HomeMy WebLinkAboutWeld TestsAlaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Visual Inspection Report Project: AK ENERGY AUTHORITY Bulk Fuel Upgrade, Unalakleet Client: Hanakal Construction Code: API Standard 1104 Procedure: HANKAL P2 Job No.: 04-740 Weld Identification I.$— Irregular bead shape. We, the undersigned, certify that the statements in this record are correct and that the welds were prepared and tested in accordance with the following Code de API 1104 Inspector: Bob McCauley Test Date: 7 ;Z s% Contractor/Client: Hankal Construction Authorized by: Project: Client: Code: Procedure: Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Fisual Inspection Report AK ENERGY AUTHORITY Bulk Fuel Upgrade, Unalakleet Hanakal Construction API Standard 1104 HANKAL P2 Job No.: 04-740 • mmm R �. M. We, the undersigned, certify that the statements in this record are correct and that the welds were prepared and tested in accordance with the following Code API 1104 Inspector: Bob McCauley Contractor/Client: Hankal Construction Test Date: f%Z /0 Authorized by: Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Visual Inspection Report Project: AK ENERGY AUTHORITY Bulk Fuel Upgrade, Unalakleet Job No.: 04-740 Client: Hanakal Construction Code: API Standard 1104 Procedure: HANKAL P2 j W1- W6 W2 W5 y W3 W4 W72i AM W12 W8 ;' W 11 m `'Mw W9 W10 3" Sched 40 pipe to 90 ells Weld identification and location to be determined during tie-in with tank piping Date Welder ID Weld Interpretation Remarks Accept Reject 7/29/2006 Chris Hall Wl X Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK 7/29/2006 Chris Hall W2 X 7/29/2006 Chris Hall W3 X 7/29/2006 Chris Hall W4 X 7/29/2006 Chris Hall W5 X 7/29/2006 Chris Hall W6 X 7/29/2006 Chris Hall W7 X 7/29/2006 Chris Hall W8 X 7/29/2006 Chris Hall W9 X 7/29/2006 Chris Hall WIO X 7/29/2006 Chris Hall Wil X 7/29/2006 Chris Hall W12 X We, the undersigned, certity that the statements m this record are correct and that the welds were prepared and tested in accordance with the following Code API 1104 Inspector: Robert McCauley CWI 84111161 Contractor/Client: Hankal Construction Si ature: Alaska industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Visual Inspection Report Project: AK ENERGY AUTHORITY Bulk Fuel Upgrade, Unalakleet Client: Hanakal Construction Code: API Standard 1104 Procedure: HANKAL P2 ram w� w6 W2 W5 W3 W4 Job No.: 04-740 3" Sched 40 pipe to 90 ells Weld identification and location to be determined during tie-in with tank piping Date Welder ID Weld Interpretation Remarks Accept Reject 7/31/2006 Chris Hill W1 X Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK 7/31/2006 Chris Hill W2 X 7/31/2006 Chris Hill W3 X 7/31/2006 Chris Hill W4 X 7/31/2006 Chris Hill W5 X 7/31/2006 Chris Hill W6 X We, the undersigned, certify that the statements in this record are correct and that the welds were prepared and tested in accordance with the following Code API 1104 Inspector: Robert McCauley CWI 84111161 Contractor/Client: Hankal Construction Si ature: Project: Client: Code: Procedure: Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Visual Inspection Report AK ENERGY AUTHORITY Bulk Fuel Upgrade, Unalakleet Hanakal Construction API Standard 1104 HANKAL P2 Wi W6 W2 W5 x� W3 W4 W7 `� W12 W8 W1 i W9 W10 Job No.: 04-740 3" Sched 40 pipe to 90 ells W13 W18 W14 W17 W15 W16 Weld identification and location to be determined during tie-in with tank piping Date Welder ID Weld Interpretation Remarks Accept Reject 8/1/2006 Chris Hill W1 X Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK 8/1/2006 Chris Hill W2 X 8/1/2006 Chris Hill W3 X 8/1/2006 Chris Hill W4 X 8/1/2006 Chris Hill W5 X 8/1/2006 Chris Hill W6 X 8/1/2006 Chris Hill W7 X 8/1/2006 Chris Hill W8 X 8/1/2006 Chris Hill W9 X 8/1/2006 Chris Hill W10 X 8/1/2006 Chris Hill W11 X 8/1/2006 Chris Hill W12 X 8/1/2006 Chris Hill W13 X 8/1/2006 Chris Hill W14 X 8/1/2006 Chris Hill W15 X 8/1/2006 Chris Hill W16 X 8/1/2006 Chris Hill W17 X 8/1/2006 Chris Hill W18 X We, the undersigned, certify that the statements in this record are correct and that the welds were prepared and tested in accordance with the following Code API 1104 Inspector: Robert McCauley CWI 84111161 Contractor/Client: Hankal Construction Si azure: Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Visual Inspection Report Project: AK ENERGY AUTHORITY Bulk Fuel Upgrade, Unalaklcet Client: Hanakal Construction Code: API Standard 1104 Procedure: HANKAL P2 6 assemblies �a Job No.: 04-740 WI through W 12 (12 welds) 3" Sched 40 pipe to 90 ells Flanges to 90 degree ells Weld identification and location to be determined during tie-in with tank piping Date Welder ID Weld Interpretation Remarks Accept Reject 8/2/2006 Chris Hill W1 X Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK 8/2/2006 Chris Hill W2 X 8/2/2006 Chris Hill W3 X 8/2/2006 Chris Hill W4 X 8/2/2006 Chris Hill W5 X 8/2/2006 Chris Hill W6 X 8/2/2006 Chris Hill W7 ° X 8/2/2006 Chris Hill W8 X 8/2/2006 Chris Hill W9 X 8/2/2006 Chris Hill W10 X 8/2/2006 Chris Hill Wi l X 8/2/2006 Chris Hill W12 X We, the undersigned, certify that the statements m this record are correct and that the welds were prepared and tested in accordance with the following Code API 1104 Inspector: Robert McCauley CWI 84111161 Contractor/Client: Hankal Construction Si ature: fCL cy�: J Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Visual Inspection Report Project: AK ENERGY AUTHORITY Bulk Fuel Upgrade, Unalakleet Client: Hanakal Construction Code: API Standard 1104 Procedure: HANKAL P2 4"Sched 80 pipe 9 girth welds .lob No.: 04-740 Weld identification and location to be determined during tie-in with tank piping Date Welder ID Weld Interpretation Remarks Accept Reject 8/3/2006 Neal Cabiness W1 Fit -up, root pass OK,(Incomplete) Fit -up, root pass OK,(Incomplete) Fit -up, root pass OK,(Incomplete) Fit -up, root pass OK,(Incomplete) Fit -up, root pass OK,(Incomplete) Fit -up, root pass OK,(Incomplete) Fit -up, root pass OK,(Incomplete) Fit -up, root pass OK,(Incomplete) Fit -up, root pass OK,(Incomplete) 8/3/2006 Neal Cabiness W2 8/3/2006 Neal Cabiness W3 8/3/2006 Neal Cabiness W4 8/3/2006 Neal Cabiness W5 8/3/2006 Neal Cabiness W6 8/3/2006 Neal Cabiness W7 8/3/2006 Neal Cabiness W8 8/3/2006 Neal Cabiness W9 We, the undersianed. certify that the statements in this record are correct and that the welds were prepared and tested in accordance with the following Code API 1104 Inspector: Robert McCauley CWI 84111161 Signature: Contractor/Client: Hankal Construction Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Visual Inspection Report Project: AK ENERGY AUTHORITY Bulk Fuel Upgrade, Unalakleet Client: Hanakal Construction Code: API Standard 1104 Procedure: HANKAL P2 3 assemblies TMIM 5 assemblies .lob No.: 04-740 Wl through W16 (16 welds) 3" Sched 40 pipe to 90 ells Flanges to 90 degree ells Weld identification and location to be determined during tie-in with tank piping Date Welder ID Weld Interpretation Remarks Accept Reject 8/3/2006 Chris Hill W1 X Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK 8/3/2006 Chris Hill W2 X 8/3/2006 Chris Hill W3 X 8/3/2006 Chris Hill W4 X 8/3/2006 Chris Hill W5 X 8/3/2006 Chris Hill W6 X 8/3/2006 Chris Hill W7 " X 8/3/2006 Chris Hill W8 X 8/3/2006 Chris Hill W9 X 8/3/2006 Chris Hill W10 X 8/3/2006 Chris Hill W11 X 8/3/2006 Chris Hill W12 X 8/3/2006 Chris Hill W13 X 8/3/2006 Chris Hill W14 X 8/3/2006 Chris Hill W15 X 8/3/2006 Chris Hill W16 X We, the undersigned, certify that the statements in this record are correct and that the welds were prepared and tested in accordance with the following Code API 1104 Inspector: Robert McCauley CWI 84111161 Contractor/Client: Hankal Construction Si ature: �c Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Visual Inspection Report Project: AK ENERGY AUTHORITY Bulk Fuel Upgrade, Unalakleet Client: Hanakal Construction Code: API Standard 1104 Procedure: HANKAL P2 Job No.: 04-740 4"Nom.Sched 80 pipe 13 joints w/root&hot, 5 welds completed Weld identification and location to be determined during tie-in with tank piping Date Welder ID Weld Interpretation Remarks Accept Reject 8/4/2006 Neal C.& Don Sh. W1 X Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK 8/4/2006 Neal C.& Don Sh. W2 X 8/4/2006 Neal C.& Don Sh. W3 X 8/4/2006 Neal C.& Don Sh. W4 X 8/4/2006 Neal C.& Don Sh. W5 X We, the undersigned, certify that the statements in this record are correct and that the welds were prepared and tested in accordance with the following Code API 1104 Inspector: Robert McCauley CWI 84111161 Contractor/Client: Hankal Construction Signature: Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Visual Inspection Report Project: Aid ENERGY AUTHORITY Bulk Fuel Upgrade, Unalakleet Client: Hanakal Construction Code: API Standard 1104 Procedure: HANKAL P2 5 assemblies Job No.: 04-740 Wl through W10 (10 welds) 3" Sched 40 pipe to 90 ells Flanges to 90 degree ells Weld identification and location to be determined during tie-in with tank piping Date Welder ID Weld Interpretation Remarks Accept Reject 8/5/2006 Chris Hill W1 X Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK 8/5/2006 Chris Hill W2 X 8/5/2006 Chris Hill W3 X 8/5/2006 Chris Hill W4 X 8/5/2006 Chris Hill W5 X 8/5/2006 Chris Hill W6 X 8/5/2006 Chris Hill W7 X 8/5/2006 Chris Hill W8 X 8/5/2006 Chris Hill W9 X 8/5/2006 Chris Hill W10 X we the undersienned, certctythat the statements in this record are correct and that the welds were prepared and tested in accordance with the following Code API 1104 Inspector. Robert McCauley CWI 94111161 Contractor/Client Hankal Construction Si afore: Project: Client: Code: Procedure: Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestrucdve Testing Report N'sual Inspection .Report AK ENERGY AUTHORITY Bulk Fuel Upgrade, Unalakleet Hanakal Construction API Standard 1104 HANKAL P2 Job No.: 04-740 4"Nom.Sched 80 pipe 9 joints w/root&hot, 9 welds completed Weld identification and location to be determined during tie-in with tank piping Date Welder ID Weld Interpretation Remarks Accept Reject 8/5/2006 Neat C.& Don Sh. W 1 X Fit -up, root pass & cap pass OK lFit-up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK 8/5/2006 Neal C.& Don Sh. W2 X 8/5/2006 Neal C.& Don Sh. W3 X 8/512006 Neal C.& Don Sh. W4 X 8/5/2006 Neat C.& Don Sh. W5 X 8/5/2006 Neal C.& Don Sh. W6 X 8/5/2006 Neal C.& Don Sh. W7 X 8/5/2006 Neal CA Don Sh. W8 X 8/5/2006 Neal C.& Don Sh. W9 X We. the undersigned, certify that the statements in this record are correct and that the welds were prepared and tested in accordance with the following Code API 1104 Inspector Robert McCauley CWI 84111161 Contractor/Client Hankal Construction S�nature:•r�'''�_- Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Deport Visual Inspection Report Project: AK ENERGY AUTHORITY Bulk Fuel Upgrade, Unalakleet Client: Hanakal Construction Code: API Standard 1104 Procedure: HANKAL P2 4"Nom.Sched 80 pipe 15 welds completed Job No.: 04-740 Weld identification and location to be determined during tie-in with tank piping Date Welder ID Weld Interpretation Remarks Accept Reject 8/6/2006 Neal G.& Don Sh. W1 X Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK 8/6/2006 Neal C_& Don Sh. W2 X 8/6/2006 Neal C.& Don Sh. W3 X 8/6/2006 Neal C.& Don Sh. W4 X 8/6/2006 Neal C.& Don Sh_ W5 X 8/6/2006 Neal C.& Don Sh. W6 X 8/6/2006 Neal C.& Don Sh. I W7 X 8/6/2006 Neal C_& Don Sh. W8 X 816/2006 Neal C.& Don Sh. W9 X 8/6/2006 Neal C.& Don Sh. W 10 X 816/2006 Neal C.& Don Sh. W11 X 8/6/2006 Neal C.& Don Sh. W12 X 8/6/2006 Neal C.& Don Sh. W13 X 8/6/2006 Neat C.& Don Sh. W 14 X 8/6/2006 Neal C.& Dan Sh. W 15 X We the undersigned, certify that the statements in this record are correct and that the welds were prepared and tested in accordance with the following Code API 1104 Inspector: Robert McCauley CWI 84111161 ,.� Contractor/Client: Hankal Construction Signature --,A,_: Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Visual Inspection Report Project: AK ENERGY AUTHORITY Bulk Fuel Upgrade, Unalakleet Client: Hanakal Construction Code: API Standard 1104 Procedure: HANKAL P2 Tn.Sched.80 pipe, (2) 90 degree ells Job No.: 04-740 Weld identification and location to be determined during tie-in with tank piping Date Welder ID Weld Interpretation Remarks Accept Reject 8/6/2006 Neal C. W 1 X Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK 8/6/2006 Neal C. W2 X 8/6/2006 Neal C. W3 X 8/6/2006 Neal C. W4 X We. the undersisned, certify that the statements in this record are correct and that the welds were prepared and tested in accordance with the following Code API 1104 Inspector. Robert McCauley CWI 84111161 Contractor/Client Hankal Construction Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report T-isuul Inspection Deport Project: AK ENERGY AUTHORITY Bulk Fuel Upgrade, Unalakleet Client: Hanakal Construction Code: API Standard 1104 Procedure: HANKAL P2 1 assembly, 2 welds 0m.'" 2 assemblies, 2 welds 1 assembly, 2 welds Job No.: 04-740 3" Sched 40 pipe to 90 ell 3" Sched 40 pipe to 90 ell 3" Sched 40 pipe to 90 ell Flange to 90 degree ell Weld identification and location to be determined during tie-in with tank piping Date Welder ID Weld Interpretation Remarks Accept Reject 817/2006 Chris Hill W1 X Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK Fit -up, root pass and cap pass OK 8/7/2006 Chris Hill W2 X 8/7/2006 Chris Hill W3 X 8/7/2006 Chris Hill W4 X 8/7/2006 Chris Hill W5 X 8/7/2006 Chris Hill W6 X We the undersigned, ceriify that the statements in this record are correct and that the welds were prepared and tested in accordance with the following Code API 1104 Inspector. Robert McCauley CWI 84111161 Contractor/Client: Hankal Construction Si afore_ /7/ ''� Project: Client: Code: Procedure: Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99604 907-344-4061 IV onrdestructive Testing Report Visual Inspection Deport AK ENERGY AUTHORITY Bulk Fuel Upgrade, Unalakleet Hanakal Construction API Standard 1104 HANKAL P2 4" Nom.Sched.80 pipe, (1) 90 degree ell `\� {{S ?z � rr Job No.: 04-740 Weld identification and location to be determined during tie-in with tank piping Bate Welder ID Weld Interpretation Remarks Accept Reject 8/7/2006 Don Shearer Wl X Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK 8/7/2006 Don Shearer W2 X We, the undersigned, certify that the statements in this record are correct and that the welds were prepared and tested in accordance with the following Code API 1104 Inspector: Robert McCaule�yC�WI 84111161 Contractor/Client Hankal Construction Si Lure: r/ �' �� Project: Client: Code: Procedure: Alaska industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-3"-4069 Nondestructive Testing Report Visual Inspection Report AK ENERGY AUTHORITY Bulls Fuel Upgrade, Unalakleet Hanakal Construction AN Standard 1104 HANKAL P2 .lob No.: 04-740 4"Nom.Sched 80 pipe 8 joints fit up w/root & hot, 2 welds completed 2 lines from marine header Weld identification and location to be determined during tie-in with tank piping Date Welder ID Weld interpretation Remarks Accept Reject 8/8/2006 Neal CA Don Sh. W1 X Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK 8/8/2006 Neal C '& Don Sh. W2 X We, the undersigned, certify that the statements in M's recora are correct auu ur " soulUS were prepared and tested in accordance with the following Code AN 1104 Inspector. Robert McCauley CWI 84111161 Contractor/Client Nankai Construction Si ature: Project: Client: Code: Procedure., Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Visual Inspection Report AK ENERGY AUTHORITY Bulk Fuel Upgrade, Unalakleet Hanakal Construction API Standard 1104 HANKAI. P2 rn _..x. _�.. �k �-: z�,. Y ,3 - �-:.s:....a_ :.