Village End Use Energy Efficiency Measures Program
AEA Grant # 2195225 Administered by Alaska Building Science Network
Lower Kalskag Final Report
Community Summary
8 community buildings and 3 teacher housing units received energy efficiency upgrades:
City Office/Bingo Hall, Water Treatment plant, Health Clinic, Tribal Office, Zackar Levi Elementary School
(Lower School) and Gymnasium, School Generator Shed, KSD Bunkhouse/library, three teacher housing
units.
Retrofits Completed: December 2007- January 2008
Lower School Gym Will Be Completed Summer 2009
Village-Wide Lighting Retrofit Summary:
• Retrofitted 244 light fixtures with electronic ballasts & T8 lamps
• Installed 51 compact fluorescent light bulbs
• Installed 16 T-5 linear fluorescent fixtures in the School Gym
• Pre-retrofit energy use for all lighting: 29.452 Kilowatts
• Post-retrofit energy use for all lighting: 17.284 Kilowatts
• Energy savings projection: 12.168 Kilowatts
• Pre-retrofit to post retrofit energy reduction: 41%
• Estimated Annual Savings:
kWh Rate (as of 11/13/08): $0.64 Fuel Cost (FY 2007 Ave): $1.89
(The Fuel Rate is taken from the FY 2007 PCE data for Upper Kalskag)
Comparative Comparative Hours Per Day/ Electrical Avoided Diesel Avoided Diesel
250 Days Per Year Savings Use (gal) Costs
Locally Estimated $14,298.4 1621.28 $3,064.21
4 Hours/day $7,804.56 884.95 $1,672.55
7 Hours/day $13,657.90 1548.65 $2,926.96
10 Hours/day $19,511.30 2212.36 $4,181.37
• Total project cost for all measures: $37,775
• Simple Payback (lighting measures only, using 7 hours/day lighting use run-time): 3.5 years
• Total village wide in-kind contribution: $ 6,818.00 (extended grant capacity by 18%)
Additional Energy Efficiency Measures:
The clinic received a programmable thermostat.
16 hr. Boiler maintenance & efficiency training
2
Alaska Building Science Network – Village End Use Energy Efficiency Program – ’07-‘08 West Region – Lower Kalskag
City of Lower Kalskag Owned Buildings
ABSN Field Manager Harry Morgan
during maintenance worker training.
2 buildings owned by the City of Lower Kalskag received energy efficient lighting upgrades as follows:
City Office/Bingo Hall, Water Treatment
• Lighting upgrades completed in: December 2007
• Retrofitted 63 light fixtures with electronic ballasts & T8 lamps
• Pre-retrofit energy use for all lighting: 5.628 Kilowatts
• Post-retrofit energy use for all lighting: 3.562 Kilowatts
• Energy savings projection: 2.066 Kilowatts
• Pre-retrofit to post retrofit energy reduction: 37%
• Estimated Annual Savings:
Comparative Comparative
Hours Per Day / Electrical Avoided Diesel Avoided
250 Days Per Year Savings Use (gal) Diesel Costs
Locally Estimated $2,913.33 330.34 $624.34
4 Hours/day $1,325.13 150.25 $283.98
7 Hours/day $2,318.98 262.95 $496.97
10 Hours/day $3,312.83 375.64 $709.95
3
Alaska Building Science Network – Village End Use Energy Efficiency Program – ’07-‘08 West Region – Lower Kalskag
City Office/Bingo Hall
Mickey Nicolai helps with lighting assessments.
Materials Installed Quantity 2-lamp electronic ballast, (2) 25 watt T8 lamps 26 4-lamp electronic ballast, (4) 25 watt T8 lamps 4 • Pre-retrofit energy use: 2856 watts
• Post-retrofit energy use: 1582 watts
• Energy savings projection: 1274 watts
• Pre-retrofit to post retrofit energy reduction: 45%
• Estimated annual savings: Comparative Comparative
Hours Per Day / Electrical Avoided Diesel Avoided Diesel
250 Days Per Year Savings Use (gal) Costs
1750 Hours/year (Est.) $1,430.00 162.15 $306.45
4 Hours/day $817.14 92.65 $175.12
7 Hours/day $1,430.00 162.15 $306.45
10 Hours/day $2,042.86 231.64 $437.79
Water Treatment plant
Andrew Wise upgrades a fixture in the water treatment plant.
