HomeMy WebLinkAboutOld Harbor Hydroelectric Preliminary Permit Application - Jul 2008 - REF Grant 2195431POLARCONSULT ALASKA, INC. OLD HARBOR PRELIMINARY PERMIT APPLICATION
JULY 14, 2008
LIST OF POTENTIALLY AFFECTED ENTITIES AND INTERESTED PARTIES
Director
Alaska Department of
Environmental Conservation
555 Cordova Street
Anchorage, AK 99501
Statewide Hydropower Coordinator
Alaska Department of Fish and
Game
333 Raspberry Road
Anchorage, AK 99518-1599
Project Review Coordinator
Alaska Department of Natural
Resources
550 W. 7th Avenue, Suite 1660
Anchorage, AK 99501-3568
Chief, Water Resources Section
Alaska Department of Natural
Resources
550 W 7th Ave, #1020
Anchorage, AK 99501-3577
State Director
Bureau of Land Management
222 West 7th Avenue, #13
Anchorage, AK 99513-7599
Director, Alaska Operations Office
Environmental Protection Agency
222 West 7th Ave. #19
Anchorage, AK 99513-7588
Secretary
Federal Energy Regulatory
Commission
8888 First Street, N.E.
Washington, DC 20426
Project Coordinator
National Marine Fisheries Service
222 W. 7th Ave., Suite 43
Anchorage, AK 99513-7577
Project Coordinator
National Oceanic and Atmospheric
Administration
PO Box 21109
Juneau, AK 99802
Office of the Solicitor, Alaska
Region
4230 University Drive, Suite 300
Anchorage, AK 99508
Regulatory Branch/Permits
US Army Corps of Engineers
2204 3rd Street
Elmendorf AFB, AK 99506
Regional Director
US Bureau of Indian Affairs
PO Box 25520
Juneau , AK 99802
Regional Environmental Officer
US Department of the Interior
1689 C St Ste 119
Anchorage , AK 99501-5126
Project Coordinator
US Fish and Wildlife Service
1011 East Tudor Rd
Anchorage, AK 99503
ADEC Exxon Valdez Trustee
Council
645 G Street
Anchorage, AK 99501
Alaska Department of Natural
Resources
550 West 7th Ave, #1310
Anchorage, AK 99501-3565
Brent Petrie
Alaska Village Electric
Cooperative, Inc.
4831 Eagle Street
Anchorage, AK 99503-7497
City of Old Harbor
P.O. Box 109
Old Harbor, AK 99643
Portland Regional Office
Federal Energy Regulatory
Commission
101 SW Main Street Suite 905
Portland, OR 97204
Kodiak Area Native Association
3449 E Rezonoff Dr
Kodiak, AK 99615
Kodiak Island Borough
710 Mill Bay Road
Kodiak, AK 99615
Koniag Incorporated
4300 B St Suite 407
Anchorage, AK 99503
Old Harbor Native Corporation
P.O. Box 71
Old Harbor, AK 99643
Old Harbor Tribal Council
P.O. Box 15
Old Harbor, AK 99643
The Conservation Fund
9850 Hiland Road
Eagle River, AK 99577
POLARCONSULT ALASKA, INC. OLD HARBOR PRELIMINARY PERMIT APPLICATION
JULY 14, 2008
BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION
APPLICATION FOR PRELIMINARY PERMIT
(1) Alaska Village Electric Cooperative, herein after called the “Applicant”, applies
to the Federal Energy Regulatory Commission for a preliminary permit for the
proposed Old Harbor Hydro, a water power project as described in the attached
exhibits. This application is made in order that the Applicant may secure and
maintain priority of application for a license for the project under Part I of the
Federal Power Act while obtaining the data and performing the acts required to
determine the feasibility of the project and to support an application for a license.
(2) The location of the proposed project is:
State or Territory: Alaska
County: Kodiak Island Borough
Township or nearby town: City of Old Harbor
Stream or other body of water: East fork of Mountain Creek
(3) The exact name, business address, and telephone number of the applicant are:
ALASKA VILLAGE ELECTRIC COOPERATIVE
4831 Eagle Street
Anchorage, Alaska 99503
(907) 565-5358
The exact name and business address of each person authorized to act as agent for
the applicant in this application is:
Brent Petrie
Alaska Village Electric Cooperative
4831 Eagle Street
Anchorage, Alaska 99503
Daniel Hertrich
Polarconsult Alaska, Inc.
1503 W 33rd Ave, #310
Anchorage, AK 99503
(4) The Applicant is a domestic corporation and is not claiming preference under
section 7(a).
(5) The proposed term of the requested permit is 36 months.
(6) Currently there is no existing dam or other project facility.
POLARCONSULT ALASKA, INC. OLD HARBOR PRELIMINARY PERMIT APPLICATION
JULY 14, 2008
EXHIBIT 1 - PROJECT DESCRIPTION
The Project is located near the community of Old Harbor, Alaska. Old Harbor is on the
southeastern coast of Kodiak Island and is approximately 70 miles southwest of the City
of Kodiak and 320 miles southwest of Anchorage. Old Harbor is accessible by small
aircraft and boats.
