Loading...
HomeMy WebLinkAboutThayer Lake Hydropower Project 12kV Transmission Line Design Basis - Dec 2020 - REF Grant 7050825electric Power Systems mc. Consulting Engineers Inside Passage Electric Cooperative Thayer Creek Hydro 12kV Line Project Electrical Design Basis EPS Project #: 20-0092 Dec 30, 2020 Submitted by: Electric Power Systems, Inc. Prepared by: Matthew S. Williams, PE Summary of Changes Revision Number Revision Date Revision Description 1 2020-12-30 Initial Submission with 95% design 2 2020-12-30 Revised per client comments 12/2020 Page 2 electric Power S sy tems 'nc. Consulting Engineers Electrical Design Basis 1 Summary...........................................................................................................................4 2 Design Standards and Codes.......................................................................................... 4 3 Project Scope Description............................................................................................... 4 4 Overhead vs. Underground Construction Considerations ............................................ 4 5 Design Basis..................................................................................................................... 6 5.1 Loading Criteria......................................................................................................... 6 5.2 Clearances..................................................................................................................6 5.3 Structures and Foundations..................................................................................... 7 5.4 Line Conductor.......................................................................................................... 8 5.5 Insulators and Hardware........................................................................................... 8 5.6 Guys and Anchors..................................................................................................... 8 5.7 Grounding.................................................................................................................. 8 5.8 Communications........................................................................................................9 6 Right -of -Way and Easements.......................................................................................... 9 7 Other Considerations....................................................................................................... 9 8 Cost Estimate................................................................................................................... 9 12/2020 Page 3 electric Power S sU tems �7 n Consulting Engineers 'nc. Electrical Design Basis Summa This report presents the design standards, design criteria and planned equipment and materials for the construction of the 12-kV tie line to connect the Thayer Creek Hydro project into Angoon, Alaska on Admiralty Island. It also addresses considerations of overhead vs underground construction for the project. Estimated electrical construction costs will be provided as an addendum to this report. 2 Design Standards and Codes The reference design standards, codes, and guidelines utilized in the development of the electrical design of the project include, but are not limited to the following: C2-2017 National Electrical Safety Code (NESC) — 2017 edition RUS 1782F-804 Specifications and Drawings for 12.5/7.2 kV Line Construction ANSI American National Standards Institute NEMA National Electrical Manufacturer's Association 3 Project Scope Description This project consists of a 12kV line extension to tie the Thayer Creek Hydro project into the Angoon electrical distribution system. It consists of a proposed underground bore beneath Kootznahoo Inlet to Turn Point, and then a 12 kV line extension over six miles in length from the Inlet to the proposed Thayer Creek hydro site. An access road is planned to be constructed from the Inlet to the site; the line is intended to follow the access road as close as possible to allow for easier access for both initial construction and line maintenance. 4 Overhead vs. Underground Construction Considerations As part of our basis of design, EPS has performed a basic analysis of the relative benefits of constructing the line from Kootznahoo Inlet to Thayer Creek with overhead construction vs underground construction. Specifically, we wanted to look at efficacy, reliability, maintenance, and costs. For efficacy, or in other words, effectiveness of the construction type, we usually consider things like energy losses during operation, installation cost, and maintenance costs. Overhead lines generally have higher impedances than equivalent underground lines and therefore higher operational losses; however, the costs of these difference in line losses is usually negligible compared to the costs associated with overall installation and maintenance. When considering reliability, there are two factors to consider: quantity of outages, and the cost and time of outages. Typically, the overhead lines end up with more outages from external events such as wind or trees. Overhead lines also lend themselves to easier troubleshooting and shorter outages; time to find and repair overhead line outages is typically a matter of hours. When faults occur on underground lines it can be days to find and repair an outage. 