Loading...
HomeMy WebLinkAboutMarshall Wind Project Concept Design Report - Oct 2013 - REF Grant 7040021MARSHALL WIND PROJECT CONCEPT DESIGN REPORT Prepared By: Mark Swenson, PE 3335 Arctic Blvd., Ste. 100 Anchorage, AK 99503 Phone: 907.564.2120 Fax: 907.564.2122 October 7, 2013 Prepared For: Alaska Village Electric Cooperative 4831 Eagle Street Anchorage, Alaska 99503 Alaska Village Marshall Wind Project Electric Cooperative Concept Design Report i 1.0 EXECUTIVE SUMMARY This report has been prepared for the Alaska Village Electric Cooperative (AVEC) to provide conceptual design and cost analysis for development of wind power generation in the community of Marshall, Alaska. Marshall is a rural community of approximately 407 year– round residents located on the north bank of Polte Slough, north of Arbor Island, on the east bank of the Yukon River in the Yukon Kuskokwim Delta. Integration of wind generated power into the existing electrical power generation system will offset diesel consumption costs and provide a renewable energy resource for this rural community. On December 18, 2008, a meteorological (met) tower was installed along the airport access road approximately 0.8 miles from Marshall. The met tower collapsed on October 12, 2009 due to an anchor failure during a strong wind event. The met tower was reinstalled at the same location during September 2012 to obtain additional wind data. The met tower is equipped with instrumentation and data loggers to evaluate and record the wind resource. The wind data collected during the met tower operation suggests that the existing wind regime is suitable for wind power generation. The results of the data acquisition and analysis of the wind resource are included in the “Marshall Wind Diesel Feasibility Study”dated October, 2013 (Appendix A). On August 7, 2012 AVEC, Hattenburg Dilley & Linnell (HDL), and V3 Energy performed a site visit to Marshall to investigate three separate locations near the community, where computer modeling identified good wind resource potential. During the site visit it was confirmed that the site where the met tower was installed is the most suitable location for installing wind turbines. For this report, AVEC selected three wind turbine configurations for evaluation. •The first configuration includes (3) Northern Power 100 Arctic turbines (NP100), formerly known as the Northwind 100. The Northern Power 100 Arctic turbines installed in Marshall will include 37 meter (121 foot) monopole towers and 21 meter blades. The NP100s are permanent magnet, direct drive wind power generator that AVEC previously installed in 10 other villages in rural Alaska. The (3) Northern Power 100 Arctic tower array has a maximum power generation output of 300 kW. •The second turbine configuration consists of (3) Vestas V20 turbines. The Vestas V20 turbine 120 kW, induction generator, installed on a 32 meter (105 foot) tower. This configuration has a maximum power generation output of 360 kW and requires a cold weather kit modification for use in Marshall. The generators will be controlled using a simple inverter with soft start and soft breaking capabilities or a more complex variable speed drive (VSD) inverter at each turbine. The turbine blades are fixed pitch. •The third turbine configuration consists of (1) Aeronautica AW33 225 turbine. The AW33 225 turbine is a 225 kW, induction generator, installed on a 40 meter (131 foot) tower. This configuration has a maximum power generation output of 225 kW. The generator will be controlled using a simple inverter with soft start and soft breaking capabilities or a more Alaska Village Marshall Wind Project Electric Cooperative Concept Design Report ii complex variable speed drive (VSD) inverter at each turbine. The turbine blades are stall regulated to limit rotation speed and torque in extreme wind events. It is anticipated that the Northern Power 100 turbines and the AW33 225 turbines would be installed on monopole towers and the V20 turbines would be installed on lattice towers. Foundations will likely include precast concrete gravity mats with rock anchors, if additional resistance is required to counteract the overturning moment of the turbines. A comparison of the three turbine configurations installed at preferred location in Marshall is presented in Tables EX 1 and EX 2 below. Table EX 1: Turbine Alternative Comparison Summary Alt Turbine Selection Site Generation Capacity (kW) Estimated Capital Cost Estimated Capital Cost per Installed kW Estimated Annual Energy Production @ 100 % Availability 1 (3) NP 100s Met Tower 300 $ 3.2 M $10,580 779,125 kWh 2 (3) V20s Met Tower 360 $ 2.9 M $8,029 718,989 kWh 3 (1) AW33 225 Met Tower 225 $ 2.7 M $11,824 653,658 kWh Source: Annual Energy Production data taken from V3 Energy’s October 2013 Marshall Wind Diesel Feasibility Analysis Table EX 2: Economic Analysis Summary Alt Annual Wind Generation @ 80% Availability (kWh) Wind Energy For Power (kWh/yr) Wind Energy For Heat (kWh/yr) Wind as % Total Power Production (%) Power Generation: Fuel Displaced by Wind Energy (gal/yr) Heating Fuel Displaced By Wind Energy (gal/yr) 1 623,300 523,707 99,593 37.4 48,893 2,546 2 575,191 471,521 103,670 34.6 38,977 2,650 3 522,926 467,889 55,037 31.4 37,454 1,407 Source: Annual Energy Production data taken from V3 Energy’s October 2013 Marshall Wind Diesel Feasibility Analysis We recommend AVEC proceed with design and permitting for installation of Alternative 1 (three Northern Power 100 Arctic turbines) in Marshall. This alternative is recommended because it maximizes the power output for Marshall’s wind regime. Also, as described in detail in the report, the NP100 option matches the majority of the wind turbine fleet that AVEC has installed in other villages throughout Alaska. AVEC’s Operations staff is familiar with this turbine and maintenance and replacement parts are already in stock or readily available. Alaska Village Marshall Wind Project Electric Cooperative Concept Design Report iii Table of Contents 1.0 EXECUTIVE SUMMARY...........................................................................................................i 1.0 INTRODUCTION.................................................................................................................... 1 1.1 BACKGROUND....................................................................................................................... 1 1.2 LOCATION.............................................................................................................................. 2 1.3 CLIMATE................................................................................................................................ 2 1.4 ELECTRICAL DEMAND ........................................................................................................... 2 1.5 EXISTING ELECTRICAL POWER SYSTEMS............................................................................... 3 1.6 MARSHALL RECOVERED HEAT POTENTIAL ........................................................................... 3 1.7 TRANSMISSION LINE EXTENSIONS........................................................................................ 4 1.8 REQUIRED POWER PLANT IMPROVEMENTS......................................................................... 4 1.9 GEOTECHNICAL INFORMATION............................................................................................ 4 1.10 LIMITATIONS....................................................................................................................... 5 2.0 MARSHALL WIND SITE ANALYSIS......................................................................................... 5 2.1 WIND TURBINE SITE INVESTIGATION ................................................................................... 5 2.1.1 METEOROLIGICAL (MET) TOWER SITE...................................................................... 6 2.1.2 ALTERNATIVE SITE 1.................................................................................................. 7 2.1.3 ALTERNATIVE SITE 2.................................................................................................. 7 2.1.4 ALTERNATIVE SITE 3.................................................................................................. 8 3.0 WIND DATA ACQUISITION AND MODELING........................................................................ 9 3.1 MARSHALL WIND RESOURCE................................................................................................ 9 4.0 WIND TURBINE SYSTEM ALTERNATIVES............................................................................ 10 4.1 MARSHALL WIND TURBINE ANALYSIS ................................................................................ 10 4.1.1 NORTHERN POWER 100 ARCTIC............................................................................. 10 4.1.2 Vestas V20............................................................................................................... 11 4.1.3 Aeronautica AW33 225........................................................................................... 11 4.2 ALTERNATIVE 1 (3) NP100 TURBINES ............................................................................ 12 4.3 ALTERNATIVE 2 (3) V20 TURBINES.................................................................................. 12 4.4 ALTERNATIVE 3 (1) AW33 225 TURBINES....................................................................... 12 Alaska Village Marshall Wind Project Electric Cooperative Concept Design Report iv 4.5 ALTERNATIVE COMPARISON SUMMARY............................................................................ 13 5.0 ECONOMIC EVALUATION................................................................................................... 13 5.1 METHODOLOGY AND APPROACH....................................................................................... 13 5.2 ECONOMIC EVALUATION RESULTS..................................................................................... 14 6.0 PREFERRED ALTERNATIVE.................................................................................................. 14 7.0 PERMITTING, ENVIRONMENTAL, AND LAND OWNERSHIP ............................................... 15 7.1 FEDERAL AVIATION ADMINISTRATION (FAA)..................................................................... 15 7.2 US FISH AND WILDLIFE SERVICE (USFWS) .......................................................................... 15 7.3 STATE HISTORIC PRESERVATION OFFICE (SHPO)................................................................ 16 7.4 DEPARTMENT OF THE ARMY (DA)...................................................................................... 17 7.5 CONTAMINATED SITES, SPILLS, AND UNDERGROUND TANKS........................................... 17 7.6 AIR QUALITY........................................................................................................................ 17 7.7 NATIONAL ENVIRONMENTAL POLICY ACT REVIEW (NEPA)................................................ 17 7.8 LAND OWNERSHIP.............................................................................................................. 18 8.0 CONCLUSIONS AND RECOMMENDATIONS........................................................................ 18 9.0 REFERENCES....................................................................................................................... 19 FIGURES Figure 1: AEA Wind Resource Map................................................................................................. 1 Figure 2: Wind Tower Site Alternatives.......................................................................................... 6 Figure 3: Airport Access Road Adjacent to Met Tower Site and Alternative Site 1....................... 7 Figure 4: Alternative Site 2............................................................................................................. 8 Figure 5: UUI Access Road and Utility Poles on Approach to Alternative Site 3............................ 9 Figure 6: NP100 Turbine Installed in Emmonak .......................................................................... 11 TABLES Table 1: Energy Consumption Data ............................................................................................... 3 Table 2: Alternative Comparison Summary.................................................................................. 13 Table 3: Economic Evaluation Summary....................................................................................... 