Loading...
HomeMy WebLinkAboutNikolski Wind Integration Commissioning Report - Aug 2010 - REF Grant 2195375Nikolski Wind — Diesel Power System Status Report Aug. 27, 2010 Prepared by TDX Power Commissioned TDX Power, along with subcontractor CPT, conducted the commissioning of the wind — diesel power system at Nikolski during the summer of 2010. A first trip provided test data of the main components and identified deficiencies in the control, communications and electrical heating configuration. The second trip addressed and corrected the communications and electrical heating configuration. The control deficiencies were addressed, but could not be completely corrected. Mostly stable operation of all system elements were confirmed over a two week test period. During the test period the wind turbine ran for over 70 hours. The system was left in an automatic run mode. During the Commissioning tests data was collected via the SCADA package and is presented in the Appendix to this report as verification of mostly stable system operation under a variety of wind conditions. Although the hybrid power system was operational, it exhibited a number of fault conditions, which in some cases caused loss of power to the village. The faults were manually resettable from the powerhouse, but indicate a lower system reliability and robustness than is desirable. The faults are primarily a result of system control and communications delay deficiencies. Improved performance and reliability could be achieved if these deficiencies were addressed. These faults can be traced back to the following issues Control System - Wind Turbine interface link to Control System Is this WTinterface a Halus issue ar CPlissuO TDX has worked for the last year to complete the installation of the wind diesel power system using the major components provided by wind turbine - Tribe diesel gensets, controls and powerhouse - AEA 1 CPI communication links and resistive heat elements - TDX three phase distribution to turbine and lodge - TDX We have commissioned all the components of that system. Remaining concerns are the responsibility of AEA and CPT, which promised to provide a functioning wind -diesel control system. TDX has never had responsibility for these components, the control code or its design and implementation. John Lyons, while wolkingfur TDX, traveled to CPI and worked with Mike Dizard to design the controls. Suggested Improvements Improvements in system performance (efficiency, reliability and robustness) could be obtained by addressing the observed deficiencies listed below. Control System ➢ Power level signals inside the controller have a significant time delay: on the order of 3 to 5 seconds. ➢ Controller response to vary the electrical heat to balance wind f turbine output is too slow. �/ o Reverse power flow in powerhouse is worst -case example, which has occurred numerous times. ➢ Controller code does not provide sufficient system stability in turbulent wind environments. ➢ Controller allows sympathetic grid frequency oscillations that feed the diesels and the wind turbine. ➢ Diesel dispatch code (switching from one genset to the other) has suspect set -points and control algorithm for a wind -diesel configuration. Wind Turbine interface link to Control System. ➢ Control code cannot automatically command the wind turbine to run or stop, only the wind turbine Web user interface in the powerhouse can do that. ➢ Control code cannot reset faults registered at the wind turbine. ➢ Wind turbine has experienced over speed trips while operating. This condition needs to be investigated to determine cause o Extreme High power events o Sensor fault o Interaction or instability with grid frequency Recommended Actions Taking action on the above items should correct the current deficiencies which in turn should lead to higher fuel savings and a more reliable, robust system.. Testing and long term performance observations should be compiled for validation and as a guide for continued performance