�� ...a _. `fs.: r;es',''.i,�-: �-%,TM..`�.•.xa,-a'«.�.as>;; .�?.:k � ,r,,,�;a.,, n4: Joke No.: 04-740 4"Nom.Sched 80 pipe 13 joints it up w/root & hot, 8 welds completed 2 lines from marine header Weld identification and location to be determined during tie-in with tank piping Date Welder ID Weld Interpretation Remarks Accept Reject 8/9/2006 Neal C.& Don Sh_ W1 X Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK R-up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK 8/9/2006 Neal C.& Don Sh. W2 X 8/9/2006 Neal G.& Don Sh. W3 X 8/9/2006 Neal C.& Don Sh. W4 X 8/9/2006 Ideal C.& Don Sh. W5 X 8/9/2006 eat C.& Don Sh. W6 X 8/9/2006 Neal C_& Don Sh. W7 X 8/9/2006 Neal C.& Don Sh. W8 X We the undersigned, certify that the statements in this record are correct and that me welds were pret�ared and tested in accordance with the following Code API 1104 Inspector Robert McCauley CWI 84111161 Contractor/Client Hankal Construction Project: Client: Code: Procedure: Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Visual Inspection Report AK ]ENERGY AUTHORITY Bulk Fuel Upgade, Unalakieet Job No.: 04-740 I3anakal Construction API Standard 1104 HANKAL P2 4x2"Tee r 2 assemblies, 6 welds Tee outlet to 2" sched 80 pipe �F for low point drain Weld identification and location to be determined during tie-in with tank piping Date Welder ID Weld Interpretation Remarks Accept Reject 8/9/2006 Chris Hill W1 X Finished weld OK Finished weld OK Finished weld OK Finished weld OK Finished weld OK Finished weld OK 8/9/2006 Chris Hill W2 X 8/9/2006 Chris Hill W3 X 8/9/2006 Chris Hill W4 X 8/9/2006 Chris Hill W5 X 8/9/2006 Chris Hill W6 X We the undersigned, cerU!y Mat the statements M uns recora are correct anu Lnat we WUIUS were prepared and tested in accordance with the following Code API 1104 _Inspector: Robert McCauley CW184111161 Contractor/Client: Hankal Construction Signature:. �r��� Project: Client: Code: Procedure: Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Mud Inspection Report AK ENERGY AUTHORITY Bulk Fuel Upgrade, Unalakleet Job No.: 04-740 Hanakal Construction API Standard 1104 HANKAL P2 ;r`t; .. i.:.....t ,Tz'�.Z- ... .'_ r shl �k r M ..9F Est-v`""tfr.'....�-:% 4"Nom.Sched 80 pipe 9 welds completed, 4 additional Joints fit up w/root & hot 2 lines from marine header Weld identification and location to be determined during tie-in with tank piping Bate Welder ID Weld Interpretation Remarks Accept Reject 8/10/2006 Neal C.& Don Sh. W1 X Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK 8/10/2006 NealC.& Don Sh. W2 X ail0/2006 Neal C.& Don Sh. W3 X 8/10/2006 Neai C.& Don Sh. W4 X 8/10/2006 Neal C.& Don Sh. W5 X 8/10/2006 Neai C.& Don Sh. W6 X 8/10/2006 Neal C.& Don Sh. W7 x 8/10/2006 Neal C.& Don Sh. W8 x 8/10/2006 Neal C.& Don Sh. W9 X We the undersigned, cgrify that the statements to this record are correct and that the welds were prepared and tested in accordance with the following Code API 1104 inspector. Robert McCauley CWI 84111161 Contractor/Client Hankal Construction Signature: 7 Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestrucdve Testing Report Visual Inspection Report Project: AK ENERGY AUTHORITY Bulk Fuel Upgrade, Unalakleet Client: Hanakal Construction Code: API Standard 1104 Procedure: HANKAL P2 ..+ 3'a ..., vYn kS11, 1.m.1 4. `Y `,Y'm; Job No.: 04-740 4"Nom.Sched 80 pipe 8 welds completed, 4 additional joints fit up w/root & hot 2 lines from marine header Weld "identification and location to be determined during tie-in with tank piping Date Welder ID Weld Interpretation Remarks Accept Reject 8/11/2006 Neal C.& Don Sh. W1 % Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fii-up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK 8/11/2006 Neal C.& Don Sh. W2 X 8/11/2006 Neal C.& Don Sh. W3 x 8/11/2006 Neal C.& Don Sh. W4 x 8/11/2006 Neal C.& Don Sh. W5 X 8/11/2006 Neal C.& Don Sh. W6 X 8/11/2006 Neal C.& Don Sh. W7 X 8/1112006 Neal C.& Don Sh. Wg X We the undersigned_ certify that the statements in this record are correct and th the welds were prepared and tested in accordance with the following Code API 1104 Inspector: Robert McCauley CWI 84111161 Contractor/Client: Nankai Construction Signature:!,:�G._=��:. if Project: Client: Code: Procedure: Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99604 907-344-4061 Nondestructive Vesting Report Visual Iiaspection Report AK ENERGY AUTHORITY Sulk Fuel Upgrade, Unaiakleet Hanakal Construction API Standard 1104 HANKAL P2 -- u.--11, .'"T-3?.,;, ;:.:'�-;. 4"Nom.Sched 80 pipe 3 welds completed 2 lines from marine header Job No.: 04-740 Weld identification and location to be determined during tie-in with tank piping Date Welder III Weld Interpretation Remarks Accept Reject 8/12/2006 Neal C.& Don Sh. W1 X lFitrup, Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK root pass & cap pass OK 8/12/2006 Neal C.& Don Sh. W2 X 8/12/2006 Neal C.& Don Sh. W3 X We the undersigned. certify that the statements in ttus recora are correct and Mat the welds were prepared and tested in accordance with the foll2ly mg Code API 1104 ector. Robert McCauley CW184111161 Signature: r Contractor/Client: Hankal Construction Alaska Industrial X-ray Inc. 4047 Kingston ®rive Anchorage, Alaska 99504 907-344-4061 Nondestructive Vesting Report Vrsual Inspection Report Project: AK ENERGY AUTHORITY Bulk Fuel Upgrade, Unalakleet Job No.: 04-740 Client: Hanakal Construction Code: API Standard 1104 Procedure: HANKAL P2 om.Sched.80 pipe, tie-in to UVEC tine at marine header Weld identification and location to be determined during tie-in with tank piping l fey root pass & cap pass +! --=-- We the undersigned, cent ay mat me sLawmenas w uu, 1-mu m-, L-11- — ,.�..- were prepared and tested in accordance with the following Code API 1104 Insaector: Robert McCauley CWI 84111161 Signature; �� Contractor/Client Hankal Construction Project: Client: Code: Procedure: Alaska Industrial X-ray Inc, 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Visual Inspection Report AID ENERGY AUTHORITY Bulk Fuel Upgrade, Unalakleet Hanakal Construction API Standard 1104 HANK.AL P2 ds, pipe to 90 degree ells 2 welds Pipe to pipe tie-ins 4"Nom.Sched 80 pipe UVEC lime from marine Deader to power plant JOIN No.: 04-740 Date Welder ID Weld Interpretation Remarks Accept Re3ect 8/14/2006 Neal C.& Don Sh. W1 X Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK Fie -up, root pass & cap pass OK Fit -up, root pass & cap pass OK 8/14/2006 Neal C_& Don Sh. W2 X 8/14/2006 Neal C.& Don Sh. W3 X 8/14/2006 Neal C.& Don Sh. W4 X We the nndersiled, cettifv that the statements to this record are correct and that the welds were prepared and tested in accordance with the following Code API 1104 Inspector. Robert McCauley CWI 84111161 Contractor/Client: Hankal Construction Signature:>: f �.U� _'✓�� G� Project: Client: Code: ]Procedure: Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Visual Inspection Report AK ENERGY AUTHORITY Bulk Fuel Upgrade, Unalakleet Hanakal Construction API Standard 1104 HANKAL P2 4"Nom.Sched 80 pipe 2 welds completed 21mes from marine header Job No.: 04-740 Date Welder ID Weld Interpretation Remarks Accept Reject 8/1412006 Neal C.& Don Sh_ Wl X Fit -up, root pass & cap pass OK Fit -up, root pass & cap pass OK 8/14/2006 Neal C.& Don Sh. W2 X We the undersigned certify that the statements in this record are correct and that the welds were prepared and tested in accordance with the following Code API 1104 Inspector_ Robert McCauley CWI 84111161 Contractor/Client: Nankal Construction Signature:-��.%�c�Mi Project: Client: Code: Procedure: Alaska Industrial X-ray Inc. 4047 Kingston ®rive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Visual Inspection Report AK ENERGY AUTHORITY Bulls Fuel Upgrade, Unalakleet ,Iola No.: 04-740 Hanakal Construction API Standard 1104 HANKAL P2 1 assembly, 3 welds 4" Sched 80 tee to (2) neck flanges Tee to 90 degree ell -- Q om 1 assembly, 1 weld Flange to 4" 40 degree ell Fabricated assemblies for terminations on UVEC pipeline Bate Welder H) Weld Interpretation Remarks Accept Reject 8/14/2006 Chris Hill Wl X Finished weld OK Finished weld OK Finished weld OK Finished weld OK 8/14/2006 Chris Hill W2 X 8/14/2006 Chris Hill W3 X 8/14/2006 Chris Hill W4 X We, the undersigned, certify that the statements in this record are correct and that the welds were prepared and tested in accordance with the following Code API 1104 Inspector: Robert McCauley CWI 84111161 Contractor/Client Hankal Construction Si G� Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Visual Inspection Report Project: AK ENERGY AUTHORITY Bulk Fuel Upgrade, Unalakleet Job No.: 04-740 Client: Hanakal Construction Code: API Standard 1104 Procedure: HANKAL P2 REPAIR WELD Pinhole leak detected from pressure test 4x2 Sched 80 pipe tee 2" outlet to 2" pipe Line from marine header to tank farm Date Welder ID Weld Interpretation Remarks Accept Reject 8/15/2006 Chris Hill Repair X Fusion defect removed by grinding a 1" section to depth of pipe wall. Preheated and welded with complete penetration. Repeat pressure test satisfactory We the undersiVed. cegi%that the statements in this record are correct and that the welds were pWared and tested in accordance with the following Code API 1104 Inspector. Robert McCauley CWI 94111161 Contractor/Client: Hankai Construction Si AL.ASKA INDUSTRIAL X-RAY 4047 KINGSTON DRIVE ANCHOAGE, AK 99904 (907) 344-4061 FAX (907) 349-3875 VISUAL INSPECTION REPORT S1, MARY PROJECT: Unalakleet Bulk Fuel Storage CUSTOMER: Hankal CODE: API Std 1104 WELD PROCEDURE: Hankal P2 WELDERS: WO I, W02, W03 and W46 were welded by Chris dill as subassemblies (flange to tee, tee to ell and flange to elf). Welds W04 through W45 were welded by Neil Cabiness and Don Shearer from Aug. 3 to 14, 2006. Marine Header W01— W04 W05 — W06 2' 3" W09 All other welds are 40' apart UVEC Power Plant Pipeline curves with road W45 — W46 , W43—W44(� 40' W40 �` 12" 10" 44' W39 Welding Conditions: Acceptable for all welds I Welding Parameters: Acceptable for all welds Description Weld ID Consumables Fit -Up VT Weld 46 girth welds on 4" None E6010 Lincoln Accepted No visible defects were detected. Air pressure test sched.80, A53/A106 5P for all was completed with no leaks detected gr.B pipe and welds fittings. Prepared W. Robert McCauley CWl#84111161 Alaska Industrial X-ray Inc. 4047 Kingston ©rive Anchorage, Alaska 99304 907-344-4061 Nondestructive Vesting Report Visual Inspection Report Project: AK Energy Authority Bulk Fuel Ijgrade Job No.: 04-740 Client: Hankal Const. Code: APII104 Procedure: AIX-VT-1 Welders ID: Surface Condition: Clean Direct View: XXX Special )Illumination: None Indirect View: Weld Location and Identifiication Sketch T)nn Shearer Date Weld Identification ;Are -]a Interpretation Remarks Accept Reject811612006 ProductionWelds WI,W2,W3 xax—M-fpa� —d-p W4,W5,W6 100% x roohotpassJUI and cap SI7 _Inspector: Sean Kelly `- Contractor/Client: Hankal Construction Test Date: 811 ti/2006 Authorized by: AlasflG . 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive %Ming Report Visual Inspection Report Project: AK energy Authority Bulk Fuel Ugrade Unaiakleet AK Job No.: 04-740 Client: Hankal Construction Code: AP11104 Procedure: A1X-1 Weld Location and Identification Sketch Date Remarks 8/16/2006 I arrived into Unakleet at 330 pm and went out to the jobsite and inftodaced myselfto the welders. I observed Don Shearer welding on a 4" sch 80 piece. I inspected the rootp:m and well as the hotpass. All looked good and he continued to finsh the weld His fill and cap was also inspected and were visually acceptable The weather -today was sunnv with a little breeze We_ the undersitaled, certify that the statements in this record are correct and that the welds Hankai Construction Test Date_ 8116/2006 Authorized by: ALASKA INDUSTRIAL X-RAY 4047 KINGSTON DRIVE ANCHORAGE, AK 99504 (907) 344-4061 FAX (907) 349-3875 JOB NO. 04-470 DATE 8/1612006 CUSTOMER Hankai Contruction 1 LOCATION Unalaklett AK PAGE 1 OF 1 PROJECT AK Energy Auth Fuel Upgrade CODE API 1104 Contract No. VISUAL WELD INSPECTION REPORT Neal Cabiness Procedure Variable Applicable Provision Comments Compliance Welding Procedure No. 5.3 Hankal 2 OK Process 5.3.2.1 SMAW OK Pipe Material 5.3.2.2 ASTM A53 OK Pipe Diameter 5.3.2.3 2 718" and over OK Pipe Wall Thickness 5.3.2.3 3/16" to .864" OK Joint Bevel 5.3.2.4 60 Degrees OK Face 5.3.2.4 1116" OK Opening 5.3.2.4 1/16" + 1/32" OK Filler Metal 5.3.2.5 SFA5.1 OK Electrical Current 5.3.2.6 D.C. OK Voltage 5.32.6 24-30 V OK Amperage P 5.3.2.6 90-170 OK O as t1/ 5.3.2.6 Electrode Size 5.3.2.6 action 5.3.29 i itne Lapse 5.3.2.10 Line Up Clamp 5.3.2.11 Cleaning 5.3.2.12 Preheat 5.3.2.13 Weider Qualification 6.0 Design Allingment 7.0 Line Up Clamp Removal 7.3 Bevel 7 4 Weather 7.5 Clearance 7.6 Filler & Finish Beads 7.8.2 Welder Identification 7.10 Visual Inspection 9.7 Undercut s 7 2 Surface Porosity 9.3.93 Reinforcement 7.8.2 Cracking 9.3.10 Radiography Procedure 11.1.2.2 Penetrameter 11.1.5 Film Identification 11.1.8 Radiographers 11.1.7 Storage 11.1.19 Density 11.1.10 Radiation 11.1.13 Rev. Downward 2 to 12 Min Yes Power Brush 100 F Min Yes _ 60 Degrees Clear 16 " min Power Brush Yes None None 1/16" / 1/8" none NIA OK OK OK OK OK OK OK OK OK Clear OK OK OK OK OK OK OK N/A Prepared By: Sean Kelly i� ALASII A INDUSTRIAL X-RAY 4047 KINGSTON DRIVE SOB NO. 04-470 ANCHORAGE, AK 99504 (907) 344-4061 FAX (907) 349-3875 DATE 8/16/2006 CUSTOMER Hankai Contruction LOCATION Unalaklett AK PAGE 1 OF 1 PROJECT AK Energy Auth Fuel Upgrade CODE API 1104 Contract No. VISUAL WELD INSPECTION REPORT Don Shearer Procedure Variable Applicable Provision Comments Compliance Welding Procedure No. 5.3 Hankal 2 OK Process 5.3.2.1 SMAWN OK Pipe Material 5.3.2.2 ASTM A53 OK Pipe Diameter 5.32.3 2 7/8" and over OK Pipe Wall Thickness 5.3.2.3 3/16" to .864" OK Joint Bevel 5.3.2.4 60 Degrees OK Face 5.3.2.4 1/16" OK Opening 5.3.2.4 1116" +_ 1132" OK Filler Metal 5.3.2.5 SFA5.1 OK Electrical Current 5.32.6 D.C. OK Voltage 5.3.2.6 24-30 V OK Amperage 5.3.2.6 90-170 OK Polarity 5.3.2.E Rev. OK Electrode Size 