14 Alaska Village Marshall Wind Project Electric Cooperative Concept Design Report v APPENDICIES Appendix A: V3 Energy’s October 2013 Marshall Wind Diesel Feasibility Appendix B: ANTHC Marshall Alaska Heat Recovery Study Appendix C: August 3, 2012 Marshall Wind Site Investigation Report Appendix D: Marshall Wind Project Feasibility Design Drawings Appendix E: Concept Level Capital Cost Estimate Appendix F: FAA Permitting Alaska Village Marshall Wind Project Electric Cooperative Concept Design Report vi ABBREVIATIONS AAC Alaska Administrative Code ADEC Alaska Department of Environmental Conservation ADF&G Alaska Department of Fish and Game ADNR Alaska Department of Natural Resources AEA Alaska Energy Authority AHRS Alaska Heritage Resource Survey AVEC Alaska Village Electric Cooperative B/C Benefit to Cost Ratio CRC Cultural Resource Consultants, LLC DA Department of Army EA Environmental Assessment ER Environmental Review FAA Federal Aviation Administration FY Fiscal Year FONSI Finding of No Significant Impact °F Degrees Fahrenheit HDL Hattenburg Dilley & Linnell ISER Institute for Social and Economic Research kW Kilowatt kWh Kilowatt Hour M Million MBTA Migratory Bird Treaty Act Met Meteorological Mph Miles per hour MWh Megawatt hour NLUR Northern Land Use Research NP100 Northern Power 100 Arctic NWI National Wetlands Inventory NWP Nationwide Permit OEAAA Obstruction Evaluation/Airport Airspace Analysis PCE Power Cost Equalization PCN Pre Construction Notification SCADA Supervisory Control and Data Acquisition Sec Section USFWS United States Fish & Wildlife Services USGS United States Geological Services WAsP Wind Atlas and Application Program Yr Year Alaska Village Marshall Wind Project Electric Cooperative Concept Design Report 1 1.0 INTRODUCTION 1.1 BACKGROUND This report has been prepared for the Alaska Village Electric Cooperative (AVEC). The purpose of this report is to provide AVEC with conceptual design and cost information for the feasibility of developing the wind energy resource in Marshall. Analysis in this report includes an assessment of the wind resource, investigation and selection of wind turbine installation locations, evaluation of permitting required for site development, preliminary wind turbine generator comparison, and economic analysis of selected turbine alternatives. The wind turbines are necessary to reduce AVEC’s dependence on diesel fuel and provide a source of renewable energy. Preliminary findings included in the Alaska Energy Authority (AEA) Alaska high resolution wind resource map indicate that the Marshall region has a Class 4 wind regime suitable for wind power development. Figure 1: AEA Wind Resource Map Alaska Village Marshall Wind Project Electric Cooperative Concept Design Report 2 1.2 LOCATION The proposed wind turbine project is located near the village of Marshall. Marshall is a rural community located on the north bank of Polte Slough, north of Arbor Island, on the east bank of the Yukon River in the Yukon Kuskokwim Delta. It lies approximately 75 air miles northeast of Bethel at approximately 61.878° North Latitude and 162.081° West Longitude (Sec. 27, T021N, R070W, Seward Meridian). Marshall is located in the Bethel Recording District. No roads connect Marshall to the rest of the state, so access is primarily by air or water. Marshall has a state owned gravel airstrip providing year round access on a 3,200’long and 100’wide runway. Barge service is available seasonally from approximately mid June through October. Marshall has a population of 407 year round residents (2010 U.S. Census Population), with 94.7% being Alaska Native or American Indian. The local residents depend heavily on the subsistence harvest of fish, moose, bear, and waterfowl. The economy is based on a mix of commercial fisheries and public sector jobs. 1.3 CLIMATE Marshall has a maritime climate with extreme temperatures ranging from 54°F to 86°F. Average annual precipitation measures 16 inches. Average summer temperatures range from 40 to 60°F. Winters are typically cold and dry with average winter temperatures ranging from 5 to 15°F. 1.4 ELECTRICAL DEMAND Historical AVEC and AEA Power Cost Equalization Program (PCE) report data was analyzed to determine trends in Marshall’s energy consumption. The Alaska PCE program is a reliable source of historic power, fuel consumption, and energy cost information for rural communities throughout the state. The PCE program provides funding subsidies to electric utilities in rural Alaskan communities for the purpose of lowering energy costs to customers. This program pays for a portion of kilowatt hours sold by the participating utility. The exact amount paid varies per location, and is determined by the amount of energy generated and sold, the amount of fuel used to generate electricity, and fuel costs. Each year, AEA publishes PCE program information including fuel consumption, power generation and sales, and electricity rates for eligible communities. During the fiscal year 2012 (July 1, 2011 to June 30 2012), 126 residential and community facilities in Marshall were eligible to receive PCE assistance. Marshall customers received funding for 42.3% of kilowatt hours sold and had electricity rates reduced from an average of 58 cents per kilowatt hour to 22 cents per kilowatt hour. Table 1 provides FY 2012 PCE and AVEC generated diesel and electricity statistics for Marshall. Alaska Village Marshall Wind Project Electric Cooperative Concept Design Report 3 Table 1: Energy Consumption Data Community Gross KWhs Generated Diesel Fuel Used Average kWh Load Peak kWh Load Customers (Residential and Community Facilities) Gallons Cost ($)Average Fuel Price ($/gallon) Diesel Efficiency (kWh/gallon) Marshall 1,643,535 126,625 408,268 3.22 12.97 190 339 150 *Source: 2012 AVEC Annual Generation Report, AVEC Operations Personnel, and Annual PCE Report FY 2012 AVEC recorded data from December 2011 to December 2012 shows Marshall’s average load was 190 kW with a peak load at 339 kW. Winter electrical demands increase approximately 50% compared to summer demand, with data showing the average load in June and July was approximately 150 kW compared to approximately 220 kW in January and February. 1.5 EXISTING ELECTRICAL POWER SYSTEMS Existing Marshall Power Plant: AVEC’s power plant is located within the community of Marshall. The plant was first energized in 1971 and consists of a “Butler Building”,wood dock, control module, storage van, crew module, and pad mounted transformers. The building and modules are constructed on a mixture of elevated timber post, grade beam and crib foundations. The “Butler Building” contains the following generator sets: (1) Cat 3456 with Cat LC6 Generator, rated at 500KW (1) Detroit Series 60 DDEC4 with Kato 6P4 1450, rated at 363KW (1) Detroit Series 60 DDEC4 with Kato 6P4 1450, rated at 236KW 1,099 kW Total Generation Capacity The power plant also includes generator appurtenances, day tank, miscellaneous tools and equipment, transfer pump, starting batteries, and station service equipment. The building contains a combined cooling system for all three generators with two remote radiators. Power is generated at 277/480V three phase and there are five fused distribution switches that distribute power to the village, one switch is a low voltage feed to the water plant, one is a single phase switch feeding the west part of town and the other three are “A, B, and C” switches feeding the east part of town, the school, and airport. Distribution voltage is 7200V. According to historic AVEC records, the power plant generated a total of 1,644,176 kWh and sold a total of 1,594,247 kWh in 2012 with an average of 12.98 kWh per gallon of diesel consumed. 1.6 MARSHALL RECOVERED HEAT POTENTIAL The Alaska Native Tribal Health Consortium (ANTHC) Division of Environmental Health and Engineering prepared a Heat Recovery Study dated July 16, 2012. The report provides the Alaska Village Marshall Wind Project Electric Cooperative Concept Design Report 4 findings for utilizing recovered heat from the existing power plant to heat the existing community store and water treatment building. According to the report, a heat recovery system was installed in 2007 in the existing power plant but it did not work as designed. Funding to repair the existing recovered heat system was awarded to the City in Round 6 of the AEA Renewable Energy Grant Fund and system repairs a currently being designed. The ANTHC report shows thermal load demand on the existing recovered heat system in Marshall is far less than available heat from the existing generators and the all heat demand will be met by the generators when the existing recovered heat system is operational. See Appendix B for the ANTHC heat recovery study. Since the current loads on the recovered heat system will be met by the waste heat from the generators, a better option to use excess wind energy from wind turbines is to install an electric boiler secondary load controllers remotely in the school boiler room and teacher housing complex. The school is not currently connected to the recovered heat loop. Therefore, excess wind power could by pass the existing recovered heat system and be used to offset approximately 2,546 gallons of fuel oil currently used to heat the school facilities. 1.7 TRANSMISSION LINE EXTENSIONS Currently three phase transmission lines are installed from the AVEC power plant to the existing school which is approximately 0.6 miles from the Met Tower Site. Utility poles with communication wires are already in place along the airport access road, which extends beyond the Met Tower Site to the United Utilities Inc. (UUI) communication tower. These existing utility poles will likely accommodate the future wind power transmission lines. 1.8 REQUIRED POWER PLANT IMPROVEMENTS Upgrades to the existing power plant switch gear and control panels are anticipated in order to accommodate wind turbine energy. AVEC is currently evaluating the power plant and will provide recommendations for necessary upgrades in the early stages of the design phase. The preliminary cost estimate included in this report considers the costs for replacement of the existing switch gear and upgrades to the control panels. 1.9 GEOTECHNICAL INFORMATION The Alaska Department of Transportation performed a geotechnical investigation in 1997 along the alignment of what is now the existing airport access road. The results of their findings are published in the July 1998 Geotechnical Report for Marshall Airport Runway Relocation.Two of the boreholes from that investigation were advanced on August 28, 1997 within approximately 400 feet of the met tower installation location. These boreholes indicate ice rich fine grained soils to a depth of 9’and 11.5’below ground surface. The drill encountered refusal in both boreholes, interpreted as bedrock. From the above referenced report, bedrock in the Marshall area is known to consist of both Permio Triassic metavolcanic and metasedimentary rocks, and Cretaceous igneous rocks. The metamorphic rocks have been recrystallized locally to hornfels by contact metamorphism where they are near igneous intrusive rocks. The metamorphic rocks are mostly gray and green, fine to medium grained, and massive to schistose. The Cretaceous igneous rocks are medium Alaska Village Marshall Wind Project Electric Cooperative Concept Design Report 5 grained, light gray to greenish gray and weakly foliated. Small bodies of intrusive granitic rock have been mapped on the surrounding mountains, and a small light green gray granodiorite is exposed in the material site near the abandoned former runway at Marshall. Due to the presence of different rock types and variable degrees of hornfelsing around the intrusive rocks, the metavolcanic and metasedimentary rocks probably exhibit variable degrees of competence in the project area. A site specific geotechnical investigation is needed to support the selection of a wind turbine foundation type and to formulate a detailed foundation design. Based on existing information a mass gravity foundation with rock anchors will likely be utilized. 1.10 LIMITATIONS This report, titled Marshall Wind Project Concept Design Report,was prepared in support of a grant funding request for design and permitting a wind tower project in Marshall, Alaska. Design information contained herein is conceptual for planning and budgetary cost estimation purposes only. 2.0 MARSHALL WIND SITE ANALYSIS 2.1 WIND TURBINE SITE INVESTIGATION On August 3, 2012, Brent Petrie (AVEC), Matt Metcalf (AVEC), Doug Vaught (V3 Energy), and Ryan Norkoli (HDL) traveled to Marshall. The purpose of the site visit was to investigate the Met Tower Site (described below) and three additional potential wind sites that had been identified through WAsP wind modeling software as possible alternatives to the Met Tower Site, see Figure 1 for locations of the Met Tower Site and three alternative sites. A memo summarizing preliminary office research and the trip report for the site investigation is included in Appendix C. Upon completion of the site investigation, the existing Met Tower Site was determined to be the most cost effective location for installing wind turbines near Marshall. Below is a summary of each potential wind turbine site. Alaska Village Marshall Wind Project Electric Cooperative Concept Design Report 6 Figure 2: Wind Tower Site Alternatives 2.1.1 METEOROLIGICAL (MET) TOWER SITE The met tower site is located at 61û52’33.3”North Latitude, 162û03’55.98”West Longitude. At this location a met tower was installed to record data starting on December 18, 2008 and collapsed October 12, 2009 due to an anchor failure. Low lying tundra vegetation covers the area and the topography is generally flat. The site is adjacent to the existing airport access road and communication wires are strung across utility poles adjacent to the airport access road. These existing poles would likely accommodate transmission lines to route power to the plant. A 1998 geotechnical report developed by the Alaska Department of Transportation (ADOT) provides borehole information within 400 feet of this location. Upon review of other available sites, the met tower site was the preferred site for wind tower development. Alaska Village Marshall Wind Project Electric Cooperative Concept Design Report 7 Figure 3: Airport Access Road Adjacent to Met Tower Site and Alternative Site 1 2.1.2 ALTERNATIVE SITE 1 Alternative Site 1 is located at 61û52’22.78”North Latitude, 162û04’07.79”West Longitude. This location was identified though wind modeling to have 7% greater annual energy production (AEP) than the Met Tower Site. Although the site development costs would be comparable to the Met Tower Site, Alternative Site 1 is located within an existing Native Allotment (NA) and due to property ownership limitations, the location was eliminated from further consideration. 