Loading...
HomeMy WebLinkAboutSaint Point Electric Boiler Sizing and Specifications Report - May 2016 - REF Grant 7081163Sand Point Excess Wind Utilization Grant # 7081163 Inclusion 1: Sand Point Wind to Heat Boiler Sizing Page 4 of 4 nx power a tanadgusix company Sand Point Wind to Heat Boiler Sizing Date 05/24/2016 Prepared by Dan L.enel TDX Power 615 E. 82nd Ave, Suite 200 Anchorage, AK 99518 www.tdxpower.com Contents Contents..................................................................................................................................................................2 1 Summary..........................................................................................................................................................3 2 Boiler Sizing...................................................................................................................................................4 2.1 Boiler selection criteria......................................................................................... 4 2.2 Available data.. ....... 4 2.3 Calculations.................................................................................................................................................5 2.3.1 Calculating excess wind power.....................................................................................................5 2.3.2 Heat demand......................................................................................................................................5 2.3.3 Effective heat delivered................................................................ 5 2.3.4 Data Validation ............................. 6 2.4 Boiler selection...................................................................................................................... 8 2.4.1 Electrical Service ......................................... 8 2.4.2 Boiler specification.............................................................................................................................8 2.4.3 Boiler cost...........................................................................................................................................8 2.4.4 Boiler selection.................................................................................................................................10 3 Fuel Savings Projections..............................................................................................................................11 4 Appendix........................................................................................................................................................12 4.1 Detailed boiler specification.......................................................................................................................12 Sand point excess wind - boiler sizing.docx 2 of 12 TDX Power Printed Copies are Uncontrolled 1 Summa Two Vestas V39 wind turbines rated at 500 kW each, are part of the generation system that powers the public electricity grid in the remote Alaskan community of Sand Point. At times of high wind, the wind turbines produce more power than can be safely absorbed by the electric grid. Currently, the excess wind energy generated during these times is converted to heat in a load bank; the hot air vented unused to the atmosphere. In order to capture the excess wind energy, an electric boiler will be added to the existing heating system at the local clinic and the school. The following describes the process used to select the boilers and predict the annual fuel savings. Sand point excess wind - boiler sizing.docx 3 of 12 TDX Power Printed Copies are Uncontrolled 2 Boiler Sizin 2.1 Boiler selection criteria The following general criteria describe the ideal boiler: ➢ Large enough to be able to absorb as much excess energy as possible ➢ Small enough to fit in the existing boiler room ➢ Optimized cost ➢ Serviceable without removing entire boiler ➢ Integrated controls with remote command capabilities ➢ Long life ➢ Well insulated to minimize heat loss Y Low water loop pressure drop Self contained safety system that shuts down boiler in case of abnormalities Some of these criteria are contradictory, so finding the best boiler size involves a trade-off between some of the requirements. A detailed boiler specification is attached. 