5.3.2.6 1/8" OK :coon 5.32.9 Downward OK a Qme Lapse 5.3.2.10 2 to 12 Min OK Line Up Clamp 5.3.2.11 Yes OK Cleaning 5.3.2.12 Power Brush OK Preheat 5.3.2.13 100 F Min OK Welder Qualification 6.0 Design Allingment 7.0 Line Up Clamp Removal 7.3 Yes OK Bevel 7.4 60 Degrees OK Weather 7.5 Clear Clear Clearance 7.6 16 " min OK Filler & Finish Beads 7.82 Power Brush OK Welder Identification 7.10 Yes OK Visual Inspection 9.7 - Undercut 9.7.2 None OK Surface Porosity 9.3.93 None OK Reinforcement 7.5.2 1/16" / 1/8" OK Cracking 9-3.10 none OK Radiography Procedure 11.1.22 WA N/A Penetrameter 11.1.5 Film Identification 11.1.8 Radiographers 11.1.7 Storage 11.1.19 Density 11.1.10 Radiation 11.1.13 Prepared By: Sean Kelly �''' Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 1 ondestmedve Testing deport Visual Inspection Report Project: Ali Energy Authority Bulk Fuel Ugrade Job No.: 04-740 Client: Hankal Cant. Code: Procedure: API 1104 AIX-w-1 Surface Condition: Clean Direct View: = Special Illuruination: None Indirect View: Date Weld Identification Area Interpretation Remarks Accept Reject 8/17/2006 Production Welds W-7 100% xxx Don Shearer roatlhotpass/f .cap W-9 Gas line i00"/o lNeil Cabiness roWhotpass/fill,cap 4" weld Fuel Line 1000/0 xxx Neil iabiness root/hotpass/filL ap 3 each 4" welds for 100% xxx Don Shearer rootjho4mswfiXc ap fuel oil We, the undersignecL cerhfv that the statements in this record are correct and that the welds Were prepared and tested in accordance with the following Code: API 1104 Inspector. Sean Kelly y Contractor/Client: Hankal Construction Test Date: 8/17/2006 Authorized by: Alaska industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99604 907-344-4061 Nondestructive Testing E port Visual Inspection Report Project: Alaska Energy Authority Bulk Fuel Upgrade Unalakleet, AK Job No.: 04-740 Client: Nankai Construction Code: API1104 Procedure: AIX-1 Weld Location and Identifiication Sketch Date Weld Identification I Area Interpretation Remarks , Accept I Reject 8/17/2006 This morning was very wet with rain so Don used a tent to shelterhimelfand the pipe from the rain He finished welding the the gas line risers from the marine header. After that weld was completed there was an air test on that spool before it could the welded to the oilier existing line. That test was successful at 140psi for 1 hour_ After huh Don started welding on the fuel oil riser_ By the end ofthe day he had completed 4 welds for that spool. Neff today welded 2 each 4"welds.He had one weld on the gas line and one weld on the fuel oil line to make. Both welds were also inspected along with dons welds with no problems being noted We the undersigned.. certify that the statements in this record are correct and that the welds lient: Hankal Construction Test Date: 8/17/2006 Authorized by: ALASKA INDUSTRIAL_ X-RAY 4047 KINGSTON DRIVE JOB NO. 04-470 ANCHORAGE, AK 99504 (907) 344-4061 FAX (907) 349-3875 DATE 8/17/2006 CUSTOMER Hankai Contruction LOCATION Unaiaklett AK PAGE 1 OF 1 PROJECT AK Energy Auth Fuel Upgrade CODE API 1104 Contract No. VISUAL WELD INSPECTION REPORT Neal Cabiness Procedure Variable Applicable Provision Comments Compliance 'fielding Procedure No. 5.3 Hankal 2 OK Process 5.3.2.1 SMAW OK Pipe Material 5.3.2.2 ASTM A53 OK Pipe Diameter 5.3.2.3 2 7/8" and over OK Pipe Wall Thickness 5.3.2.3 3116" to .864' OK Joint Bevel 5.3.2.4 60 Degrees OK Face 5.3.2.4 1116" OK Opening 5.3.2.4 1/16" + 1/32" OK Filler Metal 5.3.2.5 SFA5.1 OK Electrical Current 5.3.2.6 D.C. OK Voltage 5.3.2.6 24-30 V OK Amperage 5.3.2.6 90-170 OK Polarity 5.3.2.6 Rev. OK Electrode Size 5.3.2.6 1/8" OK ction 5.3.2.9 Downward OK "i ..ode Lapse 5.3.2.10 2 to 12 Min OK Line Up Clamp 5.3.2.11 Yes OK Cleaning 5.3.2.12 Power Brush OK Preheat 5.3a13 100 F Min OK Welder Qualification 6.0 Design Allingment 7.0 Line Up Clamp Removal 7.3 Yes OK Bevel 7.4 60 Degrees OK Weather 7.5 Rain Rain Clearance 7.6 16 " min OK Filler & Finish Beads 7.8.2 Power Brush OK Welder Identification 7.10 Yes OK Visual Inspection 9.7 Undercut 9.7.2 None OK Surface Porosity 9.3.93 None OK Reinforcement 7.8.2 1/16" / 1/8" OK Cracking 9.3.10 none OK Radiography Procedure 11.1.2.2 N/A N/A Penetrameter 11.1.5 Film Identification 11.1.5 Radiographers 11.1.7 Storage 11.1.19 Density 11.1.10 Radiation 11.1.13 Prepared By. Sean Kelly ALASKA INDUSTRIAL X-RAY 4047 KINGSTON DRIVE JOB NO. 04-470 ANCHORAGE, AK 99604 (907) 344-4061 FAX (907) 349-3875 DATE 8/17/2006 CUSTOMER Hankal Contruction LOCATION Unalaklett AK PAGE 1 OF 1 PROJECT AK Energy Auth Fuel Upgrade CODE API 1104 Contract No. VISUAL WELD INSPECTION REPORT Don Shearer Procedure Variable Applicable Provision Comments Compliance Welding Procedure No. 5.3 Hankal 2 OK Process 5.3.2.1 SMAW OK Pipe Material 5.3.2.2 ASTM A63 OK Pipe Diameter 5.3.2.3 2 7/8" and over OK Pipe Wall Thickness 5.3.2.3 3/16" to 864" OK Joint Bevel 5.3.2.4 60 Degrees OK Face 5.3.2.4 1/16 , OK Opening 5.3.2.4 1/16' + 1/32' OK, Filler Metal 5.3.2.5 SFA5.1 OK Electrical Current 5.3.2.E D.C. OK Voltage 5.3.2.6 24-30 V OK Amperage 5.3.2.6 90-170 OK Polarity 5.3.2.6 Rev_ OK Electrode Size 5.3.2.6 1/8" OK r' ction 5.32.9 Downward OK ° .e Lapse 5.32.10 2 to 12 Min OK Line Up Clamp 5.3.2.11 Yes OK Cleaning 5.3.2.12 Power Brush OK Preheat 5.3.2.13 100 F Min OK Welder Qualification 6.0 Design Allingment 7.0 Line Up Clamp Removal 7.3 Yes OK Bevel 7.4 60 Degrees OK Weather 7.5 Rain Rain Clearance 7.6 16 " min OK Filler & Finish Beads 7.8.2 Power Brush OK Welder Identification 7.10 Yes OK Visual Inspection 9.7 Undercut 9.7.2 None OK Surface Porosity 9.3.93 None OK Reinforcement 7.&2 1/16" / 118" OK Cracking 9.3.10 none OK Radiography Procedure 11.1.2.2 N/A N/A Penetrameter 11.1.5 Film Identification 11.1.E Radiographers 11.1.7 Storage 11.1.19 Density 11.1.10 Radiation 11.1.13 Prepared By Sean Kelly Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99604 907-344-4061 Nondestructive Testing Deport Visual Inspection Report Project: AK Energy Authority Bulk Fuel ilgrade Job No.: 04-740 Client: Hankal Const. Code: API1104 Procedure: AIX-VT-1 weld Surface Condition: Clean Direct View: XXX Special Munination: None Indirect View: Welders ID: Neil �ahine_cc - T'%-- et.o___ Date Weld Identification Area Interpretation - --- -- Remarks Accept Reject 8l1812006 Production Welds 2" LPD Fuel fail W-4,W-5 100%, Don Shearer rwVbotpa-T cap 2" LPD Gas Line 'N-4, W-5 100% ax Don Shearer rooUhoYgass/fll caP e Gas Line W-7A 100% xxx Neil Cabiness root/hotpass/fill cap 4" Fuel tail Lure W-9 I00% Neil Cabin.—Vhotpasslfacap OwMcsucuQ. M umb 1cw1m are carrec:r anu t[1at the weias Inspector: Sean Kelly Contractor/client: Hankal Construction Test Date: 8/18/2006 Authorized by: Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 90e-344-4061 Nondestructive Testing Deport Visual Inspection Report Project: Alaska Energy Authority Bulk Fuel Upgrade Unalakleet, AID Job No.: 04-740 Client: Hankal Construction Code: API1104 Procedure: AIX-I Weld Location and identification Sketch Date Weld Identification I Area Interpretation Remarks. Accept Reject 8/18/2006 This morning was sunny and cold with the breeze. Don Shearer was welding a spool together for the Low Point Drains for each the gas line and the fuel oil line. The welds were for the road crossing part ofthe spool. Neil was welding the tie-in weld from the marine header to the fuel oil line. Both Don and Neil and there fitups anpeeted and root pass visually inspected. After acceptance they both completed there welds . After lunch ned tied in the gas line from the marine header and don welded both the LPDs to the fuel oil line and the gas line_ All welds were visually inspected dewing the intie process and were acceptable. We. the undersigned. certify that the statements in this record are correct and that the welds were prepared and tested in accordance with the following Code: API 1104 Hankal Construction Test Date: 8118/2006 Authorized by: ALASKA INDUSTRIAL X-RAY 4047 KINGSTON DRIVE ANCHORAGE, AK 99504 (907) 344-4061 FAX (907) 349-3875 CUSTOMER Hankal Contruction JOB NO. 04-470 DATE 8/18/2006 LOCATION Unalaklett AK PAGE 1 OF 1 PROJECT AK Energy Auth Fuel Upgrade CODE API 1104 Contract No. VISUAL WELD INSPECTION REPORT Neal Cabiness Procedure Variable Applicable Provision Comments Compliance Welding Procedure No. 5.3 Hankal 2 OK Process 5.3.2.1 SMAW OK Pipe Material: 5.3.2.2 ASTM A53 OK Pipe Diameter 5.3.2.3 2 7/8" and over OK Pipe Wall Thickness 5.3.2.3 3/16" to .864" OK Joint Bevel 5.3.2.4 60 Degrees OK Face 5.3.2.4 1/16" OK Opening 5.32.4 1/16" +_ 1/32" OK Filler Metal 5.3.2.5 SFA5.1 OK Electrical Current 5.3.2.6 D.C. OK Voltage 5.3.2.6 24-30 V OK Amperage 5.3.2.6 90-170 OK Polarity 5.3.2.6 Rev. OK Electrode Size 5.3.2.6 1/87 OK ction 5.3.2.9 Downward OK 1 arae Lapse 5.3.2.10 2 to 12 Mtn OK Line Up Clamp 5.3.2.11 Yes OK Cleaning 5.3.2.12 Power Brush OK Preheat 5.3.2.13 100 F Min OK Welder Qualification 6.0 Design Allingment 7.0 Line Up Clamp Removal 7.3 Yes OK Bevel 7.4 60 Degrees OK Weather 7.5 Clear Clear Clearance 7.6 16 " min OK Filler $ Finish Beads 7.8.2 Power Brush OK Welder Identification 7.10 Yes OK Visual Inspection 9.7 _ Undercut 9.7.2 None OK Surface Porosity 9.3.93 None OK Reinforcement 7.82 1/16" / 1/8" OK Cracking 9.3.10 none OK Radiography Procedure 11.1.22 NIA N/A Penetrameter 11.1.5 Film Identification 11.1.8 Radiographers 11.1.7 Storage 11.1.19 Density 11.1.10 Radiation 11.1.13 Prepared By: Sean Kelly- '' ALASKA INDUSTRIAL X-RAY 4047 KINGSTON DRIVE JOB NO. 04-470 ANCHORAGE, AK 99604 (907) 344-4061 FAX (907) 349-3875 DATE 8/18/2006 CUSTOMER Hankal Contrucilon LOCATION Unalaklett AK PAGE 1 OF 1 PROJECT AK Energy Auth Fuel Upgrade CODE API 1104 Contract No. VISUAL WELD INSPECTION REPORT Don Shearer Procedure Variable Applicable Provision Comments Compliance Welding Procedure No. 5.3 Hankai 2 OK Process 5.3.2.1 SMAW OK Pipe Material 5.3.2.2 ASTM A53 OK Pipe Diameter 5.3.2.3 2 718" and over OK Pipe Wall Thickness 5.3.2.3 3/16" to .864" OK Joint Bevel 5.32.4 60 Degrees OK Face 5.3.2.4 1/16" OK Opening 5.3.2.4 1116" +_ 1/32" OK Filler Metal 5.3.2.5 SFA5.1 OK Electrical Current 5.3.2.6 D.C. OK Voltage 5.3.2.6 24-30 V OK Amperage 5.3.2.6 90-170 OK Polarity 5.3.2.6 Rev. OK Electrode Size 5.3.2.6 1/8" OK ' 'ction 5.3.2.9 Downward OK l wle Lapse 5.3.2.10 2 to 12 Min OK Line Up Clamp 5.3.2.11 Yes OK Cleaning 5.3.z12 Power Brush OK Preheat 5.3.2.13 100 F Min OK Welder Qualification 6.0 Design Allingment 7.0 Line Up Clamp Removal 7.3 Yes OK Bevel 7.4 60 Degrees OK Weather 7.5 Clear Clear Clearance 7.6 16 " min OK Filler & Finish IBeads 7.6.2 Power Brush OK Weider Identification 7.10 Yes OK Visual inspection 9.7 _ Undercut 9.7.2 None OK Surface Porosity 9.3.93 None OK Reinforcement 7.8.2 1116" / 1/8" OK Cracking 9.3.10 none OK Radiography Procedure 11.1.2.2 N/A N/A Penetrameter 11.1.5 Film Identification 11.1.8 Radiographers 11.1.7 Storage 11.1.19 Density 11.1.10 Radiation 11.1.13 Prepared By: Sean Kelly 9 - Alaska industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Visual Inspection Deport Project: AK Energy Authority Bulk Fuel Ugrade Job No.: 04-740 Client: Hankal Const. Code: Procedure: API 1104 AIX-VT-1 Surface Condition: Clean Direct View: XXX Special Illumination: None Indirect View: Date Weld Identification Area interpretation Remarks Accept Reject 811 912006 Production Welds 4" Lines Bridge crossing Welds Gas Line W31 100% xxx Neal Root/Hotpass Don Fill and Cap Fuel oil W 34 100% xxx Neal Root/Hotpass Don Fill and Cap Gas Line W30 I Om/n "x Neal weld out Fuel Oil W33 100% xxx Neal weld out Fuel Oil W32 100% xxx Neal weld out Fuel Oil W29 Neal weld out End Caps W-1 1000% xxx Don Shearer weld out W-2 100% xXIN Don Shearer weld out we, we underslaled certil* that the statements in this record are correct and that the welds were prepared and tested in accordance with the following Code API 1104 nos ectar: Sean Kelly Contractor/Client: Hankal Construction Test Date: 81/9/2006 " " Authorized by: Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive T esiing Report VistiralInspection Report Project: Alaska Energy Authority Htlik Fuel Upgrade UnalakleeL AID Join No.: 04-740 Client: Hankal Construction Code: API1104 Procedure: AIX-1 Weld Location and Identification Sketch Date I Weld 8/19/2006 The momimg started with an air test an the fuel oil line. After that test was successful they tested the gas line. That lest was also successful. Don Shearer was welding on end caps for the air test on sections for the bridge crossing. Those two welds were visually inspected during the welding process and was acceptable. Neal was weldingtogether sections for the bridge crossing also. He had welded the root and hotpass in three welds and welded out two complete welds Don welded the fill and cap on the welds that veal lust vid the root and hotnass in. We. the undersigned certify that the statements in this record are correct and that the welds were pretoared and tested in accordance with the following Code: API 1104 Inspector: SeanKell - Contractor/Client: Hankal Construction Test Date: 8/19/2006 Authorized by: ALASKA INDUSTRIAL X-RAY 4047 KINGSTON DRIVE JOB NO. 04-470 ANCHORAGE, AK 99504 (907) 344-4061 FAX (907) 349-3875 DATE 8/19/2006 CUSTOMER Hankal Contruction LOCATION Unalaklett AK PAGE 1 OF 1 PROJECT AK Energy Auth Fuel Upgrade CODE API 1104 Contract No. VISUAL WELD INSPECTION REPORT Don Shearer Procedure Variable Applicable Provision Comments Compliance Welding Procedure No. 5.3 Hankal 2 OK Process 5.3.2.1 SMAW OK Pipe Material 5.3.2.2 ASTM A53 OK Pipe Diameter 5.3 2.3 2 7/8" and over OK Pipe Wall Thickness 5.3.2.3 3/16" to .864" OK Joint Bevel 5.3.2.4 60 Degrees OK Face 5.3.2.4 1116" OK Opening 5.3.2.4 1/16" + 1/32" OK Filler Metal 5.3.2.5 SFA5.1 OK Electrical Current 5.3.2.6 D.C. OK Voltage 5.3.2.6 24-30 V OK Amperage 5.3.2.E 90-170 OK Polarity 5.3.2.6 Rev. OK Electrode Size 5.3.2.6 118" OK i 'ction 5.3.2.9 Downward OK 1 .ae Lapse 5.3.2.10 2 to 12 Min OK Line Up Clamp 5.3.2.11 Yes OK Cleaning 5.3.2.12 Power Brush OK Preheat 5.3.2.13 100 F Min OK Welder Qualification 6.0 Design Allingment 7.0 Line Up Clamp Removal 7.3 Yes OK Bevel 7.4 60 Degrees OK Weather 7.5 Clear Clear Clearance 7.6 16 " min OK Filler & Finish Beads 7.8.2 Power Brush OK Welder Identification 7.10 Yes OK Visual Inspection 9_7 Undercut 9.7.2 None OK Surface Porosity 9.3.93 None OK Reinforcement 7.8.2 1/16" / 1/8" OK Cracking 9.3.10 none OK Radiography Procedure 11.1.2.2 N/A N/A Penetrameter 11.1.5 Film Identification 11.1.8 Radiographers 11.1.7 Storage 11.1.19 Density 11.1.10 Radiation 11.1.13 Prepared By: Sean Kelly ALASKA INDUSTRIAL X-RAY 4047 KINGSTON DRIVE JOB NO. 04-470 ANCHORAGE, AK 99504 (907) 344-4061 FAX (907) 349-3875 DATE 8/19/2006 CUSTOMER Hankai Contruction LOCATION Unalaklett AK PAGE 1 OF 1 PROJECT AK Energy Auth Fuel Upgrade CODE API 1104 Contract No. VISUAL WELD INSPECTION REPORT Neal Cabiness Procedure Variable Applicable