HomeMy WebLinkAboutDCVR-HCI-7DESIGN CLARIFICATION%VERIFICATION REQUEST CONTRACTOR: PROJECT: SPEC. NO.: Hankal Construction, Inc. Unalakleet Bulk Fuel Upgrade DC/VR NO.: HCI-7 CONTRACT NO.: REG-06-088 DRAWINGS NO.: C-10 DESCRIPTION OF REQUEST: An elevation discrepancy has been discovered. 8x12 posts and 6x6 timbers set to date are 6" too high. The result is that the 8x12 posts are shallow in embedment. If the shallow embedment is acceptable, the elevation can be corrected by removing the top 6x6 timber and resetting it at the bottom of the stack. The 8x12 posts could then be trimmed to specific elevation. Please advise. Rapid Response Requested -- Work Has Stopped. ATTACHMENT: YES[- NoZ CHANGE ORDER: YES[] NOM IF YES PROVIDE RFP: WRITTEN BY: DAVE SHELLENBERGER DATE: APPROVED BY: DATE: DAVE SHELLENBERGER RESPONSE: RFP REQUIRED: YES NO BY: DATE: This is NOT any authorization for additional reimbursement or time extension. Authorization of such can be made only by the owner through a change order in accordance with the contract documents. DCVRFORM