Materials Installed Quantity 2-lamp electronic ballast, (2) 32 watt T8 lamps 33
• Pre-retrofit energy use: 2772 watts
• Post-retrofit energy use: 1980 watts
• Energy savings projection: 792 watts
• Pre-retrofit to post retrofit energy reduction: 29%
• Estimated annual savings: Comparative Comparative
Hours Per Day / Electrical Avoided Diesel Avoided Diesel
250 Days Per Year Savings Use (gal) Costs 2920 Hours/year (Est.) $1,483.33 168.19 $317.88
4 Hours/day $507.99 57.60 $108.86
7 Hours/day $888.98 100.80 $190.51
10 Hours/day $1,269.97 144.00 $272.16
4
Alaska Building Science Network – Village End Use Energy Efficiency Program – ’07-‘08 West Region – Lower Kalskag
Village of Lower Kalskag Owned Buildings
2 buildings owned by the Village of Lower Kalskag received energy efficient lighting upgrades as follows:
Health Clinic, Tribal Office
• Lighting upgrades completed in: December 2007
• Retrofitted 35 light fixtures with electronic ballasts & T8 lamps
• Installed 2 compact fluorescent light bulbs
• Pre-retrofit energy use for all lighting: 2.31 Kilowatts
• Post-retrofit energy use for all lighting: 1.92 Kilowatts
• Energy savings projection: 0.39 Kilowatts
• Pre-retrofit to post retrofit energy reduction: 17%
• Estimated Annual Savings:
Comparative Comparative
Hours Per Day / Electrical Avoided Diesel Avoided
250 Days Per Year Savings Use (gal) Diesel Costs
Locally Estimated $498.62 56.54 $106.86
4 Hours/day $250.15 28.36 $53.61
7 Hours/day $437.76 49.64 $93.81
10 Hours/day $625.37 70.91 $134.02
Additional Energy Efficiency Measures:
The clinic received a programmable thermostat.
Notes: For programmable thermostats in community buildings we work with local maintenance staff. Our
goal is to set thermostats to a night-time and weekend set-back of 62 - 64 degrees and a daytime temp of
68-70 degrees. Programmable thermostats used and maintained as programmed are known to achieve
an overall fuel savings of between 5 and 10% over non-programmed thermostats.
5
Alaska Building Science Network – Village End Use Energy Efficiency Program – ’07-‘08 West Region – Lower Kalskag
Health Clinic
Programmable thermostat installed in the Clinic.
Materials Installed Quantity 2-lamp electronic ballast, (2) 25 watt T8 lamps 15 3-lamp electronic ballast, (2) 25 watt T8 lamps 4 4-lamp electronic ballast, (4) 25 watt T8 lamps 5
CFL-20 W 2
• Pre-retrofit energy use: 1650 watts
• Post-retrofit energy use: 1403 watts
• Energy savings projection: 247 watts
• Pre-retrofit to post retrofit energy reduction: 15%
• Estimated annual savings: Comparative Comparative
Hours Per Day / Electrical Avoided Diesel Avoided Diesel
250 Days Per Year Savings Use (gal) Costs 1700 Hours/year (Est.) $269.32 30.54 $57.72
4 Hours/day $158.43 17.96 $33.95
7 Hours/day $277.25 31.44 $59.41
10 Hours/day $396.06 44.91 $84.88
Additional Energy Efficiency Measures: The clinic received a programm able thermostat.
Tribal Office
Fixtures re-lamped with 25 watt T-8
lamps for additional savings. Community computer lab.