2.1.3 ALTERNATIVE SITE 2 Alternative Site 2 is located at 61û53’09.58”North Latitude, 162û02’59.58”West Longitude. Alternative Site 2 wind modeling indicates 3% less AEP compared to the Met Tower Site. The site is located approximately 1 mile further from the AVEC power plant than the Met Tower Site. Alternative 2 site development would result in additional transmission line costs and site development costs for a lower quality wind source compared to the Met Tower Site. Alternative Site 2 was eliminated from consideration. Alaska Village Marshall Wind Project Electric Cooperative Concept Design Report 8 Figure 4: Alternative Site 2 2.1.4 ALTERNATIVE SITE 3 Alternative Site 3 is located at 61û53’43.99”North Latitude, 162û03’08.6”West Longitude. Alternative Site 3 was identified through wind modeling to have 14% greater AEP than the Met Tower Site. The site is located approximately 1.5 miles from the existing maintained road system. The area is accessed via a rough single lane gravel trail which follows the existing United Utilities Inc. (UUI) communication lines alignment to a communication tower on a nearby mountain top. The existing utility poles that route communication lines back to Marshall would likely be able to accommodate power transmission lines. However, some of the existing utility poles are leaning over due to inadequate foundation soil support. The utility poles were installed within the last 5 years and considering the amount of movement that has already taken place, maintenance costs and useful life are significant concerns with this site. Due to the following considerations, Alternative Site 3 was not selected for further evaluation: higher initial construction costs, increased maintenance concerns for transmission lines, line losses due to additional transmission length, and lack of year round overland access to the site. Alaska Village Marshall Wind Project Electric Cooperative Concept Design Report 9 Figure 5: UUI Access Road and Utility Poles on Approach to Alternative Site 3 3.0 WIND DATA ACQUISITION AND MODELING 3.1 MARSHALL WIND RESOURCE On December 18, 2008, a meteorological (met) tower was installed along the airport access road approximately 0.8 miles from Marshall. The met tower collapsed on October 12, 2009 due to an anchor failure during a strong wind event. The met tower was reinstalled at the same location in September 2012 to obtain additional wind data and fill in data gaps for the portion of the year that no site specific data exists. It should be noted that the met tower failed in 2009 during a strong wind event and the months which no data exists for are likely conducive to power generation. The met tower is equipped with instrumentation and data loggers to evaluate and record the wind resource. The wind data collected during met tower operation suggests that the existing wind regime in this location is suitable for wind power generation. The results of the data acquisition and analysis of the wind resource are included in “Marshall Wind Diesel Feasibility Study”dated October, 2013 (Appendix A). Alaska Village Marshall Wind Project Electric Cooperative Concept Design Report 10 4.0 WIND TURBINE SYSTEM ALTERNATIVES 4.1 MARSHALL WIND TURBINE ANALYSIS Three types of wind turbines were selected by AVEC for preliminary cost analysis to assess cost feasibility: Northern Power Systems Arctic (NP100) turbines; Vestas V20 turbines; and the Aeronautica AW22 225. These turbines were selected because they can be installed in configurations that provide 225 kW to 360 kW to the existing power generation system and have fixed pitch blades. These configurations are classified as medium wind diesel penetration systems having a goal to offset 20% to 50% of the community’s energy demand with wind power. A medium penetration system provides a balance between the amount of energy provided and the complexity of the wind generation and integration systems. 4.1.1 NORTHERN POWER 100 ARCTIC The analyzed turbine configuration consists of (3) NP100 turbines on 37 meter monpole towers. The NP100’s are manufactured by Northern Power Systems in Barre, Vermont. The NP100 turbine is normally rated at 100 kW. The NP 100s are permanent magnet, synchronous, direct drive wind power generators. AVEC has previously installed similar turbines with hub heights ranging 30 to 37 meters, in the following rural Alaska villages: Chevak 400 kW Emmonak –400 kW Gambell –300 kW Hooper Bay –300 kW Kasigluk –300 kW Mekoryuk –200 kW Quinhagak –300 kW Savoonga –200 kW Shaktoolik –200 kW Toksook Bay –400 kW 3,000 kW AVEC’s Existing Total NP100 Power Generation Capacity Each turbine is equipped with active yaw control, but does not have blade pitch control capability. Alaska Village Marshall Wind Project Electric Cooperative Concept Design Report 11 Figure 6: NP100 Turbine Installed in Emmonak 4.1.2 Vestas V20 The second option is installing (3) remanufacturer Vestas Wind Systems A/S V20 turbines. The V20 is a 120 kW rated, fixed pitch turbine with active yaw and a high speed rotor with three blades. Vestas is an international turbine manufacturer based in the Denmark, with their American operations based in Portland, Oregon. The V20s were commonly used as small scale industrial wind turbines in the 1980’s and 1990’s. More recently, these turbines have been replaced in wind farms with new large scale turbines with 1 megawatt capacity or greater. The decommissioned V20s were sold to independent contractors, such as Halus Power Systems in San Leandro, CA, for refurbishment and resale. The V20 is a 32 meter (85 foot) high, 120 kW, induction generator. The turbines are equipped with a 20 meter diameter rotor. Installing three V20s in Marshall would produce a maximum output of 360 kW at a wind speed of 15 mph. The generator power output can be controlled using a simple inverter and soft breaking or a variable speed drive (VSD) complex inverter. V20 turbines are the same wind turbines as the Vestas V17 (except that the blades are 20 meters long instead of 17 meters long). V17 turbines have been previously installed in Alaska at Kokhanok. 4.1.3 Aeronautica AW33 225 The third turbine option is installing one Aeronautica AW33 225 turbine. Aeronautica Windpower Inc. started in 2008 as a turbine refurbishment company. In 2010 they purchased the rights to manufacture and sell the Norwin 225 and Norwin 750 turbines under their name. The AW33 225 turbine is a 40 meter (131 foot) high, 225 kW, induction generator. The turbines are equipped with a 33 meter diameter rotor. This configuration has a maximum power generation output of 225 kW. The blades are fixed pitch and stall regulated at high wind speeds. The blades are aerodynamically designed to stall during extreme wind events in order to maintaining a safe operating speed. This method of control eliminates the mechanical and Alaska Village Marshall Wind Project Electric Cooperative Concept Design Report 12 electric blade control systems involved with pitch controlled turbines. There are no Aeronautica turbines installed in Alaska at this time. 4.2 ALTERNATIVE 1 (3) NP100 TURBINES This alternative proposes installation of (3) NP100 turbines at met tower for a total cumulative generation capacity of 300 kW. The project includes construction of 900 feet of 16 foot wide gravel access trail and (3) 2,600 square foot gravel pads at the wind tower locations. The proposed trail and wind tower pads are anticipated to be 4 feet thick and consist of locally available sands and gravels compacted to 90% maximum density. The turbines are installed on a 37 meter high, lattice tower. The tower foundation is anticipated to include precast concrete gravity above shallow volcanic bedrock. Power is delivered from the wind turbines to the Marshall power plant by a 0.8 mile long transmission line. Reference Sheet C1.02, Appendix D for a site plan of Alternative 1. The wind farm modeling included V3 Energy’s October, 2013 Marshall Wind Diesel Feasibility Analysis (Appendix A) predicts that this alternative will add 623 MWh/year of annual energy production to the Marshall power generation system at 80% turbine availability. The construction cost for this alternative is estimated to be $10,580 per installed kW assuming the new power plant is complete and operational. See Capital Cost Estimate included in Appendix E. 4.3 ALTERNATIVE 2 (3) V20 TURBINES This alternative proposes installation of (3) V20 turbines at the met tower site for total cumulative generation capacity of 360 kW. The project includes construction of 900 feet of 16 foot wide gravel access trail and (3) 2,600 square foot gravel pads at the wind tower locations. The proposed trail and wind tower pads are anticipated to be 4 feet thick and consist of locally available sands and gravels compacted to 90% maximum density. The turbines are installed on a 32 meter high lattice tower. The tower foundation is anticipated to include precast concrete gravity above shallow volcanic bedrock. Power is delivered from the wind turbines to the Marshall power plant by a 0.8 mile long transmission line. Reference Sheet C1.03, Appendix D for a site plan of Alternative 2. The wind farm modeling included V3 Energy’s October, 2013 Marshall Wind Diesel Feasibility Analysis (Appendix A) and predicts that this alternative will add 575 MWh/year of annual energy production to the Marshall power generation system at 80% turbine availability . The construction cost for this alternative is estimated to be $8,029 per installed KW assuming the new power plant is complete and operational. See Capital Cost Estimate included in Appendix E. 4.4 ALTERNATIVE 3 (1) AW33 225 TURBINES This alternative proposes installation of (1) AW33 225 turbines at met for a potential generation capacity of 225 kW. The project includes construction of a 300 foot gravel access trail and (1) 2,600 square foot wind tower pads. The proposed trail and wind tower pads are anticipated to be 4 feet thick and consist of locally available sands and gravels compacted to 90% maximum density. The turbine is installed on a 40 meter high, conical, monopole tower. Alaska Village Marshall Wind Project Electric Cooperative Concept Design Report 13 The tower foundation is anticipated to include precast concrete gravity mats with rock anchors to resist the increased overturning moment. The AW33 225 towers are anticipated to require larger foundations than the NP100 turbines due to larger reaction forces from the increased tower weight, longer blade diameters, and increased swept area. Power is delivered from the wind turbines to the Marshall power plant by a 0.75 mile long transmission line. Reference Sheet C1.04, Appendix D, for a site plan of Alternative 3. The wind farm modeling included V3 Energy’s October 2013 Marshall Wind Diesel Feasibility Analysis (Appendix B) and predicts that this alternative will add 522 MWh/year of annual energy production to Marshall power generation system at 80% turbine availability . The construction cost for this alternative is estimated to be $11,824 per installed KW assuming the new power plant is complete and operational and 225 kW of power is delivered from the new turbine. See Capital Cost Estimate included in Appendix E. 4.5 ALTERNATIVE COMPARISON SUMMARY Table 2 below summarizes the capital costs and estimated annual energy production for each turbine alternative. Table 2: Alternative Comparison Summary Alt Turbine Selection Site Generation Capacity (kW) Estimated Capital Cost Estimated Capital Cost per Installed kW Estimated Annual Energy Production @ 80 % Availability 1 (3) NP 100s Met Tower 300 $ 3.2 M $10,580 721,365 kWh 2 (3) V20s Met Tower 360 $ 2.9 M $8,029 579,681 kWh 3 (1) AW33 225 Met Tower 225 $ 2.7 M $11,824 520,962 kWh *Source:Annual Energy Production data taken from V3 Energy’s October 2013 Marshall Wind Diesel Feasibility Analysis 5.0 ECONOMIC EVALUATION 5.1 METHODOLOGY AND APPROACH The Marshall Wind Diesel Feasibility Analysis prepared by V3 Energy (Appendix A) includes a wind power analysis of the Marshall power generation system using HOMER energy modeling software with the previously described wind turbine alternatives. The software was configured for a medium, with the first priority to meet the community’s electrical demands and the second priority to serve the recovered heat system through a secondary load controller (electric boiler). The analysis considered an average diesel fuel price of $4.99 per gallon for the Alaska Village Marshall Wind Project Electric Cooperative Concept Design Report 14 projected 20 year project life. The modeling assumptions and results of V3’s analysis are presented in Appendix A. V3 inserted the power generation and fuel consumption results from the HOMER modeling into the economic modeling program developed by the Institute for Social and Economic Research (ISER). AEA’s uses the ISER economic model as the standard approach for scoring wind project design and construction grant applications. The ISER model considers the capital cost of construction and annual cost of operating and maintaining the wind turbines and weighs them against the benefit cost savings realized from the volume of displaced diesel fuel required for power generation and heating public facilities. The analysis develops a benefit/cost ratio that can be used to compare wind turbine alternatives. See V3’s economic analysis results in Appendix A. 5.2 ECONOMIC EVALUATION RESULTS Table 3 below summarizes the findings of the V3’s economic evaluation for each turbine alternative. Table 3: Economic Evaluation Summary Alt Annual Wind Generation @ 80% Availability (kWh) Wind Energy For Power (kWh/yr) Wind Energy For Heat (kWh/yr) Wind as % Total Power Production (%) Power Generation: Fuel Displaced by Wind Energy (gal/yr) Thermal Generation: Heating Fuel Displaced by Wind Energy (gal/yr) Benefit/ Cost Ratio 1 623,300 523,707 99,593 37.4 42,893 2,546 0.95 2 575,191 471,521 103,670 34.6 38,977 2,650 0.95 3 522,926 467,889 55,037 31.4 37,454 1,407 0.99 *Source:Annual Energy Production data taken from V3 Energy’s October 2013 Marshall Wind Diesel Feasibility Analysis 6.0 PREFERRED ALTERNATIVE Based on the findings of the site analysis, wind modeling, and economic evaluation, Alternative 1 is the preferred alternative for Marshall wind turbine development. This alternative consists of construction of (3) NP100 turbines at the Met Tower Site. Each turbine has the potential to generate 100 kW, for an aggregate total power generation of 300 kW. The NP100 turbine is the preferred alternative because it maximizes power production and matches AVEC’s existing turbine fleet so that maintenance and operational procedures are consistent among AVEC turbine installations. The three turbine installation would allow for redundancy in the system and the ability to perform turbine maintenance without eliminating wind power from the system. The economic evaluation above assumes that the turbine array operates at the 300 kW energy output level. However, for better system performance, the turbine should be modulated by occasionally shutting down turbines to consistently provide medium penetration to the Marshall grid and adequate excess energy to meet recovered heat demands. Alaska Village Marshall Wind Project Electric Cooperative Concept Design Report 15 7.0 PERMITTING, ENVIRONMENTAL, AND LAND OWNERSHIP 7.1 FEDERAL AVIATION ADMINISTRATION (FAA) The FAA requires an Obstruction Evaluation/Airport Airspace Analysis (OE/AAA) and submittal of a Notice of Proposed Construction or Alteration (45 days prior to construction) for projects proposing construction or alteration of any of the following: 1. A structure that exceeds 200 feet above ground level 2. A structure located in proximity to an airport and will not exceed the slope ratio 3. A structure involving construction of a traverse way 4. A structure emitting frequencies, and does not meet the conditions of the FAA Co location Policy 5. A structure located in an instrument approach area that might exceed part 77 Subpart C 6. A structure located on an airport or heliport On November 13, 2012, a Determination of No Hazard to Air Navigation from the FAA was issued for two Northern Power 100 wind turbines (Reference No. 2012 WTW 7872 OE and 2012 WTW 7873 OE) at the met tower site. See Appendix F for FAA determinations. This determination will have to be modified based on the final tower configuration determined during design. 7.2 US FISH AND WILDLIFE SERVICE (USFWS) Marshall is located within the Yukon Kuskokwim Delta Ecoregion and lies on the northeastern boundary of the Yukon Delta National Wildlife Refuge. According to Alaska’s 32 Ecoregions: “The area is characterized by lakes, streams, tidal flats, wet tundra, and sedge flats that support an abundant population of waterfowl and shorebirds; providing breeding grounds for more than 20 species of waterfowl and 10 species of shorebirds. The Yukon Kuskokwim Delta supports 50% of the world’s black brant, the majority of the world’s emperor geese, all of North America’s nesting cackling Canada geese, and the highest density of nesting tundra swans. The long tailed duck, scaup, common eider, spectacled eider, northern pintail, green winged teal, and northern shoveler can also be found here.” The USFWS lists the spectacled eider as threatened. Spectacled eiders typically nest on coastal tundra near shallow ponds or lakes, usually within 10 feet of the water. The current range map does not depict spectacled eider use of the area. Consultation with USFWS in September 2013 revealed that Marshall is outside the vicinity of expected spectacled eider habitat. USFWS recommends avoiding vegetation clearing for regions throughout the state of Alaska. For the Yukon Kuskokwim Delta region the following avoidance periods apply: 1. Shrub and Open Habitat –May 5th through July 25th (except in habitat that supports Canada geese, swan, and black scoter) 2. Canada geese and swan habitat –April 20th through July 25th 3. Black scoter habitat –May 5th through August 10th Under the Migratory Bird Treaty Act (MBTA): Alaska Village Marshall Wind Project Electric Cooperative Concept Design Report 16 “It is illegal for anyone to “take”migratory birds, their eggs, feathers or nests.“Take”includes by any means or in any manner, any attempt at hunting, pursuing, wounding, killing, possessing or transporting any migratory bird, nest, egg, or part thereof. Take and possession under MBTA can be authorized through regulations, such as hunting regulations, or permits (e.g., salvage, research, depredation, or falconry). The MTBA does not distinguish between intentional and unintentional take. In Alaska, all native birds except grouse and ptarmigan (protected by the State of Alaska) are protected under the MBTA.” The Yukon Delta National Wildlife Refuge also supports spawning and rearing habitat for 44 species of fish including all five North American Pacific Salmon. A review of ADF&G’s Anadromous Waters Catalog lists Poltes Slough (AWC Code: 334 20 11000 2375) as the closest fish bearing stream to the project area. The Slough supports the presence of chum, coho, and king salmon and connects to the main stem of the Yukon River (AWC Code: 334 20 11000). The project is located far enough from the Slough that secondary indirect impacts from construction related activities are unlikely to impact water quality. Informal Section 7 consultation with USFWS is recommended once the project progresses past the preliminary site evaluation stage, per USFWS's Land Based wind Energy Guidelines, to identify potential impacts to general avian species and determine whether measures to avoid and minimize effects are necessary. 7.3 STATE HISTORIC PRESERVATION OFFICE (SHPO) Preliminary research by Cultural Resource Consultants, LLC was performed on the Met Tower Site. According to the Alaska Heritage Resource Survey (AHRS) files there are no known historic or archaeological sites within the proposed project area. In addition, the project area is located outside of an area defined as “highest potential for cultural resources”which extends two to three blocks from the river and includes a cemetery and two other areas of reported graves. This high potential area does not include the proposed wind tower locations. An historic and archaeological survey was conducted along the roadway from the town site of Marshall to the airstrip. Results of the survey suggested that, although the airport access road had been constructed prior to the survey, it appeared to have no impact on historic or prehistoric sites. Preliminary research results did reveal one known historic resource within the proposed project area, the Paimute Marshall Trail (RST 168). The Paimute Marshall Trail is an historic trail used as a connecting route from the Yukon River at Paimute through Russian Mission to Marshall. The trail is shown in the 1973 Department of Transportation and Public Facilities trails inventory, on Maps 73 and 74 (Russian Mission Quadrangle), as Trail #18. The trail does not have an AHRS number, but since it is listed as a qualified RS2477 right of way. The Alaska State Historic Preservation Office indicated that a cultural resources survey would be necessary to collect information on the Paimute Marshall Trail to evaluate it and determine whether or not it is eligible for listing on the National Register of Historic Places. Based on existing AHRS information and the findings of previous investigations, there is a relatively low probability of undiscovered archaeological and historic sites within area proposed for development. In accordance with the National Historic Preservation Act, the undertaking Alaska Village Marshall Wind Project Electric Cooperative Concept Design Report 17 will need to be reviewed by the SHPO. During formal Section 106 consultation the SHPO will determine whether additional surveys and mitigation will be required. 7.4 DEPARTMENT OF THE ARMY (DA) Section 404 of the Clean Water Act requires a permit for placement of fill in wetlands and waters of the United States. The National Wetlands Inventory (NWI) database does not have data for the Marshall area. However, current wetland mapping in adjacent areas with similar habitat and landform features indicates the area contains wetlands under DA jurisdiction. A new Nationwide Permit (NWP) issued in 2012 for Land Based Renewable Energy General Facilities (NWP 51) authorizes discharge of fill for wind tower construction if loss of wetlands does not exceed 1/2 acre. This permit also covers other associated work, including utility lines, parking lots, and roads inside of the wind generation facility. Access roads and transmission lines used to connect the facility to existing infrastructure require separate permitting (NWP 12 or 14). Submittal requirements for NWP 51 include Pre Construction Notification (PCN) and PCN requires a wetlands delineation documenting project impacts. Completion of wetlands delineation for the area proposed for development is recommended. The DA recommends that wetlands delineation is completed within the designated growing season for specific regions. Marshall is located within Alaska’s Interior Forested Lowlands and Uplands Ecoregion, which has a growing season that begins on May 3 rd and ends on October 3rd. 7.5 CONTAMINATED SITES, SPILLS, AND UNDERGROUND TANKS A search of the Alaska Department of Environmental Conservation’s (ADEC) contaminated sites database revealed three active contaminated sites within the Village of Marshall. No known contaminated sites are located within the area proposed for development. 7.6 AIR QUALITY According to Alaska Administrative Code (AAC) 18 AAC 50, the community of Marshall is considered a Class II area. As such, there are designated maximum allowable increases for particulate matter 10 (PM 10) micrometers or less in size, nitrogen dioxide, and sulfur dioxide. Activities in these areas must operate in such a way that they do not exceed listed air quality controls for these compounds. The nature and extent of the proposed project is not likely to increase emissions or contribute to a violation of an ambient air quality standard or cause a maximum allowable increase for a Class II area. 7.7 NATIONAL ENVIRONMENTAL POLICY ACT REVIEW (NEPA) The federal government’s role in regulating wind power development is limited to projects occurring on federal lands or projects that have some form of federal involvement. The federal nexus for the proposed wind tower site in Marshall is likely with the DA for placement of fill in wetlands. Construction of the wind towers at the proposed development site would require preparation of an Environmental Review (ER) document. Similar to an Environmental Assessment (EA), an ER will provide an assessment of potential environmental impacts and Alaska Village Marshall Wind Project Electric Cooperative Concept Design Report 18 identify avoidance, minimization, and mitigation measures. A Finding of No Significant Impact (FONSI) determination by the funding agency will be needed. Results from a preliminary environmental review are summarized below: 1. In accordance with the National Historic Preservation Act, Section 106 consultation will be required for the project. 