAHRENHEIT OEMOLITTON DIAMETER DIAGONAL. DIAGRAM DIMENSION DMSION DEAD LOAO DUPLICATE ORAWING(S) EAST, ELECTRICAL (OWG DISCIPLINE) EACH EACH FACE ENERGY GRADE LINE EXPANSION JOINT ELBOW. ELEVATION EMBED OED ENGINEER END OF PIPE EQUIPMENT EQUIVALENT EACH SIDE, EQUAL SPACE EW EXC EXT FAS FB FON FF FG FlG FLG FLR FOC FOW FPS FlPT FT FTG FW G GA GA GAL GALV GPM GR GVL HOPE HEX HGL HP HSS HTR HVAC HWL HYO HZ l&C IBC ID IE IF INCL INSTR INV IRR ISO JB JCT JF JT KIP KO KV KW KWH LB LF u UH UV LONG LT LTD LTG LV LWL MA MAINT MAN MAS MAX MECH MCC MED MFR MH Ml MIN MISC MJ MOD MON MPT MSL mv MM CONCEPTUAL DESIGN DRAWINGS DA CONCEPTUAL DESIGN DRAWINGS DA CONCEPTUAL DESIGN DRAWINGS BY DESCRIPTION EACH WAY EXCAVATION EXTERIOR, EXTERNAL, EXTENSION FABRICATE FLAT BAR FOUNCATION FlN ISHEO FLOOR FlNISHED GRADE FlGURE FLANGE, FLANGED FLOOR FACE OF CONCRm FACE OF WAU Fro' PER SECOND FEMALE PIPE lHREAD FOOT/Fro' FOOTING, ITTTING FlELD WELD GAS GAGE (METAL THICKNESS) GAGE, GAUGE GALLON GALVANIZED GALLONS PER MINUTE GRADE GRAVEL HIGH DENSITY POLYETHYLENE HEXAGONAL HYDRAULIC GRADE LINE HORSEPOWER HOLLOW STRUCTURAL SHAPE HEATER HEATING, VENT ILATION, & AIR CONOITTONING HIGH WATER LEVEL HYDRANT HERTZ (CYCLES PER SECOND) INSTRUMENTATION AND CONTROL ll'ITERNATIONAL BU ILDING CODE INSIDE (OR INTERNAL) DIAMETER INYffiT ELEVATION INSIDE FACE INCLUDE, INCLUDING INSTRUMENTATION INVERT IRRIGATION ISOMETRIC JUNCTION BOX (J-BOX) JUNCTION JOINT FlUER JOINT KIP (1000 POUNDS) KNOCK OUT KILOVOLTS KILOWATTS (REAL POWER) KILOWATT HOUR POUND LINEAR FOOT LIVE LOAD LONG LEG HORIZONTAL LONG LEG VERTICAL LONGITUDINAL LEFT LIMITED LIGHTING LOUVER LOW WATER LEVEL MIUIAMPERES MAINTENANCE MANUAL MASONRY MAXIMUM MECHANICAL MOTOR CONTROL CENTER MEDIUM MANUFACT1JRER MANHOLE MILE MINIMUM MISCELLANEOUS MECHANICAL JOINT MODIFY MONUMENT MALE PIPE THREAD MEAN SEA LEVEL MIUl\IOLTS N N/A NC NEG NO No. NOM NPS NPSH NPT NRS NTS O&M QC OD OF OF OPNG OPT ORIG OUT OVHG OWSJ oz p PA PAR PC PCC PCF PCT PED PEN PERF PERM PERP PH Pl PL PLC PN PNL PREFAB PRELIM PREP PRES PRV PSF PSI PSIA PSIG PT PVC P'IMT Q QTY R RCP RCP REINF REM REQD RET REV ROW RPM RS RT s SAN SCH SCH EM SID SEC SECT SF SHT SLTD SN soc SPA SPEC so SS STA STD STIR STL STLG STOR SUSP SW SWPPP SY ABBREVIATIONS NORTH, NMRAL NOT APPLICABLE NORMAUY CLOSED NEGATIVE NORMAUY OPEN NUMBER NOMINAL NOMINAL PIPE SIZE NET POSITTVE SUCTION HEAD NATIONAL PIPE lHREAD NON-RISING STEM NOT TO SCAILE OPERATIONS AND MAINTENANCE ON CEl'ITER OUTSIDE DIAMETER OUTSIDE FACE OVER FL Ow OPENING OPTIONAL ORIGINAL OllfLET OVERHANG OPEN WEBBED STEEL JOISTS OUNCE PIJMP ACTUATOR, PNEUMATIC PARAUEL POINT OF CURVE. PRECAST PORTLAND CEMENT CONCRETE POUNDS PER CUBIC FOOT PERCENT PEDESTAL PENETRATION PERFORATED PERMANENT PERPENDICULAR PHASE POINT OF ltm'RSECTION PLATE, PROPERTY LINE PROGRAMMABLE LCJGIC CONTROLLER PNEUMATIC PANEL PREFABRICATED PRELIMINARY PREPAIRE PRESSURE VALVE. PRESSURE RELIEF OR REDUCING POUNDS PER SQUAIR[ FOOT POUNDS PER SQUARE INCH POUNDS PER SQUARE INCH ABSOLUTE POUNDS PER SQUARE INCH GAUGE POINT. POINT OF TANGENCY POLYVINYL CHLORIDE PAVEM ENT RATE OF FLOW QUANTITY RADIUS RECEPTICLE PIPE. REINFORCED CONCRETE REINFORCE/REINFORCED REMOVE REQUIRED RET>JNING REVISION RIGllT OF WAY REVOLUTIONS PER MINllfE RISING STEM RIGllT SOUTH SANITARY SCHEDULE SCHEMATIC DRAIN STORM SECONDARY, SECONDS SECTION SQUARE FOOT /FEET SHEET SLOTTED SNOW LOAD SLAB ON GRADE SPACING SPECIFICATION SQUARE STAINLESS STEEL STATION, STAIR STANDARD STIRRUP STEEL STOPLCJG STORAGE SUSP ENDED WATER. SERVICE STORMWATER POLLUTION PREVENTION PLAN SQUARE YARD WARNING SYM SYMM SYS T&B TBM TOH TEMP TK TMTR TO OPNG TOB TOC TOCMU TOCOL TOD TOF TOG TOL TOM TOP TOPO TOS TOW TP TYP USC UFC UG UHMW ULT UNO UPC UPS UTIL v VA VAC VAR VC voe VEL VERT VFD VOL VPC VPI VPT I/SD w W/ W/O WLD ws WT WWF XMFR XSEC YD 0 1/2 1 ---I IF THIS 84R DOES NOT MEASURE 1 ~ THEN ORAWlNG IS NOT TO SCALE. SYMBOL SYMMETRICAL SYSTEM TOP AND BOTTOM TEMPORARY BENCHMARK TOTAL DYNAMIC HEAD TEMPORARY TANK lHERMOMETER TOP OF OPENING TOP OF BANK TOP OF CONCRETE TOP OF CMU TOP OF COLUMN TOP OF OUCT TOP OF FOOTING TOP OF GRATING TOLERANCE TOP OF MASONRY TOP OF PLATE/PIPE TOPCJGRAPHIC TOP OF SLAB/STEEL TOP OF WALL TELEPHONE POLE TYPICAL UNIFORM BUILDING COOE UNI FO RM FlRE CODE UNDERGROUND ULTA HIGH MOLECULAR WEIGHT ULTIMATE UNLESS NOTED OTHERWISE UNIFORM PLUMBING CODE UNINTERRUPTED POWER SUPPLY UTILITY VALVE, VAULT, VENT, VOLT(S) VOLT AMPERE VACUUM, VOLTS ALTERNATING CURRENT VARIES, VARIABLE VERTICAL CURVE VOLTS DIRECT CURRENT VELOCITY VERTICAL VARIABLE FREOUENCY DRl\IE VOLUME VERTICAL POINT OF CURVATURE VERTICAL POINT OF INTERSECTION VERTICAL POINT OF TANGENCY VARIABLE SPEED DRIVE WEST. WIRE. WASTE WITH WITHOUT WELDED WATER SURFACE, WATER SUPPLY WEIGllT, WATERTIGllT WELDED WIRE FABRIC TRANSFORMER CROSS SECTION YARD MCMILLEN, LLC 1401 SHORELINE OR. SUITE 100 BOISE, ID 83702 OFFlCE: 208.~2.4214 FAX: 208.342.4216 GENERAL NOTES: 1. SCOPE OF WORK : THESE DRAWINGS WERE DEVELOPED AS PART OF A FEASIBILITY STUDY FOR ALTERNATIVES TO DELIVER POWER SUPPLY TO THE CITY OF AJ<UTAN FROM LOUD CREEK. THE INFORMATION PRESENTED WITHIN THESE DRAWINGS IS CONSIDERED CONCEPTUAL AND INTENDED FOR GENERAL PRESENTATION OF ALTERNATIVES. 2. THESE ABBREVIATIONS APP LY TO THE ENTIRE SET OF CONTRACT DRAWINGS. 3. LISTING OF ABBREVIATIONS DOES NOT IMPLY ALL ABBREVIATIONS ARE LISED IN THE CONTRACT DRAWINGS. . 4. ABBREVIATIONS SHOWN ON THIS SHEET INCLUDE VARIATIONS OF THE WORD. FOR EXAMPLE, •Moo• MAY MEAN MODIFY OR MODI FlCATION: "INC" MAY MEAN INCLUD ED OR INCLUDING; "REINF• MAY MEAN EITHER REINFORCE OR REINFORCING. 5. SCREENING OR SHADING OF WORK IS USED TO IN DICATE EXISTING COMPONENTS OR TO DE-EMPHASIZE PROPOSED IMPROVEMENTS TO HIGHLIGHT SELECTED TRADE WORK. REFER TO CONTEXT OF EACH SHEET FOR USAGE. PLAN SHEET SYMBOLS PLAN NORTH ARROW INDICATIEs~N DIRECTION OF SCALE : 1/2"= 1'-0" SECTION IDENTIFICATION (1) SECTION CUT ON DRA\\1NG C102: L ~~f~~N -~DRAWING WHERE SECTION IS DRAWN (2) ON DRAWING C1Q3 lHIS SECTION IS IDENTIFIED AS: d SECTION LETIER C:l="CTION A ~S~C=AL~EL:Ll~/~2~._'--,.-_-0~.----f...,.~C~D::-13 \.._DRA\\1NG WHERE DETAIL OCCURS' DETAIL IDENTIFICATION (1) DETAIL CAU-OIJT ON DRAWING C102: ~G~~~R 1 C102 / ----- I I DRAWING l'IHERE I I DETAIL IS SHOWN I I , _____ / (2) ON DRA\\1NG C103 lHIS SECTION IS IDENTIFlED AS: DETAIL NUMBER DETAIL 1 _S_C_A-LE_;_l_/_2 __ =-1-'--o~----......,~r~""'oJ:-1 \._DRAWING WHERE DETAIL OCCURS• 'NOTE: IF PLAN AND SECTION (OR C£TAIL CALL-OUT AND DETAIL) ARE SHOWN ON SAME DRAWING. DRAWING NUMBER IS REPLACED BY A LINE. STANDARD DETAIL IDENTIFICATION (1) DETAIL CALL-OIJ T ON PLAN OR SECTION: STANDARD DETAIL NUMBER l----------c_11Y __ o_F_A_K_UT_A_N_._A_LA_s_K_A ________ --1 DES IG NED D.AXNESS DRAWING LO UD CREEK HYDROPOWER DEVELOPMENT ~----------------------------------! DRAWN R. GUERRERO 2 STAN DARD ABBRE~ATIONS AND SYMBOLS CHECKED M. Mci.AILLEN ISSUED DATE 6/1 /tl SCALE: NONE 6/1 /11 MM CONCEPTUAL DESIGN DRAWINGS J/JO 10 DA CONCEPTUAL DESIGN DRAWINGS 2/26/10 DA CONCEPTUAL OESIGN ORAWINGS DATE BY DESCRIPTION \ J ~ FUTURE AKUTAN HARBOR 100 200 300 400 PROPOSED TRANSMISSION LI NE ROUTE SEE NOTE 4 LOCATION Of ·"'-POWERHOUSE LANDING AREA ~ I. TOPOGRAPHY OBTAINED FROM UNIMAK OlMORANGLE WAS USED FOR TliE CONCEPTVAL D£SICN STUDY. SllE SPECIFIC TOPOGRAPHIC DATA WAS NOT DMLOPED FOR TliE CONCEPTUAL DESIGN STUDY. 2 . LOUD CREEK HYOROPOWER OMLOPMENT SITE IS LOCATED SOVlli Of THE COY Of AKUTAN . 3. Tli£ CONCEPTUAL DESIGN ST\JllY IDENTFlEO ANO E.VALUATEO TWO ALTERNATl'IES FOR HYDROPOWER OE.VEl.OPMENT AT LOUD CREEK. THESE ALTERNATl'IES ARE IUUSIRATEO ON THE FOLLOWING DRAWINGS: -BAS£ CASE: owe 4, s -ALTERNATM'. 1: OWG 4, 6 4 . SE.VERAL OPTIONS WERE E.VALUATEO FOR A POWER TRANSMISSION LINE FROM THE LOUD CREEK HYOROPOWER OE.VELOPMENT SITE TO THE LOAD DEMAND SITES INCLUDING CITY Of AK UTAN, TRIDENT. ANO THE FUIVRE AKUTAN HJR BOR FACILmES. VARIOUS ROUTING OPTIONS AND CONSTRUCTION METHODS AR E PRESENTED WITlilN THE CONCEPTUAL DESIGN REPORT. THE GENERAL ROUTE AROUND THE WEST ENO Of AKUTAN HARBOR WAS THE PRIMARY TRANSMISSION ROl/nNG CONSIDERED. ----....._ .....-. HlGH -'-.../TIDE LINE ~-:;,,~ _ __,F\ ,...1oo~Oo l ,,do---~ . '. ,:~~ J;\;;;~SE:-~ST ' """ ~RK DAM SITE ( \ ~-----VlEST FORK LOUD~· CREEK WATERSHED . ~ BOUNDARY 0.19 SO I.ti ' .. CJ ' 700 WARNING ------,,, PROPOSED EAST FORK DAM SITE I I I 0 1/2 w MCMILLEN, LLC IF MS BAA OOES NOT MEASURE 1'" THEN DRAWIN G IS NOT TO SCAL.£. 1401 SHORELINE DR. SUllE 100 BOISE. ID 83702 omcE: 208.342.4214 FAX: 208.342.4216 '<: '\ "-/' -~-"-/ "-100 '\ I 'O<§l / 900 101XY' 1cP \ -..... "- I ........ -- / CllY OF AKUTAN, ALASKA DESIGNED D. AXNESS 1----------------------------i ~-----L_o_u_o_c_R_E_EK_H_Y_D_R_o_P_o_w_rn_o_EV_E_Lo_P_M_E_N_r ____ ---1 oRAwN R. wooD GE NERAL SIT E PLAN CHECKED M. McMILl EN ISSUED DATE 6 /1 /11 DRAWING 3 SCALE: AS NOTED WORK ITEMS: SCOPE OF WORK : THESE DRAWING S WERE DEVELOPED AS PART OF A CONCEPTUAL DESIGN STUDY FOR ALTERNATIVES TO DELIVER POWER SUPPLY TO THE CITY Of AKUTAN FROM LOUD CREEK. THE INFORMATION PRESENTED ON THE DRAWINGS IS CONSIDERED CONCEPTUAL AND IS INTEN DED FOR GENERAL ILLUSTRATION AND COMPARISON OF ALTERNATIVES . THE ALTERNATIVES WERE DEVELOPED BASED ON EXISTING AVAILABLE DATA. SITE SPECIFIC STUDIES TO OBTAIN GEOTECHNICAL AND TOPOGRAPHICAL DATA WERE NOT OBTAINED FOR THE CONCEPTUAL DES IGN STUDY, BUT WILL BE REQUIRED If THE SELECTED ALTERNATIVE IS ADVANCED TO FINAL DESICN. SITE ACCESS: 1. CONSTRUCT A CONSTRUCTION ACCESS DOCK. 2. CONSTRUCT A CONSTRUCTION ACCESS ROAO ALONG THE PIPELINE PATH TO THE DAM SITE. 3. STAB ILIZE TH E ROAD . 4. PROVIDE SECURITY FENCING AND SIGNAGE POWERHOUSE CONSTRUCTION 1. CLEAR AND GRUB THE POWERHOUSE SITE 2. EXCAVATE POWERHOUSE SITE TO BEDROCK 3. ANCHOR FOUNDATION SLAB TO BEDROCK 4 . CONSTRUCT SlAB 5. DELIVER AND INSTALL THE POWERHOUS E BUILDING AND EQUIPMENT 6. CONNECT TO PENSTOCK PIPELINE 7 . CONNECT TO POWER TRANSMISSION TRANSFORMER 8. STARTUP AND TESTING PENSTOCK PIPELINE CONSTRUCTION 1. DELIVER HOPE PIPE, VALVES AND APPURTENANCES 2. WELD HOPE PIPE TOGETHER 3. PROCESS OR flAUL -IN BACKFILL MATERIAL 4. CONSTRUCT THRUSTBLOCK AT POWERHOUSE 5. EXCAVATE TRENCH AND INSTALL PIPELINE 6. MOUND BACKFILL OVER PIPE DAM CONSTRUCTION 1. PROVIDE WATER CONTROL AT DAM SITE 2. CLEAR AND GRUB VEGETATION AND DISPOSE OF PROPERLY 3. DELIVER SEEPAGE BARRIER MATERIALS 4. EXCAVATE SOIL TO BEDROCK (EST. LESS TflAN 10-FT DEEP) 5 . CONSTRUCT SEEPAGE BARRIER AND FOUNDATION PREPARATION 6 . CONSTRUCT PENSTOCK INTAKE AND OUTLET STRUCTURE FOUNDATIONS 7. CONSTRUCT DAM 8. CONSTRUCT OUTLET AND PENSTOCK INTAKE STRUCTURES 9. CONSTRUCT SPILLWAY 10. INSTALL MONITORING ANO CONTROL EQUIPMENT PROJECT DES IGN NOTES: WATERSHED CHARACTERISTICS 1. GEOLOGY OF THE WATERSHED IS DESCRIBED AS: COLLUVIUM, TEPHRA. AND VOLCANIC ROCK 2. GEOTECHNICAL EVALUATION IS RECOMMENDED BEFORE FINAL DESIGN 3. VEGETATION IN THE WATERSHED IS: NATIVE TUNDRA 4. APPROXIMATE SLOPES IN THE WATERSHED ARE: 10% -70% 5. AVERAGE MINIMUM DAILY TEMPERATURE JS: 26"F 6. AVERAGE MAXIM UM DAILY TEMPERATURE IS: 54'f HYDROLOGY (REGIONAL REGRESSION EQUATIONS) 1. 50% RECURRENCE PROBABILITY FLOW: 77 CFS 2. 1 % RECURRENCE PROBABILITY FLOW: 240 CFS 3. STREAM GAGE DATA IS RECOMMENDED BEFORE FINAL DESIGN HYDRAULICS 1. OUTLET STRUCTURE CAPACITY: 80 CFS 2. PRELIMINARY SPILLWAY CAPACITY: 712 CFS 3. PENSTOCK INTAKE CAPACITY: EAST FORK = 9 CFS WEST FORK = 6 CFS EMBANKMENT DES IGN I. COMPACTED EARTHFILL DAM WITH A SEEPAGE CONTROL SYSTEM. COMPACTION IS EXPECTED TO BE 95% OF MAXIMUM STANDARD DENSITY (STANDARD PROCTOR) AS DEFINED BY THE ASTM STANDARD 696-07E-STANDARD TEST METHODS FOR LABORATORY COMPACTION CHARACTERISTICS OF SOIL USING STANDARD EFFORT. 2. EMBANKMENT DEPTH IS 1 O~ LARGER THAN DESIGN DEPTH TO ACCOUNT FOR EXPECTED SETTLEMENT. 3. SEEPAGE PROTECTION PROVIDED BY A DRAINAGE DIAPHRAGM AND PROTECTED DRAIN OUTLET 4 . COLD WEATHER CONSIDERATIONS WILL BE INCLUDED IN FINAL DESIGN. SPILLWAY AND OUTLET DESIGN 1. OUTLET IS A DROP INLET PIPE OUTLET. THE OUTLET IS DESIGNED TO CONVEY WATER IN THE ANNULAR SPACE BETWEEN THE OUTLET RISER PIPE AND A LARGER PIPE FUNCTIONING AS A DEBRIS AND ICE RACK. THE VELOCITY OF THE WATER IN THE ANN ULAR SPACE BETWEEN THE TWO PIPES WILL BE LI MITED TO TWO-FEET PER SECOND AT THE 50% RECURRENCE PROBAB ILITY DESIGN FLOW. THE DROP INLET RISER PIPE WILL BE CONSTRUCTED OF TWO VERTICAL CONCENTRIC PIPES WfTH CONCRETE CAST BETWEEN THEM. THE OUTER "TRASH RACK" PIPE WILL BE CORRUGATED 14-GAUGE ALUMIN IZED STEEL PIPE. 2. THE SPILLWAY WILL BE CONSTRUCTED IN UNDISTURBED EARTH ADJACENT TO THE COMPACTED FILL OF THE DAM . THE SPILLWAY WILL BE PROTECTED WfTH RI PRAP OVER A GEOTEXTILE TO PREVENT PIPING FAILURE. PENSTOCK DES IGN 1. THE PENSTOCK/PIPELINE WILL BE DESIGNED TO CONVEY 3.5 CFS IN A 16-INCH HOPE PIPELINE. THE RES ULTING VELOCITIES ARE APPROXIMATELY FEET PER SECOND (FPS) FOR THE EAST FORK 16"~. 4.3 FPS FOR WEST FORK. 6 .5 FPS FOR 18 "~ COMBINED. 2. MOUND BACKFILL OVER PIPE IF NECESSARY TO PROVIDE SUFFICIENT COVER. 3 . INSTALL PENSTOCK APPURTENANCES 4. PRESSURE TEST 5. CONNECT TO POWERHOUSE 6. STARTUP AND TESTING A\ 6/1 /1 1 MM CONCEPTUAL DESIGN DRAWINGS Jl.. 3/30/10 DA CONCEPTUAL DESIGN DRAWINGS &,, 2/26/10 DA CONCEPTUAL DESIGN DRAWINGS REV DATE BY DESCRIPTION DRAINAGE AREA 380 AC AVERAGE STREAM SLOPES: 10% FREQUENCY PEAK INFLOW Q; PHYSICAL DATA PRINCIPAL .se!WIAr 50% 80 CFS SURFACE AREA POND ~ 5 AC MAXIMUM DEPTH OF WATER = 8 FT AUXILIARY ~ 1% 240 CFS EFFIECTIVE FILL HT 10 FT (LOW POINT ON CENTERLINE TO AUXILIARY SPILLWAY) SEDIMENT STORAGE: BELOW CREST ~ 1 AC FT ELEV: OUTLET = 4 95, SPILLWAY = 496, SETTLED FlLL • 500 WARNING 0 1/2 1 Q I If lHIS BAR DOES NOT MEASURE 1 • THEN DRAWING IS NOT TO SCALE. MCMILLEN, LLC 1401 SHORELINE DR. SUITE 100 BOISE, ID 63702 OFFlCE: 208.342.4214 FAX: 206.342.4216 l----------c_1TY __ o_F_A_K_u_TA_N_._A_LA_S_K_A ________ __, DESIGNED 0. AXNESS DRAWING LOUD CREEK HYDROPOWER DEV ELOPMENT 1-~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~-i DRAWN R. WOOD 4 DESIGN CR ITER IA CHECKED M. McMILLEN ISSUED DATE 6/1 /11 SCALE: AS NOTED 6/1/11 3/30/10 2/26/10 DATE WEST FORK LOUD\ CREEK WATERSHED BOUNDARY -·· -- MM CONCEPTUAL DESIGN DRAWINGS DA CONCEPTUAL DESIGN DRAWINGS DA CONCEPTUAL DESIGN DRAWINGS BY DESCRIPTION ' \ --- -~ POWER TRANSMISSION LINE TO CITY OF AKUTAN ANO NEW HARBOR FACILffiES. SEE DRAWING 3 CLIMBING TURN CLIMBING TURN i:; I rtt : v; ' &: \. ~; \,\ ~~~: ~/ -. I . . I /'./\ ( \ \ \ "-LANDING AREA -.....: " I \ WARNING L-#2 If TiilS BAA DOES NOT MEASURE 1 • THEN DRAWING IS ~OT TO SCALE. I I \ \ \ --........ ....... \ \§I "" u· I o\ \ g: I ~I \~\ ~: I I \ : I \ \ : / I I I \ ~PROPOSED 1 s"e r PENSTOCK IPE I i \ ·~-::::::===~ "-.. rHIGH ' ' I llOE LINE ' 500 PROPOSED SPILLWAY ' ' ---....... ' ' ' ·, ,."/.'~,-------- ' ------------ ,,,~.-?:'-- - -- - -~ \~\ , -7~ '-.., JEAST FORK LOUD CREEK \ ~~"" ) 1 PROPOSED '-.., WATERSHED BOUNDARY ~ \.-.7"· ''-. 7 EAST FORK TOTAL AREA 0.59 SO Ml ~,., ·,.. DAM SITE '· ' / / / / . ' PROPOSED ' OUTLET \ STRUCTU RE. \ \ \ / \ \ ) I \ SITE PLAN SCALE: 1 "= 200' ~ 1. THE RESERVOIR AREA IS ESTIMATED AT APPROXIMATELY 1 ACRES WITH A STORAGE VOLUME Of LESS THAN 1 0 ACRE FT. THE DAM HEIGHT IS LESS THAN 10 FEET. THE RESERVOIR WILL BE OPTll.l lZEO IN SIZE DURING FINAL ENGINEERING WITH NEW SITE SPEC IFIC TOPOGRAPH IC MAPPING. 2. TOPOGRAPHY OBTAI NED FROM UNIMAK OUADRANGl.E WAS USED FOR THE CONCEPTUAL DESIGN STUOY. SITE SPECIFIC TOPOGRAPHIC DATA WAS NOT DEVELOPED FOR THE CONCEPTUAL DESIGN STUDY. 3 . 1HE EAST FORK DAM LOCATION IS APPROXIMATE. THE ORIENTATION, HEIGHT, AND APPURTANCES LOCATION WOULO BE OPTIMIZEO DURING FINAL ENGINEERI NG BASED ON SITE SPECIFIC CEOTECHNICAL AND TOPOGRAPHIC MAPPING. 4 . PENSTOCK ROUTING IS APPROXIMATE BASED ON AVAILABLE TOPOGRAPHIC MAPPING. 1HE ILLUSTRATED ROUTING WAS DEVELOPED TO DETERMINE PENSTOCK LENGni , MATERIAL OUANTlllES. AND OVERALL CONSTRUCTION APPROACH AS WELL AS AVAILABLE OPERATING HEAD FOR 1HE POWERHOUSE. 5 . SEE DRAWING 4 FOR A SUMMARY OF THE GENERAL DESIGN CRITERIA FOR THE DAI.I, PENSTOCK, POWERHOUSE, ANO LOADING DOCK FACILITIES. 6 . THE NEW ROAD WILL PROVIDE ACCESS TO THE PENSTOCK AND DAI.I OR OPERATION ANO MAINTENANCE. THE ROUTING SHOWN IS APPROXIMATE BASED ON THE AVAILABLE TOPOGRAPHIC MAPPING. ACCESS ROAD IS SIZED FOR ATV VEHICLES. ------------ DRAWING Cl1Y OF AKUTAN, ALASKA DESIGNED 0 . AXNESS 1--~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~---t MCMILLEN, LLC 1401 SHOREUNE DR. SUITE 100 BOISE, ID 83702 OFFICE: 208.342.4214 FAX: 208.342.421 6 LOUD CREEK HYDROPOWER DEVELOPMENT 1--~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~--t DRAWN R. WOOD SITE PLAN BASE CASE CHECKED M. McMILLEN ISSUED DATE 6/1 /11 5 SCALE: AS NOTED -·· - 6/1/11 MM CONCEPTUAL DESIGN DRAWINGS 3/30/10 DA CONCEPTUAL DESIGN DRAWINGS 2/26/1 D DA CONCEPTUAL DESIGN DRAWINGS WEST FORK LOUD\ CREEK WATERSHED BOUNDARY --- DATE BY DESCRIPTION - ' ' --.- ~ ~ ~ 1. THE RESERVOIR AREA IS ESTIMATED AT AP PROXIMATELY 1 ACRES WITH '-.. LANDING AREA A STORAGE VOLUME OF LESS THAN 10 ACRE FEET. THE OAt.t HEIGHT IS LESS THAN I 0 FT. THE RESERVOIR WILL BE OPTIMIZED IN SIZE DURING FINAL ENGINEERING WITH NEW SITE SPECIFIC TOPOCRAPHIC MAPPING. POWER TRANSMISSION LINE TO CITY OF AK UTAN ANO NEW HARBOR FACILITIES, SEE DRAWING 3 CLIMBING TURN " " PROPOSED ACCESS ROAD (6' WIDE) \ \ \ WARNING 6 1/2 If lli!S BAR DOES NOT MEAS URE 1 • THEN DRAWING IS NOT TO $CAL£. I I -- PROPOSED POWERHOUSE TAILRACE \ \ \ \ .~ l§ I o::· <.)' I ol \ :>. 5 · ;i :5: l --" " ' rHIGH ', I TIDE LINE ' ' ' '\~I . 18"~ PENSTOCK %PIPE INTERSECTION _,,,---soo SEE NOTE 8 / ( , I _/ \ :~PROPOSED 16"~ _/ ~ PENSTOCK PIPE \ \ '~----- PROPOSED SP ILLWAY --" " ........ " " --------------- PROPOSED PENSTOCK INTAKE ~\ ,)Y -------------~ ~-~··?~) 1 PROPOSED '-.. '-.. J~kis~~~ ~U~N~EK , 7-. . 7 EAST FORK TOTAL AREA 0.59 SO Ml •• '· ._ DAM SITE ' ' / I / / / / SITE PLA N SCALE: 1 "= 200' PRO PO~~ OUTLET w \ STRUCTURE \ ' '\ \ \ \ \ \ ) 2. TOPOGRAPHY OBTAINED FROM UNIMAK QUACRANGLE Wl>S USED FOR THE CONCEPTUAL DESIGN STUDY. SITE SPECIFIC TOPOGRAPHIC DATA Wi>S NOT DEVELOPED FOR THE CONCEPTUAL DESIGN STUDY. 3. THE WT AND WEST FORK DAM LOCATIONS ARE APPROX IMATE. THE ORIENTATION, HEIGHT, ANO APPURTANCES LOCATION WOULD BE OPTIMIZED DURING FINAL ENGINEERING BASED ON SITE SPECI FIC GEOTECHNICAL AND TOPOGRAPHICAL MAPPING. 4. PENSTOCK ROUTING IS APPROXIMATE BASED ON AVAILABLE TOPOGRAPHIC MAPPING. THE ILLUSTRATED ROUTING Wi>S DEVELOPED TO DETERMINE PENSTOCK LENGTH, MATERIAL QUANTITIES, ANO OVERALL CONSTRUCTION APPROACH AS WELL AS AVAILAB LE OPERATING HEAD FOR THE POWERHOUSE. 5. SEE DRAWING 4 FOR A SUMMARY OF THE GENERAL DESIGN CRITERIA FOR THE DAM. PENSTOCK, POWERHOUSE, AND LOADING DOCK FAC ILITIES. 6. ALTERNATNE 1 CONSISTS or THE FACILITIES PROPOSED FOR THE BASE CASE PLUS A NEW DIVERSION DAM ANO PENSTOCK LOCATED ON THE WEST FORK OF LOUD CREEK. ALTERNATIVE 1 Wi>S DEVELOPED TO PROVIDE ACOITIONAL FLOW TO THE POWERHOUSE TO INCRWE THE OVERALL ANNUAL GENERATION. 7 . THE NEW ROAD WILL PROVIDE ACCESS TO THE PENSTOCK AND DAM OR OPERATION AND MIANTENANCE. THE ROUTING SHOWN IS APPROXIMATE BASED ON THE AVAILABLE TOPOGRAPHIC MAPPING. ACCESS ROAD IS SIZED FOR ATV VEHICLES . 5 . 16"~ PENSTOCK FROM WEST FORK DIVERSION DAM WILL TIE INTO THE WT FORK PENSTOCK. FULL ISOLATION VALVES WILL BE PROVIDED . -----" ------ DRAWING MCMILLEN, LLC 1-----------c_1TY __ o_F_A_K_u_TA_N_._A_LA_s_K_A ________ _, oEslGNm D. AXNESs 1401 SHORELINE DR. SUITE too BOISE. ID 83702 OFFJCE; 206.342.4214 FAX: 208.342.4216 LOUD CRE EK HYDROPOWER DEVELOPMENT !-~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~--; DRAWN R. WOOD SITE PLAN ALTERNAT IVE CHECKED M. McMILLEN ISSUED DATE 6/1 /11 6 SCALE: AS NOTEO PEN STOCK INTAKE VALVE VAULT II PENSTOCK TO~ : : POWERHOUSE "I I I I I I u __J EXISTING SLOPE 6/1/11 MM CONCEPTUAL DES IGN DRAWINGS 3/30/10 DA CONCEPTUAL DES IGN DRAWINGS 2/26/10 DA CONCEPTUAL DESIGN DRAWINGS I I I I I I I I I I I I II II II II L 200'± 1YPICAL DI VER SION DAM CONC EPT PLAN SCALE: NTS OUTLET STRUCTURE RISER EL-495 CONCRETE BASE DATE BY DESCRIPTION CONTOUR LINES, TYP APPROACH CHANNEL GRADE 53 DIRECTION Of FLOW 12' LEVEL SECTION CREST ELc496' RIPRAP SPILLWAY PROTECTION OUTLET GRADE 10% 1. POND CREST ELEVATION IS ASSUMED TO BE 500-FT ABOVE MEAN SEA LEVEL (BASED ON THE UNIMAK A-6 GEOREFERENCED PDF USGS TOPOGRAPHICAL MAP). 2. ELEVATIONS AND LENGTHS SHOWN ON THESE CONCEPTUAL DESIGN PLANS ARE BASED UPON THE ASSUMED DAM CREST ELEVATION OF 500 -FT. 3. FlELO OBSERVATIONS OCCURRED DURING A OCTOBER 24, 2009 FIELD VISIT . THE GROUND SURFACE WAS COVERED WITH 12 TO 16 INCHES OF SNOW. 4 . TOPOGRAPHIC INFORMATION (A GROUND BASED SURVEY OR A GROUND TRUTHEO LIOAR SURVEY) WILL BE COLLECTED PRIOR TO FlNAL DESIGN AND CONSTRUCTION OF THE DAM, PIPELINE AND HYDROPOWER PLANT AND POWERHOUSE. 5. THE PLANS MUST BE UPDATED AND VER IFIED AFTER THE DATA IS COLLECTED. 6. THE DRAINAGE AREA AND POOL AREA MUST BE SURVEYED IN ADDITION TO THE AREAS WHERE CONSTRUCTION WILL OCCUR. THESE AREAS 00 NOT NEEO THE PRECISION Of SURVEY INFORMATION COLLECTED IN THE VICINl1Y OF THE OAM, PIPELINE, ROAD AND POWERHOUSE. HOWEVER, THE INFORMATION IS IMPORTANT IN THE DESIGN AND MODERATION Of THE RESERVOIR ANO POWERHOUSE. PROFIL E ON CENTERLINE OF SP ILLWAY DIRECTION OF FLOW 13 GRADE TOP Of DAM EL=SOO' SEEPAGE BARRIER (SHEETP ILE OR GROUT) ---------.,,,_ CUTOFF TRENCH/ ~ 1 "' 'f. I s' SCALE: NTS DRAINAGE DIAPHRAGM / / _J, _,(_ 1 I SECTI ON ~ OF OU TLET STR UCTURE WARNING 6 1/2 If THIS BAR DOES NOT MEASURE 1 • THEN DRAWING IS NOT TO SCALE:. SCALE: NTS MCMILLEN, LL C 1.\01 SHORELINE DR. SUITE 100 BOISE. ID 83702 OFFICE: 208.342.4214 FAX: 208.342.4216 PIPE OUTILET EL-489.4 -----------1 -----~ w OUTLET CHANNEL \;<· °" '\' EXISTING g ;,, GROUNOLINE ED 1----------C-JTY __ o_F_A_K_u_r _A_N_. _A_LA_s_K_A _________ -; DES IGNED D. AXNESS DRAWING 7 CHECKED M. McM ILLEN LOUD CREEK HYDROPOWER DEVELOPMENT 1-----------------------------------!0RAWN R. WOOD DAM TYP ICAL PLAN AND SEC TIONS ISSUED DATE 6 /1 /11 SCALE: AS NOTIEO /CATWAf.K FOR TRASHRACK AND AIR-VENT SCREEN ACCESS TRASH RACK I I I I I I I I I --SZ NORMAL OPERATING ( -----_/I ...___ -POOL EL 495± ...___ VALVE VA ULT ~Y-...___ t-0...___ ----PENSTOCK ---INSTAf.L NEW-\ INTAKE ---~ --__ RESILIENT ---v ...___ --~ --_WEDGE VAf.VE ......_ . --""~ml----...___ --POWERHOUSE ...___ ~ ...___ \ :~'Iii ~ I ...___ SLUICE ISOLATION GATE ~ _/ ~ 16"~ PENSTOCK SLUICE PIPE LOUD CREEK - SECTION ALONG ~ OF PENSTO CK EB SCALE: NTS Cl1Y OF AK UTAN , ALASKA DRAWING WARN ING DESIGNED D. AXNESS MCMILLEN, LLC LO UD CR EE K HYDRO POWER DEVE LOPMEN T 8 0 1/2 , DRAWN R. WOOD IMHJ'"""li' H Ol SHORELINE OR. DAM ,f\ 6 /1/11 MM CONCEPTUAL DESIGN DRAWINGS IF THIS BAR DOES "IOT SUITE 100 OFFlCE; 2oa.342.42H CHECKED M. McM ILLEN ,f:!,. 3/30/10 DA CONCEPTUAL DESIGN DRAWINGS MEASURE \" 1l<EN DRAWING BOISE. ID 83702 F~: 208.342.4216 PEN STOCK SEC TI ON IS NOT TO SCALE. IA\ 2/26/10 DA CONCEPTUAL DESIGN DRAWINGS ISSUED DATE~_l _ REV DATE BY DESCRIPTION SCALE: AS NOTED EXISTING GROUNDLINE 6/1 /11 MM CONCEPTUAL DESIGN DRAWINGS 3/30/10 DA CONCEPTUAL DESIGN DRAWINGS 2/26/10 DA CONCEPTUAL DESIGN DRAWINGS DATE BY DESCRIPTION REVEGETATE CU T SLOPES TREAD WIDTH ACCESS ROAD CROSS-SECTIONS SCALE: NTS 6'-0" TREAD OUTSLOPE 3% v ' ACCESS ROAD CLEARING SCALE: NTS 6" OF¥.," MINUS ROAD MIX -/ IMPORTED GRAVEL OR APPROVEO CUT MATERIAL "' <·1 v ' .. WARNING 0 1/2 !liiiiiiiil! IF THIS BAA: DOES NOT MEASURE 1" THEN DAAWING IS NOT TO SCALE. MCMILLEN, LLC 1 '401 SHORElJNE DR. SUITE 100 BOISE. ID 8J702 OFFICE: 208.342.4214 FAX: 208.342.4216 ~ \ ELEVATION -------- ~ tn I i:l 0 0: u ------~1 ___ ----- PLAN SCALE: NTS CLIMBING TURN SCALE: (NTS) "' "-. SEE ACCESS ROAD CROSS , ~SECTIONS DETAIL. SPREAD CUT / ' ---------MATERIAL IN A THIN LAYER OVER \_,; EXISTING VEGETATION. SECTION CD 1----------C-ITY __ o_F_A_K_u_TA_N_,_A_LA_s_K_A ________ ---I DESIGNED D. AXNESS DRAWING LOUD CREEK HYDROPOWER DEVELOPMENT l-~~~~~~~~~~~~~~~~~~~~~~~~~~~~~-1 DRAWN R. WOOD 9 ROADWAY DETAILS CHECKED M. McMILLEN ISSUED DATE 6/1 /11 SCALE: AS NOTED \ \ \ \ ', \ \ , , PROPOSED ' , ' 0 ACCESS ROAD \ ~'t, '-----~ (6'WIDE) ... "--1 ., --~~=~'~==---;;;;;=48F======-------_J._ ' ~ I .. -··--E'Asr FOR ---o~- ','\ / __. .. ..--··-._K_l0UDCR[£1(-\ g "' "> ---\ , I , -___.,_ __ _ ~~ --.. --. 0 .r.j,":>\ .. · -.. "' \ uo cR£~.--"-··-. \ //, '. 1 6 "~ -.. _ ·-.. ·. EJ>S~fOR~'-o._.. ··-.. -.. _ .. /. ,/ ';._ • PENSTOCK PIPE -.. ~ .. -· · ~ _//~·'\ _ .. _.. ""' PROPO~ED . ;, . JOO PROPOSED POWERHOIJSE TAILRACE EAST FORK I 1 . DAM SITE I I I I I I I I 600 I ,.,,-EAST FORK LOUD V CREEK WATERSHED I BOUNDARY I I "' / f- l I I I I "'-HIGH I I TIDE LINE / I loo I I I 600 EAST FORK DAM 500 JOO 16"~ PENSTOCK PIPE (BURIED W/ AT LEAST J-f'T OF GROUND COVER) EAST FORK LOUD CREEK PENSTOCK PLAN SCALE: 1·-150' EXISTING GROUND I / / PROPOSED DOCK LANDING STRUCTURE \_AKUTAN BAY\ POWER LINE POWER TRANSMISSION LINE TO CITY or AKUTAN AND NEW HARBOR FACILITIES 600 _o~_L __ ..__ ___________ __Ji...._ ___________ __1 _________________________ _!. ____________ ...1.......::~-..~~~~~~~~~~-~-0 l O+DO 15+00 20+00 25+DO JO+OO 35+00 40+00 EAST FORK LOUD CREEK PENSTOCK PROFILE SCALE: 1"= 150' WARNING CITY OF AKUTAN, ALASKA DES IGNED D. AXNESS 6/1/11 MM CONCEPTUAL DESIGN DRAWINGS 3/30/10 DA CONCEPTUAL DESIGN DRAWINGS 2/26/ 10 DA CONCEPTUAL DESIGN DRAWINGS DATE BY DESCRIPTION L-¥2 If THIS BAA DOES ~OT MEASURE 1 ~ THEN DRAWING IS NOT TO SCA!.£. MCMILLEN, LLC 1401 SHOREl.INE OR. SUllE 100 BOISE. ID 83702 orncE: 208.342.4214 FAX: 208.342.421 6 f--------------------------------1 LOUD CREEK HYDROPOWER DEVELOPMEN T 1--------------------------------;DRAWN R. WOOD PIPELINE PLAN, PROFI L E, AND DETAILS BASE CASE CHECKED M. McM ILLEN ISSUED DATE 6/1 /11 DRAWING 10 SCALE: AS NOTEO ~ 500 ~ lQ.Q._ 3QQ_ .!..22.... _o_ ·. *' \<:h. \\ ·.c: \'t ·. ("\ \~ .'Fo \ \ cRt.t.\I. .. -.. -··-. fORl'-LO\JO .. -·-.. ---~ .. -~S.!_. .. -··--··-··-.. 300 EAST FORK AND WE ST FORK LOUD CRE EK PEN STOCK PLA N SCAU:: 1 ·-150' 18"~ PENSTOCK PIPE_/ (BURIED W/ AT LfAST J-FT OF CROVND COVER) / / / / / / / / / ~/PROPOSED ""--v LANCING AREA PROPOSED DOCK LANDING \_ STRUCTU RE AKUTAN BAY\ POWER LINE POWER TRANSMISSION UNE TO CllY OF AKUTAN ANO NEW HARBOR FAC IUTIES - / / / OAM /WEST FORK /EXISTlNG GROUNO / 18"o PENSTOCK PIPE INTERSECTION (16+56) 16"o PENSTOCK PIPE (BUR IED W/ AT LEAST J-FT OF GROUND COVER) .._ _ _._ ____________ _._ ____________ _._ ____________ ..._ ____________ .._ ___________ --J.__..:;:::._ __ ~~~...i.