Materials Installed Quantity
2-Lamp Fixture (w/existing electronic ballast) re-lamped with (2)25 watt T8 Lamps 11
• Pre-retrofit energy use: 660 watts
• Post-retrofit energy use: 517 watts
• Energy savings projection: 143 watts
• Pre-retrofit to post retrofit energy reduction: 22%
• Estimated annual savings: Comparative Comparative
Hours Per Day / Electrical Avoided Diesel Avoided Diesel
250 Days Per Year Savings Use (gal) Costs 2500 Hours/year (Est.) $229.30 26.00 $49.14
4 Hours/day $91.72 10.40 $19.66
7 Hours/day $160.51 18.20 $34.40
10 Hours/day $229.30 26.00 $49.14
Note: Fixtures contained existing electronic ballast & 32 watt T-8 lamps installed previously. All fixtures
were re-lamped 25 watt T-8 lamps.
6
Alaska Building Science Network – Village End Use Energy Efficiency Program – ’07-‘08 West Region – Lower Kalskag
Kuspuk School District Owned Buildings
Maintenance workers practice lighting
retrofits.
Earl Morgan packs up used fluorescent
lamps.
Jeromy Hoeldt works on a fixture at
Lower Kalskag Elementary school.
6 buildings owned by the School District received energy efficient lighting upgrades as follows:
Zackar Levi Elementary School and gymnasium (Lower School), School Generator Shed, KSD
Bunkhouse/library, KSD leased teacher housing (1 unit), KSD owned teacher housing (2 units).
• Lighting upgrades completed in January 2008, Lower School Gymnasium will be completed Summer
2009
• Installed 49 compact fluorescent light bulbs
• Retrofitted 146 light fixtures with electronic ballasts & T8 lamps
• Installed 16 T-5 linear fluorescent fixtures
• Pre-retrofit energy use for all lighting: 21.514 Kilowatts
• Post-retrofit energy use for all lighting: 11.802 Kilowatts
• Energy savings projection: 9.712 Kilowatts
• Pre-retrofit to post retrofit energy reduction: 45%
• Estimated Annual Savings:
Comparative Comparative
Hours Per Day / Electrical Avoided Diesel Avoided
250 Days Per Year Savings Use (gal) Diesel Costs
Locally Estimated $10,886.4 1234.40 $2,333.02
4 Hours/day $6,229.28 706.33 $1,334.96
7 Hours/day $10,901.2 1236.07 $2,336.18
10 Hours/day $15,573.1 1765.82 $3,337.40
7
Alaska Building Science Network – Village End Use Energy Efficiency Program – ’07-‘08 West Region – Lower Kalskag
Zackar Levi Elementary
T-8 strip fixtures replace inefficient High
Output T-12 fixtures saving approx
1000 watts in the school hallway.
25 watt T-8 lamps save energy while
improving over-all light levels in school
classrooms for a better learning
environment.
Materials Installed Quantity
2-lamp electronic ballast, (2) 25 watt T8 lamps 11 3-lamp electronic ballast, (2) 25 watt T8 lamps 5 4-Lamp Fixture (w/existing electronic ballast) re- 27 4-lamp fixture 3-lamp ballast (3) 25 watt T8 lamps 27 8 ft strip fixture, 4-lamp electronic ballast (4) 32 9
• Pre-retrofit energy use: 9927 watts
• Post-retrofit energy use: 5880 watts
• Energy savings projection: 4047 watts
• Pre-retrofit to post retrofit energy reduction: 40%
• Estimated annual savings: Comparative Comparative
Hours Per Day / Electrical Avoided Diesel Avoided Diesel
250 Days Per Year Savings Use (gal) Costs 2500 Hours/year (Est.) $6,489.36 735.82 $1,390.70
4 Hours/day $2,595.75 294.33 $556.28
7 Hours/day $4,542.56 515.07 $973.49
10 Hours/day $6,489.36 735.82 $1,390.70
Note: Some fixtures contained existing electronic ballast and 32 watt T -8 lamps installed previously. All
4-lamp fixtures (54 total) were de-lamped to three 25 watt T-8 lamps each.