Provision Comments Compliance Welding Procedure No. 5.3 Hankal 2 OK Process 5.3.2.1 SMAW OK Pipe Material 5.3.2.2 ASTM A53 OK Pipe Diameter 5.3.2.3 2 7/8" and over OK Pipe Wall Thickness 5.3.2.3 3/16" to .864" OK Joint Bevel 5.3.2.4 60 Degrees OK Face 5.3.2.4 1 /16" OK Opening 5.3.2.4 1/16" + 1/32" OK Filler Metal 5.32.5 SFA5.1 OK Electrical Current 5.3.2.6 D.C. OK Voltage 5.3.2.6 24-30 V OK Amperage 5.3.2.6 90-170 OK Polarity 5.3.2.6 Rev. OK Electrode Size 5.32.6 1/9, OK r Ctlon 5.3.2.9 Downward OK i safe Lapse 5.3.2.10 2 to 12 Min OK Line Up Clamp 5.3.2.11 Yes OK Cleaning 5.3.2.12 Power Brush OK Preheat 5.3.2.13 100 F Min OK Welder Qualification 6.0 Design Allingment 7.0 Line Up Clamp Removal 7.3 Yes OK Bevel 7.4 60 Degrees OK Weather 7.5 Clear Clear Clearance 7.6 16 " min OK Filler & Finish Beads 7.8.2 Power Brush OK Welder Identification 7.10 Yes OK Visual Inspection 9.7 Undercut 9.7.2 None OK Surface Porosity 9.3.93 None OK Reinforcement 7.8.2 1/16" / 1/8" OK Cracking 9.3.10 none OK Radiography Procedure 11.1.2.2 N/A N/A Penetrameter 11.1.5 Film Identification 11.1.8 Radiographers 11.1.7 Storage 11.1.19 Density 11.1.10 Radiation 11.1.13 Prepared By: Sean Kelly Alaska Industrial X-ray Inc. t. 4047 Kingston Drive Jt7 Anchorage, Alaska 36504 507-344-4061 Nondestructive Testing Report Visual Inspection Report Project: Alaska Energy Authority Bulk Fuel Upgrade Unalakleet, AK Job No.: Client: Hankal Construction Code: AP11104 Procedure: AIX-1 Veld Location and Identification Sketch Hate Meld identification Area Interpretation Remarks Accept I Reject /2t}/20ii6 This morning Neal started with welding on the test cap on the fuel oil line in preparation for the air test. While the lest was going on he welded out W27 on the gas line and another test cap for the gas line. All welds were visually inspected during th welding process with no problems being noted. The air test for the fuel line and the gas line for the bridge section was done and was successful_ We. the uundersmned, certifv that the statements m this record are correct and that the welds 04-740 Inspector: SeanKelly _yr Contractor/Client: Hankal Construction Test Date: 8120/2006 Authorized by: Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-844-4061 Nondestructive Testing Report Visual Inspection Report Project: AK Energy Authority Bulk Fuel Ugrade Job No.: 04-740 Client: Hankal Cant_ Code: API 1104 Surface Condition: Clean Direct View: XXX Procedure: AIX-VT-1 Special Illumination: None Indirect View: Weld Location and Identification Sketch Welders ID: Neat Cabiness Date Weld Identification Area Interpretation Remarks Accept Reject 8/20/2006 Production Welds 4" Lines Bridge cossiag Welds Gas Line W27 100% Neat RooUHotpass, Fill and Cap We, the undersigned cerlsay that the statements in ibis record are correct and that the welds were prepared and tested in accordance with the following Code: API 1104 Inspector: Sean Kelly `,%" Contractor/Client: Nankai Construction Test Date: 8/20/2006Authorized by: ALASKA INDUSTRIAL X-RAY 4047 KINGSTON DRIVE JOB NO. 04-470 ANCHORAGE, AK 98504 (907) 344-4061 FAX (907) 349-3875 DATE 8/20/2006 CUSTOMER Hankai Contruction LOCATION Unalaklet# AK PAGE 1 OF 1 PROJECT AK Energy Auth Fuel Upgrade CODE API 1104 Contract No. VISUAL WELD INSPECTION REPORT Neal Cabiness Procedure Variable Applicable Provision Comments Compliance Welding Procedure No. 5.3 Hankal 2 OK Process 5.3.2.1 SMAW OK Pipe Material 5.3.2.2 ASTM A53 OK Pipe Diameter 5.3.2.3 2 7/8" and over OK Pipe Wall Thickness 5.32.3 3/16" to .864" OK Joint Bevel 5.3.2.4 60 Degrees OK Face 5.3.2.4 1/16" OK Opening 5.3.2.4 1116" + 1/32" OK Filler Metal 5.3.2.5 SFA5.1 OK Electrical Current 5.3.2.6 D.C. OK Voltage 5.3.2.6 24.30 V OK Amperage 5.3.2.6 90-170 OK Polarity 5.3.2.6 Rev. OK Electrode Size 5.3.2.6 1/8" OK I Alon 5.3.2.9 Downward OK Time Lapse 5.3.2.10 2 to 12 Min OK Line Up Clamp 5.3.2.11 Yes OK Cleaning 5.3.2.12 Power Brush OK Preheat 5.3.2.13 100 F Min OK Welder Qualification 6.0 Design Allingment 7.0 Line Up Clamp Removal 7.3 Yes OK Bevel 7.4 60 Degrees OK Weather 7.5 Clear Clear Clearance 7.6 16 " min OK Filler & Finish Beads 7.8.2 Power Brush OK Welder Identification 7.10 Yes OK Visual Inspection 9.7 Undercut 9.7.2 None OK Surface Porosity 9.3.93 None OK Reinforcement 7.8.2 1116" / 118" OK Cracking 9.3.10 none OK Radiography Procedure 11.1.2.2 N/A NIA Penetrameter 11.1.5 Film Identification 11.1.8 Radiographers 11.1.7 Storage 11.1.19 Density 11.1.10 Radiation 11.1.13 Prepared By: Sean Kelly" Alaska industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99604 907-344-4061 Nondestrue ve Testing Report Visual Inspection Report Project: Alaska Energy Authority Bulk Fuel Upgrade UnaiakIeet AID Job No.: 04-740 Client: Hankal Construction Code: API1104 Procedure: AIX-I Weld Location and Identification Sketch Weld Identification I Area 8/21/2006 InLis morning Neal cut off 4 each test caps after yesterdays tests_ After colcplebon of that job he helped prepare for the road eiosmre_ when the trench was dug out the crew layed the pipe in place for the bridge crossing and ftlled m tine trencb and got the road back mto service_ There was no welding that We the undersigned. certiiv that the statements in this record are correct and that the welds Test Bate_ 8121 /2006 Contractor/Client: Hankal Construction Authorized by: Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Visual Inspection Report Project: AK Energy Authority Bulk Fuel bgrade Job No.: 04-740 Client: I4ankal Const Code: API1104 Procedure: AIX-VT-1 Welders ID: Neal Cabiness Surface Condition: Clean Direct View: XXX Special HImnination: None Indirect View: Weld Location and Identification Sketch Date Weld Identification Area Interpretation Remarks Accept Reject 8/21/2006 Production welds 4" Lines Bridge crossing Welds No welding done We. the mdemigned_ CP_rhfV thgt thP. Onti-mi- ftc in this rar A o ,-..,-1 ­t +1,-. +1,- �...7.7._ were prepared and tested in accordance with the following Code: API 1104 Inspector Sears Kelly Contractor/Client: Hankal Construction Test Date: 8/2112006 Authorized by: Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Deport Vismd Inspection deport Project: AK Energy Authority Bulk Fuel Ugrade Job No.: 04-740 Client: Hankal Const. Code: Procedure: Welders ID: API 1104 AIX-VT-3 Neal ('ahmPac Surfaee Condition: Clem Direct View: XXX Special Illumination: None Indirect View: Date Weld Identification Area Interpretation Remarks Accept Reject 812212006 Production Welds 4" Lines Fuel OR W27A 100% x Neal-root/hotpass fill and cap W2713 100°ro x deal- roolfimxz acsfill and cap W27C 1000% x Neal-root/hotpace �11 and rap W27D 100% x Neal- rocthotpass,fiil and cap Gas Line W25C 1tXD'�o x Neat-rooOwtpassfiii and cap W25D 1000/6 x Neal 3oWho4pass 0 and cV m mu-s samfu are conea ana that the wetas Were Dared and tested in acconlance with the. -fnllnuvina d nT t I AA Inspector: Sean Kelly Contractor/Client: Hankal Construction Test Date_ 8/22/2006 _ Authorized by: Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestruedve Vesting Report visual Inspection Report Project: Alaska Energy Authority Bulk Fuel Upgrade Unalakieet, AK Job No.: 04-740 Client: Hankal Construction Code: API1104 Procedure: ADC-1 Weld I.oeation and Identification Stretch Date I Weld Remarks W ILZ11 O This morning weal started off prepping Siting for the fitting ofthe pipe in the ditch_ He an down a 45 degree elbow and made two 20 degree Somgs. After the Siting were prepped he welded them onto smaller spools and then oho the pipelines for the gas and fuel oil lines All welds were visually inspected during St -up and throughout the welding process with no problems noted The weather was raining so he used a tarp tocover himself and the welds. We. the undersigned, certify that the statements in this record are correct and that the welds Contractor/Client: Test Date: 8/22/2006 — - Authorized by: Hankal Construction ALASKA INDUSTRIAL X-RAY 4047 KINGSTON DRIVE ANCHORAGE, AK 99504 (907) 344-4061 FAX (907) 349-3875 ,JOB NO. 04-470 DATE 8/22/2006 CUSTOMER Hankal Contruction LOCATION Unalaklett AK PAGE 1 OF 1 PROJECT AK Energy Auth Fuel Upgrade CODE API 1104 Contract No. VISUAL WELD INSPECTION REPORT Neal Cabiness Procedure Variable Applicable Provision Comments Compliance No. Process Pipe Material Pipe Diameter Pipe Wall Thickness .point Bevel Face Opening Filler Metal Electrical Current Voltage Amperage Polarity Electrode Size fiction __.ie Lapse Line Up Clamp Cleaning Preheat Welder Qualification Design Allingment Line Up Clamp Removal Bevel Weather Clearance Filler & Finish Beads Welder Identification Visual Inspection Undercut Surface Porosity Reinforcement Cracking Radiography Procedure Penetrameter Film Identification Radiographers Storage Density Radiation 5.3 5.3.2.1 5.3.2.2 5.3.2.3 5.3.2.3 5.3.2.4 5.3.2.4 5.3.2.4 5.3.2.5 SMAW ASTM A53 2 7/8" and over 3/16" to .864" 60 Degrees 1116" 1116" + 1/32" SFA5.1 5.3.2-6 - D.C. 5.3.2.6 24-30 V 5.3.2.6 90-170 5.3.2.6 Rev. 5.3.2.6 118" 5.3.2.9 Downward 5.3.2.10 2to12Min 5.3.2.11 Yes 5.3.2.12 Power Brush 5.3.2.13 100 F Min 6.0 7.0 7.3 Yes 7.4 60 Degrees 7.5 rain 7.6 16 " min 7-8.2 Power Brush 7.10 Yes 9.7 9.7.2 None 9.3.93 None 7.8.2 1/16" / 1/8" 9.3.10 none 11.1.2.2 NIA 11.1.5 11.1.8 -- 11.1.7 11.1.19 11-1.10 11.1.13 OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK Tarp OK OK OK OK OK OK OK OK N/A Prepared By_ Sean Kelly Alaska industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 _Nondestructive Testing Report Visual Inspection Report Project: AK Enemy Authority Bulk Fuel Ugrade Join No.: 04-740 Client: Hankal Cont. Code: Procedure: API 1104 AIX-SIT-1 Welders 113: Neal Cabiness Surface Condition: Clean Direct View: XXX Special Illumination: None Indirect View: Date Weld Identification Area Interpretation Remarks Accept Reject 812312006 Production Welds 4" Lmes i Gas Line W25A 100% x Neal-rooi/hotpass fill and cap W25B 1000/0 x Neal-—Vhntrr+a_ec fill and cap W 16 100% x Neal- root/hotpass fill and rap Fuel oil wig 1000/0 Neal-rowhotpass ffl and cap Neal -root/hotpassfil] and cap We the undersigned, ceatifv that the statements in this record are correct and that the welds were vrevared and tested in accordance with the following; Code: API 1104 Inspector- ScanKelly -�'�.---- .._.. ContractorlClient: Nankai Construction Test Date: 8/23/2006 Authorized by: Alaska Industrial X-ray Inc. 4947 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Visutallnspection Report Project: Alaska Energy Authori Bulk Fuel Upgrade Unalaklect, AK Job No.: 04-740 Client: Hankal Constructions Code: API1104 Procedure: AIX-1 Weld Location and identification Sketch 8/23/2UU6 INeal this moming welded on the gas fine welding out W25)B and then putting that spool into place to weldout W25A After lunch he welded out the two remaining welds oh the fuel oil Wl Sand W 16 on the gas line. All welds were visually inspected during tine welding process with no emblems note& We the undersigned, certify that the statements in this record are correct and that the welds were nrenared and tested in accordance with the following Code: API 1104 1 , Inspector: Sean Kell r`' Contractor/Client: Hankal Construction Test Date: 8/23/2006 Authorized by: ALASKA INDUSTRIAL X-RAY 4047 KINGSTON DRIVE ANCHORAGE, AK 99504 (907) 3444061 FAX (907) 349 ;875 .DOB NO. 04-470 DATE 8/23/2006 CUSTOMER Hankal Contruction LOCATION Unaiaklett AK PAGE 1 OF 1 PROJECT AK Energy Auth Fuel Upgrade CODE API 1104 Contract No. VISUAL WELD INSPECTION REPORT Neal Cabiness Procedure Variable Applicable Provision Comments Compliance Process Pipe Material Pipe Diameter Pipe Wall Thickness Joint Bevel Face Opening Filler Metal Electrical Current Voltage Amperage Polarity Electrode Size ction . _ ie Lapse Line Up Clamp Cleaning Preheat Welder Qualification Design Allingment Line Up Clamp Removal Bevel Weather Clearance Filler & Finish Beads Welder Identification Visual Inspection Undercut Surface Porosity Reinforcement Cracking Radiography Procedure Penetrameter Film Identification Radiographers Storage Density Radiation 5.3 5.3.2.1 5.3.2.2 5.3.2.3 5.3.2.3 5.3.2.4 5.3.2.4 5.3.2.4 5.3.2.5 5.3.2.6 5.3.2.6 5.3.2.6 5.3.2-6 5.3.2.6 5.3.2.9 5.3.2.10 5.3Z11 5.3.2.12 5.3.2.13 6.0 7.0 7.3 7.4 7.5 7.6 7.8.2 7.10 Hankal 2 SMAW ASTM A53 2 7/8" and over 3/16" to .864" 60 Degrees 1l16" 1116" +_ 1132" SFA5.1 D.C. 24-30 V 90-170 Rev. 1/8" Downward 2to12Min Yes Power Brush 100 F Min Yes 60 Degrees rain 16 " min Power Brush Yes 9.7 9.7.2 None 9.3.93 None 7.8.2 1116" / 1 /8" 9.3.10 none 11.1.2.2 N/A 11.1.5 11.1s 11.1.7 11.i.19 11.1.10 11.1.13 OK OK OK OK OK OK OK OK .OK OK OK OK OK OK OK OK OK OK OK OK Tarp OK OK OK OK OK OK OK OK N/A Prepared By. Sean Kell4_ Project: Client: Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Visual Inspection Report AK Energy Authority Balk Fuel Ugrade Job No.: 04-740 Hankal Coast. Code: API1104 Procedure: AIX VT-1 Surface Condition: Clean Direct View: XXX Special Illumination: Nome Indirect View: Weld Location and Identification Sketch 1Ar lA__ M. \T__1 Date - Weld Identification Area Interpretation Remarks Accept Reject 8/24/2006 Prodnotian Welds V Lines Gras Line W32 100% x 9. N-1-r—t/ho4ws fill and cap Fuel oil W35 1000/0 x Neal-rootbotpass fill and cap 3 We. the undersi ggrtlty ttlat the statements in lnls recora are correa anti Mat ale WuMi were prepared and tested in accordance with the following Cale: AN 1104 Inspector: Sean Kelly _ �Contractor/Client: Hankal Construction Test Date: 8/24/2006 Authorized by: Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Visual Inspection Report Project: Alaska Energy Authority Bulk Fuel Upgrade Unalakleet, Aid Job No.: 04-740 Client: Hankal Construction Code: API1104 Procedure: AIX-I Weld Location and Identification Sketch Identification Area 8/24/2006 JNeal this morning welded on tie gas line welding oul W32 and W35 on the fuel oil line. These welds are located under the bridge as you are exiting sown. Both welds were visually inspected during the welding process. Both welds were acceptable. After lunch neat was fabbing up a spool for the air test We. the undersicmed. cer & that the statements in this_record_ are correct and that the welds were pmared and tested in accordance with the following Code: API 1104 Inspector: Sean Kelly Contractor/Client: Hankai Construction Test Data: 8/24/2006 Authorized by: AL.ASKA INDUSTRIAL X-RAY ",047 KINGSTON DRIVE - ANCHORAGE, AK 99504 (907) 344-4061 FAX (907) 349-3876 JOB NO. 04-470 DATE 3/2412006 CUSTOMER Hankal Contruction LOCATION Unalakiett AK PAGE 1 OF 1 PROJECT AK Energy Auth Fuel Upgrade CODE API 1104 Contract No. VISUAL WELD INSPECTION REPORT Neal Cabiness Procedure Variable Applicable Provision Comments Compliance Welding Procedure No. 5.3 rid[ 1ACH 14 � Process 5.3.2.1 SMAW OK Pipe Material 5.3.2.2 ASTM A53 - OK Pipe Diameter 5.3.2.3 2 7/8" and over OK Pipe Wall Thickness 5.3.2.3 3/16" to .864" OK Joint Bevel 5.3.2.4 60 Degrees OK Face 5.3.2.4 1 /16" OK Opening 5.3.2.4 1/16" + 1132" OK Filler Metal 5.3.2-5 SFA5.1 OK Electrical Current 5.3.2.6 D.C. OK Voltage 5.3.2.6 24-30 V OK Amperage 5.32.6 90-170 OK Polarity 5.3.2.6 Rev. OK T strode Size 5.3.2.6 1 /8" OK L 5.3.2.9 Downward OK _..,xtion Time Lapse 5.3.2.10 2 to 12 Min OK Line Up Clamp 5.3.2.11 Yes OK Cleaning 5.3.2.12 Power Brush OK Preheat 5.3.2.13 100 F Min OK Welder Qualification 6.0 Design Allingment 7.0 Line Up Clamp Removal 7.3 Yes OK Bevel 7.4 60 Degrees OK Weather 7.5 Cloudy OK Clearance 7.6 16 " min OK Filler & Finish Beads 7.8.2 Power Brush OK Welder Identification 7.10 Yes OK Visual Inspection 9.7 Undercut 9.7.2 None OK Surface Porosity 9.3.93 None OK Reinforcement 7.8.2 1116" / 119, OK Cracking 9.3.10 none OK Radiography Procedure 11.1.2.2 N/A N/A Penetrameter 11.1.5 Film Identification 11.1.8 Radiographers 11.1.7 Storage 11.1.19 Density 11.1.10 Radiation 11.1.13 Prepared By: Sean Kelly Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Tes7ing Report Visual Inspection Report Project: AK Energy Authority Bulk Fuel Ugrade Job No.: 04-740 Client: I-Iankal Const. Code: API 1104 Surface Condition: Clean Direct View: XXX Procedure: AIX VT-1 Special Illumination: . None Indirect View: Date Weld Identification Tank Farm Area Interpretation Remarks Accept Reject 812512006 Production Welds 4" Lines Gas Ume W101 1000/0 x Neal-noot/hotpassfiH and cap W103 IW/o x NeW .