--o _o_ 10+00 15+00 MM CONCEPTUAL DESIGN DRAWINGS DA CONCEPTUAL DESIGN DRAWINGS DA CONCEPTUAL DESIGN DRAWINGS BY DESCRIPTION 20+00 25+00 JO+OO EAST FO RK LOUD CREEK PENSTOCK PROFILE SCALE: 1"• 150' WAR NING 0 1/2 w If TlilS BAR OOE:S NOT MWURE 1 • THEN DRAWING IS NOT TO SCAI.£. MCMILLEN, LLC H Ol SHOR EUNE DR. SUITE 100 BOISE. 10 83702 OFFICE: 208.342.4214 FAX: 208.342.4216 35+00 5+00 10+00 15+00 WEST FOR K LOUD CR EEK PE NSTO CK PROFILE SCAI.£: 1·-150' CITY OF AKUTAN, ALASKA DESIGNED D. AXNESS !--------------------------------! LOU D CREEK HY DROPOWER DEVELOPMENT !-------------------------------!DRAWN R. WOOD PIPELINE PLA N, PROFILE , AND DETAI LS ALTERNAT IVE 1 CHECKED M. McMI LLEN ISSUED DATE 6/1 /1 1 20+00 DRAWING 11 SCAI.£: AS NOTED ~ll- . . 0 0 I I l:l g FTG: 2'-0" AC/DC PANEl.S 8"TTER IES PRE-ENGINEERED METAL BUILDING WAU I I I I l_j I I 32'-0" ROLL -UP DOOR MAN DOOR ~ 24" CONCRETE"'"\. SLAS '\_ L ____ J ____ L ...L.--------L - SWITCH GEAR AND CONTROL PANEL MM CONCEPTUAL DESIGN DRAWINGS DA CONCEPTUAL DESIGN DRAWINGS DA CONCEPTUAL DESIGN DRAWINGS BY DESCRIPTION FOUNDATION PLAN SCALE: J/6°= 1'-o· WARNING 0 1/2 -IF llilS BAA DOES NOT MEASURE 1 • UiEN DRAWING IS NOT TO SC.U:. PENSTOCK PRE-ENGINEERED METAL BUILDING WALL FTC: 2'-0" ® . - -0 """J I ___ J MCMILLEN, LLC 1401 SHORELINE DR. SUITE 100 BOISE, ID 83702 OFACE: 208.342.4214 F/.X: 208.342.4216 TURB INE INLET VALVE EXTERIOR PAVING OR FlNISH GRADE PER CML -- 0 I ;,. !$J T.0.F. .. 2·-0· T.O. SLAB : CONC SLAB SEE Pl.AN T.0 . SLAB VARIES EXTER IOR CONCRETE WALL FOOTING ® SCALE: 3/4" = 1·-0· T.O. SLAB EXTERIOR PAVING OR FINISH GRADE PER CML 1 /2" PREMOLDEO EXP. JT. TYP. 0 I -- 'o TAILRACE CHANNEL~ \'""'"'"\ I ;,. ~ -'-------~ I 2·-0 • I l$i T.O.F . .. : . . E?<TERIOR CONCRETE WALL FOOTIN G CD SCALE: J/4" = 1·-0· 1----------c_1TY __ o_F_A_K_u_r A_N_._A_LA_s_K_A ________ --1 DESIGNED D. AXNESs LOUD CREEK HYDROPOWER DEVELOPM ENT !--------------------------------!DRAWN R. WOOD POWERHOUSE FOUNDATION PLAN AND SECTIONS CHECKED M. McMILLEN ISSUED DATE 6/1 /11 CONC SlAB SEE PLAN DRAWING 12 SCALE: AS NOTED "' I 350 KW, 3/ 480/60 SYNCHRO NOUS GENERATOR 6/1/11 MM CONCEPTUAL DESIGN DRAWINGS J/J0/10 DA CONCEPTUAL DESIGN DRAWING S 2/26/1 0 DA CO NCEPTUAL DESIGN DRAWI NGS DATE BY DESCRIPTION r SHAFT CENTER LINE CANYON PEL TON TURBINE 0 0 14'-4" REF TURB INE GENERATOR PLAN @ SCALE: 3/ 4" • 1 '-o· 12 NEE DLE VALVE PIT TURBINE INLET CENTERLINE "' I .. 6'-9" WARNIN G 0 1/2 ........-MCMILLEN, LLC IF THIS BAR 00£5 NOT MEASURE 1 • THEN DRAWING IS NOT TO SCALE . 1401 SHOR ELINE DR. SUITE 100 BOISE, ID 83702 omcE: 208.342.4214 FAX: 208.342.4216 ,... I "' b I "N b I .... ~ I "N 0. l .... CANYON PEL TON TURB INE OR EOUAL SHAFT CENTERLINE TAILRACE WATER LEVEL . . SECTION SCALE: 3/4 " • 1·-0· .. NEEDLE VALVE PIT ED TURBINE INLET CENTERLINE FLOOR LEVEL O> I "N .., .I N 1-----------c _1TY __ o_F_AK_u_r_A_N_._A_LA_s_K_A ________ --1 DEsiGNm 0 . AXNEss DRAWING LO UD CREEK HYDROPOWER DEVELOPM ENT POWER HOUSE GENERATOR PLAN AND SECTION CH ECKED M. Mc MILLEN ISSUED DATE 6 /1 /11 13 SCALE: AS NOTED 2 7= 0 .,; 0 0 <t l11 2 b 0 0 gi ~ Ill 2 0 0 0 '° a 0 <t U'I ,. I ( wr:r.iu ~·'I I' , MM CONCEPTUAL DESIGN DRAWINGS DA CONCEPTUAL DESIGN DRAWINGS DA CONCEPTUAL DESIGN DRAWINGS BY DESCRIPTION oi-~ ..... , __ : .. l6~·'1'::l.ll 1 11l 1 w WARNING 0 1/2 IWiiijl! IF llllS BAA OOES NOT MEASUR E l" THEN DRAWINCi IS NOT TO SCAl.E . 155°4 3.0 00' \II W3S84 165°42 .000' W z 0 0 0 ·=" 0 o, · Aku~n _,_B,.,1,;aL&.11il..ut _____ _,__.., 1 r-·-i Vi , L; g,h+ IBANSMISSION LINE ROUTE OPTIONS· OPTION 1 -INSTA LL CABLE DIRECTLY ACROSS AKUTAN flARBOR fROM LOUD CREEK TO TflE DIESEL POWER flOUSE IN TflE CITY OF AKUTAN (APPROXIMATELY 0.9 MILES UNDERWATER). OPTION 2 -INSTAU. CABLE INSIDE PERIMETER OF AKUTAN H ARBOR FROM LOUD CREEK TO THE WEST SIOE OF IBIOENT FACILITIES. THE ROUTE CROSSES NORTH Of IBIDENT TflEN FOLLOWS TRAIL FROM EAST SIDE OF TRIDENT TO TflE DIESEL PO'A£R HOUSE IN TflE CITY Of AKUTAN (APPROXIMATELY 3.2 MILES UNDERWATER ANO 0. 7 MILES UNDERGROUND). # ~ 'I AKUTAN / ~DIESEL GENERATION POl'YUl HOUSE OPTION 3 -SAME ROUTE AS OPTIOH 2. EXCEPT TflE CABLE IS BROUGHT ASflORE AND ROUTED AROUND TflE PROPOSED HARBOR DOCK FACILITIES ON TflE WEST END OF AKUTAN HARBOR (APPROXIMATELY 3.1 MILES UNOERWA TER ANO 0.9 MILES UNDERGROUND). SECTIONALIZING EQUIPMENT WILL BE UTILIZED TO PROVIDE PO'A£R FOR THE PROPOSED FACILITIES. OPTION 4 -INSTALL CABLE INSIDE PERIMETER OF AKUTAN flARBOR FROM LOUD CREEK TO TflE LOCATION OF PROPOSED flARBOR DOCKING fl.CILITIES ON WEST END Of AKUTAN flARBOR, THEN UNDERGROUND ALONG PROPOSED ROAD FROM TflE PROPOSED DOCKING FACILITIES TO THE CITY Of AKUTAN (APPROXIMATELY 1.7 MILES UNDERWATER AND 2.6 MILES UNDERGROUND). SECTIONALIZING EQUIPMENT WILL BE UTILIZED TD PROVIDE POWER FOR THE PROPOSED FACILITIES. # ,/Akutan /""----ROUTE OPTION 1 # 00 05 l (•irulos 1-.. '. ,..._ ·-~-__......,,..__,-~,""--T--~-'-T ...J 01) 0 ~ I ii l 't.n. Mdr• ,.,~ .• 1i:d 'Nlfh Ti 11•, ''~~l(lf13 1~01"'tiaJ • ;o:"Q'tpl1)i •:W\"'Y notJnJ':Jgf:~r1,.,., 'lnftnpr.: TRANSMISSION LINE ROUTE OPTIONS MCMILLEN, LLC 14-01 SHORELINE OR. SUITE 100 BOISE, 10 83702 OFFICE: 208.342.4 214 FAX: 208.342.4216 J I OPTOIN 4A -ROUTING WOULD BEGIN AT TflE LOUD CREEK HYDRO PLANT. THEN ENTER AKUTAN HARBOR RUNNING UNDERWATER FOLLOWING THE PERIMETER OF TflE HARBOR VIA SUBMARINE CABLE TO TflE HARBOR F ACIUTIES L OCATED AT TflE WEST END OF AKUTAN HARBOR. (OVERALL LENGTH IS APPROX IMATELY 1.70 MILES). OPTION 5 -INSTALL CABLE FROM AKUTAN TO TRIDENT FACILITIES FOR TIE (APPROXIMATE LY 0.5 MILES UNDERGROUND). OPTION 6 -INSTALL CABLE UNDERGROUND (ROADLESS) FROM LOUD CREEK TO TflE LOCATI ON OF PROPOSED flARBOR DOCKING FACILITIES ON WEST END OF AKU TAN HARBOR, TflEN UNDERGROUND ALONG PROPOSED ROAD FROM TflE PROPOSED DOCKING FACILI TIES TO THE CITY OF AKUTAN (APPROXIMATELY 2.0 MILES ROADLESS UNDER GROUND AND 2 .6 MILES UNDERGROUND). SECTIONALI ZING EQUIPMENT \\Ill. BE UTILIZED TO PROVIDE POWER FOR THE PROPOSED FACILITIES. OPTION 6A -ROUTING WOULD BE COMPLETE LY OVERLAND IN THE UPLAND AREA TO TflE HARBOR FACILITIES LOCATED ON TflE WEST END OF TflE AKUTAN HARBOR. (OVERALL LENGTH IS APPROXIMATELY 2.0 MILES). v l/ -~---·----··-··----..,.-· ___ ..:._::;.__ ___ __,__,_ _________ -=;:=--=--.I.....--' t 6.5"4S 0011 ' "'I 165 -i 4 4 _('lC11')' W 155°4 ~.000' w WG.384 1 -5°~2.000' W CITY OF AKUTAN, ALASKA DESIGNED D. AXNESS 1-----------------------------------1 DRAWING LOUD CREEK HYDROPOWER DEVELOPMENT 1---------------------------------lDRAWN R. WOOD 14 TRANSMIS SION LIN E ROUTING OPTIONS CHECKED M. McMILLEN z 0 0 0 "' 0 0 "' ul ISSUED DATE 6/1 /11 SCALE: AS NOTED APPENDIX B COST ESTIMATES City Of Akutan-Loud Creek Hydro Option 1 Lo ud Creek to Akutan -Directly Crossing Harbor utilizing submarine cable only Assembly Section Cans w/ Elbows #2 cu 15 kV Submarine Cable (All Inclusive) #2 cu 15 kV kV URD Cable 4" HOPE Condu it w/ fittings Trench/Plow 50 % Rock T rench 50% Professional Services Engineering Construction Mgt. Equipment 04 cat w/p low Boom Truck Backhoe Pickup Skidsteer 4 wheeler wire equip undgrd 1 Crews of 4 men Room Board Qty 0 4752 0 0 600 600 Q!y 1 0 1 2 1 2 0 4 Weight Cost FRT diff 250 $2,000 $113 2 $5 $1 1 $5 $0 0 $0 $0 0 $0 $0 Onshore co nstruction duration Unit CosUunit 0.9 (mi) $4 ,000.00 0.9 (mi) $4 ,000.00 Professional Services Subtotal RenUmo Ext Rent Fue l $10,000 $1 ,667 $960 $3,500 $0 $0 $3,500 $583 $640 $1 ,800 $600 $1,280 $4,000 $667 $640 $1,000 $333 $320 $2,500 $0 $0 Total #days Per Day Total 5 $200 $4 ,000 Subtotal <2 > $11,690 Material Cost Hours $2, 113 24 $50 1.08 $6 0.015 $5 0.015 $0 0 .09 $0 0.27 4 men 12hr -#of days $3,600 $3,600 $7,200 Total $2 ,627 $0 $1 ,223 $1,880 $1,307 $653 $0 $7,690 Ext Hours 0 0 0 54 162 216 4 .5 Distance = Labor Rate = La bor Cost $3,960 $178 $2 $2 $15 $45 Subtotal 20% Contingency Subtotal <1> $ per mile 4 , 752 ft or 0.9 mile $165 per mh Lab & Mat Cost $6 ,073 $228 $8 $8 $15 $45 Subtotal $1 ,1 27,246 $225,449 $1,352,696 $1,502,995 Extended Total $0 $1 ,084,406 $0 $0 $8,910 $26,730 $1,120 ,046 Total <1>•<2> $1,364,386 June 8 , 2011 $1,244,496 $/mile City Of Akutan-Loud Creek Hydro Option 2 Loud Creek to Akutan -Fo ll owing the s horeline to Trident and onshore to Akutan Material Assembly Q!y Weight Cost FRT diff Cost Hours Section Cans w/ Elbows 6 250 $2,000 $113 $2 , 113 24 #2 cu 15 kV Submarine Cable (All Inclusive) 16896 $50 1.08 #2 cu 15 kV kV URD Cable 11088 1 $5 $0 $5 0.015 4" HOPE Conduit w/ fittings 73 92 1 $4 $0 $4 0.015 Trench/Plow 50% 1848 0 $0 $0 $0 0.09 Rock Trench 50% 1848 0 $0 $0 $0 0.27 4 men 12hr -#of days Profess i onal Services Unit Cost/unit Engineering 3.9 (mi) $4,000.00 $15 ,600 Constru ction Mgt. 3.9 (mi) $4,000 .00 $15,600 Professiona l Services Subtotal $31 ,200 Equipment Q!y Rent/mo Ext Ren t Fuel Total 04 cat w/plow 1 $10,000 $7 ,667 $4,416 $12,083 Boom Truck 0 $3 ,500 $0 $0 $0 Backhoe 1 $3,500 $2,683 $2 ,944 $5,627 Pickup 1 $1,800 $1 ,380 $2 ,9 44 $4 ,3 24 Skidsteer 1 $4,000 $3 ,067 $2 ,944 $6,011 4 wheeler 2 $1 ,000 $1 ,533 $1,472 $3 ,005 wire equip undgrd 1 $2 ,500 $1 ,917 $0 $1,917 Total $32,967 1 Crews of 4 men #days Per Day Total Room B oard 4 23 $200 $18,400 Subtotal 121 $51,367 Ext Hours 144 166 111 166 499 1086 22 .635 Labor Cost $0 $178 $2 $2 $15 $45 Subtotal 20% Co ntingency Subtotal 111 $ per mile Total <1l+<2l Distance= Labor Rate= Lab & Mat Cost $2, 113 $228 $8 $6 $15 $45 Subtotal $4,142,1 85 $828,437 $4,970,622 $1,274,51 8 $5,021,98 8 June 8, 2011 16 ,896 Ft or 3.2 mile Submarine 3,696 Ft or .7 mile URD $165 per mh Extended Total $12 ,675 $3 ,85 5,667 $85 ,378 $47,494 $27,443 $82 ,3 28 $4,110,985 $18,008 $/mile City Of Akutan-Loud Creek Hydro Option 3 Loud Creek to Akutan -Same as Op ti on 2 with onsho re portion at proposed dock facilities Assembly Section Cans w/ Elbows #2 cu 15 kV Submarine Cable (All Inclusive) #2 cu 15 kV kV URD Cable 4" HOPE Conduit w/ fittings Trench/Plow 50% Rock Trench 50% Professional Services Engineering Construction Mgt. Equipment 04 cat w/plow Boom Truck Backhoe Pi ckup Skid steer 4 wheeler wire eq uip undgrd Barge 1 Crews of 4 men Room Board Q!Y 9 16368 14256 9504 2376 2376 Q!Y 1 0 1 1 1 2 1 1 4 Weight Cost FRT diff 250 $2,000 $113 1 $5 $0 1 $4 $0 0 $0 $0 0 $0 $0 Unit Cost/unit 4 .0 (mi) $4,000 .00 4 .0 (mi) $4,000.00 Professional Services Subtotal Rent/mo Ext Rent Fuel $10,000 $10,000 $5,760 $3,500 $0 $0 $3,500 $3,500 $3,840 $1 ,800 $1,800 $3,840 $4 ,000 $4,000 $3 ,840 $1,000 $2,000 $1,920 $2,500 $2,500 $0 10,000 $10 ,000 Total #days Per Day Total 30 $200 $24 ,000 Subtotal <2l $77,000 Material Cost $2 ,113 $50 $5 $4 $0 $0 Hours 24 1.08 0 .015 0 .015 0.09 0.27 4 men 12hr -#of days $16 ,000 $16 ,000 $32,000 Total $15 ,760 $0 $7 ,340 $5,640 $7,840 $3,920 $2 ,500 $10 ,000 $53 ,000 Ext Hours 216 214 143 214 642 1428 29.745 Labor Cost $0 $178 $2 $2 $15 $45 Subtotal 20% Contingency Subtotal <1 l $ per mil e Total <1 l+<2l June 8, 2011 Distance= 16,368 Ft or 3.1 mile Submarine 4 ,752 Ft or 0.9 mile URD Labor Rate= $165 per mh Lab & Mat Extended Cost Total $2,113 $19,013 $228 $3,735,178 $8 $109,771 $6 $61,063 $15 $35,284 $45 $105 ,851 Subtotal $4,066,159 $17,224 $/mile $4,098,159 $819 ,6 32 $4,917,791 $1,229,448 $4,994,791 City Of Akutan-Loud Creek Hydro Option 4 Loud Creek to Akutan -Submarine from Loud creek to proposed dock facilities then onshore URD following purposed road to Akutan Power House Assembly Section Cans w/ Elbows #2 cu 15 kV Submarine Cable (All Inclusive) #2 cu 15 kV kV URD Cable 4" HOPE Conduit w/ fittings Trench/Plow 50% Rock Trench 50% Professional Services Engineering Construction Mgt. Equipment 04 cat w/plow Boom Truck Backhoe Pickup Skidsteer 4 whee ler wire equip undgrd 1 Crew of 4 men Room Board Q!Y 17 8976 44352 29568 7392 7392 Qty 1 0 1 1 1 4 1 4 Weight Cost FRT diff 250 $2 ,000 $112 .50 1 $5 $0.23 1 $4 $0.45 0 $0 $0 .00 0 $0 $0 .00 Unit Cost/un it 4.5 (m i) $4,000.00 4.5 (mi) $4,000 .00 Professiona l Services Subtotal Rent/mo Ext Rent Fuel $10 ,000 $29,333 $16 ,896 $3,500 $0 $0 $3 ,500 $10,267 $11,264 $1 ,800 $5,280 $11 ,264 $4,000 $11,733 $11 ,264 $1 ,000 $11,733 $11 ,264 $2,500 $7,333 $0 Tota l #days Pe r Day Total 88 $200 $70,400 Subtotal (2l $20 8,032 Material Cost $2,112.50 $50.00 $5.23 $3.95 $0 .00 $0.00 Hours 24 1.08 0.015 0 .015 0 .09 0 .27 4 men 12hr -#of days $18,000 $18,000 $36 ,000 Total $46,229 $0 $21,531 $16,544 $22 ,997 $22,997 $7,333 $137 ,632 Ext Hours 408 665 444 665 1996 4178 87 .04 Labor Cost $0 $178 $2 $2 $15 $45 Subtotal 30% Contingency Subtotal 111 $ per mile Total <1>+<2> Distance= Labor Rate= Lab & Mat Cost $2 ,112.50 $228 .20 $7.70 $6.43 $14 .85 $44 .55 Subtotal $3,090,805 $927,242 $4,018,047 $892,899 $4,226,079 June 8, 2011 8,976 Ft or 1.7 mile Submarine 14,784 Ft or 2 .8 mile URD $165 per mh Extended Total $35,913 $2 ,048,323 $341 ,510 $189 ,974 $109 ,771 $329 ,3 14 $3 ,054,805 $9,183 $/mile City Of Akutan-Lo ud Creek Hydro Optio n 4a Loud Creek to Akutan -L o ud Creek to Harbo r -Submarine from Loud Creek to Harbor Ass embly Section Cans w/ Elbows #2 cu 15 kV Submarine Cable (All Inclusive) #2 cu 15 kV kV URD Cable 4 " HOPE Conduit w/ fittings Trench/Plow 50 % Rock Trench 50% Profes sional Services Engineering Construction Mgt. Equipment 04 cat w/plow Boom Truck Backhoe Pickup Skid steer 4 wheeler wire equip undgrd 1 Crew of 4 men Room B oard Qty 2 8976 1800 1200 300 300 Qty 1 0 1 1 1 4 1 4 Weight Cost FRT diff 250 $2,000 $112.50 1 $5 $0.23 1 $4 $0.45 0 $0 $0.00 0 $0 $0.00 Unit Cost/unit 1.8 (mi) $4,000.00 1.8 (mi) $4 ,000 .00 Professional Services Subtotal Rent/mo Ext Rent Fuel $10,000 $1,667 $960 $3,500 $0 $0 $3,500 $583 $640 $1 ,800 $300 $640 $4,0 00 $667 $640 $1,000 $667 $640 $2,500 $417 $0 Total #days Per Day Total 5 $200 $4 ,000 Subtotal <2> $11 ,820 Material Cost $2,112.50 $50.00 $5 .23 $3 .95 $0 .00 $0 .00 1.08 0 .015 0.01 5 0 .0 9 0 .2 7 4 men 12hr -#of days $7 ,255 $7 ,255 $14,509 Total $2,627 $0 $1,223 $940 $1,307 $1,307 $417 $7,820 Ext Hours 48 27 18 27 81 201 4.1875 Distance = Labor Rate= Labor Cost $0 $178 $2 $2 $15 $45 Subtotal 30% Co ntinge n c y Subtotal <1 > $ per mile Total <1>•<2> June 8, 2011 8,976 Ft or 1. 7 mile Submarine 600 Ft URD $165 per mh Lab & Mat Extended Cost Total $2,112.50 $4,225 $228 .20 $2,048 ,323 $7.70 $13,860 $6.43 $7,710 $14.85 $4,455 $44 .55 $13,365 Subtotal $2,091,938 $12,463 $/m ile $2,10 6,447 $631,9 34 $2,738 ,3 81 $1,509,885 $2,750,201 City Of Akutan-Lo ud Creek Hydro Option 5-Akutan P ower House t o Existing Trident Facitlities Assembly Section Cans w/ Elbows #2 cu 15 kV Submarine Cable (All Inclusive) #2 cu 15 kV kV URD Cable 4 " HOPE Conduit w/ fittings Trench/Plow 50% Rock Trench 50% Pro f essio nal Services Engineering Construction Mgt. Equipment 04 cat w/plow Boom Truck Backhoe Pickup Skidsteer 4 wheeler wire equip undgrd 1 Crews of 4 men Room B o ard Q!Y 6 0 7920 5280 1320 1320 Q!Y 1 0 1 1 1 2 1 4 Weight Cost FRT diff 250 $2 ,000 $113 $5 $0 1 $4 $0 0 $0 $0 0 $0 $0 Unit CosUunit 0 .5 (mi) $4,000.00 0 .5 (mi) $4,000 .00 Professional Services Subtotal RenUmo Ext Rent Fuel $10 ,000 $6,000 $3 ,456 $3 ,500 $0 $0 $3,500 $2,100 $2,304 $1,800 $1,080 $2,304 $4 ,000 $2,400 $2,304 $1,000 $1,200 $1, 152 $2,500 $1 ,500 $0 Total #days Per Day Total 18 $200 $14,400 Subtotal <2> $40,20 0 Material Cost $2,113 $50 $5 $4 $0 $0 Hours 24 1.08 0 .015 0 .015 0.09 0.27 4 men 12hr -# of days $2 ,000 $2 ,000 $4 ,000 Total $9,456 $0 $4,404 $3,384 $4,704 $2,352 $1 ,500 $25,800 Ext Hours 144 119 79 119 356 817 17.025 Di stance= Labor Rate= Labor Cost $0 $178 $2 $2 $15 $45 Su bt o tal 20% Co ntingency Su b t o tal (1> $ per mile Total (1l•(2l June 8, 2011 0 Ft or 0 mile Submarine 2,640 Ft or .5 mile URD $165 per mh Lab & Mat Extended Cost Tota l $2 , 113 $12,675 $228 $0 $8 $60,984 $6 $33,924 $15 $19,602 $45 $58,806 Subtotal $185,991 $70 $/mile $1 89,991 $37,998 $227,989 $455,97 8 $2 68,1 89 City Of Akutan-Loud Creek Hydro Option 6 Loud Creek to Akutan -Overland URD from Loud Creek to proposed dock facilities then onshore URD following proposed road to Akutan Power House Material Assembly Q!Y Weight Cost FRT diff Cost Hours Section Cans w/ Elbows 25 250 $2 ,000 $112 .50 $2,112.50 24 #2 cu 15 kV Submarine Cable (All Inclusive) 0 $50.00 1.08 #2 cu 15 kV kV URD Cable 76032 1 $5 $0 .23 $5 .23 0.015 4 " HOPE Conduit w/ fittings 50688 1 $4 $0.45 $3 .95 0 .015 Trench/Plow 50 %-Road 7392 0 $0 $0.00 $0 .00 0.09 Rock Trench 50 %-Road 7392 0 $0 $0 .00 $0.00 0.27 Establish level path for equip 10560 0 $0 $0 .00 $0.00 0 .5 Rock Trench -no road 10560 0 $0 $0 .00 $0 .00 0.27 4 men 12hr -#of days Professional Services Unit Cost/unit Engineering 4 .8 (mi) $4,000.00 $19,200 Construction Mgt. 4 .8 (mi) $4,000.00 $19,200 Professional Services Subtotal $38,400 Equipment Q!Y Rent/mo Ext Rent Fuel Total 04 cat w/plow 2 $10,000 $92,333 $53 ,184 $145,517 #of crew= Boom Truck 0 $3,500 $0 $0 $0 Backhoe 2 $3,500 $32,317 $0 $32 ,317 Pickup 1 $1,800 $8,310 $0 $8,310 Skid steer 1 $4,000 $18,467 $0 $18,467 4 wheeler 4 $1,000 $18,467 $0 $18,467 wire equip undgrd 1 $2,500 $11,542 $0 $11,542 Trencher 1 $25,000 $115,417 $0 $115,417 Airtrack 2 $5,000 $46,167 $0 $46,167 Total $234 ,6 19 1 Crew of 4 men #days Per Day Total Room Board 4 277 $200 $221 ,600 Subtotal <2 > $456 ,219 June 8, 2011 Distance= 10,560 Ft or 2.0 mile Roadless 14,784 Ft or 2.8 mile URD in Road Labor Rate= $165 per mh Labor Lab & Mat Extended Ext Hours Cost Cost Total 600 $0 $2,112 .50 $52,813 $178 $228 .20 $0 1140 $2 $7 .70 $585,446 760 $2 $6 .43 $325,670 665 $15 $14.85 $109 ,771 1996 $45 $44.55 $329,314 5280 $83 $82.50 $871 ,200 2851 $68 $67.50 $712,800 13293 Subtotal $2,987 ,014 276 .94 $10 ,762 $/mile Subtotal $3,025,414 2 20% Contingency $605,083 Subtotal <1> $3,630,497 $ per mile $756,354 Total (1l+(2l $4,086,716 City Of Akutan-Loud Creek Hydro Option 6A Loud Creek to Harbor • Overland (primitive road included) fromLoud Creek to proposed dock facilities Material Assembly Qty Weight Cost FRT diff Cost Hours Section Cans w/ Elbows 12 250 $2,000 $112.50 $2,112.50 10 #2 cu 15 kV Submarine Cable (All Inclusive) 0 $50.00 0 #2 cu 15 kV kV URD Cable 31600 1 $5 $0.23 $5 .23 0 .015 4" HOPE Conduit w/ fittings 21000 1 $4 $0.45 $3.95 0 .0 15 Trench/Plow 50%-Road 5500 0 $0 $0.00 $0.00 0 .09 Rock Trench 50%-Road 5500 0 $0 $0 .00 $0.00 0 .27 Establish level path for equ ip 5000 0 $0 $0.00 $0.00 0.5 Rock T rench -no road 5000 0 $0 $0.00 $0.00 0 .27 4 men 12hr-#of days Professional Services Un it Cost/unit Eng ineering 2 .0 (mi) $4,000.00 $8 ,000 Construction Mgt. 2.0 (mi) $4,000.00 $8 ,000 Professional Services Subtotal $16,000 Equipment Qty Rent/mo Ext Rent Fuel Total 04 cat w/plow 2 $10 ,000 $47,000 $27 ,072 $74,072 #of crew= Boom Truck 0 $3,500 $0 $0 $0 Backhoe 2 $3 ,500 $16,450 $0 $16,450 Pickup 1 $1,800 $4 ,230 $0 $4,230 S kidsteer 1 $4,000 $9,400 $0 $9,400 4 wheeler 4 $1,000 $9,400 $0 $9,400 wire equip undgrd 1 $2,500 $5,875 $0 $5,875 Trencher 1 $25,000 $58 ,750 $0 $58,750 Airtrack 2 $5,000 $23,500 $0 $23,500 Total $119,427 1 Crew of 4 men #days Pe r Day Tota l Room Board 141 $200 $0 Subtotal <2l $119,427 June 8, 2011 Distance= 10,560 ft or 2.0 mile Roadless Labor Rate= $165 per mh Labor Lab & Mat Extended Ext Hours Cost Cost Total 120 $0 $2 ,112 .50 $25,350 $0 $50.00 $0 474 $2 $7.70 $243 ,320 315 $2 $6.43 $134 ,925 495 $15 $14.85 $81,675 1485 $45 $44.55 $245,025 2500 $83 $82.50 $4 12,500 1350 $68 $67.50 $337,500 6739 Subtotal $1,480 ,295 140.3958 $140 $/Mile Subtotal $1,496,295 20% Contingency $299,259 Subtotal <1l $1,795,554 2 $ per mile $897,777 Total <1>•<2l $1,914,981 APPENDIX C SCHEDULE ID ,o Task Name ·-1·-·s C onceptual Study 2 FERC jurisdiction declaration 3 Define Permitting Requirements 4 State of Alaska Grant Process 5 13 State of Alaska funding 6 Preliminary engineering 7 13 Survey 8 13 Geo technical 9 Permitting 10 Permits issued 11 Final Design 12 Submarine cable bathymetric surv 13 Order turbine/generator 14 Order submarine cable 15 Bid construction work 16 Contractor awarded site work 17 Contractor purchase materials anc ---:rs-Mobilize for site construction 19· Turbine/generator equip delivery 20 Deliver submarine cable 21 Site construction work 22 Turbine/generator install 23 Project online Project: Loud Creek Hydro Project De Date: Wed 6/8/1 1 Task Split Duration -0 days 6 mons 1 mon 3 mons O days 90 days 2 mons 2 mons 12 mons O days 2 mons 2 mons O days O days 2 mons 10 edays 2 mons 1 mon 12 mons 6 mons 5 mons 1 mon O days Start . 3 '4 Mon 10/31/1 ~ I I Mon 10/31 /11' Mon 4/16/12 Mon 5/14/121 I Fri 8/3/121 Mon 8/6/12 Mon 8/6/12 ; Moo 12/10112 1 Mon 12110/12 1 Fr i 11 /8/13 1 Mon 11 /11 /13! i Mon 11 /11 /13 Fri 11 /8 /13 Fri 1/3 /14j Mon 1/6/14J Fri 2/28/141 Tue 3/11 /14 Tue 5/6/14! Mon 11 /11 /13 Mon 1/6/14 I Mon 6 /23/141 I Mon 11 /10/141 Fri 12/5/1 4 1 n _.§£ 1 5 6 Progress Milestone 1:_:;_~~.T ~T1 0 • LOUD CREEK HYDRO PROJECT ~2011 11 I 12 : 1 : 2 u__ r4 Ts ---- Summary Project Summary 8/3 ·------ -----------------------------------------· ---- Page 1 External Tasks EX1ernal Milestone .. --=i Deadline APPENDIX D HARBOR POWER CONSUMPTION ESTIMATES McMillen, LLC Summary Power Consumer Harbor Harbor Residences Hovercraft Faci lity Resorts (2) Co mmercial Bu ild ings (2) Restaurants (2) WWTF Total Power (kWh/year) 1,150,000 60,000 11,000 150,000 150,000 250,000 132,000 1,903,000 Proj ect: City of Akutan-Loud Creek Hydropower Development De scr i pti on: Anticipated Power Consumption Summary Prep ared by: ____________________ _ Date: 12/10/10 Checked: DSA -----1 Job No.: ___ --1 McMillen, LLC Project: City of Akutan-Loud Creek Hydropower Development Date: 12/10/10 Desc ription: Harbor Re sidences Checked: DSA Prepared by: ____________ _ Job No.: Assumptions: 1. Akutan, AK residential power useage is similar to other Alaska residences. 2. Re si dential power use in Alaska follows t he same trends as the rest of the United States. 3. Peak use of power ls 5 kW per home. 4. Average daily demand i s the average annual demand distributed across 24 hours per day. 5. Conversion Fac tor -1 Btu= 0.000 293 07108333 kilowatt hour References : Power Req uirements http://www.eia.doe.gov/emeu/recs/historicaldata/historical data80 02.html http://www.akenergyauthority.org/Geothermal/AkutanGeothermalEnergyDemandandStakeholderAssessment2010.pdf Census Information http://guickfacts.census.gov/gfd/states/02000.html Year Million BTU/yr Kw H/yr 1987 1 30.5 1990 4 32.3 1993 7 34 1997 11 35 2001 15 36 2005 19 2010 24 2032 46 Increase i n power use predicted from 2005 to 2032 In 2005 res idential Alaska electrical power use was: Year Households US Census US Census 2000 2009 Average increase per year New Households Households in 2005 Power use per household 2005 2032 221,600 283,879 6,920 256,199 8041 8491 KwH 8900 9500 10000 10300 10600 Pred icted (Power Eq) Kw H/yr 8800 9700 10000 10300 10500 10700 10800 11300 106% 2.06E+09 KWH Compare to Akutan Geothermal Energy Demands Assessment 2010 Report estimated that Akutan spends approximately $157,000 annually on household heating. Each household spent $3,000 annually on heating. Number of households is approximately 52. The City's e lectric usage is approximately 560,000 kw hrs annually. Each household uses a pproximately 11,0000 kw hrs. annually. Assume In dividual average demand Assume Annual Use Average Use 12,000 KwH/yr 1.37 Kw 5 households 60,000 Kw Hrs/yr 7 Kw -----t McMillen, LLC Project: City of Akutan-Loud Creek Hydropower Development Description: Harbor Facility Prepared by: _______________ _ Assumptions: 1 . Conversio n Factor -1 Btu = 0.000 293 071 083 33 kilowatt hour 2. Electrical pow er genera t ed with diesel generators varies from 13 to 14.5 KwH per gallon of diesel. References: Power Requirements http://www. a ke ne rgya uth ori ty. org/ Geot he rm al/Akutan Geot he rma IE ne rgyDe man d ands take holder Assess me nt2O10. pdf Date: 12/10/10 Checked: DSA -----1 Job No.: -----1 The Akutan Geothermal Energy Demands Assessment 2010 predicted the need for approximateley 80,000 gallons of diesel power use annually for the harbor facil ity. Ele ctrical Demands of Harbor Average Daily Use Oil Use gal/yr 79,377 gal/day 220 Electrical Use Electrical Use@ @ 13 KwH/gal 14.S KwH/gal Kw H/yr Kw H/yr 1,030,000 1,150,000 Kw H/day 2,800 Kw H/day 3,200 McMillen, LLC Project: City of Aku t an-Loud Creek Hydropower Development Description : Hovercraft Fa cility Prepared by: ______________ _ Assumptions: 1. Conversion Factor -1 Btu = 0.000 293 071 083 33 kilowatt hour 2. Electrical power generated with diese l generators varies from 13 to 14.5 KwH per gallon of diesel. Use . References : Power Requirements Date : 12/10/10 Checked : DSA ------- Job No.: ------4 http://www.akenergyauthority.org/Geothermal /AkutanGeotherma1EnergyDemandandStakeholderAssessment2010.pdf The Akutan Geothermal Energy Demands Assessment 2010 predicted t he need for approximateley 80,000 gallons of diesel power use annually for the harbor facility. Electrica l El ectrical Use Use@ 13 @14.5 Oi l Use Kw H/gal KwH/gal gal/yr Kw H/yr Kw H/yr Electrical Demand s of Harbor 730 9,000 11,000 gal/day Kw H/day Kw H/day Average Da ily Use 2 25 30 APPENDIX E Project Monthly Energy Generation Table Loud Creek Summary of Monthly Estimated Energy Production for Average Water Year Alternative Base Case (Dam on East Fork Only) Alt #1 (dam on both East & West Fork) Total Jan Feb Mar Apr May Ju n Jul Aug Sep Oct Nov Dec (MWh) ElllBElllDl&llmlll!IIBllDlllDIDllD IBIEllDDl&DllDl&IDlllDllDlmlBIBml APPENDIX F COST OF ENERGY CALCULATIONS Project: Loud Creek Hydropower Description: Cost of Power Calculations By: Mort McMillen Purpose: Determ ine the cost of power for the proposed Loud Creek Hydropower Facility. Reference: Main body of report ( 1) Table 6 -Project Costs (2) Table 7 -Cost of Power Tabl e 6 presents a summary of the estimated project costs for the base case and alternative 1 for options 4 and 4a. Transmission option 4 cons ists of a submarine cable (intertidal burial) around the perimeter of Akutan Bay to the new harbor facilities, then exit to follow the future harbor dock service road to the city diesel power plant utilizing conventional underground power cable. Transmission option 4a consists of a submarine cable, (Intertidal) around the perimeter of Akutan Bay to the new Ha rbor facilities . This is a Harbor only transmission cost. The total project costs presented within Table 96 will be used for the cost element of the cost of power. The values presented in Table 6 are calculated as follows: 1. Capital Cost Obtained from Table 6 -Project Costs. These costs represent the total project cost association with the base case and alternative 1, options 4 and 4a transmission options. 