8
Alaska Building Science Network – Village End Use Energy Efficiency Program – ’07-‘08 West Region – Lower Kalskag
School Generator shed
Materials Installed Quantity 2-lamp electronic ballast, (2) 25 watt T8 lamps 1 4-lamp electronic ballast, (4) 25 watt T8 lamps 1
CFL-14 W 7
• Pre-retrofit energy use: 672 watts
• Post-retrofit energy use: 235 watts
• Energy savings projection: 437 watts
• Pre-retrofit to post retrofit energy reduction: 65%
• Estimated annual savings: Comparative Comparative Hours Per Day / Electrical Avoided Diesel Avoided Diesel
250 Days Per Year Savings Use (gal) Costs
500 Hours/year (Est.) $140.15 15.89 $30.03
4 Hours/day $280.29 31.78 $60.07
7 Hours/day $490.51 55.62 $105.12
10 Hours/day $700.73 79.45 $150.17
KSD Bunkhouse/library
Materials Installed Quantity 2-lamp electronic ballast, (2) 25 watt T8 lamps 56 CFL-20 W 4 CFL-23 W 1 • Pre-retrofit energy use: 4432 watts
• Post-retrofit energy use: 2735 watts
• Energy savings projection: 1697 watts
• Pre-retrofit to post retrofit energy reduction: 38%
• Estimated annual savings: Comparative Comparative
Hours Per Day / Electrical Avoided Diesel Avoided Diesel
250 Days Per Year Savings Use (gal) Costs 500 Hours/year (Est.) $544.23 61.71 $116.63
4 Hours/day $1,088.46 123.42 $233.26
7 Hours/day $1,904.80 215.98 $408.21
10 Hours/day $2,721.14 308.55 $583.15
9
Alaska Building Science Network – Village End Use Energy Efficiency Program – ’07-‘08 West Region – Lower Kalskag
KSD leased teacher housing
Materials Installed Quantity
2-lamp electronic ballast, (2) 25 watt T8 lamps 1 CFL-14 W 4 CFL-20 W 8 CFL-27 W 3 • Pre-retrofit energy use: 1204 watts
• Post-retrofit energy use: 344 watts
• Energy savings projection: 860 watts
• Pre-retrofit to post retrofit energy reduction: 71%
• Estimated annual savings: Comparative Comparative
Hours Per Day / Electrical Avoided Diesel Avoided Diesel
250 Days Per Year Savings Use (gal) Costs
1500 Hours/year (Est.) $827.41 93.82 $177.32
4 Hours/day $551.60 62.55 $118.21
7 Hours/day $965.31 109.45 $206.87
10 Hours/day $1,379.01 156.36 $295.53
KSD owned teacher housing
Materials Installed Quantity 2-lamp electronic ballast, (2) 25 watt T8 lamps 6 CFL-14 W 8 CFL-23 W 3 • Pre-retrofit energy use: 1035 watts
• Post-retrofit energy use: 463 watts
• Energy savings projection: 572 watts
• Pre-retrofit to post retrofit energy reduction: 55%
• Estimated annual savings: Comparative Comparative
Hours Per Day / Electrical Avoided Diesel Avoided Diesel
250 Days Per Year Savings Use (gal) Costs 1500 Hours/year (Est.) $550.32 62.40 $117.94
4 Hours/day $366.88 41.60 $78.62
7 Hours/day $642.04 72.80 $137.59
10 Hours/day $917.20 104.00 $196.56
10
Alaska Building Science Network – Village End Use Energy Efficiency Program – ’07-‘08 West Region – Lower Kalskag
KSD owned teacher housing
Materials Installed Quantity
2-lamp electronic ballast, (2) 25 watt T8 lamps 1 4-lamp electronic ballast, (3) 25 watt T8 lamps 1 CFL-14 W 4 CFL-20 W 6 CFL-23 W 1 • Pre-retrofit energy use: 452 watts
• Post-retrofit energy use: 321 watts
• Energy savings projection: 131 watts
• Pre-retrofit to post retrofit energy reduction: 29%
• Estimated annual savings: Comparative Comparative
Hours Per Day / Electrical Avoided Diesel Avoided Diesel
250 Days Per Year Savings Use (gal) Costs
1500 Hours/year (Est.) $126.04 14.29 $27.01
4 Hours/day $84.02 9.53 $18.01
7 Hours/day $147.04 16.67 $31.51
10 Hours/day $210.06 23.82 $45.02
11
Alaska Building Science Network – Village End Use Energy Efficiency Program – ’07-‘08 West Region – Lower Kalskag
School Gym
Existing High Output magnetic ballast
and T-12 lamps are inefficient and
provide poor lighting.