-roct%oipassfill and cap Fuel oil W 101 100% x Neal-root/hotpass fill and cap W104 100% x Neal-rooi/hotpasr __fill and cap - - - ....,i r.. OMLwa c.utz lu iallD isi im dic t. rit.'t:t ana umi Lne weias were Prepared arid tested in accordance with the fallowing Code: API 1104 .,r Inspector: Sean Kelly J = � ContractortClient: Hankal Construction Test Date: 8125/2006 Authorized bv- Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Vesting Report T isual Inspection Report Project: Alaska Energy Authority Bulk Fuel Upgrade Unaiakleet, AK Job No.: 04-740 Client: Hankal Construction Code: API1104 Procedure: AIX-1 Weld Location and Identification Sketch Date I Weld Identification I Area I Interpretation I Remarks 8/25/2006 This morning heal started Tabbing up spool at the tank fam, tothe road that leads to tows He had to weld four welds 2 each foe the gas line and the fuel oil line. The gas line welds are numbered W 101 and W 103 with the fuel oil line numbed W 101 and W 104_ All welds were visually inspetded daring the welding proem with no problems noted. We. the undersigned certify that the statements in this record are correct and that the welds were pMwed and tested in accordance with the following Code: API 1104 Inspector: Sean Kell_.. a. "" Contractor/Client: Hankal Construction Test Date: 8/25/2006 Authorized by: ALASKA INDUSTRIAL X-RAY 4047 KINGSTON DRIVE ANCHORAGE, AK 99504 (907) 344-4061 FAX (907) 349-3875 JOB NO. 04-470 DATE 8/25/2006 CUSTOMER Hankal Contruction LOCATION Unalaklett AK PAGE 1 OF 1 PROJECT AK Energy Auth Fuel Upgrade CODE API 1104 Contract No. VISUAL WELD INSPECTION REPORT Neal Cabiness Procedure Variable Applicable Provision cn.. same _ Process Pipe Material Pipe Diameter Pipe Wall Thickness Joint Bevel Face Opening Filler Metal Electrical Current Voltage Amperage Polarity Electrode Size ?ction _ie Lapse Line Up Clamp Cleaning Preheat Welder Qualification Design Aflingment Line Up Clamp Removal Bevel Weather Clearance Filler & Finish Beads Welder Identification Visual Inspection Undercut Surface Porosity Reinforcement Cracking Radiography Procedure Penetrameter Film Identification Radiographers Storage Density Radiation 5.3 5.3.2.1 5.3.2.2 5.3.2.3 5.3.2.3 5.3.2.4 5.3.2.4 5.3.2.4 5.3.2.5 5.3.2.6 5.3.2.6 5.32.6 5.3.2.6 5.3.2.6 5.3.2.9 5.3.2.10 5.3.2.11 5.3.2.12 5.3.2.13 6.0 7.0 7.3 7.4 7.5 7.6 7.8.2 7.10 9.7 9.7.2 9.3.93 7.8.2 9.3.10 ASTM A53 2 7/8" and over 3/16" to .864" 60 Degrees 1/16" 1/16" + 1/32' SFA5.1 D.C. 24-30 V 90-170 Rev. 118.1 Downward 2to12Min Yes Power Brush 100 F Min Yes 60 Degrees Sunny 16" min Power Brush Yes None None 1/16" / 1/8" none N/A OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK N/A Prepared By: Sean Kelly `'_ Alaska Industrial X-ray Inc. 4047 Kingston ©rive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Hisual Inspection Report Project: AK Energy Authority Bulk Fuel Ugrade Job No.: 04-740 Client: Hankal Const. Code: API1104 Procedure: AIX-VT-I welaers lu: Nenl UnhinPcc Surface Condition: Clean Direct View: XXX Special Illumination: None Indirect View: Date Weld Identification Tank Farm Area Interpretation Remarks Accept Reject 8/26/2006 ftoduction welds 4" Ianes Gas lane W95 100% x Neal-mot/hgtpass fjl and cap W96 1 Qti'fo I x Neal-rooUhotpass M and cap W97 100% x Neal f1 and cap W99 1000/0 x Neal _root/hotpass M and cap Fuet oil Line W95 1000/0 x Neal-roodhotpass fill and cap W96 100% x Neal-rootlho4ws M1 and cap W97 100% x Neal-root/hotpass fil} and cap W99 1000% x Neal-root(hotpass fill and cap S17e ts.,. —aeiiucuW in uus 1C,Y;um arm Correct ana mat file welds WCr4CprKpared and tested in accordance with the Code: API 1104 �i Inspector: Sean YCIW c J CantractorfClient: Hankai Construction Test Date: 8/26/2006 Authorized by: Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99604 907-344-4061 Nondestructive Testing Report Visual Inspection Report Project: Alaska Energy Authority Bulk Fuel Upgrade Unalakleet, AK Job No.: 04-740 Client: Hankal Construction Code: API1104 Procedure: AIX-1 Weld Location and Identification Sketch Remarks 61Lb/LUU0 I Today neat was welding spools at the tank farm to the road leading totown. He welded up 4 welds to the fuel oil line W99,W97,W96,W95 and 4 each to the gas line W99,W97,W96,W95. All welds were visually inspected before and during the welding process The fitup was OK on all welds with no problems noted The weather today was suety with a sliRbt breeze We, the undersimed, certify that the statements in this reord are correct and that the welds were prepared and tested in accordance with the following Code: API 1104 Inspector: Sean Kelly Contractor/Client: Hankal Construction Test Date: 8/26/2006 Authorized by: ALASKA INDUSTRIAL X-RAY 4047 KINGSTON DRIVE JOB NO. 04-470 ANCHORAGE, AK 99504 (907) 344-4061 FAX (907) 349-3875 DATE 8/26/2006 CUSTOMER Hankal Contruction LOCATION Unalaklett AK PAGE 1 OF 1 PROJECT AK Energy Auth Fuel Upgrade CODE API 1104 Contract No. VISUAL WELD INSPECTION REPORT Neal Cabiness Procedure Variable Applicable Provision Comments Compliance Welding Procedure No. 5.3 Hankal 2 _ OK Process 5.3.2.1 SMAW OK Pipe Material 5.3.2.2 ASTM A53 OK Pipe Diameter 5.3.2.3 2 7/8" and over OK Pipe Wall Thickness 5.3.2.3 3116' to .864" OK Joint Bevel 5.3.2.4 60 Degrees OK Face 5.3.2.4 1/16" OK Opening 5.3.2.4 1/16" + 1/32" OK Filler Metal 5.3.25 SFA5.1 OK Electrical Current 5.3.2.6 D.C. OK Voltage 5.3.2.6 24-30 V OK Amperage 5.3.2.6 90-170 OK Polarity 5.3.2.6 Rev- OK Electrode Size 5.3.2.6 1/8" OK 'Ction 5.3.2.9 Downward OK I line Lapse 5.3.2.10 2 to 12 Min OK Lane Up Clamp 5.3.2.11 Yes OK Cleaning 5.3.212 Power Brush OK Preheat 5.3.2.13 100 F Min OK Welder Qualification 6.0 Design Allingment 7.0 Line Up Clamp Removal 7.3 Yes OK Bevel 7.4 60 Degrees OK Weather 7.5 Sunny OK Clearance 7.6 16 " min OK Filler & Finish Beads 7.8.2 Power Brush OK Welder Identification 7.10 Yes OK Visual Inspection 9.7 Undercut 9.7.2 None OK Surface Porosity 9.3.93 None OK Reinforcement 7.8.2 1/16" / 1/8" OK Cracking 9.3.10 none OK Radiography Procedure 11.1.2.2 N/A N/A Penetrameter 11.1.5 Film Identification 11.1.8 Radiographers 11.1.7 Storage 11.1.19 Density 11.1.10 Radiation 11.1.13 Prepared By. Sean Kelly - Project: Client: Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestmctive Testing Report Visual Inspection Report AK Energy Authority Hulk Fuel Ugrade Job No.: 04-740 Hankal Const Code: API1104 Procedure: AIX-VT-1 W id iD• Neap CabinesS Surface Condition: Clean Direct View: XXX Special Illumination: None Indirect View: e ers Date Weld Identification Farm Area InterpretationRejectTank Apt RejectRemarks 8/27/2006 Production Welds 4" Ianes Gas Line W100 100% x Neal -tnovhotpass fill and cap W98 I00"/o x Neal 400t&otpass M and cap Fuel Oil Line W I00 100% x Neat-motlhoVws fill and cap W98 100% x Neal-rootliaotpass,fin and cap We the undersiened certiiv that the statements m tt11s record are correct ana um Ire weius were prepared and tested m accordance with the fo110wine Code: API 1104 Inspector: Sean Kelly _ Contractor/Client: Hankal Construction Test Date: 8/2712006 Authorized by: Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Visual Inspection Report Project: Alaska Energy Authority Bulk Fuel Upgrade Unalakleet, AK Job No.: 04-740 Client: Hankal Construction Code: API1104 Procedure: AIX-1 ®Veld Location and Identi5cation Sketch Weld Remarks 8/27/2006 Today neat was welding spools at the tank fumto the mad leading to town _Ike welded up 2 welds to the fuel oil line W 100, W98 and 2 each to the gas line W l00, W98. All welds were visually mspeded before and during the welding prates$. The fitup was OK on all welds with no problems noted The weather todav was clondv _ We the undersigned certify that the statements in this record are correct and that the welds were prepared and tested in accordance with the following Code: API 1104 Inspector: Sean Kellv - ° - Contractor/Client: Hankal Construction Test Date: 3/27/2006 Authorized by: ALASKA INDUSTRIAL X-RAY 4047 KINGSTON DRIVE JOB NO. 04-470 ANCHORAGE, AK 99504 (907) 344-4061 FAX (907) 349-3875 DATE 8/2712006 CUSTOMER Hankal Contruction LOCATION Unalakleet AK PAGE 1 OF 1 PROJECT AK Energy Auth Fuel Upgrade CODE API 1104 Contract No. VISUAL WELD INSPECTION REPORT Neal Cabiness Procedure Variable Applicable Provision Comments Compliance Welding Procedure No. 5.3 Hankal 2 OK Process 5.3.2.1 SMAW OK Pipe Material 5.3.2.2 ASTM A53 OK Pipe Diameter 5.3.2.3 2 7/8" and fiver OK Pipe Wall Thickness 5.3.2.3 3/16" to .864" OK Joint Bevel 5.3.2.4 60 Degrees OK Face 5.3.2.4 111 T OK Opening 5.3.2.4 1/16" + 1/32" OK Filler Metal 5.32.5 SFA5.1 OK Electrical Current 5.32.6 D.C. OK Voltage 5.32.6 24-30 V OK Amperage 5.3.2.6 90-170 OK Polarity 5.3.2.6 Rev. OK Electrode Size 5.3.2.6 1/8" OK action 5.3.2.9 Downward 'OK rime Lapse 5.3.2.10 2 to 12 Min OK Line Up Clamp 5.3.2.11 Yes OK Cleaning 5.3.2.12 Power Brush OK Preheat 5.3.2.13 100 F Min OK Welder Qualification 6.0 Design Allingment 7.0 Line Up Clamp Removal 7.3 Yes OK Bevel 7.4 60 Degrees OK Weather 7.5 cloudy OK Clearance 7.6 16 " min OK Filler & Finish Beads 7.8.2 Power Brush OK Welder Identification 7.10 Yes OK Visual Inspection 9.7 Undercut 9.7.2 None OK Surface Porosity 9.3.93 None OK Reinforcement 7.82 1116" / 1/8" OK Cracking 9.3.10 none OK Radiography Procedure 11.1.2.2 N/A NIA Penetrameter 11.1.5 Film Identification 11.1.8 Radiographers 11.1.7 Storage 11.1.19 Density 11.1.10 Radiation 11.1.13 Prepared By: Sean Kelly , Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99604 907-344-4061 Nondestructive Testing Report Visuallnspection Report Project: Ali Energy Authority Bulk Fuel Ugrade Client: Hankal Conk. Code: API11O4 Procedure: AiX-VT-1 1Nc4lnr#-. In- AT-1 f �hin,,ce Surface Condition: Clean Special Illumination: None Job No.: 04- l40 Direct View: XXX Indirect View: Date Weld Identification Tank Farm Area Interpretation Remarks Accept Reject 8/28/2006 Production Weft 4" Lmes Gas Line W90 100a/o x Neal 400t/ho4ass fiii and cap W91 100% x Neal 4owhatpass;G i and cap W93 100a/a x Neal gooUhoipass fill and cap W94 100a/a x Neal-rootlhotpassl and cap lhel Oil Line W90 100°/a x Neat mot/hotpass fill and qp W91 100a/0 x Ideal-rowbotpass fill and cap W93 100a/0 x Neal-rootlhotpass fill and cap W94 1001% x Neat -roc otpassf iII and cap Inspector. Sean Kelly i _ C4mtracdor/Client: Hankal Construction Test Date: 8/28/2006 L Authorized by: Project: Client: Alaska industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Vesting Report Visual Inspection Report Alaska Energy Authority Bulk Fuel Upgrade Unalakleet, AK Job No.: 04-740 Hankal Construction Code; API1104 Procedure: AIX-1 Weld Location and Identifiication Sketch Date I Weld Identification I Area 8/28/2006 Today neal stand on the road f um the tank farm to the bridge. He welded two double joints 1 each gas and fuel oil. Both welds are numbered W93. He then bad the spool dropped into place anti welded than to the piece in the ditch to the fain_ Those welds were W94. Those spools were then tested with air at 135psi for i hour and the tests were successful. After lunch He continued to jump from gas line to fuel oil line makin¢ welds He welded out 4 each welds for gas and fnel oiL We the undersigned. certifv that the statements m this record are correct and that the welds Inspector: Sean Kelly Test Date. 8128/2006 Contractor/Client: Hankal Construction Authorized by: ALASKA INDUSTRIAL X-RAY 4047 KINGSTON DRIVE JOB NO. 04-470 ANCHORAGE, AK 99504 (907) 344-4061 FAX (907) 349-3875 DATE 8/28/2006 CUSTOMER Hankal Contruction LOCATION Unalakleet AK PAGE 1 OF 1 PROJECT AK Energy Auth Fuel Upgrade CODE API 1104 Contract No. VISUAL WELD INSPECTION REPORT Neal Cabiness Procedure Variable Applicable Provision Comments Compliance Welding Procedure No. 5.3 Hankal 2 OK Process 5.3.2.1 SMAW OK Pipe Material 5.3.2.2 ASTM A53 OK Pipe Diameter 5.3.2.3 2 7/8" and over OK Pipe Wall Thickness 5.3.2.3 3/16" to .864" OK Joint Bevel 5.3.2.4 60 Degrees OK Face 5.3:2.4 1/16" OK Opening 5.3.2.4 1/16" + 1/32" OK Filler Metal 5.3.2.5 SFA5.1 OK Electrical Current 5.3.2.6 D.C. OK Voltage 5.3.2.6 24-30 V OK Amperage 5.3.2.6 90-170 OK Polarity 5.3.2.6 Rev. OK '- ctrode Size 5.3.2.6 1/8" OK _ action 5.3.2.9 Downward OK Time Lapse 5.3.2.10 2 to 12 Min OK Line Up Clamp 5.3.2.11 Yes OK Cleaning 5.3.2.12 Power Brush OK Preheat 5.3.2.13 100 F Min OK Welder Qualification 6.0 Design AlGngment 7.0 Line Up Clamp Removal 7.3 Yes OK Bevel 7.4 60 Degrees OK Weather 7.5 Fog OK Clearance 7.6 16 " min OK Filler & Finish Beads 7.8.2 Power Brush OK Welder Identification 7.10 Yes OK Visual Inspection 9.7 Undercut 9.7.2 None OK Surface Porosity 9.3.93 None OK Reinforcement 7.8.2 1116, / 118" OK Cracking 9.3.1 o none OK Radiography Procedure 11.12.2 N/A N/A Penetrameter 11.1.5 Film Identification 11.1.8 Radiographers 11.1.7 Storage 11.1.19 Density 11.1.10 Radiation 11.1.13 Prepared By. Sean Kelly`�.�� Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Visual Inspection Report Project: AK 1:nergy Authority Bulk Fuel Ugrade Job No.: 04-740 Client: Hankal Const. Code: Procedure: API 1104 AIX-VT-1 Welders ID: Neal Cabiness Surface Condition: Clean direct View: XXX Special Blurnination: Done Indirect View: Date Weld Identification Tank Farm Area Interpretation Accept lZe� Remarks 3/2912006 FFroducam Weeds z Gas 1-ine W87 100% a AT�1-aonUhoYpassfill and cap W8s 100% x :Neal-raoUhoV..,5R —d cap W89 € 16€10% s IN.1 -raafl� ad cog W92 10(3°fe x Neal 4eoVhovawM and cap Fhet OU Line W87 1040/0 � -nd-T Wn 1w/D X �Nte'd-rootiEtagxis lrcai 3.t/h.Va.,�M dOd eag W89 � 100% x vfroi .,.,l,St and cap W92 g� TWXY x LN— —sMa dCap i Y We, the under ig_ned., cerffy that the sigements m this record are correct and IhW the welds were repared and tested w acmr► mx vaft the Mowing Cock: AM 1104 Inspector: Sean Y—eiy r ✓ contractulClient Hankal Construction Test Date. 81291200_1 — �~ f Authwized by - Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Visual Inspection Deport Project: Alaska Energy Authority Bulk Fuel Upgrade Hnalakleet, AK Job No.: 04-740 Client: Hankal Constmction Code: API1104 Procedure: AIX-1 Weld Location and Identification Sketch Date I Weld Identification I Area 8/29/2006 IThe day started witb neat welding m the pipeline from the tmk fame to the bridge. His RrA welds were W89 on the fuel and gas lk=. The fits was good on bath welds vM no pmb€em durmgthe wehfmg procem He then weldedbreemme welds each on the fuel and gas lines. These welds are numbered W3&WS7 am€ W92. AI€ welds were vsuai€y n3sP tnm z during the weidmg and the We. the undersigned certifv that the statements in this recmrd are correct and that the welds were prepared and tested in accordance with the thllowing Code- API 1104 Inspector_ Sean Kelly _ %niraror/Client: l-iar€kai Construction Test Date: 8/29/2006 Authorized by_ ALASKA INDUSTRIAL X-RAY 4047 KINGSTON DRIVE JOB NO. 04-470 ANCHORAGE, AK 99504 (907) 344-4061 FAX (907) 349-3875 DATE 8/29/2006 CUSTOMER Hankal Contruction LOCATION Unaiakleet AK PAGE 1 OF 1 PROJECT AK Energy Auth Fuel Upgrade CODE API 1104 Contract No. VISUAL WELD INSPECTION REPORT Neal Cabiness Procedure Variable Applicable Provision Comments Compliance Welding Procedure No. 5.3 Hankal 2 OK Process 5.3.2.1 SMAW OK Pape Material 5.3.2.2 ASTM A53 OK Pipe Diameter 5.3.2.3 2 718" and over OK Pipe Wall Thickness 5.3.2.3 3/16" to .864" OK Joint Bevel 5-3.2.4 60 Degrees OK Face 5.3.2.4 1 /16" OK Opening 5.3.2.4 1/16" + 1/32" OK Filler Metal 5.3.2.5 SFA5.1 OK Electrical Current 5.3.2.6 D.C. OK Voltage 5.3.2.6 24-30 V OK Amperage 5.3.2.6 90-170 OK Polarity 5.3.2.6 Rev. OK Re�ctrode Size 5.3.2.6 1/8" OK action 5.3.2.9 Downward OK Time Lapse 5.3.2.10 2 to 12 Min OK Line Up Clamp 5.3.2.11 Yes OK Cleaning 5.3.2.12 Power Brush OK Preheat 5.3.2.13 100 F Min OK Welder Qualification 6.0 Design Allingment 7.0 Line Up Clamp Removal 7.3 Yes OK Bevel 7.4 60 Degrees OK Weather 7.5 Fog/Clouds OK Clearance 7.6 16 "min OK Faller & Finish Beads 7.8.2 Power Brush OK Welder Identification 7.10 Yes OK Visual Inspection 9.7 Undercut 9.7.2 None OK Surface Porosity 9.3.93 None OK Reinforcement 7.82 1/16" / 1/8" OK Cracking 9.3.10 none OK Radiography Procedure 11.1.2.2 NIA N/A Penetrameter 11.1.5 Film Identification 11.1.8 Radiographers 11.1.7 Storage 11.1.19 Density 11.1,10 Radiation 11.1.13 ' Prepared By. Sean Kelly ' s Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report risuallnspecdota Report Project: AK Energy Authority Bulk Fuel Ugrade Job No.: 04-740 Client: Hankal Const, Code: API 1104 Surface Condition: Clean Direct View: XXX Procedure: AIX-VT-1 Special Illumination: None Indirect View: Weld Location and Identification Sketch Welders ID_ NPaI Cnhini cc Date Weld Identification Tank Farm Area Interpretation Remarks Accept Reject 8/30/2006 Production Welds 4" Lines Gas Line W86 100% x Neal-root/hotpass,flll and cap W85 100% x Neal-root/hotpass fill and cap W84 100% x Neal-root/hotpassfill and cap W83 100% x Neal-roobhotpass fill and cap Fuel Oil Line W86 100% x Neid-rooUhotpass fill and cap W 85 100% x Neal-rootlhotpassfill and cap W84 100% x Neal-rooVhotpass,fill and cap W83 100% x Neal-root/hotpass,fill and cap wu Correct ana mat me welds were nrenared and tested in accordance with the following Code: API 1104 Inspector: Sean Kelly Contractor/Client: Hallkai Construction Test Date: 8/30/2006 Authorized by: Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99304 907-344-4061 Nondestructive Testing Report Visual Inspection Report Project: Alaska Energy Authority Bulk Fuel Upgrade Unalakieet, AK Job No.: 04-740 Client: Hankal Construction Code: API1104 Procedure: AIX-1 Weld Location and Identification Sketch Date Weld Identification Area interpretation Remarks Accept I Reject 8/30/2006 The day started with neat welding on the pipeline from the tank farm to the bridge. His ,first welds were W 86 on the fuel and gas lines. The fitup was good on both welds with no problem during the welding process. He then welded three more welds each on the fuel and gas lines. These welds are numbered W 5, W 84 and W83. All welds were visually inspected prior and during the welding process and the welds were acceptable. After completion of welds an air test was performed on the line. The pressure was 135 psi for 1 hour. The test was successful and the line can be dropped into the ditch and he buried We. the undersigned, certify that the statements in this record are correct and that the welds Sean Contractor/Client: Hankal Construction Test Date: 8/30/2006 Authorized by: ALASKA INDUSTRIAL X-RAY 4047 KINGSTON DRIVE JOB NO. 04-470 ANCHORAGE, AK 99504 (907) 344-4061 FAX (907) 349-3875 DATE 8/30/2006 CUSTOMER Hankal Contruction LOCATION Unalakleet AK PAGE 1 OF 1 PROJECT AK Energy Auth Fuel Upgrade CODE API 1104 Contract No. VISUAL WELD INSPECTION REPORT Neal Cabiness Procedure Variable Applicable Provision Comments Compliance Welding Procedure No. 5.3 Hankal 2 OK Process 5.3.2.1 SMAW OK Pipe Material 5.3.2.2 ASTM A53 OK Pipe Diameter 5.3.2.3 2 7/8" and over OK Pipe Wall Thickness 5.3.2.3 3/16" to .864" OK Joint Bevel 5.3.2.4 60 Degrees OK Face 5.3.2.4 1/16'1 OK Opening 5.3.2.4 1/16" + 1/32" OK Filler Metal 5.3.2.5 SFA5.1 OK Electrical Current 5.3.2.6 D.C. OK Voltage 5.3.2.6 24-30 V OK Amperage 5.3.2.6 90-170 OK Polarity 5.3.2.6 Rev. OK Elo-*rode Size 5.3.2.6 1/8" OK D, Jon 5.3.2.9 Downward OK Time Lapse 5.3.2.10 2 to 12 Min OK Line Up Clamp 5.3.2.11 Yes OK Cleaning 5.3.2.12 Power Brush _ OK Preheat 5.3.2.13 100 F Min OK Welder Qualification 6.0 Design Allingment 7.0 Line Up Clamp Removal 7.3 Yes OK Bevel 7.4 60 Degrees OK Weather 7.5 Cloudy/Rain Tent OK Clearance 7.6 16 " min OK Filler & Finish Beads 7.8.2 Power Brush OK Welder Identification 7.10 Yes OK Visual Inspection 9.7 _ Undercut 9.7.2 None OK Surface Porosity 9.3.93 None OK Reinforcement 7.8.2 1/16" / 1/8" OK Cracking 9.3.10 none OK ladiography Procedure 11.1.2.2 N/A N/A Penetrameter 11.1.5 Film Identification 11.1.8 Radiographers 11.1.7 Storage 11.1.19 Density 11.1.10 Radiation 11.1,13 Prepared By: Sean Kelly "- Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Visuallnspection Retort Project: AK Energy Authority Bulk Fuel Ugrade Job No.: 04-740 Client: Hankal Const. Code: Procedure: API 1104 AIX-VT-1 Welders ID: Neal Cabiness Surface Condition: Clean Direct View: XXX Special Illumination: None Indirect View: Weld Location and Identification Sketch Date Weld Identification Tank Farm Area Interpretation Remarks Accept Reject 8/31/2006 Production Welds 4" Lines Gas Line W81 100% x Neat-root/hotpass,fill and cap W82 I00% x Neal-ruuAotpass,Iill and cap Fuel Oil Line W81 100% x Neal -root/hotpass,fill and cap W92 10Me x Beal-rootlhotpass,fill and eap We the undersigned, certiiy that the statements in this record are correct and that the welds were prepared and tested in ac oordallcce with the following Code: API 1104 Inspector: Sean Kelly .*_. - Contractor/Client: Hankal Construction Test Date: 8/31/2006 Authorized by: Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report — Visual Inspection Resort Project: Alaska Energy Authority Bulk Fuel Upgrade Unalakleet, AK Job No.: 04-740 Client: Hankal Constriction Code: API1104 Procedure: AIX-1 Weld Location and Identification Sketch Date I Weld Identification I Area I Interpretation Remarks 8/31/2006 ITOday was very windy so neal used a wind break to weld out 2 each welds on the gas line and the fuel oil line. These welds are numbered W81 and W82. All four welds were visually inspected during the fit -up and welding process with not problems noted. We, the undersigned, certify that the statements in this record are correct and that the welds were prepared and tested m accordance with the following Code: API 1104 Inspector: Sean Kelly Contractor/Client: Hankal Construction Test Date: 8/31/2006 Authorized by: ALASKA INDUSTRIAL X-RAY "147 KINGSTON DRIVE JOB NO. 04-470 ANCHORAGE, AK 99504 (907) 344-4061 FAX (907) 349-3875 DATE 8/31/2006 CUSTOMER Hankal Contruction LOCATION Unalakleet AK PAGE 1 OF 1 PROJECT AK Energy Auth Fuel Upgrade CODE API 1104 Contract No. VISUAL WELD INSPECTION REPORT Neal Cabiness Procedure Variable Applicable Provision Comments s Compliance Welding Procedure No. 5.3 Hankal 2 OK Process 5.3.2.1 SMAW OK Pipe Material 5.3.2.2 ASTM A53 OK Pipe Diameter 5.3.2.3 2 7/8" and over OK Pipe Wall Thickness 5.3.2.3 3/16" to .864" OK Joint Bevel 5,3.2.4 60 Degrees OK Face 5.3.2.4 1116" OK Opening 5.3.2.4 1116" +_ 1/32" OK Filler Metal 5.3.2.5 SFA5.1 OK Electrical Current 5.3.2.E D.C. OK Voltage 5.3.2.6 24-30 V OK Amperage 5.3.2.6 90-170 OK Polarity 5.3.2.6 Rev. OK E' .rode Size 5.3.2.6 1/8" OK D►. _ 4tion 5.3.2.9 Downward OK Time Lapse 5.3.2.10 2 to 12 Min OK Line Up Clamp 5.3.2.11 YES OK Cleaning 5.3.2.12 Power Brush OK Preheat 5.3.2.13 100 F Min OK Welder Qualification 6.0 Design Allingment 7.0 Line Up Clamp Removal 7.3 Yes OK Bevel 7.4 60 Degrees OK Weather 7.5 SunnyAAfindy Wind Break OK Clearance 7.6 16 " min OK Filler & Finish Beads 7.8.2 Power Brush OK Welder Identification 7.10 Yes OK Visual Inspection 9.7 Undercut 9.7.2 None OK Surface Porosity 9.3.93 None OK Reinforcement 7.8.2 1/16" / 1/8" OK Cracking 9.3,10 none OK Radiography Procedure 11.1.2.2 N/A N/A Penetrameter 11.1.5 Film Identification 11.1.8 Radiographers 11.1.7 Storage 11.1.19 Density 11.1.10 Radiation 11.1.13 Prepared By: Sean Kelly HAlaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Visual Inspection Report Project: AK Energy Authority Bulk Fuel Ugrade Job No.: 04-740 Client: Hankal Const. Code: API1104 Procedure: AiX-VT-I Welders ID: Neal Cabiness Surface Condition: Clean Direct View: XXX Special Illumination: None Indirect View: Date Weld Identification Tank Farm Area Interpretation Remarks Accept Reject 911/2006 Production Welds 4' L fiics Gas Line W76 100% x Neal-root/hotpass,fill and cap W77 100% x Neal-root/hotpassfiill and cap W78 100% x Neal-root/hotpass fill and cap W79 100% x Neal-root/hotpass,fill and cap W80 100% x Neal-root/hotpass fill and cap Fuef Oil Line W 76 100% x Neal-root/holpasO and cap W77 100% x Neal-root/hotpassfiill and cap 478 100% x Neal-root/hotpass,fill and cap W79 100% x Neat-root4telpass,Sil and cap W 80 100% x Neal 4wt&o4ass Sll and cap We. the undersigned, certify that the statements in this record are correct and that the welds were oreoared and tested in accordance with the fellowine Code: API 1104 Inspector: Sean Kelly ContractorlClient: Hankal Construction Test Date: 9/112006 ,>�-- " Authorized by: Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Deport Visual Inspection Report Project: Alaska Energy Authority Bulk Fuel Upgrade Unalakleet, AK Job No.: 04-740 Client: Hankal Construction Code: AN 1104 Procedure: AIX-I Weld Location and Identification Sketch Date Weld Identifiication Area Interpretation Remarks Accept Reject 9/ 112006 Today neal is welding on both the fuel oil line and the gas line. He has 10 welds to make to get the air test done by the end ofthe day. His fist welds are W80 on both lines. His fit -up and rootpass was inspected and was acceptable and he continued to finish both welds. He then welded out another 4 more welds before lunch with no problems. After lunch the wind pickup and neat used the wind break to shelter him and the welds from the wind. He welded out 4 more welds 2 welds on the gas line and two on the fuel oil line. All welds were visully inspected and were acceptable. Neal then welded on the cap for the air test and both lines were then pressured up to 135 psi for 1 hour. The test was suucessful. Sean Contractor/Client: Test Date: 9/1 /2006 Authorized by: Hankal Construction ALASKA INDUSTRIAL X-RAY 4047 KINGSTON DRIVE ANCHORAGE, AK 99504 (907) 344-4061 FAX (907) 349-3875 CUSTOMER Hankal Contruction LOCATION Unaiakleet AK PROJECT AK Enerov Auth Fu, JOB NO. 04-470 DATE 9/1/2006 PAGE 1 OF CODE API 1104 Contract No. 1 VISUAL WELD INSPECTION REPORT Neal Cabiness Procedure Variable Applicable Provision Comments Compliance Welding Procedure No. Process Pipe Material Pipe Diameter Pipe Wall Thickness Joint Bevel Face Opening Filler Metal Electrical Current Voltage Amperage Polarity Eipctrode Size Mon Time Lapse Line Up Clamp Cleaning Preheat Welder Qualification 5.3 5.3.2.1 5.3.2.2 5.3.2.3 5.3.2.3 5.3.2.4 5.3.2.4 5.3.2.4 5.3.2.5 5:3.2.6 5.3.2.6 5.3.2.6 5.3.2.6 5.3.2.E 6-3.2.9 5.3.2.10 5.3.2.11 5.3.2.12 5.3.2.13 6.0 SMAW ASTM A53 2 7/8" and over 3/16" to .864" 60 Degrees 1/16" 1/16" + 1/32" SFA5.1 D.C. 24-30 V 90-170 Rev. 1/8" Downward 2to12Min Yes Power Brush 100 F Min Design Allingment 7.0 Line Up Clamp Removal 7.3 Yes Bevel 7.4 60 Degrees Weather 7.5 Sunny/Windy Clearance 7.6 16 " min Filler & Finish Beads 7.8.2 Power Brush Welder Identification 7.10 Yes Visual Inspection 9.7 Undercut 9.72 None Surface Porosity 9.3.93 None Reinforcement 7.8.2 1/16" / 118" Cracking 9.3.10 none Radiography Procedure 11.1.2.2 NIA Penetrameter 11.1.5 Film identification 11.1.8 Radiographers 11.1.7 Storage 11.1.19 Density 11.1.10 Radiation 11.1.13 OK OK OK OK OK OK OK OK OK ---- OK OK OK OK OK OK OK OK OK OK OK Wind Break OK OK OK OK OK OK OK OK NIA 9 Prepared By: Sean Kelly Z' Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Visual Inspection Report Project: AK Energy Authority Bulk Fuel Ugrade Job No.: 04-740 Client: Hankal Const. Code: API1104 Procedure: AIX-VT-1 Welders ID: Neal Cabiness Surface Condition: Clean Direct View: XXX Special Illumination: None Indirect View: Date Weld Identification. Tank Farm Area Interpretation Remarks Accept Reject 91212006 Production Welds 4" Lines Gas Lille W73 100% x Neal--roovhotpass fill and cap W74 100% x Neal-rooUhotpass fill and crap W75 100% x Neal-root/hotpassfill and cap Riel Oil Line W73 100% x Neal-rootlhotpass ll and cap W74 10M x Neal-rootlhotpass fill and cap W75 100% x Neal-root/hotpassf ll and cap Inspector: Sean Kelly _ Contractor/Client: Hankal Construction Test Date: 9/2/2006 Authorized by: Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Visual Inspection Report Project: Alaska Energy Authority Balk Fuel Upgrade Unalakleet, AK Job No.: 04-740 Client: Hankal Construction Code: Procedure: API 1104 A1X-1 Weld Location and Identification Sketch Date Weld Identification Area Interpretation Remarks Accept Reject 9/2/2006 Today neal is welding on both the fuel oil line and the gas line. He has 6 welds to make to get the done by the end of the day_ His fist welds are W75 on both lines. His fit -up and rootpass was inspected and was