HomeMy WebLinkAboutPtarmigan Lake-Creek Hydroelectric Project Alternative Energy Grant Proposal - Feb 2008 - REF Grant 2195335Homer Electric Association. Inc.
Corporate Office Cetttr;d Peninsula Service Center
1977 hak, Street 280 Airport WaN
Horner, Alaska 99603-7090 Kent€i, Alaska 9961
Phone 19071235-9551 11Itom; (907) _'83-4W 1
FAX 19(17) 2 5-3313 1'AN (907)-M-7I2?
PROJECT SPECIFIC INFORMATION
In support of the
ALTERNATIVE ENERGY GRANT PROPOSAL
PRECONSTRUCTION GRANT APPLICATION
For
PTARMIGAN LAKEICREEK PROJECT
Prepared by:
Homer Electric Association, Inc.
February 11, 2008
2008-02-11 AEA Aft Energy Giant App - Ptarmigan Lake ATouchstone Energy' Cooperative :
ALTERNATIVE ENERGY GRANT PROPOSAL
PRE CONSTRUCTION APPLICATION
Homer. Electric Association, Inc. — PTARMIGAN LAKE/CREEK PROJECT
PROJECT DESCRIPTION
HEA is evaluating the potential for a small, low -impact hydro facility utilizing the water resources
provided by Ptarmigan Lake/Creek. Ptarmigan Lake, which is located at an elevation of
approximately 800 ft MSL, flows into Ptarmigan Creek approximately 2.25 mi upstream of the
Seward Highway, about 2.5 mi southeast of the town of Crown Point in Kenai Peninsula
Borough, Alaska. The nearest major town is Seward, which is located approximately 26 miles
south of Crown Point. A map of the proposed project area is provided below,
The Ptarmigan Lake watershed is about 32 mi2, and the lake has an approximate surface area
of 815 acres. Ptarmigan Creek, which discharges into Kenai Lake, has an average annual flow
of 111 cubic feet per second (cfs). The project would generate power with approximately 235 ft
of head and have an anticipated generation capacity of about 4.0 MW.
As part of an initial assessment, information gathering will be undertaken to assess the
feasibility of constructing a dam andfor diversion dike to raise the surface elevation of Ptarmigan
Lake to increase storage for generation. The proposed project would have a siphon (or gravity
feed) intake in Ptarmigan Lake, near the point at which it flows into Ptarmigan Creek. Water
would be conveyed from the intake through a pipeline or penstock that would lead to a
powerhouse. The powerhouse would be located near the bank of Ptarmigan Creek and would
discharge into Ptarmigan Creek or Kenai Lake. The powerhouse tailrace would be designed to
carry the project flow to Ptarmigan Creek or Kenai Lake. The dimensions of the tailrace would
be developed based on terrain and other pertinent information to be obtained during the study
phase.
The project would include 2 — 4 mi of new overhead transmission line employing one of two
potential transmission options: 1) power generated at the powerhouse at low voltage would be
transmitted to a remote transformer, where it would be converted to 115 kV and connected to
February 11, 2008 Page 2 of 7
ALTERNATIVE ENERGY GRANT PROPOSAL
PRECONSTRUCTION APPLICATION
Homer Electric Association, Inc. — PTARMIGAN LAKE/CREEK PROJECT
the existing transmission grid or 2) power generated at the project would be transmitted directly
to the grid from a step-up transformer near the powerhouse.
The legal description and ownership of lands (ADNR 2006) within the proposed project
boundary are provided in the table below. All land is referenced to the Seward Meridian.
Unshaded rows pertain to the lake outlet and creek. Shaded rows include sections for the entire
Lakeshore.
Township
Range
Section
Ownership
4N
lE
South % of 19
State
4N
lE
South % of 20
USDA Forest Service
4N.
1E
27 ".
USDA Vorest Service
1E''
28
iJSDATorest-Service "_
4N
1E
29
USDA Forest Service
4N
lE
30
State
4N
1E
31
USDA Forest Service
oresYService.
