HomeMy WebLinkAboutEkwok Village End Use Energy Efficiency Measures Program Final Report 2010 Village End Use Energy Efficiency Measures Program
AEA Grant # 2195225 Administered by Alaska Building Science Network
Ekwok Final Report
Community Summary
11 community buildings received energy efficiency upgrades as follows:
City Offices, City Shop, Gas Station, VPSO Building, ENL Tribal Office, EPA Building, Clinic, Boys & Girls Club,
Russian Church, William "Sonny" Nelson School Shop and Generator Building, School Storage & Furnace Rooms,
School Gym
Retrofits Completed: August 2009 – January 2010
ABSN Field Management by: Harry Morgan and Anna Hilbruner.
Trained 5 local maintenance staff who were employed by village entities to complete lighting retrofits
Village-Wide Lighting Retrofit Summary:
• Retrofitted 81 light fixtures with electronic ballasts & T8 lamps
• Installed 54 compact fluorescent light bulbs
• Installed 20 T5 linear fluorescent fixtures
• Pre-retrofit energy use for all lighting: 18.82 Kilowatts
• Post-retrofit energy use for all lighting: 8.35 Kilowatts
• Energy savings projection: 10.47 Kilowatts
• Pre-retrofit to post retrofit energy reduction: 56%
• Estimated Annual Savings:
kWh Rate (FY 2009 Ave): $0.50 Fuel Cost (FY 2009 Ave): $3.66
Comparative Comparative
Hours Per Day/ Electrical Avoided Diesel Avoided Diesel
250 Days Per Year Savings Use (gal) Costs
Locally Estimated Use $8,303 1,351 $4,945
4 Hours/day $5,236 852 $3,118
7 Hours/day $9,163 1,491 $5,457
10 Hours/day $13,090 2,130 $7,796
• Total project cost for all measures: $20,000 (Allocated according to number of lighting retrofits and tracked grant expense)
• Simple Payback (lighting measures only, using 7 hours/day lighting use run-time): 2.18 years
• Total village wide in-kind contribution for lighting projects: $5,813
2
Alaska Building Science Network – Village End Use Energy Efficiency Program – ’08-’10 Final Report NW/SW Region – Ekwok
City of Ekwok Owned Buildings
4 buildings owned by the City of Ekwok received energy efficient lighting upgrades as follows:
City Offices, City Shop, Gas Station, VPSO Building
• Lighting upgrades completed in: January 2010
• Retrofitted 22 light fixtures with electronic ballasts & T8 lamps
• Installed 36 compact fluorescent light bulbs
• Pre-retrofit energy use for all lighting: 6.288 Kilowatts
• Post-retrofit energy use for all lighting: 1.964 Kilowatts
• Energy savings projection: 4.324 Kilowatts
• Pre-retrofit to post retrofit energy reduction: 69%
• Estimated Annual Savings:
Comparative Comparative
Hours Per Day / Electrical Avoided Diesel Avoided
250 Days Per Year Savings Use (gal) Diesel Costs
Locally Estimated $3,198.73 520.54 $1,905.18
4 Hours/day $2,162.00 351.83 $1,287.70
7 Hours/day $3,783.50 615.70 $2,253.48
10 Hours/day $5,405.00 879.58 $3,219.25
“The lights are nice and bright, just the thing we need here for long winter nights and short days.”