T-5 energy efficient lighting replaces
high output fluorescent light fixtures in
school gymnasium.
T-5 fixtures save energy while
improving light levels in large spaces.
Materials Installed Quantity
T-5 fixture, electronic ballast, (2) 54 watt T-5 HO 16 • Pre-retrofit energy use: 3792 watts
• Post-retrofit energy use: 1824 watts
• Energy savings projection: 1968 watts
• Pre-retrofit to post retrofit energy reduction: 52%
• Estimated annual savings: Comparative Comparative
Hours Per Day / Electrical Avoided Diesel Avoided Diesel
250 Days Per Year Savings Use (gal) Costs
1750 Hours/year (Est.) $2,208.98 250.47 $473.39
4 Hours/day $1,262.28 143.13 $270.51
7 Hours/day $2,208.98 250.47 $473.39
10 Hours/day $3,155.69 357.82 $676.28
12
Alaska Building Science Network – Village End Use Energy Efficiency Program – ’07-‘08 West Region – Lower Kalskag
SchoolGymPre&Post
These retrofits will be completed Summer 2009
Lower
Kalskag
Elementary
School Gym
Length
(feet)
Width
(feet)
Ceiling
Height
(feet)
Type of
Existing
Fixture
# of
Existing
Fixtures
Existing
Fixture
Wattage
Total
Existing
Wattage
Existing
Foot-
candles
New
Foot-
Candles
# of
New
Fixtures
New
fixtures
New
Fixture
Wattage
Total
New
Wattage
44.833 33.833 22.5
HPS
150
watt
160 0 47
direct, 59 16
T-5
2
lamps
114 1824
sloping ceiling: 20' 5" low to 24'3" at
peak
HPS
250
watt
260 0 30
indirect
T-5
3
lamps
171 0
Existing watts per False Pass and Craig from
AK Lighting
8' T12
2-lamp
HO
16 237 3,792
T-5
6
lamps
342 0
Total Existing
Watts 3,792 Total New Watts 1824
6, 4-lamp fixtures is the same light output as 12, 2-lamp fixtures. (Which is an average of 47 foot candles at floor level). To simplify and achieve fixture - for fixture exchange we can go
with 16, 2-lamp fixtures, which is 32 lamps - the same as 8, 4-lamp fixtures which will give an average foot candle spread of
Percent Savings Pre to Post Retrofit: 51.90%
Savings & Payback Calculation for Gym: 1750 New watts / old watts
Assume 1750 hrs / year for 250 days/year of use neg 1 (New watts / Old watts x 100 - 100) / 100
Full cost of electricity: 0.6414 /kWh Cost of Elect is $0.6414/kWh as of 11/13/08. Request rates from AVEC
Watts of existing lighting: 3,792
New wattage for T5 fixtures: 1,824
Calculation: (Watts) x (hrs/year) / (1000w/kw) x (cost of electricity) = (cost / year)
Existing Cost: $4,256
Retrofitted Cost: $2,047
Annual Savings: $2,209
Est material & shipping cost of Gym retrofit: $3,057
Simple Payback: Materials cost / annual savings = 1.38 years (for retrofit to pay for itself in materials)
Lower Kalskag, In-Kind Contribution Tracking Record - ABSN Energy Efficiency Projects:
In-Kind Item Dates
Hours
Contri-
buted
Hourly
Wage
Value /
Amount Notes
Staff time for project contact,
introduction & review of intro
materials (Number of entities
x 1 hour each)
3.00 $ 15.00 $ 45.00 list number of entities
Staff time for Attending
teleconference (TC/IRA) 1.00 $ 15.00 $ 15.00
list # of staff & wages if possible
($15/hr is an average wage for
village entity staff).