12/2020 Page 4 electric Power S sv terns Consulting Engineers inc. Electrical Design Basis Maintenance on costs on overhead lines tend to skew heavily towards the cost of clearing; these lines require clearing to be performed on a regularly scheduled interval. In addition, visual inspections of the line are used to identify any areas where poles, crossarms or insulators might need replacement. As visual inspection of underground lines is limited to the above ground equipment, maintenance for underground lines tends to take place in response to outages, unless visible damage or disrepair is noted on the above ground equipment and pads. When comparing the initial construction cost of underground construction vs. overhead construction, underground construction is more expensive than its equivalent overhead. Typically, we expect underground construction to be on the order of one -and -a -half to three times the cost of overhead construction. Specifically, for this project, one item that we anticipate factoring into the underground construction cost is rock excavation. We anticipate the construction to encounter considerable rock; this will drive up the cost of trenching which is one of the highest cost line items in underground construction. For this project, we estimate that the underground construction would be approximately 2.5 times the estimated overhead construction cost. Another under consideration is the overall life cycle of the installation. For underground construction, we typically assume an overall project life of 30 years before the system will require replacement. For overhead line construction, a project life cycle of 50 years is typically assumed. Finally, we considered a line design where the line was installed partially underground in segments where it might be feasible to do so. However, each of these transitions from overhead to underground and back up again will add two additional riser structures, with their additional cost. The risers also include associated terminations of the underground cable for transition to and from overhead construction, which are additional points of failure on the system, as underground cable failure most frequently occurs at terminations and splices. Each termination point is also a potential point of additional line impedance. Also, and perhaps as critically, underground cable adds a capacitive effect to the line. Due to the smaller nature of this hydro generation, adding this additional capacitance may require installation of line reactance to offset this capacitance, which also adds line losses, additional cost, and maintenance. Therefore, primarily because of installation cost, but also for ease of troubleshooting and maintenance, we have selected overhead construction as the basis of design for the entirety of the section of line between Turn Point and Thayer Creek on this project. 12/2020 Page 5 electric Power S sv terns �S M . Consulting Engineers Electrical Design Basis 5 Design Basis The following are the design criteria that the overhead line design is based upon. 5.1 Loading Criteria The overhead line will be designed for the following loading criteria using NESC Grade B construction: 1) NESC Heavy Loading (NESC Rule 250B) A 40 mph wind (4 psf), with'/ -inch of radial ice, at 0°F, with NESC Grade B load and strength factors as summarized in the table below: Load Factors/Strength Factors Item Wind Loads Wire Tension Loads Vertical Loads Wood Structures 2.5/0.65 1.65/0.65 1.5/0.65 Guy Wire 2.5/0.9 1.65/0.9 1.5/0.9 Anchors and Support Hardware 2.5/1.0 1.65/1.0 1.5/1.0 2) Extreme Wind Loading (NESC Rule 250C) A 110 mph (36.9 psf) with no ice, at 40°F. This will be applied with a 1.0 load factor and strength factors of 0.75 for wood poles, 0.9 for guys, and 1.0 for anchors and hardware. 5.2 Clearances Ground Clearances for this project will be based on NESC minimum clearance requirements with supplemental good practice adders included. The clearance condition will be the cable or conductor sag at either 32 degrees F with 1/2" radial ice (57pcf) or sag at the maximum operating temperature; whichever results in the greater sag. The maximum operating temperature for the communications cables and 12.5 kV conductor will be 120 degrees F (minimum allowed per NESC requirements). 12/2020 Page 6 electric Power S sv terns �S M . Consulting Engineers Electrical Design Basis The following table summarizes the NESC minimum clearances for the conductors of this project, as well as our recommended supplemental adders: Comm over Comm over 12.5kV over 12.5kV over Areas Roads and Areas Roads and Accessible to Land Accessible to Land Pedestrians Traversed by Pedestrians Traversed by Only Vehicles Only Vehicles NESC minimum clearance (from 15.5 ft 9.5 ft 14.5 ft 18.5 ft Table 232-1 Extra Clearance for construction variations, snow, 2.5 ft 2.5 ft 2.5 ft 2.5 ft sag increase, etc TOTAL DESIGN 18 ft 12 ft 17 ft 21 ft CLEARANCE Line design will mostly assume that vehicle traffic is possible (with the exception of steep slopes), so ground clearance will be based upon those columns above. In addition, wherever the line crosses the roadway, a minimum of 20 feet of road clearance to all conductors and comm cables will be designed for. 5.3 Structures and Foundations Basic structures for this line will consist of single wood pole structures using crossarm construction. Pole top assemblies will consist of RUS based configurations. Raptor protection configurations will be used based upon the RUS "P" units, including using 10 foot arms with a pole top center phase to provide additional spacing between conductors. Wood crossarms will be used for tangent and small angle applications; fiberglass deadend arm assemblies will be used for deadends and larger angles. Wood Poles will be Douglas Fir, pressure treated with pentachlorophenal. Anticipated minimum pole class will be class 3; pole lengths are expected to be 45 feet minimum, up to 60 feet if the terrain of the routing dictates. Foundations will be direct embedded and backfilled with native or imported granular material. Rock is expected to be encountered along the route; rock drilling with lower embedment depths will be used in areas with subsurface solid rock conditions. 