~ Ernie Nelson City Administrator
3
Alaska Building Science Network – Village End Use Energy Efficiency Program – ’08-’10 Final Report NW/SW Region – Ekwok
City Offices
Materials Installed Quantity
2-lamp electronic ballast, (2) 25 watt T8 lamps 10 3-lamp electronic ballast, (3) 25 watt T8 lamps 4 4-lamp electronic ballast, (3) 25 watt T8 lamps 4
CFL-14 W 6 CFL-20 W 3 CFL-27 W 1 Outdoor 23w Flood 4 • Pre-retrofit energy use: 3972 watts
• Post-retrofit energy use: 1319 watts
• Energy savings projection: 2653 watts
• Pre-retrofit to post retrofit energy reduction: 67%
• Estimated annual savings: Comparative Comparative Hours Per Day / Electrical Avoided Diesel Avoided Diesel
250 Days Per Year Savings Use (gal) Costs
4 Hours/day $1,326.50 215.87 $790.07
7 Hours/day $2,321.38 377.77 $1,382.63
10 Hours/day $3,316.25 539.67 $1,975.18
1820 Hours/year (Est.) $2,414.23 392.88 $1,437.93
City Shop
Materials Installed Quantity Outdoor 23w Flood 9
• Pre-retrofit energy use: 900 watts
• Post-retrofit energy use: 207 watts
• Energy savings projection: 693 watts
• Pre-retrofit to post retrofit energy reduction: 77%
• Estimated annual savings: Comparative Comparative Hours Per Day / Electrical Avoided Diesel Avoided Diesel
250 Days Per Year Savings Use (gal) Costs
4 Hours/day $346.50 56.39 $206.38
7 Hours/day $606.38 98.68 $361.16
10 Hours/day $866.25 140.97 $515.94
1000 Hours/year (Est.) $346.50 56.39 $206.38
4
Alaska Building Science Network – Village End Use Energy Efficiency Program – ’08-’10 Final Report NW/SW Region – Ekwok
Gas Station
Materials Installed Quantity CFL-23 W 5 Outdoor 23w Flood 1 • Pre-retrofit energy use: 600 watts
• Post-retrofit energy use: 138 watts
• Energy savings projection: 462 watts
• Pre-retrofit to post retrofit energy reduction: 77%
• Estimated annual savings: Comparative Comparative Hours Per Day / Electrical Avoided Diesel Avoided Diesel
250 Days Per Year Savings Use (gal) Costs
4 Hours/day $231.00 37.59 $137.59
7 Hours/day $404.25 65.79 $240.77
10 Hours/day $577.50 93.98 $343.96
500 Hours/year (Est.) $115.50 18.80 $68.79
VPSO Building
Materials Installed Quantity 2-lamp electronic ballast, (2) 25 watt T8 lamps 4 CFL-14 W 4 CFL-20 W 3
• Pre-retrofit energy use: 816 watts
• Post-retrofit energy use: 300 watts
• Energy savings projection: 516 watts
• Pre-retrofit to post retrofit energy reduction: 63%
• Estimated annual savings: Comparative Comparative
Hours Per Day / Electrical Avoided Diesel Avoided Diesel
250 Days Per Year Savings Use (gal) Costs
4 Hours/day $258.00 41.99 $153.67
7 Hours/day $451.50 73.47 $268.92
10 Hours/day $645.00 104.96 $384.17
1250 Hours/year (Est.) $322.50 52.48 $192.08
5
Alaska Building Science Network – Village End Use Energy Efficiency Program – ’08-’10 Final Report NW/SW Region – Ekwok
Ekwok Village Council Owned Buildings
4 buildings owned by the Ekwok Village Council received energy efficient lighting upgrades as follows:
ENL Tribal Office, EPA Building, Clinic, Boys & Girls Club
• Lighting upgrades completed in January 2010
• Retrofitted 37 light fixtures with electronic ballasts & T8 lamps
• Installed 16 compact fluorescent light bulbs
• Pre-retrofit energy use for all lighting: 5.951 Kilowatts
• Post-retrofit energy use for all lighting: 2.605 Kilowatts
• Energy savings projection: 3.346 Kilowatts
• Pre-retrofit to post retrofit energy reduction: 56%
• Estimated Annual Savings:
Comparative Comparative
Hours Per Day / Electrical Avoided Diesel Avoided
250 Days Per Year Savings Use (gal) Diesel Costs
Locally Estimated $3,178.38 517.23 $1,893.06
4 Hours/day $1,673.00 272.25 $996.45
7 Hours/day $2,927.75 476.44 $1,743.79
10 Hours/day $4,182.50 680.63 $2,491.12
6
Alaska Building Science Network – Village End Use Energy Efficiency Program – ’08-’10 Final Report NW/SW Region – Ekwok
ENL Tribal Office Building
Materials Installed Quantity 2-lamp electronic ballast, (2) 25 watt T8 lamps 12 CFL-20 W 2 CFL-23 W 2 • Pre-retrofit energy use: 1358 watts
• Post-retrofit energy use: 638 watts
• Energy savings projection: 720 watts
• Pre-retrofit to post retrofit energy reduction: 53%
• Estimated annual savings: Comparative Comparative Hours Per Day / Electrical Avoided Diesel Avoided Diesel
250 Days Per Year Savings Use (gal) Costs
4 Hours/day $360.00 58.58 $214.42
7 Hours/day $630.00 102.52 $375.23
10 Hours/day $900.00 146.46 $536.05
2000 Hours/year (Est.) $720.00 117.17 $428.84