2. Financing It was assumed that 100% financing would be required for the project. This assumption requires financing costs be incorporated into the cost of power analysis. 3. Debt With 100% financing, the debt required will match the capital cost. This debt value will be used to calculate the cost of financing . 4. Term The loan period was assumed at 30 years to finance the project. 5. Interest Rate An interest rate of 6% was assumed for the loan. This value will be used to calculate the annual principal and interest cost association with servicing the loan. 6. Annual Prin cipal and Interest (P&I) The annual P&I cost is determined from the following equation : P&I = P (,l) (1 +,l)N (1 + A-)N - 1 With P&I = Principal and Interest($) P =Original principal (debt) A-= Interest Rate (6%) N =Loan Period (30 years) Therefore calculating for the base alternative and alternative 1, the following P & I values can be determined . Base Case . Option 4 : P & I = (8.306,280) (0 .06) (1.06)30 (1.06)30 -1 = $603,442 Base Case. Option 4a : P & I= (6,712.200) (0.06) (1.06)30 (1 .06)30 -1 = $677, 195 Alternative 1. Option 4a : P & I = (7 ,727.400) (0 .06) (1 .06)30 (1 .06)30 -1 = $561,387 7. Annual O&M The annual O&M based on experience with other similar sized projects was estimated at $100 ,000/ year. 8. Annual Energy Production As outlined in the energy production section of the report, the estimated annual energy production was: Base case= 1, 132,861 Assuming a plant factor of 37% Alternative 1 = 1,548, 100 Assuming a plant factor of 39 % Reference Table 4 -Base case energy production of the report. 9. Annual Cost of Power($/ KWh) Using the values calculated in items 1 through 8, the annual cost of power can be calculated as follows: Annual cost of Power = [Annual P&I +Annual O&Ml Annual Energy Production Therefore, for the base case and alternative 1 considering transmission options 4 and 4a : Base Case Option 4 = Base Case Option 4a = Alternative 1 Option 4 = Alternative 1 Option 4a = [603.442 + 100,0001 = $0.62/ kwh 1, 132,861 [487,641 + 100 .0001 = $0.52/ kwh 1,132,861 [677 .195 + 100,0001 = $0.50/ kwh 1,548,100 [561 ,387 + 100,0001 = $0.43/ kwh 1,548,100 These values were estimated using a spreadsheet model. Rounding through the excel spreadsheet may result in slight variations in the final values due to rounding within the excel spreadsheet. Summary The ca lculated values for annual cost of power are presented in Table 7. McMillen, LLC Project: City of Akutan Description: Loud Creek Hydropower Deve lopment Prepared by:_D_S_A ____________ _ Construction Cost Summary -Base Case Task Cost Turbine-Generator Equipment $ 1,040,000 Dam Construction $ 320,000 Penstock(s) $ 700,000 Powerhouse Foundations $ 180,000 Powerhouse Building $ 162,000 Misc. Powerhouse Equipment $ 30,000 Roads/Dock $ 310,000 Substation $ 353,000 Transmission $ 4 ,226 ,000 Option #4 Trident or Harbor Interconnection $ 270,000 Freiqht ($50,000/ba rqe) $ 50,000 Construction management/Startup $ 50 ,000 Assume most CM by RMA/City of Ackutan Subtotal $ 7,691,000 Engineering and Permitting <@ 8% $ 615,280 Total $ 8 ,306,280 Does not include standby generator set (to be located at Harbor) Date: 6/8/11 Checked: -----i Job No.: -----i McMill en, LLC Project: City of Akutan Descripti on: Loud Creek Hydropower Development Pre p ared by:_D_S_A ___________ _ Construction Cost Summary -Alternative 1 Task Cost T urbine-Generator Equipment $ 1,300 ,000 Dam Constru ction $ 640,000 Penstock (s) $ 950,000 Powerhouse Foundations $ 180,000 Powerhouse Building $ 162,000 Misc. Powerhouse Equ ipment $ 20,000 Roads/Dock $ 380,000 Substation $ 353,000 Transmission $ 4 ,226 ,000 Option #4 T ri dent Interconnection $ 270,000 Freight ($50,000/barge) $ 100,000.00 Construct ion manaqemenUstartup $ 50,000.00 Assumes most CM by RMNCity of Akutan Subtotal $ 8,631,000 Enqineerinq and Permittinq ~8% $ 690,480 Total $ 9,321,480 Does not include s tand by generator set (to be located at Ha rbor) Da te: 6/8/11 Checked : Job No.:----t McMillen, LLC Proj ect: City of Akutan Description: Loud Creek Hydropower Development Prepared by :_D_S_A ______________ _ Powerhouse Foundation Cost Estimate -Base Case and Alternative 1 LABOR MATERIAL DESCRIPTION QTY UNIT UN IT TOTAL UNIT TOTAL General Reqmts Mobil izatio n/Demobilization 1 EA $ -$ - Concrete Found ation 57 CY $ 400.00 $ 22,820.00 $ 500.00 $ 28,524.00 $ 22,820.00 $ 28,524.00 Labor Costs $ 75 per hou r EQUIPMENT UNIT TOTAL $ 25,000.00 400 $ 22,8 19.56 $ 47,819.56 Subtotal Contingency (30%) Akutan Factor (30%) Date : 6/8/11 Checked : Job No.:--------1 SUBCONTRACTOR UNIT TOTAL $ - $ - $ 99,163.56 $ 29,749.07 $ 29,749.07 Profit and Overhead (20%) $ 19,832.71 Total $ 178,494.40 McMillen, LLC EES CONSULTING Project: City of Akutan De scription: Loud Creek Hydropower Deve lopment Prepared by:_D_P_J ----------- Powerhouse Superstructure Cost Estimate -Base Case and Alternative 1 LABOR MATERIAL DESCRIPTION QTY UNIT UNIT TOTAL UNIT TOTAL Specialties PRE-ENGI N EERED BUI LD IN G 900 SF $ 10.00 $9,000.00 $ 90.00 $81 ,000.00 $9,000.00 $81 ,000.00 Labor Costs $ 75 per hour A ssume general contractor will provide equipment requ i red for erection of building (forklift) Date: 6/8/11 Checked: -----JobNo.: ----- EQUIPMENT SUBCONTRACTOR UNIT TOTAL UNIT TOTAL $ - $ -$ - Subtotal $ 90,000.00 Contingency (30%) $ 27,000.00 A kutan Factor (30 %) $ 27,000.00 Profit and Overhead (20%) $ 18,000.00 Total $162,000.00 McMillen, LLC Project: City of Akutan EES CONSULTING Description: Loud Cr eek Hydropower Development Prepared by: _D_PJ ____________ _ Powerhouse Turbine Generator Equipment Cost Estimate -Base Case LABOR MATERIAL DESCRIPTION QTY UNIT UNIT TOTAL UNIT TOTAL Mechani cal/Electrical Equ ipment pa ck age HR $ 180.00 $ -$ - Installation 200 HR $ 75.00 $ 15,000.00 LS $ 5,000.00 Commission ing 4 0 HR $ 75.00 $ 3 ,000.00 $ - Shi ooino 1 LS $50,000.00 $ 50,000.00 $ 68 ,000 .00 $ 5,000 .00 Labor Cos $ 75 per hour Date: 6/8/11 Checked : -------1 Job No.: -------1 EQUIPMENT SUBCONTRACTOR UNIT TOTAL UNIT TOTAL $ - L S $500,000.00 $ 1,800 .00 $ 700.00 $502,500 .00 $ - Subtotal $ 575 ,500 .00 Contingency (30%) $ 172,650.00 Akutan Factor (30%) $ 172,650.00 Profit and Overhead (20%) $ 115,100.00 Total $ 1,035,900.00 For S umm ary Tab le Use $1,040,000.00 McMillen, LLC Project: City of Akutan EES CONSULTING Description: Loud Creek Hydropower Deve lopment Prepared by:_D_PJ ____________ _ Powerhouse Turbine Generator Equipment Cost Estimate ·Ba Alt 1 LABOR MATERIAL DESCRIPTION QTY UNIT UNIT TOTAL UNIT TOTAL Mechanical/Electrical Equipment package HR $ 180.00 $ -$ - Installation 200 HR $ 75.00 $ 15,000.00 LS $ 5,000.00 Commissioning 40 HR $ 75.00 $ 3,000 .00 $ - Shipping 1 LS $50,000.00 $ 50,000.00 $ 68,000.00 $ 5,000.00 Labor Cos $ 75 per hour Date: 6/8/11 Check ed : Job No.: -------1 -------t EQUIPMENT SUBCONTRACTOR UNIT TOTAL UNIT TOTAL $ - LS $645,000.00 $ 1,800 .00 $ 700.00 $647,500.00 $ - Subtotal $ 720,500.00 Contingency (30%) $ 216,150.00 Akutan Factor (30%) $ 216,1 50.00 Profit and Overhead (20%) $ 144,100.00 Total $ 1,296,900 .00 For Summary Table Use $1 ,300,000.00 McMillen, LLC Project: Ci ty of Akutan EES CONS ULTING Description : Loud Creek Hydropower Development Prepared by:_D_PJ __________ _ Powerhouse Superstructure and accessory Equipment Cost Estimate -Base Case LABOR MATERIAL DESCRIPTION QTY UNIT UNIT TOTAL UNIT TOTAL Mechanical/Electrical HVAC 16 HR $ 75.00 $ 1 ,200.00 $ - LIGHTING/RECEPTICALS 24 LS $ 75.00 $ 1,800.00 $ - DRAINAGE 8 LS $ 75.00 $ 600 .00 $ - $ 1,200.00 $ - Labor Cos $ 75 per hour Date: 6/8/11 Checked: Job No.: -------t --------1 EQUIPMENT SUBCONTRACTOR UNIT TOTAL UNIT TOTAL $ - LS $10,000.00 $ 3,800.00 $ 700.00 $14,500 .00 $ - Subtotal $ 15,700.00 Contingency (30%) $ 4,710.00 Akutan Factor (30%) $ 4,710.00 Profit and Overhead (2C $ 3, 140.00 Total $ 28,260.00 For Summary Table Use $30,000.00 McMillen, LLC Project: City of Akutan EES CONSULTING De scripti on: Loud Creek Hydropower Development Prepared by:_D_PJ __________ _ Powerhouse Superstructure and accessory Equipment Cost Estimate -Alternative 1 LABOR MATERIAL DESCRIPTION QTY UNIT UNIT TOTAL UN IT TOTAL Mechanical/Electrical HVAC 16 HR $ 75.00 $ 1,200.00 $ - LIGHTING/RECEPTICALS 24 LS $ 75.00 $ 1,800.00 $ - DRAINAGE 8 LS $ 75.00 $ 600.00 $ - $1,200.00 $ - Labor Cos $ 75 per hour Dat e: 6/8/11 Checked: Job No.: --------1 EQUIPMENT SUBCONTRACTOR UNIT TOTAL UNIT TOTAL $ - LS $ 8,000.00 $ 1,800.00 $ 700.00 $10,500.00 $ - Subtotal $ 11,700.00 Contini:iencv (30%) $ 3,510.00 Akutan Factor (30%) $ 3,510.00 Profit and Overhead (21 $ 2 ,340.00 Total $ 21 ,060.00 F or Summa ry Table Use $20,000.00 McMill en, LLC Proj ect: City of Akutan Des cri ption: loud Creek Hydropower Development Prepa red by:""D"""SA;.;.._ _____________ _ Road Construction Cost Estimate -Base Case LABOR MATERIAL DESCRIPTION QTY UNIT UNIT TOTAL UN IT TOTAL Mobilization Access A TV acce ss road cuVfi ll 120 HRS $ -$ - re-veqetatio n 0.50 AC $ 20,000 $ 10,000.00 $ 43,068 $ 21,534.00 qravel 500 CY $ $ 40 $ 20,000.00 !leotextile 2200 SY $ 2 $ 4.400.00 $ 2 $ 4.400.00 oolvethvlene dock 16.5' x 10') 3 EA $ -$ 2,160 $ 6,480.00 al uminum qanqwav 14' x 35'1 1 EA $ -$ 5,500 $ 5,500.00 oil es 2 EA $ 2,000 $ 4,000.00 $ 1,000 $ 2,000.00 qravel unloadinq ramo/oad (40'x50'x1 'l 100 CY $ -$ 40 $ 4,000.00 $ 18,400.00 $ 6 3,914.00 Labor Costs $ 75 per hour NOTES: Costs fo r Tacoma (98402 ). to be shippe d on ba rge to Akutan (Pacific Alaska Frei ghtways) EZ Docks 360-352-3084 Gravel Lo ry Grego ry (U nalas ka Roads Dept) says that all grave l for Akutan comes from Unalaska. $ $ $ $ s $ Date : 6/8/11 Checked: Job No.,-------t EQUIPMENT SUBCONTRACTOR UN IT TOTAL UNIT TOTAL $ 36,000.00 250 $ 30,000.00 $ - $ -$ - 15 $ 7,500.00 $ - $ $ - 500 $ 1,500.00 $ - 500 $ 500.00 $ - 5,000 $ 10,000.00 $ - 10 s 1,000.00 $ - $ 86 ,500.00 $ - Subtotal $ 168,814.00 Continqe ncv 130'/ol $ 50,644.20 Akuta n Factor (30%) $ 50 ,644.20 Profit and Ove rhead (20%) $ 33,762.80 Total $ 303,865.20 For Summary Table Use $310,000.00 Bill Shaishn ikoff (907) 581 -1409 -intends to be the lowest bidder when it comes time to bid . $34 /cy fo r 1"; $35/cy fo r 3/4"minus, de livered on the ba rge. McMillen, LLC Project: City of Akutan Date: 6/8/11 Description: Loud Creek Hydropow er Development Prepared by:_D"""SA ______________ _ Checked : _____ _ Job No.: _____ _ Road Con struction Cost Estimate -Alternative 1 LABOR MATERIAL EQU IPMENT SUBCONTRACTOR DESCRIPTION QTY UNIT UNIT TOTAL UN IT TOTAL UNIT TOTAL UNIT TOTAL Mobilization $ 44,000.00 Access ATV access road cuVfill 160 HRS $ -$ -$ 250 $ 40,000.00 $ - re-ve qetation 0 .67 AC $ 20,000 $ 13,300.00 $ 43,068 $ 28,640.00 $ -$ - oravel 670 CY $ -$ 40 $ 26,800.00 $ 15 $ 10,050.00 $ - oeotexti le 3000 SY $ 2 $ 6,000.00 $ 2 $ 6,000.00 $ -$ polvethvlene dock 16 .5' x 10') 3 EA $ -$ 2 ,160 $ 6,480.00 $ 500 $ 1,500.00 $ - aluminum oanowav 14' x 35') 1 EA $ -$ 5,500 $ 5,500.00 $ 500 $ 500.00 $ - piles 2 EA $ 2,000 $ 4 ,000.00 $ 1,000 $ 2,000.00 $5,000 $ 10,000.00 $ - qravel unloadinq ramp/pad (40'x50'x1') 100 CY $ -$ 40 $ 4,000.00 $ 10 s 1,000.00 $ - $ 23,300.00 $ 79,420.00 $ 107,050.00 $ - Labor Costs $ 75 per hour Subtotal $ 209,no.oo Contint:iencv (30%) $ 62,931.00 Akutan Factor (30%) $ 62,931 .00 Profit and Overhead (20%) $ 41 ,954.00 Total ~ 377,586.00 NOTES: For Summary Table Use $380,000.00 Costs for Tacoma (98402), to be shipped on barge to Akutan (Pacific Alaska Freig htways) EZ Docks 360-352-3084 Gravel Lory Gre gory (Unalaska Roads Dept) says that all gravel for Akutan comes from Unalaska. Bill Shaishnikoff (907) 581 -1409 -intends to be the lowest bidder when it comes time to bid. $34/cy for 1"; $35/cy for 3/4 "minus, delivere d on the barge. McMillen, LLC Project: City of Akutan Description: Loud Cre ek Hydropower Development Prepared by:_D_S_A _____________ _ Dam Construction Cost Estimate -Base Case LABOR MATERIAL DESCRIPTION QTY UNIT UNIT TOTAL UNIT TOTAL General ReQmts Mobilization/Demobilization $ -$ - Included in Foundation and Road Mobilization Site Develooment DewaterinQ 30 DAYS $ 150 $ 4,500 $ - Excavation and Compaction, Pond (1000 cy) 120 HRS $ 75 $ 9,000 $ - Bentonite 22.4 TONS $ 150 $ 3,360 $ 250 $ 5,600 Erosion and Sedi ment Control 500 LF $ 2 $ 1,000 $ 5 $ 2,500 Rock Riprap (spillway+ pipe) 100 CY $ 18 $ 1,800 $ 70 $ 7,000 Concrete Foundation for droo inlet works 10 CY $ 1,500 $ 15,000 $ 500 $ 5,000 Metals CMP sleeve riser (inlet) 10 LF $ 60 $ 600 $ 100 $ 1,000 Wood/Plastic Fiberglass gratino walkwav 40 LF $ 75 $ 3,000 $ 100 $ 4,000 Pipe suooort 40 EA $ 75 $ 3,000 $ 100 $ 4 ,000 8'x3' fiberglass trash rack 3 EA $ 75 $ 225 $ 1,200 $ 3,600 48" HOPE riser (inlet) 20 FT $ 75 $ 1,500 $ 102 $ 2,040 Low Level Outl et-18" 100 FT $ 60 $ 6,000 $ 25 $ 2,500 $ 48,985 $ 37,240 Labor Costs $ 75 per hour $ $ $ $ $ $ $ $ $ Date: 6/8/11 Checked: -------1 Job No.: -------t EQUIPMENT SUBCONTRACTOR UNIT TOTAL UNIT TOTAL $ -$ - 1,000 $ 30,000 $ - 300 $ 36,000 $ - 2 $ 1,000 $ - 100 $ 10,000 $ - 500 $ 5.000 $ - 50 $ 500 $ - 50 $ 2,000 $ - 50 $ 2,000 $ -$ - 100 $ 2,000 $ - $ 88,500 $ - Subtotal $ 174,725.00 Contingency (30%) $ 52,417.50 Akutan Factor (30%) $ 52,417.50 Profit a nd Overhead (20%) $ 34,945.00 Total $ 314,505.00 McMillen , LLC Proj ect: Ci ty of Akut an Dat e: 6/8/11 Description: Loud Creek Hydropower Development Prepared by:_D_SA ____________ _ Ch ecke d : _____ --1 Job No.: ------4 Dam Construction Cost Estim ate - A lternative 1 LABOR MATERIAL EQUIPMENT SUBCONTRACTOR DESCRIPTION QTY UNIT UN IT TOTAL UNIT TOTAL UNIT TOTAL UNIT TOTAL Gener al Reamts Mobilization/Demobilization 1 EA $ -$ -$ -$ - Included in Foundation and Road Mobilization Site Development Dewateri na 60 DAYS $ 150.00 $ 9,000.00 $ -1,000 $ 60 ,000.00 $ - Excavation , Pond (1500 cy) 240 HRS $ 75.00 $ 18 ,000.00 $ -300 $ 72 ,000.00 $ - Erosion and Sediment Control 1000 LF $ 2.00 $ 2 ,000.00 $ 5.00 $ 5,000 .00 2 $ 2,000.00 $ - Rock Riprap (s pillway+ pipe) 200 CY $ 18.00 $ 3 ,600.00 $ 70.00 $ 14,000.00 100 $ 20 ,000.00 $ - Concrete Foundation for drop inlet works 20 CY $ 1,000.00 $ 20 ,000.00 $ 500.00 $ 10,000.00 500 $ 10,000.00 $ - Metals CMP sleeve riser (inlet) 20 LF $ 60.0 0 $ 1.200.00 $ 100.00 $ 2,000 .00 50 $ 1,000.00 $ - Wood/Plastic FiberQlass QratinQ wa lkway 80 LF $ 75.00 $ 6 ,000.00 $ 100.00 $ 8,000.00 50 4000 $ - Pipe support 80 EA $ 40 .00 $ 3,200.00 $ 100.00 $ 8,000.00 50 4000 Vinvl shee t Pile 2000 SF $ 1.00 $ 2,000.00 s 10 .00 $ 20 ,000 .00 10 20000 8'x3 ' fiberalas s trash rack 6 EA $ -$1,200.00 $ 7,200.00 $ -$ - 48" HOP E riser (inlet) 20 FT $ 50 .00 $ 1,000.00 $ 102.00 $ 2,040.00 100 $ 2,000.00 $ - Low Level -18" 100 FT $ 60 .00 $ 6 ,000.00 $ 25 .00 $ 2,500.00 50 $ 5,000.00 0 $ -$ -$ - 0 $ -$ -$ - $ 72,000 .00 $ 78,740.00 $ 200,000.00 $ - Labor Costs $ 75 per ho ur Subtotal $ 350 ,740.00 Contim:iencv (30 %) $ 105,222 .00 Akutan Factor (30%) $ 105,222.00 Profit and Overhead (20 %) $ 70 ,148.00 For Summary Table Use $640,000.00 Total $ 631 ,332.00 McMillen, LLC Project: City of Akutan Description: loud Creek Hydropower Deve lopment Prepared by:_D_S_A ____________ _ Penstock Construction Cost Estimate -Base Case LABOR MATERIAL DESCRI PTION QTY UN IT Gener al Ream ts Mobilization/Demobilization Included in Foundation and Road Mobilization Site Development Dewaterina 7 DAYS Erosion and Sediment Control 4000 LF Concrete Thrust blocks 4 EA Pioe 16" SOR 7.3 HOPE 2500 ft 18" SOR 7.3 HOPE 24" SOR 7 .3 HOPE Pipe Transport NOTES: HOPE install ation price : http://www.hdpe.com/fus ion/fusion_cost_g uideline.shtml HOPE pricing from United Pipe, Tacoma Labor Costs $ 75 per hour $ $ $ $ $ $ UNIT TOTAL UNIT TOTAL $ -$ - 100 $ 700 $ - 1 $ 4,000 $ 3 $ 12,000 1,000 $ 4,000 $ 500 $ 2 ,000 20 $ 50,000 $ 35 $ 86,500 20 $ -$ 44 $ - 20 $ -$ 93 $ - $ 50,000 $ - $ 58,700 $ 150,500 Date: 6/8/11 Checked: _____ -t Job No.: ------t EQUIPMENT SUBCONTRACTOR UNIT TOTAL UNIT TOTAL $ -$ - $ 500 $ 3,500 $ - $ 2 $ 8,000 $ - $ 500 $ 2 ,000 $ - $ - $ 65 $ 162,50 0 $ - $ 65 $ - $ -$ - $ -$ - $ -$ - $ 176,000 $ - Subtotal $ 385,200.00 Contingency (30%) $ 115,560.00 Akutan Factor (30%) $ 115,560.00 Profit and Overhead (20%) $ 77,040.00 Tot al $ 693,360.00 McMillen, LLC Project: City of Akutan Description: Loud Creek Hydropower Development Prepared by: _D_S_A _____________ _ Penstock Construction Cost Estimate -Alternative #1 LABOR MATERIAL DESCRIPTION QTY UNIT General Reqmts Mobilization/Demobilization 1 EA Site Development Dewatering 7 DAYS Erosion and Sed iment Control 4000 LF Concrete Thrust blocks 14 EA Pipe 16" SDR 17 HOPE 950 ft 18" SOR 7.3 HOPE 2500 Pipe Transport NOTES: HOPE installation price : http://www .hdpe.com/fusion/fusion_cost_guideline.shtml HOPE pricing from United Pipe, Tacoma Labor Costs $ 75 per hour UNIT TOTAL UNIT TOTAL $ -$ - $ 100.00 $ 700.00 $ - $ 1.00 $ 4,000.00 $ 3.00 $ 12,000 .00 $ 1,000.00 $ 14,000.00 $ 500 .00 $ 7,000.00 $ -$ - $ 20.00 $ 19,000.00 $ 19.47 $ 18,497.00 $ 20.00 $ 50,000.00 $ 43.79 $109,475.00 $ 50,000.00 $ 87,700.00 $196,972.00 Date: 6/8/11 Checked: -------Job No.: -------1 EQUIPMENT SUBCONTRACTOR UNIT TOTAL UNIT TOTAL $ -$ - 500 $ 3,500.00 $ - 2 $ 8,000.00 $ - 500 $ 7,000.00 $ - $ -$ - 65 $ 61,750.00 $ - 65 $ 162,500.00 $ - $ -$ - $ 242,750 .00 $ - Subto t al $ 527,422.00 Contingency (30 %) $ 158,226 .60 Akuta n Factor (30%) $ 158,226.60 Profit and Overhead (20%) $ 105,484 .40 Total $ 949,359 .60