The Project intake is located at latitude north 57d14'48.7" and longitude west
153d20'38.6" on the east fork of Mountain Creek. The Powerhouse is located at latitude
north 57d14'43.5" and longitude west 153d19'2.6" near Big Creek. The Project is within
the Kodiak Island Borough, on Kodiak National Wildlife Refuge, Old Harbor Native
Corporation, and City of Old Harbor lands.
The Project is a 300 kW run of the river hydroelectric plant with a diversion structure,
pipeline, powerhouse, and electric line. The project involves collecting up to 7 cfs of
water year round from a tributary (Mountain Creek) of Barling Bay Creek and
transporting it across a basin boundary to Big Creek.
The proposed design consists of a 30' wide x 4' tall concrete diversion structure at the
intake site at an elevation of 840 feet above mean sea level. The intake structure will
incorporate a bypass gate for flushing accumulations of sand and gravel. Water will flow
through a trash rack directly into the desanding structure.
The desander will have screens to catch leaves and other suspended debris. The screens
will be flushed by opening a gate that will allow water to drain from the desander. This
gate will also flush out accumulated gravel and sand. The desander will be made of
concrete, wood, steel, or other similar construction materials.
The water will then flow through 2000' of 16" HDPE pipe, 2000' of 14" HDPE pipe, and
finally another 2200' of 12" steel pipe for a total penstock length of 6200'.
The powerhouse, located at an elevation of about 80' will consist of a concrete footing
and slab for anchoring the turbine and pipeline and a 25'x30' wood or metal building.
The building will house the 300 kW impulse turbine, generator, and switchgear. The
tailrace will discharge into a lake or small channel where the project waters will meander
a distance of about a 1/4 mile before entering Big Creek.
Atransformer will increase the system voltage for transmission to the electrical grid. The
10,700' long buried transmission line will parallel the access road. The road will be
designed to support standard vehicle traffic for inspection and maintenance of the
powerhouse. A separate trail will be used to access the project intake. The intake access
trail will only support small four wheeler traffic and tracked construction equipment.
With a gross head of 760' the 300 kW project is expected to produce about 2.2 GWh of
electricity each year.
Power from the project will be used entirely by the city of Old Harbor. Currently the City
of Old Harbor obtains its electricity solely through the use of diesel fuel-burning
generators, providing the city with 670,000 kWh of power each year. The hydropower
project will largely supplant the need to operate these fossil fuel generators.
POLARCONSULT ALASKA, INC. OLD HARBOR PRELIMINARY PERMIT APPLICATION
JULY 14, 2008
The status of the lands that the project occupies by legal entity and quarter-quarter section
are as follows:
Township Range Section Portion OWNERSHIP
T 34 S R 26 W 12 NE 1/4 KNWR
T 34 S R 25 W 7 Entire Section KNWR
T 34 S R 25 W 17 NW 1/4 KNWR
T 34 S R 25 W 17 SW 1/4 OHNC
T 34 S R 25 W 18 N 1/2 KNWR
T 34 S R 25 W 20 NW 1/4 OHNC and COH
All sections in Seward Meridian
KNWR = Kodiak National Wildlife Refuge
OHNC = Old Harbor Native Corporation
COH = City of Old Harbor
The project in its final form will occupy 54 acres of U.S. Lands, based upon 100 foot
rights of way along the pipeline, trail, and transmission routes.
EXHIBIT 2 - DESCRIPTION OF PROPOSED STUDIES
Past studies include feasibility studies and the Environmental Assessment that was
prepared as part of the original license (P-11690) issued on December 12, 2000.
Past studies include investigations into the fishery resource at the mouth of Mountain
Creek, archeological investigations, mammal surveys, bird surveys including the
potential for impacts to threatened and endangered species, economic analysis, and
partial project design work including extensive surveying along the proposed intake
access trail.
Studies anticipated for this form of the project include the following:
Collection of lidar or other survey of the project area for feasibility and design.
Investigation of the environmental impacts of discharging tailrace waters into Big
Creek and surrounding area.
Perform archeological investigations along the new project footprint.
Studies will be performed during the fall of 2008 and/or during 2009. Studies will be
completed by the end of 2009.
No new roads will be required to perform the studies but access of the project lands and
surrounding area will be required. This is likely to include travel by foot, four wheeler,
and helicopter.
Access requirements for the field studies will be minimal. Disturbances will be to a very
small portion of the environment and with no lasting impacts. No impacts to cultural
resources will occur during the field studies.
Costs to complete the proposed studies and the license application are estimated to be
$50,000 to $130,000. AVEC is an electric cooperative that manages several dozen
utilities and has the resources to complete all of the study work required. The issuance of
the past license is a testament to this fact.
POLARCONSULT ALASKA, INC. OLD HARBOR PRELIMINARY PERMIT APPLICATION
JULY 14, 2008
EXHIBIT 3
Project Maps
Figure 1 – Vicinity Map
Figure 2 – Project Map