EPA Building
Materials Installed Quantity 2-lamp electronic ballast, (2) 25 watt T8 lamps 2 3-lamp electronic ballast, (3) 25 watt T8 lamps 4 4-lamp electronic ballast, (3) 25 watt T8 lamps 3 CFL-20 W 2 Outdoor 23w Flood 2
• Pre-retrofit energy use: 1784 watts
• Post-retrofit energy use: 699 watts
• Energy savings projection: 1085 watts
• Pre-retrofit to post retrofit energy reduction: 61%
• Estimated annual savings: Comparative Comparative
Hours Per Day / Electrical Avoided Diesel Avoided Diesel
250 Days Per Year Savings Use (gal) Costs
4 Hours/day $542.50 88.28 $323.12
7 Hours/day $949.38 154.50 $565.45
10 Hours/day $1,356.25 220.71 $807.79
2000 Hours/year (Est.) $1,085.00 176.57 $646.23
7
Alaska Building Science Network – Village End Use Energy Efficiency Program – ’08-’10 Final Report NW/SW Region – Ekwok
Clinic
Materials Installed Quantity 2-lamp electronic ballast, (2) 25 watt T8 lamps 1 4-lamp electronic ballast, (3) 25 watt T8 lamps 6 De-lamping from 4 to 3 lamps/fixture saved additional watts. 4-lamp electronic ballast, (4) 25 watt T8 lamps 4 CFL-20 W 2 CFL-23 W 5 • Pre-retrofit energy use: 2289 watts
• Post-retrofit energy use: 1011 watts
• Energy savings projection: 1278 watts
• Pre-retrofit to post retrofit energy reduction: 56%
• Estimated annual savings: Comparative Comparative Hours Per Day / Electrical Avoided Diesel Avoided Diesel
250 Days Per Year Savings Use (gal) Costs
4 Hours/day $639.00 103.99 $380.59
7 Hours/day $1,118.25 181.98 $666.04
10 Hours/day $1,597.50 259.97 $951.48
1820 Hours/year (Est.) $1,162.98 189.26 $692.68
Boys & Girls Club
Materials Installed Quantity 2-lamp electronic ballast, (2) 25 watt T8 lamps 5 CFL-27 W 1 • Pre-retrofit energy use: 520 watts
• Post-retrofit energy use: 257 watts
• Energy savings projection: 263 watts
• Pre-retrofit to post retrofit energy reduction: 51%
• Estimated annual savings: Comparative Comparative Hours Per Day / Electrical Avoided Diesel Avoided Diesel
250 Days Per Year Savings Use (gal) Costs
4 Hours/day $131.50 21.40 $78.32
7 Hours/day $230.13 37.45 $137.06
10 Hours/day $328.75 53.50 $195.81
1600 Hours/year (Est.) $210.40 34.24 $125.32
8
Alaska Building Science Network – Village End Use Energy Efficiency Program – ’08-’10 Final Report NW/SW Region – Ekwok
Russian Orthodox Church Owned Buildings
1 building owned by the community supported Russian Orthodox Church received energy efficient lighting
upgrades as follows:
Russian Orthodox Church
Materials Installed Quantity CFL-27 W 2
• Lighting upgrades completed in January 2010
• Installed 2 compact fluorescent light bulbs
• Pre-retrofit energy use for all lighting: 0.2 Kilowatts
• Post-retrofit energy use for all lighting: 0.054 Kilowatts
• Energy savings projection: 0.146 Kilowatts
• Pre-retrofit to post retrofit energy reduction: 73%
• Estimated Annual Savings:
Comparative Comparative
Hours Per Day / Electrical Avoided Diesel Avoided
250 Days Per Year Savings Use (gal) Diesel Costs
4 Hours/day $73.00 11.88 $43.48
7 Hours/day $127.75 20.79 $76.09
10 Hours/day $182.50 29.70 $108.70
900 Hours/year (Est.) $65.70 10.69 $39.13
9
Alaska Building Science Network – Village End Use Energy Efficiency Program – ’08-’10 Final Report NW/SW Region – Ekwok
Southwest Region School District Owned Buildings
3 buildings owned by the Southwest Region School District received energy efficient lighting upgrades as follows
William "Sonny" Nelson School:
School Shop, School Storage & Back, School Gym
• Lighting upgrades completed in January 2010
• Retrofitted 22 light fixtures with electronic ballasts & T8 lamps
• Installed 20 T5 linear fluorescent fixtures
• Pre-retrofit energy use for all lighting: 6.388 Kilowatts
• Post-retrofit energy use for all lighting: 3.732 Kilowatts
• Energy savings projection: 2.656 Kilowatts
• Pre-retrofit to post retrofit energy reduction: 42%
• Estimated Annual Savings:
Comparative Comparative
Hours Per Day / Electrical Avoided Diesel Avoided
250 Days Per Year Savings Use (gal) Diesel Costs
Locally Estimated $1,860.50 302.77 $1,108.13
4 Hours/day $1,328.00 216.11 $790.97
7 Hours/day $2,324.00 378.19 $1,384.19
10 Hours/day $3,320.00 540.28 $1,977.41
In-kind Labor: Southwest Region School District generously provided all maintenance staff labor in -kind to the
grant to complete school facility, teacher housing and Gym T5 lighting retrofits - resulting in substantial direct cost
savings to the grant.