FSDATbrest Service
3,5
USDA Forest Service ". .
4N
1W
25
Municipal
4N
1 W
36
USDA Forest Service
The project in its final form would likely consist of a dam, pipeline/penstock, powerhouse,
access road, and transmission lines. All improvements could potentially affect a combination of
federal, state, and private lands. No portion of the potential project area has been designated
as a Wilderness Area, recommended for designation as a Wilderness Area, or designated as
Wilderness Study Area, No portion of the project area has been included in the Wild and Scenic
River System.
Power from the project would be available to customers of Homer Electric Association and other
areas served by the existing transmission grid. Power from the proposed project would be
important to the citizens of the Kenai Peninsula and would be environmentally beneficial and
cost effective as an alternative source of energy to offset fossil fuel generation. The power from
the proposed project would reduce consumption of non-renewable carbon -based energy
sources, thereby helping to improve air quality in Kenai Peninsula Borough.
PROPOSED STUDY PROGRAM
The study program, which HEA hopes will culminate in the filing of a License Application with
FERC, would be conducted according to the Commission's licensing regulations.
Potential Study Program Elements
Engineering and feasibility
• Hydrology
• Bathymetry
February 11, 2008 Page 3 of 7
ALTERNATIVE ENERGY GRANT PROPOSAL
PRECONSTRUCTION APPLICATION
Homer Electric Association, Inc. — PTARMIGAN LAKE/CREEK PROJECT
• Stream gauging
• Dam stability and soils tests and analysis (if needed)
• Preliminary design, i.e., unit type and size
• Tunnel/pipeline alignment
• Evaluation of transmission line route
• Financial analysis
Environmental Studies
• Fish species composition
• Fish habitat assessment
• Rare, Threatened and Endangered (RTE) species inventory
• Vegetation
• Wildlife
• Recreation
• Cultural
• Aesthetics
• Project effects analysis
Stakeholder Consultation
HEA will consult with potential stakeholder entities (i.e., agencies, NGOs, Native Corporations,
and communities) early in the study phase to ensure that all significant concerns are addressed
and planned for in the studies in anticipation of the licensing process for the Ptarmigan Lake !
Ptarmigan Creek project.
MANAGEMENT & TECHNICAL CAPACITY
Homer Electric Association is a well established railbelt electric cooperative that has been
serving its members since 1945. The cooperative operates and maintains both fossil fuel and
hydroelectric generation facilities, including the 120MW Bradley Lake Hydroelectric Plant. Its
management and staff are well prepared to oversee the development of this small hydro facility
from its conception through construction and operation. Where needed, HEA will contract with
qualified firms and consultants to conduct the engineering, studies and detailed design
associated with the project.
PRECONSTRUCTION COST ESTIMATES & FINANCING
It is generally recognized that initial capital costs for alternative energy projects are significantly
higher than comparable fossil fuel generation assets, though the long-term benefits of
alternative energy projects can be substantial. Denali Commission and AEA funding can help to
offset some of these initial project screening and capital costs and contribute to the economic
and social viability of an eventual project. HEA is strategically planning to expand its generation
portfolio to include renewable energy sources. This application is one result of implementing this
February 11, 2009 Page 4 of 7
ALTERNATIVE ENERGY GRANT PROPOSAL
PRECONSTRUCTION APPLICATION
Homer Electric Association, Inc. — PTARMIGAN LAKE/CREEK PROJECT
planning effort. The purpose of this long-term vision is to provide more consistently priced,
environmentally responsible energy to balance the traditional generation resources currently
available.
One of the stated elements of the proposed study program is to develop a financial analysis or
model for the project. This will be one of the first tasks undertaken by HEA along with further
engineering feasibility study. The table below details the preconstruction costs that lead to a
FERC license application.