2. A wetlands delineation of the proposed site is necessary to obtain a preliminary jurisdictional determination and Section 404/10 DA Permit. 3. Informal consultation with the USFWS is recommended to identify potential effects to threatened or endangered species and possible avoidance and minimization measures. 4. Vegetation clearing shall be scheduled to take place outside appropriate recommended time periods of avoidance, per the USFWS’s recommendations. 5. File FAA form 7460 1 at least 45 days prior to construction. This has been filed for NP100 turbines. 7.8 LAND OWNERSHIP The Alaska Department of Natural Resources (ADNR) Special Management Lands Division indicates the proposed tower site is located within the designated city boundary of Marshall. The Alaska Division of Community and Regional Affairs (DCRA) Area Use Map for Marshall indicates the proposed tower site is located on land owned by Maserculiq, Inc. AVEC and Maserculiq, Inc. have an existing lease agreement in place June 1, 2012 through July 31, 2013 for the installation of the meteorological tower. 8.0 CONCLUSIONS AND RECOMMENDATIONS The high cost of diesel fuel and available wind resource near Marshall makes wind power an attractive component to the electrical power generation system. A wind site investigation and subsequent wind modeling analysis determined that Marshall has a Class 4 wind resource and is suited for wind site development. Economic analysis of the turbine alternatives presented in this report included a configuration of three NP100 turbines installed at the Met Tower Site. The economic analysis projected that three NP100 turbines could offset approximately 42,893 gallons of diesel fuel per year while generating 623,300 kWh/yr. The following actions are recommended to continue the progress of wind turbine development in Marshall: Alaska Village Marshall Wind Project Electric Cooperative Concept Design Report 19 Recommendations 1. Enter into negotiations with Maserculiq, Inc. for site control and access for a geotechnical investigation and wind project development at the Met Tower Site. 2. Consult with Marshall community leaders to understand and minimize the impacts to subsistence activities from wind project development at the Met Tower Site. 3. Perform wetland delineation at the Met Tower Site and proceed with permitting per the recommendations included in Section 7 of this report. 4. Perform a geotechnical investigation at the Met Tower Site to develop wind tower foundation design. 5. Perform additional investigation and design of improvements to incorporate wind power into the existing power plant at Marshall. 6. Continue discussion with Northern Power to determine the NP 100 turbines could be installed in Marshall with 24 meter blades on 48 meter lattice towers. This configuration is not currently recommended by Northern Power, but would increase energy production and better fit Marshall’s wind regime. 7. Perform detailed design of a selected alternative, and apply for construction grant funds. 9.0 REFERENCES Alaska Community Database, Community Information Summaries (CIS) http://www.commerce.state.ak.us/dca/commdb/CF_CIS.html, accessed on 9/12/2012 Alaska Energy Authority (AEA).2012. Statistical Report of the Power Cost Equalization Program, Fiscal Year 2011. Twenty Third Edition. April 2012. Alaska Department of Environmental Conservation (ADEC).18 AAC 50 Air Quality Control: As Amended through August 1, 2012. ADEC. Division of Spill Prevention and Response.Last accessed on September 6, 2012. http://dec.alaska.gov/applications/spar/CSPSearch/results.asp. State of Alaska Department of Transportation (ADOT) Northern Region Technical Services Geology.Geotechnical Report, Marshall Airport Runway Relocation.July 1998. Alaska Native Tribal Health Consortium (ANTHC) Division of Environmental Health and Engineering.Marshall, Alaska Heat Recovery Study. July 16, 2012. Alaska Department of Fish & Game (ADF&G). Wildlife Action Plan Section IIIB: Alaska’s 32 Ecoregions http://www.adfg.alaska.gov/static/species/wildlife_action_plan/section3b.pdf. Last accessed on September 6, 2012. ADF&G. Anadromous Waters Catalog.http://www.adfg.alaska.gov/sf/SARR/AWC/. Last accessed on September 6, 2012. Alaska Village Marshall Wind Project Electric Cooperative Concept Design Report 20 ADF&G. 2012c. Refuges, Sanctuaries, Critical Habitat Areas and Wildlife Refuges. http://www.adfg.alaska.gov/index.cfm?adfg=protectedareas.locator. Last accessed on September 7, 2012. ADNR. 2012. Division of Special Management Lands. http://www.navmaps.alaska.gov/specialmanagementlands/. Last accessed on September 7, 2012. Alaska Department of Commerce, Community, and Economic Development; Division of Community and Regional Affairs.Marshall Area Use Map. 2006. FAA. Obstruction Evaluation/Airport Airspace Analysis (OE/AAA). https://oeaaa.faa.gov/oeaaa/external/portal.jsp012. Last accessed on August 26, 2012. USACE.Regional Supplement to the Corps of Engineers Wetland Delineation Manual: Alaska Region (Version 2.0). http://www.usace.army.mil/Portals/2/docs/civilworks/regulatory/reg_supp/erdc el_tr 07 24.pdf. Last accessed on September 6, 2012. USFWS.United States Fish and Wildlife Service Endangered Species: Listed and Candidate Species in Alaska, Spectacled Eider (Somateria fischeri). http://alaska.fws.gov/fisheries/endangered/species/spectacled_eider.htm. Last accessed on September 6, 2012. USFWS. Yukon Delta National Wildlife Refuge. http://www.fws.gov/refuges/profiles/index.cfm?id=74540. Last accessed on September 6, 2012. USFWS.U.S. Fish and Wildlife Service Land Clearing Guidance for Alaska: Recommended Time Periods to Avoid Vegetation Clearing. http://alaska.fws.gov/fisheries/fieldoffice/anchorage/pdf/vegetation_clearing.pdf. Last accessed on September 7, 2012. USFWS.U.S. Fish and Wildlife Service National Wetlands Inventory. http://107.20.228.18/Wetlands/WetlandsMapper.html#. Last accessed on September 6, 2012. V3 Energy.Marshall Wind Diesel Feasibility Study.September 14, 2012. Northern Economics.Proposed Wind Project in Marshall: Economic Evaluation Report. September 17, 2012. Appendix A V3 Energy’s October 2013 Marshall Wind Diesel Feasibility Marshall Wind-Diesel Feasibility Analysis October 7, 2013 Douglas Vaught, P.E. dvaught@v3energy.com V3 Energy, LLC Eagle River, Alaska Marshall Wind-Diesel Feasibility Analysis P a g e | i This report was prepared by V3 Energy, LLC under contract to Alaska Village Electric Cooperative to assess the technical and economic feasibility of installing wind turbines in Marshall. This analysis is part of a conceptual design project funded in Round IV of the Renewable Energy Fund administered by the Alaska Energy Authority. Contents Introduction..................................................................................................................................................1 Village of Marshall ....................................................................................................................................1 Wind Resource..............................................................................................................................................2 Measured Wind Speeds............................................................................................................................4 Wind Roses................................................................................................................................................4 Wind Frequency Rose...........................................................................................................................5 Total Value (power density) Rose.........................................................................................................5 Wind-Diesel Hybrid System Overview ..........................................................................................................5 Low Penetration Configuration.................................................................................................................6 Medium Penetration Configuration..........................................................................................................6 High Penetration Configuration................................................................................................................7 Wind-Diesel System Components.............................................................................................................8 Wind Turbine(s) ....................................................................................................................................8 Supervisory Control System..................................................................................................................8 Synchronous Condenser .......................................................................................................................8 Secondary Load.....................................................................................................................................9 Deferrable Load ....................................................................................................................................9 Interruptible Load...............................................................................................................................10 Storage Options ..................................................................................................................................10 Wind Turbine Options.................................................................................................................................11 Northern Power Systems NPS100-21 ARCTIC.........................................................................................11 Vestas V20...............................................................................................................................................12 Aeronautica AW33-225...........................................................................................................................12 Homer Software Wind-Diesel Model..............................................................................................................13 Diesel Power Plant..................................................................................................................................13 Wind Turbines.........................................................................................................................................13 Marshall Wind-Diesel Feasibility Analysis P a g e | ii Electric Load............................................................................................................................................14 Thermal Load ..........................................................................................................................................15 Diesel Generators ...................................................................................................................................15 Economic Analysis.......................................................................................................................................16 Wind Turbine Costs.................................................................................................................................16 Fuel Cost..................................................................................................................................................17 Modeling Assumptions ...........................................................................................................................17 Conclusion and Recommendations ............................................................................................................20 Marshall Wind-Diesel Feasibility Analysis P a g e | 1 Introduction Alaska Village Electric Cooperative (AVEC) is the electric utility for the City of Marshall. AVEC was awarded a grant from the Alaska Energy Authority (AEA) to complete feasibility work for installation of wind turbines, with planned construction in 2015. Village of Marshall Marshall is located on the north bank of Polte Slough, north of Arbor Island, on the east bank of the Yukon River in the Yukon-Kuskokwim Delta. It lies on the northeastern boundary of the Yukon Delta National Wildlife Refuge. The climate of Marshall is maritime with temperatures ranging between -54 and 86 °F. Average annual rainfall measures 16 inches. Heavy winds in the fall and winter often limit air accessibility. The Lower Yukon is ice-free from mid-June through October. An expedition came upon an Eskimo village called "Uglovaia" at this site in 1880. Gold was discovered on nearby Wilson Creek in 1913. "Fortuna Ledge" became a placer mining camp, named after the first child born at the camp, Fortuna Hunter. Its location on a channel of the Yukon River was convenient for riverboat landings. A post office was established in 1915, and the population grew to over 1,000. Later, the village was named for Thomas Riley Marshall, Vice President of the United States under Woodrow Wilson from 1913-21. The community became known as "Marshall's Landing." When the village incorporated as a second-class city in 1970, it was named Fortuna Ledge but was commonly referred to as Marshall. The name was officially changed to Marshall in 1984. A federally-recognized tribe is located in the community -- the Native Village of Marshall. Marshall is a traditional Yup'ik Eskimo village. Subsistence and fishing-related activities support most residents. Members of the Village of Ohogamiut also live in Marshall. The sale, importation, and possession of alcohol are banned in the village. According to Census 2010, there were 108 housing units in the community and 100 were occupied. Its population was 94.7 percent American Indian or Alaska Native; 2.7 percent white; 0.2 percent Asian; 2.4 percent of the local residents had multi-racial backgrounds. Additionally, 0.2 percent of the population was of Hispanic descent. Water is derived from five wells. Approximately 70% of the city (60 homes) is served by a piped circulating water and sewer system and has full plumbing. The remainder of the city must haul water and use honey buckets. An unpermitted landfill is available, and the city has a refuse collection service. Electricity is provided by Alaska Village Electric Cooperative. There is one school located in the Marshall Wind-Diesel Feasibility Analysis P a g e | 2 community, attended by 133 students. Local hospitals or health clinics include Agnes Boliver Health Clinic (Marshall). Emergency Services have river and air access. Emergency service is provided by a health aide. Marshall has a seasonal economy with most activity during the summer. Fishing, fish processing, and BLM firefighting positions are available seasonally. In 2010, 39 residents held commercial fishing permits. Subsistence activities supplement income. Salmon, moose, bear, and waterfowl are harvested. Trapping provides some income. No roads connect Marshall to other communities, so access to Marshall is primarily by air or water. The city has a State-owned 3,201' long by 100' wide gravel airstrip. The community is also serviced by barge. Many residents have boats and in winter they rely on snow machines and dog teams for travel. Wind Resource A met tower was installed at the proposed wind turbine site in Marshall on December 18, 2008 and was in continuous operation until October 10, 2009 when an anchor failed during a wind storm and the tower collapsed. The met tower was replaced in September 2012 and is presently operational. With the data through September 2013, a mean annual wind speed of 6.27 m/s was measured, with a mean annual wind power density of 396 W/m 2. This indicates a Class 4 (good) wind resource. Other aspects of the wind resource also are promising for wind power development. By IEC 61400-1, 3rd edition classification, Marshall is category II to III-C, indicating low turbulence (mean TI at 15 m/s = 0.090) and a moderate probability of extreme wind events. The latter measure is somewhat difficult to quantify with only 24 months of data, but the site clearly is not energetic enough to be IEC Class I. All three wind turbines profiled in this report are certified for IEC Class II conditions. Marshall met tower data synopsis Data start date December 18, 2008 Data end date Operational (data gap from Oct. 2009 to Sept. 2012); data thru September 26, 2013 for analysis Wind power class (by WPD) Class 4 (good) Wind speed average (30 meters) 6.27 m/s measured IEC 61400-1 3rd ed. extreme winds Class II/III (note: 23 months data) Wind power density (30 meters) 396 W/m 2 Weibull distribution parameters k = 1.60, c = 6.8 m/s Roughness Class 0.77 (rough pasture) Power law exponent 0.133 (low wind shear) Frequency of calms (4.0 m/s threshold) 34% Mean Turbulence Intensity 0.090 (IEC 61400-1 3 rd ed. turbulence category C) Marshall Wind-Diesel Feasibility Analysis P a g e | 3 Topographic map Google Earth image Marshall Wind-Diesel Feasibility Analysis P a g e | 4 Measured Wind Speeds Measured wind speeds in Marshall are excellent for an inland site and very promising for wind power development. Wind Speed Sensor Summary Variable Speed 30 m A Speed 30 m B Speed 22 m Measurement height (m) 30 30 22 Mean wind speed (m/s) 6.11 6.15 5.90 MoMM wind speed (m/s) 6.23 6.27 6.01 Max 10-min wind speed (m/s) 26.7 30.8 26.6 Weibull k 1.61 1.57 1.57 Weibull c (m/s) 6.81 6.82 6.55 Mean power density (W/m²) 359 378 331 MoMM power density (W/m²) 376 396 345 Mean energy content (kWh/m²/yr) 3,146 3,311 2,896 MoMM energy content (kWh/m²/yr) 3,296 3,471 3,025 Energy pattern factor 2.41 2.51 2.47 Frequency of calms (%) 35.1 35.9 37.3 Marshall Wind speed graph Wind Roses Winds at the Marshall met tower test site are primarily east-northeast, north-northwest with occasional winds from south-southeast (wind frequency rose), with the strongest winds east-northeast (mean value rose). The power density rose indicates that the power producing winds at the site are predominately east-northeast. Multiple wind turbines should oriented an axis north-northeast to south-southwest to provide good exposure to ENE and SSE winds and avoid tower shadowing. Marshall Wind-Diesel Feasibility Analysis P a g e | 5 Note that a wind threshold of 4.0 m/s was selected for the definition of calm winds. With this threshold, the Marshall met tower site experienced 34 percent calm conditions during the test period. Wind Frequency Rose Total Value (power density) Rose Wind-Diesel Hybrid System Overview Wind-diesel power systems are categorized based on their average penetration levels, or the overall proportion of wind-generated electricity compared to the total amount of electrical energy generated. Commonly used categories of wind-diesel penetration levels are low penetration, medium penetration, and high penetration. The wind penetration level is roughly equivalent to the amount of diesel fuel displaced by wind power. Note however that the higher the level of wind penetration, the more complex and expensive a control system and demand-management strategy is required. Categories of wind-diesel penetrationlevels Penetration Category Wind Penetration Level Operating Characteristics and System Requirements Instantaneous Average Very Low <60% <8%Diesel generator(s) runs full time Wind power reduces net load on diesel All wind energy serves primary load No supervisory control system Low 60 to 120% 8 to 20%Diesel generator(s) runs full time At high wind power levels, secondary loads are dispatched to insure sufficient diesel loading, or wind generation is curtailed Relatively simple control system Medium 120 to 300% 20 to 50%Diesel generator(s) runs full time At medium to high wind power levels, secondary loads are dispatched to insure sufficient diesel loading At high wind power levels, complex secondary load Marshall Wind-Diesel Feasibility Analysis P a g e | 6 Penetration Category Wind Penetration Level Operating Characteristics and System Requirements Instantaneous Average control system is needed to ensure heat loads do not become saturated Sophisticated control system High (Diesels-off Capable) 300+% 50 to 150%At high wind power levels, diesel generator(s) may be shut down for diesels-off capability Auxiliary components required to regulate voltage and frequency Sophisticated control system Low Penetration Configuration Low-penetration wind-diesel systems require the fewest modifications to a new or existing power system in that maximum wind penetration is never sufficient to present potential electrical stability problems. But, low penetration wind systems tend to be less economical than higher penetration systems due to the limited annual fuel savings compared to a relatively high total wind system installation costs. This latter point is because all of the fixed costs of a wind power project – equipment mobilization and demobilization, distribution connection, new road access, permitting, land acquisition, etc. – are spread across fewer turbines, resulting in relatively high per kW installed costs. Medium Penetration Configuration Medium penetration mode is very similar to high penetration mode except that no electrical storage is employed in the system and wind capacity is designed for a moderate and usable amount of excess wind energy that must be diverted to thermal loads. All of AVEC’s modern wind power systems are designed as medium penetration systems. Marshall Wind-Diesel Feasibility Analysis P a g e | 7 High Penetration Configuration Other communities, such as Kokhanok, are more aggressively seeking to offset diesel used for thermal and electrical energy. They are using configurations which will allow for the generator sets to be turned off and use a significant portion of the wind energy for various heating loads. The potential benefit of these systems is the highest, however currently the commissioning for these system types due to the increased complexity, can take longer. Marshall Wind-Diesel Feasibility Analysis P a g e | 8 Wind-Diesel System Components Listed below are the main components of a medium to high-penetration wind-diesel system: Wind turbine , plus tower and foundation Supervisory control system Synchronous condenser Secondary load Deferrable load Interruptible load Storage Wind Turbine(s) Village-scale wind turbines are generally considered as 50 kW to 250 kW rated output. This turbine size once dominated with worldwide wind power industry but has been left behind in favor of much larger 1,000 kW plus capacity turbines for utility grid-connected projects. Conversely, many turbines are manufactured for home or farm application, but generally these are 10 kW or smaller. Consequently, few new manufacture village size-class turbines are on the market, although a large supply of used and/or remanufactured turbines are available. The latter typically result from the repower of older wind farms in the Continental United States and Europe with new, larger wind turbines. Supervisory Control System Medium- and high-penetration wind-diesel systems require fast-acting real and reactive power management to compensate for rapid variation in village load and wind turbine power output. A wind- diesel system master controller, also called a supervisory controller, would be installed inside the existing Marshall power plant or in a new module adjacent to it. The supervisory controller would select the optimum system configuration based on village electric load demand and available wind power. Synchronous Condenser A synchronous condenser, sometimes called a synchronous compensator, is a specialized synchronous electric motor with an output shaft that spins freely. Its excitation field is controlled by a voltage regulator to either generate or absorb reactive power as needed to support the grid voltage or to maintain the grid power factor at a specified level. This is necessary for diesels-off wind turbine operations, but generally not required for wind systems that maintain a relatively large output diesel generator online at all times. Marshall Wind-Diesel Feasibility Analysis P a g e | 9 Synchronous condenser in Kokhanok Secondary Load To avoid curtailing wind turbines during periods of high wind/low load demand, a secondary or “dump” load is installed to absorb excess system (principally wind) power beyond that required to meet the electrical load. The secondary load converts excess wind energy into heat via an electric boiler typically installed in the diesel generator heat recovery loop. This heat can be for use in space and water heating through the extremely rapid (sub-cycle) switching of heating elements, such as an electric boiler imbedded in the diesel generator jacket water heat recovery loop. As seen in Figure 16, a secondary load controller serves to stabilize system frequency by providing a fast responding load when gusting wind creates system instability. An electric boiler is a common secondary load device used in wind-diesel power systems. An electric boiler (or boilers), coupled with a boiler grid interface control system, in a new module outside the Marshall power plant building, would be sized to absorb up to 200 kW of instantaneous energy (full output of the wind turbines). The grid interface monitors and maintains the temperature of the electric hot water tank and establishes a power setpoint. The wind-diesel system master controller assigns the setpoint based on the amount of unused wind power available in the system. Frequency stabilization is another advantage that can be controlled with an electric boiler load. The boiler grid