Staff time for Attending
teleconference (City) 1.00 $ 15.00 $15.00 "
Staff time for Attending
teleconference (School) 1.00 $ 15.00 $ 15.00 "
Conservative village office
administrative percentage of total
project cost less ABSN Admin %.
Total project cost = $37,775/village
- (our admin percentage , (around
12%) Approx: $4,533) = $33,242 x
5.5% = $1,828 (this 5.5% village
admin cost estimate is spread
across all entities we work with for
the course of the grant for
completing all energy efficiency
measures. These are primarily for
cumulative, otherwise unaccounted
time expense for village- based
project support.
Feb,
'07
through
Dec '08
$ 1,828.00
Each time we call, email, or fax a village
entity, someone has to receive the
communication, review and/or forward the
information, follow-up on requests, etc.
Whether it is to set-up a teleconference,
verify maintenance staff participation in
lighting or boiler trainings, set-up in-kind
lodging and transportation, lighting
trainings, track a shipment, verify
completion of lighting in a given building,
ship lamps and ballasts out of the village,
request a labor reimbursement agreement,
or invoice etc, etc. Village expenses for
phone charges, copying and fax costs,
office supplies, etc are part of this amount.
Lodging for ABSN Field
Managers - 1st assessment
site visit
Dec
17-20
2007
$100
Lodging at KSD Lower School x 4
days and at Aniak vocational
school 1 day
Lodging for ABSN Field
Managers - 2nd site visit
Jan 21-
23
2008
$75 Lodging at KSD Lower School 3
days
School T8 lighting upgrades 125.00 $ 25.00 $ 3,125.00 Best guestimate on wage and
hours
Lower School T5s, etc . . 80.00 $ 25.00 $ 2,000.00
Install 16, T-5 fixtures in HS gym
(Best guestimate on wage and
hours)
KSD-labor support for T5 and
T8 lighting upgrades - Earl
Morgan, local KSD Maint staff
30.00
$20.00 $ 600.00 Various lighting retrofit support
KSD notes:
$(1,000.00)
KSD is providing all labor In-Kind for
their full time maintenance staff
however they invoiced us for
$1,000.00 (66.6 hrs) in Nov '08
financial reporting for their on-call
maint staff they had to hire specifically
for the projects.
TOTAL $ 6,818.00
15
Alaska Building Science Network – Village End Use Energy Efficiency Program – ’07-‘08 West Region – Lower Kalskag
Bethel Boiler Trainings at Yuut Elitnaurviat Learning Center, October 7-8 & 15-16, 2008
ABSN Master Boiler Technician Charlie Deer presents at Bethel area boiler
training -Yuut Elitnaurviat, the Learning Center Shop in Bethel, October, 2008.
Training on oil burner combustion
efficiency and maintenance.
The Native Village of Lower Kalskag maintenance staff Micky Nicolai traveled to Bethel October 7 and 8,
2008 to participate in this training. ABSN partnered with Association of Village Council Presidents
Housing Authority and YKHC’s Yuut Elitnaurviat Learning Center to provide ABSN’s 16 -hour boiler
training course to 4 rural maintenance staff from ’07-’08 villages covered under this VEUEEM grant.
Additionally 11 AVCP Housing maintenance staff from Bethel and surrounding western villages attended
this training. Charlie Deer’s training hours were covered by matching funds from ABSN. AEA VEUEEM
grant funds were used to cover training coordination, air fare, meals and lodging in Bethel for VEUEEM
grant village maintenance staff.
Components of a Bacharach Flu Gas
Analyzing Kit used in boiler efficiency
training and left with capable maint
staff for use in their villages.
Smoke-test kit for analyzing flu gases for
boiler efficiency
Schematic of outdoor
temperature sensing boiler
control
During this 16-hour course ABSN’s boiler specialist C harlie Deer instructed maintenance staff in the
fundamentals of boiler and fuel energy efficiency. Training topics covered: fuel, proper heating system
sizing, testing boiler efficiency with a flu gas analyzer kit, cleaning and tuning boilers for energy
efficiency, control options and proper control function, burner and nozzle components and function,
outdoor temperature boiler controls, programmable thermostats, etc.