PRECONSTRUCTION STUDY PROGRAM ELEMENTS Budeet
Feasibility Evaluation (Financial & Engineering Models)
$ 100,000.00
Initiate Stakeholder Consultation
$
30,000.00
Prepare and file Pre -Application Document (PAD)
$
20,000.00
FERC Seeping
$
20,000.00
Proposed Study Plan (PSP)
$
20,000.00
Revised Study Plan (RSP)
$
20,000.00
Initiate Field Studies
$ 200,000.00
Complete Field Studies
$
25,000.00
Additional/Supplementary Data Collection
$
25,000.00
Draft License Application.
$
20,000.00
File License Application
$
20,000.00
Total Proposed Study Program
$ 500,000.00
The estimated cost of conducting studies, investigations, tests, surveys, mapping and
developing plans and specifications for the proposed Ptarmigan Lake I Ptarmigan Creek Project
is $500,000. AEA funding requested here will support the feasibility evaluation listed above.
Preconstruction funds will .initially be drawn from a combination of grant funding and internal
financing. Other options may be explored depending on the results of the preconstruction
assessments.
PRELIMINARY COSTS & BENEFIT -COST ESTIMATE
A preliminary benefit -cost estimate is provided in the spreadsheet on page 7. Assumptions
pertaining to power production, construction, financing and avoided costs are noted at the top of
the analysis. The costs and savings are brought to present worth in 2008 for comparison. The
benefit -cost ratio for this project is estimated at 1.93.
This paragraph will briefly describe the costs considered in the analysis. Once the project is past
the preconstruction phase and has entered a FERC licensing process, an additional one million
dollars is allocated for licensing, further studies and detailed design. Preliminary construction
capital costs for this 4.OMW project are estimated at $3,500IkW, or approximately $14,000,000.
The cost of this construction capital is amortized over a thirty year period. Operations &
Maintenance (0&M) costs are based on HEA experience and are escalated over the life of the
project. All these costs are brought to a 2008 present worth value of $35,114,669.
February 11, 2008 Page 5 of 7
ALTERNATIVE ENERGY GRANT PROPOSAL
PRECONSTRUCTION APPLICATION
Homer Electric Association, Inc. — PTARMIGAN LAKE/CREEK PROJECT
The project savings are estimated as HEA's avoided cost of purchasing power produced by
natural gas at $8.29/MMBtu in 2007 dollars. The avoided cost of power is escalated by 5% per
year over the project life and then brought to a present worth in 2008 equal to $67,788,522.
February 11, 2008 Page 6 of 7
ALTERNATIVE ENERGY GRANT PROPOSAL
PRECONSTRUCTION APPLICATION
Homer Electric Association, Inc. — PTARMIGAN LAKE/CREEK PROJECT
6
jd j
N
l�OisV
y
-
� t�i to Noma I°
Ay N rm Nl r 1
- 7 [ N 1 `� l ICSI � H- d •f m pY f r -fl
�IdOCb
ti. H.H4f}Uf49:�.yrafu+49:Hi��£9UtI�u44f9?f§li5dr�`R.�t?,�';!-YY49Ylt�iRbRIH�`H, 4.�.v
1 m mINyM1 m M `M1 M{ {M I[Sld N I[S N OItl3 3 1r r5z1�
_ N
V4
1 M M OJVVID 4ljd : N ILS} fMiCO lil fL3 dN tl M 1 I"� t N
I 6Yi61lY,f� f+_!h IICI 1�{{{ tl I[I 1� 001 0Y.16-a1 lO3d{{I
MI I
Il�tlHn
lldrym
III��dtl?N
6j}I
°
vN(�4'+9
Vb
m4B O4/l]� +il}m�f
Ihryle Co
II i �M169�:m�°IIIlI 4t(`rypil�iy`'�mdlell�ctryvn�.Nnri'{j'�NPn
N1�nMN67l� dw3 I, W4lyy �
Sj
11t I-
�.b�br
4BskkiMNth
�I rrH lrn Nf9
I �C a._j
/3333�E1E�(mrt4R{
^N4)
I f9l!1�€
- - I 9b9 , I49� I 49� Ib9 Vr641N�6f 6)
a
I ..