2.2 Available data The following data was available to determine the best boiler size: ➢ One year of hourly data for electric loads, diesel generator output, wind turbine output (WT1, WT2), load bank power, wind speed- and temperature (anemometer data from each wind turbine) ➢ Two years (2014 and 2015) of daily data for electric loads, diesel generator output, wind turbine output (WT1, WT2), load bank power, wind speed- and temperature (anemometer data from each wind turbine) ➢ Heating fuel consumption of the Clinic for the year 2015 ➢ Heating fuel consumption of the School for the years 2009 and 2010 ➢ Heating degree days (min., max., average and annual sum) for the years 2000 to 2015 for Sand Point ➢ Existing boiler data y Wind turbine data Sand point excess wind - boiler sizing.docx 4 of 12 TDX Power Printed Copies are Uncontrolled 2.3 Calculations 2.3.1 Calculating excess wind power Using the daily data and the wind turbine power curve, the theoretically available wind power potential was calculated based on the measured wind speed- and temperature for each hour. For each data point, the excess wind power was calculated: PEW PW - PD + PD(min) - PLD(min) PEW ? 0 (negative values were set to zero) PEW: Excess wind power Pw: Potential wind power PD: Diesel generation PD(min): min. genset load PLD(min): control margin for the load bank. PLD(mnn) = min(50 kW, PW) The boiler control is not fast enough to cope with rapid power fluctuations due to wind gusts. The load bank will still be required to shave -off short power peaks due to wind gusts. The control margin for the load bank was assumed to be 50 kW (but no more than the potential wind power), the minimum genset load 180 kW. 2.3.2 Heat demand Based on the annual heating oil consumption and the cumulative heating -degree-days for the same year, the relative heat demand (kWl°F) for both the school and the clinic were calculated. With this information, the actual heat demand for each day of the daily data set was calculated using the measured ambient temperature. 2.3.3 Effective heat delivered The buildings will only accept heat until their heat demand is satisfied, even if there would be more excess wind power available. The effective heat delivered can never exceed the combined heat demand of the school and the clinic. The result of minimum(excess wind power, [heat demand school + heat demand clinic]) represents the heat delivered, not limited by boiler size (infinite boiler capacity). A similar calculation was done further limiting the heat demand of the school and the clinic by the respective boiler size. This represents the heat effectively delivered. The average effective delivered heat was calculated for the entire data set with an array of selected boiler sizes for the school and the clinic and compared to the average heat delivered with infinite boiler size. The ratio (percentage) of these numbers represent the capability of the boilers to supply the maximum excess heat possible. Since the goal of the selection process is to maximize the effective delivered heat as a result of the combined effect of both boiler sizes, we calculated the impact of one boiler size by setting the other boiler size to 1000 kW (representing infinity). In reality, the boilers are controlled by supply temperature and excess wind availability. With this, they may or may not operate at the same time or at the same relative power setting. However, the boiler size should be large enough to be able to make use of the available excess power, independent of the operation of the other boiler. The results of the sizing calculation can be summarized in the following graph: Sand point excess wind - boiler sizing.docx 5 of 12 TDX Power Printed Copies are Uncontrolled 350 300 250 — 200 } L a 0 0 150 0 V N 100 50 0 75.00 % Sand Point Boiler size selection 80.00% 85.00% 90.00% 95.00% Total heat captured vs. available heat 140 120 100 3 Y 80 N .y d 0 60 -,0 40 20 0 100.004E C u As can be seen, the heat captured approaches 99.8% of the available heat with 260 kW boiler size for the school and 80 kW for the clinic. Increasing the boiler size beyond this will not result in a better use of the available excess wind energy. 2.3.4 Data Validation The daily data set was used to calculate the boiler size. Wind data is stochastic in nature-, during gusty days, the power output of the wind turbines can change significantly from one hour to the next. Since we had hourly data available (but with a limited set of data points)- we calculated the excess wind power for each data point for both the hourly and the daily data sets. We then presented the data in the form of a histogram to be able to visually compare the two data sets. Sand point excess wind - boiler sizing.docx 6of12 TDX Power Printed Copies are Uncontrolled 500 450 400 c 350 0 .y 300 a o 250 200 E Z 150 100 50 0 0 8000 7000 6000 5000 0 7 4000 a 0 3000 2000 1000 0 0 Histogram Excess Wind Power (daily data) 100 200 300 400 500 Excess Wind Power [kW] 600 700 Histogram Excess Wind Power (hourly data) 200 Sand point excess wind - boiler sizing.docx TDX Power 400 600 Bin size [kW] 7 of 12 100.0% 90.0% 80.0% y 70.0% 60.0% c 0 50.0% L d 40.0% 0 30.0% d u 20.0% a 10.0 % 0.0% 800 100.0 % 87.5 % 75.0% y' 0 .Y 62.5% y L a 50.0% o m w 37.5 E- j 25.0% " 12.5 % 0.0% 800 j Printed Copies are Uncontrolled The histograms show that the hourly data is actually a bit more evenly distributed than the daily data. If any accuracy was lost using the daily data, it would result in erring towards higher excess wind power and therefore slightly larger boiler size. 2.4 Boiler selection The above size calculation resulted in a utilization graph that gives an indication to the max. feasible boiler size. However, the actually selected boiler size depends on other factors as mentioned in 2.1 above. 2.4.1 Electrical Service Also considered was the feasibility of powering the electric boilers using the existing electric services in place for the school and clinic, including existing service transformers. Using the existing service transformer works well for the clinic, which has a 150kVA (120/208 V)service transformer and draws on average approx. 15 kW, with peak demand of approximately 31 kW. The conditions at the school are less favorable. The school has a 225kVA (277/480 V) transformer that is reasonably loaded and would not support an additional 270 kW of load based on the nominal rating. However, distribution transformers are typically and intentionally oversized and able to be overloaded on a short term basis. Also, the kVA rating is based on a relatively high ambient temperature. Typically, when there are heating demands and excess wind at Sand Point, ambient temperature is low and cooling conditions are optimal. TDX is considering installing temperature monitoring on the existing school transformer, such that the boiler power draw can be limited in the event of high transformer oil temperature. We feel this is worth pursuing, in that installing and maintaining a large service transformer is expensive, and incurs additional no load loss on a 365/24/7 basis. However, final selection is still pending. 2.4.2 Boiler specification Based on the above calculations, the site conditions and the control requirements, we developed a boiler specifications for both boilers, see attached. The boiler size target range specified: Clinic: 65...75...85 kW School: 240...270...300 kW 2.4.3 Boiler cost Boiler prices vary widely between manufacturers, but follow generally along the following criteria: r Vessel size. Most manufacturers have a limited set of vessel sizes to facilitate production. A given vessel size will accommodate a wide range of heating element power and arrangement. The vessel is the most expensive part of the boiler. Heating elements. The number and rating of heating elements used is dependent on the voltage, the capability of the controls (number of steps) and the power density. Higher number of elements cost more and require more (costly) electrical control elements. v Controls. The capability and refinement of the controls range widely. From simple thermostats to sophisticated PID controllers and multi -step controllers. Sand point excess wind - boiler sizing.docx 8 of 12 TDX Power Printed Copies are Uncontrolled While the cost of the boiler is a major cost contributor, the cost of the associated transformer and disconnect also must be considered. Using RSMeans cost data, we did a simple cost calculation for various boiler sizes to get an indication of the relative cost of the boiler and associated equipment: $200 $180 $160 $140 $80 E $60 $40 $20 $0 0 Relative Electric Boiler Equipment Cost +Boiler --tl—Transformer 12470 to 480 V — - Fused disconnect 480 V � —0—Total Poly. (Total) - 100 200 300 400 500 600 700 800 Boiler kW As expected, the relative cost ($/kW boiler size) generally favors larger boilers. The resulting total equipment cost is based on discreet values for boiler, transformer and disconnect. The up -tick at 370 kW is due to unfavorable step size of the transformer and disconnect (500 kVA, 600 A). Sand point excess wind - boiler sizing.docx 9of3.2 TDX Power Printed Copies are Uncontrolled 2.4.4 Boiler selection We obtained boiler quotes from four man ufacturerslrepresentatives and are in the process of reviewing them and make a final selection. Selection criteria: ➢ Adherence to specification ➢ Cost, including transportation ➢ Dimensions, orientation (smaller size preferred) Number and size of steps/elements ➢ Controllers used ➢ Ability to integrate into master control system ➢ Quality of documents and service received ➢ Previous experience with