acceptable and he continued to finish both welds. He then welded out another 4 more welds before lunch with no problems. After lunch the wind pickup and neal used the wind break to shelter him and the welds from the wind. He welded out 4 more welds 2 welds on the gas line and two on the fuel oil line. All welds were visully inspected and were acceptable_ They moved pipe offthe road and into the ditch and began to cover the pipe to open part ofthe road. Sean Contractor/Client: Test Date: 9/2/2006 Authorized by: Hankal Construction ALASKA INDUSTRIAL X-RAY 4047 KINGSTON DRIVE ANCHORAGE, AK 99504 (907) 344-4061 FAX (907) 349-3875 JOB NO. 04-470 DATE 9/2/2006 CUSTOMER Hankal Contruction LOCATION Unalakleet AK PAGE 1 OF 1 PROJECT AK Energy Auth Fuel Upgrade CODE API 1104 Contract No. VISUAL WELD INSPECTION REPORT Neal Cabiness Procedure Variable Applicable Provision Comments Compliance Welding Procedure No. 5.3 Hankal 2 OK Process 5.3.2.1 SMAW OK Pipe Material 5.3.2.2 ASTM A53 OK Pipe Diameter 5.3.2.3 2 7/8" and over OK Pipe Wall Thickness 5.3.2.3 3/16" to .864" OK Joint Bevel 5.3.2.4 60 Degrees OK Face 5.3.2.4 1/16" OK Opening 5.3.2.4 1/16" +_ 1/32" OK Filler Metal 5.3.2.5 SFA5.1 OK Electrical Current 5.3.2.6 D.C. OK Voltage 5.3.2.6 24-30 V OK Amperage 5.3.2.6 90-1.70 OK Polarity 5.3.2.6 Rev. OK Ei,� `rode Size 5.3.2.6 1/8" OK D, Aion 5.3.2.9 Downward OK Time Lapse 5.3.2.10 2 to 12 Min OK Line Up Clamp 5.3.2.11 Yes OK Cleaning 5.3.2.12 Power Brush OK Preheat 5.3.2.13 100 F Min OK Welder Qualification 6.0 Design Allingment 7.0 Line Up Clamp Removal 7.3 Yes OK Bevel 7.4 60 Degrees OK Weather 7.5 Sunny/Windy Wind Break OK Clearance 7.6 16 " min OK Filler & Finish Beads 7.8.2 Power Brush OK Welder Identification 7.10 Yes OK Visual Inspection 9.7 Undercut 9.7.2 None OK Surface Porosity 9.3.93 None OK Reinforcement 7.8.2 1/16" / 1/8" OK Cracking 9.3.10 none OK Radiography Procedure 11.1.2.2 N/A N/A Penetrameter 11.1.5 Film -Identification 11.1.8 Radiographers 11.1.7 Storage 11.1.19 Density 11.1.10 Radiation 11.1.13 - Prepared By: Sean Kell Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Visual Inspection Report Project: Alaska Energy Authority Bulk Fuel Upgrade Unalakleet, AK Job No.: 04-740 Client: Hankal Construction Code: API1104 Procedure: AIX-1 Weld Location and Identification Sketcb Date Weld Identification Area Interpretation Remarks Accept f Reject 9/3/2006 Today neat will weld out 2 each welds on the fuel oil and gas line piping. These welds will be numbered W 71 and W72. All welds were visually inspected during the welding process and were accepted. Neal also welded end caps on each pipeline so an air test could be performed after completion of the production welds. And air test was peifmmed at 129 psi for i hour and the result was successful. We the undersigned: certify that the statements in this record are correct and that the welds Inspector: Sean Kelly _:'lam Contractor/Client: Hankal Construction r Test Date: 9/3/2006 Authorized by: ALASKA INDUSTRIAL X-RAY A047 KINGSTON DRIVE ANCHORAGE, AK 99504 (907) 344-4061 FAX (907) 349-3875 CUSTOMER Hankal Contruction JOB NO. 04-470 DATE 9/3/2006 LOCATION Unalakleet AK PROJECT AK Energy Auth Fuel Upgrade CODE API 1104 PAGE 1 OF Contract No. 1 VISUAL WELD INSPECTION REPORT Neal Cabiness Procedure Variable Applicable Provision Comments Compliance Welding Procedure No. 5.3 Hankai 2 OK Process 5.3.2.1 SMAW OK Pipe Material 5.3.2.2 ASTM A53 OK Pipe Diameter 5.3.2.3 2 7/8" and over OK Pipe Wall Thickness 5.3.2.3 3/16" to .864" OK Joint Bevel 5.3.2.4 60 Degrees OK Face 5.3.2.4 1 /16" OK Opening 5.3.2.4 1116" + 1/32" OK Filler Metal 5.3.2.5 SFA5.1 OK Electrical Current 5.3.2.6 D.C. OK Voltage 5.3.2.6 24-30 V OK Amperage 5.3.2.6 90-170 OK Polarity 5.3.2.6 Rev. OK EF 'rode Size 5.3.2.6 118" OK Di. _ rtion 5.3.2.9 Downward OK Time Lapse 5.3.2.10 2 to 12 Min OK Line Up Clamp 5.3.2.11 Yes OK Cleaning 5.3.2.12 Power Brush OK Preheat 5.3.2.13 100 F Min OK Welder Qualification 6.0 Design Ailingment 7.0 Line Up Clamp Removal 7.3 Yes OK Bevel 7.4 60 Degrees OK Weather 7.5 Sunny OK Clearance 7.6 16 " min OK Filler & Finish Beads 7.8.2 Power Brush OK Welder Identification 7.10 Yes OK Visual Inspection 9.7 Undercut 9.7.2 None OK Surface Porosity 9.3.93 None OK Reinforcement 7.8.2 1/16" / 1/8" OK Cracking 9.3.10 none OK Radiography Procedure 11.1.2.2 N/A N/A Penetrameter 11.1.5 Film Identification 11.1.8 Radiographers 11.1.7 Storage 11.1.19 Density 11.1.10 Radiation 11.1.13 Prepared By: Sean `. r' Kelly `. �.,. AAlaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 17 907-3444061 Nondestructive Testing Report Visual Inspection Report Project: AK Energy Authority Bulk Fuel Ugrade Job No.: 04-740 Client: Hankal Const. Code: API 1104 Surface Condition: Clean Direct View: XXX Procedure: AIX-VT-1 Special Illumination: None Indirect View: Welaers w: Neal cahiness Date Weld Identification Tank Farm Area Interpretation Remarks Accept Reject 9/4/2006 Production Welds 4" Lines Gas Line W68 100% x Neal-root/hotpassfiill and cap W69 100% x Neal -root/hotpass,fili and cap LPD #2 W4 100% x Neal-root/hotpassfiill and cap LPD 92 W5 1000/0 x Neal-rootrhotpass,fill and cap W1,W2,W3,W6,W7 100% x Neal repaired welds Fuel Oil Line W68 100% x Neal-root/hotpass fill and cap W69 1000/0 x Neal-root/hotpass,fill and cap LPD #2 W4 100% x Neal-root/hotpass,fill and cap LPD #2 W5 100% x I Neal-root/hotpassfiil and cap W 1, W3 100% x Neal repaired welds 0 Inspector: Sean Kelly Contractor/Client: Hankal Construction Test Date: 9/4/2006 — Authorized by: K Alaska Industrial X-ray Inc. 4047 Kingston Drive, Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Visual Inspection Report Project: Alaska Energy Authority Bulk Fuel Upgrade Unalakleet, AK Job No.: 04-740 Client: Hankal Construction Code: API1104 Procedure: AIX-1 Weld Location and Identification Sketch Date Weld Identification Area Interpretation Remarks Accept I Reject 9/4/2006 Today veal will weld out 4 welds 4" line fuel oil and gas line piping_ These welds will be numbered later. Neal also welded 4 each 2" welds 2 on the gas line and 2 on the fuel oil line._ All welds were visually Visually inspected and were acceptable. He also has to repair 7 each 2" welds for the LPDs due to IP, Porosity and cold lap that the previous welder did not fix. Sean Kelly ,�" Contractor/Client: Hankal Construction Test Date: 9/4/2006 Authorized by: ALASKA INDUSTRIAL X-RAY 4047 KINGSTON DRIVE JOB NO. 04-470 ANCHORAGE, AK 99504 (907) 344-4061 FAX (907) 349-3875 DATE 9/4/2006 CUSTOMER Hankal Contruction LOCATION Unalakleet AK PAGE 1 OF 1 PROJECT AK Energy Auth Fuel Upgrade CODE API 1104 Contract No. VISUAL WELD INSPECTION REPORT Neal Cabiness Procedure Variable Applicable Provision Comments Compliance Welding Procedure No. 5.3 Hankal 2 OK Process 5.3.2.1 S MAW OK Pipe Material 5.3.2.2 ASTM A53 OK Pipe Diameter 5.3.2.3 2 7/8" and over OK Pipe Wall Thickness 5.3.2.3 3/16" to .864" OK Joint Bevel 5.3.2.4 60 Degrees OK Face 5.3.2.4 1/16" OK Opening 5.3.2.4 1/16" + 1/32" OK Filler Metal 5.3.2.5 SFA5.1 OK Electrical Current 5.3.2.6 D.C. OK Voltage 5.3.2.6 24-30 V OK Amperage 5.3.2.6 90-170 OK Polarity 5.3.2.6 Rev. OK F°nctrode Size 5.3.2.6 1/8" OK action 5.3.2.9 Downward OK Time Lapse 5.3.2.10 2 to 12 Min OK Line Up Clamp 5.3.2.11 Yes OK Cleaning 5.3.2.12 Power Brush OK Preheat 5.3.2.13 100 F Min OK Welder Qualification 6.0 Design Allingment 7.0 Line Up Clamp Removal 7.3 Yes OK Bevel 7.4 60 Degrees OK Weather 7.5 Sunny OK Clearance 7.6 16 " min OK Filler & Finish Beads 7.8.2 Power Brush OK Welder Identification 7.10 Yes OK Visual Inspection 9.7 Undercut 9.7.2 None OK Surface Porosity 9.3.93 None OK Reinforcement 7.8.2 1/16" / 1/8" OK Cracking 9.3.10 none OK Radiography Procedure 11.1.2.2 N/A N/A Penetrameter 11.1.5 Film Identification 11.1.8 Radiographers 11.1.7 Storage 11.1.19 Density 11.1.10 Radiation 11.1.13 Prepared By: Sean Kell-' Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report risuad Inspection Report Project: AK Energy Authority Bulk Fuel Ugrade Job No.: 04-740 Client: Hankal Const. Code: Procedure: API 1104 AIX-VT-I Surface Condition: Clean Direct View: XXX Special Illumination: None Indirect View: Date Weld Identification Tank Farrel Area Interpretation Remarks Accept Reject- 9/5/2006 Production Welds V Lines Gas Line W64 100% x Neal-root/hotpus fill and cap W66 1000/0 x Neal-root(hotpass,fitl and cap W67 100% x Neal -root/hotpassfill and cap W70 100% x Neal-roodhotpass fill and cap Fhel Oil Line W64 1000/0 x Neal-rootlhotpass fill and cap W66 1000/0 x Neal -rootlhotpassfill and cap W67 100% x Neal-root/hotpass,fill and cap W70 100% x Neal-root/hotpass;M and cap We, the undersigned, certify that the statements in this record are correct and that the welds Inspector. Sean Kelly Contractor/Client: Hankal Construction Test Date: 915/2006 �, Authorized by: Alaska Industrial X-ray Inc. 4047 Kingston ®rive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Resort Visual Inspection Report Project: Alaska Energy Authority Bulk Fuel Upgrade Unalakleet, AK .lob No.: Client: Hankal Construction Code: API1104 Procedure: AIX-1 Feld Location and Identification Sketch b4-740 Date Weld Identification Area I Interpretation I Remarks Accept J Reject 9/5/2006 Today was a cloudy and cold morning. Neal and crew placed the LPDs into postion in the ditch and made cuts to weld the spool into place. He has 4 welds to make 2 each on the fuel oil line and 2 each on the gas line. All 4 welds fit -up great and gaps were inspected prior to welding. The rootpass and hotpass were also inspected with no problem noted. Fill and cap looked good at inspection. After lunch neal welded out 4 more welds 2 each on fuel oil and gas line out ofthe ditch. These welds will be tied into the line that is in the ditch now. All welds were also inspected without and repairs needed Sean Contractor/Client: Hankal Construction Test Bate: 9/5/2006 Authorized by: ALASKA INDUSTRIAL X-RAY 4047 KINGSTON DRIVE JOB NO. 04-470 ANCHORAGE, AK 99504 (907) 3"-4061 FAX (907) 349-3875 DATE 9/5/2006 CUSTOMER Hankal Contruction LOCATION Unalakleet AK PAGE 1 OF 1 PROJECT AK Energy Auth Fuel Upgrade CODE API 1104 Contract No. VISUAL WELD INSPECTION REPORT Neal Cabiness Procedure Variable Applicable Provision Comments Compliance Welding Procedure No. 5.3 Hankal 2 OK Process 5.3.2.1 SMAW OK Pipe Material 5.3.2.2 ASTM A53 OK Pipe Diameter 5.3.2.3 2 7/8" and over OK Pipe Wall Thickness 5.3.2.3 3/16" to .864" OK Joint Bevel 5.3.2.4 60 Degrees OK Face 5.3.2.4 1/16" OK Opening 5.3.2.4 1/16" + 1/32" OK Filler Metal 5.3.2.5 SFA5.1 OK Electrical Current 5.3.2.6 D.C. OK Voltage 5.3.2.6 24-30 V OK Amperage 5.3.2.6 90-170 OK Polarity 5.3.2.6 Rev. OK r",4ctrode Size 5.3.2.6 1/8" OK ,action 5.3.2.9 Downward OK Time Lapse 5.3.2.10 2 to 12 Min OK Line Up Clamp 5.3.2.11 Yes OK Cleaning 5.3.2.12 Power Brush OK Preheat 5.3.2.13 100 F Min OK Welder Qualification 6.0 Design Allingment 7.0 Line Up Clamp Removal 7.3 Yes OK Bevel 7.4 60 Degrees OK Weather 7.5 Cloudy OK Clearance 7.6 16 " min OK Filler & Finish Beads 7.8.2 Power Brush OK Welder Identification 7.10 Yes OK Visual Inspection 9.7 Undercut 9.7.2 None OK Surface Porosity 9.3.93 None OK Reinforcement 7.8.2 1/16" / 1/8" OK Cracking 9.3.10 none OK Radiography Procedure 11.1.2.2 N/A N/A Penetrameter 11.1.5 Film Identification 11.1.8 Radiographers 11.1.7 Storage 11.1.19 Density 11.1.10 Radiation 11.1.13 Prepared By: Sean Kelly Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99604 907-344-4061 Nondestruefive Testing Report Visual Inspection Report Project: AK Energy Authority Bulk Fuel Ugrade Job No.: 04-740 Client: Hankal Const. Code: API 1104 Surface Condition: Clean Direct View: XXX Procedure: AIX-VT-1 Special IDumiaation: None Indirect View: Welders ID: Bill Cambell Nf-A C nhinPcc Date Weld Identification Tank Farm Area Interpretation Remarks Accept Reject 916/2006 Production welds Gas Line W59 10010/0 x Neal-root/hotpassfiill and cap W60 1000/0 x Neal-r.Vhotpass fill and cap W61 100% x Bill-,,,&hotpass,fill and cap W62 100% x Neal-roouhotpu011 and cap W63 1000/0 x Neal-rootthotpass fill and cap W65 100% x Neal -root/hotpass H and cap Fhel Oil W59 100% x Neal-root/hotpass;H and cap W60 1000/0 x Neal-root/hotpass,iill and cap W61 100% x Bill-root/hatpa&%U and cap W62 100% x I Neal-roovhotpassM and cap W63 1000/0 x Neal-root/hotpa.M and cap W65 1000/0 x INeal -root/hotpass fill and cap Inspector: Sean Kelly _Contractor/Client: Hankal Construction a Test Date: 9/6/2006 Authorized by: Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report VsualInspection Report Project: Alaska Energy Authority Bulk Fuel Upgrade Unalakleet, AK Job No.: 04-740 Client: Hankal Construction Code: API1104 Procedure: AIX-1 Weld Location and Identification Sketch Date Weld Identification Area Interpretation Remarks Accept I Reject 9/6/2006 Today Bill Cambell started welding on the pipeline. His first two welds were W61 on the gas and the fuel oil line. Both welds were visually inspected throughout the entire welding process to insure his quality of work No problems werwe noted and both welds were acceptable. Neal was welding on couple welds just down from bill. His welds were also inspected with no problem. After lunch neal welded out couple more welds and two test caps for the air test. The test was run at 130psi for 1 hour and was a success. The end caps will be cut offtomorrow and both neat and bill will continue to weld on the pipeline. We. the undersigned. certify that the statements in this record are correct and that the welds were prepared and tested in accordance with thePilowing Code: API 1104 Sean Contractor/Client: Test Date: 9/6/2006 Authorized by: Hankal Construction ALASKA INDUSTRIAL X-RAY 4047 KINGSTON DRIVE ANCHORAGE, AK 99504 (907) 344-4061 FAX (907) 349-3875 CUSTOMER Hankal Contruction JOB NO. 04-470 DATE 9/6/2006 LOCATION Unalakleet AK PROJECT AK Energy Auth Fuel Upgrade PAGE 1 OF CODE API 1104 Contract No. 1 VISUAL WELD INSPECTION REPORT Neal Cabiness/Bill Cambell .Procedure Variable Applicable Provision Comments Compliance Welding Procedure No. 5.3 Hankal 2 OK Process 5.3.2.1 SMAW OK Pipe Material 5.3.2.2 ASTM A53 OK Pipe Diameter 5.3.2.3 2 7/8" and over OK Pipe Wall Thickness 5.3.2.3 3/16" to .864" OK Joint Bevel 5.3.2.4 60 Degrees OK Face 5.3.2.4 1 /16" OK Opening 5.3.2.4 1/16" + 1/32" OK Filler Metal 5.3.2.5 SFA5.1 OK Electrical Current 5.3.2.6 D.C. OK Voltage 5.3.2.6 24-30 V OK Amperage 5.3.2.6 90-170 OK Polarity 5.3.2.6 Rev. OK "pctrode Size 5.3.2.6 1/8" OK action 53.2.9 Downward OK Time Lapse 5.3.2.10 2 to 12 Min OK Line Up Clamp 5.3.2.11 Yes OK Cleaning 5.3.2.12 Power Brush OK Preheat 5.3.2.13 100 F Min OK Welder Qualification 6.0 Design Allingment 7.0 Line Up Clamp Removal 7.3 Yes OK Bevel 7.4 60 Degrees OK Weather 7.5 Cloudy/Wind wind break OK Clearance 7.6 16 " min OK Filler & Finish Beads 7.8.2 Power Brush OK Welder Identification 7.10 Yes OK Visual