I f- I I 1313
G O t
3
{j I I LL] W3MImitl M M1 tl h �} M iL
M1i {,{
kM1dI1fll�m Ye�[J 4 Wad
d 0 Mt 3ml f`i h M I- 1 } I im
E , M1_ IlY N� IMMUNE
W W OS
i I 1 3 W I R[ 1€€
C�'
NIiN1 1tlftl
PRIOR.
IS9 6Y 49€4AI 1 { H� ,� F9 6) F9: ,f91Hi+91 fA.W,HjfM.H H W He IH{49 49i
I
'jjjjAUf
j , j
{ , j
a❑l
R(�l rtrd v^rj r
f�i �flf .".
I lnFnr µ[I
{1 1['S.
f i[C7S I r�N
p
°U
[E tui I �
{[ 1 fr'r {ICf
(S 5 `f1
Ny�ei'MtvFNlMrvi fMn
0 I I
� 1{niH}eS�Nfila4ivr{Hriw.aSFr+4YM j(lldi (�1:
tt H"'FI•H 6Y �49.vr;E3 EYi�'rIM-^4vri'9+H+4'��HjYt WIV`E5 4aW
[ I M�-Is'S-rowibl n'"'is,lr Ire'r Im, '.r a{.c. 'iu1 - m- I •--1'
p-U
rt F 1 r E
Ogg H i3 ' lL_:SF� 4l N yI Wif 4314�;� I
, 93im i.y a y" i NrffalW'4Y
-i - 1 - 1 - { E
f9 � i 13 i t 3
[]
I �, 1
i 1 ! 11 kl 1 i
aCIC
- j} -
�
C y3
,,
f)101 ,+r139 KiY 1 I I I ! i{ j-I-
1 1
F
pJ
%�
I IO III, 10 Ord N IM mim-l4 PId IF[)fOS�f) M31(rjM1l(4�431fr; �d -I dO m RM1 NlWI'.iN))lM rt m;tl WIC IDIrt�NiN
H 6? {9- 7749rFA,ml jjM}d 4'r. ENEm M �I iP W WI alwi WiC�O Iw w G !M I11°] I°�`ItlD h}IiY
i E^'7Jmi1M1IM1IWI01OG1 i O I}`m N NIryS GY DI pSIOliplmlltilM1 H" M1 WI N N}�tMl if.}.�
t [ Id N
HI1rN�IMIrd�
�
bl�m�yq'(gtb31 I ! N NiU4�N� NINI��[�IIC]i { iS3 Iln[�
� H', � F If9164591M,IfHF49idY 644/.+A. �bY �.61,4)F Ib9i61 IdIIM,d/,M•�f��M H4�.�'Vr{c9 �. '&!:d%Ib}k
i
} I f� E ,
N! I s
-WAS�S
�
!
W OSlro�AtM1'I IWI !�k Imo+
] �i��d4�f9441 b9 NHl b9F•N Vl (A-49:NiM 49 -
�,U c.'-
! .b9iM 6V 1p�Nfe49�4A]]]]]]'691yy'f9lyS�b4 i `
;
G"
_ d N
- 1 - rl{f� N,N•NIN NN�N.NiN�.M� � � -
♦-
btl�tl btlbb_olb btloro tl0'.O1 ] b�,P- - ! : I 'bitl: - � bb,b{tl
&I.HI.N'br b1 i949��:69W W�63.69'.W-HiR63,d1'S9K E96963ib9': b1 f9.Hf9 dl�fAt9(9:N:(A'.69(9.fA (9:&1; 63'6969:d1If9:dllH f9 t9: H:
UH
-
o M1 w whir In I°iur' _
❑a
1
y 1
>r '
o N,N I-
nw
N,N'N N NINi{�F�N N N N:t�v.N N N N.N:N NrN
February 11, 2008 Page 7 of 7