12/2020 Page 7 electric Power S sv terns �S M . Consulting Engineers Electrical Design Basis 5.4 Line Conductor The overhead line conductor selected for this project will be #1/0 ACSR bare conductor. #1/0 AWG, 6/1 stranding ACSR Code Name "Raven" Weight: 0.145 Ibs/ft. Diameter: 0.398 inches Rated Tensile Strength: 4,380 Ibs Tensions will be designed in accordance with the tension limitations defined in the NESC. In addition, a low temperature vibration control limitation of 18% rated strength at 23 IF will be used to eliminate the requirement for vibration dampeners. 5.5 Insulators and Hardware Polymer pin -type 15kV insulators will be used for tangent and small angle applications. Pin insulators will not be loaded to more than their maximum reference cantilever load (approximately 50% of their Specified Cantilever Load) under NESC Heavy and extreme loading. Polymer suspension -type insulators will be used for dead-end pole top assemblies. Suspension insulators will be loaded to not more than their Routine Test Load (approximately 50% of their Specified Mechanical Load) under NESC Heavy and extreme loading. 5.6 Guys and Anchors Guys and anchors on wood pole structures will be designed to take the entire load in the direction in which they act; the pole will act as a strut only. Anchors and guy hardware will be sized to meet or exceed the rated breaking strength of the guy strand. Guys will be bonded to the pole grounds. 3/8" EHS guy strand will be used. Anchors will be plate anchors, or grouted rock anchors in locations where sub -surface rock is encountered. 5.7 Grounding Pole grounding will be designed for all pole locations with downguys, transformers, risers, reclosers, and other similar equipment installed. The grounding will consist of a 5/8" diameter ground rod driven at the pole, attached to a ground wire which will run the majority of the length of the pole up to the neutral conductor. Pole hardware, including communications hardware and messengers, will be bonded to the pole ground. In addition to the specific locations noted above, pole grounds will be located such that there are always four grounds in each mile of line to meet the requirements of an effectively grounded neutral. 12/2020 Page 8 electric Power S sv terns �S M . Consulting Engineers Electrical Design Basis 5.8 Communications In addition to the 12kV line conductors, this project will be designed with an underbuild fiber optic cable for system communications. The fiber optic cable will consist of a 24 count cable, which should be more than adequate for the requirements of this project. The fiber will be single -mode, gel -free, all -dielectric outdoor aerial cable lashed to a W EHS messenger wire. The communications cable and messenger will be located below the neutral conductor with enough separation to maintain it as a communications space on the pole. In addition to the general line design criteria noted above, the fiber optic cable design will allow for slack cable storage periodically along the route. The design will be based upon providing 150 feet of slack cable approximately every 1500 feet along the route, in accordance with industry standards. 6 Right -of -Way and Easements All poles, conductors, equipment, downguys and anchors for this project will fall within the proposed 200' right-of-way for the roadway and power line; no additional easement is expected to be required. 7 Other Considerations In addition to the materials noted above in the design criteria, we have planned for installation of two reclosers, one near the power house, and one near the Inlet crossing. Overhead solid dielectric pole mounted reclosers with associated SEL controllers and power supply transformers are planned. These reclosers will provide operational switching capabilities as well as line protection for the project. Finally, the design is based upon close proximity to the access road as noted above; the nature of the access road project is such that final alignment of the access road can be modified all the way through the construction process. Therefore, although our design is based upon the current access road design, it is anticipated that design will need to be reviewed and modified based upon the final constructed alignment and grading of the roadway. 8 Cost Estimate An engineer's estimate for the electrical construction cost of the line has been included as an addendum to this report. Note that a separate cost for the Kootznahoo Inlet crossing was prepared earlier in April of 2020, and is not included again in this estimate for the line construction. End of Electrical Design Basis. 12/2020 Page 9 electric Power S sv terns �S M . Consulting Engineers Thayer Creek Hydro Project 12kV Tie Line - Turn Pt to Thayer Creek Powerhouse Estimate Summary Sheet Item Description Item Subtotal Cost 1) 12.5 kV Overhead Line Costs $ 2,650,822 Poles and Foundations $ 531,621 Conductor $ 703,937 Pole Top Assemblies $ 184,276 Guys, Anchors, Grounding $ 231,612 Fiber Optic Underbuild $ 659,624 Reclosers, Risers and Miscellaneous $ 339,753 2) Construction Management, Engineering, and Staking $ 345,000 Construction Management Costs $ 250,000 Final Design Engineering $ 50,000 Field Staking for Construction $ 45,000 Subtotal Cost Before Contingency $ 2,995,822 Contingency Factor (10%) $ 299,582 Total Estimated Cost for Overhead 12 kV Line $ 3,295,405