manufacturer/representative Sand point excess wind - boiler sizing.docx 10 of 12 TDX Power Printed Copies are Uncontrolled 3 Fuel Savings Projections Based on historical temperature and fuel consumption data for both buildings, for an average season (Normalized to the past 15 year average of heating -degree-day data) we made the following fuel consumption predictions: v On a 15 year average, the school is projected to burn 35270 gal, if fuel oil is the sole source of heat. The excess wind power is projected to save 16083 gal. This represents a fuel saving of 45.6%. i- On a 15 year average, the clinic is projected to burn 11778 gal, if fuel oil is the sole source of heat. The excess wind power is projected to save 5512 gal. This represents a fuel saving of 46.8%. The savings projection is based on two years of City load data and daily average wind speed as measured by the wind turbine anemometers, and boiler sizes of 270kW and 75kW respectively. It also assumes power plant genset minimum load of 180KW and the need to absorb 50kW of excess wind at the power plant for frequency regulation purposes. The projections also assume the school and clinic divide the excess energy proportionally based on these boiler sizes. Since the school and the clinic are powered from the same source, we can only make an accurate prediction for the combined fuel savings; the actual split between school and clinic depends on the actual heat demand, the existing boiler control modes and actual heating loop temperature variations etc.. However, the proposed electric boiler controls will allow to measure and adjust the excess wind power distribution if needed. Actual cost savings will depend upon the cost of fuel and rate for excess electricity, and will be addressed separately. Sand point excess wind - boiler sizing.docx 11 of 12 TDX Power Printed Copies are Uncontrolled 4 Appendix 4.1 Detailed boiler specification Sand point excess wind - boiler sizing.docx 12 of 12 TDX Power Printed Copies are Uncontrolled TOX power a tanadgusix company Sand Point Excess Wind Power Utilization Electric Boiler Specification Date 02/29/2016 Prepared by Dan Lenel TDX Power 615 E. 82nd Ave, Suite 200 Anchorage, AK 99518 www.tdxpower.com Contents Contents..................................................................................................................................................................2 1 Electrically heated water boiler 75 M..........................................................................................................3 1.1 Standard specification.................................................................................................................................3 1.2 Optional equipment.........................................•---•.......................................................................................4 2 Electrically heated water boiler 270 M........................................................................................................5 2.1 Standard specification.................................................................................................................................5 2.2 Optional equipment.....................................................................................................................................6 Sand Point boiler spec.docx 2 of 6 TDX Power Printed Copies are Uncontrolled 1 Electrically heated water boiler 75 kW 1.1 Standard specification Project name: Sand Point Excess Wind Item: Electric boiler for clinic Location: Sand Point, Alaska Seismic zone: 4 Ambient conditions: Indoor, 50...120 °F Rated heat output: 65...75...85 kW Electric power service: 3 phase 208 VAC Max. step size: 20% of heat output Working fluid: 50% Water150% ethylene glycol Working pressure: 30 psig Working temperature: max. 200 °F Pressure vessel: Welded steel vessel according to ASME boiler and pressure vessel code, section IV Insulation: Fiberglass or similar, minimum thickness 1.5" Boiler enclosure: Metal enclosure with easy access to heating- and control elements, rustproof. Controls enclosure: Integral to boiler enclosure or NEMA class 1 or 12 enclosure attached to boiler enclosure. Fluid connections: Flanged or threaded NPT Drain with shut-off valve, 112" minimum size Air vent: Automatic air vent/vacuum breaker with shut-off valve Safety valve: Approved and sized according to ASME boiler and pressure vessel code, section I. Heating elements: Individual heating elements rated for continuous duty, sheathed with high temperature, nickel -based material (i.e. Inconel). Elements shall be flanged or threaded and easily replaceable with only minimal disassembly required. Heating element switching: By 3-pole magnetic contactors with at least 500,000 full load cycles service life, or solid state relays with zero -crossover switching, or a combination of these. 