interface will automatically adjust the amount of power it is drawing to maintain system frequency within acceptable limits. Deferrable Load A deferrable load is electric load that must be met within some time period, but exact timing is not important. Loads are normally classified as deferrable because they have some storage associated with them. Water pumping is a common example - there is some flexibility as to when the pump actually operates, provided the water tank does not run dry. Other examples include ice making and battery charging. A deferrable load operates second in priority to the primary load and has priority over charging batteries, should the system employ batteries as a storage option. Marshall Wind-Diesel Feasibility Analysis P a g e | 10 Interruptible Load Electric heating either in the form of electric space heaters or electric water boilers should be explored as a means of displacing stove oil with wind-generated electricity. It must be emphasized that electric heating is only economically viable with excess electricity generated by a renewable energy source such as wind and not from diesel-generated power. It is typically assumed that 41 kWh of electric heat is equivalent to one gallon of heating fuel oil. Storage Options Electrical energy storage provides a means of storing wind generated power during periods of high winds and then releasing the power as winds subside. Energy storage has a similar function to a secondary load but the stored, excess wind energy can be converted back to electric power at a later time. There is an efficiency loss with the conversion of power to storage and out of storage. The descriptions below are informative but are not currently part of the overall system design. Batteries Battery storage is a generally well-proven technology and has been used in Alaskan power systems including Fairbanks (Golden Valley Electric Association), Wales and Kokhanok, but with mixed results in the smaller communities. Batteries are most appropriate for providing medium-term energy storage to allow a transition, or bridge, between the variable output of wind turbines and diesel generation. This “bridging” period is typically 5 to 15 minutes long. Storage for several hours or days is also possible with batteries, but this requires higher capacity and cost. In general, the disadvantages of batteries for utility- scale energy storage, even for small utility systems, are high capital and maintenance costs and limited lifetime. Of particular concern to rural Alaska communities is that batteries are heavy and expensive ship and most contain hazardous substances that require special removal from the village at end of service life and disposal in specially-equipped recycling centers. There are a wide variety of battery types with different operating characteristics. Advanced lead acid and zinc-bromide flow batteries were identified as “technologically simple” energy storage options appropriate for rural Alaska in an Alaska Center for Energy and Power (ACEP) July, 2009 report on energy storage. Nickel-cadmium (NiCad) batteries have been used in rural Alaska applications such as the Wales wind-diesel system. Advantages of NiCad batteries compared to lead-acid batteries include a deeper discharge capability, lighter weight, higher energy density, a constant output voltage, and much better performance during cold temperatures. However, NiCads are considerably more expensive than lead-acid batteries and one must note that the Wales wind-diesel system had a poor operational history and has not been functional for over ten years. Because batteries operate on direct current (DC), a converter is required to charge or discharge when connected to an alternating current (AC) system. A typical battery storage system would include a bank of batteries and a power conversion device. The batteries would be wired for a nominal voltage of roughly 300 volts. Individual battery voltages on a large scale system are typically 1.2 volts DC. Recent advances in power electronics have made solid state inverter/converter systems cost effective and preferable a power conversion device. The Kokhanok wind-diesel system is designed with a 300 volts DC battery bank coupled to a grid-forming power converter for production of utility-grade real and reactive Marshall Wind-Diesel Feasibility Analysis P a g e | 11 power. Following some design and commissioning delays, the solid state converter system in Kokhanok should be operational by late 2013 and will be monitored closely for reliability and effectiveness. Wind Turbine Options Several village-scale wind turbines are considered suitable for Marshall. The guiding criteria are turbine output rating in relation to electric load, simplicity of design, AVEC Operations department preferences, redundancy, and cost considerations. The turbines chose for review in this CDR are the Northern Power Systems NPS 100, the Vestas V20, and the Aeronautica 33-225. Northern Power Systems NPS100-21 ARCTIC The Northern Power 100-21 ARCTIC (NPS100-21), formerly known as the Northwind 100 (NW100), is rated at 100 kW and is equipped with a permanent magnet, synchronous generator, is direct drive (no gearbox), can be equipped with heaters and insulation, and has been tested to ensure operation in extreme cold climates. The turbine has a 21 meter diameter rotor and is available with a 30 or 37 meter monopole towers, or a 48 meter lattice tower. The rotor blades are fixed pitch for stall control but the turbine is also inverter regulated for maximum 100 kW power output. For Marshall, the NPS100-21 will be equipped with a cold climate package enabling a minimum operating temperature of -40° C. The Northern Power 100 is the most widely represented village-scale wind turbine in Alaska with a significant number of installations in the Yukon-Kuskokwim Delta and on St. Lawrence Island. The Northern Power 100-21 wind turbine is manufactured in Barre, Vermont, USA. More information may be found at http://www.northernpower.com/. Northern Power NPS100 wind turbine Marshall Wind-Diesel Feasibility Analysis P a g e | 12 Vestas V20 The Vestas V20 was originally manufactured by Vestas Wind Systems A/S in Denmark and is no longer in production. It is, however, available as a remanufactured unit from Halus Power Systems in California (represented in Alaska by Marsh Creek, LLC) and from Talk, Inc. in Minnesota. The V20 is rated at 120 kW and is a higher output version of the two Vestas V17 wind turbines installed in Kokhanok in 2011. The V20 has a fixed-pitch, stall-regulated rotor coupled to an asynchronous (induction) generator via a gearbox drive. The original turbine design included low speed and high speed generators in order to optimize performance at low and high wind speeds. The two generators are connected to the gearbox with belt drives and a clutch mechanism. In some installations though – especially sites with a high mean wind speeds – the low speed generator is removed to eliminate a potential failure point. Vestas V17 wind turbines in Kokhanok (similar to the V20) Aeronautica AW33-225 The Aeronautica AW33-225 wind turbine is manufactured new by Aeronautica in Durham, New Hampshire. This turbine was originally designed by the Danish-manufacturer Norwin in the 1980’s with a 29 meter rotor diameter and had a long and successful history in the wind industry before being replaced by larger capacity turbines for utility-scale grid-connect installations. The original 29 meter rotor diameter design is available as the AW29-225 for IEC Class IA wind regimes. The AW33-225 is a new variant designed for IEC Class II and III winds. The AW225 turbine is stall-regulated, has a synchronous (induction) generator, active yaw control, is rated at 225 kW power output, and is available with 30, 40, or 50 meter tubular steel towers. The AW33-225 is cold climate certified to -30° C and is new to the Alaska market with no in-state installations at present. While the AW29-225 has a typical cut-out wind speed of 25 m/s, the larger rotor diameter AW33-225 is designed for a cut-out speed of 22 m/s. More information can be found at http://aeronauticawind.com/aw/index.html. Marshall Wind-Diesel Feasibility Analysis P a g e | 13 Aeronautica AW 33-225 wind turbine (29-225 version shown) Homer Software Wind-Diesel Model Homer energy modeling software was used to analyze the existing Marshall power plant. Homer software was designed to analyze hybrid power systems that contain a mix of conventional and renewable energy sources, such as diesel generators, wind turbines, solar panels, batteries, etc. and is widely used to aid development of Alaska village wind power projects. It is a static energy balance model, however, and is not designed to model the dynamic stability of a wind-diesel power system, although it will provide a warning that renewable energy input is potential sufficient to result in system instability. Diesel Power Plant Electric power (comprised of the diesel power plant and the electric power distribution system) in Marshall is provided by AVEC with the following diesel configuration. Marshall powerplantdiesel generators Generator Electrical Capacity Diesel Engine Model Generator 1 500 kW Caterpillar 3456 Cat LC6 2 363 kW Detroit Series 60 DDEC4 Kato 6P4-1450 3 236 kW Detroit Series 60 DDEC4 Kato 6P4-1450 Wind Turbines This CDR evaluates installation of three new Northern Power Systems NPS100-21 turbines for 300 kW installed capacity, three remanufactured Vestas V20 turbines for 360 kW installed capacity, or one new Aeronautica AW33-225 turbines for 225 KW installed capacity. Standard temperature and pressure (STP) power curves are shown below. Note that for the Homer analysis, site elevation was adjusted to reflect the measured mean annual air density of 1.294 kg/m3. Marshall Wind-Diesel Feasibility Analysis P a g e | 14 Northern Power 100-24 Arctic Vestas V20 Aeronautica AW33-225 Electric Load Marshall electric load data, collected from March 2012 to September 2013, was received from William Thompson of AVEC. These data are in 15 minute increments and represent total electric load demand during each time step. The data were processed by adjusting the date/time stamps nine hours from UTC to Yukon/Alaska time, converting the data from kWh to kW, and creating a January 1 to December 31 hourly list for export to HOMER software. The resulting load is shown graphically below. Average load is 190 kW with a 323 kW peak load and an average daily load demand of 4,561 kWh. This compares to a 185 kW average load reported to the RCA for the 2012 PCE report. Electric load Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Ann 50 100 150 200 250 300 350 Seasonal Profile max daily high mean daily low min Marshall Wind-Diesel Feasibility Analysis P a g e | 15 Thermal Load Powerplant heat recovery in Marshall is non-functional at present with fairly long distances to relatively large heat loads. Homer modeling indicates that excess wind energy from the wind turbine combinations considered would be large enough to warrant construction of a recovered heat system or remote placement of a secondary load controller/electric boiler in a building with high thermal demand, such as the new school or the water plant. Due to the relatively modest amount of predicted excess energy from wind turbine operation, it is assumed that the school and/or water plant can use this excess energy to displace heating oil usage. Diesel Generators The HOMER model was constructed with all three Marshall diesel generators. For cost modeling purposes, AEA assumes a generator O&M cost of $0.020/kWh. Other diesel generator information pertinent to the HOMER model is shown below. Individual generator fuel curve information is available but Homer modeling with generator-specific fuel curves indicated fuel efficiency of 15.3 kWh/gal in the base case (no wind turbines). This is higher than AVEC’s reported fuel efficiency of 12.98 kWh/gal to Regulatory Commission of Alaska for the 2012 Power Cost Equalization Report, and the 14.44 kWh/gal efficiency for Marshall documented in AVEC’s 2011 annual generation report. Diesel generator HOMER modeling information Diesel generator Caterpillar 3456 Detroit Series 60 DDEC4 Detroit Series 60 DDEC4 Power output (kW) 500 363 236 Intercept coeff. (L/hr/kW rated) 0.00651 0.0195 0.0146 Slope (L/hr/kW output) 0.2382 0.2122 0.2384 Minimum electric load (%) 5.0% (25 kW) 6.9% (25 kW) 10.6% (25 kW) Heat recovery ratio (% of waste heat that can serve the thermal load) 22 22 22 Intercept coefficient – the no-load fuel consumption of the generator divided by its capacity Slope – the marginal fuel consumption of the generator 0 6 12 18 24 0 50 100 150 200 250 Daily Profile Hour Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 0 6 12 18 24 DMap 90 138 186 234 282 330 kW Marshall Wind-Diesel Feasibility Analysis P a g e | 16 Cat 3456 fuel efficiency curve DD60 DDEC4 Gen 2 DD60 DDEC4 Gen 3 Economic Analysis Installation of wind turbines in medium penetration mode is evaluated in this report to demonstrate