10
Alaska Building Science Network – Village End Use Energy Efficiency Program – ’08-’10 Final Report NW/SW Region – Ekwok
School Shop
Materials Installed Quantity 2-lamp electronic ballast, (2) 25 watt T8 lamps 3 4-lamp electronic ballast, (4) 25 watt T8 lamps 10
• Pre-retrofit energy use: 1932 watts
• Post-retrofit energy use: 1038 watts
• Energy savings projection: 894 watts
• Pre-retrofit to post retrofit energy reduction: 46%
• Estimated annual savings: Comparative Comparative Hours Per Day / Electrical Avoided Diesel Avoided Diesel
250 Days Per Year Savings Use (gal) Costs
4 Hours/day $447.00 72.74 $266.24
7 Hours/day $782.25 127.30 $465.91
10 Hours/day $1,117.50 181.86 $665.59
1000 Hours/year (Est.) $447.00 72.74 $266.24
School Storage & Back Room
Materials Installed Quantity 2-lamp electronic ballast, (2) 25 watt T8 lamps 9
• Pre-retrofit energy use: 756 watts
• Post-retrofit energy use: 414 watts
• Energy savings projection: 342 watts
• Pre-retrofit to post retrofit energy reduction: 45%
• Estimated annual savings: Comparative Comparative
Hours Per Day / Electrical Avoided Diesel Avoided Diesel
250 Days Per Year Savings Use (gal) Costs
4 Hours/day $171.00 27.83 $101.85
7 Hours/day $299.25 48.70 $178.24
10 Hours/day $427.50 69.57 $254.62
1000 Hours/year (Est.) $171.00 27.83 $101.85
11
Alaska Building Science Network – Village End Use Energy Efficiency Program – ’08-’10 Final Report NW/SW Region – Ekwok
School Gym
Yellow / green HID lighting – pre-retrofit,
low color rendering index (CRI) of 60 - 70
New T5 HIF fixtures
high color rendering index (CRI) of 85
“I was able to get up to Ekwok the other day... what a difference the new T-5 lighting makes! We are
getting at least twice the light levels as we used to. The difference in light quality and atmosphere for the
kids is worth as much as the cost savings to me. Without your help I don't know when we would have
had the funding to do that re-lamp.”
- 9-16-09 Comments from a phone call with Kim Endicott, Director of Maintenance, Southwest Region School District
Materials Installed Quantity T5 fixture, electronic ballast, (2) 54 watt T5 HO 20
• Pre-retrofit energy use: 3700 watts
• Post-retrofit energy use: 2280 watts
• Energy savings projection: 1420 watts
• Pre-retrofit to post retrofit energy reduction: 38%
• Estimated annual savings: Comparative Comparative Hours Per Day / Electrical Avoided Diesel Avoided Diesel
250 Days Per Year Savings Use (gal) Costs
4 Hours/day $710.00 115.54 $422.88
7 Hours/day $1,242.50 202.20 $740.04
10 Hours/day $1,775.00 288.85 $1,057.20
1750 Hours/year (Est.) $1,242.50 202.20 $740.04
ABSN T5 Lighting plans are designed to increase the average light levels throughout the area when all
fixtures are switched on - in comparison with former existing light output. Existing switching controls are
normally retained - allowing users to choose the appropriate number of light fixtures / rows of light
fixtures needed for various use patterns. In many cases school staff will choose not to use all fixtures
available, thereby achieving more electrical savings than is shown above. Considering light quality,
ABSN T5 lighting plans employ 54-watt, high output T5 lamps with a color-rendering index (CRI) of 85.
Existing light fixtures in rural high ceiling areas typically have a CRI ranging from 30 to 70. With the T5
retrofits, the boost in CRI greatly improves light quality – resulting in objects appearing much closer to
their true color as seen under sunlight. This increased light quality can result in less light needed to
illuminate a given space - for example fewer rows of fixtures selected to light the space.
12
Alaska Building Science Network – Village End Use Energy Efficiency Program – ’08-’10 Final Report NW/SW Region – Ekwok
Ekwok - Alaska Building Science Network - T5 Lighting Upgrade Details
These retrofits were completed in (August, 2009).
Ekwok
School
Gym
Length
(feet)
Width
(feet)
Ceiling
Height
(feet)
Type of
Existing
Fixture
# of
Existing
Fixtures
Existing
Fixture
Wattage
Total
Existing
Wattage
Existing
Foot-
candles
New
Foot-
Candles
# of
New
Fixtures
New
fixtures
New
Fixture
Wattage
Total
New
Wattage
70 50 20'4"
HPS
150
watt
160 0 13-16 35 - 37 20
T-5
2
lamps
114 2280
Color shade
of walls
HPS
250
watt
260 0
T-5
3
lamps
171 0
Multi-
Vapor
175
watt
20 185 3,700
T-5
6
lamps
342 0
Total Existing Watts 3,700 Total New Watts 2280
Percent Savings Pre to Post Retrofit: 38.38%
Savings & Payback Calculation for Gym: 1750 New watts / old watts
Assume 1750 hrs / year for 250 days/year of use
Full cost of electricity: $ 0.50 /kWh
Watts of existing lighting: 3,700
New wattage for T5 fixtures: 2,280
Calculation: (Watts) x (hrs/year) / (1000w/kw) x (cost of electricity) = (cost / year)
Existing
Cost: $ 3,238
Retrofitted Cost: $ 1,995 T5 Materials costs $ 3,454.00
Annual Savings: $ $ 1,243 T5 shipping costs $ 198.58
Material & shipping cost of Gym retrofit: $3,652.58
Simple Payback: Materials cost / annual savings = 2.94 years (for retrofit to pay for itself in materials)
13
Alaska Building Science Network – Village End Use Energy Efficiency Program – ’08-’10 Final Report NW/SW Region – Ekwok
Ekwok, In-Kind Contribution Tracking Record - ABSN Energy Efficiency Projects:
In-Kind Item Dates
Hours
Contri-
buted
Hourly
Wage
Value /
Amount Notes
Staff time for project contact,
introduction & review of intro
materials
3 $ 20.00 $ 60.00 Number of entities x 1 hour
each
Staff time for Attending
teleconference 2 $ 20.00 $ 40.00 TC/IRA
Staff time for Attending
teleconference 2 $ 20.00 $ 40.00 City
Staff time for Attending
teleconference 1 $ 20.00 $ 20.00 School
Maint. Staff time to accompany
Field Manager on building
assessments
8 $ 15.00 $ 120.00 1st site visit - city
Conservative village office
administrative percentage of
total project cost less ABSN
Admin %. Total project cost
= $20,000/village - (our admin
percentage, (around 12%)
Approx: $2,400) = $17,600 x
5.5% = $968 (this 5.5% village
admin cost estimate is spread
across all entities we work with
for the course of the grant for
completing all energy efficiency
measures. These are primarily
for cumulative, otherwise
unaccounted time expense for
village- based project support.
Feb, '07
through $968
Each time we call, email, or fax
a village entity, someone has to
receive the communication,
review and/or forward the
information, follow-up on
requests, etc. Whether it is to
set-up a teleconference, verify
maintenance staff participation
in lighting or boiler trainings,
set-up in-kind lodging and
transportation, lighting trainings,
track a shipment, verify
completion of lighting in a given
building, ship lamps and
ballasts out of the village,
request a labor reimbursement
agreement, or invoice etc.
Village expenses for phone
charges, copying and fax costs,
office supplies, etc. are part of
this amount.
Lodging for ABSN Field
Managers 6 $ 75.00 $ 450.00 1st & 2nd site visits - city
School Labor for T8 Upgrades 20 $ 20.00 $ 400.00 Estimated Maint Labor for
T8s
School Labor for T5 Gym
Upgrades $ 3,700.00
Conservative estimate for total labor
contributed including travel and
fringe costs.
Tribe backhaul/Photos Labor 1 $ 15.00 $ 15.00
TOTAL $5,813.00
The capacity of ABSN’s scope of work was greatly increased by the response of local communities to work in
partnership with ABSN and provide in-kind services of project coordination, paid labor for lighting retrofits,
transportation and lodging for ABSN field staff, and other valuable contributions. This allowed ABSN and the
community of Ekwok to deliver 29% more energy savings measures beyond the original grant funding.