Inspection 9.7 Undercut 9.7.2 None OK Surface Porosity 9.3.93 None OK Reinforcement 7.8.2 1/16" / 1/8" OK Cracking 9.3.10 none OK Radiography Procedure 11.1.2.2 N/A N/A Penetrameter 11.1.5 Film Identification 11.1.8 Radiographers 11.1.7 Storage 11.1.19 Density 11.1.10 Radiation 11.1.13 Prepared By: Sean Kelly ii Alaska Industrial X-ray Inc. 4047 Kingston ®rive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Visual Inspection Report Project: AK Energy Authority Bulk Fuel Ugrade Job No.: 04-740 Client: Hankal Const. Code: Procedure: API 1104 AIX-VT-I Welders ID: Rill Camhell Surface Condition: Clean Direct View: XXX Special rumination: None Indirect View: Weld Location and Identification Sketch NPnI Cnhinacc Date Weld Identification Tank Farm Area Interpretation Remarks Accept Reject 9/7/2006 Production Welds Gas Line W58 100% x Neal-rooVhctpass,fill and cap W57 100% x I Neal-root/hotpass,0 and cap W 56 100% x Neal-root/hotpassfill and cap W55 100% x Neal-root/hotpass fill and cap No number yet 100% x Bill-root/hotpass fih and cap No number yet 100% x Bill -root/hotpassfi l and cap Fuel Oil W 58 100% x Neal-root/hotpass fill and cap W57 100% x Neal-root/hotpass fill and cap W56 100% x Neal-roct/hotpassXdl and cap W55 t00% x Neal-root/hotpass fill and cap No number yet t00% x Bill-root/hotpass,fill and cap No number yet 100% 1 x Bill -root/hotpassJill and cap - e, 111e ulluelsignea, ceraty that ine Statements in inns Iecow are correct and that the welds were prepared and tested in accordance with the,,fbllowin2 Code: API 1104 Inspector: Sean Kelly Contractor/Client: Hankal Construction Test Date: 9/7/2006 Authorized by: Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nonrdestruetive Vesting Report Visual Inspection Report Project: Alaska Energy Authority Duck Fuel Upgrade Unalakleet, AK Job No.: 04-740 Client: Hankal Construction Code: API1104 Procedure: AIX-1 Weld Location and Identification Sketch Date I Weld Identification I Area Remarks 9/7/2006 1 Today was very wet with rain. Both neal and bill used shelters to protect themselves from the weather. Neal made 8 welds today while Bill made 4 welds. All welds were visually ims eted throughout the welding process with no problems noted We, the undersigned- certify that the statements in this record are correct and that the welds were prepared and tested in accordance with UWfoflowing Code: API 1104 Inspector: Sean Kelly- � -­— Contractor/Client: Hankal Construction Test Date: 9/7/2006 Authorized by: ALASKA INDUSTRIAL X-RAY 4047 KINGSTON DRIVE JOB NO. 04-470 ANCHORAGE, AK 99504 (907) 344-4061 FAX (907) 349-3875 DATE 9/7/2006 CUSTOMER Hankal Contruction LOCATION Unalakleet AK PAGE 1 OF 1 PROJECT AK Energy Auth Fuel Upgrade CODE API 1104 Contract No. VISUAL WELD INSPECTION REPORT Neal Cabiness/Bill Cambell Procedure Variable Applicable Provision Comments Compliance Welding Procedure No. 5.3 Hankal 2 OK Process 5.3.2.1 SMAW OK Pipe Material 5.3.2.2 ASTM A53 OK Pipe Diameter 5.3.2.3 2 7/8" and over OK Pipe Wall Thickness 5.3.2.3 3/16" to .864" OK Joint Bevel 5.3.2.4 60 Degrees OK Face 5.3.2.4 1/16" OK Opening 5.3.2.4 1/16" + 1/32" OK Filler Metal 5.3.2.5 SFA5.1 OK Electrical Current 5.3.2.6 D.C. OK Voltage 5.3.2.6 24-30 V OK Amperage 5.3.2.6 90-170 OK Polarity 5.3.2.6 Rev. OK Feectrode Size 5.3.2.6 1/8" OK action 5.3.2.9 Downward OK Time Lapse 5.3.2.10 2 to 12 Min OK Line Up Clamp 5.3.2.11 Yes OK Cleaning 5.3.2.12 Power Brush OK Preheat 5.3.2.13 100 F Min OK Welder Qualification 6.0 Design Allingment 7.0 Line Up Clamp Removal 7.3 Yes OK Bevel 7.4 60 Degrees OK Weather 7.5 RAIN!!! Shelter OK Clearance 7.6 16 " min OK Filler & Finish Beads 7.8.2 Power Brush OK Welder Identification 7.10 Yes OK Visual Inspection 9.7 Undercut 9.7.2 None OK Surface Porosity 9.3.93 None OK Reinforcement 7.8.2 1/16" / 1/8" OK Cracking 9.3.10 none OK Radiography Procedure 11.1.2.2 N/A N/A Penetrameter 11.1.5 Film Identification 11.1.8 Radiographers 11.1.7 Storage 11.1.19 Density 11.1.10 Radiation 11.1.13 - Prepared By: Sean Kell Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99604 907-344-4061 Nondestructive Testing Deport Visual Inspection deport Project: AK Energy Authority Sulk Fuel Ugrade Job No.: 04-740 Client: Hankal Const. Code: API1104 Procedure: AIX-OJT-I Welders ID: Surface Condition: Clean Direct View: XXX Special Illumination: None Indirect View: Neal Cabiness Date Weld Identification Tank Farm Area Interpretation Remarks Accept Reject 9/8/2006 Production Welds Gras Line W51 100% x Neal-root/hotpass,fill and cap W52 100% x Neal-root/hotpass fill and cap W53 100% x Neal-roct/hotpass,fili and cap W54 100% x Neal-rootlhotpassfill and cap Fuel W W51 100% x Neal-root/hotpass,fill and cap W 52 100% x Neal-rootlhotpass,fill and cap W53 100% x Neal-root/hotpass.fill and cap W54 I00% s 1 Neal-root/hotpass fill and cap We, the undersigned, certify that the statements in this record are correct and that the welds Inspector: Sean Kelly ContractorlClient: Hankal Construction Test Date: 9/8/2006 Authorized by: Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report Visual Inspection Report Project: Alaska Energy Authority Bulk Fuel Upgrade Unalakleet, AK Job No.: 04-740 Client: Hankal Construction Code: API1104 Procedure: AIX-1 Weld Location and Identification Sketch Date Weld Identification Area Interpretation Remarks Accept I Reject 9/8/2006 Today was dry but windy. Bill welded on the test caps for the bridge penetration and ran an air test at 135 psi for 1 hour. The test results were successful. Neal welded 8 welds 4 each on the fuel oil line and 4 each on the gas line. All welds were visually inspected prior and during the welding process without any problems noted Sean are correct a le: API 1104 Contractor/Client: Hankal Construction Test Date: 9/8/2006 Authorized by: ALASKA INDUSTRIAL X-RAY 4047 KINGSTON DRIVE ANCHORAGE, AK 99504 (907) 344-4061 FAX (907) 349-3875 JOB NO. 04-470 DATE 9/8/2006 CUSTOMER Hankal Contruction LOCATION Unalakleet AK PROJECT AK Energy Auth Fuel Upgrade CODE API 1104 PAGE 1 OF Contract No. 1 VISUAL WELD INSPECTION REPORT Neal Cabiness Procedure Variable Applicable Provision Comments Compliance Welding Procedure No. 5.3 Hankal 2 OK Process 5.3.2.1 SMAW OK Pipe Material 5.3.2.2 ASTM A53 OK Pipe Diameter 5.3.2.3 2 7/8" and over OK Pipe Wall Thickness 5.3.2.3 3/16" to .864" OK Joint Bevel 5.3.2.4 60 Degrees OK Face 5.3.2.4 1/16" OK Opening 5.3.2.4 1/16" + 1/32" OK Filler Metal 5.3.2.5 SFA5.1 OK Electrical Current 5.3.2.6 D.C. OK Voltage 5.3.2.6 24-30 V OK Amperage 5.3.2.6 90-170 OK Polarity 5.3.2.6 Rev. OK r°-ctrode Size 5.3.2.6 1/8" OK ,fiction 5.3.2.9 Downward OK Time Lapse 5.3.2.10 2 to 12 Min OK Line Up Clamp 5.3.2.11 Yes OK Cleaning 5.3.2.12 Power Brush OK Preheat 5.3.2.13 100 F Min OK Welder Qualification 6.0 Design Allingment 7.0 Line Up Clamp Removal 7.3 Yes OK Bevel 7.4 60 Degrees OK Weather 7.5 Windy Shelter OK Clearance 7.6 16 " min OK Filler & Finish Beads 7.8.2 Power Brush OK Welder Identification 7.10 Yes OK Visual Inspection 9.7 Undercut 9.7.2 None OK Surface Porosity 9.3.93 None OK Reinforcement 7.8.2 1/16" / 1/8" OK Cracking 9.3.10 none OK Radiography Procedure 11.1.2.2 N/A N/A Penetrameter 11.1.5 Film Identification 11.1.8 Radiographers 11.1.7 Storage 11.1.19 Density 11.1.10 Radiation 11.1.13 Prepared By: Sean Kell '' Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 lNrondestruelive Testing Report Visual Inspection Report Project: AK Energy Authority Bulk Fuel Ugrade Job No.: 04- 740 Client: Hankal Const. Code: API1104 Procedure: AIX-VT-1 Welders ID: Surface Condition: Clean Direct View: XXX Special Illumination: None Indirect View: Feld Location and Identification Sketch Neal Cabiness Date Weld Identification Tank Farm Area Interpretation Remarks Accept Reject 9/9/2" Production Welds Gas Line W48 100% x Neal-root/hotpassM and cap W49 100°/u x Neal-rootlhotpassM and cap W50 IOwo x Neal-root/hotpassfill and cap Fuel Oil W48 100% x Neal-reot/hotpass,Gll and cap W49 100% x Neal-root/hotpass,fiIl and cap W 50 100% x Neal-root/hotpassfiill and cap We, the undersigned, certify that the statements in this record are correct and that the welds were oreoared and tested in accordance with the &Howine Code: API 1104 Inspector: Sean Kelly f Contractor/Client: Hankal Construction Test Date: 9/9/2006 Authorized by: Alaska Industrial X-ray Inc. 4047 Kingston ®rive Anchorage, Alaska 99504 907-344-4061 Nondestructive Vesting Report Visual Inspection Report Project: Alaska Energy Authority Bulb Fuel Upgrade Unalakleet, AK Job No.: 04-740 Client: Hankal Construction Code: API1104 Procedure: AIX-1 Weld Location and Identification Sketch Date I Weld Identification I Area Remarks 9/9/2006 1 Today was wet with rain. Neal completed the last six welds before they close the road for the final tie-ins. His fit -ups and rootpasses were all visually inspected with no problems observed His filler passes and caps were all inspeted with no problems noted He uesed a shelter to keep himself and the welds We, the undersigned, certify that the statements in this record are correct and that the welds were -prepared and tested in accordance with followin Code: API 1104 r Inspector: Sean Kelly Contractor/Client: Hankal Construction Test Date: 9/9/2006 Authorized by: ALASKA INDUSTRIAL X-RAY 4047 KINGSTON DRIVE ANCHORAGE, AK 99504 (907) 344-4061 FAX (907) 349-3875 CUSTOMER Hanka! Contruction JOB NO. 04-470 DATE 9/9/2006 LOCATION Unalakleet AK PROJECT AK Energy Auth Fuel Upgrade CODE API 1104 PAGE 1 OF Contract No. 1 VISUAL WELD INSPECTION REPORT Neal Cabiness Procedure Variable Applicable Provision Comments Compliance Welding Procedure No. 5.3 Hankal 2 OK Process 5.3.2.1 SMAW OK Pipe Material 5.3.2.2 ASTM A53 OK Pipe Diameter 5.3.2.3 2 7/8" and over OK Pipe Wall Thickness 5.3.2.3 3/16" to .864" OK Joint Bevel 5.3.2.4 60 Degrees OK Face 5.3.2.4 1/16" OK Opening 5.3.2.4 1116" + 1/32" OK Filler Metal 5.3.2.5 SFA5.1 OK Electrical Current 5.3.2.6 D.C. OK Voltage 5.3.2.6 24-30 V OK Amperage 5.3.2.6 90-170 OK Polarity 5.3.2.6 Rev. OK Fa-ctrode Size 5.3.2.6 1/8" OK yction 5.3.2.9 Downward OK Time Lapse 5.3.2.10 2 to 12 Min OK Line Up Clamp 5.3.2.11 Yes OK Cleaning 5.3.2.12 Power Brush OK Preheat 5.3.2.13 100 F Min OK Welder Qualification 6.0 Design Allingment 7.0 Line Up Clamp Removal 7.3 Yes OK Bevel 7.4 60 Degrees OK Weather 7.5 Rain Shelter OK Clearance 7.6 16 " min OK Filler & Finish Beads 7.8.2 Power Brush OK Welder Identification 7.10 Yes OK Visual Inspection 9.7 Undercut 9.7.2 None OK Surface Porosity 9.3.93 None OK Reinforcement 7.8.2 1/16" / 1/8" OK Cracking 9.3.10 none OK Radiography Procedure 11.1.2.2 N/A N/A Penetrameter 11.1.5 Film Identification 11.1.8 Radiographers 11.1.7 Storage 11.1.19 Density 11.1.10 Radiation 11.1.13 Prepared By: Sean Kell _ Alaska industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Report NsualInspection Report Project: AK Energy Authority Bulk Fuel Ugrade Job No.: 04-740 Client: Hankal Const, Code: API 1104 Surface Condition: Clean Direct View: XXX Procedure: AIX-VT-1 Special Mumination: None Indirect View: Welders ID: Neal Cabiness Date Weld Identification Tank Farm Area Interpretation Remarks Accept Reject 9/1012006 Production welds Gas Line W49A 1000/0 x Neal-root/hotpass,fill and cap W50A 100% x Neal-root/hoipass fill and cap Ebel Oil W49A 100% x Neal-root(hotpass,fill and cap W 50A 1000/0 x Neal-rootlhotpassfill and cap we, the unaersiarled, certuv that the statements in tins record are correct and that the welds Test Date: 9/10/2006 - G Contractor/Client: Authorized by: Hankai Construction Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Vesting Deport Visual Inspection Report Project: Alaska Energy Authority Bulk Fuel Upgrade Unaiakleet, AK Job No.: 04-740 Client: Ilankal Construction Code: API1104 Procedure: AIX-I Weld Location and Identification Sketch Date Weld Identification Area Interpretation Remarks Accept I Reject 9/ 10/2006 Today is the last day for the underground piping. Neal has 4 welds to make. He has to add a pup on each the gas line and the fuel oil line then they will put the pipe into the ditch and through the bridge holes that have been cut to run the line under the bridge. After the lines were into position Neal made the final tie-in welds for the gas line and the fuel oil line. All 4 welds were visully inspected during the welding process and were considered acceptable. Bill welded the test caps onto the ends of the gas line and the fuel oil line to test the lines on monday morning. We. the undersigned, certify that the statements in this record are correct and that the welds Sean Contractor/Client: Hankal Construction Test Date: 9/10/2006 Authorized by: ALASKA INDUSTRIAL X-RAY 4047 KINGSTON DRIVE JOB NO. 04-470 ANCHORAGE, AK 99504 (907) 344-4061 FAX (907) 349-3875 DATE 9/10/2006 CUSTOMER Hankal Contruction LOCATION Unalakleet AK PAGE 1 OF 1 PROJECT AK Energy Auth Fuel Upgrade CODE API 1104 Contract No. VISUAL WELD INSPECTION REPORT Neal Cabiness/Bill Cambell Procedure Variable Applicable Provision Comments Compliance Welding Procedure No. 5.3 Hankal 2 OK Process 5.3.2.1 SMAW OK Pipe Material 5.3.2.2 ASTM A53 OK Pipe Diameter 5.3.2.3 2 7/8" and over OK Pipe Wall Thickness 5.3.2.3 3/16" to .864" OK Joint Bevel 5.3.2.4 60 Degrees OK Face 5.3.2.4 1/16" OK Opening 5.3.2.4 1116" + 1/32" OK Filler Metal 5.3.2.5 SFA5.1 OK Electrical Current 5.3.2.6 D.C. OK Voltage 5.3.2.6 24-30 V OK Amperage 5.3.2.6 90-170 OK Polarity 5.3.2.6 Rev. OK "-'4ctrode Size 5.3.2.6 1/8" OK action 5.3.2.9 Downward OK Time Lapse 5.3.2.10 2 to 12 Min OK Line Up Clamp 5.3.2.11 Yes OK Cleaning 5.3.2.12 Power Brush OK Preheat 5.3.2.13 100 F Min OK Welder Qualification 6.0 Design Allingment 7.0 Line Up Clamp Removal 7.3 Yes OK Bevel 7.4 60 Degrees OK Weather 7.5 Sunny OK Clearance 7.6 16 " min OK Filler & Finish Beads 7.8.2 Power Brush OK Welder Identification 7.10 Yes OK Visual Inspection 9.7 Undercut 9.7.2 None OK Surface Porosity 9.3.93 None OK Reinforcement 7.8.2 1/16" / 1/8" OK Cracking 9.3.10 none OK Radiography Procedure 11.1.2.2 N/A N/A Penetrameter 11.1.5 Film Identification 11.1.8 Radiographers 11.1.7 Storage 11.1.19 Density 11.1.10 Radiation 11.1.13 Prepared By: Sean Kell Alaska Industrial X-ray Inc. 4047 Kingston Drive Anchorage, Alaska 99504 907-344-4061 Nondestructive Testing Deport Visual Inspection Report Project: Alaska Energy Authority Bulk Fuel Upgrade Unalakleet, AK Job No.: 04-740 Client: Hankal Construction Code: API1104 Procedure: AIX-1 Weld Location and Identification Sketch Date I Weld Identification I Area I Interpretation I Remarks 9/ 11/2006 This morning they tested both the gas and the fuel oil lines from the tank farm to the bridge. The pressure was 130 psi for 1 hour with all exposed welds checked for leaks with soap and water. No leaks were found and the test held for 1 hour. Test results were successful. Sean Contractor/Client: Hankal Construction Test Date: 9/11/2006 Authorized by: