HomeMy WebLinkAboutSaint Mary's - Pitka Point Wing Energy Project Conceptual Design Report - Sep 2012 - REF Grant 7040017Saint Mary's, Alaska Wind Power
Conceptual Design Analysis
September 17, 2012
Douglas Vaught, P.E.
dvaught@v3energy.com
V3 Energy, LLC
Eagle River, Alaska
V3 ENERGY LLC
Eagle River, Alaska 907.350.5047
Saint Mary's, Alaska Wind Power Conceptual Design Analysis P a g e I i
This report was prepared by V3 Energy, LLC under contract to Alaska Village Electric Cooperative to
assess the technical and economic feasibility of installing wind turbines at the Pitka's Point wind site
near the villages of Saint Mary's and Pitka's Point. This analysis is part of a conceptual design report and
final project design funded in Round IV of the Renewable Energy Fund administered by Alaska Energy
Authority
Contents
Introduction..................................................................................................................................................1
Synopsis of Economic Modeling Results...................................................................................................1
Villageof St. Mary's/Andreafsky...............................................................................................................1
Wind Resource at Pitka's Point and Saint Mary's.........................................................................................2
WindSpeed...............................................................................................................................................4
ExtremeWinds..........................................................................................................................................5
WindDirection..........................................................................................................................................6
Temperatureand Density.........................................................................................................................6
Wind -Diesel System Design and Equipment.................................................................................................7
DieselPower Plant....................................................................................................................................8
WindTurbines...........................................................................................................................................8
NorthernPower 100 ARCTIC.................................................................................................................8
EWT52-900............................................................................................................................................ 9
LoadDemand................................................................................................................................................ 9
St. Mary's Electric Load.............................................................................................................................9
Combined Saint Mary's-Pilot Station Electric Load................................................................................10
ThermalLoad..........................................................................................................................................11
DieselGenerators...................................................................................................................................11
WASP Modeling, Wind Turbine Layout.......................................................................................................12
OrographicModeling..............................................................................................................................12
WindTurbine Project Site.......................................................................................................................14
Northern Power 100 ARCTIC Turbine Layout.........................................................................................14
WASP Modeling Results for Northern Power 100 ARCTIC Array........................................................14
EWT52-900 Turbine Layout....................................................................................................................16
WASP Modeling Results for EWT 52-900 Turbine...............................................................................16
EconomicAnalysis.......................................................................................................................................18
V3 ENERGY LLC
Cagle River, Alaska 907.3503047
Saint Mary's, Alaska Wind Power Conceptual Design Analysis P a g e I ii
WindTurbine Costs.................................................................................................................................18
St. Mary's to Pilot Station Intertie Cost..................................................................................................18
FuelCost..................................................................................................................................................19
ModelingAssumptions...........................................................................................................................19
Homer Software Modeling Results.........................................................................................................22
Configuration 1: St. Mary's Only; No Intertie to Pilot Station, NP 100 Turbine Option ....................22
Configuration 2: St. Mary's Only; No Intertie to Pilot Station, EWT Turbine Option .........................23
Configuration 3: St. Mary's Intertied to Pilot Station, EWT Turbine Option......................................24
Appendix A, WASP Wind Farm Report, Pitka's Point Site, NP 100 Turbines...............................................25
Appendix B, WAsP Turbine Site Report, Pitka's Point Site, EWT Turbine...................................................26
Appendix C, HOMER System Report, St. Marys, 3 NP 100 Turbines..........................................................27
Appendix D, HOMER System Report, St. Mary's, 1 EWT-500 Turbine........................................................28
Appendix E, HOMER System Report, St. Mary's + Pilot Station, 1 EWT-500 Turbine.................................29
V3 ENERGY LLC
Cagle River, Alaska 907.3503047
Saint Marys, Alaska Wind Power Conceptual Design Analysis P a g e 1 1
Introduction
Alaska Village Electric Cooperative (AVEC) is the electric utility for the City of Saint Mary's/Andreafsky as
well as the interconnected village of Pitka's Point. AVEC was awarded a grant from the Alaska Energy
Authority (AEA) to complete feasibility and design work for installation of wind turbines, with planned
construction in 2014.
Wind resource studies of the St. Mary's area began in 2007 with identification of possible wind turbine
sites on Pitka's Point Corporation land and Saint Mary's corporation land, located relatively near each
other between the villages of Saint Mary's and Pitka's Point. Both sites were equipped with 40 meter
met towers, but the Pitka's Point site eventually proved to have the superior wind resource and was
chosen as the primary site for conceptual design and feasibility work.
CRW Engineering Group, LLC was contracted by AVEC to develop a conceptual design report and design
package for a wind turbine project in Saint Mary's. This analysis is a component of that larger effort.
Synopsis of Economic Modeling Results
Three wind turbine options were modeled for energy balance and economic benefit and cost with
Homer software.
• Configuration 1 considers three Northern Power 100 turbines serving only the Saint Mary's
electrical and thermal load.
• Configuration 2 serves the same load, but substitutes one EWT 52-900 turbine in place of the
Northern Power turbines.
• Configuration 3 maintains use of the EWT turbine, but adds the Pilot Station electrical load via
construction of an intertie.
Basic economic modeling results are presented in the table below.
Project configuration economic modeling results
Configuration
Wind Turbine Type and Electric Loads
Benefit -to -Cost
Simple Payback
No.
Served
Ratio
Period
1
NP 100's; Saint Mary's
0.94
n/a
2
EWT 52-900; Saint Mary's
1.03
13.6 years
3
EWT 52-900; Saint Mary's + Pilot Station
1.06
10.9 years
Village of St. Mary's/Andreafsky
St. Mary's is located 450 air miles west-northwest of Anchorage on the north bank of the Andreafsky
River, five miles from its confluence with the Yukon River. The City of St. Mary's encompasses the Yupik
villages of St. Mary's and Andreafsky. St. Mary's is a Yupik Eskimo community that maintains a fishing
and subsistence lifestyle. The sale of alcohol is prohibited in the city. According to Census 2010, 507
people live in St. Mary's and Andreafsky. There are 209 housing units in the community and 151 are
occupied. Its population is 91.5 percent Alaska Native, 3.8 percent Caucasion, and 4.7 percent multi-
racial.
V3 ENERGY LLC
Eagle River, Alaska 907.3503047
Saint Marys, Alaska Wind Power Conceptual Design Analysis
Page 12
Water is derived from Alstrom Creek reservoir and is
treated. Most homes in the village have complete plumbing
and are connected to the piped water and sewer system.
Waste heat from the power plant supports the circulating
water system. A 1.7-million-gallon sewage lagoon provides
waste treatment. A washeteria is available nearby at Pitka's
Point. An unpermitted landfill is shared with Pitka's Point.
Electricity is provided by AVEC with interconnection to the
village of Pitka's Point and the St. Mary's airport (station
code KSM). There is one school located in the community, attended by 185 students. There is a local
health clinic staffed by a health practitioner and four health aides. Emergency Services have river,
limited highway, and air access.
Wind Resource at Pitka's Point and Saint Mary's
The wind resource measured at the Pitka's Point met tower site is outstanding with measured wind
power class 6 by measurement of wind power density and wind speed. Extensive wind resource analysis
has been conducted in the Saint Mary's region, with met towers at a lower elevation site closer to the
village of Saint Mary's and near Mountain Village, in addition to the Pitka's Point met tower.
Documented in Saint Mary's Area Wind Power Report by V3 Energy, LLC, dated July 20, 2010, the wind
resource measured at the nearby Saint Mary's met tower site is less robust than that measured at
Pitka's Point and appears to experience similar icing problems. The Mountain Village wind resource is
very good as well with mean wind speed near that measured at Pitka's Point. Considering the inland
location of Saint Mary's/Pitka's Point, the wind resource measure at the Pitka's Point met tower site is
highly unusual, and very favorable, with its combination of a high annual average wind speed, relatively
low elevation, likely good geotechnical conditions, and proximity to existing roads and infrastructure.
A 40 meter NRG Systems, Inc. tubular -type meteorological (met) tower was installed on Pitka's Point
Native Corporation land on the bluff immediately above the Yukon River with excellent exposure to
northeasterly winds down the Andreafsky River, northerly winds from the mountains and southerly
winds from the flat, tundra plains leading toward Bethel. The met tower site is near an active rock
quarry and visual inspection of that quarry indicates the likelihood of excellent geotechnical conditions
for wind turbine foundations. Also of advantage for the site is near proximity of the road connecting
Saint Mary's to Pitka's Point, the airport and Mountain Village. A two-phase power distribution line
(connecting the St. Mary's powerplant to Pitka's Point as one phase and to the airport as the second
phase) routes on the south side of the road. This line could be upgraded to three-phase at minimal cost
to connect wind turbines to three-phase distribution in Saint Mary's.
The Pitka's Point wind resource is comprehensively described in Pitka's Point, Alaska Wind Resource
Report by V3 Energy, LLC, dated April 25, 2012.
Pitka's Point met tower data synopsis
Data dates October 26, 2007 to February 12, 2009 (16 months)
Wind power class Class 6 (excellent), based on wind power density
V3 ENERGY LLC
Eagle River, Alaska 907.3503047
Saint Marys, Alaska Wind Power Conceptual Design Analysis
Page 13
Wind power density mean, 38 m
Wind speed mean, 38 m
Max. 10-min wind speed
Maximum 2-sec. wind gust
Weibull distribution parameters
Wind shear power law exponent
Roughness class
IEC 61400-1, 3rd ed. classification
Turbulence intensity, mean (at 38 m)
Calm wind frequency (at 38 m)
558 W/mZ
7.62 m/s (17.0 mph)
29.5 m/s
26.3 m/s (81.2 mph), January 2008
k = 1.93, c = 8.63 m/s
0.176 (low)
2.09 (description: few trees)
Class II-c (at 38 meters)
0.076 (at 15 m/s)
20% (< 4 m/s) (16 mo. measurement period)
Google Earth image, Pitka's Point and Saint Mary's
Pitka's Point met tower location
sla. J �- _Y m
i
V3 ENERGY LLC
Eagle River, Alaska 907.3503047
Saint Marys, Alaska Wind Power Conceptual Design Analysis
Page 14
Wind Speed
Anemometer data obtained from the met tower, from the perspectives of both mean wind speed and
mean wind power density, indicate an outstanding wind resource. Note that cold temperatures
contributed to a higher wind power density than standard conditions would yield for the measured
mean wind speeds.
Anemometer data summary
Speed 38 Speed 29 Speed 28 Speed 21
Variable m m m IceFree m
Measurement height (m)
Mean wind speed (m/s)
MoMM wind speed (m/s)
Median wind speed (m/s)
Max wind speed (m/s)
Weibull k
Weibull c (m/s)
Mean power density (W/m2)
MoMM power density (W/m2)
Mean energy content (kWh/mz/yr)
MoMM energy content (kWh/mZ/yr)
Energy pattern factor
Frequency of calms (%) (< 4 m/s)
MoMM = mean of monthly means
38
28.8
28.2
21
7.68
7.29
7.33
6.83
7.62
7.24
7.33
6.78
7.20
6.80
7.00
6.40
29.50
29.20
27.50
28.40
1.94
1.89
2.22
1.88
8.64
8.20
8.26
7.68
573
502
441
414
559
490
441
404
5,015
4,396
3,861
3,627
4,897
4,294
3,861
3,541
1.95
2.00
1.73
2.01
20.4
21.9
17.6
24.7
Time series calculations indicate high mean wind speeds during the winter months with more moderate,
but still relatively high, mean wind speeds during summer months. This correlates well with the Saint
Mary's/Andreafsky/Pitka's Point village load profile where winter months see high demand for
electricity and heat and the summer months have lower demand for electricity and heat. The daily wind
profiles indicate relatively even wind speeds throughout the day with slightly higher wind speeds during
night hours.
38 m anemometer data summary
Max
Max 10-
gust (2
Std.
Weibull
Weibull
Mean
Median
min avg
sec)
Dev.
k
c
Month
(m/s)
(m/s)
(m/s)
(m/s)
(m/s)
(-)
(m/s)
Jan
10.17
10.70
29.5
35.9
5.34
1.97
11.45
Feb
9.21
9.20
20.1
23.3
4.07
2.41
10.36
Mar
8.62
8.50
21.8
26.3
4.33
2.07
9.71
Apr
7.98
7.80
16.9
20.6
2.83
3.05
8.90
May
7.27
6.90
21.8
27.1
3.67
2.06
8.19
Jun
5.70
5.80
13.2
15.3
2.62
2.28
6.40
Jul
7.98
7.70
21.7
26.3
3.33
2.55
8.99
Aug
5.89
5.70
15.3
17.9
2.95
2.05
6.62
V3 ENERGY LLC
Eagle River, Alaska 907.3503047
Saint Marys, Alaska Wind Power Conceptual Design Analysis
Page 15
Sep
6.37
6.70
12.5
16.8
2.44
2.85
7.11
Oct
6.80
6.60
20.1
24.8
3.81
1.80
7.62
Nov
7.32
6.40
24.1
29.8
4.48
1.72
8.23
Dec
8.97
8.90
22.9
27.5
4.69
1.95
10.07
Annual
7.62
7.20
29.5
35.9
4.09
1.94
8.64
Monthly time series, mean wind speeds
Extreme Winds
A modified Gumbel distribution analysis, based on monthly maximum winds vice annual maximum
winds, was used to predict extreme winds at the Pitka's Point met tower site. Sixteen months of data
though are minimal at best and hence results should be viewed with caution. Nevertheless, with data
available the predicted Vref (maximum ten-minute average wind speed) in a 50 year return period (in
other words, predicted to occur once every 50 years) is 41.6 m/s. This result classifies the site as Class II
by International Electrotechnical Commission 61400-1, 3rd edition (IEC3) criteria. IEC extreme wind
probability classification is one criteria - with turbulence the other- that describes a site with respect to
suitability for particular wind turbine models. Note that the IEC3 Class II extreme wind classification,
which clearly applies to the Pitka's Point met tower site, indicates relatively energetic winds and
turbines installed at this location should be IEC3 Class II rated.
Site extreme wind probability table, 38 m data
Period (years)
Vref
(m/s)
Gust
(m/s)
IEC 61400-1, 3rd ed.
Class Vref, m/s
3
29.2
35.5
1 50.0
10
35.4
43.1
II 42.5
20
37.0
45.0
111 37.5
30
39.6
48.2
designer-
50
41.6
50.6
S
specified
100
44.2
53.8
average gust factor:
1.22
V3 ENERGY
LLC
Cagle River, Alaska 907.3503047
Saint Marys, Alaska Wind Power Conceptual Design Analysis
Page 16
Wind Direction
Wind frequency rose data indicates that winds at the Pitka's Point met tower site are primarily bi-
directional, with northerly and east -northeasterly winds predominating. The mean value rose indicates
that east -northeasterly winds are of higher intensity than northerly winds, but interesting, the
infrequent south -southeasterly winds, when they do occur, are highly energetic and likely indicative of
storm winds.
Wind frequency rose (38 m vane)
Wind Frequency Rose
Wind energy rose (38 m anem.)
Total Wind Energy (38 m�
iw• �` ,a
330` s.
Temperature and Density
The Pitka's Point met tower site experiences cool summers and cold winters with resulting higher than
standard air density. Calculated annual air density during the met tower test period exceeds the 1.204
kg/m3standard air density for a 177 meter elevation by 5.7 percent. This is advantageous in wind power
operations as wind turbines produce more power at low temperatures (high air density) than at
standard temperature and density.
Temperature and density table
Month
Mean
('F)
Min
('F)
Temperature
Max Mean
('F) ('C)
Min
('C)
Max
('C)
Mean
(kg/m3)
Air Density
Min
(kg/m')
Max
(kg/m')
Jan
4.7
-20.2
39.0
-15.1
-29.0
3.9
1.325
1.204
1.416
Feb
4.1
-24.7
32.4
-15.5
-31.5
0.2
1.343
1.264
1.430
Mar
11.0
-14.3
38.8
-11.7
-25.7
3.8
1.275
1.204
1.397
Apr
19.5
-6.3
44.2
-7.0
-21.3
6.8
1.299
1.235
1.372
May
39.4
13.8
65.5
4.1
-10.1
18.6
1.247
1.185
1.314
Jun
49.2
29.5
70.2
9.5
-1.4
21.2
1.223
1.174
1.272
Jul
50.5
37.9
81.9
10.3
3.3
27.7
1.220
1.149
1.250
V3 ENERGY LLC
Cagle River, Alaska 907.3503047
Saint Marys, Alaska Wind Power Conceptual Design Analysis
Page 17
Aug
51.3
33.1
70.9
10.7
0.6
21.6
1.218
1.173
1.263
Sep
45.1
30.0
64.6
7.3
-1.1
18.1
1.233
1.187
1.270
Oct
22.7
5.0
37.2
-5.2
-15.0
2.9
1.290
1.252
1.339
Nov
16.3
-14.6
44.6
-8.7
-25.9
7.0
1.308
1.234
1.398
Dec
13.9
-16.2
45.0
-10.1
-26.8
7.2
1.307
1.204
1.403
Annual
27.4
-24.7
81.9
-2.5
-31.5
27.7
1.273
1.149
1.430
Wind -Diesel System Design and Equipment
Wind -diesel power systems are categorized based on their average penetration levels, or the overall
proportion of wind -generated electricity compared to the total amount of electrical energy generated.
Commonly used categories of wind -diesel penetration levels are low penetration, medium penetration,
and high penetration. The wind penetration level is roughly equivalent to the amount of diesel fuel
displaced by wind power. Note however that the higher the level of wind penetration, the more
complex and expensive a control system and demand -management strategy is required. This is a good
compromise between of displaced fuel usage and relatively minimal system complexity and is AVEC's
preferred system configuration. Installation of three Northern Power 100 wind turbines or one
EWT52/54-900 wind turbine at the Pitka's Point would be configured at the medium penetration level.
Categories of wind -diesel penetration levels
Penetration
Penetration Level
Operating characteristics and system requirements
Instantaneous
Average
Low
0% to 50%
Less than
Diesel generator(s) run full time at greater than minimum
20%
loading level. Requires minimal changes to existing diesel
control system. All wind energy generated supplies the
village electric load; wind turbines function as "negative
load" with respect to diesel generator governor response.
Medium
0% to 100+%
20%to
Diesel generator(s) run full time at greater than minimum
50%
loading level. Requires control system capable of
automatic generator start, stop and paralleling. To control
system frequency during periods of high wind power input,
system requires fast acting secondary load controller
matched to a secondary load such as an electric boiler
augmenting a generator heat recovery loop. At high wind
power levels, secondary (thermal) loads are dispatched to
absorb energy not used by the primary (electric) load.
Without secondary loads, wind turbines must be curtailed
to control frequency.
High
0% to 150+%
Greater
Diesel generator(s) can be turned off during periods of
(Diesels -off
than 50%
high wind power levels. Requires sophisticated new
Capable)
control system, significant wind turbine capacity, secondary
(thermal) load, energy storage such as batteries or a flywheel,
and possibly additional components such as demand -
managed devices.
HOMER energy modeling software was used to analyze the Saint Mary's power System. HOMER was
designed to analyze hybrid power systems that contain a mix of conventional and renewable energy
V3 ENERGY LLC
Eagle River, Alaska 907.3503047
Saint Marys, Alaska Wind Power Conceptual Design Analysis
Page 18
sources, such as diesel generators, wind turbines, solar panels, batteries, etc. and is widely used to aid
development of Alaska village wind power projects.
Diesel Power Plant
Electric power (comprised of the diesel power plant and the electric power distribution system) in Saint
Mary's is provided by AVEC. The existing power plant in Saint Mary's consists of one Cummins diesel
generator model QSX15G9 rated at 499 kW output, and two Caterpillar diesel generators, a model 3508
rated at 611 kW output and a model 3512 rated at 908 kW output.
St. Mary's power plant diesel generators
Generator Electrical Capacity Diesel Engine Model
1 499 kW Cummins QSX15G9
2 611 kW Caterpillar 3508
3 908 kW Caterpillar 3512
Wind Turbines
This report considers installation of three Northern Power 100 ARCTIC turbines for 300 kW installed
wind capacity to serve only the Saint Mary's load, or one EWT 52-900 for 900 kW installed wind capacity
to serve Saint Mary's initially but then both Saint Mary's and Pilot Station upon completion of the
intertie, which can be considered a companion project. With capacity considerations, three Northern
Power 100 turbines best match the St. Mary's load while the EWT52-900 turbine, given its much higher
energy output, works best when serving an intertied St. Mary's-to-Pilot Station load.
Northern Power 100 ARCTIC
The Northern Power 100 ARCTIC, formerly known as the Northwind 100 (NW100) Arctic, is rated at 100
kW and is equipped with a permanent magnet, synchronous generator, is direct drive (no gearbox), and
is equipped with heaters and has been tested to ensure operation in extreme cold climates. The turbine
has a 21 meter diameter rotor operating at a 37 meter hub height. The turbine is stall -controlled and in
the proposed version will be equipped with an arctic package enabling continuous operation at
temperatures down to -40' C. The Northern Power 100 ARCTIC is the most widely represented village -
scale wind turbine in Alaska with a significant number of installations in the Yukon-Kuskokwim Delta and
on St. Lawrence Island. The Northern Power 100 ARCTIC wind turbine is manufactured in Barre,
Vermont, USA. More information can be found at http://www.northernpower.com/. The turbine
power curve is shown below.
Northern Power 100 ARCTIC power curve
12fl
§ 30
ak
0
5 10 15 24 25
Wind Speed (mfs)
V3 ENERGY LLC
Cagle River, Alaska 907.3503047
Saint Marys, Alaska Wind Power Conceptual Design Analysis
Page 19
EWT52-900
The EWT52-900 is an IEC Class II -A wind turbine rated at 900 kW, equipped with a direct drive,
permanent magnet, synchronous generator, a 52 meter diameter rotor, and 40, 50 or 75 meter high
towers. The turbine is pitch -controlled, variable speed, and can be equipped with an arctic package
enabling continuous operation at temperatures down to -40' C. A variant of this turbine is the EWT54-
900 which is identical to the EWT52-900 but equipped with a 54 meter diameter rotor and limited to IEC
Class III sites. The wind resource analysis of the Pitka's Point met tower indicated sufficiently strong
wind gust potential to classify the site as IEC Class II by extreme wind probability (see earlier discussion
in this report).
Three EWT-900 wind turbines are presently operational in Alaska, one in Delta Junction and two in
Kotzebue. The EWT52-900 wind turbine is manufactured in Amersfoort, The Netherlands, with North
American representation in Bloomington, Minnesota. More information can be found at
http://www.ewtinternational.com/?id=4 . The turbine power curve is shown below.
EWT52-900 power curve
1,)04)
80D
Ymy ?D�}
T 4DD
a
�NO
Load Demand
Power C u rve
WimF 5pacdimisf
This analysis includes stand-alone electric and thermal load demand in St. Mary's (which includes
Andreafsky and Pitka's Point) and the combined electric load demand of St. Mary's and nearby Pilot
Station once the proposed electrical intertie is complete.
St. Mary's Electric Load
Saint Mary's/Andreafsky load data, collected from December 26, 2009 to October 27, 2011, was
received from Mr. Bill Thompson of AVEC. These data are in 15 minute increments and represent total
electric load demand during each time step. The data were processed by adjusting the date/time
stamps nine hours from GMT to Yukon/Alaska time, multiplying each value by four to translate kWh to
kW (similar to processing of the wind turbine data), and creating a January 1 to December 31 hourly list
for export to HOMER software. The resulting load is shown graphically below. Average load is 354 kW
with a 621 kW peak load and an average daily load demand of 8,496 kWh.
V3 ENERGY LLC
Cagle River, Alaska 907.3503047
Saint Marys, Alaska Wind Power Conceptual Design Analysis
Page 110
Seasonal Profit&
,rare reo niar APr May dun Jul xug pep iJel now l.re-- Puin
St. Mary's electric load
TD8
ODD
FAS
Y 4D-D����yy ���yy
0 ++4
O W D
2D8
9 im
500
M
550
550
450
,'_50
250
150
0 12 18 24 ♦] ' '' !
NCY Jan eh r ia- Apr hlayJun Jul Aug Sep'Oct r6ov Qec
Combined Saint Mary's-Pilot Station Electric Load
Pilot Station is not equipped with automated logging equipment to document the electric load. But,
with plant operator logs, AVEC tracks the electric load which is documented in AVEC's annual generation
report and also in the power cost equalization reports that AVEC submits to Regulatory Commission of
Alaska. It is assumed that the Pilot Station electrical load is similar to that of St. Mary's load on a daily
and monthly basis. Hence, the measured St. Mary's load was scaled to a daily load demand of 13,726
kWh to represent a combine St. Mary's-Pilot Station electrical system when the intertie is complete.
St. Mary's-Pilot Station combined electric load
1.1100 Seas Ona
J.
n 800
Y
0
oTA
2Dfl '
i 4D0
dan rea roser Apr rosy jWT Jui Aug pep Lra NOW ueo Ann
V3 ENERGY LLC
Cagle River, Alaska 907.3503047
2�
V
Max
,�F+ly hig
msaie
daily Jaw
rein
k
98d
J340
700
5b0
420
20
Saint Marys, Alaska Wind Power Conceptual Design Analysis P a g e 111
Thermal Load
The thermal load demand in St. Mary's is well quantified and described in a report entitled St. Mary's,
Alaska Heat Recovery Study, prepared for the Alaska Energy Authority by Alaska Energy and Engineering,
Inc. and dated August 31, 2011. This report is quite comprehensive and won't be summarized here.
Thermal load data needed for HOMER modeling was extracted from a heat demand/heat available
graph on page 5 of the report. Monthly thermal heat demand is graphed as a heating fuel equivalent in
gallons per month, which was converted to kW demand with a conversion of 0.0312 gallons heating fuel
per kWh. Although not entirely precise, the monthly heat demand was equalized across the entire day
for each month and then randomized a bit with a five percent day-to-day and five percent time step -to -
time step random variability. Resulting thermal load is show below.
Saint Mary's thermal load
WD
4g 0
� 3r00
(U 200
0
J
19a
g
dan reo Nier Apr Way run Jul rug pep kAm rrov vec Ann
?70
i 200
03
0 190
4
0 B 12 1S 24
Hour
24
0
.wady hr,
near
gaily lax
n-ir
k
440
2W
200
200
120
40
Diesel Generators
The HOMER model was constructed with all three St. Mary's generators. For cost modeling purposes,
AEA assumes a generator O&M cost of $0.020/kWh. For HOMER modeling purposes, this was converted
to $2.50/operating hour for each diesel generator. Other diesel generator information pertinent to the
HOMER model is shown in the table below. Note that the Saint Mary's power plant operates is
equipped with automated switchgear and can operate in automatic mode with generators in parallel.
Diesel generator HOMER modeling information
Diesel generator
Cummins
Caterpillar
Caterpillar
QSX15G9
3508
3512
Power output (kW)
499
611
908
Intercept coeff. (L/hr/kW
rated)
.0222
0.0233
0.0203
Slope (L/hr/kW output)
0.215
0.238
0.233
Minimum electric
0%
0%
0%
load (%)
(0 kW)
(0 kW)
(0 kW)
V3 ENERGY LLC
Cagle River, Alaska 907.3503047
Saint Marys, Alaska Wind Power Conceptual Design Analysis
Page 112
Diesel generator
Cummins
Caterpillar
Caterpillar
QSX15G9
3508
3512
Heat recovery ratio (% of
waste heat that can serve the
22
22
22
thermal load)
Intercept coefficient —the no-load fuel consumption of the generator divided by its capacity
Slope — the marginal fuel consumption of the generator
Fuel efficiency curve,
QSX15G9
0 20 40 80
otttpur.I%)
Electrical — Tlaarrnel
Fuel efficiency curve, Cat
3508
40
W
m
.221)
10
0
90 100
Fuel efficiency curve, Cat
3508
1D
Fa
4a
CBD
m
� 20
10
Ouiptrt {46} Output {%)
Toth Electrical — Tterrnl — Total EW_ctricad — Tharmal — Total
WASP Modeling, Wind Turbine Layout
WASP (Wind Atlas Analysis and Application Program) and is PC -based software for predicting wind
climates, wind resources and power production from wind turbines and wind farms and was used to
model the Pitka's Point terrain and wind turbine performance.
WAsP software calculates gross and net annual energy production (AEP) for turbines contained within
wind farms, such as an array of two or more turbines in proximity to each other. For s single turbine
array, WASP calculates gross AEP. With one turbine, net AEP is identical to gross AEP as there is no wake
loss to consider.
Orographic Modeling
WAsP modeling begins with import of a digital elevation map (DEM) of the subject site and surrounding
area and conversion of coordinates to Universal Transverse Mercator (UTM). UTM is a geographic
coordinate system that uses a two-dimensional Cartesian coordinate system to identify locations on the
surface of Earth. UTM coordinates reference the meridian of its particular zone (60 longitudinal zones
are further subdivided by 20 latitude bands) for the easting coordinate and distance from the equator
for the northing coordinate. Units are meters. Elevations of the DEMs are converted to meters if
necessary for import into WASP software.
A met tower reference point is added to the digital elevation map, wind turbine locations identified, and
a wind turbine(s) selected to perform the calculations. WASP considers the orographic (terrain) effects
on the wind (plus surface roughness and obstacles) and calculates how wind flow increases or decreases
at each node of the DEM grid. The mathematical model has a number of limitations, including the
assumption of overall wind regime of the turbine site is the same as the met tower reference site,
prevailing weather conditions are stable over time, and the surrounding terrain at both sites is
V3 ENERGY LLC
Cagle River, Alaska 907.3503047
Saint Marys, Alaska Wind Power Conceptual Design Analysis
113
sufficiently gentle and smooth to ensure laminar, attached wind flow. WAsP software is not capable of
modeling turbulent wind flow resulting from sharp terrain features such as mountain ridges, canyons,
shear bluffs, etc.
Orographic modeling of the wind across the site, with the Pitka's Point met tower as the reference site,
indicates an outstanding wind resource on the top edge of the bluff, especially downhill from the met
tower toward the Yukon River and the village of Pitka's Point.
Orographic modeling of Pitka's Point site area, plan view
Orographic modeling of Pitka's Point site area, view to west
V3 ENERGY LLC
Eagle River, Alaska 907.3503047
Saint Marys, Alaska Wind Power Conceptual Design Analysis P a g e 114
Wind Turbine Project Site
The project site is Pitka's Point Native Corporation land on and near the location of the Pitka's Point met
tower, with boundaries of the Pitka's Point/Saint Mary's Airport road to the north, a rock quarry to the
east, the bluff to the south, and a Native Allotment to the west. More specifically, AVEC has obtained
site control on Lot 6 within these general boundaries for turbine siting. Site control of Lot 6 is adequate
to site one EWT52-900 turbine, but lease rights to additional Pitka's Point Native Corporation property
on the bluff edge would be necessary for an ideal layout of Northern Power 100 turbines.
It is important to note that winds at the project site, though very robust as a Class 6 wind resource, are
prone to rime icing conditions in winter. Rime icing is more problematic for wind turbine operations
than freezing rain (clear ice) given its tenacity and longevity in certain climatic conditions. Anti -icing
and/or de-icing features may be necessary to sustain availability during the winter months.
Northern Power 100 ARCTIC Turbine Layout
The Northern Power turbines are located on the bluff edge, which is on and near Lot 6 on Pitka's Point
Native Corporation land. Using WAsP software, turbine locations were selected that have high gross
energy production based on predicted site wind speeds, but at the same time result in minimal array
loss, thus yielding a high net energy production.
NP 100 Turbine Layout
Turbine UTM (easting, northing) Latitude, Longitude
NP 100 wtg 1 Zone 3V 591577, 6879392 62.035691° N, 163.24939° W
NP 100 wtg 2 Zone 3V 591646, 6879471 62.036383° N, 163.24803° W
NP 100 wtg 3 Zone 3V 591715, 6879552 62.037093° N, 163.24667° W
WASP Modeling Results for Northern Power 100 ARCTIC Array
The following table presents the WASP software analysis of energy production and capacity factor
performance of the Northern Power 100 in a three turbine array at 100% turbine availability (percent of
time that the turbine is on-line and available for energy production). The Northern Power 100 performs
very well in the Pitka's Point wind regime with excellent annual energy production and minimal array
wake loss.
Note that the standard (atmospheric conditions) power curve was compensated to the measured mean
annual site air density of 1.273 kg/ m3. For the stall -controlled Northern Power 100, power output (for
each m/s wind speed step) of the standard power curve was multiplied by the ratio of site air density to
standard air density of 1.225 kg kg/m3 and capped at a maximum 100 kW output.
Northern Power 100 annual energy production 3 turbine array, 100% availability
Parameter
Total
Average Each
Minimum Each
Maximum Each
(MWh/yr)
(MWh/yr)
(MWh/yr)
(MWh/yr)
Net AEP
1,025
341.8
337.6
345.1
Gross AEP
1,043
347.8
345.9
350.6
Wake loss
1.71 %
-
-
-
V3 ENERGY LLC
Cagle River, Alaska 907.3503047
Saint Mary's, Alaska Wind Power Conceptual Design Analysis P a g e 115
Northern Power 100 turbines, view to north
Northern Power 100 turbines, view to south
V3 ENERGY LLC
Eagle River, Alaska 907.3503047
Saint Marys, Alaska Wind Power Conceptual Design Analysis
1 16
EWT52-900 Turbine Layout
Although orographic modeling indicates highest wind resource on the bluff edge downhill from the met
tower, toward the Yukon River and the village of Pitka's Point, land use restrictions dictated placement
of the turbine in the southeast corner of Lot 6. This location, though, should still be considered highly
desirable for wind energy production by any standard.
EWT 52-900 Turbine Layout
Turbine UTM (easting, northing) Latitude, Longitude
EWT 52-900 Zone 3V 591648, 6879454 62.036230° N, 163.24800 W°
WASP Modeling Results for EWT 52-900 Turbine
The following table presents the WAsP software analysis of energy production for the EWT 52-900 wind
turbine at 100% turbine availability (percent of time that the turbine is on-line and available for energy
production). The EWT turbine is predicted to perform extremely well in the Pitka's Point wind regime
with excellent capacity factors and annual energy productions.
Note that the standard (atmospheric conditions) power curve was compensated to the measured mean
annual site air density of 1.273 kg/m3. For the pitch -controlled EWT 52-, power output (for each m/s
wind speed step) is multiplied by the ratio of site air density to standard air density of 1.225 kg kg/m3,
raised to the one-third power.
EWT 52-900 annual energy production, variable turbine availability
EWT 52-900
(50 meter hub height)
Energy Production
Turbine Availability (KWh/yr) Capacity Factor (%)
100% 3,397,000 43.1
95% 3,227,000 40.9
80% 2,717,000 34.5
V3 ENERGY LLC
Eagle River, Alaska 907.3503047
Saint Mary's, Alaska Wind Power Conceptual Design Analysis 117
EWT turbine, view to southwest (village of Pitka's Point top center)
EWT turbine, view to east (village of St. Mary's top right)
V3 ENERGY LLC
Eagle River, Alaska 907.3503047
Saint Marys, Alaska Wind Power Conceptual Design Analysis P a g e 118
Economic Analysis
Homer software was used to model static energy balance of the Saint Mary's electrical and thermal
power system at one hour increments of time. For both wind turbines considered, they are modeled as
connected to the electrical distribution system with first priority to serve the electrical load and second
priority to serve the thermal load via a secondary load controller and electric boiler.
Wind Turbine Costs
Capital and installation costs of three Northern Power 100 ARCTIC wind turbines to serve the village of
St. Mary's are based on AVEC's cost estimate in their Renewable Energy Fund Round V proposal. Total
proposed project cost, including distribution system extension and AVEC cost share, is $4,443,244,
based on a cost estimate developed in 2011 for a Renewable Energy Fund Round 5 analysis.
An alternative consideration, which would serve only the village of St. Mary's initially but later would
also serve the village of Pilot Station once the intertie is complete, is installation of one EWT52-900 wind
turbine on a 50 meter tower. Total project cost for the EWT52-900 turbine, including distribution
system extension and power plant upgrades, is $6,153,991.
St. Mary's to Pilot Station Intertie Cost
An economic analysis of the EWT 52-900 wind turbine in a combined Saint Mary's/Pilot Station electrical
system must include the cost of connection as the intertie does not presently exist. This cost, though, is
more than simply the cost to build the intertie. It includes avoided costs such as a power plant and bulk
fuel upgrade in Pilot Station that will not be built if an intertie to Saint Mary's is constructed instead.
Interestingly, this also includes the opportunity of wind power. Airspace restrictions around Pilot
Station preclude the option of wind turbines for the village, but with an intertie, the wind power project
plan for St. Mary's will be available to also serve Pilot Station.
A preliminary cost analysis of non-intertie vs. intertie scenarios is presented in the table below.
Although the intertie itself is projected to cost $5.95 million, the net cost of the intertie, with avoided
capital costs considered, is a very modest $260,000.
Without Intertie
St. Mary's Pilot Station
With Intertie
St. Mary's Pilot Station
Notes
Powerplant
capital cost $5.50 M $5.50 M
$5.80 M $0.75 M
Bulk fuel capital
cost $4.61 M $2.39 M
$5.76 M 0
Wind turbine
NP100's for St. M.,
capital cost $4.44 M 0
$6.15 M 0
or EWT for both
Intertie capital
Cost Difference
cost
$5.95 M
(no turbines)
Total Cost
(wind turbines
not included) $18.00 M
$18.26 M
$260,000
V3 ENERGY LLC
Cagle River, Alaska 907.3503047
Saint Marys, Alaska Wind Power Conceptual Design Analysis P a g e 119
Beyond the avoided capital costs, the benefits of an electrical intertie between Saint Mary's and Pilot
Station include increased efficiency of the diesel generators in Saint Mary's as they will operate at higher
loading levels and hence more efficient points of their fuel curves, reduced operating and maintenance
expenses with fewer diesel generators on line, lower labor costs, reduced maintenance expenses, and
reduced repair and emergency expenses with operations consolidated in Saint Mary's. A separate
economic analysis indicates a benefit -to -cost ratio of approximately 1.20 for 20 to 50 year evaluation
periods.
Fuel Cost
A fuel price of $5.02/gallon ($1.33/Liter) was chosen for the initial HOMER analysis by reference to
Alaska Fuel Price Projections 2012-2035, prepared for Alaska Energy Authority by the Institute for Social
and Economic Research (ISER), dated July, 2012. The $5.02/gallon price reflects the average value of all
fuel prices between the 2014 (assumed project start year) fuel price of $4.53/gallon and the 2033 (20
year project end year) fuel price of $5.48/gallon using the medium price projection analysis with social
cost of carbon (SCC) included (see ISER spreadsheet for Renewable Energy Fund Round 6 analysis).
By comparison, the fuel price for Stebbins (without social cost of carbon) reported to Regulatory
Commission of Alaska for the 2011 PCE report is $2.71/gallon ($0.716/Liter).
Fuel cost table
Average Average
Cost Scenario 2014 (/gal) 2033 (/gal) (/gallon) (/Liter)
Medium w/ SCC $4.53 $5.48 $5.02 $1.33
Modeling Assumptions
HOMER energy modeling software was used to analyze the Saint Mary's power System. HOMER is a
static energy model designed to analyze hybrid power systems that contain a mix of conventional and
renewable energy sources, such as diesel generators, wind turbines, solar panels, batteries, etc. Homer
software is widely used in the State of Alaska to aid development of village wind -diesel power projects.
HOMER modeling assumptions are detailed in the table below. Many assumptions, such as project life,
discount rate, operations and maintenance (O&M) costs, etc. are AEA default values. Other
assumptions, such as diesel overhaul cost and time between overhaul are based on general rural Alaska
power generation experience.
The base or comparison scenario is the existing St. Mary's/Andreafsky powerplant with its present
configuration of diesel generators. Also assumed in the base or comparison scenario is that excess
powerplant heat serves the thermal load via a heat recovery loop.
Wind turbines constructed at the Pitka's Point site are assumed to operate in parallel with the diesel
generators. Excess energy will serve thermal loads via a secondary load controller and electric boiler.
Installation cost of either three NW100 wind turbines or one EWT-500 wind turbine assumes a three-
phase distribution line extension from the road to the wind turbine site plus a two-phase to three-phase
V3 ENERGY LLC
Cagle River, Alaska 907.3503047
Saint Marys, Alaska Wind Power Conceptual Design Analysis
Page 120
upgrade of the distribution system from the line extension tie-in to an existing three-phase distribution
point on the west side of the village of St. Mary's.
Basic modeling assumptions
Economic Assumptions
Project life 20 years (2014 to 2033)
Discount rate 3%
System fixed O&M cost (non -fuel) $683,198/year (St. Mary's only);
$964,500/year (St. Mary's + Pilot Station)
Operating Reserves
Load in current time step
10%
Wind power output
50%
Fuel Properties (both types)
Heating value
43.2 MJ/kg (18,600 BTU/Ib)
Density
820 kg/m3 (6.85 lb/gal)
Price
$5.02/gal ($1.33/Liter)
Diesel Generators
Generator capital cost
$0 (gensets already exist)
O&M cost
$2.50/hour (at $0.02/kWh)
Time between overhauls
20,000 hours (run time)
Overhaul cost (all diesel gensets)
$75,000
Minimum load
0 kW; based on AVEC's inverter/battery integration plan to
enable diesels -off operation of the wind -diesel system
Schedule
Optimized
Wind Turbines
Availability
80% (note that EWT turbine is guaranteed by manufacturer
to achieve 95% availability, less downtime due to icing)
O&M cost
$0.0469/kWh for NP 100 and $0.018/kWh for EWT 52-900
(equates to $41,900/year for 3 NP 100 turbines and
$48,250/year for EWT 52-900; based on 34% turbine CF both
turbines)
Wind speed
7.69 m/s at the Pitka's Point wind; scaled to 6.75 m/s in
Homer software for 80% turbine availability (38 meter level)
Energy Loads
Electric: St. Mary's
8.74 MWh/day measured in St. Mary's power plant
Electric: St. Mary's + Pilot Station
13.73 MWh/day; St. Mary's power plant data scaled to
accommodate Pilot Station load
Thermal
5.22 MWh/day based on recovered heat report written by
AEE, Inc.
Project Cost Assumptions
Three basic project configuration and benefit -to -cost evaluations are considered with Homer modeling,
as listed below.
Configuration Number:
1. Three Northern Power 100 wind turbines serving only the Saint Mary's electrical and thermal
load; total project cost of $4,443,244.
V3 ENERGY LLC
Cagle River, Alaska 907.3503047
Saint Marys, Alaska Wind Power Conceptual Design Analysis 121
2. One EWT 52-900 wind turbine serving only the Saint Mary's electrical and thermal load; total
project cost of $6,153,991.
3. One EWT 52-900 wind turbine serving an intertied Saint Mary's and Pilot Station electrical load
and Saint Mary's thermal load; total project cost of $6,413,991. This cost estimate reflects the
cost of installing one EWT 52-900 turbine in St. Mary's plus the cost the St. Mary's to Pilot
Station intertie less the avoided capital costs when closing the Pilot Station powerhouse and
consolidating generation operations to Saint Mary's (see below).
Configuration 3: Saint Mary's to Pilot Station cost summary
Project Item Cost
EWT turbine project cost, St. Mary's $6.15 M
Intertie project cost + $5.95 M
Combined powerplant and bulk fuel upgrades (if intertied) + $12.31 M
Individual village powerplant and bulk fuel upgrades (no intertie - $18.00 M
Total cost: turbine project + St. Mary's-to-Pilot Station intertie - $6.41 M
Percent cost increase from turbine project alone +4.2%
V3 ENERGY LLC
Eagle River, Alaska 907.3503047
W Z
O
U
a)
a
O i
C:
M
00
IOW
rn Ln
r, n
�
N
O
O
tD
00
W
00
O
r-I
M
N
'
00
M
O
Ln
O
N
I�
tp
00
I�
I
Ln
O
I-
O
O
O
V
Ln
" Ln
o
lD
Ln
o
F
O
Ln
Ln
Ln
tD
Ln
O
Ln
M
N
0
V
4J
qj)-
(6
" al
" ci
m
Ili
Lf1
'
ZT
o�
O
ro
a)
..
f
r
L
2
I
M
O
m
4
L \ \ \ cr)
c-I ^ W C C C O l.f)
aj toM
al ri
0 N
c-I
L
O
E
a
+'
�
>
O
Q O
O
L
O
—
aj
+,
U
>�
C
m
cv
N O
+,
O
Q
4-1
N
O
L
L
a!
Q
� +'
O a1
C
+,
N
U C
a
Q
arc
+J
in
0 m
w
!JJ w
c,
LOU
T
N o
\
00
X
Lu L
N U
Ln
ua--�
U \
N
X N
w v
on
00
c
N
(U
a,
_ fo
N O tab
L.L fo
O
aJ M i
C7
M
aJ N
C v
�
CD
ci
o0
C
r,
00
OA U
o
Ln
U
N
U J
O
N
rI
_ •0
rl
ri
J
M
Ln
�M-I
�
Lrl
N
0
r`
'a O
O
O
O
Od
w
�
V
N
Lrl
W
LqLrl
OU -le
o
O
l0
O
U
n
d
Z
`1
Lri
Lfl
Lri
SZ„
o
^
j.
o
o
i
i
cY'f
^
C
M
N
00
O
>
>
Va
*'
m
t>
v
o
n
l0
rn
ri
~
tN/}
iN/?
C*.4.l
r0
t/?
N
cM-I
c�-I
>
0.0
M
Ol
N
m
Ln:
of
Lri
J
v
rn
Ln
O
]-
0
ri
ri
o
c
v
=3U
. o
C
E
v
o
w
U
L
N
i
4-4�
i
_
LLJ a
O
v
4�
t
>
o
Co
Q
p
— U
tp
O
o
4J
i
.-
+,
�
-O
U
(Y)
t�
3
0
Q
�
> ti
Lu
L
N
H
N
3
i
Q
o
v
o
4-1
C
C
U
LL
m
N
Cfl
0.
E
N o
\
X
ti V
M
i
Ua-
U
L6
W v
^
00
00
>c
G
N
Ln
- —
O
N O
00
N
7 >
ci
W ro
(U M
m
Ln
�
N
�
M
Ln
C
00
00
(J -1
OA .0
ro
CD
�--I
L r
JLn
1.0
v
= O
m
J
O
O
a)
0
-1
O
M
_
c-I
C
M
O
_0 O
M
O
w
�
V
L1)
00
W
0
O
O
Il
N
rz
d
Z
M
tT
M
tD
LD
j,
0,o
i
i
O
N
00
O
\
00
O
m
N
00
fo
r-I
O
of
r-i00
on
oro
�
C
rn
c
J �,
cc
0
0
J
N
00
o 0
V
i
v
D.0 H
00
O
Cyt
aJ
E
1
O
ti
a)i
coo
Z E
ro
L
a)
LLI y
— u
aj
4�
t
>
co
a
O
oe
tD
O
0
'a
v
3
o
L
Q+
o
W
4-1
L
H
aJ
u
ai
N
3
i
Q
O
v
n
O
�-
C
C
U
W
m
(n
m
0.
Saint Mary's, Alaska Wind Power Conceptual Design Analysis P a g e 125
Appendix A, WASP Wind Farm Report, Pitka's Point Site, NP 100
Turbines
V3 ENERGY LLC
Eagle River, Alaska %7,3-10.5047
9/12/12
Wind farm report for'Northern Power 100'
'Northern Power 100' wind farm
Produced on 9/12/2012 at 10:49:30 AM by licenced user: Douglas J. Vaught, V3 Energy, USA using WAsP version:
10.02.0010
Summary results
Parameter
Total
Average
Minimum
Maximum
Net AEP [MWh]
1025.507
341.836
337.647
345.105
Gross AEP [MWh]
1043.365
347.788
345.942
350.628
Wake loss [%]
1.71
-
-
-
Site results
Site
Location [m]
Turbine
Elevation [m]
Height [m]
Net AEP [MWh]
Wake loss [%]
wtg 1
(591577, 6879392)
NWP 100
162.1809
38
337.647
2.4
wtg2
(591646, 6879471)
NWP 100
169.5611
37
342.756
2.25
wtg3
(591715, 6879552)
NWP 100
170
38
345.105
0.49
Site wind climates
Site
Location [m]
H [m] A [m/s]
k
U [m/s]
E [W/m2]
RIX [%]
dRIX [%]
wtg1
(591577, 6879392)
38 8.5
2.02
7.56
519
4.0
0.7
wtg2
(591646, 6879471)
37 8.6
2.01
7.63
536
3.6
0.4
wtg3
(591715, 6879552)
38 8.5
2.02
7.57
521
3.5
0.3
The wind farm lies in a map called KWIGUKutmDV.
file:///C:/Users/Doug/AppData/Loca I/Temp/WaspReporti ngTem pora ryFile.htm 1 1/7
9/12/12
Wind farm report for'Northern Power 100'
a
6MDDD
i
4
The wind farm is in a project called PitcaPoint_testcase
A wind atlas called Wind atlas 2 was used to calculate the predicted wind climates
Calculation of annual output for'Northern Power 100'
0
Decay constants: 0.075 0.075 0.075 0.075 0.075 0.075 0.075 0.075 0.075 0.075 0.075 0.075 0.075 0.075 0.075 0.075
0.075 0.075 0.075 0.075 0.075 0.075 0.075 0.075 0.075 0.075 0.075 0.075 0.075 0.075 0.075 0.075 0.075 0.075
0.075 0.075
cPrrnr 1 (n°1
Turbine
A [m/s]
k
Freq. [%]
U [m/s]
MWh (free)
MWh (park)
Eff. [%]
wtg 1
9.7
2.29
5.64
8.58
24.111
24.111
100.0
wtg2
9.9
2.28
5.78
8.74
25.327
25.327
100.0
wtg3
19.7
2.30
5.62
8.60
24.074
24.074
100.0
Sector 1 total
-
-
I-
-
173.512
173.512
1100.0
Sertnr 2 (1 no)
Turbine
A [m/s]
k
Freq. [%]
U [m/s]
MWh (free)
MWh (park)
Eff. [%]
wtg 1
9.4
2.25
5.51
8.29
22.368
22.368
100.0
wtg2
9.5
2.24
5.60
8.43
23.273
23.273
100.0
wtg3
19.4
2.25
5.56
18.34
122.775
122.775
1100.0
Sector 2 total
-
-
-
-
68.417
68.417
100.0
Sector 3 (200)
file:///C:/Users/Doug/AppData/Loca I/Temp/WaspReportingTem pora ryFile.htm 1 2/7
9/12/12
Wind farm report for'Northern Power 100'
Turbine
A [m/s]
k
IFreq. [%]
U [m/s]
MWh (free)
MWh (park)
Eff. [%]
Wtg 1
8.7
2.12
4.59
7.72
16.651
16.651
100.0
wtg2
8.8
2.10
4.58
7.79
16.829
16.829
100.0
wtg3
8.8
2.13
4.69
7.80
17.298
17.298
100.0
Sector 3 total
-
-
-
-
150.778
150.778
1100.0
Sector 4 (30°)
Turbine
A [m/s]
k
Freq. [%]
U [m/s]
MWh (free)
MWh (park)
Eff. [%]
Wtg 1
8.1
2.09
3.78
7.17
12.123
10.739
88.58
wtg2
8.2
2.10
3.77
7.25
12.336
10.984
89.04
wtg3
8.2
2.09
3.84
7.23
12.513
12.513
100.0
Sector 4 total
I - I
-
I -I
-
136.972
134.236
192.6
Sartnr 5 (4n°)
Turbine
A [m/s]
k
Freq. [%]
U [m/s]
MWh (free)
MWh (park)
Eff. [%]
Wtg 1
8.1
2.34
3.52
7.16
11.268
7.042
62.49
wtg2
8.2
2.33
3.57
7.28
11.797
8.586
72.78
wtg3
8.2
2.34
3.58
17.23
111.645
111.645
1100.0
Sector 5 total
-
-
-
-
34.710
127.273
178.57
Sector 6 (500)
Turbine
A [m/s]
k
Freq. [%]
U [m/s]
MWh (free)
MWh (park)
Eff. [%]
Wtg 1
8.9
2.40
4.11
7.87
15.503
12.846
82.86
wtg2
8.9
2.39
4.08
7.91
15.487
13.612
87.89
wtg3
19.0
2.40
4.18
17.95
116.013
116.013
1100.0
Sector 6 total
-
-
-
-
47.002
42.470
90.36
SPrtnr 7 (6no)
Turbine A [m/s]
k
Freq. [%]
U [m/s]
MWh (free)
MWh (park)
Eff. [%]
Wtg 1 10.0
2.22
5.19
8.87
23.064
23.037
99.88
wtg2 10.1
2.21
5.20
8.93
23.284
23.284
100.0
wtg3 10.1
2.22
5.29
18.97
23.818
123.818
1100.0
Sector 7 total -
-
-
-
70.167
70.139
99.96
Sector R (700)
Turbine
A [m/s]
k
Freq. [%]
U [m/s]
MWh (free)
MWh (park)
Eff. [%]
wtg 1
9.8
2.10
4.93
8.66
21.019
21.019
100.0
wtg2
9.7
2.08
4.80
8.61
20.298
20.298
100.0
wtg3
9.8
2.09
4.96
8.70
21.230
21.230
100.0
Sector 8 total
-
-
-
-
162.548
162.548
1100.0
Sartnr 9 (Rno)
Turbine A [m/s]
k
Freq. [%]
U [m/s]
MWh (free)
MWh (park)
Eff. [%]
Wtg 1 9.1
2.03
4.23
8.04
16.219
16.219
100.0
wtg2 9.0
2.02
4.12
8.00
15.657
15.657
100.0
wtg3 9.1
2.03
4.22
8.04
116.163
116.163
1100.0
Sector 9 total -
-
-
-
48.039
148.039
1100.0
Sartnr 1 n (Qn°l
Turbine
A [m/s]
k
Freq. [%]
U [m/s]
MWh (free)
MWh (park)
Eff. [%]
Wtg 1
8.3
2.13
3.67
7.38
12.369
12.369
100.0
wtg2
8.3
2.12
3.58
7.35
12.005
12.005
100.0
wtg3
8.3
2.13
3.66
7.38
12.341
12.341
100.0
Sector 10 total
-
-
-
-
36.71-9
136.71.5
1100.0
Sector 11 1000
Turbine JA [m/s] Ik IFreq. [%] U [m/s] IMWh (free) IMWh (park) jEff. [%]
file:///C:/Users/Doug/AppData/Loca I/Temp/WaspReportingTem pora ryFile.htm I 3/7
9/12/12
Wind farm report for'Northern Power 100'
Wtg 1
8.0
2.15
13.41
7.09
10.753
10.753
100.0
wtg2
8.0
2.14
3.35
7.08
10.526
10.526
100.0
wtg3
8.0
2.15
3.37
7.07
10.577
10.577
100.0
Sector 11 total
-
-
-
-
31.855
31.855
100.0
Sector 12 (1100)
Turbine
A [m/s]
k
Freq. [%]
U [m/s]
MWh (free)
MWh (park)
Eff. [%]
Wtg 1
7.8
2.10
2.88
6.90
8.651
8.651
100.0
wtg2
7.8
2.09
2.86
6.90
8.577
8.577
100.0
wtg3
17.8
2.10
2.83
6.88
18.437
8.437
100.0
Sector 12 total
-
-
-
-
125.664
125.664
1100.0
Sector 13 1200
Turbine
A [m/s]
k
Freq. [%]
U [m/s]
MWh (free)
MWh (park)
Eff. [%]
Wtg 1
8.0
2.10
2.32
7.08
7.283
7.283
100.0
wtg2
8.0
2.09
2.32
7.08
7.282
7.282
100.0
wtg3
18.0
2.10
2.27
7.05
7.089
17.089
1100.0
Sector 13 total
-
-
-
-
121.654
121.654
1100.0
Sector 14 (1300)
Turbine
A [m/s]
k
Freq. [%]
U [m/s]
MWh (free)
MWh (park)
Eff. [%]
Wtg 1
8.4
2.12
1.93
7.46
6.616
6.616
100.0
wtg2
8.5
2.11
1.94
7.49
6.707
6.707
100.0
wtg3
18.4
2.12
1.89
7.41
16.426
6.426
1100.0
Sector 14 total
-
-
-
-
119.749
119.749
100.0
Sector 15 1400
Turbine
JA [m/s]
18.9
k
1.94
Freq. [%]
2.00
U [m/s]
7.91
MWh (free)
7.424
MWh (park)
7.424
Eff. [%]
100.0
Wtg 1
wtg2
9.0
1.96
1.99
7.94
7.455
7.455
100.0
wtg3
8.8
1.94
1.96
7.85
7.209
7.209
100.0
Sector 15 total
-
-
-
-
22.087
122.087
1100.0
Sector 16 1500
Turbine
A [m/s]
k
Freq. [%]
U [m/s]
MWh (free)
MWh (park)
Eff. [%]
Wtg 1
9.5
1.67
2.26
8.45
8.802
8.802
100.0
wtg2
9.6
1.67
2.29
8.58
9.062
9.062
100.0
wtg3
19.4
1.67
2.22
8.40
18.614
8.614
100.0
Sector 16 total
-
-
-
-
126.477
126.477
1100.0
Sector 17 (1600)
Turbine
A [m/s]
k
Freq. [%]
U [m/s]
MWh (free)
MWh (park)
Eff. [%]
Wtg 1
9.6
1.69
2.42
8.60
9.651
9.651
100.0
wtg2
9.8
1.67
2.47
8.74
9.974
9.974
100.0
wtg3
9.6
1.68
2.39
8.55
9.446
9.446
100.0
Sector 17 total
-
-
-
-
129.071
129.071
100.0
Sector 18 (1701)
Turbine
A [m/s]
k
Freq. [%]
U [m/s]
MWh (free)
MWh (park)
Eff. [%]
Wtg 1
9.7
1.82
2.43
8.60
9.910
9.910
100.0
wtg2
9.9
1.82
2.48
8.77
10.366
10.366
100.0
wtg3
19.7
1.82
2.42
8.60
19.864
9.864
1100.0
Sector 18 total
-
-
-
-
130.139
130.139
1100.0
Sector 19 (1800)
Turbine
A [m/s]
Ik
IFreq.
JU [m/s]
IMWh (free)
IMWh (park)
jEff. [%]
Wtg 1
8.4
11.72
12.10
17.52
17.150
17.150
1100.0
file:///C:/Users/Doug/AppData/Loca I/Temp/WaspReportingTem pora ryFile.htm 1 4/7
9/12/12
Wind farm report for'Northern Power 100'
wtg2
18.6
11.71
12.15 17.64
7.456
17.456
1100.0
wtg3
18.5
11.73
12.12
17.60
7.324
17.324
1100.0
Sector 19 total
-
-
-
-
21.931
121.931
1100.0
Sector 20 (1900)
Turbine
A [m/s]
k
Freq. [%]
U [m/s]
MWh (free)
MWh (park)
Eff. [%]
Wtg 1
7.2
1.79
1.87
6.37
4.902
4.902
100.0
wtg2
7.3
1.79
1.90
6.45
5.100
5.100
100.0
wtg3
17.2
1.78
1.89
16.44
5.041
5.041
100.0
Sector 20 total
-
-
-
-
15.043
15.043
100.0
Sector 21 (2000)
Turbine
A [m/s]
k
Freq. [%]
U [m/s]
MWh (free)
MWh (park)
Eff. [%]
Wtg 1
6.4
1.96
1.54
5.71
3.218
3.218
100.0
wtg2
6.5
1.95
1.54
5.76
3.271
3.271
100.0
wtg3
16.5
1.96
1.58
5.77
3.364
3.364
100.0
Sector 21 total
-
-
-
-
9.853
19.853
1100.0
Sector 22 (2100)
Turbine
A [m/s]
k
Freq. [%]
U [m/s]
MWh (free)
MWh (park)
Eff. [%]
Wtg 1
5.9
2.07
1.20
5.25
2.018
2.018
100.0
wtg2
6.0
2.07
1.18
5.30
2.038
1.723
84.54
wtg3
6.0
2.06
1.22
5.30
2.108
1.701
80.73
Sector 22 total
-
-
-
-
6.164
15.443
188.3
Sector 23 (2200)
Turbine
A [m/s]
k
Freq. [%]
U [m/s]
MWh (free)
MWh (park)
Eff. [%]
Wtg 1
5.7
2.35
0.97
5.09
1.437
1.437
100.0
wtg2
5.8
2.37
0.97
5.16
1.482
0.800
54.02
wtg3
15.8
2.35
0.99
5.14
11.499
0.658
43.88
Sector 23 total
-
-
-
-
14.417
12.895
165.54
Sector 24 2300
Turbine
A [m/s]
k
Freq. [%]
U [m/s]
MWh (free)
MWh (park)
Eff. [%]
Wtg 1
6.1
2.79
0.92
5.45
1.535
1.535
100.0
wtg2
6.1
2.78
0.92
5.47
1.542
1.110
72.01
wtg3
6.2
2.79
0.94
5.50
1.602
1.160
72.4
Sector 24 total
-
-
-
-
4.679
13.806
81.33
Sector 25 (2400)
Turbine
A [m/s]
k
Freq. [%]
U [m/s]
MWh (free)
MWh (park)
Eff. [%]
Wtg 1
6.0
2.72
1.17
5.37
1.889
1.889
100.0
wtg2
6.0
2.71
1.17
5.37
1.889
1.882
99.66
wtg3
16.1
2.72
1.19
5.42
1.969
1.969
199.99
Sector 25 total
-
-
-
-
15.746
15.740
199.89
Sector 26 2500
Turbine
A [m/s]
k
Freq. [%]
U [m/s]
MWh (free)
MWh (park)
Eff. [%]
Wtg 1
6.0
2.55
1.14
5.35
1.868
1.868
100.0
wtg2
6.0
2.53
1.12
5.33
1.815
1.815
100.0
wtg3
16.1
2.54
1.15
5.38
1.916
1.916
100.0
Sector 26 total
I -
I -
I -
-
15.599
15.599
1100.0
Sector 27 (2600)
Turbine
A [m/s]
Ik
IFreq.
JU [m/s]
IMWh (free) MWh (park)
jEff. [%]
Wtg 1
5.9
12.41
1.01
5.26
1.609 1.609
1100.0
wtg2
5.9
12.40
10.98
15.23
11.550 1.550
1100.0
file:///C:/Users/Doug/AppData/Loca I/Temp/WaspReportingTem pora ryFile.htm 1 5/7
9/12/12
wtg 3
Sector 27 total
Wind farm report for'Northern Power 100'
5.9 12.41 11.01 15.27
1.618 11.618 1100.0
4.777 14.777 1100.0
Sector 29 (27n°)
Turbine
A [m/s]
k
Freq. [%]
U [m/s]
MWh (free)
MWh (park)
Eff. [%]
Wtg 1
5.9
2.42
1.05
5.27
1.677
1.677
100.0
wtg2
5.9
2.42
1.02
5.25
1.618
1.618
100.0
wtg3
16.0
2.44
1.07
15.29
11.728
11.728
1100.0
Sector 28 total
I -
I -
I -
15.023
15.023
1100.0
Sartnr 2Q (2Rno)
Turbine
A [m/s]
k
Freq. [%]
U [m/s]
MWh (free)
MWh (park)
Eff. [%]
Wtg 1
6.4
2.55
1.43
5.71
2.763
2.763
100.0
wtg2
6.4
2.54
1.39
5.68
2.656
2.656
100.0
wtg3
6.5
2.56
1.43
5.74
2.795
2.795
100.0
Sector 29 total
-
-
-
-
8.214
18.214
100.0
Cartnr in (?QnO)
Turbine
A [m/s]
k
Freq. [%]
U [m/s]
MWh (free)
MWh (park)
Eff. [%]
Wtg 1
7.1
2.63
1.63
6.30
3.959
3.959
100.0
wtg2
7.1
2.62
1.60
6.28
3.863
3.863
100.0
wtg3
7.1
2.63
1.62
6.29
3.909
3.909
100.0
Sector 30 total
-
-
-
-
11.731
111.731
1100.0
Sartnr 31 ('inno)
Turbine
A [m/s]
k
Freq. [%]
U [m/s]
MWh (free)
MWh (park)
Eff. [%]
Wtg 1
7.6
2.29
1.71
6.70
4.834
4.834
100.0
wtg2
7.6
2.31
1.69
6.71
4.779
4.779
100.0
wtg3
7.5
2.29
1.69
6.67
4.727
4.727
100.0
Sector 31 total
I -
I -
I -
I -
114.339
114.339
1100.0
Sartnr R7 (11 no)
Turbine
A [m/s]
k
Freq. [%]
U [m/s]
MWh (free)
MWh (park)
Eff. [%]
Wtg 1
8.1
2.03
2.13
7.15
6.798
6.798
100.0
wtg2
8.1
2.03
2.09
7.18
6.733
6.733
100.0
wtg3
8.0
2.03
2.10
7.11
6.638
16.638
1100.0
Sector 32 total
-
-
-
-
120.169
120.169
1100.0
Sertnr';I (,i2no1
Turbine
A [m/s]
k
Freq. [%]
U [m/s]
MWh (free)
MWh (park)
Eff. [%]
Wtg 1
7.5
2.14
2.82
6.60
7.791
7.791
100.0
wtg2
7.5
2.10
2.79
6.68
7.877
7.877
100.0
wtg3
7.4
2.13
2.77
6.55
7.526
7.526
100.0
Sector 33 total
-
-
-
-
23.195
123.195
1100.0
Sartnr '44 ('4'4no)
Turbine
A [m/s]
k
Freq. [%]
U [m/s]
MWh (free)
MWh (park)
Eff. [%]
Wtg 1
8.2
2.49
3.42
7.25
11.188
11.188
100.0
wtg2
8.3
2.47
3.45
7.33
11.516
11.516
100.0
wtg3
8.1
2.49
3.36
7.19
10.814
10.814
100.0
Sector 34 total
-
-
-
-
33.517
133.517
1100.0
Sector 35 (34n°)
Turbine
A [m/s]
k
Freq. [%]
U [m/s]
MWh (free)
MWh (park)
Eff. [%]
Wtg 1
9.0
2.57
4.11
8.04
16.104
16.104
100.0
wtg2
9.2
2.56
4.18
8.16
16.749
16.749
100.0
wtg3
9.0
2.56
4.04
7.97
15.638
15.638
100.0
file:///C:/Users/Doug/AppData/Loca I/Temp/WaspReportingTem pora ryFile.htm I 6/7
9/12/12
Wind farm report for 'Northern Power 100'
(Sector 35 total +- - - - 48.491 I48.491 1100.0 I
Sector 36 (3500)
Turbine
A [m/s]
k
Freq. [%]
U [m/s]
MWh (free)
MWh (park)
Eff. [%]
wtg 1
9.7
2.45
4.95
8.60
21.417
21.417
100.0
wtg2
9.9
2.44
5.06
8.76
22.454
22.454
100.0
wtg3
9.7
2.46
4.89
8.57
21.047
21.047
100.0
Sector 36 total
-
-
-
-
164.918
164.918
1100.0
All SPctnm
Turbine
Location [m]
MWh (free)
MWh (park)
Eff. [%]
wtg1
(591577, 6879392)
345.942
337.647
97.6
wtg2
(591646, 6879471)
350.628
342.756
97.75
wtg3
Wind farm
(591715, 6879552)
346.794
11043.365
345.105
11025.507
99.51
198.29
Data origins information
The map was imported by 'User' from a file called
'C:\Users\User\Documents\WIndConsUItLLC\Alaska\MAPS\KWIGUKutm DV. map', on a computer called 'SERVER'. The map
file data were last modified on the 2/7/2012 at 6:08:37 PM
There is no information about the origin of the wind atlas associated with this wind farm.
The wind turbine generator associated with this wind farm was imported by 'Doug' from a file called
'C:\Users\Doug\Documents\Wind Turbines\WAsP turbine curves\NW100B_21, 37 meter.wtg', on a computer called
'V3ENERGYACER-PC'. The wind turbine generator file was last modified on the 8/29/2012 at 10:35:48 AM
Project parameters
The wind farm is in a project called PitcaPoint_testcase.
Here is a list of all the parameters with non -default values:
Air density: 1.272 (default is 1.225)
file:///C:/Users/Doug/AppData/Local/Temp/WaspRepartingTemporaryFile.html 7/7
Saint Marys, Alaska Wind Power Conceptual Design Analysis P a g e 126
Appendix B, WAsP Turbine Site Report, Pitka's Point Site, EWT Turbine
V3 ENERGY LLC
Eagle River, Alaska %7,3-10.5047
9/11/12
Turbine site report for'EWT turbine site'
'EWT turbine site' Turbine site
Produced on 9/11/2012 at 11:37:19 PM by licenced user: Douglas I Vaught, V3 Energy, USA using WASP Version:
10.02.0010
Site information
Location in the map
The turbine is located at co-ordinates (591648,6879454) in a map called 'KWiguk A3'. The site elevation is 170.0 m
a.s.l.
Site effects
Sector
Angle [0]
Or.Spd [%]
Or.Tur [0]
Obs.Spd [%]
Rgh.Spd [%]
Rix [%]
1
0
27.48
-6.1
0.00
0.00
0.2
2
10
22.71
-6.4
0.00
0.00
1.0
3
20
18.03
-5.9
0.00
0.00
0.0
4
130
14.06
-4.5
0.00
0.00
0.0
5
40
11.36
-2.5
0.00
0.00
1.4
6
50
10.36
-0.1
0.00
0.00
2.3
7
60
11.24
2.4
0.00
0.00
1.7
file:///C:/Users/Doug/AppData/Loca I/Temp/WaspReportingTem pora ryFile.htm 1 1/3
9/11/12
Turbine site report for'EWT turbine site'
8
170
13.84
4.4
0.00
0.00
2.1
9
80
17.75
5.8
0.00
0.00
2.5
10
90
22.40
6.4
0.00
0.00
2.7
11
100
27.18
6.2
0.00
0.00
3.6
12
110
31.54
5.3
0.00
0.00
4.4
13
120
35.00
3.8
0.00
0.00
5.3
14
130
37.24
2.0
0.00
0.00
5.5
15
140
38.04
0.1
0.00
0.00
6.2
16
150
37.33
-1.9
0.00
0.00
6.3
17
160
35.19
-3.7
0.00
0.00
6.5
18
170
31.79
-5.2
0.00
0.00
5.9
19
180
27.48
-6.1
0.00
0.00
5.4
20
190
22.71
-6.4
0.00
0.00
5.1
21
200
18.03
-5.9
0.00
0.00
6.3
22
210
14.06
-4.5
0.00
0.00
6.3
23
220
11.36
-2.5
0.00
0.00
7.7
24
230
10.36
-0.1
0.00
0.00
2.9
25
240
11.24
2.4
0.00
0.00
2.8
26
250
13.84
4.4
0.00
0.00
2.9
27
260
17.75
5.8
0.00
0.00
1.0
28
270
22.40
6.4
0.00
0.00
2.0
29
280
27.18
6.2
0.00
0.00
4.7
30
290
31.54
5.3
0.00
0.00
10.6
31
300
35.00
3.8
0.00
0.00
6.1
32
310
37.24
2.0
0.00
0.00
1.8
33
320
38.04
0.1
0.00
0.00
0.8
34
330
37.33
-1.9
0.00
0.00
0.0
340
35.19
-3.7
-5.2
0.00
10.00
0.00
0.00
0.0
10.0
L35
36
350
31.79
The all -sector RIX (ruggedness index) for the site is 3.4%
The predicted wind climate at the turbine site
Tota I
Mean wind speed 8.45 m/s
Mean power density 1725 W/mz
Wind at maximum power density distribution
13.39 m/s
63 (W/mz)/(m/s)
file:///C:/Users/Doug/AppData/Loca I/Temp/WaspReportingTem pora ryFile.htm 1 2/3
9/11/12 Turbine site report for'EWT turbine site'
Results
Me Location [m] ITurbine Height [m] Net AEP [GWh] lWake loss [%]
:WT turbine site (591648, 6879454) EWT52-900 150 13.397 10.0
The combined (omnidirectional) Weibull distribution predicts a gross AEP of 3.432 GWh and the emergent (sum of
sectors) distribution predicts a gross AEP of 3.397 GWh. (The difference is 1.02% )
Project parameters
The site is in a project called Saint Mary's EWT.
Here is a list of all the parameters with non -default values:
Air density: 1.273 (default is 1.225)
Data origins information
The map was imported by 'Doug' from a file called 'C:\Users\Doug\Documents\AVEC\St Marys\WAsP\Surfer
conversion\Kwiguk A3.map', on a computer called 'V3ENERGYACER-PC'. The map file data were last modified on the
8/31/2012 at 9:47:38 AM
There is no information about the origin of the wind atlas file.
The wind turbine generator was imported by 'Doug' from a file called 'C:\Users\Doug\Documents\Wind Turbines\WAsP
turbine curves\EWT52-900, 50 m.wtg', on a computer called 'V3ENERGYACER-PC'. The wind turbine generator file were
last modified on the 8/31/2012 at 1:12:58 PM
file:///C:/Users/Doug/AppData/Local/Temp/WaspRepartingTemporaryFile.html 3/3
Saint Mary's, Alaska Wind Power Conceptual Design Analysis P a g e 127
Appendix C, HOMER System Report, St. Mary's, 3 NP 100 Turbines
V3 ENERGY LLC
Eagle River, Alaska %7,3-10. 047
9/17/12
System Report - St Marys -Pilot Stn, REF 6 analysis
System Report - St Marys -Pilot Stn, REF 6 analysis
Sensitivity case
Primary Load 1 Scaled Average: 8,496 kWh/d
Wind Data Scaled Average: 6.75 m/s
EWT 52-900, rho=1.272 Capital Cost Multiplier: 1
System Fixed O&M Cost: 683,198 $/yr
System architecture
Wind turbine Northwind100B, rho=1.272
QSX15G9 499 kW
Cat 3508 611 kW
Cat 3512 908 kW
Cost summary
Total net present cost
$ 30,255,056
Levelized cost of energy
$ 0.556/kWh
Operating cost
$ 1,734,959/yr
15,aao,00
0
L7
aaa 5,000,00
Q.
to
Z
0
Net Present Costs
— Narthwind100B, rha=1.272
- asxl sG9
— Cat 3505
— Cat 3512
— Boiler
Other
Component
Capital
Replacement
O&M
Fuel
Salvage
Total
Northwind100B, rho=1.272
4,443,244
0
623,366
0
0
5,066,611
QSX15G9
0
444,142
315,626
10,940,718
-21,344
11,679,142
Cat 3508
0
0
10,191
668,347
-30,148
648,390
Cat 3512
0
0
0
0
-40,695
-40,695
Boiler
0
0
0
2,737,356
0
2,737,356
Other
0
0
10,164,263
0
0
10,164,263
System
4,443,244
1 444,142
11,113,448
14,346,421
-92,187
1 30,255,064
Annualized Costs
Capital I Replacement I O&M I Fuel I Salvage
Component
file:///C:/Users/Doug/AppData/Loca I/Temp/St_Marys-Pilot_Stn,_RE F_6_a na lysis.htm
Total
1/6
9/17/12
System Report - St Marys -Pilot Stn, REF 6 analysis
Northwind100B, rho=1.272
QSX15G9
($/Yr)
($/Yr)
($/Yr)
($/Yr)
($/Yr)
($/Yr)
298,656
0
41,900
0
0
340,556
0
29,853
21,215
735,388
-1,435
785,022
Cat 3508
0
0
685
44,923
-2,026
43,582
Cat 3512
0
0
0
0
-2,735
-2,735
Boiler
0
0
0
183,993
0
183,993
Other
0
0
683,198
0
0
683,198
System
298,656
29,853
746,998
964,305
-6,196
2,033,616
1,000,000
0
-1,550,050
LL
s
m-2,000,000
C�
m
-3,000,000
O
z
-4,000,00D
-5,000,000 _�_T
Electrical
11111 m elm s M a 0 1 all-
5 B ' 7 0 9 10 11 '12 13 14'15 = Year Kumber
Component
Production
Fraction
(kWh/yr)
Wind turbines
836,247
27%
QSX15G9
2,140,260
69%
Cat 3508
125,717
4%
Cat 3512
0
0%
Total
3,102,223
100%
500
— �S7C15G9
= Cat 3508
= Cat 3512
u-0
Consumption
Fraction
Load
(kWh/yr)
AC primary load
3,101,035
100%
Total
3,101,035
100%
Quantity
Value
Units
Excess electricity
1,183
kWh/yr
file:///C:/Users/Doug/AppData/Loca
I/Temp/St-Marys-Pilot_Stn,_RE F-6-a na lysis.htm
— Capital
Replacement
Salvage
— Operating
— Fuel
2/6
9/17/12 System Report - St Marys -Pilot Stn, REF 6 analysis
Unmet load 0.000549 kWh/yr
Capacity shortage 0.00 kWh/yr
Renewable fraction 0.166
Thermal
Component
Production
Fraction
(kWh/yr)
726,109
38%
QSX15G9
Cat 3508
45,463
1,138,333
2%
Boiler
60%
Excess electricity
1,183
0%
Total
1,911,089
100%
Q;!(
"K
2N
Y ��5� D r�y5
UO 2
E 1 ED
1-00
5D
,D
rbguninivAve raae IneFinalF'rcfauGiiun
uan Feo mar Apr niay jun. uui Aug pep va rmy L?Ec
Load
Consumption
Fraction
(kWh/yr)
Thermal load
1,905,663
100%
Total
1,905,663
100%
Quantity
Value
Units
Excess thermal energy
5,426
kWh/yr
QS1C15t�9
Cat 3508
— Cat 3512
— Bailer
Ext Eiectrimr t
AC Wind Turbine: Northwind100B, rho=1.272
Variable
Value
Units
Total rated capacity
300
kW
Mean output
95.5
kW
Capacityfactor
31.8
%
Total production
836,247
kWh/yr
Variable
Value
Units
Minimum output
0.00
kW
Maximum output
295
kW
Wind penetration
27.0
%
Hours of operation
7,339
hr/yr
Levelized cost
0.407
$/kWh
file:///C:/Users/Doug/AppData/Loca I/Temp/St_Marys-Pilot_Stn,_RE F_6_a na lysis.htm 3/6
9/17/12 System Report - St Marys -Pilot Stn, REF 6 analysis
24
I
I ortlhw
ind100B. 17o=t.272Out ut
WIL
- rEL - _Pf I.lay �Un .. - _ - _. . -. .. - _-
QSX15G9
Quantity
Value
Units
Hours of operation
8,486
hr/yr
N umber of starts
88
starts/yr
Operational life
2.36
49.0
yr
%
Capacityfactor
Fixed generation cost
21.0
$/hr
Marginal generation cost
0.285
$/kWhyr
Quantity
Value
Units
Electrical production
2,140,260
kWh/yr
Mean electrical output
252
kW
Min. electrical output
1.32
kW
Max electrical output
453
kW
Thermal production
726,109
kWh/yr
Mean thermal output
85.6
kW
Min. thermal output
24.3
kW
Max. thermal output
135
kW
Quantity
Value
Units
Fuel consumption
552,923
L/yr
Specific fuel consumption
0.258
L/kWh
Fuel energy input
5,440,765
kWh/yr
Mean electrical efficiency
39.3
%
Mean total efficiency
52.7
%
3L�4
24 QSX15 9 Qutput kw
400
I
16
a
12 � 1� � � II �1� I � � 2W
c
.;sn Fey Nlaa Apa Niag'
Cat 3508
Quantity
Value
Units
Hours of operation
274
hr/yr
file:///C:/Users/Doug/AppData/Loca I/Temp/St_Marys-Pilot_Stn,_RE F_6_a na lysis.htm 4/6
9/17/12 System Report - St Marys -Pilot Stn, REF 6 analysis
Number of starts
87
starts/yr
Operational life
73.0
yr
Capacityfactor
2.35
%
Fixed generation cost
25.2
$/hr
Marginal generation cost
0.316
$/kWhyr
Quantity
Value
Units
Electrical production
Mean electrical output
125,717
kWh/yr
459
kW
Min. electrical output
308
kW
Max electrical output
546
kW
Thermal production
45,463
kWh/yr
Mean thermal output
166
kW
Min. thermal output
121
kW
Max. thermal output 192 kW
Quantity Value Units
Fuel consumption
33,777
L/yr
Specific fuel consumption
0.269
L/kWh
Fuel energy input
332,366
kWh/yr
Mean electrical efficiency
37.8
%
Mean total efficiency
51.5
%
24
Cat 3512
Quantity
Value
Units
Hours of operation
0
hr/yr
Number of starts
0
starts/yr
Operational life
1,000
yr
Capacityfactor
0.00
%
Fixed generation cost
30.8
$/hr
Marginal generation cost
0.310
$/kWhyr
Quantity
Value
Units
Electrical production
0.00
kWh/yr
Mean electrical output
0.00
kW
Min. electrical output
0.00
kW
Max. electrical output
0.00
kW
file:///C:/Users/Doug/AppData/Loca I/Temp/St_Marys-Pilot_Stn,_RE F_6_a na lysis.htm 5/6
9/17/12 System Report - St Marys -Pilot Stn, REF 6 analysis
Thermal production
0.00
kWh/yr
Mean thermal output
0.00
kW
Min. thermal output
0.00
kW
Max thermal output
0.00
1 kW
Quantity
Value
Units
Fuel consumption
0
L/yr
Specific fuel consumption
0.000
L/kWh
Fuel energy input
0
kWh/yr
Mean electrical efficiency
0.0
%
Mean total efficiency
0.0
%
24
pan Fib Mar Apr :lay uur. ;UI Aug SEG- Oct NDV DEC
Emissions
Pollutant
Emissions (kg/yr)
Carbon dio)ade
1,911,006
Carbon mono)ade
3,814
Unburned hydocarbons
422
Particulate matter
287
Sulfur dioxide
3,851
Nitrogen oxides
34,029
file:///C:/Users/Doug/AppData/Loca I/Temp/St_Marys-Pilot_Stn,_RE F_6_a na lysis.htm 6/6
Saint Mary's, Alaska Wind Power Conceptual Design Analysis P a g e 128
Appendix D, HOMER System Report, St. Mary's, 1 EWT-500 Turbine
V3 ENERGY LLC
Eagle River, Alaska %7,3-10. 047
9/17/12 System Report - St Marys -Pilot Stn, REF 6 analysis
System Report - St Marys -Pilot Stn, REF 6 analysis
Sensitivity case
Primary Load 1 Scaled Average: 8,496 kWh/d
Wind Data Scaled Average: 6.75 m/s
EWT 52-900, rho=1.272 Capital Cost Multiplier: 1
System Fixed O&M Cost: 683,198 $/yr
System architecture
Wind turbine 1 EWT 52-900, rho=1.272
QSX15G9 499 kW
Cat 3508 611 kW
Cat 3512 908 kW
Cost summary
Total net present cost
$ 27,725,176
Levelized cost of energy
$ 0.502/kWh
Operating cost
$ 1,449,923/yr
12,000, D D D
�o,oco,aa�
±R 8,0fl0,000
i�
0
L7 $,000,000
m
4,000,000
Q.
Z 2,000,000
0
-2,000,000
Casty HOW _.' OF WM
Capital Replacement wpErating FuEI SSIV13gE
Net Present Costs
EINT52-9DG, rtra=1.272
— 12SX15G9
— Cat 35
— Cat 3512
— 8viler
- Other
Component
Capital
Replacement
OEM
Fuel
Salvage
Total
EWT 52-900, rho=1.272
6,153,991
0
717,838
0
0
6,871,830
QSX15G9
0
393,079
292,528
7,640,398
-5,606
8,320,399
Cat 3508
0
0
5,728
375,983
-35,131
346,580
Cat 3512
0
0
0
0
-40,695
-40,695
Boiler
0
0
0
2,062,807
0
2,062,807
Other
0
0
10,164,263
0
0
10,164,263
System
6,153,991
1 393,079
11,180,359
10,079,184
-81,432
27,725,180
Annualized Costs
Capital I Replacement I O&M
Component
file:///C:/Users/Doug/AppData/Loca I/Temp/St_Marys-Pilot_Stn,_RE F_6_a na lysis.htm
Fuel I Salvage I Total
1/6
9/17/12
System Report - St Marys -Pilot Stn, REF 6 analysis
EWT 52-900, rho=1.272
QSX15G9
($/Yr)
($/Yr)
($/Yr)
($/Yr)
($/Yr)
($/Yr)
413,645
0
48,250
0
0
461,895
0
26,421
19,663
513,555
-377
559,262
Cat 3508
0
0
385
25,272
1 -2,361
23,296
Cat 3512
0
0
0
0
-2,735
-2,735
Boiler
0
0
0
138,653
0
138,653
Other
0
0
683,198
0
0
683,198
System
413,645
1 26,421
751,496
677,480
-5,474
1 1,863,568
2.000.0100
fl
i;
0
m
C�
m-4,000,000
C
,r
O
-8,000,000
0 1 2 3 e, 5 - 2 5 10 11 12 1" 'q 15 1'
Year llmrtber
Electrical
Component
Production
Fraction
(kWh/yr)
2,483,950
63%
Wind turbine
QSX15G9
1,394,670
35%
Cat 3508
70,731
2%
Cat 3512
0
0%
Total
3,949,351
100%
M0
e[
400
Y
300
4 200
d
100
ID
Consumption
Fraction
Load
(kWh/yr)
AC primary load
3,101,035
100%
Total
3,101,035
100%
Quantity
Value
Units
Excess electricity
848,323
kWh/yr
file:///C:/Users/Doug/AppData/Loca
I/Temp/St-Marys-Pilot_Stn,_RE F-6-a na lysis.htm
— �S7C15G9
= Cat 3508
= Cat 35112
— Capital
Replacement
Salvage
— Operating
— Fuel
2/6
9/17/12 System Report - St Marys -Pilot Stn, REF 6 analysis
Unmet load 0.000183 kWh/yr
Capacity shortage 0.00 kWh/yr
Renewable fraction 0.425
Thermal
Component
Production
Fraction
(kWh/yr)
QSX15G9
529,058
23%
Cat 3508
25,573
1 %
Boiler
857,821
38%
Excess electricity
848,323
38%
Total
2,260,776
100%
410c
F.9OninIV Ave FBCie 1 rfermal YrOaucroon
dan reD F., APT riay,run uui ,qua pep UIX MW L,__
Load
Consumption
Fraction
(kWh/yr)
Thermal load
1,905,663
100%
Total
1,905,663
100%
Quantity
Value
Units
Excess thermal energy
355,113
kWh/yr
AC Wind Turbine: EWT 52-900, rho=1.272
Variable
Value
Units
Total rated capacity
900
kW
Mean output
284
kW
Capacityfactor
31.5
%
Total production
2,483,950
1 kWh/yr
Variable
Value
Units
Minimum output
0.00
kW
Maximum output
885
kW
Wind penetration
80.1
%
Hours of operation
8,218
hr/yr
Levelized cost
0.186
$/kWh
QS1C15t�9
Cat 3508
Cat 3512
Bailer
F me&E Eiectrimr t
file:///C:/Users/Doug/AppData/Loca I/Temp/St_Marys-Pilot_Stn,_RE F_6_a na lysis.htm 3/6
9/17/12 System Report - St Marys -Pilot Stn, REF 6 analysis
F65fTFi?_4Rf1. rht-9_MObi fr:iit lkw
24
-__ .-... IYIay Jun — - _ - _. - _. .. _
QSX15G9
Quantity
Value
Units
Hours of operation
7,865
hr/yr
N umber of starts
232
starts/yr
Operational life
2.54
yr
Capacityfactor
31.9
%
Fixed generation cost
21.0
$/hr
Marginal generation cost
0.285
$/kWhyr
Quantity
Value
Units
Electrical production
1,394,670
kWh/yr
Mean electrical output
177
kW
Min. electrical output
0.188
kW
Max electrical output
453
kW
Thermal production
529,058
kWh/yr
Mean thermal output
67.3
kW
Min. thermal output
24.0
kW
Max. thermal output
135
1 kW
Quantity
Value
Units
Fuel consumption
386,131
L/yr
Specific fuel consumption
0.277
L/kWh
Fuel energy input
3,799,532
kWh/yr
Mean electrical efficiency
36.7
%
Mean total efficiency
50.6
%
4_+
i
D9Y1r1rt'4 OLItnidt
k
1Clay iun
Cat 3508
Quantity
Value
Units
Hours of operation
154
hr/yr
400
Soo
200
100
0
file:///C:/Users/Doug/AppData/Loca I/Temp/St_Marys-Pilot_Stn,_RE F_6_a na lysis.htm 4/6
9/17/12 System Report - St Marys -Pilot Stn, REF 6 analysis
Number of starts
59
starts/yr
Operational life
130
yr
Capacityfactor
1.32
%
Fixed generation cost
25.2
$/hr
Marginal generation cost
0.316
$/kWhyr
Quantity
Value
Units
Electrical production
Mean electrical output
70,731
kWh/yr
459
kW
Min. electrical output
368
kW
Max electrical output
546
kW
Thermal production
25,573
kWh/yr
Mean thermal output
166
kW
Min. thermal output 139 kW
Max. thermal output 192 kW
Quantity Value Units
Fuel consumption
19,001
L/yr
Specific fuel consumption
0.269
L/kWh
Fuel energy input
186,974
kWh/yr
Mean electrical efficiency
37.8
%
Mean total efficiency
51.5
%
24
Cat 3512
Quantity
Value
Units
Hours of operation
0
hr/yr
Number of starts
0
starts/yr
Operational life
1,000
yr
Capacityfactor
0.00
%
Fixed generation cost
30.8
$/hr
Marginal generation cost
0.310
$/kWhyr
Quantity
Value
Units
Electrical production
0.00
kWh/yr
Mean electrical output
0.00
kW
Min. electrical output
0.00
kW
Max. electrical output
0.00
kW
TT
i
file:///C:/Users/Doug/AppData/Loca I/Temp/St_Marys-Pilot_Stn,_RE F_6_a na lysis.htm 5/6
9/17/12 System Report - St Marys -Pilot Stn, REF 6 analysis
Thermal production
0.00
kWh/yr
Mean thermal output
0.00
kW
Min. thermal output
0.00
kW
Max thermal output
0.00
1 kW
Quantity
Value
Units
Fuel consumption
0
L/yr
Specific fuel consumption
0.000
L/kWh
Fuel energy input
0
kWh/yr
Mean electrical efficiency
0.0
%
Mean total efficiency
0.0
%
24
pan Fib Mar Apr :lay uur. ;UI Aug SEG- Oct NDV DEC
Emissions
Pollutant
Emissions (kg/yr)
Carbon dio)ade
1,342,680
Carbon mono)ade
2,633
Unburned hydocarbons
292
Particulate matter
199
Sulfur dioxide
2,707
Nitrogen oxides
23,498
file:///C:/Users/Doug/AppData/Loca I/Temp/St_Marys-Pilot_Stn,_RE F_6_a na lysis.htm 6/6
Saint Mary's, Alaska Wind Power Conceptual Design Analysis P a g e 129
Appendix E, HOMER System Report, St. Mary's + Pilot Station, 1 EWT-500
Turbine
V3 ENERGY LLC
Eagle River, Alaska %7,3-10. 047
9/17/12 System Report - St Marys -Pilot Stn, REF 6 analysis
System Report - St Marys -Pilot Stn, REF 6 analysis
Sensitivity case
Primary Load 1 Scaled Average: 13,726 kWh/d
Wind Data Scaled Average: 6.75 m/s
EWT 52-900, rho=1.272 Capital Cost Multiplier: 1.04
System Fixed O&M Cost: 964,500 $/yr
System architecture
Wind turbine 1 EWT 52-900, rho=1.272
QSX15G9 499 kW
Cat 3508 611 kW
Cat 3512 908 kW
Cost summary
Total net present cost
$ 39,219,376
Levelized cost of energy
$ 0.465/kWh
Operating cost
$ 2,205,058/yr
Cast Flaw Smlmry
20,000,000
15,000,000
0
L7
10,000,000
Q.
m
Vm
Z
0
-5,0D0,D00
Capital Replacement Oper$tirtg FuEI SSIV13gE
Net Present Costs
Ef 52-9DG, rtra=1.272
— 12SX15139
— Cat 35
— Cat 3512
— 8viler
- Other
Component
Capital
Replacement
O&M
Fuel
Salvage
Total
EWT 52-900, rho=1.272
6,413,689
0
717,838
0
0
7,131,528
QSX15G9
0
218,024
166,553
3,832,180
-21,676
4,195,081
Cat 3508
0
100,115
79,706
4,915,244
-35,588
5,059,477
Cat 3512
0
100,004
79,483
6,654,991
-35,837
6,798,643
Boiler
0
0
0
1,685,331
0
1,685,331
Other
0
0
14,349,329
0
0
14,349,329
System
6,413,689
1 418,143
15,392,909
17,087,746
-93,101
39,219,392
Annualized Costs
Capital I Replacement I O&M
Component
file:///C:/Users/Doug/AppData/Loca I/Temp/St_Marys-Pilot_Stn,_RE F_6_a na lysis.htm
Fuel I Salvage I Total
1/6
9/17/12
System Report - St Marys -Pilot Stn, REF 6 analysis
EWT52-900,rho=1.272
QSX15G9
($/Yr)
($/Yr)
($/Yr)
($/Yr)
($/Yr)
($/Yr)
431,101
0
48,250
0
0
479,351
0
14,655
11,195
257,583
-1,457
281,975
Cat 3508
0
6,729
5,358
330,382
-2,392
340,076
Cat 3512
0
6,722
5,343
447,320
-2,409
456,976
Boiler
0
0
0
113,281
0
113,281
Other
0
0
964,500
0
0
964,500
System
431,101
28,106
1 1,034,645
1,148,565
1 -6,258
1 2,636,159
2,0110,000
4
0
li-2,OU8,000
s
m
C�
R-4,000,000
C
,r
O
Z -a,00-13,000
-8,000,00-0
U 1 2 3 e, 5 e. f 5 1D 11 12 1
Electrical
Component
Production
Fraction
(kWh/yr)
2,483,950
46%
Wind turbine
QSX15G9
672,038
13%
Cat 3508
916,917
17%
Cat 3512
1,275,518
24%
Total
5,348,422
100%
s00
— �S7C15G9
= Cat 3508
Cat 3512
Y
4-1310
4
20-D
Consumption
Fraction
Load
(kWh/yr)
AC primary load
5,009,989
100%
Total
5,009,989
100%
Quantity
Value
Units
Excess electricity
338,447
kWh/yr
file:///C:/Users/Doug/AppData/Loca
I/Temp/St-Marys-Pilot_Stn,_RE F-6-a na lysis.htm
— Capital
Replacement
Salvage
— Operating
— Fuel
2/6
9/17/12
System Report - St Marys -Pilot Stn, REF 6 analysis
Unmet load 0.00555 kWh/yr
Capacity shortage 0.00 kWh/yr
Renewable fraction 0.332
Thermal
Component
Production
Fraction
(kWh/yr)
271,406
13%
QSX15G9
Cat 3508
336,030
16%
Cat 3512
Boiler
447,474
21 %
700,847
33%
Excess electricity
338,447
16%
Total
2,094,204
100%
B50
C110
259
2,06
E 15C
10
50
11 11 11� n ��� � wwnl 11
11 �nnnnnn
�n i nnnnnn
1:�11:. ■ v 11 11 11 11 II sY.YW
Load Consumption Fraction
(kWh/yr)
Thermal load 1,905,663 100%
Total 1,905,663 100%
Quantity Value Units
Excess thermal energy 188,542 kWh/yr
AC Wind Turbine: EWT 52-900, rho=1.272
Variable
Value
Units
Total rated capacity
900
kW
Mean output
284
kW
Capacityfactor
31.5
%
Total production
2,483,950
kWh/yr
Variable
Value
Units
Minimum output
0.00
kW
Maximum output
885
kW
Wind penetration
49.6
%
Hours of operation
8,218
hr/yr
Levelized cost
0.193
1 $/kWh
QS1€15G8
— cat 3508
- Gat 3512
- Boiler
Excess Electricity
file:///C:/Users/Doug/AppData/Loca I/Temp/St_Marys-Pilot_Stn,_RE F_6_a na lysis.htm 3/6
System Report - St Marys -Pilot Stn, REF 6 analysis
F65fTFi?_4fH1. rht-9_MObi fr:iit
kVw
QSX15G9
Quantity
Value
Units
Hours of operation
4,478
hr/yr
N umber of starts
431
starts/yr
Operational life
4.47
15.4
yr
%
Capacityfactor
Fixed generation cost
21.0
$/hr
Marginal generation cost
0.285
$/kWhyr
Quantity
Value
Units
Electrical production
Mean electrical output
672,038
kWh/yr
150
kW
Min. electrical output
0.413
kW
Max electrical output
499
kW
Thermal production
271,406
kWh/yr
Mean thermal output
60.6
kW
Min. thermal output
24.0
kW
Max. thermal output
146
kW
Quantity
Value
Units
Fuel consumption
193,671
L/yr
Specific fuel consumption
0.288
L/kWh
Fuel energy input
1,905,724
kWh/yr
Mean electrical efficiency
35.3
%
Mean total efficiency
49.5
%
11119.71W
24
m 1B
a
0
x �
U
Jan Fea pa play jun _.4f - _
Cat 3508
Quantity
Value
Units
Hours of operation
2,143
hr/yr
file:///C:/Users/Doug/AppData/Loca I/Temp/St_Marys-Pilot_Stn,_RE F_6_a na lysis.htm 4/6
9/17/12 System Report - St Marys -Pilot Stn, REF 6 analysis
Number of starts
680
starts/yr
Operational life
9.33
yr
Capacityfactor
17.1
%
Fixed generation cost
25.2
$/hr
Marginal generation cost
0.316
$/kWhyr
Quantity
Value
Units
Electrical production
Mean electrical output
916,917
kWh/yr
428
kW
Min. electrical output
22.6
kW
Max electrical output
555
kW
Thermal production
336,030
kWh/yr
Mean thermal output
157
kW
Min. thermal output
37.4
kW
Max. thermal output
194 kW
Value Units
Quantity
Fuel consumption
248,407
L/yr
Specific fuel consumption
0.271
L/kWh
Fuel energy input
2,444,326
kWh/yr
Mean electrical efficiency
37.5
%
Mean total efficiency
51.3
%
24
Cat 3512
Quantity
Value
Units
Hours of operation
2,137
hr/yr
N umber of starts
302
starts/yr
Operational life
9.36
yr
Capacityfactor
16.0
%
Fixed generation cost
30.8
$/hr
Marginal generation cost
0.310
$/kWhyr
Quantity
Value
Units
Electrical production
1,275,518
kWh/yr
Mean electrical output
597
kW
Min. electrical output
89.2
1 kW
Max electrical output
814
kW
l4T M
Q00
4W
240
120
0
file:///C:/Users/Doug/AppData/Loca I/Temp/St_Marys-Pilot_Stn,_RE F_6_a na lysis.htm 5/6
9/17/12 System Report - St Marys -Pilot Stn, REF 6 analysis
Thermal production
447,474
kWh/yr
Mean thermal output
209
kW
Min. thermal output
65.2
kW
Max thermal output
271
kW
Quantity
Value
Units
Fuel consumption
336,331
L/yr
Specific fuel consumption
Fuel energy input
0.264
L/kWh
kWh/yr
%
3,309,494
Mean electrical efficiency
38.5
Mean total efficiency
52.1
%
24
an Feb Mar Apr hbay Jun. Jul Aug Sep � _. , _ . � _L
Emissions
Pollutant
Emissions (kg/yr)
Carbon dio)ade
2,275,165
Carbon mono)ade
5,060
Unburned hydocarbons
560
Particulate matter
381
Sulfur dio)ade
4,577
Nitrogen oxides
45,148
file:///C:/Users/Doug/AppData/Loca I/Temp/St_Marys-Pilot_Stn,_RE F_6_a na lysis.htm 6/6