the economic impact of these turbines with the following configuration: turbines are connected to the electrical distribution system with first priority to serve the electrical load, and second priority to serve the thermal load via a secondary load controller and electric boiler. Wind Turbine Costs Project capital and construction costs for the three evaluated wind turbines were obtained from HDL, Inc. and are presented below. Detailed information regarding HDL’s cost estimates is available in their portion of this conceptual design report. Project cost estimates Turbine No. Turbines HDL Estimated Project Cost Installed kW Cost per kW Capacity Tower Type Tower Height (meters) Northern Power NPS100-21 Arctic 3 $3,441,275 285 $12,074 Monopole 37 Vestas V20 3 $3,102,175 360 $8,617 Lattice 32 Aeronautica AW33-225 1 $2,808,025 225 $12,480 Monopole 50 Marshall Wind-Diesel Feasibility Analysis P a g e | 17 Fuel Cost A fuel price of $4.99/gallon ($1.32/Liter) was chosen for the initial HOMER analysis by reference to Alaska Fuel Price Projections 2013-2035, prepared for Alaska Energy Authority by the Institute for Social and Economic Research (ISER), dated June 30, 2013 and the 2013_06_R7Prototype_final_07012013 Excel spreadsheet, also written by ISER. The $4.99/gallon price reflects the average value of all fuel prices between the 2015 (the assumed project start year) fuel price of $4.17/gallon and the 2034 (20 year project end year) fuel price of $5.98/gallon using the medium price projection analysis with an average social cost of carbon (SCC) of $0.61/gallon included. By comparison, the fuel price for Marshall (without social cost of carbon) reported to Regulatory Commission of Alaska for the 2012 PCE report is $3.32/gallon ($0.88/Liter), without inclusion of the SCC. Assuming an SCC of $0.40/gallon (ISER Prototype spreadsheet, 2013 value), the Marshall’s 2012 diesel fuel price was $3.72/gallon ($0.98/Liter). Heating fuel displacement by excess energy diverted to thermal loads is valued at $6.32/gallon ($1.67/Liter) as an average price for the 20 year project period. This price was determined by reference to the 2013_06_R7Prototype_final_07012013 Excel spreadsheet where heating oil is valued at the cost of diesel fuel (with SCC) plus $1.05/gallon, assuming heating oil displacement between 1,000 and 25,000 gallons per year. Fuel cost table (SCC included) ISER med. projection 2015 (/gal) 2034 (/gal) Average (/gallon) Average (/Liter) Diesel Fuel $4.17 $5.98 $4.99 $1.32 Heating Oil $5.22 $7.03 $6.04 $1.60 Modeling Assumptions As noted previously, HOMER energy modeling software was used to analyze a wind-diesel hybrid power plant to serve Marshall. HOMER is designed to analyze hybrid power systems that contain a mix of conventional and renewable energy sources, such as diesel generators, wind turbines, solar panels, batteries, etc. and is widely used to aid development of Alaska village wind power projects. Modeling assumptions are detailed in the table below. Assumptions such as project life, discount rate, operations and maintenance (O&M) costs, etc. are AEA default values and contained in the ISER spreadsheet model. Other assumptions, such as diesel overhaul cost and time between overhaul are based on general rural Alaska power generation experience. The base or comparison scenario is the existing power plant with no functional heat recovery loop. Note that wind turbines installed in Marshall will operate in parallel with the diesel generators. Excess energy will serve thermal loads via a secondary load controller and electric boiler (to be installed). Installation cost of wind turbines assumes construction of three phase power distribution to the selected site, plus civil, permitting, integration and other related project costs. Marshall Wind-Diesel Feasibility Analysis P a g e | 18 Homer modeling assumptions Economic Assumptions Project life 20 years (2015 to 2034) Discount rate 3% Operating Reserves Load in current time step 10% Wind power output 100% (Homer setting to always force diesels on) Fuel Properties (no. 2 diesel for powerplant) Heating value 46.8 MJ/kg (140,000 BTU/gal) Density 830 kg/m 3 (6.93 lb./gal) Price (20 year average; ISER 2013, medium projection plus social cost of carbon) $4.99/gal ($1.32/Liter) Fuel Properties (no. 1 diesel to serve thermal loads) Heating value 44.8 MJ/kg (134,000 BTU/gal) Density 830 kg/m 3 (6.93 lb./gal) Price (20 year average; ISER 2013, medium projection plus social cost of carbon) $6.04/gal ($1.60/Liter) Diesel Generators Generator capital cost $0 (new generators already funded) O&M cost $0.02/kWh (reference: ISER 2013 Prototype spreadsheet) Diesel generator efficiency (Homer) 15.2 kWh/gal (from diesel fuel curves) Diesel generator efficiency (ISER) 13.0 kWh/gal (from 2012 PCE report) Minimum load 25 kW; based on AVEC’s operational criteria of 25 kW minimum diesel loading with their wind-diesel systems Schedule Optimized Wind Turbines Availability 80% O&M cost $0.049/kWh (reference: ISER 2013 Prototype spreadsheet) Wind speed 6.27 m/s at 30 m, 100% turbine availability 5.57 m/s at 30 m, 80% turbine availability Density adjustment 1.242 kg/m^3 (mean of monthly means of 18 months of Marshall met tower data; Homer wind resource elevation set at -150 meters to simulate the Marshall air density Power law exponent 0.133 (met tower data) Hub height/tower type NPS100-21 Arctic: 37 meter monopole V20: 32 meter lattice AW33-225: 50 meter monopole Energy Loads Electric 4.56 MWh/day average Marshall power plant load Thermal Undefined at present; assumed large enough to absorb excess wind energy Marshall Wind-Diesel Feasibility Analysis P a g e | 20 Conclusion and Recommendations Marshall has a very good wind resource for wind power development, especially considering its distance from the Bering Sea coast. Wind behavior is desirable with low turbulence, low wind shear, moderate extreme wind probability, and little evidence of severe icing conditions. The analysis in this report considered configurations of three Northern Power 100 wind turbines, three remanufactured Vestas V20 wind turbines, or one Aeronautica AW225 wind turbine, all in a medium penetration configuration with no electrical storage and a wind-heat node at the school or the water plant. It is recommended that this project proceed to the design phase. Further analysis and discussion may better highlight advantages and disadvantages of each option considered, but at present all three options present nearly equivalent economic valuation, hence turbine choice is largely a matter of preference for the utility. Appendix B ANTHC Marshall Alaska Heat Recovery Study Appendix C August 3, 2012 Marshall Wind Site Investigation Report Marshall WAsP Site Options Analysis July 23, 2012 Using ten months of wind data collected from the Marshall met tower (Site 0050), WAsP software was used to model the wind regime of Marshall and to predict mean wind speed and turbine performance at the met tower site and three possible alternative wind power sites, shown in the maps below. Topographic maps Google Earth map WAsP wind speed map Predicted site wind speed and turbine performance Wind speed and turbine annual energy production (AEP) are calculated by the WAsP software. Turbine AEP is based on the NW100B turbine at a 30 meter hub height, the height of the met tower upper level anemometers. Turbine hub height is 37 meters, hence actual turbine AEP would be better than indicated below, but setting turbine hub height at anemometer height simplifies the analysis and the purpose here is comparative, not actual. Once a site is chosen and the CDR written, turbine type and actual hub height will be adjusted to obtain true predicted performance. Site comparison table Mean wind speed Mean power density AEP AEP compared to met tower site m/s W/m² MWh/yr % Met tower site 6.19 336 239.5 100% Alternate Site 1 6.44 388 255.7 107% Alternate Site 2 6.09 330 231.9 97% Alternate Site 3 6.72 441 274.2 114% Recommendation The wind site options in Marshall, in a general sense, are good considering Marshall’s distance upriver from the coast. The met tower site is roughly comparable to alternate site 2, but nearby alternate site 1, just 315 meters straight downhill from the met tower site toward the Yukon River, is predicted at 7 percent higher energy production. Alternate site 3, located on a rise on the road leading to the UUI tower on Pilcher Mountain, is the best of the four sites with predicted 14 percent higher turbine energy production than at the met tower site. It is recommended that all four possible wind sites be investigated for landownership and access issues. Distribution line construction costs should be compared to turbine performance over time to determine highest net present value; this will help determine the preferred turbine site for development. H:\jobs\12-025 Marshall Wind Project\Site Visit 8-3-12\PHOTOLOG.docx Page 1 Photo 1: Met Tower Site Photo 2: Seasonal Access Road to Alternative Sites 2 and 3 Photo 3: Existing UUI Communication Pole Settlement Photo 4: Access Road to Airport, between Marshall and Wilson Creek H:\jobs\12-025 Marshall Wind Project\Site Visit 8-3-12\PHOTOLOG.docx Page 2 Photo 5: Native Allotment near Alternative Site 1 Photo 6: Inside Existing AVEC Power Plant Appendix D Marshall Wind Project Feasibility Design Drawings MARSHALL WIND PROJECTMARSHALLFEASIBILITY DESIGN DRAWINGSMARSHALL, ALASKASHEET INDEXNOT FORCONSTRUCTION4831 Eagle StreetAnchorage, Alaska 99503 ABBREVIATIONSLEGENDEARTHWORKTUNDRA PROTECTIONNOT FORCONSTRUCTION4831 Eagle StreetAnchorage, Alaska 99503 NOT FORCONSTRUCTION4831 Eagle StreetAnchorage, Alaska 99503 NOT FORCONSTRUCTION4831 Eagle StreetAnchorage, Alaska 99503 NOT FORCONSTRUCTION4831 Eagle StreetAnchorage, Alaska 99503 NOT FORCONSTRUCTION4831 Eagle StreetAnchorage, Alaska 99503 NOT FORCONSTRUCTION4831 Eagle StreetAnchorage, Alaska 99503 NOT FORCONSTRUCTION4831 Eagle StreetAnchorage, Alaska 99503 Appendix E Concept Level Capital Cost Estimate Concept Level EstimateMarshall Wind Farm ConstructionAlternative Cost Summary9/30/13SUMMARYDescription Estimated Construction Installed kW Estimated Construction Tower TypeCost Cost/ Installed kWAlternative 1 - (3) Northern Power 100 Arctic Turbines $ 3,174,175.00 300 $ 10,580.58 MonopoleAlternative 2 - (3) V20's $ 2,890,575.00 360 $ 8,029.38 Lattice Alternative 3- (1) AW33-225 $ 2,660,400.00 225 $ 11,824.00 Monopole Concept Level Estimate Marshall Wind Farm Construction Alternative 1 9/30/13 Item Estimated Quantity Unit Price ($) Subtotal ($) Alternative 1 (3) Northern Power 100 Arctic Turbines 1 4,123 CY Borrow 25 103,075 2 24,000 SF Geotextile 2 48,000 3 3 Each Concrete Gravity Mat Foundations 100,000 300,000 4 3 Each Northern Power 100B Arctic Wind Turbines 375,000 1,125,000 5 3,500 LF Electrical Spur Line to New Power Plant Location 37 129,500 6 1 Sum Wireless Communication System 75,000 75,000 7 1 Sum Wind Turbine Power Integration 250,000 250,000 8 1 Sum Labor 130,000 130,000 9 1 Sum Equipment 125,000 125,000 10 1 Sum Freight 450,000 450,000 11 1 Sum Indirects 150,000 150,000 Subtotal Construction 2,885,575$ Land Acquisition $0 Project Contingency @ 10% 288,600$ 0 Years Inflation @ 2% $0 Total 3,174,175$ Installed Generation Capacity 300 kW Total Cost 3,174,175$ Cost/Installed kW $10,581 Description Concept Level Estimate Marshall Wind Farm Construction Alternative 2 9/30/13 Item Estimated Quantity Unit Price ($) Subtotal ($) Alternative 2 (3) V20's 1 4,123 CY Borrow 25 103,075 2 24,000 SF Geotextile 2 48,000 3 3 Each Concrete Gravity Mat Foundations 104,000 312,000 4 3 Each Vestas V20 Wind Turbines 225,000 675,000 5 3,100 LF Electrical Spur Line to New Power Plant Location 37 114,700 6 1 Sum Wireless Communication System 75,000 75,000 7 1 Sum Wind Turbine Power Integration 375,000 375,000 8 1 Sum Labor 150,000 175,000 9 1 Sum Equipment 100,000 150,000 10 1 Sum Freight 332,000 400,000 11 1 Sum Indirects 175,000 200,000 Subtotal Construction 2,627,775$ Land Acquisition $0 Project Contingency @ 10% 262,800$ 0 Years Inflation @ 2% $0 Total 2,890,575$ Installed Generation Capacity 360 kW Total Cost 2,890,575$ Cost/Installed kW $8,029 Description Concept Level Estimate Marshall Wind Farm Construction Alternative 3 9/30/13 Item Estimated Quantity Unit Price ($) Subtotal ($) Alternative 3 (1) AW33 225 1 1,400 CY Borrow 25 35,000 2 8,000 SF Geotextile 2 16,000 3 1 Each Concrete Gravity Mat Foundations 275,000 275,000 4 1 Each AW33 225 Wind Turbines 600,000 600,000 5 2,500 LF Electrical Spur Line to New Power Plant Location 37 92,500 6 1 Sum Wireless Communication System 75,000 75,000 7 1 Sum Wind Turbine Power Integration 400,000 400,000 8 1 Sum Labor 25,000 175,000 9 1 Sum Equipment 150,000 150,000 10 1 Sum Freight 525,000 400,000 11 1 Sum Indirects 200,000 200,000 Subtotal Construction 2,418,500$ Land Acquisition $0 Project Contingency @ 10% 241,900$ 0 Years Inflation @ 2% $0 Total 2,660,400$ Installed Generation Capacity 225 kW Total Cost 2,660,400$ Cost/Installed kW $11,824 Description Appendix E FAA Permitting