3-pole circuit breaker for each element. Temperature controller: Electronic multi -stage PI controller with independent temperature sensor. Instrumentation: Pressure gauge with shut-off valve, dampened. Supply temperature gauge Sand Point boiler spec.docx 3 of 6 TDX Power Printed Copies are Uncontrolled Control panel: Operator control panel, integral to the boiler, with the following control elements: - Temperature controller - ON/OFF switch with indicator light - Indicator light for each heating element or stage - Disable switch for each heating element or stage - Alarm/trip indicator light Safety controls Low water cut-off Over -temperature limiter, self -resetting Over -temperature limiter, manual reset Control 110 Provide dry contact "boiler operating" Provide dry contact "boiler alarm" Provide dry contact "boiler trip" Provide terminals for safety shutdown loop. 1.2 Optional equipment Please quote all options as line items. Stage disable contacts: Power limit input: Additional control 110 Sand Point boiler spec.docx Wiring provision (terminal strip) for external in -line contacts that can break the control loop to each step contactor. Control input (4...20 mA or 0... 5...10VDC or ModBus) to the boiler stage controller to limit the max. boiler electrical load. Provide dry contact, opens on low water cut-out Provide dry contact, opens on over -temperature (auto IRS) Provide dry contact, opens on over -temperature (man IRS) 4 of 6 TDX Power Printed Copies are Uncontrolled 2 Electrically heated water boiler 270 M 2.1 Standard specification Project name: Sand Point Excess Wind Item: Electric boiler for school Location: Sand Point, Alaska Seismic zone: 4 Ambient conditions: Indoor, 50...120 °F Rated heat output: 240..270...300 kW Electric power service: 3 phase 480 VAC Max. step size: 20% of heat output Working fluid: 50% Water150% ethylene glycol Working pressure: 30 psig Working temperature: max. 200 °F Pressure vessel: Welded steel vessel according to ASME boiler and pressure vessel code, section IV Insulation: Fiberglass or similar, minimum thickness 1.5" Boiler enclosure: Metal enclosure with easy access to heating- and control elements, rustproof. Controls enclosure: Integral to boiler enclosure or NEMA class 1 or 12 enclosure attached to boiler enclosure. Fluid connections: Flanged or threaded NPi Drain with shut-off valve, 1/2" minimum size Air vent: Automatic air vent/vacuum breaker with shut-off valve Safety valve: Approved and sized according to ASME boiler and pressure vessel code, section I. Heating elements: Individual heating elements rated for continuous duty, sheathed with high temperature, nickel -based material (i.e. Inconel). Elements shall be flanged or threaded and easily replaceable with only minimal disassembly required. Heating element switching: By 3-pole magnetic contactors with at least 500,000 full load cycles service life, or solid state relays with zero -crossover switching, or a combination of these. 3-pole circuit breaker for each element. Temperature controller: Electronic multi -stage PI controller with independent temperature sensor. Instrumentation: Pressure gauge with shut-off valve, dampened. Supply temperature gauge Sand Point boiler spec.docx 5 of 6 TDX Power Printed Copies are Uncontrolled Control panel: Operator control panel, integral to the boiler, with the following control elements: - Temperature controller - ON/OFF switch with indicator light - Indicator light for each heating element or stage - Disable switch for each heating element or stage - Alarm/trip indicator light Safety controls Low water cut-off Over -temperature limiter, self -resetting Over -temperature limiter, manual reset Control 1/0 Provide dry contact "boiler operating" Provide dry contact "boiler alarm" Provide dry contact 'boiler trip" Provide terminals for safety shutdown loop. 2.2 Optional equipment Please quote all options as line items. Stage disable contacts: Power limit input: Additional control 1/0 Sand Point boiler spec.docx Wiring provision (terminal strip) for external in -line contacts that can break the control loop to each step contactor. Control input (4...20 mA or 0...5...I OVDC or ModBus) to the boiler stage controller to limit the max. boiler electrical load. Provide dry contact, opens on low water cut-out Provide dry contact, opens on over -temperature (auto RS) Provide dry contact, opens on over -temperature (man IRS) 6of6 TDX Power Printed Copies are Uncontrolled